Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
RPU WATER SUPPLY PLAN
Phase I Funding
October 21, 2011
Develop a safe, reliable, local,
sustainable, and cost effective water
supply to maintain Riverside’s water
independence for the next 100 years.
(Excerpt): Increase local water supply through:
Increased use of recycled water
• Direct delivery to offset potable demand
• Groundwater recharge
Overview of Water Supply Planning
0
25,000
50,000
75,000
100,000
125,000
Dem
an
d (
AF
Y)
Year
Shortage /
Need
Developed
Resources
Estimated imported water
cost to meet demand:
Riverside Water Demand
Cost of Water to meet demand: $1,300 - $2,500 AF
Future Recycled Water Operations
52,400 AFY Plant Operation
(7,100) AFY In-Plant Use
(25,000) AFY Required flow to Santa Ana River
20,300 AFY Available for Recycling
Discharge to SAR – 48% In-plant use –
13%
Recycled Water Future – 30%
Recycled Water Phase 1 – 9%
Consultant Study for Recycled System
Estimated Capital Cost:
Pipelines $ 319,000,000
Reservoirs $ 31,000,000
Pump Stations $ 23,000,000
Advanced Treatment $ 165,000,000
Recharge Basins $ 8,000,000
Total Estimated Cost: $ 546,000,000 - $42/customer/month
Approximately $2,200/AF
Staff believed lower cost alternative was available!
RPU Alternative Recycled Water System
Two Project Recycled Water Alternative
Phase 1: Arlington-Central Recycled Water Pipeline
Phase 2: Santa Ana River Pipeline to Pellissier Ranch
Total Project Cost: $155 million - $9/customer/month
Approximately $425 AF
Water Supply Increase: 25,000 AFY
• 5,000 AFY Groundwater Recharge (Recycled)
• 15,000 AFY Groundwater Recharge (Storm water)
• 2,300 AFY Direct Use (Recycled)
• 2,600 AFY Wholesale/Exchange (Recycled)
RPU Alternative Recycled Water System
Recommendation
Phase 1: Arlington-Central Recycled Water Pipeline - Now
Phase 2: Santa Ana River Pipeline to Pellissier Ranch - Future
Phase 1 Project Cost: $39 million
$4 million cost
Total Water Supply Increase: 8,600 AFY
• 5,000 AFY Groundwater Recharge
• 1,000 AFY Direct Use (Recycled)
• 2,600 AFY Wholesale/Exchange (Recycled)
• Enough water for 17,000 households
Arlington - Central Pipeline
Project Elements – Distribution System:
6 miles of transmission and distribution pipelines
• Arlington Av. from Van Buren Blvd. to Riverside Av.
Interconnection to Riverside Canal downstream of Gage Canal tie
• Interconnection for wholesale service to WMWD
Connection to existing Central Av. purple pipe
Project Elements – Water Quality Control Plant:
Dedicated service pipeline
New storage reservoir and pump station
Metering and control facilities
Project Elements – Groundwater Recharge
Groundwater recharge basins for Arlington Basin
• Potential joint project with WMWD
• Use existing Riverside Canal & WMWD pump
station/pipelines
Connection to Mockingbird Lake dam outlet
• Provide for storm water capture
• Diluent water for regulatory requirements
• Creates dual use recharge basins
Arlington - Central Pipeline
Potential for Recycled Water Service to:
Adams Elementary School
Shamel Park
Don Jones Park
Ramona High School
Jefferson Elementary School
Low Park
Pachappa Elementary School
Olivewood Memorial Park
Poly High School
Alcott Elementary School
Parkways and Medians
Arlington - Central Pipeline
Implementation Timeline – Phase 1
Phase 1 Project – Arlington Central Pipeline
Projected in Service Fall 2014
• Construction Start Winter 2012 / Spring 2013
Groundwater Recharge permitting by project
partner(s)
Concept Approval
and CEQA
Engineering Construction
2011 2012 2013 2014
Recycled Water Rate Plan
Structure as fixed charge
Similar to Electric reliability charge
$4/month - Typical Residential and Commercial Customer
$2.00 / month effective March 2012
+$2.00 / month effective March 2013
95% of customers at this rate
Towards Riverside Water Independence for 100 years!
Recommendation
That the Board of Public
Utilities endorse moving
forward with the process
to implement Phase 1 of
the Recycled Water Plan