Upload
randolf-griffin
View
218
Download
0
Embed Size (px)
Citation preview
A business of
Transmission Services Agreement
2
Agenda
Why have a Transmission Services Agreement (“TSA”)?
Where does the TSA fit within TWBP commercial arrangements?
Content of TSA
Next steps
3
Why have a Transmission Services Agreement?
KEPCO owns the electricity transmission assets…
… and KPX, as system operator, operates these assets…
… so some form of arrangement between KEPCO and KPX is needed “… to establish the contractual and operational framework under which
KEPCO provides transmission assets to KPX.”
4
Why have a Transmission Services Agreement (2)?
We believe that the current MOCIE notification which requires KEPCO to provide transmission assets to KPX will not be sufficient going forward – for example, the current notification does not address roles and responsibilities for transmission system planning detailed provision of information and access to systems (e.g. SCADA,
analysis datasets, rating information) inspection of assets rights / obligations for testing of new infrastructure rights / obligations in force majeure situations performance and operating standards (other than for protection assets) general terms (e.g. modifications, disputes, confidentiality etc.)
It does not provide for any incentive mechanism for asset availability The contents of the draft Korean TSA and concepts used are consistent with
international practice - in particular, we have drawn on the Australian and Brazilian TSAs and on wider international experience on incentive regimes
5
Where does the TSA fit? (1)
The TWBP commercial arrangements are intended to conform to the best practice document structure for a liberalised electricity market…
Legislative framework
Regulatory documents
Technical codesMarket agreements
6
• Provision of assets to SO
• Maintenance / inspection rights
• Physical operation of network
• Co-ordination of network expansion
• Availability incentives
Where does the TSA fit? (2)
Each agreement deals with a consistent set of commercial and technical issues – e.g. the technical details of information to be provided by KEPCO to KPX on transmission assets is set out in the TSA under which KEPCO agree to provide the assets
G PSB D
Market Code• Multilateral governance
• MOCIE approval
• Market Governance• Pool Rules• System operation and
security• Revenue and
operational metering• Settlement rules• Retail market
operations
TSA• Bilateral governance
• MOCIE approval
T SO
Grid Code• MOCIE approval
• Connection• Network planning and
expansion• Network pricing
T SO G PSB T D
There are three key documents in the market agreements and technical codes category…
Proposed changes to any of the documents must be reviewed to check for inconsistencies, and must be approved by MOCIE
SO
7
Where does the TSA fit? (3)
The TSA is therefore a key part of the overall commercial arrangements for the TWBP environment it provides the contractual framework for the provision of transmission assets
to the system operator its effective operation influences the overall efficiency of the operation of the
market
As such, in common with the market code and grid code KEC / MOCIE have a valid interest in the terms of the TSA, particularly in
relation to the promotion of overall efficiency compliance with the terms of the TSA should be a legal requirement set
down by KEC / MOCIE modifications to the TSA going forward should be approved by KEC /
MOCIE
8
Content and purpose
The Transmission Services Agreement:
Lists the assets to be operated by KPX
Sets out rights and obligations for maintenance and inspection
Sets out rights and obligations for physical asset operation
Defines rights and obligations for network planning and new connections
Sets out governance procedures
Provides an incentive regime for asset availability
The current draft of the TSA represents drafting instructions to lawyers – it is not the final version of the agreement
9
Provision of relevant assets
KEPCO agrees to provide all “relevant assets” for commercial use and operational control by KPX, on an exclusive basis, subject to the terms of the TSA
The “relevant assets” are all transmission assets owned or maintained by KEPCO save those listed in Schedule 1 of the TSA
The relevant assets may be changed according to the procedure set out in the TSA when new transmission assets are commissioned the capability of assets changes assets are retired
10
Maintenance obligations and inspection rights
KEPCO is required to maintain its relevant assets (and associated equipment) in accordance with
the technical requirements of the Market Code ensure all personnel are appropriately accredited
KPX may inspect the KEPCO facilities according to the procedures set out in the TSA to verify compliance
11
Physical operation of assets
KEPCO must ensure that KPX always has access to information and systems necessary for physical operation, including SCADA data analysis datasets technical asset information (set out in Schedule 3)
KEPCO is required to comply with switching instructions (incl. for reactive plant) from KPX in accordance with the Market Code
KPX is required to set out standards / principles for protection system configuration; for its own protection equipment, KEPCO is required to implement these standards
KPX, with KEPCO, must develop a black start plan, and comply with the Market Code in the event of a total or partial shutdown
12
Network expansion planningThe process of network expansion planning in the TSA is divided into indicative planning and detailed planning
Indicative network planning
Forecasting possible G & L growth over next 10 years
Analysis of existing and future transfer capabilities
Statement of high level requirements for transmission augmentation
Other operational and economic information of use to prospective market participants
Detailed network planning
Development of detailed requirements for transmission augmentation
Analysis of technical options for augmentation
Full specification of detail of optimal augmentation option
Scheduling of augmentation projects across system
This separation is consistent with international practice – e.g. the processes followed by NEMMCO in Australia and NGC in the UK
13
Network expansion planning (2)
KPX is required to ensure that, for long term planning purposes, KEPCO has access to system
models and information used for operational planning provide an indicative expansion plan to KEPCO
KEPCO is required to provide justification where it has not taken into account information provided by KPX in its detailed expansion plan
KPX and KEPCO are required to publish their respective plans
14
New connections
KEPCO is required to provide information to KPX on proposed new connections, and provide
justification where it has not taken into account comments by KPX keep KPX informed of changes to existing connection details
KPX must agree KEPCO proposals for testing of new assets prior to their connection to the relevant assets programme of testing confirmation that assets meet performance / operating requirements confirmation of detail of safety measures
15
Governance and general terms
KEC shall arbitrate between KPX and KEPCO in any disputes under the TSA (assuming the dispute resolution procedures in the Market Code do not apply)
The TSA can only be modified following a proposal from KEPCO or KPX, and proposed modifications must be approved by MOCIE
The TSA contains force majeure and confidentiality conditions
16
Incentive regime on asset availability
The regime is intended to ensure that the assets are provided in a way which is consistent with overall economic efficiency in the market provide incentives to ensure assets are available and well maintained provide incentives to commit to (and implement) timely outages ensure that some portion of the cost to the market of amending generation /
load schedules to manage transmission constraints resulting from transmission outages is borne by KEPCO
The incentive regime in the TSA mirrors international practice UK: distribution companies Brazil: Transmission Concessionaires
17
UK: Distribution incentive scheme
Ofgem (UK regulator) recently introduced an incentive scheme for distributors to penalise those companies which fail to meet targets for number of interruptions length of interruptions quality of telephone response to customers
The scheme will initially run for 3 years (from April 2002)
Discos can be penalised by up to 2% of their annual regulated revenue (c. £4m per company per annum) for failure to meet targets
They can earn additional revenue in the final year if they exceed targets
18
Brazil: ISO – Transmission owner scheme
The TSA between ONS (the Brazilian ISO) and the Transmission Concessionaire contains an incentive scheme for asset availability
ONS pays the TC 1/12 of its annual allowed revenue per month - the allowed revenue for transmission assets includes: Direct and indirect costs of transmission network services Availability of equipment to compensate reactive power Ancillary services
The payment from ONS is reduced by a factor based on the duration of planned and unplanned outages
The per minute reduction in payments for unplanned outages is higher than that for planned planned outages: R$ 10/minute unplanned outages: R$ 150/minute for first 300 minutes, R$ 10/minute
thereafter
19
Brazil: ISO – Transmission owner scheme (2)
No reduction is made for outages which are less than one minute in duration result from network improvements are requested by ONS or third parties for operational or safety reasons are caused unintentionally by ONS result from force majeure
The reduction in payments will be capped as follows for each year, the reduction will be no more than 25% of allowed revenue for each month, the reduction will be no more than 50% of the monthly
allowed revenue, with the remainder being carried over to the following month (subject to the yearly maximum)
The reduction rates per minute do note vary by time or asset class In the first 6 months of operation, ONS calculates the reduction in
payments, but it is not applied
20
Detail of incentive regime in draft Korean TSA
The TSA defines a concept of “permitted outages” notified to KPX at least 4 weeks prior to commencement end on time
For each year, and for each class of asset, there is a maximum duration and frequency of permitted outages
Outages not notified more than 4 weeks in advance do not count against this maximum duration / frequency but do count as non-permitted
For all non-permitted outages, KEPCO is required to pay KPX a sum defined by a schedule to the agreement (to be defined)
21
Incentive regime – worked example
Suppose for asset class j that the permitted off-peak outage duration was 10 hours and the permitted off-peak outage frequency was 5
Asset class J Cumulative duration
for threshold purposes
Cumulative frequency
for threshold purposes
Penalty incurred
?
Outage of 2 hours notified on time 2 1 No
Outage of 1 hour notified on time 3 2 No
Outage of 2 hours not notified on time
3 2 2 x value
Outage of 10 hours notified on time
13 3 3 x value
Outage of 5 hours notified on time 18 4 5 x value
22
Incentive regime options
it could be “turned off” for the early period (e.g. first year?) of market operation, particularly if the regulatory regime for transmission is not well developed at that stage
the specification of the outage thresholds and the penalty values could be more or less detailed (e.g. by class of asset, by time period etc.)
some types of outages could be taken out of the regime (e.g. outages caused by KPX or resulting from force majeure)
the regime could be “two sided” – it could offer KEPCO an upside if they take fewer outages than planned penalties if they take more outages than planned
There are a number of possible options around the incentive scheme as currently specified – for example
23
Next steps
The current draft of the TSA has been developed by KPX / PwC represents drafting instructions to lawyers
To reach a finalised and enforceable agreement the agreement will need to be reviewed by KPX, KEPCO and KEC / MOCIE,
and possible refined so that each are comfortable with its content the drafting needs to be legally reviewed KEC / MOCIE need to ensure that the legal market framework requires
compliance with the TSA
A business of
PwC ConsultingTM
refers to the management consulting services businesses of the member firms of the worldwide PricewaterhouseCoopers organisation.
2001 PricewaterhouseCoopers. All rights reserved.