Route Evaluation Study Allegany Wind Power Project Town of Allegany, NY CME Project No. 08-132d Prepared for: Allegany Wind LLC 44 East 30 th Street, 10 th floor New York, NY 10011 Prepared by: 17 Computer Drive West Albany, New York 12205-1683 (518) 446-0396 January 12, 2010 (Revised February 10, 2010)

Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Route Evaluation Study

Allegany Wind Power Project

Town of Allegany, NY

CME Project No. 08-132d

Prepared for:

Allegany Wind LLC

44 East 30th Street, 10th floor New York, NY 10011

Prepared by:

17 Computer Drive West

Albany, New York 12205-1683 (518) 446-0396

January 12, 2010

(Revised February 10, 2010)

Page 2: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 1

1. Introduction, Purpose and Proposed Project: Allegany Wind LLC is proposing to construct a wind-powered, electric generating project in the Town of Allegany (Cattaraugus County, New York) to begin in 2011. The project will include approximately 29 wind towers, a system of gravel access roads, a buried electrical collection system, substation, a 6,000 square-foot (SF) Operation and Maintenance (O&M) building, and a temporary 5 acre construction staging area located on Chipmunk Road. The wind turbines will generate approximately 2.5 megawatts (MW) of power each, equating to a maximum capacity of approximately 72.5 MW. Access to the proposed tower sites is located off of Nichols Run Road and Chipmunk Run Road. Approximately 8.2 miles of gravel access roads will be constructed to access the sites. Access to the O&M building will be provided off of Chipmunk Road while access to the substation will be provided off of Camelback Lane or Riverside Drive. Refer to Figures 1 and 2 for the regional location map and proposed tower locations. During construction there will be temporary increases in truck traffic on area roadways served by the project. The purpose of this evaluation is to document the existing transportation conditions in the area and identify probable local travel routes, constraints, and proposed improvements. It is noted that this evaluation does not identify a specific regional routing plan for the wind farm site and that the future transportation provider for the project should document potential regional constraints such as bridge restrictions as the project is progressed. However, it is assumed that the wind tower components will be shipped to the local transportation network via Interstate 86 (NY Route 17). It is recommended that the transportation provider determine if some of the heavier wind farm components such as the transformer can be regionally shipped to the site via the existing railroad line that runs through Olean located to the north of the project site. 2. Methodology A field inventory, photo log, and visual assessment was conducted to evaluate possible travel routes. Sample roadway characteristics and conditions were documented. Representatives were contacted including the Cattaraugus County Civil Engineer and the Town of Allegany Highway Superintendent to understand jurisdictional concerns and permit requirements. Research was conducted on wind turbine transportation requirements, and a potential worst-case design vehicle was evaluated to identify possible intersection improvements. 3. Vehicle Types The number, size and type of trucks depend on the specific project and the equipment being hauled. Turbine components and associated truck trips can generally be classified as follows: Wind Turbine Equipment

• Blade Sections – Blades are transported on trailers with one to three blades per vehicle. Blades typically control the length of the design vehicle, and the radius of the curves along the travel route to the site. Specialized transport vehicles are designed with articulating (manual or self steering) rear axles to allow maneuverability through curves.

• Tower Sections – Typically transported in three to four sections depending on the supplier. Towers generally can control the height and width of the design vehicle dimensions.

• Nacelle – The turbine and related elements are typically the heaviest component transported.

• Hub and Nose Cone – Typically transported with one or more of the same element on a vehicle. These elements are not critical elements related to design vehicle dimensions.

• Escort Vehicles

Page 3: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 2

Construction Equipment and Materials

• Construction of Site Roads – Conventional trucks carrying stone, gravel and miscellaneous construction equipment.

• Crane – For assembly of the wind towers, cranes are transported in sections over numerous trips to the site. Assembled cranes may be crawled between tower sites.

• Concrete trucks for tower foundations. • Construction staff and other incidental truck trips.

Page 4: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph
Page 5: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph
Page 6: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 5

4. Trip Generation The following table represents an order-of-magnitude estimate of the total number of loaded truck trips entering the project site associated with construction of the towers. This trip generation estimate does not include the trips associated with the construction of the access roads.

Table 1 – Preliminary Trip Generation Estimate (loaded trucks entering) Component/Truck Type Assumption Trips Blades One blade per truck, 3 per tower 87 Towers 6 tower sections per tower 174 Nacelle One nacelle per truck 29 Hub, Nose Cone, and other components

7 truck trips per tower 203

Road Construction Gravel trucks 10 cubic yards per truck, plus other construction equipment.

Unk

Crane Several trips per access point depending on the degree of disassembly.

Unk

Concrete 250 to 450 cubic yards per foundation, 8 cubic yards per truck. Assume 50 trips per tower.

1,450

Total Heavy Vehicle Trips 1,943 unk = unknown Note: trips should be doubled to account for exiting. 5. Design Vehicle Research Transportation of turbine components and associated construction material involves numerous conventional and specialized transportation vehicles. Wind turbine components (such as the tower sections, blade sections and nacelle) are transported separately. The actual dimensions and specifications of the design vehicles may vary, depending on the specific type of truck and trailer arrangement used for transport. For planning purposes, worst-case transport requirements are based on the Nordex N100 (2.5 MW) Turbine. However, market availability of wind turbines could dictate the use of an alternate turbine from the proposed Nordex N100 machine. Any turbine ultimately selected will be of similar technology, size, appearance, operating characteristics, and approximate generating capacity. The following table summarizes the blade length for the Nordex N100 turbine with a 327-foot (99.8 m) hub height.

Table 2 – Nordex Turbine Blade Lengths Blade length Turbine

Supplier Turbine Size

(MW) Metric English Nordex 2.5 48.7 m 160 ft

This table shows that the blade length for the Nordex N100 is 160-feet. Therefore, for the purpose of this route analysis, design vehicles were developed assuming a 160-foot trailer with and without a manually controlled articulated rear axle as shown in the following drawings. The minimum turning radius requirements will ultimately be dependent on the wind turbine supplier selected. Both design vehicles were used to determine the worst-case scenario for each intersection.

Design Vehicle 1 without Manually Controlled Articulated Rear Axle

Design Vehicle Dimensions for Route Planning Purposes. Actual Dimensions will vary.

Page 7: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 6

Design Vehicle 2 with Manually Controlled Articulated Rear Axle

6. Route Evaluation An initial evaluation of the potential local routing plan was conducted by traveling area roadways and documenting existing conditions. Probable travel routes, constraints, and potential improvements were then identified. The following table summarizes the results of the existing conditions inventory. Refer to Figure 3 for roadway grades on the probable travel routes.

Table 3 – Road Characteristics

Road From To Lane Width

Pavement Condition

Surface Type Speed Limit

State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

NY Route 16 I-86 Pennsylvania Line Varies 22-52 Good Asphalt Varies

30-55 mph US Route 219 I-86 River Street 48 Good Asphalt 55-mph

NY Route 417 W. Five Mile Rd NY Route 16 Varies22-62 Good Asphalt Varies

30-45-mph NY Route 952W I-86 NY Route 417 24 Good Asphalt 45-mph

County Roads Route 30 (Nine Mile Rd/ Chipmunk Rd)

Allegany Indian Reservation Allegany Town line 22 Poor Asphalt 45-mph

Route 60 (Nine Mile Rd/ Four Mile Rd/River Rd)

Allegany Indian Reservation City of Olean line 20 Fair Asphalt 45-mph

Local Roads Nine Mile Rd US Route 219 County Rd 30 22 Fair/Poor Asphalt 45-mph Chipmunk Rd County Rd 30 Chipmunk Run Rd 22 Fair/Poor Asphalt 45-mph Chipmunk Run Rd Chipmunk Rd Nichols Run Rd 20-22 Poor Oil-Stone/Dirt 55-mph

Nichols Run Rd Church St NY Route 16 20 Poor Asphalt – Oil-Stone/Dirt

Varies 40-45-mpn

Old US Rt 219/Main St Interstate 86 Old Rt 219/Main St 20-24 Fair Asphalt Varies 20-40-mph

Church St Main St Nichols Run Rd 20 Poor Asphalt 30-mph State Line Rd NY Route 16 Nichols Run Rd 20 Poor Oil-Stone/Dirt Not Posted

Constitution Ave NY Route 417 Buffalo St 22 Good Asphalt Varies 30-35-mph

Buffalo St Constitution Ave Wayne St 34-36 Good Asphalt 30-mph Wayne St Buffalo St NY Route 16 34-36 Good Asphalt 30-mph W. Riverside Dr County Rd 60 NY Route 16 22-24 Good Asphalt 30-mph

The local routing plan also evaluated all roads in the project vicinity for bridge restrictions to ensure that the preferred and alternate routes can accommodate the design vehicles. A list of bridge restrictions are referenced in Table 4 and are shown on Figure 4.

Design Vehicle Dimensions for Route Planning Purposes. Actual Dimensions will vary.

Page 8: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 7

Table 4 – Bridge Restrictions

Number BIN Town Carried Crossed Restriction Dimension3 Primary Owner

1 66001691 Carrollton Town I-86 219 Height 833' ON

14' 3" Under NYSDOT

2a 10734721 Allegany Town I-86 Nine Mile Rd

CR 6 Height 833' ON 14' 3" Under NYSDOT

2b 1073471 Allegany Town I-86 Nine Mile Rd

CR 6 Height 833' 0" ON 14' 9" Under NYSDOT

Width 13’5” ON Posted Load

R-Posted (No): Closed to commercial traffic 3 6064850 Allegany

Town 951R Allegheny River

Height 10’9” ON

NYSDOT

4a 10737921 Allegany Town I-86 417 Height 833' ON

15' 2" Under NYSDOT

4b 10737911 Allegany Town I-86 417 Height 833' ON

14' 3" Under NYSDOT

5 10920322 Allegany Town I-86 Five Mile Rd Height 833' ON

13' 9" Under NYSDOT

6 10920511,2 Olean City I-86 Buffalo St. Height 833' ON

15' Under NYSDOT

7 77073201,2 Olean City

Western NY & Penn Buffalo St Height 833' ON

14' Under Railroad

8a 10920611,2 Olean City I-86 Johnson St Height 833' ON

14' 4” Under NYSDOT

8b 10920621,2 Olean City I-86 Johnson St Height 833' ON

14' 4” Under NYSDOT

9a 10920811,2 Olean City I-86 River St Height 833' ON

14' 2” Under NYSDOT

9b 10920821,2 Olean City I-86 River St Height 833' ON

14' 1” Under NYSDOT

10 10920991 Olean City 16 I-86 Height 833' ON

16' 1” Under NYSDOT

Key: BIN = Bridge Identification Number 1 = Noted 16 Food Manufactured/Modular Home Route. 2 = Noted Construction and other Restrictions area (# 05-2007-0019). Construction area is from mile marker 17-5112-

3124 to 17- 5112-5013. Isolated EB left lane closure. Right lane width is 12’ with 10’ shoulder. 3 = Dimensions noted are the permitted vertical clearance.

Based on this assessment, there are several route options from Interstate 86 to each of the proposed wind tower access roads. It is assumed that the wind components will typically be delivered directly to the tower sites and that the staging area will be used primarily to store spools of cable, set up the construction trailers, park vehicles and dozers, etc. Refer to Figure 5 which shows the preferred local travel route of the wind components, as well as other potential alternate routes for each site. The Preferred Access Route is considered the most probable route for access to each site. It is noted that some of geometric constraints for the alternate route options are provided to illustrate why the Preferred Access Route was identified as the most desirable route to the wind turbine sites. The preferred route option to the proposed O&M building and the substation are also shown on Figure 5. 6A. Preferred Wind Turbine Access Route:

To Wind Turbine Sites 1E-18E: Use Exit 26 from Interstate 86. Turn right onto NY Route 16 and travel southbound through the City of Olean and southbound and westbound through the Town of Olean into the Town of Allegany. Turn right onto Nichols Run Road and travel west. Turn right onto Chipmunk Run Road and travel north to the site access road. Turn right into the site. To Wind Turbine Sites 1W-11W: Use Exit 26 from Interstate 86. Turn right onto NY Route 16 and travel southbound through the City of Olean and southbound and westbound through the Town of Olean into the Town of Allegany. Turn right onto Nichols Run Road and travel west through the Chipmunk Run Road intersection. Travel west on Nichols Run Road and turn right into the site access road.

Page 9: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 8

6B. Alternate Wind Turbine Access Route #1:

To Wind Turbine Sites 1E-18E: Use the eastbound Exit 23 off ramp from Interstate 86. Turn right onto US Route 219 and travel southbound through the Allegany Indian Reservation and into the Town of Carrollton. Turn left onto Old Route 219/Main Street and continue southbound into the Village of Limestone. Turn left onto Church Street and travel eastbound toward the Town of Allegany. Church Street turns into Nichols Run Road. Continue eastbound on Nichols Run Road and turn left onto Chipmunk Run Road. Travel northbound on Chipmunk Run Road and turn right into the site access road. To Wind Turbine Sites 1W-11W: Use the eastbound Exit 23 off ramp from Interstate 86. Turn right onto US Route 219 and travel southbound through the Allegany Indian Reservation and into the Town of Carrollton. Turn left onto Old Route 219/Main Street and continue southbound into the Village of Limestone. Turn left onto Church Street and travel eastbound toward the Town of Allegany. Church Street turns into Nichols Run Road. Continue eastbound on Nichols Run Road and turn left into the site access road. Alternate Access Route #1 Constraints: A review of the intersection geometry indicates that the design vehicle travel paths will impact non-participating parcels located at the I-86 Eastbound Off Ramp/US Route 219 intersection and at the Main Street/Church Street intersection. In addition, the design vehicles may have difficulty traversing a significant 11% grade located on Nichols Run Road prior to the wind turbine site access roads (as shown on Figure 3).

6C. Alternate Wind Turbine Access Route #2:

To Wind Turbine Sites 1E-18E: Use the eastbound Exit 23 off ramp from Interstate 86. Turn right onto US Route 219 and travel southbound. Turn left onto Nine Mile Road (turns into County Road 30) and travel eastbound. Turn right onto Chipmunk Road (County Road 30) and travel southbound through the Town of Carrollton. Continue southbound and turn left into the site access road. To Wind Turbine Sites 1W-11W: Use the eastbound Exit 23 off ramp from Interstate 86. Turn right onto US Route 219 and travel southbound. Turn left onto Nine Mile Road (turns into County Road 30) and travel eastbound. Turn right onto Chipmunk Road (County Road 30) and travel southbound through the Town of Carrollton. Chipmunk Road turns into Chipmunk Run Road. Continue southbound and turn right onto Nichols Run Road. Continue westbound on Nichols Run Road and turn right into the site access road. Alternate Access Route #2 Constraints: A review of the intersection geometry indicates that the design vehicle travel paths will impact non-participating parcels located at the I-86 Eastbound Off Ramp/US Route 219 intersection, impact light poles at the US Route 219/Nine Mile Road intersection, and require the removal of a structure on a non-participating parcel at the Nine Mile Road/Chipmunk Road intersection. In addition, the design vehicles may have difficulty traversing a significant 12% grade located on Chipmunk Road prior to the wind turbine site access roads (as shown on Figure 3).

6D. Alternate Wind Turbine Access Route #3:

To Wind Turbine Sites 1E-18E: Use Exit 24 from Interstate 86 and travel southbound on NY Route 952W. Turn left onto NY Route 417 and travel eastbound into the City of Olean. Turn right onto NY Route 16 and travel southbound through the City of Olean and southbound and westbound through the Town of Olean into the Town of Allegany. Turn right onto Nichols Run Road and travel west. Turn right onto Chipmunk Run Road and travel north to the site access road. Turn right into the site. To Wind Turbine Sites 1W-11W: Use Exit 24 from Interstate 86 and travel southbound on NY Route 952W. Turn left onto NY Route 417 and travel eastbound into the City of Olean. Turn

Page 10: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 9

right onto NY Route 16 and travel southbound through the City of Olean and southbound and westbound through the Town of Olean into the Town of Allegany. Turn right onto Nichols Run Road and travel west through the Chipmunk Run Road intersection. Travel west on Nichols Run Road and turn right into the site access road. Alternate Access Route #3 Constraints: A review of the intersection geometry indicates that the Exit 24 ramps may need to be improved to accommodate the design vehicle travel paths. In addition, the design vehicle travel paths will also impact non-participating parcels located in the City of Olean at the NY Route 16/NY Route 417 intersection.

6E. Alternate Wind Turbine Access Route #4:

To Wind Turbine Sites 1E-18E: Use the railroad station located adjacent to Constitution Avenue in the City of Olean to transport the wind tower components. Turn left onto Constitution Avenue and travel eastbound. Turn right onto Buffalo Street and travel southbound. Bear left onto Wayne Street and travel eastbound toward NY Route 16. Turn right onto NY Route 16 and travel southbound through the City of Olean and southbound and westbound through the Town of Olean into the Town of Allegany. Turn right onto Nichols Run Road and travel west. Turn right onto Chipmunk Run Road and travel north to the site access road. Turn right into the site. To Wind Turbine Sites 1W-11W: Use the railroad station located adjacent to Constitution Avenue in the City of Olean to transport the wind tower components. Turn left onto Constitution Avenue and travel eastbound. Turn right onto Buffalo Street and travel southbound. Bear left onto Wayne Street and travel eastbound toward NY Route 16. Turn right onto NY Route 16 and travel southbound through the City of Olean and southbound and westbound through the Town of Olean into the Town of Allegany. Turn right onto Nichols Run Road and travel west through the Chipmunk Run Road intersection. Travel west on Nichols Run Road and turn right into the site access road. Alternate Access Route #4 Constraints: A review of the intersection geometry indicates that the design vehicle travel paths will impact non-participating parcels at the Buffalo Street/Constitution Avenue intersection and impact utility and signal poles located at the NY Route 16/Wayne Street intersection. It is noted that the shorter but heavier wind tower components could still be transported via the railroad to minimize regional truck travel.

6F. Alternate Wind Turbine Access Route #5:

To Wind Turbine Sites 1E-18E: Use Exit 26 from Interstate 86. Turn right onto NY Route 16 and travel southbound through the City of Olean and southbound and westbound through the Town of Olean into the Town of Allegany. Turn right onto a new proposed access road from NY Route 16 that utilizes on old mining road. This new access road will connect to the access road for the wind tower sites. To Wind Turbine Sites 1W-11W: Use Exit 26 from Interstate 86. Turn right onto NY Route 16 and travel southbound through the City of Olean and southbound and westbound through the Town of Olean into the Town of Allegany. Turn right onto a new proposed access road from NY Route 16 that utilizes on old mining road. This new access road will connect to Chipmunk Run Road. Turn left onto Chipmunk Run Road and travel southbound. Turn right on to Nichols Run Road and travel west. Continue westbound on Nichols Run Road and turn right into the site access road. Alternate Access Route #5 Constraints: No geometric constraints have been identified.

Page 11: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 10

6G. Alternate Wind Turbine Access Route #6:

To Wind Turbine Sites 1E-18E: Use Exit 26 from Interstate 86. Turn right onto NY Route 16 and travel southbound through the City of Olean and southbound and westbound through the Town of Olean into the Town of Allegany. Turn right onto State Line Road and travel north through the Nichols Run Road/Chipmunk Run Road intersection. State Line Road turns into Chipmunk Run Road. Travel north to the site access road and turn right into the site. To Wind Turbine Sites 1W-11W: Use Exit 26 from Interstate 86. Turn right onto NY Route 16 and travel southbound through the City of Olean and southbound and westbound through the Town of Olean into the Town of Allegany. Turn right onto State Line Road and travel north to the Nichols Run Road/Chipmunk Run Road intersection. Turn left onto Nichols Run Road. Travel west on Nichols Run Road and turn right into the site access road.

Alternate Access Route #6 Constraints: A review of the intersection geometry indicates that the design vehicle travel paths will impact non-participating parcels located at the NY Route 16/State Line Road intersection.

6H. O&M Building Access Route:

To O&M Building: Use the eastbound or westbound Exit 23 off ramp from Interstate 86. Turn right or left onto US Route 219 and travel southbound. Turn left onto Nine Mile Road (turns into County Road 30) and travel eastbound. Turn right onto Chipmunk Road (County Road 30) and travel southbound and turn left into to the O&M building/staging area. O&M Building Access Route Constraints: It is noted that the O&M building/staging area will be used primarily to store spools of cable, set up the construction trailers, park vehicles and dozers, etc. Therefore, these types of vehicles are not as large as the oversized component delivery trucks and will not experience the constraints associated with the wind tower component vehicles as detailed in the Alternate Wind Turbine Access Route #2 summary. However, while it is possible to access the O&M building/staging area from the north on Chipmunk Road, it may be difficult for certain types of vehicles such as construction trailers to navigate the steep vertical and curvilinear horizontal curves located between the O&M building and the wind turbine site access road to the south on Chipmunk Road (as shown on Figure 3). Therefore, it is recommended that the construction trailers and other similar transport vehicles be restricted from using Chipmunk Road to the south of the O&M building and utilize one of the preferred or alternative routes detailed above to access the wind turbine sites.

6I. Substation Access Routes:

To Substation (Option 1): Use Exit 26 from Interstate 86. Turn right onto NY Route 16 and travel southbound through the City of Olean and turn right onto McCann Hollow Road and travel west. Turn right onto South Avenue and travel north. Turn left onto Stoneybrook Road and travel west. Stoneybrook Road turns into Camelback Lane and continues northbound. Continue on Camelback Lane to the private land necessary to access the substation. To Substation (Option 2): Use Exit 26 from Interstate 86. Turn right onto NY Route 16 and travel southbound through the City of Olean and turn right onto Riverside Drive. Travel west and turn left onto Camelback Lane. Continue on Camelback Lane southbound to the private land necessary to access the substation. Substation Access Route Constraints: It is noted that the anticipated design vehicle destined to the substation will be primarily construction vehicles/delivery trucks associated with building the structure, and passenger vehicles. Therefore, these types of vehicles are not as large as the oversized turbine component delivery trucks. No geometric constraints have been identified. It is also noted that portions of Camelback Lane is a private road and that

Page 12: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 11

Allegany Wind LLC anticipates entering into an agreement with the landowner to gain use of Camelback Lane during both construction and operation/maintenance of the substation.

7. Constraints and Conceptual Improvements for the Preferred Access Route.

Each of the routes described above and shown on Figure 5 has a number of constraining features, particularly intersection turning radii. The path of the worst-case design vehicle was evaluated along the preferred travel route to identify conceptual intersection improvements required. Figure 6 shows the locations of the constraining intersections for the Preferred Access Route and the alternate access routes. An individual diagram was developed to show potential improvement areas for each of the constraints along the preferred travel routes as shown on Figure 7. This diagram shows approximate right-of-way and generally includes two improvement options for each of the intersections where applicable:

• Path Option A – Widening for an articulating design vehicle – This option shows

that an articulating design vehicle will require improvement on both the inside and outside curve of an intersection.

• Path Option B – Widening for a non-articulating design vehicle – This option

shows that a non-articulating design vehicle will require widening only on the inside of the curve.

The final limit of improvements may be a combination of widening on the inside and the outside of the curve and is expected to be within the areas shown on Figure 7. These limits will be confirmed with the final wind turbine supplier and transportation provider. It is also noted that Nichols Run Road has been posted for a 10 ton weight limit just west of Chipmunk Run Road due to rutting of the existing oil and stone surface from gas, oil, and timber truck activities located in the project vicinity. It may be necessary to improve some local road segments that provide access to the proposed tower locations, such as Nichols Run Road and Chipmunk Run Road. The extent of the roadway segment improvements will be verified with the contractor. The minimum site access road specifications shown on Figure 8 should apply.

Figure 8 – Minimum Pavement Cross Section Specifications

8. Loads and Permits

Special hauling permits are required when loads exceed legal dimensions or weights. The following table summarizes these maximum legal dimensions for State Highways. Transport of the blades, nacelles, tower sections and crane will require a variety of special hauling permits. Actual loads will depend on the specific turbine supplier, crane equipment chosen, and degree of disassembly of the crane.

(15 feet)

(1 foot) (1.3 feet)

Page 13: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 12

Table 5 – Dimensional Criteria for Special Hauling Permits Element Oversized? (Yes/No)

Approximate Dimension Vehicle Characteristic State

Highway Limit Blade Nacelle Tower

Sections Crane

Width of vehicle, inclusive of load 8 feet 1

Yes 12.0’

Yes 12.0’

Yes 16’

Yes Unk

Height of vehicle from underside of tire to top of vehicle, inclusive of load

13 feet 6 inches

No 12.4‘

Yes 15’

Yes 16’

Yes Unk

Length of combination of vehicles inclusive of load and bumpers

65 feet 1

Yes > 160’

Yes < 160’

Yes < 160’

Yes < 160’

Weight of component excluding vehicle 80,000 pounds

No

Yes 182,000

lbs

Yes 136,800

lbs

Yes >500,000

lbs Source: adapted from NYSDOT PERM 30 Information Concerning Special Hauling Permits 1) Qualifying or Access Highways allow 8.5 foot width and unlimited length. The types of permits depend on the characteristics of the vehicle and its cargo, number of trips, distance traveled, and duration. Nacelles can weigh approximately 182,000 lbs, and when combined with the transport vehicle, the total weight can exceed 200,000 pounds. When any vehicle exceeds 200,000 pounds, exceeds 16 feet in width or height, or exceeds 160 feet in length, special super load permits (PERMIT Type 1S) are required from the NYSDOT for each vehicle trip. The following list summarizes the driveway permits and special hauling permits that may be required for this project. Allegany Wind LLC will coordinate with the affected agencies and transportation providers to insure the all required permits are obtained.

Roadway Improvement/Driveway Permits • NYSDOT – A Highway Work Permit (PERM 33) will be required for any physical

improvements within the NYSDOT right-of-way. This will apply for state highway intersection or road improvements.

• Cattaraugus County – Based on conversations with the County Civil Engineer, no permits are expected for the Preferred Access Route.

• Town of Allegany – Based on conversations with the Highway Superintendent, no permits are required.

Overload Permits • NYSDOT – NYSDOT permit package outlines the guidelines, types and fees for various

special hauling permits. Based on this outline and discussions with NYSDOT special hauling permit representatives, it is expected that the project will require the Type 13 Jobsite permit to cover most of the special hauling trips (not including super loads). Type 13 permits are issued at 6 month intervals and can be extended for up to a maximum of one year. Several Type 1 permits for individual convoys may also be required such as the following:

o PERM 85 – Special Hauling Route Survey for Over Dimensional Vehicles o PERM 12 – Special Hauling Pre-Approval Application Form for Future Permit o PERM 80 – Special Hauling Pre-Approval Application Form for a Future Crane

Permit o PERM 39-1 – Special Hauling Trip & Building Movement Permit o PERM 39-2k – Special Hauling Monthly, Annual & Blanket Permit o PERM 39-3g – Special Hauling Permit Amendment o PERM 99 – Special Hauling Permit Additional Trailer Attachment Form o PERM 39-4 – Special Hauling Permit Vehicle Configuration Attachment Sheet

• Cattaraugus County – Based on conversations with the County Civil Engineer, no permits are expected for the Preferred Access Route.

Page 14: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Allegany Wind LLC, Allegany Wind Power Project

Engineers, Planners and Surveyors Route Evaluation Study- Page 13

• Town of Allegany – Based on meetings with the Highway Superintendent, specific overload permits required for transport vehicles will be developed for this project based on criteria similar to the NYSDOT permits.

9. Remediation Plan Specialized transport vehicles with numerous axles are designed to distribute the weight and minimize roadway impacts, nevertheless roadway impacts might occur. The condition of the transportation infrastructure will be left as good, or better than it was found at the beginning of the project. The basis for the remediation plan is a preconstruction photo log (see Appendix A), that establishes the pre-existing conditions. In addition to the photo log, a pre-construction video and an associated report outlining pre-construction conditions, including road culvert pipes and the reinforcement measures that will be employed along the haul routes will be provided prior to construction of the wind farm project. Allegany Wind LLC is committed to working with the Town, County, and State agencies to confirm necessary transportation improvements before and after completion of the project, and that such improvements will be stipulated in the project approval. This could include:

• Additional route and condition surveys. • Bonding of improvements. • Temporary removal of obstacles and replacement in kind. • Completion of improvements before the project. • Restoration after the project.

10. Conclusions The purpose of this assessment is to determine the probable local travel routes and potential improvements required for delivery of major wind turbine components during the construction of the Allegany Wind Power Project for the purpose of determining potential environmental impacts. A number of intersection and segment improvements have been identified. A logistics firm and/or transportation provider experienced with oversized loads will be engaged in the final routing and permit process. Confirmation of improvements, construction details, traffic control plans, escort vehicles, scheduling, etc. will be necessary. F:\Projects\2008\08-132d\DRAFT Report.doc

Page 15: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph
Page 16: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph
Page 17: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph
Page 18: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph
Page 19: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph
Page 20: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Appendix A

Existing Conditions Photographs

Page 21: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph
Page 22: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory

Photograph 1 – Constitution Ave at Railroad Driveway Photograph 2 – Railroad Driveway at Constitution Ave

Photograph 3 – Constitution Ave at Railroad Driveway Photograph 4 – Constitution Ave at Buffalo St

Photograph 5 – Buffalo St at Constitution Ave Photograph 6 – Buffalo St at Constitution Ave

Page 23: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory (Continued)

Photograph 7 – Wayne St at NY Route 16 Photograph 8 – NY Route 16 at Wayne St

Photograph 9 – Plaza Drwy at NY Route 16/Wayne St Photograph 10 – NY Route 16 at Wayne St

Photograph 11 – NY Route 16 at NY Route 417 Photograph 12 – NY Route 417 at NY Route 16

Page 24: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory (Continued)

Photograph 13 – NY Route 16 at NY Route 417 Photograph 14 – NY Route 417 at NY Route 16

Photograph 15 – NY Route 16 Bridge at Allegany River Photograph 16 – NY Route 16 in City of Olean

Photograph 17 – NY Route 16 at Olean Hospital Photograph 18 – NY Route 16 at Exit 26

Page 25: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory (Continued)

Photograph 19 –Exit 26 at NY Route 16 Photograph 20 – Exit 26 Ramp at NY Route 16

Photograph 21 – NY Route 16 at Exit 16 Photograph 22 – NY Route 417 at 7th St

Photograph 23 – NY Route 417 at River Rd Photograph 24 – NY Route 417 at NY Route 952W

Page 26: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory (Continued)

Photograph 25 – NY Route 952W at NY Route 417 Photograph 26 – NY Route 417 at NY Route 952W

Photograph 27 – NY Route 952W south of Exit 24 Photograph 28 – NY Route 952W at Exit 24 EB Off

Photograph 29 – Exit 24 EB Off at NY Route 952W Photograph 30 – NY Route 952W at Exit 24 EB Off

Page 27: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory (Continued)

Photograph 31 – Exit 24 WB Off at NY Route 952W Photograph 32 – NY Route 952W at NY Route 952W

Photograph 33 – NY Route 952W at Exit 24 WB Off Photograph 34 – US Route 219 at Exit 23 EB Off

Photograph 35 – US Route 219 at Exit 23 EB Off Photograph 36 – Exit 23 EB Off at US Route 219

Page 28: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory (Continued)

Photograph 37 – US Route 219 at Nine Mile Rd Photograph 38 – Nine Mile Rd at US Route 219

Photograph 39 – US Route 219 at Nine Mile Rd Photograph 40 – US Route 219

Photograph 41 – Nine Mile Road Photograph 42 – County Road 30 at Chipmunk Rd

Page 29: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory (Continued)

Photograph 43 – Chipmunk Rd at County Road 30 Photograph 44 – County Road 30 at Chipmunk Rd

Photograph 45 – Chipmunk Rd at County Road 30 Photograph 46 – Chipmunk Road

Photograph 47 – Chipmunk Run Road Photograph 48 – Chipmunk Run Rd at Nichols Run Rd

Page 30: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory (Continued)

Photograph 49 – Nichols Run Rd at Chipmunk Run Rd Photograph 50 – State Line Rd at Nichols Run Rd

Photograph 51 – Nichols Run Rd Photograph 52 – Nichols Run Road at Chipmunk Run Rd

Photograph 53 – NY Route 16 at Nichols Run Rd Photograph 54 – Nichols Run Rd at NY Route 16

Page 31: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory (Continued)

Photograph 55 – NY Route 16 at Nichols Run Rd Photograph 56 – Old Mining Rd at NY Route 16

Photograph 57 – NY Route 16 at Old Mining Rd Photograph 58 – Nichols Run Rd

Photograph 59 – Nichols Run Rd Photograph 60 – Main St at Church St

Page 32: Route Evaluation Study Allegany Wind Power Project Town of ... DEIS/3... · Pavement Condition Surface Type Speed Limit State Roads Interstate 86 Exit 26 Exit 23 48 Good Asphalt 65-mph

Road Condition Picture Inventory (Continued)

Photograph 61 – Main St at Church St Photograph 62 – Church St at Main St

Photograph 63 – NY Route 16 at State Line Rd Photograph 64 – NY Route 16 at State Line Rd

Photograph 65 – State Line Rd at NY Route 16 Photograph 66 – State Line Rd at NY Route 16