22
Round Hill Solar Project Augusta County, VA Community Information Meeting June 30, 2020

Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Round Hill Solar ProjectAugusta County, VA

Community Information Meeting June 30, 2020

Page 2: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Submit questions and comments

On desktop it will look something

like this.

On mobile devices and

tablets it will look

something like this.

Page 3: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Agenda Introductions Strata Solar Solar in Virginia Solar Photovoltaic (PV) Characteristics Project Overview Site Location and Selection Facility Site Design Visual Simulations Project Benefits Augusta County Permitting Process Key Permits and Reviews Questions and Answers Wrap-Up

Page 4: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Project Team Introduction

Dave StonerDevelopment Consultant

Louis IannoneSite Acquisition & Development

Chelsea WoodfinDevelopment Manager

Valerie LongAttorney

Jamie WeistP.E. & Associate

Cutter SydnorP.E.

Ellen TusingEngineer

Strata Solar

Kimley-Horn

Williams Mullen

Page 5: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Strata Solar• Leading US Utility-Scale Solar Company

• Based in Durham, NC

• Fully Integrated Company• Develop• Engineer and Build• Finance• Own• Operate and Maintain

• 400 Professional Staff + 1,000 Construction Staff

• More information at www.stratasolar.com

Page 6: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Constructed 200+ Projects

2,000 MW Nationwide

Projects Operating in 22 states

National O&M Coverage

No other company has developed and constructed more utility-scale solar projects than Strata Solar

Strata Solar

Page 7: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

• Constructed 7 projects in VA totaling 267MW

• Operating those 7 projects under contract to Dominion

• 5 projects totaling 362MW currently in construction

• 10 projects in development totaling 895 MW, including Round Hill

• Close working relationship with Dominion Energy

Strata Solar’s Experience in Virginia Constructed and Operating

Under Construction

Project Location Size (Mwac)

COD

Gloucester Gloucester, VA 20.0 2019

Sappony Sussex, VA 20.0 2018

Buckingham Buckingham, VA 22.0 2018

Scott II Powhatan, VA 22.0 2018

Correctional New Kent, VA 22.5 2018

Remington Fauquier, VA 20.0 2017

Colonial Trail Surry, VA 142.5 2019

Project Location Size(Mwac)

COD

Spring Grove I Surry, VA 97.0 2020

Rochambeau James City, VA 20.0 2021

Ft. Powhatan Prince George, VA 150.0 2021

Myrtle Suffolk, VA 15.0 2020

Greensville Greensville, VA 80.0 2020

Page 8: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Strata Network Operations Center

Page 9: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Solar in VirginiaWhy Are We Hearing So Much About Solar Projects?• Solar is a huge new growth industry that rural

communities and landowners can benefit from

• It’s one of the cheapest sources of energy today –and that’s why Dominion and the State of Virginia has embraced it in their future energy plans

• It is not just driven by government policies and mandates

• It’s not just Virginia – this same transition and growth of solar is happening in most states

Page 10: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Solar PV Characteristics• Low-cost new energy source

• Non-obtrusive land use

• No noise

• No glare or light

• No health, safety, nor environmental concerns• No toxic materials • No EMF• No shock or fire hazard

• Decreased storm water runoff once operational compared to existing agricultural use via ground cover and storm water basins

• No impact to property values

• Decommissioning• Proper removal and salvage/disposal of

components• Allows return to agricultural or timber use

Page 11: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Round Hill Solar Project Overview• Applicant: Round Hill Solar, LLC

• Size: 83 megawatt (MW) utility-scale solar farm

• Location: 1.5 mi north of Stuarts Draft

• Site: Predominately agricultural use;

– 10 parcels – 880 acres

– Approximately 560 acre development

• Design: Solar Photovoltaic (PV) with Tracking Technology

• Interconnect: To Dominion’s existing 115kV transmission line

• Power Sales: Regional Utility

• Investment: $100 million Investment in Augusta County

• Schedule: Development 2019-2021

– Construction Q4 2021-2022

– Operations Q4 2022

Page 12: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Site Location and Selection

• Willing landowner partners• Suitable acreage and topography

– allows for reasonable setbacks and buffers

• Transmission line onsite for interconnection

• Large but contiguous site • Rural area with few immediate

neighbors• Mostly farm land, which minimizes

impact on natural habitats• GA zoning - allows solar but not

located on land slated for industrial development -Comprehensive Plan

Page 13: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Preliminary Site Plan

Page 14: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Facility Site DesignSetbacks: • 50-200’+ from roads or adjacent properties to the

solar arrays • Setbacks vary depending upon adjacent use

Buffers: • Minimum 30’ vegetative screen around perimeter • Design varies depending upon adjacent use

Design:• 15’ height limit for solar facilities • Gentle topography allows minimized grading • Grass & clover mix groundcover under panel

areas, pollinator species mix in buffers• Stormwater and erosion and sedimentation

control facilities

Decommissioning: • Plan & Security

Page 15: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Visual SimulationsGuthrie Road

Day of Planting

Projected 10-Year Growth (2-3’ per year)

Page 16: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Visual SimulationsWhite Hill Road

Day of Planting (10’ Tall)

Projected 10-Year Growth (2-3’ per year)

Page 17: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Project BenefitsRevenue Generation and Economic BenefitsCapital investment of approximately $100 million in Augusta County,

generating tax benefits and economic activityAugusta County revenue share payment in lieu tax of $116,000 annually; net

$4.1 million over 35-year project life; requires County OrdinanceSiting Agreement payments to Augusta County at start of constructionDirect and indirect economic effect in the County of labor income plus

purchase of local goods and services of approximately $30 million during construction and $700,000 annually during operations

Job CreationWill create approximately 200 construction jobs over a 12-month timeline8-10 permanent operations jobs, plus additional contractors for operations

and maintenance

Page 18: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Project Benefits (Continued)

Community Benefits Significant local economic benefits with minimal requirement for Augusta County

facilities or services New industry to “partner with the community” on various potential initiatives Workforce training and development Solar energy educational opportunities Long-term open land preservation (after decommissioning)

Environmental Benefits Clean, efficient, reliable, renewable power for up to 16,000 Virginia homes Supports Virginia and Dominion’s renewable energy goals Project offsets annual carbon dioxide emissions approx. equivalent to removing

40,000 cars from VA highways, 1000 railcars of coal, or 450 million lbs. of carbon emissions.

Page 19: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Augusta County Special Use Permit• Zoning Ordinance allows solar on GA zoned land subject to Special Use

Permit• Application will be consistent with ordinance and provide:

– Community Meeting– Economic Impact Analyses– Site Plan meeting setback and buffering requirements– Landscaping Plan– Ocular Study– Construction Traffic Plan and Road Repair Bond– Property Value Study– Decommissioning Plan and Bonding– Analysis of “substantially in accordance” with Comprehensive Plan

• Review process will include multiple public hearings for citizen input

••

Page 20: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Additional Permits and Reviews1. VA Department of Environmental Protection Permit by Rule

2. Studies and Reviews

a. Threatened and Endangered Species Review – VA Department of Environmental Protection

b. Archaeological and Cultural Resource Surveys – VA Department of Historic Resources

3. US Army Corps of Engineers Wetlands Delineation and Permit, if needed

4. VPDES Storm Water Discharge Permit

5. Erosion & Sedimentation Control Permits

6. VDOT Crossings and Driveway Permits

7. Phase I Environmental Site Assessment

8. Certificate of Public Convenience & Necessity (VA Utility PPA or Acquisition)

Page 21: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Questions and AnswersAdditional questions after the meeting may be submitted to:[email protected]

- or -

Contact Louis or Dave (contact info on next page)

Q&A will be posted on website in the future

Page 22: Round Hill Solar Project€¦ · Round Hill Solar Project. Augusta County, VA. Community Information Meeting . June 30, 2020

Closing• Information is available at

• https://www.roundhillsolarproject.com/• Website will be updated with Q&A and new information over time

• Printed materials available at:Community Development Department Stuarts Draft LibraryAugusta County Government Center 2857 Stuarts Draft Highway, #10718 Government Center Lane, Verona, VA Stuarts Draft, VA

• Can submit questions or comments by email or phone below

• Contacts:Louis Iannone David StonerManager, Site Acquisition & Development Strata Solar Development Consultant919-960-6015 x305 [email protected] [email protected]