ROMANIA
ERBD LOAN 33391 – “CONSTANTA BYPASS”
REHABILITATION WORKS FOR 7 BRIDGES IN
DOBROGEA AREA
PREQUALIFICATION DOCUMENTS
Final Version
FEBRUARY 2011
PQD pt publicare in Dobrogea Area
page 1 of 70
PREQUALIFICATION DOCUMENTS
TABLE OF CONTENTS
INVITATION FOR PREQUALIFICATION............................................................................................................. 2
INSTRUCTIONS TO APPLICANTS......................................................................................................................... 7
1. GENERAL .......................................................................................................................................................... 7
2. ELIGIBILITY AND QUALIFICATION CRITERIA ....................................................................................................... 7
3. PREPARATION AND SUBMISSION OF APPLICATIONS ............................................................................................ 8
4. PREQUALIFICATION AND TENDERING................................................................................................................. 9
PREQUALIFICATION DATA ................................................................................................................................. 12
PARA. 1.1 NAME OF THE EMPLOYER ................................................................................................................. 12
PARA. 1.2 CONTRACT FOR PREQUALIFICATION.................................................................................................. 12
PARA. 1.3 TENDERING SCHEDULE ..................................................................................................................... 12
PARA. 1.4 TYPE OF CONTRACT.......................................................................................................................... 13
PARA. 2.1 ELIGIBILITY ....................................................................................................................................... 13
PARA. 2.2 QUALIFICATION CRITERIA ................................................................................................................. 13
1 General Experience. .................................................................................................................................. 13
2 Personnel Capabilities. ............................................................................................................................. 17
3 Equipment Capabilities. ............................................................................................................................ 19
4 Financial Position. .................................................................................................................................... 21
5 Litigation History ...................................................................................................................................... 21
PARA. 2.2 JOINT VENTURE REQUIREMENTS ...................................................................................................... 21
PARA. 3.1 SITE VISIT/PRE-TENDER MEETING.................................................................................................... 22
PARA. 3.2 LANGUAGE........................................................................................................................................ 22
PARA. 3.3 PREQUALIFICATION APPLICATION ..................................................................................................... 22
PARA. 3.4 ADDRESS OF EMPLOYER ................................................................................................................... 22
PARA. 3.5 DEADLINE FOR SUBMISSION.............................................................................................................. 22
PARA. 3.5 IDENTIFICATION OF APPLICATION...................................................................................................... 22
PARA. 4.2 RESULTS OF PREQUALIFICATION ....................................................................................................... 22
LETTER OF APPLICATION................................................................................................................................... 24
APPLICATION FORMS........................................................................................................................................... 28
GENERAL INFORMATION........................................................................................................................................... 29
GENERAL EXPERIENCE RECORD ............................................................................................................................... 30
JOINT VENTURE SUMMARY ...................................................................................................................................... 31
PARTICULAR EXPERIENCE RECORD .......................................................................................................................... 32
DETAILS OF CONTRACTS OF SIMILAR NATURE AND COMPLEXITY............................................................................. 33
CONSTRUCTION EXPERIENCE IN KEY ACTIVITIES ..................................................................................................... 34
CURRENT CONTRACT COMMITMENTS /WORKS IN PROGRESS ................................................................................... 35
PERSONNEL CAPABILITIES ........................................................................................................................................ 36
CANDIDATE SUMMARY............................................................................................................................................. 37
EQUIPMENT CAPABILITIES ........................................................................................................................................ 38
FINANCIAL CAPABILITY ............................................................................................................................................ 39
LITIGATION HISTORY ................................................................................................................................................ 41
VOLUME II ................................................................................................................................................................ 42
Volume II includes general information on the location, scope and duration of the contract(s)
and other relevant data as appropriate on the project, the works, the tender, the contract etc
PQD pt publicare in Dobrogea Area
page 2 of 70
VOLUME I
ROMANIA
ERBD Loan 33391 – “Constanta Bypass”
INVITATION FOR PREQUALIFICATION
Rehabilitation Works for 7 Bridges in Dobrogea Area
This Invitation for Prequalification follows the General Procurement Notice for this project,
which was published in Procurement Opportunities, on 4th of January 2011.
Romanian National Company of Motorways and National Roads / Romania (the Employer)
intends applying the proceeds of a loan from the European Bank for Reconstruction and
Development [the Bank] towards the cost of:
Lot 4 -
“Rehabilitation works for Bridge no. 07 at Cernavoda, on A2 km 157+600
andfor Bridge no. 10 over the railway on DN 2B km 47+975 at Gaiseanca”
Lot 5 – “Rehabilitation works for Bridge no. 08 at Borcea, on A2 km 149+680”
Lot 6 -
“Rehabilitation works for Bridge no. 4 on DN 22C km 38+002 at Poarta Alba, for Bridge
no. 5 on DN 2A km 196+739 at Ovidiu, for Bridge no. 6 on DN 3 km 242+286 at Murfatlar
(Basarabi) and for Bridge no. 9 on DN 39 km 49+157 at Mangalia”.
The Employer intends prequalifying firms and joint ventures to tender for the following contracts
to be funded from part of the proceeds of the loan, as they might prefer (each lot will be subject to
an individual contract):
Lot 4, Lot 5, Lot 6, Lot 4 + Lot 5, Lot 4 + Lot 6, Lot 5 + Lot 6, Lot 4 + Lot 5 + Lot6
The rehabilitation and maintenance works included in the Project, mainly concern superstructure
and bridge deck, with only limited intervention on infrastructure, for the following bridges:
Lot 4 – “Rehabilitation works for Bridge no. 07 at Cernavoda, on A2 km 157+600 and for Bridge
no. 10 over the railway on DN 2B km 47+975 at Gaiseanca”
Bridge no. 07 at Cernavoda, on A2 km 157+600
This Bridge is located near Cernavoda on the A2 motorway inserted in the Trans-European
Network – Transport Priority Project number 7 section Fetesti-Cernavoda which connects the
Black Sea with Central Europe, over the Danube River. This bridge runs North-West to South-
East and is a 21 span structure, composed by two different parts: 3 main spans which are a
metallic truss bridge with a steel transversal section allowing the road and rail traffic and the
approach ramps composed by 18 spans of a double road carriageway also supported by a metallic
structure.
PQD pt publicare in Dobrogea Area
page 3 of 70
The main characteristics of this bridge are defined as follows:
• Structure typology: metallic truss bridge
• Overhead Length: 1596 m
• Overhead Width: 34.40 m
• Number of spans: 21(17+3+1)
• Greater span length: 166.90 m
Bridge no. 10 over the railway on DN 2B km 47+975 at Gaiseanca
This bridge is located near Gaiseanca on the DN 2B national road which connects Braila to Buzau
approximately at the km 47, over a railway. This bridge runs North-East to South-West and is a 3
span structure composed by pre-stressed concrete beams.
The main characteristics of this bridge are defined as follows:
• Structure typology: pre-stressed concrete.
• Overhead Length: 42 m
• Overhead Width: 10.70 m
• Number of spans: 3
• Greater span length: 18 m
Lot 5 – Rehabilitation works for Bridge no. 08 at Borcea, on A2 km 149+680
This Bridge is located near Fetesti on the A2 motorway (approximately at the km 150) inserted in
the European Transport Corridor IV section Fetesti-Cernavoda which connects the Black Sea with
Central Europe, over the Danube River. This bridge runs North-West to South-East and is a 14
span structure, composed by two different parts: 3 main spans which are a metallic truss bridge
with a steel transversal section allowing the road and rail traffic and the approach ramps
composed by 11 spans of a double road carriageway supported by pre-stressed concrete beams.
The main characteristics of this bridge are defined as follows:
• Structure typology: metallic truss bridge and pre-stressed concrete.
• Overhead Length: 968 m
• Overhead Width: 34.40 m
• Number of spans: 14 (3+3+8)
• Standard Concrete Span Length: 50 m
• Greater span length: 140.90 m
PQD pt publicare in Dobrogea Area
page 4 of 70
Lot 6 - “Rehabilitation works for Bridge no. 4 on DN 22C km 38+002 at Poarta Alba, for Bridge
no. 5 on DN 2A km 196+739 at Ovidiu, for Bridge no. 6 on DN 3 km 242+286 at Murfatlar
(Basarabi) and for Bridge no. 9 on DN 39 km 49+157 at Mangalia”
Bridge no. 4 on DN 22C km 38+002 at Poarta Alba
This bridge is located near Porta Alba on the DN22C national road which connects Cernavoda to
Constanta approximately at the km 38, over the Danube-Black Sea Channel. This bridge runs
North to South and is a 3 span structure, which the main span is an arch bridge composed by a
steel beams transversal section and the approach ramps are a simple pre-stressed concrete beams
bridge.
The main characteristics of this bridge are defined as follows:
• Structure typology: Arch bridge, steel - concrete
• Overhead Length: 170 m
• Overhead Width: 22.40 m
• Number of spans: 3
• Greater span length: 111 m
Bridge no. 5 on DN 2A km 196+739 at Ovidiu
This bridge is located near Ovidiu on the DN2A national road which connects Harsova to
Constanta approximately at the km 196, over the Danube-Black Sea Channel. This bridge runs
North to South and is a 6 span structure, which the main span is an arch bridge composed by a
steel beams transversal section and the approach ramps are a small continuous span bridge
composed by pre-stressed concrete beams.
The main characteristics of this bridge are defined as follows:
• Structure typology: Arch bridge, steel - concrete
• Overhead Length: 261 m
• Overhead Width: 22.30 m
• Number of spans: 6(2+1+3)
• Standard Concrete Span Length: 30 m
• Greater span length: 111 m
Bridge no. 6 on DN 3 km 242+286 at Murfatlar (Basarabi)
This bridge is located near Basarabi on the DN3 national road which connects Bucharest to
Constanta approximately at the km 242, over the Danube-Black Sea Channel.. This bridge runs
PQD pt publicare in Dobrogea Area
page 5 of 70
North-East to South-West and is a 5 span structure, which the main span is an arch bridge
composed by a steel beams transversal section and the approach ramps are a small continuous
span bridge composed by pre-stressed concrete beams.
The main characteristics of this bridge are defined as follows:
• Structure typology: Arch bridge, steel - concrete and pre-stressed concrete for side spans
• Overhead Length: 226 m
• Overhead Width: 14.20 m
• Number of spans: 5 (2+1+2)
• Standard Concrete Span Length: 30 m
• Greater span length: 104.5 m
Bridge no. 9 on DN 39 km 49+157 at Mangalia
This Bridge is located in Mangalia on the DN39 national road which connects Constanta to
Mangalia and runs North-West to South-East approximately at the km 49. This bridge is a 8 span
structure divided as follows: 3 steel spans and 5 pre-stressed concrete spans.
The main characteristics of this bridge are defined as follows:
• Structure typology: steel - concrete and pre-stressed concrete beam bridge
• Overhead Length: 434 m
• Overhead Width: 19.30 m
• Number of spans: 8
Greater span length: 95.20 m
Generally speaking, the list of the rehabilitations works refers to:
• Restoring to a former state and/or capacity
• Improving serviceability (structural and/or functional)
• Strengthening
The works mainly consist in concrete repair, steel structure over-coating, joints and bearings
replacement, pavement removal and replacement, walkway pavement and waterproofing, lighting
electrical equipment replacement
Prequalification and tendering for contracts to be financed with the proceeds of a loan from the
Bank is open to firms and joint ventures of firms from any country.
Procurement under projects financed by the European Bank for Reconstruction and Development (the
Bank), is carried out in accordance with procedures laid down in the Bank’s Procurement Policies and
Rules.
PQD pt publicare in Dobrogea Area
page 6 of 70
Prequalification documents can be downloaded from the site below.
The prequalification documents must be duly completed and delivered to the address below,
before 5th of April 2011, 11:00 local hour. Documents which are received late will be rejected
and returned unopened.
Interested firms may obtain further information from the following office:
Romanian National Company of Motorways and National Roads
Contact name Mrs. LIVIU COSTACHE – General Director
Executing agency Romanian National Company of Motorways and National Roads
Address No. 38 Dinicu Golescu Blvd, sector 1, 11th floor, 010873, Bucharest,
ROMANIA
Web site www.cnadnr.ro
Tel: (40) 021 264 32 92
Fax: (40) 021 312 66 62
Date: …nd of … 20…
PQD pt publicare in Dobrogea Area
page 7 of 70
INSTRUCTIONS TO APPLICANTS
1. General
1.1 The Employer, as defined in the Prequalification Data, intends using the proceeds of a loan
from the European Bank for Reconstruction and Development (the Bank), to finance
contract(s) for which this Invitation for Prequalification is issued. Payments by the Bank will
be made only at the request of the Employer and upon approval by the Bank and will be
subject in all respects to the terms and conditions of the Loan Agreement. The proceeds of the
Bank’s loan will not be used for payments to persons or entities, or for any import of goods, if
such payment or import is prohibited by a decision of the United Nations Security Council
taken under Chapter VII of the Charter of the United Nations.
1.2 The Employer intends prequalifying firms and joint ventures to tender for the contract(s)
outlined in the Prequalification Data.
1.3 The tendering schedule is outlined in the Prequalification Data.
1.4 General information on the location, scope and duration of the contract and other relevant data
is attached as Volume II. The tender documents will be modelled on the Bank's Standard
Tender Documents. The type of contract to be used is specified in the Prequalification Data.
2. Eligibility and qualification criteria
2.1 Subject to paragraph 1.1, prequalification is open to firms and joint ventures from any country
or countries, unless specified otherwise in the Prequalification Data.
2.2 Prequalification will be based on the applicant meeting the minimum pass/fail criteria
regarding the applicant's general and particular experience, personnel and equipment
capabilities, and financial position, specified in the Prequalification Data, as demonstrated by
the applicant's responses in the forms attached to the Letter of Application and other requested
documentation. Specific requirements for joint ventures are also set forth in the
Prequalification Data. The Employer reserves the right to waive minor deviations from the
criteria, if they do not materially affect the capability of an applicant to perform the contract.
2.3 When the applicant intends obtaining highly specialised inputs (essential for execution of the
contract) from specialised subcontractors, application forms shall be completed for such
subcontractors and their inputs.
2.4 No affiliate of the Employer shall be eligible to tender or participate in a tender in any capacity
whatsoever, unless it can be demonstrated that there is not a significant degree of common
ownership, influence or control between the Employer and the affiliate.
2.5 Where a firm, its affiliates or parent company, in addition to consulting, also has the capability
to manufacture or supply goods or to construct works, that firm, its affiliates or parent
company normally cannot be a supplier of goods or works on a project for which it provides
consulting services, unless it can be demonstrated that there is not a significant degree of
common ownership, influence or control.
PQD pt publicare in Dobrogea Area
page 8 of 70
2.6 An applicant shall not be eligible to participate where it has been determined to have engaged
in corrupt, fraudulent, coercive or collusive practices in accordance with sub-paragraph 4.9(c).
3. Preparation and submission of applications
3.1 If specified in the Prequalification Data, a clarification meeting and/or site visit will be held at
the time, date and place specified. Prospective applicants may request in writing clarification
of the project requirements and the criteria for qualification at any time up to 21 days prior to
the deadline set for the submission of applications. The written responses will be sent to all
prospective applicants that have received the prequalification documents (including the query
but without identifying the source).
3.2 All information requested for prequalification shall be provided in the language specified in
the Prequalification Data. Where information is provided in another language it shall be
accompanied by a translation into the language of the prequalification documents. This
translation will govern and be used for interpreting the information. Information should be
submitted in the formats specified in the application forms in these prequalification
documents.
3.3 The application for prequalification shall consist of the following:
(a) the Letter of Application
(b) the forms and documentation specified in the Prequalification Data.
3.4 Failure to provide information which is essential to evaluate the applicant's qualifications or to
provide timely clarification or substantiation of the information supplied may result in
disqualification of the applicant.
3.5 Submission of applications for prequalification must be received in sealed envelopes, which
shall be delivered either by hand or by registered mail, to the address specified in the
Prequalification Data no later than the date specified in the Prequalification Data, and shall
bear the identification specified in the Prequalification Data. The Employer reserves the right
to accept or reject late applications.
3.6 The name and mailing address of the applicant shall be clearly marked on the envelope.
PQD pt publicare in Dobrogea Area
page 9 of 70
4. Prequalification and tendering
4.1 The Employer reserves the right to:
1 amend the scope and value of any contract(s) to be tendered, in which event only those
prequalified applicants who meet the amended requirements will be invited to tender for
the contract(s).
2 reject or accept any application; and
3 cancel the prequalification process and reject all applications.
The Employer shall neither be liable nor be under any obligation to inform the applicant of
the grounds for such action.
4.2 Applicants will be advised in writing by fax or telex, within the period specified in the
Prequalification Data, of the result of their application and of the names of the prequalified
applicants, without giving any reason for the Employer's decision.
4.3 Only firms and joint ventures that have been prequalified under this procedure will be
invited to tender. A firm may apply for prequalification both individually and as part of a
joint venture. However, a prequalified firm or a member of a prequalified joint venture
may participate as a tenderer in only one tender, either individually or as a partner in a
joint venture, for the contract. Submission or participation by a tenderer in more than one
tender for a contract (other than alternatives which have been permitted or requested) will
result in the disqualification of all tenders for that contract in which the party is involved.
However, this does not limit the inclusion of the same subcontractor in more than one
tender.
4.4 An applicant may be “conditionally prequalified” by the Employer, that is, prequalified
subject to certain specified requirements being met by the applicant prior to a prescribed
deadline, such as: the issuance of the Invitation to Tender. Requirements for “conditional
prequalification” include such factors as:
• revision to a preliminary joint venture agreement;
• substitution of a specialised subcontractor or collaborator which is determined to be
unqualified;
• improving critical project management;
• access to special equipment;
• recruiting experts in specialised fields;
• the applicant’s questionable ability to undertake the proposed contract due to the pending
award of other significant contracts;
• submitting bank reference(s) or evidence of line of credit.
4.5 At the time of submitting their tenders, prequalified tenderers shall update the relevant
information used for prequalification to confirm that they continue to comply with the
qualification criteria and verify that the information previously provided is still valid and
PQD pt publicare in Dobrogea Area
page 10 of 70
correct. A tenderer shall be disqualified if it no longer meets the qualification
requirements at the time of contract award.
4.6 Joint ventures must comply with the following requirements:
(a) The formation of a joint venture after prequalification, and any change in a
prequalified joint venture, will be subject to the written approval of the Employer prior
to the deadline for submission of tenders. Such approval may be denied if (i) partners
withdraw from a joint venture and the remaining partners do not meet the qualifying
requirements; (ii) the level of participation by partners or the structure of the joint
venture is substantially changed; (iii) the new joint venture is not qualified; or (iv) in
the opinion of the Employer, a substantial reduction in competition may result.
(b) Any tender shall be signed so as to legally bind all joint venture partners, jointly and
severally, and any tender shall be submitted with a copy of the joint venture agreement
providing for joint and several liability with respect to the contract.
4.7 The prequalification of a joint venture does not necessarily prequalify any of its partners
individually or as a partner in any other joint venture or association. In case of dissolution
of a joint venture, each of the constituent firms may prequalify if they meet all the
prequalification requirements, subject to the written approval of the Employer prior to the
deadline for submission of tenders.
4.8 Prequalified tenderers will be required to provide a tender security as outlined in the
Prequalification Data. The successful tenderer will be required to provide a performance
security. Details of these securities will be specified in the tender documents.
4.9 The Bank requires that clients (including beneficiaries of Bank loans), as well as tenderers, suppliers, contractors, concessionaires and consultants under Bank-financed contracts,
observe the highest standard of ethics during the procurement and execution of such contracts. In pursuance of this policy, the Bank:
(a) defines, for the purposes of this provision, the terms set forth below as follows:
(i) "corrupt practice" means the offering, giving, receiving, or soliciting, directly or indirectly,
anything of value to influence improperly the actions of another party;
(ii) "fraudulent practice" means any act or omission, including a misrepresentation, that
knowingly or recklessly misleads, or attempts to mislead, a party to obtain a financial or other benefit or to avoid an obligation;
(iii) “coercive practice” means impairing or harming, or threatening to impair or harm, directly or indirectly, any party or the property of the party to influence improperly the actions of a
party;
(iv) “collusive practice” means an arrangement between two or more parties designed to achieve an improper purpose, including influencing improperly the actions of another party;
PQD pt publicare in Dobrogea Area
page 11 of 70
(b) will reject a proposal for prequalification if it determines that an applicant recommended for prequalification has engaged in corrupt, fraudulent, coercive
or collusive practices in competing for the contract in question;
(c) will declare a firm ineligible indefinitely or for a stated period of time, to be prequalified under a Bank-financed contract if it at any time determines that:
• the firm has engaged in corrupt, fraudulent, coercive or collusive practices in competing for, or in executing, a Bank-financed contract; or
• the firm has been found by a judicial process or other official inquiry to have engaged in corrupt, fraudulent, coercive or collusive practices.
PQD pt publicare in Dobrogea Area
page 12 of 70
PREQUALIFICATION DATA
Instructions to Applicants:
para. 1.1 Name of the Employer
Romanian National Company of Motorways and National Roads
para. 1.2 Contract for Prequalification
Rehabilitation and maintenance works for 7 bridges in the Dobrogea area. Works are dived in
3(three) lots, as follows:
Lot 4 -
“Rehabilitation works for Bridge no. 07 at Cernavoda, on A2 km 157+600 and for Bridge
no. 10 over the railway on DN 2B km 47+975 at Gaiseanca”
Lot 5 – “Rehabilitation works for Bridge no. 08 at Borcea, on A2 km 149+680”
Lot 6 -
“Rehabilitation works for Bridge no. 4 on DN 22C km 38+002 at Poarta Alba, for Bridge
no. 5 on DN 2A km 196+739 at Ovidiu, for Bridge no. 6 on DN 3 km 242+286 at Murfatlar
(Basarabi) and for Bridge no. 9 on DN 39 km 49+157 at Mangalia”.
The works mainly consist in concrete repair, steel structure overcoating, joints and bearings
replacement, pavement removal and replacement, walkway pavement and waterproofing, lighting
electrical equipment replacement
para. 1.3 Tendering Schedule
The planned tendering schedule is as follows:
Invitation to prequalify 11th of February 2011
Submission of Prequalification Applications 5th of April 2011
Results of Prequalification 25th of April 2011
Invitation to tender 16th of May 2011
Submission of tenders 4th of July 2011
Contract Award 15th of August 2011
PQD pt publicare in Dobrogea Area
page 13 of 70
para. 1.4 Type of Contract
The contract will be based on unit prices. The FIDIC Conditions of Contract for Civil Works -
first edition – 1999 (Red Book), will be used. The Tender Documents will be the Bank’s Standard
Tender Document for civil works.
para. 2.1 Eligibility
No restrictions.
para. 2.2 Qualification Criteria
To be prequalified, an applicant must demonstrate to the Employer that it substantially satisfies
the requirements regarding experience, personnel, equipment, financial position and litigation
history, specified below:
1 General Experience.
The applicant shall meet the following minimum criteria:
Lot 4 -
(a) average annual turnover in construction (defined as billing for works in progress and
completed) over the last 5 years (2005-2009) not less than 17.5 million Euro (use Forms
2 and 2A)
(b) successful experience as prime contractor in the execution of at least two bridge construction or rehabilitation projects (construction or rehabilitation of a bridge within a larger project will be
considered as a bridge project), of a nature and complexity comparable to the proposed
contract, of a value of 7 million Euro each and fully executed (started and finished) from the 1st
of January 2005 to the deadline for submission of the present prequalification (use Form 3A)
(c) achievement of the following minimum total key production rate, as yearly average,
from the 1st of January 2005 to the deadline for submission of the present
prequalification (use Form 3B):
pavement on bridges, inclusive of waterproofing – 7,700 m2
concrete elements protection with epoxy and polyurethane resin coat – 25,000 m2
anti-corrosion treatment and painting of steel structures– 33,000 m2
Lot 5 –
(a) average annual turnover in construction (defined as billing for works in progress and
completed) over the last 5 years (2005-2009) not less than 20.5 million Euro (use Forms
2 and 2A)
(b) successful experience as prime contractor in the execution of at least two bridge construction or rehabilitation projects (construction or rehabilitation of a bridge within a larger project will be
considered as a bridge project), of a nature and complexity comparable to the proposed
contract, of a value of 8.2 million Euro each and fully executed (started and finished) from the
1st of January 2005 to the deadline for submission of the present prequalification (use Form 3A)
PQD pt publicare in Dobrogea Area
page 14 of 70
(c) achievement of the following minimum total key production rate, as yearly average,
from the 1st of January 2005 to the deadline for submission of the present
prequalification (use Form 3B):
pavement on bridges, inclusive of waterproofing – 7,000 m2
concrete elements protection with epoxy and polyurethane resin coat – 21,000 m2
Lot 6 -
(a) average annual turnover in construction (defined as billing for works in progress and
completed) over the last 5 years (2005-2009) not less than 15.9 million Euro (use Forms
2 and 2A)
(b) successful experience as prime contractor in the execution of bridge construction or
rehabilitation projects and/or in the execution of bridge construction or rehabilitation
included in complex projects, of a nature and complexity comparable to the proposed
contract, of a cumulated value of 6.4 million Euro, fully executed (started and finished)
from the 1st of January 2005 to the deadline for submission of the present
prequalification and not smaller than 1.5 million Euro each (use Form 3A);
(c) achievement of the following minimum total key production rate, as yearly average,
from the 1st of January 2005 to the deadline for submission of the present
prequalification (use Form 3B):
pavement on bridges, inclusive of waterproofing – 8,800 m2
concrete elements protection with epoxy and polyurethane resin coat – 26,000 m2
anti-corrosion treatment and painting of steel structures– 26,000 m2
Lot 4 + Lot 5
(a) average annual turnover in construction (defined as billing for works in progress and
completed) over the last 5 years (2005-2009) not less than 38 million Euro (use Forms 2
and 2A)
(b) successful experience as prime contractor in the execution of at least two bridge construction or rehabilitation projects (construction or rehabilitation of a bridge within a larger project will be
considered as a bridge project), of a nature and complexity comparable to the proposed
contract, of a value of 15.2 million Euro each and fully executed (started and finished) from the
1st of January 2005 to the deadline for submission of the present prequalification (use Form 3A)
(c) achievement of the following minimum total key production rate, as yearly average,
from the 1st of January 2005 to the deadline for submission of the present
prequalification (use Form 3B):
pavement on bridges, inclusive of waterproofing – 14,700 m2
concrete elements protection with epoxy and polyurethane resin coat – 46,000 m2
anti-corrosion treatment and painting of steel structures– 33,000 m2
Lot 4 + Lot 6
(a) average annual turnover in construction (defined as billing for works in progress and
completed) over the last 5 years (2005-2009) not less than 33.4 million Euro (use Forms
2 and 2A)
(b) successful experience as prime contractor in :
PQD pt publicare in Dobrogea Area
page 15 of 70
• successful experience as prime contractor in the execution of at least two bridge
construction or rehabilitation projects (construction or rehabilitation of a bridge within a
larger project will be considered as a bridge project), of a nature and complexity
comparable to the proposed contract, of a value of 7 million Euro each and fully executed
(started and finished) from the 1st of January 2005 to the deadline for submission of the
present prequalification (use Form 3A) and in
• the execution of bridge construction or rehabilitation projects and/or in the
execution of bridge construction or rehabilitation included in complex projects, of a
nature and complexity comparable to the proposed contract, of a cumulated value of
6.4 million Euro, fully executed (started and finished) from the 1st of January 2005
to the deadline for submission of the present prequalification and not smaller than
1.5 million Euro each (use Form 3A); the projects presented for compliance with the
second bullet of the present criterion shall be different than the ones presented for
compliance with the first bullet.
(c) achievement of the following minimum total key production rate, as yearly average,
from the 1st of January 2005 to the deadline for submission of the present
prequalification (use Form 3B):
pavement on bridges, inclusive of waterproofing – 16,500 m2
concrete elements protection with epoxy and polyurethane resin coat – 51,000 m2
anti-corrosion treatment and painting of steel structures– 59,000 m2
Lot 5 + Lot 6
(a) average annual turnover in construction (defined as billing for works in progress and
completed) over the last 5 years (2005-2009) not less than 36.5 million Euro (use Forms
2 and 2A)
(b) successful experience as prime contractor in:
• successful experience as prime contractor in the execution of at least two bridge
construction or rehabilitation projects (construction or rehabilitation of a bridge
within a larger project will be considered as a bridge project), of a nature and
complexity comparable to the proposed contract, of a value of 8.2 million Euro each
and fully executed (started and finished) from the 1st of January 2005 to the deadline
for submission of the present prequalification (use Form 3A) and in
• the execution of bridge construction or rehabilitation projects and/or in the execution
of bridge construction or rehabilitation included in complex projects, of a nature and
complexity comparable to the proposed contract, of a cumulated value of 6.4 million
Euro, fully executed (started and finished) from the 1st of January 2005 to the
deadline for submission of the present prequalification and not smaller than 1.5
million Euro each (use Form 3A); the projects presented for compliance with the
second bullet of the present criterion shall be different than the ones presented for
compliance with the first bullet.
(c) achievement of the following minimum total key production rate, as yearly average,
from the 1st of January 2005 to the deadline for submission of the present
prequalification (use Form 3B):
pavement on bridges, inclusive of waterproofing – 15,800 m2
concrete elements protection with epoxy and polyurethane resin coat – 47,000 m2
PQD pt publicare in Dobrogea Area
page 16 of 70
anti-corrosion treatment and painting of steel structures– 26,000 m2
Lot 4 + Lot 5 + Lot 6
(a) average annual turnover in construction (defined as billing for works in progress and
completed) over the last 5 years (2005-2009) not less than 54 million Euro (use Forms 2
and 2A)
(b) successful experience as prime contractor in
• successful experience as prime contractor in the execution of at least two bridge
construction or rehabilitation projects (construction or rehabilitation of a bridge
within a larger project will be considered as a bridge project), of a nature and
complexity comparable to the proposed contract, of a value of 15.2 million Euro
each and fully executed (started and finished) from the 1st of January 2005 to the
deadline for submission of the present prequalification (use Form 3A) and in
• the execution of bridge construction or rehabilitation projects and/or in the execution
of bridge construction or rehabilitation included in complex projects, of a nature and
complexity comparable to the proposed contract, of a cumulated value of 6.4 million
Euro, fully executed (started and finished) from the 1st of January 2005 to the
deadline for submission of the present prequalification and not smaller than 1.5
million Euro each (use Form 3A); the projects presented for compliance with the
second bullet of the present criterion shall be different than the ones presented for
compliance with the first bullet.
(c) achievement of the following minimum total key production rate, as yearly average,
from the 1st of January 2005 to the deadline for submission of the present
prequalification (use Form 3B):
pavement on bridges, inclusive of waterproofing – 23,500 m2
concrete elements protection with epoxy and polyurethane resin coat – 72,000 m2
anti-corrosion treatment and painting of steel structures– 58,500 m2
Notes:
The project value that will be taken into consideration is either the total project value, when the
contractor was acting as sole contractor, or the share of the total project value corresponding to its
share of the joint-venture participation, when the contractor was member of a joint-venture. The
project value corresponds to the value of the works, net of VAT and of any financing costs or
other similar costs. If a particular project was including other items (for example construction /
rehabilitation of a road), the value retained will be the one specifically related to bridge works.
In case that the applicant was member in a Joint Venture in a contract, the quantities of works
related to the applicant will be assessed the following way:
• where the applicant was performing all the works of a particular category, 100% of the
respective quantity of works is taken into consideration for the purpose of the evaluation;
• where the applicant had a share of more than 33% in the JV where all the resources were
put in common, 100% of the respective quantity of works is taken into consideration for
the purpose of the evaluation;
• where the applicant had a minor share (i.e. less or equal than 33%) in a JV where all the
resources were put in common, the percentage representing the share in JV shall be
PQD pt publicare in Dobrogea Area
page 17 of 70
applied to the total quantities executed under the contract, in order to identify the quantity
that shall be taken into consideration for the purpose of the evaluation.
2 Personnel Capabilities.
The applicant shall provide suitably qualified personnel to fill the following positions. For each
position the applicant will supply information (in Forms 5 and 5A) on a first choice candidate and
an alternate, each of whom should meet the experience requirements specified below:
Lot 4
Position Total experience
(years)
In similar works*
(years)
As manager of
similar works*
(years)
Project manager 10 7 4
Senior Bridge
Engineer
15 10
Site manager 1 10 7 4
Site manager 2 10 7 4
Lot 5
Position Total experience
(years)
In similar works*
(years)
As manager of
similar works*
(years)
Project manager 10 7 4
Senior Bridge
Engineer
15 10
Site manager 10 7 4
Lot6
Position Total experience
(years)
In similar works*
(years)
As manager of
similar works*
(years)
Project manager 10 7 4
Senior Bridge
Engineer
15 10
Site manager 1 10 7 4
Site manager 2 10 7 4
Site manager 3 10 7 4
Site manager 4 10 7 4
PQD pt publicare in Dobrogea Area
page 18 of 70
Lot 4 + Lot 5
Position Total experience
(years)
In similar works*
(years)
As manager of
similar works*
(years)
Project manager 10 7 4
Senior Bridge
Engineer
15 10
Site manager 1 10 7 4
Site manager 2 10 7 4
Site manager 3 10 7 4
Lot 4 + Lot 6
Position Total experience
(years)
In similar works*
(years)
As manager of
similar works*
(years)
Project manager 10 7 4
Senior Bridge
Engineer 1
15 10
Senior Bridge
Engineer 2
15 10
Site manager 1 10 7 4
Site manager 2 10 7 4
Site manager 3 10 7 4
Site manager 4 10 7 4
Site manager 5 10 7 4
Site manager 6 10 7 4
Lot 5 + Lot 6
Position Total experience
(years)
In similar works*
(years)
As manager of
similar works*
(years)
Project manager 10 7 4
Senior Bridge
Engineer 1
15 10
Senior Bridge
Engineer 2
15 10
Site manager 1 10 7 4
Site manager 2 10 7 4
Site manager 3 10 7 4
Site manager 4 10 7 4
Site manager 5 10 7 4
PQD pt publicare in Dobrogea Area
page 19 of 70
Lot 4 + Lot 5 + Lot 6
Position Total experience
(years)
In similar works*
(years)
As manager of
similar works*
(years)
Project manager 10 7 4
Senior Bridge
Engineer 1
15 10
Senior Bridge
Engineer 2
15 10
Site manager 1 10 7 4
Site manager 2 10 7 4
Site manager 3 10 7 4
Site manager 4 10 7 4
Site manager 5 10 7 4
Site manager 6 10 7 4
Site manager 7 10 7 4
* Similar works are considered bridge works
3 Equipment Capabilities.
The applicant shall own, or have assured access to (through hire, lease, purchase agreement,
availability of manufacturing equipment, or other means), the following key items of equipment in
full working order, and must demonstrate that, based on known commitments, they will be
available for use in the proposed contract. The applicant may also list alternative equipment which
he would propose to use for the contract, together with an explanation of the proposal (use Form
6).
Lot 4
Equipment type and characteristics Minimum number required
1. By-bridge with a maxim payload of
platform of 600Kg
2
2. Lorry trucks 5
3. Asphalt plant 1
4. High Pressure (30000 psi) Waterjetting
SSPC-SP12
12
Lot 5
Equipment type and characteristics Minimum number required
1. By-bridge with a maxim payload of
platform of 600Kg
2
2. Lorry trucks 5
3. Asphalt plant 1
PQD pt publicare in Dobrogea Area
page 20 of 70
4. High Pressure (30000 psi) Waterjetting
SSPC-SP12
12
Lot 6
Equipment type and characteristics Minimum number required
1. By-bridge with a maxim payload of
platform of 600Kg
4
2. Lorry trucks 8
3. Asphalt plant 1
4. High Pressure (30000 psi) Waterjetting
SSPC-SP12
8
Lot 4 + Lot 5
Equipment type and characteristics Minimum number required
1. By-bridge with a maxim payload of
platform of 600Kg
3
2. Lorry trucks 10
3. Asphalt plant 1
4. High Pressure (30000 psi) Waterjetting
SSPC-SP12
24
Lot 4 + Lot 6
Equipment type and characteristics Minimum number required
1. By-bridge with a maxim payload of
platform of 600Kg
4
2. Lorry trucks 12
3. Asphalt plant 1
4. High Pressure (30000 psi) Waterjetting
SSPC-SP12
20
Lot 5 + Lot 6
Equipment type and characteristics Minimum number required
1. By-bridge with a maxim payload of
platform of 600Kg
4
2. Lorry trucks 12
3. Asphalt plant 1
4. High Pressure (30000 psi) Waterjetting
SSPC-SP12
20
Lot 4 + Lot 5 + Lot 6
Equipment type and characteristics Minimum number required
PQD pt publicare in Dobrogea Area
page 21 of 70
1. By-bridge with a maxim payload of
platform of 600Kg
7
2. Lorry trucks 18
3. Asphalt plant 1
4. High Pressure (30000 psi) Waterjetting
SSPC-SP12
32
4 Financial Position.
The applicant shall demonstrate that it has access to, or has available, liquid assets, unencumbered
real assets, lines of credit, and other financial means sufficient to meet the construction cash flow
for the contract for a period of 5 months, estimated as not less than (use Form 7):
Lot 4 – 2.9 million Euro or equivalent, taking into account the applicant's commitments for other
contracts.
Lot 5 - 3.4 million Euro or equivalent, taking into account the applicant's commitments for other
contracts.
contracts.
Lot 6 – 3.2 million Euro or equivalent, taking into account the applicant's commitments for other
contracts.
Lot 4 + Lot 5 – 6.3 million Euro or equivalent, taking into account the applicant's commitments
for other contracts.
Lot 4 + Lot 6 – 5.1 million Euro or equivalent, taking into account the applicant's commitments
for other contracts.
Lot 5 + Lot 6 – 6.6 million Euro or equivalent, taking into account the applicant's commitments
for other contracts.
Lot 4 + Lot 5 + Lot 6 – 9.5 million Euro or equivalent, taking into account the applicant's
commitments for other contracts.
The audited balance sheets for the last 5 (five) years shall be submitted and must demonstrate the
soundness of the applicant's financial position, showing long-term profitability. Where necessary,
the Employer will make inquiries with the applicant's bankers.
5 Litigation History
The applicant shall provide accurate information on any current or past litigation or arbitration
resulting from contracts completed or under execution by him over the last 5 (five) years (use
Form 8). A consistent history of awards against the applicant or any partner of a joint venture
may result in failure of the application.
All pending litigation shall in total not represent more than 25% of the Applicant’s average net
worth and shall be treated as resolved against the Applicant.
para. 2.2 Joint Venture Requirements
Joint Venture Requirements
Joint ventures must satisfy the following minimum qualification requirements:
PQD pt publicare in Dobrogea Area
page 22 of 70
(a) The lead partner shall meet not less than 40 percent of the qualifying criteria for general
experience point (a) (turnover) specified above. It shall also meet the criteria of soundness
of financial position and litigation history.
(b) The other partners (not more than 2) shall individually meet not less than 25 percent of the
qualifying criteria for general experience point (a) (turnover) specified above. They shall
also, individually, meet the criteria of soundness of financial position and litigation history.
(c) The joint venture must satisfy collectively the criteria for general experience points (b) and
(c), personnel and equipment capabilities and financial position (access to liquid assets,
unencumbered real assets, lines of credit) stated above, for which purpose the relevant
figures for each of the partners shall be added to arrive at the joint venture's total capacity.
Individual members must each satisfy the requirements for audited balance sheets and
litigation.
para. 3.1 Site Visit/Pre-Tender Meeting
Site visits will be held at the following date: 21st – 26
th of March 2011
Pre-tender meeting will be held at the following date: 28th of March 2011 – 1
st of April 2011
para. 3.2 Language
Language of the application for prequalification is English
para. 3.3 Prequalification Application
All the documents specified as forms in annex to this one.
para. 3.4 Address of Employer
38 Dinicu Golescu Blvd, 010873, Bucharest, Romania
para. 3.5 Deadline for Submission
5th of April 2011, at 11:00 o’clock.
para. 3.5 Identification of Application
The applicant shall write the words Application to prequalify for “Rehabilitation works for 7
bridges in Dobrogea area”, clearly specifying the Lot or combination of Lots on the envelope
containing all the application documents
para. 4.2 Results of Prequalification
Applicants will be notified of the results of the prequalification by the Employer by fax, within 10
weeks of the date of submission of applications.
para. 4.8 Tender Security
Tender security requested for tendering will be as follows:
PQD pt publicare in Dobrogea Area
page 23 of 70
Lot 4 – 420,000 Euro or equivalent,
Lot 5 – 500,000 Euro or equivalent,
Lot 6 – 385,000 Euro or equivalent,
Lot 4 + Lot 5 – 920,000 Euro or equivalent,
Lot 4+ Lot 6 – 805,000 Euro or equivalent,
Lot 5+ Lot 6 – 885,000 Euro or equivalent,
Lot 4+ Lot 5 + Lot 6 – 1,305,000 Euro or equivalent,
and shall be submitted in the form of a bank guarantee in Euro or equivalent in Romanian lei. The
exchange rate will be the annual rate as published by Romanian National Bank (BNR).
PQD pt publicare in Dobrogea Area
page 24 of 70
LETTER OF APPLICATION
[ Letterhead of the Applicant, or lead partner of a joint venture, including full postal address,
telephone no., fax no., telex no., email address and cable address ]
Date:................................
To: Romanian National Company of Motorways and National Roads
No. 38 Dinicu Golescu Blvd, sector 1, 8th floor, room 22
010873, Bucharest, ROMANIA
Sirs,
1. Being duly authorised to represent and act on behalf of ................................... (hereinafter “the
Applicant”), and having reviewed and fully understood all the prequalification information
provided in the prequalification documents and all clarification letters published on the web site
of the RNCMNR until the deadline for submission, the undersigned hereby apply to be
prequalified by yourselves as a tenderer for the following contract under the “Rehabilitation works
for 10 bridges in Dobrogea area” project:
Contract number Contract name
Lot x or any combination of
lots that the Applicant may
prefer
As appropriated
2. Attached to this letter are copies of original documents defining:
(a) the Applicant's legal status;
(b) its principal place of business;
(c) its place of incorporation (for Applicants which are corporations); or its place of
registration (for applicants which are partnerships or individually owned firms).
For applications by joint ventures, all information requested in the prequalification documents
is to be provided for the joint venture, if it already exists, and for each party to the joint venture
separately. The lead partner should be clearly identified. Each partner in the joint venture
shall sign the letter.
PQD pt publicare in Dobrogea Area
page 25 of 70
3. You and your authorised representatives are hereby authorised to conduct any inquiries or
investigations to verify the statements, documents and information submitted in connection
with this application, and to seek clarification from our bankers and clients regarding any
financial and technical aspects. This Letter of Application will also serve as authorisation
for any individual or authorised representative of any institution referred to in the supporting
information, to provide such information deemed necessary and as requested by yourselves
to verify statements and information provided in this application, such as the resources,
experience, and competence of the Applicant.
4. You and your authorised representatives may contact the following persons for further
information:
General and managerial inquiries
Contact 1 Telephone 1
Contact 2 Telephone 2
Personnel inquiries
Contact 1 Telephone 1
Contact 2 Telephone 2
Technical inquiries
Contact 1 Telephone 1
Contact 2 Telephone 2
Financial inquiries
Contact 1 Telephone 1
Contact 2 Telephone 2
Applications by joint ventures should provide on a separate sheet the requested information for
each party to the application.
5. This application is made in the full understanding that:
(a) tenders by prequalified applicants will be subject to verification of all information
submitted for prequalification at the time of tendering;
(b) you reserve the right to:
� amend the scope and value of any contracts tendered under this project; in such
an event, tenders will only be invited from prequalified applicants who meet the
revised requirements; and
PQD pt publicare in Dobrogea Area
page 26 of 70
� reject or accept any application, cancel the prequalification process, and reject
all applications; and
(c) you shall not be liable for any such actions and shall be under no obligation to inform
the Applicant of the grounds for such actions.
Applicants who are not joint ventures should delete paragraphs 6 and 7 and initial the
deletions.
6. Appended to this application, we give details of the participation of each party, including
capital contribution and profit/loss agreements, in the joint venture or association. We also
specify the financial commitment in terms of the percentage of the value of the (each)
contract, and the responsibilities for execution of the (each) contract.
7. We confirm that in the event that we tender, that tender, as well as any resulting contract,
will be:
(a) signed so as to legally bind all partners, jointly and severally; and
(b) submitted with a conformed joint venture agreement substantially in accordance
with the joint venture details outlined in the submission under paragraph 6 above and
providing joint and several liability of all partners in the event the contract is awarded to us.
PQD pt publicare in Dobrogea Area
page 27 of 70
8. The undersigned declare that the statements made and the information provided in the duly
completed application are complete, true, and correct in every detail.
Signed
Name
Authorised representative, for and on behalf of
(name of Applicant or lead partner of a joint
venture)
Signed
Signed
Name
Name
Authorised representative, for and on behalf of
(name of partner)
Authorised representative, for and on behalf of
(name of partner)
PQD pt publicare in Dobrogea Area
page 29 of 70
APPLICATION FORM (1) PAGE OF PAGES
General Information
All individual firms and each partner of a joint venture applying for prequalification are
requested to complete the information in this form.
Where the Applicant proposes to use named subcontractors for critical components of the works,
or for works in excess of [10 percent] of the value of the whole works, the following information
should also be supplied for the specialist subcontractor(s).
1. Name of firm
2. Head office address
3. Telephone
Contact
4. Fax
Telex
5. Place of incorporation / registration
Year of incorporation / registration
PQD pt publicare in Dobrogea Area
page 30 of 70
APPLICATION FORM (2) PAGE OF PAGES
General Experience Record
Name of Applicant or partner of a joint venture
All individual firms and all partners of a joint venture are requested to complete the information
in this form. The information supplied should be the annual turnover of the Applicant (or each
member of a joint venture), in terms of the amounts billed to clients for each year for work in
progress or completed, converted into euros, at the National Bank of Romania rate of exchange at
the end of the period reported.
Use a separate sheet for each partner of a joint venture.
Applicants are not required to enclose testimonials, certificates and publicity material with their
applications.
Annual turnover data (construction only)
Year Turnover Euro equivalent
1.
2.
3.
4.
5.
PQD pt publicare in Dobrogea Area
page 31 of 70
APPLICATION FORM (2A) PAGE OF PAGES
Joint Venture Summary
Names of all partners of a joint venture
1. Lead partner
2. Partner
3. Partner
Total value of annual construction turnover, in terms of work billed to clients, in euro equivalent,
converted at the National Bank of Romania rate of exchange at the end of the period reported:
Annual turnover data (construction only; euro equivalent)
Partner
Form 2
page no.
Year 1 Year 2
Year 3 Year 4 Year 5
1. Lead
partner
2.Partner
3.Partner
Totals
PQD pt publicare in Dobrogea Area
page 32 of 70
APPLICATION FORM (3) PAGE OF PAGES
Particular Experience Record
Name of Applicant or partner of a joint venture
To prequalify, the Applicant shall be required to pass the specified requirements set forth in this
form, as set out in the Prequalification Data.
On a separate page, using the format of Form (3A), the Applicant is requested to list all bridge
construction/rehabilitation contracts or all bridge construction / rehabilitation included in complex
projects of a value equivalent to:
7.0 million Euro for Lot 4
8.2 million Euro for Lot 5
6.4 million Euro for Lot 6, not smaller than 1.5 million Euro each
15.2 million Euro for Lot 4+Lot 5
7.0 million Euro + 6.4 million Euro (not smaller than 1.5 million Euro each) for Lot 4 + Lot 6
8.2 million Euro + 6.4 million Euro (not smaller than 1.5 million Euro each) for Lot 5 + Lot 6
15.2 million Euro + 6.4 million Euro (not smaller than 1.5 million Euro each) for Lot 4 + Lot 5 +
Lot 6
undertaken during the last 5 years. The partners of a proposed joint venture should provide details
of similar contracts proportionate to their share in the joint venture. The value should be based on
the currencies of the contracts converted into euros, at the date of completion, or for current
contracts at the time of award. The exchange rate to be taken into account will be the rate
published by the National Bank of Romania, for the related dates. The information is to be
summarised, using Form (3A), for each contract completed or under execution by the Applicant or
by each partner of a joint venture.
Where the Applicant proposes to use named subcontractors for critical components of the
works, or for work contents in excess of 10 percent of the value of the whole works, the
information in the following forms should also be supplied for each specialist subcontractor.
PQD pt publicare in Dobrogea Area
page 33 of 70
APPLICATION FORM (3A) PAGE OF PAGES
Details of Contracts of Similar Nature and Complexity
Name of Applicant or partner of a joint venture
Use a separate sheet for each contract and attach the relevant Taking Over Certificate or similar
document.
1. Number of contract
Name of contract
Country
2. Name of Employer
3. Address of Employer
4. Nature of works and special features relevant to the contract for which the Applicant
wishes to prequalify
5. Contract role (check one)
� Sole Contractor � Subcontractor � Management Contractor
� Partner in a joint venture
6. Value of the total contract/subcontract/partner share (in specified currencies at completion,
or at date of award for current contracts).
Currency Currency Currency
7. Equivalent value in euros
8. Date of award
9. Date of completion (Taking Over Certificate date)
10. Contract/subcontract duration (years and months)
years months
11. Specified requirements (key production)
12. For sole/prime contractors, indicate the approximate euro amount and nature of substantial
work (more than 20 percent in contract value) undertaken by subcontract, if any.
The Applicant should insert any specific contractual criteria required for particular operations,
such as annual volume of earthmoving, underground excavation, or placing concrete.
PQD pt publicare in Dobrogea Area
page 34 of 70
APPLICATION FORM (3B) PAGE OF PAGES
Construction Experience in Key Activities
Name of Applicant or partner of a joint venture
Use a separate sheet for each contract.
1. Number, Name and Country of contract
2. Name and Address of Employer
3. Award date (dd,mm,yyyy)
4. Completion date (dd,mm,yyyy) (Taking Over Certificate date)
5. Contract role (check one)
� Sole Contractor � Subcontractor � Management Contractor
� Partner in a joint venture
6. Total Contract Amount
- In local currency
- in EURO equivalent
7. For sole/prime contractors, indicate the approximate euro amount and nature of substantial
work (more than 20 percent in contract value) undertaken by subcontract, if any.
8. If a party in JV, specify participation of total Contract Amount
- %
- In local currency
- in EURO equivalent
9. Key production rates (as applicable for any Lot or combination of Lots the applicant might
apply for prequalification)
9.1 Pavement on bridges, inclusive of waterproofing – m2
9.2 Concrete elements protection with epoxy and polyurethane resin coat – m2
9.3 Anti-corrosion treatment and painting of steel structures – m2
PQD pt publicare in Dobrogea Area
page 35 of 70
APPLICATION FORM (4) PAGE OF PAGES
Summary Sheet:
Current Contract Commitments /Works in Progress
Name of Applicant or partner of a joint venture
Applicants and each partner to an application should provide information on their current
commitments under all contracts that have been awarded, or for which a letter of intent or
acceptance has been received, or for contracts approaching completion, but for which an
unqualified, full completion certificate has yet to be issued.
Name of contract Value of outstanding
work (current euro
equivalent)
Estimated completion date
1.
2.
3.
4.
5.
6.
PQD pt publicare in Dobrogea Area
page 36 of 70
APPLICATION FORM (5) PAGE OF PAGES
Personnel Capabilities
Name of Applicant
For specific positions essential to contract implementation, applicants should provide the names
of at least two candidates qualified to meet the specified requirements stated for each position.
The data on their experience should be supplied in separate sheets using one Form (5A) for each
candidate.
1.
Project Manager
Name of prime candidate
Name of alternate candidate
2.
Senior Bridge Engineer
Name of prime candidate
Name of alternate candidate
3.
Site Manager 1
Name of prime candidate
Name of alternate candidate
4.
Site Manager 2
Name of prime candidate
Name of alternate candidate
PQD pt publicare in Dobrogea Area
page 37 of 70
APPLICATION FORM (5A) PAGE OF PAGES
Candidate Summary
Name of Applicant
Position
Candidate
� Prime � Alternate
Candidate
information
1. Name of candidate
2. Date of birth
3. Professional qualifications
Present
employment
4. Name of employer
Address of employer
Telephone
Contact (manager / personnel officer)
Fax
Telex
Job title of candidate
Years with present Employer
Summarise professional experience over the last 20 years, in reverse chronological order.
Indicate particular technical and managerial experience relevant to the Project.
From To Company / Project / Position / Relevant technical and management
experience
PQD pt publicare in Dobrogea Area
page 38 of 70
APPLICATION FORM (6) PAGE OF PAGES
Equipment Capabilities
Name of Applicant
The Applicant shall provide adequate information to demonstrate that it has the capability to
meet the requirements for all items of equipment listed in the Prequalification Data. A separate
Form (6) shall be prepared for each item of equipment listed in the Prequalification Data, or for
alternative equipment proposed by the Applicant.
Item of equipment
Equipment
information
1. Name of manufacturer
2. Model and power rating
3. Capacity
4. Year of manufacture
Current
status
5. Current location
6. Details of current commitments
Source 7. Indicate source of the equipment
� Owned � Rented � Leased � Specially manufactured
Omit the following information for equipment owned by the Applicant or partner.
Owner 8. Name of owner
9. Address of owner
Telephone
Contact name and title
Fax
Telex
Agreements Details of rental / lease / manufacture agreements specific to the Project
PQD pt publicare in Dobrogea Area
page 39 of 70
APPLICATION FORM (7) PAGE OF PAGES
Financial Capability
Name of Applicant or partner of a joint venture
Applicants, including each partner of a joint venture, should provide financial information to
demonstrate that they meet the requirements stated in the Prequalification Data. Each applicant
or partner of a joint venture must complete this form. If necessary, use separate sheets to provide
complete banker information. A copy of the audited balance sheets should be attached.
Banker Name of banker
Address of banker
Telephone
Contact name and title
Fax
Telex
Summarise assets and liabilities in euro equivalent (at the National Bank of Romania rates of
exchange current at the end of each year) for the previous five years. Based upon known
commitments, summarise projected assets and liabilities in euro equivalent for the next two years,
unless the withholding of such information is justified by the Applicant to the satisfaction of the
Employer.
Financial
information in
euro equivalent
Actual:
previous five years
Projected:
next two years
1.
2. 3. 4. 5. 6. 7.
1. Total assets
2. Current
assets
3. Total
liabilities
4. Current
liabilities
5. Profits before
taxes
PQD pt publicare in Dobrogea Area
page 40 of 70
6. Profits after
taxes
Specify proposed sources of financing to meet the cash flow demands of the Project, net of current
commitments specified in the Prequalification Data.
Source of financing Amount (euro equivalent)
1.
2.
3.
4.
Use the National Bank of Romania exchange rate prevailing 21 days prior to the deadline for
submission of the present prequalification.
Attach audited financial statements for the last five years (for the individual Applicant or each
partner of a joint venture).
Firms owned by individuals, and partnerships, may submit their balance sheets certified by an
accountant, and supported by copies of tax returns, if audits are not required by the laws of their
countries of origin.
PQD pt publicare in Dobrogea Area
page 41 of 70
APPLICATION FORM (8) PAGE OF PAGES
Litigation History
Name of Applicant or partner of a joint venture
Applicants, including each of the partners of a joint venture, should provide information on any
history of litigation or arbitration resulting from contracts executed in the last five years or
currently under execution (refer to Prequalification Data). A separate sheet should be completed
for each partner of a joint venture.
Year Award FOR
or AGAINST
Applicant
Name of client, cause of litigation, and matter
in dispute
Disputed amount
(current value, euro
equivalent)
PQD pt publicare in Dobrogea Area
page 42 of 70
VOLUME II
The wider objective of this project is to complete maintenance and rehabilitation works on 7
bridges in Dobrogea area, in Romania. Generally speaking, the list of the rehabilitations works
refers to:
• Restoring to a former state and/or capacity
• Improving serviceability (structural and/or functional)
• Strengthening
The purpose of this Volume II is to provide general information which can help in knowing
bridges characteristics, in knowing each type of deterioration, the diagnosis of deterioration
executed on the structures by means of non-destructive and dynamics tests and in understanding
the designed solutions to rehabilitation.
The bridges and structures included in the projects present various static schemes and
configurations. The project includes:
• metallic truss bridges - bridge 7 at Cernavoda, bridge 8 at Borcea;
• precast concrete beam bridge - Bridge no. 10 over railway at Gaiseanca;
• arch bridges (bridge 4 in Poarta Alba, bridge 5 in Ovidiu and bridge 6 in
Basarabi),
• precast concrete beam bridge (bridge 9 in Mangalia);
The rehabilitation and maintenance works included in the Project mainly concern superstructure
and bridge deck, with only limited intervention on infrastructure.
The expected construction period for each Lot or any combination is of 24 months.
In the next paragraphs the main characteristics of all 3 bridges will be described.
Lot 4 – “Rehabilitation works for Bridge no. 07 at Cernavoda, on A2 km 157+600
and for Bridge no. 10 over the railway on DN 2B km 47+975 at Gaiseanca”
Bridge no. 07 at Cernavoda, on A2 km 157+600
This Bridge is located near Cernavoda on the A2 motorway (approximately at the km 158)
inserted in the European Transport Corridor IV section Fetesti-Cernavoda which connects the
Black Sea with Central Europe, over the Danube River. This bridge runs North-West to South-
East and is a 21 span structure, composed by two different parts: 3 main spans which are a
metallic truss bridge with a steel transversal section allowing the road and rail traffic and the
approach ramps composed by 18 spans of a double road carriageway also supported by a metallic
structure.
The main characteristics of this bridge are defined as follows:
PQD pt publicare in Dobrogea Area
page 43 of 70
• Structure typology: metallic truss bridge
• Overhead Length: 1596 m
• Overhead Width: 34.40 m
• Number of spans: 21(17+3+1)
• Greater span length: 166.90 m
Longitudinal section
Plan
Section
Bridge no. 10 over the railway on DN 2B km 47+975 at Gaiseanca
This bridge is located near Gaiseanca on the DN2B national road which connects Braila to Buzau
approximately at the km 47, over a railway. This bridge runs North-East to South-West and is a 3
span structure composed by pre-stressed concrete beams.
The main characteristics of this bridge are defined as follows:
• Structure typology: pre-stressed concrete.
• Overhead Length: 42 m
PQD pt publicare in Dobrogea Area
page 44 of 70
• Overhead Width: 10.70 m
• Number of spans: 3
• Greater span length: 18 m
Longitudinal section
Plan
Section
PQD pt publicare in Dobrogea Area
page 45 of 70
Lot 5 - Bridge no. 08 at Borcea, on A2 km 149+680
This Bridge is located near Fetesti on the A2 motorway (approximately at the km 150) inserted in
the European Transport Corridor IV section Fetesti-Cernavoda which connects the Black Sea with
Central Europe, over the Danube River. This bridge runs North-West to South-East and is a 14
span structure, composed by two different parts: 3 main spans which are a metallic truss bridge
with a steel transversal section allowing the road and rail traffic and the approach ramps
composed by 11 spans of a double road carriageway supported by pre-stressed concrete beams.
The main characteristics of this bridge are defined as follows:
• Structure typology: metallic truss bridge and pre-stressed concrete.
• Overhead Length: 968 m
• Overhead Width: 34.40 m
• Number of spans: 14 (3+3+8)
• Standard Concrete Span Length: 50 m
• Greater span length: 140.90 m
Longitudinal section
Plan
Section
PQD pt publicare in Dobrogea Area
page 46 of 70
Lot 6 -
“Rehabilitation works for Bridge no. 4 on DN 22C km 38+002 at Poarta Alba, for Bridge
no. 5 on DN 2A km 196+739 at Ovidiu, for Bridge no. 6 on DN 3 km 242+286 at Murfatlar
(Basarabi) and for Bridge no. 9 on DN 39 km 49+157 at Mangalia”
Bridge no. 4 on DN 22C km 38+002 at Poarta Alba
This bridge is located near Porta Alba on the DN22C national road which connects Cernavoda to
Constanta approximately at the km 38, over the Danube-Black Sea Channel. This bridge runs
North to South and is a 3 span structure, which the main span is an arch bridge composed by a
steel beams transversal section and the approach ramps are a simple pre-stressed concrete beams
bridge.
The main characteristics of this bridge are defined as follows:
• Structure typology: Arch bridge, steel - concrete
• Overhead Length: 170 m
• Overhead Width: 22.40 m
• Number of spans: 3
• Greater span length: 111 m
Longitudinal section
PQD pt publicare in Dobrogea Area
page 47 of 70
Plan
Section
Bridge no. 5 on DN 2A km 196+739 at Ovidiu
This bridge is located near Ovidiu on the DN2A national road which connects Harsova to
Constanta approximately at the km 196, over the Danube-Black Sea Channel. This bridge runs
North to South and is a 6 span structure, which the main span is an arch bridge composed by a
PQD pt publicare in Dobrogea Area
page 48 of 70
steel beams transversal section and the approach ramps are a small continuous span bridge
composed by pre-stressed concrete beams.
The main characteristics of this bridge are defined as follows:
• Structure typology: Arch bridge, steel - concrete
• Overhead Length: 261 m
• Overhead Width: 22.30 m
• Number of spans: 6(2+1+3)
• Standard Concrete Span Length: 30 m
• Greater span length: 111 m
Longitudinal section
Plan
Section
PQD pt publicare in Dobrogea Area
page 49 of 70
Bridge no. 6 on DN 3 km 242+286 at Murfatlar (Basarabi)
This bridge is located near Basarabi on the DN3 national road which connects Bucharest to
Constanta approximately at the km 242, over the Danube-Black Sea Channel.. This bridge runs
North-East to South-West and is a 5 span structure, which the main span is an arch bridge
composed by a steel beams transversal section and the approach ramps are a small continuous
span bridge composed by pre-stressed concrete beams.
The main characteristics of this bridge are defined as follows:
• Structure typology: Arch bridge, steel - concrete and pre-stressed concrete for side spans
• Overhead Length: 226 m
• Overhead Width: 14.20 m
• Number of spans: 5 (2+1+2)
• Standard Concrete Span Length: 30 m
• Greater span length: 104.5 m
Longitudinal section
PQD pt publicare in Dobrogea Area
page 50 of 70
Plan
Section
Bridge no. 9 on DN 39 km 49+157 at Mangalia
This Bridge is located in Mangalia on the DN39 national road which connects Constanta to
Mangalia and runs North-West to South-East approximately at the km 49. This bridge is a 8 span
structure divided as follows: 3 steel spans and 5 pre-stressed concrete spans.
The main characteristics of this bridge are defined as follows:
• Structure typology: steel - concrete and pre-stressed concrete beam bridge
• Overhead Length: 434 m
• Overhead Width: 19.30 m
• Number of spans: 8
• Greater span length: 95.20 m
PQD pt publicare in Dobrogea Area
page 51 of 70
Longitudinal section
Plan
Section
All different types of deterioration were organized by groups, according to the related location:
Work Type Defects Possible causes
-Coating degradation or corroded parapet
-Heavy local corrosion or damaged parapet
- Chemical or electrochemical
reaction between metal and its
environment
- Inadequate or damaged guard rail - Steel corrosion or vehicle impact
- Inadequate or damaged electrical equipment
Road finishes and equipment
- Lack of steel plates in walkway
- Lack of maintenance
- Holes or damaged pavements - Heavy traffic and/or lack of
maintenance
- Damaged or degradation drainpipes
- Deteriorated walkway pavement
- Lack of maintenance
PQD pt publicare in Dobrogea Area
page 52 of 70
- Damaged expansion joints Pavements
- Damaged bearings
- Lack of maintenance and fatigue
- Efflorescence and spalling on deck slab and
honeycomb in transverses
- Percolation of water and
inadequate aggregate grading
and/or poor compaction
- Cracking and spalling of concrete beam
- Corrosion and spalling of pier caps
- Spalling of cover over shear reinforcement
- Carbonation and/or Chlorides
- Lack of strengthening or damaged concrete
elements
- Inadequate design, poor concrete
or damaged prestressed bars
Concrete Repair
- Inadequate Superstructure - Frequent longitudinal cracks on
pre-stressed concrete beams due
to insufficient load resistance
-Coating degradation or corroded steel
structures
- Chemical or electrochemical
reaction between metal and its
environment
- Lack of stay cables maintenance
-Missing bolts
- Lack of maintenance
Steel Works
- Damaged and corrosion of inspection gantry
and rails
Chemical or electrochemical
reaction between metal and its
environment
- Cracking and disconnection of stoneworks - Water Action
- Subsidence of embankment behind abutment - Soil consolidation behind
abutment
-Landslip of cone quarters
- Damaged storm water collecting system
- Lack of maintenance
Earthworks
- Deteriorated river embankment - Erosion
Bridge 7 - Lack of metallic slabs
PQD pt publicare in Dobrogea Area
page 53 of 70
Bridge 8 - Damaged drainpipe, inadequate guard rail height, walkway slab breakdown and damaged pavement
Bridge 10 - Lack of cover on prestressed beams
PQD pt publicare in Dobrogea Area
page 54 of 70
Bridge 8 - Cracking on prestressed concrete beam due to water percolation inside socket
Bridge 7 - Corrosion on steel deck girders
PQD pt publicare in Dobrogea Area
page 55 of 70
Bridge 8 – Missing and no strengthening anchor bolts
Bridge 5 - Efflorescence and degradation of concrete around drainpipe on deck slab underside
PQD pt publicare in Dobrogea Area
page 56 of 70
Bridge 4 - Underside view of approach span – note honeycomb in transverse beam
Bridge 9 - Pier damaged maybe by gun shots
PQD pt publicare in Dobrogea Area
page 57 of 70
Bridge 7 - Corrosion on steel deck girders
Bridge 5 - Corrosion and deterioration on coating of tension steel structure
PQD pt publicare in Dobrogea Area
page 58 of 70
Bridge 6 - Coating degradation on main arcs steel
Bridge 9 - Detail of gantry – note coating breakdown
PQD pt publicare in Dobrogea Area
page 60 of 70
All intervention works were organized by groups, in accordance with the related location and type
of deterioration, as it is exposed in the following table, where designed interventions executed on
each bridge can be seen:
Bridge no. 07 at Cernavoda, on A2 km 157+600
Item Description
A Road finishes & equipment
A1
Painting of pedestrian parapet
This item requires the painting of steel pedestrian parapet, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
A3
Guard rail replacement
It needs to dismantle existing guard rail and assembling the new one with the following
operations:
- removal of the guard rail connection screws;
- cutting with oxyacetylene flame of the posts;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of the guard rail elements
and other related materials and equipment;
- local transport and handling of the guard rail elements;
- assembling of the guard rail elements;
- supply and installation of the reflective elements;
- rust protective paint;
- final paint in two layers;
- verifications after execution in accordance to the design;
- sampling and laboratory testing;
- Steel plates embedded in the reinforced concrete support beams are included.
A4
Electrical equipment replacement
It needs to dismantle existing electrical equipment and assembling the new one
PQD pt publicare in Dobrogea Area
page 61 of 70
according to the following activities:
- dismantling of the existing electrical equipment;
- loading and transport of the material resulting from the demolition to an
approved dump area;
- procurement, transport, storage and handling of the new electrical
elements and other related materials and equipment;
- assembling and installation of the new electrical elements;
- verifications after execution in accordance to the design;
- sampling and laboratory testing.
A5
Walkway slab substitution
This item refers to restoring the missing lids and to provide for lack of steel plates on the
walkways. Particularly it is sometimes required to dismantle existing walkway slab
around damaged zone, and assembling the new steel slab.
The item covers the following activities:
- dismantling of the existing walkway slab;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of all related materials and equipment;
- laying the walkway slabs;
- verifications after execution in accordance to the design;
B Pavements
B1
Roadway pavement and waterproofing replacement (on concrete deck and on metallic
deck)
The bridge pavement execution covers the following activities:
- scarifying and removing the existing bituminous surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
PQD pt publicare in Dobrogea Area
page 62 of 70
elastic materials;
- laying 40 mm thick protective course including surface preparation applying primer
coat with bitumen emulsion
- laying 40 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
B2
Roadway superficial drainage rehabilitation
The item covers the substitution of the existent drain pipes and grids:
- removal of the existing damaged drain pipes and/or related grids;
- loading and transport of the removal material to an approved dump area;
- procurement, transport, storage and handling of necessary materials and
equipment;
- installation of the new drain pipes and/or related grids;
- finishing works to ensure waterproofing;
- verifications after execution in accordance to the design.
B3
Walkway pavement replacement
The item covers the following activities:
- scarifying and removing the existing surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 20 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
B4
Expansion joints replacement
The item covers the following activities:
PQD pt publicare in Dobrogea Area
page 63 of 70
- dismantling the existing damaged joints;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- new expansion joints assembling and fitting, as per technical specifications
- verifications after execution in accordance to the design;
C
Concrete repair
For each of the following chapters about concrete repair (C1, C4) the following
activities will be covered:
- Sounding of concrete to locate areas of delamination;
- preparation and cleaning of surface by means of sand blasting and water washing
and/or concrete removal by means of hydrodemolition;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of all related materials and equipment;
- epoxy and polyurethane compounds application;
- application of a corrosion inhibitor and a cementitious mortar where concrete is
removed;
- verifications after execution in accordance to the design;
These interventions can be divided in 2 different work sequences in accordance with the
type and location of the deterioration. Therefore, when efflorescence, low corrosion and
spalling are founded, the following work steps may be implemented:
1 - Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 - Concrete sand blast cleaning to prepare the surface for receiving protective materials;
3 - Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 - Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
5 - Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar.
PQD pt publicare in Dobrogea Area
page 64 of 70
Differently, when the concrete surface present honeycomb and high corrosion and
spalling, the following work steps may be implemented:
1 - Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 - Hydrodemolition of damaged concrete with 30000 psi of pressure and concrete
removal of 4 cm, being attention with reinforcing steel;
3 - Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 - Application of a modified polymer cementitious monocompound corrosion inhibitor
like EMACO NANOCONCRETE AP from BASF or similar;
5 - Application of a thixotropic cementitious mortar with restrained expansion, fiber-
reinforced with flexible inorganic fibres, like EMACO FORMULA TIXOFIBER from
BASF or similar;
6 - Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
7 - Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar;
C1 Deck slab repair
C4 Piers concrete repair
D Steel works
D1
Overcoating of steel structures
This item requires the painting of steel structures, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
D4
Rehabilitation of inspection gantry and rails
This item requires the painting of the inspection gantry and rails, and so the following
operations became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
PQD pt publicare in Dobrogea Area
page 65 of 70
Bridge no. 10 over the railway on DN 2B km 47+975 at Gaiseanca
Item Description
A Road finishes & equipment
A2
Replacement of pedestrian parapet
It is necessary to dismantle the existing parapet and assemble the new one with the
following operations:
- removal of the parapet connection screws;
- cutting with oxyacetylene flame of the posts;
- loading and transport of the material resulting from the demolition to an approved dump
area;
- procurement, transport, storage and handling of the pedestrian parapet elements and other
related materials and equipment;
- local transport and handling of the parapet panels;
- assembling and installation of the parapet panels;
- rust protective coat painting;
- parapet painting in two layers using airless spray;
- verifications after execution in accordance to the design;
- sampling and laboratory testing;
Steel plates embedded in the reinforced concrete support beams are included.
A3
Guard rail replacement
It needs to dismantle existing guard rail and assembling the new one with the following
operations:
- removal of the guard rail connection screws;
- cutting with oxyacetylene flame of the posts;
- loading and transport of the material resulting from the demolition to an approved dump
area;
- procurement, transport, storage and handling of the guard rail elements
and other related materials and equipment;
- local transport and handling of the guard rail elements;
- assembling of the guard rail elements;
- supply and installation of the reflective elements;
PQD pt publicare in Dobrogea Area
page 66 of 70
- rust protective paint;
- final paint in two layers;
- verifications after execution in accordance to the design;
- sampling and laboratory testing;
- Steel plates embedded in the reinforced concrete support beams are included.
B Pavements
B1
Roadway pavement and waterproofing replacement (on concrete deck and on metallic deck)
The bridge pavement execution covers the following activities:
- scarifying and removing the existing bituminous surface;
- loading and transport of the material resulting from the demolition to an approved dump
area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 40 mm thick protective course including surface preparation applying primer coat
with bitumen emulsion
- laying 40 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
B2
Roadway superficial drainage rehabilitation
The item covers the substitution of the existent drain pipes and grids:
- removal of the existing damaged drain pipes and/or related grids;
- loading and transport of the removal material to an approved dump area;
- procurement, transport, storage and handling of necessary materials and
equipment;
- installation of the new drain pipes and/or related grids;
- finishing works to ensure waterproofing;
- verifications after execution in accordance to the design.
B3 Walkway pavement replacement
PQD pt publicare in Dobrogea Area
page 67 of 70
The item covers the following activities:
- scarifying and removing the existing surface;
- loading and transport of the material resulting from the demolition to an approved dump
area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 20 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
C
Concrete repair
For each of the following chapters about concrete repair (C1, C2, C3, C4) the following
activities will be covered:
- Sounding of concrete to locate areas of delamination;
- preparation and cleaning of surface by means of sand blasting and water washing and/or
concrete removal by means of hydrodemolition;
- loading and transport of the material resulting from the demolition to an approved dump
area;
- procurement, transport, storage and handling of all related materials and equipment;
- epoxy and polyurethane compounds application;
- application of a corrosion inhibitor and a cementitious mortar where concrete is removed;
- verifications after execution in accordance to the design;
These interventions can be divided in 2 different work sequences in accordance with the
type and location of the deterioration. Therefore, when efflorescence, low corrosion and
spalling are founded, the following work steps may be implemented:
1 – Sounding of concrete to locate areas of deterioration (spalling, honeycomb, corrosion);
PQD pt publicare in Dobrogea Area
page 68 of 70
2 – Concrete sand blast cleaning to prepare the surface for receiving protective materials;
3 – Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 – Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
5 – Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar.
Differently, when the concrete surface present honeycomb and high corrosion and spalling,
the following work steps may be implemented:
1 – Sounding of concrete to locate areas of deterioration (spalling, honeycomb, corrosion);
2 – Hydrodemolition of damaged concrete with 30000 psi of pressure and concrete removal
of 4 cm, being attention with reinforcing steel;
3 – Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 – Application of a modified polymer cementitious monocompound corrosion inhibitor
like EMACO NANOCONCRETE AP from BASF or similar;
5 – Application of a thixotropic cementitious mortar with restrained expansion, fiber-
reinforced with flexible inorganic fibres, like EMACO FORMULA TIXOFIBER from
BASF or similar;
6 – Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
7 – Application of a polyurethane resin protective coat like MASTERSEAL FORMULA PU
from BASF or similar;
C1 Deck slab repair
C2 Prestressed concrete beams repair
C3 Pier caps concrete repair
C4 Piers concrete repair
E Earthworks
E2
Repair of structure connection with embankment
Is required to fill embankment behind abutment up, with lean concrete.
The item covers the following activities:
- procurement, transport, storage and handling of necessary materials and equipment;
- excavation of soil in borrow pit or in an intermediary storage;
- loading and transport of the soil resulted from excavations to the approved storage
PQD pt publicare in Dobrogea Area
page 69 of 70
yards;
- filling with lean concrete;
- checking of the filling quality after compaction.
- verifications after execution in accordance to the design.
5.000.30
lean concrete
pavement
Intervention E2 scheme
E3
Cone quarters rehabilitation
Cone quarters rehabilitation by the same original materials, including land cleaning of bushes
and shrubs, excavation, filling with suitable fill material or natural aggregates stabilized with
cement.
The item covers the following activities:
- land cleaning of bushes and shrubs;
- procurement, transport, storage and handling of necessary materials and equipment;
- excavation of soil in borrow pit or in an intermediary storage;
- loading and transport of the soil resulted from excavations to the approved storage yards;
- spreading of soil in 10 cm layers and compaction;
- finishing works, check of the achieved surfaces in respect to the design;
- checking of the filling quality after compaction.
E4
Rehabilitation of storm water collecting system
The item covers the following activities:
- procurement, transport and handling of the necessary materials;
- soil excavation;
- ballast layer, including material, transport spreading and compaction;
- concrete preparation, transport and casting;
- execution of the storm water collecting system foundation;
PQD pt publicare in Dobrogea Area
page 70 of 70
- precast elements assembling;
- mortar preparation, transport and handling;
- filling the prefabricates joints;
- verifications after execution in accordance to the design.
Bridge no. 08 at Borcea, on A2 km 149+680
Item Description
A Road finishes & equipment
A1
Painting of pedestrian parapet
This item requires the painting of steel pedestrian parapet, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
A3
Guard rail replacement
It needs to dismantle existing guard rail and assembling the new one with the following
operations:
- removal of the guard rail connection screws;
- cutting with oxyacetylene flame of the posts;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of the guard rail elements
and other related materials and equipment;
- local transport and handling of the guard rail elements;
- assembling of the guard rail elements;
- supply and installation of the reflective elements;
- rust protective paint;
- final paint in two layers;
- verifications after execution in accordance to the design;
- sampling and laboratory testing;
- Steel plates embedded in the reinforced concrete support beams are included.
PQD pt publicare in Dobrogea Area
page 71 of 70
A4
Electrical equipment replacement
It needs to dismantle existing electrical equipment and assembling the new one
according to the following activities:
- dismantling of the existing electrical equipment;
- loading and transport of the material resulting from the demolition to an
approved dump area;
- procurement, transport, storage and handling of the new electrical
elements and other related materials and equipment;
- assembling and installation of the new electrical elements;
- verifications after execution in accordance to the design;
- sampling and laboratory testing.
A5
Walkway slab substitution
This item refers to restoring the missing lids and to provide for lack of steel plates on the
walkways. Particularly it is sometimes required to dismantle existing walkway slab
around damaged zone, and assembling the new steel slab.
The item covers the following activities:
- dismantling of the existing walkway slab;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of all related materials and equipment;
- laying the walkway slabs;
- verifications after execution in accordance to the design;
B Pavements
B1
Roadway pavement and waterproofing replacement (on concrete deck and on metallic
deck)
The bridge pavement execution covers the following activities:
- scarifying and removing the existing bituminous surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
PQD pt publicare in Dobrogea Area
page 72 of 70
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 40 mm thick protective course including surface preparation applying primer
coat with bitumen emulsion
- laying 40 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
B2
Roadway superficial drainage rehabilitation
The item covers the substitution of the existent drain pipes and grids:
- removal of the existing damaged drain pipes and/or related grids;
- loading and transport of the removal material to an approved dump area;
- procurement, transport, storage and handling of necessary materials and
equipment;
- installation of the new drain pipes and/or related grids;
- finishing works to ensure waterproofing;
- verifications after execution in accordance to the design.
B3
Walkway pavement replacement
The item covers the following activities:
- scarifying and removing the existing surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 20 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
B4 Expansion joints replacement
PQD pt publicare in Dobrogea Area
page 73 of 70
The item covers the following activities:
- dismantling the existing damaged joints;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- new expansion joints assembling and fitting, as per technical specifications
- verifications after execution in accordance to the design;
C
Concrete repair
For each of the following chapters about concrete repair (C1, C2, C3, C4) the following
activities will be covered:
- Sounding of concrete to locate areas of delamination;
- preparation and cleaning of surface by means of sand blasting and water washing
and/or concrete removal by means of hydrodemolition;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of all related materials and equipment;
- epoxy and polyurethane compounds application;
- application of a corrosion inhibitor and a cementitious mortar where concrete is
removed;
- verifications after execution in accordance to the design;
These interventions can be divided in 2 different work sequences in accordance with the
type and location of the deterioration. Therefore, when efflorescence, low corrosion and
spalling are founded, the following work steps may be implemented:
1 - Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 - Concrete sand blast cleaning to prepare the surface for receiving protective materials;
3 - Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 - Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
5 - Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PQD pt publicare in Dobrogea Area
page 74 of 70
PU from BASF or similar.
Differently, when the concrete surface present honeycomb and high corrosion and
spalling, the following work steps may be implemented:
1 - Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 - Hydrodemolition of damaged concrete with 30000 psi of pressure and concrete
removal of 4 cm, being attention with reinforcing steel;
3 - Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 - Application of a modified polymer cementitious monocompound corrosion inhibitor
like EMACO NANOCONCRETE AP from BASF or similar;
5 - Application of a thixotropic cementitious mortar with restrained expansion, fiber-
reinforced with flexible inorganic fibres, like EMACO FORMULA TIXOFIBER from
BASF or similar;
6 - Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
7 - Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar;
C1 Deck slab repair
C2 Prestressed concrete beams repair
C3 Pier caps concrete repair
C4 Piers concrete repair
C6
Structural Strengthening
This intervention considers the application of CFRP laminates and transverse straps on
prestressed concrete beams.
The item covers the following activities:
- procurement, transport, storage and handling of all related materials and equipment;
- application of a bicompound epoxy primer
- application of coats of epoxy adhesive for bonding new concrete with CFRP
laminates and transverse straps;
- application of CFRP laminates;
- application of CFRP straps;
- verifications after execution in accordance to the design;
E Earthworks
PQD pt publicare in Dobrogea Area
page 75 of 70
E2
Repair of structure connection with embankment
Is required to fill embankment behind abutment up, with lean concrete.
The item covers the following activities:
- procurement, transport, storage and handling of necessary materials and equipment;
- excavation of soil in borrow pit or in an intermediary storage;
- loading and transport of the soil resulted from excavations to the approved storage yards;
- filling with lean concrete;
- checking of the filling quality after compaction.
- verifications after execution in accordance to the design.
5.00
0.30
lean concrete
pavement
Intervention E2 scheme
E3
Cone quarters rehabilitation
Cone quarters rehabilitation by the same original materials, including land cleaning of
bushes and shrubs, excavation, filling with suitable fill material or natural aggregates
stabilized with cement.
The item covers the following activities:
- land cleaning of bushes and shrubs;
- procurement, transport, storage and handling of necessary materials and equipment;
- excavation of soil in borrow pit or in an intermediary storage;
- loading and transport of the soil resulted from excavations to the approved storage
yards;
- spreading of soil in 10 cm layers and compaction;
- finishing works, check of the achieved surfaces in respect to the design;
- checking of the filling quality after compaction.
E4
Rehabilitation of storm water collecting system
The item covers the following activities:
- procurement, transport and handling of the necessary materials;
- soil excavation;
- ballast layer, including material, transport spreading and compaction;
- concrete preparation, transport and casting;
PQD pt publicare in Dobrogea Area
page 76 of 70
- execution of the storm water collecting system foundation;
- precast elements assembling;
- mortar preparation, transport and handling;
- filling the prefabricates joints;
- verifications after execution in accordance to the design.
Bridge no. 4 on DN 22C km 38+002 at Poarta Alba,
Item Description
A Road finishes & equipment
A1
Painting of pedestrian parapet
This item requires the painting of steel pedestrian parapet, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
A3
Guard rail replacement
It needs to dismantle existing guard rail and assembling the new one with the following
operations:
- removal of the guard rail connection screws;
- cutting with oxyacetylene flame of the posts;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of the guard rail elements
and other related materials and equipment;
- local transport and handling of the guard rail elements;
- assembling of the guard rail elements;
- supply and installation of the reflective elements;
- rust protective paint;
- final paint in two layers;
- verifications after execution in accordance to the design;
- sampling and laboratory testing;
- Steel plates embedded in the reinforced concrete support beams are included.
A4 Electrical equipment replacement
PQD pt publicare in Dobrogea Area
page 77 of 70
It needs to dismantle existing electrical equipment and assembling the new one
according to the following activities:
- dismantling of the existing electrical equipment;
- loading and transport of the material resulting from the demolition to an
approved dump area;
- procurement, transport, storage and handling of the new electrical
elements and other related materials and equipment;
- assembling and installation of the new electrical elements;
- verifications after execution in accordance to the design;
- sampling and laboratory testing.
B Pavements
B1
Roadway pavement and waterproofing replacement (on concrete deck and on metallic
deck)
The bridge pavement execution covers the following activities:
- scarifying and removing the existing bituminous surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 40 mm thick protective course including surface preparation applying primer
coat with bitumen emulsion
- laying 40 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
B2
Roadway superficial drainage rehabilitation
The item covers the substitution of the existent drain pipes and grids:
- removal of the existing damaged drain pipes and/or related grids;
- loading and transport of the removal material to an approved dump area;
PQD pt publicare in Dobrogea Area
page 78 of 70
- procurement, transport, storage and handling of necessary materials and
equipment;
- installation of the new drain pipes and/or related grids;
- finishing works to ensure waterproofing;
- verifications after execution in accordance to the design.
B3
Walkway pavement replacement
The item covers the following activities:
- scarifying and removing the existing surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 20 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
B4
Expansion joints replacement
The item covers the following activities:
- dismantling the existing damaged joints;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- new expansion joints assembling and fitting, as per technical specifications
- verifications after execution in accordance to the design;
C
Concrete repair
For each of the following chapters about concrete repair (C1, C4) the following
activities will be covered:
PQD pt publicare in Dobrogea Area
page 79 of 70
- Sounding of concrete to locate areas of delamination;
- preparation and cleaning of surface by means of sand blasting and water washing
and/or concrete removal by means of hydrodemolition;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of all related materials and equipment;
- epoxy and polyurethane compounds application;
- application of a corrosion inhibitor and a cementitious mortar where concrete is
removed;
- verifications after execution in accordance to the design;
These interventions can be divided in 2 different work sequences in accordance with the
type and location of the deterioration. Therefore, when efflorescence, low corrosion and
spalling are founded, the following work steps may be implemented:
1 - Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 - Concrete sand blast cleaning to prepare the surface for receiving protective materials;
3 - Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 - Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
5 - Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar.
Differently, when the concrete surface present honeycomb and high corrosion and
spalling, the following work steps may be implemented:
1 - Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 - Hydrodemolition of damaged concrete with 30000 psi of pressure and concrete
removal of 4 cm, being attention with reinforcing steel;
3 - Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 - Application of a modified polymer cementitious monocompound corrosion inhibitor
like EMACO NANOCONCRETE AP from BASF or similar;
PQD pt publicare in Dobrogea Area
page 80 of 70
5 - Application of a thixotropic cementitious mortar with restrained expansion, fiber-
reinforced with flexible inorganic fibres, like EMACO FORMULA TIXOFIBER from
BASF or similar;
6 - Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
7 - Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar;
C1 Deck slab repair
C4 Piers concrete repair
D Steel works
D1
Overcoating of steel structures
This item requires the painting of steel structures, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
D4
Rehabilitation of inspection gantry and rails
This item requires the painting of the inspection gantry and rails, and so the following
operations became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
E Earthworks
E4
Rehabilitation of storm water collecting system
The item covers the following activities:
- procurement, transport and handling of the necessary materials;
- soil excavation;
- ballast layer, including material, transport spreading and compaction;
- concrete preparation, transport and casting;
- execution of the storm water collecting system foundation;
- precast elements assembling;
- mortar preparation, transport and handling;
- filling the prefabricates joints;
- verifications after execution in accordance to the design.
E5 River bank improvement
PQD pt publicare in Dobrogea Area
page 81 of 70
This item covers the following activities:
- procurement, transport, storage and handling of necessary materials and equipment;
- land cleaning of bushes and shrubs;
- soil leveling;
- loading and transport of the discard materials to the approved storage yards;
- placement of rocks as protection of basement in artificial cuts made to profile the river
banks;
- laying of river gabion mattresses made of hexagonal double twisted wire mesh filled
with stones. The woven steel wire used to manufacture the mattress is heavily zinc-
coated soft temper steel;
- casting of lean concrete layer;
- finishing works, check after execution in accordance to the design.
Bridge no. 5 on DN 2A km 196+739 at Ovidiu
Item Description
A Road finishes & equipment
A1
Painting of pedestrian parapet
This item requires the painting of steel pedestrian parapet, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
A3
Guard rail replacement
It needs to dismantle existing guard rail and assembling the new one with the following
operations:
- removal of the guard rail connection screws;
- cutting with oxyacetylene flame of the posts;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of the guard rail elements
and other related materials and equipment;
PQD pt publicare in Dobrogea Area
page 82 of 70
- local transport and handling of the guard rail elements;
- assembling of the guard rail elements;
- supply and installation of the reflective elements;
- rust protective paint;
- final paint in two layers;
- verifications after execution in accordance to the design;
- sampling and laboratory testing;
- Steel plates embedded in the reinforced concrete support beams are included.
A4
Electrical equipment replacement
It needs to dismantle existing electrical equipment and assembling the new one
according to the following activities:
- dismantling of the existing electrical equipment;
- loading and transport of the material resulting from the demolition to an
approved dump area;
- procurement, transport, storage and handling of the new electrical
elements and other related materials and equipment;
- assembling and installation of the new electrical elements;
- verifications after execution in accordance to the design;
- sampling and laboratory testing.
B Pavements
B1
Roadway pavement and waterproofing replacement (on concrete deck and on metallic
deck)
The bridge pavement execution covers the following activities:
- scarifying and removing the existing bituminous surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
PQD pt publicare in Dobrogea Area
page 83 of 70
- laying 40 mm thick protective course including surface preparation applying primer
coat with bitumen emulsion
- laying 40 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
B2
Roadway superficial drainage rehabilitation
The item covers the substitution of the existent drain pipes and grids:
- removal of the existing damaged drain pipes and/or related grids;
- loading and transport of the removal material to an approved dump area;
- procurement, transport, storage and handling of necessary materials and
equipment;
- installation of the new drain pipes and/or related grids;
- finishing works to ensure waterproofing;
- verifications after execution in accordance to the design.
B3
Walkway pavement replacement
The item covers the following activities:
- scarifying and removing the existing surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 20 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
B4
Expansion joints replacement
The item covers the following activities:
- dismantling the existing damaged joints;
PQD pt publicare in Dobrogea Area
page 84 of 70
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- new expansion joints assembling and fitting, as per technical specifications
- verifications after execution in accordance to the design;
C
Concrete repair
For each of the following chapters about concrete repair (C1, C4) the following
activities will be covered:
- Sounding of concrete to locate areas of delamination;
- preparation and cleaning of surface by means of sand blasting and water washing
and/or concrete removal by means of hydrodemolition;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of all related materials and equipment;
- epoxy and polyurethane compounds application;
- application of a corrosion inhibitor and a cementitious mortar where concrete is
removed;
- verifications after execution in accordance to the design;
These interventions can be divided in 2 different work sequences in accordance with the
type and location of the deterioration. Therefore, when efflorescence, low corrosion and
spalling are founded, the following work steps may be implemented:
1 - Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 - Concrete sand blast cleaning to prepare the surface for receiving protective materials;
3 - Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 - Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
5 - Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar.
Differently, when the concrete surface present honeycomb and high corrosion and
PQD pt publicare in Dobrogea Area
page 85 of 70
spalling, the following work steps may be implemented:
1 - Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 - Hydrodemolition of damaged concrete with 30000 psi of pressure and concrete
removal of 4 cm, being attention with reinforcing steel;
3 - Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 - Application of a modified polymer cementitious monocompound corrosion inhibitor
like EMACO NANOCONCRETE AP from BASF or similar;
5 - Application of a thixotropic cementitious mortar with restrained expansion, fiber-
reinforced with flexible inorganic fibres, like EMACO FORMULA TIXOFIBER from
BASF or similar;
6 - Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
7 - Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar;
C1 Deck slab repair
C4 Piers concrete repair
D Steel works
D1
Overcoating of steel structures
This item requires the painting of steel structures, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
D4
Rehabilitation of inspection gantry and rails
This item requires the painting of the inspection gantry and rails, and so the following
operations became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
E Earthworks
PQD pt publicare in Dobrogea Area
page 86 of 70
E4
Rehabilitation of storm water collecting system
The item covers the following activities:
- procurement, transport and handling of the necessary materials;
- soil excavation;
- ballast layer, including material, transport spreading and compaction;
- concrete preparation, transport and casting;
- execution of the storm water collecting system foundation;
- precast elements assembling;
- mortar preparation, transport and handling;
- filling the prefabricates joints;
- verifications after execution in accordance to the design.
Bridge no. 6 on DN 3 km 242+286 at Murfatlar (Basarabi)
Item Description
A Road finishes & equipment
A1
Painting of pedestrian parapet
This item requires the painting of steel pedestrian parapet, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
A3
Guard rail replacement
It needs to dismantle existing guard rail and assembling the new one with the following
operations:
- removal of the guard rail connection screws;
- cutting with oxyacetylene flame of the posts;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of the guard rail elements
and other related materials and equipment;
- local transport and handling of the guard rail elements;
- assembling of the guard rail elements;
- supply and installation of the reflective elements;
PQD pt publicare in Dobrogea Area
page 87 of 70
- rust protective paint;
- final paint in two layers;
- verifications after execution in accordance to the design;
- sampling and laboratory testing;
- Steel plates embedded in the reinforced concrete support beams are included.
A4
Electrical equipment replacement
It needs to dismantle existing electrical equipment and assembling the new one
according to the following activities:
- dismantling of the existing electrical equipment;
- loading and transport of the material resulting from the demolition to an
approved dump area;
- procurement, transport, storage and handling of the new electrical
elements and other related materials and equipment;
- assembling and installation of the new electrical elements;
- verifications after execution in accordance to the design;
- sampling and laboratory testing.
B Pavements
B1
Roadway pavement and waterproofing replacement (on concrete deck and on metallic
deck)
The bridge pavement execution covers the following activities:
- scarifying and removing the existing bituminous surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 40 mm thick protective course including surface preparation applying primer
coat with bitumen emulsion
- laying 40 mm thick wearing course including surface preparation applying primer coat
PQD pt publicare in Dobrogea Area
page 88 of 70
with bitumen emulsion
- verifications after execution in accordance to the design;
B2
Roadway superficial drainage rehabilitation
The item covers the substitution of the existent drain pipes and grids:
- removal of the existing damaged drain pipes and/or related grids;
- loading and transport of the removal material to an approved dump area;
- procurement, transport, storage and handling of necessary materials and
equipment;
- installation of the new drain pipes and/or related grids;
- finishing works to ensure waterproofing;
- verifications after execution in accordance to the design.
B3
Walkway pavement replacement
The item covers the following activities:
- scarifying and removing the existing surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 20 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
B4
Expansion joints replacement
The item covers the following activities:
- dismantling the existing damaged joints;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
PQD pt publicare in Dobrogea Area
page 89 of 70
- procurement, transport, storage and handling of all related materials and equipment;
- new expansion joints assembling and fitting, as per technical specifications
- verifications after execution in accordance to the design;
C
Concrete repair
For each of the following chapters about concrete repair (C1) the following activities
will be covered:
- Sounding of concrete to locate areas of delamination;
- preparation and cleaning of surface by means of sand blasting and water washing
and/or concrete removal by means of hydrodemolition;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of all related materials and equipment;
- epoxy and polyurethane compounds application;
- application of a corrosion inhibitor and a cementitious mortar where concrete is
removed;
- verifications after execution in accordance to the design;
These interventions can be divided in 2 different work sequences in accordance with the
type and location of the deterioration. Therefore, when efflorescence, low corrosion and
spalling are founded, the following work steps may be implemented:
1 - Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 - Concrete sand blast cleaning to prepare the surface for receiving protective materials;
3 - Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 - Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
5 - Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar.
Differently, when the concrete surface present honeycomb and high corrosion and
spalling, the following work steps may be implemented:
1 - Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
PQD pt publicare in Dobrogea Area
page 90 of 70
2 - Hydrodemolition of damaged concrete with 30000 psi of pressure and concrete
removal of 4 cm, being attention with reinforcing steel;
3 - Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 - Application of a modified polymer cementitious monocompound corrosion inhibitor
like EMACO NANOCONCRETE AP from BASF or similar;
5 - Application of a thixotropic cementitious mortar with restrained expansion, fiber-
reinforced with flexible inorganic fibres, like EMACO FORMULA TIXOFIBER from
BASF or similar;
6 - Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
7 - Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar;
C1 Deck slab repair
D Steel works
D1
Overcoating of steel structures
This item requires the painting of steel structures, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
D4
Rehabilitation of inspection gantry and rails
This item requires the painting of the inspection gantry and rails, and so the following
operations became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
E Earthworks
E4
Rehabilitation of storm water collecting system
The item covers the following activities:
- procurement, transport and handling of the necessary materials;
- soil excavation;
- ballast layer, including material, transport spreading and compaction;
PQD pt publicare in Dobrogea Area
page 91 of 70
- concrete preparation, transport and casting;
- execution of the storm water collecting system foundation;
- precast elements assembling;
- mortar preparation, transport and handling;
- filling the prefabricates joints;
- verifications after execution in accordance to the design.
E5
River bank improvement
This item covers the following activities:
- procurement, transport, storage and handling of necessary materials and equipment;
- land cleaning of bushes and shrubs;
- soil leveling;
- loading and transport of the discard materials to the approved storage yards;
- placement of rocks as protection of basement in artificial cuts made to profile the river
banks;
- laying of river gabion mattresses made of hexagonal double twisted wire mesh filled
with stones. The woven steel wire used to manufacture the mattress is heavily zinc-
coated soft temper steel;
- casting of lean concrete layer;
- finishing works, check after execution in accordance to the design.
Bridge no. 9 on DN 39 km 49+157 at Mangalia
Item Description
A Road finishes & equipment
A1
Painting of pedestrian parapet
This item requires the painting of steel pedestrian parapet, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
A3
Guard rail replacement
It needs to dismantle existing guard rail and assembling the new one with the following
operations:
- removal of the guard rail connection screws;
PQD pt publicare in Dobrogea Area
page 92 of 70
- cutting with oxyacetylene flame of the posts;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of the guard rail elements
and other related materials and equipment;
- local transport and handling of the guard rail elements;
- assembling of the guard rail elements;
- supply and installation of the reflective elements;
- rust protective paint;
- final paint in two layers;
- verifications after execution in accordance to the design;
- sampling and laboratory testing;
- Steel plates embedded in the reinforced concrete support beams are included.
A4
Electrical equipment replacement
It needs to dismantle existing electrical equipment and assembling the new one
according to the following activities:
- dismantling of the existing electrical equipment;
- loading and transport of the material resulting from the demolition to an
approved dump area;
- procurement, transport, storage and handling of the new electrical
elements and other related materials and equipment;
- assembling and installation of the new electrical elements;
- verifications after execution in accordance to the design;
- sampling and laboratory testing.
B Pavements
B3
Walkway pavement replacement
The item covers the following activities:
- scarifying and removing the existing surface;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- cleaning and removal of any loose material from the concrete surface by sand blasting;
- procurement, transport, storage and handling of all related materials and equipment;
- execution of the leveling and slope concrete;
PQD pt publicare in Dobrogea Area
page 93 of 70
- waterproofing execution in accordance with the specific instructions in use;
- performance of the in situ adherence tests of the membrane, at the required frequency;
- execution of the asphalt mortar waterproofing protection;
- assuring water tightness in correspondence of the waterproofing edges using specific
elastic materials;
- laying 20 mm thick wearing course including surface preparation applying primer coat
with bitumen emulsion
- verifications after execution in accordance to the design;
C
Concrete repair
For each of the following chapters about concrete repair (C1, C4) the following
activities will be covered:
- Sounding of concrete to locate areas of delamination;
- preparation and cleaning of surface by means of sand blasting and water washing
and/or concrete removal by means of hydrodemolition;
- loading and transport of the material resulting from the demolition to an approved
dump area;
- procurement, transport, storage and handling of all related materials and equipment;
- epoxy and polyurethane compounds application;
- application of a corrosion inhibitor and a cementitious mortar where concrete is
removed;
- verifications after execution in accordance to the design;
These interventions can be divided in 2 different work sequences in accordance with the
type and location of the deterioration. Therefore, when efflorescence, low corrosion and
spalling are founded, the following work steps may be implemented:
1 – Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 – Concrete sand blast cleaning to prepare the surface for receiving protective
materials;
3 – Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 – Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
5 – Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PQD pt publicare in Dobrogea Area
page 94 of 70
PU from BASF or similar.
Differently, when the concrete surface present honeycomb and high corrosion and
spalling, the following work steps may be implemented:
1 – Sounding of concrete to locate areas of deterioration (spalling, honeycomb,
corrosion);
2 – Hydrodemolition of damaged concrete with 30000 psi of pressure and concrete
removal of 4 cm, being attention with reinforcing steel;
3 – Concrete water washing with 1500 psi of pressure to remove oils, grease or other
substances;
4 – Application of a modified polymer cementitious monocompound corrosion inhibitor
like EMACO NANOCONCRETE AP from BASF or similar;
5 – Application of a thixotropic cementitious mortar with restrained expansion, fiber-
reinforced with flexible inorganic fibres, like EMACO FORMULA TIXOFIBER from
BASF or similar;
6 – Application of an epoxy resin primer coat like MASTERSEAL PRIMER PU from
BASF or similar;
7 – Application of a polyurethane resin protective coat like MASTERSEAL FORMULA
PU from BASF or similar;
C1 Deck slab repair
C4 Piers concrete repair
D Steel works
D1
Overcoating of steel structures
This item requires the painting of steel structures, and so the following operations
became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
- application techniques,
- impact of regulations
D4
Rehabilitation of inspection gantry and rails
This item requires the painting of the inspection gantry and rails, and so the following
operations became important factors in achieving satisfactory protection:
- surface preparation,
- coating materials,
PQD pt publicare in Dobrogea Area
page 95 of 70
- application techniques,
- impact of regulations
E Earthworks
E3
Cone quarters rehabilitation
Cone quarters rehabilitation by the same original materials, including land cleaning of
bushes and shrubs, excavation, filling with suitable fill material or natural aggregates
stabilized with cement.
The item covers the following activities:
- land cleaning of bushes and shrubs;
- procurement, transport, storage and handling of necessary materials and equipment;
- excavation of soil in borrow pit or in an intermediary storage;
- loading and transport of the soil resulted from excavations to the approved storage
yards;
- spreading of soil in 10 cm layers and compaction;
- finishing works, check of the achieved surfaces in respect to the design;
- checking of the filling quality after compaction.