ROM and DCA

ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us

Embed Size (px)

Citation preview

Page 1: ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us

ROM and DCA

Page 3: ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us

ROM

The project manager provides a rough estimate of the cost and timescale of the extension

He does this by comparing our initial ideas with other work he has undertaken

He cannot assess other costs that may be incurred e.g. are the sewer and drainage pipes of sufficient capacity for the extended house. If

we want this information we have to pay for a sewer and drains survey.

The project manager assessment lets us work out if our aspirations are achievable.

The project manager (from experience) suggests refinements to the plans and then we have something we think is achievable

Page 4: ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us

Cost of DCA

This is the architect used by the Project Manager

Having got an idea of what is achievable an architect draws up plans.

The Project Manager arranges for the architect and other surveys and planning permission submissions

We have to pay for these servicesThe plans are passed.

Page 5: ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us

DCA

We have paid for the plans, surveys and planning permission.The project manager gives a firm quote for cost and

timescales, noting contingency areas and providing detailed impacts and plans for each room and the house structure e.g.

roof, drains etc.We re-assess the viability

At this point we can change the plans etc, if the plans are altered significantly we have to go through (and pay) for the

revised drawings and further planning permissions submissions.

Page 6: ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us

Project commencement

The project manager manages the extension work:- Builders- Plumbers

- Decorators- Building Regulations control

- Final sign-off

Page 7: ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us

Project completion

The completed extension

Page 8: ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us

UNC Mod process and Xoserve

• Assumes User Pays mod and “sunny day” journey

• Mod raised

• Business rules defined

• Xoserve produce Rough Order of Magnitude

• Mod development proceeds

• [Xoserve produce Detailed Cost Analysis]

• Xoserve produce Agency Charging Statement

• Mod approved

• Xoserve develop solution

• Mod implemented

• User Pays service starts, costs recovered

Page 9: ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us

UNC Mod process and Xoserve

• Rough Order of Magnitude (ROM)– Requires business rules

– Xoserve assess (desktop exercise) impact to systems, compare to previous changes and assess timescale and cost range. Note: certain aspects cannot be estimated e.g. changes to IS systems capacity without incurring costs

– Used to assess if business case behind mod is still valid

– Date range is development timescale not implementation date for mod

• Detailed Cost Analysis (DCA)– Requires detailed business rules and volume usage

– Xoserve complete analysis phase of the project to determine design, development, testing and implementation activities.

– DCA provides firm costs and development timescales for the change

– If the change proceeds, the work done in the DCA is re-used

– DCA are chargeable to industry

Page 10: ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us

UNC Mod Process and Xoserve

• Mod Review 334 Post Implementation Review of Central Systems Funding and Governance Arrangements, review points

• Proposer to discuss mod with Xoserve prior to raising to create more informed proposal

• Shippers to provide demand information

• Check point for community to assess business case

• Basis and purpose of ROM is understood

• User Pays charging basis fully developed

• Xoserve to be more assertive in raising concerns