Upload
nestor-hubac
View
227
Download
0
Embed Size (px)
Citation preview
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 1/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
1
CLEAN DEVELOPMENT MECHANISM
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
Version 03 - in effect as of: 22 December 2006
CONTENTS
A. General description of the small scale project activity
B. Application of a baseline and monitoring methodology
C. Duration of the project activity / crediting period
D. Environmental impacts
E. Stakeholders’ comments
Annexes
Annex 1: Contact information on participants in the proposed small scale project activity
Annex 2: Information regarding public funding
Annex 3: Baseline information
Annex 4: Monitoring Information
Annex 5: Project Timeline
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 2/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
2
Revision history of this document
VersionNumber
Date Description and reason of revision
01 21 January
2003
Initial adoption
02 8 July 2005 • The Board agreed to revise the CDM SSC PDD to reflect
guidance and clarifications provided by the Board since
version 01 of this document.
• As a consequence, the guidelines for completing CDM SSC
PDD have been revised accordingly to version 2. The latest
version can be found at
<http://cdm.unfccc.int/Reference/Documents>.
03 22 December
2006
• The Board agreed to revise the CDM project design
document for small-scale activities (CDM-SSC-PDD), takinginto account CDM-PDD and CDM-NM.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 3/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
3
SECTION A. General description of small-scale project activity
A.1 Title of the small-scale project activity:
>>
Rocky Farms, Inc. Methane Recovery and Electricity Generation Project
Version 3
29 September 2008
A.2. Description of the small-scale project activity:
>>
The Rocky Farms, Inc. Methane Recovery and Electricity Generation Project (hereafter, the “Project”)
developed by developed by Rocky Farms, Inc (hereafter referred to as the “Project Developer” or “Rocky
Farms”) with technology provided by Philippine Bio-Sciences Co., Inc. (PhilBIO) is an anaerobic
digestion (AD) swine wastewater treatment project at the Rocky farrow to finish swine farm located in
Sitio Kalantas, Quisao, Pililla, Rizal, Philippines (hereafter referred to as the “Host Country”). The project is hosted by Rocky Farms Inc.
Rocky Farms’ waste management operations involve scraping and hosing down its animal waste with
fresh water. The wastewater is then channelled to a series of concrete lagoons (oxidation ponds). The
animal waste material from the farm degrades anaerobically in the farm’s lagoon system producing
significant amounts of methane.
The Project Developer will install a covered in-ground anaerobic reactor that will promote rapid
anaerobic decomposition of organic materials in the wastewater and capture the generated biogas. The
anaerobic reactor system also treats the organically laden wastewater to reduce the amount of Chemical
Oxygen Demand (COD) and Biochemical Oxygen Demand (BOD) contained prior to the wastewater
reaching the main pond system. The biogas produced in the project’s anaerobic digester will be used to
generate electricity for use on site. Currently the farm relies on electricity from the Luzon grid. With the
implementation of the project activity, electricity will be generated from the renewable biogas and will
displace the grid electricity. No emissions reductions will be claimed in the project activity from
displacing grid electricity as the amount of emission reductions is not significant.
Development of the Project will directly reduce greenhouse gas emissions produced by the release of
methane from the lagoons and carbon dioxide emissions resulting from the generation of grid electricity.
The Project is helping the Host Country fulfil the sustainable development goals outlined in Philippine
Agenda 21.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 4/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
4
• The project at Rocky Farm is the first of its kind and will act as a clean technology demonstration
project within the wastewater management sector, which could be replicated across the Philippines
and the region;• The project is an important capacity building activity, demonstrating the use of a new financial
mechanism for funding of the renewable energy and waste management sector via the Clean
Development Mechanism (CDM);
• The project increases diversity and security of energy supplied through energy self sufficiency;
• The project will result in significant reduction in levels of biological oxygen demand, chemical
oxygen demand and total suspended solids (TSS) and in turn will result in cleaner effluents. These
effluents can be recycled on-site or off-site as irrigation water. Benefits shall also accrue to the
communities in terms of cleaner water ways.
• The project will make the farm more competitive and thus ensure long term employment to the local
residents, be a source of local taxes for the Local Government Units (LGU) which in turn will
improve delivery of basic services to the community;
• The multiplier effect of this investment is likely to bring additional benefits, such as employmentopportunities, particularly in the agro-industrial sector;
• The project will make use of methane rich biogas through a closed loop process, thereby reducing
greenhouse gas emissions; and,
• The project will improve local air quality and significantly reduce odour, which in turn will directly
benefit the adjoining communities.
A.3. Project participants:
>>
Name of Party involved
(*) ((host) indicates a
host Party)
Private and/or public entity(ies)
Project participants (*)
(as applicable)
Kindly indicate if the
Party involved
wishes to be
considered as project
participant
The Philippines (host) Rocky Farms, Inc. No
United Kingdom of Great
Britain and Northern
Ireland
EcoSecurities Group Plc.
EcoSecurities Group Limited No
(*) In accordance with the CDM modalities and procedures, at the time of making the CDM-PDD
public at the stage of validation, a Party involved may or may not have provided its approval. Atthe time of requesting registration, the approval by the Party(ies) involved is required.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 5/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
5
A.4. Technical description of the small-scale project activity:
The ‘covered in-ground anaerobic reactor’, or ‘CIGAR’, breaks down organic contaminants through a
three-step biological process where wastewater is treated in the absence of oxygen. The wastewater isheld in the reactor for at least 30 days where specialized bacteria consume the waste and release methane
that is utilised as biogas for on-site electricity generation (see figure 1).
Figure 1: CIGAR pond reactor 1
The project uses CIGAR anaerobic digestion technology utilizing 1.0mm High Density Polyethylene
(HDPE) as a flexible membrane liner. HDPE is an essentially impermeable, resilient plastic which has
high durability in sunlight and rainy weather. It is produced by HUITEX from Taiwan.
HDPE liners and covers are used to provide a gas seal to prevent methane from escaping to the
atmosphere and prevent leachate from escaping to the underground aquifer. The CIGAR system is sealed
100% of the time and results in at least 95% destruction of BOD, and 80% reduction of COD. Suspended
solids, dissolved solids and colour are all improved in the CIGAR. The long retention time of at least
thirty days in the CIGAR at approximately 35 degrees Celsius reduces pathogenic material.
Methane gas makes up at least 60% of the biogas by volume. The biogas will be used to generate
electricity for the farm through a 60kW generator. This electricity will partially displace the grid supply
and the maximum renewable electricity generation is less than the total farm requirements.
A.4.1. Location of the small-scale project activity:
>>
A.4.1.1. Host Party(ies):
>>
The Philippines
A.4.1.2. Region/State/Province etc.: >>
Rizal
1 Source: “Cost Estimation of Biogas Plants in Piggeries: A Manual for Hog Raisers”, prepared by the Development Bank of the Philippines.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 6/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
6
A.4.1.3. City/Town/Community etc:
>>
Sitio Kalantas, Pililla
A.4.1.4. Details of physical location, including information allowing the
unique identification of this small-scale project activity :
>>
The project is located in the municipality of Quisao, in the province of Rizal in the Philippines. The
address of the project is: Rocky Farms, Inc., Sitio Kalantas, Quisao, Pililla, Rizal, Philippines
The GPS Coordinates are: N 13° 55.775', E 121° 23.844'
A.4.2. Type and category(ies) and technology/measure of the small-scale project activity:
>>
The category for the project activity according to the UNFCCC’s published “Appendix B - Indicative
Simplified Baseline and Monitoring Methodologies for Selected Small-Scale CDM Project Activities” is:
Type III.D (reference AMS-III.D, version 13, EB 33) – “ Methane recovery in agricultural and agro
industrial activities”.
Sectoral Scope 15: Agriculture
This project category comprises methane recovery and destruction from manure and wastes from
agricultural or agro-industrial activities that would be decaying anaerobically in the absence of the
project activity by installing methane recovery and combustion system to an existing source of methane
emissions.
A.4.3 Estimated amount of emission reductions over the chosen crediting period:
>>
Years
Annual estimation of
emission reductions over the
chosen crediting period
2009 3,201
2010 3,201
2011 3,201
2012 3,201
2013 3,201
2014 3,201
2005 3,201
Total estimated reductions (tonnes of CO2)
22,407
Total number of crediting years 7 (renewable up to 21 years)
Annual average over the crediting period
of estimated reductions (tonnes of CO2)3,201
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 7/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
7
A.4.4. Public funding of the small-scale project activity:
>>
The project has not received and is not seeking public funding.
A.4.5. Confirmation that the small-scale project activity is not a debundled component of a
large scale project activity:
Based on the information provided in Appendix C of the Simplified modalities and procedures for small-
scale clean development mechanism project activities, this Project is not a debundled component of a
larger project activity since the project participants have not registered nor operated another project in
the region surrounding the project boundary.
SECTION B. Application of a baseline and monitoring methodology
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
small-scale project activity:
>>
• Project activity type III.D (reference AMS-III.D version 13) -Methane recovery in agricultural
and agro industrial activities.
B.2 Justification of the choice of the project category:
>>
The simplified baseline and monitoring methodology AMS III.D., version 13, EB 33, Methane recovery
in agricultural and agro industrial activities, is applicable.
The project conforms to project category III.D since the project reduces anthropogenic emissions bymethane recovery and destruction from manure from agricultural or agro-industrial activities that would
be otherwise be decaying anaerobically. This selection is appropriate because the alternative to the
project activity would be to continue with the business as usual scenario. The farm would continue to
manage waste water through the existing anaerobic lagoon system and would continue to rely exclusively
on the power grids for electricity. The implementation of project activity results in emission reductions
lower than 60,000 tCO2e annually.
B.3. Description of the project boundary:
>>
According to AMS.III.D., the project boundary is the “physical geographical site of the methane recovery
facility”. As such, the project boundary encompasses the anaerobic digester, the biogas network that
carries captured methane to the generator, and the generator.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 8/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
8
Figure 2. Project Boundary under AMS.III.D.
B.4. Description of baseline and its development:
>>
As specified in Appendix B:
• The appropriate baseline for project category Type III.D (AMS-IIID, version 13) is found in
paragraph 7.
Methane recovery in agricultural and agro industrial activities (AMS-III.D, version 13)
For the methane recovery component of the project activity, the baseline has been calculated
according to project activity type III.D (version 13), Paragraph 7 which states:
“The baseline scenario is the situation where, in the absence of the project activity, biomass and
other organic matter are left to decay anaerobically within the project boundary and methane is
emitted to the atmosphere. Baseline Emissions (BEy) are calculated ex ante using the amount of
raw waste material that would decay anaerobically in the absence of the project activity, with the
most recent IPCC Tier II approach (please refer to the chapter ‘Emissions from Livestock and
Manure Management’ under the volume ‘Agriculture, Forestry and other Land use’ of the 2006IPCC Guidelines for National Greenhouse Gas Inventories).”
The project complies with this activity type as, in the absence of the project activity, organic
matter from swine wastewater is left to decay anaerobically within the project boundary in
anaerobic lagoons. The methane generated from is subsequently freely released to the
atmosphere.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 9/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
9
• Date of completing the final draft of this baseline section (DD/MM/YYYY): 30/08/2007.
The baseline study was prepared by:Mr. Oman Singh, EcoSecurities Ltd.
Tel: +60 3 2282 0612/32
E-mail: [email protected]
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered small-scale CDM project activity:
MARKET SITUATION & NATIONAL POLICIES:
The Philippines swine inventory as of January 1, 2007 was estimated at 13.5 million head, up by 3.16 %compared to previous year's level About 73 % of the total inventory came from backyard farms while
27% was from commercial farms. According to the Philippine Bureau of Agricultural Statistics, the
swine industry, which accounted for 81 % of total livestock production registered a 3.66 % growth in
2006. Filipinos are large consumers of pork with an annual per capita consumption of 13.88 kg excluding
offals and processed meat and volume of imports grow yearly, with 2006 recording an increase of
13.6%.2
The industry faces a number of obstacles including the spread of economically devastating diseases, high
marketing and transaction costs, erratic supply of imported feed ingredients, supplements and biologics,
and the limited availability of genetically superior breeding stock.3
The main regulatory agencies that monitor the industry are the Bureau of Animal Industry (BAI) and the
National Meat Inspection Commission (NMIC) under the Philippine Department of Agriculture.Environmental regulations are monitored and enforced by the Department of Environment and Natural
Resources (DENR). The primary environmental laws applicable to the project are the Clean Water Act
(2003) and the Clean Air Act (1999).
ADDITIONALITY:
According to Attachment A to Appendix B of the simplified modalities and procedures for CDM small-
scale project activities, evidence as to why the proposed project is additional is offered under the
following categories of barriers: (a) investment barrier, (b) technological barrier, and (c) prevailing
practice.
a) Investment Barrier
2 Bureau of Agricultural Statistics, Department of Agriculture, Philippines, “Swine Industry Performance Report Jan - Dec 2006” <http://www.bas.gov.ph>
3 Abuel-Ang, Pia, “Philippines Livestock and Products Annual 2004”, USDA Foreign Agricultural Service, September 2004
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 10/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
10
Small swine farms have a difficult time securing financing for the implementation of biogas waste water
management projects and, when they are able to secure financing, the interest rates tend to be high at an
average of 15.6%.4 The following factors contribute to the investment barrier which these projects face:
• Perceived Risk - Most local banks are not interested in these projects primarily because of lack of
knowledge and experience with the technology. Most small farmers perceive they are not eligible
or unable to obtain attractive terms in loans and differential access to credit is revealed in the
lower incidence of borrowing for production purposes by smallholders (4-10%) compared to
large-scale farms (24-27%). This is reinforced by the relatively high percentage of smallholders
who do not attempt to borrow from a bank because they perceive their chances of being granted a
loan as being low (31%).4
• Current Practice - Eighty percent (80%) of the backyard and commercial farms deposit their
waste products in nearby creeks and rivers. From consultations conducted in a study, the waste
management option that farms would most likely adopt is composed only of wastewater
reduction/minimization and disposal. Waste treatment and recycling/reuse are not included in
their options since they see waste treatment strategy as an additional expense.5 The current
oxidation pond based wastewater treatment method is considered standard practice in the
Philippines and the region only due to compliance reasons. Moreover, for the Project Owner, the
current pond system (business as usual scenario) is attractive, given that it works to required
specification and requires virtually no management input to achieve the key parameters. All
required land is appropriated and the current system has sufficient capacity to handle additional
waste.
• Lowest Cost - The current system represents the lowest cost option, with the only cost being the
opportunity cost of alternative land use.
The inclusion of CER revenues has therefore become an important part of the Project Owners and
Project Developers implementation and financing strategy.
(b) Technological Barrier:
The predominant technology for piggery wastewater treatment in the Philippines is through a series of
lagoons (oxidation ponds).6 Biological treatment of piggery wastewater to produce biogas is a new and
relatively unknown technology in the host country. The lack of available knowledge and confidence in
the technology, especially among small swine farms, makes this type of development difficult to
establish. As a result, most swine farm owners view this technology as risky and this risk is reflected in
the fact that there were fewer than ten swine anaerobic digestion projects in the host country when this
project was started. Moreover, many farmers are concerned that a bio-digester project is too complex to
operate and maintain. The anaerobic digestion and biogas system utilized in the project scenario is quite
different than previous experience in the Philippines. The project scenario represents a more
technologically advanced alternative to the business as usual scenario, and one that carries higher
perceived risk.
4 Christopher L. Delgado,, et al., “Policy, Technical, and Environmental Determinants and Implications of the Scaling-Up of Livestock Production in Four Fast-Growing
Developing Countries: A Synthesis” <htt p://www.fao.or g/wairdocs/lead/x6170e /x6170e00.htm>
5 Ma. Angeles O. Catelo, et al., “Backyard And Commercial Piggeries In The Philippines: Environmental Consequences And Pollution Control
Options”
6 “Cost Estimation of Biogas Plants in Piggeries: A Manual for Hog Raisers”, prepared by the Development Bank of the Philippines.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 11/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
11
Anaerobic digestion systems are perceived as relatively high risk, being based upon the function of a
biological system that is neither 100% characterised, nor performance guaranteed. The biological system
is at constant risk of chemical shocks that can wipe out the anaerobes and biological activity (andsubsequently the waste management and energy production regimes, which are both key to commercial
operations). AD systems require constant and ongoing precise management of a variety of elements,
including water flows, pH levels, etc. In general, they are perceived as a risky solution. Overall, the
project scenario involves higher perceived risks due to the performance uncertainty and a low market
share of the new technology.
(c) Prevailing Practice:
The Rocky farms project is the very first prototype CIGAR anaerobic digester project in the Philippines
and it’s the first-of-its-kind in Philippines. It was part of CDM capacity building in Philippines and was
first considered for CDM as early as 1999.7 Use of the CIGAR technology utilized in the project activity
is not common practice in the Philippines and represents a higher risk alternative to the business as usual
scenario. The minimization of wastewater is considered most desirable for pig farms and wastewater
treatment with a lagoon system would be considered if there is available space, although the lagoon
system is not profitable at all.5 There is little experience of utilising aerobic or anaerobic technologies in
Philippines. The highest priority for commercial farms is the management of their waste discharges to
simply maintain compliance with local regulation. From the project farm operator’s perspective, the
existing lagoon system is a cheap and sufficient way to clean the waste water.
SUMMARY:
The current and expected practice in the host nation, which commercial farms rely almost exclusively on
lagoon based treatment facilities for piggeries wastewater management, as well as the combination of
lack of access to financing and perceived risks of the selected technology, clearly demonstrate that the
Project is additional and therefore not the baseline scenario. The prohibitive barriers that exist in thePhilippines are confirmed by the observed trend in current piggery waste water management practices.
The barrier analysis above clearly demonstrates that the most plausible baseline scenario for wastewater
treatment is the prevailing practice of lagoon systems.
B.6. Emission reductions:
B.6.1. Explanation of methodological choices:
>>
Emissions Reductions:
According to AMS.III.D. (version 13), Baseline emissions are calculated ex ante using the amount of the
waste or raw material that would decay anaerobically in the absence of the project activity, with the most
7Alberto R. Dalusung III, “Capacity Building in Clean Development Mechanism Project Activities”, Final Report,
September 1999, Under contract no. GLO/98/G55 with UNDP.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 12/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
12
recent IPCC tier 2 approach. The actual emission reduction achieved by the project during the crediting
period will be calculated using the amount of methane recovered and destroyed by the project activity
and the maximal yearly emission reduction is limited to the yearly methane generation potential
calculated in the PDD for that year.
Hence, for ex-ante emission reduction calculations:
Total emissions reductions = Total baseline emissions - Total project emissions
In paragraph 6, of AMS III D, version 13; Project emissions are defined as:
“Project Emissions consists of CO2 emissions from use of fossil fuels or electricity for the operations
of the facility”
The only project-associated equipments are 0.25HP blowers used to direct the collected biogas to the gashandling system. This consumption will be met by the biogas electricity generation as it would only run
when the biogas generator is running. Since all the biogas collected will be utilised for energy generation,
there will be zero project emissions of this nature because the minimal power needs for operation of the
equipment associated with the CIGAR will be met entirely with renewable biogas.
Project emissions from energy generation will be taken into account where a 90% combustion efficiency
of biogas generator is applied. This approach is conservative as typical ‘combustion efficiencies’ of
internal combustion engines exceeds 95%.
Thus the total project emissions: PEy equals to project emissions from energy generation PECH4_IC,y.
B.6.2. Data and parameters that are available at validation:
Data / Parameter: Swine Level (Number of Swine)
Data unit: Head of Swine
Description: The number of swine in the facility (breeding and non-breeding) will determine
the amount waste generated, the facility design, and digester design
Source of data used: In house data from the farmers
Value applied: 879 (Breeding), 5746 (Market)
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied :
The numbers of swine will be the basis of emissions reductions calculations
based on the IPCC 2006 Tier II approach.
Any comment:
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 13/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
13
Data / Parameter: Average Weight of Swine
Data unit: Kg
Description: The average weight of swine (breeding and non-breeding) will determine the
amount waste generated, the facility design, and digester designSource of data used: In house data from the farmers
Value applied: 200.55 (Breeding), 40.12 (Market)
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied :
The average weights of swine will be the basis of emissions reductions
calculations based on the IPCC 2006 Tier II approach.
Any comment:
B.6.3 Ex-ante calculation of emission reductions:
>> Total Emissions reductions from AMS IIID, v 13 are calculated ex ante:
Emission Reductions = BEy - PEy
BECH4,y 3,557 tCO2e/yr
PEy 640 tCO2e/yr
ER 5,761 tCO2e/yr
Total Baseline Emissions are calculated ex ante as follows:
BEelec/heat,y is zero as no emissions reductions being claimed from displacing Grid Electricity.
Since there are no foreseeable project emissions as described in Section B.6.1; total baseline emissions
will be equivalent to:
BECH4,y 3,557 tCO2e/yr
BEelec/heat,y 0.0 tCO2e/yr
BEy 3,557 tCO2e/yr
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 14/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
14
Parameter Value Unit Source/Comment
GWPCH4 21
DCH4 0.00067 t/Nm
3
ACM0010
Breeding swine
Parameter Value Unit Source/Comment
MCF j 0.8
Annual Default from IPCC 2006
Tier II
Bo 0.45 kg CH4/Kg VSDefault from IPCC 2006 Tier IIfunciton of genetics
N breeding 879 head Site data
VS breeding 203.3 Kg VS/head*yr
Default from IPCC 2006 Tier II
and site data
MS breeding 100% Site data
Σ breeding_BE 64,342.2
VSbreeding
VSLT,y was determined by scaling default IPCC values as per guidance in ACM0010,
equation (4). VSdefault was used to adjust for a site-specific average animal weight as shown
here:
Parameter Value Unit Source/Comment
Wsite_breeding 200.5460751 kg/head
weighted average of sow and
boar weights from site data
Wdefault_breeding 180 kg/head
IPCC default value, function of
genetics
VSdefault_breeding 0.5
Kg
VS/head*day
IPCC default value, function of
genetics
nd breeding 365 days/yr treatment plant is operational
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 15/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
15
VSbreeding 203.3
Kg
VS/head*day
Market Swine
Parameter Value Unit Source/Comment
MCF j 0.8 %Annual Default from IPCC 2006
Tier II
Bo 0.45 kg CH4/Kg VSDefault from IPCC 2006 Tier II
funciton of genetics
Nmarket 5,746 head Site data
VSmarket 91.1 Kg VS/head*yr Default from IPCC 2006 Tier II
and site data
MSmarket 100% Site data
Σmarket_BE 188,496.9
VSmarket
VSLT,y was determined by scaling default IPCC values as per guidance in ACM0010,
equation (4). VSdefault was used to adjust for a site-specific average animal weight as shown
here:
Parameter Value Unit Source/Comment
Wsite_market 40.12339018 kg/head
weighted average all swine
subcatories based on weight
from site data
Wdefault_market 45 kg/headIPCC default value, function of
genetics
VSdefault_market 0.28 KgVS/head*day
IPCC default value, function of genetics
ndmarket 365 days/yr treatment plant is operational
VSmarket 91.1
Kg
VS/head*day
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 16/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
16
BECH4,y 3,557.4 tCO2e/yr
Project Emissions from biogas combustion in generator
The only associated project emissions are from biogas combustion, thus
PEy = PE CH4_IC, y
Equivalent to :
PE CH4_IC,y = BE CH4,y * (1- f genset_ )
Parameter Value Unit Source/Comment
BECH4,y 3557 calculated
f genset 90% from EPC provider
PECH4_IC,y 356 tCO2e/yr
PEy 356 tCO2e/yr
Ex-Post Baseline
The ex-post baseline corresponds to the lower of either: the baseline based on Tier II calculations and
made ex-ante, or the baseline based on metered biogas production. The latter is to be calculated as
follows:
Where:MD y: Methane captured and destroyed by the project activity in the year “y” (t CO2e)
BGburnt, y: Biogas flared or used as fuel in the year “y” (m3)
wCH4, y:: Methane content in biogas in the “y” (mass fraction)
DCH4, y : Density of methane at the temperature and pressure of the biogas in the year “y”
(tonnes/m3)
GWP CH4: Methane global warming potential (21)
MD y = BGburnt,y * wCH4,y * DCH4,y* GWP CH4
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 17/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
17
Baseline Determination
The baseline is the lower of the baselines predicted by the Tier II approach and the biogas-based one. Ineach verification period the baseline will be determined as such, using monitored data to calculate the
biogas baseline.
As per the methodology AMS-III.D version 13 paragraph 9, no leakage calculation is required.
B.6.4 Summary of the ex-ante estimation of emission reductions:
>>
Years
Estimation of
baseline
emissions
(tonnes of CO2
e)
Estimation of
project activity
emissions
(tonnes of
CO2e)
Estimation of
emission
reductions
(tonnes of CO2
e)
2009 3,557 356 3,201
2010 3,557 356 3,201
2011 3,557 356 3,201
2012 3,557 356 3,201
2013 3,557 356 3,201
2014 3,557 356 3,201
2015 3,557 356 3,201
Total (tonnes of CO2) 24,902 2,492 22,407
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 18/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
18
B.7 Application of a monitoring methodology and description of the monitoring plan:
B.7.1 Data and parameters monitored:
Data / Parameter: BG burnt,y (fuelled)
Data unit: Nm3 (Normal Cubic Meters at 0° C and 1.01325bar)
Description: Biogas used as fuel
Source of data to be
used:
Project developer
Value of data As measured
Description of
measurement methods
and procedures to be
applied:
The amount of biogas used as fuel in the generator will be monitored
continuously with a cumulative thermal flow meter and recorded daily.
QA/QC procedures to
be applied:
The meter will be maintained and calibrated regularly in line with
manufacturer’s recommendations.Any comment: The thermal flow meter is normalised, thus temperature and pressure do no need
to be monitored separately.
Data / Parameter: wCH4,y,
Data unit: %
Description: Methane content of Biogas
Source of data to be
used:
Project Developer
Value of data 64
Description of
measurement methods
and procedures to be
applied:
The methane content of the gas to be combusted will be analysed and recorded
monthly with a portable gas analyser.
QA/QC procedures to
be applied:
The gas analyzer will be maintained and calibrated regularly in line with
manufacturer’s recommendations.
Any comment:
Data / Parameter: EGgenerated
Data unit: kWh
Description: Electricity generated on site
Source of data to be
used:
Project developer
Value of data 525,600
Description of
measurement methods
and procedures to be
applied:
Renewable electricity generated from biogas generator will be monitored
continuously with a cumulative electricity meter and recorded daily.
QA/QC procedures to
be applied:
Meter will be maintained and calibrated regularly in line with manufacturer’s
recommendations.
Any comment:
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 19/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
19
Data / Parameter: ηgenset
Data unit: %
Description: Combustion efficiency for biogas genset
Source of data to beused:
Project developer
Value of data 90%
Description of
measurement methods
and procedures to be
applied:
A 90% default value is be used and continuous check of compliance with the
manufacturer’s specification will be done.
QA/QC procedures to
be applied:
The biogas genset will be maintained and serviced regularly in line with
manufacturer’s recommendations.
Any comment:
Data / Parameter: Monitoring of Sludge Application
Data unit:Description: Removal and application of sludge leaving the reactor.
Source of data to be
used:
Project developer
Value of data
Description of
measurement methods
and procedures to be
applied:
The sludge that accumulates at the bottom of CIGAR will be removed and dried
in an aerobic manner to be used as fertilizer. Proper soil application of the sludge
aerobically will be done to ensure there is negligible methane from anaerobic
conditions.
QA/QC procedures to
be applied:
Any comment: Sludge removal will be done after an estimated 10 years of operation. In any
event there is removal and soil application of sludge; the process will be
monitored to ensure the conditions are aerobic.
B.7.2 Description of the monitoring plan:
>>
This section details the steps taken to monitor on a regular basis the GHG emissions reductions from the
project.
The Monitoring Plan for this project has been developed to ensure that from the start, the project is well
organised in terms of the collection and archiving of complete and reliable data.
Prior to the start of the crediting period, the organisation of the monitoring team will be established.Clear roles and responsibilities will be assigned to all staff involved in the CDM project. The Project
Developer will have a designated a person on site that will be responsible for monitoring emissions
reductions of the project activity. Staff will receive some basic CDM training to ensure that they
understand the importance of complete and accurate data and records for CDM monitoring. In addition to
these qualified personnel will be designated to handle and operate equipment and machinery at the
project site.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 20/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
20
A formal set of monitoring procedures will be established prior to the start of the project. This will
ensure that high quality data is obtained. Specifically, data and records will be checked prior to being
stored and archived. Data from the project will be checked to identify possible errors or omissions.All data required for verification and issuance will be kept for at least two years after the end of the
crediting period or the last issuance of CERs of this project, whichever occurs later. Data will be
archived electronically and data backup will be maintained. Paper data back up will also be available.
All equipment will be calibrated and maintained in accordance to the manufacturer’s recommendations to
ensure accuracy of measurements. Records of calibration and maintenance will be retained as part of the
CDM monitoring system. A final data check and on-site inspection will be done by EcoSecurities prior to
any verification.
The ex-post emissions reductions in any year are limited to the yearly methane generation potential as
calculated ex-ante. The sludge that accumulates at the bottom of CIGAR will be removed after
approximately 10 years of operation and dried in an aerobic manner to be used as fertilizer.
B.8 Date of completion of the application of the baseline and monitoring methodology and the
name of the responsible person(s)/entity(ies)
>>
• Date of completing the final draft of this baseline and monitoring section (DD/MM/YYYY):
29/02/2008.
The baseline and monitoring study was prepared by:
Mr. Oman Singh, EcoSecurities Ltd.
Tel: +60 3 2282 0612/32
E-mail: [email protected]
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 21/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
21
SECTION C. Duration of the project activity / crediting period
C.1 Duration of the project activity:
C.1.1. Starting date of the project activity:
>>
01/03/2000
C.1.2. Expected operational lifetime of the project activity:
>>
25y-0m
C.2 Choice of the crediting period and related information:
C.2.1. Renewable crediting period
C.2.1.1. Starting date of the first crediting period:
>>
01/01/2009 or on the date of registration of the CDM project activity, whichever is later.
C.2.1.2. Length of the first crediting period:
>>
7y-0m
C.2.2. Fixed crediting period:
C.2.2.1. Starting date:>>
Not Applicable
C.2.2.2. Length:
>>
Not Applicable
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 22/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
22
SECTION D. Environmental impacts
>>
D.1. If required by the host Party, documentation on the analysis of the environmental impactsof the project activity:
>>
The host country does not require an analysis of the environmental impacts of the project activity.
However, the farm has been issued an environmental compliance certificates (ECC) and have valid
Permits to Discharge.
It should be noted, further, that the project activity generates considerable environmental benefits. The
CIGAR system decreases GHG emissions through two significant avenues. Prior to the project activity,
the farm relied on local grids for electricity generation. With the implementation of the project activity,
biogas collected from the degradation of swine-farm waste is used for electricity generation, thus
eliminating the demand for electricity from the grid. In addition to directly reducing the emission of
GHGs by eliminating a source of fossil fuel combustion, the project activity captures methane (CH4)from an industrial source, preventing its release into the atmosphere.
In addition to reducing GHG emissions, this closed system of energy production produces considerable
improvements for waste management at the farm. Improperly managed and insufficiently processed
wastewater discharge from piggeries can be hazardous to aquatic ecosystems and can pollute waterways.
The extent of pollution depends on the amount of organic material and solid material contained within
the wastewater as measured by biochemical oxygen demand (BOD), chemical oxygen demand (COD),
suspended solids, and colour indicators. The CIGAR system, owing to its anaerobic digestion properties,
reduces COD by approximately 80%, reduces approximately 95% of harmful BOD, diminishes
suspended solids, and improves the colour quality of the wastewater. The closed cell CIGAR technology
also eliminates foul odour that is a significant concern to nearby populations.
D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
>>
There are no foreseeable significant environmental impacts considered significant by the project
participants. Section D.1 elaborates the sustainable development and positive contributions of the project
to waste management and energy generation in the farm.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 23/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
23
SECTION E. Stakeholders’ comments
>>
E.1. Brief description how comments by local stakeholders have been invited and compiled: >>
The comments of stakeholders were articulated in an open forum conducted at Brgy. Tumana, San
Ildefonso, Bulacan on December 12, 2005.
The participants in the stakeholder consultation open forums consisted (but were not limited) of the
following:
• Representatives from the Provincial Government Development Unit,
• Representatives from the Barangay Local Governance Unit, and
• Residents living near the farm.
• Representatives of the Environment & Management Bureau (EMB) of the Department of
Environment & Natural Resources (DENR)• Other Swine Farm owners
The stakeholder consultations commenced with the brief introduction of Cargill Environmental Finance,
EcoSecurities Philippines and Infratex by Mr. Arnold S. Bufi of EcoSecurities. Arnold also introduced
the participants from the host Barangay, representatives from the municipality of Sta. Maria, and other
stakeholders. After the brief introduction, Mr. Arnold S. Bufi of EcoSecurities Philippines also
presented the clean development mechanism (CDM) concept, the motivation for the project, the Kyoto
Protocol and the proposed methane recovery project for Rocky Farm. After the presentation, an open
forum was carried out to elicit comments and issues from the various stakeholders.
E.2. Summary of the comments received:
>>
SUMMARY OF ISSUES AND CONCERNS AND RESPONSES/RECOMMENDED MEASURES
TO ADDRESS THE ISSUES
Issues Raised Response/Recommended Measures to Address the Issues
Interest on the part of community
members to pipe biogas to their
homes or fill the biogas into tanks
from Rocky Farm.
PhilBio staff explained that they discourage their clients from
doing so because it is a fire hazard and there may be regulatory
issues involved. For storage in tanks, it requires specialized
equipment to put the biogas into cylinder tanks.
Local residents wanted to know howthey would see the sustainable
development benefits of the project.
PhilBio staff explained that the project will reduce air andwater pollution, and will result in odour reduction and climate
protection.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 24/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
24
E.3. Report on how due account was taken of any comments received:
>>
All questions were answered and addressed in full. Where applicable, and where the comments were of
specific concern to the stakeholders, due account was taken; and a summary of issues and concerns, andresponses/ recommended measures to address these issues were provided. They are tabled as in section
E.2.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 25/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
25
Annex 1
CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY
Organization: Rocky Farms, Inc.
Street/P.O.Box: Circumferential Road
Building:
City: Antipolo City
State/Region: Rizal
Postfix/ZIP:
Country: Philippines
Telephone:
FAX:
E-Mail:
URL:
Represented by:Title:
Salutation: Mr.
Last Name: Ileto
Middle Name:
First Name: Jeffrey
Department:
Mobile:
Direct FAX:
Direct tel: +632 697 1708
Personal E-Mail:
Organization: EcoSecurities Group Plc.Street/P.O.Box: 40 Dawson Street
Building: -
City: Dublin
State/Region: Dublin
Postfix/ZIP: 02
Country: Ireland
Telephone: +353 1613 9814
FAX: +353 1672 4716
E-Mail: [email protected]
URL: www.ecosecurities.com
Represented by:
Title: Company SecretarySalutation: Mr.
Last Name: Browne
Middle Name: -
First Name: Patrick
Department: -
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 26/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
26
Mobile: -
Direct FAX: -
Direct tel: -
Personal E-Mail: [email protected]
Organization: EcoSecurities Group Limited.
Street/P.O.Box: 40/41 Park End Street
Building: 1st Floor Park Central
City: Oxford
State/Region:
Postfix/ZIP: OX1 1JD
Country: United Kingdom
Telephone: +44 (0) 1865 202 635
FAX: +44 (0) 1865 251 438
E-Mail: [email protected]
URL: www.ecosecurities.com
Represented by:
Title: Director
Salutation: Mr.
Last Name: Fernando
Middle Name: -
First Name: Adrian
Department: -
Mobile: -
Direct FAX: -
Direct tel: -
Personal E-Mail: [email protected]
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 27/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
27
Annex 2
INFORMATION REGARDING PUBLIC FUNDING
- Not applicable -
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 28/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
28
Annex 3
BASELINE INFORMATION
Parameters Used in Baseline Calculations.
Parameter Value Unit Comment/Source
GWPCH4 21 tCO2e/tCH4 GWP of methane / IPCC
DCH4 0.00067 t/Nm3 Density of methane at normal conditions:
temperature (20 ºC) and 1 atm pressure /
ACM0010
Annual methane conversion factor (MCF) for an
anaerobic lagoon / IPCC 2006
MCF j 0.8
table 10.17, chapter 10, volume 4
Maximum methane producing potential of the
volatile solid generated /
Bo 0.45 kg CH4/Kg VS
Default from IPCC 2006 Tier II
N breeding 879 head Number of animals of breeding type for the year y
/ Site data in the form of a pig census form filled
out by farm manager for year 2007
Nmarket 5,746 head Number of animals of market type for the year y /
Site data in the form of a pig census form filled
out by farm manager for year 2007.
MSBl,j 100% Fraction of manure handled in system j / Site data
Wsite_market 40.1 kg/head Average animal weight of a defined population at
the project site in kg / Site data in the form of a
pig census form filled out by farm manager for
year 2007
Wdefault_market 45 kg/head Default average animal weight of a defined
population in kg from where the data on VSdefault is
sourced
VSdefault_market 0.28 Kg
VS/head*day
Default value for the volatile solid excretion per
day on a dry-matter basis for a defined livestock /
IPCC default value, function of site genetics
VSmarket,y 91.1 Adjusted volatile solid excretion per year on a
dry-matter basis for market swine at the projectsite in kg-dm/animal/yr
Wsite_breed 200.5
kg/head Average animal weight of a defined population at
the project site in kg / Site data
Wdefault_breed
180
kg/head Default average animal weight of a defined
population in kg from where the data on VSdefault is
sourced
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 29/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
29
VSdefault_breed 0.5 Kg
VS/head*day
Default value for the volatile solid excretion per
day on a dry-matter basis for a defined livestock /
IPCC default value, function of site genetics
VS breed,y 203.3 Adjusted volatile solid excretion per year on adry-matter basis for breeding swine at the project
site in kg-dm/animal/yr
f genset 90 % Combustion efficiency of generator. Inclusion of
this value is very conservative and typical
combustion efficiencies for internal combustion
engines exceed 95%.
Default IPCC values for Swine.
Breeding Animals
Genetics Avg Mass (kg) Bo (kgCH4/kgVS) VS (kg/h*day)
US 198 0.48 0.5
Western Europe 198 0.45 0.46
Eastern Europe 180 0.45 0.5
Oceania 180 0.45 0.5
Latin America 28 0.29 0.3
Africa 28 0.29 0.3
Middle East 28 0.29 0.3
Asia 28 0.29 0.3
Indian Subcontinent 28 0.29 0.3
Source: Table 10A-8 IPCC 2006 Emissions from Livestock and Manure Management
Market Animals
Genetics Avg Mass (kg) Bo (kgCH4/kgVS) VS (kg/h*day)
US 46 0.48 0.27
Western Europe 50 0.45 0.3
Eastern Europe 50 0.45 0.3
Oceania 45 0.45 0.28
Latin America 28 0.29 0.3
Africa 28 0.29 0.3
Middle East 28 0.29 0.3
Asia 28 0.29 0.3Indian Subcontinent 28 0.29 0.3
Source: Table 10A-7 IPCC 2006 Emissions from Livestock and Manure
Management
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 30/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
30
Manure Management System MCFs
Average Annual Temp MCF anaerobic Lagoon (%)
28 80%
Source: Adapted from Table 10A-8 IPCC 2006 Emissions from Livestock and Manure
Management
Temperature Data
Name City/
Municipality
Province Annual
average
Temp (˚C)
Measured
Where?
Aprox. Distance
from
measurement
point to province(km)
Source
Rocky
Farm
Pililla Rizal 28.3 Cabanatuan 44.9 weatheronline.co.
uk
Pig Census as Returned from Farm Management Personnel on Site:
Census 2007
Type of Pig
Average Weight
of that type Average Number
Breed/Genetic
Source
Feed
Formulation
Suckling 7 1137 Booster feed
Prestarters 15 1065 Prestarter feed
Starters 25 1087 Starter feed
Growers 60 1078 Grower feed
Finishers 80 1268 Grower feed
Gilts 120 111 Gilt feed
Sows 200 855
Gestation &
Lactation
Boars 220 24
Largewhites,
Australia
Gestation
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 31/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
31
Annex 4
MONITORING INFORMATION
Please Refer to Section B.7.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 32/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
32
Annex 5
PROJECT TIMELINE
No. Event Date
1.
Rocky Farms project which is the very first prototype biogas
to energy CIGAR project by Philbio in the Philippines, was
part of CDM capacity building programme as documented in a
published UNDP report8.
September, 1999
2.
Rocky Farms project activity start date was 1st
March 2000,
which was the earliest date where expenditure (pre-payment)
related to the project was incurred.
March 1, 2000
3.CDM advisory services agreement between Ecosecurities and
Philbio for CDM development of Philbio’s projects. March 4, 2002
4.
Philbio actively replicates a large number of pig farm AD
projects in Philippines after Rocky Farms with a prospect of
implementing CDM, of which 9 have been registered as CDM
projects. The Department of Environment and Natural
Resources (DENR) was designated as the Designated National
Authority (DNA) on June 25 2004. Rocky Farms project was
continually featured as a model CDM project in capacity
building workshops and presentations. Subsequently a ‘CDM
Country Guide in the Philippines’ was published by the
Institute for Global Environmental Strategies in 2005; the
guide lists Rocky Farms as a potential CDM project.
2002-2005
5
Eight Philbio projects held a common Stakeholder
Consultation for CDM.
• Rocky Farm in Rizal Province
• Red Dragon I and Red Dragon II (E-pig) Farms in San
Fernando and Magalang, Pampanga
• Sto. Domingo Farm in Tarlac City
• Superior Farm in Tarlac City
• Lanatan Farm in Balayan, Batangas
• Jhon & Jhon Farm in Binangonan, Rizal
• Joliza Farm in Sta. Maria, Bulacan
October 7, 2005
6.Rocky farms project activity PDD completion date under
methodology AMS III.D. ver 6, and sent for Host Nation LOAOctober 20, 2005
7.Rocky farms project activity published for Global Stakeholder
Consultation, under methodology AMS III.D. ver 6October 25, 2005
8Alberto R. Dalusung III, “Capacity Building in Clean Development Mechanism Project Activities”, Final Report,
September 1999, Under contract no. GLO/98/G55 with UNDP.
8/6/2019 Rocky Farms Methane
http://slidepdf.com/reader/full/rocky-farms-methane 33/33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
8.Additional documents submitted for Host Nation LOA as
required by the DNA.December 7, 2005
9. Rocky Farms held an individual Stakeholder Consultation for CDM.
December 12, 2005
10.
Letter from Philbio to Rocky requesting additional documents
and clarifications for the DNA. Request made by the DNA
based on a CDM steering committee meeting which convened
6th March 2006.
May 4, 2006
11.Letter from the DNA to Philbio on submission of supporting
documents.February 12, 2007
12.Entire project activity documents re-submitted for Host
Nation LOA as required.March 20, 2007
13.Follow-up letter to the DNA on the status of the LOA.
June 7, 2007
14.
Host Nation LOA dated April 25, 2007 obtained.
Project unable to be re-submitted for validation under AMS
III.D. ver 11 due to expiry in methodology.
June 10, 2007
15.Rocky PDD, under the latest version of methodology AMS
III.D. ver 13, submitted for validation.September 5, 2007
16.Published for Global Stakeholder Consultation under
methodology AMS III.D. ver 13.September 7, 2007
17.Validation site visit conducted by DNV for project activity
under current methodology AMS III.D. ver 13.October 10, 2007
18.Project activity subsequently in validation up to latest revision
of this PDD dated 30th
September 2008.
November 2007 to
September 2008