22
Transport for London Surface Transport Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 1 of 22 Roads Directorate Hammersmith Flyover Emergency Preparedness Plan Status: Draft Version: V00e Date: 29 th Oct 2011

Roads Directorate Hammersmith Flyover Emergency

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 1 of 22

Roads Directorate  

Hammersmith Flyover  

Emergency Preparedness Plan               

Status: Draft Version: V00e Date: 29th Oct 2011

Page 2: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 2 of 22

 

BLANK PAGE

Page 3: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 3 of 22

  Distribution List  Role  Name  Organisation  Reference Structures Manager (Document Owner) 

Stephen Pottle Transport for London Master 

Director Roads Directorate Dana Skelley Transport for London  Interim Head of Tunnels & Structures 

Matthew Sercombe Transport for London  

Structures Technical Advisor  Ken Duguid Transport for London  Programme Manager – Hammersmith Flyover Strengthening Measures 

Chad Frankish Transport for London  

Project Manager  – Hammersmith Flyover Strengthening Measures 

Darren Bearwish Amey  

Head of Highway Operations  Andy Best  Transport for London  Senior Structures Route Manager 

Steve Eggleton Transport for London  

Head of Profession, Bridges and Structures 

Graham Bessant London Underground  

Traffic Management Unit, Hammersmith & Fulham 

Justin Bennett Metropolitan Police  

  Alex Gilbert Amey  HMWC Highways Operations Manager 

Andy Potts  Amey ‐ HMWC  

Director of Environment  Mahmood Siddiqi Borough of  ‐ Hammersmith and Fulham, and Kensington and Chelsea 

 

LSTCC Manager  Es George  Transport for London  LSTCC, Planned Events  Jason Diffenthal Transport for London  London Bus Operations – Hammersmith and Fulham 

Dave Leslie  Transport for London  

Development and Planning Manager, Consultation and Engagement 

Esther Johnson Transport for London  

Press and Media Relations Thomas Canning Transport for London  Works Co‐ordination ‐ North West Area 

Karl Kulasingam Transport for London  

Principal Network Impact Assessment Engineer 

Dele Olaleye Transport for London  

Regional Director  Amrit Ghose Aecom  Associate Director  Peter Sparkes Aecom       Date of Issue    Status DRAFT  

Page 4: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 4 of 22

Contents 1  Introduction 6 2  Background 6 3  Aim 7 4  Objectives 7 5  Roles and Responsibilities 8 6  Persons/Organisations to be informed when the plan is triggered 10 7  EPP Activation Procedure 10 8  Out of Office Hours 11 9  Operational Status & Trigger Levels 12 10  Operational Status ‐ Response 14 11  Traffic Management and Diversion Routes 16 12  Management of the Response and Response Organisation (Gold/Silver/Bronze) 17 13  Communications 18 14  Debriefing & Reporting 18 15  Supporting Documentation 19 

Reference Documents Ref. London Underground Emergency Preparedness Plan TfL Communications Strategy

Glossary AbbreviationEmergency Preparedness Plan EPP Highways Agency HA Highways and Maintenance Works Contract HMWC London Borough of Hammersmith and Fulham LB H&F London Borough of Kensington and Chelsea LB K&C London Emergency Service Liaison Panel LESLP London Streets Traffic Control Centre LSTCC London Streets and Tunnels Operations Centre LSTOC London Underground LU Major Incident and Response Recovery Process MIRRP Roads Directorate, TfL Surface Transport RD Transport for London TfL

Addenda Ref. Emergency Contact List

A

Page 5: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 5 of 22

Page 6: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 6 of 22

1 Introduction The Transport  for London  (TfL) Surface Transport, London Streets, Roads Directorate  (RD) has responsibility for the safe operation and maintenance of Hammersmith Flyover.  This document sets out the emergency preparedness plan (EPP) and actions required in the event of the Flyover no longer being able to carry the required loading.  The plan describes what actions shall be taken when various trigger points are reached and who is responsible for undertaking that action. 

2 Background 

Hammersmith Flyover was constructed c.1963 and  is a 16 span segmental post  tensioned structure carrying the A4 over the Hammersmith Gyratory. 

 A  3  stage  post  tensioned  special  inspection  and  structural  assessment  was  partially completed by the Highways Agency prior to transfer to TfL in 2000. A simplistic monitoring system was also  installed by  the HA. The outputs  from  this monitoring were  reviewed  in 2007 when management  of  the  structure was  brought  in  house.  It was  found  that  the system was  too  localised and  lacked  sensitivity. As a  result no meaningful  information or conclusions  could  be  obtained;  the  monitoring  was  stopped  and  TfL  commenced  new investigations. The  investigations  and  assessment was  completed  in 2009  and  found  that the  structure  was  adequate  to  carry  normal  highway  loading  up  to  and  including  40t vehicles, but does not have sufficient capacity to carry abnormal heavy loads. However, the spare capacity was found to be very low in some sections.  

 The main feature of concern is the ongoing deterioration of the post tensioning tendons. As they corrode and break the  likelihood of a sudden and catastrophic collapse of the flyover increases. This will mean that one or more spans will collapse with  little or no warning.  In the worst case this may  lead to a progressive collapse of half the bridge. The results  from the  investigations and assessment were used to determine what should be monitored and how, to help ascertain the rate of deterioration of the structure and inform decisions about when  and  what  further  action  may  be  required.  As  a  result  in  2010  a  comprehensive acoustic monitoring  system  was  installed  in  the  worse  half  the  bridge.  The monitoring system picks up events as they happen and analyses the sound print to filter out noise from those which are probable wire breaks. These sound prints are then compared with known patterns to ascertain which are confirmed as wire breaks and where they are located. A plan is  in  place  to  install monitoring  into  the Western  part  of  the  bridge  over  the  next  few months. 

 

Page 7: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 7 of 22

Recent  analysis  of  the  monitoring  systems  installed  in  the  flyover  has  shown  that  the structure  is deteriorating at a much  faster  rate  than previously anticipated. Based on  this new  knowledge  it  is  estimated  that  there  could  be  as  little  as  18  months  before Hammersmith Flyover  could become unsafe and potentially  collapse.  Immediate action  is therefore being taken to ensure the continued operation of the A4 over the flyover and the areas beneath.   The immediate plans are to install some form of temporary structure beneath the flyover or other works,  to  strengthen  it  and  prevent  the  likelihood  of  a  sudden  collapse,  however remote  the possibility. At  this stage  the details of  the  temporary structure have yet  to be determined.  It  is  likely  to  be  3‐4  months  before  construction  can  commence,  with completion  in  June 2012. Until  this  structure  is  in place  there  is a very  remote possibility that Hammersmith Flyover will collapse. This EPP will remain active until then.  

3 Aim The  aim  of  this  document  is  to  establish  the  framework  of  arrangements  for  effecting suitable  and  sufficient  responses when  pre‐determined  trigger  levels  are  reached which notify an increase in the level of risk and signify that collapse of the structure is likely.  

4 Objectives 

The principal objective  is to maintain public safety and prevent serious  injury or  loss of  life due to the full or partial collapse   The objective of this plan is to set out the management actions for Hammersmith Flyover by:  • Defining trigger points at which action should be taken. • Detailing the sequence of actions to be taken and who will undertake them. • Outlining the traffic management contingency measures in the event of a full or 

partial closure of the Flyover and the road network beneath the Flyover. • Providing details of the key contacts to facilitate a fast and coordinated approach to 

traffic management, in order to minimise disruption to the transport network as much as possible and prevent serious injury or fatalities. 

• Defining the key stakeholder and communications strategy which will need to be implemented in an emergency situation. 

  

   

Page 8: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 8 of 22

5 Roles and Responsibilities 

 Transport for London The role of TfL shall include but is not limited to: • Providing support to the emergency services where and when required  (i.e. within the 

incident containment, response and de‐escalation phases); • The implementation of recovery and return to normal service of affected assets; • Communication with media and stakeholders.  Director Roads Directorate The Director shall: • Make the final decision to implement the emergency response; • Advise senior management of the actions being taken; • Chair the emergency response panel; • Provide media and stakeholder briefings.  Structures Manager, London Streets The Structures Manager shall: • Ensure  that  the  EPP  is  developed  and  maintained  in  conjunction  with  internal  TfL 

stakeholders, the emergency services and affected Boroughs;  • Ensure  that  the  EPP  contains  details  of  local  communication  processes,  contact 

numbers,  reflect  local  conditions  and  include  relevant  information  that  will  assist responding agencies in delivering specific response arrangements; 

• Notify LU Head of Profession to initiate their own EPP; • Review  the outputs  from  the monitoring  data  to  determine when  trigger  points may 

be/have been reached; • Advise the Director of Roads when trigger points are approaching and the appropriate 

course of action to be taken; • Notify key stakeholders when the operational status of this EPP, as outlined in section 9, 

changes. • Ensure  that  TfL  Contractors  (HMWCs)  and  key  stakeholders  are  prepared  and  that 

sufficient materials and  resources are available and  capable of being deployed  to  the correct locations at short notice; 

• Prepare  in  conjunction with  the  press  office  and  communications  team  a  statement which can be issued immediately in the event of emergency action being necessary. 

 London Streets Traffic Control Centre (LSTCC) LSTCC shall: • Manage  the  LSTCC  Duties  and  Communication  Plan  as  included  and  detailed  in  the 

Major Incident Response and Recovery Policy (MIRRP); • Liaise with Structures Manager for updates; • Liaise with CentreComm (London Buses); • Notify and liaise with TfL Duty Press Liaison Officer; • Contact HMWC Operations Control Room; 

Page 9: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 9 of 22

• Confirm with Police to initiate Emergency Service Response; • Inform any other London Streets Senior Managers of incidents and effect on TLRN; • Inform the Public (via VMS on TfL and HA roads, TfL Press and Website) of incident effect 

on TLRN; • Inform Hammersmith and Fulham of effect on their borough roads.  HMWC Operations Control Room • Will contact the on‐call TfL Structures Engineer and the on‐call TfL Highways Engineer  London Underground London Underground shall: • Implement their emergency incident response as set out in their own EPP  London Buses London Buses shall: • London Buses shall be  responsible  for  the development, maintenance, communication 

and delivery of an Emergency Response Plans relevant to their own service  Responding Agencies   • The  Emergency  Services  shall  be  responsible  for  the  development,  maintenance, 

communication and delivery of Emergency Response Plans relevant to their own service and for ensuring that these are developed, where necessary, considering the plans of TfL and other responding agencies.  

 Highway Maintenance Works Contractors The HMWCs shall: • Ensure that sufficient materials and resources are available and in the correct location to 

provide a rapid response when required. • Set out traffic management, exclusion zones and diversion routes. • Assist the emergency services as required.  Communication and Press The Press and Consultation and Engagement Team shall: • Pre‐prepare  responses  to  probable  key  questions  that  are  likely  to  asked  (by  press, 

media and members of public), as a result of changes in the flyover’s operational status (as identified in Section 13). 

• Once a press  release has been  issued ensure all other key stakeholders/organisations identified are contacted. 

• Keep  stakeholders/organisations  and media  regular  informed  once  the  actions  have been initiated. 

• Answer any questions that are received by customer services.  

Page 10: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 10 of 22

6 Persons/Organisations to be informed when the plan is triggered  

Once  it has been agreed with  the Director of Roads  that action  to safeguard  the public  is necessary,  the  following  people  and  organisations  shall  be  informed  so  that  they  can implement their necessary actions.  Persons/organisations to be notified immediately when the operational status of the flyover (as outlined in section 9) changes:  TfL Roles  Contact Director of Roads  Dana Skelley Head of Highways Operations  Andy Best Highways Operation Team Area Manager (for approach roads) 

Rob O’Rourke (Highways), Annette Kay (Structures) 

LSTCC Duty Manager  Esmon George  Chief Operating Officer, London Streets  Garrett Emmerson LU Head of Profession – Bridges and Structures  Graham Bessant  Head of Tunnels & Structures  Matthew Sercombe London Bus Operations Area Manager  Dave Leslie Duty Press Officer  Thomas Canning Consultation and Engagement Manager  Esther Johnson External to TfL Roles   HMWC –Operations Manager  Andy Potts Local Authorities –    LB H&F / K&C Director of Environment  Mahmood Siddiqi Project Manager ‐ Slip Road Re‐Alignment Works (LB H&F) 

Anvar  Alizadeh 

Highways Agency  TBC    

 In addition to the above; MP’s, Transport Organisations including BAA Heathrow, Hospitals, Entertainment Venus including Hammersmith Apollo, and Schools, as identified by the Consultation and Engagement team.  

7 EPP Activation Procedure 

 Possible wire break events  are  recorded  almost  instantaneously on  a dedicated  ‘Mistras’ website  (which  can  be  accessed  by  key members  of  project  team).    The  project  team members  are  also  instantly updated by  text message  and email  confirming  the  time  and location of these events.  These  events  are  then  analysed,  and  confirmed  as wire  breaks  or  as  non‐wire  breaks  – (interpretation report provided weekly by Aecom).  

Page 11: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 11 of 22

Significant  multiple  events  require  instant  analysis  from  Physical  Acoustics  Ltd,  and discussion  with  TfL  Streets  Technical  Approval’s  Manager,  Structures  Manager  London Streets, and Aecom’s Technical Assessment Team.    The response  to  these wire breaks and  the activation of  this EPP will be  instigated by  the Structures Manager,  London  Streets  based  on  pre‐determine  trigger  levels,  as  set  out  in section 9 of this document.  

8 Out of Office Hours 

Communications  between  members  of  Aecom’s  Technical  Assessment  Team,  Physical Acoustics Ltd. and Structures Manager, London Streets during out of office hours will be via mobile phone.  If a significant number of possible wire‐breaks are reported during out of office hours,  it  is the  responsibility  of  the  Structures  Manager,  London  Streets,  to  co‐ordinate  and communicates the satisfactory response according to the risk.  If the Structures Manager is for  whatever  reason  unavailable,  the  Technical  Approvals  Manager  for  Hammersmith Flyover will be responsible for the response.    

Page 12: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 12 of 22

9 Operational Status & Trigger Levels 

Whilst the EPP is activated, the situation with regard to the structural capacity and safety of the Hammersmith Flyover will continue to be recorded as per the monitoring regime.   The situation with regard to traffic restrictions on the Hammersmith Flyover will be dependant upon trigger levels and is summarised in Table 9.1.  

STATUS

TRIGGER LEVEL

ACTIONS REQUIRED

GREEN

The decay time at critical sections within the flyover is > than 6 months.

Continue to monitor.

AMBER

The decay time is < 6 month.

Prepare to install Emergency Strengthening / OR review Emergency Strengthening (if already installed).

RED

The decay time is < 1 month.

Install Emergency Strengthening / OR Prepare to reduce live loading/ OR Enhance Emergency Strengthening/ OR Further restrict live loading

BLACK

The decay time = 0

Reduce live loading/ OR close flyover / set up exclusion zone underneath and around flyover.

 Table 9.1 – Traffic restrictions with respect to trigger levels 

 This table will be continually reviewed and updated to ensure appropriate trigger levels for each pier are in place to accurately reflect the condition of the Flyover at critical locations.  The status of the flyover is fluid, and can change from green →amber etc. but equally if actions are taken to support the affected locations the operational status can change back from amber → green.  This is outlined in the flow chart below: 

Page 13: Roads Directorate Hammersmith Flyover Emergency

NO

Continue to Monitor

Review Emergency

Strengthening/ Load restrictions

Enhance Emergency

Strengthening

Further Restrict Live Loading

Close Flyover

Set up Exclusion Zone

NO NO

YES

Continue to Monitor

Prepare to Reduce Live

Loading

Reduce Live Loading

YES

YES

YES

Green (Decay time > 6

months)

Continue to Monitor

Prepare to Install Emergency

Strengthening

Amber (Decay time < 6

months)

Red (Decay time < 1

month)

Black (Decay time = 0)

Reduce Live Loading

Review Trigger Status

Install Emergency

Strengthening

NO

Operational Status

(Decay time Trigger Levels

Page 14: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 14 of 22

 

10 Operational Status ‐ Response 

 GREEN : Continue to Monitor

 Hammersmith Flyover remains fully operational and the roads above and below are open to traffic. Existing restrictions on the Flyover still apply.   Monitoring results continue to be reviewed daily by Aecom and TfL Structures and an interpretation of the condition of the Flyover is also issued on a daily basis. From the rate of deterioration of the post‐tensioning strands, the timescale for implementation of the trigger actions is determined.  In green status the decay time at which the require level of loading cannot be sustained is > 6 months.  OR: mitigation is in place to sustain the existing level of loading, and has increased the decay time at which the required level of loading cannot be sustained to > 6 months.  

AMBER : Prepare/ Or Review Hammersmith Flyover remains fully operational and the roads above and below are open to traffic. Existing restrictions on the Flyover still apply.   In amber status the decay time at which the require level of loading cannot be sustained is < 6 months.  OR: after mitigation measures the decay rate has again dropped to < 6 months.  Structures Manager, London Streets will notify key stakeholders including LU Head of Profession – Bridges and Structures and London Bus Operations, and LB H&F. 

RED : Install strengthening or/and Reduce Loading  In red status the decay time at which the required level of loading cannot be sustained is < 1 month.  The structure is nearing the point where any level of live loading 

Page 15: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 15 of 22

cannot be sustained and mitigation is in place.  OR: after mitigation measures the decay rate has again dropped to < 1 month.  Structures Manager, London Streets will notify LSTCC and the local Highway Authority, (LB H&F). Traffic signal changes and VMS signage will be implemented by both TfL and LB H&F to reduce disruption prior to traffic management arrangements on site.   Structures Manager, London Streets will instruct Highways Operations to implement lane restrictions, road closures and diversions in line with the proposed traffic management strategy for the RED status.  Structures Manager, London Streets will notify key stakeholders including LU Head of Profession – Bridges and Structures and London Bus Operations, and LB H&F  Stakeholder Communications will need to prepare their emergency communications protocol.    Monitoring results continue to be reviewed daily by Aecom and TfL Structures, and an interpretation of the condition of the Flyover is also issued on a daily basis. From the rate of deterioration of the post‐tensioning strands, the timescale for implementation of the BLACK trigger actions is determined. 

BLACK : Reduce Live Loading/ OR Close Flyover/ OR and Set up exclusion 

zone  In black status the decay time at which the require level of loading cannot be sustained has reached 0.  In this case live loading will be reduced on the flyover to increase improve the decay rates.  OR: after mitigation measures the decay rate has again dropped to 0.  In this case, the flyover will be closed to all traffic. From the rate of deterioration of the post‐tensioning strands, the timescale for collapse of the structure is determined. and setting up and exclusion zone underneath and surrounding the flyover will be prepared.  

Page 16: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 16 of 22

 Structures Manager, London Streets will notify LSTCC and the local Highway Authority, (LB H&F). Traffic signal changes and VMS signage will be implemented by both TfL and LB H&F to reduce disruption prior to traffic management arrangements on site.   Structures Manager, London Streets will instruct Highways Operations to implement lane restrictions, road closures and diversions in line with the proposed traffic management strategy for the BLACK status. An exclusion zone will be created by erecting a hoarding perimeter at a distance of 50m from the Flyover.   Structures Manager, London Streets will notify key stakeholders including LU Head of Profession – Bridges and Structures and London Bus Operations, and LB H&F.  Stakeholder Communications will need to engage the emergency communications protocol.    An emergency review meeting will be held to discuss controlling the collapse of the Flyover, measures for the removal of debris, reinstatement of the LB H&F roads beneath the flyover, and ultimately long term options for replacement will be agreed and approved.  

  

11 Traffic Management and Diversion Routes 

Traffic management will be provided by the HMWC as and when required, based on trigger levels and the associated operational status. This will  include roads where LB H&F are the Highway Authority due to the speed in which the HMWC can be deployed and the severity of the consequences if restrictions are not implemented as soon as required.  Diversion plans for each operational status will be finalised and key stakeholders consulted once  a  press  release  has  been  issued.  The Metropolitan  Police  Service  has  already  been briefed.     

Page 17: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 17 of 22

12 Management of the Response and Response Organisation (Gold/Silver/Bronze) 

The management of the TfL Streets response shall be undertaken in a similar format to that undertaken by  the Emergency  Services,  so  that  the  right people  are  communicating with each  other  at  the  right  levels.  Where  responsibilities  can  be  delegated  to  competent resources, this shall be done.  Hammersmith  Flyover’s emergency preparation plan  shall  contain  an up‐to‐date  contacts list  of  all  TfL  and HMWC  staff  responding  on  TfL’s  behalf  to  an  incident.  It  shall  be  the responsibility of the plan owner (Structures Manager, London Streets) to ensure that these details  are  maintained  and  all  changes  and/  or  amendments  are  communicated  to  all concerned parties.   TfL Streets Gold (Strategic) Response   The role of this group is to combine and direct resources towards the strategic management of  the  incident.  It  therefore  follows  that  this  group  sets  the  framework  of  policy within which the other two levels of the system operate.   This  response  is  likely  to  include  the  Managing  Director  Surface  Transport,  the  Chief Operating Officer  (COO) London Streets, the Director of Roads and the Head of Tunnels & Structures.  The Gold  Team will  be  supported  by  a  TfL  Surface  Communications  assigned internal Media Liaison Officer.  

 The roles & responsibilities of TfL Streets “Gold” response is detailed within TfL MIRRP.  TfL Streets Silver (Tactical) Response   This role defines the actual deployment and redeployment of resources in order to achieve the overall plan. The responsibility of those at the tactical or adroit level is to determine the priority and allocation of tasks, to plan and co‐ordinate when a task will be undertaken and to obtain resources as required. 

 This response is most likely to include the Head of Tunnels & Structures (who shall provide the  link  between  “Silver”  and  “Gold”),  and  the  HMWC  Contract Manager, Maintenance Services Manager and Schemes Manager.  TfL Streets Bronze (Operational) Response  Those at the operational level shall have responsibility for functions and areas as defined in relevant local response procedures/ 

 Although TfL & the HMWC may be called to assist the emergency services in their response to an  incident; the recovery and return of asset to use following the  incident will form the main  part  of  TfL’s  response  and will  therefore  require  the  largest  commitment  of  time, budget and resources.  

 

Page 18: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 18 of 22

13 Communications  

All  direct  communication  with  members  of  the  press  or  media  shall  be  undertaken  in consultation with/through the TfL Surface Communications Team and TfL Duty Press Officer. Official  statements  shall  be  agreed  by  the  Gold  Response  Team  before  release. Where practical,  the TfL Surface Communications Team  shall dispatch a  Liaison Officer  to attend the scene to assist the TfL Gold response.    It  is to be expected that when trigger points are reached and action  is taken, there will be immediate  interest  from  the press, media and members of  the public. The key questions that will provide the focus of their attention will be: • Who is to blame? • When did TfL discover the problem? • What did TfL do before it became a Critical Incident? • What TfL are doing now that it is a Critical Incident?  Those affected by the incident need to be reassured at an early stage that: • Everything reasonably practicable was in place in an effort to prevent  the incident 

in the first place; • TfL and its HMWC, in conjunction with the Emergency Services, have plans in place 

to assess and respond to the incident;  • TfL cares about what has occurred and  is doing everything reasonably practicable 

to remedy the situation.  Regular and  timely communication between each response  team shall  take place  in order for the Silver and Gold Response Teams to be able to prioritise and provide the appropriate response to the right location and the right time.  Pre‐prepared responses shall be produced and held by the communications team and will be issued to the press/media in the event of action being necessary.  All the communications are detailed specifically in the TfL Communications Strategy set out by the Consultation and Engagement Team.  

14 Debriefing & Reporting 

During  the Recovery Stage of  the  Incident  response,  the Gold Response Team will  initiate the  debriefing  and  reporting  for  the  Incident.  The  purpose  of  this  must  be  clearly communicated to all parties involved that it is not to assign responsibility for and actions or inactions, but to capture all relevant details regarding the development and response to the incident so that lessons can be learned, best practises shared, deficiencies identified and our organisational responses can, in future, be more robust in future.  Depending  upon  the  role  undertaken  in  responding  to  the  incident  and  the  numbers  of personnel involved, debriefing may be undertaken as a group or as individuals, but must be 

Page 19: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 19 of 22

mediated by an  impartial and un‐associated party, so that events are objectively captured and conflicts of interest and personal loyalties do not distort the findings.  The party conducting the debriefing must have the authority, whether implicit or delegated, to ask the necessary questions of the personnel being debriefed. It must be understood that the debrief  is to capture  information for the organisation to  learn from and that all parties (from Director to Trainee Operative) should fully participate for this to be effective.  In the event that evidence of misconduct comes to light through the debriefing process, the appropriate authorities should be notified and the individual/s concerned notified that they should seek legal counsel, if necessary.  Following  the publication of  the  EPP,  the  London  Streets  Structures Manager will ensure that the Hammersmith Flyover Risk Register is reviewed and updated.  

15 Supporting Documentation 

 This  document  refers  to  and  details  our  response  to  the  implementation  of  conditions outlined in the LESLP Major Incident Procedure (7th Edition) Manual. It is not the intention of TfL to duplicate the LESLP Manual through the production of this document, but to outline the TfL strategic response to the declaration of a Critical Incident on Hammersmith Flyover.      

Page 20: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 20 of 22

Addendums:    

Page 21: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 21 of 22

ADDENDUM A: Emergency Contact List

Name Title Telephone Mobile TfL Auto

TfL Roles

London Streets & Tunnel Ops Centre (LSTOC)

HMWC OperationalControl Room

Andy Best Head of Highways Operations

London Streets Traffic Control Centre LSTCC

Esmon George LSTCC Duty Manager

Dana Skelley Director of Roads

Garrett Emmerson Chief Operating Officer, London Streets

Graham Bessant LU Head of Profession – Bridges and Structures

Matthew Sercombe

Head of Tunnels and Structures

Dave Leslie Area Manager, Bus Operations

Thomas Canning Duty Press Officer

Esther Johnson Consultation and Engagement Manager

External to TfL Roles

Justin Bennett Hammersmith and Fulham/ Kensington and Chelsea Traffic Management Unit

Andy Potts Highways Operations Manager (Amey - HMWC)

Mahmood Siddiqi Borough of Hammersmith and Fulham and Kensington and Chelsea – Director of Environment

TBC Highways Agency

Page 22: Roads Directorate Hammersmith Flyover Emergency

Transport for London

Surface Transport

Emergency Preparedness Plan for Hammersmith Flyover (Version –Draft) Copyright © Transport for London Page 22 of 22

   

Project Team

Stephen Pottle

Structures Manager, London Streets

Ken Duguid Technical Approvals Manager

Darren Bearwish Amey - Strengthening Measures Project Manager

Chad Frankish TfL PMC – Programme Manager

Peter Sparkes Aecom – Associate Director –Technical Assessment Advisor for Acoustic Monitoring Results