RMR EXIT STRATEGY FOR B.M. DAVIS December 16, 2003. BILL BOJORQUEZ Director of Transmission Services. RMR UNITS. EXIT TIMELINES. B.M. DAVIS EXIT SCOPE OF WORK. Phase 1 (complete by January, 2005) Installation of series reactors on both lines between White Point and Nueces Bay - PowerPoint PPT Presentation

Citation preview

Page 1: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

1

RMR EXIT STRATEGY FOR B.M. DAVIS

December 16, 2003

BILL BOJORQUEZDirector of Transmission Services

Page 2: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

Fort Phantom

San Angelo

La Palma

Rio Pecos

G

G

G G

G

G

Bates

Laredo G

B. M. Davis 335 MWLa Palma 249 MWLaredo 172 MWBates 183 MWFort Phantom 202 MW San Angelo 102 MWRio Pecos 98 MWTotal: 1,341 MW

B. M. Davis

Fort Phantom

San Angelo

La Palma

Rio Pecos

G

G

G G

G

G

Bates

Laredo G

B. M. Davis 335 MWLa Palma 249 MWLaredo 172 MWBates 183 MWFort Phantom 202 MW San Angelo 102 MWRio Pecos 98 MWTotal: 1,341 MW

B. M. Davis

RMR UNITS

Page 3: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

EXIT TIMELINES

1,341 MWTOTAL

N/A172 MWLaredo

N/A183 MWBates

Dec. 2004335 MWB.M. Davis

Dec. 2005249 MWLa Palma

Dec. 2004202 MWFort Phantom

Summer 2004102 MWSan Angelo

November, 200398 MWRio Pecos

Est. Exit Timeline CapacityUnit

1,341 MWTOTAL

N/A172 MWLaredo

N/A183 MWBates

Dec. 2004335 MWB.M. Davis

Dec. 2005249 MWLa Palma

Dec. 2004202 MWFort Phantom

Summer 2004102 MWSan Angelo

November, 200398 MWRio Pecos

Est. Exit Timeline CapacityUnit

Page 4: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

B.M. DAVIS EXIT SCOPE OF WORK

Phase 1 (complete by January, 2005)• Installation of series reactors on both lines between

White Point and Nueces Bay • Terminate the Lon Hill to CCCP into the Weil substation • Cut in the Nueces Bay – Morris 138-kV line into the

Highway 9 line • Reconnect the Westside to Davis 138-kV line and install

two 28.8 MVAR capacitor banks at Weil, Westside and Airline substations

Phase 2 (complete by June, 2006)• Nelson Sharpe 345/138-kV substation on the south side

of the Corpus Christi at the crossing of Lon Hill to Rio Hondo 345-kV line and Alazan to Celanese 138 kV line

• 150-MVA 30-degree phase shifting transformer

Page 5: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

CORPUS SYSTEM,PHASE 1 ADDITIONS

Page 6: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

CORPUS SYSTEM,PHASE 1 ADDITIONS

Page 7: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

CORPUS SYSTEM,PHASE 1 ADDITIONS

Page 8: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

CORPUS SYSTEM,PHASE 1 ADDITIONS

Page 9: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

CORPUS SYSTEM,PHASE 1 ADDITIONS

Page 10: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

CORPUS SYSTEM,PHASE 2 ADDITIONS

Page 11: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

COST

TRANSMISSION ADDITIONS PHASE 1 & 2Total Capital Cost $33.3 MAnnual TCOS $ 6.7 M

ESTIMATED RMR COSTProjected Cost Net Uplift $22 M per year

Page 12: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

QUESTIONS/MOTION

• ERCOT Staff recommends that the Board approve the Phase 1 and 2 RMR Exit Strategy for B.M. Davis Unit No 1 as described in the RMR Exit document

Page 13: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003
Page 14: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

REJECTED OPTIONS

1. Original Nelson Sharpe Proposal w/ Two Series Reactors

2. Special Protection Schemes3. Seven Series Reactors4. Multiple 138kV Upgrades5. Nelson Sharpe with New 9-mile 345kV

line into Rodd Field

Page 15: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

APPROACH

• Staged approach to determine cost effective and timely transmission alternatives

• Near-term Alternatives: Upgrades to existing infrastructure that can be expedited − Do not require CCN− Can be completed in less than three years

• Long-term Alternatives: Future lines and system upgrades necessary to ensure that load is served reliably and without uneconomic RMR support

Page 16: RMR EXIT STRATEGY FOR  B.M. DAVIS December 16, 2003

OPEN PROCESS

• September 15, ERCOT hosted stakeholder meeting in Austin to review short-term RMR alternatives

• September 22, Stakeholders submitted comments to the short-term alternatives

• September 30, ERCOT issued a draft recommendation on RMR short-term exit strategies

• October 9, TAC voted in support of alternatives for Fort Phantom and La Palma

• October 10, Second stakeholder meeting:− Long-term alternatives for the Valley and Laredo and − Short-term alternatives for Corpus Christi

• November 21, ERCOT issues a revised draft exit strategy recommendation for B.M. Davis

• November 26, Stakeholder comments on B.M. Davis exit strategy

• December 4, TAC Support of Exit Strategy