Upload
orlando-lopes
View
222
Download
0
Embed Size (px)
Citation preview
7/21/2019 RM E Prestressing Basic Part1 EC
1/43
RM BridgeProfessional Engineering Software for Bridges of all Types
RM Bridge V8i
December 2011
TRAINING PRESTRESSING BASICANALYZER PART 1: EC
7/21/2019 RM E Prestressing Basic Part1 EC
2/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC I
Bentley Systems Austria
Contents
1
General ................................................................................................................... 1-1
1.1
Starting the Program ...................................................................................... 1-1
1.2
Subjects Covered in this Training .................................................................. 1-1
2
General Example Data ........................................................................................... 2-2
2.1
Structural Model ............................................................................................ 2-2
2.2
Cross-Section ................................................................................................. 2-5
2.3
Substructure ................................................................................................... 2-7
2.4
Pre-Stressed Tendon Layout for Internal Tendons ........................................ 2-8
3
Lesson 6: Analyzer ................................................................................................ 3-9
4
Lesson 6: Tendon Definitions .............................................................................. 4-11
4.1 Tendon Material Import ............................................................................... 4-11
4.2 Definition of Tendon Groups ....................................................................... 4-12
4.3 Assign the Tendon Group to the Elements .................................................. 4-13
4.4
Definition of the Cable Geometry ............................................................... 4-14
4.5 Definition of the Tendon Stressing Schedule .............................................. 4-17
5 Lesson 7: Load Management ............................................................................... 5-19
6 Lesson 8: Load Definitions .................................................................................. 6-21
6.1 Definition of Load Cases for Self Weight ................................................... 6-21
6.2 Definition of Load Cases for the Additional Loads ..................................... 6-23
6.3 Definition of Load Cases for Pre-Stressing ................................................. 6-24
6.4 Definition of Load Cases for the Creep and Shrinkage Effects ................... 6-25
7
Lesson 9: Definition of Construction Stage 1 ...................................................... 7-26
7.1
Creation of construction stages .................................................................... 7-26
7.2
First construction stage ................................................................................ 7-27
7.2.1
Activation ................................................................................................. 7-27
7.2.2
Schedule actinscalculations ................................................................. 7-27
8
Lesson 10: Definition of Construction Stage 2 ...................................................... 8-1
8.1
Element Activation ........................................................................................ 8-1
7/21/2019 RM E Prestressing Basic Part1 EC
3/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC II
Bentley Systems Austria
8.2
Calculation (Static) ........................................................................................ 8-1
9
Lesson 11: Definition of Construction Stage 3 ...................................................... 9-2
9.1
Element Activation ........................................................................................ 9-2
9.2
Calculation (Static) ........................................................................................ 9-2
10
Lesson 12: Definition of Final Stage (Creep) ...................................................... 10-3
10.1
Calculation (Static) ...................................................................................... 10-3
11 The Calculation .................................................................................................... 11-4
11.1 Calculation options ...................................................................................... 11-4
11.2 Special settings ............................................................................................ 11-5
12
Result presentation ............................................................................................... 12-7
12.1 Possibilities in presentation of results .......................................................... 12-7
12.2 Diagram creation via RM-Sets .................................................................... 12-8
7/21/2019 RM E Prestressing Basic Part1 EC
4/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 1-1
Bentley Systems Austria
1 GeneralThe understanding of basic definitions and concepts as given in the Getting Started ex-
ample is assumed in the following example.
The principles shown in the Getting Started example for Modeler and Analyzer:
Defining the structural model
Defining a tendon geometry
Defining loads
Defining a traffic loading case
Defining a construction schedule
Running the calculation
Viewing the results
Fiber stress check
Ultimate load check
Shear capacity check
1.1 Starting the Program
The program installation must be completed before any work can be started. The instal-
lation procedure automatically creates the following icon on the desktop:
To start the program, use the desktop icon or select the icon from the Windows Start
menu atAll Programs, Bentley.
1.2 Subjects Covered in this Training Detail modeling in Modeler (temperature points + pier and support conditions).
Load definition for three construction stages.
Traffic loading case definition in accordance with DIN.
Construction schedule definition for the three construction stages.
Making the structural analysis. Calculation result viewing.
Fiber stress check.
Ultimate load check.
Shear capacity check.
7/21/2019 RM E Prestressing Basic Part1 EC
5/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 2-2
Bentley Systems Austria
2 General Example DataIn this example, a three span bridge is presented with a hollow box girder. It is built
span by span in three construction stages.
Figure 2-1: 3D-view of the bridge.
The span widths of the pre-stressed concrete girder are 40m, 60 m and 40m. The heightof the box cross-section is variable along the curved bridge axis.
2.1 Structural Model
40m 60m 40m
10x4m 10x4m15x4m
A4A1 A2 A3
20m
Figure 2-2: Structural model.
System axis: Horizontal plan
1.Part: Straight Line: Station: 0-20 m
7/21/2019 RM E Prestressing Basic Part1 EC
6/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 2-3
Bentley Systems Austria
2.Part: Spiral: A=100, RENDE=200m: Station: 20-70 m
3.Part: Circle: R=200: Station: 70-140 m
System axis: Vertical plan1.Part: Line: dXabsolute=65m, dZabsolute= 1.083m Station: 0-65 m
2.Part: Line: dXdifference=75m, dZabsolute= -0.2924m Station: 65-140 m
Rounding with Insert parabola by intersection R=2000m
Pier at A2:Height: 20m (4 Elements each 5m).
Pier at A 3:Height: 20m (4 Elements each 5m).
Numbering system:
Node numbers (span) : 101-111-126-136Element numbers (span) : 101-110,111-125,126-135
Active elements:
Construction Stage 1: 101-113, 1100-1103, 1200-1204
Construction Stage 2: 114-128, 1300-1304
Construction Stage 3: 129-135, 1400-1403
7/21/2019 RM E Prestressing Basic Part1 EC
7/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 2-4
Bentley Systems Austria
10x4m
40m 60m 40m
10x4m 10x4m15x4m
A4A1A2
A3
40m
10x4m
A212m
40m 60m
15x4m
A1 A2 A3
Stage 1:
A1
Stage 2:
12m
Stage 3:
113
135
128
Figure 2-3: Construction stages.
Axis 1 Axis 2
1102
X
Z
1101
1402
1401
101-110
Axis 3 Axis 4
111-125 126-135
Figure 2-4: Support definition.
7/21/2019 RM E Prestressing Basic Part1 EC
8/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 2-5
Bentley Systems Austria
2.2 Cross-Section
Y
Z
13,0 m
6,5 m 6,5 m
3,00 m 3,00 m
5,0 m
0,20 m
1,50m1,50m
1,0m 1,0m
0,25m
h_cs_tab(sg)
d_bot_tab(sg)d_web_tab(sg)
0,40m
0,90 m
4,0m 4,0m
0,40m12,2 m
0,15 m
1,5m1,5m
2,00 m 2,00 m
Figure 2-5: Main girder cross -section.
Node 0Spring 1100
Node 1101 Spring 1102Spring 1101
Y
Z
AXIS 1
2,40m 2,40m
Node 101
Figure 2-6: Definition of bearings at axis 1.
7/21/2019 RM E Prestressing Basic Part1 EC
9/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 2-6
Bentley Systems Austria
Node 0
Spring 1400
Node 1401 Spring 1402Spring 1401
Y
Z
AXIS 4
2,40m 2,40m
Node 136
Figure 2-7: Definition of bearings at axis 4.
1.5m
Y
Z
5.0m
Figure 2-8: Pier cross-section.
7/21/2019 RM E Prestressing Basic Part1 EC
10/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 2-7
Bentley Systems Austria
Table 2-1: Spring constants.
Element CX [kN/m] CY [kN/m] CZ [kN/m] CMX [kNm] CMY [kNm] CMZ [kNm]
1100 1e8 1e8 1e8 1e8 1e8 1e81101 1e8 1e8
1102 1e8
1400 1e8 1e8 1e8 1e8 1e8 1e8
1401 1e8 1e8
1402 1e8
2.3 Substructure
seg2
Pier1
0
20m
Segment 1
Connection point
Start of segment 2
Axis 2
Connection point
1202
1203
Eccentric connection of the pierwith the main girder
1204
111 seg1
1201
seg2
Pier1
Figure 2-9: SubstructureAxis 2Pier 1 (Segment2).
0
20m
Segment 1
Connection point
Start of segment 3
Axis 3
Connection point
1302
1303
Eccentric connection of the pierwith the main girder
1304
126 seg1
1301
Seg3
Pier2
Seg3
Pier2
Figure 2-10: SubstructureAxis 2Pier 2 (Segment3).
7/21/2019 RM E Prestressing Basic Part1 EC
11/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 2-8
Bentley Systems Austria
2.4 Pre-Stressed Tendon Layout for Internal Tendons
Tendon 101Tendon 102
Tendon 103
Clearance 40cm from top Clearance 40cm from top
Clearance 20cm from bottom Clearance 20cm from bottomClearance 20cm from bottom
12 m16 m
140 m
12 m 18 m12 m
40m 40m60 m
12 m 18 m 12 m
101 123104 108 111 114 118 126 133 135129
16 m12 m
Figure 2-11: Tendon arrangement
span 1: 101 (12 tendons) Ac=16cm2, duct area Ah=50cm
2(Nodes 101-115)
span 2: 102 (18 tendons) Ac=16cm2, duct area Ah=50cm
2(Nodes 108-129)
span 3: 103 (12 tendons) Ac=16cm2, duct area Ah=50cm
2(Nodes 123-136)
7/21/2019 RM E Prestressing Basic Part1 EC
12/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 3-9
Bentley Systems Austria
3 Lesson 6: Analyzer
In the following chapters further inputs for the preparation of the project in Analyzer
will be shown and explained.
Before continue with the inputs it is recommended to recalculate the project the sys-
tem which was exported from the analyzer. This step is necessary because on the one
hand the data is with this checked and on the other hand this is needed for geometry
depended inputs (e.g.: referring to the centre of gravity at the definition of the tendon
geometry).
By clicking the Recalc button in the main input window (Analyzer) a new windowwith recalc options opens. For now only two recalc options should be activated
Cross-section calculation and Structural check. However, it is possible to leave the
default options. In this case there would come a warning that no stage is defined this
is just information that no stage was calculated because no stage (actions) is defined.
Figure 3-1: Recalculation window
After the calculation and refreshing of the 3D View (using free hand symbols or just s
small rotation of the system) also the statical model in the main window is updated (ec-
centricities, element axis, etc). By clicking the right mouse button view options (last
button in the menu) can be defined (f.e. cross-sections, element bodies, tendons, etc).
All structure data defined in Modeler and exported to Analyzer can be seen under Prop-
ertiesor Structurein Analyzer tree menu. Theoretically all these data can be modified.
7/21/2019 RM E Prestressing Basic Part1 EC
13/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 3-10
Bentley Systems Austria
However, note that after each export of the data fromModelerto theAnalyzer, the mod-ified structural data (those, coming from Modeler) are overwritten. In this case all the
modifications are lost and have to be done once again if they were not saved by TCL
export. In this case, if the data/modifications were properly saved into TCL, the TCL
can be imported and the data will be overwritten once again. Thats why is for perma-nent changes recommended to edit the structure in Modeler.
7/21/2019 RM E Prestressing Basic Part1 EC
14/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 4-11
Bentley Systems Austria
4 Lesson 6: Tendon Definitions
In the following chapter, the definition for the tendons will be done. In Modeler most of
the structure definitions are already done. The only structure definition which is missing
is the specification of the tendons layout and the according stressing procedure.
4.1 Tendon Material Import
To define a tendon correctly a material is needed. All material used in Modeler were
also exported to the Analyzer and are saved to the project database
(PropertiesMaterial). The Tendon material has to be imported manually.
To load the material properties go to Menu File Load Default Properties or to
tree menu Configuration Load Default Properties.
A new window opens.
In this window are the Materials (or Variables) copied from the program database (left
side of the window) to the project database (right side). There are different material
groups from which a certain material can be selected and copied to the project database.
Multiple selection of material is possible by using the space button.
Select appropriate material for pre-stressing (as it is shown in the figure below).
7/21/2019 RM E Prestressing Basic Part1 EC
15/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 4-12
Bentley Systems Austria
Figure 4-1: Load default propertiesimporting material to the project database.
4.2 Definition of Tendon Groups
The tendon geometry will be simplified so that all the tendons practically positioned in
the webs will grouped together and located in the middle of the cross-section. At that
principle and due to the three construction stages only three tendons have to be defined.
Further simplification will be done based on the fact that the tendons overlap each other
on some intervals. Thats why only one tendon geometry (master tendon) have to be
defined with the full 3D geometry over the whole length of the structure. Then the indi-
vidual tendon groups can be defined using the geometry of the master tendon. These
tendon groups are called slave tendons.
This procedure will be used mainly for preliminary designs where the tendon geometry
has to be designed. The advantage is that you can change the geometry of all tendon
groups by changing only the master tendon.
7/21/2019 RM E Prestressing Basic Part1 EC
16/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 4-13
Bentley Systems Austria
Open the list for the definition of tendons under Structure Tendons Ele-
ment Assignment.
Select the insert after button to open the input window for master ten-don and tendon group definition.
Input the data as shown in the table below.
Definition of
Tendon Groups
Structure Type Type - internal Type - internal Type - internal Type - internal
Tendongeometry
Master profile Slave profile Slave profile Slave profile
TendonsOrginal
Geometry- 1 1 1
TndNum 1 101 102 103
Element Assign-
mentMaterial
EN_Eurocode:
Strand-1640/1860
EN_Eurocode:
Strand-1640/1860
EN_Eurocode:
Strand-1640/1860
EN_Eurocode:
Strand-1640/1860
Top Table Number 1 12 18 12
At [m2] 0.0016 0.0016 0.0016 0.0016
Ad [m2] 0.0050 0.0050 0.0050 0.0050
Beta
[Deg/m]0.151 0.151 0.151 0.151
Friction 0.25 0.25 0.25 0.25
Descrip-
tionMaster cable
Prestressing
cable 101
Prestressing
cable 102
Prestressing
cable 103
Note: More detailed information about the individual entries in the input window can be found by cal l-
ing the program help (F1).
4.3 Assign the Tendon Group to the Elements
Now the elements have to be assigned to the tendons. By this action the program gets
the information through which elements the tendon goes.
Select the insert after button in the lower table to open the input window
The tendon groups are listed in the upper table and the elements to be assigned to the
selected tendon are displayed in the lower table.
Input the data using the information shown in the table below.
Input the Cable As-
signment
STRUCTURE TdNum 1 101 102 103
El from 101 101 108 123
TENDON DATA El to 135 113 128 135
El step 1 1 1 1
EL. ASSIGNMENT
Bottom table
7/21/2019 RM E Prestressing Basic Part1 EC
17/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 4-14
Bentley Systems Austria
4.4 Definition of the Cable GeometryNow the actual geometry of the tendon will be defined. As already mentioned above, in
this example will be only the geometry of the master tendon defined. The salve tendons
will have the same geometry as the master tendon due to the definition above (slave
tendons with a reference to the master tendon).
Activate the master tendon in the upper list to start the definitions of the ten-
don geometry.
Select the info button between the upper and lower list.
The input window for the graphical tendon geometry definition will be opened. Please
note that the graphical screen will be empty if you havent recalculated the cross-
sections and the structure before. However, in this window the preview can be changed
between different views (CS view, elevation, plan, isometric and side elevation) where
can be graphically seen the defined input.
Figure 4-2: Tendon geometry input window with graphical overview.
7/21/2019 RM E Prestressing Basic Part1 EC
18/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 4-15
Bentley Systems Austria
Click the insert after button on the left bottom side of the screen to activate the
input field.
Define the tendon positions as it is shown in the table below.
The input for one tendon position is confirmed by clicking on the APPLY but-
ton.
Input the Cable
Geometry
STRUCTURE TdNum 1
Ref. Elem. 101 104 108 111 114
TENDON DATA CS pnt - SP-B - SP-T -
X/L 0 0 0 0 0
GEOMETRY eY[m] 0 0.2 0 -0.4 0
eZ[m] 0 0 0 0 0
Bottom table Rel. to Elem CS pnt Elem CS pnt Elem
Alfa1 Free Value Free Value Free
Value - 0 - 0 -
Alfa2 Free Value Free Value Free
Value - 0 - 0 -
Rel. to Elem Node Elem Node Elem
Extern
TdNum 1
Ref. Elem. 118 123 126 133 135
CS pnt SP-B - SP-T SP-B -
X/L 0.5 0 0 0 1
eY[m] 0.2 0 -0.4 0.2 0
eZ[m] 0 0 0 0 0
Rel. to CS pnt Elem CS pnt CS pnt Elem
Alfa1 Value Free Value Value Free
Value 0 - 0 0 -
Alfa2 Value Free Value Value Free
Value 0 - 0 0 -
Rel. to Node Elem Node Node Elem
Extern
The tendon definition for the master tendon is now completed and will be displayed in
the main graphic screen after calling redraw (freehand symbol V) or by rotating of the
system. The tendon profile is drawn in a turquoise color.
Note: More detailed information about the individual entries in the input window can be found by cal l-ing the program help (F1).
The different ways of referring are shown more detailed in the figures below.
7/21/2019 RM E Prestressing Basic Part1 EC
19/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 4-16
Bentley Systems Austria
CG
NODE
RP
Tendon position
CG
NODE
RP
Tendon position
CG
NODE
RP
Tendon position
ez e
y
ey
ez
ez
ey
Figure 4-3: Different references for the tendon positionsame tendon position but different eccentricities
and different reference points.
Figure 4-4: Different references for the angle Alpha1 the same applies for
7/21/2019 RM E Prestressing Basic Part1 EC
20/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 4-17
Bentley Systems Austria
Note: The reference point has to be created in Modeler (or even in Analyzer) and the Reference-Set hasto be of type Geometry Point or Stress Check Point.
The reference point itself can also vary along the bridge axis. And this possibility can be used to
define the tendon geometrysometimes it is the best approach. In the Analayzer there the tendon
has to be created and at the geometry definition the only thing that has to be defined is that the
tendon is in all elements relative to the reference point (with or without any eccentricity).
With finished tendon geometry definition of the master tendon also the geometry of the
slave tendons is defined the reference to the master tendon was defined and the ele-
ments were also assigned already.
To see the all tendons in the general 3D view the project has to be calculated at the
same principle as before starting with the tendon geometry definition (recalculation of
the cross-sections and structure check).
4.5 Definition of the Tendon Stressing Schedule
The tendon stressing actions are not defined in the stage directly but are defined sepa-
rately and are afterwards referenced. The tendon stressing procedure is defined under
Tendon Actions.
Select ScheduleStages Tendon Actions to start the stressing definitions.
All the actions that are applied to the tendons are defined in the two tables in this win-
dow. The top table lists all the actions applied to the tendons. The bottom table displays
details of the action for one tendon that is selected in the top table.In this window all the actions (pre-stressing, wedge slip, relaxation, etc) for certain ten-
don (group) are defined.
The Tendon 101 is stressed in the first construction sequence and can be stressed from
both sides. The Tendon 102 and 103 are stressed in the subsequent construction stages
stage 2 and stage 3. Due to practical capabilities of pre-stressing, these two cable can be
stressed only from the right side.
Note: The left and right side of the tendon is defined by the tendon orientationx coor-
dinates. The left side is there where the tendons stars and the right side is there where
the tendon endsor in another words XL < XR.
The stressing of the tendon can be defined by a force or by a factor, whereby the factor
references to the maximum allowable force in the tendon defined in the assigned ma-
terial (PropertiesMaterial).
Each tendon will be firstly for 5% overstressed and after this a wedge slip of 6 mm hap-
pens and so the stresses in the tendon are under the maximal allowable stress/force.
Define the tendon stressing actions as is shown in the tables below.
7/21/2019 RM E Prestressing Basic Part1 EC
21/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 4-18
Bentley Systems Austria
Input the TendonSchedule
SCHEDULE. STRESS/RELAX/WEDGE
PREL
WEDL
PRER
WEDRType FACT. - FACT. -
STAGES TENDON 101 101 101 101
Factor / Wedge [m] 1.05 0.006 1.05 0.006
TENDON ACT: Stress label STG1 STG 1 STG 1 STG 1
Top table
STRESS/RELAX/WEDGE PRER WEDR PRER WEDR
Type FACT. - FACT. -
TENDON 102 102 103 103
Factor / Wedge [m] 1.05 0.006 1.05 0.006
Stress label STG2 STG2 STG3 STG3
The stress label has to be defined for referencing to it (and so to the corresponding ten-
don actions) by the construction sequence definition.
By clicking the info button the stresses (and forces) in the tendon (selected by the
action) and up to the selected stressing action are graphically displayed.
Figure 4-5: Diagram of stresses and forces in the tendon after corresponding stressing action.
7/21/2019 RM E Prestressing Basic Part1 EC
22/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 5-19
Bentley Systems Austria
5 Lesson 7: Load Management
Load Management (Schedule Load Definition Load Management) is used for
automatic summation of permanent loads whereby certain load cases (loads) are (can
be) grouped together. For example the self weight from each construction sequences is
summed up to one load case (SW-SUM = SW-STG1 + SW-STG2 + SW-STGn).
In total the main capability of the load management is:
An individual loading case can be defined so that, after calculation, its resultsare automatically added to 1, 2 or 3 other load cases.
An individual loading case can be defined so that, after calculation, its resultsare automatically combined into 1, 2 or 3 envelopes.
Loading cases and envelopes defined in Load Management are set up (initialized;
created) using the LcInit function. Instead of using the LcInit function an automaticinitialization of the Load Management load cases can be done by activating the check
box Init Load Manager in the Recalc pad.
Define the Load Management as it is shown in the table below.
Input for the Load
Manager
Schedule Load Manag. SW SDL PT CS
Load case I SW-SUM SDL-SUM PT-SUM CS-SUMLoad Definition State Total Total Total Total
Load case II STG-SUM STG--SUM STG-SUM STG-SUM
Load Management State Total Total Total Total
Load case III - - - -
Top table State - - - -
Envelope I - - - -
Comb I - - - -
Envelope II - - - -
Comb II - - - -
Envelope III - - - -
Comb III - - - -
The load management can be also created by loading the appropriate load manager tem-
plate from Menu (Extras Loading and Stages Load Management Definitions
(English). The Load Manager for traveler load (TR), wet concrete load (WC) incremen-
tal launching method (ILM) and for cable loads (CABLE) can be deleted or ignored.
The final creep loading case is CS-SUM should not be added to the general loading case
as it is necessary to have the final creep and shrinkage effects separate so that the struc-
7/21/2019 RM E Prestressing Basic Part1 EC
23/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 5-20
Bentley Systems Austria
ture can be checked after construction (before final creep and shrinkage) with live load-ing and other loading combinations and at the time infinity with live loading and other
combination.
7/21/2019 RM E Prestressing Basic Part1 EC
24/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 6-21
Bentley Systems Austria
6 Lesson 8: Load Definitions
Loads are defined by Load Cases or by Load Sets ( Schedule Load Definition
Load Case Definition or Load Set Definition). Several loads can be combined into
one Load Case or also in one Load Set.
Load Set cannot be calculated directly and thats why they have to be assigned to the
Load Case. One Load Set can be assigned to different Load Cases. It is also possible to
define a different multiplication factor for the loads defined in the Load Set.
With creating a load case the defined load is not calculated. The load is calculated with
the calc action in the schedule actions.
In this example the loads will be defined only in the load cases.
6.1 Definition of Load Cases for Self Weight
The bridge is build in three construction stages and thats why also three separate self
weight load cases have to be created and each of them has to be calculated in corres-
ponding stage.
Change into Schedule Load Definition Load Case DefinitionTop Table
The window is split into two lists. At the top the load cases are listed and in the bottomlist the defined loads for the selected load case are listed.
Define the self weight load cases as is shown in the table below.
Definition of LoadCases
Schedule Name SW-STG1 SW-STG2 SW-STG3
Type Permanent Permanent Permanent
Load CaseDefini-
tionLoad Manag. SW SW SW
DescriptionSelf weight 1st
construction
stage
Self weight 2ndconstruction
stage
Self weight 3rdconstruction
stage
Top table
The type of the load case (Duration type: Permanent or Non-Permanent) defines if the
load is permanent or notwill it be considered in the calculation of creep and shrinkage
effects or not.
The input Load Manag. establishes the connection to the Load Manager. At that
principle now all the results due to the self weight loads (SW-STG1, SW-STG2 and
7/21/2019 RM E Prestressing Basic Part1 EC
25/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 6-22
Bentley Systems Austria
SW-STG3) will be saved/copied (superposed) to two load cases defined in the loadmanagerSW-SUM and STG-SUM.
The load cases were created and now actual loads have to be defined.
Change into Schedule Load Definition Load Case Definition Bottom
Table
The load type to be used in this example is Self weig just as load or Self
weightload and mass
Definition of LoadCases
Schedule. Number SW-STG1 SW-STG2 SW-STG3
Loading
Uni-
form load
Uni-
form load
Uni-
form load
Uni-
form load
Uni-
form loadLoad Case Defini-
tionType
Self
weight
Self
weight
Self
weight
Self
weight
Self
weight
From 101 1201 114 1301 129
Bottom table To 113 1204 128 1304 135
Step 1 1 1 1 1
Rx 0 0 0 0 0
Ry -1 -1 -1 -1 -1
Rz 0 0 0 0 0
Gam
[kN/m3]0 0 0 0 0
If gamma is set to 0 then the specific weight used in the calculation of the self weight istaken from the one assigned to the element via the assigned material (see Structure
Elements Material or Properties Material data). If the values is defined (and is
unequal zero) then this values is taken as specific weight and used in the calculations.
In the load cases SW-STG1 and SW-STG2 also the self weight of the piers has to be
defined.
Note: For faster and easier definition of the load cases it would be possible to defined first one load case
and the load for it. Afterwards, the subsequent load cases could be created by copying, renaming
and renumbering of the first load case.
Another approach would be: First to create one load case (top table) and activate the option
Load only elements, activated in current stage and then in the definition of the load (bottom ta-ble) define/load all elements (stepwise: 101-135, 1201-1204 and 1301-1304; or at once: 101-1304) with the same load type. Afterwards that load case has to be copied twice (the total number
of the load cases has to be the same as the number of the construction stages in our case this
means three).
For detailed load description use program help (F1) or the Appendix where all load types areexplained.
7/21/2019 RM E Prestressing Basic Part1 EC
26/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 6-23
Bentley Systems Austria
6.2 Definition of Load Cases for the Additional LoadsIn this example three different superimposed dead loads (left concrete barrier, right con-
crete barrier and road weigh) will be created and calculated. All of them will be defined
in one load case.
Also these loads have to be taken into account for the creep and shrinkage calculation
and have to be thats why set to permanent.
Insert Load Set
Schedule Name SDL
Type Permanent
Load Case Defini-
tion
Load Manag. SDL
Top table
Define Load Sets forthe Additional Loads
Schedule Number SDL SDL SDL
Loading Uniform load Uniform load Uniform load
Load Case Defini-
tionType
Uniform con-
centric elementload
Uniform eccen-
tric element load
Uniform eccen-
tric element load
From 101 101 101
Bottom table To 135 135 135
Step 1 1 1
Qx [kN/m] 0 0 0
Qy [kN/m] -35 -6.1 -6.1
Qz [kN/m] 0 0 0
Direction Global Global Global
Eccentricity -Local+Z
Elem-Ecc
Local+Z
Elem-Ecc
Ey [m] - 0 0
Ez [m] - +6.3 -6.3
Load applica-
tionReal length Real length Real length
DefinitionLoad/Unit
length
Load/Unitlength
Load/Unitlength
At the creation of the load case the link to the load management was defined at the same
principle as for the self weight load cases.
The Z-Element eccentricity defines the eccentricity length (in the Z-direction - transver-
sal) between the element/cross-section gravity centre to the node. At that principle it is
possible to define the eccentricity relative to the node (same applies for the definition of
the horizontal load). In our case there will be no difference due to the cross-sections
symmetry.
7/21/2019 RM E Prestressing Basic Part1 EC
27/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 6-24
Bentley Systems Austria
Ez
CG
Figure 6-1: Local Y-Element eccentricity.
6.3 Definition of Load Cases for Pre-Stressing
For now only the tendon geometry and tendon stressing procedure was defined. To ap-
ply the load on the structure load cases have to be defined also. Define the load cases as
it is shown in the table below.
Insert Load Set
Schedule Name PT-STG1 PT-STG2 PT-SRG3
Type Permanent Permanent Permanent
Load Case Defini-
tionLoad Manager. PT PT PT
Top table
Define Load Sets forthe Tendons
Schedule Number PT-STG1 PT-STG2 PT-STG3
Loading Stressing Stressing Stressing
Load Case Defini-tion
TypeTendon stress-
ingTendon stress-
ingTendon stress-
ing
From 101 102 103
Bottom table To 101 102 103
Step 1 1 1
TypeIncrement
Force
Increment
Force
Increment
Force
The selection of the type of stressing (Incremental-Force or Total-Force) has effect only
if multi-stage stressing procedure is defined. It must be defined whether the total stress-ing force of a stress level has to be applied or only the differential force when compared
to a previously applied stress group (for more information see the RM Analysis user
guide chapter 11.5.3).
7/21/2019 RM E Prestressing Basic Part1 EC
28/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 6-25
Bentley Systems Austria
6.4 Definition of Load Cases for the Creep and Shrinkage Ef-fects
Insert Load Case
Schedule Number CS-STG1 CS-STG2 CS-STG3 CS-INF
Type Permanent Permanent Permanent Permanent
Load Case Defini-
tionLoad Info CS CS CS -
Top table
Load cases for calculation of creep and shrinkage effects have to be just created noload definition (in the bottom table) has to be defined.
The definition of the load cases is done only because of the load management and post-
processingthe results of the calculation of the time effects (done by the creep action)
are saved to these load cases and accordingly to the load cases defined in load manage-
ment.
The creep and shrinkage load cases are linked to the load management at the same prin-
ciple as other load cases definition of the load management label/input (CS). Du to
that definition and the definition of the load management the creep and shrinkage results
are saved/copied to the CS-SUM load case and added to the STG-SUM load case.
The final creep and shrinkage effect (at time infinite CS-INF) are saved only to thatload case because there is no load management label defined for this load case. This has
to be done due to the combinations where different factors are used for time effects at
time 0 and time infinite.
7/21/2019 RM E Prestressing Basic Part1 EC
29/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 7-26
Bentley Systems Austria
7 Lesson 9: Definition of Construction Stage 1
The definition of the required definitions (structure including tendons, load cases and
tendon stressing procedure) for the construction sequence calculation is finished and the
definitions for the construction sequence calculation can start.
This definition is done underScheduleStages Activation orSchedule Actions.
In the top table a construction stage is created (and listed) and some basic definitions are
defined. The bottom table changes between theActivationsand Schedule Actions.
In the Activation table it is defined which elements are activated in the corresponding(construction) stagethe active elements becomes a part of active structural system and
can be loaded and included in the calculation.
In the Schedule Actions table it is defined which actions (static calculations, dynamic
calculations, plot actions, design actions, list actions, etc.) should be made in the corres-
ponding (construction) stage.
Construction stages have a time start and duration.
7.1 Creation of construction stages
Change to
Schedule
Stages
Activation Top table
Select the append button to open the input window for the construction stage
definition. Insert the construction stage named STG1 and the description
Construction Stage 1 here.
Use the same principle to add also other stages (as is shown in the table below)
Input Active Elements
to Stage 1
Schedule Name STG1 STG2 STG3 STG-FIN
DescriptionFirst con-struction
stage
Secondconstruction
stage
Thirdconstruction
stage
Final con-struction
stage
Stages
Activation
Bottom table
7/21/2019 RM E Prestressing Basic Part1 EC
30/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 7-27
Bentley Systems Austria
7.2 First construction stage
7.2.1 Activation
Change to ScheduleStagesActivation Bottom table
Select the append button to open the input window for element activation
Activate the elements as is shown in the table below.
Input Active Elementsfor Stage 1
Schedule Activate
Deactivate
Stages From 101 1201 1100 1200
To 113 1204 1102 1200
Activation Step 1 1 1 1
Age 14 42 0 0
Bottom table ts 0 0 0 0
Agedefines the ageof concrete when it is activated for the first time (becomes a part
of the structural system) and will be considered by the calculation of creep and shrin-
kage effects. The input tsdefines the time (after pouring the concrete) when shrin-
kage starts.
The spring elements have to be also activatedthey are representing the support condi-
tions.
7.2.2 Schedu le actins calculat ions
Input the Calcu-
lation (Static)
for Stage 1
Schedule ActionCalcu-
lation
(Static)
Calcu-lation
(Static)
Calcu-lation
(Static)
Calcu-lation
(Static)
Calcu-lation
(Static)
Loadcase
action
Type Calc Stress Calc GROUT Creep LcInit
StagesInp1
SW-STG1
- PT-STG1 - 1STG-SUM
Inp2 - STG1 - STG1 - -
Inp3 - - - - -
Schedule Actions Out1 - - - - CS-STG1STG1-
SUM
Out2 * * * - * -
Bottom table Delta-T 0 0 0 0 28 -
Calc is the actions which calculates a normal load case
Stressconverts the tendon forces, defined through the definition of the tendon stressing
actions, into loads whereby the corresponding elements are loaded. However, these
loads are not calculated jetthey are just converted.
These forces (pre-stressing effects) are calculated (applied on the structure) by the Calc
action which is the subsequent action, whereby the reference to the corresponding pre-
7/21/2019 RM E Prestressing Basic Part1 EC
31/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 7-28
Bentley Systems Austria
stressing load casehas to be definedStress Label STG1 and the Load Case PT-STG1are referencing to the same tendon.
Groutaction simulates grouting of tendon ducts and with this action the composite be-
haviour between the concrete elements (cross-section) and tendon is established (strain
in the tendon is equal to the strain of the corresponding elements).
Hereby also the cross-section values changes and these changes can be in the calcula-
tion properly taken into account. This is done by the definition of the recalculation op-
tions defined in the recalc pad (- duct areas, + tendon areas, - grouted areas). The new
cross-sections values are used in the global calculation and are also saved to the corres-
ponding list file (cross.lst).
With Creepaction the time effects are calculatedcreep and shrinkage of concrete andrelaxation of tendons. The corresponding functions for the calculation are predefined
(and can be modified) under Properties Variables and are assigned to the materials
under Properties Material Data. The time effects can be also graphically displayed
underResults Plot Creep/Shrinkage Curves.
Delta-T defines how long a certain system is exposed to the time effects time to the
next structural change or when an additional permanent load is added. The Number of
time steps (Input-1) defines in how many calculation intervals the howl time interval
(Delta-T) is subdivided, whereby it is possible that the subdivision step is linear or loga-
rithmic (Recalculation pad C+S). For smaller time intervals it is recommended to
use 1 time step and for longer time interval (for time infinitefinal creep) 3 to 5time (logarithmic) time steps. Each time step is saved to a separate load case and the
total effect is saved to the predefined dummy load case (Output-4).
For the calculation of relaxation (Include Steel relaxation recalculation option) the
summation load case has to be defined in the recalculation window (pad). This has to be
done to define which (permanent) loads have to be considered in the calculation.
With the Action LcInit (Load case In i tialization) certain load case can be copied or an
empty load case is created if there is no load case defined in the Input-1empty load
case is created (initialized).
In this example the summation load case (STG-SUM) is copied to a new one (STG1-
SUM) at the end of the construction stage. At that time are in the summation load case
all (calculated) loads from the first construction stage summarized (SW-STG1+PT-
STG1+CS-STG1) due to the definitions in load management. To see the results of the
loads in the first construction stage only, this has to be done, due to the automatic add-
ing of the results from the subsequent calculations, which will be defined in the second
construction stage.
The results of each calculation action are additionally saved also to a list file defined in
each action separately (definition of the Output-2).
7/21/2019 RM E Prestressing Basic Part1 EC
32/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 8-1
Bentley Systems Austria
8 Lesson 10: Definition of Construction Stage 2At the same principle also the activation and schedule actions in the second and third
construction stage have to be defined. Due to the analogy of the schedule actions the
howl construction stage could be copied and the definition accordingly modified. The
activations are not copied and have to be additionally defined accordingly to the active
system in the second construction stage.
Another way to define subsequent construction stages is to define (copy and modify)
them via TCL (here the data is exported, copied, modified and afterwards imported).
8.1 Element Activation
Input Active Elements
to Stage 2
Schedule Activate
Deactivate
Stages From 114 1300 1301
To 128 1300 1304
Activation Step 1 1 1
Age 14 0 42
Bottom table ts 0 0 0
8.2 Calculation (Static)
Input the Calculation(Static) for
Stage 2
Schedule ActionCalculation
(Static)
Calculation
(Static)
Calculation
(Static)
Calculation
(Static)
Type Calc Stress Calc GROUT
Stages Inp1 SW-STG2 - PT-STG2 STG2
Inp2 - STG2 - -
Inp3 - - -
Schedule Actions Out1 - - - -
Out2 * * * -
Bottom table Delta-T 0 0 0 0
ActionCalculation
(Static)Load case
action
Type Creep LcInit
Inp1 - STG-SUM
Inp2 1 -
Inp3 -
Out1 CS-STG2 STG2-SUM
Out2 - -
Delta-T 28 -
7/21/2019 RM E Prestressing Basic Part1 EC
33/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 9-2
Bentley Systems Austria
9 Lesson 11: Definition of Construction Stage 3
9.1 Element Activation
Input Active Elementsto Stage 3
Schedule Activate
Deactivate
Stages From 129 1400
To 135 1402
Activation Step 1 1
Age 14 0
Bottom table ts 0 0
9.2 Calculation (Static)
Input the Calculation
(Static) forStage 2
Schedule ActionCalculation
(Static)
Calculation
(Static)
Calculation
(Static)
Calculation
(Static)
Type Calc Stress Calc GROUT
Stages Inp1 SW-STG3 - PT- STG3 STG3
Inp2 - STG3 - -
Inp3 - - -
Schedule Actions Out1 - - - -
Out2 * * * -
Bottom table Delta-T 0 0 0 0
ActionCalculation
(Static)
Load case
action
Type Creep LcInit
Inp1 - STG-SUM
Inp2 1 -
Inp3 -
Out1 CS- STG3 STG3-SUM
Out2 - -
Delta-T 21 -
7/21/2019 RM E Prestressing Basic Part1 EC
34/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 10-3
Bentley Systems Austria
10 Lesson 12: Definition of Final Stage (Creep)
With the last construction stage the final state of the bridge will be simulated.
For this the super imposed dead loads will be applied on the structure and final time
effects will be calculatedt= (Delta-T=10000 days).
No additional element activation is necessary because the entire system is already act i-
vated.
10.1 Calculation (Static)
Input the Calcula-
tion (Static) forthe Final Stage
Schedule ActionCalculation
(Static)
Load caseaction
Load caseaction
Load caseaction
Type Calc Creep LcInit LcAddLc
Stages Inp1 SDL - STG-SUM CS-INF
Inp2 - 5 -STG-INF-
SUM
Inp3 - - - -
Schedule Actions Out1 - CS-INFSTG-INF-
SUM-
Out2 * * - -
Bottom table Delta-T - 10000 - -
In this stage first the superimposed dead loads are applied on the structure and then the
final time effects are calculated.
Because at the end two final load cases are needed including all construction e ffects
(loads) with and without final time effects. To have them two additional actions have to
be defined. After the calculation of the SDL loads the summation load cases is updated
(the SDL results are added to the STG-SUM load case) due to the definition of the load
management. After the Creepaction the summation load case (STG-SUM) is not up-
dated due to the definition of the CS-INF load casethe load case was not linked to
load management. Thats why first the summation load case is copied (LcInit actions)
and then the final time effects (CS-INF) are manually added (LcAddLc) to the copiedload case (STG-INF-SUM).
7/21/2019 RM E Prestressing Basic Part1 EC
35/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 11-4
Bentley Systems Austria
11 The CalculationThe construction stage definition is finished now and the first calculation can be done.
Click on theRecalcbutton .
Figure 11-1: Recalc pad.
11.1 Calculation options
Cross-section calculationCross-sections have to be calculated at least once. Hereby the file cross.lst is automati-
cally created. If the cross-section doesnt change(and were once already calculated) thisstep can be skipped.
Structure check
This calculation options checks the structure, deactivates all elements, initializes the
result database and creates a number of list files (material.lst, stress.lst, struct.lst and
tendon.lst)
7/21/2019 RM E Prestressing Basic Part1 EC
36/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 11-5
Bentley Systems Austria
If the system doesnt change also this option can be, in certain circumstances, skipped
in additional calculations (the calculation of the construction stages was done and all
stages are skipped; in this case also the optionInit Load Manger has to be turned off).
Note that the envelope files (*.sup) are saved to the main directory (and not the
sub-directoryDefaultSchedule) and are not automatically initialized (only by the SupI-
nit action in the schedule actions). The same fallows for the list (*.list), plot (*.pl and*.pla) and influence (*infl) files which are create/overwritten by the calculation.
With the action GoDel (Group System commands) it is possible to delete the corres-
ponding files in the main working directory as same as in the sub directory. This is rec-
ommended to do to ensure that no files from previous calculations remain.
Stage Calculation
Activation and calculation of the schedule actions in the constructions stages is done.
Influence-lines calculation
Influence lines have to be calculated at least once to make a live load calculation. If the
influence lines data exists (*.infl) and the structure or lane definition was not changed,
this options can be skipped for additional calculations.
Note: For now this option is not needed jet but can be activated.
Time Effects (C+S+Rel.)
To calculate the time effects this option has to be activated, irrespective that creep ac-
tions in schedule actions are defined. This allows making fast calculations, without in-
cluding time effects, very easily.
Include Steel Relexation
The relaxation of pre-stressing steel is also calculated at the calculation of creep and
shrinkage if this option is activated and the summation load case is defined.
Init Load Manager
Before starting with the calculation of the stages all load cases and envelopes defined in
load management are initialized (created).
11.2 Special settingsCross-section correction
This option activates the calculation of the new cross-section values due to the tendons
in it as it explained in7.2.2.
SumLC (summation load case)
Definition of the summation load cases of permanent loads, which is used for different
calculations (Steel relaxation, camber calculation, etc).
7/21/2019 RM E Prestressing Basic Part1 EC
37/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 11-6
Bentley Systems Austria
It is used also as a Initial Strain load case if the input of certain standard depended de-
sign checks (seePre-Stressing Training ExampleAnalyzer Part II) references to it.
Calculation
By clicking on theRecalcbutton (in the recalc pad) the recalculation of the active sche-
dule starts. By clicking on theRecalc allbutton all schedule variants will be successive-
ly calculated depending on the defined sequence.
Note: Schedule variants can be defined under Schedule Schedule Variants. Here it is possible to
define different construction variants (construction schedules) at the same system and in the same
project (folder) whereby each variant is saved to its own subfolder.
The calculation status can be seen in the lower windows when the calculation is run-
ning. The status shows which stage, which action and which calculation steps are cur-rently calculated. If in the schedule also plot actions are defined, then the generated
plots are displayed in the main window (4 at once) also.
A calculation protocol is created (recalc.log) and saved to theDefaultSchedule (if more
schedules are calculated the protocol is saved to the corresponding folder) as text file. Ii
is possible to open in from there or by clicking the corresponding button in the program
itself.
During the calculation warnings and errors can occur. The warnings are displayed at the
end of the calculation (e.g.: WARNING: System important files(s) cross.lst cannot be
deleted!)and should be interpreted as hints which should be checked. On the other hand
the calculation is aborted automatically if the definition is incorrect (the calculationcant proceed)ERROR (e.g.: in the schedule actions a load case wants to be calcu-
lated but wasnt created; or the name of the created and calculated load case isnt the
same; in this case the calculation is aborted and an error is displayed; ERROR: Load
case name of the LC does not exist.). Where the calculation stopped can be also seen
in the schedule actions listthose stages (top list) and actions (bottom list) which were
calculated have an OKin the status column.
A running calculation can be aborted also by the user by clicking on the ESC button.
The calculations starts (depending on the calculation options) with the calculation of the
cross-section values and structure control and then the initialization of load manger
(load cases) is done. Thereafter the construction sequence calculation starts where thestages are consecutive calculated, whereby at begin of each stage first the elements are
activated and then each stage action is calculated.
7/21/2019 RM E Prestressing Basic Part1 EC
38/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 12-7
Bentley Systems Austria
12 Result presentationIn RM Bridge there is possible to represents the results at different ways. Some of them
are more detailed explained below.
12.1 Possibilities in presentation of results
One of the possibilities to see the results is via Results Load Cases / Envelopes
(Influence lines, etc). Here certain result presentation options have to be defined:
Load case / Envelope; Element Group (if created); Result component (Displacements,
Forces, Stresses); etc. Once this is defined is possible to export the results to a list file
(Print) or to make a diagram (Diagram). By clicking on the Diagram button a new win-
dow opens where additional definitions have to done and once also this is finished the
diagram is created by clicking on the OK button.
Another possibility (with the same approach as above) to create a digram is by the defi-
nition of so calledRmSets. This approach will be more detailed explained in next chap-
ter.
The post processing can be done also with Plot Containers which are created under
Results Plot Conatiners and have to be plotted by the DoPLot actions in schedule
actions. Here not only results can be displayed but the structure itself also. The ap-
proach allows completely free design of the graphical output. The predefined Macros
facilitate the rapid generation (for more information see the RM Analysis User Guide
chapter 8.4.2).
Many predefined plots (e.g.: tendon scheme, tendon geometry, cross-sections, materialdiagrams, creep and shrinkage diagrams, load sets, etc) can be referenced directly in
schedule actions (List/Plot Actions) and plotted by recalculation of the project or only
by this actions (clickRun actionon the left side between the top and bottom list).
A comprehensive presentation (output) of structural data via cad files (DGN or DWG)
is possible withinDraw Manager(ExtrasRM Draw Manager).
Reports can be created within TDF-Reports (File Reports (TDF) Create/Edit
Structure).
An overview of schedule actions defined in each stage can be done by the HTML Stage
Viewer (Extras HTMLStage Viewer).
7/21/2019 RM E Prestressing Basic Part1 EC
39/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 12-8
Bentley Systems Austria
12.2 Diagram creation via RM-Sets
Go to PropertiesRM-Sets Top table(list)
Click on the insert after button and define a name of RM-Set. It is possible to de-
fine the description also which will be seen in the created diagram. The type of
RM-Set is Result representation (RESULT).
Figure 12-1: New RM-Set.
After confirming the input by clicking on the OK button the window for the de-
finition of the diagram is opened by clicking on the i button.
Here are several tabs for the definition of the diagram. There are two tabs for the gener-al definitions (scale, paper size, paper orientation, etc) and three other for different re-
sult presentations:
Load Case results
Envelope results
Reinforcement
Normally the correct definition of a diagram (RM-Sets) has to include the definition of
the elements for which the results should be represented and what results should be
represented which includes
definition of the load case / envelope / reinforcement
definition of the result component (bending moment, normal force, shear
force, etc.) / leading superposition value (MinMz, MaxMz, MinQy,
MaxQ, MinNx, MaxNx, etc) and a result component / attribute set
If different result components are defined in one RM-Set the program will automatically
create more diagrams. Same fallows also for the different types of reinforcements
(Attribute Sets)
7/21/2019 RM E Prestressing Basic Part1 EC
40/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 12-9
Bentley Systems Austria
Change to the tab Elements.
Define the elements for which the results should be displayed as is shown in the
pictures below.
Figure 12-2: Definition of elements for which the diagram should be shown.
The approach used above uses the predefined element groups which were created al-
ready in modeler (they could be also created/modified in Analyzer). The sane could be
achieved on a different way which is shown in the picture belowhere the elements are
selected by the definition of an element series.
1. Type of referencing to elements
2. Definition of elements
3. Confirming the input
7/21/2019 RM E Prestressing Basic Part1 EC
41/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 12-10
Bentley Systems Austria
Figure 12-3: Definition of elements for which the diagram should be shown.
Change to the tab Load Cases.
Define the Load case for which the results should be displayed as is shown in
the picture below. Parallel also the results component is defined.
7/21/2019 RM E Prestressing Basic Part1 EC
42/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 12-11
Bentley Systems Austria
It would be possible to add (Insert after) for the same result component different load
cases or for the same load case different result component. Of course, a mixture of both
is also possible. In this case more diagrams would be created.
If the stresses should be displayed, it has to be defined where in the cross-section thestresses should be represented/calculated. This is done by the definition of additional
results parameters (dashed square)for stresses the stress point has to be chosen addi-
tionally.
The diagram can be displayed by clicking on the Plot to file button. The same data
can be exported also to list file (Report file) or to MS Excel (Write to XLS).
The definition of the RM-Set is confirmed by clicking on Save.
The created RM-Set/Diagram can be also seen under Results Plot RM-Sets.
1. Choosing of an Load Case
2. Definition of a result component
3. Confirming the input
7/21/2019 RM E Prestressing Basic Part1 EC
43/43
RM Bridge
Training Prestressing BasicANALYZERPart 1: EC 12-12
The diagram can be also plotted in the default schedule. This is done via DgmSet action.
At that principle it is possible to plot more diagrams with one RM-Set. As it was already
explained, the summation load case is after each calculation updated. Referring to it
within an RM-Set and plotting the RM-Set using the DgmSet action at different times
will produce different diagrams. But the name of the output file (plot file), defined inthe DgmSet action, has to be different (if not the diagrams are overwritten).
The plot files created at that principle are saved to the (DefaultSchedule). A fast access
to this directory is also possible under Results Plot Directory (DefaultSche-
dule).