Upload
surya892
View
237
Download
0
Embed Size (px)
Citation preview
8/13/2019 Rla Descriptive
1/22
Residual Life Assessment and Life Extension Programme in
Utility Boilers BHELs Experience
Dr V T Sathyanathan, M.E., Ph.D.
Additional General Manager / Research & Development
BHEL, Tiruchirappalli 620014
1.0 INTRODUCTION
Thermal power plants form the major portion of the installed capacity in our country
and , there always exist a wide gap between supply and demand of energy. To bridge
this gap , there is a need to set up new plants for which huge financial investments and
long gestation period is required . Indias thermal Power generation started in 1899
with small thermal power plant with stoker fired Boilers. We have then moved on to
30 MW, 60 MW, 110 MW, 200/210 MW and 500 MW unit rating in the last 2 to 3
decades. Indias power requirement is increasing at an exponential rate and is
expected that more than 1,50,000 MW of installed generation capacity will be
required by 2000 AD. This may need very high initial investment to the tune of a few
thousand corers. Combined with this huge financial requirement, the gestation
period for new units are still in the range of 24 to 36 months depending upon the
rating of the units. Hence, there is a need to look at our ageing units and get their
useful life extended. In India about 15 20 % of utility power generation can be taken
as power from captive power generation. Hence to meet the immediate power
demand, the attention is focussed on extending the useful life of ageing power plants .
Rehabilitation of ageing steam generators through life extension program is the most
cost effective method to achieve the extended useful life . The concept of Renovation
8/13/2019 Rla Descriptive
2/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
will help in minimising the gap between supply and demand to some extent.
Remaining life assessment of these units will help in identifying the critical areasthat need refurbishment / replacement , which when carried out will ensure reliable
operation.
Boilers normally designed for a specific life are capable to deliver an extended useful
life because of the conservatism built-in during design stage itself. Pressure part
components operating at high pressure and temperature are prone for service damageslike creep, fatigue or a combination of creep and fatigue. The assessment calls for
certain special techniques over and above the routine requirements like laboratory
analysis by doing destructive testing through sampling and Non- destructive
examination like Ultrasonics , Oxide scale thickness measurement etc., . Special
techniques as detection of hydrogen damage in waterwalls by attenuation method as
well as corrosion damage of pressure part components are employed on a need based
requirement, depending upon the operational history of specific unit.
Assessment programme will help in identifying the components that can be
considered for continued operation , components that need reexamination after
specific interval and components that require modification/replacement so that the
utility can plan life extension activity in a programmed and phased manner. This
enables the owner to stagger the investment necessary for such rehabilitation in cost-
economic way.
Units that have limitation in achieving full load can be specifically addressed in the
rehabilitation programme so as to regain the lost capacity. Certain state-of-the art
improvements in design could also be investigated for implementation to improve the
efficiency of the plant.
BHEL, as a premier Organisation in the Power Sector of India, through our rich
8/13/2019 Rla Descriptive
3/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
2.0 RESIDUAL LIFE ASSESSMENT STUDY
As we go into the details of pressure part life assessment, it is worth looking into
material damage mechanisms, which can cause pressure part failures and reduction in
life of the pressure parts.
Pressure parts deteriorate continuously during service due to time dependent
degradation mechanisms such as oxidation, corrosion, creep, fatigue and interactions
of the above. In actual practice, material damage results from interactions of two or
more of these failure causing mechanisms.
Long term overheating Thermal Fatigue
8/13/2019 Rla Descriptive
4/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
extent of damage to a component. Hence, independent study of each unit even in the
same station is a basic need to establish the precise status of each component.Various methods of measuring creep life assessment may be classified into two
categories.
- Method based on the operational history in which the expended life of a
component is examined on the basis of operational history and standard
material properties.- Methods based on post service examination and / or testing on the actual
component.
Precise operational data seldom available in practice. Moreover, as the lower bound
stress rupture properties are considered in the absence of precise knowledge of the
material data, operational history based approach leads to pessimistic life assessment.
However, such an exercise would be very useful in identifying the critical component
that require thorough scrutiny.
Post exposure test (PET) comprises of destructive and non-destructive techniques.
These methods require accessibility to the actual component and hence can be taken
up only during overhauls or planned outages.
Destructive test approaches are helpful in arriving at numerical estimates of remaining
useful life. In case of boiler components like superheater tubes destructive testing by
sampling can also be used since it is relatively easier to remove the samples and
reweld with spool pieces, as compared to the headers and steam pipes of boiler.
In case of thick walled components, it is advisable to combine all the NDT
approaches along with replication to study the surface metallography.
The various stepsadopted in pressure part life assessment in involve the following:
* Review of operational history of equipment.
* Anal sis of data records and maintenance/o erha l reports
8/13/2019 Rla Descriptive
5/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
2.1 Review of Operational History of equipment:
The operational history of the equipments/boiler is reviewed with reference tonumber and details of startup and shutdown, operational regimes maintained,
duration and extent of parameter escalation especially steam temperature and water
chemistry regimes. This information helps in identifying the extent of deviation
in operating condition from design and consequently the areas to be examined in
detail by destructive/non-destructive methods can be identified .
2.2 Analysis of Data Records and Maintenance / Overhaul Reports :
Observations during planned shutdown provide a wealth of information on
equipment condition / deterioration. Generally this information is utilized by the
maintenance planning division for preventive maintenance and replacement. History
cards covering replacements done during routine maintenance/forced outages
and planned overhauls will be reviewed so that current status of the unit is assessed
and equipment degradation trend formulated.
Analysis of the data along with design review helps in formulating the maintenance
strategy and also in deciding scope of detailed examination.
2.3 Analysis of Failure Records and Reports :
As the main aim of the life assessment study is to ascertain/ extend the life of
components designed with a finite life, the failure records are a basic source of
information for the study. Reports containing detailed metallurgical analysis will
help in evaluating the failures.
Marking up of pressure part failures in the arrangement drawing helps in
identifying the weaker areas. Analysis reports on premature failures can indicate
the deviations in operating conditions or design lacunas that need correction for
extending the life of the components.
2.4 Visual Examination :
Visual examination is carried out to assess material wastage due to oxidation,
erosion/ corrosion problems, fouling conditions of heat transfer surfaces, integrity of
8/13/2019 Rla Descriptive
6/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
2.5 Dimensional Measurements :
Essentially thickness and outside diameter measurements form the dimensionalmeasurements. Thickness measurements at critical areas give a measure of
thickness loss over the year due to erosion and corrosion. Outside diameter
measurements are generally employed to determine the swelling (bulging) due to
creep.
2.6 Non-Destructive Examination :
The following Non Destructive Examination ( NDE ) are normally carried out prior
to examination by replica technique.
2.6.1 Liquid Penetrant Examination :
This technique is adopted primarily for detection of cracks or crack like
discontinuities that are open to the surface of a part, like surface porosity, pitting, pin
holes and other weld defects. In principle, the liquid penetrant is applied to thesurface to be examined and allowed to enter into the discontinuities. All excess
penetrant is then removed, surface dried and the developer applied. The
developer serves both as a blotter to absorb the penetrant coming out by capillary
action and as a contrasting background to enhance the visibility of the indication.
2.6.2 Magnetic Particle Examination :
This technique is adopted for locating surface and sub-surface discontinuities like
seams, laps, quenching and grinding cracks and surface rupture occurring on welds.
This method is also used for detecting surface fatigue cracks developed during
service. Magnetic particle inspection helps to detect cracks and discontinuities
on or near the surface in ferromagnetic materials using dry magnetic particle
testing equipment. The testing is done by magnetising at least two mutually
perpendicular direction to ensure detection of defects in all possible orientations.
2.6.3 Ultra-sonic Testing :
By using high frequency sound waves the surface and sub surface flaws can be
detected. Cracks, laminations, shrinkages, cavities, flakes, pores and binding faults
that act as discontinuities in metal gas interfaces can also be easily detected
8/13/2019 Rla Descriptive
7/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
2.7.1 Waterwalls :
Waterwall tube samples will be removed from high heat flux zone for evaluatingthe deposit content and constituents of the deposits. Weight loss method is adopted
for calculating deposit content. The need for chemical cleaning will be decided
based on the deposit content and the constituents of the deposit.
The analysis report may include the need or otherwise for
chemical cleaning. Recommendation on solvent for ensuring the effective removal
of the deposit will also be included as per requirement.
2.7.2 Metallurgical Examination of High Temperature Tubes :
The tube samples removed from superheater will be analysed for any
metallurgical degradation in service. Transverse ring segments from the tubes
will be metallographically prepared and examined using light optical microscope up
to a magnification of 500 x.
Carbide morphology and distribution, presence of creep cavities, dimensional
evidence of creep bulging, and tube wall thinning will be evaluated. The oxidescale thickness on steam side surface will be measured and used in estimating the
extent of damage as also the general operating temperature for the running hours.
2.8 In-situ Metallography by Replica Technique :
The high temperature components in utilities when subjected to high stress for a
long time undergo steady changes in transformation of strengthening carbide
phases followed by creep cavitation. This is the beginning of creep or slow
plastic deformation leading to gradual bulging of pressure parts
8/13/2019 Rla Descriptive
8/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
The following three distinct stages of creep occur in several alloys. The first stage of
creep occurs in a short period which is transient. The second stage or steady state
creep occurs over a very long duration of several years. The metallurgical changeslike carbide transformation and dispersion occurs. In this stage formation of minute
creep voids along the grain boundary surfaces also accompanies creep deformation.
In the third stage of creep, the creep voids increase in number and size and get
oriented and connected. They generate micro cracks, and the micro cracks connect
themselves resulting in the initiation and growth of macro crack with sudden fracture
in some zones depending on the operating stress at that zone. The replication is the
technique adopted to obtain the microstructure 'in-situ' by nondestructive
metallography. This technique is used in areas where sample removal is difficult
and not viable on cost economic aspects. Figure 2 shows a pictorial representation of
taking replica.
. Figure 2 A pictorial representation of taking replica
As far as the thick walled components like headers and main steam line and hot reheat
lines are concerned, the replica taken are evaluated based on Wedel and Neubauer
classification.
2.9 Remnant Life Determination based on Accelerated Creep Rupture Testing
8/13/2019 Rla Descriptive
9/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
2.9.1 Parametric extrapolation:
Specimen from each sample tube will be subjected to a specified stress andtemperature. Time to rupture versus temperature will be plotted and the
extrapolation will be done for the operating temperature to decide the remaining
life.
The assumptions made in the above method are
a) Thickness variation is not considered and hence the operating stress is
assumed as uniform.
b) Metal temperature considered for extrapolation is assumed as constant and
metal temperature increase due to building of oxide scale over a period
is not accounted.
2.9.2 Application Of Life Fraction Technique :
The life fraction rule says that during creep the fractional reduction in life after time
t , at a given stress and temperature is t / tr , where tr is the time to rupture under
the same stress and temperature. The failure would occur when sum of the fractionsof life equals unity.
2.10 Remnant Life Calculation based on Service Temperature :
Tube samples removed from boiler are evaluated for microstructure classification
based on which the service temperature can be evaluated taking into consideration
the operating hours collected from the plant records.
Another method of estimating operating temperature is based on oxide scale
measurement. As steam passes through the tubes at high temperature, the metal
is oxidized. Knowing the operating hours and oxide thickness measured in mils, the
average temperature 't' is calculated .
2.10.1 Calculation of Remaining Life :
Assuming oxidation rates for a specific period , the average stress can be
calculated for the aging duration considered. With average stress value Larsen-
Miller parameter can be calculated for the particular material. With the Larsen-
Miller parameter rupture life can be calculated using metal temperature values.
Fraction of life consumed is the ratio of operating period divided by rupture
8/13/2019 Rla Descriptive
10/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
Total Number Of Boilers (As on July 2000)
Power BoilersIndustrial Boilers
BHEL Boilers
In India
In Abroad
Non BHEL BoilersIn India
In Abroad
127
7156
52
42
10
7575
-
The details of assessment and recommendations pertaining to specific three units are
discussed as case studies.
The first case study refers to a boiler supplied to a refinery which was taken up for
study when the unit had clocked about 150,000 hrs. of operation. The findings fromthe study revealed that except for replacement of outlet header of SH the remaining
components were found to be good for continued operation.
The second case study is relating to a reheat balanced draft unit which was taken up
for study after 130,000 hrs of operation. This unit had experienced frequent outages
on account of reheat system. The methodology and the scope was finalised based on
operational history. The findings from the study revealed that most of the
components were found to be good for continued operation and the anticipated life
can be achieved only with for part replacement of hot reheat header and reheater
coils.
The third case study is relating to a reheat, balanced draft unit which was taken up for
assessment when the unit has clocked 110,000 hrs. This unit had forced outages in
platen superheater and in economiser, because of which the utility had done
replacement of the above prior to study. Since this boiler had certain limitations inachieving the rated capacity and also there was a need to improve the boiler
efficiency, the rehabilitation proposal called for measures to take care of the above
aspects over and above the scope identified from the findings of remaining life
assessment study.
8/13/2019 Rla Descriptive
11/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
3.1.2 Field Study :
The non reheat boiler operating at temperature below 427 C was checked mainly forintegrity of welds and also for suitability of waterwalls and superheater coils for
continued operation. Though the components are designed for an operating
temperature below 427 C, replication was carried out at SH outlet header
considering the service hours to which the components have been subjected.
The study revealed that the condition of boiler drum , water walls and SH coils are
good enough for continued operation.
The secondary superheater outlet header when examined with fiberscope indicated
presence of ligament cracks in longitudinal section . Few ligaments on the left
extreme were only found to have cracks where as the other ligaments were found to
be having just initiation of cracks.
To bring back the unit in service, it was necessary to replace the header as the crack
size in few ligament locations were beyond acceptable limits. As the unit was nothaving readily a spare header for replacement, it was decided to partly remove the left
extreme portion of the header which had cracks in ligaments beyond acceptable level
and start the unit. The superheater coils pertaining to the removed portion were
retained in position in order to avoid any possible gas laning. The removed portion
of header material was analysed in Laboratory and the lab analysis indicated that the
ligament crack was due to corrosion fatigue. The typical inside view of the affected
header is given in figure-4.
8/13/2019 Rla Descriptive
12/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
3.1.3 Laboratory Analysis :The cut piece from SH outlet header was taken up for detailed analysis. The damage
in the ligament location was attributed to corrosion fatigue. Corrosion damage wasseen on inside surface of the header in other locations also. Though the replica taken
from the header parent metal location did not reveal any microstructure degradation,
the material was tested for tensile strength and yield strength which confirmed the
suitability of material for further operation. The hardness measurements carried out at
different locations confirmed no softening of material .
Considering the metallurgical condition of the header and also based on the above
laboratory results, it was decided to keep the unit in service for a limited period with
the old header till replacement is arranged.
The replacement decision was taken considering the corrosion damages seen on
steam side surface of the header which was mainly attributed to collection of
condensate during shut down. No drain provision was available in the original design
and hence the condensate gets collected during shutdown .
The new header supplied was provided with drain arrangement and the utility was
recommended to avoid any collection of condensate during prolonged planned
outage of the unit and also to maintain water regime as per suppliers
recommendation.
Thus the remaining life assessment study carried in the above unit indicated the
possibility for continued operation with the existing components and it was
necessary only to replace part of SH assemblies and the secondary SH outlet headerwith a new header .
3.2 CASE STUDY II.
A 140 MW reheat , balanced draft type unit was taken up for study after a service
period of 130,000 hours . The review of operational history indicated failures in cold
reheat header stub as well as in ligament locations of reheat outlet header. Thescope for assessment was finalised based on the failure history and on the outcome of
discussions with station authorities. The work scope for remaining life assessment
study covered the following.
Detection of hydrogen damage in water walls using attenuation principle.
8/13/2019 Rla Descriptive
13/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
4. Reheater Misalignment of coils and low remaining life
5. Cold RH Header Erosion in stub bends
6. Hot reheat header Ligament cracks particularly near the T piece.7. Desuperheater Enlargement of nozzle hole and also cracks in
the liner plates.
8. Piping No microstructure degradation
The boiler which was designed for a maximum evaporating capacity of 450 T/hr was
operating at lower load and with frequent failures in reheater. The deterioration in
calorific value of fuel was the reason for load limitation.
Visual inspection carried out on cold reheat header stubs showed rupture opening at
few locations particularly near bend region.
The ligament space at the header inside surface was checked using fiberscope and
cracks were seen in circumferential ligaments particularly near T piece. ( both sides )
Ultrasonic testing using pulse echo with angle beam probe was done for checking
the ligaments in other locations and for sizing the defect.
The other ligament locations were found to be free from service cracks. The replica
taken covering the weld and the heat affected zone location of the reheat outlet
header revealed that the header material had not undergone any micro structural
degradation. The decision to continue to operate with existing cracks in the ligament
location adjacent to the T piece was carefully done after evaluation of the crack size
and taking into consideration the duration required for arranging replacement.
The header pipe thickness nearer to T piece weld was lower as compared to T piecethickness. The increase in stress at this location is likely to cause an early damage and
any additional thermal stress due to mal functioning of spray system will aggravate
the situation. In view of this, spray system was checked. The reheat steam
temperature control was not proper because of damage to control valve seat.
Till replacement of affected portion of header is carried out, the utility was
recommended to take care of the following aspects.
The spray control valve was recommended for replacement with a new valve.
Thermocouples at cold reheat inlet header and outlet header were installed at critical
locations and the temperatures were recommended to be monitored to avoid undue
8/13/2019 Rla Descriptive
14/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
Thus with the remaining life assessment study done in this unit, the utility could plan
for life extension and the life extension programme for this unit could be done only
by part replacement of specific components as identified above thereby theinvestment required for life extension programme could be minimised.
3.3 CASE STUDY III
This case study covers the details of remaining life assessment done in one of the 110
MW units. The furnace construction was of refractory design, the air ingress in the
boiler was more and this was causing poor efficiency in operation. While formulating
the proposal for rehabilitation of this unit, this aspect was also taken into account.
Accordingly, the refurbishment programme included activities to improve boiler
efficiency and also the replacements necessary as identified in remaining life
assessment study
Evaporation - 375 TONS/HR.
SH design pressure - 139 KG/CM2
SH design temperature - 540 CMake - BHEL (Czech design)
Type - Balanced draft/Reheat
Service hours - 110,000.
The utility had carried out replacement of platen SH with modified design as the
unit experienced frequent tube failures in platens. Also the economiser located in
2nd pass was replaced with modified design to minimise failures on account of gas
side erosion.
The major findings from the RLA study are given below:
1. Boiler drum Existing drum found to be in good condition.
2. Water walls Bow observed in different locations.
3. SH & RH coils The SH & RH coils were found to have adequate
remaining life. Alignment disturbed.
4. Platen SH headers The common header connecting the branch headers
when examined by replication, was found to have
8/13/2019 Rla Descriptive
15/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
The following major recommendations were given.
Bowed water wall sections to be replaced
Platen common header along with stubs for connecting the branch headers to bereplaced. The details are shown in fig. 6
Alignment band provision for SH / RH coils.
To minimise air ingress, it was recommended to replace waterwalls, horizontal
pass and second pass with membrane / steam-cooled walls. ( Shown in thick line
in fig 5 )
Also existing slag crusher system for furnace bottom ash handling was
recommended for replacement with water impounded hopper to eliminate airingress.
4.0 BHELS Experience In Life Extension Programme
BHEL has been engaged in the design, manufacture and supply of boilers / steam
generators from its manufacturing unit at Tiruchirapalli, since 1963. The range of
boilers supplied by BHEL covers utility boilers from 30 - 500 MW capacities, and
also industrial boilers for Steel plants, Fertiliser plants, Paper industry, Sugar plants
etc. These boilers are capable of firing various fuels and industrial by-products like
black liquor, blast furnace gas, coke oven gas, Corex TM gas, bagasse, rice husk etc.
The design is based on the technical know-how obtained from various leaders in
international market as well that developed through in-house R&D efforts.
BHEL has been updating the boiler design over the years to suit our Indian conditions
as well as the deteriorating coal quality. BHEL is also updating the design of boilers,
by incorporating a number of state-of-the-art technologies and also utilising the
feedback from over 500 BHEL boilers in operation in the country and abroad. These
latest practices are adopted, wherever applicable, on the R&M packages proposed by
BHEL. The list of such major R&M packages carried out by BHEL for the boiler
proper (excluding ESP retrofit / augmentation) is given in Annexure 2. BHEL has
l i d fi / i f h 100 ESP f ili / i
8/13/2019 Rla Descriptive
16/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
Remaining Life Assessment plays a vital role . BHEL has gained vast experience in
this field and has rededicated itself to serve the customers by continuously updating
its technology.
5.0 References:
1. CBIP Publication no. 168 : Thermal Power Stations in India
2. Sri K. Rajendran & Dr V T Sathyanathan - BHELs Approach / Experience in
R&M of Boiler & Auxiliaries - Indian Institute of Plant Engineers Conference -
DIU - 1998
3. Dr. V T Sathyanathan & R Rajasekaran - Coal fired Boiler design for Reliability
and Maintainability - Indian Institute of Plant Engineers Conference - Madras
1994
4. P.Nagamanickam , K. Rajendran & Dr. V.T. Sathyanathan - Residual life
assessment of boilers - BHEL s experience - Conference on Residual lie
assessment NTPC, Korba 1999
5. N. Ayodhi - RLA Based Life Extension Programme: BHELs Experience In
Indian Utilities
6. Sri. A.M. Pagedar / CEA / Delhi - R&M of Thermal Units - Its economics -
LIPREX Seminar - Hyderabad
7. Dr V T Sathyanthan & K Sivaraman Residual Life Assessment and Renovation
& Modernisation for Major Equipments of Captive Power Plants BHEL Journal,
Vol. 21 No. 1, Feb. 2000.
8/13/2019 Rla Descriptive
17/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
ANNEXURE
BHELs Experience in Rehabilitation & Modernisation
OVERSEAS PROJECTS
Sl.
No.
Name of the
Customer
Name of the Power Station
and Capacity
Nature of Work Carried Out Remarks
01 Tenaga
NasionalBerhad,
Malaysia
i) TJPS Stage I
2 x 60 MWii) TJPS Stage II
2 x 60 MW
iii) TJPS Stage III
3 x 120 MW
Rehabilitation of boilers.
Rehabilitation of turbine and generator auxiliaries.
Replacement of total station controls and instrumentation with
microprocessor-based system.
Life assessment and extension survey.
Incorporation of natural gas firing facility in three 120 MW
boilers.
More than
GuaranteedEfficiency
achieved.
Power
consumption in
FD/ID Fans
achieved
02 Tenaga
Nasional
Berhad,
Malaysia
SIPS
2 x 120 MW Rehabilitation of boilers.
Rehabilitation of turbine and generator auxiliaries.
Replacement of total station controls and instrumentation with
microprocessor-based system.
Life assessment and extension survey.
Incorporation of natural gas firing facility in two 120 MW boilers.
--- do ---
03 TenagaNasional
Berhad,
Malaysia
Prai3 x 120 MW
Rehabilitation of boilers. Rehabilitation of turbine and generator auxiliaries.
Replacement of total station controls and instrumentation with
microprocessor-based system.
Life assessment and extension survey.
--- do ---
Dr V T Sathyanathan, M.E.., Ph.D.
BHEL, Trichy 62014
Page : 17/22
8/13/2019 Rla Descriptive
18/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
Sl.No.
Name of theCustomer
Name of the Power Stationand Capacity
Nature of Work Carried Out Remarks
04 General
Electric
Company,
Libya
Tripoli West TPS
60 MW boiler
(Stein Industrie, France,
make)
Replacement of all bowed waterwalls.
Replacement of superheaters, superheater supports.
Revamping of burners.
Revamping of ducts and insulation.
05 GeneralElectric
Company,
Libya
Bengazi8 x 160 t/hr boilers (Babcock
Company make)
Replacement of waterwalls. Replacement of refractory & insulation.
Replacement of burners.
Replacement of expansion bellows.
Servicing of soot blowers, valves, fuel pumping and heating
station.
Servicing of fans.
Replacement of APH elements and servicing.
Renovation of controls and instrumentation.
Chemical cleaning.
06 General
Electric
Company,
Libya
Zuera Desalination Plant
2 x 90 t/hr boilers
(IDRO, TERMICI, Italy,
make)
Replacement of waterwalls, bank tubes.
Replacement of insulation.
Replacement of economiser.
Servicing of valves, soot blowers.
Servicing of burners. Servicing of fans.
Revamping of controls and instrumentation.
Dr V T Sathyanathan, M.E.., Ph.D.
BHEL, Trichy 62014
Page : 18/22
8/13/2019 Rla Descriptive
19/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
Sl.No.
Name of theCustomer
Name of the Power Stationand Capacity
Nature of Work Carried Out Remarks
07 General
Electric
Company,
Libya
Dhama TPS
3 x 120 t/hr boilers (Babcock,
Germany, make)
Replacement of waterwalls.
Replacement of soot blowers.
Replacement of refractory and insulation.
Revamping of burners.
Servicing of valves.
Revamping of fuel system equipment.
Servicing of fans.
Servicing of airpreheaters and element replacement.
Chemical cleaning.
08 Bangladesh
Power
DevelopmentBoard,
Bangladesh
Siddhirganj
1 x 50 MW (225 t/hr boilers)
(CE, USA, make)
Replacement of complete furnace walls.
Replacement of complete bank tubes.
Replacement of superheater partly. Replacement of side waterwall headers.
Replacement of damaged burners.
Servicing of entire boiler including fan, APH, safety valves and
other valves.
Replacement of APH seals.
Replacement of refractory & insulation.
Replacement of water level indicator.
Replacement of part-duct and expansion joints.
Servicing of controls and instrumentation.
Chemical cleaning.
Dr V T Sathyanathan, M.E.., Ph.D.
BHEL, Trichy 62014
Page : 19/22
8/13/2019 Rla Descriptive
20/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
DOMESTIC PROJECTS
(During the period 1990 to 1999)
Sl.
No.
Name of the
Customer
Name of the Power
Station & Capacity
Nature of Work Carried Out Remarks
01 Neyveli
LigniteCorpn. Ltd.
(NLC)
4 x 50 MW
Unit nos. 2,3,4 & 5Boilers of Russian make
Complete pressure parts replacement (waterwalls,
economiser, downcomer, SH, SH headers, DESH, entireMS piping etc. about 350 tons).
All valves reconditioning / replacement.
All non-pressure parts renovation.
Measures for performance uprating/low capacity
restoration.
Unit loaded to 235 t/hr
(design 220 t/hr). Exit gas temperature
reduced from 190C to
140C.
02 Steel
Authority ofIndia Ltd
(SAIL)
Bokaro Steel Plant
3 x 220 t/hrUnit nos. 3,4 & 5
Boilers of Russian make
Pressure part replacement in waterwall, screen SH, Conv.
SH, (Platen SH, redesigned with material upgrades).
Burner performance uprating.
APH (tubular) performance improvement.
Other non-pressure parts renovation.
Metal temperature scanner system introduction.
Boiler loaded to full capacity.
03 Bihar State
ElectricityBoard
(BSEB)
Unit nos. 1-4 & 5-6
8x50 MW Boilers
Replacement of complete downcomer pipes.
Replacement of waterwall tubes partial. Replacement of superheater - modified design.
Replacement of economiser blocks - modified .
Replacement of main steam piping.
Replacement of airheater blocks.
Work under progress.
Dr V T Sathyanathan, M.E.., Ph.D.
BHEL, Trichy 62014
Page : 20/22
8/13/2019 Rla Descriptive
21/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
SlNo.
Name of theCustomer
Name of the PowerStation & Capacity
Nature of Work Carried Out Remarks
04 APSEB Kothagudem TPS
2 x 110 MW
Unit nos. 7 & 8
Exit gas temperature reduction by second pass pressure
parts redesign and replacement. About 50C gas
temperature reduction
achieved.
05 RSEB Kota TPS
2 x 110 MW
Unit nos. 1 & 2
Lost capacity restoration with fuel system upgrades
HEA ignitor introduction in place of eddy plate ignitor.
Full parameters achieved
since 1995.
06 TNEB Ennore
2 x 110 MW
Unit nos. 3 & 4
Complete pressure part re-engineering (tangent tube
waterwall to membrane tube waterwall).
Performance uprating (lost capacity restoration).
Work under progress.
07 SAIL Bhilai Steel Plant
2 x 150 t/hr
Boilers of Russianmake
Non pressure part renovation.
Total downcomer /upriser replacement
DESH replacement. SH headers replacement.
08 APSEB Kothagudem
2 x 110 MW
Unit nos. 5 & 6
Complete pressure part re-engineering (tangent tube
waterwall to membrane tube waterwall).
Performance uprating (lost capacity restoration).
Non pressure part renovation.
Work under progress.
09 HSEB Panipat TPS
4 x 110 MW
Unit nos. 1,2
Milling system capacity upgradation. Work under progress.
Dr V T Sathyanathan, M.E.., Ph.D.
BHEL, Trichy 62014
Page : 21/22
8/13/2019 Rla Descriptive
22/22
Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience
SlNo.
Name of theCustomer
Name of the PowerStation & Capacity
Nature of Work Carried Out Remarks
10 UPSEB Obra Unit no. 11
200 MW Mill capacity upgradation.
3rd PA fan introduction.
Airpreheater sector widening from 52to 70.
Lost capacity of boiler
restored.
11 SFC, Kota 2x90 T/Hr Boilers Lost capacity enhancement.
Higher size mill replacement.
Performance review for low-grade coal.
Capacity enhancement by
more than 15% carried out
successfully.
12 Gujarat
Narmada
Valley
Fertiliser
Corporation,
Bharuch
3x180 T/Hr VU 40
Boilers Fuel conversion additional gas firing facility.
Forced drain system for soot blowers (State-of-the-art
improvement).
Fuel conversion implemented
and successfully tested at full
load.
Forced drain system for soot
blowers supplied and
commissioned.13 IOC,
Mathura
3x150 T/Hr VU 40
Boilers Conversion of boiler for 100% natural gas firing. Conversion completed and
performance proved.
14 IOC, Haldia 3x125 T/Hr Boilers Low NOx burner retrofit. Burner retrofit completed and
working.
Dr V T Sathyanathan, M.E.., Ph.D.
BHEL, Trichy 62014
Page : 22/22