Rla Descriptive

Embed Size (px)

Citation preview

  • 8/13/2019 Rla Descriptive

    1/22

    Residual Life Assessment and Life Extension Programme in

    Utility Boilers BHELs Experience

    Dr V T Sathyanathan, M.E., Ph.D.

    Additional General Manager / Research & Development

    BHEL, Tiruchirappalli 620014

    1.0 INTRODUCTION

    Thermal power plants form the major portion of the installed capacity in our country

    and , there always exist a wide gap between supply and demand of energy. To bridge

    this gap , there is a need to set up new plants for which huge financial investments and

    long gestation period is required . Indias thermal Power generation started in 1899

    with small thermal power plant with stoker fired Boilers. We have then moved on to

    30 MW, 60 MW, 110 MW, 200/210 MW and 500 MW unit rating in the last 2 to 3

    decades. Indias power requirement is increasing at an exponential rate and is

    expected that more than 1,50,000 MW of installed generation capacity will be

    required by 2000 AD. This may need very high initial investment to the tune of a few

    thousand corers. Combined with this huge financial requirement, the gestation

    period for new units are still in the range of 24 to 36 months depending upon the

    rating of the units. Hence, there is a need to look at our ageing units and get their

    useful life extended. In India about 15 20 % of utility power generation can be taken

    as power from captive power generation. Hence to meet the immediate power

    demand, the attention is focussed on extending the useful life of ageing power plants .

    Rehabilitation of ageing steam generators through life extension program is the most

    cost effective method to achieve the extended useful life . The concept of Renovation

  • 8/13/2019 Rla Descriptive

    2/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    will help in minimising the gap between supply and demand to some extent.

    Remaining life assessment of these units will help in identifying the critical areasthat need refurbishment / replacement , which when carried out will ensure reliable

    operation.

    Boilers normally designed for a specific life are capable to deliver an extended useful

    life because of the conservatism built-in during design stage itself. Pressure part

    components operating at high pressure and temperature are prone for service damageslike creep, fatigue or a combination of creep and fatigue. The assessment calls for

    certain special techniques over and above the routine requirements like laboratory

    analysis by doing destructive testing through sampling and Non- destructive

    examination like Ultrasonics , Oxide scale thickness measurement etc., . Special

    techniques as detection of hydrogen damage in waterwalls by attenuation method as

    well as corrosion damage of pressure part components are employed on a need based

    requirement, depending upon the operational history of specific unit.

    Assessment programme will help in identifying the components that can be

    considered for continued operation , components that need reexamination after

    specific interval and components that require modification/replacement so that the

    utility can plan life extension activity in a programmed and phased manner. This

    enables the owner to stagger the investment necessary for such rehabilitation in cost-

    economic way.

    Units that have limitation in achieving full load can be specifically addressed in the

    rehabilitation programme so as to regain the lost capacity. Certain state-of-the art

    improvements in design could also be investigated for implementation to improve the

    efficiency of the plant.

    BHEL, as a premier Organisation in the Power Sector of India, through our rich

  • 8/13/2019 Rla Descriptive

    3/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    2.0 RESIDUAL LIFE ASSESSMENT STUDY

    As we go into the details of pressure part life assessment, it is worth looking into

    material damage mechanisms, which can cause pressure part failures and reduction in

    life of the pressure parts.

    Pressure parts deteriorate continuously during service due to time dependent

    degradation mechanisms such as oxidation, corrosion, creep, fatigue and interactions

    of the above. In actual practice, material damage results from interactions of two or

    more of these failure causing mechanisms.

    Long term overheating Thermal Fatigue

  • 8/13/2019 Rla Descriptive

    4/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    extent of damage to a component. Hence, independent study of each unit even in the

    same station is a basic need to establish the precise status of each component.Various methods of measuring creep life assessment may be classified into two

    categories.

    - Method based on the operational history in which the expended life of a

    component is examined on the basis of operational history and standard

    material properties.- Methods based on post service examination and / or testing on the actual

    component.

    Precise operational data seldom available in practice. Moreover, as the lower bound

    stress rupture properties are considered in the absence of precise knowledge of the

    material data, operational history based approach leads to pessimistic life assessment.

    However, such an exercise would be very useful in identifying the critical component

    that require thorough scrutiny.

    Post exposure test (PET) comprises of destructive and non-destructive techniques.

    These methods require accessibility to the actual component and hence can be taken

    up only during overhauls or planned outages.

    Destructive test approaches are helpful in arriving at numerical estimates of remaining

    useful life. In case of boiler components like superheater tubes destructive testing by

    sampling can also be used since it is relatively easier to remove the samples and

    reweld with spool pieces, as compared to the headers and steam pipes of boiler.

    In case of thick walled components, it is advisable to combine all the NDT

    approaches along with replication to study the surface metallography.

    The various stepsadopted in pressure part life assessment in involve the following:

    * Review of operational history of equipment.

    * Anal sis of data records and maintenance/o erha l reports

  • 8/13/2019 Rla Descriptive

    5/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    2.1 Review of Operational History of equipment:

    The operational history of the equipments/boiler is reviewed with reference tonumber and details of startup and shutdown, operational regimes maintained,

    duration and extent of parameter escalation especially steam temperature and water

    chemistry regimes. This information helps in identifying the extent of deviation

    in operating condition from design and consequently the areas to be examined in

    detail by destructive/non-destructive methods can be identified .

    2.2 Analysis of Data Records and Maintenance / Overhaul Reports :

    Observations during planned shutdown provide a wealth of information on

    equipment condition / deterioration. Generally this information is utilized by the

    maintenance planning division for preventive maintenance and replacement. History

    cards covering replacements done during routine maintenance/forced outages

    and planned overhauls will be reviewed so that current status of the unit is assessed

    and equipment degradation trend formulated.

    Analysis of the data along with design review helps in formulating the maintenance

    strategy and also in deciding scope of detailed examination.

    2.3 Analysis of Failure Records and Reports :

    As the main aim of the life assessment study is to ascertain/ extend the life of

    components designed with a finite life, the failure records are a basic source of

    information for the study. Reports containing detailed metallurgical analysis will

    help in evaluating the failures.

    Marking up of pressure part failures in the arrangement drawing helps in

    identifying the weaker areas. Analysis reports on premature failures can indicate

    the deviations in operating conditions or design lacunas that need correction for

    extending the life of the components.

    2.4 Visual Examination :

    Visual examination is carried out to assess material wastage due to oxidation,

    erosion/ corrosion problems, fouling conditions of heat transfer surfaces, integrity of

  • 8/13/2019 Rla Descriptive

    6/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    2.5 Dimensional Measurements :

    Essentially thickness and outside diameter measurements form the dimensionalmeasurements. Thickness measurements at critical areas give a measure of

    thickness loss over the year due to erosion and corrosion. Outside diameter

    measurements are generally employed to determine the swelling (bulging) due to

    creep.

    2.6 Non-Destructive Examination :

    The following Non Destructive Examination ( NDE ) are normally carried out prior

    to examination by replica technique.

    2.6.1 Liquid Penetrant Examination :

    This technique is adopted primarily for detection of cracks or crack like

    discontinuities that are open to the surface of a part, like surface porosity, pitting, pin

    holes and other weld defects. In principle, the liquid penetrant is applied to thesurface to be examined and allowed to enter into the discontinuities. All excess

    penetrant is then removed, surface dried and the developer applied. The

    developer serves both as a blotter to absorb the penetrant coming out by capillary

    action and as a contrasting background to enhance the visibility of the indication.

    2.6.2 Magnetic Particle Examination :

    This technique is adopted for locating surface and sub-surface discontinuities like

    seams, laps, quenching and grinding cracks and surface rupture occurring on welds.

    This method is also used for detecting surface fatigue cracks developed during

    service. Magnetic particle inspection helps to detect cracks and discontinuities

    on or near the surface in ferromagnetic materials using dry magnetic particle

    testing equipment. The testing is done by magnetising at least two mutually

    perpendicular direction to ensure detection of defects in all possible orientations.

    2.6.3 Ultra-sonic Testing :

    By using high frequency sound waves the surface and sub surface flaws can be

    detected. Cracks, laminations, shrinkages, cavities, flakes, pores and binding faults

    that act as discontinuities in metal gas interfaces can also be easily detected

  • 8/13/2019 Rla Descriptive

    7/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    2.7.1 Waterwalls :

    Waterwall tube samples will be removed from high heat flux zone for evaluatingthe deposit content and constituents of the deposits. Weight loss method is adopted

    for calculating deposit content. The need for chemical cleaning will be decided

    based on the deposit content and the constituents of the deposit.

    The analysis report may include the need or otherwise for

    chemical cleaning. Recommendation on solvent for ensuring the effective removal

    of the deposit will also be included as per requirement.

    2.7.2 Metallurgical Examination of High Temperature Tubes :

    The tube samples removed from superheater will be analysed for any

    metallurgical degradation in service. Transverse ring segments from the tubes

    will be metallographically prepared and examined using light optical microscope up

    to a magnification of 500 x.

    Carbide morphology and distribution, presence of creep cavities, dimensional

    evidence of creep bulging, and tube wall thinning will be evaluated. The oxidescale thickness on steam side surface will be measured and used in estimating the

    extent of damage as also the general operating temperature for the running hours.

    2.8 In-situ Metallography by Replica Technique :

    The high temperature components in utilities when subjected to high stress for a

    long time undergo steady changes in transformation of strengthening carbide

    phases followed by creep cavitation. This is the beginning of creep or slow

    plastic deformation leading to gradual bulging of pressure parts

  • 8/13/2019 Rla Descriptive

    8/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    The following three distinct stages of creep occur in several alloys. The first stage of

    creep occurs in a short period which is transient. The second stage or steady state

    creep occurs over a very long duration of several years. The metallurgical changeslike carbide transformation and dispersion occurs. In this stage formation of minute

    creep voids along the grain boundary surfaces also accompanies creep deformation.

    In the third stage of creep, the creep voids increase in number and size and get

    oriented and connected. They generate micro cracks, and the micro cracks connect

    themselves resulting in the initiation and growth of macro crack with sudden fracture

    in some zones depending on the operating stress at that zone. The replication is the

    technique adopted to obtain the microstructure 'in-situ' by nondestructive

    metallography. This technique is used in areas where sample removal is difficult

    and not viable on cost economic aspects. Figure 2 shows a pictorial representation of

    taking replica.

    . Figure 2 A pictorial representation of taking replica

    As far as the thick walled components like headers and main steam line and hot reheat

    lines are concerned, the replica taken are evaluated based on Wedel and Neubauer

    classification.

    2.9 Remnant Life Determination based on Accelerated Creep Rupture Testing

  • 8/13/2019 Rla Descriptive

    9/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    2.9.1 Parametric extrapolation:

    Specimen from each sample tube will be subjected to a specified stress andtemperature. Time to rupture versus temperature will be plotted and the

    extrapolation will be done for the operating temperature to decide the remaining

    life.

    The assumptions made in the above method are

    a) Thickness variation is not considered and hence the operating stress is

    assumed as uniform.

    b) Metal temperature considered for extrapolation is assumed as constant and

    metal temperature increase due to building of oxide scale over a period

    is not accounted.

    2.9.2 Application Of Life Fraction Technique :

    The life fraction rule says that during creep the fractional reduction in life after time

    t , at a given stress and temperature is t / tr , where tr is the time to rupture under

    the same stress and temperature. The failure would occur when sum of the fractionsof life equals unity.

    2.10 Remnant Life Calculation based on Service Temperature :

    Tube samples removed from boiler are evaluated for microstructure classification

    based on which the service temperature can be evaluated taking into consideration

    the operating hours collected from the plant records.

    Another method of estimating operating temperature is based on oxide scale

    measurement. As steam passes through the tubes at high temperature, the metal

    is oxidized. Knowing the operating hours and oxide thickness measured in mils, the

    average temperature 't' is calculated .

    2.10.1 Calculation of Remaining Life :

    Assuming oxidation rates for a specific period , the average stress can be

    calculated for the aging duration considered. With average stress value Larsen-

    Miller parameter can be calculated for the particular material. With the Larsen-

    Miller parameter rupture life can be calculated using metal temperature values.

    Fraction of life consumed is the ratio of operating period divided by rupture

  • 8/13/2019 Rla Descriptive

    10/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    Total Number Of Boilers (As on July 2000)

    Power BoilersIndustrial Boilers

    BHEL Boilers

    In India

    In Abroad

    Non BHEL BoilersIn India

    In Abroad

    127

    7156

    52

    42

    10

    7575

    -

    The details of assessment and recommendations pertaining to specific three units are

    discussed as case studies.

    The first case study refers to a boiler supplied to a refinery which was taken up for

    study when the unit had clocked about 150,000 hrs. of operation. The findings fromthe study revealed that except for replacement of outlet header of SH the remaining

    components were found to be good for continued operation.

    The second case study is relating to a reheat balanced draft unit which was taken up

    for study after 130,000 hrs of operation. This unit had experienced frequent outages

    on account of reheat system. The methodology and the scope was finalised based on

    operational history. The findings from the study revealed that most of the

    components were found to be good for continued operation and the anticipated life

    can be achieved only with for part replacement of hot reheat header and reheater

    coils.

    The third case study is relating to a reheat, balanced draft unit which was taken up for

    assessment when the unit has clocked 110,000 hrs. This unit had forced outages in

    platen superheater and in economiser, because of which the utility had done

    replacement of the above prior to study. Since this boiler had certain limitations inachieving the rated capacity and also there was a need to improve the boiler

    efficiency, the rehabilitation proposal called for measures to take care of the above

    aspects over and above the scope identified from the findings of remaining life

    assessment study.

  • 8/13/2019 Rla Descriptive

    11/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    3.1.2 Field Study :

    The non reheat boiler operating at temperature below 427 C was checked mainly forintegrity of welds and also for suitability of waterwalls and superheater coils for

    continued operation. Though the components are designed for an operating

    temperature below 427 C, replication was carried out at SH outlet header

    considering the service hours to which the components have been subjected.

    The study revealed that the condition of boiler drum , water walls and SH coils are

    good enough for continued operation.

    The secondary superheater outlet header when examined with fiberscope indicated

    presence of ligament cracks in longitudinal section . Few ligaments on the left

    extreme were only found to have cracks where as the other ligaments were found to

    be having just initiation of cracks.

    To bring back the unit in service, it was necessary to replace the header as the crack

    size in few ligament locations were beyond acceptable limits. As the unit was nothaving readily a spare header for replacement, it was decided to partly remove the left

    extreme portion of the header which had cracks in ligaments beyond acceptable level

    and start the unit. The superheater coils pertaining to the removed portion were

    retained in position in order to avoid any possible gas laning. The removed portion

    of header material was analysed in Laboratory and the lab analysis indicated that the

    ligament crack was due to corrosion fatigue. The typical inside view of the affected

    header is given in figure-4.

  • 8/13/2019 Rla Descriptive

    12/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    3.1.3 Laboratory Analysis :The cut piece from SH outlet header was taken up for detailed analysis. The damage

    in the ligament location was attributed to corrosion fatigue. Corrosion damage wasseen on inside surface of the header in other locations also. Though the replica taken

    from the header parent metal location did not reveal any microstructure degradation,

    the material was tested for tensile strength and yield strength which confirmed the

    suitability of material for further operation. The hardness measurements carried out at

    different locations confirmed no softening of material .

    Considering the metallurgical condition of the header and also based on the above

    laboratory results, it was decided to keep the unit in service for a limited period with

    the old header till replacement is arranged.

    The replacement decision was taken considering the corrosion damages seen on

    steam side surface of the header which was mainly attributed to collection of

    condensate during shut down. No drain provision was available in the original design

    and hence the condensate gets collected during shutdown .

    The new header supplied was provided with drain arrangement and the utility was

    recommended to avoid any collection of condensate during prolonged planned

    outage of the unit and also to maintain water regime as per suppliers

    recommendation.

    Thus the remaining life assessment study carried in the above unit indicated the

    possibility for continued operation with the existing components and it was

    necessary only to replace part of SH assemblies and the secondary SH outlet headerwith a new header .

    3.2 CASE STUDY II.

    A 140 MW reheat , balanced draft type unit was taken up for study after a service

    period of 130,000 hours . The review of operational history indicated failures in cold

    reheat header stub as well as in ligament locations of reheat outlet header. Thescope for assessment was finalised based on the failure history and on the outcome of

    discussions with station authorities. The work scope for remaining life assessment

    study covered the following.

    Detection of hydrogen damage in water walls using attenuation principle.

  • 8/13/2019 Rla Descriptive

    13/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    4. Reheater Misalignment of coils and low remaining life

    5. Cold RH Header Erosion in stub bends

    6. Hot reheat header Ligament cracks particularly near the T piece.7. Desuperheater Enlargement of nozzle hole and also cracks in

    the liner plates.

    8. Piping No microstructure degradation

    The boiler which was designed for a maximum evaporating capacity of 450 T/hr was

    operating at lower load and with frequent failures in reheater. The deterioration in

    calorific value of fuel was the reason for load limitation.

    Visual inspection carried out on cold reheat header stubs showed rupture opening at

    few locations particularly near bend region.

    The ligament space at the header inside surface was checked using fiberscope and

    cracks were seen in circumferential ligaments particularly near T piece. ( both sides )

    Ultrasonic testing using pulse echo with angle beam probe was done for checking

    the ligaments in other locations and for sizing the defect.

    The other ligament locations were found to be free from service cracks. The replica

    taken covering the weld and the heat affected zone location of the reheat outlet

    header revealed that the header material had not undergone any micro structural

    degradation. The decision to continue to operate with existing cracks in the ligament

    location adjacent to the T piece was carefully done after evaluation of the crack size

    and taking into consideration the duration required for arranging replacement.

    The header pipe thickness nearer to T piece weld was lower as compared to T piecethickness. The increase in stress at this location is likely to cause an early damage and

    any additional thermal stress due to mal functioning of spray system will aggravate

    the situation. In view of this, spray system was checked. The reheat steam

    temperature control was not proper because of damage to control valve seat.

    Till replacement of affected portion of header is carried out, the utility was

    recommended to take care of the following aspects.

    The spray control valve was recommended for replacement with a new valve.

    Thermocouples at cold reheat inlet header and outlet header were installed at critical

    locations and the temperatures were recommended to be monitored to avoid undue

  • 8/13/2019 Rla Descriptive

    14/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    Thus with the remaining life assessment study done in this unit, the utility could plan

    for life extension and the life extension programme for this unit could be done only

    by part replacement of specific components as identified above thereby theinvestment required for life extension programme could be minimised.

    3.3 CASE STUDY III

    This case study covers the details of remaining life assessment done in one of the 110

    MW units. The furnace construction was of refractory design, the air ingress in the

    boiler was more and this was causing poor efficiency in operation. While formulating

    the proposal for rehabilitation of this unit, this aspect was also taken into account.

    Accordingly, the refurbishment programme included activities to improve boiler

    efficiency and also the replacements necessary as identified in remaining life

    assessment study

    Evaporation - 375 TONS/HR.

    SH design pressure - 139 KG/CM2

    SH design temperature - 540 CMake - BHEL (Czech design)

    Type - Balanced draft/Reheat

    Service hours - 110,000.

    The utility had carried out replacement of platen SH with modified design as the

    unit experienced frequent tube failures in platens. Also the economiser located in

    2nd pass was replaced with modified design to minimise failures on account of gas

    side erosion.

    The major findings from the RLA study are given below:

    1. Boiler drum Existing drum found to be in good condition.

    2. Water walls Bow observed in different locations.

    3. SH & RH coils The SH & RH coils were found to have adequate

    remaining life. Alignment disturbed.

    4. Platen SH headers The common header connecting the branch headers

    when examined by replication, was found to have

  • 8/13/2019 Rla Descriptive

    15/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    The following major recommendations were given.

    Bowed water wall sections to be replaced

    Platen common header along with stubs for connecting the branch headers to bereplaced. The details are shown in fig. 6

    Alignment band provision for SH / RH coils.

    To minimise air ingress, it was recommended to replace waterwalls, horizontal

    pass and second pass with membrane / steam-cooled walls. ( Shown in thick line

    in fig 5 )

    Also existing slag crusher system for furnace bottom ash handling was

    recommended for replacement with water impounded hopper to eliminate airingress.

    4.0 BHELS Experience In Life Extension Programme

    BHEL has been engaged in the design, manufacture and supply of boilers / steam

    generators from its manufacturing unit at Tiruchirapalli, since 1963. The range of

    boilers supplied by BHEL covers utility boilers from 30 - 500 MW capacities, and

    also industrial boilers for Steel plants, Fertiliser plants, Paper industry, Sugar plants

    etc. These boilers are capable of firing various fuels and industrial by-products like

    black liquor, blast furnace gas, coke oven gas, Corex TM gas, bagasse, rice husk etc.

    The design is based on the technical know-how obtained from various leaders in

    international market as well that developed through in-house R&D efforts.

    BHEL has been updating the boiler design over the years to suit our Indian conditions

    as well as the deteriorating coal quality. BHEL is also updating the design of boilers,

    by incorporating a number of state-of-the-art technologies and also utilising the

    feedback from over 500 BHEL boilers in operation in the country and abroad. These

    latest practices are adopted, wherever applicable, on the R&M packages proposed by

    BHEL. The list of such major R&M packages carried out by BHEL for the boiler

    proper (excluding ESP retrofit / augmentation) is given in Annexure 2. BHEL has

    l i d fi / i f h 100 ESP f ili / i

  • 8/13/2019 Rla Descriptive

    16/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    Remaining Life Assessment plays a vital role . BHEL has gained vast experience in

    this field and has rededicated itself to serve the customers by continuously updating

    its technology.

    5.0 References:

    1. CBIP Publication no. 168 : Thermal Power Stations in India

    2. Sri K. Rajendran & Dr V T Sathyanathan - BHELs Approach / Experience in

    R&M of Boiler & Auxiliaries - Indian Institute of Plant Engineers Conference -

    DIU - 1998

    3. Dr. V T Sathyanathan & R Rajasekaran - Coal fired Boiler design for Reliability

    and Maintainability - Indian Institute of Plant Engineers Conference - Madras

    1994

    4. P.Nagamanickam , K. Rajendran & Dr. V.T. Sathyanathan - Residual life

    assessment of boilers - BHEL s experience - Conference on Residual lie

    assessment NTPC, Korba 1999

    5. N. Ayodhi - RLA Based Life Extension Programme: BHELs Experience In

    Indian Utilities

    6. Sri. A.M. Pagedar / CEA / Delhi - R&M of Thermal Units - Its economics -

    LIPREX Seminar - Hyderabad

    7. Dr V T Sathyanthan & K Sivaraman Residual Life Assessment and Renovation

    & Modernisation for Major Equipments of Captive Power Plants BHEL Journal,

    Vol. 21 No. 1, Feb. 2000.

  • 8/13/2019 Rla Descriptive

    17/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    ANNEXURE

    BHELs Experience in Rehabilitation & Modernisation

    OVERSEAS PROJECTS

    Sl.

    No.

    Name of the

    Customer

    Name of the Power Station

    and Capacity

    Nature of Work Carried Out Remarks

    01 Tenaga

    NasionalBerhad,

    Malaysia

    i) TJPS Stage I

    2 x 60 MWii) TJPS Stage II

    2 x 60 MW

    iii) TJPS Stage III

    3 x 120 MW

    Rehabilitation of boilers.

    Rehabilitation of turbine and generator auxiliaries.

    Replacement of total station controls and instrumentation with

    microprocessor-based system.

    Life assessment and extension survey.

    Incorporation of natural gas firing facility in three 120 MW

    boilers.

    More than

    GuaranteedEfficiency

    achieved.

    Power

    consumption in

    FD/ID Fans

    achieved

    02 Tenaga

    Nasional

    Berhad,

    Malaysia

    SIPS

    2 x 120 MW Rehabilitation of boilers.

    Rehabilitation of turbine and generator auxiliaries.

    Replacement of total station controls and instrumentation with

    microprocessor-based system.

    Life assessment and extension survey.

    Incorporation of natural gas firing facility in two 120 MW boilers.

    --- do ---

    03 TenagaNasional

    Berhad,

    Malaysia

    Prai3 x 120 MW

    Rehabilitation of boilers. Rehabilitation of turbine and generator auxiliaries.

    Replacement of total station controls and instrumentation with

    microprocessor-based system.

    Life assessment and extension survey.

    --- do ---

    Dr V T Sathyanathan, M.E.., Ph.D.

    BHEL, Trichy 62014

    Page : 17/22

  • 8/13/2019 Rla Descriptive

    18/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    Sl.No.

    Name of theCustomer

    Name of the Power Stationand Capacity

    Nature of Work Carried Out Remarks

    04 General

    Electric

    Company,

    Libya

    Tripoli West TPS

    60 MW boiler

    (Stein Industrie, France,

    make)

    Replacement of all bowed waterwalls.

    Replacement of superheaters, superheater supports.

    Revamping of burners.

    Revamping of ducts and insulation.

    05 GeneralElectric

    Company,

    Libya

    Bengazi8 x 160 t/hr boilers (Babcock

    Company make)

    Replacement of waterwalls. Replacement of refractory & insulation.

    Replacement of burners.

    Replacement of expansion bellows.

    Servicing of soot blowers, valves, fuel pumping and heating

    station.

    Servicing of fans.

    Replacement of APH elements and servicing.

    Renovation of controls and instrumentation.

    Chemical cleaning.

    06 General

    Electric

    Company,

    Libya

    Zuera Desalination Plant

    2 x 90 t/hr boilers

    (IDRO, TERMICI, Italy,

    make)

    Replacement of waterwalls, bank tubes.

    Replacement of insulation.

    Replacement of economiser.

    Servicing of valves, soot blowers.

    Servicing of burners. Servicing of fans.

    Revamping of controls and instrumentation.

    Dr V T Sathyanathan, M.E.., Ph.D.

    BHEL, Trichy 62014

    Page : 18/22

  • 8/13/2019 Rla Descriptive

    19/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    Sl.No.

    Name of theCustomer

    Name of the Power Stationand Capacity

    Nature of Work Carried Out Remarks

    07 General

    Electric

    Company,

    Libya

    Dhama TPS

    3 x 120 t/hr boilers (Babcock,

    Germany, make)

    Replacement of waterwalls.

    Replacement of soot blowers.

    Replacement of refractory and insulation.

    Revamping of burners.

    Servicing of valves.

    Revamping of fuel system equipment.

    Servicing of fans.

    Servicing of airpreheaters and element replacement.

    Chemical cleaning.

    08 Bangladesh

    Power

    DevelopmentBoard,

    Bangladesh

    Siddhirganj

    1 x 50 MW (225 t/hr boilers)

    (CE, USA, make)

    Replacement of complete furnace walls.

    Replacement of complete bank tubes.

    Replacement of superheater partly. Replacement of side waterwall headers.

    Replacement of damaged burners.

    Servicing of entire boiler including fan, APH, safety valves and

    other valves.

    Replacement of APH seals.

    Replacement of refractory & insulation.

    Replacement of water level indicator.

    Replacement of part-duct and expansion joints.

    Servicing of controls and instrumentation.

    Chemical cleaning.

    Dr V T Sathyanathan, M.E.., Ph.D.

    BHEL, Trichy 62014

    Page : 19/22

  • 8/13/2019 Rla Descriptive

    20/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    DOMESTIC PROJECTS

    (During the period 1990 to 1999)

    Sl.

    No.

    Name of the

    Customer

    Name of the Power

    Station & Capacity

    Nature of Work Carried Out Remarks

    01 Neyveli

    LigniteCorpn. Ltd.

    (NLC)

    4 x 50 MW

    Unit nos. 2,3,4 & 5Boilers of Russian make

    Complete pressure parts replacement (waterwalls,

    economiser, downcomer, SH, SH headers, DESH, entireMS piping etc. about 350 tons).

    All valves reconditioning / replacement.

    All non-pressure parts renovation.

    Measures for performance uprating/low capacity

    restoration.

    Unit loaded to 235 t/hr

    (design 220 t/hr). Exit gas temperature

    reduced from 190C to

    140C.

    02 Steel

    Authority ofIndia Ltd

    (SAIL)

    Bokaro Steel Plant

    3 x 220 t/hrUnit nos. 3,4 & 5

    Boilers of Russian make

    Pressure part replacement in waterwall, screen SH, Conv.

    SH, (Platen SH, redesigned with material upgrades).

    Burner performance uprating.

    APH (tubular) performance improvement.

    Other non-pressure parts renovation.

    Metal temperature scanner system introduction.

    Boiler loaded to full capacity.

    03 Bihar State

    ElectricityBoard

    (BSEB)

    Unit nos. 1-4 & 5-6

    8x50 MW Boilers

    Replacement of complete downcomer pipes.

    Replacement of waterwall tubes partial. Replacement of superheater - modified design.

    Replacement of economiser blocks - modified .

    Replacement of main steam piping.

    Replacement of airheater blocks.

    Work under progress.

    Dr V T Sathyanathan, M.E.., Ph.D.

    BHEL, Trichy 62014

    Page : 20/22

  • 8/13/2019 Rla Descriptive

    21/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    SlNo.

    Name of theCustomer

    Name of the PowerStation & Capacity

    Nature of Work Carried Out Remarks

    04 APSEB Kothagudem TPS

    2 x 110 MW

    Unit nos. 7 & 8

    Exit gas temperature reduction by second pass pressure

    parts redesign and replacement. About 50C gas

    temperature reduction

    achieved.

    05 RSEB Kota TPS

    2 x 110 MW

    Unit nos. 1 & 2

    Lost capacity restoration with fuel system upgrades

    HEA ignitor introduction in place of eddy plate ignitor.

    Full parameters achieved

    since 1995.

    06 TNEB Ennore

    2 x 110 MW

    Unit nos. 3 & 4

    Complete pressure part re-engineering (tangent tube

    waterwall to membrane tube waterwall).

    Performance uprating (lost capacity restoration).

    Work under progress.

    07 SAIL Bhilai Steel Plant

    2 x 150 t/hr

    Boilers of Russianmake

    Non pressure part renovation.

    Total downcomer /upriser replacement

    DESH replacement. SH headers replacement.

    08 APSEB Kothagudem

    2 x 110 MW

    Unit nos. 5 & 6

    Complete pressure part re-engineering (tangent tube

    waterwall to membrane tube waterwall).

    Performance uprating (lost capacity restoration).

    Non pressure part renovation.

    Work under progress.

    09 HSEB Panipat TPS

    4 x 110 MW

    Unit nos. 1,2

    Milling system capacity upgradation. Work under progress.

    Dr V T Sathyanathan, M.E.., Ph.D.

    BHEL, Trichy 62014

    Page : 21/22

  • 8/13/2019 Rla Descriptive

    22/22

    Residual Life Assessment and Life Extension Programme in Utility Boilers BHELs Experience

    SlNo.

    Name of theCustomer

    Name of the PowerStation & Capacity

    Nature of Work Carried Out Remarks

    10 UPSEB Obra Unit no. 11

    200 MW Mill capacity upgradation.

    3rd PA fan introduction.

    Airpreheater sector widening from 52to 70.

    Lost capacity of boiler

    restored.

    11 SFC, Kota 2x90 T/Hr Boilers Lost capacity enhancement.

    Higher size mill replacement.

    Performance review for low-grade coal.

    Capacity enhancement by

    more than 15% carried out

    successfully.

    12 Gujarat

    Narmada

    Valley

    Fertiliser

    Corporation,

    Bharuch

    3x180 T/Hr VU 40

    Boilers Fuel conversion additional gas firing facility.

    Forced drain system for soot blowers (State-of-the-art

    improvement).

    Fuel conversion implemented

    and successfully tested at full

    load.

    Forced drain system for soot

    blowers supplied and

    commissioned.13 IOC,

    Mathura

    3x150 T/Hr VU 40

    Boilers Conversion of boiler for 100% natural gas firing. Conversion completed and

    performance proved.

    14 IOC, Haldia 3x125 T/Hr Boilers Low NOx burner retrofit. Burner retrofit completed and

    working.

    Dr V T Sathyanathan, M.E.., Ph.D.

    BHEL, Trichy 62014

    Page : 22/22