Upload
stephanie-chapman
View
212
Download
0
Embed Size (px)
Citation preview
RISK MANAGEMENT PRESENTATIONASQ- GREATER HOUSTON SECTION
1405
Lila Carden, Ph.D., MBA, PMP
University of Houston
Instructional Associate Professor
Agenda
ISO 31000 - Published in November 2009 Benefits of Risk Management 21 Ways to Excel at Project Management Risk Management Processes Risk Management Application Top 10 Risk Issues 10 Golden Rules of Project Risk
Management
ISO 31000Published in November 2009
First international standard of risk management Provides principles and generic guidelines on risk
management Plans will still need to include the needs of a specific
organization Standard that can be used by any public, private
or community enterprise, association, group or individual Not industry specific Useful for all managers – operational, financial and
project
Gjerdrum, D. (2013). The new ERM gold standard: ISO 31000:2009. Retrieved from http://www.riskandinsurance.com/story.jsp?storyId=322335271
ISO 31000Published in November 2009
Framework to integrate the process of managing risks and reporting Risk management processes include
identifying, analyzing, responding, implementing and monitoring risks.
Two key functions throughout implementation Communication and consultation need to include
internal and external stakeholders Monitor and review need to include controls,
lessons learned, responses to risks and ready for change
Gjerdrum, D. (2013). The new ERM gold standard: ISO 31000:2009. Retrieved from http://www.riskandinsurance.com/story.jsp?storyId=322335271
Benefits of Risk Management
Establishes project feasibility Lowers costs – rework and unforeseen late efforts are
reduced Establishes project priority and management
support - risk plan noting competence and preparation
Enables project portfolio management – low risk and high risk projects
Exposes weakness in project plans Plans management reserves Facilitates project communication and monitoring –
exposes weaknesses to the team
Kendrick. T. (2009). Identifying and managing project risk. New York: AMACOM.
21 Ways to Excel at Project Management
Managing the risks is number 6 on the list Top 5 include
Sponsorship and Leadership Defining the business objectives Defining the project Ensuring the project is a manageable size Defining the budget
Haughey, D. ( 2013). 21 ways to excel at project management. Retrieved from http://www.projectsmart.com/
7
Risk Management Processes
PMBOK’s project risk management processes include:
Plan Risk Management – how to conduct risk management activities
Identify Risks – determine risks and document characteristics
Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Responses Control Risks
PMI Global Standard. (2013). A guide to the project management body of knowledge (5th ed.). Newtown Square, Pennsylvania: Project Management Institute, Inc.
Plan Risk ManagementTABLE OF CONTENTS
1.0 Purpose Of The Risk Management Plan 2.0 RISK MANAGEMENT PROCEDURE 2.1 Process 2.2 ROLES AND RESPONSIBILITIES 2.3 Risk Identification 2.3.1 Methods for Risk Identification 2.4 Risk Analysis 2.4.1 Qualitative Risk Analysis 2.4.2 Quantitative Risk Analysis 2.5 Risk Response Planning 2.6 Risk Monitoring, Controlling, And Reporting 2.7 Risk Contingency Budgeting 3.0 TOOLS AND PRACTICES 4.0 CLOSING A RISK 5.0 LESSONS LEARNED
Identify Risks9
Techniques Brainstorming Interviewing Root Cause Analysis Delphi Technique – way to reach consensus of
expertsFacilitator uses a questionnaire to obtain ideasThe responses are summarized then re-circulated
to the experts for additional comments Risk Breakdown Structure – structure for identifying
risk
PMI Global Standard. (2013). A guide to the project management body of knowledge (5th ed.). Newtown Square, Pennsylvania: Project Management Institute, Inc.
Identify Risk Risk Breakdown Structure
10
Perform Qualitative Risk Analysis11
Tool Risk Priority Matrix - probability and impact
Perform Quantitative Risk Analysis12
Tools and techniques Sensitivity Analysis – tornado diagram (useful for comparing importance and
impact of variables) Expected Monetary Value Analysis – decision tree
http://goo.gl/DXSglV Modeling and Simulation – translates uncertainties to impact of project
objectives Monte Carlo
The model is computed many times with the input variables (cost estimates, durations) chosen at random for each iteration from the probability distributions of these variables.
A probability distribution (total cost or completion date) is calculated - Example - 12% likely to meet the $41 million most likely cost
estimate or a 70% likelihood of success with a budget of $50 million
PMI Global Standard. (2013). A guide to the project management body of knowledge (5th ed.). Newtown Square, Pennsylvania: Project Management Institute, Inc.
Plan Risk Responses
Negative risks Avoid – change plan to eliminate threat entirely
or shut down project entirely Transfer – shifts risk to third party (consultant) Mitigate – reduce probability or impact
Develop prototype Accept – not take any action
Contingency Reserve – time, money or resources
PMI Global Standard. (2013). A guide to the project management body of knowledge (5th ed.). Newtown Square, Pennsylvania: Project Management Institute, Inc.
Plan Risk Responses
Positive Risks Exploit – ensure opportunity is realized
Most talented resources Enhance – increase the probably and/or impact
Adding more resources Share – allocating all or some of the ownership
of the opportunity Joint ventures, partnerships
Accept – take advantage of the opportunity if realized
PMI Global Standard. (2013). A guide to the project management body of knowledge (5th ed.). Newtown Square, Pennsylvania: Project Management Institute, Inc.
Control Risk Responses
Use Risk Register to Implement risk response plans Track identified risks Identify new risks Evaluate risk process effectiveness
throughout the project – risk audits including project review meetings Deliverable statusSchedule progressCosts
PMI Global Standard. (2013). A guide to the project management body of knowledge ((5th ed.). Newtown Square, Pennsylvania: Project Management Institute, Inc.
Application – Risk Overview Example16
http://capstone.tamu.edu/Teams/Spring%20%2708/VEG/deliverables/VEG_RiskAssessment.pdf http://goo.gl/6clVE5
Top 10 Risk IssuesDr. Dieter Fink
1. Understanding the risk concept 2. Agreeing on what is project risk 3. Recognizing risk events 4. Determining the risk management approach 5. Determining the risk tolerance 6. Preparing the risk management plan 7. Developing organizational risk processes 8. Estimating risk severity 9. Preparing the risk breakdown structure 10. Creating and updating the risk register
• Fink, D. (2011). Trends: Key Issues in Project Risk Management. TPM (February/March). Retrieved from
http://www.jkr.gov.my/prokom/images/stories/pdf/RM/trends.pdf
10 Golden Rules of Project Risk Management Bart Jutte
• 1. Make risk management part of your project• 2. Identify risks early in your project• 3. Communicate about risks• 4. Consider both threats and opportunities• 5. Clarify ownership of issues• 6. Prioritize risks• 7. Analyze risks• 8. Plan and implement risk responses• 9. Register project risks• 10. Track risks and associated tasks
Jutte, B. (2010). 10 golden rules of project risk management . Retrieved from http://www.projectsmart.com/articles/10-golden-rules-of-project-risk-management.php
Intaver InstituteRiskyProject 5
http://intaver.com/index-tutorial4.html
References
• Fink, D. (2011). Trends: Key Issues in Project Risk Management. TPM (February/March). Retrieved from
http://www.jkr.gov.my/prokom/images/stories/pdf/RM/trends.pdf• Gjerdrum, D. (2013). The new ERM gold standard: ISO 31000:2009.
Retrieved from http://www.riskandinsurance.com/story.jsp?storyId=322335271• Haughey, D. ( 2013). 21 ways to excel at project management. Retrieved
from http://www.projectsmart.com/• Jutte, B. (2010). 10 golden rules of project risk management . Retrieved from
http://www.projectsmart.com/articles/10-golden-rules-of-project-risk-management.php
• Kendrick. T. (2009). Identifying and managing project risk. New York: AMACOM.
• PMI Global Standard. (2013). A guide to the project management body of knowledge (5th ed.). Newtown Square, Pennsylvania: Project Management Institute, Inc.