Rijkswaterstaat and the PAS
Experiences with the new rules for nitrogen deposition for
management of main roads, waterways and waterworks
Carla Mors and
Chrisjan Leermakers
November 30, 2015
Rijkswaterstaat
2 Rijkswaterstaat and the PAS RWS UNCLASS November 30, 2015
Main tasks Rijkswaterstaat
• Construction and maintenance of main roads
• Construction and maintenance of main waterways
• Management of main water bodies
• Defence against flooding
Rijkswaterstaat
3 Rijkswaterstaat and the PAS RWS UNCLASS
November 30, 2015
Rijkswaterstaat
4 Rijkswaterstaat and the PAS RWS UNCLASS
Manual for infrastructural projects
November 30, 2015
• MIRT Dutch Multi-annual Programme for Infrastructure, Spatial Development and Transport
• The MIRT includes important infrastructural projects under the Dutch Infrastructure Planning Act
• Contribution traffic and shipping on N-deposition about 5-20 %
• Difference with other nitrogen sources: linear form
• Own manual with a specific protocol is developed by Rijkswaterstaat
RWS instructie Programma Aanpak Stikstof (PAS)
Voor HWN, HVWN en HWS projecten, Juni 2015
Rijkswaterstaat
5 Rijkswaterstaat and the PAS RWS UNCLASS November 30, 2015
Rijkswaterstaat
6 Rijkswaterstaat and the PAS RWS UNCLASS
What’s different? (1)
November 30, 2015
• No study of ecological effects N-deposition needed anymore in specific Appropriate Assessment : this is done in general AA for the PAS where area analyses have been done for all Natura 2000-sites;
(Effectstudies in specific AA still needed for other aspects such as noise on breeding birds.)
• Special position: priority projects with room for development secured: gives more assurance beforehand
• (Road or water)project organizations check if the reservated room for development is enough; estimating realization-phase is most difficult
• If adjustments are needed: this happens twice a year in the context of the programming of the PAS.
Rijkswaterstaat
7 Rijkswaterstaat and the PAS RWS UNCLASS
What’s different? (2)
November 30, 2015
• Distance limit priority projects : 3 km for main roads, 5 km for main waterways; addition of nitrogen outside these boundaries: => checked in general via AERIUS Monitor
• For temporary projects more calculations needed than before, because of low ‘irrelevance limit’: 0,05 mol/ha/year
Rijkswaterstaat
8 Rijkswaterstaat and the PAS RWS UNCLASS November 30, 2015
Rijkswaterstaat
9 Rijkswaterstaat and the PAS RWS UNCLASS
Still questions
November 30, 2015
• How to execute in time the right calculations in AERIUS? (the project deadlines still stand)
• How to be sure that the juridical rules are being subdued?
• If the amounts of nitrogen surpluses exceed these of the reservations: will the adjustments of the reservation be taken in time?
• What if recovery measures turn out to be not enough: are there extra nature management measures at hand for the specific hexagons where it's needed for? Is this ecologically possible? And if not: will there be in time an escape-plan with extra measures at a resources-level? And will there be enough money and public support available for this?
Rijkswaterstaat
10 Rijkswaterstaat and the PAS RWS UNCLASS November 30, 2015
Thanks for your attention,
Carla and Chrisjan from Rijkswaterstaat