Upload
abhinav-goyal
View
377
Download
5
Tags:
Embed Size (px)
DESCRIPTION
drilling rig hydraulics
Citation preview
Summer Internship Project Report
On
Optimization of Rig Hydraulics & Hole
Cleaning
For Internship Under
Drilling Department
Cairn India Limited
Submitted By-
Abhinav Goyal
University of Petroleum &
Energy studies
SUMMER INTERNSHIP PROJECT
Contents
BASICS OF HYDRAULICS ________________________________________________________________________________ 1
FLOW REGIMES __________________________________________________________________________________________ 2
FLOW ( RHEOLOGICAL ) MODELS ______________________________________________________________________ 4
ANNULAR PRESSURE LOSSES __________________________________________________________________________ 7
DRILLSTRING PRESSURE LOSSES ______________________________________________________________________ 8
HOLE CLEANING _________________________________________________________________________________________ 9
BIT OPTIMIZATION _____________________________________________________________________________________ 10
BIT HYDRAULIC ANALYSIS______________________________________________________________________________________11
MANGLA WELL ANALYSIS_______________________________________________________________________________________12
FIELD REPORT ________________________________________________________________________________________________20-47
REFERENCES ____________________________________________________________________________________________48
SUMMER INTERNSHIP PROJECT
LIST OF FIGURES
FIG 1. Effect of ROP on min. flow rate for hole cleaning_____________________________13
FIG 2. Hole cleaning parameters _____________________________________________________ 13
FIG 3. Critical velocity vs depth _______________________________________________________14
FIG 4. Pressure losses vs rate _________________________________________________________14
FIG 5. Circulating pressure vs depth _________________________________________________ 15
FIG 6. ECD vs depth ___________________________________________________________________ 15
FIG 7. Impact force vs flow rate ______________________________________________________ 16
FIG 8. Bit pressure loss vs flow rate __________________________________________________16
Fig 9. Hydraulic HP vs flow rate ______________________________________________________ 17
SUMMER INTERNSHIP PROJECT
ACKNOWLEDGEMENT
I would like to thank my respected mentor Mr. Deepak Sharma Sir for his able guidance
and support throughout the development of the internship project. His constant
suggestions have been valuable and his teachings during the course of my discussions
would continue to be guiding principle in my works in the future as well.
I would also like to Mr. Jayabrata Kolay Sir and Mr. Satyam Krishna Sir who were always
available for discussions at length at the various concepts that could be incorporated in the
project. Their suggestions and ideas helped me to develop our project successfully.
Finally I would like to thank the Cairn India Limited and the entire Drilling Department
for providing me an opportunity to apply my technical knowledge and see it materialize in
the form of this project.
Regards,
ABHINAV GOYAL
SUMMER INTERNSHIP PROJECT
INTRODUCTION
The summer internship program at Cairn India Limited was an 8 week integrated learning curve,
blending the intricacies of Office work with the technicalities of drilling at rig sites. The internship
started with assigning of a major project in Office. I was assigned Optimization of Rig Hydraulics
and hole cleaning and its simulation using WellPlan module of LANDMARK software suite. I started
my project with building my basics about the topic and reviewing the Hydraulic analysis of
different wells to have a clear picture of what I would be doing. I selected Mangala Horizontal
producer for my analysis so as to cover all the aspects of hole cleaning and optimization in both
vertical and horizontal sections of a well and perform a comparative analysis. The whole office
project span continued for around 4 weeks wherein I completed my manual calculations of
Hydraulics and hole cleaning (pressure drop calculations, bit hydraulic calculations and vertical
well hole cleaning calculations) along with the interpretation of the graphical results generated
from the Wellplan Hydraulic module with my mentor.
A three week field trip to Barmer asset (Rajasthan) was lined up for the interns and we had to
select a topic for our field visit project. I decided to go with “Cementation and Pressure testing of
Casing”. The field experience was something that I never had since my exposure to Petroleum
Engineering but the internship at Cairn gave me the the opportunity to see Drilling, Wireline
logging and Cementing operations, all at different field sites which was a wonderful experience
mentored by the best professionals in the Indian oil field industry as well as expatriates from other
countries. I as an intern was grasping all the knowledge that I could get from the work going around
at the fields and studied the operations extensively by observation.
The last week of the Internship was all about collaborating all the knowledge that I have gained in
the previous 7 weeks, discussing the doubts regarding the projects and to deliver all that in a
systematic presentation form.
My internship at Cairn India during the 2013 summer gave me a huge amount of experience that
really has put me streets ahead of where I was when I started. Experience on a CV is immeasurably
valuable, and from a company such as Cairn India it is worth even more. I was given complete free
rein over a research topic tied into their current operations in Barmer, so I really did feel like one
of the team. My internship really has given me an excellent start to my career, and the whole
experience has been extremely enjoyable and invaluable.
SUMMER INTERNSHIP PROJECT
Page 1
1. BASICS OF HYDRAULICS
The hydraulic system serves many purposes in the well. Since it is centred on the mud system, the
purposes of mud and hydraulics are often common to each other. The hydraulics system has
many effects on the well. Therefore, the reasons for giving attentions to hydraulics are abundant.
The more common reasons are as follows:
-Control sub-surface pressures,
-Provide a buoyancy effect to the drill string and casing,
-Minimize hole erosion due to the mud's washing action during movement,
-Remove cuttings from the well, clean the bit, and remove cuttings from below the bit,
-Increase penetration rate,
-Size surface equipment such as pumps,
-Control surge pressures created by lowering pipe into the well,
-Minimize well bore pressure reductions from swabbing when pulling pipe from the well,
-Evaluate pressure increases in the well bore when circulating the mud,
-Maintain control of the well during kicks
Hydrostatic Pressure
The hydrostatic pressure of the drilling fluid is an essential feature in maintaining control of a
well and preventing blow-outs. It is defined, in a practical sense, as the static pressure of a
column of fluid. Although the fluid is generally mud, it can include air, natural gas, foam, mist, or
aerated mud. Only liquid-based systems such as mud will be considered in this text. The
hydrostatic pressure of a mud column is a function of the mud weight and the true vertical depth
of the well. It is imperative that attention be given to the well depth so that the measured depth,
or total depth, is not used inadvertently. Since mud weights and well depths are often measured
with different units, the equation constants will vary. Common forms of the hydrostatic pressure
equation are as follows:
PH= 0.052 (mud weight, lb/gal) (depth, ft), PH= psia
If a column of fluid contains several mud weights, the total hydrostatic pressure is the sum of the
individual sections:
PH= ∑ c ρi Li
c = conversion constant
ρ = mud weight for the section of interest
SUMMER INTERNSHIP PROJECT
Page 2
L = length for the section of interest
Equivalent Mud Weight
Drilling operations often involve several fluid densities, pressures resulting from fluid circulation,
and perhaps applied surface pressure during kick control operations. It is useful in practical
applications to discuss this complex pressure and fluid density arrangement on a common basis.
The approach most widely used is to convert all pressures to an "equivalent mud weight" that
would provide the same pressures in a static system with no surface pressure.
EMW = (total pressure x 19.23) / true vertical depth
EMW= equivalent mud weight, lb/gal
19.23 =reciprocal of the 0.052 constant
Buoyancy
The drilling fluid provides a beneficial effect relative to drill string weight or hook load. When
pipe is lowered into the well, the mud system will support, or buoy, some of the pipe weight. This
effect is termed buoyancy, or buoyant forces. The buoyed weight of the drill string will be less
than the in-air weight of the pipe. Buoyant forces are a function of the volume and weight of the
displaced fluid. Heavier mud has greater buoyant forces than low-density mud.
BW = BF x (in-air weight)
BW = buoyed weight, BF = buoyancy factor
2. Flow Regimes
While drilling fluids are flowing in a well, the manner in which the fluid behaves may vary. This
behavior is often termed the flow regime. The most common regimes are laminar, turbulent, and
transitional. Unfortunately, it is impossible to clearly define each type in the well.As an example,
mud flow may be predominantly laminar, although the flow near the pipe walls during pipe
rotation may be turbulent.
Laminar Flow
The most common annular flow regime is laminar. It exists from very low pump rates to the rate at
which turbulence begins. Characteristics of laminar flow useful to the drilling engineer are low
friction pressures and minimum hole erosion. Laminar flow can be described as individual layers,
SUMMER INTERNSHIP PROJECT
Page 3
or laminar, moving through the pipe or annulus. The center layers usually move at rates greater
than the layers near the well bore or pipe. The flow profile describes the variations in layer
velocities. These variations are controlled by the shear resistant capabilities of the mud. A high
yield point for the mud tends to make the layers move at more uniform rates. Cuttings removal is
often discussed as being more difficult with laminar now. The cuttings appear to move outward
from the higher-velocity layers to the more acquiescent areas. These outer layers have very low
velocities and may not be effective in removing the cuttings. A common procedure for minimizing
the problem is to increase the yield point, which decreases layer velocity variations. An alternative
is to pump a 10-20-bbl high-viscosity plug to "sweep" the annulus of cuttings.
Turbulent Flow
Turbulence occurs when increased velocities between the layers create shear strengths exceeding
the ability of the mud to remain in laminar flow. The layered structure becomes chaotic and
turbulent. Turbulence occurs commonly in the drill string and occasionally around the drill collars.
Much published literature suggests that annular turbulent flow increases hole erosion problems.
The flow stream is continuously swirling into the walls. In addition, the velocity at the walls is
significantly greater than the wall layer in laminar flow. Many industry personnel believe that
turbulent flow and the formation type are the controlling parameters for erosion.
Transitional Flow
Unfortunately, it is often difficult to estimate the flow rate at which turbulence will occur. In
addition, turbulence may occur in various stages. It is convenient to describe this "grey" area as a
transitional stage.
Turbulence Criteria
The Reynolds number approach is used almost exclusively in the industry. Turbulence occurs when
the ratio of the momentum of the liquid to the viscosity ability of the liquid to dampen permeations
exceeds some empirically determined value. The momentum force of the liquid is its velocity times
its density. The viscous ability of the liquid to damp out permeations is the internal resistance
against change and the effects of the walls of the borehole. For the simple case of Newtonian, non
elastic liquid flowing in a pipe dampening effect is the quotient of the viscosity and the diameter of
the well bore.
NR = ρ V D / µ
NR = Reynolds number
ρ= density
SUMMER INTERNSHIP PROJECT
Page 4
D = diameter
µ= viscosity
A simpler equation used in the literature to predict the Reynolds number at the upper limit of
laminar flow is as follows:
NR= 3,470 - 1,370 n
The relation for the Reynolds number between the transition and turbulent flow regimes is
NR= 4,270 - 1,370 n
It is obvious from equations that the Reynolds number is sliding, with its dependency on the flow
behavior index (n). The position of intersection between the laminar and turbulent flow pressure
losses depends on the equations being used.
Critical Velocity
The term critical velocity is used to define the single velocity at which the flow regime changes
from laminar to turbulent. This variable is the most important since all other members are
considered constant in a typical equation. Since no single Reynolds number defines the transitional
zone, it follows that a range of critical velocities may be necessary to determine the flow regime.
In practical applications, a critical velocity (Vc ) and an actual velocity (Val ) are calculated. If Val< Vc
the flow is laminar. If Vic< Va the flow is turbulent. If Val ≅ Vc calculations are made with both flow
regimes and the larger pressure losses are used.
3. Flow (Rheological) Models
A mathematical model is used to describe the fluid behavior under dynamic conditions. The model
can be used to calculate friction pressures, swab and surge pressures, and slip velocities of cuttings
in fluids. The models most used in the drilling industry are Bingham Plastic, Power Law and
Herschel Buckley.
Terms used in mud models are shear stress and shear rate. In drilling operations, the shear stress
and shear rate are analogous to pump pressure and rate, respectively.
Newtonian Fluids
SUMMER INTERNSHIP PROJECT
Page 5
The model used initially to describe drilling mud was the Newtonian model, τ α γ. It stated that
pump pressure (shear stress) would increase proportionally to shear rate. If a constant of
proportionality is applied to represent fluid viscosity, τ = µ γ
Unfortunately, drilling mud usually cannot be described by a single viscosity term. They require
two or more points for an accurate representation of behavior. As a result, the Newtonian model
generally is not used in hydraulics plans.
Bingham Plastic
The Bingham model was developed to describe more effectively drilling mud presently in use.
Bingham theorized that some amount of stress would be required to overcome the mud's gel
structure before it would initiate movement τ = µpγ + τy
τy= yield stress, µp =fluid viscosity
In practical terms, the equation states that a certain pressure would be applied to the mud to
initiate movement. Flowing mud pressures would be a function of the initial yield pressure and the
fluid viscosity.
Shear rates are normally taken at 300 and 600 rpm rates on the viscometer.
The fluid viscosity (µp) and the yield stress (τy) are calculated as follows:
µp= θ600- θ300
θ600, θ300= readings at 600 and 300 rpm, respectively.
τy= θ300- µp
The fluid viscosity is termed plastic viscosity (PV) due to the plastic nature of the fluid and is
measured in centipoise (cp). The size, shape, and concentration of particles affect the plastic
viscosity in the mud system. As mud solids increase, the plastic viscosity increases. The plastic
viscosity is a mud property that is not affected by most chemical thinners and can be controlled
only by altering the state or number of solids.
The yield stresses τy, is given the name of yield point and is measured in lb/100 ft2 . It is a function
of the inter-particle attraction of the solids in the mud. Chemical thinners, dispersants, and
viscosifiers control the yield point.
Power Law
The Power Law model is a standard mathematical expression used to describe a non-linear curve.
The equation for drilling fluids is :
SUMMER INTERNSHIP PROJECT
Page 6
τ = K (γ)n
K= consistency index; n = flow behavior index
The flow behavior index is descriptive of the degree to which the fluid is non Newtonian.
n = 3.32 log (θ600/ θ300)
K = θ300/ 511
Herschel - Buckley (Modified Power Law)
This model combines the features of the Newtonian, Bingham Plastic, and Power Law models. It is
a three parameter model that reproduces the results of the previous three models when the
appropriate parameters have been measured. Unfortunately, the three parameters are difficult to
derive from the rheometer readings. In practice, it is assumed that the YP is equal to the 3 rpm
reading. Using this assumption allows the calculation of the n and K values. The general form of the
equation is τ= YP + Kγn where
YP = θ3 (lb/100 ft2),
n = (3.32) log [(θ600– YP) ÷ (θ300– YP)],
K = θ300÷ 511n
SUMMER INTERNSHIP PROJECT
Page 7
4. Annulus pressure drop calculations
SUMMER INTERNSHIP PROJECT
Page 8
5. Drill string pressure loss
SUMMER INTERNSHIP PROJECT
Page 9
6. Hole cleaning
SUMMER INTERNSHIP PROJECT
Page 10
A major function of the drilling fluid is to transport drill cuttings from the bottom of the hole to the
surface where they can be removed. Poor hole cleaning can result in severe operational problems
including:
• High torque and drag
• Reduced rate of penetration
• Stuck pipe
• Difficulty running casing
• Primary cementing failures.
The ability of the fluid to clean the hole is dependent upon the rheology and density of the fluid, its
flow rate, and the size of the cutting. For any size particle (cutting), the upward movement of the
particle with the fluid flow will be partially negated by the effect of gravity that is promoting the
settling of the particle. The settling rate is termed the slip velocity ( Vs ). By comparing Vs to the
annular velocity ( Va ) in the interval, the net particle transport time (NPT) for the particle and the
annular transport time(ATT) can be calculated. These values will give the engineer the minimum
time required to transport a cutting to the surface.
Cuttings Concentration
When drilling the well, the rate of penetration may generate a larger volume of cuttings than can
be circulated out of the wellbore in one circulation. This results in a build up of cuttings in the
drilling fluid in the annulus. The concentration of cuttings ( Ca) in the fluid in any annular interval
can be calculated by using the following equations.
Depending upon the formations drilled, a Ca> 8% to 10% volume can result in hole cleaning
problems such as mud rings and pack-off.
7. Bit optimization
SUMMER INTERNSHIP PROJECT
Page 11
Optimized hydraulic design is defined here as the determination of the jet nozzle sizes and flow
rates to satisfy an optimization criterion. Criteria used are the maximization of the bit hydraulic
power per square inch (HSI) or of the impact force (IF).
Constraints in this optimization process include rig capability limitations - maximum available
standpipe pressure Pmax, maximum horsepower of the rig pumps, minimum required and
maximum available flow rate, and downhole-tool limitations.
The goal of the optimization is to determine the total flow area TFA, the nozzle sizes and the flow
rate to deliver maximum bit hydraulic horsepower (HSI) or impact force (IF) within the limitation
of maximum pump pressure and hydraulic power available from the drilling fluid pumps.
Some drilling programs select flow rates by using the maximum possible jet velocity for a particular
selected annular velocity. Jet velocity increases as the pressure across a nozzle increases. The flow
rate in the circulating system is selected to be as low as possible to provide the maximum pressure
available for the drill bit. Some rule-of-thumb guidelines recommend that the nozzle velocity be
maintained above 230 ft/s to reduce the possibility of plugged jet nozzles.
The parasitic pressure loss, which includes all pressure losses in the system except the bit pressure
drop, is calculated using the equation:
PParasitic = KQu
Determine the slope u and the coefficient K of the parasitic pressure loss equation and apply the
optimization.
SUMMER INTERNSHIP PROJECT
Page 12
8. Bit hydraulic analysis
SUMMER INTERNSHIP PROJECT
Page 13
MANGALA GENERIC WELL
MANGLA FIELD
HORIZONTAL PRODUCER
8-1/2 in. HOLE HYDRAULIC ANALYSIS
SUMMER INTERNSHIP PROJECT
Page 14
Fig.1 Effect of ROP on min. flow rate for hole cleaning
Fig 2. Hole cleaning parameters
SUMMER INTERNSHIP PROJECT
Page 15
Fig 3. CRITICAL VELOCITY VS DEPTH
Fig 4. PRESSURE LOSSES VS RATE
SUMMER INTERNSHIP PROJECT
Page 16
Fig 5 Circulating pressure Vs Depth
Fig 6. Ecd vs depth
SUMMER INTERNSHIP PROJECT
Page 17
Fig 7. Impact force vs Pumprate
Fig 8. Pressure loss Vs Rate
SUMMER INTERNSHIP PROJECT
Page 18
Fig 9. Bit power Vs pump rate
SUMMER INTERNSHIP PROJECT
Page 19
CONCLUSION
SUMMER INTERNSHIP PROJECT
Page 20
SUMMER INTERNSHIP PROJECT
Page 21
CEMENTING This section of the report highlights the process of primary cementation along with different
surface & subsurface cementing equipment. Cementing an oil or gas well comprises the
displacement of cement slurry down the drillstring, tubing or casing to a predefined section of
the annulus of the well. The cement slurry itself typically contains water, portland cement and
various additives.
Functions of Cement
1. Isolate a hydrocarbon bearing formation from other formations,
2. Protect and secure the casing in the well,
3. Prevent caving of the hole,
4. Provide a firm seal and anchor for the wellhead equipment,
5. Protect casing from corrosion by sulfate rich formation waters
Cement Slurry
API has defined standard classes (Class A to Class H) as well as standard types of cement used within oil
and gas wells. The standard types are:
1. Ordinary,
2. Moderate sulfate-resistant,
3. High sulfate-resistant
Commonly Used class of cement is Class G.
Class G: Intended as basic cement in the depth range: surface to 8,000 [ft], when used with accelerators
and retarders covers wide range of temperatures and pressures, available in moderate and high sulfate-
resistance types.
The physical properties of cement and cement slurries include:
1. Thickening time,
2. Water content,
SUMMER INTERNSHIP PROJECT
Page 22
3. Slurry density,
4. Compressive strength
5. Fluid loss
6. Yield
Cement slurry additives
1. Accelerators: chemicals which reduce the setting time of a cement system, and increase the rate of
compressive strength development.
2. Retarders: chemicals which extend the setting time of a cement system.
3. Extenders: materials which lower the density of a cement system, and/or reduce the quantity of
cement per unit volume of set product.
4. Weighting Agents: materials which increase the density of a cement system.
5. Dispersants: chemicals which reduce the viscosity of a cement slurry.
6. Fluid-Loss Control Agents: materials which control the loss of the aqueous phase of a cement system
to the formation.
7. Lost Circulation Control Agents: materials which control the loss of cement slurry to weak or vugular
formations.
8. Specialty Additives: miscellaneous additives, e.g., antifoam agents, fibers etc.
Cementing equipment
1. Surface equipment
1. Cement storage vessel (silo) Powdered cement material is delivered into the silo through a closed system. The cement is aerated by
the delivery tanker and transferred through heavy-duty hoses from the delivery tanker to a rigid pipe
to the bottom of the silo using compressed air. The delivery driver controls the discharge rate and driver
adjusts the flow of air in to the tank and consequently the rate of flow of cement into the silo.
The silo is fitted with a pressure release vent line at the bottom which connects to dust collector to
allow air to escape through filters which control dust emission.
SUMMER INTERNSHIP PROJECT
Page 23
2. Surge tank
For proper mixing operations the supply of cement should be steady, and the pressure at the mixer
bowl should remain constant. The bulk cement is moved from the storage tank toward the cement
mixer, driven by the differential pressure created between the tank and the end of the line. If the line
is longer the cement tends to separate from the conveying air into slugs, giving pulsar flow. To smooth
the flow and allow for operational requirements, such as changing from one storage tank to another, a
surge tank is used.
3. Continuous mixing unit- Schlumberger
This cementation unit is state of art mixing and pumping unit for land operations. The power unit allows
mixing and pumping cement at rates to 17bbl/min and at pressures to 10,000 psi. Pumps are available
with rating to 10,000 psi. A SLURRY CHIEF mixer with automated density control is used in conjuction
with 6 bbl. mixing tube and a 14 bbl. averaging tank. This arrangement produces superior density
control and separates the critical mixing stage. It also provides the ability to mix 20 bbl of cement in
batch mode for squeeze and plug operations. The CemCAT system is used to monitor and record
treatment parameters and to provide a job report.
CEMENT STORAGE - SILO
SUMMER INTERNSHIP PROJECT
Page 24
Features
Two triplex pumps with 260 hhp power per pump
17 bbl/min max pump rate
Working Pressure rating to 10,000 psi
Automatic density control
Two nonradioactive densitometers
Four Centrifugal pumps for reliability
CemCAT real time monitoring
4. Batch Mixer Twin 50 bbl. batch mixers are available for mixing of cement slurries or other fluids. The Unit features
two centrifugal pumps for picking up fluids, recirculating for mixing and for delivering fluid to high
pressure pumps.
2. Subsurface Equipment
1. Wiper plugs
Wiper plugs are elastomeric devices that provide a physical barrier between fluids pumped inside the
casing. A bottom plug separates the cement slurry from the spacer and a top plug separates the cement
slurry from the displacement fluid. The bottom plug has a membrane that ruptures when it lands at the
bottom of the casing string, creating a pathway through which the cement slurry may flow into the
SCHLUMBERGER CEMENTING UNIT
SUMMER INTERNSHIP PROJECT
Page 25
annulus. The top plug does not have a membrane; therefore, when it lands on top of the bottom plug,
hydraulic communication is severed between the casing interior and the annulus.
2. Float collar & float shoe
• Acts as check valve
• Prevents cement back flow into casing
• Typically run in pairs
• Available in differential fill design
• All components drillable
BOTTOM PLUG (INSIDE VIEW) FLOAT SHOE
SUMMER INTERNSHIP PROJECT
Page 26
Pre cementing considerations
1. Circulate the well before cementation job for at least 1.5 complete volume cycles. ( can be 1.5
-2.5 times hole volume).
2. Stage pump rate to the maximum rate planned during the cementing operation. Monitor well
for whole mud losses
3. Check that there are no gas shows while circulating with pipe on bottom.
4. Mud should be conditioned to exhibit “easy-to remove” properties including low fluid loss, thin
rheological properties, and a flat gel profile.
5. Ensure that the dry bulk supply lines from silo to surge tank (and batch mixer) are clean and
vented thoroughly by blowing air through these lines.
6. Don’t fluff lightweight blend because that can induce particle segregation.
Procedure for primary cementation of production casing
1. Make up SLB cementing head, one pumping line from mud pump and cementing line from SLB
fly mixing unit.
2. Flush cement line with drill water and pressure test line to low pressure 300 psi and high
pressure 3300 psi.
3. Break circulation with mud and circulate 150% hole capacity = 427 bbl. = 5144 strokes. Break
circulation slowly and increase circulation rate in stages to 5 bpm = 60 spm while monitoring
losses.
4. Reciprocate casing while circulating and displacing fluid. Land casing when 50 bbl. is remaining.
CEMENTING HEAD
SUMMER INTERNSHIP PROJECT
Page 27
5. Batch mix 95 bbl. of 13.0 ppg slurry.
6. Drop bottom plug #1.
7. Pump 75 bbl. 11.5 ppg weighted spacer at 5 bpm with mud pump @ 60 spm. Total strokes 903.
8. Isolate rig circulating system from cementing manifold.
9. Release lower wiper plug #2.
10. Fly mix 44 bbl. 13 ppg cement slurry @ 5bpm.
11. Pump remaining 95 bbl. batched 13 ppg cement slurry @ 5bpm.
12. Drop Top Plug.
13. Start displacement from unit, pumping a total of 166.1 bbl. of water at following rates
100 bbl. of water @ 5bpm
30 bbl. of water @ 4bpm
30 bbl. of water @ 2bpm
6.10 bbl. of water @ 1.0bpm
14. During displacement reciprocate the casing with stroke length 10ft.
15. Bump plug with 500 psi over final circulating pressure. If plug not bumped, pump additional
1.45 bbl. (1/2 of shoe track) = MAXIMUM 167.55 bbl.
Procedure for pressure test casing
1. If plug bumped, line up SLB cementing unit and isolate rig pumps. Pressure test casing with
cement unit using water to 4000 psi for 10 minutes and record the fluid volume pumped.
2. Bleed off pressure and check if float is holding – record the fluid volume returned.
3. If float is not holding re-bump plug, close all cementing head valves and WOC. Check for
backflow every 30 minutes.
4. If float is holding, rig down all cementing lines and cement head.
Contingency plan
1. Acceptable density window for fly mixed slurry is from 12.9 ppg to 13.10 ppg.
2. In case the float is not holding the Master valve has to be closed. Keep checking every 4 hrs.
and when the return stop, open the casing to atmosphere.
3. If the pump does not bump (after pumping the calculated volume of displacement). Do not
overdisplace more than half shoe track volume i.e. 1.45 bbl.
Special considerations
1. Centralisation Casing stand-off through critical sections should be a minimum of 70%. Standoff is defined as NAC/ (HR-
CR), where NAC = the Narrowest Annular Clearance between the casing and the wellbore, HR = hole
SUMMER INTERNSHIP PROJECT
Page 28
radius, and CR = casing radius (CR). Standoff can range from 0 % (casing against the hole wall) to 100 %
(casing perfectly centered in the hole).
Deviation < 45 degrees = 1 centralizer per 30 ft joint
Deviation > 45 degrees = 2 centralizers per 30 ft joint (For tight radius bends and severe doglegs, adding
2 centralizers per joint may increase the rigidity of the casing string such that running in the hole may
be more difficult.)
2. U-tubing & cement free fall Cement slurry density inside pipe is greater than the density of the fluid in the annulus, so it will fall to
seek an equilibrium. With a closed system this will tend to pull a vacuum at the wellhead. The rate of
fall depends on density differential and friction factor. Hold back pressure if needed and modeling can
be done with cementing simulator
3. Two bottom Plugs To prevent contamination of spacer/mud and spacer/cement in the casing. The procedure for usage of
two bottom plugs:-
1. Place both bottom plugs in the cement head, resting on pull pin #5 & #6.
2. Circulate the well by opening valve #4.
3. Drop 1st bottom plug
a. Open valve #3 (equalize pressure)
b. Open pull pin #6
c. Close valve #4
d. Pump the spacer using valve #3
4. Load top plug in cement head
a. Open valve #2, #3, #4 (equalize pressure)
b. Close pull pin #6.
c. Open top cap #1.
d. Open pull pin #5 to shift 2nd bottom plug above pull pin #6.
e. Close pull pin #5
f. Place top plug on pull pin #5.
g. Close the top cap #1.
h. Close valve #2, #3, #4
5. Top and Bottom Plug having been loaded in the cement head, the process would proceed as
per normal procedure with spacer already pumped.
SUMMER INTERNSHIP PROJECT
Page 29
HOISTING SYSTEM This section of the report covers a basic idea of the hoisting system and its immediate and
interim uses during operations at various stages of the process of drilling a well. It would also
include the some of the rig specification from the rigs that were visited during the field trip of
the internship.
The Drawworks
Peculiar Features:
Heart of the rig
Enabling equipment to be run in and out of the hole
Provide power for making or breaking joints
Principle components: drumshaft group, catshaft and coring reel group, main drive
shaft and jacketshaft group, rotary component group, and controls
Drumshaft group
It is the main shaft involved in the Hoisting drum to reel the line to raise and lower loads.
Components include:
DRAW-WORKS
SUMMER INTERNSHIP PROJECT
Page 30
Brakes; used to stop the movement using the brake lever
Cooling system; water cooling system to remove heat generated during braking
Auxiliary brakes; hydrodynamic (hydraumatic) or eddy current (uses magnetic forces)
Some other shafts in the Drawworks include:
Catshaft: It comprises the catheads and the catshaft assembly. The Mechanical catheads are
spooled with a suitable length of wire line connected to the tongs. The tongs on the driller’s
side is called make-up tongs and on the other side called break-out tongs.
Coring reel drum: It contains sufficient small diameter (9/16 in) wire line to reach the bottom
of the hole, generally Used for lowering and retrieving any device to the hole bottom.
Main drive shaft and jacket group: They are used on many modern rigs to generate electricity.
Electric cables used to deliver power to motors attached main drive power to the main drive
shaft, rotary table and mud pumps.
Rotary countershaft group: Required when the rotary table is powered directly from the draw-
works.
Hoisting tackle
Block and tackle system is used to handle weight of drill string. Continuous line is wound
around a number of fixed and traveling pulleys.
Here, the line segments between sets of pulleys act to multiply the single pull exerted by the
hoisting drum. This allows many thousands of pounds of drill string or casing to be lowered
into or pulled from hole. It includes different components: crown block, traveling block and
drilling hook, dead line anchor and weight indicator, and drilling line
Crown block
It provides means of taking wire line from the hoisting drum to the traveling block. Basically, it
is a collection of number of pulleys fastened to the top of the derrick.
The drilling line is reeved around the crown block and traveling bock sheaves. One end comes
to an anchoring clamp called dead line anchor. The other end goes to the hoisting drum
described as fast line. During hoisting the drum spools more fast line than the distance traveled
by the traveling block. The speed of the dead line is zero while that of the fast line is equal to
the number of drilling lines times the speed of the traveling block. Crown block must be
positioned such that the fast line sheave is close to the center line of the hoisting drum.
SUMMER INTERNSHIP PROJECT
Page 31
Reeving Process
Reeving means to string up the drilling line through the hoisting system. Reeving is mostly done
with mast laid down on horse back or in vertical position.
a. Pick up one end of the drilling line; pass it through the slot on the substructure from where it goes over the dead line anchor.
b. The crewmember then pass the line over the dead pulley, pulling it all the way to the traveling block, which is previously placed in the middle of the mast. Crane or forklift can be used to drag the line for reeving.
c. Line end is passed around the first pulley of the traveling block, and pulled back to the crown block.
d. Same procedure is repeated till the line has passed over all required number of pulleys in crown and traveling.
e. After passing the line end through the last pulley, which will be called fast sheave, line is dragged to the Drawworks drum and secured it there.
f. Driller starts the Drawworks and reeves in sufficient number of wraps on the drum, while crew keeps on loosening the line from the spare line drum.
g. Pass the other end of the line through the dead anchor and clamp it and secure it. h. Drilling line is now reeved in and is ready for use.
Note: The angle formed by the fast line and the vertical is called fleet angle. Fleet angle should
be less than 1.5 deg.
Crown block as it is clear from the above is a steel framework with the sheaves mounted
parallel on a shaft. The sheaves are mounted on a double-row tapered roller bearings to
minimize friction. A sheave for the line from coring reel shaft is also on the block. Small sheave
for the manila rope from friction catheads may be also found.
Traveling block and drilling hook
It is similar to the crown block as it also contains sheaves and helps in hoisting the drill string
(running in and pulling out of hole). Manufactured from high quality steel, each pulley
mounted on large diameter of anti-friction bearings. Sheaves diameter should be 30-35 times
the diameter of the drilling line to prevent excessive wear and increase fatigue life of line.
Manufacturing Constraints
• Short and slim for less room
SUMMER INTERNSHIP PROJECT
Page 32
• Heavy to overcome the drilling line friction
• Free of protrusions and sharp edges for safety of workers
It is combined with the hook into one unit named “Hook Block”. The hook is used to connect
the traveling block to the swivel and the rest of the drill string.
Deadline anchor and weight indicators
A base and slightly rotatable drum attached to the rig floor, it provides a means of securing the
dead line and measuring the hook load. Hook load measured by a sensitive load cell or pressure
transformer. Here, a pressure signal is sent to the rig floor through a fluid filled hose connected
to a weight indicator. The weight indicator has two pointers; one shows total hook load and
other weight on bit.
Slip and Cut Practice
After calculating the ton miles during drilling, tripping etc. the drill line is slipped and cut at
particular length so that wear in the line is spread as uniformly as possible over its entire length
and at the same time the critical load areas are shifted. During slipping phase the deadline
anchor brake is slacked to allow the drill line to slide through. For cutting the block line has to
Hook load indicator
SUMMER INTERNSHIP PROJECT
Page 33
be removed from the Drawworks drum. The block hanging line hangs traveling Block. Special
precautions have to be taken during the operation.
Drilling line
A wire rope made up of number of strands wound around a steel core. Each strand contains a
number of small wires wound around central core. Several types of wire ropes:
• Round strand
• Flattened strand
• Locked coil
• Half locked
• Multi-strand
The Basic difference in all these above types is related to the following parameters:
• Internal structure
• Weight per unit length
• Breaking strength
• Number of wires in each strand
• Number of strands
• Type of core
In oil well drilling, round-strand wire are only used. Peculiar features of Round-strand ropes
are:
• Widely used in most hoisting operation; oil or mining
• More economical than others
• Consists of six strands wound over a fiber core or a small wire rope
• The wire rope described by the number of strands
Described as: either 6x9/9/1; means 6 strands each consists of 9 outer wires, 9 inner wires,
and one central core, or 6x19, meaning 6 strands each contains 19 wires
Also described by the type of lay: Lang’s lay or ordinary (regular) lay
Lang’s lay, wires and strands are twisted in the same directions; right hand or left hand. This
type of twist increases wire rope resistance to wear.
Ordinary lay; wires and strands twisted in opposite direction, with major advantage being that
it is easier to install and handle than lang’s lay
SUMMER INTERNSHIP PROJECT
Page 34
Drilling line design considerations
Typical line is round-strand, Lang’s lay, 6x19 construction with independent wire rope core
(IWRC)
Sizes varies from ½ to 2 in (51 mm)
Described by nominal diameter, mass per unit length and nominal strength
Specifications given in API Spec 9A
Slips and Elevators
Slips are used to hold the weight of the drill string. The slips are placed around the drill pipe
and lowered into position with the pipe into the rotary table.
Due to the weight of the drill string, slip dies bite into the pipe body and holds it in place by
wedge action. Slips must be maintained in good condition with all pins, elements and dies
inspected regularly. Slips must be set and removed correctly to minimize damage to pipe and
the slips themselves.
Floorman are close to the elevators and blocks when the slips are set and lifted. Slips are heavy;
they must be handled by the correct number of crew and should be left properly balanced.
Power Slips are hydraulic or pneumatically operated slips used on the rig floor to avoid manual
handling of the slips. Spider Elevators and slips are also pneumatic operated slips used during
running in of casing, when casing weight is very high and more than the capacity of the manual
side door elevator, but always before casing enters open hole.
Tongs Rig tongs are on the rig floor for making up and breaking out pipe.
One tong is fastened by a sling of required length to the make-up piston end and the other end to the break-out piston end Moreover snub lines are attached from the tongs to anchor posts on both sides. The tong jaws are latched and set on each side of the pipe coupling. For making
SUMMER INTERNSHIP PROJECT
Page 35
up a connection, the make up piston is pulled up to apply torque through the tong. The second tong through onto the anchor post takes up the reaction torque. The process is reversed for breaking out a connection. Tongs are tied back clear of the rotary table when not in use. Tongs are hung on a special suspension line run over a sheave up the mast to a counter weight. This allows the tongs to be raised or lowered to the tool joint height. Power Tongs are used to make up or break out drill pipe or casing/tubing connections by
engaging the tong jaws around the connections and then rotate to accurately torque up or
break out the tubular. Spinning of the joint is done at high gear and torque up at low gear or
breaking out is done at low gear. Power tongs are normally hydraulically driven. For some
power tongs a rig tong is used for backing up or breaking out a connection while with some
other power tongs the back up device is an integral part of the tong.
Power Tong is hung from the crown block if it is part of the rig floor equipments like Hawk Jaw
and tongs like casing power tong are hung on winch line. They should be secured in one corner
after use. Hydraulic unit of the tong is kept away from the rig floor.
Job description of Cranes operating on rig site: For moving equipments on to the rig floor, using crane, bring the equipment close to the rig floor, using forklift if possible. Hook up crane using inspected slings and shackles. Raise the load, make sure it is balanced and slings are all clear. When lowering the load on to the rig
POWER TONGS PIPE SPINNER
SUMMER INTERNSHIP PROJECT
Page 36
floor, crane operator to follow the instructions of signalman. At all times there should be only one person giving signals.
Man Riding
Man Riding (using the air winch and a riding belt to lift a man up) is sometimes required for
special or unforeseen operations in the derrick and substructure. A special riding belt is fitted
about the rider waist, the winch line shackled to the lifting eye and the rider hoisted on the
winch. Man riding can only be performed under special conditions and only with a certified
Man Riding winch and a man riding basket.
HSE Warning: Both rider and winch operator need to be experienced. Man Riding winch is not
to be used for any other lifting purposes.
Working on Monkey Board The Derrickman works most of the time alone on the monkey board. His job is to open the
elevator, and retrieve the stand of Drill Collar or pipe and rack it in the finger during pulling out
of hole and to throw the pipe into elevator and close the elevator during running in. He should
Man Riding Equipment
SUMMER INTERNSHIP PROJECT
Page 37
be properly trained in the job. Sometimes due to the addition of down hole tools, stands of
BHA have awkward height. Derrickman is required to handle the stands from monkey board.
Winches are installed on the rig floor, the monkey board and in the substructure. Winches may
be hydraulically operated or air operated.
Monkey board winch is a smaller winch, installed on a pedestal, for pulling the drill collar stands
for racking. As Derrickman is working alone most of the time and at such a height, he should
take care of his own safety while operating.
Rig Specifications
JE#18
Derrick a) Type Telescopic mast Make LCI
B) Height 122Ft
Travelling Block a) Make american block
b) Type block with unitized hook
c) Rating 250 mt ; 5 sheave; 1 1/8" groove
Draw works a) Make LCI - 1100
b) Type Removable brake flange
AIR WINCH
SUMMER INTERNSHIP PROJECT
Page 38
42" Dia x 12" Wide
c) Drum Diameter 18" x 39"
Wire rope size a) Make Usha martin
b)Details 1 1/8" dia, 6x19s construction
Engines a) Make Caterpillar C-15
b) Type Diesel driven
c) Rating 540 HP
Mast Model 122 x 440 Twin Box (per API 4F) Key Features:
• Twin box leg fixed base design allows fast positioning of rig before mast is raised. Clear height is 122' below crown.
• Crossover crown with 36" fast-line sheave plus five 30" sheaves. All sheaves mounted on Timken double-row bearings.
• Two hydraulic raising rams and two hydraulic telescoping rams. WE#807
Derrick a)Make NOV Rapid Rig
b) Height 100 ft
Travelling Block a) Make NOV
b) Type block with unitized hook
c) Rating 250 mt ; 5 sheave; 1 1/4" groove
Draw works a) Make NOV SSGD-250
b) Type Baylor AC Cage Induction Motor
Wire rope size a)Details 1 1/4" dia, 6x19s construction
Engines a) Rating 1000 HP
Top Drive a)Make NOV TDS 10SA
SUMMER INTERNSHIP PROJECT
Page 39
CORING
In hydrocarbon exploration and development, obtaining geological data is a primary objective.
In general, geological data are gathered from direct observation and analysis of rock cuttings
collected at surface during drilling. The geological informations thus available are valuable, but
are limited by:
Size of individual rock fragments
Rock sample contamination
Under-representation of formation of interest
In hydrocarbon exploration, cutting of core is the only way that provides intact specimens of
the selected formation for anatomy. The need to obtain information and examine formation
rock of interest, led to the development of coring techniques. Correspondingly, development
of core analysis techniques played a large part in understanding the formation characteristics
and improving the other formation evaluation techniques. Coring also helps in meeting
operators' current need for geological, drilling, completion and engineering requirements in
hydrocarbon exploration and exploitation.
GENERAL CORING METHODS
The coring methods are classified into three types:
Conventional coring method
Wire line coring method
Side wall coring method
GEOLOGICAL DATA AVAILABLE FROM CONVENTIONAL CORES
Formation lithology
Rock characteristics
Formation thickness
Stratigraphic sequence
Environment of deposition
Fracture studies
Core Log correlation
Minerology
Diagenesis
SUMMER INTERNSHIP PROJECT
Page 40
CONVENTIONAL CORING
The conventional coring is done using regular drilling equipment and rotary drilling method. This method utilises open centre bit (core bit) which cuts doughnut shaped hole, leaving cylindrical formation rock (core) in the centre. As the drilling operation progresses, the cut core rises inside the hollow tube called inner core barrel placed above core bit where it is captured and brought to surface for analysis. The size of cores cut depends on the available core barrel sizes, the size of core ranges from 1 V8" to 51/4" diameter. Many of the available conventional core barrels are able to cut 30 to 60 ft of core. Coring operaiton with conventional core barrel
Various components including the outer ba"el or body, the inner barrel that contains the core,
and the bearing and ball/seat assembly are shown. Also, a conventional diamond core bit is
illustrated, showing how the inner barrel and core catcher is arranged. Mud (indicated by
arrows) must flow through the tight annular space between inner and outer barrels and is one
SUMMER INTERNSHIP PROJECT
Page 41
area of concern in coring, especially when using lost-circulation materials, as they can lodge in
this space and jam the inner barrel.
Description of coring tools CORE BITS: Drag type, roller cone and diamond bits are used for coring. The core bits are also called as 'core heads'. CORE BARREL The core barrel has two sections; one outer core barrel and second inner core barrel.
Outer core barrel (OCB) Outer barrel is the outer body of core barrel houses inner core barrel (catcher) and connects the core bit. The size of outer core barrel is smaller than the diameter of hole drilled. This allows washover/fishing in case core barrel gets stuckup.
Inner core barrel (ICB)
The function of inner core barrel is to accept and store core as formation rock is cut. The inner core barrel is attached to the outer core barrel at the upper end. A swivel bearing system at the upper end allows the inner core barrel to remain stationary while outer core barrel rotates along with core bit. At the lower end of inner core barrel are the core catcher bowl and core catcher. This assembly catches and retains core and also helps to break up the core free from formation.
Core barrel Inner fibre core barrels
SUMMER INTERNSHIP PROJECT
Page 42
Mud flow during drilling Through the drill string, mud enters into core barrel top, then the mud flow is diverted into the annulus between inner core barrel and outer core barrel by ball check valve placed at the upper end of inner core barrel. Then the mud passes around core catcher down to cutting area of core bit.
Handling of cores Cores are cut in hard rock areas, unconsolidated sands, fractured formations etc. Surface handling of softer cores is different as the samples fall out of conventional core barrels during recovery. To minimise such damages and improper core recovery, replaceable and reusable inner core barrels are used.
Cleaning of core for visual inspection Spectral gamma logging
SUMMER INTERNSHIP PROJECT
Page 43
CIRCULATION SYSTEM
What is the circulation system?
The circulation system is the lifeline of every oil well. It is the system through which the
drilling mud travels down from the active mud tank-mud pumps-standpipe-gooseneck-
drillstring-bit and then up the annulus to flowline-shale shaker-desander-desilter-degasser
(mud conditioning equipments) to intermediate mud tank. During the cycle mud lifts the drill
cuttings to surface and acts as lubricant and coolant for the bit and drillstring.
Circulation system is one of the most important system without which we cannot drill
to the target depth. Each component of circulation system is available in number of sizes,
capacity and pressure rating; so their selection depends upon the rig size, target depth and
concerns of primary well control. The next section discusses the various components of mud
circulation system.
Components of circulation system:
1. Mud Tanks and mud mixing equipments
2. Mud pumps
3. High pressure mud flowline
4. Drill string-Bit Nozzles-Annulus
5. Shale shaker
6. Degasser
7. Mud cleaner (Desander plus Desilter)
Drilling mud is the single component that remains in contact with the wellbore throughout the
drilling operation. A properly designed and maintained drilling fluid performs several essential
functions:
Cleans the hole by transporting drilled cuttings to the surface, where they can be
mechanically removed from the fluid before it is recirculated downhole.
Balances or overcomes formation pressures in the wellbore to minimize the risk of well
control issues.
SUMMER INTERNSHIP PROJECT
Page 44
Supports and stabilizes the walls of the wellbore until casing can be set and cemented
or
Openhole completion equipment can be installed.
Prevents or minimizes damage to the producing formation.
Cools and lubricates the drillstring and bit.
LWD-MWD data transmission by mud telemetry.
The properties of the mud are checked continuously to ensure that the desired properties of
the mud are maintained. If the properties of the mud change then chemicals will be added to
the mud to bring the properties back to those that are required to fulfill the functions of the
fluid. These chemicals will be added whilst circulating through the mud pits or mud with the
required properties will be mixed in separate mud pits and slowly mixed in with the circulating
mud.
Mud Pumps:
With the exceptions of some experimental types, rigs always have been using positive
displacement reciprocating pumps. The reason behind using reciprocating pumps is their
ability to pump highly solid laden fluids and ability to operate over wide range of pressures and
flow rates by changing the liner size.
There are basically Triplex pumps (single acting) and Duplex pumps (double acting) being used
widely. Triplex pumps incorporate three cylinders pump on the forward stroke only while
duplex pumps consist of two cylinders and pump on both forward and backward strokes.
Triplex pumps are lighter and more compact than Duplex pumps and their output pressure
pulsations are not as great and are cheaper to operate.
Pumps are rated for hydraulic power, maximum pressure and maximum flowrate. We visited
John Energy 18 rig that had three triplex pumps of 1000 Hp each. Two of them were active and
one was on standby. The stroke length was 14 inch and pressure rating was 3000psi.
Different components and peripherals of the mud pumping system are as follows:
Suction line-Supercharger-gate valve-suction manifold-mud pump-discharge manifold-
pulsation dampener-pop off valve-crank shaft-diesel engine etc.
SUMMER INTERNSHIP PROJECT
Page 45
Triplex Pumps
The piston discharges in only one direction, and so the rod diameter does not affect the pump
output. The discharge volume for one pump revolution is:
=3V1Ev=3πd2LEv/4
Again the pump output is found by multiplying by the pump speed:
Q=d2LEvR/98.03
Where,
Q=flow rate (gpm)
L = stroke length (in.)
d = liner diameter (in.)
R = pump speed (spm)
More power can be delivered using a triplex pump since higher pump speeds can be used.
Inside View Triplex Pump
SUMMER INTERNSHIP PROJECT
Page 46
Pulsation Dampener:
Pulsation Dampeners utilize the compressibility of nitrogen gas for storing hydraulic
energy during pump compression. The nitrogen gas is compressed when the pulsation
dampener fills with mud from pump. When the pressure drops during the return cycle of
pump, the pulsation dampener steps in and uses its stored energy to dispense the stored fluid,
enabling a more constant flow pressure.
Supercharger:
Supercharger is a centrifugal pump that imparts a pressure around 300-400 psi to the
mud coming from the mud tank. This enables the mud pump to work at higher efficiencies.
There is gate valve after it, which ensures the flow to the suction line. Another gate valve is
used to bypass the flow directly to discharge line. The mud will be pumped by supercharger
when filling the casing while running and to fill the annulus when both the pumps fail.
Pop Off Valve:
It is a spring operated valve which has a pre-charged pressure dome (the pressure that
should not be exceeded or safety limit). If by some means the pressure generated by the pump
exceeds the pre-charged pressure the valve will release and mud will return to the mud tank
through a small return line. Pre-charged pressure was set at 2700 psi on JE-18 rig.
Pulsation Dampener
SUMMER INTERNSHIP PROJECT
Page 47
High Pressure Line:
It transports the high pressure mud for pump to the standpipe. It had 15O2 hammer
union connection and the pressure rating was 5000 psi. The diameter of the line was 8 inches.
Mud Conditioning Equipments
Contamination of drilling fluids with drilled cuttings is an un-avoidable consequence of
successful drilling operations. If the drilling fluid does not carry cuttings to the surface, the rig
either is not making hole or soon will be stuck in the hole it is making.
Shale Shaker:
It is a series of trays with vibrating screens which allow the mud to pass through but retain the
cuttings. The mesh must be chosen carefully to match the size of the solids in the mud.
The other end of the flowline is directly connected to the possum belly, which act as a
distribution box to divide the flow to three shale shakers. The no. of shakers are decided by
the volume of cuttings being handled which depends upon the hole size.
Pop Off Valve
SUMMER INTERNSHIP PROJECT
Page 48
JE 18 rig used MI SWACO Mongoose Pro shakers, each consisting of four screens. The three
motors mounted on the top of the screens impart lateral, transverse and elliptical vibrations;
this ensures maximum liquid removal from the surface of cuttings. The removed liquid falls in
the Sandtrap.
Screen size selection is the most important part of the shaker operation and it finds high
dependence on the formation we are drilling. Sandstones will generally produce finer cuttings
than the clay stones. For the bottom section of the well no. 21 JE 18 installed 140 mesh screens.
There was a gas trap sensor installed at the possum belly, which takes the mud along with
cuttings and churns the mud to separate out the gaseous fraction if any and the gas is then
sent to the mud logging unit for FID and gas chromatography. This is just a qualitative indication
of gas.
Degasser:
Degasser separates out the bulk amount of gas dissolved in mud. JE 18 used MI SWACO
Degasser; it uses a patented centrifugal force system rather than conventional vacuum or
impact systems. As such, the degasser exerts centrifugal force on the mud, multiplying the
force acting on the gas bubbles to increase buoyancy and release. The increased buoyancy
accelerates the bubble-rise velocity. As the bubbles rise toward the surface, they escape the
mud and are further broken down by flow turbulence. The gas is discharged at a safe distance
from the drilling operation while the restored mud is returned to the drilling fluid system.
Mud Cleaner:
Mud cleaner is a combined form of the desilter and desander. JE 18 uses 2-12 system
meaning 2 cones of desander and 12 cones of desilter. Desilter and desander are
hydrocyclones separators. Desilter has a lesser diameter than desander because it has to
remove finer particles. The capacity of individual desanders and desilters determine capacity
of mud cleaner. The 2-12 system has capacity of 1000 GPM. Lesser space occupied by the
system is the major advantage.
A centrifugal pump feeds mud tangentially at high speed into the housing, thus creating
high centrifugal forces. These forces multiply the settling rate so that the heavy particles are
thrown against the outer wall and descend towards the outlet (underflow).The lighter particles
move inwards and upwards as a spiralling vortex to the liquid discharge (overflow).
SUMMER INTERNSHIP PROJECT
Page 49
Hydrocyclones are designed so that only solids (plus small volume of fluid) pass out the
underflow. This should appear as a “spray discharge” and not “rope discharge”. Rope
discharge is an indication of solids overloading, and the underflow will soon plug off
completely.
Mud Tanks and Mud mixing equipment:
Mud tanks are those in which mud is prepared, stored and fed to mud pumps. Basically a rig
has an active tank which feeds the mud to suction side of the pump. Intermediate tank is the
one where the returning mud from the solid control system is received, it is then sent to the
active tank. Reserve tanks are used for the storage of mud.
JE 18 rig had one active and intermediate tank each of 45m3 capacity and having
hemispherical base. Two reserve tanks were of 45m3 capacity each and two rectangular fresh
water tanks of 42m3 each.
Mud mixing involves mixing of base solvent either water or synthetic oil with different
types of additives. The solvent in the mud tank is constantly agitated by agitators while solid
particulate additives are poured through a hopper; it then passes a strainer to remove any kind
of debris and to break lumps of solid if any. Then a jet nozzle expels the solids to the suction
side of the blower, which pressurizes and sends it to mud tank.
SUMMER INTERNSHIP PROJECT
Page 50
Well control systems:
Blowout preventer
Accumulator unit (consolidated pressure control)
accumilator bottles
reservoir tank
tubular manifold
prime electric pump
auxillary pneumatic pump
Choke manifold
ibop(as a part of the TDS)
Blowout preventer
A blowout preventer is a large, specialized valve or similar mechanical device, usually installed
redundantly in stacks, used to seal, control and monitor oil and gas wells. Blowout preventers
were developed to cope with extreme erratic pressures and uncontrolled flow (formation kick)
emanating from a well reservoir during drilling. Kicks can lead to a potentially catastrophic
event known as a blowout. In addition to controlling the downhole (occurring in the drilled
hole) pressure and the flow of oil and gas, blowout preventers are intended to prevent tubing
(e.g. drill pipe and well casing), tools and drilling fluid from being blown out of
the wellbore (also known as bore hole, the hole leading to the reservoir) when a blowout
threatens. Blowout preventers are critical to the safety of crew, rig (the equipment system
used to drill a wellbore) and environment, and to the monitoring and maintenance of well
integrity; thus blowout preventers are intended to be fail-safe devices.
Types
BOPs come in two basic types, ram and annular. Both are often used together in drilling rig BOP
stacks, typically with at least one annular BOP capping a stack of several ram BOPs.
Ram blowout preventer
A ram-type BOP is similar in operation to a gate valve, but uses a pair of opposing steel
plungers, rams. The rams extend toward the center of the wellbore to restrict flow or retract
SUMMER INTERNSHIP PROJECT
Page 51
open in order to permit flow. The inner and top faces of the rams are fitted with packers
(elastomeric seals) that press against each other, against the wellbore, and around tubing
running through the wellbore. Outlets at the sides of the BOP housing (body) are used for
connection to choke and kill lines or valves.
Rams, or ram blocks, are of four common types: pipe, blind, shear, and blind shear.
Pipe rams close around a drill pipe, restricting flow in the annulus (ring-shaped space between
concentric objects) between the outside of the drill pipe and the wellbore, but do not obstruct
flow within the drill pipe. Variable-bore pipe rams can accommodate tubing in a wider range
of outside diameters than standard pipe rams, but typically with some loss of pressure capacity
and longevity.
Blind rams (also known as sealing rams), which have no openings for tubing, can close off the
well when the well does not contain a drill string or other tubing, and seal it.
Shear rams cut through the drill string or casing with hardened steel shears.
Blind shear rams (also known as shear seal rams, or sealing shear rams) are intended to seal a
wellbore, even when the bore is occupied by a drill string, by cutting through the drill string as
the rams close off the well. The upper portion of the severed drill string is freed from the ram,
while the lower portion may be crimped and the “fish tail” captured to hang the drill string off
the BOP.
In addition to the standard ram functions, variable-bore pipe rams are frequently used as test
rams in a modified blowout preventer device known as a stack test valve. Stack test valves are
BOP STACK
SUMMER INTERNSHIP PROJECT
Page 52
positioned at the bottom of a BOP stack and resist downward pressure (unlike BOPs, which
resist upward pressures). By closing the test ram and a BOP ram about the drillstring and
pressurizing the annulus, the BOP is pressure-tested for proper function.
Annular blowout preventer
An annular-type blowout preventer can close around the drill string, casing or a non-cylindrical
object, such as the kelly. Drill pipe including the larger-diameter tool joints (threaded
connectors) can be "stripped" (i.e., moved vertically while pressure is contained below)
through an annular preventer by careful control of the hydraulic closing pressure
An annular blowout preventer uses the principle of a wedge to shut in the wellbore. It has a
donut-like rubber seal, known as an elastomeric packing unit, reinforced with steel ribs. The
original type of annular blowout preventer uses a “wedge-faced” (conical-faced) piston. As the
piston rises, vertical movement of the packing unit is restricted by the head and the sloped
face of the piston squeezes the packing unit inward, toward the center of the wellbore.
ACCUMULATOR UNIT
SUMMER INTERNSHIP PROJECT
Page 53
Well control equipments at RIG JOHN ENERGY 18(wrt rig specifications)
1 BOPS
1.Annular preventor a) Make Shaffer
b) Type annular flanged bottom
c) Rating 13 5/8 x 5000psi
2. Ram type Preventor a) Make Cameroon
b) Type U type
c) Rating 13 5/8 x 5000psi
2 BOP Control Unit a) Make CPC
b) Type
6 station with pnumetic and elctrical
pumps
c)No.of accumul. 24
Well control equipments at RIG WEATHERFORD 807(wrt rig specifications)
SUMMER INTERNSHIP PROJECT
Page 54
SURFACE EQUIPMENTS
BOP CONTROL (RIG FLOOR) BOP CONTROL UNIT
SUMMER INTERNSHIP PROJECT
Page 55
REFERENCES
Bourgoyne, A. T., Chenevert, M. E., Millheim, K. K., Young Jr., F. S. "Applied
Drilling Engineering", SPE Textbook Series: Volume 2.
Luo, Yuejin and P. A. Bern, BP Research Centre; and D. B.Chambers, BP
Exploration Co. Ltd. "Flow-Rate Predictions for Cleaning Deviated Wells."
IADC/SPE 23884.
Rabia, H. Rig Hydraulics. Entrac Software: Newcastle, England (1989):
Chapter 5.
Scott, K. F. "A New Approach to Drilling Hydraulics." Petroleum Engineer.
September 1972.