Master Plan Phase 1 – Near Term
Rose Hill Church Remodel Phase 1• Clear scope for Phase 1 (30 days) – March 1• Building Plans (2-3 months) – June 1• Engineering (4-6 weeks) – July 1• Specifications (30 days) – July 1• Budget (4 weeks) – July 1• Budget (4 weeks) – July 1• Project Plan & Sequence (4 weeks) – July 1• Start Work – when plans and funds are ready• Capital Campaign
– Groundwork is underway– Kick-Off Meeting in mid-February– Updates as Scope, Plans, Budget, and Project progress
RHC Remodel Scope
• Primary needs in next 5+ years are in two areas:– Narthex expansion– Narthex expansion– Restroom Upgrades
• Other improvements called out in the Master Plan are not yet justified
Narthex Expansion
Narthex Expansion
• Expand Coffee Fellowship area by relocating the rear wall of the sanctuary
• Improve traffic flow• Improve natural and artificial lighting• Provide visibility into the sanctuary• Update finishes and flooring
Narthex Expansion Options
• Consider replacing main entry doors• Consider including new carpeting in
sanctuary and other areas• Consider improvements to the chancel
area–Make chancel all one level– Improve sound system wiring
Narthex Expansion Options
Restroom Updates
XX
North RestroomsWest Restrooms
X
Restroom Updates
• Update fixtures, furnishings, surfaces, and flooring to modern standards in both northern and western restrooms
• Add handicap stalls in northern restrooms• Add handicap stalls in northern restrooms• Current restroom capacity seems to be
adequate for the next 5+ years – expansion is not seen as a priority at this time
• Expansion of the northern restrooms would require expensive HVAC work and eliminate the janitorial closet – not a good trade-off
Project Phases
• Phase 1 – Restroom Updates & Plans for Narthex Expansion
• Phase 2 – Narthex Expansion
Project Phases
• Everyone agrees that the Narthex expansion is the most important improvement
BUT• Restroom updates do not require engineering or
architect’s plans• Restroom updates do not require engineering or
architect’s plans• Restroom upgrade costs are relatively low
allowing us to start this work sooner• We can get the engineering and plan work for
Phase 2 done while the restrooms are in work• We can be raising funds for Phase 2 while Phase 1
is being completed
Phase 1 Cost & Time Estimates
• Phase 1A - Upgrade for northern restrooms– $50,000 3 weeks construction
• Phase 1B – Engineering, plans, and permits for narthex expansionnarthex expansion– $50,000 4 months for engrg & plans
3 more months for permits• Phase 1C - Upgrade for western restrooms
– $25,000 2 weeks construction
This are rough estimates based on many assumptions. Bids will provide the final estimates.
Phase 2 Costs• We now have only an order-of-magnitude
GUESS on the cost of Phase 2
• Phase 2 - Narthex expansion• Phase 2 - Narthex expansion– $250,000 Narthex only– $100,000 Options in sanctuary, etc.
• We will not have reasonable cost estimates for Phase 2 until the engineering and plans are complete
So what do we need to do?
• Start raising the money
• Find a few volunteers very soon for a Focus Group to make decisions on decor preferences Group to make decisions on decor preferences for the restroom upgrades
• In a few months we’ll also need a few volunteers for a Focus Group to make decisions on decor preferences for the narthex
Fund Raising Campaign
• We will have a single Fund Raising Campaign for both project Phases – Today is the Kick-off
• We encourage you to Pledge a total amount to be donated during 2019 – Pledging will help us estimate donated during 2019 – Pledging will help us estimate donations we can expect by year end
• As the donations received reach the amount needed to fund a sub-phase, work will begin on that sub-phase
• Campaign Pledge Day will be May 19th in worship
Questions?