REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-PP-012
BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery
To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other
Inspection /monitoring is required on (date) 18-Mar-14 at (time) 8:00 AM prior to WELDING
for the following location/equipment SPOOL FIT-UP AT SESA FABRICATION SHOP
Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point
SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:
SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-L-350Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name M. IMRAN/JOEL M.
QA/QC Signature Date 17-Mar-14
This form received by the undersigned Inspection Department employee:
Name Mr. Ali Saud Signature Date Time
Distribution:
QR Number #
QMIS RFI #
NOTE
SATIP SATIP-L-350-08SAIC SAIC-L-2035SATIP ITEM NO. 3.1SA INSPECTION LEVEL WCONTRACTOR INSPECTION LEVEL W
Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.
A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor
REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-WD-036
BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery
To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other
Inspection /monitoring is required on (date) 18-Mar-14 at (time) 8:00 AM prior to PRE WELDING JOINT FIT-UP
for the following location/equipment SESA FABRICATION SHOP
Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point
SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:
SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-W-011Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name ONNY HENDRA
QA/QC Signature Date 17-Mar-14
This form received by the undersigned Inspection Department employee:
Name Mr. Ali Saud Signature Date Time
Distribution:
QR Number #
QMIS RFI #
NOTE
SATIP SATIP-W-011-01SAIC SAIC-W-2005SATIP ITEM NO. 3.6SA INSPECTION LEVEL WCONTRACTOR INSPECTION LEVH
Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.
A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor
REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-WD-037
BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery
To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other
Inspection /monitoring is required on (date) 18-Mar-14 at (time) 8:00 AM prior to IN PROCESS WELD INSPECTION
for the following location/equipment SESA FABRICATION SHOP
Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point
SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:
SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-W-011Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name ONNY HENDRA
QA/QC Signature Date 17-Mar-14
This form received by the undersigned Inspection Department employee:
Name Mr. Ali Saud Signature Date Time
Distribution:
QR Number #
QMIS RFI #
NOTE
SATIP SATIP-W-011-01SAIC SAIC-W-2006SATIP ITEM NO. 3.7SA INSPECTION LEVEL SCONTRACTOR INSPECTION LEVW
Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.
A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor
REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-WD-038
BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery
To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other
Inspection /monitoring is required on (date) 18-Mar-14 at (time) 8:00 AM prior to POST-WELDING VISUAL INSPECTION
for the following location/equipment SESA FABRICATION SHOP
Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point
SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:
SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-W-011Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name ONNY HENDRA
QA/QC Signature Date 17-Mar-14
This form received by the undersigned Inspection Department employee:
Name Mr. Ali Saud Signature Date Time
Distribution:
QR Number #
QMIS RFI #
NOTE
SATIP SATIP-W-011-01SAIC SAIC-W-2007SATIP ITEM NO. 3.9SA INSPECTION LEVEL WCONTRACTOR INSPECTION LEVH
Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.
A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor
REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-WD-034
BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery
To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other
Inspection /monitoring is required on (date) 17-Mar-14 at (time) 2:00 PM prior to
for the following location/equipment SESA FABRICATION SHOP
Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point
SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:
SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-W-011Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name ONNY HENDRA
QA/QC Signature Date 16-Mar-14
This form received by the undersigned Inspection Department employee:
Name Mr. Ali Saud Signature Date Time
Distribution:
QR Number #
QMIS RFI #
NOTE
SATIP SATIP-W-011-01SAIC SAIC-W-2013SATIP ITEM NO. 3.1OSA INSPECTION LEVEL SCONTRACTOR INSPECTION LEVW
Repair of Weld Joints or Base Metal by Welding (prior to weld acceptance)
Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.
A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor
REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-WD-035
BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery
To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other
Inspection /monitoring is required on (date) 17-Mar-14 at (time) 9:00 PM prior toSelection of Weld joints for NDE
for the following location/equipment SESA FABRICATION SHOP
Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point
SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:
SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-W-011Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name ONNY HENDRA
QA/QC Signature Date 16-Mar-14
This form received by the undersigned Inspection Department employee:
Name Mr. Ali Saud Signature Date Time
Distribution:
QR Number #
QMIS RFI #
NOTE
SATIP SATIP-W-011-01SAIC SAIC-W-2015SATIP ITEM NO. 3.11SA INSPECTION LEVEL WCONTRACTOR INSPECTION LEVH
Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.
A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor