REQUEST FOR INSPECTION Saudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels To : Project Inspection Unit Mr. Ali Saud Civil Mech Plumb. Comms. Inspection /monitoring is required on 18-Mar-14 at (time 8:00 AM prior to WELDING for the following location/equipment SPOOL FIT-UP AT SESA FABRICATION SHOP Work Permit require Yes No Project Quality Plan: Hold Point SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to inspection and conforms to the project requirements. complete and in compliance with the foll SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-L-350 Signature Date Contractor/Company SAMSUNG EPC CO. LTD Telephone Fax QA/QC Name M. IMRAN/JOEL M. QA/QC Signature Date This form received by the undersigned Inspection Department employee: Name Mr. Ali Saud Signature Date Time Distribution: QR Nu QMIS NOTE SATIP SATIP-L-350-08 SAIC SAIC-L-2035 SATIP ITEM NO. 3.1 SA INSPECTION LEVEL W CONTRACTOR INSPECTION LEVEL W Note : Inspector's signature is for receiving this this request only and not for approval or disapproval o A. Original - Project Management B. 1st Copy - Inspection C. 2nd Co

RFI for 18.03.2014 Piping, Welding at SESA Fab

Embed Size (px)

Citation preview

Page 1: RFI for 18.03.2014 Piping, Welding at SESA Fab

REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-PP-012

BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery

To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other

Inspection /monitoring is required on (date) 18-Mar-14 at (time) 8:00 AM prior to WELDING

for the following location/equipment SPOOL FIT-UP AT SESA FABRICATION SHOP

Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point

SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:

SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-L-350Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name M. IMRAN/JOEL M.

QA/QC Signature Date 17-Mar-14

This form received by the undersigned Inspection Department employee:

Name Mr. Ali Saud Signature Date Time

Distribution:

QR Number #

QMIS RFI #

NOTE

SATIP SATIP-L-350-08SAIC SAIC-L-2035SATIP ITEM NO. 3.1SA INSPECTION LEVEL WCONTRACTOR INSPECTION LEVEL W

Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.

A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor

Page 2: RFI for 18.03.2014 Piping, Welding at SESA Fab

REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-WD-036

BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery

To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other

Inspection /monitoring is required on (date) 18-Mar-14 at (time) 8:00 AM prior to PRE WELDING JOINT FIT-UP

for the following location/equipment SESA FABRICATION SHOP

Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point

SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:

SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-W-011Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name ONNY HENDRA

QA/QC Signature Date 17-Mar-14

This form received by the undersigned Inspection Department employee:

Name Mr. Ali Saud Signature Date Time

Distribution:

QR Number #

QMIS RFI #

NOTE

SATIP SATIP-W-011-01SAIC SAIC-W-2005SATIP ITEM NO. 3.6SA INSPECTION LEVEL WCONTRACTOR INSPECTION LEVH

Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.

A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor

Page 3: RFI for 18.03.2014 Piping, Welding at SESA Fab

REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-WD-037

BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery

To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other

Inspection /monitoring is required on (date) 18-Mar-14 at (time) 8:00 AM prior to IN PROCESS WELD INSPECTION

for the following location/equipment SESA FABRICATION SHOP

Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point

SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:

SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-W-011Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name ONNY HENDRA

QA/QC Signature Date 17-Mar-14

This form received by the undersigned Inspection Department employee:

Name Mr. Ali Saud Signature Date Time

Distribution:

QR Number #

QMIS RFI #

NOTE

SATIP SATIP-W-011-01SAIC SAIC-W-2006SATIP ITEM NO. 3.7SA INSPECTION LEVEL SCONTRACTOR INSPECTION LEVW

Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.

A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor

Page 4: RFI for 18.03.2014 Piping, Welding at SESA Fab

REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-WD-038

BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery

To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other

Inspection /monitoring is required on (date) 18-Mar-14 at (time) 8:00 AM prior to POST-WELDING VISUAL INSPECTION

for the following location/equipment SESA FABRICATION SHOP

Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point

SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:

SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-W-011Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name ONNY HENDRA

QA/QC Signature Date 17-Mar-14

This form received by the undersigned Inspection Department employee:

Name Mr. Ali Saud Signature Date Time

Distribution:

QR Number #

QMIS RFI #

NOTE

SATIP SATIP-W-011-01SAIC SAIC-W-2007SATIP ITEM NO. 3.9SA INSPECTION LEVEL WCONTRACTOR INSPECTION LEVH

Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.

A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor

Page 5: RFI for 18.03.2014 Piping, Welding at SESA Fab

REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-WD-034

BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery

To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other

Inspection /monitoring is required on (date) 17-Mar-14 at (time) 2:00 PM prior to

for the following location/equipment SESA FABRICATION SHOP

Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point

SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:

SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-W-011Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name ONNY HENDRA

QA/QC Signature Date 16-Mar-14

This form received by the undersigned Inspection Department employee:

Name Mr. Ali Saud Signature Date Time

Distribution:

QR Number #

QMIS RFI #

NOTE

SATIP SATIP-W-011-01SAIC SAIC-W-2013SATIP ITEM NO. 3.1OSA INSPECTION LEVEL SCONTRACTOR INSPECTION LEVW

Repair of Weld Joints or Base Metal by Welding (prior to weld acceptance)

Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.

A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor

Page 6: RFI for 18.03.2014 Piping, Welding at SESA Fab

REQUEST FOR INSPECTIONSaudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. SA-RCTF-SS-WD-035

BI 10-00741 JO SO2636 Phase Title Clean Trasportation Fuels at Riyadh Refinery

To : Project Inspection Unit/Mr. Mr. Ali Saud Civil Mech Plumb. Comms. Elect. Other

Inspection /monitoring is required on (date) 17-Mar-14 at (time) 9:00 PM prior toSelection of Weld joints for NDE

for the following location/equipment SESA FABRICATION SHOP

Work Permit required: Yes No Project Quality Plan: Hold Point Witness Point

SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected isinspection and conforms to the project requirements. complete and in compliance with the following specifications:

SAPMT Name Mr. Julius Sawyer SAES/SAMS/Other # SAES-W-011Signature Date Contractor/Company SAMSUNG EPC CO. LTD.Telephone Fax QA/QC Name ONNY HENDRA

QA/QC Signature Date 16-Mar-14

This form received by the undersigned Inspection Department employee:

Name Mr. Ali Saud Signature Date Time

Distribution:

QR Number #

QMIS RFI #

NOTE

SATIP SATIP-W-011-01SAIC SAIC-W-2015SATIP ITEM NO. 3.11SA INSPECTION LEVEL WCONTRACTOR INSPECTION LEVH

Note : Inspector's signature is for receiving this this request only and not for approval or disapproval of the work or facility inspected.

A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor