    3 / 5

    Once the work starts the group will be divided into TG.In the following Table is presented a brief summary of the main milestones of theproject:

    Month

    Activity Deliverable

    Year 2012

    MayISO 9001 Aligned withAnnex SL

    ISO 9001 Aligned with Annex SL,

    Design Spec

    Project Plan

    Annex SL Justification Study

    Jun WG24 physical meeting

    Identification and review of inputs

    Preparation of NWIP (including

    WD1 ISO 9001 and design spec)

    Jul Start of NWIP ballot Decision on the revision of the standard

    OctFormal start of therevision project

    Analysis of NWIP comments and preparation forNov WG24 meeting

    Nov

    TC176/SC2 plenary & SC2 decision on project timeline

    WG24 physical meeting Review of additional inputs

    Timeline confirmed to ISO C/S WD1 (Rough draft)

    Dec WG24 Electronic workingWD1 (Final draft)for circulation among WG24experts

    Year 2013

    Mar WG24 physical meeting CD (Rough draft)for ballot & comment

    April WG24 Electronic working CD (Final draft)

    June CD ballot starts SC2 members review and vote on CD

    Nov WG24 physical meeting DIS (Rough draft)

    Year 2014

    Jan WG24 Electronic working DIS (Final draft)

    Mar DIS draft to ISO

    Apr DIS ballot starts Validation

    Nov WG24 physical meeting Draft FDIS

    Year 2015

    Jan WG24 Electronic working Final draft FDIS

    Mar FDIS to ISO

    July FDIS Ballot starts

    Aug FDIS ballot closes

    Sept ISO & Publication ISO 9001:2015

    Design Specification Overview (Document N 1088)

    ISO 9001:2015

    Rolf Dieter Duplois