Upload
olivia-wade
View
216
Download
1
Tags:
Embed Size (px)
Citation preview
Revised Environmental Site Assessment Guidelines & Asbestos Inspection Guidelines for Bridges
Revised Environmental Site Assessment Guidelines
Revised Environmental Site Assessment GuidelinesDeveloped in April 2009Revised with All Appropriate Inquiry as it relates to
Environmental Site Assessment under NEPA
No ROW ESA ScreeningFormerly ESA Screening by Appendix CUsed for sites or projects with:
Little or No ROW acquisitionDeep excavation expectedBUSTR file(s) to be reviewed
Restricted to identification of PCS for material management concerns
Phase I ESA If an ODOT ESA Screening includes an ODOT GIS
regulatory database search, another regulatory database search will not be conducted
InterviewsInterview current and past owners/tenantsIf an owner and/or tenant refuses to be interviewed, or
can not be reached, document the attemptsOccasionally, an owner will contact ODOT to deny
access to property. ODOT will inform consultant not to enter. This is to be documented in the report
Phase I ESA, cont ODOT’s Office of Aerial Engineering is the preferred
source for historical aerialsHistorical aerials begin in 1938May be obtained digitallyTypically more available and of better qualityAerials are free of charge from the Office of Aerial
Engineering to prime consultant for projects that have been assigned a Project Identification Number (PID)
If a database search firm does not have historical aerials, this does not release the consultant from the requirement of obtaining historical aerials.
Phase I ESA, contDocument the last date of use for USTs to determine
if it is an orphan UST (last use before 11/8/84)Do not rely on database search firms for directories
Unlike fire insurance maps, directory companies have not been consolidated making the information obtained from a database company less reliable
Unlike AAI, ODOT does not obtain property access for Phase I ESA investigationsLandowner notification letter may be sent by ODOT or
the prime consultant
Phase I ESA UpdatesProject specific and not time dependant as in AAI
OES determines if an update is needed and the information required
Why?ODOT typically goes into negotiations with regulatory
agencies on sites of concernODOT Districts monitor project areas for significant
changes and notify OES when there are concerns
Phase II ESADiscussion on Right of Entry
ODOT and/or their consultants may enter site as per ORC§163.03 and ORC §5517.01
ODOT or prime consultant sends Landowner Notification Letter
If consultant is denied access, contact ODOT DEC and prime consultant (if applicable)
ODOT will confer with landowner(s) to resolve any issuesIf still denied, ODOT will determine the necessity of
Phase II ESA on the site.If necessary, consultant may be escorted on site by law
enforcement (extremely rare)
Phase II ESA, contAny change in the scope of work requires prior
approval from OESExamples: multiple samples from 1 soil boring sent to
lab, or additional borings placed on a siteProhibited field changes
Water samples are not to be substituted for soil samples
PID, FID, and OVA readings are not substitutes for lab analysis; one sample per boring should be sent off for lab analysis.
Planning, Production & Real Estate AcquisitionDetails how ODOT acquires contaminated propertyConsultants could be asked to:
Conduct additional environmental site assessment studies
Prepare remedial options and estimated costs report May be used to support reduction of property value
Attend meetings with ODOT and/or regulatory agencies
Asbestos InspectionGuidelines For BridgesSeptember 13, 2010
Asbestos Inspection Guidelines for Bridges
Bridges are considered structures and require inspectionArranged by the DECConducted under NESHAP, prior to completion of Stage 3 plans and is
outside of the NEPA process NESHAP requires notification of all structures that will be demolished and
certain structures that will be renovatedInspections are performed to determine the amount of Asbestos present,
which is needed to complete the renovation/demolition notification requirements of NESHAP
Asbestos Inspection Guidelines for Bridges, cont
Inspections are to be conducted on the entire structureAsbestos Inspection proposals must include all costs,
including any equipment needed to fully inspect the bridgeIf there are any issues, contact either OES or the DECRequires a letter report and includes partially filled out the
OEPA Notification of Demolition and Renovation formConsultant fills out sections I, II, III, IV, VI, and VII of the
OEPA Notification of Demolition and Renovation form
Asbestos Inspection Guidelines for Bridges, contLetter Report includes
Date of inspectionLocation of structureDistrict Headquarters’ address and phone numberName, signature, and asbestos hazard evaluation
number of person who wrote reportHow the sampling locations were determinedAnalytical report
Asbestos Inspection Guidelines for Bridges, cont
Name, signature and asbestos hazard evaluation specialist number of each person who collected samples
Blueprint, diagram, or written description of the following Type of material, location and amount of confirmed ACM Sample location and date of each bulk sample Location and amounts of suspected ACM, friable and nonfriable
Asbestos Inspection Guidelines for Bridges, cont
The notification form is provided to the contractor who will comply with any remaining NESHAP requirements, fully complete the form, and send it into the OEPA
During construction, asbestos handling procedures are addressed by the following:On bridges in Construction and Materials Specification (CMS)
202.03Concrete water pipe in CMS 202.04Additional information may be found in the Construction Manual
of Procedure under sections 202.03 and 202.04
QUESTIONS?