Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Reverse Rotation in Centrifugal Compressors
40th Turbomachinery Symposium12-15 September 2011 – Houston,TX
Presented by Amr Gad
501
Outline
• Introduction• Process overview• Compressor design & construction • Narrative of reverse rotation events• Cause of reverse rotation• Possible impacts of reverse rotation• Mitigating actions taken • Lessons learned• Conclusion
1
502
Introduction
RasGas RasGas Condensate operation Condensate operation
Plant phase 1Plant phase 1Plant phase 2Plant phase 2
Loading CompressorsLoading Compressors
Shutdown statusShutdown statusphase 1 sitephase 1 site
Compressors reverse rotation Compressors reverse rotation existsexists
Presentation Purpose :Presentation Purpose :11-- Explain the impacts ,cause, and mitigations related to phase 1 Explain the impacts ,cause, and mitigations related to phase 1 compressors operation.compressors operation.22-- Phase 1 compressor operation lessons learned implemented in phaPhase 1 compressor operation lessons learned implemented in phase 2 .se 2 .
Shutdown statusShutdown statusPhase 2 sitePhase 2 site
No compressors reverse No compressors reverse ––rotation rotation
2
503
Process Overview
Phase 1 (since 2005)• Six compressors.• Design pressure ratio for LP ,MP, HP is about 3 for each stage
(Pd / Ps).• Design overall pressure ratio for the machine about 28 (Pd /
Ps).• Volume of suction vessels LP, MP, HP more than 50 meter
cube for each.
Phase 2 (since 2009)• Four compressors in operation. • Similar design pressure ratio & overall pressure ratio as phase
1.• Triple the volume of suction vessels compare to phase 1.
3
504
Process Overview
ITVs
1ST
2N
D
3RD
ASV 100% Close
Cooler
SDV Open
SDV Open
Machines During Normal Operation
4
505
Compressor Design & Construction
Phase 1 • Unit configuration: Fixed speed electric motor &
gear box& compressor.• Compressor rated at: 3.7MW• Motor rated at: 4.2 MW • Gear box speed: 1480 / 10258 RPM• Compressor operating speed: 10258 RPM
• Seal configuration: Unidirectional dry gas seal.• Bearing construction:
• Compressor: Tilt pad self equalizing• Motor: Cylindrical sleeve bearing
• Gear box design: Double helical.• Lube oil: Rundown tank with two AC pumps (Main
& Auxiliary).5
506
Reverse Rotation Events
• Reverse rotation happened since commissioning of the machines.
• However, they were only discovered after 18 month of units operations. Late discovery was due to:• No reverse rotation detection system installed.• No prior experience in-house with reverse rotation in this type of
process configuration.
6
507
Cause of Reverse Rotation
RCFA findings:• Reverse hydraulic
flow due to large amount of entrapped hydrocarbon volume in the piping and suction vessels of the MP & HP sections.
7
508
Cause of Reverse Rotation
• Hydraulic flow occurs after 10-15 seconds from a stop command till compressor coast down to zero RPM speed.
• Hydraulic flow during the reverse rotation from zero speed till 5000 RPM and back to zero again within 4 to 6 minutes.
8
509
Cause of Reverse Rotation
Speed trend (Figure A)• Unit stop very fast after stop
command.• Unit speed ramp up again in
reverse rotation to almost 5000 RPM for the compressor.
• After speed reaches 5000 RPM it cost down again to zero speed in about 4-6 minutes.
• This phenomena is repeated each time the machine stops.
Flow rate trend (Figure B)• Showing flow exchange &
equalizing between stages.
Figure A
Figure B
9
510
Possible Impacts of Reverse Rotation
Lube oil system design doesnLube oil system design doesn’’t support reverset support reverserotation with total electric power black out , asrotation with total electric power black out , asauxiliary and emergency pumps is AC driven and auxiliary and emergency pumps is AC driven and the overhead tank is designed for only 3 minutes .the overhead tank is designed for only 3 minutes .
Existing unidirectional dry gas seal are not Existing unidirectional dry gas seal are not guaranteed for such modes of operations as per guaranteed for such modes of operations as per OEM guide lines.OEM guide lines.
No detailed study conducted by OEM to confirmNo detailed study conducted by OEM to confirmimpacts on various machines components impacts on various machines components ( Impeller vanes, diffusers, Labyrinth seals ,( Impeller vanes, diffusers, Labyrinth seals ,……etc ). etc ).
Compressor componentsCompressor componentsfailure due to reversefailure due to reverse
rotationrotation
Bearings damageBearings damage
Uncontrolled gas releaseUncontrolled gas releasefrom the compressors.from the compressors.
10
511
Mitigating Actions. Phase 1 Compressors
• Minimize the number of units starts and stops until modify the system.
• Future installation of check valves at the suction of the LP & MP.
ITVs
1ST
2N
D
3R
D
ASV 100% Close
Cooler
SDV Open
SDV Open
11
512
Mitigating Actions. Phase 2 Compressors
• Interim - modified the I&C for the ITV’s of the MP & HP to fully close during machine stop.
• Final - install check valves at the suction of the LP, MP and immediately after the discharge.
ITVs, final position
1ST
2ND
3RD
ASV 100% Close
Cooler
SDV Open
SDV Open
12
513
Shutdown with ITV closing before tuning
Shutdown With ITV closing after tuning
Shutdown with check valve installed and ITV closure removed
Mitigating Actions. Phase 2 Compressors
13
514
Lessons Learned
• Dynamic simulation requirements for such process configurations.
• Mitigating actions to eliminate reverse rotation should consider:• ITV modification for complete closure during shutdown. • Installation of check valves at suction lines.
• Machines construction should include mitigating design:• Bidirectional seal will eliminate risk from reverse rotation.• Center pivot for tilting pad can accommodate reverse rotation
better than offset pivot design.• API standard is for 3 minutes run down tank design and so,
emergency DC pump is an advantage.
14
515
Conclusions
• Reverse rotation phenomena have potential to occur in the LPG refrigeration cycles.
• Reverse rotation phenomena is more common in the motor driven compressors with relatively low machine inertia.
• Detailed surveillance of coast down speed trends of new units is recommended to ensure detection of Reverse Rotation:• Reverse rotation phenomena may not increase vibration or axial
movements above alarm values.
15
516
Thank YouThank You
517
Pressure trends for unit stop
171K001B BOG COMP SUCK001B 1ST SUCTION PRESSK001B 2ND SUCTION PRESSK001B 2ND SUCTION PRESSK001B 3RD SUCTION PRESSK001B 3RD SUCTION PRESSK001B DISCHARGE PRESS171K001B C3 BOG COMP OUT
171PI1221B.PV
BARG171PI1224BA.PV
BARA171PI1226B.PV
BARG171PI1228BA.PV
BARG171PI1231B.PV
BARG171PI1233BA.PV
BARG171PI1236BA.PV
BARG171PI1237B.PV
Plot-0
11/23/2006 6:33:38 PM 11/23/2006 6:41:06 PM7.47 minutes
4
9
14
19
-1
22
4.40
4.38
4.41
4.41
4.41
4.41
4.40
0.20Pressure equalization between the three stages in conjunction with the reverse rotation
16
518
• ASV improper function is potential cause for reverse rotation during coast down.• Experienced in LNG BOG compressor when opening time upon
shutdown is more than 2 seconds due to valves stuck or instruments failures.
71K051A BOG COMP DSCH 71K051A BOG DSCH PRES 71KX051A GR KYPHSRCOMP SD 71KX051A GR KYPHSRMTR SD
71FI3142A.PV
KNM3/H71PI3129A.PV
BARG71SI3508A.PV
RPM71SI3510A.PV
RPM
Plot-0
6/6/2007 11:37:03 AM 6/6/2007 11:47:08 AM10.08 minutes
5
10
15
20
25
0
30
0
30
0
14000
0
3000
0.
0.
0.3953
0.
71K051A BOG COMP DSCH 71K051A BOG DSCH PRES 71KX051A GR KYPHSRCOMP SD 71KX051A GR KYPHSRMTR SD
71FI3142A.PV
KNM3/H71PI3129A.PV
BARG71SI3508A.PV
RPM71SI3510A.PV
RPM
Plot-0
10/6/2006 9:29:51 PM 10/6/2006 9:32:05 PM2.23 minutes
5
10
15
20
25
0
30
0
30
0
14000
0
3000
0.
0.
0.45781
0.
17
519