Restoration Procedure of NER Grid Nov-2013

Embed Size (px)

Citation preview

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    1/89

    BLACK START

    AND

    RESTORATION PROCEDURES

    OF

    NER GRID

    - 9

    :2013

    ( )

    ,

    7930069th Revision

    Month: November2013

    POWER SYSTEM OPERATION CORPORATION LTD(A wholly owned subsidiary of POWERGRID)

    NORTH EASTERN REGIONAL LOAD DESPATCH CENTRE,Shillong793006

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    2/89

    Black start and Restoration Procedures of NER Grid

    INDEX

    CHAPTER DESCRIPTION PAGE NO

    1 Black Start Facility 1-3

    2 System Restoration Approach 4-9

    3 Power Maps of NER 10-18

    4 Network Diagram of NER 19-27

    5 Broad classification of North Eastern Regional Grid 28-34

    6 Black Start & Restoration Procedures 35-76

    6.1 Restoration of NER Grid after total collapse, when

    power from Eastern Region (ER) is available

    36-55

    6.2 Restoration of NER Grid after total collapse, when

    power from Eastern Region (ER) is not available

    56-71

    6.3 Restoration of 400 / 132 kV Network comprising of

    Manipur, South Assam, Mizoram, Tripura, AGTPP and

    Palatana after partial collapse.

    72-75

    6.4 Restoration of 132 kV Network comprising of Manipur

    (except Jiribam) and Loktak, after partial collapse.

    76-76

    7 Reporting Procedure 77-81

    List of Annexures

    Annexures DESCRIPTION PAGE NO

    i) List of Power Stations with black start facilities 83

    ii) List of Major sub-stations with synchromising facilities 84

    iii) List of shunt reactors in NER 85

    iv) Addition of New Transmmission Lines 86

    v ) Three phase fault level of Major Sub-stations in NER 87

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    3/89

    Black start and Restoration Procedures of NER Grid

    North Eastern Regional Load dispatch Centre, Shillong

    Black Start Facil i ty1.1 ----- Existing Black Start Facilities

    1.2 ----- Survival/ Auxiliary Power requirement

    1.3 ----- Startup power requirement

    1.4 ----- Synchronizing facilities at Power Stations / major Sub-Stations

    1.5 ----- Shunt Reactors at major Power Station and Sub-Stations

    CHAPTER 1

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    4/89

    Black start and Restoration Procedures of NER Grid

    1.1 Existing Black Start Facilities:

    A list of Generating Stations of NER (North Eastern Region) having black start facilities

    is elaborated in Annexure-I

    1.2 Survival/ Auxiliary Power requirement:

    Survival/Auxiliary power is required to avoid damages of some equipment as well as

    functioning of some essential facilities, in case of supply failure. Immediate

    arrangement of power is very essential for the following:-

    1. Battery Charging

    2. Emergency Lighting

    3. Compressors for breaker operation4. Lubricating Oil Pumps

    5. Communication & Telemetry System

    6. Turbine Emergency Oil Pump

    In power stations of NER, auxiliary power requirement is very nominal i.e. around 100-

    150 kW as unit sizes are small except Ranganadi units.

    1.3 Startup power requirement:For restoration of Generating Unit, startup power is required for its auxiliaries. The

    requirement of Startup power of various units is as follow:-

    Gas - 2 % of Unit Capacity

    Hydro - 1 % of Unit Capacity

    Startup power requirement for Gas Generating Unit is high as the major auxiliaries like

    Gas Compressor, BFP, ID Fan, FD Fan, CW Pump etc. are of bigger size and the

    starting torque is large. However, startup power requirement for Hydro Generating Unitis less because of few auxiliaries.

    List of DG Set installed in the Generating Stations is atAnnexure-I

    1.4 Synchronizing facilities at Power Stations / major Sub-Stations:

    Synchronizing facilities play a vital role in building up of systems and also for inter-

    connection of different sub-systems/islands. List of major Sub-Stations which have

    synchronization facilities is indicated at Annexure-II.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    5/89

    Black start and Restoration Procedures of NER Grid

    1.5 Shunt Reactors at major Power Station and Sub-Stations:

    It is very essential to contain voltage during the restoration process of a collapsed

    system. During the early restoration process, lines are generally lightly loaded due to

    the restricted drawl by the drawing utilities and voltage starts rising up in different busesas system size grows. Shunt Reactors play a vital role to contain voltage. List of Shunt

    Reactors available in NER is indicated in Annexure - III.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    6/89

    Black start and Restoration Procedures of NER Grid

    SYSTEM RESTORATION APPROACH2.1 ----- General Guidelines

    2.2 ----- Initial Course of Action

    2.3 ----- Important Considerations during Restoration

    2.4 ----- Special Consideration in extending/availing start up power

    2.5 ----- DONTS

    CHAPTER 2

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    7/89

    Black start and Restoration Procedures of NER Grid

    The following specific points must be adopted considering the importance of system

    restoration:-

    2.1 General Guidelines:i) This document should be available in the Control Room of each Load Despatch

    Centre & readily accessible to all system operators.

    ii) Black Start and Restoration Procedure of Regional Grid under various conditions

    (Partial / Total Blackout) shall be reviewed /updated by NERLDC annually in

    consultation with NLDC, all Users, STU, SLDC, CTU and NERPC Secretariat.

    (As per Clause No 5.8(a) of IEGC)

    iii) Black Start and Restoration Procedure of each system of Users/STU/CTU withina Region under various conditions (Partial / Total Blackout) will be finalized by

    the concerned Users/STU/CTU in co-ordination with NERLDC. The procedure

    will be reviewed, confirmed and/or revised once every year. Mock trial run of this

    procedure for different sub-system shall be carried out by Users/STU/CTU at

    least once in every six months under intimation of NERLDC. Diesel Generators

    set for black start would be tested on weekly basis and test report shall be sent to

    NERLDC on quarterly basis. (As per Clause No 5.8(b) of IEGC)

    iv) List of essential loads with categories to be prepared by User/SLDC and sent to

    NERLDC. Inter State/Inter Regional links, synchronizing points and essential

    loads to be restored on priority shall be available with NLDC, RLDC & SLDC. (As

    per Clause No 5.8(c) of IEGC)

    v) NERLDC will co-ordinate entire restoration process through SLDC /ISGS

    /POWERGRID etc.

    vi) During restoration process, NERLDC is to be allowed to operate the Grid with

    reduced security standard for voltage and frequency in order to achieve fastest

    possible recovery. (As per Clause No 5.8(d) of IEGC)

    vii) All communication channels required for voice communication during the

    restoration process must be operational. At least one channel of voice

    communication is to be kept free for NERLDC communication. (As per Clause No

    5.8(e) of IEGC & As per Clause No 17 of CEA (Grid Standards) Regulation)

    viii) Healthiness of communication system and ancillaries at all Load Despatch

    Centres, Power Stations and Sub-Stations should be checked at least once in

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    8/89

    Black start and Restoration Procedures of NER Grid

    every week to ensure availability of communication system during the periods of

    crisis.

    ix) List of phone numbers(V-SAT, Landline, Mobile & ULDC) of Control Rooms of

    all Load Despatch Centres, Power Stations and important Grid Sub-Stationsshould be available at all Control Rooms and to be distributed to all concerned.

    Any change or addition of above phone numbers should be incorporated time to

    time and to be communicated to all concerned.

    x) Constituents should organize one day appreciation course on power system

    restoration at regional level, at least once in a year for

    a. Top Management Group/Chief of Load Despatch Centres

    b. Load Despatch Personnel/Power System Operators/Sub-Station

    Operators

    xi) System Operators are expected to be thoroughly conversant with

    a. Reactive Capability of Generators

    b. Voltage Control through the following means :-

    Charging the shorter line first

    Switching off Capacitor Bank

    Taking Bus Reactors into service

    Charging Transformers and taking Bus Reactors into service

    Converting Line Reactors into Bus Reactors wherever feasible.

    Operating Generators at minimum Voltage levels

    Changing Transformer Taps

    Energisation of fewer High Voltage Lines.

    c. Network connectivity by heart and

    d. They should be able to converse fluently in Hindi/English

    xii) Power Station which has Black Start capability should be tested at least once in a

    month. Power Station which has DG Set should be explored for Black Start

    Capability.

    xiii) Synchronization facility wherever available should be checked periodically and

    should be kept in working condition. Periodic report of non-functioning of

    Synchronoscope is to be sent to NERLDC.

    xiv) All equipment such as Disturbance Recorders and Event Loggers shall be kept in

    healthy condition, so that under no condition such important data is lost. Periodic

    report of non-functioning of Disturbance Recorder/Sequential Event Recorder to

    be sent to NERLDC. (As per 15.4 of CEA Grid Standards Regulation)

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    9/89

    Black start and Restoration Procedures of NER Grid

    xv) Priority wise loads are to be secured in steps during restoration process. This is

    to be documented by each User/SLDC and informed to NERLDC.

    xvi) OLTC of Transformers shall be tested at least once in a week. Periodic report of

    non-functioning of OLTC of Transformer to be sent to NERLDC.2.2 Initial Course of Action:

    i) Assess (a) extent of black out, (b) whether any sub-system/island is alive or not,

    (c) whether interconnection with Eastern Region is still there or not. If

    interconnection with Eastern Region is there, then how much load can be

    connected

    ii) Appraise the severity of disturbance to all concerned.

    iii) Open all circuit breakers at Power Station / Sub-Stations that have blacked out,to establish well defined starting point of restoration.

    iv) Note the relay indications and reset them, if operated.

    v) Check whether any equipment or any element has suffered damage or

    developed a technical snag.

    vi) Chalk out the optimum path for restoration after checking the grid elements that

    were under outage before disturbance.

    vii) Defer all planned outage as per IEGC 5.7.4 (g)

    2.3 Important Considerations during Restoration:

    i) Generating Stations which have black start facilities have to start up immediately.

    ii) Availability of Generation Capacity in each island / sub system to be ensured.

    iii) Availability of transmission lines in the interconnection between islands / sub

    systems to be ensured.

    iv) Load to be added in small steps with smaller and radial loads. Larger load may

    be connected after consultation with NERLDC.

    v) For developing island / sub system, special care should be taken to closely co-

    ordinate the load pick-ups with the ramp rate of generation and to be ensured

    that the frequency of the island is maintained within sustainable limit (around 50

    Hz).

    vi) If required, Governor and AVR of the units of the island are to be kept in manual

    mode.

    vii) UFRs are to be kept deactivated as frequency excursions at this stage may be

    wider than normal condition. SPS are also to be kept deactivated.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    10/89

    Black start and Restoration Procedures of NER Grid

    viii) A reasonable active to reactive power ratio is to be maintained so that the

    machine can be operated normally.

    ix) Auxiliary power to be readily available so that machine can be operated normally.

    x) Total auxiliary power drawn by the sub-system to be kept within 3% of thecapacity of the source.

    xi) Before synchronization between two islands there should be proper co-ordination

    for frequency adjustment.

    xii) Risky synchronization shall be avoided as small island may not be able to survive

    the jerk

    xiii) While releasing loads, it is to be ascertained whether machines can supply the

    power.

    xiv) Tap Position of Transformer, Bus Voltage and Frequency at Power Stations and

    Sub-Stations should be closely monitored to ensure that over fluxing does not

    occur.

    xv) Shift personnel should promptly formulate the strategy to be adopted in co-

    ordination with NERLDC for quick restoration of the Grid.

    xvi) The work of restoration in the Control Room should be shared & coordinated

    among the shift personnel for smooth & quick restoration. Crisis Management

    Group to be formed, consisting of expert personnel & called for early restoration

    of the system.

    xvii) Shift personnel should preferably be retained till restoration is over, before

    handing over the charge to the next shift.

    2.4 Special Consideration in extending/availing start up power:

    I. Power Plant Operators should be able to differentiate between the followings :

    a. Full auxiliary power needed to start all machines

    b. Minimum auxiliary power needed to start a minimum number of

    machines.

    II. For availing start up power, the following considerations should be kept in mind :

    a. Nearness to the source

    b. 132 kV lines vis--vis 220 kV/ 400 kV lines

    c. Shorter route having a number of intermediate sub-stations vis-a-vis

    longer route having very few/ no intermediate sub-stations

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    11/89

    Black start and Restoration Procedures of NER Grid

    III. For extending start up power from one sub-system to another sub-system or from

    one utility to another utility, the following clear-cut authority should be given to

    SLDC :-

    a. Line through which start up power is to be extendedb. Quantum of such start up power

    c. Normal time period admissible

    IV. Concerned SLDC should also be empowered to resort to load shedding or

    bring up additional generation wherever possible, to extend start up power

    to neighboring sub-systems/utilities during the period of crisis.

    2.5 DONTS:

    i) Do not panic

    ii) Do not load any Generator beyond 80% of its capacity

    iii) Do not load any Line/ICT beyond 80% of its capacity

    iv) Do not hastily connect loads and ensure that the island / sub-system frequency

    be within sustainable range

    v) Once power extended to a Power Station/Utility, it should not be withdrawn

    except in case of extreme emergency and without intimation to NERLDC, as

    actions taken up at Power Stations would have to be redone.

    vi) No communication disputes should be raised during the restoration period.

    vii) Till the restoration procedure is over, load despatch centers should not be

    disturbed in undesirable manner while discharging their duties and they should

    not be expected to function as Management Information System.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    12/89

    Black start and Restoration Procedures of NER Grid

    North Eastern Regional Load dispatch Centre, Shillong

    Power Maps of NER3.1 ----- NER Network

    3.2 ----- Assam Network

    3.3 ----- Arunachal Pradesh Network

    3.4 ----- Meghalaya Network

    3.5 ----- Manipur Networh

    3.6 ----- Mizoram Network

    3.7 ----- Nagaland Network

    3.8 ----- Tripura Network

    CHAPTER 3

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    13/89

    9

    WestBengal

    3.1 POWER MAP OF NORTH EAST REGIONAL GRID

    Chin

    Along

    Daporizo

    BhutanRanganadi

    Ziro

    Naharlugan13

    Dhemaji

    Tinsukia

    Dibrugarh

    Doomdooma

    Margherita

    KhupiBhalukpong

    NirjuliMajuli

    Maran

    Sibsagar

    AGBPP

    17

    Bhutan

    Birpara(ER)

    Gelyphu(Bhutan)

    Salakati

    Motonga(Bhutan)

    Rangia

    Balipara

    921

    Gohpur

    12 14

    15 Mariani(PG)

    Nazira

    18

    16

    Mokokchung

    Deomali

    Binaguri(ER)

    Gossaigaon

    Gauripur

    Bongaigaon

    BTPS 2

    1

    BTPS (NTPC)

    4

    3

    Kukurmara

    5 7

    Kahilipara6

    8

    Sarusajai 9

    11

    10Misa

    SamaguriGolaghat

    Bokajan

    Doyang

    WokhaKiphire

    Rongkhon

    Agia

    Boko8

    54

    6 7

    Langpi

    Kopili Sankardevnagar

    Diphu

    Dimapur

    Dimapur (S) Kohima

    Meluri

    NEEPCO (in MW)

    Nangalbibra3

    Mawngap

    Nongstoin Mawlai

    NEIGRIHMS

    2 1Khleihriat(S) Khandong

    Haflong Karong

    Ranganadi - 3x135

    Doyang - 3x25

    Cherapunjee NEHU LeshkaKhleihriat

    Haflong

    AGBPP - 4x33.6+2x35+3xAGTPP - 4x21

    BangladeshLumshnong

    Dullavcherra

    Badarpur

    19 20

    SrikonaPailapool

    Jiribam

    Imphal(S)

    Imphal

    Rengpang

    Yaingangpokpi

    Khandong - 2x25

    Kopili - 4x50

    Kopili St II - 2x25

    Tripura

    1. Dharmanagar

    2. Kailashahar

    3. Kamalpur

    4. Dhalabil

    Meghalaya

    1. Umiam

    2. Umiam St I3. Umiam St II

    4. Umiam St III

    Bangladesh 13

    4 2AGTPP

    Kolasib

    Silchar

    BairabiLoktak

    Churachandpur

    Kongba

    Ningthonkhong

    Kakching

    Important Lines (in ckm)1. 400 kV Misa-Balipara D/C - 190

    2. 400 kV Balipara-Bongaigaon D/C - 5803. 400 kV Balipara - Ranganadi D/C - 3324. 400 kV Bongaigaon - Binaguri D/C - 436

    NHPC (in MW)

    Loktak - 3x35

    LEGEND

    400 kV -5. Agartala6. Bodhjangnagar

    5. Umiam St IV6. Umtru

    8 95 6

    710

    KumarghatLuangmual 1. 220 kV Misa - Dimapur D/C - 247

    220 kV -132 kV -

    7. Jirania8. Baramura

    9. Teliamura

    10. Ambasa

    11 Surjamaninagar

    Assam

    7. EPIP II (Norbong)

    8. EPIP I (Raja)

    9. Killing (Byrnihat)

    11

    Rokhia

    Udaipur

    Palatana

    P.K. BariAizawl

    Zuangtui

    Serchhip

    (Bukpui)

    Saitual

    2. 220 kV Misa - Mariani S/C - 220

    3. 220 kV Misa- AGBPP S/C - 382.9

    4. 220 kV Misa - Samaguri D/C - 68.8

    5. 220 kV MIsa - Kopili T/C - 221.4

    6. 220 kV Samaguri - Mariani S/C - 168

    7. 220 kV Mariani - AGBPP S/C - 162.98. 220 kV Balipara - Samaguri S/C - 65

    Hydro -

    Thermal -

    POWERGRID

    NEEPCO

    NHPC

    1. Jogigopa2. Dhaligaon

    3. Nalbari

    4. Bornagar

    5. Sipajhar

    6. Sisugram

    7. CTPS

    8. Narengi9. Rowta

    10. Baghjap

    11. Depota

    12. Pavoi

    13.

    NLakhimpur

    14.- Bokaghat15. Jorhat

    16.LTPS

    17.NTPS

    18. Mariani

    19. Panchgram

    20.

    Panchgram(New)

    BangladeshKhawiva

    (Lunglei)

    9 - 220 kV Sarusajai - Samaguri D/C - 247

    10. 220 kV Bongaigaon - Salakati S/C - 1

    11. 220 kV Salakati - BTPS D/C - 8

    12. 220 kV Sarusajai - Langpi D/C - 216.4

    AssamMeghalaya

    Tripura

    Others

    11

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    14/89

    )

    g

    .2 POWER MAP OF ASSAM

    Doomdooma

    inaguri (PG)Gelyphu(Bhutan) Motonga

    Khupi (NO)

    North Lakhimpur

    Ranganadi (NO)

    Nirjuli (PG)

    Gohpur

    Dhemaji Tinsukia

    Dibrugarh

    Maran

    Margherita

    AGBPP (

    NTPS

    Birpara (PG)

    Salakati (PG)

    Bhutan (Bhutan) Balipara (PG)Ghoramari

    Rowta

    DepotaPavoi

    MajuliLTPS

    SibsagarNazira

    Deomali (AP)

    Gossaigaon

    BTPS(NTPC

    Bongaigaon (PG)

    Dhaligaon

    Bornagar Rangia

    Nalbari

    Sipajhar

    Sisugram

    CTPS

    Bokakhat

    SamaguriGolaghat

    Jorhat (Garmur)

    Mariani

    MokokchungBTPS

    AgiaGauripur

    Jogigopa

    Boko

    KahiliparaBagjhap

    Langpi

    Misa (PG)

    Sankardev Nagar

    Bokajan

    MeghalayaKukurmara

    Sarusajai Kopili (NO)

    Diphu Dimapur(NG)

    NarengiKilling

    (Byrnihat) (ME) Khandong (NO)Dimapur (PG)

    Umtru (ME) Haflong

    Khliehriat (PG)

    Haflong (PG)

    Lumshnong (ME)

    Badarpur (PG)

    BangladeshDullavcherra

    TripuraPalatana (OTPC)

    Dharmanagar (TR)

    Kumarghat

    Panchgram(old)

    Panchgram(New

    Srikona

    Silchar

    Kolasib (MI)

    Pailapool

    Jiribam (PG) Legend400 kV

    220 kV

    132 kV

    66 kV

    Gas

    Hydro

    12

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    15/89

    Bhutan

    3.3 POWER MAP OF ARUNACHAL PRADESH

    Legend400 kV220 kV132 kV

    Hydro

    Along

    Daporizo

    Ziro (PG)

    Ranganadi

    Bhalukpong

    Khupi (NO)

    Naharlagun

    Nirjuli (PG)

    AGBPP (NO)

    Deomali

    Balipara (PG)Gohpur (AS)

    13

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    16/89

    Kahilipara (AS)

    Sarusajai (AS)

    Khandong(NO)

    3.4 POWER MAP OF MEGHALAYA

    1.Adhunik Cement

    2.Hill Cement

    3.JUD Cement4.GVIL Cement

    10. Maithan11. Sai prakash12. Greystone13. Mega carbide

    Kahilipara(AS)

    5.CMCL

    6.MCL7.Trishul8.Nalari

    14. New Umtru

    Agia (As)

    Bongaigaon (PG)

    AssamSarusajai (AS)

    Kukurmara(AS)

    EPIP II (Norbong)

    8Misa (PG)

    9. Shyam Century

    Killing(Byrnihat) Umtru

    7 13

    1211 EPIP I (Raja Bagan)

    Mendipathar14 9 10

    Ampati Nongstoin

    Umiam St IV

    Umiam St IIUmiam St I

    Umiam St III

    Umiam

    NEIGRIHMS

    NEHU

    Legend

    400 kV

    Rongkhon

    (Tura)Nangalbibra

    Mawngap

    Sohra

    (Cherapunjee)

    Mawlai

    Leshka

    Khleihriat

    Khleihriat (PG)1

    Lumshnon2

    34

    6 5

    220 kV132 kV Bangladesh

    Silchar (PG)Panchgram (AS)Badarpur (PG)

    14

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    17/89

    AizwalPG

    3.5 POWER MAP OF MANIPUR

    Dimapur (PG)

    Kohima (NG)

    Karong

    Haflong

    Badarpur (PG) Yaingangpokpi

    Pailapool (AS)

    Imphal

    (PG) Yurembam

    Jiribam

    (PG)

    Rengpang Kongba

    Loktak (NH) Ningthoukhong

    ChurachandpurKakching

    Mizoram Legend132 kVHydro

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    18/89

    Tripura

    Bangladesh

    My

    anmar

    3.6 POWER MAP OF MIZORAM

    Badarpur (PG)

    Bairabi

    Jiribam (PG)

    Kolasib

    Kumarghat

    Vairengte Serlui-B

    Luangmual

    Aizwal (PG) Zuangtui

    Saitual

    Serchhip(Bukpui)

    Khawiva

    (Lunglei)

    Lungse

    Legend

    132 kV

    66 kV

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    19/89

    ArunachalPradesh3.7 POWER MAP OF NAGALAND

    Mariani (AS)

    Naginimara

    TuliMon

    Tizit

    Mokokchung

    Doyang (NO) Tuensang

    Bokajan (AS)Dimapur (PG)

    WokhaLikhimro

    Misa (PG)1

    Dimapur

    Zunheboto

    Kiphire

    Chumukedima Meluri

    GaneshnagarKohima

    Karong (MA)

    Imphal (PG)Legend

    220 kV

    132 kV66 kV

    Hydro

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    20/89

    Aizwal(PG)

    M

    izoram

    3.8 POWER MAP OF TRIPURA

    Dullavcherra (AS)

    Dharmanagar

    Badarpur (PG)

    Silchar

    Kailashahar

    KamalpurP K Bari

    Kumarghat

    JiraniaBodhjangnagar

    Dhalabil

    (Khowai)

    Ambasa

    Agartala AGTPP (NO)Teliamura

    (Gamaitila

    Badarghat Baramura

    Rokhia

    Surjamaninagar

    Gokulnagar

    Udaipur

    Palatana

    (OTPC)

    Sonamura

    (Rabindranagar)

    Amarpur

    Gumti

    Bagafa

    Belonia

    Sabroom

    Satchand Legend

    400 kV

    132 kV66 kV

    Gas

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    21/89

    Black start and Restoration Procedures of NER Grid

    Network Diagram of NER4.1 ----- NER Network

    4.2 ----- Assam Network

    4.3 ----- Arunachal Pradesh Network

    4.4 ----- Meghalaya Network

    4.5 ----- Manipur Networh

    4.6 ----- Mizoram Network

    4.7 ----- Nagaland Network

    4.8 ----- Tripura Network

    CHAPTER 4

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    22/89

    37

    63

    3

    25

    92

    69

    13

    118

    15

    4

    18

    12

    37

    28

    41

    4

    9

    12

    41

    46

    35

    7

    18

    10 3

    126

    217

    160km

    50

    2 .23

    28 8

    30

    24

    7

    1

    57

    106

    72 6

    0 45

    10

    7

    73

    12

    11

    34

    65

    76

    2x315

    95

    15

    4x25

    45

    67

    101

    124

    63

    50

    1

    50

    65

    26

    89

    35

    39

    20

    169

    1

    26

    36

    53

    13

    2

    80

    22

    42

    60

    50

    58

    40

    50

    53

    42

    4.1Network D iagram of Nor th Eastern Regional Gri dRanganadi(NO)

    Bongaigaon(PG) 50

    2x80+2x50 50 290298 30 % 63

    Balipara (PG)

    50 16650 2x360

    3x135

    Ziro(PG Daporizo

    New Siliguri(ER) 224 63Motonga (Bhutan)

    Rangia(AS)Bhalukpong(AR) 63

    42 Nirjuli(PG) 4 1820 (AR) A

    (

    New Siliguri(ER)218

    63 63

    315 106

    Nalbari (AS)

    22

    Sipajhar(AS)49

    38 44

    Khupi(NO) 22

    72

    45

    282x50

    31550+80 N. Lakhimpur

    (AS) Naharlagun(AR)

    45

    AGBPP(NO

    87 82

    Pasigh

    Birpara(ER)

    160 Dhaligaon42 Bornagar(AS 34

    27

    108 64Rowta(AS) Depota(AS)

    9

    Tezpur(AS)

    4x25 Dhemaji(AS)

    1x10019 )

    4x33.6+2x35

    (AR)

    Roing

    Salakati(PG Gaupur 63(AS)

    AMP(AS)37

    Sisugram(AS) CTPS(AS)

    Gohpur(AS) Majuli

    222220

    Deomali(AR161 (PG)

    Gelephu(Bh) 2x50 Gossaigaon(AS) 64 1 BRPL Narengi(AS)20 2x30 Pavoi (AS)

    168 163 24 Tez

    49 3

    22 Kukurmara(A

    KaheliparaAS)12

    3 2935 5

    Dispur(AS) Jagirod (AS)

    HPC,J

    Sankardev

    Nagar

    51 77

    2x12.5

    168

    2x12.

    Mariani

    2x100

    20Mariani

    New

    (PG) Tinsukia

    (PG

    Nam(PG

    BTPS(NTPC)

    3x250 MW

    Azara (AS) 1x315 803

    Boko (AS)

    63

    3x100

    Sarusajai(AS)108

    Langpi(AS)

    2x50130

    Diphu

    (AS)

    3x50

    50Samaguri (AS)

    (AS)

    Jorhat

    (AS)

    LTPS(AS)

    4x15+3x30+

    1x37.2

    (AS)

    2x50

    BTPS .4 Trishul .3 Shyam Century Bokakhat

    (AS) 1 .1EPIP II 3Nalari

    .4 Maithan

    4.4

    (AS)45 69

    1x50 1x50

    2x80+1x1661

    2x50Umtru(ME)

    4x2.8

    30

    (ME)

    167

    EPIP I(ME)

    2x160

    Sai Prakash.7 Greystone

    1Mega Carbide

    113

    Misa(PG) Golaghat(AS)

    Nazira(AS)

    2x50

    2x25+

    NTPS(AS)3x23+1x12.5+

    1x30+1x22

    Agia

    (AS) 70Umiam IV(ME)

    8

    2x30 10Umiam St III(ME)

    2x30 2x31563

    Byrnihat(ME) Leshka(ME)3x42

    Kopili(NO)Bokajan

    (AS)Moran(AS)

    Sibsagar(AS)

    1x20

    43

    131 Umiam II(ME) 3 Umiam St I(ME)Umiam(ME) 50 Khliehriat8 26 Kopili StII(NO) 4x50 Ledo(AS)

    Palatana

    2x9Tura (ME)

    Mawngap 33(ME)

    4x953

    5 7

    (ME)

    63

    5

    Khliehriat(PG)

    1x251x60+1x160

    Khandong(NO)

    2x363

    80 57

    Nangalbibra(ME)

    2354

    Nongstoin(ME)

    Mawlai(ME)

    9

    NEHU(ME) NEIGRIHMS(ME)

    Adhunik Cement

    Hill Cement42

    JUD Cement

    Lumshnong41

    2x25

    Haflong (PG)63 1

    Dibrugarh(AS)

    1x125 63

    Udaipur(TR)

    6 40

    Rokhia(TR)6x8+2x21

    1x30

    Cherapunjee(ME)

    Dharmanagar

    35 (TR)

    Dullavcherra(AS)29

    63

    (ME)

    GVIL Cement

    CMCL

    77

    23 1

    219

    Badarpur (PG)

    Haflong (AS)

    Dimapur(PG)

    Doyang (NO)

    933x25

    Mokokc

    (PG

    247

    18 Agartala(TR

    )

    2x2

    45 Dhalabil

    50

    Kailashor

    MCL

    63 HPC,P

    Panchgram(AS)

    19140

    2x10027

    30Wokha58 (NG)

    2x

    1

    Badarghat3

    (TR)

    18

    AGTPP(NO)8

    Kamalpur

    (TR) 3231

    (TR)(TR

    ) 2x632x200

    1

    Srikona(AS)35

    Pailapool

    (AS)

    Dimapur(NG) Kohima

    (NG)

    Mokokchung(NG)

    74

    2x100+2x54x21

    130

    1041

    Silchar (PG)

    20119

    Bairabi(MZ)4x5.7

    30

    Kolasib(MZ)

    Imphal(PG)

    20 60Karong(MA)

    Kh

    36 (

    Surajmani Nagar(TR)

    Legend

    18 Bodhjangnagar(TR)8

    2x10

    P K Bari(TR)

    Kumarghat(PG)

    133 Aizawl(PG) 66

    172

    Jiribam(MA)

    Jiribam

    Imphal

    (MA) Likhimro(NG) 3x8

    Ka

    400 kV 220 kV

    132 kV 66 kV

    Line Length in km

    7

    Jirania(TR)

    14 25 45 Melriat

    5

    Sinhmui(MZ)

    20 1

    Longmol(MZ)

    Rengpang(MA) 40

    Saitual(MZ)

    (PG)82

    42

    Yaingangpokpi

    (MA)33

    23

    45

    Kongba

    (M

    Reactor/Capacitor Capacity in MVAR

    Transformer Capacity in MVA

    30Baramura(TR) Teliamura Ambasa Melriat

    (New) (PG)W. Phaileng

    Zungtui(MZ)

    50

    54 69 Loktak(NH) Ningthoukhong Churacha(MA

    Installed Capacity in MW 2x5+1x6.5+2x21 (TR) (TR)(Mz) 30 (MZ) Serchip(MZ) Lunglei(MZ) 3x35

    11 (MA)

    20

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    23/89

    70

    1

    31

    13

    63

    64

    118

    259

    50

    30

    126

    .2

    44

    18

    1

    8

    34

    113

    12

    46

    73

    76

    12

    11

    44

    57

    5

    101

    106

    43

    72

    51

    60

    65

    64

    39 8

    89

    20

    45

    26

    50

    54

    53

    22

    60

    13

    39

    80

    25

    36

    43

    3

    53

    5 3

    NETWORK DIAGRAM OF ASSAM GRID

    Bongaigaon(PG) 63

    224 63 50

    298

    290

    30% 63Balipara (PG) 73

    63 Kameng(NO)

    w Siliguri

    (ER)

    irpara

    21863

    167

    63

    63

    Killing 2x16

    2x25 Rangia

    2x16

    Khupi 67(NO)

    72 2864

    2x50

    9

    315 50

    2x10 1x16.5

    166

    57

    50

    132x200

    Ranganadi(NO)

    Pavoi

    AGBPP((ER) 160 315 Nalbari Motonga 49 Biswanath Chariali (PG) Itanagar (AR) 4x33.6+2

    Salakati2x25

    2x50+80

    Gauripur

    2x16

    106

    42

    22

    86

    Bornagar

    38 Sipajhar

    27

    Depota2x31.5

    Tezpur

    Nirjuli(PG)

    4x25

    77

    50+80 N.

    45

    383

    Majuli

    63

    Dhemaji

    2x16

    + 3x319

    Deom25

    2x50 Gossaigaon .6 BRPL 2x25108 Gohpur 220 163

    lyphu 3hutan) 49 3

    63

    2x16

    22

    37

    DhaligaonAPM

    Rowta

    2x25 1x16+1x10

    Biswanath Charali

    168168

    2x12.5

    2x100 Mariani1x20MV 1x16

    20

    Mariani New(PG) 3x10

    Doomdooma(Rupai)

    Tins

    2

    BTPS BTPS2x80+1x1601x16

    2x25 1x12.5+1x16

    Sisugram2x25

    Narengi 1x16+1x30CTPS2x30

    (Pavoi)

    452x12.5

    MVA

    80Mokokchung

    NTPC)

    x250 Agia 1x315

    Kukurmara

    632x31.5+1x40 12 20 2x16 3x50

    2x25+

    1x16

    (PG)

    LTPS

    3x20

    1x50

    1x40+1x12.5

    3

    Azara

    2x50

    Kahilipara

    2x10

    3 29

    Dispur

    1x31.5+2x30 2x16

    35

    2x16

    Baghjhap

    Samaguri

    2x25Sankardev

    Jorhat(Garmur

    2x16Mokokchung

    (NG)69

    4x15+3x30+

    1x37.2

    2x7.5

    3x20

    2x10

    Boko61

    1x50

    2x40

    Sarusajai

    3x100

    3x31.5

    Umtru(ME)

    Umtru130

    108

    Langpi

    2x50

    34

    5050

    HPC,J Nagar

    (Lanka)

    Diphu

    2x16

    2x5

    95

    2x16Bokakhat

    Golaghat

    2x25

    1x20+1x10

    1x16

    3x5

    40

    Bokajan

    2x25

    Nazira(Gargaon)

    2x25

    2x25

    Sibsagar

    2x16

    2x50

    1x31.5

    2x25+

    1x20

    1x10

    36

    2x31

    Dibrugarh

    NTP

    3x23+1x

    +1x30+

    FCI

    50Killing(ME) Misa(PG)

    2x315 4x25

    124

    50

    Dimapur(PG)

    Dimapur(PG)

    Dimapur(NG)

    Moran

    2x16

    74

    217

    42

    Khliehriat 41(PG) 77

    Panchgram

    63 2x16

    Kopili(NO)4x50

    Kopili StII (NO)

    1x25

    119

    1x60+1x160

    Khandong(NO)

    63

    107

    Badarpur (PG)67

    Kolasib(MZ)

    Haflong(PG)

    12x10

    Haflong

    63

    Silchar (PG)

    Lumshnong (ME)

    2x63

    232

    HPC,P

    140

    2x10

    Panchgram

    119

    Imphal(New)

    Kumarghat(PG)

    atana (OTPC)247

    63 50

    160

    2x200 191

    Srikona Pailapool35

    (PG)

    15

    Legend

    400 kV 220 kV

    Melriat (PG)

    29Dharmanagar (TR)

    Dullavcherra

    1x3.5

    P K Bari

    (TR)2x25

    3x10 Jiribam(PG)

    1x20 132 kV 66 kV

    Line Length in km

    Reactor/Capacitor Capacity in MVAR

    Transformer Capacity in MVA

    Installed Capacity in MW21

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    24/89

    n

    1

    18

    Legend

    400 kV

    220 kV

    132 kV

    66 k 33 kV

    Length in km

    tor/Capacitor Capacity in MVAR

    nsformer Capacity in MVA

    alled Capacity in MW

    AGBPP(NO)4x33.66+2x35.01+3x30

    Note : 1. For the sake of continuity of the Network, Lines & Buses owned by others shown

    2. 400 kV Lines owned by POWERGRID

    3 NETWORK DIAGRAM OF ARUNACHAL PRADESH GRID

    Khupi(NO)

    Bongaigao(PG)

    Bhalukpong

    30 %

    298

    290

    2x50

    63

    63

    2x315

    Balipara(PG)

    50+80

    Biswanath

    Chariali

    166

    50

    2x360

    Ranganadi(NO)3x105

    45

    Ziro(PG)

    Daporizo Along

    87 82

    Pasighat

    52

    Roing

    35

    Kimi(NO)

    8

    1x16Tezpur

    (AS)

    9

    164 4x25 50+8

    (PG)

    1x20+1x15

    Naharlagun

    Pare(NO)2x55

    1x15 2x5 1x15

    20 2x15

    Tezu

    Kameng (NO)

    Samaguri(AS) 63

    304

    Gohpur(AS)

    43 4

    4x150 73

    Lower Subansiri (NH)8x250

    2x20

    2x10 Nirjuli(PG)

    Itanagar(AP)

    Namsai

    2x15

    Miao

    Jairampur

    Deomali

    19

    2x16

    Khonsa Changlang

    1x100

    22

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    25/89

    46

    37

    9

    30

    41

    9

    113

    18

    .4 .1

    .2

    .2 82

    2 30 3

    .7km

    .4

    1km

    .3

    26

    4.4 NETWORK DIAGRAM OF MEGHALAYA GRID

    Misa(PG) Bongaigaon(PG)

    Sarusajai(AS)

    Kahilipara(AS)

    New Umtru2x40 2x160

    2

    Killing

    10

    16750

    217

    63

    Silchar(PG)

    3

    3

    Maithan

    4

    Shyam Ce

    Sai Praka

    Mendipathar

    Agia(AS)

    3

    Umtru4x2.8

    Umiam St IV2x30

    1

    41

    8

    10

    17

    Umiam St II 32x9 12

    EPIP II (Norbong)

    2x20

    Trishul

    Umiam St III2x30

    Nalari

    1x50+2x

    Greystone

    EPIP I

    MegaCarbide

    17 69

    1x12.5

    57 71Mawlai

    3x20

    Umiam

    7

    5

    2x20

    Umiam St I

    4x9

    532x20

    Ampati Rongkhon(Tura)

    1x20+4x5

    Nangalbibra

    2x12.5

    Nongstoin 3

    Mawngap 2 NEHU

    7

    NEIGRIHMS

    Khliehriat63

    8

    Legend

    1x40

    1x12.5

    2x20 2x10

    Sohra

    (Cherapunjee

    Hill Cement

    AdhunikCement

    24

    JUD Cement

    5

    Khliehriat(PG)

    Leshka

    3x42400 kV

    220 kV

    132 kV

    33 kV

    Under const

    Lumshnong

    2x5 MPL

    GVIL CMCLCement

    MCL

    Under long outage

    ine Length in km

    eactor/Capacitor Capacity in MVAR

    ransformer Capacity in MVA

    nstalled Capacity in MW

    Panchgram(AS)

    23

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    26/89

    101

    1

    35

    22

    11

    26

    60

    50

    Legend400 kV

    132 kV 33 kV

    Length in km

    ctor/Capacitor Capacity in MVAR

    nsformer Capacity in MVA

    alled Capacity in MW

    Note : 1. For the sake of continuity of the Network, Lines & Buses owned by others shown

    5 NETWORK DIAGRAM OF MANIPUR GRID

    Kohima(NG)

    Karong

    Haflong(PG) Imphal

    2x20

    Yaingangpokpi Kongba Kakching

    Badarpur (PG) 67Jiribam

    Imphal (PG)42 33 45

    Pailapool (AS) 15

    (MA)

    Jiribam

    2x50

    20

    3x20

    23

    1x20 2x20

    38

    Aizwal(PG) 172

    1x20

    (PG)

    40

    1x12.5

    Rengpang42

    Ningthoukhong

    2x12.5

    1x20

    Churachandpur

    82

    Loktak(NH)

    24

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    27/89

    7

    107

    30

    1x12.5+1x6.3Legend

    33 kV

    66 kV

    132 kV 400 k

    Line Length in km

    Reactor/Capacitor Capacity in MVAR

    Transformer Capacity in MVA

    Installed Capacity in MW

    4.6 NETWORK DIAGRAM OF MIZORAM GRID

    Badarpur(PG)

    Kumarghat(PG)

    Aizawl

    (PG)

    133

    20

    66

    172

    1

    1x6.3

    1x12.5

    Jiribam

    (PG)

    2x12.5 160

    Bairabi

    1x12.5

    Kolasib(Bawktlang)

    Silchar

    (PG)

    W Phaileng Sinhmui

    Luangmual

    50

    Melriat

    Saitual

    2x50Melriat

    5 54 1x6.3 55

    ZuangtuiBukpui Khawiva

    2x12.5 2x12.5 (Lunglei)

    25

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    28/89

    3

    124

    169

    2

    5

    1

    26

    8

    50

    58

    27

    36

    56

    50

    4.7 NETWORK DIAGRAM OF NAGALAND GRID

    Misa (PG) Bokajan(AS)

    Mokokchung (PG)2x50 53

    Mariani(POWERGRID)

    Dimapur

    Doyang (NO)3x25

    93 30

    1 50

    1x25

    Mokokchung

    Mariani(AS)Tul Nagnimora

    (PG)57 34 Tizit Mon

    Wokha

    1x7.5 46 44 31

    Imphal(PG)

    Dimapur

    3x20

    4

    Kohima

    1x5

    74

    Meluri

    Zunheboto

    Kiphire42

    Tuensang

    1x5

    1x7.5 1x5 1x5 1x5

    3x8 1x12 3x10

    Singrijan Karong(MA)

    Legend

    33 kV

    66 kV

    132 kV 220 kV

    Line Length in km

    Ganesh

    Nagar 1x10

    Power House2

    Chumukidima

    1x10

    2x10MVA

    Nito Farm

    Likhimro3x8

    Reactor/Capacitor Capacity in MVAR

    Transformer Capacity in MVA

    12

    3 1x5 1x5

    Installed Capacity in MWBokajan(AS) Dairy Farm

    26

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    29/89

    4.8 NETWORK DIAGRAM OF TRIPURA GRID

    22

    Silchar 1x4 SonamuraSatchand

    2x10 2x15 (Rabindranagar)

    5012 Gakulnagar Bagafa

    1x4Sabroom

    Badarghat 1x15 2x515 1x10

    1x15 Belonia

    80 251x5+1x10

    1x10 Dharmanagar63 24 (Mission Tilla)

    233x7.5/2.5/5

    Palatana(OTPC)Udaipur 29 Dullavcherra

    2x363 1x125 (Banduar) 1x10 (AS)

    1x15+2x1 Rokhia 1x30 1x8+2x21 2x2 Kailashar6 40 6x8+2x21 (Gournagar)

    3518 2x7.5/2.5/5

    1x1

    1x15+1x1 3x25+2x20Dhalabil(Khowai) Kumarghat

    4518 Agartala

    AGTPP(NO) 8(79 Tilla) Badarpur

    45 Surajmani Nagar 4x21Kamalpur 119

    1x1031 1 Aizawl

    1x10 2x100+2x50 104 131

    133 20

    Gumti 2x1003x5 Bodhjangnagar 126

    18 8P K Bari

    1x4 1x15 Silchar

    Monarchak (NO) Amarpur 2x257 Jirania

    1x104 2x10

    Legend

    400 kV

    132 kV

    66 kV

    33 kV

    Line Length in km

    Reactor/Capacitor Capacity in MVAR

    Transformer Capacity in MVA

    Installed Capacity in MW

    35

    3

    247

    37

    45

    25

    3

    24

    31

    15

    40

    30

    32

    35

    4

    5

    15

    18

    2x6.3

    Baramura 1x3012 25

    2x5+1x6.5+2x21 Teliamura

    1x15 1x7.5/2.5/5

    1x7.5

    Ambasa

    Teliamura(Gamaitilla) 1x6.3+1x4

    27

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    30/89

    Black start and Restoration Procedures of NER Grid

    Broad classif ication of North Eastern

    Regional Grid5.1 ----- 400 / 220 kV Network of POWERGRID

    5.2 ----- 220 / 132 kV Network of Assam System

    5.3 ----- 220 / 132 kV Network of Arunachal Pradesh System

    5.4 ----- 400 / 220 / 132 kV Network comprising of Nagaland, Manipur,

    South Assam, Mizoram, Tripura, Meghalaya, POWERGRID andNETC (North East Transmission Company)

    CHAPTER 5

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    31/89

    Black start and Restoration Procedures of NER Grid

    North Eastern Region (NER) comprises of seven states viz Arunachal Pradesh, Assam,

    Manipur, Meghalaya, Mizoram, Nagaland & Tripura. NHPC NEEPCO & OTPCL are

    the Central Generating Companies presently operating in the region with installed

    capacity of 105 MW,1130 MW & 363 MW respectively.Depending on the network connectivity, NER Grid is broadly classified as

    follows.

    a) 400 / 220 kV Network of POWERGRID

    b) 220 / 132 kV Network of Assam System

    c) 220 / 132 kV Network of Arunachal Pradesh System

    d) 400 / 220 / 132 kV Network comprising of Nagaland, Manipur,

    South Assam, Mizoram, Tripura, Meghalaya,POWERGRID andNETC (North East Transmission Company).

    5.1 400 / 220 kV Network of POWERGRID:

    This is the main back-bone network of NER Grid comprising of 400 kV and 220 kV

    transmission lines of POWERGRID (PG). NER Grid is connected to ER Grid through

    this network. The network configuration is described as below:

    a. 400 kV Bongaigaon (PG) Sub-Station of NER is connected with 400 kV NewSiliguri (PG) Sub-Station of ER through 400 kV D/C New SiliguriBongaigaon

    lines.

    b. 220 kV Salakati (PG) Sub-Station of NER is connected to 220 kV Birpara (PG)

    Sub-Station of ER through 220 kV D/C BirparaSalakati lines. 220 kV Salakati

    Sub-Station and 400 kV Bongaigaon Sub-Station are connected through 315

    MVA ICT.

    c. Bongaigaon (PG) Sub-Station is connected to Balipara (PG) Sub-Stationthrough 400 kV D/C BongaigaonBalipara lines.

    d. 400 kV D/C BaliparaMisa lines and 400 kV D/C Balipara Ranganadi lines

    connect Balipara (PG) Sub-Station with Misa (PG) Sub-Station and Ranganadi

    (NEEPCO) Power Station respectively. 400 kV Bus of Misa is connected to 220

    kV Bus through 315 MVA ICT.

    e. Misa (PG) Sub-Station is connected with Kopili (NEEPCO) Power Station,

    Dimapur (PG) Sub-Station and AGBPP (NEEPCO) through 220 kV T/C Misa

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    32/89

    Black start and Restoration Procedures of NER Grid

    Kopili lines, 220 kV D/C Misa Dimapur lines and 400 kV S/C Misa

    Kathalguri line (charged at 220 kV) respectively.

    f. Misa (PG) Sub-Station is also connected to Mariani (Assam) Sub-Station and

    Samaguri (Assam) Sub-Station through 220 kV S/C Misa Mariani line and220 kV D/C MisaSamaguri line.

    g. Misa (PG) Sub-Station is connected with Killing (Byrnihat) Sub-Station of

    Meghalaya through 220 kV D/C MisaKilling lines.

    h. Mariani Sub-Station is connected to AGBPP (NEEPCO) through 400 kV S/C

    MarianiKathalguri line (charged at 220 kV)

    5.2 220 / 132 kV Network of Assam System:

    Assam has its own 220 kV & 132 kV Network through which it is connected to the Main

    Grid. Except South Assam, connectivity of Assam system with the Main Grid is better

    than other states connectivity to the Main Grid. Connectivity of Assam system with the

    Grid is as follows:-

    a. BTPS (Assam) Sub-Station is connected with Salakati (PG) Sub-Station

    through 220 kV D/C BTPS Salakati lines. Again, 220 kV Bus of BTPS is

    connected to 132 Bus through 2 X 80MVA + 1 X 160 MVA.

    b. Dhaligaon, Barnagar, Nalbari, Rangia, Rowta, Sipajhar , Sisugram and Depota

    Sub-Stations are connected with BTPS, Kahilipara, Pavoi, Samaguri and

    Balipara (PG) Sub-Stations through 132 kV lines. 220 kV Bus of Samaguri Sub-

    Station is connected to 132 kV Bus through 3 X 50 MVA ICT. Again, Samaguri

    Sub-station is connected with Balipara (PG) Sub-station through 220 kV

    SamaguriBalipara S/C line.

    c. Agia Sub-Station is connected with BTPS Sub-Station through 220 kV D/C

    BTPS Agia lines. Presently, one circuit of 220 kV BTPS Agia is under

    outage.

    d. Sarusajai Sub-Station is connected with Agia Sub-Station through AgiaBoko-

    Sarusajai line and AgiaSarusajai respectively.

    e. Sarusajai Sub-Station is connected with Samaguri Sub-Station,Jahawar

    Nagar(GIS) Sub-Station and Langpi Power Station through 220 kV Sarusajai

    Jahawar Nagar- Samaguri I and 220 kV Sarusajai Samaguri II lines and

    220 kV D/C SarusajaiLangpi lines respectively.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    33/89

    Black start and Restoration Procedures of NER Grid

    f. Kahilipara Sub-Station is connected with Sarusajai Sub-Station through four

    numbers of 132 kV Sarusajai Kahilipara lines & with Rangia Sub-Station

    through 132 kV Kahilipara Sishugram - Rangia & 132 kV S/C Kahilipara

    Rangia lines.g. LTPS, NTPS, Tinsukia and Dibrugarh Sub-System is connected with Mariani

    Sub-Station and AGBPP through 132 kV S/C LTPS - Mariani and 220 kV D/C

    TinsukiaAGBPP lines respectively.

    h. Mariani, Golaghat and Bokajan Sub-Stations are connected with Dimapur (PG)

    Sub-Station through 132 kV S/C MarianiGolaghat - Bokajan - Dimapur line.

    i. Gohpur, Pavoi (Bishwanath Chariali), North Lakhimpur, Dhemaji and Majuli

    Sub-Stations are connected with Nirjuli (PG) Sub-Station through 132 kV S/C

    Nirjuli Gohpur line. Gohpur, Pavoi (Bishwanath Chariali), North Lakhimpur,

    Dhemaji and Majuli Sub-Stations are also connected with Balipara (PG) Sub-

    Station through 132 kV Balipara Gohpur line and with Samaguri and Depota

    Sub-Stations through 132 kV Samaguri Depota Pavoi line (T-connection

    near Depota in between Depota & Pavoi).

    5.3 220 / 132 kV Network of Arunachal Pradesh System:

    The connectivity of 220 kV & 132 kV Network of Arunachal Pradesh is as follow:-

    a) Ziro(PG), Daporizo and Along Sub-Stations are connected with Ranganadi

    (NEEPCO) Power Station through 132 kV S/C RanganadiZiro line.

    b) Nirjuli (PG) Sub-Station is connected with Ranganadi (NEEPCO) Power Station

    & SMS Sub-Station of Arunachal through 132 kV S/C Ranganadi SMS -

    Nirjuli line (T Connection at SMS) and also with Gohpur Sub-Station of Assam

    through 132 kV S/C NirjuliGohpur line.

    c) Itanagar Sub-Station is connected with 132 kV Nirjuli (PG) Sub-Station through

    four nos. 33 kV feeders. Again, Itanagar can draw power from SMS Sub-station

    via Naharlagun Sub-station through 132 kV SMS Naharlagun-Itanagar line

    (Presently charged at 33 kV).

    d) Khupi, Kimi Sub-Stations are connected with Balipara (PG) Sub-Station

    through 132 kV S/C BaliparaKhupi - Kimi line and Deomali is connected with

    AGBPP (NEEPCO) through 220 kV S/C AGBPPDeomali line respectively.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    34/89

    Black start and Restoration Procedures of NER Grid

    North Eastern Regional Load dispatch Centre, Shillong

    5.4400 / 220 / 132 kV Network comprising of Nagaland, Manipur, SouthAssam, Mizoram, Tripura, Meghalaya,POWERGRID and NETC (North

    East Transmission Company :The connectivity of 132 kV Network comprising of Nagaland, Manipur, South Assam,

    Mizoram, Tripura and Meghalaya is as follow:-

    1. Nagaland System is connected with the Main Grid through:-

    a) 132 kV D/C Dimapur (PG)Dimapur line.

    b) 132 kV S/C Dimapur (PG)Kohima line (presently under outage).

    c) 132 kV S/C Karong (Manipur)Kohima line.

    d) 132 kV S/C Doyang (NEEPCO) - Mokokchung line.

    e) 132 kV S/C Mariani (Assam) Mokokchung line (presently under

    outage)..

    f) 66 kV S/C DimapurBokajan (Assam) line

    ** Nagaland is also co nnected with As sam sy stem throu gh the fol lowing 33

    kV and 11 kV feeders :

    i) GargaonNaginimara

    ii)SonariTigit

    iii)Chanki - Moriani

    2. Manipur System is connected with the Main Grid through :-a) 132 kV D/C Imphal (PG)Imphal lines.

    b) 132 kV S/C Imphal (PG)Ningthoukhong line.

    c) 132 kV S/C Kohima (Nagaland)Karong line.

    d) 132 kV S/C Loktak (NHPC)Ningthoukhong line.

    e) 132 kV S/C Loktak (NHPC)Rengpang line.

    f) 132/33 kV, 1 X 20 MVA Transformer at Jiribam (PG) Sub-Station

    3. Mizoram System is connected with the Main Grid through :-a) 132 kV S/C Aizawl (PG)Zuangtui line.

    b) 132 kV S/C Aizawl (PG)Laungmual line.

    c) 132 kV S/C Badarpur (PG)Kolasib line.

    d) 132 kV S/C Aizawl (PG)Kolasib line.

    4. Tripura System is connected with the Main Grid through :-

    a) 132 kV D/C AGTPP (NEEPCO)Agartala lines

    b) 132 kV S/C Kumarghat (PG)P K Bari line

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    35/89

    Black start and Restoration Procedures of NER Grid

    c) 132 kV S/C Dullavcherra (Assam)Dharmanagar (Missiontila) line

    d) 132 kV S/C PalatanaSurjyamani Nagar line

    e) 132 kV S/C PalatanaUdaipur line

    5. South Assam is connected with the Main Grid through :-a) 132 kV S/C Badarpur(PG)Panchgram line.

    b) 132 kV S/C Lumshnong (Meghalaya)Panchgram line

    c) 132 kV S/C Dharmanagar (Tripura)Dullavcherra line.

    d) 132 kV S/C Jiribam (PG)Pailapool line.

    e) 132 kV S/C Haflong (PG)Haflong line.

    f) 132 kV S/C Silchar Dullavcherra line.

    g) 132 kV S/C SilcharPanchgram line.

    h) 132 kV D/C SilcharSrikona lines.

    i) 33 kV S/C Khandong (NEEPCO)Umrangshu line.

    6. Meghalaya system is connected with the Main Grid through :-

    a) 220 kV D/C MisaKilling (Byrnihat) lines.

    b) 132 kV D/C Khliehriat(PG)Khliehriat lines.

    c) 132 kV S/C Panchgram(Assam)Lumshnong line.

    d) 132 kV Agia (Assam)Nangalbibra line.

    e) 132 kV D/C Kahilipara(Assam) - Umtru lines.

    f) 132 kV D/C Sarusajai (Assam)Umtru lines.

    7. The connectivity of the 132 kV System with 400 kV & 220 kV System

    & major connectivity of intra 132 kV System:-

    a. Dimapur (PG) Sub-Station is connected with Misa (PG) Sub-Station through

    220 kV D/C MisaDimapur lines. 220 kV Bus of Dimapur (PG) Sub-Station

    is connected to 132 kV Bus through 2X100 MVA ICT.

    b. Dimapur (PG) Sub-Station is connected with Imphal (PG) Sub-Station

    through 132 kV S/C DimapurImphal line.

    c. Imphal (PG) Sub-Station is connected with Loktak (NHPC) Power Station

    through 132 kV S/C ImphalLoktak line.

    d. Loktak (NHPC) Power Station is connected with Jiribam (PG) Sub-Station

    through 132 kV S/C LoktakJiribam line.

    e. Jiribam (PG) Sub-Station is connected with Haflong (PG) Sub-Station,

    Badarpur (PG) Sub-Station and Aizawl (PG) Sub-Station through 132 kV

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    36/89

    Black start and Restoration Procedures of NER Grid

    S/C JiribamHaflong line, 132 kV S/C JiribamBadarpur line and 132 kV

    S/C JiribamAizawl line respectively.

    f. Khandong (NEEPCO) Power Station is connected with Kopili (NEEPCO)

    Power Station through 132 kV D/C Kopili Khandong lines. 220 kV Bus ofKopili Power Station is connected to 132 kV Bus through 1X160 MVA ICT.

    g. Khandong (NEEPCO) Power Station is connected with Khliehriat (PG) Sub-

    Station and Haflong (PG) Sub-Station through 132 kV D/C Khandong

    Khliehriat lines and 132 kV S/C KhandongHaflong line respectively.

    h. Badarpur (PG) Sub-Station is connected with Khliehriat (PG) Sub-Station ,

    Kumarghat (PG) Sub-Station, Jiribam (PG) Sub-Station and Aizawal (PG)

    Sub-Station through 132 kV S/C Khliehriat Badarpur line, 132 kV S/C

    KumarghatBadarpur line, 132 kV S/C BadarpurJiribam line and 132 kV

    S/C BadarpurKolasib - Aizawl lines respectively.

    i. Again, Badarpur (PG) Sub-Station is connected with Silchar (PG) Sub-

    Station through 132 kV (D/C) BadarpurSilchar lines.

    j. 132 kV bus of Silchar Sub-Station is connected with 400 kV bus through

    400 / 132 kV, 2 x 200 MVA ICT.

    k. Silchar Sub-Station is connected with Palatana Power station through 400

    kV D/C SilcharPalatana lines. Palatana Power station is also connected

    with Tripura system through 132 kV PalatanaUdaipur & 132 kV Palatana

    Surjyamani Nagar lines respectively.

    l. Again, Silchar Sub-Station is connected with Killing (Byrnihat) sub-stationthrough 400 kV S/C Silchar Byrnihat line. 400 kV bus of Byrnihat Sub-Station is connected to 220 kV bus through 2 x 315 MVA ICT.

    m. Kumarghat (PG) Sub-Station is connected with AGTPP (NEEPCO) and

    Aizawl (PG) Sub-Station through 132 kV S/C KumarghatAGTPP line and

    132 kV S/C KumargahtAizawl line respectively.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    37/89

    Black start and Restoration Procedures of NER Grid

    Black Start & Restoration Procedures6.1 ----- Restoration of NER Grid after total collapse, when power from

    ER is available

    6.2 ----- Restoration of NER Grid after total collapse, when power from

    Eastern Region (ER) is not available

    6.3 ----- Restoration of 400 / 132 kV Network comprising of Manipur,

    South Assam, Mizoram, Tripura, AGTPP and Palatana afterpartial collapse.

    6.4 ----- Restoration of 132 kV Network comprising of Manipur (except

    Jiribam) and Loktak, after partial collapse.

    CHAPTER 6

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    38/89

    Black start and Restoration Procedures of NER Grid

    This Chapter explains broad guidelines for restoring the system after black out. The

    procedure is split up for the following scenarios:-

    1. Restoration of NER Grid after total collapse, when power from Eastern Region

    (ER) is available2. Restoration of NER Grid after total collapse, when power from Eastern Region

    (ER) is not available

    3. Restoration of 400 / 132 kV Network comprising of Manipur, South Assam,

    Mizoram, Tripura, AGTPP and Palatana after partial collapse.

    4. Restoration of 132 kV Network comprising of Manipur (except Jiribam) and Loktak,

    after partial collapse.

    NER Grid under above scenarios will be restored after building up of some sub-systems /

    islands on the basis of available resources. Source of start up power is to be identified

    whether it is available within sub-system / island or outside the sub-system / island for early

    restoration. The following procedure is to be adopted for restoration of affected system:-

    I. Source of startup power

    II. Identifying the critical / essential loads of each sub-system / island

    III. Points of synchronization with other sub-system / island

    IV. Action to be taken by various Generating Stations and Sub-Stations.

    6.1 Restoration of NER Grid after total collapse, when power from ER is

    available

    For restoration of NER Grid from total collapse condition, a multi-pronged restoration

    strategy is envisaged in which some sub-systems and islands are to be built up

    simultaneously by utilizing power from Eastern Region (ER) and black start facilities

    available in various Power Stations in North Eastern Region.

    For restoration of NER Grid from total collapse condition, the following sub-systems /

    islands are to be built up in parallel:-

    6.1.1 The system, consisting of the following sub-systems are to be built up in

    parallel, by utilizing power from ER

    SUB SYSTEM#1:a. Main network comprising of Bongaigaon(PG), Salakati(PG),

    Gelephu(PG),Balipara(PG),Ranganadi(NEEPCO) ,Nirjuli(PG), Misa(PG),

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    39/89

    Black start and Restoration Procedures of NER Grid

    AGBPP(NEEPCO), Dimapur(PG), Doyang(NEEPCO), Byrnihat(MeECL),

    Kopili(NEEPCO),Khandong(NEEPCO),Khliehriat(PG),Haflong(PG),

    Badarpur(PG), Silchar (PG) and Palatana(OTPC).

    b. Arunachal Pradeshcomprising of Khupi, Kimi, Ziro, Itanagar andDeomali,c. Central Assam comprising of Gohpur, Depota, Pavoi, Depota, Rowta,

    Dhemaji, North Lakhimpur, Majuli, Samaguri, Mariani

    d. South Assam comprising of Panchgram, Dullavcherra Srikona and

    Pailapool

    e. Nagaland System comprising ofDimapur , Kohima and Mokukchung

    SUB SYSTEM#2:Lower Assam comprising of BTPS, Agia, Dhaligaon, Barnagar, Nalbari,

    Rangia, Sipajhar, Sarusajai, Kahilipara and Langpi

    6.1.2 ISLAND B: Upper Assam comprising of NTPS, LTPS with Dibrugarh,

    Nazira and Tinsukia

    6.1.3 ISLAND C: comprising of Meghalaya System

    6.1.4 ISLAND D:comprising of AGTPP(NEEPCO), Tripura and Mizoram

    6.1.5 ISLAND E: comprising of Loktak (NHPC) and Manipur

    6.1.1 Restoration of systems to be built up by utilizing power from ER

    Sub-system #1 and sub-system #2 shall be restored in parallel after taking power from

    Eastern Region. Simultaneously, all the generating Stations which have black-start

    facilities are to be advised to bring their units as fast as possible, so that, islands can be

    formed for early restoration of the system

    6.1.1.1 Restoration of sub-system #1

    Restoration of sub-system #1 consists of Main NER network, Arunachal,Central Assam,

    South Assam and Nagaland. Restoration procedure of this sub-system is as follow:-

    1) Power required for this sub system shall be taken from New Siliguri (ER) Sub-

    Station to Bongaigaon (NER) Sub-Station through any one of 400 kV D/C New

    SiliguriBongaigaon lines.

    2) In case of delay in receiving power from New Siliguri (ER) Sub-Station, then the

    following procedure shall be adopted :-

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    40/89

    Black start and Restoration Procedures of NER Grid

    Salakati (NER) Sub-Station shall receive power from Birpara (ER) Sub-Station

    through any one of 220 kV D/C Birpara Salakati lines. Any one of 400 kV

    Bus(s) at Bongaigaon Sub-Station shall be charged through 315 MVA ICT at

    Bongaigaon Sub-Station. Again, Salakati Sub-Station shall charge any one of220 / 132 kV , 50 MVA ICT & shall extend power to Gelephu through 132 kV

    S/C Saklakati Gelephu line.Load at Gelephu can be connected in co-

    ordination with NLDC & Bhutan. Bus Reactors (at Annex III) at New Siliguri Sub-

    Station and Bongaigaon Sub-Station shall be taken into service to contain

    voltage. Bongaigaon (PG) Sub-Station shall extend power to Balipara (PG) Sub-

    Station through any one of 400 kV D/C Balipara Bongaigaon lines. Any one of

    220 kV Bus(s) at Salakati Sub-Station shall be charged through 315 MVA ICT at

    Bongaigaon Sub-Station. If required, Tertiary Reactor at Bongaigaon (at Annex

    III) may be taken into service to contain voltage.

    Restoration of Arunachal Pradesh

    3) Balipara (PG) Sub-Station shall extend power to Misa (PG) Sub-Station through

    any one of 400 kV D/C BaliparaMisa lines and Shunt Reactors (at Annex III) at

    Balipara and Misa Sub-Stations shall be taken into service to contain voltage.

    Any one of 220 kV Bus(s) at Balipara Sub-Station shall be charged through any

    one of 2 x 315 MVA ICT at Balipara Sub-Station. If required, Tertiary Reactor at

    Balipara (at Annex III) may be taken into service to contain voltage. 132 kV Bus

    at Balipara Sub-Station shall be charged through 2X50 MVA ICT at Balipara

    Sub-Station. Balipara Sub-Station shall extend power to Khupi & Kimi Sub-

    Stations of Arunachal through 132 kV Balipara Khupi - Kimi lines. Load at

    Khupi & Kimi shall be connected in co-ordination with SLDC, Arunachal Pradesh.

    4) Ranganadi (NEEPCO) Power Station can receive power from Balipara (PG)

    Sub-Station through any one of 400 kV D/C BaliparaRanganadi lines. Any one

    of 132 kV Bus(s) at Ranganadi Power Station shall be charged through any one

    of 2X360 MVA ICT at Ranganadi Power Station. Ranganadi (NEEPCO) Power

    Station shall extend power to SMS (Arunachal Pradesh) and Nirjuli (PG) Sub-

    Stations through 132 kV S/C RanganadiSMS - Nirjuli (T Connection at SMS)

    and shall extend power to Daporijo and Along (Arunachal Pradesh) Sub-Stations

    through 132 kV S/C Ranganadi Ziro - DaporijoAlong lines. Shunt Reactors

    (at Annex III) at Ranganadi Power Station shall be taken into service to contain

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    41/89

    Black start and Restoration Procedures of NER Grid

    voltage. Load shall be connected at SMS, Ziro, Daporijo and Along in co-

    ordination with SLDC, Arunachal Pradesh.

    5) 33 kV Bus at Nirjuli Sub-Station shall be charged through any one of 1X10+1X16

    MVA ICT at Nirjuli Sub-Station. Nirjuli Sub-Station shall extend power to Itanagar(Arunachal Pradesh) Sub-Station through any one of four nos of 33 kV feeders.

    Itanagar Sub-Station can also receive power from SMS Sub-Station through

    Naharlagun (Arunachal Pradesh) Sub-Station. Load shall be connected at

    Itanagar in co-ordination with SLDC, Arunachal Pradesh.

    Restoration of Cental Assam6) Balipara (PG) Sub-Station shall also extend power to Gohpur (Assam) Sub-

    Station through 132 kV S/C BaliparaGohpur line. Gohpur Sub-Station can also

    receive power from Samaguri and Depota Sub-Stations through 132 kV

    Samaguri Pavoi (Bishwanath Chariali) - Gohpur line and 132 kV Depota

    Pavoi (Bishwanath Chariali) Gohpur line respectively. Load shall be connected

    at Gohpur in co-ordination with SLDC, Assam. Balipara (PG) Sub-Station shall

    extend power to Depota(Assam) Sub-Station through 132 kV Balipara Depota

    line. Load at Depota shall be connected in co-ordination with SLDC, Assam.

    Depota Sub-Station shall extend power to Rowta Sub-Station through 132 kV

    Depota Rowta line. Load at Rowta shall be connected in co-ordination with

    SLDC, Assam.

    7) Gohpur (Assam) Sub-Station shall extend power to North Lakhimpur, Dhemaji

    and Majuli Sub-Stations. Loads at North Lakhimpur, Dhemaji and Majuli shall be

    connected in co-ordination with SLDC, Assam.

    8) Ranganadi (NEEPCO) Power Station shall bring their machines if required and

    synchronize with this sub-system. Otherwise, if the power received from Balipara

    Sub-Station is delayed, Ranganadi Power Station shall black start one of their

    three units and shall charge 132 kV Bus and extend power to SMS, Nirjuli & Ziro

    Sub-Stations and wait for extension of power from Balipara Sub-Stations. If

    possible they can also charge one circuit of 400 kV D/C Ranganadi Balipara

    line for synchronization.

    9) Gohpur Sub-Station can also receive power from Nirjuli (PG) Sub-Station

    through 132 kV NirjuliGohpur line.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    42/89

    Black start and Restoration Procedures of NER Grid

    Note : SLDC, Ass am and Arunach al Pradesh sh al l co-ordinate with NERLDC

    before connect ing loads to their systems.

    10) Any one of 220 kV Bus(s) at Misa Sub-Station shall also be charged through anyone of 2 x 315 MVA ICT at Misa Sub-Station after receiving power from Balipara

    (PG) Sub-Station. If required, Tertiary Reactor at Misa (at Annex III) may be

    taken into service to contain voltage.

    11) Misa Sub-Station shall extend power to Samaguri (Assam) Sub-Station through

    any one of 220 kV D/C MisaSamaguri lines. Shunt Reactors (at Annex III) at

    Samaguri Sub-Station shall be taken into service to contain voltage. 132 kV Bus

    at Samaguri Sub-Station may be charged through any one of 3X50 MVA ICT.

    Load at Samagurishall be connected in co-ordination with SLDC, Assam.

    12) Misa Sub-Station shall extend power to Byrnihat (Meghalaya) Sub-Station

    through any one of 220 kV D/C Misa Killing (Byrnihat) lines. 132 kV Bus at

    Byrnihat Sub-Station shall be charged through any one of 2X160 MVA ICT.

    Byrnihat Sub-Station shall extend power to EPIP II Sub-Station through any one

    of 132 kV D/C ByrnihatEPIP II lines. Load at EPIP II may be catered to in co-

    ordination with SLDC, Meghalaya. EPIP II Sub-Station shall extend power to

    EPIP I Sub-Station through any one of 132 kV D/C EPIP II EPIP I lines. Load

    at EPIP I may be catere to in co-ordination with SLDC, Meghalaya and power

    shall be extended progressively to Meghalaya power stations for synchronization

    of machines. The related segregated operations will be carried out in close

    coordination with NERLDC.

    13) Byrnihat (Killing) shall extend power to Silchar sub-station through 400 kV S/C

    SilcharByrnihat line, if voltage permits.

    14) Mariani (Assam) Sub-Station can receive power either from Misa Sub-Station

    through 400 kV S/C Misa Mariani line (Charged at 220 kV) or Samaguri

    (Assam) Sub-Station through 220 kV S/C SamaguriMariani line (presently one

    circuit is available). Shunt Reactors (at Annex III) at Mariani Sub-Station shall be

    taken into service to contain voltage. Load at Mariani shall be connected in co-

    ordination with SLDC, Assam.

    15) Kopili (NEEPCO) Power Station shall receive power from Misa Sub-Station

    through any one of 220 kV T/C Misa Kopili lines. Kopili Power Station shall

    bring their machines by taking start up power from this sub-system and

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    43/89

    Black start and Restoration Procedures of NER Grid

    synchronize the machines with this sub-system. Otherwise, if the power received

    from Misa Sub-Station is delayed, Kopili Power Station shall black start one of

    four units and shall charge 220 kV Bus and extend power to Khandong Power

    Station and wait for extension of power from Misa Sub-Stations.16) 132 kV Bus at Kopili Power Station shall be charged through 160 MVA ICT at

    Kopili Power Station.

    17) Kopili Power Station shall extend power to Khandong (NEEPCO) Power Station

    through any one of 132 kV D/C Kopili Khandong lines. Khandong Power

    Station shall bring machines, if required, by taking startup power from this sub-

    system and synchronize the machines with this sub-system. Otherwise, if the

    power received from Kopili Power Station is delayed, Khandong Power Station

    shall black start one of three units and shall charge 132 kV Bus and extend

    power to Haflong & Khliehriat Sub-Stations and wait for extension of power from

    Kopili Power Station. If possible, they can also charge one circuit of 132 kV D/C

    KopiliKhandong lines for synchronization.

    Restoration of South Assam

    18) Khandong Power Station shall charge 33 kV Bus through any one of

    1X16+1X7.5 MVA Transformer. Khandong shall extend power to Umrangshoo

    Sub-Station through 33 kV S/C of Khandong Umrangshoo line. Load at

    Umrangsho shall be connected in co-ordination with SLDC, Assam.

    19) Khandong Power Station shall extend power to Khliehriat (PG) and Haflong (PG)

    Sub-Stations through any one of 132 kV D/C of KhandongKhliehriat lines and

    132 kV S/C KhandongHaflong line respectively.

    20) Khliehriat (PG) Power Station shall extend power to Badarpur (PG) Sub-Station

    through 132 kV S/C Khliehriat- Badarpur line.

    21) Badarpur Sub-Station shall extend power to Panchgram (Assam) Sub-Station

    through 132 kV S/C Badarpur Panchgram line. Panchgram Sub-station shall

    also receive power from Silchar through 132 kV Silchar Panchgram line.

    Panchgram Sub-Station shall extend power to Srikona Sub-Station through 132

    kV Panchgram Srikona line. Srikona shall extend power to Pailapool through

    132 kV S/C SrikonaPailapool line. Load at Panchgram, Srikona and Pailapool

    shall be connected in co-ordination with SLDC, Assam.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    44/89

    Black start and Restoration Procedures of NER Grid

    22) This sub-system shall be synchronized with Island D at Badarpur (PG) through

    132 kV S/C BadapurKumarghat line.

    23) Again, Badarpur shall extend power to Silchar through any one of132 kV D/C

    BadarpurSilchar lines. Silchar shall extend power to Srikona through any oneof 132 kV D/C Silchar - Srikona lines.

    24) Silchar shall charge any one of 400 kV bus through any one of 400 / 132 kV 2

    x200 MVA ICT. All the shunt reactors at Silchar sub-station (at Annex III) shall be

    put into service to contain voltage.

    25) Silchar shall extend power to Palatana Power station through any one of 400 kV

    D/C SilcharPalatana Lines, if voltage permits. Before this, Palatana shall take

    start up power through any one of 132 kV Udaipur Palatana and 132 kV

    Surjyamani Nagar - Palatana of Tripura system (Island D) and shall synchronise

    its unit.

    26) This sub-system shall be synchronized with Island E at Badarpur (PG) through

    132 kV S/C BadapurJiribam line.

    27) This sub-system shall be synchronized with Island C at Khliehriat (PG) through

    132 kV D/C KhliehriatKhliehriat lines.

    28) Badarpur Sub-Station shall extend power to Kolasib (Mizoram) Sub-Station

    through 132 kV S/C BadarpurKolasib line. Load at Kolasib shall be connected

    in co-ordination with SLDC, Mizoram.

    29) Kolasib Sub-Station shall extend power to Bairabi (Mizoram) Power Station for

    survival/auxiliary power through 66 kV KolasibBairabi line.

    30) Haflong (PG) Sub-Station shall extend power to Haflong (Assam) Sub-Station

    through 132 kV S/C HaflongHaflong line. Load at Haflong shall be connected

    in co-ordination with SLDC, Assam.

    31) Mariani Sub-Station shall extend power to AGBPP (NEEPCO) through 400 kV

    S/C Mariani AGBPP line (charged at 220 kV). AGBPP shall bring their

    machines by taking start up power from this sub-system and synchronize the

    machines with this sub-system. AGBPP shall extend power to Deomali

    (Arunachal Pradesh) Sub-station through 220 kV S/C AGBPP Deomali line.

    Load at Deomali shall be connected in co-ordination with SLDC, Arunachal

    Pradesh.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    45/89

    Black start and Restoration Procedures of NER Grid

    32) Misa (PG) Sub-Station shall extend power to Dimapur (PG) Sub-station through

    any one of 220 kV D/C Misa Dimapur lines. 132 kV Bus at Dimapur Sub-

    Station shall be charged through any one of 2X100 MVA ICT at Dimapur.

    Restoration of Nagaland system33) Dimapur (PG) Sub-Station shall extend power to Dimapur (Nagaland) Sub-

    Station through any one of 132 kV D/C DimapurDimapur line. Load at Dimapur

    shall be connected in co-ordination with SLDC, Nagaland.

    34) Dimapur (PG) Sub-station shall extend power to Kohima Sub-Station through

    132 kV S/C Dimapur Kohima line. Load at Kohima shall be connected in co-

    ordination with SLDC, Nagaland.

    35) Kohima Sub-station shall extend power to Meluri Sub-Station through 132 kVS/C KohimaMeluri line. Load at Meluri shall be connected in co-ordination with

    SLDC, Nagaland.

    36) Meluri Sub-Station shall extend power to Khiphire Sub-Station through 132 kV

    S/C Meluri Khiphire line. Load at Khiphire shall be connected in co-ordination

    with SLDC, Nagaland.

    37) 66 kV Bus at Khiphire Sub-Station shall be charged through any one of 3X6.5

    MVA ICT at Khiphire Sub-Station.

    38) Khiphire Sub-Station shall extend power to Likhimro Power Station through 66

    kV KhiphireLikhimro line.

    39) Dimapur (PG) Sub-Station shall also extend power to Doyang (NEEPCO) Power

    Station through any one of 132 kV D/C Dimapur Doyang lines. Doyang Power

    Station shall bring generation, if required and synchronize.Otherwise, if the

    power received from Dimapur Sub-Station is delayed, Doyang Power Station

    shall black start one of three units & shall charge 132 kV bus and extend power

    to Mokakchung Sub-Station.

    40) Doyang (NEEPCO) Power Station shall extend power to Mokokchung Sub-

    Station through 132 kV S/C Doyang Mokukchung line. Load at Mokokchung

    shall be connected in co-ordination with SLDC, Nagaland.

    41) This sub-system may also be synchronized with Island E at Dimapur (PG)

    through 132 kV S/C DimapurImphal line.

    42) Dimapur (PG) Sub-Station can also receive power form Mariani Sub-Station

    through 132 kV S/C MarianiGolaghatBokajan - Dimapur line.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    46/89

    Black start and Restoration Procedures of NER Grid

    43) Mokokchung Sub-Station can also receive power from Mariani Sub-Station

    through 132 kV S/C MarianiMokokchung line. Presently 132 kV S/C Mariani

    Mokokchung line is under long outage. Early restoration of this line will help to

    extend power to Mokokchung.

    Note: SLDC, Ass am and Nagaland sh al l co-ordinate with NERLDC before

    conn ect ing loads to their system

    If ER power received by Misa Sub-Station is delayed then power shall be

    taken from the following sources:-

    i. From Island C, Khliehriat (PG) Sub-Station can receive power from

    Khliehriat (Meghalaya) Sub-Station through any one of 132 kV D/C

    KhliehriatKhliehriat lines.

    ii. From Island C, Panchgram (Assam) Sub-Station can receive power from

    Khliehriat (Meghalaya) Sub-Station through 132 kV S/C Khliehriat

    Lumnsnong - Panchgram line.

    iii. From Island D, Badarpur (PG) Sub-Station can receive power from

    Kumarghat Sub-Station through 132 kV S/C BadarpurKumarghat line.

    iv. From Island D, Kolasib Sub-Station can receive power from Aizawl Sub-

    Station through 132 kV S/C KolasibAizawl line

    v. From Island D, Panchgram (Assam) Sub-Station can receive power from

    Dharmanagar Sub-Station through 132 kV S/C Dharmanagar -

    Dullavcherra - Panchgram line.

    vi. From Island E, Haflong (PG) Sub-Station can receive power from Jiribam

    Sub-Station through 132 kV S/C HaflongJiribam line.

    vii. From Island E, Dimapur (PG) Sub-Station can receive power from

    Imphal(PG) Sub-Station through 132 kV S/C Imphal - Dimapur line.

    6.1.1.2 Restoration of sub-system #2

    Restoration of sub-system #2 consists of Lower Assam. Restoration procedure for this

    sub-system is as follow:-

    1) From sub-system #1, Salakati (PG) Sub-Station shall extend power to BTPS

    (Assam) Sub-Station through any one of 220 kV D/C SalakatiBTPS lines.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    47/89

    Black start and Restoration Procedures of NER Grid

    2) BTPS Sub-Station shall extend power to Agia (Assam) Sub-Station through 220

    kV BTPS Agia line. Presently one circuit of 220 kV BTPS Agia is available.

    Load at Agia shall be connected in co-ordination with SLDC, Assam.

    3) 132 kV Bus at BTPS Sub-Station shall be charged through any one of2X80+1X160 MVA ICT at BTPS Sub-Station. BTPS Sub-Station shall extend

    power to Dhaligaon (Assam) Sub-Station through any one of 132 kV D/C BTPS

    Dhaligaon lines. Load at Dhaligaon shall be connected in co-ordination with

    SLDC, Assam.

    4) Dhaligaon Sub-Station shall extend power to Rangia (Assam) Sub-Station and

    Barnagar (Assam) Sub-Station through 132 kV Dhaligaon Barnagar and 132

    kV Dhaligaon Nalbari - Rangia lines. Load at Nalbari, Rangia and Barnagar

    shall be connected in co-ordination with SLDC, Assam. 132 kV S/C Rangia

    Barnagar line shall be closed.

    5) Again, Rangia shall extend power to Motonga (Bhutan) through 132 kV Rangia

    Motonga line. Gelephu can also receive power through Motonga.

    6) Rangia Sub-Station shall extend power Sisugram (Assam) Sub-Station through

    132 kV S/C RangiaSishugram line. Load at Sishugram shall be connected. If

    required, Rangia Sub-Station shall extend power to Rowta Sub-Station too

    through 132 kV RangiaSipajhar - Rowta & 132 kV RangiaRowta line. Load

    at Sipajhar & Rowta may be connected in co-ordination with SLDC, Assam.

    7) Agia (Assam) Sub-Station shall extend power to Sarusajai (Assam) Sub-Station

    through 220 kV S/C Agia Sarusajai or 220 kV Agia Boko Sarusajai lines.

    132 kV Bus at Sarusajai Sub-Station shall be charged through any one of 3X100

    MVA ICT at Sarusajai. Load at Sarusajai & Boko shall be connected in co-

    ordination with SLDC, Assam.

    8) Sarusajai Sub-Station shall extend power to Kahilipara (Assam) Sub-Station

    through any one line of four nos. of 132 kV SarusajaiKahilipara lines. Load at

    Kahilipara shall be connected in co-ordination with SLDC, Assam.

    9) Sarusajai Sub-Station shall extend power to Langpi (Assam) Power Station

    through any one of 220 kV D/C Sarusajai Langpi lines. Sarusajai shall also

    extend power to Jahawar Nagar(GIS) Sub-station through 220 kV Sarusajai -

    Jahawar Nagar(GIS) line.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    48/89

    Black start and Restoration Procedures of NER Grid

    10) Kahilipara Sub-Station can also receive power from Rangia and Sisugram Sub-

    Stations through 132 kV S/C RangiaKahilipara line and 132 kV S/C Sisugram

    Kahilipara line respectively.

    11) Sarusajai Sub-Station can also receive power from Samaguri Sub-Station of sub-system #1 through 220 kV D/C SarusajaiSamaguri -II

    Remark: SLDC, As sam shall co-ord inate wi th NERLDC/Meghalaya SLDC

    before connect ing loads.

    Note : If ER power intended to be received by this system is delayed then power

    shall be taken/extended from the following sources :-

    i. From Island C, Sarusajai Sub-Station can receive power from Umtru

    (Meghalaya) Power Station through any one of 132 kV D/C Umtru -

    Sarusajai lines.

    ii. From Island C, Kahilipara Sub-Station can receive power from Umtru

    (Meghalaya) Power Station through any one 132 kV D/C Umtru -

    Kahilipara lines.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    49/89

    Black start and Restoration Procedures of NER Grid

    6.1.2 Restoration of Island B

    Restoration Island B consists of Upper Assam. Restoration of this Island could be done

    by its own black-start facility as in follow:

    1) NTPS (Assam) shall black-start and charge 66 kV Bus at NTPS. Load at NTPS

    shall be connected in co-ordination with SLDC Assam. NTPS shall bring and

    synchronize other units.

    2) NTPS shall extend power to LTPS (Assam) through any one of 132 kV D/C

    LTPSNTPS lines. LTPS shall bring generation and synchronize.

    3) NTPS shall extend power to Tinsukia & Nazira (Assam) Sub-Stations through

    any one of 66 kV D/C NTPS Tinsukia and any one of 66 kV D/C NTPS

    Nazira lines respectively. Load at Tinsukia and Nazira shall be connected in co-

    ordination with SLDC Assam.

    4) 132 kV Bus at NTPS shall be charged through any one of 2X25 MVA ICT at

    NTPS.

    5) NTPS shall also extend power to Tinsukia (Assam) Sub-Station through 132 kV

    S/C NTPS -Tinsukia line.

    6) LTPS shall extend power to Dibrugarh (Assam) Sub-Stations through 132 kV

    S/C LTPS Dibrugrah and 132 kV S/C LTPS - Nazira line. Load at Dibrugarh

    shall be connected in co-ordination with SLDC Assam. 132 kV LTPS Nazira

    line shall be closed.

    7) This island shall be synchronized with sub-system #1 at Mariani (Assam) through

    132 kV S/C LTPSMariani line.

    Note: If Black start by NTPS is not possible, then start up power for this Island

    shall be received from the following sources:-

    i. From sub system #1, Tinsukia Sub-Station can receive power from

    AGBPP through any one of 220 kV D/C Tinsukia AGBPP line andshall extend start up power to NTPS through 132 kV S/C Tinsukia

    NTPS line.

    ii. From sub system #1, LTPS can receive power from Mariani Sub-Station

    through 132 kV S/C MarianiLTPS line.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    50/89

    Black start and Restoration Procedures of NER Grid

    6.1.3 Restoration of Island C

    Restoration of Island C consists of Meghalaya System. Meghalaya system can be built

    up by its own black-start facilities. Restoration procedure for this Island is as follow:-

    1) Umiam St I Power Station shall black-start and charge 132 kV Bus at Umiam St IPower Station. Umiam St III Power Station shall also black start and charge132

    kV Bus at Umiam St III Power Station.

    2) Umiam St I Power Station shall synchronize with Umiam St III Power Station at

    Umium St III Power Station through any one of 132 kV D/C Umiam St I Umiam

    St III lines. Umiam St I & III Power Stations shall bring and synchronize other

    machines. Load at Umiam St III shall be connected in co-ordination with SLDC

    Meghalaya.3) Umiam St I Power Station shall extend power to Umiam St II Power Station

    through 132 kV S/C Umiam St I Umiam II line for survival/auxiliary power.

    Umiam St II Power Station shall bring generation if required and synchronize.

    4) Umiam St III Power Station shall extend power to Umiam St IV Power Station

    through any one of 132 kV D/C Umiam St III Umiam IV line for

    survival/auxiliary power. Umiam St IV Power Station shall bring generation if

    required and synchronize.

    5) Umiam St III Power Station shall extend power to Umtru Power Station through

    any one of 132 kV D/C Umiam St III Umtru lines. Load at Umtru shall be

    connected in co-ordination with SLDC Meghalaya. Umtru Power Station shall

    bring generation if required and synchronize.

    6) Umiam St I Power Station shall extend power to Mawlai and NEHU Sub-Stations

    through 132 kV S/C Umiam St I Mawlai line and 132 kV S/C Umiam St I

    Umiam - NEHU line respectively. Load at Mawlai, Umiam and NEHU shall be

    connected in co-ordination with SLDC Meghalaya.

    7) NEHU Sub-Station shall extend power to Khliehriat Sub-Station through 132 kV

    S/C NEHU NEIGRIHMS - Khliehriat line or 132 kV NEHU Khliehriat line.

    Load at Khliehriat and NEIGRIHMS shall be connected in co-ordination with

    SLDC Meghalaya.

    8) Khliehriat Sub-Station shall extend power to Lumsnong Sub-Station through 132

    kV S/C Khliehriat- Lumsnong line.Load at Lumsnong shall be connected in co-

    ordination with SLDC Meghalaya.

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    51/89

    Black start and Restoration Procedures of NER Grid

    9) Again, Power shall be extended to Leshka power station from Khliehriat

    (Meghalaya) Sub-Station through 132 kV D/C KhliehriatLeshka lines.

    10) This island shall be synchronized with sub-system #2 at Sarusajai (Assam) Sub-

    Station and Kahilipara (Assam) Sub-Station through any one of 132 kV D/CUmtru Sarusajai lines or through any one of 132 kV D/C Umtru Kahilipara

    lines.

    11) This island shall be synchronized with sub-system #1 at Khliehriat (PG) Sub-

    Station through any one of 132 kV D/C KhliehriatKhliehriat lines from Badarpur

    (PG) via restored Island D.

    Note: If Black Start by Meghalaya Power Stations is not possible then start up power

    for this Island shall be received from the following sources:

    i. From sub-system#1, Khliehriat (Meghalaya) Sub-Station can receive

    power from Khliehriat (PG) Sub-Station through any one of 132 kV D/C

    KhliehriatKhliehriat lines and extend power to Umiam St I and Leshka

    Power Station through NEHU & Umiam Sub-Stations and 132 kV D/C

    KhliehriatLeshka lines respectively, for brining generation.

    ii. From Sub System #1, Khliehriat (Meghalaya) Sub-Station can receive

    power from Panchgram (Assam) Sub-Station through 132 kV

    Panchgram - LumsnongKhliehriat line.

    iii. From Sub System #2, Umtru (Meghalaya) Sub-System can receive

    power from Sarusajai (Assam) Sub-Station through any one of 132 kV

    D/C Sarusajai Umtru lines and extend power to Umiam St III Power

    Station through any one of 132 kV D/C Umiam St III - Umtru for brining

    generation.

    iv. From Sub System #2, Umtru (Meghalaya) Sub-Station can receive

    power from Kahilipara (Assam) Sub-Station through any one of 132 kV

    D/C Kahilipara Umtru lines and extend power to Umiam St III Power

    Station through any one of 132 kV D/C Umiam St III - Umtru for brining

    generation.

    v. From Sub System #1, Umtru (Meghalaya) Sub-Station can receive

    power from Killing (Meghalaya) Sub-Station through 132 kVD/CKilling

    EPIPIIUmtru

  • 7/23/2019 Restoration Procedure of NER Grid Nov-2013

    52/89

    Black start and Restoration Procedures of NER Grid

    North Eastern Regional Load dispatch Centre, Shillong

    6.1.4 Restoration of Island D :

    Restoration of Island D consists of AGTPP, Tripura and Mizoram. AGTPP and Tripura

    System can restore its system by their own black start facilities. Restoration procedure

    for this Island is as follow:-

    Restoration of Tripura system

    1) Rokhia (Tripura) Power Station shall black start and charge 66 kV Bus at

    Rokhia Power Station. Load at Rokhia shall be connected in co-ordination with

    SLDC, Tripura. Rokhia Power Station shall bring and synchronize other

    machines.

    2) 132 kV Bus at Rokhia Power Station shall be charged through 30 MVA ICT at

    Rokhia Power Station.

    3) Rokhia Power Station shall extend power to Agartala Sub-Station through any

    one of 132 kV D/C RokhiaAgartala lines. Load at Agartala shall be connected

    in co-ordination with SLDC, Tripura.

    4) AGTPP (NEEPCO) shall black start one of its unit and charge 132 kV Bus at

    AGTPP. AGTPP shall synchronize Tripura System through any one of 132 kV

    D/C AGTPP Agartala lines. AGTPP shall bring and synchronize other

    machines.5) Agartala Sub-Station shall extend power to Baramura Power Station through

    132 kV S/C Agartala Budhjangnagar Jirania - Baramura lines. Baramura

    Power Station shall bring generation and synchronize with this Island.

    6) Budhjangnagar shall extend power to S Nagar through 132 kV Budhjangnagar -

    S Nagar line.Then S Nagar sh