Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Republic of the PhilippinesPROVINCE OF BENGUET
La Trinidad
BIDS AND AWARDS COMMITTEE(Infrastructure)
______________________________________________________________
MINUTES OF MEETING OF THE BIDS AND AWARDS COMMITTEE – INFRASTRUCTURE HELD ON APRIL 24, 2012 AT PEO CONFERENCE HALL, WANGAL, LA TRINIDAD, BENGUET
PRESENT:Engr. Aning M. Binayan, Provincial Engineer ChairpersonMs. Nora S. Asiong, Provincial Budget Officer Vice ChairpersonMs. Imelda I. Macanes, Provincial Treasurer MemberEngr. Reny S. Tabdi, Assistant Prov’l. Engineer MemberEngr. Orlando T. Oidi, Assistant Prov’l. Assessor Member
RESOLUTION NO. 2012- 04 - 031
A RESOLUTION RECOMMENDING THE AWARD OF PROJECTS TO THE LONE/LOWEST CALCULATED AND RESPONSIVE BIDDERS.
WHEREAS, the Provincial Government of Benguet advertised the Invitation to Bid for the projects and posted in the Philippine Government Electronic Procurement System (PhilGEPS), Benguet website(www.benguet.gov.ph), designated areas at the Provincial Capitol Lobby, and at the Office of the Provincial Engineer from April 12, 2012 – April 20, 2012.
WHEREAS, in accordance to Section 53.9 of RA 9184 as amended, the BAC- Infrastructure is allowed to procure Projects through Small Value Procurement under the other modes of procurement.
WHEREAS, the Bids and Awards Committee (BAC) has invited qualified contractors to negotiate with the BAC- Infrastructure for the procurement of said projects in consonance with Section 53.9 of RA 9184 as amended.
WHEREAS, in response to the invitation, contractors participated in the bidding conducted on April 24, 2012.
Page 1 of 7
WHEREAS, after the opening of bids, an evaluation was conducted by the Technical Working Group (TWG) and after deliberation by the BAC of the results, 8 projects were recommended for award to the lone calculated responsive bidders and 4 projects were recommended for award to the lowest calculated responsive bidder as follows.
PROJECT NO. 4Name of Project IMPROVEMENT ALONG TULUDAN- SAYANGAN
PROVINCIAL ROADProject Location CATTUBO, ATOK, BENGUETTotal Project Cost P 500,000.00ABC P 500,000.00 Source of Fund CY 2012 20% PDF Min Licensed Required Small ARequired Bid Security P 25,000.00
BIDDER: Actual surety bond Bid Amount:JCA GEN. CONST. &
ENGG. SERVICES P 25,000.00 P 498,801.00
PROJECT NO. 5Name of Project CLUSTER “A”: a) CONSTRUCTION OF POSEL-
SACLALAN WAITING SHED; b) INSTALLATION OF NAPITEW- OBANGA WATERWORKS SYSTEM
Project Location a) AMGALEYGUEY, BUGUIAS; b) BAC. SUR, BUGUIAS, BENGUET
Total Project Cost a) P 200,000.00 + b) P 75,000.00= P 275,000.00
ABC a) P 200,000.00 + b) P 75,000.00= P 275,000.00
Source of Fund a) SUPP. BUDGET #6-2011 CCO; b) CY 2012 20% PDF
Min Licensed Required Small ARequired Bid Security P 13,750.00
BIDDER: Actual surety bond Bid Amount:NORTHBASE
CONSTRUCTION P 13,750.00 a) P 198,760.67
b) P 74,553.56TOT. = P 273,314.23
PROJECT NO. 6Name of Project CONSTRUCTION OF RETAINING WALL ALONG
LOO- TABA-AO BARANGAY ROADProject Location LOO, BUGUIAS, BENGUETTotal Project Cost P 500,000.00 ABC P 500,000.00 Source of Fund CY 2011 20% PDF -CCOMin Licensed Required Small A
BIDS AND AWARDS COMMITTEE ON INFRASTRUCTURERESOLUTION OF AWARD NO. 2012-04-031
Page 2 of 7
Required Bid Security P 25,000.00BIDDER: Actual surety bond Bid Amount:
TOCLO CONSTRUCTION P 25,000.00 P 491,202.30HGW=3 ENGG. & CONSTRUCTION
P 25,000.00 P 498,969.45
PROJECT NO. 7Name of Project CONSTRUCTION OF STAGE AT JOSE OPILES
ELEM. SCHOOL, PETICANProject Location TINONGDAN, ITOGON, BENGUETTotal Project Cost P 150,000.00 ABC P 150,000.00 Source of Fund CY 2011 20% PDF Min Licensed Required Small ARequired Bid Security P 7,500.00
BIDDER: Actual surety bond Bid Amount:JESSIE CONSTRUCTION
SERVICES P 7,500.00 P 149,489.73
PROJECT NO. 8Name of Project CLUSTER “B”: a) RECONST. OF TENMONGAO
FOOTBRIDGE AT DAGAO, CAYAPES; b) REHAB. OF PUKGONG GASWILING WATERWORKS SYSTEM
Project Location a) CAYAPES, KAPANGAN; b) GASWILING, KAPANGAN, BENGUET
Total Project Cost a) P 200,000.00 + b) P 221,643.00= P 421,643.00
ABC a) P 200,000.00 + b) P 221,643.00= P 421,643.00
Source of Fund a & b) CALAMITY FUND 2010 Min Licensed Required Small ARequired Bid Security P 21,082.15
BIDDER: Actual surety bond Bid Amount:POLO ENGG. &
CONSTRUCTION P 21,085.00 a) P 199,777.51
b) P 220,887.60TOT. = P 420,665.11
PROJECT NO. 9Name of Project CONSTRUCTION OF PUDONG ELEM. SCHOOL
COMFORT ROOMProject Location PUDONG, KAPANGAN, BENGUETTotal Project Cost P 450,000.00 ABC P 450,000.00 Source of Fund SEF- 2011 CCO- ELEM. EDUC. Min Licensed Required Small ARequired Bid Security P 22,500.00
BIDDER: Actual surety bond Bid Amount:BALANGCOD
CONSTRUCTION P 22,500.00 P 448,856.81
BIDS AND AWARDS COMMITTEE ON INFRASTRUCTURERESOLUTION OF AWARD NO. 2012-04-031
Page 3 of 7
PROJECT NO. 10Name of Project CONSTRUCTION OF MULTI- PURPOSE
WAITING SHED AT KAMYOGAN, BADEOProject Location BADEO, KIBUNGAN, BENGUETTotal Project Cost P 500,000.00 ABC P 500,000.00 Source of Fund CY 2011 20% PDFMin Licensed Required Small ARequired Bid Security P 25,000.00
BIDDER: Actual surety bond Bid Amount:LEGAB CONSTRUCTION P 25,000.00 P 499,027.99
PROJECT NO. 12Name of Project CLUSTER “C”: a) COMPLETION OF MULTI-
PURPOSE WAREHOUSE AT BINENG; b) CONCRETING OF THIRTY(30) METERS COMMUNAL ROAD OF ZONE 1 AT UPPER WANGAL
Project Location a) BINENG, LA TRINIDAD; b) WANGAL, LA TRINIDAD, BENGUET
Total Project Cost a) P 300,000.00 + b) P 89,000.00= P 389,000.00
ABC a) P 300,000.00 + b) P 89,000.00= P 389,000.00
Source of Fund a) SUPP. BUDGET #6- 2011- CCO; & b) TRUST FUND HOUSING
Min Licensed Required Small ARequired Bid Security P 19,450.00(SURETY); P 7,780.00 (CASH BOND)
BIDDER: Actual surety bond Bid Amount:SHAD CONSTRUCTION P 7,800.00(CASH BOND) ‘a) P 294,865.50
b) P 86,330.41TOT. = P 381,195.91
ALMOND ENGINEERING & CONSTRUCTION
P 20,000.00 (SURETY BOND)
a) P 298,828.40b) P 88,564.25
TOT. = P 387,392.65
PROJECT NO. 13Name of Project CLUSTER “D”: a) CONST. OF WATERWORKS
(CONST. OF TABBAC WATERWORKS SYSTEM) BULALACAO; b) CONST. OF CONCRETE PATHWAY @ SABIAN PRIMARY SCHOOL, UPPER TANEG
Project Location a) BULALACAO, MANKAYAN; b) TANEG, MANKAYAN, BENGUET
Total Project Cost a) P 370,000.00 + b) P 100,000.00= P 470,000.00
ABC a) P 370,000.00 + b) P 100,000.00= P 470,000.00
Source of Fund a) CY 2012 20% PDF; & b) CY 2011 20%
BIDS AND AWARDS COMMITTEE ON INFRASTRUCTURERESOLUTION OF AWARD NO. 2012-04-031
Page 4 of 7
PDF- CCO Min Licensed Required Small ARequired Bid Security P 23,500.00
BIDDER: Actual surety bond Bid Amount:MALCO CONSTRUCTION P 23,500.00 ‘a) P 368,839.96
‘b) P 99,378.68TOT. = P 468,218.64
PROJECT NO. 14Name of Project REPAIR OF TWO CLASSROOMS BUILDING OF
NANGALISAN ELEM. SCHOOLProject Location NANGALISAN, TUBA, BENGUETTotal Project Cost P 389,144.13 ABC P 389,144.13 Source of Fund SEF- 2012 LUMPSUM MOOE Min Licensed Required Small ARequired Bid Security P 19,457.21
BIDDER: Actual surety bond Bid Amount:ROBEN RUNAS
CONSTRUCTION P 19,500.00 P 386,655.37
SHAD CONSTRUCTION P 19,457.25 P 399,788.64(OVER & ABOVE THE ABC)
PROJECT NO. 15Name of Project CONST. OF UPPER TOLLGATE CAMP 6
WATER SYSTEMProject Location CAMP 6, TUBA, BENGUETTotal Project Cost P 250,000.00 ABC P 250,000.00Source of Fund CY 2011 20% PDF Min Licensed Required Small ARequired Bid Security P 12,500.00.00
BIDDER: Actual surety bond Bid Amount:SHAD CONSTRUCTION P 12,500.00 P 249,475.40
PROJECT NO. 16Name of Project CONST. OF WAITING SHED WITH COMFORT
ROOM ALONG MANGGA FMR (PHASE I)Project Location CAMP 3, TUBA, BENGUETTotal Project Cost P 300,000.00 ABC P 300,000.00Source of Fund CY 2011 20% PDF Min Licensed Required Small ARequired Bid Security P 15,000.00.00
BIDDER: Actual surety bond Bid Amount:ROBEN RUNAS
CONSTRUCTION P 15,000.00 P 293,864.22
SHAD CONSTRUCTION P 15,000.00 P 299,515.32
BIDS AND AWARDS COMMITTEE ON INFRASTRUCTURERESOLUTION OF AWARD NO. 2012-04-031
Page 5 of 7
PROJECT NO. 17Name of Project REHAB. OF TACARANG- BATO SPRING
DEVELOPMENT, BAAYANProject Location BAAYAN, TUBLAY, BENGUETTotal Project Cost P 107,251.00 ABC P 107,251.00Source of Fund CY 2012 20% PDF Min Licensed Required Small ARequired Bid Security P 5,362.55
BIDDER: Actual surety bond Bid Amount:HILLSTONE BUILDERS P 5,365.00 P 106,743.00
NOW, THEREFORE, WE, Members of the Bids and Awards Committee, hereby RESOLVED, as it is hereby done to recommend to the Local Chief Executive, that the projects be awarded to the contractors who offered the lone/lowest calculated and responsive bid as enumerated above.
DONE at the PEO Conference Hall, Wangal, La Trinidad, Benguet this 24TH day of April, 2012.
RESOLVED FINALLY, to forward this resolution to Honorable Nestor B. Fongwan, Provincial Governor for his approval. Let copies hereof be furnished to the Provincial Budget Office, Provincial Accounting Office, Provincial Treasury Office and the Provincial Auditors Office for their ready reference and file. Likewise a copy be furnished to the Provincial Engineering Office for their further appropriate action and implementation.
BIDS AND AWARDS COMMITTEE ON INFRASTRUCTURERESOLUTION OF AWARD NO. 2012-04-031
Page 6 of 7
UNANIMOUSLY APPROVED
RENY S. TABDI ORLANDO T. OIDI
Assistant Provincial Engineer Assistant Prov’l. Assessor Member Member
IMELDA I. MACANES NORA S. ASIONG Provincial Treasurer Provincial Budget Officer
Member Vice Chairman
ANING M. BINAYANProvincial Engineer and Chairperson
Bids and Awards Committee on (Infrastructure)
ATTESTED:
ELFREN Q. GAUDIA Engineer IV and Chairman
BAC Secretariat
APPROVED:
NESTOR B. FONGWAN Provincial Governor
_____________________________Date of Approval
NBF/AMB/EQG/jrg’12
BIDS AND AWARDS COMMITTEE ON INFRASTRUCTURERESOLUTION OF AWARD NO. 2012-04-031
Page 7 of 7