37
AFRICAN DEVELOPMENT BANK GROUP REPUBLIC OF KENYA TOWNS SUSTAINABLE WATER SUPPLY AND SANITATION PROGRAM APPRAISAL REPORT OWAS/EARC DEPARTMENTS October 2016 Public Disclosure Authorized Public Disclosure Authorized

REPUBLIC OF KENYA TOWNS SUSTAINABLE … · african development bank group republic of kenya towns sustainable water supply and sanitation program appraisal report owas/earc departments

  • Upload
    builien

  • View
    222

  • Download
    0

Embed Size (px)

Citation preview

AFRICAN DEVELOPMENT BANK GROUP

REPUBLIC OF KENYA

TOWNS SUSTAINABLE WATER SUPPLY AND SANITATION

PROGRAM

APPRAISAL REPORT

OWAS/EARC DEPARTMENTS

October 2016

Pu

bli

c D

iscl

osu

re A

uth

ori

zed

Pub

lic

Dis

clo

sure

Au

tho

rize

d

TABLE OF CONTENTS

I – STRATEGIC THRUST & RATIONALE..................................................................... 1

1.1 PROGRAM LINKAGES WITH COUNTRY STRATEGY AND OBJECTIVES ...................................... 1

1.2 RATIONALE FOR BANK’S INVOLVEMENT ................................................................................ 2

1.3 DEVELOPMENT PARTNER COORDINATION .............................................................................. 3

II – PROGRAM DESCRIPTION ......................................................................................... 4

2.1 PROGRAM OBJECTIVE .............................................................................................................. 4

2.2 PROGRAM COMPONENTS ......................................................................................................... 5

2.3 TECHNICAL SOLUTION RETAINED AND OTHER ALTERNATIVES ............................................. 5

2.4 PROGRAM TYPE ....................................................................................................................... 6

2.5 PROGRAM COST AND FINANCING ARRANGEMENTS ................................................................ 6

2.6 PROGRAM’S TARGET AREA AND POPULATION ....................................................................... 8

2.7 PARTICIPATORY PROCESS FOR PROGRAM IDENTIFICATION, DESIGN AND IMPLEMENTATION 8

2.8 BANK GROUP EXPERIENCE, LESSONS REFLECTED IN PROGRAM DESIGN ............................... 9

2.9 KEY PERFORMANCE INDICATORS .......................................................................................... 10

III – PROGRAM FEASIBILITY ......................................................................................... 10

3.1 ECONOMIC AND FINANCIAL PERFORMANCE ......................................................................... 10

3.2 ENVIRONMENTAL AND SOCIAL IMPACTS .............................................................................. 11

IV – IMPLEMENTATION ................................................................................................... 14

4.1 IMPLEMENTATION ARRANGEMENTS ..................................................................................... 14

4.2 MONITORING AND EVALUATION (M&E) .............................................................................. 17

4.3 GOVERNANCE ........................................................................................................................ 17

4.4 SUSTAINABILITY .................................................................................................................... 18

4.5 RISK MANAGEMENT .............................................................................................................. 19

4.6 KNOWLEDGE BUILDING ......................................................................................................... 19

V – LEGAL INSTRUMENTS AND AUTHORITY ......................................................... 19

5.1 LEGAL INSTRUMENT .............................................................................................................. 19

5.2 CONDITIONS ASSOCIATED WITH BANK’S INTERVENTION ..................................................... 20

5.3 COMPLIANCE WITH BANK POLICIES ...................................................................................... 20

VI – RECOMMENDATION ................................................................................................ 20

APPENDICES .......................................................................................................................... I

APPENDIX 1: KENYA’S COMPARATIVE SOCIO-ECONOMIC INDICATORS ............................................. I

APPENDIX 2: TABLE OF AFDB’S PORTFOLIO IN THE COUNTRY ........................................................ II

APPENDIX 3: KEY RELATED PROJECTS FINANCED BY THE DPS IN THE COUNTRY .......................... III

APPENDIX 4: MAP OF KENYA AND TARGET TOWNS ......................................................................... IV

APPENDIX 5: JUSTIFICATION FOR FINANCING MORE THAN 50% OF THE PROGRAM COST THROUGH AN

ADB LOAN ........................................................................................................................................ V

APPENDIX 6: CLIMATE SCREENING – FULL RESULTS ...................................................................... VII

i

Currency Equivalents

June 2016

UA 1 = KES 143.3506

UA 1 = USD 1.4029

UA 1 = EUR 1.2600

FISCAL YEAR:

July 1 – June 30

Weights and Measures

1 metric ton = 2204 pounds (lbs)

1 kilogram (kg) = 2.200 pounds (lbs)

1 meter (m) = 3.28 feet (ft)

1 millimeter (mm) = 0.03937 inch (“)

1 kilometer (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

ii

ACRONYMS AND ABBREVIATIONS

ADB African Development Bank MIS Management Information System

AfDB African Development Bank Group MTP-II Medium Term Plan II

ADF African Development Fund MoWI Ministry of Water and Irrigation

AEG Aid Effectiveness Group NCCRS National Climate Change Response Strategy

AES Aid Effectiveness Secretariat NEMA National Environment Management Authority

AFD Agence Ffrançaise de Développement NPV Net Present Value

AREP Adaptation Review and Evaluation Procedures

NRW Non-Revenue Water

AWSB Athi Water Services Board NWSS National Water Services Strategy 2007-2015

CCAP Climate Change Action Plan O&M Operation & Maintenance

CPPR Country Portfolio Performance Review OAG Office of the Auditor General

CSP Country Strategy Paper PAP Project Affected Population

DO Development Objective PCR Project/Program Completion Report

DP Development Partner PIT Program Implementation Team

DPF Development Partnership Forum PPG Public and Publicly Guaranteed

DPG Development Partners Consultative Group RAP Resettlement Action Plan

DSA Debt Sustainability Analysis RBLF Result Based Logical Framework

EARC Bank’s Eastern Africa Regional Resource Center

RMC Regional Member Country

EIA Environmental Impact Assessment RVWSB Rift Valley Water Services Board

EIRR Economic Internal Rate of Return SC Steering Committee

ENPV Economic Net Present Value SDG Sustainable Development Goal

ERP Enterprise Resource Planning SIDA Swedish International Development Cooperation Agency

ESAP Environmental and Social Assessment Procedure

SWG Sector Working Group

ESIA Environmental and Social Impact Assessment TWSB Tana Water Services Board

ESMF Environmental and Social Management Framework

UA Unit of Account

ESMP Environmental and Social Management Plan WRMA Water Resources Management Authority

EU European Union WASREB Water Services Regulatory Board

FIRR Financial Internal Rate of Return WB The World Bank

FM Financial Management WSB Water Services Board

FNPV Financial Net Present Value WSP Water Service Provider

GCG GoK Coordinating Group WSTG Water Sector Technical Group

GDP Gross Domestic Product

GoK Government of Kenya

HDI Human Development Index

IFAD International Fund for Agricultural Development

IFMIS Integrated Financial Management Information System

IP Implementation Progress

IPR Implementation Progress Report

IPSAS International Public Sector Accounting Standards

IWRM Integrated Water Resources Management

JICA Japan International Cooperation Agency

KES Kenyan Shillings

KfW Kreditanstalt fur Wiederaufbau

KOICA Korea International Cooperation Agency

KPI Key Performance Indicator

M&E Monitoring & Evaluation

MIC-TAF Middle Income Country Technical Assistance Fund

iii

LOAN INFORMATION

Client’s information

Recipient: Republic of Kenya

Executing Agency: Ministry of Water and Irrigation (MoWI)

Financing plan

Source Amount (million UA) Instrument

ADB 271.721 (USD 381.191m) Loan

ADF Loan 5.135 Loan

ADF Grant 0.512 Grant

MIC-TAF 1.200 Grant

GoK 43.388 Counterpart

Total Cost 321.955

ADB’s key financing information

Loan Currency USD

Loan Type Fully Flexible Loan

Tenor 25 years inclusive of grace period

Grace period 8 years

Repayments Consecutive semi-annual payments after grace period

Interest Rate Base Rate +Funding Cost Margin+ Lending Margin + Maturity Premium

Base Rate Floating Base Rate (6-month USD LIBOR reset each 1st February and 1st

August). A free option to fix the Base Rate is available.

Funding Cost Margin The Bank funding cost margin as determined each 1st January and 1st July

and applied to the Base Rate each 1st February and 1st August

Lending Margin 80 basis points (0.8%)

Maturity Premium - 0% if Average Loan Maturity <= 12.75 years

- 0.10% if 12.75< Average Loan Maturity <=15

- 0.20% if Average Loan Maturity >15 years

Front-end fees 0.25% of the loan amount payable at latest at signature of the loan

agreement

Commitment fees 0.25% of the undisbursed amount. Commitment fees start accruing 60

days after signature of the loan agreement and are payable on Payment

dates

Option to convert the Base Rate In addition to the free option to fix the floating Base Rate, the borrower

may reconvert the fix rate to floating or refix it on part or full disbursed

amount. Transaction fees are payable.

Option to cap or collar the Base

Rate

The borrower may cap or set both cap and floor on the Base Rate to be

applied on part or full disbursed amount. Transaction fees are payable.

Option to convert loan currency The borrower may convert the loan currency for both undisbursed and/or

disbursed amounts in full or part to another approved lending currency of

the Bank. Transaction fees are payable.

ADF loan key financing information

Currency Unit of Account

Interest rate spread 1%

Commitment fee 0.5% per annum on the undisbursed loan amount

Service charge 0.75% per annum on amount disbursed and outstanding

Duration 30 years

Grace period 5 years

iv

Key financial and economic analysis information

FNPV (at 10% base case) KES 16,288 million

FIRR (at 10% base case) 17.0 %

ENPV (at 10% base case) KES 73,897 million

EIRR (at 10% base case) 33.8 %

Timeframe - Main Milestones (expected)

Concept Note Approval June 2016

Program Approval October 2016

Effectiveness December 2016

Completion June 2021

Last Disbursement September 2021

v

Program Summary

Program

Overview

The main objective of the program is to improve the access, quality, availability and sustainability of water supply and wastewater management services in multiple towns in Kenya,

with a view to catalyzing commercial activities, driving economic growth, employment creation, improving quality of life of the people and building resilience against climate variability and change. The program objective will be achieved through: i) construction and rehabilitation of water supply and sanitation infrastructure (including expansion into informal settlements) for improved water and sanitation services; and ii) capacity development of water service providers, the sector regulator for improved service efficiency and women and youth for increased

employment opportunities. The program will support water supply infrastructure in 19 towns and sanitation infrastructures in 17 towns, providing more than 2.1 million people with reliable and sustainable water supply services and more than 1.3 million people with water-borne sewerage systems. In addition, the program will create more than 15,000 new jobs during and after construction. The program will cost an estimated USD 451.66 million of which USD 324.86 million will be

in foreign currency. An African Development Bank (ADB) loan of (USD 381.19m), African

Development Fund (ADF) loan (USD 7.20m) and grant (USD 0.72m) and a Middle Income

Country Technical Assistance Fund (MIC-TAF) grant (USD 1.68m) will cover 86.52% of the

program costs. The program is expected to be implemented over 54 months starting in January

2017. The government of Kenya (GoK) contributes USD 60.87 million (UA 43.39m) in

counterpart contribution to be budgeted for annually starting from the 2016/2017 fiscal year.

Needs

Assessment

Kenya’s economic and social developments as stated in Vision 2030 depend heavily on an adequate and sustainable provision of water supply and sanitation services. Moreover, the rapid urbanization in the country calls for more effective and efficient water and sanitation services provision in order for cities and towns to remain as drivers of economic growth. Currently serious challenges are being encountered in the delivery of water and sanitation services in the selected towns, which are currently not able to cope with the rapid growth in demand and demographic

changes. Currently, access to water and water-borne sanitation services in these towns remains low ranging from 10 to 55% and 0 to 40% respectively, which is well below the Sustainable Development Goals (SDG’s) targets. The selected towns are: (i) those prioritized by the government in the Medium Term Plan II (MTP-II) (2013-2017); (ii) with low water and sanitation coverage; and (iii) where the water and sanitation needs are not being addressed by any other development partners (DPs).

Bank’s Added

Value

The proposed program fits within the pillar 1 of the Bank’s Country Strategy Paper (CSP) for 2014–2018, “focusing on enhancing physical infrastructure to unleash inclusive growth” and contributes to Outcome 3: Enhanced access to more reliable water supply and improved sanitation. The program also resonates with three (3) of the High-5s: Feed Africa, Industrialize Africa, and Improved the quality of life for the people of Africa.

The proposed program complements the completed Water Services Boards Support Project and the ongoing Small Towns and Rural Water Supply and Sanitation Project which was approved in 2009 and scheduled to be completed in 2016. The Bank has had a long engagement with the GoK in the water and sanitation sector which began in 1978. This program will continue this partnership and will support the government as it addresses the urban development challenges and reforms in the sector.

Knowledge

Management

The program will add to the extensive body of knowledge on the water and sanitation sector that has been generated overtime in Kenya. In particular it will build lessons for the design and management of similar interventions with potential for replication throughout the country as well as to other regional member countries (RMCs). The proposed study on the impact of water supply and sanitation services on job creation will analyze the potential of the water and sanitation sector

to unlock the latent economic and job creating opportunities for the people. Studies for future investments will build on global best practices and success cases in the country, and ensure climate change, gender and any other cross-cutting issues are mainstreamed. The knowledge obtained will be captured, documented and shared within the Bank and with other DPs and RMCs.

vi

Results Based Logical Framework Country and Program Name: Kenya Towns Sustainable Water Supply and Sanitation Program – Kenya Purpose of the Program: To unlock economic growth potential and improve quality of life of the people through provision of safe, affordable and sustainable water and sanitation services.

RESULTS CHAIN PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS/MITIGATION

MEASURES Indicator (including CSI) Baseline (2015) Target (2020)

IMP

AC

T

Improved quality of life of the people through increased access to water supply and sanitation services

1. Access to water supply and sanitation services (%) 63%, 57% 75%, 71% UN report

2. Under five mortality rate 51/1,000 20/1,000 National statistics

OU

TC

OM

ES

1. Improved water and sanitation services

1.1 People with access to piped water (50% women) 1,140,000 2,110,000 Program progress report`

Potential conflict between counties and water works development agencies: involvement of counties from conceptual stage and continuous engagement. Reduced water resources due to climate change: support to preparation of adaptation plans, and capacity building for the implementation.

1.2 People with access to sewerage (50% women) 390,000 1,340,000

2. Improved service efficiency and sustainability

2.1 % of NRW in target towns 45% Less than 30%

2.2 Hours of water supply per day 8 hours 24 hours

2.2 O&M cost coverage 90% 150%

3. Increased employment opportunities

3.1 No. of direct permanent and temporary job created 0 600 (at least 30% women), 3,200

3.2 No. of indirect permanent and temporary job created as a result of the program

0 2000, 10,000 (more than 30% women)

OU

TP

UT

S

Component 1: Water Supply & Sanitation Infrastructure Program progress report

Delays due to compensation issues: early negotiations involving county governments and awareness exercises directed at the identified PAPs. Insufficient capacity of the implementation teams: clustering of WSBs based on capacity assessment and close interaction with the PITs through the EARC.

1.1 Construction of water supply infrastructure

1.1.1 Length of water pipes laid 0 km 1,000 km

1.1.2 No. of water treatment plants constructed/ upgraded 0 20

1.1.3 No. of intake structures constructed/ rehabilitated 0 17

1.2 Construction of sanitation infrastructure

1.2.1 Length of sewer pipes laid 0 km 500 km

1.2.2 No. of wastewater treatment plants constructed/ upgraded 0 17

1.2.3 No. of ablution blocks constructed 0 67

Component 2: Institutional Development Support

2.1 Capacity development 2.1.1 No. of laboratories constructed, supplied with equipment 0, 0 11, 19

2.1.2 No. of exhausters procured 0 7

2.1 .3 No. of WSP/WSB staff trained 0 800 (at least 30% women)

2.1.4 No. of climate mainstreamed WSP business plans developed/revised (gender-informed)

0 20

2.1.5 No. of studies prepared for future investments 0 12

.KE

Y

AC

TIV

ITIE

S ACTIVITIES INPUTS

Component 1: Water Supply & Sanitation Infrastructure: Construction, rehabilitation and expansion of water supply infrastructure; and Construction of sewerage

infrastructure and ablution blocks.

Component 2: Institutional Development Support: Development of business plans; Capacity assessment and training of WSPs, women and youth; Construction of

laboratories and provision of equipment; Support to the WASERB and the WRMA; and Preparation of future investment projects.

Component 3: Program Management*: Annual audits; Operation costs (staff salaries, office spaces, fuel, vehicle maintenance, staff travel expenses, steering

committee meetings etc.); and Land compensation.

By component: 1) UA 259.93m,

2) UA 18.64m, 3) UA 43.39m

Total Program Cost - UA 321.95 million

ADB: UA271.72m; ADF-loan: UA5.13m; ADF-

grant: UA0.51m; MIC-TAF: UA1.20m; GoK:

UA43.39m

* Component to be financed by the government

vii

PROGRAM IMPLEMENTATION SCHEDULE

Component 1: Water Supply and Sanitation Infrastructure

Component 2: Institutional Development Support

Component 3: Program Management

Project Disbursment Deadline - Sep. 2021

1-4 Works (design & build): Water Supply and Sanitation Infrastructure

1-3 Supervision of Works (design & build)

1-2 Works: Water Supply and Sanitation Infrastructure

2021

Advance Procurment Activities

Activity

Loans/Grants Signature

Loans/Grants Effectiveness

20192018

Q4 Q1 Q2 Q3

2016 2017 2020

Q1 Q2 Q1 Q2Q4Q2Q1 Q3 Q4

Mid-term Review

Program Completion

1-1 Desing Review and Supervision of Works

Q4 Q3Q4 Q1 Q2 Q3Q3

Program Approval

2-2 Climate Change Adaptation

3-3 Land Compensation

3-2 Program Operation

First Disbursment

1-5 Last mile connectivity support

3-1 Program Audit

2-6 Training of Women and Youth on Management of Water and Sanitation Businesses

2-1 Institutional Development

2-5 Support to WASREB and WRMA

2-4 Knowledge Work

2-3 Studies for Future Investment

1

REPORT AND RECOMMENDATION OF THE MANAGEMENT OF THE AFDB GROUP TO THE BOARD

OF DIRECTORS ON THE PROPOSED ADB AND ADF LOANS AND ADF AND MIC-TAF GRANTS TO

THE GOVERNMENT OF THE REPUBLIC OF KENYA FOR THE KENYA TOWNS SUSTAINABLE

WATER SUPPLY AND SANITATION PROGRAM

Management submits the following report and recommendation on proposed ADB loan of USD

381.191 million, ADF loan not exceeding UA 5.135 million, and ADF grant of UA 0.512 million

and MIC-TAF grant not exceeding UA 1.200 million to finance the Kenya Towns Sustainable

Water Supply and Sanitation Program.

I – STRATEGIC THRUST & RATIONALE

1.1 Program Linkages with Country Strategy and Objectives

1.1.1 The Kenya Vision 2030 aims to transform and elevate the country to an industrialized,

middle income country, providing a high quality of life to all its citizens by 2030. The country has

in the recent past experienced positive economic growth, alongside an increased rate of

urbanization. It is widely acknowledged that urbanization in Kenya has supported the gross

domestic product (GDP) growth, economic transformation, increases in productivity and incomes,

and employment creation1. Overall GDP growth was estimated at 5.5% in 2015 and projected to

rise to 6.0% in 2016 and 6.4% in 2017. Cities and towns have the potential to drive sustainable

economic growth and social development, and it is projected that more than half of the people in

Kenya will be living in cities and towns by 2030, who will need jobs, housing, infrastructure and

other services. Furthermore, following the promulgation of the Constitution of Kenya in 2010, the

47 new county governments are now responsible for devolved services resulting in new

developments in and around county headquarters resulting in an increase in the urban population.

1.1.2 While vibrant cities and towns are critical for the economic development of the country,

rapid urban growth and demographic changes are posing challenges on the water and sanitation

services delivery. Furthermore, inadequate investments in water and sanitation infrastructure is

negatively impacting the main productive sectors of agriculture, tourism, manufacturing, service

industries and energy. Despite increased government investments in the sector (from $82.5 million

per annum in 2005 to $450 million in 2015), the financing gap to meet the Vision 2030 targets for

water and sanitation in the country remains huge at about USD 19.2 Billion (World Bank, 2016),

resulting in access to improved water source and improved/shared sanitation facilities remaining

at 63% and 57% respectively2, well below the Sustainable Development Goal (SDG) targets which

aim at universal access. The low access rate is partly attributed to rapid urbanization, population

growth, weak institutional capacity of the sector and negative impacts of climate change. The

selected towns under the program are: (i) those prioritized by the government in the Medium Term

Plan II (MTP-II) (2013-2017); (ii) with low water and sanitation coverage; and (iii) where the

water and sanitation needs are not being addressed by any other development partners (DPs).

1.1.3 The government of Kenya (GoK) has shown consistent commitment to the sector reforms

since the enactment of the Water Act 2002, and the DPs continue to support the reform process.

Following the promulgation of the new constitution, water and sanitation services are now a

devolved function of the county governments and a new Water Act is in the process of being

enacted to align with the new constitution. The new water bill has passed through the parliament

and its awaiting signature into law by the president.

1 Largest urban centers generate 70% of country’s GDP. 2 Joint Monitoring Programme 2015

2

1.1.4 The water sector reforms have provided a supportive and progressive framework on which

devolution in Kenya can build on in ensuring efficient service delivery. Key challenges the sector

continues to address include: (i) weak capacity of the new institutions to effectively implement

their mandate; (ii) weak governance in the sector institutions; (iii) economically unviable water

service providers; and (iv) the need for more infrastructure investments to cope with the rapid

population increase, urbanization and economic growth. In addition to addressing the challenges

posed by insufficient infrastructure base and weak institutional capacity, the proposed program

will further support the reform initiatives, such as regular performance monitoring and tariff

reviews by Water Services Regulatory Board (WASREB). This support will enhance the

sustainability of the water services providers (WSPs) that are mandated with operating and

maintaining the water infrastructure in the towns. The Bank’s support under the program will

include assistance in coherent investment planning and project preparation in order to deliver

timely and sustainable infrastructure for effective water and sanitation services to the 47 counties.

1.1.5 The GoK’s Vision 2030 and its five (5) years MTP-II form the development blue print for

the country with the three (3) key development areas of: (i) economic growth; (ii) social investment

and poverty reduction; and (iii) institutional strengthening and improvement in governance. The

Vision 2030 pillars are anchored on infrastructure development, public sector reform and

macroeconomic stability. Kenya’s economic and social developments, as stated in the Vision

2030, are heavily dependent on adequate and sustainable provision of water supply and sanitation

services. Furthermore, the rapid urbanization in the country calls for more effective and efficient

water and sanitation services in order for cities and towns to remain as drivers of economic growth.

The MTP-II (under the economic and social pillars) prioritizes water and sanitation infrastructural

investments including expansion of water supply and sanitation in major and medium towns and

water resources development and management.

1.2 Rationale for Bank’s Involvement

1.2.1 Despite the latent economic growth potential in the targeted 28 towns, the development

and growth of these towns is still constrained by prevailing deficiencies in urban infrastructure3

and the low service levels, both in the existing built-up areas (including the informal settlements)

and its peripheries where townships are expanding; deteriorating environmental conditions; and

insufficient finances and weak management capacity. The water supply coverage in the target

towns varies from below 10% to around 55%. Water borne sanitation does not exist in many of

the target towns with average global service coverage of approximately 13%. Currently, only about

half of the WSPs under the program are able to supply water for more than 16 hour per day and

cover operation and maintenance (O&M) cost, while non-revenue water range between 31 and

66%. Delivery of safe, adequate and reliable water and sanitation services to these towns is hence

a high priority.

1.2.2 This program fits within the pillar 1 of the Bank’s Country Strategy Paper (CSP) 2014–

2018, “focusing on enhancing physical infrastructure to unleash inclusive growth” and contributes

to the Outcome 3: Enhanced access to more reliable water supply and improved sanitation. The

proposed program will improve water and sanitation services for commercial and industrial use,

household consumption, and also for minor irrigation and livestock requirements in some towns,

thereby enhancing food security.

1.2.3 The program aligns with the Bank’s Integrated Water Resource Management Policy (2000)

and the Bank’s Strategy for 2013-2022 which recognizes development and management of water

as central to Africa’s sustainable growth. The program is also supported by the Urban

Development Strategy (2011) by providing strategic infrastructures for economic growth. The

3 Poor infrastructure is slowing down economic development, constraining household economic development including businesses,

attractiveness for investment.

3

program’s support to provision of water and sanitation services and capacity building with focus

on women and youth are aligned to Pillars II and III of the Bank’s Gender Strategy (2014-2018)

and Bank Group Strategy for Jobs for Youth in Africa (2016-2025). By enhancing the capacity of

the country to provide basic services especially to conflict-prone areas, the program aligns with

the Bank’s Strategy for Addressing Fragility and Building Resilience in Africa (2014-2019). In

line with Knowledge Management Strategy (2015-2020), lessons from this intervention will help

improve the quality of the Bank’s involvements in urban water and sanitation sub-sector. By

providing sustainable and affordable water and sanitation services, the program will lay

foundations for industrialization and food security, enhance the sources of economic and social

resilience of the people, and contribute to improved quality of life for the people which are in line

with the five (5) priority areas of focus (High-5s) to advance Africa’s transformative agenda to

deliver the outcomes of the Bank’s Strategy for 2013-2022.

1.2.4 The proposed program further complements the completed Water Services Boards Support

Project and the ongoing Small Towns and Rural Water Supply and Sanitation Project approved in

2009 and scheduled to be completed in 2016. The Bank has had a long engagement with the GoK

in the water and sanitation sector since 1978. This program will continue this partnership and

support the government as it moves forward to address the next generation of urban development

challenges and reforms in the sector.

1.3 Development Partner Coordination

1.3.1 The apex aid coordination body in Kenya is the Development Partnership Forum (DPF)

established in 2011. The forum is attended by heads of diplomatic missions and aid agencies, and

heads of government departments. The DPF meets twice a year to discuss key policy issues, and

agrees on a set of deliverables over the subsequent six (6) months. Other groups include the DPs

Consultative Group (DPG), the GoK Coordinating Group (GCG), the Aid Effectiveness Group

(AEG), the Aid Effectiveness Secretariat (AES) and the Sector Working Groups (SWGs).

Table 1: DP Coordination Groups Coordination Group Membership and Role

DPs Consultative Group (DPG) Heads of diplomatic mission and aid agency GoK Coordinating Group (GCG) Heads of government department meeting every month

Aid Effectiveness Group (AEG) Coordinates the dialogue between the DPG and the GCG; Monitors and reports on the progress of agreed deliverables and the global aid effectiveness objectives; and provides advisory support to the SWGs

Aid Effectiveness Secretariat (AES)

The AES established at the National Treasury is the secretariat to the AEG.

1.3.2 The Bank, through the East African Resource Centre (EARC) participates at all levels of

aid coordination and chairs the DP’s working Group on Education, and co-chairs the AEG with

the National Treasury. The EARC also participates in several SWGs, including on roads, water

and sanitation, energy, and public finance management.

1.3.3 DPs active in the water sector currently have a commitment of about USD 1.0 billion

towards water and sanitation projects including institutional support. Most of these come from the

AfDB, the World Bank (WB), Kreditanstalt fuer Wiederaufbau (KfW), Japan International

Cooperation Agency (JICA), Agence Française de Développement (AFD) and the government of

Italy. Water supply and sanitation projects for towns are supported by a number of donors and

allocation of towns and activities is coordinated by the government. Collaboration between donors

has been scaled up with the establishment of the Water Sector Technical Group (WSTG) which

meets once every two (2) months and is currently being chaired by the WB.

4

The financing arrangements of infrastructure development in the sector leans towards division of

labor between DPs and the government, with the GoK coordinating and allocating DPs areas and

activities of focus. The mission held consultative meetings with DPs to harmonize the program

with ongoing and upcoming projects in the urban water and sanitation sub-sector and to ensure

synergies and complementarities. DPs’ interventions in town water supply and sanitation are

listed in

1.3.4 Table 3, and it is evident that all donors are allocated areas of focus in support of the GoK’s

global target of increasing coverage for water supply and sanitation.

Table 2: Summary of the Sector Financing

Sector or subsector Size

GDP Budget Labor Force

Water and Sanitation NA 3.9% NA

Players – Water and Sanitation Public Annual Expenditure (ave. 2014 & 2015)

Government DPs

KES Billion 23 26

% 47 53

Level of Donor Coordination Existence of Thematic Working Groups Y Existence of SWAps or Integrated Sector Approaches Y AfDB's Involvement in DPs coordination Y

Table 3: Examples of other DPs’ Interventions in Town Water Supply and Sanitation Financier Project/Program Target Areas

KfW Water Sector Development Programme Nairobi City Water Distribution Network Nairobi Satellite Towns and Sanitation Program

Migori, Homa Bay, Kericho, Litein, Kisii and Nyamira towns Nairobi and satellite towns

WB Water & Sanitation Services & Improvement Project (WaSSIP)

Water Security and Climate Resilience Nairobi Sanitation Output Based Aid (OBA)

Project Kenya Urban Water & Sanitation OBA Fund for

Low Income Areas Project

Wote, Masalani, Baricho, Taveta Lumi, Ellegerini, Kapsoya, Kwanza, Kapcherop, Suswa, Kapindaram, Nyalani Mombasa Masalani, Bute, Moyale and Rumuruti and towns Wajir, Garissa, Mandera, Marsabit and Isiolo Counties Nairobi metropolitan

Government of Italy

Kenya Italian Debt development Program Rehabilitation of Water and Sanitation-Kiambere Rehabilitation of Water and Sanitation - Kirandich Itare Dam Water Supply Project Mariakani-Kaloleni Water Project Tarbo Laseru Water Project Manooni Water Project

Kabarnet, Kabartonjo, Kapsoo - Kaptarakwa, Kituro, Kaput, Pusol, West Karachuonyo, Sindo Migwani, Kajiado Umanyi, Kibwezi, Kathangachini, Wajir towns

JICA Narok Water Project Rural Water Supply in Baringo County

Narok Town Baringo County

AFD Complementary Funding for Nairobi Water and Sewage

Complementary Funding for Kisumu Water and Sewerage

Extension of Nairobi Water Supply

Machakos and Kisumu Town, Nairobi

II – PROGRAM DESCRIPTION

2.1 Program Objective

2.1.1 The water and sanitation sector goal is to contribute to the health and quality of life and

reduce poverty levels of the population of Kenya through provision of water and sanitation services

on a sustainable basis.

2.1.2 The main objective of the program is to improve the access, quality, availability and

sustainability of water supply (in 19 towns) and wastewater management services (in 17 towns),

World Bank 50% AfDB 24% Italy 5% JICA 4.5% AFD 4% (KfW, IFAD 12.5% Sida, EU, KOICA)

5

with a view to catalyzing commercial activities, driving economic growth, improving quality of

life of the people and building resilience against climate variability and change.

2.2 Program Components

2.2.1 The program will cover 28 towns, supporting water supply infrastructure in 19 towns and

sanitation infrastructure in 17 towns (where reliable water supply services are already provided or

will be supported under the proposed program). Resources are also set aside for various capacity

development activities and preparation of future investment projects. The components and outputs

of the proposed program are provided in Table 4.

Table 4: Program Components

Component & Outputs Est. cost

(million USD)

1. Water Supply & Sanitation Infrastructure 1-1 Construction of water supply infrastructure (including expansion into informal

settlements) 1-2 Construction and rehabilitation of sewerage infrastructure and ablution blocks 1-3 Last mile pipe connectivity support 1-5 Design review and supervision of works consultancy

315.044 (224.570)

2. Institutional Development Support 2-1 Provision of water testing laboratories and equipment 2-2 Provision of equipment to manage Non-revenue Water (NRW) (leakage detection

devices, billing systems etc.) 2-3 Provision of equipment for sewer maintenance including sewer flushing units 2-4 Provision of exhausters 2-5 Provision of Vehicles 2-6 Procurement of Enterprise Resource Planning (ERP) packages 2-7 Climate change: risk assessment and preparation of action plans, provision of water

reuse facilities for schools and piloting of biogas domes for markets and anaerobic bioreactor for landfills

2-8 Capacity assessment and provision of training for WSPs and WSBs on O&M of water supply and sewerage infrastructure including promotion of environmental health and hygiene practices.

2-9 Preparatory studies (up to tender documents) for future investments 2-10 Study on impact of water supply and sanitation services on job creation with gender

focus 2-11 Support to the WASREB and the WRMA 2-12 Training of women and youth on management of water and sanitation businesses

arising out of the program

23.656 (16.862)

3. Program Management * 3-1 Annual Financial Audits, and Technical Audits when required 3-2 Operation costs (staff salaries, office spaces, fuel, vehicle maintenance, staff travel

expenses, steering committee meetings etc.) 3-3 Land Compensation

55.335 (39.444)

Total Base Cost 394.034

(280.875)

Contingencies (Physical & Price) 57.630

(41.080)

Total Cost 451.664 (321.955)

* activities to be financed by the government, figures in ( ) are in UA

2.3 Technical Solution Retained and Other Alternatives

2.3.1 Technical solutions retained are based on studies conducted for each sub-project, taking

into account available water resources, socio-economic status of each town, appropriate

technology and capital and operational costs.

6

2.3.2 Reduction of non-revenue water as well as enhanced capacity of the WSPs are integral part

of the program for efficient delivery of water and sanitation services and sustainability of the

investments.

2.3.3 Various technical solutions were explored (Table 5) for the program taking into account

characteristics of water sources, operation and maintenance costs and capacity in the country.

Table 5: Analysis of the Various Alternatives Considered Alternative Brief Description Selected Option / Reasons for Rejection

Water sources - Use of pumps for raw water main and distribution.

Use of pumping which require constant power supply to reduce distance for water conveyance.

Sources of the water supply services for respective sub-projects are either surface or groundwater selected based on water resources assessment. As much as possible, water intake points were selected to avoid or minimize use of pumping and allow for gravity conveyance for reduced operation cost.

Sanitation options - Sewerage system for low density areas and on-site sanitation for densely populated areas.

Uniformly providing water-borne sanitation infrastructure in all target towns.

Due to high O&M cost of the system, sewerage will be introduced to business center districts and areas with high population density where the option could be economically justified and continuous use of on-site sanitation could pose health and environmental threats. Sites for wastewater treatment plants were selected to minimize pumping. For other areas, septic tanks will continue to be the most viable option, and the program will provide exhausters for the improved management of these facilities. Promotion of environmental health and hygiene is incorporated in the interventions.

Integrated services delivery – Water supply intervention without sanitation services.

Investment for water supply infrastructure only with no provision for sanitation.

Option of only supporting water infrastructure, though financially more viable, was rejected to ensure environmental and social sustainability, and to enable reuse of treated water downstream. Sanitation infrastructure will be supported under the program in towns where water will be provided under the program or where water is already available through completed/ ongoing projects. For towns whose sanitation studies are not ready, readiness of sanitation projects will be supported under the proposed program for future investments.

2.4 Program Type

2.4.1 The proposed program supports infrastructure investments as well as institutional capacity

development funded through a combination of loans, grants and government counterpart

contribution. The program involves multiple projects or interventions to be implemented in

beneficiary towns located across Kenya. The funding instrument for the proposed intervention is

sector investment. The program complements with the projects/programs funded by other donors

and government that focus on urban water and sanitation sub-sector by supporting components or

towns that are not covered by other DPs.

2.5 Program Cost and Financing Arrangements

2.5.1 The total cost of the program for the components, defined in 2.2 above, is estimated at USD

451.664 million, net of taxes and duties. Of this, USD 324.858 million or 71.92% is in foreign

currency and USD 126.806 million is in local currency. Tables au-dessous provide the summary

of the program costs.

7

Table 6: Program Cost Estimates by Component in million USD

Component Foreign

Exchange Local

Currency Total

Foreign Currency %

% Total

1. Water Supply & Sanitation Infrastructure 299.712

(213.641) 64.939

(46.290) 364.651

(259.931) 82.19% 80.73%

2. Institutional Development Support 25.146

(17.924) 0.999

(0.712) 26.145

(18.636) 96.18% 5.79%

3. Program Management 0.000

(0.000) 60.868

(43.388) 60.868

(43.388) 0.00% 13.48%

Total 324.858

(231.565) 126.806 (90.390)

451.664 (321.955)

71.92% 100.0%

( ) is in million UA

Table 7: Sources of Financing in million USD Source Foreign Exchange Local Currency Total %

ADB 315.253 (224.719) 65.938 (47.002) 381.191 (271.721) 84.40%

ADF loan 7.203 (5.135) – 7.203 (5.135) 1.59%

ADF grant 0.718 (0.512) – 0.718 (0.512) 0.16%

MIC-TAF 1.683 (1.200) – 1.683 (1.200) 0.37%

GoK – 60.868 (43.388) 60.868 (43.388) 13.48%

Total 324.858 (231.565) 126.806 (90.390) 451.664 (321.955) 100%

( ) is in million UA

Table 8: Program Cost by Category of Expenditure in million USD Category of Expenditure

Foreign Currency Local Currency Total % Foreign

A. Works 266.905 (190.255) 65.938 (47.002) 332.843 (237.257) 80.19%

B. Services 47.866 (34.120) – 47.866 (34.120) 100.00%

C. Goods 10.087 (7.190) – 10.087 (7.190) 100.00%

D. Operating Cost – 60.868 (43.388) 60.868 (43.388) 0.00%

Total 324.858 (231.565) 126.806 (90.390) 451.664 (321.955) 71.92%

( ) is in million UA

Table 9: Expenditure by Component and Source in million USD

Component ADB ADF-loan ADF-grant

MIC-TAF

GoK Total

1. Water Supply & Sanitation Infrastructure

364.651 (259.930)

– – – – 364.651

(259.930)

2. Institutional Development Support

16.540 (11.790)

7.203 (5.135)

0.718 (0.512)

1.683 (1.200)

– 26.145

(18.637)

3. Program Management – – – – 60.868

(43.388) 60.868

(43.388)

Total 381.191

(271.721) 7.203

(5.135) 0.718

(0.512) 1.683

(1.200) 60.868

(43.388) 451.664

(321.955)

( ) is in million UA

Table 10: Category of Expenditure by Funding Source in million UA Category of Expenditure

ADB ADF-loan ADF-grant MIC-TAF GoK Total

A. Works 332.843

(237.257) – – – –

332.843 (237.257)

B. Services 38.262

(27.274) 7.203

(5.135) 0.718

(0.512) 1.683

(1.200) –

47.382 (33.775)

C. Goods 10.087 (7.190)

– – – – 10.087 (7.190)

D. Operating Costs – – – – 60.868

(43.388) 60.868

(43.388)

Total 381.191

(271.721) 7.203

(5.135) 0.718

(0.512) 1.683

(1.200) 60.868

(43.388) 451.664

(321.955)

( ) is in million UA

8

Table 11: Expenditure Schedule by Component in million USD Component 2017 2018 2019 2020 2021 Total

1. Water Supply & Sanitation Infrastructure

72.811 (51.901)

137.101 (97.728)

137.101 (97.728)

17.068 (12.166)

0.570 (0.406)

364.651 (259.930)

2. Institutional Development Support

8.542 (6.089)

9.085 (6.476)

7.795 (5.556)

0.582 (0.415)

0.140 (0.100)

26.145 (18.637)

3. Component C: Program Management

41.494 (29.578)

4.844 (3.453)

4.844 (3.453)

4.844 (3.453)

4.844 (3.453)

60.868 (43.388)

Total Costs 122.848 (87.568)

151.030 (107.657)

149.740 (106.737)

22.493 (16.034)

5.554 (3.959)

451.664 (321.955)

( ) is in million UA

2.6 Program’s Target Area and Population

2.6.1 The proposed program will cover 28 towns comprising small to large-scale sub-projects

spread across Kenya. The major beneficiaries will include the eight (8) water services boards

(WSBs), over 15 WSPs and population within the beneficiary towns who will benefit from

improved service delivery and reliable access to sustainable water and sanitation. The support to

the WASREB and the Water Resources Management Authority (WRMA), which is expected to

result in enhanced performance of WSPs will indirectly deliver wider benefits to the population.

2.6.2 At the end of the interventions, more than 2.1 million people will have reliable and

sustainable water supply services while more than 1.3 million people will be connected to water-

borne sewerage systems. The program benefits include: (a) improved reliability of the water and

sanitation services; (b) overall improvement of the public health situation in the beneficiary towns

as a result of more reliable water supply and sanitation services; (c) an improved O&M capacity

of WSPs; and (d) improved business environment for industries that rely on dependable water and

sanitation services.

2.7 Participatory Process for Program Identification, Design and Implementation

2.7.1 Public consultations form an integral part of the program. The program has adopted an

inclusive coordination framework comprising all stakeholders (including county governments,

WSPs, and beneficiaries) to ensure engagement, local ownership and exchange of information

during and after implementation.

2.7.2 Consultations have been conducted at various stages of the program development with a

range of stakeholders to ensure their concerns and expectations with respect to the positive and

negative impacts of the program are well captured and integrated in the program.

2.7.3 During program preparation and appraisal and preparation of the environmental and social

management framework (ESMF) report, discussions were held with different stakeholders

including WSBs, WSPs, National Environment Management Authority (NEMA), county

government officials and target beneficiaries. Similarly, in line with the environmental and social

impact assessment (ESIA) regulations of the GoK, beneficiaries and project affected populations

(PAPs) were consulted during the preliminary assessment studies and environmental impact

assessments (EIAs) conducted by the government to provide an overview of proposed sub-

projects, challenges and mitigation and obtain views on anticipated benefits, opportunities and

concerns of the interventions.

2.7.4 Generally, stakeholders expressed broad support and positive attitude towards the program,

as the proposed interventions will address the poor water supply and sanitation, health and

economic challenges faced in the towns. Communities welcomed the opportunity to improve their

living conditions through the developments that will be brought about by the program. The Bank

noted some concerns highlighted during field visits to the sub-project sites, such as (i) the need for

host communities, affected by construction activities due to pipeline routes, to benefit from the

9

water supply interventions, (ii) employment opportunities for the youths during the construction

phase, (iii) the need to recognize multiple demands for water resources and to avoid water-induced

conflicts, and (iv) prompt communication with stakeholders during implementation. These issues

were addressed by the Ministry of Water and Irrigation (MoWI) and the WSBs and will be further

addressed in site specific environmental and social management plans (ESMPs) and overall design

of the program. For instance the jobs to be generated by the program will benefit the youth and the

women foremost.

2.7.5 Consultation and public participation is a continuous process, which began at an early stage

during program preparation and continues as needed. As the program implementation progresses,

the MoWI, the WSBs, WSPs and county authorities will continue to consult with key stakeholders

with respect to improved benefits, suitability of the infrastructure, design and timing of

construction.

2.8 Bank Group Experience, Lessons Reflected in Program Design

2.8.1 As of July 2016, the Bank’s portfolio in the country comprises of 31 active operations -24

public sector projects and 7 private sector operations, with a net total commitment of UA 1.82

billion. The Bank’s investment in the water and sanitation sector accounts for about 16% of the

current public sector portfolio. The current (2015) Country Portfolio Performance Review (CPPR)

assessment ratings returned satisfactory with an overall disbursement rate of 48%. The portfolio

recorded a development objective (DO) rating of 3.584, indicating a stronger likelihood that the

most ongoing operations will meet their development objectives and an implementation progress

(IP) rating of 3.23, implying a satisfactory progress on project implementation. In addition, there

is no project-at-risk in the portfolio and there is neither a problematic project nor a potentially

problematic project in the portfolio. There is no outstanding Project Completion Report (PCR) and

conditions precedent to first disbursement for all ongoing operations in the sector have been

fulfilled.

2.8.2 Bank’s assistance in the water and sanitation sector in Kenya has focused on both

infrastructure and institutional support, and from 1978 to date a total of 14 operations have been

financed of which 4 are ongoing. The support has been aimed at achieving national goals for water

and sanitation as articulated in the relevant national policy documents; namely the Constitution of

Kenya (2010), the Vision 2030 document, and the National Water Services Strategy 2007-2015

(NWSS).

2.8.3 Some of the key lessons learnt from on-going and past interventions in the country by the

Bank and other DPs are taken into account in the design of the program. The main lessons taken

into account are:

Streamlined implementation arrangements: In order to streamline implementation

arrangements, the program selected three (3) WSBs based on capacity assessments to lead the

implementation on behalf of the other five (5) WSBs. In addition, given the delays encountered

in justifying expenses paid from special accounts in the past projects, daily operational costs

will be fully covered by counterpart fund, which allows the program not to use revolving fund

(special account) methods.

Improved readiness: To ensure timely implementation of the program and comply with the

Bank’s Presidential Directive (PD) 02/2105, sub-projects were selected based on the readiness

of studies including ESIA among other criteria. For the seven (7) sub-projects that are still at

preliminary design stage, design and build method of implementation will be introduced to

4 The DO rating ranges from 3.00 to 4.00

10

commence works in the shortest possible period. Advance procurement activities for the

recruitment of design review and supervision consultancies commenced in July 2016.

Members of the program implementing teams (PITs) have been appointed and their profiles

were reviewed during appraisal. The steering committee (SC) for the program has also been

established.

Integrated interventions: The program will ensure water supply and sanitation infrastructure

investments and capacity development of WSPs form part of an integrated package for each

sub-projects. Sanitation interventions incorporate promotion of environmental health and

hygiene practices with a focus on sanitation hotspots. Where applicable, the program will

ensure complementarities with other interventions funded by other DPs and the GoK, especially

in towns where water supply investments have not been matched by corresponding sanitation

facilities for the safe disposal of wastewater. The program will enhance capacity of WSPs to

operate, monitor and deliver improved services. Supports to the WASREB and the WRMA are

also expected to contribute to improved performance of WSPs and sustainable service delivery.

Inclusive service delivery: The WSPs will ensure service provision to underprivileged

households through water kiosks, extensions into informal settlements and social tariff structure

guided by WASREB Tariff Guidelines. Resources will also be set aside for the training of

women and youth on management of water and sanitation businesses arising from the program,

such as management of water kiosks and operation and maintenance of water and sanitation

infrastructure.

2.9 Key Performance Indicators

2.9.1 The key performance indicators for monitoring of the program’s achievements are

identified and captured in the result based logical framework (RBLF). In line with the objective of

the program, outcome indicators include those that capture improved quality of life of people in

target towns such as service coverage and employment opportunities, and enhanced capacity of

WSPs. Output indicators were selected to capture progress of major infrastructure investments and

institutional capacity development activities under the program.

2.9.2 The three (3) PITs will prepare quarterly and annual program progress reports in

collaboration with other WSBs presenting the progress of output indicators. Outcome and output

indicators will also be monitored through the PITs. Indicators will be updated in the

implementation progress report (IPR) and necessary adjustments to the program implementation

will be made as appropriate.

III – PROGRAM FEASIBILITY

3.1 Economic and Financial Performance

Table 12: Key Economic and Financial Figures

FIRR 17.04% and FNPV KES 16,288 million (at 10% base case)

EIRR 33.85% and ENPV KES 73,897 million (at 10% base case) FIRR: Financial Internal Rate of Return, FNPV: Financial Net Present Value

EIRR: Economic Internal Rate of Return, ENPV: Economic Net Present Value

3.1.1 The beneficiary towns are at differing levels of access to water supply and sewerage

services. The financial and economic analysis has taken into account the assumptions contained in

the subsequent paragraphs.

3.1.2 The program will be implemented over an estimated 4 year period and will have a life span

of 20 years from completion of implementation in 2021.

11

3.1.3 The estimated base population with access to piped water of the towns as at 2015 is

projected to be 1.14 million people. This is expected to grow to 2.11 million by 2021 and thereafter

grow at an average of 2.4% per annum.

3.1.4 For purposes of this analysis, a proxy average tariff was adopted, considering the different

sizes of the target towns. Most of the target towns have tariffs approved by the WASREB, and for

the few that do not have approved tariffs, the WASREB is working towards ensuring that the WSPs

are operating with an approved tariff. The analysis assumes a gradual progression from O&M cost

coverage recovery, subsequently reaching full cost recovery to cover investments.

3.1.5 Operating and maintenance costs, including administration overheads, are estimated to be

55% of the revenue generated, a significant improvement on the current performance of most of

the utilities that are relying on subsidies from the county governments to cover electricity bills and

in some cases, wages. It is anticipated, in this analysis, that as the WSPs improve their non-revenue

water (NRW) situation, and through improvements in billing and collection systems, the utilities

can then graduate to full cost recovery status. Furthermore, the analysis assumes that there will be

need for capital reinvestment, amounting to 10% of the capital expenditure after 10 years of

operation to cater for major refurbishments and efficiency enhancements.

3.1.6 The EIRR considers the incremental benefits arising from reduction in health costs due to

reduction in waterborne infections. It also considers the time saving benefit, as women and

children spend less time fetching water. This will lead to an increase in the focus on other income

generating activities, thus improving the livelihoods of the communities.

3.1.7 Sensitivity analysis was undertaken to assess the impact on the FIRR and EIRR of increases

in the capital costs and tariff reductions, and concluded that the reductions in tariffs, have a more

accelerated impact on the viability program than the measured increases in capital costs. This goes

to buttress the proposed interventions in NRW and improvements in billing and collection

efficiencies of the WSP. The sensitivity analysis’ conclusion is that both increases in capital costs

and reductions in tariffs of up to 20% will not result in the interventions being unviable.

3.2 Environmental and Social Impacts

Environmental Impacts

3.2.1 The program has been classified Category 2 in accordance to the African Development

Bank’s Environmental and Social Assessment Procedures (ESAP), which indicates that the

anticipated environmental and social risks associated with the sub-project investments are

temporal, minimal and can be mitigated based on measures elaborated in site specific ESMPs.

Detailed designs for some of the proposed sub-project investments are under development, hence,

the appropriate environmental and social management instrument proposed and validated by the

Bank’s Compliance and Safeguards Division is an ESMF. An ESMF is prepared for Bank

operations that finance multiple small to large scale sub-projects whose location, scope and designs

are not precisely known at the time the Bank appraises and approves the operation. Consequently,

environmental and social assessment and other safeguard measures can be confirmed during

project implementation phase. The ESMF will ensure compliance with the environmental

regulations of the GoK and safeguard requirements of the Bank, and more importantly foster

environmental and social sustainability of the program interventions.

3.2.2 Main environmental and social benefits: The program will generate positive environmental

and socio-economic impacts because of increased access to water and sanitation services. The

water supply and sanitation service investments under the program will include infrastructure for

bulk water supply, wastewater management, upstream activities to ensure sustainability of

investments (catchment management for selected sites, community outreach, water quality and

12

quantity monitoring, etc.) and enhanced downstream productive water uses to ensure investment

performance. Key benefits include: (i) spurred economic and employment opportunities leading

to socio-economic development of the towns; (ii) increased educational enrolment and attendance

for children; (iii) improved household health status; (iv) time savings to engage in other productive

activities (women); (v) enhanced climate resilience status of the population and environment; and

(vi) reduction in the potential for conflicts in water-stressed areas.

3.2.3 Potential adverse environmental and social impacts: The potential adverse environmental

and social impacts of the program vary with the sub-projects, some of which are indicated in the

technical annexes B7. The major impacts envisaged from the interventions include those typically

associated with construction activities such as soil erosion, air and water pollution of surface and

groundwater from construction machinery effluents, interruption of existing infrastructure when

refurbishing or installing pipelines. Additional impacts associated with the sub-projects include

isolated cases of land acquisition for pipeline transmission routes and siting of new facilities, water

abstraction and changes to water outflows from rivers and associated impacts on downstream

human and ecosystem needs, poor location of sewerage facilities that may result in public

nuisance, as well as risk of HIV/AIDs spread due to influx of construction workers in sub-project

areas, among others.

3.2.4 Mitigation: In line with the already prepared ESMF, site specific ESMPs will be prepared

for each sub-project to identify the significance and magnitude of potential impacts as well as the

mitigation measures to minimize, avoid and compensate for all environmental and social risks.

Some of the measures anticipated in the ESMF include re-vegetating disturbed lands in

construction areas, erosion control, ensure environmental flows, implement appropriate system to

manage solid wastes, ensure discharge effluent as per NEMA Water Quality Regulation, and

implementing sustainable catchment management plans to reverse forest cover loss and land

degradation, siting of sewage treatment facilities at least 10 km from town centres, and educating

communities on personal hygiene and environmental sanitation.

Climate Change

3.2.5 According to the Bank’s Climate Safeguards Screening, the program was classified

Category II, indicating the program interventions may be vulnerable to climate risks and require

the application of the Bank’s Adaptation Review and Evaluation Procedures (AREP) tool to

manage those risks. The program is a strategic response to the impacts of climate change and has

been designed to reflect projected climate change risks.

3.2.6 The GoK has shown proactive commitment to tackling the challenges of climate change

and environmental degradation plaguing the water sector. The National Climate Change Response

Strategy (NCCRS) was prepared to focus on developing robust adaptation and mitigation

interventions to address the impacts of climate change in country while the Climate Change Action

Plan (CCAP) 2013-2017 was developed as the government’s instrument to effectively implement

and operationalize the NCCRS for building climate resilience in all sectors, including water and

sanitation. Consistent with this plan, the program proposes to strengthen the climate resilience of

the water supply and sanitation systems of the towns through ensuring technical designs for the

proposed infrastructures reflect the projected climatic changes of the respective towns. In addition,

the program will also explore some of the CCAP’s priority climate adaptation options for the water

sector customized to the needs of each beneficiary town including: (i) riverbank restoration and

catchment protection activities; (ii) capacity building and campaign programs at the sub-

project/town levels to promote water conservation and water-use efficiency as well as water

capture and storage such as rainwater harvesting; (iii) rehabilitation and equipping of WSPs’

laboratory for effective water quality monitoring; and (iv) strengthen and build capacity of the

WRMA for early warning systems, to execute river flow monitoring and to enhance their capacity

for flood, and drought prediction and monitoring in the catchment. The major investments in

13

addressing NRW will ultimately reduce energy costs associated with pumping, and thus contribute

positively to reduction in carbon emissions.

Gender

3.2.7 Women constitute about 50% of the total Kenya population and the GoK recognizes the

importance of their full participation in the development process to facilitate sustainable

development and equity. The Gender Development Index for Kenya for 2014 is 0.913 and places

it amongst countries with a medium gender equality in Human Development Index 5 (HDI)

achievements. The National Gender Policy (2011) aims to mainstream gender concerns in the

national development process in order to improve the social, legal/civic, and economic and cultural

conditions of women, men, girls and boys in Kenya. NWSS commits to ensuring that all Kenya

people are covered by the formal water supply system and that poor Kenyans pay tariffs that they

can afford. The strategy promotes the participation of women in water governance and decision-

making processes and makes requirements for one gender to occupy at least one third of posts at

all levels.

3.2.8 Within the context of the GoK’s strategic gender goals and the MoWI’s ongoing activities

integrating gender concerns, the water sector mainstreams gender consideration in all its

initiatives. This include establishment of the Gender Desk Office in MoWI to coordinate policy

implementation and create awareness on gender in water utilities as well as incorporating gender-

based indicators in performance contracts with utilities as an avenue to ensure integration of gender

concerns. The proposed program is designed to respond to the diverse livelihood needs of both

men and women. Women will especially benefit from increased access to safe, adequate and

uninterrupted water and sanitation service resulting in improved heath and reduced burden and

time spent on collecting water. This is expected to accrue directly from increased access to water

and sanitation services at household level and also indirectly from improved water and sanitation

in health institutions and schools.

3.2.9 It is recognized that the direct employment of women in the water sector is less than their

male counterparts. Hence, the program will target women specifically as administrators and

management of water supply infrastructures. For instance, the program will ensure that at least

50% of the operators of water kiosks are women and they receive training as mechanics to

regularly repair and maintain the water pumps. Additionally, the multi-stakeholder forums

established at each sub-project intervention area and will promote and track the participation of

women. This will help build on and enhance the participation of women in the town water service

governance structure and process such as water user associations.

Social

3.2.10 Kenya’s economic growth has propelled the country towards middle income status with

expansion in financial and communications being behind the accelerated growth. However, the

country is still placed in the low human development category with a HDI of 0.58 in 2014 and

position of 145 out of 188 countries. Poverty remains high (approx. 40% of the population) with

high inequality especially in the arid and semi-arid regions in the north and north east. There has

been significant decline in infant and child mortality rates (from 115/1,000 in 2003 to 52/1,000 in

2014) with maternal mortality rate being 362/10,000. Awareness of AIDS is now universal in

Kenya, however only 56% of women and 66% men have comprehensive knowledge about HIV

and AIDS prevention. Major challenges facing the prevention and treatment of HIV/AIDS are

changing of behavior of the population and affordability of drugs. Malaria and tuberculosis still

constitute major health threats and causes of death.

5 Human Development Index (HDI): A composite index by UNDP measuring average achievement in three (3) basic dimensions

of human development—a long and healthy life, knowledge and a decent standard of living.

14

3.2.11 The proposed program will bring significant social benefits to urban, peri-urban and rural

towns faced with the enormous challenge of meeting growing water and sanitation service

demands. The program will enhance employment and empowerment opportunities that will target

both women and youths within the intervention areas. It is anticipated that 3 categories of job

opportunities will be created through the program: (i) direct jobs comprise mainly temporary jobs

created during construction - over 10,000 jobs are anticipated, (ii) indirect jobs that will help local

supply industries to develop, including manufacturers of pipes, water pumps, chemical companies,

security services, cement manufacturers, and training providers, and (iii) permanent jobs will be

created to support the operation and maintenance of the water supply and wastewater

infrastructures, including water kiosk operators, plumbers, wastewater treatment operators, septic

tank emptying service providers, sewer pipe cleaners and new staff for the WSPs.

3.2.12 In order to maximize the job opportunities and create equitable access and shared

prosperity, the program interventions will target women and youths for skills development and

training on management, and water and sanitation businesses. The program will ensure that at least

30% of trainees in the skill development interventions are women. In addition, 50 apprenticeships

positions attached to eight (8) WSBs will be created (at least 50% women) under the program to

equip and provide youth with exposure to professional level skills.

3.2.13 The provision of water for multiple uses (domestic, irrigation and livestock) in semi-arid

areas of northern Kenya can address potential water-induced conflicts between communities or

between two (2) conflicting uses. Ultimately, water infrastructure provide opportunities for social

cohesion and resilience, and foster inter-cultural connections.

Involuntary Resettlement

3.2.14 Sub-project activities may require land access and/or land acquisition for pipeline

transmission routes and construction of new infrastructures. For the sub-projects, the RAPs will

be prepared once the exact location, scope, and detailed designs of the interventions have been

completed. Preparation of site specific resettlement action plans (RAPs) have been initiated

already in areas where sites have been confirmed.

IV – IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 In 2010, Kenya adopted a new constitution that ushered in a devolved system of

government. This resulted in the creation of 47 counties administered locally through county

governments, and headed by a governor. The country is currently undertaking an alignment of its

laws with the constitution, and at the time of appraisal, the Water Bill was going through

parliamentary debate. The bill, once passed into law, thus succeeding the Water Act 2002, will

articulate the roles and responsibilities of the various players in the sector.

4.1.2 The institutional structure of the water sector at national level has the MoWI at the helm.

The ministry provides strategic policy direction and leadership to the sector. There are eight (8)

WSBs currently existing, which were established under section 51 of the Water Act 2002, whose

mandate is to bring about efficiency, economy and sustainability in the provision of water and

sewerage services in the country. These WSBs are currently responsible for developing water

supply and sanitation infrastructure within their areas of coverage.

4.1.3 The program will be implemented across the country covering 28 towns. The GoK will be

the borrower and the grants recipient, and the MoWI will be responsible for the program. Based

on the capacity assessments of the WSBs and the Bank’s experience gained from implementing

water and sanitation projects in the country, the three (3) WSBs of Tana, Athi and Rift Valley are

15

designated as implementing boards that will implement the program within their board areas and

on behalf of the other five (5) beneficiary WSBs. In order to streamline implementation

arrangements, it was agreed that Athi WSB (AWSB) will lead the implementation of sub-projects

within Athi, Tanathi and Coast WSBs areas of responsibility, while Tana WSB (TWSB) will lead

sub-projects under Tana and Northern WSBs. The Rift Valley WSB (RVWSB) will lead

implementation of sub-projects under Rift Valley, Lake Victoria North and South WSBs. The chief

executive officers of the designated boards will assume full responsibility for the successful

implementation of the program components under their jurisdiction. In line with the prevailing

country system of signing performance contracts, this program will form part of the performance

contracts of the executives and the staff involved in its implementation. Capacity development

support to the WASREB and the WRMA will be channelled through the AWSB.

4.1.4 Each of the designated boards will establish a PIT led by a program coordinator assigned

by the implementing board, with staff assigned from the other five (5) beneficiary WSBs. Each

PIT will be composed of the following personnel: Program Coordinator; Water and Sanitation

Engineer/M&E Expert; Procurement Expert; Accountant, Environmentalist and Social Expert.

The CVs of the staff assigned to the PITs were reviewed and approved by the Bank during

appraisal, thus satisfying program implementation readiness requirements in line with the Bank’s

PD 02/2105. In addition to the PITs, the program will ensure the recruitment of qualified design

review and supervision consulting firms to support the implementation of the program and enhance

the capacities of the PITs.

4.1.5 At national level, a SC has been established and is composed of representatives of the

MoWI, the eight (8) WSBs, WRMA, WASREB and the National Treasury to provide program

oversight, and coordinate implementation. The implementation arrangements are detailed in

Technical Annex B3.

Implementation Schedule

4.1.6 The program will be implemented over a period of 54 months following fulfilment of

conditions for first disbursement, expected before January 2017. Procurement processes of various

services has already commenced in July 2016, while most of works are scheduled to commence in

the third quarter of 2017. Program completion is set for 30 June 2021 and the deadline for last

disbursement will be 30 September 2021.

Procurement Arrangements

4.1.7 Procurement of goods (including non-consultancy services), works and the acquisition of

consulting services, financed by the Bank for the program, will be carried out in accordance with

the “Procurement Policy for Bank Group Funded Operations”, dated October 2015 and following

the provisions stated in the Financing Agreement. Specifically, procurement would be carried out

following Bank Procurement Methods and Procedures, using the relevant Bank Standard or Model

Solicitation Documents, for all contracts since the Borrower Procurement System under the Public

Procurement and Asset Disposal Act of 2015 shall not relied upon for any category of procurement

under the program. Third Party Procurement Methods and Procedures shall not be used.

4.1.8 The assessment of procurement risks at the country, sector, and program levels and of

procurement capacity at the executing agency, were undertaken for the program and are detailed

in the technical annexes B.5, the output of which have informed the decisions on the procurement

regimes being used under the program. The appropriate mitigation measures and costs have been

included in the procurement capacity development action plan under the program.

16

Financial Management and Audit Arrangements

4.1.9 The financial management (FM) of the program will be carried out by the three (3)

designated WSBs of AWSB, TWSB and RVWSB in line with the agreed implementation

arrangements. While the three (3) designated boards have proper structures in place, the appraisal

observed that RVWSB required additional financial management capacity enhancement. The

RVWSB is restructuring its finance department to reduce the weaknesses observed.

4.1.10 The designated boards will be accountable for the program funds and financial reporting,

and will use their respective accounting systems for all the program’s financial transactions. Part

of the program’s funds will be utilized to implement robust Enterprise Resource Planner (ERP)

systems for selected boards in order to eliminate the use of manual accounting systems and

unintegrated reporting software that is prone to errors

4.1.11 The three (3) WSBs’ budgeting processes were found to be adequate and their budgets are

approved by their respective Boards of Directors before submission to the National Treasury,

through the MoWI for inclusion into the national budget. Budget monitoring is done quarterly and

variance reports produced;

4.1.12 The three (3) WSB’s internal audit departments, which report directly to the Boards, will

include this program in their annual work plans. The Bank’s supervision missions, to be carried

out at least twice a year, will review internal audit report of the program, which will inform

decision makers on strengths and weaknesses of internal control systems and adherence with

policies and guidelines.

4.1.13 The annual project financial statements will be prepared in accordance with the

International Public Sector Accounting Standards (IPSAS) annually by 30th September. The

annual financial statements should include: (i) a balance sheet that shows assets and liabilities; (ii)

a statement of receipts and expenditures showing separately Bank’s funding, those of counterpart

and co-financiers if applicable, and cash balances; and (iii) notes to the financial statements

describing the applicable accounting principles in place and a detailed analysis of the main

accounts.

4.1.14 In addition, the program will provide an update on financial performance of the program

as part of the quarterly progress report as required by the Bank not later than 45 days after the end

of the quarter.

4.1.15 The program financial statements will be audited by the Kenya’s Office of the Auditor

General (OAG) using the bank’s audit terms of reference. The audited program financial

statements will be submitted to the Bank within six (6) months after the close of the financial year.

Disbursement Arrangements

4.1.16 On disbursements, the program will utilize the Bank’s direct payment method as explained

in the Bank’s Disbursement Handbook. This method will be used for all payments to contractors

or service providers upon recommendations of their satisfactory performance by the program

authorized consultants and officials. The Bank’s disbursement letter will be issued stipulating key

disbursement procedures and practices.

4.1.17 The program funds will be tax exempt and the WSB’s will ensure that they have sought

and obtained the necessary tax exemptions in time, in order to minimize delays in payments, and

hence program implementation.

17

4.2 Monitoring and Evaluation (M&E)

4.2.1 The program will be monitored using key performance indicators (KPIs) at input and

output levels, and tracks progress towards realizing the outcomes reflected in the program’s RBLF.

The outcome objectives will be measured through monitoring access to services provision,

including water service coverage ratio, level of NRW, number of sewerage connections, sewerage

services coverage and improved quality of sewage effluent. The outputs will mainly be measured

through production capacity for treated water and volume of wastewater removed and treated, as

well as the key facilities constructed. The PITs will be responsible for the overall monitoring and

supervision of the sub-project activities including ESMP implementation. They will produce

periodic progress reports on the status of the various sub-project activities under the program

including financial and procurement status, asset management, stakeholder participation,

safeguards, risks and mitigation measures. A program mid-term review will be carried out in 2019

to assess the validity of the design assumptions and objectives, re-examine the implementation

arrangements and undertake a course correction, if necessary. Once the program approaches

substantial completion, a completion report will be prepared that includes details of the

achievements against the indicators in the RBLF. The Bank shall also conduct regular program

monitoring through supervision missions, while Bank experts at the EARC will regularly support

the program. M&E tools will include a Management Information System (MIS) developed in

collaboration with WASREB, under previous Bank support. The program M&E process will be

linked with the annual water sector review system, in cooperation with other DPs and the MoWI.

Table 13: Key Program Milestones

Timeframe Milestone Monitoring Process/feedback loop

Jul. 2016 Start of advance procurement of a consulting firms for design reviews and supervision of works

Request for expression of interest and request for proposals published

Dec. 2016 Signing and effectiveness Loan agreements signed and declared effective by the Bank

Jan. 2017 Launching Launching workshop organized

Apr. 2017 Start of procurement of a contractors for works

Tender issued

Aug. 2017 Start of works Works contract signed Jun. 2019 Mid-term review Mid-term review undertaken Jun. 2021 Completion of program Program completion report

4.3 Governance

4.3.1 The 2010 Constitution of Kenya ushered in a decentralized government structure, which is

expected to facilitate wider consultation on developmental and governance issues going forward.

In the 2015 Mo Ibrahim Index of African Governance, Kenya scored 58.8 out of 100, and was

ranked 14th out of the 54 countries. The country showed improvements in the areas of

“participation and human rights” and “sustainable economic opportunity” but performed poorly in

the area of “safety and rule of law”. The government continues to fight corruption and since 2015,

the Government adopted the e-procurement system to ensure procurement processes are

transparent, more predictable, and less prone to manipulation. The use of Integrated Financial

Management Information System (IFMIS) has also been made mandatory for all government and

donor funded projects to enhance accountability and ensure project funds are used for intended

purposes.

4.3.2 At sector level, the awaited passage of the Water Bill by the National Assembly and

assenting by the President into law is expected to provide guidance on sector regulation and

governance going forwards. With water services being a devolved function of government,

decisions on service provision will be made at the county level, and that will result in improved

18

service delivery and increased participation of beneficiaries in decision making. The role of

WASREB in the regulation of the sector, provides check and balances on sector players, brings

uniformity and ensures the protection of consumers through ensuring the levying of fair tariffs for

fair services. Existing pro-poor mechanisms in tariff setting will continue to ensure that the poor

and vulnerable members of society will also enjoy water supply, which is enshrined in the Kenyan

Constitution as a human right.

4.3.3 The program will adopt all current and future governance and anti-corruption policies and

guidelines of the country. The proposed support to WASREB, and the technical and financial

audits embedded in the program will also ensure that funds are used for intended purposes, and

with due regard to economy and efficiency. Other measures shall include the Bank’s prior review

and clearance of most project procurement activities, and continuous program supervisions to

follow up closely on implementation progress on site.

4.4 Sustainability

4.4.1 While the program will be implemented by the WSBs, and in line with the institutional

framework and systems in existence in Kenya, operation and maintenance of the infrastructure is

the responsibility of the WSPs (water companies) that fall under the control and responsibility of

the county governments. For financial and operational sustainability of the WSPs, the program

will support the WSPs to build their capacities through training and provision of equipment to

support credit control, billing and collection systems, reduction in and management of NRW, asset

management and good governance. Reduction in NRW and efficiency improvements in water and

sewerage systems will result in improvements in the financial health of the WSPs, enabling them

to reinvest in improvements, increasing connections and staff retention. Furthermore, the

WASREB has in place tariff setting guidelines, which ensure the setting of fair tariffs that also

provide for pro-poor mechanisms.

4.4.2 Under the environmental safeguards, issues of catchment protection will be entrenched in

the program in line with integrated water resource management (IWRM) principles to ensure

catchment and water towers protection, the protection of water sources and mainstreaming

resilience to climate variability and change. In this respect, this program will support the WRMA

to fulfil its mandate to effectively regulate and manage water resources in collaboration with

stakeholders for sustainable development.

4.4.3 Furthermore, the regulation of the sector is of paramount importance to sustainability, and

support to the WASREB has been included in the program. The WASREB’s mandate is to oversee

the implementation of policies and strategies relating to provision of water and sewerage services.

This includes, but is not limited to: issuance of licenses for the provision of water services;

development of guidelines for fixing of tariffs for provision of water services; monitor compliance

with established standards for the design, construction, operation and maintenance of facilities for

water services, preparation of water safety plans among others. The setting of affordable and cost

recovery tariffs is at the heart of the sustainability of WSPs and the sector. This program will

support the WASREB in some of their activities in order to build and enhance their capacity to

regulate the sector.

19

4.5 Risk Management

4.5.1 Table 14 presents the main risks and mitigation measures.

Table 14: Risks and Mitigation Measures

Risk Probability/

Impact Mitigation measures

The potential conflict between counties and water works development agencies

Low probability/ high impact

Counties including WSPs have been involved from the conceptual stage of each sub-project and are supportive of the implementation arrangement. In addition, currently there is no framework in place for counties to borrow to finance infrastructure of the scale under the program. The Bank and WSBs will ensure that counties and WSPs are involved in the program implementation and appropriate capacity development support will be provided under the program for the smooth hand over of assets. In addition, the passage of the Water Bill 2016 into law will further give clarity to demarcation of responsibilities among sector players.

Delays caused due to the resettlements and compensation not being handled timely or properly

Medium probability/ high impact

The risk is mitigated by the fact that negotiations have already started involving county governments. Moreover, awareness exercises directed at the identified PAPs of the sub-projects and sensitization are ongoing as part of the RAP preparation process.

Reduced water resources due to climate change

Medium probability/ high impact

The program will include climate change adaptation support which entails local level climate change impact assessments and preparation of plans, and capacity building for the implementation of plans. Potential support include development of management procedure for WSPs to cope with drought situation and riverbank and catchment protection.

Delays caused by insufficient capacity of the implementation teams

Low probability/ medium impact

Implementation teams were clustered led by the three (3) best performing WSBs. The PIT members have working experience with DPs, most being conversant in the Bank procedures. The Bank will maintain close interaction with the PIT through the EARC and half yearly field supervision missions to provide timely support whenever necessary.

4.6 Knowledge Building

4.6.1 The program will generate critical knowledge for the performance of the water and

sanitation sector in the country, which will build up lessons for the design and management of

similar interventions, to be adapted for replication throughout the country as well as in other

RMCs. The study on impact of water supply and sanitation services on job creation will analyze

the potential of the water and sanitation sector in unlocking sustainable economic growth and in

creating opportunities for the people. Studies for future investments will build on global best

practices and success cases in the country and ensure climate change, gender and any other cross-

cutting issues are mainstreamed.

4.6.2 The IPR, quarterly progress reports, audit, and completion reports will also provide

information on various aspects of the program for further diagnosis. Given that program covers

wide geographic areas and a large number of towns, there is potential to generate useful lessons.

In line with Knowledge Management Strategy 2015-2020, the knowledge obtained will be

captured, documented and shared within the Bank and with other DPs and RMCs.

V – LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal Instrument

5.1.1 The program will be financed by and ADB Loan, ADF Loan and Grant and MIC-TAF

Grant.

20

5.2 Conditions Associated with Bank’s Intervention

A. Condition Precedent to Entry into Force of the Loan & Grant Agreements:

(i) ADB and ADF Loans: The loan agreements shall enter into force subject to fulfilment

by the borrower of the provisions of Section 12.01 of the General Conditions Applicable

to Loan Agreements and Guarantee Agreements of the African Development Bank.

(ii) ADF Grant: The grant protocol of agreement for the ADF Grant shall enter into force

upon signature.

(iii) MIC-TAF: The grant protocol of agreement for the MIC-TAF grant shall enter into

force upon signature.

B. Condition Precedent to First Disbursement of the Loans and Grants

The obligations of the Bank to make the first disbursement of the loans and grants shall be

conditional upon the entry into force of the agreements and the fulfillment by the borrower,

in form and substance satisfactory to the Bank, of the following condition:

(i) Evidence of signature of subsidiary financing agreements between the GoK and each

WSB for the on-lending of the loans and transfer of the grants on terms and conditions

acceptable to the Bank.

C. Other Condition

The borrower shall provide evidence, in form and substance satisfactory:

(i) Evidence of each designated WSB having signed implementation memoranda of

understanding (MOU) with all other WSBs that are part of the cluster.

D. Undertakings

The borrower undertakes and agrees, in form and substance satisfactory to the Bank, to

(i) Ensure that counterpart funds by GoK will be available during program implementation;

(ii) Ensure that all PAPs in accordance with the sub-project’s RAPs, are compensated prior

to the commencement of any construction on affected parts of the program;

(iii) Carry out the program in accordance with: (a) Bank’s rules and procedures; (b) national

legislation; and (c) the recommendations, requirements and procedures set forth in the

ESMF prepared for the program; and

(iv) Deliver to the Bank program quarterly reports, financial and technical audit reports in

form and substance acceptable to the Bank, including the recipient’s implementation of

the ESMF.

5.3 Compliance with Bank Policies

5.3.1 This program complies with applicable Bank policies except the 50% cost sharing principle

laid down in the Policy on Expenditure Eligible for Bank Group Financing. However, through the

justification contained in Appendix 5, management supports the view that the country has

exhibited strong ownership and commitment to the water sector as a whole and to the program

specifically.

VI – RECOMMENDATION

Management recommends that the Board of Directors approve the proposed ADB loan of USD

381.191 million, the ADF loan of UA 5.135 million, the ADF grant of UA 0.512 million and the

MIC-TAF grant of UA 1.200 million to the Republic of Kenya for the purposes and subject to the

conditions stipulated in this report.

I

APPENDICES

Appendix 1: Kenya’s Comparative Socio-Economic Indicators

Year Kenya Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2014 580 30,067 80,386 53,939Total Population (millions) 2014 45.5 1,136.9 6.0 1.3Urban Population (% of Total) 2014 25.2 39.9 47.6 78.7Population Density (per Km²) 2014 78.5 37.8 73.3 24.3GNI per Capita (US $) 2013 1 160 2 310 4 168 39 812Labor Force Participation - Total (%) 2014 67.4 66.1 67.7 72.3Labor Force Participation - Female (%) 2014 46.7 42.8 52.9 65.1Gender -Related Dev elopment Index Value 2007-2013 0.908 0.801 0.506 0.792Human Dev elop. Index (Rank among 187 countries) 2013 147 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2013 43.4 39.6 17.0 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2014 2.7 2.5 1.3 0.4Population Grow th Rate - Urban (%) 2014 4.3 3.4 2.5 0.7Population < 15 y ears (%) 2014 42.0 40.8 28.2 17.0Population >= 65 y ears (%) 2014 2.7 3.5 6.3 16.3Dependency Ratio (%) 2014 82.1 62.4 54.3 50.4Sex Ratio (per 100 female) 2014 99.5 100.4 107.7 105.4Female Population 15-49 y ears (% of total population) 2014 24.3 24.0 26.0 23.0Life Ex pectancy at Birth - Total (y ears) 2014 62.2 59.6 69.2 79.3Life Ex pectancy at Birth - Female (y ears) 2014 64.2 60.7 71.2 82.3Crude Birth Rate (per 1,000) 2014 34.3 34.4 20.9 11.4Crude Death Rate (per 1,000) 2014 8.0 10.2 7.7 9.2Infant Mortality Rate (per 1,000) 2013 47.5 56.7 36.8 5.1Child Mortality Rate (per 1,000) 2013 70.7 84.0 50.2 6.1Total Fertility Rate (per w oman) 2014 4.3 4.6 2.6 1.7Maternal Mortality Rate (per 100,000) 2013 400.0 411.5 230.0 17.0Women Using Contraception (%) 2014 51.3 34.9 62.0 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2012 18.1 46.9 118.1 308.0Nurses (per 100,000 people)* 2004-2012 79.2 133.4 202.9 857.4Births attended by Trained Health Personnel (%) 2009-2012 43.8 50.6 67.7 ...Access to Safe Water (% of Population) 2012 61.7 67.2 87.2 99.2Healthy life ex pectancy at birth (y ears) 2012 53.0 51.3 57 69Access to Sanitation (% of Population) 2012 29.6 38.8 56.9 96.2Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2013 6.0 3.7 1.2 ...Incidence of Tuberculosis (per 100,000) 2013 268.0 246.0 149.0 22.0Child Immunization Against Tuberculosis (%) 2013 79.0 84.3 90.0 ...Child Immunization Against Measles (%) 2013 93.0 76.0 82.7 93.9Underw eight Children (% of children under 5 y ears) 2005-2013 16.4 20.9 17.0 0.9Daily Calorie Supply per Capita 2011 2 189 2 618 2 335 3 503Public Ex penditure on Health (as % of GDP) 2013 1.9 2.7 3.1 7.3

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2011-2014 114.4 106.3 109.4 101.3 Primary School - Female 2011-2014 114.6 102.6 107.6 101.1 Secondary School - Total 2011-2014 67.0 54.3 69.0 100.2 Secondary School - Female 2011-2014 64.5 51.4 67.7 99.9Primary School Female Teaching Staff (% of Total) 2012-2014 48.1 45.1 58.1 81.6Adult literacy Rate - Total (%) 2006-2012 72.2 61.9 80.4 99.2Adult literacy Rate - Male (%) 2006-2012 78.1 70.2 85.9 99.3Adult literacy Rate - Female (%) 2006-2012 66.9 53.5 75.2 99.0Percentage of GDP Spent on Education 2009-2012 6.6 5.3 4.3 5.5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2012 9.8 8.8 11.8 9.2Agricultural Land (as % of land area) 2012 0.5 43.4 43.4 28.9Forest (As % of Land Area) 2012 6.1 22.1 28.3 34.9Per Capita CO2 Emissions (metric tons) 2012 0.3 1.1 3.0 11.6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

KenyaCOMPARATIVE SOCIO-ECONOMIC INDICATORS

June 2016

0

10

20

30

40

50

60

70

80

90

100

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

Infant Mortality Rate( Per 1000 )

Kenya Africa

0

500

1000

1500

2000

2500

20

00

20

05

20

07

20

08

20

09

20

10

20

11

20

12

20

13

GNI Per Capita US $

Kenya Africa

0.0

0.5

1.0

1.5

2.0

2.5

3.0

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Population Growth Rate (%)

Kenya Africa

01020304050607080

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Life Expectancy at Birth (years)

Kenya Africa

II

Appendix 2: Table of AfDB’s Portfolio in the Country

The status and performance of the Bank’s project portfolio in Kenya as in July 2016 is

summarized in the Table below.

Sector Name Long name Loan Number

Company

Name

Approval

Date Into Force

Completion

Date

Loan Amount

(UA Million)

Disb.

Ratio

A. Public SectorAgriculture KENYA-DROUGHT RESILIENCE & SUSTAINABLE LIVELIHOOD PROGRAM IN 2100150028345 ADF 12/19/2012 5/5/2013 12/31/2018 37.4 11.2%

SMALLSCALE IRRIGATION & AGRICULTURE VALUE CHAIN DEVELOPMENT 2000130014530 ADB 11/18/2015 6/15/2016 06/30/2022 28.3 0.0%

5570155000751 GAFSP TF 11/18/2015 2/4/2016 06/30/2022 16.3 0.0%

Agriculture Total 82.1 5.1%

Social AFRICAN VIRTUAL UNIVERSITY SUPPORT PROJECT (PHASE 2) 2100155021616 ADF 12/16/2011 1/24/2012 06/30/2017 10.0 82.0%

EAST AFRICA CENTERS OF EXCELLENCE KENYA 2100150031997 ADF 10/03/2014 7/7/2015 12/31/2019 25.0 1.5%

SUPPORT TO HIGHER EDUCATION SCIENCE AND TECHNOLOGY TO ENHANC 2100150027993 ADF 11/14/2012 2/19/2013 06/30/2018 28.0 46.4%

SUPPORT TO TVET AND TRAINING FOR RELEVANT SKILLS DEVELOPMENT 2100150033295 ADF 07/01/2015 12/10/2015 06/30/2021 41.0 1.2%

Social Total 104.0 21.2%

Power ADF - PRG FOR TURKANA T-LINE 2100140000101 ADF 10/02/2013 12/8/2014 03/15/2019 15.9 0.0%

ADF PRG MENENGAI 2100140000151 ADF 10/22/2014 (blank) 12/31/2020 9.1 #DIV/0!

ETHIOPIA-KENYA ELECTRICITY HIGHWAY(KENYA) 2100150027845 ADF 09/19/2012 3/1/2013 12/31/2018 75.0 25.9%

KENYA - LAST MILE CONNECTIVITY PROJECT 2100150032195 ADF 11/19/2014 10/2/2015 12/31/2019 90.0 17.4%

KENYA - TANZANIA INTERCONNECTION (KENYA) 2100150032846 ADF 02/18/2015 11/13/2015 12/31/2019 27.5 0.0%

MENENGAI GEOTHERMAL DEVELOPMENT PROJECT 2100150026101 ADF 12/14/2011 7/10/2012 12/31/2017 80.0 69.7%

5565130000101 SCF 12/14/2011 7/10/2012 12/31/2017 5.4 56.2%

5565155000401 SCF 12/14/2011 3/12/2012 12/31/2017 12.5 46.1%

NELSAP INTERCONNECTION PROJECT - KENYA 2100150022643 ADF 06/16/2010 7/26/2011 12/31/2017 39.8 53.9%

POWER TRANSMISSION IMPROVEMENT PROJECT 2100150023752 ADF 12/06/2010 12/14/2011 05/30/2017 46.7 77.3%

LAST MILE CONNECTIVITY PROJECT - 2 2000200000152 ADB 06/27/2016 (blank) 12/31/2022 96.5 #DIV/0!

Power Total 498.3 40.0%

Transport MOMBASA -NAIROBI-ADDIS ABABA CORRIDOR PHASE III - KENYA 2100150025546 ADF 11/30/2011 6/29/2012 12/31/2018 120.0 67.2%

MOMBASA-MARIAKANI ROAD HIGHWAY PROJECT 2100150032743 ADF 03/11/2015 10/29/2015 06/30/2021 80.0 0.4%

MOMBASA-NAIROBI-ADDIS CORRIDOR II - KEN 2100150020744 ADF 07/01/2009 4/2/2010 12/31/2016 125.0 81.5%

MULTINATIONAL: ARUSHA-HOLILI/TAVETA-VOI ROAD (KENYA) 2100150028894 ADF 04/16/2013 10/18/2013 12/31/2018 75.0 46.9%

NAIROBI OUTER RING ROAD PROJECT IMPROVEMENT PROJECT 2100150030144 ADF 11/13/2013 5/8/2014 12/31/2018 77.0 22.1%

2100155026117 ADF 11/13/2013 9/26/2014 12/31/2018 0.6 21.0%

SIRARI CORRIDOR ACCESSIBILITY & ROAD SAFETY IMPROVEMENT PROJ 2000130015238 ADB 03/30/2016 (blank) 12/31/2021 163.3 0.0%

5580155000451 EU AITF 03/30/2016 (blank) 12/31/2021 7.9 0.0%

Transport Total 648.9 36.3%

Water Sup/Sanit LAKE VICTORIA WATER AND SANITATION PROGRAM 2100155019967 ADF 12/17/2010 4/4/2011 12/30/2017 73.0 63.2%

NAIROBI RIVER REHABILITAION: SEWERAGE IMPROVEMENT PROJECT 2100150023655 ADF 12/06/2010 12/9/2011 12/31/2016 35.0 80.9%

SMALL MED TOWNS WATER SUPPLY & WASTE WAT 2100150021543 ADF 11/03/2009 5/14/2010 12/30/2016 70.0 71.1%

THWAKE MULTIPURPOSE WATER DEVELOPMENT PROGRAM 2100150029993 ADF 10/30/2013 5/28/2014 12/31/2019 61.7 1.0%

2100155025973 ADF 10/30/2013 1/27/2014 12/31/2019 1.2 6.9%

Water Sup/Sanit Total 240.9 51.8%

Public Total 1,574.2 37.0%

B. Private

Finance EQUITY BANK (KENYA) LIMITED 2000130013731 ADB 11/05/2014 7/3/2015 12/31/2024 106.0 100.0%

IMPERIAL BANK KENY IN RESPECT OF COMMERZBANK RPA 2000130015730 ADB 05/03/2016 (blank) 05/31/2017 0.5 97.0%

2000130015731 ADB 05/03/2016 (blank) 05/31/2017 0.1 0.0%

JAMII BORA KENYA 2000130015735 ADB 06/14/2016 (blank) 02/05/2025 3.6 #DIV/0!

Finance Total 110.2 99.9%

Power LAKE TURKANA WIND POWER EKF 2000130011534 ADB 04/26/2013 3/24/2014 01/19/2028 15.9 33.6%

LAKE TURKANA WIND POWER PROJECT 2000130011533 ADB 04/26/2013 3/24/2014 01/19/2028 91.4 33.6%

LAKE TURKANA WIND POWER PROJECT - SUB DEBT TRANCHE 2000130010533 ADB 04/26/2013 3/24/2014 01/19/2028 4.0 100.0%

THIKA THERMAL POWER PROJECT 2000130008130 ADB 12/07/2011 10/19/2012 06/01/2026 22.3 100.0%

Power Total 133.6 46.7%

Private Total 243.8 70.3%

Grand Total 1,817.9 41.7%

III

Appendix 3: Key Related Projects Financed by the DPs in the Country

Donor Facility/ Funding Source Project Name

Government of Netherlands Kisii Water Supply and Sanitation Project (Bunyunyu Dam)

Government of Sweden Water & Sanitation Programme

Government of Finland Support to Water Resources Management and Water Service Provision

(WSTF)

Government of Belgium

Sabor- Iten Water Supply Project

Sabor- Iten Water Supply Project (phase 2)

Kajiado Water Rural Water Supply

Government of Italy

Rehabilitation of Water and Sanitation-Kiambere

Rehabilitation of Water and Sanitation - Kirandich

Itare Dam Water Supply Project

Mariakani-Kaloleni Water Project

Additional water works under Kenya Italian Debt development

Program (KIDDP) - Kipipiri

Tarbo Laseru Water Project

Habaswein Water Project

Manooni Water Project

Pusol Water Project

Government of Germany

Water Sector Development Programme (Lake Victoria South)

Water Sector Development (Support to Water Services Trust Fund)

Nairobi City Water Distribution Network

Nairobi Satellite Towns and Sanitation Program

Government of France

Complementary Funding for Nairobi Water and Sewage

Complementary Funding for Kisumu Water and Sewerage

Extension of Nairobi Water Supply (Northern Collector)

Government of Japan

Narok Water Project

Rural Water Supply in Baringo County

The Project for Management of Non-Revenue Water in Kenya

The Project on Capacity Development for Effective Management of

Floods

International Development Association

(IDA)

Water & Sanitation Services & Improvement Project (WaSSIP)

Water Security and Climate Resilience

Nairobi Sanitation OBA Project

Kenya Urban Water & Sanitation OBA Fund for Low Income Areas

Project

African Development Bank/ Fund

Lake Victoria Water Supply & Sanitation Programme Phase II

Nairobi Rivers Basin Restoration Programme: Sewerage

improvement project

Small Towns and Rural Water Supply and Sanitation Project

Water Services Support Project

Thwake Multi-purpose Water Development Program Phase I

Arab Bank for Economic Development in

Africa (BADEA)

Rehabilitation of water and sanitation in Oloitokitok Town

Garissa Sewerage Project

OPEC Garissa Sewerage Project

United Nations International Children

Education Fund (UNICEF) WASH Access and Utilisation

International Fund for Agricultural

Development (IFAD) Upper Tana Natural Resources Management Project

Government of Korea Improvement of water supply in Sirisia, Bungoma County

IV

Appendix 4: Map of Kenya and Target Towns

Source of map: http://www.mapsofworld.com/kenya/

: Towns covered by ongoing Small Towns and Rural Water Supply and Sanitation Project

: Propose towns under the proposed program

V

Appendix 5: Justification for financing more than 50% of the Program Cost

through an ADB Loan

Out of the estimated project total cost of USD 452 million (approximately UA 322 million),

the GoK shall contribute USD 61 million (UA 43.4 million) representing 13.48% of the total

costs net of taxes. This is less that the recommended 50% minimum counterpart contribution

as per the Bank’s 2008 Policy on Expenditure Eligible for Bank Group Financing. Further, the

Policy states that the ADB may finance more than 50% of the total project costs on a case-by-

case basis and up to a limit that does not exceed 100%.

The justification sought in this case is premised on the fact that, the GoK only qualified from

1st September 2015 as a Blend Country with access to ADB funds. In line with the transition

framework that stipulates a definite period for countries graduating from ADF only to ADB

only described under the ADF Resource Allocation Guidelines, the GoK would qualify for a

waiver on the 50% requirement criterion. However, pursuant to the ‘Guidance on implementing

the policy on expenditures eligible for Bank Group financing with regards to counterpart

funding’ issued on 10 December 2014, no policy waiver is required, ‘but rather a justification

for Bank financing of a higher proportion of project costs...’

The justification for the reduced Government contribution is qualified on the following

considerations:

Country Commitment to implement its Overall Development Program: Kenya’s development

strategy is the MTP-II (2013-2017). The government is committed to implementing the MTP-

II and continues to both mobilize resources for the purpose and to strengthen the linkage

between the plan and the national budget. The government is also under obligation to provide

15% of its resources to 47 county governments while also providing for all other sectoral

investments. This is provided for in the 2010 constitution which, in its Fourth Schedule, lists

provision of water and sanitation as a function of county governments, with the policy support

from the national government.

Financing Allocated by the Country to Sectors Targeted by Bank Assistance: Government

continues to prioritize Environment protection, Water and Natural Resources - EWNR in its

annual budget allocations as indicated in Table A.1. This is national budget for the sector and

does not include county budget allocations for the sector.

Table A.1: Budget allocation

Description Budget year

2015/16 2016/17

Financing allocated to Environment protection, Water and Natural

Resources - EWNR (billion KES) 55.4 92.9

Share of EWNR in the total budget (%) 3.4% 3.7%

Country Budget Situation and Debt Level: The current budget situation is summarized in Table

A.2. Less than 5% of government spending is dependent on foreign aid. Kenya’s gross domestic

public debt was 24½ percent of GDP at end-September 2015. Domestic debt is issued mostly

in the form of Treasury bonds (75 percent of domestic debt) and Treasury bills (19 percent).

Commercial banks hold half of the domestic debt, with nonbanks holding another 42 percent

and the central bank holding most of the remainder. The domestic debt is of relatively large

size by regional standards. Rollover risks appear moderate. The average maturity of Kenya’s

VI

domestic debt shortened, from 5.8 years in June 2011 to 5.2 years in June 2013 and 4.9 years

in June 2014.

According to the March 2016 debt sustainable analysis (DSA), under the DSA baseline

scenario, all external debt indicators remain well below the policy dependent debt burden

thresholds. In this scenario, the debt burden increases over the next 10 years but remains within

sustainable bounds. The NPV of external public and publicly guaranteed (PPG) debt would

peak at 25 percent of GDP in 2016 and remain around this level through 2025, falling gradually

thereafter. This trajectory remains well below the 50-percent indicative threshold. The NPV of

the debt-to-exports ratio would reach 141 percent in 2016 and ease gradually in following

years, remaining well under an indicative threshold of 200 percent.

Table A.2: Budget situation

Description Budget year

2015/16 likely 2016/17 budgeted

Total Expenditure as % of GDP 25.4 27.4

Domestic Revenues as % of GDP 19.2 20.3

Share of Foreign Loans and Grants in total Budget 7.7 6.9

Share of General Budget Support in total Budget 0 0

Foreign Loans and Grants as % of GDP 2 2

In light of the above considerations, there is therefore a case for the Bank to limit the

government’s counterpart funding requirement for this very important program to the proposed

13.48%. It is expected that this amount will ensure requisite ownership by the authorities and

help expedite the program’s implementation process.

VII

Appendix 6: Climate Screening – Full Results

Scorecard: Water - Supply and Sanitation / Alimentation en eau et assainissement

SAP ID : P-KE-E00-011-02

Project Name: Kenya Towns Sustainable Water Supply and Sanitation Program

SCORES:

Topic Selected Option Score

Asset lifetime / Durée de vie des biens

matériels

The project includes major physical assets with an asset life of >

30 years/

Le projet couvre d’importants biens matériels dont la durée de vie

est supérieure à 30 ans

25

Service continuity / Continuité du

service

All four criteria included to an adequate level/

Tous les quatre critères sont pris en compte à un niveau

convenable

2

Water resources / Ressources en eau There is intermittent or seasonal rainfall distribution with medium

to high evaporation/

Il y a une répartition intermittente ou saisonnière des précipitations

avec une évaporation moyenne à élevée

10

Risk management / Gestion des

risques

There is commitment to develop contingency or response plans/

Un engagement ferme existe pour l’élaboration de plans

d’urgence et de réponse

5

Resource variability / Variabilité des

ressources en eau

During drought periods, supply to all or some sectors has to be

rationed, and flooding incidents can have significant impacts/

Durant les périodes de sécheresse, l’approvisionnement en eau de

tous les secteurs ou de certains secteurs doit être rationné, et les

incidents découlant des inondations peuvent avoir des impacts

importants

10

Competing uses / Utilisations

concurrentes

Existing allocations are sensitive to climate but are maintained by

regulation from upstream and | or enforcement of appropriate

water legislation/

La provision des ressources en eau à différents utilisateurs en place

à l’heure actuelle est sensible au climat mais est maintenue par la

réglementation des pays situés en amont du cours d’eau et/ou par

l’application des lois et règlements appropriés régissant le secteur

de l’eau

5

Additional score - Additional Score Not Specified

Total Score 57 JUSTIFICATIONS:

Topic Justification for Selected Option

Asset lifetime / Durée de vie des biens

matériels

The life time of the assets under the project ranges from 10 to 80 years.

Concrete works last about 10-20 years, pipes 60-70 years mechanical 10-15

years, treatment structures and reservoirs could go higher than 50 years.

Service continuity / Continuité du

service

The Program aims to build the a capacity of regional water service boards and

water service providers to improve the sustainability of water investments,

reduce non-revenue water, billing systems and environmental monitoring

including improving resilience to climate change through provision of early

warning systems.

Water resources / Ressources en eau The Program's sub-project areas exhibit varied vulnerability to climate

variability and change. Generally, Kenya has in recent years had its share of

climate-related impacts: prolonged droughts; frost in some of the productive

agricultural areas; hailstorms; extreme flooding; receding lake levels; drying of

rivers and other wetlands; among others leading to large economic losses and

adversely impacting food security. Other climate change impacts include

widespread disease epidemics, sea-level rise, and depletion of glaciers on

Mount Kenya.

VIII

Risk management / Gestion des

risques

The Program sub-project towns are currently operating below WSS services

demands of residents due to increased population demands and spells of water

scarcity. In extreme shortage of water, the utilities will trigger their rationing

mechanisms along with pricing to trigger efficient use of water resources as

well as provide services from storage facilities. Furthermore, Kenya has action

plans to manage extreme events, including the Water Act, Vision 2030, and

National Climate Change Adaptation Plans. With improvement in economic

development, the country plans to improve the quality and storage capacity and

hence mitigate long term variability.

Resource variability / Variabilité des

ressources en eau

Water Supply may be prone to drought events particularly for the beneficiary

towns dependent on seasonal rivers as sources of water, hence the need to

manage both supply and demand of services. Diversification of water sources

to mitigate variability (ground water and surface water), increasing storage

capacity, catchment protection and exploring new resources are some of the

measures to boost supply. The demand side measures include pricing,

rationing, utilization of improved metering system and awareness creation

which are naturally part of the utility business. The project would build capacity

in all of these areas.

Competing uses / Utilisations

concurrentes

Kenya has established policies and institutions to effectively manage its water

resources. Water abstraction is managed by the Water Resources Management

Authority that employs an integrated water resources management approach

and enforces appropriate regulation for water allocation to various users. The

Program will also support and build capacity of water resources users

association.

Additional score - Additional Score Additional score is not required CATEGORISATION:

Category 1

[EN] Projects may be very vulnerable to climate risk. Requires a detailed

evaluation of climate change risks and adaptation measures. Comprehensive

risk management and adaptation measures should be integrated into the project

design and implementation plans. /

[FR] Les projets peuvent être très vulnérables aux risques liés au changement

climatique. Ceci nécessite par conséquent une analyse détaillée des risques liés

au changement climatique et la mise en place des mesures d’adaptation. La

gestion intégrée des risques et les mesures d’adaptation devraient être

incorporées dans les plans de conception et de mise en œuvre des projets.

Category 2

[EN] Projects may be vulnerable to climate risk. Requires a review of climate

change risks and adaptation measures. Practical risk management and

adaptation options should be integrated into the project design and

implementation plans. /

[FR] Les projets peuvent être vulnérables aux risques liés au changement

climatique. Ceci nécessite par conséquent une analyse des risques liés au

changement climatique et la mise en place des mesures d’adaptation. Les

options pratiques de gestion des risques et d’adaptation devraient être

incorporées dans les plans de conception et de mise en œuvre des projets.

Category 3

[EN] Projects are not vulnerable to climate risk. A voluntary consideration of

low cost risk management and adaptation measures is recommended, but no

further action is required. /

[FR] Les projets ne sont pas vulnérables aux risques liés au changement

climatique. L’analyse facultative de la gestion des risques à faible coût et des

mesures d’adaptation est recommandée, mais sans aucune action

complémentaire.