Upload
others
View
20
Download
0
Embed Size (px)
Citation preview
OFFICIAL USE
1 OFFICIAL USE
REPUBLIC OF KAZAKHSTAN
ALMATY TROLLEYBUS PROJECT
FEASIBILITY AND DUE DILIGENCE STUDY
TERMS OF REFERENCE
1. BACKGROUND
The City of Almaty (the “City”) with population of 1.8 million is the country’s largest and most
important business and financial centre, contributing around 25 per cent of the national GDP. As
most of rapidly growing conglomerates, the city is experiencing deficit of convenient “green”
public transportation aggravated by an increasing number of private cars.
Almaty is the only city in Kazakhstan with trolleybus system. Current trolleybus fleet was
purchased 10 years ago, and it is close to its full depreciation. Subsequently, the City approached
the European Bank for Reconstruction and Development (the “EBRD” or the “Bank”) to finance
renewal of the trolleybus fleet through the purchase of 200 new hybrid trolleybuses and associated
depot equipment (the “Project”). EBRD loan would be provided for the benefit of
Almatyelectrotrans LLP (the “Company” or “AET”).
The City sees the Project as an important measure to improve the environmental situation via
expanding electric transport. The Project will allow the Company to improve passenger services
by replacing the existing deteriorating fleet and providing vehicles for new lines, should the City
decide to expand the trolleybus network. Better public transport services will prevent further
modal shift from public transport to personal cars.
The City’s public transport carries over 450 million passengers annually. The bulk of passenger
traffic (86 per cent) is carried by buses operated by private and municipal companies. Trolleybuses
account for 11 per cent of traffic, and the metro for 3 per cent.
Since 2017, the Almaty City Akimat (the “Akimat”) has subsidised public transport operations
based on the number of serviced passengers. This was a major step to support public transport
that has allowed operators to improve their services and renew the bus fleet. The subsidies are
provided exclusively to the operators with new buses for up to 10 years of operations. In mid-
2019, the Akimat has started to provide subsidies for trolleybus operation as well. Overall the City
allocated KZT 23 billion (EUR 53 million) to support bus services in 2019. This practice is
expected to continue in the future.
The Company is fully owned by the City. It operates 709 buses and 160 trolleybuses carrying
around 180 million passengers per year (40 per cent of the City’s passenger traffic). The Company
operates 51 bus and 8 trolleybus lines, with a total route length of 2,890 and 240 km respectively.
AET has 4 bus and 1 trolleybus depots and 16 operating sub-stations for trolleybuses with a total
capacity of 55,600 kW. The total number of employees is circa 2,500. One fourth of trolleybus
drivers are women. The Company’s fare revenue is mostly collected by the operator of the Onay
e-ticketing system, which retains up to 10 per cent as a service fee.
OFFICIAL USE
2 OFFICIAL USE
The EBRD is currently overseeing implementation of a TC assignment to assist Almaty in
developing a Green City Action Plan. The TC’s implementation should start in [month] 2020 and
will last for 18 months.
In order to prepare the project for financing, the EBRD wishes to appoint a consultant (the
“Consultant”) to perform a feasibility study to determine the scope and viability of the Project,
preliminary costs and provide recommendations on the technical specifications of the trolleybuses
and the depot.
2. THE OBJECTIVE
The Bank needs a comprehensive analysis of the proposed investments in Almaty. The specific
objectives of the assignment are to:
Task Series 1 – Feasibility Study and Due Diligence
The specific objectives of this assignment are to:
a) review existing studies and perform consultations with beneficiary and key
stakeholders;
b) perform demand study, network assessment and network development scenarios
c) analyse trolleybus lines and operational trolleybus fleet requirements, including for
scenarios;
d) assess maintenance facilities (trolleybus depot and spare parts) and determine any
upgrade requirements, including for scenarios;
e) assess trolleybus infrastructure, power supply/substations, including for hybrid
trolleybus systems (additional power off-take) and determine any upgrade
requirements, including for scenarios;
f) perform comparative assessment of trolleybus hybrid (battery) trolleybus and fully
electric bus (as an option) for network extensions and/or optimisation, considering
infrastructure costs, supply/maintenance issues and risks involved;
g) prepare financial and economic cash flows and lifetime assessments of proposed
investment;
h) prepare project implementation and procurement plan, including possible phasing
and/or scenarios;
i) prepare detailed technical requirements for trolleybus fleet and depot, for open
procurement of trolleybuses and depot works in line with the EBRD PP&Rs.
Task Series 2 – Environmental and social assessment
Environmental and social due diligence of the project for full project scope, including notably
trolleybus fleet and depot, in accordance with the Banks Environmental and Social Policy and
Performance Requirements.
Task Series 3 – Recommendation of operational and regulatory support
This task is to assess existing practices, resources and tools and recommend measures to ensure
successful introduction of the new trolleybus fleet onto all company trolleybus lines, and the
corresponding withdrawal of existing bus services.
The specific objectives of this assignment are to:
OFFICIAL USE
3 OFFICIAL USE
a) review of City practices for reporting and licencing of bus operations, requirements and
possible timeline for withdrawal of existing licences, as appropriate
b) assessment of company management and accounting systems, recommendation of MIS
system
c) recommendation of focus actions for post-signing regulatory and operational support (notably,
public service contract and corporate development plan).
In the completion of these tasks, the Consultant will consult with all relevant studies and
stakeholders.
The Consultant will cooperate closely with all teams at the Bank, notably for technical,
environmental, social and financial assessments, and provide any required technical inputs and
advice for completion of their tasks.
3. SCOPE OF WORK
Task Series 1 – Feasibility Study and Due Diligence
1.1 Analysis of urban transport system
The Consultant will provide an overview of City’s public transport market. It will include but
should not be limited to the following:
Overview of public transport market in the City;
Review and analyse the most recent sector strategy, route network of the City;
Overview of regulatory framework and institutional set up, including proposal on the new
tariff system based on E-ticketing;
Review proposed E-ticketing solution and the investment contract with the operator.
Main parameters of services, including number of routes for different modes;
Number of passengers carried and their structure in terms of eligibility to social discounts;
Number of operators and description of their fleets in terms of type, size and age,
Annual turnover in the sector
Suburban service scale.
The Consultant will collect all potentially required data on urban transport system, including
demand and supply levels of public transport service, public transport prioritisation, cost of
services provided and their main driving factors, tariffs structure and passengers, fleet conditions,
etc.
The Consultant will review the current fare revenue collection and enforcement system on
municipal and privately rendered services and any plans for expansion of the system.
Notably, the Consultant shall consult the Almaty Sustainable Transport Strategy 2013-2023 and
other outputs of the Sustainable Transport Project, concluded in 2017.
1.2 Network and demand assessment
The Consultant will document, review and assess current trolleybus route network in terms of level
of service supply, demand and competition with other modes.
OFFICIAL USE
4 OFFICIAL USE
Using outputs and files of the TranCAD demand model developed under the Sustainable Transport
Project, the Consultant shall update the model with latest ridership data from the automated fare
system, along with network, socio-economic and other data, to provide a reference baseline
network and demand model for 2020. The Consultant shall complement available ridership data
with sample occupancy and/or non-paying and concessionary passenger surveys as appropriate
The Consultant shall consider proposed reorganisation of the route network, including notably
simplification of bus network and improvement of main routes (metro, LRT, trolleybus and main
bus routes) and two new interchange terminals and, in consultation with City and along with
complementary modelling and network scenarios, will use this as a basis for proposed trolleybus
network and related scenarios.
The Consultant will carry out a thorough review of the existing public transport services along
trolleybus routes, including modes, quantity of vehicles on each route, service frequency during
peak and off-peak hours, and average capacity of vehicles on the route.
The study of trolleybus routes should take into account the following factors:
number of vehicles required for service and volume of annual vehicle kilometres required;
distance from the existing depot;
demand and required service levels (in terms of frequency);
existing trolleybus infrastructure and its current condition, including old unused
substations;
condition of roads, trolleybus stops etc.
Based on suitable assumptions of ridership attraction and using transport model or other
assessments, as appropriate, the Consultant will provide a forecast of potential number of
passengers for each route, based on a number of network development scenarios, considering
expansions to areas and routes not currently served by trolleybus.
Depending on chosen tariff scenario, the Consultant shall forecast fare revenue with a breakdown
including revenue from full fare paying and concessionary passengers.
The ridership forecast shall include passengers transferred from competing bus routes to each
trolleybus route, based on assumptions for revision of these bus routes, to be cancelled, shortened
or otherwise adjusted. This assessment shall include indicative ridership volume, based on fleet
capacity and available data, and expiry date of existing licence.
1.3. Analysis of the Municipal Trolleybus Operator
The Consultant will carry out an overview of the Company’s performance by documenting and
providing necessary comments covering the following:
Scope of services;
Market position and share;
Organisational structure and number of staff breakdown;
Composition and capacity of company’s management;
Size and structure of the fleet;
Detailed inventory of existing trolleybus infrastructure and facilities, its condition and
remaining useful life;
Condition of the trolleybus infrastructure and facilities including trolleybus traction power
system, bus stops, depot, maintenance and repair facilities, end turning points including
driver rest facilities, if any, administration building, etc
OFFICIAL USE
5 OFFICIAL USE
Revenue structure;
Cost structure and trends
City budget subsidised (current and estimated following transfer of the financing
obligations for privileged passengers to the local level.
The Consultant will provide main key performance indicators and suggest comparable benchmarks
in CIS and the region).
The information above should include at least the last three years’ data.
The Consultant will also provide key performance indicators of the Company for at least the past
three years and indicate comparable benchmarks in CIS and the region. The Consultant will
document the organizational structure of the Company.
1.4. Investment Plan and Cost estimates
The Consultant shall prepare the investment plan for the proposed project comprising fleet and
infrastructure works, with relevant options as appropriate, which would enable the rehabilitation
of the trolleybus system and fleet to a standard allowing at least 10 years of operating life from
end of works, requiring only routine maintenance thereon.
The investment plan shall notably consider:
Trolleybus fleet, considering appropriate size, performance and aesthetics
Upgrade and expansion of trolleybus depot(s)
Modernisation of substations, power infrastructure and catenaries
The Consultant will specify and agree with the Company the main functional and quality
parameters for new trolleybuses to determine a realistic price for new vehicles.
In the context of the envisaged Project scope and initial budget, the Consultant will provide a list
of assumptions to be used for cost estimates. These should be supported to the extent possible with
references to similar projects.
The Consultant shall present a number of investment scenarios for a justified choice to be made
by the Client, which may include inter-alia:
Baseline option, based on existing trolleybus network, with service pattern responsive to
forecast demand
Network expansion scenarios, using of extended trolleybus lines, hybrid (battery)
trolleybus from existing lines and/or fully electric bus (as an option)
Network optimisation, by reduction of trolleybus catenaries in areas of low usage or
requiring critical repair, through extended use of hybrid (battery) trolleybus and ‘in motion’
charging and/or fully electric bus (as an option)
For each scenario, the Consultant will present a breakdown of estimated overall costs of the
planned investments. These will include capital and operational cost for the whole life cycle of
the assets. The costs will be based on the planned volume of services and size of the fleet and will
be linked to variables like energy prices, average monthly net earnings of a driver, depreciation,
taxes, etc.
The Consultant will make a comparative assessment of the investment scenarios and recommend
a scenario for investment, based on whole life cost and risk assessment.
OFFICIAL USE
6 OFFICIAL USE
As part of the investment plan, the Consultant shall propose, in collaboration with the Client, Bank
and relevant parties, the investment components to be allocated under the loan, city budget or
other.
The Consultant shall discuss the foreseen procurement strategy for the purchase of new
trolleybuses, construction of new trolleybus infrastructure, notably depots and rehabilitation of the
existing substations, if any. Based on the best international practices and local circumstances, the
Consultant will propose and document in the report a Procurement Strategy and Plan for all
envisaged project components.
1.5 Key project savings and benchmarks (emissions, energy savings, efficiency etc)
Using the emissions model and parameters provided by EBRD, the Consultant shall perform the
assessment for the expected reduction of emissions and savings as a result of the project
implementation.
Specifically, the consultant should prepare the following calculations:
Expected improvement in farebox ratio
Expected efficiency improvements (reduction of repair and maintenance costs and related
number of staff, per operating trolleybus),
Expected electricity savings to be achieved as a result of the investment programme
implementation (per km of trolleybus service).
Annual reduction in tonnes of CO2, PM and NOx for improved public transport operations
(baseline pre-investment and post-investment projection);
Key project monitoring benchmarks vs baseline (ie CO2 reduction, repair and maintenance
costs per operating trolleybus),
The assessment shall include both improvements in trolleybus efficiency and modal shift transfer
from existing minibus routes and other.
Based on the estimated emissions and energy savings, the Consultant will develop justification for
any investment grant or any alternative co-financing, which may be requested to support
investment.
1.6. Economic Cost-Benefit Analysis and Inputs for Financial Model
The Consultant shall prepare an Economic Internal Rate of Return (EIRR) for the project
presenting the economic costs and benefits from improved trolleybus operations, including
investment and maintenance costs, operating costs savings, time savings, modal shift benefits.
EIRR shall compare a without-project situation with projection of current operating conditions and
funding levels and post-investment situation with improved infrastructure and services.
The Consultant will be involved in preparation of a Financial Model by the Bank. The Consultant
will, inter alia, gather all necessary inputs and provide key assumptions regarding the Company’s
operations for the financial model. The key assumption will be based on the proposed operational
plan and its implementation timetable agreed with the Bank.
The key assumptions for the financial model should cover a period of thirteen years and separately
outline:
Breakdown of the Company’s cost and revenue components;
OFFICIAL USE
7 OFFICIAL USE
Forecast of trolleybus cost on a basis of the planned scope of services, and present vehicle
km price, including likely inflation;
Emissions and CO2 reduction and electricity savings to be achieved as a result of the
investment programme implementation;
Tariff progression;
Fare revenue, compensation for concessionary passengers and subsidy from municipal
budget.
1.7. Justification for the Project approval
Based on the Due Diligence report, the Consultant will:
Provide input, arguments and justification for the project approval by the stakeholders;
Prepare a presentation for the City council and provide input on the application for the
Bank’s and key donor approvals, as well as participate in related meetings.
1.8. Prepare Supply Requirements, including the technical specifications of the new
trolleybus fleet and related depot facilities to be financed
The Consultant shall prepare the Supply Requirements, including the technical specifications, to
be used in the tender for the new trolleybus fleet and related depot facilities to be procured. This
should comply with all relevant EU regulations (including emissions standards, safety, fire safety,
disabled access etc.), and ensure that all specifications are amenable to an open, international
tender using EBRD’s procurement rules and policies.
The trolleybus fleet shall include relevant maintenance provisions, as agreed for the fleet,
including possible extended warranty and/or service agreements and requirements for integration
of relevant ticketing, user information and bus fleet management systems (automated vehicle
location, AVL) as appropriate.
The specifications shall include related studies and layout plans for bus depot facilities, notably
maintenance facilities, and as required for tender.
The Consultant shall also propose appropriate tender evaluation and qualification criteria for
trolleybus fleet and depot.
Task Series 2: Environmental and Social Assessment (ESA)
Task 2.1: Environmental and Social Audit and Assessment
The Consultant will carry out an Environmental and Social Audit and Assessment (“ESA”) in
order to assess the environmental and social aspects of the Project, to be consistent with local
relevant environmental and permitting requirements and the EBRD’s 2014 Environmental and
Social Policy and associated Performance Requirements. The purchase of new bus fleet and
upgrading of the bus depot is a brownfield category B project under the EBRD ESP, requiring an
environmental and social audit of the existing facilities and operations and environmental and
social conditions relevant to the Project and a focussed environmental and social assessment that
is proportionate to the project’s nature, size and location, as well as to the characteristics of the
potential impacts and risks.
The ESA will characterise potential future adverse impacts associated with the project, identify
potential improvement opportunities, and recommend any measures needed to avoid, or where
avoidance is not possible, minimise and mitigate adverse impacts.
OFFICIAL USE
8 OFFICIAL USE
Applicable Requirements:
The E&S Assessment is to be carried out in accordance with:
Applicable local, national and regional requirements, including those related with ESIAs /
EIAs and associated public disclosure and consultation requirements.
The EBRD’s ESP (and the incorporated Performance Requirements (PRs)), and relevant
European Union (EU) directives.
Relevant international conventions and protocols relating to environmental and social
issues, as transposed into national legislation.
The objective of the E&S Assessment is to identify and assess the potentially significant existing
environmental and social risks and future adverse environmental and social impacts and benefits
of the proposed Projects, assess compliance with applicable laws and the EBRD ESP and PRs,
determine the measures needed to prevent or minimise and mitigate the adverse impacts, and
identify potential environmental and social opportunities, including those that would improve the
environmental and social sustainability of the Projects and/or the associated current operations.
The assessment process will be commensurate with, and proportional to, the current E&S risks
and potential future impacts of the Projects. The assessment will cover, in an integrated way, all
relevant direct and indirect environmental and social impacts and issues of the Projects at all
relevant stages of the project cycle (e.g. pre-construction, construction, operation, and
decommissioning or closure and reinstatement).
The Environmental and Social Audit (as defined in Section 3.11.4) is required to assess the current
operations relevant to the Projects in terms of compliance with national legislation as well as
possible historical environmental, health and safety, and social issues.
Specifically, the ESA aims to:
Describe and characterise a relevant environmental and social baseline commensurate with
the risks posed by the current site operations and the Project.
Identify existing and Project-related environmental and social impacts and risks.
Identify if any additional studies will be required to cover relevant aspects in greater detail
(e.g. Road safety, resettlement, retrenchment, etc.; any such work will be commissioned
under separate Terms of Reference).
Assess potential gender aspects and priorities among nearby communities to understand
women’s and men’s concerns;
Identify potential environmental and social opportunities and/or the associated current
operations, including those consistent with the EBRD’s GET principles and criteria;
Perform ex-ante estimation of physical environmental benefits of the Project or
verification of the estimations already performed by the bank in line with EBRD’s GET
Handbook;
Prepare a draft Stakeholder Engagement Plan (SEP), draft Environmental and Social
Action Plan (ESAP) and draft Non-Technical Summary (NTS).
Review of Available Data and Site Visit
The Consultant will identify and review all studies and baseline data available from the Client:
Where available, the local EIA of the Projects;
Any strategic level studies and documents relating to the Project, including any land
acquisition documentation if applicable;
OFFICIAL USE
9 OFFICIAL USE
Project designs.
Data and documentation are in Kazakh. This list is not exhaustive and the Consultant must be
prepared to review, and also request, further documentation that does not appear above.
Following the review of available data, the Consultant will visit the site, to obtain any
supplementary information needed to carry out the E&S Audit requirements and complete the E&S
Assessment.
The data review process will include a simple media search to determine whether any relevant
issues regarding the Project, the City or Company have been reported through the media and to
determine the importance of these through additional verification during the due diligence work.
If no relevant issues are identified through this process the Consultant will include a statement to
this effect in its report.
Following completion of the data review and site visit the Consultant will deliver a summary of
key findings.
Task 2.2: Environmental and Social Audit
The E&S Audit is required to review the current and, to a limited extent, past operational
performance of the Company existing operations and facilities in terms of their compliance with
relevant national environmental laws and regulations and EBRD PRs, including relevant EU
environmental standards and guidelines. The Consultant should provide cross-reference with other
sections of the Feasibility Study, in particular the technical assessment, in case of any overlap.
Key issues to be covered under the E&S Audit may include, but are not limited to:
The Company’s existing environmental and social management systems, policies and
practices, organisational capacity and resources, including description of the number of
personnel; number and percentage of women and men in total staff count as well as across
all levels/categories;
Human Resources and employment policies (relating to e.g. child labour, forced labour,
and non-discrimination, workers’ organisations, contractor management, retrenchment and
employment);
Equal opportunities policies and practices in the Company; assessment of potential
employment opportunities for under-represented groups in the workplace (i.e. women or
men, people with the disabilities, different age groups, ethnic groups, etc.) and
recommendations on what measures need to be made or what policies need to be revised
to ensure equality of opportunity in the Company;
Occupational health and safety (local and national requirements, applicable EU/
international requirement and standards, key health and safety issues, control and major
accident hazards, current health and safety monitoring programme, summary of regulatory
compliance status, summary of health and safety expenditures, emergency response etc.);
Pollution prevention measures implemented by the Company and overall regulatory
compliance with national requirements and pertinent EU standards including applicable
Best Available Techniques. In addition, this assessment will need to review compliance
with good international practice as a benchmark against current operations;
Community health, safety and security as it relates to the Company’s existing operations;
Major hazards assessment and management; existing emergency situation management
plans in the event of an incident or accident;
OFFICIAL USE
10 OFFICIAL USE
Current company policy and practice in relation to avoidance of third party access to
potentially hazardous areas (fences, security, personnel, others);
Management of potentially hazardous works (including excavation works, work in
confined spaces, etc.);
Traffic management;
Contractor management and oversight;
Waste management and waste minimisation;
The Client’s policy and procedures regarding land acquisition (compensation policy,
consultation activities related to land acquisition including grievance management, if
applicable);
The Client’s supply chain (e.g. suppliers of main materials and resources including energy;
presence of women-owned businesses) and identification of relevant environmental, social,
labour and/or reputation issues; and
Current stakeholder identification and engagement practices, including public interaction
and responsiveness to public comments, complaints and questions.
The Consultant will be guided by the relevant requirements of the Bank’s E&S Performance
Requirements. The findings of the E&S Audit should also be considered in the completion of the
PR compliance assessment.
Task 2.3: Environmental and Social Assessment
Project Description & Identification of Relevant Associated Activities & Operations:
The Consultant will prepare a description of the Project including details of any alternatives1
considered for the project and information on associated operations and activities. In accordance
with EBRD PR1, paragraph 9, the Consultant will identify:
Any potentially significant environmental, health and safety, and social issues or risks
associated with relevant other activities or facilities, which are not part of the Project but
which may be directly or indirectly influenced by the Project, exist solely because of the
Project or could present a risk to the Project
Cumulative impacts of the Project in combination with impacts from other relevant past,
present and reasonably foreseeable developments.
Unplanned but predictable activities enabled by the Project that may occur later or at a
different location.
Environmental and social risks associated with the primary supply chains central to the
Project’s core operational functions.
Analysis of Legal Requirements
The Consultant will identify applicable local, regional and national environmental and social laws
and regulatory requirements of the jurisdictions in which the Project operates, including those laws
implementing Kazakhstan’s obligations under international law. The Consultant will analyse
local/national assessment and permitting requirements and the EBRD environmental and social
requirements and compare them within a gap analysis in tabular format.
As required, the Consultant will identify any issues that require legal interpretations for the Bank
to raise with its legal advisors. The Consultant is not required to provide legal opinions. The
Consultant will identify, review and take into consideration any relevant strategic level assessment
documentation.
1 Project alternatives to include: Zero (“no project”) alternative, siting and routing alternatives, infrastructure and traffic
connection alternatives, design alternatives
OFFICIAL USE
11 OFFICIAL USE
Baseline Conditions
Building on the Environmental and Social Audit, the E&S Assessment will include a review of
the aspects of the physical, biological and socio-economic environment likely to be affected by
the proposed Project. The Study shall also identify respective needs and concerns of different
disadvantaged groups and/or those with less voice, such as women, to be addressed in the design,
implementation, and monitoring and evaluation of the project.
The baseline characterisation will include consideration of the inter-relationship between the
relevant factors, as well as the exposure, vulnerability and resilience of these factors to natural and
manmade disaster risks.
Project Assessment
In accordance with the Bank’s ESP (2014), the Consultant will analyse the potential environmental
and social impacts and risks of the Project, as well as opportunities that the Project may provide,
including infrastructure development and other associated facilities, for which the EBRD financing
is being sought.
The E&S Assessment will include a review of the likely effects of the proposed Project on the
physical, biological and socio-economic environment to provide an identification and
characterisation of potential E&S impacts and benefits.
This review will be structured to include all relevant stages of the Project’s life, e.g. construction,
operation and maintenance, closure and decommissioning, and residual E&S impacts. The level
of analysis and reporting will be commensurate with the magnitude of risks and impacts of the
identified issues. If the assessment determines that there are potential risks associated with
resettlement, impacts on livelihoods and expropriation, the Consultant will need to discuss and
agree with the EBRD on the specific requirements to address these risks including the potential
need for a Resettlement Action Plan or Livelihood Restoration Plan.
If an EIA has been prepared under the national requirements, the Consultant will also include a
summary statement of compliance of the national EIA’s process with the EU EIA Directive,
including:
how the project was screened by the national authorities;
which EIA procedure was followed;
how the public participation process was carried out;
potential cumulative impacts and area of influence issues (e.g. raw material sourcing); and
whether any impact on designated or identified nature conservation areas or other sensitive
areas has been identified.
The Consultant will also assess:
the occupational health and safety issues by the Company and its contractors undertaking
the Project related works, including employees and workers exposure to noise, dust,
electricity, physical and other risks during modernization and refurbishment works.
public safety and security issues and the impacts on stakeholders. This should include an
assessment of potential gender-specific health and security issues and impacts (i.e. impacts
during construction and maintenance phase of the service, temporary or permanent
disruption of the service, timetable of the provision of the services, safety concerns of
accessing the services (location sensitivity, and any other security aspects (for example, an
increase of male workers in the area, which may lead to an increase in the risk of
harassment and assaults).
OFFICIAL USE
12 OFFICIAL USE
community health, safety and security risks and benefits, including traffic management and
potential nuisance to local community during both construction and operation of the
Project.
whether or not women would be disproportionally affected by the proposed investment
programme and identify any opportunities to specifically address their needs and concerns
so as to enable them to benefit to an even greater extent from project activities.
the capacity and competency of the company to manage health and safety and road safety
risks, comparing them against good internal practice.
GET Identification and / or estimation or verification of physical environmental impacts
In accordance with the Bank’s GET Handbook, the Consultant will analyse the potential
environmental opportunities of the Project or potential for improvements in the current
operations which can be categorised as:
climate change mitigation (reduction of greenhouse gas emissions)
climate change adaptation (enhancement of climate change resilience)
other environmental benefits (including improved resource efficiency, reduced local
pollution, improved resilience and restoration of ecosystems).
In the proposals made by the Consultant, the general economic feasibility of the projects and/or
project components should be taken into account.
In line with the Bank’s GET Handbook, the Consultant will:
identify project components that meet the GET principles and criteria and are on the
positive lists of activities qualifying for GET or covered by the climate adaptation
approach;
assess the physical environmental benefits of the project and/or project components that
qualify for GET ;
confirm the proportion of GET finance and GET benefits of the project and explaining how
this fits into the GET strategy, as well as examining other contributing factors and total
GET benefits.
Stakeholder engagement
The E&S assessment will include an appropriate stakeholder engagement process in accordance
with EBRD PR 10 to ensure identification of all key E&S risks and impacts of the Project to local
communities. This will include the key concerns the local communities have of the Project.
Mitigation and management of Risks and Impacts
For each identified adverse future impact, issue and/or risk, the Consultant will propose measures
to avoid, minimise, mitigate or compensate for them.
EBRD PR Compliance Assessment
Based on the results of the E&S Assessment, the Consultant shall evaluate the compliance status
of the Project with the EBRD PRs using the format provided in Annex 1 and 2. Note that the
compliance assessment should also take into consideration the findings of the E&S Audit.
Project RAP In case resettlement or displacement is anticipated, the Consultant is expected to
utilize any existing Resettlement and Compensation Framework, to develop a Resettlement Action
Plan and/or Livelihood Restoration Plan to include provisions to compensate women as well as
men for loss of livelihood, address gender issues in planning and executing the resettlement
throughout the whole resettlement process (consultation and participation, resettlement planning,
and resettlement and rehabilitation) in line with PR5.
The Consultant will clearly outline the roles and responsibilities of both the City authorities and
the Company.
OFFICIAL USE
13 OFFICIAL USE
Project ESAP
The Consultant shall develop a comprehensive ESAP to address gaps and issues identified during
the Project appraisal. The ESAP should be based on the Gap Analysis and will be presented and
sequenced by PRs. Actions identified must be numbered, clearly defined, indicate a time frame for
completion (with specific reference to those actions that must be completed before financial close
if appropriate) and a responsible party specified. Further, each item must contain a description of
the factors that will be used to determine when the identified action is closed/completed. The
Consultant should also inform the City and Company about any material budget implications of
ESAP items (although this information may not be required in the public domain). A guide for
presenting the ESAP is provided in Annex 3. The ESAP will clearly outline how the
responsibilities for any of the actions/measures will be cascaded down from the City to Company,
i.e.it will clearly indicate the transfer of obligations from the City to the Company.
Project Stakeholder Engagement Plan
The Consultant shall prepare a draft Stakeholder Engagement Plan (“SEP”) in English, and
Bosnian in compliance with the PR10. The scope and level of detail of the SEP will be scaled to
fit the needs of the Project and the objectives of EBRD PR10. Following review of the Project
operations, the Consultant will propose a format best suited for the specific Project needs.
Guidance for the contents of an SEP is provided in Annex 4 of the E&S guidance pack. The SEP
should be developed in consultation with the relevant Client and incorporate stakeholder
mapping results
Project Non-Technical Summary
The Consultant will prepare, in consultation with the Client, a concise, over-arching, standalone
Non-Technical Summary (“NTS”) in English, and Bosnian. The NTS will be written in non-
technical language and the Consultant will ensure that the NTS can be used to demonstrate
compliance with the EBRD requirements, and provide confirmation that the documents are ready
for public disclosure.
An indicative list of issues for the NTS is given in Annex 5 of the E&S guidance pack.
Task Series 3: Recommendation of operational and regulatory support
This task is to assess existing practices, resources and tools and recommend measures to ensure
successful introduction of the new trolleybus fleet onto all company trolleybus lines, and the
corresponding withdrawal of existing bus services.
Task 3.1: Review of City practices for reporting and licencing of bus operation
The Consultant shall review the requirements and timeline for cancellation and/or transfer of
ongoing licences, as a requirement for the introduction of new trolleybus services and capturing
of ridership levels.
The Consultant will review existing practices, including the following (pertaining in particular to
bus routes affected by the project):
Division of rights and responsibilities between city and bus operators
Bus service contract provisions, regulation and control
Procedures for cancellation, withdrawal and/or transfer of licences
Level and quality of city operational oversight, including data recorded in city database or
elsewhere
Requirements for technical/financial reporting of operators
OFFICIAL USE
14 OFFICIAL USE
The review shall include legal/regulatory review to back up existing practices, notably including
contracting, enforcement and fare collection, and possible future arrangements.
The Consultant shall consult with a sample of existing operators, as part of this assessment.
Task 3.2: Assessment of company management systems, recommendation of MIS system
The Consultant shall assess Company system and methods for management and accounting, to
ensure compatibility with monitoring and reporting requirements under a PSC. This shall include
the following:
Review and analyse the Company’s existing management information systems (“MIS”) and
procedures, including the extent of automation and computerisation, identifying any
immediate shortcomings and development needs.
Recommend a computer-based MIS that would register, monitor and provide key management
information across all areas of the Client’s activities, considering, in particular that the system
can produce such financial and other information which is required for reporting to third parties
(in particular reporting to the EBRD as will be defined in the financing agreements), public
authorities and the general public.
Recommend a suitable MIS system, including hardware and software components, with list of
functional requirements and budget breakdown, for loan or TC funding or local budget, as
appropriate
Task 3.3: Recommendation of focus actions for post-signing regulatory and operational
support
Based on practices for existing bus licences, the Consultant shall assess a suitable timetable for
any required withdrawal or transfer of relevant route licences, on or after the commencement of
new trolleybus services. This programme shall be coherent with ridership scenarios, developed
under task 1.1.
The Consultant shall indicate an action plan for any required measures, including regulatory,
contractual, social or training-related, to accompany the timetable and ensure effective withdrawal
of existing licences. Notably, the Consultant shall consider a possible staff transfer plan (notably
drivers and controllers) to the new trolleybus fleet, as relevant.
The Consultant shall recommend those actions, considered important for the effectiveness of
future operations, notably the following:
Implementation of public service contract (PSC) to provide improved transparency in operator
payments and service obligations
Corporate development plan for Company, to ensure improved financial and operational
performance for new fleet operation and reporting under the PSC
Regulatory and planning support to City, to plan the public transport network, support
improved.
For relevant actions, the Consultant shall provide an outline scope/terms of reference, timeline,
resources and budget for consideration of the Bank.
OFFICIAL USE
15 OFFICIAL USE
4. IMPLEMENTATION ARRANGEMENTS AND DELIVERABLES
The duration of the entire assignment is expected to be 20 weeks in total, of which
8 weeks for draft feasibility and due diligence report (task series 1, tasks 1.1-1.6 and task
series 3)
10 weeks for draft E&S due diligence assignment (task series 2)
14 weeks for draft technical specifications (task 1.7)
20 weeks for final technical specification and all deliverables
The Consultant shall mobilise at least the following missions to Almaty:
Project inception for data collection and consultations with beneficiary and stakeholders
Presentation of draft due diligence report
Discussion of draft technical specifications
The Consultant will report principally to the Bank and to the Company, as required.
The Consultant will supply all necessary computer hardware and software required to deliver the
services, together with the necessary office equipment.
The Consultant will be responsible for arranging their own transport, accommodation,
communications, materials, printing and report preparation etc. (the Consultant will be responsible
for the cost of connection time for calls/faxes/internet).
The Company will provide serviced and furnished office accommodation for the Consultant, plus
suitable office space for meetings, together with access to all relevant information, reports, maps,
studies, legal documents etc., at no cost to the Consultant.
All reports should be produced in English and Russian language, with 3 copies in English and 6
copies in Russian.
The Consultant will provide soft copies of all project deliverables to the EBRD using Microsoft-
Office where appropriate, including source files (XLS spreadsheets, DOC reports).
The Consultant shall keep the Bank’s Team in Almaty and London fully updated of the progress
of the assignment.
The Consultant shall provide the following reports on the activities performed. Timelines relate to
reports in draft version in English language, except where indicated.
Document (in English language and in electronic format) Deadline
Feasibility and Due Diligence Study (tasks 1.1-1.7, task series 3)
Inception report M+2 weeks
Draft report on Due Diligence Study M+8 weeks
Final report on Due Diligence Study M+10 weeks
E&S Due Diligence Study (task series 2)
Draft E&S documents (RAP, SAP, ESAP, NTS.) M+10 weeks
Final reports M+12 weeks
Technical specifications (task 1.8)
Draft technical specifications M + 14 weeks
Final technical specifications M + 20 weeks
M = commencement date of the assignment
OFFICIAL USE
16 OFFICIAL USE
5. CONSULTANT PROFILE
It is estimated that the Consultant shall mobilise the following experts:
Senior public transport specialist with at least 15 years of experience in planning and
operations of urban transport systems, including trolleybuses and related infrastructure;
Senior trolleybus specialist with at least 7 years of experience in trolleybus fleet
management, maintenance and operations, including trolleybuses and hybrid (battery)
trolleybuses;
Economist/Modeller with preferably 7 years of experience in economic and transport
modelling assessments, including urban transport studies and modelling software.
Familiarity with modelling software including TransCAD is required.
Finance Expert with preferably 7 years of relevant professional experience in financial and
economic assessment, preferably in an urban transport or municipal services. The expert
should be familiar with selection and use of management information systems (MIS)
Electrical Expert with at least 7 years of experience in power systems and including
trolleybus catenary and power infrastructure;
Building Specialist, with preferably 7 years of relevant professional experience in building
and/or engineering, preferably with experience in depots or transport logistics parks and
good knowledge of local building regulations
Environmental and Social Experts - with experience in ESIAs and E&S due diligence,
health & safety, stakeholder engagement, public consultation and disclosure in the local
context, gender and inclusion expertise, and/or resettlement expertise, in urban transport
sector with experience of similar assignments and with recent track record in the region.
Such experts need to demonstrate knowledge and experience of typical lender/IFI E&S
standards and their implementation. Senior experts need to have at least 8 years’ relevant
experience and appropriate academic qualifications.
Consultants should demonstrate previous project experience in similar regions. Fluency in Russian
and experience in Kazakhstan or Central Asian region would be an advantage. It is mandatory for
a Senior public transport specialist or Senior trolleybus specialist to speak Russian.
OFFICIAL USE
17 OFFICIAL USE
ANNEX 1
E&S GUIDANCE 1
SAMPLE REPORT FORMAT FOR AN E&S AUDIT AND ASSESSMENT REPORT (BROWNFIELD)
Note: The following is an indicative list of issues for possible inclusion in an E&S Audit and
Assessment report for a Brownfield Project. The Consultant is expected to use its professional
judgement to determine what issues (either listed below or additional) are relevant to the Project.
Issues which are not relevant to this project should be covered by a short statement that they have
been considered but do not apply in this case.
Executive Summary
A concise summary description of the Project, its rationale, the existing operations and overall
setting, significant environmental and social impacts, recommended mitigation and enhancement
measures, monitoring proposals, and the extent of the Client’s commitment to these
recommendations and proposals.
1 | Project Description
Precise description of the Project within its geographical, environmental and socio-economic
context. This should include information on whether and how the Project is part of a wider
development plan/programme. A systematic comparison of feasible alternatives to the project in
terms of location, project technology or design in terms of potential environmental and social
impacts. This should include the ‘do-nothing’ option.
2 | Legal Requirements
Outline of the policy, legal and administrative context of the ESIA summarising the
environmental and social and project approval requirements of the Bank, co-financiers and
applicable regional/global conventions or agreements. The timeframe for public consultation,
project appraisal and implementation should be outlined.
Applicable IFI Environmental and Social Assessment procedures;
Host Country, Regional and International Regulatory Framework, standards and
guidelines, treaties applicable;
Approach to benchmarking.
3 | Baseline Conditions
A description of relevant aspects of the physical and natural environment and socio-economic
conditions in areas affected by the existing operations and the Project to include, inter alia:
Air emissions and noise;
Biological and ecological resources (fauna, flora, biodiversity, protected species, critical
habitats, ecosystems);
Climatic factors and climate change (e.g. greenhouse gas emissions, including from land
use, land use change and forestry, and sectors of population more affected by climate
change);
Cultural heritage, including architectural and archaeological heritage;
Geomorphology and geology;
Land (past and current use, permanent or temporary acquisition);
Land use patterns;
Landscape and visual aspects;
Material assets;
Mitigation potential and impacts relevant to adaptation;
OFFICIAL USE
18 OFFICIAL USE
Other social issues: community, settlement patterns and residential properties, vulnerable
groups;
Public and / or site specific transportation system;
Socio-economic status of the population (disaggregated by gender, age, ethnicity, and
other social characteristics);
Soil (organic matter, erosion, compaction, sealing);
Stakeholder engagement practices;
Water (accessibility, quantity and quality, surface and groundwater) and waste water
management;
Worker and public health and safety.
4 | Potential Impacts
Identification of the potential environmental and social impacts that could be associated with the
existing operations and the Project, including those of an indirect and cumulative nature. Impacts
which are unlikely to arise or be insignificant should be recorded, together with the rationale for
why they are considered to be unlikely or insignificant. Potential impacts must be considered at
the following levels:
Local impacts;
National impacts;
Regional/Global impacts.
5 | Characterisation of Impacts and Opportunities
Identification and characterisation of positive and negative environmental and social impacts in
terms of magnitude, significance, reversibility, extent and duration. The possibility for cumulative
impacts is to be considered. Quantitative data must be employed to the greatest extent possible.
The chapter should also identify opportunities for environmental and social enhancement and
identify key uncertainties and data gaps. Both the existing operations and the following Project
stages must be considered in this evaluation where appropriate:
Construction phase;
Operation and maintenance;
Closure and decommissioning;
Residual environmental and social impacts.
6 | Management of Impacts and Issues
An outline of the feasible cost-effective measures to avoid, minimise, mitigate or compensate for
environmental and social impacts to acceptable levels and address other environmental and social
issues; such as the need for worker health and safety improvements, inter-agency coordination,
community involvement, institutional strengthening or training within the executing agency/
governmental agencies/Client or at the community level. Additionally, an outline of any measures
that would enhance environmental and social aspects within the area affected by the Project and
the existing operations and characterisation of the nature of any residual environmental and social
impacts or issues that have not been addressed. A description of the financial provisions for
potential risks (for example escrow accounts and insurance cover to provide for inter alia
abandonment and decommissioning, site remediation and oil spills and other emergencies). Both
the existing operations and the following Project stages must be considered where appropriate:
Construction;
Implementation and maintenance;
Closure and decommissioning;
Residual environmental and social impacts.
OFFICIAL USE
19 OFFICIAL USE
7 | Monitoring and Supervision
A description of how environmental and social impacts and issues will be monitored and managed
in practice; including an indication of how the Project will be supervised by lenders and
governmental agencies. Estimates should be provided for capital expenditure and operation and
maintenance costs where possible. The following stages must be considered where appropriate:
Construction;
Implementation and maintenance;
Closure and decommissioning.
8 | Mitigation and Management Plan
A record of all measures required to address environmental and social impacts and issues as well
as monitoring and supervisory activities associated with these should be consolidated in tabular
form. This should also indicate institutional responsibilities, timeframes and associated costs.
Appendices
Names of those responsible for preparing the E&S Assessment
References and sources of information
Records of public meetings and consultations held
Supporting technical data
EBRD Compliance Summary Table (see E&S Guidance 2)
OFFICIAL USE
20 OFFICIAL USE
ANNEX 2
ENVIRONMENTAL AND SOCIAL ASSESSMENT: EBRD COMPLIANCE SUMMARY TABLE
Introduction
The Compliance Summary provides a systematic review of project compliance with the EBRD Environmental and Social Policy, as defined through
the applicable Performance Requirements (PRs). Scope of compliance is all PRs applicable to non-FI projects. The review is intended to provide a
baseline against which to judge future performance of projects through the annual environmental and social reporting process.
Between 2 and 10 indicators are identified for each of the applicable PRs: 1, 2, 3, 4, 5, 6, 7, 8 and 10.
Guidance
For all PRs (Indicators with whole number references) provide a summary of overall compliance with the PR. Justification for any derogation from a
PR should be summarised and supporting documents referenced.
For each indicator within a PR, please complete the 3 steps below:
1. Decide whether the indicator is applicable. For Category A and B projects the starting point is that all indicators are applicable unless the
project has no significant aspects relevant to the indicator (i.e. no risks), in which case the indicator should be scored "NA" and a brief summary
of the reason given. For Category C projects the starting point is all indicators are NA unless the project has a significant aspect relevant to the
indicator (i.e. there is a material risk).
2. Decide whether an opinion is possible. If not (for example if the indicator will apply, but it is too early in the project) score as "NOP" and
provide a brief summary of why. Where lack of opinion represents a material omission to the review refer to where this is addressed in the
report and summarise any recommendations.
OFFICIAL USE
21 OFFICIAL USE
3. Score the indicator as follows and provide brief justification.
EC Exceeding Compliance: The project has gone beyond the expectations of EBRD’s PR requirements. EBRD should be able to use projects rated EC as a role model for positive Environmental and Social effects.
FC Fully Compliant: The project is fully in compliance with EBRD’s requirements, and EU and local environmental, health and safety policies and guidelines.
PC Partial Compliance: The project is not in full compliance with EBRD’s requirements, but has systems, processes or mitigation measure in place which are working towards addressing the deficiencies.
MN Material Non-compliance: The project is not in material compliance with EBRD’s requirements, and the systems, processes and mitigation measures in place are not working towards addressing the deficiencies.
4. Comments/Issues: Provide a brief commentary (one or two sentences) on the relevance of this requirement for the project and an explanation
of the chosen score.
5. Actions Required: Where applicable, briefly describe any actions required by the client to achieve full compliance with each requirement.
Where a relevant action is included in the ESAP for this project, please provide a reference to the ESAP.
6. PR Summary: Provide an overall summary against the PR, using the above compliance definitions with supporting commentary. In some
cases it may be sufficient to address a PR at summary level only, depending on Stage 1 above.
Note: The Material Non-compliance score (at both Indicator and PR level) has significant implications for Project approval and requires particular care. In judging
whether the measures sufficiently address deficiencies the consultant should consider in a structured way both the level of residual (post-approval) risk and the level
of confidence that the Project can successfully bring the issue into compliance with the Policy through the ESAP. The table below illustrates the approach to be taken.
Risk
High PC MN MN
Medium PC PC MN
Low FC PC PC High Medium Low Confidence
OFFICIAL USE
22 OFFICIAL USE
KPI Ref.
Performance Requirement Score Comments/ Issues Actions Required ESAP Ref.
1 Assessment and Management of Environmental and Social Impacts and Issues
Summary:
1.1 Environmental and Social Assessment
1.2 Environmental and Social Management Systems
1.3 Environmental and Social Policy2
1.4 Environmental and Social Management Plan
1.5 Organisational Capacity and Commitment
1.6 Supply Chain Management
1.7 Project Monitoring and Reporting3
2 Labour and Working Conditions
Summary:
2.1 Human Resource Policies and Working Relationships
2.2 Child and Forced Labour
2.3 Non-Discrimination and Equal Opportunity
2.4 Workers Organizations
2 Where the project represents a substantial extension to the client activities, confirm that Policy and supporting management systems and plans are appropriate for the new activities. 3 At appraisal stage there will be limited information. Compliance assessment should address specific plans for monitoring and reporting (against for example ESAP requirements)
and also consider whether there is evidence of weak monitoring/reporting by client on other relevant projects - which may reduce confidence in future performance.
OFFICIAL USE
23 OFFICIAL USE
KPI Ref.
Performance Requirement Score Comments/ Issues Actions Required ESAP Ref.
2.5 Wages, benefits, and conditions of work and accommodation
2.6 Retrenchment4
2.7 Grievance Mechanism
2.8 Non-Employee Workers
2.9 Supply Chain
2.10 Security Personnel Requirements
3 Resource Efficiency and Pollution Prevention and Control NB. Appraisal should carefully consider (and state) what regulations or standards have been applied to compliance assessment (eg EU, National, Sector Best Practice). Assessments should address consideration of the performance of alternative techniques.
Summary:
3.1 Resource Efficiency
3.2 Pollution Prevention and Control - Air emissions
3.3 Pollution Prevention and Control - Waste waters
3.4 Greenhouse Gases5
3.5 Water
3.6 Wastes
3.7 Hazardous Substances and Materials
4 Will not be applicable to many projects at appraisal stage. However evidence, within the last 3 years of client approach to retrenchment which is not compatible with the Policy
should be taken into consideration. 5 Particular attention should be given to client demonstration of consideration of alternatives. Projects expected annually to produce more than 25,000 tonnes of Co2 equivalent
should provide an emission inventory and plans for annual reporting.
OFFICIAL USE
24 OFFICIAL USE
KPI Ref.
Performance Requirement Score Comments/ Issues Actions Required ESAP Ref.
4 Health and Safety
Summary:
4.1 Occupational Health and Safety
4.2 Community Health and Safety
4.3 Infrastructure, Building, and Equipment Design and Safety
4.4 Hazardous Materials Safety
4.5 Product and Services Safety
4.6 Traffic and Road Safety
4.7 Natural Hazards
4.8 Exposure to Disease
4.9 Emergency Preparedness and Response
5 Land Acquisition, Involuntary Resettlement and Economic Displacement
Summary:
5.1 Avoid or minimise displacement
5.2 Consultation
5.3 Compensation for displaced persons
5.4 Grievance mechanism
5.5 RAP/LRP documentation
5.6 RAP/LRP implementation
5.7 Monitoring
OFFICIAL USE
25 OFFICIAL USE
KPI Ref.
Performance Requirement Score Comments/ Issues Actions Required ESAP Ref.
6 Biodiversity and Living Natural Resources
Summary:
6.1 Assessment of Biodiversity and Living Natural Resources
6.2 Conservation of Biodiversity
6.3 Sustainable Management of Living Natural Resources
7 Indigenous People
Summary:
7.1 Indigenous People Assessment
7.2 Adverse Effects Avoidance and Indigenous Peoples Development Plan
7.3 Information Disclosure, Meaningful Consultation and Informed Participation
7.4 Grievance Mechanism and Prevention of Ethnically Based Discrimination
7.5 Compensation and Benefit-Sharing
7.6 Impacts/Relocation on Traditional or Customary Lands and Cultural Heritage
OFFICIAL USE
26 OFFICIAL USE
KPI Ref.
Performance Requirement Score Comments/ Issues Actions Required ESAP Ref.
8 Cultural Heritage
Summary:
8.1 Assessment and Management of Impacts on Cultural Heritage
8.2 Consultation with affected communities and other stakeholders
8.3 Project use of Cultural Heritage
10 Information Disclosure and Stakeholder Engagement
Summary:
10.1 Stakeholder Engagement Plan
10.2 Operational Grievance Mechanism
Overall Compliance
National Environmental, Social, Health and Safety Requirements
EU Environmental, Social, Health and Safety Requirements
OFFICIAL USE
27 OFFICIAL USE
ANNEX 3
ENVIRONMENTAL AND SOCIAL ACTION PLAN TEMPLATE
No. Action
Environmental & Social Risks
(Liability/Benefits)
Requirement
(Legislative, EBRD PR, Best
Practice)
Resources, Investment Needs,
Responsibility Timetable
Target and Evaluation Criteria
for Successful Implementation
Status
PR1 Assessment and Management of Environmental and Social Impacts and Issues
1.1 Develop and implement an EMS
Optimisation of environmental management though a formalised system. Provide resources for training and monitoring of emissions
EBRD PR1
Voluntary and best practice
Own resources, external consultants
Cost
Assign responsibilities
20xx Develop and implement an EMS
Attain ISO 14001 or equivalent certification
Annual EHS Report to the Bank
PR2 Labour and Working Conditions
2.1
PR3 Resource Efficiency and Pollution Prevention and Control
3.1
PR4 Health and Safety
4.1
PR5 Land Acquisition, Involuntary Resettlement and Economic Displacement
5.1
OFFICIAL USE
28 OFFICIAL USE
No. Action
Environmental & Social Risks
(Liability/Benefits)
Requirement
(Legislative, EBRD PR, Best
Practice)
Resources, Investment Needs,
Responsibility Timetable
Target and Evaluation Criteria
for Successful Implementation
Status
PR6 Biodiversity and Living Natural Resources
6.1
PR7 Indigenous People
7.1
PR8 Cultural Heritage
8.1
PR10 Information Disclosure and Stakeholder Engagement
10.1
OFFICIAL USE
29 OFFICIAL USE
ANNEX 4
GUIDANCE FOR A STAKEHOLDER ENGAGEMENT PLAN
The following is an indicative list of issues for possible inclusion in a Stakeholder
Engagement Plan. The Consultant is expected to use its professional judgement to
determine what issues (either listed below or additional) are relevant to the Project.
A Stakeholder Engagement Plan will need to:
Briefly identify the Project location and areas subject to impact (e.g., list of
communities)
Record what the Project is legally required to do regarding disclosure and
consultation
Identify all stakeholders, including stakeholder maps (if relevant)
Identify any specific groups who might be considered vulnerable or need more
support in the consultation process, e.g. because of their level of literacy,
gender, socio-economic level, ethnicity/language, or location (e.g., proximity
of the project to school, hospital, etc.). For each identified group, specify how
meaningful consultation will be undertaken
Report on any previous consultation and disclosure activities
Define which documents will be released, including a schedule, and in what
language(s)
Define where documents will be available (physical and online addresses) ,
e.g. provide names of specific newspapers, bulletin board locations, etc.
Define how people will be notified of the document availability
State the beginning and end dates of the consultation
Provide a table or list of meetings, activities or opportunities for comment. If
locations/dates are not yet known, state how people will be informed of the
dates
State who/where should comments be sent to, what will happen to them and
how people will be advised of the outcomes
Define how grievances will be handled (including a specific public grievance
process)
Define the monitoring and reporting activities for the stakeholder engagement
process
Define the responsibilities for delivering the stakeholder engagement process
The SEP should be concise and not exceed 15 pages in length, excluding annexes.
Please also see guidance note:
http://www.ebrd.com/downloads/about/sustainability/grievance-mechanism.pdf
OFFICIAL USE
30 OFFICIAL USE
ANNEX 5
INDICATIVE LIST OF ISSUES FOR A NON-TECHNICAL SUMMARY
The following is an indicative list of issues for possible inclusion in a Non-Technical
Summary. The Consultant is expected to use its professional judgement to determine
what issues (either listed below or additional) are relevant to the Project.
Non-Technical Executive Summary
1 | Project Description
A concise and comprehensive description of the Project
Proposed works and subsequent maintenance/operation
Scheme map and typical cross sections
2 | Background
Rationale of the Project, the need for the scheme and scheme objectives
Legal aspects and compliance with relevant environmental and social laws
Current environmental and social situation and considerations
History of the Project development and planning; including an outline of the
main alternatives that were studied, their environmental and social impacts,
and the reasons for making the final selection
3 | Process
ESIA process carried out and integration with design
A statement of the national EIA process’s compliance with the EU EIA
Directive
Public consultations and disclosure and dealing with objections
4 | Environmental Benefits, Adverse Impacts and Mitigation Measures
Land use planning and changes
Water resources, impacts and management measures
Habitats, ecology (flora and fauna) and nature conservation, impacts and
management measures
Landscape and visual impacts, impacts and management measures
Air quality, impacts and management measures
Traffic, noise and vibration; impacts and management measures
Waste management
Raw material sourcing and transportation, including borrow pits
Road safety, impacts and management measures
Associated infrastructure impacts and management measures
Cumulative impacts
Induced (indirectly consequential) impacts
Occupational health and safety issues; including explosives safety
Disruption, health and safety during construction
Consistency with policy, law and other plans
Environmental management plans, mitigation measures and compensatory
measures
OFFICIAL USE
31 OFFICIAL USE
5 | Social Benefits, Adverse Impacts and Mitigation Measures
Socio-economic impacts; including gender and management measures (taking
into account gender specificities and needs)
Impacts on businesses and employment
Impacts to existing infrastructure and public services
Local traffic and access impacts
Land acquisition and resettlement (cross reference any resettlement report that
is being developed)
Contractor management, including the siting and management of worker
camps,
Community impacts (confirm that no Roma are known to utilise the land
and/or corridor route)
Labour issues and standards
Public road safety; including health and safety mitigation in the design
Social management plans, mitigation measures and compensatory measures
Cultural heritage, impacts and management measures
6 | Monitoring of Impacts
Process for monitoring the identified impacts
On-going solicitation of further comments
Process for addressing any issues arising