40
REPUBLIC OF BURUNDI PROJECT COMPLETION REPORT BURUNDI - BUTUTSI AGROPASTORAL DEVELOPMENT AGRICULTURE AND AGRO-INDUSTRY DEPARTMENT APRIL 2009

REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

REPUBLIC OF BURUNDI

PROJECT COMPLETION REPORT

BURUNDI - BUTUTSI AGROPASTORAL DEVELOPMENT AGRICULTURE AND AGRO-INDUSTRY DEPARTMENT APRIL 2009

Page 2: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

TABLE OF CONTENTS

Page

Table of contents, List of tables, List of annexes, Currencies and measures,

Acronyms and Abbreviations, Basic project data, Executive summary, i-xi

I. INTRODUCTION 1

II. PROJECT OBJECTIVE AND FORMULATION 1

2.1 Sector-based and specific project objectives 1

2.2 Project description 1

III. PROJECT IMPLEMENTATION 2

3.1 Loan effectiveness and project Start-up 2

3.2 Modifications made 2

3.3 Projected and actual implementation schedule 2

3.4 Reporting 2

3.5 Procurement Arrangements 3

3.6 Source of financing 3

IV. PROJECT PERFORMANCE 3

4.1 Overall Assessment 3

4.2 Operational Performance 4

4.3 Institutional performance 7

4.4 Performance of consultants, contractors and suppliers 7

4.5 Financial performance 8

4.6 Economic performance 8

V. SOCIO-ECONOMIC AND ENVIRONMENTAL IMPACTS 8

5.1 Social impact 8

5.2 Environmental impact 8

VI. PROJECT VIABILITY 9

VII. PERFORMANCE OF THE BANK AND THE BORROWER 9

7.1 Performance of the Bank 9

7.2 Performance of the Borrower 9

VIII. OVERALL PERFORMANCE AND RATING 9

IX. CONCLUSIONS, LESSONS LEARNT AND RECOMMENDATIONS 9

9.1 Conclusions 9

9.2 Lessons Learnt 10

9.3 Recommendations 10

LIST OF TABLES

Page

Table 3.2 Comparative table of project costs per source of financing 3

Page 3: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

LIST OF ANNEXES Page

Annex 1 Project Location Map 1

Annex 2 Annual disbursements of ADB loan and for entire Project 3

Annex 3 Project financial and economic return 2

Annex 4 Project Organization chart 2

Annex 5 Performance evaluation and rating 3

Annex 6 Activities undertaken as part of IGAs 1

Annex 7 Recommendations Follow-up Matrix 1

Annex 8 Information sources 1

Annex 9 Observations of borrower and executing agency 1

This report has been prepared by Messrs H. Lam, Agronomist (consultant, OSAN.1, Mission Leader), Diallo Boubacar Cissé

(consultant, Livestock Expert), Patrice NDIMANAYA (consultant, Agro-economist) following a mission conducted in

Burundi from 11 to 26 October 2008. All questions on the project should be addressed to the authors, to Mr. Ojukwu

Chiji Chinedum, Division Manager OSAN.1 (Ext. 2292) or to Mr. Ali Abou Sabâa, Director OSAN (Ext. 2037).

Page 4: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

i

CURRENCIES AND MEASURES

October 2008

Unit of Account = 1927.35 Burundi Franc

Unit of Account = 1.57 USD

Unit of Account = 1.07 Euro

FISCAL YEAR

1 January to 31 December

WEIGHTS AND MEASURES

1 TONNE = 2204 Pounds (lbs)

1 kilogramme (kg) = 2.2 lbs

1 metre (m) = 3.28 feet (ft)

1 millimetre (mm) = 0.03937 inch (“)

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

At Appraisal (1988)

On Completion (2008)

1 UA 1 FUA=167.263 BIF 1927.35 BIF

Trend of annual average exchange rate

Year 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997

BIF/UA 191.1 196 232.14 273.1 296.987 340.769 361.4 379.46 413.88 471.67

Exchange rates correspond to annual averages of the period under review

ACRONYMS AND ABREVIATIONS

ADB : African Development Bank

ADF : African Development Fund

BIF : Burundi Franc

CSC : Community Solidarity Chain

ERR : Economic Rate of Return FAO : United Nations Food and Agriculture Organization

IGA : Income-Generating Activities

ISABU : Burundi Institute of Agronomic Sciences

LGS : List of Goods and Services

m3 : Cubic Metres

MINAGRIL : Ministry of Agriculture and Livestock

Mm3 : Million Cubic Metres

MUA : Million Units of Account

NGO : Non- governmental Organization

PCR : Project Completion Report

PDAL : Provincial Department of Agriculture and Livestock

R/D : Research/Development

STD : Special Drawing Rights

TD : Tender Document

UA : Unit of Account

USD : United States Dollars

Year 1998 1999 2000 2001 2002 2003 2004 2005 200606 2007

BIF/UA 674.6

1

839.55 1031.77 1093.92 1417.85 15556.51 1618.89 1502.90 1569.73 1692.07

Page 5: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

ii

BURUNDI

BUTUTSI AGROPASTORAL DEVELOPMENT PROJECT

RETROSPECTIVE PROJECT MATRIX

REVISION DATE: MARCH 2009

PREPARE D BY: HAMADI A. LAM

Hierarchy of Objectives (HO)

Objectively Verifiable Indicators (OVI)

Means of Verification (MoV)

Assumptions/Risks

Appraisal/Reformulation PCR

Sector-based Objective

1. Contribute to improving the living standards of the

population of the BUTUTSI project area.

1. Increase in household income.

1 Increase in household income

1. Socio-economic surveys.

Project objective/goal

1. The income of farmers and stockbreeders in project

area increased.

2. Productivity and soil conservation improved

3. The isolation of Bututsi region decreased.

1.1. The monetary income of farmers involved in

the project exceeded average by 90,000

BIF/person in the project region

2.1 Main crops’ yield stepped up from 25% to

150% over project duration.

3.1 176 km of rural roads rehabilitated.

1.1 The monetary income of farmers involved in the

project scaled up from 90,000 BIF/individual to

213,326 in the Bututsi region

2.1 The main crops’ yield soared from 14% to 100%.

3.1 rural roads rehabilitated.

1.1 Regional surveys (MAE, Project).

2.1 Appraisal report, reference situation, small-scale project complementary surveys.

3.1 Reference situation, works contract documents

1. Political stability and conducive socio-

economic environment

2. Conducive trend in prices of main

products.

Expected results/yields Indicators of results or achievements

A. Development of food crop Production

1.1. Food crop production increased (maize, beans,

potatoes).

2.2. Food crop production diversified.

B. Livestock Development

1.1 Animal health improved thanks to the treatment of ticks

and infections

1.1.1 Animals treated for ticks

1.1.2 Animals inoculated against rinderpest, symptomatic

anthrax and foot-and-mouth disease.

1.1 Yields of 3-4 main crops increased at least

from 25 to 150% between the beginning and end

of project.

2.1 At least two (2) crops/products introduced by

the project are grown in project area.

1.1 A significant number of tick treatments have

been conducted during project period.

1.1.2 A significant number of animals have been

inoculated against rinderpest, symptomatic

anthrax and foot-and-mouth disease during the

entire project period

1.1.1 Maize sorghum and beans yields increased as

follows:

-Maize: from 0.8 T/ha to 1. 9 T/ha

-Beans: from 0.7T/ha to 0.8T/ha

- Sorghum : from 0.8T/ha to 1.17T/ha

-Potato: from negligible quantity to 9T/ha

2.1.1 Two (2) crops/products (potato and wheat)

introduced by the project are grown in project area.

1.1.1 About 6,887,164 tick treatments as compared

to 6,164,840 projected tick treatments (84.35%)

have been carried out during the entire project

period.

1.1.2 Cattle were inoculated against

symptomatic anthrax (32,698 head), rinderpest

(51,337), foot-and-mouth disease (727) during the

entire project period

1.1.3 Some 1,311 head of cattle were inoculated

against East Coast Fever at project closure.

Project progress report

Supervision report

Same

Provincial Livestock Department Report

1. Technical packages properly applied by

farmers

3. Availability of inputs.

1 Properly followed preventive measures

Page 6: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

iii

1.1.3 Calves were immunized against cattle theileriosis

(East Coast Fever).

1.2 Local breeds were improved and breeding bulls

disseminated

1.2.1 Milk yield (litre /day) increased

1.2.2 The number of cattle increased thanks to the

restocking of cattle herds through the community solidarity

chain scheme

C. Infrastructure

1.1 BUTUTSI region opened up

1.1.3 Numerous cattle inoculated against East

coast fever.

1.2.1 Some 500 breeding bulls were disseminated

during the entire project period.

1.2.1 Milk yield exceeding 2-3 litres/d

1.2.2 Numerous improved thoroughbred heifers,

bulls and goats were distributed through the

community solidarity chain.

1.1. 176 km of rural roads rehabilitated at project

closure

1.2.1 Some 441 breeding cattle were distributed at

the end of project (88%)

1.2.1 Milk production soared from 2-3 l/d to 6 l/d

at project closure.

1.2.1 873 improved thoroughbred heifers, 60 bulls,

and 7500 goats disseminated through the community

solidarity chain (Schema de Chaine de Solidarite

Communautaire- CSC) scheme

1.1. A total of 124 km of rural roads rehabilitated

at project closure.

Works procurement

Works acceptance report

2. Community Solidarity Chain Scheme

well respected

Activities

1. food crops Development

2. Livestock Development

3. Agroforestry

4. Women’s income-generating activities

5. .Infrastructure and rural roads

6. Monitoring-Evaluation/

7. Project management

Total

The following funds were envisaged for the

implementation of project activities.

(Costs in ADF Million)

UA

1.4

1.2

0.04

1.68

1.09

1.04

6.45

Project documents

Disbursement document

Project progress report

Project audit report

Supervision

1. Resources are available.

2. Sound Financial management by Project

Management Unit.

Page 7: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

iv

PROJECT BASELINE DATA

1. Country : Burundi

2. Project : BUTUTSI Agro-pastoral Development Project

3. Loan Number : 2100150000057

4. Borrower : Government of the Republic of Burundi

5. Executing Agency : Ministry of Agriculture and Livestock

A. LOAN Appraisal estimate Actual

1. Amount in (UA) 6,456,575 UA 5,881,446.82

2. Interest Rate 0.75 varies

3. Reimbursement period 50 years 50 years

4. Grace period 10 years 10 years

5. Loan approval date 14 December 1988

6. Signature date 28 May 1989

7. Date of entry into Force 19 September 1989

8. Projected start of activities 1989

9. Actual launching 1992

B. PROJECT DATA

Financing Plan

Appraisal estimate Actual Expenditure Gap (+ or -)

ADF UA 6,456,575 UA 5,881,446.82 UA + 575,128.18

IFAD SDR 6,700,000 SDR 2,521,820.86 SDR + 4,171,179.14

GOVERNMENT BIF 384,704,900 BIF 1,631,493,494 BIF - 1,246,788,594

2 Effective date of first disbursement 5 October 1990

3 Initial loan closing Date 31/12/1995

4 Deadline of last disbursement 31/03/2008

5 Start of activitie 4th quarter of 1989

6 Date of completion of activities 31 December 2007

C PERFORMANCE INDICATORS

___________________________________________________________________________

1. Balance in (UA) : 575,128.18

2. Cancellation in (UA) : 575,128.18

3. Slippage/advance with respect to schedule

Slippage on effectiveness 9 months

Slippage on completion date 12 years

Slippage on last disbursement 13 years

Number of extensions of last disbursement date Two

4. Project implementation status: The physical implementation of activities was completed on 31

December 2007, initially scheduled for 31 December 1995. In order to ensure sustainability of

activities, provincial services continue to support and assist project beneficiaries.

Page 8: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

v

List of verifiable indicators as compared to initial appropriations

Categories of expenditure Approved Budget

in UA

Actual expenditure

in UA

Difference (+ or -)

in UA

a) Goods 2,399,068.84 2,033,682.05 + 365,386.79

b) Works 1,549,267.96 1,283,528.36 + 265,739.6

c) Services 935,098,49 938,939.06 - 3,840.57

d) Recurrent 1,573,139.71 1,359,369.17 + 213,770.54

e) Contingencies -- 265,928.18 - 265,928.18

Total 6,456,575 5,881,446.82 + 575,128.18

5. Institutional Performance : unsatisfactory FairX Satisfactory

6. Performance of the borrower : unsatisfactory FairX Satisfactory

7. Performance of the Bank : unsatisfactory FairX Satisfactory

8. Performance of contractors : unsatisfactory Fair Satisfactory X

9. Performance of technical Assistance: unsatisfactory Fair Satisfactory X

10. Performance of consultant : unsatisfactory Fair Satisfactory

(Consulting firms) X

11. Economic rate of return (%) APPRAISAL PCR

17. 7% 6%

D. MISSIONS

Mission Type Number of

missions

Mission Date Number of

persons

Composition of mission Person/d

Identification 3 1983, 1985 and

1987

IFAD, ADF

Preparation 1 1987 IFAD, ADF

Appraisal 1 June 1988 4 J.P. Rigoulot (agronomist)

M. M. Kalala (Agricultural

economist)

D.Lekorchi (Civil Engineer)

Reformulation 1 10/1996 3 1 Irrigation Engineer

1 Agronomist

1 Agricultural economist

14

14

14

Supervision 11 27/03/96

20/11/97

1/11/98

14/06/99

28/06/2000

10/12/2000

17/12/2001

26/04/2005

16/12/2005

20/06/2006

4/12/2007

Agronomist

NA

Completion 1 11/10/2008 3 1 Agronomist

1 Agricultural economist

1 Livestock Expert

14

12

14

Page 9: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

vi

E. Annual Disbursement in Million UA)

Year ADF Actual

Disbursement (UA)

IFAD actual

Disbursement

(SDR)

Government actual Disbursement

(BIF)

1990 109.875.26 82.233.83 Government actual Disbursement in BIF

stands at 1,631,493,494 that is, roughly 4 times

the appraisal budget at the following exchange

rate.

1 UA = BIF 167,263 in 1988.

1991 118.893.79 159.672.35

1992 310.557.62 347.461.02

1993 333.645.52 432.706.81

1994 453.590.21 582.378.29

1995 182.885.69 74.940.58

1996 357.502.56 93.802

1997 51.449.68 299.278.19

1998 427.358.57 116.147.14

1999 55.971.37 239.266.38

2000 -- 64.782.27

2001 -- --

2002 -- --

2003 -- --

2004 -- --

2005 371.099.4 --

2006 1.293.728.75 29.052

2007 1.477.991.2 --

2008 549.307.97 --

TOTAL 6.093.857.59 2.521.820.86

Disbursement

rate

94.38 % 37.63 %

Balance to be

cancelled

575,128.18

Page 10: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

vii

F. PROCUREMENT LIST

SERIAL No. DESCRIPTION

ENTREPRISE Or NATIONALITY APPROVAL

PROCUREMENT

AMOUNT

IMPLEMENTATION

DEADLINE REMARKS

SUPPLIER

1 One station wagon SOGERBU II Ltd. BURUNDIAN - 2,497,420 BIF 3 ½ months 50% ADF and 50% IFAD

2 Seven 4x4 pick-up double cab vehicles SOGERBU II Ltd. BURUNDIAN - 20,574,491 BIF 3 ½ months 50% ADF and 50% IFAD

3 Five single cab pick-up vehicles SOGERBU II Ltd. BURUNDIAN - 9,972,572 BIF 3 ½ months 50% ADF and 50% IFAD

4 Two 3-3.5 Ton vanss SOGERBU II Ltd. BURUNDIAN - 7,521,410 BIF 3 1/2 months 50% ADF and 50% IFAD

5 2 YAMAHA DT motorcycles UNION MOTOR PARTS BURUNDIAN - 11,082,280 BIF 3months 50% ADF and 50% IFAD

6 100 Great lakes symba bicycles Industrie Burundaise du cycle BURUNDIAN - 2,672,400 BIF 1 ½ months 50% ADF and 50% IFAD

7 One Mercedes Benz truck type L1314/48 SOGERBU I Ltd. BURUNDIAN - 7,809,500 BIF 1 1/2 months 50% ADF and 50% IFAD

8 Two 4x4 jeeps SOGERBU I Ltd. BURUNDIAN - 14,600,000 BIF 2 ½ months 50% ADF and 50% IFAD

9 Four Mercedes Benz trucks MERCEDES BENZ AG POST FACH 600202 GERMAN - 572,339.60 DM 9 months 50% ADF and 50% IFAD 50% ADF and 50% IFAD

10 Agricultural implements, construction site equipment and materials IPEP (Industrie des Produits/et Proc FRENCH 1749,090.82 FF 9 months 50% ADF and 50% IFAD 50% ADF and 50% IFAD

11 Mobile Compressor and Accessories BIASA, Rameinstraat 123 BELGIAN - 200.80 LST 12 months 50% ADF and 50% IFAD 50% ADF and 50% IFAD

12 Construction of headquarters SOBIMAC BURUNDIAN - 174,094,074 BIF 9 months Extension amount of 9,475.926 BIF

13 300 Tonnes of urea fertilizer CHIMUSA-Emmanuel NYANKIYE BURUNDIAN - 129,013.42 USD - 50% ADF and 50% IFAD

14 10,000 doses of bovine semen and 5,000 BABIKA Tharcice IMPORT-EXPORT BURUNDIAN - 18,589,000 BIF 6 months 50% ADF and 50% IFAD

synchromate B + hormone treatments

5,000 PMGS gonadrotropine hormone Implants

15 Office equipment and supplies SOMECA BURUNDIAN - 1,381,233.02FBe 10 months 50% ADF and 50% IFAD

16 Veterinary Products and equipment BABIKA Tharcice IMPORT-EXPORT BURUNDIAN - 6,709,816 BIF 6 months 50% ADF and 50% IFAD

17 Veterinary Products and equipment IVM (Institute of veterinary medicine) FRENCH - 344,685.6FF 6 months Received 60% of procurement but never supplied

18 Ingredients for the manufacturer of salt licks

LAPROVET

FRENCH - 197,496 FF 8 months 50% ADF and 50% IFAD

19 600 Tonnes of DAP fertilizer, 600 Tonnes of Kcl fertilizer SOCIMPORTEX BURUNDIAN - 476,749.79 USD - 50% IFAD

20 Technical Assistance for credit SOGEAC BURUNDIAN - 47,950,000 BIF 30 months Contract was for 24 months but with extension

21 ISL Diesel Engine NAHV BURUNDI BURUNDIAN - 970,000 BIF - 50% ADF and 50% IFAD

22 Technical Assistance for facilitation training Compagnie Jules Van Lancker Belgian - 197,274 USD - 50% ADF and 50% IFAD

23 Furniture and household appliances

S.R.M.B

BURUNDIAN - 23,141,927 BIF 7 months

50% ADF and 50% IFAD

24

Mid-term review

SWEDISH FARM AND AGRO INDUSTRIAL SWEDISH - 23,449,000 BIF -

50% ADF and 50% IFAD

25 Financial Audit for fiscal years 1996-1998 A.D EXPERTS-CONSEIL BURUNDIAN - 9,910,000 BIF 3 months 10% of procurement not billed

26 Publication of international procurement notices GROUPE JEUNE AFRIQUE FRENCH - 27,000 USD - 50% ADF and 50% IFAD

Page 11: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

viii

27 Supply of Inputs (seed, seedling,

ISABU

BURUNDIAN - 218,196,000BIF Same day 69,095,600 BIF paid by ADF and

28 And improved animal breeds)

164,691,900 BIF by IFAD,

given that the difference of

15,591,500BIF was used for

the procurement of small holder dairy animal

29 Artificial insemination equipment and Supplies COOPER BURUNDI L.T.D BURUNDIAN - 179,928 USD - 50% ADF and 50% IFAD however ADF did

Serial No.

Not pay the balance of 8996 USD

which is less than 20,000 AU

DESCRIPTION ENTREPRISE/ SUPPLIER NATIONALITY APPROVAL

PROCUREMENT

AMOUNT

IMPLEMENTATION

DEADLINE REMARKS

30 Audit of project accounts fiscal years 1990- A.D EXPERTS-CONSEIL BURUNDIAN

- 24,000 USD - 50% ADF and 50% IFAD

31 Computer equipment and supplies SOFT CENTER BURUNDIAN

23/09/2005 13,174,500 BIF 6 months 100% ADF

32 Technical Assistance for monitoring/evaluation Dr Pascal Firmin NDIMIRA BURUNDIAN

31/03/2006 65,000 USD 6 months 100% ADF

33 2 tipper trucks, 15 motorcycles and 58 bicycles BONAUTO S.a BURUNDIAN

06/01/2006 188,050,000 BIF 6 months 100% ADF

34 90 tonnes of urea fertilizer Ets Francis GASHAKA BURUNDIAN

08/11/2005 71,550,000 BIF 3 months 100% ADF

35 2 NISSAN Jeeps, 3 double cab vehicles OLD EAST BURUNDIAN

06/01/2005 153,350,000 BIF 6 months 100% ADF

36 Technical assistance in training, facilitation AGRICONSULT S.a BURUNDIAN

05/05/2006 58,723,000 BIF 6 months 100% ADF

37 Technical assistance in accounting and management MASABO Adelin BURUNDIAN

14/10/2005 43,200 USD 6 months 100% ADF consultant died during mission

38 260 Tonnes of DAP fertilizers and 100 Tonnes of Kcl RUTA Company BURUNDIAN 08/11/2005 272,100,000 BIF 2 ½ months 100% ADF

39 Technical assistance in accounting and management Jean Marc Pétré French 19/04/2006 53,800 USD 9 months 100% ADF consultant abandoned the mission

40 200 improved-breed goats Ets NDAYIZEYE Jean BURUNDIAN

05/06/2007 41,000,000 BIF 3 ½ months 100% ADF

41 250 Frisian cows and 50 bulls Ferdinand KIVUTO BURUNDIAN

05/06/2007 188,970,000BIF 3 ½ months 100% ADF

42 360 cattle and 200 male goats Ets KANANI Adrien BURUNDIAN

06/06/2007 41,862,400 BIF 3 months 100% ADF

43 613 cattle Ets KANANI Adrien BURUNDIAN

11/2/2007 427,694,820 BIF 10 months 100% ADF

44 6 mills CREGECI LTD BURUNDIAN

08/11/02006 24,000,000 BIF 5 ½ months 100% ADF

45 Fully equipped tractor RUN COMPANY LTD BURUNDIAN

13/03/2007 53,900 EUROS 3 ½ months 100% ADF

46 Accounting and financial audit 2005, 2006 and 2007 GLOBOFAN CONSULTANTS KENYAN 23/02/2007 30,488,103 BIF 2 ½ months 100% ADF

47 Rehabilitation of rural tracks

Ets NDEREGO Antoine

BURUNDIAN 19/04/2007 1,025,949,044 BIF 9 months

100% ADF

The last bills were not settled

Because of forged signatures

on one of the definitive acceptance

documents

Page 12: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

ix

48

49

Rehabilitation of veto centres and agronomists’ offices

EBATER

BURUNDIAN

27/10/2006 60,699,310 BIF 4 months 100% ADF

50 Rehabilitation of poultry farms and centre

SOCEA

BURUNDIAN

27/10/2006 48,338,852 BIF 3 months 100% ADF

51 Rehabilitation of headquarter offices, garage,

ERETRACO

BURUNDIAN

27/10/2006 56,496,994 BIF 6 months 100% ADF

52 Equipment for MUZENGA poultry centre

SPEED LINK

BURUNDIAN

17/04/2007 33,676,880 BIF 7 months 100% ADF

53

537 goats Lot No.1

RIVUZIMANA Balthazar

BURUNDIAN

25/10/2007 10,872,102 BIF 3 months 100% ADF

54

252 goats Lot No.2

NKURUNZIZA Christophe

BURUNDIAN

25/10/2007 5,152,140 BIF 3 months 100% ADF

55 537 goats Lot No.3 HAKIZIMANA Willybroad BURUNDIAN

25/10/2007 1,330,700 BIF 3 months 100% ADF

56 408 goats s Lot No.4 NIMUBONA Gérard BURUNDIAN

25/10/2007 8,347,680 BIF 3 months 100% ADF

57

531 goats s Lot No.5

NIYONIZIGIYE Laurent

BURUNDIAN

25/10/2007 7,371,000 BIF 3 months 100% ADF

58

315 goats Lot No.6

KARIKUNZIRA Déo

BURUNDIAN

25/10/2007 6,547,500 BIF 3 months 100% ADF

59

Technical assistance for animal restocking

FAO

Rep. Burundi 27/02/2006 191,409USD 24 months 100% ADF

Page 13: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

x

EXECUTIVE SUMMARY

1. Background: Burundi has experienced a difficult food situation with persistent

regional and seasonal variations. A quarter of the population, mostly living in rural areas, has

been unable to meet its food needs. Such is the case with the BUTUTSI region (project area).

There have been several stages of preparation of this project, with IFAD identification

missions in 1983 and 1985, and a joint IFAD-ADF identification mission in June 1987. The

final project preparation phase was carried out by the FAO Investment Centre (IC), and a

project appraisal mission was then conducted by ADF in 1988.

2. Project objectives and components: The specific project objectives are: (a)

Increase in farmers’ income; (b) Improve soil conservation and productivity; and (c) Open up

the BUTUTSI region. These objectives were to be achieved through the following

components: (a) Food crop development; (b) Livestock development; (c) Women’s income-

generating activities; (d) Credit; (e) Agroforestry and land protection; and (f) Infrastructure

and rural roads.

3. Project Implementation: The project loan was approved by the Bank on 14

December 1988 and the relevant loan agreements signed on 27 January 1989 with IFAD and

on 28 May 1989 with ADF respectively. The date of effectiveness was 19 September 1989,

and implementation fell behind schedule owing to the 1993 Social and political crises and

sanctions imposed by the Bank from 1999 to the beginning of 2005. After these sanctions

were lifted, a Bank supervision mission conducted in April/May 2005 made for formulation

of a recovery programme for the 2005-2007 period.

4. Project Performance: After the recovery programme started in 2005, the project

gained new impetus and recorded satisfactory results, as follows : (i) Food crop development

allowed for the dissemination of several tonnes of various crop seeds from seed-production

centers and private participants/ farmers’ associations; (ii) Livestock development had

positively impacted on animal health and involved restocking of herds and genetic

improvement; (iii) introduced new disease-resistant and high-yielding varieties. (iv) Women’s

income-generating activities provided much needed support to women, unemployed

graduates and demobilized military personnel in market gardening, bee-farming and poultry-

farming.

5. Project Social and Environmental Impact: The project has invested tremendous

resources in the promotion of collective action. In an atmosphere of social crisis, this strategy

has contributed to reconciling communities and promoting a structuring culture driven by

common interest. This project is credited with taking into account the lack of job security for

young graduates who, in the aftermath of the war, faced difficulties in finding employment.

Concerning the environment, significant efforts have been made by farmers to protect lands

from soil erosion and restore soil fertility in the Bututsi project intervention area.

6. Project Sustainability: The project has helped to provide farmers with innovative

and adapted seed production and multiplication techniques, farming techniques, as well as

environmental protection techniques. With respect to livestock (inoculation coverage, setting-

up of community solidarity chains and smallholder dairy farms), the project makes for the

viability and sustainability of activities undertaken for the population.

Page 14: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

xi

7. Conclusions, Lessons learnt and recommendations

7.1 Conclusion

On the whole, project activities have been undertaken in a satisfactory manner, despite

slippage in the implementation schedule. The project has scored satisfactory results

essentially in the course of the 2005-2007 period. Farmers showed keen interest in seed

multiplication and restocking of livestock population through a community solidarity chain

system which has strengthened social cohesion.

7.2 Lessons learnt: The following lessons derived from project implementation could

lead to improved performances: i) the participatory approach helped to cement communal

bonds and to creating community solidarity chains, thereby consolidating social cohesion. This

an approach should be perpetuated; (ii) It is important to recruit technical assistance at the very

beginning of the project in order to bring on board, as early as possible, the experienced

personnel needed to carry out activities, train senior staff and transfer appropriate skills and

technologies wherever institutional capacity is weak; (iii) It is important to define a project

action area reference situation prior to project start-up, so as to improve the monitoring and

evaluation system.

7.3 Recommendations:

7.3.1 For the Borrower : The main recommendations are as follows : i) Reorganize and

revitalize the seed sector by involving the private sector and farmer groups/associations ; ii)

strengthen the capacities of the Provincial Department of Agriculture and Livestock so as to

enable it provide supervision and training; iii) enable more intensive agriculture-livestock

integration with the aim of restoring and improving soil fertility through the production and

use of organic manure, given the high cost of chemical fertilizer; and iv) Pursue cooperation

between FAO and ISABU so as to consolidate the animal population restocking programme

and zootechnical monitoring.

7.3.2 For the Bank: (I) Promote parallel financing instead of joint financing so as to

avoid interruption in activities in the event of suspension of disbursements by one of the

donors ; (ii) continue to support the rural sector and strengthen the Bank’s presence in the

country.

Page 15: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

I. INTRODUCTION

1.1 Burundi has experienced a difficult food situation as a result of rapid population

growth (3% per annum), limited arable land for agriculture and gradual soil depletion, owing

to erosion, mineral and organic deficiency. While Burundi has achieved food self-sufficiency

at the national level, there are persistent regional and seasonal disparities, and as a result, a

quarter of the population, mostly living in rural areas, is still unable to meet its food needs.

Such is the case with the Bututsi region (project area) among those regions experiencing the

most severe food shortages. Project preparation was entrusted to the FAO in 1986, and IFAD

then requested to co-finance the project.

1.2 Background: Project preparation comprised several phases, with IFAD

identifications mission in 1983 and 1985 and a joint IFAD-ADF identification mission in

June 1987. The final project preparation was conducted by the FAO Investment Centre (IC).

The mission concluded that the project should be limited to the northern part of the Bututsi

region, contrary to the desire of the Government to see the project cover the entire Bututsi

region. A project appraisal mission was then conducted by the ADF in 1988. The project was

scheduled to span five years with ADF financing for 6, 456,575.00 Units of Accounts (UA)

and IFAD co-financing for an amount of UA 7.01 million. Initial disbursements were made in

1990 for the ADB and in 1991 for IFAD. The project was readjusted in 1988 by ADB and

IFAD and by ADB during a supervision mission, after the withdrawal of IFAD in April 2005.

The readjustment enabled the Bank to formulate a recovery programme for the 2005-2007

period.

1.3 The initial project design involving the two donors, (with contribution by the

government of Burundi) was conducted along two separate lines. Hence: (i) There are

differences in the number, outline and title of components: the ADF loan agreement

presented an 11-component project as compared to 7 components for IFAD; (ii) The list of

goods and services representing ADF financing categories is based on the list of components,

whereas the IFAD drew up a classic list of categories.

II. PROJECT OBJECTIVE

2.1 Project Sector-based and specific objectives

2.1.1 The project’s general objective (GO) was to «contribute to improving the general

standard of living of the population in the Bututsi project area». The specific project

objectives were to: (a) Increase farmers’ income; (b) Improve soil conservation and

productivity; and (c) Open up the BUTUTSI region.

2.2 Project Description

To achieve its set objectives, the project laid emphasis on increasing food crop production,

developing fodder crop production, improving the cattle breeds and starting new stockraising

activities. These objectives can be achieved through intensification of existing crops and

introduction of new cash crops, improvement of existing cattle breeds and the conduct of

pilot actions regarding stockbreeding and agroforestry. These activities were to be

implemented through the following components: (a) Food crop development; (b) Livestock

development; (c) Women’s income-generating activities; (d) Credit; e) Agroforestry and land

protection; (f) Infrastructure and rural feeder roads; and (g) Institutional support. The credit

component was cancelled due to very low credit recovery rate.

Page 16: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

2

III. PROJECT IMPLEMENTATION

3.1 Loan effectiveness and Project Start-up

3.1.1 The project loan was approved by the Bank on 14 December 1988 and the loan

agreement signed on 28 May 1989 (6 months later), and the loan came into force on 19

September 1989, that is 5 months after signature of loan agreement. The project did not get

underway until 1992-1993. Beginning in 1993, however, the country was in the grips of a

social and political crisis. In addition, just as the project was about to be resumed in 1998, it

was suspended from 1999 to 2004, owing to unpaid arrears. After the arrears were settled in

2005, the Bank conducted a supervision and reformulation mission from 27 April to 9 May

2005, which helped to put in place a recovery programme for the 2005-2007 period.

Activities were completed on 31 December 2007, and the project ended on 30 June 2008.

3.2 Modifications

3.2.1 Following the disruptions in project implementation and IFAD withdrawal,

project activities were readjusted. The following major modifications were made: (i) increase

in livestock population especially small ruminants (ii) involvement of FAO in the project,

which was not planned from the beginning; (iii) Introduction of income-generating activities

after IFAD eliminated the credit component. The remaining project components were as

follows: (a) Food crop development; (b) Livestock development; (c) Women’s income-

generating activities; (d) Agroforestry and land protection; (e) Infrastructure and rural tracks;

and (f) Institutional support. As already indicated in paragraph 2.2, the credit component was

cancelled.

3.2.2 The size of the population has also increased. In 1988, the target population was

estimated at 188,300 inhabitants in 5 communes, namely: Bururi, Matana, Rutovu, Songa and

Vyanda, while 2006 the target population was about 250,000 inhabitants 6 communes (the

above-mentioned five in addition to the Mugamba commune). The number of farms

represents about 48,000 to 50,000 households.

3.3 Projected and actual implementation schedule

Initially, the implementation schedule indicated that the project would be executed

over a five-year period. However, this time frame has been greatly exceeded, since project

activities were spread over a thirteen-year period (excluding 2004-2005 period). The loan

agreement was signed by IFAD on 27 January 1989 and ADF on 28 May 1989, and first

disbursements were on 5 October 1990 for ADF and 8 January 1991 for IFAD Competitive

bidding scheduled for the first two quarters of 1981 took place only in May 1991. Buildings

and living quarters were finalized at the beginning of 1995 instead of the end of 1990, as

indicated in the projected implementation schedule.

3.4 Reporting

In this period, the project produced, on regular basis, 68 quarterly reports and 17

annual reports. These reports helped monitor the implementation of project activities. With

regard to auditing, 10 reports were submitted on a regular basis in accordance with Bank

requirements. The partner institutions (FAO and ISABU) periodically submitted progress

reports which contributed to monitoring their intervention on the ground. A mid-term review

Page 17: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

3

report was drawn up in 1996 by SWEED FARM consulting firm. This report was not

approved by the borrower, on grounds of non-compliance with TORs.

3.5 Procurement

During the project implementation period, 57 contracts were awarded through

competitive bidding procedures. They mainly concerned procurement of capital goods,

vehicles, infrastructure, technical assistance, administrative and financial monitoring,

stockraising and agricultural inputs. Overall, procedures were conducted in accordance with

Bank and borrower procedures. Both Government and Bank administrative procedures

sometimes undermined the smooth conduct of activities. Nevertheless, it should be

considered that all the contracts awarded were satisfactorily executed with the exception of

the rehabilitation of rural tracks. Indeed, works entrusted to NDEREGO have not been

completed, and moreover, the firm was engaged in fraudulent practices, by submitting fake

final acceptance reports. When it discovered these fraudulent practices, the Bank denied

requests for payment relating to the works in question. The Bank was informed that

Government had instituted legal proceedings against the enterprise. The Government was

requested to clarify this matter and keep the ADB informed of the outcome of the

proceedings.

3.6 Financing Sources and Disbursements

The project was co-financed by ADF, IFAD, Government and BNDE. The ADF

loan stands at UA 6,456,575.00. The amount disbursed is UA 5,926,366.79, that is 91.7%.

The loan balance, which stands at UA 530,208.21, has already been cancelled. As at 2004,

IFAD had already honoured its commitments up to 37.6%. BNDE’s participation did not

materialize, as shown in the table below.

Comparative table of project costs by financing source (in millions)

Appraisal cost Completion cost Gap

ADF in UA 6.46 5.88 -0.58

IFAD in SDR 6.7 2.52 -4.18

Government in BIF 3.84 16.3 +12.46

BNDE+ in UA 0.07 0 -0.07 NB+ : The loan agreement provided that the Government, in conjunction with the BUTUTSI projectwould contract a loan

with the BNDE to rehabilitate the KIRYAMA dairy farm. However the farm went bankrupt and the Government did not

proceed with the said request for credit.

IV. PROJECT PERFORMANCE

4.1 Overall Rating

The 1993-2004 period was characterized by a slowdown in activities following

the suspension of disbursement by donors. In addition, this period saw a massive departure of

the senior staff responsible for project implementation and a perpetual change of Directors,

which somewhat undermined project implementation. After the resumption of activities in

2005, the project gained fresh impetus and recorded satisfactory results.

Page 18: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

4

4.2 Operational Performances

4.2.1 The project had significant outputs and the main activities programmed after its

resumption, were implemented as expected, meeting and even exceeding, set objectives. The

implementation status of various project components is as follows:

Component 1: Food crop Development

4.2.2 Seed Production : The project produced and distributed to seed-production

centres: 2692 tonnes (T) of potatoes planted on 295.7 ha, as compared to the 2857 tonnes

envisaged (implementation rate of about 94%); 78.6 tonnes of sorghum against 37.2 (210%

implementation rate); 309.6 tonnes of maize as against 191.9 tonnes (69.4%); A Total of

28,493,870 sweet potato cuttings were produced as compared to 31,943,000 projected

(89.2%); wheat : 281.8 tonnes against 164.9 tonnes projected (52.2%). Private individuals

and associations produced 1337 tonnes of potatoes, 42.4 tonnes of maize, 60 tonnes of

sorghum, 24 tonnes of wheat, 284 tonnes of beans. 2644 private

stakeholders/farmer’ associations engaged in the production and multiplication of seeds of

different crop types. 93 private participants contributed to the multiplication of mosaic-

resistant cassava cuttings on 40 ha. The application of technical packages, with the

introduction of the project, (improved seeds, organic manure, and fertilizers) led to improved

yields (ha/tonne) for the main food crops: maize: 1.9 tonnes/ha against 0.8 tonne/ha, that is a

138% increase; beans: 0.8 against 0.7 tonne/ha (14.3%); sorghum: 1.17 tonnes/ha against 0.8

tonne/ha (46%).

4.2.3 Research and Development programme: This sub-component was implemented

through an agreement signed with the Burundi Institute of Agronomic Sciences (ISABU).

ISABU’s missions were to: (i) conduct pilot extension activities and support the training of

extension officers; (ii) aid productivity improvement through agriculture-livestock

integration; (iii) promote production of pre-basic seeds and provide technical support to seed-

production centres; and (iv) promote agro forestry. ISABU has identified 50 pilot farmers in

the three communes of Bururi, Mugamba and Matana, as compared to the 60 (20 per

commune) projected, that is 83.3% implementation of the agreement.

4.2.4 Action has been taken to protect farms from soil erosion. Between February 2006

and December 2007, 12,050 Calliandra Calothyrus plants were planted on 3,520 m of contour

lines. About 70,000 Tripsacum and Pennisetum sprouted roots were made available and

planted along hedges and in farms. As regards support to the training and extension unit, two

training sessions were conducted: The first session was on sorghum cultivation management

and yield preservation with 25 participants including 5 women, and the other session on

techniques for management of potato, sweet potato and fodder crop cultivation.

4.2.5 ISABU experienced constraints in the delivery of animals (demand for animals

exceeded supply), seed supply (seed sector not organized, water management, dormancy

problems, lack of germplasm and high demand nationwide)

4.2.6 As regards financial achievement, of a total of BIF 218,163,900 representing the

total agreement amount, BIF 163,438,300 was transferred to ISABU. BIF 158,367,428 was

spent (including pending orders), that is about 96.87%. A balance of 6,243,298 FBI is

available on ISABU’s account. ISABU’s technical and scientific support has been

commendable. In order to contribute to building the capacities of the Research and

Development unit, it is recommended that the movable and immovable property procured as

Page 19: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

5

part of this project (cf agreement between project and ISABU) be handed over to the Ministry

of Agriculture and Livestock and then reassigned to ISABU.

4.2.7 Organic manure production and fertilizer dissemination: The project provided for

the installation of 48,000 Composters and 33,984 at the end of the project, in all about 70.8%,

were put in place in six communes with a manure-production volume of 203,900 m². The

dissemination of chemical fertilizers was conducted as follows: 778,000 Kg of DAP; 700,000

kg of KCL; and 152,870 kg of Urea. In order to adjust soil acidity, 55,000 kg of ground

limestone, that is 81% of the initial 68,000 kg, were mixed into the soil.

4.2.8 Component 2: Livestock Development: The main objective of this component

was the improvement of animal health and seed, and animal re-population. The number of

tick treatments was 6,887,164, as compared to the projected 8,164,840 treatments, that is an

achievement rate of 84.35%. For internal parasites, 721,500 doses were scheduled and

907,845 doses were effectively applied giving an achievement rate of 125%. Concerning East

Coast Fever control, 1,311 cattle were inoculated. The animals were vaccinated against

symptomatic anthrax (32,698 head), foot-and-mouth disease (727), and rinderpest (51,737) in

conjunction with the national veterinary laboratory. The rate of participation in inoculation

campaigns is quite high: 55% for activities with a 50% subsidy and 90% for activities

subsidized at the rate of 100%. The programme to rehabilitate veterinary facilities and

provide them with drugs has been entirely implemented.

4.2.9 The project provided cattle feed and developed fodder crops with satisfactory

results. Concerning genetic improvement and cattle dissemination, more than 9,200 artificial

insemination operations have been conducted; 283 stud bulls, 194 stud goats were

disseminated; in addition, more than 279 smallholdings received 2,227 head of livestock,

(477 cattle and 1,750 goats). Animal yields in slaughter weight (fattening) could not be

quantified, given that the animals were procured at the end of the project. Milk production

increased on average from 2/3 litres/d (local Ankole breed) to 6 litres/d (improved Frisian

breed). ISABU provided the project with 63 animals as compared to the projected 160. This

is due to lack of germoplasm and the fact that it was impossible to directly negotiate contracts

(unauthorized by public procurement commission) with specialized scientific institutions in

the sub-region. The partnership with FAO helped to consolidate the outputs this activity,

since monitoring and supervision were properly undertaken. Such supervision activities will

be pursued by the services of the Ministry of Agriculture and Livestock, whose officers and

staff have been trained by the project.

4.2.10 All the actions have helped to ensure livestock development while improving the

zootechnical performance of animals. Livestock trends in the Bututsi Project area are

assessed as follows: (i) increase in cattle numbers from 70,000 head in 1990 to 74,359 in

1999 and 89,795 in 2005; (ii) During the same period, the number of small ruminants

increased respectively from 50,000 in 1990 to 62,372 in 1999, and then to 92,268 in 2005.

Actions to boost animal health and restock the animal population have contributed to such

increase.

4.2.11 The restocking of the animal population may be considered as one of the

successes of the project. This activity has been implemented through a participatory livestock

management approach commonly called the "Community Solidarity Chain“ (chaine de

solidarite communautaire -CSC), which is a cycle consisting in providing each individual

concerned with a heifer to raise until it calves. The offspring are raised and tended and then in

turn given to other persons as soon as they are weaned off and independent of their mothers,

Page 20: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

6

and so on. 873improved breed heifers have been disseminated in 873 households, 60 bulls in

60 households and 7,500 male goats in 2,500 households have been disseminated through the

CSC. The CSC chain is managed by a committee elected by beneficiaries from amongst

community members. A total of 410 farmers have participated in the CSC on the 82 pilot

districts. The selection of farmers to receive the heifers is based on the following criteria: the

farmer should (i) not already have cattle or smaller stock; (ii) have 25 acres of fodder crops;

(iii) have fodder crops planted along contour lines and footpaths; (iv) have well shaded

composters; (v) agree to build a modern stable; and (vi) agree to practise permanent housing

as a method of animal husbandry.

4.2.12 Component 3: Agroforestery and land protection: Activities under this

component consisted in plant production, land protection and reforestation. The population

has been sensitized and trained in land management. Of a total of 4,640,000 forest plants

projected, the project produced 4,053,876, that is an achievement rate of 87.36%. Private

operators produced 318,575 forests plants out of 532,000 envisaged and 318,635 agro-

forestry plants out of 660,000 projected. Distribution of seedlings and saplings (forestry and

agro-forestry) produced by farmer groups stands at 376,223 as compared to 378,085 plants

projected, that is an implementation rate of 99.5%.

4.2.13 Component 4: Women’s income-generating activities: Support here concerned

women, unemployed graduates and demobilized military personnel. The poultry-farming and

bee-keeping sub-components achieved their set objectives with the construction of 2 chicken

houses, procurement of 275 parent chicks, production of 1,500 chicks from the parental stock

which benefitted some 445 persons (201 men and 244 women) and support to 15 bee-farming

associations, supply of 850 modern hives to 193 persons, including 46 women. The results of

implementation of these activities were satisfactory and should be followed up by a technical

staff of the province. Market gardening activities benefitted 2,202 persons, generating an

annual income estimated at BIF 469,743,934, that is, a per capital income of 213,326 BIF.

Market gardening has clearly scaled-up rural women’s income, in comparison with the

average per capita income in the Bututsi region which is BIF 90,000.

4.2.14 Component 5: Infrastructure and Rural tracks: The objective of the

component was to rehabilitate buildings and rural tracks. Rehabilitation works on buildings

(offices, warehouses, veterinary centres, farms, and dwellings) were carried out at a rate of

100 %. Of a total of 176 km of rehabilitated roads, 124 km were without road-surfacing

works, since NDEREGO enterprise went bankrupt. Rehabilitation activities on veterinary

facilities were completed, with 7 veterinary centres rehabilitated.

4.2.15 Component 6/7: Project Management/Monitoring-Evaluation: As required by

the civil service, project staff were absorbed by the PDAL, thereby facilitating continuity in

supervision activities. Project administration and financial management have been improved

thanks to the installation of accounting, computerization and monitoring software. An

inventory of stock and fixed assets (automobile fleet, equipment and buildings) was prepared.

This inventory will be used as the basis for allocation of goods. The objective of the

Monitoring and Evaluation Unit was to provide useful information on the status of project

activities and the project performances and impact. The project conducted socio-economic

and market price surveys. The project benefited from technical assistance support for

monitoring and evaluation, and a monitoring-evaluation manual has been prepared.

Page 21: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

7

4.3 Institutional Performance

The project was initially managed by a management unit under the office of the

Minister. For the validation of technical programmes, a steering committee reported, on a

quarterly basis, to a monitoring committee chaired by the Director General for Extension

Work, co-chaired by the Governor of the province concerned and comprising a representative

of the staff, farmers and technical ministries involved in the project. Project management

underwent numerous changes (7 different directors), with the attendant impact on project

implementation deadlines.

The executing agency’s performance is rated as fair.

Performance of consultants, contractors and suppliers

4.4 Performance of consultants

4.4.1 Training/Supervision and Monitoring-Evaluation/Management: The mission of

the technical assistance to provide training/supervision for 27staff/monthS could not be

completed, owing to socio- political upheaval in the country. This assistance was replaced by

six-month missions. The project also benefited from six-month technical assistance missions

in the areas of training, monitoring-evaluation and management. The consultant conducted a

socio-economic survey and produced the following documents: Training modules,

Monitoring-evaluation manual, Farms’ reference situation, Accounts chart and Guide to use

of software. The consultant’s performance was deemed satisfactory.

4.4.2 FAO and ISABU Intervention: FAO has played a key role based on the

agreement it concluded with the project. In accordance with its mission, as set forth in the

framework agreement, FAO: (i) sensitized the populations to whom animals were distributed,

set up and provided support for community solidarity chain management committees and

technical support for the selection and setting-up of the community solidarity chain (CSC);

(ii) strengthened the capacities of senior staff, workers and farmer-stockbreeders. FAO

support is deemed satisfactory. ISABU properly accomplished its mission in implementing its

agreement with the project. ISABU’s performance is rated satisfactory.

4.4.3 Audit: Project accounts were audited for the 1996-1998 and 1999-2000 periods,

the 2005, 2006 and 2007 fiscal years and for the period from January to June 2008. The audit

and management consulting firms submitted satisfactory reports. Overall, all consultancy and

technical assistance was satisfactory.

Performance of contractors

4.4.4 As regards infrastructure, the main outputs are as follows: construction of project

headquarters, rehabilitation of feeder roads, rehabilitation of veterinary centres, rehabilitation

of farms and poultry-farm centres, rehabilitation of headquarters offices, garage, warehouse

and house. Except for the rehabilitation of feeder roads, enterprises executed their contracts

satisfactorily. However, the performance of NDEREGO enterprise was deemed

unsatisfactory, and litigation is pending between the enterprise and the administration for

fraud and use of forged documents (drawing up fake final acceptance reports prior to

completion of works).

Page 22: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

8

4.4.5 Performance of suppliers: This heading covers vehicles, office equipment,

stockbreeding and agricultural inputs, animals, poultry, etc. All equipment was delivered in

accordance with technical specifications, and no objections or claims have been registered.

4.5 Financial performance

Given that the project was implemented during a period of socio-political turmoil,

performances fell below expectations. Between 1990 and 2006, the project recorded negative

cash flows, but two years after the conflict, began producing positive cash flows. Sustainable

income may only be expected in respect of the inputs invested in farms between 2005 and

2008. The intensified restocking of the animal population during this period favoured

biomass production. Increased biomass in turn favoured the expansion of climbing bean

varieties whose yields were 2 or even 3 times greater than the traditionally cultivated dwarf

bean variety. That spared farmer-breeders the purchase of this legume which is a staple food

crop in the country. Beside zootechnic products, the crop sectors have registered a 30 % yield

increase.

4.6 Economic Performance

As soon as peace returned to the country, the additional project-generated

products were as follows: 814 tonnes of potatoes, 465 tonnes of maize, 2,618 tonnes of sweet

potato, 810 tonnes of cassava and 79 tonnes of beans. Maize and bean seeds as well as sweet

potatoe and cassava cuttings are for local subsistence. Further effects of the project have

concerned the generation of temporary employment during infrastructure

construction/rehabilitation and input production. The project created an environment

conducive to high demand for inputs (fertilizers, seeds, cattle feed, veterinary medications,

etc...) and this trend will sustain local trade. The internal rate of return, calculated over a 15-

year period at project closure, is 6%, compared to 17.7% envisaged at appraisal. With the

losses incurred by beneficiaries during the war not taken into account, the ERR is very low.

V. SOCIAL AND ENVIRONMENTAL IMPACT

5.1 Social Impact: Farm development, operation of mills and poultry farming were

organized either in catchment areas or in farmers’ groups. Against a backdrop of social crisis,

this strategy helped reconcile communities and promoted a structuring culture driven by

common interest. The organization of collective action and participation in finding jobs for

young graduates and demobilized military personnel contributed to peacebuilding. These

target groups, together with young farmers, were included amongst the beneficiaries of IGAs.

Women’s groups provided an experience-sharing framework, thereby freeing women from

isolation. Gender considerations in project implementation reduced distortions in access to

project resources.

5.2 Environmental Impact: Significant efforts were made by farmers to protect lands

from soil erosion and to restore soil fertility in the Bututsi Project intervention area.

Experience with wooded areas has shown that shrubby legumes fare better in pastures. The

planting of shrubby legumes on contour lines, in addition to other erosion-control measures

yielded positive results in terms of soil protection and conservation.

Page 23: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

9

VI. PROJECT VIABILITY AND SUSTAINABILITY

The project capitalised numerous outputs in the areas of agriculture and

stockbreeding. Farmer training, supervision and extension services have helped to equip

farmers with adapted and innovating seed production and multiplication techniques, farming

techniques to aid environmental protection and organisational techniques. Concerning

stockbreeding, the rehabilitation of the veterinary infrastructure, the extension of fodder

crops, the setting-up of the Community Solidarity Chain, are conducive to viable and

sustainable population-centred actions. As regards the continuity of seed multiplication by

private operators, activities will be undertaken by the following associations:

DUTABARANE in BITEZI (MATANA) and DUFATANEMUNDA in MUZENGA. The

Ministry of Agriculture and Livestock has a provincial administrative and technical structure

staffed by technicians carrying out technical supervision from the provincial level to « hill”

(commune) level, thereby ascertaining sustainability and consolidation of project outputs.

Road maintenance will be carried out by the BURURI province with the participation of the

inhabitants through associations.

VII. PERFORMANCE OF THE BANK AND THE BORROWER

7.1 Performance of the Bank

Overall, the performance of the Bank is rated as fair. It should be noted that the Bank

allowed a five-year project to extend to 18 years. The Bank should have stopped the project

to avoid increasing financial charges and adversely affecting performance which could lead

to reduced flows to Burundi.

7.2 Performance of the borrower

During the period when disbursements were suspended, the Government made a

contribution of BIF 1,631,493,494 covering 19 months’ salary arrears for Government-paid

staff for 2002 and 2003. However, the Government was unable to take the measures needed

to curb project implementation delays. The borrower’s performance is rated as fair.

VIII. OVERALL PERFORMANCE AND RATING

The overall project performance is deemed satisfactory, based on results.

Sustained efforts by project management, supported by various stakeholders and partners,

have helped to achieve appreciable results.

IX. CONCLUSIONS, LESSONS LEARNT AND RECOMMANDATIONS

9.1 Conclusions

The project has recorded satisfactory results mainly from the 2005-2007 period,

during which activities actually resumed. Seed production and multiplication activities were

conducted with ISABU support and the participation of private operators and farmer

associations. The restocking of animal population including genetic improvement of local

breeds and the setting-up of the community solidarity chains have been great successes with

the stockbreeders who participated in large numbers in the programme.

Page 24: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

10

9.2 Lessons learnt: Lessons learnt could help improve project formulation and

performance in the future. They are as follows:

(i) Project design: As explained in paragraph 1.3 above, co-financing with

IFAD raised certain project implementation difficulties. For future

cofinancing, equal sharing of financing of goods and services should be

avoided. Instead, each donor should finance clearly targeted project

components;

(ii) Monitoring: Importance of frequent Government and Bank supervision

missions to systematically make adjustments needed during project

implementation and take decisions regarding project continuity in the

event of persistent conflict, thereby avoiding the tying up of resources

which entails increased costs (on undisbursed funds) and affects the

allocation of country resources in ADF cycles.

(iii) Participatory approach: The participatory approach was adopted during

project reformulation. It contributed to strengthening the social fabric in

communes, and community solidarity chains were the cement of social

cohesion. Due importance should be given to such a participatory approach

in the design of similar projects.

(iv) Capacity building: Where technical assistance is envisaged, it is imperative

to recruit the technical assistance at the very beginning of the project in

order to have, early enough, the experienced personnel needed to carry out

activities, train senior staff and transfer appropriate skills and technologies

in areas of weak institutional capacity;

(v) Baseline data: It is important to define the project area reference situation

prior to project start-up, so as to improve the monitoring and evaluation

system;

9.3 Recommendations

9.3.1 Recommendations to the borrower:

(i) Reorganize and revitalize the seed sector by involving private operators

and farmers’ groups/associations in activities (Para. 4.2.2);

(ii) Strengthen the capacities of the Provincial Department of Agriculture and

Livestock so as to enable it to continuously provide supervision and

training. To achieve this objective, the project’s movable and immovable

property (vehicles, buildings, operating funds, computer equipment...)

should be reassigned to PDAL (Para. 4.2.9);

Page 25: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

11

(iii) Pursue cooperation with FAO and ISABU so as to consolidate the animal

population restocking programme and the zootechnic monitoring of

animals (Para.4.2.9) ;

(iv) Follow through with the fraudulent practice proceedings against

NDEREGO enterprise and inform the Bank of measures and decisions

taken (Para. 3.5);

9.3.2 For the Bank

(i) Adopt parallel financing as opposed to joint financing in order to avoid

dsirupting activities, should one of the donors suspend disbursements

(Para. 1.3);

(ii) Continue to support the rural sector and increase Bank presence in

Burundi;

(iii) In future, implement the rules of procedure concerning loan cancellation

for projects experiencing significant implementation delays. (Para. 7.1).

Page 26: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 1

BURUNDI

BUTUTTSI AGROPASTORAL DEVELOPMENT PROJECT

Map of Burundi with project location area

This map was provided by the African Development Bank staff to be used exclusively by readers of the report to which it is

appended. The names used and boundaries appearing on this map do not imply any jugement whatsoever by the ADB Group

and its members regarding the legal status of a territory nor the approval or acceptance of its boundaries.

Page 27: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 2

Page 1 / 3

BURUNDI

BUTUTSI AGROPASTORAL DEVELOPMENT PROJECT

Details of ADF disbursements

REQUEST No. DATE AMOUNT CURRENCY

FDR 1/90B 18/10/1999 22,738,500 BIF

DP 2/91/PB/FAD 19/12/1991 32,964,513 BIF

DP 02/91PB/FAD 06/02/1992 959,265 BIF

DP 03/91PB/FAD 06/02/1992 8,256,787 BIF

DP 04/91PB/FAD 06/02/1992 3,514,275 BIF

DP 05/91PB/FAD 06/02/1992 1,336,200 BIF

DP 1/92PB/FAD 07/05/1992 3,967,938 BIF

DP 3/92/PB/FAD 30/09/1992 13,057,056 BIF

DP 5/92/PB/FAD 30/09/1992 256,021.72 FRF

DP 6/92/PB/FAD 18/10/1992 8,467,482 BIF

DP 4/92/PB/FAD 24/11/1992 390,475 BIF

DP 07/92 15/12/1992 85,850,94 DEM

DP 3/PB/92 15/12/1992 31,403,272 BIF

DP 08/92 22/12/1992 3,012 GBP

DP 09/92 22/12/1992 20,921 BEF

DP 10/92/FAD 08/01/1993 3,991,663 BIF

DP 3/92 (COMPL 19/01/1993 20,181,722 BIF

DP 11/92/FAD 18/03/1993 512,043.43 FRF

DP 12/92/FAD 28/04/1993 64,506.71 USD

DP 2/92/FAD 17/06/1993 2,028,295 BIF

DP 13/92/PB/F 28/06/1993 16,678,996 BIF

DP 14/93/PB 19/07/1993 1,582,083 BIF

DP 17/PB 19/07/1993 4,027,761 BIF

DP 21/PB/FAD 24/09/1993 9,294,500 BIF

DP 19/PB/FAD 05/10/1993 621,555 BEF

DP 20/93/FFAD 05/10/1993 5,986,935 BIF

DP 2/92/COMPL 14/10/1993 4,001,631 BIF

DP 24/PB/FAD 22/12/1993 3, 354, 908 BIF

DP 22/93/FAD 07/01/1994 7,028 GBP

DP 23/93/FAD 07/01/1994 48,815 BEF

DP 26//93/FAD 25/01/1994 17,599,714 BIF

DP 27/93/FAD 25/01/1994 9,581,297 BIF

DP 19(COMPL) 03/02/1994 514,740.18 BEF

DP 25/93/FAD 18/02/1994 103,405.08 FRF

DP 28/93/FAD 28/12/1994 200,318.88 DEM

RG F93/0193-1 29/03/1994 128,724 USD

DP 31/94/FAD 28/04/1994 59,248.80 FRF

DP 30/93/FAD 28/04/1994 11,683,894 BIF

RG N° F93/0193-2 13/06/1994 109,650.88 USD

DP 29/93/FAD 14/07/1994 69,061.65 BEF

DP 15/PB/FAD 14/07/1994 11,181,070 BIF

DP 30/93 (COMPL) 19/09/1994 2,743,527 BIF

DP 36/94/FAD 09/01/1995 554,114 BIF

DP 35/94/FAD 09/01/1995 3,596,250 BIF

DP 34/94/FAD 19/01/1995 11,173,064 BIF

DP 33/PB/FAD 19/01/1995 17,745,091 BIF

DP 37/94/FAD 31/01/1995 39,499.25 FRF

DP 18/PB/FAD 13/06/1995 485,000 BIF

DP 9/95/FAD 23/06/1995 8,026,282 BIF

DP 40/95/FAD 23/06/1995 14,875 USD

DP 38/PB/FAD 24/07/1995 11,019,881 BIF

DP 41/95/FAD 14/08/1995 4,440,318 BIF

DP 42/95/FAD 13/08/1995 2,044,933 BIF

DP 44/96/FAD 04/04/1996 2,547,187 BIF

Page 28: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 2

Page 2 / 3

DP 45/96/FAD 12/04/1996 2,547,187 BIF

DP 46/96/FAD 12/04/1996 15,052.35 USD

DF 32/FAD/94 28/05/1996 108,585,261 BIF

DP 43/FAD/95 07/06/1996 12,464,633 BIF

DP 47/96/FAD 24/06/1996 2,547,187 BIF

DP 48/96/FAD 09/07/1996 3,471,289 BIF

DP 51/96/FAD 11/10/1996 2,547,187 BIF

DP 49/96/FAD 04/11/1996 78,835 SEK

DP 54/96/FAD 04/12/1996 6,542.53 USD

DP 55 - 61/ FAD 04/11/1997 10,280,002 BIF

DP 62/FAD 04/11/1997 4,876,714 BIF

DP 57/96/FAD 21/11/1997 189,937 SEK

DP 60/97/FAD 03/02/1997 4,459,500 BIF

DF 63/97/FAD 03/02/1997 148,797,985 BIF

DP 63/97/FAD 03/02/1997 31,655 SEK

DP 67/98/FAD 29/10/1998 1,148,750 BIF

DF 65/FAD/98 07/12/1998 93,051,968 BIF

DP 69/99/FAD 03/03/1999 3,227,959 BIF

FDR 1/90B 18/10/1999 22,738,500 BIF

DP 70/99/FAD 19/07/1999 13,500 FRF

DP 64-68/98 02/08/1999 3,446,250 BIF

DP N-73/99/FAD 05/11/1999 34,547,800 BIF

DP 75 20/06/2005 80,967 USD

DP 52 21/06/2005 2,190,000 BIF

DP 74 22/06/2005 2,297,500 BIF

DP 63 22/06/2005 5,110,000 BIF

DP 76 09/07/2005 7,500 USD

DP 77 09/07/2005 4,500 USD

DP 02/05 05/09/2005 11,854,200 BIF

DP 01/06 05/09/2005 45,713,700 BIF

DF 03/06 07/09/2006 400,000,000 BIF

DF 05/06 11/04/2006 49,724,000 BIF

DP 06/06 12/04/2006 13,174,500 BIF

DP 09/06 12/04/2006 13,000 USD

DP 07/06 05/05/2006 173,300,000 BIF

DP 09 05/05/2006 71,550,000 BIF

DP 04/06 05/05/2006 153,350,000 BIF

DP 10/06 06/06/2006 11,742,000 BIF

DF 12/06 06/06/2006 405,502,476 BIF

DP 13/06 06/06/2006 12,000 USD

DP 14/06 06/072006 22,750 USD

DP 15/06 01/09/2006 193,700,000 BIF

DP 16/06 12/09/2006 20,548,500 BIF

DP 19/06 20/09/2006 61,801 USD

DP 18/06 20/09/2006 78,400,000 BIF

DP 20/06 19/10/2006 16,900 USD

DP 21/06 31/10/2006 14,750,000 BIF

DP 17/06 09/12/2006 570,000,000 BIF

DP 22/06 29/12/2006 16,250 USD

DP 24 06/02/2007 25,687 USD

DP 26 14/02/2007 13,000 USD

DP 23 01/03/2007 14,677,500 BIF

DP 28/07/PB 08/03/2007 11,742,000 BIF

DP 25/06/PB 27/03/2007 16,900 USD

DP 30 27/03/2007 33,597 USD

DP 31 27/04/2007 29,521,270 BIF

DP 32 27/04/2007 38,671,392 BIF

DP 34 27/04/2007 24,000,000 BIF

DP 36 11/06/2007 8,130,160 BIF

PF 35/07/PB 10/07/2007 679,339,021 BIF

DP 37 17/07/2007 40,452,334 BIF

DP 38 10/09/2007 22,862 USD

Page 29: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 2

Page 3 / 3

DP 41 12/09/2007 41,862,400 BIF

DP 42 11/09/2007 106,692,355 BIF

DP 43 11/09/2007 98,323,329 BIF

DP 30 19/09/2007 57,400,000 BIF

DP 44 08/10/2007 2,032,540 BIF

DP 45 09/10/2007 3,040,810 BIF

DP 46 09/10/2007 3,040,810 BIF

DP 51 06/11/2007 27,372 USD

DP 50 07/11/2007 160,956,778 BIF

DP 49 07/11/2007 150,874,387 BIF

DP 53 07/11/2007 53,900 EUROS

DP 48 05/12/2007 2,032,540 BIF

DP 57 05/12/2007 37,736,654 BIF

DP 56 05/12/2007 61,472,374 BIF

DP 54 11/12/2007 188,970,000 BIF

DP 55 11/12/2007 41,000,000 BIF

DP 52 20/12/2007 397,740,874 BIF

DP 40 28/12/2007 31,074,040 BIF

DP 63 18/01/2008 2,416,942 BIF

DP 62 18/01/2008 39,445,013 BIF

DP 61 18/01/2008 73,170,762 BIF

DP 39 18/01/2008 7,250,317 BIF

DP 60 18/01/2008 2,032,540 BIF

DP 65 06/02/2008 16,044,660 BIF

DP 64 13/02/2008 427,694,820 BIF

DP 59 26/02/2008 33,676,880 BIF

Page 30: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annx 3

Page 1 / 2

BURUNDI

Calculation of internal rate of return

BUTUTTSI AGROPASTORAL DEVELOPMENT PROJECT

- The economic analysis was conducted over a 35-year period, that is 17 years after project closure.

- The project’s economic costs, investment and operating costs are the actual costs provided by the project’s accounting department. Only agriculture- related gains

were considered in the analysis.

- The prices used are financial prices. The capital opportunity cost (COC) used is 15 %.

Year Actual

disbursement

ADF Disbursement in BIF

IFAD

Disbursement

in BIF PDAL OPERATING COST

FARMER INVESTMENT TOTAL COST TOTAL INCOME CASH FLOW

Government (BIF )

1990 0 25,506,443 19,089,761 82436472 5668577 132,701,253 94,960,583 -37,740,670 1991 0 32,469,894 43,606,519 86935188 35605067 198,616,668 97,897,508 -100,719,160 1992 0 92,231,576 103,191,406 91433904 31524713 318,381,599 100,925,266 -217,456,333 1993 0 113,696,050 147,453,067 95932620 30146278 387,228,015 104,046,666 -283,181,349 1994 0 163,927,502 210,471,514 100431336 22620833 497,451,185 107,264,604 -390,186,581 1995 0 69,397,804 28,436,952 104930052 46129000 248,893,808 119,463,716 -129,430,092 1996 0 147,963,160 38,822,772 109428768 32261894 328,476,594 149,090,783 -179,385,811 1997 0 24,267,271 141,160,544 113927484 15361424 294,716,723 136,906,215 -157,810,508 1998 0 288,300,365 78,354,022 118426200 61430880 546,511,467 128,524,481 -417,986,986 1999 0 46,990,764 200,876,089 122924916 76945175 447,736,944 158,079,030 -289,657,914 2000 0 0 66,840,403 127423632 128973792 323,237,827 155,630,026 -167,607,801 2001 407,873,374 0 0 131922348 96958869 636,754,591 152,091,876 -484,662,715 2002 407,873,374 0 0 136421064 22842462 567,136,900 149,196,392 -417,940,508

Page 31: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annx 3

Page 2 / 2

2003 407,873,374 0 0 140919780 21278667 570,071,821 147,464,192 -422,607,629 2004 407,873,374 0 0 145,418,496 20327680 573,619,550 151,827,957 -421,791,593 2005 0 389,635,776 0 149,917,212 20327680 559,880,668 583,270,246 23,389,578

2006 0 1537601835 0 154414728 20327680 1,712,344,243 1,390,700,420 -321,643,823

2007 0 2998304625 0 159047170 20327680 3,177,679,475 1,973,970,666 -1,203,708,809

2008 0 189,754,744 0 163818585 20327680 373,901,009 2,372,663,437 1,998,762,428

2009 0 0 0 168733143 1,479,001,940 1,647,735,083 2,502,608,903 854,873,820

2010 0 0 0 173795137 1,956,559,761 2,130,354,898 2,632,783,669 502,428,771

2011 0 0 0 179008991 2,096,138,146 2,275,147,137 2,762,843,785 487,696,648

2012 0 0 0 184379261 2,235,736,162 2,420,115,423 2,892,903,901 472,788,478

2013 0 0 0 189910639 2,375,354,398 2,565,265,037 3,022,761,167 457,496,130

2014 0 0 0 195607958 2,514,993,462 2,710,601,420 3,153,024,133 442,422,713

2015 0 0 0 201476197 2,654,653,977 2,856,130,174 3,339,078,999 482,948,825

2016 0 0 0 207520483 2,794,336,588 3,001,857,071 3,520,562,865 518,705,794

2017 0 0 0 213746097 2,934,041,958 3,147,788,055 3,711,188,731 563,400,676

2018 0 0 0 220158480 3,073,770,769 3,293,929,249 3,897,243,597 603,314,348

2019 0 0 0 226763234 3,213,523,724 3,440,286,958 4,083,298,463 643,011,505

2020 0 0 0 233566131 3,353,301,548 3,586,867,679 4,269,353,329 682,485,650

2021 0 0 0 240573115 3,493,104,986 3,733,678,101 4,455,408,195 721,730,094

2022 0 0 0 247790309 3,632,934,807 3,880,725,116 4,641,463,061 760,737,945

2023 0 0 0 255224018 3,772,791,803 4,028,015,821 4,827,517,927 799,502,106

ERR 6%

Page 32: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 4

Page 1 / 2

ORGANISATION CHARTS

BAPDP ORGANISATION CHART AT PROJECT START (in 1990)

RD DIVISION ANIMAL PRODUCTION DIVISION LAND DEVELOPMENT DVISION SEED PRODUCTION

DIVISION

PERSONNEL

DIVISION

ROADS AND INFRASTRUCTIURE

DIVISION

T/E DIVISION ANIMAL HEALTH DIVISION WATERSHED AND SWAMP

DIVISION

INPUT DIVISION ACCOUNTING

DIVISION

INFRASTRUCTURE MAINTENANCE

DIVISION

GROUP PROMOTION DIVISION CROP DIVISION SUPPLIES DIVISION

SYLVICULTURE AND AGROFORESTRY DIVISION

LEGEND :

S.T.A. : Senior Technical Adviser

T.A. : Technical Adviser

R/D-T-E : Research-Development-Training-Extension

MINISTERY OF AGRICULTURE AND

LIVESTOCK

DIRECTORATE OF MOBILIZATION FOR SELF-

RELIANT DEVELOPMENT AND AGRICULTURAL

EXTENSION

DEPARTMENT OF BUTUTSI AGRO-SYLVO-

PASTORAL PROJECT

CREDIT UNIT + TECHNICAL ADVISER MONITORING EVALUATION AND

PLANNING UNIT + STA

SECRETARIAT

INFRASTRUCTURE SERVICES

ADMINISTRATION AND

MANAGEMENT SERVICE

+ T.A.

CROP PRODUCTION

SERVICE

LAND PROTECTION

SERVICE

LIVESTOCK SERVICE

+ TECHNICAL

ADVISER

R/D-T-E SERVICE

CARTAGE

Page 33: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 4

Page 2 / 2

BAPDP ORGANIZATION CHART (Current)

MINISTRY OF AGRICULTURE

AND LIVESTOCK DIRECTORATE OF AGRICULTURAL EXTENSION

MONITORING COMMITTEE

STEERING COMMITTEE

BUTUTSI APDP MANAGEMENT SECRETARIAT

CARTAGE

LIAISON OFFICE

WOMEN

ACTIVITES SERVICE

RURAL ROADS AND INFRASTRUCTURE SERVICES

AGROFORESTRY AND LAND PROTECTION SERVICE

Livestock

Service

PLANT

PRODUCTION

SERVICE

ADMINISTRATION

AND

MANAGEMENT

SERVICE

ACCOUNTING

PERSONNEL

STOCKS AND SUPPLIES

TRAINING AND EXTENSION &

MONITORING –EVALUATION

AND

PLANNING UNIT

SEED AND

FOODCROP

PRODUCTION

DIVISION

GENETIC

IMPROVEMENT

DIVISION

ANIMAL

HEALTH

DIVISION

ANIMAL PRODUCTION

DIVISION

AGROFORESTRY

DIVISION

RURAL

TRACKS

DIVISION

SOCIAL

ACTION

Page 34: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 5

Page 1/ 3

BURUNDI

BUTUTSI AGROPASTORAL DEVELOPMENT PROJECT

(APDP-BUTUTSI)

Evaluation and performance rating

Form IP 1

Implementation Performance

Component indicator Score

(1-4)

Remarks

1. adherence to implementation

schedule

1 The project did not comply with its implementation schedule.

Initially scheduled for a 5-year period, the project spanned 18 years.

This is due to the socio-political crisis that rocked the country from

1993 to 1996 and to Bank and IFAD sanctions for arrears.

2. Compliance with costs 2 There were no cost overruns.

3. Compliance with rules 3 All loan conditions were met within deadlines. Bank procurement

rules were followed and complied with.

4. Adequacy of Monitoring/

evaluation and reporting

2 Project management was deemed satisfactory. Project progress and

audit reports were submitted to the Bank.

5. Satisfactory operations SO NA

Total 8

Overall rating of implementation

performance

2 The overall project implementation performance is rated as fair

Form BP 1

Performance by the Bank

Component indicator Score

(1-4)

Remarks

1. Identification 2 Two IFAD identification missions were organized in 1983 and 1985

and a joint IFAD/ADF identification mission was conducted in June

1987. The projet was a Government priority.

2. Preparation 2 The final project preparation was made by the FAO Investment Centre

(IC). The project statement and matrix were not produced.

3. Appraisal 2 A project appraisal mission was fielded by ADF in 1988. The project

matrix was not produced.

4. Supervision 2 14 Supervision missions were carried out with inadequate composition

of teams. They were interrupted by teh disturbances in the country.

However, they were appreciated by the borrower and provided an

opportunity to help resolve project management issues.

Total 8

Overall Bank performance

rating

2 Overall Bank performance is rated fair.

Page 35: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 5

Page 2/ 3

Form PO 1

Project Outcome

Component Indicators Score

(1-4)

Observations

1. Relevance and achievement of objectives 3

i) Macro-economic Policy 3 The project has contributed to socio-economic development

and poverty reduction, consolidation of food security,

employment creation, increase in population’s income.

ii) Sector-based policy 3 The project contributes significantly to agricultural sector

development.

iii) Physical achievement 3 The project outputs are significant and meet its physical

objectives.

iv) Financial component 2 The final project cost is lower than estimated at appraisal.

v) Poverty reduction, social impact and gender 4 The project has had a very positive impact on poverty

reduction and the social conditions of the population,

particularly those of rural women through income-generating

activities.

vi) Environment 3 The populations were highly sensitized concerning the

production of agroforestry plants in Watershed protection.

They received training on land management. The agro-sylvo-

zootechnic integration approach was introduced.

vii) Private sector Development 3 The project initiated private seed multiplication operators who

will take over during the post-project period with a view to

perpetuating the activity. The marketing of inputs and

veterinary drugs has already been handed over to private

operators.

2. Institution building 2.7

i) Institutional framework 3 The project contributed to the forming of farmers’ associations

and PDAL and ISABU supervisors, as well as senior

administrative staff of the province in order to ensure greater

sustainability.

ii) Integrated financial management Systems,

including audit systems

2 The borrower kept separate accounts for the project, and the

loan expenditure was audited. There was no project auditing

during the initial years

iii) Technology transfer 3 Seed production and multiplication techniques as well as herd

management techniques were transferred to farmers-

stockbreeders.

iv) Staffing with qualified personnel (including

rotation), training and counterpart personnel

3 Staff were provided by PDAL.

3. Sustainability 2.2

i) Ongoing commitment of the borrower 3 The borrower fulfilled its responsibility with regard to

provision of funds (staff salaries) during the disbursement

period. PDAL is involved as a stakeholder in the monitoring of

activities.

ii) Environmental policy 2 The legal framework exists, but is compromised by inadequate

institutional capacities of the Ministry of Agriculture.

iii) Institutional framework 3 The project set-up is integrated into the existing organisation

of MINAGRIL and cooperates with technical partners (FAO

and ISABU).

iv) Technical viability and staffing 3 Farmer-stockbreeders’ associations cooperate closely with

technical staff of BURURI PDAL.

v) Financial viability and cost recovery

mechanisms.

2 Farms generate good incomes

vi) Economic viability 3 Farmers contribute to development of the Bururi Province

through income generated from milk and agricultural

production.

Page 36: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 5

Page 3/ 3

vii) Environmental viability 2 Agroforestry plantations enable erosion control and protection.

The use of organic manure considerably mitigates the adverse

impacts of the few chemical fertilizer applications.

viii) Farm sustainability and maintenance

(availability of funds to defray recurrent cost,

spare parts, rural roads).

3 Farmer-stockbreeders’ associations have already started

bearing the cost of agricultural inputs procurement using

proceeds from produce sales (milk, beans). The DPAL

provides supervision in accordance with the role assigned it in

the province.

4. Economic rate of return 1 The project’s economic internal rate of return at completion is

6% as compared to 17.7% estimated at appraisal.

TOTAL 9.9

Overall rating of outcomes 2.6 The project is rated overall as satisfactory.

Page 37: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 6

BURUNDI

Activities conducted as part of Women’s Income-Generating Activities

Unit Projection Actual Rate (%) Men Women Milling Number 6 6 100 6 61 Rehabilitation of

input marketing

warehouses

Number 3 3 100 - -

Rehabilitation of

the salt block

manufacturing

house

Number 1 1 100 - -

Market gardening Thousands of sachets 20 20 100 597 2736 Bee-farming Number of

associations

15 15 100 147 46

Poultry-farming Number of

associations

41 41 100 201 244

Creating new Number 720 868 120 3659 6896 Capacity building Number of themes 15 11 73 458 970 Fertilizer

marketing

Tonnes 130 136.2 104 202 7

As regards poultry-farming, 41 associations received 4150 chicks,out of the 4150 chicks envisaged, that is 100 %. Concerning bee-farming,

2250 modern hives were disseminated to a level of 100 % of projections. Data from previous years (1990-2004) are not available, given that

the component started up at a time when disbursements had ceased. Despite implementation of scheduled activities, existing groups and

those formed later (2244) were trained on farm organization and management.

Page 38: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 7

BUTUTSI AGROPASTORAL DEVELOPMENT PROJECT

(APDP-BUTUTSI)

RECOMMENDATIONS AND FOLLOW-UP MATRIX

Recommendations Observations Recommendations and

Responsibilities

Project Design

*Project consistency : Beneficiaries

adhered to project implementation The project achieved its objectives To ensure sustainability, Government should put

in place a monitoring and supervision

mechanism * Project Preparation: the project was

designed without reference study There is need to conduct a socio-

economic survey during the project

implementation phase.

A preliminary study needed to determine

status-quo and needs.

*Appraisal: The unit provides periodic reports

on a regular basis but the M&E

system was not in place

Put in place the evaluation system at project on-

set in order to measure project performances at

any time. *Implementation It took the project 12 months to get

started. Conditionality for initial disbursement should be

put in place early enough.

Technical implementation

*Technical outputs: All Technical outputs were

satisfactory with the exception of

performance of

NDEREGO entreprise.

Exclude NDEREGO entreprise from any future

ADF-financed procurement.

Financial Implementation

*Total project cost Reduced after IFAD withdrawal Avoid financing of a component by more than

one donor. *Financial Management Proper keeping of financial

statements/ledgers and proper

financial training of project

financial officals and management

Need for recruitment of trained and competent

personnel.

* Annual audits Audits conducted and annual

reports submitted on a regular

basis except during years of

difficulty.

Systematically conduct audits to ensure better

project management.

*Disbursement All disbursements were made

even though processing periods are

sometimes long.

The Bank should ensure speedy processing of

disbursement requests.

* Project valuation and sustainability output consolidation undertaken by

PDAL. The restocking of animal

population through the CSC has

enabled farmers-stockbreeders to

own livestock.

Government will support and consolidate

associations.

Page 39: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annexe 8

BURUNDI

BUTUTSI AGROPASTORAL DEVELOPMENT PROJECT

(APDP-BUTUTSI)

INFORMATION SOURCES

INFORMATION TYPE SOURCES

Technical Implementation

Status of work Progress Reports by project implementation unit

Results from field visits and working sessions of the project completion

mission

General data Reports from Project Implementation Unit

Results from field visits and working sessions of the completion mission with

several project stakeholders

Bank supervision Mission reports

Financial data

Project cost trend Bank and IFAD evaluation report and project implementation unit report –

Bank disbursement service.

Procurement list Reports from Project Implementation Unit

Audit reports

Disbursements Bank disbursement report

Audits Borrower’s audit report

Economic and Financial Analyses

Price Findings from field visits and consultant’s monitoring-evaluation reports

Technical Operations Data Results from field visits and working sessions of the project completion

mission

Bank’s appraisal report

Social and Environmental Impact Results from field visits and working sessions of the completion mission with

farmer-stockbreeders

Bank’s appraisal report

Bank’s supervision reports.

Page 40: REPUBLIC OF BURUNDI - African Development Bank...project scaled up from 90,000 BIF/individual to 213,326 in the Bututsi region 2.1 The main crops’ yield soared from 14% to 100%

Annex 9

BURUNDI

BUTUTSI AGROPASTORAL DEVELOPMENT PROJECT

(APDP-BUTUTSI)

OBSERVATIONS OF THE BORROWER AND EXECUTING AGENCY

(Observations requested with deadline set for 15 June 2009. No response from

Government.)