Upload
anshu-shah
View
217
Download
0
Embed Size (px)
Citation preview
8/6/2019 Report of Work
http://slidepdf.com/reader/full/report-of-work 1/2
During the said period I was reporting to Shri P Barik ,SO/F and responsible for
CM/PM/BM and up keeping of Group –C related equipments . EMU Group-C comprisesFollowing systems:
1. 220KV Switchyard and its associated equipments.
2. Oil filled Power Transformers including 3 MVA auxiliary transformers.3. 16.5 KV IPBD, SPPT and NGTS.
4. Relay Test Lab.
5. Auto transfer and station Billing & Metering system.6. Static excitation system for Main Generator.
7. Synchronizing scheme for 220KV, 16.5KV, 6.6KV and 415V system.
8. CWPH area electrical equipment including IDCTS fan motors
9. PWPH, DM Plant and PTP area electrical equipment.10. Station elevators.
11. Station equipment Earthing and lightning protection system.
During the above said period following major works were carried out.1. Start up activities of electrical system after EMCCR work which includes Gen.
excitation system checks, Main generator protection checks, GT CB checks, Power connections of GT, UT and SPPT. Preparation for main generator OCC and SCC test,
which includes Dummy load test, Implementation of Jumpers, Preparation of Data
sheet for protective relays and excitation circuit. Normalizations of Jumpers provided
during OCC and SCC test and unit synchronization.2. Modifications of 220 KV Bus I which includes cutting of 220 KV Bus at three
locations, Installation of flexible Clamps and corona ring and replacement of bus
support clamps.3. Protection circuit checks during commissioning of replaced 6.6 KV Class III and
415 V class III and II switchgears which includes, a) Protective numeric relaycalibrations and setting, Programmable Scheme Logic (PSL) preparation. b) CTs andPTs Checks c) Protection logic checks c)Phasing out and synchronization checks.
4. Installation and commissioning of New 3 MVA transformer which includes
installation of transformer on foundation, laying and connections of power andcontrol cables, Transformer commissioning checks, Hot oil circulation and putting
into service.
5. Investigation of various incidences,
a) Tripping of PFP on stalling protection. b) Tripping of moderator pump on Earth fault.
c) Tripping of ECCS pumps during its routine tests.
d) Tripping of 220 KV line on Back up earth fault protections.e) Actuation of Class A2 due to start up over current protection during OCC test
6. 11KV distribution Board A and B Protection circuit commissioning and relay
setting work.7. Detail Investigation of Unit trip on 87 GT protection which includes Primary
injection test, all Power Equipment like GT/UT/IPBD/Excitation transformer
/SPPT/NGT/CT LAs/Bushing/String Insulator checks, HV test of IPBD and 220 KV
8/6/2019 Report of Work
http://slidepdf.com/reader/full/report-of-work 2/2
circuit, Complete checks of protective circuit like CT loop checks, Relay checks, CT
terminal and JB inspections.
8. Box up of G T and UT after its overhauling work and its electrical and oil test.9. PM checks of GT, UT and tech specification related 6.6 KV and 415 V Class III
and II load’s relay calibration checks, GT Bay PM checks during Unit # 2 BSD.
10. Preparation of tender for station elevators and Condition monitoring checks of electrical equipments.
11. Condition monitoring checks of electrical equipments which includes DGA, Oil
test as per IS, LA third Harmonic measurements, Transformer electrical tests, HTmotor C and DF Test.
12. Execution of WO For Elevator maintenance,220 KV Switchyard maintenance,
CM checks of electrical equipments,Thermography of electrical equipments.
13. Co-ordination for Inspection Electrical Installation through CEA and ISO relatedwork.
14. Procurements of various spares related to the system, its up keeping and
verifications.
15. Documents work like preparation of maintenance reports, data entry for CMchecks, QAMS updation, ECMS Updation and CMMS entry.
16. Revision of Maintenance procedure and checklist Report.17. Preparation of OERC documents review report and its compilation. Presented on
‘Power transformer reliability SOER’ in OERC.
18.Participated in Protective relay workshop at TAPS.
Completion of Tech. Spec related PM checks.
Availability of Group –C equipments
220 KV bus II Modification similar to Bus I
Updation of PM procedure
220 KV CT Replacement/Refurbishments
220 KV DS Overhauling work
220 KV CB Overhauling work.
Numeric relays for main generator protection