Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
1
REPORT OF OVERSIGHT COMMITTEES REPORTING DIRECTLY TO THE COUNCIL allowed in terms of Section 8(1)(f)(b)(i) of the Rules and Orders for consideration by the Council Agenda of the Council Meeting of the CITY OF TSHWANE METROPOLITAN MUNICIPALITY which will be held in the Council Chamber, Sammy Marks Conference Centre, corner Madiba and Lilian Ngoyi Streets, Pretoria, on THURSDAY, 30 JUNE 2016, at 10:00 to consider the matter as set out in the agenda hereafter.
PAGES F. FROM THE SECTION 79 OVERSIGHT COMMITTEE:
FINANCE: 15 JUNE 2016 ……………………………………………… 4-39 ALDERWOMAN AWMK MOSUPYOE-LETSHOLO SPEAKER 24 June 2016
2
F. REPORT TO COUNCIL
The Speaker, in terms of Section 8(1)(f)(b)(i) of the Rules and Orders, proposes to Council that the reports contained in this agenda, from the Meeting of the Section 79 Oversight Committee: Finance held on 15 June 2016, be submitted for consideration, and subsequently requests the Chair of Chairs, Councillor RJ Kekana, to present the report to Council.
3
COUNCIL AGENDA: CITY OF TSHWANE METROPOLITAN MUNICIPALITY: 30 JUNE 2016 REPORT TO COUNCIL INDEX (The recommendations appear on the pages indicated in brackets)
Pages F. FROM THE SECTION 79 OVERSIGHT COMMITTEE:
FINANCE: 15 JUNE 2016
1. Office of the Speaker Annual performance report of the Section 79 Oversight Committee: Finance for the Financial Year 2015/16…………………………………..…. 4–39(31) (From the Section 79 Oversight Committee: Finance: 15 June 2016)
*******
4
COUNCIL AGENDA: CITY OF TSHWANE METROPOLITAN MUNICIPALITY: 30 JUNE 2016 REPORT TO COUNCIL JRK THEMA (012 358 1723) SECTION 79 OVERSIGHT COMMITTEE: FINANCE: 15 JUNE 2016 1. OFFICE OF THE SPEAKER
ANNUAL PERFORMANCE REPORT OF THE SECTION 79 OVERSIGHT COMMITTEE: FINANCE FOR 2015/2016 (From the Section 79 Oversight Committee: Finance: 15 June 2016)
1. PURPOSE
The aim of this report is to provide an overview and reflection on the performance of the Section 79 Oversight Committee: Finance for the period July 2015 to June 2016. Furthermore, this report will identify areas where there is a need for improvement in order to achieve the goals as set by the Committee in its process plan, as attached.
2. STRATEGIC OBJECTIVES This report addresses the following Strategic Objectives of the City of Tshwane:
Strategic Objective 4: “Promote good governance and an active citizenry”.
Strategic Objective 5: “Improved financial sustainability” 3. BACKGROUND
The Governance Model of the City of Tshwane as per Council resolution dated 9 June 2011, led to the re-establishment of Council Oversight Committees that were initially established through Section 80 of the Municipal Structures Act. The main objective of this process was to enhance efficiency, accountability and responsiveness. This Model focused on assigning different roles, to ensure clear separation of powers and functions between Council and the Executive, in order to enhance and strengthen Council’s oversight role. The activities conducted by the Section 79 Oversight Committee: Finance, are in accordance with the Governance Model. This report, in summary, highlights findings from meetings and inspections conducted by the Committee, in compliance with its oversight mandate, as per the provisions of its Terms of Reference.
4. DISCUSSION
The Section 79 Oversight Committee: Finance performs its functions in order to render an advisory legislative role to Council. In executing its duties, the Committee has a responsibility of promoting the principles of good governance and monitoring compliance with provisions of legislation governing local government, in particular, the Municipal Finance Management Act.
5
This report will cover information pertaining oversight activities conducted by the Committee for the period July 2015 to June 2016, including:
4.1 Supporting legislation; 4.2 Terms of reference; 4.3 Committee membership; 4.4 First quarter performance; 4.5 Second quarter performance; 4.6 Third quarter performance; 4.7 Fourth quarter performance; 4.8 Application of policies and By-Laws; 4.9 Analysis of the process plan; and 4.10 2015/16 Performance of the Department.
4.1 SUPPORTING LEGISLATION
The work of the Oversight Committee is guided mainly by the following legislation:
Constitution of the Republic of South Africa, Act 108 of 1996;
Local Government Municipal Systems Act, Act 32 of 2000;
Local Government Municipal Structures Act, Act 117 of 1998;
Local Government Municipal Finance Management Act, Act 56 of 2003; and
Intergovernmental Relations Framework Act, Act 13 of 2005.
In order to align with the new section of the law that informed the establishment of Oversight and Standing Committees, Council adopted terms of reference for each Committee. The Terms of Reference below are for the Finance Section 79 Oversight Committee:
4.2 TERMS OF REFERENCE
Specific Functions The Section 79 Oversight Committee: Finance has three functions namely: 1. Scrutinising reports in relation to its core function referred to it by Council emanating
from the Executive Mayor and/or Mayoral Committee and advising Council;
2. an oversight role in relation to its core function on the performance of the executive on behalf of Council; and
3. in relation to its core function, an advisory legislative role.
4.3 COMMITTEE MEMBERSHIP
In line with the Municipal Systems Act 59 (1)(2)(3) as approved by Council, the following amendments were made on representation of the Democratic Alliance Councillors.
DA COUNCILLOR REPLACEMENT
EFFECTIVE DATE
Khumalo, Z Roos, A 14 January 2016
Campbell, AW. Smith, F 08 October 2015
6
The representation of political parties in the Oversight Committee is determined in the manner outlined in the terms of reference quoted herein and below:
(Unaltered) F1. MEMBERS In terms of Section 79(1)(b) the Council “may appoint” the members from among the Council’s members (ordinary Councillors). In accordance with the Hare Quota in conjunction with the Largest Remaining Formulae, Section 79 Committees comprise of 20 members (Chairperson included), proportionally composed as follows:
AFRICAN NATIONAL CONGRESS (ANC)
DEMOCRATIC ALLIANCE (DA)
AFRICAN CHRISTIAN DEMOCRATIC PARTY (ACDP)
KEKANA,RJ (CHAIRPERSON) DLAMINI, BL FLEMING, DL KATAKE, NS LEBESE, OS MAREDI, F MATHENJWA, N MORUDU, MGR NGWENYA, C RAMMUSHI, J ZITHA, P
ROOS, A
FOURIE, ML MIDDELBERG, L OSMAN, A SMITH, F RAMOHOEBO, R VAN DEN HEEVER, C VISSER, G
KISSOONDUTH, A
4.4 First Quarter Performance
The Committee executed the following activities in this quarter to comply with the oversight mandate:
Meeting - 16 July 2015;
Meeting - 13 August 2015; and
Inspection-in-Loco – 10 September 2015. 4.4.1 Oversight Committee meetings
In the 1st quarter, the Committee held two meetings on 16 July 2015 and 13 August 2015. Below are the reports which were presented by the department and discussed. Status of the resolutions of these meetings is fully outlined in the attached Annexure A on resolution tracking.
7
a) 16 JULY 2015 COMMITTEE MEETING
Item Department Title of the report Author/ Initiator
Resolutions
1. Finance 2014/15 FY Annual performance report: Finance Oversight Committee & Draft Process Plan 2015/2016
JRK Thema
1. That cognizance be taken of the contents of this report.
2. That the Department of Finance submit a quarterly report to the Finance Oversight Committee on:
o Progress made in addressing challenges identified in Call Centres, Customer Care Walk-in Centres and Municipal Stores as reflected in this report.
o Funded and filled positions, to realise the strategic objectives of the City.
o Implementation of the Regionalisation Model, outlining funding and resources allocated, in order to accelerate service delivery.
o The interventions by Supply Chain Division to improve procurement processes and contractor management.
o That the provision of the legislation contained in the report be considered and complied with
o That the Departments submit presentations and reports to the Committee, in line with the provisions of the Rules and Orders By-law and Circular 9 Report Flow.
8
o That the challenges on page 31 (items 4.7 and 4.8) be removed and included in a separate Annexure to this report under the heading “Policies and By-Laws approved by Council that relates to the Oversight Committee: Finance.
o That for future references
the subject “Policies approved” by Council be included in the draft Programme/Business Plan for the City of Tshwane
That regarding the quarterly report on the Finance Oversight Committee, the following also be included in the draft Programme/Business Plan:
o Progress made in addressing challenges identified in Call Centres, Customer Care Walk-in Centres and Municipal Stores as reflected in this report.
o Funded and filled positions, to realize the strategic objectives of the City.
o Implementation of the Regionalization Model, outlining funding and resources allocated, in order to accelerate service delivery.
o The interventions by Supply Chain Division to improve procurement processes and contractor management.
9
3. That the following reports/ presentations originally submitted by Councillor ML Fourie be included in the draft Programme/ Business plan:
Supply Chain Management: Monthly
Analysis of creditor payments: Monthly:
o Overdue o Creditors paid
Tenders awarded and deviations.
Contract management.
Revenue Management: Monthly
o Age analysis of Debtors per Region/Ward/Suburb
o Credit control activities per Region/Ward/Suburb
o The following information should be included in the report:
o Number of electricity cut-offs instructions
o Number of successful electricity cut-offs.
o Number of electricity cut-offs not possible and reasons for failure to implement.
o Number of legal/authorised electricity re-connections.
o No responses to credit control actions.
o Cash Flow: Monthly o Budget control: Quarterly o Operating expenditure:
Actual v/s Budget o Capital expenditure;
Actual v/s Budget o Unauthorized expenditure o Fruitless and Wasteful
expenditure o Irregular expenditure o Monitoring of Legislative
Reporting Requirements and compliance: Monthly
10
o Customer Care and Call
Centre performance: Quarterly
o Human Resources: Quarterly
o Staffing and vacancies per staffing level.
o Training o Suspensions o Disciplinary actions
9. That the starting time of
meetings in the draft Programme/Business Plan be corrected to reflect the agreed time of 12:00 and that the dates of monthly Oversight meetings be included in the draft Programme/Business Plan
b) 13 AUGUST 2015 COMMITTEE MEETING
4.4.2 Inspection-in-Loco
The Committee conducted one Inspection-in-Loco during the first quarter of the 2015/16 financial year, on 10 September 2015 with a view to check whether the City’s capital projects are in line with the SDBIP. Zithobeni Sports Stadium, Refilwe Sports Stadium and Cullinan Library Park are capital projects which were visited by the Committee in Region 5 & 7. Through thorough discussions, the Committee decided not to visit the New Gazankulu Clinic due to the geographical distance, only Region 5&7 were visited. According to the 2014/15 SDBIP the Cullinan Library Park project only began in the third quarter of the 2014/2015 financial year.
a) Findings of the Inspection-in-Loco at Cullinan Library Park:
Item Department Matters
Considered
Author/ Initiator
Findings from the inspection
Resolutions
1. Sports and
Recreation
Inspection- in-
loco: Cullinan
Library Park
JRK Thema
Start Date:
12/05/14
Expected
completion:
22/10/15
That a financial
breakdown of costs for
the Cullinan Library and
ground works be
provided as well as a
breakdown of costs for
11
Budget Allocated
2014/15:
20 Million
Milestone/Status:
-Phase 1 bulk
earthworks
completed on 30
March 2015
-Relocation of
electrical cables in
progress as at 15
September 2015
-All concrete works
completed.
Brickwork and
plastering 80%
complete as at 15
September 2015.
-Mechanical
connections 40%
at 21 September
2015.
-Completion of
building structure.
65% at 30
September 2015.
-Internal/external
finishes to the
main building in
progress
-Practical
completion of the
external works at
30 October 2015
-General progress
was at 65%.
the upgrading of the
Zithobeni and Refilwe
stadiums.
12
Challenges at Cullinan Library Park: a) Delaying of vital construction information by the City of Tshwane’s architectural
services official servicing the project:
Programme: The delayed information provided by the architect to the professional team has interrupted the contractor to adhere to work according to the programme and timeframes. Budget: The contractor had to be granted various extensions of time with cost and this has a negative impact on the project. b) Budget shortfall: The project was exposed to the possibility of not having sufficient funds to be completed. Should the insufficiency persist, it could delay the completion of the project. c) Breakdown in negotiations between the sub-contractors and the main
contractor with regard to 25% local expenditure as per the Council resolution: Through back and forth negotiations with the local community, subcontractors, main contractor and interventions of the Tshwane’s Department, the project lost a total of 35 days due to stoppages caused by local community’s dissatisfaction of the project role. The Council resolution requires that 25% of the projects’ budget be spent on utilising local laborers, machinery and sub-contractors and this was the source of the conflict.
b) Findings of Inspection-in-Loco at Refilwe Stadium
Item Department Matters
Considered
Author/ Initiator
Findings from the inspection
Resolutions
2. Sports and
Recreation
Inspection- in-
loco: Refilwe
Sports Stadium
JRK Thema
Handover date:
22/05/2015
Expected completion
date:30/06/ 2016
Budget Allocated:
- R15 000 000
allocated
for 2015/16.
R79 750 (0.5%) actual
expenditure until 31/08/
2015. R14 920 250
(99.5%) remaining
Milestone/Status:
- 30/09/ 2014:
approval of
consulting team.
That a financial
breakdown of
costs for the
Cullinan Library
and ground works
be provided as
well as a
breakdown of
costs for the
upgrading of the
Zithobeni and
Refilwe stadiums.
13
Challenges at Refilwe Stadium: The following challenges together with the interventions took place:
Reduction in 2015/16 budget allocation resulting in contractual challenges;
Adjustment budget applied;
Six months delay in appointment of consultants and contractors by SCM division;
Departmental top management and MMC intervention took place;
Detailed planning and costing completed in one month to expedite project
implementation; and
Removal of existing structures that were not included in the drawings caused
unnecessary delays.
- October to
November 2014:
site survey, BoQ
and estimates, site
briefing, PSC,
procurement status
etc. 15/12/ 2014:
tender advertised
and site briefing
session with
contractors.
- June to May 2015:
implementation of
appointments.
- 20 June to 22/05/
2015- commence
with construction
- June 2016:
completion of all
works and site
handover.
14
c) Findings of Inspection-in-Loco at Zithobeni Stadium
Item Department Matters
Considered
Author/ Initiator
Findings from the inspection
Resolutions
1. Sports and
Recreation
Inspection- in-
loco: Zithobeni
Sports Stadium
JRK Thema
Handover date:
22 May 2015
Expected completion
date: 18 May 2016
Budget Allocated:
- R15 000 000
allocated for 2015/16
- R354344 (2.3%)
actual expenditure
until 3/08/ 2015
- R14 645 656 (97.7%)
Remaining
- Milestone/Status
Site establishment/
clearance 27/08/2015
- Boundary wall:
18/09/2015
- Guardhouse, ticket
booth: 25/09/ 2015
- Refuse area: 25/09/15
- Buildings under
pavilion: 12/12/2015
- Field earthworks, S/W
system:12/12/ 2015
- Soccer field, athletics
track: 26/03/2016
- Road works and
paving: 26/03/2016
That a financial
breakdown of costs
for the Cullinan
Library and ground
works be provided
as well as a
breakdown of costs
for the upgrading of
the Zithobeni and
Refilwe stadiums.
15
- Pavilion Extension:
29/04/2016
- Landscaping:
18/05/ 2016
Challenges at Zithobeni Stadium: The following challenges together with the interventions took place:
Reduction in 2015/16 budget allocation resulting in contractual challenges;
Adjustment budget applied;
Six months delay in appointment of consultants and contractors by SCM division;
Departmental top management and MMC intervention took place;
Detailed planning and costing completed in one month to expedite project implementation;
Removal of existing structures that were not included in the drawings caused unnecessary delays.
In this Inspection- in- loco the Committee resolved as follows: That a financial breakdown of costs for the Cullinan Library and groundworks be provided as well as a breakdown of costs for the upgrading of the Zithobeni and Refilwe stadiums.
4.5 SECOND QUARTER PERFORMANCE The Committee executed the following activities in this quarter to comply with the oversight mandate:
Meeting - 8 October 2015;
Meeting - 12 November 2015 (cancelled);
No meeting scheduled for December 2015.
4.5.1 Oversight Committee meetings In the 2nd quarter of 2015/16 Financial Year, the Committee held two meetings on 8 October 2015 and 12 November 2014. The reports below were presented by the department and discussed in the meetings held.
16
a) 8 October 2015 meeting:
b) 12 November 2015 Meeting: Councillor Oscar Mathafa was appointed by the Chairperson and Speaker to act as Chairperson of the Committee for the day, wherein the Rules and Orders By-Law, Section 4 (2) was contravened by the appointment. The meeting was aborted due to diverse interpretation of the said clause by various members of the Committee.
Item Department Matters considered
Author/ Initiator
Resolutions
1.
Department of
Finance
Challenges identified
at municipal stores
during the oversight
committee
inspections-in-loco
DCM: Dr.Ndivho Lukhwareni
That the Deputy City
Manager prepares a
proper report and
come and present the
report in person.
That an official letter,
signed by the
Chairperson of the
Oversight Committee:
Finance be directed to
the Office of the
Deputy City Manager
regarding the stores.
2. Economic Development
Tshepo 10000 SED: Themba Mhlekwa
That cognizance be taken of the above presentations and that electronic versions of the presentations be forwarded to members of the Committee in order to interrogate the matters in future
3. Department of
Finance
Presentation on the
turnaround strategy
in the Supply Chain
Division
Bongani Mntambo
That cognizance be taken of the above presentations and that electronic versions of the presentations be forwarded to members of the Committee in order to interrogate the matters in future
17
4.6 THIRD QUARTER PERFORMANCE 4.6.1 OVERSIGHT COMMITTEE MEETINGS
The Committee executed the following activities in this quarter to comply with the oversight mandate:
Meeting - 14 January 2016;
Meeting - 11 February 2016; and
Meeting – 10 March 2016. The Section 79 Oversight Committee meetings are held on a monthly basis as per the approved Annual Council Calendar. In this quarter, three (3) meetings were held as mentioned above of which the focus was to assess the performance of the department and to determine adherence to the Service Delivery and Budget Implementation Plan (SDBIP) by the Department. The details of these meetings are as follows:
a) 14 January 2016 Committee meeting:
Item Department Matters Considered
Author/ Initiator
Resolutions
1. Department of Finance
Supply Chain Management performance (Tenders over R10m)
Bongani Mntambo
That the matter be
further discussed in
the next meeting
and that accurate
information
regarding the
questions posed by
Councillors, be
given at the
meeting.
18
Item Department Matters Considered
Author/ Initiator
Resolutions
2. Department of Finance
Current staffing of the Finance Department
Bertha Maleka
That the
presentation
regarding the
organisational
structure of the
Finance Department
inclusive of
divisions,a
breakdown of
staffing levels as
well as challenges
experienced be
presented at the
next meeting of the
Oversight
Committee.
That feedback be
given at the next
meeting regarding
the skills and
capacity levels of
staff in order to
determine if they
comply with the
minimum competent
levels required by
the National
Treasury.
3. Department of Finance
Analysis of Debtors per region
Ronny Shilenge
That this presentation be presented at the next meeting.
19
Item Department Matters Considered
Author/ Initiator
Resolutions
4. Finance Oversight Committee
Mid Term Performance Report of the Committee
JKR Thema That cognisance be taken of the contents of this report. That the Finance Department allocate sufficient budget for capital projects. That the Rules and orders Bylaw need to be complied with as well as be reviewed to avoid diverse interpretation of the clauses and avoid wasteful expenditures
5. Department of Finance
Progress report on Call Centres
Mankiti Khaebane
That feedback be given at the next meeting regarding, inter alia, a dedicated priority line for Councillors and a query resolution report.
6. Office of the Speaker
Section 79 Oversight Committee: Finance-First Quarter Performance Report of the 2015/16 Financial Year
JRK Thema Chairperson ruled that this item be dealt with during the discussion of the Mid-Term Performance report.
b) 11 February 2016 Committee meeting:
Item Department Matters considered
Author/ Initiator
Resolution
1. Department of Finance
Financial Performance on Opex and Capex
ED: Nthabiseng Mokete
That a complete
report be submitted
at the next meeting,
bearing in mind that
the report might
already have served
before Council.
20
b) 10 March 2016 Committee meeting:
2. Department of Finance
MLAP, State of controls and Risk management within finance
ED: Dyalan Pillay
That cognisance be
taken of the
presentation on
Management Letter
Action Plan (MLAP),
State of Controls
and Risk
Management within
Finance.
That the mid-term
progress report on
the findings of the
Auditor General
Management letter
be further discussed
at the next meeting.
3. Department of Finance
Indigent Budget ED: Nthabiseng Mokete
That the report
regarding the
debtor’s analysis be
extended to include
the arrear accounts
of the formal
indigent.
Item Department Matters considered Author/ Initiator
Resolutions
1. Department of Finance
Staffing Matters: Group Financial Services
Bertha Maleka The Councillors
adopted the
presentation.
2. Department of Finance
Priority line for Councillors Acting SED: Mankiti Khaebane
That cognizance be taken of the presentation.
3.
Department of Finance
Debtors Ageing report
ED:Chris Thipe
That cognizance be taken of the presentation.
21
4.7 FOURTH QUARTER PERFORMANCE
The Committee executed the following activities in this quarter to comply with the oversight mandate:
Meeting - 8 April 2016 (rescheduled from 7 April 2016);
Meeting - 12 May 2016; and
Meeting - 10 June 2016.
4. Department of Finance
Age analysis per (Service CAT)
ED:Chris Thipe That cognizance be taken of the presentation.
5. Department of Finance
Debtors summary: Age analysis comparison
ED:Chris Thipe That cognizance be taken of the presentation.
6. Department of Finance
Regional Operational Centre Department Progress report on Regional Municipal Stores on findings by Section 79 Oversight Committee of Finance.
ED: Frans Manganye
That cognisance be taken on the actions taken to correct and improve the status of Regional Municipal Stores in all Regions of the City as per findings of Section 79 Oversight Committee on Finance during the respective Inspections-in-loco during January 2015 to June 2015. That cognisance be taken that the affected and responsible departments will continue working on the areas where improvement is not yet satisfactory.
22
As per approved Annual Calendar, the Committee was scheduled to hold its meeting on 7 April 2016, but the meeting was rescheduled for 08 April 2016 due to the State of the City Address. Below are the points that were highlighted in the meeting:
a) 8 April 2016 Committee meeting.
Item Department Matters considered
Author/ Initiator
Resolutions
1. Department of Finance
Tshepo 10000 SED: Thembeka Mphefu
That cognisance be taken of presentation regarding the Tshepo 10000 programme and that a progress report in this regard be submitted in July 2016
2. Office of the Speaker
Section 79 Finance Oversight Committee: Third Quarter Performance Report
JRK Thema 1 .That cognizance be taken of the contents of this report. 2. That vacant posts be funded to capacitate the Finance Department, in the next financial year. A report on filling of vacancies should be submitted quarterly effective from July 2016, to update the Committee of the status quo.
23
3. That more budgets be allocated to improve security in Municipal stores in the next financial year. A quarterly report must be submitted, effective from July 2016 on the matter.
4. That the number of Tshepo 10000 co-operatives conducting business with the City be improved from 1.02% and 1.43% to at least 25% as per the requirement of Supply Chain Management for the next financial year. A progress report in that regard should be submitted to the Committee in July 2016.
3. Department of Finance
MFMA In year Financial Report (Monthly Budget Statement) for the period ending 29 February 2016
ED: Nthabiseng Mokete
1.That cognizance be taken of the contents of this report
24
b) 12 May 2016 Committee meeting:
4.8 APPLICATION OF RELEVANT LEGISLATION, POLICIES AND BY-LAWS
An observation on legislative compliance was monitored through the Inspections-in-Loco conducted by the Committee in the three capital projects as mentioned in the report, the Library Park as well as the two stadia. Weaknesses were identified in that shortfalls on project’s budget poses a threat in completing the projects and this has a negative impact on the City’s core desired objective of providing service delivery to its communities. Capital projects are allocated budget which is provided for in the MTREF and the SDBIP as prescribed in the MFMA and Preferential Procurement Policy Framework Act. No.5 of 2000 and Regulations Section 19 (1) (d), stipulated as follows: “A Municipality may spend money on a capital project only if the sources of funding have been considered, are available and have not been committed for other purposes.” These projects mentioned above have been approved by Council, therefore by not injecting the approved total amount to the project contradicts the Council’s resolution and has negative repercussions.
4.9 ANALYSIS OF THE PROCESS PLAN
There were two inspections conducted in line the adopted 2015/16 Process Plan which is attached for ease of reference as an annexure to this report. The inspections focused on capital projects of the City with a view of establishing if they are in line with the Service Delivery Budget and Implementation Plan (SDBIP). Effective from the third quarter of the financial year, the process plan was not adhered to in order to dispose the backlog of outstanding reports which still needed to serve before the Committee. The backlog is mainly because reports which the Committee requested from the Department were not submitted timeously. In addition, the cancelled Committee meeting of November 2015 further added to the backlog.
Item Department Matters considered
Author/ Initiator
Resolutions
1. Department of Finance
Creditors Age analysis: 31 January to 31 March
ED: Tommy Ngwenya
That cognisance be taken of the presentation regarding the Creditor’s Age analysis report from 31 January 2016 to 31 March 2016
25
The Inspection-in-Loco that was scheduled for February 2016, as per the approved process plan, was postponed to accommodate reports that were available to serve before the Committee. It is critical to note that strong systems are compulsory to promote coordination and prevent fragmentation of such systems, in accordance with the Municipal Systems Act (2000) Section 11(3)(g)(j) read with Section 40 which stipulate that: Section 11 (3) (g)(j) “A municipality exercises its legislative or executive authority by- (g) monitoring and, where appropriate, regulating municipal services where those
services are provided by service providers other than the municipality (j) monitoring the impact and effectiveness of any services, policies, programs or plans”
Section 40” “A Municipality must establish mechanisms to monitor and review its performance
management system.”
4.10 PERFORMANCE OF THE DEPARTMENT
a) Staff Complement The total staff complement for the Department was standing at 1448, during the last interaction with the Committee. There were 28 Director positions, in terms of the approved structure, which formed part of the 1448. Five (5) out of the twenty eight (28) positions were vacant and two (2) were never filled, according to the report received. The two positions were part of the new division, Treasury Office. The other two became vacant as a result of a resignation and retirement. The below diagram represented the state of affairs with regard to Director positions:
Designation Approved posts as per structure
Posts filled as per the Migration and Placement process
Vacancies Proposed vacancies to be filled in 2015/2016
Director 28 23 5 4
In addition to the vacant Director positions, the following incumbents were acting in Top Management positions: • ED: Financial Reporting & Assets – Acting GCFO; • ED: Tshwane Bus – Acting ED SCM; • ED: Treasury – Acting ED Revenue Management; • Director: Front Office and Funding Management – Acting ED Treasury; and • Director: Expenditure Management – Acting ED Financial Reporting & Assets.
26
The two Directors in the above category, continued doing their regular functions as Directors. The risk associated with this structure was that the staff had to overstretch by performing additional functions related to the vacant positions. This could result in low morale, fatigue and underperformance. Human Resources is a legislative requirement and the following legislation was therefore contravened. The Section 66 (1) (d) of the Municipal Systems Act states that: “A Municipal Manager, within a policy framework determined by the municipal Council and subject to any applicable legislation, must establish a process or mechanism to regularly evaluate the staff establishment and, if necessary, review the staff establishment and the remuneration and conditions of service.” b) Office Accommodation
The lease agreement of the building utilised by the department, expired on 31 December 2014. It is anticipated that the staff in BKS building will be moved to the new office space in Sammy Marks Square and the date will be communicated soon. Furthermore, offices are overcrowded and there are structural issues/problems to the building that include air conditioners as well as drainage system. However, the department is utilising the available resources to maximum capacity.
c) Departmental Business Plan
25% of procurement budget has been provided for empowerment of cooperatives, but in the first quarter only 1.43% was utilised with an additional 1.02% utilized in the second quarter. In view of this rate, the Strategic Objective 02, “Promoting shared economic growth and job creation” will not be achieved.
In order to improve the SCM, a turnaround strategy has been introduced and hopefully in the current quarter there will be improvements. In the previous financial year the Oversight Committee conducted inspections in all Municipal Stores and one of the findings were that security systems at the stores are poor. The Department is therefore commended for taking a step in addressing this issue. A feedback report from the Office of the Deputy City Manager: Service Delivery section was tabled before the March 2016 Oversight Committee meeting, wherein an estimated R16 million was allocated towards improvement of the security system in the Municipal stores.
d) Review of Supply Chain Management Policy
The Council of the City of Tshwane adopted an amended SCM Policy on the 31 July 2013. Section 6.4 of the SCM Policy states that the Accounting Officer should at least annually review the implementation of the policy and when he consider it necessary may submit the proposal for the amendments to Council. The review is placed on C9 for inclusion in the agenda for the next Mayoral Committee.
27
The review is therefore long overdue, noting that the National Treasury reviews policies of supply chain management annually. The supply chain section needs to keep abreast with the National Treasury and in that way, MFMA Regulations stated below will be complied with.
“The Accounting Officer of a municipality must in terms of Section 62(1)(f)(iv) of the Act, take all reasonable steps to ensure that the Municipality or municipal entity has and implements a supply chain management policy as set out in Regulation 2."
e) Progress on the Inspections conducted in 2015/2016
The Committee conducted an inspection on 10 September 2015 with a view of establishing whether the City’s capital projects are in line with the SDBIP. Zithobeni Sports Stadium, Refilwe Sports Stadium and Cullinan Library Park are capital projects which were visited by the Committee situated in Region 5 & 7.
Since the visit, there have been developments which are detailed as follows:
i) Cullinan Library Park
Progress to date:
General progress at 97%;
Roofing complete;
Lifts installed;
Electrical installations at 75%;
All doors and windows fitted;
Access road completed;
Caretaker’s house completed;
Interior finishes at 95% Water, sewer and storm water at 95%;
Landscaping to commence with completion in June 2016; and
Anticipated practical completion date 15 June 2016.
Challenges and mitigations:
Industrial actions from local sub-contractors and labour causing stoppages for 3 weeks during February 2016. Additional fund request as part of adjustment budget process approved to the value of R 11,500,000.
Budget shortfall has been addressed to complete project and honour contract. Intervention by SRAC Management on stoppages by local sub-contractors.
ii) Zithobeni Stadium: Progress to date:
General progress at 60%;
Roadworks and parking areas completed;
Pavilion extensions 80% complete;
28
All civil works completed;
Buildings under pavilions 95% complete; and
Completion and handover by June 2016.
Challenges and mitigations:
Consolidation of 2 sites prohibiting plan approval which could delay construction. Town Planning Department and Legal Department were brought in to resolve the matter;
Budget reduction during allocation of 2015/16 budget resulted in R 15 m shortfall. Funds from Pilditch Stadium were transferred to complete this project;
Local sub-contracting was a challenge but top Management intervened in this regard;
There were challenges with quality of concrete works on pavilion extensions wherein engineers were consulted and quality of work monitored by means of independent.tests.
iii) Refilwe Stadium:
As a result of the disputes between the two companies (Joint Venture), the other pulled out of the project and the notification of withdrawal had gone through relevant processes. It became an automatic cancellation of the contract between the City and the Joint Venture.
In light of this new development, the SRAC department instructed the professional team to assess the work already completed and to quantify the work that still needs to be undertaken to complete the work. Below is a summary of work carried out:
MILESTONE DESCRIPTION
DATE
COMMENT
Revised Bill of Quantity 29 January 2016 The document was forwarded to the PMU in the office of the DCM for the appointment of the new contractor to complete the works
Advertise tender February 2016 The tender was advertised and a site briefing session took place with the contractors
Closing Tender 2 March 2016 Completed
Adjudication of tender 3 March 2016 Completed
Appointment of contractor
End March 2016 In process
Completion Date: The initial completion date was agreed for 30 June 2016. The construction period will be 12 months after the appointment of a new contractor which will take the project to end February 2017.
29
Progress to date:
Previous appointment cancelled and new tender compiled;
Re-advertised and the recommended contractor exceeded the available budget. 4.11. PERFORMANCE OF THE FINANCE OVERSIGHT COMMITTEE
This current financial year the Committee not only attended to its oversight function as mandated but has also participated in the workshops, study tours, conferences and seminars as part of capacity building and skills development.
4.12 CHALLENGES FACED BY THE OVERSIGHT COMMITTEE FINANCE
The main challenges limiting the Committee in executing its responsibilities revolve around procedure during meetings. The procedure for meetings as outlined in the terms of reference of the Committee indicates that meetings are conducted in accordance with the provisions of the Council’s Rules and Orders By-Laws, read with any specific Council approved Policy and Procedure regarding the functioning of the Committee. The challenges can therefore be summarised as follows: i. Reports which the Committee requested from the Department were not submitted
timeously to the Committee and thus created a backlog.
ii. Diverse interpretation of the Rules and Orders By-Laws, Section 4 (2).
iii. Most of the Committee members have been performing tasks without laptops (tools of trade). The matter was reported and relevant documents provided for the laptops to be replaced or repaired but without luck. This hampered their individual performance and the Committee in executing its responsibilities.
Mitigations (in relation to the challenges above)
i. Presentations should be treated as Agenda items and should therefore be sent together with the notice of the meetings as required by the Rules and Orders. Circular 9 Report Flow must be complied with by the Department;
ii. The Department is compelled in terms of the Governance Model, to account on its
performance to the Section 79 Oversight Committee;
iii. The submission of reports by Department must be in line with the Rules and Orders By-Law, to avoid the backlog of reports.
5. COMMENTS OF THE STAKEHOLDER DEPARTMENTS Not applicable.
30
6. IMPLICATIONS 6.1 HUMAN RESOURCES
The performance of the department is likely to be affected negatively by the vacant positions.
6.2 FINANCES
Budget shortfalls create unnecessary delays on completion of projects.
6.3 COMMUNICATION
The report is for consideration by the Committee and Council, resolutions herein will be communicated to relevant department(s).
6.4 PREVIOUS COUNCIL AND MAYORAL COMMITTEE RESOLUTIONS
The content of report addresses the Governance Model which is a Council resolution of 09 June 2011 and highlights non-compliance with the Rules and Orders By-Law, a Council resolution of 29 November 2012 due to diverse interpretations.
6.5 CONSTITUTIONAL AND LEGAL FACTORS
The report reflects compliance or non-compliance with provisions of the following legislation:
Constitution of the Republic of South Africa; Local Government Municipal Systems Act, Act 32 of 2000; Local Government Municipal Structures Act, Act 117 of 1998; Local Government Municipal Finance Management Act, Act 56 of 2003; and Intergovernmental Relations Framework Act, Act 13 of 2005.
7. CONCLUSION
The Section 79 Oversight Committee: Finance has performed its duties according to its terms of reference as adopted by Council. Reports and presentations for the period under review will assist Council (through the Section 79 Committee) in proposing measures to improve the performance of the Department in line with the Municipal Systems Act. This report outlines Annual Performance of the Committee for the Financial Year 2015/16 and it covers meetings held and analysis of the performance of the department. The department should at all times strive for excellence by complying with the above provisions of legislation. This would assist the City to achieve a clean audit and adhere to good governance principles.
31
The Inspection conducted during the period under review and its findings will assist Council in developing measures to improve the quality of services rendered to the community, in line with Batho Pele Principles. This report outlines oversight activities for the 2015/2016 Financial Year and it covers meetings held, inspections conducted with regard to the legislative prescripts which informs the mandate of the department, as well as the analysis of the process plan and challenges faced by the Committee.
ANNEXURES:
A: Process Plan for 2015/16 financial year. B: Councillor’s Attendance Register. RECOMMENDED:
1. That congnisance be taken of the contents of this report.
2. That the Finance Department submit a report quarterly to the Committee, highlighting the
status of challenges listed in items 4.4 and 4.10, effective from September 2016.
3. That Rules and Orders Bylaw be complied with consistently, further that it be reviewed to
avoid diverse interpretation of the clauses that lead to wasteful expenditure through
cancellation of meetings.
(Remark:
The Section 79 Oversight Committee at its meetig held on 15 June 2016 unanimously agreed that certain minor amendments be made in the body of the report. The said amendments were made.)
32
ANNEXURE A: PROCESS PLAN
PROGRAM/ BUSINESS PLAN FOR CITY OF TSHWANE SECTION 79 OVERSIGHT COMMITTEE: FINANCE
JULY 2015 – JUNE 2016
DATE TIME ACTIVITY REPORTS AND PRESENTATIONS
ACTUAL REPORTS CONSIDERED
OUTSTANDING REPORTS
RESPONSIBLE DIVISION
16 July 2015
12:00 Committee Meeting
Report on the findings of the previous inspection In-Loco
Committee Annual
report
Planning Session for the Fin Year 2015/2016 and adoption of process plan
Oversight Committee : Finance
Oversight Committee: Finance
Oversight Committee: Finance
13 August 2015
12:00 Committee Meeting
Presentation on all Inspection In-Loco’s conducted at the stores in all the regions
Finance department
33
Presentation on the
turnaround strategy in the Supply Chain Division
Finance department
10 September 2015
09:00 Inspection In-Loco
Capital project/Asset under construction to be identified.
Oversight Committee
8 October 2015
12:00 Committee Meeting
Report on the findings of the previous inspection In-Loco
Quarterly progress report on the challenges identified in stores.
Quarterly progress report on the challenges identified in customer care centers.
Quarterly progress report on Tshepo 10000
Oversight Committee
Finance department
Finance department
Finance department
12 November 2015
12:00 Committee Meeting
Presentation on the
analysis of debtors per Regions and Wards.
Presentation on the budget spent on
Finance department
Finance department
34
indigents.
Presentation on tenders over R10m,awarded, deviations & contracts.
Presentation on the current staffing in the following departments: Treasury, Budget, Revenue, Supply Chain, assets & strategic customer centers & operation centers.
Finance department
Finance department
14 January 2016
12:00 Committee Meeting
Mid-term performance report of the oversight committee.
Mid-term report on CAPEX & OPEX
Mid-term progress report on the findings of the Auditor General(Management letter)
Finance department
Finance department
Finance department
11 February 2016
09:00 Inspection In-Loco
Capital project/Asset under construction to be identified.
Oversight Committee : Finance
35
10 March 2016
12:00 Committee Meeting
Report on the findings of the previous inspection In-Loco.
Presentation on outstanding debtors, actual collection over 60 days.
Presentation on analysis of creditors payments: (monthly overdue)
Oversight committee: Finance
Finance department
Finance department
8 April 2016
12:00 Committee Meeting
Quarterly progress
report on the challenges identified in stores.
Quarterly progress report on the challenges identified in customer care centers.
Quarterly progress report on Tshepo 10000
Oversight Committee : Finance
Finance department
Finance department
36
12 May 2016
09:00 Inspection in-loco
Capital project/Asset under construction to be identified.
Oversight Committee : Finance
9 June 2016
12:00 Committee Meeting
Report on the findings of the previous inspection In-Loco.
Presentation on CAPEX & OPEX
Presentation on all outstanding reports.
Oversight Committee : Finance
Finance department
Finance department
37
ANNEXURE B: COUNCILLORS ATTENDANCE REGISTER
Councillors: FINANCE OVERSIGHT COMMITTEE
16 Jul 2015
13 Aug 2015
10 Sep 2015
08 Oct 2015
12 Nov 2015
Dec 2015
Jan 2016
Feb 2016
Mar 2016
Apr 2016
May 2016
Jun 2016
CM
IN CM
IN CM
IN CM
IN CM
IN CM
IN CM
IN CM
IN CM
IN CM
IN CM
IN CM
IN
Kekana, RJ P - P - - P P - LOA
- - - P - P - P - P - P -
Dlamini, BL
P - P - - P P - AWL
- - - P - P - LOA
- P - P -
Fleming, DL
AWL
- AWL
- - A A - AWL
- - - AWL
- P - p - A - A -
KATAKE, NS
P - P - - P P - AWL
- - - P - P - P - P - P -
Lebese, OS
P - P - - P LOA
- P - - - P - AWL
- p - P - A -
Maredi,F P - P - - A P - P - - - AWL
- AWL
- P - A - P -
Mathenjjwa, N
P - P - - P P - AWL
- - - AWL
- AWL
- AWL
- A - P -
Morudu, MGR
P - P - - A A - P - - - P - AW
- P - P - P -
38
L
Ngwenya, C P P
- -
P - - P LOA
- P - - - P - P - P - P - P -
Rammushi, J
P - P - - P P - P - - - P - P - P - P - P -
Zitha, P P - P - - P P - AWL
- - - P - P - P - P - P -
Khumalo,Z Roos, A
P -
- -
A -
- -
- -
A -
A -
- -
P -
- -
- -
- -
P -
- -
- P
- -
- P
- -
- P
- -
- P
- -
Fourie,ML
P - P - - L OA
P - P - - - P - P - P - P - P -
Middelburg,L
P - A - - P P - P - - - p - P - LOA
- P - P -
Osman, A P - A - - P P - P - - - P - P - P - A - P -
Ramohoebo, M
P - P - - P P - P - - - P - P - P - P - P -
Campbell, AW Smith, F
P -
- -
AWL -
- -
- -
- AWL
- -
- -
- P
- -
- -
- -
- P
- -
- P
- -
- P
- -
- P
- -
- A
- -
Van Den Heever, C
LOA
- A - - P LOA
- P - - - P - P - P - P - P -
39
Visser, G
P - P - - P P - P - - - P - P - P - P - P -
Kissoonduth, A
P - P - - A P - P - - - P - P - P - P - P -
Glossary:
P=Present; A=Absent; CM=Committee meeting; IN=Inspection-in-loco; - = no committee meeting, no inspection, cllr not part of the committee at that time. AWL= absent without letter LOA= Leave Of Absent
Please note: That Councilor Roos, A replaced Councilor Khumalo, Z. from February 2016.
That Councilor Smith, F replaced Councilor Campbell from 08 October 2015
That Councilor Mathafa,O was present as the acting chairperson when the meeting was disrupted.
That the council was on recess in December, hence no meeting took place.