Replacement Reserve Escrow Disbursement
Process Training
April 2012
CHFA – The Connecticut Housing Finance Authority999 West Street, Rocky Hill, CT 06067
2
Replacement Reserve Escrow Revision: Intent
Goals: 1. Reduce the time between review and
approval for owners2. Establish a formalized process for review of
various projects3. Eliminate capital replacement review on
HUD insured properties
3
Replacement Reserve Escrow Revision: Outcome
1. Eliminates Technical Services review for properties w/o CHFA debt
2. Eliminates CHFA reviews for HUD insured properties
3. Created Appendix G to CHFA Standards of Design and Construction – establishing classifications for review certifications
4. Created Capital Improvements Guidelines (CIG)5. Revised the Replacement Reserve Policy6. Created Capital Improvement Schedule
4
No CHFA Financing
Technical Services’ review will not be required for properties that do not have CHFA financing. Examples:
DECD transferred grants Certain TCAP, Exchange CDBG Grants, Green Retrofit Program
5
HUD Insured Projects
Eliminates CHFA reviews for HUD insured properties
CHFA will rely on HUD authorizations for
project review and escrow disbursement.
9250 will be acceptable verification
Electronic copies will be acceptable
CHFA Standards ofDesign & Construction
Goal: Develop affordable, safe housing, with as much quality, energy efficiency, durability, comfort, air quality, and environmental sustainability as the marketplace, resources and need will permit. Volume I – Project Planning and Technical Review
Process Volume II – Health, Safety and Sustainability
Standards and Guidelines Volume III – Appendices CHFA Capital Improvement Guidelines (CIG)
7
Section 00054 & Appendix G
Volume I – Section 00054: Capital Improvements – Repairs/Replacements/Installations References Appendix G and Capital Improvement Guidelines
(CIG) Written description of review/approval process
Appendix G: CHFA Capital Improvement Project Classifications for Repairs/Replacements/ Installations Classifications A, B.1 & B.2 and C Project classifications describe the level of required
certification of conformance to CHFA Standards for repairs/replacements/installations, as determined by the complexity and costs of the project(s).
8
Classification A
If the Owner will be completing “A” projects, the Owner may certify that work has been completed according to CHFA Standards of Design and Construction
Examples: Carpet, Storm Doors, Appliances
Owners must submit Request for Pre-Approval (HM 6-21) if ≥$10,000
Owners must submit Request to Release Escrow Funds (HM 6-24) for reimbursement
9
Classification B
If the Owner will be completing “B” projects B.1: Less than 20K – Owner may self-certify B.2: Greater than or equal to 20K – A Building Design
Professional (BDP) must determine scope of work and certify completion
Examples Roofing/Siding/MEP Repairs/Replacements BDPs: CT-licensed/insured Building and/or Home Inspector,
HUD-approved Inspector, insured FHA 203K Compliance Consultant, Architect, Professional Engineer, Licensed Environmental Consultant, or Approved Vendor
Owners must submit Request for Pre-Approval (HM 6-21) if ≥$10,000
Owners must submit Request to Release Escrow Funds (HM 6-24) for reimbursement
10
Classification C If the Owner will be completing “C” projects Tech Services (TS) review and acceptance of scope, final bid
documents and contract required Examples: Site utility work, structural repairs and heat/smoke/fire
detection/suppression/elevator repairs May require a Field Observer (determined by TS) Building Design Professional certification required
BDPs: CT-licensed/insured Building and/or Home Inspector, HUD-approved Inspector, insured FHA 203K Compliance Consultant, Architect, Professional Engineer, Licensed Environmental Consultant, or Approved Vendor
Owners must submit Request for Technical Services Review and Approval (HM 6-21TS)
Owners must submit (HM 6-21) & (HM 6-24) as required under Classification A & B
11
Capital Improvement Guidelines “CIG” – created to assist Owners, Property
Managers, Developers and internal CHFA staff Provides general guidelines for repair and replacement
projects identified in Appendix G Divided into three sections (Classifications A, B &C)
with specific project examples Includes documentation requirements Includes “Questions to Consider” – suggested related
issues and conditions References to related Standards section(s) Energy-efficient measures and suggestions Project-specific questions and related issues to consider
12
Replacement Reserve Observations
Observation and verification policy change: Observations will occur as determined by scope of work and
may include one or more observations by Building Design Professional (Classification B) and or Technical Services (Classification C).
Asset Management will observe a sampling of the work completed or items purchased at the next scheduled site visit.
Asset Management reserves the right to require observations prior to release of funds for any reason.
13
Capital Improvement Schedule
Capital Improvement Schedule (HM 6-xx) submitted with annual budget
For owners to estimate when work will be completed throughout fiscal year…
…and costs associated with the work Provides Asset Management, Finance and Technical Services
with a schedule to forecast potential workload demands Standardized for potential electronic analysis via MFaSys Owners may revise during fiscal year
Y:\Common Area\TSAM Committee Items\Capital Improvement Schedule.xls
14
Process & Forms
Technical Services Review and Approval (HM6-21TS) - NEW Escrow Release Pre-Approval (HM6-21) - Revised Request To Release Escrow Funds (HM6-24) - Slight
Revision Authorization to Release Escrow (HM6-20) - Revised Replacement Reserve Descriptive Codes (HM6-22) - Slight
Revision Residual Receipts & General Operating Descriptive Codes
(HM6-23) – No Change Escrow Disbursement Policy - Revised Capital Improvement Schedule (HM 6-xx) - NEW
15
Classification A: Scenario 1 Owner intends to install 30 storm doors. The
total cost is less than $10,000. Storm doors are on Capital Improvement
Schedule submitted with annual budget. Owner does not need to seek pre-approval. Following completion of installation, the
Request to Release Escrow Funds is submitted.
Y:\Common Area\TSAM Committee Items\Sample Forms for PP\PP Scenario 1.xls
16
Classification A: Scenario 2 Owner intends to rehab 4 kitchens by replacing
cabinets and plumbing for $15,000. Owner reviews Appendix G to determine certification
requirements. Project falls under Classification A; Owner can certify
but must obtain Asset Management pre-approval. Owner submits Escrow Release Pre-Approval form
with Recommended Vendor, Scope of Work, and 3 quotes attached.
Asset Manager gives pre-approval; Owner completes work and submits HM 6-24.
Y:\Common Area\TSAM Committee Items\Sample Forms for PP\PP Scenario 2.xls
17
Classification B: Scenario 3 The community building roof needs replacing at a
total cost of $9,000. Owner reviews Appendix G to determine certification
requirements and the guidance provided in the CIG. Project falls under Classification B.1; Owner or Building
Design Professional (BDP) must certify. Owner completes work and submits HM 6-24.
Y:\Common Area\TSAM Committee Items\Sample Forms for PP\PP Scenario 3.xls
18
Classification B: Scenario 4 Owner intends to pave entire parking area at a cost of $50,000.
Owner reviews Appendix G to determine certification requirements and the guidance provided in the CIG.
Project falls under Classification B.2 Owner retains BDP to certify compliance with Standards, scope
of work & construction Owner submits Escrow Release Pre-Approval form (HM 6-
21) with Scope of Work and 3 quotes attached. Pre-Approval form must be signed by Owner and BDP
Asset Manager gives pre-approval; Owner completes work and submits HM 6-24.
Y:\Common Area\TSAM Committee Items\Sample Forms for PP\PP Scenario 4.xls
19
Classification C: Scenario 5 Owner intends to replace a boiler at a cost of $50,000.
Owner reviews Appendix G to determine certification requirements and the guidance provided in the CIG.
Project falls under Classification C Owner retains BDP to certify compliance with Standards,
scope of work & construction TS/AM & BDP meet and review proposed scope Technical Services requires at least a 2 week turnaround
time for review of plans and specs Owner submits CHFA Technical Services Review & Approval
form (HM 6-21TS) with scope of work, plans, drawings Asset Manager sends to Technical Services for review
Y:\Common Area\TSAM Committee Items\Sample Forms for PP\PP Scenario 5.xls
20
Classification C: Scenario 5 Continued
Technical Services communicates directly with BDP during the review process
Technical Services signs off and notifies Asset Management
Owner obtains 3 quotes and submits Escrow Release Pre-Approval (HM 6-21) to Asset Manager
Technical Services reviews and accepts Asset Manager approves and notifies Owner to
proceed Owner completes work and submits HM 6-24
Owner & BDP sign HM 6-24 for certification of standards
21
Owner Benefits
More direct input and control of construction project
Compresses timeline by eliminating CHFA review time for Classifications A & B
Defines Capital Improvement process For HUD insured properties, eliminates review
and inspection, shortening the escrow release time
Consolidates escrow disbursement processes Provides clear & direct guidelines for specific
projects
22
Conclusion
No Technical Services Participation: Properties with no CHFA funding HUD Insured Developments All projects under Classifications A & B
Technical Services Participation: Any projects under Classification C CNA Review Loans, Refinancing, Workout and Preservation Environmental Testing Review Emergency Participation Any Asset Management inquiries
23
Questions & Comments