Replacement Castlebrae High School
The Site
Tree from original
field boundary
East Neighbourhood
Centre and Library
Proposed
School site
Harewood Drive Retail Units Existing stone wall
forming boundary
Arthur’s Seat
(behind trees)
Castlebrae
Business Centre
Proposed
School site
East Neighbourhood
Centre and Library
Existing Library
garden
Online: www.edinburgh.gov.uk/newcastlebraehighschool
Email: [email protected]
Comments can be made until Monday 4th March
Have your say...Have your say...
The Terraces
The Terraces provide a
comfortable outdoor dining,
social or teaching space
with terraced seating and
views to Arthurs Seat. This
will also be one of the main
outdoor routes from lower to
upper ground floors
Replacement Castlebrae High School
External Spaces
Town Square
As part of the construction
works taking place for the
School, we will link the
paved areas outside the
East Neighbourhood Centre
and retail units to complete
the Town Square which was
part of the 2014 masterplan.
This area could become a
focal point for the
community
The Wetlands
The Wetlands provide a
sustainable drainage
solution for the School which
can be used as a safe
learning environment for
Science and other subjects
3G Pitch
A floodlit, professional
quality 3G sports pitch - this
will be available out of hours
for community use, through
Edinburgh Leisure
Memorial to
Craig Millar
There are a number of
options available for the
Craig Millar memorial which
currently sits in the centre of
the site.
a/ Leave the existing
Memorial where it is (not
always accessible to the
public within the secure
School grounds;
b/ Mark the original location
within the School grounds
and move the Memorial
closer to Harewood Drive to
allow it to be accessed by
the public at any time.
Recreation Area
An open grassed area for
general recreation and
active play for the School,
which could also be
available for community use
by arrangement with the
School
Futureproofing Castlebrae
The initial proposals are designed to accommodate 700 pupils.
As part of the design process, the team have been asked to
consider how the School could be extended to accommodate up
to 1200 pupils as part of an Expansion Strategy.
Phase 2 will involve an extension to the north of the School
building including additional teaching accommodation, along
with an enlarged car park and extra Sports pitch.
The team have also considered how best to extend a School with
minimal disruption to the School’s day to day operation.
1. Phase 1 Building
2. Phase 2 Extension
3. Phase 1 Car Park
4. Phase 2 Car Park
5. Phase 1 Sports Pitch
6. Phase 2 Sports Pitch
1
2
3
6
Let us know your
thoughts about this
important part of the site
and the history of
Craigmillar
4
5
Online: www.edinburgh.gov.uk/newcastlebraehighschool
Email: [email protected]
Comments can be made until Monday 4th March
Have your say...Have your say...
Replacement Castlebrae High School
The Building
View from Niddrie Mains Road
Start with a Superblock form
React to topography View from Niddrie Mains Road, looking east
View from Niddrie Mains Road, looking north west
Respond to daylighting requirements for
adjacent buildings
Establish layers of
accommodation
Identify the key elements
of the building
Develop the “Learning Landscape”
Online: www.edinburgh.gov.uk/newcastlebraehighschool
Email: [email protected]
Comments can be made until Monday 4th March
Have your say...Have your say...
01
03
02
04
06
05
Replacement Castlebrae High School
Internal Spaces
Lower Ground Floor
Upper Ground Floor
Second Floor
Third Floor
Online: www.edinburgh.gov.uk/newcastlebraehighschool
Email: [email protected]
Comments can be made until Monday 4th March
Have your say...Have your say...
Dining Space
Assembly
Learning Plaza