Upload
hari-sankar
View
173
Download
1
Embed Size (px)
Citation preview
Construction
Construction and Building Materials 19 (2005) 595–603
and Building
MATERIALSwww.elsevier.com/locate/conbuildmat
Repair and structural performance of initially crackedreinforced concrete slabs
Waleed A. Thanoon, M.S. Jaafar *, M. Razali A. Kadir, J. Noorzaei
Department of Civil Engineering, Universiti Putra Malaysia, UPM, Serdang, Selangor, 43400 Darul Ehsan, Malaysia
Received 29 November 2002; received in revised form 10 September 2004; accepted 28 January 2005
Available online 21 March 2005
Abstract
Crack is one of the most common defects observed in reinforced concrete slabs and beams. Major cracks in concrete structures
may occur due to overloading, corrosion of reinforcement or differential settlement of support. To restore the structural capacity of
the distressed elements, retrofitting and/or strengthening are needed. There are different techniques available for retrofitting and
strengthening of different reinforced concrete structural elements reported in the literature. This paper investigates the structural
behaviour of cracked reinforced concrete one-way slab, which is repaired using different techniques.
Five different techniques are used for the purpose of repair in the cracked concrete slab namely; cement grout, epoxy injection, fer-
rocement layer, carbon fibre strip and section enlargement. The slabs were loaded to failure stage and the structural response of each
slab specimens have been predicted in terms of deflection, variation of strain in concrete and steel, collapse loads and the failuremodes.
The efficiency of different repair and strengthening techniques and their effects on the structural behaviour of cracked one-way
reinforced concrete slab had been analyzed. It was observed that the type of repair technique used will affect the load carrying capac-
ity of the slab and will lead to a redistribution of the strains and hence stresses in both concrete and steel reinforcement. All repair
techniques are found to be able to restore or enhance the structural capacity of cracked concrete slabs.
� 2005 Elsevier Ltd. All rights reserved.
Keywords: Repair and strengthening; Distressed concrete slab; Ferrocement; CFRP; Epoxy injection; Grouting; Section enlargement
1. Introduction
In practice, situations arise where existing concrete
structures or some of their components may, for a vari-
ety of reasons, be found to be inadequate and in need of
repair and/or strengthening. The inadequacy may be due
to mechanical damage, functional changes, overstress
due to temperature changes, or corrosion of reinforce-
ment. A common feature of a number of different causes
of deterioration is that there is a reduction of the alka-linity of the concrete, which allows oxidation of the rein-
forcing steel to take place. This oxidation process leads
to cracking of the concrete and possible spalling of the
cover to the reinforcement.
0950-0618/$ - see front matter � 2005 Elsevier Ltd. All rights reserved.
doi:10.1016/j.conbuildmat.2005.01.011
* Corresponding author. Tel.: +603 89466377; fax: +603 86567129.
E-mail address: [email protected] (M.S. Jaafar).
Bridges are one of the concrete structures, which nor-
mally exhibit severe distress due to their exposure toharsh environment. Different repair techniques have
been successfully developed to strengthen a given struc-
ture or part of it to restore its serviceability and strength.
It is also prudent to consider durability aspect when re-
pair or strengthening is carried out. With the advance-
ment of new materials technology, which have
superior mechanical properties and excellent resistance
to electrochemical corrosion, many effective repairsand strengthening techniques have been developed.
The final selection of a suitable and most effective meth-
od generally depends on simplicity, speed of application,
structural performance and total cost.
Studies have shown that fibre reinforced plates (FRP)
increase the strength of flexural members significantly.
Carbon fibre reinforced polymer has a high strength to
Fig. 1. Test set up.
596 W.A. Thanoon et al. / Construction and Building Materials 19 (2005) 595–603
weight ratio, favourable fatigue behaviour and excellent
resistance to electrochemical corrosion to make it prac-
tically suited for structural application [1]. A study con-
ducted by Alfarabi et al. [2] showed that, although the
FRP increase the failure loads, most of the beams
strengthened by FRP started the failure at the curtail-ment zones of the plates. The epoxy used to laminate
the plate at the soffit of flexural members only failed
at loads much higher than the required level [3]. Similar
study also found that the failure modes for repaired
structures may change from ductile to brittle [4]. The
probability of this change depends largely on the
percentage of FRP being used, the location of FRP
and the presence of shear reinforcement in the existingstructures.
Toong and Li [5] investigated the effect of using car-
bon fibre reinforced polymers (CFRP) plates to
strengthen one-way spanning slab to increase the flex-
ural capacity with particular emphasis on the cracking
behaviour at working load. All the CFRP strengthened
specimens exhibited large increase in load carrying
capacity ranging from 60% to 140%.Ferrocement is a type of thin composite material
made of cement mortar reinforced with uniformly dis-
tributed layers of continuous, relatively small diameter
wire meshes. The use of ferrocement proper in repair
was first introduced by Romualdi [6] and Iron [7] in
the early 1980s mainly as relining membranes for the re-
pair of liquid retaining structures, such as pools, sewer
lines, tunnels, etc. Investigation into the use of ferroce-ment as strengthening components for the repair and
strengthening of reinforced concrete beams was re-
viewed by Paramasivam et al. [8]. In general, the dam-
aged concrete and reinforcement (if also damaged)
were removed and replaced with ferrocement, with or
without any changes in overall dimensions of the beam.
The beams were tested under static or cyclic loading [6]
conditions. The strengthened beams were reported to ex-hibit improved cracking resistance, flexural stiffness and
the ultimate loads compared to the original beams.
These improvements; however, depend on the full com-
posite action between the ferrocement layers.
Al-Kubaisy and Zamin [9] presented the flexural
behaviour of reinforced concrete slabs strengthened with
ferrocement tension zone cover. Twelve simply sup-
ported (500 mm2) reinforced concrete slabs were testedunder flexural load. The effect of the percentage of wire
mesh reinforcement in the ferrocement layer, thickness
of the ferrocement layer and the type of connection be-
tween the ferrocement layer and reinforced concrete slab
on the ultimate flexural load, first crack load, crack
width and spacing and load–deflection relationship were
considered.
Other technical methods used for repair of reinforcedconcrete structures are epoxy injection and cement gro-
uting techniques. These techniques are widely used to
treat cracking problem in concrete. The procedure used
is well established in the literature [10–12].
This paper presents a study on the effects of different
repair techniques on the structural response of one way
reinforced concrete slab. The techniques include:
(a) carbon fibre reinforced polymers (CFRP) strip;
(b) cement grout, i.e., SikaGrout214;
(c) epoxy injection, i.e., Sikadur52;
(d) ferrocement cover and;
(e) section enlargement.
These techniques had been selected for their potential to
either increase the structural capacity of members or torestore the original capacity of the sections. Further-
more, this study focuses on the serviceability, strength
and ductility performance for each of the repair tech-
niques to ascertain their potential application in cracked
reinforced concrete slabs.
2. Experimental procedure and repair technique
In order to investigate the effect of various repair
techniques on the structural response of one way slab,
a total of six full scale one-way reinforced concrete slabs
having a dimension of 2.5 m long · 1.0 m wide and
0.15 m thick are cast, cured and tested. The steel rein-
forcement consists of five 10 mm diameter high-yield de-
formed bars with a characteristic strength of 460 N/mm2. The 28-day cube compressive strength, fcu of the
concrete used is 30 N/mm2. All specimens are tested un-
der two-line load located in the middle third of the slab
specimen as shown in Fig. 1. Initially, all slabs are
loaded to 2/3 of their expected ultimate load capacity
or after the development of cracks in the specimens (ini-
tial load ranges between 34 and 40 kN), except for the
control slab, which is loaded until failure. Subse-quently, the load has been released and the specimens
W.A. Thanoon et al. / Construction and Building Materials 19 (2005) 595–603 597
are removed from the testing frame so that repairs may
be carried out.
The resulting cracks in different concrete slab speci-
mens were repaired using each of the techniques men-
tioned above. The specimens are then re-tested to
failure after allowing a suitable curing period. The re-sponse of each specimen in terms of deflection, stiffness,
cracking load, ultimate load, and failure pattern are
analyzed. The repair techniques applied on cracked
slabs are shown in Fig. 2.
2.5 m
Applied L
Epoxy
0.15 m
0.05 m
0.15 m
15 mm
132 mm
50 mm
(e) Section enlarg
Epoxy (Sikadur52)
Epoxy (Sikadur30)
Inlet Port
Fine crack
Reinforced steel bar
(c) Ferrocement layer – S4.
50mm
30 mm
Grout
Fine crack
Before Repair
Reinforced steel bar
(a) Grout pouring – S2.
Fig. 2. Five different repair techniques ap
2.1. Grout pouring technique using SikaGrout 214 (Slab
S2)
At the end of first stage of loading (34 kN), two flex-
ural cracks of 0.88 mm width each were observed at the
middle third of the slab. The resulted crack paths havebeen enlarged by 50 mm in width and 30 mm in depth
to expose the main steel reinforcement. The exposed
reinforcement and concrete surfaces were cleaned using
steel brush, water jet and compressed air before grout is
oad
5Y 10 4R 10 + 5 R 8
1 m
5 Y 104R 10 + 5 R 8
ement – S6.
0.833 m
Ordinary reinforcementWiremesh
Mid-span of concrete slab
Patch with cement mortar
Skeletal steel
(b) Epoxy injection – S3.
0.15 m
1 m
50 mm
1.2 mm
2 m
2.5 m
Carbon Fibre Reinforced Polymer (CFRP)
(d) CFRP strip – S5.
plied on cracked reinforced slabs.
Fig. 3. Cracks repaired using grout pouring technique.
598 W.A. Thanoon et al. / Construction and Building Materials 19 (2005) 595–603
poured into the enlarged extents, see Fig. 3. The grout
used is SikaGrout214 of a density 2.2 kg/L. It is anon-shrink premixed high strength cementitious grout.
The mixing ratio used is 25 kg of grout to 4.4 kg of
water. The specimen has been tested after allowing 7
days for curing.
2.2. Epoxy injection technique (slab S3)
Similar to slab specimens S2, two flexural cracks of0.65 mm width each were observed at the middle third
of the slab under a total load of 37.4 kN. In this repair
method, injection nipples are installed along the crack
path at 200 mm centers as shown in Fig. 4. Sikadur30
was used to fix the injection nipples in position as well
as to seal the surface of the cracks. The epoxy used to
Fig. 5. Cracks repaired usin
(a) Crack pattern before repair.
Fig. 4. Cracks repaired using epoxy injection technique.
fill the crack is Sikadur52, which is low viscosity epoxy,
free flowing and fast curing injection resin based on 2-
component solvent free epoxy resin. It has a density of
1.1 kg/L, tensile strength of 25 N/mm2 (7 days) and a
compressive strength of 40 MPa at 20 �C within 24 h.
The viscosity of Sikadur52 is equal to 290 and 130 cpsat a temperature of 20 and 30 �C, respectively. The crackwidth limits for Sikadur52 is between 0.2 and 5 mm.
Sikadur52 was injected from one end of the crack until
the material exudes from the next nipple. The injection
process was repeated until the whole crack is filled with
the epoxy material.
2.3. Ferrocement layer (slab S4)
The crack pattern observed at the end of initial load
stage (38 kN) is shown in Fig. 5(a). The maximum crack
width found at this load was equal to 0.75 mm. In this
technique, a 30 mm depth concrete from the bottom of
the slab was removed using a concrete chisel and ham-
mer. This concrete layer has been removed only from
the middle third portion of the slab (with dimensionsof 850 mm · 850 mm) as shown in Fig. 5(b).
Two layers of 12.5 mm2 opening galvanized welded
wire mesh of 1.25 mm diameter and a layer of skeletal
steel (5R6) are fixed with the original reinforcement of
the slab after the concrete surface was roughened as
shown in Fig. 5b. Cement mortar (cement to sand ratio
is 1:2 with w/c ratio equal to 0.5) is applied and cured for
28 days.
2.4. Carbon fibre reinforced polymers strip (slab S5)
The crack pattern observed at the end of initial load
stage (34 kN) is shown in Fig. 6(a). The maximum crack
width found at this load was equal to 0.6 mm. A 50 mm
wide and 2 m long CFRP strip having 1.2 mm thickness
has been externally bonded to the tension face of thereinforced concrete slab using Sikadur30 epoxy adhesive
(bonding agent). The carbon fibre strip has been kept at
g ferrocement cover.
(b) Wire mesh used for repair.
(a) Crack pattern before repair. (b) CFRP laminate in position.
Fig. 6. Strengthening the slab with CFRP laminate.
W.A. Thanoon et al. / Construction and Building Materials 19 (2005) 595–603 599
Table 1
Characteristic of Sikadur30 epoxy
Characteristics Guide values
Sag flow 3–5 mm at 35 �CCompressive strength 75–100 N/mm2
Tensile strength 20–30 N/mm2
Shear strength 15–20 N/mm2
E-modulus (static) 8000–16,000 N/mm2
Shrinkage 0.04–0.08%
Glass transition point 50–70 �C
the central part of the slab. The choice of CFRP was
based on theoretical analysis using strain compatibilitymethod and assuming both steel and CFRP yielded at
the same time with the concrete compressive strain
reaches 0.0035. The analytical calculation shows that
the expected failure load of the strengthened slab with
CFRP is equal to 106 kN (double the capacity of the
slab).
The concrete surface where the CFRP strip will be lo-
cated was roughened and cleaned using compressed airand water jet. Sikadur30 epoxy adhesive was next ap-
plied on the roughened concrete surface (2–3 mm thick).
The CFRP was then fixed on the Sikadur30 adhesive
layer as shown in Fig. 6(b). The tensile strength of the
carbon fibre strip is 2800 N/mm2, its modulus of elastic-
ity is 165,000 N/mm2 and the density is 1.5 kg/L. The
main characteristic of the Sikadur30 epoxy is presented
in Table 1.
2.5. Section enlargement (slab S6)
The crack pattern observed at the end of initial load
stage (34 kN) is shown in Fig. 7(a). The maximum crack
width found at this load was equal to 0.65 mm. In this
repair technique, the bottom of the cracked slab is rein-
forced with additional 50 mm thick concrete layer rein-
(a) Crack pattern before repair.
Fig. 7. Strengthening by enla
forced with additional steel reinforcement. The
strengthened slab was designed to fail at ultimate load
of 104 kN.
The bottom surface of the slab was roughened and a
number of holes have been drilled to a depth equal to
the effective depth of the slab. After cleaning the dust,
48 pieces of R10 steel bars (act as shear connectors) of
155 mm long were inserted in the holes and fixed in po-sition using Sikadur30 epoxy adhesive as shown in Fig.
7(b). Additional flexural steel reinforcement 5R10 and
5R8 was next fixed to the shear connectors. Similar con-
crete mix is used to cast the additional 50 mm concrete
layer and kept for 28 days for curing before retesting
the specimen.
(b) Roughened surface and steel provided.
rging the slab section.
130.93 kN
101.41 kN
57.12 kN52.2 kN
66.96 kN
57.12 kN
0
20
40
60
80
100
120
140
160
S1 S2 S3 S4 S5 S6
Slab
Load
(kN
)
(+ 17.23 % )
(- 8.61 % )(0 % )
(+ 77.39 % )
(+ 129.22 % )
ControlSlab
Fig. 9. Ultimate loads for slabs 1–6.
600 W.A. Thanoon et al. / Construction and Building Materials 19 (2005) 595–603
3. Results and discussions
3.1. Cracking and ultimate loads
The initial cracking loads for different reinforced con-
crete slab specimens are shown in Fig. 8 along with thecontrol slab (S1). All the repaired concrete slabs exhibit
higher cracking load compared to the control slab, ex-
cept S5. The repaired specimens using grout pouring,
epoxy injection and section enlargement techniques
show 35% increase in the cracking loads compared to
the control slab. While the use of ferrocement layer in-
crease the cracking load by 17.8%. The strengthening
of the slab by using the CFRP at its soffit, withoutrepairing the initial cracks, improves the crack width
only. In this specimen, new cracks are developed at
slightly lower load compared to the original slab.
Fig. 9 shows the ultimate failure loads for all the slab
specimens. It could be observed that all the repair tech-
niques used in this study are capable of restoring the
ultimate capacity of the defected slab except specimen
S3 where the cracks have been treated by epoxy injec-tion. However, the reduction in strength is only 8.6%
compared with the control slab. The ultimate capacity
of slabs S5 and S6, which are repaired by CFRP and sec-
tion enlargement, respectively, show 77.4% and 130%
higher ultimate load capacities compared to the control
slab. The increase in the ultimate strength for slab spec-
imen S5 is in agreement with the result reported by
Toong and Li [5] even though the ratio of CFRP striparea to the overall cross-section area used in this study
is very small (0.04). Moreover, there is no increase in
the ultimate capacity of the specimen repaired by ferro-
cement cover compared to the control slab which is
matching well with the conclusion reported by Al-Kub-
aisy and Zamin [9].
Both crack and ultimate loads for all slabs also indi-
cate that the repaired structures had a high degree ofintegrity. The main concern that engineers normally
have are related to the ability of the repair material to
integrate and act compositely with the parent materials
37.00 kN
25.00 kN
32.52 kN
37.44 kN37.44 kN
27.60 kN
0
10
20
30
40
50
60
S1 s2 s3 s4 s5 s6Slab
Load
(kN
)
(+ 35.65 %) (+ 35.65 %)
(+ 17.83 %)
(- 9.42 %)
(+ 34.06 %)
Control Slab
Fig. 8. Cracking loads for slabs 1–6.
did not appear to be a problem for any of the repair
techniques being investigated in this study.
3.2. Slab deflections
Fig. 10 shows load–deflection for each of the slabs.
These deflections are recorded at the mid-span. The slab
specimens show almost similar stiffness except specimen
S6, where the deflection has decreased due to the stiff-
ness of the extra concrete layer of concrete that has been
added. The stiffness has increased more significantlycompared to other specimens. Deflection patterns for
the control slab S1 and specimens S2, S3 and S4 showed
that all of them had similar initial stiffness. However,
after two-third of the ultimate load, these specimens ex-
hibit different level of ductility pattern. The maximum
deflections observed in S3 (epoxy injection) and S4 (fer-
rocement layer) are 15% lower compared to the control
slab, while pouring the crack with grout show 20% in-crease in maximum deflection compared to the original
slab.
19.00 mm
22.90 mm
16.31 mm
15.83 mm
38.65 mm
18.83 mm
0
20
40
60
80
100
120
140
0 10 20 30 40 5Deflection (mm)
Load
(kN
)
0
Control Slab - S1Grout Pouring - S2Epoxy Injection - S3Ferrocement - S4CFRP Strip - S5Enlargement - S6
Fig. 10. Load–deflection curves for all slabs.
185
230
195
60
115
360
0
50
100
150
200
250
300
350
400
450
S1 S2 S3 S4 S5 S6
Slabs
Co
ncr
ete
Str
ain
(x
10-6
)
Fig. 12. Concrete compressive strain at 50 kN load level.
W.A. Thanoon et al. / Construction and Building Materials 19 (2005) 595–603 601
On the other hand, specimen S5 (CFRP) and speci-
men S6 (Section enlargement), show different variation
in load–deflection curves compared to all other speci-
mens. The specimen repaired by section enlargement
exhibits higher stiffness and the load–deflection curve
shows much stiffer behaviour. The maximum deflectionobserved is almost the same as observed in the control
slab but occurred at more than twice the ultimate load.
Moreover, non-ductile variation in the load–deflection
curve could be observed in this specimen, which change
the ductile behaviour observed in the control slab. The
specimen reinforced with the carbon fibre strip shows
no change in the initial stiffness compared to the control
slab. With the increase of loading, the stiffness decreasesat a higher rate compared to specimen S1, S2, S3 and S4.
Hence, the CFRP strip has a significant effect on the
stiffness in the advance stage of loading.
3.3. Strain distribution
Fig. 11 shows the variation of the concrete compres-
sive strain at the mid-span at a distance of 25 mm belowthe top fibre of the reinforced concrete slab specimens
versus the applied load. This location however, is very
close to the N.A of the slab section and hence the values
of the strains are very small. It was recorded during the
test that the N.A. is shifting up as the applied load in-
creases and its depth during different loading stages
changed from 40 to 30 mm (approximately) in speci-
mens S1, S2, S3 and S4. For specimens strengthenedwith CFRP and reinforced concrete layer (S5 and S6),
the depth of N.A changed approximately from 70 to
45 mm near failure load.
Fig. 12 represents the concrete strain in different slab
specimens when the applied load is equal to 50 kN (near
by failure load of the control slab). All the slab speci-
mens exhibit lower strain values compared to the control
slab. The decrease in the concrete strain in specimens S2,S3 and S4 has been found ranging between 30% and
539226
257206
177
314
0
20
40
60
80
100
120
140
0 100 200 300 400 500 600Strain (x 10-6)
Load
(kN
)
Control Slab - S1Grout Pouring - S2Epoxy Injection - S3Ferrocement - S4CFRP Strip - S5Enlargement - S6
Fig. 11. Variation of concrete compressive strain for all slabs.
50%, while in S5 and S6 specimens, the reduction in
compressive strain of concrete has been recorded at
65% and 85%, respectively.
For the specimen reinforced with additional rein-
forced concrete layer, it was observed that the strain in
the additional reinforced concrete layer is not compati-
ble with strain in the original slab although initially bothlayers act as a composite section. This is due to provid-
ing insufficient number of shear connectors which leads
to the occurrence of horizontal longitudinal cracks be-
tween the two layers.
3.4. Failure modes and mechanism
Fig. 13 shows the crack pattern of all the strength-ened slab specimens at failure. The tests were stopped
when excessive deflection and/or excessive wide cracks
were observed although the specimens did not com-
pletely collapse. It is clear from the crack patterns in
the slabs S1, S2, S3 and S4 almost similar modes of fail-
ure have been observed. Cracks started at the tension
sides and increased in width and length with the applied
loads. In the control slab the neutral axis location isshifted upwards until the concrete strain reaches its ulti-
mate value. At this stage, the steel reinforcement is
yielded which quickly led to compressive crushing of
concrete. This failure mechanism is a typical ductile fail-
ure observed in under-reinforced concrete sections.
However, in the repaired specimens, the ductility is not
clearly observed as in the control slab.
The failure mechanism in Slab S5, which has beenstrengthened by CFRP strip, is different from other slab
specimens since CFRP laminates is additional reinforce-
ment. The failure is characterized by shearing of
the concrete interface with the CFRP strip (relative
Fig. 13. Crack patterns and modes of failures for strengthened slabs.
602 W.A. Thanoon et al. / Construction and Building Materials 19 (2005) 595–603
slippage) associated with less warning compared to
other slab specimens. The failure was sudden and oc-
curred immediately after the peeling of the CFRP strips.
This is due to insufficient anchorage length of the CFRPstrip. The strain measured before failure in the CFRP
laminate is 60% of its yielding strain which comply with
peeling failure (and not rupture failure) observed in this
specimen. The number of cracks observed at failure is
more but the cracks width are smaller compared to
other specimens.
For S6 slab specimens, in addition to the transverse
cracks, horizontal crack had been formed at the bound-aries between the original slab and the additional con-
crete layer due to shearing.
4. Conclusion
Based on this study, the following conclusions could
be drawn:
(i) The repaired structures had similar or higher
cracking and ultimate loads compared to the con-
trol slab.
(ii) The repairs using grout, epoxy injection and ferro-
cement layers showed behaviours similar to that of
the control slab in terms of strength and ductility
performance. In other words, these repair tech-niques can safely adopt the normal reinforced con-
crete design for concrete slabs.
(iii) CFRP and section enlargement repair techniques
for the cracked slabs showed superior structural
performance in terms of strength. The ductility
performance for these slabs, however, is less than
that of the control slabs.
(iv) It could also be concluded that all repairs tech-niques used are effective to at least restore the
structural performance of cracked reinforced con-
crete slabs.
Acknowledgements
The authors thank Sika Kimia Sdn. Bhd., Malaysiafor providing the CFRP strip and other Sika products.
Moreover, the authors acknowledge Mr. Wong Chee
Wai and Mr. Tan Khong Yee for their contribution in
the experimental work.
W.A. Thanoon et al. / Construction and Building Materials 19 (2005) 595–603 603
References
[1] Clarke JK, Waldron P. The reinforcement of concrete structures
with advanced composites. Struct Eng 1996;74(17/3):1996.
[2] Alfarabi S, Alsulaimani GJ, Basunbul IA, Bamch MH, Ghaeb
BN. Strengthening of initially loaded reinforced concrete beams
with using FRP plates. ACI Struct J 1994 (March):160–8.
[3] El-Mihilmy MT, Tedesco JW. Analysis of reinforced beams
strengthened with FRP laminates. J Struct Eng
2000:684–91.
[4] Arduni M, Tommaso AD, Nanni A. Brittle failure in FRP plate
and sheet bonded beams. ACI Struct J 1997;94:363–70.
[5] Toong K Chan, Li Xiaoan. Improving crack behaviour of one-
way slabs with carbon fibre plates. In: Proceedings of the 4th
Asia-Pacific structural engineering and construction conference,
September 13–15, 2000, Kuala Lumpur, vol. 2; 2000. p. 351–58.
[6] Romualdi JP, Lim CTE, Ong KCG. Strengthening of RC beams
with ferrocement laminates. Cement Concrete Compos
1998;20:53–65.
[7] Irons M. Ferrocement for infrastructure rehabilitation. Concrete
Int Design Constr 1987;9:24–8.
[8] Paramasivam P. Laminated ferrocement for better repair. Con-
crete Int: Design Constr 1987;9:34–8.
[9] Al-Kubaisy MA, Jumaat Mohd Zamin. Flexural behaviour of
reinforced concrete slabs with ferrocement tension zone cover.
Constr Build Mater 2000;14:245–52.
[10] Emmons PH. Concrete repair and maintenance. R.S. Means
INC; 1994.
[11] Allen RTL, Edwards SC. The repair of concrete struc-
tures. Blackie; 1987.
[12] Raina VK. Concrete bridge practice-construction, maintenance
and rehabilitation. 2nd ed. New Delhi: Tata McGraw Hill; 1993.