i
MUSHOLLA AN-NUR
JL. Batas Barat Rt.005 / 010 Kel. Baru, Pasar Rebo Jakarta timur
RENOVASI MUSHOLLA AN-NUR 2008 – 2009 TAHAP II
(PROPOSAL)
Dokumen ini disiapkan dan diawasi oleh:
Panitia Renovasi Musholla An – Nur
ii
Daftar Isi Daftar Isi............................................................................................................................. ii Daftar Gambar .................................................................................................................. ii Daftar Tabel ...................................................................................................................... ii I. KONDISI SAMPAI DENGAN SAAT INI..................................................................... 1 I. 1. Kegiatan – kegiatan ............................................................................................. 2 I. 2. Laporan Keuangan .............................................................................................. 6 II. RENCANA PERENCANAAN TAHAP II ................................................................... 6 III. JADWAL PELAKSANAAN ........................................................................................ 8 IV. SANGAT DIHARAPKAN PARTISIPASI DAN DUKUNGAN DARI PARA DONATUR....................................................................................................................... 10 IV. 1. BENTUK SUMBANGAN / DONASI............................................................. 11 IV. 2. CARA PENYAMPAIAN SUMBANGAN....................................................... 11 V. PENUTUP................................................................................................................... 11 Lampiran .......................................................................................................................... 12 1. Salinan Surat Keterangan Pembukaan Rekening Renovasi .......................... 12 2. Kepanitiaan ............................................................................................................. 13 3. Kondisi Musholla & Gambar Rencana Teknis ................................................... 14 4. Gambar Rencana Teknis ...................................................................................... 16 5. Rencana Anggaran Biaya ..................................................................................... 17 6. Laporan Keuangan Terakhir................................................................................. 20 7. Salinan Sertifikat Wakaf ........................................................................................ 38
Daftar Gambar Gambar 1 Pembentukan Kepanitiaan................................................................................ 2 Gambar 2 Persiapan tempat kerja untuk tukang ............................................................... 3 Gambar 3 Pembongkaran Mushalla lama......................................................................... 4 Gambar 4 Kegiatan Pengecoran Lt II ............................................................................... 4 Gambar 5 Status Pekerjaan per 11 Februari 2009 ........................................................... 5 Gambar 6 Musholla An-Nur Sebelum Direnovasi........................................................... 14 Gambar 7 Kegiatan Kerja Bakti Menjelang Romadhon 1429H/2008 M ........................ 14 Gambar 8 Kondisi Pembangunan Musholla Saat ini ...................................................... 15 Daftar Tabel Tabel 1 Kondisi Keuangan Per Tgl 22 Januari 2009 ........................................................ 6 Tabel 2 Sumbangan Material Per Tgl 22 Januari 2009 .................................................... 6 Tabel 3 Jadwal Pelaksanaan Pekerjaan............................................................................ 9 Tabel 4 Rencana Anggaran Biaya ................................................................................... 17 Tabel 5 Laporan Keuangan Tanggal 16 Februari 2009 ................................................. 20
1
RENOVASI TAHAP II MUSHOLLA AN-NUR 2008 - 2009 RT 05/10 KEL. BARU, PASAR REBO, JAKARTA TIMUR
(PROPOSAL)
Hanyalah yang memakmurkan masjid-masjid Allah ialah orang-orang yang
beriman kepada Allah dan hari kemudian, serta tetap mendirikan sholat,
menunaikan zakat dan tidak takut (kepada siapapun) selain kepada Allah, maka
merekalah orang-orang yang diharapkan termasuk golongan orang-orang yang
mendapat petunjuk. (QS. 9:18)
Ass. Wr. Wb.
Pembaca yang berbahagia, proposal ini akan berisi penjelasan ringkas tahap I
renovasi Musholla An-Nur (http://mushollaannur.wordpress.com) . Setelah tahap I
selesai dilaksanakan per tanggal 18 Januari 2009 yang lalu, selanjutnya
dilaksanakan pekerjaan tahap II. Masih banyak beban dan pekerjaan yang harus
diselesaikan. Oleh karenanya, sangat diharapkan bantuan dari pembaca sekalian
untuk bersama – sama memikul tanggung jawab dalam syiar Agama ini. Mudah –
mudahan proposal ini mampu memberikan gambaran mengenai beban dan
tanggung jawab tersebut. Panitia tetap menerima saran dan sumbangsih yang lain
demi perbaikan dan penyempurnaan kegiatan renovasi secara keseluruhan.
I. KONDISI SAMPAI DENGAN SAAT INI
Secara resmi renovasi Musholla An-Nur telah dimulai tanggal 11 Nopember 2008
dengan dibentuknya kepanitiaan renovasi dan dimulainya pencarian dana
renovasi.
2
I. 1. Kegiatan – kegiatan
Secara kronologis kegiatan – kegiatan yang telah dilakukan kurang lebih sebagai
berikut:
1. Pembentukan Kepanitian,
Dilaksanakan tanggal 11 Nopember 2008 yang lalu. Susunan kepanitian
dapat dilihat pada lampiran dokumen proposal ini.
Gambar 1 Pembentukan Kepanitiaan
2. Pencarian Dana
Secara resmi kegiatan pencarian dana dilaksanakan 2 minggu setelah
kepanitaan terbentuk. Dengan diselesaikannya proposal tahap I,
perlengkapan kesekretariatan dan rekening bersama (joint account) yang
menggunakan nama Ketua Panitia dan Bendahara
3. Persiapan Pekerjaan
Dilaksanakan pada Hari Ahad 7 Desember 2008 yaitu dengan melakukan
kerja bakti guna menyiapkan tempat kerja untuk tukang agar cuaca dan
musim hujan tidak mengganggu aktivitas tukang.
3
Gambar 2 Persiapan tempat kerja untuk tukang
4. Pembongkaran Musholla lama
Pembongkaran Musholla lama dilakukan dengan kerja bakti jamaah pada
tanggal 21 Desember 2008. Selanjutnya tukang meneruskan pekerjaan
menaikkan bata tembok lantai I dan persiapan infrastruktur pengecoran
lantai dua.
4
Gambar 3 Pembongkaran Mushalla lama
5. Kegiatan Pengecoran Lantai II
Sebagai pekerjaan akhir tahap I, dilakukan pengecoran dak lantai II.
Kegiatan ini dilaksanakan pada tanggal 18 Januari 2009.
Gambar 4 Kegiatan Pengecoran Lt II
5
6. Kondisi Saat ini
Sampai dengan saat ini (11 Februari 2009) penembokan lantai 2 sudah
dilakukan. Demikian juga tiang penyangga kuda – kuda rangka atap telah
selesai dicor. Tiang – tiang dak penyangga pengecoran telah dibongkar
dan dirapikan
Gambar 5 Status Pekerjaan per 11 Februari 2009
6
I. 2. Laporan Keuangan
Kondisi dana dan laporan keungan secara ringkas dapat dijelaskan sebagai
berikut: Tabel 1 Kondisi Keuangan Per Tgl 22 Januari 2009
No Uraian Jumlah (Rp.)
A Dana Kas Musholla
20,000,000
B Sumbangan/Donatur
68,345,000
D Total (A+B)
88,345,000
E Pengeluaran
65,896,000
F Sisa saldo (D-E)
22,449,000
Diterima sumbangan material sebagai berikut: Tabel 2 Sumbangan Material Per Tgl 22 Januari 2009
No Material Satuan Jumlah
1 Batu bata buah 5,000
2 Pasir truk 1
3 Split truk 1
4 Semen sak 58
5 Ember Ngecor unit 10
Selengkapnya mengenai kondisi keuangan dan material dapat dilihat di lampiran
proposal ini atau di situs renovasi Musholla http://mushollaannur.wordpress.com
II. RENCANA PERENCANAAN TAHAP II
Setelah pengecoran lantai dilaksanakan, kegiatan berikutnya adalah melanjutkan
pembuatan tembok lantai 2 yang sekarang sudah dimulai. Sampai dengan saat ini
(3 Februari 2009) tembok lantai 2 semuanya sudah dibangun. Namun demikian,
7
untuk sementar kegiatan terpaksa dihentikan karena ketidakcukupan dana yang
tersedia saat ini. Untuk sampai selesai, kegiatan yang harus dilakukan adalah :
1. Pengadaan dan pemasangan kuda – kuda, rangka atap dan genteng
2. Pengadaan dan pemasangan pintu, kusen dan angin – angin/ventilasi
3. Penyelesaian pembangunan tempat wudhu, peturasan dan
perlengkapannya
4. Finishing, pekerjaan penyelesaian akhir berupa pengacian, pengecatan
dan pagar.
Untuk keseluruhan pekerjaan tersebut, diperkirakan masih diperlukan dana
sebesar Rp.93.937.656,- (Sembilan puluh tiga juta sembilan ratus tiga puluh
tujuh ribu enam ratus lima puluh enam rupiah) dengan rincian sbagai berikut.
No Komponene Biaya Estimasi Biaya (Rp.) I Material & Jasa Rangka - Atap 22,411,694 II Material & Jasa Pintu, Jendela dan Ventilasi 19,395,700 III Material Tempat Wudhu & Peturasan 1,685,500 IV Material Pagar, Tangga 17,143,600 V Material Finishing 10,850,000 VI Jasa Tukang & Kenek Pekerjaan III, IV, V 20,160,000 Total 91,646,494 Biaya Tak Teduga 2.5 % 2,291,162.3 Total Estimasi Biaya 93,937,656
Selanjutnya rincian anggaran biaya tersebut disertakan dalam lampiran.
Sumber Dana Dalam pembangunan tahap II musholla An Nur ini, panitia mengandalkan sumber
dana dari:
1. Sisa saldo renovasi tahap I
Sisa saldo pembangunan tahap I sebesar Rp. 5.000.000,- (Lima puluh
juta rupiah) 2. Sumbangan dari Jamaah/Pengurus
Panitia terus mengupayakan agar diperoleh sumbangan dana / material
dari para jamaah sekitar, penguru, maupun panitia. 3. Donatur dan sumber – sumber dana yang lain
8
Mengingat biaya yang diperlukan masih culup besar, maka panita dan
jamaah Musholla sangat mengharapkan bantuan dan dukungan dari para
donatur. Selain pengajuan proposal, panitia juga mengunakan model yang
lain seperti penjualan kupon sumbangan yang nilai nominalnya Rp.
10.000,- per kupon. Donatur juga dapat memberikan sumbangan dananya
dengan mengisi kotak amal yang disediakan di teras musholla.
Kondisi keuangan terakhir disertakan dalam lampiran dokumen proposal ini.
Dengan kondisi keuangan saat ini, maka dengan terpaksa pembangunan fisik
sementara akan dihentikan. Panita akan fokus untuk mencari dana sehingga
mencukupi batas minimal untuk melaksanakan pekerjaan (minimal pekerjaan
rangka atap dan genteng). Sementara agar tidak terjadi rembesan saat hujan,
atap akan ditutup dengan terpal. Meskipun demikian, pekerjaan – pekerjaan
untuk merapikan lantai bawah tetap dilanjutkan sehingga musholla dapat segera
difungsikan kembali minimal untuk keperluan dasar yaitu shalat berjamaah.
III. JADWAL PELAKSANAAN Mengingat keterbatasan dana yang tersedia saat ini, maka pembangunan fisik
akan dilanjutkan jika dana yang tersedia sudah mencukupi untuk pekerjaan
utama yaitu pengerjaan rangka atap dan genteng.
9
Tabel 3 Jadwal Pelaksanaan Pekerjaan
Bulan/Minggu Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09
No Kegiatan 14-Feb
1-Mar
16-Mar
31-Mar
15-Apr
30-Apr
15-May
30-May
14-Jun
29-Jun
14-Jul
29-Jul
13-Aug
28-Aug
I Pencarian Dana
I.1 Pencarian Dana Tahap Rangka
Atap
I.2 Pencarian Dana Pekerjaan
Lainnya II Pekerjaan Tahap II
II.1 Rangka Atap + Genting II.2 Tempat Wudlu II.3 Pintu, Jendela, Ventilasi II.4 Pagar & Finishing
III Peresmian, Penggunaan Pertama Ramadhan 1430H
10
IV. SANGAT DIHARAPKAN PARTISIPASI DAN DUKUNGAN DARI PARA DONATUR
Sudah kita pahami bersama bahwa kegiatan dakwah dan syiar Islam merupakan fardu
‘ain yang menjadi kewajiban setiap individu muslim. Kegiatan syiar dan dakwah
tersebut tentu saja disesuaikan dengan kemampuan dan keahlian masing – masing
individu tiap muslim. Masing – masing individu dapat mengambi peran yang berbeda
satu sama lain namun dengan tetap mengacu kepada satu tujuan bersama yaitu demi
kemajuan bersama ummat muslim dalam beribadah, baik ibadah yang bersifat ritual
maupun amaliah.
Dengan pemahaman demikian, maka kami panitia renovasi dan pengurus Musholla An
Nur mengharapkan partisipasi dan dukungan Bapak / Ibu sekalian dalam mendukung
pengembangan Musholla An Nur. Dalam hal ini dukungan yang kami harapkan adalah
berupa sumbangan material pembangunann baik berupa dana maupun bahan
material yang dibutuhkan dengan tetap diharapkan do’a dan dukungan moral lainnya.
Panitia dan pengurus menyadari bahwa yang paling berkepentingan terhadap
Musholla tersebut adalah masyarakat sekitar. Oleh karena itu, tahap pertama dan
prioritas utama target pengumpulan dana tersebut adalah jamaah dan masyarakat
sekitar. Namun dikarenakan kebutuhan dana yang cukup besar dan di sisi lain
kemampuan jamaah dan masyarakat sekitar yang terbatas, maka dirasakan perlu
untuk memperluas target sumber dana (donasi) di luar jamaah dan masyarakat
sekeliling. Oleh karena itulah, maka proposal dan permohonan dana ini sampai ke
tangan Bapak / Ibu yang terhormat.
11
IV. 1. BENTUK SUMBANGAN / DONASI Panitia menerima donasi/sumbangan berupa
1. Dana / uang
2. Bahan / material bangunan yang diperlukan. Dengan catatan, jika material yang
kami terima ternyata melebihi kebutuhan maka bahan / material tersebut akan
kami lelang dengan tetap memberikan laporan kepada semua donator.
IV. 2. CARA PENYAMPAIAN SUMBANGAN 1. Dana / uang
Donator dapat memberikan sumbangan dana dengan cara ditransfer ke
rekening panita renovasi Bank Mandiri Capem Pasar Rebo a.n. a.n. :
Sujarot & Mujiono No.: 129-00-0680336-1
Untuk wilayah Jabotabek, panita dapat mengambil ke tempat yang telah
ditentukan oleh donator
2. Bahan / material bangunan
Donator dapat menyampaikan sumbangan tersebut ke alamat :
Musholla An Nur, Jl. Batas Barat, RT 05/10 Kel. Baru, Pasar Rebo,
Jakarta Timur
Panita dapat mengambil ke tempat yang telah ditentukan oleh donator,
dengan catatan lokasi di area Jabodetabek
V. PENUTUP
Tidak ada niat lain dari pembuatan dan penyampaian proposal ini Insyaallah semata
untuk mencari keridlaan Allah S.W.T dengan jalan menyediakan fasilitas ibadah baik
ritual maupun amaliah bagi ummat Islam di lingkungan Kelurahan Baru khususnya
maupun ummat Islam secara keseluruhan pada umumnya. Kami, panitia
pengembangan, pengurus Musholla, maupun jamaah mengucapkan terima kasih yang
setulusnya atas dukungan material maupun moral dari Bapak/Ibu sekalian, disertai
do’a Mudah – mudahan Allah S.W.T meridhai dan menerima segala amal ibadah yang
kita lakukan.
Panita pembangunan menerima segala sumbang saran, maupun komentar guna
kemajuan dan kejayaan syiar Islam. Saran tersebut dapat disampaikan kepada panitia
melalui berbagai saluran, antara lain :
1. Musholla An Nur, Jl. Batas Barat RT 05/10 Kel. Baru, Pasar Rebo, Jakarta
Timur
12
2. Kontak person masing – masing anggota panitia seperti pada lampiran
Kepanitiaan
3. Email melalui email address : [email protected],
4. Blog pengembangan musholla di http://mushollaannur.wordpress.com
Lampiran 1. Salinan Surat Keterangan Pembukaan Rekening Renovasi
13
2. Kepanitiaan
MUSHOLLA AN-NUR
JL. Batas Barat Rt.005 / 010 Kel. Baru, Pasar Rebo Jakarta timur
PENGEMBANGAN & RENOVASI MUSHOLLA
2008 – 2009
SUSUNAN KEPANITIAN
PENASEHAT : 1. H. M. ISHAQ 087878134119
2. H.SUNGKONO 08161308754
3. KAPTEN RASMIN 087709688/
02168608642
4. SUGIMAN / KETUA RT.005
5. H. BAMBANG,SE.
KETUA : Ir. MUJIONO, M.T 081510109832
WAKIL KETUA : MUJI SANTOSO 081314789915
SEKRETARIS : MISWAN, S.Ag. 081310433729
WAKIL SEKRETARIS : AGUS SUTEJO 081905271036
PENGAWAS KEUANGAN : MUKTY ROSYID,S.Pd 081398054499
BENDAHARA : SUJAROT 081546055665
KORD. DANA ANDI FAIZAL 08128506858
ANGGOTA 1. KEMIN SUSENO
2. REMAJA MUSHOLLA
PENGAWAS BANGUNAN : Ir. SUNGKONO 081389918
SEKSI PERLENGKAPAN : 1. IVAN SANTOSO 081310920087
2. MARALI 0218728753
14
3. Kondisi Musholla & Gambar Rencana Teknis
Gambar 6 Musholla An-Nur Sebelum Direnovasi
Gambar 7 Kegiatan Kerja Bakti Menjelang Romadhon 1429H/2008 M
15
Gambar 8 Kondisi Pembangunan Musholla Saat ini
16
4. Gambar Rencana Teknis <dihapus, untuk memperkecil ukuran file>
17
5. Rencana Anggaran Biaya
PENGEMBANGAN & RENOVASI MUSHOLLA 2008 – 2009
RENCANA ANGGARAN BIAYA TAHAP II Tabel 4 Rencana Anggaran Biaya
MUSHOLLA AN-NUR JL. Batas Barat Rt.005 / 010 Kel. Baru, Pasar Rebo Jakarta timur
PENGEMBANGAN & RENOVASI MUSHOLLA 2008 – 2009
RENCANA ANGGARAN BIAYA TAHAP II
NO JENIS PEKERJAAN VOL SATUAN HARGA
SAT. (Rp.) JUMLAH (Rp) Total (Rp)
I Material & Jasa Rangka - Atap
22,411,693.99
1 Rangka Atap Baja Ringan 96 M2
130,000.00
12,480,000.00 8M x 17 M
2 Genteng Morando 2,500 BH
2,500.00
6,250,000.00
3 Gipsum Plafon bawah 33 Lembar
55,000.00
1,803,278.69 2.928
4 Gipsum Plafon Atas 34 Lembar
55,000.00
1,878,415.30 2.928
5 Kaya Plafon 3 M3
2,160,000.00
6,480,000.00 2.928
II Material & Jasa Pintu, Jendela dan Ventilasi
19,395,700.00
1 Pintu Alumunium Keliling 41.60 M
80,000.00
3,328,000.00 3 buah x (2.2+2) *2 2 buah x (2.1 + 2) * 2
2 Jendela Alumunium Keliling 99.20 M
80,000.00
7,936,000.00 8 buah x (1.5+0.5) *2 14 buah x (0.9 + 1.5) * 2
3 Ventilasi Alumunium Keliling 65.80 M
80,000.00
5,264,000.00 47 buah x (0.4+0.3) * 2
18
NO JENIS PEKERJAAN VOL SATUAN HARGA
SAT. (Rp.) JUMLAH (Rp) Total (Rp)
4 Kaca Pintu 21.60 M2
55,000.00
1,188,000.00 3 buah x (2.2x2) 2 buah x (2.1x 2)
5 Kaca Jendela 24.90 M2
55,000.00
1,369,500.00 8 buah x (1.5x0.5) 14 buah x (0.9 x1.5)
6 Kaca Ventilasi 5.64 M2
55,000.00
310,200.00 47 buah x (0.4x0.3)
III Material Tempat Wudhu & Peturasan
1,685,500.00
1 Pipa Paralon 1/2 inch 10.00 Pcs
16,000.00
160,000.00
2 Pipa Paralon 3/4 inch 5.00 Pcs
25,000.00
125,000.00
3 Pipa Paralon 3 inch wavin 3.00 Pcs
55,000.00
165,000.00
4 Knee 3 inch 3.00 Pcs
3,500.00
10,500.00
5 Knee 3/4 inch 5.00 Pcs
3,000.00
15,000.00
6 Knee 1/2 inch 10.00 Pcs
3,000.00
30,000.00
7 Kran Air 10.00 BH
25,000.00
250,000.00
8 Tangki Air 500 l 1.00 BH
700,000.00
700,000.00
9 Stop Kran 1.00 BH
50,000.00
50,000.00
10 Radar Air Otomatis 1.00 SET
80,000.00
80,000.00
11 Lain - lain (lem, solasi, dll) 1.00 LS
100,000.00
100,000.00
IV Material Pagar, Tangga
17,143,600.00 1 Tangga Luar
a Batu Bata 640.00 BH
340.00
217,600.00
b Besi Pagar 12.00 M
350,000.00
4,200,000.00 (7 +14 ) M * 0.8 M
19
NO JENIS PEKERJAAN VOL SATUAN HARGA
SAT. (Rp.) JUMLAH (Rp) Total (Rp) 2 Pagar Balkon 2 * 2 * 2 * 1/2
a Batu Bata 1,400.00 BH
340.00
476,000.00 (7 +14 +14) M * 0.8 M
b Besi Pagar 35.00 M
350,000.00
12,250,000.00
V Material Finishing
10,850,000.00
1 Cat 5.00 FIL
350,000.00
1,750,000.00
2 Aquaprof 1.00 FIL
850,000.00
850,000.00
3 Semen 125.00 SACK
54,000.00
6,750,000.00
4 Amplas, Peralatan lain - lain 1.00 LS
1,500,000.00
1,500,000.00
VI Jasa Tukang & Kenek Pekerjaan III, IV, V
20,160,000.00
1 Tukang 144.00 OH
65,000.00
9,360,000.00
2 org x 3 bulan x 6 hari x 4 minggu
2 Kenek 216.00 OH
50,000.00
10,800,000.00
3 org x 3 bulan x 6 hari x 4 minggu
JUMLAH
91,646,493.99
BIAYA TAK TERDUGA 2.50%
2,291,162.35
TOTAL BIAYA
93,937,656.34
20
6. Laporan Keuangan Terakhir
Laporan Keuangan Tanggal 16 Februari 2009 Tabel 5 Laporan Keuangan Tanggal 16 Februari 2009
Penerimaan (Rp.) Pengeluaran(Rp.)
No Tanggal Uraian Debet Tanggal Uraian Kredit Saldo (Rp.)
1 09-Nov-08
Saldo Awal Kas Musholla 20,000,000
09-Nov-08 Pengeluaran Keskretariatan 1,000,000
19,000,000
2 09-Nov-08
H. Kusnan (RT. 7) 5,000,000
24,000,000
3 09-Nov-08
P Helmi (Kel. Kalisari) 500,000
24,500,000
4 09-Nov-08
P Muji Santoso (RT 7) 200,000
24,700,000
5 11-Nov-08
P Mujiono (Kel. Kalisari) 1,500,000
26,200,000
6 11-Nov-08
P M Rasyid (RT 7 ) 1,000,000
11-Nov-08 Biaya Meterai 20,000
27,180,000
14-Nov-08 Papan Pengumuman & Kotak amal 400,000
26,780,000
16-Nov-08 Spanduk & Photo Copy 250,000
26,530,000
7 17-Nov-08
H. Madil (Kalisari) 50,000
17-Nov-08 Ongkos bongkar bata 100,000
26,480,000
8 17-Nov-08
Sdr. Rizal Pondok Gede 100,000
26,580,000
9 17-Nov-08
Sdri. Martha (Bengkulu) 50,000
26,630,000
10 17-Nov-08
P Lukman (RT 7) 50,000
26,680,000
11 23-Nov- P Mochdar (Kel. Kalisari) 500,000
21
08 27,180,000 12 23-Nov-
08 P Sugimin (RT 7)
500,000
27,680,000
13 23-Nov-08
P Surya Saputra (RT 7) 1,000,000
28,680,000
14 25-Nov-08
P Endang Rachman (RT 7) 1,000,000
29,680,000
15 25-Nov-08
P Agus Sutejo (RT 7) 200,000
29,880,000
16 25-Nov-08
Ibu Endang Susilowati (Kebon Pala) 100,000
29,980,000
17 25-Nov-08
P Rasmin (RT 5) 3,000,000
32,980,000
18 25-Nov-08
P Kemin (RT 7) 200,000
33,180,000
19 25-Nov-08
P Ivan Santoso (RT 7) 100,000
33,280,000
20 27-Nov-08
Bp. Sujarot 200,000
33,480,000
21 27-Nov-08
Bp. Beno Salinas (Bekasi) 100,000
33,580,000
22 29-Nov-08
Bp. Wartam 250,000
33,830,000
23 30-Nov-08
Bp Ribut 150,000
33,980,000
24 30-Nov-08
Bp. Suparjan 100,000
34,080,000
25 30-Nov-08
Bp. Ishak 150,000
34,230,000
26 30-Nov-08
Bp. M Adhi Kurnia 100,000
34,330,000
27 30-Nov-08
Bp. Sigit (Kalisari) 500,000
34,830,000
Total 36,600,000 1,770,000 34,830,000
22
LAPORAN KEUANGAN 28 Desember 2008
Penerimaan (Rp.) Pengeluaran(Rp.)
No Tanggal Uraian Debet Tanggal Uraian Kredit Saldo (Rp.)
27 01-Dec-08 Saldo Awal bulan Desember 36,600,000
1,770,000
34,830,000
28 01-Dec-08 Bp. Harsono, Kalisari 100,000
34,930,000
29 04-Dec-08 Bp. Ivan Santoso 500,000
35,430,000
30 05-Dec-08 Bp. Agus Sudarta, RT 5 300,000
35,730,000
31 05-Dec-08 Bp. H. Hubri 400,000
36,130,000
32 05-Dec-08 Bp. Irdiantoro Susanto, Bekasi 500,000
36,630,000
33 05-Dec-08 Bp. Widodo, Kalisari 1,500,000
38,130,000
34 06-Dec-08 Bp. Misbach, Kalisari
50,000
06-Dec-08
Ongkos Bongkar Batu Bata 100,000
38,080,000
35 06-Dec-08 Bp. Suparno, RT 7 50,000
38,130,000
36 06-Dec-08 Bp. Siswoyo, Pembina 50,000
38,180,000
37 07-Dec-08 Bp. H. Hasan, RT 5 500,000
38,680,000
38 07-Dec-08 Bp. Hanafi Zain, RT 5 500,000
39,180,000
39 08-Dec-08 Bp. Sukarsa, Dekel 500,000
39,680,000
40 08-Dec-08 Bp. Endang Rachman 300,000
39,980,000
41 08-Dec-08 Bp. Soni A., Bintaro 1,000,000
23
40,980,000 42 08-Dec-08 Bp. Maksum, Bintaro
1,000,000
41,980,000
43 10-Dec-08 Bp. Harry Fitri, Jakarta 500,000
42,480,000
44 10-Dec-08 Ibu Suminah, Bekasi 250,000
42,730,000
45 10-Dec-08 Bp. Budi Siswanto, RT 7 500,000
43,230,000
46 10-Dec-08 Hasil Penjualan Kupon, Kurban 120,000
43,350,000
47 10-Dec-08 Kupon Karyawan TMIN 1,500,000
44,850,000
48 12-Dec-08 Bp. Apik Paksa Driya, Bandung 100,000
44,950,000
49 13/12/2008 Bp. Thony Lordian 100,000
45,050,000
50
14-Dec-08
Pengeluaran Biaya Kerja Bakti 40,000
45,010,000
51 13-Dec-08 Ibu Nani Kurnia/Ibu Pono 300,000
45,310,000
52 13-Dec-08 Saweran ibu -2 majlis ta'lim An Nur 300,000
45,610,000
53 13-Dec-08 Sri Kustiono 50,000
45,660,000
54 13-Dec-08 Bu Sumarsono RT 03/02 150,000
45,810,000
55 13-Dec-08 Bp Sugiman RT 05 300,000
46,110,000
56 13-Dec-08 Bp. Tomo 100,000
46,210,000
57 13-Dec-08 Bu Rajina RT 07 50,000
46,260,000
58 15-Dec-08 Bu Andi E Sutarto 1,000,000
15-Dec-08
Pasir 1 truk 1,200,000
46,060,000
24
Cakar Ayam 10 bh 550,000
45,510,000
Benang 4,000
45,506,000
Ongkos bongkar pasir 20,000
45,486,000
59 16-Dec-08 Bp, Namri RT 07 50,000
16-Dec-08
Besi 12 inch 12 btg
1,200,000
44,336,000
Pahat Beton 24,000
44,312,000
17-Dec-08
Pacul 32,000
44,280,000
Buku 1 bh 10,000
44,270,000
Pulpen 2,000
44,268,000
Spidol 6,000
44,262,000
60 18-Dec-08 Bp. Widodo, RT 08 200,000
18-Dec-08
Besi 6 inch 10 btg 160,000
44,302,000
61 18-Dec-08 Bp. Suroto (TMMIN, Jakarta) 50,000
Besi 10 inch 10 btg 350,000
44,002,000
Kawat bendrad 2 kg 40,000
43,962,000
mata gergaji besi 2 bh 26,000
43,936,000
gegep 2 bh 24,000
43,912,000
split 2 colt 350,000
43,562,000
semen 10 sak 540,000
43,022,000
ember 6 buah 30,000
42,992,000
kunci besi 23,000
42,969,000
25
batu kali 1 colt 160,000
42,809,000
palu 1 bh 15,000
42,794,000
pensil 1 1,000
42,793,000
62 19-Dec-08 Penjualan Kupon @ 50000 135,000
19-Dec-08
Besi 10 inch 10 btg 450,000
42,478,000
63 19-Dec-08 Penjualan Kupon @ 50000 50,000
Papan cor 10 bh 120,000
42,408,000
Paku 5 cm 1 kg 16,000
42,392,000
Semen 15 sak 810,000
41,582,000
64 20-Dec-08 Majlis Taklim Al Muttaqin 200,000
20-Dec-08
Besi 12 inch 30 btg
1,800,000
39,982,000
Besi 6 inch 20 btg 320,000
39,662,000
Kawat ayakan 20,000
39,642,000
Triplek 9 mm 2 bh 190,000
39,452,000
Paku 7 cm 1 kg 16,000
39,436,000
Besi ring 12 inch 120,000
39,316,000
Paralon 3 inch 1 bh 65,000
39,251,000
Kne 3 inch 2 bh 30,000
39,221,000
Lem Paralon 1 bh 6,000
39,215,000
Pasir 2 truk 2,400,000
36,815,000
Ongkos bongkar pasir 50,000
36,765,000
26
Ongkos Tukang + Kenek
1,180,000
35,585,000
65 21-Dec-08 Bp. Kastono
500,000
21-Dec-08
Pengeluaran Biaya Kerja Bakti 100,000
35,985,000
66 22-Dec-08 Bp. Eko RT 06 200,000
22-Dec-08
Besi 8 inch 30 btg 990,000
35,195,000
67 22-Dec-08 Hamba Allah 1,000,000
Kawat bendrad 5 kg 90,000
36,105,000
68 22-Dec-08 Ibu Rusli Cijantung 100,000
Besi ring 21 bh 71,000
36,134,000
69 22-Dec-08 Bp. Sudaya RT 07
1,000,000
Ongkos Bongkar Batu Bata 30,000
37,104,000
70 22-Dec-08 Bp. H Joni, Bekasi 100,000
37,204,000
71 22-Dec-08 Bp. Johan 300,000
37,504,000
72 22-Dec-08 Bp. Tomo, Kalisari 200,000
37,704,000
73 23-Dec-08 Bp. Samsuhadi 500,000
23-Dec-08
Pulsa Operasional 100,000
38,104,000
74 23-Dec-08 Bp. Kamsudi, SMK 22 500,000
Papan cor 20 bh 190,000
38,414,000
75 23-Dec-08 Bp. Muslim, SMK 22 200,000
Paku 10 cm 2 kg 36,000
38,578,000
76 23-Dec-08 Bp. Utin, SMK 22 200,000
Paku 7 cm 2 kg 36,000
38,742,000
77 23-Dec-08 Bp. Win Kusdiatmono RT 4 500,000
39,242,000
78 24-Dec-08 H. Lukman 100,000
39,342,000
79 24-Dec-08 Hamba Allah 200,000
39,542,000
25-Dec- Semen 10 540,000
27
08 sak 39,002,000
benang 2
buah 4,000
38,998,000 80 26-Dec-08 Lelang Genteng
550,000 26-Dec-08
Paku 4 kg 64,000
39,484,000
81 26-Dec-08 Hj Tammah 150,000
Kaso 1 kubik 2,160,000
37,474,000
82 26-Dec-08 Bp. Wahyu Hidayat, PT. Mahatetra 500,000
Kaso balok 10 btg 640,000
37,334,000
Papan Cor 100 lbr 900,000
36,434,000
83 27-Dec-08 Hamba Allah 300,000
27-Dec-08
Ongkos Tukang
2,055,000
34,679,000
84 27-Dec-08 Hamba Allah 5,000,000
gegep 2 bh 24,000
39,655,000
Kaso 4x6 1/2 kubik
1,080,000
38,575,000
27-Dec-08
Besi 10 inch 100 btg
4,300,000
34,275,000
Kayu balok 10 btg 640,000
33,635,000
Besi 12 inch 100 btg
6,000,000
27,635,000
85 28-Dec-08 Bp. Dody RT 7 50,000
28-Dec-08
Papan 3 lbr 135,000
27,550,000
86 28-Dec-08 Ibu Mardhani 60,000
27,610,000
29-Dec-08
Papan 6 lbr 270,000
27,340,000
Kaso 4x6 1/2 kubik
1,080,000
26,260,000
Paku 7 cm 5 kg 80,000
26,180,000
Triplek 8 ml 5 lbr 475,000
25,705,000
28
Triplek 6 mm 20 lbr
1,300,000
24,405,000
Paku 4 xm 1 kg 16,000
24,389,000
87 30-Dec-08 Bp. Parjan, RT 7 200,000
30-Dec-08
Photo Copy+lakban 100,000
24,489,000
88 31-Dec-08 Bp. Tata Mulyana, RT 7 300,000
31-Dec-08
Paku 5 cm 4 kg 64,000
24,725,000
Kaso 4x6 1 kubik
2,160,000
22,565,000
Total 62,565,000 40,000,000
22,565,000
LAPORAN KEUANGAN 22Januari 2009 Penerimaan (Rp.) Pengeluaran(Rp.)
No Tanggal Uraian Debet Tanggal Uraian Kredit Saldo (Rp.)
88 01/01/09 Saldo Awal bulan Januari 62,565,000
40,000,000 22,565,000
89 01/01/09 Bp. Bambang RT 5 2,500,000
01-Jan-09
Papan Cor 75 lbr
675,000 24,390,000
Paku 7 cm 3 kg
48,000 24,342,000
90 02/01/09 Bp. Wasiran, RT 7 110,000
02-Jan-09
Kaso 4x6 1kubik
2,160,000 22,292,000
91 02/01/09 Bp. Sarto, RW 9 1,000,000
Paku 7 cm 3 kg
48,000 23,244,000
92 04/01/09 Bp. Hari Winarko
300,000
03-Jan-09
Ongkos Tukang+Kenek
1,895,000 21,649,000 93 04/01/09 Bp.
Juminianto, Kalisari 100,000
04-Jan-09
Paku 7
48,000 21,701,000
29
94 04/01/09 Penjualan Kupon 360,000
Paku 4 cm 48,000 22,013,000
95 05/01/09 Penjualan Kupon 650,000
Cakar Ayam 116,000 22,547,000
Triplek 6 mm 30 lmbar
1,320,000 21,227,000
Bambu Bagesting, 30 unit
285,000 20,942,000
04-Jan-09
Rokok Kerja Bakti
100,000 20,842,000
96 06/01/09 Bp. Sungkono, RT 7 500,000
05-Jan-08
Paku 5 cm 48,000 21,294,000
97 06/01/09 Bp. Arifin Junaedi, Kalisari 1,000,000
Paku 7 cm
48,000 22,246,000 98 06/01/09 Bp. Mujiono,
Kalisari 100,000 06-Jan-09
Konsumsi Lembur
75,000 22,271,000
Lampu Neon 2 24,000 22,247,000
99 07/01/09 Alm. Ibu Maryanah 200,000
07-Jan-09
Konsumsi Lembur
81,000 22,366,000
Kawat Bendrad
64,000 22,302,000
Kaso 4 x 6 2 ikat
280,000 22,022,000
Kaso 4 x 6 5 ikat
625,000 21,397,000
Triplek 6 mm 6 lmbar
396,000 21,001,000
Besi 12 inch, 23 btg
1,380,000 19,621,000
Kawat Bendrad
90,000 19,531,000
Meteran 2 19,505,000
30
buah 26,000
100 08/01/09 Bp. Hernowo, Vietnam 2,000,000
08-Jan-09
Potokopi Proposal
100,000 21,405,000
101 08/01/09 Hamba Allah, Austria 4,500,000
Kawat Bendrad
54,000 25,851,000
Papan Cor 15 lbr
135,000 25,716,000
Kaso 4 x 6, 5 ikat
625,000 25,091,000
102 09/01/09 Pendapatan Kotak Amal 1,700,000
Paku 7 cm, 2 kg
32,000 26,759,000
103 09/01/09 Bp. Sungedi (RT 7)
100,000
09-Jan-09
Ongkos Tukang+Kenek
2,780,000 24,079,000
Papan Cor 15 lbr
135,000 23,944,000
Besi 10 inch,
20 btg
860,000 23,084,000
Paku 7 cm, 2
kg
32,000 23,052,000
Kawat
Bendrad
54,000 22,998,000
Kaso 4 x 6, 4
ikat
500,000 22,498,000
Reng 1 ikat
120,000 22,378,000
Paku 5 cm, 3
kg
48,000 22,330,000
Test pen
5,000 22,325,000
10-Jan-09
Kaso 4 x 6, 3 ikat
375,000 21,950,000
10-Jan-09
Gembok 25,000 21,925,000
31
104 11/01/09 Bu Eni, 100,000
Reng 3 x 4, 2 ikat
250,000 21,775,000
105 11/01/09 H. Didi, RT 4 100,000
Paku 7cm, 2kg 32,000 21,843,000
Paku 5 cm, 1 kg
16,000 21,827,000
Besi 10 inch, 10 btg
430,000 21,397,000
Triplek 6 mm, 1 lbr
66,000 21,331,000
Besi 10 inch, 5 btg
215,000 21,116,000
Kawat bendrard, 3 kg
54,000 21,062,000
14-Jan-09
Reng 2 ikay 250,000 20,812,000
Paku 7cm 2 kg 32,000 20,780,000
Benang 5,000 20,775,000
Paku 7cm 2 kg 32,000 20,743,000
Ember Cor 30 bh
150,000 20,593,000
Pengki, 12 bh 84,000 20,509,000
14-Jan-09
Semen 80 sck 4,320,000 16,189,000
106 17/01/09 Bp. Suwanto 100,000
17-Jan-09
Pasir 1 Truk 1,200,000 15,089,000
107 17/01/09 Gongseng Motor
100,000
Ongkos bongkar material
50,000 15,139,000
108 17/01/09 Hamba Allah 30,000
17-Jan-09
Cetak Kupon 40 pcs
250,000 14,919,000
32
109 17/01/09 Hamba Allah, Cimanggis 3,000,000
17,919,000
110 17/01/09 H. Komarudin 500,000 18,419,000 111 17/01/09 Bp. Misbach 50,000 18,469,000 112 17/01/09 Bp. Rasmin 1,000,000 19,469,000 113 17/01/09 Kupon
Karyawan Toyota 480,000
19,949,000 114 17/01/09 Penjualan
Kusen 300,000
20,249,000 115 18/01/09 Bp. Machbul,
RT 4 500,000
20,749,000 116 18/01/09 Bp. Drs. Yanto
SMK 22 1,000,000
18-Jan-09
Ongkos Tukang+Kenek
1,850,000 19,899,000 117 18/01/09 Bp. Suwito, RT
4 500,000 Kerja Bakti,
rokok
227,000 20,172,000 118 18/01/09 Penjualan
Kupon 150,000
Ongkos bongkar material
40,000 20,282,000
119 18/01/09 Ibu Herni Sp.d, SMK 22
50,000
Sewa Molen+ Operator
300,000 20,032,000 120 18/01/09 Bp. Drs. Eko
Suryono, SMK 22 50,000
Pasir 1 Truk
1,200,000 18,882,000 121 18/01/09 Bp. Sutarmo,
RT 4 300,000 Split 1 Truk
1,200,000 17,982,000 122 18/01/09 Bp. Letkol H.
Sukabi 200,000 Besi 10 inch, 2
btg
86,000 18,096,000 123 18/01/09 Bp. Anang, RT
7 50,000 Split 1 colt
700,000 17,446,000
20-Jan-09
Besi 20 btg 860,000 16,586,000
Paku 5 cm 1 kg
16,000 16,570,000
33
Besi 12 inch 10
600,000 15,970,000
Kawat bendrad 2kg
36,000 15,934,000
besi 8 inch 5btg
165,000 15,769,000
Lot 1 bh 10,000 15,759,000
Kwt bendrad 2kg
36,000 15,723,000
Kaso 4 x 6 4 btg
88,000 15,635,000
reng 5 btg 60,000 15,575,000
paku campur 1kg
16,000 15,559,000
Paku 7 cm 2 kg
32,000 15,527,000
124 21/01/08 Bp. Juhaeni 500,000
21-Jan-09
Bata Merah, 500 pcs
1,500,000 14,527,000
125 21/01/09 Hamba Allah 150,000
Uang rokok bongkar
65,000 14,612,000
126 21/01/09 H. Herman Cs 500,000 15,112,000 127 21/01/09 Bp. Sukamto 1,000,000 16,112,000 128 23/01/09 BKM Toyota
Sunter 300,000
23-Jan-09
Ongkos Tukang + Kenek
1,000,000 15,412,000
23-Jan-09
Biaya Kuli Material
100,000 15,312,000
25-Jan-09
Bambu Steger 54,000 15,258,000
129 26/01/09 Bp. Sarbandiyanto, RT 4 500,000
15,758,000 130 26/01/09 Bp. Wasiran, 150,000 15,908,000
34
RT 6/ 10 131 26/01/09 Hamba Allah 130,000 16,038,000 132 26/01/09 Bp. Kamsudi,
SMK 22 70,000
16,108,000 133 26/01/09 Ibu Ema,
Kalisari 100,000
16,208,000 134 26/01/09 Bp. Hendra,
RT 4 500,000
16,708,000 135 26/01/09 Hamba Allah 100,000 16,808,000 136 27/01/09 Bp. Hj Ali bin
Abdul Halim, Kuningan 1,000,000
17,808,000
26-Jan-09
Besi 10inch 8 btg
264,000 17,544,000
Kawat bendrad 1 kg
18,000 17,526,000
Cincin 2 ikat
140,000 17,386,000
papan cor 20
lbr
180,000 17,206,000
27-Jan-09
Kwt ayakan 20,000 17,186,000
Glass box 8 bh 132,000 17,054,000
137 28/01/09 Bp. Hari Murtijo, Jakarta 200,000
28-Jan-09
Biaya bongkar pasir
20,000 17,234,000 138 29/01/09 Penjualan
Kupon 590,000 Semen 5 sak
270,000 17,554,000 139 30/01/09 Kotak Amal
Keliling RT 7 940,000
18,494,000
29-Jan-09
Besi 8 inch 10 btg
330,000 18,164,000
besi 10 inch 20 btg
860,000 17,304,000
35
besi 12inch 10btg
600,000 16,704,000
30-Jan-09
Paku 7 cm 32,000 16,672,000
Paku 5 cm 1 kg
16,000 16,656,000
16,656,000 140 31/01/09 Hj. Abdul
Rachim 1,000,000
31-Jan-09
Ongkos Tukang + Kenek
1,625,000 16,031,000
31-Jan-09
Semen 5 sak 270,000 15,761,000
Total 93,975,000 78,214,000 15,761,000
No Nama Donatur Nama Donatur Material Satuan Jumlah No Material 1 CV. Ba Ta Tsa Batu bata 5,000 1 Batu bata 2 Bp. H Sungkono Split truk 1 3 Split 3 Bp. H Sungkono Pasir truk 1 2 Pasir
4 Bp. H Akhmad Khozin Pasir truk 1 3 Split
5 Ucok Warung, Kalisari Semen sak 10 4 Semen 6 Material Yasmin Kalisari Semen sak 4 5 Ember Ngecor 7 Material Yasmin Kalisari Ember Ngecor unit 10 8 Hamba Allah Semen sak 5 9 Sahrudin Semen sak 20
LAPORAN KEUANGAN 12 Februari 2009
Penerimaan (Rp.) Pengeluaran(Rp.)
No Tanggal Uraian Debet Tanggal Uraian Kredit Saldo (Rp.)
88 01-Feb-09
Saldo Awal bulan Januari 93,975,000
78,214,000
15,761,000
36
03-Feb-09 Besi 10inch 20btg
860,000
14,901,000
Paku 7 cm 2kg 32,000
14,869,000
paku 5 cm 2kg 32,000
14,837,000
kawat bendrad 2 kg
32,000
14,805,000
Mata gergaji 1
pcs
13,000
14,792,000
04-Feb-09 Glass box 8 bh
120,000
14,672,000 89 05-Feb-
09 Penjualan Kupon
30,000 05-Feb-09 Paku 7cm 1 kg
16,000
14,686,000
Paku 5cm 1kg
16,000
14,670,000
Besi 10" 10
btg
430,000
14,240,000
06-Feb-09 Besi 10" 10
btg
430,000
13,810,000
06-Feb-09 Pahat 1 bh
13,000
13,797,000
Reng 1 ikar
70,000
13,727,000
07-Feb-09 Ongkos Tukang+Kenek
1,415,000
12,312,000
08-Feb-09 Bata merah
1000pc
265,000
12,047,000
Semen 5 sack
270,000
11,777,000
09-Feb-09 Pasir Putih 1
truck
1,200,000
10,577,000
37
90 11-Feb-09
Penjualan Kayu Bekas 400,000
09-Feb-09 Bongkar Pasir 20,000
10,957,000
91 11-Feb-09
Bp. Hj. Mustopha 50,000
11,007,000
92 12-Feb-09
Ibu Hj. Danarti 500,000
12-Feb-09 Semen 5 sack 270,000
11,237,000
93 12-Feb-09
PT. Suar Amarta Solusindo 1,500,000
12,737,000
94 12-Feb-09
Mujiono Kalisari 500,000
13,237,000
95 12-Feb-09
Penjualan Kayu Bekas 650,000
13,887,000
12-Feb-09
Kotak Amal 1,100,000
14,987,000
Total 98,705,000
83,718,000
14,987,000
38