Upload
everett-stephens
View
216
Download
4
Embed Size (px)
Citation preview
Renewable Renewable & &
Alternative Alternative PowerPower
Senate Energy, Utilities & Communications Committee
Stuart R. Hemphill
Director, Renewable and Alternative Power
Southern California Edison
The Hon. Christine Kehoe, Chair
February 26, 2008
Page: 2
Renewable Renewable & &
Alternative Alternative PowerPower
Overview
• SCE still leads the nation in renewable deliveries• 16 percent of customers’ needs are met with renewable energy• Contracted-for renewable energy is sufficient to meet 20% target
• Based on current law, however, it is clear that load serving entities will not achieve energy deliveries of 20% by 2010
• Contracts are sufficient, but on-line timing is problematic• Transmission and a clogged interconnection queue have impeded
near term deliveries• Increasing customer demand creates a moving target
• With modest changes to existing law, 2010 deliveries may still be possible
• Expand supply options by looking out of state• Authorize the use of unbundled renewable energy credits• Expand eligibility for California Solar Initiative
Page: 3
Renewable Renewable & &
Alternative Alternative PowerPower
SCE’s Resource Mix
2007 (Estimated)
6%
7% 20%
16%
51%
Natural Gas
Renewables
NuclearCoal
Large Hydro
All Resources100% = 79 Billion kWh
62%
4%
5%
21%
8%
Geothermal
Biomass
Wind
Small Hydro
Renewable Resources100% = 12.5 Billion kWh
Solar
Page: 4
Renewable Renewable & &
Alternative Alternative PowerPower
31
4
6
11
Eligible Renewable Procurement Activity2002 To Present
• Alta Wind Power (4.9)• Calpine (2.0)• Coso (1.8)• Stirling (1.8)
35 Contracts 17 Billion kWh
Completed five solicitations to date; 2008 solicitation pending release
Contracts are primarily 10-20 year agreements
Number of Contracts
Maximum Energy Under Contract
Page: 5
Renewable Renewable & &
Alternative Alternative PowerPower
40 100 500 700 1,100 1,5002,200
4,200
15,000
28,300
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007
The Interconnection Queue Has Become Backlogged
Until 2005, there were few renewable projects in queue
Renewable projects begin to enter queue
Massive amount of projects in queue leads to breakdown of queue process
Cumulative of Renewable Generators Only in Interconnection Queue, in MW (Summer Maximum)Source: SCE Generation Interconnection Database
Note: Full generation in queue = 41,400 MW
Page: 6
Renewable Renewable & &
Alternative Alternative PowerPower
Increasing Customer Demand Creates Higher Goals
62,000
64,000
66,000
68,000
70,000
72,000
74,000
76,000
78,000
80,000
2003 2004 2005 2006
Forecasted
Recorded
GWh
Source: SCE’s Demand Forecasting Group
Mar ‘03
Mar ‘03
Mar ‘03
Mar ‘03
Apr ‘04
Apr ‘04
Apr ‘04
Dec ‘04
Dec ‘04
Oct ‘05
• Much greater level of new construction
• Higher use, due to homes in inland regions
• Historically low interest rates, including mortgage rates
Primary Causes for Higher than Expected
Growth
Page: 7
Renewable Renewable & &
Alternative Alternative PowerPower
9.0
1.8
1.4
Change in EnergyConsumption
Increase in SCE's RenewableGoals due to Increased Energy
Consumption
Direct Access Customers Returned, Creating Even Higher Goals
Returning Direct Access Customers
10.4 (15.2% Increase)
2002-2006 Change in Annual Energy Consumption (Billion kWh)
2.1 (15.2% Increase)
Page: 8
Renewable Renewable & &
Alternative Alternative PowerPower
Steps California Can Take To Increase Renewable Deliveries Before 2010
Broaden and deepen the renewables market Relax the in-state delivery requirement
Neighboring states have abundant, high quality resources Increasing supply will increase competition and reduce overall
program costs Authorize the use of Renewable Energy Credits (RECs)
Use of RECs is widespread in other states with Renewables Portfolio Standards
Increase the eligibility for the California Solar Initiative
Eliminate the “on site” requirement in the Million Solar Roofs statute to increase penetration of solar installations
Expand eligibility for CSI funds to all entities installing distribution level solar systems
Page: 9
Renewable Renewable & &
Alternative Alternative PowerPower
Estimates of Potential Energy Deliveries By 2010
Billions of kWh, SCE’s Portfolio
8.5
1.00.2
Authorizing Renewable EnergyCredits (Existing Customer-
Owned Solar)
Expanding Eligibility for CSIProgram (Assumes 500 MW of
New Development)
Expanding Eligibility for Out ofState Renewables and
Authorizing RECs (ViableProjects Rejected Due to Current
Delivery Requirements)
Percent of 2010 Energy Needs 0.25% 1.0% 10.0%
Page: 10
Renewable Renewable & &
Alternative Alternative PowerPower
Steps California Can Take To Increase Renewable Deliveries Beyond 2010
Accelerate California’s Renewable Energy Transmission Initiative
New transmission will likely take 7-10 years after new lines are identified
Encourage the federal government to extend and lengthen incentives
Production Tax Credits for wind Investment Tax Credits for solar
Support CPUC’s environmental reviews for new transmission lines
Work with federal government agencies to gain Concurrence on State renewable policy Land access to support transmission needed for renewables
With CAISO’s lead, continue to champion interconnection queue reform