Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Gallups Quarry Superfund Project Plainfield Connecticut
SDMS DocID 3934 Project No 7194138
Remedial Investigation Report Volume 1 - Text and Figures
submitted to
US EPA - Region I Boston Massachusetts
DRAFT MARCH 15 1996 FIRST REVISION AUGUST 9 1996
SECOND REVISION OCTOBER 22 1996 FINAL JUNE 1997
ENVIRONMENTAL Formerly Environmental Science amp Engineering Inc
410 Amherst Street Nashua NH 03063 Telephone (603) 889-3737
GENERAL
Volume 1
Volume 2
Volume 3
Volume 4
Volume 5
Volume 6
Volume 7
Gallups Quarry Superfimd Project - Remedial Investigation
TABLE OF CONTENTS
Text and Figures
Tables
Plates
Appendices A B C D E Famp G
Appendices H I J amp K
Appendices L M amp N
Appendices O P Q R S T U amp V
5797wpdoc8galluprifinaltextrigentoc061397 QST Environmental
Remedial Investigation
Gallups Quarry Superfund Project
Plainfield Connecticut
Submitted to
US EPA - Region I
Boston Massachusetts
Prepared by
QST Environmental
(formerly Environmental Science amp Engineering Inc)
Nashua New Hampshire
June 1997
QST Project No 71941380430
Gallups Quarry Superfund Project - RI Executive Summary
Executive Summary
EI Purpose of the Report This document presents the Remedial Investigation (RI) Report which was completed for the
Gallups Quarry Superfund Site (Site) pursuant to the requirements of US Environmental Protection Agency (EPA) Administrative Order by Consent Docket Number 1-93-1080 (Order)
issued September 7 1993 The Site is a former sand and gravel quarry and is located on Tarbox
Road in the Town of Plainfield Connecticut (see Figure E-l) The Study Area includes the Site
as well as areas west and north of the Site
Investigation of the Site was initiated in 1978 when unlicensed waste disposal operations were
discovered at the property Emergency clean-up operations were conducted in three disposal
areas by the Connecticut Department of Environmental Protection (CTDEP) in April 1978
(Metcalf amp Eddy 1993) Following the initial clean-up effort a series of surface and subsurface
sampling events were performed by the CTDEP the Connecticut Department of Health (CTDOH) and US Environmental Protection Agency (EPA) Based primarily on the detection of
groundwater contamination the Site was listed on the National Priorities List (NPL) on October 4 1989 During 1992 and 1993 EPA conducted a limited investigation through the Superfund
Technical Assessment amp Response Team (START) initiative in an effort to expedite the
completion of the Remedial InvestigationFeasibility Study (RIFS) The requirements of the
Order as well as data included in the START report (Metcalf amp Eddy 1993) provided the
framework for the Remedial Investigation
This RI Report is the sixteenth major deliverable under the Order The first major deliverable
the Remedial InvestigationFeasibility Study Work Plan - Phase 1A was finalized and submitted to EPA on August 29 1994 QST Environmental (formerly Environmental Science amp Engineering Inc (ESE)) finalized the Work Plan and has prepared all of the other deliverables
The Phase 1A field investigation was completed in January 1995 The second major deliverable
the Phase 1A Data Report dated March 24 1995 was submitted to EPA following completion of
the Phase 1A field investigation The findings of the Phase 1A Investigation were described in
the Initial Site Characterization Report (ISCR) which was finalized and submitted to EPA on
March 1 1996 A Work Plan for the Phase IB field investigation was finalized and submitted on
October 11 1995
In addition to the Phase 1A field investigation the Phase 1A Work Plan also described the Long-
Term Monitoring Program which was initiated upon completion of the Phase 1A field
investigation The Long-Term Monitoring Program includes the quarterly collection and analysis
of groundwater and semi-annual collection and analysis of surface water and nearby residential
well samples The Phase IB field investigation commenced on October 12 1995 Following the
5797wpdocsglaquollupfsfinlaquoltextexecnimmri060997 E-l QST Environmental
SOURCE PLAINFIELD CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP 75 MINUTE SERIES 1983
410 Amherst Street 124000 Nashua NH 03063
(603) 889-3737
0 GALLUPS QUARRY SUPERFUND PROJECT
PLAINFIELD CONNECTICUT SCALE IN MILES REMEDIAL INVESTIGATION REPORT
comacncur FIGURE E-l
SITE LOCATION MAP DRAWING NAME ELOCDWG FILE NUMBER 7194-138
QUADRANGLE LOCATION
SCALE AS SHOWN REVISION 0 I DRAWN BY PAP [DATE 5997
Gallups Quarry Superand Project - RI Executive Summary
completion of drilling activities the Phase IB groundwater sampling task and the fourth quarter
1995 Long-Term Monitoring sampling event were performed simultaneously in November 1995
Seven Data Reports have been submitted to the EPA for the following Long-Term Monitoring
Program sampling events the second and third quarters of 1995 all four quarters of 1996 and
the first quarter of 1997 (ESE 1996a 1996b 1996c 1997a 1997b) The draft RI Report was
submitted to EPA on March 15 1996 (and revised and resubmitted October 22 1996) and included the results of the fourth quarter of 1995 sampling event On March 29 1996 the
following two deliverables were submitted to EPA Development and Initial Screening of Alternatives Report and Detailed Analysis Work Plan The draft Feasibility Study was submitted
to EPA on January 27 1997 This RI Report describes the methods and findings of both the Phase 1A and IB field studies and includes data collected during the April July and November
1995 February May August and November 1996 and February 1997 Long-Term Monitoring
sampling events
E2 Site Background E21 Area Description
The 29-acre Gallups Quarry Site is located on the north side of Tarbox Road in the Town of
Plainfield Windham County Connecticut The Site which is currently vacant is bounded by
wooded areas and wetlands associated with Mill Brook (which flows from east to west
approximately 250 feet north of the Site) single-family residences and several commercial
properties Approximately 700 feet north of the Site on the opposite side of Mill Brook is an industrial park which contains an Intermark Fabric Corporation facility (formerly the Pervel
Industries flock plant) and a Safety Kleen Corporation accumulation facility Further north of the
industrial park are several presently vacant mill buildings which were previously occupied by various manufacturers including Pervel Industries and the InterRoyal Corporation The Plainfield sewage treatment plant which discharges to Mill Brook and its major tributary (Fry Brook) is
located approximately 1800 feet northwest of the property
E22 Site Operational History
Limited information is available regarding the early operational history of the Site Historical
aerial photographs and records at the Town of Plainfield Assessors office indicate that in 1951
the Site was owned by a Mr Johnson and that some quarrying activities were underway in the
southern portion of the Site In 1964 the Site was purchased by C Stanton Gallup Although
detailed usage of the Site from 1964 through 1977 is poorly documented records indicate that the
Site was used as a source of aggregate and was occupied by the Connecticut Department of
Transportation (CTDOT) who were operating an asphalt batching plant
5797WTgtdocsgallupfsfinltextexec8ummri060997 E-3 QST Environmental
Gallups Quarry Superfund Project - RI Executive Summary
As a result of complaints from neighboring residents the CTDEP and the Connecticut State
Police initiated an investigation of the Site in January of 1978 The CTDEP investigation
concluded that the Site was used from the summer of 1977 until December 1977 for unlicensed
waste disposal Evidence collected by CTDEP indicates that Chemical Waste Removal Inc
(CWR) of Bridgeport Connecticut transported drummed and bulk liquid waste material to the
Site These materials reportedly included a variety of industrial wastes
Emergency clean up efforts were performed during the summer of 1978 under the direction of the
CTDEP and the Connecticut State Police This involved the removal and off-site disposal of
1584 drums 5000 gallons of free liquid and 2277 cubic yards of contaminated soil from three
distinct locations on the Site The drums as well as liquid waste and contaminated soil were
removed from the Primary and Secondary Disposal Areas located in the northern portion of the
Site Remedial measures performed at the Seepage Bed reportedly located in the central portion
of the Site included the excavation of contaminated soil and in-situ treatment of remaining soils
through the addition of 20 tons of lime A buried inverted dump truck body was also reportedly
removed from the Site In addition to these remedial activities mine detectors were utilized to search for additional buried drums There was no evidence of additional buried drums and it
was believed that all drums were recovered during the cleanup operations
Since the 1978 cleanup operations the Site has been vacant although there are some indications
that the Site has been utilized by trespassers for recreational purposes
E23 Summary of Previous Investigation
ations and sampling events were conducted at the Gallups Quarry Site The significant previous
investigations are as follows
bull A general site investigation performed on behalf of the State of Connecticut (Fuss amp
ONeill 1979) which included the installation of 22 monitoring wells 19 test pits (13
of which were completed as shallow monitoring wells) and the collection of surface
water and sediment samples The investigation was completed within several months
of the States remedial efforts described above Groundwater from monitoring wells
and nearby residential wells as well as surface water from Mill Brook was sampled
several times from the period of July to December 1978
bull Various CTDEP monitoring events for groundwater surface water and sediment
occurred from 1979 until 1993 Sampling events were conducted in October 1979
January and November 1980 April and October 1981 April 1982 and December
1983 CTDEP also performed a biodiversity survey in 1985 in an effort to evaluate
potential impacts to the Mill Brook wetland In addition CTDEP also conducted
sampling anq (analysis of neighboring residential wells in 1992 and 1993
5797wpdocraquogallupf8finlaquoltextexecsummri060997 E-4 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
bull A Hazard Ranking System (HRS) Study was completed in 1987 by NUS Corporation
foi ZPA The Study included the collection of water samples from two existing
moiiitoring wells and three surface watersediment locations
bull A review of historic aerial photographs of the Study Area was performed by the
Bionetics Corporation on behalf of the EPA Photographs dating back to 1951 were
included in the review which was published in 1990 (Bionetics Corp 1990)
bull In cooperation with EPA the USGS performed a geohydrologic investigation at the
Study Area in 1993 This investigation included geophysical surveys (EM-34 and GPR) to characterize various subsurface features One monitoring well was installed
bull In 1993 the US Fish and Wildlife Service performed a field study to characterize the
habitats within the Study Area The study was finalized in 1995
bull Various sampling events were conducted in 1989 and 1993 on behalf of the EPA During these sampling events groundwater from existing monitoring wells and nearby
residential wells as well as surface soil samples were collected for analysis
The significant findings of these investigations are summarized as follows
bull The initial study completed at the Site by Fuss amp ONeill in 1979 concluded that
groundwater in the vicinity of the former disposal areas had been impacted by certain
volatile organic compounds (VOC) and metals A well-defined groundwater plume which contained these various constituents extended in a northwest direction away
from the Site
bull Periodic CTDEP sampling events from 1979-1982 indicated the wells downgradient of
the former disposal areas consistently showed detectable levels of constituents similar
to those disposed of on-site The results of CTDEP sampling events indicated that
nearby residential wells had not been impacted by the Site
bull The USGS study provided an updated geological characterization of the Study Area
and suggested the potential presence of a bedrock fault zone located in the vicinity of
the Former Seepage Bed
bull The results of the 1989 and 1993 sampling events generally confirmed the findings of
previous groundwater quality investigations and indicated that VOC concentrations
decreased significantly in the period between 1982 and 1993
5797wpdocgglaquollupfsfiiultextexecnjmmri060997 E-5 QST Environmental
Gallups Quarry Superfiotd Project - RI Executive Summary
To supplement historical data and data obtained during the Phase 1A field program a CTDEP file
search was performed to obtain information pertinent to groundwater contamination for industrial
properties neighboring the Site The available information indicates that
bull two separate companies Pervel Industries and InterRoyal Corporation operated
manufacturing facilities at locations approximately 2500 feet north of the Site
bull Pervel Industries also maintained a second facility (a fabric flock plant) located
approximately 1000 feet north of the Site across Mill Brook
bull there have been documented releases of 111-trichloroethane (TCA) and toluene at
the northern-most Pervel plant
bull contaminated soil and sediment associated with a 1985 spill of 111-TCA at the
northern-most Pervel facility was stored in an impoundment located on the eastern
(upgradient) side of the Pervel flock plant property
bull the contaminated soilsediment impoundment was located approximately 1000 feet
from the northern end of the Site
bull the results of historical groundwater monitoring at the former Pervel flock plant
located a few hundred feet north of the Site show the presence of elevated
concentrations of several VOC including tetrachloroethene (PCE) and TCA
E3 Summary of Remedial Investigations Phase 1A Field Investigations
In order to maximize the efficiency of the Site characterization program for the Gallups Quarry
Site multiple phases of data collection and evaluation were performed during the Phase 1A field
program Screening level surveys completed during the initial weeks of the field program
utilizing fast-turnaround data generation and evaluation techniques were used to focus data
collection efforts during the latter part of the Phase 1A field program The screening surveys
included
bull A visual site reconnaissance involving transit by foot and direct observations and
photographic documentation of significant features along approximately 39000 feet of
trend lines covering the entire Site
bull Geophysical surveys including electromagnetic terrain conductivity (EM) and
magnetometer surveys along 25-foot spaced trend lines totalling approximately
5797wpdocBgallupf8finaltextexeclaquoummri060997 E-6 Q5T Environmental
Gallups Quarry Superfimd Project - Rl Executive Summary
39000 feet in length and covering the entire Site follow-up EM-31 and
magnetometer surveys and a test pit program in three areas where anomalies were
observed and a seismic refraction survey west of the Former Seepage Bed
bull A microwell survey which included the collection of 126 groundwater samples from
multiple depths at 50 locations within the Study Area field gas chromatograph
analyses of all of these samples for an indicator list of 8 VOC laboratory analyses of
121 of these samples for metals and 12 of the samples for VOC and
bull A soil vapor survey which involved the collection of soil vapor samples from 106
locations throughout the Site and on-site analyses for an indicator list of 8 VOC
Based on these screening level and historical data a groundwater monitoring well installation
sampling and analytical program was designed The program as approved by EPA included the
following
bull The installation of 5 wells at 2 designated background locations These wells include
a shallow overburden and a bedrock well in the northern portion of the Site and two
overburden wells (screened at the water table and in a deeper till horizon) and a
bedrock well in the southern portion of the Site Background soil and groundwater
samples were collected from these locations
bull The installation of 19 wells at seven locations downgradient (northwest) of the Former
Primary and Secondary Disposal Areas to assess and define the boundaries of a
contaminant plume identified during the microwell survey These wells included 17
overburden wells and two bedrock wells
bull The installation of six wells at three locations located north and east of the Former
Primary Disposal Area to assess groundwater quality and flow directions in these
areas These wells included five wells screened in overburden and one in bedrock
bull The installation of two bedrock wells and one overburden well at two locations in the
vicinity of the Former Seepage Bed This included one bedrock well placed within an
inferred bedrock faultfracture zone to assess the zones potential to act as a preferred
contaminant transport pathway
bull The installation of five wells at two locations in the southern portion of the Site to
assess very limited screening-level VOC detections in this portion of the property
These wells include four overburden wells (two shallow and two top-of-till) and one
5797wpdoclaquoglaquollupftfinlaquolte)rtexecraquoummri060997 E-7 QST Environmental
Gallups Quarry Superfund Project - RI Executive Summary
bedrock well In addition six groundwater piezometers were installed to assess groundwater flow directions in the southern portion of the Study Area gtmdashr
Samples from three of the newly installed wells (MW102TT MW106TT and MW116T) were analyzed for Appendix IX parameters Samples from the remaining newly installed monitoring wells and three existing wells (SW-9 SW-10 SW-12) were analyzed for Target Analyte ListTarget Compound List (TALTCL) parameters Twelve nearby residential wells were also sampled for TALTCL parameters (although VOC were analyzed using EPA method 5242) In addition to the monitoring well installation and groundwater sampling program outlined above the following tasks were performed during the Phase 1A field program
bull Air quality monitoring to establish ambient air quality prior to and during the intrusive investigations A total of eight air monitoring stations were established at locations within and at the Site perimeter
bull Water-level measurements were recorded to assess horizontal and vertical groundwater flow directions and aquifer testing (including evaluations of the remaining existing monitoring wells) using slug tests was conducted to assess the hydraulic conductivity of the aquifer
bull Soil boring programs within the three known disposal areas to assess the nature and extent of residual contamination A total of ten soil borings were completed at the three areas Each boring was continuously sampled and terminated at auger refusal Selected samples were submitted for laboratory analysis for TALTCL parameters based on lithology depth and photoionization detector (PID) headspace readings as set forth in the Work Plan
bull Surface watersediment sampling was performed at 17 locations including Mill Brook Fry Brook Packers Pond and in an unnamed pond on Tarbox Road just south of the entrance to the Site In addition wetland soil samples were collected from 10 locations within the Study Area All samples were submitted for analysis for TALTCL parameters
bull Federal and State jurisdiction^ wetland delineations were performed
Phase IB Field Investigations The data collected during Phase 1A was supplemented with the following additional investigative activities conducted during the Phase IB field investigation
5797wpdocsgallupfsfiMltextexecsummri060997 E-8 QST Environmental
Gallups Quarry Superand Project - RI Executive Summary
bull Quantitative air monitoring for site-specific compounds in the vicinity of the Former
Prirary Disposal Area
bull Collection and analysis of soil samples from six additional soil borings in the Former
Primary Disposal Area to more fully characterize the extent of residual VOC and PCB
contamination
bull The installation of seven additional groundwater monitoring wells and one additional
piezometer to obtain additional groundwater data from the downgradient portion of the
plume and from the northnorthwest portion of the Site The monitoring wells
included (3) two well clusters and (1) bedrock well
bull Collection of groundwater samples from each new monitoring well and from five
existing wells on the former Pervel facility and analysis of these samples for VOC to confirm the downgradient extent of the plume originating in the Former Primary
Disposal Area and
bull The performance of constant flow tests consisting of short-term pumping tests on selected groundwater monitoring wells to supplement Phase 1A hydraulic conductivity
data so that groundwater velocities and transport rates and aquifer yield could be
more accurately determined
Long-Term Monitoring Program
A Long Term Monitoring Program was initiated upon completion of the Phase 1A field investigation The Long-Term Monitoring Program includes the quarterly collection and analysis
of groundwater and semi-annual collection and analysis of surface water and nearby residential
well samples Data from eight quarterly sampling rounds (performed in April July and
November 1995 February May August and November 1996 and February 1997) are presented
and discussed The Conceptual Model discussion is based on the 1995 quarterly sampling rounds
Any minor adjustments to the Conceptual Model resulting from later monitoring rounds are
addressed in the FS
E4 Conceptual Model of the Study Area E41 Physical Characteristics E411 Physiography
The Site is located along the eastern border of the Quinebaug Valley Lowland The region is
characterized by relatively low relief and numerous glacial features The regional landscape is
5797wpdoc8glaquollupfBfinaltextexecraquoummri060997 E-9 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
significantly influenced by the structure of the underlying crystalline metamorphic bedrock The
topography of the Site is highly irregular primarily due to past quarrying operations including
numerous overgrown mounds of earthen materials and excavated depressions The ground
surface on the Site generally slopes from the east to the west and to a large degree is controlled by the underlying bedrock surface North and west of the Site the ground surface elevation
decreases in the Mill Brook floodplain which is described as a low lying heavily vegetated
wetland
E412 Geology
The overburden deposits in the area consist of materials deposited as a result of glacial processes during the Pleistocene epoch A range of glacially-derived materials including till meltwater or
stratified drift deposits and post-glacial deposits of floodplain alluvium comprise the major
surficial geologic units in the vicinity of the Site The significant surficial deposits encountered
within the Study Area during the RI are till and stratified drift Stratified drift deposits can be
further broken down into coarser-grained or finer-grained components The Study Area is
dominated by coarser-grained deposits which represent various ice-contact or outwash features associated with the retreat of the ice-mass Finer-grained components also exist to a limited
extent within the Study Area and are the result of lacustrine deposition which occurred when
low-lying areas were inundated by a glacial lake Much of the Sites overburden geology
represents the transition of depositional environments as the glacier progressively retreated from
the area Although alluvial floodplain deposits were encountered at locations within the present
Mill Brook floodplain the significance of these deposits is minor
The thickness of the stratified drift deposits range from non-existent in the vicinity of bedrock
outcrops in the eastern portion of the Site to approximately 70 feet The overburden thickness
increases in response to a decrease in the elevation of the bedrock surface Till was encountered just above the bedrock surface at nearly every location The till horizon ranges in thickness from
approximately 10 to 20 feet with the thickest accumulations located along bedrock highs
Surficial exposures of glacial till were observed on the Site The till is relatively dense and is
comprised of a fine sandy matrix with abundant gravel cobbles and boulders
Bedrock in the vicinity of the Site mapped as a lower member of the Quinebaug Formation
consists of hornblende gneiss biotite gneiss and amphibolite and is strongly faulted and folded
exhibiting varying degrees of mylonitization Geophysical surveys performed prior to and during
the Phase 1A field program indicate that a northwest-trending fracture zone may extend across the
central portion of the Site Based on the drilling program depths to bedrock range from zero to
83 feet below ground surface within the Study Area Bedrock elevations are greatest in the
eastern central portion of the Site and decrease to the north and west and to a lesser degree to
the south
5797wpdocsgallupfsfinaltextexecsummri060997 E-10 QSTEnvironmental
Gallups Quarry Superfund Project - RI Executive Summary
E413 Hydrogeology
E4131 Hydraulic Conductivity
The hydraulic conductivity distributions within the overburden and bedrock formations were
evaluated through the performance of constant flow (pumping) tests and rising and falling head
slug tests Hydraulic conductivity measurements indicate that coarse-grained stratified drift
deposits in the lower portion of the aquifer are the most permeable subsurface materials in the Study Area with a mean hydraulic conductivity of 0005 centimeters per second (cms) The
highest hydraulic conductivities were found in the lower portion of the aquifer northwest of the Former Primary Disposal Area where the mean hydraulic conductivity is 0037 cms The mean
hydraulic conductivity of the finer-grained deposits in the upper portion of the aquifer is about
0001 cms
The mean hydraulic conductivity for the till wells (000047 cms) is a factor of ten less than the
average value for coarse stratified drift and varies between 00002 cms and 0002 cms The till
appears to be hydrogeologically distinct from the other overburden deposits and on the average
provides increased resistance to groundwater flow This added resistance is not considered to be
significant however because the consistency of the till and overburden deposits are highly
variable and the hydraulic conductivity contrast is relatively small The slug test results for the
bedrock wells yield the lowest (000018 cms) average hydraulic conductivity
E4132 Groundwater Flow
Horizontal Flow
Overburden groundwater flow south of the Former Seepage Bed is primarily east to west and is
influenced by two factors (1) the slope of the bedrock surface which defines the base of the
unconsolidated deposits and (2) regional hydrologic drainage patterns The average east-west horizontal hydraulic gradient in the southern portion of the Study Area is approximately 001 feet
per foot (feet change in piezometric head per horizontal foot of distance)
In the northern portion of the Study Area three hydrogeologically distinct zones exist South of the Former Primary and Secondary Disposal Areas the hydraulic gradient is steep (approximately
003 feet per foot) and is strongly influenced by the dip of the bedrock surface (01 feet per foot)
The saturated thickness increases from zero south of well MW109 to about 20 to 30 feet near the
former disposal areas North-northwest of the former disposal areas the hydraulic gradient
lessens significantly to a range of 00003 to 00007 feet per foot representing a factor of 40 to
100 reduction North-northeast of Mill Brook the hydraulic gradient is about 0007 feet per foot
Available data indicate that currently northwest of the railroad tracks groundwater flow in the middle to lower portions of the aquifer converges from the northeast and southwest toward a
centerline area generally defined in the downgradient direction by wells MW105 MW102 and
5797wpdoclaquoglaquoliupfraquofirultextexeclaquoummri060997 E-ll QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
MW101 The flow direction near these wells is from the former disposal areas to the northwest
Northeast of this centerline groundwater flows in a southwesterly direction from the vicinity of
Mill Brook and the former Pervel flock plant North of Mill Brook and west of the railroad
tracks the predominant groundwater flow direction becomes more westerly
No significant seasonal changes in horizontal groundwater flow directions were observed in the
Study Area Groundwater levels were generally highest in January 1995 and decreased by about
two feet through the period ending on July 11 1995 Levels then increased by about one foot
from July to November
General overburden groundwater pathlines for the northern portion of the Site are shown on
Figure E-2
Groundwater in bedrock moves primarily in a westerly direction south of the Former Seepage
Bed while in the northern Study Area the predominant bedrock flow component is toward the
northwest In both areas the hydraulic gradient is on the order of 002 feet per foot Groundwater in bedrock near the Former Seepage Bed flows to the northwest and exhibits no apparent
influence from the locally identified fracture zones
Vertical Flow
Vertical flow of groundwater is an important component in the upper several feet of the bedrock
unit Water level measurements indicate that groundwater is discharging from bedrock into the
overburden at every location measured except MW109 In most clusters the vertical hydraulic
gradient between bedrock and overburden is an order of magnitude greater than the horizontal
gradient
In the overburden aquifer the downward vertical flow component is significant within shallow
deposits near the Former Primary Disposal Area (wells MW107 MW108 and MW116) and the
upward flow is important in the upper portion of the aquifer near Mill Brook The downward
groundwater flow within the Former Primary Disposal Area appears to be primarily associated
with infiltration of precipitation and collection of surface water runoff from upland areas This
causes VOC concentrations to be highest in the middle to lower portions of the aquifer Stream
5797wpdocsgallupftfinaltextexecsummri060997 E-12 QST Environmental
N
LEGEND
WATERCOURSE
PROPERTY BOUNDARY
bullPIEZOMETRIC HEAD CONTOUR LOWER PORTION OF AQUIFER NOVEMBER 6 1995 (FEET)
GROUNDWATER PATHLINE
NOTES
1 BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM - CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
400 400 800
SCALE IN FEET
410 Amherst Street Nashua NH 03063
(603) 889-3737 UmHOHHM
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE E-2
SJjTff WIDE GROUNDWATER FLOW DRAWING NAM6 RIWIDEFWDWG FILE NUMBER 7194 138
SCALEAS SHAWN REVISION 1 DRAWN BY DJB DATE 5997
Gallups Quarry Superfiind Project - RI Executive Summary
piezometer data and groundwater flow modeling indicate that Mill Brook generally gains water
from the overburden aquifer within the Study Area
E414 Ecology
Wetlands delineations were performed to the extreme northern and western boundaries of the
Study Area up to the Mill Brook channel using both the State of Connecticuts accepted criteria
(which focuses on soil types and hydric soil characteristics) and the Federal criteria using US
Army Corps of Engineer methods (which includes the examination of vegetation hydrology and
soils) Most of the wetlandupland boundary occurs along the edge of a steep grade The sharp
relief produces a narrow transition between uplands and wetlands The delineated lines reflect
this as the State and USACOE wetland boundaries coincide at nearly every location With the
exception of an area intersecting a small portion of the Site at the northernmost edge of the
property east of the former disposal areas no wetland areas were identified on the Site
A preliminary identification of plant and animal species present in the Study Area was conducted during the wetlands delineation A limited number of wildlife species were observed Numerous
plant species were identified over the heavily vegetated Study Area No endangered species were
observed nor are reported to reside in the Study Area
E42 Nature and Extent of Contamination
E421 Contaminant Source Investigation The following summarizes the findings of contaminant source investigations conducted during the
RI program
bull Previous remedial activities have completely removed the waste materials (intact drums and bulk liquid waste) from the Site
bull The Former Seepage Bed and the Former Secondary Disposal Area contain
little residual contamination from the disposal activities which occurred in the
late 1970s
bull Residual levels of contamination primarily VOC and PCB were measured in
the Former Primary Disposal Area In general the highest levels of VOC are
located at or just below the groundwater table in native soils immediately
beneath the fill materials and diminish rapidly with depth Low levels of
PCB were detected primarily within shallow fill materials
5797wpdocraquogallupftfinlaquoltextexecraquoummri060997 E-14 QST Environmental
Gallups Quarry Superfiutd Project - Rl Executive Summary
bull Other than the three known former disposal areas and the remains of a
former CTDOT asphalt plant no other disposal areas were found to exist on -
the Site
E422 Groundwater Quality
Groundwater quality data collected during the Remedial Investigation indicate the following
bull No significant groundwater contamination was detected within the overburden
or bedrock units in either the southern Study Area or in the vicinity of the
Former Seepage Bed
bull In the northern Study Area a narrow low to moderate-concentration VOC
plume was detected in the overburden aquifer extending from the vicinity of
the Former Primary Disposal Area to the northwest towards Mill Brook
TCA and DCE were consistently detected at all locations along the plume
centerline at concentrations as high as 240 ppb and 1300 ppb respectively
bull Comparison of present concentrations with historical data indicate that VOC
levels are significantly decreasing with time From 1978 through 1995 TCA
TCE and PCE concentrations have decreased on the average by more than a
factor of two every two years representing environmental half-lives of less
than two years
bull The size and orientation of the plume are in excellent agreement with the
established groundwater flow directions
bull Available information indicates that the leading edge of the VOC plume
associated with the Former Primary Disposal Area is located in the vicinity of
monitoring well clusters MW-102 and MW-101 Concentrations of TCA and
DCE reduce to below MCLs at MW-101 Contaminant migration rates also
support this delineation of the front of the site-related VOC plume
bull Increasing PCE detections in the downgradient portion of the plume exhibit
inconsistencies with calculated migration rates from the Site Groundwater
flow directions VOC transport rates and historical concentration trends
indicate that PCE detections in wells MW118 MW116 MW103 MW118
MW102 and MW101 may be associated with contaminant transport from the
former Pervel flock plant However it is also possible that the PCE
detections at locations MW102 and MW101 are attributable to the former
disposal areas In addition contaminated groundwater from Pervel may have
5797wpdocsgal]upfraquofinaltextexeclaquoummri060997 E-15 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
also contributed TCA TCE DCE and vinyl chloride to the site related VOC
plume
Results of surface watersediment sampling and analyses stream piezometer measurements and groundwater flow modeling indicate that some discharge
of the shallow portion of the plume into Mill Brook is occurring However
the concentrations of VOC detected in the brook are well below those
reported to cause adverse effects in fish or wildlife
Bedrock is not considered a preferred pathway for contaminant migration due
to its characteristically low hydraulic conductivity and the predominantly
upward component of groundwater flow from bedrock to overburden which
exists throughout the Study Area
5797wpdocsgallupftfinlaquoltcxtexec8ummri060997 E-16 QfT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents
Section Page
10 Introduction bdquo 1-1
11 Purpose of the Report 1-1 12 Report Organization 1-2
13 Site Background 1-3 131 Area Description Demography and Land Use 1-3 132 Operational History 1-5
133 Summary of Previous Investigations 1-7
20 Field Investigations 2-1
21 Site Survey 2-1
211 Initial Site Survey 2-1
212 As-Installed Survey 2-1
22 Site Reconnaissance 2-2
221 Visual Observations of the Ground Surface 2-2
222 Air Quality Survey 2-2
223 Exclusion Zone Identification 2-4
224 Project Support Measures 2-4
225 Identification of Sensitive Human Receptors 2-5
23 Geophysical Surveys 2-5
231 Electromagnetic Terrain Conductivity (EM) Survey 2-7 232 Magnetometer (MAG) Survey 2-7
233 Additional EM and MAG Surveys 2-8
234 Seismic Refraction Survey 2-8
24 Groundwater Sampling Using Temporary Well Points 2-9
25 Soil Gas Survey 2-12
26 Soil Borings at Disposal Areas 2-15
261 Phase 1A Soil Borings 2-15
262 Phase IB Soil Borings 2-16 27 Installation of Monitoring Wells and Background Soils Sampling 2-17
271 Phase 1A Monitoring Well Placement-Rationale 2-19
272 Phase IB Monitoring Well Placement-Rationale 2-21
273 General Monitoring Well Installation Techniques 2-22
274 Stream Piezometers and Gauges 2-24
5797wpdocsgalluprifinaltextmarterrifhl061297 i QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
Table of Contents (continued)
275 Groundwater Piezometers 2-25
28 Aquifer Parameter Testing 2-25
281 Grain Size Analysis 2-25
282 Slug Tests 2-26
283 Constant Flow Tests 2-26
29 Groundwater Sampling 2-26
291 Monitoring Wells 2-27
292 Residential Wells 2-29
210 Surface Water and Sediment Sampling 2-29
211 Wetland Soil Sampling 2-31
212 Evaluation of Existing Monitoring Wells 2-31
213 Ecological Assessment 2-32
2131 Wetland Delineation 2-32 2132 Plant and Wildlife Survey 2-33
214 Test Pit Explorations 2-33
30 Physical Characteristics of the Study Area 3-1
31 General Characteristics 3-1
311 Regional Physiography 3-1
312 Study Area Physiography 3-1
313 Surface Water Features 3-2
314 Climate 3-3
32 Geology 3-3
321 Regional Surficial Geology 3-3
322 Local Surficial Geology 3-4
323 Regional Bedrock Geology 3-7
324 Local Bedrock Geology 3-8
33 Hydrogeology 3-9
331 Hydraulic Conductivity 3-9
332 Groundwater Flow 3-10
34 Ecology 3-17
341 Wetland Delineation 3-17
342 Plant and Animal Survey 3-19
40 Nature and Extent of Contamination 4-1
41 Contaminant Source Investigation 4-2
5797wpdocsggtlluprifinaltextmasteiTifhl061297 ii QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
Table of Contents (continued)
411 Visual Site Reconnaissance 4-2
412 Soil Vapor Survey 4-4
413 Geophysical Investigations and Test Pits 4-5
414 Background Soils 4-6
415 Soils From Former Known Disposal Areas 4-7
416 Contaminant Source Investigations Summary 4-15
42 Groundwater Quality 4-17
421 Temporary Well Point Investigation 4-17
422 Groundwater Monitoring Wells 4-18
423 Residential Wells 4-26
43 Surface Water Sediment and Wetland Soils 4-27 431 Surface Water 4-27
432 Sediment 4-31
433 Wetland Soils 4-32
44 Air Quality 4-34
441 Baseline Air Quality Survey 4-34
442 Perimeter Air Monitoring 4-34
45 Potential Sensitive Human Receptors 4-35
50 Contaminant Fate and Transport 5-1
51 Theory 5-1
511 Advection by Groundwater Flow 5-1
512 Dispersion 5-3 513 Advection Due to Fluid Density Differences 5-5
514 Biological and Chemical Degradation 5-5
515 Volatilization 5-7
516 Aqueous Solubility 5-7
52 Study Area-Specific Characteristics 5-7
521 Retardation Factors 5-7
522 Chemical Migration Rates 5-9
523 Time-Dependent Concentration Reductions 5-14
5797wpdocBg8lluprifinaltextmlaquo8terrifhl061297 Hi QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
60 Summary and Conclusions 6-1
61 Conceptual Model of the Study Area 6-1
611 Geology 6-1
612 Hydrogeology 6-2
613 Nature and Extent of Contamination bdquo 6-5
70 References 7-1
5797wpdocsgnlluprifinlaquoltextmasterriftil061297 Jy QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Table of Contents (continued)
List of Tables
Table 1-1 Summary of Results of Groundwater Analyses (CTDEP)
Table 1-2 Summary of Results of Groundwater Analyses (MampE 1993)
Table 1-3 Summary of Results of Groundwater Analyses Former Pervel Flock Plant (HRP)
Table 2-1 Microwell Sampling Intervals
Table 2-2 Former Disposal Area Soil Samples Submitted for Laboratory Analyses
Table 2-3 Monitoring Well Survey Data and Screen Intervals
Table 2-4 Geologic Descriptions of Soil Samples Collected for Grain Size Analyses
Table 2-5 Sample Inventory
Table 2-6 Existing Well Summary
Table 3-1 Hydraulic Conductivity Values
Table 3-2 Hydraulic Conductivity Values Estimated from Grain Size Distributions
Table 3-3 Monitoring Well Water Level Elevation Data
Table 3-4 Summary of Vertical Hydraulic Gradients Between Pairs of MWs in Study Area
Table 3-5 Stream Piezometer Water Level Elevation Data
Table 3-6 Plants Identified During the Wetland Delineation
Table 4-1 Summary of Visual Site Reconnaissance
Table 4-2 Background Soil Volatile Organic Compounds Table 4-3 Background Soil MetalsCyanide
Table 4-4 Disposal Areas Soil Volatile Organic Compounds
Table 4-5 Disposal Areas Soil Semivolatile Organic Compounds
Table 4-6 Disposal Areas Soil PesticidesPCB
Table 4-7 Disposal Areas Soil MetalsCyanide
Table 4-8 Microwell Survey Selected Volatile Organics
Table 4-9 Microwell Survey Results of Volatile Organics Laboratory Analyses
Table 4-10 Microwell Survey Results of Inorganic Laboratory Analyses
Table 4-11 Groundwater Volatile Organic Compounds January 1995
Table 4-12 Groundwater Volatile Organic Compounds April 1995
Table 4-13 Groundwater Volatile Organic Compounds July 1995
Table 4-14 Groundwater Volatile Organic Compounds November 1995
5797wpdocggalluprifinraquoltextmalaquoterrifhl061297 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Tables (Contd)
Table 4-15 Groundwater Volatile Organic Compounds February 1996
Table 4-16 Groundwater Volatile Organic Compounds May 1996
Table 4-17 Groundwater Volatile Organic Compounds August 1996
Table 4-18 Groundwater Volatile Organic Compounds November 1996
Table 4-19 Groundwater Volatile Organic Compounds February 1997
Table 4-20 Groundwater Semivolatile Organic Compounds January 1995
Table 4-21 Groundwater Semivolatile Organic Compounds April 1995
Table 4-22 Groundwater Semivolatile Organic Compounds July 1995
Table 4-23 Groundwater Semivolatile Organic Compounds November 1995
Table 4-24 Groundwater Semivolatile Organic Compounds February 1996
Table 4-25 Groundwater Semivolatile Organic Compounds May 1996 Table 4-26 Groundwater Semivolatile Organic Compounds August 1996
Table 4-27 Groundwater Semivolatile Organic Compounds November 1996
Table 4-28 Groundwater Semivolatile Organic Compounds February 1997
Table 4-29 Groundwater PesticidesPCB April July and November 1995 February and August 1996 February 1997
Table 4-30 Groundwater MetalsCyanide January 1995
Table 4-31 Groundwater MetalsCyanide April 1995
Table 4-32 Groundwater MetalsCyanide July 1995
Table 4-33 Groundwater MetalsCyanide November 1995
Table 4-34 Groundwater MetalsCyanide February 1996
Table 4-35 Groundwater MetalsCyanide May 1996
Table 4-36 Groundwater MetalsCyanide August 1996
Table 4-37 Groundwater MetalsCyanide November 1996
Table 4-38 Groundwater Metals February 1997
Table 4-39 Residential Wells Volatile Organic Compounds January 1995
Table 4-40 Residential Wells Volatile Organic Compounds July 1995
Table 4-41 Residential Wells Volatile Organic Compounds February 1996
Table 4-42 Residential Wells Volatile Organic Compounds August 1996
Table 4-43 Residential Wells PesticidesPCB January 1995
Table 4-44 Residential Wells PesticidesPCB July 1995
Table 4-45 Residential Wells PesticidesPCB February 1996
Table 4-46 Residential Wells PesticidePCB August 1996
Table 4-47 Residential Wells Metals January 1995
5797wpdocsg lluprifinaltextmastemfiil061297 VI QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Tables (Contd)
Table 4^8 Residential Wells Metals July 1995
Table 4-49 Residential Wells MetalsCyanide February 1996
Table 4-50 Residential Wells MetalsCyanide August 1996
Table 4-51 Field Observations of Habitat and Water Quality September 1994
Table 4-52 Surface Water Quality April and November 1995 May and November 1996
Table 4-53 Surface Water Volatile Organic Compounds September 1994
Table 4-54 Surface Water Volatile Organic Compounds April 1995
Table 4-55 Surface Water Volatile Organic Compounds November 1995
Table 4-56 Surface Water Volatile Organic Compounds May 1996
Table 4-57 Surface Water Volatile Organic Compounds November 1996
Table 4-58 Surface Water Volatile Organic Compounds September 1994 April 1995 May
1996
Table 4-59 Surface Water Total MetalsCyanide September 1994
Table 4-60 Surface Water Dissolved Metals September 1994
Table 4-61 Surface Water Total Metals April 1995
Table 4-62 Surface Water Dissolved Metals April 1995
Table 4-63 Surface Water Total and Dissolved Metals November 1995
Table 4-64 Surface Water Total and Dissolved Metals May 1996
Table 4-65 Surface Water Total and Dissolved Metals November 1996
Table 4-66 SedimentWetland Soils Metals September 1994
Table 4-67 SedimentWetland Soils Volatile Organic Compounds September 1994 Table 4-68 SedimentWetland Soils Semivolatile Organic Compounds September 1994
Table 4-69 SedimentWetland Soils PesticidesPCB September 1994
Table 4-70 Human Receptors Survey Location of Day Care Facilities Within 1-Mile Radius
of Site
Table 5-1 Fate and Transport Parameters for Study Area Volatile Organic Compounds
Table 5-2 Total Organic Carbon Measurements for Soil Samples
Table 5-3 Historical Concentration Data
5797wpdoclaquoglaquolluprifinaltextmasterriftil061297 Vll QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Figures
Figure E-l Site Location Map
Figure E-2 Site Wide Groundwater Flow
Figure 1-1 Site Location Map
Figure 1-2 Property Boundaries and Adjacent Landowners
Figure 1-3 Surface Water and Groundwater Classification Zones and Locations of Former
Disposal Areas
Figure 1-4 Groundwater Monitoring Wells Installed by Fuss amp ONeill
Figure 1-5 Site Location Map and Nearby Industrial Properties
Figure 3-1 Groundwater Elevations MW101 Series Figure 3-2 Groundwater Elevations MW102 Series
Figure 3-3 Groundwater Elevations MW103 Series
Figure 3-4 Groundwater Elevations MW104 Series
Figure 3-5 Groundwater Elevations MW105 Series
Figure 3-6 Groundwater Elevations MW106 Series
Figure 3-7 Groundwater Elevations MW107 Series
Figure 3-8 Groundwater Elevations MW108 Series
Figure 3-9 Groundwater Elevations MW109 Series
Figure 3-10 Groundwater Elevations MW110 Series
Figure 3-11 Groundwater Elevations MW111 Series
Figure 3-12 Groundwater Elevations MW112 Series
Figure 3-13 Groundwater Elevations MW113 Series
Figure 3-14 Groundwater Elevations MW114 Series
Figure 3-15 Groundwater Elevations MW115 Series
Figure 3-16 Groundwater Elevations MW116 Series
Figure 3-17 Groundwater Elevations MW117 Series
Figure 3-18 Groundwater Elevations MW118 Series
Figure 3-19 Groundwater Elevations MW119 Series
Figure 3-20 Groundwater Elevations SW3 Series
Figure 3-21 Three-Dimensional Groundwater Flow Map
5797wpdoc8galluprifiruiltextmasterriftil061297 viii QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
Figure 5-1
Figure 5-2
Figure 5-3
List of Figures (Contd) Groundwater VOC Concentrations vs Time - Downgradient from Former
Primary Disposal Area
Groundwater VOC Concentrations vs Time - Near Former Pervel Facility
Groundwater VOC Concentrations vs Time - Downgradient Portion of VOC
Plume
Figure 5-4 Evaluation of Biodegradation and Rainwater Dilution Rates in VOC Plume
5797wpdocraquogalluprifinaltextmasterrifhl061297 ix QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Plates
Plate 2-1 Baseline Survey Grid Air Monitoring Seismic Refraction Line Locations
Plate 2-2 Microwell Locations
Plate 2-3 Soil Vapor Probe and Soil Boring Locations
Plate 2-4 Monitoring Wells PiezometersStream Gauge Locations
Plate 2-5 Residential Well Locations
Plate 2-6 Surface WaterSediment and Wetland Soil Sampling Locations
Plate 2-7 Location of Test Pits Performed at Geophysical Anomalies
Plate 3-1 Study Area Topographic Features
Plate 3-2 Geologic Cross-Sections A-A amp C-C Plate 3-3 Geologic Cross-Section D-D
Plate 3-4 Geologic Cross-Section B-B Plate 3-5 Geologic Cross-Sections E-Eamp F-F
Plate 3-6 Bedrock Surface Contour Map
Plate 3-7 Bedrock Fracture Zones as Determined by Seismic and Magnetometer Surveys
Plate 3-8 Lower Overburden Piezometric Surface November 6 1995
Plate 3-9 Shallow Overburden Piezometric Surface November 6 1995
Plate 3-10 Saturated Overburden Thickness November 6 1995
Plate 3-11 Bedrock Piezometric Surface November 6 1995
Plate 3-12 Vertical Ground water Flow Through Plume Center Line
Plate 3-13 Deep vs Shallow Piezometric Head Differences
Plate 3-14 Wetland Delineation Map September 1994
Plate 4-1 Survey Grid amp Features Noted During Site Reconnaissance August-September
1994
Plate 4-2 Former Primary Disposal Area Soil Borings VOC Data and Cross-Sections
Plate 4-3 Former Primary Disposal Area Soil Borings PCB Data and Cross-Sections
Plate 4-4 VOC Detections Field GC and Laboratory Analyses in Microwells
Plate 4-5 Laboratory Results of Metals Analyses in Microwells
Plate 4-6 Groundwater VOC Data January April July and November 1995 Sampling
Events
Plate 4-7 Groundwater VOC Data February May August and November 1996 and
February 1997 Sampling Events
Plate 5-1 Groundwater Travel Times in Overburden Aquifer November 6 1995
5797wpdocsgi lluprifinaltextmasteirifnl061297 X QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
Table of Contents (continued)
List of Appendices
Appendix A Weston Geophysical Inc Report
Appendix B Microwell Logs
Appendix C Soil Boring and Rock Coring Logs and Well Construction Forms
Appendix D Groundwater Sampling Forms
Appendix E Test Pit Logs
Appendix F Single-Well Hydraulic Conductivity Test Procedures
Appendix G Grain Size Data
Appendix H Phase 1A Laboratory Reports
Appendix I April 1995 Laboratory Reports
Appendix J July 1995 Laboratory Reports
Appendix K Phase IBNovember 1995 Laboratory Reports
Appendix L February 1996 Laboratory Reports
Appendix M May 1996 Laboratory Reports
Appendix N August 1996 Laboratory Reports
Appendix O November 1996 Laboratory Reports
Appendix P February 1997 Laboratory Reports
Appendix Q Data Validation Reports
Appendix R pH TOC Moisture Results Soil Samples
Appendix S Environmental Metals Statistics
Appendix T Air Monitoring Results
Appendix U Model of Groundwater Near Mill Brook Appendix V Methodology for Piezometric Head Contouring and Groundwater Pathline
Generation
5797wpdocsgalluprifinlaquoltextmagterri fhl061297 XI QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
10 Introduction
11 Purpose of the Report This document presents the Remedial Investigation Report (RI) which was completed for the
Gallops Quarry Superfund Site (Site) pursuant to the requirements of US Environmental
Protection Agency (EPA) Administrative Order by Consent Docket Number 1-93-1080 (Order)
issued September 7 1993 The Gallups Quarry property is the site of a former sand and gravel
quarry and is located on Tarbox Road in the town of Plainfield Windham County Connecticut
(see Figure 1-1) According to the Town of Plainfield Tax Assessors office the property (Map
10 Block 30 Lot 32) is an irregularly shaped parcel comprised of approximately 29 acres
Investigation of the quarry was initiated in 1978 when unlicensed waste disposal operations were
discovered at the property Emergency clean-up operations were conducted by the Connecticut
Department of Environmental Protection (CTDEP) in April 1978 (Metcalf amp Eddy 1993)
Following the initial clean-up effort a study was conducted to characterize the nature and extent
of residual contamination at the Site (Fuss amp ONeill 1979) A series of surface and subsurface
sampling events conducted by the CTDEP the Connecticut Department of Health and the US
Environmental Protection Agency (EPA) between the years of 1978 and 1988 prompted EPA to
propose on June 21 1988 that the Site be listed on the National Priorities List (NPL) The Site
was finally listed on the NPL on October 4 1989 During 1992 and 1993 EPA conducted a
limited investigation through the Superfund Technical Assessment amp Response Team (START)
initiative in an effort to expedite the completion of the Remedial InvestigationFeasibility Study
(RIFS) The requirements of the Order as well as data included in the START report (Metcalf
amp Eddy 1993) provided the framework for this investigation
This Report is the sixteenth major deliverable under the Order The first major deliverable the
Remedial InvestigationFeasibility Study Work Plan - Phase 1A was finalized and submitted to
EPA on August 29 1995 QST Environmental (formerly Environmental Science amp Engineering
Inc (ESE)) finalized the Work Plan and has prepared all of the other deliverables The Phase 1A
field investigation was completed in January 1995 The second major deliverable the Phase 1A
Data Report dated March 24 1995 was submitted to EPA following completion of the Phase 1A
field investigation The findings of the Phase 1A investigation were described in the Initial Site
Characterization Report (ISCR) which was finalized and submitted to EPA on March 1 1996 A
Work Plan for the Phase IB field investigation was also finalized and submitted on October 11
1995
In addition to the actual Phase 1A field investigation the Phase 1A Work Plan also described the
Long Term Monitoring Program which was initiated upon completion of the Phase 1A field
5797wpdocraquogalluprifinaltextmlaquoiterrifhl061297 1-1 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
investigation The Long Term Monitoring Program includes the quarterly collection and analysis
of groundwatei and semi-annual collection and analysis of surface water and nearby residential
well samples
The Phase IB field investigation commenced on October 12 1995 Following the completion of
drilling activities the Phase IB groundwater sampling task and the fourth quarter 1995 Long
Term Monitoring sampling event were performed simultaneously in November 1995 Seven
Data Reports have been submitted to the EPA for the following Long-Term Monitoring Program
sampling events the second and third quarters of 1995 all four quarters of 1996 and the first
quarter of 1997 (ESE 1996a 1996b 1996c 1997a 1997b) The draft RI Report was submitted
to EPA on March 15 1996 (and revised and resubmitted October 22 1996) and included the
results of the fourth quarter of 1995 sampling event On March 29 1996 the following two
deliverables were submitted to EPA Development and Initial Screening of Alternatives Report
and Detailed Analysis Work Plan The draft Feasibility Study was submitted to EPA on January
27 1997 This RI Report describes the methods and findings of both the Phase 1A and IB field
studies and includes data collected during the April July and November 1995 February May
August and November 1996 and February 1997 Long-Term Monitoring sampling events
12 Report Organization The RI is presented in seven main sections following the Executive Summary The remainder of
Section 1 presents Site background information Section 2 presents the various field methods and
procedures used during the field investigations including descriptions of any changes or
deviations from the Work Plan Section 3 describes the physical characteristics of the Study
Area and Section 4 presents the findings of studies designed to determine the nature and extent of
contamination within the Study Area Section 5 is a discussion of the various fate and transport
mechanisms associated with the contaminants of concern Section 6 summarizes the conceptual
model of conditions within the Study Area Finally a list of references cited in this report is
presented in Section 7
Volume 1 of this Report presents the text and figures of the RI Volume 2 contains all Tables
referenced in the report Volume 3 contains all Plates referenced in the Report Volume 4 and
all subsequent volumes contain the Appendices referenced in the Report
5797wpdocggaIluprifinaltextmasterrifhl061297 1-2 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
13 Site Background 131 Area Description Demography and Land Use
For the purposes of this report the Site is considered to be the actual property owned by the
late Stanton Gallup from 1964 until his death in 1994 The Study Area includes the Site as
well as surrounding properties from which data were collected during the RI
The Site is located on the north side of Tarbox Road in the Town of Plainfield Windham County
Connecticut (see Figure 1-1) The Site is situated approximately 2000 feet west of interchange
87 on Interstate 395 and approximately one-mile southwest of Plainfield Center As shown on
Figure 1-2 the Site is irregularly shaped and is approximately 2200 feet long (north to south)
and 300 to 1100 feet wide (east to west) A number of previous references have described the
Site as ranging in size from 20 to 22 acres however the Town of Plainfield Tax Maps and areal
calculations performed by ESE indicate that the size of the Site is approximately 29 acres In
addition to the Site the Study Area includes additional areas located to the north and northwest of
the Site (as shown on Figure 1-1) and a number of discrete smaller areas located to the east and
south of the Site used for collecting upgradient surface watersediment samples
The Site is currently vacant and much of it is heavily vegetated Numerous overgrown mounds
and excavations are scattered across the Site and are presumed to be features remnant of the
former sand and gravel quarry operations Other than concrete foundations remnant of former
Site operations no structures presently exist on the property Surface features observed on the
Site during the Phase 1A visual reconnaissance survey are described in more detail in Section
411
As shown on Figure 1-2 the Site is bounded to the east by Route 12 (Norwich Road) single-family residences and a plumbing supply company An active railroad right-of-way (presently
operated by the Providence and Worcester Railroad) bounds the Site to the west Wooded areas
and wetlands associated with Mill Brook bound the Site to the north and Tarbox Road and several
single family residences bound the Site to the south
Surface water bodies located within or near the Study Area include Mill Brook Fry Brook and
Packers Pond As shown on Figure 1-3 Mill Brook flows from east to west along the northern
edge of the Study Area until its confluence with Fry Brook Mill Brook turns toward the south
at this confluence and continues flowing in a south-southwesterly direction (as Mill Brook) and
eventually drains into Packers Pond [Note Packers Pond is not shown on Figure 1-3 due to the
larger scale of this figure however the relative location of Packers Pond approximately 1 mile
west of the Site can be seen on Figure 1-1]
5797wpdocBgalluprifinaltextmasteiTifhl061297 1-3 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Based on the CTDEP Water Quality Classification Map of Thames Southeast Coast and
Pawcatuck River Basins Sheet 2 of 2 (1986) surface water located within the section of Mill
Brook between Route 12 and the confluence with Fry Brook (shown on Figure 1-3) is classified
as BA The BA classification indicates that the surface water body may not be meeting the
Class A water quality criteria for one or more designated uses which include potential drinking
water supply fish and wildlife habitat recreational use and agricultural and industrial supply
although the goal is to ultimately restore the water body to Class A standards Surface water
within Fry Brook and the lower section of Mill Brook (located down stream of the confluence of
the two brooks) is classified as Be The Be classification indicates that the water meets Class B
criteria and is suitable for cold water fisheries The designated uses for Class B surface water
include most of those described for Class A however Class B waters are NOT designated as a
potential drinking water supply Surface water located within Packers Pond (not shown on Figure
1-3) is designated as CBc The CBc designation indicates that Packers Pond is not meeting the
Class B water quality criteria for one or more designated uses or is a Class C water body which
is basically a downgraded version of Class B However the CTDEP goal for surface water
designated as CBc is to restore it to Class B conditions
As shown on Figure 1-3 groundwater located within the northern portion of the Study Area
between Route 12 and the MillFry Brook confluence is classified as GBGA which indicates that
the groundwater may not be suitable for direct human consumption without the need for treatment
due to waste discharges spills or leaks of chemicals or land use impacts The CTDEP goal for
groundwater classified as GBGA is to prevent further degradation by preventing any additional
discharges which would cause irreversible contamination Groundwater at all other locations
within the Study Area is classified as GA which is presumed suitable for direct human
consumption without need for treatment In addition one of the goals of the CTDEP for
groundwater classified as GBGA is to restore it to GA standards
It should be noted that the surface water classifications described above are based on existing
CTDEP maps which were published prior to the preparation of this report During the course of
this investigation the CTDEP proposed amendments which were intended to clarify the language
of the States Water Quality Standards and simplify the Departments system for considering
requested modifications Based on conversations with a representative of the CTDEP (Personal
Communication Bobowitz 1996) the single letter (eg Class A) and dual letter (and associated
goal) classification (eg BA) system will be maintained Areas presently designated by dual
classifications will only be modified once the desired goal for that water body or aquifer has been
attained According to the CTDEP the only significant change will be the eventual elimination of
the use of lower case suffixes (eg Be) which are currently used to indicate very specific
restrictions or uses for certain water bodies (ie B rather than Be)
5797wpdocsgalluprifinaltextmasterrifhl061297 1-4 QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
Within the Study Area directly west of the Site (across the railroad tracks) are open cropland
(presently a cornfield) wooded areas and a residential property (parcel 24 shown on Figure 1shy
2) The property boundaries and land owners for the Site and other nearby parcels are also
shown on Figure 1-2 Immediately north of the Site are approximately 85 acres of wooded
undeveloped land through which flows Mill Brook An overhead power line easement (not shown
on Figure 1-2) runs adjacent to the northernmost Site boundary On the north side of Mill Brook
is an industrial park which contains an Intermark Fabric Corporation facility (formerly the Pervel
Industries flock plant) and a Safety Kleen Corporation accumulation facility Northeast of Mill
Brook are woodlands and Saint Johns Cemetery Further north of the industrial park are several
vacant mill buildings which were occupied until the late 1980s by various manufacturers including
Pervel Industries and the InterRoyal Corporation The Plainfield sewage treatment plant which
discharges to Mill Brook and its major tributary (Fry Brook) is located approximately 1800 feet
northwest of the property
The Town of Plainfield with a land area of 427 square miles has a population of approximately
14200 Plainfields principal industries include varied manufacturing and distribution centers as
well as tourism based businesses In addition the rural areas of Plainfield are occupied by many
small dairy and produce farms
^ 132 Operational History
Information regarding the operational history of Gallups Quarry was obtained from published
reports for previous Site studies including Site Analysis Gallups Quarry Plainfield CT
(Bionetics Corporation 1990) and Final Data Summary Report START Initiative (Metcalf amp
Eddy 1993) as well as information from various sources collected during the preparation of the
Gallups Quarry Remedial InvestigationFeasibility Study Work Plan (ESE 1994) Little detailed information concerning the early operational history of the Site exists
A review of an aerial photograph of the Site taken in 1951 depicts the Site as an undeveloped
parcel although some quarry activities in the southern portion of the property appear to be
underway (ESE 1994) Records at the town of Plainfield Assessors office indicate that in 1951
the Site was owned by a Mr Johnson who was operating a sand and gravel quarry In 1964 the
Site was purchased by C Stanton Gallup (Metcalf amp Eddy 1993) Although detailed usage of
the Site from 1964 through 1977 is poorly documented records indicate that the Site was used as
a source of aggregate and was occupied by the Connecticut Department of Transportation
(CTDOT) which operated an asphalt batching plant (ESE 1994) The exact date of CTDOT
presence at the Site is unclear although it is believed to coincide with the construction of Route
52 (now known as Interstate 395) Evidence of the former asphalt batching plant operations are
5797wpdocsgalluprifinalteirtinalaquoterrifhl061297 1-5 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
still present at the Site Mounds of asphalt paving material and areas covered with hardened
liquid asphalt ere observed at a number of locations throughout the Site
As a result of complaints from neighboring residents the CTDEP and the Connecticut State
Police initiated an investigation of the Site in early January 1978 During a Site visit on January
13 1978 representatives of the CTDEP reportedly observed partially buried drums containing
suspected hazardous materials and ordered that all Site operations be stopped The CTDEP
investigation concluded that the Site was used from the summer of 1977 until December 1977 for
unlicensed waste disposal
As described in the Order evidence collected by CTDEP indicates that Chemical Waste Removal
Inc (CWR) of Bridgeport Connecticut transported drummed and bulk liquid waste material to the
Site and was the sole known transporter of waste to the Site These wastes reportedly included a
variety of industrial wastes which were transported to and disposed of at the Site It was reported
that Mr Gallup jointly operated the quarry with Mr Dick Trayner of Dick Trayner and Sons
Trucking Company at the time of the illegal waste disposal activities
According to CTDEP and State Police records the drums and liquid wastes were reportedly
disposed of at three distinct locations on the Site These areas were subsequently labeled the
Primary Disposal Area the Secondary Disposal Area and the Seepage Bed The Primary and
Secondary Disposal Areas were reportedly located in the northern portion of the Site while the
Seepage Bed was reportedly located in the central portion of the Site The reported locations of
these former disposal areas are shown on Figure 1-3
According to a report issued by Fuss amp ONeill (FampO 1979) the Primary Disposal Area
consisted of an area approximately 04 acres in size The Secondary Disposal Area was described
by the FampO report as a linear trench which encompassed an approximate area of 007 acres
located adjacent to the railroad tracks and just west of the Primary Disposal Area The Seepage
Bed was located in the central portion of the Site and according to the FampO report was
approximately 40 feet by 50 feet in size and consisted of an excavation into which an inverted
truck body filled and covered with crushed stone was placed A metal pipe which extended
from the dump body to the ground surface was reportedly used for direct discharge of liquid
wastes According to the FampO report the liquid wastes reportedly disposed of in the Seepage
Bed consisted of low pH liquids which were believed to be by-products associated with metal
finishing operations
Initial cleanup efforts were performed by Chem-Trol Inc during the summer of 1978 under the
direction of the CTDEP and the Connecticut State Police A Connecticut State Police Possessed
5797wpdocsglaquolluprifinaltextmasterrifhl061297 1-6 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
Property Report (PPR) lists the following materials as removed from the Site 1584 drums (some
of which were crushed andor decomposed) 5000 gallons of free liquid and 2277 cubic yards
of contaminated earth The PPR also lists 127715 tons of moderately contaminated soil which
was removed from the Site Additional remedial measures included the neutralization of residual
contamination at the Seepage Bed by placing 20 tons of lime at that location
Although no information concerning the actual number of drums or quantity of waste transported
to the Site by CWR is available it was believed that all of the drums had been recovered upon
completion of the cleanup operations Mine detectors were utilized to search for additional buried
drums however no indications of additional buried drums were discovered
Since the 1978 cleanup operations the Site has been vacant Public vehicular access to the Site
has been limited by the placement of boulders and mounded soil at access locations around the
Site During this time evidence of off-road vehicle tire tracks and small quantities of debris
(beverage cans bottles spent shotgun shell casings and empty gasoline cans) indicate that the
Site has been utilized by trespassers for recreational purposes However it appears that Site
usage has decreased since August 1994 when fencing and additional boulders were placed at
potential access locations and the perimeter of the property was posted with warning signs
133 Summary of Previous Investigations
Following the CTDEP removal activities a number of environmental investigations and sampling
events were conducted at the Gallups Quarry Site This section summarizes environmental
studies conducted at the Site prior to the RIFS as compiled performed and reported by Metcalf
amp Eddy (1993) as part of the EPAs Region I START Initiative or as reported by the original
investigators)
1331 Evaluation of a Chemical Waste Disposal Area Tarbox Road Site Plainfield Connecticut Fuss amp ONeill 1979
Between June 6 and October 30 1978 Fuss amp ONeill Inc performed a hydrogeological
investigation within the Study Area in conjunction with the cleanup and remedial operations
directed by the CTDEP and Connecticut State Police The findings of this investigation were
presented in a report issued to the CTDEP dated January 29 1979 The tasks completed during
this investigation included the following
bull The installation of 22 test borings which were completed as groundwater
monitoring wells (SW series) including three shallow-bedrock wells near the
Former Seepage Bed (SW-10 SW-11 SW-12) The locations of these wells are
shown in Figure 1-4
5797wpdocsgalluprifinaltextmlaquo8terrifhl061297 1-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
bull Excavation of 19 test pits (using a backhoe) 13 of which were completed as
shallow groundwater monitoring wells
bull The establishment of 12 surface water gauging stations along Mill Brook and Fry
Brook
bull The collection of surface water and groundwater water for laboratory analysis
FampO collected groundwater samples from the monitoring wells in July October and December
1978 Several nearby domestic wells were also sampled in July and October 1978 Groundwater
samples were analyzed for metals volatile organic compounds (VOC) and the following general
chemical parameters chemical oxygen demand (COD) total dissolved solids (TDS) total
Kjeldahl nitrogen (TKN) chloride total organic carbon (TOC) total carbon total cyanide
specific conductance and pH
FampO also collected surface water samples from seven of the stream gauging stations in
September October and November 1978 In general the surface water samples were analyzed
for the same chemical parameters described above
The chemical testing results indicated groundwater in the vicinity and downgradient of the Former
Disposal Areas had been impacted by several organic and inorganic constituents VOC detected
included ethanol methanol isopropanol ethyl acetate acetone toluene benzene trichloroethene
(TCE) 111- trichloroethane (TCA) tetrachloroethene (PCE) methyl isobutyl ketone (MIBK)
methyl ethyl ketone (MEK) and methylene chloride Various metals including aluminum
chromium copper magnesium nickel zinc iron and silver were reported at widely variable
concentrations in some groundwater samples According to the START Report the domestic
wells did not appear to be significantly impacted
FampO concluded that a well-defined groundwater contaminant plume extended from the former
disposal areas towards Mill Brook northwest of the Site and that the flow direction of the plume
was controlled by the local water table gradient The plume was characterized by the presence of
organic compounds which included acetate benzene ethanol isopropanol MEK MIBK
toluene TCA and xylene The plume also contained widely variable concentrations of various
metals including copper nickel boron aluminum magnesium manganese iron silver
cadmium and lead
The START Report indicated that since little or no information is available regarding FampOs field
methods (eg field notes chain-of-custody collection of field QC samples) or analytical
5797wpdoc8galluprifinaltextmastemfnl061297 1-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
methods (eg detection limits turbidity filtering sample preservation analysis of lab QC
samples) comparison of the test results to current regulatory criteria (eg Maximum Contaminant
Levels [MCL]) was not appropriate for any definitive purpose
1332 CTDEP Periodic Monitoring 1979 to 1983
As described in the START Report the CTDEP performed periodic monitoring of groundwater
(including domestic wells) surface water and sediment in the Study Area from 1979 until 1983
The periodic monitoring was not systematic in terms of the wells or locations that were sampled
or the parameters tested for The results of the CTDEP monitoring are in the form of laboratory
results compiled and presented in the START report A summary table of results for the CTDEP
groundwater monitoring activities as presented in the START report is included in this report as
Table 1-1
The dates of groundwater sample collection and analysis for the CTDEPs monitoring program
are as follows
bull October 1979
bull January 1980
bull November 1980
bull April 1981
bull October 1981
bull April 1982
Sample analytical parameters varied from event to event but typically included pH COD
specific conductivity hydrocarbons chlorides and selected metals (cadmium chromium copper iron nickel and zinc)
The CTDEP also collected surface water and sediment samples on the following dates
bull January 1980 (surface water)
bull October 1981 (surface water and sediment)
bull April 1982 (surface water)
bull December 1983 (surface water)
It was noted in the START Report that no information was available regarding the CTDEP sampling methods or analytical procedures and that this limited the usefulness of the data except
for comparative purposes Nonetheless the START Report concluded that the available analytical
data collected by CTDEP during the period from 1972 to 1982 indicated that the Site and areas to
5797wpdoc8falluprifinaltextmasterrifnl061297 1-9 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
the north-northwest were impacted by the past disposal of VOC metals and acid wastes This
conclusion wa5 based on the fact that up until the last recorded groundwater sampling event
performed by CTDEP (1982) four monitoring wells (SW7D SW13 SW17S and SW17D)
exhibited detectable concentrations of contaminants characteristic of the types of wastes which
were reportedly disposed of on the Site The contaminants detected in these wells included
various common industrial organic solvents (both chlorinated hydrocarbons and ketones) as well
as several petroleum aromatic hydrocarbons Chlorinated hydrocarbon concentrations for these
wells ranged from 10000 to 80000 parts per billion (ppb) for 111-Trichloroethane (TCA) 30
to 1000 ppb for Tetrachloroethane (PCE) and 1000 to 14000 ppb for Trichloroethene (TCE)
Ketones detected included Acetone (5000 to 22000 ppb) methyl ethyl ketone (MEK) ranged
from 12000 to 150000 ppb and methyl iso butyl ketone (MIBK) ranged from 60 to 7000 ppb)
The main aromatics detected included toluene (up to 17000 ppb) and xylene (up to 3000 ppb)
1333 CTDEP BioDiversity Study 1985
The CTDEP conducted a field survey on November 4 1985 to evaluate potential impacts from
migration of groundwater from the Site to the Mill Brook wetland The study was conducted in
an area where leachate was observed to be breaking out from the wetlands into Mill Brook
The precise location is unclear however the START Report indicates that the impact zone was
subjectively estimated to be approximately 200 feet west of the railroad bridge The leachate
was described as an area showing evidence of organic enrichment and iron hydroxide precipitation
which extended a distance of approximately 100 feet downstream
The study reported a background species Diversity Index value of 257 compared to a value of
236 for the area of study The minor difference in diversity represented by this measure was
primarily considered to be a result of low flow conditions as much higher diversity indices
indicative of excellent water quality were observed during a previous bioassessment in that
area
As part of the CTDEP study four surface water samples were collected (one control and three
downstream) from Mill Brook on 8 November 1985 for acute aquatic toxicity bioassays using
water fleas (Daphniapulex) The results of this testing are summarized in a CTDEP
interdepartmental memorandum (dated November 18 1985) that is included with the results of the
biodiversity study The assay employed three replicates per sample and 10 individual organisms
per replicate The endpoint of the assay was percent survival after 48 hour exposure to the water
All samples yielded average survival rates of greater than 83 Based on the results of the tests
the CTDEP concluded that no acute toxicity was demonstrated
5797wpdocsgalluprifinaltextmasterrifnl061297 1-10 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The BioDiversity study report indicated that well MW17S was sampled and that a strong
solventacid odor was noted Further information on sampling and analyses of this well by
CTDEP in 1985 was not included in the report
1334 Hazard Ranking System (HRS) Study - NUSFIT 1986 to 19874
On September 15 1987 the Superfund Division of NUS Corporation completed the Final HRS
Documentation Package for Gallups Quarry The package contains information on the cleanup
and subsequent environmental evaluations including State Police documents and logs regarding
the investigation into the unlicensed disposal activities CTDEP and State Police documents
concerning cleanup activities affidavits taken from individuals involved in the disposal activities
and miscellaneous correspondence related to the criminal investigation and cleanup activities
The HRS package includes the EPAs Preliminary Assessment for Gallups Quarry which was
completed by NUS in July 1986 During the Preliminary Assessment NUS sampled two of the
existing monitoring wells (SW17D and SW18) and three surface watersediment locations The
surface and groundwater samples were screened in-house for benzene TCE toluene PCE
chlorobenzene ethyl benzene and xylenes None of these compounds were detected in MW18 or
the surface water samples All of the compounds (except chlorobenzene) were detected in
MW17S with toluene and xylenes measured at the highest concentrations With the exception of
pH temperature and conductivity no data were available regarding the sediment samples
Based on a file review and limited sampling the Preliminary Assessment concluded as in
previous studies that VOC contamination existed at the Site and that contaminated groundwater
was migrating in a west to northwest direction from the Site NUS recommended that a Site
Investigation be conducted to further evaluate the on-site conditions and potential off-site impacts
1335 Residential Well Sampling 1989
In 1989 Roy F Weston Inc under contract to EPA collected samples from 10 private wells in
the vicinity of the Site The samples were analyzed for VOC semi-volatile compounds (SVOC)
and metals Very low levels of some VOC (chloromethane TCA and carbon tetrachloride)
SVOC (phthalates) and metals (barium and copper) were detected in several wells but at
concentrations well below their respective EPA MCL In a memo dated May 25 1989 (included
as Appendix G of the START Report) EPA concluded that the levels detected in this investigation
did not represent a public health threat
5797wpdocsgalluprifinaltextmraquosterrifhl061297 1-11 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
1336 Site Analysis - Bionetics Corporation 1990
In November 1990 the Bionetics Corporation under contract to EPA completed an analysis of
historical aerial photographs taken of the Site in 1951 1970 1974 1975 1981 and 1988
Based on analyses of these aerial photographs the report suggested that disposal-related activities may have started at the quarry as early as 1970 However this conclusion was based on the
presence of features such as excavated areas mounded materials possible containers and the presence of access roads all of which are also indicative of typical quarrying operations
1337 Health Assessment - US Department of Health and Human Services (DHHS) 1991
The US Department of Health and Human Services completed a Health Assessment for Gallups Quarry on January 30 1991 to assess potential human health effects from exposure to
contamination at the Site The assessment was based on previous chemical testing data available
for the Site (ie data collected by Fuss amp ONeill Inc in 1978 and by CTDEP in 1979 through
1983)
The report concluded that if present at high enough concentrations VOC and heavy metals
detected at the Site could have potential public health implications The report recommended that
a program of groundwater monitoring be instituted along with on-site soil and surface water sampling and that additional health data for the area be evaluated as it becomes available
1338 Residential Well and Surficial Soil Sampling - Roy F Weston 1993
In 1993 Roy F Weston Inc under contract to EPA sampled 8 residential supply wells in the
vicinity of the Site The samples were analyzed for VOC SVOC and metals In addition
Weston collected seven surficial soil samples (within 3 inches of the ground surface) from areas
of apparent staining in the vicinity of the Former Primary and Secondary Disposal Areas Two
samples were collected in January 1993 and the other five were collected in February 1993 The
soil samples collected in January were submitted to the laboratory for analysis for pH and
cyanide and for metals screening using X-ray fluorescence techniques (XRF) The five samples
collected in February were analyzed for cyanide
The results of the XRF screening analyses indicated that the two samples collected in January
contained levels of copper ranging from 160 to 400 ppm No other metals were detected above
normal background levels Cyanide levels for all seven soil samples were reported in the range
of 87 to 345 ppm
5797wpdocsgalluprifinaltextmasterrifiil061297 1-12 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
The well water analytical results indicated that 111-TCA was detected in three of the residential
wells at levels of 05 to 12 ppb well below EPA MCL for 111-TCA of 200 ppb Copper and
iron were detected at levels below the EPA MCL in several of the samples analyzed SVOC were
not detected
1339 Groundwater Monitoring and Well Survey Metcalf amp Eddy 1993
In November 1992 Metcalf amp Eddy performed a well condition survey of the remaining existing
monitoring wells at the Site as part of a groundwater monitoring well investigation conducted for
the EPA Thirteen of the original twenty-two monitoring wells installed by Fuss amp ONeill Inc
were located fewer than half of which were determined to be in a condition capable of producing
viable samples In February 1993 Metcalf amp Eddy collected samples from ten of the wells
installed by Fuss amp ONeill Inc and from a USGS well installed in 1992 The samples were
analyzed for VOC SVOC metals and cyanide
Groundwater analytical results were consistent with earlier studies but confirmed that VOC levels
were significantly decreasing with time Low levels of VOC were detected at monitoring wells
SW3S and SW3D located downgradient of the Former Primary Disposal Area and at SW13
located downgradient of the Former Secondary Disposal Area The highest levels of VOC were
detected in wells SW17S (15000 ppb of xylene 1700 ppb of toluene 460 ppb of TCA 34 ppb
of TCE 22 ppb of PCE) and SW17D (1500 ppb of 12-DCE 720 ppb of TCA 16 ppb of TCE
and 27 ppb of PCE) A summary of the results of the 1993 Metcalf amp Eddy monitoring are
presented in Table 1-2 In general the concentrations detected in these wells for this sampling
event were substantially lower than concentrations recorded during the previous groundwater
sampling in 1982
13310 Geohydrology of the Gallups Quarry Area Plainfield Connecticut USGS 1993
In 1993 the United States Geological Survey (USGS) issued a draft report on Geohydrology of
the Gallups Quarry Area Plainfield Connecticut (finalized in 1995) The work was performed as
part of the EPAs START program and was designed to assist in the RIFS scoping process
The USGS study interpreted the subsurface geologic conditions at the Site to provide guidance for
subsequent investigations Field investigations for the study included ground penetrating radar
(GPR) and electromagnetic (EM-34) geophysical surveys the drilling of three test borings the
installation of a monitoring well in one of the borings (shown on Figure 1-4) and the
measurement of flow rate and specific conductance in Mill Brook
5797wpdocraquosalluprifiiultextmasterrifiil061297 1-13 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The USGS investigation provided data on overburden soil units the depth to bedrock and
bedrock structure Existing subsurface information derived from previous test boring logs and the
data collected from the three test borings drilled by the USGS were used in conjunction with GPR
data and the results of the EM-34 terrain conductivity survey to develop geological cross-sections
across the Site In addition the GPR survey indicated the possible presence of a west-northwest
trending fault zone beneath the property located south of the Former Seepage Bed The location
of this suspected fault zone as estimated by the USGS is consistent with the approximate location
inferred by previous regional geological studies (Dixon 1965 and Boynton and Smith 1965)
An electromagnetic survey performed downgradient (northwest) of the Former Secondary and
Primary Disposal Areas indicated a northwesterly-trending pattern of increased terrain
conductivity levels as compared with levels at other areas of the Site The USGS interpreted the
increased levels as possibly indicative of either the presence of a groundwater plume containing
residual metal contamination or a natural change in subsurface strata Surface water
measurements collected in Mill Brook indicated that specific conductance increased slightly
downstream of the railroad bridge however the observed differences were so small that the
USGS did not consider them to be indicative of changes in water quality caused by the presence
of dissolved contaminants
13311 Habitat Characterization for Gallups Quarry Superfund Site US Fish and Wildlife Service March 1995
In June of 1993 the US Fish and Wildlife Service conducted a field survey for the purposes of
characterizing the habitat of the Site and surrounding wetland and stream ecosystems The study
was qualitative in nature conducted on foot by trained biologists with the objective of correlating
observations on habitat (primarily vegetation) with known reference material such as topography
maps and aerial photographs The study also included direct and indirect (eg animal tracks)
observations to assess the presence (or absence) of wildlife
The report provides a description of methods and general Site characteristics as well as a more
detailed discussion of wildlife habitat for both the Site and the Mill Brook wetland ecosystem
The study is partial in that it accents what types of animals would be anticipated to be present for
each habitat type even though most of these animals were not directly observed
The report concludes with a description of 29 different types of cover that can be cross-
referenced to areas delineated on a Site map (not to scale) Several Tables are also presented
which inventory birds mammals reptiles amphibians trees shrubs and herbaceous vegetation
that were either observed or would be expected to inhabit the Site
5797wpdocsgalluprifinaItextmasterriftil061297 1-14 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
13312 Adjacent Properties Incident Reports and File Review 1995
To supplement data obtained during the Phase 1A field program a CTDEP file search was
performed to obtain information pertinent to groundwater contamination for industrial properties
neighboring the Site The preliminary findings of this review were submitted in a letter from
ESE to EPA on March 28 1995
A number of incident reports were on file regarding two nearby companies Pervel Industries
Inc and InterRoyal Corporation which have the potential to impact conditions within the Study
Area Figure 1-5 shows the locations of these facilities relative to the Site The significant
findings of the file searches are presented below
Pervel Industries
Pervel Industries Inc manufactured plastic film and laminated textile products (eg flocked
velvet) Pervel reportedly occupied two separate facilities north of the Site The main facility
located approximately 2500 feet north of the Site is believed to have been occupied by Pervel
from the 1940s or 1950s to at least the late 1980s This facility abutted the southern side of the
InterRoyal facility described below A second Pervel facility known as the flock plant (presently
operated by Intermark Fabric Corporation) was located approximately 1000 feet north of the
Site just north of Mill Brook The dates of Pervels occupation at the flock plant cannot be
clearly ascertained from the information available in the files however the review of historic
aerial photographs indicate that the facility has existed since the early 1970s
In 1988 at the request of EPA and CTDEP the NUS Corporation performed a Preliminary
Assessment (PA) at the main facility In an effort to determine eligibility for the National
Priorities List (NPL) NUS reviewed the activities associated with the 1984 closure of a sludge
and waste water lagoon located at the facility Based on their review of the available data NUS
recommended that a Screening Site Inspection (SSI) be performed
The NUS PA report also described a 1985 spill of 600 gallons of 111-TCA and a 1987 spill of
300 gallons of toluene at the northernmost facility According to the PA report contaminated soil
and sediment associated with the 1985 spill was excavated and stored in an impoundment at the
flock plant located just north of the Gallups Site The report indicates the presence of
contaminants in the area where the contaminated soil and sediment were stored suggesting that
the impoundment leaked andor there are other (undocumented) environmental concerns at the
flock plant
5797wpdocraquogalluprifinaltextmlaquosterrifhl061297 1-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The results of recent (late 1980s through the early 1990s) quarterly groundwater monitoring
efforts conducted at the former Pervel flock plant (HRP 1993) indicate the presence of a number
of VOC including 111-TCA TCE PCE and 12-DCE well above their respective MCL The
results of these sampling events as summarized in Table 1-3 (from HRP 1993) indicate that
there has been a general decrease in the concentrations of contaminants seen in these wells over
time The highest recorded concentrations for these constituents are as follows 111-TCA (518
ppb) PCE (466 ppb) TCE (63 ppb) and 12-DCE (906 ppb) According to the HRP report
groundwater flow in the vicinity of the former Pervel flock plant is generally from east to west
(towards the northern portion of the Study Area) However these interpretations were based on a
limited number of data points confined to the Pervel flock plant property
InterRoyal Corporation
The InterRoyal Corporation is located adjacent to and just north of the main Pervel facility
described above The CTDEP files include a memorandum from the NUS Corporation to EPA
dated August 18 1989 which references a 1984 Preliminary Assessment performed by CTDEP
which recommended that a low priority Site Inspection be performed The NUS memo presents a
chronology of Site activities up to 1989 which includes CTDEPs 1987 finding that the company
was in violation of several State Hazardous Waste Management regulations and CTDEPs
subsequent revocation of InterRoyals NPDES permit Based on a CTDEP 1988 Site inspection
NUS recommended to EPA that a high priority Screening Site Inspection be conducted
In 1988 InterRoyal contracted an environmental consultant to prepare an environmental
assessment (EA) for the proposed sale of the property The EA report (ERT 1988) concluded
that substantive on-site contamination of groundwater surface water and soils existed The
principal contaminants were identified as VOC (including TCE trans-l2-DCE PCE vinyl
chloride toluene and xylenes) and priority pollutant metals Groundwater flow direction was
described in the EA report as principally towards the south and southwest
5797wpdoc8galluprifinaltextmasterrifhl061297 1-16 QZT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
20 Field Investigations
This Section describes the field methods and procedures used to accomplish the various field
investigation tasks performed during Phase 1A and Phase IB Also included are descriptions of
any deviations from the approved Work Plan As noted in the appropriate subsections any
deviations from the Work Plan were approved by EPA (or EPAs oversight contractor) prior to
implementation Discussions of the findings results and significance of these investigations are
presented in Sections 3 and 4 of this Report
21 Site Survey 211 Initial Site Survey At the start of the Phase 1A field investigation an initial Site survey was performed to confirm
and update the location and elevation of features included in the base map provided by EPA (EPA
drawing number 707600 dated October 14 1993) The initial Site survey also served as Site
control by establishing a 250-foot grid across the entire Site which was identified by the
installation of labelled stakes at the intersection of each 250-foot grid line Horizontal control for
the 250-foot grid (and all subsequently surveyed features) coincides with the Connecticut State
Plane Coordinate System North American Datum of 1927 Vertical control coincides with the
National Geodetic Vertical Datum (NGVD) of 1929 and was established using nearby USGS benchmarks The 250-foot grid (shown on Plate 2-1) provided known reference locations from
which field personnel could measure the locations of Site features
In addition to the 250-foot control grid the initial survey also established a series of parallel lines
(trend lines) across the Site for use during subsequent visual reconnaissance and geophysical
surveys The trend lines (also shown on Plate 2-1) are roughly parallel to the Providence amp Worcester railroad which abuts the western edge of the property The first trend line (Line A)
was located approximately 50 feet east of the railroad right-of-way with subsequent lines (Line
B through Line HH) spaced at 25-foot intervals Each of the trend lines were staked at 250shy
foot intervals using labelled stakes
212 As-Installed Survey
Following the initial Site survey additional surveying events were performed as needed
throughout the duration of the Phase 1A and Phase IB field investigation programs to locate
various sampling locations and other pertinent investigation features These subsequent surveys
were initiated shortly after the completion of each investigation task Besides the various
surveyors control features such as temporary benchmarks and turning points the features
surveyed included wetland delineation flags surface watersediment and wetland soil sampling
5797wpdocsglaquolluprifinlaquoltextrnasterrifhl061297 2-1 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
locations microwells soil vapor points soil borings monitoring wells (existing and newly
installed) stream gauges piezometers and seismic survey lines
All pertinent investigation-related features within approximately 1500 feet of the Site were
included in the survey Several surface watersediment sampling locations beyond 1500 feet from
the Site were not surveyed and their locations are estimated based on their proximity to mapped
physical features such as bridges or roads
The surveying services for this investigation were performed by KWP Associates Inc of Pomfret
Center Connecticut a licensed and registered surveyor in the State of Connecticut The survey
was completed as a third-order plane survey as defined by the standards and specifications in
Exhibit 14-1 of the Compendium of Superfund Field Operations Methods December 1987
(USEPA 1987)
22 Site Reconnaissance 221 Visual Observations of the Ground Surface
A visual reconnaissance of the Site was conducted during an approximate three week period
beginning on August 23 1994 and ending on September 13 1994 During the visual Site
reconnaissance the entire length of each trending line (shown on Plate 2-1) was walked to
identify and map any features which may have been indicative of unknown disposal areas Any
features such as areas of stained soil partially buried man-made objects remnants of buildings
abandoned equipment containers (eg drums tanks) pits depressions mounds and any other
apparent unnatural materials were photographed and noted on field maps and in a field notebook
Also potential disposal features identified during review of historic aerial photographs (Bionetics
Corporation 1990) were located and investigated The locations of features were flagged and
approximated using the survey stakes installed during the initial Site survey The results of the
field reconnaissance were also used to determine additional soil gas sampling locations (described
in Section 25) during subsequent Phase 1A investigations
222 Air Quality Survey
A baseline air quality survey was conducted prior to the start of Phase 1A intrusive field
investigations The survey was performed using a photoionization detector (PID) equipped with
an 117eV lamp to measure total VOC vapors and a direct reading aerosol monitor (RAM-1) to
measure respirable particulates Baseline air quality readings were recorded at eight stations
(AM-1 through AM-8) located across the Site The monitoring stations included areas along the
Site perimeter as well as interior locations at the three known former disposal areas The
locations of the eight baseline air monitoring stations are shown on Plate 2-2
5797wpdocsgalluprifinaltextmlaquo8temfnl061297 2-2 QZT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
In addition to the baseline air quality survey air monitoring was performed on a weekly basis at the eight locations during the entire Phase 1A field investigation Wind direction wind speed
temperature and barometric pressure were also continuously monitored at an on-site
meteorological station
During the Phase IB investigation quantitive air monitoring was performed for site specific
compounds The Phase IB air sampling was performed in the vicinity of the Former Primary
Disposal Area on October 24 1995 This location was selected based on the findings of the
Phase 1A field program Four samples were collected along the perimeter of the Former Primary
Disposal Area at the northern southern eastern and western edges of the perimeter One
background sample was collected at a location approximately 300 feet south of and upwind from the Former Primary Disposal Area The sample locations are shown in Plate 2-2 The samples
were analyzed for the following volatile organic compounds (VOC) toluene ethyl benzene xylenes (total) and tetrachloroethane (PCE) and polychlorinated biphenyls (PCBs)
VOC samples were collected on stainless steel Tenax tubes which were connected to Dupont
Alpha 1 sampling pumps Samples for PCBs were collected on 037z glass fiber filters using
Dupont Alpha 1 and BIOS AirPro 6000D sampling pumps The sampling media was attached to
the sampling pumps using silicone tubing The pumps were secured to wood stakes and
positioned approximately 5 feet above the ground surface
The pumps used to collect the VOC samples were set to pump at a flow rate of between 0014 to
0016 liters per minute and allowed to pump approximately eight hours The pumps used to collect the PCB samples were set to pump at a flow rate of between 27 and 33 liters per minute
and were allowed to pump approximately eight hours All of the sampling pumps were calibrated prior to and after the sampling event using a primary gas flow mini-Buck Model M-5 Calibrator
Ambient meteorological conditions including temperature relative humidity barometric pressure
and wind speed and direction were monitored during the sampling event using ESEs on-site Qualimetrics meteorological monitoring instrument
A VOC and a PCB field blank were collected at background location AS 105 The VOC Tenax
tube and the PCB glass fiber filter were appropriately labeled opened and then immediately
resealed The field blanks were stored and shipped with the samples
At the completion of the sampling event the VOC Tenax sample tubes (including the field blank)
were sealed placed in clean plastic bags and refrigerated at 4degC until they were shipped The
samples were then shipped to the laboratory in coolers The PCB sample filters were sealed
5797wpdocsgalluprifinaltextmasterrifhl061297 2-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
wrapped in bubbie wrap and packed along with the PCB field blank in a cardboard box for
shipment to the laboratory An unopened VOC Tenax tube and PCB glass fiber filter were
submitted with tae samples as a trip blank The VOC Tenax sample field blank and trip blank
tubes were packed in a cooler with ice and sent to ESEs Denver Colorado Laboratory where
they were analyzed by EPA Method TO1 The PCB glass fiber sample field blank and trip
blank filters were sent to ESEs Denver Colorado Laboratory where they were analyzed by
SW846 EPA Method 8080 The results of the air quality survey are discussed in Section 44
223 Exclusion Zone Identification
Prior to the start of Phase 1A field activities preliminary exclusion zones were identified to limit
the risk of workers exposure to potentially hazardous conditions Based on existing data and
observations made during the Site visual reconnaissance the three known former disposal areas
and the area immediately surrounding a former CTDOT asphalt plant structure were staked and
flagged with caution tape A contaminant reduction zone (CRZ) was established adjacent to the
exclusion zone in the prevailing upwind direction during investigations at each location The
CRZ was established for decontamination operations of Site personnel and equipment
224 Project Support Measures
All field investigations were managed from a field office located within an approximate 10000
square foot support center which was situated at the southern end of the Site along Tarbox Road
The support center consisted of an approximate 100 foot by 100 foot area surrounded by a 6 foot-
high chain link fence The support center housed an office trailer an impermeable bermed
decontamination pad lined with 60 mil thick textured HDPE potable water storage tanks storage
units (drums dumpsters and tanks) for investigation derived wastes the weather station and
portable sanitary facilities The office trailer was connected to electric utilities and telephone
service to facilitate normal business and emergency operations A storage trailer for supplies and
equipment was located adjacent to the support center
The field office was used to support field activities by providing the following services
bull personnel sign-in and sign-out sheets
bull daily field activity log book
bull Health amp Safety log book
bull storage of Personal Protective Equipment (PPE)
bull communications center
bull posting of project plans
bull management of project field files
bull briefingmeeting room to coordinate field activities
5797wpdocsgalluprifinaltextmasterrifW061297 2-4 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull meeting place for emergency evacuations and
bull lunch area
The support center also provided an access control point for the Site as it is the only practical
location where four wheeled vehicles could enter or exit the Site Other non-vehicular access
points were blocked with boulders or mounded soils Other access to the Site is limited due to
the presence of heavy vegetation steep slopes and wetlands In addition warning signs
prohibiting trespassing were posted every 100 feet along the Site perimeter prior to the start of
Phase 1A field activities
225 Identification of Sensitive Human Receptors
A survey to identify potential human receptors in the vicinity of the Site was performed This
survey was used to identify any private water supply wells schools nursing homes and day care
facilities located within a one mile radius of the Site The survey was performed by reviewing
available records and documents from the following sources
bull Town of Plainfield Municipal Offices
bull Northeast District Health Department
bull Connecticut Department of Environmental Protection
bull Connecticut Natural Resource Center and
bull Connecticut Department of Health and Addiction Services
In addition to the file reviews interviews were conducted with neighbors and knowledgeable local
people Finally a windshield survey was conducted for the area located within a one mile radius
of the Site
23 Geophysical Surveys During the Phase 1A investigation comprehensive geophysical surveys of the Site were conducted
by Weston Geophysical Corporation of Northborough Massachusetts using electromagnetic
terrain conductivity (EM) magnetometer (MAG) and seismic refraction survey techniques The
purpose of the EM and MAG surveys was to obtain Site-wide screening data to identify the
locations if any of potential subsurface disposal features or objects such as pits trenches drums
or tanks The initial EM and MAG surveys were conducted along each of the trend lines
established during the initial Site survey as shown on Plate 2-1
The purpose of the seismic refraction survey was to determine the location and orientation of the
inferred bedrock fault (if present) in the central portion of the Site Although bedrock
characterization was not one of the intended purposes of the MAG survey subsequent review of
5797wpdocsgalluprifinaltextmasterriftil061297 2-5 QSTT Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
the acquired MAG data provided some information regarding the nature of the shallow bedrock
surface in the central portion of the Site
The presence of heavy vegetation over much of the intended survey area required approximately
two weeks of brush cutting and clearing in order to gain access to the trending lines and to ensure
complete coverage of the Site Once the proposed survey lines were accessible the initial MAG
and EM surveys were conducted along each trending line with data collected at five-foot intervals
The Work Plan stated that the five-foot intervals would be determined by laying a fiberglass
measuring tape along each trend line between survey stakes However the presence of heavy
vegetation prohibited the efficient use of this technique Since the exact locations of any
unexplained anomalies would be later determined during subsequent EM and MAG surveys (and
confirmed during test pit explorations) it was determined that the five-foot intervals could be
efficiently and accurately estimated by an experienced equipment operator by counting paces
between intervals and making adjustments as necessary at each survey stake (which were located
every 250 feet along each line)
As stated in the Work Plan ground penetrating radar (GPR) was to be used if necessary to
further characterize any unexplained anomalies identified during the initial EM and MAG surveys
The presence of abundant vegetation and rough ground surface conditions in the areas of interest
precluded the reasonable use of GPR As approved by EPA the precise locations of unexplained
anomalies identified during the initial EM and MAG surveys were determined during additional
EM and MAG surveys using a finer (5 foot by 5 foot) survey grid superimposed over the general
vicinity of each anomaly
The seismic refraction survey was conducted along six roughly parallel lines which were placed
normal to the anticipated strike of the inferred bedrock fault The locations of the six seismic
lines are shown in Plate 2-3 Each seismic line (Line 1 through 6) is comprised of two 250-foot
long lines which overlap by 125 feet This resulted in a total of 375 feet of continuous coverage
along each line
A complete report provided by Weston Geophysical Corporation describing the theoretical basis
for these surveys is presented as Appendix A Generalized discussions describing the field
methods and equipment used during each geophysical survey are presented below
5797wpdoclaquogalluprifinaltextmastemfnl061297 2-6 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
231 Electromagnetic Terrain Conductivity (EM) Survey
The initial EM survey was performed by Weston Geophysical Corporation over a three day
period (September 14-16 1994) using a Geonics EM-31 electromagnetic terrain conductivity
logger and a Model 720 Polycorder Background terrain conductivity readings were collected at
the beginning and end of each day from an area determined to be relatively free of electrical
interference The background station was located at the extreme southeastern corner of the Site
well away from the overhead electrical lines located along Tarbox Road and Route 12 (Norwich
Road) The EM-31 was calibrated daily by the operator and data was downloaded in the field to
a computer as needed typically twice a day
Following daily calibration the EM survey was performed by the instrument operator who paced
the entire length of each trend line with the EM meter and data logger Terrain conductivity
measurements were made and digitally recorded at five-foot intervals along each line The
presence of surficial objects and other features (eg steel fencing) that would cause interference
or produce anomalies were noted in the field notebook and accounted for during the data
evaluation Terrain conductivity data were subsequently plotted on a base map of the Site and
contoured to produce the terrain conductivity contour map included in the Weston Report in
Appendix A The results of the EM survey are discussed in Section 413
232 Magnetometer (MAG) Survey
The initial MAG survey was conducted by Weston Geophysical Corporation over a period of 7
days (September 7-14 1994) using two GEM-VI and one EGampG Model 856 magnetometers The
two GEM units were used for data acquisition while the EGampG unit was used as a base station to
monitor diurnal changes in the earths magnetic field The base station was established at the
southeastern corner of the Site where there was no interference from metallic objects or overhead powerlines and where no significant magnetic field gradients were observed
The MAG survey was performed by walking each trending line wiih one of the data acquisition
magnetometers (GEM-VI) and recording the magnetic field at every five-foot interval determined
by pacing The MAG data were eventually corrected for diurnal background fluctuations in the
earths magnetic field as determined at the base station and plotted on a base map to produce the
magnetic contour map which is included in the Weston Report in Appendix A The results of the
magnetometer survey are discussed in Section 413
5797wpdocsglaquolluprifinaltextmlaquo8terriftJ061297 2-7 QST Environmental
Gallups Quarry SuperUna1 Project - Remedial Investigation
233 Additional EM and MAG Surveys
In lieu of GPP surveys additional EM and MAG surveys were performed to determine the
precise location of any terrain conductivity or magnetic anomalies which could not be explained
by the presence of surficial metallic debris The additional surveys were performed over a 5-foot
by 5-foot grid in the vicinity of each unexplainable anomaly
A total of four unexplainable anomalies within three separate areas were eventually investigated
with additional EM and MAG surveys Once the locations of the anomalies were accurately
located each anomaly was further assessed by excavating test pits to identify the source of the
anomaly The test pit operations are discussed in Section 214 and the findings of the test pit
excavations are discussed in Section 4133
234 Seismic Refraction Survey
A seismic refraction survey was conducted along six 375-foot lines located within the suspected
fault zone An ABEM Terraloc 24-channel digital recording seismograph system was utilized for data collection The 375-foot spread lengths consisted of two overlapping 250-foot long lines
with geophones spaced in ten-foot intervals The endpoints of each seismic line were staked in
the field to facilitate the subsequent location survey
In accordance with the Work Plan shot points were located at each end point midpoint and
quarter point in addition to an offset from each end point The Work Plan had stated that
seismic energy would be produced by either an elastic wave generator or weight drop However
due to access constraints at the Site EPA approved the use of an alternate energy source For
these surveys seismic energy was generated using 8 gauge seismic shotgun shells discharged
approximately 2 to 3 feet below ground surface
The energy created by the shell blast travels through the ground and refracts along interfaces
between materials of different propagation velocity and density characteristics Interpretation of
these data on a time vs distance plot is conducted for the seismic wave arrival times at each
geophone The propagation velocities can be categorized into various geologic materials such as
overburden saturated overburden bedrock formations and weathered or fractured formations A
comprehensive discussion of the theoretical basis and operation of this technique is presented in
the Weston Geophysical report provided as Appendix A The results of the seismic refraction
survey are discussed in Section 32
5797wpdoc8gaIIuprifinaltextmasterrifnl061297 2-8 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
24 Groundwater Sampling Using Temporary Well Points Between August 29 and October 7 1994 a total of 60 small-diameter temporary well points
(microwells) were installed at predetermined locations using direct push techniques for the
purpose of collecting groundwater samples for both on-site and off-site chemical analysis At 10
of these locations equipment refusal occurred prior to encountering groundwater thus reducing
the total number of sampled locations to 50 The results of the chemical analyses were used to
determine the nature and extent (both horizontal and vertical) of groundwater contamination (VOC
and metals) within the Study Area Data obtained during this survey were ultimately used to determine the optimum location for subsequently-installed permanent groundwater monitoring
wells The surveyed locations of the temporary well points (TW101-TW160) including the 10 unsampled locations are shown on Plate 2-4 A summary of the locations and depth intervals for
each microwell is presented in Table 2-1
A total of 126 samples were analyzed on-site for selected VOC using a portable gas chromatograph (GC) A total of 121 samples (not including duplicates and field blanks) were
submitted for off-site laboratory analysis for cyanide and metals Also 12 samples (not including
field blanks and trip blanks) were submitted for off-site laboratory analysis for VOC to confirm
the on-site GC analytical data
The microwells were comprised of a 082 inch diameter (062 inch inside diameter) steel riser
pipe of varying lengths equipped with a hardened steel tip and a 5 foot long slotted section at the
leading end The 5 foot long slotted section (or screen) consisted of a four longitudinal rows of 2
inch long by 0015 inch wide slots Each microwell was advanced into the subsurface using
either an electrically or hydraulically powered vibratory impact hammer which was mounted on a
telescoping mast The mast drive-hammer and all other ancillary equipment were mounted on an all-terrain vehicle for maximum mobility
Individual sections of riser pipe (which varied in length up to a maximum of 21 feet) were
connected using a slip coupling over the butted ends of adjacent sections The slip coupling is
either electrically welded or crimped (using a hydraulic crimping tool) over the connection to
form a water tight joint
All materials were steam cleaned prior to use and only used at one location to avoid cross
contamination between sampling locations
The objective at each location was to drive the microwell into the saturated overburden and collect
a groundwater sample from three successively deeper intervals The desired sampling intervals
were as follows five feet below the top of the water table midway between the top and bottom of
5797wpdocsgalluprifinaltextmlaquoraquotemfhl061297 2-9 QST Environmental
Gallups Quarry SuperUna1 Project - Remedial Investigation
the aquifer and at the bottom of the aquifer (ie the refusal depth) A middle andor deep sample
was not collected if refusal was encountered without significant advancement of the well point
between sample depths (minimum of 10 feet) The midpoint sampling depth was estimated based
on the refusal depths encountered at nearby microwells
Once the microwell was driven to the desired depth purging and sampling was accomplished
using a manually operated inertial pump comprised of an adequate length of dedicated 38 inch
(inside diameter) polyethylene tubing equipped with a bottom check valve In operation the
inertial pump is lowered into the screen section of the microwell and repeatedly raised and
lowered (manually) a distance of approximately one foot This reciprocating action causes water
to rise within the tube until it is ultimately discharged at the ground surface into either a bucket or
sample container Between one and three riser volumes were purged from each microwell prior
to sample collection except for the first sample (5 feet below the top of the water table) which was
collected without purging All purge water was containerized and eventually transported off-site
for treatment and disposal
Once a groundwater sample was acquired it was labelled packed in a cooler and transported to
the on-site laboratory Each sample was analyzed on-site using a portable gas chromatograph
for the following eight VOC
bull l2-dichloroethene(DCE)
bull 111 -trichloroethane (111 TCA)
bull trichloroethene (TCE)
bull benzene
bull toluene
bull acetone
bull methyl ethyl ketone (MEK)
bull methyl iso-butyl ketone (MIBK)
Groundwater samples from each location were also collected filtered through a 045 micron
filter preserved with nitric acid and submitted to an off-site laboratory for analysis for the
following metals
bull aluminum
bull arsenic
bull cadmium
bull chromium
bull copper
5797wpdoc8galluprifinaltextmasterrifhl061297 2-10 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
bull iron
bull lead
bull manganese
bull nickel
bull zinc
Unfiltered samples were also collected preserved with sodium hydroxide (NaOH) and submitted
for analysis for cyanide In addition duplicates of 12 of the VOC samples analyzed in the field
were submitted for laboratory analysis for VOC for confirmation purposes Samples for off-site
VOC analyses were preserved in the field by addition of hydrochloric acid (HC1) to obtain a pH
less than 2
Samples for on-site VOC analyses were collected into 40 ml glass vials equipped with a teflonshy
lined silicon septum Each vial was filled capped labelled and refrigerated until it was
analyzed Samples were typically analyzed within several hours of collection Prior to analysis
the sample was removed from the refrigerator and 10 ml of water was withdrawn and discarded
The withdrawal of 10 ml of water created a headspace within each vial into which any VOC
present in the liquid would partition To complete the VOC partitioning process the vial was
then placed into a constant temperature (90 degC) water bath for a minimum of 15 minutes Just
prior to analysis a 250 micro-liter air sample was withdrawn from the headspace within the vial
by inserting the needle of the syringe through the teflon-lined septum and injected into the
portable gas chromatograph for analysis
A Photovac 10S50 portable gas chromatograph equipped with a CPCIL 5 encapsulated column
was used for on-site analysis The Photovac 10S50 gas chromatograph (GC) was filled every
morning with zero grade air and allowed to warm-up for 30 minutes prior to daily operation in
accordance with SOP 4001 and manufacturers instructions
The GC detector flow oven temperature and gain setting (sensitivity setting) were checked and
verified every morning and throughout the day Field GC standards were prepared daily by
diluting commercially available certified pure liquid chemical standards with deionized water
Three separate standards a low-concentration level a mid-concentration level and a high-
concentration level standard containing the eight select VOC were prepared in order to obtain a
three-point calibration curve Glass gas-tight syringes were used for preparation of standards and
sample injection AH syringes were decontaminated using methanol deionized water and
compressed gaseous nitrogen
5797wpdocsgalluprifinaltextmlaquo8terrifhl061297 2-11 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The GC operating condition was checked in the morning and during the day using machine
blanks syringa blanks and standards All three standards were run with a syringe blank directly
before and after each injection after every ten samples and at least once in the morning and once
in the afternoon each day In accordance with the QAQC program and SOP 4009 a duplicate
groundwater sample was collected in the field in a separate 40 ml glass vial immediately
following the collection of the original sample The second vial was used for duplicate analyses
after every ten samples
In the event that a sample analysis showed a contaminant chromatographic peak with an area
greater than the high-concentration standard or the range of the GC operating parameters (off-
scale) a smaller aliquot (l10th the original sample injection volume) was taken from the second
vial and injected into the GC All pertinent information concerning the smaller aliquot was
recorded on the GC strip chart and in the field log book
The GC strip chart was labeled with the sample identification number or corresponding
identification information (eg sample ID syringe blank etc) All pertinent information (eg
sample ID) was recorded in a field log book
In accordance with the QAQC program all samples were kept at 4degC prior to analysis and were
analyzed within 48 hours of their collection time
A total of 23 microwells (TW101-TW123) were installed by Pine and Swallow Associates Inc of
Groton Massachusetts Due to limited ability to access certain locations with the available
equipment the remaining 37 microwells were installed by a second subcontractor MyKroWaters
Inc of Concord Massachusetts Installation logs are presented in Appendix B The results of
the microwell survey are discussed in Section 421 The microwell installations were later
abandoned by filling them with cement grout and cutting the risers off below the ground surface
25 Soil Gas Survey In an effort to identify the location of any previously unknown potential disposal areas a Site-
wide soil gas survey was conducted From September 26 1994 through October 12 1994 a
total of 106 soil gas sampling probes were installed across the Site Soil gas samples were
analyzed on-site using a portable gas chromatograph
A 100-foot sampling grid was used to systematically cover the Site however actual locations
were dependent on accessibility and the ability to advance the soil gas probes to the desired depth
beneath the ground surface Besides the sampling at the intersection of grid lines six additional
locations were investigated due to the presence of empty drums found at the ground surface
5797wpdoC8galluprifinaltextmastemfnl061297 2-12 QST Environmental
Gallups Quarry Superfiind Project - Remedial Investigation
during the Site reconnaissance or anomalies detected during the EM and MAG surveys The
extreme northeastern corner and eastern side of the Site were not included in the soil gas survey
since they are either wetlands or heavily wooded Also an approximate 15000 square foot area
just north of the Former Seepage Bed was not tested due to the presence of a large pile of
boulders The surveyed locations of each soil gas sampling point (SV101-SV206) are shown in
Plate 2-5 The locations of SV111 SV201 and SV141 are approximate based on field
measurements from surveyed locations
Each soil gas sampling probe consisted of a four inch long hardened steel combination drive
point and screen which was connected to an adequate length of 316 inch diameter polyethylene
tubing The pointscreen and tubing assembly were inserted inside a hollow steel shaft which was
then driven into the ground with an electrically powered vibratory hammer
An abundance of gravel cobbles and boulders in the central portion of the Site prohibited the
advancement of several probes to the minimum depth specified in the Work Plan (25 feet) After
discussions with EPAs oversight contractor regarding the surface conditions in this area it was
agreed that at the rocky locations the probe would be driven as far as possible (typically 15-2
feet) and a two-foot by two-foot sheet of polyethylene sheeting would be placed on the ground
surface surrounding the probe and weighted with native topsoil The purpose of the plastic sheet
was to minimize atmospheric influence during the sampling procedure
Once the point was driven to the sampling depth the hollow steel shaft was extracted leaving the
expendable pointscreen and tubing in place The small annular space surrounding the sampling
tube was tightly packed with native soil to ensure that gas samples were representative of soil
pore space and not atmospheric conditions Once the probe was in place any excess plastic
tubing was trimmed leaving approximately 15 feet of tubing above the ground surface Each
tube was clamped and sealed until it was eventually sampled typically within a few days of
installation
To collect a soil gas sample one end of a 280 ml glass sample chamber (equipped with teflon
stopcocks and a sampling septum) was connected to the tubing using a short length of silicon
tubing A battery-operated vacuum pump was then attached to the other end of the chamber and
used to draw a soil gas sample from the tubing Once a sample was acquired the stopcocks were
closed and the pump shut off The sample chamber was then transported to the on-site laboratory
for analysis
Just prior to analysis the needle of a gas tight syringe was inserted through the sampling septum of the glass chamber and an aliquot of the soil gas sample was removed The sample was then
5797wpdoclaquogalluprifinaltextma8terrifiU061297 2-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
injected into the gas chromatograph for analysis A Photovac 10S50 portable gas chromatograph
was used to analyze each sample for the following 8 VOC
bull l2-dichloroethene(DCE)
bull 111-trichloroethane (111 TCA)
bull trichloroethene (TCE)
bull benzene
bull toluene
bull acetone
bull methyl ethyl ketone (MEK)
bull methyl iso-butyl ketone (MIBK)
The Photovac 10S50 gas chromatograph (GC) was filled every morning with zero grade air and
allowed to warm-up for 30 minutes prior to daily operation in accordance with SOP 4001 and
manufacturers instructions
The GC detector flow oven temperature and gain setting (sensitivity setting) were checked and
verified every morning and throughout the day Field GC standards were prepared daily using
certified pure neat liquid standards from sealed vials Glass gas tight syringes were used for
preparation of standards and sample injection All syringes were decontaminated using methanol
deionized water and nitrogen
The GC operating condition was checked in the morning and during the day using machine
blanks syringe blanks and standards Standards were run with a syringe blank directly before
and after each injection every ten samples In accordance with the QAQC program a duplicate
soil gas sample was collected in the field in a separate glass sample chamber immediately
following the collection of the original sample After the original sample was injected into the
GC the duplicate sample from the separate glass sample chamber was injected into the GC The
data quality objective (DQO) for field analysis using the GC was maintained at or better than _+
30 relative percent difference In the event that a sample analysis showed a contaminant
chromatographic peak with an area greater than the range of the GC operating parameters (off-
scale) a smaller aliquot (I10th the original sample injection volume) was taken from the glass
sample chamber and injected into the GC AH pertinent information concerning the smaller
aliquot was recorded on the GC strip chart and in the field log book
5797wpdocsgalluprifinaltextma8teiTifiil061297 2-14 QST Environmental
Gattups Quarry Superfund Project - Remedial Investigation
The GC strip chart was labeled with the sample identification number or corresponding
identification (eg sample ID syringe blank etc) The analysis number and corresponding
identification information was also recorded in the soil gas survey field log book
All sampling equipment (exclusive of the dedicated expendable probes) was decontaminated between each sample by flushing with copious amounts of compressed nitrogen The results of the
soil gas survey are discussed in Section 41
26 Soil Borings at Disposal Areas A total of sixteen soil borings SB101 through SB116 were advanced at the three known former disposal areas Ten soil borings (SB 101 through SB110) were completed as part of the Phase 1A
investigation between October 4 and 13 1994 Six additional borings were advanced within the
Former Primary Disposal Area on November 2 1995 as part of the Phase IB investigation The
locations of the soil borings are shown on Plate 2-5 The objective of these borings was to obtain
soil samples to characterize subsurface lithology and determine the present level and distribution
of residual contaminants within each former disposal area The analyses performed on samples
collected during the Phase 1A investigation (ie SB101-SB110) included TCLTAL parameters
as well as pH (EPA Method 9045) total organic carbon (ASTM Method D 17565373) moisture
content and particle size distribution Samples collected during the Phase IB investigation
(SB111-SB116) were submitted for laboratory analyses for VOC and PCBPesticides The samples submitted for analysis and the depth intervals sampled are shown in Table 2-2 The
results of the soil boring program are discussed in Section 41 All soil boring logs are shown in
Appendix C
261 Piiase 1A Soil Borings Each boring completed as part of the Phase 1A investigation was advanced until equipment refusal was encountered using a truck mounted drill rig equipped with a 425 inch (inside diameter)
hollow stem augers The drilling operations were performed by Environmental Drilling Inc of
Sterling Massachusetts As shown in Plate 2-5 three of the borings were placed in the reported
location of the Former Seepage Bed (SB101-SB103) three were placed within the Former
Secondary Disposal Area (SB104-SB106) and four were placed within the Former Primary
Disposal Area (SB107-SB110) The Work Plan required that samples be collected and submitted
for laboratory analysis from each boring from specific depth intervals (0-1 foot 1 to 10 feet and
10 feet to the water table) and from each distinct hydrological unit encountered (eg coarse
stratified drift fine stratified drift and till) and from the capillary fringe at each disposal area
The number of samples actually submitted for analysis was dependent on the depth to water and
the number of hydrogeologic horizons encountered at each area In general samples submitted
579Twpdoc8galluprifinaltextmlaquo8terrifhl061297 2-15 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
for laboratory analysis were selected from within each depth range or horizon based on PID
readings andcr visual observations
Soil samples from the 0-1 foot interval were collected from the ground surface using a stainless
steel hand trowel All subsequent samples were collected using a standard 2-inch diameter split-
spoon sampling device in accordance with ASTM Method D-1586-84 Each sample was
screened in the field for total VOC using a PID equipped with an 117 eV lamp Each sample
was then visually classified and logged in a field notebook and on boring logs A portion of each
sample was placed into glass jars and sealed with aluminum foil and a screw cap for headspace
analysis The headspace sample was ultimately saved for archival purposes
All sampling equipment was decontaminated prior to use and between each sample using a
detergent wash and tap water rinse followed by methanol nitric acid and deionized water rinses
All drilling equipment was steam cleaned between boring locations All decontamination rinseates
were containerized and eventually transported off-site for treatment and disposal Likewise all
soil cuttings were containerized for eventual off-site disposal Upon completion each borehole
was filled to the ground surface with a bentonitecement grout mixture and marked with a labeled
stake so that its location could be surveyed
262 Phase IB Soil Borings
Data obtained during the Phase 1A investigation indicate the presence of residual soil
contamination in the vicinity of the Former Primary Disposal Area In order to more fully
characterize the extent of this residual contamination six additional soil borings were completed
along the perimeter and within the Former Primary Disposal Area These borings (SB111shy
SB116) were installed by Connecticut Test Borings Inc of Seymour Connecticut using a track
mounted drill rig equipped with a standard split-spoon soil sampler Two samples from each
boring were submitted for laboratory analysis of TCL VOC and pesticidesPCBs At each
location a surface soil sample was collected from the 0-1 foot interval and submitted for
laboratory analysis Soil samples were then collected continuously from a depth of 1 foot below
the ground surface to the water table A discrete sample from within this zone was submitted for
laboratory analysis based on PID results At locations where no elevated PID headspace readings
were encountered a sample collected from the capillary zone was submitted for laboratory
analysis
5797wpdocsglaquolluprifinaItextmraquo8terrifiil061297 2-16 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
27 Installation of Monitoring Wells and Background Soils Sampling
Following the evaluation of data obtained during the visual Site reconnaissance and microwell
and soil gas surveys a network of monitoring wells was designed that would allow groundwater sampling and analysis and measurements of hydraulic parameters The installation of monitoring
wells at upgradient locations was also included to allow collection of background soil samples and
to determine upgradient groundwater quality
The majority of the Phase 1A investigation monitoring wells were installed by Environmental
Drilling Inc of Sterling MA A second drilling contractor Maher Environmental of North Reading MA was added in December in order to complete the monitoring well program before
the onset of winter The well installation program began on November 7 1994 and was completed on December 29 1994
The original Work Plan specified that a total of 47 monitoring wells would be installed but contemplated that the final number and locations of the monitoring wells could be adjusted based
on the findings of the preliminary screening surveys (ie the microwell and soil gas surveys)
Based on these data which were presented to EPA throughout the course of the screening surveys
EPA approved a Phase 1A monitoring well network which consisted of a total of 39 monitoring
wells at 16 locations
During the course of the Phase 1A monitoring well installation program one anticipated
intermediate depth overburden well (MW109T) was not installed because there was only
approximately 35 feet of saturated overburden encountered at that location A total of 38
monitoring wells at 16 locations were installed The surveyed locations of these wells are shown on Plate 2-6
By the end of the Phase 1A field program a total of 16 locations (or clusters) were completed
and were comprised of the following
bull (2) four well clusters (MW105 and MW107)
bull (4) three well clusters (MW101 MW108 MW112 and MW115) bull (8) two well clusters (MW102 MW103 MW104 MW106 MW109 MW113
MW114 andMW116) and
bull (2) single wells (MW110 and MW111)
(Note An additional 6 groundwater piezometers [PZ201-PZ206] were also installed)
5797wpdocsgalluprifinaltextmasterrifhl061297 2-17 QST Environmental
Gallups Quarry Superjvnd Project - Remedial Investigation
To further delineate the nature and extent of contamination and to refine the hydrogeologic
characteristics within the area of investigation a total of seven groundwater monitoring wells (and
one piezometer PZ301) were installed as part of the Phase IB investigation
The wells completed during Phase IB included the following
bull (3) two well clusters (MW117 MW118 and MW119)
bull (1) bedrock well (installed at the Phase 1A location MW102)
All Phase IB monitoring wells were installed by Connecticut Test Boring Inc utilizing a track-
mounted drill rig The surveyed locations of these wells are shown on Plate 2-6
AH monitoring well labels include a suffix code (eg S TT T or B) which indicates the location
of the screened interval (or open interval in the case of bedrock wells) for that particular well
The screen interval for each prefix is
S - Shallow well in which the screen intersects the surface of the water table
TT - Top-of-Till well in which the bottom of the screen is located just above the till
horizon
T - Till well in which the screen was placed within the till horizon and
B - Bedrock well in which the overburden is sealed off with steel casing which is
grouted into the bedrock surface and the well consists of an unscreened open hole
below the top of the bedrock surface
The TT T and B designations are geologically specific (top-of-till till or bedrock) while the S
designation is depth specific Monitoring well MW109S is in fact located within a till horizon but
was designated as an S well since the screen intersected the surface of the water table Similarly
although monitoring well MW110S is designated as a shallow(s) well observations recorded
during its installation indicate that MW110S is set just below the top-of-till interval
Specifically the 45 wells completed during the Phase 1A and IB investigations included the
following
bull 18 shallow (S) water table wells
bull 13 top of till (TT) wells
5797wpdoc8galluprifinaltextmasterrifhl061297 2-18 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull 5 till (T) wells and
bull 9 bedrock (B) wells
271 Phase 1A Monitoring Well Placement-Rationale
2711 Phase 1A Upgradient Monitoring Wells and Background Soil Sampling
Two monitoring well clusters MW109 (S B) and MW112 (S TT B) were installed to provide
soil and groundwater samples from various depths from locations upgradient of the known former
disposal areas These data were obtained to provide chemical data which was assumed to be
representative of background conditions The general location of these two well clusters was in
accordance with the general east to west direction of groundwater flow across the Site which had
been indicated during previous investigations and by the location of the contaminant plume
identified during the microwell survey The location of MW112 cluster (south of the Former
Seepage Bed) would also serve to confirm the presence or absence of radial groundwater flow
patterns away from the Former Seepage Bed During the installation of these wells soil samples
from stratified drift and till horizons were collected and submitted for laboratory analysis for
TALTCL parameters
A shallow top of till and bedrock well were installed at location MW112 The overburden wells
at this location were successfully installed using hollow stem augers A shallow till and bedrock
well were planned for location MW109 However since only approximately 35 feet of saturated
overburden was encountered at that location only one well MW109S was installed in the
overburden
The overburden and bedrock monitoring wells at these locations were constructed in accordance
with the general procedures described above with the exception of MW109S An abundance of boulders at this location prohibited the ability to advance augers or drive casing more than several
feet below the ground surface After numerous attempts within a 100-foot radius of the desired
location a backhoe was ultimately required to excavate a pilot hole in the unsaturated zone to
approximately 8 feet below the ground surface Augers were then lowered into the pilot hole and
advanced to the refusal depth of 12 feet The overburden well was then constructed as described
in Section 273
The bedrock well at MW109 was installed using a mud rotary drilling technique to drill an
overburden pilot hole to the bedrock surface into which 5-inch diameter steel casing was lowered
and seated on the top of the bedrock surface Another pilot hole was then drilled into the bedrock
to receive the permanent 3-inch casing The bedrock was subsequently cored as described in
Section 273
5797wpdoC8galluprifinaltextmaBterriftU061297 2-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
2712 Phase 1A Monitoring Wells - Former Primary and Secondary Disposal Areas
A total of nineteen ground water monitoring wells were installed in seven cluster locations at
downgradient areas relative to the known Former Primary and Secondary Disposal Areas
Monitoring wells MW102 (S TT) MW105 (S TT T B) and MW107 (S TT T B) were
located along the centerline of a groundwater contaminant plume detected during the microwell
survey and earlier studies
Well clusters MW101 (S TT T) MW103 (S TT) MW104 (S TT) and MW106 (S TT) were
located in areas believed to be beyond the edges of the contaminant plume delineated during the
microwell survey These wells were placed at these locations in an effort to define the plume
boundaries In addition the location of MW103 was selected by EPA to address historic
references to a leachate seep reportedly observed at Mill Brook west of the railroad bridge
Besides the nineteen wells described above another six monitoring wells at three locations were
installed in the vicinity of the Former Primary and Secondary Disposal Areas MW116 (S T) MW108 (S TT B) and MW110S were located north northeast and east of the former disposal
areas respectively to confirm the plume boundaries in these areas
2713 Phase 1A Monitoring Wells - Former Seepage Bed Area
A total of three monitoring wells were installed in the general vicinity of the Former Seepage
Bed A single bedrock well MW11 IB was placed west of the Former Seepage Bed within the
potential fracturefault zone identified by the geophysical studies The purpose of this well was to
assist in evaluation of whether the inferred fracturefault zone may be acting as a preferential
contaminant transport pathway from the Former Seepage Bed The location of MW113 (S B)
west of the Former Seepage Bed was selected to confirm water quality and to obtain
hydrogeological data in this area since an abundance of cobbles prohibited the advancement of
microwells into the saturated zone in this area
2714 Phase 1A Monitoring Wells - Southern Portion of the Site
Five monitoring wells located at two clusters (MW114 and MW115) were installed to determine
water quality and to characterize the hydrogeological parameters in the southern portion of the
Site Although there is no evidence to suggest that disposal activities occurred in areas of the Site
south of the Former Seepage Bed MW114 (S TT) and MW115 (S TT B) were placed to
coincide with locations at which low levels of VOC were detected during the microwell survey
5797wpdocsgalluprifinaltextmasterri fhl061297 2-20 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
272 Phase IB Monitoring Well Placement-Rationale The results of the Phase 1A investigation indicate that a well-defined low to moderate-VOC
concentration groundwater plume originates in the vicinity of the Former Primary Disposal Area
The plume is defined by the presence of certain VOC primarily TCA 12-DCE and xylene The
highest concentrations of these compounds were detected at MW107TT with decreasing
concentrations at downgradient well clusters MW105 MW102 and MW101
The compound PCE was detected in groundwater monitoring wells within the plume but its
distribution in groundwater exhibited inconsistencies with migration from the former disposal
areas In addition the observed concentrations of PCE did not coincide with the observed rate of
plume attenuation and transport rates possibly indicating an off-site source A goal of the Phase
IB investigation was to obtain additional information concerning overburden groundwater quality
and flow patterns in the area north-northwest of the Former Primary Disposal Area in order to
assess the potential for an off-site source
2721 Phase IB Monitoring Wells-Former Primary and Secondary Disposal Areas
One bedrock monitoring well (MW102B) was installed downgradient of the Former Primary and
Secondary Disposal Areas as part of the Phase IB investigation Data collected during the Phase
1A field program indicate that bedrock hydraulic gradients are generally upward across the Study
Area and that bedrock is not a preferential pathway for contaminant migration However low
concentrations of certain VOC were detected in bedrock well MW105B located downgradient of
the Former Primary Disposal Area To determine the nature of contaminant migration in bedrock
further downgradient from the source area a bedrock monitoring well was installed in the vicinity
of well cluster MW102 During the installation of MW102B soil samples were collected from
three intervals within the saturated portion of the overburden aquifer (15-17 30-32 and 45-57
feet below the ground surface) and submitted for laboratory analysis for total organic carbon
(EPA Method 9060)
2722 Phase IB Monitoring Well - North-Northwest of the Site Data obtained from CTDEP files during the Phase 1A investigation indicate that monitoring wells
located on the western and northern sides of the former Pervel flock plant (located just north of
the Site across Mill Brook) historically contained elevated concentrations of certain VOC
particularly PCE TCA and DCE A contribution of VOC in groundwater from this area could
explain at least partly the VOC detections in the wells at MW101 To confirm the potential for
groundwater flow from the former Pervel facility to the area around well MW101 and to further
refine the understanding of groundwater quality and flow in areas north-northwest of the Former
Primary Disposal Area three additional monitoring well couplets and one groundwater piezometer
5797wpdocsgalluprifinaltextmasterrifiil061297 2-21 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
were installed The Phase IB well couplets designated as MW117 MW118 and MW119
consisted of a shallow overburden well and a deep monitoring well screened above the till
horizon A groundwater piezometer designated as PZ-301 was installed in this area to provide
additional hydraulic data The surveyed locations of the seven monitoring wells and the
piezometer installed as part of the Phase IB investigation are shown on Plate 2-6
273 General Monitoring Well Installation Techniques
At each monitoring well (or cluster) location continuous soil sampling was initiated using either a
truck or track mounted drill rig equipped with 425 inch (ID) hollow stem augers and standard 2shy
inch diameter split-spoons The objective was to continuously sample and complete the deepest
overburden boring at each location using hollow stem augers A variety of subsurface conditions
(eg running sands greater that anticipated saturated overburden thicknesses and an abundance of
cobbles and boulders) prohibited the use of hollow stem augers all the way to completion depth at
many locations In order to overcome these drilling conditions EPA approved drive and wash
drilling techniques using water as a drilling fluid to complete many of the deeper overburden
monitoring wells The source of drilling water for this investigation was a nearby fire hydrant
which is connected to the local municipal potable supply system The introduction of drilling
fluids is generally avoided whenever possible as the presence of foreign fluids may cause some
dilution of any constituents which may be present The subsequent use of low-flow purging and
sampling techniques (discussed in Section 29) gave maximum assurance that samples collected
were representative of the natural formation waters
When drive and wash techniques were used the preferred casing diameter was six-inches Six-
inch diameter casing allowed the construction of a desired filterpack thickness of two inches (for
two inch diameter wells) However five-inch diameter and in some cases four-inch diameter
casing was also used primarily at locations in which access and drilling conditions prohibited the
advancement of six-inch casing in a timely and efficient manner EPA approved the use of five-
and four- inch diameter casing provided that the resulting monitoring wells were capable of
yielding low turbidity groundwater samples (which they ultimately did)
In accordance with the Work Plan continuous soil sampling was attempted at the deepest boring
at each location to provide continuous stratigraphic control However the presence of
uncontrollable running sands within certain intervals at several locations made the timely
collection of continuous viable samples extremely difficult In an effort to adhere to the original
schedule as closely as possible EPA approved lengthening the sampling frequency from
continuous to five-foot intervals at locations where running sands were encountered
5797wpdocsgalluprifinaltextmasterrifhI061297 2-22 QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
At several locations auger or casing refusal during the sampling stage was encountered above the
expected depth to bedrock (ie within or on top of the till horizon) At certain bedrock locations
which did not require further soil sampling EPA approved advancing and setting casing using
mud rotary drilling techniques In cases where drilling mud was used as the circulation media
powdered bentonite (National Sanitation Foundation International approved) was mixed with
potable water to yield a relatively thin drilling mud Once the borehole was drilled and stabilized
with drilling mud permanent steel casing was advanced and set The drilling mud was then
completely flushed from the borehole using fresh water and containerized (along with the water)
for eventual disposal In general the use of drilling mud is avoided whenever possible to
eliminate the introduction of foreign compounds in the aquifer Since drilling mud was used to
drill through overburden material (at bedrock wells only) and drilling mud was never in contact
with bedrock fractures the use of mud is not believed to have had any impact on groundwater
samples collected from these wells
All overburden monitoring wells were constructed using 2-inch diameter schedule 40 PVC well
screen and riser All screens consisted of continuous slot construction with 001-inch wide slots
The filter pack sand size grade was selected based on grain size data obtained during the soil
boring program The size-grade chosen (Morie OON) was selected in accordance with EPA
requirements (4 to 6 times the mesh size which retained 70 of the formation material) Most
screens were 10 feet long however several wells screened in till were constructed using 5-foot
long screens due to the limited thickness of the till horizon at those locations (MW105T
MW112T and MW116T) and the requirement to not install screens across different geologic
horizons Regardless of the screen length the filterpack surrounding the well screen extended a
minimum of one foot above the top of the screen A minimum two-foot thick seal of hydrated
bentonite clay was then emplaced above the filter sand pack Bentonitecement grout was then pumped from the bottom of the remaining annular space surrounding the riser pipe to the ground
surface Stainless steel centralizers were utilized to center the PVC screen within the borehole
Each well was completed with a locking 4-inch diameter steel protective casing which was
cemented in place approximately five feet below the ground surface
The bedrock wells were completed as open hole monitoring wells A minimum of four-inch
diameter steel casing was driven and seated on the bedrock surface A 3875-inch diameter pilot
hole was then drilled a maximum distance of five feet into competent rock Permanent 3-inch
diameter steel casing was then cemented into the pilot hole using tremie pipe and allowed to cure
for a minimum of 24 hours Once cured the grout inside the three inch casing was drilled out to
allow the bedrock to be cored At each location a minimum of 10 feet and a maximum of 25
feet of rock was cored using standard NX coring equipment The termination of all bedrock
wells was dependent on the occurrence of water-bearing fractures identified within the cored hole
5797wpdocsgalluprifinaltextmasterrifhl061297 2-23 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
Coring was terminated when evidence of water-bearing fractures were encountered All bedrock
wells were corHeted as open bedrock wells (ie not screened) as it appeared that the cpen holes
would not in-fl or collapse Each bedrock well was furnished with a locking 4-inch diameter
steel protective casing which was cemented in place over the permanent 3-inch diameter steel
riser
All monitoring wells were developed to remove residual particulates from the well and filter pack
and to restore the natural permeability of the formation Following well completion a minimum
of 48 hours were allowed to elapse before well development was initiated to allow the wells to
equilibrate and the grout to set Development was accomplished by overpumping various sections
of the screened interval until the field geologist determined that the pump discharge was visibly
free of particulate material Well development times varied from well to well and depended upon
the amount of fine (silt-clay) grained material at each screen interval Well development times
were usually on the order of several hours Water generated during well development was
containerized for eventual shipment off-site
All soil boring logs rock coring logs and monitoring well construction logs are provided in
Appendix C A summary table which shows survey data and other pertinent information for each
monitoring well and piezometer is presented as Table 2-3
274 Stream Piezometers and Gauges
Nine piezometers were installed at various locations within Mill Brook to monitor surface water
conditions and to determine the role of the local groundwater system in relation to stream
dynamics Water levels were recorded during several periods of the investigation to determine if
Mill Brook is a discharge or recharge point for groundwater in the vicinity of the Site In
addition five stream gauges were installed at piezometer locations PZ-1 PZ-3 and PZ-6 and at
two additional locations in Fry Brook one above and one below the confluence with Mill Brook
The locations of the stream piezometers and gauges are shown on Plate 2-6
Each stream piezometer consisted of a one-foot long slotted steel well point connected to threaded
and coupled lengths 125 inch ID steel pipe with a threaded cap The piezometers were
manually driven a minimum of two feet into the stream bed Water level readings were collected
by lowering an electronic water level indicator along both the inside and outside of the piezometer
to obtain depth to water readings for shallow groundwater beneath the stream bed and depth to
surface water respectively The stream gauges consist of a graduated steel scale attached to a
steel post which was driven into the stream bed
5797wpdocsgalluprifinaltex1masterrifhl061297 2-24 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
275 Groundwater Piezometers
Although not specified in the Phase 1A Work Plan EPA approved the installation of six shallow
groundwater piezometers (PZ-201 through PZ-206) in the southern portion of the Study Area to
provide additional overburden piezometric data A seventh groundwater piezometer PZ-301
was installed north of the Site during the Phase IB investigation The locations of the
groundwater piezometers PZ-201 through PZ-206 and PZ-301 are provided on Plate 2-6
The seven groundwater piezometers were installed using either a track or a truck-mounted drill
rig equipped with 425 inside diameter hollow stem augers At each location the augers were
advanced and the piezometer set at approximately five feet below the top of the groundwater
table The piezometers were constructed of 1-inch diameter PVC well screen and riser equipped
with five-foot long screens Once the screen was set a sand pack was installed to approximately
one foot above the top of the screen A hydrated bentonite seal was then emplaced on top of the
filterpack The remainder of die annular space was backfilled with clean native soil and capped
with concrete Each piezometer was furnished with a lockable protective casing which was
cemented in place Upon completion each piezometer was surveyed and included in each
subsequent round of groundwater level measurements
28 Aquifer Parameter Testing 281 Grain Size Analysis
A total of 41 soil samples collected during the Phase 1A soil boring and monitoring well
installation programs were submitted for laboratory grain size analysis All grain size analyses
were performed using common sieve and hydrometer techniques in accordance with ASTM
Method D 422-63 (Reapproved 1990)
Of the 41 samples 16 were obtained from horizons described as fine stratified drift 15 were
obtained from horizons described as coarse stratified drift and 10 were obtained from horizons
described as till A total of 29 of the samples were obtained during the soil boring program
and 12 were obtained from samples collected during the monitoring well installation program
The analyses were conducted by Geotechnics Inc of Pittsburgh PA a laboratory which
specializes in geotechnical analyses A summary of the samples submitted and their depth interval
is presented as Table 2-4 The results of grain size analyses are discussed in Section 33 In
addition to grain size these samples were also submitted for laboratory analysis for pH moisture
content and total organic carbon
5797wpdoc8galluprifinaltextmasterrifhl061297 2-25 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
282 Slug Tests
Single-well variable head aquifer tests were conducted on all the wells installed during the Phase
1A investigation between January 5 and 27 1995 Rising and falling head tests were performed
on each well using a manually deployed solid cylinder or slug A pressure transducer and an
electronic data logger were used to measure and record the water level response in the well (on a
logarithmic time scale) after the slug was submerged (falling head) and removed (rising head)
Changes in water levels were recorded until the water had returned to or near the original static
level The data collected from the slug tests were analyzed to determine hydraulic conductivity
values for the screened intervals in each well The rate of change of hydraulic head was analyzed
using the Bouwer-Rice Method (Bouwer and Rice 1976) implemented in the computer program
AQTESOLV (Geraghty amp Miller Inc 1989) The results are presented in Section 33 of this
report
283 Constant Flow Tests
Constant flow tests consisting of short-term pumping tests were performed on selected
groundwater monitoring wells as part of the Phase IB investigation Constant flow tests were performed on the following wells MW102TT MW103TT MW104TT MW105TT
MW107TT MW117(S TT) MW118(S T) and MW119(S TT) In these tests an approximate
steady-state drawdown is established in the well and an analytical model of flow to a well is used
to compute hydraulic conductivity The tests were conducted using a variable speed submersible
pump and an electronic water level indicator Prior to the start of each test the static water level
was determined The tests were conducted by running the pumps at a constant known pumping
rate for short periods of time (typically less than 15 minutes) while recording drawdown until
equilibrium was reached The pumping rate drawdown and well construction details were then
used to calculate the hydraulic conductivity The results of the constant flow tests are discussed
in Section 33 of this report Field data and examples of the data reduction method are presented
in Appendix F
29 Groundwater Sampling In accordance with the Work Plan a complete round of groundwater samples was collected
following completion of the Phase 1A monitoring well installation program during January 11shy
19 1995 and is referred to as the Phase lAJanuary 1995 sampling event Subsequent
sampling events were performed as part of the Long Term Monitoring Program during April
July and November 1995 February May August and November 1996 and February 1997 As
discussed in Section 1-1 of this report individual Data Reports for all of the Long-Term
Monitoring Program sampling events (except November 1995 which was presented with the draft
RI Report) have been submitted to EPA
5797wpdoc8galIuprifin8ltextma8terrifnl061297 2-26 QZT Environmental
Gallups Quarry Suptrfund Project - Remedial Investigation
During the Phase IB field program seven new wells were installed and added to the list of wells
that were sampled (for VOC only) during the November 1995 monitoring event Six of these
wells (MW117STT MW118STT and MW119STT) were not added to the list of wells to be
sampled under the Long Term Monitoring Program although MW102B (also installed during
Phase IB) was added to the Long Term Monitoring list In addition to the wells installed during
the Phase IB investigation the following five existing wells located on the former Pervel
property were included as part of the Phase IBNovember 1995 sampling event MW-A -B -C
-2 and -3 The existing on-site wells SW-3S and SW-3D were also included in the Phase
IBNovember 1995 sampling event and the subsequent Long-Term Monitoring Program sampling
events Since the November 1995 Long-Term Monitoring event included wells that were specific
to the Phase IB investigation the November 1995 sampling event is referred to as Phase
IBNovember 1995
During the period spanning the nine sampling events discussed in this report EPA has approved
modifications to the list of wells sampled under the Long-Term Monitoring Program
Modifications to the list of wells sampled have been to delete certain wells particularly those
located in the southern portion of the Site where no site related compounds have been or are
expected to be detected After the July 1995 sampling event wells at the following locations
were eliminated from the Long Term Monitoring Program MW111 MW112 MW114 SW-9
SW-10 and SW-12 Monitoring wells located at MW110 MW113 and MW115 were eliminated
following the Phase IBNovember 1995 sampling event The following subsections describe the
field methods which have been used consistently over the nine sampling events discussed in this
report Table 2-5 shows which wells were included in each sampling event
291 Monitoring Wells The groundwater sampling locations are shown on Plate 2-4 Low-flow purging and sampling
procedures were used to collect groundwater samples in an effort to obtain turbidity-free samples
and to minimize disturbance of the natural formation
The following sequential procedures were employed during the groundwater sampling effort
1) The static water level was measured using an electronic water level indicator
2) The absence of LNAPL was visually confirmed by observation of a sample
collected using a clear plastic bailer
3) All 2 inch diameter (or larger) monitoring wells were sampled using a stainless steel electric submersible pump (Grundfos Redi-Flo 2) equipped with teflon
5797wpdocsgalluprifinaltextmasterrifhl061297 2-27 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
discharge tubing To initiate the purging procedure the intake for the pump was
owered into the mid-section of the well screen For wells smaller than 2 inch
aiameter (ie existing SW- series wells) Teflon tubing equipped with a bottom
check valve was used to inertially purge the well
4) Water was purged from the well at a low flow rate (approximately 05 litersmin)
which was continuously monitored The water quality field parameters
(temperature pH conductivity and turbidity) were monitored during the purging
process until they had stabilized within 10 over three consecutive readings
5) Once the parameters had stabilized (or a minimum of five well volumes had been
purged) groundwater samples were collected for laboratory analysis Samples
were collected from the discharge end of the pump tubing by directly filling the
appropriate sample containers in the following order VOC SVOC (including
pesticides and PCB) metals inorganic compounds At wells that did not stabilize
below the 5 NTU turbidity requirement additional metals samples were collected
filtered through a 045 micron filter and submitted for dissolved metals analyses
(in addition to total metals)
6) Samples were collected from the upper and lower portion of each well using a
clear plastic bailer to visually assess the potential presence of NAPL
All sampling equipment was decontaminated between sampling events All purge water was
containerized for eventual off-site disposal
Duplicate samples matrix spikes matrix spike duplicates field blanks and trip blanks were
included as part of the QAQC procedures All groundwater monitoring sampling forms are
included as Appendix D Most groundwater samples were submitted for TALTCL VOC SVOC
pesticidesPCB and metals although a small number of samples collected during the Phase
lAJanuary 1995 and April 1995 event were submitted for VOC SVOC pesticidesPCB and
metals by Appendix IX methods Also certain samples were selectively submitted for VOC
analyses by Method 5242 The analytical methods for each sample submitted for laboratory
analysis are shown in Table 2-5
5797wpdocsgalluprifinlaquoltextmlaquosterrifhl061297 2-28 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
292 Residential Wells A total of fourteen private drinking water supply wells (DW101-DW114) were scheduled to be
sampled as part of the groundwater sampling program However two of the residences (DW101
and DW112) were unoccupied and inaccessible at the time of each of the sampling events The
residential wells are located along the eastern perimeter of the Site along Route 12 (Norwich
Road) adjacent to the southern portion of the Site along Tarbox Road and along Lillibridge
Road well south of the Site The residential well sampling locations are provided on Plate 2-5
In accordance with the Long-Term Monitoring Program the residential wells were sampled on a
semi-annual basis during the regularly scheduled summer and winter quarterly sampling events
In addition to the Phase lAJanuary 1995 sampling event residential groundwater samples were
collected during July 1995 February 1996 and August 1996 as shown in Table 2-5
Prior to the collection of groundwater samples from the residential wells a visual survey was
conducted to identify the sampling point closest to the well and to determine if any treatment
systems were in use A description and sketch of the supply system was recorded in field
notebooks Each system was opened and allowed to drain for approximately 15 minutes to purge
the plumbing system and obtain representative samples Field parameters were recorded during
purging to determine when stabilization had occurred The groundwater samples collected from
the residential wells were submitted for laboratory analysis of TCL SVOC pesticides PCB TAL
metalscyanide and VOC using EPA Method 5242
210 Surface Water and Sediment Sampling As part of the Phase 1A Investigation surface water and sediment sampling was conducted on
September 13-16 November 22 and December 29 1994 Although all locations were originally
sampled during the September sampling event three samples were lost in transit and had to be reshycollected A total of seventeen sample locations along Mill Brook and unnamed tributaries (UB1shy
UB10 and LB1-LB2) Fry Brook (FBI) Packers Pond (PP1-PP3) and a small pond along Tarbox
Road (TR1) were included in this program The re-sampled locations were UBS and UB6 (112294) and TR1 (122994) Due to dry conditions surface water samples could not be
obtained from the following locations UBS UBS UB6 UB7 and PP1
In accordance with the Long Term Monitoring program additional surface water samples were
collected during the April 1995 November 1995 May 1996 and November 1996 sampling
events to coincide with the approximate seasonal high- (ie spring) and low-water (ie autumn)
periods Following the initial Phase lAJanuary 1995 sampling event and per the request of
EPA the location of UB6 was moved due south to Mill Brook and renamed UB6A The surface
watersediment sample locations are shown on Plate 2-6 Sample locations by date are shown on
Table 2-5
5797wpdocsgalluprifiMltextmasterrifhl061297 2-29 Q5T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Surface water samples were collected using the actual laboratory sample containers by direct
immersion into the water Parameters which required the use of preservatives (eg metals
requires the addition of nitric acid to the sample) were collected in a stainless steel beaker and
transferred directly to the sample container to prevent loss of the preservatives during sampling
All sampling equipment was decontaminated after each use and placed into clean plastic bags
before moving on to the next station Surface water samples were collected starting at the most
downstream locations and progressed in order upstream The surface water samples were
submitted for laboratory analysis for TCLTAL compounds VOC and the following wet
chemistry parameters total organic carbon total dissolved solids total suspended solids hardness
and alkalinity The samples collected during April 1995 November 1995 and May 1996 were
also submitted for laboratory analysis of SVOC pesticides and PCBs The following field
measurements were also collected as part of the sample collection temperature conductivity
pH dissolved oxygen and turbidity
In addition to surface water during September 1994 sediment samples were collected at each of
the 17 locations (including the dry locations referenced above) Samples were collected at a depth
of 0 - 8 below the surface using manually operated soil or mud augers which were
decontaminated between sample locations The sediment samples were collected starting at the
most downstream locations and progressed in order upstream The sediment samples collected
contained greater than 30 percent solids based on visual and manual determination Samples were
submitted for laboratory analysis for TCLTAL compounds and for total organic carbon
Physical stream bed parameters (width depth and flow rate) were measured at surface water
sampling locations where discernable flow occurred This task was completed in April 1995
since the stream was at extremely low flow stages during the September 1994 sampling round
and a number of surface water sampling locations were nearly dry During the April 1995
surface water sampling event stream flow conditions were such that flow rates could be measured
at the following 5 locations UB4 UB6A UB9 UB10 FBI Locations at Packers Pond and the
small pond on the south side of Tarbox Road (TR-1) were not subject to these stream
measurements
Stream width and depth measurements were made using a fiberglass tape measure Depth and
stream flow measurements were recorded at the midpoint and quarter-points across the stream
Stream flow measurements were recorded using a Swoffer model 2100 in-situ flow meter The
flow meter was mounted on a graduated aluminum shaft which was equipped with an electronic
digital readout To calculate stream-flow the average cross-sectional area in square feet was
multiplied by the average water velocity (feetsec)
5797wpdocsgraquolluprifinaltextmasterrifhl061297 2-30 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
211 Wetland Soil Sampling In early September 1994 samples of wetland soils were collected from 10 locations within the
Study Area These sample locations (QW1-QW10) are shown on Plate 2-6 (and on Plate 3-14
which shows delineated wetlands as discussed in Section 341) Each sampling station was
marked with labeled stakes which were eventually included in the Site location survey The
samples were collected at locations situated near the edge of the wetlands at depths within one foot of the water table and below the organic mat The samples were collected using manually
operated soil or mud augers which were decontaminated between sample locations The samples were submitted for analysis of TCLTAL compounds and total organic carbon The results of the
wetland soil sampling program are discussed in Section 43
212 Evaluation of Existing Monitoring Wells As part of the Phase 1A investigation the remaining 11 monitoring wells installed during the
1978 Fuss and ONeill Inc investigation were evaluated to determine which wells could provide
usable water level data The present condition of each well was documented and a water level and total depth measurement were taken and compared to well construction logs If the wells
were determined to be potentially viable an attempt was made to test them for hydraulic
responsiveness by conducting rising and falling head slug tests Several of the wells were missing
protective casings had been broken off below the ground surface or had infilled with sediment
The results of the hydraulic evaluations are presented in Section 33 The locations of the
remaining existing monitoring wells are shown on Plate 2-4
A summary of the condition of each existing monitoring well is presented as Table 2-6 The
majority of the existing wells are presently in poor condition Most of these wells are lacking
surface seals andor adequate protective casings Several of the wells have no protective casings at all and are comprised only of PVC riser which is broken at or near the ground surface
Based on the present total depths of several of these wells compared to their total depths at the time of construction it is evident that the screen section of several of these wells have infilled
with sand or silt Based on their present condition and the fact that new monitoring wells have
been installed ESE recommended that any of the existing wells not included as part of the Long-
Term Monitoring Program be properly abandoned Following this recommendation EPA
approved the abandonment of the following wells SW13 SW14 SW17S D and SW18 Also
the protective casings at existing wells SW-3S SW-3D SW-9 SW-10 and SW-12 were repaired
since these wells are used to measure groundwater elevations as part of the Long-Term
Monitoring Program
5797wpdoc8galluprifinaltextmasterrifhl061297 2-31 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
213 Ecological Assessment 2131 Wetlanl Delineation
A wetland delineation was conducted on Site and focused primarily on the wetlands located north
and west of the Study Area This survey was limited to the Site side of Mill Brook up to the
present channel In order to meet both Federal and State requirements two methods were used to
delineate the Study Area wetland boundaries In accordance with federal requirements wetlands
were delineated using US Army Corps of Engineers (COE) methods Since the State of
Connecticut recognizes a slightly different methodology for wetland delineation the services of a
soil scientist certified by the Society of Soil Scientists of Southern New England were also
required The only difference between the two methods is that while the COE requires analysis
of vegetation composition hydrology and hydric soil indicators the State of Connecticut requires
only the analysis of hydric soil indicators
Jurisdictional wetland boundaries were determined by evaluating several points along the
hydrologic gradient Vegetation soil and hydrology criteria were measured or observed to
determine whether the point was within or above the Jurisdictional wetland boundary In order
for an area to be judged Jurisdictional wetland criteria must be met for all three parameters (ie
vegetation hydrology and soil)
21311 Vegetation
Wetland criteria for vegetation was based on the National List of Plant Species That Occur in
Wetlands (Reed 1988) Dominant plant species were identified at the observation point and listed
on data forms for routine on-site wetland determination The stratum where the plant occurred
(canopy shrub or herb) and indicator status for that plant were recorded A dominance of
wetland indicator species indicates that the vegetation criteria is met A dominance of upland
indicator species indicates that wetland criteria are not met
21312 Hydrology
Hydrologic criteria includes the visual observation of surface water inundation soil saturation or
indirect indication of previous saturation or inundation Indirect evidence includes watermarks
(stain lines on vegetation or structures) drift lines (debris deposited in a line at the high water
mark) sediment deposits and drainage patterns within wetlands
21313 Hydric Soils
The identification of hydric soil criteria includes soil types named as hydric by USDA Soil
Conservation Service or the presence of hydric indicators within the soil profile Indicators
include mottling or streaking of organic materials high organic content the presence of sulfitic
material soil colors (gleyed colors) and others
5797wpdoc8galluprifinaltextmasteirifhl061297 2-32 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
2132 Plant and Wildlife Survey
The objective of the Phase 1A ecological assessment was to qualitatively identify any real or
potential impacts to local ecological receptors within the Study Area or otherwise influenced by
the conditions originating at the Site All observations on plants and animals were noted in field
logs during the wetland delineation
The results of this survey will assist the EPA in the performance of a more formal ecological risk
assessment During the ecological risk assessment sediment soil water and air quality data and
observations of plant and animal communities will be used (see also Section 123) to identify any areas where impacts have occurred The results of the qualitative plant and animal survey
conducted during the wetland investigation are discussed in Section 34 of the text
214 Test Pit Explorations In lieu of ground penetrating radar surveys (as discussed in Section 233) and with EPA
approval additional EM and MAG surveys were performed over a five-foot by five-foot grid in
the vicinity of unexplainable anomalies which were detected during the initial EM and MAG
surveys Once accurate locations for the anomalies were determined and marked on the ground
surface test pit explorations were conducted to confirm the source of the anomalies
On December 21 1994 test pits were excavated at a total of four locations at which
unexplainable anomalies were detected The test pits were performed under the observation of
EPA oversight contractor personnel The locations of the four anomalies and associated test pits are shown on Plate 2-7 At each anomaly a trench (or series of trenches) was systematically
excavated in one to two foot lifts using a backhoe The trenches were oriented to intersect the
longest axis of each anomaly to maximize the possibility of unearthing the source of the anomaly Once a lift was complete soil obtained from the trench walls as well as that obtained from the
backhoe bucket was screened with a PID for evidence of VOC The excavated soil and the trench
itself were also visually monitored for objects capable of producing the anomalies detected during the geophysical surveys and for other features possibly associated with disposal activities (eg
stained soil)
Once the source of each anomaly was discovered the object was excavated and the test pit was
backfilled and regraded with clean soil obtained from the excavation Since no elevated PID
readings or other signs of disposal features were encountered during the test pit operations no
soil samples were submitted for laboratory analysis Test pit logs for these excavations are
presented in Appendix E
5797wpdocsgalluprifinaltextmasterrifhl061297 2-33 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
30 Physical Characteristics of the Study Area
31 General Characteristics 311 Regional Physiography
The Site is located along the eastern border of the Quinebaug Valley Lowland This regional
feature is dominated by the southerly flowing Quinebaug River and is comprised of a north-south
trending lowland area which is approximately 2 to 3 miles in width and approximately 25 miles
long The Quinebaug River originates at headwaters located in central Massachusetts and
terminates at Norwich Connecticut where it merges with the Shetucket River approximately 12 miles south of the Site The confluence of these two rivers form the Thames River which flows
to the south approximately 15 miles and ultimately discharges into Long Island Sound
The region is characterized by relatively low relief and numerous glacial features The regional
landscape is significantly influenced by the structure of the underlying crystalline metamorphic
bedrock which is discontinuously overlain by Pleistocene glacial sediments of variable thickness
Lowland surficial features are characteristic of late Pleistocene glacial retreat processes and
include numerous kettleholes and swamps many of which are interconnected by a network of
slow draining streams
Land surface elevations in the vicinity of the Site range from approximately 150 to just over 220
feet above sea level Lowlands are bounded to the east and west by upland terrain which consists of irregular hilly areas of moderate relief The uplands contain many areas with large bedrock
ledges generally thin glacial deposits (predominantly till) poorly drained valleys and small
isolated swamps Elevations in the uplands range from 200 to 600 feet above sea level
312 Study Area Physiography
The topography on the Site is highly irregular primarily due to past quarrying operations
Numerous overgrown mounds of earthen materials (eg crushed stone sand and gravel) and
excavated depressions are scattered throughout the Site Visual reconnaissance and a number of
screening surveys (eg soil gas and surface geophysical investigations) have confirmed that many
of the features previously identified from the review of historic aerial photographs as potential
disposal areas (Bionetics 1990) were in fact features remnant of quarrying and former CTDOT
operations
The ground surface on the Site (shown on Plate 3-1) generally slopes from east to west and to a
large degree is controlled by the underlying bedrock surface The highest point within the Study
Area consists of a bedrock high overlain by a thin veneer of till and is located in the eastern
5797wpdoclaquogalluprifinraquoltextma8terri fhl061297 3-1 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
central portion of the Site Elevations in this vicinity peak at approximately 230 feet above sea
level
The northern portion of the Site which includes the Former Primary and Secondary Disposal
Areas consists predominantly of open sparsely or non-vegetated areas of sand and gravel This cover material is presumed to have been distributed over the ground surface following CTDEP
Site remediation efforts in 1979 Presently the Former Primary and Secondary Disposal Areas are visible as roughly circular depressions which are approximately 150 feet and 60 feet in
diameter respectively The depressions are approximately 8 to 12 feet deep relative to the
surrounding ground surface These depressions intermittently contain as much as several inches
of standing water which accumulates during periods of heavy precipitation The bottoms of the
depressions are lightly vegetated with various grasses and weeds
North and west of the Site the ground surface elevation decreases as the Mill Brook floodplain is
encountered The floodplain area consists of low lying heavily vegetated wetland areas which
are periodically inundated
Excluding the isolated topographic high spot at the eastern margin of the Site the southern
portion of the Site (from the vicinity of the Former Seepage Bed to Tarbox Road) can be
described as generally flat but includes numerous man-made small-scale features such as
mounds or depressions
313 Surface Water Features
The Site is centrally located within the Mill Brook drainage basin which encompasses
approximately 18 square miles The Mill Brook drainage basin is part of the larger Quinebaug
River regional drainage basin Mill Brook a tributary to the Quinebaug River is located 250 feet
north of the Site and flows from east to west Approximately 1000 feet northwest of the Site (in
the vicinity of the Plainfield municipal sewage treatment plant) Mill Brook is joined by Fry
Brook which flows from the north Packers Pond which is located approximately 3000 feet
west of the Site was formed by the construction of a dam across Mill Brook
There are no surface water bodies located on the Site itself although several low areas (which
were excavated during previous site activities) have been observed to contain ponded water during
periods of extended precipitation
Surface water flow rates (determined during the April 1995 sampling event) were determined for
the following five locations in Mill Brook UB4 UB6A UB9 UB10 and at FBI in Fry Brook
Along Mill Brook flow rates ranged from approximately 23 cubic feet per second (cfs) at the
5797wpdocsgalluprifinaltextmasterrifnl061297 3-2 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
most upstream location (UB4) to approximately 31 cfs at the most downstream location (UB10)
Along the northern Study Area a 3 cfs increase was observed from Stations UB6 to UB10
representing a flow rate increase of about 025 cfs per 100 feet of stream length The flow rate in Fry Brook (Station FBI) was approximately 16 cfs
314 Climate The Site is located within Connecticuts Central climate division According to published
National Weather Service data (USGS 1993) the average annual temperature is approximately
50degF the coldest month is January with an average temperature of 258T and the warmest month is July with an average temperature of 714degF Annual precipitation at nearby recording
stations (located in Norwich CT and North Foster RI) averages approximately 53 inches per
year and ranges between approximately 41 and 68 inches per year (based on historic data from
1978 to 1991) The monthly distribution of precipitation is relatively even throughout the year
32 Geology 321 Regional Surficial Geology
The surficial or overburden deposits in the area consist of unconsolidated materials deposited as a
result of glaciation during the Pleistocene epoch Various glacially-derived materials including till meltwater or stratified drift deposits and post-glacial deposits of floodplain alluvium
comprise the major surficial geologic units in the vicinity of the Site Areas covered by eolian dune deposits are also noted on surficial geologic maps of the area although no dune deposits are
found within the Study Area
Till deposits in the region consist of non-sorted and generally non-stratified mixtures of sediments
with grain sizes ranging from clay to boulders Till is formed by the direct deposition of ice debris on the land surface Generally the color and lithology of till is dependant upon the
composition of local surficial deposits underlying bedrock and northerly adjacent bedrock from
which the till was derived Tills deposited during two periods of glaciation are present in the
region and blanket the bedrock surface in various thicknesses The most extensive and prevalent
till which is commonly present in surface exposures was likely deposited during late
Wisconsinan glaciation (USGS 1995) This till is referred to as upper till and is described as
predominantly loose to moderately compact generally sandy and frequently stony
A less commonly exposed lower (older) till was deposited during earlier glaciation possibly during the Illinoisan or early Wisconsinan glaciation periods The lower till is generally compact
to very compact and is typically finer-grained and less stony than the younger upper till A
weathered zone is usually present between the two till units
5797wpdoc8gnlluprifinaltextmasterrifnl061297 3-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Directly overlying the till (or bedrock where till is absent) are glacial meltwater deposits
collectively referred to as stratified drift These deposits consist of poorly to well sorted
assemblages of gravel sand silt and clay which were deposited by glacial meltwater during the retreat of the last ice sheet Variations in the composition structure and texture of the stratified
drift deposits are dependent upon the depositional environment in which they formed Deposits exhibiting a relatively high degree of sorting andor stratification can usually be classified as
either glaciofluvial (stream) deposits glaciodeltaic (where streams entered glacial lakes) deposits or glaciolacustrine (lake bottom) deposits The horizontal and vertical contacts between these
deposits are generally transitional and were dependent upon the available sediment load and
proximity to the various depositional environments (eg streams or lakes) associated with the
retreating ice front For example coarse-grained deposits of sands and gravel were usually
deposited proximal to the ice margin while further away primarily in glacial lakes deposits of
fine sand silts and clay were prevalent Poorly sorted deposits of relatively coarse material were
typically deposited at the ice front or along bedrock valley walls During the glacial retreat
these deposits would be left behind or collapsed on any underlying deposits Contemporaneously bedrock valleys were frequently dammed by glacial deposits andor masses
of glacial ice behind which glacial meltwater could accumulate forming glacial lakes Gradual
retreat of the ice margin as well as the formation (and eventual draining) of glacial lakes over
time would result in changes in the depositional environment which are seen as textural changes in the stratified drift deposits
Postglacial deposits of sand gravel silt and organic materials are also present as floodplain
alluvium along streams and rivers in the region The texture of alluvium varies over short
distances both laterally and vertically and is generally less than 5 feet thick along small streams
Since alluvial material typically represents re-worked glacial deposits the alluvium is often similar to the surrounding parent glacial material
322 Local Surficial Geology
The Study Area is located on the eastern flank of a pre-glacial bedrock valley and is bounded to
the east by bedrock-controlled upland areas and to the west by an area known as the Quinebaug
Valley lowlands Following the last period of glaciation (in which the relatively thin veneer of till
was deposited) various temporary depositional environments existed as a result of the presence of
an ice and sediment dam approximately 10 miles south of the Study Area which caused the
formation of a glacial lake Evidence of the lake (referred to as Glacial Lake Quinebaug) is well
documented in the literature (Stone amp Randall 1977) As the ice sheet retreated northward deposits left behind were dominated by sand and gravels associated with the formation of a series
of progressive and coalescing deltaic complexes which developed within the rising lake In lower
lying areas where deltas did not form finer-grained sand silt and clay was deposited Although
5797wpdocsgalluprifinaltextma8terrifhl061297 3-4 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
much of this sediment may originally have been deposited with some degree of structure or
sorting much of the structure was lost (collapsed) when the ice mass eventually melted away
The depositional environment was further complicated by the presence of residual ice blocks left
behind during the retreat of the main body of the glacier As the various depositional features
formed around these ice-blocks their eventual melting left behind depressions or kettles into
which fine sediment could settle While many kettles were eventually filled many remain as
detached or poorly drained ponds
As a result of the depositional history of the Study Area the primary surficial or overburden
deposits encountered are till and stratified drift Depending upon location the stratified drift may
be generally broken down into fine (eg silt and fine sand) or coarse (eg sand and gravel)
grained components but at many locations the change is transitional and subtle in both vertical
and horizontal directions The thickness of the stratified drift deposits ranges from non-existent
up to approximately 70 feet At some locations distinct structure is exhibited while at other
locations the structure has collapsed Post-glacial alluvial floodplain deposits were encountered
at locations within the present Mill Brook floodplain however the overall significance of these
deposits is minor
To illustrate the local geological features a series of geologic cross-sections have been prepared
At several locations lithologic data from pre-RI wells (both on-site and off-site) were
incorporated for additional detail The boring logs from which the cross sections were prepared
are included in Appendix C
As shown in cross-sections A-A B-B C-C D-D E-E and F-F (Plates 3-2 through 3-5) till
was encountered just above the bedrock surface at nearly every location The till horizon ranges
in thickness from approximately 10 to 20 feet with the thickest accumulations located along the
centrally located topographic high Surficial exposures of glacial till were observed within the
central portion of the Site as seen in cross sections A-A and C-C The till observed within the
Study Area is comprised of a fine sandy matrix containing abundant gravel cobbles and
boulders The till deposits seen in the topographically higher areas (ie elevations greater than
approximately 160 feet) were for the most part unsaturated Although reference literature for
this area (USGS 1995) describe the possible presence of two different till horizons no apparent
differentiation was observed at the site
As seen in the boring log from MW111 deposits of till are exposed at the ground surface and in
the central area of the Site However as shown on cross sections A-A and C-C (Plate 3-2) and
D-D (Plate 3-3) the bedrock surface drops off rapidly in southerly westerly and northerly
directions where relatively thick accumulations of stratified drift have been deposited over the till
5797wpdocsgalluprifinlaquoltextmalaquotemfhl061297 3-5 QFT Environmental
Gallups Quarry Superftind Project - Remedial Investigation
Within 500 feet of the central portion of the Site the overall thickness of the stratified drift
deposits increase to nearly 70 feet In the vicinity of MW113 (west of the central portion of the
Site) the lower portion of the stratified drift is comprised of approximately 30 feet of very fine to
medium-grained sand with occasional thin layers of silt This deposit appears to increase in
thickness towards the west while it thins towards the central portion of the Site where it pinches
out against the till Overlying these fine-grained deposits are approximately 30 feet of poorly
structured sand and gravel which includes abundant cobble sized material The coarser upper
stratified drift material also thins eastward towards the Site where it is in contact with the till
The coarse upper material is generally unsaturated with the groundwater table occurring at the
approximate upper surface of the fine sand
The southern portion of the Study Area is shown on cross sections A-A (Plate 3-2) and D-D
(Plate 3-3) As indicated on the southern end of cross section A-A approximately 35 feet of
stratified drift overlies the till in the vicinity of MW112 Although much of the stratified drift at
MW112 is relatively coarse an approximately 12 foot thick layer of fine-grained sand and silt is
present from about eight to twenty feet below the ground surface From MW112 the thickness of
the stratified drift thins to the north where it contacts the central topographic high
From the southeastern corner of the Site near MW112 the bedrock surface slopes downward
towards the west-southwest to a depth of approximately 75 feet below the ground surface (as seen
at location MW115 on the southern end of cross section D-D[Plate 3-3]) At MW115
approximately 65 feet of stratified drift (comprised of a sandy matrix containing a significant
amount of coarser gravel and cobbles) overlies approximately 10 feet of till
As seen in cross section B-B (shown on Plate 3-4) and A-A (Plate 3-2) the northeastern portion
of the Site (in the vicinity of the Former Primary Disposal Area) is comprised of fairly well
sorted fine- to medium-grained sand with occasional thin lenses of very fine sand and silt The
lenses of finer-grained materials appear only locally in the vicinity of MW107 and MW108 at a
depth of about 25 feet and are typically only a few inches to a few feet in thickness with limited
lateral extent Beneath the fine-grained sand and silt and directly overlying the till is 10 to 20
feet of coarser-grained sand and gravel Moving westward along cross section B-B in the
vicinity of MW105 the fine-grained sand thins and grades into coarser sand and gravel deposits
The coarse sand and gravel deposits directly overlie the till and thicken to nearly 50 feet towards
the west in response to the downward slope of the bedrock surface This portion of the Study
Area which is northwest (and downgradient) of the Former Primary and Secondary Disposal
Areas is overlain by a thin veneer of recent alluvial and swamp deposits associated with the
present Mill Brook channel and floodplain As shown on the cross section (B-B) the stratified
drift deposits in this area are very nearly saturated throughout their entire thickness
5797wpdoc8galluprifinaltextmasterrifiiiy061297 3-6 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
North of the Former Primary Disposal Area (along the northern end of cross section D-D) the
bedrock surface continues to gradually slope downward (to the north) until the approximate
location of MW116 North of MW116 the bedrock surface is interpreted as appearing to rise
based on the depth to till deposits encountered beneath MW119 Stratified drift deposits
immediately north of the Former Primary Disposal Area in the vicinity of MW116 are dominated
by approximately 25 feet of fine grained sand and silt Further north along section D-D the
finer sand and silt deposits thin and are overlain by coarser grained sand and gravels Relatively
thin post-glacial stream alluvium and modern swamp deposits associated with Mill Brook are also
seen in the vicinity of MW116 and MW119 A roughly east-west cross section (E-E [Plate 3-5])
has been prepared to illustrate the lithologic features in the area north-northwest of the former
disposal areas This cross section starts at MW119 (described above) and runs west to MW101
in a line approximately parallel to Mill Brook The fine sandsilt deposit seen in the vicinity of
MW119 is also observed to the west at MW117 at the same approximate thickness and elevation
Westward from MW117 the fine sandsilt deposit grades into the more prevalent coarse sand and
gravel deposits observed at MW118 and MW101 The northernmost cross section (F-F [Plate 3shy
5]) extends westward from MW3 (located just east of the former Pervel flock plant) to PZ301
As shown on F-F this portion of the Study Area is dominated by collapsed coarse sand and
gravel deposits at least to the completion depths of the borings (MW3 MWC and PZ301) along
the line
323 Regional Bedrock Geology
Bedrock in the vicinity of the Site is mapped as a lower member of the Quinebaug Formation
which is composed of metasedimentary and metavolcanic rocks of Paleozoic age The Quinebaug
Formation is part of the Putnam Group and exhibits a sillimanite grade of metamorphism The
bedrock consists of primarily light to dark grey fine- to medium-grained hornblende gneiss biotite gneiss and amphibolite Bedrock in the area is strongly faulted and folded and exhibits
varying degrees of mylonitization A major fault zone known as the Lake Char fault is located
approximately 03 miles east of the Site The Lake Char fault is a north-south trending fault
which offsets rock units of the Putnam Group and the Hope Valley Alaskite Gneiss formation A
northwest-trending fault is shown on the USGS Bedrock Geologic Map (Dixon 1965) of the
Plainfield Quadrangle in the vicinity of the Former Seepage Bed The existence and approximate
location of the suspected fault was based on aeromagnetic data published in 1965 (Boynton amp
Smith 1965) Bedrock located north of the inferred fault is mapped as more intensely
metamorphosed cataclasites and blastomylonites The fault is mapped as extending into the Tatnic
Hill formation to the west but is not mapped within the Hope Valley Alaskite Gneiss formation
which is located to the east
5797wpdoc8galluprifinaltextmasterrifhl061297 3-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
324 Local Bedrock Geology
Confirmed depns to bedrock were determined based on the elevations of bedrock outcrops and
the collection of bedrock cores at nine boring locations (MW102B MW105B MW107B
MW108B MW109B MW111B MW112B MW113B and MW115B) Inferred depths to
bedrock were made at seven additional locations (MW101 MW102 MW103 MW104 MW114
MW116 MW117 MW118 and MW119) based on boring data obtained during the drilling of the
deepest wells at each cluster (which indicates the minimum depth to bedrock) and based on trends
seen at the confirmed depth locations Based on this evidence it is likely that unconfirmed depths
to bedrock are accurate to within several feet of the actual depths At MW110S no attempt was
made to advance the boring more than about 12 feet below the ground surface (the depth needed
for the required shallow well at that location) Depths to bedrock ranged from approximately 13
feet at MW111B to 83 feet at MW113B Drilling difficulties associated with the presence of
boulders just below the ground surface at MW11 IB made it difficult to determine the exact depth that bedrock was first encountered at this location Suspected boulders were encountered starting
at approximately six feet below the ground surface and casing was driven to a refusal depth of
approximately 15 feet before bedrock coring began
Based on the data described above a bedrock surface contour map is shown on Plate 3-6
Bedrock elevations are highest in the eastern central portion of the Study Area and decrease to the
north and west and to a lesser degree to the south
Within the Study Area bedrock consists of grey fine- to medium-grained gneiss with varying
contents of amphibolite biotite and hornblende Various degrees of weathering and competency
were also observed Detailed rock core descriptions are presented on the rock coring logs
provided in Appendix C
The primary objective of the seismic refraction survey (discussed in Section 234) was to
identify if present the location of a possible bedrock fault suspected to exist hi the vicinity of the
Former Seepage Bed As discussed in Section 323 the approximate location of the suspected
fault was estimated from the regional USGS Bedrock Geologic Map based on an aeromagnetic
survey conducted in 1965 Ground penetrating radar surveys conducted by the USGS (1995)
identified a northward dipping subsurface reflector beneath the central portion of the Site This
reflector was interpreted as a potential bedrock fault feature The relatively high strength of the
reflector was attributed to fault gouge (or other infilling) material or possibly sorbed inorganic
compounds No subsurface explorations were conducted at the time of the USGS investigation to
confirm the nature of the radar reflector
5797wpdocsgalluprifinaltextmiiraquoterrifnl061297 3-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Evaluation of data obtained from the seismic refraction survey indicates the presence of possible
bedrock fractures on seismic lines 3 through 6 (Plate 3-7) In addition to these interpreted
fracture zones the overall relatively low seismic velocities (12000 ftsec vs 15000 to 18000
ftsec for intact crystalline rock) indicate that in general the rock is somewhat fractured
Although the original intent of the magnetometer (MAG) survey was not to interpret bedrock
features data obtained during the MAG survey (which covered a much larger area) indicate the
presence of several linear-shaped sharp magnetic gradients bounding a zone with a different
magnetic signature The change in magnetic signature was interpreted as potentially associated
with changes in bedrock lithology and fracturing across a broad faultfracture zone in the central
portion of the Site These interpretations are described in further detail in the Weston
Geophysical Report included as Appendix A The locations of the magnetically determined
bedrock features are also shown on Plate 3-7 While the seismically interpreted fractures do not
strongly coincide with linear features seen in the MAG data they do lie within the magnetically
determined fractured zone
The geophysical data described above as well as the rock-core retrieved from MW111B further suggest that bedrock beneath the central portion of the Site may be more accurately characterized
as a series of fractures and faults rather than an area of competent bedrock with one or two
discrete faults
33 Hydrogeology The following sections discuss data collection and evaluation results relative to groundwater flow
directions and rates in overburden deposits and the upper portion of the bedrock unit
331 Hydraulic Conductivity The hydraulic conductivity distributions within the overburden and bedrock formations were
evaluated through the performance of rising and falling head slug tests constant flow tests and
by empirical correlations with measured soil grain size distributions The slug test methodology
and data analysis methods are discussed in Appendix F Because the falling head test results for
shallow wells were influenced to some degree by soil above the water table only rising head test
data were used for the water table wells to compute mean values The constant flow test
methodology is described in Section 283 and Appendix F Table 3-1 summarizes the measured
hydraulic conductivity values from the slug and constant flow tests for wells grouped together
based on lithology and screen depth as follows shallow top-of-till till and bedrock Hydraulic
conductivity estimates based on grain size are listed in Table 3-2 for comparison but only
constant flow and slug-test data were used to calculate mean hydraulic conductivity values for
different portions of the aquifer Laboratory grain size data are presented in Appendix G
5797wpdocraquogalluprifinlaquoltextmastem fill061297 3-9 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
The top-of-till wells are considered to be the most representative of the more permeable section of X^^JF
the overburden aquifer characterized by coarser soil grain sizes where a large percentage of the
total groundwater flow occurs Across the Study Area the mean hydraulic conductivity for the
top-of-till wells is 0005 centimeters per second (cms) with values ranging from 0000053 cms
to 0074 cms Northwest of the railroad tracks in the northern portion of the Study Area where
the aquifer thickens the mean hydraulic conductivity for top-of-till wells (MW102TT
MW103TT MW104TT MW117TT and MW118TT) is 0037 cms This value of 0037 cms
which is approximately an order of magnitude larger than the overall Study Area mean for top-ofshy
till wells appears to be most representative of the hydraulic conductivity within the major portion
of the VOC plume By comparison the grain size results are similar in magnitude but somewhat
lower than the Study Area average for the constant-flow and slug tests because they indicate an
average hydraulic conductivity of 0003 cms for the coarse stratified drift samples with values
ranging from 00006 cms to 0006 cms The mean hydraulic conductivity for shallow wells
which are generally screened in finer-grained soils is 0001 cms and varies between 000006
cms and 002 cms The shallow well constant-flow and slug test results are comparable to the
mean grain-size correlation value of 0002 cms for fine stratified drift soil samples
The mean hydraulic conductivity for the till wells (000047 cms) is approximately a factor of ten
less than the mean Study Area top-of-till value and varies between 00002 cms and 0002 cms
The till appears to be hydrogeologically different from the other overburden deposits and on the
average provides increased resistance to groundwater flow This added resistance is not
considered to be significant however because the consistency of the till is highly variable and the
hydraulic conductivity contrast is relatively small
The slug test results for the bedrock wells yield the lowest average hydraulic conductivity
000018 cms The bedrock results though should be considered less accurate than the
overburden estimates due to the highly variable nature of the fractures in the rock matrix and their
associated non-linear effect on computed hydraulic conductivity
332 Groundwater Flow
3321 Surficial (Overburden) Groundwater Flow
The following discussion on overburden groundwater flow is organized according to relative
locations within the Study Area All references to flow direction are inferred based on measured
hydraulic gradients The central portion of the Site in the vicinity of the Former Seepage Bed is
dominated by the presence of a bedrock-controlled topographic high which for the most part is
overlain by unsaturated till Because of this feature overburden groundwater flow patterns can be
effectively treated as separate entities those located to the north of the hill and those located to
the south
5797wpdocraquoglaquolluprifinlaquoltextmasterrifhl061297 3-10 QampT Environmental
Gallups Quarry Superand Project - Remedial Investigation
Table 3-3 summarizes the water level data collected from monitoring wells and piezometers
during the quarterly monitoring rounds Plates 3-8 and 3-9 depict deep and shallow piezometric head distributions respectively (for November 6 1995) throughout the northern Study Area
Plate 3-9 also shows the piezometric head distribution in the southern Study Area Groundwater
flow maps for other dates are presented in the ISCR (ESE 1995) Water level data for the
monitoring wells at the former Pervel facility were used in both the shallow and deep flow maps
because they are screened in the middle portion of the aquifer As a result these wells are
considered to be hydraulically representative of both portions of the aquifer A saturated
thickness map (Plate 3-10) was created by subtracting the interpolated bedrock surface (Plate 3-6)
from the shallow overburden piezometric surface measured on November 6 1995 which is approximately equal to the groundwater table configuration To facilitate interpretation of flow
patterns calculated two-dimensional groundwater pathlines which represent the mean horizontal trajectory of a parcel of groundwater in the overburden aquifer originating from several locations
in the Study Area are also shown however the pathlines do not account for vertical flow within the aquifer which is important in the shallow portion of the aquifer Data interpolation by the
method of kriging piezometric head contour development and numerical computation of pathlines were performed using the data analysis and visualization software package Tecplot
(Amtec Engineering 1994) The pathlines are based on a steady state velocity field computed
directly from the interpolated head distribution using Darcys law and assume homogeneous
isotropic conditions
Southern Study Area
Overburden groundwater flow south of the Former Seepage Bed is primarily influenced by two factors (1) the slope of the bedrock surface which defines the base of the unconsolidated deposits and (2) regional hydrologic drainage patterns The west-southwest dip of the bedrock
surface strongly influences the general east to west flow of groundwater The average east-west
horizontal hydraulic gradient in the southern portion of the Study Area is approximately 001 feet per foot (feet of vertical head change per foot of horizontal distance)near well MW112S and
piezometer PZ-202 whereas the typical bedrock surface slope in this area is about 01 feet per
foot The configuration of the bedrock surface is important because the slope of the groundwater
table in the overburden would tend to equal the slope of the underlying bedrock in cases where
the saturated thickness is relatively small and the slope is large This process is analogous to flow
in a river where the water surface profile tends to reflect the slope of the river bed under steady-
state conditions In the southern Study Area the water table slope (ie horizontal hydraulic
gradient) is steep but less than the dip of the bedrock surface because the saturated thickness of
the overburden aquifer increases in the direction of flow The saturated thickness increase also
5797wpdocsglaquolluprifinlaquoltextmlaquogterrifiil061297 3-11 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
increases the transmissivity of the aquifer (and decreases the resistance to flow) thus causing the
horizontal hydtaulic gradient in the overburden to be less than the bedrock slope The
overburden becomes unsaturated north of PZ203 due to the continued increase of the bedrock
surface elevation in the direction of the Former Seepage Bed The wetlands and stream located a
few hundred feet west of the railroad tracks also affect flow directions and rates because they act
as discharge points for groundwater
Northern Study Area
Due to the increased saturated thickness north-northwest of the Former Primary Disposal Area
groundwater flow conditions in both shallow and deep sections of the aquifer are discussed The
top-of-till wells are considered to be most representative of horizontal flow conditions in all but
the shallow portion of the aquifer Primary reasons for the differences between shallow and deep
flow conditions include (1) the deep aquifer hydraulic conductivity northwest of the railroad
tracks is a factor of about 40 greater than the shallow hydraulic conductivity resulting in the
lower to middle portions of the aquifer controlling regional groundwater movement and (2)
rainwater infiltration and hydraulic influences of Mill Brook cause vertical flow to be important in
certain areas of the shallow aquifer The focus of this section is horizontal groundwater flow in
the middle to lower sections of the aquifer as characterized by Plate 3-8 Shallow flow
conditions (Plate 3-9) are discussed in Section 3323
In the northern portion of the Study Area three hydrogeologically distinct zones exist Between
the Former Primary Disposal Area and the Former Seepage Bed the hydraulic gradient is steep
(approximately 003 feet per foot between wells MW109S and MW110S) and is strongly
influenced by the dip of the bedrock surface (01 feet per foot) As shown on the insert on Plate
3-10 the saturated overburden thickness increases from zero south of well MW109 to about 20 to
30 feet near the former disposal areas North-northwest of the Former Primary Disposal Area the
hydraulic gradient lessens significantly to a range of 00003 to 00007 feet per foot between wells
MW105TT and MW102TT representing a factor of 40 to 100 reduction The most important
factors which produce the flatter gradients in this area are the more than order-of-magnitude
increase in hydraulic conductivity of the coarser-grained deposits and the substantial increase in
the saturated overburden thickness northwest of the railroad tracks North-northeast of Mill
Brook the hydraulic gradient is about 0007 feet per foot near wells MW117TT and MW118TT
Northwest of the railroad tracks groundwater flow in the middle to lower portions of the aquifer
converges from the northeast and southwest toward a centerline area generally defined in the
downgradient direction by wells MW105 and MW102 The flow direction near these wells is
generally to the northwest Northeast of this centerline groundwater flows in a southwesterly
5797wpdocsgalluprifinaltextmasterrifhl061297 3-12 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
^ ^ direction from the vicinity of Mill Brook and the former Pervel flock plant North of Mill Brook
and west of the railroad tracks the predominant groundwater flow direction becomes more
westerly As discussed in Section 42 and 52 these flow directions are very consistent with the
observed groundwater contaminant distribution
No significant seasonal changes in horizontal groundwater flow directions were observed in the
Study Area Figures 3-1 to 3-20 are groundwater elevation hydrographs for each well cluster in
the Study Area representing the period January 1995 to May 1997 (except for wells MW117
MW118 and MW119 which were not installed until November 1995) Groundwater levels were
high in January 1995 May 1996 and February 1997 and decreased by about two feet during July
1995 and August 1996 This variation is consistent with the fact that recharge rates become very
small during the summer months
3322 Bedrock Groundwater Flow
Groundwater flow within fractures in the top ten to 20 feet of the bedrock unit was evaluated
through the performance of the hydraulic conductivity (slug) tests and water level measurements
in monitoring wells A bedrock piezometric head map based on November 6 1995 water levels
is shown on Plate 3-11 along with inferred groundwater pathlines For the pathline development
it was assumed that the hydraulic conductivity distribution is isotropic because potential
influences of fracture orientation on flow direction have not been quantified As expected the
direction of the dip of the bedrock surface has a major influence on the horizontal hydraulic
gradient and flow direction However vertical flow from bedrock to overburden is also
important as discussed in Section 3323
South of the Former Seepage Bed groundwater in bedrock moves primarily in a westerly
direction while in the northern Study Area the predominant flow component is toward the
northwest In both areas the horizontal hydraulic gradient is on the order of 002 feet per foot
The steepest gradients (003 feet per foot) are found in the vicinity of the Former Seepage Bed
and the local high in the bedrock surface just east of MW111 The horizontal hydraulic gradient
reduces to about 001 feet per foot in the southern portion of the Study Area (near wells MW115
MW114 and MW112) and north-northwest of the former disposal areas Groundwater flow in
bedrock near the Former Seepage Bed is toward the northwest in the direction of wells MW113
and MW106 and exhibits no apparent influence from the locally increased fracturing identified
from the geophysical investigation and the hydraulic testing in well MW111B
5797wpdocsgalluprifinaltextm8tem fhl061297 3-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
3323 Vertical Flow
BedrockDeep Overburden Interface
Vertical groundwater flow is an important component in the upper several feet of the bedrock
unit This observation is supported by the water level hydrographs (Figure 3-1 to 3-20) and data
presented in Table 3-4 which summarizes the vertical hydraulic gradients between pairs of
monitoring wells in various well clusters across the Study Area Data characterizing the hydraulic
interaction between the bedrock and the lower portion of the overburden were evaluated for the
following well pairs MW102B-MW102TT MW105B - MW105T MW107B - MW107T
MW108B - MW108TT MW109B - MW109S MW112B - MW112T MW113B - MW113S and
MW1 15B - MW1 15TT For all measurement dates groundwater was found to be discharging
from bedrock into overburden at each location except for the January 1995 and February and May
1996 measurements at location MW109 At MW109 the saturated overburden thickness is less
than a few feet and MW109 is located at a much higher bedrock elevation relative to all other
locations at which upward vertical flow from bedrock was measured The vertical hydraulic
gradients between bedrock and top-of-till wells are generally more than a factor of ten greater
than the horizontal hydraulic gradients within the VOC plume downgradient from the Former
Primary Disposal Area
Overburden
In the overburden aquifer the vertical flow component is significant within shallow deposits in ~
the vicinity of the Former Primary Disposal Area and within the streambed sediments and the
upper portion of the aquifer near Mill Brook Plan view and cross-section maps were developed
to illustrate vertical piezometric head differences Plate 3-12 shows the November 6 1995
vertical piezometric head distribution and general groundwater flow directions along geologic
cross-section B-B Plate 3-13 is a plan view contour map of the shallow minus deep piezometric
head difference in the overburden aquifer As shown by the water level hydrographs the vertical
hydraulic gradients in the aquifer are relatively consistent throughout the observation period
Consistent downward hydraulic gradients have been observed at well clusters MW107 MW108
and MW116 Near the Former Primary Disposal Area water levels in MW107S were two to
three feet higher than the level in MW107TT resulting in a downward vertical hydraulic gradient
that is about a factor of 100 greater than the horizontal gradient from MW107TT to MW105TT
In addition shallow piezometric heads near MW108 and MW1 16 have ranged from 05 to 15
feet higher than heads in the lower portion of the aquifer This downward component at MW107
likely results from the low hydraulic conductivity of shallow soils near the well screen of
MW107S (factor of 200 less than underlying deposits refer to MW107S and MW107TT data in
Table 3-1) and drainage of surface water runoff from upslope areas into the depression formed by
excavation of the Former Primary Disposal Area The low hydraulic conductivity test result for
5797wpdocsgalluprifinlaquoltextmasteiTifhl06 1297 3-14 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW107S and the observed downward hydraulic gradient may be related to the increased silt
content of soils near well MW107S The vertical VOC distribution at location MW107 (shown
on Plate 3-12 and discussed in Section 4) also strongly supports a predominantly vertical
groundwater flow direction in the upper portion of the aquifer because only trace levels of VOC
were detected in MW107S The downward hydraulic gradients in the vicinity of wells MW108
and MW116 (Plate 3-13) also appear to be associated with the higher hydraulic conductivity of
deep deposits compared to shallow soils (Section 331) and groundwater recharge
West of the railroad tracks near well clusters MW102 MW101 and MW118 the measured flow
direction in the aquifer is predominantly horizontal based on the negligible vertical hydraulic
gradient between shallow and top-of-till wells at these locations However in the immediate
vicinity of Mill Brook vertical groundwater flow is important within the upper several feet of the
aquifer In the vicinity of wells MW103 MW117 and MW119 shallow piezometric heads are
generally 03 to one foot lower than deep heads Using a representative aquifer thickness of 50
feet the average upward vertical hydraulic gradient in this area is about 001 feet per foot by
comparison the local horizontal hydraulic gradient is approximately 0007 feet per foot Based
on these data a significant fraction of the shallow aquifer near wells MW103 MW117 and
MW119 may be discharging into Mill Brook Within the lower portion of the aquifer the
vertical hydraulic gradient becomes very small in magnitude
To further evaluate the hydraulic influence of Mill Brook on the overburden aquifer a vertical
two-dimensional numerical groundwater flow model was developed and a sensitivity analysis was
performed (Appendix U) The results of the modeling indicate that vertical flow in the upper
portion of the stratified drift aquifer near Mill Brook is more important west of the railroad tracks
(eg near wells MW101 and MW102) than east of the tracks (eg near well MW119) This
difference is due to the much smaller horizontal hydraulic gradients (on the order of 00003 feet
per foot) that are present west of the railroad tracks compared to ths area north of Mill Brook and
east of the railroad (horizontal gradients approximately 0007 feet per foot) Because the mean
water level in the brook is lower than the groundwater table elevation vertical flow is created in
the upper portion of the stratified drift aquifer and the depth to which this vertical flow is
important is greater in areas where the horizontal hydraulic gradient (and groundwater velocity is
less) In the vicinity of wells MW101 and MW102 the groundwater flow simulations indicate that
as much as one-third to one-half of the stratified drift aquifer may discharge into Mill Brook
East of the railroad tracks no greater than ten to 25 percent of the groundwater flow in the
stratified drift aquifer is estimated to discharge into the brook
East of the railroad tracks and south of Mill Brook a consistent downward groundwater flow component is observed in addition to the regional horizontal flow component As discussed
5797wpdocraquograquolluprifinaltextmaBterrifhl061297 3-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
above this downward component is largest near the Former Primary Disposal Area A small
downward flow component was also observed in the vicinity of wells MW106 and MW104
Figure 3-21 is a three-dimensional perspective drawing of groundwater movement in the
overburden aquifer which was developed to further illustrate the relative importance of the
horizontal and vertical flow components in the vicinity of the Former Primary Disposal Area
The figure consists of the two sets of piezometric head contours representing shallow and deep
(top-of-till) water level measurements recorded on February 2 1995 The lower piezometric
surface is representative of flow conditions throughout the middle to lower portions of the aquifer
The upper surface represents the piezometric head variation near the water table Presented
together in the same figure these two sets of contours allow an interpretation of the predominant
(but not all) three-dimensional pathlines originating in the vicinity of the Former Primary Disposal
Area As the pathlines illustrate shallow groundwater near these locations is expected to move
predominantly downward in the upper portion of the aquifer (although some local horizontal flow
may occur due to variations in the hydraulic conductivity of aquifer material) due to the large
vertical hydraulic gradients and the small aquifer thickness
Once groundwater has passed through the less permeable shallow soils it moves in a
predominantly horizontal direction dictated by the piezometric head distribution in the lower
portion of the aquifer
Based on the stream piezometer data presented in Table 3-5 Mill Brook generally gains water
from the overburden aquifer in the northern portion of the Study Area For most dates stream
bed flow was upward at piezometers PZ-6 PZ-5 PZ-4 PZ-4A and PZ-4B located west of the
railroad tracks and at piezometers PZ-1 and PZ-2 located east of the railroad tracks The
streambed vertical flow direction at piezometer PZ-3 located immediately upstream from a beaver
dam and possibly influenced by backwater effects was variable These data are consistent with
the shallow groundwater flow conditions depicted in Plate 3-9 where the head contours passing
through Mill Brook are bent (or V) in an upstream direction This piezometric head contour
pattern is representative of a gaining stream
Any groundwater discharge from the aquifer into Mill Brook would be significantly diluted by
flow in the brook A rough estimate of the potential surface water dilution rate can be obtained
by comparing the stream flow rate with the total discharge rate of groundwater through a given
vertical cross-sectional area For example using an upper bound hydraulic conductivity estimate
of 100 feet per day (0035 cms) a horizontal hydraulic gradient of 0001 feet per foot and an
area 200 feet wide (plume width) by 20 feet deep (about one-third of the aquifer thickness) a
conservatively high estimate of potential discharge from the contaminated portion of the aquifer
5797wpdocraquogalluprifinaltextmasterrifhl061297 3-16 Q^T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
into Mill Brook is approximately 0005 cubic feet per second or cfs (21 gpm) Based on a
measured stream flow rate of about 30 cfs at station UB10 the concentrations of dissolved
constituents in groundwater would be reduced by a factor of about 6000 upon mixing with the
entire stream flow
34 Ecology An ecological study was performed primarily to delineate wetlands and to make local observations
of the types and abundance of plants and animals in the area
341 Wetland Delineation
Delineation of wetlands within the Study Area and adjacent lands was conducted during the period
of August 26 to September 1 1994 Team members included two ESE wetlands biologists and a
certified soil scientist affiliated with the Soil Science Society of Southern New England As
discussed in Section 2131 the delineation performed to meet the States criteria focused on soil
types and hydric soil characteristics while the delineation performed to meet the Federal criteria
used USACOE methods which include the examination of vegetation hydrology and soils
As shown on Plate 3-14 wetlands were identified and delineated along the northern and western
portions of the Study Area Areas bordering the Site to the south and east reflect upland
conditions
Wetland delineation efforts were initiated along the face of a steep gradient along the southwestern
portion of the study area (west of the railroad grade) This allowed the field team to observe the
most obvious characteristics of both upland and wetland regimes Areas reflecting more subtle
wetlandupland indicators were investigated after having gained local experience with the obvious features
The wetland bordering the southwestern portion of the study area is a white cedar swamp
(unnamed) supporting a varying density of trees The swamp is hydraulically connected to the
Mill Brook system by a narrow stream The stream limits surface water flow causing the swamp
to maintain a long hydro period (duration of inundation or saturation) even though it is
topographically higher than the receiving floodplain It appears that the swamp remains inundated
during most years with the possible exception of drought years Judging from the high hydraulic
conductivity of the surrounding soils the swamp receives water through seepage from
surrounding uplands and to a lesser degree from surface water runoff
Portions of the swamp support a low density of older cedars while other areas support denser
stands of young cedars It appeared that the older age class occurred in deeper water while the
5797wpdocsgalluprifinraquoltextmasterrifhl061297 3-17 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
younger stands favored shallower water White cedar trees are not tolerant of fire events and it is r
likely that this age class distribution reflects a fire-maintained system where the deeper portions of
the swamp have been more effective in excluding natural fires hence supporting the oldest
cedars Additional hydrophytic plant species identified within the transition zone include red
maple common reed duckweed jewelweed cattail and coast pepper-bush
The upland system bordering the cedar swamp and floodplain forest supports a sub-climax to near
climax hardwood forest Topography of the upland includes steep slopes to gently undulating
land Canopy vegetation (trees) are dominated by oak species (red white and chestnut) with
white oaks nearer the wetland transition area and red and chestnut occurring on the higher
portions of the uplands Other canopy species included white ash quaking aspen hickories and
dogwoods Common understory vegetation included sheep laurel black cherry and green briar
Herbaceous vegetation included species found in the under story and canopy in addition to hay-
scented fern among others
Northward of the stream feature draining the cedar swamp lies the broad floodplain of Mill Brook which closely coincides with the northern boundary of the Site The floodplain is generally flat with many small raised hummocks This area reflects more seasonal fluctuations in hydro period and shallower water depths than the cedar swamp a result of more efficient drainage of the system For this reason natural succession is more advanced and the system supports a higher _ Jgth
diversity of hardwood canopy under story and herbaceous species composition
With the exception of two small isolated topographic depressions (excavated pits) located just west of the southern portion of the Site the delineated wetland areas correspond with the edge of the Mill Brook floodplain Most of the wetlandupland boundary occurs along the edge of a steep grade which closely coincides with the 150-foot ground elevation contour interval The sharp relief produces a narrow transition zone between upland and wetland communities The delineated lines reflect this as the State and USACOE wetland boundaries coincide at nearly
every location The State and USACOE lines are different in a small area adjacent to the railroad tracks immediately north of the Site In this area the State line is upgradient of the USACOE line The soils above the floodplain do not exhibit hydric soil characteristics as defined in the federal manual used for delineating wetlands The soil appears well-drained and depth to water is at a lower elevation than the floodplain soil just a few feet away The soil resembles the description of Suncook an excessively drained soil commonly mapped with Rippowam soils Both Rippowam and Suncook soils are listed on the State hydric soils list while Suncook is not listed by SCS as a hydric soil
5797wpdocsgalluprifinaltextmasterrifhl061297 3-18 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
A relatively small area of wetlands were determined to occur within the boundaries of the Site proper Wetlands occur in the area northeast (upgradient) of the Former Primary and Secondary
Disposal Areas and along the northern border of the Site east of the railroad bed The two topographic depressions corresponding to the former disposal areas (primary and secondary) lack
hydrophytic vegetation and hydric soil characteristics Other excavated areas to the south and
southwest (on-site) support hydrophytic vegetation and meet hydrology criteria but lack hydric
soil characteristics The depression to the southwest bordering the railroad supports hydrophytic vegetation and is occasionally inundated with surface water (following significant precipitation
events) but lacks hydric soil indicators In this area the ponded water was judged to be the
result of a confining layer of residual tar (presumed to be associated with former CTDOT asphalt
plant operations) immediately beneath an organic layer which causes precipitation to accumulate
342 Plant and Animal Survey
Site Characterization
An objective investigation of native plant and animal species and their habitat was conducted by US Fish and Wildlife Service (USFWS) staff in summer of 1993 (Prior et al 1995) Their
examination included a Site walkover observation and mapping of vegetation cover (shrubs
trees hydrophytic plants) and observation of direct or indirect evidence of wildlife (birds mammals amphibians) Although the Site proper is characterized as highly disturbed no
conclusions were drawn with regard to the effects of past human disturbance on the local ecology
The large majority of plant and animal species observed in the study are native to the region and
commonly found in other disturbed communities andor wetland environs
Reconnaissance of the study Site and adjacent lands was performed prior to delineation activities
to identify habitat types terrain physical access and develop logistics for completing the wetland
delineation The study area is a peninsular feature which extends northward and westward from
the Site entrance at Tarbox Road The study area is bisected diagonally by the railroad right-ofshy
way The Gallup Quarry Site (the quarry) lies to the east of the railroad divide and the remainder
of the study area (the west end) lies to the west Portions of the east boundary of the quarry abut
State Route 12 with other areas bounded by private property
The boundaries of the peninsula are characterized generally by steep slopes which are met
immediately by wetlands The upland soils are glacial till with some areas composed mostly of sands with coarse gravel occurring with lower frequency Some of the higher and relatively
undisturbed areas are composed of large rocks protruding to the ground surface Soils in the
transition zones between upland and wetland are composed of organic muck overlying sand
5797wpdoc8gilluprifinaltextmalaquoterriftil061297 3-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
These natural conditions along with historical use of portions of the area (mining and
manufacturing) cre responsible for the character of the plant communities found throughout the
study area The quarry reflects significant disturbance from historical mining and asphalt
operations The Site has numerous excavated depressional areas and areas of mounded earth
material These features significantly distinguish the quarried area from the area off-site to the
west which is undeveloped and relatively undisturbed The assemblage of plants in the quarry
reflects these conditions many of the excavated zones are devoid of vegetation and areas adjacent
to them support a mix of successional pioneer species Density of vegetation ranges from bare
soil to dense brush and sapling sized trees Areas of highest vegetation density are associated
with both low elevation (greatest soil moisture regime) and age (length of time since disturbance)
Trees throughout the quarry are young and small in comparison with those found in the forested
areas west of the railroad Vegetation on-site is characterized as early successional species The
more common species include black willow northern bayberry eastern cotton-wood quaking
aspen goldenrod and black cherry
Few wildlife species were observed or noted during wetland delineation activities Wildlife
activity within the Study Area was limited during the survey period but should be expected to
support a much greater diversity of wildlife during the spring and summer seasons when birds
(especially migratory) conduct nesting and rearing activities Most of the species observed during
the survey are expected to overwinter at the study area Bird species recorded include mourning
dove eastern peewee tufted titmouse black-capped chickadee blue jay white-breasted nuthatch
gray catbird American robin and northern cardinal
Vegetation species were recorded during the wetland delineation and are presented in Table 3-6
These reflect species occurring within wetland transition zones Additional species are expected
to occur in more xeric uplands and deeper wetlands
Although no qualitative samples of freshwater macroinvertebrates were obtained the distribution
of different genera between stations would appear to be strongly influenced by the variable
substrate composition and habitat which ranges from shaded moderate flowing rocky stream bed
(eg UB1 UB9) to sunny low energy depositional areas containing sand or deep muck (eg
UBS LB2)
5797wpdocsgalluprifinaltextmasterrifnl061297 3-20 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
40 Nature and Extent of Contamination
This section discusses the distribution of contaminants within the various media throughout the
Study Area and is based on analytical data collected during nine separate sampling events These nine sampling events include the Phase 1A investigation the Phase IB investigation and the Long-
Term Monitoring Program events conducted during April July November 1995 February May
August and November 1996 and February 1997) The results of the Phase 1A investigation
Phase IB investigation and the Long-Term Monitoring Program sampling events (except
November 1995 which was conducted concurrently with the Phase IB investigation) were also
presented in earlier reports (ESE 1995 -1995b -1995c 1996a 1996b 1996c 1997a 1997b)
Section 41 addresses the results of investigations into potential source areas including surface and subsurface soil Section 42 addresses the results of groundwater investigations Section 43
presents the results of investigations of surface water sediments and wetland soils Section 44 addresses the results of air monitoring investigations Section 45 identifies potential sensitive
human receptors within a one mile radius of the Site
Sample analyses were performed pursuant to the Gallups Quarry Superfund Project RIFS Quality Assurance Project Plan dated August 29 1994 Laboratory analytical testing for Level 4
was generally conducted for analytes identified in the Contract Laboratory Program (CLP) target
compound list (TCL) for organics and target analyte list (TAL) for inorganics Analyses were
conducted pursuant to the CLP Statement of Work for Organics MultimediaMulticoncentrations
Document OLM 018 and the CLP Statement of Work for Inorganics
MultimediaMulticoncentrations Document ILM 030 Appendix IX analyses were conducted by
CLP and SW-846 Methods as described in the QAPP Low-level VOC in drinking water were analyzed by EPA Method 5242 with CLP SOW reporting Laboratory reports for the Phase 1A
Phase IB and Long-Term Monitoring Program sampling events are presented in Appendices H
through P Laboratory data for sample splits collected by EPAs oversight contractor during the
Phase 1A July 1995 and Phase IBNovember 1995 sampling events are also presented in
Appendices H J and K respectively The results of detected analytes are summarized in Section 4 tables The definitions of the qualifiers used for the laboratory data precede the tables in
Section 4 As discussed in various sections analyte concentrations are given either as milligramskilogram (mgkg) or microgramsliter (ugL) The units mgkg are also used
interchangeably with the term part per million (ppm) The units ugL are equivalent to parts per
billion (ppb)
Data validation was performed on all Level 4 data according to the requirements of EPA Region
I Laboratory Data Validation Functional Guidelines for Evaluating Organic Analyses (February 1
5797wpdoclaquogilluprifinaltextmlaquo8terrifiJ061297 4-1 QZT Environmental
Gallups Quarry Superjund Project - Remedial Investigation
1988 as modified November 1 1988) and Inorganic Analyses (June 13 1988 as modified
February 1989) Data validation was performed by David MacLean an independent data
validator Summaries of Mr MacLeans data validation results are presented in Appendix Q
41 Contaminant Source Investigation 411 Visual Site Reconnaissance
A comprehensive visual site reconnaissance was conducted over a three week period from August
23 until September 13 1994 to determine the potential presence of unknown disposal areas
Prior to the start of this survey a grid system was established to allow systematic coverage of the
Site and to locate features of interest The grid used to conduct the visual Site reconnaissance is
described in Section 21 A Site plan which includes the survey grid and the features described
below is shown on Plate 4-1 The features identified on Plate 4-1 are also summarized in Table 4-1
Based on this visual survey the ground surface in the northern portion of the Site which includes the Former Primary and Secondary Disposal Areas is covered with sand and gravel with sparse
to no vegetation Topographic relief is estimated to be as much as 20 to 30 feet and is attributed
to the Sites past usage as a sand and gravel quarry Many of the topographic low spots were
observed to contain either standing water (following rain events) or moist soil (indicative of
intermittent periods of ponded water)
The central portion of the Site which contains the Former Seepage Bed is presently heavily
vegetated Crushed stone and boulders are evident over a large portion of this area and the soils
consist mainly of a sandy till Immediately east and northeast of the Former Seepage Bed is a
topographic high with numerous boulders at the ground surface Evidence of previous test pit
explorations were also observed in this general vicinity Asphalt and mounds of asphalt pavement
were also observed in several areas and are presumed to be remanent of the State of Connecticut
Department of Transportation (CTDOT) asphalt plant operations discussed in Section 132
The southern portion of the Site contains the entrance to the former CTDOT asphalt plant as well
as the remains of the former plant itself These remains consist primarily of concrete footings
and retaining walls The remains of the asphalt plant are located along trending lines E through
K approximately 800 to 900 feet north of Tarbox Road The remains of a 6-foot diameter brick
and concrete masonry structure were observed along with an 8-inch diameter clay pipe leading
into the ground at the former plant location
The area located in the southwestern portion of the Site along line A includes mounded earthen
material piled along the western perimeter of the Site Scattered metal debris including several
5797wpdocsgalluprifinaltextmasterrifiil061297 4-2 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
empty rusted drums were observed adjacent to and partially buried within the mounded materials
Other objects consisting of timbers steel culvert tires and mounded asphalt were also observed
along the A line Mounded earthen materials located on lines M and N (400 to 650 feet north of
Tarbox Road) were observed to also contain miscellaneous debris (corrugated steel culvert hoses
and cables tires etc) and several empty rusted drums These areas are presently heavily
vegetated Other areas at the southern portion of the Site consist of a mixture of grassland and
brush There are numerous mounds of earthen material and scattered patches of asphalt and
pavement remanent of CTDOT operations throughout this portion of the Site
The Bionetics Corporations under contract to USEPA performed a review of historic aerial
photographs of the site and issued a Site Analysis Report (Bionetics Corp 1990) The historical
aerial photographs were used to prepare a Site plan which indicated the locations of suspected or
potential disposal areas (Figure 4-10 from the Phase 1A Work Plan (ESE 1994)) That Site plan
showed the locations of the three known former disposal areas as well as several much smaller
features described below Based on the visual reconnaissance performed during the RI areas
described in the Bionetics Report as either stained or wet or standing liquid or wet ground
correspond to topographic low spots in which ponded rainwater has been observed In addition
no visual evidence indicative of disposal activities was observed in the vicinity of the several
pits (dated 1981 through 1988) identified in the Bionetics Report These pits are believed to
be remnant of previous investigation test pits
An area described in the Bionetics Report as an extraction and an area of disturbed ground
northwest of the Former Seepage Bed correspond to an excavated area in which asphalt and
miscellaneous debris were observed during the Site reconnaissance The presence of mounded
materials in the vicinity of the Former Seepage Bed was confirmed during this visual
reconnaissance The mounded materials observed are comprised of earthen materials andor
asphalt pavement
A number of areas located within the southern portion of the Site were described in the Bionetics
Report as suspected disposal areas Features described as containing liquid generally
correspond to topographic low spots which were observed during the Site reconnaissance to
contain ponded rainwater following rain events The large feature described in the Bionetics
Report as extraction with liquid and associated dark toned material corresponds to a presently
open excavation in which asphalt was observed No features or specific objects were observed
during the Site reconnaissance which correspond to the locations of the unidentified objects
noted in the report The remains of a circular foundation observed during the Site reconnaissance
in the vicinity of the former CTDOT plant corresponds to the location of the possible vertical
5797wpdocraquogalluprifiiwltextmasterrifhl061297 4-3 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
tank Scattered mounds of earthen materials observed throughout the southern portion of the
Site correspond to the numerous mounded materials identified in the Report
Based on the observations made during this survey it is apparent that the landforms on-site have
been altered numerous times during past usage Extensive areas are presently heavily overgrown
and do not appear stressed Various earthen materials have been excavated and mounded at
numerous locations throughout the property and are presumed to be remnant of the former sand
and gravel quarrying operation andor the operation of the State DOT asphalt plant Also
patches of asphalt and mounds of asphalt pavement ranging from several to tens of square feet in
size were observed at multiple areas around the Site
The major features described as potential or suspected disposal areas in the Bionetics Report were
identified and described during the visual reconnaissance Although several empty 55 gallon
drums in various states of decomposition and scattered debris (consisting mainly of residential
trash scrap metal car parts etc) were observed at a number of locations across the Site no
intact drums or significantly stained or stressed areas were observed Other than the three known
former disposal areas no features were observed during the visual reconnaissance which indicate
the potential presence of large disposal or dumping areas
The above mentioned areas which contain debris including several empty 55-gallon drums were
further assessed during the soil gas and geophysical screening surveys performed as part of the
Phase 1A investigation The findings of these screening surveys are discussed below
412 Soil Vapor Survey
The soil vapor survey conducted on-site included a total of 100 soil vapor points installed along
an approximate 100-foot orthogonal grid Six additional sampling points were installed at three
locations where partially buried decomposed or empty 55-gallon drums were observed during
the visual site reconnaissance and at three areas where geophysical surveys detected the presence
of EM-31 andor MAG anomalies Each soil gas sample was analyzed for the presence of the
following eight VOC using a portable gas chromatograph acetone benzene 12-dichloroethene
(DCE) methylethyl ketone (MEK) methyl-isobutyl ketone (MIBK) 111-trichloroethane (TCA)
trichloroethene (TCE) and toluene
Of the 106 soil vapor sampling points tested detectable concentrations of VOC were identified at
only three locations These three locations SV160 SV165 and SV172 (shown on Plate 2-5)
were all located within approximately 50 feet of the Former Primary Disposal Area Specifically
TCE was detected at SV160 and SV165 and TCA was detected at SV165 and SV172
5797wpdocsgalluprifinaltextmasterrifhl061297 4-4 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
Likewise no VOC were detected at three additional survey points SV201 SV205 and SV206
installed within one foot of the 55-gallon drum which was observed at each of those locations or
at survey points SV202 SV203 and SV204 located in the vicinity of geophysical anomalies
identified during the EM-31 and MAG surveys
As described in the Work Plan the soil gas investigation was used as a screening survey to
identify apparent soil contamination in an effort to locate any potential unknown disposal areas
Based on the results of the soil gas survey no additional potential disposal areas were identified
413 Geophysical Investigations and Test Pits
Electromagnetic terrain conductivity (EM-31) and magnetometer surveys were conducted by
Weston Geophysical of Northboro Massachusetts as screening surveys to identify potential
unknown disposal areas The Weston Geophysical Report (provided as Appendix A) describes
in detail the findings of the geophysical investigations The significant findings of these two
screening surveys and of the follow-up test pit program are discussed below
4131 EM-31 Survey
The electromagnetic terrain conductivity measured across the Site was generally uniform with
most anomalies being attributed to wholly exposed or partially buried metallic debris (eg
automobile body parts empty rusted drums scrap pipe angle iron steel culvert and steel cable)
However two EM-31 anomalies could not be accounted for by noted surface features As shown
on Plate 2-14 the two unexplained EM-31 anomalies were located along trend line M at station
550 and at station 590 Due to the complexity of the anomaly located at station 550 an estimate
of its ferrous mass could not be made The second EM-31 anomaly was described as limited in
extent and was estimated to contain approximately 100 pounds of ferrous material assuming a burial depth of five feet (smaller objects at shallower depths would also explain the anomaly)
4132 Magnetometer Survey
The magnetometer survey identified a relatively flat gradient across the Site with a number of
localized anomalies most of which corresponded directly with visible surface features or objects
(as described above) A total of four anomalies were identified which could not be readily
attributed to known surface features Two of these anomalies occurred along trend line M and
correspond to the two EM-31 anomalies described above A third magnetometer anomaly was
identified along trend line C between stations 760 and 800 This anomaly was described as
approximately 10 feet in width and was interpreted as being the result of small amounts of ferrous
material spread over the length of the anomaly (approximately 40 feet) A fourth anomaly was
identified along line L at station 315 This anomaly was interpreted to consist of a small
amount of ferrous material buried at shallow depth
5797wpdocsgalluprifinaltextmraquosterrifhl061297 4-5 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4133 Test Pit Investigations
As described above the geophysical screening surveys revealed a total of four locations at which
EM-31 or magnetometer (or both) anomalies were detected that could not be attributed to visible
surface features The anomalies measured along line M were noted in both the EM-31 and
magnetometer surveys while the anomalies along lines C and L were only measured in the
magnetometer survey To confirm the source of these anomalies test pits were excavated at the
location of each anomaly Test pit excavation was observed by EPA oversight personnel
The presence of varying amounts of miscellaneous buried scrap metal debris described below
was identified at each test pit location At the anomaly located along Line C the excavated
debris included small rusted cans sheet metal and steel cable During the excavation of the test
pit located at the anomaly along line L a three foot long piece of a solid iron rod
approximately one inch in diameter was found buried approximately four inches below the ground
surface At the anomalies located along Line M a variety of ferrous debris was uncovered
including a crushed eight foot section of corrugated steel culvert approximately 2 feet in
diameter sheet metal nuts bolts steel cable and small rusted cans No drums intact or
otherwise were encountered at any location Soil removed from each excavation as well as the
side walls and bottoms of the excavations were screened for the presence of VOC using a PID
No elevated PID readings were measured Furthermore no visible evidence of staining was
noted in the soil at any of the excavations Upon excavation all metallic debris was placed on
the ground surface adjacent to the excavation and the test pits were backfilled with native soil
Test pit logs for the four test pits are shown in Appendix E
414 Background Soils
Soil samples were collected at two monitoring well cluster locations MW109 and MW112 to
determine the general Site background levels of TALTCL compounds The two locations were
chosen based on their upgradient position in relation to the former disposal areas The soils were
submitted for laboratory analysis for TALTCL parameters (VOC SVOC pesticides PCS
metals and cyanide) Tables 4-2 and 4-3 show the positive detections for VOC and metals
These tables only show the constituents that were detected at the site Constituents that were not
detected in any sample are not shown There were no detections of SVOC or pesticidesPCB in
any background soil sample
Due to the limited surficial deposits and abundance of boulders encountered at the MW109
location samples could only be collected from the 6-8 foot interval which is representative of till
at this location Discrete samples collected at the MW112 location were obtained from the 8-10
foot and 40-42 foot intervals which represent stratified drift and till respectively Composite
5797wpdocsglluprifinlaquoltextmlaquosterrifhl061297 4-6 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
samples from MW112 were collected from the 7-14 foot and 34-40 foot intervals (stratified drift
and till respectively) These depths were chosen based on their lithology
The results of the laboratory analyses for the soils collected at MW109 indicate the presence of
trace concentrations (0004 mgkg) of toluene no other VOC were detected No detectable
concentrations of SVOC pesticides or PCB were encountered in soil from the MW109 sample
location
Soils collected at the MW112 location also contained detectable concentrations of toluene
Toluene was detected at concentrations of 003 0017 0029 and 0032 mgkg from 8-10 feet 7shy
14 feet 10-14 feet and 34-40 feet respectively Trace concentrations of methylene chloride
(0003 mgkg) and trichloroethene (0002 mgkg) were also detected in the MW112 sample at 10shy
14 feet and 40-42 feet respectively No detectable concentrations of SVOC pesticides or PCB
were identified at the MW112 location
Although the source of the VOC is unknown all three of these compounds are organic solvents
that are (or were ) commonly used in many household (eg spot removers paint strippers
aerosols) commercial (eg pesticide formulations inks and dyes) and industrial (eg
degreasers) products
Metals concentrations in background soil boring samples are shown on Table 4-3 As expected
various metals were detected in all soil samples Analytical results for metals for all of the
MW112 samples were within the common range for soils found in the eastern United States
Heavy metals were generally detected only at trace concentrations Alkaline earth metals (eg
Ca Mg K) were detected at levels not unexpected for soils in the region Background concentrations of metals in subsurface soils were used for comparison purposes in analyzing the
significance of the metals concentrations measured in other non-background soil samples
415 Soils From Former Known Disposal Areas
Soil borings were drilled at each former known disposal area to determine whether residual
contamination remains in surface and subsurface soils During the Phase 1A investigation a total
of ten soil borings were performed Soil samples were collected from these borings and
submitted for laboratory analysis for TALTCL parameters (VOC SVOC pesticides PCB
metals) pH total organic carbon (TOC) and moisture content An additional six borings were
performed during the Phase IB Investigation Soil samples collected during the Phase IB
Investigation were submitted for laboratory analysis for VOC and pesticidesPCBs The
locations of the soil borings are shown on Plate 2-3
5797wpdoc8galluprifinaltextma8terrifhl061297 4-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Samples from the 0-1 foot interval were collected from each boring by hand using a stainless
steel scoop Continuous soil samples beneath the 0-1 foot interval were collected using a truck-
mounted drill rig equipped with standard split-spoon samplers Generally samples were collected
from both above and below the water table and at depth within each of the former known
disposal areas In addition each significant lithologic unit was sampled The specific sampling
depths and length cf sampling interval varied for different analytical parameters depending on the
lithology and volume of sample recovered from each spoon Sample intervals and analytes are
summarized in Table 2-2
A brief description of the reported historical disposal activities and the findings of the Soil
Sampling Program for each specific area are described below Positive hit tables showing the
laboratory results for soil boring samples collected from within the former known disposal areas
are presented in Tables 4-4 through 4-7 The unvalidated laboratory data for TALTCL
parameters are presented in Appendix H (Phase 1A data) and K (Phase IB data) Laboratory
results for pH total organic carbon and moisture content are presented in Appendix R
4151 Former Seepage Bed
The Former Seepage Bed is located near the center of the Site This feature is located on the
north side of a local bedrock high which is overlain by 10 to 20 feet of boundary till Historical
records indicate that this area was used for the direct discharge of liquid waste to the ground
surface It has been reported that an inverted dump truck body was buried in this area and was
connected to the ground surface via a pipe Liquid wastes were then reportedly poured directly
into the pipe The wastes reportedly dumped in this area have been described as low pH liquids
characteristic of metal pickling liquors The dump truck body and the contaminated earth were
removed in 1979 during CTDEP remedial efforts Approximately 20 tons of lime (which is
approximately equal to 10 cubic yards) was reportedly spread in the vicinity of the seepage bed to
neutralize any residual low pH material The soil boring program indicated that fill material in
this area extends from 3 to 7 feet below the ground surface Based on the approximate lateral
extent of this former disposal feature (as shown in historic plans of the Site) approximately 230
yards of sand and gravel fill material were used to backfill the CTDEP excavation
To investigate this area three soil borings (SB101 SB102 and SB103) were completed The
borings within the Former Seepage Bed were terminated at auger refusal depths of 68 feet
(SB101) 185 feet (SB102) and 160 feet (SB103) Within this area groundwater was only
encountered in the bottom 6 inches of the deepest boring (SB 102)
5797wpdocsgalluprifinaltextmasteiTifnl061297 4-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Surface Soil Sample Results - Former Seepage Bed
As shown in Table 2-2 the 0-1 foot interval was sampled at each location and submitted for
laboratory analysis for VOC SVOC pesticides PCB and metals No VOC were detected in this
interval at any of the three soil borings within the Former Seepage Bed In the 0-1 foot interval
very low levels of SVOC primarily polynuclear aromatic hydrocarbons (PAH) were detected at
SB101 and SB103 The concentrations of PAH ranged from 0012 ppm to 0076 ppm Moderate
concentrations of bis(2-ethylhexyl)phthlate (15 ppm) were also seen in this interval at SB101
Trace levels of certain pesticides were also seen in the 0-1 foot interval at SB101 [44-DDE
(00014 ppm) 44-DDT (0019 ppm) and 44-DDD (0041 ppm)] and at SB102 [44-DDD
(0011 ppm)] At SB102 a low level of PCB (Aroclor-1260 at 0027 ppm) was detected in the
surface soil sample
The results of metals analyses have been compared to background soils metal concentrations
determined from soil samples collected from the background monitoring wells MW109 and
MW112 With the exception of calcium (12200 ppm) and magnesium (9620 ppm) seen in the
0-1 foot interval at SB102 most metals in the surface soil samples were close to the background
concentrations seen at the Site The elevated concentrations of both calcium and magnesium are
attributed to the 20 tons of lime which were used in this area by CTDEP Compared to the
background level seen for lead (35 ppm) the concentration of this metal in the 0-1 foot interval
was slightly higher at SB101 (59 ppm) SB102 (43 ppm) and SB103 (69 ppm) Also silver
which was not seen in any of the background samples was detected in the 0-1 foot interval at
SB101 at 87 ppm
Unsaturated Zone Sampling Results - Former Seepage Bed
Within the unsaturated zone below the 0-1 foot interval described above only trace levels of
VOC were detected Toluene was seen in SB101 (4-6 feet) and SB102 (16-18 feet) at a
concentration of 0002 ppm Xylene (total) was also detected at the same two intervals at the
same concentrations The only other VOC detected was TCE in SB101 (4-6 feet) at a
concentration of 0004 ppm
The only SVOC detected within the unsaturated zone at the Former Seepage Bed was di-n-octyl
phthlate detected in all three borings at various depths at concentrations ranging from 001 to
0021 ppm Very low concentrations of several pesticides (SB101) and PCB (SB101 and SB102)
were detected at various depths in unsaturated zone samples below the 0-1 foot interval The
pesticides 44-DDD (0033 ppm) 44-DDT (0024 ppm) and dieldrin (000064 ppm) were
5797wpdocBgalluprifinaltextmlaquosteiTifhl061297 4-9 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
detected at SB 101 The highest detections of the PCS for Aroclor-1260 and Aroclor-1254 were
0027 (SB102 0-1 feet) and 0034 ppm (SB1012-5 feet) respectively
Within the unsaturated zone below the 0-1 foot interval the only metals detected above the
highest background concentrations were aluminum barium iron magnesium manganese and
potassium The highest concentration of each of these metals was only slightly higher than
background levels and all were within the same order of magnitude
Among the Former Seepage Bed borings only one (SB 102) encountered groundwater above the
auger refusal depth Since only six inches of saturated soil was encountered the limited sample
volume was submitted for VOC analysis only No VOC were detected in this sample
pH TOC Moisture Content - Former Seepage Bed
The pH of samples collected in this area ranged from 622 to 792 Total organic carbon values
(mgkg) ranged from 1600 to 23000 Moisture contents ranged from 42 to 105 percent
4152 Former Secondary Disposal Area
The Former Secondary Disposal Area is located in the northwestern corner of the Site adjacent to
the railroad tracks The Disposal Area is presently seen as a depression which is approximately
50 feet wide by 60 feet long and is approximately 6 to 8 feet below the surrounding ground
surface The ground surface at this area is covered by approximately 2 feet of backfill (mostly
sand) material The fill is underlain by fine- to coarse-grained sand which ranges in thickness
from approximately 6 to 22 feet Sandy till ranging in thickness from 10 to 20 feet underlies the
sand The depth to groundwater from the bottom of the depression is approximately 10 feet
Historical records indicate that this area was used for the disposal of drummed liquid wastes
Approximately 200 drums and an unknown quantity of contaminated soil were removed in 1979
during CTDEP remediation efforts
In order to characterize residual contamination which may be present beneath this area three soil
borings (SB 104 SB 105 and SB 106) were performed within the depressed area ranging in depth
from 30 feet (SB 105) to 36 feet (SB 104) Within this area groundwater was encountered at
approximately 10 feet below the ground surface
5797wpdocsglaquolluprifinlaquoltextmaBterrifnl061297 4-10 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Surface Soil Sample Results - Former Secondary Disposal Area
Within the 0-1 foot interval only a trace concentration of one VOC (ethyl benzene at 00006
ppm) was detected (at SB104) The only SVOC detected in this interval was butylbenzylphthlate
(014 ppm) at SB 104 Very low concentrations of pesticidesPCB were measured at each boring
Aroclor-1254 was detected at SB104 (0025 ppm) and SB105 (0021 ppm) Aroclor-1260 was
detected at all three borings ranging in concentration from 00089 to 0031 ppm Dieldrin was
detected at SB 104 at trace levels (000048 ppm)
In the 0-1 foot interval nearly every metal detected occurred at concentrations close to those for
the background samples with the exception of lead which was detected at a concentration of 118
ppm at SB 104 Cyanide was detected in this interval at very low concentrations ranging from 16
to 97 ppm
Unsaturated Zone Sample Results - Former Secondary Disposal Area
Between the 0-1 foot interval and the groundwater table at the Former Secondary Disposal Area
no VOC were detected The only SVOC detected in this zone were at very low levels
(butylbenzylphthlate at 0037 ppm and di-n-octylphthlate at 0012 to 0029 ppm) Also in this
interval at SB104 and SB105 low levels of the PCB Aroclor-1254 and -1260 were detected at
concentrations up to 0055 ppm and 0018 ppm respectively Dieldrin was detected at a trace
level (00014 ppm) at SB104 Within this zone most of the metals were close to the background
soil concentrations except for lead (224 ppm) at SB104 and copper (476 ppm) at SB105
Cyanide was detected in the 1-10 foot interval at SB104 and SB105 at very low concentrations of
83 and 31 ppm respectively
Saturated Zone Sample Results - Former Secondary Disposal Area
Beneath the groundwater table within the Former Secondary Disposal Area no VOC were
detected The only SVOC detected was di-n-octylphthalate which ranged in concentration from
002 to 008 ppm Very low levels of endrin (00004 ppm) and Aroclor-1248 (001 ppm) were
also detected just below the water table but were not present in the deepest sample collected (26shy
28 feet) The only metals which were detected below the water table at concentrations notably
higher than background levels were copper and nickel Copper ranged in concentration from 621
to 863 ppm while nickel ranged from 119 to 169 ppm The highest concentrations of these
two metals were detected just below the groundwater table
5797wpdocsgalluprifinaltextmasterrifhl061297 4-11 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
pH TOC Moisture Content - Former Secondary Disposal Area
The soil pH ranged from 688 to 751 TOC ranged from lt 1500 to 2800 mgkg and moisture
content ranged from 37 to 124 percent
4153 Former Primary Disposal Area
The Former Primary Disposal Area is located at the northern end of the Site approximately 150 feet east of the Former Secondary Disposal Area This feature is seen as a circular depression
approximately 130 feet in diameter (at the top edge) and is approximately 8 to 10 feet lower than
the surrounding ground surface Non-native fill material (sand and gravel) ranged in thickness
from approximately 2 to 4 feet Underlying the fill is an approximately 15- to 20- foot thick
generally sandy horizon which overlies 6 to 15 feet of till The water table in this area ranges
from approximately 3 to 6 feet beneath the ground surface in the bottom of the depression
Records indicate that approximately 1400 drums and approximately 5000 gallons of free liquids
were removed from the Former Primary Disposal Area during CTDEP cleanup efforts
Approximately 2000 to 3000 cubic yards of contaminated soil were also removed during that
effort
During the Phase 1A (1994) investigation a total of four soil borings (SB107-SB110) were
completed within the Former Primary Disposal Area to characterize the extent of residual soil
contamination These borings ranged in depth from 24 feet at SB108 to 39 feet at SB109 An
additional six borings (SB111-SB116) were completed during the Phase IB (1995) investigation
Samples collected during the Phase IB investigation were submitted for laboratory analysis for
VOC and PCBPesticides The purpose of the additional borings was to further delineate the
lateral extent of residual VOC and PCB contamination in the unsaturated portion of the soil The
Phase IB borings were terminated just below the groundwater surface typically five to seven feet
below the ground surface The locations of all of the borings are shown on Plate 2-5 however a
detailed close-up showing the boring locations within the Former Primary Disposal Area is shown
as an insert on Plates 4-2 and 4-3 which are discussed below The tabulated laboratory data for
both the Phase 1A and Phase IB soil borings are shown on Tables 4-4 through 4-7 (VOC SVOC
pesticidesPCB and metals respectively)
Surface Soil Sample Results - Former Primary Disposal Area
In the 0-1 foot interval only a limited number of VOC were detected generally at very low
concentrations (Table 4-4) The compounds detected in the 0-1 foot interval (followed by
concentration [ppm] and location) are as follows acetone (0007 ppm at SB107)
5797wpdocsgalluprifinaltextmasterri fhl061297 4-12 QST Environmental
Catlaps Quarry Superfund Project - Remedial Investigation
tetrachloroethene (PCE) (0018 ppm at SB109 and 0002 at SB113) toluene (0005 at SB112
0003 at SB1H and 0002 at SB115) ethyl benzene (0002 at SB113) and total xylenes (0010 at
SB113) In this same interval several phthalates (butylbenzyl bis(2-ethylhexyl) diethyl and dishy
n-octyl) were detected at various locations (Table 4-5) with no apparent spatial trend at
concentrations ranging from 0008 to 17 ppm Several PAH compounds were also detected at
SB110 in the 0-1 foot interval at concentrations ranging from 0007 to 0017 ppm As shown in
Table 4-6 Aroclor 1254 was detected in the 0-1 foot interval at every boring at concentrations
ranging from 0046 to 43 ppm Aroclor-1260 was also detected in the 0-1 foot interval at
concentrations ranging from 0046 to 23 ppm Trace concentrations of several pesticides were
also detected in the 0-1 foot interval in some borings as follows heptachlor epoxide (000058 to
0052 ppm) dieldrin (000059 to 0043 ppm) 44-DDE (000089 to 0081 ppm) and 44-DDT
(000048 to 0027 ppm) Aluminum (12200 ppm at SB110) was the only metal in the 0-1 foot
interval that was detected at concentrations significantly greater than background levels (Table 4shy
7) Cyanide was detected at a very low concentration of 16 ppm at both SB109 and SB110
Unsaturated Zone Soil Sample Results - Former Primary Disposal Area
Beneath the 0-1 foot interval but above the water table a small number of VOC were detected at
various concentrations and locations (Table 4-4) Within this zone no VOC were detected at
SB107 At SB108 methylene chloride was detected at 0001 ppm Ethyl benzene was detected
at SB 109 (015 ppm) SB110 (54 ppm) SB111 (0048 ppm) and SB115 (16 ppm) Total
xylenes were seen at SB109 (16 ppm) SB110 (46 ppm) SB111 (064 ppm) and SB115 (80
ppm) Toluene was detected at SB 110 through SB 115 at concentrations ranging from 0003 to 12
ppm PCE was seen at SB109 SB111 SB114 and SB116 at concentrations which ranged from
0003 to 17 ppm and at SB115 at 28 ppm 111-TCA was detected at SB111 112 114 115
and 116 from 0001 to 14 ppm TCE was also seen at SB111 114 115 and 116 at
concentrations ranging from 0002 to 17 ppm 2-butanone (MEK) was detected at SB111 at
0005 ppm 12-DCE was seen at both SB115 (016 ppm) and SB116 (0009 ppm) Finally 11shy
DCA (0008 ppm) 11 -DCE (0009 ppm) and carbon disulfide (0022 ppm) were all seen at
SB115 Methylene chloride (0001 ppm) was detected at SB108 These detections occurred in
the transition zone between fill and native deposits
The SVOC detected in this zone (shown on Table 4-5) included several phthalates at
concentrations ranging from 0039 to 46 ppm Napthalene was also detected at SB109 (047
ppm) and SB110 (63 ppm) 12-dichlorobenzene and 2-methylnapthalene were detected at SB110
at 098 and 081 ppm respectively The most frequent occurrence and highest concentrations of
phthlates (and SVOC in general) occurred at SB 109 and SB 110
5797wpdocraquogalluprifinaltextmlaquolaquoterrifhl061297 4-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
As shown on Table 4-6 Aroclor-1254 occurred at most of the borings in this zone at gtbullraquo
concentrations ranging from 00023 to 64 ppm Aroclor-1242 (0043 to 017 ppm) and Aroclorshy
1260 (043 to 24 ppm) were detected at SB109 and SB110 Pesticides were also detected at trace
to very low concentrations at several locations These compounds include dieldrin (000028 shy
00046 ppm) 44-DDE (000043 - 00063 ppm) 44-DDT (00013 - 00081 ppm) beta BHC
(00013-00021 ppm) and delta BHC (000086-00024 ppm) endrin ketone (00028 ppm)
heptachlor epoxide (0008 ppm) heptachlor (00093 ppm) endosulfan I (0008 ppm) and
methoxychlor (0140 ppm) Table 4-7 shows that the only metals detected within this zone at
concentrations significantly higher than background levels were cadmium (131 ppm) and copper
(103 ppm) both of which occurred at SB109 Cyanide was detected in SB110 in the 1-35 foot
interval at a very low concentration of 32 ppm
Saturated Zone Soil Sample Results - Former Primary Disposal Area
The highest concentrations of VOC within the Former Primary Disposal Area occurred just below
the surface of the groundwater table in the natural deposits immediately underlying fill material
As shown on Table 4-4 in the 4-6 foot interval at SB 109 the following VOC were detected 12shy
DCE (059 ppm) PCE (36 ppm) TCA (98 ppm) TCE (62 ppm) ethyl benzene (85 ppm)
toluene (44 ppm) and xylenes (46 ppm) In the next deepest interval sampled (14-16 feet)
generally the same compounds were detected however the concentrations were lower by an
order of magnitude At the last sampled interval (30-32 feet) generally the same compounds
were again detected but at trace levels (0001-0006 ppm) Cyanide was detected in SB110 in the
10-16 foot interval at a very low concentration of 11 ppm
A total of six SVOC were detected just below the water table at a depth of 4-8 feet below ground
surface (Table 4-5) phthalates (0039 to 0058 ppm) napthalene (021 ppm) 2-methylnapthalene
(0034 ppm) phenol (016 ppm) and 124-trichlorobenzene (0046 ppm) SVOC at greater
depths were napthalene (0076 ppm) in the 10-16 foot interval and bis(2-ethylhexyl)phthlate (11
ppm) at the 22-32 foot interval Aroclor-1254 was detected at concentrations which decreased
with depth from 02 ppm at 4-8 feet to 00096 ppm at 23-34 feet
In the saturated zone no metals were detected at levels significantly greater than background
pH TOG Moisture Content - Former Primary Disposal Area
Values for soil pH ranged from 609 to 745 TOC ranged from lt 1500 to 5500 mgkg and
moisture content ranged from 49 to 282 percent
5797wpdocsgalluprifinaltextmasterrifnl061297 4-14 QST Environmental
Gallups Quarry Superfand Project - Remedial Investigation
416 Contaminant Source Investigations Summary
The previous discussions regarding the contaminant source investigations are grouped into two
categories
bull surveys to identify unknown disposal areas (if any) and
bull investigations at known former disposal areas
Based on the findings of the Visual Site Reconnaissance the Soil Vapor Survey and the
Geophysical Investigations (including the subsequent confirmatory Test Pits) it is apparent that
significant unknown hazardous materials disposal features do not exist at the Site
Based on investigations performed within the known former disposal areas it is evident that the
Former Seepage Bed and the Former Secondary Disposal Area contain generally trace levels of
VOC SVOC pesticides PCB compounds and cyanide For the most part soil metal
concentrations are comparable to background levels measured at upgradient locations at the Site
although very low levels of cyanide (ranging from 11 - 97 mgkg) were also detected at various
depths within the Former Primary and Secondary Disposal Areas Elevated levels of calcium and
magnesium detected at the Former Seepage Bed can be attributed to the large amount of lime
which was reportedly used during remedial efforts Although elevated concentrations of several
other metals were detected at a few locations these levels appear to fall within regional range
values (for the metals with published ranges)
The Former Primary Disposal Area appears to be the only area with notable levels of residual
contamination primarily VOC including ethyl benzene toluene xylene TCA TCE and PCE
In general the highest VOC concentrations are located at or just below the groundwater table in
native materials immediately beneath the fill materials These concentrations diminish quickly
with depth Toluene ethyl benzene xylene and in one case a low level of PCE were also
detected at or near the ground surface within the fill material Empty gasoline cans numerous
off-road vehicle tire tracks and the remains of large campfire pits have been observed in the
vicinity of the former disposal areas Of the VOC detected the ones considered most significant
are those which are also seen in groundwater above their respective MCL (groundwater results
are discussed separately in section 42) In an effort to illustrate the locations where the more
notable amounts of residual VOC contamination are found Plate 4-2 which shows the locations
of total chlorinated VOC has been prepared On this plate the values for total chlorinated VOC
have been color-coded as follows sample intervals where all compounds were below the detection
limit (BDL) are not colored intervals where total chlorinated VOC values are present but less
5797wpdoc8glaquolluprifinraquoltextmasterrifhl061297 4-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
than 1 ppm are shown in green values between 1 and 10 ppm are shown in yellow and locations
between 10 and 35 ppm are shown in red The highest value for any interval is 31277 ppm
As indicated on Plate 4-2 total chlorinated VOC concentrations were either BDL or less than 1
ppm for the majority of intervals sampled Total concentrations between 1 and 10 ppm (ie
yellow zones on Plate 4-2) were detected at two locations SB108 and SB109 Total chlorinated
VOC concentrations in the 4-6 interval at SB108 were 155 ppm At SB109 total chlorinated
VOC concentrations were between 1 and 10 ppm within the 2-4 foot interval (17 ppm) and the
14-16 foot interval (213 ppm) Total chlorinated VOC concentrations exceeded 10 ppm at two
locations SB 109 (2019 ppm in the 4-6 foot interval) and SB115 (31277 ppm in the 3-5 foot
interval) As seen on the plan view insert on Plate 4-2 SB109 and SB115 are located within
approximately 25 feet of each other in the northwestern quadrant of the Former Primary Disposal
Area The zone of highest chlorinated VOC contamination appears to be located just beneath the
fill horizon in close proximity to the groundwater surface
Trace to low-levels of PCB were also detected in both near surface samples and (at one location)
at a depth of 32 feet below the ground surface The highest concentration of any single PCB
compound was 64 parts per million in the 1-35 foot interval at SB110 Other detections
included 43 ppm (SB107 0-1 foot interval) 3 ppb (0-1 foot interval at SB109 and SB110) 28
ppm (0-1 foot interval at SB113) 23 ppm (0-1 foot interval at SB107) and 24 ppm (1-35 foot
interval at SB110) All other detections were below 15 ppm
Plate 4-3 has been prepared to illustrate the distribution of PCB compounds detected within the
Former Primary Disposal Area Plate 4-3 shows the concentration and locations for total PCB
compounds for all intervals sampled with the area
Total PCB concentrations have been grouped and color coded on Plate 4-3 as follows sample
intervals where no PCB were detected (BDL) are shown as colorless zones where total PCB were
detected at concentrations less than 1 ppm are shown in green Intervals containing between 1
and 5 ppm total PCB are yellow and intervals between 5 and 10 ppm are shown in red (the
highest value for total PCB compounds anywhere was 88 ppm)
As shown on Plate 4-3 total PCB values at the majority of locations within the Former Primary
Disposal Area are less than 1 ppm Values between 1 and 5 ppm (shown in yellow) were
detected at SB109 SB110 and SB113 These intervals all occur within four feet of the ground
surface and all are within the fill horizon The only intervals where total PCB concentrations are
between 5 and 10 ppm are the 0-1 foot interval at SB107 (66 ppm) and the 1 to 35 foot interval
5797wpdoc8galluprifinaltextmastemfhl061297 4-16 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
at SB 110 (88 ppm) There does not seem to be any spatial trend or relationship among these
detections as the detections are scattered among all quadrants of the disposal area
42 Groundwater Quality 421 Temporary Well Point Investigation
The results of the temporary well point investigation discussed in Section 24 indicated the
presence of a narrow groundwater plume (approximately 250 feet in width) of volatile organic
compounds (VOC) originating at the Former Primary Disposal Area and extending about 700 feet
in a northwesterly direction VOC were detected up to Mill Brook and at trace levels at one
location near the northern bank of the brook Plate 4-4 summarizes the VOC detections at
different locations and depths in the aquifer A summary of these field and laboratory data is
presented on Table 4-8 and Table 4-9 respectively The area extent of this VOC plume is in
excellent agreement with the groundwater flow directions measured in the northern Study Area (as
discussed in Section 422) The primary chlorinated VOC detected were 111-trichloroethane
(TCA) trichloroethene (TCE) and 12-dichloroethene (DCE) VOC concentrations within the
Former Primary Disposal Area were found to decrease significantly with depth indicating that the
source material is probably located near or above the water table Further downgradient VOC
were detected at generally lower concentrations and were present throughout the entire aquifer
thickness with no apparent depth-dependent trend Various contaminant transport mechanisms
are discussed in Section 50
In the southern portion of the Study Area low-level detections of methyl isobutyl ketone (MIBK)
were detected in samples from two microwells Also acetone and methylethyl ketone (MEK)
were detected at one location adjacent to Tarbox Road No other VOC were detected at any
location
Due to variability in the results of field VOC analyses (using a portable gas chromatograph) and
off-site laboratory analyses it was determined that the field GC results should not be relied upon
as the only source of information to evaluate either the VOC plume boundary or absolute levels of
particular constituents within the plume Rather the microwell results were subsequently used to
guide the location of monitoring wells and to evaluate relative horizontal and vertical
concentration variations within the VOC plume Water quality data from monitoring wells were
then used to confirm the microwell results and delineate plume boundaries
The results of laboratory metals analyses shown in Table 4-10 and Plate 4-5 do not indicate any
significant source areas on the Site nor are there any apparent trends in occurrence or
concentrations of metals Lead was detected at variable depths and concentrations at a total of 15
microwell locations (TW102 103 104 107 115 120 126 128 139 141 143 148 151 and
5797wpdoclaquogilluprifinaltextmlaquo8terrifhl061297 4-17 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
152) These locations represent nearly every portion of the study area With several exceptions
the majority of iiicrowell lead detections were trace to very low (ie lt 10 ugL) Exceptions
included results from single samples collected at locations TW120 (192 ugL) TW-128 (644
ugL) and TW151 (182 ugL) Although several of the locations at which lead was detected are
downgradient of former disposal areas most of the detections were at locations that are either
upgradient or a large distance (400 to 1000 feet) from former disposal areas Furthermore while
lead was detected at some downgradient locations there were other downgradient locations at
which lead was not detected at all It is also noted that lead was only detected at a concentration
of 1 ugL at the microwell (TW143) placed in the center of the Former Primary Disposal Area
and that lead was not detected at all in the two nearest downgradient (relative to the Former
Primary Disposal Area) microwell locations (TW119 and 137) Based on the lack of significant
detections of lead in most microwells on the Site and the fact that metals are typically much less
mobile than VOC the majority of these detections were not considered to be Site related and may
be attributed to an off-site source Numerous off-site activities may have resulted in lead
contaminations including most notably the observed presence of large lead-containing batteries
abandoned along the west side of the railroad bed and fire armhunting activities (as evidenced by
the large number of spent shotgun shell casings observed in the area)
422 Groundwater Monitoring Wells
The initial (Phase 1A) monitoring well network was designed to (1) confirm the findings of the
microwell survey with respect to the chlorinated VOC plume in the northern Study Area and the
two isolated MIBK detections in the southern Study Area and (2) provide hydraulic data to
determine groundwater flow directions and rates An additional objective of the network was to
evaluate potential bedrock groundwater issues related to the Former Seepage Bed which is
located in an area where the water table lies below the base of the overburden formation
Following the Phase 1A monitoring well installation and sampling program additional rounds of
groundwater samples were collected in April July November 1995 February May August
November 1996 and February 1997 under the Long-Term Monitoring Program In October
1995 additional wells were installed during the Phase IB field program to address groundwater
quality and flow directions from areas north of the site The newly installed monitoring wells
(MW117STT MW118STT MW119STT and MW102B) and the existing monitoring wells
located at the former Pervel flock plant (MW-A -B -C -2 and -3) were also included only in
the November 1995 round of groundwater sampling and were sampled only for VOC analyses
Further details of the monitoring well installation program are provided in Section 27 The
following sections present and discuss the groundwater sampling results for VOC SVOC metals
and pesticidesPCB for all nine rounds of sampling
5797wpdocsgalIuprifinaltextmlaquosteiTifhl061297 4-18 QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
4221 VOC
This section discusses the VOC data collected from groundwater monitoring wells during the nine
sampling events conducted between January 1995 and February 1997 Positive groundwater VOC
detections for the nine sampling events are shown in Tables 4-11 through 4-19 respectively VOC
data for the four 1995 events are presented graphically on Plate 4-6 and the VOC data for the
four 1996 events and the February 1997 event are presented on Plate 4-7
42211 Overburden
Northern Study Area
As shown in Plates 4-6 and 4-7 the monitoring well data for all nine sampling events generally
confirm the microwell survey results with regard to the distribution of VOC downgradient from
the Former Primary Disposal Area
The various VOC detected are grouped into chlorinated VOC (eg TCA TCE 11- and 12shy
DCE tetrachloroethene (PCE) 11-DCA 12-dichloropropane carbon tetrachloride methylene
chloride chloroform and vinyl chloride) and non-chlorinated VOC (eg ethyl benzene toluene
xylene benzene styrene and carbon disulfide) As shown in Plates 4-6 and 4-7 the distribution
of these compounds as reported for the November 1995 and February 1997 sample events
respectively has been used to delineate the horizontal boundaries of a VOC plume which
originates in the vicinity of the Former Primary Disposal Area The plume boundary as depicted
on Plates 4-6 and 4-7 is defined by the locations where any compound was detected in excess of
its respective EPA MCL during the November 1995 and February 1997 sampling rounds
Locations at which VOC were detected at levels greater than their respective MCL during at least one sampling round were MW101(STTT) MW102(STTB) MW105 (STTTB)
MW107(TT) and MW-C (located at the former Pervel flock plant facility) MW116T exceed the
MCL for PCE only and only on one occasion (January 1995 at 17 ppb) VOC in samples
collected from MW116T during the eight subsequent sampling events were all below their
respective MCL At MW101 the only compound which was detected in excess of its MCL was
PCE which was detected in the shallow well at a maximum concentration of 6 ppb in the top-ofshy
till well at concentrations ranging from 15 to 32 ppb and between 22 and 30 ppb in the till well
At MW102S compounds detected in excess of their MCLs were 11-DCE (between 3 and 19
ppb) 12-DCE (between 72 and 670 ppb) PCE (between 10 and 43 ppb) 111-TCA (one
exceedance in July 1995 at 240 ppb) TCE (between 15 and 88 ppb) and vinyl chloride (from not
detected to 86 ppb) At MW102TT compounds that exceeded their respective MCL were 11shy
DCE (from not detected to 35 ppb) 12-DCE (between 140 and 1300 ppb) PCE (above the
MCL during four of the sampling events up to 14 ppb) 111-TCA (one exceedance in August
5797wpdocsgalluprifinaltextmasterrifhl061297 4-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
1996 at 200 ppb) TCE (one exceedence in February 1997 at 7 ppb) and vinyl chloride (from not
detected to 430 ppb) MW102B and MW105S each had a one-time MCL exceedence for only
vinyl chloride both occurrences at 3 ppb (in May 1996 at MW102B and in August 1996 at
MW105S
At MW105TT six compounds have exceeded their respective MCL as follows 11-DCE (up to
32 ppb) 12-DCE (between 150 and 1100 ppb) PCE (up to 9 ppb) 111-TCA (between 37 and
390 ppb) TCE (two exceedences up to 14 ppb) and vinyl chloride (from not-detected to 710
ppb) MCL exceedences detected at MW105T are as follow 11-DCE (two exceedences both at
12 ppb) 12-DCE (between 43 and 430 ppb) 111-TCA (one exceedence 380 ppb in February
1996) TCE (one exceedence 27 ppb in November 1995) and vinyl chloride (from not detected
to 1400 ppb) The only compound that exceeded its respective MCL in MW105B is 12-DCE
(between 2 and 180 ppb) MW107TT has had MCL exceedence of the following three
compounds 11-DCE (from not detected to 16 ppb) 12-DCE (between 72 and 1100 ppb) and
vinyl chloride (between 120 and 430 ppb)
Although there is some variation in the distribution and concentration of VOC with each sample
event the plume defined by the November 1995 data set (as shown on Plate 4-6) is nearly
identical to the plume defined by the February 1997 data set (as shown on Plate 4-7) Further
discussion of VOC concentration variations with time is provided in Section 52
Typically VOC in wells located beyond the boundaries of the plume were detected at estimated
or trace to very-low concentrations and were not detected with any regularity VOC were
detected at low levels in at least two-thirds of the samples collected from the following wells
located beyond the boundaries of the plume MW103TT (12-DCE and PCE) MW108B 11shy
DCE PCE and TCA) MW116T (PCE and TCA) SW3S (12-DCE PCE and 11-DCA) and
SW3D (12-DCE TCA and 11-DCA) PCE was detected in excess of its MCL at location
MW116T (17 ppb) during the first sampling event (January 1995) but it was never detected
above 3J ppb in the eight subsequent sampling events
TCA and 12-DCE which were detected in wells at all three locations along the plume centerline
(ie MW107 MW105 and MW102) appear to be good tracers for assessing contaminant
migration away from the Former Primary Disposal Area Based on 1995 data these compounds
have been incorporated into contaminant travel-time analyses presented in Section 5 At locations
MW107 and MW105 the highest concentrations were measured in the top-of-till wells with only
low to trace levels in the shallow wells (TCA and 12-DCE concentration up to 130 ppb and
1100 ppb respectively in MW107TT and up to 390 ppb and 1100 ppb respectively in
MW105TT At location MW102 TCA and DCE were detected at similar concentrations (up to
5797wpdoc8galluprifinaltextmasterrifhl061297 4-20 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
240 and 1300 ppb respectively) in shallow and top-of-till wells For all sampling dates TCA
concentrations in the top-of-till wells along the plume centerline varied from 24 to 390 ppb and
12-DCE levels in the top-of-till wells along the plume centerline ranged from 72 to 1300 ppb
No significant reduction in TCA or 12-DCE concentrations with distance from the Former
Primary Disposal Area is apparent at locations MW107 MW105 and MW102
TCE 11-dichloroethane ethyl benzene benzene 11-DCE 12-dichloropropane PCE toluene
vinyl chloride and xylenes were also detected at each of the three plume centerline locations but
as shown in Plates 4-6 and 4-7 their concentration distributions were more sporadic and TCE
11-DCE PCE and vinyl chloride were the only compounds that exceed their respective MCL
during at least one sampling event TCE was found at concentrations up to 88 ppb (in well
MW102S) 11-DCE was found at concentrations up to 35 ppb (in well MW102TT) the
maximum PCE concentration was measured at 43 ppb (in well MW102S) and vinyl chloride was
measured as high as 1400 ppb (well MW105T) The second highest vinyl chloride value was
710 ppb (well MW105TT) and all other vinyl chloride measurements ranged from not-detected up
to 430 ppb
Wells located within the northern portion of the Site where VOC have never been detected include
MW106TT MW109B and MW110S
Based on the monitoring well and microwell results concentrations within the VOC plume appear
to be relatively evenly distributed throughout the lower three-quarters of the aquifer thickness
Throughout most of the plume area (eg MW107 MW105 and MW101) VOC levels in the
upper five to 15 feet of the aquifer are typically near the detection limit The concentration
reduction near the water table is likely associated with rainwater infiltration Evidence of
infiltration includes the consistently downward hydraulic gradients at MW107 MW108 and
MW116 At these locations the vertical hydraulic gradient is on the order of a factor of 100
greater than the horizontal hydraulic gradient within the VOC plume Location MW102 where
shallow and deep concentrations are similar in magnitude is an exception to this trend of low
concentration near the water table A plausible explanation for the observed concentrations in
MW102S is the hydraulic influence of Mill Brook which as discussed in Section 3323 causes
upward flow in the upper portion of the aquifer near the brook Upward flow near the brook and
MW102S is also supported by the upward hydraulic gradients measured between MW102S and
the stream piezometer PZ-4B
The present PCE distribution in groundwater exhibits inconsistencies with migration from the
Former Disposal Areas PCE was consistently detected at levels above the 5 ppb MCL up to 43
ppb in groundwater samples from wells MW102S MW101TT and MW101T PCE was
5797wpdocraquogalluprifinaltextmasterrifhl061297 4-21 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
measured in well MW116T at 17 ppb in the initial sampling round (January 1995) and
consistently at trace levels in subsequent sampling rounds However only trace levels of PCE
were detected at the MW105 or MW107 locations and the only occurrences of PCE at MW105
or MW107 greater than 5 ppb were three estimated detections of 6 7 and 9 ppb at MW105TT
PCE was not detected in well SW3S and was detected once at a trace level in well SW3D
Monitoring wells MW102 and MW101 are downgradient from both the Former Disposal Areas
and the former Pervel flock plant where PCE TCA and DCE groundwater contamination has
been documented (Section 52) During the November 1995 sampling event VOC detected at
MW-C (located at the former Pervel flock plant) include DCE (97 ppb) TCE (11 ppb) and PCE
(24 ppb) Based on available data MW116 is located downgradient from the former Pervel
flock plant Groundwater flow conditions in the past would need to have been different from
present conditions for MW116 to be downgradient from the Former Disposal Areas Although
the PCE detections at locations MW102 and MW101 could be attributable to historical releases
from the Former Disposal Areas the regional flow pattern and spatial distribution of PCE in
groundwater suggest that contamination from the former Pervel facility has at a minimum
contributed to VOC (PCE TCA and DCE) contamination of these locations Further discussion
of the PCE detections and other VOC concentration variations is provided in Section 52
Southern Study Area
In the southern portion of the Study Area groundwater samples were collected from overburden
monitoring wells at five locations SW9 MW112 MW113 MW114 and MW115 As shown
on Plates 4-6 4-7 no VOC were detected in any of the wells As a result of the consistent lack of
detections wells at these locations were dropped from the Long-Term Monitoring Program (with
EPA approval) after three sampling events These data are consistent with the microwell survey
results but do not support the low-level detections of methyl isobutyl ketone in the two microwell
samples (Section 421)
42212 Bedrock
During the RI VOC were detected in bedrock wells at the following locations MW102 MW105
MW107 MW108 and SW-10 Since the only VOC detected at SW-10 was TCA at an estimated
trace concentration (1J ppb) during the January event and TCA was not detected in SW-10
during the subsequent two sampling events this well was eventually dropped from the Long Term
Monitoring Program (with EPA approval) following the July event All other bedrock wells in
the southern portion of the Study Area (MW111 MW112 MW113 SW-12) were likewise
dropped from the monitoring program At location MW108B estimated concentrations of PCE
(3J ppb) and TCA (up to 9J ppb) were detected during the January and April sampling events
therefore samples collected from this well during the July and November events were submitted
5797wpdocsgalluprifinaltextmasterriftil061297 4-22 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
for VOC analyses using EPA Method 5242 which hs lower detection limits than the TCL
Methods The results of the July and November events for MW108B indicate that other VOC are
present but generally at trace to very low concentrations The highest detections of TCA and
PCE at this location were 92 and an estimated 5 ppb respectively Other VOC detected at
MW108 were carbon tetrachloride (12 ppb) 11-DCA (1 ppb) 12-DCA (015J ppb) 11-DCE
(13 ppb) and xylene (01J ppb)
The only VOC detected at MW107B was TCA which was measured during three events at
concentrations ranging between 059J and 2 ppb Over the nine sampling events VOC detected
at MW105B included 11-DCA (BDL to 9J ppb) 11-DCE (BDL-4J ppb) 12-DCE (11-140J
ppb) 12-dichloropropane (2J ppb in January 1995 and February 1996 only) TCA (2J-12 ppb)
and TCE (BDL-3J ppb)
MW102B was installed during the Phase IB investigation and therefore was only sampled during
five events VOC detected at MW102B were typically at estimated trace concentrations and
only PCE was detected in every round (2J to 4J ppb) The only MCL exceedence was a single
estimated detection of vinyl chloride (3J ppb)
In general VOC detected in bedrock wells were also detected in overburden wells at the same
locations although the concentrations seen in the bedrock wells are significantly lower typically
by an order of magnitude relative to concentrations seen in the top-of-till wells The only
notable exception to this trend is at location MW108 where VOC were not typically detected in
the overburden wells (with the exception of an estimated 2J ppb of DCE detected once in
MW108S and once in MW108TT) At MW105 and MW107 VOC concentrations seen in the till
wells are similar to the low concentrations detected in wells screened in the underlying bedrock
The low VOC levels detected in bedrock wells located in the northern portion of the Study Area
demonstrate that bedrock is not a preferred pathway for contaminant migration This conclusion
is supported by the groundwater hydraulics data outlined in Section 3323 which demonstrate
that the average hydraulic conductivity of the bedrock is more than a factor of 200 less than the
overburden hydraulic conductivity In spite of the upward hydraulic gradient from bedrock to
overburden (factor of ten to 100 larger than the horizontal hydraulic gradient within the VOC
plume) which was found to exist throughout the Study Area vertical (transverse) dispersion
caused by flow in the bedrock fracture system has apparently caused VOC to migrate a limited
distance into the bedrock
5797wpdocsgalIuprifinaltextmasterrifhl061297 4-23 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4222 Semivolatile Organic Compounds
Tables 4-20 through 4-28 present the analytical results for SVOC in groundwater for the nine
sampling events Overall SVOC were detected infrequently and generally at only trace levels
Naphthalene 2-methylphenol and 12-dichlorobenzene were the most frequently detected SVOC
compounds in groundwater samples Naphthalene was detected during every sampling event
generally at MW105 MW107 and MW102 locations within the top-of-till wells and occasionally
also within till at well MW105T The highest naphthalene measurement was 10 ppb in
MW105TT 2-methylphenol was also detected during every sampling event always in well
MW107TT and with lesser frequency in MW105TT MW105T and MW102TT the highest
concentration detected was 3 ppb In eight of the nine sampling events 12-dichlorobenzene was
detected in at least one of the following wells MW102TT MW105TT MW105T MW107TT
and the maximum concentration measured was 4 ppb Maximum bis(2-ethylhexyl)phthalate was
detected in at least one well during six of the nine sampling events the concentrations ranged
from 04J to 35 ppb The locations of the bis(2-ethylhexyl)phthalate detections were sporadic it
was detected three times at MW108S twice at MW014S and MW116T and only once at eleven
wellsTrace levels of the following other compounds were detected during various sampling
events acenaphthene (03J ppb) butylbenzylphthlate (U ppb) di-n-butylphthlate (04J ppb) 4shy
chloroaniline (2J ppb) 24-dichlorophenol (U ppb) fluorene (06J ppb) 4-chloro-3-methylphenol
(2J ppb) phenanthrene (02J ppb) 4-bromophenyl-phenylether (2J ppb) n-nitroso-di-nshy
propylamine (9J ppb) 14-dichlorobenzene (up to 2J ppb) diethylphthlate (up to 04J ppb) 24shy
dimethylphenol (up to 8J ppb) di-n-octylphthlate (up to 46B ppb) 4 methylphenol (2J ppb) and
phenol (up to 4J ppb) The majority of these compounds occur in either the till or top-of-till
wells located within the VOC plume shown on Plates 4-6 and 4-7 (eg MW102 MW105 and
MW107) although there were infrequent detections of compounds at MW103 MW104 MW106
MW108 MW109 SW3D MW112 and MW116 as well
4223 Pesticides and PCB
The only detection of PCB in groundwater was during the April event when Aroclor 1242 was
detected in MW103S and TT at estimated concentrations of 042J and 018J ppb respectively
Estimated low levels of a few pesticides were detected in a small number of groundwater samples
Endosulfan I was detected once (002J ppb in MW107S during April 1995) Endrin was detected
once (00031 JP in MW109S during February 1996) methoxychlor was detected once (012J in
MW107S during February 1997) alpha-BHC was detected once in four wells (during February
1997 up to 0011 JP ppb) beta-BHC was detected twice up to 004J ppb (at MW107S in July
1995 and at MW107TT in February 1996) and gamma-BHC was detected in three samples up to
001JP (at MW105B and MW116S during November 1995 and at MW102S during August 1996)
All positive detections for pesticide and PCB compounds are shown on Table 4-29 (Note Table
5797wpdocraquogalluprifinflltextmasterriftil061297 4-24 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
4-29 only includes those sample IDs where a pesticide or PCB compound has ever been detected)
4224 Inorganics
Tables 4-30 through 4-38 present the analytical results for total (and where applicable dissolved)
metals in groundwater (During sampling low flow purging techniques were used to minimize
disturbance of formation water In cases where turbidity levels less than 5 NTU could be
achieved samples for both total and dissolved metals were collected Otherwise samples were submitted for total metals analyses only) Cyanide has not been detected in any groundwater
sample Metals were generally not detected in groundwater above applicable MCLs and metals
in groundwater samples across the Study Area were similar in concentration to metals detected in
designated groundwater background samples
Analytical results of a duplicate sample collected from MW107S during August 1996 had
anomalously high values Between January 1995 and August 1996 nine samples (seven rounds
plus two duplicate samples) were collected from this well and analyzed for total metals Only one
sample contained inorganic compounds in excess of EPA MCLs or Connecticut Remediation
Standards This sample which was the duplicate sample collected in August 1996 contained
elevated concentrations of aluminum chromium cobalt magnesium manganese and nickel In
order to evaluate the significance of this particular data set a statistical analysis for the
identification of outliers was performed following the procedures described in the EPA guidance
document Statistical Analysis of Ground Water Monitoring Data at RCRA Facilities (EPA530shy
SW089-026) For this analysis a test statistic (TJ was generated (using the average maximum
and standard deviation) from the nine samples for each inorganic analyte detected in this well If
the test statistic was greater than a critical value (1764) representing a 995 level of
significance then there is a strong likelihood that the maximum value for each data set is a statistical outlier If a given analyte was not detected in a given sample the detection limit2 was
used for statistical calculations
Maximum concentrations for nine of the thirteen analytes that have been detected in this well
were found to be statistical outliers Six of the statistical outliers were found in the MW107S
duplicate sample collected in August 1996 which suggests that the inorganic data from this
particular sample are not representative of groundwater quality in the immediate vicinity of this
well Although a specific reason why this sample contained such anomalously high levels is not
apparent it seems clear that this sample is not representative of the actual groundwater metal
concentrations at this location This is supported by the fact that the other sample from this well
on this date has metals concentrations consistent with previous sampling rounds Therefore the
metals data from this duplicate sample have been presented in this Report but are considered not
to be valid
5797wpdocBgalluprifinaltextmasterrifhl061297 4-25 QSTT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4225 DioxinsFurans and Additional Appendix IX Parameters
During the January 1995 sampling event samples from three locations (MW102TT MW106TT
and MW116T) were submitted for laboratory analysis for full Appendix IX parameters During
the April 1995 sampling event samples from MW105TT were also submitted for full Appendix IX
analyses The results for the VOC SVOC PesticidePCB and metals analyses for these samples
have been included in the appropriate tables as discussed in previous sections The results of
Appendix IX analyses that are not common to target analyte and target compound lists
(TALTCL) are discussed below Analyte groups specific to the Appendix IX lists include
herbicides (EPA Method 8150) volatiles by direct aqueous injection (EPA method modified
8015) Phenols (EPA Method 4202) Sulfide (EPA Method 3761) Organophosphorus Pesticides
(EPA Method 8141) PesticidesPCB by EPA Method 8080 and DioxinsFurans
The only detections for any of the analyte classes specific to Appendix IX compounds during the
January 1995 event were phenols (MW102TT at 7 ppb and MW116T at 15J ppb) During the
April 1995 event the dioxinfuran compounds HxCDD (total) and TCDF (total) were detected at
MW105TT at concentrations of 705 and 193 ngL (part per trillion)
423 Residential Wells
Residential wells were sampled during the Phase 1A investigation (January 1995) and again
during July 1995 February 1996 and August 1996 under the Long-Term Monitoring Program
4231 Volatile Organic Compounds
Tables 4-39 through 4-42 present the results of VOC analyses for residential well samples The
locations of these wells are shown on Plate 2-5 TCA was detected at DW114 during all four
sampling events and was also detected once at DW111 and DW113 the concentration ranged
from 018J to 066 ppb Chloroform was detected during three of the sampling events twice at
DW102 and once at DW104 and DW107 the maximum concentration detected was 19 ppb The
following compounds were also detected at low levels once bromodichloromethane (2 ppb at
DW107) dibromochloromethane (084J ppb) PCE (016J ppb at DW114) chloromethane (082J
ppb at DW103) and at DW111 ethylbenzene (025J ppb) toluene (012J ppb) and xylenes
(0 U) Since these locations are not downgradient with respect to the Site the occurrence of
these compounds in these wells are not likely to be Site related
4232 Semivolatile Organic Compounds
No SVOC were detected in any residential well sample during any of the four sampling events
5797wpdocsgalIuprifinaltextmasterrifhl061297 4-26 QT Environmental
Gallups Quarry Superjund Project - Remedial Investigation
4233 Pesticides and PCS
Tables 4-43 through 4-46 present the analytical results of pesticide and PCB analyses for
residential well samples Alpha-chlordane and gamma-chlordane were both detected in all four samples collected from DW105 and in three of the samples collected from DW106 The
maximum concentrations measured were 0095 ppb for alph-chlordane and 004 ppb for gamma-chlordane During August 1996 44-DDE and heptachlor epoxide were both also detected at
DW105 and DW106 (001J ppb for 44-DCE and up to 002J ppb for heptachlor epoxideNo PCB compounds were detected in any residential well The fact that DW105 and DW106 are not
downgradient relative to the site indicate that these compounds are likely attributable to the off-site use of these pesticides and are not site-related
4234 Inorganics
Tables 4-47 through 4-50 present the analytical results of metals and cyanide analyses for
residential well samples for the four sampling events Heavy metals were generally not detected
or were detected at trace levels Alkaline earth metals (eg Ca Mg K) were detected at levels
not unexpected for natural groundwater in the region
43 Surface Water Sediment and Wetland Soils Surface water sediment and wetland soils upstream adjacent to and downstream of the Site
were sampled and analyzed during the Phase 1A investigation to assess the potential if any for
transport of constituents of concern from the Site Sample locations are shown on Plate 2-6 Sediment was collected from one additional location (UB-6A) during the April 1995 sampling round As part of the Long Term Monitoring Program additional rounds of surface water
samples were collected during the April and November 1995 and May and November 1996
sampling events The samples were analyzed for VOC SVOC metalscyanide and pesticidePCB with the exception of the November 1996 samples which with EPA approval
were analyzed only for VOC and metals It is noted that following the Phase 1A sampling event
(September 1994) stations UB-1 UB-2 and UB-3 were eliminated from the Long Term
Monitoring Program (with EPA approval) as these locations are upstream of station UB-4 which
is also upstream from the Site Also station UB-6 (which was located on a tributary to Mill
Brook and sampled during the Phase 1A program) was replaced by station UB-6A (located within
Mill Brook) during the four Long-Term Monitoring events
431 Surface Water During September 1994 water quality indicators (pH dissolved oxygen temperature
conductivity turbidity) were measured in the field at eleven surface water sampling stations six
in Upper Mill Brook two in Lower Mill Brook (below the confluence with Fry Brook) one in
Fry Brook and two in Packers Pond The remaining six locations were dry at the time of
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 4-27 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
sampling As presented in Table 4-51 the water quality of the watershed as judged by both field
measurements and wet chemistry (TSS alkalinity hardness) was good to excellent It may
however be important to note that all of the samples were taken under fair weather conditions so
the influence of potential non-point sources during storm events cannot be assessed with this data
set Table 4-51 presents a qualitative assessment (eg slight moderate obvious) of potential
Local Non-Point Source Pollution As most sampling stations are either adjacent to or
downstream from developed (eg streets highways residences agricultural or industrial
property) the immediate andor cumulative impact of storm events cannot be evaluated in this
report During the four Long-Term Monitoring surface water sampling events field parameters
were again measured The results of these sampling events are shown in Table 4-52
During the September 1994 Phase 1A investigation surface water temperature ranged from 60 degF
(UB1 UB2) to 70degF (PP3) Surface water at most locations contained adequate concentrations of
dissolved oxygen ranging from 335 (UB2) to 1035 (UB8) mg1 but were slightly acidic with
pH varying from 528 (UB1) to 572 (PP3) Dissolved solids measured indirectly as specific
conductivity varied from 120 (UB1) to 710 (PP3) imhoscm
During the four Long-Term Monitoring sampling events surface water temperatures ranged from
526 to 617degF in April 1995 and 420 to 508degF in May 1996 to seasonally lower temperatures
of 396 to 453degF in November 1995 and 374 to 400degF in November 1996 The dissolved
oxygen concentrations were generally similar between the various sampling events ranging from
a low of 335 mg1 (at UB-2 in September 1994) to a high of 1030 mg1 (at PP-1 in November
1996) pH measurements indicated slightly acidic water with the following ranges 514 to 605
in April 1995 574 to 667 in November 1995 615 to 701 in May 1996 and 472 to 620 in
November 1996 Conductivity values were in the same general range between the different
sampling events with the lowest measurement of 1 anhoscm at PP-1 in November 1996 and the
highest measurement of 523 xmhoscm at UB-5 in April 1995
Based on laboratory results surface water in the area is fairly soft ranging in hardness (as
CaCO3) from 12 (TR-1 during April 1995) to 179 (UB2 during September 1994) mg1 and in
alkalinity from lt 1 (UBS during April 1995) to 67 (UB2 during September 1994) mg1 Total
dissolved solids and total organic carbon were below 200 ppm and 15 ppm respectively at nearly
every station during all five sample events A total of 58 total suspended solids analyses were
performed on samples collected during the five sampling events Most of the results were below
the detection limit and only 10 samples exceeded 10 mg1 The highest concentrations were
detected at UB-5 (between 82 and 2470 mg1 in the four samples collected at that location) and at
PP-1 (between 87 and 1500 mg1 in the three samples collected at that location)
5797wpdocraquogalluprifinaltextmasterrifhl061297 4-28 QST Environmental
Gallups Quarry Supcrjund Project - Remedial Investigation
4311 VOC- Surface Water
Data presenting he concentrations of various VOC for each individual surface water location are
presented in Table 4-53 through 4-57 for the September 1994 April and November 1995 and
May and November 1996 sampling events respectively VOC were not detected in the upstream
portion of Mill Brook Six VOC were detected at least once in the five rounds of surface water
samples collected from 11 locations The most consistent detections were 12-DCE and PCE in
Fry Brook sample FB-1 12-DCE was detected every round at FB-1 and occasionally at four
other locations up to 8J ppb and PCE was detected every round at FB-1 and occasionally at
three other locations up to 11 ppb Sample location FB-1 is approximately 1500 feet upstream
of the confluence of Fry Brook and Mill Brook the detections at FB-1 are not likely to be Site-
related and may result from nearby industrial activities The other detections of PCE and DCE
were at trace concentrations at locations below the confluence of Fry and Mill Brooks In
addition TCA was detected once at UB-10 at 3J ppb TCE was detected twice at FB-1 and once
at UB-9 up to 2 ppb carbon disulfide was detected in seven samples representing six locations
up to 20 ppb and toluene was detected twice at upgradient location UB-5 at 1J ppb All of the
VOC concentrations detected are well below those expected to cause adverse effects in fish or
wildlife (USEPA 1986)
4312 SVOC - Surface Water
During the September 1994 sampling event only low levels of one SVOC compound 4shy
methylphenol (28 ppb PP3 1 ppb UB2) were detected in surface water samples The locations
where SVOC were detected are far upstream (UB 2) and downstream (Packer Pond) locations and
are unlikely to have been impacted by the Site During the April 1995 sampling event the only
SVOC detected were trace levels of fluoranthene (04J ppb) phenanthrene (03J ppb) and pyrene
(04J ppb) all of which were detected at UB-5 which is upstream from the site There were no
SVOC detected in any surface water samples during the November 1995 event During the May
1996 sampling event bis(2-ethylhexyl)phthalate was detected in four samples at concentrations
ranging from 05J ppb to 140J ppb The locations of the detections are upgradient of the Site
(UB-5 and UB-8) and downgradient of the Site (LB-2 and PP-1) The sample from LB-2 also had
an estimated low level of di-n-octylphthalate (7J ppb) Table 4-58 presents all of the SVOc
detections in surface water samples (Note Table 4-58 only includes those sample IDs where a
SVOC has ever been detected)
4313 PesticidesPCBs - Surface Water
No pesticides or PCB compounds were detected in any surface water samples
5797wpdocsgalluprifinaltextmraquosterrifhl061297 4-29 Q5T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4314 Total and Dissolved Metals - Surface Water
Because of the ubiquity of naturally occurring metals in surface waters metals results are more
easily interpreted by generating descriptive statistics Descriptive statistics for metals measured in
surface water during 1994 and 1995 are presented in Appendix S Data presenting total and
dissolved metals concentrations for each individual sampling location during all five sampling
events are presented in Tables 4-59 through 4-65
Total Metals
Cadmium silver and thallium were not detected in any samples during the five sampling events
Other constituents detected in only one or two samples during each event include arsenic (up to
296J ppb) beryllium (once at 26B ppb) chromium (up to 764 ppb) cobalt (up to 26 IB ppb)
copper (up to 165 ppb) cyanide (up to 466 ppb) mercury (once at 018B ppb) nickel (up to
821 ppb) selenium (181J ppb at PP3) silver (once at 3J ppb) and vanadium (133 ppb) With
die exception of station UB2 during the September 1994 sampling event UB-5 during die April
1995 May 1996 and November 1996 events and PP-1 during the May and November 1996 events the remaining metals (aluminum barium calcium iron lead magnesium manganese
potassium sodium and zinc) were detected at concentrations that are expected in natural waters
(Hem 1989)
Dissolved Metals
Beryllium cadmium cobalt mercury selenium and thallium were not detected in any sample
Constituents detected infrequently and at low concentrations include antimony arsenic
chromium nickel silver vanadium and zinc Copper was detected at several locations upstream
and downstream from the site at concentrations ranging from 25 to 208B ppb although there
was no pattern in its occurrence or concentration Lead was detected at least once at each of the
sampling locations ranging in concentration from 1J ppb to 188 ppb The occurrences of lead
did not show a pattern die highest measurements were as follows 11 ppb at PP-3 in September
1994 188 ppb at UB-9 in April 1995 16J ppb at UB-4 in November 1995 56J ppb at UB-5 in
May 1996 and 91J ppb at UB-5 in November 1996 Locations UB-4 and UB-5 are upgradient
of the Site The lead detections in Packer Pond samples likely results from non-point sources to
Packers Pond The remaining metals (aluminum barium calcium copper iron lead
magnesium manganese potassium and sodium) were detected at concentrations that are expected
in natural waters (Hem 1989)
Concentrations of total and dissolved metals in surface waters were generally detected infrequently
and at concentrations below ambient water quality criteria ie those that would not pose a threat
5797wpdocsgalluprifinraquoItextmaBterriftil061297 4-30 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
to fish or wildlife (EPA 1986) Heavy metals such as copper and lead generally considered
harmful to aquatic life were detected at locations (Fry Brook and Packers Pond) that are not
likely to be impacted by the Site One location UB-5 (which was dry during September 1994)
contained elevated levels of most metals during the 1995 and 1996 sampling events This sample
station is located well upstream from the site on a tributary to Mill Brook which originates in a
small pond adjacent to Interstate 395 in a highly commercialized area
432 Sediment
A total of seventeen sediment samples were collected during the Phase 1A field survey
(September 1994) six of which were dry at the time The composition of the sediment samples
varied from deep muck (eg LB-02) to a firm sandy substrate (eg UBS) The total organic
carbon (TOC) content of the sediments (presented in Table 4-30) ranged from 075 (UB4) to 16
(PP1) percent with an average of 57 percent
4321 Inorganics - Sediment
Because of the ubiquity of naturally occurring metals in sediment these constituents are more
easily interpreted by generating descriptive statistics which are presented for each individual
metal in Appendix S Data presented for metals at each individual sampling location are
presented in Table 4-66
Antimony and thallium were not detected above the detection limit Beryllium cadmium
chromium cyanide mercury selenium and silver were detected infrequently and when detected
had concentrations close to the respective detection limit andor were detected at remote upstream
or downstream locations With the exception of maximum concentrations detected at PP3 (a
location at Packer Pond which receives stormwater runoff from Lillibridge Road) the remaining metals (aluminum arsenic barium calcium cobalt copper iron lead magnesium manganese
nickel potassium sodium vanadium and zinc) were detected at concentrations within the ranges
expected in naturally occurring soils or sediments (Beyer 1990 Fitchko 1989 Shacklette and
Boerngen 1984)
4322 VOC - Sediment
Analytical results for concentrations of VOC in sediment samples are presented in Table 4-41
VOC were generally detected infrequently and at relatively low concentrations in sediments
Ketones (acetone and 2-butanone) were detected at remote upstream (UB1 UB6) and downstream
(PP1 PP2 PP3) locations One or more of the compounds toluene trichloroethene methylene
chloride and xylenes were detected at trace levels at upstream locations north and east of the Site
(UB-3 UB-5 UB-6 UB-7 and UB-9) Xylenes were detected at a concentration of 31 pm in the
sediment sample from Fry Brook (FB-1) Only toluene at trace level of 0009J ppm was
5797wpdocsgalluprifinaltextma8terrifhl061297 4-31 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
detected in the sediment sample from UB-10 located in Mill Brook near the downgradient edge
of the Gallups plume No VOC were detected in sediment samples from downstream locations
LB-1 and LB-2
4323 SVOC - Sediment
As shown on Table 4-68 the primary SVOC constituents detected were PAH ranging from non-
detect (~ 03 ppm) to 15 ppm No apparent concentration gradient could be determined with
respect to location (eg upstream to downstream) The detections of PAH likely reflect non-
point contributions from local sources such as stormwater runoff from the railroad tracks and
nearby roads
Elevated concentrations of bis(2-ethylhexyl)phthalate were measured in Fry Brook (1300 ppm
FBI) and lower Mill Brook (64 ppm LB2) below the confluence of these two streams The
source appears to originate in Fry Brook
4324 PesticidesPCB - Sediment
Analytical results for pesticides and PCB are provided on Table 4-69 PCB compounds
(Arochlor-1242 -1254 and -1260) were detected in sediment samples from only three locations
all upstream (FB-1 at 019 ppm UB-8 at 0023J ppm and UB-7 at 00064J ppm)
Organochlorine pesticide compounds were also detected infrequently with no apparent trend with
regard to location or source The concentrations in sediment ranged from non-detect (~ 1-3 ppb)
to 39 ppb (methoxychlor at PP1) and their occurrence likely reflects residues of persistent
compounds that were routinely used for insect control before being banned from commercial
production
433 Wetland Soils
A total of 10 wetland soil samples were collected during the field survey most of which were
close to the water table at the time of collection The wetland sampling locations are shown on
Plates 2-6 and 3-14 The total organic carbon content (mgkg) of the wetland soils is as follows
QW1 (160000) QW2 (54600) QW3 (37200) QW4 (35200) QW5 (23900) QW6 (25600)
QW7 (gt 160000) QW8 (gt 160000) QW9 (33600) and QW10 (42600)
4331 Inorganics - Wetland Soils
Because of the ubiquity of naturally-occurring metals in wetland soils these constituents are more
easily interpreted by generating descriptive statistics which are presented for each individual
metal in Appendix S Analytical results for metals at each individual sampling location are
presented in Table 4-66
5797wpdocsgalluprifinaltextmasterrifhl061297 4-32 QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
Cadmium and cyanide were not detected in any sample Antimony arsenic beryllium cobalt
mercury selenium silver and thallium were detected infrequently and at trace levels at or below
the detection limit None of the remaining metals (aluminum barium calcium chromium
copper iron lead magnesium manganese nickel potassium sodium vanadium and zinc)
exceeded normal ranges expected for naturally occurring soils (Beyer 1990 Fitchko 1989
Shacklette and Boerngen 1984)
4332 VOC - Wetland Soils
Analytical results for VOC in wetland soils are provided on Table 4-67 VOC including acetone
2-butanone TCE and carbon disulfide were detected infrequently and at low concentrations
Acetone concentrations ranged from non-detect to 056 ppm (QW8) and 2-butanone concentrations
ranged from 0004 ppm (QW10) to 0067 ppm (QW8) QW8 is located in a remote wooded
location approximately 2000 feet west of the Site QW10 is located a few hundred feet west of
the southern portion of the Site
Acetone and 2-butanone were also detected at lower concentrations (015 and 0033 ppm
respectively) at location QW-1 several hundred feet southeast of the Former Primary Disposal Area A trace level of TCE (0004J ppm) was detected in wetlands soil sample QW-2 collected
approximately 50 feet east of the Former Primary Disposal Area This detection may be related
to the Former Primary Disposal Area since TCE has been detected in this area Based on the
topography however surface water runoff from the former disposal area is unlikely to impact the
wetland No other wetland soil samples had concentrations detected above the instrument
detection limit
Although the source of these VOC is unknown acetone 2-butanone and carbon disulfide are all
commonly used in the laboratory and may have been introduced during post-processing sampling
Some of these compounds are organic solvents that are (or were ) commonly used in many
household (eg spot removers paint strippers aerosols) commercial (eg pesticide
formulations inks and dyes) and industrial (eg degreasers) products Their presence in
wetlands soils samples at low concentrations may be the result of localized human activity in the
area
4333 SVOC - Wetland Soils
Analytical results for SVOC in wetland soils are provided on Table 4-68 The primary
constituents detected were the phthalate esters and PAH PAH were detected infrequently at
generally below 01 ppm Phthalate esters were also detected infrequently ranging from non-
detect to 22 ppm (QW8) The presence of these compounds is likely to be associated with
periodic or seasonal flooding of wetlands as the wetland sampling locations are remote and
5797wpdocsgpluprifinaltextma8terrifhl061297 4-33 QST Environmental
Gallups Quarry Superjimd Project - Remedial Investigation
generally inaccessible except on foot Since these compounds are relatively immobile except in
surface water or as airborne particulates these compounds may have originated from non-point
sources such as the railroad line or runoff from nearby highways
4334 PesticidesPCB - Wetland Soils
Analytical results for pesticides and PCB are provided on Table 4-69 PCB compounds
(Arochlor-1242 -1254 and -1260) were detected infrequently and at low concentrations
The presence of trace levels of PCB compounds in wetland soil samples QW-1 QW-2 QW-3
and QW-4 may be Site-related however PCBs are ubiquitous environmental contaminants that
were widely used in industry and may thus be present in soils as a result of past activities at
surrounding industries Other sources of input into the local environment might include
atmospheric deposition transport from upstream sources and deposition following flood events
Organochlorine pesticide compounds were also detected infrequently with no apparent trend with
regard to location or source The concentrations in wetland soils ranged from non-detect to 0016
ppm (44-DDE at QW1) and their occurrence likely reflects residues of persistent compounds
that were routinely used for insect control before being banned from commercial production
44 Air Quality 441 Baseline Air Quality Survey
Ambient air quality was determined prior to the start of Phase 1A intrusive investigations to
establish a baseline for air quality For the baseline survey air quality in the breathing zone
(between approximately three and six feet above the ground surface) was determined based on
measurements of total VOC (using a PID equipped with an 117 eV lamp) and respirable dust
(using a aerosol meter) at eight locations across the Site These eight stations were located at
each of the three known Former Disposal Areas and at upwind and downwind locations along the
perimeter of the Site The locations of the eight baseline air monitoring stations (AM1-AM8) are
shown on Plate 2-1 During the baseline survey no VOC readings were detected above the EPA
approved action level of 1 ppm at any of the eight monitoring locations Also no respirable dust
readings greater than the EPA-approved action level of 005 mgm3 were recorded during the
baseline survey at any of the monitoring stations
442 Perimeter Air Monitoring
Throughout the duration of the Phase 1A field investigations ambient air quality was monitored
on a weekly basis at the eight stations for the same parameters described above In addition to
the eight air monitoring stations continuous air monitoring was performed at each discrete
investigation area (eg each microwell soil boring etc) in the workers breathing zone and at the
5797wpdocsgaIIuprifinaltextmasterrifhl061297 4-34 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
perimeter of each task specific exclusion zone Air monitoring in the work zones was augmented
with instruments to measure hydrogen cyanide and lower explosion levels Also compound
specific calorimetric equipment (eg Draeger tubes) were used to compliment total VOC
measurements recorded with a PID
No readings above ihe EPA-approved action levels were recorded at the perimeter of the Site
throughout the entire duration of the Phase 1A investigation Elevated worker breathing zone
readings for total VOC were recorded during two of the four soil borings performed within the
Former Primary Disposal Area (SB109 and SB110) Varying but sustained elevated VOC
readings in the workers breathing zone during these two soil borings required the use of OSHA
Level C protection equipment These VOC vapors appeared to dissipate rapidly as no elevated
readings were recorded at the downward perimeter of the exclusion zone
Based on the baseline and periodic air monitoring performed during the investigation undisturbed
ambient air quality in the vicinity of the Site does not appear to have been impacted by former
disposal practices at the Site To confirm this compound specific air monitoring was performed
during the Phase IB investigation
As part of the Phase IB investigation quantitative air monitoring was performed in the vicinity of
the Former Primary Disposal Area The following compounds were detected in shallow soil
during the Phase 1A investigation and therefore were the target analytes for the air monitoring
performed during the Phase IB investigation toluene ethyl benzene total xylenes
tetrachloroethene and PCBs Data from the Phase IB investigation indicate that none of these
compounds were present at any of the air sampling locations for the duration (approximately eight
hours) of the sampling event The laboratory results of these analyses are presented in Appendix
T
45 Potential Sensitive Human Receptors The survey was used to identify any water supply wells schools nursing homes and day care
facilities including in-home day cares within a one-mile radius of the Site
Water Supplies
There are three community water companies serving portions of the Plainfield area within a one-
mile radius of the Site the Gallup Water Company Brookside Water Company and Glen Acres
Water Company The Gallup Water Company operates two wells located in downtown
Plainfield approximately 4000 feet north of the Site The Gallup Water Company presently
services approximately 700 households and three schools (Plainfield Middle School Plainfield
5797wpdocsgalluprifinaltextmlaquoraquoterriltinl061297 4-35 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Central and St Johns) The Brookside Water Company operates two wells located east of 1-395
on the corner of Dow Road and Colonial Road approximately 4000 feet northeast of the Site
The Brookside Water Company presently services approximately 225 homes The water service
lines for the Gallup and Brookside Water Companies are interconnected allowing mixing of the
waters The Glen Acres Water Company has two wells located approximately 2200 feet west of
the Site and services approximately 36 homes The majority of the area west south and east of
the Site and some properties north of the Site rely on individual private wells for their water
supply
One school is located within a one-mile radius of the Site This is the St John Building located
approximately 5200 feet north of the Site This school served students in grades Kindergarten
through eighth grade until 1995 after which the school operates only as a pre-school This
facility is serviced by the Gallup Water Company
Nursing Homes and Elderly Housing
One nursing home and one elderly housing facility are located within one mile of the Site The
Villa Maria Convalescent Home is located approximately 5000 feet north of the Site and is
served by the Gallup Water Company Lawton House Elderly Housing Apartments is located
approximately 4800 feet north of the Site and is also served by the Gallup Water Company
Day Care Facilities
There are eight in-home child day care facilities within a one-mile radius of the Site The
operators and locations are listed on Table 4-70 Only one of these facilities is serviced by a
private supply well That facility located at 134 Lathrop Road is located approximately 3500
feet southeast (upgradient) of the Site
5797wpdoc8galluprifinaltextmasterrifnl061297 4-36 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
50 Contaminant Fate and Transport
This section discusses the environmental fate and transport parameters associated with the
compounds detected during the Remedial Investigation Section 51 details the theoretical basis
for the evaluation of fate and transport characteristics In Section 52 Site-specific fate and
transport parameter values are presented and VOC migration rates and concentration variations
are discussed
51 Theory Migration persistence and relative distribution of compounds between air water and soil depend
on both hydrogeologic and compound-specific parameters The following discussion addresses
each of these parameters as they may affect behavior of compounds within the Study Area
511 Advection by Groundwater Flow
Within a porous medium (soil) the advection rate of dissolved or aqueous-phase compounds
under transient conditions is based on Darcys law (Bear 1979)
where
v= average pore velocity (lengthtime)
K= hydraulic conductivity (lengthtime)
i= hydraulic gradient (lengthlength or dimensionless) which equals
the piezometric head difference between two points on a
groundwater pathline divided by the distance between the two
points
n= effective or drainable porosity (volume of voidstotal soil volume)
of the soil approximately equal to the specific yield
Rj= retardation factor (R gt_ 1) a dimensionless parameter that
represents the ratio of groundwater pore velocity to the actual
advection rate in a sorbing (onto immobile soil grains) porous
medium under transient concentration conditions
5797wpdoc8glaquolluprifinaltextmasterriftil061297 5-1 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
5111 Sorption
The retardation factor Rj represents the attenuation of a plumes frontal advancement due to
sorption ie temporary storage on soil grains Examples of analyses for which retardation
must be considered include (1) calculation of the time required for contamination to reach a given
downgradient location and (2) determination of the time required to remediate a contaminated
aquifer The retardation factor is defined by the following relationship (Freeze and Cherry
1979)
where pb is the bulk dry density of the soil (massvolume) n is the effective porosity of the soil
(volume of voidstotal soil volume) and K^ is the soil-water partition coefficient (volumemass)
often referred to as the distribution coefficient
The soil-water partition coefficient is the relative magnitude of the chemical concentration on solid
particles and in pore water for a particular soil (Lyman et al 1982)
C = AT C
where
C = concentration of the compound sorbed to the solid phase of the soil (mass
chemicalbulk dry mass soil) and
Q = concentration of the compound in the pore water of the soil (massvolume)
In this expression it is implicitly assumed that an equilibrium exists between the solid and water
phases and that the sorption process is linear (Freundlich isotherm with exponent equal to unity)
over the range of concentrations considered
For non-ionic organic compounds such as VOC Kj can be estimated from the measured fraction
of organic carbon naturally occurring in the soil fx (grams organic carbongram dry soil) and
the organic carbon sorption coefficient K^ (Tinsley 1979) as long as f^ gt_ 0001
5797wpdocsgalluprifinaltextmasterrifnl061297 5-2 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Values of K for many common organic compounds are available in the literature K is also
related to the octanol-water partition coefficient K^ for which a large data base is also available
(eg Hansch and Leo 1979) For fine-grained soil particles K and K^ can be related as
follows (Karickhoff et al 1979)
Kx = 063
Chemical-specific relationships between K and K^ also exist for several VOC (eg Lyman et
al 1982) K values for VOC in the Study Area are presented in Table 5-1
5112 Transport by Dissolved Organic Carbon
For certain families of organic compounds the presence of dissolved organic carbon (DOC) in
groundwater can partially reverse the sorption process to soil particles and release sorbed
constituents to groundwater As a result the migration of these compounds under certain
circumstances can be enhanced (Enfield and Bengtsson 1988) Increases in mobility are greatest
for very hydrophobic (high K) compounds such as pesticides polycyclic aromatic hydrocarbons
(PAH) and dioxins Due to their characteristically low K^s VOC transport in groundwater is
generally unaffected by partitioning to DOC unless DOC concentrations exceed 10000 mgL
(Enfield and Bengtsson 1988) Typically natural DOC concentrations in groundwater range
from 1 to 10 mgL
512 Dispersion
Dispersion is a dilution process by which an initial volume of aqueous solution continually mixes
with increasing portions of the flow system Dispersion occurs on a small or microscopic scale
due to molecular diffusion in the water phase nonuniform velocity distributions within the pore
space and to a large degree the tortuous pathlines that groundwater follows during movement
through interconnected soil pores of different sizes and shapes On a macroscopic scale
dispersion results from geologic heterogeneities such as layers and lenses of contrasting soil type
(ie hydraulic conductivity) In practice dispersion is primarily due to variations in hydraulic
conductivity which produce large gradients in advective transport It is well known that aquifers
contain horizontal layers or lenses of coarser and finer grained materials compared to the average
material type that can result in zones of significantly higher and lower hydraulic conductivity
respectively than the screen interval value determined from pumping and slug tests Factor of
ten hydraulic conductivity variations or more over the thickness of an aquifer are not uncommon
5797wpdocsgalluprifinaltextmasterrifhl061297 5-3 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
(Freyberg 1986 Gelhar et al 1985 Robertson et al 1991 and Sudicky et al 1983) For
contaminant transport the more permeable zones are more important because they determine the
maximum distance over which dissolved constituents will migrate from the source area
With respect to chemical migration from a source area to an arbitrary downgradient location
dispersion will cause contaminants to arrive in a shorter time interval than the travel time based
on the mean groundwater pore velocity (Section 511) This reduced travel time associated with
dispersion is due to advection in the zones of higher hydraulic conductivity that cause the
concentration distribution in the longitudinal (flow) direction to spread out or disperse The
additional length Ld that a chemical may migrate due to dispersion can be estimated from the
following relationship (Bear 1979)
where
t = total time of groundwater travel (= VL^ laquo
Rj = retardation factor
DL = longitudinal dispersion coefficient (length 2time)
In a porous medium the longitudinal dispersion coefficient can be estimated as follows
DL =
where
v = groundwater pore velocity
aL = longitudinal dispersivity of the aquifer (length)
The percent reduction in travel time along a pathline due to longitudinal dispersion can be
calculated using the equation (Bear 1979)
where
At = reduction in travel time along a pathline due to longitudinal dispersion ()
5797wpdocsgalluprifinaltextmasterrifhl061297 5-4 QST Environmental
Gallups Quarry Superfond Project - Remedial Investigation
A t = mdash- 100 ^total
Ld = additional distance (in excess of advection distance) that chemical migrates due to
longitudinal dispersion
= total distance of travel by mean advection (average groundwater flow rate)
An excellent summary of estimated longitudinal dispersivity values for numerous sites is given by
Gelhar et al (1985)
513 Advection Due to Fluid Density Differences
Advective transport can also occur due to fluid density differences in cases where the total
dissolved solids (TDS) concentration is very high A typical example is salinity intrusion into an
aquifer where the greater density of the salt water (TDS 35000000 ppb) causes it to sink within
the fresh water aquifer This causes downward advection of groundwater and results in
stratification of the aquifer into varying zones of salinity However density effects can be caused
by any dissolved compound if the concentration is high enough Laboratory experiments have
shown that density effects do not begin to be observed until the total dissolved concentration in a
plume exceeds background levels by about 1000000 to 5000000 ppb (Schincariol and
Schwartz 1990 Schwille 1988) As a result fluid density effects are not important in the Study
Area
514 Biological and Chemical Degradation
In recent years groundwater scientists have begun to understand the role of microorganisms in
the subsurface transformation of organic chemicals Recent studies have shown that large numbers of organisms can exist in the subsurface environment In many cases organic compounds can be completely degraded to harmless products However by-products can also be
produced which are more mobile and toxic than the parent compound These transformations can
make it difficult to correlate groundwater contamination with particular sources Quantitative
predictions of the fate of biologically reactive chemicals are approximate at best This is due to a
lack of understanding of the biochemical transformation process and variability of transformation
rates in an aquifer (eg as much as two orders of magnitude over a distance of less than 1 m)
For example Wood et al (1980) have demonstrated in the laboratory and observed in the field
the following anaerobic transformations of parent compounds to daughter products
5797wpdoc8galluprifinaltextmasterriftJ061297 5-5 QST Environmental
Gallups Quarry Superfiind Project - Remedial Investigation
carbon tetrachloride -bull chloroform -raquo methylene chloride
trans-12-d ichloroethene
PCE -bull TCE - cis-l2-dichloroethene - vinyl chloride
11-dichloroethene
111-trichIoroethane -raquo 11-dichloroethane - chloroethane
The transformation of PCE (tetrachloroethene) and TCE (trichloroethene) to vinyl chloride is an
example of a transformation to a daughter compound which is considerably more toxic than its
parent compound
Persistence in the environment can be described by a parameter known as the environmental
half-life of a compound The environmental half-life tQ is related to a decay constant X
(Itime) in a first-order decay process
X = ln(2)tm
where ln(2) = 0693 The product of the decay constant and the porewater concentration is equal
to the rate (masstimeunit volume) at which a compound degrades into another form of
compound In practice the parameter half-life is an empirical parameter that quantifies mass loss
due to biological photochemical chemical or physical (eg volatilization) degradation
mechanisms
Within the subsurface biological activity is believed to be the principal cause of the
mineralization (ie transformation to inorganic constituents) of organic compounds (Alexander
1978) Hydrolysis is the reaction of compounds with water or the hydroxide or hydromium ions
associated with water However organic functional groups such as halogenated organics (eg
TCE TCA PCE) ketones benzenes and phenols are generally resistant to this mechanism
(Lyman et al 1982) Oxidation (loss of electrons during a chemical reaction ) and reduction
(gain of electrons during a chemical reaction) can also alter and attenuate organic compounds
For most inorganic compounds geochemical transformations are the most important degradation
mechanisms Due to the complexity of degradation processes and the fact that little data is
typically available to adequately model the loss mechanisms prediction of decay rates in the field
as discussed above is very difficult and not often feasible especially for biodegradation
5797wpdocsgalluprifinaltextmasterrifnl061297 5-6 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
515 Volatilization
The Henrys law coefficient H (Morel 1983) is an air-water partition coefficient which relates
the equilibrium concentrations in air and water for volatile compounds in a multi-phase system
such as the unsaturated zone of the subsurface or the air-water interface of a water body
H = C 1C
where C and eurobdquo are the chemical concentrations in air and water respectively The coefficient is
used in the calculation of volatilization from a water body or soil and for the determination of
solids water and air concentrations resulting from chemical partitioning in a contaminated
unsaturated soil
Organic compounds with Henrys law coefficients greater than 103 atm-m3mole are generally
considered to be highly volatile These compounds can volatilize relatively rapidly from water at
air-water interfaces such as surface water bodies or groundwater tables However the rate of
volatilization is also controlled by diffusion in the water phase Table 5-1 summarizes values of
the Henrys law coefficient for selected organic constituents detected in the Study Area
516 Aqueous Solubility
The solubility of a compound in water is the maximum amount of that compound that will
dissolve in a unit volume of pure water at a specified temperature Water solubility is one of the
most important fate and transport parameters Highly soluble compounds tend to have relatively
low KK values and Henrys law coefficients and tend to be more readily biodegradable by
microorganisms in soil Table 5-1 lists solubilities for VOC detected in the Study Area
52 Study Area-Specific Characteristics 521 Retardation Factors
A Site-specific evaluation of chemical migration rates in groundwater was conducted by
measuring the total organic carbon content TOC of 31 soil samples from the northern Study
Area (Table 5-2) The parameter f (Section 51) is equal to TOC expressed as a fraction As
discussed in Sections 26 and 2721 an ASTM method was used to measure the 4 of the 28
samples from the Former Primary Disposal Area (SB-series borings) EPA Method 9060 was
used to analyze the three samples from the boring for well MW102B The fK measurements for
the SB-series soils samples range from less than 00015 to a maximum of 0023 and the
geometric mean is 00023 In these calculations values below the detection limit of 00015 were
assigned one-half the detection limit These f^ values are typical of high hydraulic conductivity
sand and gravel aquifers
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 5-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The measured values for the three MW102B samples are uncharacteristically low for coarse
stratified drift The geometric mean of these samples is 0000014 which is a factor of 100 lower
than the SB-series data The discrepancy appears to be due to the fact that EPA Method 9060 is
designed for TOC analysis of water samples The f values for the three MW102B samples are
expected to be on the order of 0001 based on comparisons with organic carbon values for
samples of a similar lithology from the Gallups Quarry and other sites Furthermore as
discussed by Karickhoff et al (1979) the available correlations that relate f^ to retardation factor
Ra are not valid below f = 0001 Below values of f = 0001 mechanisms other than
sorption to organic carbon (eg chemical adsorption to mineral surfaces) begin to dominate with
the result that overall sorption and retardation of VOC do not decrease even though the TOC
content of the aquifer materials does Therefore if f^ lt 0001 researchers have indicated that
in many cases calculations of Rd can use f^ = 0001 to account for these alternative sorption
mechanisms For these reasons the SB-series f^ data that are representative of coarse stratified
drift were used in the transport evaluations discussed in the following sections
The average f^ for the SB-series soil samples located below the water table were also calculated
to evaluate vertical trends in the data These samples include
Sample Depth (feet bgs) TOC (mgkg)
SB 104 15-17 lt1500
SB104 26-28 1700
SB108 6-8 lt1500
SB 109 4-8 1600
SB109 10-16 lt1500
SB109 17-24 1500
SB109 24-32 1600
The geometric average f for these samples is 00012 if one-half the detection limit is used for f
lt 00015 Because this average excludes shallow samples with larger silt contents it is
considered more representative of the higher hydraulic conductivity coarse-grained soils which
primarily control groundwater transport
Table 5-1 summarizes chemical-specific retardation factors for VOC detected in Study Area
groundwater These estimates are based on a f value of 00012 which as discussed above is
near the minimum value appropriate for the calculation of R Actual retardation factors in the
aquifer will be nonuniform due to the inherent variability of soil organic carbon content For
example retardation factors based on an f of 00012 may be more appropriate for evaluation of
5797wpdocsgalluprifinaltextmasterri fal061297 5-8 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
transport rates in the middle to lower portions of the aquifer where the soil is generally coarser
and contains less silt which is associated with the organic carbon content Conversely the
average value of 00023 for all samples is likely more representative of soils in the upper portion
of the aquifer and above the water table In any case this overall variability in f^ values for the
aquifer is considered to be smaller in magnitude than the natural variability in hydraulic
conductivity values for the site The recent detailed field investigations in sand and gravel
aquifers referenced in Section 512 have shown that it is not uncommon for hydraulic
conductivities to vary by as much as a factor of ten over a scale of a few feet Variations in both
f and hydraulic conductivity values impact predicted chemical transport rates (Section 511)
A bulk dry density of 18 gcm3 and an effective porosity of 025 were estimated from the
literature based on soil grain size analyses Potential variability associated with these parameters
is small compared to k^ estimates and is not important for the following transport rate evaluation
The results in Table 5-1 are useful for comparing relative mobilities for different compounds and
assessing contaminant migration rates relative to groundwater pore velocities 11-dichloroethane
is expected to be the most mobile VOC while PCE and ethyl benzene should be the least mobile
The tracer compounds TCA and DCE are expected to migrate about a factor of two slower than
the groundwater with DCE migration being the fastest
522 Chemical Migration Rates
5221 Groundwater Travel Times
Compound-specific migration rates in the overburden aquifer were examined using Darcys law
(Section 511) to compute groundwater pore velocities from (1) measured horizontal hydraulic
gradients defined by the November 1995 piezometric surface maps (Section 332) (2) the
hydraulic conductivity data (Table 3-1) and (3) estimated retardation factors (Table 5-1) The first step was to construct a map of groundwater times-of-travel along the various pathlines shown
on the groundwater flow maps for the southern Study Area (Plate 3-9) and for the lower portion
of the aquifer in the northern Study Area (Plate 3-8) Groundwater travel times along each of the
pathlines were modelled using the Tecplot software and the interpolated piezometric head
distribution to define the continuous horizontal hydraulic gradient distribution Additional
information regarding pathline computation using Tecplot is provided in Appendix Q Since the
more permeable zones in an aquifer are known to control the rate of advancement of a plumes
leading edge (Section 512) the upper bound hydraulic conductivity estimates from Table 3-1
were considered From a review of these measurements it was determined that a mean hydraulic
conductivity of 004 centimeters per second (115 feet per day) would be reasonable to use in the
time-of-travel computations in the northern Study Area because this value is representative of the
more permeable coarse-grained soils north and northwest of the Former Primary Disposal Area
(ie wells MW102TT MW103TT MW104TT MW117TT and MW118TT) A lower
5797wpdoc8galluprifinaltextmlaquosterrifhl061297 5-9 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
hydraulic conductivity of 00025 cms (7 ftday) representing the geometric mean value for wells
MW114TT and MW115TT was selected for the southern Study Area An effective porosity of
025 was used in the calculations
The travel-time analysis results are shown in Plate 5-1 Markers denoting half-year (northern
Study Area) and five-year (southern Study Area) travel-time intervals have been placed on each of
the pathlines to allow evaluation of spatial variations in groundwater pore velocity and
determination of total groundwater travel-time between different locations The time period
required for a particular VOC to migrate along a pathline can be estimated as the product of the
groundwater travel-time and the compound-specific retardation factor listed in Table 5-1
5222 Groundwater Flushing Rates
Another useful relationship to consider when evaluating chemical migration is the time period
required to reduce the concentration in a specific portion of an aquifer by groundwater flushing
Assuming that source material is no longer introducing contamination into the portion of the
aquifer (ie control volume) being evaluated the US EPA Batch Flushing Model (EPA 1988)
provides such a relationship
p v = J V h )
where In is the natural logarithm to the base e Rd is the retardation factor C0 is the initial or
starting average groundwater concentration in the control volume Q is the final average
concentration and Pv is the number of groundwater pore volumes which have flowed through the
control volume Pv can be estimated as
P =-raquo v Ltotal
where v is the groundwater pore velocity (Section 511) t is the time duration being considered
and L^ is the total distance or length along a characteristic pathline (from upgradient to
downgradient) through the volume of aquifer material The model assumes complete mixing of
contaminants (ie infinite dispersion) within the control volume Brusseau (1996) demonstrated
that in part due to this assumption the Batch Flushing Model can partially account for
nonequilibrium desorption (ie delayed release) of VOC from soil
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 5-10 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
For example the southern Study Area (area south of the Former Seepage Bed) can be considered a control volume with a characteristic groundwater flushing rate In this area a time t of order 10 years is required for groundwater to flow through a distance L^ of about 400 feet thus indicating an average pore velocity v of about 40 feet per year In other words one pore volume of groundwater flushes through the overburden deposits in the southern Study Area in approximately 10 years From the Batch Flushing Model it can be seen that for a nonsorbing compound with R = 1 23 pore volumes [ln(10)] would need to flush through this area to lower average concentrations by a factor of ten assuming no source material remained east of the southern Study Area or above the water table 46 pore volumes would be needed for a factor of 100 reduction Since each pore volume roughly corresponds to 10 years the factors of 10 and 100 concentration reductions would require time periods of about 23 and 46 years respectively If however one were considering a compound with R = 3 the corresponding times would be about 70 and 140 years
5223 Discussion In the northern Study Area three areas of characteristically different horizontal hydraulic gradients exist in the overburden aquifer The steepest gradients (on the order of 0025 feet per foot) are found south of the former disposal areas Assuming the hydraulic conductivity in this area is 004 cmsec Plate 5-1 shows that the groundwater travel time through this portion of the aquifer is expected to be much less than one year However hydraulic conductivity data and soil descriptions suggest that a more representative hydraulic conductivity value for the till deposits in this area would be 0001 cmsec or less which would correspond to a travel time of five years or more (eg from MW109 to the Former Primary Disposal Area)
Northeast of well MW116 north of Mill Brook and in the vicinity of the former Pervel flock plant the hydraulic gradient is about 0007 feet per foot and a hydraulic conductivity of 004 cmsec is representative of the aquifer As a result the largest groundwater pore velocities are expected to exist in these areas For example as shown in Plate 5-1 the expected groundwater travel time is about one to two years from the vicinity of Pervel to MW116 and from Pervel to MW101
Groundwater travel times downgradient from the Former Primary Disposal Area are much longer due to the low hydraulic gradients northwest of the railroad tracks In the vicinity of MW105 and MW102 the gradient is about 00003 feet per foot or more than a factor of 20 less than the gradient northeast of this area For example the estimated groundwater travel time (ignoring longitudinal dispersion) from MW107 to MW102 near the front of the VOC plume is about 8 to
10 years By comparison almost 20 years has passed since the documented disposal in the late 1970s Based on the retardation factors (Table 5-1) for TCA (R = 23) and DCE (R = 14)
5797wpdocsgalluprifinaltextmasterrifhl061297 5-11 QS7 Environmental
Gallups Quarry Superand Project - Remedial Investigation
the estimated travel times for these compounds from MW107 to MW102 are about 20 years and
13 years respectively Considering these chemical migration rates and the fact that TCA and
DCE were detected at quantifiable levels along the VOC plume centerline and at location
MW102 it appears reasonable to conclude that these compounds are associated with the former
disposal areas
However as discussed in Section 4221 the present PCE distribution in groundwater exhibits
inconsistencies with migration from the former disposal areas Although historical detections of
PCE were found in well cluster SW17 which is located downgradient from the Former Primary
Disposal Area and near well cluster MW105 the concentrations had reduced from a maximum of
1000 ppb in 1980 to near the detection limit by early 1993 (Section 523) Based on this rate of
reduction PCE concentrations at diis location would be expected to have fallen below or near the
detection limit by 1995 In fact only trace levels were detected in wells MW105TT and
MW105T during two of the four 1995 sampling events Furthermore the measured groundwater
flow directions in the overburden aquifer indicate that many of the pathlines originating near the
former Pervel flock plant pass through the vicinity of wells MW117 MW118 MW119 MW116
MW103 MW102 and MW101 Although MW101 and MW102 are downgradient from both
Pervel and the former disposal areas groundwater flow conditions in the past would need to have
been different from present conditions for MW116 and MW103 to be downgradient from the
former disposal areas As discussed in Section 4 elevated levels of PCE TCA and DCE have
been detected in monitoring wells located on the former Pervel property Also PCE TCA and
DCE were detected in wells MW116T MW118TT and MW103TT located downgradient from
Pervel during the 1995 sampling rounds and PCE TCE and DCE were detected in well MW-C
on the former Pervel property The travel time of these compounds from Pervel to wells
MW116 MW118 MW103 MW102 and MW101 is estimated to be two to six years Taking
this into consideration along with the VOC detections in the Pervel wells during the period 1987
to 1989 (Section 523) it is possible that the low-level PCE TCA and DCE detections in
MW116T MW118TT and MW103TT represent the last remaining portion of a Pervel VOC
plume The lack of VOC detections in wells MW117 and MW119 could be explained by dilution
in these areas or by the fact that these wells may not be immediately downgradient from the
historical source area(s) on the former Pervel property
The migration rate of PCE compared to the disposal area tracer compounds TCA and DCE also
supports the existence of an off-site PCE source The expected migration rate of PCE is a factor
of two to four slower than that of TCA and DCE due to their differing K values Assuming all
of these VOC were released within a few years of each other the leading edges of the TCA and
DCE plumes should be much farther downgradient than the PCE plume Instead as evidenced by
the data shown in Plate 4-6 the opposite is true because a PCE concentration of about 30 ppb has
5797wpdocsgalluprifinaltextmasterrifnl061297 5-12 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
been detected at MW101 In terms of groundwater migration (not including retardation) from the
Former Primary Disposal Area the elevated PCE concentrations at location MW101 would
represent a total travel-time from the former disposal areas which is more than a factor of two
greater than that required for the leading edge of the TCA-DCE plume to reach MW102
Comparing the relative mobilities of PCE TCA and DCE (Table 5-1) the time required for PCE
to migrate from the Former Primary Disposal Area to well MW101 should be more than a factor
of four to eight longer than the TCADCE travel time to MW102 Based on this comparison the
PCE detections at MW101 could be attributed to transport from Pervel It is also possible that
the Pervel groundwater contamination has impacted the MW102 area Although the PCE
detections at locations MW102 and MW101 could be attributable to historical releases from the
former disposal areas the above findings (flow directions spatial PCE distribution travel times)
suggest that contamination from the former Pervel facility has at a minimum contributed to VOC
contamination (PCE and possibly DCE and TCA) at these locations
The above discussion also highlights the important issue of what defines the leading edge of the
zone of VOC contamination in the overburden aquifer Several of the above findings suggest that
the downgradient extent of VOC contamination associated with the former disposal areas is
located near wells MW102 and MW101 The convergent nature of the groundwater flow patterns
in the northern Study Area clearly establish a narrow well-defined preferred pathway of low-level
contaminant migration from the Former Primary Disposal Area The chemical analysis results
from the monitoring well sampling program confirm the measured flow directions Further
whereas TCA and DCE can presently be traced continuously along the plume centerline at
elevated levels (well locations MW107 MW105 and MW102) PCE cannot These findings
suggest that the PCE contamination in groundwater may be attributable to the former Pervel flock
plant and should not be used solely to define the leading edge of the VOC plume The time-ofshy
travel computations support the location of the disposal area VOC plume between MW102 and
MW101 The reduction of TCA and DCE concentrations to less than 10 ppb and the decrease of
xylene to below detection at MW101 is also consistent with the interpretation that the disposal
area VOC plume does not extend far beyond MW102 In addition the groundwater pore velocity
in the vicinity of wells MW102 and MW101 is estimated to be about 50 feet per year which is as
much as a factor of 20 lower than rates upgradient from this area Based on this pore velocity
and the retardation factors in Table 5-1 the migration rates of TCA and PCE are expected to be
about 20 and 10 feetyear respectively At these rates the estimated travel times for TCA and
PCE from MW102 to MW101 are about 20 and 35 years respectively As discussed in the
following section given the relatively large rates of historical VOC concentration reductions
which have been observed in the northern Study Area it is expected that PCE 12-DCE 11shy
DCE and TCE levels near MW102 will fall below MCLs within the above 20- to 35-year period
due to biodegradation and dilution mechanisms Reduction rates for vinyl chloride which also
5797wpdocsgalluprifinaltextmlaquoraquoterrifhl061297 5-13 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
has been detected above MCLs near MW102 will likely lag behind the other VOC because it is a
final chlorinated breakdown product
523 Time-Dependent Concentration Reductions
5231 Observed Concentration Changes
Significant groundwater concentration reductions with time have been observed in the northern
Study Area from the late 1970s through the 1995 sampling rounds To illustrate these temporal
trends concentration data for selected VOC were plotted versus time to quantitatively evaluate the
reduction rates The observed rates of concentration reduction are also compared to predicted
values using the groundwater flushing relationships presented in Section 5222 and are evaluated
to determine site-specific estimates of biodegradation rates
Figures 5-1 through 5-3 contain the concentration vs time graphs for three groups of wells
organized according to transport characteristics and location Group 1 (Figure 5-1) immediately
downgradient from the former disposal areas (SW17S SW17D SW13 MW107TT MW105S
and MW105TT) Group 2 (Figure 5-2) within the downgradient portion of the VOC plume
(MW102S MW102TT MW101TT) and Group 3 (Figure 5-3) the area northeast of the VOC
plume and downgradient from the former Pervel flock plant Data from the Group 1 wells
provide a good historical perspective on improvements in groundwater quality resulting from
source removal activities in the late 1970s and from ongoing biodegradation and rainwater
infiltration (flushing) within the Former Primary Disposal Area The Group 2 wells are located
within the downgradient portion of the VOC plume and in a section of the aquifer where the
hydraulic gradient and associated groundwater transport rates are up to a factor of 20 lower than
in other parts of the northern Study Area Group 3 wells are downgradient from the former
Pervel facility where elevated levels of PCE and TCA have been detected and are located in the
portion of the aquifer with the highest groundwater flushing rates
5232 Evaluation of Concentration Reduction Rates and Mechanisms
The most important aspect of the semilogarithmic plots in Figures 5-1 to 5-3 is the characteristic
slope or trend of the concentrations as a function of time Specifically it can be seen that many
of the graphs exhibit an almost straight-line decrease in concentration with time This linear
variation is often observed with historical groundwater quality data because the linearity has a
physical basis First many biodegradation mechanisms can be modelled as a first-order decay
process (Section 51) which produces a straight-line decrease in concentrations on a semi-log plot
Second flushing of clean groundwater (eg rainwater infiltration or uncontaminated
groundwater) through a contaminated volume of aquifer material has been shown (Section
5222 Brusseau (1996)) to exhibit the same type of response In both of these approximate
first-order processes the slope of the straight-line response is inversely proportional to the
5797wpdocsgalluprifinaltextmasterrifhl061297 5-14 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
environmental half-life (Section 514) for that mechanism and a particular chemical compound
Using the relationships developed in Section 5222 the environmental half-life associated with
groundwater flushing can be defined as
Substituting the expression for pore volume Pv the flushing half-life can also be written
From the above expression it can be seen that the flushing half-life for a particular compound is
directly proportional to the chemical retardation factor and inversely proportional to the
groundwater pore velocity The groundwater flushing rate represents the rate at which
concentrations in a particular portion of the aquifer are reduced In contrast to biodegradation
groundwater flushing does not reduce the total mass of a compound in the aquifer because the
contaminants are advected to downgradient areas
In the Group 1 area historical VOC data for the SW-series wells (Metcalf amp Eddy 1993) (eg SW13 and SW17) summarized in Table 5-3 and on Figure 5-1 show that TCA TCE and PCE
levels in groundwater downgradient from the Former Primary Disposal Area have typically
decreased by a factor of more than 100 from the late 1970s to 1993 Using the SW17S data
from 1980 to 1993 the estimated environmental half-lifes for TCA TCE and PCE are
approximately 15 20 and 24 years respectively From February 1993 through the present the
shallow concentration reduction rates (SW17S and MW105S) are much higher corresponding to TCA TCE PCE and DCE environmental half-lives of about 03 lt 1 03 and 04 years
respectively Concentration reduction rates in the lower portion of the aquifer (SW17D and
MW105TT) from February 1993 through the end of 1995 are a factor of two to three slower than
shallow rates the estimated environmental half-lifes for TCA PCE and DCE in the deep aquifer are about 06 09 and 09 years respectively The higher concentration reduction rates in the
shallow aquifer may be due to rainwater infiltration andor increased biodegradation These
decreases in VOC levels are likely due to a combination of (1) source removal and source
depletion (ie soil concentration reduction by flushing mechanisms) within the former waste
disposal areas (2) mixing of rainwater infiltration with groundwater which can be a significant
dilution mechanism in the wetland areas as evidenced by the frequent occurrence of ponded water
and (3) biodegradation by microorganisms in soil
5797wpdoc8galluprifiiialtextmlaquoraquoterrifhl061297 5-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Vinyl chloride does not follow the same trends of reducing concentrations exhibited by the other
chlorinated VOC Vinyl chloride concentrations in wells MW107TT and MW105TT generally
increased during the 1995 sampling rounds Since this compound is the final chlorinated
breakdown product of PCE TCE and DCE it appears that the vinyl chloride detections are the
result of biodegradation The apparent increase in vinyl chloride concentrations and decrease in
DCE levels in well MW107TT may be further evidence that vinyl chloride detections are
associated with biodegradation mechanisms
The observed Group 1 environmental half-lifes are consistent with predicted half-lifes due to
groundwater flushing From Plate 5-1 the estimated groundwater travel time from MW107 to
MW105 is 05 to 1 year which corresponds to 1 to 2 groundwater pore volumes per year
flushing through the Group 1 Area Using the retardation factors in Table 5-1 the predicted
flushing half-lifes for DCE TCA and TCE range from 05-10 08-16 and 07-14 years
respectively and the flushing half-life for PCE is between 14 and 3 years This good agreement
between observed and predicted rates of concentration reduction downgradient from the former
disposal areas is additional evidence that source removal activities were successful and natural
mechanisms are actively producing further reductions in contaminant levels The fact that deep-
aquifer PCE and TCA concentrations near MW105 have decreased more rapidly than predicted
groundwater flushing rates during the period 1993 to 1995 suggests that biodegradation is
breaking down these parent compounds Furthermore TCA TCE and PCE reduction rates
before 1993 were much slower and are similar in magnitude to flushing rates This indicates that
biodegradation before 1993 was less important Assuming this is the case the estimated
biodegradation half-lifes for PCE and TCA for the period 1993 to 1995 range from 13-25 and
10-24 years respectively near the Former Primary Disposal Area In contrast observed
reduction rates for TCE and DCE are slower than predicted flushing rates which may be
evidence that breakdown of their respective parent compounds was significant during the period
1993 to 1995 Indeed this interpretation is consistent with the observed biodegradation of PCE
In the Group 2 area (Figure 5-2) VOC levels (with the exception of DCE) at well cluster
MW102 appear to increase in 1995 while concentrations at cluster MW101 remained relatively
constant The concentration increase at MW102 may be due to the fact that this cluster is near
the leading edge of the VOC plume and groundwater flushing rates in this area are relatively low
However as discussed in Section 522 the increased PCE and TCA levels along with daughter
products such as TCE DCE vinyl chloride and DCA may be associated with transport of the
PCE and TCA plumes on the former Pervel property
The most interesting of the Group 3 wells are wells MW-A -B and -C located on the former
Pervel property As shown on Figure 5-3 PCE and TCA concentrations in wells MW-A and
5797wpdoc8galluprifinaltextmasterrifhl061297 5-16 QampT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW-B reduced to below detection limits by 1990 These rates of reduction correspond to halfshy
lifes of about 02 years for TCA and 03 years for PCE By comparison based on travel time
estimates from Plate 5-1 predicted groundwater flushing half-lifes for TCA and PCE
concentration reduction near Pervel are about 08 and 14 years respectively Assuming the
differences between observed concentration reduction rates and rates predicted by groundwater
flushing alone are due to biodegradation the biodegradation half-lifes for TCA and PCE are 03
and 04 years respectively In well MW-C TCA levels have reduced at a rate consistent with a
02-year half-life while the PCE half-life is approximately 05 years The corresponding
estimated biodegradation half-lifes for TCA and PCE at MW-C are 03 and 08 years
respectively Therefore biodegradation appears to be the major cause of the observed TCA and
PCE concentration reductions in the Pervel wells The lack of PCE or TCA detections in well
clusters MW119 and MW117 during the November 1995 sampling round are also consistent with
the rates of reduction in the Pervel wells For example the estimated travel times of PCE and
TCA from Pervel to the MW119 and MW117 wells are on the order of 4 and 2 years
respectively Since PCE and TCA levels in wells MW-A and MW-B were below detection by the
beginning of 1990 this groundwater with no detectable levels of either compound would be
expected to have passed through the MW119 and MW117 wells by the beginning of 1994 (PCE)
or 1992 (TCA)
In contrast the groundwater travel time from Pervel to wells MW116 MW103 and MW118 is
estimated to be up to one year longer than the travel time to MW119 and MW117 This would
correspond to increased travel times for PCE and TCA of about 4 and 25 years respectively
Based on these estimates low but detectable levels of PCE and TCA would be expected in wells
MW116 MW103 and MW118 during 1995 groundwater sampling In fact PCE TCA and
DCE were detected at each of these locations in 1995 at trace levels Slightly higher
concentrations of PCE and TCA were detected in MW116T during January 1995 but trace levels
were detected during each of the three subsequent 1995 rounds Further these rates of PCE and
TCA migration from Pervel would be consistent with the detections in well clusters MW102 and
MW101
Additional estimates of biodegradation rates were made by evaluating concentration reductions
within the parcel of groundwater located near well SW17 in 1980 Using the travel times shown
in Plate 5-1 it is estimated that about five years would be required for groundwater to travel from
SW17 to MW102 The corresponding chemical migration rates for TCA TCE and PCE are 12
11 and 20 years respectively Due to longitudinal dispersion (Section 512) the actual travel
times would be somewhat less Therefore groundwater presently in the MW102 area is expected
to be representative of historical (1980) groundwater contamination from the SW17 area
Neglecting possible contaminant contributions from Pervel most of the VOC concentration
5797wpdocsglaquolluprifinaltextmalaquoteiTifTil061297 5-17 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
reductions occurring in this parcel of groundwater as it traveled from SW17 to MW102 would be
due to biodegradation and rainwater infiltration
Figure 5-4 shows the TCA TCE and PCE concentration data from 1980 and 1982 for SW17S
and from January and November 1995 for wells MW102S and MW102TT The slopes of the
lines connecting the data from these two periods provide estimates of the combined biodegradation
and rainwater dilution rates for these compounds The combined half-lives for these two
mechanisms are 15 years (TCA) 18 years (TCE) and 21 years (PCE) From Bear (1979) the
half-life for rainwater dilution can be estimated as
n - b
where n = effective porosity b = saturated thickness and I = groundwater recharge rate due to
rainwater infiltration Using n = 025 b = 60 feet and I = 30 inchesyear (USGS 1995) the
half-life for dilution due to rainwater infiltration is about 4 years Using this value the estimated
biodegradation rates for TCA TCE and PCE within the VOC plume are 24 33 and 44 years
respectively These estimated biodegradation rates for TCA and PCE are a factor of two to three
less than estimated rates near the Former Primary Disposal Area during the period 1993 to 1995
5233 Summary
From the late 1970s through the four 1995 sampling rounds groundwater concentrations in the
VOC plume downgradient from the Former Primary Disposal Area have decreased at a rapid rate
The groundwater quality data from 1995 indicates that this trend of reducing concentrations is
continuing Based on these concentration reduction rates most VOC levels will fall below their
respective MCLs in a period of less than four years Vinyl chloride is an exception to this trend
because increased levels of this compound were detected in 1995 apparently due to the chemical
break down of its parent compounds PCE TCE and DCE
Analyses of these concentration reductions with time indicate that biodegradation and dilution by
rainwater infiltration are the key mechanisms responsible for these changes with biodegradation
likely the most important component Within the VOC plume biodegradation and rainwater
infiltration are reducing most VOC (with the exception of vinyl chloride) concentrations by about
a factor of two every two years which corresponds to an environmental half-life of two years
5797wpdocsglaquolluprifinaltextmraquosterrifnl061297 5-18 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
60 Summary and Conclusions
This section provides the conceptual model developed for the Study Area based on the findings
of the Phase 1A and IB field investigations and the results of the Long-Term Monitoring
Program sampling events
61 Conceptual Model of the Study Area The conceptual model was developed from the collection and analyses of information and data
from the Remedial Investigation (RI) as well as historical information and data A conceptual
model is an overview of the Study Area taking into account all media and their interrelationships
and describes in summary fashion Site conditions as they pertain to contaminant sources and
migration pathways This conceptual model will be used to support the evaluation of potential
remedial alternatives for the Feasibility Study
611 Geology
Geologic data collected during the RI indicate the following
bull Significant surficial or overburden deposits encountered in the Study Area are till
and glacial deposits referred to as stratified drift
bull The till is relatively dense and is comprised of a fine sandy matrix with abundant
gravel cobbles and boulders The till was encountered directly above bedrock at
most locations at thicknesses of 10 to 20 feet with the thickest accumulations
located along the topographic (bedrock) high in the central area of the Site
bull The stratified drift typically overlies the till or bedrock and consists of poorly to
well sorted deposits of gravel sand and silt Grain size analyses indicate that the
stratified drift is primarily comprised of fine to coarse sands with lesser amounts
of silt and fine gravel The stratified drift thickness varies from less than a few
feet in upland areas to as much as 70 feet in the vicinity of Mill Brook
bull Bedrock within the Study Area consists of grey fine- to medium-grained gneiss
with varying contents of amphibolite biotite and hornblende The bedrock
surface is characterized by a large slope and dips to the northwest and west-
southwest from a bedrock high located about 400 feet southeast of the Former
Seepage Bed The total bedrock surface relief in the Study Area approaches 100
feet
5797wpdocsgalluprifinaltejctmasterri fhl061297 6-1 QfT Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull Geophysical investigations (seismic refraction and magnetometer surveys)
conducted in the vicinity of the Former Seepage Bed did not reveal evidence of
one or two suspected discrete bedrock faults Rather the bedrock in the central
portion of the Site may be more accurately characterized as a series of
interconnected (to varying degrees) fractures and faults
^
612 Hydrogeology
Data regarding hydrogeologic conditions are summarized as follows
Hydraulic Conductivity
bull Across the Study Area test results indicate that the hydraulic conductivity
of the shallow overburden deposits averages approximately 0001
centimeters per second (cms) while the mean hydraulic conductivity for
the deep portion of the aquifer is about 0005 cmsec A mean hydraulic
conductivity of about 0037 cms is more representative of coarser-grained
deposits in the middle to lower portions of the overburden aquifer
northwest of the railroad tracks where the saturated thickness increases to
almost 70 feet
bull The mean hydraulic conductivity of the till (000047 cms) is a factor of
ten less than the average for the stratified drift deposits in the lower
portion of the aquifer and varies between 00002 and 0002 cms
Although the hydraulic conductivity of the till indicates that it is less
permeable and hydrogeologically distinct from the overlying stratified drift
deposits the hydraulic conductivity contrast is not large enough to
significantly alter groundwater flow directions or rates
cir
bull The mean bedrock hydraulic conductivity (000018 cms) is a factor of 25
lower than the average for the coarse-grained stratified drift Due to the
heterogeneous nature of fracture sizes and interconnectivity and their
associated nonlinear effect on groundwater flow rates the hydraulic
conductivity of the bedrock can be expected to be highly variable
throughout the Study Area
5797wpdocsgalluprifinaltextmasterrifhl061297 6-2 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
Groundwater Flow
bull The overburden aquifer is the preferred pathway for groundwater transport
of dissolved constituents This conclusion is supported by the hydraulic
conductivity test results and observations that an upward groundwater
flow component from bedrock to overburden exists throughout most of the
Study Area VOC detections in bedrock wells are believed to be caused
by vertical dispersion in the upper portion of the fractured bedrock
bull Because the unconsolidated deposits become unsaturated in the vicinity of
the Former Seepage Bed discussions of groundwater flow in overburden
are naturally divided into northern and southern portions of the Study
Area
bull Overburden groundwater flow south of the Former Seepage Bed is
generally from east to west at an average hydraulic gradient of 001 feet
per foot (vertical change in piezometric head per horizontal distance) and
is strongly influenced by the bedrock surface and drainage to the wetlands
and stream west of the railroad tracks The saturated thickness in this
area increases from zero near the bedrock high (northeast corner) to more
than 60 feet near the railroad tracks
bull Three distinct zones of overburden groundwater flow exist in the northern
Study Area In the area between the Former Primary and Secondary
Disposal Area and the Former Seepage Bed groundwater flow is largely
through till deposits and toward the north-northwest The hydraulic
gradient in this area is steep (about 003 feet per foot) and strongly
influenced by the dip of the bedrock surface and the lower hydraulic
conductivity of the till deposits The saturated thickness increases from
zero south of MW109 to 20 to 30 feet near the former disposal areas
North-northwest of these areas the hydraulic gradient lessens significantly
to a range of 00003 to 00007 feet per foot (factor of 40 to 100
reduction) North and northeast of Mill Brook the hydraulic gradient is
about 0007 feet per foot
bull Available data indicate that in the northern Study Area overburden
groundwater flow north-northwest of the Former Primary and Secondary
Disposal Areas exhibits a strongly convergent pattern The flow
5797wpdocsgalluprifinaltextmlaquosterriftU061297 6-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
converges from the east-northeast and southwest toward a centerline
generally defined in the downgradient direction by wells MW105
MW102 and MW101 Groundwater flows along this centerline from the
former disposal areas to the northwest Groundwater also flows from the
vicinity of the former Pervel flock plant in southwesterly and westerly
directions toward wells MW116 MW103 and MW101
South of the Former Seepage Bed groundwater flow within the upper
portion of the bedrock unit is primarily in a westerly direction In the
northern Study Area the predominant bedrock flow component is toward
the northwest In both areas the hydraulic gradient is relatively steep and
averages about 002 feet per foot Groundwater flow in bedrock near the
Former Seepage Bed is toward the northwest in the direction of wells
MW113 and MW106 and exhibits no apparent influence from locally
increased fracturing identified from the geophysical investigation and the
hydraulic testing in well MW11 IB
Vertical flow of groundwater is important in the upper several feet of the
bedrock unit Groundwater flow was found to be discharging from
bedrock to overburden at all locations during each of the measurement
dates with the exception of MW109 At MW109 the saturated overburden
thickness is less than a few feet and MW109 is located over a much
higher bedrock elevation than all other wells at which vertical flow from
bedrock was measured
Vertical flow in the overburden aquifer is of increased importance in two
areas in the vicinity of the Former Primary Disposal Area (wells clusters
MW107 MW108 and MW116) where vertical flow directions are
downward and within the upper portion of the aquifer near Mill Brook
where vertical flow is upward
Stream piezometer data and groundwater flow modeling indicate that Mill
Brook generally gains water from the overburden aquifer in the northern
portion of the Study Area
5797wpdoc8galluprifinaltextmraquosterrifhl061297 6-4 Q5T Environmental
Gallups Quarry SuperfimdProject - Remedial Investigation
613 Nature and Extent of Contamination
6131 Contaminant Source Investigation
The following summarizes the findings of contaminant source investigations during the RI
bull Previous remedial activities have completely removed the waste materials
(intact drums and bulk liquid waste) from the Site
bull The Former Seepage Bed and the Former Secondary Disposal Area
contain little residual contamination from the disposal activities which
occurred in the late 1970s
bull Residual levels of contamination primarily VOC and PCB were detected
in the Former Primary Disposal area In general the highest levels of
VOC are located at or just below the groundwater table in native soils
immediately beneath the fill materials and diminish rapidly with depth
PCB were detected primarily within fill materials
bull Other than the three known former disposal areas and the remains of the
former CTDOT asphalt plant no other significant disposal areas were
found to exist on the Site
6132 Groundwater Quality
Groundwater quality data collected during the Phase 1A program indicate the following
bull No significant groundwater contamination was detected within the
overburden or bedrock units in either the southern Study Area or in the
vicinity of the Former Seepage Bed
bull In the northern Study Area a narrow low to moderate-concentration
VOC plume (primarily TCA and DCE) was detected in the overburden
aquifer extending from the Former Primary Disposal Area to the
northwest towards Mill Brook
bull Comparison of present concentrations with historical data indicate that
concentrations within the VOC plume are significantly decreasing with
time From 1978 through 1995 TCA TCE and PCE concentrations
have decreased on the average by more than a factor of two every two
5797wpdocsgalluprifinaltextnui8terrifhl061297 6-5 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
years This trend appears to have continued through the four 1995
sampling rounds for these as well as other VOC with the exception of
the break down product vinyl chloride Biodegradation and dilution by
rainwater infiltration have been identified as the primary mechanisms
causing the concentration reductions with biodegradation the most
important component
The size and orientation of the VOC plume are in excellent agreement
with the established groundwater flow directions
Available information indicates that the leading edge of the VOC plume
associated with the Former Primary Disposal Area is located between
monitoring well clusters MW102 and MW101 VOC transport rates and
the reduction of TCA and DCE levels to estimated values at MW101
support this conclusion
PCE detections in the downgradient portion of the plume exhibit
inconsistencies with migration from the Site Groundwater pathlines and
time-of-travel estimates indicate that the PCE may be attributable to
contaminant transport from the former Pervel facility located north of the
Site Specifically it is possible that PCE detections at locations MW118
MW116 MW103 MW102 and MW101 may have resulted from
groundwater transport from the vicinity of the former Pervel flock plant
However it is also plausible that the PCE detections at locations MW102
and MW101 are attributable to the former disposal areas
Results of surface watersediment sampling and analyses stream
piezometer measurements and groundwater flow modeling indicate that
some discharge of the shallow portion of the plume into Mill Brook is
occurring There are low-level detections of VOC in the section of brook
intersecting the plume however the concentrations are well below those
reported to cause adverse effects in wildlife Detections downstream
adjacent to the municipal sewage treatment plant and below the confluence
of Fry Brook and Mill Brook are probably attributable to off-site sources
along Fry Brook north of the Study Area
Only one of the bedrock wells (MW105B) indicated elevated levels of
VOC Trace levels of a limited number of VOC were also detected in
5797wpdocsgalluprifinaltextma8terrifhl061297 6-6 QStf Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW102B MW107B MW108B and SW-10 however bedrock is not a
preferred pathway for contaminant migration due to its characteristically
low hydraulic conductivity and the consistent upward component of
ground water flow from bedrock to overburden which exists throughout the
Study Area
5797wpdocsgalluprifinaltextmastemfiil061297 6-7 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
70 References
Alexander M 1978 Biodegradation of Toxic Chemicals in Water and Soil in Proc 176th
National Meeting Miami Beach FL Sept 10-15 v 93 American Chemical
SocietyDivision of Environmental Chemistry
Amtec Engineering 1994 Tecplot Version 6 Belevue WA
Bear J 1979 Hydraulics of Groundwater McGraw-Hill
Beyer WN 1990 Evaluating Soil Contamination US Fish Wildl Serv Biol Rep 90(2) 25
pp July 1990
Bouwer H and Rice RC 1976 A Slug Test Method for Determining Hydraulic Conductivity
of Unconfined Aquifers with Completely or Partially Penetrating Wells Water Resources
Research vol 12 no 3 pp 423-428
Boynton GR and Smith CW 1965 Aeromagnetic map of the Plainfield quadrangle New
London and Windham counties Connecticut US Geological Survey Geophysical
Investigations Map GP-541 scale 124000
Brusseau ML 1996 Evaluation of Simple Methods for Estimating Contaminant Removal by
Flushing Groundwater V 34 No 1 pp 19-22
CTDEP 1986 Water Quality Classification Map for the Thames Southeast Coast and Pawcatuck River Basins Sheet 2 of 2 CTDEP Water Compliance Unit Hartford
Connecticut
Dixon HR 1965 Bedrock geologic map of the Plainfield quadrangle Windham and New
London Counties Connecticut US Geological Survey Geologic Quadrangle Map GQshy
481 scale 124000
Enfield CG and Bengtsson G 1988 Macromolecular Transport of Hydrophobic
Contaminants in Aqueous Environment Groundwater v 26 no 1 pp 64-70
ERT 1988 Preliminary Hazardous Waste and Petroleum Hydrocarbon Contamination Evaluation
of the InterRoyal Property Plainfield CT
5797wpdoc8galluprifinaltextmasterrifhl061297 7-1 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
ESE 1994 Gallups Quarry Superfund Project RIFS Work Plan Phase 1A (Prepared by Haley
amp Aldnch Inc Finalized by ESE)
ESE 1995 Initial Site Characterization Report March 1 1996
ESE 1995a April 1995 Long-Term Monitoring Report July 28 1995
ESE 1995b July 1995 Long-Term Monitoring Report October 27 1995
ESE 1996a Long-Term Monitoring Program - Data Report February 1996 Sampling Event
June 19 1996
ESE1996b Long-Term Monitoring Program - Data Report May 1996 Sampling Event
September 24 1996
ESE 1996c Long-Term Monitoring Program - Data Report August 1996 Sampling Event
December 18 1996
ESE 1997a Long-Term Monitoring Program - Data Report November 1996 Sampling Event
March 31 1997
ESE 1997b Long-Term Monitoring Program - Data Report February 1997 Sampling Event
May 21 1997
Fitchko J 1989 Criteria for Contaminated SoilSediment Cleanup Pudvan Publishing
Company Northbrook IL
Freeze RA and Cherry JA 1979 Groundwater Prentice-Hall Inc Englewood Cliffs
New Jersey
Freyberg DL 1986 A Natural Gradient Experiment on Solute Transport in a Sand Aquifer 2
Spatial Moments and the Advection and Dispersion of Nonreactive Tracers Water
Resources Research Vol 22 pp 2031-2046
Fuss and ONeill Inc 1979 Evaluation of a chemical waste disposal area Tarbox Road site
Plainfield Connecticut January 1979
5797wpdocsgalluprifinaltextmlaquoraquotemfhl061297 7-2 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Gelhar LW Montogluo A Welty C Rehfeldt KE 1985 A Review of Field-Scale
Physical Solute Transport Processes in Saturated and Unsaturated Porous Media Electric
Power Research Institute Report No EA-4190
Geraghty amp Miller Inc 1989 Aqtesolv Aquifer Test Solver Version 11 Reston VA October
1979
Hansch C and AJ Leo 1979 Substituent Constants for Correlations Analysis in Chemistry
and Biology John Wiley amp Sons New York
Hem JD 1989 Study and Interpretation of the Chemical Characteristics of Natural Water (3rd
Edition) USGS Water-Supply Paper 2254 US Government Printing Office
Washington DC
HRP Associates Inc 1993 Addendum to Groundwater Monitoring Report Former Pervel
Industries Flocking Plant March and June 1993 Sampling Events HRP Associates
Inc Plainville Connecticut
Karickhoff SW DS Brown and TA Scott 1979 Sorption of Hydrophobic Pollutants on
Natural Sediments Water Research Vol 13 pp 241-248
Lyman WJ Reehl WF Rosenblatt DH 1982 Handbook of Chemical Property
Estimation Methods-Environmental Behavior of Organic Compounds McGraw-Hill
Metcalf amp Eddy 1993 Final Data Summary Report START Initiative Gallups Quarry Plainfield Connecticut
Morel MM 1983 Principles of Aquatic Chemistry John Wiley amp Sons
Prior T Eaton L and Sperduto M 1995 Habitat Characterization for Gallups Quarry
Superfund Site Plainfield Connecticut United States Department of Interior Fish and
Wildlife Service New England Field Offices Concord NH
Reed PB 1988 National List of Plant Species That Occur in Wetlands Connecticut US Fish
amp Wildlife Service Washington DC NERC-881807 105p
Robertson WD Cherry JA Sudicky EA 1991 Groundwater Contamination from Two
Small Septic Systems on Sand Aquifers Groundwater v 29 no 1 pp 82-92
5797wpdocsgalluprifinaltextmlaquoraquoterrifhl061297 7-3 QST Environmental
Gallups Quarry SuperJUnd Project - Remedial Investigation
Schincariol RA and Schwartz FW 1990 An Experimental Investigation of Variable Density
flow and Mixing in Homogeneous and Heterogeneous Media Water Resources Research
v26 no 10 pp2317-2329
Schwille F 1988 Dense Chlorinated Solvents in Porous and Fractured Media translated from
German and Edited by JF Pankow Lewis Publishers Chelsea Michigan
Shacklette HT and Boerngen JC 1984 Element Concentrations in Soils and Other Surficial
Materials in Conterminous United States USGS Professional Paper 1270 US
Government Printing Office Washington DC
Sudicky EA Cherry JA and Frind EO 1983 Migration of Contaminants in Groundwater
at a Landfill A Case Study 4 A Natural Gradient Dispersion Test J Hydrology v 63
pp 81-108
US EPA 1986 Quality Criteria for Water Office of Water Regulations and Standards
Washington DC USEPA 4405-86-001 (NTIS PB87-226759)
US EPA 1987 A Compendium of Superfund Field Operations Methods US EPA540Pshy
87001 (NTIS No PB88-181557)
US EPA 1988 Interim Final Guidance on Remedial Actions for Contaminated Groundwater at
Superfund Sites US EPA Washington DC
US Fish and Wildlife Service 1995 Habitat Characterization for Gallups Quarry Superfund
Site Plainfield CT Concord NH 16 p
USGS 1993 Geohydrology of the Gallups Quarry Area Plainfield CT
5797wpdocsglaquolluprifinaltextmasterrifhl061297 7-4 QST Environmental
SOURCE PLAINFIELD75 MINUTE
124000
0 A 2
SCALE IN MILES
OONNECnCPT
OlMDIMNGLE LOCATION
CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP SERIES 1983
410 Amherst Street Nashua NH 03063
(603) 689-3737
GALLUPS QUARRY SUPERFUND PROJECT PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 1-1
SITE LOCATION MAP DRAWING NAME 1LOCDWG miE NUMBER 7194-138
SCALE AS SHOW [REVISION 0 I DRAWN BY PAD IPATE gg97
N
500 0 500
SCALE IN FEET
LOT NUMBER OWNER
1 C STANTON GALLUP 2 KENNETH R MOFFITT 3 INTERMARK FABRIC CORP 4 NORMAN ATLAS 5 FREDERICK BARRETT 6 WILLIAM ROPERANNE OWENS 7 ROBERT GLUCK
TILCON MINERALS INC 9 TOWN OF PLAINFIELD 10 ROBERT GLUCK 1 1 STANTON GALLUP 12 - 15 EDWARD DUNCAN 16 ELAINE M NILSON 17 ADOLPH SHAGZDA 18 ANTHONY FATONEJOSEPH FATONE 19 NANCY LAMIRANDE 20 KENNETH R MOFFITT 21 CONNECTICUT DOT 22 ST JOHNS CHURCH 23 DOROTHY CARON 24 ALFRED AND EVELIN RIENDEAU 25 PAUL GELINAS AND JOAN BURNORE 26 ALBERT SR AND ANN WILCOX
LEGEND
D LOT NUMBER
-- WATERCOURSE GALLUPS QUARRY SITE
PROPERTY BOUNDARY
NOTES
BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM - CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
410 Amherst Street Nashua NH 03063
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 1-2 1000
PROPERTY BOUNDARIES AND ADJACENT LANDOWNERS
DRAWING NAM^ PROPBNDDWG |^LE NUMBER 7194 138 SCALE AS SHOW^REVISION 0 |pRAWN BY PAD loATE 5997
GB
N
LEGEND
WATERCOURSE
TO PACKERS POND (CUSS CBc)
APPROX 1 MILE WEST OF SITE
PROPERTY
CLASS Be
BOUNDARY
SURFACE WATER
CLASS BA SURFACE WATER
CLASS GE GROUNDWATER
CLASS GEGA GROUNDWATER
NOTES
1 BASE PLAN PROVIDED BY USEPADATED 14 OCTOBER 1993
DRAWING NO 707600
2 HORIZONTAL DATUM shy CONNECTICUT STATE PLANSYSTEM NORTH AMERICAN
COORDINATE DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROMPLAINFIELD TAX ASSESSORS OFFICE
TOWN OF
4 UNLESS OTHERWISE INDICATEDCLASSIFICATION IS GA
CONNECTICUT GROUNDWATER
410 Amherst Street Nashua MH 030G3
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
500 0
SCALE IN
500
FEET
1000 FIGURE 1-3
CONNECTICUT SURFACE AND GROUNDWATER CLASSIFICATION ZONES
DRAWING NAME SOILTYPEDWG
SCALE AS SfcWN [RFVISION 0 l o R A W N B Y D-fB FILE NUMBER 7194 138
G1097
LEGEND
WATERCOURSE
PROPERTY BOUNDARY
LOCATION OF PREVIOUSLY INSTALLED MONITORING WELL
NOTES
1 BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM shy CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
410 Amherst Street Nashua NH 03063
(603) 869-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
- REMEDIAL INVESTIGATION REPORT
500 0 500 1000 FIGURE 1-4
GROUNDWATER MONITOR WELLS INSTALLED BY SCALE IN FEET FUSS amp ONEILL IN 1978 AND USGS IN 1993
DRAWING NAME SWMAGDWG FILE NUMBER 7194 138
SCALE A3 SHQHW [REVISION 0 [DRAWN BY DJB |DATE 51097
bull- - n V i _raquo-A raquoraquobull bull Jpoundi _
SOURCE PLAINFIELD CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP 75 MINUTE SERIES 1983
124000 410 Amber atNashua NH
Street 03063
(603) 889-3737
0 GALLUPS QUARRY SUPERFUND PROJECT
SCALE IN MILES PLAINFIELD CONNECTICUT REMEDIAL INVESTIGATION REPORT
FIGURE 1-5 COHNgOICOT
SITE LOCATION MAP AND NEARBY INDUSTRIAL PROPERTIES
QURANGLE LOCATION NAME LOCMAPXXDWG FILE NUMBER 7194138
SCALE AS SHOWN [REVISION 0 I DRAWN BY CBG loATE 5997
1450
FIGURE 3-1 GROUNDWATER ELEVATIONS MW-101
1420 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-101S MW-101TT MW-1 01 T
FIGURE 3-2 GROUNDWATER ELEVATIONS MW-102
1450shy
OJ 2
LLJ 1445shy
O CO
1440shyMW-102B WAS NOT INSTALLED UNTIL PHASE IB
1435
LLJ _l HI DC LJJ
I QZ
O cc CD
1430shy
1425shy
1420 010195
1 041195
1 072095
1 102895 020596
I 051596
I 082396
1 120196
1 031197 061997
DATE
MW-102S MW-102TT ---pound-- MW-102B
FIGURE 3-4 GROUNDWATER ELEVATIONS MW-104
1450
CO
LLJ 1445shy
O CO lt |mdash 1440shy
lt 1435shy
LLJ _J LLJ
CC LLJ 1430shy
I Q Z D O CC C5
1425
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-104S MW-104TT
FIGURE 3-5 GROUNDWATER ELEVATIONS MW-105
1450
CO2 LLJ 1445shy
O CO
1440shy
1435shy
LLI
LU tr QJ 1430shy
I Q
D O cc O
1425shy
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-105S MW-105TT MW-105T -X- MW-105B
1450
FIGURE 3-6 GROUNDWATER ELEVATIONS MW-106
1420 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-106S MW-106TT
1450
FIGURE 3-3 GROUNDWATER ELEVATIONS MW-103
1415 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-103S MW-103TT
FIGURE 3-7 GROUNDWATER ELEVATIONS MW-107
1490
CO
x- -X
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-107S MW-107TT MW-107T -Xshy MW-107B
FIGURE 3-8 GROUNDWATER ELEVATIONS MW-108
1465shy
(02 LU
1460shy
O CO
1455shy
1450shy
LU
LU
CC LU
lt
1445shy
1440shy
Q
mdashJocc O
14j vshy^
1430 010195
1 041195
1
072095 1
102895 T T
020596 051596
DATE 082396
1 120196 031197 061997
MW-1083 MW-1 08TT MW-1 08B
1580
FIGURE 3-9 GROUNDWATER ELEVATIONS MW-109
(0 1575shy
1530 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-109S MW-109B
1470
FIGURE 3-10 GROUNDWATER ELEVATIONS MW-110S
1450 i 1 i i i 1 r 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-110S
1610
FIGURE 3-11 GROUNDWATER ELEVATIONS MW-111B
1530 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-111B
1590
FIGURE 3-12 GROUNDWATER ELEVATIONS MW-112
lt) 1580shy
149 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-1123 MW-112T MW-112B
FIGURE 3-13 GROUNDWATER ELEVATIONS MW-113
1510shy
2UJ
O m lt
1500shy
1490shy
1480shy
LU _l LJJ
CC LU
1470shy
1460shy
Q
OCC O
145degH
1440 010195 041195 072095
1 102895 020596 051596
DATE 082396
1 120196
1 031197 061997
MW-113S MW-113B
1580
FIGURE 3-14 GROUNDWATER ELEVATIONS MW-114
1460 i r 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-114S MW-114TT
150
FIGURE 3-15 GROUNDWATER ELEVATIONS MW-115
1465 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-115S MW-115TT --pound-- MW-115B
1455
FIGURE 3-16 GROUNDWATER ELEVATIONS MW-116
1425 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-116S MW-116T
FIGURE 3-17 GROUNDWATER ELEVATIONS MW-117
1480shy
CO
LJJ gto CD
1475shy
1470shy
LU LU
CC LU
1465shy
WELLS AT THIS LOCATION WERE NOT INSTALLED UNTIL PHASE 1B
O z D O CC (5
1460shy
1455 010195
1 041195 072095
I 102895
1 1020596 051596
DATE
1 082396 120196 031197 061997
MW-117S MW-117TT
FIGURE 3-18 GROUNDWATER ELEVATIONS MW-118
1465shy
LU 1440shy
LLJ
CC LU 1435shy WELLS AT THIS LOCATION WERE
I Q Z D O CC CD
1430shy
1425shy
NOT INSTALLED UNTIL PHASE 1B
1420 010195
1 041195
I 072095
1 102895 020596
1 051596
DATE 082396 120196 031197 061997
MW-118S MW-118TT
FIGURE 3-19 GROUNDWATER ELEVATIONS MW-119
1475shy
CO2 LJJ
1470shy
o m
1465shy
1460shy
UJ_i UJ cc LJJ
1455
1450shy
WELLS AT THIS LOCATION WERE NOT INSTALLED UNTIL PHASE 1B
Q Z
O cc O
1445shy
1440 010195 041195
1 072095
I102895
I I 020596 051596
DATE
1 082396
i 1 201 96 031 1 97 061 997
MW-119S MW-119TT
1455
FIGURE 3-20 GROUNDWATER ELEVATIONS SW-3SD
1425 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
SW-3S SW-3D
Originals in color
VERTICAL
PROJECTED FOOTPRINT of FORMER PRIMARY
DISPOSAL AREA
MILL BROOK
NOTES (1)
(2)(3)
THE SAME CONTOUR INTERVALS ARE USED FOR THE SHALLOW AND DEEP MAPS
WATER LEVEL DATA COLLECTED 2-2-95 VERTICAL EXAGGERATION = 10X
410 Amherst Street THIS FIGURE SHOWS ONLY THE PREDOMINANT OVERBURDEN GROUNDWATER FLOW PATHWAYS WHICH ORIGINATE Nashua NH 03063 IN THE VICINTY OF THE FORMER PRIMARY DISPOSAL AREA AS VIEWED FROM THE EAST (603) 889-3737
ALTHOUGH THIS DEPICTION IS BAStU ON PlEZOMETRlC HEAD OAiA (MEASURED ON FEBRUARY 2 1335) THIS FiGURE DOES NOT SHOW EVERY POSSIBLE FLOW PATHWAY WITHIN THE OVERBURDEN AQUIFER THE UPPER SURFACE REPRESENTS THE SURFACE OF THE WATER TABLE THE LOWER SURFACE REPRESENTS GALLUPS QUARRY SUPERFUND SITE A PLANE DEFINED BY THE PIEZOMETRIC HEAD AS MEASURED IN WELLS WHICH ARE SCREENED IN THE LOWER PORTION OF THE OVERBURDEN AQUIFER THE LOWER PLANE DOES NOT REPRESENT THE LOWER BOUNDARY OF THE OVERBURDEN AQUIFER AND NEITHER PLANE IS GEOLOGICALLY SPECIFIC PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 3-21
PREDOMINANT OVERBURDEN GROUNDWATER FLOW PATHWAYS IN NORTHERN PORTION OF STUDY AREA
DRAWING NAME FLOWPATHDWG IFILE NUMBER 7194 138
SCALE NT5 JREVSION 1 JDRAWN BY CBG [DATE 6-9-97~
lt 4 Original includes color coding
10s r SW-17SandMW105S Ho5 SW-17D and MW105TT
P 1 V |
1deg4 i
4 mI U 5 k 4 3
i i f J |103 1I Un |
|io2 bull m2
bull I U = i ii gtv o r
BDL mdasha I bullM BDL a i i c CM ltD 0 ltj at agt c c at at T c I 1 I i i i
SW-13 c MW105S I10s pound
1I Un =
m4
104 I U sect
J 1I 3 bull PCE -m
H103| IU sect bull TCA
2 ^ TCE 102
m
I bull 1 2-DCE A i 1
T VINYL CHLORIDE 1 0 ^h
bull A1
10deg BDL = BELOW DETECTION LIMIT 10deg 1 U = V 3 X
=
ni-M ^ ^ ^ laquote BDL 0 V o0 CV tfi _ CO CXgt o0 ogt ogt 2 C oraquo oraquo cn O) O lt C
i- r- -3 4 1 1995
MW105TT MW107TT 105 105
E pound
i shy104
2 = 104 I = ^^to^f^P 410 Araherst Street bull^OJfcCfe Nashua NH 03063 103 103 ^raquo^^^j^ (603) 889-3737 f bull 1
- T T T shy ~ A102 i1 bull bull S 102
GALLUPS QUARR y SUPERFUND SITE I 1
PLAINFIELD CONNECTICUT REMEDIAL INVEi iTIGATOJV REPORT 10 101
i 1 FIGU RE 5 110deg i = 10deg
BDL laquo BDL VOC CONCENTRATION CHANGES VERSUS TIME M
^ i DOWNGRADIENT FROM FORt ilER PRIMARY DISPOSAL AREA sect o ^ O
^
-5lt 5amp -s= z1
1995 1995
Original includes color coding
CO
NC
ENTR
ATIO
N (
ppb)
IU sect MW102S
s 105 MW102TT
104 1 i 104
103 1 103
102 I I A sect 102
1
A
T
1 101
10deg i 10deg
nni BDL +shytr a O o
1995 1995
bull PCE
bull TCA A TCE
bull 12-DCE
T VINYL CHLORIDE
MW101TT 105
104
103
102
10deg
BDL
1995
410 Amhersl Street Nashua NH 03063
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 5-2
VOC CONCENTRATION CHANGES VERSUS TIME DOWNGRADIENT PORTION OF PLUME
BDL = BELOW DETECTION LIMIT
s
104 tmdash a IU I
1 IU103 U-o 1F= E
i 105 to2 tmdash r 1 1deg1 i~ deg 10degL
BDL Emdash oS
105 i
104 i
103 i
102 bull
101 1
10deg
BDL 0S
105 9
104 B
103 I
102 i
101
10deg 1
BDL OCOogt
^ 00 ogt
^ra lt cltJgt
C O 0 0
0gt
MW-A
4 bull
1 1 1
co 01
MW-B
_J 1 1
1
i CO
8)
MW-C
11 1
lt lt
CO CO ogt
bullbull
laquoftr i i bull i
mn
Tbull1
bullbull
bull i
9
bull
bullM bullM bullbull- 1
egt lt t a) a
aai Tshy^
WM cN gjcI) lt J1
bull 1
bull 11 1
MM bullMl bullfr- 1
c4 0aigt C
t bullgt araquo lt raquo
T ^
Original includes color coding
10 |
-iM 10 s
-irvS 10 |
nn2 10
bullm1 bull
1UJ
oni AZs
^^^f
MW116T
A a
A =J =3
1995
bull
bullA
PCE
TCA
TCE
1 2-DCE
sect
1
s
I I 1
A gti
T VINYL CHLORIDE
BDL = BELOW DETECTION LIMIT
410 Amherst Street bull^OJUV^ Nashua NH 03063 ^raquo^^ ^jj^ (603) 889 3737
nmranmini x
GALLOPS QlARRy SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 5-3
VOC CONCENTRATION CHANGES VERSUS TIME AREA NORTH-NORTHEAST OF PLUME
I Original includes color coding
SW-17S MW102S and MW102TT
410 Amherst Street Nashua NH 03063
bull PCE (603) 889-3737
bull TCA A GALLUPS QUARRY SUPERFUND SITE TCE
PLAINFIELD CONNECTICUT REMEDIAL INVESTIGATION REPORT
BDL = BELOW DETECTION LIMIT
FIGURE 5-4
EVALUATION OF BIODEGRADAT10N AND RAINWATER DILUTION RATES IN VOC PLUME
(D NOTE FORWELLS MW102S and MW102TT ONLY JANUARY and NOVEMBER 1995 DATA ARE PLOTTED
GENERAL
Volume 1
Volume 2
Volume 3
Volume 4
Volume 5
Volume 6
Volume 7
Gallups Quarry Superfimd Project - Remedial Investigation
TABLE OF CONTENTS
Text and Figures
Tables
Plates
Appendices A B C D E Famp G
Appendices H I J amp K
Appendices L M amp N
Appendices O P Q R S T U amp V
5797wpdoc8galluprifinaltextrigentoc061397 QST Environmental
Remedial Investigation
Gallups Quarry Superfund Project
Plainfield Connecticut
Submitted to
US EPA - Region I
Boston Massachusetts
Prepared by
QST Environmental
(formerly Environmental Science amp Engineering Inc)
Nashua New Hampshire
June 1997
QST Project No 71941380430
Gallups Quarry Superfund Project - RI Executive Summary
Executive Summary
EI Purpose of the Report This document presents the Remedial Investigation (RI) Report which was completed for the
Gallups Quarry Superfund Site (Site) pursuant to the requirements of US Environmental Protection Agency (EPA) Administrative Order by Consent Docket Number 1-93-1080 (Order)
issued September 7 1993 The Site is a former sand and gravel quarry and is located on Tarbox
Road in the Town of Plainfield Connecticut (see Figure E-l) The Study Area includes the Site
as well as areas west and north of the Site
Investigation of the Site was initiated in 1978 when unlicensed waste disposal operations were
discovered at the property Emergency clean-up operations were conducted in three disposal
areas by the Connecticut Department of Environmental Protection (CTDEP) in April 1978
(Metcalf amp Eddy 1993) Following the initial clean-up effort a series of surface and subsurface
sampling events were performed by the CTDEP the Connecticut Department of Health (CTDOH) and US Environmental Protection Agency (EPA) Based primarily on the detection of
groundwater contamination the Site was listed on the National Priorities List (NPL) on October 4 1989 During 1992 and 1993 EPA conducted a limited investigation through the Superfund
Technical Assessment amp Response Team (START) initiative in an effort to expedite the
completion of the Remedial InvestigationFeasibility Study (RIFS) The requirements of the
Order as well as data included in the START report (Metcalf amp Eddy 1993) provided the
framework for the Remedial Investigation
This RI Report is the sixteenth major deliverable under the Order The first major deliverable
the Remedial InvestigationFeasibility Study Work Plan - Phase 1A was finalized and submitted to EPA on August 29 1994 QST Environmental (formerly Environmental Science amp Engineering Inc (ESE)) finalized the Work Plan and has prepared all of the other deliverables
The Phase 1A field investigation was completed in January 1995 The second major deliverable
the Phase 1A Data Report dated March 24 1995 was submitted to EPA following completion of
the Phase 1A field investigation The findings of the Phase 1A Investigation were described in
the Initial Site Characterization Report (ISCR) which was finalized and submitted to EPA on
March 1 1996 A Work Plan for the Phase IB field investigation was finalized and submitted on
October 11 1995
In addition to the Phase 1A field investigation the Phase 1A Work Plan also described the Long-
Term Monitoring Program which was initiated upon completion of the Phase 1A field
investigation The Long-Term Monitoring Program includes the quarterly collection and analysis
of groundwater and semi-annual collection and analysis of surface water and nearby residential
well samples The Phase IB field investigation commenced on October 12 1995 Following the
5797wpdocsglaquollupfsfinlaquoltextexecnimmri060997 E-l QST Environmental
SOURCE PLAINFIELD CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP 75 MINUTE SERIES 1983
410 Amherst Street 124000 Nashua NH 03063
(603) 889-3737
0 GALLUPS QUARRY SUPERFUND PROJECT
PLAINFIELD CONNECTICUT SCALE IN MILES REMEDIAL INVESTIGATION REPORT
comacncur FIGURE E-l
SITE LOCATION MAP DRAWING NAME ELOCDWG FILE NUMBER 7194-138
QUADRANGLE LOCATION
SCALE AS SHOWN REVISION 0 I DRAWN BY PAP [DATE 5997
Gallups Quarry Superand Project - RI Executive Summary
completion of drilling activities the Phase IB groundwater sampling task and the fourth quarter
1995 Long-Term Monitoring sampling event were performed simultaneously in November 1995
Seven Data Reports have been submitted to the EPA for the following Long-Term Monitoring
Program sampling events the second and third quarters of 1995 all four quarters of 1996 and
the first quarter of 1997 (ESE 1996a 1996b 1996c 1997a 1997b) The draft RI Report was
submitted to EPA on March 15 1996 (and revised and resubmitted October 22 1996) and included the results of the fourth quarter of 1995 sampling event On March 29 1996 the
following two deliverables were submitted to EPA Development and Initial Screening of Alternatives Report and Detailed Analysis Work Plan The draft Feasibility Study was submitted
to EPA on January 27 1997 This RI Report describes the methods and findings of both the Phase 1A and IB field studies and includes data collected during the April July and November
1995 February May August and November 1996 and February 1997 Long-Term Monitoring
sampling events
E2 Site Background E21 Area Description
The 29-acre Gallups Quarry Site is located on the north side of Tarbox Road in the Town of
Plainfield Windham County Connecticut The Site which is currently vacant is bounded by
wooded areas and wetlands associated with Mill Brook (which flows from east to west
approximately 250 feet north of the Site) single-family residences and several commercial
properties Approximately 700 feet north of the Site on the opposite side of Mill Brook is an industrial park which contains an Intermark Fabric Corporation facility (formerly the Pervel
Industries flock plant) and a Safety Kleen Corporation accumulation facility Further north of the
industrial park are several presently vacant mill buildings which were previously occupied by various manufacturers including Pervel Industries and the InterRoyal Corporation The Plainfield sewage treatment plant which discharges to Mill Brook and its major tributary (Fry Brook) is
located approximately 1800 feet northwest of the property
E22 Site Operational History
Limited information is available regarding the early operational history of the Site Historical
aerial photographs and records at the Town of Plainfield Assessors office indicate that in 1951
the Site was owned by a Mr Johnson and that some quarrying activities were underway in the
southern portion of the Site In 1964 the Site was purchased by C Stanton Gallup Although
detailed usage of the Site from 1964 through 1977 is poorly documented records indicate that the
Site was used as a source of aggregate and was occupied by the Connecticut Department of
Transportation (CTDOT) who were operating an asphalt batching plant
5797WTgtdocsgallupfsfinltextexec8ummri060997 E-3 QST Environmental
Gallups Quarry Superfund Project - RI Executive Summary
As a result of complaints from neighboring residents the CTDEP and the Connecticut State
Police initiated an investigation of the Site in January of 1978 The CTDEP investigation
concluded that the Site was used from the summer of 1977 until December 1977 for unlicensed
waste disposal Evidence collected by CTDEP indicates that Chemical Waste Removal Inc
(CWR) of Bridgeport Connecticut transported drummed and bulk liquid waste material to the
Site These materials reportedly included a variety of industrial wastes
Emergency clean up efforts were performed during the summer of 1978 under the direction of the
CTDEP and the Connecticut State Police This involved the removal and off-site disposal of
1584 drums 5000 gallons of free liquid and 2277 cubic yards of contaminated soil from three
distinct locations on the Site The drums as well as liquid waste and contaminated soil were
removed from the Primary and Secondary Disposal Areas located in the northern portion of the
Site Remedial measures performed at the Seepage Bed reportedly located in the central portion
of the Site included the excavation of contaminated soil and in-situ treatment of remaining soils
through the addition of 20 tons of lime A buried inverted dump truck body was also reportedly
removed from the Site In addition to these remedial activities mine detectors were utilized to search for additional buried drums There was no evidence of additional buried drums and it
was believed that all drums were recovered during the cleanup operations
Since the 1978 cleanup operations the Site has been vacant although there are some indications
that the Site has been utilized by trespassers for recreational purposes
E23 Summary of Previous Investigation
ations and sampling events were conducted at the Gallups Quarry Site The significant previous
investigations are as follows
bull A general site investigation performed on behalf of the State of Connecticut (Fuss amp
ONeill 1979) which included the installation of 22 monitoring wells 19 test pits (13
of which were completed as shallow monitoring wells) and the collection of surface
water and sediment samples The investigation was completed within several months
of the States remedial efforts described above Groundwater from monitoring wells
and nearby residential wells as well as surface water from Mill Brook was sampled
several times from the period of July to December 1978
bull Various CTDEP monitoring events for groundwater surface water and sediment
occurred from 1979 until 1993 Sampling events were conducted in October 1979
January and November 1980 April and October 1981 April 1982 and December
1983 CTDEP also performed a biodiversity survey in 1985 in an effort to evaluate
potential impacts to the Mill Brook wetland In addition CTDEP also conducted
sampling anq (analysis of neighboring residential wells in 1992 and 1993
5797wpdocraquogallupf8finlaquoltextexecsummri060997 E-4 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
bull A Hazard Ranking System (HRS) Study was completed in 1987 by NUS Corporation
foi ZPA The Study included the collection of water samples from two existing
moiiitoring wells and three surface watersediment locations
bull A review of historic aerial photographs of the Study Area was performed by the
Bionetics Corporation on behalf of the EPA Photographs dating back to 1951 were
included in the review which was published in 1990 (Bionetics Corp 1990)
bull In cooperation with EPA the USGS performed a geohydrologic investigation at the
Study Area in 1993 This investigation included geophysical surveys (EM-34 and GPR) to characterize various subsurface features One monitoring well was installed
bull In 1993 the US Fish and Wildlife Service performed a field study to characterize the
habitats within the Study Area The study was finalized in 1995
bull Various sampling events were conducted in 1989 and 1993 on behalf of the EPA During these sampling events groundwater from existing monitoring wells and nearby
residential wells as well as surface soil samples were collected for analysis
The significant findings of these investigations are summarized as follows
bull The initial study completed at the Site by Fuss amp ONeill in 1979 concluded that
groundwater in the vicinity of the former disposal areas had been impacted by certain
volatile organic compounds (VOC) and metals A well-defined groundwater plume which contained these various constituents extended in a northwest direction away
from the Site
bull Periodic CTDEP sampling events from 1979-1982 indicated the wells downgradient of
the former disposal areas consistently showed detectable levels of constituents similar
to those disposed of on-site The results of CTDEP sampling events indicated that
nearby residential wells had not been impacted by the Site
bull The USGS study provided an updated geological characterization of the Study Area
and suggested the potential presence of a bedrock fault zone located in the vicinity of
the Former Seepage Bed
bull The results of the 1989 and 1993 sampling events generally confirmed the findings of
previous groundwater quality investigations and indicated that VOC concentrations
decreased significantly in the period between 1982 and 1993
5797wpdocgglaquollupfsfiiultextexecnjmmri060997 E-5 QST Environmental
Gallups Quarry Superfiotd Project - RI Executive Summary
To supplement historical data and data obtained during the Phase 1A field program a CTDEP file
search was performed to obtain information pertinent to groundwater contamination for industrial
properties neighboring the Site The available information indicates that
bull two separate companies Pervel Industries and InterRoyal Corporation operated
manufacturing facilities at locations approximately 2500 feet north of the Site
bull Pervel Industries also maintained a second facility (a fabric flock plant) located
approximately 1000 feet north of the Site across Mill Brook
bull there have been documented releases of 111-trichloroethane (TCA) and toluene at
the northern-most Pervel plant
bull contaminated soil and sediment associated with a 1985 spill of 111-TCA at the
northern-most Pervel facility was stored in an impoundment located on the eastern
(upgradient) side of the Pervel flock plant property
bull the contaminated soilsediment impoundment was located approximately 1000 feet
from the northern end of the Site
bull the results of historical groundwater monitoring at the former Pervel flock plant
located a few hundred feet north of the Site show the presence of elevated
concentrations of several VOC including tetrachloroethene (PCE) and TCA
E3 Summary of Remedial Investigations Phase 1A Field Investigations
In order to maximize the efficiency of the Site characterization program for the Gallups Quarry
Site multiple phases of data collection and evaluation were performed during the Phase 1A field
program Screening level surveys completed during the initial weeks of the field program
utilizing fast-turnaround data generation and evaluation techniques were used to focus data
collection efforts during the latter part of the Phase 1A field program The screening surveys
included
bull A visual site reconnaissance involving transit by foot and direct observations and
photographic documentation of significant features along approximately 39000 feet of
trend lines covering the entire Site
bull Geophysical surveys including electromagnetic terrain conductivity (EM) and
magnetometer surveys along 25-foot spaced trend lines totalling approximately
5797wpdocBgallupf8finaltextexeclaquoummri060997 E-6 Q5T Environmental
Gallups Quarry Superfimd Project - Rl Executive Summary
39000 feet in length and covering the entire Site follow-up EM-31 and
magnetometer surveys and a test pit program in three areas where anomalies were
observed and a seismic refraction survey west of the Former Seepage Bed
bull A microwell survey which included the collection of 126 groundwater samples from
multiple depths at 50 locations within the Study Area field gas chromatograph
analyses of all of these samples for an indicator list of 8 VOC laboratory analyses of
121 of these samples for metals and 12 of the samples for VOC and
bull A soil vapor survey which involved the collection of soil vapor samples from 106
locations throughout the Site and on-site analyses for an indicator list of 8 VOC
Based on these screening level and historical data a groundwater monitoring well installation
sampling and analytical program was designed The program as approved by EPA included the
following
bull The installation of 5 wells at 2 designated background locations These wells include
a shallow overburden and a bedrock well in the northern portion of the Site and two
overburden wells (screened at the water table and in a deeper till horizon) and a
bedrock well in the southern portion of the Site Background soil and groundwater
samples were collected from these locations
bull The installation of 19 wells at seven locations downgradient (northwest) of the Former
Primary and Secondary Disposal Areas to assess and define the boundaries of a
contaminant plume identified during the microwell survey These wells included 17
overburden wells and two bedrock wells
bull The installation of six wells at three locations located north and east of the Former
Primary Disposal Area to assess groundwater quality and flow directions in these
areas These wells included five wells screened in overburden and one in bedrock
bull The installation of two bedrock wells and one overburden well at two locations in the
vicinity of the Former Seepage Bed This included one bedrock well placed within an
inferred bedrock faultfracture zone to assess the zones potential to act as a preferred
contaminant transport pathway
bull The installation of five wells at two locations in the southern portion of the Site to
assess very limited screening-level VOC detections in this portion of the property
These wells include four overburden wells (two shallow and two top-of-till) and one
5797wpdoclaquoglaquollupftfinlaquolte)rtexecraquoummri060997 E-7 QST Environmental
Gallups Quarry Superfund Project - RI Executive Summary
bedrock well In addition six groundwater piezometers were installed to assess groundwater flow directions in the southern portion of the Study Area gtmdashr
Samples from three of the newly installed wells (MW102TT MW106TT and MW116T) were analyzed for Appendix IX parameters Samples from the remaining newly installed monitoring wells and three existing wells (SW-9 SW-10 SW-12) were analyzed for Target Analyte ListTarget Compound List (TALTCL) parameters Twelve nearby residential wells were also sampled for TALTCL parameters (although VOC were analyzed using EPA method 5242) In addition to the monitoring well installation and groundwater sampling program outlined above the following tasks were performed during the Phase 1A field program
bull Air quality monitoring to establish ambient air quality prior to and during the intrusive investigations A total of eight air monitoring stations were established at locations within and at the Site perimeter
bull Water-level measurements were recorded to assess horizontal and vertical groundwater flow directions and aquifer testing (including evaluations of the remaining existing monitoring wells) using slug tests was conducted to assess the hydraulic conductivity of the aquifer
bull Soil boring programs within the three known disposal areas to assess the nature and extent of residual contamination A total of ten soil borings were completed at the three areas Each boring was continuously sampled and terminated at auger refusal Selected samples were submitted for laboratory analysis for TALTCL parameters based on lithology depth and photoionization detector (PID) headspace readings as set forth in the Work Plan
bull Surface watersediment sampling was performed at 17 locations including Mill Brook Fry Brook Packers Pond and in an unnamed pond on Tarbox Road just south of the entrance to the Site In addition wetland soil samples were collected from 10 locations within the Study Area All samples were submitted for analysis for TALTCL parameters
bull Federal and State jurisdiction^ wetland delineations were performed
Phase IB Field Investigations The data collected during Phase 1A was supplemented with the following additional investigative activities conducted during the Phase IB field investigation
5797wpdocsgallupfsfiMltextexecsummri060997 E-8 QST Environmental
Gallups Quarry Superand Project - RI Executive Summary
bull Quantitative air monitoring for site-specific compounds in the vicinity of the Former
Prirary Disposal Area
bull Collection and analysis of soil samples from six additional soil borings in the Former
Primary Disposal Area to more fully characterize the extent of residual VOC and PCB
contamination
bull The installation of seven additional groundwater monitoring wells and one additional
piezometer to obtain additional groundwater data from the downgradient portion of the
plume and from the northnorthwest portion of the Site The monitoring wells
included (3) two well clusters and (1) bedrock well
bull Collection of groundwater samples from each new monitoring well and from five
existing wells on the former Pervel facility and analysis of these samples for VOC to confirm the downgradient extent of the plume originating in the Former Primary
Disposal Area and
bull The performance of constant flow tests consisting of short-term pumping tests on selected groundwater monitoring wells to supplement Phase 1A hydraulic conductivity
data so that groundwater velocities and transport rates and aquifer yield could be
more accurately determined
Long-Term Monitoring Program
A Long Term Monitoring Program was initiated upon completion of the Phase 1A field investigation The Long-Term Monitoring Program includes the quarterly collection and analysis
of groundwater and semi-annual collection and analysis of surface water and nearby residential
well samples Data from eight quarterly sampling rounds (performed in April July and
November 1995 February May August and November 1996 and February 1997) are presented
and discussed The Conceptual Model discussion is based on the 1995 quarterly sampling rounds
Any minor adjustments to the Conceptual Model resulting from later monitoring rounds are
addressed in the FS
E4 Conceptual Model of the Study Area E41 Physical Characteristics E411 Physiography
The Site is located along the eastern border of the Quinebaug Valley Lowland The region is
characterized by relatively low relief and numerous glacial features The regional landscape is
5797wpdoc8glaquollupfBfinaltextexecraquoummri060997 E-9 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
significantly influenced by the structure of the underlying crystalline metamorphic bedrock The
topography of the Site is highly irregular primarily due to past quarrying operations including
numerous overgrown mounds of earthen materials and excavated depressions The ground
surface on the Site generally slopes from the east to the west and to a large degree is controlled by the underlying bedrock surface North and west of the Site the ground surface elevation
decreases in the Mill Brook floodplain which is described as a low lying heavily vegetated
wetland
E412 Geology
The overburden deposits in the area consist of materials deposited as a result of glacial processes during the Pleistocene epoch A range of glacially-derived materials including till meltwater or
stratified drift deposits and post-glacial deposits of floodplain alluvium comprise the major
surficial geologic units in the vicinity of the Site The significant surficial deposits encountered
within the Study Area during the RI are till and stratified drift Stratified drift deposits can be
further broken down into coarser-grained or finer-grained components The Study Area is
dominated by coarser-grained deposits which represent various ice-contact or outwash features associated with the retreat of the ice-mass Finer-grained components also exist to a limited
extent within the Study Area and are the result of lacustrine deposition which occurred when
low-lying areas were inundated by a glacial lake Much of the Sites overburden geology
represents the transition of depositional environments as the glacier progressively retreated from
the area Although alluvial floodplain deposits were encountered at locations within the present
Mill Brook floodplain the significance of these deposits is minor
The thickness of the stratified drift deposits range from non-existent in the vicinity of bedrock
outcrops in the eastern portion of the Site to approximately 70 feet The overburden thickness
increases in response to a decrease in the elevation of the bedrock surface Till was encountered just above the bedrock surface at nearly every location The till horizon ranges in thickness from
approximately 10 to 20 feet with the thickest accumulations located along bedrock highs
Surficial exposures of glacial till were observed on the Site The till is relatively dense and is
comprised of a fine sandy matrix with abundant gravel cobbles and boulders
Bedrock in the vicinity of the Site mapped as a lower member of the Quinebaug Formation
consists of hornblende gneiss biotite gneiss and amphibolite and is strongly faulted and folded
exhibiting varying degrees of mylonitization Geophysical surveys performed prior to and during
the Phase 1A field program indicate that a northwest-trending fracture zone may extend across the
central portion of the Site Based on the drilling program depths to bedrock range from zero to
83 feet below ground surface within the Study Area Bedrock elevations are greatest in the
eastern central portion of the Site and decrease to the north and west and to a lesser degree to
the south
5797wpdocsgallupfsfinaltextexecsummri060997 E-10 QSTEnvironmental
Gallups Quarry Superfund Project - RI Executive Summary
E413 Hydrogeology
E4131 Hydraulic Conductivity
The hydraulic conductivity distributions within the overburden and bedrock formations were
evaluated through the performance of constant flow (pumping) tests and rising and falling head
slug tests Hydraulic conductivity measurements indicate that coarse-grained stratified drift
deposits in the lower portion of the aquifer are the most permeable subsurface materials in the Study Area with a mean hydraulic conductivity of 0005 centimeters per second (cms) The
highest hydraulic conductivities were found in the lower portion of the aquifer northwest of the Former Primary Disposal Area where the mean hydraulic conductivity is 0037 cms The mean
hydraulic conductivity of the finer-grained deposits in the upper portion of the aquifer is about
0001 cms
The mean hydraulic conductivity for the till wells (000047 cms) is a factor of ten less than the
average value for coarse stratified drift and varies between 00002 cms and 0002 cms The till
appears to be hydrogeologically distinct from the other overburden deposits and on the average
provides increased resistance to groundwater flow This added resistance is not considered to be
significant however because the consistency of the till and overburden deposits are highly
variable and the hydraulic conductivity contrast is relatively small The slug test results for the
bedrock wells yield the lowest (000018 cms) average hydraulic conductivity
E4132 Groundwater Flow
Horizontal Flow
Overburden groundwater flow south of the Former Seepage Bed is primarily east to west and is
influenced by two factors (1) the slope of the bedrock surface which defines the base of the
unconsolidated deposits and (2) regional hydrologic drainage patterns The average east-west horizontal hydraulic gradient in the southern portion of the Study Area is approximately 001 feet
per foot (feet change in piezometric head per horizontal foot of distance)
In the northern portion of the Study Area three hydrogeologically distinct zones exist South of the Former Primary and Secondary Disposal Areas the hydraulic gradient is steep (approximately
003 feet per foot) and is strongly influenced by the dip of the bedrock surface (01 feet per foot)
The saturated thickness increases from zero south of well MW109 to about 20 to 30 feet near the
former disposal areas North-northwest of the former disposal areas the hydraulic gradient
lessens significantly to a range of 00003 to 00007 feet per foot representing a factor of 40 to
100 reduction North-northeast of Mill Brook the hydraulic gradient is about 0007 feet per foot
Available data indicate that currently northwest of the railroad tracks groundwater flow in the middle to lower portions of the aquifer converges from the northeast and southwest toward a
centerline area generally defined in the downgradient direction by wells MW105 MW102 and
5797wpdoclaquoglaquoliupfraquofirultextexeclaquoummri060997 E-ll QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
MW101 The flow direction near these wells is from the former disposal areas to the northwest
Northeast of this centerline groundwater flows in a southwesterly direction from the vicinity of
Mill Brook and the former Pervel flock plant North of Mill Brook and west of the railroad
tracks the predominant groundwater flow direction becomes more westerly
No significant seasonal changes in horizontal groundwater flow directions were observed in the
Study Area Groundwater levels were generally highest in January 1995 and decreased by about
two feet through the period ending on July 11 1995 Levels then increased by about one foot
from July to November
General overburden groundwater pathlines for the northern portion of the Site are shown on
Figure E-2
Groundwater in bedrock moves primarily in a westerly direction south of the Former Seepage
Bed while in the northern Study Area the predominant bedrock flow component is toward the
northwest In both areas the hydraulic gradient is on the order of 002 feet per foot Groundwater in bedrock near the Former Seepage Bed flows to the northwest and exhibits no apparent
influence from the locally identified fracture zones
Vertical Flow
Vertical flow of groundwater is an important component in the upper several feet of the bedrock
unit Water level measurements indicate that groundwater is discharging from bedrock into the
overburden at every location measured except MW109 In most clusters the vertical hydraulic
gradient between bedrock and overburden is an order of magnitude greater than the horizontal
gradient
In the overburden aquifer the downward vertical flow component is significant within shallow
deposits near the Former Primary Disposal Area (wells MW107 MW108 and MW116) and the
upward flow is important in the upper portion of the aquifer near Mill Brook The downward
groundwater flow within the Former Primary Disposal Area appears to be primarily associated
with infiltration of precipitation and collection of surface water runoff from upland areas This
causes VOC concentrations to be highest in the middle to lower portions of the aquifer Stream
5797wpdocsgallupftfinaltextexecsummri060997 E-12 QST Environmental
N
LEGEND
WATERCOURSE
PROPERTY BOUNDARY
bullPIEZOMETRIC HEAD CONTOUR LOWER PORTION OF AQUIFER NOVEMBER 6 1995 (FEET)
GROUNDWATER PATHLINE
NOTES
1 BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM - CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
400 400 800
SCALE IN FEET
410 Amherst Street Nashua NH 03063
(603) 889-3737 UmHOHHM
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE E-2
SJjTff WIDE GROUNDWATER FLOW DRAWING NAM6 RIWIDEFWDWG FILE NUMBER 7194 138
SCALEAS SHAWN REVISION 1 DRAWN BY DJB DATE 5997
Gallups Quarry Superfiind Project - RI Executive Summary
piezometer data and groundwater flow modeling indicate that Mill Brook generally gains water
from the overburden aquifer within the Study Area
E414 Ecology
Wetlands delineations were performed to the extreme northern and western boundaries of the
Study Area up to the Mill Brook channel using both the State of Connecticuts accepted criteria
(which focuses on soil types and hydric soil characteristics) and the Federal criteria using US
Army Corps of Engineer methods (which includes the examination of vegetation hydrology and
soils) Most of the wetlandupland boundary occurs along the edge of a steep grade The sharp
relief produces a narrow transition between uplands and wetlands The delineated lines reflect
this as the State and USACOE wetland boundaries coincide at nearly every location With the
exception of an area intersecting a small portion of the Site at the northernmost edge of the
property east of the former disposal areas no wetland areas were identified on the Site
A preliminary identification of plant and animal species present in the Study Area was conducted during the wetlands delineation A limited number of wildlife species were observed Numerous
plant species were identified over the heavily vegetated Study Area No endangered species were
observed nor are reported to reside in the Study Area
E42 Nature and Extent of Contamination
E421 Contaminant Source Investigation The following summarizes the findings of contaminant source investigations conducted during the
RI program
bull Previous remedial activities have completely removed the waste materials (intact drums and bulk liquid waste) from the Site
bull The Former Seepage Bed and the Former Secondary Disposal Area contain
little residual contamination from the disposal activities which occurred in the
late 1970s
bull Residual levels of contamination primarily VOC and PCB were measured in
the Former Primary Disposal Area In general the highest levels of VOC are
located at or just below the groundwater table in native soils immediately
beneath the fill materials and diminish rapidly with depth Low levels of
PCB were detected primarily within shallow fill materials
5797wpdocraquogallupftfinlaquoltextexecraquoummri060997 E-14 QST Environmental
Gallups Quarry Superfiutd Project - Rl Executive Summary
bull Other than the three known former disposal areas and the remains of a
former CTDOT asphalt plant no other disposal areas were found to exist on -
the Site
E422 Groundwater Quality
Groundwater quality data collected during the Remedial Investigation indicate the following
bull No significant groundwater contamination was detected within the overburden
or bedrock units in either the southern Study Area or in the vicinity of the
Former Seepage Bed
bull In the northern Study Area a narrow low to moderate-concentration VOC
plume was detected in the overburden aquifer extending from the vicinity of
the Former Primary Disposal Area to the northwest towards Mill Brook
TCA and DCE were consistently detected at all locations along the plume
centerline at concentrations as high as 240 ppb and 1300 ppb respectively
bull Comparison of present concentrations with historical data indicate that VOC
levels are significantly decreasing with time From 1978 through 1995 TCA
TCE and PCE concentrations have decreased on the average by more than a
factor of two every two years representing environmental half-lives of less
than two years
bull The size and orientation of the plume are in excellent agreement with the
established groundwater flow directions
bull Available information indicates that the leading edge of the VOC plume
associated with the Former Primary Disposal Area is located in the vicinity of
monitoring well clusters MW-102 and MW-101 Concentrations of TCA and
DCE reduce to below MCLs at MW-101 Contaminant migration rates also
support this delineation of the front of the site-related VOC plume
bull Increasing PCE detections in the downgradient portion of the plume exhibit
inconsistencies with calculated migration rates from the Site Groundwater
flow directions VOC transport rates and historical concentration trends
indicate that PCE detections in wells MW118 MW116 MW103 MW118
MW102 and MW101 may be associated with contaminant transport from the
former Pervel flock plant However it is also possible that the PCE
detections at locations MW102 and MW101 are attributable to the former
disposal areas In addition contaminated groundwater from Pervel may have
5797wpdocsgal]upfraquofinaltextexeclaquoummri060997 E-15 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
also contributed TCA TCE DCE and vinyl chloride to the site related VOC
plume
Results of surface watersediment sampling and analyses stream piezometer measurements and groundwater flow modeling indicate that some discharge
of the shallow portion of the plume into Mill Brook is occurring However
the concentrations of VOC detected in the brook are well below those
reported to cause adverse effects in fish or wildlife
Bedrock is not considered a preferred pathway for contaminant migration due
to its characteristically low hydraulic conductivity and the predominantly
upward component of groundwater flow from bedrock to overburden which
exists throughout the Study Area
5797wpdocsgallupftfinlaquoltcxtexec8ummri060997 E-16 QfT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents
Section Page
10 Introduction bdquo 1-1
11 Purpose of the Report 1-1 12 Report Organization 1-2
13 Site Background 1-3 131 Area Description Demography and Land Use 1-3 132 Operational History 1-5
133 Summary of Previous Investigations 1-7
20 Field Investigations 2-1
21 Site Survey 2-1
211 Initial Site Survey 2-1
212 As-Installed Survey 2-1
22 Site Reconnaissance 2-2
221 Visual Observations of the Ground Surface 2-2
222 Air Quality Survey 2-2
223 Exclusion Zone Identification 2-4
224 Project Support Measures 2-4
225 Identification of Sensitive Human Receptors 2-5
23 Geophysical Surveys 2-5
231 Electromagnetic Terrain Conductivity (EM) Survey 2-7 232 Magnetometer (MAG) Survey 2-7
233 Additional EM and MAG Surveys 2-8
234 Seismic Refraction Survey 2-8
24 Groundwater Sampling Using Temporary Well Points 2-9
25 Soil Gas Survey 2-12
26 Soil Borings at Disposal Areas 2-15
261 Phase 1A Soil Borings 2-15
262 Phase IB Soil Borings 2-16 27 Installation of Monitoring Wells and Background Soils Sampling 2-17
271 Phase 1A Monitoring Well Placement-Rationale 2-19
272 Phase IB Monitoring Well Placement-Rationale 2-21
273 General Monitoring Well Installation Techniques 2-22
274 Stream Piezometers and Gauges 2-24
5797wpdocsgalluprifinaltextmarterrifhl061297 i QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
Table of Contents (continued)
275 Groundwater Piezometers 2-25
28 Aquifer Parameter Testing 2-25
281 Grain Size Analysis 2-25
282 Slug Tests 2-26
283 Constant Flow Tests 2-26
29 Groundwater Sampling 2-26
291 Monitoring Wells 2-27
292 Residential Wells 2-29
210 Surface Water and Sediment Sampling 2-29
211 Wetland Soil Sampling 2-31
212 Evaluation of Existing Monitoring Wells 2-31
213 Ecological Assessment 2-32
2131 Wetland Delineation 2-32 2132 Plant and Wildlife Survey 2-33
214 Test Pit Explorations 2-33
30 Physical Characteristics of the Study Area 3-1
31 General Characteristics 3-1
311 Regional Physiography 3-1
312 Study Area Physiography 3-1
313 Surface Water Features 3-2
314 Climate 3-3
32 Geology 3-3
321 Regional Surficial Geology 3-3
322 Local Surficial Geology 3-4
323 Regional Bedrock Geology 3-7
324 Local Bedrock Geology 3-8
33 Hydrogeology 3-9
331 Hydraulic Conductivity 3-9
332 Groundwater Flow 3-10
34 Ecology 3-17
341 Wetland Delineation 3-17
342 Plant and Animal Survey 3-19
40 Nature and Extent of Contamination 4-1
41 Contaminant Source Investigation 4-2
5797wpdocsggtlluprifinaltextmasteiTifhl061297 ii QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
Table of Contents (continued)
411 Visual Site Reconnaissance 4-2
412 Soil Vapor Survey 4-4
413 Geophysical Investigations and Test Pits 4-5
414 Background Soils 4-6
415 Soils From Former Known Disposal Areas 4-7
416 Contaminant Source Investigations Summary 4-15
42 Groundwater Quality 4-17
421 Temporary Well Point Investigation 4-17
422 Groundwater Monitoring Wells 4-18
423 Residential Wells 4-26
43 Surface Water Sediment and Wetland Soils 4-27 431 Surface Water 4-27
432 Sediment 4-31
433 Wetland Soils 4-32
44 Air Quality 4-34
441 Baseline Air Quality Survey 4-34
442 Perimeter Air Monitoring 4-34
45 Potential Sensitive Human Receptors 4-35
50 Contaminant Fate and Transport 5-1
51 Theory 5-1
511 Advection by Groundwater Flow 5-1
512 Dispersion 5-3 513 Advection Due to Fluid Density Differences 5-5
514 Biological and Chemical Degradation 5-5
515 Volatilization 5-7
516 Aqueous Solubility 5-7
52 Study Area-Specific Characteristics 5-7
521 Retardation Factors 5-7
522 Chemical Migration Rates 5-9
523 Time-Dependent Concentration Reductions 5-14
5797wpdocBg8lluprifinaltextmlaquo8terrifhl061297 Hi QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
60 Summary and Conclusions 6-1
61 Conceptual Model of the Study Area 6-1
611 Geology 6-1
612 Hydrogeology 6-2
613 Nature and Extent of Contamination bdquo 6-5
70 References 7-1
5797wpdocsgnlluprifinlaquoltextmasterriftil061297 Jy QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Table of Contents (continued)
List of Tables
Table 1-1 Summary of Results of Groundwater Analyses (CTDEP)
Table 1-2 Summary of Results of Groundwater Analyses (MampE 1993)
Table 1-3 Summary of Results of Groundwater Analyses Former Pervel Flock Plant (HRP)
Table 2-1 Microwell Sampling Intervals
Table 2-2 Former Disposal Area Soil Samples Submitted for Laboratory Analyses
Table 2-3 Monitoring Well Survey Data and Screen Intervals
Table 2-4 Geologic Descriptions of Soil Samples Collected for Grain Size Analyses
Table 2-5 Sample Inventory
Table 2-6 Existing Well Summary
Table 3-1 Hydraulic Conductivity Values
Table 3-2 Hydraulic Conductivity Values Estimated from Grain Size Distributions
Table 3-3 Monitoring Well Water Level Elevation Data
Table 3-4 Summary of Vertical Hydraulic Gradients Between Pairs of MWs in Study Area
Table 3-5 Stream Piezometer Water Level Elevation Data
Table 3-6 Plants Identified During the Wetland Delineation
Table 4-1 Summary of Visual Site Reconnaissance
Table 4-2 Background Soil Volatile Organic Compounds Table 4-3 Background Soil MetalsCyanide
Table 4-4 Disposal Areas Soil Volatile Organic Compounds
Table 4-5 Disposal Areas Soil Semivolatile Organic Compounds
Table 4-6 Disposal Areas Soil PesticidesPCB
Table 4-7 Disposal Areas Soil MetalsCyanide
Table 4-8 Microwell Survey Selected Volatile Organics
Table 4-9 Microwell Survey Results of Volatile Organics Laboratory Analyses
Table 4-10 Microwell Survey Results of Inorganic Laboratory Analyses
Table 4-11 Groundwater Volatile Organic Compounds January 1995
Table 4-12 Groundwater Volatile Organic Compounds April 1995
Table 4-13 Groundwater Volatile Organic Compounds July 1995
Table 4-14 Groundwater Volatile Organic Compounds November 1995
5797wpdocggalluprifinraquoltextmalaquoterrifhl061297 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Tables (Contd)
Table 4-15 Groundwater Volatile Organic Compounds February 1996
Table 4-16 Groundwater Volatile Organic Compounds May 1996
Table 4-17 Groundwater Volatile Organic Compounds August 1996
Table 4-18 Groundwater Volatile Organic Compounds November 1996
Table 4-19 Groundwater Volatile Organic Compounds February 1997
Table 4-20 Groundwater Semivolatile Organic Compounds January 1995
Table 4-21 Groundwater Semivolatile Organic Compounds April 1995
Table 4-22 Groundwater Semivolatile Organic Compounds July 1995
Table 4-23 Groundwater Semivolatile Organic Compounds November 1995
Table 4-24 Groundwater Semivolatile Organic Compounds February 1996
Table 4-25 Groundwater Semivolatile Organic Compounds May 1996 Table 4-26 Groundwater Semivolatile Organic Compounds August 1996
Table 4-27 Groundwater Semivolatile Organic Compounds November 1996
Table 4-28 Groundwater Semivolatile Organic Compounds February 1997
Table 4-29 Groundwater PesticidesPCB April July and November 1995 February and August 1996 February 1997
Table 4-30 Groundwater MetalsCyanide January 1995
Table 4-31 Groundwater MetalsCyanide April 1995
Table 4-32 Groundwater MetalsCyanide July 1995
Table 4-33 Groundwater MetalsCyanide November 1995
Table 4-34 Groundwater MetalsCyanide February 1996
Table 4-35 Groundwater MetalsCyanide May 1996
Table 4-36 Groundwater MetalsCyanide August 1996
Table 4-37 Groundwater MetalsCyanide November 1996
Table 4-38 Groundwater Metals February 1997
Table 4-39 Residential Wells Volatile Organic Compounds January 1995
Table 4-40 Residential Wells Volatile Organic Compounds July 1995
Table 4-41 Residential Wells Volatile Organic Compounds February 1996
Table 4-42 Residential Wells Volatile Organic Compounds August 1996
Table 4-43 Residential Wells PesticidesPCB January 1995
Table 4-44 Residential Wells PesticidesPCB July 1995
Table 4-45 Residential Wells PesticidesPCB February 1996
Table 4-46 Residential Wells PesticidePCB August 1996
Table 4-47 Residential Wells Metals January 1995
5797wpdocsg lluprifinaltextmastemfiil061297 VI QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Tables (Contd)
Table 4^8 Residential Wells Metals July 1995
Table 4-49 Residential Wells MetalsCyanide February 1996
Table 4-50 Residential Wells MetalsCyanide August 1996
Table 4-51 Field Observations of Habitat and Water Quality September 1994
Table 4-52 Surface Water Quality April and November 1995 May and November 1996
Table 4-53 Surface Water Volatile Organic Compounds September 1994
Table 4-54 Surface Water Volatile Organic Compounds April 1995
Table 4-55 Surface Water Volatile Organic Compounds November 1995
Table 4-56 Surface Water Volatile Organic Compounds May 1996
Table 4-57 Surface Water Volatile Organic Compounds November 1996
Table 4-58 Surface Water Volatile Organic Compounds September 1994 April 1995 May
1996
Table 4-59 Surface Water Total MetalsCyanide September 1994
Table 4-60 Surface Water Dissolved Metals September 1994
Table 4-61 Surface Water Total Metals April 1995
Table 4-62 Surface Water Dissolved Metals April 1995
Table 4-63 Surface Water Total and Dissolved Metals November 1995
Table 4-64 Surface Water Total and Dissolved Metals May 1996
Table 4-65 Surface Water Total and Dissolved Metals November 1996
Table 4-66 SedimentWetland Soils Metals September 1994
Table 4-67 SedimentWetland Soils Volatile Organic Compounds September 1994 Table 4-68 SedimentWetland Soils Semivolatile Organic Compounds September 1994
Table 4-69 SedimentWetland Soils PesticidesPCB September 1994
Table 4-70 Human Receptors Survey Location of Day Care Facilities Within 1-Mile Radius
of Site
Table 5-1 Fate and Transport Parameters for Study Area Volatile Organic Compounds
Table 5-2 Total Organic Carbon Measurements for Soil Samples
Table 5-3 Historical Concentration Data
5797wpdoclaquoglaquolluprifinaltextmasterriftil061297 Vll QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Figures
Figure E-l Site Location Map
Figure E-2 Site Wide Groundwater Flow
Figure 1-1 Site Location Map
Figure 1-2 Property Boundaries and Adjacent Landowners
Figure 1-3 Surface Water and Groundwater Classification Zones and Locations of Former
Disposal Areas
Figure 1-4 Groundwater Monitoring Wells Installed by Fuss amp ONeill
Figure 1-5 Site Location Map and Nearby Industrial Properties
Figure 3-1 Groundwater Elevations MW101 Series Figure 3-2 Groundwater Elevations MW102 Series
Figure 3-3 Groundwater Elevations MW103 Series
Figure 3-4 Groundwater Elevations MW104 Series
Figure 3-5 Groundwater Elevations MW105 Series
Figure 3-6 Groundwater Elevations MW106 Series
Figure 3-7 Groundwater Elevations MW107 Series
Figure 3-8 Groundwater Elevations MW108 Series
Figure 3-9 Groundwater Elevations MW109 Series
Figure 3-10 Groundwater Elevations MW110 Series
Figure 3-11 Groundwater Elevations MW111 Series
Figure 3-12 Groundwater Elevations MW112 Series
Figure 3-13 Groundwater Elevations MW113 Series
Figure 3-14 Groundwater Elevations MW114 Series
Figure 3-15 Groundwater Elevations MW115 Series
Figure 3-16 Groundwater Elevations MW116 Series
Figure 3-17 Groundwater Elevations MW117 Series
Figure 3-18 Groundwater Elevations MW118 Series
Figure 3-19 Groundwater Elevations MW119 Series
Figure 3-20 Groundwater Elevations SW3 Series
Figure 3-21 Three-Dimensional Groundwater Flow Map
5797wpdoc8galluprifiruiltextmasterriftil061297 viii QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
Figure 5-1
Figure 5-2
Figure 5-3
List of Figures (Contd) Groundwater VOC Concentrations vs Time - Downgradient from Former
Primary Disposal Area
Groundwater VOC Concentrations vs Time - Near Former Pervel Facility
Groundwater VOC Concentrations vs Time - Downgradient Portion of VOC
Plume
Figure 5-4 Evaluation of Biodegradation and Rainwater Dilution Rates in VOC Plume
5797wpdocraquogalluprifinaltextmasterrifhl061297 ix QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Plates
Plate 2-1 Baseline Survey Grid Air Monitoring Seismic Refraction Line Locations
Plate 2-2 Microwell Locations
Plate 2-3 Soil Vapor Probe and Soil Boring Locations
Plate 2-4 Monitoring Wells PiezometersStream Gauge Locations
Plate 2-5 Residential Well Locations
Plate 2-6 Surface WaterSediment and Wetland Soil Sampling Locations
Plate 2-7 Location of Test Pits Performed at Geophysical Anomalies
Plate 3-1 Study Area Topographic Features
Plate 3-2 Geologic Cross-Sections A-A amp C-C Plate 3-3 Geologic Cross-Section D-D
Plate 3-4 Geologic Cross-Section B-B Plate 3-5 Geologic Cross-Sections E-Eamp F-F
Plate 3-6 Bedrock Surface Contour Map
Plate 3-7 Bedrock Fracture Zones as Determined by Seismic and Magnetometer Surveys
Plate 3-8 Lower Overburden Piezometric Surface November 6 1995
Plate 3-9 Shallow Overburden Piezometric Surface November 6 1995
Plate 3-10 Saturated Overburden Thickness November 6 1995
Plate 3-11 Bedrock Piezometric Surface November 6 1995
Plate 3-12 Vertical Ground water Flow Through Plume Center Line
Plate 3-13 Deep vs Shallow Piezometric Head Differences
Plate 3-14 Wetland Delineation Map September 1994
Plate 4-1 Survey Grid amp Features Noted During Site Reconnaissance August-September
1994
Plate 4-2 Former Primary Disposal Area Soil Borings VOC Data and Cross-Sections
Plate 4-3 Former Primary Disposal Area Soil Borings PCB Data and Cross-Sections
Plate 4-4 VOC Detections Field GC and Laboratory Analyses in Microwells
Plate 4-5 Laboratory Results of Metals Analyses in Microwells
Plate 4-6 Groundwater VOC Data January April July and November 1995 Sampling
Events
Plate 4-7 Groundwater VOC Data February May August and November 1996 and
February 1997 Sampling Events
Plate 5-1 Groundwater Travel Times in Overburden Aquifer November 6 1995
5797wpdocsgi lluprifinaltextmasteirifnl061297 X QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
Table of Contents (continued)
List of Appendices
Appendix A Weston Geophysical Inc Report
Appendix B Microwell Logs
Appendix C Soil Boring and Rock Coring Logs and Well Construction Forms
Appendix D Groundwater Sampling Forms
Appendix E Test Pit Logs
Appendix F Single-Well Hydraulic Conductivity Test Procedures
Appendix G Grain Size Data
Appendix H Phase 1A Laboratory Reports
Appendix I April 1995 Laboratory Reports
Appendix J July 1995 Laboratory Reports
Appendix K Phase IBNovember 1995 Laboratory Reports
Appendix L February 1996 Laboratory Reports
Appendix M May 1996 Laboratory Reports
Appendix N August 1996 Laboratory Reports
Appendix O November 1996 Laboratory Reports
Appendix P February 1997 Laboratory Reports
Appendix Q Data Validation Reports
Appendix R pH TOC Moisture Results Soil Samples
Appendix S Environmental Metals Statistics
Appendix T Air Monitoring Results
Appendix U Model of Groundwater Near Mill Brook Appendix V Methodology for Piezometric Head Contouring and Groundwater Pathline
Generation
5797wpdocsgalluprifinlaquoltextmagterri fhl061297 XI QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
10 Introduction
11 Purpose of the Report This document presents the Remedial Investigation Report (RI) which was completed for the
Gallops Quarry Superfund Site (Site) pursuant to the requirements of US Environmental
Protection Agency (EPA) Administrative Order by Consent Docket Number 1-93-1080 (Order)
issued September 7 1993 The Gallups Quarry property is the site of a former sand and gravel
quarry and is located on Tarbox Road in the town of Plainfield Windham County Connecticut
(see Figure 1-1) According to the Town of Plainfield Tax Assessors office the property (Map
10 Block 30 Lot 32) is an irregularly shaped parcel comprised of approximately 29 acres
Investigation of the quarry was initiated in 1978 when unlicensed waste disposal operations were
discovered at the property Emergency clean-up operations were conducted by the Connecticut
Department of Environmental Protection (CTDEP) in April 1978 (Metcalf amp Eddy 1993)
Following the initial clean-up effort a study was conducted to characterize the nature and extent
of residual contamination at the Site (Fuss amp ONeill 1979) A series of surface and subsurface
sampling events conducted by the CTDEP the Connecticut Department of Health and the US
Environmental Protection Agency (EPA) between the years of 1978 and 1988 prompted EPA to
propose on June 21 1988 that the Site be listed on the National Priorities List (NPL) The Site
was finally listed on the NPL on October 4 1989 During 1992 and 1993 EPA conducted a
limited investigation through the Superfund Technical Assessment amp Response Team (START)
initiative in an effort to expedite the completion of the Remedial InvestigationFeasibility Study
(RIFS) The requirements of the Order as well as data included in the START report (Metcalf
amp Eddy 1993) provided the framework for this investigation
This Report is the sixteenth major deliverable under the Order The first major deliverable the
Remedial InvestigationFeasibility Study Work Plan - Phase 1A was finalized and submitted to
EPA on August 29 1995 QST Environmental (formerly Environmental Science amp Engineering
Inc (ESE)) finalized the Work Plan and has prepared all of the other deliverables The Phase 1A
field investigation was completed in January 1995 The second major deliverable the Phase 1A
Data Report dated March 24 1995 was submitted to EPA following completion of the Phase 1A
field investigation The findings of the Phase 1A investigation were described in the Initial Site
Characterization Report (ISCR) which was finalized and submitted to EPA on March 1 1996 A
Work Plan for the Phase IB field investigation was also finalized and submitted on October 11
1995
In addition to the actual Phase 1A field investigation the Phase 1A Work Plan also described the
Long Term Monitoring Program which was initiated upon completion of the Phase 1A field
5797wpdocraquogalluprifinaltextmlaquoiterrifhl061297 1-1 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
investigation The Long Term Monitoring Program includes the quarterly collection and analysis
of groundwatei and semi-annual collection and analysis of surface water and nearby residential
well samples
The Phase IB field investigation commenced on October 12 1995 Following the completion of
drilling activities the Phase IB groundwater sampling task and the fourth quarter 1995 Long
Term Monitoring sampling event were performed simultaneously in November 1995 Seven
Data Reports have been submitted to the EPA for the following Long-Term Monitoring Program
sampling events the second and third quarters of 1995 all four quarters of 1996 and the first
quarter of 1997 (ESE 1996a 1996b 1996c 1997a 1997b) The draft RI Report was submitted
to EPA on March 15 1996 (and revised and resubmitted October 22 1996) and included the
results of the fourth quarter of 1995 sampling event On March 29 1996 the following two
deliverables were submitted to EPA Development and Initial Screening of Alternatives Report
and Detailed Analysis Work Plan The draft Feasibility Study was submitted to EPA on January
27 1997 This RI Report describes the methods and findings of both the Phase 1A and IB field
studies and includes data collected during the April July and November 1995 February May
August and November 1996 and February 1997 Long-Term Monitoring sampling events
12 Report Organization The RI is presented in seven main sections following the Executive Summary The remainder of
Section 1 presents Site background information Section 2 presents the various field methods and
procedures used during the field investigations including descriptions of any changes or
deviations from the Work Plan Section 3 describes the physical characteristics of the Study
Area and Section 4 presents the findings of studies designed to determine the nature and extent of
contamination within the Study Area Section 5 is a discussion of the various fate and transport
mechanisms associated with the contaminants of concern Section 6 summarizes the conceptual
model of conditions within the Study Area Finally a list of references cited in this report is
presented in Section 7
Volume 1 of this Report presents the text and figures of the RI Volume 2 contains all Tables
referenced in the report Volume 3 contains all Plates referenced in the Report Volume 4 and
all subsequent volumes contain the Appendices referenced in the Report
5797wpdocggaIluprifinaltextmasterrifhl061297 1-2 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
13 Site Background 131 Area Description Demography and Land Use
For the purposes of this report the Site is considered to be the actual property owned by the
late Stanton Gallup from 1964 until his death in 1994 The Study Area includes the Site as
well as surrounding properties from which data were collected during the RI
The Site is located on the north side of Tarbox Road in the Town of Plainfield Windham County
Connecticut (see Figure 1-1) The Site is situated approximately 2000 feet west of interchange
87 on Interstate 395 and approximately one-mile southwest of Plainfield Center As shown on
Figure 1-2 the Site is irregularly shaped and is approximately 2200 feet long (north to south)
and 300 to 1100 feet wide (east to west) A number of previous references have described the
Site as ranging in size from 20 to 22 acres however the Town of Plainfield Tax Maps and areal
calculations performed by ESE indicate that the size of the Site is approximately 29 acres In
addition to the Site the Study Area includes additional areas located to the north and northwest of
the Site (as shown on Figure 1-1) and a number of discrete smaller areas located to the east and
south of the Site used for collecting upgradient surface watersediment samples
The Site is currently vacant and much of it is heavily vegetated Numerous overgrown mounds
and excavations are scattered across the Site and are presumed to be features remnant of the
former sand and gravel quarry operations Other than concrete foundations remnant of former
Site operations no structures presently exist on the property Surface features observed on the
Site during the Phase 1A visual reconnaissance survey are described in more detail in Section
411
As shown on Figure 1-2 the Site is bounded to the east by Route 12 (Norwich Road) single-family residences and a plumbing supply company An active railroad right-of-way (presently
operated by the Providence and Worcester Railroad) bounds the Site to the west Wooded areas
and wetlands associated with Mill Brook bound the Site to the north and Tarbox Road and several
single family residences bound the Site to the south
Surface water bodies located within or near the Study Area include Mill Brook Fry Brook and
Packers Pond As shown on Figure 1-3 Mill Brook flows from east to west along the northern
edge of the Study Area until its confluence with Fry Brook Mill Brook turns toward the south
at this confluence and continues flowing in a south-southwesterly direction (as Mill Brook) and
eventually drains into Packers Pond [Note Packers Pond is not shown on Figure 1-3 due to the
larger scale of this figure however the relative location of Packers Pond approximately 1 mile
west of the Site can be seen on Figure 1-1]
5797wpdocBgalluprifinaltextmasteiTifhl061297 1-3 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Based on the CTDEP Water Quality Classification Map of Thames Southeast Coast and
Pawcatuck River Basins Sheet 2 of 2 (1986) surface water located within the section of Mill
Brook between Route 12 and the confluence with Fry Brook (shown on Figure 1-3) is classified
as BA The BA classification indicates that the surface water body may not be meeting the
Class A water quality criteria for one or more designated uses which include potential drinking
water supply fish and wildlife habitat recreational use and agricultural and industrial supply
although the goal is to ultimately restore the water body to Class A standards Surface water
within Fry Brook and the lower section of Mill Brook (located down stream of the confluence of
the two brooks) is classified as Be The Be classification indicates that the water meets Class B
criteria and is suitable for cold water fisheries The designated uses for Class B surface water
include most of those described for Class A however Class B waters are NOT designated as a
potential drinking water supply Surface water located within Packers Pond (not shown on Figure
1-3) is designated as CBc The CBc designation indicates that Packers Pond is not meeting the
Class B water quality criteria for one or more designated uses or is a Class C water body which
is basically a downgraded version of Class B However the CTDEP goal for surface water
designated as CBc is to restore it to Class B conditions
As shown on Figure 1-3 groundwater located within the northern portion of the Study Area
between Route 12 and the MillFry Brook confluence is classified as GBGA which indicates that
the groundwater may not be suitable for direct human consumption without the need for treatment
due to waste discharges spills or leaks of chemicals or land use impacts The CTDEP goal for
groundwater classified as GBGA is to prevent further degradation by preventing any additional
discharges which would cause irreversible contamination Groundwater at all other locations
within the Study Area is classified as GA which is presumed suitable for direct human
consumption without need for treatment In addition one of the goals of the CTDEP for
groundwater classified as GBGA is to restore it to GA standards
It should be noted that the surface water classifications described above are based on existing
CTDEP maps which were published prior to the preparation of this report During the course of
this investigation the CTDEP proposed amendments which were intended to clarify the language
of the States Water Quality Standards and simplify the Departments system for considering
requested modifications Based on conversations with a representative of the CTDEP (Personal
Communication Bobowitz 1996) the single letter (eg Class A) and dual letter (and associated
goal) classification (eg BA) system will be maintained Areas presently designated by dual
classifications will only be modified once the desired goal for that water body or aquifer has been
attained According to the CTDEP the only significant change will be the eventual elimination of
the use of lower case suffixes (eg Be) which are currently used to indicate very specific
restrictions or uses for certain water bodies (ie B rather than Be)
5797wpdocsgalluprifinaltextmasterrifhl061297 1-4 QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
Within the Study Area directly west of the Site (across the railroad tracks) are open cropland
(presently a cornfield) wooded areas and a residential property (parcel 24 shown on Figure 1shy
2) The property boundaries and land owners for the Site and other nearby parcels are also
shown on Figure 1-2 Immediately north of the Site are approximately 85 acres of wooded
undeveloped land through which flows Mill Brook An overhead power line easement (not shown
on Figure 1-2) runs adjacent to the northernmost Site boundary On the north side of Mill Brook
is an industrial park which contains an Intermark Fabric Corporation facility (formerly the Pervel
Industries flock plant) and a Safety Kleen Corporation accumulation facility Northeast of Mill
Brook are woodlands and Saint Johns Cemetery Further north of the industrial park are several
vacant mill buildings which were occupied until the late 1980s by various manufacturers including
Pervel Industries and the InterRoyal Corporation The Plainfield sewage treatment plant which
discharges to Mill Brook and its major tributary (Fry Brook) is located approximately 1800 feet
northwest of the property
The Town of Plainfield with a land area of 427 square miles has a population of approximately
14200 Plainfields principal industries include varied manufacturing and distribution centers as
well as tourism based businesses In addition the rural areas of Plainfield are occupied by many
small dairy and produce farms
^ 132 Operational History
Information regarding the operational history of Gallups Quarry was obtained from published
reports for previous Site studies including Site Analysis Gallups Quarry Plainfield CT
(Bionetics Corporation 1990) and Final Data Summary Report START Initiative (Metcalf amp
Eddy 1993) as well as information from various sources collected during the preparation of the
Gallups Quarry Remedial InvestigationFeasibility Study Work Plan (ESE 1994) Little detailed information concerning the early operational history of the Site exists
A review of an aerial photograph of the Site taken in 1951 depicts the Site as an undeveloped
parcel although some quarry activities in the southern portion of the property appear to be
underway (ESE 1994) Records at the town of Plainfield Assessors office indicate that in 1951
the Site was owned by a Mr Johnson who was operating a sand and gravel quarry In 1964 the
Site was purchased by C Stanton Gallup (Metcalf amp Eddy 1993) Although detailed usage of
the Site from 1964 through 1977 is poorly documented records indicate that the Site was used as
a source of aggregate and was occupied by the Connecticut Department of Transportation
(CTDOT) which operated an asphalt batching plant (ESE 1994) The exact date of CTDOT
presence at the Site is unclear although it is believed to coincide with the construction of Route
52 (now known as Interstate 395) Evidence of the former asphalt batching plant operations are
5797wpdocsgalluprifinalteirtinalaquoterrifhl061297 1-5 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
still present at the Site Mounds of asphalt paving material and areas covered with hardened
liquid asphalt ere observed at a number of locations throughout the Site
As a result of complaints from neighboring residents the CTDEP and the Connecticut State
Police initiated an investigation of the Site in early January 1978 During a Site visit on January
13 1978 representatives of the CTDEP reportedly observed partially buried drums containing
suspected hazardous materials and ordered that all Site operations be stopped The CTDEP
investigation concluded that the Site was used from the summer of 1977 until December 1977 for
unlicensed waste disposal
As described in the Order evidence collected by CTDEP indicates that Chemical Waste Removal
Inc (CWR) of Bridgeport Connecticut transported drummed and bulk liquid waste material to the
Site and was the sole known transporter of waste to the Site These wastes reportedly included a
variety of industrial wastes which were transported to and disposed of at the Site It was reported
that Mr Gallup jointly operated the quarry with Mr Dick Trayner of Dick Trayner and Sons
Trucking Company at the time of the illegal waste disposal activities
According to CTDEP and State Police records the drums and liquid wastes were reportedly
disposed of at three distinct locations on the Site These areas were subsequently labeled the
Primary Disposal Area the Secondary Disposal Area and the Seepage Bed The Primary and
Secondary Disposal Areas were reportedly located in the northern portion of the Site while the
Seepage Bed was reportedly located in the central portion of the Site The reported locations of
these former disposal areas are shown on Figure 1-3
According to a report issued by Fuss amp ONeill (FampO 1979) the Primary Disposal Area
consisted of an area approximately 04 acres in size The Secondary Disposal Area was described
by the FampO report as a linear trench which encompassed an approximate area of 007 acres
located adjacent to the railroad tracks and just west of the Primary Disposal Area The Seepage
Bed was located in the central portion of the Site and according to the FampO report was
approximately 40 feet by 50 feet in size and consisted of an excavation into which an inverted
truck body filled and covered with crushed stone was placed A metal pipe which extended
from the dump body to the ground surface was reportedly used for direct discharge of liquid
wastes According to the FampO report the liquid wastes reportedly disposed of in the Seepage
Bed consisted of low pH liquids which were believed to be by-products associated with metal
finishing operations
Initial cleanup efforts were performed by Chem-Trol Inc during the summer of 1978 under the
direction of the CTDEP and the Connecticut State Police A Connecticut State Police Possessed
5797wpdocsglaquolluprifinaltextmasterrifhl061297 1-6 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
Property Report (PPR) lists the following materials as removed from the Site 1584 drums (some
of which were crushed andor decomposed) 5000 gallons of free liquid and 2277 cubic yards
of contaminated earth The PPR also lists 127715 tons of moderately contaminated soil which
was removed from the Site Additional remedial measures included the neutralization of residual
contamination at the Seepage Bed by placing 20 tons of lime at that location
Although no information concerning the actual number of drums or quantity of waste transported
to the Site by CWR is available it was believed that all of the drums had been recovered upon
completion of the cleanup operations Mine detectors were utilized to search for additional buried
drums however no indications of additional buried drums were discovered
Since the 1978 cleanup operations the Site has been vacant Public vehicular access to the Site
has been limited by the placement of boulders and mounded soil at access locations around the
Site During this time evidence of off-road vehicle tire tracks and small quantities of debris
(beverage cans bottles spent shotgun shell casings and empty gasoline cans) indicate that the
Site has been utilized by trespassers for recreational purposes However it appears that Site
usage has decreased since August 1994 when fencing and additional boulders were placed at
potential access locations and the perimeter of the property was posted with warning signs
133 Summary of Previous Investigations
Following the CTDEP removal activities a number of environmental investigations and sampling
events were conducted at the Gallups Quarry Site This section summarizes environmental
studies conducted at the Site prior to the RIFS as compiled performed and reported by Metcalf
amp Eddy (1993) as part of the EPAs Region I START Initiative or as reported by the original
investigators)
1331 Evaluation of a Chemical Waste Disposal Area Tarbox Road Site Plainfield Connecticut Fuss amp ONeill 1979
Between June 6 and October 30 1978 Fuss amp ONeill Inc performed a hydrogeological
investigation within the Study Area in conjunction with the cleanup and remedial operations
directed by the CTDEP and Connecticut State Police The findings of this investigation were
presented in a report issued to the CTDEP dated January 29 1979 The tasks completed during
this investigation included the following
bull The installation of 22 test borings which were completed as groundwater
monitoring wells (SW series) including three shallow-bedrock wells near the
Former Seepage Bed (SW-10 SW-11 SW-12) The locations of these wells are
shown in Figure 1-4
5797wpdocsgalluprifinaltextmlaquo8terrifhl061297 1-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
bull Excavation of 19 test pits (using a backhoe) 13 of which were completed as
shallow groundwater monitoring wells
bull The establishment of 12 surface water gauging stations along Mill Brook and Fry
Brook
bull The collection of surface water and groundwater water for laboratory analysis
FampO collected groundwater samples from the monitoring wells in July October and December
1978 Several nearby domestic wells were also sampled in July and October 1978 Groundwater
samples were analyzed for metals volatile organic compounds (VOC) and the following general
chemical parameters chemical oxygen demand (COD) total dissolved solids (TDS) total
Kjeldahl nitrogen (TKN) chloride total organic carbon (TOC) total carbon total cyanide
specific conductance and pH
FampO also collected surface water samples from seven of the stream gauging stations in
September October and November 1978 In general the surface water samples were analyzed
for the same chemical parameters described above
The chemical testing results indicated groundwater in the vicinity and downgradient of the Former
Disposal Areas had been impacted by several organic and inorganic constituents VOC detected
included ethanol methanol isopropanol ethyl acetate acetone toluene benzene trichloroethene
(TCE) 111- trichloroethane (TCA) tetrachloroethene (PCE) methyl isobutyl ketone (MIBK)
methyl ethyl ketone (MEK) and methylene chloride Various metals including aluminum
chromium copper magnesium nickel zinc iron and silver were reported at widely variable
concentrations in some groundwater samples According to the START Report the domestic
wells did not appear to be significantly impacted
FampO concluded that a well-defined groundwater contaminant plume extended from the former
disposal areas towards Mill Brook northwest of the Site and that the flow direction of the plume
was controlled by the local water table gradient The plume was characterized by the presence of
organic compounds which included acetate benzene ethanol isopropanol MEK MIBK
toluene TCA and xylene The plume also contained widely variable concentrations of various
metals including copper nickel boron aluminum magnesium manganese iron silver
cadmium and lead
The START Report indicated that since little or no information is available regarding FampOs field
methods (eg field notes chain-of-custody collection of field QC samples) or analytical
5797wpdoc8galluprifinaltextmastemfnl061297 1-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
methods (eg detection limits turbidity filtering sample preservation analysis of lab QC
samples) comparison of the test results to current regulatory criteria (eg Maximum Contaminant
Levels [MCL]) was not appropriate for any definitive purpose
1332 CTDEP Periodic Monitoring 1979 to 1983
As described in the START Report the CTDEP performed periodic monitoring of groundwater
(including domestic wells) surface water and sediment in the Study Area from 1979 until 1983
The periodic monitoring was not systematic in terms of the wells or locations that were sampled
or the parameters tested for The results of the CTDEP monitoring are in the form of laboratory
results compiled and presented in the START report A summary table of results for the CTDEP
groundwater monitoring activities as presented in the START report is included in this report as
Table 1-1
The dates of groundwater sample collection and analysis for the CTDEPs monitoring program
are as follows
bull October 1979
bull January 1980
bull November 1980
bull April 1981
bull October 1981
bull April 1982
Sample analytical parameters varied from event to event but typically included pH COD
specific conductivity hydrocarbons chlorides and selected metals (cadmium chromium copper iron nickel and zinc)
The CTDEP also collected surface water and sediment samples on the following dates
bull January 1980 (surface water)
bull October 1981 (surface water and sediment)
bull April 1982 (surface water)
bull December 1983 (surface water)
It was noted in the START Report that no information was available regarding the CTDEP sampling methods or analytical procedures and that this limited the usefulness of the data except
for comparative purposes Nonetheless the START Report concluded that the available analytical
data collected by CTDEP during the period from 1972 to 1982 indicated that the Site and areas to
5797wpdoc8falluprifinaltextmasterrifnl061297 1-9 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
the north-northwest were impacted by the past disposal of VOC metals and acid wastes This
conclusion wa5 based on the fact that up until the last recorded groundwater sampling event
performed by CTDEP (1982) four monitoring wells (SW7D SW13 SW17S and SW17D)
exhibited detectable concentrations of contaminants characteristic of the types of wastes which
were reportedly disposed of on the Site The contaminants detected in these wells included
various common industrial organic solvents (both chlorinated hydrocarbons and ketones) as well
as several petroleum aromatic hydrocarbons Chlorinated hydrocarbon concentrations for these
wells ranged from 10000 to 80000 parts per billion (ppb) for 111-Trichloroethane (TCA) 30
to 1000 ppb for Tetrachloroethane (PCE) and 1000 to 14000 ppb for Trichloroethene (TCE)
Ketones detected included Acetone (5000 to 22000 ppb) methyl ethyl ketone (MEK) ranged
from 12000 to 150000 ppb and methyl iso butyl ketone (MIBK) ranged from 60 to 7000 ppb)
The main aromatics detected included toluene (up to 17000 ppb) and xylene (up to 3000 ppb)
1333 CTDEP BioDiversity Study 1985
The CTDEP conducted a field survey on November 4 1985 to evaluate potential impacts from
migration of groundwater from the Site to the Mill Brook wetland The study was conducted in
an area where leachate was observed to be breaking out from the wetlands into Mill Brook
The precise location is unclear however the START Report indicates that the impact zone was
subjectively estimated to be approximately 200 feet west of the railroad bridge The leachate
was described as an area showing evidence of organic enrichment and iron hydroxide precipitation
which extended a distance of approximately 100 feet downstream
The study reported a background species Diversity Index value of 257 compared to a value of
236 for the area of study The minor difference in diversity represented by this measure was
primarily considered to be a result of low flow conditions as much higher diversity indices
indicative of excellent water quality were observed during a previous bioassessment in that
area
As part of the CTDEP study four surface water samples were collected (one control and three
downstream) from Mill Brook on 8 November 1985 for acute aquatic toxicity bioassays using
water fleas (Daphniapulex) The results of this testing are summarized in a CTDEP
interdepartmental memorandum (dated November 18 1985) that is included with the results of the
biodiversity study The assay employed three replicates per sample and 10 individual organisms
per replicate The endpoint of the assay was percent survival after 48 hour exposure to the water
All samples yielded average survival rates of greater than 83 Based on the results of the tests
the CTDEP concluded that no acute toxicity was demonstrated
5797wpdocsgalluprifinaltextmasterrifnl061297 1-10 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The BioDiversity study report indicated that well MW17S was sampled and that a strong
solventacid odor was noted Further information on sampling and analyses of this well by
CTDEP in 1985 was not included in the report
1334 Hazard Ranking System (HRS) Study - NUSFIT 1986 to 19874
On September 15 1987 the Superfund Division of NUS Corporation completed the Final HRS
Documentation Package for Gallups Quarry The package contains information on the cleanup
and subsequent environmental evaluations including State Police documents and logs regarding
the investigation into the unlicensed disposal activities CTDEP and State Police documents
concerning cleanup activities affidavits taken from individuals involved in the disposal activities
and miscellaneous correspondence related to the criminal investigation and cleanup activities
The HRS package includes the EPAs Preliminary Assessment for Gallups Quarry which was
completed by NUS in July 1986 During the Preliminary Assessment NUS sampled two of the
existing monitoring wells (SW17D and SW18) and three surface watersediment locations The
surface and groundwater samples were screened in-house for benzene TCE toluene PCE
chlorobenzene ethyl benzene and xylenes None of these compounds were detected in MW18 or
the surface water samples All of the compounds (except chlorobenzene) were detected in
MW17S with toluene and xylenes measured at the highest concentrations With the exception of
pH temperature and conductivity no data were available regarding the sediment samples
Based on a file review and limited sampling the Preliminary Assessment concluded as in
previous studies that VOC contamination existed at the Site and that contaminated groundwater
was migrating in a west to northwest direction from the Site NUS recommended that a Site
Investigation be conducted to further evaluate the on-site conditions and potential off-site impacts
1335 Residential Well Sampling 1989
In 1989 Roy F Weston Inc under contract to EPA collected samples from 10 private wells in
the vicinity of the Site The samples were analyzed for VOC semi-volatile compounds (SVOC)
and metals Very low levels of some VOC (chloromethane TCA and carbon tetrachloride)
SVOC (phthalates) and metals (barium and copper) were detected in several wells but at
concentrations well below their respective EPA MCL In a memo dated May 25 1989 (included
as Appendix G of the START Report) EPA concluded that the levels detected in this investigation
did not represent a public health threat
5797wpdocsgalluprifinaltextmraquosterrifhl061297 1-11 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
1336 Site Analysis - Bionetics Corporation 1990
In November 1990 the Bionetics Corporation under contract to EPA completed an analysis of
historical aerial photographs taken of the Site in 1951 1970 1974 1975 1981 and 1988
Based on analyses of these aerial photographs the report suggested that disposal-related activities may have started at the quarry as early as 1970 However this conclusion was based on the
presence of features such as excavated areas mounded materials possible containers and the presence of access roads all of which are also indicative of typical quarrying operations
1337 Health Assessment - US Department of Health and Human Services (DHHS) 1991
The US Department of Health and Human Services completed a Health Assessment for Gallups Quarry on January 30 1991 to assess potential human health effects from exposure to
contamination at the Site The assessment was based on previous chemical testing data available
for the Site (ie data collected by Fuss amp ONeill Inc in 1978 and by CTDEP in 1979 through
1983)
The report concluded that if present at high enough concentrations VOC and heavy metals
detected at the Site could have potential public health implications The report recommended that
a program of groundwater monitoring be instituted along with on-site soil and surface water sampling and that additional health data for the area be evaluated as it becomes available
1338 Residential Well and Surficial Soil Sampling - Roy F Weston 1993
In 1993 Roy F Weston Inc under contract to EPA sampled 8 residential supply wells in the
vicinity of the Site The samples were analyzed for VOC SVOC and metals In addition
Weston collected seven surficial soil samples (within 3 inches of the ground surface) from areas
of apparent staining in the vicinity of the Former Primary and Secondary Disposal Areas Two
samples were collected in January 1993 and the other five were collected in February 1993 The
soil samples collected in January were submitted to the laboratory for analysis for pH and
cyanide and for metals screening using X-ray fluorescence techniques (XRF) The five samples
collected in February were analyzed for cyanide
The results of the XRF screening analyses indicated that the two samples collected in January
contained levels of copper ranging from 160 to 400 ppm No other metals were detected above
normal background levels Cyanide levels for all seven soil samples were reported in the range
of 87 to 345 ppm
5797wpdocsgalluprifinaltextmasterrifiil061297 1-12 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
The well water analytical results indicated that 111-TCA was detected in three of the residential
wells at levels of 05 to 12 ppb well below EPA MCL for 111-TCA of 200 ppb Copper and
iron were detected at levels below the EPA MCL in several of the samples analyzed SVOC were
not detected
1339 Groundwater Monitoring and Well Survey Metcalf amp Eddy 1993
In November 1992 Metcalf amp Eddy performed a well condition survey of the remaining existing
monitoring wells at the Site as part of a groundwater monitoring well investigation conducted for
the EPA Thirteen of the original twenty-two monitoring wells installed by Fuss amp ONeill Inc
were located fewer than half of which were determined to be in a condition capable of producing
viable samples In February 1993 Metcalf amp Eddy collected samples from ten of the wells
installed by Fuss amp ONeill Inc and from a USGS well installed in 1992 The samples were
analyzed for VOC SVOC metals and cyanide
Groundwater analytical results were consistent with earlier studies but confirmed that VOC levels
were significantly decreasing with time Low levels of VOC were detected at monitoring wells
SW3S and SW3D located downgradient of the Former Primary Disposal Area and at SW13
located downgradient of the Former Secondary Disposal Area The highest levels of VOC were
detected in wells SW17S (15000 ppb of xylene 1700 ppb of toluene 460 ppb of TCA 34 ppb
of TCE 22 ppb of PCE) and SW17D (1500 ppb of 12-DCE 720 ppb of TCA 16 ppb of TCE
and 27 ppb of PCE) A summary of the results of the 1993 Metcalf amp Eddy monitoring are
presented in Table 1-2 In general the concentrations detected in these wells for this sampling
event were substantially lower than concentrations recorded during the previous groundwater
sampling in 1982
13310 Geohydrology of the Gallups Quarry Area Plainfield Connecticut USGS 1993
In 1993 the United States Geological Survey (USGS) issued a draft report on Geohydrology of
the Gallups Quarry Area Plainfield Connecticut (finalized in 1995) The work was performed as
part of the EPAs START program and was designed to assist in the RIFS scoping process
The USGS study interpreted the subsurface geologic conditions at the Site to provide guidance for
subsequent investigations Field investigations for the study included ground penetrating radar
(GPR) and electromagnetic (EM-34) geophysical surveys the drilling of three test borings the
installation of a monitoring well in one of the borings (shown on Figure 1-4) and the
measurement of flow rate and specific conductance in Mill Brook
5797wpdocraquosalluprifiiultextmasterrifiil061297 1-13 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The USGS investigation provided data on overburden soil units the depth to bedrock and
bedrock structure Existing subsurface information derived from previous test boring logs and the
data collected from the three test borings drilled by the USGS were used in conjunction with GPR
data and the results of the EM-34 terrain conductivity survey to develop geological cross-sections
across the Site In addition the GPR survey indicated the possible presence of a west-northwest
trending fault zone beneath the property located south of the Former Seepage Bed The location
of this suspected fault zone as estimated by the USGS is consistent with the approximate location
inferred by previous regional geological studies (Dixon 1965 and Boynton and Smith 1965)
An electromagnetic survey performed downgradient (northwest) of the Former Secondary and
Primary Disposal Areas indicated a northwesterly-trending pattern of increased terrain
conductivity levels as compared with levels at other areas of the Site The USGS interpreted the
increased levels as possibly indicative of either the presence of a groundwater plume containing
residual metal contamination or a natural change in subsurface strata Surface water
measurements collected in Mill Brook indicated that specific conductance increased slightly
downstream of the railroad bridge however the observed differences were so small that the
USGS did not consider them to be indicative of changes in water quality caused by the presence
of dissolved contaminants
13311 Habitat Characterization for Gallups Quarry Superfund Site US Fish and Wildlife Service March 1995
In June of 1993 the US Fish and Wildlife Service conducted a field survey for the purposes of
characterizing the habitat of the Site and surrounding wetland and stream ecosystems The study
was qualitative in nature conducted on foot by trained biologists with the objective of correlating
observations on habitat (primarily vegetation) with known reference material such as topography
maps and aerial photographs The study also included direct and indirect (eg animal tracks)
observations to assess the presence (or absence) of wildlife
The report provides a description of methods and general Site characteristics as well as a more
detailed discussion of wildlife habitat for both the Site and the Mill Brook wetland ecosystem
The study is partial in that it accents what types of animals would be anticipated to be present for
each habitat type even though most of these animals were not directly observed
The report concludes with a description of 29 different types of cover that can be cross-
referenced to areas delineated on a Site map (not to scale) Several Tables are also presented
which inventory birds mammals reptiles amphibians trees shrubs and herbaceous vegetation
that were either observed or would be expected to inhabit the Site
5797wpdocsgalluprifinaItextmasterriftil061297 1-14 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
13312 Adjacent Properties Incident Reports and File Review 1995
To supplement data obtained during the Phase 1A field program a CTDEP file search was
performed to obtain information pertinent to groundwater contamination for industrial properties
neighboring the Site The preliminary findings of this review were submitted in a letter from
ESE to EPA on March 28 1995
A number of incident reports were on file regarding two nearby companies Pervel Industries
Inc and InterRoyal Corporation which have the potential to impact conditions within the Study
Area Figure 1-5 shows the locations of these facilities relative to the Site The significant
findings of the file searches are presented below
Pervel Industries
Pervel Industries Inc manufactured plastic film and laminated textile products (eg flocked
velvet) Pervel reportedly occupied two separate facilities north of the Site The main facility
located approximately 2500 feet north of the Site is believed to have been occupied by Pervel
from the 1940s or 1950s to at least the late 1980s This facility abutted the southern side of the
InterRoyal facility described below A second Pervel facility known as the flock plant (presently
operated by Intermark Fabric Corporation) was located approximately 1000 feet north of the
Site just north of Mill Brook The dates of Pervels occupation at the flock plant cannot be
clearly ascertained from the information available in the files however the review of historic
aerial photographs indicate that the facility has existed since the early 1970s
In 1988 at the request of EPA and CTDEP the NUS Corporation performed a Preliminary
Assessment (PA) at the main facility In an effort to determine eligibility for the National
Priorities List (NPL) NUS reviewed the activities associated with the 1984 closure of a sludge
and waste water lagoon located at the facility Based on their review of the available data NUS
recommended that a Screening Site Inspection (SSI) be performed
The NUS PA report also described a 1985 spill of 600 gallons of 111-TCA and a 1987 spill of
300 gallons of toluene at the northernmost facility According to the PA report contaminated soil
and sediment associated with the 1985 spill was excavated and stored in an impoundment at the
flock plant located just north of the Gallups Site The report indicates the presence of
contaminants in the area where the contaminated soil and sediment were stored suggesting that
the impoundment leaked andor there are other (undocumented) environmental concerns at the
flock plant
5797wpdocraquogalluprifinaltextmlaquosterrifhl061297 1-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The results of recent (late 1980s through the early 1990s) quarterly groundwater monitoring
efforts conducted at the former Pervel flock plant (HRP 1993) indicate the presence of a number
of VOC including 111-TCA TCE PCE and 12-DCE well above their respective MCL The
results of these sampling events as summarized in Table 1-3 (from HRP 1993) indicate that
there has been a general decrease in the concentrations of contaminants seen in these wells over
time The highest recorded concentrations for these constituents are as follows 111-TCA (518
ppb) PCE (466 ppb) TCE (63 ppb) and 12-DCE (906 ppb) According to the HRP report
groundwater flow in the vicinity of the former Pervel flock plant is generally from east to west
(towards the northern portion of the Study Area) However these interpretations were based on a
limited number of data points confined to the Pervel flock plant property
InterRoyal Corporation
The InterRoyal Corporation is located adjacent to and just north of the main Pervel facility
described above The CTDEP files include a memorandum from the NUS Corporation to EPA
dated August 18 1989 which references a 1984 Preliminary Assessment performed by CTDEP
which recommended that a low priority Site Inspection be performed The NUS memo presents a
chronology of Site activities up to 1989 which includes CTDEPs 1987 finding that the company
was in violation of several State Hazardous Waste Management regulations and CTDEPs
subsequent revocation of InterRoyals NPDES permit Based on a CTDEP 1988 Site inspection
NUS recommended to EPA that a high priority Screening Site Inspection be conducted
In 1988 InterRoyal contracted an environmental consultant to prepare an environmental
assessment (EA) for the proposed sale of the property The EA report (ERT 1988) concluded
that substantive on-site contamination of groundwater surface water and soils existed The
principal contaminants were identified as VOC (including TCE trans-l2-DCE PCE vinyl
chloride toluene and xylenes) and priority pollutant metals Groundwater flow direction was
described in the EA report as principally towards the south and southwest
5797wpdoc8galluprifinaltextmasterrifhl061297 1-16 QZT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
20 Field Investigations
This Section describes the field methods and procedures used to accomplish the various field
investigation tasks performed during Phase 1A and Phase IB Also included are descriptions of
any deviations from the approved Work Plan As noted in the appropriate subsections any
deviations from the Work Plan were approved by EPA (or EPAs oversight contractor) prior to
implementation Discussions of the findings results and significance of these investigations are
presented in Sections 3 and 4 of this Report
21 Site Survey 211 Initial Site Survey At the start of the Phase 1A field investigation an initial Site survey was performed to confirm
and update the location and elevation of features included in the base map provided by EPA (EPA
drawing number 707600 dated October 14 1993) The initial Site survey also served as Site
control by establishing a 250-foot grid across the entire Site which was identified by the
installation of labelled stakes at the intersection of each 250-foot grid line Horizontal control for
the 250-foot grid (and all subsequently surveyed features) coincides with the Connecticut State
Plane Coordinate System North American Datum of 1927 Vertical control coincides with the
National Geodetic Vertical Datum (NGVD) of 1929 and was established using nearby USGS benchmarks The 250-foot grid (shown on Plate 2-1) provided known reference locations from
which field personnel could measure the locations of Site features
In addition to the 250-foot control grid the initial survey also established a series of parallel lines
(trend lines) across the Site for use during subsequent visual reconnaissance and geophysical
surveys The trend lines (also shown on Plate 2-1) are roughly parallel to the Providence amp Worcester railroad which abuts the western edge of the property The first trend line (Line A)
was located approximately 50 feet east of the railroad right-of-way with subsequent lines (Line
B through Line HH) spaced at 25-foot intervals Each of the trend lines were staked at 250shy
foot intervals using labelled stakes
212 As-Installed Survey
Following the initial Site survey additional surveying events were performed as needed
throughout the duration of the Phase 1A and Phase IB field investigation programs to locate
various sampling locations and other pertinent investigation features These subsequent surveys
were initiated shortly after the completion of each investigation task Besides the various
surveyors control features such as temporary benchmarks and turning points the features
surveyed included wetland delineation flags surface watersediment and wetland soil sampling
5797wpdocsglaquolluprifinlaquoltextrnasterrifhl061297 2-1 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
locations microwells soil vapor points soil borings monitoring wells (existing and newly
installed) stream gauges piezometers and seismic survey lines
All pertinent investigation-related features within approximately 1500 feet of the Site were
included in the survey Several surface watersediment sampling locations beyond 1500 feet from
the Site were not surveyed and their locations are estimated based on their proximity to mapped
physical features such as bridges or roads
The surveying services for this investigation were performed by KWP Associates Inc of Pomfret
Center Connecticut a licensed and registered surveyor in the State of Connecticut The survey
was completed as a third-order plane survey as defined by the standards and specifications in
Exhibit 14-1 of the Compendium of Superfund Field Operations Methods December 1987
(USEPA 1987)
22 Site Reconnaissance 221 Visual Observations of the Ground Surface
A visual reconnaissance of the Site was conducted during an approximate three week period
beginning on August 23 1994 and ending on September 13 1994 During the visual Site
reconnaissance the entire length of each trending line (shown on Plate 2-1) was walked to
identify and map any features which may have been indicative of unknown disposal areas Any
features such as areas of stained soil partially buried man-made objects remnants of buildings
abandoned equipment containers (eg drums tanks) pits depressions mounds and any other
apparent unnatural materials were photographed and noted on field maps and in a field notebook
Also potential disposal features identified during review of historic aerial photographs (Bionetics
Corporation 1990) were located and investigated The locations of features were flagged and
approximated using the survey stakes installed during the initial Site survey The results of the
field reconnaissance were also used to determine additional soil gas sampling locations (described
in Section 25) during subsequent Phase 1A investigations
222 Air Quality Survey
A baseline air quality survey was conducted prior to the start of Phase 1A intrusive field
investigations The survey was performed using a photoionization detector (PID) equipped with
an 117eV lamp to measure total VOC vapors and a direct reading aerosol monitor (RAM-1) to
measure respirable particulates Baseline air quality readings were recorded at eight stations
(AM-1 through AM-8) located across the Site The monitoring stations included areas along the
Site perimeter as well as interior locations at the three known former disposal areas The
locations of the eight baseline air monitoring stations are shown on Plate 2-2
5797wpdocsgalluprifinaltextmlaquo8temfnl061297 2-2 QZT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
In addition to the baseline air quality survey air monitoring was performed on a weekly basis at the eight locations during the entire Phase 1A field investigation Wind direction wind speed
temperature and barometric pressure were also continuously monitored at an on-site
meteorological station
During the Phase IB investigation quantitive air monitoring was performed for site specific
compounds The Phase IB air sampling was performed in the vicinity of the Former Primary
Disposal Area on October 24 1995 This location was selected based on the findings of the
Phase 1A field program Four samples were collected along the perimeter of the Former Primary
Disposal Area at the northern southern eastern and western edges of the perimeter One
background sample was collected at a location approximately 300 feet south of and upwind from the Former Primary Disposal Area The sample locations are shown in Plate 2-2 The samples
were analyzed for the following volatile organic compounds (VOC) toluene ethyl benzene xylenes (total) and tetrachloroethane (PCE) and polychlorinated biphenyls (PCBs)
VOC samples were collected on stainless steel Tenax tubes which were connected to Dupont
Alpha 1 sampling pumps Samples for PCBs were collected on 037z glass fiber filters using
Dupont Alpha 1 and BIOS AirPro 6000D sampling pumps The sampling media was attached to
the sampling pumps using silicone tubing The pumps were secured to wood stakes and
positioned approximately 5 feet above the ground surface
The pumps used to collect the VOC samples were set to pump at a flow rate of between 0014 to
0016 liters per minute and allowed to pump approximately eight hours The pumps used to collect the PCB samples were set to pump at a flow rate of between 27 and 33 liters per minute
and were allowed to pump approximately eight hours All of the sampling pumps were calibrated prior to and after the sampling event using a primary gas flow mini-Buck Model M-5 Calibrator
Ambient meteorological conditions including temperature relative humidity barometric pressure
and wind speed and direction were monitored during the sampling event using ESEs on-site Qualimetrics meteorological monitoring instrument
A VOC and a PCB field blank were collected at background location AS 105 The VOC Tenax
tube and the PCB glass fiber filter were appropriately labeled opened and then immediately
resealed The field blanks were stored and shipped with the samples
At the completion of the sampling event the VOC Tenax sample tubes (including the field blank)
were sealed placed in clean plastic bags and refrigerated at 4degC until they were shipped The
samples were then shipped to the laboratory in coolers The PCB sample filters were sealed
5797wpdocsgalluprifinaltextmasterrifhl061297 2-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
wrapped in bubbie wrap and packed along with the PCB field blank in a cardboard box for
shipment to the laboratory An unopened VOC Tenax tube and PCB glass fiber filter were
submitted with tae samples as a trip blank The VOC Tenax sample field blank and trip blank
tubes were packed in a cooler with ice and sent to ESEs Denver Colorado Laboratory where
they were analyzed by EPA Method TO1 The PCB glass fiber sample field blank and trip
blank filters were sent to ESEs Denver Colorado Laboratory where they were analyzed by
SW846 EPA Method 8080 The results of the air quality survey are discussed in Section 44
223 Exclusion Zone Identification
Prior to the start of Phase 1A field activities preliminary exclusion zones were identified to limit
the risk of workers exposure to potentially hazardous conditions Based on existing data and
observations made during the Site visual reconnaissance the three known former disposal areas
and the area immediately surrounding a former CTDOT asphalt plant structure were staked and
flagged with caution tape A contaminant reduction zone (CRZ) was established adjacent to the
exclusion zone in the prevailing upwind direction during investigations at each location The
CRZ was established for decontamination operations of Site personnel and equipment
224 Project Support Measures
All field investigations were managed from a field office located within an approximate 10000
square foot support center which was situated at the southern end of the Site along Tarbox Road
The support center consisted of an approximate 100 foot by 100 foot area surrounded by a 6 foot-
high chain link fence The support center housed an office trailer an impermeable bermed
decontamination pad lined with 60 mil thick textured HDPE potable water storage tanks storage
units (drums dumpsters and tanks) for investigation derived wastes the weather station and
portable sanitary facilities The office trailer was connected to electric utilities and telephone
service to facilitate normal business and emergency operations A storage trailer for supplies and
equipment was located adjacent to the support center
The field office was used to support field activities by providing the following services
bull personnel sign-in and sign-out sheets
bull daily field activity log book
bull Health amp Safety log book
bull storage of Personal Protective Equipment (PPE)
bull communications center
bull posting of project plans
bull management of project field files
bull briefingmeeting room to coordinate field activities
5797wpdocsgalluprifinaltextmasterrifW061297 2-4 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull meeting place for emergency evacuations and
bull lunch area
The support center also provided an access control point for the Site as it is the only practical
location where four wheeled vehicles could enter or exit the Site Other non-vehicular access
points were blocked with boulders or mounded soils Other access to the Site is limited due to
the presence of heavy vegetation steep slopes and wetlands In addition warning signs
prohibiting trespassing were posted every 100 feet along the Site perimeter prior to the start of
Phase 1A field activities
225 Identification of Sensitive Human Receptors
A survey to identify potential human receptors in the vicinity of the Site was performed This
survey was used to identify any private water supply wells schools nursing homes and day care
facilities located within a one mile radius of the Site The survey was performed by reviewing
available records and documents from the following sources
bull Town of Plainfield Municipal Offices
bull Northeast District Health Department
bull Connecticut Department of Environmental Protection
bull Connecticut Natural Resource Center and
bull Connecticut Department of Health and Addiction Services
In addition to the file reviews interviews were conducted with neighbors and knowledgeable local
people Finally a windshield survey was conducted for the area located within a one mile radius
of the Site
23 Geophysical Surveys During the Phase 1A investigation comprehensive geophysical surveys of the Site were conducted
by Weston Geophysical Corporation of Northborough Massachusetts using electromagnetic
terrain conductivity (EM) magnetometer (MAG) and seismic refraction survey techniques The
purpose of the EM and MAG surveys was to obtain Site-wide screening data to identify the
locations if any of potential subsurface disposal features or objects such as pits trenches drums
or tanks The initial EM and MAG surveys were conducted along each of the trend lines
established during the initial Site survey as shown on Plate 2-1
The purpose of the seismic refraction survey was to determine the location and orientation of the
inferred bedrock fault (if present) in the central portion of the Site Although bedrock
characterization was not one of the intended purposes of the MAG survey subsequent review of
5797wpdocsgalluprifinaltextmasterriftil061297 2-5 QSTT Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
the acquired MAG data provided some information regarding the nature of the shallow bedrock
surface in the central portion of the Site
The presence of heavy vegetation over much of the intended survey area required approximately
two weeks of brush cutting and clearing in order to gain access to the trending lines and to ensure
complete coverage of the Site Once the proposed survey lines were accessible the initial MAG
and EM surveys were conducted along each trending line with data collected at five-foot intervals
The Work Plan stated that the five-foot intervals would be determined by laying a fiberglass
measuring tape along each trend line between survey stakes However the presence of heavy
vegetation prohibited the efficient use of this technique Since the exact locations of any
unexplained anomalies would be later determined during subsequent EM and MAG surveys (and
confirmed during test pit explorations) it was determined that the five-foot intervals could be
efficiently and accurately estimated by an experienced equipment operator by counting paces
between intervals and making adjustments as necessary at each survey stake (which were located
every 250 feet along each line)
As stated in the Work Plan ground penetrating radar (GPR) was to be used if necessary to
further characterize any unexplained anomalies identified during the initial EM and MAG surveys
The presence of abundant vegetation and rough ground surface conditions in the areas of interest
precluded the reasonable use of GPR As approved by EPA the precise locations of unexplained
anomalies identified during the initial EM and MAG surveys were determined during additional
EM and MAG surveys using a finer (5 foot by 5 foot) survey grid superimposed over the general
vicinity of each anomaly
The seismic refraction survey was conducted along six roughly parallel lines which were placed
normal to the anticipated strike of the inferred bedrock fault The locations of the six seismic
lines are shown in Plate 2-3 Each seismic line (Line 1 through 6) is comprised of two 250-foot
long lines which overlap by 125 feet This resulted in a total of 375 feet of continuous coverage
along each line
A complete report provided by Weston Geophysical Corporation describing the theoretical basis
for these surveys is presented as Appendix A Generalized discussions describing the field
methods and equipment used during each geophysical survey are presented below
5797wpdoclaquogalluprifinaltextmastemfnl061297 2-6 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
231 Electromagnetic Terrain Conductivity (EM) Survey
The initial EM survey was performed by Weston Geophysical Corporation over a three day
period (September 14-16 1994) using a Geonics EM-31 electromagnetic terrain conductivity
logger and a Model 720 Polycorder Background terrain conductivity readings were collected at
the beginning and end of each day from an area determined to be relatively free of electrical
interference The background station was located at the extreme southeastern corner of the Site
well away from the overhead electrical lines located along Tarbox Road and Route 12 (Norwich
Road) The EM-31 was calibrated daily by the operator and data was downloaded in the field to
a computer as needed typically twice a day
Following daily calibration the EM survey was performed by the instrument operator who paced
the entire length of each trend line with the EM meter and data logger Terrain conductivity
measurements were made and digitally recorded at five-foot intervals along each line The
presence of surficial objects and other features (eg steel fencing) that would cause interference
or produce anomalies were noted in the field notebook and accounted for during the data
evaluation Terrain conductivity data were subsequently plotted on a base map of the Site and
contoured to produce the terrain conductivity contour map included in the Weston Report in
Appendix A The results of the EM survey are discussed in Section 413
232 Magnetometer (MAG) Survey
The initial MAG survey was conducted by Weston Geophysical Corporation over a period of 7
days (September 7-14 1994) using two GEM-VI and one EGampG Model 856 magnetometers The
two GEM units were used for data acquisition while the EGampG unit was used as a base station to
monitor diurnal changes in the earths magnetic field The base station was established at the
southeastern corner of the Site where there was no interference from metallic objects or overhead powerlines and where no significant magnetic field gradients were observed
The MAG survey was performed by walking each trending line wiih one of the data acquisition
magnetometers (GEM-VI) and recording the magnetic field at every five-foot interval determined
by pacing The MAG data were eventually corrected for diurnal background fluctuations in the
earths magnetic field as determined at the base station and plotted on a base map to produce the
magnetic contour map which is included in the Weston Report in Appendix A The results of the
magnetometer survey are discussed in Section 413
5797wpdocsglaquolluprifinaltextmlaquo8terriftJ061297 2-7 QST Environmental
Gallups Quarry SuperUna1 Project - Remedial Investigation
233 Additional EM and MAG Surveys
In lieu of GPP surveys additional EM and MAG surveys were performed to determine the
precise location of any terrain conductivity or magnetic anomalies which could not be explained
by the presence of surficial metallic debris The additional surveys were performed over a 5-foot
by 5-foot grid in the vicinity of each unexplainable anomaly
A total of four unexplainable anomalies within three separate areas were eventually investigated
with additional EM and MAG surveys Once the locations of the anomalies were accurately
located each anomaly was further assessed by excavating test pits to identify the source of the
anomaly The test pit operations are discussed in Section 214 and the findings of the test pit
excavations are discussed in Section 4133
234 Seismic Refraction Survey
A seismic refraction survey was conducted along six 375-foot lines located within the suspected
fault zone An ABEM Terraloc 24-channel digital recording seismograph system was utilized for data collection The 375-foot spread lengths consisted of two overlapping 250-foot long lines
with geophones spaced in ten-foot intervals The endpoints of each seismic line were staked in
the field to facilitate the subsequent location survey
In accordance with the Work Plan shot points were located at each end point midpoint and
quarter point in addition to an offset from each end point The Work Plan had stated that
seismic energy would be produced by either an elastic wave generator or weight drop However
due to access constraints at the Site EPA approved the use of an alternate energy source For
these surveys seismic energy was generated using 8 gauge seismic shotgun shells discharged
approximately 2 to 3 feet below ground surface
The energy created by the shell blast travels through the ground and refracts along interfaces
between materials of different propagation velocity and density characteristics Interpretation of
these data on a time vs distance plot is conducted for the seismic wave arrival times at each
geophone The propagation velocities can be categorized into various geologic materials such as
overburden saturated overburden bedrock formations and weathered or fractured formations A
comprehensive discussion of the theoretical basis and operation of this technique is presented in
the Weston Geophysical report provided as Appendix A The results of the seismic refraction
survey are discussed in Section 32
5797wpdoc8gaIIuprifinaltextmasterrifnl061297 2-8 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
24 Groundwater Sampling Using Temporary Well Points Between August 29 and October 7 1994 a total of 60 small-diameter temporary well points
(microwells) were installed at predetermined locations using direct push techniques for the
purpose of collecting groundwater samples for both on-site and off-site chemical analysis At 10
of these locations equipment refusal occurred prior to encountering groundwater thus reducing
the total number of sampled locations to 50 The results of the chemical analyses were used to
determine the nature and extent (both horizontal and vertical) of groundwater contamination (VOC
and metals) within the Study Area Data obtained during this survey were ultimately used to determine the optimum location for subsequently-installed permanent groundwater monitoring
wells The surveyed locations of the temporary well points (TW101-TW160) including the 10 unsampled locations are shown on Plate 2-4 A summary of the locations and depth intervals for
each microwell is presented in Table 2-1
A total of 126 samples were analyzed on-site for selected VOC using a portable gas chromatograph (GC) A total of 121 samples (not including duplicates and field blanks) were
submitted for off-site laboratory analysis for cyanide and metals Also 12 samples (not including
field blanks and trip blanks) were submitted for off-site laboratory analysis for VOC to confirm
the on-site GC analytical data
The microwells were comprised of a 082 inch diameter (062 inch inside diameter) steel riser
pipe of varying lengths equipped with a hardened steel tip and a 5 foot long slotted section at the
leading end The 5 foot long slotted section (or screen) consisted of a four longitudinal rows of 2
inch long by 0015 inch wide slots Each microwell was advanced into the subsurface using
either an electrically or hydraulically powered vibratory impact hammer which was mounted on a
telescoping mast The mast drive-hammer and all other ancillary equipment were mounted on an all-terrain vehicle for maximum mobility
Individual sections of riser pipe (which varied in length up to a maximum of 21 feet) were
connected using a slip coupling over the butted ends of adjacent sections The slip coupling is
either electrically welded or crimped (using a hydraulic crimping tool) over the connection to
form a water tight joint
All materials were steam cleaned prior to use and only used at one location to avoid cross
contamination between sampling locations
The objective at each location was to drive the microwell into the saturated overburden and collect
a groundwater sample from three successively deeper intervals The desired sampling intervals
were as follows five feet below the top of the water table midway between the top and bottom of
5797wpdocsgalluprifinaltextmlaquoraquotemfhl061297 2-9 QST Environmental
Gallups Quarry SuperUna1 Project - Remedial Investigation
the aquifer and at the bottom of the aquifer (ie the refusal depth) A middle andor deep sample
was not collected if refusal was encountered without significant advancement of the well point
between sample depths (minimum of 10 feet) The midpoint sampling depth was estimated based
on the refusal depths encountered at nearby microwells
Once the microwell was driven to the desired depth purging and sampling was accomplished
using a manually operated inertial pump comprised of an adequate length of dedicated 38 inch
(inside diameter) polyethylene tubing equipped with a bottom check valve In operation the
inertial pump is lowered into the screen section of the microwell and repeatedly raised and
lowered (manually) a distance of approximately one foot This reciprocating action causes water
to rise within the tube until it is ultimately discharged at the ground surface into either a bucket or
sample container Between one and three riser volumes were purged from each microwell prior
to sample collection except for the first sample (5 feet below the top of the water table) which was
collected without purging All purge water was containerized and eventually transported off-site
for treatment and disposal
Once a groundwater sample was acquired it was labelled packed in a cooler and transported to
the on-site laboratory Each sample was analyzed on-site using a portable gas chromatograph
for the following eight VOC
bull l2-dichloroethene(DCE)
bull 111 -trichloroethane (111 TCA)
bull trichloroethene (TCE)
bull benzene
bull toluene
bull acetone
bull methyl ethyl ketone (MEK)
bull methyl iso-butyl ketone (MIBK)
Groundwater samples from each location were also collected filtered through a 045 micron
filter preserved with nitric acid and submitted to an off-site laboratory for analysis for the
following metals
bull aluminum
bull arsenic
bull cadmium
bull chromium
bull copper
5797wpdoc8galluprifinaltextmasterrifhl061297 2-10 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
bull iron
bull lead
bull manganese
bull nickel
bull zinc
Unfiltered samples were also collected preserved with sodium hydroxide (NaOH) and submitted
for analysis for cyanide In addition duplicates of 12 of the VOC samples analyzed in the field
were submitted for laboratory analysis for VOC for confirmation purposes Samples for off-site
VOC analyses were preserved in the field by addition of hydrochloric acid (HC1) to obtain a pH
less than 2
Samples for on-site VOC analyses were collected into 40 ml glass vials equipped with a teflonshy
lined silicon septum Each vial was filled capped labelled and refrigerated until it was
analyzed Samples were typically analyzed within several hours of collection Prior to analysis
the sample was removed from the refrigerator and 10 ml of water was withdrawn and discarded
The withdrawal of 10 ml of water created a headspace within each vial into which any VOC
present in the liquid would partition To complete the VOC partitioning process the vial was
then placed into a constant temperature (90 degC) water bath for a minimum of 15 minutes Just
prior to analysis a 250 micro-liter air sample was withdrawn from the headspace within the vial
by inserting the needle of the syringe through the teflon-lined septum and injected into the
portable gas chromatograph for analysis
A Photovac 10S50 portable gas chromatograph equipped with a CPCIL 5 encapsulated column
was used for on-site analysis The Photovac 10S50 gas chromatograph (GC) was filled every
morning with zero grade air and allowed to warm-up for 30 minutes prior to daily operation in
accordance with SOP 4001 and manufacturers instructions
The GC detector flow oven temperature and gain setting (sensitivity setting) were checked and
verified every morning and throughout the day Field GC standards were prepared daily by
diluting commercially available certified pure liquid chemical standards with deionized water
Three separate standards a low-concentration level a mid-concentration level and a high-
concentration level standard containing the eight select VOC were prepared in order to obtain a
three-point calibration curve Glass gas-tight syringes were used for preparation of standards and
sample injection AH syringes were decontaminated using methanol deionized water and
compressed gaseous nitrogen
5797wpdocsgalluprifinaltextmlaquo8terrifhl061297 2-11 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The GC operating condition was checked in the morning and during the day using machine
blanks syringa blanks and standards All three standards were run with a syringe blank directly
before and after each injection after every ten samples and at least once in the morning and once
in the afternoon each day In accordance with the QAQC program and SOP 4009 a duplicate
groundwater sample was collected in the field in a separate 40 ml glass vial immediately
following the collection of the original sample The second vial was used for duplicate analyses
after every ten samples
In the event that a sample analysis showed a contaminant chromatographic peak with an area
greater than the high-concentration standard or the range of the GC operating parameters (off-
scale) a smaller aliquot (l10th the original sample injection volume) was taken from the second
vial and injected into the GC All pertinent information concerning the smaller aliquot was
recorded on the GC strip chart and in the field log book
The GC strip chart was labeled with the sample identification number or corresponding
identification information (eg sample ID syringe blank etc) All pertinent information (eg
sample ID) was recorded in a field log book
In accordance with the QAQC program all samples were kept at 4degC prior to analysis and were
analyzed within 48 hours of their collection time
A total of 23 microwells (TW101-TW123) were installed by Pine and Swallow Associates Inc of
Groton Massachusetts Due to limited ability to access certain locations with the available
equipment the remaining 37 microwells were installed by a second subcontractor MyKroWaters
Inc of Concord Massachusetts Installation logs are presented in Appendix B The results of
the microwell survey are discussed in Section 421 The microwell installations were later
abandoned by filling them with cement grout and cutting the risers off below the ground surface
25 Soil Gas Survey In an effort to identify the location of any previously unknown potential disposal areas a Site-
wide soil gas survey was conducted From September 26 1994 through October 12 1994 a
total of 106 soil gas sampling probes were installed across the Site Soil gas samples were
analyzed on-site using a portable gas chromatograph
A 100-foot sampling grid was used to systematically cover the Site however actual locations
were dependent on accessibility and the ability to advance the soil gas probes to the desired depth
beneath the ground surface Besides the sampling at the intersection of grid lines six additional
locations were investigated due to the presence of empty drums found at the ground surface
5797wpdoC8galluprifinaltextmastemfnl061297 2-12 QST Environmental
Gallups Quarry Superfiind Project - Remedial Investigation
during the Site reconnaissance or anomalies detected during the EM and MAG surveys The
extreme northeastern corner and eastern side of the Site were not included in the soil gas survey
since they are either wetlands or heavily wooded Also an approximate 15000 square foot area
just north of the Former Seepage Bed was not tested due to the presence of a large pile of
boulders The surveyed locations of each soil gas sampling point (SV101-SV206) are shown in
Plate 2-5 The locations of SV111 SV201 and SV141 are approximate based on field
measurements from surveyed locations
Each soil gas sampling probe consisted of a four inch long hardened steel combination drive
point and screen which was connected to an adequate length of 316 inch diameter polyethylene
tubing The pointscreen and tubing assembly were inserted inside a hollow steel shaft which was
then driven into the ground with an electrically powered vibratory hammer
An abundance of gravel cobbles and boulders in the central portion of the Site prohibited the
advancement of several probes to the minimum depth specified in the Work Plan (25 feet) After
discussions with EPAs oversight contractor regarding the surface conditions in this area it was
agreed that at the rocky locations the probe would be driven as far as possible (typically 15-2
feet) and a two-foot by two-foot sheet of polyethylene sheeting would be placed on the ground
surface surrounding the probe and weighted with native topsoil The purpose of the plastic sheet
was to minimize atmospheric influence during the sampling procedure
Once the point was driven to the sampling depth the hollow steel shaft was extracted leaving the
expendable pointscreen and tubing in place The small annular space surrounding the sampling
tube was tightly packed with native soil to ensure that gas samples were representative of soil
pore space and not atmospheric conditions Once the probe was in place any excess plastic
tubing was trimmed leaving approximately 15 feet of tubing above the ground surface Each
tube was clamped and sealed until it was eventually sampled typically within a few days of
installation
To collect a soil gas sample one end of a 280 ml glass sample chamber (equipped with teflon
stopcocks and a sampling septum) was connected to the tubing using a short length of silicon
tubing A battery-operated vacuum pump was then attached to the other end of the chamber and
used to draw a soil gas sample from the tubing Once a sample was acquired the stopcocks were
closed and the pump shut off The sample chamber was then transported to the on-site laboratory
for analysis
Just prior to analysis the needle of a gas tight syringe was inserted through the sampling septum of the glass chamber and an aliquot of the soil gas sample was removed The sample was then
5797wpdoclaquogalluprifinaltextma8terrifiU061297 2-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
injected into the gas chromatograph for analysis A Photovac 10S50 portable gas chromatograph
was used to analyze each sample for the following 8 VOC
bull l2-dichloroethene(DCE)
bull 111-trichloroethane (111 TCA)
bull trichloroethene (TCE)
bull benzene
bull toluene
bull acetone
bull methyl ethyl ketone (MEK)
bull methyl iso-butyl ketone (MIBK)
The Photovac 10S50 gas chromatograph (GC) was filled every morning with zero grade air and
allowed to warm-up for 30 minutes prior to daily operation in accordance with SOP 4001 and
manufacturers instructions
The GC detector flow oven temperature and gain setting (sensitivity setting) were checked and
verified every morning and throughout the day Field GC standards were prepared daily using
certified pure neat liquid standards from sealed vials Glass gas tight syringes were used for
preparation of standards and sample injection All syringes were decontaminated using methanol
deionized water and nitrogen
The GC operating condition was checked in the morning and during the day using machine
blanks syringe blanks and standards Standards were run with a syringe blank directly before
and after each injection every ten samples In accordance with the QAQC program a duplicate
soil gas sample was collected in the field in a separate glass sample chamber immediately
following the collection of the original sample After the original sample was injected into the
GC the duplicate sample from the separate glass sample chamber was injected into the GC The
data quality objective (DQO) for field analysis using the GC was maintained at or better than _+
30 relative percent difference In the event that a sample analysis showed a contaminant
chromatographic peak with an area greater than the range of the GC operating parameters (off-
scale) a smaller aliquot (I10th the original sample injection volume) was taken from the glass
sample chamber and injected into the GC AH pertinent information concerning the smaller
aliquot was recorded on the GC strip chart and in the field log book
5797wpdocsgalluprifinaltextma8teiTifiil061297 2-14 QST Environmental
Gattups Quarry Superfund Project - Remedial Investigation
The GC strip chart was labeled with the sample identification number or corresponding
identification (eg sample ID syringe blank etc) The analysis number and corresponding
identification information was also recorded in the soil gas survey field log book
All sampling equipment (exclusive of the dedicated expendable probes) was decontaminated between each sample by flushing with copious amounts of compressed nitrogen The results of the
soil gas survey are discussed in Section 41
26 Soil Borings at Disposal Areas A total of sixteen soil borings SB101 through SB116 were advanced at the three known former disposal areas Ten soil borings (SB 101 through SB110) were completed as part of the Phase 1A
investigation between October 4 and 13 1994 Six additional borings were advanced within the
Former Primary Disposal Area on November 2 1995 as part of the Phase IB investigation The
locations of the soil borings are shown on Plate 2-5 The objective of these borings was to obtain
soil samples to characterize subsurface lithology and determine the present level and distribution
of residual contaminants within each former disposal area The analyses performed on samples
collected during the Phase 1A investigation (ie SB101-SB110) included TCLTAL parameters
as well as pH (EPA Method 9045) total organic carbon (ASTM Method D 17565373) moisture
content and particle size distribution Samples collected during the Phase IB investigation
(SB111-SB116) were submitted for laboratory analyses for VOC and PCBPesticides The samples submitted for analysis and the depth intervals sampled are shown in Table 2-2 The
results of the soil boring program are discussed in Section 41 All soil boring logs are shown in
Appendix C
261 Piiase 1A Soil Borings Each boring completed as part of the Phase 1A investigation was advanced until equipment refusal was encountered using a truck mounted drill rig equipped with a 425 inch (inside diameter)
hollow stem augers The drilling operations were performed by Environmental Drilling Inc of
Sterling Massachusetts As shown in Plate 2-5 three of the borings were placed in the reported
location of the Former Seepage Bed (SB101-SB103) three were placed within the Former
Secondary Disposal Area (SB104-SB106) and four were placed within the Former Primary
Disposal Area (SB107-SB110) The Work Plan required that samples be collected and submitted
for laboratory analysis from each boring from specific depth intervals (0-1 foot 1 to 10 feet and
10 feet to the water table) and from each distinct hydrological unit encountered (eg coarse
stratified drift fine stratified drift and till) and from the capillary fringe at each disposal area
The number of samples actually submitted for analysis was dependent on the depth to water and
the number of hydrogeologic horizons encountered at each area In general samples submitted
579Twpdoc8galluprifinaltextmlaquo8terrifhl061297 2-15 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
for laboratory analysis were selected from within each depth range or horizon based on PID
readings andcr visual observations
Soil samples from the 0-1 foot interval were collected from the ground surface using a stainless
steel hand trowel All subsequent samples were collected using a standard 2-inch diameter split-
spoon sampling device in accordance with ASTM Method D-1586-84 Each sample was
screened in the field for total VOC using a PID equipped with an 117 eV lamp Each sample
was then visually classified and logged in a field notebook and on boring logs A portion of each
sample was placed into glass jars and sealed with aluminum foil and a screw cap for headspace
analysis The headspace sample was ultimately saved for archival purposes
All sampling equipment was decontaminated prior to use and between each sample using a
detergent wash and tap water rinse followed by methanol nitric acid and deionized water rinses
All drilling equipment was steam cleaned between boring locations All decontamination rinseates
were containerized and eventually transported off-site for treatment and disposal Likewise all
soil cuttings were containerized for eventual off-site disposal Upon completion each borehole
was filled to the ground surface with a bentonitecement grout mixture and marked with a labeled
stake so that its location could be surveyed
262 Phase IB Soil Borings
Data obtained during the Phase 1A investigation indicate the presence of residual soil
contamination in the vicinity of the Former Primary Disposal Area In order to more fully
characterize the extent of this residual contamination six additional soil borings were completed
along the perimeter and within the Former Primary Disposal Area These borings (SB111shy
SB116) were installed by Connecticut Test Borings Inc of Seymour Connecticut using a track
mounted drill rig equipped with a standard split-spoon soil sampler Two samples from each
boring were submitted for laboratory analysis of TCL VOC and pesticidesPCBs At each
location a surface soil sample was collected from the 0-1 foot interval and submitted for
laboratory analysis Soil samples were then collected continuously from a depth of 1 foot below
the ground surface to the water table A discrete sample from within this zone was submitted for
laboratory analysis based on PID results At locations where no elevated PID headspace readings
were encountered a sample collected from the capillary zone was submitted for laboratory
analysis
5797wpdocsglaquolluprifinaItextmraquo8terrifiil061297 2-16 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
27 Installation of Monitoring Wells and Background Soils Sampling
Following the evaluation of data obtained during the visual Site reconnaissance and microwell
and soil gas surveys a network of monitoring wells was designed that would allow groundwater sampling and analysis and measurements of hydraulic parameters The installation of monitoring
wells at upgradient locations was also included to allow collection of background soil samples and
to determine upgradient groundwater quality
The majority of the Phase 1A investigation monitoring wells were installed by Environmental
Drilling Inc of Sterling MA A second drilling contractor Maher Environmental of North Reading MA was added in December in order to complete the monitoring well program before
the onset of winter The well installation program began on November 7 1994 and was completed on December 29 1994
The original Work Plan specified that a total of 47 monitoring wells would be installed but contemplated that the final number and locations of the monitoring wells could be adjusted based
on the findings of the preliminary screening surveys (ie the microwell and soil gas surveys)
Based on these data which were presented to EPA throughout the course of the screening surveys
EPA approved a Phase 1A monitoring well network which consisted of a total of 39 monitoring
wells at 16 locations
During the course of the Phase 1A monitoring well installation program one anticipated
intermediate depth overburden well (MW109T) was not installed because there was only
approximately 35 feet of saturated overburden encountered at that location A total of 38
monitoring wells at 16 locations were installed The surveyed locations of these wells are shown on Plate 2-6
By the end of the Phase 1A field program a total of 16 locations (or clusters) were completed
and were comprised of the following
bull (2) four well clusters (MW105 and MW107)
bull (4) three well clusters (MW101 MW108 MW112 and MW115) bull (8) two well clusters (MW102 MW103 MW104 MW106 MW109 MW113
MW114 andMW116) and
bull (2) single wells (MW110 and MW111)
(Note An additional 6 groundwater piezometers [PZ201-PZ206] were also installed)
5797wpdocsgalluprifinaltextmasterrifhl061297 2-17 QST Environmental
Gallups Quarry Superjvnd Project - Remedial Investigation
To further delineate the nature and extent of contamination and to refine the hydrogeologic
characteristics within the area of investigation a total of seven groundwater monitoring wells (and
one piezometer PZ301) were installed as part of the Phase IB investigation
The wells completed during Phase IB included the following
bull (3) two well clusters (MW117 MW118 and MW119)
bull (1) bedrock well (installed at the Phase 1A location MW102)
All Phase IB monitoring wells were installed by Connecticut Test Boring Inc utilizing a track-
mounted drill rig The surveyed locations of these wells are shown on Plate 2-6
AH monitoring well labels include a suffix code (eg S TT T or B) which indicates the location
of the screened interval (or open interval in the case of bedrock wells) for that particular well
The screen interval for each prefix is
S - Shallow well in which the screen intersects the surface of the water table
TT - Top-of-Till well in which the bottom of the screen is located just above the till
horizon
T - Till well in which the screen was placed within the till horizon and
B - Bedrock well in which the overburden is sealed off with steel casing which is
grouted into the bedrock surface and the well consists of an unscreened open hole
below the top of the bedrock surface
The TT T and B designations are geologically specific (top-of-till till or bedrock) while the S
designation is depth specific Monitoring well MW109S is in fact located within a till horizon but
was designated as an S well since the screen intersected the surface of the water table Similarly
although monitoring well MW110S is designated as a shallow(s) well observations recorded
during its installation indicate that MW110S is set just below the top-of-till interval
Specifically the 45 wells completed during the Phase 1A and IB investigations included the
following
bull 18 shallow (S) water table wells
bull 13 top of till (TT) wells
5797wpdoc8galluprifinaltextmasterrifhl061297 2-18 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull 5 till (T) wells and
bull 9 bedrock (B) wells
271 Phase 1A Monitoring Well Placement-Rationale
2711 Phase 1A Upgradient Monitoring Wells and Background Soil Sampling
Two monitoring well clusters MW109 (S B) and MW112 (S TT B) were installed to provide
soil and groundwater samples from various depths from locations upgradient of the known former
disposal areas These data were obtained to provide chemical data which was assumed to be
representative of background conditions The general location of these two well clusters was in
accordance with the general east to west direction of groundwater flow across the Site which had
been indicated during previous investigations and by the location of the contaminant plume
identified during the microwell survey The location of MW112 cluster (south of the Former
Seepage Bed) would also serve to confirm the presence or absence of radial groundwater flow
patterns away from the Former Seepage Bed During the installation of these wells soil samples
from stratified drift and till horizons were collected and submitted for laboratory analysis for
TALTCL parameters
A shallow top of till and bedrock well were installed at location MW112 The overburden wells
at this location were successfully installed using hollow stem augers A shallow till and bedrock
well were planned for location MW109 However since only approximately 35 feet of saturated
overburden was encountered at that location only one well MW109S was installed in the
overburden
The overburden and bedrock monitoring wells at these locations were constructed in accordance
with the general procedures described above with the exception of MW109S An abundance of boulders at this location prohibited the ability to advance augers or drive casing more than several
feet below the ground surface After numerous attempts within a 100-foot radius of the desired
location a backhoe was ultimately required to excavate a pilot hole in the unsaturated zone to
approximately 8 feet below the ground surface Augers were then lowered into the pilot hole and
advanced to the refusal depth of 12 feet The overburden well was then constructed as described
in Section 273
The bedrock well at MW109 was installed using a mud rotary drilling technique to drill an
overburden pilot hole to the bedrock surface into which 5-inch diameter steel casing was lowered
and seated on the top of the bedrock surface Another pilot hole was then drilled into the bedrock
to receive the permanent 3-inch casing The bedrock was subsequently cored as described in
Section 273
5797wpdoC8galluprifinaltextmaBterriftU061297 2-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
2712 Phase 1A Monitoring Wells - Former Primary and Secondary Disposal Areas
A total of nineteen ground water monitoring wells were installed in seven cluster locations at
downgradient areas relative to the known Former Primary and Secondary Disposal Areas
Monitoring wells MW102 (S TT) MW105 (S TT T B) and MW107 (S TT T B) were
located along the centerline of a groundwater contaminant plume detected during the microwell
survey and earlier studies
Well clusters MW101 (S TT T) MW103 (S TT) MW104 (S TT) and MW106 (S TT) were
located in areas believed to be beyond the edges of the contaminant plume delineated during the
microwell survey These wells were placed at these locations in an effort to define the plume
boundaries In addition the location of MW103 was selected by EPA to address historic
references to a leachate seep reportedly observed at Mill Brook west of the railroad bridge
Besides the nineteen wells described above another six monitoring wells at three locations were
installed in the vicinity of the Former Primary and Secondary Disposal Areas MW116 (S T) MW108 (S TT B) and MW110S were located north northeast and east of the former disposal
areas respectively to confirm the plume boundaries in these areas
2713 Phase 1A Monitoring Wells - Former Seepage Bed Area
A total of three monitoring wells were installed in the general vicinity of the Former Seepage
Bed A single bedrock well MW11 IB was placed west of the Former Seepage Bed within the
potential fracturefault zone identified by the geophysical studies The purpose of this well was to
assist in evaluation of whether the inferred fracturefault zone may be acting as a preferential
contaminant transport pathway from the Former Seepage Bed The location of MW113 (S B)
west of the Former Seepage Bed was selected to confirm water quality and to obtain
hydrogeological data in this area since an abundance of cobbles prohibited the advancement of
microwells into the saturated zone in this area
2714 Phase 1A Monitoring Wells - Southern Portion of the Site
Five monitoring wells located at two clusters (MW114 and MW115) were installed to determine
water quality and to characterize the hydrogeological parameters in the southern portion of the
Site Although there is no evidence to suggest that disposal activities occurred in areas of the Site
south of the Former Seepage Bed MW114 (S TT) and MW115 (S TT B) were placed to
coincide with locations at which low levels of VOC were detected during the microwell survey
5797wpdocsgalluprifinaltextmasterri fhl061297 2-20 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
272 Phase IB Monitoring Well Placement-Rationale The results of the Phase 1A investigation indicate that a well-defined low to moderate-VOC
concentration groundwater plume originates in the vicinity of the Former Primary Disposal Area
The plume is defined by the presence of certain VOC primarily TCA 12-DCE and xylene The
highest concentrations of these compounds were detected at MW107TT with decreasing
concentrations at downgradient well clusters MW105 MW102 and MW101
The compound PCE was detected in groundwater monitoring wells within the plume but its
distribution in groundwater exhibited inconsistencies with migration from the former disposal
areas In addition the observed concentrations of PCE did not coincide with the observed rate of
plume attenuation and transport rates possibly indicating an off-site source A goal of the Phase
IB investigation was to obtain additional information concerning overburden groundwater quality
and flow patterns in the area north-northwest of the Former Primary Disposal Area in order to
assess the potential for an off-site source
2721 Phase IB Monitoring Wells-Former Primary and Secondary Disposal Areas
One bedrock monitoring well (MW102B) was installed downgradient of the Former Primary and
Secondary Disposal Areas as part of the Phase IB investigation Data collected during the Phase
1A field program indicate that bedrock hydraulic gradients are generally upward across the Study
Area and that bedrock is not a preferential pathway for contaminant migration However low
concentrations of certain VOC were detected in bedrock well MW105B located downgradient of
the Former Primary Disposal Area To determine the nature of contaminant migration in bedrock
further downgradient from the source area a bedrock monitoring well was installed in the vicinity
of well cluster MW102 During the installation of MW102B soil samples were collected from
three intervals within the saturated portion of the overburden aquifer (15-17 30-32 and 45-57
feet below the ground surface) and submitted for laboratory analysis for total organic carbon
(EPA Method 9060)
2722 Phase IB Monitoring Well - North-Northwest of the Site Data obtained from CTDEP files during the Phase 1A investigation indicate that monitoring wells
located on the western and northern sides of the former Pervel flock plant (located just north of
the Site across Mill Brook) historically contained elevated concentrations of certain VOC
particularly PCE TCA and DCE A contribution of VOC in groundwater from this area could
explain at least partly the VOC detections in the wells at MW101 To confirm the potential for
groundwater flow from the former Pervel facility to the area around well MW101 and to further
refine the understanding of groundwater quality and flow in areas north-northwest of the Former
Primary Disposal Area three additional monitoring well couplets and one groundwater piezometer
5797wpdocsgalluprifinaltextmasterrifiil061297 2-21 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
were installed The Phase IB well couplets designated as MW117 MW118 and MW119
consisted of a shallow overburden well and a deep monitoring well screened above the till
horizon A groundwater piezometer designated as PZ-301 was installed in this area to provide
additional hydraulic data The surveyed locations of the seven monitoring wells and the
piezometer installed as part of the Phase IB investigation are shown on Plate 2-6
273 General Monitoring Well Installation Techniques
At each monitoring well (or cluster) location continuous soil sampling was initiated using either a
truck or track mounted drill rig equipped with 425 inch (ID) hollow stem augers and standard 2shy
inch diameter split-spoons The objective was to continuously sample and complete the deepest
overburden boring at each location using hollow stem augers A variety of subsurface conditions
(eg running sands greater that anticipated saturated overburden thicknesses and an abundance of
cobbles and boulders) prohibited the use of hollow stem augers all the way to completion depth at
many locations In order to overcome these drilling conditions EPA approved drive and wash
drilling techniques using water as a drilling fluid to complete many of the deeper overburden
monitoring wells The source of drilling water for this investigation was a nearby fire hydrant
which is connected to the local municipal potable supply system The introduction of drilling
fluids is generally avoided whenever possible as the presence of foreign fluids may cause some
dilution of any constituents which may be present The subsequent use of low-flow purging and
sampling techniques (discussed in Section 29) gave maximum assurance that samples collected
were representative of the natural formation waters
When drive and wash techniques were used the preferred casing diameter was six-inches Six-
inch diameter casing allowed the construction of a desired filterpack thickness of two inches (for
two inch diameter wells) However five-inch diameter and in some cases four-inch diameter
casing was also used primarily at locations in which access and drilling conditions prohibited the
advancement of six-inch casing in a timely and efficient manner EPA approved the use of five-
and four- inch diameter casing provided that the resulting monitoring wells were capable of
yielding low turbidity groundwater samples (which they ultimately did)
In accordance with the Work Plan continuous soil sampling was attempted at the deepest boring
at each location to provide continuous stratigraphic control However the presence of
uncontrollable running sands within certain intervals at several locations made the timely
collection of continuous viable samples extremely difficult In an effort to adhere to the original
schedule as closely as possible EPA approved lengthening the sampling frequency from
continuous to five-foot intervals at locations where running sands were encountered
5797wpdocsgalluprifinaltextmasterrifhI061297 2-22 QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
At several locations auger or casing refusal during the sampling stage was encountered above the
expected depth to bedrock (ie within or on top of the till horizon) At certain bedrock locations
which did not require further soil sampling EPA approved advancing and setting casing using
mud rotary drilling techniques In cases where drilling mud was used as the circulation media
powdered bentonite (National Sanitation Foundation International approved) was mixed with
potable water to yield a relatively thin drilling mud Once the borehole was drilled and stabilized
with drilling mud permanent steel casing was advanced and set The drilling mud was then
completely flushed from the borehole using fresh water and containerized (along with the water)
for eventual disposal In general the use of drilling mud is avoided whenever possible to
eliminate the introduction of foreign compounds in the aquifer Since drilling mud was used to
drill through overburden material (at bedrock wells only) and drilling mud was never in contact
with bedrock fractures the use of mud is not believed to have had any impact on groundwater
samples collected from these wells
All overburden monitoring wells were constructed using 2-inch diameter schedule 40 PVC well
screen and riser All screens consisted of continuous slot construction with 001-inch wide slots
The filter pack sand size grade was selected based on grain size data obtained during the soil
boring program The size-grade chosen (Morie OON) was selected in accordance with EPA
requirements (4 to 6 times the mesh size which retained 70 of the formation material) Most
screens were 10 feet long however several wells screened in till were constructed using 5-foot
long screens due to the limited thickness of the till horizon at those locations (MW105T
MW112T and MW116T) and the requirement to not install screens across different geologic
horizons Regardless of the screen length the filterpack surrounding the well screen extended a
minimum of one foot above the top of the screen A minimum two-foot thick seal of hydrated
bentonite clay was then emplaced above the filter sand pack Bentonitecement grout was then pumped from the bottom of the remaining annular space surrounding the riser pipe to the ground
surface Stainless steel centralizers were utilized to center the PVC screen within the borehole
Each well was completed with a locking 4-inch diameter steel protective casing which was
cemented in place approximately five feet below the ground surface
The bedrock wells were completed as open hole monitoring wells A minimum of four-inch
diameter steel casing was driven and seated on the bedrock surface A 3875-inch diameter pilot
hole was then drilled a maximum distance of five feet into competent rock Permanent 3-inch
diameter steel casing was then cemented into the pilot hole using tremie pipe and allowed to cure
for a minimum of 24 hours Once cured the grout inside the three inch casing was drilled out to
allow the bedrock to be cored At each location a minimum of 10 feet and a maximum of 25
feet of rock was cored using standard NX coring equipment The termination of all bedrock
wells was dependent on the occurrence of water-bearing fractures identified within the cored hole
5797wpdocsgalluprifinaltextmasterrifhl061297 2-23 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
Coring was terminated when evidence of water-bearing fractures were encountered All bedrock
wells were corHeted as open bedrock wells (ie not screened) as it appeared that the cpen holes
would not in-fl or collapse Each bedrock well was furnished with a locking 4-inch diameter
steel protective casing which was cemented in place over the permanent 3-inch diameter steel
riser
All monitoring wells were developed to remove residual particulates from the well and filter pack
and to restore the natural permeability of the formation Following well completion a minimum
of 48 hours were allowed to elapse before well development was initiated to allow the wells to
equilibrate and the grout to set Development was accomplished by overpumping various sections
of the screened interval until the field geologist determined that the pump discharge was visibly
free of particulate material Well development times varied from well to well and depended upon
the amount of fine (silt-clay) grained material at each screen interval Well development times
were usually on the order of several hours Water generated during well development was
containerized for eventual shipment off-site
All soil boring logs rock coring logs and monitoring well construction logs are provided in
Appendix C A summary table which shows survey data and other pertinent information for each
monitoring well and piezometer is presented as Table 2-3
274 Stream Piezometers and Gauges
Nine piezometers were installed at various locations within Mill Brook to monitor surface water
conditions and to determine the role of the local groundwater system in relation to stream
dynamics Water levels were recorded during several periods of the investigation to determine if
Mill Brook is a discharge or recharge point for groundwater in the vicinity of the Site In
addition five stream gauges were installed at piezometer locations PZ-1 PZ-3 and PZ-6 and at
two additional locations in Fry Brook one above and one below the confluence with Mill Brook
The locations of the stream piezometers and gauges are shown on Plate 2-6
Each stream piezometer consisted of a one-foot long slotted steel well point connected to threaded
and coupled lengths 125 inch ID steel pipe with a threaded cap The piezometers were
manually driven a minimum of two feet into the stream bed Water level readings were collected
by lowering an electronic water level indicator along both the inside and outside of the piezometer
to obtain depth to water readings for shallow groundwater beneath the stream bed and depth to
surface water respectively The stream gauges consist of a graduated steel scale attached to a
steel post which was driven into the stream bed
5797wpdocsgalluprifinaltex1masterrifhl061297 2-24 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
275 Groundwater Piezometers
Although not specified in the Phase 1A Work Plan EPA approved the installation of six shallow
groundwater piezometers (PZ-201 through PZ-206) in the southern portion of the Study Area to
provide additional overburden piezometric data A seventh groundwater piezometer PZ-301
was installed north of the Site during the Phase IB investigation The locations of the
groundwater piezometers PZ-201 through PZ-206 and PZ-301 are provided on Plate 2-6
The seven groundwater piezometers were installed using either a track or a truck-mounted drill
rig equipped with 425 inside diameter hollow stem augers At each location the augers were
advanced and the piezometer set at approximately five feet below the top of the groundwater
table The piezometers were constructed of 1-inch diameter PVC well screen and riser equipped
with five-foot long screens Once the screen was set a sand pack was installed to approximately
one foot above the top of the screen A hydrated bentonite seal was then emplaced on top of the
filterpack The remainder of die annular space was backfilled with clean native soil and capped
with concrete Each piezometer was furnished with a lockable protective casing which was
cemented in place Upon completion each piezometer was surveyed and included in each
subsequent round of groundwater level measurements
28 Aquifer Parameter Testing 281 Grain Size Analysis
A total of 41 soil samples collected during the Phase 1A soil boring and monitoring well
installation programs were submitted for laboratory grain size analysis All grain size analyses
were performed using common sieve and hydrometer techniques in accordance with ASTM
Method D 422-63 (Reapproved 1990)
Of the 41 samples 16 were obtained from horizons described as fine stratified drift 15 were
obtained from horizons described as coarse stratified drift and 10 were obtained from horizons
described as till A total of 29 of the samples were obtained during the soil boring program
and 12 were obtained from samples collected during the monitoring well installation program
The analyses were conducted by Geotechnics Inc of Pittsburgh PA a laboratory which
specializes in geotechnical analyses A summary of the samples submitted and their depth interval
is presented as Table 2-4 The results of grain size analyses are discussed in Section 33 In
addition to grain size these samples were also submitted for laboratory analysis for pH moisture
content and total organic carbon
5797wpdoc8galluprifinaltextmasterrifhl061297 2-25 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
282 Slug Tests
Single-well variable head aquifer tests were conducted on all the wells installed during the Phase
1A investigation between January 5 and 27 1995 Rising and falling head tests were performed
on each well using a manually deployed solid cylinder or slug A pressure transducer and an
electronic data logger were used to measure and record the water level response in the well (on a
logarithmic time scale) after the slug was submerged (falling head) and removed (rising head)
Changes in water levels were recorded until the water had returned to or near the original static
level The data collected from the slug tests were analyzed to determine hydraulic conductivity
values for the screened intervals in each well The rate of change of hydraulic head was analyzed
using the Bouwer-Rice Method (Bouwer and Rice 1976) implemented in the computer program
AQTESOLV (Geraghty amp Miller Inc 1989) The results are presented in Section 33 of this
report
283 Constant Flow Tests
Constant flow tests consisting of short-term pumping tests were performed on selected
groundwater monitoring wells as part of the Phase IB investigation Constant flow tests were performed on the following wells MW102TT MW103TT MW104TT MW105TT
MW107TT MW117(S TT) MW118(S T) and MW119(S TT) In these tests an approximate
steady-state drawdown is established in the well and an analytical model of flow to a well is used
to compute hydraulic conductivity The tests were conducted using a variable speed submersible
pump and an electronic water level indicator Prior to the start of each test the static water level
was determined The tests were conducted by running the pumps at a constant known pumping
rate for short periods of time (typically less than 15 minutes) while recording drawdown until
equilibrium was reached The pumping rate drawdown and well construction details were then
used to calculate the hydraulic conductivity The results of the constant flow tests are discussed
in Section 33 of this report Field data and examples of the data reduction method are presented
in Appendix F
29 Groundwater Sampling In accordance with the Work Plan a complete round of groundwater samples was collected
following completion of the Phase 1A monitoring well installation program during January 11shy
19 1995 and is referred to as the Phase lAJanuary 1995 sampling event Subsequent
sampling events were performed as part of the Long Term Monitoring Program during April
July and November 1995 February May August and November 1996 and February 1997 As
discussed in Section 1-1 of this report individual Data Reports for all of the Long-Term
Monitoring Program sampling events (except November 1995 which was presented with the draft
RI Report) have been submitted to EPA
5797wpdoc8galIuprifin8ltextma8terrifnl061297 2-26 QZT Environmental
Gallups Quarry Suptrfund Project - Remedial Investigation
During the Phase IB field program seven new wells were installed and added to the list of wells
that were sampled (for VOC only) during the November 1995 monitoring event Six of these
wells (MW117STT MW118STT and MW119STT) were not added to the list of wells to be
sampled under the Long Term Monitoring Program although MW102B (also installed during
Phase IB) was added to the Long Term Monitoring list In addition to the wells installed during
the Phase IB investigation the following five existing wells located on the former Pervel
property were included as part of the Phase IBNovember 1995 sampling event MW-A -B -C
-2 and -3 The existing on-site wells SW-3S and SW-3D were also included in the Phase
IBNovember 1995 sampling event and the subsequent Long-Term Monitoring Program sampling
events Since the November 1995 Long-Term Monitoring event included wells that were specific
to the Phase IB investigation the November 1995 sampling event is referred to as Phase
IBNovember 1995
During the period spanning the nine sampling events discussed in this report EPA has approved
modifications to the list of wells sampled under the Long-Term Monitoring Program
Modifications to the list of wells sampled have been to delete certain wells particularly those
located in the southern portion of the Site where no site related compounds have been or are
expected to be detected After the July 1995 sampling event wells at the following locations
were eliminated from the Long Term Monitoring Program MW111 MW112 MW114 SW-9
SW-10 and SW-12 Monitoring wells located at MW110 MW113 and MW115 were eliminated
following the Phase IBNovember 1995 sampling event The following subsections describe the
field methods which have been used consistently over the nine sampling events discussed in this
report Table 2-5 shows which wells were included in each sampling event
291 Monitoring Wells The groundwater sampling locations are shown on Plate 2-4 Low-flow purging and sampling
procedures were used to collect groundwater samples in an effort to obtain turbidity-free samples
and to minimize disturbance of the natural formation
The following sequential procedures were employed during the groundwater sampling effort
1) The static water level was measured using an electronic water level indicator
2) The absence of LNAPL was visually confirmed by observation of a sample
collected using a clear plastic bailer
3) All 2 inch diameter (or larger) monitoring wells were sampled using a stainless steel electric submersible pump (Grundfos Redi-Flo 2) equipped with teflon
5797wpdocsgalluprifinaltextmasterrifhl061297 2-27 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
discharge tubing To initiate the purging procedure the intake for the pump was
owered into the mid-section of the well screen For wells smaller than 2 inch
aiameter (ie existing SW- series wells) Teflon tubing equipped with a bottom
check valve was used to inertially purge the well
4) Water was purged from the well at a low flow rate (approximately 05 litersmin)
which was continuously monitored The water quality field parameters
(temperature pH conductivity and turbidity) were monitored during the purging
process until they had stabilized within 10 over three consecutive readings
5) Once the parameters had stabilized (or a minimum of five well volumes had been
purged) groundwater samples were collected for laboratory analysis Samples
were collected from the discharge end of the pump tubing by directly filling the
appropriate sample containers in the following order VOC SVOC (including
pesticides and PCB) metals inorganic compounds At wells that did not stabilize
below the 5 NTU turbidity requirement additional metals samples were collected
filtered through a 045 micron filter and submitted for dissolved metals analyses
(in addition to total metals)
6) Samples were collected from the upper and lower portion of each well using a
clear plastic bailer to visually assess the potential presence of NAPL
All sampling equipment was decontaminated between sampling events All purge water was
containerized for eventual off-site disposal
Duplicate samples matrix spikes matrix spike duplicates field blanks and trip blanks were
included as part of the QAQC procedures All groundwater monitoring sampling forms are
included as Appendix D Most groundwater samples were submitted for TALTCL VOC SVOC
pesticidesPCB and metals although a small number of samples collected during the Phase
lAJanuary 1995 and April 1995 event were submitted for VOC SVOC pesticidesPCB and
metals by Appendix IX methods Also certain samples were selectively submitted for VOC
analyses by Method 5242 The analytical methods for each sample submitted for laboratory
analysis are shown in Table 2-5
5797wpdocsgalluprifinlaquoltextmlaquosterrifhl061297 2-28 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
292 Residential Wells A total of fourteen private drinking water supply wells (DW101-DW114) were scheduled to be
sampled as part of the groundwater sampling program However two of the residences (DW101
and DW112) were unoccupied and inaccessible at the time of each of the sampling events The
residential wells are located along the eastern perimeter of the Site along Route 12 (Norwich
Road) adjacent to the southern portion of the Site along Tarbox Road and along Lillibridge
Road well south of the Site The residential well sampling locations are provided on Plate 2-5
In accordance with the Long-Term Monitoring Program the residential wells were sampled on a
semi-annual basis during the regularly scheduled summer and winter quarterly sampling events
In addition to the Phase lAJanuary 1995 sampling event residential groundwater samples were
collected during July 1995 February 1996 and August 1996 as shown in Table 2-5
Prior to the collection of groundwater samples from the residential wells a visual survey was
conducted to identify the sampling point closest to the well and to determine if any treatment
systems were in use A description and sketch of the supply system was recorded in field
notebooks Each system was opened and allowed to drain for approximately 15 minutes to purge
the plumbing system and obtain representative samples Field parameters were recorded during
purging to determine when stabilization had occurred The groundwater samples collected from
the residential wells were submitted for laboratory analysis of TCL SVOC pesticides PCB TAL
metalscyanide and VOC using EPA Method 5242
210 Surface Water and Sediment Sampling As part of the Phase 1A Investigation surface water and sediment sampling was conducted on
September 13-16 November 22 and December 29 1994 Although all locations were originally
sampled during the September sampling event three samples were lost in transit and had to be reshycollected A total of seventeen sample locations along Mill Brook and unnamed tributaries (UB1shy
UB10 and LB1-LB2) Fry Brook (FBI) Packers Pond (PP1-PP3) and a small pond along Tarbox
Road (TR1) were included in this program The re-sampled locations were UBS and UB6 (112294) and TR1 (122994) Due to dry conditions surface water samples could not be
obtained from the following locations UBS UBS UB6 UB7 and PP1
In accordance with the Long Term Monitoring program additional surface water samples were
collected during the April 1995 November 1995 May 1996 and November 1996 sampling
events to coincide with the approximate seasonal high- (ie spring) and low-water (ie autumn)
periods Following the initial Phase lAJanuary 1995 sampling event and per the request of
EPA the location of UB6 was moved due south to Mill Brook and renamed UB6A The surface
watersediment sample locations are shown on Plate 2-6 Sample locations by date are shown on
Table 2-5
5797wpdocsgalluprifiMltextmasterrifhl061297 2-29 Q5T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Surface water samples were collected using the actual laboratory sample containers by direct
immersion into the water Parameters which required the use of preservatives (eg metals
requires the addition of nitric acid to the sample) were collected in a stainless steel beaker and
transferred directly to the sample container to prevent loss of the preservatives during sampling
All sampling equipment was decontaminated after each use and placed into clean plastic bags
before moving on to the next station Surface water samples were collected starting at the most
downstream locations and progressed in order upstream The surface water samples were
submitted for laboratory analysis for TCLTAL compounds VOC and the following wet
chemistry parameters total organic carbon total dissolved solids total suspended solids hardness
and alkalinity The samples collected during April 1995 November 1995 and May 1996 were
also submitted for laboratory analysis of SVOC pesticides and PCBs The following field
measurements were also collected as part of the sample collection temperature conductivity
pH dissolved oxygen and turbidity
In addition to surface water during September 1994 sediment samples were collected at each of
the 17 locations (including the dry locations referenced above) Samples were collected at a depth
of 0 - 8 below the surface using manually operated soil or mud augers which were
decontaminated between sample locations The sediment samples were collected starting at the
most downstream locations and progressed in order upstream The sediment samples collected
contained greater than 30 percent solids based on visual and manual determination Samples were
submitted for laboratory analysis for TCLTAL compounds and for total organic carbon
Physical stream bed parameters (width depth and flow rate) were measured at surface water
sampling locations where discernable flow occurred This task was completed in April 1995
since the stream was at extremely low flow stages during the September 1994 sampling round
and a number of surface water sampling locations were nearly dry During the April 1995
surface water sampling event stream flow conditions were such that flow rates could be measured
at the following 5 locations UB4 UB6A UB9 UB10 FBI Locations at Packers Pond and the
small pond on the south side of Tarbox Road (TR-1) were not subject to these stream
measurements
Stream width and depth measurements were made using a fiberglass tape measure Depth and
stream flow measurements were recorded at the midpoint and quarter-points across the stream
Stream flow measurements were recorded using a Swoffer model 2100 in-situ flow meter The
flow meter was mounted on a graduated aluminum shaft which was equipped with an electronic
digital readout To calculate stream-flow the average cross-sectional area in square feet was
multiplied by the average water velocity (feetsec)
5797wpdocsgraquolluprifinaltextmasterrifhl061297 2-30 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
211 Wetland Soil Sampling In early September 1994 samples of wetland soils were collected from 10 locations within the
Study Area These sample locations (QW1-QW10) are shown on Plate 2-6 (and on Plate 3-14
which shows delineated wetlands as discussed in Section 341) Each sampling station was
marked with labeled stakes which were eventually included in the Site location survey The
samples were collected at locations situated near the edge of the wetlands at depths within one foot of the water table and below the organic mat The samples were collected using manually
operated soil or mud augers which were decontaminated between sample locations The samples were submitted for analysis of TCLTAL compounds and total organic carbon The results of the
wetland soil sampling program are discussed in Section 43
212 Evaluation of Existing Monitoring Wells As part of the Phase 1A investigation the remaining 11 monitoring wells installed during the
1978 Fuss and ONeill Inc investigation were evaluated to determine which wells could provide
usable water level data The present condition of each well was documented and a water level and total depth measurement were taken and compared to well construction logs If the wells
were determined to be potentially viable an attempt was made to test them for hydraulic
responsiveness by conducting rising and falling head slug tests Several of the wells were missing
protective casings had been broken off below the ground surface or had infilled with sediment
The results of the hydraulic evaluations are presented in Section 33 The locations of the
remaining existing monitoring wells are shown on Plate 2-4
A summary of the condition of each existing monitoring well is presented as Table 2-6 The
majority of the existing wells are presently in poor condition Most of these wells are lacking
surface seals andor adequate protective casings Several of the wells have no protective casings at all and are comprised only of PVC riser which is broken at or near the ground surface
Based on the present total depths of several of these wells compared to their total depths at the time of construction it is evident that the screen section of several of these wells have infilled
with sand or silt Based on their present condition and the fact that new monitoring wells have
been installed ESE recommended that any of the existing wells not included as part of the Long-
Term Monitoring Program be properly abandoned Following this recommendation EPA
approved the abandonment of the following wells SW13 SW14 SW17S D and SW18 Also
the protective casings at existing wells SW-3S SW-3D SW-9 SW-10 and SW-12 were repaired
since these wells are used to measure groundwater elevations as part of the Long-Term
Monitoring Program
5797wpdoc8galluprifinaltextmasterrifhl061297 2-31 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
213 Ecological Assessment 2131 Wetlanl Delineation
A wetland delineation was conducted on Site and focused primarily on the wetlands located north
and west of the Study Area This survey was limited to the Site side of Mill Brook up to the
present channel In order to meet both Federal and State requirements two methods were used to
delineate the Study Area wetland boundaries In accordance with federal requirements wetlands
were delineated using US Army Corps of Engineers (COE) methods Since the State of
Connecticut recognizes a slightly different methodology for wetland delineation the services of a
soil scientist certified by the Society of Soil Scientists of Southern New England were also
required The only difference between the two methods is that while the COE requires analysis
of vegetation composition hydrology and hydric soil indicators the State of Connecticut requires
only the analysis of hydric soil indicators
Jurisdictional wetland boundaries were determined by evaluating several points along the
hydrologic gradient Vegetation soil and hydrology criteria were measured or observed to
determine whether the point was within or above the Jurisdictional wetland boundary In order
for an area to be judged Jurisdictional wetland criteria must be met for all three parameters (ie
vegetation hydrology and soil)
21311 Vegetation
Wetland criteria for vegetation was based on the National List of Plant Species That Occur in
Wetlands (Reed 1988) Dominant plant species were identified at the observation point and listed
on data forms for routine on-site wetland determination The stratum where the plant occurred
(canopy shrub or herb) and indicator status for that plant were recorded A dominance of
wetland indicator species indicates that the vegetation criteria is met A dominance of upland
indicator species indicates that wetland criteria are not met
21312 Hydrology
Hydrologic criteria includes the visual observation of surface water inundation soil saturation or
indirect indication of previous saturation or inundation Indirect evidence includes watermarks
(stain lines on vegetation or structures) drift lines (debris deposited in a line at the high water
mark) sediment deposits and drainage patterns within wetlands
21313 Hydric Soils
The identification of hydric soil criteria includes soil types named as hydric by USDA Soil
Conservation Service or the presence of hydric indicators within the soil profile Indicators
include mottling or streaking of organic materials high organic content the presence of sulfitic
material soil colors (gleyed colors) and others
5797wpdoc8galluprifinaltextmasteirifhl061297 2-32 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
2132 Plant and Wildlife Survey
The objective of the Phase 1A ecological assessment was to qualitatively identify any real or
potential impacts to local ecological receptors within the Study Area or otherwise influenced by
the conditions originating at the Site All observations on plants and animals were noted in field
logs during the wetland delineation
The results of this survey will assist the EPA in the performance of a more formal ecological risk
assessment During the ecological risk assessment sediment soil water and air quality data and
observations of plant and animal communities will be used (see also Section 123) to identify any areas where impacts have occurred The results of the qualitative plant and animal survey
conducted during the wetland investigation are discussed in Section 34 of the text
214 Test Pit Explorations In lieu of ground penetrating radar surveys (as discussed in Section 233) and with EPA
approval additional EM and MAG surveys were performed over a five-foot by five-foot grid in
the vicinity of unexplainable anomalies which were detected during the initial EM and MAG
surveys Once accurate locations for the anomalies were determined and marked on the ground
surface test pit explorations were conducted to confirm the source of the anomalies
On December 21 1994 test pits were excavated at a total of four locations at which
unexplainable anomalies were detected The test pits were performed under the observation of
EPA oversight contractor personnel The locations of the four anomalies and associated test pits are shown on Plate 2-7 At each anomaly a trench (or series of trenches) was systematically
excavated in one to two foot lifts using a backhoe The trenches were oriented to intersect the
longest axis of each anomaly to maximize the possibility of unearthing the source of the anomaly Once a lift was complete soil obtained from the trench walls as well as that obtained from the
backhoe bucket was screened with a PID for evidence of VOC The excavated soil and the trench
itself were also visually monitored for objects capable of producing the anomalies detected during the geophysical surveys and for other features possibly associated with disposal activities (eg
stained soil)
Once the source of each anomaly was discovered the object was excavated and the test pit was
backfilled and regraded with clean soil obtained from the excavation Since no elevated PID
readings or other signs of disposal features were encountered during the test pit operations no
soil samples were submitted for laboratory analysis Test pit logs for these excavations are
presented in Appendix E
5797wpdocsgalluprifinaltextmasterrifhl061297 2-33 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
30 Physical Characteristics of the Study Area
31 General Characteristics 311 Regional Physiography
The Site is located along the eastern border of the Quinebaug Valley Lowland This regional
feature is dominated by the southerly flowing Quinebaug River and is comprised of a north-south
trending lowland area which is approximately 2 to 3 miles in width and approximately 25 miles
long The Quinebaug River originates at headwaters located in central Massachusetts and
terminates at Norwich Connecticut where it merges with the Shetucket River approximately 12 miles south of the Site The confluence of these two rivers form the Thames River which flows
to the south approximately 15 miles and ultimately discharges into Long Island Sound
The region is characterized by relatively low relief and numerous glacial features The regional
landscape is significantly influenced by the structure of the underlying crystalline metamorphic
bedrock which is discontinuously overlain by Pleistocene glacial sediments of variable thickness
Lowland surficial features are characteristic of late Pleistocene glacial retreat processes and
include numerous kettleholes and swamps many of which are interconnected by a network of
slow draining streams
Land surface elevations in the vicinity of the Site range from approximately 150 to just over 220
feet above sea level Lowlands are bounded to the east and west by upland terrain which consists of irregular hilly areas of moderate relief The uplands contain many areas with large bedrock
ledges generally thin glacial deposits (predominantly till) poorly drained valleys and small
isolated swamps Elevations in the uplands range from 200 to 600 feet above sea level
312 Study Area Physiography
The topography on the Site is highly irregular primarily due to past quarrying operations
Numerous overgrown mounds of earthen materials (eg crushed stone sand and gravel) and
excavated depressions are scattered throughout the Site Visual reconnaissance and a number of
screening surveys (eg soil gas and surface geophysical investigations) have confirmed that many
of the features previously identified from the review of historic aerial photographs as potential
disposal areas (Bionetics 1990) were in fact features remnant of quarrying and former CTDOT
operations
The ground surface on the Site (shown on Plate 3-1) generally slopes from east to west and to a
large degree is controlled by the underlying bedrock surface The highest point within the Study
Area consists of a bedrock high overlain by a thin veneer of till and is located in the eastern
5797wpdoclaquogalluprifinraquoltextma8terri fhl061297 3-1 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
central portion of the Site Elevations in this vicinity peak at approximately 230 feet above sea
level
The northern portion of the Site which includes the Former Primary and Secondary Disposal
Areas consists predominantly of open sparsely or non-vegetated areas of sand and gravel This cover material is presumed to have been distributed over the ground surface following CTDEP
Site remediation efforts in 1979 Presently the Former Primary and Secondary Disposal Areas are visible as roughly circular depressions which are approximately 150 feet and 60 feet in
diameter respectively The depressions are approximately 8 to 12 feet deep relative to the
surrounding ground surface These depressions intermittently contain as much as several inches
of standing water which accumulates during periods of heavy precipitation The bottoms of the
depressions are lightly vegetated with various grasses and weeds
North and west of the Site the ground surface elevation decreases as the Mill Brook floodplain is
encountered The floodplain area consists of low lying heavily vegetated wetland areas which
are periodically inundated
Excluding the isolated topographic high spot at the eastern margin of the Site the southern
portion of the Site (from the vicinity of the Former Seepage Bed to Tarbox Road) can be
described as generally flat but includes numerous man-made small-scale features such as
mounds or depressions
313 Surface Water Features
The Site is centrally located within the Mill Brook drainage basin which encompasses
approximately 18 square miles The Mill Brook drainage basin is part of the larger Quinebaug
River regional drainage basin Mill Brook a tributary to the Quinebaug River is located 250 feet
north of the Site and flows from east to west Approximately 1000 feet northwest of the Site (in
the vicinity of the Plainfield municipal sewage treatment plant) Mill Brook is joined by Fry
Brook which flows from the north Packers Pond which is located approximately 3000 feet
west of the Site was formed by the construction of a dam across Mill Brook
There are no surface water bodies located on the Site itself although several low areas (which
were excavated during previous site activities) have been observed to contain ponded water during
periods of extended precipitation
Surface water flow rates (determined during the April 1995 sampling event) were determined for
the following five locations in Mill Brook UB4 UB6A UB9 UB10 and at FBI in Fry Brook
Along Mill Brook flow rates ranged from approximately 23 cubic feet per second (cfs) at the
5797wpdocsgalluprifinaltextmasterrifnl061297 3-2 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
most upstream location (UB4) to approximately 31 cfs at the most downstream location (UB10)
Along the northern Study Area a 3 cfs increase was observed from Stations UB6 to UB10
representing a flow rate increase of about 025 cfs per 100 feet of stream length The flow rate in Fry Brook (Station FBI) was approximately 16 cfs
314 Climate The Site is located within Connecticuts Central climate division According to published
National Weather Service data (USGS 1993) the average annual temperature is approximately
50degF the coldest month is January with an average temperature of 258T and the warmest month is July with an average temperature of 714degF Annual precipitation at nearby recording
stations (located in Norwich CT and North Foster RI) averages approximately 53 inches per
year and ranges between approximately 41 and 68 inches per year (based on historic data from
1978 to 1991) The monthly distribution of precipitation is relatively even throughout the year
32 Geology 321 Regional Surficial Geology
The surficial or overburden deposits in the area consist of unconsolidated materials deposited as a
result of glaciation during the Pleistocene epoch Various glacially-derived materials including till meltwater or stratified drift deposits and post-glacial deposits of floodplain alluvium
comprise the major surficial geologic units in the vicinity of the Site Areas covered by eolian dune deposits are also noted on surficial geologic maps of the area although no dune deposits are
found within the Study Area
Till deposits in the region consist of non-sorted and generally non-stratified mixtures of sediments
with grain sizes ranging from clay to boulders Till is formed by the direct deposition of ice debris on the land surface Generally the color and lithology of till is dependant upon the
composition of local surficial deposits underlying bedrock and northerly adjacent bedrock from
which the till was derived Tills deposited during two periods of glaciation are present in the
region and blanket the bedrock surface in various thicknesses The most extensive and prevalent
till which is commonly present in surface exposures was likely deposited during late
Wisconsinan glaciation (USGS 1995) This till is referred to as upper till and is described as
predominantly loose to moderately compact generally sandy and frequently stony
A less commonly exposed lower (older) till was deposited during earlier glaciation possibly during the Illinoisan or early Wisconsinan glaciation periods The lower till is generally compact
to very compact and is typically finer-grained and less stony than the younger upper till A
weathered zone is usually present between the two till units
5797wpdoc8gnlluprifinaltextmasterrifnl061297 3-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Directly overlying the till (or bedrock where till is absent) are glacial meltwater deposits
collectively referred to as stratified drift These deposits consist of poorly to well sorted
assemblages of gravel sand silt and clay which were deposited by glacial meltwater during the retreat of the last ice sheet Variations in the composition structure and texture of the stratified
drift deposits are dependent upon the depositional environment in which they formed Deposits exhibiting a relatively high degree of sorting andor stratification can usually be classified as
either glaciofluvial (stream) deposits glaciodeltaic (where streams entered glacial lakes) deposits or glaciolacustrine (lake bottom) deposits The horizontal and vertical contacts between these
deposits are generally transitional and were dependent upon the available sediment load and
proximity to the various depositional environments (eg streams or lakes) associated with the
retreating ice front For example coarse-grained deposits of sands and gravel were usually
deposited proximal to the ice margin while further away primarily in glacial lakes deposits of
fine sand silts and clay were prevalent Poorly sorted deposits of relatively coarse material were
typically deposited at the ice front or along bedrock valley walls During the glacial retreat
these deposits would be left behind or collapsed on any underlying deposits Contemporaneously bedrock valleys were frequently dammed by glacial deposits andor masses
of glacial ice behind which glacial meltwater could accumulate forming glacial lakes Gradual
retreat of the ice margin as well as the formation (and eventual draining) of glacial lakes over
time would result in changes in the depositional environment which are seen as textural changes in the stratified drift deposits
Postglacial deposits of sand gravel silt and organic materials are also present as floodplain
alluvium along streams and rivers in the region The texture of alluvium varies over short
distances both laterally and vertically and is generally less than 5 feet thick along small streams
Since alluvial material typically represents re-worked glacial deposits the alluvium is often similar to the surrounding parent glacial material
322 Local Surficial Geology
The Study Area is located on the eastern flank of a pre-glacial bedrock valley and is bounded to
the east by bedrock-controlled upland areas and to the west by an area known as the Quinebaug
Valley lowlands Following the last period of glaciation (in which the relatively thin veneer of till
was deposited) various temporary depositional environments existed as a result of the presence of
an ice and sediment dam approximately 10 miles south of the Study Area which caused the
formation of a glacial lake Evidence of the lake (referred to as Glacial Lake Quinebaug) is well
documented in the literature (Stone amp Randall 1977) As the ice sheet retreated northward deposits left behind were dominated by sand and gravels associated with the formation of a series
of progressive and coalescing deltaic complexes which developed within the rising lake In lower
lying areas where deltas did not form finer-grained sand silt and clay was deposited Although
5797wpdocsgalluprifinaltextma8terrifhl061297 3-4 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
much of this sediment may originally have been deposited with some degree of structure or
sorting much of the structure was lost (collapsed) when the ice mass eventually melted away
The depositional environment was further complicated by the presence of residual ice blocks left
behind during the retreat of the main body of the glacier As the various depositional features
formed around these ice-blocks their eventual melting left behind depressions or kettles into
which fine sediment could settle While many kettles were eventually filled many remain as
detached or poorly drained ponds
As a result of the depositional history of the Study Area the primary surficial or overburden
deposits encountered are till and stratified drift Depending upon location the stratified drift may
be generally broken down into fine (eg silt and fine sand) or coarse (eg sand and gravel)
grained components but at many locations the change is transitional and subtle in both vertical
and horizontal directions The thickness of the stratified drift deposits ranges from non-existent
up to approximately 70 feet At some locations distinct structure is exhibited while at other
locations the structure has collapsed Post-glacial alluvial floodplain deposits were encountered
at locations within the present Mill Brook floodplain however the overall significance of these
deposits is minor
To illustrate the local geological features a series of geologic cross-sections have been prepared
At several locations lithologic data from pre-RI wells (both on-site and off-site) were
incorporated for additional detail The boring logs from which the cross sections were prepared
are included in Appendix C
As shown in cross-sections A-A B-B C-C D-D E-E and F-F (Plates 3-2 through 3-5) till
was encountered just above the bedrock surface at nearly every location The till horizon ranges
in thickness from approximately 10 to 20 feet with the thickest accumulations located along the
centrally located topographic high Surficial exposures of glacial till were observed within the
central portion of the Site as seen in cross sections A-A and C-C The till observed within the
Study Area is comprised of a fine sandy matrix containing abundant gravel cobbles and
boulders The till deposits seen in the topographically higher areas (ie elevations greater than
approximately 160 feet) were for the most part unsaturated Although reference literature for
this area (USGS 1995) describe the possible presence of two different till horizons no apparent
differentiation was observed at the site
As seen in the boring log from MW111 deposits of till are exposed at the ground surface and in
the central area of the Site However as shown on cross sections A-A and C-C (Plate 3-2) and
D-D (Plate 3-3) the bedrock surface drops off rapidly in southerly westerly and northerly
directions where relatively thick accumulations of stratified drift have been deposited over the till
5797wpdocsgalluprifinlaquoltextmalaquotemfhl061297 3-5 QFT Environmental
Gallups Quarry Superftind Project - Remedial Investigation
Within 500 feet of the central portion of the Site the overall thickness of the stratified drift
deposits increase to nearly 70 feet In the vicinity of MW113 (west of the central portion of the
Site) the lower portion of the stratified drift is comprised of approximately 30 feet of very fine to
medium-grained sand with occasional thin layers of silt This deposit appears to increase in
thickness towards the west while it thins towards the central portion of the Site where it pinches
out against the till Overlying these fine-grained deposits are approximately 30 feet of poorly
structured sand and gravel which includes abundant cobble sized material The coarser upper
stratified drift material also thins eastward towards the Site where it is in contact with the till
The coarse upper material is generally unsaturated with the groundwater table occurring at the
approximate upper surface of the fine sand
The southern portion of the Study Area is shown on cross sections A-A (Plate 3-2) and D-D
(Plate 3-3) As indicated on the southern end of cross section A-A approximately 35 feet of
stratified drift overlies the till in the vicinity of MW112 Although much of the stratified drift at
MW112 is relatively coarse an approximately 12 foot thick layer of fine-grained sand and silt is
present from about eight to twenty feet below the ground surface From MW112 the thickness of
the stratified drift thins to the north where it contacts the central topographic high
From the southeastern corner of the Site near MW112 the bedrock surface slopes downward
towards the west-southwest to a depth of approximately 75 feet below the ground surface (as seen
at location MW115 on the southern end of cross section D-D[Plate 3-3]) At MW115
approximately 65 feet of stratified drift (comprised of a sandy matrix containing a significant
amount of coarser gravel and cobbles) overlies approximately 10 feet of till
As seen in cross section B-B (shown on Plate 3-4) and A-A (Plate 3-2) the northeastern portion
of the Site (in the vicinity of the Former Primary Disposal Area) is comprised of fairly well
sorted fine- to medium-grained sand with occasional thin lenses of very fine sand and silt The
lenses of finer-grained materials appear only locally in the vicinity of MW107 and MW108 at a
depth of about 25 feet and are typically only a few inches to a few feet in thickness with limited
lateral extent Beneath the fine-grained sand and silt and directly overlying the till is 10 to 20
feet of coarser-grained sand and gravel Moving westward along cross section B-B in the
vicinity of MW105 the fine-grained sand thins and grades into coarser sand and gravel deposits
The coarse sand and gravel deposits directly overlie the till and thicken to nearly 50 feet towards
the west in response to the downward slope of the bedrock surface This portion of the Study
Area which is northwest (and downgradient) of the Former Primary and Secondary Disposal
Areas is overlain by a thin veneer of recent alluvial and swamp deposits associated with the
present Mill Brook channel and floodplain As shown on the cross section (B-B) the stratified
drift deposits in this area are very nearly saturated throughout their entire thickness
5797wpdoc8galluprifinaltextmasterrifiiiy061297 3-6 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
North of the Former Primary Disposal Area (along the northern end of cross section D-D) the
bedrock surface continues to gradually slope downward (to the north) until the approximate
location of MW116 North of MW116 the bedrock surface is interpreted as appearing to rise
based on the depth to till deposits encountered beneath MW119 Stratified drift deposits
immediately north of the Former Primary Disposal Area in the vicinity of MW116 are dominated
by approximately 25 feet of fine grained sand and silt Further north along section D-D the
finer sand and silt deposits thin and are overlain by coarser grained sand and gravels Relatively
thin post-glacial stream alluvium and modern swamp deposits associated with Mill Brook are also
seen in the vicinity of MW116 and MW119 A roughly east-west cross section (E-E [Plate 3-5])
has been prepared to illustrate the lithologic features in the area north-northwest of the former
disposal areas This cross section starts at MW119 (described above) and runs west to MW101
in a line approximately parallel to Mill Brook The fine sandsilt deposit seen in the vicinity of
MW119 is also observed to the west at MW117 at the same approximate thickness and elevation
Westward from MW117 the fine sandsilt deposit grades into the more prevalent coarse sand and
gravel deposits observed at MW118 and MW101 The northernmost cross section (F-F [Plate 3shy
5]) extends westward from MW3 (located just east of the former Pervel flock plant) to PZ301
As shown on F-F this portion of the Study Area is dominated by collapsed coarse sand and
gravel deposits at least to the completion depths of the borings (MW3 MWC and PZ301) along
the line
323 Regional Bedrock Geology
Bedrock in the vicinity of the Site is mapped as a lower member of the Quinebaug Formation
which is composed of metasedimentary and metavolcanic rocks of Paleozoic age The Quinebaug
Formation is part of the Putnam Group and exhibits a sillimanite grade of metamorphism The
bedrock consists of primarily light to dark grey fine- to medium-grained hornblende gneiss biotite gneiss and amphibolite Bedrock in the area is strongly faulted and folded and exhibits
varying degrees of mylonitization A major fault zone known as the Lake Char fault is located
approximately 03 miles east of the Site The Lake Char fault is a north-south trending fault
which offsets rock units of the Putnam Group and the Hope Valley Alaskite Gneiss formation A
northwest-trending fault is shown on the USGS Bedrock Geologic Map (Dixon 1965) of the
Plainfield Quadrangle in the vicinity of the Former Seepage Bed The existence and approximate
location of the suspected fault was based on aeromagnetic data published in 1965 (Boynton amp
Smith 1965) Bedrock located north of the inferred fault is mapped as more intensely
metamorphosed cataclasites and blastomylonites The fault is mapped as extending into the Tatnic
Hill formation to the west but is not mapped within the Hope Valley Alaskite Gneiss formation
which is located to the east
5797wpdoc8galluprifinaltextmasterrifhl061297 3-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
324 Local Bedrock Geology
Confirmed depns to bedrock were determined based on the elevations of bedrock outcrops and
the collection of bedrock cores at nine boring locations (MW102B MW105B MW107B
MW108B MW109B MW111B MW112B MW113B and MW115B) Inferred depths to
bedrock were made at seven additional locations (MW101 MW102 MW103 MW104 MW114
MW116 MW117 MW118 and MW119) based on boring data obtained during the drilling of the
deepest wells at each cluster (which indicates the minimum depth to bedrock) and based on trends
seen at the confirmed depth locations Based on this evidence it is likely that unconfirmed depths
to bedrock are accurate to within several feet of the actual depths At MW110S no attempt was
made to advance the boring more than about 12 feet below the ground surface (the depth needed
for the required shallow well at that location) Depths to bedrock ranged from approximately 13
feet at MW111B to 83 feet at MW113B Drilling difficulties associated with the presence of
boulders just below the ground surface at MW11 IB made it difficult to determine the exact depth that bedrock was first encountered at this location Suspected boulders were encountered starting
at approximately six feet below the ground surface and casing was driven to a refusal depth of
approximately 15 feet before bedrock coring began
Based on the data described above a bedrock surface contour map is shown on Plate 3-6
Bedrock elevations are highest in the eastern central portion of the Study Area and decrease to the
north and west and to a lesser degree to the south
Within the Study Area bedrock consists of grey fine- to medium-grained gneiss with varying
contents of amphibolite biotite and hornblende Various degrees of weathering and competency
were also observed Detailed rock core descriptions are presented on the rock coring logs
provided in Appendix C
The primary objective of the seismic refraction survey (discussed in Section 234) was to
identify if present the location of a possible bedrock fault suspected to exist hi the vicinity of the
Former Seepage Bed As discussed in Section 323 the approximate location of the suspected
fault was estimated from the regional USGS Bedrock Geologic Map based on an aeromagnetic
survey conducted in 1965 Ground penetrating radar surveys conducted by the USGS (1995)
identified a northward dipping subsurface reflector beneath the central portion of the Site This
reflector was interpreted as a potential bedrock fault feature The relatively high strength of the
reflector was attributed to fault gouge (or other infilling) material or possibly sorbed inorganic
compounds No subsurface explorations were conducted at the time of the USGS investigation to
confirm the nature of the radar reflector
5797wpdocsgalluprifinaltextmiiraquoterrifnl061297 3-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Evaluation of data obtained from the seismic refraction survey indicates the presence of possible
bedrock fractures on seismic lines 3 through 6 (Plate 3-7) In addition to these interpreted
fracture zones the overall relatively low seismic velocities (12000 ftsec vs 15000 to 18000
ftsec for intact crystalline rock) indicate that in general the rock is somewhat fractured
Although the original intent of the magnetometer (MAG) survey was not to interpret bedrock
features data obtained during the MAG survey (which covered a much larger area) indicate the
presence of several linear-shaped sharp magnetic gradients bounding a zone with a different
magnetic signature The change in magnetic signature was interpreted as potentially associated
with changes in bedrock lithology and fracturing across a broad faultfracture zone in the central
portion of the Site These interpretations are described in further detail in the Weston
Geophysical Report included as Appendix A The locations of the magnetically determined
bedrock features are also shown on Plate 3-7 While the seismically interpreted fractures do not
strongly coincide with linear features seen in the MAG data they do lie within the magnetically
determined fractured zone
The geophysical data described above as well as the rock-core retrieved from MW111B further suggest that bedrock beneath the central portion of the Site may be more accurately characterized
as a series of fractures and faults rather than an area of competent bedrock with one or two
discrete faults
33 Hydrogeology The following sections discuss data collection and evaluation results relative to groundwater flow
directions and rates in overburden deposits and the upper portion of the bedrock unit
331 Hydraulic Conductivity The hydraulic conductivity distributions within the overburden and bedrock formations were
evaluated through the performance of rising and falling head slug tests constant flow tests and
by empirical correlations with measured soil grain size distributions The slug test methodology
and data analysis methods are discussed in Appendix F Because the falling head test results for
shallow wells were influenced to some degree by soil above the water table only rising head test
data were used for the water table wells to compute mean values The constant flow test
methodology is described in Section 283 and Appendix F Table 3-1 summarizes the measured
hydraulic conductivity values from the slug and constant flow tests for wells grouped together
based on lithology and screen depth as follows shallow top-of-till till and bedrock Hydraulic
conductivity estimates based on grain size are listed in Table 3-2 for comparison but only
constant flow and slug-test data were used to calculate mean hydraulic conductivity values for
different portions of the aquifer Laboratory grain size data are presented in Appendix G
5797wpdocraquogalluprifinlaquoltextmastem fill061297 3-9 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
The top-of-till wells are considered to be the most representative of the more permeable section of X^^JF
the overburden aquifer characterized by coarser soil grain sizes where a large percentage of the
total groundwater flow occurs Across the Study Area the mean hydraulic conductivity for the
top-of-till wells is 0005 centimeters per second (cms) with values ranging from 0000053 cms
to 0074 cms Northwest of the railroad tracks in the northern portion of the Study Area where
the aquifer thickens the mean hydraulic conductivity for top-of-till wells (MW102TT
MW103TT MW104TT MW117TT and MW118TT) is 0037 cms This value of 0037 cms
which is approximately an order of magnitude larger than the overall Study Area mean for top-ofshy
till wells appears to be most representative of the hydraulic conductivity within the major portion
of the VOC plume By comparison the grain size results are similar in magnitude but somewhat
lower than the Study Area average for the constant-flow and slug tests because they indicate an
average hydraulic conductivity of 0003 cms for the coarse stratified drift samples with values
ranging from 00006 cms to 0006 cms The mean hydraulic conductivity for shallow wells
which are generally screened in finer-grained soils is 0001 cms and varies between 000006
cms and 002 cms The shallow well constant-flow and slug test results are comparable to the
mean grain-size correlation value of 0002 cms for fine stratified drift soil samples
The mean hydraulic conductivity for the till wells (000047 cms) is approximately a factor of ten
less than the mean Study Area top-of-till value and varies between 00002 cms and 0002 cms
The till appears to be hydrogeologically different from the other overburden deposits and on the
average provides increased resistance to groundwater flow This added resistance is not
considered to be significant however because the consistency of the till is highly variable and the
hydraulic conductivity contrast is relatively small
The slug test results for the bedrock wells yield the lowest average hydraulic conductivity
000018 cms The bedrock results though should be considered less accurate than the
overburden estimates due to the highly variable nature of the fractures in the rock matrix and their
associated non-linear effect on computed hydraulic conductivity
332 Groundwater Flow
3321 Surficial (Overburden) Groundwater Flow
The following discussion on overburden groundwater flow is organized according to relative
locations within the Study Area All references to flow direction are inferred based on measured
hydraulic gradients The central portion of the Site in the vicinity of the Former Seepage Bed is
dominated by the presence of a bedrock-controlled topographic high which for the most part is
overlain by unsaturated till Because of this feature overburden groundwater flow patterns can be
effectively treated as separate entities those located to the north of the hill and those located to
the south
5797wpdocraquoglaquolluprifinlaquoltextmasterrifhl061297 3-10 QampT Environmental
Gallups Quarry Superand Project - Remedial Investigation
Table 3-3 summarizes the water level data collected from monitoring wells and piezometers
during the quarterly monitoring rounds Plates 3-8 and 3-9 depict deep and shallow piezometric head distributions respectively (for November 6 1995) throughout the northern Study Area
Plate 3-9 also shows the piezometric head distribution in the southern Study Area Groundwater
flow maps for other dates are presented in the ISCR (ESE 1995) Water level data for the
monitoring wells at the former Pervel facility were used in both the shallow and deep flow maps
because they are screened in the middle portion of the aquifer As a result these wells are
considered to be hydraulically representative of both portions of the aquifer A saturated
thickness map (Plate 3-10) was created by subtracting the interpolated bedrock surface (Plate 3-6)
from the shallow overburden piezometric surface measured on November 6 1995 which is approximately equal to the groundwater table configuration To facilitate interpretation of flow
patterns calculated two-dimensional groundwater pathlines which represent the mean horizontal trajectory of a parcel of groundwater in the overburden aquifer originating from several locations
in the Study Area are also shown however the pathlines do not account for vertical flow within the aquifer which is important in the shallow portion of the aquifer Data interpolation by the
method of kriging piezometric head contour development and numerical computation of pathlines were performed using the data analysis and visualization software package Tecplot
(Amtec Engineering 1994) The pathlines are based on a steady state velocity field computed
directly from the interpolated head distribution using Darcys law and assume homogeneous
isotropic conditions
Southern Study Area
Overburden groundwater flow south of the Former Seepage Bed is primarily influenced by two factors (1) the slope of the bedrock surface which defines the base of the unconsolidated deposits and (2) regional hydrologic drainage patterns The west-southwest dip of the bedrock
surface strongly influences the general east to west flow of groundwater The average east-west
horizontal hydraulic gradient in the southern portion of the Study Area is approximately 001 feet per foot (feet of vertical head change per foot of horizontal distance)near well MW112S and
piezometer PZ-202 whereas the typical bedrock surface slope in this area is about 01 feet per
foot The configuration of the bedrock surface is important because the slope of the groundwater
table in the overburden would tend to equal the slope of the underlying bedrock in cases where
the saturated thickness is relatively small and the slope is large This process is analogous to flow
in a river where the water surface profile tends to reflect the slope of the river bed under steady-
state conditions In the southern Study Area the water table slope (ie horizontal hydraulic
gradient) is steep but less than the dip of the bedrock surface because the saturated thickness of
the overburden aquifer increases in the direction of flow The saturated thickness increase also
5797wpdocsglaquolluprifinlaquoltextmlaquogterrifiil061297 3-11 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
increases the transmissivity of the aquifer (and decreases the resistance to flow) thus causing the
horizontal hydtaulic gradient in the overburden to be less than the bedrock slope The
overburden becomes unsaturated north of PZ203 due to the continued increase of the bedrock
surface elevation in the direction of the Former Seepage Bed The wetlands and stream located a
few hundred feet west of the railroad tracks also affect flow directions and rates because they act
as discharge points for groundwater
Northern Study Area
Due to the increased saturated thickness north-northwest of the Former Primary Disposal Area
groundwater flow conditions in both shallow and deep sections of the aquifer are discussed The
top-of-till wells are considered to be most representative of horizontal flow conditions in all but
the shallow portion of the aquifer Primary reasons for the differences between shallow and deep
flow conditions include (1) the deep aquifer hydraulic conductivity northwest of the railroad
tracks is a factor of about 40 greater than the shallow hydraulic conductivity resulting in the
lower to middle portions of the aquifer controlling regional groundwater movement and (2)
rainwater infiltration and hydraulic influences of Mill Brook cause vertical flow to be important in
certain areas of the shallow aquifer The focus of this section is horizontal groundwater flow in
the middle to lower sections of the aquifer as characterized by Plate 3-8 Shallow flow
conditions (Plate 3-9) are discussed in Section 3323
In the northern portion of the Study Area three hydrogeologically distinct zones exist Between
the Former Primary Disposal Area and the Former Seepage Bed the hydraulic gradient is steep
(approximately 003 feet per foot between wells MW109S and MW110S) and is strongly
influenced by the dip of the bedrock surface (01 feet per foot) As shown on the insert on Plate
3-10 the saturated overburden thickness increases from zero south of well MW109 to about 20 to
30 feet near the former disposal areas North-northwest of the Former Primary Disposal Area the
hydraulic gradient lessens significantly to a range of 00003 to 00007 feet per foot between wells
MW105TT and MW102TT representing a factor of 40 to 100 reduction The most important
factors which produce the flatter gradients in this area are the more than order-of-magnitude
increase in hydraulic conductivity of the coarser-grained deposits and the substantial increase in
the saturated overburden thickness northwest of the railroad tracks North-northeast of Mill
Brook the hydraulic gradient is about 0007 feet per foot near wells MW117TT and MW118TT
Northwest of the railroad tracks groundwater flow in the middle to lower portions of the aquifer
converges from the northeast and southwest toward a centerline area generally defined in the
downgradient direction by wells MW105 and MW102 The flow direction near these wells is
generally to the northwest Northeast of this centerline groundwater flows in a southwesterly
5797wpdocsgalluprifinaltextmasterrifhl061297 3-12 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
^ ^ direction from the vicinity of Mill Brook and the former Pervel flock plant North of Mill Brook
and west of the railroad tracks the predominant groundwater flow direction becomes more
westerly As discussed in Section 42 and 52 these flow directions are very consistent with the
observed groundwater contaminant distribution
No significant seasonal changes in horizontal groundwater flow directions were observed in the
Study Area Figures 3-1 to 3-20 are groundwater elevation hydrographs for each well cluster in
the Study Area representing the period January 1995 to May 1997 (except for wells MW117
MW118 and MW119 which were not installed until November 1995) Groundwater levels were
high in January 1995 May 1996 and February 1997 and decreased by about two feet during July
1995 and August 1996 This variation is consistent with the fact that recharge rates become very
small during the summer months
3322 Bedrock Groundwater Flow
Groundwater flow within fractures in the top ten to 20 feet of the bedrock unit was evaluated
through the performance of the hydraulic conductivity (slug) tests and water level measurements
in monitoring wells A bedrock piezometric head map based on November 6 1995 water levels
is shown on Plate 3-11 along with inferred groundwater pathlines For the pathline development
it was assumed that the hydraulic conductivity distribution is isotropic because potential
influences of fracture orientation on flow direction have not been quantified As expected the
direction of the dip of the bedrock surface has a major influence on the horizontal hydraulic
gradient and flow direction However vertical flow from bedrock to overburden is also
important as discussed in Section 3323
South of the Former Seepage Bed groundwater in bedrock moves primarily in a westerly
direction while in the northern Study Area the predominant flow component is toward the
northwest In both areas the horizontal hydraulic gradient is on the order of 002 feet per foot
The steepest gradients (003 feet per foot) are found in the vicinity of the Former Seepage Bed
and the local high in the bedrock surface just east of MW111 The horizontal hydraulic gradient
reduces to about 001 feet per foot in the southern portion of the Study Area (near wells MW115
MW114 and MW112) and north-northwest of the former disposal areas Groundwater flow in
bedrock near the Former Seepage Bed is toward the northwest in the direction of wells MW113
and MW106 and exhibits no apparent influence from the locally increased fracturing identified
from the geophysical investigation and the hydraulic testing in well MW111B
5797wpdocsgalluprifinaltextm8tem fhl061297 3-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
3323 Vertical Flow
BedrockDeep Overburden Interface
Vertical groundwater flow is an important component in the upper several feet of the bedrock
unit This observation is supported by the water level hydrographs (Figure 3-1 to 3-20) and data
presented in Table 3-4 which summarizes the vertical hydraulic gradients between pairs of
monitoring wells in various well clusters across the Study Area Data characterizing the hydraulic
interaction between the bedrock and the lower portion of the overburden were evaluated for the
following well pairs MW102B-MW102TT MW105B - MW105T MW107B - MW107T
MW108B - MW108TT MW109B - MW109S MW112B - MW112T MW113B - MW113S and
MW1 15B - MW1 15TT For all measurement dates groundwater was found to be discharging
from bedrock into overburden at each location except for the January 1995 and February and May
1996 measurements at location MW109 At MW109 the saturated overburden thickness is less
than a few feet and MW109 is located at a much higher bedrock elevation relative to all other
locations at which upward vertical flow from bedrock was measured The vertical hydraulic
gradients between bedrock and top-of-till wells are generally more than a factor of ten greater
than the horizontal hydraulic gradients within the VOC plume downgradient from the Former
Primary Disposal Area
Overburden
In the overburden aquifer the vertical flow component is significant within shallow deposits in ~
the vicinity of the Former Primary Disposal Area and within the streambed sediments and the
upper portion of the aquifer near Mill Brook Plan view and cross-section maps were developed
to illustrate vertical piezometric head differences Plate 3-12 shows the November 6 1995
vertical piezometric head distribution and general groundwater flow directions along geologic
cross-section B-B Plate 3-13 is a plan view contour map of the shallow minus deep piezometric
head difference in the overburden aquifer As shown by the water level hydrographs the vertical
hydraulic gradients in the aquifer are relatively consistent throughout the observation period
Consistent downward hydraulic gradients have been observed at well clusters MW107 MW108
and MW116 Near the Former Primary Disposal Area water levels in MW107S were two to
three feet higher than the level in MW107TT resulting in a downward vertical hydraulic gradient
that is about a factor of 100 greater than the horizontal gradient from MW107TT to MW105TT
In addition shallow piezometric heads near MW108 and MW1 16 have ranged from 05 to 15
feet higher than heads in the lower portion of the aquifer This downward component at MW107
likely results from the low hydraulic conductivity of shallow soils near the well screen of
MW107S (factor of 200 less than underlying deposits refer to MW107S and MW107TT data in
Table 3-1) and drainage of surface water runoff from upslope areas into the depression formed by
excavation of the Former Primary Disposal Area The low hydraulic conductivity test result for
5797wpdocsgalluprifinlaquoltextmasteiTifhl06 1297 3-14 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW107S and the observed downward hydraulic gradient may be related to the increased silt
content of soils near well MW107S The vertical VOC distribution at location MW107 (shown
on Plate 3-12 and discussed in Section 4) also strongly supports a predominantly vertical
groundwater flow direction in the upper portion of the aquifer because only trace levels of VOC
were detected in MW107S The downward hydraulic gradients in the vicinity of wells MW108
and MW116 (Plate 3-13) also appear to be associated with the higher hydraulic conductivity of
deep deposits compared to shallow soils (Section 331) and groundwater recharge
West of the railroad tracks near well clusters MW102 MW101 and MW118 the measured flow
direction in the aquifer is predominantly horizontal based on the negligible vertical hydraulic
gradient between shallow and top-of-till wells at these locations However in the immediate
vicinity of Mill Brook vertical groundwater flow is important within the upper several feet of the
aquifer In the vicinity of wells MW103 MW117 and MW119 shallow piezometric heads are
generally 03 to one foot lower than deep heads Using a representative aquifer thickness of 50
feet the average upward vertical hydraulic gradient in this area is about 001 feet per foot by
comparison the local horizontal hydraulic gradient is approximately 0007 feet per foot Based
on these data a significant fraction of the shallow aquifer near wells MW103 MW117 and
MW119 may be discharging into Mill Brook Within the lower portion of the aquifer the
vertical hydraulic gradient becomes very small in magnitude
To further evaluate the hydraulic influence of Mill Brook on the overburden aquifer a vertical
two-dimensional numerical groundwater flow model was developed and a sensitivity analysis was
performed (Appendix U) The results of the modeling indicate that vertical flow in the upper
portion of the stratified drift aquifer near Mill Brook is more important west of the railroad tracks
(eg near wells MW101 and MW102) than east of the tracks (eg near well MW119) This
difference is due to the much smaller horizontal hydraulic gradients (on the order of 00003 feet
per foot) that are present west of the railroad tracks compared to ths area north of Mill Brook and
east of the railroad (horizontal gradients approximately 0007 feet per foot) Because the mean
water level in the brook is lower than the groundwater table elevation vertical flow is created in
the upper portion of the stratified drift aquifer and the depth to which this vertical flow is
important is greater in areas where the horizontal hydraulic gradient (and groundwater velocity is
less) In the vicinity of wells MW101 and MW102 the groundwater flow simulations indicate that
as much as one-third to one-half of the stratified drift aquifer may discharge into Mill Brook
East of the railroad tracks no greater than ten to 25 percent of the groundwater flow in the
stratified drift aquifer is estimated to discharge into the brook
East of the railroad tracks and south of Mill Brook a consistent downward groundwater flow component is observed in addition to the regional horizontal flow component As discussed
5797wpdocraquograquolluprifinaltextmaBterrifhl061297 3-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
above this downward component is largest near the Former Primary Disposal Area A small
downward flow component was also observed in the vicinity of wells MW106 and MW104
Figure 3-21 is a three-dimensional perspective drawing of groundwater movement in the
overburden aquifer which was developed to further illustrate the relative importance of the
horizontal and vertical flow components in the vicinity of the Former Primary Disposal Area
The figure consists of the two sets of piezometric head contours representing shallow and deep
(top-of-till) water level measurements recorded on February 2 1995 The lower piezometric
surface is representative of flow conditions throughout the middle to lower portions of the aquifer
The upper surface represents the piezometric head variation near the water table Presented
together in the same figure these two sets of contours allow an interpretation of the predominant
(but not all) three-dimensional pathlines originating in the vicinity of the Former Primary Disposal
Area As the pathlines illustrate shallow groundwater near these locations is expected to move
predominantly downward in the upper portion of the aquifer (although some local horizontal flow
may occur due to variations in the hydraulic conductivity of aquifer material) due to the large
vertical hydraulic gradients and the small aquifer thickness
Once groundwater has passed through the less permeable shallow soils it moves in a
predominantly horizontal direction dictated by the piezometric head distribution in the lower
portion of the aquifer
Based on the stream piezometer data presented in Table 3-5 Mill Brook generally gains water
from the overburden aquifer in the northern portion of the Study Area For most dates stream
bed flow was upward at piezometers PZ-6 PZ-5 PZ-4 PZ-4A and PZ-4B located west of the
railroad tracks and at piezometers PZ-1 and PZ-2 located east of the railroad tracks The
streambed vertical flow direction at piezometer PZ-3 located immediately upstream from a beaver
dam and possibly influenced by backwater effects was variable These data are consistent with
the shallow groundwater flow conditions depicted in Plate 3-9 where the head contours passing
through Mill Brook are bent (or V) in an upstream direction This piezometric head contour
pattern is representative of a gaining stream
Any groundwater discharge from the aquifer into Mill Brook would be significantly diluted by
flow in the brook A rough estimate of the potential surface water dilution rate can be obtained
by comparing the stream flow rate with the total discharge rate of groundwater through a given
vertical cross-sectional area For example using an upper bound hydraulic conductivity estimate
of 100 feet per day (0035 cms) a horizontal hydraulic gradient of 0001 feet per foot and an
area 200 feet wide (plume width) by 20 feet deep (about one-third of the aquifer thickness) a
conservatively high estimate of potential discharge from the contaminated portion of the aquifer
5797wpdocraquogalluprifinaltextmasterrifhl061297 3-16 Q^T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
into Mill Brook is approximately 0005 cubic feet per second or cfs (21 gpm) Based on a
measured stream flow rate of about 30 cfs at station UB10 the concentrations of dissolved
constituents in groundwater would be reduced by a factor of about 6000 upon mixing with the
entire stream flow
34 Ecology An ecological study was performed primarily to delineate wetlands and to make local observations
of the types and abundance of plants and animals in the area
341 Wetland Delineation
Delineation of wetlands within the Study Area and adjacent lands was conducted during the period
of August 26 to September 1 1994 Team members included two ESE wetlands biologists and a
certified soil scientist affiliated with the Soil Science Society of Southern New England As
discussed in Section 2131 the delineation performed to meet the States criteria focused on soil
types and hydric soil characteristics while the delineation performed to meet the Federal criteria
used USACOE methods which include the examination of vegetation hydrology and soils
As shown on Plate 3-14 wetlands were identified and delineated along the northern and western
portions of the Study Area Areas bordering the Site to the south and east reflect upland
conditions
Wetland delineation efforts were initiated along the face of a steep gradient along the southwestern
portion of the study area (west of the railroad grade) This allowed the field team to observe the
most obvious characteristics of both upland and wetland regimes Areas reflecting more subtle
wetlandupland indicators were investigated after having gained local experience with the obvious features
The wetland bordering the southwestern portion of the study area is a white cedar swamp
(unnamed) supporting a varying density of trees The swamp is hydraulically connected to the
Mill Brook system by a narrow stream The stream limits surface water flow causing the swamp
to maintain a long hydro period (duration of inundation or saturation) even though it is
topographically higher than the receiving floodplain It appears that the swamp remains inundated
during most years with the possible exception of drought years Judging from the high hydraulic
conductivity of the surrounding soils the swamp receives water through seepage from
surrounding uplands and to a lesser degree from surface water runoff
Portions of the swamp support a low density of older cedars while other areas support denser
stands of young cedars It appeared that the older age class occurred in deeper water while the
5797wpdocsgalluprifinraquoltextmasterrifhl061297 3-17 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
younger stands favored shallower water White cedar trees are not tolerant of fire events and it is r
likely that this age class distribution reflects a fire-maintained system where the deeper portions of
the swamp have been more effective in excluding natural fires hence supporting the oldest
cedars Additional hydrophytic plant species identified within the transition zone include red
maple common reed duckweed jewelweed cattail and coast pepper-bush
The upland system bordering the cedar swamp and floodplain forest supports a sub-climax to near
climax hardwood forest Topography of the upland includes steep slopes to gently undulating
land Canopy vegetation (trees) are dominated by oak species (red white and chestnut) with
white oaks nearer the wetland transition area and red and chestnut occurring on the higher
portions of the uplands Other canopy species included white ash quaking aspen hickories and
dogwoods Common understory vegetation included sheep laurel black cherry and green briar
Herbaceous vegetation included species found in the under story and canopy in addition to hay-
scented fern among others
Northward of the stream feature draining the cedar swamp lies the broad floodplain of Mill Brook which closely coincides with the northern boundary of the Site The floodplain is generally flat with many small raised hummocks This area reflects more seasonal fluctuations in hydro period and shallower water depths than the cedar swamp a result of more efficient drainage of the system For this reason natural succession is more advanced and the system supports a higher _ Jgth
diversity of hardwood canopy under story and herbaceous species composition
With the exception of two small isolated topographic depressions (excavated pits) located just west of the southern portion of the Site the delineated wetland areas correspond with the edge of the Mill Brook floodplain Most of the wetlandupland boundary occurs along the edge of a steep grade which closely coincides with the 150-foot ground elevation contour interval The sharp relief produces a narrow transition zone between upland and wetland communities The delineated lines reflect this as the State and USACOE wetland boundaries coincide at nearly
every location The State and USACOE lines are different in a small area adjacent to the railroad tracks immediately north of the Site In this area the State line is upgradient of the USACOE line The soils above the floodplain do not exhibit hydric soil characteristics as defined in the federal manual used for delineating wetlands The soil appears well-drained and depth to water is at a lower elevation than the floodplain soil just a few feet away The soil resembles the description of Suncook an excessively drained soil commonly mapped with Rippowam soils Both Rippowam and Suncook soils are listed on the State hydric soils list while Suncook is not listed by SCS as a hydric soil
5797wpdocsgalluprifinaltextmasterrifhl061297 3-18 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
A relatively small area of wetlands were determined to occur within the boundaries of the Site proper Wetlands occur in the area northeast (upgradient) of the Former Primary and Secondary
Disposal Areas and along the northern border of the Site east of the railroad bed The two topographic depressions corresponding to the former disposal areas (primary and secondary) lack
hydrophytic vegetation and hydric soil characteristics Other excavated areas to the south and
southwest (on-site) support hydrophytic vegetation and meet hydrology criteria but lack hydric
soil characteristics The depression to the southwest bordering the railroad supports hydrophytic vegetation and is occasionally inundated with surface water (following significant precipitation
events) but lacks hydric soil indicators In this area the ponded water was judged to be the
result of a confining layer of residual tar (presumed to be associated with former CTDOT asphalt
plant operations) immediately beneath an organic layer which causes precipitation to accumulate
342 Plant and Animal Survey
Site Characterization
An objective investigation of native plant and animal species and their habitat was conducted by US Fish and Wildlife Service (USFWS) staff in summer of 1993 (Prior et al 1995) Their
examination included a Site walkover observation and mapping of vegetation cover (shrubs
trees hydrophytic plants) and observation of direct or indirect evidence of wildlife (birds mammals amphibians) Although the Site proper is characterized as highly disturbed no
conclusions were drawn with regard to the effects of past human disturbance on the local ecology
The large majority of plant and animal species observed in the study are native to the region and
commonly found in other disturbed communities andor wetland environs
Reconnaissance of the study Site and adjacent lands was performed prior to delineation activities
to identify habitat types terrain physical access and develop logistics for completing the wetland
delineation The study area is a peninsular feature which extends northward and westward from
the Site entrance at Tarbox Road The study area is bisected diagonally by the railroad right-ofshy
way The Gallup Quarry Site (the quarry) lies to the east of the railroad divide and the remainder
of the study area (the west end) lies to the west Portions of the east boundary of the quarry abut
State Route 12 with other areas bounded by private property
The boundaries of the peninsula are characterized generally by steep slopes which are met
immediately by wetlands The upland soils are glacial till with some areas composed mostly of sands with coarse gravel occurring with lower frequency Some of the higher and relatively
undisturbed areas are composed of large rocks protruding to the ground surface Soils in the
transition zones between upland and wetland are composed of organic muck overlying sand
5797wpdoc8gilluprifinaltextmalaquoterriftil061297 3-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
These natural conditions along with historical use of portions of the area (mining and
manufacturing) cre responsible for the character of the plant communities found throughout the
study area The quarry reflects significant disturbance from historical mining and asphalt
operations The Site has numerous excavated depressional areas and areas of mounded earth
material These features significantly distinguish the quarried area from the area off-site to the
west which is undeveloped and relatively undisturbed The assemblage of plants in the quarry
reflects these conditions many of the excavated zones are devoid of vegetation and areas adjacent
to them support a mix of successional pioneer species Density of vegetation ranges from bare
soil to dense brush and sapling sized trees Areas of highest vegetation density are associated
with both low elevation (greatest soil moisture regime) and age (length of time since disturbance)
Trees throughout the quarry are young and small in comparison with those found in the forested
areas west of the railroad Vegetation on-site is characterized as early successional species The
more common species include black willow northern bayberry eastern cotton-wood quaking
aspen goldenrod and black cherry
Few wildlife species were observed or noted during wetland delineation activities Wildlife
activity within the Study Area was limited during the survey period but should be expected to
support a much greater diversity of wildlife during the spring and summer seasons when birds
(especially migratory) conduct nesting and rearing activities Most of the species observed during
the survey are expected to overwinter at the study area Bird species recorded include mourning
dove eastern peewee tufted titmouse black-capped chickadee blue jay white-breasted nuthatch
gray catbird American robin and northern cardinal
Vegetation species were recorded during the wetland delineation and are presented in Table 3-6
These reflect species occurring within wetland transition zones Additional species are expected
to occur in more xeric uplands and deeper wetlands
Although no qualitative samples of freshwater macroinvertebrates were obtained the distribution
of different genera between stations would appear to be strongly influenced by the variable
substrate composition and habitat which ranges from shaded moderate flowing rocky stream bed
(eg UB1 UB9) to sunny low energy depositional areas containing sand or deep muck (eg
UBS LB2)
5797wpdocsgalluprifinaltextmasterrifnl061297 3-20 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
40 Nature and Extent of Contamination
This section discusses the distribution of contaminants within the various media throughout the
Study Area and is based on analytical data collected during nine separate sampling events These nine sampling events include the Phase 1A investigation the Phase IB investigation and the Long-
Term Monitoring Program events conducted during April July November 1995 February May
August and November 1996 and February 1997) The results of the Phase 1A investigation
Phase IB investigation and the Long-Term Monitoring Program sampling events (except
November 1995 which was conducted concurrently with the Phase IB investigation) were also
presented in earlier reports (ESE 1995 -1995b -1995c 1996a 1996b 1996c 1997a 1997b)
Section 41 addresses the results of investigations into potential source areas including surface and subsurface soil Section 42 addresses the results of groundwater investigations Section 43
presents the results of investigations of surface water sediments and wetland soils Section 44 addresses the results of air monitoring investigations Section 45 identifies potential sensitive
human receptors within a one mile radius of the Site
Sample analyses were performed pursuant to the Gallups Quarry Superfund Project RIFS Quality Assurance Project Plan dated August 29 1994 Laboratory analytical testing for Level 4
was generally conducted for analytes identified in the Contract Laboratory Program (CLP) target
compound list (TCL) for organics and target analyte list (TAL) for inorganics Analyses were
conducted pursuant to the CLP Statement of Work for Organics MultimediaMulticoncentrations
Document OLM 018 and the CLP Statement of Work for Inorganics
MultimediaMulticoncentrations Document ILM 030 Appendix IX analyses were conducted by
CLP and SW-846 Methods as described in the QAPP Low-level VOC in drinking water were analyzed by EPA Method 5242 with CLP SOW reporting Laboratory reports for the Phase 1A
Phase IB and Long-Term Monitoring Program sampling events are presented in Appendices H
through P Laboratory data for sample splits collected by EPAs oversight contractor during the
Phase 1A July 1995 and Phase IBNovember 1995 sampling events are also presented in
Appendices H J and K respectively The results of detected analytes are summarized in Section 4 tables The definitions of the qualifiers used for the laboratory data precede the tables in
Section 4 As discussed in various sections analyte concentrations are given either as milligramskilogram (mgkg) or microgramsliter (ugL) The units mgkg are also used
interchangeably with the term part per million (ppm) The units ugL are equivalent to parts per
billion (ppb)
Data validation was performed on all Level 4 data according to the requirements of EPA Region
I Laboratory Data Validation Functional Guidelines for Evaluating Organic Analyses (February 1
5797wpdoclaquogilluprifinaltextmlaquo8terrifiJ061297 4-1 QZT Environmental
Gallups Quarry Superjund Project - Remedial Investigation
1988 as modified November 1 1988) and Inorganic Analyses (June 13 1988 as modified
February 1989) Data validation was performed by David MacLean an independent data
validator Summaries of Mr MacLeans data validation results are presented in Appendix Q
41 Contaminant Source Investigation 411 Visual Site Reconnaissance
A comprehensive visual site reconnaissance was conducted over a three week period from August
23 until September 13 1994 to determine the potential presence of unknown disposal areas
Prior to the start of this survey a grid system was established to allow systematic coverage of the
Site and to locate features of interest The grid used to conduct the visual Site reconnaissance is
described in Section 21 A Site plan which includes the survey grid and the features described
below is shown on Plate 4-1 The features identified on Plate 4-1 are also summarized in Table 4-1
Based on this visual survey the ground surface in the northern portion of the Site which includes the Former Primary and Secondary Disposal Areas is covered with sand and gravel with sparse
to no vegetation Topographic relief is estimated to be as much as 20 to 30 feet and is attributed
to the Sites past usage as a sand and gravel quarry Many of the topographic low spots were
observed to contain either standing water (following rain events) or moist soil (indicative of
intermittent periods of ponded water)
The central portion of the Site which contains the Former Seepage Bed is presently heavily
vegetated Crushed stone and boulders are evident over a large portion of this area and the soils
consist mainly of a sandy till Immediately east and northeast of the Former Seepage Bed is a
topographic high with numerous boulders at the ground surface Evidence of previous test pit
explorations were also observed in this general vicinity Asphalt and mounds of asphalt pavement
were also observed in several areas and are presumed to be remanent of the State of Connecticut
Department of Transportation (CTDOT) asphalt plant operations discussed in Section 132
The southern portion of the Site contains the entrance to the former CTDOT asphalt plant as well
as the remains of the former plant itself These remains consist primarily of concrete footings
and retaining walls The remains of the asphalt plant are located along trending lines E through
K approximately 800 to 900 feet north of Tarbox Road The remains of a 6-foot diameter brick
and concrete masonry structure were observed along with an 8-inch diameter clay pipe leading
into the ground at the former plant location
The area located in the southwestern portion of the Site along line A includes mounded earthen
material piled along the western perimeter of the Site Scattered metal debris including several
5797wpdocsgalluprifinaltextmasterrifiil061297 4-2 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
empty rusted drums were observed adjacent to and partially buried within the mounded materials
Other objects consisting of timbers steel culvert tires and mounded asphalt were also observed
along the A line Mounded earthen materials located on lines M and N (400 to 650 feet north of
Tarbox Road) were observed to also contain miscellaneous debris (corrugated steel culvert hoses
and cables tires etc) and several empty rusted drums These areas are presently heavily
vegetated Other areas at the southern portion of the Site consist of a mixture of grassland and
brush There are numerous mounds of earthen material and scattered patches of asphalt and
pavement remanent of CTDOT operations throughout this portion of the Site
The Bionetics Corporations under contract to USEPA performed a review of historic aerial
photographs of the site and issued a Site Analysis Report (Bionetics Corp 1990) The historical
aerial photographs were used to prepare a Site plan which indicated the locations of suspected or
potential disposal areas (Figure 4-10 from the Phase 1A Work Plan (ESE 1994)) That Site plan
showed the locations of the three known former disposal areas as well as several much smaller
features described below Based on the visual reconnaissance performed during the RI areas
described in the Bionetics Report as either stained or wet or standing liquid or wet ground
correspond to topographic low spots in which ponded rainwater has been observed In addition
no visual evidence indicative of disposal activities was observed in the vicinity of the several
pits (dated 1981 through 1988) identified in the Bionetics Report These pits are believed to
be remnant of previous investigation test pits
An area described in the Bionetics Report as an extraction and an area of disturbed ground
northwest of the Former Seepage Bed correspond to an excavated area in which asphalt and
miscellaneous debris were observed during the Site reconnaissance The presence of mounded
materials in the vicinity of the Former Seepage Bed was confirmed during this visual
reconnaissance The mounded materials observed are comprised of earthen materials andor
asphalt pavement
A number of areas located within the southern portion of the Site were described in the Bionetics
Report as suspected disposal areas Features described as containing liquid generally
correspond to topographic low spots which were observed during the Site reconnaissance to
contain ponded rainwater following rain events The large feature described in the Bionetics
Report as extraction with liquid and associated dark toned material corresponds to a presently
open excavation in which asphalt was observed No features or specific objects were observed
during the Site reconnaissance which correspond to the locations of the unidentified objects
noted in the report The remains of a circular foundation observed during the Site reconnaissance
in the vicinity of the former CTDOT plant corresponds to the location of the possible vertical
5797wpdocraquogalluprifiiwltextmasterrifhl061297 4-3 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
tank Scattered mounds of earthen materials observed throughout the southern portion of the
Site correspond to the numerous mounded materials identified in the Report
Based on the observations made during this survey it is apparent that the landforms on-site have
been altered numerous times during past usage Extensive areas are presently heavily overgrown
and do not appear stressed Various earthen materials have been excavated and mounded at
numerous locations throughout the property and are presumed to be remnant of the former sand
and gravel quarrying operation andor the operation of the State DOT asphalt plant Also
patches of asphalt and mounds of asphalt pavement ranging from several to tens of square feet in
size were observed at multiple areas around the Site
The major features described as potential or suspected disposal areas in the Bionetics Report were
identified and described during the visual reconnaissance Although several empty 55 gallon
drums in various states of decomposition and scattered debris (consisting mainly of residential
trash scrap metal car parts etc) were observed at a number of locations across the Site no
intact drums or significantly stained or stressed areas were observed Other than the three known
former disposal areas no features were observed during the visual reconnaissance which indicate
the potential presence of large disposal or dumping areas
The above mentioned areas which contain debris including several empty 55-gallon drums were
further assessed during the soil gas and geophysical screening surveys performed as part of the
Phase 1A investigation The findings of these screening surveys are discussed below
412 Soil Vapor Survey
The soil vapor survey conducted on-site included a total of 100 soil vapor points installed along
an approximate 100-foot orthogonal grid Six additional sampling points were installed at three
locations where partially buried decomposed or empty 55-gallon drums were observed during
the visual site reconnaissance and at three areas where geophysical surveys detected the presence
of EM-31 andor MAG anomalies Each soil gas sample was analyzed for the presence of the
following eight VOC using a portable gas chromatograph acetone benzene 12-dichloroethene
(DCE) methylethyl ketone (MEK) methyl-isobutyl ketone (MIBK) 111-trichloroethane (TCA)
trichloroethene (TCE) and toluene
Of the 106 soil vapor sampling points tested detectable concentrations of VOC were identified at
only three locations These three locations SV160 SV165 and SV172 (shown on Plate 2-5)
were all located within approximately 50 feet of the Former Primary Disposal Area Specifically
TCE was detected at SV160 and SV165 and TCA was detected at SV165 and SV172
5797wpdocsgalluprifinaltextmasterrifhl061297 4-4 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
Likewise no VOC were detected at three additional survey points SV201 SV205 and SV206
installed within one foot of the 55-gallon drum which was observed at each of those locations or
at survey points SV202 SV203 and SV204 located in the vicinity of geophysical anomalies
identified during the EM-31 and MAG surveys
As described in the Work Plan the soil gas investigation was used as a screening survey to
identify apparent soil contamination in an effort to locate any potential unknown disposal areas
Based on the results of the soil gas survey no additional potential disposal areas were identified
413 Geophysical Investigations and Test Pits
Electromagnetic terrain conductivity (EM-31) and magnetometer surveys were conducted by
Weston Geophysical of Northboro Massachusetts as screening surveys to identify potential
unknown disposal areas The Weston Geophysical Report (provided as Appendix A) describes
in detail the findings of the geophysical investigations The significant findings of these two
screening surveys and of the follow-up test pit program are discussed below
4131 EM-31 Survey
The electromagnetic terrain conductivity measured across the Site was generally uniform with
most anomalies being attributed to wholly exposed or partially buried metallic debris (eg
automobile body parts empty rusted drums scrap pipe angle iron steel culvert and steel cable)
However two EM-31 anomalies could not be accounted for by noted surface features As shown
on Plate 2-14 the two unexplained EM-31 anomalies were located along trend line M at station
550 and at station 590 Due to the complexity of the anomaly located at station 550 an estimate
of its ferrous mass could not be made The second EM-31 anomaly was described as limited in
extent and was estimated to contain approximately 100 pounds of ferrous material assuming a burial depth of five feet (smaller objects at shallower depths would also explain the anomaly)
4132 Magnetometer Survey
The magnetometer survey identified a relatively flat gradient across the Site with a number of
localized anomalies most of which corresponded directly with visible surface features or objects
(as described above) A total of four anomalies were identified which could not be readily
attributed to known surface features Two of these anomalies occurred along trend line M and
correspond to the two EM-31 anomalies described above A third magnetometer anomaly was
identified along trend line C between stations 760 and 800 This anomaly was described as
approximately 10 feet in width and was interpreted as being the result of small amounts of ferrous
material spread over the length of the anomaly (approximately 40 feet) A fourth anomaly was
identified along line L at station 315 This anomaly was interpreted to consist of a small
amount of ferrous material buried at shallow depth
5797wpdocsgalluprifinaltextmraquosterrifhl061297 4-5 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4133 Test Pit Investigations
As described above the geophysical screening surveys revealed a total of four locations at which
EM-31 or magnetometer (or both) anomalies were detected that could not be attributed to visible
surface features The anomalies measured along line M were noted in both the EM-31 and
magnetometer surveys while the anomalies along lines C and L were only measured in the
magnetometer survey To confirm the source of these anomalies test pits were excavated at the
location of each anomaly Test pit excavation was observed by EPA oversight personnel
The presence of varying amounts of miscellaneous buried scrap metal debris described below
was identified at each test pit location At the anomaly located along Line C the excavated
debris included small rusted cans sheet metal and steel cable During the excavation of the test
pit located at the anomaly along line L a three foot long piece of a solid iron rod
approximately one inch in diameter was found buried approximately four inches below the ground
surface At the anomalies located along Line M a variety of ferrous debris was uncovered
including a crushed eight foot section of corrugated steel culvert approximately 2 feet in
diameter sheet metal nuts bolts steel cable and small rusted cans No drums intact or
otherwise were encountered at any location Soil removed from each excavation as well as the
side walls and bottoms of the excavations were screened for the presence of VOC using a PID
No elevated PID readings were measured Furthermore no visible evidence of staining was
noted in the soil at any of the excavations Upon excavation all metallic debris was placed on
the ground surface adjacent to the excavation and the test pits were backfilled with native soil
Test pit logs for the four test pits are shown in Appendix E
414 Background Soils
Soil samples were collected at two monitoring well cluster locations MW109 and MW112 to
determine the general Site background levels of TALTCL compounds The two locations were
chosen based on their upgradient position in relation to the former disposal areas The soils were
submitted for laboratory analysis for TALTCL parameters (VOC SVOC pesticides PCS
metals and cyanide) Tables 4-2 and 4-3 show the positive detections for VOC and metals
These tables only show the constituents that were detected at the site Constituents that were not
detected in any sample are not shown There were no detections of SVOC or pesticidesPCB in
any background soil sample
Due to the limited surficial deposits and abundance of boulders encountered at the MW109
location samples could only be collected from the 6-8 foot interval which is representative of till
at this location Discrete samples collected at the MW112 location were obtained from the 8-10
foot and 40-42 foot intervals which represent stratified drift and till respectively Composite
5797wpdocsglluprifinlaquoltextmlaquosterrifhl061297 4-6 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
samples from MW112 were collected from the 7-14 foot and 34-40 foot intervals (stratified drift
and till respectively) These depths were chosen based on their lithology
The results of the laboratory analyses for the soils collected at MW109 indicate the presence of
trace concentrations (0004 mgkg) of toluene no other VOC were detected No detectable
concentrations of SVOC pesticides or PCB were encountered in soil from the MW109 sample
location
Soils collected at the MW112 location also contained detectable concentrations of toluene
Toluene was detected at concentrations of 003 0017 0029 and 0032 mgkg from 8-10 feet 7shy
14 feet 10-14 feet and 34-40 feet respectively Trace concentrations of methylene chloride
(0003 mgkg) and trichloroethene (0002 mgkg) were also detected in the MW112 sample at 10shy
14 feet and 40-42 feet respectively No detectable concentrations of SVOC pesticides or PCB
were identified at the MW112 location
Although the source of the VOC is unknown all three of these compounds are organic solvents
that are (or were ) commonly used in many household (eg spot removers paint strippers
aerosols) commercial (eg pesticide formulations inks and dyes) and industrial (eg
degreasers) products
Metals concentrations in background soil boring samples are shown on Table 4-3 As expected
various metals were detected in all soil samples Analytical results for metals for all of the
MW112 samples were within the common range for soils found in the eastern United States
Heavy metals were generally detected only at trace concentrations Alkaline earth metals (eg
Ca Mg K) were detected at levels not unexpected for soils in the region Background concentrations of metals in subsurface soils were used for comparison purposes in analyzing the
significance of the metals concentrations measured in other non-background soil samples
415 Soils From Former Known Disposal Areas
Soil borings were drilled at each former known disposal area to determine whether residual
contamination remains in surface and subsurface soils During the Phase 1A investigation a total
of ten soil borings were performed Soil samples were collected from these borings and
submitted for laboratory analysis for TALTCL parameters (VOC SVOC pesticides PCB
metals) pH total organic carbon (TOC) and moisture content An additional six borings were
performed during the Phase IB Investigation Soil samples collected during the Phase IB
Investigation were submitted for laboratory analysis for VOC and pesticidesPCBs The
locations of the soil borings are shown on Plate 2-3
5797wpdoc8galluprifinaltextma8terrifhl061297 4-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Samples from the 0-1 foot interval were collected from each boring by hand using a stainless
steel scoop Continuous soil samples beneath the 0-1 foot interval were collected using a truck-
mounted drill rig equipped with standard split-spoon samplers Generally samples were collected
from both above and below the water table and at depth within each of the former known
disposal areas In addition each significant lithologic unit was sampled The specific sampling
depths and length cf sampling interval varied for different analytical parameters depending on the
lithology and volume of sample recovered from each spoon Sample intervals and analytes are
summarized in Table 2-2
A brief description of the reported historical disposal activities and the findings of the Soil
Sampling Program for each specific area are described below Positive hit tables showing the
laboratory results for soil boring samples collected from within the former known disposal areas
are presented in Tables 4-4 through 4-7 The unvalidated laboratory data for TALTCL
parameters are presented in Appendix H (Phase 1A data) and K (Phase IB data) Laboratory
results for pH total organic carbon and moisture content are presented in Appendix R
4151 Former Seepage Bed
The Former Seepage Bed is located near the center of the Site This feature is located on the
north side of a local bedrock high which is overlain by 10 to 20 feet of boundary till Historical
records indicate that this area was used for the direct discharge of liquid waste to the ground
surface It has been reported that an inverted dump truck body was buried in this area and was
connected to the ground surface via a pipe Liquid wastes were then reportedly poured directly
into the pipe The wastes reportedly dumped in this area have been described as low pH liquids
characteristic of metal pickling liquors The dump truck body and the contaminated earth were
removed in 1979 during CTDEP remedial efforts Approximately 20 tons of lime (which is
approximately equal to 10 cubic yards) was reportedly spread in the vicinity of the seepage bed to
neutralize any residual low pH material The soil boring program indicated that fill material in
this area extends from 3 to 7 feet below the ground surface Based on the approximate lateral
extent of this former disposal feature (as shown in historic plans of the Site) approximately 230
yards of sand and gravel fill material were used to backfill the CTDEP excavation
To investigate this area three soil borings (SB101 SB102 and SB103) were completed The
borings within the Former Seepage Bed were terminated at auger refusal depths of 68 feet
(SB101) 185 feet (SB102) and 160 feet (SB103) Within this area groundwater was only
encountered in the bottom 6 inches of the deepest boring (SB 102)
5797wpdocsgalluprifinaltextmasteiTifnl061297 4-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Surface Soil Sample Results - Former Seepage Bed
As shown in Table 2-2 the 0-1 foot interval was sampled at each location and submitted for
laboratory analysis for VOC SVOC pesticides PCB and metals No VOC were detected in this
interval at any of the three soil borings within the Former Seepage Bed In the 0-1 foot interval
very low levels of SVOC primarily polynuclear aromatic hydrocarbons (PAH) were detected at
SB101 and SB103 The concentrations of PAH ranged from 0012 ppm to 0076 ppm Moderate
concentrations of bis(2-ethylhexyl)phthlate (15 ppm) were also seen in this interval at SB101
Trace levels of certain pesticides were also seen in the 0-1 foot interval at SB101 [44-DDE
(00014 ppm) 44-DDT (0019 ppm) and 44-DDD (0041 ppm)] and at SB102 [44-DDD
(0011 ppm)] At SB102 a low level of PCB (Aroclor-1260 at 0027 ppm) was detected in the
surface soil sample
The results of metals analyses have been compared to background soils metal concentrations
determined from soil samples collected from the background monitoring wells MW109 and
MW112 With the exception of calcium (12200 ppm) and magnesium (9620 ppm) seen in the
0-1 foot interval at SB102 most metals in the surface soil samples were close to the background
concentrations seen at the Site The elevated concentrations of both calcium and magnesium are
attributed to the 20 tons of lime which were used in this area by CTDEP Compared to the
background level seen for lead (35 ppm) the concentration of this metal in the 0-1 foot interval
was slightly higher at SB101 (59 ppm) SB102 (43 ppm) and SB103 (69 ppm) Also silver
which was not seen in any of the background samples was detected in the 0-1 foot interval at
SB101 at 87 ppm
Unsaturated Zone Sampling Results - Former Seepage Bed
Within the unsaturated zone below the 0-1 foot interval described above only trace levels of
VOC were detected Toluene was seen in SB101 (4-6 feet) and SB102 (16-18 feet) at a
concentration of 0002 ppm Xylene (total) was also detected at the same two intervals at the
same concentrations The only other VOC detected was TCE in SB101 (4-6 feet) at a
concentration of 0004 ppm
The only SVOC detected within the unsaturated zone at the Former Seepage Bed was di-n-octyl
phthlate detected in all three borings at various depths at concentrations ranging from 001 to
0021 ppm Very low concentrations of several pesticides (SB101) and PCB (SB101 and SB102)
were detected at various depths in unsaturated zone samples below the 0-1 foot interval The
pesticides 44-DDD (0033 ppm) 44-DDT (0024 ppm) and dieldrin (000064 ppm) were
5797wpdocBgalluprifinaltextmlaquosteiTifhl061297 4-9 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
detected at SB 101 The highest detections of the PCS for Aroclor-1260 and Aroclor-1254 were
0027 (SB102 0-1 feet) and 0034 ppm (SB1012-5 feet) respectively
Within the unsaturated zone below the 0-1 foot interval the only metals detected above the
highest background concentrations were aluminum barium iron magnesium manganese and
potassium The highest concentration of each of these metals was only slightly higher than
background levels and all were within the same order of magnitude
Among the Former Seepage Bed borings only one (SB 102) encountered groundwater above the
auger refusal depth Since only six inches of saturated soil was encountered the limited sample
volume was submitted for VOC analysis only No VOC were detected in this sample
pH TOC Moisture Content - Former Seepage Bed
The pH of samples collected in this area ranged from 622 to 792 Total organic carbon values
(mgkg) ranged from 1600 to 23000 Moisture contents ranged from 42 to 105 percent
4152 Former Secondary Disposal Area
The Former Secondary Disposal Area is located in the northwestern corner of the Site adjacent to
the railroad tracks The Disposal Area is presently seen as a depression which is approximately
50 feet wide by 60 feet long and is approximately 6 to 8 feet below the surrounding ground
surface The ground surface at this area is covered by approximately 2 feet of backfill (mostly
sand) material The fill is underlain by fine- to coarse-grained sand which ranges in thickness
from approximately 6 to 22 feet Sandy till ranging in thickness from 10 to 20 feet underlies the
sand The depth to groundwater from the bottom of the depression is approximately 10 feet
Historical records indicate that this area was used for the disposal of drummed liquid wastes
Approximately 200 drums and an unknown quantity of contaminated soil were removed in 1979
during CTDEP remediation efforts
In order to characterize residual contamination which may be present beneath this area three soil
borings (SB 104 SB 105 and SB 106) were performed within the depressed area ranging in depth
from 30 feet (SB 105) to 36 feet (SB 104) Within this area groundwater was encountered at
approximately 10 feet below the ground surface
5797wpdocsglaquolluprifinlaquoltextmaBterrifnl061297 4-10 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Surface Soil Sample Results - Former Secondary Disposal Area
Within the 0-1 foot interval only a trace concentration of one VOC (ethyl benzene at 00006
ppm) was detected (at SB104) The only SVOC detected in this interval was butylbenzylphthlate
(014 ppm) at SB 104 Very low concentrations of pesticidesPCB were measured at each boring
Aroclor-1254 was detected at SB104 (0025 ppm) and SB105 (0021 ppm) Aroclor-1260 was
detected at all three borings ranging in concentration from 00089 to 0031 ppm Dieldrin was
detected at SB 104 at trace levels (000048 ppm)
In the 0-1 foot interval nearly every metal detected occurred at concentrations close to those for
the background samples with the exception of lead which was detected at a concentration of 118
ppm at SB 104 Cyanide was detected in this interval at very low concentrations ranging from 16
to 97 ppm
Unsaturated Zone Sample Results - Former Secondary Disposal Area
Between the 0-1 foot interval and the groundwater table at the Former Secondary Disposal Area
no VOC were detected The only SVOC detected in this zone were at very low levels
(butylbenzylphthlate at 0037 ppm and di-n-octylphthlate at 0012 to 0029 ppm) Also in this
interval at SB104 and SB105 low levels of the PCB Aroclor-1254 and -1260 were detected at
concentrations up to 0055 ppm and 0018 ppm respectively Dieldrin was detected at a trace
level (00014 ppm) at SB104 Within this zone most of the metals were close to the background
soil concentrations except for lead (224 ppm) at SB104 and copper (476 ppm) at SB105
Cyanide was detected in the 1-10 foot interval at SB104 and SB105 at very low concentrations of
83 and 31 ppm respectively
Saturated Zone Sample Results - Former Secondary Disposal Area
Beneath the groundwater table within the Former Secondary Disposal Area no VOC were
detected The only SVOC detected was di-n-octylphthalate which ranged in concentration from
002 to 008 ppm Very low levels of endrin (00004 ppm) and Aroclor-1248 (001 ppm) were
also detected just below the water table but were not present in the deepest sample collected (26shy
28 feet) The only metals which were detected below the water table at concentrations notably
higher than background levels were copper and nickel Copper ranged in concentration from 621
to 863 ppm while nickel ranged from 119 to 169 ppm The highest concentrations of these
two metals were detected just below the groundwater table
5797wpdocsgalluprifinaltextmasterrifhl061297 4-11 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
pH TOC Moisture Content - Former Secondary Disposal Area
The soil pH ranged from 688 to 751 TOC ranged from lt 1500 to 2800 mgkg and moisture
content ranged from 37 to 124 percent
4153 Former Primary Disposal Area
The Former Primary Disposal Area is located at the northern end of the Site approximately 150 feet east of the Former Secondary Disposal Area This feature is seen as a circular depression
approximately 130 feet in diameter (at the top edge) and is approximately 8 to 10 feet lower than
the surrounding ground surface Non-native fill material (sand and gravel) ranged in thickness
from approximately 2 to 4 feet Underlying the fill is an approximately 15- to 20- foot thick
generally sandy horizon which overlies 6 to 15 feet of till The water table in this area ranges
from approximately 3 to 6 feet beneath the ground surface in the bottom of the depression
Records indicate that approximately 1400 drums and approximately 5000 gallons of free liquids
were removed from the Former Primary Disposal Area during CTDEP cleanup efforts
Approximately 2000 to 3000 cubic yards of contaminated soil were also removed during that
effort
During the Phase 1A (1994) investigation a total of four soil borings (SB107-SB110) were
completed within the Former Primary Disposal Area to characterize the extent of residual soil
contamination These borings ranged in depth from 24 feet at SB108 to 39 feet at SB109 An
additional six borings (SB111-SB116) were completed during the Phase IB (1995) investigation
Samples collected during the Phase IB investigation were submitted for laboratory analysis for
VOC and PCBPesticides The purpose of the additional borings was to further delineate the
lateral extent of residual VOC and PCB contamination in the unsaturated portion of the soil The
Phase IB borings were terminated just below the groundwater surface typically five to seven feet
below the ground surface The locations of all of the borings are shown on Plate 2-5 however a
detailed close-up showing the boring locations within the Former Primary Disposal Area is shown
as an insert on Plates 4-2 and 4-3 which are discussed below The tabulated laboratory data for
both the Phase 1A and Phase IB soil borings are shown on Tables 4-4 through 4-7 (VOC SVOC
pesticidesPCB and metals respectively)
Surface Soil Sample Results - Former Primary Disposal Area
In the 0-1 foot interval only a limited number of VOC were detected generally at very low
concentrations (Table 4-4) The compounds detected in the 0-1 foot interval (followed by
concentration [ppm] and location) are as follows acetone (0007 ppm at SB107)
5797wpdocsgalluprifinaltextmasterri fhl061297 4-12 QST Environmental
Catlaps Quarry Superfund Project - Remedial Investigation
tetrachloroethene (PCE) (0018 ppm at SB109 and 0002 at SB113) toluene (0005 at SB112
0003 at SB1H and 0002 at SB115) ethyl benzene (0002 at SB113) and total xylenes (0010 at
SB113) In this same interval several phthalates (butylbenzyl bis(2-ethylhexyl) diethyl and dishy
n-octyl) were detected at various locations (Table 4-5) with no apparent spatial trend at
concentrations ranging from 0008 to 17 ppm Several PAH compounds were also detected at
SB110 in the 0-1 foot interval at concentrations ranging from 0007 to 0017 ppm As shown in
Table 4-6 Aroclor 1254 was detected in the 0-1 foot interval at every boring at concentrations
ranging from 0046 to 43 ppm Aroclor-1260 was also detected in the 0-1 foot interval at
concentrations ranging from 0046 to 23 ppm Trace concentrations of several pesticides were
also detected in the 0-1 foot interval in some borings as follows heptachlor epoxide (000058 to
0052 ppm) dieldrin (000059 to 0043 ppm) 44-DDE (000089 to 0081 ppm) and 44-DDT
(000048 to 0027 ppm) Aluminum (12200 ppm at SB110) was the only metal in the 0-1 foot
interval that was detected at concentrations significantly greater than background levels (Table 4shy
7) Cyanide was detected at a very low concentration of 16 ppm at both SB109 and SB110
Unsaturated Zone Soil Sample Results - Former Primary Disposal Area
Beneath the 0-1 foot interval but above the water table a small number of VOC were detected at
various concentrations and locations (Table 4-4) Within this zone no VOC were detected at
SB107 At SB108 methylene chloride was detected at 0001 ppm Ethyl benzene was detected
at SB 109 (015 ppm) SB110 (54 ppm) SB111 (0048 ppm) and SB115 (16 ppm) Total
xylenes were seen at SB109 (16 ppm) SB110 (46 ppm) SB111 (064 ppm) and SB115 (80
ppm) Toluene was detected at SB 110 through SB 115 at concentrations ranging from 0003 to 12
ppm PCE was seen at SB109 SB111 SB114 and SB116 at concentrations which ranged from
0003 to 17 ppm and at SB115 at 28 ppm 111-TCA was detected at SB111 112 114 115
and 116 from 0001 to 14 ppm TCE was also seen at SB111 114 115 and 116 at
concentrations ranging from 0002 to 17 ppm 2-butanone (MEK) was detected at SB111 at
0005 ppm 12-DCE was seen at both SB115 (016 ppm) and SB116 (0009 ppm) Finally 11shy
DCA (0008 ppm) 11 -DCE (0009 ppm) and carbon disulfide (0022 ppm) were all seen at
SB115 Methylene chloride (0001 ppm) was detected at SB108 These detections occurred in
the transition zone between fill and native deposits
The SVOC detected in this zone (shown on Table 4-5) included several phthalates at
concentrations ranging from 0039 to 46 ppm Napthalene was also detected at SB109 (047
ppm) and SB110 (63 ppm) 12-dichlorobenzene and 2-methylnapthalene were detected at SB110
at 098 and 081 ppm respectively The most frequent occurrence and highest concentrations of
phthlates (and SVOC in general) occurred at SB 109 and SB 110
5797wpdocraquogalluprifinaltextmlaquolaquoterrifhl061297 4-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
As shown on Table 4-6 Aroclor-1254 occurred at most of the borings in this zone at gtbullraquo
concentrations ranging from 00023 to 64 ppm Aroclor-1242 (0043 to 017 ppm) and Aroclorshy
1260 (043 to 24 ppm) were detected at SB109 and SB110 Pesticides were also detected at trace
to very low concentrations at several locations These compounds include dieldrin (000028 shy
00046 ppm) 44-DDE (000043 - 00063 ppm) 44-DDT (00013 - 00081 ppm) beta BHC
(00013-00021 ppm) and delta BHC (000086-00024 ppm) endrin ketone (00028 ppm)
heptachlor epoxide (0008 ppm) heptachlor (00093 ppm) endosulfan I (0008 ppm) and
methoxychlor (0140 ppm) Table 4-7 shows that the only metals detected within this zone at
concentrations significantly higher than background levels were cadmium (131 ppm) and copper
(103 ppm) both of which occurred at SB109 Cyanide was detected in SB110 in the 1-35 foot
interval at a very low concentration of 32 ppm
Saturated Zone Soil Sample Results - Former Primary Disposal Area
The highest concentrations of VOC within the Former Primary Disposal Area occurred just below
the surface of the groundwater table in the natural deposits immediately underlying fill material
As shown on Table 4-4 in the 4-6 foot interval at SB 109 the following VOC were detected 12shy
DCE (059 ppm) PCE (36 ppm) TCA (98 ppm) TCE (62 ppm) ethyl benzene (85 ppm)
toluene (44 ppm) and xylenes (46 ppm) In the next deepest interval sampled (14-16 feet)
generally the same compounds were detected however the concentrations were lower by an
order of magnitude At the last sampled interval (30-32 feet) generally the same compounds
were again detected but at trace levels (0001-0006 ppm) Cyanide was detected in SB110 in the
10-16 foot interval at a very low concentration of 11 ppm
A total of six SVOC were detected just below the water table at a depth of 4-8 feet below ground
surface (Table 4-5) phthalates (0039 to 0058 ppm) napthalene (021 ppm) 2-methylnapthalene
(0034 ppm) phenol (016 ppm) and 124-trichlorobenzene (0046 ppm) SVOC at greater
depths were napthalene (0076 ppm) in the 10-16 foot interval and bis(2-ethylhexyl)phthlate (11
ppm) at the 22-32 foot interval Aroclor-1254 was detected at concentrations which decreased
with depth from 02 ppm at 4-8 feet to 00096 ppm at 23-34 feet
In the saturated zone no metals were detected at levels significantly greater than background
pH TOG Moisture Content - Former Primary Disposal Area
Values for soil pH ranged from 609 to 745 TOC ranged from lt 1500 to 5500 mgkg and
moisture content ranged from 49 to 282 percent
5797wpdocsgalluprifinaltextmasterrifnl061297 4-14 QST Environmental
Gallups Quarry Superfand Project - Remedial Investigation
416 Contaminant Source Investigations Summary
The previous discussions regarding the contaminant source investigations are grouped into two
categories
bull surveys to identify unknown disposal areas (if any) and
bull investigations at known former disposal areas
Based on the findings of the Visual Site Reconnaissance the Soil Vapor Survey and the
Geophysical Investigations (including the subsequent confirmatory Test Pits) it is apparent that
significant unknown hazardous materials disposal features do not exist at the Site
Based on investigations performed within the known former disposal areas it is evident that the
Former Seepage Bed and the Former Secondary Disposal Area contain generally trace levels of
VOC SVOC pesticides PCB compounds and cyanide For the most part soil metal
concentrations are comparable to background levels measured at upgradient locations at the Site
although very low levels of cyanide (ranging from 11 - 97 mgkg) were also detected at various
depths within the Former Primary and Secondary Disposal Areas Elevated levels of calcium and
magnesium detected at the Former Seepage Bed can be attributed to the large amount of lime
which was reportedly used during remedial efforts Although elevated concentrations of several
other metals were detected at a few locations these levels appear to fall within regional range
values (for the metals with published ranges)
The Former Primary Disposal Area appears to be the only area with notable levels of residual
contamination primarily VOC including ethyl benzene toluene xylene TCA TCE and PCE
In general the highest VOC concentrations are located at or just below the groundwater table in
native materials immediately beneath the fill materials These concentrations diminish quickly
with depth Toluene ethyl benzene xylene and in one case a low level of PCE were also
detected at or near the ground surface within the fill material Empty gasoline cans numerous
off-road vehicle tire tracks and the remains of large campfire pits have been observed in the
vicinity of the former disposal areas Of the VOC detected the ones considered most significant
are those which are also seen in groundwater above their respective MCL (groundwater results
are discussed separately in section 42) In an effort to illustrate the locations where the more
notable amounts of residual VOC contamination are found Plate 4-2 which shows the locations
of total chlorinated VOC has been prepared On this plate the values for total chlorinated VOC
have been color-coded as follows sample intervals where all compounds were below the detection
limit (BDL) are not colored intervals where total chlorinated VOC values are present but less
5797wpdoc8glaquolluprifinraquoltextmasterrifhl061297 4-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
than 1 ppm are shown in green values between 1 and 10 ppm are shown in yellow and locations
between 10 and 35 ppm are shown in red The highest value for any interval is 31277 ppm
As indicated on Plate 4-2 total chlorinated VOC concentrations were either BDL or less than 1
ppm for the majority of intervals sampled Total concentrations between 1 and 10 ppm (ie
yellow zones on Plate 4-2) were detected at two locations SB108 and SB109 Total chlorinated
VOC concentrations in the 4-6 interval at SB108 were 155 ppm At SB109 total chlorinated
VOC concentrations were between 1 and 10 ppm within the 2-4 foot interval (17 ppm) and the
14-16 foot interval (213 ppm) Total chlorinated VOC concentrations exceeded 10 ppm at two
locations SB 109 (2019 ppm in the 4-6 foot interval) and SB115 (31277 ppm in the 3-5 foot
interval) As seen on the plan view insert on Plate 4-2 SB109 and SB115 are located within
approximately 25 feet of each other in the northwestern quadrant of the Former Primary Disposal
Area The zone of highest chlorinated VOC contamination appears to be located just beneath the
fill horizon in close proximity to the groundwater surface
Trace to low-levels of PCB were also detected in both near surface samples and (at one location)
at a depth of 32 feet below the ground surface The highest concentration of any single PCB
compound was 64 parts per million in the 1-35 foot interval at SB110 Other detections
included 43 ppm (SB107 0-1 foot interval) 3 ppb (0-1 foot interval at SB109 and SB110) 28
ppm (0-1 foot interval at SB113) 23 ppm (0-1 foot interval at SB107) and 24 ppm (1-35 foot
interval at SB110) All other detections were below 15 ppm
Plate 4-3 has been prepared to illustrate the distribution of PCB compounds detected within the
Former Primary Disposal Area Plate 4-3 shows the concentration and locations for total PCB
compounds for all intervals sampled with the area
Total PCB concentrations have been grouped and color coded on Plate 4-3 as follows sample
intervals where no PCB were detected (BDL) are shown as colorless zones where total PCB were
detected at concentrations less than 1 ppm are shown in green Intervals containing between 1
and 5 ppm total PCB are yellow and intervals between 5 and 10 ppm are shown in red (the
highest value for total PCB compounds anywhere was 88 ppm)
As shown on Plate 4-3 total PCB values at the majority of locations within the Former Primary
Disposal Area are less than 1 ppm Values between 1 and 5 ppm (shown in yellow) were
detected at SB109 SB110 and SB113 These intervals all occur within four feet of the ground
surface and all are within the fill horizon The only intervals where total PCB concentrations are
between 5 and 10 ppm are the 0-1 foot interval at SB107 (66 ppm) and the 1 to 35 foot interval
5797wpdoc8galluprifinaltextmastemfhl061297 4-16 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
at SB 110 (88 ppm) There does not seem to be any spatial trend or relationship among these
detections as the detections are scattered among all quadrants of the disposal area
42 Groundwater Quality 421 Temporary Well Point Investigation
The results of the temporary well point investigation discussed in Section 24 indicated the
presence of a narrow groundwater plume (approximately 250 feet in width) of volatile organic
compounds (VOC) originating at the Former Primary Disposal Area and extending about 700 feet
in a northwesterly direction VOC were detected up to Mill Brook and at trace levels at one
location near the northern bank of the brook Plate 4-4 summarizes the VOC detections at
different locations and depths in the aquifer A summary of these field and laboratory data is
presented on Table 4-8 and Table 4-9 respectively The area extent of this VOC plume is in
excellent agreement with the groundwater flow directions measured in the northern Study Area (as
discussed in Section 422) The primary chlorinated VOC detected were 111-trichloroethane
(TCA) trichloroethene (TCE) and 12-dichloroethene (DCE) VOC concentrations within the
Former Primary Disposal Area were found to decrease significantly with depth indicating that the
source material is probably located near or above the water table Further downgradient VOC
were detected at generally lower concentrations and were present throughout the entire aquifer
thickness with no apparent depth-dependent trend Various contaminant transport mechanisms
are discussed in Section 50
In the southern portion of the Study Area low-level detections of methyl isobutyl ketone (MIBK)
were detected in samples from two microwells Also acetone and methylethyl ketone (MEK)
were detected at one location adjacent to Tarbox Road No other VOC were detected at any
location
Due to variability in the results of field VOC analyses (using a portable gas chromatograph) and
off-site laboratory analyses it was determined that the field GC results should not be relied upon
as the only source of information to evaluate either the VOC plume boundary or absolute levels of
particular constituents within the plume Rather the microwell results were subsequently used to
guide the location of monitoring wells and to evaluate relative horizontal and vertical
concentration variations within the VOC plume Water quality data from monitoring wells were
then used to confirm the microwell results and delineate plume boundaries
The results of laboratory metals analyses shown in Table 4-10 and Plate 4-5 do not indicate any
significant source areas on the Site nor are there any apparent trends in occurrence or
concentrations of metals Lead was detected at variable depths and concentrations at a total of 15
microwell locations (TW102 103 104 107 115 120 126 128 139 141 143 148 151 and
5797wpdoclaquogilluprifinaltextmlaquo8terrifhl061297 4-17 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
152) These locations represent nearly every portion of the study area With several exceptions
the majority of iiicrowell lead detections were trace to very low (ie lt 10 ugL) Exceptions
included results from single samples collected at locations TW120 (192 ugL) TW-128 (644
ugL) and TW151 (182 ugL) Although several of the locations at which lead was detected are
downgradient of former disposal areas most of the detections were at locations that are either
upgradient or a large distance (400 to 1000 feet) from former disposal areas Furthermore while
lead was detected at some downgradient locations there were other downgradient locations at
which lead was not detected at all It is also noted that lead was only detected at a concentration
of 1 ugL at the microwell (TW143) placed in the center of the Former Primary Disposal Area
and that lead was not detected at all in the two nearest downgradient (relative to the Former
Primary Disposal Area) microwell locations (TW119 and 137) Based on the lack of significant
detections of lead in most microwells on the Site and the fact that metals are typically much less
mobile than VOC the majority of these detections were not considered to be Site related and may
be attributed to an off-site source Numerous off-site activities may have resulted in lead
contaminations including most notably the observed presence of large lead-containing batteries
abandoned along the west side of the railroad bed and fire armhunting activities (as evidenced by
the large number of spent shotgun shell casings observed in the area)
422 Groundwater Monitoring Wells
The initial (Phase 1A) monitoring well network was designed to (1) confirm the findings of the
microwell survey with respect to the chlorinated VOC plume in the northern Study Area and the
two isolated MIBK detections in the southern Study Area and (2) provide hydraulic data to
determine groundwater flow directions and rates An additional objective of the network was to
evaluate potential bedrock groundwater issues related to the Former Seepage Bed which is
located in an area where the water table lies below the base of the overburden formation
Following the Phase 1A monitoring well installation and sampling program additional rounds of
groundwater samples were collected in April July November 1995 February May August
November 1996 and February 1997 under the Long-Term Monitoring Program In October
1995 additional wells were installed during the Phase IB field program to address groundwater
quality and flow directions from areas north of the site The newly installed monitoring wells
(MW117STT MW118STT MW119STT and MW102B) and the existing monitoring wells
located at the former Pervel flock plant (MW-A -B -C -2 and -3) were also included only in
the November 1995 round of groundwater sampling and were sampled only for VOC analyses
Further details of the monitoring well installation program are provided in Section 27 The
following sections present and discuss the groundwater sampling results for VOC SVOC metals
and pesticidesPCB for all nine rounds of sampling
5797wpdocsgalIuprifinaltextmlaquosteiTifhl061297 4-18 QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
4221 VOC
This section discusses the VOC data collected from groundwater monitoring wells during the nine
sampling events conducted between January 1995 and February 1997 Positive groundwater VOC
detections for the nine sampling events are shown in Tables 4-11 through 4-19 respectively VOC
data for the four 1995 events are presented graphically on Plate 4-6 and the VOC data for the
four 1996 events and the February 1997 event are presented on Plate 4-7
42211 Overburden
Northern Study Area
As shown in Plates 4-6 and 4-7 the monitoring well data for all nine sampling events generally
confirm the microwell survey results with regard to the distribution of VOC downgradient from
the Former Primary Disposal Area
The various VOC detected are grouped into chlorinated VOC (eg TCA TCE 11- and 12shy
DCE tetrachloroethene (PCE) 11-DCA 12-dichloropropane carbon tetrachloride methylene
chloride chloroform and vinyl chloride) and non-chlorinated VOC (eg ethyl benzene toluene
xylene benzene styrene and carbon disulfide) As shown in Plates 4-6 and 4-7 the distribution
of these compounds as reported for the November 1995 and February 1997 sample events
respectively has been used to delineate the horizontal boundaries of a VOC plume which
originates in the vicinity of the Former Primary Disposal Area The plume boundary as depicted
on Plates 4-6 and 4-7 is defined by the locations where any compound was detected in excess of
its respective EPA MCL during the November 1995 and February 1997 sampling rounds
Locations at which VOC were detected at levels greater than their respective MCL during at least one sampling round were MW101(STTT) MW102(STTB) MW105 (STTTB)
MW107(TT) and MW-C (located at the former Pervel flock plant facility) MW116T exceed the
MCL for PCE only and only on one occasion (January 1995 at 17 ppb) VOC in samples
collected from MW116T during the eight subsequent sampling events were all below their
respective MCL At MW101 the only compound which was detected in excess of its MCL was
PCE which was detected in the shallow well at a maximum concentration of 6 ppb in the top-ofshy
till well at concentrations ranging from 15 to 32 ppb and between 22 and 30 ppb in the till well
At MW102S compounds detected in excess of their MCLs were 11-DCE (between 3 and 19
ppb) 12-DCE (between 72 and 670 ppb) PCE (between 10 and 43 ppb) 111-TCA (one
exceedance in July 1995 at 240 ppb) TCE (between 15 and 88 ppb) and vinyl chloride (from not
detected to 86 ppb) At MW102TT compounds that exceeded their respective MCL were 11shy
DCE (from not detected to 35 ppb) 12-DCE (between 140 and 1300 ppb) PCE (above the
MCL during four of the sampling events up to 14 ppb) 111-TCA (one exceedance in August
5797wpdocsgalluprifinaltextmasterrifhl061297 4-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
1996 at 200 ppb) TCE (one exceedence in February 1997 at 7 ppb) and vinyl chloride (from not
detected to 430 ppb) MW102B and MW105S each had a one-time MCL exceedence for only
vinyl chloride both occurrences at 3 ppb (in May 1996 at MW102B and in August 1996 at
MW105S
At MW105TT six compounds have exceeded their respective MCL as follows 11-DCE (up to
32 ppb) 12-DCE (between 150 and 1100 ppb) PCE (up to 9 ppb) 111-TCA (between 37 and
390 ppb) TCE (two exceedences up to 14 ppb) and vinyl chloride (from not-detected to 710
ppb) MCL exceedences detected at MW105T are as follow 11-DCE (two exceedences both at
12 ppb) 12-DCE (between 43 and 430 ppb) 111-TCA (one exceedence 380 ppb in February
1996) TCE (one exceedence 27 ppb in November 1995) and vinyl chloride (from not detected
to 1400 ppb) The only compound that exceeded its respective MCL in MW105B is 12-DCE
(between 2 and 180 ppb) MW107TT has had MCL exceedence of the following three
compounds 11-DCE (from not detected to 16 ppb) 12-DCE (between 72 and 1100 ppb) and
vinyl chloride (between 120 and 430 ppb)
Although there is some variation in the distribution and concentration of VOC with each sample
event the plume defined by the November 1995 data set (as shown on Plate 4-6) is nearly
identical to the plume defined by the February 1997 data set (as shown on Plate 4-7) Further
discussion of VOC concentration variations with time is provided in Section 52
Typically VOC in wells located beyond the boundaries of the plume were detected at estimated
or trace to very-low concentrations and were not detected with any regularity VOC were
detected at low levels in at least two-thirds of the samples collected from the following wells
located beyond the boundaries of the plume MW103TT (12-DCE and PCE) MW108B 11shy
DCE PCE and TCA) MW116T (PCE and TCA) SW3S (12-DCE PCE and 11-DCA) and
SW3D (12-DCE TCA and 11-DCA) PCE was detected in excess of its MCL at location
MW116T (17 ppb) during the first sampling event (January 1995) but it was never detected
above 3J ppb in the eight subsequent sampling events
TCA and 12-DCE which were detected in wells at all three locations along the plume centerline
(ie MW107 MW105 and MW102) appear to be good tracers for assessing contaminant
migration away from the Former Primary Disposal Area Based on 1995 data these compounds
have been incorporated into contaminant travel-time analyses presented in Section 5 At locations
MW107 and MW105 the highest concentrations were measured in the top-of-till wells with only
low to trace levels in the shallow wells (TCA and 12-DCE concentration up to 130 ppb and
1100 ppb respectively in MW107TT and up to 390 ppb and 1100 ppb respectively in
MW105TT At location MW102 TCA and DCE were detected at similar concentrations (up to
5797wpdoc8galluprifinaltextmasterrifhl061297 4-20 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
240 and 1300 ppb respectively) in shallow and top-of-till wells For all sampling dates TCA
concentrations in the top-of-till wells along the plume centerline varied from 24 to 390 ppb and
12-DCE levels in the top-of-till wells along the plume centerline ranged from 72 to 1300 ppb
No significant reduction in TCA or 12-DCE concentrations with distance from the Former
Primary Disposal Area is apparent at locations MW107 MW105 and MW102
TCE 11-dichloroethane ethyl benzene benzene 11-DCE 12-dichloropropane PCE toluene
vinyl chloride and xylenes were also detected at each of the three plume centerline locations but
as shown in Plates 4-6 and 4-7 their concentration distributions were more sporadic and TCE
11-DCE PCE and vinyl chloride were the only compounds that exceed their respective MCL
during at least one sampling event TCE was found at concentrations up to 88 ppb (in well
MW102S) 11-DCE was found at concentrations up to 35 ppb (in well MW102TT) the
maximum PCE concentration was measured at 43 ppb (in well MW102S) and vinyl chloride was
measured as high as 1400 ppb (well MW105T) The second highest vinyl chloride value was
710 ppb (well MW105TT) and all other vinyl chloride measurements ranged from not-detected up
to 430 ppb
Wells located within the northern portion of the Site where VOC have never been detected include
MW106TT MW109B and MW110S
Based on the monitoring well and microwell results concentrations within the VOC plume appear
to be relatively evenly distributed throughout the lower three-quarters of the aquifer thickness
Throughout most of the plume area (eg MW107 MW105 and MW101) VOC levels in the
upper five to 15 feet of the aquifer are typically near the detection limit The concentration
reduction near the water table is likely associated with rainwater infiltration Evidence of
infiltration includes the consistently downward hydraulic gradients at MW107 MW108 and
MW116 At these locations the vertical hydraulic gradient is on the order of a factor of 100
greater than the horizontal hydraulic gradient within the VOC plume Location MW102 where
shallow and deep concentrations are similar in magnitude is an exception to this trend of low
concentration near the water table A plausible explanation for the observed concentrations in
MW102S is the hydraulic influence of Mill Brook which as discussed in Section 3323 causes
upward flow in the upper portion of the aquifer near the brook Upward flow near the brook and
MW102S is also supported by the upward hydraulic gradients measured between MW102S and
the stream piezometer PZ-4B
The present PCE distribution in groundwater exhibits inconsistencies with migration from the
Former Disposal Areas PCE was consistently detected at levels above the 5 ppb MCL up to 43
ppb in groundwater samples from wells MW102S MW101TT and MW101T PCE was
5797wpdocraquogalluprifinaltextmasterrifhl061297 4-21 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
measured in well MW116T at 17 ppb in the initial sampling round (January 1995) and
consistently at trace levels in subsequent sampling rounds However only trace levels of PCE
were detected at the MW105 or MW107 locations and the only occurrences of PCE at MW105
or MW107 greater than 5 ppb were three estimated detections of 6 7 and 9 ppb at MW105TT
PCE was not detected in well SW3S and was detected once at a trace level in well SW3D
Monitoring wells MW102 and MW101 are downgradient from both the Former Disposal Areas
and the former Pervel flock plant where PCE TCA and DCE groundwater contamination has
been documented (Section 52) During the November 1995 sampling event VOC detected at
MW-C (located at the former Pervel flock plant) include DCE (97 ppb) TCE (11 ppb) and PCE
(24 ppb) Based on available data MW116 is located downgradient from the former Pervel
flock plant Groundwater flow conditions in the past would need to have been different from
present conditions for MW116 to be downgradient from the Former Disposal Areas Although
the PCE detections at locations MW102 and MW101 could be attributable to historical releases
from the Former Disposal Areas the regional flow pattern and spatial distribution of PCE in
groundwater suggest that contamination from the former Pervel facility has at a minimum
contributed to VOC (PCE TCA and DCE) contamination of these locations Further discussion
of the PCE detections and other VOC concentration variations is provided in Section 52
Southern Study Area
In the southern portion of the Study Area groundwater samples were collected from overburden
monitoring wells at five locations SW9 MW112 MW113 MW114 and MW115 As shown
on Plates 4-6 4-7 no VOC were detected in any of the wells As a result of the consistent lack of
detections wells at these locations were dropped from the Long-Term Monitoring Program (with
EPA approval) after three sampling events These data are consistent with the microwell survey
results but do not support the low-level detections of methyl isobutyl ketone in the two microwell
samples (Section 421)
42212 Bedrock
During the RI VOC were detected in bedrock wells at the following locations MW102 MW105
MW107 MW108 and SW-10 Since the only VOC detected at SW-10 was TCA at an estimated
trace concentration (1J ppb) during the January event and TCA was not detected in SW-10
during the subsequent two sampling events this well was eventually dropped from the Long Term
Monitoring Program (with EPA approval) following the July event All other bedrock wells in
the southern portion of the Study Area (MW111 MW112 MW113 SW-12) were likewise
dropped from the monitoring program At location MW108B estimated concentrations of PCE
(3J ppb) and TCA (up to 9J ppb) were detected during the January and April sampling events
therefore samples collected from this well during the July and November events were submitted
5797wpdocsgalluprifinaltextmasterriftil061297 4-22 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
for VOC analyses using EPA Method 5242 which hs lower detection limits than the TCL
Methods The results of the July and November events for MW108B indicate that other VOC are
present but generally at trace to very low concentrations The highest detections of TCA and
PCE at this location were 92 and an estimated 5 ppb respectively Other VOC detected at
MW108 were carbon tetrachloride (12 ppb) 11-DCA (1 ppb) 12-DCA (015J ppb) 11-DCE
(13 ppb) and xylene (01J ppb)
The only VOC detected at MW107B was TCA which was measured during three events at
concentrations ranging between 059J and 2 ppb Over the nine sampling events VOC detected
at MW105B included 11-DCA (BDL to 9J ppb) 11-DCE (BDL-4J ppb) 12-DCE (11-140J
ppb) 12-dichloropropane (2J ppb in January 1995 and February 1996 only) TCA (2J-12 ppb)
and TCE (BDL-3J ppb)
MW102B was installed during the Phase IB investigation and therefore was only sampled during
five events VOC detected at MW102B were typically at estimated trace concentrations and
only PCE was detected in every round (2J to 4J ppb) The only MCL exceedence was a single
estimated detection of vinyl chloride (3J ppb)
In general VOC detected in bedrock wells were also detected in overburden wells at the same
locations although the concentrations seen in the bedrock wells are significantly lower typically
by an order of magnitude relative to concentrations seen in the top-of-till wells The only
notable exception to this trend is at location MW108 where VOC were not typically detected in
the overburden wells (with the exception of an estimated 2J ppb of DCE detected once in
MW108S and once in MW108TT) At MW105 and MW107 VOC concentrations seen in the till
wells are similar to the low concentrations detected in wells screened in the underlying bedrock
The low VOC levels detected in bedrock wells located in the northern portion of the Study Area
demonstrate that bedrock is not a preferred pathway for contaminant migration This conclusion
is supported by the groundwater hydraulics data outlined in Section 3323 which demonstrate
that the average hydraulic conductivity of the bedrock is more than a factor of 200 less than the
overburden hydraulic conductivity In spite of the upward hydraulic gradient from bedrock to
overburden (factor of ten to 100 larger than the horizontal hydraulic gradient within the VOC
plume) which was found to exist throughout the Study Area vertical (transverse) dispersion
caused by flow in the bedrock fracture system has apparently caused VOC to migrate a limited
distance into the bedrock
5797wpdocsgalIuprifinaltextmasterrifhl061297 4-23 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4222 Semivolatile Organic Compounds
Tables 4-20 through 4-28 present the analytical results for SVOC in groundwater for the nine
sampling events Overall SVOC were detected infrequently and generally at only trace levels
Naphthalene 2-methylphenol and 12-dichlorobenzene were the most frequently detected SVOC
compounds in groundwater samples Naphthalene was detected during every sampling event
generally at MW105 MW107 and MW102 locations within the top-of-till wells and occasionally
also within till at well MW105T The highest naphthalene measurement was 10 ppb in
MW105TT 2-methylphenol was also detected during every sampling event always in well
MW107TT and with lesser frequency in MW105TT MW105T and MW102TT the highest
concentration detected was 3 ppb In eight of the nine sampling events 12-dichlorobenzene was
detected in at least one of the following wells MW102TT MW105TT MW105T MW107TT
and the maximum concentration measured was 4 ppb Maximum bis(2-ethylhexyl)phthalate was
detected in at least one well during six of the nine sampling events the concentrations ranged
from 04J to 35 ppb The locations of the bis(2-ethylhexyl)phthalate detections were sporadic it
was detected three times at MW108S twice at MW014S and MW116T and only once at eleven
wellsTrace levels of the following other compounds were detected during various sampling
events acenaphthene (03J ppb) butylbenzylphthlate (U ppb) di-n-butylphthlate (04J ppb) 4shy
chloroaniline (2J ppb) 24-dichlorophenol (U ppb) fluorene (06J ppb) 4-chloro-3-methylphenol
(2J ppb) phenanthrene (02J ppb) 4-bromophenyl-phenylether (2J ppb) n-nitroso-di-nshy
propylamine (9J ppb) 14-dichlorobenzene (up to 2J ppb) diethylphthlate (up to 04J ppb) 24shy
dimethylphenol (up to 8J ppb) di-n-octylphthlate (up to 46B ppb) 4 methylphenol (2J ppb) and
phenol (up to 4J ppb) The majority of these compounds occur in either the till or top-of-till
wells located within the VOC plume shown on Plates 4-6 and 4-7 (eg MW102 MW105 and
MW107) although there were infrequent detections of compounds at MW103 MW104 MW106
MW108 MW109 SW3D MW112 and MW116 as well
4223 Pesticides and PCB
The only detection of PCB in groundwater was during the April event when Aroclor 1242 was
detected in MW103S and TT at estimated concentrations of 042J and 018J ppb respectively
Estimated low levels of a few pesticides were detected in a small number of groundwater samples
Endosulfan I was detected once (002J ppb in MW107S during April 1995) Endrin was detected
once (00031 JP in MW109S during February 1996) methoxychlor was detected once (012J in
MW107S during February 1997) alpha-BHC was detected once in four wells (during February
1997 up to 0011 JP ppb) beta-BHC was detected twice up to 004J ppb (at MW107S in July
1995 and at MW107TT in February 1996) and gamma-BHC was detected in three samples up to
001JP (at MW105B and MW116S during November 1995 and at MW102S during August 1996)
All positive detections for pesticide and PCB compounds are shown on Table 4-29 (Note Table
5797wpdocraquogalluprifinflltextmasterriftil061297 4-24 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
4-29 only includes those sample IDs where a pesticide or PCB compound has ever been detected)
4224 Inorganics
Tables 4-30 through 4-38 present the analytical results for total (and where applicable dissolved)
metals in groundwater (During sampling low flow purging techniques were used to minimize
disturbance of formation water In cases where turbidity levels less than 5 NTU could be
achieved samples for both total and dissolved metals were collected Otherwise samples were submitted for total metals analyses only) Cyanide has not been detected in any groundwater
sample Metals were generally not detected in groundwater above applicable MCLs and metals
in groundwater samples across the Study Area were similar in concentration to metals detected in
designated groundwater background samples
Analytical results of a duplicate sample collected from MW107S during August 1996 had
anomalously high values Between January 1995 and August 1996 nine samples (seven rounds
plus two duplicate samples) were collected from this well and analyzed for total metals Only one
sample contained inorganic compounds in excess of EPA MCLs or Connecticut Remediation
Standards This sample which was the duplicate sample collected in August 1996 contained
elevated concentrations of aluminum chromium cobalt magnesium manganese and nickel In
order to evaluate the significance of this particular data set a statistical analysis for the
identification of outliers was performed following the procedures described in the EPA guidance
document Statistical Analysis of Ground Water Monitoring Data at RCRA Facilities (EPA530shy
SW089-026) For this analysis a test statistic (TJ was generated (using the average maximum
and standard deviation) from the nine samples for each inorganic analyte detected in this well If
the test statistic was greater than a critical value (1764) representing a 995 level of
significance then there is a strong likelihood that the maximum value for each data set is a statistical outlier If a given analyte was not detected in a given sample the detection limit2 was
used for statistical calculations
Maximum concentrations for nine of the thirteen analytes that have been detected in this well
were found to be statistical outliers Six of the statistical outliers were found in the MW107S
duplicate sample collected in August 1996 which suggests that the inorganic data from this
particular sample are not representative of groundwater quality in the immediate vicinity of this
well Although a specific reason why this sample contained such anomalously high levels is not
apparent it seems clear that this sample is not representative of the actual groundwater metal
concentrations at this location This is supported by the fact that the other sample from this well
on this date has metals concentrations consistent with previous sampling rounds Therefore the
metals data from this duplicate sample have been presented in this Report but are considered not
to be valid
5797wpdocBgalluprifinaltextmasterrifhl061297 4-25 QSTT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4225 DioxinsFurans and Additional Appendix IX Parameters
During the January 1995 sampling event samples from three locations (MW102TT MW106TT
and MW116T) were submitted for laboratory analysis for full Appendix IX parameters During
the April 1995 sampling event samples from MW105TT were also submitted for full Appendix IX
analyses The results for the VOC SVOC PesticidePCB and metals analyses for these samples
have been included in the appropriate tables as discussed in previous sections The results of
Appendix IX analyses that are not common to target analyte and target compound lists
(TALTCL) are discussed below Analyte groups specific to the Appendix IX lists include
herbicides (EPA Method 8150) volatiles by direct aqueous injection (EPA method modified
8015) Phenols (EPA Method 4202) Sulfide (EPA Method 3761) Organophosphorus Pesticides
(EPA Method 8141) PesticidesPCB by EPA Method 8080 and DioxinsFurans
The only detections for any of the analyte classes specific to Appendix IX compounds during the
January 1995 event were phenols (MW102TT at 7 ppb and MW116T at 15J ppb) During the
April 1995 event the dioxinfuran compounds HxCDD (total) and TCDF (total) were detected at
MW105TT at concentrations of 705 and 193 ngL (part per trillion)
423 Residential Wells
Residential wells were sampled during the Phase 1A investigation (January 1995) and again
during July 1995 February 1996 and August 1996 under the Long-Term Monitoring Program
4231 Volatile Organic Compounds
Tables 4-39 through 4-42 present the results of VOC analyses for residential well samples The
locations of these wells are shown on Plate 2-5 TCA was detected at DW114 during all four
sampling events and was also detected once at DW111 and DW113 the concentration ranged
from 018J to 066 ppb Chloroform was detected during three of the sampling events twice at
DW102 and once at DW104 and DW107 the maximum concentration detected was 19 ppb The
following compounds were also detected at low levels once bromodichloromethane (2 ppb at
DW107) dibromochloromethane (084J ppb) PCE (016J ppb at DW114) chloromethane (082J
ppb at DW103) and at DW111 ethylbenzene (025J ppb) toluene (012J ppb) and xylenes
(0 U) Since these locations are not downgradient with respect to the Site the occurrence of
these compounds in these wells are not likely to be Site related
4232 Semivolatile Organic Compounds
No SVOC were detected in any residential well sample during any of the four sampling events
5797wpdocsgalIuprifinaltextmasterrifhl061297 4-26 QT Environmental
Gallups Quarry Superjund Project - Remedial Investigation
4233 Pesticides and PCS
Tables 4-43 through 4-46 present the analytical results of pesticide and PCB analyses for
residential well samples Alpha-chlordane and gamma-chlordane were both detected in all four samples collected from DW105 and in three of the samples collected from DW106 The
maximum concentrations measured were 0095 ppb for alph-chlordane and 004 ppb for gamma-chlordane During August 1996 44-DDE and heptachlor epoxide were both also detected at
DW105 and DW106 (001J ppb for 44-DCE and up to 002J ppb for heptachlor epoxideNo PCB compounds were detected in any residential well The fact that DW105 and DW106 are not
downgradient relative to the site indicate that these compounds are likely attributable to the off-site use of these pesticides and are not site-related
4234 Inorganics
Tables 4-47 through 4-50 present the analytical results of metals and cyanide analyses for
residential well samples for the four sampling events Heavy metals were generally not detected
or were detected at trace levels Alkaline earth metals (eg Ca Mg K) were detected at levels
not unexpected for natural groundwater in the region
43 Surface Water Sediment and Wetland Soils Surface water sediment and wetland soils upstream adjacent to and downstream of the Site
were sampled and analyzed during the Phase 1A investigation to assess the potential if any for
transport of constituents of concern from the Site Sample locations are shown on Plate 2-6 Sediment was collected from one additional location (UB-6A) during the April 1995 sampling round As part of the Long Term Monitoring Program additional rounds of surface water
samples were collected during the April and November 1995 and May and November 1996
sampling events The samples were analyzed for VOC SVOC metalscyanide and pesticidePCB with the exception of the November 1996 samples which with EPA approval
were analyzed only for VOC and metals It is noted that following the Phase 1A sampling event
(September 1994) stations UB-1 UB-2 and UB-3 were eliminated from the Long Term
Monitoring Program (with EPA approval) as these locations are upstream of station UB-4 which
is also upstream from the Site Also station UB-6 (which was located on a tributary to Mill
Brook and sampled during the Phase 1A program) was replaced by station UB-6A (located within
Mill Brook) during the four Long-Term Monitoring events
431 Surface Water During September 1994 water quality indicators (pH dissolved oxygen temperature
conductivity turbidity) were measured in the field at eleven surface water sampling stations six
in Upper Mill Brook two in Lower Mill Brook (below the confluence with Fry Brook) one in
Fry Brook and two in Packers Pond The remaining six locations were dry at the time of
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 4-27 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
sampling As presented in Table 4-51 the water quality of the watershed as judged by both field
measurements and wet chemistry (TSS alkalinity hardness) was good to excellent It may
however be important to note that all of the samples were taken under fair weather conditions so
the influence of potential non-point sources during storm events cannot be assessed with this data
set Table 4-51 presents a qualitative assessment (eg slight moderate obvious) of potential
Local Non-Point Source Pollution As most sampling stations are either adjacent to or
downstream from developed (eg streets highways residences agricultural or industrial
property) the immediate andor cumulative impact of storm events cannot be evaluated in this
report During the four Long-Term Monitoring surface water sampling events field parameters
were again measured The results of these sampling events are shown in Table 4-52
During the September 1994 Phase 1A investigation surface water temperature ranged from 60 degF
(UB1 UB2) to 70degF (PP3) Surface water at most locations contained adequate concentrations of
dissolved oxygen ranging from 335 (UB2) to 1035 (UB8) mg1 but were slightly acidic with
pH varying from 528 (UB1) to 572 (PP3) Dissolved solids measured indirectly as specific
conductivity varied from 120 (UB1) to 710 (PP3) imhoscm
During the four Long-Term Monitoring sampling events surface water temperatures ranged from
526 to 617degF in April 1995 and 420 to 508degF in May 1996 to seasonally lower temperatures
of 396 to 453degF in November 1995 and 374 to 400degF in November 1996 The dissolved
oxygen concentrations were generally similar between the various sampling events ranging from
a low of 335 mg1 (at UB-2 in September 1994) to a high of 1030 mg1 (at PP-1 in November
1996) pH measurements indicated slightly acidic water with the following ranges 514 to 605
in April 1995 574 to 667 in November 1995 615 to 701 in May 1996 and 472 to 620 in
November 1996 Conductivity values were in the same general range between the different
sampling events with the lowest measurement of 1 anhoscm at PP-1 in November 1996 and the
highest measurement of 523 xmhoscm at UB-5 in April 1995
Based on laboratory results surface water in the area is fairly soft ranging in hardness (as
CaCO3) from 12 (TR-1 during April 1995) to 179 (UB2 during September 1994) mg1 and in
alkalinity from lt 1 (UBS during April 1995) to 67 (UB2 during September 1994) mg1 Total
dissolved solids and total organic carbon were below 200 ppm and 15 ppm respectively at nearly
every station during all five sample events A total of 58 total suspended solids analyses were
performed on samples collected during the five sampling events Most of the results were below
the detection limit and only 10 samples exceeded 10 mg1 The highest concentrations were
detected at UB-5 (between 82 and 2470 mg1 in the four samples collected at that location) and at
PP-1 (between 87 and 1500 mg1 in the three samples collected at that location)
5797wpdocraquogalluprifinaltextmasterrifhl061297 4-28 QST Environmental
Gallups Quarry Supcrjund Project - Remedial Investigation
4311 VOC- Surface Water
Data presenting he concentrations of various VOC for each individual surface water location are
presented in Table 4-53 through 4-57 for the September 1994 April and November 1995 and
May and November 1996 sampling events respectively VOC were not detected in the upstream
portion of Mill Brook Six VOC were detected at least once in the five rounds of surface water
samples collected from 11 locations The most consistent detections were 12-DCE and PCE in
Fry Brook sample FB-1 12-DCE was detected every round at FB-1 and occasionally at four
other locations up to 8J ppb and PCE was detected every round at FB-1 and occasionally at
three other locations up to 11 ppb Sample location FB-1 is approximately 1500 feet upstream
of the confluence of Fry Brook and Mill Brook the detections at FB-1 are not likely to be Site-
related and may result from nearby industrial activities The other detections of PCE and DCE
were at trace concentrations at locations below the confluence of Fry and Mill Brooks In
addition TCA was detected once at UB-10 at 3J ppb TCE was detected twice at FB-1 and once
at UB-9 up to 2 ppb carbon disulfide was detected in seven samples representing six locations
up to 20 ppb and toluene was detected twice at upgradient location UB-5 at 1J ppb All of the
VOC concentrations detected are well below those expected to cause adverse effects in fish or
wildlife (USEPA 1986)
4312 SVOC - Surface Water
During the September 1994 sampling event only low levels of one SVOC compound 4shy
methylphenol (28 ppb PP3 1 ppb UB2) were detected in surface water samples The locations
where SVOC were detected are far upstream (UB 2) and downstream (Packer Pond) locations and
are unlikely to have been impacted by the Site During the April 1995 sampling event the only
SVOC detected were trace levels of fluoranthene (04J ppb) phenanthrene (03J ppb) and pyrene
(04J ppb) all of which were detected at UB-5 which is upstream from the site There were no
SVOC detected in any surface water samples during the November 1995 event During the May
1996 sampling event bis(2-ethylhexyl)phthalate was detected in four samples at concentrations
ranging from 05J ppb to 140J ppb The locations of the detections are upgradient of the Site
(UB-5 and UB-8) and downgradient of the Site (LB-2 and PP-1) The sample from LB-2 also had
an estimated low level of di-n-octylphthalate (7J ppb) Table 4-58 presents all of the SVOc
detections in surface water samples (Note Table 4-58 only includes those sample IDs where a
SVOC has ever been detected)
4313 PesticidesPCBs - Surface Water
No pesticides or PCB compounds were detected in any surface water samples
5797wpdocsgalluprifinaltextmraquosterrifhl061297 4-29 Q5T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4314 Total and Dissolved Metals - Surface Water
Because of the ubiquity of naturally occurring metals in surface waters metals results are more
easily interpreted by generating descriptive statistics Descriptive statistics for metals measured in
surface water during 1994 and 1995 are presented in Appendix S Data presenting total and
dissolved metals concentrations for each individual sampling location during all five sampling
events are presented in Tables 4-59 through 4-65
Total Metals
Cadmium silver and thallium were not detected in any samples during the five sampling events
Other constituents detected in only one or two samples during each event include arsenic (up to
296J ppb) beryllium (once at 26B ppb) chromium (up to 764 ppb) cobalt (up to 26 IB ppb)
copper (up to 165 ppb) cyanide (up to 466 ppb) mercury (once at 018B ppb) nickel (up to
821 ppb) selenium (181J ppb at PP3) silver (once at 3J ppb) and vanadium (133 ppb) With
die exception of station UB2 during the September 1994 sampling event UB-5 during die April
1995 May 1996 and November 1996 events and PP-1 during the May and November 1996 events the remaining metals (aluminum barium calcium iron lead magnesium manganese
potassium sodium and zinc) were detected at concentrations that are expected in natural waters
(Hem 1989)
Dissolved Metals
Beryllium cadmium cobalt mercury selenium and thallium were not detected in any sample
Constituents detected infrequently and at low concentrations include antimony arsenic
chromium nickel silver vanadium and zinc Copper was detected at several locations upstream
and downstream from the site at concentrations ranging from 25 to 208B ppb although there
was no pattern in its occurrence or concentration Lead was detected at least once at each of the
sampling locations ranging in concentration from 1J ppb to 188 ppb The occurrences of lead
did not show a pattern die highest measurements were as follows 11 ppb at PP-3 in September
1994 188 ppb at UB-9 in April 1995 16J ppb at UB-4 in November 1995 56J ppb at UB-5 in
May 1996 and 91J ppb at UB-5 in November 1996 Locations UB-4 and UB-5 are upgradient
of the Site The lead detections in Packer Pond samples likely results from non-point sources to
Packers Pond The remaining metals (aluminum barium calcium copper iron lead
magnesium manganese potassium and sodium) were detected at concentrations that are expected
in natural waters (Hem 1989)
Concentrations of total and dissolved metals in surface waters were generally detected infrequently
and at concentrations below ambient water quality criteria ie those that would not pose a threat
5797wpdocsgalluprifinraquoItextmaBterriftil061297 4-30 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
to fish or wildlife (EPA 1986) Heavy metals such as copper and lead generally considered
harmful to aquatic life were detected at locations (Fry Brook and Packers Pond) that are not
likely to be impacted by the Site One location UB-5 (which was dry during September 1994)
contained elevated levels of most metals during the 1995 and 1996 sampling events This sample
station is located well upstream from the site on a tributary to Mill Brook which originates in a
small pond adjacent to Interstate 395 in a highly commercialized area
432 Sediment
A total of seventeen sediment samples were collected during the Phase 1A field survey
(September 1994) six of which were dry at the time The composition of the sediment samples
varied from deep muck (eg LB-02) to a firm sandy substrate (eg UBS) The total organic
carbon (TOC) content of the sediments (presented in Table 4-30) ranged from 075 (UB4) to 16
(PP1) percent with an average of 57 percent
4321 Inorganics - Sediment
Because of the ubiquity of naturally occurring metals in sediment these constituents are more
easily interpreted by generating descriptive statistics which are presented for each individual
metal in Appendix S Data presented for metals at each individual sampling location are
presented in Table 4-66
Antimony and thallium were not detected above the detection limit Beryllium cadmium
chromium cyanide mercury selenium and silver were detected infrequently and when detected
had concentrations close to the respective detection limit andor were detected at remote upstream
or downstream locations With the exception of maximum concentrations detected at PP3 (a
location at Packer Pond which receives stormwater runoff from Lillibridge Road) the remaining metals (aluminum arsenic barium calcium cobalt copper iron lead magnesium manganese
nickel potassium sodium vanadium and zinc) were detected at concentrations within the ranges
expected in naturally occurring soils or sediments (Beyer 1990 Fitchko 1989 Shacklette and
Boerngen 1984)
4322 VOC - Sediment
Analytical results for concentrations of VOC in sediment samples are presented in Table 4-41
VOC were generally detected infrequently and at relatively low concentrations in sediments
Ketones (acetone and 2-butanone) were detected at remote upstream (UB1 UB6) and downstream
(PP1 PP2 PP3) locations One or more of the compounds toluene trichloroethene methylene
chloride and xylenes were detected at trace levels at upstream locations north and east of the Site
(UB-3 UB-5 UB-6 UB-7 and UB-9) Xylenes were detected at a concentration of 31 pm in the
sediment sample from Fry Brook (FB-1) Only toluene at trace level of 0009J ppm was
5797wpdocsgalluprifinaltextma8terrifhl061297 4-31 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
detected in the sediment sample from UB-10 located in Mill Brook near the downgradient edge
of the Gallups plume No VOC were detected in sediment samples from downstream locations
LB-1 and LB-2
4323 SVOC - Sediment
As shown on Table 4-68 the primary SVOC constituents detected were PAH ranging from non-
detect (~ 03 ppm) to 15 ppm No apparent concentration gradient could be determined with
respect to location (eg upstream to downstream) The detections of PAH likely reflect non-
point contributions from local sources such as stormwater runoff from the railroad tracks and
nearby roads
Elevated concentrations of bis(2-ethylhexyl)phthalate were measured in Fry Brook (1300 ppm
FBI) and lower Mill Brook (64 ppm LB2) below the confluence of these two streams The
source appears to originate in Fry Brook
4324 PesticidesPCB - Sediment
Analytical results for pesticides and PCB are provided on Table 4-69 PCB compounds
(Arochlor-1242 -1254 and -1260) were detected in sediment samples from only three locations
all upstream (FB-1 at 019 ppm UB-8 at 0023J ppm and UB-7 at 00064J ppm)
Organochlorine pesticide compounds were also detected infrequently with no apparent trend with
regard to location or source The concentrations in sediment ranged from non-detect (~ 1-3 ppb)
to 39 ppb (methoxychlor at PP1) and their occurrence likely reflects residues of persistent
compounds that were routinely used for insect control before being banned from commercial
production
433 Wetland Soils
A total of 10 wetland soil samples were collected during the field survey most of which were
close to the water table at the time of collection The wetland sampling locations are shown on
Plates 2-6 and 3-14 The total organic carbon content (mgkg) of the wetland soils is as follows
QW1 (160000) QW2 (54600) QW3 (37200) QW4 (35200) QW5 (23900) QW6 (25600)
QW7 (gt 160000) QW8 (gt 160000) QW9 (33600) and QW10 (42600)
4331 Inorganics - Wetland Soils
Because of the ubiquity of naturally-occurring metals in wetland soils these constituents are more
easily interpreted by generating descriptive statistics which are presented for each individual
metal in Appendix S Analytical results for metals at each individual sampling location are
presented in Table 4-66
5797wpdocsgalluprifinaltextmasterrifhl061297 4-32 QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
Cadmium and cyanide were not detected in any sample Antimony arsenic beryllium cobalt
mercury selenium silver and thallium were detected infrequently and at trace levels at or below
the detection limit None of the remaining metals (aluminum barium calcium chromium
copper iron lead magnesium manganese nickel potassium sodium vanadium and zinc)
exceeded normal ranges expected for naturally occurring soils (Beyer 1990 Fitchko 1989
Shacklette and Boerngen 1984)
4332 VOC - Wetland Soils
Analytical results for VOC in wetland soils are provided on Table 4-67 VOC including acetone
2-butanone TCE and carbon disulfide were detected infrequently and at low concentrations
Acetone concentrations ranged from non-detect to 056 ppm (QW8) and 2-butanone concentrations
ranged from 0004 ppm (QW10) to 0067 ppm (QW8) QW8 is located in a remote wooded
location approximately 2000 feet west of the Site QW10 is located a few hundred feet west of
the southern portion of the Site
Acetone and 2-butanone were also detected at lower concentrations (015 and 0033 ppm
respectively) at location QW-1 several hundred feet southeast of the Former Primary Disposal Area A trace level of TCE (0004J ppm) was detected in wetlands soil sample QW-2 collected
approximately 50 feet east of the Former Primary Disposal Area This detection may be related
to the Former Primary Disposal Area since TCE has been detected in this area Based on the
topography however surface water runoff from the former disposal area is unlikely to impact the
wetland No other wetland soil samples had concentrations detected above the instrument
detection limit
Although the source of these VOC is unknown acetone 2-butanone and carbon disulfide are all
commonly used in the laboratory and may have been introduced during post-processing sampling
Some of these compounds are organic solvents that are (or were ) commonly used in many
household (eg spot removers paint strippers aerosols) commercial (eg pesticide
formulations inks and dyes) and industrial (eg degreasers) products Their presence in
wetlands soils samples at low concentrations may be the result of localized human activity in the
area
4333 SVOC - Wetland Soils
Analytical results for SVOC in wetland soils are provided on Table 4-68 The primary
constituents detected were the phthalate esters and PAH PAH were detected infrequently at
generally below 01 ppm Phthalate esters were also detected infrequently ranging from non-
detect to 22 ppm (QW8) The presence of these compounds is likely to be associated with
periodic or seasonal flooding of wetlands as the wetland sampling locations are remote and
5797wpdocsgpluprifinaltextma8terrifhl061297 4-33 QST Environmental
Gallups Quarry Superjimd Project - Remedial Investigation
generally inaccessible except on foot Since these compounds are relatively immobile except in
surface water or as airborne particulates these compounds may have originated from non-point
sources such as the railroad line or runoff from nearby highways
4334 PesticidesPCB - Wetland Soils
Analytical results for pesticides and PCB are provided on Table 4-69 PCB compounds
(Arochlor-1242 -1254 and -1260) were detected infrequently and at low concentrations
The presence of trace levels of PCB compounds in wetland soil samples QW-1 QW-2 QW-3
and QW-4 may be Site-related however PCBs are ubiquitous environmental contaminants that
were widely used in industry and may thus be present in soils as a result of past activities at
surrounding industries Other sources of input into the local environment might include
atmospheric deposition transport from upstream sources and deposition following flood events
Organochlorine pesticide compounds were also detected infrequently with no apparent trend with
regard to location or source The concentrations in wetland soils ranged from non-detect to 0016
ppm (44-DDE at QW1) and their occurrence likely reflects residues of persistent compounds
that were routinely used for insect control before being banned from commercial production
44 Air Quality 441 Baseline Air Quality Survey
Ambient air quality was determined prior to the start of Phase 1A intrusive investigations to
establish a baseline for air quality For the baseline survey air quality in the breathing zone
(between approximately three and six feet above the ground surface) was determined based on
measurements of total VOC (using a PID equipped with an 117 eV lamp) and respirable dust
(using a aerosol meter) at eight locations across the Site These eight stations were located at
each of the three known Former Disposal Areas and at upwind and downwind locations along the
perimeter of the Site The locations of the eight baseline air monitoring stations (AM1-AM8) are
shown on Plate 2-1 During the baseline survey no VOC readings were detected above the EPA
approved action level of 1 ppm at any of the eight monitoring locations Also no respirable dust
readings greater than the EPA-approved action level of 005 mgm3 were recorded during the
baseline survey at any of the monitoring stations
442 Perimeter Air Monitoring
Throughout the duration of the Phase 1A field investigations ambient air quality was monitored
on a weekly basis at the eight stations for the same parameters described above In addition to
the eight air monitoring stations continuous air monitoring was performed at each discrete
investigation area (eg each microwell soil boring etc) in the workers breathing zone and at the
5797wpdocsgaIIuprifinaltextmasterrifhl061297 4-34 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
perimeter of each task specific exclusion zone Air monitoring in the work zones was augmented
with instruments to measure hydrogen cyanide and lower explosion levels Also compound
specific calorimetric equipment (eg Draeger tubes) were used to compliment total VOC
measurements recorded with a PID
No readings above ihe EPA-approved action levels were recorded at the perimeter of the Site
throughout the entire duration of the Phase 1A investigation Elevated worker breathing zone
readings for total VOC were recorded during two of the four soil borings performed within the
Former Primary Disposal Area (SB109 and SB110) Varying but sustained elevated VOC
readings in the workers breathing zone during these two soil borings required the use of OSHA
Level C protection equipment These VOC vapors appeared to dissipate rapidly as no elevated
readings were recorded at the downward perimeter of the exclusion zone
Based on the baseline and periodic air monitoring performed during the investigation undisturbed
ambient air quality in the vicinity of the Site does not appear to have been impacted by former
disposal practices at the Site To confirm this compound specific air monitoring was performed
during the Phase IB investigation
As part of the Phase IB investigation quantitative air monitoring was performed in the vicinity of
the Former Primary Disposal Area The following compounds were detected in shallow soil
during the Phase 1A investigation and therefore were the target analytes for the air monitoring
performed during the Phase IB investigation toluene ethyl benzene total xylenes
tetrachloroethene and PCBs Data from the Phase IB investigation indicate that none of these
compounds were present at any of the air sampling locations for the duration (approximately eight
hours) of the sampling event The laboratory results of these analyses are presented in Appendix
T
45 Potential Sensitive Human Receptors The survey was used to identify any water supply wells schools nursing homes and day care
facilities including in-home day cares within a one-mile radius of the Site
Water Supplies
There are three community water companies serving portions of the Plainfield area within a one-
mile radius of the Site the Gallup Water Company Brookside Water Company and Glen Acres
Water Company The Gallup Water Company operates two wells located in downtown
Plainfield approximately 4000 feet north of the Site The Gallup Water Company presently
services approximately 700 households and three schools (Plainfield Middle School Plainfield
5797wpdocsgalluprifinaltextmlaquoraquoterriltinl061297 4-35 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Central and St Johns) The Brookside Water Company operates two wells located east of 1-395
on the corner of Dow Road and Colonial Road approximately 4000 feet northeast of the Site
The Brookside Water Company presently services approximately 225 homes The water service
lines for the Gallup and Brookside Water Companies are interconnected allowing mixing of the
waters The Glen Acres Water Company has two wells located approximately 2200 feet west of
the Site and services approximately 36 homes The majority of the area west south and east of
the Site and some properties north of the Site rely on individual private wells for their water
supply
One school is located within a one-mile radius of the Site This is the St John Building located
approximately 5200 feet north of the Site This school served students in grades Kindergarten
through eighth grade until 1995 after which the school operates only as a pre-school This
facility is serviced by the Gallup Water Company
Nursing Homes and Elderly Housing
One nursing home and one elderly housing facility are located within one mile of the Site The
Villa Maria Convalescent Home is located approximately 5000 feet north of the Site and is
served by the Gallup Water Company Lawton House Elderly Housing Apartments is located
approximately 4800 feet north of the Site and is also served by the Gallup Water Company
Day Care Facilities
There are eight in-home child day care facilities within a one-mile radius of the Site The
operators and locations are listed on Table 4-70 Only one of these facilities is serviced by a
private supply well That facility located at 134 Lathrop Road is located approximately 3500
feet southeast (upgradient) of the Site
5797wpdoc8galluprifinaltextmasterrifnl061297 4-36 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
50 Contaminant Fate and Transport
This section discusses the environmental fate and transport parameters associated with the
compounds detected during the Remedial Investigation Section 51 details the theoretical basis
for the evaluation of fate and transport characteristics In Section 52 Site-specific fate and
transport parameter values are presented and VOC migration rates and concentration variations
are discussed
51 Theory Migration persistence and relative distribution of compounds between air water and soil depend
on both hydrogeologic and compound-specific parameters The following discussion addresses
each of these parameters as they may affect behavior of compounds within the Study Area
511 Advection by Groundwater Flow
Within a porous medium (soil) the advection rate of dissolved or aqueous-phase compounds
under transient conditions is based on Darcys law (Bear 1979)
where
v= average pore velocity (lengthtime)
K= hydraulic conductivity (lengthtime)
i= hydraulic gradient (lengthlength or dimensionless) which equals
the piezometric head difference between two points on a
groundwater pathline divided by the distance between the two
points
n= effective or drainable porosity (volume of voidstotal soil volume)
of the soil approximately equal to the specific yield
Rj= retardation factor (R gt_ 1) a dimensionless parameter that
represents the ratio of groundwater pore velocity to the actual
advection rate in a sorbing (onto immobile soil grains) porous
medium under transient concentration conditions
5797wpdoc8glaquolluprifinaltextmasterriftil061297 5-1 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
5111 Sorption
The retardation factor Rj represents the attenuation of a plumes frontal advancement due to
sorption ie temporary storage on soil grains Examples of analyses for which retardation
must be considered include (1) calculation of the time required for contamination to reach a given
downgradient location and (2) determination of the time required to remediate a contaminated
aquifer The retardation factor is defined by the following relationship (Freeze and Cherry
1979)
where pb is the bulk dry density of the soil (massvolume) n is the effective porosity of the soil
(volume of voidstotal soil volume) and K^ is the soil-water partition coefficient (volumemass)
often referred to as the distribution coefficient
The soil-water partition coefficient is the relative magnitude of the chemical concentration on solid
particles and in pore water for a particular soil (Lyman et al 1982)
C = AT C
where
C = concentration of the compound sorbed to the solid phase of the soil (mass
chemicalbulk dry mass soil) and
Q = concentration of the compound in the pore water of the soil (massvolume)
In this expression it is implicitly assumed that an equilibrium exists between the solid and water
phases and that the sorption process is linear (Freundlich isotherm with exponent equal to unity)
over the range of concentrations considered
For non-ionic organic compounds such as VOC Kj can be estimated from the measured fraction
of organic carbon naturally occurring in the soil fx (grams organic carbongram dry soil) and
the organic carbon sorption coefficient K^ (Tinsley 1979) as long as f^ gt_ 0001
5797wpdocsgalluprifinaltextmasterrifnl061297 5-2 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Values of K for many common organic compounds are available in the literature K is also
related to the octanol-water partition coefficient K^ for which a large data base is also available
(eg Hansch and Leo 1979) For fine-grained soil particles K and K^ can be related as
follows (Karickhoff et al 1979)
Kx = 063
Chemical-specific relationships between K and K^ also exist for several VOC (eg Lyman et
al 1982) K values for VOC in the Study Area are presented in Table 5-1
5112 Transport by Dissolved Organic Carbon
For certain families of organic compounds the presence of dissolved organic carbon (DOC) in
groundwater can partially reverse the sorption process to soil particles and release sorbed
constituents to groundwater As a result the migration of these compounds under certain
circumstances can be enhanced (Enfield and Bengtsson 1988) Increases in mobility are greatest
for very hydrophobic (high K) compounds such as pesticides polycyclic aromatic hydrocarbons
(PAH) and dioxins Due to their characteristically low K^s VOC transport in groundwater is
generally unaffected by partitioning to DOC unless DOC concentrations exceed 10000 mgL
(Enfield and Bengtsson 1988) Typically natural DOC concentrations in groundwater range
from 1 to 10 mgL
512 Dispersion
Dispersion is a dilution process by which an initial volume of aqueous solution continually mixes
with increasing portions of the flow system Dispersion occurs on a small or microscopic scale
due to molecular diffusion in the water phase nonuniform velocity distributions within the pore
space and to a large degree the tortuous pathlines that groundwater follows during movement
through interconnected soil pores of different sizes and shapes On a macroscopic scale
dispersion results from geologic heterogeneities such as layers and lenses of contrasting soil type
(ie hydraulic conductivity) In practice dispersion is primarily due to variations in hydraulic
conductivity which produce large gradients in advective transport It is well known that aquifers
contain horizontal layers or lenses of coarser and finer grained materials compared to the average
material type that can result in zones of significantly higher and lower hydraulic conductivity
respectively than the screen interval value determined from pumping and slug tests Factor of
ten hydraulic conductivity variations or more over the thickness of an aquifer are not uncommon
5797wpdocsgalluprifinaltextmasterrifhl061297 5-3 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
(Freyberg 1986 Gelhar et al 1985 Robertson et al 1991 and Sudicky et al 1983) For
contaminant transport the more permeable zones are more important because they determine the
maximum distance over which dissolved constituents will migrate from the source area
With respect to chemical migration from a source area to an arbitrary downgradient location
dispersion will cause contaminants to arrive in a shorter time interval than the travel time based
on the mean groundwater pore velocity (Section 511) This reduced travel time associated with
dispersion is due to advection in the zones of higher hydraulic conductivity that cause the
concentration distribution in the longitudinal (flow) direction to spread out or disperse The
additional length Ld that a chemical may migrate due to dispersion can be estimated from the
following relationship (Bear 1979)
where
t = total time of groundwater travel (= VL^ laquo
Rj = retardation factor
DL = longitudinal dispersion coefficient (length 2time)
In a porous medium the longitudinal dispersion coefficient can be estimated as follows
DL =
where
v = groundwater pore velocity
aL = longitudinal dispersivity of the aquifer (length)
The percent reduction in travel time along a pathline due to longitudinal dispersion can be
calculated using the equation (Bear 1979)
where
At = reduction in travel time along a pathline due to longitudinal dispersion ()
5797wpdocsgalluprifinaltextmasterrifhl061297 5-4 QST Environmental
Gallups Quarry Superfond Project - Remedial Investigation
A t = mdash- 100 ^total
Ld = additional distance (in excess of advection distance) that chemical migrates due to
longitudinal dispersion
= total distance of travel by mean advection (average groundwater flow rate)
An excellent summary of estimated longitudinal dispersivity values for numerous sites is given by
Gelhar et al (1985)
513 Advection Due to Fluid Density Differences
Advective transport can also occur due to fluid density differences in cases where the total
dissolved solids (TDS) concentration is very high A typical example is salinity intrusion into an
aquifer where the greater density of the salt water (TDS 35000000 ppb) causes it to sink within
the fresh water aquifer This causes downward advection of groundwater and results in
stratification of the aquifer into varying zones of salinity However density effects can be caused
by any dissolved compound if the concentration is high enough Laboratory experiments have
shown that density effects do not begin to be observed until the total dissolved concentration in a
plume exceeds background levels by about 1000000 to 5000000 ppb (Schincariol and
Schwartz 1990 Schwille 1988) As a result fluid density effects are not important in the Study
Area
514 Biological and Chemical Degradation
In recent years groundwater scientists have begun to understand the role of microorganisms in
the subsurface transformation of organic chemicals Recent studies have shown that large numbers of organisms can exist in the subsurface environment In many cases organic compounds can be completely degraded to harmless products However by-products can also be
produced which are more mobile and toxic than the parent compound These transformations can
make it difficult to correlate groundwater contamination with particular sources Quantitative
predictions of the fate of biologically reactive chemicals are approximate at best This is due to a
lack of understanding of the biochemical transformation process and variability of transformation
rates in an aquifer (eg as much as two orders of magnitude over a distance of less than 1 m)
For example Wood et al (1980) have demonstrated in the laboratory and observed in the field
the following anaerobic transformations of parent compounds to daughter products
5797wpdoc8galluprifinaltextmasterriftJ061297 5-5 QST Environmental
Gallups Quarry Superfiind Project - Remedial Investigation
carbon tetrachloride -bull chloroform -raquo methylene chloride
trans-12-d ichloroethene
PCE -bull TCE - cis-l2-dichloroethene - vinyl chloride
11-dichloroethene
111-trichIoroethane -raquo 11-dichloroethane - chloroethane
The transformation of PCE (tetrachloroethene) and TCE (trichloroethene) to vinyl chloride is an
example of a transformation to a daughter compound which is considerably more toxic than its
parent compound
Persistence in the environment can be described by a parameter known as the environmental
half-life of a compound The environmental half-life tQ is related to a decay constant X
(Itime) in a first-order decay process
X = ln(2)tm
where ln(2) = 0693 The product of the decay constant and the porewater concentration is equal
to the rate (masstimeunit volume) at which a compound degrades into another form of
compound In practice the parameter half-life is an empirical parameter that quantifies mass loss
due to biological photochemical chemical or physical (eg volatilization) degradation
mechanisms
Within the subsurface biological activity is believed to be the principal cause of the
mineralization (ie transformation to inorganic constituents) of organic compounds (Alexander
1978) Hydrolysis is the reaction of compounds with water or the hydroxide or hydromium ions
associated with water However organic functional groups such as halogenated organics (eg
TCE TCA PCE) ketones benzenes and phenols are generally resistant to this mechanism
(Lyman et al 1982) Oxidation (loss of electrons during a chemical reaction ) and reduction
(gain of electrons during a chemical reaction) can also alter and attenuate organic compounds
For most inorganic compounds geochemical transformations are the most important degradation
mechanisms Due to the complexity of degradation processes and the fact that little data is
typically available to adequately model the loss mechanisms prediction of decay rates in the field
as discussed above is very difficult and not often feasible especially for biodegradation
5797wpdocsgalluprifinaltextmasterrifnl061297 5-6 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
515 Volatilization
The Henrys law coefficient H (Morel 1983) is an air-water partition coefficient which relates
the equilibrium concentrations in air and water for volatile compounds in a multi-phase system
such as the unsaturated zone of the subsurface or the air-water interface of a water body
H = C 1C
where C and eurobdquo are the chemical concentrations in air and water respectively The coefficient is
used in the calculation of volatilization from a water body or soil and for the determination of
solids water and air concentrations resulting from chemical partitioning in a contaminated
unsaturated soil
Organic compounds with Henrys law coefficients greater than 103 atm-m3mole are generally
considered to be highly volatile These compounds can volatilize relatively rapidly from water at
air-water interfaces such as surface water bodies or groundwater tables However the rate of
volatilization is also controlled by diffusion in the water phase Table 5-1 summarizes values of
the Henrys law coefficient for selected organic constituents detected in the Study Area
516 Aqueous Solubility
The solubility of a compound in water is the maximum amount of that compound that will
dissolve in a unit volume of pure water at a specified temperature Water solubility is one of the
most important fate and transport parameters Highly soluble compounds tend to have relatively
low KK values and Henrys law coefficients and tend to be more readily biodegradable by
microorganisms in soil Table 5-1 lists solubilities for VOC detected in the Study Area
52 Study Area-Specific Characteristics 521 Retardation Factors
A Site-specific evaluation of chemical migration rates in groundwater was conducted by
measuring the total organic carbon content TOC of 31 soil samples from the northern Study
Area (Table 5-2) The parameter f (Section 51) is equal to TOC expressed as a fraction As
discussed in Sections 26 and 2721 an ASTM method was used to measure the 4 of the 28
samples from the Former Primary Disposal Area (SB-series borings) EPA Method 9060 was
used to analyze the three samples from the boring for well MW102B The fK measurements for
the SB-series soils samples range from less than 00015 to a maximum of 0023 and the
geometric mean is 00023 In these calculations values below the detection limit of 00015 were
assigned one-half the detection limit These f^ values are typical of high hydraulic conductivity
sand and gravel aquifers
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 5-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The measured values for the three MW102B samples are uncharacteristically low for coarse
stratified drift The geometric mean of these samples is 0000014 which is a factor of 100 lower
than the SB-series data The discrepancy appears to be due to the fact that EPA Method 9060 is
designed for TOC analysis of water samples The f values for the three MW102B samples are
expected to be on the order of 0001 based on comparisons with organic carbon values for
samples of a similar lithology from the Gallups Quarry and other sites Furthermore as
discussed by Karickhoff et al (1979) the available correlations that relate f^ to retardation factor
Ra are not valid below f = 0001 Below values of f = 0001 mechanisms other than
sorption to organic carbon (eg chemical adsorption to mineral surfaces) begin to dominate with
the result that overall sorption and retardation of VOC do not decrease even though the TOC
content of the aquifer materials does Therefore if f^ lt 0001 researchers have indicated that
in many cases calculations of Rd can use f^ = 0001 to account for these alternative sorption
mechanisms For these reasons the SB-series f^ data that are representative of coarse stratified
drift were used in the transport evaluations discussed in the following sections
The average f^ for the SB-series soil samples located below the water table were also calculated
to evaluate vertical trends in the data These samples include
Sample Depth (feet bgs) TOC (mgkg)
SB 104 15-17 lt1500
SB104 26-28 1700
SB108 6-8 lt1500
SB 109 4-8 1600
SB109 10-16 lt1500
SB109 17-24 1500
SB109 24-32 1600
The geometric average f for these samples is 00012 if one-half the detection limit is used for f
lt 00015 Because this average excludes shallow samples with larger silt contents it is
considered more representative of the higher hydraulic conductivity coarse-grained soils which
primarily control groundwater transport
Table 5-1 summarizes chemical-specific retardation factors for VOC detected in Study Area
groundwater These estimates are based on a f value of 00012 which as discussed above is
near the minimum value appropriate for the calculation of R Actual retardation factors in the
aquifer will be nonuniform due to the inherent variability of soil organic carbon content For
example retardation factors based on an f of 00012 may be more appropriate for evaluation of
5797wpdocsgalluprifinaltextmasterri fal061297 5-8 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
transport rates in the middle to lower portions of the aquifer where the soil is generally coarser
and contains less silt which is associated with the organic carbon content Conversely the
average value of 00023 for all samples is likely more representative of soils in the upper portion
of the aquifer and above the water table In any case this overall variability in f^ values for the
aquifer is considered to be smaller in magnitude than the natural variability in hydraulic
conductivity values for the site The recent detailed field investigations in sand and gravel
aquifers referenced in Section 512 have shown that it is not uncommon for hydraulic
conductivities to vary by as much as a factor of ten over a scale of a few feet Variations in both
f and hydraulic conductivity values impact predicted chemical transport rates (Section 511)
A bulk dry density of 18 gcm3 and an effective porosity of 025 were estimated from the
literature based on soil grain size analyses Potential variability associated with these parameters
is small compared to k^ estimates and is not important for the following transport rate evaluation
The results in Table 5-1 are useful for comparing relative mobilities for different compounds and
assessing contaminant migration rates relative to groundwater pore velocities 11-dichloroethane
is expected to be the most mobile VOC while PCE and ethyl benzene should be the least mobile
The tracer compounds TCA and DCE are expected to migrate about a factor of two slower than
the groundwater with DCE migration being the fastest
522 Chemical Migration Rates
5221 Groundwater Travel Times
Compound-specific migration rates in the overburden aquifer were examined using Darcys law
(Section 511) to compute groundwater pore velocities from (1) measured horizontal hydraulic
gradients defined by the November 1995 piezometric surface maps (Section 332) (2) the
hydraulic conductivity data (Table 3-1) and (3) estimated retardation factors (Table 5-1) The first step was to construct a map of groundwater times-of-travel along the various pathlines shown
on the groundwater flow maps for the southern Study Area (Plate 3-9) and for the lower portion
of the aquifer in the northern Study Area (Plate 3-8) Groundwater travel times along each of the
pathlines were modelled using the Tecplot software and the interpolated piezometric head
distribution to define the continuous horizontal hydraulic gradient distribution Additional
information regarding pathline computation using Tecplot is provided in Appendix Q Since the
more permeable zones in an aquifer are known to control the rate of advancement of a plumes
leading edge (Section 512) the upper bound hydraulic conductivity estimates from Table 3-1
were considered From a review of these measurements it was determined that a mean hydraulic
conductivity of 004 centimeters per second (115 feet per day) would be reasonable to use in the
time-of-travel computations in the northern Study Area because this value is representative of the
more permeable coarse-grained soils north and northwest of the Former Primary Disposal Area
(ie wells MW102TT MW103TT MW104TT MW117TT and MW118TT) A lower
5797wpdoc8galluprifinaltextmlaquosterrifhl061297 5-9 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
hydraulic conductivity of 00025 cms (7 ftday) representing the geometric mean value for wells
MW114TT and MW115TT was selected for the southern Study Area An effective porosity of
025 was used in the calculations
The travel-time analysis results are shown in Plate 5-1 Markers denoting half-year (northern
Study Area) and five-year (southern Study Area) travel-time intervals have been placed on each of
the pathlines to allow evaluation of spatial variations in groundwater pore velocity and
determination of total groundwater travel-time between different locations The time period
required for a particular VOC to migrate along a pathline can be estimated as the product of the
groundwater travel-time and the compound-specific retardation factor listed in Table 5-1
5222 Groundwater Flushing Rates
Another useful relationship to consider when evaluating chemical migration is the time period
required to reduce the concentration in a specific portion of an aquifer by groundwater flushing
Assuming that source material is no longer introducing contamination into the portion of the
aquifer (ie control volume) being evaluated the US EPA Batch Flushing Model (EPA 1988)
provides such a relationship
p v = J V h )
where In is the natural logarithm to the base e Rd is the retardation factor C0 is the initial or
starting average groundwater concentration in the control volume Q is the final average
concentration and Pv is the number of groundwater pore volumes which have flowed through the
control volume Pv can be estimated as
P =-raquo v Ltotal
where v is the groundwater pore velocity (Section 511) t is the time duration being considered
and L^ is the total distance or length along a characteristic pathline (from upgradient to
downgradient) through the volume of aquifer material The model assumes complete mixing of
contaminants (ie infinite dispersion) within the control volume Brusseau (1996) demonstrated
that in part due to this assumption the Batch Flushing Model can partially account for
nonequilibrium desorption (ie delayed release) of VOC from soil
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 5-10 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
For example the southern Study Area (area south of the Former Seepage Bed) can be considered a control volume with a characteristic groundwater flushing rate In this area a time t of order 10 years is required for groundwater to flow through a distance L^ of about 400 feet thus indicating an average pore velocity v of about 40 feet per year In other words one pore volume of groundwater flushes through the overburden deposits in the southern Study Area in approximately 10 years From the Batch Flushing Model it can be seen that for a nonsorbing compound with R = 1 23 pore volumes [ln(10)] would need to flush through this area to lower average concentrations by a factor of ten assuming no source material remained east of the southern Study Area or above the water table 46 pore volumes would be needed for a factor of 100 reduction Since each pore volume roughly corresponds to 10 years the factors of 10 and 100 concentration reductions would require time periods of about 23 and 46 years respectively If however one were considering a compound with R = 3 the corresponding times would be about 70 and 140 years
5223 Discussion In the northern Study Area three areas of characteristically different horizontal hydraulic gradients exist in the overburden aquifer The steepest gradients (on the order of 0025 feet per foot) are found south of the former disposal areas Assuming the hydraulic conductivity in this area is 004 cmsec Plate 5-1 shows that the groundwater travel time through this portion of the aquifer is expected to be much less than one year However hydraulic conductivity data and soil descriptions suggest that a more representative hydraulic conductivity value for the till deposits in this area would be 0001 cmsec or less which would correspond to a travel time of five years or more (eg from MW109 to the Former Primary Disposal Area)
Northeast of well MW116 north of Mill Brook and in the vicinity of the former Pervel flock plant the hydraulic gradient is about 0007 feet per foot and a hydraulic conductivity of 004 cmsec is representative of the aquifer As a result the largest groundwater pore velocities are expected to exist in these areas For example as shown in Plate 5-1 the expected groundwater travel time is about one to two years from the vicinity of Pervel to MW116 and from Pervel to MW101
Groundwater travel times downgradient from the Former Primary Disposal Area are much longer due to the low hydraulic gradients northwest of the railroad tracks In the vicinity of MW105 and MW102 the gradient is about 00003 feet per foot or more than a factor of 20 less than the gradient northeast of this area For example the estimated groundwater travel time (ignoring longitudinal dispersion) from MW107 to MW102 near the front of the VOC plume is about 8 to
10 years By comparison almost 20 years has passed since the documented disposal in the late 1970s Based on the retardation factors (Table 5-1) for TCA (R = 23) and DCE (R = 14)
5797wpdocsgalluprifinaltextmasterrifhl061297 5-11 QS7 Environmental
Gallups Quarry Superand Project - Remedial Investigation
the estimated travel times for these compounds from MW107 to MW102 are about 20 years and
13 years respectively Considering these chemical migration rates and the fact that TCA and
DCE were detected at quantifiable levels along the VOC plume centerline and at location
MW102 it appears reasonable to conclude that these compounds are associated with the former
disposal areas
However as discussed in Section 4221 the present PCE distribution in groundwater exhibits
inconsistencies with migration from the former disposal areas Although historical detections of
PCE were found in well cluster SW17 which is located downgradient from the Former Primary
Disposal Area and near well cluster MW105 the concentrations had reduced from a maximum of
1000 ppb in 1980 to near the detection limit by early 1993 (Section 523) Based on this rate of
reduction PCE concentrations at diis location would be expected to have fallen below or near the
detection limit by 1995 In fact only trace levels were detected in wells MW105TT and
MW105T during two of the four 1995 sampling events Furthermore the measured groundwater
flow directions in the overburden aquifer indicate that many of the pathlines originating near the
former Pervel flock plant pass through the vicinity of wells MW117 MW118 MW119 MW116
MW103 MW102 and MW101 Although MW101 and MW102 are downgradient from both
Pervel and the former disposal areas groundwater flow conditions in the past would need to have
been different from present conditions for MW116 and MW103 to be downgradient from the
former disposal areas As discussed in Section 4 elevated levels of PCE TCA and DCE have
been detected in monitoring wells located on the former Pervel property Also PCE TCA and
DCE were detected in wells MW116T MW118TT and MW103TT located downgradient from
Pervel during the 1995 sampling rounds and PCE TCE and DCE were detected in well MW-C
on the former Pervel property The travel time of these compounds from Pervel to wells
MW116 MW118 MW103 MW102 and MW101 is estimated to be two to six years Taking
this into consideration along with the VOC detections in the Pervel wells during the period 1987
to 1989 (Section 523) it is possible that the low-level PCE TCA and DCE detections in
MW116T MW118TT and MW103TT represent the last remaining portion of a Pervel VOC
plume The lack of VOC detections in wells MW117 and MW119 could be explained by dilution
in these areas or by the fact that these wells may not be immediately downgradient from the
historical source area(s) on the former Pervel property
The migration rate of PCE compared to the disposal area tracer compounds TCA and DCE also
supports the existence of an off-site PCE source The expected migration rate of PCE is a factor
of two to four slower than that of TCA and DCE due to their differing K values Assuming all
of these VOC were released within a few years of each other the leading edges of the TCA and
DCE plumes should be much farther downgradient than the PCE plume Instead as evidenced by
the data shown in Plate 4-6 the opposite is true because a PCE concentration of about 30 ppb has
5797wpdocsgalluprifinaltextmasterrifnl061297 5-12 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
been detected at MW101 In terms of groundwater migration (not including retardation) from the
Former Primary Disposal Area the elevated PCE concentrations at location MW101 would
represent a total travel-time from the former disposal areas which is more than a factor of two
greater than that required for the leading edge of the TCA-DCE plume to reach MW102
Comparing the relative mobilities of PCE TCA and DCE (Table 5-1) the time required for PCE
to migrate from the Former Primary Disposal Area to well MW101 should be more than a factor
of four to eight longer than the TCADCE travel time to MW102 Based on this comparison the
PCE detections at MW101 could be attributed to transport from Pervel It is also possible that
the Pervel groundwater contamination has impacted the MW102 area Although the PCE
detections at locations MW102 and MW101 could be attributable to historical releases from the
former disposal areas the above findings (flow directions spatial PCE distribution travel times)
suggest that contamination from the former Pervel facility has at a minimum contributed to VOC
contamination (PCE and possibly DCE and TCA) at these locations
The above discussion also highlights the important issue of what defines the leading edge of the
zone of VOC contamination in the overburden aquifer Several of the above findings suggest that
the downgradient extent of VOC contamination associated with the former disposal areas is
located near wells MW102 and MW101 The convergent nature of the groundwater flow patterns
in the northern Study Area clearly establish a narrow well-defined preferred pathway of low-level
contaminant migration from the Former Primary Disposal Area The chemical analysis results
from the monitoring well sampling program confirm the measured flow directions Further
whereas TCA and DCE can presently be traced continuously along the plume centerline at
elevated levels (well locations MW107 MW105 and MW102) PCE cannot These findings
suggest that the PCE contamination in groundwater may be attributable to the former Pervel flock
plant and should not be used solely to define the leading edge of the VOC plume The time-ofshy
travel computations support the location of the disposal area VOC plume between MW102 and
MW101 The reduction of TCA and DCE concentrations to less than 10 ppb and the decrease of
xylene to below detection at MW101 is also consistent with the interpretation that the disposal
area VOC plume does not extend far beyond MW102 In addition the groundwater pore velocity
in the vicinity of wells MW102 and MW101 is estimated to be about 50 feet per year which is as
much as a factor of 20 lower than rates upgradient from this area Based on this pore velocity
and the retardation factors in Table 5-1 the migration rates of TCA and PCE are expected to be
about 20 and 10 feetyear respectively At these rates the estimated travel times for TCA and
PCE from MW102 to MW101 are about 20 and 35 years respectively As discussed in the
following section given the relatively large rates of historical VOC concentration reductions
which have been observed in the northern Study Area it is expected that PCE 12-DCE 11shy
DCE and TCE levels near MW102 will fall below MCLs within the above 20- to 35-year period
due to biodegradation and dilution mechanisms Reduction rates for vinyl chloride which also
5797wpdocsgalluprifinaltextmlaquoraquoterrifhl061297 5-13 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
has been detected above MCLs near MW102 will likely lag behind the other VOC because it is a
final chlorinated breakdown product
523 Time-Dependent Concentration Reductions
5231 Observed Concentration Changes
Significant groundwater concentration reductions with time have been observed in the northern
Study Area from the late 1970s through the 1995 sampling rounds To illustrate these temporal
trends concentration data for selected VOC were plotted versus time to quantitatively evaluate the
reduction rates The observed rates of concentration reduction are also compared to predicted
values using the groundwater flushing relationships presented in Section 5222 and are evaluated
to determine site-specific estimates of biodegradation rates
Figures 5-1 through 5-3 contain the concentration vs time graphs for three groups of wells
organized according to transport characteristics and location Group 1 (Figure 5-1) immediately
downgradient from the former disposal areas (SW17S SW17D SW13 MW107TT MW105S
and MW105TT) Group 2 (Figure 5-2) within the downgradient portion of the VOC plume
(MW102S MW102TT MW101TT) and Group 3 (Figure 5-3) the area northeast of the VOC
plume and downgradient from the former Pervel flock plant Data from the Group 1 wells
provide a good historical perspective on improvements in groundwater quality resulting from
source removal activities in the late 1970s and from ongoing biodegradation and rainwater
infiltration (flushing) within the Former Primary Disposal Area The Group 2 wells are located
within the downgradient portion of the VOC plume and in a section of the aquifer where the
hydraulic gradient and associated groundwater transport rates are up to a factor of 20 lower than
in other parts of the northern Study Area Group 3 wells are downgradient from the former
Pervel facility where elevated levels of PCE and TCA have been detected and are located in the
portion of the aquifer with the highest groundwater flushing rates
5232 Evaluation of Concentration Reduction Rates and Mechanisms
The most important aspect of the semilogarithmic plots in Figures 5-1 to 5-3 is the characteristic
slope or trend of the concentrations as a function of time Specifically it can be seen that many
of the graphs exhibit an almost straight-line decrease in concentration with time This linear
variation is often observed with historical groundwater quality data because the linearity has a
physical basis First many biodegradation mechanisms can be modelled as a first-order decay
process (Section 51) which produces a straight-line decrease in concentrations on a semi-log plot
Second flushing of clean groundwater (eg rainwater infiltration or uncontaminated
groundwater) through a contaminated volume of aquifer material has been shown (Section
5222 Brusseau (1996)) to exhibit the same type of response In both of these approximate
first-order processes the slope of the straight-line response is inversely proportional to the
5797wpdocsgalluprifinaltextmasterrifhl061297 5-14 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
environmental half-life (Section 514) for that mechanism and a particular chemical compound
Using the relationships developed in Section 5222 the environmental half-life associated with
groundwater flushing can be defined as
Substituting the expression for pore volume Pv the flushing half-life can also be written
From the above expression it can be seen that the flushing half-life for a particular compound is
directly proportional to the chemical retardation factor and inversely proportional to the
groundwater pore velocity The groundwater flushing rate represents the rate at which
concentrations in a particular portion of the aquifer are reduced In contrast to biodegradation
groundwater flushing does not reduce the total mass of a compound in the aquifer because the
contaminants are advected to downgradient areas
In the Group 1 area historical VOC data for the SW-series wells (Metcalf amp Eddy 1993) (eg SW13 and SW17) summarized in Table 5-3 and on Figure 5-1 show that TCA TCE and PCE
levels in groundwater downgradient from the Former Primary Disposal Area have typically
decreased by a factor of more than 100 from the late 1970s to 1993 Using the SW17S data
from 1980 to 1993 the estimated environmental half-lifes for TCA TCE and PCE are
approximately 15 20 and 24 years respectively From February 1993 through the present the
shallow concentration reduction rates (SW17S and MW105S) are much higher corresponding to TCA TCE PCE and DCE environmental half-lives of about 03 lt 1 03 and 04 years
respectively Concentration reduction rates in the lower portion of the aquifer (SW17D and
MW105TT) from February 1993 through the end of 1995 are a factor of two to three slower than
shallow rates the estimated environmental half-lifes for TCA PCE and DCE in the deep aquifer are about 06 09 and 09 years respectively The higher concentration reduction rates in the
shallow aquifer may be due to rainwater infiltration andor increased biodegradation These
decreases in VOC levels are likely due to a combination of (1) source removal and source
depletion (ie soil concentration reduction by flushing mechanisms) within the former waste
disposal areas (2) mixing of rainwater infiltration with groundwater which can be a significant
dilution mechanism in the wetland areas as evidenced by the frequent occurrence of ponded water
and (3) biodegradation by microorganisms in soil
5797wpdoc8galluprifiiialtextmlaquoraquoterrifhl061297 5-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Vinyl chloride does not follow the same trends of reducing concentrations exhibited by the other
chlorinated VOC Vinyl chloride concentrations in wells MW107TT and MW105TT generally
increased during the 1995 sampling rounds Since this compound is the final chlorinated
breakdown product of PCE TCE and DCE it appears that the vinyl chloride detections are the
result of biodegradation The apparent increase in vinyl chloride concentrations and decrease in
DCE levels in well MW107TT may be further evidence that vinyl chloride detections are
associated with biodegradation mechanisms
The observed Group 1 environmental half-lifes are consistent with predicted half-lifes due to
groundwater flushing From Plate 5-1 the estimated groundwater travel time from MW107 to
MW105 is 05 to 1 year which corresponds to 1 to 2 groundwater pore volumes per year
flushing through the Group 1 Area Using the retardation factors in Table 5-1 the predicted
flushing half-lifes for DCE TCA and TCE range from 05-10 08-16 and 07-14 years
respectively and the flushing half-life for PCE is between 14 and 3 years This good agreement
between observed and predicted rates of concentration reduction downgradient from the former
disposal areas is additional evidence that source removal activities were successful and natural
mechanisms are actively producing further reductions in contaminant levels The fact that deep-
aquifer PCE and TCA concentrations near MW105 have decreased more rapidly than predicted
groundwater flushing rates during the period 1993 to 1995 suggests that biodegradation is
breaking down these parent compounds Furthermore TCA TCE and PCE reduction rates
before 1993 were much slower and are similar in magnitude to flushing rates This indicates that
biodegradation before 1993 was less important Assuming this is the case the estimated
biodegradation half-lifes for PCE and TCA for the period 1993 to 1995 range from 13-25 and
10-24 years respectively near the Former Primary Disposal Area In contrast observed
reduction rates for TCE and DCE are slower than predicted flushing rates which may be
evidence that breakdown of their respective parent compounds was significant during the period
1993 to 1995 Indeed this interpretation is consistent with the observed biodegradation of PCE
In the Group 2 area (Figure 5-2) VOC levels (with the exception of DCE) at well cluster
MW102 appear to increase in 1995 while concentrations at cluster MW101 remained relatively
constant The concentration increase at MW102 may be due to the fact that this cluster is near
the leading edge of the VOC plume and groundwater flushing rates in this area are relatively low
However as discussed in Section 522 the increased PCE and TCA levels along with daughter
products such as TCE DCE vinyl chloride and DCA may be associated with transport of the
PCE and TCA plumes on the former Pervel property
The most interesting of the Group 3 wells are wells MW-A -B and -C located on the former
Pervel property As shown on Figure 5-3 PCE and TCA concentrations in wells MW-A and
5797wpdoc8galluprifinaltextmasterrifhl061297 5-16 QampT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW-B reduced to below detection limits by 1990 These rates of reduction correspond to halfshy
lifes of about 02 years for TCA and 03 years for PCE By comparison based on travel time
estimates from Plate 5-1 predicted groundwater flushing half-lifes for TCA and PCE
concentration reduction near Pervel are about 08 and 14 years respectively Assuming the
differences between observed concentration reduction rates and rates predicted by groundwater
flushing alone are due to biodegradation the biodegradation half-lifes for TCA and PCE are 03
and 04 years respectively In well MW-C TCA levels have reduced at a rate consistent with a
02-year half-life while the PCE half-life is approximately 05 years The corresponding
estimated biodegradation half-lifes for TCA and PCE at MW-C are 03 and 08 years
respectively Therefore biodegradation appears to be the major cause of the observed TCA and
PCE concentration reductions in the Pervel wells The lack of PCE or TCA detections in well
clusters MW119 and MW117 during the November 1995 sampling round are also consistent with
the rates of reduction in the Pervel wells For example the estimated travel times of PCE and
TCA from Pervel to the MW119 and MW117 wells are on the order of 4 and 2 years
respectively Since PCE and TCA levels in wells MW-A and MW-B were below detection by the
beginning of 1990 this groundwater with no detectable levels of either compound would be
expected to have passed through the MW119 and MW117 wells by the beginning of 1994 (PCE)
or 1992 (TCA)
In contrast the groundwater travel time from Pervel to wells MW116 MW103 and MW118 is
estimated to be up to one year longer than the travel time to MW119 and MW117 This would
correspond to increased travel times for PCE and TCA of about 4 and 25 years respectively
Based on these estimates low but detectable levels of PCE and TCA would be expected in wells
MW116 MW103 and MW118 during 1995 groundwater sampling In fact PCE TCA and
DCE were detected at each of these locations in 1995 at trace levels Slightly higher
concentrations of PCE and TCA were detected in MW116T during January 1995 but trace levels
were detected during each of the three subsequent 1995 rounds Further these rates of PCE and
TCA migration from Pervel would be consistent with the detections in well clusters MW102 and
MW101
Additional estimates of biodegradation rates were made by evaluating concentration reductions
within the parcel of groundwater located near well SW17 in 1980 Using the travel times shown
in Plate 5-1 it is estimated that about five years would be required for groundwater to travel from
SW17 to MW102 The corresponding chemical migration rates for TCA TCE and PCE are 12
11 and 20 years respectively Due to longitudinal dispersion (Section 512) the actual travel
times would be somewhat less Therefore groundwater presently in the MW102 area is expected
to be representative of historical (1980) groundwater contamination from the SW17 area
Neglecting possible contaminant contributions from Pervel most of the VOC concentration
5797wpdocsglaquolluprifinaltextmalaquoteiTifTil061297 5-17 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
reductions occurring in this parcel of groundwater as it traveled from SW17 to MW102 would be
due to biodegradation and rainwater infiltration
Figure 5-4 shows the TCA TCE and PCE concentration data from 1980 and 1982 for SW17S
and from January and November 1995 for wells MW102S and MW102TT The slopes of the
lines connecting the data from these two periods provide estimates of the combined biodegradation
and rainwater dilution rates for these compounds The combined half-lives for these two
mechanisms are 15 years (TCA) 18 years (TCE) and 21 years (PCE) From Bear (1979) the
half-life for rainwater dilution can be estimated as
n - b
where n = effective porosity b = saturated thickness and I = groundwater recharge rate due to
rainwater infiltration Using n = 025 b = 60 feet and I = 30 inchesyear (USGS 1995) the
half-life for dilution due to rainwater infiltration is about 4 years Using this value the estimated
biodegradation rates for TCA TCE and PCE within the VOC plume are 24 33 and 44 years
respectively These estimated biodegradation rates for TCA and PCE are a factor of two to three
less than estimated rates near the Former Primary Disposal Area during the period 1993 to 1995
5233 Summary
From the late 1970s through the four 1995 sampling rounds groundwater concentrations in the
VOC plume downgradient from the Former Primary Disposal Area have decreased at a rapid rate
The groundwater quality data from 1995 indicates that this trend of reducing concentrations is
continuing Based on these concentration reduction rates most VOC levels will fall below their
respective MCLs in a period of less than four years Vinyl chloride is an exception to this trend
because increased levels of this compound were detected in 1995 apparently due to the chemical
break down of its parent compounds PCE TCE and DCE
Analyses of these concentration reductions with time indicate that biodegradation and dilution by
rainwater infiltration are the key mechanisms responsible for these changes with biodegradation
likely the most important component Within the VOC plume biodegradation and rainwater
infiltration are reducing most VOC (with the exception of vinyl chloride) concentrations by about
a factor of two every two years which corresponds to an environmental half-life of two years
5797wpdocsglaquolluprifinaltextmraquosterrifnl061297 5-18 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
60 Summary and Conclusions
This section provides the conceptual model developed for the Study Area based on the findings
of the Phase 1A and IB field investigations and the results of the Long-Term Monitoring
Program sampling events
61 Conceptual Model of the Study Area The conceptual model was developed from the collection and analyses of information and data
from the Remedial Investigation (RI) as well as historical information and data A conceptual
model is an overview of the Study Area taking into account all media and their interrelationships
and describes in summary fashion Site conditions as they pertain to contaminant sources and
migration pathways This conceptual model will be used to support the evaluation of potential
remedial alternatives for the Feasibility Study
611 Geology
Geologic data collected during the RI indicate the following
bull Significant surficial or overburden deposits encountered in the Study Area are till
and glacial deposits referred to as stratified drift
bull The till is relatively dense and is comprised of a fine sandy matrix with abundant
gravel cobbles and boulders The till was encountered directly above bedrock at
most locations at thicknesses of 10 to 20 feet with the thickest accumulations
located along the topographic (bedrock) high in the central area of the Site
bull The stratified drift typically overlies the till or bedrock and consists of poorly to
well sorted deposits of gravel sand and silt Grain size analyses indicate that the
stratified drift is primarily comprised of fine to coarse sands with lesser amounts
of silt and fine gravel The stratified drift thickness varies from less than a few
feet in upland areas to as much as 70 feet in the vicinity of Mill Brook
bull Bedrock within the Study Area consists of grey fine- to medium-grained gneiss
with varying contents of amphibolite biotite and hornblende The bedrock
surface is characterized by a large slope and dips to the northwest and west-
southwest from a bedrock high located about 400 feet southeast of the Former
Seepage Bed The total bedrock surface relief in the Study Area approaches 100
feet
5797wpdocsgalluprifinaltejctmasterri fhl061297 6-1 QfT Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull Geophysical investigations (seismic refraction and magnetometer surveys)
conducted in the vicinity of the Former Seepage Bed did not reveal evidence of
one or two suspected discrete bedrock faults Rather the bedrock in the central
portion of the Site may be more accurately characterized as a series of
interconnected (to varying degrees) fractures and faults
^
612 Hydrogeology
Data regarding hydrogeologic conditions are summarized as follows
Hydraulic Conductivity
bull Across the Study Area test results indicate that the hydraulic conductivity
of the shallow overburden deposits averages approximately 0001
centimeters per second (cms) while the mean hydraulic conductivity for
the deep portion of the aquifer is about 0005 cmsec A mean hydraulic
conductivity of about 0037 cms is more representative of coarser-grained
deposits in the middle to lower portions of the overburden aquifer
northwest of the railroad tracks where the saturated thickness increases to
almost 70 feet
bull The mean hydraulic conductivity of the till (000047 cms) is a factor of
ten less than the average for the stratified drift deposits in the lower
portion of the aquifer and varies between 00002 and 0002 cms
Although the hydraulic conductivity of the till indicates that it is less
permeable and hydrogeologically distinct from the overlying stratified drift
deposits the hydraulic conductivity contrast is not large enough to
significantly alter groundwater flow directions or rates
cir
bull The mean bedrock hydraulic conductivity (000018 cms) is a factor of 25
lower than the average for the coarse-grained stratified drift Due to the
heterogeneous nature of fracture sizes and interconnectivity and their
associated nonlinear effect on groundwater flow rates the hydraulic
conductivity of the bedrock can be expected to be highly variable
throughout the Study Area
5797wpdocsgalluprifinaltextmasterrifhl061297 6-2 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
Groundwater Flow
bull The overburden aquifer is the preferred pathway for groundwater transport
of dissolved constituents This conclusion is supported by the hydraulic
conductivity test results and observations that an upward groundwater
flow component from bedrock to overburden exists throughout most of the
Study Area VOC detections in bedrock wells are believed to be caused
by vertical dispersion in the upper portion of the fractured bedrock
bull Because the unconsolidated deposits become unsaturated in the vicinity of
the Former Seepage Bed discussions of groundwater flow in overburden
are naturally divided into northern and southern portions of the Study
Area
bull Overburden groundwater flow south of the Former Seepage Bed is
generally from east to west at an average hydraulic gradient of 001 feet
per foot (vertical change in piezometric head per horizontal distance) and
is strongly influenced by the bedrock surface and drainage to the wetlands
and stream west of the railroad tracks The saturated thickness in this
area increases from zero near the bedrock high (northeast corner) to more
than 60 feet near the railroad tracks
bull Three distinct zones of overburden groundwater flow exist in the northern
Study Area In the area between the Former Primary and Secondary
Disposal Area and the Former Seepage Bed groundwater flow is largely
through till deposits and toward the north-northwest The hydraulic
gradient in this area is steep (about 003 feet per foot) and strongly
influenced by the dip of the bedrock surface and the lower hydraulic
conductivity of the till deposits The saturated thickness increases from
zero south of MW109 to 20 to 30 feet near the former disposal areas
North-northwest of these areas the hydraulic gradient lessens significantly
to a range of 00003 to 00007 feet per foot (factor of 40 to 100
reduction) North and northeast of Mill Brook the hydraulic gradient is
about 0007 feet per foot
bull Available data indicate that in the northern Study Area overburden
groundwater flow north-northwest of the Former Primary and Secondary
Disposal Areas exhibits a strongly convergent pattern The flow
5797wpdocsgalluprifinaltextmlaquosterriftU061297 6-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
converges from the east-northeast and southwest toward a centerline
generally defined in the downgradient direction by wells MW105
MW102 and MW101 Groundwater flows along this centerline from the
former disposal areas to the northwest Groundwater also flows from the
vicinity of the former Pervel flock plant in southwesterly and westerly
directions toward wells MW116 MW103 and MW101
South of the Former Seepage Bed groundwater flow within the upper
portion of the bedrock unit is primarily in a westerly direction In the
northern Study Area the predominant bedrock flow component is toward
the northwest In both areas the hydraulic gradient is relatively steep and
averages about 002 feet per foot Groundwater flow in bedrock near the
Former Seepage Bed is toward the northwest in the direction of wells
MW113 and MW106 and exhibits no apparent influence from locally
increased fracturing identified from the geophysical investigation and the
hydraulic testing in well MW11 IB
Vertical flow of groundwater is important in the upper several feet of the
bedrock unit Groundwater flow was found to be discharging from
bedrock to overburden at all locations during each of the measurement
dates with the exception of MW109 At MW109 the saturated overburden
thickness is less than a few feet and MW109 is located over a much
higher bedrock elevation than all other wells at which vertical flow from
bedrock was measured
Vertical flow in the overburden aquifer is of increased importance in two
areas in the vicinity of the Former Primary Disposal Area (wells clusters
MW107 MW108 and MW116) where vertical flow directions are
downward and within the upper portion of the aquifer near Mill Brook
where vertical flow is upward
Stream piezometer data and groundwater flow modeling indicate that Mill
Brook generally gains water from the overburden aquifer in the northern
portion of the Study Area
5797wpdoc8galluprifinaltextmraquosterrifhl061297 6-4 Q5T Environmental
Gallups Quarry SuperfimdProject - Remedial Investigation
613 Nature and Extent of Contamination
6131 Contaminant Source Investigation
The following summarizes the findings of contaminant source investigations during the RI
bull Previous remedial activities have completely removed the waste materials
(intact drums and bulk liquid waste) from the Site
bull The Former Seepage Bed and the Former Secondary Disposal Area
contain little residual contamination from the disposal activities which
occurred in the late 1970s
bull Residual levels of contamination primarily VOC and PCB were detected
in the Former Primary Disposal area In general the highest levels of
VOC are located at or just below the groundwater table in native soils
immediately beneath the fill materials and diminish rapidly with depth
PCB were detected primarily within fill materials
bull Other than the three known former disposal areas and the remains of the
former CTDOT asphalt plant no other significant disposal areas were
found to exist on the Site
6132 Groundwater Quality
Groundwater quality data collected during the Phase 1A program indicate the following
bull No significant groundwater contamination was detected within the
overburden or bedrock units in either the southern Study Area or in the
vicinity of the Former Seepage Bed
bull In the northern Study Area a narrow low to moderate-concentration
VOC plume (primarily TCA and DCE) was detected in the overburden
aquifer extending from the Former Primary Disposal Area to the
northwest towards Mill Brook
bull Comparison of present concentrations with historical data indicate that
concentrations within the VOC plume are significantly decreasing with
time From 1978 through 1995 TCA TCE and PCE concentrations
have decreased on the average by more than a factor of two every two
5797wpdocsgalluprifinaltextnui8terrifhl061297 6-5 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
years This trend appears to have continued through the four 1995
sampling rounds for these as well as other VOC with the exception of
the break down product vinyl chloride Biodegradation and dilution by
rainwater infiltration have been identified as the primary mechanisms
causing the concentration reductions with biodegradation the most
important component
The size and orientation of the VOC plume are in excellent agreement
with the established groundwater flow directions
Available information indicates that the leading edge of the VOC plume
associated with the Former Primary Disposal Area is located between
monitoring well clusters MW102 and MW101 VOC transport rates and
the reduction of TCA and DCE levels to estimated values at MW101
support this conclusion
PCE detections in the downgradient portion of the plume exhibit
inconsistencies with migration from the Site Groundwater pathlines and
time-of-travel estimates indicate that the PCE may be attributable to
contaminant transport from the former Pervel facility located north of the
Site Specifically it is possible that PCE detections at locations MW118
MW116 MW103 MW102 and MW101 may have resulted from
groundwater transport from the vicinity of the former Pervel flock plant
However it is also plausible that the PCE detections at locations MW102
and MW101 are attributable to the former disposal areas
Results of surface watersediment sampling and analyses stream
piezometer measurements and groundwater flow modeling indicate that
some discharge of the shallow portion of the plume into Mill Brook is
occurring There are low-level detections of VOC in the section of brook
intersecting the plume however the concentrations are well below those
reported to cause adverse effects in wildlife Detections downstream
adjacent to the municipal sewage treatment plant and below the confluence
of Fry Brook and Mill Brook are probably attributable to off-site sources
along Fry Brook north of the Study Area
Only one of the bedrock wells (MW105B) indicated elevated levels of
VOC Trace levels of a limited number of VOC were also detected in
5797wpdocsgalluprifinaltextma8terrifhl061297 6-6 QStf Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW102B MW107B MW108B and SW-10 however bedrock is not a
preferred pathway for contaminant migration due to its characteristically
low hydraulic conductivity and the consistent upward component of
ground water flow from bedrock to overburden which exists throughout the
Study Area
5797wpdocsgalluprifinaltextmastemfiil061297 6-7 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
70 References
Alexander M 1978 Biodegradation of Toxic Chemicals in Water and Soil in Proc 176th
National Meeting Miami Beach FL Sept 10-15 v 93 American Chemical
SocietyDivision of Environmental Chemistry
Amtec Engineering 1994 Tecplot Version 6 Belevue WA
Bear J 1979 Hydraulics of Groundwater McGraw-Hill
Beyer WN 1990 Evaluating Soil Contamination US Fish Wildl Serv Biol Rep 90(2) 25
pp July 1990
Bouwer H and Rice RC 1976 A Slug Test Method for Determining Hydraulic Conductivity
of Unconfined Aquifers with Completely or Partially Penetrating Wells Water Resources
Research vol 12 no 3 pp 423-428
Boynton GR and Smith CW 1965 Aeromagnetic map of the Plainfield quadrangle New
London and Windham counties Connecticut US Geological Survey Geophysical
Investigations Map GP-541 scale 124000
Brusseau ML 1996 Evaluation of Simple Methods for Estimating Contaminant Removal by
Flushing Groundwater V 34 No 1 pp 19-22
CTDEP 1986 Water Quality Classification Map for the Thames Southeast Coast and Pawcatuck River Basins Sheet 2 of 2 CTDEP Water Compliance Unit Hartford
Connecticut
Dixon HR 1965 Bedrock geologic map of the Plainfield quadrangle Windham and New
London Counties Connecticut US Geological Survey Geologic Quadrangle Map GQshy
481 scale 124000
Enfield CG and Bengtsson G 1988 Macromolecular Transport of Hydrophobic
Contaminants in Aqueous Environment Groundwater v 26 no 1 pp 64-70
ERT 1988 Preliminary Hazardous Waste and Petroleum Hydrocarbon Contamination Evaluation
of the InterRoyal Property Plainfield CT
5797wpdoc8galluprifinaltextmasterrifhl061297 7-1 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
ESE 1994 Gallups Quarry Superfund Project RIFS Work Plan Phase 1A (Prepared by Haley
amp Aldnch Inc Finalized by ESE)
ESE 1995 Initial Site Characterization Report March 1 1996
ESE 1995a April 1995 Long-Term Monitoring Report July 28 1995
ESE 1995b July 1995 Long-Term Monitoring Report October 27 1995
ESE 1996a Long-Term Monitoring Program - Data Report February 1996 Sampling Event
June 19 1996
ESE1996b Long-Term Monitoring Program - Data Report May 1996 Sampling Event
September 24 1996
ESE 1996c Long-Term Monitoring Program - Data Report August 1996 Sampling Event
December 18 1996
ESE 1997a Long-Term Monitoring Program - Data Report November 1996 Sampling Event
March 31 1997
ESE 1997b Long-Term Monitoring Program - Data Report February 1997 Sampling Event
May 21 1997
Fitchko J 1989 Criteria for Contaminated SoilSediment Cleanup Pudvan Publishing
Company Northbrook IL
Freeze RA and Cherry JA 1979 Groundwater Prentice-Hall Inc Englewood Cliffs
New Jersey
Freyberg DL 1986 A Natural Gradient Experiment on Solute Transport in a Sand Aquifer 2
Spatial Moments and the Advection and Dispersion of Nonreactive Tracers Water
Resources Research Vol 22 pp 2031-2046
Fuss and ONeill Inc 1979 Evaluation of a chemical waste disposal area Tarbox Road site
Plainfield Connecticut January 1979
5797wpdocsgalluprifinaltextmlaquoraquotemfhl061297 7-2 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Gelhar LW Montogluo A Welty C Rehfeldt KE 1985 A Review of Field-Scale
Physical Solute Transport Processes in Saturated and Unsaturated Porous Media Electric
Power Research Institute Report No EA-4190
Geraghty amp Miller Inc 1989 Aqtesolv Aquifer Test Solver Version 11 Reston VA October
1979
Hansch C and AJ Leo 1979 Substituent Constants for Correlations Analysis in Chemistry
and Biology John Wiley amp Sons New York
Hem JD 1989 Study and Interpretation of the Chemical Characteristics of Natural Water (3rd
Edition) USGS Water-Supply Paper 2254 US Government Printing Office
Washington DC
HRP Associates Inc 1993 Addendum to Groundwater Monitoring Report Former Pervel
Industries Flocking Plant March and June 1993 Sampling Events HRP Associates
Inc Plainville Connecticut
Karickhoff SW DS Brown and TA Scott 1979 Sorption of Hydrophobic Pollutants on
Natural Sediments Water Research Vol 13 pp 241-248
Lyman WJ Reehl WF Rosenblatt DH 1982 Handbook of Chemical Property
Estimation Methods-Environmental Behavior of Organic Compounds McGraw-Hill
Metcalf amp Eddy 1993 Final Data Summary Report START Initiative Gallups Quarry Plainfield Connecticut
Morel MM 1983 Principles of Aquatic Chemistry John Wiley amp Sons
Prior T Eaton L and Sperduto M 1995 Habitat Characterization for Gallups Quarry
Superfund Site Plainfield Connecticut United States Department of Interior Fish and
Wildlife Service New England Field Offices Concord NH
Reed PB 1988 National List of Plant Species That Occur in Wetlands Connecticut US Fish
amp Wildlife Service Washington DC NERC-881807 105p
Robertson WD Cherry JA Sudicky EA 1991 Groundwater Contamination from Two
Small Septic Systems on Sand Aquifers Groundwater v 29 no 1 pp 82-92
5797wpdocsgalluprifinaltextmlaquoraquoterrifhl061297 7-3 QST Environmental
Gallups Quarry SuperJUnd Project - Remedial Investigation
Schincariol RA and Schwartz FW 1990 An Experimental Investigation of Variable Density
flow and Mixing in Homogeneous and Heterogeneous Media Water Resources Research
v26 no 10 pp2317-2329
Schwille F 1988 Dense Chlorinated Solvents in Porous and Fractured Media translated from
German and Edited by JF Pankow Lewis Publishers Chelsea Michigan
Shacklette HT and Boerngen JC 1984 Element Concentrations in Soils and Other Surficial
Materials in Conterminous United States USGS Professional Paper 1270 US
Government Printing Office Washington DC
Sudicky EA Cherry JA and Frind EO 1983 Migration of Contaminants in Groundwater
at a Landfill A Case Study 4 A Natural Gradient Dispersion Test J Hydrology v 63
pp 81-108
US EPA 1986 Quality Criteria for Water Office of Water Regulations and Standards
Washington DC USEPA 4405-86-001 (NTIS PB87-226759)
US EPA 1987 A Compendium of Superfund Field Operations Methods US EPA540Pshy
87001 (NTIS No PB88-181557)
US EPA 1988 Interim Final Guidance on Remedial Actions for Contaminated Groundwater at
Superfund Sites US EPA Washington DC
US Fish and Wildlife Service 1995 Habitat Characterization for Gallups Quarry Superfund
Site Plainfield CT Concord NH 16 p
USGS 1993 Geohydrology of the Gallups Quarry Area Plainfield CT
5797wpdocsglaquolluprifinaltextmasterrifhl061297 7-4 QST Environmental
SOURCE PLAINFIELD75 MINUTE
124000
0 A 2
SCALE IN MILES
OONNECnCPT
OlMDIMNGLE LOCATION
CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP SERIES 1983
410 Amherst Street Nashua NH 03063
(603) 689-3737
GALLUPS QUARRY SUPERFUND PROJECT PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 1-1
SITE LOCATION MAP DRAWING NAME 1LOCDWG miE NUMBER 7194-138
SCALE AS SHOW [REVISION 0 I DRAWN BY PAD IPATE gg97
N
500 0 500
SCALE IN FEET
LOT NUMBER OWNER
1 C STANTON GALLUP 2 KENNETH R MOFFITT 3 INTERMARK FABRIC CORP 4 NORMAN ATLAS 5 FREDERICK BARRETT 6 WILLIAM ROPERANNE OWENS 7 ROBERT GLUCK
TILCON MINERALS INC 9 TOWN OF PLAINFIELD 10 ROBERT GLUCK 1 1 STANTON GALLUP 12 - 15 EDWARD DUNCAN 16 ELAINE M NILSON 17 ADOLPH SHAGZDA 18 ANTHONY FATONEJOSEPH FATONE 19 NANCY LAMIRANDE 20 KENNETH R MOFFITT 21 CONNECTICUT DOT 22 ST JOHNS CHURCH 23 DOROTHY CARON 24 ALFRED AND EVELIN RIENDEAU 25 PAUL GELINAS AND JOAN BURNORE 26 ALBERT SR AND ANN WILCOX
LEGEND
D LOT NUMBER
-- WATERCOURSE GALLUPS QUARRY SITE
PROPERTY BOUNDARY
NOTES
BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM - CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
410 Amherst Street Nashua NH 03063
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 1-2 1000
PROPERTY BOUNDARIES AND ADJACENT LANDOWNERS
DRAWING NAM^ PROPBNDDWG |^LE NUMBER 7194 138 SCALE AS SHOW^REVISION 0 |pRAWN BY PAD loATE 5997
GB
N
LEGEND
WATERCOURSE
TO PACKERS POND (CUSS CBc)
APPROX 1 MILE WEST OF SITE
PROPERTY
CLASS Be
BOUNDARY
SURFACE WATER
CLASS BA SURFACE WATER
CLASS GE GROUNDWATER
CLASS GEGA GROUNDWATER
NOTES
1 BASE PLAN PROVIDED BY USEPADATED 14 OCTOBER 1993
DRAWING NO 707600
2 HORIZONTAL DATUM shy CONNECTICUT STATE PLANSYSTEM NORTH AMERICAN
COORDINATE DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROMPLAINFIELD TAX ASSESSORS OFFICE
TOWN OF
4 UNLESS OTHERWISE INDICATEDCLASSIFICATION IS GA
CONNECTICUT GROUNDWATER
410 Amherst Street Nashua MH 030G3
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
500 0
SCALE IN
500
FEET
1000 FIGURE 1-3
CONNECTICUT SURFACE AND GROUNDWATER CLASSIFICATION ZONES
DRAWING NAME SOILTYPEDWG
SCALE AS SfcWN [RFVISION 0 l o R A W N B Y D-fB FILE NUMBER 7194 138
G1097
LEGEND
WATERCOURSE
PROPERTY BOUNDARY
LOCATION OF PREVIOUSLY INSTALLED MONITORING WELL
NOTES
1 BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM shy CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
410 Amherst Street Nashua NH 03063
(603) 869-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
- REMEDIAL INVESTIGATION REPORT
500 0 500 1000 FIGURE 1-4
GROUNDWATER MONITOR WELLS INSTALLED BY SCALE IN FEET FUSS amp ONEILL IN 1978 AND USGS IN 1993
DRAWING NAME SWMAGDWG FILE NUMBER 7194 138
SCALE A3 SHQHW [REVISION 0 [DRAWN BY DJB |DATE 51097
bull- - n V i _raquo-A raquoraquobull bull Jpoundi _
SOURCE PLAINFIELD CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP 75 MINUTE SERIES 1983
124000 410 Amber atNashua NH
Street 03063
(603) 889-3737
0 GALLUPS QUARRY SUPERFUND PROJECT
SCALE IN MILES PLAINFIELD CONNECTICUT REMEDIAL INVESTIGATION REPORT
FIGURE 1-5 COHNgOICOT
SITE LOCATION MAP AND NEARBY INDUSTRIAL PROPERTIES
QURANGLE LOCATION NAME LOCMAPXXDWG FILE NUMBER 7194138
SCALE AS SHOWN [REVISION 0 I DRAWN BY CBG loATE 5997
1450
FIGURE 3-1 GROUNDWATER ELEVATIONS MW-101
1420 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-101S MW-101TT MW-1 01 T
FIGURE 3-2 GROUNDWATER ELEVATIONS MW-102
1450shy
OJ 2
LLJ 1445shy
O CO
1440shyMW-102B WAS NOT INSTALLED UNTIL PHASE IB
1435
LLJ _l HI DC LJJ
I QZ
O cc CD
1430shy
1425shy
1420 010195
1 041195
1 072095
1 102895 020596
I 051596
I 082396
1 120196
1 031197 061997
DATE
MW-102S MW-102TT ---pound-- MW-102B
FIGURE 3-4 GROUNDWATER ELEVATIONS MW-104
1450
CO
LLJ 1445shy
O CO lt |mdash 1440shy
lt 1435shy
LLJ _J LLJ
CC LLJ 1430shy
I Q Z D O CC C5
1425
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-104S MW-104TT
FIGURE 3-5 GROUNDWATER ELEVATIONS MW-105
1450
CO2 LLJ 1445shy
O CO
1440shy
1435shy
LLI
LU tr QJ 1430shy
I Q
D O cc O
1425shy
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-105S MW-105TT MW-105T -X- MW-105B
1450
FIGURE 3-6 GROUNDWATER ELEVATIONS MW-106
1420 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-106S MW-106TT
1450
FIGURE 3-3 GROUNDWATER ELEVATIONS MW-103
1415 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-103S MW-103TT
FIGURE 3-7 GROUNDWATER ELEVATIONS MW-107
1490
CO
x- -X
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-107S MW-107TT MW-107T -Xshy MW-107B
FIGURE 3-8 GROUNDWATER ELEVATIONS MW-108
1465shy
(02 LU
1460shy
O CO
1455shy
1450shy
LU
LU
CC LU
lt
1445shy
1440shy
Q
mdashJocc O
14j vshy^
1430 010195
1 041195
1
072095 1
102895 T T
020596 051596
DATE 082396
1 120196 031197 061997
MW-1083 MW-1 08TT MW-1 08B
1580
FIGURE 3-9 GROUNDWATER ELEVATIONS MW-109
(0 1575shy
1530 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-109S MW-109B
1470
FIGURE 3-10 GROUNDWATER ELEVATIONS MW-110S
1450 i 1 i i i 1 r 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-110S
1610
FIGURE 3-11 GROUNDWATER ELEVATIONS MW-111B
1530 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-111B
1590
FIGURE 3-12 GROUNDWATER ELEVATIONS MW-112
lt) 1580shy
149 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-1123 MW-112T MW-112B
FIGURE 3-13 GROUNDWATER ELEVATIONS MW-113
1510shy
2UJ
O m lt
1500shy
1490shy
1480shy
LU _l LJJ
CC LU
1470shy
1460shy
Q
OCC O
145degH
1440 010195 041195 072095
1 102895 020596 051596
DATE 082396
1 120196
1 031197 061997
MW-113S MW-113B
1580
FIGURE 3-14 GROUNDWATER ELEVATIONS MW-114
1460 i r 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-114S MW-114TT
150
FIGURE 3-15 GROUNDWATER ELEVATIONS MW-115
1465 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-115S MW-115TT --pound-- MW-115B
1455
FIGURE 3-16 GROUNDWATER ELEVATIONS MW-116
1425 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-116S MW-116T
FIGURE 3-17 GROUNDWATER ELEVATIONS MW-117
1480shy
CO
LJJ gto CD
1475shy
1470shy
LU LU
CC LU
1465shy
WELLS AT THIS LOCATION WERE NOT INSTALLED UNTIL PHASE 1B
O z D O CC (5
1460shy
1455 010195
1 041195 072095
I 102895
1 1020596 051596
DATE
1 082396 120196 031197 061997
MW-117S MW-117TT
FIGURE 3-18 GROUNDWATER ELEVATIONS MW-118
1465shy
LU 1440shy
LLJ
CC LU 1435shy WELLS AT THIS LOCATION WERE
I Q Z D O CC CD
1430shy
1425shy
NOT INSTALLED UNTIL PHASE 1B
1420 010195
1 041195
I 072095
1 102895 020596
1 051596
DATE 082396 120196 031197 061997
MW-118S MW-118TT
FIGURE 3-19 GROUNDWATER ELEVATIONS MW-119
1475shy
CO2 LJJ
1470shy
o m
1465shy
1460shy
UJ_i UJ cc LJJ
1455
1450shy
WELLS AT THIS LOCATION WERE NOT INSTALLED UNTIL PHASE 1B
Q Z
O cc O
1445shy
1440 010195 041195
1 072095
I102895
I I 020596 051596
DATE
1 082396
i 1 201 96 031 1 97 061 997
MW-119S MW-119TT
1455
FIGURE 3-20 GROUNDWATER ELEVATIONS SW-3SD
1425 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
SW-3S SW-3D
Originals in color
VERTICAL
PROJECTED FOOTPRINT of FORMER PRIMARY
DISPOSAL AREA
MILL BROOK
NOTES (1)
(2)(3)
THE SAME CONTOUR INTERVALS ARE USED FOR THE SHALLOW AND DEEP MAPS
WATER LEVEL DATA COLLECTED 2-2-95 VERTICAL EXAGGERATION = 10X
410 Amherst Street THIS FIGURE SHOWS ONLY THE PREDOMINANT OVERBURDEN GROUNDWATER FLOW PATHWAYS WHICH ORIGINATE Nashua NH 03063 IN THE VICINTY OF THE FORMER PRIMARY DISPOSAL AREA AS VIEWED FROM THE EAST (603) 889-3737
ALTHOUGH THIS DEPICTION IS BAStU ON PlEZOMETRlC HEAD OAiA (MEASURED ON FEBRUARY 2 1335) THIS FiGURE DOES NOT SHOW EVERY POSSIBLE FLOW PATHWAY WITHIN THE OVERBURDEN AQUIFER THE UPPER SURFACE REPRESENTS THE SURFACE OF THE WATER TABLE THE LOWER SURFACE REPRESENTS GALLUPS QUARRY SUPERFUND SITE A PLANE DEFINED BY THE PIEZOMETRIC HEAD AS MEASURED IN WELLS WHICH ARE SCREENED IN THE LOWER PORTION OF THE OVERBURDEN AQUIFER THE LOWER PLANE DOES NOT REPRESENT THE LOWER BOUNDARY OF THE OVERBURDEN AQUIFER AND NEITHER PLANE IS GEOLOGICALLY SPECIFIC PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 3-21
PREDOMINANT OVERBURDEN GROUNDWATER FLOW PATHWAYS IN NORTHERN PORTION OF STUDY AREA
DRAWING NAME FLOWPATHDWG IFILE NUMBER 7194 138
SCALE NT5 JREVSION 1 JDRAWN BY CBG [DATE 6-9-97~
lt 4 Original includes color coding
10s r SW-17SandMW105S Ho5 SW-17D and MW105TT
P 1 V |
1deg4 i
4 mI U 5 k 4 3
i i f J |103 1I Un |
|io2 bull m2
bull I U = i ii gtv o r
BDL mdasha I bullM BDL a i i c CM ltD 0 ltj at agt c c at at T c I 1 I i i i
SW-13 c MW105S I10s pound
1I Un =
m4
104 I U sect
J 1I 3 bull PCE -m
H103| IU sect bull TCA
2 ^ TCE 102
m
I bull 1 2-DCE A i 1
T VINYL CHLORIDE 1 0 ^h
bull A1
10deg BDL = BELOW DETECTION LIMIT 10deg 1 U = V 3 X
=
ni-M ^ ^ ^ laquote BDL 0 V o0 CV tfi _ CO CXgt o0 ogt ogt 2 C oraquo oraquo cn O) O lt C
i- r- -3 4 1 1995
MW105TT MW107TT 105 105
E pound
i shy104
2 = 104 I = ^^to^f^P 410 Araherst Street bull^OJfcCfe Nashua NH 03063 103 103 ^raquo^^^j^ (603) 889-3737 f bull 1
- T T T shy ~ A102 i1 bull bull S 102
GALLUPS QUARR y SUPERFUND SITE I 1
PLAINFIELD CONNECTICUT REMEDIAL INVEi iTIGATOJV REPORT 10 101
i 1 FIGU RE 5 110deg i = 10deg
BDL laquo BDL VOC CONCENTRATION CHANGES VERSUS TIME M
^ i DOWNGRADIENT FROM FORt ilER PRIMARY DISPOSAL AREA sect o ^ O
^
-5lt 5amp -s= z1
1995 1995
Original includes color coding
CO
NC
ENTR
ATIO
N (
ppb)
IU sect MW102S
s 105 MW102TT
104 1 i 104
103 1 103
102 I I A sect 102
1
A
T
1 101
10deg i 10deg
nni BDL +shytr a O o
1995 1995
bull PCE
bull TCA A TCE
bull 12-DCE
T VINYL CHLORIDE
MW101TT 105
104
103
102
10deg
BDL
1995
410 Amhersl Street Nashua NH 03063
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 5-2
VOC CONCENTRATION CHANGES VERSUS TIME DOWNGRADIENT PORTION OF PLUME
BDL = BELOW DETECTION LIMIT
s
104 tmdash a IU I
1 IU103 U-o 1F= E
i 105 to2 tmdash r 1 1deg1 i~ deg 10degL
BDL Emdash oS
105 i
104 i
103 i
102 bull
101 1
10deg
BDL 0S
105 9
104 B
103 I
102 i
101
10deg 1
BDL OCOogt
^ 00 ogt
^ra lt cltJgt
C O 0 0
0gt
MW-A
4 bull
1 1 1
co 01
MW-B
_J 1 1
1
i CO
8)
MW-C
11 1
lt lt
CO CO ogt
bullbull
laquoftr i i bull i
mn
Tbull1
bullbull
bull i
9
bull
bullM bullM bullbull- 1
egt lt t a) a
aai Tshy^
WM cN gjcI) lt J1
bull 1
bull 11 1
MM bullMl bullfr- 1
c4 0aigt C
t bullgt araquo lt raquo
T ^
Original includes color coding
10 |
-iM 10 s
-irvS 10 |
nn2 10
bullm1 bull
1UJ
oni AZs
^^^f
MW116T
A a
A =J =3
1995
bull
bullA
PCE
TCA
TCE
1 2-DCE
sect
1
s
I I 1
A gti
T VINYL CHLORIDE
BDL = BELOW DETECTION LIMIT
410 Amherst Street bull^OJUV^ Nashua NH 03063 ^raquo^^ ^jj^ (603) 889 3737
nmranmini x
GALLOPS QlARRy SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 5-3
VOC CONCENTRATION CHANGES VERSUS TIME AREA NORTH-NORTHEAST OF PLUME
I Original includes color coding
SW-17S MW102S and MW102TT
410 Amherst Street Nashua NH 03063
bull PCE (603) 889-3737
bull TCA A GALLUPS QUARRY SUPERFUND SITE TCE
PLAINFIELD CONNECTICUT REMEDIAL INVESTIGATION REPORT
BDL = BELOW DETECTION LIMIT
FIGURE 5-4
EVALUATION OF BIODEGRADAT10N AND RAINWATER DILUTION RATES IN VOC PLUME
(D NOTE FORWELLS MW102S and MW102TT ONLY JANUARY and NOVEMBER 1995 DATA ARE PLOTTED
Remedial Investigation
Gallups Quarry Superfund Project
Plainfield Connecticut
Submitted to
US EPA - Region I
Boston Massachusetts
Prepared by
QST Environmental
(formerly Environmental Science amp Engineering Inc)
Nashua New Hampshire
June 1997
QST Project No 71941380430
Gallups Quarry Superfund Project - RI Executive Summary
Executive Summary
EI Purpose of the Report This document presents the Remedial Investigation (RI) Report which was completed for the
Gallups Quarry Superfund Site (Site) pursuant to the requirements of US Environmental Protection Agency (EPA) Administrative Order by Consent Docket Number 1-93-1080 (Order)
issued September 7 1993 The Site is a former sand and gravel quarry and is located on Tarbox
Road in the Town of Plainfield Connecticut (see Figure E-l) The Study Area includes the Site
as well as areas west and north of the Site
Investigation of the Site was initiated in 1978 when unlicensed waste disposal operations were
discovered at the property Emergency clean-up operations were conducted in three disposal
areas by the Connecticut Department of Environmental Protection (CTDEP) in April 1978
(Metcalf amp Eddy 1993) Following the initial clean-up effort a series of surface and subsurface
sampling events were performed by the CTDEP the Connecticut Department of Health (CTDOH) and US Environmental Protection Agency (EPA) Based primarily on the detection of
groundwater contamination the Site was listed on the National Priorities List (NPL) on October 4 1989 During 1992 and 1993 EPA conducted a limited investigation through the Superfund
Technical Assessment amp Response Team (START) initiative in an effort to expedite the
completion of the Remedial InvestigationFeasibility Study (RIFS) The requirements of the
Order as well as data included in the START report (Metcalf amp Eddy 1993) provided the
framework for the Remedial Investigation
This RI Report is the sixteenth major deliverable under the Order The first major deliverable
the Remedial InvestigationFeasibility Study Work Plan - Phase 1A was finalized and submitted to EPA on August 29 1994 QST Environmental (formerly Environmental Science amp Engineering Inc (ESE)) finalized the Work Plan and has prepared all of the other deliverables
The Phase 1A field investigation was completed in January 1995 The second major deliverable
the Phase 1A Data Report dated March 24 1995 was submitted to EPA following completion of
the Phase 1A field investigation The findings of the Phase 1A Investigation were described in
the Initial Site Characterization Report (ISCR) which was finalized and submitted to EPA on
March 1 1996 A Work Plan for the Phase IB field investigation was finalized and submitted on
October 11 1995
In addition to the Phase 1A field investigation the Phase 1A Work Plan also described the Long-
Term Monitoring Program which was initiated upon completion of the Phase 1A field
investigation The Long-Term Monitoring Program includes the quarterly collection and analysis
of groundwater and semi-annual collection and analysis of surface water and nearby residential
well samples The Phase IB field investigation commenced on October 12 1995 Following the
5797wpdocsglaquollupfsfinlaquoltextexecnimmri060997 E-l QST Environmental
SOURCE PLAINFIELD CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP 75 MINUTE SERIES 1983
410 Amherst Street 124000 Nashua NH 03063
(603) 889-3737
0 GALLUPS QUARRY SUPERFUND PROJECT
PLAINFIELD CONNECTICUT SCALE IN MILES REMEDIAL INVESTIGATION REPORT
comacncur FIGURE E-l
SITE LOCATION MAP DRAWING NAME ELOCDWG FILE NUMBER 7194-138
QUADRANGLE LOCATION
SCALE AS SHOWN REVISION 0 I DRAWN BY PAP [DATE 5997
Gallups Quarry Superand Project - RI Executive Summary
completion of drilling activities the Phase IB groundwater sampling task and the fourth quarter
1995 Long-Term Monitoring sampling event were performed simultaneously in November 1995
Seven Data Reports have been submitted to the EPA for the following Long-Term Monitoring
Program sampling events the second and third quarters of 1995 all four quarters of 1996 and
the first quarter of 1997 (ESE 1996a 1996b 1996c 1997a 1997b) The draft RI Report was
submitted to EPA on March 15 1996 (and revised and resubmitted October 22 1996) and included the results of the fourth quarter of 1995 sampling event On March 29 1996 the
following two deliverables were submitted to EPA Development and Initial Screening of Alternatives Report and Detailed Analysis Work Plan The draft Feasibility Study was submitted
to EPA on January 27 1997 This RI Report describes the methods and findings of both the Phase 1A and IB field studies and includes data collected during the April July and November
1995 February May August and November 1996 and February 1997 Long-Term Monitoring
sampling events
E2 Site Background E21 Area Description
The 29-acre Gallups Quarry Site is located on the north side of Tarbox Road in the Town of
Plainfield Windham County Connecticut The Site which is currently vacant is bounded by
wooded areas and wetlands associated with Mill Brook (which flows from east to west
approximately 250 feet north of the Site) single-family residences and several commercial
properties Approximately 700 feet north of the Site on the opposite side of Mill Brook is an industrial park which contains an Intermark Fabric Corporation facility (formerly the Pervel
Industries flock plant) and a Safety Kleen Corporation accumulation facility Further north of the
industrial park are several presently vacant mill buildings which were previously occupied by various manufacturers including Pervel Industries and the InterRoyal Corporation The Plainfield sewage treatment plant which discharges to Mill Brook and its major tributary (Fry Brook) is
located approximately 1800 feet northwest of the property
E22 Site Operational History
Limited information is available regarding the early operational history of the Site Historical
aerial photographs and records at the Town of Plainfield Assessors office indicate that in 1951
the Site was owned by a Mr Johnson and that some quarrying activities were underway in the
southern portion of the Site In 1964 the Site was purchased by C Stanton Gallup Although
detailed usage of the Site from 1964 through 1977 is poorly documented records indicate that the
Site was used as a source of aggregate and was occupied by the Connecticut Department of
Transportation (CTDOT) who were operating an asphalt batching plant
5797WTgtdocsgallupfsfinltextexec8ummri060997 E-3 QST Environmental
Gallups Quarry Superfund Project - RI Executive Summary
As a result of complaints from neighboring residents the CTDEP and the Connecticut State
Police initiated an investigation of the Site in January of 1978 The CTDEP investigation
concluded that the Site was used from the summer of 1977 until December 1977 for unlicensed
waste disposal Evidence collected by CTDEP indicates that Chemical Waste Removal Inc
(CWR) of Bridgeport Connecticut transported drummed and bulk liquid waste material to the
Site These materials reportedly included a variety of industrial wastes
Emergency clean up efforts were performed during the summer of 1978 under the direction of the
CTDEP and the Connecticut State Police This involved the removal and off-site disposal of
1584 drums 5000 gallons of free liquid and 2277 cubic yards of contaminated soil from three
distinct locations on the Site The drums as well as liquid waste and contaminated soil were
removed from the Primary and Secondary Disposal Areas located in the northern portion of the
Site Remedial measures performed at the Seepage Bed reportedly located in the central portion
of the Site included the excavation of contaminated soil and in-situ treatment of remaining soils
through the addition of 20 tons of lime A buried inverted dump truck body was also reportedly
removed from the Site In addition to these remedial activities mine detectors were utilized to search for additional buried drums There was no evidence of additional buried drums and it
was believed that all drums were recovered during the cleanup operations
Since the 1978 cleanup operations the Site has been vacant although there are some indications
that the Site has been utilized by trespassers for recreational purposes
E23 Summary of Previous Investigation
ations and sampling events were conducted at the Gallups Quarry Site The significant previous
investigations are as follows
bull A general site investigation performed on behalf of the State of Connecticut (Fuss amp
ONeill 1979) which included the installation of 22 monitoring wells 19 test pits (13
of which were completed as shallow monitoring wells) and the collection of surface
water and sediment samples The investigation was completed within several months
of the States remedial efforts described above Groundwater from monitoring wells
and nearby residential wells as well as surface water from Mill Brook was sampled
several times from the period of July to December 1978
bull Various CTDEP monitoring events for groundwater surface water and sediment
occurred from 1979 until 1993 Sampling events were conducted in October 1979
January and November 1980 April and October 1981 April 1982 and December
1983 CTDEP also performed a biodiversity survey in 1985 in an effort to evaluate
potential impacts to the Mill Brook wetland In addition CTDEP also conducted
sampling anq (analysis of neighboring residential wells in 1992 and 1993
5797wpdocraquogallupf8finlaquoltextexecsummri060997 E-4 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
bull A Hazard Ranking System (HRS) Study was completed in 1987 by NUS Corporation
foi ZPA The Study included the collection of water samples from two existing
moiiitoring wells and three surface watersediment locations
bull A review of historic aerial photographs of the Study Area was performed by the
Bionetics Corporation on behalf of the EPA Photographs dating back to 1951 were
included in the review which was published in 1990 (Bionetics Corp 1990)
bull In cooperation with EPA the USGS performed a geohydrologic investigation at the
Study Area in 1993 This investigation included geophysical surveys (EM-34 and GPR) to characterize various subsurface features One monitoring well was installed
bull In 1993 the US Fish and Wildlife Service performed a field study to characterize the
habitats within the Study Area The study was finalized in 1995
bull Various sampling events were conducted in 1989 and 1993 on behalf of the EPA During these sampling events groundwater from existing monitoring wells and nearby
residential wells as well as surface soil samples were collected for analysis
The significant findings of these investigations are summarized as follows
bull The initial study completed at the Site by Fuss amp ONeill in 1979 concluded that
groundwater in the vicinity of the former disposal areas had been impacted by certain
volatile organic compounds (VOC) and metals A well-defined groundwater plume which contained these various constituents extended in a northwest direction away
from the Site
bull Periodic CTDEP sampling events from 1979-1982 indicated the wells downgradient of
the former disposal areas consistently showed detectable levels of constituents similar
to those disposed of on-site The results of CTDEP sampling events indicated that
nearby residential wells had not been impacted by the Site
bull The USGS study provided an updated geological characterization of the Study Area
and suggested the potential presence of a bedrock fault zone located in the vicinity of
the Former Seepage Bed
bull The results of the 1989 and 1993 sampling events generally confirmed the findings of
previous groundwater quality investigations and indicated that VOC concentrations
decreased significantly in the period between 1982 and 1993
5797wpdocgglaquollupfsfiiultextexecnjmmri060997 E-5 QST Environmental
Gallups Quarry Superfiotd Project - RI Executive Summary
To supplement historical data and data obtained during the Phase 1A field program a CTDEP file
search was performed to obtain information pertinent to groundwater contamination for industrial
properties neighboring the Site The available information indicates that
bull two separate companies Pervel Industries and InterRoyal Corporation operated
manufacturing facilities at locations approximately 2500 feet north of the Site
bull Pervel Industries also maintained a second facility (a fabric flock plant) located
approximately 1000 feet north of the Site across Mill Brook
bull there have been documented releases of 111-trichloroethane (TCA) and toluene at
the northern-most Pervel plant
bull contaminated soil and sediment associated with a 1985 spill of 111-TCA at the
northern-most Pervel facility was stored in an impoundment located on the eastern
(upgradient) side of the Pervel flock plant property
bull the contaminated soilsediment impoundment was located approximately 1000 feet
from the northern end of the Site
bull the results of historical groundwater monitoring at the former Pervel flock plant
located a few hundred feet north of the Site show the presence of elevated
concentrations of several VOC including tetrachloroethene (PCE) and TCA
E3 Summary of Remedial Investigations Phase 1A Field Investigations
In order to maximize the efficiency of the Site characterization program for the Gallups Quarry
Site multiple phases of data collection and evaluation were performed during the Phase 1A field
program Screening level surveys completed during the initial weeks of the field program
utilizing fast-turnaround data generation and evaluation techniques were used to focus data
collection efforts during the latter part of the Phase 1A field program The screening surveys
included
bull A visual site reconnaissance involving transit by foot and direct observations and
photographic documentation of significant features along approximately 39000 feet of
trend lines covering the entire Site
bull Geophysical surveys including electromagnetic terrain conductivity (EM) and
magnetometer surveys along 25-foot spaced trend lines totalling approximately
5797wpdocBgallupf8finaltextexeclaquoummri060997 E-6 Q5T Environmental
Gallups Quarry Superfimd Project - Rl Executive Summary
39000 feet in length and covering the entire Site follow-up EM-31 and
magnetometer surveys and a test pit program in three areas where anomalies were
observed and a seismic refraction survey west of the Former Seepage Bed
bull A microwell survey which included the collection of 126 groundwater samples from
multiple depths at 50 locations within the Study Area field gas chromatograph
analyses of all of these samples for an indicator list of 8 VOC laboratory analyses of
121 of these samples for metals and 12 of the samples for VOC and
bull A soil vapor survey which involved the collection of soil vapor samples from 106
locations throughout the Site and on-site analyses for an indicator list of 8 VOC
Based on these screening level and historical data a groundwater monitoring well installation
sampling and analytical program was designed The program as approved by EPA included the
following
bull The installation of 5 wells at 2 designated background locations These wells include
a shallow overburden and a bedrock well in the northern portion of the Site and two
overburden wells (screened at the water table and in a deeper till horizon) and a
bedrock well in the southern portion of the Site Background soil and groundwater
samples were collected from these locations
bull The installation of 19 wells at seven locations downgradient (northwest) of the Former
Primary and Secondary Disposal Areas to assess and define the boundaries of a
contaminant plume identified during the microwell survey These wells included 17
overburden wells and two bedrock wells
bull The installation of six wells at three locations located north and east of the Former
Primary Disposal Area to assess groundwater quality and flow directions in these
areas These wells included five wells screened in overburden and one in bedrock
bull The installation of two bedrock wells and one overburden well at two locations in the
vicinity of the Former Seepage Bed This included one bedrock well placed within an
inferred bedrock faultfracture zone to assess the zones potential to act as a preferred
contaminant transport pathway
bull The installation of five wells at two locations in the southern portion of the Site to
assess very limited screening-level VOC detections in this portion of the property
These wells include four overburden wells (two shallow and two top-of-till) and one
5797wpdoclaquoglaquollupftfinlaquolte)rtexecraquoummri060997 E-7 QST Environmental
Gallups Quarry Superfund Project - RI Executive Summary
bedrock well In addition six groundwater piezometers were installed to assess groundwater flow directions in the southern portion of the Study Area gtmdashr
Samples from three of the newly installed wells (MW102TT MW106TT and MW116T) were analyzed for Appendix IX parameters Samples from the remaining newly installed monitoring wells and three existing wells (SW-9 SW-10 SW-12) were analyzed for Target Analyte ListTarget Compound List (TALTCL) parameters Twelve nearby residential wells were also sampled for TALTCL parameters (although VOC were analyzed using EPA method 5242) In addition to the monitoring well installation and groundwater sampling program outlined above the following tasks were performed during the Phase 1A field program
bull Air quality monitoring to establish ambient air quality prior to and during the intrusive investigations A total of eight air monitoring stations were established at locations within and at the Site perimeter
bull Water-level measurements were recorded to assess horizontal and vertical groundwater flow directions and aquifer testing (including evaluations of the remaining existing monitoring wells) using slug tests was conducted to assess the hydraulic conductivity of the aquifer
bull Soil boring programs within the three known disposal areas to assess the nature and extent of residual contamination A total of ten soil borings were completed at the three areas Each boring was continuously sampled and terminated at auger refusal Selected samples were submitted for laboratory analysis for TALTCL parameters based on lithology depth and photoionization detector (PID) headspace readings as set forth in the Work Plan
bull Surface watersediment sampling was performed at 17 locations including Mill Brook Fry Brook Packers Pond and in an unnamed pond on Tarbox Road just south of the entrance to the Site In addition wetland soil samples were collected from 10 locations within the Study Area All samples were submitted for analysis for TALTCL parameters
bull Federal and State jurisdiction^ wetland delineations were performed
Phase IB Field Investigations The data collected during Phase 1A was supplemented with the following additional investigative activities conducted during the Phase IB field investigation
5797wpdocsgallupfsfiMltextexecsummri060997 E-8 QST Environmental
Gallups Quarry Superand Project - RI Executive Summary
bull Quantitative air monitoring for site-specific compounds in the vicinity of the Former
Prirary Disposal Area
bull Collection and analysis of soil samples from six additional soil borings in the Former
Primary Disposal Area to more fully characterize the extent of residual VOC and PCB
contamination
bull The installation of seven additional groundwater monitoring wells and one additional
piezometer to obtain additional groundwater data from the downgradient portion of the
plume and from the northnorthwest portion of the Site The monitoring wells
included (3) two well clusters and (1) bedrock well
bull Collection of groundwater samples from each new monitoring well and from five
existing wells on the former Pervel facility and analysis of these samples for VOC to confirm the downgradient extent of the plume originating in the Former Primary
Disposal Area and
bull The performance of constant flow tests consisting of short-term pumping tests on selected groundwater monitoring wells to supplement Phase 1A hydraulic conductivity
data so that groundwater velocities and transport rates and aquifer yield could be
more accurately determined
Long-Term Monitoring Program
A Long Term Monitoring Program was initiated upon completion of the Phase 1A field investigation The Long-Term Monitoring Program includes the quarterly collection and analysis
of groundwater and semi-annual collection and analysis of surface water and nearby residential
well samples Data from eight quarterly sampling rounds (performed in April July and
November 1995 February May August and November 1996 and February 1997) are presented
and discussed The Conceptual Model discussion is based on the 1995 quarterly sampling rounds
Any minor adjustments to the Conceptual Model resulting from later monitoring rounds are
addressed in the FS
E4 Conceptual Model of the Study Area E41 Physical Characteristics E411 Physiography
The Site is located along the eastern border of the Quinebaug Valley Lowland The region is
characterized by relatively low relief and numerous glacial features The regional landscape is
5797wpdoc8glaquollupfBfinaltextexecraquoummri060997 E-9 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
significantly influenced by the structure of the underlying crystalline metamorphic bedrock The
topography of the Site is highly irregular primarily due to past quarrying operations including
numerous overgrown mounds of earthen materials and excavated depressions The ground
surface on the Site generally slopes from the east to the west and to a large degree is controlled by the underlying bedrock surface North and west of the Site the ground surface elevation
decreases in the Mill Brook floodplain which is described as a low lying heavily vegetated
wetland
E412 Geology
The overburden deposits in the area consist of materials deposited as a result of glacial processes during the Pleistocene epoch A range of glacially-derived materials including till meltwater or
stratified drift deposits and post-glacial deposits of floodplain alluvium comprise the major
surficial geologic units in the vicinity of the Site The significant surficial deposits encountered
within the Study Area during the RI are till and stratified drift Stratified drift deposits can be
further broken down into coarser-grained or finer-grained components The Study Area is
dominated by coarser-grained deposits which represent various ice-contact or outwash features associated with the retreat of the ice-mass Finer-grained components also exist to a limited
extent within the Study Area and are the result of lacustrine deposition which occurred when
low-lying areas were inundated by a glacial lake Much of the Sites overburden geology
represents the transition of depositional environments as the glacier progressively retreated from
the area Although alluvial floodplain deposits were encountered at locations within the present
Mill Brook floodplain the significance of these deposits is minor
The thickness of the stratified drift deposits range from non-existent in the vicinity of bedrock
outcrops in the eastern portion of the Site to approximately 70 feet The overburden thickness
increases in response to a decrease in the elevation of the bedrock surface Till was encountered just above the bedrock surface at nearly every location The till horizon ranges in thickness from
approximately 10 to 20 feet with the thickest accumulations located along bedrock highs
Surficial exposures of glacial till were observed on the Site The till is relatively dense and is
comprised of a fine sandy matrix with abundant gravel cobbles and boulders
Bedrock in the vicinity of the Site mapped as a lower member of the Quinebaug Formation
consists of hornblende gneiss biotite gneiss and amphibolite and is strongly faulted and folded
exhibiting varying degrees of mylonitization Geophysical surveys performed prior to and during
the Phase 1A field program indicate that a northwest-trending fracture zone may extend across the
central portion of the Site Based on the drilling program depths to bedrock range from zero to
83 feet below ground surface within the Study Area Bedrock elevations are greatest in the
eastern central portion of the Site and decrease to the north and west and to a lesser degree to
the south
5797wpdocsgallupfsfinaltextexecsummri060997 E-10 QSTEnvironmental
Gallups Quarry Superfund Project - RI Executive Summary
E413 Hydrogeology
E4131 Hydraulic Conductivity
The hydraulic conductivity distributions within the overburden and bedrock formations were
evaluated through the performance of constant flow (pumping) tests and rising and falling head
slug tests Hydraulic conductivity measurements indicate that coarse-grained stratified drift
deposits in the lower portion of the aquifer are the most permeable subsurface materials in the Study Area with a mean hydraulic conductivity of 0005 centimeters per second (cms) The
highest hydraulic conductivities were found in the lower portion of the aquifer northwest of the Former Primary Disposal Area where the mean hydraulic conductivity is 0037 cms The mean
hydraulic conductivity of the finer-grained deposits in the upper portion of the aquifer is about
0001 cms
The mean hydraulic conductivity for the till wells (000047 cms) is a factor of ten less than the
average value for coarse stratified drift and varies between 00002 cms and 0002 cms The till
appears to be hydrogeologically distinct from the other overburden deposits and on the average
provides increased resistance to groundwater flow This added resistance is not considered to be
significant however because the consistency of the till and overburden deposits are highly
variable and the hydraulic conductivity contrast is relatively small The slug test results for the
bedrock wells yield the lowest (000018 cms) average hydraulic conductivity
E4132 Groundwater Flow
Horizontal Flow
Overburden groundwater flow south of the Former Seepage Bed is primarily east to west and is
influenced by two factors (1) the slope of the bedrock surface which defines the base of the
unconsolidated deposits and (2) regional hydrologic drainage patterns The average east-west horizontal hydraulic gradient in the southern portion of the Study Area is approximately 001 feet
per foot (feet change in piezometric head per horizontal foot of distance)
In the northern portion of the Study Area three hydrogeologically distinct zones exist South of the Former Primary and Secondary Disposal Areas the hydraulic gradient is steep (approximately
003 feet per foot) and is strongly influenced by the dip of the bedrock surface (01 feet per foot)
The saturated thickness increases from zero south of well MW109 to about 20 to 30 feet near the
former disposal areas North-northwest of the former disposal areas the hydraulic gradient
lessens significantly to a range of 00003 to 00007 feet per foot representing a factor of 40 to
100 reduction North-northeast of Mill Brook the hydraulic gradient is about 0007 feet per foot
Available data indicate that currently northwest of the railroad tracks groundwater flow in the middle to lower portions of the aquifer converges from the northeast and southwest toward a
centerline area generally defined in the downgradient direction by wells MW105 MW102 and
5797wpdoclaquoglaquoliupfraquofirultextexeclaquoummri060997 E-ll QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
MW101 The flow direction near these wells is from the former disposal areas to the northwest
Northeast of this centerline groundwater flows in a southwesterly direction from the vicinity of
Mill Brook and the former Pervel flock plant North of Mill Brook and west of the railroad
tracks the predominant groundwater flow direction becomes more westerly
No significant seasonal changes in horizontal groundwater flow directions were observed in the
Study Area Groundwater levels were generally highest in January 1995 and decreased by about
two feet through the period ending on July 11 1995 Levels then increased by about one foot
from July to November
General overburden groundwater pathlines for the northern portion of the Site are shown on
Figure E-2
Groundwater in bedrock moves primarily in a westerly direction south of the Former Seepage
Bed while in the northern Study Area the predominant bedrock flow component is toward the
northwest In both areas the hydraulic gradient is on the order of 002 feet per foot Groundwater in bedrock near the Former Seepage Bed flows to the northwest and exhibits no apparent
influence from the locally identified fracture zones
Vertical Flow
Vertical flow of groundwater is an important component in the upper several feet of the bedrock
unit Water level measurements indicate that groundwater is discharging from bedrock into the
overburden at every location measured except MW109 In most clusters the vertical hydraulic
gradient between bedrock and overburden is an order of magnitude greater than the horizontal
gradient
In the overburden aquifer the downward vertical flow component is significant within shallow
deposits near the Former Primary Disposal Area (wells MW107 MW108 and MW116) and the
upward flow is important in the upper portion of the aquifer near Mill Brook The downward
groundwater flow within the Former Primary Disposal Area appears to be primarily associated
with infiltration of precipitation and collection of surface water runoff from upland areas This
causes VOC concentrations to be highest in the middle to lower portions of the aquifer Stream
5797wpdocsgallupftfinaltextexecsummri060997 E-12 QST Environmental
N
LEGEND
WATERCOURSE
PROPERTY BOUNDARY
bullPIEZOMETRIC HEAD CONTOUR LOWER PORTION OF AQUIFER NOVEMBER 6 1995 (FEET)
GROUNDWATER PATHLINE
NOTES
1 BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM - CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
400 400 800
SCALE IN FEET
410 Amherst Street Nashua NH 03063
(603) 889-3737 UmHOHHM
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE E-2
SJjTff WIDE GROUNDWATER FLOW DRAWING NAM6 RIWIDEFWDWG FILE NUMBER 7194 138
SCALEAS SHAWN REVISION 1 DRAWN BY DJB DATE 5997
Gallups Quarry Superfiind Project - RI Executive Summary
piezometer data and groundwater flow modeling indicate that Mill Brook generally gains water
from the overburden aquifer within the Study Area
E414 Ecology
Wetlands delineations were performed to the extreme northern and western boundaries of the
Study Area up to the Mill Brook channel using both the State of Connecticuts accepted criteria
(which focuses on soil types and hydric soil characteristics) and the Federal criteria using US
Army Corps of Engineer methods (which includes the examination of vegetation hydrology and
soils) Most of the wetlandupland boundary occurs along the edge of a steep grade The sharp
relief produces a narrow transition between uplands and wetlands The delineated lines reflect
this as the State and USACOE wetland boundaries coincide at nearly every location With the
exception of an area intersecting a small portion of the Site at the northernmost edge of the
property east of the former disposal areas no wetland areas were identified on the Site
A preliminary identification of plant and animal species present in the Study Area was conducted during the wetlands delineation A limited number of wildlife species were observed Numerous
plant species were identified over the heavily vegetated Study Area No endangered species were
observed nor are reported to reside in the Study Area
E42 Nature and Extent of Contamination
E421 Contaminant Source Investigation The following summarizes the findings of contaminant source investigations conducted during the
RI program
bull Previous remedial activities have completely removed the waste materials (intact drums and bulk liquid waste) from the Site
bull The Former Seepage Bed and the Former Secondary Disposal Area contain
little residual contamination from the disposal activities which occurred in the
late 1970s
bull Residual levels of contamination primarily VOC and PCB were measured in
the Former Primary Disposal Area In general the highest levels of VOC are
located at or just below the groundwater table in native soils immediately
beneath the fill materials and diminish rapidly with depth Low levels of
PCB were detected primarily within shallow fill materials
5797wpdocraquogallupftfinlaquoltextexecraquoummri060997 E-14 QST Environmental
Gallups Quarry Superfiutd Project - Rl Executive Summary
bull Other than the three known former disposal areas and the remains of a
former CTDOT asphalt plant no other disposal areas were found to exist on -
the Site
E422 Groundwater Quality
Groundwater quality data collected during the Remedial Investigation indicate the following
bull No significant groundwater contamination was detected within the overburden
or bedrock units in either the southern Study Area or in the vicinity of the
Former Seepage Bed
bull In the northern Study Area a narrow low to moderate-concentration VOC
plume was detected in the overburden aquifer extending from the vicinity of
the Former Primary Disposal Area to the northwest towards Mill Brook
TCA and DCE were consistently detected at all locations along the plume
centerline at concentrations as high as 240 ppb and 1300 ppb respectively
bull Comparison of present concentrations with historical data indicate that VOC
levels are significantly decreasing with time From 1978 through 1995 TCA
TCE and PCE concentrations have decreased on the average by more than a
factor of two every two years representing environmental half-lives of less
than two years
bull The size and orientation of the plume are in excellent agreement with the
established groundwater flow directions
bull Available information indicates that the leading edge of the VOC plume
associated with the Former Primary Disposal Area is located in the vicinity of
monitoring well clusters MW-102 and MW-101 Concentrations of TCA and
DCE reduce to below MCLs at MW-101 Contaminant migration rates also
support this delineation of the front of the site-related VOC plume
bull Increasing PCE detections in the downgradient portion of the plume exhibit
inconsistencies with calculated migration rates from the Site Groundwater
flow directions VOC transport rates and historical concentration trends
indicate that PCE detections in wells MW118 MW116 MW103 MW118
MW102 and MW101 may be associated with contaminant transport from the
former Pervel flock plant However it is also possible that the PCE
detections at locations MW102 and MW101 are attributable to the former
disposal areas In addition contaminated groundwater from Pervel may have
5797wpdocsgal]upfraquofinaltextexeclaquoummri060997 E-15 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
also contributed TCA TCE DCE and vinyl chloride to the site related VOC
plume
Results of surface watersediment sampling and analyses stream piezometer measurements and groundwater flow modeling indicate that some discharge
of the shallow portion of the plume into Mill Brook is occurring However
the concentrations of VOC detected in the brook are well below those
reported to cause adverse effects in fish or wildlife
Bedrock is not considered a preferred pathway for contaminant migration due
to its characteristically low hydraulic conductivity and the predominantly
upward component of groundwater flow from bedrock to overburden which
exists throughout the Study Area
5797wpdocsgallupftfinlaquoltcxtexec8ummri060997 E-16 QfT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents
Section Page
10 Introduction bdquo 1-1
11 Purpose of the Report 1-1 12 Report Organization 1-2
13 Site Background 1-3 131 Area Description Demography and Land Use 1-3 132 Operational History 1-5
133 Summary of Previous Investigations 1-7
20 Field Investigations 2-1
21 Site Survey 2-1
211 Initial Site Survey 2-1
212 As-Installed Survey 2-1
22 Site Reconnaissance 2-2
221 Visual Observations of the Ground Surface 2-2
222 Air Quality Survey 2-2
223 Exclusion Zone Identification 2-4
224 Project Support Measures 2-4
225 Identification of Sensitive Human Receptors 2-5
23 Geophysical Surveys 2-5
231 Electromagnetic Terrain Conductivity (EM) Survey 2-7 232 Magnetometer (MAG) Survey 2-7
233 Additional EM and MAG Surveys 2-8
234 Seismic Refraction Survey 2-8
24 Groundwater Sampling Using Temporary Well Points 2-9
25 Soil Gas Survey 2-12
26 Soil Borings at Disposal Areas 2-15
261 Phase 1A Soil Borings 2-15
262 Phase IB Soil Borings 2-16 27 Installation of Monitoring Wells and Background Soils Sampling 2-17
271 Phase 1A Monitoring Well Placement-Rationale 2-19
272 Phase IB Monitoring Well Placement-Rationale 2-21
273 General Monitoring Well Installation Techniques 2-22
274 Stream Piezometers and Gauges 2-24
5797wpdocsgalluprifinaltextmarterrifhl061297 i QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
Table of Contents (continued)
275 Groundwater Piezometers 2-25
28 Aquifer Parameter Testing 2-25
281 Grain Size Analysis 2-25
282 Slug Tests 2-26
283 Constant Flow Tests 2-26
29 Groundwater Sampling 2-26
291 Monitoring Wells 2-27
292 Residential Wells 2-29
210 Surface Water and Sediment Sampling 2-29
211 Wetland Soil Sampling 2-31
212 Evaluation of Existing Monitoring Wells 2-31
213 Ecological Assessment 2-32
2131 Wetland Delineation 2-32 2132 Plant and Wildlife Survey 2-33
214 Test Pit Explorations 2-33
30 Physical Characteristics of the Study Area 3-1
31 General Characteristics 3-1
311 Regional Physiography 3-1
312 Study Area Physiography 3-1
313 Surface Water Features 3-2
314 Climate 3-3
32 Geology 3-3
321 Regional Surficial Geology 3-3
322 Local Surficial Geology 3-4
323 Regional Bedrock Geology 3-7
324 Local Bedrock Geology 3-8
33 Hydrogeology 3-9
331 Hydraulic Conductivity 3-9
332 Groundwater Flow 3-10
34 Ecology 3-17
341 Wetland Delineation 3-17
342 Plant and Animal Survey 3-19
40 Nature and Extent of Contamination 4-1
41 Contaminant Source Investigation 4-2
5797wpdocsggtlluprifinaltextmasteiTifhl061297 ii QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
Table of Contents (continued)
411 Visual Site Reconnaissance 4-2
412 Soil Vapor Survey 4-4
413 Geophysical Investigations and Test Pits 4-5
414 Background Soils 4-6
415 Soils From Former Known Disposal Areas 4-7
416 Contaminant Source Investigations Summary 4-15
42 Groundwater Quality 4-17
421 Temporary Well Point Investigation 4-17
422 Groundwater Monitoring Wells 4-18
423 Residential Wells 4-26
43 Surface Water Sediment and Wetland Soils 4-27 431 Surface Water 4-27
432 Sediment 4-31
433 Wetland Soils 4-32
44 Air Quality 4-34
441 Baseline Air Quality Survey 4-34
442 Perimeter Air Monitoring 4-34
45 Potential Sensitive Human Receptors 4-35
50 Contaminant Fate and Transport 5-1
51 Theory 5-1
511 Advection by Groundwater Flow 5-1
512 Dispersion 5-3 513 Advection Due to Fluid Density Differences 5-5
514 Biological and Chemical Degradation 5-5
515 Volatilization 5-7
516 Aqueous Solubility 5-7
52 Study Area-Specific Characteristics 5-7
521 Retardation Factors 5-7
522 Chemical Migration Rates 5-9
523 Time-Dependent Concentration Reductions 5-14
5797wpdocBg8lluprifinaltextmlaquo8terrifhl061297 Hi QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
60 Summary and Conclusions 6-1
61 Conceptual Model of the Study Area 6-1
611 Geology 6-1
612 Hydrogeology 6-2
613 Nature and Extent of Contamination bdquo 6-5
70 References 7-1
5797wpdocsgnlluprifinlaquoltextmasterriftil061297 Jy QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Table of Contents (continued)
List of Tables
Table 1-1 Summary of Results of Groundwater Analyses (CTDEP)
Table 1-2 Summary of Results of Groundwater Analyses (MampE 1993)
Table 1-3 Summary of Results of Groundwater Analyses Former Pervel Flock Plant (HRP)
Table 2-1 Microwell Sampling Intervals
Table 2-2 Former Disposal Area Soil Samples Submitted for Laboratory Analyses
Table 2-3 Monitoring Well Survey Data and Screen Intervals
Table 2-4 Geologic Descriptions of Soil Samples Collected for Grain Size Analyses
Table 2-5 Sample Inventory
Table 2-6 Existing Well Summary
Table 3-1 Hydraulic Conductivity Values
Table 3-2 Hydraulic Conductivity Values Estimated from Grain Size Distributions
Table 3-3 Monitoring Well Water Level Elevation Data
Table 3-4 Summary of Vertical Hydraulic Gradients Between Pairs of MWs in Study Area
Table 3-5 Stream Piezometer Water Level Elevation Data
Table 3-6 Plants Identified During the Wetland Delineation
Table 4-1 Summary of Visual Site Reconnaissance
Table 4-2 Background Soil Volatile Organic Compounds Table 4-3 Background Soil MetalsCyanide
Table 4-4 Disposal Areas Soil Volatile Organic Compounds
Table 4-5 Disposal Areas Soil Semivolatile Organic Compounds
Table 4-6 Disposal Areas Soil PesticidesPCB
Table 4-7 Disposal Areas Soil MetalsCyanide
Table 4-8 Microwell Survey Selected Volatile Organics
Table 4-9 Microwell Survey Results of Volatile Organics Laboratory Analyses
Table 4-10 Microwell Survey Results of Inorganic Laboratory Analyses
Table 4-11 Groundwater Volatile Organic Compounds January 1995
Table 4-12 Groundwater Volatile Organic Compounds April 1995
Table 4-13 Groundwater Volatile Organic Compounds July 1995
Table 4-14 Groundwater Volatile Organic Compounds November 1995
5797wpdocggalluprifinraquoltextmalaquoterrifhl061297 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Tables (Contd)
Table 4-15 Groundwater Volatile Organic Compounds February 1996
Table 4-16 Groundwater Volatile Organic Compounds May 1996
Table 4-17 Groundwater Volatile Organic Compounds August 1996
Table 4-18 Groundwater Volatile Organic Compounds November 1996
Table 4-19 Groundwater Volatile Organic Compounds February 1997
Table 4-20 Groundwater Semivolatile Organic Compounds January 1995
Table 4-21 Groundwater Semivolatile Organic Compounds April 1995
Table 4-22 Groundwater Semivolatile Organic Compounds July 1995
Table 4-23 Groundwater Semivolatile Organic Compounds November 1995
Table 4-24 Groundwater Semivolatile Organic Compounds February 1996
Table 4-25 Groundwater Semivolatile Organic Compounds May 1996 Table 4-26 Groundwater Semivolatile Organic Compounds August 1996
Table 4-27 Groundwater Semivolatile Organic Compounds November 1996
Table 4-28 Groundwater Semivolatile Organic Compounds February 1997
Table 4-29 Groundwater PesticidesPCB April July and November 1995 February and August 1996 February 1997
Table 4-30 Groundwater MetalsCyanide January 1995
Table 4-31 Groundwater MetalsCyanide April 1995
Table 4-32 Groundwater MetalsCyanide July 1995
Table 4-33 Groundwater MetalsCyanide November 1995
Table 4-34 Groundwater MetalsCyanide February 1996
Table 4-35 Groundwater MetalsCyanide May 1996
Table 4-36 Groundwater MetalsCyanide August 1996
Table 4-37 Groundwater MetalsCyanide November 1996
Table 4-38 Groundwater Metals February 1997
Table 4-39 Residential Wells Volatile Organic Compounds January 1995
Table 4-40 Residential Wells Volatile Organic Compounds July 1995
Table 4-41 Residential Wells Volatile Organic Compounds February 1996
Table 4-42 Residential Wells Volatile Organic Compounds August 1996
Table 4-43 Residential Wells PesticidesPCB January 1995
Table 4-44 Residential Wells PesticidesPCB July 1995
Table 4-45 Residential Wells PesticidesPCB February 1996
Table 4-46 Residential Wells PesticidePCB August 1996
Table 4-47 Residential Wells Metals January 1995
5797wpdocsg lluprifinaltextmastemfiil061297 VI QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Tables (Contd)
Table 4^8 Residential Wells Metals July 1995
Table 4-49 Residential Wells MetalsCyanide February 1996
Table 4-50 Residential Wells MetalsCyanide August 1996
Table 4-51 Field Observations of Habitat and Water Quality September 1994
Table 4-52 Surface Water Quality April and November 1995 May and November 1996
Table 4-53 Surface Water Volatile Organic Compounds September 1994
Table 4-54 Surface Water Volatile Organic Compounds April 1995
Table 4-55 Surface Water Volatile Organic Compounds November 1995
Table 4-56 Surface Water Volatile Organic Compounds May 1996
Table 4-57 Surface Water Volatile Organic Compounds November 1996
Table 4-58 Surface Water Volatile Organic Compounds September 1994 April 1995 May
1996
Table 4-59 Surface Water Total MetalsCyanide September 1994
Table 4-60 Surface Water Dissolved Metals September 1994
Table 4-61 Surface Water Total Metals April 1995
Table 4-62 Surface Water Dissolved Metals April 1995
Table 4-63 Surface Water Total and Dissolved Metals November 1995
Table 4-64 Surface Water Total and Dissolved Metals May 1996
Table 4-65 Surface Water Total and Dissolved Metals November 1996
Table 4-66 SedimentWetland Soils Metals September 1994
Table 4-67 SedimentWetland Soils Volatile Organic Compounds September 1994 Table 4-68 SedimentWetland Soils Semivolatile Organic Compounds September 1994
Table 4-69 SedimentWetland Soils PesticidesPCB September 1994
Table 4-70 Human Receptors Survey Location of Day Care Facilities Within 1-Mile Radius
of Site
Table 5-1 Fate and Transport Parameters for Study Area Volatile Organic Compounds
Table 5-2 Total Organic Carbon Measurements for Soil Samples
Table 5-3 Historical Concentration Data
5797wpdoclaquoglaquolluprifinaltextmasterriftil061297 Vll QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Figures
Figure E-l Site Location Map
Figure E-2 Site Wide Groundwater Flow
Figure 1-1 Site Location Map
Figure 1-2 Property Boundaries and Adjacent Landowners
Figure 1-3 Surface Water and Groundwater Classification Zones and Locations of Former
Disposal Areas
Figure 1-4 Groundwater Monitoring Wells Installed by Fuss amp ONeill
Figure 1-5 Site Location Map and Nearby Industrial Properties
Figure 3-1 Groundwater Elevations MW101 Series Figure 3-2 Groundwater Elevations MW102 Series
Figure 3-3 Groundwater Elevations MW103 Series
Figure 3-4 Groundwater Elevations MW104 Series
Figure 3-5 Groundwater Elevations MW105 Series
Figure 3-6 Groundwater Elevations MW106 Series
Figure 3-7 Groundwater Elevations MW107 Series
Figure 3-8 Groundwater Elevations MW108 Series
Figure 3-9 Groundwater Elevations MW109 Series
Figure 3-10 Groundwater Elevations MW110 Series
Figure 3-11 Groundwater Elevations MW111 Series
Figure 3-12 Groundwater Elevations MW112 Series
Figure 3-13 Groundwater Elevations MW113 Series
Figure 3-14 Groundwater Elevations MW114 Series
Figure 3-15 Groundwater Elevations MW115 Series
Figure 3-16 Groundwater Elevations MW116 Series
Figure 3-17 Groundwater Elevations MW117 Series
Figure 3-18 Groundwater Elevations MW118 Series
Figure 3-19 Groundwater Elevations MW119 Series
Figure 3-20 Groundwater Elevations SW3 Series
Figure 3-21 Three-Dimensional Groundwater Flow Map
5797wpdoc8galluprifiruiltextmasterriftil061297 viii QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
Figure 5-1
Figure 5-2
Figure 5-3
List of Figures (Contd) Groundwater VOC Concentrations vs Time - Downgradient from Former
Primary Disposal Area
Groundwater VOC Concentrations vs Time - Near Former Pervel Facility
Groundwater VOC Concentrations vs Time - Downgradient Portion of VOC
Plume
Figure 5-4 Evaluation of Biodegradation and Rainwater Dilution Rates in VOC Plume
5797wpdocraquogalluprifinaltextmasterrifhl061297 ix QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Plates
Plate 2-1 Baseline Survey Grid Air Monitoring Seismic Refraction Line Locations
Plate 2-2 Microwell Locations
Plate 2-3 Soil Vapor Probe and Soil Boring Locations
Plate 2-4 Monitoring Wells PiezometersStream Gauge Locations
Plate 2-5 Residential Well Locations
Plate 2-6 Surface WaterSediment and Wetland Soil Sampling Locations
Plate 2-7 Location of Test Pits Performed at Geophysical Anomalies
Plate 3-1 Study Area Topographic Features
Plate 3-2 Geologic Cross-Sections A-A amp C-C Plate 3-3 Geologic Cross-Section D-D
Plate 3-4 Geologic Cross-Section B-B Plate 3-5 Geologic Cross-Sections E-Eamp F-F
Plate 3-6 Bedrock Surface Contour Map
Plate 3-7 Bedrock Fracture Zones as Determined by Seismic and Magnetometer Surveys
Plate 3-8 Lower Overburden Piezometric Surface November 6 1995
Plate 3-9 Shallow Overburden Piezometric Surface November 6 1995
Plate 3-10 Saturated Overburden Thickness November 6 1995
Plate 3-11 Bedrock Piezometric Surface November 6 1995
Plate 3-12 Vertical Ground water Flow Through Plume Center Line
Plate 3-13 Deep vs Shallow Piezometric Head Differences
Plate 3-14 Wetland Delineation Map September 1994
Plate 4-1 Survey Grid amp Features Noted During Site Reconnaissance August-September
1994
Plate 4-2 Former Primary Disposal Area Soil Borings VOC Data and Cross-Sections
Plate 4-3 Former Primary Disposal Area Soil Borings PCB Data and Cross-Sections
Plate 4-4 VOC Detections Field GC and Laboratory Analyses in Microwells
Plate 4-5 Laboratory Results of Metals Analyses in Microwells
Plate 4-6 Groundwater VOC Data January April July and November 1995 Sampling
Events
Plate 4-7 Groundwater VOC Data February May August and November 1996 and
February 1997 Sampling Events
Plate 5-1 Groundwater Travel Times in Overburden Aquifer November 6 1995
5797wpdocsgi lluprifinaltextmasteirifnl061297 X QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
Table of Contents (continued)
List of Appendices
Appendix A Weston Geophysical Inc Report
Appendix B Microwell Logs
Appendix C Soil Boring and Rock Coring Logs and Well Construction Forms
Appendix D Groundwater Sampling Forms
Appendix E Test Pit Logs
Appendix F Single-Well Hydraulic Conductivity Test Procedures
Appendix G Grain Size Data
Appendix H Phase 1A Laboratory Reports
Appendix I April 1995 Laboratory Reports
Appendix J July 1995 Laboratory Reports
Appendix K Phase IBNovember 1995 Laboratory Reports
Appendix L February 1996 Laboratory Reports
Appendix M May 1996 Laboratory Reports
Appendix N August 1996 Laboratory Reports
Appendix O November 1996 Laboratory Reports
Appendix P February 1997 Laboratory Reports
Appendix Q Data Validation Reports
Appendix R pH TOC Moisture Results Soil Samples
Appendix S Environmental Metals Statistics
Appendix T Air Monitoring Results
Appendix U Model of Groundwater Near Mill Brook Appendix V Methodology for Piezometric Head Contouring and Groundwater Pathline
Generation
5797wpdocsgalluprifinlaquoltextmagterri fhl061297 XI QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
10 Introduction
11 Purpose of the Report This document presents the Remedial Investigation Report (RI) which was completed for the
Gallops Quarry Superfund Site (Site) pursuant to the requirements of US Environmental
Protection Agency (EPA) Administrative Order by Consent Docket Number 1-93-1080 (Order)
issued September 7 1993 The Gallups Quarry property is the site of a former sand and gravel
quarry and is located on Tarbox Road in the town of Plainfield Windham County Connecticut
(see Figure 1-1) According to the Town of Plainfield Tax Assessors office the property (Map
10 Block 30 Lot 32) is an irregularly shaped parcel comprised of approximately 29 acres
Investigation of the quarry was initiated in 1978 when unlicensed waste disposal operations were
discovered at the property Emergency clean-up operations were conducted by the Connecticut
Department of Environmental Protection (CTDEP) in April 1978 (Metcalf amp Eddy 1993)
Following the initial clean-up effort a study was conducted to characterize the nature and extent
of residual contamination at the Site (Fuss amp ONeill 1979) A series of surface and subsurface
sampling events conducted by the CTDEP the Connecticut Department of Health and the US
Environmental Protection Agency (EPA) between the years of 1978 and 1988 prompted EPA to
propose on June 21 1988 that the Site be listed on the National Priorities List (NPL) The Site
was finally listed on the NPL on October 4 1989 During 1992 and 1993 EPA conducted a
limited investigation through the Superfund Technical Assessment amp Response Team (START)
initiative in an effort to expedite the completion of the Remedial InvestigationFeasibility Study
(RIFS) The requirements of the Order as well as data included in the START report (Metcalf
amp Eddy 1993) provided the framework for this investigation
This Report is the sixteenth major deliverable under the Order The first major deliverable the
Remedial InvestigationFeasibility Study Work Plan - Phase 1A was finalized and submitted to
EPA on August 29 1995 QST Environmental (formerly Environmental Science amp Engineering
Inc (ESE)) finalized the Work Plan and has prepared all of the other deliverables The Phase 1A
field investigation was completed in January 1995 The second major deliverable the Phase 1A
Data Report dated March 24 1995 was submitted to EPA following completion of the Phase 1A
field investigation The findings of the Phase 1A investigation were described in the Initial Site
Characterization Report (ISCR) which was finalized and submitted to EPA on March 1 1996 A
Work Plan for the Phase IB field investigation was also finalized and submitted on October 11
1995
In addition to the actual Phase 1A field investigation the Phase 1A Work Plan also described the
Long Term Monitoring Program which was initiated upon completion of the Phase 1A field
5797wpdocraquogalluprifinaltextmlaquoiterrifhl061297 1-1 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
investigation The Long Term Monitoring Program includes the quarterly collection and analysis
of groundwatei and semi-annual collection and analysis of surface water and nearby residential
well samples
The Phase IB field investigation commenced on October 12 1995 Following the completion of
drilling activities the Phase IB groundwater sampling task and the fourth quarter 1995 Long
Term Monitoring sampling event were performed simultaneously in November 1995 Seven
Data Reports have been submitted to the EPA for the following Long-Term Monitoring Program
sampling events the second and third quarters of 1995 all four quarters of 1996 and the first
quarter of 1997 (ESE 1996a 1996b 1996c 1997a 1997b) The draft RI Report was submitted
to EPA on March 15 1996 (and revised and resubmitted October 22 1996) and included the
results of the fourth quarter of 1995 sampling event On March 29 1996 the following two
deliverables were submitted to EPA Development and Initial Screening of Alternatives Report
and Detailed Analysis Work Plan The draft Feasibility Study was submitted to EPA on January
27 1997 This RI Report describes the methods and findings of both the Phase 1A and IB field
studies and includes data collected during the April July and November 1995 February May
August and November 1996 and February 1997 Long-Term Monitoring sampling events
12 Report Organization The RI is presented in seven main sections following the Executive Summary The remainder of
Section 1 presents Site background information Section 2 presents the various field methods and
procedures used during the field investigations including descriptions of any changes or
deviations from the Work Plan Section 3 describes the physical characteristics of the Study
Area and Section 4 presents the findings of studies designed to determine the nature and extent of
contamination within the Study Area Section 5 is a discussion of the various fate and transport
mechanisms associated with the contaminants of concern Section 6 summarizes the conceptual
model of conditions within the Study Area Finally a list of references cited in this report is
presented in Section 7
Volume 1 of this Report presents the text and figures of the RI Volume 2 contains all Tables
referenced in the report Volume 3 contains all Plates referenced in the Report Volume 4 and
all subsequent volumes contain the Appendices referenced in the Report
5797wpdocggaIluprifinaltextmasterrifhl061297 1-2 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
13 Site Background 131 Area Description Demography and Land Use
For the purposes of this report the Site is considered to be the actual property owned by the
late Stanton Gallup from 1964 until his death in 1994 The Study Area includes the Site as
well as surrounding properties from which data were collected during the RI
The Site is located on the north side of Tarbox Road in the Town of Plainfield Windham County
Connecticut (see Figure 1-1) The Site is situated approximately 2000 feet west of interchange
87 on Interstate 395 and approximately one-mile southwest of Plainfield Center As shown on
Figure 1-2 the Site is irregularly shaped and is approximately 2200 feet long (north to south)
and 300 to 1100 feet wide (east to west) A number of previous references have described the
Site as ranging in size from 20 to 22 acres however the Town of Plainfield Tax Maps and areal
calculations performed by ESE indicate that the size of the Site is approximately 29 acres In
addition to the Site the Study Area includes additional areas located to the north and northwest of
the Site (as shown on Figure 1-1) and a number of discrete smaller areas located to the east and
south of the Site used for collecting upgradient surface watersediment samples
The Site is currently vacant and much of it is heavily vegetated Numerous overgrown mounds
and excavations are scattered across the Site and are presumed to be features remnant of the
former sand and gravel quarry operations Other than concrete foundations remnant of former
Site operations no structures presently exist on the property Surface features observed on the
Site during the Phase 1A visual reconnaissance survey are described in more detail in Section
411
As shown on Figure 1-2 the Site is bounded to the east by Route 12 (Norwich Road) single-family residences and a plumbing supply company An active railroad right-of-way (presently
operated by the Providence and Worcester Railroad) bounds the Site to the west Wooded areas
and wetlands associated with Mill Brook bound the Site to the north and Tarbox Road and several
single family residences bound the Site to the south
Surface water bodies located within or near the Study Area include Mill Brook Fry Brook and
Packers Pond As shown on Figure 1-3 Mill Brook flows from east to west along the northern
edge of the Study Area until its confluence with Fry Brook Mill Brook turns toward the south
at this confluence and continues flowing in a south-southwesterly direction (as Mill Brook) and
eventually drains into Packers Pond [Note Packers Pond is not shown on Figure 1-3 due to the
larger scale of this figure however the relative location of Packers Pond approximately 1 mile
west of the Site can be seen on Figure 1-1]
5797wpdocBgalluprifinaltextmasteiTifhl061297 1-3 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Based on the CTDEP Water Quality Classification Map of Thames Southeast Coast and
Pawcatuck River Basins Sheet 2 of 2 (1986) surface water located within the section of Mill
Brook between Route 12 and the confluence with Fry Brook (shown on Figure 1-3) is classified
as BA The BA classification indicates that the surface water body may not be meeting the
Class A water quality criteria for one or more designated uses which include potential drinking
water supply fish and wildlife habitat recreational use and agricultural and industrial supply
although the goal is to ultimately restore the water body to Class A standards Surface water
within Fry Brook and the lower section of Mill Brook (located down stream of the confluence of
the two brooks) is classified as Be The Be classification indicates that the water meets Class B
criteria and is suitable for cold water fisheries The designated uses for Class B surface water
include most of those described for Class A however Class B waters are NOT designated as a
potential drinking water supply Surface water located within Packers Pond (not shown on Figure
1-3) is designated as CBc The CBc designation indicates that Packers Pond is not meeting the
Class B water quality criteria for one or more designated uses or is a Class C water body which
is basically a downgraded version of Class B However the CTDEP goal for surface water
designated as CBc is to restore it to Class B conditions
As shown on Figure 1-3 groundwater located within the northern portion of the Study Area
between Route 12 and the MillFry Brook confluence is classified as GBGA which indicates that
the groundwater may not be suitable for direct human consumption without the need for treatment
due to waste discharges spills or leaks of chemicals or land use impacts The CTDEP goal for
groundwater classified as GBGA is to prevent further degradation by preventing any additional
discharges which would cause irreversible contamination Groundwater at all other locations
within the Study Area is classified as GA which is presumed suitable for direct human
consumption without need for treatment In addition one of the goals of the CTDEP for
groundwater classified as GBGA is to restore it to GA standards
It should be noted that the surface water classifications described above are based on existing
CTDEP maps which were published prior to the preparation of this report During the course of
this investigation the CTDEP proposed amendments which were intended to clarify the language
of the States Water Quality Standards and simplify the Departments system for considering
requested modifications Based on conversations with a representative of the CTDEP (Personal
Communication Bobowitz 1996) the single letter (eg Class A) and dual letter (and associated
goal) classification (eg BA) system will be maintained Areas presently designated by dual
classifications will only be modified once the desired goal for that water body or aquifer has been
attained According to the CTDEP the only significant change will be the eventual elimination of
the use of lower case suffixes (eg Be) which are currently used to indicate very specific
restrictions or uses for certain water bodies (ie B rather than Be)
5797wpdocsgalluprifinaltextmasterrifhl061297 1-4 QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
Within the Study Area directly west of the Site (across the railroad tracks) are open cropland
(presently a cornfield) wooded areas and a residential property (parcel 24 shown on Figure 1shy
2) The property boundaries and land owners for the Site and other nearby parcels are also
shown on Figure 1-2 Immediately north of the Site are approximately 85 acres of wooded
undeveloped land through which flows Mill Brook An overhead power line easement (not shown
on Figure 1-2) runs adjacent to the northernmost Site boundary On the north side of Mill Brook
is an industrial park which contains an Intermark Fabric Corporation facility (formerly the Pervel
Industries flock plant) and a Safety Kleen Corporation accumulation facility Northeast of Mill
Brook are woodlands and Saint Johns Cemetery Further north of the industrial park are several
vacant mill buildings which were occupied until the late 1980s by various manufacturers including
Pervel Industries and the InterRoyal Corporation The Plainfield sewage treatment plant which
discharges to Mill Brook and its major tributary (Fry Brook) is located approximately 1800 feet
northwest of the property
The Town of Plainfield with a land area of 427 square miles has a population of approximately
14200 Plainfields principal industries include varied manufacturing and distribution centers as
well as tourism based businesses In addition the rural areas of Plainfield are occupied by many
small dairy and produce farms
^ 132 Operational History
Information regarding the operational history of Gallups Quarry was obtained from published
reports for previous Site studies including Site Analysis Gallups Quarry Plainfield CT
(Bionetics Corporation 1990) and Final Data Summary Report START Initiative (Metcalf amp
Eddy 1993) as well as information from various sources collected during the preparation of the
Gallups Quarry Remedial InvestigationFeasibility Study Work Plan (ESE 1994) Little detailed information concerning the early operational history of the Site exists
A review of an aerial photograph of the Site taken in 1951 depicts the Site as an undeveloped
parcel although some quarry activities in the southern portion of the property appear to be
underway (ESE 1994) Records at the town of Plainfield Assessors office indicate that in 1951
the Site was owned by a Mr Johnson who was operating a sand and gravel quarry In 1964 the
Site was purchased by C Stanton Gallup (Metcalf amp Eddy 1993) Although detailed usage of
the Site from 1964 through 1977 is poorly documented records indicate that the Site was used as
a source of aggregate and was occupied by the Connecticut Department of Transportation
(CTDOT) which operated an asphalt batching plant (ESE 1994) The exact date of CTDOT
presence at the Site is unclear although it is believed to coincide with the construction of Route
52 (now known as Interstate 395) Evidence of the former asphalt batching plant operations are
5797wpdocsgalluprifinalteirtinalaquoterrifhl061297 1-5 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
still present at the Site Mounds of asphalt paving material and areas covered with hardened
liquid asphalt ere observed at a number of locations throughout the Site
As a result of complaints from neighboring residents the CTDEP and the Connecticut State
Police initiated an investigation of the Site in early January 1978 During a Site visit on January
13 1978 representatives of the CTDEP reportedly observed partially buried drums containing
suspected hazardous materials and ordered that all Site operations be stopped The CTDEP
investigation concluded that the Site was used from the summer of 1977 until December 1977 for
unlicensed waste disposal
As described in the Order evidence collected by CTDEP indicates that Chemical Waste Removal
Inc (CWR) of Bridgeport Connecticut transported drummed and bulk liquid waste material to the
Site and was the sole known transporter of waste to the Site These wastes reportedly included a
variety of industrial wastes which were transported to and disposed of at the Site It was reported
that Mr Gallup jointly operated the quarry with Mr Dick Trayner of Dick Trayner and Sons
Trucking Company at the time of the illegal waste disposal activities
According to CTDEP and State Police records the drums and liquid wastes were reportedly
disposed of at three distinct locations on the Site These areas were subsequently labeled the
Primary Disposal Area the Secondary Disposal Area and the Seepage Bed The Primary and
Secondary Disposal Areas were reportedly located in the northern portion of the Site while the
Seepage Bed was reportedly located in the central portion of the Site The reported locations of
these former disposal areas are shown on Figure 1-3
According to a report issued by Fuss amp ONeill (FampO 1979) the Primary Disposal Area
consisted of an area approximately 04 acres in size The Secondary Disposal Area was described
by the FampO report as a linear trench which encompassed an approximate area of 007 acres
located adjacent to the railroad tracks and just west of the Primary Disposal Area The Seepage
Bed was located in the central portion of the Site and according to the FampO report was
approximately 40 feet by 50 feet in size and consisted of an excavation into which an inverted
truck body filled and covered with crushed stone was placed A metal pipe which extended
from the dump body to the ground surface was reportedly used for direct discharge of liquid
wastes According to the FampO report the liquid wastes reportedly disposed of in the Seepage
Bed consisted of low pH liquids which were believed to be by-products associated with metal
finishing operations
Initial cleanup efforts were performed by Chem-Trol Inc during the summer of 1978 under the
direction of the CTDEP and the Connecticut State Police A Connecticut State Police Possessed
5797wpdocsglaquolluprifinaltextmasterrifhl061297 1-6 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
Property Report (PPR) lists the following materials as removed from the Site 1584 drums (some
of which were crushed andor decomposed) 5000 gallons of free liquid and 2277 cubic yards
of contaminated earth The PPR also lists 127715 tons of moderately contaminated soil which
was removed from the Site Additional remedial measures included the neutralization of residual
contamination at the Seepage Bed by placing 20 tons of lime at that location
Although no information concerning the actual number of drums or quantity of waste transported
to the Site by CWR is available it was believed that all of the drums had been recovered upon
completion of the cleanup operations Mine detectors were utilized to search for additional buried
drums however no indications of additional buried drums were discovered
Since the 1978 cleanup operations the Site has been vacant Public vehicular access to the Site
has been limited by the placement of boulders and mounded soil at access locations around the
Site During this time evidence of off-road vehicle tire tracks and small quantities of debris
(beverage cans bottles spent shotgun shell casings and empty gasoline cans) indicate that the
Site has been utilized by trespassers for recreational purposes However it appears that Site
usage has decreased since August 1994 when fencing and additional boulders were placed at
potential access locations and the perimeter of the property was posted with warning signs
133 Summary of Previous Investigations
Following the CTDEP removal activities a number of environmental investigations and sampling
events were conducted at the Gallups Quarry Site This section summarizes environmental
studies conducted at the Site prior to the RIFS as compiled performed and reported by Metcalf
amp Eddy (1993) as part of the EPAs Region I START Initiative or as reported by the original
investigators)
1331 Evaluation of a Chemical Waste Disposal Area Tarbox Road Site Plainfield Connecticut Fuss amp ONeill 1979
Between June 6 and October 30 1978 Fuss amp ONeill Inc performed a hydrogeological
investigation within the Study Area in conjunction with the cleanup and remedial operations
directed by the CTDEP and Connecticut State Police The findings of this investigation were
presented in a report issued to the CTDEP dated January 29 1979 The tasks completed during
this investigation included the following
bull The installation of 22 test borings which were completed as groundwater
monitoring wells (SW series) including three shallow-bedrock wells near the
Former Seepage Bed (SW-10 SW-11 SW-12) The locations of these wells are
shown in Figure 1-4
5797wpdocsgalluprifinaltextmlaquo8terrifhl061297 1-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
bull Excavation of 19 test pits (using a backhoe) 13 of which were completed as
shallow groundwater monitoring wells
bull The establishment of 12 surface water gauging stations along Mill Brook and Fry
Brook
bull The collection of surface water and groundwater water for laboratory analysis
FampO collected groundwater samples from the monitoring wells in July October and December
1978 Several nearby domestic wells were also sampled in July and October 1978 Groundwater
samples were analyzed for metals volatile organic compounds (VOC) and the following general
chemical parameters chemical oxygen demand (COD) total dissolved solids (TDS) total
Kjeldahl nitrogen (TKN) chloride total organic carbon (TOC) total carbon total cyanide
specific conductance and pH
FampO also collected surface water samples from seven of the stream gauging stations in
September October and November 1978 In general the surface water samples were analyzed
for the same chemical parameters described above
The chemical testing results indicated groundwater in the vicinity and downgradient of the Former
Disposal Areas had been impacted by several organic and inorganic constituents VOC detected
included ethanol methanol isopropanol ethyl acetate acetone toluene benzene trichloroethene
(TCE) 111- trichloroethane (TCA) tetrachloroethene (PCE) methyl isobutyl ketone (MIBK)
methyl ethyl ketone (MEK) and methylene chloride Various metals including aluminum
chromium copper magnesium nickel zinc iron and silver were reported at widely variable
concentrations in some groundwater samples According to the START Report the domestic
wells did not appear to be significantly impacted
FampO concluded that a well-defined groundwater contaminant plume extended from the former
disposal areas towards Mill Brook northwest of the Site and that the flow direction of the plume
was controlled by the local water table gradient The plume was characterized by the presence of
organic compounds which included acetate benzene ethanol isopropanol MEK MIBK
toluene TCA and xylene The plume also contained widely variable concentrations of various
metals including copper nickel boron aluminum magnesium manganese iron silver
cadmium and lead
The START Report indicated that since little or no information is available regarding FampOs field
methods (eg field notes chain-of-custody collection of field QC samples) or analytical
5797wpdoc8galluprifinaltextmastemfnl061297 1-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
methods (eg detection limits turbidity filtering sample preservation analysis of lab QC
samples) comparison of the test results to current regulatory criteria (eg Maximum Contaminant
Levels [MCL]) was not appropriate for any definitive purpose
1332 CTDEP Periodic Monitoring 1979 to 1983
As described in the START Report the CTDEP performed periodic monitoring of groundwater
(including domestic wells) surface water and sediment in the Study Area from 1979 until 1983
The periodic monitoring was not systematic in terms of the wells or locations that were sampled
or the parameters tested for The results of the CTDEP monitoring are in the form of laboratory
results compiled and presented in the START report A summary table of results for the CTDEP
groundwater monitoring activities as presented in the START report is included in this report as
Table 1-1
The dates of groundwater sample collection and analysis for the CTDEPs monitoring program
are as follows
bull October 1979
bull January 1980
bull November 1980
bull April 1981
bull October 1981
bull April 1982
Sample analytical parameters varied from event to event but typically included pH COD
specific conductivity hydrocarbons chlorides and selected metals (cadmium chromium copper iron nickel and zinc)
The CTDEP also collected surface water and sediment samples on the following dates
bull January 1980 (surface water)
bull October 1981 (surface water and sediment)
bull April 1982 (surface water)
bull December 1983 (surface water)
It was noted in the START Report that no information was available regarding the CTDEP sampling methods or analytical procedures and that this limited the usefulness of the data except
for comparative purposes Nonetheless the START Report concluded that the available analytical
data collected by CTDEP during the period from 1972 to 1982 indicated that the Site and areas to
5797wpdoc8falluprifinaltextmasterrifnl061297 1-9 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
the north-northwest were impacted by the past disposal of VOC metals and acid wastes This
conclusion wa5 based on the fact that up until the last recorded groundwater sampling event
performed by CTDEP (1982) four monitoring wells (SW7D SW13 SW17S and SW17D)
exhibited detectable concentrations of contaminants characteristic of the types of wastes which
were reportedly disposed of on the Site The contaminants detected in these wells included
various common industrial organic solvents (both chlorinated hydrocarbons and ketones) as well
as several petroleum aromatic hydrocarbons Chlorinated hydrocarbon concentrations for these
wells ranged from 10000 to 80000 parts per billion (ppb) for 111-Trichloroethane (TCA) 30
to 1000 ppb for Tetrachloroethane (PCE) and 1000 to 14000 ppb for Trichloroethene (TCE)
Ketones detected included Acetone (5000 to 22000 ppb) methyl ethyl ketone (MEK) ranged
from 12000 to 150000 ppb and methyl iso butyl ketone (MIBK) ranged from 60 to 7000 ppb)
The main aromatics detected included toluene (up to 17000 ppb) and xylene (up to 3000 ppb)
1333 CTDEP BioDiversity Study 1985
The CTDEP conducted a field survey on November 4 1985 to evaluate potential impacts from
migration of groundwater from the Site to the Mill Brook wetland The study was conducted in
an area where leachate was observed to be breaking out from the wetlands into Mill Brook
The precise location is unclear however the START Report indicates that the impact zone was
subjectively estimated to be approximately 200 feet west of the railroad bridge The leachate
was described as an area showing evidence of organic enrichment and iron hydroxide precipitation
which extended a distance of approximately 100 feet downstream
The study reported a background species Diversity Index value of 257 compared to a value of
236 for the area of study The minor difference in diversity represented by this measure was
primarily considered to be a result of low flow conditions as much higher diversity indices
indicative of excellent water quality were observed during a previous bioassessment in that
area
As part of the CTDEP study four surface water samples were collected (one control and three
downstream) from Mill Brook on 8 November 1985 for acute aquatic toxicity bioassays using
water fleas (Daphniapulex) The results of this testing are summarized in a CTDEP
interdepartmental memorandum (dated November 18 1985) that is included with the results of the
biodiversity study The assay employed three replicates per sample and 10 individual organisms
per replicate The endpoint of the assay was percent survival after 48 hour exposure to the water
All samples yielded average survival rates of greater than 83 Based on the results of the tests
the CTDEP concluded that no acute toxicity was demonstrated
5797wpdocsgalluprifinaltextmasterrifnl061297 1-10 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The BioDiversity study report indicated that well MW17S was sampled and that a strong
solventacid odor was noted Further information on sampling and analyses of this well by
CTDEP in 1985 was not included in the report
1334 Hazard Ranking System (HRS) Study - NUSFIT 1986 to 19874
On September 15 1987 the Superfund Division of NUS Corporation completed the Final HRS
Documentation Package for Gallups Quarry The package contains information on the cleanup
and subsequent environmental evaluations including State Police documents and logs regarding
the investigation into the unlicensed disposal activities CTDEP and State Police documents
concerning cleanup activities affidavits taken from individuals involved in the disposal activities
and miscellaneous correspondence related to the criminal investigation and cleanup activities
The HRS package includes the EPAs Preliminary Assessment for Gallups Quarry which was
completed by NUS in July 1986 During the Preliminary Assessment NUS sampled two of the
existing monitoring wells (SW17D and SW18) and three surface watersediment locations The
surface and groundwater samples were screened in-house for benzene TCE toluene PCE
chlorobenzene ethyl benzene and xylenes None of these compounds were detected in MW18 or
the surface water samples All of the compounds (except chlorobenzene) were detected in
MW17S with toluene and xylenes measured at the highest concentrations With the exception of
pH temperature and conductivity no data were available regarding the sediment samples
Based on a file review and limited sampling the Preliminary Assessment concluded as in
previous studies that VOC contamination existed at the Site and that contaminated groundwater
was migrating in a west to northwest direction from the Site NUS recommended that a Site
Investigation be conducted to further evaluate the on-site conditions and potential off-site impacts
1335 Residential Well Sampling 1989
In 1989 Roy F Weston Inc under contract to EPA collected samples from 10 private wells in
the vicinity of the Site The samples were analyzed for VOC semi-volatile compounds (SVOC)
and metals Very low levels of some VOC (chloromethane TCA and carbon tetrachloride)
SVOC (phthalates) and metals (barium and copper) were detected in several wells but at
concentrations well below their respective EPA MCL In a memo dated May 25 1989 (included
as Appendix G of the START Report) EPA concluded that the levels detected in this investigation
did not represent a public health threat
5797wpdocsgalluprifinaltextmraquosterrifhl061297 1-11 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
1336 Site Analysis - Bionetics Corporation 1990
In November 1990 the Bionetics Corporation under contract to EPA completed an analysis of
historical aerial photographs taken of the Site in 1951 1970 1974 1975 1981 and 1988
Based on analyses of these aerial photographs the report suggested that disposal-related activities may have started at the quarry as early as 1970 However this conclusion was based on the
presence of features such as excavated areas mounded materials possible containers and the presence of access roads all of which are also indicative of typical quarrying operations
1337 Health Assessment - US Department of Health and Human Services (DHHS) 1991
The US Department of Health and Human Services completed a Health Assessment for Gallups Quarry on January 30 1991 to assess potential human health effects from exposure to
contamination at the Site The assessment was based on previous chemical testing data available
for the Site (ie data collected by Fuss amp ONeill Inc in 1978 and by CTDEP in 1979 through
1983)
The report concluded that if present at high enough concentrations VOC and heavy metals
detected at the Site could have potential public health implications The report recommended that
a program of groundwater monitoring be instituted along with on-site soil and surface water sampling and that additional health data for the area be evaluated as it becomes available
1338 Residential Well and Surficial Soil Sampling - Roy F Weston 1993
In 1993 Roy F Weston Inc under contract to EPA sampled 8 residential supply wells in the
vicinity of the Site The samples were analyzed for VOC SVOC and metals In addition
Weston collected seven surficial soil samples (within 3 inches of the ground surface) from areas
of apparent staining in the vicinity of the Former Primary and Secondary Disposal Areas Two
samples were collected in January 1993 and the other five were collected in February 1993 The
soil samples collected in January were submitted to the laboratory for analysis for pH and
cyanide and for metals screening using X-ray fluorescence techniques (XRF) The five samples
collected in February were analyzed for cyanide
The results of the XRF screening analyses indicated that the two samples collected in January
contained levels of copper ranging from 160 to 400 ppm No other metals were detected above
normal background levels Cyanide levels for all seven soil samples were reported in the range
of 87 to 345 ppm
5797wpdocsgalluprifinaltextmasterrifiil061297 1-12 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
The well water analytical results indicated that 111-TCA was detected in three of the residential
wells at levels of 05 to 12 ppb well below EPA MCL for 111-TCA of 200 ppb Copper and
iron were detected at levels below the EPA MCL in several of the samples analyzed SVOC were
not detected
1339 Groundwater Monitoring and Well Survey Metcalf amp Eddy 1993
In November 1992 Metcalf amp Eddy performed a well condition survey of the remaining existing
monitoring wells at the Site as part of a groundwater monitoring well investigation conducted for
the EPA Thirteen of the original twenty-two monitoring wells installed by Fuss amp ONeill Inc
were located fewer than half of which were determined to be in a condition capable of producing
viable samples In February 1993 Metcalf amp Eddy collected samples from ten of the wells
installed by Fuss amp ONeill Inc and from a USGS well installed in 1992 The samples were
analyzed for VOC SVOC metals and cyanide
Groundwater analytical results were consistent with earlier studies but confirmed that VOC levels
were significantly decreasing with time Low levels of VOC were detected at monitoring wells
SW3S and SW3D located downgradient of the Former Primary Disposal Area and at SW13
located downgradient of the Former Secondary Disposal Area The highest levels of VOC were
detected in wells SW17S (15000 ppb of xylene 1700 ppb of toluene 460 ppb of TCA 34 ppb
of TCE 22 ppb of PCE) and SW17D (1500 ppb of 12-DCE 720 ppb of TCA 16 ppb of TCE
and 27 ppb of PCE) A summary of the results of the 1993 Metcalf amp Eddy monitoring are
presented in Table 1-2 In general the concentrations detected in these wells for this sampling
event were substantially lower than concentrations recorded during the previous groundwater
sampling in 1982
13310 Geohydrology of the Gallups Quarry Area Plainfield Connecticut USGS 1993
In 1993 the United States Geological Survey (USGS) issued a draft report on Geohydrology of
the Gallups Quarry Area Plainfield Connecticut (finalized in 1995) The work was performed as
part of the EPAs START program and was designed to assist in the RIFS scoping process
The USGS study interpreted the subsurface geologic conditions at the Site to provide guidance for
subsequent investigations Field investigations for the study included ground penetrating radar
(GPR) and electromagnetic (EM-34) geophysical surveys the drilling of three test borings the
installation of a monitoring well in one of the borings (shown on Figure 1-4) and the
measurement of flow rate and specific conductance in Mill Brook
5797wpdocraquosalluprifiiultextmasterrifiil061297 1-13 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The USGS investigation provided data on overburden soil units the depth to bedrock and
bedrock structure Existing subsurface information derived from previous test boring logs and the
data collected from the three test borings drilled by the USGS were used in conjunction with GPR
data and the results of the EM-34 terrain conductivity survey to develop geological cross-sections
across the Site In addition the GPR survey indicated the possible presence of a west-northwest
trending fault zone beneath the property located south of the Former Seepage Bed The location
of this suspected fault zone as estimated by the USGS is consistent with the approximate location
inferred by previous regional geological studies (Dixon 1965 and Boynton and Smith 1965)
An electromagnetic survey performed downgradient (northwest) of the Former Secondary and
Primary Disposal Areas indicated a northwesterly-trending pattern of increased terrain
conductivity levels as compared with levels at other areas of the Site The USGS interpreted the
increased levels as possibly indicative of either the presence of a groundwater plume containing
residual metal contamination or a natural change in subsurface strata Surface water
measurements collected in Mill Brook indicated that specific conductance increased slightly
downstream of the railroad bridge however the observed differences were so small that the
USGS did not consider them to be indicative of changes in water quality caused by the presence
of dissolved contaminants
13311 Habitat Characterization for Gallups Quarry Superfund Site US Fish and Wildlife Service March 1995
In June of 1993 the US Fish and Wildlife Service conducted a field survey for the purposes of
characterizing the habitat of the Site and surrounding wetland and stream ecosystems The study
was qualitative in nature conducted on foot by trained biologists with the objective of correlating
observations on habitat (primarily vegetation) with known reference material such as topography
maps and aerial photographs The study also included direct and indirect (eg animal tracks)
observations to assess the presence (or absence) of wildlife
The report provides a description of methods and general Site characteristics as well as a more
detailed discussion of wildlife habitat for both the Site and the Mill Brook wetland ecosystem
The study is partial in that it accents what types of animals would be anticipated to be present for
each habitat type even though most of these animals were not directly observed
The report concludes with a description of 29 different types of cover that can be cross-
referenced to areas delineated on a Site map (not to scale) Several Tables are also presented
which inventory birds mammals reptiles amphibians trees shrubs and herbaceous vegetation
that were either observed or would be expected to inhabit the Site
5797wpdocsgalluprifinaItextmasterriftil061297 1-14 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
13312 Adjacent Properties Incident Reports and File Review 1995
To supplement data obtained during the Phase 1A field program a CTDEP file search was
performed to obtain information pertinent to groundwater contamination for industrial properties
neighboring the Site The preliminary findings of this review were submitted in a letter from
ESE to EPA on March 28 1995
A number of incident reports were on file regarding two nearby companies Pervel Industries
Inc and InterRoyal Corporation which have the potential to impact conditions within the Study
Area Figure 1-5 shows the locations of these facilities relative to the Site The significant
findings of the file searches are presented below
Pervel Industries
Pervel Industries Inc manufactured plastic film and laminated textile products (eg flocked
velvet) Pervel reportedly occupied two separate facilities north of the Site The main facility
located approximately 2500 feet north of the Site is believed to have been occupied by Pervel
from the 1940s or 1950s to at least the late 1980s This facility abutted the southern side of the
InterRoyal facility described below A second Pervel facility known as the flock plant (presently
operated by Intermark Fabric Corporation) was located approximately 1000 feet north of the
Site just north of Mill Brook The dates of Pervels occupation at the flock plant cannot be
clearly ascertained from the information available in the files however the review of historic
aerial photographs indicate that the facility has existed since the early 1970s
In 1988 at the request of EPA and CTDEP the NUS Corporation performed a Preliminary
Assessment (PA) at the main facility In an effort to determine eligibility for the National
Priorities List (NPL) NUS reviewed the activities associated with the 1984 closure of a sludge
and waste water lagoon located at the facility Based on their review of the available data NUS
recommended that a Screening Site Inspection (SSI) be performed
The NUS PA report also described a 1985 spill of 600 gallons of 111-TCA and a 1987 spill of
300 gallons of toluene at the northernmost facility According to the PA report contaminated soil
and sediment associated with the 1985 spill was excavated and stored in an impoundment at the
flock plant located just north of the Gallups Site The report indicates the presence of
contaminants in the area where the contaminated soil and sediment were stored suggesting that
the impoundment leaked andor there are other (undocumented) environmental concerns at the
flock plant
5797wpdocraquogalluprifinaltextmlaquosterrifhl061297 1-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The results of recent (late 1980s through the early 1990s) quarterly groundwater monitoring
efforts conducted at the former Pervel flock plant (HRP 1993) indicate the presence of a number
of VOC including 111-TCA TCE PCE and 12-DCE well above their respective MCL The
results of these sampling events as summarized in Table 1-3 (from HRP 1993) indicate that
there has been a general decrease in the concentrations of contaminants seen in these wells over
time The highest recorded concentrations for these constituents are as follows 111-TCA (518
ppb) PCE (466 ppb) TCE (63 ppb) and 12-DCE (906 ppb) According to the HRP report
groundwater flow in the vicinity of the former Pervel flock plant is generally from east to west
(towards the northern portion of the Study Area) However these interpretations were based on a
limited number of data points confined to the Pervel flock plant property
InterRoyal Corporation
The InterRoyal Corporation is located adjacent to and just north of the main Pervel facility
described above The CTDEP files include a memorandum from the NUS Corporation to EPA
dated August 18 1989 which references a 1984 Preliminary Assessment performed by CTDEP
which recommended that a low priority Site Inspection be performed The NUS memo presents a
chronology of Site activities up to 1989 which includes CTDEPs 1987 finding that the company
was in violation of several State Hazardous Waste Management regulations and CTDEPs
subsequent revocation of InterRoyals NPDES permit Based on a CTDEP 1988 Site inspection
NUS recommended to EPA that a high priority Screening Site Inspection be conducted
In 1988 InterRoyal contracted an environmental consultant to prepare an environmental
assessment (EA) for the proposed sale of the property The EA report (ERT 1988) concluded
that substantive on-site contamination of groundwater surface water and soils existed The
principal contaminants were identified as VOC (including TCE trans-l2-DCE PCE vinyl
chloride toluene and xylenes) and priority pollutant metals Groundwater flow direction was
described in the EA report as principally towards the south and southwest
5797wpdoc8galluprifinaltextmasterrifhl061297 1-16 QZT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
20 Field Investigations
This Section describes the field methods and procedures used to accomplish the various field
investigation tasks performed during Phase 1A and Phase IB Also included are descriptions of
any deviations from the approved Work Plan As noted in the appropriate subsections any
deviations from the Work Plan were approved by EPA (or EPAs oversight contractor) prior to
implementation Discussions of the findings results and significance of these investigations are
presented in Sections 3 and 4 of this Report
21 Site Survey 211 Initial Site Survey At the start of the Phase 1A field investigation an initial Site survey was performed to confirm
and update the location and elevation of features included in the base map provided by EPA (EPA
drawing number 707600 dated October 14 1993) The initial Site survey also served as Site
control by establishing a 250-foot grid across the entire Site which was identified by the
installation of labelled stakes at the intersection of each 250-foot grid line Horizontal control for
the 250-foot grid (and all subsequently surveyed features) coincides with the Connecticut State
Plane Coordinate System North American Datum of 1927 Vertical control coincides with the
National Geodetic Vertical Datum (NGVD) of 1929 and was established using nearby USGS benchmarks The 250-foot grid (shown on Plate 2-1) provided known reference locations from
which field personnel could measure the locations of Site features
In addition to the 250-foot control grid the initial survey also established a series of parallel lines
(trend lines) across the Site for use during subsequent visual reconnaissance and geophysical
surveys The trend lines (also shown on Plate 2-1) are roughly parallel to the Providence amp Worcester railroad which abuts the western edge of the property The first trend line (Line A)
was located approximately 50 feet east of the railroad right-of-way with subsequent lines (Line
B through Line HH) spaced at 25-foot intervals Each of the trend lines were staked at 250shy
foot intervals using labelled stakes
212 As-Installed Survey
Following the initial Site survey additional surveying events were performed as needed
throughout the duration of the Phase 1A and Phase IB field investigation programs to locate
various sampling locations and other pertinent investigation features These subsequent surveys
were initiated shortly after the completion of each investigation task Besides the various
surveyors control features such as temporary benchmarks and turning points the features
surveyed included wetland delineation flags surface watersediment and wetland soil sampling
5797wpdocsglaquolluprifinlaquoltextrnasterrifhl061297 2-1 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
locations microwells soil vapor points soil borings monitoring wells (existing and newly
installed) stream gauges piezometers and seismic survey lines
All pertinent investigation-related features within approximately 1500 feet of the Site were
included in the survey Several surface watersediment sampling locations beyond 1500 feet from
the Site were not surveyed and their locations are estimated based on their proximity to mapped
physical features such as bridges or roads
The surveying services for this investigation were performed by KWP Associates Inc of Pomfret
Center Connecticut a licensed and registered surveyor in the State of Connecticut The survey
was completed as a third-order plane survey as defined by the standards and specifications in
Exhibit 14-1 of the Compendium of Superfund Field Operations Methods December 1987
(USEPA 1987)
22 Site Reconnaissance 221 Visual Observations of the Ground Surface
A visual reconnaissance of the Site was conducted during an approximate three week period
beginning on August 23 1994 and ending on September 13 1994 During the visual Site
reconnaissance the entire length of each trending line (shown on Plate 2-1) was walked to
identify and map any features which may have been indicative of unknown disposal areas Any
features such as areas of stained soil partially buried man-made objects remnants of buildings
abandoned equipment containers (eg drums tanks) pits depressions mounds and any other
apparent unnatural materials were photographed and noted on field maps and in a field notebook
Also potential disposal features identified during review of historic aerial photographs (Bionetics
Corporation 1990) were located and investigated The locations of features were flagged and
approximated using the survey stakes installed during the initial Site survey The results of the
field reconnaissance were also used to determine additional soil gas sampling locations (described
in Section 25) during subsequent Phase 1A investigations
222 Air Quality Survey
A baseline air quality survey was conducted prior to the start of Phase 1A intrusive field
investigations The survey was performed using a photoionization detector (PID) equipped with
an 117eV lamp to measure total VOC vapors and a direct reading aerosol monitor (RAM-1) to
measure respirable particulates Baseline air quality readings were recorded at eight stations
(AM-1 through AM-8) located across the Site The monitoring stations included areas along the
Site perimeter as well as interior locations at the three known former disposal areas The
locations of the eight baseline air monitoring stations are shown on Plate 2-2
5797wpdocsgalluprifinaltextmlaquo8temfnl061297 2-2 QZT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
In addition to the baseline air quality survey air monitoring was performed on a weekly basis at the eight locations during the entire Phase 1A field investigation Wind direction wind speed
temperature and barometric pressure were also continuously monitored at an on-site
meteorological station
During the Phase IB investigation quantitive air monitoring was performed for site specific
compounds The Phase IB air sampling was performed in the vicinity of the Former Primary
Disposal Area on October 24 1995 This location was selected based on the findings of the
Phase 1A field program Four samples were collected along the perimeter of the Former Primary
Disposal Area at the northern southern eastern and western edges of the perimeter One
background sample was collected at a location approximately 300 feet south of and upwind from the Former Primary Disposal Area The sample locations are shown in Plate 2-2 The samples
were analyzed for the following volatile organic compounds (VOC) toluene ethyl benzene xylenes (total) and tetrachloroethane (PCE) and polychlorinated biphenyls (PCBs)
VOC samples were collected on stainless steel Tenax tubes which were connected to Dupont
Alpha 1 sampling pumps Samples for PCBs were collected on 037z glass fiber filters using
Dupont Alpha 1 and BIOS AirPro 6000D sampling pumps The sampling media was attached to
the sampling pumps using silicone tubing The pumps were secured to wood stakes and
positioned approximately 5 feet above the ground surface
The pumps used to collect the VOC samples were set to pump at a flow rate of between 0014 to
0016 liters per minute and allowed to pump approximately eight hours The pumps used to collect the PCB samples were set to pump at a flow rate of between 27 and 33 liters per minute
and were allowed to pump approximately eight hours All of the sampling pumps were calibrated prior to and after the sampling event using a primary gas flow mini-Buck Model M-5 Calibrator
Ambient meteorological conditions including temperature relative humidity barometric pressure
and wind speed and direction were monitored during the sampling event using ESEs on-site Qualimetrics meteorological monitoring instrument
A VOC and a PCB field blank were collected at background location AS 105 The VOC Tenax
tube and the PCB glass fiber filter were appropriately labeled opened and then immediately
resealed The field blanks were stored and shipped with the samples
At the completion of the sampling event the VOC Tenax sample tubes (including the field blank)
were sealed placed in clean plastic bags and refrigerated at 4degC until they were shipped The
samples were then shipped to the laboratory in coolers The PCB sample filters were sealed
5797wpdocsgalluprifinaltextmasterrifhl061297 2-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
wrapped in bubbie wrap and packed along with the PCB field blank in a cardboard box for
shipment to the laboratory An unopened VOC Tenax tube and PCB glass fiber filter were
submitted with tae samples as a trip blank The VOC Tenax sample field blank and trip blank
tubes were packed in a cooler with ice and sent to ESEs Denver Colorado Laboratory where
they were analyzed by EPA Method TO1 The PCB glass fiber sample field blank and trip
blank filters were sent to ESEs Denver Colorado Laboratory where they were analyzed by
SW846 EPA Method 8080 The results of the air quality survey are discussed in Section 44
223 Exclusion Zone Identification
Prior to the start of Phase 1A field activities preliminary exclusion zones were identified to limit
the risk of workers exposure to potentially hazardous conditions Based on existing data and
observations made during the Site visual reconnaissance the three known former disposal areas
and the area immediately surrounding a former CTDOT asphalt plant structure were staked and
flagged with caution tape A contaminant reduction zone (CRZ) was established adjacent to the
exclusion zone in the prevailing upwind direction during investigations at each location The
CRZ was established for decontamination operations of Site personnel and equipment
224 Project Support Measures
All field investigations were managed from a field office located within an approximate 10000
square foot support center which was situated at the southern end of the Site along Tarbox Road
The support center consisted of an approximate 100 foot by 100 foot area surrounded by a 6 foot-
high chain link fence The support center housed an office trailer an impermeable bermed
decontamination pad lined with 60 mil thick textured HDPE potable water storage tanks storage
units (drums dumpsters and tanks) for investigation derived wastes the weather station and
portable sanitary facilities The office trailer was connected to electric utilities and telephone
service to facilitate normal business and emergency operations A storage trailer for supplies and
equipment was located adjacent to the support center
The field office was used to support field activities by providing the following services
bull personnel sign-in and sign-out sheets
bull daily field activity log book
bull Health amp Safety log book
bull storage of Personal Protective Equipment (PPE)
bull communications center
bull posting of project plans
bull management of project field files
bull briefingmeeting room to coordinate field activities
5797wpdocsgalluprifinaltextmasterrifW061297 2-4 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull meeting place for emergency evacuations and
bull lunch area
The support center also provided an access control point for the Site as it is the only practical
location where four wheeled vehicles could enter or exit the Site Other non-vehicular access
points were blocked with boulders or mounded soils Other access to the Site is limited due to
the presence of heavy vegetation steep slopes and wetlands In addition warning signs
prohibiting trespassing were posted every 100 feet along the Site perimeter prior to the start of
Phase 1A field activities
225 Identification of Sensitive Human Receptors
A survey to identify potential human receptors in the vicinity of the Site was performed This
survey was used to identify any private water supply wells schools nursing homes and day care
facilities located within a one mile radius of the Site The survey was performed by reviewing
available records and documents from the following sources
bull Town of Plainfield Municipal Offices
bull Northeast District Health Department
bull Connecticut Department of Environmental Protection
bull Connecticut Natural Resource Center and
bull Connecticut Department of Health and Addiction Services
In addition to the file reviews interviews were conducted with neighbors and knowledgeable local
people Finally a windshield survey was conducted for the area located within a one mile radius
of the Site
23 Geophysical Surveys During the Phase 1A investigation comprehensive geophysical surveys of the Site were conducted
by Weston Geophysical Corporation of Northborough Massachusetts using electromagnetic
terrain conductivity (EM) magnetometer (MAG) and seismic refraction survey techniques The
purpose of the EM and MAG surveys was to obtain Site-wide screening data to identify the
locations if any of potential subsurface disposal features or objects such as pits trenches drums
or tanks The initial EM and MAG surveys were conducted along each of the trend lines
established during the initial Site survey as shown on Plate 2-1
The purpose of the seismic refraction survey was to determine the location and orientation of the
inferred bedrock fault (if present) in the central portion of the Site Although bedrock
characterization was not one of the intended purposes of the MAG survey subsequent review of
5797wpdocsgalluprifinaltextmasterriftil061297 2-5 QSTT Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
the acquired MAG data provided some information regarding the nature of the shallow bedrock
surface in the central portion of the Site
The presence of heavy vegetation over much of the intended survey area required approximately
two weeks of brush cutting and clearing in order to gain access to the trending lines and to ensure
complete coverage of the Site Once the proposed survey lines were accessible the initial MAG
and EM surveys were conducted along each trending line with data collected at five-foot intervals
The Work Plan stated that the five-foot intervals would be determined by laying a fiberglass
measuring tape along each trend line between survey stakes However the presence of heavy
vegetation prohibited the efficient use of this technique Since the exact locations of any
unexplained anomalies would be later determined during subsequent EM and MAG surveys (and
confirmed during test pit explorations) it was determined that the five-foot intervals could be
efficiently and accurately estimated by an experienced equipment operator by counting paces
between intervals and making adjustments as necessary at each survey stake (which were located
every 250 feet along each line)
As stated in the Work Plan ground penetrating radar (GPR) was to be used if necessary to
further characterize any unexplained anomalies identified during the initial EM and MAG surveys
The presence of abundant vegetation and rough ground surface conditions in the areas of interest
precluded the reasonable use of GPR As approved by EPA the precise locations of unexplained
anomalies identified during the initial EM and MAG surveys were determined during additional
EM and MAG surveys using a finer (5 foot by 5 foot) survey grid superimposed over the general
vicinity of each anomaly
The seismic refraction survey was conducted along six roughly parallel lines which were placed
normal to the anticipated strike of the inferred bedrock fault The locations of the six seismic
lines are shown in Plate 2-3 Each seismic line (Line 1 through 6) is comprised of two 250-foot
long lines which overlap by 125 feet This resulted in a total of 375 feet of continuous coverage
along each line
A complete report provided by Weston Geophysical Corporation describing the theoretical basis
for these surveys is presented as Appendix A Generalized discussions describing the field
methods and equipment used during each geophysical survey are presented below
5797wpdoclaquogalluprifinaltextmastemfnl061297 2-6 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
231 Electromagnetic Terrain Conductivity (EM) Survey
The initial EM survey was performed by Weston Geophysical Corporation over a three day
period (September 14-16 1994) using a Geonics EM-31 electromagnetic terrain conductivity
logger and a Model 720 Polycorder Background terrain conductivity readings were collected at
the beginning and end of each day from an area determined to be relatively free of electrical
interference The background station was located at the extreme southeastern corner of the Site
well away from the overhead electrical lines located along Tarbox Road and Route 12 (Norwich
Road) The EM-31 was calibrated daily by the operator and data was downloaded in the field to
a computer as needed typically twice a day
Following daily calibration the EM survey was performed by the instrument operator who paced
the entire length of each trend line with the EM meter and data logger Terrain conductivity
measurements were made and digitally recorded at five-foot intervals along each line The
presence of surficial objects and other features (eg steel fencing) that would cause interference
or produce anomalies were noted in the field notebook and accounted for during the data
evaluation Terrain conductivity data were subsequently plotted on a base map of the Site and
contoured to produce the terrain conductivity contour map included in the Weston Report in
Appendix A The results of the EM survey are discussed in Section 413
232 Magnetometer (MAG) Survey
The initial MAG survey was conducted by Weston Geophysical Corporation over a period of 7
days (September 7-14 1994) using two GEM-VI and one EGampG Model 856 magnetometers The
two GEM units were used for data acquisition while the EGampG unit was used as a base station to
monitor diurnal changes in the earths magnetic field The base station was established at the
southeastern corner of the Site where there was no interference from metallic objects or overhead powerlines and where no significant magnetic field gradients were observed
The MAG survey was performed by walking each trending line wiih one of the data acquisition
magnetometers (GEM-VI) and recording the magnetic field at every five-foot interval determined
by pacing The MAG data were eventually corrected for diurnal background fluctuations in the
earths magnetic field as determined at the base station and plotted on a base map to produce the
magnetic contour map which is included in the Weston Report in Appendix A The results of the
magnetometer survey are discussed in Section 413
5797wpdocsglaquolluprifinaltextmlaquo8terriftJ061297 2-7 QST Environmental
Gallups Quarry SuperUna1 Project - Remedial Investigation
233 Additional EM and MAG Surveys
In lieu of GPP surveys additional EM and MAG surveys were performed to determine the
precise location of any terrain conductivity or magnetic anomalies which could not be explained
by the presence of surficial metallic debris The additional surveys were performed over a 5-foot
by 5-foot grid in the vicinity of each unexplainable anomaly
A total of four unexplainable anomalies within three separate areas were eventually investigated
with additional EM and MAG surveys Once the locations of the anomalies were accurately
located each anomaly was further assessed by excavating test pits to identify the source of the
anomaly The test pit operations are discussed in Section 214 and the findings of the test pit
excavations are discussed in Section 4133
234 Seismic Refraction Survey
A seismic refraction survey was conducted along six 375-foot lines located within the suspected
fault zone An ABEM Terraloc 24-channel digital recording seismograph system was utilized for data collection The 375-foot spread lengths consisted of two overlapping 250-foot long lines
with geophones spaced in ten-foot intervals The endpoints of each seismic line were staked in
the field to facilitate the subsequent location survey
In accordance with the Work Plan shot points were located at each end point midpoint and
quarter point in addition to an offset from each end point The Work Plan had stated that
seismic energy would be produced by either an elastic wave generator or weight drop However
due to access constraints at the Site EPA approved the use of an alternate energy source For
these surveys seismic energy was generated using 8 gauge seismic shotgun shells discharged
approximately 2 to 3 feet below ground surface
The energy created by the shell blast travels through the ground and refracts along interfaces
between materials of different propagation velocity and density characteristics Interpretation of
these data on a time vs distance plot is conducted for the seismic wave arrival times at each
geophone The propagation velocities can be categorized into various geologic materials such as
overburden saturated overburden bedrock formations and weathered or fractured formations A
comprehensive discussion of the theoretical basis and operation of this technique is presented in
the Weston Geophysical report provided as Appendix A The results of the seismic refraction
survey are discussed in Section 32
5797wpdoc8gaIIuprifinaltextmasterrifnl061297 2-8 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
24 Groundwater Sampling Using Temporary Well Points Between August 29 and October 7 1994 a total of 60 small-diameter temporary well points
(microwells) were installed at predetermined locations using direct push techniques for the
purpose of collecting groundwater samples for both on-site and off-site chemical analysis At 10
of these locations equipment refusal occurred prior to encountering groundwater thus reducing
the total number of sampled locations to 50 The results of the chemical analyses were used to
determine the nature and extent (both horizontal and vertical) of groundwater contamination (VOC
and metals) within the Study Area Data obtained during this survey were ultimately used to determine the optimum location for subsequently-installed permanent groundwater monitoring
wells The surveyed locations of the temporary well points (TW101-TW160) including the 10 unsampled locations are shown on Plate 2-4 A summary of the locations and depth intervals for
each microwell is presented in Table 2-1
A total of 126 samples were analyzed on-site for selected VOC using a portable gas chromatograph (GC) A total of 121 samples (not including duplicates and field blanks) were
submitted for off-site laboratory analysis for cyanide and metals Also 12 samples (not including
field blanks and trip blanks) were submitted for off-site laboratory analysis for VOC to confirm
the on-site GC analytical data
The microwells were comprised of a 082 inch diameter (062 inch inside diameter) steel riser
pipe of varying lengths equipped with a hardened steel tip and a 5 foot long slotted section at the
leading end The 5 foot long slotted section (or screen) consisted of a four longitudinal rows of 2
inch long by 0015 inch wide slots Each microwell was advanced into the subsurface using
either an electrically or hydraulically powered vibratory impact hammer which was mounted on a
telescoping mast The mast drive-hammer and all other ancillary equipment were mounted on an all-terrain vehicle for maximum mobility
Individual sections of riser pipe (which varied in length up to a maximum of 21 feet) were
connected using a slip coupling over the butted ends of adjacent sections The slip coupling is
either electrically welded or crimped (using a hydraulic crimping tool) over the connection to
form a water tight joint
All materials were steam cleaned prior to use and only used at one location to avoid cross
contamination between sampling locations
The objective at each location was to drive the microwell into the saturated overburden and collect
a groundwater sample from three successively deeper intervals The desired sampling intervals
were as follows five feet below the top of the water table midway between the top and bottom of
5797wpdocsgalluprifinaltextmlaquoraquotemfhl061297 2-9 QST Environmental
Gallups Quarry SuperUna1 Project - Remedial Investigation
the aquifer and at the bottom of the aquifer (ie the refusal depth) A middle andor deep sample
was not collected if refusal was encountered without significant advancement of the well point
between sample depths (minimum of 10 feet) The midpoint sampling depth was estimated based
on the refusal depths encountered at nearby microwells
Once the microwell was driven to the desired depth purging and sampling was accomplished
using a manually operated inertial pump comprised of an adequate length of dedicated 38 inch
(inside diameter) polyethylene tubing equipped with a bottom check valve In operation the
inertial pump is lowered into the screen section of the microwell and repeatedly raised and
lowered (manually) a distance of approximately one foot This reciprocating action causes water
to rise within the tube until it is ultimately discharged at the ground surface into either a bucket or
sample container Between one and three riser volumes were purged from each microwell prior
to sample collection except for the first sample (5 feet below the top of the water table) which was
collected without purging All purge water was containerized and eventually transported off-site
for treatment and disposal
Once a groundwater sample was acquired it was labelled packed in a cooler and transported to
the on-site laboratory Each sample was analyzed on-site using a portable gas chromatograph
for the following eight VOC
bull l2-dichloroethene(DCE)
bull 111 -trichloroethane (111 TCA)
bull trichloroethene (TCE)
bull benzene
bull toluene
bull acetone
bull methyl ethyl ketone (MEK)
bull methyl iso-butyl ketone (MIBK)
Groundwater samples from each location were also collected filtered through a 045 micron
filter preserved with nitric acid and submitted to an off-site laboratory for analysis for the
following metals
bull aluminum
bull arsenic
bull cadmium
bull chromium
bull copper
5797wpdoc8galluprifinaltextmasterrifhl061297 2-10 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
bull iron
bull lead
bull manganese
bull nickel
bull zinc
Unfiltered samples were also collected preserved with sodium hydroxide (NaOH) and submitted
for analysis for cyanide In addition duplicates of 12 of the VOC samples analyzed in the field
were submitted for laboratory analysis for VOC for confirmation purposes Samples for off-site
VOC analyses were preserved in the field by addition of hydrochloric acid (HC1) to obtain a pH
less than 2
Samples for on-site VOC analyses were collected into 40 ml glass vials equipped with a teflonshy
lined silicon septum Each vial was filled capped labelled and refrigerated until it was
analyzed Samples were typically analyzed within several hours of collection Prior to analysis
the sample was removed from the refrigerator and 10 ml of water was withdrawn and discarded
The withdrawal of 10 ml of water created a headspace within each vial into which any VOC
present in the liquid would partition To complete the VOC partitioning process the vial was
then placed into a constant temperature (90 degC) water bath for a minimum of 15 minutes Just
prior to analysis a 250 micro-liter air sample was withdrawn from the headspace within the vial
by inserting the needle of the syringe through the teflon-lined septum and injected into the
portable gas chromatograph for analysis
A Photovac 10S50 portable gas chromatograph equipped with a CPCIL 5 encapsulated column
was used for on-site analysis The Photovac 10S50 gas chromatograph (GC) was filled every
morning with zero grade air and allowed to warm-up for 30 minutes prior to daily operation in
accordance with SOP 4001 and manufacturers instructions
The GC detector flow oven temperature and gain setting (sensitivity setting) were checked and
verified every morning and throughout the day Field GC standards were prepared daily by
diluting commercially available certified pure liquid chemical standards with deionized water
Three separate standards a low-concentration level a mid-concentration level and a high-
concentration level standard containing the eight select VOC were prepared in order to obtain a
three-point calibration curve Glass gas-tight syringes were used for preparation of standards and
sample injection AH syringes were decontaminated using methanol deionized water and
compressed gaseous nitrogen
5797wpdocsgalluprifinaltextmlaquo8terrifhl061297 2-11 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The GC operating condition was checked in the morning and during the day using machine
blanks syringa blanks and standards All three standards were run with a syringe blank directly
before and after each injection after every ten samples and at least once in the morning and once
in the afternoon each day In accordance with the QAQC program and SOP 4009 a duplicate
groundwater sample was collected in the field in a separate 40 ml glass vial immediately
following the collection of the original sample The second vial was used for duplicate analyses
after every ten samples
In the event that a sample analysis showed a contaminant chromatographic peak with an area
greater than the high-concentration standard or the range of the GC operating parameters (off-
scale) a smaller aliquot (l10th the original sample injection volume) was taken from the second
vial and injected into the GC All pertinent information concerning the smaller aliquot was
recorded on the GC strip chart and in the field log book
The GC strip chart was labeled with the sample identification number or corresponding
identification information (eg sample ID syringe blank etc) All pertinent information (eg
sample ID) was recorded in a field log book
In accordance with the QAQC program all samples were kept at 4degC prior to analysis and were
analyzed within 48 hours of their collection time
A total of 23 microwells (TW101-TW123) were installed by Pine and Swallow Associates Inc of
Groton Massachusetts Due to limited ability to access certain locations with the available
equipment the remaining 37 microwells were installed by a second subcontractor MyKroWaters
Inc of Concord Massachusetts Installation logs are presented in Appendix B The results of
the microwell survey are discussed in Section 421 The microwell installations were later
abandoned by filling them with cement grout and cutting the risers off below the ground surface
25 Soil Gas Survey In an effort to identify the location of any previously unknown potential disposal areas a Site-
wide soil gas survey was conducted From September 26 1994 through October 12 1994 a
total of 106 soil gas sampling probes were installed across the Site Soil gas samples were
analyzed on-site using a portable gas chromatograph
A 100-foot sampling grid was used to systematically cover the Site however actual locations
were dependent on accessibility and the ability to advance the soil gas probes to the desired depth
beneath the ground surface Besides the sampling at the intersection of grid lines six additional
locations were investigated due to the presence of empty drums found at the ground surface
5797wpdoC8galluprifinaltextmastemfnl061297 2-12 QST Environmental
Gallups Quarry Superfiind Project - Remedial Investigation
during the Site reconnaissance or anomalies detected during the EM and MAG surveys The
extreme northeastern corner and eastern side of the Site were not included in the soil gas survey
since they are either wetlands or heavily wooded Also an approximate 15000 square foot area
just north of the Former Seepage Bed was not tested due to the presence of a large pile of
boulders The surveyed locations of each soil gas sampling point (SV101-SV206) are shown in
Plate 2-5 The locations of SV111 SV201 and SV141 are approximate based on field
measurements from surveyed locations
Each soil gas sampling probe consisted of a four inch long hardened steel combination drive
point and screen which was connected to an adequate length of 316 inch diameter polyethylene
tubing The pointscreen and tubing assembly were inserted inside a hollow steel shaft which was
then driven into the ground with an electrically powered vibratory hammer
An abundance of gravel cobbles and boulders in the central portion of the Site prohibited the
advancement of several probes to the minimum depth specified in the Work Plan (25 feet) After
discussions with EPAs oversight contractor regarding the surface conditions in this area it was
agreed that at the rocky locations the probe would be driven as far as possible (typically 15-2
feet) and a two-foot by two-foot sheet of polyethylene sheeting would be placed on the ground
surface surrounding the probe and weighted with native topsoil The purpose of the plastic sheet
was to minimize atmospheric influence during the sampling procedure
Once the point was driven to the sampling depth the hollow steel shaft was extracted leaving the
expendable pointscreen and tubing in place The small annular space surrounding the sampling
tube was tightly packed with native soil to ensure that gas samples were representative of soil
pore space and not atmospheric conditions Once the probe was in place any excess plastic
tubing was trimmed leaving approximately 15 feet of tubing above the ground surface Each
tube was clamped and sealed until it was eventually sampled typically within a few days of
installation
To collect a soil gas sample one end of a 280 ml glass sample chamber (equipped with teflon
stopcocks and a sampling septum) was connected to the tubing using a short length of silicon
tubing A battery-operated vacuum pump was then attached to the other end of the chamber and
used to draw a soil gas sample from the tubing Once a sample was acquired the stopcocks were
closed and the pump shut off The sample chamber was then transported to the on-site laboratory
for analysis
Just prior to analysis the needle of a gas tight syringe was inserted through the sampling septum of the glass chamber and an aliquot of the soil gas sample was removed The sample was then
5797wpdoclaquogalluprifinaltextma8terrifiU061297 2-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
injected into the gas chromatograph for analysis A Photovac 10S50 portable gas chromatograph
was used to analyze each sample for the following 8 VOC
bull l2-dichloroethene(DCE)
bull 111-trichloroethane (111 TCA)
bull trichloroethene (TCE)
bull benzene
bull toluene
bull acetone
bull methyl ethyl ketone (MEK)
bull methyl iso-butyl ketone (MIBK)
The Photovac 10S50 gas chromatograph (GC) was filled every morning with zero grade air and
allowed to warm-up for 30 minutes prior to daily operation in accordance with SOP 4001 and
manufacturers instructions
The GC detector flow oven temperature and gain setting (sensitivity setting) were checked and
verified every morning and throughout the day Field GC standards were prepared daily using
certified pure neat liquid standards from sealed vials Glass gas tight syringes were used for
preparation of standards and sample injection All syringes were decontaminated using methanol
deionized water and nitrogen
The GC operating condition was checked in the morning and during the day using machine
blanks syringe blanks and standards Standards were run with a syringe blank directly before
and after each injection every ten samples In accordance with the QAQC program a duplicate
soil gas sample was collected in the field in a separate glass sample chamber immediately
following the collection of the original sample After the original sample was injected into the
GC the duplicate sample from the separate glass sample chamber was injected into the GC The
data quality objective (DQO) for field analysis using the GC was maintained at or better than _+
30 relative percent difference In the event that a sample analysis showed a contaminant
chromatographic peak with an area greater than the range of the GC operating parameters (off-
scale) a smaller aliquot (I10th the original sample injection volume) was taken from the glass
sample chamber and injected into the GC AH pertinent information concerning the smaller
aliquot was recorded on the GC strip chart and in the field log book
5797wpdocsgalluprifinaltextma8teiTifiil061297 2-14 QST Environmental
Gattups Quarry Superfund Project - Remedial Investigation
The GC strip chart was labeled with the sample identification number or corresponding
identification (eg sample ID syringe blank etc) The analysis number and corresponding
identification information was also recorded in the soil gas survey field log book
All sampling equipment (exclusive of the dedicated expendable probes) was decontaminated between each sample by flushing with copious amounts of compressed nitrogen The results of the
soil gas survey are discussed in Section 41
26 Soil Borings at Disposal Areas A total of sixteen soil borings SB101 through SB116 were advanced at the three known former disposal areas Ten soil borings (SB 101 through SB110) were completed as part of the Phase 1A
investigation between October 4 and 13 1994 Six additional borings were advanced within the
Former Primary Disposal Area on November 2 1995 as part of the Phase IB investigation The
locations of the soil borings are shown on Plate 2-5 The objective of these borings was to obtain
soil samples to characterize subsurface lithology and determine the present level and distribution
of residual contaminants within each former disposal area The analyses performed on samples
collected during the Phase 1A investigation (ie SB101-SB110) included TCLTAL parameters
as well as pH (EPA Method 9045) total organic carbon (ASTM Method D 17565373) moisture
content and particle size distribution Samples collected during the Phase IB investigation
(SB111-SB116) were submitted for laboratory analyses for VOC and PCBPesticides The samples submitted for analysis and the depth intervals sampled are shown in Table 2-2 The
results of the soil boring program are discussed in Section 41 All soil boring logs are shown in
Appendix C
261 Piiase 1A Soil Borings Each boring completed as part of the Phase 1A investigation was advanced until equipment refusal was encountered using a truck mounted drill rig equipped with a 425 inch (inside diameter)
hollow stem augers The drilling operations were performed by Environmental Drilling Inc of
Sterling Massachusetts As shown in Plate 2-5 three of the borings were placed in the reported
location of the Former Seepage Bed (SB101-SB103) three were placed within the Former
Secondary Disposal Area (SB104-SB106) and four were placed within the Former Primary
Disposal Area (SB107-SB110) The Work Plan required that samples be collected and submitted
for laboratory analysis from each boring from specific depth intervals (0-1 foot 1 to 10 feet and
10 feet to the water table) and from each distinct hydrological unit encountered (eg coarse
stratified drift fine stratified drift and till) and from the capillary fringe at each disposal area
The number of samples actually submitted for analysis was dependent on the depth to water and
the number of hydrogeologic horizons encountered at each area In general samples submitted
579Twpdoc8galluprifinaltextmlaquo8terrifhl061297 2-15 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
for laboratory analysis were selected from within each depth range or horizon based on PID
readings andcr visual observations
Soil samples from the 0-1 foot interval were collected from the ground surface using a stainless
steel hand trowel All subsequent samples were collected using a standard 2-inch diameter split-
spoon sampling device in accordance with ASTM Method D-1586-84 Each sample was
screened in the field for total VOC using a PID equipped with an 117 eV lamp Each sample
was then visually classified and logged in a field notebook and on boring logs A portion of each
sample was placed into glass jars and sealed with aluminum foil and a screw cap for headspace
analysis The headspace sample was ultimately saved for archival purposes
All sampling equipment was decontaminated prior to use and between each sample using a
detergent wash and tap water rinse followed by methanol nitric acid and deionized water rinses
All drilling equipment was steam cleaned between boring locations All decontamination rinseates
were containerized and eventually transported off-site for treatment and disposal Likewise all
soil cuttings were containerized for eventual off-site disposal Upon completion each borehole
was filled to the ground surface with a bentonitecement grout mixture and marked with a labeled
stake so that its location could be surveyed
262 Phase IB Soil Borings
Data obtained during the Phase 1A investigation indicate the presence of residual soil
contamination in the vicinity of the Former Primary Disposal Area In order to more fully
characterize the extent of this residual contamination six additional soil borings were completed
along the perimeter and within the Former Primary Disposal Area These borings (SB111shy
SB116) were installed by Connecticut Test Borings Inc of Seymour Connecticut using a track
mounted drill rig equipped with a standard split-spoon soil sampler Two samples from each
boring were submitted for laboratory analysis of TCL VOC and pesticidesPCBs At each
location a surface soil sample was collected from the 0-1 foot interval and submitted for
laboratory analysis Soil samples were then collected continuously from a depth of 1 foot below
the ground surface to the water table A discrete sample from within this zone was submitted for
laboratory analysis based on PID results At locations where no elevated PID headspace readings
were encountered a sample collected from the capillary zone was submitted for laboratory
analysis
5797wpdocsglaquolluprifinaItextmraquo8terrifiil061297 2-16 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
27 Installation of Monitoring Wells and Background Soils Sampling
Following the evaluation of data obtained during the visual Site reconnaissance and microwell
and soil gas surveys a network of monitoring wells was designed that would allow groundwater sampling and analysis and measurements of hydraulic parameters The installation of monitoring
wells at upgradient locations was also included to allow collection of background soil samples and
to determine upgradient groundwater quality
The majority of the Phase 1A investigation monitoring wells were installed by Environmental
Drilling Inc of Sterling MA A second drilling contractor Maher Environmental of North Reading MA was added in December in order to complete the monitoring well program before
the onset of winter The well installation program began on November 7 1994 and was completed on December 29 1994
The original Work Plan specified that a total of 47 monitoring wells would be installed but contemplated that the final number and locations of the monitoring wells could be adjusted based
on the findings of the preliminary screening surveys (ie the microwell and soil gas surveys)
Based on these data which were presented to EPA throughout the course of the screening surveys
EPA approved a Phase 1A monitoring well network which consisted of a total of 39 monitoring
wells at 16 locations
During the course of the Phase 1A monitoring well installation program one anticipated
intermediate depth overburden well (MW109T) was not installed because there was only
approximately 35 feet of saturated overburden encountered at that location A total of 38
monitoring wells at 16 locations were installed The surveyed locations of these wells are shown on Plate 2-6
By the end of the Phase 1A field program a total of 16 locations (or clusters) were completed
and were comprised of the following
bull (2) four well clusters (MW105 and MW107)
bull (4) three well clusters (MW101 MW108 MW112 and MW115) bull (8) two well clusters (MW102 MW103 MW104 MW106 MW109 MW113
MW114 andMW116) and
bull (2) single wells (MW110 and MW111)
(Note An additional 6 groundwater piezometers [PZ201-PZ206] were also installed)
5797wpdocsgalluprifinaltextmasterrifhl061297 2-17 QST Environmental
Gallups Quarry Superjvnd Project - Remedial Investigation
To further delineate the nature and extent of contamination and to refine the hydrogeologic
characteristics within the area of investigation a total of seven groundwater monitoring wells (and
one piezometer PZ301) were installed as part of the Phase IB investigation
The wells completed during Phase IB included the following
bull (3) two well clusters (MW117 MW118 and MW119)
bull (1) bedrock well (installed at the Phase 1A location MW102)
All Phase IB monitoring wells were installed by Connecticut Test Boring Inc utilizing a track-
mounted drill rig The surveyed locations of these wells are shown on Plate 2-6
AH monitoring well labels include a suffix code (eg S TT T or B) which indicates the location
of the screened interval (or open interval in the case of bedrock wells) for that particular well
The screen interval for each prefix is
S - Shallow well in which the screen intersects the surface of the water table
TT - Top-of-Till well in which the bottom of the screen is located just above the till
horizon
T - Till well in which the screen was placed within the till horizon and
B - Bedrock well in which the overburden is sealed off with steel casing which is
grouted into the bedrock surface and the well consists of an unscreened open hole
below the top of the bedrock surface
The TT T and B designations are geologically specific (top-of-till till or bedrock) while the S
designation is depth specific Monitoring well MW109S is in fact located within a till horizon but
was designated as an S well since the screen intersected the surface of the water table Similarly
although monitoring well MW110S is designated as a shallow(s) well observations recorded
during its installation indicate that MW110S is set just below the top-of-till interval
Specifically the 45 wells completed during the Phase 1A and IB investigations included the
following
bull 18 shallow (S) water table wells
bull 13 top of till (TT) wells
5797wpdoc8galluprifinaltextmasterrifhl061297 2-18 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull 5 till (T) wells and
bull 9 bedrock (B) wells
271 Phase 1A Monitoring Well Placement-Rationale
2711 Phase 1A Upgradient Monitoring Wells and Background Soil Sampling
Two monitoring well clusters MW109 (S B) and MW112 (S TT B) were installed to provide
soil and groundwater samples from various depths from locations upgradient of the known former
disposal areas These data were obtained to provide chemical data which was assumed to be
representative of background conditions The general location of these two well clusters was in
accordance with the general east to west direction of groundwater flow across the Site which had
been indicated during previous investigations and by the location of the contaminant plume
identified during the microwell survey The location of MW112 cluster (south of the Former
Seepage Bed) would also serve to confirm the presence or absence of radial groundwater flow
patterns away from the Former Seepage Bed During the installation of these wells soil samples
from stratified drift and till horizons were collected and submitted for laboratory analysis for
TALTCL parameters
A shallow top of till and bedrock well were installed at location MW112 The overburden wells
at this location were successfully installed using hollow stem augers A shallow till and bedrock
well were planned for location MW109 However since only approximately 35 feet of saturated
overburden was encountered at that location only one well MW109S was installed in the
overburden
The overburden and bedrock monitoring wells at these locations were constructed in accordance
with the general procedures described above with the exception of MW109S An abundance of boulders at this location prohibited the ability to advance augers or drive casing more than several
feet below the ground surface After numerous attempts within a 100-foot radius of the desired
location a backhoe was ultimately required to excavate a pilot hole in the unsaturated zone to
approximately 8 feet below the ground surface Augers were then lowered into the pilot hole and
advanced to the refusal depth of 12 feet The overburden well was then constructed as described
in Section 273
The bedrock well at MW109 was installed using a mud rotary drilling technique to drill an
overburden pilot hole to the bedrock surface into which 5-inch diameter steel casing was lowered
and seated on the top of the bedrock surface Another pilot hole was then drilled into the bedrock
to receive the permanent 3-inch casing The bedrock was subsequently cored as described in
Section 273
5797wpdoC8galluprifinaltextmaBterriftU061297 2-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
2712 Phase 1A Monitoring Wells - Former Primary and Secondary Disposal Areas
A total of nineteen ground water monitoring wells were installed in seven cluster locations at
downgradient areas relative to the known Former Primary and Secondary Disposal Areas
Monitoring wells MW102 (S TT) MW105 (S TT T B) and MW107 (S TT T B) were
located along the centerline of a groundwater contaminant plume detected during the microwell
survey and earlier studies
Well clusters MW101 (S TT T) MW103 (S TT) MW104 (S TT) and MW106 (S TT) were
located in areas believed to be beyond the edges of the contaminant plume delineated during the
microwell survey These wells were placed at these locations in an effort to define the plume
boundaries In addition the location of MW103 was selected by EPA to address historic
references to a leachate seep reportedly observed at Mill Brook west of the railroad bridge
Besides the nineteen wells described above another six monitoring wells at three locations were
installed in the vicinity of the Former Primary and Secondary Disposal Areas MW116 (S T) MW108 (S TT B) and MW110S were located north northeast and east of the former disposal
areas respectively to confirm the plume boundaries in these areas
2713 Phase 1A Monitoring Wells - Former Seepage Bed Area
A total of three monitoring wells were installed in the general vicinity of the Former Seepage
Bed A single bedrock well MW11 IB was placed west of the Former Seepage Bed within the
potential fracturefault zone identified by the geophysical studies The purpose of this well was to
assist in evaluation of whether the inferred fracturefault zone may be acting as a preferential
contaminant transport pathway from the Former Seepage Bed The location of MW113 (S B)
west of the Former Seepage Bed was selected to confirm water quality and to obtain
hydrogeological data in this area since an abundance of cobbles prohibited the advancement of
microwells into the saturated zone in this area
2714 Phase 1A Monitoring Wells - Southern Portion of the Site
Five monitoring wells located at two clusters (MW114 and MW115) were installed to determine
water quality and to characterize the hydrogeological parameters in the southern portion of the
Site Although there is no evidence to suggest that disposal activities occurred in areas of the Site
south of the Former Seepage Bed MW114 (S TT) and MW115 (S TT B) were placed to
coincide with locations at which low levels of VOC were detected during the microwell survey
5797wpdocsgalluprifinaltextmasterri fhl061297 2-20 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
272 Phase IB Monitoring Well Placement-Rationale The results of the Phase 1A investigation indicate that a well-defined low to moderate-VOC
concentration groundwater plume originates in the vicinity of the Former Primary Disposal Area
The plume is defined by the presence of certain VOC primarily TCA 12-DCE and xylene The
highest concentrations of these compounds were detected at MW107TT with decreasing
concentrations at downgradient well clusters MW105 MW102 and MW101
The compound PCE was detected in groundwater monitoring wells within the plume but its
distribution in groundwater exhibited inconsistencies with migration from the former disposal
areas In addition the observed concentrations of PCE did not coincide with the observed rate of
plume attenuation and transport rates possibly indicating an off-site source A goal of the Phase
IB investigation was to obtain additional information concerning overburden groundwater quality
and flow patterns in the area north-northwest of the Former Primary Disposal Area in order to
assess the potential for an off-site source
2721 Phase IB Monitoring Wells-Former Primary and Secondary Disposal Areas
One bedrock monitoring well (MW102B) was installed downgradient of the Former Primary and
Secondary Disposal Areas as part of the Phase IB investigation Data collected during the Phase
1A field program indicate that bedrock hydraulic gradients are generally upward across the Study
Area and that bedrock is not a preferential pathway for contaminant migration However low
concentrations of certain VOC were detected in bedrock well MW105B located downgradient of
the Former Primary Disposal Area To determine the nature of contaminant migration in bedrock
further downgradient from the source area a bedrock monitoring well was installed in the vicinity
of well cluster MW102 During the installation of MW102B soil samples were collected from
three intervals within the saturated portion of the overburden aquifer (15-17 30-32 and 45-57
feet below the ground surface) and submitted for laboratory analysis for total organic carbon
(EPA Method 9060)
2722 Phase IB Monitoring Well - North-Northwest of the Site Data obtained from CTDEP files during the Phase 1A investigation indicate that monitoring wells
located on the western and northern sides of the former Pervel flock plant (located just north of
the Site across Mill Brook) historically contained elevated concentrations of certain VOC
particularly PCE TCA and DCE A contribution of VOC in groundwater from this area could
explain at least partly the VOC detections in the wells at MW101 To confirm the potential for
groundwater flow from the former Pervel facility to the area around well MW101 and to further
refine the understanding of groundwater quality and flow in areas north-northwest of the Former
Primary Disposal Area three additional monitoring well couplets and one groundwater piezometer
5797wpdocsgalluprifinaltextmasterrifiil061297 2-21 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
were installed The Phase IB well couplets designated as MW117 MW118 and MW119
consisted of a shallow overburden well and a deep monitoring well screened above the till
horizon A groundwater piezometer designated as PZ-301 was installed in this area to provide
additional hydraulic data The surveyed locations of the seven monitoring wells and the
piezometer installed as part of the Phase IB investigation are shown on Plate 2-6
273 General Monitoring Well Installation Techniques
At each monitoring well (or cluster) location continuous soil sampling was initiated using either a
truck or track mounted drill rig equipped with 425 inch (ID) hollow stem augers and standard 2shy
inch diameter split-spoons The objective was to continuously sample and complete the deepest
overburden boring at each location using hollow stem augers A variety of subsurface conditions
(eg running sands greater that anticipated saturated overburden thicknesses and an abundance of
cobbles and boulders) prohibited the use of hollow stem augers all the way to completion depth at
many locations In order to overcome these drilling conditions EPA approved drive and wash
drilling techniques using water as a drilling fluid to complete many of the deeper overburden
monitoring wells The source of drilling water for this investigation was a nearby fire hydrant
which is connected to the local municipal potable supply system The introduction of drilling
fluids is generally avoided whenever possible as the presence of foreign fluids may cause some
dilution of any constituents which may be present The subsequent use of low-flow purging and
sampling techniques (discussed in Section 29) gave maximum assurance that samples collected
were representative of the natural formation waters
When drive and wash techniques were used the preferred casing diameter was six-inches Six-
inch diameter casing allowed the construction of a desired filterpack thickness of two inches (for
two inch diameter wells) However five-inch diameter and in some cases four-inch diameter
casing was also used primarily at locations in which access and drilling conditions prohibited the
advancement of six-inch casing in a timely and efficient manner EPA approved the use of five-
and four- inch diameter casing provided that the resulting monitoring wells were capable of
yielding low turbidity groundwater samples (which they ultimately did)
In accordance with the Work Plan continuous soil sampling was attempted at the deepest boring
at each location to provide continuous stratigraphic control However the presence of
uncontrollable running sands within certain intervals at several locations made the timely
collection of continuous viable samples extremely difficult In an effort to adhere to the original
schedule as closely as possible EPA approved lengthening the sampling frequency from
continuous to five-foot intervals at locations where running sands were encountered
5797wpdocsgalluprifinaltextmasterrifhI061297 2-22 QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
At several locations auger or casing refusal during the sampling stage was encountered above the
expected depth to bedrock (ie within or on top of the till horizon) At certain bedrock locations
which did not require further soil sampling EPA approved advancing and setting casing using
mud rotary drilling techniques In cases where drilling mud was used as the circulation media
powdered bentonite (National Sanitation Foundation International approved) was mixed with
potable water to yield a relatively thin drilling mud Once the borehole was drilled and stabilized
with drilling mud permanent steel casing was advanced and set The drilling mud was then
completely flushed from the borehole using fresh water and containerized (along with the water)
for eventual disposal In general the use of drilling mud is avoided whenever possible to
eliminate the introduction of foreign compounds in the aquifer Since drilling mud was used to
drill through overburden material (at bedrock wells only) and drilling mud was never in contact
with bedrock fractures the use of mud is not believed to have had any impact on groundwater
samples collected from these wells
All overburden monitoring wells were constructed using 2-inch diameter schedule 40 PVC well
screen and riser All screens consisted of continuous slot construction with 001-inch wide slots
The filter pack sand size grade was selected based on grain size data obtained during the soil
boring program The size-grade chosen (Morie OON) was selected in accordance with EPA
requirements (4 to 6 times the mesh size which retained 70 of the formation material) Most
screens were 10 feet long however several wells screened in till were constructed using 5-foot
long screens due to the limited thickness of the till horizon at those locations (MW105T
MW112T and MW116T) and the requirement to not install screens across different geologic
horizons Regardless of the screen length the filterpack surrounding the well screen extended a
minimum of one foot above the top of the screen A minimum two-foot thick seal of hydrated
bentonite clay was then emplaced above the filter sand pack Bentonitecement grout was then pumped from the bottom of the remaining annular space surrounding the riser pipe to the ground
surface Stainless steel centralizers were utilized to center the PVC screen within the borehole
Each well was completed with a locking 4-inch diameter steel protective casing which was
cemented in place approximately five feet below the ground surface
The bedrock wells were completed as open hole monitoring wells A minimum of four-inch
diameter steel casing was driven and seated on the bedrock surface A 3875-inch diameter pilot
hole was then drilled a maximum distance of five feet into competent rock Permanent 3-inch
diameter steel casing was then cemented into the pilot hole using tremie pipe and allowed to cure
for a minimum of 24 hours Once cured the grout inside the three inch casing was drilled out to
allow the bedrock to be cored At each location a minimum of 10 feet and a maximum of 25
feet of rock was cored using standard NX coring equipment The termination of all bedrock
wells was dependent on the occurrence of water-bearing fractures identified within the cored hole
5797wpdocsgalluprifinaltextmasterrifhl061297 2-23 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
Coring was terminated when evidence of water-bearing fractures were encountered All bedrock
wells were corHeted as open bedrock wells (ie not screened) as it appeared that the cpen holes
would not in-fl or collapse Each bedrock well was furnished with a locking 4-inch diameter
steel protective casing which was cemented in place over the permanent 3-inch diameter steel
riser
All monitoring wells were developed to remove residual particulates from the well and filter pack
and to restore the natural permeability of the formation Following well completion a minimum
of 48 hours were allowed to elapse before well development was initiated to allow the wells to
equilibrate and the grout to set Development was accomplished by overpumping various sections
of the screened interval until the field geologist determined that the pump discharge was visibly
free of particulate material Well development times varied from well to well and depended upon
the amount of fine (silt-clay) grained material at each screen interval Well development times
were usually on the order of several hours Water generated during well development was
containerized for eventual shipment off-site
All soil boring logs rock coring logs and monitoring well construction logs are provided in
Appendix C A summary table which shows survey data and other pertinent information for each
monitoring well and piezometer is presented as Table 2-3
274 Stream Piezometers and Gauges
Nine piezometers were installed at various locations within Mill Brook to monitor surface water
conditions and to determine the role of the local groundwater system in relation to stream
dynamics Water levels were recorded during several periods of the investigation to determine if
Mill Brook is a discharge or recharge point for groundwater in the vicinity of the Site In
addition five stream gauges were installed at piezometer locations PZ-1 PZ-3 and PZ-6 and at
two additional locations in Fry Brook one above and one below the confluence with Mill Brook
The locations of the stream piezometers and gauges are shown on Plate 2-6
Each stream piezometer consisted of a one-foot long slotted steel well point connected to threaded
and coupled lengths 125 inch ID steel pipe with a threaded cap The piezometers were
manually driven a minimum of two feet into the stream bed Water level readings were collected
by lowering an electronic water level indicator along both the inside and outside of the piezometer
to obtain depth to water readings for shallow groundwater beneath the stream bed and depth to
surface water respectively The stream gauges consist of a graduated steel scale attached to a
steel post which was driven into the stream bed
5797wpdocsgalluprifinaltex1masterrifhl061297 2-24 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
275 Groundwater Piezometers
Although not specified in the Phase 1A Work Plan EPA approved the installation of six shallow
groundwater piezometers (PZ-201 through PZ-206) in the southern portion of the Study Area to
provide additional overburden piezometric data A seventh groundwater piezometer PZ-301
was installed north of the Site during the Phase IB investigation The locations of the
groundwater piezometers PZ-201 through PZ-206 and PZ-301 are provided on Plate 2-6
The seven groundwater piezometers were installed using either a track or a truck-mounted drill
rig equipped with 425 inside diameter hollow stem augers At each location the augers were
advanced and the piezometer set at approximately five feet below the top of the groundwater
table The piezometers were constructed of 1-inch diameter PVC well screen and riser equipped
with five-foot long screens Once the screen was set a sand pack was installed to approximately
one foot above the top of the screen A hydrated bentonite seal was then emplaced on top of the
filterpack The remainder of die annular space was backfilled with clean native soil and capped
with concrete Each piezometer was furnished with a lockable protective casing which was
cemented in place Upon completion each piezometer was surveyed and included in each
subsequent round of groundwater level measurements
28 Aquifer Parameter Testing 281 Grain Size Analysis
A total of 41 soil samples collected during the Phase 1A soil boring and monitoring well
installation programs were submitted for laboratory grain size analysis All grain size analyses
were performed using common sieve and hydrometer techniques in accordance with ASTM
Method D 422-63 (Reapproved 1990)
Of the 41 samples 16 were obtained from horizons described as fine stratified drift 15 were
obtained from horizons described as coarse stratified drift and 10 were obtained from horizons
described as till A total of 29 of the samples were obtained during the soil boring program
and 12 were obtained from samples collected during the monitoring well installation program
The analyses were conducted by Geotechnics Inc of Pittsburgh PA a laboratory which
specializes in geotechnical analyses A summary of the samples submitted and their depth interval
is presented as Table 2-4 The results of grain size analyses are discussed in Section 33 In
addition to grain size these samples were also submitted for laboratory analysis for pH moisture
content and total organic carbon
5797wpdoc8galluprifinaltextmasterrifhl061297 2-25 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
282 Slug Tests
Single-well variable head aquifer tests were conducted on all the wells installed during the Phase
1A investigation between January 5 and 27 1995 Rising and falling head tests were performed
on each well using a manually deployed solid cylinder or slug A pressure transducer and an
electronic data logger were used to measure and record the water level response in the well (on a
logarithmic time scale) after the slug was submerged (falling head) and removed (rising head)
Changes in water levels were recorded until the water had returned to or near the original static
level The data collected from the slug tests were analyzed to determine hydraulic conductivity
values for the screened intervals in each well The rate of change of hydraulic head was analyzed
using the Bouwer-Rice Method (Bouwer and Rice 1976) implemented in the computer program
AQTESOLV (Geraghty amp Miller Inc 1989) The results are presented in Section 33 of this
report
283 Constant Flow Tests
Constant flow tests consisting of short-term pumping tests were performed on selected
groundwater monitoring wells as part of the Phase IB investigation Constant flow tests were performed on the following wells MW102TT MW103TT MW104TT MW105TT
MW107TT MW117(S TT) MW118(S T) and MW119(S TT) In these tests an approximate
steady-state drawdown is established in the well and an analytical model of flow to a well is used
to compute hydraulic conductivity The tests were conducted using a variable speed submersible
pump and an electronic water level indicator Prior to the start of each test the static water level
was determined The tests were conducted by running the pumps at a constant known pumping
rate for short periods of time (typically less than 15 minutes) while recording drawdown until
equilibrium was reached The pumping rate drawdown and well construction details were then
used to calculate the hydraulic conductivity The results of the constant flow tests are discussed
in Section 33 of this report Field data and examples of the data reduction method are presented
in Appendix F
29 Groundwater Sampling In accordance with the Work Plan a complete round of groundwater samples was collected
following completion of the Phase 1A monitoring well installation program during January 11shy
19 1995 and is referred to as the Phase lAJanuary 1995 sampling event Subsequent
sampling events were performed as part of the Long Term Monitoring Program during April
July and November 1995 February May August and November 1996 and February 1997 As
discussed in Section 1-1 of this report individual Data Reports for all of the Long-Term
Monitoring Program sampling events (except November 1995 which was presented with the draft
RI Report) have been submitted to EPA
5797wpdoc8galIuprifin8ltextma8terrifnl061297 2-26 QZT Environmental
Gallups Quarry Suptrfund Project - Remedial Investigation
During the Phase IB field program seven new wells were installed and added to the list of wells
that were sampled (for VOC only) during the November 1995 monitoring event Six of these
wells (MW117STT MW118STT and MW119STT) were not added to the list of wells to be
sampled under the Long Term Monitoring Program although MW102B (also installed during
Phase IB) was added to the Long Term Monitoring list In addition to the wells installed during
the Phase IB investigation the following five existing wells located on the former Pervel
property were included as part of the Phase IBNovember 1995 sampling event MW-A -B -C
-2 and -3 The existing on-site wells SW-3S and SW-3D were also included in the Phase
IBNovember 1995 sampling event and the subsequent Long-Term Monitoring Program sampling
events Since the November 1995 Long-Term Monitoring event included wells that were specific
to the Phase IB investigation the November 1995 sampling event is referred to as Phase
IBNovember 1995
During the period spanning the nine sampling events discussed in this report EPA has approved
modifications to the list of wells sampled under the Long-Term Monitoring Program
Modifications to the list of wells sampled have been to delete certain wells particularly those
located in the southern portion of the Site where no site related compounds have been or are
expected to be detected After the July 1995 sampling event wells at the following locations
were eliminated from the Long Term Monitoring Program MW111 MW112 MW114 SW-9
SW-10 and SW-12 Monitoring wells located at MW110 MW113 and MW115 were eliminated
following the Phase IBNovember 1995 sampling event The following subsections describe the
field methods which have been used consistently over the nine sampling events discussed in this
report Table 2-5 shows which wells were included in each sampling event
291 Monitoring Wells The groundwater sampling locations are shown on Plate 2-4 Low-flow purging and sampling
procedures were used to collect groundwater samples in an effort to obtain turbidity-free samples
and to minimize disturbance of the natural formation
The following sequential procedures were employed during the groundwater sampling effort
1) The static water level was measured using an electronic water level indicator
2) The absence of LNAPL was visually confirmed by observation of a sample
collected using a clear plastic bailer
3) All 2 inch diameter (or larger) monitoring wells were sampled using a stainless steel electric submersible pump (Grundfos Redi-Flo 2) equipped with teflon
5797wpdocsgalluprifinaltextmasterrifhl061297 2-27 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
discharge tubing To initiate the purging procedure the intake for the pump was
owered into the mid-section of the well screen For wells smaller than 2 inch
aiameter (ie existing SW- series wells) Teflon tubing equipped with a bottom
check valve was used to inertially purge the well
4) Water was purged from the well at a low flow rate (approximately 05 litersmin)
which was continuously monitored The water quality field parameters
(temperature pH conductivity and turbidity) were monitored during the purging
process until they had stabilized within 10 over three consecutive readings
5) Once the parameters had stabilized (or a minimum of five well volumes had been
purged) groundwater samples were collected for laboratory analysis Samples
were collected from the discharge end of the pump tubing by directly filling the
appropriate sample containers in the following order VOC SVOC (including
pesticides and PCB) metals inorganic compounds At wells that did not stabilize
below the 5 NTU turbidity requirement additional metals samples were collected
filtered through a 045 micron filter and submitted for dissolved metals analyses
(in addition to total metals)
6) Samples were collected from the upper and lower portion of each well using a
clear plastic bailer to visually assess the potential presence of NAPL
All sampling equipment was decontaminated between sampling events All purge water was
containerized for eventual off-site disposal
Duplicate samples matrix spikes matrix spike duplicates field blanks and trip blanks were
included as part of the QAQC procedures All groundwater monitoring sampling forms are
included as Appendix D Most groundwater samples were submitted for TALTCL VOC SVOC
pesticidesPCB and metals although a small number of samples collected during the Phase
lAJanuary 1995 and April 1995 event were submitted for VOC SVOC pesticidesPCB and
metals by Appendix IX methods Also certain samples were selectively submitted for VOC
analyses by Method 5242 The analytical methods for each sample submitted for laboratory
analysis are shown in Table 2-5
5797wpdocsgalluprifinlaquoltextmlaquosterrifhl061297 2-28 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
292 Residential Wells A total of fourteen private drinking water supply wells (DW101-DW114) were scheduled to be
sampled as part of the groundwater sampling program However two of the residences (DW101
and DW112) were unoccupied and inaccessible at the time of each of the sampling events The
residential wells are located along the eastern perimeter of the Site along Route 12 (Norwich
Road) adjacent to the southern portion of the Site along Tarbox Road and along Lillibridge
Road well south of the Site The residential well sampling locations are provided on Plate 2-5
In accordance with the Long-Term Monitoring Program the residential wells were sampled on a
semi-annual basis during the regularly scheduled summer and winter quarterly sampling events
In addition to the Phase lAJanuary 1995 sampling event residential groundwater samples were
collected during July 1995 February 1996 and August 1996 as shown in Table 2-5
Prior to the collection of groundwater samples from the residential wells a visual survey was
conducted to identify the sampling point closest to the well and to determine if any treatment
systems were in use A description and sketch of the supply system was recorded in field
notebooks Each system was opened and allowed to drain for approximately 15 minutes to purge
the plumbing system and obtain representative samples Field parameters were recorded during
purging to determine when stabilization had occurred The groundwater samples collected from
the residential wells were submitted for laboratory analysis of TCL SVOC pesticides PCB TAL
metalscyanide and VOC using EPA Method 5242
210 Surface Water and Sediment Sampling As part of the Phase 1A Investigation surface water and sediment sampling was conducted on
September 13-16 November 22 and December 29 1994 Although all locations were originally
sampled during the September sampling event three samples were lost in transit and had to be reshycollected A total of seventeen sample locations along Mill Brook and unnamed tributaries (UB1shy
UB10 and LB1-LB2) Fry Brook (FBI) Packers Pond (PP1-PP3) and a small pond along Tarbox
Road (TR1) were included in this program The re-sampled locations were UBS and UB6 (112294) and TR1 (122994) Due to dry conditions surface water samples could not be
obtained from the following locations UBS UBS UB6 UB7 and PP1
In accordance with the Long Term Monitoring program additional surface water samples were
collected during the April 1995 November 1995 May 1996 and November 1996 sampling
events to coincide with the approximate seasonal high- (ie spring) and low-water (ie autumn)
periods Following the initial Phase lAJanuary 1995 sampling event and per the request of
EPA the location of UB6 was moved due south to Mill Brook and renamed UB6A The surface
watersediment sample locations are shown on Plate 2-6 Sample locations by date are shown on
Table 2-5
5797wpdocsgalluprifiMltextmasterrifhl061297 2-29 Q5T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Surface water samples were collected using the actual laboratory sample containers by direct
immersion into the water Parameters which required the use of preservatives (eg metals
requires the addition of nitric acid to the sample) were collected in a stainless steel beaker and
transferred directly to the sample container to prevent loss of the preservatives during sampling
All sampling equipment was decontaminated after each use and placed into clean plastic bags
before moving on to the next station Surface water samples were collected starting at the most
downstream locations and progressed in order upstream The surface water samples were
submitted for laboratory analysis for TCLTAL compounds VOC and the following wet
chemistry parameters total organic carbon total dissolved solids total suspended solids hardness
and alkalinity The samples collected during April 1995 November 1995 and May 1996 were
also submitted for laboratory analysis of SVOC pesticides and PCBs The following field
measurements were also collected as part of the sample collection temperature conductivity
pH dissolved oxygen and turbidity
In addition to surface water during September 1994 sediment samples were collected at each of
the 17 locations (including the dry locations referenced above) Samples were collected at a depth
of 0 - 8 below the surface using manually operated soil or mud augers which were
decontaminated between sample locations The sediment samples were collected starting at the
most downstream locations and progressed in order upstream The sediment samples collected
contained greater than 30 percent solids based on visual and manual determination Samples were
submitted for laboratory analysis for TCLTAL compounds and for total organic carbon
Physical stream bed parameters (width depth and flow rate) were measured at surface water
sampling locations where discernable flow occurred This task was completed in April 1995
since the stream was at extremely low flow stages during the September 1994 sampling round
and a number of surface water sampling locations were nearly dry During the April 1995
surface water sampling event stream flow conditions were such that flow rates could be measured
at the following 5 locations UB4 UB6A UB9 UB10 FBI Locations at Packers Pond and the
small pond on the south side of Tarbox Road (TR-1) were not subject to these stream
measurements
Stream width and depth measurements were made using a fiberglass tape measure Depth and
stream flow measurements were recorded at the midpoint and quarter-points across the stream
Stream flow measurements were recorded using a Swoffer model 2100 in-situ flow meter The
flow meter was mounted on a graduated aluminum shaft which was equipped with an electronic
digital readout To calculate stream-flow the average cross-sectional area in square feet was
multiplied by the average water velocity (feetsec)
5797wpdocsgraquolluprifinaltextmasterrifhl061297 2-30 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
211 Wetland Soil Sampling In early September 1994 samples of wetland soils were collected from 10 locations within the
Study Area These sample locations (QW1-QW10) are shown on Plate 2-6 (and on Plate 3-14
which shows delineated wetlands as discussed in Section 341) Each sampling station was
marked with labeled stakes which were eventually included in the Site location survey The
samples were collected at locations situated near the edge of the wetlands at depths within one foot of the water table and below the organic mat The samples were collected using manually
operated soil or mud augers which were decontaminated between sample locations The samples were submitted for analysis of TCLTAL compounds and total organic carbon The results of the
wetland soil sampling program are discussed in Section 43
212 Evaluation of Existing Monitoring Wells As part of the Phase 1A investigation the remaining 11 monitoring wells installed during the
1978 Fuss and ONeill Inc investigation were evaluated to determine which wells could provide
usable water level data The present condition of each well was documented and a water level and total depth measurement were taken and compared to well construction logs If the wells
were determined to be potentially viable an attempt was made to test them for hydraulic
responsiveness by conducting rising and falling head slug tests Several of the wells were missing
protective casings had been broken off below the ground surface or had infilled with sediment
The results of the hydraulic evaluations are presented in Section 33 The locations of the
remaining existing monitoring wells are shown on Plate 2-4
A summary of the condition of each existing monitoring well is presented as Table 2-6 The
majority of the existing wells are presently in poor condition Most of these wells are lacking
surface seals andor adequate protective casings Several of the wells have no protective casings at all and are comprised only of PVC riser which is broken at or near the ground surface
Based on the present total depths of several of these wells compared to their total depths at the time of construction it is evident that the screen section of several of these wells have infilled
with sand or silt Based on their present condition and the fact that new monitoring wells have
been installed ESE recommended that any of the existing wells not included as part of the Long-
Term Monitoring Program be properly abandoned Following this recommendation EPA
approved the abandonment of the following wells SW13 SW14 SW17S D and SW18 Also
the protective casings at existing wells SW-3S SW-3D SW-9 SW-10 and SW-12 were repaired
since these wells are used to measure groundwater elevations as part of the Long-Term
Monitoring Program
5797wpdoc8galluprifinaltextmasterrifhl061297 2-31 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
213 Ecological Assessment 2131 Wetlanl Delineation
A wetland delineation was conducted on Site and focused primarily on the wetlands located north
and west of the Study Area This survey was limited to the Site side of Mill Brook up to the
present channel In order to meet both Federal and State requirements two methods were used to
delineate the Study Area wetland boundaries In accordance with federal requirements wetlands
were delineated using US Army Corps of Engineers (COE) methods Since the State of
Connecticut recognizes a slightly different methodology for wetland delineation the services of a
soil scientist certified by the Society of Soil Scientists of Southern New England were also
required The only difference between the two methods is that while the COE requires analysis
of vegetation composition hydrology and hydric soil indicators the State of Connecticut requires
only the analysis of hydric soil indicators
Jurisdictional wetland boundaries were determined by evaluating several points along the
hydrologic gradient Vegetation soil and hydrology criteria were measured or observed to
determine whether the point was within or above the Jurisdictional wetland boundary In order
for an area to be judged Jurisdictional wetland criteria must be met for all three parameters (ie
vegetation hydrology and soil)
21311 Vegetation
Wetland criteria for vegetation was based on the National List of Plant Species That Occur in
Wetlands (Reed 1988) Dominant plant species were identified at the observation point and listed
on data forms for routine on-site wetland determination The stratum where the plant occurred
(canopy shrub or herb) and indicator status for that plant were recorded A dominance of
wetland indicator species indicates that the vegetation criteria is met A dominance of upland
indicator species indicates that wetland criteria are not met
21312 Hydrology
Hydrologic criteria includes the visual observation of surface water inundation soil saturation or
indirect indication of previous saturation or inundation Indirect evidence includes watermarks
(stain lines on vegetation or structures) drift lines (debris deposited in a line at the high water
mark) sediment deposits and drainage patterns within wetlands
21313 Hydric Soils
The identification of hydric soil criteria includes soil types named as hydric by USDA Soil
Conservation Service or the presence of hydric indicators within the soil profile Indicators
include mottling or streaking of organic materials high organic content the presence of sulfitic
material soil colors (gleyed colors) and others
5797wpdoc8galluprifinaltextmasteirifhl061297 2-32 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
2132 Plant and Wildlife Survey
The objective of the Phase 1A ecological assessment was to qualitatively identify any real or
potential impacts to local ecological receptors within the Study Area or otherwise influenced by
the conditions originating at the Site All observations on plants and animals were noted in field
logs during the wetland delineation
The results of this survey will assist the EPA in the performance of a more formal ecological risk
assessment During the ecological risk assessment sediment soil water and air quality data and
observations of plant and animal communities will be used (see also Section 123) to identify any areas where impacts have occurred The results of the qualitative plant and animal survey
conducted during the wetland investigation are discussed in Section 34 of the text
214 Test Pit Explorations In lieu of ground penetrating radar surveys (as discussed in Section 233) and with EPA
approval additional EM and MAG surveys were performed over a five-foot by five-foot grid in
the vicinity of unexplainable anomalies which were detected during the initial EM and MAG
surveys Once accurate locations for the anomalies were determined and marked on the ground
surface test pit explorations were conducted to confirm the source of the anomalies
On December 21 1994 test pits were excavated at a total of four locations at which
unexplainable anomalies were detected The test pits were performed under the observation of
EPA oversight contractor personnel The locations of the four anomalies and associated test pits are shown on Plate 2-7 At each anomaly a trench (or series of trenches) was systematically
excavated in one to two foot lifts using a backhoe The trenches were oriented to intersect the
longest axis of each anomaly to maximize the possibility of unearthing the source of the anomaly Once a lift was complete soil obtained from the trench walls as well as that obtained from the
backhoe bucket was screened with a PID for evidence of VOC The excavated soil and the trench
itself were also visually monitored for objects capable of producing the anomalies detected during the geophysical surveys and for other features possibly associated with disposal activities (eg
stained soil)
Once the source of each anomaly was discovered the object was excavated and the test pit was
backfilled and regraded with clean soil obtained from the excavation Since no elevated PID
readings or other signs of disposal features were encountered during the test pit operations no
soil samples were submitted for laboratory analysis Test pit logs for these excavations are
presented in Appendix E
5797wpdocsgalluprifinaltextmasterrifhl061297 2-33 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
30 Physical Characteristics of the Study Area
31 General Characteristics 311 Regional Physiography
The Site is located along the eastern border of the Quinebaug Valley Lowland This regional
feature is dominated by the southerly flowing Quinebaug River and is comprised of a north-south
trending lowland area which is approximately 2 to 3 miles in width and approximately 25 miles
long The Quinebaug River originates at headwaters located in central Massachusetts and
terminates at Norwich Connecticut where it merges with the Shetucket River approximately 12 miles south of the Site The confluence of these two rivers form the Thames River which flows
to the south approximately 15 miles and ultimately discharges into Long Island Sound
The region is characterized by relatively low relief and numerous glacial features The regional
landscape is significantly influenced by the structure of the underlying crystalline metamorphic
bedrock which is discontinuously overlain by Pleistocene glacial sediments of variable thickness
Lowland surficial features are characteristic of late Pleistocene glacial retreat processes and
include numerous kettleholes and swamps many of which are interconnected by a network of
slow draining streams
Land surface elevations in the vicinity of the Site range from approximately 150 to just over 220
feet above sea level Lowlands are bounded to the east and west by upland terrain which consists of irregular hilly areas of moderate relief The uplands contain many areas with large bedrock
ledges generally thin glacial deposits (predominantly till) poorly drained valleys and small
isolated swamps Elevations in the uplands range from 200 to 600 feet above sea level
312 Study Area Physiography
The topography on the Site is highly irregular primarily due to past quarrying operations
Numerous overgrown mounds of earthen materials (eg crushed stone sand and gravel) and
excavated depressions are scattered throughout the Site Visual reconnaissance and a number of
screening surveys (eg soil gas and surface geophysical investigations) have confirmed that many
of the features previously identified from the review of historic aerial photographs as potential
disposal areas (Bionetics 1990) were in fact features remnant of quarrying and former CTDOT
operations
The ground surface on the Site (shown on Plate 3-1) generally slopes from east to west and to a
large degree is controlled by the underlying bedrock surface The highest point within the Study
Area consists of a bedrock high overlain by a thin veneer of till and is located in the eastern
5797wpdoclaquogalluprifinraquoltextma8terri fhl061297 3-1 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
central portion of the Site Elevations in this vicinity peak at approximately 230 feet above sea
level
The northern portion of the Site which includes the Former Primary and Secondary Disposal
Areas consists predominantly of open sparsely or non-vegetated areas of sand and gravel This cover material is presumed to have been distributed over the ground surface following CTDEP
Site remediation efforts in 1979 Presently the Former Primary and Secondary Disposal Areas are visible as roughly circular depressions which are approximately 150 feet and 60 feet in
diameter respectively The depressions are approximately 8 to 12 feet deep relative to the
surrounding ground surface These depressions intermittently contain as much as several inches
of standing water which accumulates during periods of heavy precipitation The bottoms of the
depressions are lightly vegetated with various grasses and weeds
North and west of the Site the ground surface elevation decreases as the Mill Brook floodplain is
encountered The floodplain area consists of low lying heavily vegetated wetland areas which
are periodically inundated
Excluding the isolated topographic high spot at the eastern margin of the Site the southern
portion of the Site (from the vicinity of the Former Seepage Bed to Tarbox Road) can be
described as generally flat but includes numerous man-made small-scale features such as
mounds or depressions
313 Surface Water Features
The Site is centrally located within the Mill Brook drainage basin which encompasses
approximately 18 square miles The Mill Brook drainage basin is part of the larger Quinebaug
River regional drainage basin Mill Brook a tributary to the Quinebaug River is located 250 feet
north of the Site and flows from east to west Approximately 1000 feet northwest of the Site (in
the vicinity of the Plainfield municipal sewage treatment plant) Mill Brook is joined by Fry
Brook which flows from the north Packers Pond which is located approximately 3000 feet
west of the Site was formed by the construction of a dam across Mill Brook
There are no surface water bodies located on the Site itself although several low areas (which
were excavated during previous site activities) have been observed to contain ponded water during
periods of extended precipitation
Surface water flow rates (determined during the April 1995 sampling event) were determined for
the following five locations in Mill Brook UB4 UB6A UB9 UB10 and at FBI in Fry Brook
Along Mill Brook flow rates ranged from approximately 23 cubic feet per second (cfs) at the
5797wpdocsgalluprifinaltextmasterrifnl061297 3-2 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
most upstream location (UB4) to approximately 31 cfs at the most downstream location (UB10)
Along the northern Study Area a 3 cfs increase was observed from Stations UB6 to UB10
representing a flow rate increase of about 025 cfs per 100 feet of stream length The flow rate in Fry Brook (Station FBI) was approximately 16 cfs
314 Climate The Site is located within Connecticuts Central climate division According to published
National Weather Service data (USGS 1993) the average annual temperature is approximately
50degF the coldest month is January with an average temperature of 258T and the warmest month is July with an average temperature of 714degF Annual precipitation at nearby recording
stations (located in Norwich CT and North Foster RI) averages approximately 53 inches per
year and ranges between approximately 41 and 68 inches per year (based on historic data from
1978 to 1991) The monthly distribution of precipitation is relatively even throughout the year
32 Geology 321 Regional Surficial Geology
The surficial or overburden deposits in the area consist of unconsolidated materials deposited as a
result of glaciation during the Pleistocene epoch Various glacially-derived materials including till meltwater or stratified drift deposits and post-glacial deposits of floodplain alluvium
comprise the major surficial geologic units in the vicinity of the Site Areas covered by eolian dune deposits are also noted on surficial geologic maps of the area although no dune deposits are
found within the Study Area
Till deposits in the region consist of non-sorted and generally non-stratified mixtures of sediments
with grain sizes ranging from clay to boulders Till is formed by the direct deposition of ice debris on the land surface Generally the color and lithology of till is dependant upon the
composition of local surficial deposits underlying bedrock and northerly adjacent bedrock from
which the till was derived Tills deposited during two periods of glaciation are present in the
region and blanket the bedrock surface in various thicknesses The most extensive and prevalent
till which is commonly present in surface exposures was likely deposited during late
Wisconsinan glaciation (USGS 1995) This till is referred to as upper till and is described as
predominantly loose to moderately compact generally sandy and frequently stony
A less commonly exposed lower (older) till was deposited during earlier glaciation possibly during the Illinoisan or early Wisconsinan glaciation periods The lower till is generally compact
to very compact and is typically finer-grained and less stony than the younger upper till A
weathered zone is usually present between the two till units
5797wpdoc8gnlluprifinaltextmasterrifnl061297 3-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Directly overlying the till (or bedrock where till is absent) are glacial meltwater deposits
collectively referred to as stratified drift These deposits consist of poorly to well sorted
assemblages of gravel sand silt and clay which were deposited by glacial meltwater during the retreat of the last ice sheet Variations in the composition structure and texture of the stratified
drift deposits are dependent upon the depositional environment in which they formed Deposits exhibiting a relatively high degree of sorting andor stratification can usually be classified as
either glaciofluvial (stream) deposits glaciodeltaic (where streams entered glacial lakes) deposits or glaciolacustrine (lake bottom) deposits The horizontal and vertical contacts between these
deposits are generally transitional and were dependent upon the available sediment load and
proximity to the various depositional environments (eg streams or lakes) associated with the
retreating ice front For example coarse-grained deposits of sands and gravel were usually
deposited proximal to the ice margin while further away primarily in glacial lakes deposits of
fine sand silts and clay were prevalent Poorly sorted deposits of relatively coarse material were
typically deposited at the ice front or along bedrock valley walls During the glacial retreat
these deposits would be left behind or collapsed on any underlying deposits Contemporaneously bedrock valleys were frequently dammed by glacial deposits andor masses
of glacial ice behind which glacial meltwater could accumulate forming glacial lakes Gradual
retreat of the ice margin as well as the formation (and eventual draining) of glacial lakes over
time would result in changes in the depositional environment which are seen as textural changes in the stratified drift deposits
Postglacial deposits of sand gravel silt and organic materials are also present as floodplain
alluvium along streams and rivers in the region The texture of alluvium varies over short
distances both laterally and vertically and is generally less than 5 feet thick along small streams
Since alluvial material typically represents re-worked glacial deposits the alluvium is often similar to the surrounding parent glacial material
322 Local Surficial Geology
The Study Area is located on the eastern flank of a pre-glacial bedrock valley and is bounded to
the east by bedrock-controlled upland areas and to the west by an area known as the Quinebaug
Valley lowlands Following the last period of glaciation (in which the relatively thin veneer of till
was deposited) various temporary depositional environments existed as a result of the presence of
an ice and sediment dam approximately 10 miles south of the Study Area which caused the
formation of a glacial lake Evidence of the lake (referred to as Glacial Lake Quinebaug) is well
documented in the literature (Stone amp Randall 1977) As the ice sheet retreated northward deposits left behind were dominated by sand and gravels associated with the formation of a series
of progressive and coalescing deltaic complexes which developed within the rising lake In lower
lying areas where deltas did not form finer-grained sand silt and clay was deposited Although
5797wpdocsgalluprifinaltextma8terrifhl061297 3-4 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
much of this sediment may originally have been deposited with some degree of structure or
sorting much of the structure was lost (collapsed) when the ice mass eventually melted away
The depositional environment was further complicated by the presence of residual ice blocks left
behind during the retreat of the main body of the glacier As the various depositional features
formed around these ice-blocks their eventual melting left behind depressions or kettles into
which fine sediment could settle While many kettles were eventually filled many remain as
detached or poorly drained ponds
As a result of the depositional history of the Study Area the primary surficial or overburden
deposits encountered are till and stratified drift Depending upon location the stratified drift may
be generally broken down into fine (eg silt and fine sand) or coarse (eg sand and gravel)
grained components but at many locations the change is transitional and subtle in both vertical
and horizontal directions The thickness of the stratified drift deposits ranges from non-existent
up to approximately 70 feet At some locations distinct structure is exhibited while at other
locations the structure has collapsed Post-glacial alluvial floodplain deposits were encountered
at locations within the present Mill Brook floodplain however the overall significance of these
deposits is minor
To illustrate the local geological features a series of geologic cross-sections have been prepared
At several locations lithologic data from pre-RI wells (both on-site and off-site) were
incorporated for additional detail The boring logs from which the cross sections were prepared
are included in Appendix C
As shown in cross-sections A-A B-B C-C D-D E-E and F-F (Plates 3-2 through 3-5) till
was encountered just above the bedrock surface at nearly every location The till horizon ranges
in thickness from approximately 10 to 20 feet with the thickest accumulations located along the
centrally located topographic high Surficial exposures of glacial till were observed within the
central portion of the Site as seen in cross sections A-A and C-C The till observed within the
Study Area is comprised of a fine sandy matrix containing abundant gravel cobbles and
boulders The till deposits seen in the topographically higher areas (ie elevations greater than
approximately 160 feet) were for the most part unsaturated Although reference literature for
this area (USGS 1995) describe the possible presence of two different till horizons no apparent
differentiation was observed at the site
As seen in the boring log from MW111 deposits of till are exposed at the ground surface and in
the central area of the Site However as shown on cross sections A-A and C-C (Plate 3-2) and
D-D (Plate 3-3) the bedrock surface drops off rapidly in southerly westerly and northerly
directions where relatively thick accumulations of stratified drift have been deposited over the till
5797wpdocsgalluprifinlaquoltextmalaquotemfhl061297 3-5 QFT Environmental
Gallups Quarry Superftind Project - Remedial Investigation
Within 500 feet of the central portion of the Site the overall thickness of the stratified drift
deposits increase to nearly 70 feet In the vicinity of MW113 (west of the central portion of the
Site) the lower portion of the stratified drift is comprised of approximately 30 feet of very fine to
medium-grained sand with occasional thin layers of silt This deposit appears to increase in
thickness towards the west while it thins towards the central portion of the Site where it pinches
out against the till Overlying these fine-grained deposits are approximately 30 feet of poorly
structured sand and gravel which includes abundant cobble sized material The coarser upper
stratified drift material also thins eastward towards the Site where it is in contact with the till
The coarse upper material is generally unsaturated with the groundwater table occurring at the
approximate upper surface of the fine sand
The southern portion of the Study Area is shown on cross sections A-A (Plate 3-2) and D-D
(Plate 3-3) As indicated on the southern end of cross section A-A approximately 35 feet of
stratified drift overlies the till in the vicinity of MW112 Although much of the stratified drift at
MW112 is relatively coarse an approximately 12 foot thick layer of fine-grained sand and silt is
present from about eight to twenty feet below the ground surface From MW112 the thickness of
the stratified drift thins to the north where it contacts the central topographic high
From the southeastern corner of the Site near MW112 the bedrock surface slopes downward
towards the west-southwest to a depth of approximately 75 feet below the ground surface (as seen
at location MW115 on the southern end of cross section D-D[Plate 3-3]) At MW115
approximately 65 feet of stratified drift (comprised of a sandy matrix containing a significant
amount of coarser gravel and cobbles) overlies approximately 10 feet of till
As seen in cross section B-B (shown on Plate 3-4) and A-A (Plate 3-2) the northeastern portion
of the Site (in the vicinity of the Former Primary Disposal Area) is comprised of fairly well
sorted fine- to medium-grained sand with occasional thin lenses of very fine sand and silt The
lenses of finer-grained materials appear only locally in the vicinity of MW107 and MW108 at a
depth of about 25 feet and are typically only a few inches to a few feet in thickness with limited
lateral extent Beneath the fine-grained sand and silt and directly overlying the till is 10 to 20
feet of coarser-grained sand and gravel Moving westward along cross section B-B in the
vicinity of MW105 the fine-grained sand thins and grades into coarser sand and gravel deposits
The coarse sand and gravel deposits directly overlie the till and thicken to nearly 50 feet towards
the west in response to the downward slope of the bedrock surface This portion of the Study
Area which is northwest (and downgradient) of the Former Primary and Secondary Disposal
Areas is overlain by a thin veneer of recent alluvial and swamp deposits associated with the
present Mill Brook channel and floodplain As shown on the cross section (B-B) the stratified
drift deposits in this area are very nearly saturated throughout their entire thickness
5797wpdoc8galluprifinaltextmasterrifiiiy061297 3-6 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
North of the Former Primary Disposal Area (along the northern end of cross section D-D) the
bedrock surface continues to gradually slope downward (to the north) until the approximate
location of MW116 North of MW116 the bedrock surface is interpreted as appearing to rise
based on the depth to till deposits encountered beneath MW119 Stratified drift deposits
immediately north of the Former Primary Disposal Area in the vicinity of MW116 are dominated
by approximately 25 feet of fine grained sand and silt Further north along section D-D the
finer sand and silt deposits thin and are overlain by coarser grained sand and gravels Relatively
thin post-glacial stream alluvium and modern swamp deposits associated with Mill Brook are also
seen in the vicinity of MW116 and MW119 A roughly east-west cross section (E-E [Plate 3-5])
has been prepared to illustrate the lithologic features in the area north-northwest of the former
disposal areas This cross section starts at MW119 (described above) and runs west to MW101
in a line approximately parallel to Mill Brook The fine sandsilt deposit seen in the vicinity of
MW119 is also observed to the west at MW117 at the same approximate thickness and elevation
Westward from MW117 the fine sandsilt deposit grades into the more prevalent coarse sand and
gravel deposits observed at MW118 and MW101 The northernmost cross section (F-F [Plate 3shy
5]) extends westward from MW3 (located just east of the former Pervel flock plant) to PZ301
As shown on F-F this portion of the Study Area is dominated by collapsed coarse sand and
gravel deposits at least to the completion depths of the borings (MW3 MWC and PZ301) along
the line
323 Regional Bedrock Geology
Bedrock in the vicinity of the Site is mapped as a lower member of the Quinebaug Formation
which is composed of metasedimentary and metavolcanic rocks of Paleozoic age The Quinebaug
Formation is part of the Putnam Group and exhibits a sillimanite grade of metamorphism The
bedrock consists of primarily light to dark grey fine- to medium-grained hornblende gneiss biotite gneiss and amphibolite Bedrock in the area is strongly faulted and folded and exhibits
varying degrees of mylonitization A major fault zone known as the Lake Char fault is located
approximately 03 miles east of the Site The Lake Char fault is a north-south trending fault
which offsets rock units of the Putnam Group and the Hope Valley Alaskite Gneiss formation A
northwest-trending fault is shown on the USGS Bedrock Geologic Map (Dixon 1965) of the
Plainfield Quadrangle in the vicinity of the Former Seepage Bed The existence and approximate
location of the suspected fault was based on aeromagnetic data published in 1965 (Boynton amp
Smith 1965) Bedrock located north of the inferred fault is mapped as more intensely
metamorphosed cataclasites and blastomylonites The fault is mapped as extending into the Tatnic
Hill formation to the west but is not mapped within the Hope Valley Alaskite Gneiss formation
which is located to the east
5797wpdoc8galluprifinaltextmasterrifhl061297 3-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
324 Local Bedrock Geology
Confirmed depns to bedrock were determined based on the elevations of bedrock outcrops and
the collection of bedrock cores at nine boring locations (MW102B MW105B MW107B
MW108B MW109B MW111B MW112B MW113B and MW115B) Inferred depths to
bedrock were made at seven additional locations (MW101 MW102 MW103 MW104 MW114
MW116 MW117 MW118 and MW119) based on boring data obtained during the drilling of the
deepest wells at each cluster (which indicates the minimum depth to bedrock) and based on trends
seen at the confirmed depth locations Based on this evidence it is likely that unconfirmed depths
to bedrock are accurate to within several feet of the actual depths At MW110S no attempt was
made to advance the boring more than about 12 feet below the ground surface (the depth needed
for the required shallow well at that location) Depths to bedrock ranged from approximately 13
feet at MW111B to 83 feet at MW113B Drilling difficulties associated with the presence of
boulders just below the ground surface at MW11 IB made it difficult to determine the exact depth that bedrock was first encountered at this location Suspected boulders were encountered starting
at approximately six feet below the ground surface and casing was driven to a refusal depth of
approximately 15 feet before bedrock coring began
Based on the data described above a bedrock surface contour map is shown on Plate 3-6
Bedrock elevations are highest in the eastern central portion of the Study Area and decrease to the
north and west and to a lesser degree to the south
Within the Study Area bedrock consists of grey fine- to medium-grained gneiss with varying
contents of amphibolite biotite and hornblende Various degrees of weathering and competency
were also observed Detailed rock core descriptions are presented on the rock coring logs
provided in Appendix C
The primary objective of the seismic refraction survey (discussed in Section 234) was to
identify if present the location of a possible bedrock fault suspected to exist hi the vicinity of the
Former Seepage Bed As discussed in Section 323 the approximate location of the suspected
fault was estimated from the regional USGS Bedrock Geologic Map based on an aeromagnetic
survey conducted in 1965 Ground penetrating radar surveys conducted by the USGS (1995)
identified a northward dipping subsurface reflector beneath the central portion of the Site This
reflector was interpreted as a potential bedrock fault feature The relatively high strength of the
reflector was attributed to fault gouge (or other infilling) material or possibly sorbed inorganic
compounds No subsurface explorations were conducted at the time of the USGS investigation to
confirm the nature of the radar reflector
5797wpdocsgalluprifinaltextmiiraquoterrifnl061297 3-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Evaluation of data obtained from the seismic refraction survey indicates the presence of possible
bedrock fractures on seismic lines 3 through 6 (Plate 3-7) In addition to these interpreted
fracture zones the overall relatively low seismic velocities (12000 ftsec vs 15000 to 18000
ftsec for intact crystalline rock) indicate that in general the rock is somewhat fractured
Although the original intent of the magnetometer (MAG) survey was not to interpret bedrock
features data obtained during the MAG survey (which covered a much larger area) indicate the
presence of several linear-shaped sharp magnetic gradients bounding a zone with a different
magnetic signature The change in magnetic signature was interpreted as potentially associated
with changes in bedrock lithology and fracturing across a broad faultfracture zone in the central
portion of the Site These interpretations are described in further detail in the Weston
Geophysical Report included as Appendix A The locations of the magnetically determined
bedrock features are also shown on Plate 3-7 While the seismically interpreted fractures do not
strongly coincide with linear features seen in the MAG data they do lie within the magnetically
determined fractured zone
The geophysical data described above as well as the rock-core retrieved from MW111B further suggest that bedrock beneath the central portion of the Site may be more accurately characterized
as a series of fractures and faults rather than an area of competent bedrock with one or two
discrete faults
33 Hydrogeology The following sections discuss data collection and evaluation results relative to groundwater flow
directions and rates in overburden deposits and the upper portion of the bedrock unit
331 Hydraulic Conductivity The hydraulic conductivity distributions within the overburden and bedrock formations were
evaluated through the performance of rising and falling head slug tests constant flow tests and
by empirical correlations with measured soil grain size distributions The slug test methodology
and data analysis methods are discussed in Appendix F Because the falling head test results for
shallow wells were influenced to some degree by soil above the water table only rising head test
data were used for the water table wells to compute mean values The constant flow test
methodology is described in Section 283 and Appendix F Table 3-1 summarizes the measured
hydraulic conductivity values from the slug and constant flow tests for wells grouped together
based on lithology and screen depth as follows shallow top-of-till till and bedrock Hydraulic
conductivity estimates based on grain size are listed in Table 3-2 for comparison but only
constant flow and slug-test data were used to calculate mean hydraulic conductivity values for
different portions of the aquifer Laboratory grain size data are presented in Appendix G
5797wpdocraquogalluprifinlaquoltextmastem fill061297 3-9 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
The top-of-till wells are considered to be the most representative of the more permeable section of X^^JF
the overburden aquifer characterized by coarser soil grain sizes where a large percentage of the
total groundwater flow occurs Across the Study Area the mean hydraulic conductivity for the
top-of-till wells is 0005 centimeters per second (cms) with values ranging from 0000053 cms
to 0074 cms Northwest of the railroad tracks in the northern portion of the Study Area where
the aquifer thickens the mean hydraulic conductivity for top-of-till wells (MW102TT
MW103TT MW104TT MW117TT and MW118TT) is 0037 cms This value of 0037 cms
which is approximately an order of magnitude larger than the overall Study Area mean for top-ofshy
till wells appears to be most representative of the hydraulic conductivity within the major portion
of the VOC plume By comparison the grain size results are similar in magnitude but somewhat
lower than the Study Area average for the constant-flow and slug tests because they indicate an
average hydraulic conductivity of 0003 cms for the coarse stratified drift samples with values
ranging from 00006 cms to 0006 cms The mean hydraulic conductivity for shallow wells
which are generally screened in finer-grained soils is 0001 cms and varies between 000006
cms and 002 cms The shallow well constant-flow and slug test results are comparable to the
mean grain-size correlation value of 0002 cms for fine stratified drift soil samples
The mean hydraulic conductivity for the till wells (000047 cms) is approximately a factor of ten
less than the mean Study Area top-of-till value and varies between 00002 cms and 0002 cms
The till appears to be hydrogeologically different from the other overburden deposits and on the
average provides increased resistance to groundwater flow This added resistance is not
considered to be significant however because the consistency of the till is highly variable and the
hydraulic conductivity contrast is relatively small
The slug test results for the bedrock wells yield the lowest average hydraulic conductivity
000018 cms The bedrock results though should be considered less accurate than the
overburden estimates due to the highly variable nature of the fractures in the rock matrix and their
associated non-linear effect on computed hydraulic conductivity
332 Groundwater Flow
3321 Surficial (Overburden) Groundwater Flow
The following discussion on overburden groundwater flow is organized according to relative
locations within the Study Area All references to flow direction are inferred based on measured
hydraulic gradients The central portion of the Site in the vicinity of the Former Seepage Bed is
dominated by the presence of a bedrock-controlled topographic high which for the most part is
overlain by unsaturated till Because of this feature overburden groundwater flow patterns can be
effectively treated as separate entities those located to the north of the hill and those located to
the south
5797wpdocraquoglaquolluprifinlaquoltextmasterrifhl061297 3-10 QampT Environmental
Gallups Quarry Superand Project - Remedial Investigation
Table 3-3 summarizes the water level data collected from monitoring wells and piezometers
during the quarterly monitoring rounds Plates 3-8 and 3-9 depict deep and shallow piezometric head distributions respectively (for November 6 1995) throughout the northern Study Area
Plate 3-9 also shows the piezometric head distribution in the southern Study Area Groundwater
flow maps for other dates are presented in the ISCR (ESE 1995) Water level data for the
monitoring wells at the former Pervel facility were used in both the shallow and deep flow maps
because they are screened in the middle portion of the aquifer As a result these wells are
considered to be hydraulically representative of both portions of the aquifer A saturated
thickness map (Plate 3-10) was created by subtracting the interpolated bedrock surface (Plate 3-6)
from the shallow overburden piezometric surface measured on November 6 1995 which is approximately equal to the groundwater table configuration To facilitate interpretation of flow
patterns calculated two-dimensional groundwater pathlines which represent the mean horizontal trajectory of a parcel of groundwater in the overburden aquifer originating from several locations
in the Study Area are also shown however the pathlines do not account for vertical flow within the aquifer which is important in the shallow portion of the aquifer Data interpolation by the
method of kriging piezometric head contour development and numerical computation of pathlines were performed using the data analysis and visualization software package Tecplot
(Amtec Engineering 1994) The pathlines are based on a steady state velocity field computed
directly from the interpolated head distribution using Darcys law and assume homogeneous
isotropic conditions
Southern Study Area
Overburden groundwater flow south of the Former Seepage Bed is primarily influenced by two factors (1) the slope of the bedrock surface which defines the base of the unconsolidated deposits and (2) regional hydrologic drainage patterns The west-southwest dip of the bedrock
surface strongly influences the general east to west flow of groundwater The average east-west
horizontal hydraulic gradient in the southern portion of the Study Area is approximately 001 feet per foot (feet of vertical head change per foot of horizontal distance)near well MW112S and
piezometer PZ-202 whereas the typical bedrock surface slope in this area is about 01 feet per
foot The configuration of the bedrock surface is important because the slope of the groundwater
table in the overburden would tend to equal the slope of the underlying bedrock in cases where
the saturated thickness is relatively small and the slope is large This process is analogous to flow
in a river where the water surface profile tends to reflect the slope of the river bed under steady-
state conditions In the southern Study Area the water table slope (ie horizontal hydraulic
gradient) is steep but less than the dip of the bedrock surface because the saturated thickness of
the overburden aquifer increases in the direction of flow The saturated thickness increase also
5797wpdocsglaquolluprifinlaquoltextmlaquogterrifiil061297 3-11 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
increases the transmissivity of the aquifer (and decreases the resistance to flow) thus causing the
horizontal hydtaulic gradient in the overburden to be less than the bedrock slope The
overburden becomes unsaturated north of PZ203 due to the continued increase of the bedrock
surface elevation in the direction of the Former Seepage Bed The wetlands and stream located a
few hundred feet west of the railroad tracks also affect flow directions and rates because they act
as discharge points for groundwater
Northern Study Area
Due to the increased saturated thickness north-northwest of the Former Primary Disposal Area
groundwater flow conditions in both shallow and deep sections of the aquifer are discussed The
top-of-till wells are considered to be most representative of horizontal flow conditions in all but
the shallow portion of the aquifer Primary reasons for the differences between shallow and deep
flow conditions include (1) the deep aquifer hydraulic conductivity northwest of the railroad
tracks is a factor of about 40 greater than the shallow hydraulic conductivity resulting in the
lower to middle portions of the aquifer controlling regional groundwater movement and (2)
rainwater infiltration and hydraulic influences of Mill Brook cause vertical flow to be important in
certain areas of the shallow aquifer The focus of this section is horizontal groundwater flow in
the middle to lower sections of the aquifer as characterized by Plate 3-8 Shallow flow
conditions (Plate 3-9) are discussed in Section 3323
In the northern portion of the Study Area three hydrogeologically distinct zones exist Between
the Former Primary Disposal Area and the Former Seepage Bed the hydraulic gradient is steep
(approximately 003 feet per foot between wells MW109S and MW110S) and is strongly
influenced by the dip of the bedrock surface (01 feet per foot) As shown on the insert on Plate
3-10 the saturated overburden thickness increases from zero south of well MW109 to about 20 to
30 feet near the former disposal areas North-northwest of the Former Primary Disposal Area the
hydraulic gradient lessens significantly to a range of 00003 to 00007 feet per foot between wells
MW105TT and MW102TT representing a factor of 40 to 100 reduction The most important
factors which produce the flatter gradients in this area are the more than order-of-magnitude
increase in hydraulic conductivity of the coarser-grained deposits and the substantial increase in
the saturated overburden thickness northwest of the railroad tracks North-northeast of Mill
Brook the hydraulic gradient is about 0007 feet per foot near wells MW117TT and MW118TT
Northwest of the railroad tracks groundwater flow in the middle to lower portions of the aquifer
converges from the northeast and southwest toward a centerline area generally defined in the
downgradient direction by wells MW105 and MW102 The flow direction near these wells is
generally to the northwest Northeast of this centerline groundwater flows in a southwesterly
5797wpdocsgalluprifinaltextmasterrifhl061297 3-12 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
^ ^ direction from the vicinity of Mill Brook and the former Pervel flock plant North of Mill Brook
and west of the railroad tracks the predominant groundwater flow direction becomes more
westerly As discussed in Section 42 and 52 these flow directions are very consistent with the
observed groundwater contaminant distribution
No significant seasonal changes in horizontal groundwater flow directions were observed in the
Study Area Figures 3-1 to 3-20 are groundwater elevation hydrographs for each well cluster in
the Study Area representing the period January 1995 to May 1997 (except for wells MW117
MW118 and MW119 which were not installed until November 1995) Groundwater levels were
high in January 1995 May 1996 and February 1997 and decreased by about two feet during July
1995 and August 1996 This variation is consistent with the fact that recharge rates become very
small during the summer months
3322 Bedrock Groundwater Flow
Groundwater flow within fractures in the top ten to 20 feet of the bedrock unit was evaluated
through the performance of the hydraulic conductivity (slug) tests and water level measurements
in monitoring wells A bedrock piezometric head map based on November 6 1995 water levels
is shown on Plate 3-11 along with inferred groundwater pathlines For the pathline development
it was assumed that the hydraulic conductivity distribution is isotropic because potential
influences of fracture orientation on flow direction have not been quantified As expected the
direction of the dip of the bedrock surface has a major influence on the horizontal hydraulic
gradient and flow direction However vertical flow from bedrock to overburden is also
important as discussed in Section 3323
South of the Former Seepage Bed groundwater in bedrock moves primarily in a westerly
direction while in the northern Study Area the predominant flow component is toward the
northwest In both areas the horizontal hydraulic gradient is on the order of 002 feet per foot
The steepest gradients (003 feet per foot) are found in the vicinity of the Former Seepage Bed
and the local high in the bedrock surface just east of MW111 The horizontal hydraulic gradient
reduces to about 001 feet per foot in the southern portion of the Study Area (near wells MW115
MW114 and MW112) and north-northwest of the former disposal areas Groundwater flow in
bedrock near the Former Seepage Bed is toward the northwest in the direction of wells MW113
and MW106 and exhibits no apparent influence from the locally increased fracturing identified
from the geophysical investigation and the hydraulic testing in well MW111B
5797wpdocsgalluprifinaltextm8tem fhl061297 3-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
3323 Vertical Flow
BedrockDeep Overburden Interface
Vertical groundwater flow is an important component in the upper several feet of the bedrock
unit This observation is supported by the water level hydrographs (Figure 3-1 to 3-20) and data
presented in Table 3-4 which summarizes the vertical hydraulic gradients between pairs of
monitoring wells in various well clusters across the Study Area Data characterizing the hydraulic
interaction between the bedrock and the lower portion of the overburden were evaluated for the
following well pairs MW102B-MW102TT MW105B - MW105T MW107B - MW107T
MW108B - MW108TT MW109B - MW109S MW112B - MW112T MW113B - MW113S and
MW1 15B - MW1 15TT For all measurement dates groundwater was found to be discharging
from bedrock into overburden at each location except for the January 1995 and February and May
1996 measurements at location MW109 At MW109 the saturated overburden thickness is less
than a few feet and MW109 is located at a much higher bedrock elevation relative to all other
locations at which upward vertical flow from bedrock was measured The vertical hydraulic
gradients between bedrock and top-of-till wells are generally more than a factor of ten greater
than the horizontal hydraulic gradients within the VOC plume downgradient from the Former
Primary Disposal Area
Overburden
In the overburden aquifer the vertical flow component is significant within shallow deposits in ~
the vicinity of the Former Primary Disposal Area and within the streambed sediments and the
upper portion of the aquifer near Mill Brook Plan view and cross-section maps were developed
to illustrate vertical piezometric head differences Plate 3-12 shows the November 6 1995
vertical piezometric head distribution and general groundwater flow directions along geologic
cross-section B-B Plate 3-13 is a plan view contour map of the shallow minus deep piezometric
head difference in the overburden aquifer As shown by the water level hydrographs the vertical
hydraulic gradients in the aquifer are relatively consistent throughout the observation period
Consistent downward hydraulic gradients have been observed at well clusters MW107 MW108
and MW116 Near the Former Primary Disposal Area water levels in MW107S were two to
three feet higher than the level in MW107TT resulting in a downward vertical hydraulic gradient
that is about a factor of 100 greater than the horizontal gradient from MW107TT to MW105TT
In addition shallow piezometric heads near MW108 and MW1 16 have ranged from 05 to 15
feet higher than heads in the lower portion of the aquifer This downward component at MW107
likely results from the low hydraulic conductivity of shallow soils near the well screen of
MW107S (factor of 200 less than underlying deposits refer to MW107S and MW107TT data in
Table 3-1) and drainage of surface water runoff from upslope areas into the depression formed by
excavation of the Former Primary Disposal Area The low hydraulic conductivity test result for
5797wpdocsgalluprifinlaquoltextmasteiTifhl06 1297 3-14 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW107S and the observed downward hydraulic gradient may be related to the increased silt
content of soils near well MW107S The vertical VOC distribution at location MW107 (shown
on Plate 3-12 and discussed in Section 4) also strongly supports a predominantly vertical
groundwater flow direction in the upper portion of the aquifer because only trace levels of VOC
were detected in MW107S The downward hydraulic gradients in the vicinity of wells MW108
and MW116 (Plate 3-13) also appear to be associated with the higher hydraulic conductivity of
deep deposits compared to shallow soils (Section 331) and groundwater recharge
West of the railroad tracks near well clusters MW102 MW101 and MW118 the measured flow
direction in the aquifer is predominantly horizontal based on the negligible vertical hydraulic
gradient between shallow and top-of-till wells at these locations However in the immediate
vicinity of Mill Brook vertical groundwater flow is important within the upper several feet of the
aquifer In the vicinity of wells MW103 MW117 and MW119 shallow piezometric heads are
generally 03 to one foot lower than deep heads Using a representative aquifer thickness of 50
feet the average upward vertical hydraulic gradient in this area is about 001 feet per foot by
comparison the local horizontal hydraulic gradient is approximately 0007 feet per foot Based
on these data a significant fraction of the shallow aquifer near wells MW103 MW117 and
MW119 may be discharging into Mill Brook Within the lower portion of the aquifer the
vertical hydraulic gradient becomes very small in magnitude
To further evaluate the hydraulic influence of Mill Brook on the overburden aquifer a vertical
two-dimensional numerical groundwater flow model was developed and a sensitivity analysis was
performed (Appendix U) The results of the modeling indicate that vertical flow in the upper
portion of the stratified drift aquifer near Mill Brook is more important west of the railroad tracks
(eg near wells MW101 and MW102) than east of the tracks (eg near well MW119) This
difference is due to the much smaller horizontal hydraulic gradients (on the order of 00003 feet
per foot) that are present west of the railroad tracks compared to ths area north of Mill Brook and
east of the railroad (horizontal gradients approximately 0007 feet per foot) Because the mean
water level in the brook is lower than the groundwater table elevation vertical flow is created in
the upper portion of the stratified drift aquifer and the depth to which this vertical flow is
important is greater in areas where the horizontal hydraulic gradient (and groundwater velocity is
less) In the vicinity of wells MW101 and MW102 the groundwater flow simulations indicate that
as much as one-third to one-half of the stratified drift aquifer may discharge into Mill Brook
East of the railroad tracks no greater than ten to 25 percent of the groundwater flow in the
stratified drift aquifer is estimated to discharge into the brook
East of the railroad tracks and south of Mill Brook a consistent downward groundwater flow component is observed in addition to the regional horizontal flow component As discussed
5797wpdocraquograquolluprifinaltextmaBterrifhl061297 3-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
above this downward component is largest near the Former Primary Disposal Area A small
downward flow component was also observed in the vicinity of wells MW106 and MW104
Figure 3-21 is a three-dimensional perspective drawing of groundwater movement in the
overburden aquifer which was developed to further illustrate the relative importance of the
horizontal and vertical flow components in the vicinity of the Former Primary Disposal Area
The figure consists of the two sets of piezometric head contours representing shallow and deep
(top-of-till) water level measurements recorded on February 2 1995 The lower piezometric
surface is representative of flow conditions throughout the middle to lower portions of the aquifer
The upper surface represents the piezometric head variation near the water table Presented
together in the same figure these two sets of contours allow an interpretation of the predominant
(but not all) three-dimensional pathlines originating in the vicinity of the Former Primary Disposal
Area As the pathlines illustrate shallow groundwater near these locations is expected to move
predominantly downward in the upper portion of the aquifer (although some local horizontal flow
may occur due to variations in the hydraulic conductivity of aquifer material) due to the large
vertical hydraulic gradients and the small aquifer thickness
Once groundwater has passed through the less permeable shallow soils it moves in a
predominantly horizontal direction dictated by the piezometric head distribution in the lower
portion of the aquifer
Based on the stream piezometer data presented in Table 3-5 Mill Brook generally gains water
from the overburden aquifer in the northern portion of the Study Area For most dates stream
bed flow was upward at piezometers PZ-6 PZ-5 PZ-4 PZ-4A and PZ-4B located west of the
railroad tracks and at piezometers PZ-1 and PZ-2 located east of the railroad tracks The
streambed vertical flow direction at piezometer PZ-3 located immediately upstream from a beaver
dam and possibly influenced by backwater effects was variable These data are consistent with
the shallow groundwater flow conditions depicted in Plate 3-9 where the head contours passing
through Mill Brook are bent (or V) in an upstream direction This piezometric head contour
pattern is representative of a gaining stream
Any groundwater discharge from the aquifer into Mill Brook would be significantly diluted by
flow in the brook A rough estimate of the potential surface water dilution rate can be obtained
by comparing the stream flow rate with the total discharge rate of groundwater through a given
vertical cross-sectional area For example using an upper bound hydraulic conductivity estimate
of 100 feet per day (0035 cms) a horizontal hydraulic gradient of 0001 feet per foot and an
area 200 feet wide (plume width) by 20 feet deep (about one-third of the aquifer thickness) a
conservatively high estimate of potential discharge from the contaminated portion of the aquifer
5797wpdocraquogalluprifinaltextmasterrifhl061297 3-16 Q^T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
into Mill Brook is approximately 0005 cubic feet per second or cfs (21 gpm) Based on a
measured stream flow rate of about 30 cfs at station UB10 the concentrations of dissolved
constituents in groundwater would be reduced by a factor of about 6000 upon mixing with the
entire stream flow
34 Ecology An ecological study was performed primarily to delineate wetlands and to make local observations
of the types and abundance of plants and animals in the area
341 Wetland Delineation
Delineation of wetlands within the Study Area and adjacent lands was conducted during the period
of August 26 to September 1 1994 Team members included two ESE wetlands biologists and a
certified soil scientist affiliated with the Soil Science Society of Southern New England As
discussed in Section 2131 the delineation performed to meet the States criteria focused on soil
types and hydric soil characteristics while the delineation performed to meet the Federal criteria
used USACOE methods which include the examination of vegetation hydrology and soils
As shown on Plate 3-14 wetlands were identified and delineated along the northern and western
portions of the Study Area Areas bordering the Site to the south and east reflect upland
conditions
Wetland delineation efforts were initiated along the face of a steep gradient along the southwestern
portion of the study area (west of the railroad grade) This allowed the field team to observe the
most obvious characteristics of both upland and wetland regimes Areas reflecting more subtle
wetlandupland indicators were investigated after having gained local experience with the obvious features
The wetland bordering the southwestern portion of the study area is a white cedar swamp
(unnamed) supporting a varying density of trees The swamp is hydraulically connected to the
Mill Brook system by a narrow stream The stream limits surface water flow causing the swamp
to maintain a long hydro period (duration of inundation or saturation) even though it is
topographically higher than the receiving floodplain It appears that the swamp remains inundated
during most years with the possible exception of drought years Judging from the high hydraulic
conductivity of the surrounding soils the swamp receives water through seepage from
surrounding uplands and to a lesser degree from surface water runoff
Portions of the swamp support a low density of older cedars while other areas support denser
stands of young cedars It appeared that the older age class occurred in deeper water while the
5797wpdocsgalluprifinraquoltextmasterrifhl061297 3-17 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
younger stands favored shallower water White cedar trees are not tolerant of fire events and it is r
likely that this age class distribution reflects a fire-maintained system where the deeper portions of
the swamp have been more effective in excluding natural fires hence supporting the oldest
cedars Additional hydrophytic plant species identified within the transition zone include red
maple common reed duckweed jewelweed cattail and coast pepper-bush
The upland system bordering the cedar swamp and floodplain forest supports a sub-climax to near
climax hardwood forest Topography of the upland includes steep slopes to gently undulating
land Canopy vegetation (trees) are dominated by oak species (red white and chestnut) with
white oaks nearer the wetland transition area and red and chestnut occurring on the higher
portions of the uplands Other canopy species included white ash quaking aspen hickories and
dogwoods Common understory vegetation included sheep laurel black cherry and green briar
Herbaceous vegetation included species found in the under story and canopy in addition to hay-
scented fern among others
Northward of the stream feature draining the cedar swamp lies the broad floodplain of Mill Brook which closely coincides with the northern boundary of the Site The floodplain is generally flat with many small raised hummocks This area reflects more seasonal fluctuations in hydro period and shallower water depths than the cedar swamp a result of more efficient drainage of the system For this reason natural succession is more advanced and the system supports a higher _ Jgth
diversity of hardwood canopy under story and herbaceous species composition
With the exception of two small isolated topographic depressions (excavated pits) located just west of the southern portion of the Site the delineated wetland areas correspond with the edge of the Mill Brook floodplain Most of the wetlandupland boundary occurs along the edge of a steep grade which closely coincides with the 150-foot ground elevation contour interval The sharp relief produces a narrow transition zone between upland and wetland communities The delineated lines reflect this as the State and USACOE wetland boundaries coincide at nearly
every location The State and USACOE lines are different in a small area adjacent to the railroad tracks immediately north of the Site In this area the State line is upgradient of the USACOE line The soils above the floodplain do not exhibit hydric soil characteristics as defined in the federal manual used for delineating wetlands The soil appears well-drained and depth to water is at a lower elevation than the floodplain soil just a few feet away The soil resembles the description of Suncook an excessively drained soil commonly mapped with Rippowam soils Both Rippowam and Suncook soils are listed on the State hydric soils list while Suncook is not listed by SCS as a hydric soil
5797wpdocsgalluprifinaltextmasterrifhl061297 3-18 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
A relatively small area of wetlands were determined to occur within the boundaries of the Site proper Wetlands occur in the area northeast (upgradient) of the Former Primary and Secondary
Disposal Areas and along the northern border of the Site east of the railroad bed The two topographic depressions corresponding to the former disposal areas (primary and secondary) lack
hydrophytic vegetation and hydric soil characteristics Other excavated areas to the south and
southwest (on-site) support hydrophytic vegetation and meet hydrology criteria but lack hydric
soil characteristics The depression to the southwest bordering the railroad supports hydrophytic vegetation and is occasionally inundated with surface water (following significant precipitation
events) but lacks hydric soil indicators In this area the ponded water was judged to be the
result of a confining layer of residual tar (presumed to be associated with former CTDOT asphalt
plant operations) immediately beneath an organic layer which causes precipitation to accumulate
342 Plant and Animal Survey
Site Characterization
An objective investigation of native plant and animal species and their habitat was conducted by US Fish and Wildlife Service (USFWS) staff in summer of 1993 (Prior et al 1995) Their
examination included a Site walkover observation and mapping of vegetation cover (shrubs
trees hydrophytic plants) and observation of direct or indirect evidence of wildlife (birds mammals amphibians) Although the Site proper is characterized as highly disturbed no
conclusions were drawn with regard to the effects of past human disturbance on the local ecology
The large majority of plant and animal species observed in the study are native to the region and
commonly found in other disturbed communities andor wetland environs
Reconnaissance of the study Site and adjacent lands was performed prior to delineation activities
to identify habitat types terrain physical access and develop logistics for completing the wetland
delineation The study area is a peninsular feature which extends northward and westward from
the Site entrance at Tarbox Road The study area is bisected diagonally by the railroad right-ofshy
way The Gallup Quarry Site (the quarry) lies to the east of the railroad divide and the remainder
of the study area (the west end) lies to the west Portions of the east boundary of the quarry abut
State Route 12 with other areas bounded by private property
The boundaries of the peninsula are characterized generally by steep slopes which are met
immediately by wetlands The upland soils are glacial till with some areas composed mostly of sands with coarse gravel occurring with lower frequency Some of the higher and relatively
undisturbed areas are composed of large rocks protruding to the ground surface Soils in the
transition zones between upland and wetland are composed of organic muck overlying sand
5797wpdoc8gilluprifinaltextmalaquoterriftil061297 3-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
These natural conditions along with historical use of portions of the area (mining and
manufacturing) cre responsible for the character of the plant communities found throughout the
study area The quarry reflects significant disturbance from historical mining and asphalt
operations The Site has numerous excavated depressional areas and areas of mounded earth
material These features significantly distinguish the quarried area from the area off-site to the
west which is undeveloped and relatively undisturbed The assemblage of plants in the quarry
reflects these conditions many of the excavated zones are devoid of vegetation and areas adjacent
to them support a mix of successional pioneer species Density of vegetation ranges from bare
soil to dense brush and sapling sized trees Areas of highest vegetation density are associated
with both low elevation (greatest soil moisture regime) and age (length of time since disturbance)
Trees throughout the quarry are young and small in comparison with those found in the forested
areas west of the railroad Vegetation on-site is characterized as early successional species The
more common species include black willow northern bayberry eastern cotton-wood quaking
aspen goldenrod and black cherry
Few wildlife species were observed or noted during wetland delineation activities Wildlife
activity within the Study Area was limited during the survey period but should be expected to
support a much greater diversity of wildlife during the spring and summer seasons when birds
(especially migratory) conduct nesting and rearing activities Most of the species observed during
the survey are expected to overwinter at the study area Bird species recorded include mourning
dove eastern peewee tufted titmouse black-capped chickadee blue jay white-breasted nuthatch
gray catbird American robin and northern cardinal
Vegetation species were recorded during the wetland delineation and are presented in Table 3-6
These reflect species occurring within wetland transition zones Additional species are expected
to occur in more xeric uplands and deeper wetlands
Although no qualitative samples of freshwater macroinvertebrates were obtained the distribution
of different genera between stations would appear to be strongly influenced by the variable
substrate composition and habitat which ranges from shaded moderate flowing rocky stream bed
(eg UB1 UB9) to sunny low energy depositional areas containing sand or deep muck (eg
UBS LB2)
5797wpdocsgalluprifinaltextmasterrifnl061297 3-20 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
40 Nature and Extent of Contamination
This section discusses the distribution of contaminants within the various media throughout the
Study Area and is based on analytical data collected during nine separate sampling events These nine sampling events include the Phase 1A investigation the Phase IB investigation and the Long-
Term Monitoring Program events conducted during April July November 1995 February May
August and November 1996 and February 1997) The results of the Phase 1A investigation
Phase IB investigation and the Long-Term Monitoring Program sampling events (except
November 1995 which was conducted concurrently with the Phase IB investigation) were also
presented in earlier reports (ESE 1995 -1995b -1995c 1996a 1996b 1996c 1997a 1997b)
Section 41 addresses the results of investigations into potential source areas including surface and subsurface soil Section 42 addresses the results of groundwater investigations Section 43
presents the results of investigations of surface water sediments and wetland soils Section 44 addresses the results of air monitoring investigations Section 45 identifies potential sensitive
human receptors within a one mile radius of the Site
Sample analyses were performed pursuant to the Gallups Quarry Superfund Project RIFS Quality Assurance Project Plan dated August 29 1994 Laboratory analytical testing for Level 4
was generally conducted for analytes identified in the Contract Laboratory Program (CLP) target
compound list (TCL) for organics and target analyte list (TAL) for inorganics Analyses were
conducted pursuant to the CLP Statement of Work for Organics MultimediaMulticoncentrations
Document OLM 018 and the CLP Statement of Work for Inorganics
MultimediaMulticoncentrations Document ILM 030 Appendix IX analyses were conducted by
CLP and SW-846 Methods as described in the QAPP Low-level VOC in drinking water were analyzed by EPA Method 5242 with CLP SOW reporting Laboratory reports for the Phase 1A
Phase IB and Long-Term Monitoring Program sampling events are presented in Appendices H
through P Laboratory data for sample splits collected by EPAs oversight contractor during the
Phase 1A July 1995 and Phase IBNovember 1995 sampling events are also presented in
Appendices H J and K respectively The results of detected analytes are summarized in Section 4 tables The definitions of the qualifiers used for the laboratory data precede the tables in
Section 4 As discussed in various sections analyte concentrations are given either as milligramskilogram (mgkg) or microgramsliter (ugL) The units mgkg are also used
interchangeably with the term part per million (ppm) The units ugL are equivalent to parts per
billion (ppb)
Data validation was performed on all Level 4 data according to the requirements of EPA Region
I Laboratory Data Validation Functional Guidelines for Evaluating Organic Analyses (February 1
5797wpdoclaquogilluprifinaltextmlaquo8terrifiJ061297 4-1 QZT Environmental
Gallups Quarry Superjund Project - Remedial Investigation
1988 as modified November 1 1988) and Inorganic Analyses (June 13 1988 as modified
February 1989) Data validation was performed by David MacLean an independent data
validator Summaries of Mr MacLeans data validation results are presented in Appendix Q
41 Contaminant Source Investigation 411 Visual Site Reconnaissance
A comprehensive visual site reconnaissance was conducted over a three week period from August
23 until September 13 1994 to determine the potential presence of unknown disposal areas
Prior to the start of this survey a grid system was established to allow systematic coverage of the
Site and to locate features of interest The grid used to conduct the visual Site reconnaissance is
described in Section 21 A Site plan which includes the survey grid and the features described
below is shown on Plate 4-1 The features identified on Plate 4-1 are also summarized in Table 4-1
Based on this visual survey the ground surface in the northern portion of the Site which includes the Former Primary and Secondary Disposal Areas is covered with sand and gravel with sparse
to no vegetation Topographic relief is estimated to be as much as 20 to 30 feet and is attributed
to the Sites past usage as a sand and gravel quarry Many of the topographic low spots were
observed to contain either standing water (following rain events) or moist soil (indicative of
intermittent periods of ponded water)
The central portion of the Site which contains the Former Seepage Bed is presently heavily
vegetated Crushed stone and boulders are evident over a large portion of this area and the soils
consist mainly of a sandy till Immediately east and northeast of the Former Seepage Bed is a
topographic high with numerous boulders at the ground surface Evidence of previous test pit
explorations were also observed in this general vicinity Asphalt and mounds of asphalt pavement
were also observed in several areas and are presumed to be remanent of the State of Connecticut
Department of Transportation (CTDOT) asphalt plant operations discussed in Section 132
The southern portion of the Site contains the entrance to the former CTDOT asphalt plant as well
as the remains of the former plant itself These remains consist primarily of concrete footings
and retaining walls The remains of the asphalt plant are located along trending lines E through
K approximately 800 to 900 feet north of Tarbox Road The remains of a 6-foot diameter brick
and concrete masonry structure were observed along with an 8-inch diameter clay pipe leading
into the ground at the former plant location
The area located in the southwestern portion of the Site along line A includes mounded earthen
material piled along the western perimeter of the Site Scattered metal debris including several
5797wpdocsgalluprifinaltextmasterrifiil061297 4-2 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
empty rusted drums were observed adjacent to and partially buried within the mounded materials
Other objects consisting of timbers steel culvert tires and mounded asphalt were also observed
along the A line Mounded earthen materials located on lines M and N (400 to 650 feet north of
Tarbox Road) were observed to also contain miscellaneous debris (corrugated steel culvert hoses
and cables tires etc) and several empty rusted drums These areas are presently heavily
vegetated Other areas at the southern portion of the Site consist of a mixture of grassland and
brush There are numerous mounds of earthen material and scattered patches of asphalt and
pavement remanent of CTDOT operations throughout this portion of the Site
The Bionetics Corporations under contract to USEPA performed a review of historic aerial
photographs of the site and issued a Site Analysis Report (Bionetics Corp 1990) The historical
aerial photographs were used to prepare a Site plan which indicated the locations of suspected or
potential disposal areas (Figure 4-10 from the Phase 1A Work Plan (ESE 1994)) That Site plan
showed the locations of the three known former disposal areas as well as several much smaller
features described below Based on the visual reconnaissance performed during the RI areas
described in the Bionetics Report as either stained or wet or standing liquid or wet ground
correspond to topographic low spots in which ponded rainwater has been observed In addition
no visual evidence indicative of disposal activities was observed in the vicinity of the several
pits (dated 1981 through 1988) identified in the Bionetics Report These pits are believed to
be remnant of previous investigation test pits
An area described in the Bionetics Report as an extraction and an area of disturbed ground
northwest of the Former Seepage Bed correspond to an excavated area in which asphalt and
miscellaneous debris were observed during the Site reconnaissance The presence of mounded
materials in the vicinity of the Former Seepage Bed was confirmed during this visual
reconnaissance The mounded materials observed are comprised of earthen materials andor
asphalt pavement
A number of areas located within the southern portion of the Site were described in the Bionetics
Report as suspected disposal areas Features described as containing liquid generally
correspond to topographic low spots which were observed during the Site reconnaissance to
contain ponded rainwater following rain events The large feature described in the Bionetics
Report as extraction with liquid and associated dark toned material corresponds to a presently
open excavation in which asphalt was observed No features or specific objects were observed
during the Site reconnaissance which correspond to the locations of the unidentified objects
noted in the report The remains of a circular foundation observed during the Site reconnaissance
in the vicinity of the former CTDOT plant corresponds to the location of the possible vertical
5797wpdocraquogalluprifiiwltextmasterrifhl061297 4-3 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
tank Scattered mounds of earthen materials observed throughout the southern portion of the
Site correspond to the numerous mounded materials identified in the Report
Based on the observations made during this survey it is apparent that the landforms on-site have
been altered numerous times during past usage Extensive areas are presently heavily overgrown
and do not appear stressed Various earthen materials have been excavated and mounded at
numerous locations throughout the property and are presumed to be remnant of the former sand
and gravel quarrying operation andor the operation of the State DOT asphalt plant Also
patches of asphalt and mounds of asphalt pavement ranging from several to tens of square feet in
size were observed at multiple areas around the Site
The major features described as potential or suspected disposal areas in the Bionetics Report were
identified and described during the visual reconnaissance Although several empty 55 gallon
drums in various states of decomposition and scattered debris (consisting mainly of residential
trash scrap metal car parts etc) were observed at a number of locations across the Site no
intact drums or significantly stained or stressed areas were observed Other than the three known
former disposal areas no features were observed during the visual reconnaissance which indicate
the potential presence of large disposal or dumping areas
The above mentioned areas which contain debris including several empty 55-gallon drums were
further assessed during the soil gas and geophysical screening surveys performed as part of the
Phase 1A investigation The findings of these screening surveys are discussed below
412 Soil Vapor Survey
The soil vapor survey conducted on-site included a total of 100 soil vapor points installed along
an approximate 100-foot orthogonal grid Six additional sampling points were installed at three
locations where partially buried decomposed or empty 55-gallon drums were observed during
the visual site reconnaissance and at three areas where geophysical surveys detected the presence
of EM-31 andor MAG anomalies Each soil gas sample was analyzed for the presence of the
following eight VOC using a portable gas chromatograph acetone benzene 12-dichloroethene
(DCE) methylethyl ketone (MEK) methyl-isobutyl ketone (MIBK) 111-trichloroethane (TCA)
trichloroethene (TCE) and toluene
Of the 106 soil vapor sampling points tested detectable concentrations of VOC were identified at
only three locations These three locations SV160 SV165 and SV172 (shown on Plate 2-5)
were all located within approximately 50 feet of the Former Primary Disposal Area Specifically
TCE was detected at SV160 and SV165 and TCA was detected at SV165 and SV172
5797wpdocsgalluprifinaltextmasterrifhl061297 4-4 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
Likewise no VOC were detected at three additional survey points SV201 SV205 and SV206
installed within one foot of the 55-gallon drum which was observed at each of those locations or
at survey points SV202 SV203 and SV204 located in the vicinity of geophysical anomalies
identified during the EM-31 and MAG surveys
As described in the Work Plan the soil gas investigation was used as a screening survey to
identify apparent soil contamination in an effort to locate any potential unknown disposal areas
Based on the results of the soil gas survey no additional potential disposal areas were identified
413 Geophysical Investigations and Test Pits
Electromagnetic terrain conductivity (EM-31) and magnetometer surveys were conducted by
Weston Geophysical of Northboro Massachusetts as screening surveys to identify potential
unknown disposal areas The Weston Geophysical Report (provided as Appendix A) describes
in detail the findings of the geophysical investigations The significant findings of these two
screening surveys and of the follow-up test pit program are discussed below
4131 EM-31 Survey
The electromagnetic terrain conductivity measured across the Site was generally uniform with
most anomalies being attributed to wholly exposed or partially buried metallic debris (eg
automobile body parts empty rusted drums scrap pipe angle iron steel culvert and steel cable)
However two EM-31 anomalies could not be accounted for by noted surface features As shown
on Plate 2-14 the two unexplained EM-31 anomalies were located along trend line M at station
550 and at station 590 Due to the complexity of the anomaly located at station 550 an estimate
of its ferrous mass could not be made The second EM-31 anomaly was described as limited in
extent and was estimated to contain approximately 100 pounds of ferrous material assuming a burial depth of five feet (smaller objects at shallower depths would also explain the anomaly)
4132 Magnetometer Survey
The magnetometer survey identified a relatively flat gradient across the Site with a number of
localized anomalies most of which corresponded directly with visible surface features or objects
(as described above) A total of four anomalies were identified which could not be readily
attributed to known surface features Two of these anomalies occurred along trend line M and
correspond to the two EM-31 anomalies described above A third magnetometer anomaly was
identified along trend line C between stations 760 and 800 This anomaly was described as
approximately 10 feet in width and was interpreted as being the result of small amounts of ferrous
material spread over the length of the anomaly (approximately 40 feet) A fourth anomaly was
identified along line L at station 315 This anomaly was interpreted to consist of a small
amount of ferrous material buried at shallow depth
5797wpdocsgalluprifinaltextmraquosterrifhl061297 4-5 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4133 Test Pit Investigations
As described above the geophysical screening surveys revealed a total of four locations at which
EM-31 or magnetometer (or both) anomalies were detected that could not be attributed to visible
surface features The anomalies measured along line M were noted in both the EM-31 and
magnetometer surveys while the anomalies along lines C and L were only measured in the
magnetometer survey To confirm the source of these anomalies test pits were excavated at the
location of each anomaly Test pit excavation was observed by EPA oversight personnel
The presence of varying amounts of miscellaneous buried scrap metal debris described below
was identified at each test pit location At the anomaly located along Line C the excavated
debris included small rusted cans sheet metal and steel cable During the excavation of the test
pit located at the anomaly along line L a three foot long piece of a solid iron rod
approximately one inch in diameter was found buried approximately four inches below the ground
surface At the anomalies located along Line M a variety of ferrous debris was uncovered
including a crushed eight foot section of corrugated steel culvert approximately 2 feet in
diameter sheet metal nuts bolts steel cable and small rusted cans No drums intact or
otherwise were encountered at any location Soil removed from each excavation as well as the
side walls and bottoms of the excavations were screened for the presence of VOC using a PID
No elevated PID readings were measured Furthermore no visible evidence of staining was
noted in the soil at any of the excavations Upon excavation all metallic debris was placed on
the ground surface adjacent to the excavation and the test pits were backfilled with native soil
Test pit logs for the four test pits are shown in Appendix E
414 Background Soils
Soil samples were collected at two monitoring well cluster locations MW109 and MW112 to
determine the general Site background levels of TALTCL compounds The two locations were
chosen based on their upgradient position in relation to the former disposal areas The soils were
submitted for laboratory analysis for TALTCL parameters (VOC SVOC pesticides PCS
metals and cyanide) Tables 4-2 and 4-3 show the positive detections for VOC and metals
These tables only show the constituents that were detected at the site Constituents that were not
detected in any sample are not shown There were no detections of SVOC or pesticidesPCB in
any background soil sample
Due to the limited surficial deposits and abundance of boulders encountered at the MW109
location samples could only be collected from the 6-8 foot interval which is representative of till
at this location Discrete samples collected at the MW112 location were obtained from the 8-10
foot and 40-42 foot intervals which represent stratified drift and till respectively Composite
5797wpdocsglluprifinlaquoltextmlaquosterrifhl061297 4-6 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
samples from MW112 were collected from the 7-14 foot and 34-40 foot intervals (stratified drift
and till respectively) These depths were chosen based on their lithology
The results of the laboratory analyses for the soils collected at MW109 indicate the presence of
trace concentrations (0004 mgkg) of toluene no other VOC were detected No detectable
concentrations of SVOC pesticides or PCB were encountered in soil from the MW109 sample
location
Soils collected at the MW112 location also contained detectable concentrations of toluene
Toluene was detected at concentrations of 003 0017 0029 and 0032 mgkg from 8-10 feet 7shy
14 feet 10-14 feet and 34-40 feet respectively Trace concentrations of methylene chloride
(0003 mgkg) and trichloroethene (0002 mgkg) were also detected in the MW112 sample at 10shy
14 feet and 40-42 feet respectively No detectable concentrations of SVOC pesticides or PCB
were identified at the MW112 location
Although the source of the VOC is unknown all three of these compounds are organic solvents
that are (or were ) commonly used in many household (eg spot removers paint strippers
aerosols) commercial (eg pesticide formulations inks and dyes) and industrial (eg
degreasers) products
Metals concentrations in background soil boring samples are shown on Table 4-3 As expected
various metals were detected in all soil samples Analytical results for metals for all of the
MW112 samples were within the common range for soils found in the eastern United States
Heavy metals were generally detected only at trace concentrations Alkaline earth metals (eg
Ca Mg K) were detected at levels not unexpected for soils in the region Background concentrations of metals in subsurface soils were used for comparison purposes in analyzing the
significance of the metals concentrations measured in other non-background soil samples
415 Soils From Former Known Disposal Areas
Soil borings were drilled at each former known disposal area to determine whether residual
contamination remains in surface and subsurface soils During the Phase 1A investigation a total
of ten soil borings were performed Soil samples were collected from these borings and
submitted for laboratory analysis for TALTCL parameters (VOC SVOC pesticides PCB
metals) pH total organic carbon (TOC) and moisture content An additional six borings were
performed during the Phase IB Investigation Soil samples collected during the Phase IB
Investigation were submitted for laboratory analysis for VOC and pesticidesPCBs The
locations of the soil borings are shown on Plate 2-3
5797wpdoc8galluprifinaltextma8terrifhl061297 4-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Samples from the 0-1 foot interval were collected from each boring by hand using a stainless
steel scoop Continuous soil samples beneath the 0-1 foot interval were collected using a truck-
mounted drill rig equipped with standard split-spoon samplers Generally samples were collected
from both above and below the water table and at depth within each of the former known
disposal areas In addition each significant lithologic unit was sampled The specific sampling
depths and length cf sampling interval varied for different analytical parameters depending on the
lithology and volume of sample recovered from each spoon Sample intervals and analytes are
summarized in Table 2-2
A brief description of the reported historical disposal activities and the findings of the Soil
Sampling Program for each specific area are described below Positive hit tables showing the
laboratory results for soil boring samples collected from within the former known disposal areas
are presented in Tables 4-4 through 4-7 The unvalidated laboratory data for TALTCL
parameters are presented in Appendix H (Phase 1A data) and K (Phase IB data) Laboratory
results for pH total organic carbon and moisture content are presented in Appendix R
4151 Former Seepage Bed
The Former Seepage Bed is located near the center of the Site This feature is located on the
north side of a local bedrock high which is overlain by 10 to 20 feet of boundary till Historical
records indicate that this area was used for the direct discharge of liquid waste to the ground
surface It has been reported that an inverted dump truck body was buried in this area and was
connected to the ground surface via a pipe Liquid wastes were then reportedly poured directly
into the pipe The wastes reportedly dumped in this area have been described as low pH liquids
characteristic of metal pickling liquors The dump truck body and the contaminated earth were
removed in 1979 during CTDEP remedial efforts Approximately 20 tons of lime (which is
approximately equal to 10 cubic yards) was reportedly spread in the vicinity of the seepage bed to
neutralize any residual low pH material The soil boring program indicated that fill material in
this area extends from 3 to 7 feet below the ground surface Based on the approximate lateral
extent of this former disposal feature (as shown in historic plans of the Site) approximately 230
yards of sand and gravel fill material were used to backfill the CTDEP excavation
To investigate this area three soil borings (SB101 SB102 and SB103) were completed The
borings within the Former Seepage Bed were terminated at auger refusal depths of 68 feet
(SB101) 185 feet (SB102) and 160 feet (SB103) Within this area groundwater was only
encountered in the bottom 6 inches of the deepest boring (SB 102)
5797wpdocsgalluprifinaltextmasteiTifnl061297 4-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Surface Soil Sample Results - Former Seepage Bed
As shown in Table 2-2 the 0-1 foot interval was sampled at each location and submitted for
laboratory analysis for VOC SVOC pesticides PCB and metals No VOC were detected in this
interval at any of the three soil borings within the Former Seepage Bed In the 0-1 foot interval
very low levels of SVOC primarily polynuclear aromatic hydrocarbons (PAH) were detected at
SB101 and SB103 The concentrations of PAH ranged from 0012 ppm to 0076 ppm Moderate
concentrations of bis(2-ethylhexyl)phthlate (15 ppm) were also seen in this interval at SB101
Trace levels of certain pesticides were also seen in the 0-1 foot interval at SB101 [44-DDE
(00014 ppm) 44-DDT (0019 ppm) and 44-DDD (0041 ppm)] and at SB102 [44-DDD
(0011 ppm)] At SB102 a low level of PCB (Aroclor-1260 at 0027 ppm) was detected in the
surface soil sample
The results of metals analyses have been compared to background soils metal concentrations
determined from soil samples collected from the background monitoring wells MW109 and
MW112 With the exception of calcium (12200 ppm) and magnesium (9620 ppm) seen in the
0-1 foot interval at SB102 most metals in the surface soil samples were close to the background
concentrations seen at the Site The elevated concentrations of both calcium and magnesium are
attributed to the 20 tons of lime which were used in this area by CTDEP Compared to the
background level seen for lead (35 ppm) the concentration of this metal in the 0-1 foot interval
was slightly higher at SB101 (59 ppm) SB102 (43 ppm) and SB103 (69 ppm) Also silver
which was not seen in any of the background samples was detected in the 0-1 foot interval at
SB101 at 87 ppm
Unsaturated Zone Sampling Results - Former Seepage Bed
Within the unsaturated zone below the 0-1 foot interval described above only trace levels of
VOC were detected Toluene was seen in SB101 (4-6 feet) and SB102 (16-18 feet) at a
concentration of 0002 ppm Xylene (total) was also detected at the same two intervals at the
same concentrations The only other VOC detected was TCE in SB101 (4-6 feet) at a
concentration of 0004 ppm
The only SVOC detected within the unsaturated zone at the Former Seepage Bed was di-n-octyl
phthlate detected in all three borings at various depths at concentrations ranging from 001 to
0021 ppm Very low concentrations of several pesticides (SB101) and PCB (SB101 and SB102)
were detected at various depths in unsaturated zone samples below the 0-1 foot interval The
pesticides 44-DDD (0033 ppm) 44-DDT (0024 ppm) and dieldrin (000064 ppm) were
5797wpdocBgalluprifinaltextmlaquosteiTifhl061297 4-9 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
detected at SB 101 The highest detections of the PCS for Aroclor-1260 and Aroclor-1254 were
0027 (SB102 0-1 feet) and 0034 ppm (SB1012-5 feet) respectively
Within the unsaturated zone below the 0-1 foot interval the only metals detected above the
highest background concentrations were aluminum barium iron magnesium manganese and
potassium The highest concentration of each of these metals was only slightly higher than
background levels and all were within the same order of magnitude
Among the Former Seepage Bed borings only one (SB 102) encountered groundwater above the
auger refusal depth Since only six inches of saturated soil was encountered the limited sample
volume was submitted for VOC analysis only No VOC were detected in this sample
pH TOC Moisture Content - Former Seepage Bed
The pH of samples collected in this area ranged from 622 to 792 Total organic carbon values
(mgkg) ranged from 1600 to 23000 Moisture contents ranged from 42 to 105 percent
4152 Former Secondary Disposal Area
The Former Secondary Disposal Area is located in the northwestern corner of the Site adjacent to
the railroad tracks The Disposal Area is presently seen as a depression which is approximately
50 feet wide by 60 feet long and is approximately 6 to 8 feet below the surrounding ground
surface The ground surface at this area is covered by approximately 2 feet of backfill (mostly
sand) material The fill is underlain by fine- to coarse-grained sand which ranges in thickness
from approximately 6 to 22 feet Sandy till ranging in thickness from 10 to 20 feet underlies the
sand The depth to groundwater from the bottom of the depression is approximately 10 feet
Historical records indicate that this area was used for the disposal of drummed liquid wastes
Approximately 200 drums and an unknown quantity of contaminated soil were removed in 1979
during CTDEP remediation efforts
In order to characterize residual contamination which may be present beneath this area three soil
borings (SB 104 SB 105 and SB 106) were performed within the depressed area ranging in depth
from 30 feet (SB 105) to 36 feet (SB 104) Within this area groundwater was encountered at
approximately 10 feet below the ground surface
5797wpdocsglaquolluprifinlaquoltextmaBterrifnl061297 4-10 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Surface Soil Sample Results - Former Secondary Disposal Area
Within the 0-1 foot interval only a trace concentration of one VOC (ethyl benzene at 00006
ppm) was detected (at SB104) The only SVOC detected in this interval was butylbenzylphthlate
(014 ppm) at SB 104 Very low concentrations of pesticidesPCB were measured at each boring
Aroclor-1254 was detected at SB104 (0025 ppm) and SB105 (0021 ppm) Aroclor-1260 was
detected at all three borings ranging in concentration from 00089 to 0031 ppm Dieldrin was
detected at SB 104 at trace levels (000048 ppm)
In the 0-1 foot interval nearly every metal detected occurred at concentrations close to those for
the background samples with the exception of lead which was detected at a concentration of 118
ppm at SB 104 Cyanide was detected in this interval at very low concentrations ranging from 16
to 97 ppm
Unsaturated Zone Sample Results - Former Secondary Disposal Area
Between the 0-1 foot interval and the groundwater table at the Former Secondary Disposal Area
no VOC were detected The only SVOC detected in this zone were at very low levels
(butylbenzylphthlate at 0037 ppm and di-n-octylphthlate at 0012 to 0029 ppm) Also in this
interval at SB104 and SB105 low levels of the PCB Aroclor-1254 and -1260 were detected at
concentrations up to 0055 ppm and 0018 ppm respectively Dieldrin was detected at a trace
level (00014 ppm) at SB104 Within this zone most of the metals were close to the background
soil concentrations except for lead (224 ppm) at SB104 and copper (476 ppm) at SB105
Cyanide was detected in the 1-10 foot interval at SB104 and SB105 at very low concentrations of
83 and 31 ppm respectively
Saturated Zone Sample Results - Former Secondary Disposal Area
Beneath the groundwater table within the Former Secondary Disposal Area no VOC were
detected The only SVOC detected was di-n-octylphthalate which ranged in concentration from
002 to 008 ppm Very low levels of endrin (00004 ppm) and Aroclor-1248 (001 ppm) were
also detected just below the water table but were not present in the deepest sample collected (26shy
28 feet) The only metals which were detected below the water table at concentrations notably
higher than background levels were copper and nickel Copper ranged in concentration from 621
to 863 ppm while nickel ranged from 119 to 169 ppm The highest concentrations of these
two metals were detected just below the groundwater table
5797wpdocsgalluprifinaltextmasterrifhl061297 4-11 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
pH TOC Moisture Content - Former Secondary Disposal Area
The soil pH ranged from 688 to 751 TOC ranged from lt 1500 to 2800 mgkg and moisture
content ranged from 37 to 124 percent
4153 Former Primary Disposal Area
The Former Primary Disposal Area is located at the northern end of the Site approximately 150 feet east of the Former Secondary Disposal Area This feature is seen as a circular depression
approximately 130 feet in diameter (at the top edge) and is approximately 8 to 10 feet lower than
the surrounding ground surface Non-native fill material (sand and gravel) ranged in thickness
from approximately 2 to 4 feet Underlying the fill is an approximately 15- to 20- foot thick
generally sandy horizon which overlies 6 to 15 feet of till The water table in this area ranges
from approximately 3 to 6 feet beneath the ground surface in the bottom of the depression
Records indicate that approximately 1400 drums and approximately 5000 gallons of free liquids
were removed from the Former Primary Disposal Area during CTDEP cleanup efforts
Approximately 2000 to 3000 cubic yards of contaminated soil were also removed during that
effort
During the Phase 1A (1994) investigation a total of four soil borings (SB107-SB110) were
completed within the Former Primary Disposal Area to characterize the extent of residual soil
contamination These borings ranged in depth from 24 feet at SB108 to 39 feet at SB109 An
additional six borings (SB111-SB116) were completed during the Phase IB (1995) investigation
Samples collected during the Phase IB investigation were submitted for laboratory analysis for
VOC and PCBPesticides The purpose of the additional borings was to further delineate the
lateral extent of residual VOC and PCB contamination in the unsaturated portion of the soil The
Phase IB borings were terminated just below the groundwater surface typically five to seven feet
below the ground surface The locations of all of the borings are shown on Plate 2-5 however a
detailed close-up showing the boring locations within the Former Primary Disposal Area is shown
as an insert on Plates 4-2 and 4-3 which are discussed below The tabulated laboratory data for
both the Phase 1A and Phase IB soil borings are shown on Tables 4-4 through 4-7 (VOC SVOC
pesticidesPCB and metals respectively)
Surface Soil Sample Results - Former Primary Disposal Area
In the 0-1 foot interval only a limited number of VOC were detected generally at very low
concentrations (Table 4-4) The compounds detected in the 0-1 foot interval (followed by
concentration [ppm] and location) are as follows acetone (0007 ppm at SB107)
5797wpdocsgalluprifinaltextmasterri fhl061297 4-12 QST Environmental
Catlaps Quarry Superfund Project - Remedial Investigation
tetrachloroethene (PCE) (0018 ppm at SB109 and 0002 at SB113) toluene (0005 at SB112
0003 at SB1H and 0002 at SB115) ethyl benzene (0002 at SB113) and total xylenes (0010 at
SB113) In this same interval several phthalates (butylbenzyl bis(2-ethylhexyl) diethyl and dishy
n-octyl) were detected at various locations (Table 4-5) with no apparent spatial trend at
concentrations ranging from 0008 to 17 ppm Several PAH compounds were also detected at
SB110 in the 0-1 foot interval at concentrations ranging from 0007 to 0017 ppm As shown in
Table 4-6 Aroclor 1254 was detected in the 0-1 foot interval at every boring at concentrations
ranging from 0046 to 43 ppm Aroclor-1260 was also detected in the 0-1 foot interval at
concentrations ranging from 0046 to 23 ppm Trace concentrations of several pesticides were
also detected in the 0-1 foot interval in some borings as follows heptachlor epoxide (000058 to
0052 ppm) dieldrin (000059 to 0043 ppm) 44-DDE (000089 to 0081 ppm) and 44-DDT
(000048 to 0027 ppm) Aluminum (12200 ppm at SB110) was the only metal in the 0-1 foot
interval that was detected at concentrations significantly greater than background levels (Table 4shy
7) Cyanide was detected at a very low concentration of 16 ppm at both SB109 and SB110
Unsaturated Zone Soil Sample Results - Former Primary Disposal Area
Beneath the 0-1 foot interval but above the water table a small number of VOC were detected at
various concentrations and locations (Table 4-4) Within this zone no VOC were detected at
SB107 At SB108 methylene chloride was detected at 0001 ppm Ethyl benzene was detected
at SB 109 (015 ppm) SB110 (54 ppm) SB111 (0048 ppm) and SB115 (16 ppm) Total
xylenes were seen at SB109 (16 ppm) SB110 (46 ppm) SB111 (064 ppm) and SB115 (80
ppm) Toluene was detected at SB 110 through SB 115 at concentrations ranging from 0003 to 12
ppm PCE was seen at SB109 SB111 SB114 and SB116 at concentrations which ranged from
0003 to 17 ppm and at SB115 at 28 ppm 111-TCA was detected at SB111 112 114 115
and 116 from 0001 to 14 ppm TCE was also seen at SB111 114 115 and 116 at
concentrations ranging from 0002 to 17 ppm 2-butanone (MEK) was detected at SB111 at
0005 ppm 12-DCE was seen at both SB115 (016 ppm) and SB116 (0009 ppm) Finally 11shy
DCA (0008 ppm) 11 -DCE (0009 ppm) and carbon disulfide (0022 ppm) were all seen at
SB115 Methylene chloride (0001 ppm) was detected at SB108 These detections occurred in
the transition zone between fill and native deposits
The SVOC detected in this zone (shown on Table 4-5) included several phthalates at
concentrations ranging from 0039 to 46 ppm Napthalene was also detected at SB109 (047
ppm) and SB110 (63 ppm) 12-dichlorobenzene and 2-methylnapthalene were detected at SB110
at 098 and 081 ppm respectively The most frequent occurrence and highest concentrations of
phthlates (and SVOC in general) occurred at SB 109 and SB 110
5797wpdocraquogalluprifinaltextmlaquolaquoterrifhl061297 4-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
As shown on Table 4-6 Aroclor-1254 occurred at most of the borings in this zone at gtbullraquo
concentrations ranging from 00023 to 64 ppm Aroclor-1242 (0043 to 017 ppm) and Aroclorshy
1260 (043 to 24 ppm) were detected at SB109 and SB110 Pesticides were also detected at trace
to very low concentrations at several locations These compounds include dieldrin (000028 shy
00046 ppm) 44-DDE (000043 - 00063 ppm) 44-DDT (00013 - 00081 ppm) beta BHC
(00013-00021 ppm) and delta BHC (000086-00024 ppm) endrin ketone (00028 ppm)
heptachlor epoxide (0008 ppm) heptachlor (00093 ppm) endosulfan I (0008 ppm) and
methoxychlor (0140 ppm) Table 4-7 shows that the only metals detected within this zone at
concentrations significantly higher than background levels were cadmium (131 ppm) and copper
(103 ppm) both of which occurred at SB109 Cyanide was detected in SB110 in the 1-35 foot
interval at a very low concentration of 32 ppm
Saturated Zone Soil Sample Results - Former Primary Disposal Area
The highest concentrations of VOC within the Former Primary Disposal Area occurred just below
the surface of the groundwater table in the natural deposits immediately underlying fill material
As shown on Table 4-4 in the 4-6 foot interval at SB 109 the following VOC were detected 12shy
DCE (059 ppm) PCE (36 ppm) TCA (98 ppm) TCE (62 ppm) ethyl benzene (85 ppm)
toluene (44 ppm) and xylenes (46 ppm) In the next deepest interval sampled (14-16 feet)
generally the same compounds were detected however the concentrations were lower by an
order of magnitude At the last sampled interval (30-32 feet) generally the same compounds
were again detected but at trace levels (0001-0006 ppm) Cyanide was detected in SB110 in the
10-16 foot interval at a very low concentration of 11 ppm
A total of six SVOC were detected just below the water table at a depth of 4-8 feet below ground
surface (Table 4-5) phthalates (0039 to 0058 ppm) napthalene (021 ppm) 2-methylnapthalene
(0034 ppm) phenol (016 ppm) and 124-trichlorobenzene (0046 ppm) SVOC at greater
depths were napthalene (0076 ppm) in the 10-16 foot interval and bis(2-ethylhexyl)phthlate (11
ppm) at the 22-32 foot interval Aroclor-1254 was detected at concentrations which decreased
with depth from 02 ppm at 4-8 feet to 00096 ppm at 23-34 feet
In the saturated zone no metals were detected at levels significantly greater than background
pH TOG Moisture Content - Former Primary Disposal Area
Values for soil pH ranged from 609 to 745 TOC ranged from lt 1500 to 5500 mgkg and
moisture content ranged from 49 to 282 percent
5797wpdocsgalluprifinaltextmasterrifnl061297 4-14 QST Environmental
Gallups Quarry Superfand Project - Remedial Investigation
416 Contaminant Source Investigations Summary
The previous discussions regarding the contaminant source investigations are grouped into two
categories
bull surveys to identify unknown disposal areas (if any) and
bull investigations at known former disposal areas
Based on the findings of the Visual Site Reconnaissance the Soil Vapor Survey and the
Geophysical Investigations (including the subsequent confirmatory Test Pits) it is apparent that
significant unknown hazardous materials disposal features do not exist at the Site
Based on investigations performed within the known former disposal areas it is evident that the
Former Seepage Bed and the Former Secondary Disposal Area contain generally trace levels of
VOC SVOC pesticides PCB compounds and cyanide For the most part soil metal
concentrations are comparable to background levels measured at upgradient locations at the Site
although very low levels of cyanide (ranging from 11 - 97 mgkg) were also detected at various
depths within the Former Primary and Secondary Disposal Areas Elevated levels of calcium and
magnesium detected at the Former Seepage Bed can be attributed to the large amount of lime
which was reportedly used during remedial efforts Although elevated concentrations of several
other metals were detected at a few locations these levels appear to fall within regional range
values (for the metals with published ranges)
The Former Primary Disposal Area appears to be the only area with notable levels of residual
contamination primarily VOC including ethyl benzene toluene xylene TCA TCE and PCE
In general the highest VOC concentrations are located at or just below the groundwater table in
native materials immediately beneath the fill materials These concentrations diminish quickly
with depth Toluene ethyl benzene xylene and in one case a low level of PCE were also
detected at or near the ground surface within the fill material Empty gasoline cans numerous
off-road vehicle tire tracks and the remains of large campfire pits have been observed in the
vicinity of the former disposal areas Of the VOC detected the ones considered most significant
are those which are also seen in groundwater above their respective MCL (groundwater results
are discussed separately in section 42) In an effort to illustrate the locations where the more
notable amounts of residual VOC contamination are found Plate 4-2 which shows the locations
of total chlorinated VOC has been prepared On this plate the values for total chlorinated VOC
have been color-coded as follows sample intervals where all compounds were below the detection
limit (BDL) are not colored intervals where total chlorinated VOC values are present but less
5797wpdoc8glaquolluprifinraquoltextmasterrifhl061297 4-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
than 1 ppm are shown in green values between 1 and 10 ppm are shown in yellow and locations
between 10 and 35 ppm are shown in red The highest value for any interval is 31277 ppm
As indicated on Plate 4-2 total chlorinated VOC concentrations were either BDL or less than 1
ppm for the majority of intervals sampled Total concentrations between 1 and 10 ppm (ie
yellow zones on Plate 4-2) were detected at two locations SB108 and SB109 Total chlorinated
VOC concentrations in the 4-6 interval at SB108 were 155 ppm At SB109 total chlorinated
VOC concentrations were between 1 and 10 ppm within the 2-4 foot interval (17 ppm) and the
14-16 foot interval (213 ppm) Total chlorinated VOC concentrations exceeded 10 ppm at two
locations SB 109 (2019 ppm in the 4-6 foot interval) and SB115 (31277 ppm in the 3-5 foot
interval) As seen on the plan view insert on Plate 4-2 SB109 and SB115 are located within
approximately 25 feet of each other in the northwestern quadrant of the Former Primary Disposal
Area The zone of highest chlorinated VOC contamination appears to be located just beneath the
fill horizon in close proximity to the groundwater surface
Trace to low-levels of PCB were also detected in both near surface samples and (at one location)
at a depth of 32 feet below the ground surface The highest concentration of any single PCB
compound was 64 parts per million in the 1-35 foot interval at SB110 Other detections
included 43 ppm (SB107 0-1 foot interval) 3 ppb (0-1 foot interval at SB109 and SB110) 28
ppm (0-1 foot interval at SB113) 23 ppm (0-1 foot interval at SB107) and 24 ppm (1-35 foot
interval at SB110) All other detections were below 15 ppm
Plate 4-3 has been prepared to illustrate the distribution of PCB compounds detected within the
Former Primary Disposal Area Plate 4-3 shows the concentration and locations for total PCB
compounds for all intervals sampled with the area
Total PCB concentrations have been grouped and color coded on Plate 4-3 as follows sample
intervals where no PCB were detected (BDL) are shown as colorless zones where total PCB were
detected at concentrations less than 1 ppm are shown in green Intervals containing between 1
and 5 ppm total PCB are yellow and intervals between 5 and 10 ppm are shown in red (the
highest value for total PCB compounds anywhere was 88 ppm)
As shown on Plate 4-3 total PCB values at the majority of locations within the Former Primary
Disposal Area are less than 1 ppm Values between 1 and 5 ppm (shown in yellow) were
detected at SB109 SB110 and SB113 These intervals all occur within four feet of the ground
surface and all are within the fill horizon The only intervals where total PCB concentrations are
between 5 and 10 ppm are the 0-1 foot interval at SB107 (66 ppm) and the 1 to 35 foot interval
5797wpdoc8galluprifinaltextmastemfhl061297 4-16 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
at SB 110 (88 ppm) There does not seem to be any spatial trend or relationship among these
detections as the detections are scattered among all quadrants of the disposal area
42 Groundwater Quality 421 Temporary Well Point Investigation
The results of the temporary well point investigation discussed in Section 24 indicated the
presence of a narrow groundwater plume (approximately 250 feet in width) of volatile organic
compounds (VOC) originating at the Former Primary Disposal Area and extending about 700 feet
in a northwesterly direction VOC were detected up to Mill Brook and at trace levels at one
location near the northern bank of the brook Plate 4-4 summarizes the VOC detections at
different locations and depths in the aquifer A summary of these field and laboratory data is
presented on Table 4-8 and Table 4-9 respectively The area extent of this VOC plume is in
excellent agreement with the groundwater flow directions measured in the northern Study Area (as
discussed in Section 422) The primary chlorinated VOC detected were 111-trichloroethane
(TCA) trichloroethene (TCE) and 12-dichloroethene (DCE) VOC concentrations within the
Former Primary Disposal Area were found to decrease significantly with depth indicating that the
source material is probably located near or above the water table Further downgradient VOC
were detected at generally lower concentrations and were present throughout the entire aquifer
thickness with no apparent depth-dependent trend Various contaminant transport mechanisms
are discussed in Section 50
In the southern portion of the Study Area low-level detections of methyl isobutyl ketone (MIBK)
were detected in samples from two microwells Also acetone and methylethyl ketone (MEK)
were detected at one location adjacent to Tarbox Road No other VOC were detected at any
location
Due to variability in the results of field VOC analyses (using a portable gas chromatograph) and
off-site laboratory analyses it was determined that the field GC results should not be relied upon
as the only source of information to evaluate either the VOC plume boundary or absolute levels of
particular constituents within the plume Rather the microwell results were subsequently used to
guide the location of monitoring wells and to evaluate relative horizontal and vertical
concentration variations within the VOC plume Water quality data from monitoring wells were
then used to confirm the microwell results and delineate plume boundaries
The results of laboratory metals analyses shown in Table 4-10 and Plate 4-5 do not indicate any
significant source areas on the Site nor are there any apparent trends in occurrence or
concentrations of metals Lead was detected at variable depths and concentrations at a total of 15
microwell locations (TW102 103 104 107 115 120 126 128 139 141 143 148 151 and
5797wpdoclaquogilluprifinaltextmlaquo8terrifhl061297 4-17 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
152) These locations represent nearly every portion of the study area With several exceptions
the majority of iiicrowell lead detections were trace to very low (ie lt 10 ugL) Exceptions
included results from single samples collected at locations TW120 (192 ugL) TW-128 (644
ugL) and TW151 (182 ugL) Although several of the locations at which lead was detected are
downgradient of former disposal areas most of the detections were at locations that are either
upgradient or a large distance (400 to 1000 feet) from former disposal areas Furthermore while
lead was detected at some downgradient locations there were other downgradient locations at
which lead was not detected at all It is also noted that lead was only detected at a concentration
of 1 ugL at the microwell (TW143) placed in the center of the Former Primary Disposal Area
and that lead was not detected at all in the two nearest downgradient (relative to the Former
Primary Disposal Area) microwell locations (TW119 and 137) Based on the lack of significant
detections of lead in most microwells on the Site and the fact that metals are typically much less
mobile than VOC the majority of these detections were not considered to be Site related and may
be attributed to an off-site source Numerous off-site activities may have resulted in lead
contaminations including most notably the observed presence of large lead-containing batteries
abandoned along the west side of the railroad bed and fire armhunting activities (as evidenced by
the large number of spent shotgun shell casings observed in the area)
422 Groundwater Monitoring Wells
The initial (Phase 1A) monitoring well network was designed to (1) confirm the findings of the
microwell survey with respect to the chlorinated VOC plume in the northern Study Area and the
two isolated MIBK detections in the southern Study Area and (2) provide hydraulic data to
determine groundwater flow directions and rates An additional objective of the network was to
evaluate potential bedrock groundwater issues related to the Former Seepage Bed which is
located in an area where the water table lies below the base of the overburden formation
Following the Phase 1A monitoring well installation and sampling program additional rounds of
groundwater samples were collected in April July November 1995 February May August
November 1996 and February 1997 under the Long-Term Monitoring Program In October
1995 additional wells were installed during the Phase IB field program to address groundwater
quality and flow directions from areas north of the site The newly installed monitoring wells
(MW117STT MW118STT MW119STT and MW102B) and the existing monitoring wells
located at the former Pervel flock plant (MW-A -B -C -2 and -3) were also included only in
the November 1995 round of groundwater sampling and were sampled only for VOC analyses
Further details of the monitoring well installation program are provided in Section 27 The
following sections present and discuss the groundwater sampling results for VOC SVOC metals
and pesticidesPCB for all nine rounds of sampling
5797wpdocsgalIuprifinaltextmlaquosteiTifhl061297 4-18 QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
4221 VOC
This section discusses the VOC data collected from groundwater monitoring wells during the nine
sampling events conducted between January 1995 and February 1997 Positive groundwater VOC
detections for the nine sampling events are shown in Tables 4-11 through 4-19 respectively VOC
data for the four 1995 events are presented graphically on Plate 4-6 and the VOC data for the
four 1996 events and the February 1997 event are presented on Plate 4-7
42211 Overburden
Northern Study Area
As shown in Plates 4-6 and 4-7 the monitoring well data for all nine sampling events generally
confirm the microwell survey results with regard to the distribution of VOC downgradient from
the Former Primary Disposal Area
The various VOC detected are grouped into chlorinated VOC (eg TCA TCE 11- and 12shy
DCE tetrachloroethene (PCE) 11-DCA 12-dichloropropane carbon tetrachloride methylene
chloride chloroform and vinyl chloride) and non-chlorinated VOC (eg ethyl benzene toluene
xylene benzene styrene and carbon disulfide) As shown in Plates 4-6 and 4-7 the distribution
of these compounds as reported for the November 1995 and February 1997 sample events
respectively has been used to delineate the horizontal boundaries of a VOC plume which
originates in the vicinity of the Former Primary Disposal Area The plume boundary as depicted
on Plates 4-6 and 4-7 is defined by the locations where any compound was detected in excess of
its respective EPA MCL during the November 1995 and February 1997 sampling rounds
Locations at which VOC were detected at levels greater than their respective MCL during at least one sampling round were MW101(STTT) MW102(STTB) MW105 (STTTB)
MW107(TT) and MW-C (located at the former Pervel flock plant facility) MW116T exceed the
MCL for PCE only and only on one occasion (January 1995 at 17 ppb) VOC in samples
collected from MW116T during the eight subsequent sampling events were all below their
respective MCL At MW101 the only compound which was detected in excess of its MCL was
PCE which was detected in the shallow well at a maximum concentration of 6 ppb in the top-ofshy
till well at concentrations ranging from 15 to 32 ppb and between 22 and 30 ppb in the till well
At MW102S compounds detected in excess of their MCLs were 11-DCE (between 3 and 19
ppb) 12-DCE (between 72 and 670 ppb) PCE (between 10 and 43 ppb) 111-TCA (one
exceedance in July 1995 at 240 ppb) TCE (between 15 and 88 ppb) and vinyl chloride (from not
detected to 86 ppb) At MW102TT compounds that exceeded their respective MCL were 11shy
DCE (from not detected to 35 ppb) 12-DCE (between 140 and 1300 ppb) PCE (above the
MCL during four of the sampling events up to 14 ppb) 111-TCA (one exceedance in August
5797wpdocsgalluprifinaltextmasterrifhl061297 4-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
1996 at 200 ppb) TCE (one exceedence in February 1997 at 7 ppb) and vinyl chloride (from not
detected to 430 ppb) MW102B and MW105S each had a one-time MCL exceedence for only
vinyl chloride both occurrences at 3 ppb (in May 1996 at MW102B and in August 1996 at
MW105S
At MW105TT six compounds have exceeded their respective MCL as follows 11-DCE (up to
32 ppb) 12-DCE (between 150 and 1100 ppb) PCE (up to 9 ppb) 111-TCA (between 37 and
390 ppb) TCE (two exceedences up to 14 ppb) and vinyl chloride (from not-detected to 710
ppb) MCL exceedences detected at MW105T are as follow 11-DCE (two exceedences both at
12 ppb) 12-DCE (between 43 and 430 ppb) 111-TCA (one exceedence 380 ppb in February
1996) TCE (one exceedence 27 ppb in November 1995) and vinyl chloride (from not detected
to 1400 ppb) The only compound that exceeded its respective MCL in MW105B is 12-DCE
(between 2 and 180 ppb) MW107TT has had MCL exceedence of the following three
compounds 11-DCE (from not detected to 16 ppb) 12-DCE (between 72 and 1100 ppb) and
vinyl chloride (between 120 and 430 ppb)
Although there is some variation in the distribution and concentration of VOC with each sample
event the plume defined by the November 1995 data set (as shown on Plate 4-6) is nearly
identical to the plume defined by the February 1997 data set (as shown on Plate 4-7) Further
discussion of VOC concentration variations with time is provided in Section 52
Typically VOC in wells located beyond the boundaries of the plume were detected at estimated
or trace to very-low concentrations and were not detected with any regularity VOC were
detected at low levels in at least two-thirds of the samples collected from the following wells
located beyond the boundaries of the plume MW103TT (12-DCE and PCE) MW108B 11shy
DCE PCE and TCA) MW116T (PCE and TCA) SW3S (12-DCE PCE and 11-DCA) and
SW3D (12-DCE TCA and 11-DCA) PCE was detected in excess of its MCL at location
MW116T (17 ppb) during the first sampling event (January 1995) but it was never detected
above 3J ppb in the eight subsequent sampling events
TCA and 12-DCE which were detected in wells at all three locations along the plume centerline
(ie MW107 MW105 and MW102) appear to be good tracers for assessing contaminant
migration away from the Former Primary Disposal Area Based on 1995 data these compounds
have been incorporated into contaminant travel-time analyses presented in Section 5 At locations
MW107 and MW105 the highest concentrations were measured in the top-of-till wells with only
low to trace levels in the shallow wells (TCA and 12-DCE concentration up to 130 ppb and
1100 ppb respectively in MW107TT and up to 390 ppb and 1100 ppb respectively in
MW105TT At location MW102 TCA and DCE were detected at similar concentrations (up to
5797wpdoc8galluprifinaltextmasterrifhl061297 4-20 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
240 and 1300 ppb respectively) in shallow and top-of-till wells For all sampling dates TCA
concentrations in the top-of-till wells along the plume centerline varied from 24 to 390 ppb and
12-DCE levels in the top-of-till wells along the plume centerline ranged from 72 to 1300 ppb
No significant reduction in TCA or 12-DCE concentrations with distance from the Former
Primary Disposal Area is apparent at locations MW107 MW105 and MW102
TCE 11-dichloroethane ethyl benzene benzene 11-DCE 12-dichloropropane PCE toluene
vinyl chloride and xylenes were also detected at each of the three plume centerline locations but
as shown in Plates 4-6 and 4-7 their concentration distributions were more sporadic and TCE
11-DCE PCE and vinyl chloride were the only compounds that exceed their respective MCL
during at least one sampling event TCE was found at concentrations up to 88 ppb (in well
MW102S) 11-DCE was found at concentrations up to 35 ppb (in well MW102TT) the
maximum PCE concentration was measured at 43 ppb (in well MW102S) and vinyl chloride was
measured as high as 1400 ppb (well MW105T) The second highest vinyl chloride value was
710 ppb (well MW105TT) and all other vinyl chloride measurements ranged from not-detected up
to 430 ppb
Wells located within the northern portion of the Site where VOC have never been detected include
MW106TT MW109B and MW110S
Based on the monitoring well and microwell results concentrations within the VOC plume appear
to be relatively evenly distributed throughout the lower three-quarters of the aquifer thickness
Throughout most of the plume area (eg MW107 MW105 and MW101) VOC levels in the
upper five to 15 feet of the aquifer are typically near the detection limit The concentration
reduction near the water table is likely associated with rainwater infiltration Evidence of
infiltration includes the consistently downward hydraulic gradients at MW107 MW108 and
MW116 At these locations the vertical hydraulic gradient is on the order of a factor of 100
greater than the horizontal hydraulic gradient within the VOC plume Location MW102 where
shallow and deep concentrations are similar in magnitude is an exception to this trend of low
concentration near the water table A plausible explanation for the observed concentrations in
MW102S is the hydraulic influence of Mill Brook which as discussed in Section 3323 causes
upward flow in the upper portion of the aquifer near the brook Upward flow near the brook and
MW102S is also supported by the upward hydraulic gradients measured between MW102S and
the stream piezometer PZ-4B
The present PCE distribution in groundwater exhibits inconsistencies with migration from the
Former Disposal Areas PCE was consistently detected at levels above the 5 ppb MCL up to 43
ppb in groundwater samples from wells MW102S MW101TT and MW101T PCE was
5797wpdocraquogalluprifinaltextmasterrifhl061297 4-21 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
measured in well MW116T at 17 ppb in the initial sampling round (January 1995) and
consistently at trace levels in subsequent sampling rounds However only trace levels of PCE
were detected at the MW105 or MW107 locations and the only occurrences of PCE at MW105
or MW107 greater than 5 ppb were three estimated detections of 6 7 and 9 ppb at MW105TT
PCE was not detected in well SW3S and was detected once at a trace level in well SW3D
Monitoring wells MW102 and MW101 are downgradient from both the Former Disposal Areas
and the former Pervel flock plant where PCE TCA and DCE groundwater contamination has
been documented (Section 52) During the November 1995 sampling event VOC detected at
MW-C (located at the former Pervel flock plant) include DCE (97 ppb) TCE (11 ppb) and PCE
(24 ppb) Based on available data MW116 is located downgradient from the former Pervel
flock plant Groundwater flow conditions in the past would need to have been different from
present conditions for MW116 to be downgradient from the Former Disposal Areas Although
the PCE detections at locations MW102 and MW101 could be attributable to historical releases
from the Former Disposal Areas the regional flow pattern and spatial distribution of PCE in
groundwater suggest that contamination from the former Pervel facility has at a minimum
contributed to VOC (PCE TCA and DCE) contamination of these locations Further discussion
of the PCE detections and other VOC concentration variations is provided in Section 52
Southern Study Area
In the southern portion of the Study Area groundwater samples were collected from overburden
monitoring wells at five locations SW9 MW112 MW113 MW114 and MW115 As shown
on Plates 4-6 4-7 no VOC were detected in any of the wells As a result of the consistent lack of
detections wells at these locations were dropped from the Long-Term Monitoring Program (with
EPA approval) after three sampling events These data are consistent with the microwell survey
results but do not support the low-level detections of methyl isobutyl ketone in the two microwell
samples (Section 421)
42212 Bedrock
During the RI VOC were detected in bedrock wells at the following locations MW102 MW105
MW107 MW108 and SW-10 Since the only VOC detected at SW-10 was TCA at an estimated
trace concentration (1J ppb) during the January event and TCA was not detected in SW-10
during the subsequent two sampling events this well was eventually dropped from the Long Term
Monitoring Program (with EPA approval) following the July event All other bedrock wells in
the southern portion of the Study Area (MW111 MW112 MW113 SW-12) were likewise
dropped from the monitoring program At location MW108B estimated concentrations of PCE
(3J ppb) and TCA (up to 9J ppb) were detected during the January and April sampling events
therefore samples collected from this well during the July and November events were submitted
5797wpdocsgalluprifinaltextmasterriftil061297 4-22 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
for VOC analyses using EPA Method 5242 which hs lower detection limits than the TCL
Methods The results of the July and November events for MW108B indicate that other VOC are
present but generally at trace to very low concentrations The highest detections of TCA and
PCE at this location were 92 and an estimated 5 ppb respectively Other VOC detected at
MW108 were carbon tetrachloride (12 ppb) 11-DCA (1 ppb) 12-DCA (015J ppb) 11-DCE
(13 ppb) and xylene (01J ppb)
The only VOC detected at MW107B was TCA which was measured during three events at
concentrations ranging between 059J and 2 ppb Over the nine sampling events VOC detected
at MW105B included 11-DCA (BDL to 9J ppb) 11-DCE (BDL-4J ppb) 12-DCE (11-140J
ppb) 12-dichloropropane (2J ppb in January 1995 and February 1996 only) TCA (2J-12 ppb)
and TCE (BDL-3J ppb)
MW102B was installed during the Phase IB investigation and therefore was only sampled during
five events VOC detected at MW102B were typically at estimated trace concentrations and
only PCE was detected in every round (2J to 4J ppb) The only MCL exceedence was a single
estimated detection of vinyl chloride (3J ppb)
In general VOC detected in bedrock wells were also detected in overburden wells at the same
locations although the concentrations seen in the bedrock wells are significantly lower typically
by an order of magnitude relative to concentrations seen in the top-of-till wells The only
notable exception to this trend is at location MW108 where VOC were not typically detected in
the overburden wells (with the exception of an estimated 2J ppb of DCE detected once in
MW108S and once in MW108TT) At MW105 and MW107 VOC concentrations seen in the till
wells are similar to the low concentrations detected in wells screened in the underlying bedrock
The low VOC levels detected in bedrock wells located in the northern portion of the Study Area
demonstrate that bedrock is not a preferred pathway for contaminant migration This conclusion
is supported by the groundwater hydraulics data outlined in Section 3323 which demonstrate
that the average hydraulic conductivity of the bedrock is more than a factor of 200 less than the
overburden hydraulic conductivity In spite of the upward hydraulic gradient from bedrock to
overburden (factor of ten to 100 larger than the horizontal hydraulic gradient within the VOC
plume) which was found to exist throughout the Study Area vertical (transverse) dispersion
caused by flow in the bedrock fracture system has apparently caused VOC to migrate a limited
distance into the bedrock
5797wpdocsgalIuprifinaltextmasterrifhl061297 4-23 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4222 Semivolatile Organic Compounds
Tables 4-20 through 4-28 present the analytical results for SVOC in groundwater for the nine
sampling events Overall SVOC were detected infrequently and generally at only trace levels
Naphthalene 2-methylphenol and 12-dichlorobenzene were the most frequently detected SVOC
compounds in groundwater samples Naphthalene was detected during every sampling event
generally at MW105 MW107 and MW102 locations within the top-of-till wells and occasionally
also within till at well MW105T The highest naphthalene measurement was 10 ppb in
MW105TT 2-methylphenol was also detected during every sampling event always in well
MW107TT and with lesser frequency in MW105TT MW105T and MW102TT the highest
concentration detected was 3 ppb In eight of the nine sampling events 12-dichlorobenzene was
detected in at least one of the following wells MW102TT MW105TT MW105T MW107TT
and the maximum concentration measured was 4 ppb Maximum bis(2-ethylhexyl)phthalate was
detected in at least one well during six of the nine sampling events the concentrations ranged
from 04J to 35 ppb The locations of the bis(2-ethylhexyl)phthalate detections were sporadic it
was detected three times at MW108S twice at MW014S and MW116T and only once at eleven
wellsTrace levels of the following other compounds were detected during various sampling
events acenaphthene (03J ppb) butylbenzylphthlate (U ppb) di-n-butylphthlate (04J ppb) 4shy
chloroaniline (2J ppb) 24-dichlorophenol (U ppb) fluorene (06J ppb) 4-chloro-3-methylphenol
(2J ppb) phenanthrene (02J ppb) 4-bromophenyl-phenylether (2J ppb) n-nitroso-di-nshy
propylamine (9J ppb) 14-dichlorobenzene (up to 2J ppb) diethylphthlate (up to 04J ppb) 24shy
dimethylphenol (up to 8J ppb) di-n-octylphthlate (up to 46B ppb) 4 methylphenol (2J ppb) and
phenol (up to 4J ppb) The majority of these compounds occur in either the till or top-of-till
wells located within the VOC plume shown on Plates 4-6 and 4-7 (eg MW102 MW105 and
MW107) although there were infrequent detections of compounds at MW103 MW104 MW106
MW108 MW109 SW3D MW112 and MW116 as well
4223 Pesticides and PCB
The only detection of PCB in groundwater was during the April event when Aroclor 1242 was
detected in MW103S and TT at estimated concentrations of 042J and 018J ppb respectively
Estimated low levels of a few pesticides were detected in a small number of groundwater samples
Endosulfan I was detected once (002J ppb in MW107S during April 1995) Endrin was detected
once (00031 JP in MW109S during February 1996) methoxychlor was detected once (012J in
MW107S during February 1997) alpha-BHC was detected once in four wells (during February
1997 up to 0011 JP ppb) beta-BHC was detected twice up to 004J ppb (at MW107S in July
1995 and at MW107TT in February 1996) and gamma-BHC was detected in three samples up to
001JP (at MW105B and MW116S during November 1995 and at MW102S during August 1996)
All positive detections for pesticide and PCB compounds are shown on Table 4-29 (Note Table
5797wpdocraquogalluprifinflltextmasterriftil061297 4-24 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
4-29 only includes those sample IDs where a pesticide or PCB compound has ever been detected)
4224 Inorganics
Tables 4-30 through 4-38 present the analytical results for total (and where applicable dissolved)
metals in groundwater (During sampling low flow purging techniques were used to minimize
disturbance of formation water In cases where turbidity levels less than 5 NTU could be
achieved samples for both total and dissolved metals were collected Otherwise samples were submitted for total metals analyses only) Cyanide has not been detected in any groundwater
sample Metals were generally not detected in groundwater above applicable MCLs and metals
in groundwater samples across the Study Area were similar in concentration to metals detected in
designated groundwater background samples
Analytical results of a duplicate sample collected from MW107S during August 1996 had
anomalously high values Between January 1995 and August 1996 nine samples (seven rounds
plus two duplicate samples) were collected from this well and analyzed for total metals Only one
sample contained inorganic compounds in excess of EPA MCLs or Connecticut Remediation
Standards This sample which was the duplicate sample collected in August 1996 contained
elevated concentrations of aluminum chromium cobalt magnesium manganese and nickel In
order to evaluate the significance of this particular data set a statistical analysis for the
identification of outliers was performed following the procedures described in the EPA guidance
document Statistical Analysis of Ground Water Monitoring Data at RCRA Facilities (EPA530shy
SW089-026) For this analysis a test statistic (TJ was generated (using the average maximum
and standard deviation) from the nine samples for each inorganic analyte detected in this well If
the test statistic was greater than a critical value (1764) representing a 995 level of
significance then there is a strong likelihood that the maximum value for each data set is a statistical outlier If a given analyte was not detected in a given sample the detection limit2 was
used for statistical calculations
Maximum concentrations for nine of the thirteen analytes that have been detected in this well
were found to be statistical outliers Six of the statistical outliers were found in the MW107S
duplicate sample collected in August 1996 which suggests that the inorganic data from this
particular sample are not representative of groundwater quality in the immediate vicinity of this
well Although a specific reason why this sample contained such anomalously high levels is not
apparent it seems clear that this sample is not representative of the actual groundwater metal
concentrations at this location This is supported by the fact that the other sample from this well
on this date has metals concentrations consistent with previous sampling rounds Therefore the
metals data from this duplicate sample have been presented in this Report but are considered not
to be valid
5797wpdocBgalluprifinaltextmasterrifhl061297 4-25 QSTT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4225 DioxinsFurans and Additional Appendix IX Parameters
During the January 1995 sampling event samples from three locations (MW102TT MW106TT
and MW116T) were submitted for laboratory analysis for full Appendix IX parameters During
the April 1995 sampling event samples from MW105TT were also submitted for full Appendix IX
analyses The results for the VOC SVOC PesticidePCB and metals analyses for these samples
have been included in the appropriate tables as discussed in previous sections The results of
Appendix IX analyses that are not common to target analyte and target compound lists
(TALTCL) are discussed below Analyte groups specific to the Appendix IX lists include
herbicides (EPA Method 8150) volatiles by direct aqueous injection (EPA method modified
8015) Phenols (EPA Method 4202) Sulfide (EPA Method 3761) Organophosphorus Pesticides
(EPA Method 8141) PesticidesPCB by EPA Method 8080 and DioxinsFurans
The only detections for any of the analyte classes specific to Appendix IX compounds during the
January 1995 event were phenols (MW102TT at 7 ppb and MW116T at 15J ppb) During the
April 1995 event the dioxinfuran compounds HxCDD (total) and TCDF (total) were detected at
MW105TT at concentrations of 705 and 193 ngL (part per trillion)
423 Residential Wells
Residential wells were sampled during the Phase 1A investigation (January 1995) and again
during July 1995 February 1996 and August 1996 under the Long-Term Monitoring Program
4231 Volatile Organic Compounds
Tables 4-39 through 4-42 present the results of VOC analyses for residential well samples The
locations of these wells are shown on Plate 2-5 TCA was detected at DW114 during all four
sampling events and was also detected once at DW111 and DW113 the concentration ranged
from 018J to 066 ppb Chloroform was detected during three of the sampling events twice at
DW102 and once at DW104 and DW107 the maximum concentration detected was 19 ppb The
following compounds were also detected at low levels once bromodichloromethane (2 ppb at
DW107) dibromochloromethane (084J ppb) PCE (016J ppb at DW114) chloromethane (082J
ppb at DW103) and at DW111 ethylbenzene (025J ppb) toluene (012J ppb) and xylenes
(0 U) Since these locations are not downgradient with respect to the Site the occurrence of
these compounds in these wells are not likely to be Site related
4232 Semivolatile Organic Compounds
No SVOC were detected in any residential well sample during any of the four sampling events
5797wpdocsgalIuprifinaltextmasterrifhl061297 4-26 QT Environmental
Gallups Quarry Superjund Project - Remedial Investigation
4233 Pesticides and PCS
Tables 4-43 through 4-46 present the analytical results of pesticide and PCB analyses for
residential well samples Alpha-chlordane and gamma-chlordane were both detected in all four samples collected from DW105 and in three of the samples collected from DW106 The
maximum concentrations measured were 0095 ppb for alph-chlordane and 004 ppb for gamma-chlordane During August 1996 44-DDE and heptachlor epoxide were both also detected at
DW105 and DW106 (001J ppb for 44-DCE and up to 002J ppb for heptachlor epoxideNo PCB compounds were detected in any residential well The fact that DW105 and DW106 are not
downgradient relative to the site indicate that these compounds are likely attributable to the off-site use of these pesticides and are not site-related
4234 Inorganics
Tables 4-47 through 4-50 present the analytical results of metals and cyanide analyses for
residential well samples for the four sampling events Heavy metals were generally not detected
or were detected at trace levels Alkaline earth metals (eg Ca Mg K) were detected at levels
not unexpected for natural groundwater in the region
43 Surface Water Sediment and Wetland Soils Surface water sediment and wetland soils upstream adjacent to and downstream of the Site
were sampled and analyzed during the Phase 1A investigation to assess the potential if any for
transport of constituents of concern from the Site Sample locations are shown on Plate 2-6 Sediment was collected from one additional location (UB-6A) during the April 1995 sampling round As part of the Long Term Monitoring Program additional rounds of surface water
samples were collected during the April and November 1995 and May and November 1996
sampling events The samples were analyzed for VOC SVOC metalscyanide and pesticidePCB with the exception of the November 1996 samples which with EPA approval
were analyzed only for VOC and metals It is noted that following the Phase 1A sampling event
(September 1994) stations UB-1 UB-2 and UB-3 were eliminated from the Long Term
Monitoring Program (with EPA approval) as these locations are upstream of station UB-4 which
is also upstream from the Site Also station UB-6 (which was located on a tributary to Mill
Brook and sampled during the Phase 1A program) was replaced by station UB-6A (located within
Mill Brook) during the four Long-Term Monitoring events
431 Surface Water During September 1994 water quality indicators (pH dissolved oxygen temperature
conductivity turbidity) were measured in the field at eleven surface water sampling stations six
in Upper Mill Brook two in Lower Mill Brook (below the confluence with Fry Brook) one in
Fry Brook and two in Packers Pond The remaining six locations were dry at the time of
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 4-27 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
sampling As presented in Table 4-51 the water quality of the watershed as judged by both field
measurements and wet chemistry (TSS alkalinity hardness) was good to excellent It may
however be important to note that all of the samples were taken under fair weather conditions so
the influence of potential non-point sources during storm events cannot be assessed with this data
set Table 4-51 presents a qualitative assessment (eg slight moderate obvious) of potential
Local Non-Point Source Pollution As most sampling stations are either adjacent to or
downstream from developed (eg streets highways residences agricultural or industrial
property) the immediate andor cumulative impact of storm events cannot be evaluated in this
report During the four Long-Term Monitoring surface water sampling events field parameters
were again measured The results of these sampling events are shown in Table 4-52
During the September 1994 Phase 1A investigation surface water temperature ranged from 60 degF
(UB1 UB2) to 70degF (PP3) Surface water at most locations contained adequate concentrations of
dissolved oxygen ranging from 335 (UB2) to 1035 (UB8) mg1 but were slightly acidic with
pH varying from 528 (UB1) to 572 (PP3) Dissolved solids measured indirectly as specific
conductivity varied from 120 (UB1) to 710 (PP3) imhoscm
During the four Long-Term Monitoring sampling events surface water temperatures ranged from
526 to 617degF in April 1995 and 420 to 508degF in May 1996 to seasonally lower temperatures
of 396 to 453degF in November 1995 and 374 to 400degF in November 1996 The dissolved
oxygen concentrations were generally similar between the various sampling events ranging from
a low of 335 mg1 (at UB-2 in September 1994) to a high of 1030 mg1 (at PP-1 in November
1996) pH measurements indicated slightly acidic water with the following ranges 514 to 605
in April 1995 574 to 667 in November 1995 615 to 701 in May 1996 and 472 to 620 in
November 1996 Conductivity values were in the same general range between the different
sampling events with the lowest measurement of 1 anhoscm at PP-1 in November 1996 and the
highest measurement of 523 xmhoscm at UB-5 in April 1995
Based on laboratory results surface water in the area is fairly soft ranging in hardness (as
CaCO3) from 12 (TR-1 during April 1995) to 179 (UB2 during September 1994) mg1 and in
alkalinity from lt 1 (UBS during April 1995) to 67 (UB2 during September 1994) mg1 Total
dissolved solids and total organic carbon were below 200 ppm and 15 ppm respectively at nearly
every station during all five sample events A total of 58 total suspended solids analyses were
performed on samples collected during the five sampling events Most of the results were below
the detection limit and only 10 samples exceeded 10 mg1 The highest concentrations were
detected at UB-5 (between 82 and 2470 mg1 in the four samples collected at that location) and at
PP-1 (between 87 and 1500 mg1 in the three samples collected at that location)
5797wpdocraquogalluprifinaltextmasterrifhl061297 4-28 QST Environmental
Gallups Quarry Supcrjund Project - Remedial Investigation
4311 VOC- Surface Water
Data presenting he concentrations of various VOC for each individual surface water location are
presented in Table 4-53 through 4-57 for the September 1994 April and November 1995 and
May and November 1996 sampling events respectively VOC were not detected in the upstream
portion of Mill Brook Six VOC were detected at least once in the five rounds of surface water
samples collected from 11 locations The most consistent detections were 12-DCE and PCE in
Fry Brook sample FB-1 12-DCE was detected every round at FB-1 and occasionally at four
other locations up to 8J ppb and PCE was detected every round at FB-1 and occasionally at
three other locations up to 11 ppb Sample location FB-1 is approximately 1500 feet upstream
of the confluence of Fry Brook and Mill Brook the detections at FB-1 are not likely to be Site-
related and may result from nearby industrial activities The other detections of PCE and DCE
were at trace concentrations at locations below the confluence of Fry and Mill Brooks In
addition TCA was detected once at UB-10 at 3J ppb TCE was detected twice at FB-1 and once
at UB-9 up to 2 ppb carbon disulfide was detected in seven samples representing six locations
up to 20 ppb and toluene was detected twice at upgradient location UB-5 at 1J ppb All of the
VOC concentrations detected are well below those expected to cause adverse effects in fish or
wildlife (USEPA 1986)
4312 SVOC - Surface Water
During the September 1994 sampling event only low levels of one SVOC compound 4shy
methylphenol (28 ppb PP3 1 ppb UB2) were detected in surface water samples The locations
where SVOC were detected are far upstream (UB 2) and downstream (Packer Pond) locations and
are unlikely to have been impacted by the Site During the April 1995 sampling event the only
SVOC detected were trace levels of fluoranthene (04J ppb) phenanthrene (03J ppb) and pyrene
(04J ppb) all of which were detected at UB-5 which is upstream from the site There were no
SVOC detected in any surface water samples during the November 1995 event During the May
1996 sampling event bis(2-ethylhexyl)phthalate was detected in four samples at concentrations
ranging from 05J ppb to 140J ppb The locations of the detections are upgradient of the Site
(UB-5 and UB-8) and downgradient of the Site (LB-2 and PP-1) The sample from LB-2 also had
an estimated low level of di-n-octylphthalate (7J ppb) Table 4-58 presents all of the SVOc
detections in surface water samples (Note Table 4-58 only includes those sample IDs where a
SVOC has ever been detected)
4313 PesticidesPCBs - Surface Water
No pesticides or PCB compounds were detected in any surface water samples
5797wpdocsgalluprifinaltextmraquosterrifhl061297 4-29 Q5T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4314 Total and Dissolved Metals - Surface Water
Because of the ubiquity of naturally occurring metals in surface waters metals results are more
easily interpreted by generating descriptive statistics Descriptive statistics for metals measured in
surface water during 1994 and 1995 are presented in Appendix S Data presenting total and
dissolved metals concentrations for each individual sampling location during all five sampling
events are presented in Tables 4-59 through 4-65
Total Metals
Cadmium silver and thallium were not detected in any samples during the five sampling events
Other constituents detected in only one or two samples during each event include arsenic (up to
296J ppb) beryllium (once at 26B ppb) chromium (up to 764 ppb) cobalt (up to 26 IB ppb)
copper (up to 165 ppb) cyanide (up to 466 ppb) mercury (once at 018B ppb) nickel (up to
821 ppb) selenium (181J ppb at PP3) silver (once at 3J ppb) and vanadium (133 ppb) With
die exception of station UB2 during the September 1994 sampling event UB-5 during die April
1995 May 1996 and November 1996 events and PP-1 during the May and November 1996 events the remaining metals (aluminum barium calcium iron lead magnesium manganese
potassium sodium and zinc) were detected at concentrations that are expected in natural waters
(Hem 1989)
Dissolved Metals
Beryllium cadmium cobalt mercury selenium and thallium were not detected in any sample
Constituents detected infrequently and at low concentrations include antimony arsenic
chromium nickel silver vanadium and zinc Copper was detected at several locations upstream
and downstream from the site at concentrations ranging from 25 to 208B ppb although there
was no pattern in its occurrence or concentration Lead was detected at least once at each of the
sampling locations ranging in concentration from 1J ppb to 188 ppb The occurrences of lead
did not show a pattern die highest measurements were as follows 11 ppb at PP-3 in September
1994 188 ppb at UB-9 in April 1995 16J ppb at UB-4 in November 1995 56J ppb at UB-5 in
May 1996 and 91J ppb at UB-5 in November 1996 Locations UB-4 and UB-5 are upgradient
of the Site The lead detections in Packer Pond samples likely results from non-point sources to
Packers Pond The remaining metals (aluminum barium calcium copper iron lead
magnesium manganese potassium and sodium) were detected at concentrations that are expected
in natural waters (Hem 1989)
Concentrations of total and dissolved metals in surface waters were generally detected infrequently
and at concentrations below ambient water quality criteria ie those that would not pose a threat
5797wpdocsgalluprifinraquoItextmaBterriftil061297 4-30 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
to fish or wildlife (EPA 1986) Heavy metals such as copper and lead generally considered
harmful to aquatic life were detected at locations (Fry Brook and Packers Pond) that are not
likely to be impacted by the Site One location UB-5 (which was dry during September 1994)
contained elevated levels of most metals during the 1995 and 1996 sampling events This sample
station is located well upstream from the site on a tributary to Mill Brook which originates in a
small pond adjacent to Interstate 395 in a highly commercialized area
432 Sediment
A total of seventeen sediment samples were collected during the Phase 1A field survey
(September 1994) six of which were dry at the time The composition of the sediment samples
varied from deep muck (eg LB-02) to a firm sandy substrate (eg UBS) The total organic
carbon (TOC) content of the sediments (presented in Table 4-30) ranged from 075 (UB4) to 16
(PP1) percent with an average of 57 percent
4321 Inorganics - Sediment
Because of the ubiquity of naturally occurring metals in sediment these constituents are more
easily interpreted by generating descriptive statistics which are presented for each individual
metal in Appendix S Data presented for metals at each individual sampling location are
presented in Table 4-66
Antimony and thallium were not detected above the detection limit Beryllium cadmium
chromium cyanide mercury selenium and silver were detected infrequently and when detected
had concentrations close to the respective detection limit andor were detected at remote upstream
or downstream locations With the exception of maximum concentrations detected at PP3 (a
location at Packer Pond which receives stormwater runoff from Lillibridge Road) the remaining metals (aluminum arsenic barium calcium cobalt copper iron lead magnesium manganese
nickel potassium sodium vanadium and zinc) were detected at concentrations within the ranges
expected in naturally occurring soils or sediments (Beyer 1990 Fitchko 1989 Shacklette and
Boerngen 1984)
4322 VOC - Sediment
Analytical results for concentrations of VOC in sediment samples are presented in Table 4-41
VOC were generally detected infrequently and at relatively low concentrations in sediments
Ketones (acetone and 2-butanone) were detected at remote upstream (UB1 UB6) and downstream
(PP1 PP2 PP3) locations One or more of the compounds toluene trichloroethene methylene
chloride and xylenes were detected at trace levels at upstream locations north and east of the Site
(UB-3 UB-5 UB-6 UB-7 and UB-9) Xylenes were detected at a concentration of 31 pm in the
sediment sample from Fry Brook (FB-1) Only toluene at trace level of 0009J ppm was
5797wpdocsgalluprifinaltextma8terrifhl061297 4-31 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
detected in the sediment sample from UB-10 located in Mill Brook near the downgradient edge
of the Gallups plume No VOC were detected in sediment samples from downstream locations
LB-1 and LB-2
4323 SVOC - Sediment
As shown on Table 4-68 the primary SVOC constituents detected were PAH ranging from non-
detect (~ 03 ppm) to 15 ppm No apparent concentration gradient could be determined with
respect to location (eg upstream to downstream) The detections of PAH likely reflect non-
point contributions from local sources such as stormwater runoff from the railroad tracks and
nearby roads
Elevated concentrations of bis(2-ethylhexyl)phthalate were measured in Fry Brook (1300 ppm
FBI) and lower Mill Brook (64 ppm LB2) below the confluence of these two streams The
source appears to originate in Fry Brook
4324 PesticidesPCB - Sediment
Analytical results for pesticides and PCB are provided on Table 4-69 PCB compounds
(Arochlor-1242 -1254 and -1260) were detected in sediment samples from only three locations
all upstream (FB-1 at 019 ppm UB-8 at 0023J ppm and UB-7 at 00064J ppm)
Organochlorine pesticide compounds were also detected infrequently with no apparent trend with
regard to location or source The concentrations in sediment ranged from non-detect (~ 1-3 ppb)
to 39 ppb (methoxychlor at PP1) and their occurrence likely reflects residues of persistent
compounds that were routinely used for insect control before being banned from commercial
production
433 Wetland Soils
A total of 10 wetland soil samples were collected during the field survey most of which were
close to the water table at the time of collection The wetland sampling locations are shown on
Plates 2-6 and 3-14 The total organic carbon content (mgkg) of the wetland soils is as follows
QW1 (160000) QW2 (54600) QW3 (37200) QW4 (35200) QW5 (23900) QW6 (25600)
QW7 (gt 160000) QW8 (gt 160000) QW9 (33600) and QW10 (42600)
4331 Inorganics - Wetland Soils
Because of the ubiquity of naturally-occurring metals in wetland soils these constituents are more
easily interpreted by generating descriptive statistics which are presented for each individual
metal in Appendix S Analytical results for metals at each individual sampling location are
presented in Table 4-66
5797wpdocsgalluprifinaltextmasterrifhl061297 4-32 QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
Cadmium and cyanide were not detected in any sample Antimony arsenic beryllium cobalt
mercury selenium silver and thallium were detected infrequently and at trace levels at or below
the detection limit None of the remaining metals (aluminum barium calcium chromium
copper iron lead magnesium manganese nickel potassium sodium vanadium and zinc)
exceeded normal ranges expected for naturally occurring soils (Beyer 1990 Fitchko 1989
Shacklette and Boerngen 1984)
4332 VOC - Wetland Soils
Analytical results for VOC in wetland soils are provided on Table 4-67 VOC including acetone
2-butanone TCE and carbon disulfide were detected infrequently and at low concentrations
Acetone concentrations ranged from non-detect to 056 ppm (QW8) and 2-butanone concentrations
ranged from 0004 ppm (QW10) to 0067 ppm (QW8) QW8 is located in a remote wooded
location approximately 2000 feet west of the Site QW10 is located a few hundred feet west of
the southern portion of the Site
Acetone and 2-butanone were also detected at lower concentrations (015 and 0033 ppm
respectively) at location QW-1 several hundred feet southeast of the Former Primary Disposal Area A trace level of TCE (0004J ppm) was detected in wetlands soil sample QW-2 collected
approximately 50 feet east of the Former Primary Disposal Area This detection may be related
to the Former Primary Disposal Area since TCE has been detected in this area Based on the
topography however surface water runoff from the former disposal area is unlikely to impact the
wetland No other wetland soil samples had concentrations detected above the instrument
detection limit
Although the source of these VOC is unknown acetone 2-butanone and carbon disulfide are all
commonly used in the laboratory and may have been introduced during post-processing sampling
Some of these compounds are organic solvents that are (or were ) commonly used in many
household (eg spot removers paint strippers aerosols) commercial (eg pesticide
formulations inks and dyes) and industrial (eg degreasers) products Their presence in
wetlands soils samples at low concentrations may be the result of localized human activity in the
area
4333 SVOC - Wetland Soils
Analytical results for SVOC in wetland soils are provided on Table 4-68 The primary
constituents detected were the phthalate esters and PAH PAH were detected infrequently at
generally below 01 ppm Phthalate esters were also detected infrequently ranging from non-
detect to 22 ppm (QW8) The presence of these compounds is likely to be associated with
periodic or seasonal flooding of wetlands as the wetland sampling locations are remote and
5797wpdocsgpluprifinaltextma8terrifhl061297 4-33 QST Environmental
Gallups Quarry Superjimd Project - Remedial Investigation
generally inaccessible except on foot Since these compounds are relatively immobile except in
surface water or as airborne particulates these compounds may have originated from non-point
sources such as the railroad line or runoff from nearby highways
4334 PesticidesPCB - Wetland Soils
Analytical results for pesticides and PCB are provided on Table 4-69 PCB compounds
(Arochlor-1242 -1254 and -1260) were detected infrequently and at low concentrations
The presence of trace levels of PCB compounds in wetland soil samples QW-1 QW-2 QW-3
and QW-4 may be Site-related however PCBs are ubiquitous environmental contaminants that
were widely used in industry and may thus be present in soils as a result of past activities at
surrounding industries Other sources of input into the local environment might include
atmospheric deposition transport from upstream sources and deposition following flood events
Organochlorine pesticide compounds were also detected infrequently with no apparent trend with
regard to location or source The concentrations in wetland soils ranged from non-detect to 0016
ppm (44-DDE at QW1) and their occurrence likely reflects residues of persistent compounds
that were routinely used for insect control before being banned from commercial production
44 Air Quality 441 Baseline Air Quality Survey
Ambient air quality was determined prior to the start of Phase 1A intrusive investigations to
establish a baseline for air quality For the baseline survey air quality in the breathing zone
(between approximately three and six feet above the ground surface) was determined based on
measurements of total VOC (using a PID equipped with an 117 eV lamp) and respirable dust
(using a aerosol meter) at eight locations across the Site These eight stations were located at
each of the three known Former Disposal Areas and at upwind and downwind locations along the
perimeter of the Site The locations of the eight baseline air monitoring stations (AM1-AM8) are
shown on Plate 2-1 During the baseline survey no VOC readings were detected above the EPA
approved action level of 1 ppm at any of the eight monitoring locations Also no respirable dust
readings greater than the EPA-approved action level of 005 mgm3 were recorded during the
baseline survey at any of the monitoring stations
442 Perimeter Air Monitoring
Throughout the duration of the Phase 1A field investigations ambient air quality was monitored
on a weekly basis at the eight stations for the same parameters described above In addition to
the eight air monitoring stations continuous air monitoring was performed at each discrete
investigation area (eg each microwell soil boring etc) in the workers breathing zone and at the
5797wpdocsgaIIuprifinaltextmasterrifhl061297 4-34 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
perimeter of each task specific exclusion zone Air monitoring in the work zones was augmented
with instruments to measure hydrogen cyanide and lower explosion levels Also compound
specific calorimetric equipment (eg Draeger tubes) were used to compliment total VOC
measurements recorded with a PID
No readings above ihe EPA-approved action levels were recorded at the perimeter of the Site
throughout the entire duration of the Phase 1A investigation Elevated worker breathing zone
readings for total VOC were recorded during two of the four soil borings performed within the
Former Primary Disposal Area (SB109 and SB110) Varying but sustained elevated VOC
readings in the workers breathing zone during these two soil borings required the use of OSHA
Level C protection equipment These VOC vapors appeared to dissipate rapidly as no elevated
readings were recorded at the downward perimeter of the exclusion zone
Based on the baseline and periodic air monitoring performed during the investigation undisturbed
ambient air quality in the vicinity of the Site does not appear to have been impacted by former
disposal practices at the Site To confirm this compound specific air monitoring was performed
during the Phase IB investigation
As part of the Phase IB investigation quantitative air monitoring was performed in the vicinity of
the Former Primary Disposal Area The following compounds were detected in shallow soil
during the Phase 1A investigation and therefore were the target analytes for the air monitoring
performed during the Phase IB investigation toluene ethyl benzene total xylenes
tetrachloroethene and PCBs Data from the Phase IB investigation indicate that none of these
compounds were present at any of the air sampling locations for the duration (approximately eight
hours) of the sampling event The laboratory results of these analyses are presented in Appendix
T
45 Potential Sensitive Human Receptors The survey was used to identify any water supply wells schools nursing homes and day care
facilities including in-home day cares within a one-mile radius of the Site
Water Supplies
There are three community water companies serving portions of the Plainfield area within a one-
mile radius of the Site the Gallup Water Company Brookside Water Company and Glen Acres
Water Company The Gallup Water Company operates two wells located in downtown
Plainfield approximately 4000 feet north of the Site The Gallup Water Company presently
services approximately 700 households and three schools (Plainfield Middle School Plainfield
5797wpdocsgalluprifinaltextmlaquoraquoterriltinl061297 4-35 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Central and St Johns) The Brookside Water Company operates two wells located east of 1-395
on the corner of Dow Road and Colonial Road approximately 4000 feet northeast of the Site
The Brookside Water Company presently services approximately 225 homes The water service
lines for the Gallup and Brookside Water Companies are interconnected allowing mixing of the
waters The Glen Acres Water Company has two wells located approximately 2200 feet west of
the Site and services approximately 36 homes The majority of the area west south and east of
the Site and some properties north of the Site rely on individual private wells for their water
supply
One school is located within a one-mile radius of the Site This is the St John Building located
approximately 5200 feet north of the Site This school served students in grades Kindergarten
through eighth grade until 1995 after which the school operates only as a pre-school This
facility is serviced by the Gallup Water Company
Nursing Homes and Elderly Housing
One nursing home and one elderly housing facility are located within one mile of the Site The
Villa Maria Convalescent Home is located approximately 5000 feet north of the Site and is
served by the Gallup Water Company Lawton House Elderly Housing Apartments is located
approximately 4800 feet north of the Site and is also served by the Gallup Water Company
Day Care Facilities
There are eight in-home child day care facilities within a one-mile radius of the Site The
operators and locations are listed on Table 4-70 Only one of these facilities is serviced by a
private supply well That facility located at 134 Lathrop Road is located approximately 3500
feet southeast (upgradient) of the Site
5797wpdoc8galluprifinaltextmasterrifnl061297 4-36 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
50 Contaminant Fate and Transport
This section discusses the environmental fate and transport parameters associated with the
compounds detected during the Remedial Investigation Section 51 details the theoretical basis
for the evaluation of fate and transport characteristics In Section 52 Site-specific fate and
transport parameter values are presented and VOC migration rates and concentration variations
are discussed
51 Theory Migration persistence and relative distribution of compounds between air water and soil depend
on both hydrogeologic and compound-specific parameters The following discussion addresses
each of these parameters as they may affect behavior of compounds within the Study Area
511 Advection by Groundwater Flow
Within a porous medium (soil) the advection rate of dissolved or aqueous-phase compounds
under transient conditions is based on Darcys law (Bear 1979)
where
v= average pore velocity (lengthtime)
K= hydraulic conductivity (lengthtime)
i= hydraulic gradient (lengthlength or dimensionless) which equals
the piezometric head difference between two points on a
groundwater pathline divided by the distance between the two
points
n= effective or drainable porosity (volume of voidstotal soil volume)
of the soil approximately equal to the specific yield
Rj= retardation factor (R gt_ 1) a dimensionless parameter that
represents the ratio of groundwater pore velocity to the actual
advection rate in a sorbing (onto immobile soil grains) porous
medium under transient concentration conditions
5797wpdoc8glaquolluprifinaltextmasterriftil061297 5-1 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
5111 Sorption
The retardation factor Rj represents the attenuation of a plumes frontal advancement due to
sorption ie temporary storage on soil grains Examples of analyses for which retardation
must be considered include (1) calculation of the time required for contamination to reach a given
downgradient location and (2) determination of the time required to remediate a contaminated
aquifer The retardation factor is defined by the following relationship (Freeze and Cherry
1979)
where pb is the bulk dry density of the soil (massvolume) n is the effective porosity of the soil
(volume of voidstotal soil volume) and K^ is the soil-water partition coefficient (volumemass)
often referred to as the distribution coefficient
The soil-water partition coefficient is the relative magnitude of the chemical concentration on solid
particles and in pore water for a particular soil (Lyman et al 1982)
C = AT C
where
C = concentration of the compound sorbed to the solid phase of the soil (mass
chemicalbulk dry mass soil) and
Q = concentration of the compound in the pore water of the soil (massvolume)
In this expression it is implicitly assumed that an equilibrium exists between the solid and water
phases and that the sorption process is linear (Freundlich isotherm with exponent equal to unity)
over the range of concentrations considered
For non-ionic organic compounds such as VOC Kj can be estimated from the measured fraction
of organic carbon naturally occurring in the soil fx (grams organic carbongram dry soil) and
the organic carbon sorption coefficient K^ (Tinsley 1979) as long as f^ gt_ 0001
5797wpdocsgalluprifinaltextmasterrifnl061297 5-2 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Values of K for many common organic compounds are available in the literature K is also
related to the octanol-water partition coefficient K^ for which a large data base is also available
(eg Hansch and Leo 1979) For fine-grained soil particles K and K^ can be related as
follows (Karickhoff et al 1979)
Kx = 063
Chemical-specific relationships between K and K^ also exist for several VOC (eg Lyman et
al 1982) K values for VOC in the Study Area are presented in Table 5-1
5112 Transport by Dissolved Organic Carbon
For certain families of organic compounds the presence of dissolved organic carbon (DOC) in
groundwater can partially reverse the sorption process to soil particles and release sorbed
constituents to groundwater As a result the migration of these compounds under certain
circumstances can be enhanced (Enfield and Bengtsson 1988) Increases in mobility are greatest
for very hydrophobic (high K) compounds such as pesticides polycyclic aromatic hydrocarbons
(PAH) and dioxins Due to their characteristically low K^s VOC transport in groundwater is
generally unaffected by partitioning to DOC unless DOC concentrations exceed 10000 mgL
(Enfield and Bengtsson 1988) Typically natural DOC concentrations in groundwater range
from 1 to 10 mgL
512 Dispersion
Dispersion is a dilution process by which an initial volume of aqueous solution continually mixes
with increasing portions of the flow system Dispersion occurs on a small or microscopic scale
due to molecular diffusion in the water phase nonuniform velocity distributions within the pore
space and to a large degree the tortuous pathlines that groundwater follows during movement
through interconnected soil pores of different sizes and shapes On a macroscopic scale
dispersion results from geologic heterogeneities such as layers and lenses of contrasting soil type
(ie hydraulic conductivity) In practice dispersion is primarily due to variations in hydraulic
conductivity which produce large gradients in advective transport It is well known that aquifers
contain horizontal layers or lenses of coarser and finer grained materials compared to the average
material type that can result in zones of significantly higher and lower hydraulic conductivity
respectively than the screen interval value determined from pumping and slug tests Factor of
ten hydraulic conductivity variations or more over the thickness of an aquifer are not uncommon
5797wpdocsgalluprifinaltextmasterrifhl061297 5-3 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
(Freyberg 1986 Gelhar et al 1985 Robertson et al 1991 and Sudicky et al 1983) For
contaminant transport the more permeable zones are more important because they determine the
maximum distance over which dissolved constituents will migrate from the source area
With respect to chemical migration from a source area to an arbitrary downgradient location
dispersion will cause contaminants to arrive in a shorter time interval than the travel time based
on the mean groundwater pore velocity (Section 511) This reduced travel time associated with
dispersion is due to advection in the zones of higher hydraulic conductivity that cause the
concentration distribution in the longitudinal (flow) direction to spread out or disperse The
additional length Ld that a chemical may migrate due to dispersion can be estimated from the
following relationship (Bear 1979)
where
t = total time of groundwater travel (= VL^ laquo
Rj = retardation factor
DL = longitudinal dispersion coefficient (length 2time)
In a porous medium the longitudinal dispersion coefficient can be estimated as follows
DL =
where
v = groundwater pore velocity
aL = longitudinal dispersivity of the aquifer (length)
The percent reduction in travel time along a pathline due to longitudinal dispersion can be
calculated using the equation (Bear 1979)
where
At = reduction in travel time along a pathline due to longitudinal dispersion ()
5797wpdocsgalluprifinaltextmasterrifhl061297 5-4 QST Environmental
Gallups Quarry Superfond Project - Remedial Investigation
A t = mdash- 100 ^total
Ld = additional distance (in excess of advection distance) that chemical migrates due to
longitudinal dispersion
= total distance of travel by mean advection (average groundwater flow rate)
An excellent summary of estimated longitudinal dispersivity values for numerous sites is given by
Gelhar et al (1985)
513 Advection Due to Fluid Density Differences
Advective transport can also occur due to fluid density differences in cases where the total
dissolved solids (TDS) concentration is very high A typical example is salinity intrusion into an
aquifer where the greater density of the salt water (TDS 35000000 ppb) causes it to sink within
the fresh water aquifer This causes downward advection of groundwater and results in
stratification of the aquifer into varying zones of salinity However density effects can be caused
by any dissolved compound if the concentration is high enough Laboratory experiments have
shown that density effects do not begin to be observed until the total dissolved concentration in a
plume exceeds background levels by about 1000000 to 5000000 ppb (Schincariol and
Schwartz 1990 Schwille 1988) As a result fluid density effects are not important in the Study
Area
514 Biological and Chemical Degradation
In recent years groundwater scientists have begun to understand the role of microorganisms in
the subsurface transformation of organic chemicals Recent studies have shown that large numbers of organisms can exist in the subsurface environment In many cases organic compounds can be completely degraded to harmless products However by-products can also be
produced which are more mobile and toxic than the parent compound These transformations can
make it difficult to correlate groundwater contamination with particular sources Quantitative
predictions of the fate of biologically reactive chemicals are approximate at best This is due to a
lack of understanding of the biochemical transformation process and variability of transformation
rates in an aquifer (eg as much as two orders of magnitude over a distance of less than 1 m)
For example Wood et al (1980) have demonstrated in the laboratory and observed in the field
the following anaerobic transformations of parent compounds to daughter products
5797wpdoc8galluprifinaltextmasterriftJ061297 5-5 QST Environmental
Gallups Quarry Superfiind Project - Remedial Investigation
carbon tetrachloride -bull chloroform -raquo methylene chloride
trans-12-d ichloroethene
PCE -bull TCE - cis-l2-dichloroethene - vinyl chloride
11-dichloroethene
111-trichIoroethane -raquo 11-dichloroethane - chloroethane
The transformation of PCE (tetrachloroethene) and TCE (trichloroethene) to vinyl chloride is an
example of a transformation to a daughter compound which is considerably more toxic than its
parent compound
Persistence in the environment can be described by a parameter known as the environmental
half-life of a compound The environmental half-life tQ is related to a decay constant X
(Itime) in a first-order decay process
X = ln(2)tm
where ln(2) = 0693 The product of the decay constant and the porewater concentration is equal
to the rate (masstimeunit volume) at which a compound degrades into another form of
compound In practice the parameter half-life is an empirical parameter that quantifies mass loss
due to biological photochemical chemical or physical (eg volatilization) degradation
mechanisms
Within the subsurface biological activity is believed to be the principal cause of the
mineralization (ie transformation to inorganic constituents) of organic compounds (Alexander
1978) Hydrolysis is the reaction of compounds with water or the hydroxide or hydromium ions
associated with water However organic functional groups such as halogenated organics (eg
TCE TCA PCE) ketones benzenes and phenols are generally resistant to this mechanism
(Lyman et al 1982) Oxidation (loss of electrons during a chemical reaction ) and reduction
(gain of electrons during a chemical reaction) can also alter and attenuate organic compounds
For most inorganic compounds geochemical transformations are the most important degradation
mechanisms Due to the complexity of degradation processes and the fact that little data is
typically available to adequately model the loss mechanisms prediction of decay rates in the field
as discussed above is very difficult and not often feasible especially for biodegradation
5797wpdocsgalluprifinaltextmasterrifnl061297 5-6 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
515 Volatilization
The Henrys law coefficient H (Morel 1983) is an air-water partition coefficient which relates
the equilibrium concentrations in air and water for volatile compounds in a multi-phase system
such as the unsaturated zone of the subsurface or the air-water interface of a water body
H = C 1C
where C and eurobdquo are the chemical concentrations in air and water respectively The coefficient is
used in the calculation of volatilization from a water body or soil and for the determination of
solids water and air concentrations resulting from chemical partitioning in a contaminated
unsaturated soil
Organic compounds with Henrys law coefficients greater than 103 atm-m3mole are generally
considered to be highly volatile These compounds can volatilize relatively rapidly from water at
air-water interfaces such as surface water bodies or groundwater tables However the rate of
volatilization is also controlled by diffusion in the water phase Table 5-1 summarizes values of
the Henrys law coefficient for selected organic constituents detected in the Study Area
516 Aqueous Solubility
The solubility of a compound in water is the maximum amount of that compound that will
dissolve in a unit volume of pure water at a specified temperature Water solubility is one of the
most important fate and transport parameters Highly soluble compounds tend to have relatively
low KK values and Henrys law coefficients and tend to be more readily biodegradable by
microorganisms in soil Table 5-1 lists solubilities for VOC detected in the Study Area
52 Study Area-Specific Characteristics 521 Retardation Factors
A Site-specific evaluation of chemical migration rates in groundwater was conducted by
measuring the total organic carbon content TOC of 31 soil samples from the northern Study
Area (Table 5-2) The parameter f (Section 51) is equal to TOC expressed as a fraction As
discussed in Sections 26 and 2721 an ASTM method was used to measure the 4 of the 28
samples from the Former Primary Disposal Area (SB-series borings) EPA Method 9060 was
used to analyze the three samples from the boring for well MW102B The fK measurements for
the SB-series soils samples range from less than 00015 to a maximum of 0023 and the
geometric mean is 00023 In these calculations values below the detection limit of 00015 were
assigned one-half the detection limit These f^ values are typical of high hydraulic conductivity
sand and gravel aquifers
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 5-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The measured values for the three MW102B samples are uncharacteristically low for coarse
stratified drift The geometric mean of these samples is 0000014 which is a factor of 100 lower
than the SB-series data The discrepancy appears to be due to the fact that EPA Method 9060 is
designed for TOC analysis of water samples The f values for the three MW102B samples are
expected to be on the order of 0001 based on comparisons with organic carbon values for
samples of a similar lithology from the Gallups Quarry and other sites Furthermore as
discussed by Karickhoff et al (1979) the available correlations that relate f^ to retardation factor
Ra are not valid below f = 0001 Below values of f = 0001 mechanisms other than
sorption to organic carbon (eg chemical adsorption to mineral surfaces) begin to dominate with
the result that overall sorption and retardation of VOC do not decrease even though the TOC
content of the aquifer materials does Therefore if f^ lt 0001 researchers have indicated that
in many cases calculations of Rd can use f^ = 0001 to account for these alternative sorption
mechanisms For these reasons the SB-series f^ data that are representative of coarse stratified
drift were used in the transport evaluations discussed in the following sections
The average f^ for the SB-series soil samples located below the water table were also calculated
to evaluate vertical trends in the data These samples include
Sample Depth (feet bgs) TOC (mgkg)
SB 104 15-17 lt1500
SB104 26-28 1700
SB108 6-8 lt1500
SB 109 4-8 1600
SB109 10-16 lt1500
SB109 17-24 1500
SB109 24-32 1600
The geometric average f for these samples is 00012 if one-half the detection limit is used for f
lt 00015 Because this average excludes shallow samples with larger silt contents it is
considered more representative of the higher hydraulic conductivity coarse-grained soils which
primarily control groundwater transport
Table 5-1 summarizes chemical-specific retardation factors for VOC detected in Study Area
groundwater These estimates are based on a f value of 00012 which as discussed above is
near the minimum value appropriate for the calculation of R Actual retardation factors in the
aquifer will be nonuniform due to the inherent variability of soil organic carbon content For
example retardation factors based on an f of 00012 may be more appropriate for evaluation of
5797wpdocsgalluprifinaltextmasterri fal061297 5-8 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
transport rates in the middle to lower portions of the aquifer where the soil is generally coarser
and contains less silt which is associated with the organic carbon content Conversely the
average value of 00023 for all samples is likely more representative of soils in the upper portion
of the aquifer and above the water table In any case this overall variability in f^ values for the
aquifer is considered to be smaller in magnitude than the natural variability in hydraulic
conductivity values for the site The recent detailed field investigations in sand and gravel
aquifers referenced in Section 512 have shown that it is not uncommon for hydraulic
conductivities to vary by as much as a factor of ten over a scale of a few feet Variations in both
f and hydraulic conductivity values impact predicted chemical transport rates (Section 511)
A bulk dry density of 18 gcm3 and an effective porosity of 025 were estimated from the
literature based on soil grain size analyses Potential variability associated with these parameters
is small compared to k^ estimates and is not important for the following transport rate evaluation
The results in Table 5-1 are useful for comparing relative mobilities for different compounds and
assessing contaminant migration rates relative to groundwater pore velocities 11-dichloroethane
is expected to be the most mobile VOC while PCE and ethyl benzene should be the least mobile
The tracer compounds TCA and DCE are expected to migrate about a factor of two slower than
the groundwater with DCE migration being the fastest
522 Chemical Migration Rates
5221 Groundwater Travel Times
Compound-specific migration rates in the overburden aquifer were examined using Darcys law
(Section 511) to compute groundwater pore velocities from (1) measured horizontal hydraulic
gradients defined by the November 1995 piezometric surface maps (Section 332) (2) the
hydraulic conductivity data (Table 3-1) and (3) estimated retardation factors (Table 5-1) The first step was to construct a map of groundwater times-of-travel along the various pathlines shown
on the groundwater flow maps for the southern Study Area (Plate 3-9) and for the lower portion
of the aquifer in the northern Study Area (Plate 3-8) Groundwater travel times along each of the
pathlines were modelled using the Tecplot software and the interpolated piezometric head
distribution to define the continuous horizontal hydraulic gradient distribution Additional
information regarding pathline computation using Tecplot is provided in Appendix Q Since the
more permeable zones in an aquifer are known to control the rate of advancement of a plumes
leading edge (Section 512) the upper bound hydraulic conductivity estimates from Table 3-1
were considered From a review of these measurements it was determined that a mean hydraulic
conductivity of 004 centimeters per second (115 feet per day) would be reasonable to use in the
time-of-travel computations in the northern Study Area because this value is representative of the
more permeable coarse-grained soils north and northwest of the Former Primary Disposal Area
(ie wells MW102TT MW103TT MW104TT MW117TT and MW118TT) A lower
5797wpdoc8galluprifinaltextmlaquosterrifhl061297 5-9 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
hydraulic conductivity of 00025 cms (7 ftday) representing the geometric mean value for wells
MW114TT and MW115TT was selected for the southern Study Area An effective porosity of
025 was used in the calculations
The travel-time analysis results are shown in Plate 5-1 Markers denoting half-year (northern
Study Area) and five-year (southern Study Area) travel-time intervals have been placed on each of
the pathlines to allow evaluation of spatial variations in groundwater pore velocity and
determination of total groundwater travel-time between different locations The time period
required for a particular VOC to migrate along a pathline can be estimated as the product of the
groundwater travel-time and the compound-specific retardation factor listed in Table 5-1
5222 Groundwater Flushing Rates
Another useful relationship to consider when evaluating chemical migration is the time period
required to reduce the concentration in a specific portion of an aquifer by groundwater flushing
Assuming that source material is no longer introducing contamination into the portion of the
aquifer (ie control volume) being evaluated the US EPA Batch Flushing Model (EPA 1988)
provides such a relationship
p v = J V h )
where In is the natural logarithm to the base e Rd is the retardation factor C0 is the initial or
starting average groundwater concentration in the control volume Q is the final average
concentration and Pv is the number of groundwater pore volumes which have flowed through the
control volume Pv can be estimated as
P =-raquo v Ltotal
where v is the groundwater pore velocity (Section 511) t is the time duration being considered
and L^ is the total distance or length along a characteristic pathline (from upgradient to
downgradient) through the volume of aquifer material The model assumes complete mixing of
contaminants (ie infinite dispersion) within the control volume Brusseau (1996) demonstrated
that in part due to this assumption the Batch Flushing Model can partially account for
nonequilibrium desorption (ie delayed release) of VOC from soil
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 5-10 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
For example the southern Study Area (area south of the Former Seepage Bed) can be considered a control volume with a characteristic groundwater flushing rate In this area a time t of order 10 years is required for groundwater to flow through a distance L^ of about 400 feet thus indicating an average pore velocity v of about 40 feet per year In other words one pore volume of groundwater flushes through the overburden deposits in the southern Study Area in approximately 10 years From the Batch Flushing Model it can be seen that for a nonsorbing compound with R = 1 23 pore volumes [ln(10)] would need to flush through this area to lower average concentrations by a factor of ten assuming no source material remained east of the southern Study Area or above the water table 46 pore volumes would be needed for a factor of 100 reduction Since each pore volume roughly corresponds to 10 years the factors of 10 and 100 concentration reductions would require time periods of about 23 and 46 years respectively If however one were considering a compound with R = 3 the corresponding times would be about 70 and 140 years
5223 Discussion In the northern Study Area three areas of characteristically different horizontal hydraulic gradients exist in the overburden aquifer The steepest gradients (on the order of 0025 feet per foot) are found south of the former disposal areas Assuming the hydraulic conductivity in this area is 004 cmsec Plate 5-1 shows that the groundwater travel time through this portion of the aquifer is expected to be much less than one year However hydraulic conductivity data and soil descriptions suggest that a more representative hydraulic conductivity value for the till deposits in this area would be 0001 cmsec or less which would correspond to a travel time of five years or more (eg from MW109 to the Former Primary Disposal Area)
Northeast of well MW116 north of Mill Brook and in the vicinity of the former Pervel flock plant the hydraulic gradient is about 0007 feet per foot and a hydraulic conductivity of 004 cmsec is representative of the aquifer As a result the largest groundwater pore velocities are expected to exist in these areas For example as shown in Plate 5-1 the expected groundwater travel time is about one to two years from the vicinity of Pervel to MW116 and from Pervel to MW101
Groundwater travel times downgradient from the Former Primary Disposal Area are much longer due to the low hydraulic gradients northwest of the railroad tracks In the vicinity of MW105 and MW102 the gradient is about 00003 feet per foot or more than a factor of 20 less than the gradient northeast of this area For example the estimated groundwater travel time (ignoring longitudinal dispersion) from MW107 to MW102 near the front of the VOC plume is about 8 to
10 years By comparison almost 20 years has passed since the documented disposal in the late 1970s Based on the retardation factors (Table 5-1) for TCA (R = 23) and DCE (R = 14)
5797wpdocsgalluprifinaltextmasterrifhl061297 5-11 QS7 Environmental
Gallups Quarry Superand Project - Remedial Investigation
the estimated travel times for these compounds from MW107 to MW102 are about 20 years and
13 years respectively Considering these chemical migration rates and the fact that TCA and
DCE were detected at quantifiable levels along the VOC plume centerline and at location
MW102 it appears reasonable to conclude that these compounds are associated with the former
disposal areas
However as discussed in Section 4221 the present PCE distribution in groundwater exhibits
inconsistencies with migration from the former disposal areas Although historical detections of
PCE were found in well cluster SW17 which is located downgradient from the Former Primary
Disposal Area and near well cluster MW105 the concentrations had reduced from a maximum of
1000 ppb in 1980 to near the detection limit by early 1993 (Section 523) Based on this rate of
reduction PCE concentrations at diis location would be expected to have fallen below or near the
detection limit by 1995 In fact only trace levels were detected in wells MW105TT and
MW105T during two of the four 1995 sampling events Furthermore the measured groundwater
flow directions in the overburden aquifer indicate that many of the pathlines originating near the
former Pervel flock plant pass through the vicinity of wells MW117 MW118 MW119 MW116
MW103 MW102 and MW101 Although MW101 and MW102 are downgradient from both
Pervel and the former disposal areas groundwater flow conditions in the past would need to have
been different from present conditions for MW116 and MW103 to be downgradient from the
former disposal areas As discussed in Section 4 elevated levels of PCE TCA and DCE have
been detected in monitoring wells located on the former Pervel property Also PCE TCA and
DCE were detected in wells MW116T MW118TT and MW103TT located downgradient from
Pervel during the 1995 sampling rounds and PCE TCE and DCE were detected in well MW-C
on the former Pervel property The travel time of these compounds from Pervel to wells
MW116 MW118 MW103 MW102 and MW101 is estimated to be two to six years Taking
this into consideration along with the VOC detections in the Pervel wells during the period 1987
to 1989 (Section 523) it is possible that the low-level PCE TCA and DCE detections in
MW116T MW118TT and MW103TT represent the last remaining portion of a Pervel VOC
plume The lack of VOC detections in wells MW117 and MW119 could be explained by dilution
in these areas or by the fact that these wells may not be immediately downgradient from the
historical source area(s) on the former Pervel property
The migration rate of PCE compared to the disposal area tracer compounds TCA and DCE also
supports the existence of an off-site PCE source The expected migration rate of PCE is a factor
of two to four slower than that of TCA and DCE due to their differing K values Assuming all
of these VOC were released within a few years of each other the leading edges of the TCA and
DCE plumes should be much farther downgradient than the PCE plume Instead as evidenced by
the data shown in Plate 4-6 the opposite is true because a PCE concentration of about 30 ppb has
5797wpdocsgalluprifinaltextmasterrifnl061297 5-12 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
been detected at MW101 In terms of groundwater migration (not including retardation) from the
Former Primary Disposal Area the elevated PCE concentrations at location MW101 would
represent a total travel-time from the former disposal areas which is more than a factor of two
greater than that required for the leading edge of the TCA-DCE plume to reach MW102
Comparing the relative mobilities of PCE TCA and DCE (Table 5-1) the time required for PCE
to migrate from the Former Primary Disposal Area to well MW101 should be more than a factor
of four to eight longer than the TCADCE travel time to MW102 Based on this comparison the
PCE detections at MW101 could be attributed to transport from Pervel It is also possible that
the Pervel groundwater contamination has impacted the MW102 area Although the PCE
detections at locations MW102 and MW101 could be attributable to historical releases from the
former disposal areas the above findings (flow directions spatial PCE distribution travel times)
suggest that contamination from the former Pervel facility has at a minimum contributed to VOC
contamination (PCE and possibly DCE and TCA) at these locations
The above discussion also highlights the important issue of what defines the leading edge of the
zone of VOC contamination in the overburden aquifer Several of the above findings suggest that
the downgradient extent of VOC contamination associated with the former disposal areas is
located near wells MW102 and MW101 The convergent nature of the groundwater flow patterns
in the northern Study Area clearly establish a narrow well-defined preferred pathway of low-level
contaminant migration from the Former Primary Disposal Area The chemical analysis results
from the monitoring well sampling program confirm the measured flow directions Further
whereas TCA and DCE can presently be traced continuously along the plume centerline at
elevated levels (well locations MW107 MW105 and MW102) PCE cannot These findings
suggest that the PCE contamination in groundwater may be attributable to the former Pervel flock
plant and should not be used solely to define the leading edge of the VOC plume The time-ofshy
travel computations support the location of the disposal area VOC plume between MW102 and
MW101 The reduction of TCA and DCE concentrations to less than 10 ppb and the decrease of
xylene to below detection at MW101 is also consistent with the interpretation that the disposal
area VOC plume does not extend far beyond MW102 In addition the groundwater pore velocity
in the vicinity of wells MW102 and MW101 is estimated to be about 50 feet per year which is as
much as a factor of 20 lower than rates upgradient from this area Based on this pore velocity
and the retardation factors in Table 5-1 the migration rates of TCA and PCE are expected to be
about 20 and 10 feetyear respectively At these rates the estimated travel times for TCA and
PCE from MW102 to MW101 are about 20 and 35 years respectively As discussed in the
following section given the relatively large rates of historical VOC concentration reductions
which have been observed in the northern Study Area it is expected that PCE 12-DCE 11shy
DCE and TCE levels near MW102 will fall below MCLs within the above 20- to 35-year period
due to biodegradation and dilution mechanisms Reduction rates for vinyl chloride which also
5797wpdocsgalluprifinaltextmlaquoraquoterrifhl061297 5-13 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
has been detected above MCLs near MW102 will likely lag behind the other VOC because it is a
final chlorinated breakdown product
523 Time-Dependent Concentration Reductions
5231 Observed Concentration Changes
Significant groundwater concentration reductions with time have been observed in the northern
Study Area from the late 1970s through the 1995 sampling rounds To illustrate these temporal
trends concentration data for selected VOC were plotted versus time to quantitatively evaluate the
reduction rates The observed rates of concentration reduction are also compared to predicted
values using the groundwater flushing relationships presented in Section 5222 and are evaluated
to determine site-specific estimates of biodegradation rates
Figures 5-1 through 5-3 contain the concentration vs time graphs for three groups of wells
organized according to transport characteristics and location Group 1 (Figure 5-1) immediately
downgradient from the former disposal areas (SW17S SW17D SW13 MW107TT MW105S
and MW105TT) Group 2 (Figure 5-2) within the downgradient portion of the VOC plume
(MW102S MW102TT MW101TT) and Group 3 (Figure 5-3) the area northeast of the VOC
plume and downgradient from the former Pervel flock plant Data from the Group 1 wells
provide a good historical perspective on improvements in groundwater quality resulting from
source removal activities in the late 1970s and from ongoing biodegradation and rainwater
infiltration (flushing) within the Former Primary Disposal Area The Group 2 wells are located
within the downgradient portion of the VOC plume and in a section of the aquifer where the
hydraulic gradient and associated groundwater transport rates are up to a factor of 20 lower than
in other parts of the northern Study Area Group 3 wells are downgradient from the former
Pervel facility where elevated levels of PCE and TCA have been detected and are located in the
portion of the aquifer with the highest groundwater flushing rates
5232 Evaluation of Concentration Reduction Rates and Mechanisms
The most important aspect of the semilogarithmic plots in Figures 5-1 to 5-3 is the characteristic
slope or trend of the concentrations as a function of time Specifically it can be seen that many
of the graphs exhibit an almost straight-line decrease in concentration with time This linear
variation is often observed with historical groundwater quality data because the linearity has a
physical basis First many biodegradation mechanisms can be modelled as a first-order decay
process (Section 51) which produces a straight-line decrease in concentrations on a semi-log plot
Second flushing of clean groundwater (eg rainwater infiltration or uncontaminated
groundwater) through a contaminated volume of aquifer material has been shown (Section
5222 Brusseau (1996)) to exhibit the same type of response In both of these approximate
first-order processes the slope of the straight-line response is inversely proportional to the
5797wpdocsgalluprifinaltextmasterrifhl061297 5-14 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
environmental half-life (Section 514) for that mechanism and a particular chemical compound
Using the relationships developed in Section 5222 the environmental half-life associated with
groundwater flushing can be defined as
Substituting the expression for pore volume Pv the flushing half-life can also be written
From the above expression it can be seen that the flushing half-life for a particular compound is
directly proportional to the chemical retardation factor and inversely proportional to the
groundwater pore velocity The groundwater flushing rate represents the rate at which
concentrations in a particular portion of the aquifer are reduced In contrast to biodegradation
groundwater flushing does not reduce the total mass of a compound in the aquifer because the
contaminants are advected to downgradient areas
In the Group 1 area historical VOC data for the SW-series wells (Metcalf amp Eddy 1993) (eg SW13 and SW17) summarized in Table 5-3 and on Figure 5-1 show that TCA TCE and PCE
levels in groundwater downgradient from the Former Primary Disposal Area have typically
decreased by a factor of more than 100 from the late 1970s to 1993 Using the SW17S data
from 1980 to 1993 the estimated environmental half-lifes for TCA TCE and PCE are
approximately 15 20 and 24 years respectively From February 1993 through the present the
shallow concentration reduction rates (SW17S and MW105S) are much higher corresponding to TCA TCE PCE and DCE environmental half-lives of about 03 lt 1 03 and 04 years
respectively Concentration reduction rates in the lower portion of the aquifer (SW17D and
MW105TT) from February 1993 through the end of 1995 are a factor of two to three slower than
shallow rates the estimated environmental half-lifes for TCA PCE and DCE in the deep aquifer are about 06 09 and 09 years respectively The higher concentration reduction rates in the
shallow aquifer may be due to rainwater infiltration andor increased biodegradation These
decreases in VOC levels are likely due to a combination of (1) source removal and source
depletion (ie soil concentration reduction by flushing mechanisms) within the former waste
disposal areas (2) mixing of rainwater infiltration with groundwater which can be a significant
dilution mechanism in the wetland areas as evidenced by the frequent occurrence of ponded water
and (3) biodegradation by microorganisms in soil
5797wpdoc8galluprifiiialtextmlaquoraquoterrifhl061297 5-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Vinyl chloride does not follow the same trends of reducing concentrations exhibited by the other
chlorinated VOC Vinyl chloride concentrations in wells MW107TT and MW105TT generally
increased during the 1995 sampling rounds Since this compound is the final chlorinated
breakdown product of PCE TCE and DCE it appears that the vinyl chloride detections are the
result of biodegradation The apparent increase in vinyl chloride concentrations and decrease in
DCE levels in well MW107TT may be further evidence that vinyl chloride detections are
associated with biodegradation mechanisms
The observed Group 1 environmental half-lifes are consistent with predicted half-lifes due to
groundwater flushing From Plate 5-1 the estimated groundwater travel time from MW107 to
MW105 is 05 to 1 year which corresponds to 1 to 2 groundwater pore volumes per year
flushing through the Group 1 Area Using the retardation factors in Table 5-1 the predicted
flushing half-lifes for DCE TCA and TCE range from 05-10 08-16 and 07-14 years
respectively and the flushing half-life for PCE is between 14 and 3 years This good agreement
between observed and predicted rates of concentration reduction downgradient from the former
disposal areas is additional evidence that source removal activities were successful and natural
mechanisms are actively producing further reductions in contaminant levels The fact that deep-
aquifer PCE and TCA concentrations near MW105 have decreased more rapidly than predicted
groundwater flushing rates during the period 1993 to 1995 suggests that biodegradation is
breaking down these parent compounds Furthermore TCA TCE and PCE reduction rates
before 1993 were much slower and are similar in magnitude to flushing rates This indicates that
biodegradation before 1993 was less important Assuming this is the case the estimated
biodegradation half-lifes for PCE and TCA for the period 1993 to 1995 range from 13-25 and
10-24 years respectively near the Former Primary Disposal Area In contrast observed
reduction rates for TCE and DCE are slower than predicted flushing rates which may be
evidence that breakdown of their respective parent compounds was significant during the period
1993 to 1995 Indeed this interpretation is consistent with the observed biodegradation of PCE
In the Group 2 area (Figure 5-2) VOC levels (with the exception of DCE) at well cluster
MW102 appear to increase in 1995 while concentrations at cluster MW101 remained relatively
constant The concentration increase at MW102 may be due to the fact that this cluster is near
the leading edge of the VOC plume and groundwater flushing rates in this area are relatively low
However as discussed in Section 522 the increased PCE and TCA levels along with daughter
products such as TCE DCE vinyl chloride and DCA may be associated with transport of the
PCE and TCA plumes on the former Pervel property
The most interesting of the Group 3 wells are wells MW-A -B and -C located on the former
Pervel property As shown on Figure 5-3 PCE and TCA concentrations in wells MW-A and
5797wpdoc8galluprifinaltextmasterrifhl061297 5-16 QampT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW-B reduced to below detection limits by 1990 These rates of reduction correspond to halfshy
lifes of about 02 years for TCA and 03 years for PCE By comparison based on travel time
estimates from Plate 5-1 predicted groundwater flushing half-lifes for TCA and PCE
concentration reduction near Pervel are about 08 and 14 years respectively Assuming the
differences between observed concentration reduction rates and rates predicted by groundwater
flushing alone are due to biodegradation the biodegradation half-lifes for TCA and PCE are 03
and 04 years respectively In well MW-C TCA levels have reduced at a rate consistent with a
02-year half-life while the PCE half-life is approximately 05 years The corresponding
estimated biodegradation half-lifes for TCA and PCE at MW-C are 03 and 08 years
respectively Therefore biodegradation appears to be the major cause of the observed TCA and
PCE concentration reductions in the Pervel wells The lack of PCE or TCA detections in well
clusters MW119 and MW117 during the November 1995 sampling round are also consistent with
the rates of reduction in the Pervel wells For example the estimated travel times of PCE and
TCA from Pervel to the MW119 and MW117 wells are on the order of 4 and 2 years
respectively Since PCE and TCA levels in wells MW-A and MW-B were below detection by the
beginning of 1990 this groundwater with no detectable levels of either compound would be
expected to have passed through the MW119 and MW117 wells by the beginning of 1994 (PCE)
or 1992 (TCA)
In contrast the groundwater travel time from Pervel to wells MW116 MW103 and MW118 is
estimated to be up to one year longer than the travel time to MW119 and MW117 This would
correspond to increased travel times for PCE and TCA of about 4 and 25 years respectively
Based on these estimates low but detectable levels of PCE and TCA would be expected in wells
MW116 MW103 and MW118 during 1995 groundwater sampling In fact PCE TCA and
DCE were detected at each of these locations in 1995 at trace levels Slightly higher
concentrations of PCE and TCA were detected in MW116T during January 1995 but trace levels
were detected during each of the three subsequent 1995 rounds Further these rates of PCE and
TCA migration from Pervel would be consistent with the detections in well clusters MW102 and
MW101
Additional estimates of biodegradation rates were made by evaluating concentration reductions
within the parcel of groundwater located near well SW17 in 1980 Using the travel times shown
in Plate 5-1 it is estimated that about five years would be required for groundwater to travel from
SW17 to MW102 The corresponding chemical migration rates for TCA TCE and PCE are 12
11 and 20 years respectively Due to longitudinal dispersion (Section 512) the actual travel
times would be somewhat less Therefore groundwater presently in the MW102 area is expected
to be representative of historical (1980) groundwater contamination from the SW17 area
Neglecting possible contaminant contributions from Pervel most of the VOC concentration
5797wpdocsglaquolluprifinaltextmalaquoteiTifTil061297 5-17 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
reductions occurring in this parcel of groundwater as it traveled from SW17 to MW102 would be
due to biodegradation and rainwater infiltration
Figure 5-4 shows the TCA TCE and PCE concentration data from 1980 and 1982 for SW17S
and from January and November 1995 for wells MW102S and MW102TT The slopes of the
lines connecting the data from these two periods provide estimates of the combined biodegradation
and rainwater dilution rates for these compounds The combined half-lives for these two
mechanisms are 15 years (TCA) 18 years (TCE) and 21 years (PCE) From Bear (1979) the
half-life for rainwater dilution can be estimated as
n - b
where n = effective porosity b = saturated thickness and I = groundwater recharge rate due to
rainwater infiltration Using n = 025 b = 60 feet and I = 30 inchesyear (USGS 1995) the
half-life for dilution due to rainwater infiltration is about 4 years Using this value the estimated
biodegradation rates for TCA TCE and PCE within the VOC plume are 24 33 and 44 years
respectively These estimated biodegradation rates for TCA and PCE are a factor of two to three
less than estimated rates near the Former Primary Disposal Area during the period 1993 to 1995
5233 Summary
From the late 1970s through the four 1995 sampling rounds groundwater concentrations in the
VOC plume downgradient from the Former Primary Disposal Area have decreased at a rapid rate
The groundwater quality data from 1995 indicates that this trend of reducing concentrations is
continuing Based on these concentration reduction rates most VOC levels will fall below their
respective MCLs in a period of less than four years Vinyl chloride is an exception to this trend
because increased levels of this compound were detected in 1995 apparently due to the chemical
break down of its parent compounds PCE TCE and DCE
Analyses of these concentration reductions with time indicate that biodegradation and dilution by
rainwater infiltration are the key mechanisms responsible for these changes with biodegradation
likely the most important component Within the VOC plume biodegradation and rainwater
infiltration are reducing most VOC (with the exception of vinyl chloride) concentrations by about
a factor of two every two years which corresponds to an environmental half-life of two years
5797wpdocsglaquolluprifinaltextmraquosterrifnl061297 5-18 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
60 Summary and Conclusions
This section provides the conceptual model developed for the Study Area based on the findings
of the Phase 1A and IB field investigations and the results of the Long-Term Monitoring
Program sampling events
61 Conceptual Model of the Study Area The conceptual model was developed from the collection and analyses of information and data
from the Remedial Investigation (RI) as well as historical information and data A conceptual
model is an overview of the Study Area taking into account all media and their interrelationships
and describes in summary fashion Site conditions as they pertain to contaminant sources and
migration pathways This conceptual model will be used to support the evaluation of potential
remedial alternatives for the Feasibility Study
611 Geology
Geologic data collected during the RI indicate the following
bull Significant surficial or overburden deposits encountered in the Study Area are till
and glacial deposits referred to as stratified drift
bull The till is relatively dense and is comprised of a fine sandy matrix with abundant
gravel cobbles and boulders The till was encountered directly above bedrock at
most locations at thicknesses of 10 to 20 feet with the thickest accumulations
located along the topographic (bedrock) high in the central area of the Site
bull The stratified drift typically overlies the till or bedrock and consists of poorly to
well sorted deposits of gravel sand and silt Grain size analyses indicate that the
stratified drift is primarily comprised of fine to coarse sands with lesser amounts
of silt and fine gravel The stratified drift thickness varies from less than a few
feet in upland areas to as much as 70 feet in the vicinity of Mill Brook
bull Bedrock within the Study Area consists of grey fine- to medium-grained gneiss
with varying contents of amphibolite biotite and hornblende The bedrock
surface is characterized by a large slope and dips to the northwest and west-
southwest from a bedrock high located about 400 feet southeast of the Former
Seepage Bed The total bedrock surface relief in the Study Area approaches 100
feet
5797wpdocsgalluprifinaltejctmasterri fhl061297 6-1 QfT Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull Geophysical investigations (seismic refraction and magnetometer surveys)
conducted in the vicinity of the Former Seepage Bed did not reveal evidence of
one or two suspected discrete bedrock faults Rather the bedrock in the central
portion of the Site may be more accurately characterized as a series of
interconnected (to varying degrees) fractures and faults
^
612 Hydrogeology
Data regarding hydrogeologic conditions are summarized as follows
Hydraulic Conductivity
bull Across the Study Area test results indicate that the hydraulic conductivity
of the shallow overburden deposits averages approximately 0001
centimeters per second (cms) while the mean hydraulic conductivity for
the deep portion of the aquifer is about 0005 cmsec A mean hydraulic
conductivity of about 0037 cms is more representative of coarser-grained
deposits in the middle to lower portions of the overburden aquifer
northwest of the railroad tracks where the saturated thickness increases to
almost 70 feet
bull The mean hydraulic conductivity of the till (000047 cms) is a factor of
ten less than the average for the stratified drift deposits in the lower
portion of the aquifer and varies between 00002 and 0002 cms
Although the hydraulic conductivity of the till indicates that it is less
permeable and hydrogeologically distinct from the overlying stratified drift
deposits the hydraulic conductivity contrast is not large enough to
significantly alter groundwater flow directions or rates
cir
bull The mean bedrock hydraulic conductivity (000018 cms) is a factor of 25
lower than the average for the coarse-grained stratified drift Due to the
heterogeneous nature of fracture sizes and interconnectivity and their
associated nonlinear effect on groundwater flow rates the hydraulic
conductivity of the bedrock can be expected to be highly variable
throughout the Study Area
5797wpdocsgalluprifinaltextmasterrifhl061297 6-2 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
Groundwater Flow
bull The overburden aquifer is the preferred pathway for groundwater transport
of dissolved constituents This conclusion is supported by the hydraulic
conductivity test results and observations that an upward groundwater
flow component from bedrock to overburden exists throughout most of the
Study Area VOC detections in bedrock wells are believed to be caused
by vertical dispersion in the upper portion of the fractured bedrock
bull Because the unconsolidated deposits become unsaturated in the vicinity of
the Former Seepage Bed discussions of groundwater flow in overburden
are naturally divided into northern and southern portions of the Study
Area
bull Overburden groundwater flow south of the Former Seepage Bed is
generally from east to west at an average hydraulic gradient of 001 feet
per foot (vertical change in piezometric head per horizontal distance) and
is strongly influenced by the bedrock surface and drainage to the wetlands
and stream west of the railroad tracks The saturated thickness in this
area increases from zero near the bedrock high (northeast corner) to more
than 60 feet near the railroad tracks
bull Three distinct zones of overburden groundwater flow exist in the northern
Study Area In the area between the Former Primary and Secondary
Disposal Area and the Former Seepage Bed groundwater flow is largely
through till deposits and toward the north-northwest The hydraulic
gradient in this area is steep (about 003 feet per foot) and strongly
influenced by the dip of the bedrock surface and the lower hydraulic
conductivity of the till deposits The saturated thickness increases from
zero south of MW109 to 20 to 30 feet near the former disposal areas
North-northwest of these areas the hydraulic gradient lessens significantly
to a range of 00003 to 00007 feet per foot (factor of 40 to 100
reduction) North and northeast of Mill Brook the hydraulic gradient is
about 0007 feet per foot
bull Available data indicate that in the northern Study Area overburden
groundwater flow north-northwest of the Former Primary and Secondary
Disposal Areas exhibits a strongly convergent pattern The flow
5797wpdocsgalluprifinaltextmlaquosterriftU061297 6-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
converges from the east-northeast and southwest toward a centerline
generally defined in the downgradient direction by wells MW105
MW102 and MW101 Groundwater flows along this centerline from the
former disposal areas to the northwest Groundwater also flows from the
vicinity of the former Pervel flock plant in southwesterly and westerly
directions toward wells MW116 MW103 and MW101
South of the Former Seepage Bed groundwater flow within the upper
portion of the bedrock unit is primarily in a westerly direction In the
northern Study Area the predominant bedrock flow component is toward
the northwest In both areas the hydraulic gradient is relatively steep and
averages about 002 feet per foot Groundwater flow in bedrock near the
Former Seepage Bed is toward the northwest in the direction of wells
MW113 and MW106 and exhibits no apparent influence from locally
increased fracturing identified from the geophysical investigation and the
hydraulic testing in well MW11 IB
Vertical flow of groundwater is important in the upper several feet of the
bedrock unit Groundwater flow was found to be discharging from
bedrock to overburden at all locations during each of the measurement
dates with the exception of MW109 At MW109 the saturated overburden
thickness is less than a few feet and MW109 is located over a much
higher bedrock elevation than all other wells at which vertical flow from
bedrock was measured
Vertical flow in the overburden aquifer is of increased importance in two
areas in the vicinity of the Former Primary Disposal Area (wells clusters
MW107 MW108 and MW116) where vertical flow directions are
downward and within the upper portion of the aquifer near Mill Brook
where vertical flow is upward
Stream piezometer data and groundwater flow modeling indicate that Mill
Brook generally gains water from the overburden aquifer in the northern
portion of the Study Area
5797wpdoc8galluprifinaltextmraquosterrifhl061297 6-4 Q5T Environmental
Gallups Quarry SuperfimdProject - Remedial Investigation
613 Nature and Extent of Contamination
6131 Contaminant Source Investigation
The following summarizes the findings of contaminant source investigations during the RI
bull Previous remedial activities have completely removed the waste materials
(intact drums and bulk liquid waste) from the Site
bull The Former Seepage Bed and the Former Secondary Disposal Area
contain little residual contamination from the disposal activities which
occurred in the late 1970s
bull Residual levels of contamination primarily VOC and PCB were detected
in the Former Primary Disposal area In general the highest levels of
VOC are located at or just below the groundwater table in native soils
immediately beneath the fill materials and diminish rapidly with depth
PCB were detected primarily within fill materials
bull Other than the three known former disposal areas and the remains of the
former CTDOT asphalt plant no other significant disposal areas were
found to exist on the Site
6132 Groundwater Quality
Groundwater quality data collected during the Phase 1A program indicate the following
bull No significant groundwater contamination was detected within the
overburden or bedrock units in either the southern Study Area or in the
vicinity of the Former Seepage Bed
bull In the northern Study Area a narrow low to moderate-concentration
VOC plume (primarily TCA and DCE) was detected in the overburden
aquifer extending from the Former Primary Disposal Area to the
northwest towards Mill Brook
bull Comparison of present concentrations with historical data indicate that
concentrations within the VOC plume are significantly decreasing with
time From 1978 through 1995 TCA TCE and PCE concentrations
have decreased on the average by more than a factor of two every two
5797wpdocsgalluprifinaltextnui8terrifhl061297 6-5 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
years This trend appears to have continued through the four 1995
sampling rounds for these as well as other VOC with the exception of
the break down product vinyl chloride Biodegradation and dilution by
rainwater infiltration have been identified as the primary mechanisms
causing the concentration reductions with biodegradation the most
important component
The size and orientation of the VOC plume are in excellent agreement
with the established groundwater flow directions
Available information indicates that the leading edge of the VOC plume
associated with the Former Primary Disposal Area is located between
monitoring well clusters MW102 and MW101 VOC transport rates and
the reduction of TCA and DCE levels to estimated values at MW101
support this conclusion
PCE detections in the downgradient portion of the plume exhibit
inconsistencies with migration from the Site Groundwater pathlines and
time-of-travel estimates indicate that the PCE may be attributable to
contaminant transport from the former Pervel facility located north of the
Site Specifically it is possible that PCE detections at locations MW118
MW116 MW103 MW102 and MW101 may have resulted from
groundwater transport from the vicinity of the former Pervel flock plant
However it is also plausible that the PCE detections at locations MW102
and MW101 are attributable to the former disposal areas
Results of surface watersediment sampling and analyses stream
piezometer measurements and groundwater flow modeling indicate that
some discharge of the shallow portion of the plume into Mill Brook is
occurring There are low-level detections of VOC in the section of brook
intersecting the plume however the concentrations are well below those
reported to cause adverse effects in wildlife Detections downstream
adjacent to the municipal sewage treatment plant and below the confluence
of Fry Brook and Mill Brook are probably attributable to off-site sources
along Fry Brook north of the Study Area
Only one of the bedrock wells (MW105B) indicated elevated levels of
VOC Trace levels of a limited number of VOC were also detected in
5797wpdocsgalluprifinaltextma8terrifhl061297 6-6 QStf Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW102B MW107B MW108B and SW-10 however bedrock is not a
preferred pathway for contaminant migration due to its characteristically
low hydraulic conductivity and the consistent upward component of
ground water flow from bedrock to overburden which exists throughout the
Study Area
5797wpdocsgalluprifinaltextmastemfiil061297 6-7 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
70 References
Alexander M 1978 Biodegradation of Toxic Chemicals in Water and Soil in Proc 176th
National Meeting Miami Beach FL Sept 10-15 v 93 American Chemical
SocietyDivision of Environmental Chemistry
Amtec Engineering 1994 Tecplot Version 6 Belevue WA
Bear J 1979 Hydraulics of Groundwater McGraw-Hill
Beyer WN 1990 Evaluating Soil Contamination US Fish Wildl Serv Biol Rep 90(2) 25
pp July 1990
Bouwer H and Rice RC 1976 A Slug Test Method for Determining Hydraulic Conductivity
of Unconfined Aquifers with Completely or Partially Penetrating Wells Water Resources
Research vol 12 no 3 pp 423-428
Boynton GR and Smith CW 1965 Aeromagnetic map of the Plainfield quadrangle New
London and Windham counties Connecticut US Geological Survey Geophysical
Investigations Map GP-541 scale 124000
Brusseau ML 1996 Evaluation of Simple Methods for Estimating Contaminant Removal by
Flushing Groundwater V 34 No 1 pp 19-22
CTDEP 1986 Water Quality Classification Map for the Thames Southeast Coast and Pawcatuck River Basins Sheet 2 of 2 CTDEP Water Compliance Unit Hartford
Connecticut
Dixon HR 1965 Bedrock geologic map of the Plainfield quadrangle Windham and New
London Counties Connecticut US Geological Survey Geologic Quadrangle Map GQshy
481 scale 124000
Enfield CG and Bengtsson G 1988 Macromolecular Transport of Hydrophobic
Contaminants in Aqueous Environment Groundwater v 26 no 1 pp 64-70
ERT 1988 Preliminary Hazardous Waste and Petroleum Hydrocarbon Contamination Evaluation
of the InterRoyal Property Plainfield CT
5797wpdoc8galluprifinaltextmasterrifhl061297 7-1 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
ESE 1994 Gallups Quarry Superfund Project RIFS Work Plan Phase 1A (Prepared by Haley
amp Aldnch Inc Finalized by ESE)
ESE 1995 Initial Site Characterization Report March 1 1996
ESE 1995a April 1995 Long-Term Monitoring Report July 28 1995
ESE 1995b July 1995 Long-Term Monitoring Report October 27 1995
ESE 1996a Long-Term Monitoring Program - Data Report February 1996 Sampling Event
June 19 1996
ESE1996b Long-Term Monitoring Program - Data Report May 1996 Sampling Event
September 24 1996
ESE 1996c Long-Term Monitoring Program - Data Report August 1996 Sampling Event
December 18 1996
ESE 1997a Long-Term Monitoring Program - Data Report November 1996 Sampling Event
March 31 1997
ESE 1997b Long-Term Monitoring Program - Data Report February 1997 Sampling Event
May 21 1997
Fitchko J 1989 Criteria for Contaminated SoilSediment Cleanup Pudvan Publishing
Company Northbrook IL
Freeze RA and Cherry JA 1979 Groundwater Prentice-Hall Inc Englewood Cliffs
New Jersey
Freyberg DL 1986 A Natural Gradient Experiment on Solute Transport in a Sand Aquifer 2
Spatial Moments and the Advection and Dispersion of Nonreactive Tracers Water
Resources Research Vol 22 pp 2031-2046
Fuss and ONeill Inc 1979 Evaluation of a chemical waste disposal area Tarbox Road site
Plainfield Connecticut January 1979
5797wpdocsgalluprifinaltextmlaquoraquotemfhl061297 7-2 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Gelhar LW Montogluo A Welty C Rehfeldt KE 1985 A Review of Field-Scale
Physical Solute Transport Processes in Saturated and Unsaturated Porous Media Electric
Power Research Institute Report No EA-4190
Geraghty amp Miller Inc 1989 Aqtesolv Aquifer Test Solver Version 11 Reston VA October
1979
Hansch C and AJ Leo 1979 Substituent Constants for Correlations Analysis in Chemistry
and Biology John Wiley amp Sons New York
Hem JD 1989 Study and Interpretation of the Chemical Characteristics of Natural Water (3rd
Edition) USGS Water-Supply Paper 2254 US Government Printing Office
Washington DC
HRP Associates Inc 1993 Addendum to Groundwater Monitoring Report Former Pervel
Industries Flocking Plant March and June 1993 Sampling Events HRP Associates
Inc Plainville Connecticut
Karickhoff SW DS Brown and TA Scott 1979 Sorption of Hydrophobic Pollutants on
Natural Sediments Water Research Vol 13 pp 241-248
Lyman WJ Reehl WF Rosenblatt DH 1982 Handbook of Chemical Property
Estimation Methods-Environmental Behavior of Organic Compounds McGraw-Hill
Metcalf amp Eddy 1993 Final Data Summary Report START Initiative Gallups Quarry Plainfield Connecticut
Morel MM 1983 Principles of Aquatic Chemistry John Wiley amp Sons
Prior T Eaton L and Sperduto M 1995 Habitat Characterization for Gallups Quarry
Superfund Site Plainfield Connecticut United States Department of Interior Fish and
Wildlife Service New England Field Offices Concord NH
Reed PB 1988 National List of Plant Species That Occur in Wetlands Connecticut US Fish
amp Wildlife Service Washington DC NERC-881807 105p
Robertson WD Cherry JA Sudicky EA 1991 Groundwater Contamination from Two
Small Septic Systems on Sand Aquifers Groundwater v 29 no 1 pp 82-92
5797wpdocsgalluprifinaltextmlaquoraquoterrifhl061297 7-3 QST Environmental
Gallups Quarry SuperJUnd Project - Remedial Investigation
Schincariol RA and Schwartz FW 1990 An Experimental Investigation of Variable Density
flow and Mixing in Homogeneous and Heterogeneous Media Water Resources Research
v26 no 10 pp2317-2329
Schwille F 1988 Dense Chlorinated Solvents in Porous and Fractured Media translated from
German and Edited by JF Pankow Lewis Publishers Chelsea Michigan
Shacklette HT and Boerngen JC 1984 Element Concentrations in Soils and Other Surficial
Materials in Conterminous United States USGS Professional Paper 1270 US
Government Printing Office Washington DC
Sudicky EA Cherry JA and Frind EO 1983 Migration of Contaminants in Groundwater
at a Landfill A Case Study 4 A Natural Gradient Dispersion Test J Hydrology v 63
pp 81-108
US EPA 1986 Quality Criteria for Water Office of Water Regulations and Standards
Washington DC USEPA 4405-86-001 (NTIS PB87-226759)
US EPA 1987 A Compendium of Superfund Field Operations Methods US EPA540Pshy
87001 (NTIS No PB88-181557)
US EPA 1988 Interim Final Guidance on Remedial Actions for Contaminated Groundwater at
Superfund Sites US EPA Washington DC
US Fish and Wildlife Service 1995 Habitat Characterization for Gallups Quarry Superfund
Site Plainfield CT Concord NH 16 p
USGS 1993 Geohydrology of the Gallups Quarry Area Plainfield CT
5797wpdocsglaquolluprifinaltextmasterrifhl061297 7-4 QST Environmental
SOURCE PLAINFIELD75 MINUTE
124000
0 A 2
SCALE IN MILES
OONNECnCPT
OlMDIMNGLE LOCATION
CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP SERIES 1983
410 Amherst Street Nashua NH 03063
(603) 689-3737
GALLUPS QUARRY SUPERFUND PROJECT PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 1-1
SITE LOCATION MAP DRAWING NAME 1LOCDWG miE NUMBER 7194-138
SCALE AS SHOW [REVISION 0 I DRAWN BY PAD IPATE gg97
N
500 0 500
SCALE IN FEET
LOT NUMBER OWNER
1 C STANTON GALLUP 2 KENNETH R MOFFITT 3 INTERMARK FABRIC CORP 4 NORMAN ATLAS 5 FREDERICK BARRETT 6 WILLIAM ROPERANNE OWENS 7 ROBERT GLUCK
TILCON MINERALS INC 9 TOWN OF PLAINFIELD 10 ROBERT GLUCK 1 1 STANTON GALLUP 12 - 15 EDWARD DUNCAN 16 ELAINE M NILSON 17 ADOLPH SHAGZDA 18 ANTHONY FATONEJOSEPH FATONE 19 NANCY LAMIRANDE 20 KENNETH R MOFFITT 21 CONNECTICUT DOT 22 ST JOHNS CHURCH 23 DOROTHY CARON 24 ALFRED AND EVELIN RIENDEAU 25 PAUL GELINAS AND JOAN BURNORE 26 ALBERT SR AND ANN WILCOX
LEGEND
D LOT NUMBER
-- WATERCOURSE GALLUPS QUARRY SITE
PROPERTY BOUNDARY
NOTES
BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM - CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
410 Amherst Street Nashua NH 03063
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 1-2 1000
PROPERTY BOUNDARIES AND ADJACENT LANDOWNERS
DRAWING NAM^ PROPBNDDWG |^LE NUMBER 7194 138 SCALE AS SHOW^REVISION 0 |pRAWN BY PAD loATE 5997
GB
N
LEGEND
WATERCOURSE
TO PACKERS POND (CUSS CBc)
APPROX 1 MILE WEST OF SITE
PROPERTY
CLASS Be
BOUNDARY
SURFACE WATER
CLASS BA SURFACE WATER
CLASS GE GROUNDWATER
CLASS GEGA GROUNDWATER
NOTES
1 BASE PLAN PROVIDED BY USEPADATED 14 OCTOBER 1993
DRAWING NO 707600
2 HORIZONTAL DATUM shy CONNECTICUT STATE PLANSYSTEM NORTH AMERICAN
COORDINATE DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROMPLAINFIELD TAX ASSESSORS OFFICE
TOWN OF
4 UNLESS OTHERWISE INDICATEDCLASSIFICATION IS GA
CONNECTICUT GROUNDWATER
410 Amherst Street Nashua MH 030G3
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
500 0
SCALE IN
500
FEET
1000 FIGURE 1-3
CONNECTICUT SURFACE AND GROUNDWATER CLASSIFICATION ZONES
DRAWING NAME SOILTYPEDWG
SCALE AS SfcWN [RFVISION 0 l o R A W N B Y D-fB FILE NUMBER 7194 138
G1097
LEGEND
WATERCOURSE
PROPERTY BOUNDARY
LOCATION OF PREVIOUSLY INSTALLED MONITORING WELL
NOTES
1 BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM shy CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
410 Amherst Street Nashua NH 03063
(603) 869-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
- REMEDIAL INVESTIGATION REPORT
500 0 500 1000 FIGURE 1-4
GROUNDWATER MONITOR WELLS INSTALLED BY SCALE IN FEET FUSS amp ONEILL IN 1978 AND USGS IN 1993
DRAWING NAME SWMAGDWG FILE NUMBER 7194 138
SCALE A3 SHQHW [REVISION 0 [DRAWN BY DJB |DATE 51097
bull- - n V i _raquo-A raquoraquobull bull Jpoundi _
SOURCE PLAINFIELD CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP 75 MINUTE SERIES 1983
124000 410 Amber atNashua NH
Street 03063
(603) 889-3737
0 GALLUPS QUARRY SUPERFUND PROJECT
SCALE IN MILES PLAINFIELD CONNECTICUT REMEDIAL INVESTIGATION REPORT
FIGURE 1-5 COHNgOICOT
SITE LOCATION MAP AND NEARBY INDUSTRIAL PROPERTIES
QURANGLE LOCATION NAME LOCMAPXXDWG FILE NUMBER 7194138
SCALE AS SHOWN [REVISION 0 I DRAWN BY CBG loATE 5997
1450
FIGURE 3-1 GROUNDWATER ELEVATIONS MW-101
1420 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-101S MW-101TT MW-1 01 T
FIGURE 3-2 GROUNDWATER ELEVATIONS MW-102
1450shy
OJ 2
LLJ 1445shy
O CO
1440shyMW-102B WAS NOT INSTALLED UNTIL PHASE IB
1435
LLJ _l HI DC LJJ
I QZ
O cc CD
1430shy
1425shy
1420 010195
1 041195
1 072095
1 102895 020596
I 051596
I 082396
1 120196
1 031197 061997
DATE
MW-102S MW-102TT ---pound-- MW-102B
FIGURE 3-4 GROUNDWATER ELEVATIONS MW-104
1450
CO
LLJ 1445shy
O CO lt |mdash 1440shy
lt 1435shy
LLJ _J LLJ
CC LLJ 1430shy
I Q Z D O CC C5
1425
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-104S MW-104TT
FIGURE 3-5 GROUNDWATER ELEVATIONS MW-105
1450
CO2 LLJ 1445shy
O CO
1440shy
1435shy
LLI
LU tr QJ 1430shy
I Q
D O cc O
1425shy
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-105S MW-105TT MW-105T -X- MW-105B
1450
FIGURE 3-6 GROUNDWATER ELEVATIONS MW-106
1420 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-106S MW-106TT
1450
FIGURE 3-3 GROUNDWATER ELEVATIONS MW-103
1415 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-103S MW-103TT
FIGURE 3-7 GROUNDWATER ELEVATIONS MW-107
1490
CO
x- -X
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-107S MW-107TT MW-107T -Xshy MW-107B
FIGURE 3-8 GROUNDWATER ELEVATIONS MW-108
1465shy
(02 LU
1460shy
O CO
1455shy
1450shy
LU
LU
CC LU
lt
1445shy
1440shy
Q
mdashJocc O
14j vshy^
1430 010195
1 041195
1
072095 1
102895 T T
020596 051596
DATE 082396
1 120196 031197 061997
MW-1083 MW-1 08TT MW-1 08B
1580
FIGURE 3-9 GROUNDWATER ELEVATIONS MW-109
(0 1575shy
1530 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-109S MW-109B
1470
FIGURE 3-10 GROUNDWATER ELEVATIONS MW-110S
1450 i 1 i i i 1 r 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-110S
1610
FIGURE 3-11 GROUNDWATER ELEVATIONS MW-111B
1530 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-111B
1590
FIGURE 3-12 GROUNDWATER ELEVATIONS MW-112
lt) 1580shy
149 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-1123 MW-112T MW-112B
FIGURE 3-13 GROUNDWATER ELEVATIONS MW-113
1510shy
2UJ
O m lt
1500shy
1490shy
1480shy
LU _l LJJ
CC LU
1470shy
1460shy
Q
OCC O
145degH
1440 010195 041195 072095
1 102895 020596 051596
DATE 082396
1 120196
1 031197 061997
MW-113S MW-113B
1580
FIGURE 3-14 GROUNDWATER ELEVATIONS MW-114
1460 i r 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-114S MW-114TT
150
FIGURE 3-15 GROUNDWATER ELEVATIONS MW-115
1465 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-115S MW-115TT --pound-- MW-115B
1455
FIGURE 3-16 GROUNDWATER ELEVATIONS MW-116
1425 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-116S MW-116T
FIGURE 3-17 GROUNDWATER ELEVATIONS MW-117
1480shy
CO
LJJ gto CD
1475shy
1470shy
LU LU
CC LU
1465shy
WELLS AT THIS LOCATION WERE NOT INSTALLED UNTIL PHASE 1B
O z D O CC (5
1460shy
1455 010195
1 041195 072095
I 102895
1 1020596 051596
DATE
1 082396 120196 031197 061997
MW-117S MW-117TT
FIGURE 3-18 GROUNDWATER ELEVATIONS MW-118
1465shy
LU 1440shy
LLJ
CC LU 1435shy WELLS AT THIS LOCATION WERE
I Q Z D O CC CD
1430shy
1425shy
NOT INSTALLED UNTIL PHASE 1B
1420 010195
1 041195
I 072095
1 102895 020596
1 051596
DATE 082396 120196 031197 061997
MW-118S MW-118TT
FIGURE 3-19 GROUNDWATER ELEVATIONS MW-119
1475shy
CO2 LJJ
1470shy
o m
1465shy
1460shy
UJ_i UJ cc LJJ
1455
1450shy
WELLS AT THIS LOCATION WERE NOT INSTALLED UNTIL PHASE 1B
Q Z
O cc O
1445shy
1440 010195 041195
1 072095
I102895
I I 020596 051596
DATE
1 082396
i 1 201 96 031 1 97 061 997
MW-119S MW-119TT
1455
FIGURE 3-20 GROUNDWATER ELEVATIONS SW-3SD
1425 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
SW-3S SW-3D
Originals in color
VERTICAL
PROJECTED FOOTPRINT of FORMER PRIMARY
DISPOSAL AREA
MILL BROOK
NOTES (1)
(2)(3)
THE SAME CONTOUR INTERVALS ARE USED FOR THE SHALLOW AND DEEP MAPS
WATER LEVEL DATA COLLECTED 2-2-95 VERTICAL EXAGGERATION = 10X
410 Amherst Street THIS FIGURE SHOWS ONLY THE PREDOMINANT OVERBURDEN GROUNDWATER FLOW PATHWAYS WHICH ORIGINATE Nashua NH 03063 IN THE VICINTY OF THE FORMER PRIMARY DISPOSAL AREA AS VIEWED FROM THE EAST (603) 889-3737
ALTHOUGH THIS DEPICTION IS BAStU ON PlEZOMETRlC HEAD OAiA (MEASURED ON FEBRUARY 2 1335) THIS FiGURE DOES NOT SHOW EVERY POSSIBLE FLOW PATHWAY WITHIN THE OVERBURDEN AQUIFER THE UPPER SURFACE REPRESENTS THE SURFACE OF THE WATER TABLE THE LOWER SURFACE REPRESENTS GALLUPS QUARRY SUPERFUND SITE A PLANE DEFINED BY THE PIEZOMETRIC HEAD AS MEASURED IN WELLS WHICH ARE SCREENED IN THE LOWER PORTION OF THE OVERBURDEN AQUIFER THE LOWER PLANE DOES NOT REPRESENT THE LOWER BOUNDARY OF THE OVERBURDEN AQUIFER AND NEITHER PLANE IS GEOLOGICALLY SPECIFIC PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 3-21
PREDOMINANT OVERBURDEN GROUNDWATER FLOW PATHWAYS IN NORTHERN PORTION OF STUDY AREA
DRAWING NAME FLOWPATHDWG IFILE NUMBER 7194 138
SCALE NT5 JREVSION 1 JDRAWN BY CBG [DATE 6-9-97~
lt 4 Original includes color coding
10s r SW-17SandMW105S Ho5 SW-17D and MW105TT
P 1 V |
1deg4 i
4 mI U 5 k 4 3
i i f J |103 1I Un |
|io2 bull m2
bull I U = i ii gtv o r
BDL mdasha I bullM BDL a i i c CM ltD 0 ltj at agt c c at at T c I 1 I i i i
SW-13 c MW105S I10s pound
1I Un =
m4
104 I U sect
J 1I 3 bull PCE -m
H103| IU sect bull TCA
2 ^ TCE 102
m
I bull 1 2-DCE A i 1
T VINYL CHLORIDE 1 0 ^h
bull A1
10deg BDL = BELOW DETECTION LIMIT 10deg 1 U = V 3 X
=
ni-M ^ ^ ^ laquote BDL 0 V o0 CV tfi _ CO CXgt o0 ogt ogt 2 C oraquo oraquo cn O) O lt C
i- r- -3 4 1 1995
MW105TT MW107TT 105 105
E pound
i shy104
2 = 104 I = ^^to^f^P 410 Araherst Street bull^OJfcCfe Nashua NH 03063 103 103 ^raquo^^^j^ (603) 889-3737 f bull 1
- T T T shy ~ A102 i1 bull bull S 102
GALLUPS QUARR y SUPERFUND SITE I 1
PLAINFIELD CONNECTICUT REMEDIAL INVEi iTIGATOJV REPORT 10 101
i 1 FIGU RE 5 110deg i = 10deg
BDL laquo BDL VOC CONCENTRATION CHANGES VERSUS TIME M
^ i DOWNGRADIENT FROM FORt ilER PRIMARY DISPOSAL AREA sect o ^ O
^
-5lt 5amp -s= z1
1995 1995
Original includes color coding
CO
NC
ENTR
ATIO
N (
ppb)
IU sect MW102S
s 105 MW102TT
104 1 i 104
103 1 103
102 I I A sect 102
1
A
T
1 101
10deg i 10deg
nni BDL +shytr a O o
1995 1995
bull PCE
bull TCA A TCE
bull 12-DCE
T VINYL CHLORIDE
MW101TT 105
104
103
102
10deg
BDL
1995
410 Amhersl Street Nashua NH 03063
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 5-2
VOC CONCENTRATION CHANGES VERSUS TIME DOWNGRADIENT PORTION OF PLUME
BDL = BELOW DETECTION LIMIT
s
104 tmdash a IU I
1 IU103 U-o 1F= E
i 105 to2 tmdash r 1 1deg1 i~ deg 10degL
BDL Emdash oS
105 i
104 i
103 i
102 bull
101 1
10deg
BDL 0S
105 9
104 B
103 I
102 i
101
10deg 1
BDL OCOogt
^ 00 ogt
^ra lt cltJgt
C O 0 0
0gt
MW-A
4 bull
1 1 1
co 01
MW-B
_J 1 1
1
i CO
8)
MW-C
11 1
lt lt
CO CO ogt
bullbull
laquoftr i i bull i
mn
Tbull1
bullbull
bull i
9
bull
bullM bullM bullbull- 1
egt lt t a) a
aai Tshy^
WM cN gjcI) lt J1
bull 1
bull 11 1
MM bullMl bullfr- 1
c4 0aigt C
t bullgt araquo lt raquo
T ^
Original includes color coding
10 |
-iM 10 s
-irvS 10 |
nn2 10
bullm1 bull
1UJ
oni AZs
^^^f
MW116T
A a
A =J =3
1995
bull
bullA
PCE
TCA
TCE
1 2-DCE
sect
1
s
I I 1
A gti
T VINYL CHLORIDE
BDL = BELOW DETECTION LIMIT
410 Amherst Street bull^OJUV^ Nashua NH 03063 ^raquo^^ ^jj^ (603) 889 3737
nmranmini x
GALLOPS QlARRy SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 5-3
VOC CONCENTRATION CHANGES VERSUS TIME AREA NORTH-NORTHEAST OF PLUME
I Original includes color coding
SW-17S MW102S and MW102TT
410 Amherst Street Nashua NH 03063
bull PCE (603) 889-3737
bull TCA A GALLUPS QUARRY SUPERFUND SITE TCE
PLAINFIELD CONNECTICUT REMEDIAL INVESTIGATION REPORT
BDL = BELOW DETECTION LIMIT
FIGURE 5-4
EVALUATION OF BIODEGRADAT10N AND RAINWATER DILUTION RATES IN VOC PLUME
(D NOTE FORWELLS MW102S and MW102TT ONLY JANUARY and NOVEMBER 1995 DATA ARE PLOTTED
Gallups Quarry Superfund Project - RI Executive Summary
Executive Summary
EI Purpose of the Report This document presents the Remedial Investigation (RI) Report which was completed for the
Gallups Quarry Superfund Site (Site) pursuant to the requirements of US Environmental Protection Agency (EPA) Administrative Order by Consent Docket Number 1-93-1080 (Order)
issued September 7 1993 The Site is a former sand and gravel quarry and is located on Tarbox
Road in the Town of Plainfield Connecticut (see Figure E-l) The Study Area includes the Site
as well as areas west and north of the Site
Investigation of the Site was initiated in 1978 when unlicensed waste disposal operations were
discovered at the property Emergency clean-up operations were conducted in three disposal
areas by the Connecticut Department of Environmental Protection (CTDEP) in April 1978
(Metcalf amp Eddy 1993) Following the initial clean-up effort a series of surface and subsurface
sampling events were performed by the CTDEP the Connecticut Department of Health (CTDOH) and US Environmental Protection Agency (EPA) Based primarily on the detection of
groundwater contamination the Site was listed on the National Priorities List (NPL) on October 4 1989 During 1992 and 1993 EPA conducted a limited investigation through the Superfund
Technical Assessment amp Response Team (START) initiative in an effort to expedite the
completion of the Remedial InvestigationFeasibility Study (RIFS) The requirements of the
Order as well as data included in the START report (Metcalf amp Eddy 1993) provided the
framework for the Remedial Investigation
This RI Report is the sixteenth major deliverable under the Order The first major deliverable
the Remedial InvestigationFeasibility Study Work Plan - Phase 1A was finalized and submitted to EPA on August 29 1994 QST Environmental (formerly Environmental Science amp Engineering Inc (ESE)) finalized the Work Plan and has prepared all of the other deliverables
The Phase 1A field investigation was completed in January 1995 The second major deliverable
the Phase 1A Data Report dated March 24 1995 was submitted to EPA following completion of
the Phase 1A field investigation The findings of the Phase 1A Investigation were described in
the Initial Site Characterization Report (ISCR) which was finalized and submitted to EPA on
March 1 1996 A Work Plan for the Phase IB field investigation was finalized and submitted on
October 11 1995
In addition to the Phase 1A field investigation the Phase 1A Work Plan also described the Long-
Term Monitoring Program which was initiated upon completion of the Phase 1A field
investigation The Long-Term Monitoring Program includes the quarterly collection and analysis
of groundwater and semi-annual collection and analysis of surface water and nearby residential
well samples The Phase IB field investigation commenced on October 12 1995 Following the
5797wpdocsglaquollupfsfinlaquoltextexecnimmri060997 E-l QST Environmental
SOURCE PLAINFIELD CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP 75 MINUTE SERIES 1983
410 Amherst Street 124000 Nashua NH 03063
(603) 889-3737
0 GALLUPS QUARRY SUPERFUND PROJECT
PLAINFIELD CONNECTICUT SCALE IN MILES REMEDIAL INVESTIGATION REPORT
comacncur FIGURE E-l
SITE LOCATION MAP DRAWING NAME ELOCDWG FILE NUMBER 7194-138
QUADRANGLE LOCATION
SCALE AS SHOWN REVISION 0 I DRAWN BY PAP [DATE 5997
Gallups Quarry Superand Project - RI Executive Summary
completion of drilling activities the Phase IB groundwater sampling task and the fourth quarter
1995 Long-Term Monitoring sampling event were performed simultaneously in November 1995
Seven Data Reports have been submitted to the EPA for the following Long-Term Monitoring
Program sampling events the second and third quarters of 1995 all four quarters of 1996 and
the first quarter of 1997 (ESE 1996a 1996b 1996c 1997a 1997b) The draft RI Report was
submitted to EPA on March 15 1996 (and revised and resubmitted October 22 1996) and included the results of the fourth quarter of 1995 sampling event On March 29 1996 the
following two deliverables were submitted to EPA Development and Initial Screening of Alternatives Report and Detailed Analysis Work Plan The draft Feasibility Study was submitted
to EPA on January 27 1997 This RI Report describes the methods and findings of both the Phase 1A and IB field studies and includes data collected during the April July and November
1995 February May August and November 1996 and February 1997 Long-Term Monitoring
sampling events
E2 Site Background E21 Area Description
The 29-acre Gallups Quarry Site is located on the north side of Tarbox Road in the Town of
Plainfield Windham County Connecticut The Site which is currently vacant is bounded by
wooded areas and wetlands associated with Mill Brook (which flows from east to west
approximately 250 feet north of the Site) single-family residences and several commercial
properties Approximately 700 feet north of the Site on the opposite side of Mill Brook is an industrial park which contains an Intermark Fabric Corporation facility (formerly the Pervel
Industries flock plant) and a Safety Kleen Corporation accumulation facility Further north of the
industrial park are several presently vacant mill buildings which were previously occupied by various manufacturers including Pervel Industries and the InterRoyal Corporation The Plainfield sewage treatment plant which discharges to Mill Brook and its major tributary (Fry Brook) is
located approximately 1800 feet northwest of the property
E22 Site Operational History
Limited information is available regarding the early operational history of the Site Historical
aerial photographs and records at the Town of Plainfield Assessors office indicate that in 1951
the Site was owned by a Mr Johnson and that some quarrying activities were underway in the
southern portion of the Site In 1964 the Site was purchased by C Stanton Gallup Although
detailed usage of the Site from 1964 through 1977 is poorly documented records indicate that the
Site was used as a source of aggregate and was occupied by the Connecticut Department of
Transportation (CTDOT) who were operating an asphalt batching plant
5797WTgtdocsgallupfsfinltextexec8ummri060997 E-3 QST Environmental
Gallups Quarry Superfund Project - RI Executive Summary
As a result of complaints from neighboring residents the CTDEP and the Connecticut State
Police initiated an investigation of the Site in January of 1978 The CTDEP investigation
concluded that the Site was used from the summer of 1977 until December 1977 for unlicensed
waste disposal Evidence collected by CTDEP indicates that Chemical Waste Removal Inc
(CWR) of Bridgeport Connecticut transported drummed and bulk liquid waste material to the
Site These materials reportedly included a variety of industrial wastes
Emergency clean up efforts were performed during the summer of 1978 under the direction of the
CTDEP and the Connecticut State Police This involved the removal and off-site disposal of
1584 drums 5000 gallons of free liquid and 2277 cubic yards of contaminated soil from three
distinct locations on the Site The drums as well as liquid waste and contaminated soil were
removed from the Primary and Secondary Disposal Areas located in the northern portion of the
Site Remedial measures performed at the Seepage Bed reportedly located in the central portion
of the Site included the excavation of contaminated soil and in-situ treatment of remaining soils
through the addition of 20 tons of lime A buried inverted dump truck body was also reportedly
removed from the Site In addition to these remedial activities mine detectors were utilized to search for additional buried drums There was no evidence of additional buried drums and it
was believed that all drums were recovered during the cleanup operations
Since the 1978 cleanup operations the Site has been vacant although there are some indications
that the Site has been utilized by trespassers for recreational purposes
E23 Summary of Previous Investigation
ations and sampling events were conducted at the Gallups Quarry Site The significant previous
investigations are as follows
bull A general site investigation performed on behalf of the State of Connecticut (Fuss amp
ONeill 1979) which included the installation of 22 monitoring wells 19 test pits (13
of which were completed as shallow monitoring wells) and the collection of surface
water and sediment samples The investigation was completed within several months
of the States remedial efforts described above Groundwater from monitoring wells
and nearby residential wells as well as surface water from Mill Brook was sampled
several times from the period of July to December 1978
bull Various CTDEP monitoring events for groundwater surface water and sediment
occurred from 1979 until 1993 Sampling events were conducted in October 1979
January and November 1980 April and October 1981 April 1982 and December
1983 CTDEP also performed a biodiversity survey in 1985 in an effort to evaluate
potential impacts to the Mill Brook wetland In addition CTDEP also conducted
sampling anq (analysis of neighboring residential wells in 1992 and 1993
5797wpdocraquogallupf8finlaquoltextexecsummri060997 E-4 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
bull A Hazard Ranking System (HRS) Study was completed in 1987 by NUS Corporation
foi ZPA The Study included the collection of water samples from two existing
moiiitoring wells and three surface watersediment locations
bull A review of historic aerial photographs of the Study Area was performed by the
Bionetics Corporation on behalf of the EPA Photographs dating back to 1951 were
included in the review which was published in 1990 (Bionetics Corp 1990)
bull In cooperation with EPA the USGS performed a geohydrologic investigation at the
Study Area in 1993 This investigation included geophysical surveys (EM-34 and GPR) to characterize various subsurface features One monitoring well was installed
bull In 1993 the US Fish and Wildlife Service performed a field study to characterize the
habitats within the Study Area The study was finalized in 1995
bull Various sampling events were conducted in 1989 and 1993 on behalf of the EPA During these sampling events groundwater from existing monitoring wells and nearby
residential wells as well as surface soil samples were collected for analysis
The significant findings of these investigations are summarized as follows
bull The initial study completed at the Site by Fuss amp ONeill in 1979 concluded that
groundwater in the vicinity of the former disposal areas had been impacted by certain
volatile organic compounds (VOC) and metals A well-defined groundwater plume which contained these various constituents extended in a northwest direction away
from the Site
bull Periodic CTDEP sampling events from 1979-1982 indicated the wells downgradient of
the former disposal areas consistently showed detectable levels of constituents similar
to those disposed of on-site The results of CTDEP sampling events indicated that
nearby residential wells had not been impacted by the Site
bull The USGS study provided an updated geological characterization of the Study Area
and suggested the potential presence of a bedrock fault zone located in the vicinity of
the Former Seepage Bed
bull The results of the 1989 and 1993 sampling events generally confirmed the findings of
previous groundwater quality investigations and indicated that VOC concentrations
decreased significantly in the period between 1982 and 1993
5797wpdocgglaquollupfsfiiultextexecnjmmri060997 E-5 QST Environmental
Gallups Quarry Superfiotd Project - RI Executive Summary
To supplement historical data and data obtained during the Phase 1A field program a CTDEP file
search was performed to obtain information pertinent to groundwater contamination for industrial
properties neighboring the Site The available information indicates that
bull two separate companies Pervel Industries and InterRoyal Corporation operated
manufacturing facilities at locations approximately 2500 feet north of the Site
bull Pervel Industries also maintained a second facility (a fabric flock plant) located
approximately 1000 feet north of the Site across Mill Brook
bull there have been documented releases of 111-trichloroethane (TCA) and toluene at
the northern-most Pervel plant
bull contaminated soil and sediment associated with a 1985 spill of 111-TCA at the
northern-most Pervel facility was stored in an impoundment located on the eastern
(upgradient) side of the Pervel flock plant property
bull the contaminated soilsediment impoundment was located approximately 1000 feet
from the northern end of the Site
bull the results of historical groundwater monitoring at the former Pervel flock plant
located a few hundred feet north of the Site show the presence of elevated
concentrations of several VOC including tetrachloroethene (PCE) and TCA
E3 Summary of Remedial Investigations Phase 1A Field Investigations
In order to maximize the efficiency of the Site characterization program for the Gallups Quarry
Site multiple phases of data collection and evaluation were performed during the Phase 1A field
program Screening level surveys completed during the initial weeks of the field program
utilizing fast-turnaround data generation and evaluation techniques were used to focus data
collection efforts during the latter part of the Phase 1A field program The screening surveys
included
bull A visual site reconnaissance involving transit by foot and direct observations and
photographic documentation of significant features along approximately 39000 feet of
trend lines covering the entire Site
bull Geophysical surveys including electromagnetic terrain conductivity (EM) and
magnetometer surveys along 25-foot spaced trend lines totalling approximately
5797wpdocBgallupf8finaltextexeclaquoummri060997 E-6 Q5T Environmental
Gallups Quarry Superfimd Project - Rl Executive Summary
39000 feet in length and covering the entire Site follow-up EM-31 and
magnetometer surveys and a test pit program in three areas where anomalies were
observed and a seismic refraction survey west of the Former Seepage Bed
bull A microwell survey which included the collection of 126 groundwater samples from
multiple depths at 50 locations within the Study Area field gas chromatograph
analyses of all of these samples for an indicator list of 8 VOC laboratory analyses of
121 of these samples for metals and 12 of the samples for VOC and
bull A soil vapor survey which involved the collection of soil vapor samples from 106
locations throughout the Site and on-site analyses for an indicator list of 8 VOC
Based on these screening level and historical data a groundwater monitoring well installation
sampling and analytical program was designed The program as approved by EPA included the
following
bull The installation of 5 wells at 2 designated background locations These wells include
a shallow overburden and a bedrock well in the northern portion of the Site and two
overburden wells (screened at the water table and in a deeper till horizon) and a
bedrock well in the southern portion of the Site Background soil and groundwater
samples were collected from these locations
bull The installation of 19 wells at seven locations downgradient (northwest) of the Former
Primary and Secondary Disposal Areas to assess and define the boundaries of a
contaminant plume identified during the microwell survey These wells included 17
overburden wells and two bedrock wells
bull The installation of six wells at three locations located north and east of the Former
Primary Disposal Area to assess groundwater quality and flow directions in these
areas These wells included five wells screened in overburden and one in bedrock
bull The installation of two bedrock wells and one overburden well at two locations in the
vicinity of the Former Seepage Bed This included one bedrock well placed within an
inferred bedrock faultfracture zone to assess the zones potential to act as a preferred
contaminant transport pathway
bull The installation of five wells at two locations in the southern portion of the Site to
assess very limited screening-level VOC detections in this portion of the property
These wells include four overburden wells (two shallow and two top-of-till) and one
5797wpdoclaquoglaquollupftfinlaquolte)rtexecraquoummri060997 E-7 QST Environmental
Gallups Quarry Superfund Project - RI Executive Summary
bedrock well In addition six groundwater piezometers were installed to assess groundwater flow directions in the southern portion of the Study Area gtmdashr
Samples from three of the newly installed wells (MW102TT MW106TT and MW116T) were analyzed for Appendix IX parameters Samples from the remaining newly installed monitoring wells and three existing wells (SW-9 SW-10 SW-12) were analyzed for Target Analyte ListTarget Compound List (TALTCL) parameters Twelve nearby residential wells were also sampled for TALTCL parameters (although VOC were analyzed using EPA method 5242) In addition to the monitoring well installation and groundwater sampling program outlined above the following tasks were performed during the Phase 1A field program
bull Air quality monitoring to establish ambient air quality prior to and during the intrusive investigations A total of eight air monitoring stations were established at locations within and at the Site perimeter
bull Water-level measurements were recorded to assess horizontal and vertical groundwater flow directions and aquifer testing (including evaluations of the remaining existing monitoring wells) using slug tests was conducted to assess the hydraulic conductivity of the aquifer
bull Soil boring programs within the three known disposal areas to assess the nature and extent of residual contamination A total of ten soil borings were completed at the three areas Each boring was continuously sampled and terminated at auger refusal Selected samples were submitted for laboratory analysis for TALTCL parameters based on lithology depth and photoionization detector (PID) headspace readings as set forth in the Work Plan
bull Surface watersediment sampling was performed at 17 locations including Mill Brook Fry Brook Packers Pond and in an unnamed pond on Tarbox Road just south of the entrance to the Site In addition wetland soil samples were collected from 10 locations within the Study Area All samples were submitted for analysis for TALTCL parameters
bull Federal and State jurisdiction^ wetland delineations were performed
Phase IB Field Investigations The data collected during Phase 1A was supplemented with the following additional investigative activities conducted during the Phase IB field investigation
5797wpdocsgallupfsfiMltextexecsummri060997 E-8 QST Environmental
Gallups Quarry Superand Project - RI Executive Summary
bull Quantitative air monitoring for site-specific compounds in the vicinity of the Former
Prirary Disposal Area
bull Collection and analysis of soil samples from six additional soil borings in the Former
Primary Disposal Area to more fully characterize the extent of residual VOC and PCB
contamination
bull The installation of seven additional groundwater monitoring wells and one additional
piezometer to obtain additional groundwater data from the downgradient portion of the
plume and from the northnorthwest portion of the Site The monitoring wells
included (3) two well clusters and (1) bedrock well
bull Collection of groundwater samples from each new monitoring well and from five
existing wells on the former Pervel facility and analysis of these samples for VOC to confirm the downgradient extent of the plume originating in the Former Primary
Disposal Area and
bull The performance of constant flow tests consisting of short-term pumping tests on selected groundwater monitoring wells to supplement Phase 1A hydraulic conductivity
data so that groundwater velocities and transport rates and aquifer yield could be
more accurately determined
Long-Term Monitoring Program
A Long Term Monitoring Program was initiated upon completion of the Phase 1A field investigation The Long-Term Monitoring Program includes the quarterly collection and analysis
of groundwater and semi-annual collection and analysis of surface water and nearby residential
well samples Data from eight quarterly sampling rounds (performed in April July and
November 1995 February May August and November 1996 and February 1997) are presented
and discussed The Conceptual Model discussion is based on the 1995 quarterly sampling rounds
Any minor adjustments to the Conceptual Model resulting from later monitoring rounds are
addressed in the FS
E4 Conceptual Model of the Study Area E41 Physical Characteristics E411 Physiography
The Site is located along the eastern border of the Quinebaug Valley Lowland The region is
characterized by relatively low relief and numerous glacial features The regional landscape is
5797wpdoc8glaquollupfBfinaltextexecraquoummri060997 E-9 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
significantly influenced by the structure of the underlying crystalline metamorphic bedrock The
topography of the Site is highly irregular primarily due to past quarrying operations including
numerous overgrown mounds of earthen materials and excavated depressions The ground
surface on the Site generally slopes from the east to the west and to a large degree is controlled by the underlying bedrock surface North and west of the Site the ground surface elevation
decreases in the Mill Brook floodplain which is described as a low lying heavily vegetated
wetland
E412 Geology
The overburden deposits in the area consist of materials deposited as a result of glacial processes during the Pleistocene epoch A range of glacially-derived materials including till meltwater or
stratified drift deposits and post-glacial deposits of floodplain alluvium comprise the major
surficial geologic units in the vicinity of the Site The significant surficial deposits encountered
within the Study Area during the RI are till and stratified drift Stratified drift deposits can be
further broken down into coarser-grained or finer-grained components The Study Area is
dominated by coarser-grained deposits which represent various ice-contact or outwash features associated with the retreat of the ice-mass Finer-grained components also exist to a limited
extent within the Study Area and are the result of lacustrine deposition which occurred when
low-lying areas were inundated by a glacial lake Much of the Sites overburden geology
represents the transition of depositional environments as the glacier progressively retreated from
the area Although alluvial floodplain deposits were encountered at locations within the present
Mill Brook floodplain the significance of these deposits is minor
The thickness of the stratified drift deposits range from non-existent in the vicinity of bedrock
outcrops in the eastern portion of the Site to approximately 70 feet The overburden thickness
increases in response to a decrease in the elevation of the bedrock surface Till was encountered just above the bedrock surface at nearly every location The till horizon ranges in thickness from
approximately 10 to 20 feet with the thickest accumulations located along bedrock highs
Surficial exposures of glacial till were observed on the Site The till is relatively dense and is
comprised of a fine sandy matrix with abundant gravel cobbles and boulders
Bedrock in the vicinity of the Site mapped as a lower member of the Quinebaug Formation
consists of hornblende gneiss biotite gneiss and amphibolite and is strongly faulted and folded
exhibiting varying degrees of mylonitization Geophysical surveys performed prior to and during
the Phase 1A field program indicate that a northwest-trending fracture zone may extend across the
central portion of the Site Based on the drilling program depths to bedrock range from zero to
83 feet below ground surface within the Study Area Bedrock elevations are greatest in the
eastern central portion of the Site and decrease to the north and west and to a lesser degree to
the south
5797wpdocsgallupfsfinaltextexecsummri060997 E-10 QSTEnvironmental
Gallups Quarry Superfund Project - RI Executive Summary
E413 Hydrogeology
E4131 Hydraulic Conductivity
The hydraulic conductivity distributions within the overburden and bedrock formations were
evaluated through the performance of constant flow (pumping) tests and rising and falling head
slug tests Hydraulic conductivity measurements indicate that coarse-grained stratified drift
deposits in the lower portion of the aquifer are the most permeable subsurface materials in the Study Area with a mean hydraulic conductivity of 0005 centimeters per second (cms) The
highest hydraulic conductivities were found in the lower portion of the aquifer northwest of the Former Primary Disposal Area where the mean hydraulic conductivity is 0037 cms The mean
hydraulic conductivity of the finer-grained deposits in the upper portion of the aquifer is about
0001 cms
The mean hydraulic conductivity for the till wells (000047 cms) is a factor of ten less than the
average value for coarse stratified drift and varies between 00002 cms and 0002 cms The till
appears to be hydrogeologically distinct from the other overburden deposits and on the average
provides increased resistance to groundwater flow This added resistance is not considered to be
significant however because the consistency of the till and overburden deposits are highly
variable and the hydraulic conductivity contrast is relatively small The slug test results for the
bedrock wells yield the lowest (000018 cms) average hydraulic conductivity
E4132 Groundwater Flow
Horizontal Flow
Overburden groundwater flow south of the Former Seepage Bed is primarily east to west and is
influenced by two factors (1) the slope of the bedrock surface which defines the base of the
unconsolidated deposits and (2) regional hydrologic drainage patterns The average east-west horizontal hydraulic gradient in the southern portion of the Study Area is approximately 001 feet
per foot (feet change in piezometric head per horizontal foot of distance)
In the northern portion of the Study Area three hydrogeologically distinct zones exist South of the Former Primary and Secondary Disposal Areas the hydraulic gradient is steep (approximately
003 feet per foot) and is strongly influenced by the dip of the bedrock surface (01 feet per foot)
The saturated thickness increases from zero south of well MW109 to about 20 to 30 feet near the
former disposal areas North-northwest of the former disposal areas the hydraulic gradient
lessens significantly to a range of 00003 to 00007 feet per foot representing a factor of 40 to
100 reduction North-northeast of Mill Brook the hydraulic gradient is about 0007 feet per foot
Available data indicate that currently northwest of the railroad tracks groundwater flow in the middle to lower portions of the aquifer converges from the northeast and southwest toward a
centerline area generally defined in the downgradient direction by wells MW105 MW102 and
5797wpdoclaquoglaquoliupfraquofirultextexeclaquoummri060997 E-ll QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
MW101 The flow direction near these wells is from the former disposal areas to the northwest
Northeast of this centerline groundwater flows in a southwesterly direction from the vicinity of
Mill Brook and the former Pervel flock plant North of Mill Brook and west of the railroad
tracks the predominant groundwater flow direction becomes more westerly
No significant seasonal changes in horizontal groundwater flow directions were observed in the
Study Area Groundwater levels were generally highest in January 1995 and decreased by about
two feet through the period ending on July 11 1995 Levels then increased by about one foot
from July to November
General overburden groundwater pathlines for the northern portion of the Site are shown on
Figure E-2
Groundwater in bedrock moves primarily in a westerly direction south of the Former Seepage
Bed while in the northern Study Area the predominant bedrock flow component is toward the
northwest In both areas the hydraulic gradient is on the order of 002 feet per foot Groundwater in bedrock near the Former Seepage Bed flows to the northwest and exhibits no apparent
influence from the locally identified fracture zones
Vertical Flow
Vertical flow of groundwater is an important component in the upper several feet of the bedrock
unit Water level measurements indicate that groundwater is discharging from bedrock into the
overburden at every location measured except MW109 In most clusters the vertical hydraulic
gradient between bedrock and overburden is an order of magnitude greater than the horizontal
gradient
In the overburden aquifer the downward vertical flow component is significant within shallow
deposits near the Former Primary Disposal Area (wells MW107 MW108 and MW116) and the
upward flow is important in the upper portion of the aquifer near Mill Brook The downward
groundwater flow within the Former Primary Disposal Area appears to be primarily associated
with infiltration of precipitation and collection of surface water runoff from upland areas This
causes VOC concentrations to be highest in the middle to lower portions of the aquifer Stream
5797wpdocsgallupftfinaltextexecsummri060997 E-12 QST Environmental
N
LEGEND
WATERCOURSE
PROPERTY BOUNDARY
bullPIEZOMETRIC HEAD CONTOUR LOWER PORTION OF AQUIFER NOVEMBER 6 1995 (FEET)
GROUNDWATER PATHLINE
NOTES
1 BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM - CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
400 400 800
SCALE IN FEET
410 Amherst Street Nashua NH 03063
(603) 889-3737 UmHOHHM
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE E-2
SJjTff WIDE GROUNDWATER FLOW DRAWING NAM6 RIWIDEFWDWG FILE NUMBER 7194 138
SCALEAS SHAWN REVISION 1 DRAWN BY DJB DATE 5997
Gallups Quarry Superfiind Project - RI Executive Summary
piezometer data and groundwater flow modeling indicate that Mill Brook generally gains water
from the overburden aquifer within the Study Area
E414 Ecology
Wetlands delineations were performed to the extreme northern and western boundaries of the
Study Area up to the Mill Brook channel using both the State of Connecticuts accepted criteria
(which focuses on soil types and hydric soil characteristics) and the Federal criteria using US
Army Corps of Engineer methods (which includes the examination of vegetation hydrology and
soils) Most of the wetlandupland boundary occurs along the edge of a steep grade The sharp
relief produces a narrow transition between uplands and wetlands The delineated lines reflect
this as the State and USACOE wetland boundaries coincide at nearly every location With the
exception of an area intersecting a small portion of the Site at the northernmost edge of the
property east of the former disposal areas no wetland areas were identified on the Site
A preliminary identification of plant and animal species present in the Study Area was conducted during the wetlands delineation A limited number of wildlife species were observed Numerous
plant species were identified over the heavily vegetated Study Area No endangered species were
observed nor are reported to reside in the Study Area
E42 Nature and Extent of Contamination
E421 Contaminant Source Investigation The following summarizes the findings of contaminant source investigations conducted during the
RI program
bull Previous remedial activities have completely removed the waste materials (intact drums and bulk liquid waste) from the Site
bull The Former Seepage Bed and the Former Secondary Disposal Area contain
little residual contamination from the disposal activities which occurred in the
late 1970s
bull Residual levels of contamination primarily VOC and PCB were measured in
the Former Primary Disposal Area In general the highest levels of VOC are
located at or just below the groundwater table in native soils immediately
beneath the fill materials and diminish rapidly with depth Low levels of
PCB were detected primarily within shallow fill materials
5797wpdocraquogallupftfinlaquoltextexecraquoummri060997 E-14 QST Environmental
Gallups Quarry Superfiutd Project - Rl Executive Summary
bull Other than the three known former disposal areas and the remains of a
former CTDOT asphalt plant no other disposal areas were found to exist on -
the Site
E422 Groundwater Quality
Groundwater quality data collected during the Remedial Investigation indicate the following
bull No significant groundwater contamination was detected within the overburden
or bedrock units in either the southern Study Area or in the vicinity of the
Former Seepage Bed
bull In the northern Study Area a narrow low to moderate-concentration VOC
plume was detected in the overburden aquifer extending from the vicinity of
the Former Primary Disposal Area to the northwest towards Mill Brook
TCA and DCE were consistently detected at all locations along the plume
centerline at concentrations as high as 240 ppb and 1300 ppb respectively
bull Comparison of present concentrations with historical data indicate that VOC
levels are significantly decreasing with time From 1978 through 1995 TCA
TCE and PCE concentrations have decreased on the average by more than a
factor of two every two years representing environmental half-lives of less
than two years
bull The size and orientation of the plume are in excellent agreement with the
established groundwater flow directions
bull Available information indicates that the leading edge of the VOC plume
associated with the Former Primary Disposal Area is located in the vicinity of
monitoring well clusters MW-102 and MW-101 Concentrations of TCA and
DCE reduce to below MCLs at MW-101 Contaminant migration rates also
support this delineation of the front of the site-related VOC plume
bull Increasing PCE detections in the downgradient portion of the plume exhibit
inconsistencies with calculated migration rates from the Site Groundwater
flow directions VOC transport rates and historical concentration trends
indicate that PCE detections in wells MW118 MW116 MW103 MW118
MW102 and MW101 may be associated with contaminant transport from the
former Pervel flock plant However it is also possible that the PCE
detections at locations MW102 and MW101 are attributable to the former
disposal areas In addition contaminated groundwater from Pervel may have
5797wpdocsgal]upfraquofinaltextexeclaquoummri060997 E-15 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
also contributed TCA TCE DCE and vinyl chloride to the site related VOC
plume
Results of surface watersediment sampling and analyses stream piezometer measurements and groundwater flow modeling indicate that some discharge
of the shallow portion of the plume into Mill Brook is occurring However
the concentrations of VOC detected in the brook are well below those
reported to cause adverse effects in fish or wildlife
Bedrock is not considered a preferred pathway for contaminant migration due
to its characteristically low hydraulic conductivity and the predominantly
upward component of groundwater flow from bedrock to overburden which
exists throughout the Study Area
5797wpdocsgallupftfinlaquoltcxtexec8ummri060997 E-16 QfT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents
Section Page
10 Introduction bdquo 1-1
11 Purpose of the Report 1-1 12 Report Organization 1-2
13 Site Background 1-3 131 Area Description Demography and Land Use 1-3 132 Operational History 1-5
133 Summary of Previous Investigations 1-7
20 Field Investigations 2-1
21 Site Survey 2-1
211 Initial Site Survey 2-1
212 As-Installed Survey 2-1
22 Site Reconnaissance 2-2
221 Visual Observations of the Ground Surface 2-2
222 Air Quality Survey 2-2
223 Exclusion Zone Identification 2-4
224 Project Support Measures 2-4
225 Identification of Sensitive Human Receptors 2-5
23 Geophysical Surveys 2-5
231 Electromagnetic Terrain Conductivity (EM) Survey 2-7 232 Magnetometer (MAG) Survey 2-7
233 Additional EM and MAG Surveys 2-8
234 Seismic Refraction Survey 2-8
24 Groundwater Sampling Using Temporary Well Points 2-9
25 Soil Gas Survey 2-12
26 Soil Borings at Disposal Areas 2-15
261 Phase 1A Soil Borings 2-15
262 Phase IB Soil Borings 2-16 27 Installation of Monitoring Wells and Background Soils Sampling 2-17
271 Phase 1A Monitoring Well Placement-Rationale 2-19
272 Phase IB Monitoring Well Placement-Rationale 2-21
273 General Monitoring Well Installation Techniques 2-22
274 Stream Piezometers and Gauges 2-24
5797wpdocsgalluprifinaltextmarterrifhl061297 i QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
Table of Contents (continued)
275 Groundwater Piezometers 2-25
28 Aquifer Parameter Testing 2-25
281 Grain Size Analysis 2-25
282 Slug Tests 2-26
283 Constant Flow Tests 2-26
29 Groundwater Sampling 2-26
291 Monitoring Wells 2-27
292 Residential Wells 2-29
210 Surface Water and Sediment Sampling 2-29
211 Wetland Soil Sampling 2-31
212 Evaluation of Existing Monitoring Wells 2-31
213 Ecological Assessment 2-32
2131 Wetland Delineation 2-32 2132 Plant and Wildlife Survey 2-33
214 Test Pit Explorations 2-33
30 Physical Characteristics of the Study Area 3-1
31 General Characteristics 3-1
311 Regional Physiography 3-1
312 Study Area Physiography 3-1
313 Surface Water Features 3-2
314 Climate 3-3
32 Geology 3-3
321 Regional Surficial Geology 3-3
322 Local Surficial Geology 3-4
323 Regional Bedrock Geology 3-7
324 Local Bedrock Geology 3-8
33 Hydrogeology 3-9
331 Hydraulic Conductivity 3-9
332 Groundwater Flow 3-10
34 Ecology 3-17
341 Wetland Delineation 3-17
342 Plant and Animal Survey 3-19
40 Nature and Extent of Contamination 4-1
41 Contaminant Source Investigation 4-2
5797wpdocsggtlluprifinaltextmasteiTifhl061297 ii QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
Table of Contents (continued)
411 Visual Site Reconnaissance 4-2
412 Soil Vapor Survey 4-4
413 Geophysical Investigations and Test Pits 4-5
414 Background Soils 4-6
415 Soils From Former Known Disposal Areas 4-7
416 Contaminant Source Investigations Summary 4-15
42 Groundwater Quality 4-17
421 Temporary Well Point Investigation 4-17
422 Groundwater Monitoring Wells 4-18
423 Residential Wells 4-26
43 Surface Water Sediment and Wetland Soils 4-27 431 Surface Water 4-27
432 Sediment 4-31
433 Wetland Soils 4-32
44 Air Quality 4-34
441 Baseline Air Quality Survey 4-34
442 Perimeter Air Monitoring 4-34
45 Potential Sensitive Human Receptors 4-35
50 Contaminant Fate and Transport 5-1
51 Theory 5-1
511 Advection by Groundwater Flow 5-1
512 Dispersion 5-3 513 Advection Due to Fluid Density Differences 5-5
514 Biological and Chemical Degradation 5-5
515 Volatilization 5-7
516 Aqueous Solubility 5-7
52 Study Area-Specific Characteristics 5-7
521 Retardation Factors 5-7
522 Chemical Migration Rates 5-9
523 Time-Dependent Concentration Reductions 5-14
5797wpdocBg8lluprifinaltextmlaquo8terrifhl061297 Hi QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
60 Summary and Conclusions 6-1
61 Conceptual Model of the Study Area 6-1
611 Geology 6-1
612 Hydrogeology 6-2
613 Nature and Extent of Contamination bdquo 6-5
70 References 7-1
5797wpdocsgnlluprifinlaquoltextmasterriftil061297 Jy QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Table of Contents (continued)
List of Tables
Table 1-1 Summary of Results of Groundwater Analyses (CTDEP)
Table 1-2 Summary of Results of Groundwater Analyses (MampE 1993)
Table 1-3 Summary of Results of Groundwater Analyses Former Pervel Flock Plant (HRP)
Table 2-1 Microwell Sampling Intervals
Table 2-2 Former Disposal Area Soil Samples Submitted for Laboratory Analyses
Table 2-3 Monitoring Well Survey Data and Screen Intervals
Table 2-4 Geologic Descriptions of Soil Samples Collected for Grain Size Analyses
Table 2-5 Sample Inventory
Table 2-6 Existing Well Summary
Table 3-1 Hydraulic Conductivity Values
Table 3-2 Hydraulic Conductivity Values Estimated from Grain Size Distributions
Table 3-3 Monitoring Well Water Level Elevation Data
Table 3-4 Summary of Vertical Hydraulic Gradients Between Pairs of MWs in Study Area
Table 3-5 Stream Piezometer Water Level Elevation Data
Table 3-6 Plants Identified During the Wetland Delineation
Table 4-1 Summary of Visual Site Reconnaissance
Table 4-2 Background Soil Volatile Organic Compounds Table 4-3 Background Soil MetalsCyanide
Table 4-4 Disposal Areas Soil Volatile Organic Compounds
Table 4-5 Disposal Areas Soil Semivolatile Organic Compounds
Table 4-6 Disposal Areas Soil PesticidesPCB
Table 4-7 Disposal Areas Soil MetalsCyanide
Table 4-8 Microwell Survey Selected Volatile Organics
Table 4-9 Microwell Survey Results of Volatile Organics Laboratory Analyses
Table 4-10 Microwell Survey Results of Inorganic Laboratory Analyses
Table 4-11 Groundwater Volatile Organic Compounds January 1995
Table 4-12 Groundwater Volatile Organic Compounds April 1995
Table 4-13 Groundwater Volatile Organic Compounds July 1995
Table 4-14 Groundwater Volatile Organic Compounds November 1995
5797wpdocggalluprifinraquoltextmalaquoterrifhl061297 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Tables (Contd)
Table 4-15 Groundwater Volatile Organic Compounds February 1996
Table 4-16 Groundwater Volatile Organic Compounds May 1996
Table 4-17 Groundwater Volatile Organic Compounds August 1996
Table 4-18 Groundwater Volatile Organic Compounds November 1996
Table 4-19 Groundwater Volatile Organic Compounds February 1997
Table 4-20 Groundwater Semivolatile Organic Compounds January 1995
Table 4-21 Groundwater Semivolatile Organic Compounds April 1995
Table 4-22 Groundwater Semivolatile Organic Compounds July 1995
Table 4-23 Groundwater Semivolatile Organic Compounds November 1995
Table 4-24 Groundwater Semivolatile Organic Compounds February 1996
Table 4-25 Groundwater Semivolatile Organic Compounds May 1996 Table 4-26 Groundwater Semivolatile Organic Compounds August 1996
Table 4-27 Groundwater Semivolatile Organic Compounds November 1996
Table 4-28 Groundwater Semivolatile Organic Compounds February 1997
Table 4-29 Groundwater PesticidesPCB April July and November 1995 February and August 1996 February 1997
Table 4-30 Groundwater MetalsCyanide January 1995
Table 4-31 Groundwater MetalsCyanide April 1995
Table 4-32 Groundwater MetalsCyanide July 1995
Table 4-33 Groundwater MetalsCyanide November 1995
Table 4-34 Groundwater MetalsCyanide February 1996
Table 4-35 Groundwater MetalsCyanide May 1996
Table 4-36 Groundwater MetalsCyanide August 1996
Table 4-37 Groundwater MetalsCyanide November 1996
Table 4-38 Groundwater Metals February 1997
Table 4-39 Residential Wells Volatile Organic Compounds January 1995
Table 4-40 Residential Wells Volatile Organic Compounds July 1995
Table 4-41 Residential Wells Volatile Organic Compounds February 1996
Table 4-42 Residential Wells Volatile Organic Compounds August 1996
Table 4-43 Residential Wells PesticidesPCB January 1995
Table 4-44 Residential Wells PesticidesPCB July 1995
Table 4-45 Residential Wells PesticidesPCB February 1996
Table 4-46 Residential Wells PesticidePCB August 1996
Table 4-47 Residential Wells Metals January 1995
5797wpdocsg lluprifinaltextmastemfiil061297 VI QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Tables (Contd)
Table 4^8 Residential Wells Metals July 1995
Table 4-49 Residential Wells MetalsCyanide February 1996
Table 4-50 Residential Wells MetalsCyanide August 1996
Table 4-51 Field Observations of Habitat and Water Quality September 1994
Table 4-52 Surface Water Quality April and November 1995 May and November 1996
Table 4-53 Surface Water Volatile Organic Compounds September 1994
Table 4-54 Surface Water Volatile Organic Compounds April 1995
Table 4-55 Surface Water Volatile Organic Compounds November 1995
Table 4-56 Surface Water Volatile Organic Compounds May 1996
Table 4-57 Surface Water Volatile Organic Compounds November 1996
Table 4-58 Surface Water Volatile Organic Compounds September 1994 April 1995 May
1996
Table 4-59 Surface Water Total MetalsCyanide September 1994
Table 4-60 Surface Water Dissolved Metals September 1994
Table 4-61 Surface Water Total Metals April 1995
Table 4-62 Surface Water Dissolved Metals April 1995
Table 4-63 Surface Water Total and Dissolved Metals November 1995
Table 4-64 Surface Water Total and Dissolved Metals May 1996
Table 4-65 Surface Water Total and Dissolved Metals November 1996
Table 4-66 SedimentWetland Soils Metals September 1994
Table 4-67 SedimentWetland Soils Volatile Organic Compounds September 1994 Table 4-68 SedimentWetland Soils Semivolatile Organic Compounds September 1994
Table 4-69 SedimentWetland Soils PesticidesPCB September 1994
Table 4-70 Human Receptors Survey Location of Day Care Facilities Within 1-Mile Radius
of Site
Table 5-1 Fate and Transport Parameters for Study Area Volatile Organic Compounds
Table 5-2 Total Organic Carbon Measurements for Soil Samples
Table 5-3 Historical Concentration Data
5797wpdoclaquoglaquolluprifinaltextmasterriftil061297 Vll QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Figures
Figure E-l Site Location Map
Figure E-2 Site Wide Groundwater Flow
Figure 1-1 Site Location Map
Figure 1-2 Property Boundaries and Adjacent Landowners
Figure 1-3 Surface Water and Groundwater Classification Zones and Locations of Former
Disposal Areas
Figure 1-4 Groundwater Monitoring Wells Installed by Fuss amp ONeill
Figure 1-5 Site Location Map and Nearby Industrial Properties
Figure 3-1 Groundwater Elevations MW101 Series Figure 3-2 Groundwater Elevations MW102 Series
Figure 3-3 Groundwater Elevations MW103 Series
Figure 3-4 Groundwater Elevations MW104 Series
Figure 3-5 Groundwater Elevations MW105 Series
Figure 3-6 Groundwater Elevations MW106 Series
Figure 3-7 Groundwater Elevations MW107 Series
Figure 3-8 Groundwater Elevations MW108 Series
Figure 3-9 Groundwater Elevations MW109 Series
Figure 3-10 Groundwater Elevations MW110 Series
Figure 3-11 Groundwater Elevations MW111 Series
Figure 3-12 Groundwater Elevations MW112 Series
Figure 3-13 Groundwater Elevations MW113 Series
Figure 3-14 Groundwater Elevations MW114 Series
Figure 3-15 Groundwater Elevations MW115 Series
Figure 3-16 Groundwater Elevations MW116 Series
Figure 3-17 Groundwater Elevations MW117 Series
Figure 3-18 Groundwater Elevations MW118 Series
Figure 3-19 Groundwater Elevations MW119 Series
Figure 3-20 Groundwater Elevations SW3 Series
Figure 3-21 Three-Dimensional Groundwater Flow Map
5797wpdoc8galluprifiruiltextmasterriftil061297 viii QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
Figure 5-1
Figure 5-2
Figure 5-3
List of Figures (Contd) Groundwater VOC Concentrations vs Time - Downgradient from Former
Primary Disposal Area
Groundwater VOC Concentrations vs Time - Near Former Pervel Facility
Groundwater VOC Concentrations vs Time - Downgradient Portion of VOC
Plume
Figure 5-4 Evaluation of Biodegradation and Rainwater Dilution Rates in VOC Plume
5797wpdocraquogalluprifinaltextmasterrifhl061297 ix QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Plates
Plate 2-1 Baseline Survey Grid Air Monitoring Seismic Refraction Line Locations
Plate 2-2 Microwell Locations
Plate 2-3 Soil Vapor Probe and Soil Boring Locations
Plate 2-4 Monitoring Wells PiezometersStream Gauge Locations
Plate 2-5 Residential Well Locations
Plate 2-6 Surface WaterSediment and Wetland Soil Sampling Locations
Plate 2-7 Location of Test Pits Performed at Geophysical Anomalies
Plate 3-1 Study Area Topographic Features
Plate 3-2 Geologic Cross-Sections A-A amp C-C Plate 3-3 Geologic Cross-Section D-D
Plate 3-4 Geologic Cross-Section B-B Plate 3-5 Geologic Cross-Sections E-Eamp F-F
Plate 3-6 Bedrock Surface Contour Map
Plate 3-7 Bedrock Fracture Zones as Determined by Seismic and Magnetometer Surveys
Plate 3-8 Lower Overburden Piezometric Surface November 6 1995
Plate 3-9 Shallow Overburden Piezometric Surface November 6 1995
Plate 3-10 Saturated Overburden Thickness November 6 1995
Plate 3-11 Bedrock Piezometric Surface November 6 1995
Plate 3-12 Vertical Ground water Flow Through Plume Center Line
Plate 3-13 Deep vs Shallow Piezometric Head Differences
Plate 3-14 Wetland Delineation Map September 1994
Plate 4-1 Survey Grid amp Features Noted During Site Reconnaissance August-September
1994
Plate 4-2 Former Primary Disposal Area Soil Borings VOC Data and Cross-Sections
Plate 4-3 Former Primary Disposal Area Soil Borings PCB Data and Cross-Sections
Plate 4-4 VOC Detections Field GC and Laboratory Analyses in Microwells
Plate 4-5 Laboratory Results of Metals Analyses in Microwells
Plate 4-6 Groundwater VOC Data January April July and November 1995 Sampling
Events
Plate 4-7 Groundwater VOC Data February May August and November 1996 and
February 1997 Sampling Events
Plate 5-1 Groundwater Travel Times in Overburden Aquifer November 6 1995
5797wpdocsgi lluprifinaltextmasteirifnl061297 X QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
Table of Contents (continued)
List of Appendices
Appendix A Weston Geophysical Inc Report
Appendix B Microwell Logs
Appendix C Soil Boring and Rock Coring Logs and Well Construction Forms
Appendix D Groundwater Sampling Forms
Appendix E Test Pit Logs
Appendix F Single-Well Hydraulic Conductivity Test Procedures
Appendix G Grain Size Data
Appendix H Phase 1A Laboratory Reports
Appendix I April 1995 Laboratory Reports
Appendix J July 1995 Laboratory Reports
Appendix K Phase IBNovember 1995 Laboratory Reports
Appendix L February 1996 Laboratory Reports
Appendix M May 1996 Laboratory Reports
Appendix N August 1996 Laboratory Reports
Appendix O November 1996 Laboratory Reports
Appendix P February 1997 Laboratory Reports
Appendix Q Data Validation Reports
Appendix R pH TOC Moisture Results Soil Samples
Appendix S Environmental Metals Statistics
Appendix T Air Monitoring Results
Appendix U Model of Groundwater Near Mill Brook Appendix V Methodology for Piezometric Head Contouring and Groundwater Pathline
Generation
5797wpdocsgalluprifinlaquoltextmagterri fhl061297 XI QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
10 Introduction
11 Purpose of the Report This document presents the Remedial Investigation Report (RI) which was completed for the
Gallops Quarry Superfund Site (Site) pursuant to the requirements of US Environmental
Protection Agency (EPA) Administrative Order by Consent Docket Number 1-93-1080 (Order)
issued September 7 1993 The Gallups Quarry property is the site of a former sand and gravel
quarry and is located on Tarbox Road in the town of Plainfield Windham County Connecticut
(see Figure 1-1) According to the Town of Plainfield Tax Assessors office the property (Map
10 Block 30 Lot 32) is an irregularly shaped parcel comprised of approximately 29 acres
Investigation of the quarry was initiated in 1978 when unlicensed waste disposal operations were
discovered at the property Emergency clean-up operations were conducted by the Connecticut
Department of Environmental Protection (CTDEP) in April 1978 (Metcalf amp Eddy 1993)
Following the initial clean-up effort a study was conducted to characterize the nature and extent
of residual contamination at the Site (Fuss amp ONeill 1979) A series of surface and subsurface
sampling events conducted by the CTDEP the Connecticut Department of Health and the US
Environmental Protection Agency (EPA) between the years of 1978 and 1988 prompted EPA to
propose on June 21 1988 that the Site be listed on the National Priorities List (NPL) The Site
was finally listed on the NPL on October 4 1989 During 1992 and 1993 EPA conducted a
limited investigation through the Superfund Technical Assessment amp Response Team (START)
initiative in an effort to expedite the completion of the Remedial InvestigationFeasibility Study
(RIFS) The requirements of the Order as well as data included in the START report (Metcalf
amp Eddy 1993) provided the framework for this investigation
This Report is the sixteenth major deliverable under the Order The first major deliverable the
Remedial InvestigationFeasibility Study Work Plan - Phase 1A was finalized and submitted to
EPA on August 29 1995 QST Environmental (formerly Environmental Science amp Engineering
Inc (ESE)) finalized the Work Plan and has prepared all of the other deliverables The Phase 1A
field investigation was completed in January 1995 The second major deliverable the Phase 1A
Data Report dated March 24 1995 was submitted to EPA following completion of the Phase 1A
field investigation The findings of the Phase 1A investigation were described in the Initial Site
Characterization Report (ISCR) which was finalized and submitted to EPA on March 1 1996 A
Work Plan for the Phase IB field investigation was also finalized and submitted on October 11
1995
In addition to the actual Phase 1A field investigation the Phase 1A Work Plan also described the
Long Term Monitoring Program which was initiated upon completion of the Phase 1A field
5797wpdocraquogalluprifinaltextmlaquoiterrifhl061297 1-1 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
investigation The Long Term Monitoring Program includes the quarterly collection and analysis
of groundwatei and semi-annual collection and analysis of surface water and nearby residential
well samples
The Phase IB field investigation commenced on October 12 1995 Following the completion of
drilling activities the Phase IB groundwater sampling task and the fourth quarter 1995 Long
Term Monitoring sampling event were performed simultaneously in November 1995 Seven
Data Reports have been submitted to the EPA for the following Long-Term Monitoring Program
sampling events the second and third quarters of 1995 all four quarters of 1996 and the first
quarter of 1997 (ESE 1996a 1996b 1996c 1997a 1997b) The draft RI Report was submitted
to EPA on March 15 1996 (and revised and resubmitted October 22 1996) and included the
results of the fourth quarter of 1995 sampling event On March 29 1996 the following two
deliverables were submitted to EPA Development and Initial Screening of Alternatives Report
and Detailed Analysis Work Plan The draft Feasibility Study was submitted to EPA on January
27 1997 This RI Report describes the methods and findings of both the Phase 1A and IB field
studies and includes data collected during the April July and November 1995 February May
August and November 1996 and February 1997 Long-Term Monitoring sampling events
12 Report Organization The RI is presented in seven main sections following the Executive Summary The remainder of
Section 1 presents Site background information Section 2 presents the various field methods and
procedures used during the field investigations including descriptions of any changes or
deviations from the Work Plan Section 3 describes the physical characteristics of the Study
Area and Section 4 presents the findings of studies designed to determine the nature and extent of
contamination within the Study Area Section 5 is a discussion of the various fate and transport
mechanisms associated with the contaminants of concern Section 6 summarizes the conceptual
model of conditions within the Study Area Finally a list of references cited in this report is
presented in Section 7
Volume 1 of this Report presents the text and figures of the RI Volume 2 contains all Tables
referenced in the report Volume 3 contains all Plates referenced in the Report Volume 4 and
all subsequent volumes contain the Appendices referenced in the Report
5797wpdocggaIluprifinaltextmasterrifhl061297 1-2 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
13 Site Background 131 Area Description Demography and Land Use
For the purposes of this report the Site is considered to be the actual property owned by the
late Stanton Gallup from 1964 until his death in 1994 The Study Area includes the Site as
well as surrounding properties from which data were collected during the RI
The Site is located on the north side of Tarbox Road in the Town of Plainfield Windham County
Connecticut (see Figure 1-1) The Site is situated approximately 2000 feet west of interchange
87 on Interstate 395 and approximately one-mile southwest of Plainfield Center As shown on
Figure 1-2 the Site is irregularly shaped and is approximately 2200 feet long (north to south)
and 300 to 1100 feet wide (east to west) A number of previous references have described the
Site as ranging in size from 20 to 22 acres however the Town of Plainfield Tax Maps and areal
calculations performed by ESE indicate that the size of the Site is approximately 29 acres In
addition to the Site the Study Area includes additional areas located to the north and northwest of
the Site (as shown on Figure 1-1) and a number of discrete smaller areas located to the east and
south of the Site used for collecting upgradient surface watersediment samples
The Site is currently vacant and much of it is heavily vegetated Numerous overgrown mounds
and excavations are scattered across the Site and are presumed to be features remnant of the
former sand and gravel quarry operations Other than concrete foundations remnant of former
Site operations no structures presently exist on the property Surface features observed on the
Site during the Phase 1A visual reconnaissance survey are described in more detail in Section
411
As shown on Figure 1-2 the Site is bounded to the east by Route 12 (Norwich Road) single-family residences and a plumbing supply company An active railroad right-of-way (presently
operated by the Providence and Worcester Railroad) bounds the Site to the west Wooded areas
and wetlands associated with Mill Brook bound the Site to the north and Tarbox Road and several
single family residences bound the Site to the south
Surface water bodies located within or near the Study Area include Mill Brook Fry Brook and
Packers Pond As shown on Figure 1-3 Mill Brook flows from east to west along the northern
edge of the Study Area until its confluence with Fry Brook Mill Brook turns toward the south
at this confluence and continues flowing in a south-southwesterly direction (as Mill Brook) and
eventually drains into Packers Pond [Note Packers Pond is not shown on Figure 1-3 due to the
larger scale of this figure however the relative location of Packers Pond approximately 1 mile
west of the Site can be seen on Figure 1-1]
5797wpdocBgalluprifinaltextmasteiTifhl061297 1-3 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Based on the CTDEP Water Quality Classification Map of Thames Southeast Coast and
Pawcatuck River Basins Sheet 2 of 2 (1986) surface water located within the section of Mill
Brook between Route 12 and the confluence with Fry Brook (shown on Figure 1-3) is classified
as BA The BA classification indicates that the surface water body may not be meeting the
Class A water quality criteria for one or more designated uses which include potential drinking
water supply fish and wildlife habitat recreational use and agricultural and industrial supply
although the goal is to ultimately restore the water body to Class A standards Surface water
within Fry Brook and the lower section of Mill Brook (located down stream of the confluence of
the two brooks) is classified as Be The Be classification indicates that the water meets Class B
criteria and is suitable for cold water fisheries The designated uses for Class B surface water
include most of those described for Class A however Class B waters are NOT designated as a
potential drinking water supply Surface water located within Packers Pond (not shown on Figure
1-3) is designated as CBc The CBc designation indicates that Packers Pond is not meeting the
Class B water quality criteria for one or more designated uses or is a Class C water body which
is basically a downgraded version of Class B However the CTDEP goal for surface water
designated as CBc is to restore it to Class B conditions
As shown on Figure 1-3 groundwater located within the northern portion of the Study Area
between Route 12 and the MillFry Brook confluence is classified as GBGA which indicates that
the groundwater may not be suitable for direct human consumption without the need for treatment
due to waste discharges spills or leaks of chemicals or land use impacts The CTDEP goal for
groundwater classified as GBGA is to prevent further degradation by preventing any additional
discharges which would cause irreversible contamination Groundwater at all other locations
within the Study Area is classified as GA which is presumed suitable for direct human
consumption without need for treatment In addition one of the goals of the CTDEP for
groundwater classified as GBGA is to restore it to GA standards
It should be noted that the surface water classifications described above are based on existing
CTDEP maps which were published prior to the preparation of this report During the course of
this investigation the CTDEP proposed amendments which were intended to clarify the language
of the States Water Quality Standards and simplify the Departments system for considering
requested modifications Based on conversations with a representative of the CTDEP (Personal
Communication Bobowitz 1996) the single letter (eg Class A) and dual letter (and associated
goal) classification (eg BA) system will be maintained Areas presently designated by dual
classifications will only be modified once the desired goal for that water body or aquifer has been
attained According to the CTDEP the only significant change will be the eventual elimination of
the use of lower case suffixes (eg Be) which are currently used to indicate very specific
restrictions or uses for certain water bodies (ie B rather than Be)
5797wpdocsgalluprifinaltextmasterrifhl061297 1-4 QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
Within the Study Area directly west of the Site (across the railroad tracks) are open cropland
(presently a cornfield) wooded areas and a residential property (parcel 24 shown on Figure 1shy
2) The property boundaries and land owners for the Site and other nearby parcels are also
shown on Figure 1-2 Immediately north of the Site are approximately 85 acres of wooded
undeveloped land through which flows Mill Brook An overhead power line easement (not shown
on Figure 1-2) runs adjacent to the northernmost Site boundary On the north side of Mill Brook
is an industrial park which contains an Intermark Fabric Corporation facility (formerly the Pervel
Industries flock plant) and a Safety Kleen Corporation accumulation facility Northeast of Mill
Brook are woodlands and Saint Johns Cemetery Further north of the industrial park are several
vacant mill buildings which were occupied until the late 1980s by various manufacturers including
Pervel Industries and the InterRoyal Corporation The Plainfield sewage treatment plant which
discharges to Mill Brook and its major tributary (Fry Brook) is located approximately 1800 feet
northwest of the property
The Town of Plainfield with a land area of 427 square miles has a population of approximately
14200 Plainfields principal industries include varied manufacturing and distribution centers as
well as tourism based businesses In addition the rural areas of Plainfield are occupied by many
small dairy and produce farms
^ 132 Operational History
Information regarding the operational history of Gallups Quarry was obtained from published
reports for previous Site studies including Site Analysis Gallups Quarry Plainfield CT
(Bionetics Corporation 1990) and Final Data Summary Report START Initiative (Metcalf amp
Eddy 1993) as well as information from various sources collected during the preparation of the
Gallups Quarry Remedial InvestigationFeasibility Study Work Plan (ESE 1994) Little detailed information concerning the early operational history of the Site exists
A review of an aerial photograph of the Site taken in 1951 depicts the Site as an undeveloped
parcel although some quarry activities in the southern portion of the property appear to be
underway (ESE 1994) Records at the town of Plainfield Assessors office indicate that in 1951
the Site was owned by a Mr Johnson who was operating a sand and gravel quarry In 1964 the
Site was purchased by C Stanton Gallup (Metcalf amp Eddy 1993) Although detailed usage of
the Site from 1964 through 1977 is poorly documented records indicate that the Site was used as
a source of aggregate and was occupied by the Connecticut Department of Transportation
(CTDOT) which operated an asphalt batching plant (ESE 1994) The exact date of CTDOT
presence at the Site is unclear although it is believed to coincide with the construction of Route
52 (now known as Interstate 395) Evidence of the former asphalt batching plant operations are
5797wpdocsgalluprifinalteirtinalaquoterrifhl061297 1-5 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
still present at the Site Mounds of asphalt paving material and areas covered with hardened
liquid asphalt ere observed at a number of locations throughout the Site
As a result of complaints from neighboring residents the CTDEP and the Connecticut State
Police initiated an investigation of the Site in early January 1978 During a Site visit on January
13 1978 representatives of the CTDEP reportedly observed partially buried drums containing
suspected hazardous materials and ordered that all Site operations be stopped The CTDEP
investigation concluded that the Site was used from the summer of 1977 until December 1977 for
unlicensed waste disposal
As described in the Order evidence collected by CTDEP indicates that Chemical Waste Removal
Inc (CWR) of Bridgeport Connecticut transported drummed and bulk liquid waste material to the
Site and was the sole known transporter of waste to the Site These wastes reportedly included a
variety of industrial wastes which were transported to and disposed of at the Site It was reported
that Mr Gallup jointly operated the quarry with Mr Dick Trayner of Dick Trayner and Sons
Trucking Company at the time of the illegal waste disposal activities
According to CTDEP and State Police records the drums and liquid wastes were reportedly
disposed of at three distinct locations on the Site These areas were subsequently labeled the
Primary Disposal Area the Secondary Disposal Area and the Seepage Bed The Primary and
Secondary Disposal Areas were reportedly located in the northern portion of the Site while the
Seepage Bed was reportedly located in the central portion of the Site The reported locations of
these former disposal areas are shown on Figure 1-3
According to a report issued by Fuss amp ONeill (FampO 1979) the Primary Disposal Area
consisted of an area approximately 04 acres in size The Secondary Disposal Area was described
by the FampO report as a linear trench which encompassed an approximate area of 007 acres
located adjacent to the railroad tracks and just west of the Primary Disposal Area The Seepage
Bed was located in the central portion of the Site and according to the FampO report was
approximately 40 feet by 50 feet in size and consisted of an excavation into which an inverted
truck body filled and covered with crushed stone was placed A metal pipe which extended
from the dump body to the ground surface was reportedly used for direct discharge of liquid
wastes According to the FampO report the liquid wastes reportedly disposed of in the Seepage
Bed consisted of low pH liquids which were believed to be by-products associated with metal
finishing operations
Initial cleanup efforts were performed by Chem-Trol Inc during the summer of 1978 under the
direction of the CTDEP and the Connecticut State Police A Connecticut State Police Possessed
5797wpdocsglaquolluprifinaltextmasterrifhl061297 1-6 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
Property Report (PPR) lists the following materials as removed from the Site 1584 drums (some
of which were crushed andor decomposed) 5000 gallons of free liquid and 2277 cubic yards
of contaminated earth The PPR also lists 127715 tons of moderately contaminated soil which
was removed from the Site Additional remedial measures included the neutralization of residual
contamination at the Seepage Bed by placing 20 tons of lime at that location
Although no information concerning the actual number of drums or quantity of waste transported
to the Site by CWR is available it was believed that all of the drums had been recovered upon
completion of the cleanup operations Mine detectors were utilized to search for additional buried
drums however no indications of additional buried drums were discovered
Since the 1978 cleanup operations the Site has been vacant Public vehicular access to the Site
has been limited by the placement of boulders and mounded soil at access locations around the
Site During this time evidence of off-road vehicle tire tracks and small quantities of debris
(beverage cans bottles spent shotgun shell casings and empty gasoline cans) indicate that the
Site has been utilized by trespassers for recreational purposes However it appears that Site
usage has decreased since August 1994 when fencing and additional boulders were placed at
potential access locations and the perimeter of the property was posted with warning signs
133 Summary of Previous Investigations
Following the CTDEP removal activities a number of environmental investigations and sampling
events were conducted at the Gallups Quarry Site This section summarizes environmental
studies conducted at the Site prior to the RIFS as compiled performed and reported by Metcalf
amp Eddy (1993) as part of the EPAs Region I START Initiative or as reported by the original
investigators)
1331 Evaluation of a Chemical Waste Disposal Area Tarbox Road Site Plainfield Connecticut Fuss amp ONeill 1979
Between June 6 and October 30 1978 Fuss amp ONeill Inc performed a hydrogeological
investigation within the Study Area in conjunction with the cleanup and remedial operations
directed by the CTDEP and Connecticut State Police The findings of this investigation were
presented in a report issued to the CTDEP dated January 29 1979 The tasks completed during
this investigation included the following
bull The installation of 22 test borings which were completed as groundwater
monitoring wells (SW series) including three shallow-bedrock wells near the
Former Seepage Bed (SW-10 SW-11 SW-12) The locations of these wells are
shown in Figure 1-4
5797wpdocsgalluprifinaltextmlaquo8terrifhl061297 1-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
bull Excavation of 19 test pits (using a backhoe) 13 of which were completed as
shallow groundwater monitoring wells
bull The establishment of 12 surface water gauging stations along Mill Brook and Fry
Brook
bull The collection of surface water and groundwater water for laboratory analysis
FampO collected groundwater samples from the monitoring wells in July October and December
1978 Several nearby domestic wells were also sampled in July and October 1978 Groundwater
samples were analyzed for metals volatile organic compounds (VOC) and the following general
chemical parameters chemical oxygen demand (COD) total dissolved solids (TDS) total
Kjeldahl nitrogen (TKN) chloride total organic carbon (TOC) total carbon total cyanide
specific conductance and pH
FampO also collected surface water samples from seven of the stream gauging stations in
September October and November 1978 In general the surface water samples were analyzed
for the same chemical parameters described above
The chemical testing results indicated groundwater in the vicinity and downgradient of the Former
Disposal Areas had been impacted by several organic and inorganic constituents VOC detected
included ethanol methanol isopropanol ethyl acetate acetone toluene benzene trichloroethene
(TCE) 111- trichloroethane (TCA) tetrachloroethene (PCE) methyl isobutyl ketone (MIBK)
methyl ethyl ketone (MEK) and methylene chloride Various metals including aluminum
chromium copper magnesium nickel zinc iron and silver were reported at widely variable
concentrations in some groundwater samples According to the START Report the domestic
wells did not appear to be significantly impacted
FampO concluded that a well-defined groundwater contaminant plume extended from the former
disposal areas towards Mill Brook northwest of the Site and that the flow direction of the plume
was controlled by the local water table gradient The plume was characterized by the presence of
organic compounds which included acetate benzene ethanol isopropanol MEK MIBK
toluene TCA and xylene The plume also contained widely variable concentrations of various
metals including copper nickel boron aluminum magnesium manganese iron silver
cadmium and lead
The START Report indicated that since little or no information is available regarding FampOs field
methods (eg field notes chain-of-custody collection of field QC samples) or analytical
5797wpdoc8galluprifinaltextmastemfnl061297 1-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
methods (eg detection limits turbidity filtering sample preservation analysis of lab QC
samples) comparison of the test results to current regulatory criteria (eg Maximum Contaminant
Levels [MCL]) was not appropriate for any definitive purpose
1332 CTDEP Periodic Monitoring 1979 to 1983
As described in the START Report the CTDEP performed periodic monitoring of groundwater
(including domestic wells) surface water and sediment in the Study Area from 1979 until 1983
The periodic monitoring was not systematic in terms of the wells or locations that were sampled
or the parameters tested for The results of the CTDEP monitoring are in the form of laboratory
results compiled and presented in the START report A summary table of results for the CTDEP
groundwater monitoring activities as presented in the START report is included in this report as
Table 1-1
The dates of groundwater sample collection and analysis for the CTDEPs monitoring program
are as follows
bull October 1979
bull January 1980
bull November 1980
bull April 1981
bull October 1981
bull April 1982
Sample analytical parameters varied from event to event but typically included pH COD
specific conductivity hydrocarbons chlorides and selected metals (cadmium chromium copper iron nickel and zinc)
The CTDEP also collected surface water and sediment samples on the following dates
bull January 1980 (surface water)
bull October 1981 (surface water and sediment)
bull April 1982 (surface water)
bull December 1983 (surface water)
It was noted in the START Report that no information was available regarding the CTDEP sampling methods or analytical procedures and that this limited the usefulness of the data except
for comparative purposes Nonetheless the START Report concluded that the available analytical
data collected by CTDEP during the period from 1972 to 1982 indicated that the Site and areas to
5797wpdoc8falluprifinaltextmasterrifnl061297 1-9 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
the north-northwest were impacted by the past disposal of VOC metals and acid wastes This
conclusion wa5 based on the fact that up until the last recorded groundwater sampling event
performed by CTDEP (1982) four monitoring wells (SW7D SW13 SW17S and SW17D)
exhibited detectable concentrations of contaminants characteristic of the types of wastes which
were reportedly disposed of on the Site The contaminants detected in these wells included
various common industrial organic solvents (both chlorinated hydrocarbons and ketones) as well
as several petroleum aromatic hydrocarbons Chlorinated hydrocarbon concentrations for these
wells ranged from 10000 to 80000 parts per billion (ppb) for 111-Trichloroethane (TCA) 30
to 1000 ppb for Tetrachloroethane (PCE) and 1000 to 14000 ppb for Trichloroethene (TCE)
Ketones detected included Acetone (5000 to 22000 ppb) methyl ethyl ketone (MEK) ranged
from 12000 to 150000 ppb and methyl iso butyl ketone (MIBK) ranged from 60 to 7000 ppb)
The main aromatics detected included toluene (up to 17000 ppb) and xylene (up to 3000 ppb)
1333 CTDEP BioDiversity Study 1985
The CTDEP conducted a field survey on November 4 1985 to evaluate potential impacts from
migration of groundwater from the Site to the Mill Brook wetland The study was conducted in
an area where leachate was observed to be breaking out from the wetlands into Mill Brook
The precise location is unclear however the START Report indicates that the impact zone was
subjectively estimated to be approximately 200 feet west of the railroad bridge The leachate
was described as an area showing evidence of organic enrichment and iron hydroxide precipitation
which extended a distance of approximately 100 feet downstream
The study reported a background species Diversity Index value of 257 compared to a value of
236 for the area of study The minor difference in diversity represented by this measure was
primarily considered to be a result of low flow conditions as much higher diversity indices
indicative of excellent water quality were observed during a previous bioassessment in that
area
As part of the CTDEP study four surface water samples were collected (one control and three
downstream) from Mill Brook on 8 November 1985 for acute aquatic toxicity bioassays using
water fleas (Daphniapulex) The results of this testing are summarized in a CTDEP
interdepartmental memorandum (dated November 18 1985) that is included with the results of the
biodiversity study The assay employed three replicates per sample and 10 individual organisms
per replicate The endpoint of the assay was percent survival after 48 hour exposure to the water
All samples yielded average survival rates of greater than 83 Based on the results of the tests
the CTDEP concluded that no acute toxicity was demonstrated
5797wpdocsgalluprifinaltextmasterrifnl061297 1-10 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The BioDiversity study report indicated that well MW17S was sampled and that a strong
solventacid odor was noted Further information on sampling and analyses of this well by
CTDEP in 1985 was not included in the report
1334 Hazard Ranking System (HRS) Study - NUSFIT 1986 to 19874
On September 15 1987 the Superfund Division of NUS Corporation completed the Final HRS
Documentation Package for Gallups Quarry The package contains information on the cleanup
and subsequent environmental evaluations including State Police documents and logs regarding
the investigation into the unlicensed disposal activities CTDEP and State Police documents
concerning cleanup activities affidavits taken from individuals involved in the disposal activities
and miscellaneous correspondence related to the criminal investigation and cleanup activities
The HRS package includes the EPAs Preliminary Assessment for Gallups Quarry which was
completed by NUS in July 1986 During the Preliminary Assessment NUS sampled two of the
existing monitoring wells (SW17D and SW18) and three surface watersediment locations The
surface and groundwater samples were screened in-house for benzene TCE toluene PCE
chlorobenzene ethyl benzene and xylenes None of these compounds were detected in MW18 or
the surface water samples All of the compounds (except chlorobenzene) were detected in
MW17S with toluene and xylenes measured at the highest concentrations With the exception of
pH temperature and conductivity no data were available regarding the sediment samples
Based on a file review and limited sampling the Preliminary Assessment concluded as in
previous studies that VOC contamination existed at the Site and that contaminated groundwater
was migrating in a west to northwest direction from the Site NUS recommended that a Site
Investigation be conducted to further evaluate the on-site conditions and potential off-site impacts
1335 Residential Well Sampling 1989
In 1989 Roy F Weston Inc under contract to EPA collected samples from 10 private wells in
the vicinity of the Site The samples were analyzed for VOC semi-volatile compounds (SVOC)
and metals Very low levels of some VOC (chloromethane TCA and carbon tetrachloride)
SVOC (phthalates) and metals (barium and copper) were detected in several wells but at
concentrations well below their respective EPA MCL In a memo dated May 25 1989 (included
as Appendix G of the START Report) EPA concluded that the levels detected in this investigation
did not represent a public health threat
5797wpdocsgalluprifinaltextmraquosterrifhl061297 1-11 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
1336 Site Analysis - Bionetics Corporation 1990
In November 1990 the Bionetics Corporation under contract to EPA completed an analysis of
historical aerial photographs taken of the Site in 1951 1970 1974 1975 1981 and 1988
Based on analyses of these aerial photographs the report suggested that disposal-related activities may have started at the quarry as early as 1970 However this conclusion was based on the
presence of features such as excavated areas mounded materials possible containers and the presence of access roads all of which are also indicative of typical quarrying operations
1337 Health Assessment - US Department of Health and Human Services (DHHS) 1991
The US Department of Health and Human Services completed a Health Assessment for Gallups Quarry on January 30 1991 to assess potential human health effects from exposure to
contamination at the Site The assessment was based on previous chemical testing data available
for the Site (ie data collected by Fuss amp ONeill Inc in 1978 and by CTDEP in 1979 through
1983)
The report concluded that if present at high enough concentrations VOC and heavy metals
detected at the Site could have potential public health implications The report recommended that
a program of groundwater monitoring be instituted along with on-site soil and surface water sampling and that additional health data for the area be evaluated as it becomes available
1338 Residential Well and Surficial Soil Sampling - Roy F Weston 1993
In 1993 Roy F Weston Inc under contract to EPA sampled 8 residential supply wells in the
vicinity of the Site The samples were analyzed for VOC SVOC and metals In addition
Weston collected seven surficial soil samples (within 3 inches of the ground surface) from areas
of apparent staining in the vicinity of the Former Primary and Secondary Disposal Areas Two
samples were collected in January 1993 and the other five were collected in February 1993 The
soil samples collected in January were submitted to the laboratory for analysis for pH and
cyanide and for metals screening using X-ray fluorescence techniques (XRF) The five samples
collected in February were analyzed for cyanide
The results of the XRF screening analyses indicated that the two samples collected in January
contained levels of copper ranging from 160 to 400 ppm No other metals were detected above
normal background levels Cyanide levels for all seven soil samples were reported in the range
of 87 to 345 ppm
5797wpdocsgalluprifinaltextmasterrifiil061297 1-12 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
The well water analytical results indicated that 111-TCA was detected in three of the residential
wells at levels of 05 to 12 ppb well below EPA MCL for 111-TCA of 200 ppb Copper and
iron were detected at levels below the EPA MCL in several of the samples analyzed SVOC were
not detected
1339 Groundwater Monitoring and Well Survey Metcalf amp Eddy 1993
In November 1992 Metcalf amp Eddy performed a well condition survey of the remaining existing
monitoring wells at the Site as part of a groundwater monitoring well investigation conducted for
the EPA Thirteen of the original twenty-two monitoring wells installed by Fuss amp ONeill Inc
were located fewer than half of which were determined to be in a condition capable of producing
viable samples In February 1993 Metcalf amp Eddy collected samples from ten of the wells
installed by Fuss amp ONeill Inc and from a USGS well installed in 1992 The samples were
analyzed for VOC SVOC metals and cyanide
Groundwater analytical results were consistent with earlier studies but confirmed that VOC levels
were significantly decreasing with time Low levels of VOC were detected at monitoring wells
SW3S and SW3D located downgradient of the Former Primary Disposal Area and at SW13
located downgradient of the Former Secondary Disposal Area The highest levels of VOC were
detected in wells SW17S (15000 ppb of xylene 1700 ppb of toluene 460 ppb of TCA 34 ppb
of TCE 22 ppb of PCE) and SW17D (1500 ppb of 12-DCE 720 ppb of TCA 16 ppb of TCE
and 27 ppb of PCE) A summary of the results of the 1993 Metcalf amp Eddy monitoring are
presented in Table 1-2 In general the concentrations detected in these wells for this sampling
event were substantially lower than concentrations recorded during the previous groundwater
sampling in 1982
13310 Geohydrology of the Gallups Quarry Area Plainfield Connecticut USGS 1993
In 1993 the United States Geological Survey (USGS) issued a draft report on Geohydrology of
the Gallups Quarry Area Plainfield Connecticut (finalized in 1995) The work was performed as
part of the EPAs START program and was designed to assist in the RIFS scoping process
The USGS study interpreted the subsurface geologic conditions at the Site to provide guidance for
subsequent investigations Field investigations for the study included ground penetrating radar
(GPR) and electromagnetic (EM-34) geophysical surveys the drilling of three test borings the
installation of a monitoring well in one of the borings (shown on Figure 1-4) and the
measurement of flow rate and specific conductance in Mill Brook
5797wpdocraquosalluprifiiultextmasterrifiil061297 1-13 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The USGS investigation provided data on overburden soil units the depth to bedrock and
bedrock structure Existing subsurface information derived from previous test boring logs and the
data collected from the three test borings drilled by the USGS were used in conjunction with GPR
data and the results of the EM-34 terrain conductivity survey to develop geological cross-sections
across the Site In addition the GPR survey indicated the possible presence of a west-northwest
trending fault zone beneath the property located south of the Former Seepage Bed The location
of this suspected fault zone as estimated by the USGS is consistent with the approximate location
inferred by previous regional geological studies (Dixon 1965 and Boynton and Smith 1965)
An electromagnetic survey performed downgradient (northwest) of the Former Secondary and
Primary Disposal Areas indicated a northwesterly-trending pattern of increased terrain
conductivity levels as compared with levels at other areas of the Site The USGS interpreted the
increased levels as possibly indicative of either the presence of a groundwater plume containing
residual metal contamination or a natural change in subsurface strata Surface water
measurements collected in Mill Brook indicated that specific conductance increased slightly
downstream of the railroad bridge however the observed differences were so small that the
USGS did not consider them to be indicative of changes in water quality caused by the presence
of dissolved contaminants
13311 Habitat Characterization for Gallups Quarry Superfund Site US Fish and Wildlife Service March 1995
In June of 1993 the US Fish and Wildlife Service conducted a field survey for the purposes of
characterizing the habitat of the Site and surrounding wetland and stream ecosystems The study
was qualitative in nature conducted on foot by trained biologists with the objective of correlating
observations on habitat (primarily vegetation) with known reference material such as topography
maps and aerial photographs The study also included direct and indirect (eg animal tracks)
observations to assess the presence (or absence) of wildlife
The report provides a description of methods and general Site characteristics as well as a more
detailed discussion of wildlife habitat for both the Site and the Mill Brook wetland ecosystem
The study is partial in that it accents what types of animals would be anticipated to be present for
each habitat type even though most of these animals were not directly observed
The report concludes with a description of 29 different types of cover that can be cross-
referenced to areas delineated on a Site map (not to scale) Several Tables are also presented
which inventory birds mammals reptiles amphibians trees shrubs and herbaceous vegetation
that were either observed or would be expected to inhabit the Site
5797wpdocsgalluprifinaItextmasterriftil061297 1-14 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
13312 Adjacent Properties Incident Reports and File Review 1995
To supplement data obtained during the Phase 1A field program a CTDEP file search was
performed to obtain information pertinent to groundwater contamination for industrial properties
neighboring the Site The preliminary findings of this review were submitted in a letter from
ESE to EPA on March 28 1995
A number of incident reports were on file regarding two nearby companies Pervel Industries
Inc and InterRoyal Corporation which have the potential to impact conditions within the Study
Area Figure 1-5 shows the locations of these facilities relative to the Site The significant
findings of the file searches are presented below
Pervel Industries
Pervel Industries Inc manufactured plastic film and laminated textile products (eg flocked
velvet) Pervel reportedly occupied two separate facilities north of the Site The main facility
located approximately 2500 feet north of the Site is believed to have been occupied by Pervel
from the 1940s or 1950s to at least the late 1980s This facility abutted the southern side of the
InterRoyal facility described below A second Pervel facility known as the flock plant (presently
operated by Intermark Fabric Corporation) was located approximately 1000 feet north of the
Site just north of Mill Brook The dates of Pervels occupation at the flock plant cannot be
clearly ascertained from the information available in the files however the review of historic
aerial photographs indicate that the facility has existed since the early 1970s
In 1988 at the request of EPA and CTDEP the NUS Corporation performed a Preliminary
Assessment (PA) at the main facility In an effort to determine eligibility for the National
Priorities List (NPL) NUS reviewed the activities associated with the 1984 closure of a sludge
and waste water lagoon located at the facility Based on their review of the available data NUS
recommended that a Screening Site Inspection (SSI) be performed
The NUS PA report also described a 1985 spill of 600 gallons of 111-TCA and a 1987 spill of
300 gallons of toluene at the northernmost facility According to the PA report contaminated soil
and sediment associated with the 1985 spill was excavated and stored in an impoundment at the
flock plant located just north of the Gallups Site The report indicates the presence of
contaminants in the area where the contaminated soil and sediment were stored suggesting that
the impoundment leaked andor there are other (undocumented) environmental concerns at the
flock plant
5797wpdocraquogalluprifinaltextmlaquosterrifhl061297 1-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The results of recent (late 1980s through the early 1990s) quarterly groundwater monitoring
efforts conducted at the former Pervel flock plant (HRP 1993) indicate the presence of a number
of VOC including 111-TCA TCE PCE and 12-DCE well above their respective MCL The
results of these sampling events as summarized in Table 1-3 (from HRP 1993) indicate that
there has been a general decrease in the concentrations of contaminants seen in these wells over
time The highest recorded concentrations for these constituents are as follows 111-TCA (518
ppb) PCE (466 ppb) TCE (63 ppb) and 12-DCE (906 ppb) According to the HRP report
groundwater flow in the vicinity of the former Pervel flock plant is generally from east to west
(towards the northern portion of the Study Area) However these interpretations were based on a
limited number of data points confined to the Pervel flock plant property
InterRoyal Corporation
The InterRoyal Corporation is located adjacent to and just north of the main Pervel facility
described above The CTDEP files include a memorandum from the NUS Corporation to EPA
dated August 18 1989 which references a 1984 Preliminary Assessment performed by CTDEP
which recommended that a low priority Site Inspection be performed The NUS memo presents a
chronology of Site activities up to 1989 which includes CTDEPs 1987 finding that the company
was in violation of several State Hazardous Waste Management regulations and CTDEPs
subsequent revocation of InterRoyals NPDES permit Based on a CTDEP 1988 Site inspection
NUS recommended to EPA that a high priority Screening Site Inspection be conducted
In 1988 InterRoyal contracted an environmental consultant to prepare an environmental
assessment (EA) for the proposed sale of the property The EA report (ERT 1988) concluded
that substantive on-site contamination of groundwater surface water and soils existed The
principal contaminants were identified as VOC (including TCE trans-l2-DCE PCE vinyl
chloride toluene and xylenes) and priority pollutant metals Groundwater flow direction was
described in the EA report as principally towards the south and southwest
5797wpdoc8galluprifinaltextmasterrifhl061297 1-16 QZT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
20 Field Investigations
This Section describes the field methods and procedures used to accomplish the various field
investigation tasks performed during Phase 1A and Phase IB Also included are descriptions of
any deviations from the approved Work Plan As noted in the appropriate subsections any
deviations from the Work Plan were approved by EPA (or EPAs oversight contractor) prior to
implementation Discussions of the findings results and significance of these investigations are
presented in Sections 3 and 4 of this Report
21 Site Survey 211 Initial Site Survey At the start of the Phase 1A field investigation an initial Site survey was performed to confirm
and update the location and elevation of features included in the base map provided by EPA (EPA
drawing number 707600 dated October 14 1993) The initial Site survey also served as Site
control by establishing a 250-foot grid across the entire Site which was identified by the
installation of labelled stakes at the intersection of each 250-foot grid line Horizontal control for
the 250-foot grid (and all subsequently surveyed features) coincides with the Connecticut State
Plane Coordinate System North American Datum of 1927 Vertical control coincides with the
National Geodetic Vertical Datum (NGVD) of 1929 and was established using nearby USGS benchmarks The 250-foot grid (shown on Plate 2-1) provided known reference locations from
which field personnel could measure the locations of Site features
In addition to the 250-foot control grid the initial survey also established a series of parallel lines
(trend lines) across the Site for use during subsequent visual reconnaissance and geophysical
surveys The trend lines (also shown on Plate 2-1) are roughly parallel to the Providence amp Worcester railroad which abuts the western edge of the property The first trend line (Line A)
was located approximately 50 feet east of the railroad right-of-way with subsequent lines (Line
B through Line HH) spaced at 25-foot intervals Each of the trend lines were staked at 250shy
foot intervals using labelled stakes
212 As-Installed Survey
Following the initial Site survey additional surveying events were performed as needed
throughout the duration of the Phase 1A and Phase IB field investigation programs to locate
various sampling locations and other pertinent investigation features These subsequent surveys
were initiated shortly after the completion of each investigation task Besides the various
surveyors control features such as temporary benchmarks and turning points the features
surveyed included wetland delineation flags surface watersediment and wetland soil sampling
5797wpdocsglaquolluprifinlaquoltextrnasterrifhl061297 2-1 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
locations microwells soil vapor points soil borings monitoring wells (existing and newly
installed) stream gauges piezometers and seismic survey lines
All pertinent investigation-related features within approximately 1500 feet of the Site were
included in the survey Several surface watersediment sampling locations beyond 1500 feet from
the Site were not surveyed and their locations are estimated based on their proximity to mapped
physical features such as bridges or roads
The surveying services for this investigation were performed by KWP Associates Inc of Pomfret
Center Connecticut a licensed and registered surveyor in the State of Connecticut The survey
was completed as a third-order plane survey as defined by the standards and specifications in
Exhibit 14-1 of the Compendium of Superfund Field Operations Methods December 1987
(USEPA 1987)
22 Site Reconnaissance 221 Visual Observations of the Ground Surface
A visual reconnaissance of the Site was conducted during an approximate three week period
beginning on August 23 1994 and ending on September 13 1994 During the visual Site
reconnaissance the entire length of each trending line (shown on Plate 2-1) was walked to
identify and map any features which may have been indicative of unknown disposal areas Any
features such as areas of stained soil partially buried man-made objects remnants of buildings
abandoned equipment containers (eg drums tanks) pits depressions mounds and any other
apparent unnatural materials were photographed and noted on field maps and in a field notebook
Also potential disposal features identified during review of historic aerial photographs (Bionetics
Corporation 1990) were located and investigated The locations of features were flagged and
approximated using the survey stakes installed during the initial Site survey The results of the
field reconnaissance were also used to determine additional soil gas sampling locations (described
in Section 25) during subsequent Phase 1A investigations
222 Air Quality Survey
A baseline air quality survey was conducted prior to the start of Phase 1A intrusive field
investigations The survey was performed using a photoionization detector (PID) equipped with
an 117eV lamp to measure total VOC vapors and a direct reading aerosol monitor (RAM-1) to
measure respirable particulates Baseline air quality readings were recorded at eight stations
(AM-1 through AM-8) located across the Site The monitoring stations included areas along the
Site perimeter as well as interior locations at the three known former disposal areas The
locations of the eight baseline air monitoring stations are shown on Plate 2-2
5797wpdocsgalluprifinaltextmlaquo8temfnl061297 2-2 QZT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
In addition to the baseline air quality survey air monitoring was performed on a weekly basis at the eight locations during the entire Phase 1A field investigation Wind direction wind speed
temperature and barometric pressure were also continuously monitored at an on-site
meteorological station
During the Phase IB investigation quantitive air monitoring was performed for site specific
compounds The Phase IB air sampling was performed in the vicinity of the Former Primary
Disposal Area on October 24 1995 This location was selected based on the findings of the
Phase 1A field program Four samples were collected along the perimeter of the Former Primary
Disposal Area at the northern southern eastern and western edges of the perimeter One
background sample was collected at a location approximately 300 feet south of and upwind from the Former Primary Disposal Area The sample locations are shown in Plate 2-2 The samples
were analyzed for the following volatile organic compounds (VOC) toluene ethyl benzene xylenes (total) and tetrachloroethane (PCE) and polychlorinated biphenyls (PCBs)
VOC samples were collected on stainless steel Tenax tubes which were connected to Dupont
Alpha 1 sampling pumps Samples for PCBs were collected on 037z glass fiber filters using
Dupont Alpha 1 and BIOS AirPro 6000D sampling pumps The sampling media was attached to
the sampling pumps using silicone tubing The pumps were secured to wood stakes and
positioned approximately 5 feet above the ground surface
The pumps used to collect the VOC samples were set to pump at a flow rate of between 0014 to
0016 liters per minute and allowed to pump approximately eight hours The pumps used to collect the PCB samples were set to pump at a flow rate of between 27 and 33 liters per minute
and were allowed to pump approximately eight hours All of the sampling pumps were calibrated prior to and after the sampling event using a primary gas flow mini-Buck Model M-5 Calibrator
Ambient meteorological conditions including temperature relative humidity barometric pressure
and wind speed and direction were monitored during the sampling event using ESEs on-site Qualimetrics meteorological monitoring instrument
A VOC and a PCB field blank were collected at background location AS 105 The VOC Tenax
tube and the PCB glass fiber filter were appropriately labeled opened and then immediately
resealed The field blanks were stored and shipped with the samples
At the completion of the sampling event the VOC Tenax sample tubes (including the field blank)
were sealed placed in clean plastic bags and refrigerated at 4degC until they were shipped The
samples were then shipped to the laboratory in coolers The PCB sample filters were sealed
5797wpdocsgalluprifinaltextmasterrifhl061297 2-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
wrapped in bubbie wrap and packed along with the PCB field blank in a cardboard box for
shipment to the laboratory An unopened VOC Tenax tube and PCB glass fiber filter were
submitted with tae samples as a trip blank The VOC Tenax sample field blank and trip blank
tubes were packed in a cooler with ice and sent to ESEs Denver Colorado Laboratory where
they were analyzed by EPA Method TO1 The PCB glass fiber sample field blank and trip
blank filters were sent to ESEs Denver Colorado Laboratory where they were analyzed by
SW846 EPA Method 8080 The results of the air quality survey are discussed in Section 44
223 Exclusion Zone Identification
Prior to the start of Phase 1A field activities preliminary exclusion zones were identified to limit
the risk of workers exposure to potentially hazardous conditions Based on existing data and
observations made during the Site visual reconnaissance the three known former disposal areas
and the area immediately surrounding a former CTDOT asphalt plant structure were staked and
flagged with caution tape A contaminant reduction zone (CRZ) was established adjacent to the
exclusion zone in the prevailing upwind direction during investigations at each location The
CRZ was established for decontamination operations of Site personnel and equipment
224 Project Support Measures
All field investigations were managed from a field office located within an approximate 10000
square foot support center which was situated at the southern end of the Site along Tarbox Road
The support center consisted of an approximate 100 foot by 100 foot area surrounded by a 6 foot-
high chain link fence The support center housed an office trailer an impermeable bermed
decontamination pad lined with 60 mil thick textured HDPE potable water storage tanks storage
units (drums dumpsters and tanks) for investigation derived wastes the weather station and
portable sanitary facilities The office trailer was connected to electric utilities and telephone
service to facilitate normal business and emergency operations A storage trailer for supplies and
equipment was located adjacent to the support center
The field office was used to support field activities by providing the following services
bull personnel sign-in and sign-out sheets
bull daily field activity log book
bull Health amp Safety log book
bull storage of Personal Protective Equipment (PPE)
bull communications center
bull posting of project plans
bull management of project field files
bull briefingmeeting room to coordinate field activities
5797wpdocsgalluprifinaltextmasterrifW061297 2-4 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull meeting place for emergency evacuations and
bull lunch area
The support center also provided an access control point for the Site as it is the only practical
location where four wheeled vehicles could enter or exit the Site Other non-vehicular access
points were blocked with boulders or mounded soils Other access to the Site is limited due to
the presence of heavy vegetation steep slopes and wetlands In addition warning signs
prohibiting trespassing were posted every 100 feet along the Site perimeter prior to the start of
Phase 1A field activities
225 Identification of Sensitive Human Receptors
A survey to identify potential human receptors in the vicinity of the Site was performed This
survey was used to identify any private water supply wells schools nursing homes and day care
facilities located within a one mile radius of the Site The survey was performed by reviewing
available records and documents from the following sources
bull Town of Plainfield Municipal Offices
bull Northeast District Health Department
bull Connecticut Department of Environmental Protection
bull Connecticut Natural Resource Center and
bull Connecticut Department of Health and Addiction Services
In addition to the file reviews interviews were conducted with neighbors and knowledgeable local
people Finally a windshield survey was conducted for the area located within a one mile radius
of the Site
23 Geophysical Surveys During the Phase 1A investigation comprehensive geophysical surveys of the Site were conducted
by Weston Geophysical Corporation of Northborough Massachusetts using electromagnetic
terrain conductivity (EM) magnetometer (MAG) and seismic refraction survey techniques The
purpose of the EM and MAG surveys was to obtain Site-wide screening data to identify the
locations if any of potential subsurface disposal features or objects such as pits trenches drums
or tanks The initial EM and MAG surveys were conducted along each of the trend lines
established during the initial Site survey as shown on Plate 2-1
The purpose of the seismic refraction survey was to determine the location and orientation of the
inferred bedrock fault (if present) in the central portion of the Site Although bedrock
characterization was not one of the intended purposes of the MAG survey subsequent review of
5797wpdocsgalluprifinaltextmasterriftil061297 2-5 QSTT Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
the acquired MAG data provided some information regarding the nature of the shallow bedrock
surface in the central portion of the Site
The presence of heavy vegetation over much of the intended survey area required approximately
two weeks of brush cutting and clearing in order to gain access to the trending lines and to ensure
complete coverage of the Site Once the proposed survey lines were accessible the initial MAG
and EM surveys were conducted along each trending line with data collected at five-foot intervals
The Work Plan stated that the five-foot intervals would be determined by laying a fiberglass
measuring tape along each trend line between survey stakes However the presence of heavy
vegetation prohibited the efficient use of this technique Since the exact locations of any
unexplained anomalies would be later determined during subsequent EM and MAG surveys (and
confirmed during test pit explorations) it was determined that the five-foot intervals could be
efficiently and accurately estimated by an experienced equipment operator by counting paces
between intervals and making adjustments as necessary at each survey stake (which were located
every 250 feet along each line)
As stated in the Work Plan ground penetrating radar (GPR) was to be used if necessary to
further characterize any unexplained anomalies identified during the initial EM and MAG surveys
The presence of abundant vegetation and rough ground surface conditions in the areas of interest
precluded the reasonable use of GPR As approved by EPA the precise locations of unexplained
anomalies identified during the initial EM and MAG surveys were determined during additional
EM and MAG surveys using a finer (5 foot by 5 foot) survey grid superimposed over the general
vicinity of each anomaly
The seismic refraction survey was conducted along six roughly parallel lines which were placed
normal to the anticipated strike of the inferred bedrock fault The locations of the six seismic
lines are shown in Plate 2-3 Each seismic line (Line 1 through 6) is comprised of two 250-foot
long lines which overlap by 125 feet This resulted in a total of 375 feet of continuous coverage
along each line
A complete report provided by Weston Geophysical Corporation describing the theoretical basis
for these surveys is presented as Appendix A Generalized discussions describing the field
methods and equipment used during each geophysical survey are presented below
5797wpdoclaquogalluprifinaltextmastemfnl061297 2-6 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
231 Electromagnetic Terrain Conductivity (EM) Survey
The initial EM survey was performed by Weston Geophysical Corporation over a three day
period (September 14-16 1994) using a Geonics EM-31 electromagnetic terrain conductivity
logger and a Model 720 Polycorder Background terrain conductivity readings were collected at
the beginning and end of each day from an area determined to be relatively free of electrical
interference The background station was located at the extreme southeastern corner of the Site
well away from the overhead electrical lines located along Tarbox Road and Route 12 (Norwich
Road) The EM-31 was calibrated daily by the operator and data was downloaded in the field to
a computer as needed typically twice a day
Following daily calibration the EM survey was performed by the instrument operator who paced
the entire length of each trend line with the EM meter and data logger Terrain conductivity
measurements were made and digitally recorded at five-foot intervals along each line The
presence of surficial objects and other features (eg steel fencing) that would cause interference
or produce anomalies were noted in the field notebook and accounted for during the data
evaluation Terrain conductivity data were subsequently plotted on a base map of the Site and
contoured to produce the terrain conductivity contour map included in the Weston Report in
Appendix A The results of the EM survey are discussed in Section 413
232 Magnetometer (MAG) Survey
The initial MAG survey was conducted by Weston Geophysical Corporation over a period of 7
days (September 7-14 1994) using two GEM-VI and one EGampG Model 856 magnetometers The
two GEM units were used for data acquisition while the EGampG unit was used as a base station to
monitor diurnal changes in the earths magnetic field The base station was established at the
southeastern corner of the Site where there was no interference from metallic objects or overhead powerlines and where no significant magnetic field gradients were observed
The MAG survey was performed by walking each trending line wiih one of the data acquisition
magnetometers (GEM-VI) and recording the magnetic field at every five-foot interval determined
by pacing The MAG data were eventually corrected for diurnal background fluctuations in the
earths magnetic field as determined at the base station and plotted on a base map to produce the
magnetic contour map which is included in the Weston Report in Appendix A The results of the
magnetometer survey are discussed in Section 413
5797wpdocsglaquolluprifinaltextmlaquo8terriftJ061297 2-7 QST Environmental
Gallups Quarry SuperUna1 Project - Remedial Investigation
233 Additional EM and MAG Surveys
In lieu of GPP surveys additional EM and MAG surveys were performed to determine the
precise location of any terrain conductivity or magnetic anomalies which could not be explained
by the presence of surficial metallic debris The additional surveys were performed over a 5-foot
by 5-foot grid in the vicinity of each unexplainable anomaly
A total of four unexplainable anomalies within three separate areas were eventually investigated
with additional EM and MAG surveys Once the locations of the anomalies were accurately
located each anomaly was further assessed by excavating test pits to identify the source of the
anomaly The test pit operations are discussed in Section 214 and the findings of the test pit
excavations are discussed in Section 4133
234 Seismic Refraction Survey
A seismic refraction survey was conducted along six 375-foot lines located within the suspected
fault zone An ABEM Terraloc 24-channel digital recording seismograph system was utilized for data collection The 375-foot spread lengths consisted of two overlapping 250-foot long lines
with geophones spaced in ten-foot intervals The endpoints of each seismic line were staked in
the field to facilitate the subsequent location survey
In accordance with the Work Plan shot points were located at each end point midpoint and
quarter point in addition to an offset from each end point The Work Plan had stated that
seismic energy would be produced by either an elastic wave generator or weight drop However
due to access constraints at the Site EPA approved the use of an alternate energy source For
these surveys seismic energy was generated using 8 gauge seismic shotgun shells discharged
approximately 2 to 3 feet below ground surface
The energy created by the shell blast travels through the ground and refracts along interfaces
between materials of different propagation velocity and density characteristics Interpretation of
these data on a time vs distance plot is conducted for the seismic wave arrival times at each
geophone The propagation velocities can be categorized into various geologic materials such as
overburden saturated overburden bedrock formations and weathered or fractured formations A
comprehensive discussion of the theoretical basis and operation of this technique is presented in
the Weston Geophysical report provided as Appendix A The results of the seismic refraction
survey are discussed in Section 32
5797wpdoc8gaIIuprifinaltextmasterrifnl061297 2-8 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
24 Groundwater Sampling Using Temporary Well Points Between August 29 and October 7 1994 a total of 60 small-diameter temporary well points
(microwells) were installed at predetermined locations using direct push techniques for the
purpose of collecting groundwater samples for both on-site and off-site chemical analysis At 10
of these locations equipment refusal occurred prior to encountering groundwater thus reducing
the total number of sampled locations to 50 The results of the chemical analyses were used to
determine the nature and extent (both horizontal and vertical) of groundwater contamination (VOC
and metals) within the Study Area Data obtained during this survey were ultimately used to determine the optimum location for subsequently-installed permanent groundwater monitoring
wells The surveyed locations of the temporary well points (TW101-TW160) including the 10 unsampled locations are shown on Plate 2-4 A summary of the locations and depth intervals for
each microwell is presented in Table 2-1
A total of 126 samples were analyzed on-site for selected VOC using a portable gas chromatograph (GC) A total of 121 samples (not including duplicates and field blanks) were
submitted for off-site laboratory analysis for cyanide and metals Also 12 samples (not including
field blanks and trip blanks) were submitted for off-site laboratory analysis for VOC to confirm
the on-site GC analytical data
The microwells were comprised of a 082 inch diameter (062 inch inside diameter) steel riser
pipe of varying lengths equipped with a hardened steel tip and a 5 foot long slotted section at the
leading end The 5 foot long slotted section (or screen) consisted of a four longitudinal rows of 2
inch long by 0015 inch wide slots Each microwell was advanced into the subsurface using
either an electrically or hydraulically powered vibratory impact hammer which was mounted on a
telescoping mast The mast drive-hammer and all other ancillary equipment were mounted on an all-terrain vehicle for maximum mobility
Individual sections of riser pipe (which varied in length up to a maximum of 21 feet) were
connected using a slip coupling over the butted ends of adjacent sections The slip coupling is
either electrically welded or crimped (using a hydraulic crimping tool) over the connection to
form a water tight joint
All materials were steam cleaned prior to use and only used at one location to avoid cross
contamination between sampling locations
The objective at each location was to drive the microwell into the saturated overburden and collect
a groundwater sample from three successively deeper intervals The desired sampling intervals
were as follows five feet below the top of the water table midway between the top and bottom of
5797wpdocsgalluprifinaltextmlaquoraquotemfhl061297 2-9 QST Environmental
Gallups Quarry SuperUna1 Project - Remedial Investigation
the aquifer and at the bottom of the aquifer (ie the refusal depth) A middle andor deep sample
was not collected if refusal was encountered without significant advancement of the well point
between sample depths (minimum of 10 feet) The midpoint sampling depth was estimated based
on the refusal depths encountered at nearby microwells
Once the microwell was driven to the desired depth purging and sampling was accomplished
using a manually operated inertial pump comprised of an adequate length of dedicated 38 inch
(inside diameter) polyethylene tubing equipped with a bottom check valve In operation the
inertial pump is lowered into the screen section of the microwell and repeatedly raised and
lowered (manually) a distance of approximately one foot This reciprocating action causes water
to rise within the tube until it is ultimately discharged at the ground surface into either a bucket or
sample container Between one and three riser volumes were purged from each microwell prior
to sample collection except for the first sample (5 feet below the top of the water table) which was
collected without purging All purge water was containerized and eventually transported off-site
for treatment and disposal
Once a groundwater sample was acquired it was labelled packed in a cooler and transported to
the on-site laboratory Each sample was analyzed on-site using a portable gas chromatograph
for the following eight VOC
bull l2-dichloroethene(DCE)
bull 111 -trichloroethane (111 TCA)
bull trichloroethene (TCE)
bull benzene
bull toluene
bull acetone
bull methyl ethyl ketone (MEK)
bull methyl iso-butyl ketone (MIBK)
Groundwater samples from each location were also collected filtered through a 045 micron
filter preserved with nitric acid and submitted to an off-site laboratory for analysis for the
following metals
bull aluminum
bull arsenic
bull cadmium
bull chromium
bull copper
5797wpdoc8galluprifinaltextmasterrifhl061297 2-10 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
bull iron
bull lead
bull manganese
bull nickel
bull zinc
Unfiltered samples were also collected preserved with sodium hydroxide (NaOH) and submitted
for analysis for cyanide In addition duplicates of 12 of the VOC samples analyzed in the field
were submitted for laboratory analysis for VOC for confirmation purposes Samples for off-site
VOC analyses were preserved in the field by addition of hydrochloric acid (HC1) to obtain a pH
less than 2
Samples for on-site VOC analyses were collected into 40 ml glass vials equipped with a teflonshy
lined silicon septum Each vial was filled capped labelled and refrigerated until it was
analyzed Samples were typically analyzed within several hours of collection Prior to analysis
the sample was removed from the refrigerator and 10 ml of water was withdrawn and discarded
The withdrawal of 10 ml of water created a headspace within each vial into which any VOC
present in the liquid would partition To complete the VOC partitioning process the vial was
then placed into a constant temperature (90 degC) water bath for a minimum of 15 minutes Just
prior to analysis a 250 micro-liter air sample was withdrawn from the headspace within the vial
by inserting the needle of the syringe through the teflon-lined septum and injected into the
portable gas chromatograph for analysis
A Photovac 10S50 portable gas chromatograph equipped with a CPCIL 5 encapsulated column
was used for on-site analysis The Photovac 10S50 gas chromatograph (GC) was filled every
morning with zero grade air and allowed to warm-up for 30 minutes prior to daily operation in
accordance with SOP 4001 and manufacturers instructions
The GC detector flow oven temperature and gain setting (sensitivity setting) were checked and
verified every morning and throughout the day Field GC standards were prepared daily by
diluting commercially available certified pure liquid chemical standards with deionized water
Three separate standards a low-concentration level a mid-concentration level and a high-
concentration level standard containing the eight select VOC were prepared in order to obtain a
three-point calibration curve Glass gas-tight syringes were used for preparation of standards and
sample injection AH syringes were decontaminated using methanol deionized water and
compressed gaseous nitrogen
5797wpdocsgalluprifinaltextmlaquo8terrifhl061297 2-11 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The GC operating condition was checked in the morning and during the day using machine
blanks syringa blanks and standards All three standards were run with a syringe blank directly
before and after each injection after every ten samples and at least once in the morning and once
in the afternoon each day In accordance with the QAQC program and SOP 4009 a duplicate
groundwater sample was collected in the field in a separate 40 ml glass vial immediately
following the collection of the original sample The second vial was used for duplicate analyses
after every ten samples
In the event that a sample analysis showed a contaminant chromatographic peak with an area
greater than the high-concentration standard or the range of the GC operating parameters (off-
scale) a smaller aliquot (l10th the original sample injection volume) was taken from the second
vial and injected into the GC All pertinent information concerning the smaller aliquot was
recorded on the GC strip chart and in the field log book
The GC strip chart was labeled with the sample identification number or corresponding
identification information (eg sample ID syringe blank etc) All pertinent information (eg
sample ID) was recorded in a field log book
In accordance with the QAQC program all samples were kept at 4degC prior to analysis and were
analyzed within 48 hours of their collection time
A total of 23 microwells (TW101-TW123) were installed by Pine and Swallow Associates Inc of
Groton Massachusetts Due to limited ability to access certain locations with the available
equipment the remaining 37 microwells were installed by a second subcontractor MyKroWaters
Inc of Concord Massachusetts Installation logs are presented in Appendix B The results of
the microwell survey are discussed in Section 421 The microwell installations were later
abandoned by filling them with cement grout and cutting the risers off below the ground surface
25 Soil Gas Survey In an effort to identify the location of any previously unknown potential disposal areas a Site-
wide soil gas survey was conducted From September 26 1994 through October 12 1994 a
total of 106 soil gas sampling probes were installed across the Site Soil gas samples were
analyzed on-site using a portable gas chromatograph
A 100-foot sampling grid was used to systematically cover the Site however actual locations
were dependent on accessibility and the ability to advance the soil gas probes to the desired depth
beneath the ground surface Besides the sampling at the intersection of grid lines six additional
locations were investigated due to the presence of empty drums found at the ground surface
5797wpdoC8galluprifinaltextmastemfnl061297 2-12 QST Environmental
Gallups Quarry Superfiind Project - Remedial Investigation
during the Site reconnaissance or anomalies detected during the EM and MAG surveys The
extreme northeastern corner and eastern side of the Site were not included in the soil gas survey
since they are either wetlands or heavily wooded Also an approximate 15000 square foot area
just north of the Former Seepage Bed was not tested due to the presence of a large pile of
boulders The surveyed locations of each soil gas sampling point (SV101-SV206) are shown in
Plate 2-5 The locations of SV111 SV201 and SV141 are approximate based on field
measurements from surveyed locations
Each soil gas sampling probe consisted of a four inch long hardened steel combination drive
point and screen which was connected to an adequate length of 316 inch diameter polyethylene
tubing The pointscreen and tubing assembly were inserted inside a hollow steel shaft which was
then driven into the ground with an electrically powered vibratory hammer
An abundance of gravel cobbles and boulders in the central portion of the Site prohibited the
advancement of several probes to the minimum depth specified in the Work Plan (25 feet) After
discussions with EPAs oversight contractor regarding the surface conditions in this area it was
agreed that at the rocky locations the probe would be driven as far as possible (typically 15-2
feet) and a two-foot by two-foot sheet of polyethylene sheeting would be placed on the ground
surface surrounding the probe and weighted with native topsoil The purpose of the plastic sheet
was to minimize atmospheric influence during the sampling procedure
Once the point was driven to the sampling depth the hollow steel shaft was extracted leaving the
expendable pointscreen and tubing in place The small annular space surrounding the sampling
tube was tightly packed with native soil to ensure that gas samples were representative of soil
pore space and not atmospheric conditions Once the probe was in place any excess plastic
tubing was trimmed leaving approximately 15 feet of tubing above the ground surface Each
tube was clamped and sealed until it was eventually sampled typically within a few days of
installation
To collect a soil gas sample one end of a 280 ml glass sample chamber (equipped with teflon
stopcocks and a sampling septum) was connected to the tubing using a short length of silicon
tubing A battery-operated vacuum pump was then attached to the other end of the chamber and
used to draw a soil gas sample from the tubing Once a sample was acquired the stopcocks were
closed and the pump shut off The sample chamber was then transported to the on-site laboratory
for analysis
Just prior to analysis the needle of a gas tight syringe was inserted through the sampling septum of the glass chamber and an aliquot of the soil gas sample was removed The sample was then
5797wpdoclaquogalluprifinaltextma8terrifiU061297 2-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
injected into the gas chromatograph for analysis A Photovac 10S50 portable gas chromatograph
was used to analyze each sample for the following 8 VOC
bull l2-dichloroethene(DCE)
bull 111-trichloroethane (111 TCA)
bull trichloroethene (TCE)
bull benzene
bull toluene
bull acetone
bull methyl ethyl ketone (MEK)
bull methyl iso-butyl ketone (MIBK)
The Photovac 10S50 gas chromatograph (GC) was filled every morning with zero grade air and
allowed to warm-up for 30 minutes prior to daily operation in accordance with SOP 4001 and
manufacturers instructions
The GC detector flow oven temperature and gain setting (sensitivity setting) were checked and
verified every morning and throughout the day Field GC standards were prepared daily using
certified pure neat liquid standards from sealed vials Glass gas tight syringes were used for
preparation of standards and sample injection All syringes were decontaminated using methanol
deionized water and nitrogen
The GC operating condition was checked in the morning and during the day using machine
blanks syringe blanks and standards Standards were run with a syringe blank directly before
and after each injection every ten samples In accordance with the QAQC program a duplicate
soil gas sample was collected in the field in a separate glass sample chamber immediately
following the collection of the original sample After the original sample was injected into the
GC the duplicate sample from the separate glass sample chamber was injected into the GC The
data quality objective (DQO) for field analysis using the GC was maintained at or better than _+
30 relative percent difference In the event that a sample analysis showed a contaminant
chromatographic peak with an area greater than the range of the GC operating parameters (off-
scale) a smaller aliquot (I10th the original sample injection volume) was taken from the glass
sample chamber and injected into the GC AH pertinent information concerning the smaller
aliquot was recorded on the GC strip chart and in the field log book
5797wpdocsgalluprifinaltextma8teiTifiil061297 2-14 QST Environmental
Gattups Quarry Superfund Project - Remedial Investigation
The GC strip chart was labeled with the sample identification number or corresponding
identification (eg sample ID syringe blank etc) The analysis number and corresponding
identification information was also recorded in the soil gas survey field log book
All sampling equipment (exclusive of the dedicated expendable probes) was decontaminated between each sample by flushing with copious amounts of compressed nitrogen The results of the
soil gas survey are discussed in Section 41
26 Soil Borings at Disposal Areas A total of sixteen soil borings SB101 through SB116 were advanced at the three known former disposal areas Ten soil borings (SB 101 through SB110) were completed as part of the Phase 1A
investigation between October 4 and 13 1994 Six additional borings were advanced within the
Former Primary Disposal Area on November 2 1995 as part of the Phase IB investigation The
locations of the soil borings are shown on Plate 2-5 The objective of these borings was to obtain
soil samples to characterize subsurface lithology and determine the present level and distribution
of residual contaminants within each former disposal area The analyses performed on samples
collected during the Phase 1A investigation (ie SB101-SB110) included TCLTAL parameters
as well as pH (EPA Method 9045) total organic carbon (ASTM Method D 17565373) moisture
content and particle size distribution Samples collected during the Phase IB investigation
(SB111-SB116) were submitted for laboratory analyses for VOC and PCBPesticides The samples submitted for analysis and the depth intervals sampled are shown in Table 2-2 The
results of the soil boring program are discussed in Section 41 All soil boring logs are shown in
Appendix C
261 Piiase 1A Soil Borings Each boring completed as part of the Phase 1A investigation was advanced until equipment refusal was encountered using a truck mounted drill rig equipped with a 425 inch (inside diameter)
hollow stem augers The drilling operations were performed by Environmental Drilling Inc of
Sterling Massachusetts As shown in Plate 2-5 three of the borings were placed in the reported
location of the Former Seepage Bed (SB101-SB103) three were placed within the Former
Secondary Disposal Area (SB104-SB106) and four were placed within the Former Primary
Disposal Area (SB107-SB110) The Work Plan required that samples be collected and submitted
for laboratory analysis from each boring from specific depth intervals (0-1 foot 1 to 10 feet and
10 feet to the water table) and from each distinct hydrological unit encountered (eg coarse
stratified drift fine stratified drift and till) and from the capillary fringe at each disposal area
The number of samples actually submitted for analysis was dependent on the depth to water and
the number of hydrogeologic horizons encountered at each area In general samples submitted
579Twpdoc8galluprifinaltextmlaquo8terrifhl061297 2-15 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
for laboratory analysis were selected from within each depth range or horizon based on PID
readings andcr visual observations
Soil samples from the 0-1 foot interval were collected from the ground surface using a stainless
steel hand trowel All subsequent samples were collected using a standard 2-inch diameter split-
spoon sampling device in accordance with ASTM Method D-1586-84 Each sample was
screened in the field for total VOC using a PID equipped with an 117 eV lamp Each sample
was then visually classified and logged in a field notebook and on boring logs A portion of each
sample was placed into glass jars and sealed with aluminum foil and a screw cap for headspace
analysis The headspace sample was ultimately saved for archival purposes
All sampling equipment was decontaminated prior to use and between each sample using a
detergent wash and tap water rinse followed by methanol nitric acid and deionized water rinses
All drilling equipment was steam cleaned between boring locations All decontamination rinseates
were containerized and eventually transported off-site for treatment and disposal Likewise all
soil cuttings were containerized for eventual off-site disposal Upon completion each borehole
was filled to the ground surface with a bentonitecement grout mixture and marked with a labeled
stake so that its location could be surveyed
262 Phase IB Soil Borings
Data obtained during the Phase 1A investigation indicate the presence of residual soil
contamination in the vicinity of the Former Primary Disposal Area In order to more fully
characterize the extent of this residual contamination six additional soil borings were completed
along the perimeter and within the Former Primary Disposal Area These borings (SB111shy
SB116) were installed by Connecticut Test Borings Inc of Seymour Connecticut using a track
mounted drill rig equipped with a standard split-spoon soil sampler Two samples from each
boring were submitted for laboratory analysis of TCL VOC and pesticidesPCBs At each
location a surface soil sample was collected from the 0-1 foot interval and submitted for
laboratory analysis Soil samples were then collected continuously from a depth of 1 foot below
the ground surface to the water table A discrete sample from within this zone was submitted for
laboratory analysis based on PID results At locations where no elevated PID headspace readings
were encountered a sample collected from the capillary zone was submitted for laboratory
analysis
5797wpdocsglaquolluprifinaItextmraquo8terrifiil061297 2-16 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
27 Installation of Monitoring Wells and Background Soils Sampling
Following the evaluation of data obtained during the visual Site reconnaissance and microwell
and soil gas surveys a network of monitoring wells was designed that would allow groundwater sampling and analysis and measurements of hydraulic parameters The installation of monitoring
wells at upgradient locations was also included to allow collection of background soil samples and
to determine upgradient groundwater quality
The majority of the Phase 1A investigation monitoring wells were installed by Environmental
Drilling Inc of Sterling MA A second drilling contractor Maher Environmental of North Reading MA was added in December in order to complete the monitoring well program before
the onset of winter The well installation program began on November 7 1994 and was completed on December 29 1994
The original Work Plan specified that a total of 47 monitoring wells would be installed but contemplated that the final number and locations of the monitoring wells could be adjusted based
on the findings of the preliminary screening surveys (ie the microwell and soil gas surveys)
Based on these data which were presented to EPA throughout the course of the screening surveys
EPA approved a Phase 1A monitoring well network which consisted of a total of 39 monitoring
wells at 16 locations
During the course of the Phase 1A monitoring well installation program one anticipated
intermediate depth overburden well (MW109T) was not installed because there was only
approximately 35 feet of saturated overburden encountered at that location A total of 38
monitoring wells at 16 locations were installed The surveyed locations of these wells are shown on Plate 2-6
By the end of the Phase 1A field program a total of 16 locations (or clusters) were completed
and were comprised of the following
bull (2) four well clusters (MW105 and MW107)
bull (4) three well clusters (MW101 MW108 MW112 and MW115) bull (8) two well clusters (MW102 MW103 MW104 MW106 MW109 MW113
MW114 andMW116) and
bull (2) single wells (MW110 and MW111)
(Note An additional 6 groundwater piezometers [PZ201-PZ206] were also installed)
5797wpdocsgalluprifinaltextmasterrifhl061297 2-17 QST Environmental
Gallups Quarry Superjvnd Project - Remedial Investigation
To further delineate the nature and extent of contamination and to refine the hydrogeologic
characteristics within the area of investigation a total of seven groundwater monitoring wells (and
one piezometer PZ301) were installed as part of the Phase IB investigation
The wells completed during Phase IB included the following
bull (3) two well clusters (MW117 MW118 and MW119)
bull (1) bedrock well (installed at the Phase 1A location MW102)
All Phase IB monitoring wells were installed by Connecticut Test Boring Inc utilizing a track-
mounted drill rig The surveyed locations of these wells are shown on Plate 2-6
AH monitoring well labels include a suffix code (eg S TT T or B) which indicates the location
of the screened interval (or open interval in the case of bedrock wells) for that particular well
The screen interval for each prefix is
S - Shallow well in which the screen intersects the surface of the water table
TT - Top-of-Till well in which the bottom of the screen is located just above the till
horizon
T - Till well in which the screen was placed within the till horizon and
B - Bedrock well in which the overburden is sealed off with steel casing which is
grouted into the bedrock surface and the well consists of an unscreened open hole
below the top of the bedrock surface
The TT T and B designations are geologically specific (top-of-till till or bedrock) while the S
designation is depth specific Monitoring well MW109S is in fact located within a till horizon but
was designated as an S well since the screen intersected the surface of the water table Similarly
although monitoring well MW110S is designated as a shallow(s) well observations recorded
during its installation indicate that MW110S is set just below the top-of-till interval
Specifically the 45 wells completed during the Phase 1A and IB investigations included the
following
bull 18 shallow (S) water table wells
bull 13 top of till (TT) wells
5797wpdoc8galluprifinaltextmasterrifhl061297 2-18 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull 5 till (T) wells and
bull 9 bedrock (B) wells
271 Phase 1A Monitoring Well Placement-Rationale
2711 Phase 1A Upgradient Monitoring Wells and Background Soil Sampling
Two monitoring well clusters MW109 (S B) and MW112 (S TT B) were installed to provide
soil and groundwater samples from various depths from locations upgradient of the known former
disposal areas These data were obtained to provide chemical data which was assumed to be
representative of background conditions The general location of these two well clusters was in
accordance with the general east to west direction of groundwater flow across the Site which had
been indicated during previous investigations and by the location of the contaminant plume
identified during the microwell survey The location of MW112 cluster (south of the Former
Seepage Bed) would also serve to confirm the presence or absence of radial groundwater flow
patterns away from the Former Seepage Bed During the installation of these wells soil samples
from stratified drift and till horizons were collected and submitted for laboratory analysis for
TALTCL parameters
A shallow top of till and bedrock well were installed at location MW112 The overburden wells
at this location were successfully installed using hollow stem augers A shallow till and bedrock
well were planned for location MW109 However since only approximately 35 feet of saturated
overburden was encountered at that location only one well MW109S was installed in the
overburden
The overburden and bedrock monitoring wells at these locations were constructed in accordance
with the general procedures described above with the exception of MW109S An abundance of boulders at this location prohibited the ability to advance augers or drive casing more than several
feet below the ground surface After numerous attempts within a 100-foot radius of the desired
location a backhoe was ultimately required to excavate a pilot hole in the unsaturated zone to
approximately 8 feet below the ground surface Augers were then lowered into the pilot hole and
advanced to the refusal depth of 12 feet The overburden well was then constructed as described
in Section 273
The bedrock well at MW109 was installed using a mud rotary drilling technique to drill an
overburden pilot hole to the bedrock surface into which 5-inch diameter steel casing was lowered
and seated on the top of the bedrock surface Another pilot hole was then drilled into the bedrock
to receive the permanent 3-inch casing The bedrock was subsequently cored as described in
Section 273
5797wpdoC8galluprifinaltextmaBterriftU061297 2-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
2712 Phase 1A Monitoring Wells - Former Primary and Secondary Disposal Areas
A total of nineteen ground water monitoring wells were installed in seven cluster locations at
downgradient areas relative to the known Former Primary and Secondary Disposal Areas
Monitoring wells MW102 (S TT) MW105 (S TT T B) and MW107 (S TT T B) were
located along the centerline of a groundwater contaminant plume detected during the microwell
survey and earlier studies
Well clusters MW101 (S TT T) MW103 (S TT) MW104 (S TT) and MW106 (S TT) were
located in areas believed to be beyond the edges of the contaminant plume delineated during the
microwell survey These wells were placed at these locations in an effort to define the plume
boundaries In addition the location of MW103 was selected by EPA to address historic
references to a leachate seep reportedly observed at Mill Brook west of the railroad bridge
Besides the nineteen wells described above another six monitoring wells at three locations were
installed in the vicinity of the Former Primary and Secondary Disposal Areas MW116 (S T) MW108 (S TT B) and MW110S were located north northeast and east of the former disposal
areas respectively to confirm the plume boundaries in these areas
2713 Phase 1A Monitoring Wells - Former Seepage Bed Area
A total of three monitoring wells were installed in the general vicinity of the Former Seepage
Bed A single bedrock well MW11 IB was placed west of the Former Seepage Bed within the
potential fracturefault zone identified by the geophysical studies The purpose of this well was to
assist in evaluation of whether the inferred fracturefault zone may be acting as a preferential
contaminant transport pathway from the Former Seepage Bed The location of MW113 (S B)
west of the Former Seepage Bed was selected to confirm water quality and to obtain
hydrogeological data in this area since an abundance of cobbles prohibited the advancement of
microwells into the saturated zone in this area
2714 Phase 1A Monitoring Wells - Southern Portion of the Site
Five monitoring wells located at two clusters (MW114 and MW115) were installed to determine
water quality and to characterize the hydrogeological parameters in the southern portion of the
Site Although there is no evidence to suggest that disposal activities occurred in areas of the Site
south of the Former Seepage Bed MW114 (S TT) and MW115 (S TT B) were placed to
coincide with locations at which low levels of VOC were detected during the microwell survey
5797wpdocsgalluprifinaltextmasterri fhl061297 2-20 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
272 Phase IB Monitoring Well Placement-Rationale The results of the Phase 1A investigation indicate that a well-defined low to moderate-VOC
concentration groundwater plume originates in the vicinity of the Former Primary Disposal Area
The plume is defined by the presence of certain VOC primarily TCA 12-DCE and xylene The
highest concentrations of these compounds were detected at MW107TT with decreasing
concentrations at downgradient well clusters MW105 MW102 and MW101
The compound PCE was detected in groundwater monitoring wells within the plume but its
distribution in groundwater exhibited inconsistencies with migration from the former disposal
areas In addition the observed concentrations of PCE did not coincide with the observed rate of
plume attenuation and transport rates possibly indicating an off-site source A goal of the Phase
IB investigation was to obtain additional information concerning overburden groundwater quality
and flow patterns in the area north-northwest of the Former Primary Disposal Area in order to
assess the potential for an off-site source
2721 Phase IB Monitoring Wells-Former Primary and Secondary Disposal Areas
One bedrock monitoring well (MW102B) was installed downgradient of the Former Primary and
Secondary Disposal Areas as part of the Phase IB investigation Data collected during the Phase
1A field program indicate that bedrock hydraulic gradients are generally upward across the Study
Area and that bedrock is not a preferential pathway for contaminant migration However low
concentrations of certain VOC were detected in bedrock well MW105B located downgradient of
the Former Primary Disposal Area To determine the nature of contaminant migration in bedrock
further downgradient from the source area a bedrock monitoring well was installed in the vicinity
of well cluster MW102 During the installation of MW102B soil samples were collected from
three intervals within the saturated portion of the overburden aquifer (15-17 30-32 and 45-57
feet below the ground surface) and submitted for laboratory analysis for total organic carbon
(EPA Method 9060)
2722 Phase IB Monitoring Well - North-Northwest of the Site Data obtained from CTDEP files during the Phase 1A investigation indicate that monitoring wells
located on the western and northern sides of the former Pervel flock plant (located just north of
the Site across Mill Brook) historically contained elevated concentrations of certain VOC
particularly PCE TCA and DCE A contribution of VOC in groundwater from this area could
explain at least partly the VOC detections in the wells at MW101 To confirm the potential for
groundwater flow from the former Pervel facility to the area around well MW101 and to further
refine the understanding of groundwater quality and flow in areas north-northwest of the Former
Primary Disposal Area three additional monitoring well couplets and one groundwater piezometer
5797wpdocsgalluprifinaltextmasterrifiil061297 2-21 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
were installed The Phase IB well couplets designated as MW117 MW118 and MW119
consisted of a shallow overburden well and a deep monitoring well screened above the till
horizon A groundwater piezometer designated as PZ-301 was installed in this area to provide
additional hydraulic data The surveyed locations of the seven monitoring wells and the
piezometer installed as part of the Phase IB investigation are shown on Plate 2-6
273 General Monitoring Well Installation Techniques
At each monitoring well (or cluster) location continuous soil sampling was initiated using either a
truck or track mounted drill rig equipped with 425 inch (ID) hollow stem augers and standard 2shy
inch diameter split-spoons The objective was to continuously sample and complete the deepest
overburden boring at each location using hollow stem augers A variety of subsurface conditions
(eg running sands greater that anticipated saturated overburden thicknesses and an abundance of
cobbles and boulders) prohibited the use of hollow stem augers all the way to completion depth at
many locations In order to overcome these drilling conditions EPA approved drive and wash
drilling techniques using water as a drilling fluid to complete many of the deeper overburden
monitoring wells The source of drilling water for this investigation was a nearby fire hydrant
which is connected to the local municipal potable supply system The introduction of drilling
fluids is generally avoided whenever possible as the presence of foreign fluids may cause some
dilution of any constituents which may be present The subsequent use of low-flow purging and
sampling techniques (discussed in Section 29) gave maximum assurance that samples collected
were representative of the natural formation waters
When drive and wash techniques were used the preferred casing diameter was six-inches Six-
inch diameter casing allowed the construction of a desired filterpack thickness of two inches (for
two inch diameter wells) However five-inch diameter and in some cases four-inch diameter
casing was also used primarily at locations in which access and drilling conditions prohibited the
advancement of six-inch casing in a timely and efficient manner EPA approved the use of five-
and four- inch diameter casing provided that the resulting monitoring wells were capable of
yielding low turbidity groundwater samples (which they ultimately did)
In accordance with the Work Plan continuous soil sampling was attempted at the deepest boring
at each location to provide continuous stratigraphic control However the presence of
uncontrollable running sands within certain intervals at several locations made the timely
collection of continuous viable samples extremely difficult In an effort to adhere to the original
schedule as closely as possible EPA approved lengthening the sampling frequency from
continuous to five-foot intervals at locations where running sands were encountered
5797wpdocsgalluprifinaltextmasterrifhI061297 2-22 QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
At several locations auger or casing refusal during the sampling stage was encountered above the
expected depth to bedrock (ie within or on top of the till horizon) At certain bedrock locations
which did not require further soil sampling EPA approved advancing and setting casing using
mud rotary drilling techniques In cases where drilling mud was used as the circulation media
powdered bentonite (National Sanitation Foundation International approved) was mixed with
potable water to yield a relatively thin drilling mud Once the borehole was drilled and stabilized
with drilling mud permanent steel casing was advanced and set The drilling mud was then
completely flushed from the borehole using fresh water and containerized (along with the water)
for eventual disposal In general the use of drilling mud is avoided whenever possible to
eliminate the introduction of foreign compounds in the aquifer Since drilling mud was used to
drill through overburden material (at bedrock wells only) and drilling mud was never in contact
with bedrock fractures the use of mud is not believed to have had any impact on groundwater
samples collected from these wells
All overburden monitoring wells were constructed using 2-inch diameter schedule 40 PVC well
screen and riser All screens consisted of continuous slot construction with 001-inch wide slots
The filter pack sand size grade was selected based on grain size data obtained during the soil
boring program The size-grade chosen (Morie OON) was selected in accordance with EPA
requirements (4 to 6 times the mesh size which retained 70 of the formation material) Most
screens were 10 feet long however several wells screened in till were constructed using 5-foot
long screens due to the limited thickness of the till horizon at those locations (MW105T
MW112T and MW116T) and the requirement to not install screens across different geologic
horizons Regardless of the screen length the filterpack surrounding the well screen extended a
minimum of one foot above the top of the screen A minimum two-foot thick seal of hydrated
bentonite clay was then emplaced above the filter sand pack Bentonitecement grout was then pumped from the bottom of the remaining annular space surrounding the riser pipe to the ground
surface Stainless steel centralizers were utilized to center the PVC screen within the borehole
Each well was completed with a locking 4-inch diameter steel protective casing which was
cemented in place approximately five feet below the ground surface
The bedrock wells were completed as open hole monitoring wells A minimum of four-inch
diameter steel casing was driven and seated on the bedrock surface A 3875-inch diameter pilot
hole was then drilled a maximum distance of five feet into competent rock Permanent 3-inch
diameter steel casing was then cemented into the pilot hole using tremie pipe and allowed to cure
for a minimum of 24 hours Once cured the grout inside the three inch casing was drilled out to
allow the bedrock to be cored At each location a minimum of 10 feet and a maximum of 25
feet of rock was cored using standard NX coring equipment The termination of all bedrock
wells was dependent on the occurrence of water-bearing fractures identified within the cored hole
5797wpdocsgalluprifinaltextmasterrifhl061297 2-23 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
Coring was terminated when evidence of water-bearing fractures were encountered All bedrock
wells were corHeted as open bedrock wells (ie not screened) as it appeared that the cpen holes
would not in-fl or collapse Each bedrock well was furnished with a locking 4-inch diameter
steel protective casing which was cemented in place over the permanent 3-inch diameter steel
riser
All monitoring wells were developed to remove residual particulates from the well and filter pack
and to restore the natural permeability of the formation Following well completion a minimum
of 48 hours were allowed to elapse before well development was initiated to allow the wells to
equilibrate and the grout to set Development was accomplished by overpumping various sections
of the screened interval until the field geologist determined that the pump discharge was visibly
free of particulate material Well development times varied from well to well and depended upon
the amount of fine (silt-clay) grained material at each screen interval Well development times
were usually on the order of several hours Water generated during well development was
containerized for eventual shipment off-site
All soil boring logs rock coring logs and monitoring well construction logs are provided in
Appendix C A summary table which shows survey data and other pertinent information for each
monitoring well and piezometer is presented as Table 2-3
274 Stream Piezometers and Gauges
Nine piezometers were installed at various locations within Mill Brook to monitor surface water
conditions and to determine the role of the local groundwater system in relation to stream
dynamics Water levels were recorded during several periods of the investigation to determine if
Mill Brook is a discharge or recharge point for groundwater in the vicinity of the Site In
addition five stream gauges were installed at piezometer locations PZ-1 PZ-3 and PZ-6 and at
two additional locations in Fry Brook one above and one below the confluence with Mill Brook
The locations of the stream piezometers and gauges are shown on Plate 2-6
Each stream piezometer consisted of a one-foot long slotted steel well point connected to threaded
and coupled lengths 125 inch ID steel pipe with a threaded cap The piezometers were
manually driven a minimum of two feet into the stream bed Water level readings were collected
by lowering an electronic water level indicator along both the inside and outside of the piezometer
to obtain depth to water readings for shallow groundwater beneath the stream bed and depth to
surface water respectively The stream gauges consist of a graduated steel scale attached to a
steel post which was driven into the stream bed
5797wpdocsgalluprifinaltex1masterrifhl061297 2-24 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
275 Groundwater Piezometers
Although not specified in the Phase 1A Work Plan EPA approved the installation of six shallow
groundwater piezometers (PZ-201 through PZ-206) in the southern portion of the Study Area to
provide additional overburden piezometric data A seventh groundwater piezometer PZ-301
was installed north of the Site during the Phase IB investigation The locations of the
groundwater piezometers PZ-201 through PZ-206 and PZ-301 are provided on Plate 2-6
The seven groundwater piezometers were installed using either a track or a truck-mounted drill
rig equipped with 425 inside diameter hollow stem augers At each location the augers were
advanced and the piezometer set at approximately five feet below the top of the groundwater
table The piezometers were constructed of 1-inch diameter PVC well screen and riser equipped
with five-foot long screens Once the screen was set a sand pack was installed to approximately
one foot above the top of the screen A hydrated bentonite seal was then emplaced on top of the
filterpack The remainder of die annular space was backfilled with clean native soil and capped
with concrete Each piezometer was furnished with a lockable protective casing which was
cemented in place Upon completion each piezometer was surveyed and included in each
subsequent round of groundwater level measurements
28 Aquifer Parameter Testing 281 Grain Size Analysis
A total of 41 soil samples collected during the Phase 1A soil boring and monitoring well
installation programs were submitted for laboratory grain size analysis All grain size analyses
were performed using common sieve and hydrometer techniques in accordance with ASTM
Method D 422-63 (Reapproved 1990)
Of the 41 samples 16 were obtained from horizons described as fine stratified drift 15 were
obtained from horizons described as coarse stratified drift and 10 were obtained from horizons
described as till A total of 29 of the samples were obtained during the soil boring program
and 12 were obtained from samples collected during the monitoring well installation program
The analyses were conducted by Geotechnics Inc of Pittsburgh PA a laboratory which
specializes in geotechnical analyses A summary of the samples submitted and their depth interval
is presented as Table 2-4 The results of grain size analyses are discussed in Section 33 In
addition to grain size these samples were also submitted for laboratory analysis for pH moisture
content and total organic carbon
5797wpdoc8galluprifinaltextmasterrifhl061297 2-25 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
282 Slug Tests
Single-well variable head aquifer tests were conducted on all the wells installed during the Phase
1A investigation between January 5 and 27 1995 Rising and falling head tests were performed
on each well using a manually deployed solid cylinder or slug A pressure transducer and an
electronic data logger were used to measure and record the water level response in the well (on a
logarithmic time scale) after the slug was submerged (falling head) and removed (rising head)
Changes in water levels were recorded until the water had returned to or near the original static
level The data collected from the slug tests were analyzed to determine hydraulic conductivity
values for the screened intervals in each well The rate of change of hydraulic head was analyzed
using the Bouwer-Rice Method (Bouwer and Rice 1976) implemented in the computer program
AQTESOLV (Geraghty amp Miller Inc 1989) The results are presented in Section 33 of this
report
283 Constant Flow Tests
Constant flow tests consisting of short-term pumping tests were performed on selected
groundwater monitoring wells as part of the Phase IB investigation Constant flow tests were performed on the following wells MW102TT MW103TT MW104TT MW105TT
MW107TT MW117(S TT) MW118(S T) and MW119(S TT) In these tests an approximate
steady-state drawdown is established in the well and an analytical model of flow to a well is used
to compute hydraulic conductivity The tests were conducted using a variable speed submersible
pump and an electronic water level indicator Prior to the start of each test the static water level
was determined The tests were conducted by running the pumps at a constant known pumping
rate for short periods of time (typically less than 15 minutes) while recording drawdown until
equilibrium was reached The pumping rate drawdown and well construction details were then
used to calculate the hydraulic conductivity The results of the constant flow tests are discussed
in Section 33 of this report Field data and examples of the data reduction method are presented
in Appendix F
29 Groundwater Sampling In accordance with the Work Plan a complete round of groundwater samples was collected
following completion of the Phase 1A monitoring well installation program during January 11shy
19 1995 and is referred to as the Phase lAJanuary 1995 sampling event Subsequent
sampling events were performed as part of the Long Term Monitoring Program during April
July and November 1995 February May August and November 1996 and February 1997 As
discussed in Section 1-1 of this report individual Data Reports for all of the Long-Term
Monitoring Program sampling events (except November 1995 which was presented with the draft
RI Report) have been submitted to EPA
5797wpdoc8galIuprifin8ltextma8terrifnl061297 2-26 QZT Environmental
Gallups Quarry Suptrfund Project - Remedial Investigation
During the Phase IB field program seven new wells were installed and added to the list of wells
that were sampled (for VOC only) during the November 1995 monitoring event Six of these
wells (MW117STT MW118STT and MW119STT) were not added to the list of wells to be
sampled under the Long Term Monitoring Program although MW102B (also installed during
Phase IB) was added to the Long Term Monitoring list In addition to the wells installed during
the Phase IB investigation the following five existing wells located on the former Pervel
property were included as part of the Phase IBNovember 1995 sampling event MW-A -B -C
-2 and -3 The existing on-site wells SW-3S and SW-3D were also included in the Phase
IBNovember 1995 sampling event and the subsequent Long-Term Monitoring Program sampling
events Since the November 1995 Long-Term Monitoring event included wells that were specific
to the Phase IB investigation the November 1995 sampling event is referred to as Phase
IBNovember 1995
During the period spanning the nine sampling events discussed in this report EPA has approved
modifications to the list of wells sampled under the Long-Term Monitoring Program
Modifications to the list of wells sampled have been to delete certain wells particularly those
located in the southern portion of the Site where no site related compounds have been or are
expected to be detected After the July 1995 sampling event wells at the following locations
were eliminated from the Long Term Monitoring Program MW111 MW112 MW114 SW-9
SW-10 and SW-12 Monitoring wells located at MW110 MW113 and MW115 were eliminated
following the Phase IBNovember 1995 sampling event The following subsections describe the
field methods which have been used consistently over the nine sampling events discussed in this
report Table 2-5 shows which wells were included in each sampling event
291 Monitoring Wells The groundwater sampling locations are shown on Plate 2-4 Low-flow purging and sampling
procedures were used to collect groundwater samples in an effort to obtain turbidity-free samples
and to minimize disturbance of the natural formation
The following sequential procedures were employed during the groundwater sampling effort
1) The static water level was measured using an electronic water level indicator
2) The absence of LNAPL was visually confirmed by observation of a sample
collected using a clear plastic bailer
3) All 2 inch diameter (or larger) monitoring wells were sampled using a stainless steel electric submersible pump (Grundfos Redi-Flo 2) equipped with teflon
5797wpdocsgalluprifinaltextmasterrifhl061297 2-27 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
discharge tubing To initiate the purging procedure the intake for the pump was
owered into the mid-section of the well screen For wells smaller than 2 inch
aiameter (ie existing SW- series wells) Teflon tubing equipped with a bottom
check valve was used to inertially purge the well
4) Water was purged from the well at a low flow rate (approximately 05 litersmin)
which was continuously monitored The water quality field parameters
(temperature pH conductivity and turbidity) were monitored during the purging
process until they had stabilized within 10 over three consecutive readings
5) Once the parameters had stabilized (or a minimum of five well volumes had been
purged) groundwater samples were collected for laboratory analysis Samples
were collected from the discharge end of the pump tubing by directly filling the
appropriate sample containers in the following order VOC SVOC (including
pesticides and PCB) metals inorganic compounds At wells that did not stabilize
below the 5 NTU turbidity requirement additional metals samples were collected
filtered through a 045 micron filter and submitted for dissolved metals analyses
(in addition to total metals)
6) Samples were collected from the upper and lower portion of each well using a
clear plastic bailer to visually assess the potential presence of NAPL
All sampling equipment was decontaminated between sampling events All purge water was
containerized for eventual off-site disposal
Duplicate samples matrix spikes matrix spike duplicates field blanks and trip blanks were
included as part of the QAQC procedures All groundwater monitoring sampling forms are
included as Appendix D Most groundwater samples were submitted for TALTCL VOC SVOC
pesticidesPCB and metals although a small number of samples collected during the Phase
lAJanuary 1995 and April 1995 event were submitted for VOC SVOC pesticidesPCB and
metals by Appendix IX methods Also certain samples were selectively submitted for VOC
analyses by Method 5242 The analytical methods for each sample submitted for laboratory
analysis are shown in Table 2-5
5797wpdocsgalluprifinlaquoltextmlaquosterrifhl061297 2-28 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
292 Residential Wells A total of fourteen private drinking water supply wells (DW101-DW114) were scheduled to be
sampled as part of the groundwater sampling program However two of the residences (DW101
and DW112) were unoccupied and inaccessible at the time of each of the sampling events The
residential wells are located along the eastern perimeter of the Site along Route 12 (Norwich
Road) adjacent to the southern portion of the Site along Tarbox Road and along Lillibridge
Road well south of the Site The residential well sampling locations are provided on Plate 2-5
In accordance with the Long-Term Monitoring Program the residential wells were sampled on a
semi-annual basis during the regularly scheduled summer and winter quarterly sampling events
In addition to the Phase lAJanuary 1995 sampling event residential groundwater samples were
collected during July 1995 February 1996 and August 1996 as shown in Table 2-5
Prior to the collection of groundwater samples from the residential wells a visual survey was
conducted to identify the sampling point closest to the well and to determine if any treatment
systems were in use A description and sketch of the supply system was recorded in field
notebooks Each system was opened and allowed to drain for approximately 15 minutes to purge
the plumbing system and obtain representative samples Field parameters were recorded during
purging to determine when stabilization had occurred The groundwater samples collected from
the residential wells were submitted for laboratory analysis of TCL SVOC pesticides PCB TAL
metalscyanide and VOC using EPA Method 5242
210 Surface Water and Sediment Sampling As part of the Phase 1A Investigation surface water and sediment sampling was conducted on
September 13-16 November 22 and December 29 1994 Although all locations were originally
sampled during the September sampling event three samples were lost in transit and had to be reshycollected A total of seventeen sample locations along Mill Brook and unnamed tributaries (UB1shy
UB10 and LB1-LB2) Fry Brook (FBI) Packers Pond (PP1-PP3) and a small pond along Tarbox
Road (TR1) were included in this program The re-sampled locations were UBS and UB6 (112294) and TR1 (122994) Due to dry conditions surface water samples could not be
obtained from the following locations UBS UBS UB6 UB7 and PP1
In accordance with the Long Term Monitoring program additional surface water samples were
collected during the April 1995 November 1995 May 1996 and November 1996 sampling
events to coincide with the approximate seasonal high- (ie spring) and low-water (ie autumn)
periods Following the initial Phase lAJanuary 1995 sampling event and per the request of
EPA the location of UB6 was moved due south to Mill Brook and renamed UB6A The surface
watersediment sample locations are shown on Plate 2-6 Sample locations by date are shown on
Table 2-5
5797wpdocsgalluprifiMltextmasterrifhl061297 2-29 Q5T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Surface water samples were collected using the actual laboratory sample containers by direct
immersion into the water Parameters which required the use of preservatives (eg metals
requires the addition of nitric acid to the sample) were collected in a stainless steel beaker and
transferred directly to the sample container to prevent loss of the preservatives during sampling
All sampling equipment was decontaminated after each use and placed into clean plastic bags
before moving on to the next station Surface water samples were collected starting at the most
downstream locations and progressed in order upstream The surface water samples were
submitted for laboratory analysis for TCLTAL compounds VOC and the following wet
chemistry parameters total organic carbon total dissolved solids total suspended solids hardness
and alkalinity The samples collected during April 1995 November 1995 and May 1996 were
also submitted for laboratory analysis of SVOC pesticides and PCBs The following field
measurements were also collected as part of the sample collection temperature conductivity
pH dissolved oxygen and turbidity
In addition to surface water during September 1994 sediment samples were collected at each of
the 17 locations (including the dry locations referenced above) Samples were collected at a depth
of 0 - 8 below the surface using manually operated soil or mud augers which were
decontaminated between sample locations The sediment samples were collected starting at the
most downstream locations and progressed in order upstream The sediment samples collected
contained greater than 30 percent solids based on visual and manual determination Samples were
submitted for laboratory analysis for TCLTAL compounds and for total organic carbon
Physical stream bed parameters (width depth and flow rate) were measured at surface water
sampling locations where discernable flow occurred This task was completed in April 1995
since the stream was at extremely low flow stages during the September 1994 sampling round
and a number of surface water sampling locations were nearly dry During the April 1995
surface water sampling event stream flow conditions were such that flow rates could be measured
at the following 5 locations UB4 UB6A UB9 UB10 FBI Locations at Packers Pond and the
small pond on the south side of Tarbox Road (TR-1) were not subject to these stream
measurements
Stream width and depth measurements were made using a fiberglass tape measure Depth and
stream flow measurements were recorded at the midpoint and quarter-points across the stream
Stream flow measurements were recorded using a Swoffer model 2100 in-situ flow meter The
flow meter was mounted on a graduated aluminum shaft which was equipped with an electronic
digital readout To calculate stream-flow the average cross-sectional area in square feet was
multiplied by the average water velocity (feetsec)
5797wpdocsgraquolluprifinaltextmasterrifhl061297 2-30 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
211 Wetland Soil Sampling In early September 1994 samples of wetland soils were collected from 10 locations within the
Study Area These sample locations (QW1-QW10) are shown on Plate 2-6 (and on Plate 3-14
which shows delineated wetlands as discussed in Section 341) Each sampling station was
marked with labeled stakes which were eventually included in the Site location survey The
samples were collected at locations situated near the edge of the wetlands at depths within one foot of the water table and below the organic mat The samples were collected using manually
operated soil or mud augers which were decontaminated between sample locations The samples were submitted for analysis of TCLTAL compounds and total organic carbon The results of the
wetland soil sampling program are discussed in Section 43
212 Evaluation of Existing Monitoring Wells As part of the Phase 1A investigation the remaining 11 monitoring wells installed during the
1978 Fuss and ONeill Inc investigation were evaluated to determine which wells could provide
usable water level data The present condition of each well was documented and a water level and total depth measurement were taken and compared to well construction logs If the wells
were determined to be potentially viable an attempt was made to test them for hydraulic
responsiveness by conducting rising and falling head slug tests Several of the wells were missing
protective casings had been broken off below the ground surface or had infilled with sediment
The results of the hydraulic evaluations are presented in Section 33 The locations of the
remaining existing monitoring wells are shown on Plate 2-4
A summary of the condition of each existing monitoring well is presented as Table 2-6 The
majority of the existing wells are presently in poor condition Most of these wells are lacking
surface seals andor adequate protective casings Several of the wells have no protective casings at all and are comprised only of PVC riser which is broken at or near the ground surface
Based on the present total depths of several of these wells compared to their total depths at the time of construction it is evident that the screen section of several of these wells have infilled
with sand or silt Based on their present condition and the fact that new monitoring wells have
been installed ESE recommended that any of the existing wells not included as part of the Long-
Term Monitoring Program be properly abandoned Following this recommendation EPA
approved the abandonment of the following wells SW13 SW14 SW17S D and SW18 Also
the protective casings at existing wells SW-3S SW-3D SW-9 SW-10 and SW-12 were repaired
since these wells are used to measure groundwater elevations as part of the Long-Term
Monitoring Program
5797wpdoc8galluprifinaltextmasterrifhl061297 2-31 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
213 Ecological Assessment 2131 Wetlanl Delineation
A wetland delineation was conducted on Site and focused primarily on the wetlands located north
and west of the Study Area This survey was limited to the Site side of Mill Brook up to the
present channel In order to meet both Federal and State requirements two methods were used to
delineate the Study Area wetland boundaries In accordance with federal requirements wetlands
were delineated using US Army Corps of Engineers (COE) methods Since the State of
Connecticut recognizes a slightly different methodology for wetland delineation the services of a
soil scientist certified by the Society of Soil Scientists of Southern New England were also
required The only difference between the two methods is that while the COE requires analysis
of vegetation composition hydrology and hydric soil indicators the State of Connecticut requires
only the analysis of hydric soil indicators
Jurisdictional wetland boundaries were determined by evaluating several points along the
hydrologic gradient Vegetation soil and hydrology criteria were measured or observed to
determine whether the point was within or above the Jurisdictional wetland boundary In order
for an area to be judged Jurisdictional wetland criteria must be met for all three parameters (ie
vegetation hydrology and soil)
21311 Vegetation
Wetland criteria for vegetation was based on the National List of Plant Species That Occur in
Wetlands (Reed 1988) Dominant plant species were identified at the observation point and listed
on data forms for routine on-site wetland determination The stratum where the plant occurred
(canopy shrub or herb) and indicator status for that plant were recorded A dominance of
wetland indicator species indicates that the vegetation criteria is met A dominance of upland
indicator species indicates that wetland criteria are not met
21312 Hydrology
Hydrologic criteria includes the visual observation of surface water inundation soil saturation or
indirect indication of previous saturation or inundation Indirect evidence includes watermarks
(stain lines on vegetation or structures) drift lines (debris deposited in a line at the high water
mark) sediment deposits and drainage patterns within wetlands
21313 Hydric Soils
The identification of hydric soil criteria includes soil types named as hydric by USDA Soil
Conservation Service or the presence of hydric indicators within the soil profile Indicators
include mottling or streaking of organic materials high organic content the presence of sulfitic
material soil colors (gleyed colors) and others
5797wpdoc8galluprifinaltextmasteirifhl061297 2-32 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
2132 Plant and Wildlife Survey
The objective of the Phase 1A ecological assessment was to qualitatively identify any real or
potential impacts to local ecological receptors within the Study Area or otherwise influenced by
the conditions originating at the Site All observations on plants and animals were noted in field
logs during the wetland delineation
The results of this survey will assist the EPA in the performance of a more formal ecological risk
assessment During the ecological risk assessment sediment soil water and air quality data and
observations of plant and animal communities will be used (see also Section 123) to identify any areas where impacts have occurred The results of the qualitative plant and animal survey
conducted during the wetland investigation are discussed in Section 34 of the text
214 Test Pit Explorations In lieu of ground penetrating radar surveys (as discussed in Section 233) and with EPA
approval additional EM and MAG surveys were performed over a five-foot by five-foot grid in
the vicinity of unexplainable anomalies which were detected during the initial EM and MAG
surveys Once accurate locations for the anomalies were determined and marked on the ground
surface test pit explorations were conducted to confirm the source of the anomalies
On December 21 1994 test pits were excavated at a total of four locations at which
unexplainable anomalies were detected The test pits were performed under the observation of
EPA oversight contractor personnel The locations of the four anomalies and associated test pits are shown on Plate 2-7 At each anomaly a trench (or series of trenches) was systematically
excavated in one to two foot lifts using a backhoe The trenches were oriented to intersect the
longest axis of each anomaly to maximize the possibility of unearthing the source of the anomaly Once a lift was complete soil obtained from the trench walls as well as that obtained from the
backhoe bucket was screened with a PID for evidence of VOC The excavated soil and the trench
itself were also visually monitored for objects capable of producing the anomalies detected during the geophysical surveys and for other features possibly associated with disposal activities (eg
stained soil)
Once the source of each anomaly was discovered the object was excavated and the test pit was
backfilled and regraded with clean soil obtained from the excavation Since no elevated PID
readings or other signs of disposal features were encountered during the test pit operations no
soil samples were submitted for laboratory analysis Test pit logs for these excavations are
presented in Appendix E
5797wpdocsgalluprifinaltextmasterrifhl061297 2-33 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
30 Physical Characteristics of the Study Area
31 General Characteristics 311 Regional Physiography
The Site is located along the eastern border of the Quinebaug Valley Lowland This regional
feature is dominated by the southerly flowing Quinebaug River and is comprised of a north-south
trending lowland area which is approximately 2 to 3 miles in width and approximately 25 miles
long The Quinebaug River originates at headwaters located in central Massachusetts and
terminates at Norwich Connecticut where it merges with the Shetucket River approximately 12 miles south of the Site The confluence of these two rivers form the Thames River which flows
to the south approximately 15 miles and ultimately discharges into Long Island Sound
The region is characterized by relatively low relief and numerous glacial features The regional
landscape is significantly influenced by the structure of the underlying crystalline metamorphic
bedrock which is discontinuously overlain by Pleistocene glacial sediments of variable thickness
Lowland surficial features are characteristic of late Pleistocene glacial retreat processes and
include numerous kettleholes and swamps many of which are interconnected by a network of
slow draining streams
Land surface elevations in the vicinity of the Site range from approximately 150 to just over 220
feet above sea level Lowlands are bounded to the east and west by upland terrain which consists of irregular hilly areas of moderate relief The uplands contain many areas with large bedrock
ledges generally thin glacial deposits (predominantly till) poorly drained valleys and small
isolated swamps Elevations in the uplands range from 200 to 600 feet above sea level
312 Study Area Physiography
The topography on the Site is highly irregular primarily due to past quarrying operations
Numerous overgrown mounds of earthen materials (eg crushed stone sand and gravel) and
excavated depressions are scattered throughout the Site Visual reconnaissance and a number of
screening surveys (eg soil gas and surface geophysical investigations) have confirmed that many
of the features previously identified from the review of historic aerial photographs as potential
disposal areas (Bionetics 1990) were in fact features remnant of quarrying and former CTDOT
operations
The ground surface on the Site (shown on Plate 3-1) generally slopes from east to west and to a
large degree is controlled by the underlying bedrock surface The highest point within the Study
Area consists of a bedrock high overlain by a thin veneer of till and is located in the eastern
5797wpdoclaquogalluprifinraquoltextma8terri fhl061297 3-1 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
central portion of the Site Elevations in this vicinity peak at approximately 230 feet above sea
level
The northern portion of the Site which includes the Former Primary and Secondary Disposal
Areas consists predominantly of open sparsely or non-vegetated areas of sand and gravel This cover material is presumed to have been distributed over the ground surface following CTDEP
Site remediation efforts in 1979 Presently the Former Primary and Secondary Disposal Areas are visible as roughly circular depressions which are approximately 150 feet and 60 feet in
diameter respectively The depressions are approximately 8 to 12 feet deep relative to the
surrounding ground surface These depressions intermittently contain as much as several inches
of standing water which accumulates during periods of heavy precipitation The bottoms of the
depressions are lightly vegetated with various grasses and weeds
North and west of the Site the ground surface elevation decreases as the Mill Brook floodplain is
encountered The floodplain area consists of low lying heavily vegetated wetland areas which
are periodically inundated
Excluding the isolated topographic high spot at the eastern margin of the Site the southern
portion of the Site (from the vicinity of the Former Seepage Bed to Tarbox Road) can be
described as generally flat but includes numerous man-made small-scale features such as
mounds or depressions
313 Surface Water Features
The Site is centrally located within the Mill Brook drainage basin which encompasses
approximately 18 square miles The Mill Brook drainage basin is part of the larger Quinebaug
River regional drainage basin Mill Brook a tributary to the Quinebaug River is located 250 feet
north of the Site and flows from east to west Approximately 1000 feet northwest of the Site (in
the vicinity of the Plainfield municipal sewage treatment plant) Mill Brook is joined by Fry
Brook which flows from the north Packers Pond which is located approximately 3000 feet
west of the Site was formed by the construction of a dam across Mill Brook
There are no surface water bodies located on the Site itself although several low areas (which
were excavated during previous site activities) have been observed to contain ponded water during
periods of extended precipitation
Surface water flow rates (determined during the April 1995 sampling event) were determined for
the following five locations in Mill Brook UB4 UB6A UB9 UB10 and at FBI in Fry Brook
Along Mill Brook flow rates ranged from approximately 23 cubic feet per second (cfs) at the
5797wpdocsgalluprifinaltextmasterrifnl061297 3-2 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
most upstream location (UB4) to approximately 31 cfs at the most downstream location (UB10)
Along the northern Study Area a 3 cfs increase was observed from Stations UB6 to UB10
representing a flow rate increase of about 025 cfs per 100 feet of stream length The flow rate in Fry Brook (Station FBI) was approximately 16 cfs
314 Climate The Site is located within Connecticuts Central climate division According to published
National Weather Service data (USGS 1993) the average annual temperature is approximately
50degF the coldest month is January with an average temperature of 258T and the warmest month is July with an average temperature of 714degF Annual precipitation at nearby recording
stations (located in Norwich CT and North Foster RI) averages approximately 53 inches per
year and ranges between approximately 41 and 68 inches per year (based on historic data from
1978 to 1991) The monthly distribution of precipitation is relatively even throughout the year
32 Geology 321 Regional Surficial Geology
The surficial or overburden deposits in the area consist of unconsolidated materials deposited as a
result of glaciation during the Pleistocene epoch Various glacially-derived materials including till meltwater or stratified drift deposits and post-glacial deposits of floodplain alluvium
comprise the major surficial geologic units in the vicinity of the Site Areas covered by eolian dune deposits are also noted on surficial geologic maps of the area although no dune deposits are
found within the Study Area
Till deposits in the region consist of non-sorted and generally non-stratified mixtures of sediments
with grain sizes ranging from clay to boulders Till is formed by the direct deposition of ice debris on the land surface Generally the color and lithology of till is dependant upon the
composition of local surficial deposits underlying bedrock and northerly adjacent bedrock from
which the till was derived Tills deposited during two periods of glaciation are present in the
region and blanket the bedrock surface in various thicknesses The most extensive and prevalent
till which is commonly present in surface exposures was likely deposited during late
Wisconsinan glaciation (USGS 1995) This till is referred to as upper till and is described as
predominantly loose to moderately compact generally sandy and frequently stony
A less commonly exposed lower (older) till was deposited during earlier glaciation possibly during the Illinoisan or early Wisconsinan glaciation periods The lower till is generally compact
to very compact and is typically finer-grained and less stony than the younger upper till A
weathered zone is usually present between the two till units
5797wpdoc8gnlluprifinaltextmasterrifnl061297 3-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Directly overlying the till (or bedrock where till is absent) are glacial meltwater deposits
collectively referred to as stratified drift These deposits consist of poorly to well sorted
assemblages of gravel sand silt and clay which were deposited by glacial meltwater during the retreat of the last ice sheet Variations in the composition structure and texture of the stratified
drift deposits are dependent upon the depositional environment in which they formed Deposits exhibiting a relatively high degree of sorting andor stratification can usually be classified as
either glaciofluvial (stream) deposits glaciodeltaic (where streams entered glacial lakes) deposits or glaciolacustrine (lake bottom) deposits The horizontal and vertical contacts between these
deposits are generally transitional and were dependent upon the available sediment load and
proximity to the various depositional environments (eg streams or lakes) associated with the
retreating ice front For example coarse-grained deposits of sands and gravel were usually
deposited proximal to the ice margin while further away primarily in glacial lakes deposits of
fine sand silts and clay were prevalent Poorly sorted deposits of relatively coarse material were
typically deposited at the ice front or along bedrock valley walls During the glacial retreat
these deposits would be left behind or collapsed on any underlying deposits Contemporaneously bedrock valleys were frequently dammed by glacial deposits andor masses
of glacial ice behind which glacial meltwater could accumulate forming glacial lakes Gradual
retreat of the ice margin as well as the formation (and eventual draining) of glacial lakes over
time would result in changes in the depositional environment which are seen as textural changes in the stratified drift deposits
Postglacial deposits of sand gravel silt and organic materials are also present as floodplain
alluvium along streams and rivers in the region The texture of alluvium varies over short
distances both laterally and vertically and is generally less than 5 feet thick along small streams
Since alluvial material typically represents re-worked glacial deposits the alluvium is often similar to the surrounding parent glacial material
322 Local Surficial Geology
The Study Area is located on the eastern flank of a pre-glacial bedrock valley and is bounded to
the east by bedrock-controlled upland areas and to the west by an area known as the Quinebaug
Valley lowlands Following the last period of glaciation (in which the relatively thin veneer of till
was deposited) various temporary depositional environments existed as a result of the presence of
an ice and sediment dam approximately 10 miles south of the Study Area which caused the
formation of a glacial lake Evidence of the lake (referred to as Glacial Lake Quinebaug) is well
documented in the literature (Stone amp Randall 1977) As the ice sheet retreated northward deposits left behind were dominated by sand and gravels associated with the formation of a series
of progressive and coalescing deltaic complexes which developed within the rising lake In lower
lying areas where deltas did not form finer-grained sand silt and clay was deposited Although
5797wpdocsgalluprifinaltextma8terrifhl061297 3-4 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
much of this sediment may originally have been deposited with some degree of structure or
sorting much of the structure was lost (collapsed) when the ice mass eventually melted away
The depositional environment was further complicated by the presence of residual ice blocks left
behind during the retreat of the main body of the glacier As the various depositional features
formed around these ice-blocks their eventual melting left behind depressions or kettles into
which fine sediment could settle While many kettles were eventually filled many remain as
detached or poorly drained ponds
As a result of the depositional history of the Study Area the primary surficial or overburden
deposits encountered are till and stratified drift Depending upon location the stratified drift may
be generally broken down into fine (eg silt and fine sand) or coarse (eg sand and gravel)
grained components but at many locations the change is transitional and subtle in both vertical
and horizontal directions The thickness of the stratified drift deposits ranges from non-existent
up to approximately 70 feet At some locations distinct structure is exhibited while at other
locations the structure has collapsed Post-glacial alluvial floodplain deposits were encountered
at locations within the present Mill Brook floodplain however the overall significance of these
deposits is minor
To illustrate the local geological features a series of geologic cross-sections have been prepared
At several locations lithologic data from pre-RI wells (both on-site and off-site) were
incorporated for additional detail The boring logs from which the cross sections were prepared
are included in Appendix C
As shown in cross-sections A-A B-B C-C D-D E-E and F-F (Plates 3-2 through 3-5) till
was encountered just above the bedrock surface at nearly every location The till horizon ranges
in thickness from approximately 10 to 20 feet with the thickest accumulations located along the
centrally located topographic high Surficial exposures of glacial till were observed within the
central portion of the Site as seen in cross sections A-A and C-C The till observed within the
Study Area is comprised of a fine sandy matrix containing abundant gravel cobbles and
boulders The till deposits seen in the topographically higher areas (ie elevations greater than
approximately 160 feet) were for the most part unsaturated Although reference literature for
this area (USGS 1995) describe the possible presence of two different till horizons no apparent
differentiation was observed at the site
As seen in the boring log from MW111 deposits of till are exposed at the ground surface and in
the central area of the Site However as shown on cross sections A-A and C-C (Plate 3-2) and
D-D (Plate 3-3) the bedrock surface drops off rapidly in southerly westerly and northerly
directions where relatively thick accumulations of stratified drift have been deposited over the till
5797wpdocsgalluprifinlaquoltextmalaquotemfhl061297 3-5 QFT Environmental
Gallups Quarry Superftind Project - Remedial Investigation
Within 500 feet of the central portion of the Site the overall thickness of the stratified drift
deposits increase to nearly 70 feet In the vicinity of MW113 (west of the central portion of the
Site) the lower portion of the stratified drift is comprised of approximately 30 feet of very fine to
medium-grained sand with occasional thin layers of silt This deposit appears to increase in
thickness towards the west while it thins towards the central portion of the Site where it pinches
out against the till Overlying these fine-grained deposits are approximately 30 feet of poorly
structured sand and gravel which includes abundant cobble sized material The coarser upper
stratified drift material also thins eastward towards the Site where it is in contact with the till
The coarse upper material is generally unsaturated with the groundwater table occurring at the
approximate upper surface of the fine sand
The southern portion of the Study Area is shown on cross sections A-A (Plate 3-2) and D-D
(Plate 3-3) As indicated on the southern end of cross section A-A approximately 35 feet of
stratified drift overlies the till in the vicinity of MW112 Although much of the stratified drift at
MW112 is relatively coarse an approximately 12 foot thick layer of fine-grained sand and silt is
present from about eight to twenty feet below the ground surface From MW112 the thickness of
the stratified drift thins to the north where it contacts the central topographic high
From the southeastern corner of the Site near MW112 the bedrock surface slopes downward
towards the west-southwest to a depth of approximately 75 feet below the ground surface (as seen
at location MW115 on the southern end of cross section D-D[Plate 3-3]) At MW115
approximately 65 feet of stratified drift (comprised of a sandy matrix containing a significant
amount of coarser gravel and cobbles) overlies approximately 10 feet of till
As seen in cross section B-B (shown on Plate 3-4) and A-A (Plate 3-2) the northeastern portion
of the Site (in the vicinity of the Former Primary Disposal Area) is comprised of fairly well
sorted fine- to medium-grained sand with occasional thin lenses of very fine sand and silt The
lenses of finer-grained materials appear only locally in the vicinity of MW107 and MW108 at a
depth of about 25 feet and are typically only a few inches to a few feet in thickness with limited
lateral extent Beneath the fine-grained sand and silt and directly overlying the till is 10 to 20
feet of coarser-grained sand and gravel Moving westward along cross section B-B in the
vicinity of MW105 the fine-grained sand thins and grades into coarser sand and gravel deposits
The coarse sand and gravel deposits directly overlie the till and thicken to nearly 50 feet towards
the west in response to the downward slope of the bedrock surface This portion of the Study
Area which is northwest (and downgradient) of the Former Primary and Secondary Disposal
Areas is overlain by a thin veneer of recent alluvial and swamp deposits associated with the
present Mill Brook channel and floodplain As shown on the cross section (B-B) the stratified
drift deposits in this area are very nearly saturated throughout their entire thickness
5797wpdoc8galluprifinaltextmasterrifiiiy061297 3-6 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
North of the Former Primary Disposal Area (along the northern end of cross section D-D) the
bedrock surface continues to gradually slope downward (to the north) until the approximate
location of MW116 North of MW116 the bedrock surface is interpreted as appearing to rise
based on the depth to till deposits encountered beneath MW119 Stratified drift deposits
immediately north of the Former Primary Disposal Area in the vicinity of MW116 are dominated
by approximately 25 feet of fine grained sand and silt Further north along section D-D the
finer sand and silt deposits thin and are overlain by coarser grained sand and gravels Relatively
thin post-glacial stream alluvium and modern swamp deposits associated with Mill Brook are also
seen in the vicinity of MW116 and MW119 A roughly east-west cross section (E-E [Plate 3-5])
has been prepared to illustrate the lithologic features in the area north-northwest of the former
disposal areas This cross section starts at MW119 (described above) and runs west to MW101
in a line approximately parallel to Mill Brook The fine sandsilt deposit seen in the vicinity of
MW119 is also observed to the west at MW117 at the same approximate thickness and elevation
Westward from MW117 the fine sandsilt deposit grades into the more prevalent coarse sand and
gravel deposits observed at MW118 and MW101 The northernmost cross section (F-F [Plate 3shy
5]) extends westward from MW3 (located just east of the former Pervel flock plant) to PZ301
As shown on F-F this portion of the Study Area is dominated by collapsed coarse sand and
gravel deposits at least to the completion depths of the borings (MW3 MWC and PZ301) along
the line
323 Regional Bedrock Geology
Bedrock in the vicinity of the Site is mapped as a lower member of the Quinebaug Formation
which is composed of metasedimentary and metavolcanic rocks of Paleozoic age The Quinebaug
Formation is part of the Putnam Group and exhibits a sillimanite grade of metamorphism The
bedrock consists of primarily light to dark grey fine- to medium-grained hornblende gneiss biotite gneiss and amphibolite Bedrock in the area is strongly faulted and folded and exhibits
varying degrees of mylonitization A major fault zone known as the Lake Char fault is located
approximately 03 miles east of the Site The Lake Char fault is a north-south trending fault
which offsets rock units of the Putnam Group and the Hope Valley Alaskite Gneiss formation A
northwest-trending fault is shown on the USGS Bedrock Geologic Map (Dixon 1965) of the
Plainfield Quadrangle in the vicinity of the Former Seepage Bed The existence and approximate
location of the suspected fault was based on aeromagnetic data published in 1965 (Boynton amp
Smith 1965) Bedrock located north of the inferred fault is mapped as more intensely
metamorphosed cataclasites and blastomylonites The fault is mapped as extending into the Tatnic
Hill formation to the west but is not mapped within the Hope Valley Alaskite Gneiss formation
which is located to the east
5797wpdoc8galluprifinaltextmasterrifhl061297 3-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
324 Local Bedrock Geology
Confirmed depns to bedrock were determined based on the elevations of bedrock outcrops and
the collection of bedrock cores at nine boring locations (MW102B MW105B MW107B
MW108B MW109B MW111B MW112B MW113B and MW115B) Inferred depths to
bedrock were made at seven additional locations (MW101 MW102 MW103 MW104 MW114
MW116 MW117 MW118 and MW119) based on boring data obtained during the drilling of the
deepest wells at each cluster (which indicates the minimum depth to bedrock) and based on trends
seen at the confirmed depth locations Based on this evidence it is likely that unconfirmed depths
to bedrock are accurate to within several feet of the actual depths At MW110S no attempt was
made to advance the boring more than about 12 feet below the ground surface (the depth needed
for the required shallow well at that location) Depths to bedrock ranged from approximately 13
feet at MW111B to 83 feet at MW113B Drilling difficulties associated with the presence of
boulders just below the ground surface at MW11 IB made it difficult to determine the exact depth that bedrock was first encountered at this location Suspected boulders were encountered starting
at approximately six feet below the ground surface and casing was driven to a refusal depth of
approximately 15 feet before bedrock coring began
Based on the data described above a bedrock surface contour map is shown on Plate 3-6
Bedrock elevations are highest in the eastern central portion of the Study Area and decrease to the
north and west and to a lesser degree to the south
Within the Study Area bedrock consists of grey fine- to medium-grained gneiss with varying
contents of amphibolite biotite and hornblende Various degrees of weathering and competency
were also observed Detailed rock core descriptions are presented on the rock coring logs
provided in Appendix C
The primary objective of the seismic refraction survey (discussed in Section 234) was to
identify if present the location of a possible bedrock fault suspected to exist hi the vicinity of the
Former Seepage Bed As discussed in Section 323 the approximate location of the suspected
fault was estimated from the regional USGS Bedrock Geologic Map based on an aeromagnetic
survey conducted in 1965 Ground penetrating radar surveys conducted by the USGS (1995)
identified a northward dipping subsurface reflector beneath the central portion of the Site This
reflector was interpreted as a potential bedrock fault feature The relatively high strength of the
reflector was attributed to fault gouge (or other infilling) material or possibly sorbed inorganic
compounds No subsurface explorations were conducted at the time of the USGS investigation to
confirm the nature of the radar reflector
5797wpdocsgalluprifinaltextmiiraquoterrifnl061297 3-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Evaluation of data obtained from the seismic refraction survey indicates the presence of possible
bedrock fractures on seismic lines 3 through 6 (Plate 3-7) In addition to these interpreted
fracture zones the overall relatively low seismic velocities (12000 ftsec vs 15000 to 18000
ftsec for intact crystalline rock) indicate that in general the rock is somewhat fractured
Although the original intent of the magnetometer (MAG) survey was not to interpret bedrock
features data obtained during the MAG survey (which covered a much larger area) indicate the
presence of several linear-shaped sharp magnetic gradients bounding a zone with a different
magnetic signature The change in magnetic signature was interpreted as potentially associated
with changes in bedrock lithology and fracturing across a broad faultfracture zone in the central
portion of the Site These interpretations are described in further detail in the Weston
Geophysical Report included as Appendix A The locations of the magnetically determined
bedrock features are also shown on Plate 3-7 While the seismically interpreted fractures do not
strongly coincide with linear features seen in the MAG data they do lie within the magnetically
determined fractured zone
The geophysical data described above as well as the rock-core retrieved from MW111B further suggest that bedrock beneath the central portion of the Site may be more accurately characterized
as a series of fractures and faults rather than an area of competent bedrock with one or two
discrete faults
33 Hydrogeology The following sections discuss data collection and evaluation results relative to groundwater flow
directions and rates in overburden deposits and the upper portion of the bedrock unit
331 Hydraulic Conductivity The hydraulic conductivity distributions within the overburden and bedrock formations were
evaluated through the performance of rising and falling head slug tests constant flow tests and
by empirical correlations with measured soil grain size distributions The slug test methodology
and data analysis methods are discussed in Appendix F Because the falling head test results for
shallow wells were influenced to some degree by soil above the water table only rising head test
data were used for the water table wells to compute mean values The constant flow test
methodology is described in Section 283 and Appendix F Table 3-1 summarizes the measured
hydraulic conductivity values from the slug and constant flow tests for wells grouped together
based on lithology and screen depth as follows shallow top-of-till till and bedrock Hydraulic
conductivity estimates based on grain size are listed in Table 3-2 for comparison but only
constant flow and slug-test data were used to calculate mean hydraulic conductivity values for
different portions of the aquifer Laboratory grain size data are presented in Appendix G
5797wpdocraquogalluprifinlaquoltextmastem fill061297 3-9 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
The top-of-till wells are considered to be the most representative of the more permeable section of X^^JF
the overburden aquifer characterized by coarser soil grain sizes where a large percentage of the
total groundwater flow occurs Across the Study Area the mean hydraulic conductivity for the
top-of-till wells is 0005 centimeters per second (cms) with values ranging from 0000053 cms
to 0074 cms Northwest of the railroad tracks in the northern portion of the Study Area where
the aquifer thickens the mean hydraulic conductivity for top-of-till wells (MW102TT
MW103TT MW104TT MW117TT and MW118TT) is 0037 cms This value of 0037 cms
which is approximately an order of magnitude larger than the overall Study Area mean for top-ofshy
till wells appears to be most representative of the hydraulic conductivity within the major portion
of the VOC plume By comparison the grain size results are similar in magnitude but somewhat
lower than the Study Area average for the constant-flow and slug tests because they indicate an
average hydraulic conductivity of 0003 cms for the coarse stratified drift samples with values
ranging from 00006 cms to 0006 cms The mean hydraulic conductivity for shallow wells
which are generally screened in finer-grained soils is 0001 cms and varies between 000006
cms and 002 cms The shallow well constant-flow and slug test results are comparable to the
mean grain-size correlation value of 0002 cms for fine stratified drift soil samples
The mean hydraulic conductivity for the till wells (000047 cms) is approximately a factor of ten
less than the mean Study Area top-of-till value and varies between 00002 cms and 0002 cms
The till appears to be hydrogeologically different from the other overburden deposits and on the
average provides increased resistance to groundwater flow This added resistance is not
considered to be significant however because the consistency of the till is highly variable and the
hydraulic conductivity contrast is relatively small
The slug test results for the bedrock wells yield the lowest average hydraulic conductivity
000018 cms The bedrock results though should be considered less accurate than the
overburden estimates due to the highly variable nature of the fractures in the rock matrix and their
associated non-linear effect on computed hydraulic conductivity
332 Groundwater Flow
3321 Surficial (Overburden) Groundwater Flow
The following discussion on overburden groundwater flow is organized according to relative
locations within the Study Area All references to flow direction are inferred based on measured
hydraulic gradients The central portion of the Site in the vicinity of the Former Seepage Bed is
dominated by the presence of a bedrock-controlled topographic high which for the most part is
overlain by unsaturated till Because of this feature overburden groundwater flow patterns can be
effectively treated as separate entities those located to the north of the hill and those located to
the south
5797wpdocraquoglaquolluprifinlaquoltextmasterrifhl061297 3-10 QampT Environmental
Gallups Quarry Superand Project - Remedial Investigation
Table 3-3 summarizes the water level data collected from monitoring wells and piezometers
during the quarterly monitoring rounds Plates 3-8 and 3-9 depict deep and shallow piezometric head distributions respectively (for November 6 1995) throughout the northern Study Area
Plate 3-9 also shows the piezometric head distribution in the southern Study Area Groundwater
flow maps for other dates are presented in the ISCR (ESE 1995) Water level data for the
monitoring wells at the former Pervel facility were used in both the shallow and deep flow maps
because they are screened in the middle portion of the aquifer As a result these wells are
considered to be hydraulically representative of both portions of the aquifer A saturated
thickness map (Plate 3-10) was created by subtracting the interpolated bedrock surface (Plate 3-6)
from the shallow overburden piezometric surface measured on November 6 1995 which is approximately equal to the groundwater table configuration To facilitate interpretation of flow
patterns calculated two-dimensional groundwater pathlines which represent the mean horizontal trajectory of a parcel of groundwater in the overburden aquifer originating from several locations
in the Study Area are also shown however the pathlines do not account for vertical flow within the aquifer which is important in the shallow portion of the aquifer Data interpolation by the
method of kriging piezometric head contour development and numerical computation of pathlines were performed using the data analysis and visualization software package Tecplot
(Amtec Engineering 1994) The pathlines are based on a steady state velocity field computed
directly from the interpolated head distribution using Darcys law and assume homogeneous
isotropic conditions
Southern Study Area
Overburden groundwater flow south of the Former Seepage Bed is primarily influenced by two factors (1) the slope of the bedrock surface which defines the base of the unconsolidated deposits and (2) regional hydrologic drainage patterns The west-southwest dip of the bedrock
surface strongly influences the general east to west flow of groundwater The average east-west
horizontal hydraulic gradient in the southern portion of the Study Area is approximately 001 feet per foot (feet of vertical head change per foot of horizontal distance)near well MW112S and
piezometer PZ-202 whereas the typical bedrock surface slope in this area is about 01 feet per
foot The configuration of the bedrock surface is important because the slope of the groundwater
table in the overburden would tend to equal the slope of the underlying bedrock in cases where
the saturated thickness is relatively small and the slope is large This process is analogous to flow
in a river where the water surface profile tends to reflect the slope of the river bed under steady-
state conditions In the southern Study Area the water table slope (ie horizontal hydraulic
gradient) is steep but less than the dip of the bedrock surface because the saturated thickness of
the overburden aquifer increases in the direction of flow The saturated thickness increase also
5797wpdocsglaquolluprifinlaquoltextmlaquogterrifiil061297 3-11 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
increases the transmissivity of the aquifer (and decreases the resistance to flow) thus causing the
horizontal hydtaulic gradient in the overburden to be less than the bedrock slope The
overburden becomes unsaturated north of PZ203 due to the continued increase of the bedrock
surface elevation in the direction of the Former Seepage Bed The wetlands and stream located a
few hundred feet west of the railroad tracks also affect flow directions and rates because they act
as discharge points for groundwater
Northern Study Area
Due to the increased saturated thickness north-northwest of the Former Primary Disposal Area
groundwater flow conditions in both shallow and deep sections of the aquifer are discussed The
top-of-till wells are considered to be most representative of horizontal flow conditions in all but
the shallow portion of the aquifer Primary reasons for the differences between shallow and deep
flow conditions include (1) the deep aquifer hydraulic conductivity northwest of the railroad
tracks is a factor of about 40 greater than the shallow hydraulic conductivity resulting in the
lower to middle portions of the aquifer controlling regional groundwater movement and (2)
rainwater infiltration and hydraulic influences of Mill Brook cause vertical flow to be important in
certain areas of the shallow aquifer The focus of this section is horizontal groundwater flow in
the middle to lower sections of the aquifer as characterized by Plate 3-8 Shallow flow
conditions (Plate 3-9) are discussed in Section 3323
In the northern portion of the Study Area three hydrogeologically distinct zones exist Between
the Former Primary Disposal Area and the Former Seepage Bed the hydraulic gradient is steep
(approximately 003 feet per foot between wells MW109S and MW110S) and is strongly
influenced by the dip of the bedrock surface (01 feet per foot) As shown on the insert on Plate
3-10 the saturated overburden thickness increases from zero south of well MW109 to about 20 to
30 feet near the former disposal areas North-northwest of the Former Primary Disposal Area the
hydraulic gradient lessens significantly to a range of 00003 to 00007 feet per foot between wells
MW105TT and MW102TT representing a factor of 40 to 100 reduction The most important
factors which produce the flatter gradients in this area are the more than order-of-magnitude
increase in hydraulic conductivity of the coarser-grained deposits and the substantial increase in
the saturated overburden thickness northwest of the railroad tracks North-northeast of Mill
Brook the hydraulic gradient is about 0007 feet per foot near wells MW117TT and MW118TT
Northwest of the railroad tracks groundwater flow in the middle to lower portions of the aquifer
converges from the northeast and southwest toward a centerline area generally defined in the
downgradient direction by wells MW105 and MW102 The flow direction near these wells is
generally to the northwest Northeast of this centerline groundwater flows in a southwesterly
5797wpdocsgalluprifinaltextmasterrifhl061297 3-12 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
^ ^ direction from the vicinity of Mill Brook and the former Pervel flock plant North of Mill Brook
and west of the railroad tracks the predominant groundwater flow direction becomes more
westerly As discussed in Section 42 and 52 these flow directions are very consistent with the
observed groundwater contaminant distribution
No significant seasonal changes in horizontal groundwater flow directions were observed in the
Study Area Figures 3-1 to 3-20 are groundwater elevation hydrographs for each well cluster in
the Study Area representing the period January 1995 to May 1997 (except for wells MW117
MW118 and MW119 which were not installed until November 1995) Groundwater levels were
high in January 1995 May 1996 and February 1997 and decreased by about two feet during July
1995 and August 1996 This variation is consistent with the fact that recharge rates become very
small during the summer months
3322 Bedrock Groundwater Flow
Groundwater flow within fractures in the top ten to 20 feet of the bedrock unit was evaluated
through the performance of the hydraulic conductivity (slug) tests and water level measurements
in monitoring wells A bedrock piezometric head map based on November 6 1995 water levels
is shown on Plate 3-11 along with inferred groundwater pathlines For the pathline development
it was assumed that the hydraulic conductivity distribution is isotropic because potential
influences of fracture orientation on flow direction have not been quantified As expected the
direction of the dip of the bedrock surface has a major influence on the horizontal hydraulic
gradient and flow direction However vertical flow from bedrock to overburden is also
important as discussed in Section 3323
South of the Former Seepage Bed groundwater in bedrock moves primarily in a westerly
direction while in the northern Study Area the predominant flow component is toward the
northwest In both areas the horizontal hydraulic gradient is on the order of 002 feet per foot
The steepest gradients (003 feet per foot) are found in the vicinity of the Former Seepage Bed
and the local high in the bedrock surface just east of MW111 The horizontal hydraulic gradient
reduces to about 001 feet per foot in the southern portion of the Study Area (near wells MW115
MW114 and MW112) and north-northwest of the former disposal areas Groundwater flow in
bedrock near the Former Seepage Bed is toward the northwest in the direction of wells MW113
and MW106 and exhibits no apparent influence from the locally increased fracturing identified
from the geophysical investigation and the hydraulic testing in well MW111B
5797wpdocsgalluprifinaltextm8tem fhl061297 3-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
3323 Vertical Flow
BedrockDeep Overburden Interface
Vertical groundwater flow is an important component in the upper several feet of the bedrock
unit This observation is supported by the water level hydrographs (Figure 3-1 to 3-20) and data
presented in Table 3-4 which summarizes the vertical hydraulic gradients between pairs of
monitoring wells in various well clusters across the Study Area Data characterizing the hydraulic
interaction between the bedrock and the lower portion of the overburden were evaluated for the
following well pairs MW102B-MW102TT MW105B - MW105T MW107B - MW107T
MW108B - MW108TT MW109B - MW109S MW112B - MW112T MW113B - MW113S and
MW1 15B - MW1 15TT For all measurement dates groundwater was found to be discharging
from bedrock into overburden at each location except for the January 1995 and February and May
1996 measurements at location MW109 At MW109 the saturated overburden thickness is less
than a few feet and MW109 is located at a much higher bedrock elevation relative to all other
locations at which upward vertical flow from bedrock was measured The vertical hydraulic
gradients between bedrock and top-of-till wells are generally more than a factor of ten greater
than the horizontal hydraulic gradients within the VOC plume downgradient from the Former
Primary Disposal Area
Overburden
In the overburden aquifer the vertical flow component is significant within shallow deposits in ~
the vicinity of the Former Primary Disposal Area and within the streambed sediments and the
upper portion of the aquifer near Mill Brook Plan view and cross-section maps were developed
to illustrate vertical piezometric head differences Plate 3-12 shows the November 6 1995
vertical piezometric head distribution and general groundwater flow directions along geologic
cross-section B-B Plate 3-13 is a plan view contour map of the shallow minus deep piezometric
head difference in the overburden aquifer As shown by the water level hydrographs the vertical
hydraulic gradients in the aquifer are relatively consistent throughout the observation period
Consistent downward hydraulic gradients have been observed at well clusters MW107 MW108
and MW116 Near the Former Primary Disposal Area water levels in MW107S were two to
three feet higher than the level in MW107TT resulting in a downward vertical hydraulic gradient
that is about a factor of 100 greater than the horizontal gradient from MW107TT to MW105TT
In addition shallow piezometric heads near MW108 and MW1 16 have ranged from 05 to 15
feet higher than heads in the lower portion of the aquifer This downward component at MW107
likely results from the low hydraulic conductivity of shallow soils near the well screen of
MW107S (factor of 200 less than underlying deposits refer to MW107S and MW107TT data in
Table 3-1) and drainage of surface water runoff from upslope areas into the depression formed by
excavation of the Former Primary Disposal Area The low hydraulic conductivity test result for
5797wpdocsgalluprifinlaquoltextmasteiTifhl06 1297 3-14 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW107S and the observed downward hydraulic gradient may be related to the increased silt
content of soils near well MW107S The vertical VOC distribution at location MW107 (shown
on Plate 3-12 and discussed in Section 4) also strongly supports a predominantly vertical
groundwater flow direction in the upper portion of the aquifer because only trace levels of VOC
were detected in MW107S The downward hydraulic gradients in the vicinity of wells MW108
and MW116 (Plate 3-13) also appear to be associated with the higher hydraulic conductivity of
deep deposits compared to shallow soils (Section 331) and groundwater recharge
West of the railroad tracks near well clusters MW102 MW101 and MW118 the measured flow
direction in the aquifer is predominantly horizontal based on the negligible vertical hydraulic
gradient between shallow and top-of-till wells at these locations However in the immediate
vicinity of Mill Brook vertical groundwater flow is important within the upper several feet of the
aquifer In the vicinity of wells MW103 MW117 and MW119 shallow piezometric heads are
generally 03 to one foot lower than deep heads Using a representative aquifer thickness of 50
feet the average upward vertical hydraulic gradient in this area is about 001 feet per foot by
comparison the local horizontal hydraulic gradient is approximately 0007 feet per foot Based
on these data a significant fraction of the shallow aquifer near wells MW103 MW117 and
MW119 may be discharging into Mill Brook Within the lower portion of the aquifer the
vertical hydraulic gradient becomes very small in magnitude
To further evaluate the hydraulic influence of Mill Brook on the overburden aquifer a vertical
two-dimensional numerical groundwater flow model was developed and a sensitivity analysis was
performed (Appendix U) The results of the modeling indicate that vertical flow in the upper
portion of the stratified drift aquifer near Mill Brook is more important west of the railroad tracks
(eg near wells MW101 and MW102) than east of the tracks (eg near well MW119) This
difference is due to the much smaller horizontal hydraulic gradients (on the order of 00003 feet
per foot) that are present west of the railroad tracks compared to ths area north of Mill Brook and
east of the railroad (horizontal gradients approximately 0007 feet per foot) Because the mean
water level in the brook is lower than the groundwater table elevation vertical flow is created in
the upper portion of the stratified drift aquifer and the depth to which this vertical flow is
important is greater in areas where the horizontal hydraulic gradient (and groundwater velocity is
less) In the vicinity of wells MW101 and MW102 the groundwater flow simulations indicate that
as much as one-third to one-half of the stratified drift aquifer may discharge into Mill Brook
East of the railroad tracks no greater than ten to 25 percent of the groundwater flow in the
stratified drift aquifer is estimated to discharge into the brook
East of the railroad tracks and south of Mill Brook a consistent downward groundwater flow component is observed in addition to the regional horizontal flow component As discussed
5797wpdocraquograquolluprifinaltextmaBterrifhl061297 3-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
above this downward component is largest near the Former Primary Disposal Area A small
downward flow component was also observed in the vicinity of wells MW106 and MW104
Figure 3-21 is a three-dimensional perspective drawing of groundwater movement in the
overburden aquifer which was developed to further illustrate the relative importance of the
horizontal and vertical flow components in the vicinity of the Former Primary Disposal Area
The figure consists of the two sets of piezometric head contours representing shallow and deep
(top-of-till) water level measurements recorded on February 2 1995 The lower piezometric
surface is representative of flow conditions throughout the middle to lower portions of the aquifer
The upper surface represents the piezometric head variation near the water table Presented
together in the same figure these two sets of contours allow an interpretation of the predominant
(but not all) three-dimensional pathlines originating in the vicinity of the Former Primary Disposal
Area As the pathlines illustrate shallow groundwater near these locations is expected to move
predominantly downward in the upper portion of the aquifer (although some local horizontal flow
may occur due to variations in the hydraulic conductivity of aquifer material) due to the large
vertical hydraulic gradients and the small aquifer thickness
Once groundwater has passed through the less permeable shallow soils it moves in a
predominantly horizontal direction dictated by the piezometric head distribution in the lower
portion of the aquifer
Based on the stream piezometer data presented in Table 3-5 Mill Brook generally gains water
from the overburden aquifer in the northern portion of the Study Area For most dates stream
bed flow was upward at piezometers PZ-6 PZ-5 PZ-4 PZ-4A and PZ-4B located west of the
railroad tracks and at piezometers PZ-1 and PZ-2 located east of the railroad tracks The
streambed vertical flow direction at piezometer PZ-3 located immediately upstream from a beaver
dam and possibly influenced by backwater effects was variable These data are consistent with
the shallow groundwater flow conditions depicted in Plate 3-9 where the head contours passing
through Mill Brook are bent (or V) in an upstream direction This piezometric head contour
pattern is representative of a gaining stream
Any groundwater discharge from the aquifer into Mill Brook would be significantly diluted by
flow in the brook A rough estimate of the potential surface water dilution rate can be obtained
by comparing the stream flow rate with the total discharge rate of groundwater through a given
vertical cross-sectional area For example using an upper bound hydraulic conductivity estimate
of 100 feet per day (0035 cms) a horizontal hydraulic gradient of 0001 feet per foot and an
area 200 feet wide (plume width) by 20 feet deep (about one-third of the aquifer thickness) a
conservatively high estimate of potential discharge from the contaminated portion of the aquifer
5797wpdocraquogalluprifinaltextmasterrifhl061297 3-16 Q^T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
into Mill Brook is approximately 0005 cubic feet per second or cfs (21 gpm) Based on a
measured stream flow rate of about 30 cfs at station UB10 the concentrations of dissolved
constituents in groundwater would be reduced by a factor of about 6000 upon mixing with the
entire stream flow
34 Ecology An ecological study was performed primarily to delineate wetlands and to make local observations
of the types and abundance of plants and animals in the area
341 Wetland Delineation
Delineation of wetlands within the Study Area and adjacent lands was conducted during the period
of August 26 to September 1 1994 Team members included two ESE wetlands biologists and a
certified soil scientist affiliated with the Soil Science Society of Southern New England As
discussed in Section 2131 the delineation performed to meet the States criteria focused on soil
types and hydric soil characteristics while the delineation performed to meet the Federal criteria
used USACOE methods which include the examination of vegetation hydrology and soils
As shown on Plate 3-14 wetlands were identified and delineated along the northern and western
portions of the Study Area Areas bordering the Site to the south and east reflect upland
conditions
Wetland delineation efforts were initiated along the face of a steep gradient along the southwestern
portion of the study area (west of the railroad grade) This allowed the field team to observe the
most obvious characteristics of both upland and wetland regimes Areas reflecting more subtle
wetlandupland indicators were investigated after having gained local experience with the obvious features
The wetland bordering the southwestern portion of the study area is a white cedar swamp
(unnamed) supporting a varying density of trees The swamp is hydraulically connected to the
Mill Brook system by a narrow stream The stream limits surface water flow causing the swamp
to maintain a long hydro period (duration of inundation or saturation) even though it is
topographically higher than the receiving floodplain It appears that the swamp remains inundated
during most years with the possible exception of drought years Judging from the high hydraulic
conductivity of the surrounding soils the swamp receives water through seepage from
surrounding uplands and to a lesser degree from surface water runoff
Portions of the swamp support a low density of older cedars while other areas support denser
stands of young cedars It appeared that the older age class occurred in deeper water while the
5797wpdocsgalluprifinraquoltextmasterrifhl061297 3-17 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
younger stands favored shallower water White cedar trees are not tolerant of fire events and it is r
likely that this age class distribution reflects a fire-maintained system where the deeper portions of
the swamp have been more effective in excluding natural fires hence supporting the oldest
cedars Additional hydrophytic plant species identified within the transition zone include red
maple common reed duckweed jewelweed cattail and coast pepper-bush
The upland system bordering the cedar swamp and floodplain forest supports a sub-climax to near
climax hardwood forest Topography of the upland includes steep slopes to gently undulating
land Canopy vegetation (trees) are dominated by oak species (red white and chestnut) with
white oaks nearer the wetland transition area and red and chestnut occurring on the higher
portions of the uplands Other canopy species included white ash quaking aspen hickories and
dogwoods Common understory vegetation included sheep laurel black cherry and green briar
Herbaceous vegetation included species found in the under story and canopy in addition to hay-
scented fern among others
Northward of the stream feature draining the cedar swamp lies the broad floodplain of Mill Brook which closely coincides with the northern boundary of the Site The floodplain is generally flat with many small raised hummocks This area reflects more seasonal fluctuations in hydro period and shallower water depths than the cedar swamp a result of more efficient drainage of the system For this reason natural succession is more advanced and the system supports a higher _ Jgth
diversity of hardwood canopy under story and herbaceous species composition
With the exception of two small isolated topographic depressions (excavated pits) located just west of the southern portion of the Site the delineated wetland areas correspond with the edge of the Mill Brook floodplain Most of the wetlandupland boundary occurs along the edge of a steep grade which closely coincides with the 150-foot ground elevation contour interval The sharp relief produces a narrow transition zone between upland and wetland communities The delineated lines reflect this as the State and USACOE wetland boundaries coincide at nearly
every location The State and USACOE lines are different in a small area adjacent to the railroad tracks immediately north of the Site In this area the State line is upgradient of the USACOE line The soils above the floodplain do not exhibit hydric soil characteristics as defined in the federal manual used for delineating wetlands The soil appears well-drained and depth to water is at a lower elevation than the floodplain soil just a few feet away The soil resembles the description of Suncook an excessively drained soil commonly mapped with Rippowam soils Both Rippowam and Suncook soils are listed on the State hydric soils list while Suncook is not listed by SCS as a hydric soil
5797wpdocsgalluprifinaltextmasterrifhl061297 3-18 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
A relatively small area of wetlands were determined to occur within the boundaries of the Site proper Wetlands occur in the area northeast (upgradient) of the Former Primary and Secondary
Disposal Areas and along the northern border of the Site east of the railroad bed The two topographic depressions corresponding to the former disposal areas (primary and secondary) lack
hydrophytic vegetation and hydric soil characteristics Other excavated areas to the south and
southwest (on-site) support hydrophytic vegetation and meet hydrology criteria but lack hydric
soil characteristics The depression to the southwest bordering the railroad supports hydrophytic vegetation and is occasionally inundated with surface water (following significant precipitation
events) but lacks hydric soil indicators In this area the ponded water was judged to be the
result of a confining layer of residual tar (presumed to be associated with former CTDOT asphalt
plant operations) immediately beneath an organic layer which causes precipitation to accumulate
342 Plant and Animal Survey
Site Characterization
An objective investigation of native plant and animal species and their habitat was conducted by US Fish and Wildlife Service (USFWS) staff in summer of 1993 (Prior et al 1995) Their
examination included a Site walkover observation and mapping of vegetation cover (shrubs
trees hydrophytic plants) and observation of direct or indirect evidence of wildlife (birds mammals amphibians) Although the Site proper is characterized as highly disturbed no
conclusions were drawn with regard to the effects of past human disturbance on the local ecology
The large majority of plant and animal species observed in the study are native to the region and
commonly found in other disturbed communities andor wetland environs
Reconnaissance of the study Site and adjacent lands was performed prior to delineation activities
to identify habitat types terrain physical access and develop logistics for completing the wetland
delineation The study area is a peninsular feature which extends northward and westward from
the Site entrance at Tarbox Road The study area is bisected diagonally by the railroad right-ofshy
way The Gallup Quarry Site (the quarry) lies to the east of the railroad divide and the remainder
of the study area (the west end) lies to the west Portions of the east boundary of the quarry abut
State Route 12 with other areas bounded by private property
The boundaries of the peninsula are characterized generally by steep slopes which are met
immediately by wetlands The upland soils are glacial till with some areas composed mostly of sands with coarse gravel occurring with lower frequency Some of the higher and relatively
undisturbed areas are composed of large rocks protruding to the ground surface Soils in the
transition zones between upland and wetland are composed of organic muck overlying sand
5797wpdoc8gilluprifinaltextmalaquoterriftil061297 3-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
These natural conditions along with historical use of portions of the area (mining and
manufacturing) cre responsible for the character of the plant communities found throughout the
study area The quarry reflects significant disturbance from historical mining and asphalt
operations The Site has numerous excavated depressional areas and areas of mounded earth
material These features significantly distinguish the quarried area from the area off-site to the
west which is undeveloped and relatively undisturbed The assemblage of plants in the quarry
reflects these conditions many of the excavated zones are devoid of vegetation and areas adjacent
to them support a mix of successional pioneer species Density of vegetation ranges from bare
soil to dense brush and sapling sized trees Areas of highest vegetation density are associated
with both low elevation (greatest soil moisture regime) and age (length of time since disturbance)
Trees throughout the quarry are young and small in comparison with those found in the forested
areas west of the railroad Vegetation on-site is characterized as early successional species The
more common species include black willow northern bayberry eastern cotton-wood quaking
aspen goldenrod and black cherry
Few wildlife species were observed or noted during wetland delineation activities Wildlife
activity within the Study Area was limited during the survey period but should be expected to
support a much greater diversity of wildlife during the spring and summer seasons when birds
(especially migratory) conduct nesting and rearing activities Most of the species observed during
the survey are expected to overwinter at the study area Bird species recorded include mourning
dove eastern peewee tufted titmouse black-capped chickadee blue jay white-breasted nuthatch
gray catbird American robin and northern cardinal
Vegetation species were recorded during the wetland delineation and are presented in Table 3-6
These reflect species occurring within wetland transition zones Additional species are expected
to occur in more xeric uplands and deeper wetlands
Although no qualitative samples of freshwater macroinvertebrates were obtained the distribution
of different genera between stations would appear to be strongly influenced by the variable
substrate composition and habitat which ranges from shaded moderate flowing rocky stream bed
(eg UB1 UB9) to sunny low energy depositional areas containing sand or deep muck (eg
UBS LB2)
5797wpdocsgalluprifinaltextmasterrifnl061297 3-20 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
40 Nature and Extent of Contamination
This section discusses the distribution of contaminants within the various media throughout the
Study Area and is based on analytical data collected during nine separate sampling events These nine sampling events include the Phase 1A investigation the Phase IB investigation and the Long-
Term Monitoring Program events conducted during April July November 1995 February May
August and November 1996 and February 1997) The results of the Phase 1A investigation
Phase IB investigation and the Long-Term Monitoring Program sampling events (except
November 1995 which was conducted concurrently with the Phase IB investigation) were also
presented in earlier reports (ESE 1995 -1995b -1995c 1996a 1996b 1996c 1997a 1997b)
Section 41 addresses the results of investigations into potential source areas including surface and subsurface soil Section 42 addresses the results of groundwater investigations Section 43
presents the results of investigations of surface water sediments and wetland soils Section 44 addresses the results of air monitoring investigations Section 45 identifies potential sensitive
human receptors within a one mile radius of the Site
Sample analyses were performed pursuant to the Gallups Quarry Superfund Project RIFS Quality Assurance Project Plan dated August 29 1994 Laboratory analytical testing for Level 4
was generally conducted for analytes identified in the Contract Laboratory Program (CLP) target
compound list (TCL) for organics and target analyte list (TAL) for inorganics Analyses were
conducted pursuant to the CLP Statement of Work for Organics MultimediaMulticoncentrations
Document OLM 018 and the CLP Statement of Work for Inorganics
MultimediaMulticoncentrations Document ILM 030 Appendix IX analyses were conducted by
CLP and SW-846 Methods as described in the QAPP Low-level VOC in drinking water were analyzed by EPA Method 5242 with CLP SOW reporting Laboratory reports for the Phase 1A
Phase IB and Long-Term Monitoring Program sampling events are presented in Appendices H
through P Laboratory data for sample splits collected by EPAs oversight contractor during the
Phase 1A July 1995 and Phase IBNovember 1995 sampling events are also presented in
Appendices H J and K respectively The results of detected analytes are summarized in Section 4 tables The definitions of the qualifiers used for the laboratory data precede the tables in
Section 4 As discussed in various sections analyte concentrations are given either as milligramskilogram (mgkg) or microgramsliter (ugL) The units mgkg are also used
interchangeably with the term part per million (ppm) The units ugL are equivalent to parts per
billion (ppb)
Data validation was performed on all Level 4 data according to the requirements of EPA Region
I Laboratory Data Validation Functional Guidelines for Evaluating Organic Analyses (February 1
5797wpdoclaquogilluprifinaltextmlaquo8terrifiJ061297 4-1 QZT Environmental
Gallups Quarry Superjund Project - Remedial Investigation
1988 as modified November 1 1988) and Inorganic Analyses (June 13 1988 as modified
February 1989) Data validation was performed by David MacLean an independent data
validator Summaries of Mr MacLeans data validation results are presented in Appendix Q
41 Contaminant Source Investigation 411 Visual Site Reconnaissance
A comprehensive visual site reconnaissance was conducted over a three week period from August
23 until September 13 1994 to determine the potential presence of unknown disposal areas
Prior to the start of this survey a grid system was established to allow systematic coverage of the
Site and to locate features of interest The grid used to conduct the visual Site reconnaissance is
described in Section 21 A Site plan which includes the survey grid and the features described
below is shown on Plate 4-1 The features identified on Plate 4-1 are also summarized in Table 4-1
Based on this visual survey the ground surface in the northern portion of the Site which includes the Former Primary and Secondary Disposal Areas is covered with sand and gravel with sparse
to no vegetation Topographic relief is estimated to be as much as 20 to 30 feet and is attributed
to the Sites past usage as a sand and gravel quarry Many of the topographic low spots were
observed to contain either standing water (following rain events) or moist soil (indicative of
intermittent periods of ponded water)
The central portion of the Site which contains the Former Seepage Bed is presently heavily
vegetated Crushed stone and boulders are evident over a large portion of this area and the soils
consist mainly of a sandy till Immediately east and northeast of the Former Seepage Bed is a
topographic high with numerous boulders at the ground surface Evidence of previous test pit
explorations were also observed in this general vicinity Asphalt and mounds of asphalt pavement
were also observed in several areas and are presumed to be remanent of the State of Connecticut
Department of Transportation (CTDOT) asphalt plant operations discussed in Section 132
The southern portion of the Site contains the entrance to the former CTDOT asphalt plant as well
as the remains of the former plant itself These remains consist primarily of concrete footings
and retaining walls The remains of the asphalt plant are located along trending lines E through
K approximately 800 to 900 feet north of Tarbox Road The remains of a 6-foot diameter brick
and concrete masonry structure were observed along with an 8-inch diameter clay pipe leading
into the ground at the former plant location
The area located in the southwestern portion of the Site along line A includes mounded earthen
material piled along the western perimeter of the Site Scattered metal debris including several
5797wpdocsgalluprifinaltextmasterrifiil061297 4-2 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
empty rusted drums were observed adjacent to and partially buried within the mounded materials
Other objects consisting of timbers steel culvert tires and mounded asphalt were also observed
along the A line Mounded earthen materials located on lines M and N (400 to 650 feet north of
Tarbox Road) were observed to also contain miscellaneous debris (corrugated steel culvert hoses
and cables tires etc) and several empty rusted drums These areas are presently heavily
vegetated Other areas at the southern portion of the Site consist of a mixture of grassland and
brush There are numerous mounds of earthen material and scattered patches of asphalt and
pavement remanent of CTDOT operations throughout this portion of the Site
The Bionetics Corporations under contract to USEPA performed a review of historic aerial
photographs of the site and issued a Site Analysis Report (Bionetics Corp 1990) The historical
aerial photographs were used to prepare a Site plan which indicated the locations of suspected or
potential disposal areas (Figure 4-10 from the Phase 1A Work Plan (ESE 1994)) That Site plan
showed the locations of the three known former disposal areas as well as several much smaller
features described below Based on the visual reconnaissance performed during the RI areas
described in the Bionetics Report as either stained or wet or standing liquid or wet ground
correspond to topographic low spots in which ponded rainwater has been observed In addition
no visual evidence indicative of disposal activities was observed in the vicinity of the several
pits (dated 1981 through 1988) identified in the Bionetics Report These pits are believed to
be remnant of previous investigation test pits
An area described in the Bionetics Report as an extraction and an area of disturbed ground
northwest of the Former Seepage Bed correspond to an excavated area in which asphalt and
miscellaneous debris were observed during the Site reconnaissance The presence of mounded
materials in the vicinity of the Former Seepage Bed was confirmed during this visual
reconnaissance The mounded materials observed are comprised of earthen materials andor
asphalt pavement
A number of areas located within the southern portion of the Site were described in the Bionetics
Report as suspected disposal areas Features described as containing liquid generally
correspond to topographic low spots which were observed during the Site reconnaissance to
contain ponded rainwater following rain events The large feature described in the Bionetics
Report as extraction with liquid and associated dark toned material corresponds to a presently
open excavation in which asphalt was observed No features or specific objects were observed
during the Site reconnaissance which correspond to the locations of the unidentified objects
noted in the report The remains of a circular foundation observed during the Site reconnaissance
in the vicinity of the former CTDOT plant corresponds to the location of the possible vertical
5797wpdocraquogalluprifiiwltextmasterrifhl061297 4-3 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
tank Scattered mounds of earthen materials observed throughout the southern portion of the
Site correspond to the numerous mounded materials identified in the Report
Based on the observations made during this survey it is apparent that the landforms on-site have
been altered numerous times during past usage Extensive areas are presently heavily overgrown
and do not appear stressed Various earthen materials have been excavated and mounded at
numerous locations throughout the property and are presumed to be remnant of the former sand
and gravel quarrying operation andor the operation of the State DOT asphalt plant Also
patches of asphalt and mounds of asphalt pavement ranging from several to tens of square feet in
size were observed at multiple areas around the Site
The major features described as potential or suspected disposal areas in the Bionetics Report were
identified and described during the visual reconnaissance Although several empty 55 gallon
drums in various states of decomposition and scattered debris (consisting mainly of residential
trash scrap metal car parts etc) were observed at a number of locations across the Site no
intact drums or significantly stained or stressed areas were observed Other than the three known
former disposal areas no features were observed during the visual reconnaissance which indicate
the potential presence of large disposal or dumping areas
The above mentioned areas which contain debris including several empty 55-gallon drums were
further assessed during the soil gas and geophysical screening surveys performed as part of the
Phase 1A investigation The findings of these screening surveys are discussed below
412 Soil Vapor Survey
The soil vapor survey conducted on-site included a total of 100 soil vapor points installed along
an approximate 100-foot orthogonal grid Six additional sampling points were installed at three
locations where partially buried decomposed or empty 55-gallon drums were observed during
the visual site reconnaissance and at three areas where geophysical surveys detected the presence
of EM-31 andor MAG anomalies Each soil gas sample was analyzed for the presence of the
following eight VOC using a portable gas chromatograph acetone benzene 12-dichloroethene
(DCE) methylethyl ketone (MEK) methyl-isobutyl ketone (MIBK) 111-trichloroethane (TCA)
trichloroethene (TCE) and toluene
Of the 106 soil vapor sampling points tested detectable concentrations of VOC were identified at
only three locations These three locations SV160 SV165 and SV172 (shown on Plate 2-5)
were all located within approximately 50 feet of the Former Primary Disposal Area Specifically
TCE was detected at SV160 and SV165 and TCA was detected at SV165 and SV172
5797wpdocsgalluprifinaltextmasterrifhl061297 4-4 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
Likewise no VOC were detected at three additional survey points SV201 SV205 and SV206
installed within one foot of the 55-gallon drum which was observed at each of those locations or
at survey points SV202 SV203 and SV204 located in the vicinity of geophysical anomalies
identified during the EM-31 and MAG surveys
As described in the Work Plan the soil gas investigation was used as a screening survey to
identify apparent soil contamination in an effort to locate any potential unknown disposal areas
Based on the results of the soil gas survey no additional potential disposal areas were identified
413 Geophysical Investigations and Test Pits
Electromagnetic terrain conductivity (EM-31) and magnetometer surveys were conducted by
Weston Geophysical of Northboro Massachusetts as screening surveys to identify potential
unknown disposal areas The Weston Geophysical Report (provided as Appendix A) describes
in detail the findings of the geophysical investigations The significant findings of these two
screening surveys and of the follow-up test pit program are discussed below
4131 EM-31 Survey
The electromagnetic terrain conductivity measured across the Site was generally uniform with
most anomalies being attributed to wholly exposed or partially buried metallic debris (eg
automobile body parts empty rusted drums scrap pipe angle iron steel culvert and steel cable)
However two EM-31 anomalies could not be accounted for by noted surface features As shown
on Plate 2-14 the two unexplained EM-31 anomalies were located along trend line M at station
550 and at station 590 Due to the complexity of the anomaly located at station 550 an estimate
of its ferrous mass could not be made The second EM-31 anomaly was described as limited in
extent and was estimated to contain approximately 100 pounds of ferrous material assuming a burial depth of five feet (smaller objects at shallower depths would also explain the anomaly)
4132 Magnetometer Survey
The magnetometer survey identified a relatively flat gradient across the Site with a number of
localized anomalies most of which corresponded directly with visible surface features or objects
(as described above) A total of four anomalies were identified which could not be readily
attributed to known surface features Two of these anomalies occurred along trend line M and
correspond to the two EM-31 anomalies described above A third magnetometer anomaly was
identified along trend line C between stations 760 and 800 This anomaly was described as
approximately 10 feet in width and was interpreted as being the result of small amounts of ferrous
material spread over the length of the anomaly (approximately 40 feet) A fourth anomaly was
identified along line L at station 315 This anomaly was interpreted to consist of a small
amount of ferrous material buried at shallow depth
5797wpdocsgalluprifinaltextmraquosterrifhl061297 4-5 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4133 Test Pit Investigations
As described above the geophysical screening surveys revealed a total of four locations at which
EM-31 or magnetometer (or both) anomalies were detected that could not be attributed to visible
surface features The anomalies measured along line M were noted in both the EM-31 and
magnetometer surveys while the anomalies along lines C and L were only measured in the
magnetometer survey To confirm the source of these anomalies test pits were excavated at the
location of each anomaly Test pit excavation was observed by EPA oversight personnel
The presence of varying amounts of miscellaneous buried scrap metal debris described below
was identified at each test pit location At the anomaly located along Line C the excavated
debris included small rusted cans sheet metal and steel cable During the excavation of the test
pit located at the anomaly along line L a three foot long piece of a solid iron rod
approximately one inch in diameter was found buried approximately four inches below the ground
surface At the anomalies located along Line M a variety of ferrous debris was uncovered
including a crushed eight foot section of corrugated steel culvert approximately 2 feet in
diameter sheet metal nuts bolts steel cable and small rusted cans No drums intact or
otherwise were encountered at any location Soil removed from each excavation as well as the
side walls and bottoms of the excavations were screened for the presence of VOC using a PID
No elevated PID readings were measured Furthermore no visible evidence of staining was
noted in the soil at any of the excavations Upon excavation all metallic debris was placed on
the ground surface adjacent to the excavation and the test pits were backfilled with native soil
Test pit logs for the four test pits are shown in Appendix E
414 Background Soils
Soil samples were collected at two monitoring well cluster locations MW109 and MW112 to
determine the general Site background levels of TALTCL compounds The two locations were
chosen based on their upgradient position in relation to the former disposal areas The soils were
submitted for laboratory analysis for TALTCL parameters (VOC SVOC pesticides PCS
metals and cyanide) Tables 4-2 and 4-3 show the positive detections for VOC and metals
These tables only show the constituents that were detected at the site Constituents that were not
detected in any sample are not shown There were no detections of SVOC or pesticidesPCB in
any background soil sample
Due to the limited surficial deposits and abundance of boulders encountered at the MW109
location samples could only be collected from the 6-8 foot interval which is representative of till
at this location Discrete samples collected at the MW112 location were obtained from the 8-10
foot and 40-42 foot intervals which represent stratified drift and till respectively Composite
5797wpdocsglluprifinlaquoltextmlaquosterrifhl061297 4-6 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
samples from MW112 were collected from the 7-14 foot and 34-40 foot intervals (stratified drift
and till respectively) These depths were chosen based on their lithology
The results of the laboratory analyses for the soils collected at MW109 indicate the presence of
trace concentrations (0004 mgkg) of toluene no other VOC were detected No detectable
concentrations of SVOC pesticides or PCB were encountered in soil from the MW109 sample
location
Soils collected at the MW112 location also contained detectable concentrations of toluene
Toluene was detected at concentrations of 003 0017 0029 and 0032 mgkg from 8-10 feet 7shy
14 feet 10-14 feet and 34-40 feet respectively Trace concentrations of methylene chloride
(0003 mgkg) and trichloroethene (0002 mgkg) were also detected in the MW112 sample at 10shy
14 feet and 40-42 feet respectively No detectable concentrations of SVOC pesticides or PCB
were identified at the MW112 location
Although the source of the VOC is unknown all three of these compounds are organic solvents
that are (or were ) commonly used in many household (eg spot removers paint strippers
aerosols) commercial (eg pesticide formulations inks and dyes) and industrial (eg
degreasers) products
Metals concentrations in background soil boring samples are shown on Table 4-3 As expected
various metals were detected in all soil samples Analytical results for metals for all of the
MW112 samples were within the common range for soils found in the eastern United States
Heavy metals were generally detected only at trace concentrations Alkaline earth metals (eg
Ca Mg K) were detected at levels not unexpected for soils in the region Background concentrations of metals in subsurface soils were used for comparison purposes in analyzing the
significance of the metals concentrations measured in other non-background soil samples
415 Soils From Former Known Disposal Areas
Soil borings were drilled at each former known disposal area to determine whether residual
contamination remains in surface and subsurface soils During the Phase 1A investigation a total
of ten soil borings were performed Soil samples were collected from these borings and
submitted for laboratory analysis for TALTCL parameters (VOC SVOC pesticides PCB
metals) pH total organic carbon (TOC) and moisture content An additional six borings were
performed during the Phase IB Investigation Soil samples collected during the Phase IB
Investigation were submitted for laboratory analysis for VOC and pesticidesPCBs The
locations of the soil borings are shown on Plate 2-3
5797wpdoc8galluprifinaltextma8terrifhl061297 4-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Samples from the 0-1 foot interval were collected from each boring by hand using a stainless
steel scoop Continuous soil samples beneath the 0-1 foot interval were collected using a truck-
mounted drill rig equipped with standard split-spoon samplers Generally samples were collected
from both above and below the water table and at depth within each of the former known
disposal areas In addition each significant lithologic unit was sampled The specific sampling
depths and length cf sampling interval varied for different analytical parameters depending on the
lithology and volume of sample recovered from each spoon Sample intervals and analytes are
summarized in Table 2-2
A brief description of the reported historical disposal activities and the findings of the Soil
Sampling Program for each specific area are described below Positive hit tables showing the
laboratory results for soil boring samples collected from within the former known disposal areas
are presented in Tables 4-4 through 4-7 The unvalidated laboratory data for TALTCL
parameters are presented in Appendix H (Phase 1A data) and K (Phase IB data) Laboratory
results for pH total organic carbon and moisture content are presented in Appendix R
4151 Former Seepage Bed
The Former Seepage Bed is located near the center of the Site This feature is located on the
north side of a local bedrock high which is overlain by 10 to 20 feet of boundary till Historical
records indicate that this area was used for the direct discharge of liquid waste to the ground
surface It has been reported that an inverted dump truck body was buried in this area and was
connected to the ground surface via a pipe Liquid wastes were then reportedly poured directly
into the pipe The wastes reportedly dumped in this area have been described as low pH liquids
characteristic of metal pickling liquors The dump truck body and the contaminated earth were
removed in 1979 during CTDEP remedial efforts Approximately 20 tons of lime (which is
approximately equal to 10 cubic yards) was reportedly spread in the vicinity of the seepage bed to
neutralize any residual low pH material The soil boring program indicated that fill material in
this area extends from 3 to 7 feet below the ground surface Based on the approximate lateral
extent of this former disposal feature (as shown in historic plans of the Site) approximately 230
yards of sand and gravel fill material were used to backfill the CTDEP excavation
To investigate this area three soil borings (SB101 SB102 and SB103) were completed The
borings within the Former Seepage Bed were terminated at auger refusal depths of 68 feet
(SB101) 185 feet (SB102) and 160 feet (SB103) Within this area groundwater was only
encountered in the bottom 6 inches of the deepest boring (SB 102)
5797wpdocsgalluprifinaltextmasteiTifnl061297 4-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Surface Soil Sample Results - Former Seepage Bed
As shown in Table 2-2 the 0-1 foot interval was sampled at each location and submitted for
laboratory analysis for VOC SVOC pesticides PCB and metals No VOC were detected in this
interval at any of the three soil borings within the Former Seepage Bed In the 0-1 foot interval
very low levels of SVOC primarily polynuclear aromatic hydrocarbons (PAH) were detected at
SB101 and SB103 The concentrations of PAH ranged from 0012 ppm to 0076 ppm Moderate
concentrations of bis(2-ethylhexyl)phthlate (15 ppm) were also seen in this interval at SB101
Trace levels of certain pesticides were also seen in the 0-1 foot interval at SB101 [44-DDE
(00014 ppm) 44-DDT (0019 ppm) and 44-DDD (0041 ppm)] and at SB102 [44-DDD
(0011 ppm)] At SB102 a low level of PCB (Aroclor-1260 at 0027 ppm) was detected in the
surface soil sample
The results of metals analyses have been compared to background soils metal concentrations
determined from soil samples collected from the background monitoring wells MW109 and
MW112 With the exception of calcium (12200 ppm) and magnesium (9620 ppm) seen in the
0-1 foot interval at SB102 most metals in the surface soil samples were close to the background
concentrations seen at the Site The elevated concentrations of both calcium and magnesium are
attributed to the 20 tons of lime which were used in this area by CTDEP Compared to the
background level seen for lead (35 ppm) the concentration of this metal in the 0-1 foot interval
was slightly higher at SB101 (59 ppm) SB102 (43 ppm) and SB103 (69 ppm) Also silver
which was not seen in any of the background samples was detected in the 0-1 foot interval at
SB101 at 87 ppm
Unsaturated Zone Sampling Results - Former Seepage Bed
Within the unsaturated zone below the 0-1 foot interval described above only trace levels of
VOC were detected Toluene was seen in SB101 (4-6 feet) and SB102 (16-18 feet) at a
concentration of 0002 ppm Xylene (total) was also detected at the same two intervals at the
same concentrations The only other VOC detected was TCE in SB101 (4-6 feet) at a
concentration of 0004 ppm
The only SVOC detected within the unsaturated zone at the Former Seepage Bed was di-n-octyl
phthlate detected in all three borings at various depths at concentrations ranging from 001 to
0021 ppm Very low concentrations of several pesticides (SB101) and PCB (SB101 and SB102)
were detected at various depths in unsaturated zone samples below the 0-1 foot interval The
pesticides 44-DDD (0033 ppm) 44-DDT (0024 ppm) and dieldrin (000064 ppm) were
5797wpdocBgalluprifinaltextmlaquosteiTifhl061297 4-9 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
detected at SB 101 The highest detections of the PCS for Aroclor-1260 and Aroclor-1254 were
0027 (SB102 0-1 feet) and 0034 ppm (SB1012-5 feet) respectively
Within the unsaturated zone below the 0-1 foot interval the only metals detected above the
highest background concentrations were aluminum barium iron magnesium manganese and
potassium The highest concentration of each of these metals was only slightly higher than
background levels and all were within the same order of magnitude
Among the Former Seepage Bed borings only one (SB 102) encountered groundwater above the
auger refusal depth Since only six inches of saturated soil was encountered the limited sample
volume was submitted for VOC analysis only No VOC were detected in this sample
pH TOC Moisture Content - Former Seepage Bed
The pH of samples collected in this area ranged from 622 to 792 Total organic carbon values
(mgkg) ranged from 1600 to 23000 Moisture contents ranged from 42 to 105 percent
4152 Former Secondary Disposal Area
The Former Secondary Disposal Area is located in the northwestern corner of the Site adjacent to
the railroad tracks The Disposal Area is presently seen as a depression which is approximately
50 feet wide by 60 feet long and is approximately 6 to 8 feet below the surrounding ground
surface The ground surface at this area is covered by approximately 2 feet of backfill (mostly
sand) material The fill is underlain by fine- to coarse-grained sand which ranges in thickness
from approximately 6 to 22 feet Sandy till ranging in thickness from 10 to 20 feet underlies the
sand The depth to groundwater from the bottom of the depression is approximately 10 feet
Historical records indicate that this area was used for the disposal of drummed liquid wastes
Approximately 200 drums and an unknown quantity of contaminated soil were removed in 1979
during CTDEP remediation efforts
In order to characterize residual contamination which may be present beneath this area three soil
borings (SB 104 SB 105 and SB 106) were performed within the depressed area ranging in depth
from 30 feet (SB 105) to 36 feet (SB 104) Within this area groundwater was encountered at
approximately 10 feet below the ground surface
5797wpdocsglaquolluprifinlaquoltextmaBterrifnl061297 4-10 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Surface Soil Sample Results - Former Secondary Disposal Area
Within the 0-1 foot interval only a trace concentration of one VOC (ethyl benzene at 00006
ppm) was detected (at SB104) The only SVOC detected in this interval was butylbenzylphthlate
(014 ppm) at SB 104 Very low concentrations of pesticidesPCB were measured at each boring
Aroclor-1254 was detected at SB104 (0025 ppm) and SB105 (0021 ppm) Aroclor-1260 was
detected at all three borings ranging in concentration from 00089 to 0031 ppm Dieldrin was
detected at SB 104 at trace levels (000048 ppm)
In the 0-1 foot interval nearly every metal detected occurred at concentrations close to those for
the background samples with the exception of lead which was detected at a concentration of 118
ppm at SB 104 Cyanide was detected in this interval at very low concentrations ranging from 16
to 97 ppm
Unsaturated Zone Sample Results - Former Secondary Disposal Area
Between the 0-1 foot interval and the groundwater table at the Former Secondary Disposal Area
no VOC were detected The only SVOC detected in this zone were at very low levels
(butylbenzylphthlate at 0037 ppm and di-n-octylphthlate at 0012 to 0029 ppm) Also in this
interval at SB104 and SB105 low levels of the PCB Aroclor-1254 and -1260 were detected at
concentrations up to 0055 ppm and 0018 ppm respectively Dieldrin was detected at a trace
level (00014 ppm) at SB104 Within this zone most of the metals were close to the background
soil concentrations except for lead (224 ppm) at SB104 and copper (476 ppm) at SB105
Cyanide was detected in the 1-10 foot interval at SB104 and SB105 at very low concentrations of
83 and 31 ppm respectively
Saturated Zone Sample Results - Former Secondary Disposal Area
Beneath the groundwater table within the Former Secondary Disposal Area no VOC were
detected The only SVOC detected was di-n-octylphthalate which ranged in concentration from
002 to 008 ppm Very low levels of endrin (00004 ppm) and Aroclor-1248 (001 ppm) were
also detected just below the water table but were not present in the deepest sample collected (26shy
28 feet) The only metals which were detected below the water table at concentrations notably
higher than background levels were copper and nickel Copper ranged in concentration from 621
to 863 ppm while nickel ranged from 119 to 169 ppm The highest concentrations of these
two metals were detected just below the groundwater table
5797wpdocsgalluprifinaltextmasterrifhl061297 4-11 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
pH TOC Moisture Content - Former Secondary Disposal Area
The soil pH ranged from 688 to 751 TOC ranged from lt 1500 to 2800 mgkg and moisture
content ranged from 37 to 124 percent
4153 Former Primary Disposal Area
The Former Primary Disposal Area is located at the northern end of the Site approximately 150 feet east of the Former Secondary Disposal Area This feature is seen as a circular depression
approximately 130 feet in diameter (at the top edge) and is approximately 8 to 10 feet lower than
the surrounding ground surface Non-native fill material (sand and gravel) ranged in thickness
from approximately 2 to 4 feet Underlying the fill is an approximately 15- to 20- foot thick
generally sandy horizon which overlies 6 to 15 feet of till The water table in this area ranges
from approximately 3 to 6 feet beneath the ground surface in the bottom of the depression
Records indicate that approximately 1400 drums and approximately 5000 gallons of free liquids
were removed from the Former Primary Disposal Area during CTDEP cleanup efforts
Approximately 2000 to 3000 cubic yards of contaminated soil were also removed during that
effort
During the Phase 1A (1994) investigation a total of four soil borings (SB107-SB110) were
completed within the Former Primary Disposal Area to characterize the extent of residual soil
contamination These borings ranged in depth from 24 feet at SB108 to 39 feet at SB109 An
additional six borings (SB111-SB116) were completed during the Phase IB (1995) investigation
Samples collected during the Phase IB investigation were submitted for laboratory analysis for
VOC and PCBPesticides The purpose of the additional borings was to further delineate the
lateral extent of residual VOC and PCB contamination in the unsaturated portion of the soil The
Phase IB borings were terminated just below the groundwater surface typically five to seven feet
below the ground surface The locations of all of the borings are shown on Plate 2-5 however a
detailed close-up showing the boring locations within the Former Primary Disposal Area is shown
as an insert on Plates 4-2 and 4-3 which are discussed below The tabulated laboratory data for
both the Phase 1A and Phase IB soil borings are shown on Tables 4-4 through 4-7 (VOC SVOC
pesticidesPCB and metals respectively)
Surface Soil Sample Results - Former Primary Disposal Area
In the 0-1 foot interval only a limited number of VOC were detected generally at very low
concentrations (Table 4-4) The compounds detected in the 0-1 foot interval (followed by
concentration [ppm] and location) are as follows acetone (0007 ppm at SB107)
5797wpdocsgalluprifinaltextmasterri fhl061297 4-12 QST Environmental
Catlaps Quarry Superfund Project - Remedial Investigation
tetrachloroethene (PCE) (0018 ppm at SB109 and 0002 at SB113) toluene (0005 at SB112
0003 at SB1H and 0002 at SB115) ethyl benzene (0002 at SB113) and total xylenes (0010 at
SB113) In this same interval several phthalates (butylbenzyl bis(2-ethylhexyl) diethyl and dishy
n-octyl) were detected at various locations (Table 4-5) with no apparent spatial trend at
concentrations ranging from 0008 to 17 ppm Several PAH compounds were also detected at
SB110 in the 0-1 foot interval at concentrations ranging from 0007 to 0017 ppm As shown in
Table 4-6 Aroclor 1254 was detected in the 0-1 foot interval at every boring at concentrations
ranging from 0046 to 43 ppm Aroclor-1260 was also detected in the 0-1 foot interval at
concentrations ranging from 0046 to 23 ppm Trace concentrations of several pesticides were
also detected in the 0-1 foot interval in some borings as follows heptachlor epoxide (000058 to
0052 ppm) dieldrin (000059 to 0043 ppm) 44-DDE (000089 to 0081 ppm) and 44-DDT
(000048 to 0027 ppm) Aluminum (12200 ppm at SB110) was the only metal in the 0-1 foot
interval that was detected at concentrations significantly greater than background levels (Table 4shy
7) Cyanide was detected at a very low concentration of 16 ppm at both SB109 and SB110
Unsaturated Zone Soil Sample Results - Former Primary Disposal Area
Beneath the 0-1 foot interval but above the water table a small number of VOC were detected at
various concentrations and locations (Table 4-4) Within this zone no VOC were detected at
SB107 At SB108 methylene chloride was detected at 0001 ppm Ethyl benzene was detected
at SB 109 (015 ppm) SB110 (54 ppm) SB111 (0048 ppm) and SB115 (16 ppm) Total
xylenes were seen at SB109 (16 ppm) SB110 (46 ppm) SB111 (064 ppm) and SB115 (80
ppm) Toluene was detected at SB 110 through SB 115 at concentrations ranging from 0003 to 12
ppm PCE was seen at SB109 SB111 SB114 and SB116 at concentrations which ranged from
0003 to 17 ppm and at SB115 at 28 ppm 111-TCA was detected at SB111 112 114 115
and 116 from 0001 to 14 ppm TCE was also seen at SB111 114 115 and 116 at
concentrations ranging from 0002 to 17 ppm 2-butanone (MEK) was detected at SB111 at
0005 ppm 12-DCE was seen at both SB115 (016 ppm) and SB116 (0009 ppm) Finally 11shy
DCA (0008 ppm) 11 -DCE (0009 ppm) and carbon disulfide (0022 ppm) were all seen at
SB115 Methylene chloride (0001 ppm) was detected at SB108 These detections occurred in
the transition zone between fill and native deposits
The SVOC detected in this zone (shown on Table 4-5) included several phthalates at
concentrations ranging from 0039 to 46 ppm Napthalene was also detected at SB109 (047
ppm) and SB110 (63 ppm) 12-dichlorobenzene and 2-methylnapthalene were detected at SB110
at 098 and 081 ppm respectively The most frequent occurrence and highest concentrations of
phthlates (and SVOC in general) occurred at SB 109 and SB 110
5797wpdocraquogalluprifinaltextmlaquolaquoterrifhl061297 4-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
As shown on Table 4-6 Aroclor-1254 occurred at most of the borings in this zone at gtbullraquo
concentrations ranging from 00023 to 64 ppm Aroclor-1242 (0043 to 017 ppm) and Aroclorshy
1260 (043 to 24 ppm) were detected at SB109 and SB110 Pesticides were also detected at trace
to very low concentrations at several locations These compounds include dieldrin (000028 shy
00046 ppm) 44-DDE (000043 - 00063 ppm) 44-DDT (00013 - 00081 ppm) beta BHC
(00013-00021 ppm) and delta BHC (000086-00024 ppm) endrin ketone (00028 ppm)
heptachlor epoxide (0008 ppm) heptachlor (00093 ppm) endosulfan I (0008 ppm) and
methoxychlor (0140 ppm) Table 4-7 shows that the only metals detected within this zone at
concentrations significantly higher than background levels were cadmium (131 ppm) and copper
(103 ppm) both of which occurred at SB109 Cyanide was detected in SB110 in the 1-35 foot
interval at a very low concentration of 32 ppm
Saturated Zone Soil Sample Results - Former Primary Disposal Area
The highest concentrations of VOC within the Former Primary Disposal Area occurred just below
the surface of the groundwater table in the natural deposits immediately underlying fill material
As shown on Table 4-4 in the 4-6 foot interval at SB 109 the following VOC were detected 12shy
DCE (059 ppm) PCE (36 ppm) TCA (98 ppm) TCE (62 ppm) ethyl benzene (85 ppm)
toluene (44 ppm) and xylenes (46 ppm) In the next deepest interval sampled (14-16 feet)
generally the same compounds were detected however the concentrations were lower by an
order of magnitude At the last sampled interval (30-32 feet) generally the same compounds
were again detected but at trace levels (0001-0006 ppm) Cyanide was detected in SB110 in the
10-16 foot interval at a very low concentration of 11 ppm
A total of six SVOC were detected just below the water table at a depth of 4-8 feet below ground
surface (Table 4-5) phthalates (0039 to 0058 ppm) napthalene (021 ppm) 2-methylnapthalene
(0034 ppm) phenol (016 ppm) and 124-trichlorobenzene (0046 ppm) SVOC at greater
depths were napthalene (0076 ppm) in the 10-16 foot interval and bis(2-ethylhexyl)phthlate (11
ppm) at the 22-32 foot interval Aroclor-1254 was detected at concentrations which decreased
with depth from 02 ppm at 4-8 feet to 00096 ppm at 23-34 feet
In the saturated zone no metals were detected at levels significantly greater than background
pH TOG Moisture Content - Former Primary Disposal Area
Values for soil pH ranged from 609 to 745 TOC ranged from lt 1500 to 5500 mgkg and
moisture content ranged from 49 to 282 percent
5797wpdocsgalluprifinaltextmasterrifnl061297 4-14 QST Environmental
Gallups Quarry Superfand Project - Remedial Investigation
416 Contaminant Source Investigations Summary
The previous discussions regarding the contaminant source investigations are grouped into two
categories
bull surveys to identify unknown disposal areas (if any) and
bull investigations at known former disposal areas
Based on the findings of the Visual Site Reconnaissance the Soil Vapor Survey and the
Geophysical Investigations (including the subsequent confirmatory Test Pits) it is apparent that
significant unknown hazardous materials disposal features do not exist at the Site
Based on investigations performed within the known former disposal areas it is evident that the
Former Seepage Bed and the Former Secondary Disposal Area contain generally trace levels of
VOC SVOC pesticides PCB compounds and cyanide For the most part soil metal
concentrations are comparable to background levels measured at upgradient locations at the Site
although very low levels of cyanide (ranging from 11 - 97 mgkg) were also detected at various
depths within the Former Primary and Secondary Disposal Areas Elevated levels of calcium and
magnesium detected at the Former Seepage Bed can be attributed to the large amount of lime
which was reportedly used during remedial efforts Although elevated concentrations of several
other metals were detected at a few locations these levels appear to fall within regional range
values (for the metals with published ranges)
The Former Primary Disposal Area appears to be the only area with notable levels of residual
contamination primarily VOC including ethyl benzene toluene xylene TCA TCE and PCE
In general the highest VOC concentrations are located at or just below the groundwater table in
native materials immediately beneath the fill materials These concentrations diminish quickly
with depth Toluene ethyl benzene xylene and in one case a low level of PCE were also
detected at or near the ground surface within the fill material Empty gasoline cans numerous
off-road vehicle tire tracks and the remains of large campfire pits have been observed in the
vicinity of the former disposal areas Of the VOC detected the ones considered most significant
are those which are also seen in groundwater above their respective MCL (groundwater results
are discussed separately in section 42) In an effort to illustrate the locations where the more
notable amounts of residual VOC contamination are found Plate 4-2 which shows the locations
of total chlorinated VOC has been prepared On this plate the values for total chlorinated VOC
have been color-coded as follows sample intervals where all compounds were below the detection
limit (BDL) are not colored intervals where total chlorinated VOC values are present but less
5797wpdoc8glaquolluprifinraquoltextmasterrifhl061297 4-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
than 1 ppm are shown in green values between 1 and 10 ppm are shown in yellow and locations
between 10 and 35 ppm are shown in red The highest value for any interval is 31277 ppm
As indicated on Plate 4-2 total chlorinated VOC concentrations were either BDL or less than 1
ppm for the majority of intervals sampled Total concentrations between 1 and 10 ppm (ie
yellow zones on Plate 4-2) were detected at two locations SB108 and SB109 Total chlorinated
VOC concentrations in the 4-6 interval at SB108 were 155 ppm At SB109 total chlorinated
VOC concentrations were between 1 and 10 ppm within the 2-4 foot interval (17 ppm) and the
14-16 foot interval (213 ppm) Total chlorinated VOC concentrations exceeded 10 ppm at two
locations SB 109 (2019 ppm in the 4-6 foot interval) and SB115 (31277 ppm in the 3-5 foot
interval) As seen on the plan view insert on Plate 4-2 SB109 and SB115 are located within
approximately 25 feet of each other in the northwestern quadrant of the Former Primary Disposal
Area The zone of highest chlorinated VOC contamination appears to be located just beneath the
fill horizon in close proximity to the groundwater surface
Trace to low-levels of PCB were also detected in both near surface samples and (at one location)
at a depth of 32 feet below the ground surface The highest concentration of any single PCB
compound was 64 parts per million in the 1-35 foot interval at SB110 Other detections
included 43 ppm (SB107 0-1 foot interval) 3 ppb (0-1 foot interval at SB109 and SB110) 28
ppm (0-1 foot interval at SB113) 23 ppm (0-1 foot interval at SB107) and 24 ppm (1-35 foot
interval at SB110) All other detections were below 15 ppm
Plate 4-3 has been prepared to illustrate the distribution of PCB compounds detected within the
Former Primary Disposal Area Plate 4-3 shows the concentration and locations for total PCB
compounds for all intervals sampled with the area
Total PCB concentrations have been grouped and color coded on Plate 4-3 as follows sample
intervals where no PCB were detected (BDL) are shown as colorless zones where total PCB were
detected at concentrations less than 1 ppm are shown in green Intervals containing between 1
and 5 ppm total PCB are yellow and intervals between 5 and 10 ppm are shown in red (the
highest value for total PCB compounds anywhere was 88 ppm)
As shown on Plate 4-3 total PCB values at the majority of locations within the Former Primary
Disposal Area are less than 1 ppm Values between 1 and 5 ppm (shown in yellow) were
detected at SB109 SB110 and SB113 These intervals all occur within four feet of the ground
surface and all are within the fill horizon The only intervals where total PCB concentrations are
between 5 and 10 ppm are the 0-1 foot interval at SB107 (66 ppm) and the 1 to 35 foot interval
5797wpdoc8galluprifinaltextmastemfhl061297 4-16 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
at SB 110 (88 ppm) There does not seem to be any spatial trend or relationship among these
detections as the detections are scattered among all quadrants of the disposal area
42 Groundwater Quality 421 Temporary Well Point Investigation
The results of the temporary well point investigation discussed in Section 24 indicated the
presence of a narrow groundwater plume (approximately 250 feet in width) of volatile organic
compounds (VOC) originating at the Former Primary Disposal Area and extending about 700 feet
in a northwesterly direction VOC were detected up to Mill Brook and at trace levels at one
location near the northern bank of the brook Plate 4-4 summarizes the VOC detections at
different locations and depths in the aquifer A summary of these field and laboratory data is
presented on Table 4-8 and Table 4-9 respectively The area extent of this VOC plume is in
excellent agreement with the groundwater flow directions measured in the northern Study Area (as
discussed in Section 422) The primary chlorinated VOC detected were 111-trichloroethane
(TCA) trichloroethene (TCE) and 12-dichloroethene (DCE) VOC concentrations within the
Former Primary Disposal Area were found to decrease significantly with depth indicating that the
source material is probably located near or above the water table Further downgradient VOC
were detected at generally lower concentrations and were present throughout the entire aquifer
thickness with no apparent depth-dependent trend Various contaminant transport mechanisms
are discussed in Section 50
In the southern portion of the Study Area low-level detections of methyl isobutyl ketone (MIBK)
were detected in samples from two microwells Also acetone and methylethyl ketone (MEK)
were detected at one location adjacent to Tarbox Road No other VOC were detected at any
location
Due to variability in the results of field VOC analyses (using a portable gas chromatograph) and
off-site laboratory analyses it was determined that the field GC results should not be relied upon
as the only source of information to evaluate either the VOC plume boundary or absolute levels of
particular constituents within the plume Rather the microwell results were subsequently used to
guide the location of monitoring wells and to evaluate relative horizontal and vertical
concentration variations within the VOC plume Water quality data from monitoring wells were
then used to confirm the microwell results and delineate plume boundaries
The results of laboratory metals analyses shown in Table 4-10 and Plate 4-5 do not indicate any
significant source areas on the Site nor are there any apparent trends in occurrence or
concentrations of metals Lead was detected at variable depths and concentrations at a total of 15
microwell locations (TW102 103 104 107 115 120 126 128 139 141 143 148 151 and
5797wpdoclaquogilluprifinaltextmlaquo8terrifhl061297 4-17 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
152) These locations represent nearly every portion of the study area With several exceptions
the majority of iiicrowell lead detections were trace to very low (ie lt 10 ugL) Exceptions
included results from single samples collected at locations TW120 (192 ugL) TW-128 (644
ugL) and TW151 (182 ugL) Although several of the locations at which lead was detected are
downgradient of former disposal areas most of the detections were at locations that are either
upgradient or a large distance (400 to 1000 feet) from former disposal areas Furthermore while
lead was detected at some downgradient locations there were other downgradient locations at
which lead was not detected at all It is also noted that lead was only detected at a concentration
of 1 ugL at the microwell (TW143) placed in the center of the Former Primary Disposal Area
and that lead was not detected at all in the two nearest downgradient (relative to the Former
Primary Disposal Area) microwell locations (TW119 and 137) Based on the lack of significant
detections of lead in most microwells on the Site and the fact that metals are typically much less
mobile than VOC the majority of these detections were not considered to be Site related and may
be attributed to an off-site source Numerous off-site activities may have resulted in lead
contaminations including most notably the observed presence of large lead-containing batteries
abandoned along the west side of the railroad bed and fire armhunting activities (as evidenced by
the large number of spent shotgun shell casings observed in the area)
422 Groundwater Monitoring Wells
The initial (Phase 1A) monitoring well network was designed to (1) confirm the findings of the
microwell survey with respect to the chlorinated VOC plume in the northern Study Area and the
two isolated MIBK detections in the southern Study Area and (2) provide hydraulic data to
determine groundwater flow directions and rates An additional objective of the network was to
evaluate potential bedrock groundwater issues related to the Former Seepage Bed which is
located in an area where the water table lies below the base of the overburden formation
Following the Phase 1A monitoring well installation and sampling program additional rounds of
groundwater samples were collected in April July November 1995 February May August
November 1996 and February 1997 under the Long-Term Monitoring Program In October
1995 additional wells were installed during the Phase IB field program to address groundwater
quality and flow directions from areas north of the site The newly installed monitoring wells
(MW117STT MW118STT MW119STT and MW102B) and the existing monitoring wells
located at the former Pervel flock plant (MW-A -B -C -2 and -3) were also included only in
the November 1995 round of groundwater sampling and were sampled only for VOC analyses
Further details of the monitoring well installation program are provided in Section 27 The
following sections present and discuss the groundwater sampling results for VOC SVOC metals
and pesticidesPCB for all nine rounds of sampling
5797wpdocsgalIuprifinaltextmlaquosteiTifhl061297 4-18 QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
4221 VOC
This section discusses the VOC data collected from groundwater monitoring wells during the nine
sampling events conducted between January 1995 and February 1997 Positive groundwater VOC
detections for the nine sampling events are shown in Tables 4-11 through 4-19 respectively VOC
data for the four 1995 events are presented graphically on Plate 4-6 and the VOC data for the
four 1996 events and the February 1997 event are presented on Plate 4-7
42211 Overburden
Northern Study Area
As shown in Plates 4-6 and 4-7 the monitoring well data for all nine sampling events generally
confirm the microwell survey results with regard to the distribution of VOC downgradient from
the Former Primary Disposal Area
The various VOC detected are grouped into chlorinated VOC (eg TCA TCE 11- and 12shy
DCE tetrachloroethene (PCE) 11-DCA 12-dichloropropane carbon tetrachloride methylene
chloride chloroform and vinyl chloride) and non-chlorinated VOC (eg ethyl benzene toluene
xylene benzene styrene and carbon disulfide) As shown in Plates 4-6 and 4-7 the distribution
of these compounds as reported for the November 1995 and February 1997 sample events
respectively has been used to delineate the horizontal boundaries of a VOC plume which
originates in the vicinity of the Former Primary Disposal Area The plume boundary as depicted
on Plates 4-6 and 4-7 is defined by the locations where any compound was detected in excess of
its respective EPA MCL during the November 1995 and February 1997 sampling rounds
Locations at which VOC were detected at levels greater than their respective MCL during at least one sampling round were MW101(STTT) MW102(STTB) MW105 (STTTB)
MW107(TT) and MW-C (located at the former Pervel flock plant facility) MW116T exceed the
MCL for PCE only and only on one occasion (January 1995 at 17 ppb) VOC in samples
collected from MW116T during the eight subsequent sampling events were all below their
respective MCL At MW101 the only compound which was detected in excess of its MCL was
PCE which was detected in the shallow well at a maximum concentration of 6 ppb in the top-ofshy
till well at concentrations ranging from 15 to 32 ppb and between 22 and 30 ppb in the till well
At MW102S compounds detected in excess of their MCLs were 11-DCE (between 3 and 19
ppb) 12-DCE (between 72 and 670 ppb) PCE (between 10 and 43 ppb) 111-TCA (one
exceedance in July 1995 at 240 ppb) TCE (between 15 and 88 ppb) and vinyl chloride (from not
detected to 86 ppb) At MW102TT compounds that exceeded their respective MCL were 11shy
DCE (from not detected to 35 ppb) 12-DCE (between 140 and 1300 ppb) PCE (above the
MCL during four of the sampling events up to 14 ppb) 111-TCA (one exceedance in August
5797wpdocsgalluprifinaltextmasterrifhl061297 4-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
1996 at 200 ppb) TCE (one exceedence in February 1997 at 7 ppb) and vinyl chloride (from not
detected to 430 ppb) MW102B and MW105S each had a one-time MCL exceedence for only
vinyl chloride both occurrences at 3 ppb (in May 1996 at MW102B and in August 1996 at
MW105S
At MW105TT six compounds have exceeded their respective MCL as follows 11-DCE (up to
32 ppb) 12-DCE (between 150 and 1100 ppb) PCE (up to 9 ppb) 111-TCA (between 37 and
390 ppb) TCE (two exceedences up to 14 ppb) and vinyl chloride (from not-detected to 710
ppb) MCL exceedences detected at MW105T are as follow 11-DCE (two exceedences both at
12 ppb) 12-DCE (between 43 and 430 ppb) 111-TCA (one exceedence 380 ppb in February
1996) TCE (one exceedence 27 ppb in November 1995) and vinyl chloride (from not detected
to 1400 ppb) The only compound that exceeded its respective MCL in MW105B is 12-DCE
(between 2 and 180 ppb) MW107TT has had MCL exceedence of the following three
compounds 11-DCE (from not detected to 16 ppb) 12-DCE (between 72 and 1100 ppb) and
vinyl chloride (between 120 and 430 ppb)
Although there is some variation in the distribution and concentration of VOC with each sample
event the plume defined by the November 1995 data set (as shown on Plate 4-6) is nearly
identical to the plume defined by the February 1997 data set (as shown on Plate 4-7) Further
discussion of VOC concentration variations with time is provided in Section 52
Typically VOC in wells located beyond the boundaries of the plume were detected at estimated
or trace to very-low concentrations and were not detected with any regularity VOC were
detected at low levels in at least two-thirds of the samples collected from the following wells
located beyond the boundaries of the plume MW103TT (12-DCE and PCE) MW108B 11shy
DCE PCE and TCA) MW116T (PCE and TCA) SW3S (12-DCE PCE and 11-DCA) and
SW3D (12-DCE TCA and 11-DCA) PCE was detected in excess of its MCL at location
MW116T (17 ppb) during the first sampling event (January 1995) but it was never detected
above 3J ppb in the eight subsequent sampling events
TCA and 12-DCE which were detected in wells at all three locations along the plume centerline
(ie MW107 MW105 and MW102) appear to be good tracers for assessing contaminant
migration away from the Former Primary Disposal Area Based on 1995 data these compounds
have been incorporated into contaminant travel-time analyses presented in Section 5 At locations
MW107 and MW105 the highest concentrations were measured in the top-of-till wells with only
low to trace levels in the shallow wells (TCA and 12-DCE concentration up to 130 ppb and
1100 ppb respectively in MW107TT and up to 390 ppb and 1100 ppb respectively in
MW105TT At location MW102 TCA and DCE were detected at similar concentrations (up to
5797wpdoc8galluprifinaltextmasterrifhl061297 4-20 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
240 and 1300 ppb respectively) in shallow and top-of-till wells For all sampling dates TCA
concentrations in the top-of-till wells along the plume centerline varied from 24 to 390 ppb and
12-DCE levels in the top-of-till wells along the plume centerline ranged from 72 to 1300 ppb
No significant reduction in TCA or 12-DCE concentrations with distance from the Former
Primary Disposal Area is apparent at locations MW107 MW105 and MW102
TCE 11-dichloroethane ethyl benzene benzene 11-DCE 12-dichloropropane PCE toluene
vinyl chloride and xylenes were also detected at each of the three plume centerline locations but
as shown in Plates 4-6 and 4-7 their concentration distributions were more sporadic and TCE
11-DCE PCE and vinyl chloride were the only compounds that exceed their respective MCL
during at least one sampling event TCE was found at concentrations up to 88 ppb (in well
MW102S) 11-DCE was found at concentrations up to 35 ppb (in well MW102TT) the
maximum PCE concentration was measured at 43 ppb (in well MW102S) and vinyl chloride was
measured as high as 1400 ppb (well MW105T) The second highest vinyl chloride value was
710 ppb (well MW105TT) and all other vinyl chloride measurements ranged from not-detected up
to 430 ppb
Wells located within the northern portion of the Site where VOC have never been detected include
MW106TT MW109B and MW110S
Based on the monitoring well and microwell results concentrations within the VOC plume appear
to be relatively evenly distributed throughout the lower three-quarters of the aquifer thickness
Throughout most of the plume area (eg MW107 MW105 and MW101) VOC levels in the
upper five to 15 feet of the aquifer are typically near the detection limit The concentration
reduction near the water table is likely associated with rainwater infiltration Evidence of
infiltration includes the consistently downward hydraulic gradients at MW107 MW108 and
MW116 At these locations the vertical hydraulic gradient is on the order of a factor of 100
greater than the horizontal hydraulic gradient within the VOC plume Location MW102 where
shallow and deep concentrations are similar in magnitude is an exception to this trend of low
concentration near the water table A plausible explanation for the observed concentrations in
MW102S is the hydraulic influence of Mill Brook which as discussed in Section 3323 causes
upward flow in the upper portion of the aquifer near the brook Upward flow near the brook and
MW102S is also supported by the upward hydraulic gradients measured between MW102S and
the stream piezometer PZ-4B
The present PCE distribution in groundwater exhibits inconsistencies with migration from the
Former Disposal Areas PCE was consistently detected at levels above the 5 ppb MCL up to 43
ppb in groundwater samples from wells MW102S MW101TT and MW101T PCE was
5797wpdocraquogalluprifinaltextmasterrifhl061297 4-21 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
measured in well MW116T at 17 ppb in the initial sampling round (January 1995) and
consistently at trace levels in subsequent sampling rounds However only trace levels of PCE
were detected at the MW105 or MW107 locations and the only occurrences of PCE at MW105
or MW107 greater than 5 ppb were three estimated detections of 6 7 and 9 ppb at MW105TT
PCE was not detected in well SW3S and was detected once at a trace level in well SW3D
Monitoring wells MW102 and MW101 are downgradient from both the Former Disposal Areas
and the former Pervel flock plant where PCE TCA and DCE groundwater contamination has
been documented (Section 52) During the November 1995 sampling event VOC detected at
MW-C (located at the former Pervel flock plant) include DCE (97 ppb) TCE (11 ppb) and PCE
(24 ppb) Based on available data MW116 is located downgradient from the former Pervel
flock plant Groundwater flow conditions in the past would need to have been different from
present conditions for MW116 to be downgradient from the Former Disposal Areas Although
the PCE detections at locations MW102 and MW101 could be attributable to historical releases
from the Former Disposal Areas the regional flow pattern and spatial distribution of PCE in
groundwater suggest that contamination from the former Pervel facility has at a minimum
contributed to VOC (PCE TCA and DCE) contamination of these locations Further discussion
of the PCE detections and other VOC concentration variations is provided in Section 52
Southern Study Area
In the southern portion of the Study Area groundwater samples were collected from overburden
monitoring wells at five locations SW9 MW112 MW113 MW114 and MW115 As shown
on Plates 4-6 4-7 no VOC were detected in any of the wells As a result of the consistent lack of
detections wells at these locations were dropped from the Long-Term Monitoring Program (with
EPA approval) after three sampling events These data are consistent with the microwell survey
results but do not support the low-level detections of methyl isobutyl ketone in the two microwell
samples (Section 421)
42212 Bedrock
During the RI VOC were detected in bedrock wells at the following locations MW102 MW105
MW107 MW108 and SW-10 Since the only VOC detected at SW-10 was TCA at an estimated
trace concentration (1J ppb) during the January event and TCA was not detected in SW-10
during the subsequent two sampling events this well was eventually dropped from the Long Term
Monitoring Program (with EPA approval) following the July event All other bedrock wells in
the southern portion of the Study Area (MW111 MW112 MW113 SW-12) were likewise
dropped from the monitoring program At location MW108B estimated concentrations of PCE
(3J ppb) and TCA (up to 9J ppb) were detected during the January and April sampling events
therefore samples collected from this well during the July and November events were submitted
5797wpdocsgalluprifinaltextmasterriftil061297 4-22 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
for VOC analyses using EPA Method 5242 which hs lower detection limits than the TCL
Methods The results of the July and November events for MW108B indicate that other VOC are
present but generally at trace to very low concentrations The highest detections of TCA and
PCE at this location were 92 and an estimated 5 ppb respectively Other VOC detected at
MW108 were carbon tetrachloride (12 ppb) 11-DCA (1 ppb) 12-DCA (015J ppb) 11-DCE
(13 ppb) and xylene (01J ppb)
The only VOC detected at MW107B was TCA which was measured during three events at
concentrations ranging between 059J and 2 ppb Over the nine sampling events VOC detected
at MW105B included 11-DCA (BDL to 9J ppb) 11-DCE (BDL-4J ppb) 12-DCE (11-140J
ppb) 12-dichloropropane (2J ppb in January 1995 and February 1996 only) TCA (2J-12 ppb)
and TCE (BDL-3J ppb)
MW102B was installed during the Phase IB investigation and therefore was only sampled during
five events VOC detected at MW102B were typically at estimated trace concentrations and
only PCE was detected in every round (2J to 4J ppb) The only MCL exceedence was a single
estimated detection of vinyl chloride (3J ppb)
In general VOC detected in bedrock wells were also detected in overburden wells at the same
locations although the concentrations seen in the bedrock wells are significantly lower typically
by an order of magnitude relative to concentrations seen in the top-of-till wells The only
notable exception to this trend is at location MW108 where VOC were not typically detected in
the overburden wells (with the exception of an estimated 2J ppb of DCE detected once in
MW108S and once in MW108TT) At MW105 and MW107 VOC concentrations seen in the till
wells are similar to the low concentrations detected in wells screened in the underlying bedrock
The low VOC levels detected in bedrock wells located in the northern portion of the Study Area
demonstrate that bedrock is not a preferred pathway for contaminant migration This conclusion
is supported by the groundwater hydraulics data outlined in Section 3323 which demonstrate
that the average hydraulic conductivity of the bedrock is more than a factor of 200 less than the
overburden hydraulic conductivity In spite of the upward hydraulic gradient from bedrock to
overburden (factor of ten to 100 larger than the horizontal hydraulic gradient within the VOC
plume) which was found to exist throughout the Study Area vertical (transverse) dispersion
caused by flow in the bedrock fracture system has apparently caused VOC to migrate a limited
distance into the bedrock
5797wpdocsgalIuprifinaltextmasterrifhl061297 4-23 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4222 Semivolatile Organic Compounds
Tables 4-20 through 4-28 present the analytical results for SVOC in groundwater for the nine
sampling events Overall SVOC were detected infrequently and generally at only trace levels
Naphthalene 2-methylphenol and 12-dichlorobenzene were the most frequently detected SVOC
compounds in groundwater samples Naphthalene was detected during every sampling event
generally at MW105 MW107 and MW102 locations within the top-of-till wells and occasionally
also within till at well MW105T The highest naphthalene measurement was 10 ppb in
MW105TT 2-methylphenol was also detected during every sampling event always in well
MW107TT and with lesser frequency in MW105TT MW105T and MW102TT the highest
concentration detected was 3 ppb In eight of the nine sampling events 12-dichlorobenzene was
detected in at least one of the following wells MW102TT MW105TT MW105T MW107TT
and the maximum concentration measured was 4 ppb Maximum bis(2-ethylhexyl)phthalate was
detected in at least one well during six of the nine sampling events the concentrations ranged
from 04J to 35 ppb The locations of the bis(2-ethylhexyl)phthalate detections were sporadic it
was detected three times at MW108S twice at MW014S and MW116T and only once at eleven
wellsTrace levels of the following other compounds were detected during various sampling
events acenaphthene (03J ppb) butylbenzylphthlate (U ppb) di-n-butylphthlate (04J ppb) 4shy
chloroaniline (2J ppb) 24-dichlorophenol (U ppb) fluorene (06J ppb) 4-chloro-3-methylphenol
(2J ppb) phenanthrene (02J ppb) 4-bromophenyl-phenylether (2J ppb) n-nitroso-di-nshy
propylamine (9J ppb) 14-dichlorobenzene (up to 2J ppb) diethylphthlate (up to 04J ppb) 24shy
dimethylphenol (up to 8J ppb) di-n-octylphthlate (up to 46B ppb) 4 methylphenol (2J ppb) and
phenol (up to 4J ppb) The majority of these compounds occur in either the till or top-of-till
wells located within the VOC plume shown on Plates 4-6 and 4-7 (eg MW102 MW105 and
MW107) although there were infrequent detections of compounds at MW103 MW104 MW106
MW108 MW109 SW3D MW112 and MW116 as well
4223 Pesticides and PCB
The only detection of PCB in groundwater was during the April event when Aroclor 1242 was
detected in MW103S and TT at estimated concentrations of 042J and 018J ppb respectively
Estimated low levels of a few pesticides were detected in a small number of groundwater samples
Endosulfan I was detected once (002J ppb in MW107S during April 1995) Endrin was detected
once (00031 JP in MW109S during February 1996) methoxychlor was detected once (012J in
MW107S during February 1997) alpha-BHC was detected once in four wells (during February
1997 up to 0011 JP ppb) beta-BHC was detected twice up to 004J ppb (at MW107S in July
1995 and at MW107TT in February 1996) and gamma-BHC was detected in three samples up to
001JP (at MW105B and MW116S during November 1995 and at MW102S during August 1996)
All positive detections for pesticide and PCB compounds are shown on Table 4-29 (Note Table
5797wpdocraquogalluprifinflltextmasterriftil061297 4-24 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
4-29 only includes those sample IDs where a pesticide or PCB compound has ever been detected)
4224 Inorganics
Tables 4-30 through 4-38 present the analytical results for total (and where applicable dissolved)
metals in groundwater (During sampling low flow purging techniques were used to minimize
disturbance of formation water In cases where turbidity levels less than 5 NTU could be
achieved samples for both total and dissolved metals were collected Otherwise samples were submitted for total metals analyses only) Cyanide has not been detected in any groundwater
sample Metals were generally not detected in groundwater above applicable MCLs and metals
in groundwater samples across the Study Area were similar in concentration to metals detected in
designated groundwater background samples
Analytical results of a duplicate sample collected from MW107S during August 1996 had
anomalously high values Between January 1995 and August 1996 nine samples (seven rounds
plus two duplicate samples) were collected from this well and analyzed for total metals Only one
sample contained inorganic compounds in excess of EPA MCLs or Connecticut Remediation
Standards This sample which was the duplicate sample collected in August 1996 contained
elevated concentrations of aluminum chromium cobalt magnesium manganese and nickel In
order to evaluate the significance of this particular data set a statistical analysis for the
identification of outliers was performed following the procedures described in the EPA guidance
document Statistical Analysis of Ground Water Monitoring Data at RCRA Facilities (EPA530shy
SW089-026) For this analysis a test statistic (TJ was generated (using the average maximum
and standard deviation) from the nine samples for each inorganic analyte detected in this well If
the test statistic was greater than a critical value (1764) representing a 995 level of
significance then there is a strong likelihood that the maximum value for each data set is a statistical outlier If a given analyte was not detected in a given sample the detection limit2 was
used for statistical calculations
Maximum concentrations for nine of the thirteen analytes that have been detected in this well
were found to be statistical outliers Six of the statistical outliers were found in the MW107S
duplicate sample collected in August 1996 which suggests that the inorganic data from this
particular sample are not representative of groundwater quality in the immediate vicinity of this
well Although a specific reason why this sample contained such anomalously high levels is not
apparent it seems clear that this sample is not representative of the actual groundwater metal
concentrations at this location This is supported by the fact that the other sample from this well
on this date has metals concentrations consistent with previous sampling rounds Therefore the
metals data from this duplicate sample have been presented in this Report but are considered not
to be valid
5797wpdocBgalluprifinaltextmasterrifhl061297 4-25 QSTT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4225 DioxinsFurans and Additional Appendix IX Parameters
During the January 1995 sampling event samples from three locations (MW102TT MW106TT
and MW116T) were submitted for laboratory analysis for full Appendix IX parameters During
the April 1995 sampling event samples from MW105TT were also submitted for full Appendix IX
analyses The results for the VOC SVOC PesticidePCB and metals analyses for these samples
have been included in the appropriate tables as discussed in previous sections The results of
Appendix IX analyses that are not common to target analyte and target compound lists
(TALTCL) are discussed below Analyte groups specific to the Appendix IX lists include
herbicides (EPA Method 8150) volatiles by direct aqueous injection (EPA method modified
8015) Phenols (EPA Method 4202) Sulfide (EPA Method 3761) Organophosphorus Pesticides
(EPA Method 8141) PesticidesPCB by EPA Method 8080 and DioxinsFurans
The only detections for any of the analyte classes specific to Appendix IX compounds during the
January 1995 event were phenols (MW102TT at 7 ppb and MW116T at 15J ppb) During the
April 1995 event the dioxinfuran compounds HxCDD (total) and TCDF (total) were detected at
MW105TT at concentrations of 705 and 193 ngL (part per trillion)
423 Residential Wells
Residential wells were sampled during the Phase 1A investigation (January 1995) and again
during July 1995 February 1996 and August 1996 under the Long-Term Monitoring Program
4231 Volatile Organic Compounds
Tables 4-39 through 4-42 present the results of VOC analyses for residential well samples The
locations of these wells are shown on Plate 2-5 TCA was detected at DW114 during all four
sampling events and was also detected once at DW111 and DW113 the concentration ranged
from 018J to 066 ppb Chloroform was detected during three of the sampling events twice at
DW102 and once at DW104 and DW107 the maximum concentration detected was 19 ppb The
following compounds were also detected at low levels once bromodichloromethane (2 ppb at
DW107) dibromochloromethane (084J ppb) PCE (016J ppb at DW114) chloromethane (082J
ppb at DW103) and at DW111 ethylbenzene (025J ppb) toluene (012J ppb) and xylenes
(0 U) Since these locations are not downgradient with respect to the Site the occurrence of
these compounds in these wells are not likely to be Site related
4232 Semivolatile Organic Compounds
No SVOC were detected in any residential well sample during any of the four sampling events
5797wpdocsgalIuprifinaltextmasterrifhl061297 4-26 QT Environmental
Gallups Quarry Superjund Project - Remedial Investigation
4233 Pesticides and PCS
Tables 4-43 through 4-46 present the analytical results of pesticide and PCB analyses for
residential well samples Alpha-chlordane and gamma-chlordane were both detected in all four samples collected from DW105 and in three of the samples collected from DW106 The
maximum concentrations measured were 0095 ppb for alph-chlordane and 004 ppb for gamma-chlordane During August 1996 44-DDE and heptachlor epoxide were both also detected at
DW105 and DW106 (001J ppb for 44-DCE and up to 002J ppb for heptachlor epoxideNo PCB compounds were detected in any residential well The fact that DW105 and DW106 are not
downgradient relative to the site indicate that these compounds are likely attributable to the off-site use of these pesticides and are not site-related
4234 Inorganics
Tables 4-47 through 4-50 present the analytical results of metals and cyanide analyses for
residential well samples for the four sampling events Heavy metals were generally not detected
or were detected at trace levels Alkaline earth metals (eg Ca Mg K) were detected at levels
not unexpected for natural groundwater in the region
43 Surface Water Sediment and Wetland Soils Surface water sediment and wetland soils upstream adjacent to and downstream of the Site
were sampled and analyzed during the Phase 1A investigation to assess the potential if any for
transport of constituents of concern from the Site Sample locations are shown on Plate 2-6 Sediment was collected from one additional location (UB-6A) during the April 1995 sampling round As part of the Long Term Monitoring Program additional rounds of surface water
samples were collected during the April and November 1995 and May and November 1996
sampling events The samples were analyzed for VOC SVOC metalscyanide and pesticidePCB with the exception of the November 1996 samples which with EPA approval
were analyzed only for VOC and metals It is noted that following the Phase 1A sampling event
(September 1994) stations UB-1 UB-2 and UB-3 were eliminated from the Long Term
Monitoring Program (with EPA approval) as these locations are upstream of station UB-4 which
is also upstream from the Site Also station UB-6 (which was located on a tributary to Mill
Brook and sampled during the Phase 1A program) was replaced by station UB-6A (located within
Mill Brook) during the four Long-Term Monitoring events
431 Surface Water During September 1994 water quality indicators (pH dissolved oxygen temperature
conductivity turbidity) were measured in the field at eleven surface water sampling stations six
in Upper Mill Brook two in Lower Mill Brook (below the confluence with Fry Brook) one in
Fry Brook and two in Packers Pond The remaining six locations were dry at the time of
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 4-27 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
sampling As presented in Table 4-51 the water quality of the watershed as judged by both field
measurements and wet chemistry (TSS alkalinity hardness) was good to excellent It may
however be important to note that all of the samples were taken under fair weather conditions so
the influence of potential non-point sources during storm events cannot be assessed with this data
set Table 4-51 presents a qualitative assessment (eg slight moderate obvious) of potential
Local Non-Point Source Pollution As most sampling stations are either adjacent to or
downstream from developed (eg streets highways residences agricultural or industrial
property) the immediate andor cumulative impact of storm events cannot be evaluated in this
report During the four Long-Term Monitoring surface water sampling events field parameters
were again measured The results of these sampling events are shown in Table 4-52
During the September 1994 Phase 1A investigation surface water temperature ranged from 60 degF
(UB1 UB2) to 70degF (PP3) Surface water at most locations contained adequate concentrations of
dissolved oxygen ranging from 335 (UB2) to 1035 (UB8) mg1 but were slightly acidic with
pH varying from 528 (UB1) to 572 (PP3) Dissolved solids measured indirectly as specific
conductivity varied from 120 (UB1) to 710 (PP3) imhoscm
During the four Long-Term Monitoring sampling events surface water temperatures ranged from
526 to 617degF in April 1995 and 420 to 508degF in May 1996 to seasonally lower temperatures
of 396 to 453degF in November 1995 and 374 to 400degF in November 1996 The dissolved
oxygen concentrations were generally similar between the various sampling events ranging from
a low of 335 mg1 (at UB-2 in September 1994) to a high of 1030 mg1 (at PP-1 in November
1996) pH measurements indicated slightly acidic water with the following ranges 514 to 605
in April 1995 574 to 667 in November 1995 615 to 701 in May 1996 and 472 to 620 in
November 1996 Conductivity values were in the same general range between the different
sampling events with the lowest measurement of 1 anhoscm at PP-1 in November 1996 and the
highest measurement of 523 xmhoscm at UB-5 in April 1995
Based on laboratory results surface water in the area is fairly soft ranging in hardness (as
CaCO3) from 12 (TR-1 during April 1995) to 179 (UB2 during September 1994) mg1 and in
alkalinity from lt 1 (UBS during April 1995) to 67 (UB2 during September 1994) mg1 Total
dissolved solids and total organic carbon were below 200 ppm and 15 ppm respectively at nearly
every station during all five sample events A total of 58 total suspended solids analyses were
performed on samples collected during the five sampling events Most of the results were below
the detection limit and only 10 samples exceeded 10 mg1 The highest concentrations were
detected at UB-5 (between 82 and 2470 mg1 in the four samples collected at that location) and at
PP-1 (between 87 and 1500 mg1 in the three samples collected at that location)
5797wpdocraquogalluprifinaltextmasterrifhl061297 4-28 QST Environmental
Gallups Quarry Supcrjund Project - Remedial Investigation
4311 VOC- Surface Water
Data presenting he concentrations of various VOC for each individual surface water location are
presented in Table 4-53 through 4-57 for the September 1994 April and November 1995 and
May and November 1996 sampling events respectively VOC were not detected in the upstream
portion of Mill Brook Six VOC were detected at least once in the five rounds of surface water
samples collected from 11 locations The most consistent detections were 12-DCE and PCE in
Fry Brook sample FB-1 12-DCE was detected every round at FB-1 and occasionally at four
other locations up to 8J ppb and PCE was detected every round at FB-1 and occasionally at
three other locations up to 11 ppb Sample location FB-1 is approximately 1500 feet upstream
of the confluence of Fry Brook and Mill Brook the detections at FB-1 are not likely to be Site-
related and may result from nearby industrial activities The other detections of PCE and DCE
were at trace concentrations at locations below the confluence of Fry and Mill Brooks In
addition TCA was detected once at UB-10 at 3J ppb TCE was detected twice at FB-1 and once
at UB-9 up to 2 ppb carbon disulfide was detected in seven samples representing six locations
up to 20 ppb and toluene was detected twice at upgradient location UB-5 at 1J ppb All of the
VOC concentrations detected are well below those expected to cause adverse effects in fish or
wildlife (USEPA 1986)
4312 SVOC - Surface Water
During the September 1994 sampling event only low levels of one SVOC compound 4shy
methylphenol (28 ppb PP3 1 ppb UB2) were detected in surface water samples The locations
where SVOC were detected are far upstream (UB 2) and downstream (Packer Pond) locations and
are unlikely to have been impacted by the Site During the April 1995 sampling event the only
SVOC detected were trace levels of fluoranthene (04J ppb) phenanthrene (03J ppb) and pyrene
(04J ppb) all of which were detected at UB-5 which is upstream from the site There were no
SVOC detected in any surface water samples during the November 1995 event During the May
1996 sampling event bis(2-ethylhexyl)phthalate was detected in four samples at concentrations
ranging from 05J ppb to 140J ppb The locations of the detections are upgradient of the Site
(UB-5 and UB-8) and downgradient of the Site (LB-2 and PP-1) The sample from LB-2 also had
an estimated low level of di-n-octylphthalate (7J ppb) Table 4-58 presents all of the SVOc
detections in surface water samples (Note Table 4-58 only includes those sample IDs where a
SVOC has ever been detected)
4313 PesticidesPCBs - Surface Water
No pesticides or PCB compounds were detected in any surface water samples
5797wpdocsgalluprifinaltextmraquosterrifhl061297 4-29 Q5T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4314 Total and Dissolved Metals - Surface Water
Because of the ubiquity of naturally occurring metals in surface waters metals results are more
easily interpreted by generating descriptive statistics Descriptive statistics for metals measured in
surface water during 1994 and 1995 are presented in Appendix S Data presenting total and
dissolved metals concentrations for each individual sampling location during all five sampling
events are presented in Tables 4-59 through 4-65
Total Metals
Cadmium silver and thallium were not detected in any samples during the five sampling events
Other constituents detected in only one or two samples during each event include arsenic (up to
296J ppb) beryllium (once at 26B ppb) chromium (up to 764 ppb) cobalt (up to 26 IB ppb)
copper (up to 165 ppb) cyanide (up to 466 ppb) mercury (once at 018B ppb) nickel (up to
821 ppb) selenium (181J ppb at PP3) silver (once at 3J ppb) and vanadium (133 ppb) With
die exception of station UB2 during the September 1994 sampling event UB-5 during die April
1995 May 1996 and November 1996 events and PP-1 during the May and November 1996 events the remaining metals (aluminum barium calcium iron lead magnesium manganese
potassium sodium and zinc) were detected at concentrations that are expected in natural waters
(Hem 1989)
Dissolved Metals
Beryllium cadmium cobalt mercury selenium and thallium were not detected in any sample
Constituents detected infrequently and at low concentrations include antimony arsenic
chromium nickel silver vanadium and zinc Copper was detected at several locations upstream
and downstream from the site at concentrations ranging from 25 to 208B ppb although there
was no pattern in its occurrence or concentration Lead was detected at least once at each of the
sampling locations ranging in concentration from 1J ppb to 188 ppb The occurrences of lead
did not show a pattern die highest measurements were as follows 11 ppb at PP-3 in September
1994 188 ppb at UB-9 in April 1995 16J ppb at UB-4 in November 1995 56J ppb at UB-5 in
May 1996 and 91J ppb at UB-5 in November 1996 Locations UB-4 and UB-5 are upgradient
of the Site The lead detections in Packer Pond samples likely results from non-point sources to
Packers Pond The remaining metals (aluminum barium calcium copper iron lead
magnesium manganese potassium and sodium) were detected at concentrations that are expected
in natural waters (Hem 1989)
Concentrations of total and dissolved metals in surface waters were generally detected infrequently
and at concentrations below ambient water quality criteria ie those that would not pose a threat
5797wpdocsgalluprifinraquoItextmaBterriftil061297 4-30 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
to fish or wildlife (EPA 1986) Heavy metals such as copper and lead generally considered
harmful to aquatic life were detected at locations (Fry Brook and Packers Pond) that are not
likely to be impacted by the Site One location UB-5 (which was dry during September 1994)
contained elevated levels of most metals during the 1995 and 1996 sampling events This sample
station is located well upstream from the site on a tributary to Mill Brook which originates in a
small pond adjacent to Interstate 395 in a highly commercialized area
432 Sediment
A total of seventeen sediment samples were collected during the Phase 1A field survey
(September 1994) six of which were dry at the time The composition of the sediment samples
varied from deep muck (eg LB-02) to a firm sandy substrate (eg UBS) The total organic
carbon (TOC) content of the sediments (presented in Table 4-30) ranged from 075 (UB4) to 16
(PP1) percent with an average of 57 percent
4321 Inorganics - Sediment
Because of the ubiquity of naturally occurring metals in sediment these constituents are more
easily interpreted by generating descriptive statistics which are presented for each individual
metal in Appendix S Data presented for metals at each individual sampling location are
presented in Table 4-66
Antimony and thallium were not detected above the detection limit Beryllium cadmium
chromium cyanide mercury selenium and silver were detected infrequently and when detected
had concentrations close to the respective detection limit andor were detected at remote upstream
or downstream locations With the exception of maximum concentrations detected at PP3 (a
location at Packer Pond which receives stormwater runoff from Lillibridge Road) the remaining metals (aluminum arsenic barium calcium cobalt copper iron lead magnesium manganese
nickel potassium sodium vanadium and zinc) were detected at concentrations within the ranges
expected in naturally occurring soils or sediments (Beyer 1990 Fitchko 1989 Shacklette and
Boerngen 1984)
4322 VOC - Sediment
Analytical results for concentrations of VOC in sediment samples are presented in Table 4-41
VOC were generally detected infrequently and at relatively low concentrations in sediments
Ketones (acetone and 2-butanone) were detected at remote upstream (UB1 UB6) and downstream
(PP1 PP2 PP3) locations One or more of the compounds toluene trichloroethene methylene
chloride and xylenes were detected at trace levels at upstream locations north and east of the Site
(UB-3 UB-5 UB-6 UB-7 and UB-9) Xylenes were detected at a concentration of 31 pm in the
sediment sample from Fry Brook (FB-1) Only toluene at trace level of 0009J ppm was
5797wpdocsgalluprifinaltextma8terrifhl061297 4-31 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
detected in the sediment sample from UB-10 located in Mill Brook near the downgradient edge
of the Gallups plume No VOC were detected in sediment samples from downstream locations
LB-1 and LB-2
4323 SVOC - Sediment
As shown on Table 4-68 the primary SVOC constituents detected were PAH ranging from non-
detect (~ 03 ppm) to 15 ppm No apparent concentration gradient could be determined with
respect to location (eg upstream to downstream) The detections of PAH likely reflect non-
point contributions from local sources such as stormwater runoff from the railroad tracks and
nearby roads
Elevated concentrations of bis(2-ethylhexyl)phthalate were measured in Fry Brook (1300 ppm
FBI) and lower Mill Brook (64 ppm LB2) below the confluence of these two streams The
source appears to originate in Fry Brook
4324 PesticidesPCB - Sediment
Analytical results for pesticides and PCB are provided on Table 4-69 PCB compounds
(Arochlor-1242 -1254 and -1260) were detected in sediment samples from only three locations
all upstream (FB-1 at 019 ppm UB-8 at 0023J ppm and UB-7 at 00064J ppm)
Organochlorine pesticide compounds were also detected infrequently with no apparent trend with
regard to location or source The concentrations in sediment ranged from non-detect (~ 1-3 ppb)
to 39 ppb (methoxychlor at PP1) and their occurrence likely reflects residues of persistent
compounds that were routinely used for insect control before being banned from commercial
production
433 Wetland Soils
A total of 10 wetland soil samples were collected during the field survey most of which were
close to the water table at the time of collection The wetland sampling locations are shown on
Plates 2-6 and 3-14 The total organic carbon content (mgkg) of the wetland soils is as follows
QW1 (160000) QW2 (54600) QW3 (37200) QW4 (35200) QW5 (23900) QW6 (25600)
QW7 (gt 160000) QW8 (gt 160000) QW9 (33600) and QW10 (42600)
4331 Inorganics - Wetland Soils
Because of the ubiquity of naturally-occurring metals in wetland soils these constituents are more
easily interpreted by generating descriptive statistics which are presented for each individual
metal in Appendix S Analytical results for metals at each individual sampling location are
presented in Table 4-66
5797wpdocsgalluprifinaltextmasterrifhl061297 4-32 QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
Cadmium and cyanide were not detected in any sample Antimony arsenic beryllium cobalt
mercury selenium silver and thallium were detected infrequently and at trace levels at or below
the detection limit None of the remaining metals (aluminum barium calcium chromium
copper iron lead magnesium manganese nickel potassium sodium vanadium and zinc)
exceeded normal ranges expected for naturally occurring soils (Beyer 1990 Fitchko 1989
Shacklette and Boerngen 1984)
4332 VOC - Wetland Soils
Analytical results for VOC in wetland soils are provided on Table 4-67 VOC including acetone
2-butanone TCE and carbon disulfide were detected infrequently and at low concentrations
Acetone concentrations ranged from non-detect to 056 ppm (QW8) and 2-butanone concentrations
ranged from 0004 ppm (QW10) to 0067 ppm (QW8) QW8 is located in a remote wooded
location approximately 2000 feet west of the Site QW10 is located a few hundred feet west of
the southern portion of the Site
Acetone and 2-butanone were also detected at lower concentrations (015 and 0033 ppm
respectively) at location QW-1 several hundred feet southeast of the Former Primary Disposal Area A trace level of TCE (0004J ppm) was detected in wetlands soil sample QW-2 collected
approximately 50 feet east of the Former Primary Disposal Area This detection may be related
to the Former Primary Disposal Area since TCE has been detected in this area Based on the
topography however surface water runoff from the former disposal area is unlikely to impact the
wetland No other wetland soil samples had concentrations detected above the instrument
detection limit
Although the source of these VOC is unknown acetone 2-butanone and carbon disulfide are all
commonly used in the laboratory and may have been introduced during post-processing sampling
Some of these compounds are organic solvents that are (or were ) commonly used in many
household (eg spot removers paint strippers aerosols) commercial (eg pesticide
formulations inks and dyes) and industrial (eg degreasers) products Their presence in
wetlands soils samples at low concentrations may be the result of localized human activity in the
area
4333 SVOC - Wetland Soils
Analytical results for SVOC in wetland soils are provided on Table 4-68 The primary
constituents detected were the phthalate esters and PAH PAH were detected infrequently at
generally below 01 ppm Phthalate esters were also detected infrequently ranging from non-
detect to 22 ppm (QW8) The presence of these compounds is likely to be associated with
periodic or seasonal flooding of wetlands as the wetland sampling locations are remote and
5797wpdocsgpluprifinaltextma8terrifhl061297 4-33 QST Environmental
Gallups Quarry Superjimd Project - Remedial Investigation
generally inaccessible except on foot Since these compounds are relatively immobile except in
surface water or as airborne particulates these compounds may have originated from non-point
sources such as the railroad line or runoff from nearby highways
4334 PesticidesPCB - Wetland Soils
Analytical results for pesticides and PCB are provided on Table 4-69 PCB compounds
(Arochlor-1242 -1254 and -1260) were detected infrequently and at low concentrations
The presence of trace levels of PCB compounds in wetland soil samples QW-1 QW-2 QW-3
and QW-4 may be Site-related however PCBs are ubiquitous environmental contaminants that
were widely used in industry and may thus be present in soils as a result of past activities at
surrounding industries Other sources of input into the local environment might include
atmospheric deposition transport from upstream sources and deposition following flood events
Organochlorine pesticide compounds were also detected infrequently with no apparent trend with
regard to location or source The concentrations in wetland soils ranged from non-detect to 0016
ppm (44-DDE at QW1) and their occurrence likely reflects residues of persistent compounds
that were routinely used for insect control before being banned from commercial production
44 Air Quality 441 Baseline Air Quality Survey
Ambient air quality was determined prior to the start of Phase 1A intrusive investigations to
establish a baseline for air quality For the baseline survey air quality in the breathing zone
(between approximately three and six feet above the ground surface) was determined based on
measurements of total VOC (using a PID equipped with an 117 eV lamp) and respirable dust
(using a aerosol meter) at eight locations across the Site These eight stations were located at
each of the three known Former Disposal Areas and at upwind and downwind locations along the
perimeter of the Site The locations of the eight baseline air monitoring stations (AM1-AM8) are
shown on Plate 2-1 During the baseline survey no VOC readings were detected above the EPA
approved action level of 1 ppm at any of the eight monitoring locations Also no respirable dust
readings greater than the EPA-approved action level of 005 mgm3 were recorded during the
baseline survey at any of the monitoring stations
442 Perimeter Air Monitoring
Throughout the duration of the Phase 1A field investigations ambient air quality was monitored
on a weekly basis at the eight stations for the same parameters described above In addition to
the eight air monitoring stations continuous air monitoring was performed at each discrete
investigation area (eg each microwell soil boring etc) in the workers breathing zone and at the
5797wpdocsgaIIuprifinaltextmasterrifhl061297 4-34 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
perimeter of each task specific exclusion zone Air monitoring in the work zones was augmented
with instruments to measure hydrogen cyanide and lower explosion levels Also compound
specific calorimetric equipment (eg Draeger tubes) were used to compliment total VOC
measurements recorded with a PID
No readings above ihe EPA-approved action levels were recorded at the perimeter of the Site
throughout the entire duration of the Phase 1A investigation Elevated worker breathing zone
readings for total VOC were recorded during two of the four soil borings performed within the
Former Primary Disposal Area (SB109 and SB110) Varying but sustained elevated VOC
readings in the workers breathing zone during these two soil borings required the use of OSHA
Level C protection equipment These VOC vapors appeared to dissipate rapidly as no elevated
readings were recorded at the downward perimeter of the exclusion zone
Based on the baseline and periodic air monitoring performed during the investigation undisturbed
ambient air quality in the vicinity of the Site does not appear to have been impacted by former
disposal practices at the Site To confirm this compound specific air monitoring was performed
during the Phase IB investigation
As part of the Phase IB investigation quantitative air monitoring was performed in the vicinity of
the Former Primary Disposal Area The following compounds were detected in shallow soil
during the Phase 1A investigation and therefore were the target analytes for the air monitoring
performed during the Phase IB investigation toluene ethyl benzene total xylenes
tetrachloroethene and PCBs Data from the Phase IB investigation indicate that none of these
compounds were present at any of the air sampling locations for the duration (approximately eight
hours) of the sampling event The laboratory results of these analyses are presented in Appendix
T
45 Potential Sensitive Human Receptors The survey was used to identify any water supply wells schools nursing homes and day care
facilities including in-home day cares within a one-mile radius of the Site
Water Supplies
There are three community water companies serving portions of the Plainfield area within a one-
mile radius of the Site the Gallup Water Company Brookside Water Company and Glen Acres
Water Company The Gallup Water Company operates two wells located in downtown
Plainfield approximately 4000 feet north of the Site The Gallup Water Company presently
services approximately 700 households and three schools (Plainfield Middle School Plainfield
5797wpdocsgalluprifinaltextmlaquoraquoterriltinl061297 4-35 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Central and St Johns) The Brookside Water Company operates two wells located east of 1-395
on the corner of Dow Road and Colonial Road approximately 4000 feet northeast of the Site
The Brookside Water Company presently services approximately 225 homes The water service
lines for the Gallup and Brookside Water Companies are interconnected allowing mixing of the
waters The Glen Acres Water Company has two wells located approximately 2200 feet west of
the Site and services approximately 36 homes The majority of the area west south and east of
the Site and some properties north of the Site rely on individual private wells for their water
supply
One school is located within a one-mile radius of the Site This is the St John Building located
approximately 5200 feet north of the Site This school served students in grades Kindergarten
through eighth grade until 1995 after which the school operates only as a pre-school This
facility is serviced by the Gallup Water Company
Nursing Homes and Elderly Housing
One nursing home and one elderly housing facility are located within one mile of the Site The
Villa Maria Convalescent Home is located approximately 5000 feet north of the Site and is
served by the Gallup Water Company Lawton House Elderly Housing Apartments is located
approximately 4800 feet north of the Site and is also served by the Gallup Water Company
Day Care Facilities
There are eight in-home child day care facilities within a one-mile radius of the Site The
operators and locations are listed on Table 4-70 Only one of these facilities is serviced by a
private supply well That facility located at 134 Lathrop Road is located approximately 3500
feet southeast (upgradient) of the Site
5797wpdoc8galluprifinaltextmasterrifnl061297 4-36 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
50 Contaminant Fate and Transport
This section discusses the environmental fate and transport parameters associated with the
compounds detected during the Remedial Investigation Section 51 details the theoretical basis
for the evaluation of fate and transport characteristics In Section 52 Site-specific fate and
transport parameter values are presented and VOC migration rates and concentration variations
are discussed
51 Theory Migration persistence and relative distribution of compounds between air water and soil depend
on both hydrogeologic and compound-specific parameters The following discussion addresses
each of these parameters as they may affect behavior of compounds within the Study Area
511 Advection by Groundwater Flow
Within a porous medium (soil) the advection rate of dissolved or aqueous-phase compounds
under transient conditions is based on Darcys law (Bear 1979)
where
v= average pore velocity (lengthtime)
K= hydraulic conductivity (lengthtime)
i= hydraulic gradient (lengthlength or dimensionless) which equals
the piezometric head difference between two points on a
groundwater pathline divided by the distance between the two
points
n= effective or drainable porosity (volume of voidstotal soil volume)
of the soil approximately equal to the specific yield
Rj= retardation factor (R gt_ 1) a dimensionless parameter that
represents the ratio of groundwater pore velocity to the actual
advection rate in a sorbing (onto immobile soil grains) porous
medium under transient concentration conditions
5797wpdoc8glaquolluprifinaltextmasterriftil061297 5-1 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
5111 Sorption
The retardation factor Rj represents the attenuation of a plumes frontal advancement due to
sorption ie temporary storage on soil grains Examples of analyses for which retardation
must be considered include (1) calculation of the time required for contamination to reach a given
downgradient location and (2) determination of the time required to remediate a contaminated
aquifer The retardation factor is defined by the following relationship (Freeze and Cherry
1979)
where pb is the bulk dry density of the soil (massvolume) n is the effective porosity of the soil
(volume of voidstotal soil volume) and K^ is the soil-water partition coefficient (volumemass)
often referred to as the distribution coefficient
The soil-water partition coefficient is the relative magnitude of the chemical concentration on solid
particles and in pore water for a particular soil (Lyman et al 1982)
C = AT C
where
C = concentration of the compound sorbed to the solid phase of the soil (mass
chemicalbulk dry mass soil) and
Q = concentration of the compound in the pore water of the soil (massvolume)
In this expression it is implicitly assumed that an equilibrium exists between the solid and water
phases and that the sorption process is linear (Freundlich isotherm with exponent equal to unity)
over the range of concentrations considered
For non-ionic organic compounds such as VOC Kj can be estimated from the measured fraction
of organic carbon naturally occurring in the soil fx (grams organic carbongram dry soil) and
the organic carbon sorption coefficient K^ (Tinsley 1979) as long as f^ gt_ 0001
5797wpdocsgalluprifinaltextmasterrifnl061297 5-2 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Values of K for many common organic compounds are available in the literature K is also
related to the octanol-water partition coefficient K^ for which a large data base is also available
(eg Hansch and Leo 1979) For fine-grained soil particles K and K^ can be related as
follows (Karickhoff et al 1979)
Kx = 063
Chemical-specific relationships between K and K^ also exist for several VOC (eg Lyman et
al 1982) K values for VOC in the Study Area are presented in Table 5-1
5112 Transport by Dissolved Organic Carbon
For certain families of organic compounds the presence of dissolved organic carbon (DOC) in
groundwater can partially reverse the sorption process to soil particles and release sorbed
constituents to groundwater As a result the migration of these compounds under certain
circumstances can be enhanced (Enfield and Bengtsson 1988) Increases in mobility are greatest
for very hydrophobic (high K) compounds such as pesticides polycyclic aromatic hydrocarbons
(PAH) and dioxins Due to their characteristically low K^s VOC transport in groundwater is
generally unaffected by partitioning to DOC unless DOC concentrations exceed 10000 mgL
(Enfield and Bengtsson 1988) Typically natural DOC concentrations in groundwater range
from 1 to 10 mgL
512 Dispersion
Dispersion is a dilution process by which an initial volume of aqueous solution continually mixes
with increasing portions of the flow system Dispersion occurs on a small or microscopic scale
due to molecular diffusion in the water phase nonuniform velocity distributions within the pore
space and to a large degree the tortuous pathlines that groundwater follows during movement
through interconnected soil pores of different sizes and shapes On a macroscopic scale
dispersion results from geologic heterogeneities such as layers and lenses of contrasting soil type
(ie hydraulic conductivity) In practice dispersion is primarily due to variations in hydraulic
conductivity which produce large gradients in advective transport It is well known that aquifers
contain horizontal layers or lenses of coarser and finer grained materials compared to the average
material type that can result in zones of significantly higher and lower hydraulic conductivity
respectively than the screen interval value determined from pumping and slug tests Factor of
ten hydraulic conductivity variations or more over the thickness of an aquifer are not uncommon
5797wpdocsgalluprifinaltextmasterrifhl061297 5-3 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
(Freyberg 1986 Gelhar et al 1985 Robertson et al 1991 and Sudicky et al 1983) For
contaminant transport the more permeable zones are more important because they determine the
maximum distance over which dissolved constituents will migrate from the source area
With respect to chemical migration from a source area to an arbitrary downgradient location
dispersion will cause contaminants to arrive in a shorter time interval than the travel time based
on the mean groundwater pore velocity (Section 511) This reduced travel time associated with
dispersion is due to advection in the zones of higher hydraulic conductivity that cause the
concentration distribution in the longitudinal (flow) direction to spread out or disperse The
additional length Ld that a chemical may migrate due to dispersion can be estimated from the
following relationship (Bear 1979)
where
t = total time of groundwater travel (= VL^ laquo
Rj = retardation factor
DL = longitudinal dispersion coefficient (length 2time)
In a porous medium the longitudinal dispersion coefficient can be estimated as follows
DL =
where
v = groundwater pore velocity
aL = longitudinal dispersivity of the aquifer (length)
The percent reduction in travel time along a pathline due to longitudinal dispersion can be
calculated using the equation (Bear 1979)
where
At = reduction in travel time along a pathline due to longitudinal dispersion ()
5797wpdocsgalluprifinaltextmasterrifhl061297 5-4 QST Environmental
Gallups Quarry Superfond Project - Remedial Investigation
A t = mdash- 100 ^total
Ld = additional distance (in excess of advection distance) that chemical migrates due to
longitudinal dispersion
= total distance of travel by mean advection (average groundwater flow rate)
An excellent summary of estimated longitudinal dispersivity values for numerous sites is given by
Gelhar et al (1985)
513 Advection Due to Fluid Density Differences
Advective transport can also occur due to fluid density differences in cases where the total
dissolved solids (TDS) concentration is very high A typical example is salinity intrusion into an
aquifer where the greater density of the salt water (TDS 35000000 ppb) causes it to sink within
the fresh water aquifer This causes downward advection of groundwater and results in
stratification of the aquifer into varying zones of salinity However density effects can be caused
by any dissolved compound if the concentration is high enough Laboratory experiments have
shown that density effects do not begin to be observed until the total dissolved concentration in a
plume exceeds background levels by about 1000000 to 5000000 ppb (Schincariol and
Schwartz 1990 Schwille 1988) As a result fluid density effects are not important in the Study
Area
514 Biological and Chemical Degradation
In recent years groundwater scientists have begun to understand the role of microorganisms in
the subsurface transformation of organic chemicals Recent studies have shown that large numbers of organisms can exist in the subsurface environment In many cases organic compounds can be completely degraded to harmless products However by-products can also be
produced which are more mobile and toxic than the parent compound These transformations can
make it difficult to correlate groundwater contamination with particular sources Quantitative
predictions of the fate of biologically reactive chemicals are approximate at best This is due to a
lack of understanding of the biochemical transformation process and variability of transformation
rates in an aquifer (eg as much as two orders of magnitude over a distance of less than 1 m)
For example Wood et al (1980) have demonstrated in the laboratory and observed in the field
the following anaerobic transformations of parent compounds to daughter products
5797wpdoc8galluprifinaltextmasterriftJ061297 5-5 QST Environmental
Gallups Quarry Superfiind Project - Remedial Investigation
carbon tetrachloride -bull chloroform -raquo methylene chloride
trans-12-d ichloroethene
PCE -bull TCE - cis-l2-dichloroethene - vinyl chloride
11-dichloroethene
111-trichIoroethane -raquo 11-dichloroethane - chloroethane
The transformation of PCE (tetrachloroethene) and TCE (trichloroethene) to vinyl chloride is an
example of a transformation to a daughter compound which is considerably more toxic than its
parent compound
Persistence in the environment can be described by a parameter known as the environmental
half-life of a compound The environmental half-life tQ is related to a decay constant X
(Itime) in a first-order decay process
X = ln(2)tm
where ln(2) = 0693 The product of the decay constant and the porewater concentration is equal
to the rate (masstimeunit volume) at which a compound degrades into another form of
compound In practice the parameter half-life is an empirical parameter that quantifies mass loss
due to biological photochemical chemical or physical (eg volatilization) degradation
mechanisms
Within the subsurface biological activity is believed to be the principal cause of the
mineralization (ie transformation to inorganic constituents) of organic compounds (Alexander
1978) Hydrolysis is the reaction of compounds with water or the hydroxide or hydromium ions
associated with water However organic functional groups such as halogenated organics (eg
TCE TCA PCE) ketones benzenes and phenols are generally resistant to this mechanism
(Lyman et al 1982) Oxidation (loss of electrons during a chemical reaction ) and reduction
(gain of electrons during a chemical reaction) can also alter and attenuate organic compounds
For most inorganic compounds geochemical transformations are the most important degradation
mechanisms Due to the complexity of degradation processes and the fact that little data is
typically available to adequately model the loss mechanisms prediction of decay rates in the field
as discussed above is very difficult and not often feasible especially for biodegradation
5797wpdocsgalluprifinaltextmasterrifnl061297 5-6 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
515 Volatilization
The Henrys law coefficient H (Morel 1983) is an air-water partition coefficient which relates
the equilibrium concentrations in air and water for volatile compounds in a multi-phase system
such as the unsaturated zone of the subsurface or the air-water interface of a water body
H = C 1C
where C and eurobdquo are the chemical concentrations in air and water respectively The coefficient is
used in the calculation of volatilization from a water body or soil and for the determination of
solids water and air concentrations resulting from chemical partitioning in a contaminated
unsaturated soil
Organic compounds with Henrys law coefficients greater than 103 atm-m3mole are generally
considered to be highly volatile These compounds can volatilize relatively rapidly from water at
air-water interfaces such as surface water bodies or groundwater tables However the rate of
volatilization is also controlled by diffusion in the water phase Table 5-1 summarizes values of
the Henrys law coefficient for selected organic constituents detected in the Study Area
516 Aqueous Solubility
The solubility of a compound in water is the maximum amount of that compound that will
dissolve in a unit volume of pure water at a specified temperature Water solubility is one of the
most important fate and transport parameters Highly soluble compounds tend to have relatively
low KK values and Henrys law coefficients and tend to be more readily biodegradable by
microorganisms in soil Table 5-1 lists solubilities for VOC detected in the Study Area
52 Study Area-Specific Characteristics 521 Retardation Factors
A Site-specific evaluation of chemical migration rates in groundwater was conducted by
measuring the total organic carbon content TOC of 31 soil samples from the northern Study
Area (Table 5-2) The parameter f (Section 51) is equal to TOC expressed as a fraction As
discussed in Sections 26 and 2721 an ASTM method was used to measure the 4 of the 28
samples from the Former Primary Disposal Area (SB-series borings) EPA Method 9060 was
used to analyze the three samples from the boring for well MW102B The fK measurements for
the SB-series soils samples range from less than 00015 to a maximum of 0023 and the
geometric mean is 00023 In these calculations values below the detection limit of 00015 were
assigned one-half the detection limit These f^ values are typical of high hydraulic conductivity
sand and gravel aquifers
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 5-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The measured values for the three MW102B samples are uncharacteristically low for coarse
stratified drift The geometric mean of these samples is 0000014 which is a factor of 100 lower
than the SB-series data The discrepancy appears to be due to the fact that EPA Method 9060 is
designed for TOC analysis of water samples The f values for the three MW102B samples are
expected to be on the order of 0001 based on comparisons with organic carbon values for
samples of a similar lithology from the Gallups Quarry and other sites Furthermore as
discussed by Karickhoff et al (1979) the available correlations that relate f^ to retardation factor
Ra are not valid below f = 0001 Below values of f = 0001 mechanisms other than
sorption to organic carbon (eg chemical adsorption to mineral surfaces) begin to dominate with
the result that overall sorption and retardation of VOC do not decrease even though the TOC
content of the aquifer materials does Therefore if f^ lt 0001 researchers have indicated that
in many cases calculations of Rd can use f^ = 0001 to account for these alternative sorption
mechanisms For these reasons the SB-series f^ data that are representative of coarse stratified
drift were used in the transport evaluations discussed in the following sections
The average f^ for the SB-series soil samples located below the water table were also calculated
to evaluate vertical trends in the data These samples include
Sample Depth (feet bgs) TOC (mgkg)
SB 104 15-17 lt1500
SB104 26-28 1700
SB108 6-8 lt1500
SB 109 4-8 1600
SB109 10-16 lt1500
SB109 17-24 1500
SB109 24-32 1600
The geometric average f for these samples is 00012 if one-half the detection limit is used for f
lt 00015 Because this average excludes shallow samples with larger silt contents it is
considered more representative of the higher hydraulic conductivity coarse-grained soils which
primarily control groundwater transport
Table 5-1 summarizes chemical-specific retardation factors for VOC detected in Study Area
groundwater These estimates are based on a f value of 00012 which as discussed above is
near the minimum value appropriate for the calculation of R Actual retardation factors in the
aquifer will be nonuniform due to the inherent variability of soil organic carbon content For
example retardation factors based on an f of 00012 may be more appropriate for evaluation of
5797wpdocsgalluprifinaltextmasterri fal061297 5-8 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
transport rates in the middle to lower portions of the aquifer where the soil is generally coarser
and contains less silt which is associated with the organic carbon content Conversely the
average value of 00023 for all samples is likely more representative of soils in the upper portion
of the aquifer and above the water table In any case this overall variability in f^ values for the
aquifer is considered to be smaller in magnitude than the natural variability in hydraulic
conductivity values for the site The recent detailed field investigations in sand and gravel
aquifers referenced in Section 512 have shown that it is not uncommon for hydraulic
conductivities to vary by as much as a factor of ten over a scale of a few feet Variations in both
f and hydraulic conductivity values impact predicted chemical transport rates (Section 511)
A bulk dry density of 18 gcm3 and an effective porosity of 025 were estimated from the
literature based on soil grain size analyses Potential variability associated with these parameters
is small compared to k^ estimates and is not important for the following transport rate evaluation
The results in Table 5-1 are useful for comparing relative mobilities for different compounds and
assessing contaminant migration rates relative to groundwater pore velocities 11-dichloroethane
is expected to be the most mobile VOC while PCE and ethyl benzene should be the least mobile
The tracer compounds TCA and DCE are expected to migrate about a factor of two slower than
the groundwater with DCE migration being the fastest
522 Chemical Migration Rates
5221 Groundwater Travel Times
Compound-specific migration rates in the overburden aquifer were examined using Darcys law
(Section 511) to compute groundwater pore velocities from (1) measured horizontal hydraulic
gradients defined by the November 1995 piezometric surface maps (Section 332) (2) the
hydraulic conductivity data (Table 3-1) and (3) estimated retardation factors (Table 5-1) The first step was to construct a map of groundwater times-of-travel along the various pathlines shown
on the groundwater flow maps for the southern Study Area (Plate 3-9) and for the lower portion
of the aquifer in the northern Study Area (Plate 3-8) Groundwater travel times along each of the
pathlines were modelled using the Tecplot software and the interpolated piezometric head
distribution to define the continuous horizontal hydraulic gradient distribution Additional
information regarding pathline computation using Tecplot is provided in Appendix Q Since the
more permeable zones in an aquifer are known to control the rate of advancement of a plumes
leading edge (Section 512) the upper bound hydraulic conductivity estimates from Table 3-1
were considered From a review of these measurements it was determined that a mean hydraulic
conductivity of 004 centimeters per second (115 feet per day) would be reasonable to use in the
time-of-travel computations in the northern Study Area because this value is representative of the
more permeable coarse-grained soils north and northwest of the Former Primary Disposal Area
(ie wells MW102TT MW103TT MW104TT MW117TT and MW118TT) A lower
5797wpdoc8galluprifinaltextmlaquosterrifhl061297 5-9 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
hydraulic conductivity of 00025 cms (7 ftday) representing the geometric mean value for wells
MW114TT and MW115TT was selected for the southern Study Area An effective porosity of
025 was used in the calculations
The travel-time analysis results are shown in Plate 5-1 Markers denoting half-year (northern
Study Area) and five-year (southern Study Area) travel-time intervals have been placed on each of
the pathlines to allow evaluation of spatial variations in groundwater pore velocity and
determination of total groundwater travel-time between different locations The time period
required for a particular VOC to migrate along a pathline can be estimated as the product of the
groundwater travel-time and the compound-specific retardation factor listed in Table 5-1
5222 Groundwater Flushing Rates
Another useful relationship to consider when evaluating chemical migration is the time period
required to reduce the concentration in a specific portion of an aquifer by groundwater flushing
Assuming that source material is no longer introducing contamination into the portion of the
aquifer (ie control volume) being evaluated the US EPA Batch Flushing Model (EPA 1988)
provides such a relationship
p v = J V h )
where In is the natural logarithm to the base e Rd is the retardation factor C0 is the initial or
starting average groundwater concentration in the control volume Q is the final average
concentration and Pv is the number of groundwater pore volumes which have flowed through the
control volume Pv can be estimated as
P =-raquo v Ltotal
where v is the groundwater pore velocity (Section 511) t is the time duration being considered
and L^ is the total distance or length along a characteristic pathline (from upgradient to
downgradient) through the volume of aquifer material The model assumes complete mixing of
contaminants (ie infinite dispersion) within the control volume Brusseau (1996) demonstrated
that in part due to this assumption the Batch Flushing Model can partially account for
nonequilibrium desorption (ie delayed release) of VOC from soil
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 5-10 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
For example the southern Study Area (area south of the Former Seepage Bed) can be considered a control volume with a characteristic groundwater flushing rate In this area a time t of order 10 years is required for groundwater to flow through a distance L^ of about 400 feet thus indicating an average pore velocity v of about 40 feet per year In other words one pore volume of groundwater flushes through the overburden deposits in the southern Study Area in approximately 10 years From the Batch Flushing Model it can be seen that for a nonsorbing compound with R = 1 23 pore volumes [ln(10)] would need to flush through this area to lower average concentrations by a factor of ten assuming no source material remained east of the southern Study Area or above the water table 46 pore volumes would be needed for a factor of 100 reduction Since each pore volume roughly corresponds to 10 years the factors of 10 and 100 concentration reductions would require time periods of about 23 and 46 years respectively If however one were considering a compound with R = 3 the corresponding times would be about 70 and 140 years
5223 Discussion In the northern Study Area three areas of characteristically different horizontal hydraulic gradients exist in the overburden aquifer The steepest gradients (on the order of 0025 feet per foot) are found south of the former disposal areas Assuming the hydraulic conductivity in this area is 004 cmsec Plate 5-1 shows that the groundwater travel time through this portion of the aquifer is expected to be much less than one year However hydraulic conductivity data and soil descriptions suggest that a more representative hydraulic conductivity value for the till deposits in this area would be 0001 cmsec or less which would correspond to a travel time of five years or more (eg from MW109 to the Former Primary Disposal Area)
Northeast of well MW116 north of Mill Brook and in the vicinity of the former Pervel flock plant the hydraulic gradient is about 0007 feet per foot and a hydraulic conductivity of 004 cmsec is representative of the aquifer As a result the largest groundwater pore velocities are expected to exist in these areas For example as shown in Plate 5-1 the expected groundwater travel time is about one to two years from the vicinity of Pervel to MW116 and from Pervel to MW101
Groundwater travel times downgradient from the Former Primary Disposal Area are much longer due to the low hydraulic gradients northwest of the railroad tracks In the vicinity of MW105 and MW102 the gradient is about 00003 feet per foot or more than a factor of 20 less than the gradient northeast of this area For example the estimated groundwater travel time (ignoring longitudinal dispersion) from MW107 to MW102 near the front of the VOC plume is about 8 to
10 years By comparison almost 20 years has passed since the documented disposal in the late 1970s Based on the retardation factors (Table 5-1) for TCA (R = 23) and DCE (R = 14)
5797wpdocsgalluprifinaltextmasterrifhl061297 5-11 QS7 Environmental
Gallups Quarry Superand Project - Remedial Investigation
the estimated travel times for these compounds from MW107 to MW102 are about 20 years and
13 years respectively Considering these chemical migration rates and the fact that TCA and
DCE were detected at quantifiable levels along the VOC plume centerline and at location
MW102 it appears reasonable to conclude that these compounds are associated with the former
disposal areas
However as discussed in Section 4221 the present PCE distribution in groundwater exhibits
inconsistencies with migration from the former disposal areas Although historical detections of
PCE were found in well cluster SW17 which is located downgradient from the Former Primary
Disposal Area and near well cluster MW105 the concentrations had reduced from a maximum of
1000 ppb in 1980 to near the detection limit by early 1993 (Section 523) Based on this rate of
reduction PCE concentrations at diis location would be expected to have fallen below or near the
detection limit by 1995 In fact only trace levels were detected in wells MW105TT and
MW105T during two of the four 1995 sampling events Furthermore the measured groundwater
flow directions in the overburden aquifer indicate that many of the pathlines originating near the
former Pervel flock plant pass through the vicinity of wells MW117 MW118 MW119 MW116
MW103 MW102 and MW101 Although MW101 and MW102 are downgradient from both
Pervel and the former disposal areas groundwater flow conditions in the past would need to have
been different from present conditions for MW116 and MW103 to be downgradient from the
former disposal areas As discussed in Section 4 elevated levels of PCE TCA and DCE have
been detected in monitoring wells located on the former Pervel property Also PCE TCA and
DCE were detected in wells MW116T MW118TT and MW103TT located downgradient from
Pervel during the 1995 sampling rounds and PCE TCE and DCE were detected in well MW-C
on the former Pervel property The travel time of these compounds from Pervel to wells
MW116 MW118 MW103 MW102 and MW101 is estimated to be two to six years Taking
this into consideration along with the VOC detections in the Pervel wells during the period 1987
to 1989 (Section 523) it is possible that the low-level PCE TCA and DCE detections in
MW116T MW118TT and MW103TT represent the last remaining portion of a Pervel VOC
plume The lack of VOC detections in wells MW117 and MW119 could be explained by dilution
in these areas or by the fact that these wells may not be immediately downgradient from the
historical source area(s) on the former Pervel property
The migration rate of PCE compared to the disposal area tracer compounds TCA and DCE also
supports the existence of an off-site PCE source The expected migration rate of PCE is a factor
of two to four slower than that of TCA and DCE due to their differing K values Assuming all
of these VOC were released within a few years of each other the leading edges of the TCA and
DCE plumes should be much farther downgradient than the PCE plume Instead as evidenced by
the data shown in Plate 4-6 the opposite is true because a PCE concentration of about 30 ppb has
5797wpdocsgalluprifinaltextmasterrifnl061297 5-12 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
been detected at MW101 In terms of groundwater migration (not including retardation) from the
Former Primary Disposal Area the elevated PCE concentrations at location MW101 would
represent a total travel-time from the former disposal areas which is more than a factor of two
greater than that required for the leading edge of the TCA-DCE plume to reach MW102
Comparing the relative mobilities of PCE TCA and DCE (Table 5-1) the time required for PCE
to migrate from the Former Primary Disposal Area to well MW101 should be more than a factor
of four to eight longer than the TCADCE travel time to MW102 Based on this comparison the
PCE detections at MW101 could be attributed to transport from Pervel It is also possible that
the Pervel groundwater contamination has impacted the MW102 area Although the PCE
detections at locations MW102 and MW101 could be attributable to historical releases from the
former disposal areas the above findings (flow directions spatial PCE distribution travel times)
suggest that contamination from the former Pervel facility has at a minimum contributed to VOC
contamination (PCE and possibly DCE and TCA) at these locations
The above discussion also highlights the important issue of what defines the leading edge of the
zone of VOC contamination in the overburden aquifer Several of the above findings suggest that
the downgradient extent of VOC contamination associated with the former disposal areas is
located near wells MW102 and MW101 The convergent nature of the groundwater flow patterns
in the northern Study Area clearly establish a narrow well-defined preferred pathway of low-level
contaminant migration from the Former Primary Disposal Area The chemical analysis results
from the monitoring well sampling program confirm the measured flow directions Further
whereas TCA and DCE can presently be traced continuously along the plume centerline at
elevated levels (well locations MW107 MW105 and MW102) PCE cannot These findings
suggest that the PCE contamination in groundwater may be attributable to the former Pervel flock
plant and should not be used solely to define the leading edge of the VOC plume The time-ofshy
travel computations support the location of the disposal area VOC plume between MW102 and
MW101 The reduction of TCA and DCE concentrations to less than 10 ppb and the decrease of
xylene to below detection at MW101 is also consistent with the interpretation that the disposal
area VOC plume does not extend far beyond MW102 In addition the groundwater pore velocity
in the vicinity of wells MW102 and MW101 is estimated to be about 50 feet per year which is as
much as a factor of 20 lower than rates upgradient from this area Based on this pore velocity
and the retardation factors in Table 5-1 the migration rates of TCA and PCE are expected to be
about 20 and 10 feetyear respectively At these rates the estimated travel times for TCA and
PCE from MW102 to MW101 are about 20 and 35 years respectively As discussed in the
following section given the relatively large rates of historical VOC concentration reductions
which have been observed in the northern Study Area it is expected that PCE 12-DCE 11shy
DCE and TCE levels near MW102 will fall below MCLs within the above 20- to 35-year period
due to biodegradation and dilution mechanisms Reduction rates for vinyl chloride which also
5797wpdocsgalluprifinaltextmlaquoraquoterrifhl061297 5-13 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
has been detected above MCLs near MW102 will likely lag behind the other VOC because it is a
final chlorinated breakdown product
523 Time-Dependent Concentration Reductions
5231 Observed Concentration Changes
Significant groundwater concentration reductions with time have been observed in the northern
Study Area from the late 1970s through the 1995 sampling rounds To illustrate these temporal
trends concentration data for selected VOC were plotted versus time to quantitatively evaluate the
reduction rates The observed rates of concentration reduction are also compared to predicted
values using the groundwater flushing relationships presented in Section 5222 and are evaluated
to determine site-specific estimates of biodegradation rates
Figures 5-1 through 5-3 contain the concentration vs time graphs for three groups of wells
organized according to transport characteristics and location Group 1 (Figure 5-1) immediately
downgradient from the former disposal areas (SW17S SW17D SW13 MW107TT MW105S
and MW105TT) Group 2 (Figure 5-2) within the downgradient portion of the VOC plume
(MW102S MW102TT MW101TT) and Group 3 (Figure 5-3) the area northeast of the VOC
plume and downgradient from the former Pervel flock plant Data from the Group 1 wells
provide a good historical perspective on improvements in groundwater quality resulting from
source removal activities in the late 1970s and from ongoing biodegradation and rainwater
infiltration (flushing) within the Former Primary Disposal Area The Group 2 wells are located
within the downgradient portion of the VOC plume and in a section of the aquifer where the
hydraulic gradient and associated groundwater transport rates are up to a factor of 20 lower than
in other parts of the northern Study Area Group 3 wells are downgradient from the former
Pervel facility where elevated levels of PCE and TCA have been detected and are located in the
portion of the aquifer with the highest groundwater flushing rates
5232 Evaluation of Concentration Reduction Rates and Mechanisms
The most important aspect of the semilogarithmic plots in Figures 5-1 to 5-3 is the characteristic
slope or trend of the concentrations as a function of time Specifically it can be seen that many
of the graphs exhibit an almost straight-line decrease in concentration with time This linear
variation is often observed with historical groundwater quality data because the linearity has a
physical basis First many biodegradation mechanisms can be modelled as a first-order decay
process (Section 51) which produces a straight-line decrease in concentrations on a semi-log plot
Second flushing of clean groundwater (eg rainwater infiltration or uncontaminated
groundwater) through a contaminated volume of aquifer material has been shown (Section
5222 Brusseau (1996)) to exhibit the same type of response In both of these approximate
first-order processes the slope of the straight-line response is inversely proportional to the
5797wpdocsgalluprifinaltextmasterrifhl061297 5-14 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
environmental half-life (Section 514) for that mechanism and a particular chemical compound
Using the relationships developed in Section 5222 the environmental half-life associated with
groundwater flushing can be defined as
Substituting the expression for pore volume Pv the flushing half-life can also be written
From the above expression it can be seen that the flushing half-life for a particular compound is
directly proportional to the chemical retardation factor and inversely proportional to the
groundwater pore velocity The groundwater flushing rate represents the rate at which
concentrations in a particular portion of the aquifer are reduced In contrast to biodegradation
groundwater flushing does not reduce the total mass of a compound in the aquifer because the
contaminants are advected to downgradient areas
In the Group 1 area historical VOC data for the SW-series wells (Metcalf amp Eddy 1993) (eg SW13 and SW17) summarized in Table 5-3 and on Figure 5-1 show that TCA TCE and PCE
levels in groundwater downgradient from the Former Primary Disposal Area have typically
decreased by a factor of more than 100 from the late 1970s to 1993 Using the SW17S data
from 1980 to 1993 the estimated environmental half-lifes for TCA TCE and PCE are
approximately 15 20 and 24 years respectively From February 1993 through the present the
shallow concentration reduction rates (SW17S and MW105S) are much higher corresponding to TCA TCE PCE and DCE environmental half-lives of about 03 lt 1 03 and 04 years
respectively Concentration reduction rates in the lower portion of the aquifer (SW17D and
MW105TT) from February 1993 through the end of 1995 are a factor of two to three slower than
shallow rates the estimated environmental half-lifes for TCA PCE and DCE in the deep aquifer are about 06 09 and 09 years respectively The higher concentration reduction rates in the
shallow aquifer may be due to rainwater infiltration andor increased biodegradation These
decreases in VOC levels are likely due to a combination of (1) source removal and source
depletion (ie soil concentration reduction by flushing mechanisms) within the former waste
disposal areas (2) mixing of rainwater infiltration with groundwater which can be a significant
dilution mechanism in the wetland areas as evidenced by the frequent occurrence of ponded water
and (3) biodegradation by microorganisms in soil
5797wpdoc8galluprifiiialtextmlaquoraquoterrifhl061297 5-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Vinyl chloride does not follow the same trends of reducing concentrations exhibited by the other
chlorinated VOC Vinyl chloride concentrations in wells MW107TT and MW105TT generally
increased during the 1995 sampling rounds Since this compound is the final chlorinated
breakdown product of PCE TCE and DCE it appears that the vinyl chloride detections are the
result of biodegradation The apparent increase in vinyl chloride concentrations and decrease in
DCE levels in well MW107TT may be further evidence that vinyl chloride detections are
associated with biodegradation mechanisms
The observed Group 1 environmental half-lifes are consistent with predicted half-lifes due to
groundwater flushing From Plate 5-1 the estimated groundwater travel time from MW107 to
MW105 is 05 to 1 year which corresponds to 1 to 2 groundwater pore volumes per year
flushing through the Group 1 Area Using the retardation factors in Table 5-1 the predicted
flushing half-lifes for DCE TCA and TCE range from 05-10 08-16 and 07-14 years
respectively and the flushing half-life for PCE is between 14 and 3 years This good agreement
between observed and predicted rates of concentration reduction downgradient from the former
disposal areas is additional evidence that source removal activities were successful and natural
mechanisms are actively producing further reductions in contaminant levels The fact that deep-
aquifer PCE and TCA concentrations near MW105 have decreased more rapidly than predicted
groundwater flushing rates during the period 1993 to 1995 suggests that biodegradation is
breaking down these parent compounds Furthermore TCA TCE and PCE reduction rates
before 1993 were much slower and are similar in magnitude to flushing rates This indicates that
biodegradation before 1993 was less important Assuming this is the case the estimated
biodegradation half-lifes for PCE and TCA for the period 1993 to 1995 range from 13-25 and
10-24 years respectively near the Former Primary Disposal Area In contrast observed
reduction rates for TCE and DCE are slower than predicted flushing rates which may be
evidence that breakdown of their respective parent compounds was significant during the period
1993 to 1995 Indeed this interpretation is consistent with the observed biodegradation of PCE
In the Group 2 area (Figure 5-2) VOC levels (with the exception of DCE) at well cluster
MW102 appear to increase in 1995 while concentrations at cluster MW101 remained relatively
constant The concentration increase at MW102 may be due to the fact that this cluster is near
the leading edge of the VOC plume and groundwater flushing rates in this area are relatively low
However as discussed in Section 522 the increased PCE and TCA levels along with daughter
products such as TCE DCE vinyl chloride and DCA may be associated with transport of the
PCE and TCA plumes on the former Pervel property
The most interesting of the Group 3 wells are wells MW-A -B and -C located on the former
Pervel property As shown on Figure 5-3 PCE and TCA concentrations in wells MW-A and
5797wpdoc8galluprifinaltextmasterrifhl061297 5-16 QampT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW-B reduced to below detection limits by 1990 These rates of reduction correspond to halfshy
lifes of about 02 years for TCA and 03 years for PCE By comparison based on travel time
estimates from Plate 5-1 predicted groundwater flushing half-lifes for TCA and PCE
concentration reduction near Pervel are about 08 and 14 years respectively Assuming the
differences between observed concentration reduction rates and rates predicted by groundwater
flushing alone are due to biodegradation the biodegradation half-lifes for TCA and PCE are 03
and 04 years respectively In well MW-C TCA levels have reduced at a rate consistent with a
02-year half-life while the PCE half-life is approximately 05 years The corresponding
estimated biodegradation half-lifes for TCA and PCE at MW-C are 03 and 08 years
respectively Therefore biodegradation appears to be the major cause of the observed TCA and
PCE concentration reductions in the Pervel wells The lack of PCE or TCA detections in well
clusters MW119 and MW117 during the November 1995 sampling round are also consistent with
the rates of reduction in the Pervel wells For example the estimated travel times of PCE and
TCA from Pervel to the MW119 and MW117 wells are on the order of 4 and 2 years
respectively Since PCE and TCA levels in wells MW-A and MW-B were below detection by the
beginning of 1990 this groundwater with no detectable levels of either compound would be
expected to have passed through the MW119 and MW117 wells by the beginning of 1994 (PCE)
or 1992 (TCA)
In contrast the groundwater travel time from Pervel to wells MW116 MW103 and MW118 is
estimated to be up to one year longer than the travel time to MW119 and MW117 This would
correspond to increased travel times for PCE and TCA of about 4 and 25 years respectively
Based on these estimates low but detectable levels of PCE and TCA would be expected in wells
MW116 MW103 and MW118 during 1995 groundwater sampling In fact PCE TCA and
DCE were detected at each of these locations in 1995 at trace levels Slightly higher
concentrations of PCE and TCA were detected in MW116T during January 1995 but trace levels
were detected during each of the three subsequent 1995 rounds Further these rates of PCE and
TCA migration from Pervel would be consistent with the detections in well clusters MW102 and
MW101
Additional estimates of biodegradation rates were made by evaluating concentration reductions
within the parcel of groundwater located near well SW17 in 1980 Using the travel times shown
in Plate 5-1 it is estimated that about five years would be required for groundwater to travel from
SW17 to MW102 The corresponding chemical migration rates for TCA TCE and PCE are 12
11 and 20 years respectively Due to longitudinal dispersion (Section 512) the actual travel
times would be somewhat less Therefore groundwater presently in the MW102 area is expected
to be representative of historical (1980) groundwater contamination from the SW17 area
Neglecting possible contaminant contributions from Pervel most of the VOC concentration
5797wpdocsglaquolluprifinaltextmalaquoteiTifTil061297 5-17 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
reductions occurring in this parcel of groundwater as it traveled from SW17 to MW102 would be
due to biodegradation and rainwater infiltration
Figure 5-4 shows the TCA TCE and PCE concentration data from 1980 and 1982 for SW17S
and from January and November 1995 for wells MW102S and MW102TT The slopes of the
lines connecting the data from these two periods provide estimates of the combined biodegradation
and rainwater dilution rates for these compounds The combined half-lives for these two
mechanisms are 15 years (TCA) 18 years (TCE) and 21 years (PCE) From Bear (1979) the
half-life for rainwater dilution can be estimated as
n - b
where n = effective porosity b = saturated thickness and I = groundwater recharge rate due to
rainwater infiltration Using n = 025 b = 60 feet and I = 30 inchesyear (USGS 1995) the
half-life for dilution due to rainwater infiltration is about 4 years Using this value the estimated
biodegradation rates for TCA TCE and PCE within the VOC plume are 24 33 and 44 years
respectively These estimated biodegradation rates for TCA and PCE are a factor of two to three
less than estimated rates near the Former Primary Disposal Area during the period 1993 to 1995
5233 Summary
From the late 1970s through the four 1995 sampling rounds groundwater concentrations in the
VOC plume downgradient from the Former Primary Disposal Area have decreased at a rapid rate
The groundwater quality data from 1995 indicates that this trend of reducing concentrations is
continuing Based on these concentration reduction rates most VOC levels will fall below their
respective MCLs in a period of less than four years Vinyl chloride is an exception to this trend
because increased levels of this compound were detected in 1995 apparently due to the chemical
break down of its parent compounds PCE TCE and DCE
Analyses of these concentration reductions with time indicate that biodegradation and dilution by
rainwater infiltration are the key mechanisms responsible for these changes with biodegradation
likely the most important component Within the VOC plume biodegradation and rainwater
infiltration are reducing most VOC (with the exception of vinyl chloride) concentrations by about
a factor of two every two years which corresponds to an environmental half-life of two years
5797wpdocsglaquolluprifinaltextmraquosterrifnl061297 5-18 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
60 Summary and Conclusions
This section provides the conceptual model developed for the Study Area based on the findings
of the Phase 1A and IB field investigations and the results of the Long-Term Monitoring
Program sampling events
61 Conceptual Model of the Study Area The conceptual model was developed from the collection and analyses of information and data
from the Remedial Investigation (RI) as well as historical information and data A conceptual
model is an overview of the Study Area taking into account all media and their interrelationships
and describes in summary fashion Site conditions as they pertain to contaminant sources and
migration pathways This conceptual model will be used to support the evaluation of potential
remedial alternatives for the Feasibility Study
611 Geology
Geologic data collected during the RI indicate the following
bull Significant surficial or overburden deposits encountered in the Study Area are till
and glacial deposits referred to as stratified drift
bull The till is relatively dense and is comprised of a fine sandy matrix with abundant
gravel cobbles and boulders The till was encountered directly above bedrock at
most locations at thicknesses of 10 to 20 feet with the thickest accumulations
located along the topographic (bedrock) high in the central area of the Site
bull The stratified drift typically overlies the till or bedrock and consists of poorly to
well sorted deposits of gravel sand and silt Grain size analyses indicate that the
stratified drift is primarily comprised of fine to coarse sands with lesser amounts
of silt and fine gravel The stratified drift thickness varies from less than a few
feet in upland areas to as much as 70 feet in the vicinity of Mill Brook
bull Bedrock within the Study Area consists of grey fine- to medium-grained gneiss
with varying contents of amphibolite biotite and hornblende The bedrock
surface is characterized by a large slope and dips to the northwest and west-
southwest from a bedrock high located about 400 feet southeast of the Former
Seepage Bed The total bedrock surface relief in the Study Area approaches 100
feet
5797wpdocsgalluprifinaltejctmasterri fhl061297 6-1 QfT Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull Geophysical investigations (seismic refraction and magnetometer surveys)
conducted in the vicinity of the Former Seepage Bed did not reveal evidence of
one or two suspected discrete bedrock faults Rather the bedrock in the central
portion of the Site may be more accurately characterized as a series of
interconnected (to varying degrees) fractures and faults
^
612 Hydrogeology
Data regarding hydrogeologic conditions are summarized as follows
Hydraulic Conductivity
bull Across the Study Area test results indicate that the hydraulic conductivity
of the shallow overburden deposits averages approximately 0001
centimeters per second (cms) while the mean hydraulic conductivity for
the deep portion of the aquifer is about 0005 cmsec A mean hydraulic
conductivity of about 0037 cms is more representative of coarser-grained
deposits in the middle to lower portions of the overburden aquifer
northwest of the railroad tracks where the saturated thickness increases to
almost 70 feet
bull The mean hydraulic conductivity of the till (000047 cms) is a factor of
ten less than the average for the stratified drift deposits in the lower
portion of the aquifer and varies between 00002 and 0002 cms
Although the hydraulic conductivity of the till indicates that it is less
permeable and hydrogeologically distinct from the overlying stratified drift
deposits the hydraulic conductivity contrast is not large enough to
significantly alter groundwater flow directions or rates
cir
bull The mean bedrock hydraulic conductivity (000018 cms) is a factor of 25
lower than the average for the coarse-grained stratified drift Due to the
heterogeneous nature of fracture sizes and interconnectivity and their
associated nonlinear effect on groundwater flow rates the hydraulic
conductivity of the bedrock can be expected to be highly variable
throughout the Study Area
5797wpdocsgalluprifinaltextmasterrifhl061297 6-2 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
Groundwater Flow
bull The overburden aquifer is the preferred pathway for groundwater transport
of dissolved constituents This conclusion is supported by the hydraulic
conductivity test results and observations that an upward groundwater
flow component from bedrock to overburden exists throughout most of the
Study Area VOC detections in bedrock wells are believed to be caused
by vertical dispersion in the upper portion of the fractured bedrock
bull Because the unconsolidated deposits become unsaturated in the vicinity of
the Former Seepage Bed discussions of groundwater flow in overburden
are naturally divided into northern and southern portions of the Study
Area
bull Overburden groundwater flow south of the Former Seepage Bed is
generally from east to west at an average hydraulic gradient of 001 feet
per foot (vertical change in piezometric head per horizontal distance) and
is strongly influenced by the bedrock surface and drainage to the wetlands
and stream west of the railroad tracks The saturated thickness in this
area increases from zero near the bedrock high (northeast corner) to more
than 60 feet near the railroad tracks
bull Three distinct zones of overburden groundwater flow exist in the northern
Study Area In the area between the Former Primary and Secondary
Disposal Area and the Former Seepage Bed groundwater flow is largely
through till deposits and toward the north-northwest The hydraulic
gradient in this area is steep (about 003 feet per foot) and strongly
influenced by the dip of the bedrock surface and the lower hydraulic
conductivity of the till deposits The saturated thickness increases from
zero south of MW109 to 20 to 30 feet near the former disposal areas
North-northwest of these areas the hydraulic gradient lessens significantly
to a range of 00003 to 00007 feet per foot (factor of 40 to 100
reduction) North and northeast of Mill Brook the hydraulic gradient is
about 0007 feet per foot
bull Available data indicate that in the northern Study Area overburden
groundwater flow north-northwest of the Former Primary and Secondary
Disposal Areas exhibits a strongly convergent pattern The flow
5797wpdocsgalluprifinaltextmlaquosterriftU061297 6-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
converges from the east-northeast and southwest toward a centerline
generally defined in the downgradient direction by wells MW105
MW102 and MW101 Groundwater flows along this centerline from the
former disposal areas to the northwest Groundwater also flows from the
vicinity of the former Pervel flock plant in southwesterly and westerly
directions toward wells MW116 MW103 and MW101
South of the Former Seepage Bed groundwater flow within the upper
portion of the bedrock unit is primarily in a westerly direction In the
northern Study Area the predominant bedrock flow component is toward
the northwest In both areas the hydraulic gradient is relatively steep and
averages about 002 feet per foot Groundwater flow in bedrock near the
Former Seepage Bed is toward the northwest in the direction of wells
MW113 and MW106 and exhibits no apparent influence from locally
increased fracturing identified from the geophysical investigation and the
hydraulic testing in well MW11 IB
Vertical flow of groundwater is important in the upper several feet of the
bedrock unit Groundwater flow was found to be discharging from
bedrock to overburden at all locations during each of the measurement
dates with the exception of MW109 At MW109 the saturated overburden
thickness is less than a few feet and MW109 is located over a much
higher bedrock elevation than all other wells at which vertical flow from
bedrock was measured
Vertical flow in the overburden aquifer is of increased importance in two
areas in the vicinity of the Former Primary Disposal Area (wells clusters
MW107 MW108 and MW116) where vertical flow directions are
downward and within the upper portion of the aquifer near Mill Brook
where vertical flow is upward
Stream piezometer data and groundwater flow modeling indicate that Mill
Brook generally gains water from the overburden aquifer in the northern
portion of the Study Area
5797wpdoc8galluprifinaltextmraquosterrifhl061297 6-4 Q5T Environmental
Gallups Quarry SuperfimdProject - Remedial Investigation
613 Nature and Extent of Contamination
6131 Contaminant Source Investigation
The following summarizes the findings of contaminant source investigations during the RI
bull Previous remedial activities have completely removed the waste materials
(intact drums and bulk liquid waste) from the Site
bull The Former Seepage Bed and the Former Secondary Disposal Area
contain little residual contamination from the disposal activities which
occurred in the late 1970s
bull Residual levels of contamination primarily VOC and PCB were detected
in the Former Primary Disposal area In general the highest levels of
VOC are located at or just below the groundwater table in native soils
immediately beneath the fill materials and diminish rapidly with depth
PCB were detected primarily within fill materials
bull Other than the three known former disposal areas and the remains of the
former CTDOT asphalt plant no other significant disposal areas were
found to exist on the Site
6132 Groundwater Quality
Groundwater quality data collected during the Phase 1A program indicate the following
bull No significant groundwater contamination was detected within the
overburden or bedrock units in either the southern Study Area or in the
vicinity of the Former Seepage Bed
bull In the northern Study Area a narrow low to moderate-concentration
VOC plume (primarily TCA and DCE) was detected in the overburden
aquifer extending from the Former Primary Disposal Area to the
northwest towards Mill Brook
bull Comparison of present concentrations with historical data indicate that
concentrations within the VOC plume are significantly decreasing with
time From 1978 through 1995 TCA TCE and PCE concentrations
have decreased on the average by more than a factor of two every two
5797wpdocsgalluprifinaltextnui8terrifhl061297 6-5 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
years This trend appears to have continued through the four 1995
sampling rounds for these as well as other VOC with the exception of
the break down product vinyl chloride Biodegradation and dilution by
rainwater infiltration have been identified as the primary mechanisms
causing the concentration reductions with biodegradation the most
important component
The size and orientation of the VOC plume are in excellent agreement
with the established groundwater flow directions
Available information indicates that the leading edge of the VOC plume
associated with the Former Primary Disposal Area is located between
monitoring well clusters MW102 and MW101 VOC transport rates and
the reduction of TCA and DCE levels to estimated values at MW101
support this conclusion
PCE detections in the downgradient portion of the plume exhibit
inconsistencies with migration from the Site Groundwater pathlines and
time-of-travel estimates indicate that the PCE may be attributable to
contaminant transport from the former Pervel facility located north of the
Site Specifically it is possible that PCE detections at locations MW118
MW116 MW103 MW102 and MW101 may have resulted from
groundwater transport from the vicinity of the former Pervel flock plant
However it is also plausible that the PCE detections at locations MW102
and MW101 are attributable to the former disposal areas
Results of surface watersediment sampling and analyses stream
piezometer measurements and groundwater flow modeling indicate that
some discharge of the shallow portion of the plume into Mill Brook is
occurring There are low-level detections of VOC in the section of brook
intersecting the plume however the concentrations are well below those
reported to cause adverse effects in wildlife Detections downstream
adjacent to the municipal sewage treatment plant and below the confluence
of Fry Brook and Mill Brook are probably attributable to off-site sources
along Fry Brook north of the Study Area
Only one of the bedrock wells (MW105B) indicated elevated levels of
VOC Trace levels of a limited number of VOC were also detected in
5797wpdocsgalluprifinaltextma8terrifhl061297 6-6 QStf Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW102B MW107B MW108B and SW-10 however bedrock is not a
preferred pathway for contaminant migration due to its characteristically
low hydraulic conductivity and the consistent upward component of
ground water flow from bedrock to overburden which exists throughout the
Study Area
5797wpdocsgalluprifinaltextmastemfiil061297 6-7 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
70 References
Alexander M 1978 Biodegradation of Toxic Chemicals in Water and Soil in Proc 176th
National Meeting Miami Beach FL Sept 10-15 v 93 American Chemical
SocietyDivision of Environmental Chemistry
Amtec Engineering 1994 Tecplot Version 6 Belevue WA
Bear J 1979 Hydraulics of Groundwater McGraw-Hill
Beyer WN 1990 Evaluating Soil Contamination US Fish Wildl Serv Biol Rep 90(2) 25
pp July 1990
Bouwer H and Rice RC 1976 A Slug Test Method for Determining Hydraulic Conductivity
of Unconfined Aquifers with Completely or Partially Penetrating Wells Water Resources
Research vol 12 no 3 pp 423-428
Boynton GR and Smith CW 1965 Aeromagnetic map of the Plainfield quadrangle New
London and Windham counties Connecticut US Geological Survey Geophysical
Investigations Map GP-541 scale 124000
Brusseau ML 1996 Evaluation of Simple Methods for Estimating Contaminant Removal by
Flushing Groundwater V 34 No 1 pp 19-22
CTDEP 1986 Water Quality Classification Map for the Thames Southeast Coast and Pawcatuck River Basins Sheet 2 of 2 CTDEP Water Compliance Unit Hartford
Connecticut
Dixon HR 1965 Bedrock geologic map of the Plainfield quadrangle Windham and New
London Counties Connecticut US Geological Survey Geologic Quadrangle Map GQshy
481 scale 124000
Enfield CG and Bengtsson G 1988 Macromolecular Transport of Hydrophobic
Contaminants in Aqueous Environment Groundwater v 26 no 1 pp 64-70
ERT 1988 Preliminary Hazardous Waste and Petroleum Hydrocarbon Contamination Evaluation
of the InterRoyal Property Plainfield CT
5797wpdoc8galluprifinaltextmasterrifhl061297 7-1 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
ESE 1994 Gallups Quarry Superfund Project RIFS Work Plan Phase 1A (Prepared by Haley
amp Aldnch Inc Finalized by ESE)
ESE 1995 Initial Site Characterization Report March 1 1996
ESE 1995a April 1995 Long-Term Monitoring Report July 28 1995
ESE 1995b July 1995 Long-Term Monitoring Report October 27 1995
ESE 1996a Long-Term Monitoring Program - Data Report February 1996 Sampling Event
June 19 1996
ESE1996b Long-Term Monitoring Program - Data Report May 1996 Sampling Event
September 24 1996
ESE 1996c Long-Term Monitoring Program - Data Report August 1996 Sampling Event
December 18 1996
ESE 1997a Long-Term Monitoring Program - Data Report November 1996 Sampling Event
March 31 1997
ESE 1997b Long-Term Monitoring Program - Data Report February 1997 Sampling Event
May 21 1997
Fitchko J 1989 Criteria for Contaminated SoilSediment Cleanup Pudvan Publishing
Company Northbrook IL
Freeze RA and Cherry JA 1979 Groundwater Prentice-Hall Inc Englewood Cliffs
New Jersey
Freyberg DL 1986 A Natural Gradient Experiment on Solute Transport in a Sand Aquifer 2
Spatial Moments and the Advection and Dispersion of Nonreactive Tracers Water
Resources Research Vol 22 pp 2031-2046
Fuss and ONeill Inc 1979 Evaluation of a chemical waste disposal area Tarbox Road site
Plainfield Connecticut January 1979
5797wpdocsgalluprifinaltextmlaquoraquotemfhl061297 7-2 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Gelhar LW Montogluo A Welty C Rehfeldt KE 1985 A Review of Field-Scale
Physical Solute Transport Processes in Saturated and Unsaturated Porous Media Electric
Power Research Institute Report No EA-4190
Geraghty amp Miller Inc 1989 Aqtesolv Aquifer Test Solver Version 11 Reston VA October
1979
Hansch C and AJ Leo 1979 Substituent Constants for Correlations Analysis in Chemistry
and Biology John Wiley amp Sons New York
Hem JD 1989 Study and Interpretation of the Chemical Characteristics of Natural Water (3rd
Edition) USGS Water-Supply Paper 2254 US Government Printing Office
Washington DC
HRP Associates Inc 1993 Addendum to Groundwater Monitoring Report Former Pervel
Industries Flocking Plant March and June 1993 Sampling Events HRP Associates
Inc Plainville Connecticut
Karickhoff SW DS Brown and TA Scott 1979 Sorption of Hydrophobic Pollutants on
Natural Sediments Water Research Vol 13 pp 241-248
Lyman WJ Reehl WF Rosenblatt DH 1982 Handbook of Chemical Property
Estimation Methods-Environmental Behavior of Organic Compounds McGraw-Hill
Metcalf amp Eddy 1993 Final Data Summary Report START Initiative Gallups Quarry Plainfield Connecticut
Morel MM 1983 Principles of Aquatic Chemistry John Wiley amp Sons
Prior T Eaton L and Sperduto M 1995 Habitat Characterization for Gallups Quarry
Superfund Site Plainfield Connecticut United States Department of Interior Fish and
Wildlife Service New England Field Offices Concord NH
Reed PB 1988 National List of Plant Species That Occur in Wetlands Connecticut US Fish
amp Wildlife Service Washington DC NERC-881807 105p
Robertson WD Cherry JA Sudicky EA 1991 Groundwater Contamination from Two
Small Septic Systems on Sand Aquifers Groundwater v 29 no 1 pp 82-92
5797wpdocsgalluprifinaltextmlaquoraquoterrifhl061297 7-3 QST Environmental
Gallups Quarry SuperJUnd Project - Remedial Investigation
Schincariol RA and Schwartz FW 1990 An Experimental Investigation of Variable Density
flow and Mixing in Homogeneous and Heterogeneous Media Water Resources Research
v26 no 10 pp2317-2329
Schwille F 1988 Dense Chlorinated Solvents in Porous and Fractured Media translated from
German and Edited by JF Pankow Lewis Publishers Chelsea Michigan
Shacklette HT and Boerngen JC 1984 Element Concentrations in Soils and Other Surficial
Materials in Conterminous United States USGS Professional Paper 1270 US
Government Printing Office Washington DC
Sudicky EA Cherry JA and Frind EO 1983 Migration of Contaminants in Groundwater
at a Landfill A Case Study 4 A Natural Gradient Dispersion Test J Hydrology v 63
pp 81-108
US EPA 1986 Quality Criteria for Water Office of Water Regulations and Standards
Washington DC USEPA 4405-86-001 (NTIS PB87-226759)
US EPA 1987 A Compendium of Superfund Field Operations Methods US EPA540Pshy
87001 (NTIS No PB88-181557)
US EPA 1988 Interim Final Guidance on Remedial Actions for Contaminated Groundwater at
Superfund Sites US EPA Washington DC
US Fish and Wildlife Service 1995 Habitat Characterization for Gallups Quarry Superfund
Site Plainfield CT Concord NH 16 p
USGS 1993 Geohydrology of the Gallups Quarry Area Plainfield CT
5797wpdocsglaquolluprifinaltextmasterrifhl061297 7-4 QST Environmental
SOURCE PLAINFIELD75 MINUTE
124000
0 A 2
SCALE IN MILES
OONNECnCPT
OlMDIMNGLE LOCATION
CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP SERIES 1983
410 Amherst Street Nashua NH 03063
(603) 689-3737
GALLUPS QUARRY SUPERFUND PROJECT PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 1-1
SITE LOCATION MAP DRAWING NAME 1LOCDWG miE NUMBER 7194-138
SCALE AS SHOW [REVISION 0 I DRAWN BY PAD IPATE gg97
N
500 0 500
SCALE IN FEET
LOT NUMBER OWNER
1 C STANTON GALLUP 2 KENNETH R MOFFITT 3 INTERMARK FABRIC CORP 4 NORMAN ATLAS 5 FREDERICK BARRETT 6 WILLIAM ROPERANNE OWENS 7 ROBERT GLUCK
TILCON MINERALS INC 9 TOWN OF PLAINFIELD 10 ROBERT GLUCK 1 1 STANTON GALLUP 12 - 15 EDWARD DUNCAN 16 ELAINE M NILSON 17 ADOLPH SHAGZDA 18 ANTHONY FATONEJOSEPH FATONE 19 NANCY LAMIRANDE 20 KENNETH R MOFFITT 21 CONNECTICUT DOT 22 ST JOHNS CHURCH 23 DOROTHY CARON 24 ALFRED AND EVELIN RIENDEAU 25 PAUL GELINAS AND JOAN BURNORE 26 ALBERT SR AND ANN WILCOX
LEGEND
D LOT NUMBER
-- WATERCOURSE GALLUPS QUARRY SITE
PROPERTY BOUNDARY
NOTES
BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM - CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
410 Amherst Street Nashua NH 03063
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 1-2 1000
PROPERTY BOUNDARIES AND ADJACENT LANDOWNERS
DRAWING NAM^ PROPBNDDWG |^LE NUMBER 7194 138 SCALE AS SHOW^REVISION 0 |pRAWN BY PAD loATE 5997
GB
N
LEGEND
WATERCOURSE
TO PACKERS POND (CUSS CBc)
APPROX 1 MILE WEST OF SITE
PROPERTY
CLASS Be
BOUNDARY
SURFACE WATER
CLASS BA SURFACE WATER
CLASS GE GROUNDWATER
CLASS GEGA GROUNDWATER
NOTES
1 BASE PLAN PROVIDED BY USEPADATED 14 OCTOBER 1993
DRAWING NO 707600
2 HORIZONTAL DATUM shy CONNECTICUT STATE PLANSYSTEM NORTH AMERICAN
COORDINATE DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROMPLAINFIELD TAX ASSESSORS OFFICE
TOWN OF
4 UNLESS OTHERWISE INDICATEDCLASSIFICATION IS GA
CONNECTICUT GROUNDWATER
410 Amherst Street Nashua MH 030G3
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
500 0
SCALE IN
500
FEET
1000 FIGURE 1-3
CONNECTICUT SURFACE AND GROUNDWATER CLASSIFICATION ZONES
DRAWING NAME SOILTYPEDWG
SCALE AS SfcWN [RFVISION 0 l o R A W N B Y D-fB FILE NUMBER 7194 138
G1097
LEGEND
WATERCOURSE
PROPERTY BOUNDARY
LOCATION OF PREVIOUSLY INSTALLED MONITORING WELL
NOTES
1 BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM shy CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
410 Amherst Street Nashua NH 03063
(603) 869-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
- REMEDIAL INVESTIGATION REPORT
500 0 500 1000 FIGURE 1-4
GROUNDWATER MONITOR WELLS INSTALLED BY SCALE IN FEET FUSS amp ONEILL IN 1978 AND USGS IN 1993
DRAWING NAME SWMAGDWG FILE NUMBER 7194 138
SCALE A3 SHQHW [REVISION 0 [DRAWN BY DJB |DATE 51097
bull- - n V i _raquo-A raquoraquobull bull Jpoundi _
SOURCE PLAINFIELD CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP 75 MINUTE SERIES 1983
124000 410 Amber atNashua NH
Street 03063
(603) 889-3737
0 GALLUPS QUARRY SUPERFUND PROJECT
SCALE IN MILES PLAINFIELD CONNECTICUT REMEDIAL INVESTIGATION REPORT
FIGURE 1-5 COHNgOICOT
SITE LOCATION MAP AND NEARBY INDUSTRIAL PROPERTIES
QURANGLE LOCATION NAME LOCMAPXXDWG FILE NUMBER 7194138
SCALE AS SHOWN [REVISION 0 I DRAWN BY CBG loATE 5997
1450
FIGURE 3-1 GROUNDWATER ELEVATIONS MW-101
1420 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-101S MW-101TT MW-1 01 T
FIGURE 3-2 GROUNDWATER ELEVATIONS MW-102
1450shy
OJ 2
LLJ 1445shy
O CO
1440shyMW-102B WAS NOT INSTALLED UNTIL PHASE IB
1435
LLJ _l HI DC LJJ
I QZ
O cc CD
1430shy
1425shy
1420 010195
1 041195
1 072095
1 102895 020596
I 051596
I 082396
1 120196
1 031197 061997
DATE
MW-102S MW-102TT ---pound-- MW-102B
FIGURE 3-4 GROUNDWATER ELEVATIONS MW-104
1450
CO
LLJ 1445shy
O CO lt |mdash 1440shy
lt 1435shy
LLJ _J LLJ
CC LLJ 1430shy
I Q Z D O CC C5
1425
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-104S MW-104TT
FIGURE 3-5 GROUNDWATER ELEVATIONS MW-105
1450
CO2 LLJ 1445shy
O CO
1440shy
1435shy
LLI
LU tr QJ 1430shy
I Q
D O cc O
1425shy
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-105S MW-105TT MW-105T -X- MW-105B
1450
FIGURE 3-6 GROUNDWATER ELEVATIONS MW-106
1420 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-106S MW-106TT
1450
FIGURE 3-3 GROUNDWATER ELEVATIONS MW-103
1415 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-103S MW-103TT
FIGURE 3-7 GROUNDWATER ELEVATIONS MW-107
1490
CO
x- -X
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-107S MW-107TT MW-107T -Xshy MW-107B
FIGURE 3-8 GROUNDWATER ELEVATIONS MW-108
1465shy
(02 LU
1460shy
O CO
1455shy
1450shy
LU
LU
CC LU
lt
1445shy
1440shy
Q
mdashJocc O
14j vshy^
1430 010195
1 041195
1
072095 1
102895 T T
020596 051596
DATE 082396
1 120196 031197 061997
MW-1083 MW-1 08TT MW-1 08B
1580
FIGURE 3-9 GROUNDWATER ELEVATIONS MW-109
(0 1575shy
1530 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-109S MW-109B
1470
FIGURE 3-10 GROUNDWATER ELEVATIONS MW-110S
1450 i 1 i i i 1 r 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-110S
1610
FIGURE 3-11 GROUNDWATER ELEVATIONS MW-111B
1530 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-111B
1590
FIGURE 3-12 GROUNDWATER ELEVATIONS MW-112
lt) 1580shy
149 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-1123 MW-112T MW-112B
FIGURE 3-13 GROUNDWATER ELEVATIONS MW-113
1510shy
2UJ
O m lt
1500shy
1490shy
1480shy
LU _l LJJ
CC LU
1470shy
1460shy
Q
OCC O
145degH
1440 010195 041195 072095
1 102895 020596 051596
DATE 082396
1 120196
1 031197 061997
MW-113S MW-113B
1580
FIGURE 3-14 GROUNDWATER ELEVATIONS MW-114
1460 i r 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-114S MW-114TT
150
FIGURE 3-15 GROUNDWATER ELEVATIONS MW-115
1465 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-115S MW-115TT --pound-- MW-115B
1455
FIGURE 3-16 GROUNDWATER ELEVATIONS MW-116
1425 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-116S MW-116T
FIGURE 3-17 GROUNDWATER ELEVATIONS MW-117
1480shy
CO
LJJ gto CD
1475shy
1470shy
LU LU
CC LU
1465shy
WELLS AT THIS LOCATION WERE NOT INSTALLED UNTIL PHASE 1B
O z D O CC (5
1460shy
1455 010195
1 041195 072095
I 102895
1 1020596 051596
DATE
1 082396 120196 031197 061997
MW-117S MW-117TT
FIGURE 3-18 GROUNDWATER ELEVATIONS MW-118
1465shy
LU 1440shy
LLJ
CC LU 1435shy WELLS AT THIS LOCATION WERE
I Q Z D O CC CD
1430shy
1425shy
NOT INSTALLED UNTIL PHASE 1B
1420 010195
1 041195
I 072095
1 102895 020596
1 051596
DATE 082396 120196 031197 061997
MW-118S MW-118TT
FIGURE 3-19 GROUNDWATER ELEVATIONS MW-119
1475shy
CO2 LJJ
1470shy
o m
1465shy
1460shy
UJ_i UJ cc LJJ
1455
1450shy
WELLS AT THIS LOCATION WERE NOT INSTALLED UNTIL PHASE 1B
Q Z
O cc O
1445shy
1440 010195 041195
1 072095
I102895
I I 020596 051596
DATE
1 082396
i 1 201 96 031 1 97 061 997
MW-119S MW-119TT
1455
FIGURE 3-20 GROUNDWATER ELEVATIONS SW-3SD
1425 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
SW-3S SW-3D
Originals in color
VERTICAL
PROJECTED FOOTPRINT of FORMER PRIMARY
DISPOSAL AREA
MILL BROOK
NOTES (1)
(2)(3)
THE SAME CONTOUR INTERVALS ARE USED FOR THE SHALLOW AND DEEP MAPS
WATER LEVEL DATA COLLECTED 2-2-95 VERTICAL EXAGGERATION = 10X
410 Amherst Street THIS FIGURE SHOWS ONLY THE PREDOMINANT OVERBURDEN GROUNDWATER FLOW PATHWAYS WHICH ORIGINATE Nashua NH 03063 IN THE VICINTY OF THE FORMER PRIMARY DISPOSAL AREA AS VIEWED FROM THE EAST (603) 889-3737
ALTHOUGH THIS DEPICTION IS BAStU ON PlEZOMETRlC HEAD OAiA (MEASURED ON FEBRUARY 2 1335) THIS FiGURE DOES NOT SHOW EVERY POSSIBLE FLOW PATHWAY WITHIN THE OVERBURDEN AQUIFER THE UPPER SURFACE REPRESENTS THE SURFACE OF THE WATER TABLE THE LOWER SURFACE REPRESENTS GALLUPS QUARRY SUPERFUND SITE A PLANE DEFINED BY THE PIEZOMETRIC HEAD AS MEASURED IN WELLS WHICH ARE SCREENED IN THE LOWER PORTION OF THE OVERBURDEN AQUIFER THE LOWER PLANE DOES NOT REPRESENT THE LOWER BOUNDARY OF THE OVERBURDEN AQUIFER AND NEITHER PLANE IS GEOLOGICALLY SPECIFIC PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 3-21
PREDOMINANT OVERBURDEN GROUNDWATER FLOW PATHWAYS IN NORTHERN PORTION OF STUDY AREA
DRAWING NAME FLOWPATHDWG IFILE NUMBER 7194 138
SCALE NT5 JREVSION 1 JDRAWN BY CBG [DATE 6-9-97~
lt 4 Original includes color coding
10s r SW-17SandMW105S Ho5 SW-17D and MW105TT
P 1 V |
1deg4 i
4 mI U 5 k 4 3
i i f J |103 1I Un |
|io2 bull m2
bull I U = i ii gtv o r
BDL mdasha I bullM BDL a i i c CM ltD 0 ltj at agt c c at at T c I 1 I i i i
SW-13 c MW105S I10s pound
1I Un =
m4
104 I U sect
J 1I 3 bull PCE -m
H103| IU sect bull TCA
2 ^ TCE 102
m
I bull 1 2-DCE A i 1
T VINYL CHLORIDE 1 0 ^h
bull A1
10deg BDL = BELOW DETECTION LIMIT 10deg 1 U = V 3 X
=
ni-M ^ ^ ^ laquote BDL 0 V o0 CV tfi _ CO CXgt o0 ogt ogt 2 C oraquo oraquo cn O) O lt C
i- r- -3 4 1 1995
MW105TT MW107TT 105 105
E pound
i shy104
2 = 104 I = ^^to^f^P 410 Araherst Street bull^OJfcCfe Nashua NH 03063 103 103 ^raquo^^^j^ (603) 889-3737 f bull 1
- T T T shy ~ A102 i1 bull bull S 102
GALLUPS QUARR y SUPERFUND SITE I 1
PLAINFIELD CONNECTICUT REMEDIAL INVEi iTIGATOJV REPORT 10 101
i 1 FIGU RE 5 110deg i = 10deg
BDL laquo BDL VOC CONCENTRATION CHANGES VERSUS TIME M
^ i DOWNGRADIENT FROM FORt ilER PRIMARY DISPOSAL AREA sect o ^ O
^
-5lt 5amp -s= z1
1995 1995
Original includes color coding
CO
NC
ENTR
ATIO
N (
ppb)
IU sect MW102S
s 105 MW102TT
104 1 i 104
103 1 103
102 I I A sect 102
1
A
T
1 101
10deg i 10deg
nni BDL +shytr a O o
1995 1995
bull PCE
bull TCA A TCE
bull 12-DCE
T VINYL CHLORIDE
MW101TT 105
104
103
102
10deg
BDL
1995
410 Amhersl Street Nashua NH 03063
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 5-2
VOC CONCENTRATION CHANGES VERSUS TIME DOWNGRADIENT PORTION OF PLUME
BDL = BELOW DETECTION LIMIT
s
104 tmdash a IU I
1 IU103 U-o 1F= E
i 105 to2 tmdash r 1 1deg1 i~ deg 10degL
BDL Emdash oS
105 i
104 i
103 i
102 bull
101 1
10deg
BDL 0S
105 9
104 B
103 I
102 i
101
10deg 1
BDL OCOogt
^ 00 ogt
^ra lt cltJgt
C O 0 0
0gt
MW-A
4 bull
1 1 1
co 01
MW-B
_J 1 1
1
i CO
8)
MW-C
11 1
lt lt
CO CO ogt
bullbull
laquoftr i i bull i
mn
Tbull1
bullbull
bull i
9
bull
bullM bullM bullbull- 1
egt lt t a) a
aai Tshy^
WM cN gjcI) lt J1
bull 1
bull 11 1
MM bullMl bullfr- 1
c4 0aigt C
t bullgt araquo lt raquo
T ^
Original includes color coding
10 |
-iM 10 s
-irvS 10 |
nn2 10
bullm1 bull
1UJ
oni AZs
^^^f
MW116T
A a
A =J =3
1995
bull
bullA
PCE
TCA
TCE
1 2-DCE
sect
1
s
I I 1
A gti
T VINYL CHLORIDE
BDL = BELOW DETECTION LIMIT
410 Amherst Street bull^OJUV^ Nashua NH 03063 ^raquo^^ ^jj^ (603) 889 3737
nmranmini x
GALLOPS QlARRy SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 5-3
VOC CONCENTRATION CHANGES VERSUS TIME AREA NORTH-NORTHEAST OF PLUME
I Original includes color coding
SW-17S MW102S and MW102TT
410 Amherst Street Nashua NH 03063
bull PCE (603) 889-3737
bull TCA A GALLUPS QUARRY SUPERFUND SITE TCE
PLAINFIELD CONNECTICUT REMEDIAL INVESTIGATION REPORT
BDL = BELOW DETECTION LIMIT
FIGURE 5-4
EVALUATION OF BIODEGRADAT10N AND RAINWATER DILUTION RATES IN VOC PLUME
(D NOTE FORWELLS MW102S and MW102TT ONLY JANUARY and NOVEMBER 1995 DATA ARE PLOTTED
SOURCE PLAINFIELD CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP 75 MINUTE SERIES 1983
410 Amherst Street 124000 Nashua NH 03063
(603) 889-3737
0 GALLUPS QUARRY SUPERFUND PROJECT
PLAINFIELD CONNECTICUT SCALE IN MILES REMEDIAL INVESTIGATION REPORT
comacncur FIGURE E-l
SITE LOCATION MAP DRAWING NAME ELOCDWG FILE NUMBER 7194-138
QUADRANGLE LOCATION
SCALE AS SHOWN REVISION 0 I DRAWN BY PAP [DATE 5997
Gallups Quarry Superand Project - RI Executive Summary
completion of drilling activities the Phase IB groundwater sampling task and the fourth quarter
1995 Long-Term Monitoring sampling event were performed simultaneously in November 1995
Seven Data Reports have been submitted to the EPA for the following Long-Term Monitoring
Program sampling events the second and third quarters of 1995 all four quarters of 1996 and
the first quarter of 1997 (ESE 1996a 1996b 1996c 1997a 1997b) The draft RI Report was
submitted to EPA on March 15 1996 (and revised and resubmitted October 22 1996) and included the results of the fourth quarter of 1995 sampling event On March 29 1996 the
following two deliverables were submitted to EPA Development and Initial Screening of Alternatives Report and Detailed Analysis Work Plan The draft Feasibility Study was submitted
to EPA on January 27 1997 This RI Report describes the methods and findings of both the Phase 1A and IB field studies and includes data collected during the April July and November
1995 February May August and November 1996 and February 1997 Long-Term Monitoring
sampling events
E2 Site Background E21 Area Description
The 29-acre Gallups Quarry Site is located on the north side of Tarbox Road in the Town of
Plainfield Windham County Connecticut The Site which is currently vacant is bounded by
wooded areas and wetlands associated with Mill Brook (which flows from east to west
approximately 250 feet north of the Site) single-family residences and several commercial
properties Approximately 700 feet north of the Site on the opposite side of Mill Brook is an industrial park which contains an Intermark Fabric Corporation facility (formerly the Pervel
Industries flock plant) and a Safety Kleen Corporation accumulation facility Further north of the
industrial park are several presently vacant mill buildings which were previously occupied by various manufacturers including Pervel Industries and the InterRoyal Corporation The Plainfield sewage treatment plant which discharges to Mill Brook and its major tributary (Fry Brook) is
located approximately 1800 feet northwest of the property
E22 Site Operational History
Limited information is available regarding the early operational history of the Site Historical
aerial photographs and records at the Town of Plainfield Assessors office indicate that in 1951
the Site was owned by a Mr Johnson and that some quarrying activities were underway in the
southern portion of the Site In 1964 the Site was purchased by C Stanton Gallup Although
detailed usage of the Site from 1964 through 1977 is poorly documented records indicate that the
Site was used as a source of aggregate and was occupied by the Connecticut Department of
Transportation (CTDOT) who were operating an asphalt batching plant
5797WTgtdocsgallupfsfinltextexec8ummri060997 E-3 QST Environmental
Gallups Quarry Superfund Project - RI Executive Summary
As a result of complaints from neighboring residents the CTDEP and the Connecticut State
Police initiated an investigation of the Site in January of 1978 The CTDEP investigation
concluded that the Site was used from the summer of 1977 until December 1977 for unlicensed
waste disposal Evidence collected by CTDEP indicates that Chemical Waste Removal Inc
(CWR) of Bridgeport Connecticut transported drummed and bulk liquid waste material to the
Site These materials reportedly included a variety of industrial wastes
Emergency clean up efforts were performed during the summer of 1978 under the direction of the
CTDEP and the Connecticut State Police This involved the removal and off-site disposal of
1584 drums 5000 gallons of free liquid and 2277 cubic yards of contaminated soil from three
distinct locations on the Site The drums as well as liquid waste and contaminated soil were
removed from the Primary and Secondary Disposal Areas located in the northern portion of the
Site Remedial measures performed at the Seepage Bed reportedly located in the central portion
of the Site included the excavation of contaminated soil and in-situ treatment of remaining soils
through the addition of 20 tons of lime A buried inverted dump truck body was also reportedly
removed from the Site In addition to these remedial activities mine detectors were utilized to search for additional buried drums There was no evidence of additional buried drums and it
was believed that all drums were recovered during the cleanup operations
Since the 1978 cleanup operations the Site has been vacant although there are some indications
that the Site has been utilized by trespassers for recreational purposes
E23 Summary of Previous Investigation
ations and sampling events were conducted at the Gallups Quarry Site The significant previous
investigations are as follows
bull A general site investigation performed on behalf of the State of Connecticut (Fuss amp
ONeill 1979) which included the installation of 22 monitoring wells 19 test pits (13
of which were completed as shallow monitoring wells) and the collection of surface
water and sediment samples The investigation was completed within several months
of the States remedial efforts described above Groundwater from monitoring wells
and nearby residential wells as well as surface water from Mill Brook was sampled
several times from the period of July to December 1978
bull Various CTDEP monitoring events for groundwater surface water and sediment
occurred from 1979 until 1993 Sampling events were conducted in October 1979
January and November 1980 April and October 1981 April 1982 and December
1983 CTDEP also performed a biodiversity survey in 1985 in an effort to evaluate
potential impacts to the Mill Brook wetland In addition CTDEP also conducted
sampling anq (analysis of neighboring residential wells in 1992 and 1993
5797wpdocraquogallupf8finlaquoltextexecsummri060997 E-4 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
bull A Hazard Ranking System (HRS) Study was completed in 1987 by NUS Corporation
foi ZPA The Study included the collection of water samples from two existing
moiiitoring wells and three surface watersediment locations
bull A review of historic aerial photographs of the Study Area was performed by the
Bionetics Corporation on behalf of the EPA Photographs dating back to 1951 were
included in the review which was published in 1990 (Bionetics Corp 1990)
bull In cooperation with EPA the USGS performed a geohydrologic investigation at the
Study Area in 1993 This investigation included geophysical surveys (EM-34 and GPR) to characterize various subsurface features One monitoring well was installed
bull In 1993 the US Fish and Wildlife Service performed a field study to characterize the
habitats within the Study Area The study was finalized in 1995
bull Various sampling events were conducted in 1989 and 1993 on behalf of the EPA During these sampling events groundwater from existing monitoring wells and nearby
residential wells as well as surface soil samples were collected for analysis
The significant findings of these investigations are summarized as follows
bull The initial study completed at the Site by Fuss amp ONeill in 1979 concluded that
groundwater in the vicinity of the former disposal areas had been impacted by certain
volatile organic compounds (VOC) and metals A well-defined groundwater plume which contained these various constituents extended in a northwest direction away
from the Site
bull Periodic CTDEP sampling events from 1979-1982 indicated the wells downgradient of
the former disposal areas consistently showed detectable levels of constituents similar
to those disposed of on-site The results of CTDEP sampling events indicated that
nearby residential wells had not been impacted by the Site
bull The USGS study provided an updated geological characterization of the Study Area
and suggested the potential presence of a bedrock fault zone located in the vicinity of
the Former Seepage Bed
bull The results of the 1989 and 1993 sampling events generally confirmed the findings of
previous groundwater quality investigations and indicated that VOC concentrations
decreased significantly in the period between 1982 and 1993
5797wpdocgglaquollupfsfiiultextexecnjmmri060997 E-5 QST Environmental
Gallups Quarry Superfiotd Project - RI Executive Summary
To supplement historical data and data obtained during the Phase 1A field program a CTDEP file
search was performed to obtain information pertinent to groundwater contamination for industrial
properties neighboring the Site The available information indicates that
bull two separate companies Pervel Industries and InterRoyal Corporation operated
manufacturing facilities at locations approximately 2500 feet north of the Site
bull Pervel Industries also maintained a second facility (a fabric flock plant) located
approximately 1000 feet north of the Site across Mill Brook
bull there have been documented releases of 111-trichloroethane (TCA) and toluene at
the northern-most Pervel plant
bull contaminated soil and sediment associated with a 1985 spill of 111-TCA at the
northern-most Pervel facility was stored in an impoundment located on the eastern
(upgradient) side of the Pervel flock plant property
bull the contaminated soilsediment impoundment was located approximately 1000 feet
from the northern end of the Site
bull the results of historical groundwater monitoring at the former Pervel flock plant
located a few hundred feet north of the Site show the presence of elevated
concentrations of several VOC including tetrachloroethene (PCE) and TCA
E3 Summary of Remedial Investigations Phase 1A Field Investigations
In order to maximize the efficiency of the Site characterization program for the Gallups Quarry
Site multiple phases of data collection and evaluation were performed during the Phase 1A field
program Screening level surveys completed during the initial weeks of the field program
utilizing fast-turnaround data generation and evaluation techniques were used to focus data
collection efforts during the latter part of the Phase 1A field program The screening surveys
included
bull A visual site reconnaissance involving transit by foot and direct observations and
photographic documentation of significant features along approximately 39000 feet of
trend lines covering the entire Site
bull Geophysical surveys including electromagnetic terrain conductivity (EM) and
magnetometer surveys along 25-foot spaced trend lines totalling approximately
5797wpdocBgallupf8finaltextexeclaquoummri060997 E-6 Q5T Environmental
Gallups Quarry Superfimd Project - Rl Executive Summary
39000 feet in length and covering the entire Site follow-up EM-31 and
magnetometer surveys and a test pit program in three areas where anomalies were
observed and a seismic refraction survey west of the Former Seepage Bed
bull A microwell survey which included the collection of 126 groundwater samples from
multiple depths at 50 locations within the Study Area field gas chromatograph
analyses of all of these samples for an indicator list of 8 VOC laboratory analyses of
121 of these samples for metals and 12 of the samples for VOC and
bull A soil vapor survey which involved the collection of soil vapor samples from 106
locations throughout the Site and on-site analyses for an indicator list of 8 VOC
Based on these screening level and historical data a groundwater monitoring well installation
sampling and analytical program was designed The program as approved by EPA included the
following
bull The installation of 5 wells at 2 designated background locations These wells include
a shallow overburden and a bedrock well in the northern portion of the Site and two
overburden wells (screened at the water table and in a deeper till horizon) and a
bedrock well in the southern portion of the Site Background soil and groundwater
samples were collected from these locations
bull The installation of 19 wells at seven locations downgradient (northwest) of the Former
Primary and Secondary Disposal Areas to assess and define the boundaries of a
contaminant plume identified during the microwell survey These wells included 17
overburden wells and two bedrock wells
bull The installation of six wells at three locations located north and east of the Former
Primary Disposal Area to assess groundwater quality and flow directions in these
areas These wells included five wells screened in overburden and one in bedrock
bull The installation of two bedrock wells and one overburden well at two locations in the
vicinity of the Former Seepage Bed This included one bedrock well placed within an
inferred bedrock faultfracture zone to assess the zones potential to act as a preferred
contaminant transport pathway
bull The installation of five wells at two locations in the southern portion of the Site to
assess very limited screening-level VOC detections in this portion of the property
These wells include four overburden wells (two shallow and two top-of-till) and one
5797wpdoclaquoglaquollupftfinlaquolte)rtexecraquoummri060997 E-7 QST Environmental
Gallups Quarry Superfund Project - RI Executive Summary
bedrock well In addition six groundwater piezometers were installed to assess groundwater flow directions in the southern portion of the Study Area gtmdashr
Samples from three of the newly installed wells (MW102TT MW106TT and MW116T) were analyzed for Appendix IX parameters Samples from the remaining newly installed monitoring wells and three existing wells (SW-9 SW-10 SW-12) were analyzed for Target Analyte ListTarget Compound List (TALTCL) parameters Twelve nearby residential wells were also sampled for TALTCL parameters (although VOC were analyzed using EPA method 5242) In addition to the monitoring well installation and groundwater sampling program outlined above the following tasks were performed during the Phase 1A field program
bull Air quality monitoring to establish ambient air quality prior to and during the intrusive investigations A total of eight air monitoring stations were established at locations within and at the Site perimeter
bull Water-level measurements were recorded to assess horizontal and vertical groundwater flow directions and aquifer testing (including evaluations of the remaining existing monitoring wells) using slug tests was conducted to assess the hydraulic conductivity of the aquifer
bull Soil boring programs within the three known disposal areas to assess the nature and extent of residual contamination A total of ten soil borings were completed at the three areas Each boring was continuously sampled and terminated at auger refusal Selected samples were submitted for laboratory analysis for TALTCL parameters based on lithology depth and photoionization detector (PID) headspace readings as set forth in the Work Plan
bull Surface watersediment sampling was performed at 17 locations including Mill Brook Fry Brook Packers Pond and in an unnamed pond on Tarbox Road just south of the entrance to the Site In addition wetland soil samples were collected from 10 locations within the Study Area All samples were submitted for analysis for TALTCL parameters
bull Federal and State jurisdiction^ wetland delineations were performed
Phase IB Field Investigations The data collected during Phase 1A was supplemented with the following additional investigative activities conducted during the Phase IB field investigation
5797wpdocsgallupfsfiMltextexecsummri060997 E-8 QST Environmental
Gallups Quarry Superand Project - RI Executive Summary
bull Quantitative air monitoring for site-specific compounds in the vicinity of the Former
Prirary Disposal Area
bull Collection and analysis of soil samples from six additional soil borings in the Former
Primary Disposal Area to more fully characterize the extent of residual VOC and PCB
contamination
bull The installation of seven additional groundwater monitoring wells and one additional
piezometer to obtain additional groundwater data from the downgradient portion of the
plume and from the northnorthwest portion of the Site The monitoring wells
included (3) two well clusters and (1) bedrock well
bull Collection of groundwater samples from each new monitoring well and from five
existing wells on the former Pervel facility and analysis of these samples for VOC to confirm the downgradient extent of the plume originating in the Former Primary
Disposal Area and
bull The performance of constant flow tests consisting of short-term pumping tests on selected groundwater monitoring wells to supplement Phase 1A hydraulic conductivity
data so that groundwater velocities and transport rates and aquifer yield could be
more accurately determined
Long-Term Monitoring Program
A Long Term Monitoring Program was initiated upon completion of the Phase 1A field investigation The Long-Term Monitoring Program includes the quarterly collection and analysis
of groundwater and semi-annual collection and analysis of surface water and nearby residential
well samples Data from eight quarterly sampling rounds (performed in April July and
November 1995 February May August and November 1996 and February 1997) are presented
and discussed The Conceptual Model discussion is based on the 1995 quarterly sampling rounds
Any minor adjustments to the Conceptual Model resulting from later monitoring rounds are
addressed in the FS
E4 Conceptual Model of the Study Area E41 Physical Characteristics E411 Physiography
The Site is located along the eastern border of the Quinebaug Valley Lowland The region is
characterized by relatively low relief and numerous glacial features The regional landscape is
5797wpdoc8glaquollupfBfinaltextexecraquoummri060997 E-9 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
significantly influenced by the structure of the underlying crystalline metamorphic bedrock The
topography of the Site is highly irregular primarily due to past quarrying operations including
numerous overgrown mounds of earthen materials and excavated depressions The ground
surface on the Site generally slopes from the east to the west and to a large degree is controlled by the underlying bedrock surface North and west of the Site the ground surface elevation
decreases in the Mill Brook floodplain which is described as a low lying heavily vegetated
wetland
E412 Geology
The overburden deposits in the area consist of materials deposited as a result of glacial processes during the Pleistocene epoch A range of glacially-derived materials including till meltwater or
stratified drift deposits and post-glacial deposits of floodplain alluvium comprise the major
surficial geologic units in the vicinity of the Site The significant surficial deposits encountered
within the Study Area during the RI are till and stratified drift Stratified drift deposits can be
further broken down into coarser-grained or finer-grained components The Study Area is
dominated by coarser-grained deposits which represent various ice-contact or outwash features associated with the retreat of the ice-mass Finer-grained components also exist to a limited
extent within the Study Area and are the result of lacustrine deposition which occurred when
low-lying areas were inundated by a glacial lake Much of the Sites overburden geology
represents the transition of depositional environments as the glacier progressively retreated from
the area Although alluvial floodplain deposits were encountered at locations within the present
Mill Brook floodplain the significance of these deposits is minor
The thickness of the stratified drift deposits range from non-existent in the vicinity of bedrock
outcrops in the eastern portion of the Site to approximately 70 feet The overburden thickness
increases in response to a decrease in the elevation of the bedrock surface Till was encountered just above the bedrock surface at nearly every location The till horizon ranges in thickness from
approximately 10 to 20 feet with the thickest accumulations located along bedrock highs
Surficial exposures of glacial till were observed on the Site The till is relatively dense and is
comprised of a fine sandy matrix with abundant gravel cobbles and boulders
Bedrock in the vicinity of the Site mapped as a lower member of the Quinebaug Formation
consists of hornblende gneiss biotite gneiss and amphibolite and is strongly faulted and folded
exhibiting varying degrees of mylonitization Geophysical surveys performed prior to and during
the Phase 1A field program indicate that a northwest-trending fracture zone may extend across the
central portion of the Site Based on the drilling program depths to bedrock range from zero to
83 feet below ground surface within the Study Area Bedrock elevations are greatest in the
eastern central portion of the Site and decrease to the north and west and to a lesser degree to
the south
5797wpdocsgallupfsfinaltextexecsummri060997 E-10 QSTEnvironmental
Gallups Quarry Superfund Project - RI Executive Summary
E413 Hydrogeology
E4131 Hydraulic Conductivity
The hydraulic conductivity distributions within the overburden and bedrock formations were
evaluated through the performance of constant flow (pumping) tests and rising and falling head
slug tests Hydraulic conductivity measurements indicate that coarse-grained stratified drift
deposits in the lower portion of the aquifer are the most permeable subsurface materials in the Study Area with a mean hydraulic conductivity of 0005 centimeters per second (cms) The
highest hydraulic conductivities were found in the lower portion of the aquifer northwest of the Former Primary Disposal Area where the mean hydraulic conductivity is 0037 cms The mean
hydraulic conductivity of the finer-grained deposits in the upper portion of the aquifer is about
0001 cms
The mean hydraulic conductivity for the till wells (000047 cms) is a factor of ten less than the
average value for coarse stratified drift and varies between 00002 cms and 0002 cms The till
appears to be hydrogeologically distinct from the other overburden deposits and on the average
provides increased resistance to groundwater flow This added resistance is not considered to be
significant however because the consistency of the till and overburden deposits are highly
variable and the hydraulic conductivity contrast is relatively small The slug test results for the
bedrock wells yield the lowest (000018 cms) average hydraulic conductivity
E4132 Groundwater Flow
Horizontal Flow
Overburden groundwater flow south of the Former Seepage Bed is primarily east to west and is
influenced by two factors (1) the slope of the bedrock surface which defines the base of the
unconsolidated deposits and (2) regional hydrologic drainage patterns The average east-west horizontal hydraulic gradient in the southern portion of the Study Area is approximately 001 feet
per foot (feet change in piezometric head per horizontal foot of distance)
In the northern portion of the Study Area three hydrogeologically distinct zones exist South of the Former Primary and Secondary Disposal Areas the hydraulic gradient is steep (approximately
003 feet per foot) and is strongly influenced by the dip of the bedrock surface (01 feet per foot)
The saturated thickness increases from zero south of well MW109 to about 20 to 30 feet near the
former disposal areas North-northwest of the former disposal areas the hydraulic gradient
lessens significantly to a range of 00003 to 00007 feet per foot representing a factor of 40 to
100 reduction North-northeast of Mill Brook the hydraulic gradient is about 0007 feet per foot
Available data indicate that currently northwest of the railroad tracks groundwater flow in the middle to lower portions of the aquifer converges from the northeast and southwest toward a
centerline area generally defined in the downgradient direction by wells MW105 MW102 and
5797wpdoclaquoglaquoliupfraquofirultextexeclaquoummri060997 E-ll QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
MW101 The flow direction near these wells is from the former disposal areas to the northwest
Northeast of this centerline groundwater flows in a southwesterly direction from the vicinity of
Mill Brook and the former Pervel flock plant North of Mill Brook and west of the railroad
tracks the predominant groundwater flow direction becomes more westerly
No significant seasonal changes in horizontal groundwater flow directions were observed in the
Study Area Groundwater levels were generally highest in January 1995 and decreased by about
two feet through the period ending on July 11 1995 Levels then increased by about one foot
from July to November
General overburden groundwater pathlines for the northern portion of the Site are shown on
Figure E-2
Groundwater in bedrock moves primarily in a westerly direction south of the Former Seepage
Bed while in the northern Study Area the predominant bedrock flow component is toward the
northwest In both areas the hydraulic gradient is on the order of 002 feet per foot Groundwater in bedrock near the Former Seepage Bed flows to the northwest and exhibits no apparent
influence from the locally identified fracture zones
Vertical Flow
Vertical flow of groundwater is an important component in the upper several feet of the bedrock
unit Water level measurements indicate that groundwater is discharging from bedrock into the
overburden at every location measured except MW109 In most clusters the vertical hydraulic
gradient between bedrock and overburden is an order of magnitude greater than the horizontal
gradient
In the overburden aquifer the downward vertical flow component is significant within shallow
deposits near the Former Primary Disposal Area (wells MW107 MW108 and MW116) and the
upward flow is important in the upper portion of the aquifer near Mill Brook The downward
groundwater flow within the Former Primary Disposal Area appears to be primarily associated
with infiltration of precipitation and collection of surface water runoff from upland areas This
causes VOC concentrations to be highest in the middle to lower portions of the aquifer Stream
5797wpdocsgallupftfinaltextexecsummri060997 E-12 QST Environmental
N
LEGEND
WATERCOURSE
PROPERTY BOUNDARY
bullPIEZOMETRIC HEAD CONTOUR LOWER PORTION OF AQUIFER NOVEMBER 6 1995 (FEET)
GROUNDWATER PATHLINE
NOTES
1 BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM - CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
400 400 800
SCALE IN FEET
410 Amherst Street Nashua NH 03063
(603) 889-3737 UmHOHHM
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE E-2
SJjTff WIDE GROUNDWATER FLOW DRAWING NAM6 RIWIDEFWDWG FILE NUMBER 7194 138
SCALEAS SHAWN REVISION 1 DRAWN BY DJB DATE 5997
Gallups Quarry Superfiind Project - RI Executive Summary
piezometer data and groundwater flow modeling indicate that Mill Brook generally gains water
from the overburden aquifer within the Study Area
E414 Ecology
Wetlands delineations were performed to the extreme northern and western boundaries of the
Study Area up to the Mill Brook channel using both the State of Connecticuts accepted criteria
(which focuses on soil types and hydric soil characteristics) and the Federal criteria using US
Army Corps of Engineer methods (which includes the examination of vegetation hydrology and
soils) Most of the wetlandupland boundary occurs along the edge of a steep grade The sharp
relief produces a narrow transition between uplands and wetlands The delineated lines reflect
this as the State and USACOE wetland boundaries coincide at nearly every location With the
exception of an area intersecting a small portion of the Site at the northernmost edge of the
property east of the former disposal areas no wetland areas were identified on the Site
A preliminary identification of plant and animal species present in the Study Area was conducted during the wetlands delineation A limited number of wildlife species were observed Numerous
plant species were identified over the heavily vegetated Study Area No endangered species were
observed nor are reported to reside in the Study Area
E42 Nature and Extent of Contamination
E421 Contaminant Source Investigation The following summarizes the findings of contaminant source investigations conducted during the
RI program
bull Previous remedial activities have completely removed the waste materials (intact drums and bulk liquid waste) from the Site
bull The Former Seepage Bed and the Former Secondary Disposal Area contain
little residual contamination from the disposal activities which occurred in the
late 1970s
bull Residual levels of contamination primarily VOC and PCB were measured in
the Former Primary Disposal Area In general the highest levels of VOC are
located at or just below the groundwater table in native soils immediately
beneath the fill materials and diminish rapidly with depth Low levels of
PCB were detected primarily within shallow fill materials
5797wpdocraquogallupftfinlaquoltextexecraquoummri060997 E-14 QST Environmental
Gallups Quarry Superfiutd Project - Rl Executive Summary
bull Other than the three known former disposal areas and the remains of a
former CTDOT asphalt plant no other disposal areas were found to exist on -
the Site
E422 Groundwater Quality
Groundwater quality data collected during the Remedial Investigation indicate the following
bull No significant groundwater contamination was detected within the overburden
or bedrock units in either the southern Study Area or in the vicinity of the
Former Seepage Bed
bull In the northern Study Area a narrow low to moderate-concentration VOC
plume was detected in the overburden aquifer extending from the vicinity of
the Former Primary Disposal Area to the northwest towards Mill Brook
TCA and DCE were consistently detected at all locations along the plume
centerline at concentrations as high as 240 ppb and 1300 ppb respectively
bull Comparison of present concentrations with historical data indicate that VOC
levels are significantly decreasing with time From 1978 through 1995 TCA
TCE and PCE concentrations have decreased on the average by more than a
factor of two every two years representing environmental half-lives of less
than two years
bull The size and orientation of the plume are in excellent agreement with the
established groundwater flow directions
bull Available information indicates that the leading edge of the VOC plume
associated with the Former Primary Disposal Area is located in the vicinity of
monitoring well clusters MW-102 and MW-101 Concentrations of TCA and
DCE reduce to below MCLs at MW-101 Contaminant migration rates also
support this delineation of the front of the site-related VOC plume
bull Increasing PCE detections in the downgradient portion of the plume exhibit
inconsistencies with calculated migration rates from the Site Groundwater
flow directions VOC transport rates and historical concentration trends
indicate that PCE detections in wells MW118 MW116 MW103 MW118
MW102 and MW101 may be associated with contaminant transport from the
former Pervel flock plant However it is also possible that the PCE
detections at locations MW102 and MW101 are attributable to the former
disposal areas In addition contaminated groundwater from Pervel may have
5797wpdocsgal]upfraquofinaltextexeclaquoummri060997 E-15 QST Environmental
Gallups Quarry Superjund Project - RI Executive Summary
also contributed TCA TCE DCE and vinyl chloride to the site related VOC
plume
Results of surface watersediment sampling and analyses stream piezometer measurements and groundwater flow modeling indicate that some discharge
of the shallow portion of the plume into Mill Brook is occurring However
the concentrations of VOC detected in the brook are well below those
reported to cause adverse effects in fish or wildlife
Bedrock is not considered a preferred pathway for contaminant migration due
to its characteristically low hydraulic conductivity and the predominantly
upward component of groundwater flow from bedrock to overburden which
exists throughout the Study Area
5797wpdocsgallupftfinlaquoltcxtexec8ummri060997 E-16 QfT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents
Section Page
10 Introduction bdquo 1-1
11 Purpose of the Report 1-1 12 Report Organization 1-2
13 Site Background 1-3 131 Area Description Demography and Land Use 1-3 132 Operational History 1-5
133 Summary of Previous Investigations 1-7
20 Field Investigations 2-1
21 Site Survey 2-1
211 Initial Site Survey 2-1
212 As-Installed Survey 2-1
22 Site Reconnaissance 2-2
221 Visual Observations of the Ground Surface 2-2
222 Air Quality Survey 2-2
223 Exclusion Zone Identification 2-4
224 Project Support Measures 2-4
225 Identification of Sensitive Human Receptors 2-5
23 Geophysical Surveys 2-5
231 Electromagnetic Terrain Conductivity (EM) Survey 2-7 232 Magnetometer (MAG) Survey 2-7
233 Additional EM and MAG Surveys 2-8
234 Seismic Refraction Survey 2-8
24 Groundwater Sampling Using Temporary Well Points 2-9
25 Soil Gas Survey 2-12
26 Soil Borings at Disposal Areas 2-15
261 Phase 1A Soil Borings 2-15
262 Phase IB Soil Borings 2-16 27 Installation of Monitoring Wells and Background Soils Sampling 2-17
271 Phase 1A Monitoring Well Placement-Rationale 2-19
272 Phase IB Monitoring Well Placement-Rationale 2-21
273 General Monitoring Well Installation Techniques 2-22
274 Stream Piezometers and Gauges 2-24
5797wpdocsgalluprifinaltextmarterrifhl061297 i QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
Table of Contents (continued)
275 Groundwater Piezometers 2-25
28 Aquifer Parameter Testing 2-25
281 Grain Size Analysis 2-25
282 Slug Tests 2-26
283 Constant Flow Tests 2-26
29 Groundwater Sampling 2-26
291 Monitoring Wells 2-27
292 Residential Wells 2-29
210 Surface Water and Sediment Sampling 2-29
211 Wetland Soil Sampling 2-31
212 Evaluation of Existing Monitoring Wells 2-31
213 Ecological Assessment 2-32
2131 Wetland Delineation 2-32 2132 Plant and Wildlife Survey 2-33
214 Test Pit Explorations 2-33
30 Physical Characteristics of the Study Area 3-1
31 General Characteristics 3-1
311 Regional Physiography 3-1
312 Study Area Physiography 3-1
313 Surface Water Features 3-2
314 Climate 3-3
32 Geology 3-3
321 Regional Surficial Geology 3-3
322 Local Surficial Geology 3-4
323 Regional Bedrock Geology 3-7
324 Local Bedrock Geology 3-8
33 Hydrogeology 3-9
331 Hydraulic Conductivity 3-9
332 Groundwater Flow 3-10
34 Ecology 3-17
341 Wetland Delineation 3-17
342 Plant and Animal Survey 3-19
40 Nature and Extent of Contamination 4-1
41 Contaminant Source Investigation 4-2
5797wpdocsggtlluprifinaltextmasteiTifhl061297 ii QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
Table of Contents (continued)
411 Visual Site Reconnaissance 4-2
412 Soil Vapor Survey 4-4
413 Geophysical Investigations and Test Pits 4-5
414 Background Soils 4-6
415 Soils From Former Known Disposal Areas 4-7
416 Contaminant Source Investigations Summary 4-15
42 Groundwater Quality 4-17
421 Temporary Well Point Investigation 4-17
422 Groundwater Monitoring Wells 4-18
423 Residential Wells 4-26
43 Surface Water Sediment and Wetland Soils 4-27 431 Surface Water 4-27
432 Sediment 4-31
433 Wetland Soils 4-32
44 Air Quality 4-34
441 Baseline Air Quality Survey 4-34
442 Perimeter Air Monitoring 4-34
45 Potential Sensitive Human Receptors 4-35
50 Contaminant Fate and Transport 5-1
51 Theory 5-1
511 Advection by Groundwater Flow 5-1
512 Dispersion 5-3 513 Advection Due to Fluid Density Differences 5-5
514 Biological and Chemical Degradation 5-5
515 Volatilization 5-7
516 Aqueous Solubility 5-7
52 Study Area-Specific Characteristics 5-7
521 Retardation Factors 5-7
522 Chemical Migration Rates 5-9
523 Time-Dependent Concentration Reductions 5-14
5797wpdocBg8lluprifinaltextmlaquo8terrifhl061297 Hi QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
60 Summary and Conclusions 6-1
61 Conceptual Model of the Study Area 6-1
611 Geology 6-1
612 Hydrogeology 6-2
613 Nature and Extent of Contamination bdquo 6-5
70 References 7-1
5797wpdocsgnlluprifinlaquoltextmasterriftil061297 Jy QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Table of Contents (continued)
List of Tables
Table 1-1 Summary of Results of Groundwater Analyses (CTDEP)
Table 1-2 Summary of Results of Groundwater Analyses (MampE 1993)
Table 1-3 Summary of Results of Groundwater Analyses Former Pervel Flock Plant (HRP)
Table 2-1 Microwell Sampling Intervals
Table 2-2 Former Disposal Area Soil Samples Submitted for Laboratory Analyses
Table 2-3 Monitoring Well Survey Data and Screen Intervals
Table 2-4 Geologic Descriptions of Soil Samples Collected for Grain Size Analyses
Table 2-5 Sample Inventory
Table 2-6 Existing Well Summary
Table 3-1 Hydraulic Conductivity Values
Table 3-2 Hydraulic Conductivity Values Estimated from Grain Size Distributions
Table 3-3 Monitoring Well Water Level Elevation Data
Table 3-4 Summary of Vertical Hydraulic Gradients Between Pairs of MWs in Study Area
Table 3-5 Stream Piezometer Water Level Elevation Data
Table 3-6 Plants Identified During the Wetland Delineation
Table 4-1 Summary of Visual Site Reconnaissance
Table 4-2 Background Soil Volatile Organic Compounds Table 4-3 Background Soil MetalsCyanide
Table 4-4 Disposal Areas Soil Volatile Organic Compounds
Table 4-5 Disposal Areas Soil Semivolatile Organic Compounds
Table 4-6 Disposal Areas Soil PesticidesPCB
Table 4-7 Disposal Areas Soil MetalsCyanide
Table 4-8 Microwell Survey Selected Volatile Organics
Table 4-9 Microwell Survey Results of Volatile Organics Laboratory Analyses
Table 4-10 Microwell Survey Results of Inorganic Laboratory Analyses
Table 4-11 Groundwater Volatile Organic Compounds January 1995
Table 4-12 Groundwater Volatile Organic Compounds April 1995
Table 4-13 Groundwater Volatile Organic Compounds July 1995
Table 4-14 Groundwater Volatile Organic Compounds November 1995
5797wpdocggalluprifinraquoltextmalaquoterrifhl061297 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Tables (Contd)
Table 4-15 Groundwater Volatile Organic Compounds February 1996
Table 4-16 Groundwater Volatile Organic Compounds May 1996
Table 4-17 Groundwater Volatile Organic Compounds August 1996
Table 4-18 Groundwater Volatile Organic Compounds November 1996
Table 4-19 Groundwater Volatile Organic Compounds February 1997
Table 4-20 Groundwater Semivolatile Organic Compounds January 1995
Table 4-21 Groundwater Semivolatile Organic Compounds April 1995
Table 4-22 Groundwater Semivolatile Organic Compounds July 1995
Table 4-23 Groundwater Semivolatile Organic Compounds November 1995
Table 4-24 Groundwater Semivolatile Organic Compounds February 1996
Table 4-25 Groundwater Semivolatile Organic Compounds May 1996 Table 4-26 Groundwater Semivolatile Organic Compounds August 1996
Table 4-27 Groundwater Semivolatile Organic Compounds November 1996
Table 4-28 Groundwater Semivolatile Organic Compounds February 1997
Table 4-29 Groundwater PesticidesPCB April July and November 1995 February and August 1996 February 1997
Table 4-30 Groundwater MetalsCyanide January 1995
Table 4-31 Groundwater MetalsCyanide April 1995
Table 4-32 Groundwater MetalsCyanide July 1995
Table 4-33 Groundwater MetalsCyanide November 1995
Table 4-34 Groundwater MetalsCyanide February 1996
Table 4-35 Groundwater MetalsCyanide May 1996
Table 4-36 Groundwater MetalsCyanide August 1996
Table 4-37 Groundwater MetalsCyanide November 1996
Table 4-38 Groundwater Metals February 1997
Table 4-39 Residential Wells Volatile Organic Compounds January 1995
Table 4-40 Residential Wells Volatile Organic Compounds July 1995
Table 4-41 Residential Wells Volatile Organic Compounds February 1996
Table 4-42 Residential Wells Volatile Organic Compounds August 1996
Table 4-43 Residential Wells PesticidesPCB January 1995
Table 4-44 Residential Wells PesticidesPCB July 1995
Table 4-45 Residential Wells PesticidesPCB February 1996
Table 4-46 Residential Wells PesticidePCB August 1996
Table 4-47 Residential Wells Metals January 1995
5797wpdocsg lluprifinaltextmastemfiil061297 VI QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Tables (Contd)
Table 4^8 Residential Wells Metals July 1995
Table 4-49 Residential Wells MetalsCyanide February 1996
Table 4-50 Residential Wells MetalsCyanide August 1996
Table 4-51 Field Observations of Habitat and Water Quality September 1994
Table 4-52 Surface Water Quality April and November 1995 May and November 1996
Table 4-53 Surface Water Volatile Organic Compounds September 1994
Table 4-54 Surface Water Volatile Organic Compounds April 1995
Table 4-55 Surface Water Volatile Organic Compounds November 1995
Table 4-56 Surface Water Volatile Organic Compounds May 1996
Table 4-57 Surface Water Volatile Organic Compounds November 1996
Table 4-58 Surface Water Volatile Organic Compounds September 1994 April 1995 May
1996
Table 4-59 Surface Water Total MetalsCyanide September 1994
Table 4-60 Surface Water Dissolved Metals September 1994
Table 4-61 Surface Water Total Metals April 1995
Table 4-62 Surface Water Dissolved Metals April 1995
Table 4-63 Surface Water Total and Dissolved Metals November 1995
Table 4-64 Surface Water Total and Dissolved Metals May 1996
Table 4-65 Surface Water Total and Dissolved Metals November 1996
Table 4-66 SedimentWetland Soils Metals September 1994
Table 4-67 SedimentWetland Soils Volatile Organic Compounds September 1994 Table 4-68 SedimentWetland Soils Semivolatile Organic Compounds September 1994
Table 4-69 SedimentWetland Soils PesticidesPCB September 1994
Table 4-70 Human Receptors Survey Location of Day Care Facilities Within 1-Mile Radius
of Site
Table 5-1 Fate and Transport Parameters for Study Area Volatile Organic Compounds
Table 5-2 Total Organic Carbon Measurements for Soil Samples
Table 5-3 Historical Concentration Data
5797wpdoclaquoglaquolluprifinaltextmasterriftil061297 Vll QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Figures
Figure E-l Site Location Map
Figure E-2 Site Wide Groundwater Flow
Figure 1-1 Site Location Map
Figure 1-2 Property Boundaries and Adjacent Landowners
Figure 1-3 Surface Water and Groundwater Classification Zones and Locations of Former
Disposal Areas
Figure 1-4 Groundwater Monitoring Wells Installed by Fuss amp ONeill
Figure 1-5 Site Location Map and Nearby Industrial Properties
Figure 3-1 Groundwater Elevations MW101 Series Figure 3-2 Groundwater Elevations MW102 Series
Figure 3-3 Groundwater Elevations MW103 Series
Figure 3-4 Groundwater Elevations MW104 Series
Figure 3-5 Groundwater Elevations MW105 Series
Figure 3-6 Groundwater Elevations MW106 Series
Figure 3-7 Groundwater Elevations MW107 Series
Figure 3-8 Groundwater Elevations MW108 Series
Figure 3-9 Groundwater Elevations MW109 Series
Figure 3-10 Groundwater Elevations MW110 Series
Figure 3-11 Groundwater Elevations MW111 Series
Figure 3-12 Groundwater Elevations MW112 Series
Figure 3-13 Groundwater Elevations MW113 Series
Figure 3-14 Groundwater Elevations MW114 Series
Figure 3-15 Groundwater Elevations MW115 Series
Figure 3-16 Groundwater Elevations MW116 Series
Figure 3-17 Groundwater Elevations MW117 Series
Figure 3-18 Groundwater Elevations MW118 Series
Figure 3-19 Groundwater Elevations MW119 Series
Figure 3-20 Groundwater Elevations SW3 Series
Figure 3-21 Three-Dimensional Groundwater Flow Map
5797wpdoc8galluprifiruiltextmasterriftil061297 viii QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
Figure 5-1
Figure 5-2
Figure 5-3
List of Figures (Contd) Groundwater VOC Concentrations vs Time - Downgradient from Former
Primary Disposal Area
Groundwater VOC Concentrations vs Time - Near Former Pervel Facility
Groundwater VOC Concentrations vs Time - Downgradient Portion of VOC
Plume
Figure 5-4 Evaluation of Biodegradation and Rainwater Dilution Rates in VOC Plume
5797wpdocraquogalluprifinaltextmasterrifhl061297 ix QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Table of Contents (continued)
List of Plates
Plate 2-1 Baseline Survey Grid Air Monitoring Seismic Refraction Line Locations
Plate 2-2 Microwell Locations
Plate 2-3 Soil Vapor Probe and Soil Boring Locations
Plate 2-4 Monitoring Wells PiezometersStream Gauge Locations
Plate 2-5 Residential Well Locations
Plate 2-6 Surface WaterSediment and Wetland Soil Sampling Locations
Plate 2-7 Location of Test Pits Performed at Geophysical Anomalies
Plate 3-1 Study Area Topographic Features
Plate 3-2 Geologic Cross-Sections A-A amp C-C Plate 3-3 Geologic Cross-Section D-D
Plate 3-4 Geologic Cross-Section B-B Plate 3-5 Geologic Cross-Sections E-Eamp F-F
Plate 3-6 Bedrock Surface Contour Map
Plate 3-7 Bedrock Fracture Zones as Determined by Seismic and Magnetometer Surveys
Plate 3-8 Lower Overburden Piezometric Surface November 6 1995
Plate 3-9 Shallow Overburden Piezometric Surface November 6 1995
Plate 3-10 Saturated Overburden Thickness November 6 1995
Plate 3-11 Bedrock Piezometric Surface November 6 1995
Plate 3-12 Vertical Ground water Flow Through Plume Center Line
Plate 3-13 Deep vs Shallow Piezometric Head Differences
Plate 3-14 Wetland Delineation Map September 1994
Plate 4-1 Survey Grid amp Features Noted During Site Reconnaissance August-September
1994
Plate 4-2 Former Primary Disposal Area Soil Borings VOC Data and Cross-Sections
Plate 4-3 Former Primary Disposal Area Soil Borings PCB Data and Cross-Sections
Plate 4-4 VOC Detections Field GC and Laboratory Analyses in Microwells
Plate 4-5 Laboratory Results of Metals Analyses in Microwells
Plate 4-6 Groundwater VOC Data January April July and November 1995 Sampling
Events
Plate 4-7 Groundwater VOC Data February May August and November 1996 and
February 1997 Sampling Events
Plate 5-1 Groundwater Travel Times in Overburden Aquifer November 6 1995
5797wpdocsgi lluprifinaltextmasteirifnl061297 X QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
Table of Contents (continued)
List of Appendices
Appendix A Weston Geophysical Inc Report
Appendix B Microwell Logs
Appendix C Soil Boring and Rock Coring Logs and Well Construction Forms
Appendix D Groundwater Sampling Forms
Appendix E Test Pit Logs
Appendix F Single-Well Hydraulic Conductivity Test Procedures
Appendix G Grain Size Data
Appendix H Phase 1A Laboratory Reports
Appendix I April 1995 Laboratory Reports
Appendix J July 1995 Laboratory Reports
Appendix K Phase IBNovember 1995 Laboratory Reports
Appendix L February 1996 Laboratory Reports
Appendix M May 1996 Laboratory Reports
Appendix N August 1996 Laboratory Reports
Appendix O November 1996 Laboratory Reports
Appendix P February 1997 Laboratory Reports
Appendix Q Data Validation Reports
Appendix R pH TOC Moisture Results Soil Samples
Appendix S Environmental Metals Statistics
Appendix T Air Monitoring Results
Appendix U Model of Groundwater Near Mill Brook Appendix V Methodology for Piezometric Head Contouring and Groundwater Pathline
Generation
5797wpdocsgalluprifinlaquoltextmagterri fhl061297 XI QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
10 Introduction
11 Purpose of the Report This document presents the Remedial Investigation Report (RI) which was completed for the
Gallops Quarry Superfund Site (Site) pursuant to the requirements of US Environmental
Protection Agency (EPA) Administrative Order by Consent Docket Number 1-93-1080 (Order)
issued September 7 1993 The Gallups Quarry property is the site of a former sand and gravel
quarry and is located on Tarbox Road in the town of Plainfield Windham County Connecticut
(see Figure 1-1) According to the Town of Plainfield Tax Assessors office the property (Map
10 Block 30 Lot 32) is an irregularly shaped parcel comprised of approximately 29 acres
Investigation of the quarry was initiated in 1978 when unlicensed waste disposal operations were
discovered at the property Emergency clean-up operations were conducted by the Connecticut
Department of Environmental Protection (CTDEP) in April 1978 (Metcalf amp Eddy 1993)
Following the initial clean-up effort a study was conducted to characterize the nature and extent
of residual contamination at the Site (Fuss amp ONeill 1979) A series of surface and subsurface
sampling events conducted by the CTDEP the Connecticut Department of Health and the US
Environmental Protection Agency (EPA) between the years of 1978 and 1988 prompted EPA to
propose on June 21 1988 that the Site be listed on the National Priorities List (NPL) The Site
was finally listed on the NPL on October 4 1989 During 1992 and 1993 EPA conducted a
limited investigation through the Superfund Technical Assessment amp Response Team (START)
initiative in an effort to expedite the completion of the Remedial InvestigationFeasibility Study
(RIFS) The requirements of the Order as well as data included in the START report (Metcalf
amp Eddy 1993) provided the framework for this investigation
This Report is the sixteenth major deliverable under the Order The first major deliverable the
Remedial InvestigationFeasibility Study Work Plan - Phase 1A was finalized and submitted to
EPA on August 29 1995 QST Environmental (formerly Environmental Science amp Engineering
Inc (ESE)) finalized the Work Plan and has prepared all of the other deliverables The Phase 1A
field investigation was completed in January 1995 The second major deliverable the Phase 1A
Data Report dated March 24 1995 was submitted to EPA following completion of the Phase 1A
field investigation The findings of the Phase 1A investigation were described in the Initial Site
Characterization Report (ISCR) which was finalized and submitted to EPA on March 1 1996 A
Work Plan for the Phase IB field investigation was also finalized and submitted on October 11
1995
In addition to the actual Phase 1A field investigation the Phase 1A Work Plan also described the
Long Term Monitoring Program which was initiated upon completion of the Phase 1A field
5797wpdocraquogalluprifinaltextmlaquoiterrifhl061297 1-1 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
investigation The Long Term Monitoring Program includes the quarterly collection and analysis
of groundwatei and semi-annual collection and analysis of surface water and nearby residential
well samples
The Phase IB field investigation commenced on October 12 1995 Following the completion of
drilling activities the Phase IB groundwater sampling task and the fourth quarter 1995 Long
Term Monitoring sampling event were performed simultaneously in November 1995 Seven
Data Reports have been submitted to the EPA for the following Long-Term Monitoring Program
sampling events the second and third quarters of 1995 all four quarters of 1996 and the first
quarter of 1997 (ESE 1996a 1996b 1996c 1997a 1997b) The draft RI Report was submitted
to EPA on March 15 1996 (and revised and resubmitted October 22 1996) and included the
results of the fourth quarter of 1995 sampling event On March 29 1996 the following two
deliverables were submitted to EPA Development and Initial Screening of Alternatives Report
and Detailed Analysis Work Plan The draft Feasibility Study was submitted to EPA on January
27 1997 This RI Report describes the methods and findings of both the Phase 1A and IB field
studies and includes data collected during the April July and November 1995 February May
August and November 1996 and February 1997 Long-Term Monitoring sampling events
12 Report Organization The RI is presented in seven main sections following the Executive Summary The remainder of
Section 1 presents Site background information Section 2 presents the various field methods and
procedures used during the field investigations including descriptions of any changes or
deviations from the Work Plan Section 3 describes the physical characteristics of the Study
Area and Section 4 presents the findings of studies designed to determine the nature and extent of
contamination within the Study Area Section 5 is a discussion of the various fate and transport
mechanisms associated with the contaminants of concern Section 6 summarizes the conceptual
model of conditions within the Study Area Finally a list of references cited in this report is
presented in Section 7
Volume 1 of this Report presents the text and figures of the RI Volume 2 contains all Tables
referenced in the report Volume 3 contains all Plates referenced in the Report Volume 4 and
all subsequent volumes contain the Appendices referenced in the Report
5797wpdocggaIluprifinaltextmasterrifhl061297 1-2 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
13 Site Background 131 Area Description Demography and Land Use
For the purposes of this report the Site is considered to be the actual property owned by the
late Stanton Gallup from 1964 until his death in 1994 The Study Area includes the Site as
well as surrounding properties from which data were collected during the RI
The Site is located on the north side of Tarbox Road in the Town of Plainfield Windham County
Connecticut (see Figure 1-1) The Site is situated approximately 2000 feet west of interchange
87 on Interstate 395 and approximately one-mile southwest of Plainfield Center As shown on
Figure 1-2 the Site is irregularly shaped and is approximately 2200 feet long (north to south)
and 300 to 1100 feet wide (east to west) A number of previous references have described the
Site as ranging in size from 20 to 22 acres however the Town of Plainfield Tax Maps and areal
calculations performed by ESE indicate that the size of the Site is approximately 29 acres In
addition to the Site the Study Area includes additional areas located to the north and northwest of
the Site (as shown on Figure 1-1) and a number of discrete smaller areas located to the east and
south of the Site used for collecting upgradient surface watersediment samples
The Site is currently vacant and much of it is heavily vegetated Numerous overgrown mounds
and excavations are scattered across the Site and are presumed to be features remnant of the
former sand and gravel quarry operations Other than concrete foundations remnant of former
Site operations no structures presently exist on the property Surface features observed on the
Site during the Phase 1A visual reconnaissance survey are described in more detail in Section
411
As shown on Figure 1-2 the Site is bounded to the east by Route 12 (Norwich Road) single-family residences and a plumbing supply company An active railroad right-of-way (presently
operated by the Providence and Worcester Railroad) bounds the Site to the west Wooded areas
and wetlands associated with Mill Brook bound the Site to the north and Tarbox Road and several
single family residences bound the Site to the south
Surface water bodies located within or near the Study Area include Mill Brook Fry Brook and
Packers Pond As shown on Figure 1-3 Mill Brook flows from east to west along the northern
edge of the Study Area until its confluence with Fry Brook Mill Brook turns toward the south
at this confluence and continues flowing in a south-southwesterly direction (as Mill Brook) and
eventually drains into Packers Pond [Note Packers Pond is not shown on Figure 1-3 due to the
larger scale of this figure however the relative location of Packers Pond approximately 1 mile
west of the Site can be seen on Figure 1-1]
5797wpdocBgalluprifinaltextmasteiTifhl061297 1-3 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Based on the CTDEP Water Quality Classification Map of Thames Southeast Coast and
Pawcatuck River Basins Sheet 2 of 2 (1986) surface water located within the section of Mill
Brook between Route 12 and the confluence with Fry Brook (shown on Figure 1-3) is classified
as BA The BA classification indicates that the surface water body may not be meeting the
Class A water quality criteria for one or more designated uses which include potential drinking
water supply fish and wildlife habitat recreational use and agricultural and industrial supply
although the goal is to ultimately restore the water body to Class A standards Surface water
within Fry Brook and the lower section of Mill Brook (located down stream of the confluence of
the two brooks) is classified as Be The Be classification indicates that the water meets Class B
criteria and is suitable for cold water fisheries The designated uses for Class B surface water
include most of those described for Class A however Class B waters are NOT designated as a
potential drinking water supply Surface water located within Packers Pond (not shown on Figure
1-3) is designated as CBc The CBc designation indicates that Packers Pond is not meeting the
Class B water quality criteria for one or more designated uses or is a Class C water body which
is basically a downgraded version of Class B However the CTDEP goal for surface water
designated as CBc is to restore it to Class B conditions
As shown on Figure 1-3 groundwater located within the northern portion of the Study Area
between Route 12 and the MillFry Brook confluence is classified as GBGA which indicates that
the groundwater may not be suitable for direct human consumption without the need for treatment
due to waste discharges spills or leaks of chemicals or land use impacts The CTDEP goal for
groundwater classified as GBGA is to prevent further degradation by preventing any additional
discharges which would cause irreversible contamination Groundwater at all other locations
within the Study Area is classified as GA which is presumed suitable for direct human
consumption without need for treatment In addition one of the goals of the CTDEP for
groundwater classified as GBGA is to restore it to GA standards
It should be noted that the surface water classifications described above are based on existing
CTDEP maps which were published prior to the preparation of this report During the course of
this investigation the CTDEP proposed amendments which were intended to clarify the language
of the States Water Quality Standards and simplify the Departments system for considering
requested modifications Based on conversations with a representative of the CTDEP (Personal
Communication Bobowitz 1996) the single letter (eg Class A) and dual letter (and associated
goal) classification (eg BA) system will be maintained Areas presently designated by dual
classifications will only be modified once the desired goal for that water body or aquifer has been
attained According to the CTDEP the only significant change will be the eventual elimination of
the use of lower case suffixes (eg Be) which are currently used to indicate very specific
restrictions or uses for certain water bodies (ie B rather than Be)
5797wpdocsgalluprifinaltextmasterrifhl061297 1-4 QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
Within the Study Area directly west of the Site (across the railroad tracks) are open cropland
(presently a cornfield) wooded areas and a residential property (parcel 24 shown on Figure 1shy
2) The property boundaries and land owners for the Site and other nearby parcels are also
shown on Figure 1-2 Immediately north of the Site are approximately 85 acres of wooded
undeveloped land through which flows Mill Brook An overhead power line easement (not shown
on Figure 1-2) runs adjacent to the northernmost Site boundary On the north side of Mill Brook
is an industrial park which contains an Intermark Fabric Corporation facility (formerly the Pervel
Industries flock plant) and a Safety Kleen Corporation accumulation facility Northeast of Mill
Brook are woodlands and Saint Johns Cemetery Further north of the industrial park are several
vacant mill buildings which were occupied until the late 1980s by various manufacturers including
Pervel Industries and the InterRoyal Corporation The Plainfield sewage treatment plant which
discharges to Mill Brook and its major tributary (Fry Brook) is located approximately 1800 feet
northwest of the property
The Town of Plainfield with a land area of 427 square miles has a population of approximately
14200 Plainfields principal industries include varied manufacturing and distribution centers as
well as tourism based businesses In addition the rural areas of Plainfield are occupied by many
small dairy and produce farms
^ 132 Operational History
Information regarding the operational history of Gallups Quarry was obtained from published
reports for previous Site studies including Site Analysis Gallups Quarry Plainfield CT
(Bionetics Corporation 1990) and Final Data Summary Report START Initiative (Metcalf amp
Eddy 1993) as well as information from various sources collected during the preparation of the
Gallups Quarry Remedial InvestigationFeasibility Study Work Plan (ESE 1994) Little detailed information concerning the early operational history of the Site exists
A review of an aerial photograph of the Site taken in 1951 depicts the Site as an undeveloped
parcel although some quarry activities in the southern portion of the property appear to be
underway (ESE 1994) Records at the town of Plainfield Assessors office indicate that in 1951
the Site was owned by a Mr Johnson who was operating a sand and gravel quarry In 1964 the
Site was purchased by C Stanton Gallup (Metcalf amp Eddy 1993) Although detailed usage of
the Site from 1964 through 1977 is poorly documented records indicate that the Site was used as
a source of aggregate and was occupied by the Connecticut Department of Transportation
(CTDOT) which operated an asphalt batching plant (ESE 1994) The exact date of CTDOT
presence at the Site is unclear although it is believed to coincide with the construction of Route
52 (now known as Interstate 395) Evidence of the former asphalt batching plant operations are
5797wpdocsgalluprifinalteirtinalaquoterrifhl061297 1-5 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
still present at the Site Mounds of asphalt paving material and areas covered with hardened
liquid asphalt ere observed at a number of locations throughout the Site
As a result of complaints from neighboring residents the CTDEP and the Connecticut State
Police initiated an investigation of the Site in early January 1978 During a Site visit on January
13 1978 representatives of the CTDEP reportedly observed partially buried drums containing
suspected hazardous materials and ordered that all Site operations be stopped The CTDEP
investigation concluded that the Site was used from the summer of 1977 until December 1977 for
unlicensed waste disposal
As described in the Order evidence collected by CTDEP indicates that Chemical Waste Removal
Inc (CWR) of Bridgeport Connecticut transported drummed and bulk liquid waste material to the
Site and was the sole known transporter of waste to the Site These wastes reportedly included a
variety of industrial wastes which were transported to and disposed of at the Site It was reported
that Mr Gallup jointly operated the quarry with Mr Dick Trayner of Dick Trayner and Sons
Trucking Company at the time of the illegal waste disposal activities
According to CTDEP and State Police records the drums and liquid wastes were reportedly
disposed of at three distinct locations on the Site These areas were subsequently labeled the
Primary Disposal Area the Secondary Disposal Area and the Seepage Bed The Primary and
Secondary Disposal Areas were reportedly located in the northern portion of the Site while the
Seepage Bed was reportedly located in the central portion of the Site The reported locations of
these former disposal areas are shown on Figure 1-3
According to a report issued by Fuss amp ONeill (FampO 1979) the Primary Disposal Area
consisted of an area approximately 04 acres in size The Secondary Disposal Area was described
by the FampO report as a linear trench which encompassed an approximate area of 007 acres
located adjacent to the railroad tracks and just west of the Primary Disposal Area The Seepage
Bed was located in the central portion of the Site and according to the FampO report was
approximately 40 feet by 50 feet in size and consisted of an excavation into which an inverted
truck body filled and covered with crushed stone was placed A metal pipe which extended
from the dump body to the ground surface was reportedly used for direct discharge of liquid
wastes According to the FampO report the liquid wastes reportedly disposed of in the Seepage
Bed consisted of low pH liquids which were believed to be by-products associated with metal
finishing operations
Initial cleanup efforts were performed by Chem-Trol Inc during the summer of 1978 under the
direction of the CTDEP and the Connecticut State Police A Connecticut State Police Possessed
5797wpdocsglaquolluprifinaltextmasterrifhl061297 1-6 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
Property Report (PPR) lists the following materials as removed from the Site 1584 drums (some
of which were crushed andor decomposed) 5000 gallons of free liquid and 2277 cubic yards
of contaminated earth The PPR also lists 127715 tons of moderately contaminated soil which
was removed from the Site Additional remedial measures included the neutralization of residual
contamination at the Seepage Bed by placing 20 tons of lime at that location
Although no information concerning the actual number of drums or quantity of waste transported
to the Site by CWR is available it was believed that all of the drums had been recovered upon
completion of the cleanup operations Mine detectors were utilized to search for additional buried
drums however no indications of additional buried drums were discovered
Since the 1978 cleanup operations the Site has been vacant Public vehicular access to the Site
has been limited by the placement of boulders and mounded soil at access locations around the
Site During this time evidence of off-road vehicle tire tracks and small quantities of debris
(beverage cans bottles spent shotgun shell casings and empty gasoline cans) indicate that the
Site has been utilized by trespassers for recreational purposes However it appears that Site
usage has decreased since August 1994 when fencing and additional boulders were placed at
potential access locations and the perimeter of the property was posted with warning signs
133 Summary of Previous Investigations
Following the CTDEP removal activities a number of environmental investigations and sampling
events were conducted at the Gallups Quarry Site This section summarizes environmental
studies conducted at the Site prior to the RIFS as compiled performed and reported by Metcalf
amp Eddy (1993) as part of the EPAs Region I START Initiative or as reported by the original
investigators)
1331 Evaluation of a Chemical Waste Disposal Area Tarbox Road Site Plainfield Connecticut Fuss amp ONeill 1979
Between June 6 and October 30 1978 Fuss amp ONeill Inc performed a hydrogeological
investigation within the Study Area in conjunction with the cleanup and remedial operations
directed by the CTDEP and Connecticut State Police The findings of this investigation were
presented in a report issued to the CTDEP dated January 29 1979 The tasks completed during
this investigation included the following
bull The installation of 22 test borings which were completed as groundwater
monitoring wells (SW series) including three shallow-bedrock wells near the
Former Seepage Bed (SW-10 SW-11 SW-12) The locations of these wells are
shown in Figure 1-4
5797wpdocsgalluprifinaltextmlaquo8terrifhl061297 1-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
bull Excavation of 19 test pits (using a backhoe) 13 of which were completed as
shallow groundwater monitoring wells
bull The establishment of 12 surface water gauging stations along Mill Brook and Fry
Brook
bull The collection of surface water and groundwater water for laboratory analysis
FampO collected groundwater samples from the monitoring wells in July October and December
1978 Several nearby domestic wells were also sampled in July and October 1978 Groundwater
samples were analyzed for metals volatile organic compounds (VOC) and the following general
chemical parameters chemical oxygen demand (COD) total dissolved solids (TDS) total
Kjeldahl nitrogen (TKN) chloride total organic carbon (TOC) total carbon total cyanide
specific conductance and pH
FampO also collected surface water samples from seven of the stream gauging stations in
September October and November 1978 In general the surface water samples were analyzed
for the same chemical parameters described above
The chemical testing results indicated groundwater in the vicinity and downgradient of the Former
Disposal Areas had been impacted by several organic and inorganic constituents VOC detected
included ethanol methanol isopropanol ethyl acetate acetone toluene benzene trichloroethene
(TCE) 111- trichloroethane (TCA) tetrachloroethene (PCE) methyl isobutyl ketone (MIBK)
methyl ethyl ketone (MEK) and methylene chloride Various metals including aluminum
chromium copper magnesium nickel zinc iron and silver were reported at widely variable
concentrations in some groundwater samples According to the START Report the domestic
wells did not appear to be significantly impacted
FampO concluded that a well-defined groundwater contaminant plume extended from the former
disposal areas towards Mill Brook northwest of the Site and that the flow direction of the plume
was controlled by the local water table gradient The plume was characterized by the presence of
organic compounds which included acetate benzene ethanol isopropanol MEK MIBK
toluene TCA and xylene The plume also contained widely variable concentrations of various
metals including copper nickel boron aluminum magnesium manganese iron silver
cadmium and lead
The START Report indicated that since little or no information is available regarding FampOs field
methods (eg field notes chain-of-custody collection of field QC samples) or analytical
5797wpdoc8galluprifinaltextmastemfnl061297 1-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
methods (eg detection limits turbidity filtering sample preservation analysis of lab QC
samples) comparison of the test results to current regulatory criteria (eg Maximum Contaminant
Levels [MCL]) was not appropriate for any definitive purpose
1332 CTDEP Periodic Monitoring 1979 to 1983
As described in the START Report the CTDEP performed periodic monitoring of groundwater
(including domestic wells) surface water and sediment in the Study Area from 1979 until 1983
The periodic monitoring was not systematic in terms of the wells or locations that were sampled
or the parameters tested for The results of the CTDEP monitoring are in the form of laboratory
results compiled and presented in the START report A summary table of results for the CTDEP
groundwater monitoring activities as presented in the START report is included in this report as
Table 1-1
The dates of groundwater sample collection and analysis for the CTDEPs monitoring program
are as follows
bull October 1979
bull January 1980
bull November 1980
bull April 1981
bull October 1981
bull April 1982
Sample analytical parameters varied from event to event but typically included pH COD
specific conductivity hydrocarbons chlorides and selected metals (cadmium chromium copper iron nickel and zinc)
The CTDEP also collected surface water and sediment samples on the following dates
bull January 1980 (surface water)
bull October 1981 (surface water and sediment)
bull April 1982 (surface water)
bull December 1983 (surface water)
It was noted in the START Report that no information was available regarding the CTDEP sampling methods or analytical procedures and that this limited the usefulness of the data except
for comparative purposes Nonetheless the START Report concluded that the available analytical
data collected by CTDEP during the period from 1972 to 1982 indicated that the Site and areas to
5797wpdoc8falluprifinaltextmasterrifnl061297 1-9 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
the north-northwest were impacted by the past disposal of VOC metals and acid wastes This
conclusion wa5 based on the fact that up until the last recorded groundwater sampling event
performed by CTDEP (1982) four monitoring wells (SW7D SW13 SW17S and SW17D)
exhibited detectable concentrations of contaminants characteristic of the types of wastes which
were reportedly disposed of on the Site The contaminants detected in these wells included
various common industrial organic solvents (both chlorinated hydrocarbons and ketones) as well
as several petroleum aromatic hydrocarbons Chlorinated hydrocarbon concentrations for these
wells ranged from 10000 to 80000 parts per billion (ppb) for 111-Trichloroethane (TCA) 30
to 1000 ppb for Tetrachloroethane (PCE) and 1000 to 14000 ppb for Trichloroethene (TCE)
Ketones detected included Acetone (5000 to 22000 ppb) methyl ethyl ketone (MEK) ranged
from 12000 to 150000 ppb and methyl iso butyl ketone (MIBK) ranged from 60 to 7000 ppb)
The main aromatics detected included toluene (up to 17000 ppb) and xylene (up to 3000 ppb)
1333 CTDEP BioDiversity Study 1985
The CTDEP conducted a field survey on November 4 1985 to evaluate potential impacts from
migration of groundwater from the Site to the Mill Brook wetland The study was conducted in
an area where leachate was observed to be breaking out from the wetlands into Mill Brook
The precise location is unclear however the START Report indicates that the impact zone was
subjectively estimated to be approximately 200 feet west of the railroad bridge The leachate
was described as an area showing evidence of organic enrichment and iron hydroxide precipitation
which extended a distance of approximately 100 feet downstream
The study reported a background species Diversity Index value of 257 compared to a value of
236 for the area of study The minor difference in diversity represented by this measure was
primarily considered to be a result of low flow conditions as much higher diversity indices
indicative of excellent water quality were observed during a previous bioassessment in that
area
As part of the CTDEP study four surface water samples were collected (one control and three
downstream) from Mill Brook on 8 November 1985 for acute aquatic toxicity bioassays using
water fleas (Daphniapulex) The results of this testing are summarized in a CTDEP
interdepartmental memorandum (dated November 18 1985) that is included with the results of the
biodiversity study The assay employed three replicates per sample and 10 individual organisms
per replicate The endpoint of the assay was percent survival after 48 hour exposure to the water
All samples yielded average survival rates of greater than 83 Based on the results of the tests
the CTDEP concluded that no acute toxicity was demonstrated
5797wpdocsgalluprifinaltextmasterrifnl061297 1-10 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The BioDiversity study report indicated that well MW17S was sampled and that a strong
solventacid odor was noted Further information on sampling and analyses of this well by
CTDEP in 1985 was not included in the report
1334 Hazard Ranking System (HRS) Study - NUSFIT 1986 to 19874
On September 15 1987 the Superfund Division of NUS Corporation completed the Final HRS
Documentation Package for Gallups Quarry The package contains information on the cleanup
and subsequent environmental evaluations including State Police documents and logs regarding
the investigation into the unlicensed disposal activities CTDEP and State Police documents
concerning cleanup activities affidavits taken from individuals involved in the disposal activities
and miscellaneous correspondence related to the criminal investigation and cleanup activities
The HRS package includes the EPAs Preliminary Assessment for Gallups Quarry which was
completed by NUS in July 1986 During the Preliminary Assessment NUS sampled two of the
existing monitoring wells (SW17D and SW18) and three surface watersediment locations The
surface and groundwater samples were screened in-house for benzene TCE toluene PCE
chlorobenzene ethyl benzene and xylenes None of these compounds were detected in MW18 or
the surface water samples All of the compounds (except chlorobenzene) were detected in
MW17S with toluene and xylenes measured at the highest concentrations With the exception of
pH temperature and conductivity no data were available regarding the sediment samples
Based on a file review and limited sampling the Preliminary Assessment concluded as in
previous studies that VOC contamination existed at the Site and that contaminated groundwater
was migrating in a west to northwest direction from the Site NUS recommended that a Site
Investigation be conducted to further evaluate the on-site conditions and potential off-site impacts
1335 Residential Well Sampling 1989
In 1989 Roy F Weston Inc under contract to EPA collected samples from 10 private wells in
the vicinity of the Site The samples were analyzed for VOC semi-volatile compounds (SVOC)
and metals Very low levels of some VOC (chloromethane TCA and carbon tetrachloride)
SVOC (phthalates) and metals (barium and copper) were detected in several wells but at
concentrations well below their respective EPA MCL In a memo dated May 25 1989 (included
as Appendix G of the START Report) EPA concluded that the levels detected in this investigation
did not represent a public health threat
5797wpdocsgalluprifinaltextmraquosterrifhl061297 1-11 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
1336 Site Analysis - Bionetics Corporation 1990
In November 1990 the Bionetics Corporation under contract to EPA completed an analysis of
historical aerial photographs taken of the Site in 1951 1970 1974 1975 1981 and 1988
Based on analyses of these aerial photographs the report suggested that disposal-related activities may have started at the quarry as early as 1970 However this conclusion was based on the
presence of features such as excavated areas mounded materials possible containers and the presence of access roads all of which are also indicative of typical quarrying operations
1337 Health Assessment - US Department of Health and Human Services (DHHS) 1991
The US Department of Health and Human Services completed a Health Assessment for Gallups Quarry on January 30 1991 to assess potential human health effects from exposure to
contamination at the Site The assessment was based on previous chemical testing data available
for the Site (ie data collected by Fuss amp ONeill Inc in 1978 and by CTDEP in 1979 through
1983)
The report concluded that if present at high enough concentrations VOC and heavy metals
detected at the Site could have potential public health implications The report recommended that
a program of groundwater monitoring be instituted along with on-site soil and surface water sampling and that additional health data for the area be evaluated as it becomes available
1338 Residential Well and Surficial Soil Sampling - Roy F Weston 1993
In 1993 Roy F Weston Inc under contract to EPA sampled 8 residential supply wells in the
vicinity of the Site The samples were analyzed for VOC SVOC and metals In addition
Weston collected seven surficial soil samples (within 3 inches of the ground surface) from areas
of apparent staining in the vicinity of the Former Primary and Secondary Disposal Areas Two
samples were collected in January 1993 and the other five were collected in February 1993 The
soil samples collected in January were submitted to the laboratory for analysis for pH and
cyanide and for metals screening using X-ray fluorescence techniques (XRF) The five samples
collected in February were analyzed for cyanide
The results of the XRF screening analyses indicated that the two samples collected in January
contained levels of copper ranging from 160 to 400 ppm No other metals were detected above
normal background levels Cyanide levels for all seven soil samples were reported in the range
of 87 to 345 ppm
5797wpdocsgalluprifinaltextmasterrifiil061297 1-12 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
The well water analytical results indicated that 111-TCA was detected in three of the residential
wells at levels of 05 to 12 ppb well below EPA MCL for 111-TCA of 200 ppb Copper and
iron were detected at levels below the EPA MCL in several of the samples analyzed SVOC were
not detected
1339 Groundwater Monitoring and Well Survey Metcalf amp Eddy 1993
In November 1992 Metcalf amp Eddy performed a well condition survey of the remaining existing
monitoring wells at the Site as part of a groundwater monitoring well investigation conducted for
the EPA Thirteen of the original twenty-two monitoring wells installed by Fuss amp ONeill Inc
were located fewer than half of which were determined to be in a condition capable of producing
viable samples In February 1993 Metcalf amp Eddy collected samples from ten of the wells
installed by Fuss amp ONeill Inc and from a USGS well installed in 1992 The samples were
analyzed for VOC SVOC metals and cyanide
Groundwater analytical results were consistent with earlier studies but confirmed that VOC levels
were significantly decreasing with time Low levels of VOC were detected at monitoring wells
SW3S and SW3D located downgradient of the Former Primary Disposal Area and at SW13
located downgradient of the Former Secondary Disposal Area The highest levels of VOC were
detected in wells SW17S (15000 ppb of xylene 1700 ppb of toluene 460 ppb of TCA 34 ppb
of TCE 22 ppb of PCE) and SW17D (1500 ppb of 12-DCE 720 ppb of TCA 16 ppb of TCE
and 27 ppb of PCE) A summary of the results of the 1993 Metcalf amp Eddy monitoring are
presented in Table 1-2 In general the concentrations detected in these wells for this sampling
event were substantially lower than concentrations recorded during the previous groundwater
sampling in 1982
13310 Geohydrology of the Gallups Quarry Area Plainfield Connecticut USGS 1993
In 1993 the United States Geological Survey (USGS) issued a draft report on Geohydrology of
the Gallups Quarry Area Plainfield Connecticut (finalized in 1995) The work was performed as
part of the EPAs START program and was designed to assist in the RIFS scoping process
The USGS study interpreted the subsurface geologic conditions at the Site to provide guidance for
subsequent investigations Field investigations for the study included ground penetrating radar
(GPR) and electromagnetic (EM-34) geophysical surveys the drilling of three test borings the
installation of a monitoring well in one of the borings (shown on Figure 1-4) and the
measurement of flow rate and specific conductance in Mill Brook
5797wpdocraquosalluprifiiultextmasterrifiil061297 1-13 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The USGS investigation provided data on overburden soil units the depth to bedrock and
bedrock structure Existing subsurface information derived from previous test boring logs and the
data collected from the three test borings drilled by the USGS were used in conjunction with GPR
data and the results of the EM-34 terrain conductivity survey to develop geological cross-sections
across the Site In addition the GPR survey indicated the possible presence of a west-northwest
trending fault zone beneath the property located south of the Former Seepage Bed The location
of this suspected fault zone as estimated by the USGS is consistent with the approximate location
inferred by previous regional geological studies (Dixon 1965 and Boynton and Smith 1965)
An electromagnetic survey performed downgradient (northwest) of the Former Secondary and
Primary Disposal Areas indicated a northwesterly-trending pattern of increased terrain
conductivity levels as compared with levels at other areas of the Site The USGS interpreted the
increased levels as possibly indicative of either the presence of a groundwater plume containing
residual metal contamination or a natural change in subsurface strata Surface water
measurements collected in Mill Brook indicated that specific conductance increased slightly
downstream of the railroad bridge however the observed differences were so small that the
USGS did not consider them to be indicative of changes in water quality caused by the presence
of dissolved contaminants
13311 Habitat Characterization for Gallups Quarry Superfund Site US Fish and Wildlife Service March 1995
In June of 1993 the US Fish and Wildlife Service conducted a field survey for the purposes of
characterizing the habitat of the Site and surrounding wetland and stream ecosystems The study
was qualitative in nature conducted on foot by trained biologists with the objective of correlating
observations on habitat (primarily vegetation) with known reference material such as topography
maps and aerial photographs The study also included direct and indirect (eg animal tracks)
observations to assess the presence (or absence) of wildlife
The report provides a description of methods and general Site characteristics as well as a more
detailed discussion of wildlife habitat for both the Site and the Mill Brook wetland ecosystem
The study is partial in that it accents what types of animals would be anticipated to be present for
each habitat type even though most of these animals were not directly observed
The report concludes with a description of 29 different types of cover that can be cross-
referenced to areas delineated on a Site map (not to scale) Several Tables are also presented
which inventory birds mammals reptiles amphibians trees shrubs and herbaceous vegetation
that were either observed or would be expected to inhabit the Site
5797wpdocsgalluprifinaItextmasterriftil061297 1-14 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
13312 Adjacent Properties Incident Reports and File Review 1995
To supplement data obtained during the Phase 1A field program a CTDEP file search was
performed to obtain information pertinent to groundwater contamination for industrial properties
neighboring the Site The preliminary findings of this review were submitted in a letter from
ESE to EPA on March 28 1995
A number of incident reports were on file regarding two nearby companies Pervel Industries
Inc and InterRoyal Corporation which have the potential to impact conditions within the Study
Area Figure 1-5 shows the locations of these facilities relative to the Site The significant
findings of the file searches are presented below
Pervel Industries
Pervel Industries Inc manufactured plastic film and laminated textile products (eg flocked
velvet) Pervel reportedly occupied two separate facilities north of the Site The main facility
located approximately 2500 feet north of the Site is believed to have been occupied by Pervel
from the 1940s or 1950s to at least the late 1980s This facility abutted the southern side of the
InterRoyal facility described below A second Pervel facility known as the flock plant (presently
operated by Intermark Fabric Corporation) was located approximately 1000 feet north of the
Site just north of Mill Brook The dates of Pervels occupation at the flock plant cannot be
clearly ascertained from the information available in the files however the review of historic
aerial photographs indicate that the facility has existed since the early 1970s
In 1988 at the request of EPA and CTDEP the NUS Corporation performed a Preliminary
Assessment (PA) at the main facility In an effort to determine eligibility for the National
Priorities List (NPL) NUS reviewed the activities associated with the 1984 closure of a sludge
and waste water lagoon located at the facility Based on their review of the available data NUS
recommended that a Screening Site Inspection (SSI) be performed
The NUS PA report also described a 1985 spill of 600 gallons of 111-TCA and a 1987 spill of
300 gallons of toluene at the northernmost facility According to the PA report contaminated soil
and sediment associated with the 1985 spill was excavated and stored in an impoundment at the
flock plant located just north of the Gallups Site The report indicates the presence of
contaminants in the area where the contaminated soil and sediment were stored suggesting that
the impoundment leaked andor there are other (undocumented) environmental concerns at the
flock plant
5797wpdocraquogalluprifinaltextmlaquosterrifhl061297 1-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The results of recent (late 1980s through the early 1990s) quarterly groundwater monitoring
efforts conducted at the former Pervel flock plant (HRP 1993) indicate the presence of a number
of VOC including 111-TCA TCE PCE and 12-DCE well above their respective MCL The
results of these sampling events as summarized in Table 1-3 (from HRP 1993) indicate that
there has been a general decrease in the concentrations of contaminants seen in these wells over
time The highest recorded concentrations for these constituents are as follows 111-TCA (518
ppb) PCE (466 ppb) TCE (63 ppb) and 12-DCE (906 ppb) According to the HRP report
groundwater flow in the vicinity of the former Pervel flock plant is generally from east to west
(towards the northern portion of the Study Area) However these interpretations were based on a
limited number of data points confined to the Pervel flock plant property
InterRoyal Corporation
The InterRoyal Corporation is located adjacent to and just north of the main Pervel facility
described above The CTDEP files include a memorandum from the NUS Corporation to EPA
dated August 18 1989 which references a 1984 Preliminary Assessment performed by CTDEP
which recommended that a low priority Site Inspection be performed The NUS memo presents a
chronology of Site activities up to 1989 which includes CTDEPs 1987 finding that the company
was in violation of several State Hazardous Waste Management regulations and CTDEPs
subsequent revocation of InterRoyals NPDES permit Based on a CTDEP 1988 Site inspection
NUS recommended to EPA that a high priority Screening Site Inspection be conducted
In 1988 InterRoyal contracted an environmental consultant to prepare an environmental
assessment (EA) for the proposed sale of the property The EA report (ERT 1988) concluded
that substantive on-site contamination of groundwater surface water and soils existed The
principal contaminants were identified as VOC (including TCE trans-l2-DCE PCE vinyl
chloride toluene and xylenes) and priority pollutant metals Groundwater flow direction was
described in the EA report as principally towards the south and southwest
5797wpdoc8galluprifinaltextmasterrifhl061297 1-16 QZT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
20 Field Investigations
This Section describes the field methods and procedures used to accomplish the various field
investigation tasks performed during Phase 1A and Phase IB Also included are descriptions of
any deviations from the approved Work Plan As noted in the appropriate subsections any
deviations from the Work Plan were approved by EPA (or EPAs oversight contractor) prior to
implementation Discussions of the findings results and significance of these investigations are
presented in Sections 3 and 4 of this Report
21 Site Survey 211 Initial Site Survey At the start of the Phase 1A field investigation an initial Site survey was performed to confirm
and update the location and elevation of features included in the base map provided by EPA (EPA
drawing number 707600 dated October 14 1993) The initial Site survey also served as Site
control by establishing a 250-foot grid across the entire Site which was identified by the
installation of labelled stakes at the intersection of each 250-foot grid line Horizontal control for
the 250-foot grid (and all subsequently surveyed features) coincides with the Connecticut State
Plane Coordinate System North American Datum of 1927 Vertical control coincides with the
National Geodetic Vertical Datum (NGVD) of 1929 and was established using nearby USGS benchmarks The 250-foot grid (shown on Plate 2-1) provided known reference locations from
which field personnel could measure the locations of Site features
In addition to the 250-foot control grid the initial survey also established a series of parallel lines
(trend lines) across the Site for use during subsequent visual reconnaissance and geophysical
surveys The trend lines (also shown on Plate 2-1) are roughly parallel to the Providence amp Worcester railroad which abuts the western edge of the property The first trend line (Line A)
was located approximately 50 feet east of the railroad right-of-way with subsequent lines (Line
B through Line HH) spaced at 25-foot intervals Each of the trend lines were staked at 250shy
foot intervals using labelled stakes
212 As-Installed Survey
Following the initial Site survey additional surveying events were performed as needed
throughout the duration of the Phase 1A and Phase IB field investigation programs to locate
various sampling locations and other pertinent investigation features These subsequent surveys
were initiated shortly after the completion of each investigation task Besides the various
surveyors control features such as temporary benchmarks and turning points the features
surveyed included wetland delineation flags surface watersediment and wetland soil sampling
5797wpdocsglaquolluprifinlaquoltextrnasterrifhl061297 2-1 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
locations microwells soil vapor points soil borings monitoring wells (existing and newly
installed) stream gauges piezometers and seismic survey lines
All pertinent investigation-related features within approximately 1500 feet of the Site were
included in the survey Several surface watersediment sampling locations beyond 1500 feet from
the Site were not surveyed and their locations are estimated based on their proximity to mapped
physical features such as bridges or roads
The surveying services for this investigation were performed by KWP Associates Inc of Pomfret
Center Connecticut a licensed and registered surveyor in the State of Connecticut The survey
was completed as a third-order plane survey as defined by the standards and specifications in
Exhibit 14-1 of the Compendium of Superfund Field Operations Methods December 1987
(USEPA 1987)
22 Site Reconnaissance 221 Visual Observations of the Ground Surface
A visual reconnaissance of the Site was conducted during an approximate three week period
beginning on August 23 1994 and ending on September 13 1994 During the visual Site
reconnaissance the entire length of each trending line (shown on Plate 2-1) was walked to
identify and map any features which may have been indicative of unknown disposal areas Any
features such as areas of stained soil partially buried man-made objects remnants of buildings
abandoned equipment containers (eg drums tanks) pits depressions mounds and any other
apparent unnatural materials were photographed and noted on field maps and in a field notebook
Also potential disposal features identified during review of historic aerial photographs (Bionetics
Corporation 1990) were located and investigated The locations of features were flagged and
approximated using the survey stakes installed during the initial Site survey The results of the
field reconnaissance were also used to determine additional soil gas sampling locations (described
in Section 25) during subsequent Phase 1A investigations
222 Air Quality Survey
A baseline air quality survey was conducted prior to the start of Phase 1A intrusive field
investigations The survey was performed using a photoionization detector (PID) equipped with
an 117eV lamp to measure total VOC vapors and a direct reading aerosol monitor (RAM-1) to
measure respirable particulates Baseline air quality readings were recorded at eight stations
(AM-1 through AM-8) located across the Site The monitoring stations included areas along the
Site perimeter as well as interior locations at the three known former disposal areas The
locations of the eight baseline air monitoring stations are shown on Plate 2-2
5797wpdocsgalluprifinaltextmlaquo8temfnl061297 2-2 QZT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
In addition to the baseline air quality survey air monitoring was performed on a weekly basis at the eight locations during the entire Phase 1A field investigation Wind direction wind speed
temperature and barometric pressure were also continuously monitored at an on-site
meteorological station
During the Phase IB investigation quantitive air monitoring was performed for site specific
compounds The Phase IB air sampling was performed in the vicinity of the Former Primary
Disposal Area on October 24 1995 This location was selected based on the findings of the
Phase 1A field program Four samples were collected along the perimeter of the Former Primary
Disposal Area at the northern southern eastern and western edges of the perimeter One
background sample was collected at a location approximately 300 feet south of and upwind from the Former Primary Disposal Area The sample locations are shown in Plate 2-2 The samples
were analyzed for the following volatile organic compounds (VOC) toluene ethyl benzene xylenes (total) and tetrachloroethane (PCE) and polychlorinated biphenyls (PCBs)
VOC samples were collected on stainless steel Tenax tubes which were connected to Dupont
Alpha 1 sampling pumps Samples for PCBs were collected on 037z glass fiber filters using
Dupont Alpha 1 and BIOS AirPro 6000D sampling pumps The sampling media was attached to
the sampling pumps using silicone tubing The pumps were secured to wood stakes and
positioned approximately 5 feet above the ground surface
The pumps used to collect the VOC samples were set to pump at a flow rate of between 0014 to
0016 liters per minute and allowed to pump approximately eight hours The pumps used to collect the PCB samples were set to pump at a flow rate of between 27 and 33 liters per minute
and were allowed to pump approximately eight hours All of the sampling pumps were calibrated prior to and after the sampling event using a primary gas flow mini-Buck Model M-5 Calibrator
Ambient meteorological conditions including temperature relative humidity barometric pressure
and wind speed and direction were monitored during the sampling event using ESEs on-site Qualimetrics meteorological monitoring instrument
A VOC and a PCB field blank were collected at background location AS 105 The VOC Tenax
tube and the PCB glass fiber filter were appropriately labeled opened and then immediately
resealed The field blanks were stored and shipped with the samples
At the completion of the sampling event the VOC Tenax sample tubes (including the field blank)
were sealed placed in clean plastic bags and refrigerated at 4degC until they were shipped The
samples were then shipped to the laboratory in coolers The PCB sample filters were sealed
5797wpdocsgalluprifinaltextmasterrifhl061297 2-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
wrapped in bubbie wrap and packed along with the PCB field blank in a cardboard box for
shipment to the laboratory An unopened VOC Tenax tube and PCB glass fiber filter were
submitted with tae samples as a trip blank The VOC Tenax sample field blank and trip blank
tubes were packed in a cooler with ice and sent to ESEs Denver Colorado Laboratory where
they were analyzed by EPA Method TO1 The PCB glass fiber sample field blank and trip
blank filters were sent to ESEs Denver Colorado Laboratory where they were analyzed by
SW846 EPA Method 8080 The results of the air quality survey are discussed in Section 44
223 Exclusion Zone Identification
Prior to the start of Phase 1A field activities preliminary exclusion zones were identified to limit
the risk of workers exposure to potentially hazardous conditions Based on existing data and
observations made during the Site visual reconnaissance the three known former disposal areas
and the area immediately surrounding a former CTDOT asphalt plant structure were staked and
flagged with caution tape A contaminant reduction zone (CRZ) was established adjacent to the
exclusion zone in the prevailing upwind direction during investigations at each location The
CRZ was established for decontamination operations of Site personnel and equipment
224 Project Support Measures
All field investigations were managed from a field office located within an approximate 10000
square foot support center which was situated at the southern end of the Site along Tarbox Road
The support center consisted of an approximate 100 foot by 100 foot area surrounded by a 6 foot-
high chain link fence The support center housed an office trailer an impermeable bermed
decontamination pad lined with 60 mil thick textured HDPE potable water storage tanks storage
units (drums dumpsters and tanks) for investigation derived wastes the weather station and
portable sanitary facilities The office trailer was connected to electric utilities and telephone
service to facilitate normal business and emergency operations A storage trailer for supplies and
equipment was located adjacent to the support center
The field office was used to support field activities by providing the following services
bull personnel sign-in and sign-out sheets
bull daily field activity log book
bull Health amp Safety log book
bull storage of Personal Protective Equipment (PPE)
bull communications center
bull posting of project plans
bull management of project field files
bull briefingmeeting room to coordinate field activities
5797wpdocsgalluprifinaltextmasterrifW061297 2-4 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull meeting place for emergency evacuations and
bull lunch area
The support center also provided an access control point for the Site as it is the only practical
location where four wheeled vehicles could enter or exit the Site Other non-vehicular access
points were blocked with boulders or mounded soils Other access to the Site is limited due to
the presence of heavy vegetation steep slopes and wetlands In addition warning signs
prohibiting trespassing were posted every 100 feet along the Site perimeter prior to the start of
Phase 1A field activities
225 Identification of Sensitive Human Receptors
A survey to identify potential human receptors in the vicinity of the Site was performed This
survey was used to identify any private water supply wells schools nursing homes and day care
facilities located within a one mile radius of the Site The survey was performed by reviewing
available records and documents from the following sources
bull Town of Plainfield Municipal Offices
bull Northeast District Health Department
bull Connecticut Department of Environmental Protection
bull Connecticut Natural Resource Center and
bull Connecticut Department of Health and Addiction Services
In addition to the file reviews interviews were conducted with neighbors and knowledgeable local
people Finally a windshield survey was conducted for the area located within a one mile radius
of the Site
23 Geophysical Surveys During the Phase 1A investigation comprehensive geophysical surveys of the Site were conducted
by Weston Geophysical Corporation of Northborough Massachusetts using electromagnetic
terrain conductivity (EM) magnetometer (MAG) and seismic refraction survey techniques The
purpose of the EM and MAG surveys was to obtain Site-wide screening data to identify the
locations if any of potential subsurface disposal features or objects such as pits trenches drums
or tanks The initial EM and MAG surveys were conducted along each of the trend lines
established during the initial Site survey as shown on Plate 2-1
The purpose of the seismic refraction survey was to determine the location and orientation of the
inferred bedrock fault (if present) in the central portion of the Site Although bedrock
characterization was not one of the intended purposes of the MAG survey subsequent review of
5797wpdocsgalluprifinaltextmasterriftil061297 2-5 QSTT Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
the acquired MAG data provided some information regarding the nature of the shallow bedrock
surface in the central portion of the Site
The presence of heavy vegetation over much of the intended survey area required approximately
two weeks of brush cutting and clearing in order to gain access to the trending lines and to ensure
complete coverage of the Site Once the proposed survey lines were accessible the initial MAG
and EM surveys were conducted along each trending line with data collected at five-foot intervals
The Work Plan stated that the five-foot intervals would be determined by laying a fiberglass
measuring tape along each trend line between survey stakes However the presence of heavy
vegetation prohibited the efficient use of this technique Since the exact locations of any
unexplained anomalies would be later determined during subsequent EM and MAG surveys (and
confirmed during test pit explorations) it was determined that the five-foot intervals could be
efficiently and accurately estimated by an experienced equipment operator by counting paces
between intervals and making adjustments as necessary at each survey stake (which were located
every 250 feet along each line)
As stated in the Work Plan ground penetrating radar (GPR) was to be used if necessary to
further characterize any unexplained anomalies identified during the initial EM and MAG surveys
The presence of abundant vegetation and rough ground surface conditions in the areas of interest
precluded the reasonable use of GPR As approved by EPA the precise locations of unexplained
anomalies identified during the initial EM and MAG surveys were determined during additional
EM and MAG surveys using a finer (5 foot by 5 foot) survey grid superimposed over the general
vicinity of each anomaly
The seismic refraction survey was conducted along six roughly parallel lines which were placed
normal to the anticipated strike of the inferred bedrock fault The locations of the six seismic
lines are shown in Plate 2-3 Each seismic line (Line 1 through 6) is comprised of two 250-foot
long lines which overlap by 125 feet This resulted in a total of 375 feet of continuous coverage
along each line
A complete report provided by Weston Geophysical Corporation describing the theoretical basis
for these surveys is presented as Appendix A Generalized discussions describing the field
methods and equipment used during each geophysical survey are presented below
5797wpdoclaquogalluprifinaltextmastemfnl061297 2-6 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
231 Electromagnetic Terrain Conductivity (EM) Survey
The initial EM survey was performed by Weston Geophysical Corporation over a three day
period (September 14-16 1994) using a Geonics EM-31 electromagnetic terrain conductivity
logger and a Model 720 Polycorder Background terrain conductivity readings were collected at
the beginning and end of each day from an area determined to be relatively free of electrical
interference The background station was located at the extreme southeastern corner of the Site
well away from the overhead electrical lines located along Tarbox Road and Route 12 (Norwich
Road) The EM-31 was calibrated daily by the operator and data was downloaded in the field to
a computer as needed typically twice a day
Following daily calibration the EM survey was performed by the instrument operator who paced
the entire length of each trend line with the EM meter and data logger Terrain conductivity
measurements were made and digitally recorded at five-foot intervals along each line The
presence of surficial objects and other features (eg steel fencing) that would cause interference
or produce anomalies were noted in the field notebook and accounted for during the data
evaluation Terrain conductivity data were subsequently plotted on a base map of the Site and
contoured to produce the terrain conductivity contour map included in the Weston Report in
Appendix A The results of the EM survey are discussed in Section 413
232 Magnetometer (MAG) Survey
The initial MAG survey was conducted by Weston Geophysical Corporation over a period of 7
days (September 7-14 1994) using two GEM-VI and one EGampG Model 856 magnetometers The
two GEM units were used for data acquisition while the EGampG unit was used as a base station to
monitor diurnal changes in the earths magnetic field The base station was established at the
southeastern corner of the Site where there was no interference from metallic objects or overhead powerlines and where no significant magnetic field gradients were observed
The MAG survey was performed by walking each trending line wiih one of the data acquisition
magnetometers (GEM-VI) and recording the magnetic field at every five-foot interval determined
by pacing The MAG data were eventually corrected for diurnal background fluctuations in the
earths magnetic field as determined at the base station and plotted on a base map to produce the
magnetic contour map which is included in the Weston Report in Appendix A The results of the
magnetometer survey are discussed in Section 413
5797wpdocsglaquolluprifinaltextmlaquo8terriftJ061297 2-7 QST Environmental
Gallups Quarry SuperUna1 Project - Remedial Investigation
233 Additional EM and MAG Surveys
In lieu of GPP surveys additional EM and MAG surveys were performed to determine the
precise location of any terrain conductivity or magnetic anomalies which could not be explained
by the presence of surficial metallic debris The additional surveys were performed over a 5-foot
by 5-foot grid in the vicinity of each unexplainable anomaly
A total of four unexplainable anomalies within three separate areas were eventually investigated
with additional EM and MAG surveys Once the locations of the anomalies were accurately
located each anomaly was further assessed by excavating test pits to identify the source of the
anomaly The test pit operations are discussed in Section 214 and the findings of the test pit
excavations are discussed in Section 4133
234 Seismic Refraction Survey
A seismic refraction survey was conducted along six 375-foot lines located within the suspected
fault zone An ABEM Terraloc 24-channel digital recording seismograph system was utilized for data collection The 375-foot spread lengths consisted of two overlapping 250-foot long lines
with geophones spaced in ten-foot intervals The endpoints of each seismic line were staked in
the field to facilitate the subsequent location survey
In accordance with the Work Plan shot points were located at each end point midpoint and
quarter point in addition to an offset from each end point The Work Plan had stated that
seismic energy would be produced by either an elastic wave generator or weight drop However
due to access constraints at the Site EPA approved the use of an alternate energy source For
these surveys seismic energy was generated using 8 gauge seismic shotgun shells discharged
approximately 2 to 3 feet below ground surface
The energy created by the shell blast travels through the ground and refracts along interfaces
between materials of different propagation velocity and density characteristics Interpretation of
these data on a time vs distance plot is conducted for the seismic wave arrival times at each
geophone The propagation velocities can be categorized into various geologic materials such as
overburden saturated overburden bedrock formations and weathered or fractured formations A
comprehensive discussion of the theoretical basis and operation of this technique is presented in
the Weston Geophysical report provided as Appendix A The results of the seismic refraction
survey are discussed in Section 32
5797wpdoc8gaIIuprifinaltextmasterrifnl061297 2-8 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
24 Groundwater Sampling Using Temporary Well Points Between August 29 and October 7 1994 a total of 60 small-diameter temporary well points
(microwells) were installed at predetermined locations using direct push techniques for the
purpose of collecting groundwater samples for both on-site and off-site chemical analysis At 10
of these locations equipment refusal occurred prior to encountering groundwater thus reducing
the total number of sampled locations to 50 The results of the chemical analyses were used to
determine the nature and extent (both horizontal and vertical) of groundwater contamination (VOC
and metals) within the Study Area Data obtained during this survey were ultimately used to determine the optimum location for subsequently-installed permanent groundwater monitoring
wells The surveyed locations of the temporary well points (TW101-TW160) including the 10 unsampled locations are shown on Plate 2-4 A summary of the locations and depth intervals for
each microwell is presented in Table 2-1
A total of 126 samples were analyzed on-site for selected VOC using a portable gas chromatograph (GC) A total of 121 samples (not including duplicates and field blanks) were
submitted for off-site laboratory analysis for cyanide and metals Also 12 samples (not including
field blanks and trip blanks) were submitted for off-site laboratory analysis for VOC to confirm
the on-site GC analytical data
The microwells were comprised of a 082 inch diameter (062 inch inside diameter) steel riser
pipe of varying lengths equipped with a hardened steel tip and a 5 foot long slotted section at the
leading end The 5 foot long slotted section (or screen) consisted of a four longitudinal rows of 2
inch long by 0015 inch wide slots Each microwell was advanced into the subsurface using
either an electrically or hydraulically powered vibratory impact hammer which was mounted on a
telescoping mast The mast drive-hammer and all other ancillary equipment were mounted on an all-terrain vehicle for maximum mobility
Individual sections of riser pipe (which varied in length up to a maximum of 21 feet) were
connected using a slip coupling over the butted ends of adjacent sections The slip coupling is
either electrically welded or crimped (using a hydraulic crimping tool) over the connection to
form a water tight joint
All materials were steam cleaned prior to use and only used at one location to avoid cross
contamination between sampling locations
The objective at each location was to drive the microwell into the saturated overburden and collect
a groundwater sample from three successively deeper intervals The desired sampling intervals
were as follows five feet below the top of the water table midway between the top and bottom of
5797wpdocsgalluprifinaltextmlaquoraquotemfhl061297 2-9 QST Environmental
Gallups Quarry SuperUna1 Project - Remedial Investigation
the aquifer and at the bottom of the aquifer (ie the refusal depth) A middle andor deep sample
was not collected if refusal was encountered without significant advancement of the well point
between sample depths (minimum of 10 feet) The midpoint sampling depth was estimated based
on the refusal depths encountered at nearby microwells
Once the microwell was driven to the desired depth purging and sampling was accomplished
using a manually operated inertial pump comprised of an adequate length of dedicated 38 inch
(inside diameter) polyethylene tubing equipped with a bottom check valve In operation the
inertial pump is lowered into the screen section of the microwell and repeatedly raised and
lowered (manually) a distance of approximately one foot This reciprocating action causes water
to rise within the tube until it is ultimately discharged at the ground surface into either a bucket or
sample container Between one and three riser volumes were purged from each microwell prior
to sample collection except for the first sample (5 feet below the top of the water table) which was
collected without purging All purge water was containerized and eventually transported off-site
for treatment and disposal
Once a groundwater sample was acquired it was labelled packed in a cooler and transported to
the on-site laboratory Each sample was analyzed on-site using a portable gas chromatograph
for the following eight VOC
bull l2-dichloroethene(DCE)
bull 111 -trichloroethane (111 TCA)
bull trichloroethene (TCE)
bull benzene
bull toluene
bull acetone
bull methyl ethyl ketone (MEK)
bull methyl iso-butyl ketone (MIBK)
Groundwater samples from each location were also collected filtered through a 045 micron
filter preserved with nitric acid and submitted to an off-site laboratory for analysis for the
following metals
bull aluminum
bull arsenic
bull cadmium
bull chromium
bull copper
5797wpdoc8galluprifinaltextmasterrifhl061297 2-10 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
bull iron
bull lead
bull manganese
bull nickel
bull zinc
Unfiltered samples were also collected preserved with sodium hydroxide (NaOH) and submitted
for analysis for cyanide In addition duplicates of 12 of the VOC samples analyzed in the field
were submitted for laboratory analysis for VOC for confirmation purposes Samples for off-site
VOC analyses were preserved in the field by addition of hydrochloric acid (HC1) to obtain a pH
less than 2
Samples for on-site VOC analyses were collected into 40 ml glass vials equipped with a teflonshy
lined silicon septum Each vial was filled capped labelled and refrigerated until it was
analyzed Samples were typically analyzed within several hours of collection Prior to analysis
the sample was removed from the refrigerator and 10 ml of water was withdrawn and discarded
The withdrawal of 10 ml of water created a headspace within each vial into which any VOC
present in the liquid would partition To complete the VOC partitioning process the vial was
then placed into a constant temperature (90 degC) water bath for a minimum of 15 minutes Just
prior to analysis a 250 micro-liter air sample was withdrawn from the headspace within the vial
by inserting the needle of the syringe through the teflon-lined septum and injected into the
portable gas chromatograph for analysis
A Photovac 10S50 portable gas chromatograph equipped with a CPCIL 5 encapsulated column
was used for on-site analysis The Photovac 10S50 gas chromatograph (GC) was filled every
morning with zero grade air and allowed to warm-up for 30 minutes prior to daily operation in
accordance with SOP 4001 and manufacturers instructions
The GC detector flow oven temperature and gain setting (sensitivity setting) were checked and
verified every morning and throughout the day Field GC standards were prepared daily by
diluting commercially available certified pure liquid chemical standards with deionized water
Three separate standards a low-concentration level a mid-concentration level and a high-
concentration level standard containing the eight select VOC were prepared in order to obtain a
three-point calibration curve Glass gas-tight syringes were used for preparation of standards and
sample injection AH syringes were decontaminated using methanol deionized water and
compressed gaseous nitrogen
5797wpdocsgalluprifinaltextmlaquo8terrifhl061297 2-11 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The GC operating condition was checked in the morning and during the day using machine
blanks syringa blanks and standards All three standards were run with a syringe blank directly
before and after each injection after every ten samples and at least once in the morning and once
in the afternoon each day In accordance with the QAQC program and SOP 4009 a duplicate
groundwater sample was collected in the field in a separate 40 ml glass vial immediately
following the collection of the original sample The second vial was used for duplicate analyses
after every ten samples
In the event that a sample analysis showed a contaminant chromatographic peak with an area
greater than the high-concentration standard or the range of the GC operating parameters (off-
scale) a smaller aliquot (l10th the original sample injection volume) was taken from the second
vial and injected into the GC All pertinent information concerning the smaller aliquot was
recorded on the GC strip chart and in the field log book
The GC strip chart was labeled with the sample identification number or corresponding
identification information (eg sample ID syringe blank etc) All pertinent information (eg
sample ID) was recorded in a field log book
In accordance with the QAQC program all samples were kept at 4degC prior to analysis and were
analyzed within 48 hours of their collection time
A total of 23 microwells (TW101-TW123) were installed by Pine and Swallow Associates Inc of
Groton Massachusetts Due to limited ability to access certain locations with the available
equipment the remaining 37 microwells were installed by a second subcontractor MyKroWaters
Inc of Concord Massachusetts Installation logs are presented in Appendix B The results of
the microwell survey are discussed in Section 421 The microwell installations were later
abandoned by filling them with cement grout and cutting the risers off below the ground surface
25 Soil Gas Survey In an effort to identify the location of any previously unknown potential disposal areas a Site-
wide soil gas survey was conducted From September 26 1994 through October 12 1994 a
total of 106 soil gas sampling probes were installed across the Site Soil gas samples were
analyzed on-site using a portable gas chromatograph
A 100-foot sampling grid was used to systematically cover the Site however actual locations
were dependent on accessibility and the ability to advance the soil gas probes to the desired depth
beneath the ground surface Besides the sampling at the intersection of grid lines six additional
locations were investigated due to the presence of empty drums found at the ground surface
5797wpdoC8galluprifinaltextmastemfnl061297 2-12 QST Environmental
Gallups Quarry Superfiind Project - Remedial Investigation
during the Site reconnaissance or anomalies detected during the EM and MAG surveys The
extreme northeastern corner and eastern side of the Site were not included in the soil gas survey
since they are either wetlands or heavily wooded Also an approximate 15000 square foot area
just north of the Former Seepage Bed was not tested due to the presence of a large pile of
boulders The surveyed locations of each soil gas sampling point (SV101-SV206) are shown in
Plate 2-5 The locations of SV111 SV201 and SV141 are approximate based on field
measurements from surveyed locations
Each soil gas sampling probe consisted of a four inch long hardened steel combination drive
point and screen which was connected to an adequate length of 316 inch diameter polyethylene
tubing The pointscreen and tubing assembly were inserted inside a hollow steel shaft which was
then driven into the ground with an electrically powered vibratory hammer
An abundance of gravel cobbles and boulders in the central portion of the Site prohibited the
advancement of several probes to the minimum depth specified in the Work Plan (25 feet) After
discussions with EPAs oversight contractor regarding the surface conditions in this area it was
agreed that at the rocky locations the probe would be driven as far as possible (typically 15-2
feet) and a two-foot by two-foot sheet of polyethylene sheeting would be placed on the ground
surface surrounding the probe and weighted with native topsoil The purpose of the plastic sheet
was to minimize atmospheric influence during the sampling procedure
Once the point was driven to the sampling depth the hollow steel shaft was extracted leaving the
expendable pointscreen and tubing in place The small annular space surrounding the sampling
tube was tightly packed with native soil to ensure that gas samples were representative of soil
pore space and not atmospheric conditions Once the probe was in place any excess plastic
tubing was trimmed leaving approximately 15 feet of tubing above the ground surface Each
tube was clamped and sealed until it was eventually sampled typically within a few days of
installation
To collect a soil gas sample one end of a 280 ml glass sample chamber (equipped with teflon
stopcocks and a sampling septum) was connected to the tubing using a short length of silicon
tubing A battery-operated vacuum pump was then attached to the other end of the chamber and
used to draw a soil gas sample from the tubing Once a sample was acquired the stopcocks were
closed and the pump shut off The sample chamber was then transported to the on-site laboratory
for analysis
Just prior to analysis the needle of a gas tight syringe was inserted through the sampling septum of the glass chamber and an aliquot of the soil gas sample was removed The sample was then
5797wpdoclaquogalluprifinaltextma8terrifiU061297 2-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
injected into the gas chromatograph for analysis A Photovac 10S50 portable gas chromatograph
was used to analyze each sample for the following 8 VOC
bull l2-dichloroethene(DCE)
bull 111-trichloroethane (111 TCA)
bull trichloroethene (TCE)
bull benzene
bull toluene
bull acetone
bull methyl ethyl ketone (MEK)
bull methyl iso-butyl ketone (MIBK)
The Photovac 10S50 gas chromatograph (GC) was filled every morning with zero grade air and
allowed to warm-up for 30 minutes prior to daily operation in accordance with SOP 4001 and
manufacturers instructions
The GC detector flow oven temperature and gain setting (sensitivity setting) were checked and
verified every morning and throughout the day Field GC standards were prepared daily using
certified pure neat liquid standards from sealed vials Glass gas tight syringes were used for
preparation of standards and sample injection All syringes were decontaminated using methanol
deionized water and nitrogen
The GC operating condition was checked in the morning and during the day using machine
blanks syringe blanks and standards Standards were run with a syringe blank directly before
and after each injection every ten samples In accordance with the QAQC program a duplicate
soil gas sample was collected in the field in a separate glass sample chamber immediately
following the collection of the original sample After the original sample was injected into the
GC the duplicate sample from the separate glass sample chamber was injected into the GC The
data quality objective (DQO) for field analysis using the GC was maintained at or better than _+
30 relative percent difference In the event that a sample analysis showed a contaminant
chromatographic peak with an area greater than the range of the GC operating parameters (off-
scale) a smaller aliquot (I10th the original sample injection volume) was taken from the glass
sample chamber and injected into the GC AH pertinent information concerning the smaller
aliquot was recorded on the GC strip chart and in the field log book
5797wpdocsgalluprifinaltextma8teiTifiil061297 2-14 QST Environmental
Gattups Quarry Superfund Project - Remedial Investigation
The GC strip chart was labeled with the sample identification number or corresponding
identification (eg sample ID syringe blank etc) The analysis number and corresponding
identification information was also recorded in the soil gas survey field log book
All sampling equipment (exclusive of the dedicated expendable probes) was decontaminated between each sample by flushing with copious amounts of compressed nitrogen The results of the
soil gas survey are discussed in Section 41
26 Soil Borings at Disposal Areas A total of sixteen soil borings SB101 through SB116 were advanced at the three known former disposal areas Ten soil borings (SB 101 through SB110) were completed as part of the Phase 1A
investigation between October 4 and 13 1994 Six additional borings were advanced within the
Former Primary Disposal Area on November 2 1995 as part of the Phase IB investigation The
locations of the soil borings are shown on Plate 2-5 The objective of these borings was to obtain
soil samples to characterize subsurface lithology and determine the present level and distribution
of residual contaminants within each former disposal area The analyses performed on samples
collected during the Phase 1A investigation (ie SB101-SB110) included TCLTAL parameters
as well as pH (EPA Method 9045) total organic carbon (ASTM Method D 17565373) moisture
content and particle size distribution Samples collected during the Phase IB investigation
(SB111-SB116) were submitted for laboratory analyses for VOC and PCBPesticides The samples submitted for analysis and the depth intervals sampled are shown in Table 2-2 The
results of the soil boring program are discussed in Section 41 All soil boring logs are shown in
Appendix C
261 Piiase 1A Soil Borings Each boring completed as part of the Phase 1A investigation was advanced until equipment refusal was encountered using a truck mounted drill rig equipped with a 425 inch (inside diameter)
hollow stem augers The drilling operations were performed by Environmental Drilling Inc of
Sterling Massachusetts As shown in Plate 2-5 three of the borings were placed in the reported
location of the Former Seepage Bed (SB101-SB103) three were placed within the Former
Secondary Disposal Area (SB104-SB106) and four were placed within the Former Primary
Disposal Area (SB107-SB110) The Work Plan required that samples be collected and submitted
for laboratory analysis from each boring from specific depth intervals (0-1 foot 1 to 10 feet and
10 feet to the water table) and from each distinct hydrological unit encountered (eg coarse
stratified drift fine stratified drift and till) and from the capillary fringe at each disposal area
The number of samples actually submitted for analysis was dependent on the depth to water and
the number of hydrogeologic horizons encountered at each area In general samples submitted
579Twpdoc8galluprifinaltextmlaquo8terrifhl061297 2-15 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
for laboratory analysis were selected from within each depth range or horizon based on PID
readings andcr visual observations
Soil samples from the 0-1 foot interval were collected from the ground surface using a stainless
steel hand trowel All subsequent samples were collected using a standard 2-inch diameter split-
spoon sampling device in accordance with ASTM Method D-1586-84 Each sample was
screened in the field for total VOC using a PID equipped with an 117 eV lamp Each sample
was then visually classified and logged in a field notebook and on boring logs A portion of each
sample was placed into glass jars and sealed with aluminum foil and a screw cap for headspace
analysis The headspace sample was ultimately saved for archival purposes
All sampling equipment was decontaminated prior to use and between each sample using a
detergent wash and tap water rinse followed by methanol nitric acid and deionized water rinses
All drilling equipment was steam cleaned between boring locations All decontamination rinseates
were containerized and eventually transported off-site for treatment and disposal Likewise all
soil cuttings were containerized for eventual off-site disposal Upon completion each borehole
was filled to the ground surface with a bentonitecement grout mixture and marked with a labeled
stake so that its location could be surveyed
262 Phase IB Soil Borings
Data obtained during the Phase 1A investigation indicate the presence of residual soil
contamination in the vicinity of the Former Primary Disposal Area In order to more fully
characterize the extent of this residual contamination six additional soil borings were completed
along the perimeter and within the Former Primary Disposal Area These borings (SB111shy
SB116) were installed by Connecticut Test Borings Inc of Seymour Connecticut using a track
mounted drill rig equipped with a standard split-spoon soil sampler Two samples from each
boring were submitted for laboratory analysis of TCL VOC and pesticidesPCBs At each
location a surface soil sample was collected from the 0-1 foot interval and submitted for
laboratory analysis Soil samples were then collected continuously from a depth of 1 foot below
the ground surface to the water table A discrete sample from within this zone was submitted for
laboratory analysis based on PID results At locations where no elevated PID headspace readings
were encountered a sample collected from the capillary zone was submitted for laboratory
analysis
5797wpdocsglaquolluprifinaItextmraquo8terrifiil061297 2-16 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
27 Installation of Monitoring Wells and Background Soils Sampling
Following the evaluation of data obtained during the visual Site reconnaissance and microwell
and soil gas surveys a network of monitoring wells was designed that would allow groundwater sampling and analysis and measurements of hydraulic parameters The installation of monitoring
wells at upgradient locations was also included to allow collection of background soil samples and
to determine upgradient groundwater quality
The majority of the Phase 1A investigation monitoring wells were installed by Environmental
Drilling Inc of Sterling MA A second drilling contractor Maher Environmental of North Reading MA was added in December in order to complete the monitoring well program before
the onset of winter The well installation program began on November 7 1994 and was completed on December 29 1994
The original Work Plan specified that a total of 47 monitoring wells would be installed but contemplated that the final number and locations of the monitoring wells could be adjusted based
on the findings of the preliminary screening surveys (ie the microwell and soil gas surveys)
Based on these data which were presented to EPA throughout the course of the screening surveys
EPA approved a Phase 1A monitoring well network which consisted of a total of 39 monitoring
wells at 16 locations
During the course of the Phase 1A monitoring well installation program one anticipated
intermediate depth overburden well (MW109T) was not installed because there was only
approximately 35 feet of saturated overburden encountered at that location A total of 38
monitoring wells at 16 locations were installed The surveyed locations of these wells are shown on Plate 2-6
By the end of the Phase 1A field program a total of 16 locations (or clusters) were completed
and were comprised of the following
bull (2) four well clusters (MW105 and MW107)
bull (4) three well clusters (MW101 MW108 MW112 and MW115) bull (8) two well clusters (MW102 MW103 MW104 MW106 MW109 MW113
MW114 andMW116) and
bull (2) single wells (MW110 and MW111)
(Note An additional 6 groundwater piezometers [PZ201-PZ206] were also installed)
5797wpdocsgalluprifinaltextmasterrifhl061297 2-17 QST Environmental
Gallups Quarry Superjvnd Project - Remedial Investigation
To further delineate the nature and extent of contamination and to refine the hydrogeologic
characteristics within the area of investigation a total of seven groundwater monitoring wells (and
one piezometer PZ301) were installed as part of the Phase IB investigation
The wells completed during Phase IB included the following
bull (3) two well clusters (MW117 MW118 and MW119)
bull (1) bedrock well (installed at the Phase 1A location MW102)
All Phase IB monitoring wells were installed by Connecticut Test Boring Inc utilizing a track-
mounted drill rig The surveyed locations of these wells are shown on Plate 2-6
AH monitoring well labels include a suffix code (eg S TT T or B) which indicates the location
of the screened interval (or open interval in the case of bedrock wells) for that particular well
The screen interval for each prefix is
S - Shallow well in which the screen intersects the surface of the water table
TT - Top-of-Till well in which the bottom of the screen is located just above the till
horizon
T - Till well in which the screen was placed within the till horizon and
B - Bedrock well in which the overburden is sealed off with steel casing which is
grouted into the bedrock surface and the well consists of an unscreened open hole
below the top of the bedrock surface
The TT T and B designations are geologically specific (top-of-till till or bedrock) while the S
designation is depth specific Monitoring well MW109S is in fact located within a till horizon but
was designated as an S well since the screen intersected the surface of the water table Similarly
although monitoring well MW110S is designated as a shallow(s) well observations recorded
during its installation indicate that MW110S is set just below the top-of-till interval
Specifically the 45 wells completed during the Phase 1A and IB investigations included the
following
bull 18 shallow (S) water table wells
bull 13 top of till (TT) wells
5797wpdoc8galluprifinaltextmasterrifhl061297 2-18 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull 5 till (T) wells and
bull 9 bedrock (B) wells
271 Phase 1A Monitoring Well Placement-Rationale
2711 Phase 1A Upgradient Monitoring Wells and Background Soil Sampling
Two monitoring well clusters MW109 (S B) and MW112 (S TT B) were installed to provide
soil and groundwater samples from various depths from locations upgradient of the known former
disposal areas These data were obtained to provide chemical data which was assumed to be
representative of background conditions The general location of these two well clusters was in
accordance with the general east to west direction of groundwater flow across the Site which had
been indicated during previous investigations and by the location of the contaminant plume
identified during the microwell survey The location of MW112 cluster (south of the Former
Seepage Bed) would also serve to confirm the presence or absence of radial groundwater flow
patterns away from the Former Seepage Bed During the installation of these wells soil samples
from stratified drift and till horizons were collected and submitted for laboratory analysis for
TALTCL parameters
A shallow top of till and bedrock well were installed at location MW112 The overburden wells
at this location were successfully installed using hollow stem augers A shallow till and bedrock
well were planned for location MW109 However since only approximately 35 feet of saturated
overburden was encountered at that location only one well MW109S was installed in the
overburden
The overburden and bedrock monitoring wells at these locations were constructed in accordance
with the general procedures described above with the exception of MW109S An abundance of boulders at this location prohibited the ability to advance augers or drive casing more than several
feet below the ground surface After numerous attempts within a 100-foot radius of the desired
location a backhoe was ultimately required to excavate a pilot hole in the unsaturated zone to
approximately 8 feet below the ground surface Augers were then lowered into the pilot hole and
advanced to the refusal depth of 12 feet The overburden well was then constructed as described
in Section 273
The bedrock well at MW109 was installed using a mud rotary drilling technique to drill an
overburden pilot hole to the bedrock surface into which 5-inch diameter steel casing was lowered
and seated on the top of the bedrock surface Another pilot hole was then drilled into the bedrock
to receive the permanent 3-inch casing The bedrock was subsequently cored as described in
Section 273
5797wpdoC8galluprifinaltextmaBterriftU061297 2-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
2712 Phase 1A Monitoring Wells - Former Primary and Secondary Disposal Areas
A total of nineteen ground water monitoring wells were installed in seven cluster locations at
downgradient areas relative to the known Former Primary and Secondary Disposal Areas
Monitoring wells MW102 (S TT) MW105 (S TT T B) and MW107 (S TT T B) were
located along the centerline of a groundwater contaminant plume detected during the microwell
survey and earlier studies
Well clusters MW101 (S TT T) MW103 (S TT) MW104 (S TT) and MW106 (S TT) were
located in areas believed to be beyond the edges of the contaminant plume delineated during the
microwell survey These wells were placed at these locations in an effort to define the plume
boundaries In addition the location of MW103 was selected by EPA to address historic
references to a leachate seep reportedly observed at Mill Brook west of the railroad bridge
Besides the nineteen wells described above another six monitoring wells at three locations were
installed in the vicinity of the Former Primary and Secondary Disposal Areas MW116 (S T) MW108 (S TT B) and MW110S were located north northeast and east of the former disposal
areas respectively to confirm the plume boundaries in these areas
2713 Phase 1A Monitoring Wells - Former Seepage Bed Area
A total of three monitoring wells were installed in the general vicinity of the Former Seepage
Bed A single bedrock well MW11 IB was placed west of the Former Seepage Bed within the
potential fracturefault zone identified by the geophysical studies The purpose of this well was to
assist in evaluation of whether the inferred fracturefault zone may be acting as a preferential
contaminant transport pathway from the Former Seepage Bed The location of MW113 (S B)
west of the Former Seepage Bed was selected to confirm water quality and to obtain
hydrogeological data in this area since an abundance of cobbles prohibited the advancement of
microwells into the saturated zone in this area
2714 Phase 1A Monitoring Wells - Southern Portion of the Site
Five monitoring wells located at two clusters (MW114 and MW115) were installed to determine
water quality and to characterize the hydrogeological parameters in the southern portion of the
Site Although there is no evidence to suggest that disposal activities occurred in areas of the Site
south of the Former Seepage Bed MW114 (S TT) and MW115 (S TT B) were placed to
coincide with locations at which low levels of VOC were detected during the microwell survey
5797wpdocsgalluprifinaltextmasterri fhl061297 2-20 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
272 Phase IB Monitoring Well Placement-Rationale The results of the Phase 1A investigation indicate that a well-defined low to moderate-VOC
concentration groundwater plume originates in the vicinity of the Former Primary Disposal Area
The plume is defined by the presence of certain VOC primarily TCA 12-DCE and xylene The
highest concentrations of these compounds were detected at MW107TT with decreasing
concentrations at downgradient well clusters MW105 MW102 and MW101
The compound PCE was detected in groundwater monitoring wells within the plume but its
distribution in groundwater exhibited inconsistencies with migration from the former disposal
areas In addition the observed concentrations of PCE did not coincide with the observed rate of
plume attenuation and transport rates possibly indicating an off-site source A goal of the Phase
IB investigation was to obtain additional information concerning overburden groundwater quality
and flow patterns in the area north-northwest of the Former Primary Disposal Area in order to
assess the potential for an off-site source
2721 Phase IB Monitoring Wells-Former Primary and Secondary Disposal Areas
One bedrock monitoring well (MW102B) was installed downgradient of the Former Primary and
Secondary Disposal Areas as part of the Phase IB investigation Data collected during the Phase
1A field program indicate that bedrock hydraulic gradients are generally upward across the Study
Area and that bedrock is not a preferential pathway for contaminant migration However low
concentrations of certain VOC were detected in bedrock well MW105B located downgradient of
the Former Primary Disposal Area To determine the nature of contaminant migration in bedrock
further downgradient from the source area a bedrock monitoring well was installed in the vicinity
of well cluster MW102 During the installation of MW102B soil samples were collected from
three intervals within the saturated portion of the overburden aquifer (15-17 30-32 and 45-57
feet below the ground surface) and submitted for laboratory analysis for total organic carbon
(EPA Method 9060)
2722 Phase IB Monitoring Well - North-Northwest of the Site Data obtained from CTDEP files during the Phase 1A investigation indicate that monitoring wells
located on the western and northern sides of the former Pervel flock plant (located just north of
the Site across Mill Brook) historically contained elevated concentrations of certain VOC
particularly PCE TCA and DCE A contribution of VOC in groundwater from this area could
explain at least partly the VOC detections in the wells at MW101 To confirm the potential for
groundwater flow from the former Pervel facility to the area around well MW101 and to further
refine the understanding of groundwater quality and flow in areas north-northwest of the Former
Primary Disposal Area three additional monitoring well couplets and one groundwater piezometer
5797wpdocsgalluprifinaltextmasterrifiil061297 2-21 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
were installed The Phase IB well couplets designated as MW117 MW118 and MW119
consisted of a shallow overburden well and a deep monitoring well screened above the till
horizon A groundwater piezometer designated as PZ-301 was installed in this area to provide
additional hydraulic data The surveyed locations of the seven monitoring wells and the
piezometer installed as part of the Phase IB investigation are shown on Plate 2-6
273 General Monitoring Well Installation Techniques
At each monitoring well (or cluster) location continuous soil sampling was initiated using either a
truck or track mounted drill rig equipped with 425 inch (ID) hollow stem augers and standard 2shy
inch diameter split-spoons The objective was to continuously sample and complete the deepest
overburden boring at each location using hollow stem augers A variety of subsurface conditions
(eg running sands greater that anticipated saturated overburden thicknesses and an abundance of
cobbles and boulders) prohibited the use of hollow stem augers all the way to completion depth at
many locations In order to overcome these drilling conditions EPA approved drive and wash
drilling techniques using water as a drilling fluid to complete many of the deeper overburden
monitoring wells The source of drilling water for this investigation was a nearby fire hydrant
which is connected to the local municipal potable supply system The introduction of drilling
fluids is generally avoided whenever possible as the presence of foreign fluids may cause some
dilution of any constituents which may be present The subsequent use of low-flow purging and
sampling techniques (discussed in Section 29) gave maximum assurance that samples collected
were representative of the natural formation waters
When drive and wash techniques were used the preferred casing diameter was six-inches Six-
inch diameter casing allowed the construction of a desired filterpack thickness of two inches (for
two inch diameter wells) However five-inch diameter and in some cases four-inch diameter
casing was also used primarily at locations in which access and drilling conditions prohibited the
advancement of six-inch casing in a timely and efficient manner EPA approved the use of five-
and four- inch diameter casing provided that the resulting monitoring wells were capable of
yielding low turbidity groundwater samples (which they ultimately did)
In accordance with the Work Plan continuous soil sampling was attempted at the deepest boring
at each location to provide continuous stratigraphic control However the presence of
uncontrollable running sands within certain intervals at several locations made the timely
collection of continuous viable samples extremely difficult In an effort to adhere to the original
schedule as closely as possible EPA approved lengthening the sampling frequency from
continuous to five-foot intervals at locations where running sands were encountered
5797wpdocsgalluprifinaltextmasterrifhI061297 2-22 QST Environmental
Gallups Quarry Superfitnd Project - Remedial Investigation
At several locations auger or casing refusal during the sampling stage was encountered above the
expected depth to bedrock (ie within or on top of the till horizon) At certain bedrock locations
which did not require further soil sampling EPA approved advancing and setting casing using
mud rotary drilling techniques In cases where drilling mud was used as the circulation media
powdered bentonite (National Sanitation Foundation International approved) was mixed with
potable water to yield a relatively thin drilling mud Once the borehole was drilled and stabilized
with drilling mud permanent steel casing was advanced and set The drilling mud was then
completely flushed from the borehole using fresh water and containerized (along with the water)
for eventual disposal In general the use of drilling mud is avoided whenever possible to
eliminate the introduction of foreign compounds in the aquifer Since drilling mud was used to
drill through overburden material (at bedrock wells only) and drilling mud was never in contact
with bedrock fractures the use of mud is not believed to have had any impact on groundwater
samples collected from these wells
All overburden monitoring wells were constructed using 2-inch diameter schedule 40 PVC well
screen and riser All screens consisted of continuous slot construction with 001-inch wide slots
The filter pack sand size grade was selected based on grain size data obtained during the soil
boring program The size-grade chosen (Morie OON) was selected in accordance with EPA
requirements (4 to 6 times the mesh size which retained 70 of the formation material) Most
screens were 10 feet long however several wells screened in till were constructed using 5-foot
long screens due to the limited thickness of the till horizon at those locations (MW105T
MW112T and MW116T) and the requirement to not install screens across different geologic
horizons Regardless of the screen length the filterpack surrounding the well screen extended a
minimum of one foot above the top of the screen A minimum two-foot thick seal of hydrated
bentonite clay was then emplaced above the filter sand pack Bentonitecement grout was then pumped from the bottom of the remaining annular space surrounding the riser pipe to the ground
surface Stainless steel centralizers were utilized to center the PVC screen within the borehole
Each well was completed with a locking 4-inch diameter steel protective casing which was
cemented in place approximately five feet below the ground surface
The bedrock wells were completed as open hole monitoring wells A minimum of four-inch
diameter steel casing was driven and seated on the bedrock surface A 3875-inch diameter pilot
hole was then drilled a maximum distance of five feet into competent rock Permanent 3-inch
diameter steel casing was then cemented into the pilot hole using tremie pipe and allowed to cure
for a minimum of 24 hours Once cured the grout inside the three inch casing was drilled out to
allow the bedrock to be cored At each location a minimum of 10 feet and a maximum of 25
feet of rock was cored using standard NX coring equipment The termination of all bedrock
wells was dependent on the occurrence of water-bearing fractures identified within the cored hole
5797wpdocsgalluprifinaltextmasterrifhl061297 2-23 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
Coring was terminated when evidence of water-bearing fractures were encountered All bedrock
wells were corHeted as open bedrock wells (ie not screened) as it appeared that the cpen holes
would not in-fl or collapse Each bedrock well was furnished with a locking 4-inch diameter
steel protective casing which was cemented in place over the permanent 3-inch diameter steel
riser
All monitoring wells were developed to remove residual particulates from the well and filter pack
and to restore the natural permeability of the formation Following well completion a minimum
of 48 hours were allowed to elapse before well development was initiated to allow the wells to
equilibrate and the grout to set Development was accomplished by overpumping various sections
of the screened interval until the field geologist determined that the pump discharge was visibly
free of particulate material Well development times varied from well to well and depended upon
the amount of fine (silt-clay) grained material at each screen interval Well development times
were usually on the order of several hours Water generated during well development was
containerized for eventual shipment off-site
All soil boring logs rock coring logs and monitoring well construction logs are provided in
Appendix C A summary table which shows survey data and other pertinent information for each
monitoring well and piezometer is presented as Table 2-3
274 Stream Piezometers and Gauges
Nine piezometers were installed at various locations within Mill Brook to monitor surface water
conditions and to determine the role of the local groundwater system in relation to stream
dynamics Water levels were recorded during several periods of the investigation to determine if
Mill Brook is a discharge or recharge point for groundwater in the vicinity of the Site In
addition five stream gauges were installed at piezometer locations PZ-1 PZ-3 and PZ-6 and at
two additional locations in Fry Brook one above and one below the confluence with Mill Brook
The locations of the stream piezometers and gauges are shown on Plate 2-6
Each stream piezometer consisted of a one-foot long slotted steel well point connected to threaded
and coupled lengths 125 inch ID steel pipe with a threaded cap The piezometers were
manually driven a minimum of two feet into the stream bed Water level readings were collected
by lowering an electronic water level indicator along both the inside and outside of the piezometer
to obtain depth to water readings for shallow groundwater beneath the stream bed and depth to
surface water respectively The stream gauges consist of a graduated steel scale attached to a
steel post which was driven into the stream bed
5797wpdocsgalluprifinaltex1masterrifhl061297 2-24 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
275 Groundwater Piezometers
Although not specified in the Phase 1A Work Plan EPA approved the installation of six shallow
groundwater piezometers (PZ-201 through PZ-206) in the southern portion of the Study Area to
provide additional overburden piezometric data A seventh groundwater piezometer PZ-301
was installed north of the Site during the Phase IB investigation The locations of the
groundwater piezometers PZ-201 through PZ-206 and PZ-301 are provided on Plate 2-6
The seven groundwater piezometers were installed using either a track or a truck-mounted drill
rig equipped with 425 inside diameter hollow stem augers At each location the augers were
advanced and the piezometer set at approximately five feet below the top of the groundwater
table The piezometers were constructed of 1-inch diameter PVC well screen and riser equipped
with five-foot long screens Once the screen was set a sand pack was installed to approximately
one foot above the top of the screen A hydrated bentonite seal was then emplaced on top of the
filterpack The remainder of die annular space was backfilled with clean native soil and capped
with concrete Each piezometer was furnished with a lockable protective casing which was
cemented in place Upon completion each piezometer was surveyed and included in each
subsequent round of groundwater level measurements
28 Aquifer Parameter Testing 281 Grain Size Analysis
A total of 41 soil samples collected during the Phase 1A soil boring and monitoring well
installation programs were submitted for laboratory grain size analysis All grain size analyses
were performed using common sieve and hydrometer techniques in accordance with ASTM
Method D 422-63 (Reapproved 1990)
Of the 41 samples 16 were obtained from horizons described as fine stratified drift 15 were
obtained from horizons described as coarse stratified drift and 10 were obtained from horizons
described as till A total of 29 of the samples were obtained during the soil boring program
and 12 were obtained from samples collected during the monitoring well installation program
The analyses were conducted by Geotechnics Inc of Pittsburgh PA a laboratory which
specializes in geotechnical analyses A summary of the samples submitted and their depth interval
is presented as Table 2-4 The results of grain size analyses are discussed in Section 33 In
addition to grain size these samples were also submitted for laboratory analysis for pH moisture
content and total organic carbon
5797wpdoc8galluprifinaltextmasterrifhl061297 2-25 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
282 Slug Tests
Single-well variable head aquifer tests were conducted on all the wells installed during the Phase
1A investigation between January 5 and 27 1995 Rising and falling head tests were performed
on each well using a manually deployed solid cylinder or slug A pressure transducer and an
electronic data logger were used to measure and record the water level response in the well (on a
logarithmic time scale) after the slug was submerged (falling head) and removed (rising head)
Changes in water levels were recorded until the water had returned to or near the original static
level The data collected from the slug tests were analyzed to determine hydraulic conductivity
values for the screened intervals in each well The rate of change of hydraulic head was analyzed
using the Bouwer-Rice Method (Bouwer and Rice 1976) implemented in the computer program
AQTESOLV (Geraghty amp Miller Inc 1989) The results are presented in Section 33 of this
report
283 Constant Flow Tests
Constant flow tests consisting of short-term pumping tests were performed on selected
groundwater monitoring wells as part of the Phase IB investigation Constant flow tests were performed on the following wells MW102TT MW103TT MW104TT MW105TT
MW107TT MW117(S TT) MW118(S T) and MW119(S TT) In these tests an approximate
steady-state drawdown is established in the well and an analytical model of flow to a well is used
to compute hydraulic conductivity The tests were conducted using a variable speed submersible
pump and an electronic water level indicator Prior to the start of each test the static water level
was determined The tests were conducted by running the pumps at a constant known pumping
rate for short periods of time (typically less than 15 minutes) while recording drawdown until
equilibrium was reached The pumping rate drawdown and well construction details were then
used to calculate the hydraulic conductivity The results of the constant flow tests are discussed
in Section 33 of this report Field data and examples of the data reduction method are presented
in Appendix F
29 Groundwater Sampling In accordance with the Work Plan a complete round of groundwater samples was collected
following completion of the Phase 1A monitoring well installation program during January 11shy
19 1995 and is referred to as the Phase lAJanuary 1995 sampling event Subsequent
sampling events were performed as part of the Long Term Monitoring Program during April
July and November 1995 February May August and November 1996 and February 1997 As
discussed in Section 1-1 of this report individual Data Reports for all of the Long-Term
Monitoring Program sampling events (except November 1995 which was presented with the draft
RI Report) have been submitted to EPA
5797wpdoc8galIuprifin8ltextma8terrifnl061297 2-26 QZT Environmental
Gallups Quarry Suptrfund Project - Remedial Investigation
During the Phase IB field program seven new wells were installed and added to the list of wells
that were sampled (for VOC only) during the November 1995 monitoring event Six of these
wells (MW117STT MW118STT and MW119STT) were not added to the list of wells to be
sampled under the Long Term Monitoring Program although MW102B (also installed during
Phase IB) was added to the Long Term Monitoring list In addition to the wells installed during
the Phase IB investigation the following five existing wells located on the former Pervel
property were included as part of the Phase IBNovember 1995 sampling event MW-A -B -C
-2 and -3 The existing on-site wells SW-3S and SW-3D were also included in the Phase
IBNovember 1995 sampling event and the subsequent Long-Term Monitoring Program sampling
events Since the November 1995 Long-Term Monitoring event included wells that were specific
to the Phase IB investigation the November 1995 sampling event is referred to as Phase
IBNovember 1995
During the period spanning the nine sampling events discussed in this report EPA has approved
modifications to the list of wells sampled under the Long-Term Monitoring Program
Modifications to the list of wells sampled have been to delete certain wells particularly those
located in the southern portion of the Site where no site related compounds have been or are
expected to be detected After the July 1995 sampling event wells at the following locations
were eliminated from the Long Term Monitoring Program MW111 MW112 MW114 SW-9
SW-10 and SW-12 Monitoring wells located at MW110 MW113 and MW115 were eliminated
following the Phase IBNovember 1995 sampling event The following subsections describe the
field methods which have been used consistently over the nine sampling events discussed in this
report Table 2-5 shows which wells were included in each sampling event
291 Monitoring Wells The groundwater sampling locations are shown on Plate 2-4 Low-flow purging and sampling
procedures were used to collect groundwater samples in an effort to obtain turbidity-free samples
and to minimize disturbance of the natural formation
The following sequential procedures were employed during the groundwater sampling effort
1) The static water level was measured using an electronic water level indicator
2) The absence of LNAPL was visually confirmed by observation of a sample
collected using a clear plastic bailer
3) All 2 inch diameter (or larger) monitoring wells were sampled using a stainless steel electric submersible pump (Grundfos Redi-Flo 2) equipped with teflon
5797wpdocsgalluprifinaltextmasterrifhl061297 2-27 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
discharge tubing To initiate the purging procedure the intake for the pump was
owered into the mid-section of the well screen For wells smaller than 2 inch
aiameter (ie existing SW- series wells) Teflon tubing equipped with a bottom
check valve was used to inertially purge the well
4) Water was purged from the well at a low flow rate (approximately 05 litersmin)
which was continuously monitored The water quality field parameters
(temperature pH conductivity and turbidity) were monitored during the purging
process until they had stabilized within 10 over three consecutive readings
5) Once the parameters had stabilized (or a minimum of five well volumes had been
purged) groundwater samples were collected for laboratory analysis Samples
were collected from the discharge end of the pump tubing by directly filling the
appropriate sample containers in the following order VOC SVOC (including
pesticides and PCB) metals inorganic compounds At wells that did not stabilize
below the 5 NTU turbidity requirement additional metals samples were collected
filtered through a 045 micron filter and submitted for dissolved metals analyses
(in addition to total metals)
6) Samples were collected from the upper and lower portion of each well using a
clear plastic bailer to visually assess the potential presence of NAPL
All sampling equipment was decontaminated between sampling events All purge water was
containerized for eventual off-site disposal
Duplicate samples matrix spikes matrix spike duplicates field blanks and trip blanks were
included as part of the QAQC procedures All groundwater monitoring sampling forms are
included as Appendix D Most groundwater samples were submitted for TALTCL VOC SVOC
pesticidesPCB and metals although a small number of samples collected during the Phase
lAJanuary 1995 and April 1995 event were submitted for VOC SVOC pesticidesPCB and
metals by Appendix IX methods Also certain samples were selectively submitted for VOC
analyses by Method 5242 The analytical methods for each sample submitted for laboratory
analysis are shown in Table 2-5
5797wpdocsgalluprifinlaquoltextmlaquosterrifhl061297 2-28 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
292 Residential Wells A total of fourteen private drinking water supply wells (DW101-DW114) were scheduled to be
sampled as part of the groundwater sampling program However two of the residences (DW101
and DW112) were unoccupied and inaccessible at the time of each of the sampling events The
residential wells are located along the eastern perimeter of the Site along Route 12 (Norwich
Road) adjacent to the southern portion of the Site along Tarbox Road and along Lillibridge
Road well south of the Site The residential well sampling locations are provided on Plate 2-5
In accordance with the Long-Term Monitoring Program the residential wells were sampled on a
semi-annual basis during the regularly scheduled summer and winter quarterly sampling events
In addition to the Phase lAJanuary 1995 sampling event residential groundwater samples were
collected during July 1995 February 1996 and August 1996 as shown in Table 2-5
Prior to the collection of groundwater samples from the residential wells a visual survey was
conducted to identify the sampling point closest to the well and to determine if any treatment
systems were in use A description and sketch of the supply system was recorded in field
notebooks Each system was opened and allowed to drain for approximately 15 minutes to purge
the plumbing system and obtain representative samples Field parameters were recorded during
purging to determine when stabilization had occurred The groundwater samples collected from
the residential wells were submitted for laboratory analysis of TCL SVOC pesticides PCB TAL
metalscyanide and VOC using EPA Method 5242
210 Surface Water and Sediment Sampling As part of the Phase 1A Investigation surface water and sediment sampling was conducted on
September 13-16 November 22 and December 29 1994 Although all locations were originally
sampled during the September sampling event three samples were lost in transit and had to be reshycollected A total of seventeen sample locations along Mill Brook and unnamed tributaries (UB1shy
UB10 and LB1-LB2) Fry Brook (FBI) Packers Pond (PP1-PP3) and a small pond along Tarbox
Road (TR1) were included in this program The re-sampled locations were UBS and UB6 (112294) and TR1 (122994) Due to dry conditions surface water samples could not be
obtained from the following locations UBS UBS UB6 UB7 and PP1
In accordance with the Long Term Monitoring program additional surface water samples were
collected during the April 1995 November 1995 May 1996 and November 1996 sampling
events to coincide with the approximate seasonal high- (ie spring) and low-water (ie autumn)
periods Following the initial Phase lAJanuary 1995 sampling event and per the request of
EPA the location of UB6 was moved due south to Mill Brook and renamed UB6A The surface
watersediment sample locations are shown on Plate 2-6 Sample locations by date are shown on
Table 2-5
5797wpdocsgalluprifiMltextmasterrifhl061297 2-29 Q5T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Surface water samples were collected using the actual laboratory sample containers by direct
immersion into the water Parameters which required the use of preservatives (eg metals
requires the addition of nitric acid to the sample) were collected in a stainless steel beaker and
transferred directly to the sample container to prevent loss of the preservatives during sampling
All sampling equipment was decontaminated after each use and placed into clean plastic bags
before moving on to the next station Surface water samples were collected starting at the most
downstream locations and progressed in order upstream The surface water samples were
submitted for laboratory analysis for TCLTAL compounds VOC and the following wet
chemistry parameters total organic carbon total dissolved solids total suspended solids hardness
and alkalinity The samples collected during April 1995 November 1995 and May 1996 were
also submitted for laboratory analysis of SVOC pesticides and PCBs The following field
measurements were also collected as part of the sample collection temperature conductivity
pH dissolved oxygen and turbidity
In addition to surface water during September 1994 sediment samples were collected at each of
the 17 locations (including the dry locations referenced above) Samples were collected at a depth
of 0 - 8 below the surface using manually operated soil or mud augers which were
decontaminated between sample locations The sediment samples were collected starting at the
most downstream locations and progressed in order upstream The sediment samples collected
contained greater than 30 percent solids based on visual and manual determination Samples were
submitted for laboratory analysis for TCLTAL compounds and for total organic carbon
Physical stream bed parameters (width depth and flow rate) were measured at surface water
sampling locations where discernable flow occurred This task was completed in April 1995
since the stream was at extremely low flow stages during the September 1994 sampling round
and a number of surface water sampling locations were nearly dry During the April 1995
surface water sampling event stream flow conditions were such that flow rates could be measured
at the following 5 locations UB4 UB6A UB9 UB10 FBI Locations at Packers Pond and the
small pond on the south side of Tarbox Road (TR-1) were not subject to these stream
measurements
Stream width and depth measurements were made using a fiberglass tape measure Depth and
stream flow measurements were recorded at the midpoint and quarter-points across the stream
Stream flow measurements were recorded using a Swoffer model 2100 in-situ flow meter The
flow meter was mounted on a graduated aluminum shaft which was equipped with an electronic
digital readout To calculate stream-flow the average cross-sectional area in square feet was
multiplied by the average water velocity (feetsec)
5797wpdocsgraquolluprifinaltextmasterrifhl061297 2-30 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
211 Wetland Soil Sampling In early September 1994 samples of wetland soils were collected from 10 locations within the
Study Area These sample locations (QW1-QW10) are shown on Plate 2-6 (and on Plate 3-14
which shows delineated wetlands as discussed in Section 341) Each sampling station was
marked with labeled stakes which were eventually included in the Site location survey The
samples were collected at locations situated near the edge of the wetlands at depths within one foot of the water table and below the organic mat The samples were collected using manually
operated soil or mud augers which were decontaminated between sample locations The samples were submitted for analysis of TCLTAL compounds and total organic carbon The results of the
wetland soil sampling program are discussed in Section 43
212 Evaluation of Existing Monitoring Wells As part of the Phase 1A investigation the remaining 11 monitoring wells installed during the
1978 Fuss and ONeill Inc investigation were evaluated to determine which wells could provide
usable water level data The present condition of each well was documented and a water level and total depth measurement were taken and compared to well construction logs If the wells
were determined to be potentially viable an attempt was made to test them for hydraulic
responsiveness by conducting rising and falling head slug tests Several of the wells were missing
protective casings had been broken off below the ground surface or had infilled with sediment
The results of the hydraulic evaluations are presented in Section 33 The locations of the
remaining existing monitoring wells are shown on Plate 2-4
A summary of the condition of each existing monitoring well is presented as Table 2-6 The
majority of the existing wells are presently in poor condition Most of these wells are lacking
surface seals andor adequate protective casings Several of the wells have no protective casings at all and are comprised only of PVC riser which is broken at or near the ground surface
Based on the present total depths of several of these wells compared to their total depths at the time of construction it is evident that the screen section of several of these wells have infilled
with sand or silt Based on their present condition and the fact that new monitoring wells have
been installed ESE recommended that any of the existing wells not included as part of the Long-
Term Monitoring Program be properly abandoned Following this recommendation EPA
approved the abandonment of the following wells SW13 SW14 SW17S D and SW18 Also
the protective casings at existing wells SW-3S SW-3D SW-9 SW-10 and SW-12 were repaired
since these wells are used to measure groundwater elevations as part of the Long-Term
Monitoring Program
5797wpdoc8galluprifinaltextmasterrifhl061297 2-31 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
213 Ecological Assessment 2131 Wetlanl Delineation
A wetland delineation was conducted on Site and focused primarily on the wetlands located north
and west of the Study Area This survey was limited to the Site side of Mill Brook up to the
present channel In order to meet both Federal and State requirements two methods were used to
delineate the Study Area wetland boundaries In accordance with federal requirements wetlands
were delineated using US Army Corps of Engineers (COE) methods Since the State of
Connecticut recognizes a slightly different methodology for wetland delineation the services of a
soil scientist certified by the Society of Soil Scientists of Southern New England were also
required The only difference between the two methods is that while the COE requires analysis
of vegetation composition hydrology and hydric soil indicators the State of Connecticut requires
only the analysis of hydric soil indicators
Jurisdictional wetland boundaries were determined by evaluating several points along the
hydrologic gradient Vegetation soil and hydrology criteria were measured or observed to
determine whether the point was within or above the Jurisdictional wetland boundary In order
for an area to be judged Jurisdictional wetland criteria must be met for all three parameters (ie
vegetation hydrology and soil)
21311 Vegetation
Wetland criteria for vegetation was based on the National List of Plant Species That Occur in
Wetlands (Reed 1988) Dominant plant species were identified at the observation point and listed
on data forms for routine on-site wetland determination The stratum where the plant occurred
(canopy shrub or herb) and indicator status for that plant were recorded A dominance of
wetland indicator species indicates that the vegetation criteria is met A dominance of upland
indicator species indicates that wetland criteria are not met
21312 Hydrology
Hydrologic criteria includes the visual observation of surface water inundation soil saturation or
indirect indication of previous saturation or inundation Indirect evidence includes watermarks
(stain lines on vegetation or structures) drift lines (debris deposited in a line at the high water
mark) sediment deposits and drainage patterns within wetlands
21313 Hydric Soils
The identification of hydric soil criteria includes soil types named as hydric by USDA Soil
Conservation Service or the presence of hydric indicators within the soil profile Indicators
include mottling or streaking of organic materials high organic content the presence of sulfitic
material soil colors (gleyed colors) and others
5797wpdoc8galluprifinaltextmasteirifhl061297 2-32 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
2132 Plant and Wildlife Survey
The objective of the Phase 1A ecological assessment was to qualitatively identify any real or
potential impacts to local ecological receptors within the Study Area or otherwise influenced by
the conditions originating at the Site All observations on plants and animals were noted in field
logs during the wetland delineation
The results of this survey will assist the EPA in the performance of a more formal ecological risk
assessment During the ecological risk assessment sediment soil water and air quality data and
observations of plant and animal communities will be used (see also Section 123) to identify any areas where impacts have occurred The results of the qualitative plant and animal survey
conducted during the wetland investigation are discussed in Section 34 of the text
214 Test Pit Explorations In lieu of ground penetrating radar surveys (as discussed in Section 233) and with EPA
approval additional EM and MAG surveys were performed over a five-foot by five-foot grid in
the vicinity of unexplainable anomalies which were detected during the initial EM and MAG
surveys Once accurate locations for the anomalies were determined and marked on the ground
surface test pit explorations were conducted to confirm the source of the anomalies
On December 21 1994 test pits were excavated at a total of four locations at which
unexplainable anomalies were detected The test pits were performed under the observation of
EPA oversight contractor personnel The locations of the four anomalies and associated test pits are shown on Plate 2-7 At each anomaly a trench (or series of trenches) was systematically
excavated in one to two foot lifts using a backhoe The trenches were oriented to intersect the
longest axis of each anomaly to maximize the possibility of unearthing the source of the anomaly Once a lift was complete soil obtained from the trench walls as well as that obtained from the
backhoe bucket was screened with a PID for evidence of VOC The excavated soil and the trench
itself were also visually monitored for objects capable of producing the anomalies detected during the geophysical surveys and for other features possibly associated with disposal activities (eg
stained soil)
Once the source of each anomaly was discovered the object was excavated and the test pit was
backfilled and regraded with clean soil obtained from the excavation Since no elevated PID
readings or other signs of disposal features were encountered during the test pit operations no
soil samples were submitted for laboratory analysis Test pit logs for these excavations are
presented in Appendix E
5797wpdocsgalluprifinaltextmasterrifhl061297 2-33 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
30 Physical Characteristics of the Study Area
31 General Characteristics 311 Regional Physiography
The Site is located along the eastern border of the Quinebaug Valley Lowland This regional
feature is dominated by the southerly flowing Quinebaug River and is comprised of a north-south
trending lowland area which is approximately 2 to 3 miles in width and approximately 25 miles
long The Quinebaug River originates at headwaters located in central Massachusetts and
terminates at Norwich Connecticut where it merges with the Shetucket River approximately 12 miles south of the Site The confluence of these two rivers form the Thames River which flows
to the south approximately 15 miles and ultimately discharges into Long Island Sound
The region is characterized by relatively low relief and numerous glacial features The regional
landscape is significantly influenced by the structure of the underlying crystalline metamorphic
bedrock which is discontinuously overlain by Pleistocene glacial sediments of variable thickness
Lowland surficial features are characteristic of late Pleistocene glacial retreat processes and
include numerous kettleholes and swamps many of which are interconnected by a network of
slow draining streams
Land surface elevations in the vicinity of the Site range from approximately 150 to just over 220
feet above sea level Lowlands are bounded to the east and west by upland terrain which consists of irregular hilly areas of moderate relief The uplands contain many areas with large bedrock
ledges generally thin glacial deposits (predominantly till) poorly drained valleys and small
isolated swamps Elevations in the uplands range from 200 to 600 feet above sea level
312 Study Area Physiography
The topography on the Site is highly irregular primarily due to past quarrying operations
Numerous overgrown mounds of earthen materials (eg crushed stone sand and gravel) and
excavated depressions are scattered throughout the Site Visual reconnaissance and a number of
screening surveys (eg soil gas and surface geophysical investigations) have confirmed that many
of the features previously identified from the review of historic aerial photographs as potential
disposal areas (Bionetics 1990) were in fact features remnant of quarrying and former CTDOT
operations
The ground surface on the Site (shown on Plate 3-1) generally slopes from east to west and to a
large degree is controlled by the underlying bedrock surface The highest point within the Study
Area consists of a bedrock high overlain by a thin veneer of till and is located in the eastern
5797wpdoclaquogalluprifinraquoltextma8terri fhl061297 3-1 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
central portion of the Site Elevations in this vicinity peak at approximately 230 feet above sea
level
The northern portion of the Site which includes the Former Primary and Secondary Disposal
Areas consists predominantly of open sparsely or non-vegetated areas of sand and gravel This cover material is presumed to have been distributed over the ground surface following CTDEP
Site remediation efforts in 1979 Presently the Former Primary and Secondary Disposal Areas are visible as roughly circular depressions which are approximately 150 feet and 60 feet in
diameter respectively The depressions are approximately 8 to 12 feet deep relative to the
surrounding ground surface These depressions intermittently contain as much as several inches
of standing water which accumulates during periods of heavy precipitation The bottoms of the
depressions are lightly vegetated with various grasses and weeds
North and west of the Site the ground surface elevation decreases as the Mill Brook floodplain is
encountered The floodplain area consists of low lying heavily vegetated wetland areas which
are periodically inundated
Excluding the isolated topographic high spot at the eastern margin of the Site the southern
portion of the Site (from the vicinity of the Former Seepage Bed to Tarbox Road) can be
described as generally flat but includes numerous man-made small-scale features such as
mounds or depressions
313 Surface Water Features
The Site is centrally located within the Mill Brook drainage basin which encompasses
approximately 18 square miles The Mill Brook drainage basin is part of the larger Quinebaug
River regional drainage basin Mill Brook a tributary to the Quinebaug River is located 250 feet
north of the Site and flows from east to west Approximately 1000 feet northwest of the Site (in
the vicinity of the Plainfield municipal sewage treatment plant) Mill Brook is joined by Fry
Brook which flows from the north Packers Pond which is located approximately 3000 feet
west of the Site was formed by the construction of a dam across Mill Brook
There are no surface water bodies located on the Site itself although several low areas (which
were excavated during previous site activities) have been observed to contain ponded water during
periods of extended precipitation
Surface water flow rates (determined during the April 1995 sampling event) were determined for
the following five locations in Mill Brook UB4 UB6A UB9 UB10 and at FBI in Fry Brook
Along Mill Brook flow rates ranged from approximately 23 cubic feet per second (cfs) at the
5797wpdocsgalluprifinaltextmasterrifnl061297 3-2 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
most upstream location (UB4) to approximately 31 cfs at the most downstream location (UB10)
Along the northern Study Area a 3 cfs increase was observed from Stations UB6 to UB10
representing a flow rate increase of about 025 cfs per 100 feet of stream length The flow rate in Fry Brook (Station FBI) was approximately 16 cfs
314 Climate The Site is located within Connecticuts Central climate division According to published
National Weather Service data (USGS 1993) the average annual temperature is approximately
50degF the coldest month is January with an average temperature of 258T and the warmest month is July with an average temperature of 714degF Annual precipitation at nearby recording
stations (located in Norwich CT and North Foster RI) averages approximately 53 inches per
year and ranges between approximately 41 and 68 inches per year (based on historic data from
1978 to 1991) The monthly distribution of precipitation is relatively even throughout the year
32 Geology 321 Regional Surficial Geology
The surficial or overburden deposits in the area consist of unconsolidated materials deposited as a
result of glaciation during the Pleistocene epoch Various glacially-derived materials including till meltwater or stratified drift deposits and post-glacial deposits of floodplain alluvium
comprise the major surficial geologic units in the vicinity of the Site Areas covered by eolian dune deposits are also noted on surficial geologic maps of the area although no dune deposits are
found within the Study Area
Till deposits in the region consist of non-sorted and generally non-stratified mixtures of sediments
with grain sizes ranging from clay to boulders Till is formed by the direct deposition of ice debris on the land surface Generally the color and lithology of till is dependant upon the
composition of local surficial deposits underlying bedrock and northerly adjacent bedrock from
which the till was derived Tills deposited during two periods of glaciation are present in the
region and blanket the bedrock surface in various thicknesses The most extensive and prevalent
till which is commonly present in surface exposures was likely deposited during late
Wisconsinan glaciation (USGS 1995) This till is referred to as upper till and is described as
predominantly loose to moderately compact generally sandy and frequently stony
A less commonly exposed lower (older) till was deposited during earlier glaciation possibly during the Illinoisan or early Wisconsinan glaciation periods The lower till is generally compact
to very compact and is typically finer-grained and less stony than the younger upper till A
weathered zone is usually present between the two till units
5797wpdoc8gnlluprifinaltextmasterrifnl061297 3-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Directly overlying the till (or bedrock where till is absent) are glacial meltwater deposits
collectively referred to as stratified drift These deposits consist of poorly to well sorted
assemblages of gravel sand silt and clay which were deposited by glacial meltwater during the retreat of the last ice sheet Variations in the composition structure and texture of the stratified
drift deposits are dependent upon the depositional environment in which they formed Deposits exhibiting a relatively high degree of sorting andor stratification can usually be classified as
either glaciofluvial (stream) deposits glaciodeltaic (where streams entered glacial lakes) deposits or glaciolacustrine (lake bottom) deposits The horizontal and vertical contacts between these
deposits are generally transitional and were dependent upon the available sediment load and
proximity to the various depositional environments (eg streams or lakes) associated with the
retreating ice front For example coarse-grained deposits of sands and gravel were usually
deposited proximal to the ice margin while further away primarily in glacial lakes deposits of
fine sand silts and clay were prevalent Poorly sorted deposits of relatively coarse material were
typically deposited at the ice front or along bedrock valley walls During the glacial retreat
these deposits would be left behind or collapsed on any underlying deposits Contemporaneously bedrock valleys were frequently dammed by glacial deposits andor masses
of glacial ice behind which glacial meltwater could accumulate forming glacial lakes Gradual
retreat of the ice margin as well as the formation (and eventual draining) of glacial lakes over
time would result in changes in the depositional environment which are seen as textural changes in the stratified drift deposits
Postglacial deposits of sand gravel silt and organic materials are also present as floodplain
alluvium along streams and rivers in the region The texture of alluvium varies over short
distances both laterally and vertically and is generally less than 5 feet thick along small streams
Since alluvial material typically represents re-worked glacial deposits the alluvium is often similar to the surrounding parent glacial material
322 Local Surficial Geology
The Study Area is located on the eastern flank of a pre-glacial bedrock valley and is bounded to
the east by bedrock-controlled upland areas and to the west by an area known as the Quinebaug
Valley lowlands Following the last period of glaciation (in which the relatively thin veneer of till
was deposited) various temporary depositional environments existed as a result of the presence of
an ice and sediment dam approximately 10 miles south of the Study Area which caused the
formation of a glacial lake Evidence of the lake (referred to as Glacial Lake Quinebaug) is well
documented in the literature (Stone amp Randall 1977) As the ice sheet retreated northward deposits left behind were dominated by sand and gravels associated with the formation of a series
of progressive and coalescing deltaic complexes which developed within the rising lake In lower
lying areas where deltas did not form finer-grained sand silt and clay was deposited Although
5797wpdocsgalluprifinaltextma8terrifhl061297 3-4 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
much of this sediment may originally have been deposited with some degree of structure or
sorting much of the structure was lost (collapsed) when the ice mass eventually melted away
The depositional environment was further complicated by the presence of residual ice blocks left
behind during the retreat of the main body of the glacier As the various depositional features
formed around these ice-blocks their eventual melting left behind depressions or kettles into
which fine sediment could settle While many kettles were eventually filled many remain as
detached or poorly drained ponds
As a result of the depositional history of the Study Area the primary surficial or overburden
deposits encountered are till and stratified drift Depending upon location the stratified drift may
be generally broken down into fine (eg silt and fine sand) or coarse (eg sand and gravel)
grained components but at many locations the change is transitional and subtle in both vertical
and horizontal directions The thickness of the stratified drift deposits ranges from non-existent
up to approximately 70 feet At some locations distinct structure is exhibited while at other
locations the structure has collapsed Post-glacial alluvial floodplain deposits were encountered
at locations within the present Mill Brook floodplain however the overall significance of these
deposits is minor
To illustrate the local geological features a series of geologic cross-sections have been prepared
At several locations lithologic data from pre-RI wells (both on-site and off-site) were
incorporated for additional detail The boring logs from which the cross sections were prepared
are included in Appendix C
As shown in cross-sections A-A B-B C-C D-D E-E and F-F (Plates 3-2 through 3-5) till
was encountered just above the bedrock surface at nearly every location The till horizon ranges
in thickness from approximately 10 to 20 feet with the thickest accumulations located along the
centrally located topographic high Surficial exposures of glacial till were observed within the
central portion of the Site as seen in cross sections A-A and C-C The till observed within the
Study Area is comprised of a fine sandy matrix containing abundant gravel cobbles and
boulders The till deposits seen in the topographically higher areas (ie elevations greater than
approximately 160 feet) were for the most part unsaturated Although reference literature for
this area (USGS 1995) describe the possible presence of two different till horizons no apparent
differentiation was observed at the site
As seen in the boring log from MW111 deposits of till are exposed at the ground surface and in
the central area of the Site However as shown on cross sections A-A and C-C (Plate 3-2) and
D-D (Plate 3-3) the bedrock surface drops off rapidly in southerly westerly and northerly
directions where relatively thick accumulations of stratified drift have been deposited over the till
5797wpdocsgalluprifinlaquoltextmalaquotemfhl061297 3-5 QFT Environmental
Gallups Quarry Superftind Project - Remedial Investigation
Within 500 feet of the central portion of the Site the overall thickness of the stratified drift
deposits increase to nearly 70 feet In the vicinity of MW113 (west of the central portion of the
Site) the lower portion of the stratified drift is comprised of approximately 30 feet of very fine to
medium-grained sand with occasional thin layers of silt This deposit appears to increase in
thickness towards the west while it thins towards the central portion of the Site where it pinches
out against the till Overlying these fine-grained deposits are approximately 30 feet of poorly
structured sand and gravel which includes abundant cobble sized material The coarser upper
stratified drift material also thins eastward towards the Site where it is in contact with the till
The coarse upper material is generally unsaturated with the groundwater table occurring at the
approximate upper surface of the fine sand
The southern portion of the Study Area is shown on cross sections A-A (Plate 3-2) and D-D
(Plate 3-3) As indicated on the southern end of cross section A-A approximately 35 feet of
stratified drift overlies the till in the vicinity of MW112 Although much of the stratified drift at
MW112 is relatively coarse an approximately 12 foot thick layer of fine-grained sand and silt is
present from about eight to twenty feet below the ground surface From MW112 the thickness of
the stratified drift thins to the north where it contacts the central topographic high
From the southeastern corner of the Site near MW112 the bedrock surface slopes downward
towards the west-southwest to a depth of approximately 75 feet below the ground surface (as seen
at location MW115 on the southern end of cross section D-D[Plate 3-3]) At MW115
approximately 65 feet of stratified drift (comprised of a sandy matrix containing a significant
amount of coarser gravel and cobbles) overlies approximately 10 feet of till
As seen in cross section B-B (shown on Plate 3-4) and A-A (Plate 3-2) the northeastern portion
of the Site (in the vicinity of the Former Primary Disposal Area) is comprised of fairly well
sorted fine- to medium-grained sand with occasional thin lenses of very fine sand and silt The
lenses of finer-grained materials appear only locally in the vicinity of MW107 and MW108 at a
depth of about 25 feet and are typically only a few inches to a few feet in thickness with limited
lateral extent Beneath the fine-grained sand and silt and directly overlying the till is 10 to 20
feet of coarser-grained sand and gravel Moving westward along cross section B-B in the
vicinity of MW105 the fine-grained sand thins and grades into coarser sand and gravel deposits
The coarse sand and gravel deposits directly overlie the till and thicken to nearly 50 feet towards
the west in response to the downward slope of the bedrock surface This portion of the Study
Area which is northwest (and downgradient) of the Former Primary and Secondary Disposal
Areas is overlain by a thin veneer of recent alluvial and swamp deposits associated with the
present Mill Brook channel and floodplain As shown on the cross section (B-B) the stratified
drift deposits in this area are very nearly saturated throughout their entire thickness
5797wpdoc8galluprifinaltextmasterrifiiiy061297 3-6 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
North of the Former Primary Disposal Area (along the northern end of cross section D-D) the
bedrock surface continues to gradually slope downward (to the north) until the approximate
location of MW116 North of MW116 the bedrock surface is interpreted as appearing to rise
based on the depth to till deposits encountered beneath MW119 Stratified drift deposits
immediately north of the Former Primary Disposal Area in the vicinity of MW116 are dominated
by approximately 25 feet of fine grained sand and silt Further north along section D-D the
finer sand and silt deposits thin and are overlain by coarser grained sand and gravels Relatively
thin post-glacial stream alluvium and modern swamp deposits associated with Mill Brook are also
seen in the vicinity of MW116 and MW119 A roughly east-west cross section (E-E [Plate 3-5])
has been prepared to illustrate the lithologic features in the area north-northwest of the former
disposal areas This cross section starts at MW119 (described above) and runs west to MW101
in a line approximately parallel to Mill Brook The fine sandsilt deposit seen in the vicinity of
MW119 is also observed to the west at MW117 at the same approximate thickness and elevation
Westward from MW117 the fine sandsilt deposit grades into the more prevalent coarse sand and
gravel deposits observed at MW118 and MW101 The northernmost cross section (F-F [Plate 3shy
5]) extends westward from MW3 (located just east of the former Pervel flock plant) to PZ301
As shown on F-F this portion of the Study Area is dominated by collapsed coarse sand and
gravel deposits at least to the completion depths of the borings (MW3 MWC and PZ301) along
the line
323 Regional Bedrock Geology
Bedrock in the vicinity of the Site is mapped as a lower member of the Quinebaug Formation
which is composed of metasedimentary and metavolcanic rocks of Paleozoic age The Quinebaug
Formation is part of the Putnam Group and exhibits a sillimanite grade of metamorphism The
bedrock consists of primarily light to dark grey fine- to medium-grained hornblende gneiss biotite gneiss and amphibolite Bedrock in the area is strongly faulted and folded and exhibits
varying degrees of mylonitization A major fault zone known as the Lake Char fault is located
approximately 03 miles east of the Site The Lake Char fault is a north-south trending fault
which offsets rock units of the Putnam Group and the Hope Valley Alaskite Gneiss formation A
northwest-trending fault is shown on the USGS Bedrock Geologic Map (Dixon 1965) of the
Plainfield Quadrangle in the vicinity of the Former Seepage Bed The existence and approximate
location of the suspected fault was based on aeromagnetic data published in 1965 (Boynton amp
Smith 1965) Bedrock located north of the inferred fault is mapped as more intensely
metamorphosed cataclasites and blastomylonites The fault is mapped as extending into the Tatnic
Hill formation to the west but is not mapped within the Hope Valley Alaskite Gneiss formation
which is located to the east
5797wpdoc8galluprifinaltextmasterrifhl061297 3-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
324 Local Bedrock Geology
Confirmed depns to bedrock were determined based on the elevations of bedrock outcrops and
the collection of bedrock cores at nine boring locations (MW102B MW105B MW107B
MW108B MW109B MW111B MW112B MW113B and MW115B) Inferred depths to
bedrock were made at seven additional locations (MW101 MW102 MW103 MW104 MW114
MW116 MW117 MW118 and MW119) based on boring data obtained during the drilling of the
deepest wells at each cluster (which indicates the minimum depth to bedrock) and based on trends
seen at the confirmed depth locations Based on this evidence it is likely that unconfirmed depths
to bedrock are accurate to within several feet of the actual depths At MW110S no attempt was
made to advance the boring more than about 12 feet below the ground surface (the depth needed
for the required shallow well at that location) Depths to bedrock ranged from approximately 13
feet at MW111B to 83 feet at MW113B Drilling difficulties associated with the presence of
boulders just below the ground surface at MW11 IB made it difficult to determine the exact depth that bedrock was first encountered at this location Suspected boulders were encountered starting
at approximately six feet below the ground surface and casing was driven to a refusal depth of
approximately 15 feet before bedrock coring began
Based on the data described above a bedrock surface contour map is shown on Plate 3-6
Bedrock elevations are highest in the eastern central portion of the Study Area and decrease to the
north and west and to a lesser degree to the south
Within the Study Area bedrock consists of grey fine- to medium-grained gneiss with varying
contents of amphibolite biotite and hornblende Various degrees of weathering and competency
were also observed Detailed rock core descriptions are presented on the rock coring logs
provided in Appendix C
The primary objective of the seismic refraction survey (discussed in Section 234) was to
identify if present the location of a possible bedrock fault suspected to exist hi the vicinity of the
Former Seepage Bed As discussed in Section 323 the approximate location of the suspected
fault was estimated from the regional USGS Bedrock Geologic Map based on an aeromagnetic
survey conducted in 1965 Ground penetrating radar surveys conducted by the USGS (1995)
identified a northward dipping subsurface reflector beneath the central portion of the Site This
reflector was interpreted as a potential bedrock fault feature The relatively high strength of the
reflector was attributed to fault gouge (or other infilling) material or possibly sorbed inorganic
compounds No subsurface explorations were conducted at the time of the USGS investigation to
confirm the nature of the radar reflector
5797wpdocsgalluprifinaltextmiiraquoterrifnl061297 3-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Evaluation of data obtained from the seismic refraction survey indicates the presence of possible
bedrock fractures on seismic lines 3 through 6 (Plate 3-7) In addition to these interpreted
fracture zones the overall relatively low seismic velocities (12000 ftsec vs 15000 to 18000
ftsec for intact crystalline rock) indicate that in general the rock is somewhat fractured
Although the original intent of the magnetometer (MAG) survey was not to interpret bedrock
features data obtained during the MAG survey (which covered a much larger area) indicate the
presence of several linear-shaped sharp magnetic gradients bounding a zone with a different
magnetic signature The change in magnetic signature was interpreted as potentially associated
with changes in bedrock lithology and fracturing across a broad faultfracture zone in the central
portion of the Site These interpretations are described in further detail in the Weston
Geophysical Report included as Appendix A The locations of the magnetically determined
bedrock features are also shown on Plate 3-7 While the seismically interpreted fractures do not
strongly coincide with linear features seen in the MAG data they do lie within the magnetically
determined fractured zone
The geophysical data described above as well as the rock-core retrieved from MW111B further suggest that bedrock beneath the central portion of the Site may be more accurately characterized
as a series of fractures and faults rather than an area of competent bedrock with one or two
discrete faults
33 Hydrogeology The following sections discuss data collection and evaluation results relative to groundwater flow
directions and rates in overburden deposits and the upper portion of the bedrock unit
331 Hydraulic Conductivity The hydraulic conductivity distributions within the overburden and bedrock formations were
evaluated through the performance of rising and falling head slug tests constant flow tests and
by empirical correlations with measured soil grain size distributions The slug test methodology
and data analysis methods are discussed in Appendix F Because the falling head test results for
shallow wells were influenced to some degree by soil above the water table only rising head test
data were used for the water table wells to compute mean values The constant flow test
methodology is described in Section 283 and Appendix F Table 3-1 summarizes the measured
hydraulic conductivity values from the slug and constant flow tests for wells grouped together
based on lithology and screen depth as follows shallow top-of-till till and bedrock Hydraulic
conductivity estimates based on grain size are listed in Table 3-2 for comparison but only
constant flow and slug-test data were used to calculate mean hydraulic conductivity values for
different portions of the aquifer Laboratory grain size data are presented in Appendix G
5797wpdocraquogalluprifinlaquoltextmastem fill061297 3-9 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
The top-of-till wells are considered to be the most representative of the more permeable section of X^^JF
the overburden aquifer characterized by coarser soil grain sizes where a large percentage of the
total groundwater flow occurs Across the Study Area the mean hydraulic conductivity for the
top-of-till wells is 0005 centimeters per second (cms) with values ranging from 0000053 cms
to 0074 cms Northwest of the railroad tracks in the northern portion of the Study Area where
the aquifer thickens the mean hydraulic conductivity for top-of-till wells (MW102TT
MW103TT MW104TT MW117TT and MW118TT) is 0037 cms This value of 0037 cms
which is approximately an order of magnitude larger than the overall Study Area mean for top-ofshy
till wells appears to be most representative of the hydraulic conductivity within the major portion
of the VOC plume By comparison the grain size results are similar in magnitude but somewhat
lower than the Study Area average for the constant-flow and slug tests because they indicate an
average hydraulic conductivity of 0003 cms for the coarse stratified drift samples with values
ranging from 00006 cms to 0006 cms The mean hydraulic conductivity for shallow wells
which are generally screened in finer-grained soils is 0001 cms and varies between 000006
cms and 002 cms The shallow well constant-flow and slug test results are comparable to the
mean grain-size correlation value of 0002 cms for fine stratified drift soil samples
The mean hydraulic conductivity for the till wells (000047 cms) is approximately a factor of ten
less than the mean Study Area top-of-till value and varies between 00002 cms and 0002 cms
The till appears to be hydrogeologically different from the other overburden deposits and on the
average provides increased resistance to groundwater flow This added resistance is not
considered to be significant however because the consistency of the till is highly variable and the
hydraulic conductivity contrast is relatively small
The slug test results for the bedrock wells yield the lowest average hydraulic conductivity
000018 cms The bedrock results though should be considered less accurate than the
overburden estimates due to the highly variable nature of the fractures in the rock matrix and their
associated non-linear effect on computed hydraulic conductivity
332 Groundwater Flow
3321 Surficial (Overburden) Groundwater Flow
The following discussion on overburden groundwater flow is organized according to relative
locations within the Study Area All references to flow direction are inferred based on measured
hydraulic gradients The central portion of the Site in the vicinity of the Former Seepage Bed is
dominated by the presence of a bedrock-controlled topographic high which for the most part is
overlain by unsaturated till Because of this feature overburden groundwater flow patterns can be
effectively treated as separate entities those located to the north of the hill and those located to
the south
5797wpdocraquoglaquolluprifinlaquoltextmasterrifhl061297 3-10 QampT Environmental
Gallups Quarry Superand Project - Remedial Investigation
Table 3-3 summarizes the water level data collected from monitoring wells and piezometers
during the quarterly monitoring rounds Plates 3-8 and 3-9 depict deep and shallow piezometric head distributions respectively (for November 6 1995) throughout the northern Study Area
Plate 3-9 also shows the piezometric head distribution in the southern Study Area Groundwater
flow maps for other dates are presented in the ISCR (ESE 1995) Water level data for the
monitoring wells at the former Pervel facility were used in both the shallow and deep flow maps
because they are screened in the middle portion of the aquifer As a result these wells are
considered to be hydraulically representative of both portions of the aquifer A saturated
thickness map (Plate 3-10) was created by subtracting the interpolated bedrock surface (Plate 3-6)
from the shallow overburden piezometric surface measured on November 6 1995 which is approximately equal to the groundwater table configuration To facilitate interpretation of flow
patterns calculated two-dimensional groundwater pathlines which represent the mean horizontal trajectory of a parcel of groundwater in the overburden aquifer originating from several locations
in the Study Area are also shown however the pathlines do not account for vertical flow within the aquifer which is important in the shallow portion of the aquifer Data interpolation by the
method of kriging piezometric head contour development and numerical computation of pathlines were performed using the data analysis and visualization software package Tecplot
(Amtec Engineering 1994) The pathlines are based on a steady state velocity field computed
directly from the interpolated head distribution using Darcys law and assume homogeneous
isotropic conditions
Southern Study Area
Overburden groundwater flow south of the Former Seepage Bed is primarily influenced by two factors (1) the slope of the bedrock surface which defines the base of the unconsolidated deposits and (2) regional hydrologic drainage patterns The west-southwest dip of the bedrock
surface strongly influences the general east to west flow of groundwater The average east-west
horizontal hydraulic gradient in the southern portion of the Study Area is approximately 001 feet per foot (feet of vertical head change per foot of horizontal distance)near well MW112S and
piezometer PZ-202 whereas the typical bedrock surface slope in this area is about 01 feet per
foot The configuration of the bedrock surface is important because the slope of the groundwater
table in the overburden would tend to equal the slope of the underlying bedrock in cases where
the saturated thickness is relatively small and the slope is large This process is analogous to flow
in a river where the water surface profile tends to reflect the slope of the river bed under steady-
state conditions In the southern Study Area the water table slope (ie horizontal hydraulic
gradient) is steep but less than the dip of the bedrock surface because the saturated thickness of
the overburden aquifer increases in the direction of flow The saturated thickness increase also
5797wpdocsglaquolluprifinlaquoltextmlaquogterrifiil061297 3-11 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
increases the transmissivity of the aquifer (and decreases the resistance to flow) thus causing the
horizontal hydtaulic gradient in the overburden to be less than the bedrock slope The
overburden becomes unsaturated north of PZ203 due to the continued increase of the bedrock
surface elevation in the direction of the Former Seepage Bed The wetlands and stream located a
few hundred feet west of the railroad tracks also affect flow directions and rates because they act
as discharge points for groundwater
Northern Study Area
Due to the increased saturated thickness north-northwest of the Former Primary Disposal Area
groundwater flow conditions in both shallow and deep sections of the aquifer are discussed The
top-of-till wells are considered to be most representative of horizontal flow conditions in all but
the shallow portion of the aquifer Primary reasons for the differences between shallow and deep
flow conditions include (1) the deep aquifer hydraulic conductivity northwest of the railroad
tracks is a factor of about 40 greater than the shallow hydraulic conductivity resulting in the
lower to middle portions of the aquifer controlling regional groundwater movement and (2)
rainwater infiltration and hydraulic influences of Mill Brook cause vertical flow to be important in
certain areas of the shallow aquifer The focus of this section is horizontal groundwater flow in
the middle to lower sections of the aquifer as characterized by Plate 3-8 Shallow flow
conditions (Plate 3-9) are discussed in Section 3323
In the northern portion of the Study Area three hydrogeologically distinct zones exist Between
the Former Primary Disposal Area and the Former Seepage Bed the hydraulic gradient is steep
(approximately 003 feet per foot between wells MW109S and MW110S) and is strongly
influenced by the dip of the bedrock surface (01 feet per foot) As shown on the insert on Plate
3-10 the saturated overburden thickness increases from zero south of well MW109 to about 20 to
30 feet near the former disposal areas North-northwest of the Former Primary Disposal Area the
hydraulic gradient lessens significantly to a range of 00003 to 00007 feet per foot between wells
MW105TT and MW102TT representing a factor of 40 to 100 reduction The most important
factors which produce the flatter gradients in this area are the more than order-of-magnitude
increase in hydraulic conductivity of the coarser-grained deposits and the substantial increase in
the saturated overburden thickness northwest of the railroad tracks North-northeast of Mill
Brook the hydraulic gradient is about 0007 feet per foot near wells MW117TT and MW118TT
Northwest of the railroad tracks groundwater flow in the middle to lower portions of the aquifer
converges from the northeast and southwest toward a centerline area generally defined in the
downgradient direction by wells MW105 and MW102 The flow direction near these wells is
generally to the northwest Northeast of this centerline groundwater flows in a southwesterly
5797wpdocsgalluprifinaltextmasterrifhl061297 3-12 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
^ ^ direction from the vicinity of Mill Brook and the former Pervel flock plant North of Mill Brook
and west of the railroad tracks the predominant groundwater flow direction becomes more
westerly As discussed in Section 42 and 52 these flow directions are very consistent with the
observed groundwater contaminant distribution
No significant seasonal changes in horizontal groundwater flow directions were observed in the
Study Area Figures 3-1 to 3-20 are groundwater elevation hydrographs for each well cluster in
the Study Area representing the period January 1995 to May 1997 (except for wells MW117
MW118 and MW119 which were not installed until November 1995) Groundwater levels were
high in January 1995 May 1996 and February 1997 and decreased by about two feet during July
1995 and August 1996 This variation is consistent with the fact that recharge rates become very
small during the summer months
3322 Bedrock Groundwater Flow
Groundwater flow within fractures in the top ten to 20 feet of the bedrock unit was evaluated
through the performance of the hydraulic conductivity (slug) tests and water level measurements
in monitoring wells A bedrock piezometric head map based on November 6 1995 water levels
is shown on Plate 3-11 along with inferred groundwater pathlines For the pathline development
it was assumed that the hydraulic conductivity distribution is isotropic because potential
influences of fracture orientation on flow direction have not been quantified As expected the
direction of the dip of the bedrock surface has a major influence on the horizontal hydraulic
gradient and flow direction However vertical flow from bedrock to overburden is also
important as discussed in Section 3323
South of the Former Seepage Bed groundwater in bedrock moves primarily in a westerly
direction while in the northern Study Area the predominant flow component is toward the
northwest In both areas the horizontal hydraulic gradient is on the order of 002 feet per foot
The steepest gradients (003 feet per foot) are found in the vicinity of the Former Seepage Bed
and the local high in the bedrock surface just east of MW111 The horizontal hydraulic gradient
reduces to about 001 feet per foot in the southern portion of the Study Area (near wells MW115
MW114 and MW112) and north-northwest of the former disposal areas Groundwater flow in
bedrock near the Former Seepage Bed is toward the northwest in the direction of wells MW113
and MW106 and exhibits no apparent influence from the locally increased fracturing identified
from the geophysical investigation and the hydraulic testing in well MW111B
5797wpdocsgalluprifinaltextm8tem fhl061297 3-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
3323 Vertical Flow
BedrockDeep Overburden Interface
Vertical groundwater flow is an important component in the upper several feet of the bedrock
unit This observation is supported by the water level hydrographs (Figure 3-1 to 3-20) and data
presented in Table 3-4 which summarizes the vertical hydraulic gradients between pairs of
monitoring wells in various well clusters across the Study Area Data characterizing the hydraulic
interaction between the bedrock and the lower portion of the overburden were evaluated for the
following well pairs MW102B-MW102TT MW105B - MW105T MW107B - MW107T
MW108B - MW108TT MW109B - MW109S MW112B - MW112T MW113B - MW113S and
MW1 15B - MW1 15TT For all measurement dates groundwater was found to be discharging
from bedrock into overburden at each location except for the January 1995 and February and May
1996 measurements at location MW109 At MW109 the saturated overburden thickness is less
than a few feet and MW109 is located at a much higher bedrock elevation relative to all other
locations at which upward vertical flow from bedrock was measured The vertical hydraulic
gradients between bedrock and top-of-till wells are generally more than a factor of ten greater
than the horizontal hydraulic gradients within the VOC plume downgradient from the Former
Primary Disposal Area
Overburden
In the overburden aquifer the vertical flow component is significant within shallow deposits in ~
the vicinity of the Former Primary Disposal Area and within the streambed sediments and the
upper portion of the aquifer near Mill Brook Plan view and cross-section maps were developed
to illustrate vertical piezometric head differences Plate 3-12 shows the November 6 1995
vertical piezometric head distribution and general groundwater flow directions along geologic
cross-section B-B Plate 3-13 is a plan view contour map of the shallow minus deep piezometric
head difference in the overburden aquifer As shown by the water level hydrographs the vertical
hydraulic gradients in the aquifer are relatively consistent throughout the observation period
Consistent downward hydraulic gradients have been observed at well clusters MW107 MW108
and MW116 Near the Former Primary Disposal Area water levels in MW107S were two to
three feet higher than the level in MW107TT resulting in a downward vertical hydraulic gradient
that is about a factor of 100 greater than the horizontal gradient from MW107TT to MW105TT
In addition shallow piezometric heads near MW108 and MW1 16 have ranged from 05 to 15
feet higher than heads in the lower portion of the aquifer This downward component at MW107
likely results from the low hydraulic conductivity of shallow soils near the well screen of
MW107S (factor of 200 less than underlying deposits refer to MW107S and MW107TT data in
Table 3-1) and drainage of surface water runoff from upslope areas into the depression formed by
excavation of the Former Primary Disposal Area The low hydraulic conductivity test result for
5797wpdocsgalluprifinlaquoltextmasteiTifhl06 1297 3-14 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW107S and the observed downward hydraulic gradient may be related to the increased silt
content of soils near well MW107S The vertical VOC distribution at location MW107 (shown
on Plate 3-12 and discussed in Section 4) also strongly supports a predominantly vertical
groundwater flow direction in the upper portion of the aquifer because only trace levels of VOC
were detected in MW107S The downward hydraulic gradients in the vicinity of wells MW108
and MW116 (Plate 3-13) also appear to be associated with the higher hydraulic conductivity of
deep deposits compared to shallow soils (Section 331) and groundwater recharge
West of the railroad tracks near well clusters MW102 MW101 and MW118 the measured flow
direction in the aquifer is predominantly horizontal based on the negligible vertical hydraulic
gradient between shallow and top-of-till wells at these locations However in the immediate
vicinity of Mill Brook vertical groundwater flow is important within the upper several feet of the
aquifer In the vicinity of wells MW103 MW117 and MW119 shallow piezometric heads are
generally 03 to one foot lower than deep heads Using a representative aquifer thickness of 50
feet the average upward vertical hydraulic gradient in this area is about 001 feet per foot by
comparison the local horizontal hydraulic gradient is approximately 0007 feet per foot Based
on these data a significant fraction of the shallow aquifer near wells MW103 MW117 and
MW119 may be discharging into Mill Brook Within the lower portion of the aquifer the
vertical hydraulic gradient becomes very small in magnitude
To further evaluate the hydraulic influence of Mill Brook on the overburden aquifer a vertical
two-dimensional numerical groundwater flow model was developed and a sensitivity analysis was
performed (Appendix U) The results of the modeling indicate that vertical flow in the upper
portion of the stratified drift aquifer near Mill Brook is more important west of the railroad tracks
(eg near wells MW101 and MW102) than east of the tracks (eg near well MW119) This
difference is due to the much smaller horizontal hydraulic gradients (on the order of 00003 feet
per foot) that are present west of the railroad tracks compared to ths area north of Mill Brook and
east of the railroad (horizontal gradients approximately 0007 feet per foot) Because the mean
water level in the brook is lower than the groundwater table elevation vertical flow is created in
the upper portion of the stratified drift aquifer and the depth to which this vertical flow is
important is greater in areas where the horizontal hydraulic gradient (and groundwater velocity is
less) In the vicinity of wells MW101 and MW102 the groundwater flow simulations indicate that
as much as one-third to one-half of the stratified drift aquifer may discharge into Mill Brook
East of the railroad tracks no greater than ten to 25 percent of the groundwater flow in the
stratified drift aquifer is estimated to discharge into the brook
East of the railroad tracks and south of Mill Brook a consistent downward groundwater flow component is observed in addition to the regional horizontal flow component As discussed
5797wpdocraquograquolluprifinaltextmaBterrifhl061297 3-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
above this downward component is largest near the Former Primary Disposal Area A small
downward flow component was also observed in the vicinity of wells MW106 and MW104
Figure 3-21 is a three-dimensional perspective drawing of groundwater movement in the
overburden aquifer which was developed to further illustrate the relative importance of the
horizontal and vertical flow components in the vicinity of the Former Primary Disposal Area
The figure consists of the two sets of piezometric head contours representing shallow and deep
(top-of-till) water level measurements recorded on February 2 1995 The lower piezometric
surface is representative of flow conditions throughout the middle to lower portions of the aquifer
The upper surface represents the piezometric head variation near the water table Presented
together in the same figure these two sets of contours allow an interpretation of the predominant
(but not all) three-dimensional pathlines originating in the vicinity of the Former Primary Disposal
Area As the pathlines illustrate shallow groundwater near these locations is expected to move
predominantly downward in the upper portion of the aquifer (although some local horizontal flow
may occur due to variations in the hydraulic conductivity of aquifer material) due to the large
vertical hydraulic gradients and the small aquifer thickness
Once groundwater has passed through the less permeable shallow soils it moves in a
predominantly horizontal direction dictated by the piezometric head distribution in the lower
portion of the aquifer
Based on the stream piezometer data presented in Table 3-5 Mill Brook generally gains water
from the overburden aquifer in the northern portion of the Study Area For most dates stream
bed flow was upward at piezometers PZ-6 PZ-5 PZ-4 PZ-4A and PZ-4B located west of the
railroad tracks and at piezometers PZ-1 and PZ-2 located east of the railroad tracks The
streambed vertical flow direction at piezometer PZ-3 located immediately upstream from a beaver
dam and possibly influenced by backwater effects was variable These data are consistent with
the shallow groundwater flow conditions depicted in Plate 3-9 where the head contours passing
through Mill Brook are bent (or V) in an upstream direction This piezometric head contour
pattern is representative of a gaining stream
Any groundwater discharge from the aquifer into Mill Brook would be significantly diluted by
flow in the brook A rough estimate of the potential surface water dilution rate can be obtained
by comparing the stream flow rate with the total discharge rate of groundwater through a given
vertical cross-sectional area For example using an upper bound hydraulic conductivity estimate
of 100 feet per day (0035 cms) a horizontal hydraulic gradient of 0001 feet per foot and an
area 200 feet wide (plume width) by 20 feet deep (about one-third of the aquifer thickness) a
conservatively high estimate of potential discharge from the contaminated portion of the aquifer
5797wpdocraquogalluprifinaltextmasterrifhl061297 3-16 Q^T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
into Mill Brook is approximately 0005 cubic feet per second or cfs (21 gpm) Based on a
measured stream flow rate of about 30 cfs at station UB10 the concentrations of dissolved
constituents in groundwater would be reduced by a factor of about 6000 upon mixing with the
entire stream flow
34 Ecology An ecological study was performed primarily to delineate wetlands and to make local observations
of the types and abundance of plants and animals in the area
341 Wetland Delineation
Delineation of wetlands within the Study Area and adjacent lands was conducted during the period
of August 26 to September 1 1994 Team members included two ESE wetlands biologists and a
certified soil scientist affiliated with the Soil Science Society of Southern New England As
discussed in Section 2131 the delineation performed to meet the States criteria focused on soil
types and hydric soil characteristics while the delineation performed to meet the Federal criteria
used USACOE methods which include the examination of vegetation hydrology and soils
As shown on Plate 3-14 wetlands were identified and delineated along the northern and western
portions of the Study Area Areas bordering the Site to the south and east reflect upland
conditions
Wetland delineation efforts were initiated along the face of a steep gradient along the southwestern
portion of the study area (west of the railroad grade) This allowed the field team to observe the
most obvious characteristics of both upland and wetland regimes Areas reflecting more subtle
wetlandupland indicators were investigated after having gained local experience with the obvious features
The wetland bordering the southwestern portion of the study area is a white cedar swamp
(unnamed) supporting a varying density of trees The swamp is hydraulically connected to the
Mill Brook system by a narrow stream The stream limits surface water flow causing the swamp
to maintain a long hydro period (duration of inundation or saturation) even though it is
topographically higher than the receiving floodplain It appears that the swamp remains inundated
during most years with the possible exception of drought years Judging from the high hydraulic
conductivity of the surrounding soils the swamp receives water through seepage from
surrounding uplands and to a lesser degree from surface water runoff
Portions of the swamp support a low density of older cedars while other areas support denser
stands of young cedars It appeared that the older age class occurred in deeper water while the
5797wpdocsgalluprifinraquoltextmasterrifhl061297 3-17 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
younger stands favored shallower water White cedar trees are not tolerant of fire events and it is r
likely that this age class distribution reflects a fire-maintained system where the deeper portions of
the swamp have been more effective in excluding natural fires hence supporting the oldest
cedars Additional hydrophytic plant species identified within the transition zone include red
maple common reed duckweed jewelweed cattail and coast pepper-bush
The upland system bordering the cedar swamp and floodplain forest supports a sub-climax to near
climax hardwood forest Topography of the upland includes steep slopes to gently undulating
land Canopy vegetation (trees) are dominated by oak species (red white and chestnut) with
white oaks nearer the wetland transition area and red and chestnut occurring on the higher
portions of the uplands Other canopy species included white ash quaking aspen hickories and
dogwoods Common understory vegetation included sheep laurel black cherry and green briar
Herbaceous vegetation included species found in the under story and canopy in addition to hay-
scented fern among others
Northward of the stream feature draining the cedar swamp lies the broad floodplain of Mill Brook which closely coincides with the northern boundary of the Site The floodplain is generally flat with many small raised hummocks This area reflects more seasonal fluctuations in hydro period and shallower water depths than the cedar swamp a result of more efficient drainage of the system For this reason natural succession is more advanced and the system supports a higher _ Jgth
diversity of hardwood canopy under story and herbaceous species composition
With the exception of two small isolated topographic depressions (excavated pits) located just west of the southern portion of the Site the delineated wetland areas correspond with the edge of the Mill Brook floodplain Most of the wetlandupland boundary occurs along the edge of a steep grade which closely coincides with the 150-foot ground elevation contour interval The sharp relief produces a narrow transition zone between upland and wetland communities The delineated lines reflect this as the State and USACOE wetland boundaries coincide at nearly
every location The State and USACOE lines are different in a small area adjacent to the railroad tracks immediately north of the Site In this area the State line is upgradient of the USACOE line The soils above the floodplain do not exhibit hydric soil characteristics as defined in the federal manual used for delineating wetlands The soil appears well-drained and depth to water is at a lower elevation than the floodplain soil just a few feet away The soil resembles the description of Suncook an excessively drained soil commonly mapped with Rippowam soils Both Rippowam and Suncook soils are listed on the State hydric soils list while Suncook is not listed by SCS as a hydric soil
5797wpdocsgalluprifinaltextmasterrifhl061297 3-18 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
A relatively small area of wetlands were determined to occur within the boundaries of the Site proper Wetlands occur in the area northeast (upgradient) of the Former Primary and Secondary
Disposal Areas and along the northern border of the Site east of the railroad bed The two topographic depressions corresponding to the former disposal areas (primary and secondary) lack
hydrophytic vegetation and hydric soil characteristics Other excavated areas to the south and
southwest (on-site) support hydrophytic vegetation and meet hydrology criteria but lack hydric
soil characteristics The depression to the southwest bordering the railroad supports hydrophytic vegetation and is occasionally inundated with surface water (following significant precipitation
events) but lacks hydric soil indicators In this area the ponded water was judged to be the
result of a confining layer of residual tar (presumed to be associated with former CTDOT asphalt
plant operations) immediately beneath an organic layer which causes precipitation to accumulate
342 Plant and Animal Survey
Site Characterization
An objective investigation of native plant and animal species and their habitat was conducted by US Fish and Wildlife Service (USFWS) staff in summer of 1993 (Prior et al 1995) Their
examination included a Site walkover observation and mapping of vegetation cover (shrubs
trees hydrophytic plants) and observation of direct or indirect evidence of wildlife (birds mammals amphibians) Although the Site proper is characterized as highly disturbed no
conclusions were drawn with regard to the effects of past human disturbance on the local ecology
The large majority of plant and animal species observed in the study are native to the region and
commonly found in other disturbed communities andor wetland environs
Reconnaissance of the study Site and adjacent lands was performed prior to delineation activities
to identify habitat types terrain physical access and develop logistics for completing the wetland
delineation The study area is a peninsular feature which extends northward and westward from
the Site entrance at Tarbox Road The study area is bisected diagonally by the railroad right-ofshy
way The Gallup Quarry Site (the quarry) lies to the east of the railroad divide and the remainder
of the study area (the west end) lies to the west Portions of the east boundary of the quarry abut
State Route 12 with other areas bounded by private property
The boundaries of the peninsula are characterized generally by steep slopes which are met
immediately by wetlands The upland soils are glacial till with some areas composed mostly of sands with coarse gravel occurring with lower frequency Some of the higher and relatively
undisturbed areas are composed of large rocks protruding to the ground surface Soils in the
transition zones between upland and wetland are composed of organic muck overlying sand
5797wpdoc8gilluprifinaltextmalaquoterriftil061297 3-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
These natural conditions along with historical use of portions of the area (mining and
manufacturing) cre responsible for the character of the plant communities found throughout the
study area The quarry reflects significant disturbance from historical mining and asphalt
operations The Site has numerous excavated depressional areas and areas of mounded earth
material These features significantly distinguish the quarried area from the area off-site to the
west which is undeveloped and relatively undisturbed The assemblage of plants in the quarry
reflects these conditions many of the excavated zones are devoid of vegetation and areas adjacent
to them support a mix of successional pioneer species Density of vegetation ranges from bare
soil to dense brush and sapling sized trees Areas of highest vegetation density are associated
with both low elevation (greatest soil moisture regime) and age (length of time since disturbance)
Trees throughout the quarry are young and small in comparison with those found in the forested
areas west of the railroad Vegetation on-site is characterized as early successional species The
more common species include black willow northern bayberry eastern cotton-wood quaking
aspen goldenrod and black cherry
Few wildlife species were observed or noted during wetland delineation activities Wildlife
activity within the Study Area was limited during the survey period but should be expected to
support a much greater diversity of wildlife during the spring and summer seasons when birds
(especially migratory) conduct nesting and rearing activities Most of the species observed during
the survey are expected to overwinter at the study area Bird species recorded include mourning
dove eastern peewee tufted titmouse black-capped chickadee blue jay white-breasted nuthatch
gray catbird American robin and northern cardinal
Vegetation species were recorded during the wetland delineation and are presented in Table 3-6
These reflect species occurring within wetland transition zones Additional species are expected
to occur in more xeric uplands and deeper wetlands
Although no qualitative samples of freshwater macroinvertebrates were obtained the distribution
of different genera between stations would appear to be strongly influenced by the variable
substrate composition and habitat which ranges from shaded moderate flowing rocky stream bed
(eg UB1 UB9) to sunny low energy depositional areas containing sand or deep muck (eg
UBS LB2)
5797wpdocsgalluprifinaltextmasterrifnl061297 3-20 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
40 Nature and Extent of Contamination
This section discusses the distribution of contaminants within the various media throughout the
Study Area and is based on analytical data collected during nine separate sampling events These nine sampling events include the Phase 1A investigation the Phase IB investigation and the Long-
Term Monitoring Program events conducted during April July November 1995 February May
August and November 1996 and February 1997) The results of the Phase 1A investigation
Phase IB investigation and the Long-Term Monitoring Program sampling events (except
November 1995 which was conducted concurrently with the Phase IB investigation) were also
presented in earlier reports (ESE 1995 -1995b -1995c 1996a 1996b 1996c 1997a 1997b)
Section 41 addresses the results of investigations into potential source areas including surface and subsurface soil Section 42 addresses the results of groundwater investigations Section 43
presents the results of investigations of surface water sediments and wetland soils Section 44 addresses the results of air monitoring investigations Section 45 identifies potential sensitive
human receptors within a one mile radius of the Site
Sample analyses were performed pursuant to the Gallups Quarry Superfund Project RIFS Quality Assurance Project Plan dated August 29 1994 Laboratory analytical testing for Level 4
was generally conducted for analytes identified in the Contract Laboratory Program (CLP) target
compound list (TCL) for organics and target analyte list (TAL) for inorganics Analyses were
conducted pursuant to the CLP Statement of Work for Organics MultimediaMulticoncentrations
Document OLM 018 and the CLP Statement of Work for Inorganics
MultimediaMulticoncentrations Document ILM 030 Appendix IX analyses were conducted by
CLP and SW-846 Methods as described in the QAPP Low-level VOC in drinking water were analyzed by EPA Method 5242 with CLP SOW reporting Laboratory reports for the Phase 1A
Phase IB and Long-Term Monitoring Program sampling events are presented in Appendices H
through P Laboratory data for sample splits collected by EPAs oversight contractor during the
Phase 1A July 1995 and Phase IBNovember 1995 sampling events are also presented in
Appendices H J and K respectively The results of detected analytes are summarized in Section 4 tables The definitions of the qualifiers used for the laboratory data precede the tables in
Section 4 As discussed in various sections analyte concentrations are given either as milligramskilogram (mgkg) or microgramsliter (ugL) The units mgkg are also used
interchangeably with the term part per million (ppm) The units ugL are equivalent to parts per
billion (ppb)
Data validation was performed on all Level 4 data according to the requirements of EPA Region
I Laboratory Data Validation Functional Guidelines for Evaluating Organic Analyses (February 1
5797wpdoclaquogilluprifinaltextmlaquo8terrifiJ061297 4-1 QZT Environmental
Gallups Quarry Superjund Project - Remedial Investigation
1988 as modified November 1 1988) and Inorganic Analyses (June 13 1988 as modified
February 1989) Data validation was performed by David MacLean an independent data
validator Summaries of Mr MacLeans data validation results are presented in Appendix Q
41 Contaminant Source Investigation 411 Visual Site Reconnaissance
A comprehensive visual site reconnaissance was conducted over a three week period from August
23 until September 13 1994 to determine the potential presence of unknown disposal areas
Prior to the start of this survey a grid system was established to allow systematic coverage of the
Site and to locate features of interest The grid used to conduct the visual Site reconnaissance is
described in Section 21 A Site plan which includes the survey grid and the features described
below is shown on Plate 4-1 The features identified on Plate 4-1 are also summarized in Table 4-1
Based on this visual survey the ground surface in the northern portion of the Site which includes the Former Primary and Secondary Disposal Areas is covered with sand and gravel with sparse
to no vegetation Topographic relief is estimated to be as much as 20 to 30 feet and is attributed
to the Sites past usage as a sand and gravel quarry Many of the topographic low spots were
observed to contain either standing water (following rain events) or moist soil (indicative of
intermittent periods of ponded water)
The central portion of the Site which contains the Former Seepage Bed is presently heavily
vegetated Crushed stone and boulders are evident over a large portion of this area and the soils
consist mainly of a sandy till Immediately east and northeast of the Former Seepage Bed is a
topographic high with numerous boulders at the ground surface Evidence of previous test pit
explorations were also observed in this general vicinity Asphalt and mounds of asphalt pavement
were also observed in several areas and are presumed to be remanent of the State of Connecticut
Department of Transportation (CTDOT) asphalt plant operations discussed in Section 132
The southern portion of the Site contains the entrance to the former CTDOT asphalt plant as well
as the remains of the former plant itself These remains consist primarily of concrete footings
and retaining walls The remains of the asphalt plant are located along trending lines E through
K approximately 800 to 900 feet north of Tarbox Road The remains of a 6-foot diameter brick
and concrete masonry structure were observed along with an 8-inch diameter clay pipe leading
into the ground at the former plant location
The area located in the southwestern portion of the Site along line A includes mounded earthen
material piled along the western perimeter of the Site Scattered metal debris including several
5797wpdocsgalluprifinaltextmasterrifiil061297 4-2 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
empty rusted drums were observed adjacent to and partially buried within the mounded materials
Other objects consisting of timbers steel culvert tires and mounded asphalt were also observed
along the A line Mounded earthen materials located on lines M and N (400 to 650 feet north of
Tarbox Road) were observed to also contain miscellaneous debris (corrugated steel culvert hoses
and cables tires etc) and several empty rusted drums These areas are presently heavily
vegetated Other areas at the southern portion of the Site consist of a mixture of grassland and
brush There are numerous mounds of earthen material and scattered patches of asphalt and
pavement remanent of CTDOT operations throughout this portion of the Site
The Bionetics Corporations under contract to USEPA performed a review of historic aerial
photographs of the site and issued a Site Analysis Report (Bionetics Corp 1990) The historical
aerial photographs were used to prepare a Site plan which indicated the locations of suspected or
potential disposal areas (Figure 4-10 from the Phase 1A Work Plan (ESE 1994)) That Site plan
showed the locations of the three known former disposal areas as well as several much smaller
features described below Based on the visual reconnaissance performed during the RI areas
described in the Bionetics Report as either stained or wet or standing liquid or wet ground
correspond to topographic low spots in which ponded rainwater has been observed In addition
no visual evidence indicative of disposal activities was observed in the vicinity of the several
pits (dated 1981 through 1988) identified in the Bionetics Report These pits are believed to
be remnant of previous investigation test pits
An area described in the Bionetics Report as an extraction and an area of disturbed ground
northwest of the Former Seepage Bed correspond to an excavated area in which asphalt and
miscellaneous debris were observed during the Site reconnaissance The presence of mounded
materials in the vicinity of the Former Seepage Bed was confirmed during this visual
reconnaissance The mounded materials observed are comprised of earthen materials andor
asphalt pavement
A number of areas located within the southern portion of the Site were described in the Bionetics
Report as suspected disposal areas Features described as containing liquid generally
correspond to topographic low spots which were observed during the Site reconnaissance to
contain ponded rainwater following rain events The large feature described in the Bionetics
Report as extraction with liquid and associated dark toned material corresponds to a presently
open excavation in which asphalt was observed No features or specific objects were observed
during the Site reconnaissance which correspond to the locations of the unidentified objects
noted in the report The remains of a circular foundation observed during the Site reconnaissance
in the vicinity of the former CTDOT plant corresponds to the location of the possible vertical
5797wpdocraquogalluprifiiwltextmasterrifhl061297 4-3 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
tank Scattered mounds of earthen materials observed throughout the southern portion of the
Site correspond to the numerous mounded materials identified in the Report
Based on the observations made during this survey it is apparent that the landforms on-site have
been altered numerous times during past usage Extensive areas are presently heavily overgrown
and do not appear stressed Various earthen materials have been excavated and mounded at
numerous locations throughout the property and are presumed to be remnant of the former sand
and gravel quarrying operation andor the operation of the State DOT asphalt plant Also
patches of asphalt and mounds of asphalt pavement ranging from several to tens of square feet in
size were observed at multiple areas around the Site
The major features described as potential or suspected disposal areas in the Bionetics Report were
identified and described during the visual reconnaissance Although several empty 55 gallon
drums in various states of decomposition and scattered debris (consisting mainly of residential
trash scrap metal car parts etc) were observed at a number of locations across the Site no
intact drums or significantly stained or stressed areas were observed Other than the three known
former disposal areas no features were observed during the visual reconnaissance which indicate
the potential presence of large disposal or dumping areas
The above mentioned areas which contain debris including several empty 55-gallon drums were
further assessed during the soil gas and geophysical screening surveys performed as part of the
Phase 1A investigation The findings of these screening surveys are discussed below
412 Soil Vapor Survey
The soil vapor survey conducted on-site included a total of 100 soil vapor points installed along
an approximate 100-foot orthogonal grid Six additional sampling points were installed at three
locations where partially buried decomposed or empty 55-gallon drums were observed during
the visual site reconnaissance and at three areas where geophysical surveys detected the presence
of EM-31 andor MAG anomalies Each soil gas sample was analyzed for the presence of the
following eight VOC using a portable gas chromatograph acetone benzene 12-dichloroethene
(DCE) methylethyl ketone (MEK) methyl-isobutyl ketone (MIBK) 111-trichloroethane (TCA)
trichloroethene (TCE) and toluene
Of the 106 soil vapor sampling points tested detectable concentrations of VOC were identified at
only three locations These three locations SV160 SV165 and SV172 (shown on Plate 2-5)
were all located within approximately 50 feet of the Former Primary Disposal Area Specifically
TCE was detected at SV160 and SV165 and TCA was detected at SV165 and SV172
5797wpdocsgalluprifinaltextmasterrifhl061297 4-4 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
Likewise no VOC were detected at three additional survey points SV201 SV205 and SV206
installed within one foot of the 55-gallon drum which was observed at each of those locations or
at survey points SV202 SV203 and SV204 located in the vicinity of geophysical anomalies
identified during the EM-31 and MAG surveys
As described in the Work Plan the soil gas investigation was used as a screening survey to
identify apparent soil contamination in an effort to locate any potential unknown disposal areas
Based on the results of the soil gas survey no additional potential disposal areas were identified
413 Geophysical Investigations and Test Pits
Electromagnetic terrain conductivity (EM-31) and magnetometer surveys were conducted by
Weston Geophysical of Northboro Massachusetts as screening surveys to identify potential
unknown disposal areas The Weston Geophysical Report (provided as Appendix A) describes
in detail the findings of the geophysical investigations The significant findings of these two
screening surveys and of the follow-up test pit program are discussed below
4131 EM-31 Survey
The electromagnetic terrain conductivity measured across the Site was generally uniform with
most anomalies being attributed to wholly exposed or partially buried metallic debris (eg
automobile body parts empty rusted drums scrap pipe angle iron steel culvert and steel cable)
However two EM-31 anomalies could not be accounted for by noted surface features As shown
on Plate 2-14 the two unexplained EM-31 anomalies were located along trend line M at station
550 and at station 590 Due to the complexity of the anomaly located at station 550 an estimate
of its ferrous mass could not be made The second EM-31 anomaly was described as limited in
extent and was estimated to contain approximately 100 pounds of ferrous material assuming a burial depth of five feet (smaller objects at shallower depths would also explain the anomaly)
4132 Magnetometer Survey
The magnetometer survey identified a relatively flat gradient across the Site with a number of
localized anomalies most of which corresponded directly with visible surface features or objects
(as described above) A total of four anomalies were identified which could not be readily
attributed to known surface features Two of these anomalies occurred along trend line M and
correspond to the two EM-31 anomalies described above A third magnetometer anomaly was
identified along trend line C between stations 760 and 800 This anomaly was described as
approximately 10 feet in width and was interpreted as being the result of small amounts of ferrous
material spread over the length of the anomaly (approximately 40 feet) A fourth anomaly was
identified along line L at station 315 This anomaly was interpreted to consist of a small
amount of ferrous material buried at shallow depth
5797wpdocsgalluprifinaltextmraquosterrifhl061297 4-5 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4133 Test Pit Investigations
As described above the geophysical screening surveys revealed a total of four locations at which
EM-31 or magnetometer (or both) anomalies were detected that could not be attributed to visible
surface features The anomalies measured along line M were noted in both the EM-31 and
magnetometer surveys while the anomalies along lines C and L were only measured in the
magnetometer survey To confirm the source of these anomalies test pits were excavated at the
location of each anomaly Test pit excavation was observed by EPA oversight personnel
The presence of varying amounts of miscellaneous buried scrap metal debris described below
was identified at each test pit location At the anomaly located along Line C the excavated
debris included small rusted cans sheet metal and steel cable During the excavation of the test
pit located at the anomaly along line L a three foot long piece of a solid iron rod
approximately one inch in diameter was found buried approximately four inches below the ground
surface At the anomalies located along Line M a variety of ferrous debris was uncovered
including a crushed eight foot section of corrugated steel culvert approximately 2 feet in
diameter sheet metal nuts bolts steel cable and small rusted cans No drums intact or
otherwise were encountered at any location Soil removed from each excavation as well as the
side walls and bottoms of the excavations were screened for the presence of VOC using a PID
No elevated PID readings were measured Furthermore no visible evidence of staining was
noted in the soil at any of the excavations Upon excavation all metallic debris was placed on
the ground surface adjacent to the excavation and the test pits were backfilled with native soil
Test pit logs for the four test pits are shown in Appendix E
414 Background Soils
Soil samples were collected at two monitoring well cluster locations MW109 and MW112 to
determine the general Site background levels of TALTCL compounds The two locations were
chosen based on their upgradient position in relation to the former disposal areas The soils were
submitted for laboratory analysis for TALTCL parameters (VOC SVOC pesticides PCS
metals and cyanide) Tables 4-2 and 4-3 show the positive detections for VOC and metals
These tables only show the constituents that were detected at the site Constituents that were not
detected in any sample are not shown There were no detections of SVOC or pesticidesPCB in
any background soil sample
Due to the limited surficial deposits and abundance of boulders encountered at the MW109
location samples could only be collected from the 6-8 foot interval which is representative of till
at this location Discrete samples collected at the MW112 location were obtained from the 8-10
foot and 40-42 foot intervals which represent stratified drift and till respectively Composite
5797wpdocsglluprifinlaquoltextmlaquosterrifhl061297 4-6 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
samples from MW112 were collected from the 7-14 foot and 34-40 foot intervals (stratified drift
and till respectively) These depths were chosen based on their lithology
The results of the laboratory analyses for the soils collected at MW109 indicate the presence of
trace concentrations (0004 mgkg) of toluene no other VOC were detected No detectable
concentrations of SVOC pesticides or PCB were encountered in soil from the MW109 sample
location
Soils collected at the MW112 location also contained detectable concentrations of toluene
Toluene was detected at concentrations of 003 0017 0029 and 0032 mgkg from 8-10 feet 7shy
14 feet 10-14 feet and 34-40 feet respectively Trace concentrations of methylene chloride
(0003 mgkg) and trichloroethene (0002 mgkg) were also detected in the MW112 sample at 10shy
14 feet and 40-42 feet respectively No detectable concentrations of SVOC pesticides or PCB
were identified at the MW112 location
Although the source of the VOC is unknown all three of these compounds are organic solvents
that are (or were ) commonly used in many household (eg spot removers paint strippers
aerosols) commercial (eg pesticide formulations inks and dyes) and industrial (eg
degreasers) products
Metals concentrations in background soil boring samples are shown on Table 4-3 As expected
various metals were detected in all soil samples Analytical results for metals for all of the
MW112 samples were within the common range for soils found in the eastern United States
Heavy metals were generally detected only at trace concentrations Alkaline earth metals (eg
Ca Mg K) were detected at levels not unexpected for soils in the region Background concentrations of metals in subsurface soils were used for comparison purposes in analyzing the
significance of the metals concentrations measured in other non-background soil samples
415 Soils From Former Known Disposal Areas
Soil borings were drilled at each former known disposal area to determine whether residual
contamination remains in surface and subsurface soils During the Phase 1A investigation a total
of ten soil borings were performed Soil samples were collected from these borings and
submitted for laboratory analysis for TALTCL parameters (VOC SVOC pesticides PCB
metals) pH total organic carbon (TOC) and moisture content An additional six borings were
performed during the Phase IB Investigation Soil samples collected during the Phase IB
Investigation were submitted for laboratory analysis for VOC and pesticidesPCBs The
locations of the soil borings are shown on Plate 2-3
5797wpdoc8galluprifinaltextma8terrifhl061297 4-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Samples from the 0-1 foot interval were collected from each boring by hand using a stainless
steel scoop Continuous soil samples beneath the 0-1 foot interval were collected using a truck-
mounted drill rig equipped with standard split-spoon samplers Generally samples were collected
from both above and below the water table and at depth within each of the former known
disposal areas In addition each significant lithologic unit was sampled The specific sampling
depths and length cf sampling interval varied for different analytical parameters depending on the
lithology and volume of sample recovered from each spoon Sample intervals and analytes are
summarized in Table 2-2
A brief description of the reported historical disposal activities and the findings of the Soil
Sampling Program for each specific area are described below Positive hit tables showing the
laboratory results for soil boring samples collected from within the former known disposal areas
are presented in Tables 4-4 through 4-7 The unvalidated laboratory data for TALTCL
parameters are presented in Appendix H (Phase 1A data) and K (Phase IB data) Laboratory
results for pH total organic carbon and moisture content are presented in Appendix R
4151 Former Seepage Bed
The Former Seepage Bed is located near the center of the Site This feature is located on the
north side of a local bedrock high which is overlain by 10 to 20 feet of boundary till Historical
records indicate that this area was used for the direct discharge of liquid waste to the ground
surface It has been reported that an inverted dump truck body was buried in this area and was
connected to the ground surface via a pipe Liquid wastes were then reportedly poured directly
into the pipe The wastes reportedly dumped in this area have been described as low pH liquids
characteristic of metal pickling liquors The dump truck body and the contaminated earth were
removed in 1979 during CTDEP remedial efforts Approximately 20 tons of lime (which is
approximately equal to 10 cubic yards) was reportedly spread in the vicinity of the seepage bed to
neutralize any residual low pH material The soil boring program indicated that fill material in
this area extends from 3 to 7 feet below the ground surface Based on the approximate lateral
extent of this former disposal feature (as shown in historic plans of the Site) approximately 230
yards of sand and gravel fill material were used to backfill the CTDEP excavation
To investigate this area three soil borings (SB101 SB102 and SB103) were completed The
borings within the Former Seepage Bed were terminated at auger refusal depths of 68 feet
(SB101) 185 feet (SB102) and 160 feet (SB103) Within this area groundwater was only
encountered in the bottom 6 inches of the deepest boring (SB 102)
5797wpdocsgalluprifinaltextmasteiTifnl061297 4-8 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Surface Soil Sample Results - Former Seepage Bed
As shown in Table 2-2 the 0-1 foot interval was sampled at each location and submitted for
laboratory analysis for VOC SVOC pesticides PCB and metals No VOC were detected in this
interval at any of the three soil borings within the Former Seepage Bed In the 0-1 foot interval
very low levels of SVOC primarily polynuclear aromatic hydrocarbons (PAH) were detected at
SB101 and SB103 The concentrations of PAH ranged from 0012 ppm to 0076 ppm Moderate
concentrations of bis(2-ethylhexyl)phthlate (15 ppm) were also seen in this interval at SB101
Trace levels of certain pesticides were also seen in the 0-1 foot interval at SB101 [44-DDE
(00014 ppm) 44-DDT (0019 ppm) and 44-DDD (0041 ppm)] and at SB102 [44-DDD
(0011 ppm)] At SB102 a low level of PCB (Aroclor-1260 at 0027 ppm) was detected in the
surface soil sample
The results of metals analyses have been compared to background soils metal concentrations
determined from soil samples collected from the background monitoring wells MW109 and
MW112 With the exception of calcium (12200 ppm) and magnesium (9620 ppm) seen in the
0-1 foot interval at SB102 most metals in the surface soil samples were close to the background
concentrations seen at the Site The elevated concentrations of both calcium and magnesium are
attributed to the 20 tons of lime which were used in this area by CTDEP Compared to the
background level seen for lead (35 ppm) the concentration of this metal in the 0-1 foot interval
was slightly higher at SB101 (59 ppm) SB102 (43 ppm) and SB103 (69 ppm) Also silver
which was not seen in any of the background samples was detected in the 0-1 foot interval at
SB101 at 87 ppm
Unsaturated Zone Sampling Results - Former Seepage Bed
Within the unsaturated zone below the 0-1 foot interval described above only trace levels of
VOC were detected Toluene was seen in SB101 (4-6 feet) and SB102 (16-18 feet) at a
concentration of 0002 ppm Xylene (total) was also detected at the same two intervals at the
same concentrations The only other VOC detected was TCE in SB101 (4-6 feet) at a
concentration of 0004 ppm
The only SVOC detected within the unsaturated zone at the Former Seepage Bed was di-n-octyl
phthlate detected in all three borings at various depths at concentrations ranging from 001 to
0021 ppm Very low concentrations of several pesticides (SB101) and PCB (SB101 and SB102)
were detected at various depths in unsaturated zone samples below the 0-1 foot interval The
pesticides 44-DDD (0033 ppm) 44-DDT (0024 ppm) and dieldrin (000064 ppm) were
5797wpdocBgalluprifinaltextmlaquosteiTifhl061297 4-9 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
detected at SB 101 The highest detections of the PCS for Aroclor-1260 and Aroclor-1254 were
0027 (SB102 0-1 feet) and 0034 ppm (SB1012-5 feet) respectively
Within the unsaturated zone below the 0-1 foot interval the only metals detected above the
highest background concentrations were aluminum barium iron magnesium manganese and
potassium The highest concentration of each of these metals was only slightly higher than
background levels and all were within the same order of magnitude
Among the Former Seepage Bed borings only one (SB 102) encountered groundwater above the
auger refusal depth Since only six inches of saturated soil was encountered the limited sample
volume was submitted for VOC analysis only No VOC were detected in this sample
pH TOC Moisture Content - Former Seepage Bed
The pH of samples collected in this area ranged from 622 to 792 Total organic carbon values
(mgkg) ranged from 1600 to 23000 Moisture contents ranged from 42 to 105 percent
4152 Former Secondary Disposal Area
The Former Secondary Disposal Area is located in the northwestern corner of the Site adjacent to
the railroad tracks The Disposal Area is presently seen as a depression which is approximately
50 feet wide by 60 feet long and is approximately 6 to 8 feet below the surrounding ground
surface The ground surface at this area is covered by approximately 2 feet of backfill (mostly
sand) material The fill is underlain by fine- to coarse-grained sand which ranges in thickness
from approximately 6 to 22 feet Sandy till ranging in thickness from 10 to 20 feet underlies the
sand The depth to groundwater from the bottom of the depression is approximately 10 feet
Historical records indicate that this area was used for the disposal of drummed liquid wastes
Approximately 200 drums and an unknown quantity of contaminated soil were removed in 1979
during CTDEP remediation efforts
In order to characterize residual contamination which may be present beneath this area three soil
borings (SB 104 SB 105 and SB 106) were performed within the depressed area ranging in depth
from 30 feet (SB 105) to 36 feet (SB 104) Within this area groundwater was encountered at
approximately 10 feet below the ground surface
5797wpdocsglaquolluprifinlaquoltextmaBterrifnl061297 4-10 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Surface Soil Sample Results - Former Secondary Disposal Area
Within the 0-1 foot interval only a trace concentration of one VOC (ethyl benzene at 00006
ppm) was detected (at SB104) The only SVOC detected in this interval was butylbenzylphthlate
(014 ppm) at SB 104 Very low concentrations of pesticidesPCB were measured at each boring
Aroclor-1254 was detected at SB104 (0025 ppm) and SB105 (0021 ppm) Aroclor-1260 was
detected at all three borings ranging in concentration from 00089 to 0031 ppm Dieldrin was
detected at SB 104 at trace levels (000048 ppm)
In the 0-1 foot interval nearly every metal detected occurred at concentrations close to those for
the background samples with the exception of lead which was detected at a concentration of 118
ppm at SB 104 Cyanide was detected in this interval at very low concentrations ranging from 16
to 97 ppm
Unsaturated Zone Sample Results - Former Secondary Disposal Area
Between the 0-1 foot interval and the groundwater table at the Former Secondary Disposal Area
no VOC were detected The only SVOC detected in this zone were at very low levels
(butylbenzylphthlate at 0037 ppm and di-n-octylphthlate at 0012 to 0029 ppm) Also in this
interval at SB104 and SB105 low levels of the PCB Aroclor-1254 and -1260 were detected at
concentrations up to 0055 ppm and 0018 ppm respectively Dieldrin was detected at a trace
level (00014 ppm) at SB104 Within this zone most of the metals were close to the background
soil concentrations except for lead (224 ppm) at SB104 and copper (476 ppm) at SB105
Cyanide was detected in the 1-10 foot interval at SB104 and SB105 at very low concentrations of
83 and 31 ppm respectively
Saturated Zone Sample Results - Former Secondary Disposal Area
Beneath the groundwater table within the Former Secondary Disposal Area no VOC were
detected The only SVOC detected was di-n-octylphthalate which ranged in concentration from
002 to 008 ppm Very low levels of endrin (00004 ppm) and Aroclor-1248 (001 ppm) were
also detected just below the water table but were not present in the deepest sample collected (26shy
28 feet) The only metals which were detected below the water table at concentrations notably
higher than background levels were copper and nickel Copper ranged in concentration from 621
to 863 ppm while nickel ranged from 119 to 169 ppm The highest concentrations of these
two metals were detected just below the groundwater table
5797wpdocsgalluprifinaltextmasterrifhl061297 4-11 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
pH TOC Moisture Content - Former Secondary Disposal Area
The soil pH ranged from 688 to 751 TOC ranged from lt 1500 to 2800 mgkg and moisture
content ranged from 37 to 124 percent
4153 Former Primary Disposal Area
The Former Primary Disposal Area is located at the northern end of the Site approximately 150 feet east of the Former Secondary Disposal Area This feature is seen as a circular depression
approximately 130 feet in diameter (at the top edge) and is approximately 8 to 10 feet lower than
the surrounding ground surface Non-native fill material (sand and gravel) ranged in thickness
from approximately 2 to 4 feet Underlying the fill is an approximately 15- to 20- foot thick
generally sandy horizon which overlies 6 to 15 feet of till The water table in this area ranges
from approximately 3 to 6 feet beneath the ground surface in the bottom of the depression
Records indicate that approximately 1400 drums and approximately 5000 gallons of free liquids
were removed from the Former Primary Disposal Area during CTDEP cleanup efforts
Approximately 2000 to 3000 cubic yards of contaminated soil were also removed during that
effort
During the Phase 1A (1994) investigation a total of four soil borings (SB107-SB110) were
completed within the Former Primary Disposal Area to characterize the extent of residual soil
contamination These borings ranged in depth from 24 feet at SB108 to 39 feet at SB109 An
additional six borings (SB111-SB116) were completed during the Phase IB (1995) investigation
Samples collected during the Phase IB investigation were submitted for laboratory analysis for
VOC and PCBPesticides The purpose of the additional borings was to further delineate the
lateral extent of residual VOC and PCB contamination in the unsaturated portion of the soil The
Phase IB borings were terminated just below the groundwater surface typically five to seven feet
below the ground surface The locations of all of the borings are shown on Plate 2-5 however a
detailed close-up showing the boring locations within the Former Primary Disposal Area is shown
as an insert on Plates 4-2 and 4-3 which are discussed below The tabulated laboratory data for
both the Phase 1A and Phase IB soil borings are shown on Tables 4-4 through 4-7 (VOC SVOC
pesticidesPCB and metals respectively)
Surface Soil Sample Results - Former Primary Disposal Area
In the 0-1 foot interval only a limited number of VOC were detected generally at very low
concentrations (Table 4-4) The compounds detected in the 0-1 foot interval (followed by
concentration [ppm] and location) are as follows acetone (0007 ppm at SB107)
5797wpdocsgalluprifinaltextmasterri fhl061297 4-12 QST Environmental
Catlaps Quarry Superfund Project - Remedial Investigation
tetrachloroethene (PCE) (0018 ppm at SB109 and 0002 at SB113) toluene (0005 at SB112
0003 at SB1H and 0002 at SB115) ethyl benzene (0002 at SB113) and total xylenes (0010 at
SB113) In this same interval several phthalates (butylbenzyl bis(2-ethylhexyl) diethyl and dishy
n-octyl) were detected at various locations (Table 4-5) with no apparent spatial trend at
concentrations ranging from 0008 to 17 ppm Several PAH compounds were also detected at
SB110 in the 0-1 foot interval at concentrations ranging from 0007 to 0017 ppm As shown in
Table 4-6 Aroclor 1254 was detected in the 0-1 foot interval at every boring at concentrations
ranging from 0046 to 43 ppm Aroclor-1260 was also detected in the 0-1 foot interval at
concentrations ranging from 0046 to 23 ppm Trace concentrations of several pesticides were
also detected in the 0-1 foot interval in some borings as follows heptachlor epoxide (000058 to
0052 ppm) dieldrin (000059 to 0043 ppm) 44-DDE (000089 to 0081 ppm) and 44-DDT
(000048 to 0027 ppm) Aluminum (12200 ppm at SB110) was the only metal in the 0-1 foot
interval that was detected at concentrations significantly greater than background levels (Table 4shy
7) Cyanide was detected at a very low concentration of 16 ppm at both SB109 and SB110
Unsaturated Zone Soil Sample Results - Former Primary Disposal Area
Beneath the 0-1 foot interval but above the water table a small number of VOC were detected at
various concentrations and locations (Table 4-4) Within this zone no VOC were detected at
SB107 At SB108 methylene chloride was detected at 0001 ppm Ethyl benzene was detected
at SB 109 (015 ppm) SB110 (54 ppm) SB111 (0048 ppm) and SB115 (16 ppm) Total
xylenes were seen at SB109 (16 ppm) SB110 (46 ppm) SB111 (064 ppm) and SB115 (80
ppm) Toluene was detected at SB 110 through SB 115 at concentrations ranging from 0003 to 12
ppm PCE was seen at SB109 SB111 SB114 and SB116 at concentrations which ranged from
0003 to 17 ppm and at SB115 at 28 ppm 111-TCA was detected at SB111 112 114 115
and 116 from 0001 to 14 ppm TCE was also seen at SB111 114 115 and 116 at
concentrations ranging from 0002 to 17 ppm 2-butanone (MEK) was detected at SB111 at
0005 ppm 12-DCE was seen at both SB115 (016 ppm) and SB116 (0009 ppm) Finally 11shy
DCA (0008 ppm) 11 -DCE (0009 ppm) and carbon disulfide (0022 ppm) were all seen at
SB115 Methylene chloride (0001 ppm) was detected at SB108 These detections occurred in
the transition zone between fill and native deposits
The SVOC detected in this zone (shown on Table 4-5) included several phthalates at
concentrations ranging from 0039 to 46 ppm Napthalene was also detected at SB109 (047
ppm) and SB110 (63 ppm) 12-dichlorobenzene and 2-methylnapthalene were detected at SB110
at 098 and 081 ppm respectively The most frequent occurrence and highest concentrations of
phthlates (and SVOC in general) occurred at SB 109 and SB 110
5797wpdocraquogalluprifinaltextmlaquolaquoterrifhl061297 4-13 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
As shown on Table 4-6 Aroclor-1254 occurred at most of the borings in this zone at gtbullraquo
concentrations ranging from 00023 to 64 ppm Aroclor-1242 (0043 to 017 ppm) and Aroclorshy
1260 (043 to 24 ppm) were detected at SB109 and SB110 Pesticides were also detected at trace
to very low concentrations at several locations These compounds include dieldrin (000028 shy
00046 ppm) 44-DDE (000043 - 00063 ppm) 44-DDT (00013 - 00081 ppm) beta BHC
(00013-00021 ppm) and delta BHC (000086-00024 ppm) endrin ketone (00028 ppm)
heptachlor epoxide (0008 ppm) heptachlor (00093 ppm) endosulfan I (0008 ppm) and
methoxychlor (0140 ppm) Table 4-7 shows that the only metals detected within this zone at
concentrations significantly higher than background levels were cadmium (131 ppm) and copper
(103 ppm) both of which occurred at SB109 Cyanide was detected in SB110 in the 1-35 foot
interval at a very low concentration of 32 ppm
Saturated Zone Soil Sample Results - Former Primary Disposal Area
The highest concentrations of VOC within the Former Primary Disposal Area occurred just below
the surface of the groundwater table in the natural deposits immediately underlying fill material
As shown on Table 4-4 in the 4-6 foot interval at SB 109 the following VOC were detected 12shy
DCE (059 ppm) PCE (36 ppm) TCA (98 ppm) TCE (62 ppm) ethyl benzene (85 ppm)
toluene (44 ppm) and xylenes (46 ppm) In the next deepest interval sampled (14-16 feet)
generally the same compounds were detected however the concentrations were lower by an
order of magnitude At the last sampled interval (30-32 feet) generally the same compounds
were again detected but at trace levels (0001-0006 ppm) Cyanide was detected in SB110 in the
10-16 foot interval at a very low concentration of 11 ppm
A total of six SVOC were detected just below the water table at a depth of 4-8 feet below ground
surface (Table 4-5) phthalates (0039 to 0058 ppm) napthalene (021 ppm) 2-methylnapthalene
(0034 ppm) phenol (016 ppm) and 124-trichlorobenzene (0046 ppm) SVOC at greater
depths were napthalene (0076 ppm) in the 10-16 foot interval and bis(2-ethylhexyl)phthlate (11
ppm) at the 22-32 foot interval Aroclor-1254 was detected at concentrations which decreased
with depth from 02 ppm at 4-8 feet to 00096 ppm at 23-34 feet
In the saturated zone no metals were detected at levels significantly greater than background
pH TOG Moisture Content - Former Primary Disposal Area
Values for soil pH ranged from 609 to 745 TOC ranged from lt 1500 to 5500 mgkg and
moisture content ranged from 49 to 282 percent
5797wpdocsgalluprifinaltextmasterrifnl061297 4-14 QST Environmental
Gallups Quarry Superfand Project - Remedial Investigation
416 Contaminant Source Investigations Summary
The previous discussions regarding the contaminant source investigations are grouped into two
categories
bull surveys to identify unknown disposal areas (if any) and
bull investigations at known former disposal areas
Based on the findings of the Visual Site Reconnaissance the Soil Vapor Survey and the
Geophysical Investigations (including the subsequent confirmatory Test Pits) it is apparent that
significant unknown hazardous materials disposal features do not exist at the Site
Based on investigations performed within the known former disposal areas it is evident that the
Former Seepage Bed and the Former Secondary Disposal Area contain generally trace levels of
VOC SVOC pesticides PCB compounds and cyanide For the most part soil metal
concentrations are comparable to background levels measured at upgradient locations at the Site
although very low levels of cyanide (ranging from 11 - 97 mgkg) were also detected at various
depths within the Former Primary and Secondary Disposal Areas Elevated levels of calcium and
magnesium detected at the Former Seepage Bed can be attributed to the large amount of lime
which was reportedly used during remedial efforts Although elevated concentrations of several
other metals were detected at a few locations these levels appear to fall within regional range
values (for the metals with published ranges)
The Former Primary Disposal Area appears to be the only area with notable levels of residual
contamination primarily VOC including ethyl benzene toluene xylene TCA TCE and PCE
In general the highest VOC concentrations are located at or just below the groundwater table in
native materials immediately beneath the fill materials These concentrations diminish quickly
with depth Toluene ethyl benzene xylene and in one case a low level of PCE were also
detected at or near the ground surface within the fill material Empty gasoline cans numerous
off-road vehicle tire tracks and the remains of large campfire pits have been observed in the
vicinity of the former disposal areas Of the VOC detected the ones considered most significant
are those which are also seen in groundwater above their respective MCL (groundwater results
are discussed separately in section 42) In an effort to illustrate the locations where the more
notable amounts of residual VOC contamination are found Plate 4-2 which shows the locations
of total chlorinated VOC has been prepared On this plate the values for total chlorinated VOC
have been color-coded as follows sample intervals where all compounds were below the detection
limit (BDL) are not colored intervals where total chlorinated VOC values are present but less
5797wpdoc8glaquolluprifinraquoltextmasterrifhl061297 4-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
than 1 ppm are shown in green values between 1 and 10 ppm are shown in yellow and locations
between 10 and 35 ppm are shown in red The highest value for any interval is 31277 ppm
As indicated on Plate 4-2 total chlorinated VOC concentrations were either BDL or less than 1
ppm for the majority of intervals sampled Total concentrations between 1 and 10 ppm (ie
yellow zones on Plate 4-2) were detected at two locations SB108 and SB109 Total chlorinated
VOC concentrations in the 4-6 interval at SB108 were 155 ppm At SB109 total chlorinated
VOC concentrations were between 1 and 10 ppm within the 2-4 foot interval (17 ppm) and the
14-16 foot interval (213 ppm) Total chlorinated VOC concentrations exceeded 10 ppm at two
locations SB 109 (2019 ppm in the 4-6 foot interval) and SB115 (31277 ppm in the 3-5 foot
interval) As seen on the plan view insert on Plate 4-2 SB109 and SB115 are located within
approximately 25 feet of each other in the northwestern quadrant of the Former Primary Disposal
Area The zone of highest chlorinated VOC contamination appears to be located just beneath the
fill horizon in close proximity to the groundwater surface
Trace to low-levels of PCB were also detected in both near surface samples and (at one location)
at a depth of 32 feet below the ground surface The highest concentration of any single PCB
compound was 64 parts per million in the 1-35 foot interval at SB110 Other detections
included 43 ppm (SB107 0-1 foot interval) 3 ppb (0-1 foot interval at SB109 and SB110) 28
ppm (0-1 foot interval at SB113) 23 ppm (0-1 foot interval at SB107) and 24 ppm (1-35 foot
interval at SB110) All other detections were below 15 ppm
Plate 4-3 has been prepared to illustrate the distribution of PCB compounds detected within the
Former Primary Disposal Area Plate 4-3 shows the concentration and locations for total PCB
compounds for all intervals sampled with the area
Total PCB concentrations have been grouped and color coded on Plate 4-3 as follows sample
intervals where no PCB were detected (BDL) are shown as colorless zones where total PCB were
detected at concentrations less than 1 ppm are shown in green Intervals containing between 1
and 5 ppm total PCB are yellow and intervals between 5 and 10 ppm are shown in red (the
highest value for total PCB compounds anywhere was 88 ppm)
As shown on Plate 4-3 total PCB values at the majority of locations within the Former Primary
Disposal Area are less than 1 ppm Values between 1 and 5 ppm (shown in yellow) were
detected at SB109 SB110 and SB113 These intervals all occur within four feet of the ground
surface and all are within the fill horizon The only intervals where total PCB concentrations are
between 5 and 10 ppm are the 0-1 foot interval at SB107 (66 ppm) and the 1 to 35 foot interval
5797wpdoc8galluprifinaltextmastemfhl061297 4-16 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
at SB 110 (88 ppm) There does not seem to be any spatial trend or relationship among these
detections as the detections are scattered among all quadrants of the disposal area
42 Groundwater Quality 421 Temporary Well Point Investigation
The results of the temporary well point investigation discussed in Section 24 indicated the
presence of a narrow groundwater plume (approximately 250 feet in width) of volatile organic
compounds (VOC) originating at the Former Primary Disposal Area and extending about 700 feet
in a northwesterly direction VOC were detected up to Mill Brook and at trace levels at one
location near the northern bank of the brook Plate 4-4 summarizes the VOC detections at
different locations and depths in the aquifer A summary of these field and laboratory data is
presented on Table 4-8 and Table 4-9 respectively The area extent of this VOC plume is in
excellent agreement with the groundwater flow directions measured in the northern Study Area (as
discussed in Section 422) The primary chlorinated VOC detected were 111-trichloroethane
(TCA) trichloroethene (TCE) and 12-dichloroethene (DCE) VOC concentrations within the
Former Primary Disposal Area were found to decrease significantly with depth indicating that the
source material is probably located near or above the water table Further downgradient VOC
were detected at generally lower concentrations and were present throughout the entire aquifer
thickness with no apparent depth-dependent trend Various contaminant transport mechanisms
are discussed in Section 50
In the southern portion of the Study Area low-level detections of methyl isobutyl ketone (MIBK)
were detected in samples from two microwells Also acetone and methylethyl ketone (MEK)
were detected at one location adjacent to Tarbox Road No other VOC were detected at any
location
Due to variability in the results of field VOC analyses (using a portable gas chromatograph) and
off-site laboratory analyses it was determined that the field GC results should not be relied upon
as the only source of information to evaluate either the VOC plume boundary or absolute levels of
particular constituents within the plume Rather the microwell results were subsequently used to
guide the location of monitoring wells and to evaluate relative horizontal and vertical
concentration variations within the VOC plume Water quality data from monitoring wells were
then used to confirm the microwell results and delineate plume boundaries
The results of laboratory metals analyses shown in Table 4-10 and Plate 4-5 do not indicate any
significant source areas on the Site nor are there any apparent trends in occurrence or
concentrations of metals Lead was detected at variable depths and concentrations at a total of 15
microwell locations (TW102 103 104 107 115 120 126 128 139 141 143 148 151 and
5797wpdoclaquogilluprifinaltextmlaquo8terrifhl061297 4-17 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
152) These locations represent nearly every portion of the study area With several exceptions
the majority of iiicrowell lead detections were trace to very low (ie lt 10 ugL) Exceptions
included results from single samples collected at locations TW120 (192 ugL) TW-128 (644
ugL) and TW151 (182 ugL) Although several of the locations at which lead was detected are
downgradient of former disposal areas most of the detections were at locations that are either
upgradient or a large distance (400 to 1000 feet) from former disposal areas Furthermore while
lead was detected at some downgradient locations there were other downgradient locations at
which lead was not detected at all It is also noted that lead was only detected at a concentration
of 1 ugL at the microwell (TW143) placed in the center of the Former Primary Disposal Area
and that lead was not detected at all in the two nearest downgradient (relative to the Former
Primary Disposal Area) microwell locations (TW119 and 137) Based on the lack of significant
detections of lead in most microwells on the Site and the fact that metals are typically much less
mobile than VOC the majority of these detections were not considered to be Site related and may
be attributed to an off-site source Numerous off-site activities may have resulted in lead
contaminations including most notably the observed presence of large lead-containing batteries
abandoned along the west side of the railroad bed and fire armhunting activities (as evidenced by
the large number of spent shotgun shell casings observed in the area)
422 Groundwater Monitoring Wells
The initial (Phase 1A) monitoring well network was designed to (1) confirm the findings of the
microwell survey with respect to the chlorinated VOC plume in the northern Study Area and the
two isolated MIBK detections in the southern Study Area and (2) provide hydraulic data to
determine groundwater flow directions and rates An additional objective of the network was to
evaluate potential bedrock groundwater issues related to the Former Seepage Bed which is
located in an area where the water table lies below the base of the overburden formation
Following the Phase 1A monitoring well installation and sampling program additional rounds of
groundwater samples were collected in April July November 1995 February May August
November 1996 and February 1997 under the Long-Term Monitoring Program In October
1995 additional wells were installed during the Phase IB field program to address groundwater
quality and flow directions from areas north of the site The newly installed monitoring wells
(MW117STT MW118STT MW119STT and MW102B) and the existing monitoring wells
located at the former Pervel flock plant (MW-A -B -C -2 and -3) were also included only in
the November 1995 round of groundwater sampling and were sampled only for VOC analyses
Further details of the monitoring well installation program are provided in Section 27 The
following sections present and discuss the groundwater sampling results for VOC SVOC metals
and pesticidesPCB for all nine rounds of sampling
5797wpdocsgalIuprifinaltextmlaquosteiTifhl061297 4-18 QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
4221 VOC
This section discusses the VOC data collected from groundwater monitoring wells during the nine
sampling events conducted between January 1995 and February 1997 Positive groundwater VOC
detections for the nine sampling events are shown in Tables 4-11 through 4-19 respectively VOC
data for the four 1995 events are presented graphically on Plate 4-6 and the VOC data for the
four 1996 events and the February 1997 event are presented on Plate 4-7
42211 Overburden
Northern Study Area
As shown in Plates 4-6 and 4-7 the monitoring well data for all nine sampling events generally
confirm the microwell survey results with regard to the distribution of VOC downgradient from
the Former Primary Disposal Area
The various VOC detected are grouped into chlorinated VOC (eg TCA TCE 11- and 12shy
DCE tetrachloroethene (PCE) 11-DCA 12-dichloropropane carbon tetrachloride methylene
chloride chloroform and vinyl chloride) and non-chlorinated VOC (eg ethyl benzene toluene
xylene benzene styrene and carbon disulfide) As shown in Plates 4-6 and 4-7 the distribution
of these compounds as reported for the November 1995 and February 1997 sample events
respectively has been used to delineate the horizontal boundaries of a VOC plume which
originates in the vicinity of the Former Primary Disposal Area The plume boundary as depicted
on Plates 4-6 and 4-7 is defined by the locations where any compound was detected in excess of
its respective EPA MCL during the November 1995 and February 1997 sampling rounds
Locations at which VOC were detected at levels greater than their respective MCL during at least one sampling round were MW101(STTT) MW102(STTB) MW105 (STTTB)
MW107(TT) and MW-C (located at the former Pervel flock plant facility) MW116T exceed the
MCL for PCE only and only on one occasion (January 1995 at 17 ppb) VOC in samples
collected from MW116T during the eight subsequent sampling events were all below their
respective MCL At MW101 the only compound which was detected in excess of its MCL was
PCE which was detected in the shallow well at a maximum concentration of 6 ppb in the top-ofshy
till well at concentrations ranging from 15 to 32 ppb and between 22 and 30 ppb in the till well
At MW102S compounds detected in excess of their MCLs were 11-DCE (between 3 and 19
ppb) 12-DCE (between 72 and 670 ppb) PCE (between 10 and 43 ppb) 111-TCA (one
exceedance in July 1995 at 240 ppb) TCE (between 15 and 88 ppb) and vinyl chloride (from not
detected to 86 ppb) At MW102TT compounds that exceeded their respective MCL were 11shy
DCE (from not detected to 35 ppb) 12-DCE (between 140 and 1300 ppb) PCE (above the
MCL during four of the sampling events up to 14 ppb) 111-TCA (one exceedance in August
5797wpdocsgalluprifinaltextmasterrifhl061297 4-19 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
1996 at 200 ppb) TCE (one exceedence in February 1997 at 7 ppb) and vinyl chloride (from not
detected to 430 ppb) MW102B and MW105S each had a one-time MCL exceedence for only
vinyl chloride both occurrences at 3 ppb (in May 1996 at MW102B and in August 1996 at
MW105S
At MW105TT six compounds have exceeded their respective MCL as follows 11-DCE (up to
32 ppb) 12-DCE (between 150 and 1100 ppb) PCE (up to 9 ppb) 111-TCA (between 37 and
390 ppb) TCE (two exceedences up to 14 ppb) and vinyl chloride (from not-detected to 710
ppb) MCL exceedences detected at MW105T are as follow 11-DCE (two exceedences both at
12 ppb) 12-DCE (between 43 and 430 ppb) 111-TCA (one exceedence 380 ppb in February
1996) TCE (one exceedence 27 ppb in November 1995) and vinyl chloride (from not detected
to 1400 ppb) The only compound that exceeded its respective MCL in MW105B is 12-DCE
(between 2 and 180 ppb) MW107TT has had MCL exceedence of the following three
compounds 11-DCE (from not detected to 16 ppb) 12-DCE (between 72 and 1100 ppb) and
vinyl chloride (between 120 and 430 ppb)
Although there is some variation in the distribution and concentration of VOC with each sample
event the plume defined by the November 1995 data set (as shown on Plate 4-6) is nearly
identical to the plume defined by the February 1997 data set (as shown on Plate 4-7) Further
discussion of VOC concentration variations with time is provided in Section 52
Typically VOC in wells located beyond the boundaries of the plume were detected at estimated
or trace to very-low concentrations and were not detected with any regularity VOC were
detected at low levels in at least two-thirds of the samples collected from the following wells
located beyond the boundaries of the plume MW103TT (12-DCE and PCE) MW108B 11shy
DCE PCE and TCA) MW116T (PCE and TCA) SW3S (12-DCE PCE and 11-DCA) and
SW3D (12-DCE TCA and 11-DCA) PCE was detected in excess of its MCL at location
MW116T (17 ppb) during the first sampling event (January 1995) but it was never detected
above 3J ppb in the eight subsequent sampling events
TCA and 12-DCE which were detected in wells at all three locations along the plume centerline
(ie MW107 MW105 and MW102) appear to be good tracers for assessing contaminant
migration away from the Former Primary Disposal Area Based on 1995 data these compounds
have been incorporated into contaminant travel-time analyses presented in Section 5 At locations
MW107 and MW105 the highest concentrations were measured in the top-of-till wells with only
low to trace levels in the shallow wells (TCA and 12-DCE concentration up to 130 ppb and
1100 ppb respectively in MW107TT and up to 390 ppb and 1100 ppb respectively in
MW105TT At location MW102 TCA and DCE were detected at similar concentrations (up to
5797wpdoc8galluprifinaltextmasterrifhl061297 4-20 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
240 and 1300 ppb respectively) in shallow and top-of-till wells For all sampling dates TCA
concentrations in the top-of-till wells along the plume centerline varied from 24 to 390 ppb and
12-DCE levels in the top-of-till wells along the plume centerline ranged from 72 to 1300 ppb
No significant reduction in TCA or 12-DCE concentrations with distance from the Former
Primary Disposal Area is apparent at locations MW107 MW105 and MW102
TCE 11-dichloroethane ethyl benzene benzene 11-DCE 12-dichloropropane PCE toluene
vinyl chloride and xylenes were also detected at each of the three plume centerline locations but
as shown in Plates 4-6 and 4-7 their concentration distributions were more sporadic and TCE
11-DCE PCE and vinyl chloride were the only compounds that exceed their respective MCL
during at least one sampling event TCE was found at concentrations up to 88 ppb (in well
MW102S) 11-DCE was found at concentrations up to 35 ppb (in well MW102TT) the
maximum PCE concentration was measured at 43 ppb (in well MW102S) and vinyl chloride was
measured as high as 1400 ppb (well MW105T) The second highest vinyl chloride value was
710 ppb (well MW105TT) and all other vinyl chloride measurements ranged from not-detected up
to 430 ppb
Wells located within the northern portion of the Site where VOC have never been detected include
MW106TT MW109B and MW110S
Based on the monitoring well and microwell results concentrations within the VOC plume appear
to be relatively evenly distributed throughout the lower three-quarters of the aquifer thickness
Throughout most of the plume area (eg MW107 MW105 and MW101) VOC levels in the
upper five to 15 feet of the aquifer are typically near the detection limit The concentration
reduction near the water table is likely associated with rainwater infiltration Evidence of
infiltration includes the consistently downward hydraulic gradients at MW107 MW108 and
MW116 At these locations the vertical hydraulic gradient is on the order of a factor of 100
greater than the horizontal hydraulic gradient within the VOC plume Location MW102 where
shallow and deep concentrations are similar in magnitude is an exception to this trend of low
concentration near the water table A plausible explanation for the observed concentrations in
MW102S is the hydraulic influence of Mill Brook which as discussed in Section 3323 causes
upward flow in the upper portion of the aquifer near the brook Upward flow near the brook and
MW102S is also supported by the upward hydraulic gradients measured between MW102S and
the stream piezometer PZ-4B
The present PCE distribution in groundwater exhibits inconsistencies with migration from the
Former Disposal Areas PCE was consistently detected at levels above the 5 ppb MCL up to 43
ppb in groundwater samples from wells MW102S MW101TT and MW101T PCE was
5797wpdocraquogalluprifinaltextmasterrifhl061297 4-21 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
measured in well MW116T at 17 ppb in the initial sampling round (January 1995) and
consistently at trace levels in subsequent sampling rounds However only trace levels of PCE
were detected at the MW105 or MW107 locations and the only occurrences of PCE at MW105
or MW107 greater than 5 ppb were three estimated detections of 6 7 and 9 ppb at MW105TT
PCE was not detected in well SW3S and was detected once at a trace level in well SW3D
Monitoring wells MW102 and MW101 are downgradient from both the Former Disposal Areas
and the former Pervel flock plant where PCE TCA and DCE groundwater contamination has
been documented (Section 52) During the November 1995 sampling event VOC detected at
MW-C (located at the former Pervel flock plant) include DCE (97 ppb) TCE (11 ppb) and PCE
(24 ppb) Based on available data MW116 is located downgradient from the former Pervel
flock plant Groundwater flow conditions in the past would need to have been different from
present conditions for MW116 to be downgradient from the Former Disposal Areas Although
the PCE detections at locations MW102 and MW101 could be attributable to historical releases
from the Former Disposal Areas the regional flow pattern and spatial distribution of PCE in
groundwater suggest that contamination from the former Pervel facility has at a minimum
contributed to VOC (PCE TCA and DCE) contamination of these locations Further discussion
of the PCE detections and other VOC concentration variations is provided in Section 52
Southern Study Area
In the southern portion of the Study Area groundwater samples were collected from overburden
monitoring wells at five locations SW9 MW112 MW113 MW114 and MW115 As shown
on Plates 4-6 4-7 no VOC were detected in any of the wells As a result of the consistent lack of
detections wells at these locations were dropped from the Long-Term Monitoring Program (with
EPA approval) after three sampling events These data are consistent with the microwell survey
results but do not support the low-level detections of methyl isobutyl ketone in the two microwell
samples (Section 421)
42212 Bedrock
During the RI VOC were detected in bedrock wells at the following locations MW102 MW105
MW107 MW108 and SW-10 Since the only VOC detected at SW-10 was TCA at an estimated
trace concentration (1J ppb) during the January event and TCA was not detected in SW-10
during the subsequent two sampling events this well was eventually dropped from the Long Term
Monitoring Program (with EPA approval) following the July event All other bedrock wells in
the southern portion of the Study Area (MW111 MW112 MW113 SW-12) were likewise
dropped from the monitoring program At location MW108B estimated concentrations of PCE
(3J ppb) and TCA (up to 9J ppb) were detected during the January and April sampling events
therefore samples collected from this well during the July and November events were submitted
5797wpdocsgalluprifinaltextmasterriftil061297 4-22 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
for VOC analyses using EPA Method 5242 which hs lower detection limits than the TCL
Methods The results of the July and November events for MW108B indicate that other VOC are
present but generally at trace to very low concentrations The highest detections of TCA and
PCE at this location were 92 and an estimated 5 ppb respectively Other VOC detected at
MW108 were carbon tetrachloride (12 ppb) 11-DCA (1 ppb) 12-DCA (015J ppb) 11-DCE
(13 ppb) and xylene (01J ppb)
The only VOC detected at MW107B was TCA which was measured during three events at
concentrations ranging between 059J and 2 ppb Over the nine sampling events VOC detected
at MW105B included 11-DCA (BDL to 9J ppb) 11-DCE (BDL-4J ppb) 12-DCE (11-140J
ppb) 12-dichloropropane (2J ppb in January 1995 and February 1996 only) TCA (2J-12 ppb)
and TCE (BDL-3J ppb)
MW102B was installed during the Phase IB investigation and therefore was only sampled during
five events VOC detected at MW102B were typically at estimated trace concentrations and
only PCE was detected in every round (2J to 4J ppb) The only MCL exceedence was a single
estimated detection of vinyl chloride (3J ppb)
In general VOC detected in bedrock wells were also detected in overburden wells at the same
locations although the concentrations seen in the bedrock wells are significantly lower typically
by an order of magnitude relative to concentrations seen in the top-of-till wells The only
notable exception to this trend is at location MW108 where VOC were not typically detected in
the overburden wells (with the exception of an estimated 2J ppb of DCE detected once in
MW108S and once in MW108TT) At MW105 and MW107 VOC concentrations seen in the till
wells are similar to the low concentrations detected in wells screened in the underlying bedrock
The low VOC levels detected in bedrock wells located in the northern portion of the Study Area
demonstrate that bedrock is not a preferred pathway for contaminant migration This conclusion
is supported by the groundwater hydraulics data outlined in Section 3323 which demonstrate
that the average hydraulic conductivity of the bedrock is more than a factor of 200 less than the
overburden hydraulic conductivity In spite of the upward hydraulic gradient from bedrock to
overburden (factor of ten to 100 larger than the horizontal hydraulic gradient within the VOC
plume) which was found to exist throughout the Study Area vertical (transverse) dispersion
caused by flow in the bedrock fracture system has apparently caused VOC to migrate a limited
distance into the bedrock
5797wpdocsgalIuprifinaltextmasterrifhl061297 4-23 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4222 Semivolatile Organic Compounds
Tables 4-20 through 4-28 present the analytical results for SVOC in groundwater for the nine
sampling events Overall SVOC were detected infrequently and generally at only trace levels
Naphthalene 2-methylphenol and 12-dichlorobenzene were the most frequently detected SVOC
compounds in groundwater samples Naphthalene was detected during every sampling event
generally at MW105 MW107 and MW102 locations within the top-of-till wells and occasionally
also within till at well MW105T The highest naphthalene measurement was 10 ppb in
MW105TT 2-methylphenol was also detected during every sampling event always in well
MW107TT and with lesser frequency in MW105TT MW105T and MW102TT the highest
concentration detected was 3 ppb In eight of the nine sampling events 12-dichlorobenzene was
detected in at least one of the following wells MW102TT MW105TT MW105T MW107TT
and the maximum concentration measured was 4 ppb Maximum bis(2-ethylhexyl)phthalate was
detected in at least one well during six of the nine sampling events the concentrations ranged
from 04J to 35 ppb The locations of the bis(2-ethylhexyl)phthalate detections were sporadic it
was detected three times at MW108S twice at MW014S and MW116T and only once at eleven
wellsTrace levels of the following other compounds were detected during various sampling
events acenaphthene (03J ppb) butylbenzylphthlate (U ppb) di-n-butylphthlate (04J ppb) 4shy
chloroaniline (2J ppb) 24-dichlorophenol (U ppb) fluorene (06J ppb) 4-chloro-3-methylphenol
(2J ppb) phenanthrene (02J ppb) 4-bromophenyl-phenylether (2J ppb) n-nitroso-di-nshy
propylamine (9J ppb) 14-dichlorobenzene (up to 2J ppb) diethylphthlate (up to 04J ppb) 24shy
dimethylphenol (up to 8J ppb) di-n-octylphthlate (up to 46B ppb) 4 methylphenol (2J ppb) and
phenol (up to 4J ppb) The majority of these compounds occur in either the till or top-of-till
wells located within the VOC plume shown on Plates 4-6 and 4-7 (eg MW102 MW105 and
MW107) although there were infrequent detections of compounds at MW103 MW104 MW106
MW108 MW109 SW3D MW112 and MW116 as well
4223 Pesticides and PCB
The only detection of PCB in groundwater was during the April event when Aroclor 1242 was
detected in MW103S and TT at estimated concentrations of 042J and 018J ppb respectively
Estimated low levels of a few pesticides were detected in a small number of groundwater samples
Endosulfan I was detected once (002J ppb in MW107S during April 1995) Endrin was detected
once (00031 JP in MW109S during February 1996) methoxychlor was detected once (012J in
MW107S during February 1997) alpha-BHC was detected once in four wells (during February
1997 up to 0011 JP ppb) beta-BHC was detected twice up to 004J ppb (at MW107S in July
1995 and at MW107TT in February 1996) and gamma-BHC was detected in three samples up to
001JP (at MW105B and MW116S during November 1995 and at MW102S during August 1996)
All positive detections for pesticide and PCB compounds are shown on Table 4-29 (Note Table
5797wpdocraquogalluprifinflltextmasterriftil061297 4-24 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
4-29 only includes those sample IDs where a pesticide or PCB compound has ever been detected)
4224 Inorganics
Tables 4-30 through 4-38 present the analytical results for total (and where applicable dissolved)
metals in groundwater (During sampling low flow purging techniques were used to minimize
disturbance of formation water In cases where turbidity levels less than 5 NTU could be
achieved samples for both total and dissolved metals were collected Otherwise samples were submitted for total metals analyses only) Cyanide has not been detected in any groundwater
sample Metals were generally not detected in groundwater above applicable MCLs and metals
in groundwater samples across the Study Area were similar in concentration to metals detected in
designated groundwater background samples
Analytical results of a duplicate sample collected from MW107S during August 1996 had
anomalously high values Between January 1995 and August 1996 nine samples (seven rounds
plus two duplicate samples) were collected from this well and analyzed for total metals Only one
sample contained inorganic compounds in excess of EPA MCLs or Connecticut Remediation
Standards This sample which was the duplicate sample collected in August 1996 contained
elevated concentrations of aluminum chromium cobalt magnesium manganese and nickel In
order to evaluate the significance of this particular data set a statistical analysis for the
identification of outliers was performed following the procedures described in the EPA guidance
document Statistical Analysis of Ground Water Monitoring Data at RCRA Facilities (EPA530shy
SW089-026) For this analysis a test statistic (TJ was generated (using the average maximum
and standard deviation) from the nine samples for each inorganic analyte detected in this well If
the test statistic was greater than a critical value (1764) representing a 995 level of
significance then there is a strong likelihood that the maximum value for each data set is a statistical outlier If a given analyte was not detected in a given sample the detection limit2 was
used for statistical calculations
Maximum concentrations for nine of the thirteen analytes that have been detected in this well
were found to be statistical outliers Six of the statistical outliers were found in the MW107S
duplicate sample collected in August 1996 which suggests that the inorganic data from this
particular sample are not representative of groundwater quality in the immediate vicinity of this
well Although a specific reason why this sample contained such anomalously high levels is not
apparent it seems clear that this sample is not representative of the actual groundwater metal
concentrations at this location This is supported by the fact that the other sample from this well
on this date has metals concentrations consistent with previous sampling rounds Therefore the
metals data from this duplicate sample have been presented in this Report but are considered not
to be valid
5797wpdocBgalluprifinaltextmasterrifhl061297 4-25 QSTT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4225 DioxinsFurans and Additional Appendix IX Parameters
During the January 1995 sampling event samples from three locations (MW102TT MW106TT
and MW116T) were submitted for laboratory analysis for full Appendix IX parameters During
the April 1995 sampling event samples from MW105TT were also submitted for full Appendix IX
analyses The results for the VOC SVOC PesticidePCB and metals analyses for these samples
have been included in the appropriate tables as discussed in previous sections The results of
Appendix IX analyses that are not common to target analyte and target compound lists
(TALTCL) are discussed below Analyte groups specific to the Appendix IX lists include
herbicides (EPA Method 8150) volatiles by direct aqueous injection (EPA method modified
8015) Phenols (EPA Method 4202) Sulfide (EPA Method 3761) Organophosphorus Pesticides
(EPA Method 8141) PesticidesPCB by EPA Method 8080 and DioxinsFurans
The only detections for any of the analyte classes specific to Appendix IX compounds during the
January 1995 event were phenols (MW102TT at 7 ppb and MW116T at 15J ppb) During the
April 1995 event the dioxinfuran compounds HxCDD (total) and TCDF (total) were detected at
MW105TT at concentrations of 705 and 193 ngL (part per trillion)
423 Residential Wells
Residential wells were sampled during the Phase 1A investigation (January 1995) and again
during July 1995 February 1996 and August 1996 under the Long-Term Monitoring Program
4231 Volatile Organic Compounds
Tables 4-39 through 4-42 present the results of VOC analyses for residential well samples The
locations of these wells are shown on Plate 2-5 TCA was detected at DW114 during all four
sampling events and was also detected once at DW111 and DW113 the concentration ranged
from 018J to 066 ppb Chloroform was detected during three of the sampling events twice at
DW102 and once at DW104 and DW107 the maximum concentration detected was 19 ppb The
following compounds were also detected at low levels once bromodichloromethane (2 ppb at
DW107) dibromochloromethane (084J ppb) PCE (016J ppb at DW114) chloromethane (082J
ppb at DW103) and at DW111 ethylbenzene (025J ppb) toluene (012J ppb) and xylenes
(0 U) Since these locations are not downgradient with respect to the Site the occurrence of
these compounds in these wells are not likely to be Site related
4232 Semivolatile Organic Compounds
No SVOC were detected in any residential well sample during any of the four sampling events
5797wpdocsgalIuprifinaltextmasterrifhl061297 4-26 QT Environmental
Gallups Quarry Superjund Project - Remedial Investigation
4233 Pesticides and PCS
Tables 4-43 through 4-46 present the analytical results of pesticide and PCB analyses for
residential well samples Alpha-chlordane and gamma-chlordane were both detected in all four samples collected from DW105 and in three of the samples collected from DW106 The
maximum concentrations measured were 0095 ppb for alph-chlordane and 004 ppb for gamma-chlordane During August 1996 44-DDE and heptachlor epoxide were both also detected at
DW105 and DW106 (001J ppb for 44-DCE and up to 002J ppb for heptachlor epoxideNo PCB compounds were detected in any residential well The fact that DW105 and DW106 are not
downgradient relative to the site indicate that these compounds are likely attributable to the off-site use of these pesticides and are not site-related
4234 Inorganics
Tables 4-47 through 4-50 present the analytical results of metals and cyanide analyses for
residential well samples for the four sampling events Heavy metals were generally not detected
or were detected at trace levels Alkaline earth metals (eg Ca Mg K) were detected at levels
not unexpected for natural groundwater in the region
43 Surface Water Sediment and Wetland Soils Surface water sediment and wetland soils upstream adjacent to and downstream of the Site
were sampled and analyzed during the Phase 1A investigation to assess the potential if any for
transport of constituents of concern from the Site Sample locations are shown on Plate 2-6 Sediment was collected from one additional location (UB-6A) during the April 1995 sampling round As part of the Long Term Monitoring Program additional rounds of surface water
samples were collected during the April and November 1995 and May and November 1996
sampling events The samples were analyzed for VOC SVOC metalscyanide and pesticidePCB with the exception of the November 1996 samples which with EPA approval
were analyzed only for VOC and metals It is noted that following the Phase 1A sampling event
(September 1994) stations UB-1 UB-2 and UB-3 were eliminated from the Long Term
Monitoring Program (with EPA approval) as these locations are upstream of station UB-4 which
is also upstream from the Site Also station UB-6 (which was located on a tributary to Mill
Brook and sampled during the Phase 1A program) was replaced by station UB-6A (located within
Mill Brook) during the four Long-Term Monitoring events
431 Surface Water During September 1994 water quality indicators (pH dissolved oxygen temperature
conductivity turbidity) were measured in the field at eleven surface water sampling stations six
in Upper Mill Brook two in Lower Mill Brook (below the confluence with Fry Brook) one in
Fry Brook and two in Packers Pond The remaining six locations were dry at the time of
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 4-27 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
sampling As presented in Table 4-51 the water quality of the watershed as judged by both field
measurements and wet chemistry (TSS alkalinity hardness) was good to excellent It may
however be important to note that all of the samples were taken under fair weather conditions so
the influence of potential non-point sources during storm events cannot be assessed with this data
set Table 4-51 presents a qualitative assessment (eg slight moderate obvious) of potential
Local Non-Point Source Pollution As most sampling stations are either adjacent to or
downstream from developed (eg streets highways residences agricultural or industrial
property) the immediate andor cumulative impact of storm events cannot be evaluated in this
report During the four Long-Term Monitoring surface water sampling events field parameters
were again measured The results of these sampling events are shown in Table 4-52
During the September 1994 Phase 1A investigation surface water temperature ranged from 60 degF
(UB1 UB2) to 70degF (PP3) Surface water at most locations contained adequate concentrations of
dissolved oxygen ranging from 335 (UB2) to 1035 (UB8) mg1 but were slightly acidic with
pH varying from 528 (UB1) to 572 (PP3) Dissolved solids measured indirectly as specific
conductivity varied from 120 (UB1) to 710 (PP3) imhoscm
During the four Long-Term Monitoring sampling events surface water temperatures ranged from
526 to 617degF in April 1995 and 420 to 508degF in May 1996 to seasonally lower temperatures
of 396 to 453degF in November 1995 and 374 to 400degF in November 1996 The dissolved
oxygen concentrations were generally similar between the various sampling events ranging from
a low of 335 mg1 (at UB-2 in September 1994) to a high of 1030 mg1 (at PP-1 in November
1996) pH measurements indicated slightly acidic water with the following ranges 514 to 605
in April 1995 574 to 667 in November 1995 615 to 701 in May 1996 and 472 to 620 in
November 1996 Conductivity values were in the same general range between the different
sampling events with the lowest measurement of 1 anhoscm at PP-1 in November 1996 and the
highest measurement of 523 xmhoscm at UB-5 in April 1995
Based on laboratory results surface water in the area is fairly soft ranging in hardness (as
CaCO3) from 12 (TR-1 during April 1995) to 179 (UB2 during September 1994) mg1 and in
alkalinity from lt 1 (UBS during April 1995) to 67 (UB2 during September 1994) mg1 Total
dissolved solids and total organic carbon were below 200 ppm and 15 ppm respectively at nearly
every station during all five sample events A total of 58 total suspended solids analyses were
performed on samples collected during the five sampling events Most of the results were below
the detection limit and only 10 samples exceeded 10 mg1 The highest concentrations were
detected at UB-5 (between 82 and 2470 mg1 in the four samples collected at that location) and at
PP-1 (between 87 and 1500 mg1 in the three samples collected at that location)
5797wpdocraquogalluprifinaltextmasterrifhl061297 4-28 QST Environmental
Gallups Quarry Supcrjund Project - Remedial Investigation
4311 VOC- Surface Water
Data presenting he concentrations of various VOC for each individual surface water location are
presented in Table 4-53 through 4-57 for the September 1994 April and November 1995 and
May and November 1996 sampling events respectively VOC were not detected in the upstream
portion of Mill Brook Six VOC were detected at least once in the five rounds of surface water
samples collected from 11 locations The most consistent detections were 12-DCE and PCE in
Fry Brook sample FB-1 12-DCE was detected every round at FB-1 and occasionally at four
other locations up to 8J ppb and PCE was detected every round at FB-1 and occasionally at
three other locations up to 11 ppb Sample location FB-1 is approximately 1500 feet upstream
of the confluence of Fry Brook and Mill Brook the detections at FB-1 are not likely to be Site-
related and may result from nearby industrial activities The other detections of PCE and DCE
were at trace concentrations at locations below the confluence of Fry and Mill Brooks In
addition TCA was detected once at UB-10 at 3J ppb TCE was detected twice at FB-1 and once
at UB-9 up to 2 ppb carbon disulfide was detected in seven samples representing six locations
up to 20 ppb and toluene was detected twice at upgradient location UB-5 at 1J ppb All of the
VOC concentrations detected are well below those expected to cause adverse effects in fish or
wildlife (USEPA 1986)
4312 SVOC - Surface Water
During the September 1994 sampling event only low levels of one SVOC compound 4shy
methylphenol (28 ppb PP3 1 ppb UB2) were detected in surface water samples The locations
where SVOC were detected are far upstream (UB 2) and downstream (Packer Pond) locations and
are unlikely to have been impacted by the Site During the April 1995 sampling event the only
SVOC detected were trace levels of fluoranthene (04J ppb) phenanthrene (03J ppb) and pyrene
(04J ppb) all of which were detected at UB-5 which is upstream from the site There were no
SVOC detected in any surface water samples during the November 1995 event During the May
1996 sampling event bis(2-ethylhexyl)phthalate was detected in four samples at concentrations
ranging from 05J ppb to 140J ppb The locations of the detections are upgradient of the Site
(UB-5 and UB-8) and downgradient of the Site (LB-2 and PP-1) The sample from LB-2 also had
an estimated low level of di-n-octylphthalate (7J ppb) Table 4-58 presents all of the SVOc
detections in surface water samples (Note Table 4-58 only includes those sample IDs where a
SVOC has ever been detected)
4313 PesticidesPCBs - Surface Water
No pesticides or PCB compounds were detected in any surface water samples
5797wpdocsgalluprifinaltextmraquosterrifhl061297 4-29 Q5T Environmental
Gallups Quarry Superfund Project - Remedial Investigation
4314 Total and Dissolved Metals - Surface Water
Because of the ubiquity of naturally occurring metals in surface waters metals results are more
easily interpreted by generating descriptive statistics Descriptive statistics for metals measured in
surface water during 1994 and 1995 are presented in Appendix S Data presenting total and
dissolved metals concentrations for each individual sampling location during all five sampling
events are presented in Tables 4-59 through 4-65
Total Metals
Cadmium silver and thallium were not detected in any samples during the five sampling events
Other constituents detected in only one or two samples during each event include arsenic (up to
296J ppb) beryllium (once at 26B ppb) chromium (up to 764 ppb) cobalt (up to 26 IB ppb)
copper (up to 165 ppb) cyanide (up to 466 ppb) mercury (once at 018B ppb) nickel (up to
821 ppb) selenium (181J ppb at PP3) silver (once at 3J ppb) and vanadium (133 ppb) With
die exception of station UB2 during the September 1994 sampling event UB-5 during die April
1995 May 1996 and November 1996 events and PP-1 during the May and November 1996 events the remaining metals (aluminum barium calcium iron lead magnesium manganese
potassium sodium and zinc) were detected at concentrations that are expected in natural waters
(Hem 1989)
Dissolved Metals
Beryllium cadmium cobalt mercury selenium and thallium were not detected in any sample
Constituents detected infrequently and at low concentrations include antimony arsenic
chromium nickel silver vanadium and zinc Copper was detected at several locations upstream
and downstream from the site at concentrations ranging from 25 to 208B ppb although there
was no pattern in its occurrence or concentration Lead was detected at least once at each of the
sampling locations ranging in concentration from 1J ppb to 188 ppb The occurrences of lead
did not show a pattern die highest measurements were as follows 11 ppb at PP-3 in September
1994 188 ppb at UB-9 in April 1995 16J ppb at UB-4 in November 1995 56J ppb at UB-5 in
May 1996 and 91J ppb at UB-5 in November 1996 Locations UB-4 and UB-5 are upgradient
of the Site The lead detections in Packer Pond samples likely results from non-point sources to
Packers Pond The remaining metals (aluminum barium calcium copper iron lead
magnesium manganese potassium and sodium) were detected at concentrations that are expected
in natural waters (Hem 1989)
Concentrations of total and dissolved metals in surface waters were generally detected infrequently
and at concentrations below ambient water quality criteria ie those that would not pose a threat
5797wpdocsgalluprifinraquoItextmaBterriftil061297 4-30 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
to fish or wildlife (EPA 1986) Heavy metals such as copper and lead generally considered
harmful to aquatic life were detected at locations (Fry Brook and Packers Pond) that are not
likely to be impacted by the Site One location UB-5 (which was dry during September 1994)
contained elevated levels of most metals during the 1995 and 1996 sampling events This sample
station is located well upstream from the site on a tributary to Mill Brook which originates in a
small pond adjacent to Interstate 395 in a highly commercialized area
432 Sediment
A total of seventeen sediment samples were collected during the Phase 1A field survey
(September 1994) six of which were dry at the time The composition of the sediment samples
varied from deep muck (eg LB-02) to a firm sandy substrate (eg UBS) The total organic
carbon (TOC) content of the sediments (presented in Table 4-30) ranged from 075 (UB4) to 16
(PP1) percent with an average of 57 percent
4321 Inorganics - Sediment
Because of the ubiquity of naturally occurring metals in sediment these constituents are more
easily interpreted by generating descriptive statistics which are presented for each individual
metal in Appendix S Data presented for metals at each individual sampling location are
presented in Table 4-66
Antimony and thallium were not detected above the detection limit Beryllium cadmium
chromium cyanide mercury selenium and silver were detected infrequently and when detected
had concentrations close to the respective detection limit andor were detected at remote upstream
or downstream locations With the exception of maximum concentrations detected at PP3 (a
location at Packer Pond which receives stormwater runoff from Lillibridge Road) the remaining metals (aluminum arsenic barium calcium cobalt copper iron lead magnesium manganese
nickel potassium sodium vanadium and zinc) were detected at concentrations within the ranges
expected in naturally occurring soils or sediments (Beyer 1990 Fitchko 1989 Shacklette and
Boerngen 1984)
4322 VOC - Sediment
Analytical results for concentrations of VOC in sediment samples are presented in Table 4-41
VOC were generally detected infrequently and at relatively low concentrations in sediments
Ketones (acetone and 2-butanone) were detected at remote upstream (UB1 UB6) and downstream
(PP1 PP2 PP3) locations One or more of the compounds toluene trichloroethene methylene
chloride and xylenes were detected at trace levels at upstream locations north and east of the Site
(UB-3 UB-5 UB-6 UB-7 and UB-9) Xylenes were detected at a concentration of 31 pm in the
sediment sample from Fry Brook (FB-1) Only toluene at trace level of 0009J ppm was
5797wpdocsgalluprifinaltextma8terrifhl061297 4-31 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
detected in the sediment sample from UB-10 located in Mill Brook near the downgradient edge
of the Gallups plume No VOC were detected in sediment samples from downstream locations
LB-1 and LB-2
4323 SVOC - Sediment
As shown on Table 4-68 the primary SVOC constituents detected were PAH ranging from non-
detect (~ 03 ppm) to 15 ppm No apparent concentration gradient could be determined with
respect to location (eg upstream to downstream) The detections of PAH likely reflect non-
point contributions from local sources such as stormwater runoff from the railroad tracks and
nearby roads
Elevated concentrations of bis(2-ethylhexyl)phthalate were measured in Fry Brook (1300 ppm
FBI) and lower Mill Brook (64 ppm LB2) below the confluence of these two streams The
source appears to originate in Fry Brook
4324 PesticidesPCB - Sediment
Analytical results for pesticides and PCB are provided on Table 4-69 PCB compounds
(Arochlor-1242 -1254 and -1260) were detected in sediment samples from only three locations
all upstream (FB-1 at 019 ppm UB-8 at 0023J ppm and UB-7 at 00064J ppm)
Organochlorine pesticide compounds were also detected infrequently with no apparent trend with
regard to location or source The concentrations in sediment ranged from non-detect (~ 1-3 ppb)
to 39 ppb (methoxychlor at PP1) and their occurrence likely reflects residues of persistent
compounds that were routinely used for insect control before being banned from commercial
production
433 Wetland Soils
A total of 10 wetland soil samples were collected during the field survey most of which were
close to the water table at the time of collection The wetland sampling locations are shown on
Plates 2-6 and 3-14 The total organic carbon content (mgkg) of the wetland soils is as follows
QW1 (160000) QW2 (54600) QW3 (37200) QW4 (35200) QW5 (23900) QW6 (25600)
QW7 (gt 160000) QW8 (gt 160000) QW9 (33600) and QW10 (42600)
4331 Inorganics - Wetland Soils
Because of the ubiquity of naturally-occurring metals in wetland soils these constituents are more
easily interpreted by generating descriptive statistics which are presented for each individual
metal in Appendix S Analytical results for metals at each individual sampling location are
presented in Table 4-66
5797wpdocsgalluprifinaltextmasterrifhl061297 4-32 QSTEnvironmental
Gallups Quarry Superfimd Project - Remedial Investigation
Cadmium and cyanide were not detected in any sample Antimony arsenic beryllium cobalt
mercury selenium silver and thallium were detected infrequently and at trace levels at or below
the detection limit None of the remaining metals (aluminum barium calcium chromium
copper iron lead magnesium manganese nickel potassium sodium vanadium and zinc)
exceeded normal ranges expected for naturally occurring soils (Beyer 1990 Fitchko 1989
Shacklette and Boerngen 1984)
4332 VOC - Wetland Soils
Analytical results for VOC in wetland soils are provided on Table 4-67 VOC including acetone
2-butanone TCE and carbon disulfide were detected infrequently and at low concentrations
Acetone concentrations ranged from non-detect to 056 ppm (QW8) and 2-butanone concentrations
ranged from 0004 ppm (QW10) to 0067 ppm (QW8) QW8 is located in a remote wooded
location approximately 2000 feet west of the Site QW10 is located a few hundred feet west of
the southern portion of the Site
Acetone and 2-butanone were also detected at lower concentrations (015 and 0033 ppm
respectively) at location QW-1 several hundred feet southeast of the Former Primary Disposal Area A trace level of TCE (0004J ppm) was detected in wetlands soil sample QW-2 collected
approximately 50 feet east of the Former Primary Disposal Area This detection may be related
to the Former Primary Disposal Area since TCE has been detected in this area Based on the
topography however surface water runoff from the former disposal area is unlikely to impact the
wetland No other wetland soil samples had concentrations detected above the instrument
detection limit
Although the source of these VOC is unknown acetone 2-butanone and carbon disulfide are all
commonly used in the laboratory and may have been introduced during post-processing sampling
Some of these compounds are organic solvents that are (or were ) commonly used in many
household (eg spot removers paint strippers aerosols) commercial (eg pesticide
formulations inks and dyes) and industrial (eg degreasers) products Their presence in
wetlands soils samples at low concentrations may be the result of localized human activity in the
area
4333 SVOC - Wetland Soils
Analytical results for SVOC in wetland soils are provided on Table 4-68 The primary
constituents detected were the phthalate esters and PAH PAH were detected infrequently at
generally below 01 ppm Phthalate esters were also detected infrequently ranging from non-
detect to 22 ppm (QW8) The presence of these compounds is likely to be associated with
periodic or seasonal flooding of wetlands as the wetland sampling locations are remote and
5797wpdocsgpluprifinaltextma8terrifhl061297 4-33 QST Environmental
Gallups Quarry Superjimd Project - Remedial Investigation
generally inaccessible except on foot Since these compounds are relatively immobile except in
surface water or as airborne particulates these compounds may have originated from non-point
sources such as the railroad line or runoff from nearby highways
4334 PesticidesPCB - Wetland Soils
Analytical results for pesticides and PCB are provided on Table 4-69 PCB compounds
(Arochlor-1242 -1254 and -1260) were detected infrequently and at low concentrations
The presence of trace levels of PCB compounds in wetland soil samples QW-1 QW-2 QW-3
and QW-4 may be Site-related however PCBs are ubiquitous environmental contaminants that
were widely used in industry and may thus be present in soils as a result of past activities at
surrounding industries Other sources of input into the local environment might include
atmospheric deposition transport from upstream sources and deposition following flood events
Organochlorine pesticide compounds were also detected infrequently with no apparent trend with
regard to location or source The concentrations in wetland soils ranged from non-detect to 0016
ppm (44-DDE at QW1) and their occurrence likely reflects residues of persistent compounds
that were routinely used for insect control before being banned from commercial production
44 Air Quality 441 Baseline Air Quality Survey
Ambient air quality was determined prior to the start of Phase 1A intrusive investigations to
establish a baseline for air quality For the baseline survey air quality in the breathing zone
(between approximately three and six feet above the ground surface) was determined based on
measurements of total VOC (using a PID equipped with an 117 eV lamp) and respirable dust
(using a aerosol meter) at eight locations across the Site These eight stations were located at
each of the three known Former Disposal Areas and at upwind and downwind locations along the
perimeter of the Site The locations of the eight baseline air monitoring stations (AM1-AM8) are
shown on Plate 2-1 During the baseline survey no VOC readings were detected above the EPA
approved action level of 1 ppm at any of the eight monitoring locations Also no respirable dust
readings greater than the EPA-approved action level of 005 mgm3 were recorded during the
baseline survey at any of the monitoring stations
442 Perimeter Air Monitoring
Throughout the duration of the Phase 1A field investigations ambient air quality was monitored
on a weekly basis at the eight stations for the same parameters described above In addition to
the eight air monitoring stations continuous air monitoring was performed at each discrete
investigation area (eg each microwell soil boring etc) in the workers breathing zone and at the
5797wpdocsgaIIuprifinaltextmasterrifhl061297 4-34 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
perimeter of each task specific exclusion zone Air monitoring in the work zones was augmented
with instruments to measure hydrogen cyanide and lower explosion levels Also compound
specific calorimetric equipment (eg Draeger tubes) were used to compliment total VOC
measurements recorded with a PID
No readings above ihe EPA-approved action levels were recorded at the perimeter of the Site
throughout the entire duration of the Phase 1A investigation Elevated worker breathing zone
readings for total VOC were recorded during two of the four soil borings performed within the
Former Primary Disposal Area (SB109 and SB110) Varying but sustained elevated VOC
readings in the workers breathing zone during these two soil borings required the use of OSHA
Level C protection equipment These VOC vapors appeared to dissipate rapidly as no elevated
readings were recorded at the downward perimeter of the exclusion zone
Based on the baseline and periodic air monitoring performed during the investigation undisturbed
ambient air quality in the vicinity of the Site does not appear to have been impacted by former
disposal practices at the Site To confirm this compound specific air monitoring was performed
during the Phase IB investigation
As part of the Phase IB investigation quantitative air monitoring was performed in the vicinity of
the Former Primary Disposal Area The following compounds were detected in shallow soil
during the Phase 1A investigation and therefore were the target analytes for the air monitoring
performed during the Phase IB investigation toluene ethyl benzene total xylenes
tetrachloroethene and PCBs Data from the Phase IB investigation indicate that none of these
compounds were present at any of the air sampling locations for the duration (approximately eight
hours) of the sampling event The laboratory results of these analyses are presented in Appendix
T
45 Potential Sensitive Human Receptors The survey was used to identify any water supply wells schools nursing homes and day care
facilities including in-home day cares within a one-mile radius of the Site
Water Supplies
There are three community water companies serving portions of the Plainfield area within a one-
mile radius of the Site the Gallup Water Company Brookside Water Company and Glen Acres
Water Company The Gallup Water Company operates two wells located in downtown
Plainfield approximately 4000 feet north of the Site The Gallup Water Company presently
services approximately 700 households and three schools (Plainfield Middle School Plainfield
5797wpdocsgalluprifinaltextmlaquoraquoterriltinl061297 4-35 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Central and St Johns) The Brookside Water Company operates two wells located east of 1-395
on the corner of Dow Road and Colonial Road approximately 4000 feet northeast of the Site
The Brookside Water Company presently services approximately 225 homes The water service
lines for the Gallup and Brookside Water Companies are interconnected allowing mixing of the
waters The Glen Acres Water Company has two wells located approximately 2200 feet west of
the Site and services approximately 36 homes The majority of the area west south and east of
the Site and some properties north of the Site rely on individual private wells for their water
supply
One school is located within a one-mile radius of the Site This is the St John Building located
approximately 5200 feet north of the Site This school served students in grades Kindergarten
through eighth grade until 1995 after which the school operates only as a pre-school This
facility is serviced by the Gallup Water Company
Nursing Homes and Elderly Housing
One nursing home and one elderly housing facility are located within one mile of the Site The
Villa Maria Convalescent Home is located approximately 5000 feet north of the Site and is
served by the Gallup Water Company Lawton House Elderly Housing Apartments is located
approximately 4800 feet north of the Site and is also served by the Gallup Water Company
Day Care Facilities
There are eight in-home child day care facilities within a one-mile radius of the Site The
operators and locations are listed on Table 4-70 Only one of these facilities is serviced by a
private supply well That facility located at 134 Lathrop Road is located approximately 3500
feet southeast (upgradient) of the Site
5797wpdoc8galluprifinaltextmasterrifnl061297 4-36 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
50 Contaminant Fate and Transport
This section discusses the environmental fate and transport parameters associated with the
compounds detected during the Remedial Investigation Section 51 details the theoretical basis
for the evaluation of fate and transport characteristics In Section 52 Site-specific fate and
transport parameter values are presented and VOC migration rates and concentration variations
are discussed
51 Theory Migration persistence and relative distribution of compounds between air water and soil depend
on both hydrogeologic and compound-specific parameters The following discussion addresses
each of these parameters as they may affect behavior of compounds within the Study Area
511 Advection by Groundwater Flow
Within a porous medium (soil) the advection rate of dissolved or aqueous-phase compounds
under transient conditions is based on Darcys law (Bear 1979)
where
v= average pore velocity (lengthtime)
K= hydraulic conductivity (lengthtime)
i= hydraulic gradient (lengthlength or dimensionless) which equals
the piezometric head difference between two points on a
groundwater pathline divided by the distance between the two
points
n= effective or drainable porosity (volume of voidstotal soil volume)
of the soil approximately equal to the specific yield
Rj= retardation factor (R gt_ 1) a dimensionless parameter that
represents the ratio of groundwater pore velocity to the actual
advection rate in a sorbing (onto immobile soil grains) porous
medium under transient concentration conditions
5797wpdoc8glaquolluprifinaltextmasterriftil061297 5-1 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
5111 Sorption
The retardation factor Rj represents the attenuation of a plumes frontal advancement due to
sorption ie temporary storage on soil grains Examples of analyses for which retardation
must be considered include (1) calculation of the time required for contamination to reach a given
downgradient location and (2) determination of the time required to remediate a contaminated
aquifer The retardation factor is defined by the following relationship (Freeze and Cherry
1979)
where pb is the bulk dry density of the soil (massvolume) n is the effective porosity of the soil
(volume of voidstotal soil volume) and K^ is the soil-water partition coefficient (volumemass)
often referred to as the distribution coefficient
The soil-water partition coefficient is the relative magnitude of the chemical concentration on solid
particles and in pore water for a particular soil (Lyman et al 1982)
C = AT C
where
C = concentration of the compound sorbed to the solid phase of the soil (mass
chemicalbulk dry mass soil) and
Q = concentration of the compound in the pore water of the soil (massvolume)
In this expression it is implicitly assumed that an equilibrium exists between the solid and water
phases and that the sorption process is linear (Freundlich isotherm with exponent equal to unity)
over the range of concentrations considered
For non-ionic organic compounds such as VOC Kj can be estimated from the measured fraction
of organic carbon naturally occurring in the soil fx (grams organic carbongram dry soil) and
the organic carbon sorption coefficient K^ (Tinsley 1979) as long as f^ gt_ 0001
5797wpdocsgalluprifinaltextmasterrifnl061297 5-2 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
Values of K for many common organic compounds are available in the literature K is also
related to the octanol-water partition coefficient K^ for which a large data base is also available
(eg Hansch and Leo 1979) For fine-grained soil particles K and K^ can be related as
follows (Karickhoff et al 1979)
Kx = 063
Chemical-specific relationships between K and K^ also exist for several VOC (eg Lyman et
al 1982) K values for VOC in the Study Area are presented in Table 5-1
5112 Transport by Dissolved Organic Carbon
For certain families of organic compounds the presence of dissolved organic carbon (DOC) in
groundwater can partially reverse the sorption process to soil particles and release sorbed
constituents to groundwater As a result the migration of these compounds under certain
circumstances can be enhanced (Enfield and Bengtsson 1988) Increases in mobility are greatest
for very hydrophobic (high K) compounds such as pesticides polycyclic aromatic hydrocarbons
(PAH) and dioxins Due to their characteristically low K^s VOC transport in groundwater is
generally unaffected by partitioning to DOC unless DOC concentrations exceed 10000 mgL
(Enfield and Bengtsson 1988) Typically natural DOC concentrations in groundwater range
from 1 to 10 mgL
512 Dispersion
Dispersion is a dilution process by which an initial volume of aqueous solution continually mixes
with increasing portions of the flow system Dispersion occurs on a small or microscopic scale
due to molecular diffusion in the water phase nonuniform velocity distributions within the pore
space and to a large degree the tortuous pathlines that groundwater follows during movement
through interconnected soil pores of different sizes and shapes On a macroscopic scale
dispersion results from geologic heterogeneities such as layers and lenses of contrasting soil type
(ie hydraulic conductivity) In practice dispersion is primarily due to variations in hydraulic
conductivity which produce large gradients in advective transport It is well known that aquifers
contain horizontal layers or lenses of coarser and finer grained materials compared to the average
material type that can result in zones of significantly higher and lower hydraulic conductivity
respectively than the screen interval value determined from pumping and slug tests Factor of
ten hydraulic conductivity variations or more over the thickness of an aquifer are not uncommon
5797wpdocsgalluprifinaltextmasterrifhl061297 5-3 QST Environmental
Gallups Quarry Superand Project - Remedial Investigation
(Freyberg 1986 Gelhar et al 1985 Robertson et al 1991 and Sudicky et al 1983) For
contaminant transport the more permeable zones are more important because they determine the
maximum distance over which dissolved constituents will migrate from the source area
With respect to chemical migration from a source area to an arbitrary downgradient location
dispersion will cause contaminants to arrive in a shorter time interval than the travel time based
on the mean groundwater pore velocity (Section 511) This reduced travel time associated with
dispersion is due to advection in the zones of higher hydraulic conductivity that cause the
concentration distribution in the longitudinal (flow) direction to spread out or disperse The
additional length Ld that a chemical may migrate due to dispersion can be estimated from the
following relationship (Bear 1979)
where
t = total time of groundwater travel (= VL^ laquo
Rj = retardation factor
DL = longitudinal dispersion coefficient (length 2time)
In a porous medium the longitudinal dispersion coefficient can be estimated as follows
DL =
where
v = groundwater pore velocity
aL = longitudinal dispersivity of the aquifer (length)
The percent reduction in travel time along a pathline due to longitudinal dispersion can be
calculated using the equation (Bear 1979)
where
At = reduction in travel time along a pathline due to longitudinal dispersion ()
5797wpdocsgalluprifinaltextmasterrifhl061297 5-4 QST Environmental
Gallups Quarry Superfond Project - Remedial Investigation
A t = mdash- 100 ^total
Ld = additional distance (in excess of advection distance) that chemical migrates due to
longitudinal dispersion
= total distance of travel by mean advection (average groundwater flow rate)
An excellent summary of estimated longitudinal dispersivity values for numerous sites is given by
Gelhar et al (1985)
513 Advection Due to Fluid Density Differences
Advective transport can also occur due to fluid density differences in cases where the total
dissolved solids (TDS) concentration is very high A typical example is salinity intrusion into an
aquifer where the greater density of the salt water (TDS 35000000 ppb) causes it to sink within
the fresh water aquifer This causes downward advection of groundwater and results in
stratification of the aquifer into varying zones of salinity However density effects can be caused
by any dissolved compound if the concentration is high enough Laboratory experiments have
shown that density effects do not begin to be observed until the total dissolved concentration in a
plume exceeds background levels by about 1000000 to 5000000 ppb (Schincariol and
Schwartz 1990 Schwille 1988) As a result fluid density effects are not important in the Study
Area
514 Biological and Chemical Degradation
In recent years groundwater scientists have begun to understand the role of microorganisms in
the subsurface transformation of organic chemicals Recent studies have shown that large numbers of organisms can exist in the subsurface environment In many cases organic compounds can be completely degraded to harmless products However by-products can also be
produced which are more mobile and toxic than the parent compound These transformations can
make it difficult to correlate groundwater contamination with particular sources Quantitative
predictions of the fate of biologically reactive chemicals are approximate at best This is due to a
lack of understanding of the biochemical transformation process and variability of transformation
rates in an aquifer (eg as much as two orders of magnitude over a distance of less than 1 m)
For example Wood et al (1980) have demonstrated in the laboratory and observed in the field
the following anaerobic transformations of parent compounds to daughter products
5797wpdoc8galluprifinaltextmasterriftJ061297 5-5 QST Environmental
Gallups Quarry Superfiind Project - Remedial Investigation
carbon tetrachloride -bull chloroform -raquo methylene chloride
trans-12-d ichloroethene
PCE -bull TCE - cis-l2-dichloroethene - vinyl chloride
11-dichloroethene
111-trichIoroethane -raquo 11-dichloroethane - chloroethane
The transformation of PCE (tetrachloroethene) and TCE (trichloroethene) to vinyl chloride is an
example of a transformation to a daughter compound which is considerably more toxic than its
parent compound
Persistence in the environment can be described by a parameter known as the environmental
half-life of a compound The environmental half-life tQ is related to a decay constant X
(Itime) in a first-order decay process
X = ln(2)tm
where ln(2) = 0693 The product of the decay constant and the porewater concentration is equal
to the rate (masstimeunit volume) at which a compound degrades into another form of
compound In practice the parameter half-life is an empirical parameter that quantifies mass loss
due to biological photochemical chemical or physical (eg volatilization) degradation
mechanisms
Within the subsurface biological activity is believed to be the principal cause of the
mineralization (ie transformation to inorganic constituents) of organic compounds (Alexander
1978) Hydrolysis is the reaction of compounds with water or the hydroxide or hydromium ions
associated with water However organic functional groups such as halogenated organics (eg
TCE TCA PCE) ketones benzenes and phenols are generally resistant to this mechanism
(Lyman et al 1982) Oxidation (loss of electrons during a chemical reaction ) and reduction
(gain of electrons during a chemical reaction) can also alter and attenuate organic compounds
For most inorganic compounds geochemical transformations are the most important degradation
mechanisms Due to the complexity of degradation processes and the fact that little data is
typically available to adequately model the loss mechanisms prediction of decay rates in the field
as discussed above is very difficult and not often feasible especially for biodegradation
5797wpdocsgalluprifinaltextmasterrifnl061297 5-6 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
515 Volatilization
The Henrys law coefficient H (Morel 1983) is an air-water partition coefficient which relates
the equilibrium concentrations in air and water for volatile compounds in a multi-phase system
such as the unsaturated zone of the subsurface or the air-water interface of a water body
H = C 1C
where C and eurobdquo are the chemical concentrations in air and water respectively The coefficient is
used in the calculation of volatilization from a water body or soil and for the determination of
solids water and air concentrations resulting from chemical partitioning in a contaminated
unsaturated soil
Organic compounds with Henrys law coefficients greater than 103 atm-m3mole are generally
considered to be highly volatile These compounds can volatilize relatively rapidly from water at
air-water interfaces such as surface water bodies or groundwater tables However the rate of
volatilization is also controlled by diffusion in the water phase Table 5-1 summarizes values of
the Henrys law coefficient for selected organic constituents detected in the Study Area
516 Aqueous Solubility
The solubility of a compound in water is the maximum amount of that compound that will
dissolve in a unit volume of pure water at a specified temperature Water solubility is one of the
most important fate and transport parameters Highly soluble compounds tend to have relatively
low KK values and Henrys law coefficients and tend to be more readily biodegradable by
microorganisms in soil Table 5-1 lists solubilities for VOC detected in the Study Area
52 Study Area-Specific Characteristics 521 Retardation Factors
A Site-specific evaluation of chemical migration rates in groundwater was conducted by
measuring the total organic carbon content TOC of 31 soil samples from the northern Study
Area (Table 5-2) The parameter f (Section 51) is equal to TOC expressed as a fraction As
discussed in Sections 26 and 2721 an ASTM method was used to measure the 4 of the 28
samples from the Former Primary Disposal Area (SB-series borings) EPA Method 9060 was
used to analyze the three samples from the boring for well MW102B The fK measurements for
the SB-series soils samples range from less than 00015 to a maximum of 0023 and the
geometric mean is 00023 In these calculations values below the detection limit of 00015 were
assigned one-half the detection limit These f^ values are typical of high hydraulic conductivity
sand and gravel aquifers
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 5-7 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
The measured values for the three MW102B samples are uncharacteristically low for coarse
stratified drift The geometric mean of these samples is 0000014 which is a factor of 100 lower
than the SB-series data The discrepancy appears to be due to the fact that EPA Method 9060 is
designed for TOC analysis of water samples The f values for the three MW102B samples are
expected to be on the order of 0001 based on comparisons with organic carbon values for
samples of a similar lithology from the Gallups Quarry and other sites Furthermore as
discussed by Karickhoff et al (1979) the available correlations that relate f^ to retardation factor
Ra are not valid below f = 0001 Below values of f = 0001 mechanisms other than
sorption to organic carbon (eg chemical adsorption to mineral surfaces) begin to dominate with
the result that overall sorption and retardation of VOC do not decrease even though the TOC
content of the aquifer materials does Therefore if f^ lt 0001 researchers have indicated that
in many cases calculations of Rd can use f^ = 0001 to account for these alternative sorption
mechanisms For these reasons the SB-series f^ data that are representative of coarse stratified
drift were used in the transport evaluations discussed in the following sections
The average f^ for the SB-series soil samples located below the water table were also calculated
to evaluate vertical trends in the data These samples include
Sample Depth (feet bgs) TOC (mgkg)
SB 104 15-17 lt1500
SB104 26-28 1700
SB108 6-8 lt1500
SB 109 4-8 1600
SB109 10-16 lt1500
SB109 17-24 1500
SB109 24-32 1600
The geometric average f for these samples is 00012 if one-half the detection limit is used for f
lt 00015 Because this average excludes shallow samples with larger silt contents it is
considered more representative of the higher hydraulic conductivity coarse-grained soils which
primarily control groundwater transport
Table 5-1 summarizes chemical-specific retardation factors for VOC detected in Study Area
groundwater These estimates are based on a f value of 00012 which as discussed above is
near the minimum value appropriate for the calculation of R Actual retardation factors in the
aquifer will be nonuniform due to the inherent variability of soil organic carbon content For
example retardation factors based on an f of 00012 may be more appropriate for evaluation of
5797wpdocsgalluprifinaltextmasterri fal061297 5-8 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
transport rates in the middle to lower portions of the aquifer where the soil is generally coarser
and contains less silt which is associated with the organic carbon content Conversely the
average value of 00023 for all samples is likely more representative of soils in the upper portion
of the aquifer and above the water table In any case this overall variability in f^ values for the
aquifer is considered to be smaller in magnitude than the natural variability in hydraulic
conductivity values for the site The recent detailed field investigations in sand and gravel
aquifers referenced in Section 512 have shown that it is not uncommon for hydraulic
conductivities to vary by as much as a factor of ten over a scale of a few feet Variations in both
f and hydraulic conductivity values impact predicted chemical transport rates (Section 511)
A bulk dry density of 18 gcm3 and an effective porosity of 025 were estimated from the
literature based on soil grain size analyses Potential variability associated with these parameters
is small compared to k^ estimates and is not important for the following transport rate evaluation
The results in Table 5-1 are useful for comparing relative mobilities for different compounds and
assessing contaminant migration rates relative to groundwater pore velocities 11-dichloroethane
is expected to be the most mobile VOC while PCE and ethyl benzene should be the least mobile
The tracer compounds TCA and DCE are expected to migrate about a factor of two slower than
the groundwater with DCE migration being the fastest
522 Chemical Migration Rates
5221 Groundwater Travel Times
Compound-specific migration rates in the overburden aquifer were examined using Darcys law
(Section 511) to compute groundwater pore velocities from (1) measured horizontal hydraulic
gradients defined by the November 1995 piezometric surface maps (Section 332) (2) the
hydraulic conductivity data (Table 3-1) and (3) estimated retardation factors (Table 5-1) The first step was to construct a map of groundwater times-of-travel along the various pathlines shown
on the groundwater flow maps for the southern Study Area (Plate 3-9) and for the lower portion
of the aquifer in the northern Study Area (Plate 3-8) Groundwater travel times along each of the
pathlines were modelled using the Tecplot software and the interpolated piezometric head
distribution to define the continuous horizontal hydraulic gradient distribution Additional
information regarding pathline computation using Tecplot is provided in Appendix Q Since the
more permeable zones in an aquifer are known to control the rate of advancement of a plumes
leading edge (Section 512) the upper bound hydraulic conductivity estimates from Table 3-1
were considered From a review of these measurements it was determined that a mean hydraulic
conductivity of 004 centimeters per second (115 feet per day) would be reasonable to use in the
time-of-travel computations in the northern Study Area because this value is representative of the
more permeable coarse-grained soils north and northwest of the Former Primary Disposal Area
(ie wells MW102TT MW103TT MW104TT MW117TT and MW118TT) A lower
5797wpdoc8galluprifinaltextmlaquosterrifhl061297 5-9 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
hydraulic conductivity of 00025 cms (7 ftday) representing the geometric mean value for wells
MW114TT and MW115TT was selected for the southern Study Area An effective porosity of
025 was used in the calculations
The travel-time analysis results are shown in Plate 5-1 Markers denoting half-year (northern
Study Area) and five-year (southern Study Area) travel-time intervals have been placed on each of
the pathlines to allow evaluation of spatial variations in groundwater pore velocity and
determination of total groundwater travel-time between different locations The time period
required for a particular VOC to migrate along a pathline can be estimated as the product of the
groundwater travel-time and the compound-specific retardation factor listed in Table 5-1
5222 Groundwater Flushing Rates
Another useful relationship to consider when evaluating chemical migration is the time period
required to reduce the concentration in a specific portion of an aquifer by groundwater flushing
Assuming that source material is no longer introducing contamination into the portion of the
aquifer (ie control volume) being evaluated the US EPA Batch Flushing Model (EPA 1988)
provides such a relationship
p v = J V h )
where In is the natural logarithm to the base e Rd is the retardation factor C0 is the initial or
starting average groundwater concentration in the control volume Q is the final average
concentration and Pv is the number of groundwater pore volumes which have flowed through the
control volume Pv can be estimated as
P =-raquo v Ltotal
where v is the groundwater pore velocity (Section 511) t is the time duration being considered
and L^ is the total distance or length along a characteristic pathline (from upgradient to
downgradient) through the volume of aquifer material The model assumes complete mixing of
contaminants (ie infinite dispersion) within the control volume Brusseau (1996) demonstrated
that in part due to this assumption the Batch Flushing Model can partially account for
nonequilibrium desorption (ie delayed release) of VOC from soil
5797wpdocsgalluprifinaltextmlaquosterrifhl061297 5-10 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
For example the southern Study Area (area south of the Former Seepage Bed) can be considered a control volume with a characteristic groundwater flushing rate In this area a time t of order 10 years is required for groundwater to flow through a distance L^ of about 400 feet thus indicating an average pore velocity v of about 40 feet per year In other words one pore volume of groundwater flushes through the overburden deposits in the southern Study Area in approximately 10 years From the Batch Flushing Model it can be seen that for a nonsorbing compound with R = 1 23 pore volumes [ln(10)] would need to flush through this area to lower average concentrations by a factor of ten assuming no source material remained east of the southern Study Area or above the water table 46 pore volumes would be needed for a factor of 100 reduction Since each pore volume roughly corresponds to 10 years the factors of 10 and 100 concentration reductions would require time periods of about 23 and 46 years respectively If however one were considering a compound with R = 3 the corresponding times would be about 70 and 140 years
5223 Discussion In the northern Study Area three areas of characteristically different horizontal hydraulic gradients exist in the overburden aquifer The steepest gradients (on the order of 0025 feet per foot) are found south of the former disposal areas Assuming the hydraulic conductivity in this area is 004 cmsec Plate 5-1 shows that the groundwater travel time through this portion of the aquifer is expected to be much less than one year However hydraulic conductivity data and soil descriptions suggest that a more representative hydraulic conductivity value for the till deposits in this area would be 0001 cmsec or less which would correspond to a travel time of five years or more (eg from MW109 to the Former Primary Disposal Area)
Northeast of well MW116 north of Mill Brook and in the vicinity of the former Pervel flock plant the hydraulic gradient is about 0007 feet per foot and a hydraulic conductivity of 004 cmsec is representative of the aquifer As a result the largest groundwater pore velocities are expected to exist in these areas For example as shown in Plate 5-1 the expected groundwater travel time is about one to two years from the vicinity of Pervel to MW116 and from Pervel to MW101
Groundwater travel times downgradient from the Former Primary Disposal Area are much longer due to the low hydraulic gradients northwest of the railroad tracks In the vicinity of MW105 and MW102 the gradient is about 00003 feet per foot or more than a factor of 20 less than the gradient northeast of this area For example the estimated groundwater travel time (ignoring longitudinal dispersion) from MW107 to MW102 near the front of the VOC plume is about 8 to
10 years By comparison almost 20 years has passed since the documented disposal in the late 1970s Based on the retardation factors (Table 5-1) for TCA (R = 23) and DCE (R = 14)
5797wpdocsgalluprifinaltextmasterrifhl061297 5-11 QS7 Environmental
Gallups Quarry Superand Project - Remedial Investigation
the estimated travel times for these compounds from MW107 to MW102 are about 20 years and
13 years respectively Considering these chemical migration rates and the fact that TCA and
DCE were detected at quantifiable levels along the VOC plume centerline and at location
MW102 it appears reasonable to conclude that these compounds are associated with the former
disposal areas
However as discussed in Section 4221 the present PCE distribution in groundwater exhibits
inconsistencies with migration from the former disposal areas Although historical detections of
PCE were found in well cluster SW17 which is located downgradient from the Former Primary
Disposal Area and near well cluster MW105 the concentrations had reduced from a maximum of
1000 ppb in 1980 to near the detection limit by early 1993 (Section 523) Based on this rate of
reduction PCE concentrations at diis location would be expected to have fallen below or near the
detection limit by 1995 In fact only trace levels were detected in wells MW105TT and
MW105T during two of the four 1995 sampling events Furthermore the measured groundwater
flow directions in the overburden aquifer indicate that many of the pathlines originating near the
former Pervel flock plant pass through the vicinity of wells MW117 MW118 MW119 MW116
MW103 MW102 and MW101 Although MW101 and MW102 are downgradient from both
Pervel and the former disposal areas groundwater flow conditions in the past would need to have
been different from present conditions for MW116 and MW103 to be downgradient from the
former disposal areas As discussed in Section 4 elevated levels of PCE TCA and DCE have
been detected in monitoring wells located on the former Pervel property Also PCE TCA and
DCE were detected in wells MW116T MW118TT and MW103TT located downgradient from
Pervel during the 1995 sampling rounds and PCE TCE and DCE were detected in well MW-C
on the former Pervel property The travel time of these compounds from Pervel to wells
MW116 MW118 MW103 MW102 and MW101 is estimated to be two to six years Taking
this into consideration along with the VOC detections in the Pervel wells during the period 1987
to 1989 (Section 523) it is possible that the low-level PCE TCA and DCE detections in
MW116T MW118TT and MW103TT represent the last remaining portion of a Pervel VOC
plume The lack of VOC detections in wells MW117 and MW119 could be explained by dilution
in these areas or by the fact that these wells may not be immediately downgradient from the
historical source area(s) on the former Pervel property
The migration rate of PCE compared to the disposal area tracer compounds TCA and DCE also
supports the existence of an off-site PCE source The expected migration rate of PCE is a factor
of two to four slower than that of TCA and DCE due to their differing K values Assuming all
of these VOC were released within a few years of each other the leading edges of the TCA and
DCE plumes should be much farther downgradient than the PCE plume Instead as evidenced by
the data shown in Plate 4-6 the opposite is true because a PCE concentration of about 30 ppb has
5797wpdocsgalluprifinaltextmasterrifnl061297 5-12 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
been detected at MW101 In terms of groundwater migration (not including retardation) from the
Former Primary Disposal Area the elevated PCE concentrations at location MW101 would
represent a total travel-time from the former disposal areas which is more than a factor of two
greater than that required for the leading edge of the TCA-DCE plume to reach MW102
Comparing the relative mobilities of PCE TCA and DCE (Table 5-1) the time required for PCE
to migrate from the Former Primary Disposal Area to well MW101 should be more than a factor
of four to eight longer than the TCADCE travel time to MW102 Based on this comparison the
PCE detections at MW101 could be attributed to transport from Pervel It is also possible that
the Pervel groundwater contamination has impacted the MW102 area Although the PCE
detections at locations MW102 and MW101 could be attributable to historical releases from the
former disposal areas the above findings (flow directions spatial PCE distribution travel times)
suggest that contamination from the former Pervel facility has at a minimum contributed to VOC
contamination (PCE and possibly DCE and TCA) at these locations
The above discussion also highlights the important issue of what defines the leading edge of the
zone of VOC contamination in the overburden aquifer Several of the above findings suggest that
the downgradient extent of VOC contamination associated with the former disposal areas is
located near wells MW102 and MW101 The convergent nature of the groundwater flow patterns
in the northern Study Area clearly establish a narrow well-defined preferred pathway of low-level
contaminant migration from the Former Primary Disposal Area The chemical analysis results
from the monitoring well sampling program confirm the measured flow directions Further
whereas TCA and DCE can presently be traced continuously along the plume centerline at
elevated levels (well locations MW107 MW105 and MW102) PCE cannot These findings
suggest that the PCE contamination in groundwater may be attributable to the former Pervel flock
plant and should not be used solely to define the leading edge of the VOC plume The time-ofshy
travel computations support the location of the disposal area VOC plume between MW102 and
MW101 The reduction of TCA and DCE concentrations to less than 10 ppb and the decrease of
xylene to below detection at MW101 is also consistent with the interpretation that the disposal
area VOC plume does not extend far beyond MW102 In addition the groundwater pore velocity
in the vicinity of wells MW102 and MW101 is estimated to be about 50 feet per year which is as
much as a factor of 20 lower than rates upgradient from this area Based on this pore velocity
and the retardation factors in Table 5-1 the migration rates of TCA and PCE are expected to be
about 20 and 10 feetyear respectively At these rates the estimated travel times for TCA and
PCE from MW102 to MW101 are about 20 and 35 years respectively As discussed in the
following section given the relatively large rates of historical VOC concentration reductions
which have been observed in the northern Study Area it is expected that PCE 12-DCE 11shy
DCE and TCE levels near MW102 will fall below MCLs within the above 20- to 35-year period
due to biodegradation and dilution mechanisms Reduction rates for vinyl chloride which also
5797wpdocsgalluprifinaltextmlaquoraquoterrifhl061297 5-13 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
has been detected above MCLs near MW102 will likely lag behind the other VOC because it is a
final chlorinated breakdown product
523 Time-Dependent Concentration Reductions
5231 Observed Concentration Changes
Significant groundwater concentration reductions with time have been observed in the northern
Study Area from the late 1970s through the 1995 sampling rounds To illustrate these temporal
trends concentration data for selected VOC were plotted versus time to quantitatively evaluate the
reduction rates The observed rates of concentration reduction are also compared to predicted
values using the groundwater flushing relationships presented in Section 5222 and are evaluated
to determine site-specific estimates of biodegradation rates
Figures 5-1 through 5-3 contain the concentration vs time graphs for three groups of wells
organized according to transport characteristics and location Group 1 (Figure 5-1) immediately
downgradient from the former disposal areas (SW17S SW17D SW13 MW107TT MW105S
and MW105TT) Group 2 (Figure 5-2) within the downgradient portion of the VOC plume
(MW102S MW102TT MW101TT) and Group 3 (Figure 5-3) the area northeast of the VOC
plume and downgradient from the former Pervel flock plant Data from the Group 1 wells
provide a good historical perspective on improvements in groundwater quality resulting from
source removal activities in the late 1970s and from ongoing biodegradation and rainwater
infiltration (flushing) within the Former Primary Disposal Area The Group 2 wells are located
within the downgradient portion of the VOC plume and in a section of the aquifer where the
hydraulic gradient and associated groundwater transport rates are up to a factor of 20 lower than
in other parts of the northern Study Area Group 3 wells are downgradient from the former
Pervel facility where elevated levels of PCE and TCA have been detected and are located in the
portion of the aquifer with the highest groundwater flushing rates
5232 Evaluation of Concentration Reduction Rates and Mechanisms
The most important aspect of the semilogarithmic plots in Figures 5-1 to 5-3 is the characteristic
slope or trend of the concentrations as a function of time Specifically it can be seen that many
of the graphs exhibit an almost straight-line decrease in concentration with time This linear
variation is often observed with historical groundwater quality data because the linearity has a
physical basis First many biodegradation mechanisms can be modelled as a first-order decay
process (Section 51) which produces a straight-line decrease in concentrations on a semi-log plot
Second flushing of clean groundwater (eg rainwater infiltration or uncontaminated
groundwater) through a contaminated volume of aquifer material has been shown (Section
5222 Brusseau (1996)) to exhibit the same type of response In both of these approximate
first-order processes the slope of the straight-line response is inversely proportional to the
5797wpdocsgalluprifinaltextmasterrifhl061297 5-14 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
environmental half-life (Section 514) for that mechanism and a particular chemical compound
Using the relationships developed in Section 5222 the environmental half-life associated with
groundwater flushing can be defined as
Substituting the expression for pore volume Pv the flushing half-life can also be written
From the above expression it can be seen that the flushing half-life for a particular compound is
directly proportional to the chemical retardation factor and inversely proportional to the
groundwater pore velocity The groundwater flushing rate represents the rate at which
concentrations in a particular portion of the aquifer are reduced In contrast to biodegradation
groundwater flushing does not reduce the total mass of a compound in the aquifer because the
contaminants are advected to downgradient areas
In the Group 1 area historical VOC data for the SW-series wells (Metcalf amp Eddy 1993) (eg SW13 and SW17) summarized in Table 5-3 and on Figure 5-1 show that TCA TCE and PCE
levels in groundwater downgradient from the Former Primary Disposal Area have typically
decreased by a factor of more than 100 from the late 1970s to 1993 Using the SW17S data
from 1980 to 1993 the estimated environmental half-lifes for TCA TCE and PCE are
approximately 15 20 and 24 years respectively From February 1993 through the present the
shallow concentration reduction rates (SW17S and MW105S) are much higher corresponding to TCA TCE PCE and DCE environmental half-lives of about 03 lt 1 03 and 04 years
respectively Concentration reduction rates in the lower portion of the aquifer (SW17D and
MW105TT) from February 1993 through the end of 1995 are a factor of two to three slower than
shallow rates the estimated environmental half-lifes for TCA PCE and DCE in the deep aquifer are about 06 09 and 09 years respectively The higher concentration reduction rates in the
shallow aquifer may be due to rainwater infiltration andor increased biodegradation These
decreases in VOC levels are likely due to a combination of (1) source removal and source
depletion (ie soil concentration reduction by flushing mechanisms) within the former waste
disposal areas (2) mixing of rainwater infiltration with groundwater which can be a significant
dilution mechanism in the wetland areas as evidenced by the frequent occurrence of ponded water
and (3) biodegradation by microorganisms in soil
5797wpdoc8galluprifiiialtextmlaquoraquoterrifhl061297 5-15 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Vinyl chloride does not follow the same trends of reducing concentrations exhibited by the other
chlorinated VOC Vinyl chloride concentrations in wells MW107TT and MW105TT generally
increased during the 1995 sampling rounds Since this compound is the final chlorinated
breakdown product of PCE TCE and DCE it appears that the vinyl chloride detections are the
result of biodegradation The apparent increase in vinyl chloride concentrations and decrease in
DCE levels in well MW107TT may be further evidence that vinyl chloride detections are
associated with biodegradation mechanisms
The observed Group 1 environmental half-lifes are consistent with predicted half-lifes due to
groundwater flushing From Plate 5-1 the estimated groundwater travel time from MW107 to
MW105 is 05 to 1 year which corresponds to 1 to 2 groundwater pore volumes per year
flushing through the Group 1 Area Using the retardation factors in Table 5-1 the predicted
flushing half-lifes for DCE TCA and TCE range from 05-10 08-16 and 07-14 years
respectively and the flushing half-life for PCE is between 14 and 3 years This good agreement
between observed and predicted rates of concentration reduction downgradient from the former
disposal areas is additional evidence that source removal activities were successful and natural
mechanisms are actively producing further reductions in contaminant levels The fact that deep-
aquifer PCE and TCA concentrations near MW105 have decreased more rapidly than predicted
groundwater flushing rates during the period 1993 to 1995 suggests that biodegradation is
breaking down these parent compounds Furthermore TCA TCE and PCE reduction rates
before 1993 were much slower and are similar in magnitude to flushing rates This indicates that
biodegradation before 1993 was less important Assuming this is the case the estimated
biodegradation half-lifes for PCE and TCA for the period 1993 to 1995 range from 13-25 and
10-24 years respectively near the Former Primary Disposal Area In contrast observed
reduction rates for TCE and DCE are slower than predicted flushing rates which may be
evidence that breakdown of their respective parent compounds was significant during the period
1993 to 1995 Indeed this interpretation is consistent with the observed biodegradation of PCE
In the Group 2 area (Figure 5-2) VOC levels (with the exception of DCE) at well cluster
MW102 appear to increase in 1995 while concentrations at cluster MW101 remained relatively
constant The concentration increase at MW102 may be due to the fact that this cluster is near
the leading edge of the VOC plume and groundwater flushing rates in this area are relatively low
However as discussed in Section 522 the increased PCE and TCA levels along with daughter
products such as TCE DCE vinyl chloride and DCA may be associated with transport of the
PCE and TCA plumes on the former Pervel property
The most interesting of the Group 3 wells are wells MW-A -B and -C located on the former
Pervel property As shown on Figure 5-3 PCE and TCA concentrations in wells MW-A and
5797wpdoc8galluprifinaltextmasterrifhl061297 5-16 QampT Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW-B reduced to below detection limits by 1990 These rates of reduction correspond to halfshy
lifes of about 02 years for TCA and 03 years for PCE By comparison based on travel time
estimates from Plate 5-1 predicted groundwater flushing half-lifes for TCA and PCE
concentration reduction near Pervel are about 08 and 14 years respectively Assuming the
differences between observed concentration reduction rates and rates predicted by groundwater
flushing alone are due to biodegradation the biodegradation half-lifes for TCA and PCE are 03
and 04 years respectively In well MW-C TCA levels have reduced at a rate consistent with a
02-year half-life while the PCE half-life is approximately 05 years The corresponding
estimated biodegradation half-lifes for TCA and PCE at MW-C are 03 and 08 years
respectively Therefore biodegradation appears to be the major cause of the observed TCA and
PCE concentration reductions in the Pervel wells The lack of PCE or TCA detections in well
clusters MW119 and MW117 during the November 1995 sampling round are also consistent with
the rates of reduction in the Pervel wells For example the estimated travel times of PCE and
TCA from Pervel to the MW119 and MW117 wells are on the order of 4 and 2 years
respectively Since PCE and TCA levels in wells MW-A and MW-B were below detection by the
beginning of 1990 this groundwater with no detectable levels of either compound would be
expected to have passed through the MW119 and MW117 wells by the beginning of 1994 (PCE)
or 1992 (TCA)
In contrast the groundwater travel time from Pervel to wells MW116 MW103 and MW118 is
estimated to be up to one year longer than the travel time to MW119 and MW117 This would
correspond to increased travel times for PCE and TCA of about 4 and 25 years respectively
Based on these estimates low but detectable levels of PCE and TCA would be expected in wells
MW116 MW103 and MW118 during 1995 groundwater sampling In fact PCE TCA and
DCE were detected at each of these locations in 1995 at trace levels Slightly higher
concentrations of PCE and TCA were detected in MW116T during January 1995 but trace levels
were detected during each of the three subsequent 1995 rounds Further these rates of PCE and
TCA migration from Pervel would be consistent with the detections in well clusters MW102 and
MW101
Additional estimates of biodegradation rates were made by evaluating concentration reductions
within the parcel of groundwater located near well SW17 in 1980 Using the travel times shown
in Plate 5-1 it is estimated that about five years would be required for groundwater to travel from
SW17 to MW102 The corresponding chemical migration rates for TCA TCE and PCE are 12
11 and 20 years respectively Due to longitudinal dispersion (Section 512) the actual travel
times would be somewhat less Therefore groundwater presently in the MW102 area is expected
to be representative of historical (1980) groundwater contamination from the SW17 area
Neglecting possible contaminant contributions from Pervel most of the VOC concentration
5797wpdocsglaquolluprifinaltextmalaquoteiTifTil061297 5-17 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
reductions occurring in this parcel of groundwater as it traveled from SW17 to MW102 would be
due to biodegradation and rainwater infiltration
Figure 5-4 shows the TCA TCE and PCE concentration data from 1980 and 1982 for SW17S
and from January and November 1995 for wells MW102S and MW102TT The slopes of the
lines connecting the data from these two periods provide estimates of the combined biodegradation
and rainwater dilution rates for these compounds The combined half-lives for these two
mechanisms are 15 years (TCA) 18 years (TCE) and 21 years (PCE) From Bear (1979) the
half-life for rainwater dilution can be estimated as
n - b
where n = effective porosity b = saturated thickness and I = groundwater recharge rate due to
rainwater infiltration Using n = 025 b = 60 feet and I = 30 inchesyear (USGS 1995) the
half-life for dilution due to rainwater infiltration is about 4 years Using this value the estimated
biodegradation rates for TCA TCE and PCE within the VOC plume are 24 33 and 44 years
respectively These estimated biodegradation rates for TCA and PCE are a factor of two to three
less than estimated rates near the Former Primary Disposal Area during the period 1993 to 1995
5233 Summary
From the late 1970s through the four 1995 sampling rounds groundwater concentrations in the
VOC plume downgradient from the Former Primary Disposal Area have decreased at a rapid rate
The groundwater quality data from 1995 indicates that this trend of reducing concentrations is
continuing Based on these concentration reduction rates most VOC levels will fall below their
respective MCLs in a period of less than four years Vinyl chloride is an exception to this trend
because increased levels of this compound were detected in 1995 apparently due to the chemical
break down of its parent compounds PCE TCE and DCE
Analyses of these concentration reductions with time indicate that biodegradation and dilution by
rainwater infiltration are the key mechanisms responsible for these changes with biodegradation
likely the most important component Within the VOC plume biodegradation and rainwater
infiltration are reducing most VOC (with the exception of vinyl chloride) concentrations by about
a factor of two every two years which corresponds to an environmental half-life of two years
5797wpdocsglaquolluprifinaltextmraquosterrifnl061297 5-18 QST Environmental
Gallups Quarry Superjund Project - Remedial Investigation
60 Summary and Conclusions
This section provides the conceptual model developed for the Study Area based on the findings
of the Phase 1A and IB field investigations and the results of the Long-Term Monitoring
Program sampling events
61 Conceptual Model of the Study Area The conceptual model was developed from the collection and analyses of information and data
from the Remedial Investigation (RI) as well as historical information and data A conceptual
model is an overview of the Study Area taking into account all media and their interrelationships
and describes in summary fashion Site conditions as they pertain to contaminant sources and
migration pathways This conceptual model will be used to support the evaluation of potential
remedial alternatives for the Feasibility Study
611 Geology
Geologic data collected during the RI indicate the following
bull Significant surficial or overburden deposits encountered in the Study Area are till
and glacial deposits referred to as stratified drift
bull The till is relatively dense and is comprised of a fine sandy matrix with abundant
gravel cobbles and boulders The till was encountered directly above bedrock at
most locations at thicknesses of 10 to 20 feet with the thickest accumulations
located along the topographic (bedrock) high in the central area of the Site
bull The stratified drift typically overlies the till or bedrock and consists of poorly to
well sorted deposits of gravel sand and silt Grain size analyses indicate that the
stratified drift is primarily comprised of fine to coarse sands with lesser amounts
of silt and fine gravel The stratified drift thickness varies from less than a few
feet in upland areas to as much as 70 feet in the vicinity of Mill Brook
bull Bedrock within the Study Area consists of grey fine- to medium-grained gneiss
with varying contents of amphibolite biotite and hornblende The bedrock
surface is characterized by a large slope and dips to the northwest and west-
southwest from a bedrock high located about 400 feet southeast of the Former
Seepage Bed The total bedrock surface relief in the Study Area approaches 100
feet
5797wpdocsgalluprifinaltejctmasterri fhl061297 6-1 QfT Environmental
Gallups Quarry Superand Project - Remedial Investigation
bull Geophysical investigations (seismic refraction and magnetometer surveys)
conducted in the vicinity of the Former Seepage Bed did not reveal evidence of
one or two suspected discrete bedrock faults Rather the bedrock in the central
portion of the Site may be more accurately characterized as a series of
interconnected (to varying degrees) fractures and faults
^
612 Hydrogeology
Data regarding hydrogeologic conditions are summarized as follows
Hydraulic Conductivity
bull Across the Study Area test results indicate that the hydraulic conductivity
of the shallow overburden deposits averages approximately 0001
centimeters per second (cms) while the mean hydraulic conductivity for
the deep portion of the aquifer is about 0005 cmsec A mean hydraulic
conductivity of about 0037 cms is more representative of coarser-grained
deposits in the middle to lower portions of the overburden aquifer
northwest of the railroad tracks where the saturated thickness increases to
almost 70 feet
bull The mean hydraulic conductivity of the till (000047 cms) is a factor of
ten less than the average for the stratified drift deposits in the lower
portion of the aquifer and varies between 00002 and 0002 cms
Although the hydraulic conductivity of the till indicates that it is less
permeable and hydrogeologically distinct from the overlying stratified drift
deposits the hydraulic conductivity contrast is not large enough to
significantly alter groundwater flow directions or rates
cir
bull The mean bedrock hydraulic conductivity (000018 cms) is a factor of 25
lower than the average for the coarse-grained stratified drift Due to the
heterogeneous nature of fracture sizes and interconnectivity and their
associated nonlinear effect on groundwater flow rates the hydraulic
conductivity of the bedrock can be expected to be highly variable
throughout the Study Area
5797wpdocsgalluprifinaltextmasterrifhl061297 6-2 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
Groundwater Flow
bull The overburden aquifer is the preferred pathway for groundwater transport
of dissolved constituents This conclusion is supported by the hydraulic
conductivity test results and observations that an upward groundwater
flow component from bedrock to overburden exists throughout most of the
Study Area VOC detections in bedrock wells are believed to be caused
by vertical dispersion in the upper portion of the fractured bedrock
bull Because the unconsolidated deposits become unsaturated in the vicinity of
the Former Seepage Bed discussions of groundwater flow in overburden
are naturally divided into northern and southern portions of the Study
Area
bull Overburden groundwater flow south of the Former Seepage Bed is
generally from east to west at an average hydraulic gradient of 001 feet
per foot (vertical change in piezometric head per horizontal distance) and
is strongly influenced by the bedrock surface and drainage to the wetlands
and stream west of the railroad tracks The saturated thickness in this
area increases from zero near the bedrock high (northeast corner) to more
than 60 feet near the railroad tracks
bull Three distinct zones of overburden groundwater flow exist in the northern
Study Area In the area between the Former Primary and Secondary
Disposal Area and the Former Seepage Bed groundwater flow is largely
through till deposits and toward the north-northwest The hydraulic
gradient in this area is steep (about 003 feet per foot) and strongly
influenced by the dip of the bedrock surface and the lower hydraulic
conductivity of the till deposits The saturated thickness increases from
zero south of MW109 to 20 to 30 feet near the former disposal areas
North-northwest of these areas the hydraulic gradient lessens significantly
to a range of 00003 to 00007 feet per foot (factor of 40 to 100
reduction) North and northeast of Mill Brook the hydraulic gradient is
about 0007 feet per foot
bull Available data indicate that in the northern Study Area overburden
groundwater flow north-northwest of the Former Primary and Secondary
Disposal Areas exhibits a strongly convergent pattern The flow
5797wpdocsgalluprifinaltextmlaquosterriftU061297 6-3 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
converges from the east-northeast and southwest toward a centerline
generally defined in the downgradient direction by wells MW105
MW102 and MW101 Groundwater flows along this centerline from the
former disposal areas to the northwest Groundwater also flows from the
vicinity of the former Pervel flock plant in southwesterly and westerly
directions toward wells MW116 MW103 and MW101
South of the Former Seepage Bed groundwater flow within the upper
portion of the bedrock unit is primarily in a westerly direction In the
northern Study Area the predominant bedrock flow component is toward
the northwest In both areas the hydraulic gradient is relatively steep and
averages about 002 feet per foot Groundwater flow in bedrock near the
Former Seepage Bed is toward the northwest in the direction of wells
MW113 and MW106 and exhibits no apparent influence from locally
increased fracturing identified from the geophysical investigation and the
hydraulic testing in well MW11 IB
Vertical flow of groundwater is important in the upper several feet of the
bedrock unit Groundwater flow was found to be discharging from
bedrock to overburden at all locations during each of the measurement
dates with the exception of MW109 At MW109 the saturated overburden
thickness is less than a few feet and MW109 is located over a much
higher bedrock elevation than all other wells at which vertical flow from
bedrock was measured
Vertical flow in the overburden aquifer is of increased importance in two
areas in the vicinity of the Former Primary Disposal Area (wells clusters
MW107 MW108 and MW116) where vertical flow directions are
downward and within the upper portion of the aquifer near Mill Brook
where vertical flow is upward
Stream piezometer data and groundwater flow modeling indicate that Mill
Brook generally gains water from the overburden aquifer in the northern
portion of the Study Area
5797wpdoc8galluprifinaltextmraquosterrifhl061297 6-4 Q5T Environmental
Gallups Quarry SuperfimdProject - Remedial Investigation
613 Nature and Extent of Contamination
6131 Contaminant Source Investigation
The following summarizes the findings of contaminant source investigations during the RI
bull Previous remedial activities have completely removed the waste materials
(intact drums and bulk liquid waste) from the Site
bull The Former Seepage Bed and the Former Secondary Disposal Area
contain little residual contamination from the disposal activities which
occurred in the late 1970s
bull Residual levels of contamination primarily VOC and PCB were detected
in the Former Primary Disposal area In general the highest levels of
VOC are located at or just below the groundwater table in native soils
immediately beneath the fill materials and diminish rapidly with depth
PCB were detected primarily within fill materials
bull Other than the three known former disposal areas and the remains of the
former CTDOT asphalt plant no other significant disposal areas were
found to exist on the Site
6132 Groundwater Quality
Groundwater quality data collected during the Phase 1A program indicate the following
bull No significant groundwater contamination was detected within the
overburden or bedrock units in either the southern Study Area or in the
vicinity of the Former Seepage Bed
bull In the northern Study Area a narrow low to moderate-concentration
VOC plume (primarily TCA and DCE) was detected in the overburden
aquifer extending from the Former Primary Disposal Area to the
northwest towards Mill Brook
bull Comparison of present concentrations with historical data indicate that
concentrations within the VOC plume are significantly decreasing with
time From 1978 through 1995 TCA TCE and PCE concentrations
have decreased on the average by more than a factor of two every two
5797wpdocsgalluprifinaltextnui8terrifhl061297 6-5 QSTEnvironmental
Gallups Quarry Superand Project - Remedial Investigation
years This trend appears to have continued through the four 1995
sampling rounds for these as well as other VOC with the exception of
the break down product vinyl chloride Biodegradation and dilution by
rainwater infiltration have been identified as the primary mechanisms
causing the concentration reductions with biodegradation the most
important component
The size and orientation of the VOC plume are in excellent agreement
with the established groundwater flow directions
Available information indicates that the leading edge of the VOC plume
associated with the Former Primary Disposal Area is located between
monitoring well clusters MW102 and MW101 VOC transport rates and
the reduction of TCA and DCE levels to estimated values at MW101
support this conclusion
PCE detections in the downgradient portion of the plume exhibit
inconsistencies with migration from the Site Groundwater pathlines and
time-of-travel estimates indicate that the PCE may be attributable to
contaminant transport from the former Pervel facility located north of the
Site Specifically it is possible that PCE detections at locations MW118
MW116 MW103 MW102 and MW101 may have resulted from
groundwater transport from the vicinity of the former Pervel flock plant
However it is also plausible that the PCE detections at locations MW102
and MW101 are attributable to the former disposal areas
Results of surface watersediment sampling and analyses stream
piezometer measurements and groundwater flow modeling indicate that
some discharge of the shallow portion of the plume into Mill Brook is
occurring There are low-level detections of VOC in the section of brook
intersecting the plume however the concentrations are well below those
reported to cause adverse effects in wildlife Detections downstream
adjacent to the municipal sewage treatment plant and below the confluence
of Fry Brook and Mill Brook are probably attributable to off-site sources
along Fry Brook north of the Study Area
Only one of the bedrock wells (MW105B) indicated elevated levels of
VOC Trace levels of a limited number of VOC were also detected in
5797wpdocsgalluprifinaltextma8terrifhl061297 6-6 QStf Environmental
Gallups Quarry Superfund Project - Remedial Investigation
MW102B MW107B MW108B and SW-10 however bedrock is not a
preferred pathway for contaminant migration due to its characteristically
low hydraulic conductivity and the consistent upward component of
ground water flow from bedrock to overburden which exists throughout the
Study Area
5797wpdocsgalluprifinaltextmastemfiil061297 6-7 QSTEnvironmental
Gallups Quarry Superfund Project - Remedial Investigation
70 References
Alexander M 1978 Biodegradation of Toxic Chemicals in Water and Soil in Proc 176th
National Meeting Miami Beach FL Sept 10-15 v 93 American Chemical
SocietyDivision of Environmental Chemistry
Amtec Engineering 1994 Tecplot Version 6 Belevue WA
Bear J 1979 Hydraulics of Groundwater McGraw-Hill
Beyer WN 1990 Evaluating Soil Contamination US Fish Wildl Serv Biol Rep 90(2) 25
pp July 1990
Bouwer H and Rice RC 1976 A Slug Test Method for Determining Hydraulic Conductivity
of Unconfined Aquifers with Completely or Partially Penetrating Wells Water Resources
Research vol 12 no 3 pp 423-428
Boynton GR and Smith CW 1965 Aeromagnetic map of the Plainfield quadrangle New
London and Windham counties Connecticut US Geological Survey Geophysical
Investigations Map GP-541 scale 124000
Brusseau ML 1996 Evaluation of Simple Methods for Estimating Contaminant Removal by
Flushing Groundwater V 34 No 1 pp 19-22
CTDEP 1986 Water Quality Classification Map for the Thames Southeast Coast and Pawcatuck River Basins Sheet 2 of 2 CTDEP Water Compliance Unit Hartford
Connecticut
Dixon HR 1965 Bedrock geologic map of the Plainfield quadrangle Windham and New
London Counties Connecticut US Geological Survey Geologic Quadrangle Map GQshy
481 scale 124000
Enfield CG and Bengtsson G 1988 Macromolecular Transport of Hydrophobic
Contaminants in Aqueous Environment Groundwater v 26 no 1 pp 64-70
ERT 1988 Preliminary Hazardous Waste and Petroleum Hydrocarbon Contamination Evaluation
of the InterRoyal Property Plainfield CT
5797wpdoc8galluprifinaltextmasterrifhl061297 7-1 QST Environmental
Gallups Quarry Superfimd Project - Remedial Investigation
ESE 1994 Gallups Quarry Superfund Project RIFS Work Plan Phase 1A (Prepared by Haley
amp Aldnch Inc Finalized by ESE)
ESE 1995 Initial Site Characterization Report March 1 1996
ESE 1995a April 1995 Long-Term Monitoring Report July 28 1995
ESE 1995b July 1995 Long-Term Monitoring Report October 27 1995
ESE 1996a Long-Term Monitoring Program - Data Report February 1996 Sampling Event
June 19 1996
ESE1996b Long-Term Monitoring Program - Data Report May 1996 Sampling Event
September 24 1996
ESE 1996c Long-Term Monitoring Program - Data Report August 1996 Sampling Event
December 18 1996
ESE 1997a Long-Term Monitoring Program - Data Report November 1996 Sampling Event
March 31 1997
ESE 1997b Long-Term Monitoring Program - Data Report February 1997 Sampling Event
May 21 1997
Fitchko J 1989 Criteria for Contaminated SoilSediment Cleanup Pudvan Publishing
Company Northbrook IL
Freeze RA and Cherry JA 1979 Groundwater Prentice-Hall Inc Englewood Cliffs
New Jersey
Freyberg DL 1986 A Natural Gradient Experiment on Solute Transport in a Sand Aquifer 2
Spatial Moments and the Advection and Dispersion of Nonreactive Tracers Water
Resources Research Vol 22 pp 2031-2046
Fuss and ONeill Inc 1979 Evaluation of a chemical waste disposal area Tarbox Road site
Plainfield Connecticut January 1979
5797wpdocsgalluprifinaltextmlaquoraquotemfhl061297 7-2 QST Environmental
Gallups Quarry Superfund Project - Remedial Investigation
Gelhar LW Montogluo A Welty C Rehfeldt KE 1985 A Review of Field-Scale
Physical Solute Transport Processes in Saturated and Unsaturated Porous Media Electric
Power Research Institute Report No EA-4190
Geraghty amp Miller Inc 1989 Aqtesolv Aquifer Test Solver Version 11 Reston VA October
1979
Hansch C and AJ Leo 1979 Substituent Constants for Correlations Analysis in Chemistry
and Biology John Wiley amp Sons New York
Hem JD 1989 Study and Interpretation of the Chemical Characteristics of Natural Water (3rd
Edition) USGS Water-Supply Paper 2254 US Government Printing Office
Washington DC
HRP Associates Inc 1993 Addendum to Groundwater Monitoring Report Former Pervel
Industries Flocking Plant March and June 1993 Sampling Events HRP Associates
Inc Plainville Connecticut
Karickhoff SW DS Brown and TA Scott 1979 Sorption of Hydrophobic Pollutants on
Natural Sediments Water Research Vol 13 pp 241-248
Lyman WJ Reehl WF Rosenblatt DH 1982 Handbook of Chemical Property
Estimation Methods-Environmental Behavior of Organic Compounds McGraw-Hill
Metcalf amp Eddy 1993 Final Data Summary Report START Initiative Gallups Quarry Plainfield Connecticut
Morel MM 1983 Principles of Aquatic Chemistry John Wiley amp Sons
Prior T Eaton L and Sperduto M 1995 Habitat Characterization for Gallups Quarry
Superfund Site Plainfield Connecticut United States Department of Interior Fish and
Wildlife Service New England Field Offices Concord NH
Reed PB 1988 National List of Plant Species That Occur in Wetlands Connecticut US Fish
amp Wildlife Service Washington DC NERC-881807 105p
Robertson WD Cherry JA Sudicky EA 1991 Groundwater Contamination from Two
Small Septic Systems on Sand Aquifers Groundwater v 29 no 1 pp 82-92
5797wpdocsgalluprifinaltextmlaquoraquoterrifhl061297 7-3 QST Environmental
Gallups Quarry SuperJUnd Project - Remedial Investigation
Schincariol RA and Schwartz FW 1990 An Experimental Investigation of Variable Density
flow and Mixing in Homogeneous and Heterogeneous Media Water Resources Research
v26 no 10 pp2317-2329
Schwille F 1988 Dense Chlorinated Solvents in Porous and Fractured Media translated from
German and Edited by JF Pankow Lewis Publishers Chelsea Michigan
Shacklette HT and Boerngen JC 1984 Element Concentrations in Soils and Other Surficial
Materials in Conterminous United States USGS Professional Paper 1270 US
Government Printing Office Washington DC
Sudicky EA Cherry JA and Frind EO 1983 Migration of Contaminants in Groundwater
at a Landfill A Case Study 4 A Natural Gradient Dispersion Test J Hydrology v 63
pp 81-108
US EPA 1986 Quality Criteria for Water Office of Water Regulations and Standards
Washington DC USEPA 4405-86-001 (NTIS PB87-226759)
US EPA 1987 A Compendium of Superfund Field Operations Methods US EPA540Pshy
87001 (NTIS No PB88-181557)
US EPA 1988 Interim Final Guidance on Remedial Actions for Contaminated Groundwater at
Superfund Sites US EPA Washington DC
US Fish and Wildlife Service 1995 Habitat Characterization for Gallups Quarry Superfund
Site Plainfield CT Concord NH 16 p
USGS 1993 Geohydrology of the Gallups Quarry Area Plainfield CT
5797wpdocsglaquolluprifinaltextmasterrifhl061297 7-4 QST Environmental
SOURCE PLAINFIELD75 MINUTE
124000
0 A 2
SCALE IN MILES
OONNECnCPT
OlMDIMNGLE LOCATION
CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP SERIES 1983
410 Amherst Street Nashua NH 03063
(603) 689-3737
GALLUPS QUARRY SUPERFUND PROJECT PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 1-1
SITE LOCATION MAP DRAWING NAME 1LOCDWG miE NUMBER 7194-138
SCALE AS SHOW [REVISION 0 I DRAWN BY PAD IPATE gg97
N
500 0 500
SCALE IN FEET
LOT NUMBER OWNER
1 C STANTON GALLUP 2 KENNETH R MOFFITT 3 INTERMARK FABRIC CORP 4 NORMAN ATLAS 5 FREDERICK BARRETT 6 WILLIAM ROPERANNE OWENS 7 ROBERT GLUCK
TILCON MINERALS INC 9 TOWN OF PLAINFIELD 10 ROBERT GLUCK 1 1 STANTON GALLUP 12 - 15 EDWARD DUNCAN 16 ELAINE M NILSON 17 ADOLPH SHAGZDA 18 ANTHONY FATONEJOSEPH FATONE 19 NANCY LAMIRANDE 20 KENNETH R MOFFITT 21 CONNECTICUT DOT 22 ST JOHNS CHURCH 23 DOROTHY CARON 24 ALFRED AND EVELIN RIENDEAU 25 PAUL GELINAS AND JOAN BURNORE 26 ALBERT SR AND ANN WILCOX
LEGEND
D LOT NUMBER
-- WATERCOURSE GALLUPS QUARRY SITE
PROPERTY BOUNDARY
NOTES
BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM - CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
410 Amherst Street Nashua NH 03063
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 1-2 1000
PROPERTY BOUNDARIES AND ADJACENT LANDOWNERS
DRAWING NAM^ PROPBNDDWG |^LE NUMBER 7194 138 SCALE AS SHOW^REVISION 0 |pRAWN BY PAD loATE 5997
GB
N
LEGEND
WATERCOURSE
TO PACKERS POND (CUSS CBc)
APPROX 1 MILE WEST OF SITE
PROPERTY
CLASS Be
BOUNDARY
SURFACE WATER
CLASS BA SURFACE WATER
CLASS GE GROUNDWATER
CLASS GEGA GROUNDWATER
NOTES
1 BASE PLAN PROVIDED BY USEPADATED 14 OCTOBER 1993
DRAWING NO 707600
2 HORIZONTAL DATUM shy CONNECTICUT STATE PLANSYSTEM NORTH AMERICAN
COORDINATE DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROMPLAINFIELD TAX ASSESSORS OFFICE
TOWN OF
4 UNLESS OTHERWISE INDICATEDCLASSIFICATION IS GA
CONNECTICUT GROUNDWATER
410 Amherst Street Nashua MH 030G3
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
500 0
SCALE IN
500
FEET
1000 FIGURE 1-3
CONNECTICUT SURFACE AND GROUNDWATER CLASSIFICATION ZONES
DRAWING NAME SOILTYPEDWG
SCALE AS SfcWN [RFVISION 0 l o R A W N B Y D-fB FILE NUMBER 7194 138
G1097
LEGEND
WATERCOURSE
PROPERTY BOUNDARY
LOCATION OF PREVIOUSLY INSTALLED MONITORING WELL
NOTES
1 BASE PLAN PROVIDED BY USEPA DRAWING NO 707600 DATED 14 OCTOBER 1993
2 HORIZONTAL DATUM shy CONNECTICUT STATE PLAN COORDINATE SYSTEM NORTH AMERICAN DATUM OF 1927
3 PROPERTY BOUNDARIES OBTAINED FROM TOWN OF PLAINFIELD TAX ASSESSORS OFFICE
410 Amherst Street Nashua NH 03063
(603) 869-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
- REMEDIAL INVESTIGATION REPORT
500 0 500 1000 FIGURE 1-4
GROUNDWATER MONITOR WELLS INSTALLED BY SCALE IN FEET FUSS amp ONEILL IN 1978 AND USGS IN 1993
DRAWING NAME SWMAGDWG FILE NUMBER 7194 138
SCALE A3 SHQHW [REVISION 0 [DRAWN BY DJB |DATE 51097
bull- - n V i _raquo-A raquoraquobull bull Jpoundi _
SOURCE PLAINFIELD CONNECTICUT QUADRANGLE USGS TOPOGRAPHIC MAP 75 MINUTE SERIES 1983
124000 410 Amber atNashua NH
Street 03063
(603) 889-3737
0 GALLUPS QUARRY SUPERFUND PROJECT
SCALE IN MILES PLAINFIELD CONNECTICUT REMEDIAL INVESTIGATION REPORT
FIGURE 1-5 COHNgOICOT
SITE LOCATION MAP AND NEARBY INDUSTRIAL PROPERTIES
QURANGLE LOCATION NAME LOCMAPXXDWG FILE NUMBER 7194138
SCALE AS SHOWN [REVISION 0 I DRAWN BY CBG loATE 5997
1450
FIGURE 3-1 GROUNDWATER ELEVATIONS MW-101
1420 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-101S MW-101TT MW-1 01 T
FIGURE 3-2 GROUNDWATER ELEVATIONS MW-102
1450shy
OJ 2
LLJ 1445shy
O CO
1440shyMW-102B WAS NOT INSTALLED UNTIL PHASE IB
1435
LLJ _l HI DC LJJ
I QZ
O cc CD
1430shy
1425shy
1420 010195
1 041195
1 072095
1 102895 020596
I 051596
I 082396
1 120196
1 031197 061997
DATE
MW-102S MW-102TT ---pound-- MW-102B
FIGURE 3-4 GROUNDWATER ELEVATIONS MW-104
1450
CO
LLJ 1445shy
O CO lt |mdash 1440shy
lt 1435shy
LLJ _J LLJ
CC LLJ 1430shy
I Q Z D O CC C5
1425
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-104S MW-104TT
FIGURE 3-5 GROUNDWATER ELEVATIONS MW-105
1450
CO2 LLJ 1445shy
O CO
1440shy
1435shy
LLI
LU tr QJ 1430shy
I Q
D O cc O
1425shy
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-105S MW-105TT MW-105T -X- MW-105B
1450
FIGURE 3-6 GROUNDWATER ELEVATIONS MW-106
1420 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-106S MW-106TT
1450
FIGURE 3-3 GROUNDWATER ELEVATIONS MW-103
1415 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-103S MW-103TT
FIGURE 3-7 GROUNDWATER ELEVATIONS MW-107
1490
CO
x- -X
1420 010195 041195 072095 102895 020596 051596
DATE 082396 120196 031197 061997
MW-107S MW-107TT MW-107T -Xshy MW-107B
FIGURE 3-8 GROUNDWATER ELEVATIONS MW-108
1465shy
(02 LU
1460shy
O CO
1455shy
1450shy
LU
LU
CC LU
lt
1445shy
1440shy
Q
mdashJocc O
14j vshy^
1430 010195
1 041195
1
072095 1
102895 T T
020596 051596
DATE 082396
1 120196 031197 061997
MW-1083 MW-1 08TT MW-1 08B
1580
FIGURE 3-9 GROUNDWATER ELEVATIONS MW-109
(0 1575shy
1530 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-109S MW-109B
1470
FIGURE 3-10 GROUNDWATER ELEVATIONS MW-110S
1450 i 1 i i i 1 r 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-110S
1610
FIGURE 3-11 GROUNDWATER ELEVATIONS MW-111B
1530 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-111B
1590
FIGURE 3-12 GROUNDWATER ELEVATIONS MW-112
lt) 1580shy
149 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-1123 MW-112T MW-112B
FIGURE 3-13 GROUNDWATER ELEVATIONS MW-113
1510shy
2UJ
O m lt
1500shy
1490shy
1480shy
LU _l LJJ
CC LU
1470shy
1460shy
Q
OCC O
145degH
1440 010195 041195 072095
1 102895 020596 051596
DATE 082396
1 120196
1 031197 061997
MW-113S MW-113B
1580
FIGURE 3-14 GROUNDWATER ELEVATIONS MW-114
1460 i r 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-114S MW-114TT
150
FIGURE 3-15 GROUNDWATER ELEVATIONS MW-115
1465 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-115S MW-115TT --pound-- MW-115B
1455
FIGURE 3-16 GROUNDWATER ELEVATIONS MW-116
1425 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
MW-116S MW-116T
FIGURE 3-17 GROUNDWATER ELEVATIONS MW-117
1480shy
CO
LJJ gto CD
1475shy
1470shy
LU LU
CC LU
1465shy
WELLS AT THIS LOCATION WERE NOT INSTALLED UNTIL PHASE 1B
O z D O CC (5
1460shy
1455 010195
1 041195 072095
I 102895
1 1020596 051596
DATE
1 082396 120196 031197 061997
MW-117S MW-117TT
FIGURE 3-18 GROUNDWATER ELEVATIONS MW-118
1465shy
LU 1440shy
LLJ
CC LU 1435shy WELLS AT THIS LOCATION WERE
I Q Z D O CC CD
1430shy
1425shy
NOT INSTALLED UNTIL PHASE 1B
1420 010195
1 041195
I 072095
1 102895 020596
1 051596
DATE 082396 120196 031197 061997
MW-118S MW-118TT
FIGURE 3-19 GROUNDWATER ELEVATIONS MW-119
1475shy
CO2 LJJ
1470shy
o m
1465shy
1460shy
UJ_i UJ cc LJJ
1455
1450shy
WELLS AT THIS LOCATION WERE NOT INSTALLED UNTIL PHASE 1B
Q Z
O cc O
1445shy
1440 010195 041195
1 072095
I102895
I I 020596 051596
DATE
1 082396
i 1 201 96 031 1 97 061 997
MW-119S MW-119TT
1455
FIGURE 3-20 GROUNDWATER ELEVATIONS SW-3SD
1425 010195 041195 072095 102895 020596 051596 082396 120196 031197 061997
DATE
SW-3S SW-3D
Originals in color
VERTICAL
PROJECTED FOOTPRINT of FORMER PRIMARY
DISPOSAL AREA
MILL BROOK
NOTES (1)
(2)(3)
THE SAME CONTOUR INTERVALS ARE USED FOR THE SHALLOW AND DEEP MAPS
WATER LEVEL DATA COLLECTED 2-2-95 VERTICAL EXAGGERATION = 10X
410 Amherst Street THIS FIGURE SHOWS ONLY THE PREDOMINANT OVERBURDEN GROUNDWATER FLOW PATHWAYS WHICH ORIGINATE Nashua NH 03063 IN THE VICINTY OF THE FORMER PRIMARY DISPOSAL AREA AS VIEWED FROM THE EAST (603) 889-3737
ALTHOUGH THIS DEPICTION IS BAStU ON PlEZOMETRlC HEAD OAiA (MEASURED ON FEBRUARY 2 1335) THIS FiGURE DOES NOT SHOW EVERY POSSIBLE FLOW PATHWAY WITHIN THE OVERBURDEN AQUIFER THE UPPER SURFACE REPRESENTS THE SURFACE OF THE WATER TABLE THE LOWER SURFACE REPRESENTS GALLUPS QUARRY SUPERFUND SITE A PLANE DEFINED BY THE PIEZOMETRIC HEAD AS MEASURED IN WELLS WHICH ARE SCREENED IN THE LOWER PORTION OF THE OVERBURDEN AQUIFER THE LOWER PLANE DOES NOT REPRESENT THE LOWER BOUNDARY OF THE OVERBURDEN AQUIFER AND NEITHER PLANE IS GEOLOGICALLY SPECIFIC PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 3-21
PREDOMINANT OVERBURDEN GROUNDWATER FLOW PATHWAYS IN NORTHERN PORTION OF STUDY AREA
DRAWING NAME FLOWPATHDWG IFILE NUMBER 7194 138
SCALE NT5 JREVSION 1 JDRAWN BY CBG [DATE 6-9-97~
lt 4 Original includes color coding
10s r SW-17SandMW105S Ho5 SW-17D and MW105TT
P 1 V |
1deg4 i
4 mI U 5 k 4 3
i i f J |103 1I Un |
|io2 bull m2
bull I U = i ii gtv o r
BDL mdasha I bullM BDL a i i c CM ltD 0 ltj at agt c c at at T c I 1 I i i i
SW-13 c MW105S I10s pound
1I Un =
m4
104 I U sect
J 1I 3 bull PCE -m
H103| IU sect bull TCA
2 ^ TCE 102
m
I bull 1 2-DCE A i 1
T VINYL CHLORIDE 1 0 ^h
bull A1
10deg BDL = BELOW DETECTION LIMIT 10deg 1 U = V 3 X
=
ni-M ^ ^ ^ laquote BDL 0 V o0 CV tfi _ CO CXgt o0 ogt ogt 2 C oraquo oraquo cn O) O lt C
i- r- -3 4 1 1995
MW105TT MW107TT 105 105
E pound
i shy104
2 = 104 I = ^^to^f^P 410 Araherst Street bull^OJfcCfe Nashua NH 03063 103 103 ^raquo^^^j^ (603) 889-3737 f bull 1
- T T T shy ~ A102 i1 bull bull S 102
GALLUPS QUARR y SUPERFUND SITE I 1
PLAINFIELD CONNECTICUT REMEDIAL INVEi iTIGATOJV REPORT 10 101
i 1 FIGU RE 5 110deg i = 10deg
BDL laquo BDL VOC CONCENTRATION CHANGES VERSUS TIME M
^ i DOWNGRADIENT FROM FORt ilER PRIMARY DISPOSAL AREA sect o ^ O
^
-5lt 5amp -s= z1
1995 1995
Original includes color coding
CO
NC
ENTR
ATIO
N (
ppb)
IU sect MW102S
s 105 MW102TT
104 1 i 104
103 1 103
102 I I A sect 102
1
A
T
1 101
10deg i 10deg
nni BDL +shytr a O o
1995 1995
bull PCE
bull TCA A TCE
bull 12-DCE
T VINYL CHLORIDE
MW101TT 105
104
103
102
10deg
BDL
1995
410 Amhersl Street Nashua NH 03063
(603) 889-3737
GALLUPS QUARRY SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 5-2
VOC CONCENTRATION CHANGES VERSUS TIME DOWNGRADIENT PORTION OF PLUME
BDL = BELOW DETECTION LIMIT
s
104 tmdash a IU I
1 IU103 U-o 1F= E
i 105 to2 tmdash r 1 1deg1 i~ deg 10degL
BDL Emdash oS
105 i
104 i
103 i
102 bull
101 1
10deg
BDL 0S
105 9
104 B
103 I
102 i
101
10deg 1
BDL OCOogt
^ 00 ogt
^ra lt cltJgt
C O 0 0
0gt
MW-A
4 bull
1 1 1
co 01
MW-B
_J 1 1
1
i CO
8)
MW-C
11 1
lt lt
CO CO ogt
bullbull
laquoftr i i bull i
mn
Tbull1
bullbull
bull i
9
bull
bullM bullM bullbull- 1
egt lt t a) a
aai Tshy^
WM cN gjcI) lt J1
bull 1
bull 11 1
MM bullMl bullfr- 1
c4 0aigt C
t bullgt araquo lt raquo
T ^
Original includes color coding
10 |
-iM 10 s
-irvS 10 |
nn2 10
bullm1 bull
1UJ
oni AZs
^^^f
MW116T
A a
A =J =3
1995
bull
bullA
PCE
TCA
TCE
1 2-DCE
sect
1
s
I I 1
A gti
T VINYL CHLORIDE
BDL = BELOW DETECTION LIMIT
410 Amherst Street bull^OJUV^ Nashua NH 03063 ^raquo^^ ^jj^ (603) 889 3737
nmranmini x
GALLOPS QlARRy SUPERFUND SITE PLAINFIELD CONNECTICUT
REMEDIAL INVESTIGATION REPORT
FIGURE 5-3
VOC CONCENTRATION CHANGES VERSUS TIME AREA NORTH-NORTHEAST OF PLUME
I Original includes color coding
SW-17S MW102S and MW102TT
410 Amherst Street Nashua NH 03063
bull PCE (603) 889-3737
bull TCA A GALLUPS QUARRY SUPERFUND SITE TCE
PLAINFIELD CONNECTICUT REMEDIAL INVESTIGATION REPORT
BDL = BELOW DETECTION LIMIT
FIGURE 5-4
EVALUATION OF BIODEGRADAT10N AND RAINWATER DILUTION RATES IN VOC PLUME
(D NOTE FORWELLS MW102S and MW102TT ONLY JANUARY and NOVEMBER 1995 DATA ARE PLOTTED