KYRGYZ REPUBLIC
COMMUNITY DEVELOPMENT AND INVESTMENT AGENCY (ARIS)
SUSTAINABLE RURAL WATER SUPPLY AND SANITATION DEVELOPMENT
PROJECT (SRWSSDP)
COMPONENT 2: SANITATION DEVELOPMENT
«Rehabilitation of Internal Sanitary Facilities in the School Building
named after Baimbetov in Togotoi Village"
ENVIRONMENT MANAGEMENT PLAN (EMP) CHECKLIST
Bishkek 2018
____________________________________________________________________________________________
Kyrgyz Republic
Community development and Investment Agency (ARIS) Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 1
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
CONTENTS
ABBREVIATIONS ............................................................................................................................... 1
Specifications of the Facility ................................................................................................................. 2
Layout of Existing Sewerage Wells ...................................................................................................... 3
Pictures of Facility under Exiting Conditions ....................................................................................... 5
PART 1: GENERAL INFORMATION ABOUT FACILITY AND CONSTRUCTION SITE .......... 8
PART 2: ASSESSMENT OF ENVIRONMENTAL AND SOCIAL IMPACTS ............................... 10
PART 3: NEGATIVE IMPACT MITIGATION PLAN ..................................................................... 11
PART 4: MONITORING PLAN ......................................................................................................... 14
PART 5. BENEFICIARY FEEDBACK MECHANISM (BFM). ...................................................................................... 15
ABBREVIATIONS
АО Ayil Okmotu
ARIS Community development and investment agency
АСМ Asbestos-containing materials
WB World Bank
SAEPF State Agency on Environmental Protection and Forestry under the
Government of Kyrgyz Republic
SETI State Environmental and Technical Inspection under the Government of
Kyrgyz Republic
DDE Detailed Design and Estimation Documentation
EMP Environment Management Plan
SanPin Sanitation Norms and Rules
SNiP Construction Norms and Rules
SES Sanitary Epidemiological Surveillance
TS Technical specifications
____________________________________________________________________________________________
Kyrgyz Republic
Community development and Investment Agency (ARIS) Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 2
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
Specifications of the Facility
General Information
Country Kyrgyz Republic
Oblast Osh
Rayon Kara-Kuldja
Village Тogotoi
Distance from the Administrative Center 25 km (Uzgen City)
Facility Secondary School named after Baimbetov
Shifts 2
Number of students 443
Girls 217
Boys 226
Characteristics of State of the School Building and Engineering Communications
Building
Building construction year 1978
Structural type of the building In complex structures
Foundations Reinforced concrete
Walls Brick of structural construction
Floor slabs Prefabricated multi-cavity reinforced concrete panels
Roofing Asbestos slate
Availability, nature and size, supposed causes of
structural damage
No
Internal toilet facilities Not functioning
Characteristics of Outdoor Toilet Building Condition
Number of outdoor toilets within the territory 1 unit
Construction year 2000
Structural type of construction. Overall dimensions,
number of holes
Brick, 5 holes – boys, 5 holes – for girls, 2 holes for
teachers
Type of septic tank Monolithic concrete
Walls Brick
Floor slabs over septic tank Monolithic
Roofing of the structure made from (-) Asbestos concrete slates
Damaging the structure Cracks are available (where)
General conclusion about technical condition of the
school building and engineering communications
Building structure is in satisfactory condition
General conclusion about technical state of the
outdoor toilet
Unsatisfactory condition, there is no
separation/partition between holes
Environmental Situation (Natural Character Risks)
Estimated seismicity of this area according to SNiP KR 20-02: 2009 9 Flooding level risk, increasing the groundwater level no Rising the groundwater level caused by increasing the water level in rivers, construction of reservoirs and dams, loss of water from the water supply and sewage networks, and others - strong flooding at 0-0.3 m of ground water level from the ground surface, causing damage, destruction of engineering structures. - moderate flooding at 0.3-2.0 m of groundwater level of from the ground surface, causing damage, destruction of engineering structures. - slight flooding at 3.0-5.0 m groundwater level from the ground surface, causing damage, destruction of engineering structures.
Not exist
Mudflow risk level no
Flow with a very high concentration of mineral particles, rocks and rock fragments (up to
50-60% of flow volume), which suddenly arises in the basins of small mountain rivers and
dry logs and, as the rule, is caused by heavy rainfall or rapid melting of snows.
no
Flood risk level no
____________________________________________________________________________________________
Kyrgyz Republic
Community development and Investment Agency (ARIS) Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 3
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
Phase of the river water regime, a relatively short-term and non-periodic rising the water
level in the river, caused by increased snow melting, glaciers or an abundance of rains
no
Landfall risk level no
Breaking off and falling down masses of rocks from slopes of mountains due to impact of
gravity force.
Landfalls occur on slopes of river banks and valleys, in mountains and on lake shores.
The cause of the formation of landfalls is a disturbance of balance between the shearing
force of gravity and restraining forces.
no
Landslide risk level no
Movement of a large volume of rock mass down the slope or back slope due to impact of
gravity forces
no
Strong wind risk level Moderate
Wind gust velocity - 25 m/sec and more, within the mountainous areas 35 m/sec and more no
Long-term rain risk level no
Liquid atmospheric precipitation, falling continuously for several days, causing floods,
flooding. Amount of precipitation is 30 mm and more than 24 hours.
no
Layout of Existing Sewerage Wells
____________________________________________________________________________________________
Kyrgyz Republic
Community development and Investment Agency (ARIS) Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 4
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
____________________________________________________________________________________________
Kyrgyz Republic
Community development and Investment Agency (ARIS) Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 5
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
Pictures of Facility under Exiting Conditions
Picture1: School Building
Picture 2: Entrance of the building where the wash-hand basins will be installed
____________________________________________________________________________________________
Kyrgyz Republic
Community development and Investment Agency (ARIS) Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 6
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
Picture 3. Premises for sanitary facilities
Picture 4. Existing outdoor toilet
Under control of local SES the existing outdoor toilet will be dismantled by the school administration and the AO, sanitary
cleaning and dismantling will be carried out in compliance with all construction and sanitary norms and regulations. A tripartite
agreement will be signed between ARIS, AO and the school administration, where the obligations of the AO and the school
administration regarding the procedures for dismantling the outdoor toilet will be spelled out. As a result of all works, all
supporting documents (protocol and act) will be provided.
____________________________________________________________________________________________
Kyrgyz Republic
Community development and Investment Agency (ARIS) Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 7
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
Picture 5. Internal condition of the outdoor toilet
Picture 6. Planned location for construction of septic tank
According to the design and estimate documentation the contractor should clean the existing unfinished septic tank and take the
garbage out to a designated place - to a landfill, while coordinating this activity with the AO. Picture 6 shows the preliminary
location of the planned septic tank, but it can be moved to another location with the laying of a new pipe.
____________________________________________________________________________________________
Kyrgyz Republic
Community development and Investment Agency (ARIS) Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 8
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
PART 1: GENERAL INFORMATION ABOUT FACILITY AND CONSTRUCTION SITE
ORGANIZATIONAL AND ADMINISTRATIVE CONDITIONS
Organizational
conditions
(Names and contacts)
Project Management
Amanalieva Gulkaiyr Abaskanovna
SRWSSDP Coordinator
Phone: 0312 301805 (127)
Local part and/or beneficiary
Rahmanberdi uulu Shayirbek
Kashka-Zhol Ayil Okmotu Head
#25, Sooronbai Street
Tairov Tagai
Director of Secondary School named after
Baimbetov (Phone: 0772650509) Implementation
Mechanisms
(Names and contacts)
Supervision for
environmental
safeguard measures
ARIS Safeguard
Specialist
(Phone: 312 301805
(117)
Supervision for
local contractor’s
works by
SETI Technical
Supervision
Engineer
Supervision of local
inspections works
Надзор за работой
местных инспекций
SETI Technical
Supervision
Engineer
Contractor
To be determined
based on the tender
results
DESCRIPTION OF THE WORK SITE
Name of the Sub-
project
"Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetova in
Togotoi Village”
Who is owner of the
land plot?
The land is owned by the Ail Okmotu. The plot and the building are on the AO balance. There is a
State Act on the right of perpetual use of land No. 009411 Series B.
Description of works
to be carried out under
the Project
Rehabilitation of sanitary facilities and installation of sinks at the entrance is provided under the
Project. Design on sanitary facility rehabilitation includes rehabilitation of sanitary facilities with a
total area of 23.14 m². During the rehabilitation of sanitary facilities, it is planned to install 3 units
of WC pans for girls (total number of WC pans includes toilet bowls in the hygiene room), 4 units
toilet bowls for boys and 1 WC pan in hygiene room. Installation of 5 washing-basins with
connection to hot water is to be carried out at the entrance space. A special sewage structure for
waste waters with biological treatment, capacity of 6.0 m³ per day (with a sand-gravel filter) has
been designed.
Operation of sewage structure for waste waters with biological treatment (septic tank).
Upon the filling in the septic tank will be emptied. The school administration / AO should sign an
agreement with the organization providing sanitation services, which will transport sludge to the
treatment facilities of Osh.
Description of
geographical, physical,
biological, geological,
ecological and socio-
economic nature issues
The village is located 25 km from the Uzgen City - the Uzgen Rayon administrative center. The
construction site is located in the western part of Kara-Kulja Rayon, Osh Oblast, at 12 km distance
from Kara-Kulja Rayon Center. The school is located in the center of the Togotoi Village.
There are no any nature protection objects (nature reserves, cultural monuments, historical and
architectural sights) and water reservoirs at the site and next to it.
Relief of the site: even without slopes.
No any mudflows or landslides were at the site, there are no signs of soil erosion.
Ground surface: without cover
Vegetation: trees, grass. (no any cutting trees is expected)
Water supply: it is planned to connect to the Village water supply system under construction.
Sewerage: there is an autonomous sewage system, pipe cleaning is required.
During the cleaning the sewer pipes, all the water will merge with the existing septic tank, and
previously it will be cleared of debris. In the case of an unsatisfactory state of the old pipe, a new
one will be laid.
Heating: water heating.
Power supply: satisfactory condition
Ventilation: Natural
Presence of asbestos-containing materials (ACM): roofing of the existing outdoor toilet is
constructed from AS sheets. (A description how to work with AS materials is below).
Currently the school students and staff are using the outdoor toilet.
____________________________________________________________________________________________
Kyrgyz Republic
Community development and Investment Agency (ARIS) Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 9
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
The external toilet is a structure with load-bearing brick walls, with V-shaped roof covered with
wavy asbestos-cement sheets.
Dismantling works of the existing toilet will be carried out by the administration (school, AO).
Construction work will be carried out during the summer time, during the school holidays.
The Project works will not have any significant impact on transport or communal utilities.
Design works require compliance with a number of mandatory requirements, including
compliance with noise and air quality norms, timely removal of construction debris.
Application of WB policy OP 4.12 "Involuntary Resettlement" is not required.
Location and distance
from material supply,
inert materials and
water point
Clay quarry is available and located 2-3 km from the village. There is no career of sand and gravel.
Sources of water for Project works: a new water supply system.
Water to be used for manufacturing concrete, mortar and cement mortar should not contain silt,
organic materials, salts and other impurities.
LEGAL AND REGULATORY ENVIRONMENT
National legislation
and permits to be
applied to project
activities
Law of the Kyrgyz Republic on Environmental Protection (2016)
Law of the Kyrgyz Republic on Environmental Expertise (2015)
Law of the Kyrgyz Republic on General Technical Regulation on Environmental Safety in the
Kyrgyz Republic (2012)
Law of the Kyrgyz Republic on Production and Consumption Wastes (2001)
The Contractor is responsible for:
obtaining permission from the territorial Rayon Urban Planning and Architecture
Administration to carry out construction work;
signing a contract with the AO to dispose construction debris at the AO waste dump
PUBLIC CONSULTATIONS
Indicate where and
when public
consultation meetings
were held
Under the Component 2 "Development of Sanitation", a number of public consultations were held
for local people, including school students and personnel. The following topics were discussed:
promotion of the WASH (water, sanitation, hygiene)
WASH three-day training for teachers was held.
INSTITUTIONAL CAPACITY DEVELOPMENT
Is capacity
development
expected?
[ ] No or [Х] Yes.
WASH training will be conducted in May 2018
____________________________________________________________________________________________
Kyrgyz Republic Community development and Investment Agency (ARIS)
Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 10
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
PART 2: ASSESSMENT OF ENVIRONMENTAL AND SOCIAL IMPACTS
Types of work and examples of possible impacts State – in case of YES
Response for item
Additional
references
Can planned
works at the
site cause,
directly or
indirectly, any
of the
following
problems and /
or impacts:
1. Building Reconstruction/rehabilitation
Loads due to traffic at the site
Increased noise and dust levels during demolition and/or restoration works
Construction debris
[Х] Yes [] No See Items A and
B below
2. New construction
Excavation works and soil erosion consequences
Wastewater into local watercourses and groundwater aquifers
Loads due to traffic at the site
Increasing the noise and dust levels during construction
Construction debris
[Х] Yes [ ] No See Items A and
B below
3. Occupational health and safety for workers during construction [Х] Yes [ ] No See Items A and
D below
4. Ensuring traffic safety and pedestrians
The construction site is located in the village
[Х] Yes [ ] No See Items A and
D below
5. Improvement of the design of sanitary facilities in the buildings [Х] Yes [ ] No See Items F, G,
H below
6. Sewerage and waste water treatment
Sewage system and/or direct discharge of waste waters into local waterways
[Х] Yes [] No See Items I
below
7. Historical buildings and sites
Damaging monuments of historical and cultural legacy (HCL)
[ ] Yes [Х] No -
8. Allocation of land for the Project1
Using the private property
Temporary relocation of the local population due to the project activities
Involuntary resettlement measures
Impacts on income / livelihoods of local people and commercial structures
[ ] Yes [Х] No -
9. Hazardous or toxic materials2
Removal or disposal of toxic and/or hazardous wastes from construction or demolition work site
[Х] Yes [] No See Items C
below
10. Impacts on forests and / or other protected areas
Impact on the territory of protected forest plantations, buffer and/or other protection zones
Disturbances for local natural habitat of protected animals
[ ] Yes [Х] No -
1 Land acquisition (land allocation) for design works includes resettlement of local population; changes in livelihoods of the local population; penetrating the territories that are privately owned. It is related to land plots that are to be acquired or transferred to the project, and such land acquisitions or transfers are related to effect on people who live formally and/or informally within this land and / or engage in some kind of business on it (for example, they are keeping kiosks). 2 Works with toxic and/or hazardous materials include, in particular, work with asbestos, toxic paints, removal of paint containing leads and etc.
____________________________________________________________________________________________
Kyrgyz Republic Community development and Investment Agency (ARIS)
Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 11
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
Types of work and examples of possible impacts State – in case of YES
Response for item
Additional
references
11. Effects from construction of septic tank, sewer pipes:
excavation: excavation of soil, embankment, soil back filling, levelling/grading
disturbance of the soil-vegetation layer
possible impacts on groundwater (with a close groundwater level)
disturbance of the natural level of groundwater flow (dehumidification, waterlogging of soils)
[Х ] Yes [ ] No See Items J
below
PART 3: NEGATIVE IMPACT MITIGATION PLAN
Activity Parameters Mitigation measures checklist
A. General conditions
for works
Оповещение,
инструктаж и
обеспечение
безопасности
работников
(a) Local inspectorates, supervising construction work and environmental safety, as well as local residents should be properly notified
about upcoming project work.
(b) The local community should be properly informed about works through corresponding publications and/or messages in the public
areas (including at the working site).
(c) Appropriate fences are to be installed around the construction site to ensure the safety of population and children.
(d) Permits required by the legislation (using natural resources, disposal to the waste dump, etc.) for implementation of construction
work are obtained.
(e) All types of work must be performed with due safety and discipline in order to minimize negative impacts of production process
on local people and environment.
(f) Workers will have obligatory briefing of safety measures on site including briefing on application of individual safety means
meeting standard work safety (with obligatory wearing of hardhats, masks where needed, protective goggles, safety belts and
protective footwear).
(g) Appropriate indication and information signs notifying the workers about basic required rules and principles of work performance
must be installed on the site.
(h) There should be a signboard with clear information for patients about access to medical services during construction work.
(i) If the Contractor engages outside workers to construction and repair work, it is required to provide and arrange all necessary
conditions including dormitory, kitchen, shower, toilet and meals for them.
B. General civil
works
Air quality (a) Construction debris should be disposed and stored in specially designated area with subsequent disposal to a landfill.
(b) It is required to keep cleanliness at the construction site and adjacent territory.
(c) It is prohibited to burn construction wastes and structures on an open fire on the construction site.
(d) It is not allowed to have excessive accumulation of non-working construction equipment at the construction site.
Noise (a) Construction noise is allowed only during the specified working period, from 8:00 to 18:00.
(b) During works covers and hoods of engine generators, air compressors and other machines must be closed, and the machines must
be placed as far as possible from the residential buildings.
Water quality (a) Pollution of construction territory by spilled combustive and lubricating materials must be avoided to prevent polluted runoff get
into irrigation canals.
____________________________________________________________________________________________
Kyrgyz Republic Community development and Investment Agency (ARIS)
Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 12
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
Activity Parameters Mitigation measures checklist
Works with wastes (a) For construction debris, it is necessary to prepare places for temporary storage, with following transportation of it to the local
landfill.
(b) Where possible, the contractor shall ensure the recycling of suitable usable and resistant materials (excluding ACM).
(c) Domestic and food wastes from the permanent location of the Contractor's outside personnel at the site should be separated from
other construction waste and placed in special containers, which, as they have been filled, must be transported to the local waste
dump.
C. Toxic materials Work with toxic and
hazardous materials
(a) All toxic or hazardous materials, if temporarily stored within the working area, should be stored in reliable containers marked
appropriately, indicating composition and properties of this material and rules for handling it.
(b) Containers containing hazardous materials shall be placed in containers that exclude any possibility of leakage, to avoid any spills
and leaks.
(c) Paints containing toxic components or solvents made on the basis of lead should not be used in work.
Work with asbestos-
containing materials
(ACM)
(a) If there is asbestos at the construction site, it must be clearly marked as a hazardous material.
(b) If possible, asbestos will be placed in appropriate sealed containers to minimize its impact.
(c) Before to remove asbestos (if removal is necessary), it should be treated with a moisturizing compound in order to reduce the
formation of asbestos dust.
(d) Only qualified and experienced professionals are allowed to work with asbestos.
(e) If there is a need for temporary storage of asbestos-containing materials, all wastes should be placed in secure closed containers,
provided with appropriate marking.
(f) Removed asbestos cannot be reused.
D. Safety of traffic
and pedestrians
Direct/indirect damage of
construction works to
traffic and pedestrians
The contractor should ensure proper safeguard of the construction site.
It is required to equip the site with information and warning signs, fences to ensure that the site of work is to be identified and
visible, and the public should be duly notified and warned of possible dangers
It is required to ensure safe and permanent access to the existing school building during construction works at the site, if the
existing school remains open for the visiting.
E. Detailed Design
and Estimation
Documentation
(DDE)
The detailed design and estimation documentation (DDE) should include:
1) Provision about exclusion of using ACM in design work;
2) Using the local material where possible;
3) proper ventilation and natural lighting;
4) construction of floors, eliminating the slip, fall and retention of infectious material;
5) if possible, a provision on exclusion of cutting trees and shrubs.
F.Power Supply Construction of reliable power supply with connection to existing networks, according to Technical Specifications.
G. Heating Installation of electric convectors with temperature sensors.
H. Water Supply Installation of water consumption meters for accounting and rational water using..
____________________________________________________________________________________________
Kyrgyz Republic Community development and Investment Agency (ARIS)
Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 13
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
Activity Parameters Mitigation measures checklist
I. Sewerage Mounting the water and sewage pipes and construction of the new septic tank within the school territory are planned. All wastes will
enter to the septic tank (treated water will be discharged into the soil through gravel-sand filters). Once the septic tank is filled, it is
necessary to clean it with sewage cleaning machine (responsibility of the AO/School administration)
J. Effects from the
device of septic tanks,
sewer pipes.
Water pollution,
disturbance of land, flora,
fauna and landscape
Designing the appropriate drainage systems (sewage system).
Refusal from construction of excavations, having close groundwater level, designing embankments based on the condition of
preventing the interruption of aquifers.
Removal of topsoil layer
Territory planning, construction of canals and drainage systems for water collection and treatment, fencing of territory, organization
of refueling of equipment at specially installed places or at gas stations of general use.
It is forbidden to discharge not treated and not decontaminated (in accordance with norms established) waste waters into water
objects.
Elimination of flooding and drainage of territories, soil erosion, soil degradation from transport pollution, recultivation of disturbed
lands during construction, bypass of specially protected areas and valuable plantings.
Territory planning, exclusion of water stagnation sites, timely cleaning and disposal of felling residues.
Application of landscape design methods, excluding as far as possible deep holes and high embankments.
Installation of a septic tank that is in compliance with all technical specifications
____________________________________________________________________________________________
Kyrgyz Republic Community development and Investment Agency (ARIS)
Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 14
Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
PART 4: MONITORING PLAN
Stage What
(due monitoring?)
Where
(due
monitoring?)
How
(due monitoring?)
When
(frequency (or
permanent?)
Why
(due monitoring?)
Cost
(if not
included in
design
estimate)
Who
(responsible
for
monitoring?)
Des
ign
Detailed design estimation documentation (DDE) is
described in details in Item E above.
Reports and
completed DDE
prepared by the
design company
Review of
Reports and
completed DDE
prepared by the
design company
At stages of
submission by the
design company of
the completed DDE
before the expertise
To ensure that all
necessary
requirements are
included in the
tender
documentation.
Due to the
Project
expenditures
ARIS
Civ
il w
ork
s
1. Fencing the territory during construction works.
2. Information stands with contact details for local
people complaints.
3. Availability of personal protective equipment
for Contractor’s staff.
4. Prohibition on ACM use.
5. Preventing soil erosion and transfer of waste
water to adjacent water courses.
6. Appropriate collection and removal of
construction wastes.
7. Contract between the Contractor and ayil
okmotu for the disposal of construction wastes
on the local dump.
8. Preventing of dust production.
9. Noise level reduction and limitation by
working hours (from 8:00 to 18:00)
Construction site Inspection visits
to the
construction sites.
Handling the
complaints of
local people.
During construction
and up to issue of
Certificate of
completion. In case
of handling local
people complaints
To provide
compliance with
all necessary
environmental
requirements.
The
Contractor
must include
to the
bidding
documents
SETI,
SES
Op
era
tio
n
1. Proper operation of the septic tank, according to
instructions, including implementation of
cleaning as it is filled by a sewage cleaning
machine.
2. Implementation of introductory
briefing/instructions with the school
maintenance staff.
Septic tank Observations
Regularly
Due to the
requirements of
national
regulations and
standards
At the
expenditures
of AO and
School
School
Director
Inspection visits
to repair and
construction
work sites
Regularly
according to the
service instructions
SETI,
SES
____________________________________________________________________________________________
Kyrgyz Republic Community development and Investment Agency (ARIS)
Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 15 Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
PART 5. BENEFICIARY FEEDBACK MECHANISM (BFM).
ARIS is introducing an information system for handing the complaints, including complaints from citizens –
Beneficiary Feedback Mechanism (BFM).
The main objective of the ARIS BFM is the process of receiving prompt, objective information, including
assessing and reviewing appeals (statements, proposals, complaints, requests, positive feedbacks) at all stages of
project implementation, which can be supplied by citizens/beneficiaries to improve their work in future. It is also
applied to strength communication with Project beneficiaries and provide channels for feedback, and identify and
address problems, increasing transparency and accountability.
Dissemination of information about BFM goes through the following activities:
Presentation by the BFM Specialists to local authorities, AOs and Local Kenesh deputies;
During the public hearings and trainings conducted by ARIS staff. The BFM team conducts the whole
information campaign in communities
There are BFM banners to be placed on social sites (schools, kindergartens, FAP)
There are banners in Rayon administrative buildings
there is BFM page/block at the official site
All appeals and complaints from citizens to be received under SRWSSDP shall be sent to the unified system for
further processing and control.
Channels for feedback
Receiving Appeals. During the receiving appeal the following should be determined:
Type of appeal
Category of appeal
Person responsible for studying and executing the appeal.
Timeframe, during which the appeal should be regulated/solved.
Coordinated actions
Once the type of appeal is determined, the responsible BFM Specialist shall register details regarding to the
appeal in the incoming correspondence log, and then in the BFM configuration of the 1C system.
1. Hotline: + 996 (550) 70-05-22, ( calls are
received 24-hours; conversations will be
recorded );
2. WhatsApp: + 996 (770) 70-05-22, ( a
system of immediate text messaging for
mobile devices with voice and video
connections );
3. Social media (Facebook);
4. ARIS web-site: www.aris.kg
5. Verbal or written appeal received during
the on-site working meetings;
6. Incoming correspondence via ARIS
reception;
7. Incoming correspondence via BFM e-
mail: [email protected]
1. Appeals are recorded in the BEM incoming
correspondence log and are accepted for
consideration subjected to the following
information is provided:
name, surname, and patronymic name
address of registration and residence or
telephone number;
content of the appeal;
other reference information.
1.1. In cases when appeals were received without
data specified above, it is recorded in the BEM
incoming correspondence log and the sender should
be notified about it, and appeal results will be
published in the media at the local level, at the ARIS
website or announced at the AK session.
2. Appeals are to be entered into BFM configuration
in the 1C system for analysis and monitoring.
3. The appeals may be submitted anonymously.
Confidentiality must be ensured in all cases, including
when identity of the person submitting the appeal is
known, in order to avoid conflicts between interested
parties.
____________________________________________________________________________________________
Kyrgyz Republic Community development and Investment Agency (ARIS)
Sustainable Rural Water Supply and Sanitation Development Project (SRWSSDP)-1 16 Rehabilitation of Internal Sanitary Facilities in the School Building named after Baimbetov in Togotoi Village_EMP Checklist
The person who submitted the claim should receive a notification, where the BFM Specialist will report through
the phone or through other BFM channels:
Name and surname of the executor (project specialist) to which the appeal was forwarded
Deadlines for the execution (minimum 10 days, maximum 30 days since the day it was registered)
Deadlines and actions are determined in accordance with the ARIS BFM instructions on the work with the
appeals
The notification should be registered in the outgoing correspondence log. BFM Specialist will assist the addressing
person at all stages of consideration of his/her appeal and ensure that hi/her appeal is properly handled.
In the event when the citizen/ beneficiary is not satisfied with the decision resulting from consideration of the
claim, he / she has the right to appeal. Appeal is considered by a special ARIS Grievance Redress Committee.
The ARIS Executive Director should establish the Committee from Project Managers and Unit Heads, who will
conduct hearings of appeals. It is assumed that the Grievance Redress Committee will consist of 15-17 people, 2
of which are BFM members and 2 are persons that are independent of the project implementation staff and the
Government of the Kyrgyz Republic.
After appellant consideration of the claim, the citizen/beneficiary who is not satisfied with the decision received
on results of consideration has the right to appeal the decision in the judicial procedure.