Upload
others
View
19
Download
1
Embed Size (px)
Citation preview
Client: Urban Link
Project Description: Residential Dwelling with Basement Parking
Project Address: 17 Firth Avenue, Strathfield NSW
QPC Reference No: Q2020-CR173
Date of Assessment: 17th August 2020
REGISTERED QUANTITY SURVEYORS
COST REPORT
www.capital-qpc.com.au
QPC & C Pty LimitedABN 78 074 731 963
Office Address:Level 1, 1 Bells Road,Oatlands, NSW, 2117
Postal Address:PO Box 300, Oatlands, NSW, 2117
P 02 9638 5522E [email protected]
www.capital-qpc.com.au
1
Registered Quantity Surveyors Detailed Cost Report
Contents
Section 1.0 Introduction
Section 2.0 Development Description
Section 3.0 Construction Cost Summary
Section 4.0 Basis of Estimate
Section 5.0 Review of Documentation
Section 6.0 Disclaimer
Tables within Report
Table 1 - Development Information
Table 2 - Cost Estimate Summary
Table 3 - Drawing Register
Appendix
Appendix A - Council Form
Appendix B - Elemental Cost Estimate
Appendix C - Schedule of Finishes
1.0 Introduction
2.0 Development Description
2
1
Table 1 - Development Information
Balcony Areas 124 m2
Total Areas 1,144 m2
An instruction was received on 7th August 2020 to complete a cost estimate for submission with DA
documentation to Council. To this end we have carried out the following:
The development proposes the construction of a two-storey residential dwelling over a basement.
357 m2
663 m2
Parking Areas x Car Spaces
Residential Areas
Item Area
x Units
Comments
Q2020-CR173 2
Registered Quantity Surveyors Detailed Cost Report
3.0 Construction Cost Summary
Table 2 - Cost Estimate Summary
4.0 Basis of Estimate
4.1 Section 255 (EPA Regulation 2000)
4.2 Section 25J
-
-
-
-
-
-
-
4.3 Capital Investment Value
See section4.1
Excavation (Included )
Decontamination or Remediation (Excluded )
See section4.3
We advise that this is a genuine estimate of the construction costs prepared in accordance with the DA issue
Architectural Plans and draft Schedule of Finishes only. A more detailed estimate can be prepared upon
receipt of Structural Engineering and Services Documentation.
$1,948,516
Amount Comments
$2,101,117
In accordance with Section 25 J of the EP&A Regulation the proposed cost of carrying out the
development is to be determined by adding up all the costs and expenses that have been or are to be
incurred by the applicant in carrying out the development. Including the following:
In accordance with Section 255 of the EP&A Regulation the development cost includes for goods &
services tax, builders margin and all associated preliminaries & labour but excludes any project
contingency.
See section4.2
The cost of any development that is provided as affordable housing. (Not Considered )
The construction cost estimate as calculated by our firm can be summarised as follows:
Item
The following are not to be included in the proposed cost:
Total Cost of Works (Clause 255)
Capital Investment Value
$2,143,367
Total Cost of Works (Clause 25J)
In accordance with NSW Planning Circular PS 10-008 the Capital Investment Value of a development
or project includes all costs necessary to establish and operate the project, including the design and
construction of buildings, structures, associated infrastructure and fixed or mobile plant and
equipment. (Excluding contingency, land cost, development contributions, finance fees & interest and
GST)
Erection of a Building (Included )
The costs of fittings and furnishings. (Considered)
Demolition (Included )
The costs of any development that is the adaptive reuse of a heritage item (Not Considered )
Q2020-CR173 3
Registered Quantity Surveyors Detailed Cost Report
4.5 Quality
4.5 Exclusions
-
-
-
-
-
-
-
5.0 Review of Documentation
Table 3 - Drawing Register
6.0 Disclaimer
Kind Regards,
Tony Sassine B.App.Sci (Hons), AAIQS
Managing Director
A schedule has been prepared to establish a quality basis to determine the costs of finishes. The
finishes nominated are of a reasonable standard which is appropriate for the projects type and
location.
This cost estimate has been prepared for the purpose of providing an indicative development cost suitable
for DA submission to Council. All reasonable professional care and skill have been exercised to validate the
accuracy and authenticity of the information supplied. Any form of contractual, tortuous or other form of
liability for any consequences, loss or damage, which may result from other persons acting upon or using this
estimate, will not be accepted.
Urban Link 2020-080
DA0001; DA0002; DA1001;
DA1002; DA2001 - DA2004;
DA3001; DA3002; DA4001; DA5001
- DA5003
-
The estimate has been prepared based on a review of documentation supplied, including:
Reference Drawings: Issue
The following items have been excluded from this cost estimate:
Consultant
National Broadband Network Implications
Acoustic treatments exceeding the nominal allowance
Electrical Substation / Electricity Upgrades
The finishes and therefore costs may be subject to change based on future selections made by the
developer or builder.
Rock Excavation
Interest & Finance Charges
Land Costs, Rates, Legals, Stamp Duty & the like
Decontamination or Remediation
Q2020-CR173 4
Appendix A
www.capital-qpc.com.au
QPC & C Pty LimitedABN 78 074 731 963
Office Address:Level 1, 1 Bells Road,Oatlands, NSW, 2117
P 02 9638 5522E [email protected]
DATE OF REPORT:
DEVELOPMENT APPLICATION No.
CONSTRUCTION CERTIFICATE No.
APPLICANT'S NAME:
APPLICANT'S ADDRESS:
DEVELOPMENT DESCRIPTION:
DEVELOPMENT ADDRESS:
Gross Floor Area - Commercial m2 Total Gross Floor Area m2Gross Floor Area - Residential m2 Total Site Area m2Gross Floor Area - Retail m2 Total Car Parking Spaces No.Gross Floor Area - Car Parking m2Gross Floor Area - Other m2
Total Development Cost $
Total Construction Cost $Total GST (Included Above) $
Excavation $ Fit-Out - Commercial $
Cost per m2 of site area $ Cost per m2 of commercial area $
Demolition & Site Prep $ Fit-Out - Residential $
Cost m2 metre of site area $ Cost per m2 of residentail area $
Construction - Commercial $ External Works / Landscaping $
Cost per m2 of commercial area $ Cost per m2 of site area $
Construction - Residential $ Professional Fees $
Cost per m2 of residential area $ % of Development Cost %
Construction - Retail $ % of Construction Cost %
Cost per m2 of retail area $
Car Park $
Cost per m2 of site area $
Cost per space $
I certify that I have:
✓
✓
✓
✓
✓
Signed:
Name: Tony Sassine AIQS Membership Number: 1565
Position & Qualifications: Managing Director, B.App.Sci (Hons), AAIQS
Measured gross floor areas in accordance with the Method of Measurement of Building Area in the AIQS
Cost Management Manual Volume 1 (Appendix A2)
Registered Quantity Surveyor's Detailed Cost Reportfor development costs in excess of $1,000,000
213.42 /m2 Total Development Cost: $ 2,143,367
274,136
Inspected the plans the subject of the application for development consent or construction certificate.
Prepared and attached an elemental estimate generally prepared in accordance with the Australian Cost
Management Manuals from the Australian Institute of Quantity Surveyors.
Calculated the development costs in accordance with the definition of development costs in the Section 94A
Development Contributions Plan of the council at current prices.
Included GST in the calculation of development cost
137,068 /space Incl GST
2.00
44,590 620,176
34.71 /m2 826.93 /m2
183,109
142.55 /m2
876,080 42,027
1168.15 /m2 1.96
80.38 /m2
ESTIMATE DETAILS
750 1,284
2
357
2,143,367
2,101,341
194,852
103,249
Residential Dwelling with Basement Parking
17 Firth Avenue, Strathfield NSW
DEVELOPMENT DETAILS
1,107
17th August 2020
6
Appendix B
www.capital-qpc.com.au
QPC & C Pty LimitedABN 78 074 731 963
Office Address:Level 1, 1 Bells Road,Oatlands, NSW, 2117
P 02 9638 5522E [email protected]
Client: Urban LinkProject Description: Residential Dwelling with Basement ParkingProject Address: 17 Firth Avenue, Strathfield NSWDate: 17th August 2020
ELEMENT GFA Rate % TOTAL ELEMENTAL COST
SITE PREPARATION $29.68 1.72% $32,845
EXCAVATION $68.71 3.98% $76,053
SUBSTRUCTURE $182.44 10.57% $201,926
SUPERSTRUCTURE
Upper Floors $169.60 9.83% $187,718
Roof $96.23 5.58% $106,512
External Walls $202.26 11.72% $223,862
Windows $49.77 2.88% $55,083
External Doors $1.81 0.10% $2,000
Internal Walls $47.14 2.73% $52,173
Internal Screens $5.42 0.31% $6,000
Internal Doors $10.81 0.63% $11,965
FINISHES
Wall Finishes $83.80 4.86% $92,755
Floor Finishes $65.43 3.79% $72,419
Ceiling Finishes $33.11 1.92% $36,644
FITTINGS
Fitments $62.75 3.64% $69,451
Sanitary Fixtures $9.31 0.54% $10,300
SERVICES
Water & Gas Supply $42.87 2.48% $47,450
Heating, Ventilation & AC $35.50 2.06% $39,292
Fire Protection $0.81 0.05% $900
Electrical Light & Power $24.49 1.42% $27,105
Trasportation Systems $54.21 3.14% $60,000
Special Services $0.45 0.03% $500
EXTERNAL WORKS $121.86 7.06% $134,876
Subtotal - Elements $1,547,828
Preliminaries $192.29 11.14% $212,826
Profit & Overheads $135.21 7.83% $149,656
Total Construction Cost 1,107 m2 $1,725.94 100% $1,910,310
Professional Fees $38,206
Total Development Cost (Excluding GST) $1,948,516
Goods & Services Tax $194,852
Total Development Cost (Including GST) $2,143,367
ELEMENTAL COST PLAN SUMMARY
Q2020-CR173 8
Client: Urban LinkProject Description: Residential Dwelling with Basement ParkingProject Address: 17 Firth Avenue, Strathfield NSWDate: 17th August 2020
Qty Unit Rate Total
SITE PREPARATIONDemolition 1 Item 20,000.00$ 20,000.00$ Site Clearance 1,284 m2 10.00$ 12,844.90$
EXCAVATIONBulk Excavation 1,142 m3 40.00$ 45,676.80$ Trim, level and compact entire building area. 483 m2 15.00$ 7,246.20$ Detailed Foundation Excavation 93 m3 250.00$ 23,129.55$
SUBSTRUCTUREConcrete, Reo & Labour to Footings 93 m3 550.00$ 50,885.01$ Basement Perimeter Walls 369 m2 230.00$ 84,809.28$ Basement Internal Walls 90 m2 230.00$ 20,693.10$ Concrete Slab on Ground 357 m2 110.53$ 39,442.63$ Suspended Concrete Slabs N/A m2 N/ADriveways 42 m2 110.53$ 4,595.84$ Subsoil Drainage
Car Wash Pit Excl.Stormwater Pits 1 Item 1,500.00$ 1,500.00$ Discharge Control Pit Excl. -$ Rainwater Tank Incl. -$
SUPERSTRUCTUREUpper Floors
Suspended Concrete Slab 661 m2 225.43$ 148,903.54$ Concrete Slab on Ground (GF) 126 m2 110.53$ 13,952.20$ Internal Stairs 2 No. 4,000.00$ 8,000.00$ Lift Shaft 1 No. 15,133.97$ 15,133.97$ Termite Protection to Perimeter Wall 115 m 15.00$ 1,728.45$
RoofFramed Roof Structure 449 m2 90.00$ 40,368.60$ Roof Lining and Plumbing 449 m2 90.00$ 40,368.60$ Concrete Roof Structure 78 m2 265.43$ 20,674.37$ Skylight 9 m2 600.00$ 5,100.00$ Awnings Excl. -$
External WallsPerimeter Walls 627 m2 220.00$ 137,878.62$ Parapet walls 25 m2 220.00$ 5,456.00$ Mouldings 373 m 55.00$ 20,527.10$ External Columns 30 No. 2,000.00$ 60,000.00$ External Screens / Louvers Excl. -$
WindowsAluminium framed windows & doors 157 m2 350.00$ 55,083.00$ Commercial Glazing N/A Item N/A N/A
External DoorsAutomatic Doors N/A No. N/A N/ARoller Doors / Tilt Doors 1 No. 2,000.00$ 2,000.00$
Internal WallsParty Walls N/A m2 N/A N/AInternal Walls 580 m2 90.00$ 52,172.91$
Internal ScreensStorage Cages Excl. -$ Frameless Shower Screen 6 No. 1,000.00$ 6,000.00$
ELEMENTAL COST PLAN BREAKUP
Item
Q2020-CR173 9
Internal DoorsUnit Entry Doors 1 No. 1,500.00$ 1,500.00$ Internal Unit Doors 19 No. 250.00$ 4,750.00$ Internal Sliding Doors 6 No. 350.00$ 2,100.00$ Hardware to above 19 No. 85.00$ 1,615.00$ Basement Solid Doors 4 No. 500.00$ 2,000.00$
FINISHESWall Finishes
Plasterboard to Perimeter Walls 627 m2 18.00$ 11,280.98$ Plasterboard to Party Walls N/A m2 N/A N/AInsulation to above 627 m2 10.00$ 6,267.21$ Plasterboard to Internal Walls 1,159 m2 18.00$ 20,869.16$ Cornice to above 638 m 18.00$ 11,482.19$ Painting to above 1,786 m2 12.00$ 21,433.43$ Wall tiles to Bathrooms 8 No. 2,000.00$ 16,000.00$ Skirting within unit 638 m 8.50$ 5,422.15$
Floor FinishesCarpet to bedroom areas 264 m2 50.00$ 13,198.00$ Carpet to lobby areas Excl. -$ Waterproofing to Wet Areas 8 No. 450.00$ 3,600.00$ Tiling to Wet Areas 59 m2 75.00$ 4,393.50$ Tiling to kitchen & living areas 359 m2 75.00$ 26,919.75$ Waterproofing to Balconies 6 m2 40.00$ 245.60$ Timber decking to GF terrace. 118 m2 200.00$ 23,602.00$ Tiling to Balconies & Patios. 6 m2 75.00$ 460.50$
Ceiling FinishesPlasterboard to ceiling 663 m2 40.00$ 26,504.40$ Access hatches per unit 1 No. 200.00$ 200.00$ Painting to above 663 m2 15.00$ 9,939.15$
FITTINGSFitments
Sliding Mirror Wardrobe 3 No. 1,000.00$ 3,000.00$ Walk-In-Wardrobe 5 No. 1,800.00$ 9,000.00$ Kitchen Joinery incl bottler 1 No. 15,000.00$ 15,000.00$ Kitchen Benchtops 1 No. 5,000.00$ 5,000.00$ Kitchen Splashback 1 No. 2,500.00$ 2,500.00$ Laundry joinery incl tops 1 Item 3,000.00$ 3,000.00$ Linen cupboards 3 No. 850.00$ 2,550.00$ Cool Room 1 Item 8,000.00$ 8,000.00$ Vanity Joinery Custom Made 8 No. 550.00$ 4,400.00$ Mirror above Vanity 8 No. 100.00$ 800.00$ Fire Place 1 Item 7,500.00$ 7,500.00$ Internal Stair Handrails 10 m 230.00$ 2,286.20$ Void Balustrades 14 m 250.00$ 3,615.00$ Mail Boxes 1 No. 250.00$ 250.00$ Required Signage Incl. -$ Appliances -$
Oven 900mm 1 No. 800.00$ 800.00$ Cooktop 900mm 1 No. 450.00$ 450.00$ Rangehood 900mm 1 No. 400.00$ 400.00$ Dishwasher 900mm 1 No. 900.00$ 900.00$ Microwave N/A No. -$ N/A
Sanitary FixturesToilet Suite Concealed Cistern 8 No. 400.00$ 3,200.00$ Urinals N/A -$ Bath Tubs & Tapware 1 No. 1,000.00$ 1,000.00$ Vanity Basin & Mixer 8 No. 150.00$ 1,200.00$ Shower Mixer & Rose 6 No. 350.00$ 2,100.00$ Kitchen Sink & Tapware 1 No. 450.00$ 450.00$ Laundry Tub & Tapware 1 No. 350.00$ 350.00$ Bathroom Accessories 8 No. 250.00$ 2,000.00$
Q2020-CR173 10
SERVICESWater & Gas Supply
Sanitary plumbing and drainage (Units) 1 No. 40,000.00$ 40,000.00$ Sanitary plumbing and drainage (Commercial) N/A Item N/A N/AStormwater Pits, OSD, Etc. 1 Item 2,000.00$ 2,000.00$ Allowance for standard sewer connection 1 Item 3,000.00$ 3,000.00$ Rainwater Tanks 1 Item 1,500.00$ 1,500.00$ Supply of Hot Water Units 1 No. 950.00$ 950.00$ Gas Reticulation Incl. -$
Heating, Ventilation & ACAir Conditioning Ducted System 604 m2 60.00$ 36,241.80$ Ventilation to Wet Areas 9 No. 300.00$ 2,700.00$ Ventilation to Kitchen 1 No. 350.00$ 350.00$ Stair Pressurisation Excl.Mechanical Ventilation to Basement Excl.
Fire ProtectionBooster - Sprinkler Excl. -$ Fire Sprinklers to Basement Excl. -$ Fire Sprinklers to Upper Levels Excl. -$ Booster - Hydrant Excl. -$ Diesel Pump Excl. -$ Fire Hydrant Per Level Excl. -$ Fire Indicator Panel (FIP) Excl. -$ Emergency Warning & Intercommunication System (EWIS) Excl. -$ Thermal Detectors Excl. -$ Smoke Detectors 5 No. 180.00$ 900.00$
Electrical Light & PowerElectrical Services (Units) 1 Units 20,000.00$ 20,000.00$ Electrical Services (Commercial) N/A Item N/A N/ATemporary Electrical Boards 1 No. 1,000.00$ 1,000.00$ Connection Fees 1 No. 250.00$ 250.00$ Substation Excl.Light fittings to Units 1 No. 2,500.00$ 2,500.00$ Light fittings to Parking Areas 357 m2 8.00$ 2,854.80$ Light fittings to External Areas 1 Item 500.00$ 500.00$
Transportation SystemsPassenger Lift 3 levels 1 Item 60,000.00$ 60,000.00$ Escalators & Moving Walks Excl. -$ Car Lift Excl. -$ Turn Tables Excl. -$
Special ServicesLaundry Chute 1 No. 500.00$ 500.00$ Garbage Chute Per Level Excl. -$ Garbage Carousel & Compactor Excl. -$
EXTERNAL WORKSLandscaping 615 m2 45.00$ 27,696.60$ Pathway incl. Pavers 8 m2 150.00$ 1,254.00$ Stepping Stones 1 Item 5,000.00$ 5,000.00$ Planterbox / Retaining Walls 13 m 320.00$ 4,227.20$ Allowance for pool construcion incl. filtration 1 Item 45,000.00$ 45,000.00$ Tiling to pool surrounding 75 m2 150.00$ 11,248.50$ BBQ area joinery 1 No. 2,500.00$ 2,500.00$ Pool Fencing to above. 23 m 280.00$ 6,319.60$ Outside Boundary Works 20 m 650.00$ 13,071.50$ Front Fencing 20 m 380.00$ 7,641.80$ External Gates 1 No. 550.00$ 550.00$ Boundary/Divisional Fencing 148 m 70.00$ 10,367.00$
1,547,827.70$
Preliminaries & Labour 13.75% % 212,826.31$ Profit & Overheads 8.50% % 149,655.59$
1,910,309.59$
Subtotal (Trades)
Total Construction Cost (Excluding GST)
Q2020-CR173 11
Appendix C
www.capital-qpc.com.au
QPC & C Pty LimitedABN 78 074 731 963
Office Address:Level 1, 1 Bells Road,Oatlands, NSW, 2117
P 02 9638 5522E [email protected]
Client: Urban Link
Project Description: Residential Dwelling with Basement Parking
Project Address: 17 Firth Avenue, Strathfield NSW
Date: 17th August 2020
BASEMENT
Perimeter Walls: Dincel
Mechanical Ventilation Excluded
Fire Sprinklers Excluded
STRUCTURE
Generally Load Bearing Brickwork Structure
Perimeter Walls Rendered Finish
Upper Levels Concrete Slabs
Roof Type Concrete Roof Structure / Framed Roof
Roof Finish Waterproof / Roof Tiles
Windows & Doors: Powdercoated Aluminium Framed
Balcony Balustrades: Powdercoated Aluminium Framed
Passenger Lift Included
INTERNAL
Doors: Hollow doors
Door Furniture: Satin Chrome Lever
Wardrobes: Sliding Mirror Wardrobe
Walls: Plasterboard & Paint
Ceilings: Plasterboard & Paint
Cornice: Shadowline
Skirting/Architrave: 92mm MDF (Selected Profile)
Air Conditioning: Ducted System
Blinds: Vertical Fabric Blinds
Intercom: Included
Alarm: Included
FLOOR FINISHES
Bedrooms: Carpet
Living & Dining: Tiles
Kitchens: Tiles
Bathroom, Ensuite, Laundry: Tiles
Balcony: Tiles
KITCHEN
Joinery: Polyurethane Finish Floor & Wall Cupboards
Cupboard Hardware: Stainless steel handles or concealed
Benchtop: 40mm Ceaserstone or similar
Splashback: 20mm Stone
Sink: Double Bowl Undermount
SCHEDULE OF FINISHES
Q2020-CR173 13
APPLIANCES
Oven: 90cm Stainless steel oven with digital clock.
Cooktop: 90cm Stainless steel 4 burner incl wok.
Rangehood: 90cm Stainless steel slide out range.
Dishwasher: 90cm Stainless steel dishwasher.
Microwave: Excluded
Dryer: Excluded
Hot Water System: Gas Instantaneous fixed in recess box.
BATHROOM & ENSUITE
Vanity: Polyurethane Cabinet with 20mm stone top.
Basin: Included in Vanity
Mirror: Full width of vanity hung on wall.
Shower Screen: Frameless Shower Screen
Toilet Suite: Concealed Cistern Suite
Accessories: All accessories to be chrome.
Floor Waste: Smart Tile Floor Waste
LAUNDRY
Tub: 45 Litre tub and cabinet
Tapware: Flick mixer with telescopic spout.
Splashback: Wall Tiles
Q2020-CR173 14