24
June 12, 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and Herzegovina

Reform of the Renewable Energy Support Scheme System in ... · (solar and hydro power) Page 12 12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and Herzegovina

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • June 12, 2019

    Reform of the Renewable Energy Support Scheme System in Bosnia and Herzegovina

  • Working Group Members for the Reform of the RE Support Schemes in Bosnia and Herzegovina

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 2

  • ▪ The “RE world” dramatically changed since existing support schemes were introduced

    o Tremendous development of RE generation installed capacities

    o Extraordinary technology improvement

    o Significant price drop per installed kW

    o Challenges in networks related to higher feed-in of intermittent RE

    o New EU regulation for RE reflects the recent developments

    ▪ RE targets for RES based electricity cannot be fulfilled through existing support

    systems in BIH

    ▪ BIH needs to continue RE support with the objective to reach point where support will

    not be needed in a near/mid future

    ▪ Future RE support scheme must be more cost-efficient and should be market-based /

    competitive

    Motivation and Need for the Reform

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 3

  • Renewable Energy Auctions Reduce Support Cost

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 4

    Auction processes for renewable energy support level setting have reduced support cost worldwide

    Selected empirical evidence from the EU Selected empirical evidence from Latin America

  • ▪ New RES support schemes are transparent and non-discriminatory – auctions are

    introduced instead of “allocation by the order of application” (first come – first serve)

    ▪ Different support schemes for small and large RES installations

    ▪ New RES support schemes provide:

    o Either more projects, i.e. MW/MWh from RES than so far, for the same spent funds,

    o Or the same amount of projects, i.e. MW/MWh from RES as so far, for less spent funds

    ▪ Significant improvements are proposed in legal/regulatory framework for consumers

    that produce electricity for own needs (Prosumers)

    ▪ Institution of so called community energy projects is introduced in legal-regulatory

    framework for RES

    Basic Features of the New RE Support Schemes in BIH

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 5

  • ▪ Usage of positive practice of others, predominantly European countries, during

    creation of concept of new RES support scheme

    ▪ Selective application of experiences of other countries, respecting specificity of

    electricity sector in BIH

    ▪ Starting points are:

    o Existing legislation on RES, and linked to RES

    o Proposal of existing legal-regulatory framework modification and amendment

    ▪ Adaptation of the proposed model to specificities of the institutional set-up in BIH

    (model is developed as unique, while proposals for implementation are made and

    adjusted to individual entities and Brčko District)

    ▪ Modification of business processes of competent institutions for implementation of

    new support schemes - for all institutions, on different levels of authorities in BIH

    Approach for Change of RES Support Shemes in BIH

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 6

  • ▪ Large scale installations: Remuneration based on Feed in premium and Wholesale-Price/Reference Market Price

    Threshold is technology specific and between 250 and 500 kW (tbd)

    ▪ Small scale installations: Remuneration based on Feed in Tariff or Net Billing (up to defined capacity limit)

    General Concept

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 7

  • ▪ RES support in BIH is divided by:

    o RES capacity that is supported, on:

    • Support for large installations*, and

    • Support for small installations

    o Type of support, on:

    • Direct support (FIP, FIT and tax rebates), and

    • Indirect support (participation in balancing costs, priority dispatching, network connection costs, etc.)

    o Allocation support methods, on:

    • Auction (open or site specific auctions), and

    • Administrative (based on expert estimation)

    ▪ Proposed support schemes are combination of these variants

    * → Threshold between large and small installations differ by RES technologies to be defined

    Division of RES Support

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 8

  • Support for Large RES Installations

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 9

    Wind,

    Solar &

    Hydropower

    Biomass

    & Biogas

  • Support for Small RES Installations

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 10

  • ▪ Threshold to be defined by the proposed modifications and amendments of the existing

    legal-regulatory RES framework

    ▪ It should be analyzed and defined separately for each technology

    ▪ Criteria for threshold definition should be:

    o techno-economic potential for certain technologies

    o technological limitations

    o commercial limitations

    o determination to support certain technologies

    Threshold between large and small RES Installations

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 11

    TechnologyThreshold

    (kW)

    Solar 250

    Hydro 250

    Wind 150

    Biomass 500

    Biogas 500

    Proposed threshold between small and large RE installations by categories

  • Technology categories for small scale installations I (solar and hydro power)

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 12

    Technology Category (kW) Support

    Solar – Rooftop and integrated < 10 FIT fixed or net-billing

    10 – 50 FIT fixed or net-billing

    50 – 250 FIT linear decrease or net-billing up to

    X kW

    Solar – Ground mounted < 100 FIT fixed or net-billing up to X kW

    100 – 250 FIT linear decrease

    > 250 FIP – open auction

    Hydro Power Plants < 50 Net-billing

    50 – 250 FIT linear decrease or net-billing up to

    X kW

    250 – 10 000 FIP – open auction

    250-x FIP - site-specific auction, if of strategic

    interest for the government

  • 12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 13

    Wind Power Plants < 150 FIT or net-billing up to X kW

    150 – 30 000 FIP – open auction

    Biomass (solid) from forestry,

    wood, industry and agriculture

    < 150 FIT fixed or net-billing up to X

    kW

    150 - 500 FIT fixed

    500 – 1 000 FIP linear decrease

    1 000 -10 000 FIP linear decrease

    Biogas

    (Focus on farm and agro-

    industrial residues with a

    possible complementation

    share of energy-crops)

  • Recommendation for open auction design I

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 14

    Auction design features Explanation

    Technology type and size Large scale installations, solar, hydro and wind

    Type of auction Capacity based, Bidders are bidding for capacity

    Type of awarded support Feed-in-premium added to the reference market price/day-ahead market price

    Auction on the Entity levelEntity level provides maximum geographical extension in current circumstances, which enhances

    competition

    PeriodicityAuctions are organized each two years (biannually), which should be an adequate period fitting to

    conditions in BIH

    Typical auction limit

    • 30 MW for solar

    • 50 MW for hydro

    • 50 MW for wind

    Sealed bid, pay as bid Winner selection based on price only guarantees efficiency

    Selection criteria in tie-break bids Preference should be provided to the smaller projects, to enhance competition

  • Recommendation for open auction design II

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 15

    Auction design features Explanation

    Prequalification for Bidders

    Prequalification requirements enable participation of serious Bidders / Investors, on the basis of

    developed project plan and obtained licenses, permits and concessions (to be defined in Rulebook on

    auctions)

    Open for prequalified Bidders Only Bidders / Investors that pass prequalification process are invited to participate in auction

    Requested submission of bid bonds Bid bond is secured by Bidders with objective to prevent non-installation

    Bid subject to capacity cap

    Medium size cap allows for sufficient number of winners (competition!) and making use of economies

    of scale (to be defined in that way, that a competitive bidding of min. 3 bidders will be possible

    according to a prior market evaluation)

    Retention of bid bonds for

    penalization

    In case of non-installation or delay in installation, bind bond is retained. Bid bond amount should be in

    range 1.5 – 2% of average upfront investment cost calculated per kW

    Lead time for finishing installationIt is recommended to be two years, from the end of auction. In case there are known grid connection

    problems and delays in licenses, this period should be extender for half a year

  • 12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 16

    Auction design features Explanation

    Technology type and size Large scale installations, hydro, project with specific strategic public interest

    Type of auction Project based, Bidders are bidding for project which is pre-developed by the auctioneer

    Type of awarded support Feed-in-premium added to the reference market price/day-ahead market price

    Auction on the Entity levelEntity level provides maximum geographical extension in current circumstances, which

    enhances competition

    Sealed bid, pay as bid Winner selection based on price only guarantees efficiency

    Recommendation for site specific auction design I

  • 12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 17

    Auction design features Explanation

    Prequalification for BiddersPrequalification requirements enable participation of serious Bidders / Investors, on the

    basis of developed project plan and obtained licenses

    Open for prequalified BiddersOnly Bidders / Investors that pass prequalification process are invited to participate in

    auction

    Requested submission of bid bonds Bid bond is secured by Bidders with objective to prevent non-installation

    Retention of bid bonds for penalizationIn case of non-installation or delay in installation, bind bond is retained. Bid bond amount

    should be in range 1.5 – 2% of average upfront investment cost calculated per kW

    Lead time for finishing installationIt is recommended to be two years, from the end of auction. In case there are known grid

    connection problems and delays in licenses, this period should be extender for half a year

    Recommendation for site specific auction design II

  • Quantitative Analysis: Targets and Assumptions

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 18

    ▪ Quantitative analysis to investigate RE support cost

    for BIH

    ▪ Based on assumptions from official Framework

    Energy strategy & data on RE from international

    studies

    ▪ Price & demand development forecast based on

    World Bank study

    ▪ Tool provided to investigate support cost under

    different scenarios

    ▪ To achieve the 2030 target (48,1% of total RES in

    FEC, under discussion), an additional VRE capacity

    of around 2.500 MWel would be needed

    ▪ Results shown here are based on medium value

    scenario 2020-2030 from Framework Energy Strategy

    additional VRE capacity of around 700 MWel

    145

    678

    283

    425

    283

    162

    287

    283

    425

    283

    21

    84

    81

    122

    81

    21

    36

    41

    62

    88

    0

    200

    400

    600

    800

    1000

    1200

    2020 2030 - High value 2030 - Median value 2030 - 1.5x Target 2030 - Biomass FullPotential

    MW

    Wind SHPP Solar Biomass/Biogas

    Targets

  • ▪ RE sources should finally have complete balancing responsibility, as all other

    participants on the electricity market in BIH (except very small RES installations,

    for example Pi ≤ 100kW)

    ▪ Changes and amendments of the Law on RES in entities are necessary:

    o In RS current limitation should be „defrosted“ and trajectory for achievement of 100%

    of balance responsibility should be defined through the period of the several years

    o In FBIH balance responsibility should be defined in the Law on RES

    ▪ Balance intervals and schedule intervals should be 1h and 15’

    ▪ Good solution is separated balance groups for RES on the level of entities, or on

    the level of network operators

    ▪ Legislations should introduce institution of Aggregator for small RES installations

    and Prosumers

    ▪ Key roles of Network Operators and Operators for RES in implementation

    Indirect Support - Balancing

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 19

  • Net Billing

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 20

    Net billing for production for

    own needs should

    compensate excess (surplus)

    of delivered electricity based

    on energy component of retail

    price, decreased by suppliers

    expenses.

    ▪ In accordance with the Energy Community Guidelines, producers for own needs should have

    possibility to choose support scheme between net billing and FIT as alternative.

    ▪ Network tariffs for producers for own needs within net billing should have significant capacity

    component, and small energy component, with a purpose of charging for network connection.

    ▪ VAT, as well as other fees and taxes, if any, should be applied only on the net consumption

    (within predefined time period)

  • Definition of RE community energy according to RED:

    „Renewable energy community means a legal entity, including cooperatives

    i. which, according to applicable national law, is based on open and

    voluntary participation, is autonomous, and is effectively controlled by

    shareholders or members that are located in the proximity of the

    renewable energy projects owned and developed by that community;

    ii. whose shareholders or members are natural persons, local authorities,

    including municipalities, or SMEs;

    iii. whose primary purpose is to provide environmental, economic or social

    community benefits for its members or the local areas where it operates

    rather than financial profits.“

    Community Energy Projects (1)

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 21

  • ▪ Through the benefits of the realization of the community energy projects, part of the

    RES support funds returns to the „place of origin“ - end consumers of electricity in BIH.

    ▪ Implementation of Community Energy projects significantly increases awareness of the

    importance and value of the RES

    ▪ It is necessary to enable participation of community energy projects within foreseen

    main and complementary support schemes, such as:

    o Net billing

    o FiT for small installations / FiP for large installations

    o Supplementary exemption of taxes and fees payment (not part of the reform)

    ▪ Community energy projects should be additionally supported through:

    o Development of changes and amendments in relevant legal and regulatory framework

    o Definition of quotas/upper limits for community energy projects ,

    o Inclusion of Community Energy projects in strategies, action plans and RES targets

    Community Energy Projects (2)

    12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 22

  • 12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 23

    Jun‘19 Oct‘19Aug‘19

    Preparation within Working Group of Final

    Working Package consisting in:

    ✓ Draft Legislation

    ✓ Draft PPA/FAA templates

    ✓ Cost calculation methodology

    ✓ Guidelines for institutions and investors

    ✓ Accompanying documents for definition

    of institutional set-up and processes

    Preliminary Consultation Events

    Jan‘20 Jan‘21

    Final Consent of Policy Makers

    Final review and adjustment of Reform

    (Levels of FIT/FIP, thresholds, roles,

    technology quotas&volumes)

    Adoption of Legislation for

    Reform

    Final Consultation (institutions websites, events)

    Reform in

    Place

    Preliminary Consent of Policy Makers

    Timetable of Reform

  • Deutsche Gesellschaft für

    Internationale Zusammenarbeit (GIZ) GmbH

    Registered offices

    Bonn and Eschborn

    Friedrich-Ebert-Allee 36 + 40

    53113 Bonn, Germany

    T +49 228 44 60 - 0

    F +49 228 44 60 - 17 66

    E [email protected]

    I www.giz.de

    Dag-Hammarskjöld-Weg 1 - 5

    65760 Eschborn, Germany

    T +49 61 96 79 - 0

    F +49 61 96 79 - 11 15