Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
June 12, 2019
Reform of the Renewable Energy Support Scheme System in Bosnia and Herzegovina
Working Group Members for the Reform of the RE Support Schemes in Bosnia and Herzegovina
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 2
▪ The “RE world” dramatically changed since existing support schemes were introduced
o Tremendous development of RE generation installed capacities
o Extraordinary technology improvement
o Significant price drop per installed kW
o Challenges in networks related to higher feed-in of intermittent RE
o New EU regulation for RE reflects the recent developments
▪ RE targets for RES based electricity cannot be fulfilled through existing support
systems in BIH
▪ BIH needs to continue RE support with the objective to reach point where support will
not be needed in a near/mid future
▪ Future RE support scheme must be more cost-efficient and should be market-based /
competitive
Motivation and Need for the Reform
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 3
Renewable Energy Auctions Reduce Support Cost
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 4
Auction processes for renewable energy support level setting have reduced support cost worldwide
Selected empirical evidence from the EU Selected empirical evidence from Latin America
▪ New RES support schemes are transparent and non-discriminatory – auctions are
introduced instead of “allocation by the order of application” (first come – first serve)
▪ Different support schemes for small and large RES installations
▪ New RES support schemes provide:
o Either more projects, i.e. MW/MWh from RES than so far, for the same spent funds,
o Or the same amount of projects, i.e. MW/MWh from RES as so far, for less spent funds
▪ Significant improvements are proposed in legal/regulatory framework for consumers
that produce electricity for own needs (Prosumers)
▪ Institution of so called community energy projects is introduced in legal-regulatory
framework for RES
Basic Features of the New RE Support Schemes in BIH
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 5
▪ Usage of positive practice of others, predominantly European countries, during
creation of concept of new RES support scheme
▪ Selective application of experiences of other countries, respecting specificity of
electricity sector in BIH
▪ Starting points are:
o Existing legislation on RES, and linked to RES
o Proposal of existing legal-regulatory framework modification and amendment
▪ Adaptation of the proposed model to specificities of the institutional set-up in BIH
(model is developed as unique, while proposals for implementation are made and
adjusted to individual entities and Brčko District)
▪ Modification of business processes of competent institutions for implementation of
new support schemes - for all institutions, on different levels of authorities in BIH
Approach for Change of RES Support Shemes in BIH
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 6
▪ Large scale installations: Remuneration based on Feed in premium and Wholesale-Price/Reference Market Price
Threshold is technology specific and between 250 and 500 kW (tbd)
▪ Small scale installations: Remuneration based on Feed in Tariff or Net Billing (up to defined capacity limit)
General Concept
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 7
▪ RES support in BIH is divided by:
o RES capacity that is supported, on:
• Support for large installations*, and
• Support for small installations
o Type of support, on:
• Direct support (FIP, FIT and tax rebates), and
• Indirect support (participation in balancing costs, priority dispatching, network connection costs, etc.)
o Allocation support methods, on:
• Auction (open or site specific auctions), and
• Administrative (based on expert estimation)
▪ Proposed support schemes are combination of these variants
* → Threshold between large and small installations differ by RES technologies to be defined
Division of RES Support
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 8
Support for Large RES Installations
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 9
Wind,
Solar &
Hydropower
Biomass
& Biogas
Support for Small RES Installations
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 10
▪ Threshold to be defined by the proposed modifications and amendments of the existing
legal-regulatory RES framework
▪ It should be analyzed and defined separately for each technology
▪ Criteria for threshold definition should be:
o techno-economic potential for certain technologies
o technological limitations
o commercial limitations
o determination to support certain technologies
Threshold between large and small RES Installations
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 11
TechnologyThreshold
(kW)
Solar 250
Hydro 250
Wind 150
Biomass 500
Biogas 500
Proposed threshold between small and large RE installations by categories
Technology categories for small scale installations I (solar and hydro power)
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 12
Technology Category (kW) Support
Solar – Rooftop and integrated < 10 FIT fixed or net-billing
10 – 50 FIT fixed or net-billing
50 – 250 FIT linear decrease or net-billing up to
X kW
Solar – Ground mounted < 100 FIT fixed or net-billing up to X kW
100 – 250 FIT linear decrease
> 250 FIP – open auction
Hydro Power Plants < 50 Net-billing
50 – 250 FIT linear decrease or net-billing up to
X kW
250 – 10 000 FIP – open auction
250-x FIP - site-specific auction, if of strategic
interest for the government
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 13
Wind Power Plants < 150 FIT or net-billing up to X kW
150 – 30 000 FIP – open auction
Biomass (solid) from forestry,
wood, industry and agriculture
< 150 FIT fixed or net-billing up to X
kW
150 - 500 FIT fixed
500 – 1 000 FIP linear decrease
1 000 -10 000 FIP linear decrease
Biogas
(Focus on farm and agro-
industrial residues with a
possible complementation
share of energy-crops)
Recommendation for open auction design I
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 14
Auction design features Explanation
Technology type and size Large scale installations, solar, hydro and wind
Type of auction Capacity based, Bidders are bidding for capacity
Type of awarded support Feed-in-premium added to the reference market price/day-ahead market price
Auction on the Entity levelEntity level provides maximum geographical extension in current circumstances, which enhances
competition
PeriodicityAuctions are organized each two years (biannually), which should be an adequate period fitting to
conditions in BIH
Typical auction limit
• 30 MW for solar
• 50 MW for hydro
• 50 MW for wind
Sealed bid, pay as bid Winner selection based on price only guarantees efficiency
Selection criteria in tie-break bids Preference should be provided to the smaller projects, to enhance competition
Recommendation for open auction design II
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 15
Auction design features Explanation
Prequalification for Bidders
Prequalification requirements enable participation of serious Bidders / Investors, on the basis of
developed project plan and obtained licenses, permits and concessions (to be defined in Rulebook on
auctions)
Open for prequalified Bidders Only Bidders / Investors that pass prequalification process are invited to participate in auction
Requested submission of bid bonds Bid bond is secured by Bidders with objective to prevent non-installation
Bid subject to capacity cap
Medium size cap allows for sufficient number of winners (competition!) and making use of economies
of scale (to be defined in that way, that a competitive bidding of min. 3 bidders will be possible
according to a prior market evaluation)
Retention of bid bonds for
penalization
In case of non-installation or delay in installation, bind bond is retained. Bid bond amount should be in
range 1.5 – 2% of average upfront investment cost calculated per kW
Lead time for finishing installationIt is recommended to be two years, from the end of auction. In case there are known grid connection
problems and delays in licenses, this period should be extender for half a year
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 16
Auction design features Explanation
Technology type and size Large scale installations, hydro, project with specific strategic public interest
Type of auction Project based, Bidders are bidding for project which is pre-developed by the auctioneer
Type of awarded support Feed-in-premium added to the reference market price/day-ahead market price
Auction on the Entity levelEntity level provides maximum geographical extension in current circumstances, which
enhances competition
Sealed bid, pay as bid Winner selection based on price only guarantees efficiency
Recommendation for site specific auction design I
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 17
Auction design features Explanation
Prequalification for BiddersPrequalification requirements enable participation of serious Bidders / Investors, on the
basis of developed project plan and obtained licenses
Open for prequalified BiddersOnly Bidders / Investors that pass prequalification process are invited to participate in
auction
Requested submission of bid bonds Bid bond is secured by Bidders with objective to prevent non-installation
Retention of bid bonds for penalizationIn case of non-installation or delay in installation, bind bond is retained. Bid bond amount
should be in range 1.5 – 2% of average upfront investment cost calculated per kW
Lead time for finishing installationIt is recommended to be two years, from the end of auction. In case there are known grid
connection problems and delays in licenses, this period should be extender for half a year
Recommendation for site specific auction design II
Quantitative Analysis: Targets and Assumptions
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 18
▪ Quantitative analysis to investigate RE support cost
for BIH
▪ Based on assumptions from official Framework
Energy strategy & data on RE from international
studies
▪ Price & demand development forecast based on
World Bank study
▪ Tool provided to investigate support cost under
different scenarios
▪ To achieve the 2030 target (48,1% of total RES in
FEC, under discussion), an additional VRE capacity
of around 2.500 MWel would be needed
▪ Results shown here are based on medium value
scenario 2020-2030 from Framework Energy Strategy
additional VRE capacity of around 700 MWel
145
678
283
425
283
162
287
283
425
283
21
84
81
122
81
21
36
41
62
88
0
200
400
600
800
1000
1200
2020 2030 - High value 2030 - Median value 2030 - 1.5x Target 2030 - Biomass FullPotential
MW
Wind SHPP Solar Biomass/Biogas
Targets
▪ RE sources should finally have complete balancing responsibility, as all other
participants on the electricity market in BIH (except very small RES installations,
for example Pi ≤ 100kW)
▪ Changes and amendments of the Law on RES in entities are necessary:
o In RS current limitation should be „defrosted“ and trajectory for achievement of 100%
of balance responsibility should be defined through the period of the several years
o In FBIH balance responsibility should be defined in the Law on RES
▪ Balance intervals and schedule intervals should be 1h and 15’
▪ Good solution is separated balance groups for RES on the level of entities, or on
the level of network operators
▪ Legislations should introduce institution of Aggregator for small RES installations
and Prosumers
▪ Key roles of Network Operators and Operators for RES in implementation
Indirect Support - Balancing
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 19
Net Billing
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 20
Net billing for production for
own needs should
compensate excess (surplus)
of delivered electricity based
on energy component of retail
price, decreased by suppliers
expenses.
▪ In accordance with the Energy Community Guidelines, producers for own needs should have
possibility to choose support scheme between net billing and FIT as alternative.
▪ Network tariffs for producers for own needs within net billing should have significant capacity
component, and small energy component, with a purpose of charging for network connection.
▪ VAT, as well as other fees and taxes, if any, should be applied only on the net consumption
(within predefined time period)
Definition of RE community energy according to RED:
„Renewable energy community means a legal entity, including cooperatives
i. which, according to applicable national law, is based on open and
voluntary participation, is autonomous, and is effectively controlled by
shareholders or members that are located in the proximity of the
renewable energy projects owned and developed by that community;
ii. whose shareholders or members are natural persons, local authorities,
including municipalities, or SMEs;
iii. whose primary purpose is to provide environmental, economic or social
community benefits for its members or the local areas where it operates
rather than financial profits.“
Community Energy Projects (1)
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 21
▪ Through the benefits of the realization of the community energy projects, part of the
RES support funds returns to the „place of origin“ - end consumers of electricity in BIH.
▪ Implementation of Community Energy projects significantly increases awareness of the
importance and value of the RES
▪ It is necessary to enable participation of community energy projects within foreseen
main and complementary support schemes, such as:
o Net billing
o FiT for small installations / FiP for large installations
o Supplementary exemption of taxes and fees payment (not part of the reform)
▪ Community energy projects should be additionally supported through:
o Development of changes and amendments in relevant legal and regulatory framework
o Definition of quotas/upper limits for community energy projects ,
o Inclusion of Community Energy projects in strategies, action plans and RES targets
Community Energy Projects (2)
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 22
12 June 2019 Reform of the Renewable Energy Support Scheme System in Bosnia and HerzegovinaPage 23
Jun‘19 Oct‘19Aug‘19
Preparation within Working Group of Final
Working Package consisting in:
✓ Draft Legislation
✓ Draft PPA/FAA templates
✓ Cost calculation methodology
✓ Guidelines for institutions and investors
✓ Accompanying documents for definition
of institutional set-up and processes
Preliminary Consultation Events
Jan‘20 Jan‘21
Final Consent of Policy Makers
Final review and adjustment of Reform
(Levels of FIT/FIP, thresholds, roles,
technology quotas&volumes)
Adoption of Legislation for
Reform
Final Consultation (institutions websites, events)
Reform in
Place
Preliminary Consent of Policy Makers
Timetable of Reform
Deutsche Gesellschaft für
Internationale Zusammenarbeit (GIZ) GmbH
Registered offices
Bonn and Eschborn
Friedrich-Ebert-Allee 36 + 40
53113 Bonn, Germany
T +49 228 44 60 - 0
F +49 228 44 60 - 17 66
I www.giz.de
Dag-Hammarskjöld-Weg 1 - 5
65760 Eschborn, Germany
T +49 61 96 79 - 0
F +49 61 96 79 - 11 15