ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceList

Status:December2016

DeutscheWindGuard

OldenburgerStr.65

D‐26316Varel

Germany

Tel: +49‐4451‐9515‐0Fax: +49‐4451‐9515‐29Email: [email protected]:www.windguard.de

Page 2: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 2/89

Contents

1  DeutscheWindGuardGroup–AnOverview 4 

1.1  CompanyStructure 6 1.2  KeyStaffMembers 8 1.3  MembershipinStandardisationBodies 8 1.4  Accreditations 9 1.5  CustomerReferences 11 

2  SiteAssessment 16 

2.1  WindMeasurements 16 

2.1.1  ConventionalWindMeasurementswithCupAnemometersorSonicInstruments 16 2.1.2  WindMeasurementswithLiDARorSODAR 17 

2.2  MeasurementSystemSales 18 2.3  CalibrationandClassificationofRemoteSensing 19 2.4  Long‐TermEnergyYieldAssessmentforOperatingWindFarms 22 2.5  WindResourceAssessmentsandSiteSuitabilityStudiesforProposedWindFarms 23 2.6  ConceptStudiesandPre‐EvaluationsforEnergyYieldAssessments 32 2.7  Research&DevelopmentActivitiesintheFieldofSiteAssessment 33 2.8  CalculationofNoiseEmissionintheVicinityofProposedWindFarms 34 2.9  DeterminationofShadowFlickerImpactintheVicinityofProposedWindFarms 35 2.10  VisibilityAnalysis 36 2.11  Ice‐ThrowRiskAnalysis 37 

3  DueDiligenceandConsultingServices 38 

3.1  TechnicalDueDiligence 40 3.2  StrategicDueDiligenceandAssessmentofWindTurbineTypes 41 3.3  TenderandContractConsulting 44 3.4  Markets&Politics 45 3.5  FeasibilityStudiesforWindEnergyProjects 48 3.6  Scientifictraining 49 

4  WindFarmOperation,TechnicalManagementandTurbineInspection 49 

4.1  TechnicalManagementofWindFarms 49 

4.1.1  Referenceproject:technicalmanagementofalphaventusandRiffgatoffshorewindfarms 49 

4.2  TechnicalInspectionofWindTurbines 50 4.3  VibrationMeasurements/GearBoxAnalysis 52 4.4  ThermographicBoundaryLayerVisualisationofWindTurbineRotorBladesin

Operation 55 4.5  AnalysisofWindFarmOperationalData 55 

5  WindTunnelCentre 61 

5.1  AnemometerandWindDirectionSensorCalibrationandClassification 61 

Page 3: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 3/89

5.2  2DAirfoilMeasurementsinAcousticallyOptimisedLargeWindTunnelinBremerhaven 63 

6  MeasurementsonWindTurbines 64 

6.1  WindTurbinePowerCurveTesting 64 6.2  AcousticNoiseMeasurementsonWindTurbines 66 6.3  LoadMeasurementsonWindTurbines 68 

7  Offshore‐Services 69 

7.1  Offshore‐Consulting 69 7.2  SafetyTraining 73 

8  APPENDIX 75 

8.1  ListofStudiesandScientificPolicyAdviceProjects 75 8.2  ListofFeasibilityStudiesforWindEnergyProjects 81 8.3  ListofWindTurbinesManagedbyDeutscheWindGuard(TechnicalManagement) 83 8.4  ListofScientificTrainingCourses 85 

Page 4: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 4/89

1 DeutscheWindGuardGroup–AnOverview

Intoday’scomplexenergymarket,DeutscheWindGuardiscommittedtoprovidingex‐tensivescientific,technical,andoperationalservices,whichareunbiasedandmanufac‐turer‐independent.

Thecompanywasfoundedin2000andhasbeencontinuouslyexpandingeversince.TheDeutscheWindGuardGroupisanintegratedandcomprehensivenetworkwithascien‐tific‐core leadership team and 150 experienced specialists with international experi‐ence.ThewiderangeofDeutscheWindGuard’sbusinessactivitiesprovidesusadirectinsightintoallwindenergyrelatedissues.

Today,DeutscheWindGuardisoneoftheworld’sleadingserviceproviderstorenewa‐bleenergyenterprises,utilities, investorsandpublicauthorities. Internationallyrecog‐nisedaccreditationsandcertificatesaddcertaintyandobjectivityto theassessmentofallproject‐relatedinformation.

Ourcomprehensiveservicesreliablysupportthecompletelifecycleofwindpowerpro‐jects, ranging fromfeasibilitystudies; servicesrequiredduring theplanning, construc‐tion and operation phase of wind farms; through to dismantling. Onshore. Offshore.Worldwide.

Page 5: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 5/89

Page 6: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 6/89

1.1 CompanyStructure

TheWindGuardGroupconsistsofeightcompanieswithoffices inVarel,Bremerhaven,Elsfleth and Berlin, Germany, as well as Alexandria (Virginia, USA) operating in allbranchesofwindenergy.

Theparentcompany–DeutscheWindGuardGmbH–mainlydealswiththetechnicalmanagementofwindfarmsandtechnicalinspectionsofwindturbines.Furtherworkingfieldsarepolicyconsultingandthecommissioningoftechnicalstudies.

Its subsidiaries areDeutscheWindGuardWindTunnel Services, DeutscheWindGuardConsulting,DeutscheWindGuardOffshore,DeutscheWindGuardEngineering,DeutscheWindGuardSystems,WindGuardCertification,andWindGuardNorthAmerica.

DeutscheWindGuard Consulting GmbH offers wind resource and energy yield as‐sessments,windandPowerCurveMeasurements,acousticnoisemeasurements,verifi‐cationofremotesensingdevices,salesofmeasurementsystemsandtechnicalduedili‐gence services. The company is accredited as a testing and calibration laboratory ac‐cordingtoDINENISO/IEC17025andrecognizedbyIECRE.

DeutscheWindGuardWindTunnelServicesGmbH isaleadingexpertinthefieldofanemometerandwindvanecalibration.WithaWindTunnelCentreconsistingofsevendifferent wind tunnels, they also offer research and development in the field of ane‐mometryandwindmeasurementandareaccreditedasacalibrationlaboratoryaccord‐ingtoDINENISO/IEC17025,recognizedbyIECRE,aswellasMEASNETaccreditedforthecalibrationofanemometers.

DeutscheWindGuardGmbH OldenburgerStraße65

DeutscheWindGuardConsultingGmbH D‐26316Varel

DeutscheWindGuardWindTunnelServicesGmbH

Page 7: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 7/89

DeutscheWindGuardOffshoreGmbH provides consulting for the offshorewind in‐dustry, from license planning over planning of construction and execution toO&M. Asecondfieldofoperationarecertifiedsafetytrainingsforstaffworkinginthewindin‐dustry.

DeutscheWindGuardOffshoreGmbH OldenburgerStr.65

‐‐‐OffshoreConsultingServices‐‐‐ D‐26316Varel

DeutscheWindGuardOffshoreGmbH AnderWeinkaje4

‐‐‐OffshoreSafetyTrainingCentre‐‐‐ D‐26931Elsfleth

DeutscheWindGuardEngineeringGmbHworks in the field of R&D on the aerody‐namic and acoustical optimisation of wind turbines. The large scale wind tunnel inBremerhavenoffersextensivepossibilitiesforacousticandaerodynamicmeasurementsonrotorbladeprofilesathighReynold’s‐Numbersandwindspeedsupto100m/s.

DeutscheWindGuardEngineeringGmbH Überseering7

D‐27580Bremerhaven

DeutscheWindGuardSystemsGmbHdevelopsandsellsthewindfarmmanagementsoftwareWONDER3.0.

DeutscheWindGuardSystemsGmbH Bundesallee67

D‐12161Berlin

WindGuardNorthAmerica,Inc.istheUSofficeoftheWindGuardGroupandservesasacontacthubandbasisforourUScustomers.

WindGuardNorthAmerica,Inc. 1940DukeStreet,Suite200

AlexandriaVA22314,USA

WindGuardCertificationGmbHofferstypecertificationforon‐andoffshorewindtur‐binesandtheircomponentsandprovidesanswerstoallquestionsregardinggridstabil‐ityofpowergeneratingsystems.Asanindependent,accreditedcertificationbodyitpro‐videstypecertificationandcertificationofcontinuedoperationofwindturbines,certifi‐cationofpowergeneratingplants(EZA),powergeneratingunits(EZE),andatestlabor‐atoryforelectricalgridandcontrolcharacteristics.Moredetailsaregiveninaseparatereferencelistoratwww.windguard‐certification.de

WindGuardCertificationGmbH OldenburgerStraße65

D‐26316Varel

Page 8: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 8/89

1.2 KeyStaffMembers

WindGuardpossessesextensiveexpertiseinallareasofwindenergyutilisation.Severalmembersofourstaffhavemore than25yearsofexperience in thewindenergybusi‐ness.Withmany years of national and international experience,DeutscheWindGuardstaffarepartofvariousimportantR&Dcooperations.

1.3 MembershipinStandardisationBodies

DeutscheWindGuardisanactivememberofthefollowingstandardisationbodiesinthefieldofcertifiedmeasurementsandassessmentsaswellassimilarworkinggroups:

MemberofIEC61400‐12‐1(powercurve)maintenanceteam MemberofIEC61400‐13(loads)maintenanceteam MemberofIEC61400‐15(siteassessments)maintenanceteam MemberofIECREtestinglaboratorygroup MemberoftheGermanTechnicalGuidelines(FGW)TR1expertgroupfornoise

measurements MemberoftheGermanTechnicalGuidelines(FGW)TR2expertgroupforpower

curvemeasurements MemberoftheGermanTechnicalGuidelines(FGW)TR3expertgroupforpower

quality MemberoftheGermanTechnicalGuidelines(FGW)TR4expertgroupforpower

plantbehaviour MemberoftheGermanTechnicalGuidelines(FGW)TR6expertgroupforwindpo‐

tentialandenergyyields MemberoftheGermanTechnicalGuidelines(FGW)TR8expertgroupforcertifica‐

tionofPGUandPGS MEASNET,Chairmanshipofsiteassessmentexpertgroup MEASNET,Memberofanemometercalibrationexpertgroup MEASNET,Memberofpowerperformancetestingexpertgroup MEASNET,Memberofloadmeasurementexpertgroup MemberoftheGermanWindEnergyAssociation(BWE)advisoryboardforwind

resourceandenergyyieldassessments MemberoftheGermanWindEnergyAssociation(BWE)advisoryboardfortechnical

inspectionsofwindturbines MemberofWindEuropepowercurveexpertgroup InternationalEnergyAgency(IEA)–Task26–CostofWindEnergy

Page 9: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 9/89

1.4 Accreditations

Deutsche WindGuard has implemented a quality management system accredited byDeutscheAkkreditierungsstelle(DAkkS)GmbH.MembersoftheWindGuardGroupholdanumberofaccreditationsandcertifications.

DeutscheWindGuardConsulting

DeutscheWindGuardConsultingGmbHisaccreditedbyDeutscheAkkreditierungsstelleGmbH(DAkkS)asatestinglaboratoryaccordingtoDINENISO/IEC17025:2005(DAkkSregistry‐no:D‐PL‐18020)forMeasurementofWindTurbinePowerCurves;WindMeas‐urementsatSitesandPotentialSitesofWindTurbines;SiteSpecificEnergyYieldEvalu‐ations forWindFarms;SiteSuitabilityStudies;DeterminationofNoise Immission;De‐terminationofShadow Immission;NoiseEmissionMeasurementandNoise ImmissionMeasurement,aswellasLoadMeasurementonWindTurbines.

DeutscheWindGuardConsultingGmbHisaccreditedbyDeutscheAkkreditierungsstelleGmbH (DAkkS) as a calibration laboratory according to DIN EN ISO/IEC 17025:2005(DAkkS registry‐no: D‐K‐18020) for the calibration of remote sensing devices (windspeedandwinddirection).

DeutscheWindGuardConsultingGmbHisanapprovedtestinglaboratoryforthepowerperformancecompetenceareawithintheIECREscheme.

DeutscheWindGuard Consulting GmbH is aMember ofMEASNET and is accepted byMEASNETforMeasurementsofWindTurbinePowerCurvesandWindMeasurements.

DeutscheWindGuardConsultingGmbHisholderoftheconformitysealoftheFörderge‐sellschaftWindenergieundandereDezentraleEnergien(FGWe.V.)forthemeasurementofpowercurvesandnoiseemission.

Page 10: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 10/89

Deutsche WindGuardW

i ndTunnelServicesGmbH-Vare

l-G

erm

any

-

DeutscheWindGuardWindTunnelServices

DeutscheWindGuardWindTunnel ServicesGmbH is accreditedbyDeutscheAkkredi‐tierungsstelleGmbH(DAkkS)asa calibration laboratoryaccording toDINEN ISO/IEC17025:2005 (DAkkS registry‐no: D‐K‐15140) for the calibration in the field of fluidquantitiesofvelocityofgases(anemometers)anddirectionofflow(windvanes).

Deutsche WindGuard Wind Tunnel Services GmbH is an associated Member ofMEASNETandisacceptedbyMEASNETfortheCalibrationofAnemometers.

DeutscheWindGuardWindTunnelServicesGmbHisanapprovedtestinglaboratoryfortheanemometercalibrationcompetenceareawithintheIECREscheme.

DeutscheWindGuardGmbH

Deutsche WindGuard GmbH is accredited by Deutsche Akkreditierungsstelle GmbH(DAkkS) as an inspection body (Type C) according to DIN EN ISO/IEC 17020:2012(DAkkS registry‐no: D‐IS‐11013) for inspections and endoscopic examination ofwindturbines by judging and establishing the conformity with specific and – based on anexpertopinion–withgeneralrequirements.

DeutscheWindGuardOffshoreGmbH

TheBasicSafetyTrainingCourseofDeutscheWindGuardOffshore iscertifiedbyDNVGLRenewablesCertificationaccordingtoGWOBasicSafetyTrainingStandardandBasicSafetyTrainingRefresherStandard.TheyareofficiallyrecognizedbyGWOasacertifiedtrainingprovider.DeutscheWindGuardOffshore’sHelicopterUnderwaterEscapeTrain‐ing(HUET)isalsocertifiedbyDNVGLRenewablesCertification.Furthermore,theMan‐agementSystemofDeutscheWindGuardOffshoreiscertifiedbyTÜVNordaccordingtoISO9001.

Page 11: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 11/89

1.5 CustomerReferences

AnextractofDeutscheWindGuard’scustomersisshownbelow.

WindTurbineManufacturers

Page 12: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 12/89

ProjectDevelopersand/orInvestors

Page 13: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 13/89

Page 14: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 14/89

BanksandFinanciers

Page 15: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 15/89

LiDAR/SODARManufacturers

Page 16: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 16/89

2 SiteAssessment

2.1 WindMeasurements

DeutscheWindGuardConsultingGmbHisaccreditedforwindmeasurementsandpowercurve measurements by DAkkS. Over the years, more than 240 wind measurementshavebeenperformedbyDeutscheWindGuard.Thescientificcompetenceofthecompa‐nyisconfirmedbythemembershipinrenownedboards(IEC61400‐12‐1maintenancegroups,MEASNET,GermanFördergesellschaftWindenergieundandereDezentraleEn‐ergien FGW) as well as by the scientific contribution to a large number of measure‐ments.Thedevelopmentandsaleofwindmeasurementsystemsinadditiontothesen‐sor calibration, and classification of anemometers are part of Deutsche WindGuard’sexpertise.

Deutsche WindGuard Consulting has performed high‐quality wind measurements allovertheworld.Themeasurementsareperformedaccordingtothecurrentinternationalstandards and state‐of‐the‐art technology. WindGuard has experience with cup ane‐mometry,ultra‐sonic instrumentsandremotesensingtechniques(SODARandLiDAR),seetablesbelowfordetails.

2.1.1 ConventionalWindMeasurementswithCupAnemometersorSonicInstru‐ments

Country No.ofMetMasts

Austria 1

Azores 2

Bosnia 2

Bulgaria 5

Chile 1

Cyprus 6

Estonia 4

Finland 1

France 25

Georgia 1

Germany 22

Country No.ofMetMasts

GreatBritain 14

Greece 11

Indonesia 12

Ireland 5

Italy 21

Lithuania 1

Luxembourg 1

Kazakhstan 3

Macedonia 4

Mali 1

Morocco 2

Page 17: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 17/89

Country No.ofMetMasts

Netherlands 2

Panama 5

Poland 10

Romania 16

Serbia 1

Spain 5

Sweden 30

Country No.ofMetMasts

Switzerland 5

Taiwan 1

Tunisia 8

Turkey 9

Ukraine 25

Total 262

2.1.2 WindMeasurementswithLiDARorSODAR

No. InternalProjectNo.

Country No.ofSites

YearofAssessment

Client

1 VC07187 France 2 2007 Germanmanufacturer

2 VC09080 Netherlands 1 2009 Germanmanufacturer

3 VC09114 Estonia 1 2009 Estoniandeveloper

4 VC10110 Estonia 1 2010 Estoniandeveloper

5 VC11196 Norway 1 2011 Norwegiandeveloper

6 VC12295 Germany 1 2012 Germandeveloper

7 VC13040 Germany 1 2013 Germandeveloper

8 VC13282 Germany 1 2013/2014 Germandeveloper

9 VU13002 Ukraine 1 2013 Ukrainiandeveloper

10 VC15111 Germany 1 2015 Germandeveloper

11 VC15148 Germany 1 2015 Germandeveloper

12 VC15341 Germany 1 2015 Germansupplier

13 VC16190 Germany 1 2016 GermanSupplier

Page 18: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 18/89

2.2 MeasurementSystemSales

DeutscheWindGuardoffers state‐of‐the‐artmeasurement systems inwhichwe imple‐mentedour scientific competenceofmore than25years in thewindenergy industry.Our systems are equippedwith free programmable data loggers, custom‐tailored andspecificallybuilt fortheneedsofourclients.WindGuardmeasurementsystemscanbeutilised for nearly any kind of measurement, e.g. wind measurements, power curvemeasurements,SCADAintegration,scientificresearchapplicationsorcontrol‐andmoni‐toringsystems.Theconfigurationofthemeasurementwillbeperformedtogetherwiththeclientstocatertotheirrequirements.Thesystemcanbeoperatedandconfiguredviaremoteaccessusingsatellitecommunication,cellularmobilenetworks,radiocommuni‐cationordirectlines.Thesystemscanbepoweredbygridconnection,orbysolarsupplysystemsor, if requested,withuninterruptablepowersupplyunits.The flexiblescalingandmodularexpansionallowsintegratinganykindofsignaltypee.g.analogueordigitalsignalsaswellasseveralindustrialbussystemse.g.CAN,Modbus,Profibus,RS485etc.Seetablebelowforanoverviewofsystemintegrationsproduced.

Country No.ofsystemssold

Australia 23

Austria 5

Bulgaria 19

CanaryIslands 2

China 2

Cyprus 6

CzechRepublic 5

Denmark 4

Estonia 1

Finland 3

France 8

Germany 95

GreatBritain 24

Greece 7

Italy 2

Kazakhstan 1

Country No.ofsystemssold

Latvia 1

Macedonia 6

Netherlands 5

Panama 8

Poland 11

Romania 24

Serbia 3

SouthAfrica 6

Spain 2

Sweden 19

Turkey 12

Ukraine 20

UnitedKingdom 4

USA 7

Wales 1

Total 336

Page 19: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 19/89

2.3 CalibrationandClassificationofRemoteSensing

Deutsche WindGuard has special expertise in the field of testing remote sensors, socalledLiDARandSODARsystems.Onlyoneoftwocompaniescurrently,weareaccred‐itedbytheDeutscheAkkreditierungsstelleGmbH(DAkkS)asacalibrationlaboratoryforthe calibration of remote sensing devices. As one of the few companies worldwide,WindGuardownsatestingfacilityfortheclassificationandcalibrationofLiDARandSO‐DARsystems.Asaconsequence,theknowledgeofWindGuardexpertshascontributedconsiderably to thedevelopmentof international standardsandguidelines for remotesensingtechniques.

No. InternalProjectNo.

LiDAR/

SODAR

NumberofEquip‐Equip‐ment

YearofAssess‐sess‐ment

Verifi‐cationTest

Classifi‐cationTest

Client

1 VC05050 LiDAR 1 2005 X X Britishsupplier

2 VC07187 LiDAR 1 2008 X X Germanmanufacturer

3 VC07187 LiDAR 1 2010 X Germanmanufacturer

4 VC08017 LiDAR 1 2008 X Frenchsupplier

5 VC08036 LiDAR 1 2008 X Italiandeveloper

6 VC08115 LiDAR 1 2008 X Frenchsupplier

7 VC08122 LiDAR 1 2008 X USdeveloper

8 VC08205 LiDAR 2 2008 X Britishdeveloper

9 VC09114 LiDAR 1 2009 X Estoniandeveloper

10 VC09136 SODAR 1 2009 X X Swedishsupplier

11 VC10014 LiDAR 2 2010 X Frenchsupplier

12 VC10110 LiDAR 1 2010 X Estoniandeveloper

13 VC10138 LiDAR 1 2010 X USconsultant

14 VC10160 SODAR 1 2010 X USsupplier

15 VC10220 LiDAR 1 2011 X USsupplier

16 VC10222 LiDAR 1 2011 X USsupplier

17 VC11019 LiDAR 1 2011 X Britishdeveloper

18 VC11019 SODAR 1 2011 X Britishdeveloper

19 VC11174 LiDAR 1 2011 X Britishsupplier

20 VC11196 LiDAR 1 2011 X Norwegiandeveloper

21 VC11215 LiDAR 1 2011 X X Frenchsupplier

22 VC11218 LiDAR 1 2011 X Britishsupplier

23 VC12005 LiDAR 2 2012 X Frenchsupplier

24 VC12083 LiDAR 1 2012 X Britishsupplier

Page 20: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 20/89

No. InternalProjectNo.

LiDAR/

SODAR

NumberofEquip‐Equip‐ment

YearofAssess‐sess‐ment

Verifi‐cationTest

Classifi‐cationTest

Client

25 VC12295 LiDAR 1 2012 X Germandeveloper

26 VC12382 LiDAR 1 2012 X Danishdeveloper

27 VC12005 LiDAR 3 2013 X Frenchsupplier

28 VC12302 SODAR 1 2013 X Swedishdeveloper

29 VC13088 LiDAR 2 2013 X Germandeveloper

30 VC13045 LiDAR 1 2013 X Germandeveloper

31 VC13046 LiDAR 1 2013 X Germandeveloper

32 VC13118 LiDAR 2 2013 X Germandeveloper

33 VC11241 LiDAR 1 2013 X Germanconsultant

34 VC13269 LiDAR 1 2013 X Israelisupplier

35 VC13282 LiDAR 1 2013 X Germandeveloper

36 VC14253 SODAR 1 2014 X USdeveloper

37 VC14432 SODAR 1 2014 X Australiansupplier

38 VC14070 LiDAR 3 2014 X Germandeveloper

39 VC14079 LiDAR 1 2014 X Frenchdeveloper

40 VC14104 SODAR 1 2014 X X Finnishdeveloper

41 VC14069 SODAR 1 2014 X Australiansupplier

42 VC14167 LiDAR 1 2014 X Germandeveloper

43 VC13361 LiDAR 1 2014 X Danishdeveloper

44 VC14267 LiDAR 1 2014 X Germandeveloper

45 VC14302 LiDAR 1 2014 X Germandeveloper

46 VC14117 LiDAR 1 2014 X Frenchsupplier

47 VC14359 LiDAR 1 2014 X Frenchsupplier

48 VC14303 LiDAR 1 2014 X Germandeveloper

49 VC15140 LiDAR 1 2015 X Germansupplier

50 VC15081 LiDAR 1 2015 X Frenchdeveloper

51 VC15263 LiDAR 1 2015 X Germansupplier

52 VC15316 LiDAR 1 2015 X Germandeveloper

53 VC15222 LiDAR 2 2015 X Britishconsultant

54 VC15305 LiDAR 1 2015 X Netherlanddeveloper

55 VC15740 LiDAR 1 2015 X Germansupplier

Page 21: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 21/89

No. InternalProjectNo.

LiDAR/

SODAR

NumberofEquip‐Equip‐ment

YearofAssess‐sess‐ment

Verifi‐cationTest

Classifi‐cationTest

Client

56 VC15459 LiDAR 1 2015 X Germanmastsupplier

57 VC15442 LiDAR 3 2015 X Germansupplier

58 VC15465 SODAR 1 2015 X Germanconsultant

59 VC15480 LiDAR 1 2015 X Germandeveloper

60 VC16007 Lidar 1 2016 X GermanConsultant

61 VC16016 Lidar 1 2016 X GermanConsultant

62 VC16015 Lidar 1 2016 X GermanConsultant

63 VC16216 Lidar 1 2016 X GermanConsultant

64 VC16266 Lidar 1 2016 X GermanConsultant

65 VC16365 Lidar 1 2016 X GermanConsultant

66 VC16418 Lidar 2 2016 X ChineseDeveloper

67 VC16431 Lidar 1 2016 X GermanConsultant

68 VC16456 Lidar 1 2016 X GermanConsultant

69 VC16484 Lidar 1 2016 X GermanConsultant

Page 22: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 22/89

2.4 Long‐TermEnergyYieldAssessmentforOperatingWindFarms

The long‐termassessment of the energyproduction gives an outlook on the expectedlong‐termenergyyieldofoperatingwindfarms.Itisbasedonadetailedanalysisoftheproduction data from the past operating period of thewind turbines. The short‐termproductiondataiscorrelatedwithverifiedlong‐termwinddatafromdifferentsources.Wehaveperformedthiskindofserviceforalmost100windfarmswithatotalcapacityofroughly1500MW.

Country Long‐TermPredictionforOperatingWindFarms

[‐] [MW]

France 41

Germany 1408

Netherlands 31

Portugal 18

Total 1498

Page 23: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 23/89

2.5 WindResourceAssessmentsandSiteSuitabilityStudiesforPro‐posedWindFarms

Basedon solid experience inwind resource assessments, the following steps are per‐formedwithintheframeworkofanenergyyieldassessmentforaproposedwindfarm:

Evaluationofon‐sitewindmeasurementdatabymeansofspecificproceduresde‐velopedbyDeutscheWindGuard,includingadetailedcheckofmeasurementdata(e.g.in‐situcalibrationoftheutilisedcupanemometersinordertoevaluatetheirconsistencyduringthecourseofmeasurements,correctionofmastdisturbanceonanemometerreadings,fillingofdatagapsbyspecificcorrelationmethods,correctionofdynamicanemometercharacteristics)

Long‐termcorrelationofon‐sitewindmeasurementdatabymeansofspecificpro‐ceduresdevelopedbyDeutscheWindGuard,includingverificationoftheavailablelong‐termdatabydetailedcomparisonofdifferentdatasources(e.g.reanalysisdata,datafrommeteorologicalgroundstations)

Flowmodelling,optionalapplicationofthree‐dimensionalflowmodels(CFD) Minimisationoftheoveralluncertaintyofthewindresourceassessmentbydeter‐

mininganoptimisedweightingoftheavailabledatasourcesusingiterativeproce‐dures

Analysisofassumedwindturbinepowercurvesfortheenergyyieldcalculation;harmonisationofpowercurvesandpredictedwindconditionsregardingtheutilisedcupanemometertypes

Detaileduncertaintyanalysisandriskevaluation Assessmentofthetechnicallosses(e.g.lossesduetotechnicalnon‐availabilityofthe

windturbines,electricaltransmissionlosses,site‐specificcalculationoficinglossesincoldclimatebasedonmeteorologicaldata,etc.)

IECsiteclassification(i.e.sitesuitabilitystudy),includingevaluationofaverageandextremewindconditions,flowinclination,verticalwindshear,airdensity,turbu‐lenceconditions(incl.additionalturbulenceintensityduetowindturbinewakes),etc.

Specificallydevelopedknow‐howinthefieldofoffshorewindenergy Detaileddocumentationandbankablereportsincludingsolidassessmentofrisks

andtechnicallossfactors Developmentandrealisationofsupplementaryenergyyieldassessmenttechniques,

partiallywithmarketleadershipofDWG:detailedtimeseriesbasedwindfarmoper‐ationaldataevaluation,postconstructionenergyyieldassessment,calculationpro‐ceduresforlossassessmentsduetogridconstraints,calculationproceduresfortimeseriesbasedcalculationofenergyyieldcompensationsduetooffshoregriddelay

Anoverviewof the energyyield assessmentsof onshore sitesperformedbyDeutscheWindGuardisshowninthetablebelow.Sofar,onshoreenergyyieldassessmentshavebeenperformedforanoverallinstalledcapacityofmorethan20500MW.

Page 24: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 24/89

Country EnergyYieldAssessmentforProposedWind

Farms

[‐] [MW]

Australia 232

Austria 184

Belgium 68

Bosnia 115

Bulgaria 40

Chile 2

China 182

Estonia 284

Finland 100

France 780

Georgia 203

Germany 5370

GreatBritain 591

Greece 292

Honduras 7

Hungary 114

Ireland 578

Italy 1150

Country EnergyYieldAssessmentforProposedWind

Farms

Jamaica 26

Kazakhstan 425

Korea 78

Lithuania 123

Mexico 729

Morocco 266

Netherlands 516

Panama 191

Poland 698

Romania 560

Serbia 875

Spain 86

Sweden 796

Switzerland 138

Taiwan 662

Turkey 2623

Ukraine 321

USA 1119

Total 20524

EnergyyieldassessmentsforoffshoresitesmainlyintheNorthandBalticSeahavebeenperformedforanoverallinstalledcapacityofmorethan14000MW.Detailsareshowninthetablebelow.

No. ProjectNo.Year

ProjectName,RatedPower

TypeofServices Client

1 VC03125

2003

GermanBight,siteconfidential,80MW

Winddataanalysis,AssessmentofWindFarmEnergyYield,Sensitivitystudyonwindtur‐binepowercurves

confidential

2 VC04153

2004

GermanBight,siteconfidential,400MW

Winddataanalysis,AssessmentofWindFarmEnergyYield,Sensitivitystudyonwindtur‐binepowercurves

confidential

Page 25: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 25/89

No. ProjectNo.Year

ProjectName,RatedPower

TypeofServices Client

3 VC05123

2005

BalticSea,confi‐dential,400MW

Winddataanalysis,Mesoscaleflowmodel‐ling,AssessmentofWindFarmEnergyYield,Sensitivitystudyonwindturbinepowercurves

VentotecGmbH

4 VC05226

2005

GermanBight,siteconfidential,400MW

Winddataanalysis,AssessmentofWindFarmEnergyYield,Sensitivitystudyonwindturbinepowercurves,Inclusionoffardis‐tancewindfarmsinwakeanalysis,Sitesuita‐bilitystudy,Optimisationofwindfarmlayout

ENOVAEner‐gieanlagenGmbH

5 VC05226

2005

GermanBight,siteconfidential,80MW

Winddataanalysis,AssessmentofWindFarmEnergyYield,Sensitivitystudyonwindturbinepowercurves,Sitesuitabilitystudy,Optimisationofwindfarmlayout

EWEAG/ENOVA

6 VC05245

2005

China,siteconfi‐dential,upto200MW

Winddataanalysis,AssessmentofWindFarmEnergyYield

confidential

7 VC08189

2008

BalticSea,siteconfidential,400MW

Winddataanalysis,Mesoscaleflowmodel‐ling,AssessmentofWindFarmEnergyYield,Sensitivitystudyonwindturbinepowercurves,Sitesuitabilitystudy,Optimisationofwindfarmlayout

BFC‐EnergieConsultGmbH

8 VC09027

2009

GermanBight,siteconfidential,upto800MW

Winddataanalysis,AssessmentofWindFarmEnergyYield,Sitesuitabilitystudy,Op‐timisationofwindfarmlayout

InnogyNord‐see1GmbHc/oRWEIn‐nogyGmbH

9 VC09028

2009

nearshorewindfarm,confiden‐tial,100MW

Winddataanalysis,AssessmentofWindFarmEnergyYield

VentolinesB.V.

10 VC09219

2009‐2011

AmrumbankWest,upto480MW

Winddataevaluationincludingwindtunnelcalibrationofinstallationdevices,AssessmentofWindFarmEnergyYield,AssessmentofSiteParametersasrequiredfortheDesignBasis,CombinedEvaluationofwindandMetOceandata,Sensitivitystudyonwakeinfluences,Assessmentofdailyvariationofpoweroutputontimeseriesbasis

AmrumbankWestGmbH,c/oE.ONCli‐mate&Re‐newablesCentralEu‐ropeGmbH

11 VC10158

2010‐2011

Arkona‐BeckenSüdost,upto480MW

Winddataevaluationincludingwindtunnelcalibrationofinstallationdevices,AssessmentofWindFarmEnergyYield,AssessmentofSiteParametersasrequiredfortheDesignBasis,CombinedEvaluationofwindandMetOceandata,Performanceoflayoutopti‐misationswithconsiderationofcomplexwindfarmrestrictions

AWEArkonaWindparkEntwicklungs‐GmbH,c/oE.ONClimate&RenewablesCentralEu‐ropeGmbH

Page 26: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 26/89

No. ProjectNo.Year

ProjectName,RatedPower

TypeofServices Client

12 VC10249

2010‐2011

DeltaNordsee,upto480MW

Winddataevaluation,AssessmentofWindFarmEnergyYield,AssessmentofSitePa‐rametersasrequiredfortheDesignBasis,CombinedEvaluationofwindandMetOceandata,Performanceofsensitivitystudiesonwakeinfluences,Performanceoflayoutopti‐misations

c/oE.ONCli‐mate&Re‐newablesCentralEu‐ropeGmbH

13 VC11009

2011

Kårehamn(Swe‐den),upto50MW

Winddataevaluation,AssessmentofWindFarmEnergyYield,AssessmentofIECDesignParameters

E.ONVindSverigeAG,Malmö,SWE‐DEN

14 VC12105

2012‐2013

HTOD1,650MW

Winddataevaluation,Evaluationoflargescalewindresourcecalculations,AssessmentofWindFarmEnergyYield,AssessmentofSiteParametersasrequiredfortheDesignBasis,Performanceoflayoutoptimisationswithconsiderationofsitesuitability

HOCHTIEFOffshoreDe‐velopmentZweiGmbH,Essen

15 VC12105

2012‐2013

HTOD2,680MW

Winddataevaluation,Evaluationoflargescalewindresourcecalculations,AssessmentofWindFarmEnergyYield,AssessmentofSiteParametersasrequiredfortheDesignBasis,Performanceoflayoutoptimisationswithconsiderationofsitesuitability

HOCHTIEFOffshoreDe‐velopmentZweiGmbH,Essen

16 VC11236

2011‐2012

Wikinger,upto430MW

Winddataevaluation,AssessmentofWindFarmEnergyYield,AssessmentofSitePa‐rametersasrequiredfortheDesignBasis,Performanceoflayoutoptimisationswithconsiderationofsitesuitability

IberdrolaRenovables/ScottishPow‐erRenewablesOffshore,Spain/UK

17 VC11236

2011‐2012

WikingerSüd,upto80MW

Winddataevaluation,AssessmentofWindFarmEnergyYield,AssessmentofSitePa‐rametersasrequiredfortheDesignBasis,Performanceoflayoutoptimisationswithconsiderationofsitesuitability

IberdrolaRenovables/ScottishPow‐erRenewablesOffshore,Spain/UK

18 VC11236

2011‐2012

Windanker,upto400MW

Winddataevaluation,AssessmentofWindFarmEnergyYield,AssessmentofSitePa‐rametersasrequiredfortheDesignBasis,Performanceoflayoutoptimisationswithconsiderationofsitesuitability

IberdrolaRenovables/ScottishPow‐erRenewablesOffshore,Spain/UK

19 VC12378

2012‐2013

Aquamarin,upto680MW

Winddataevaluation,Evaluationoflargescalewindresourcecalculations,AssessmentofWindFarmEnergyYield

BARDEngi‐neeringGmbH,Bre‐men

Page 27: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 27/89

No. ProjectNo.Year

ProjectName,RatedPower

TypeofServices Client

20 VC13083

2013

KihnuWindFarmupto500MW

Evaluationofthewinddatameasuredatthesite;Evaluationofavailableregionallong‐termdatasourcestogeneratealong‐termextrapolationoftheonsitedata,Assessmentofthelong‐termaveragewinddistributionatthesite,Calculationoftheexpectedannualenergyyieldofthewindfarm,Analysisoftheuncertainties,Assessmentofthesiteaccord‐ingtoIECwindturbinedesignparametersforthewindfarmconfiguration,chosenbycus‐tomer

EestiEnergiaSATaastu‐venergiaEttevõteBURenewableEnergy

21 VC13114

2013

BorkumWestII DetailedevaluationofproductiondatafromoperatingGermanoffshorewindfarm,Devel‐opmentandrealisationofmethodologytopredictdailyandmonthlyenergyyieldofGermanoffshorewindfarm,relevantforcal‐culationofpenaltypaymentsforgridconnec‐tiondelay,Evaluationandassessmentofna‐celleanemometerdataforpredictionofdailyandmonthlyenergyyieldofGermanoffshorewindfarm,relevantforcalculationofpenaltypaymentsforgridconnectiondelay

TrianelGmbH,Lombardenstr.28,Aachen

22 VC13169

2013

Wikinger,Wik‐ingerSüd,Windanker,upto800MW

Reassessmenttocoverdeviatingwindfarmlayoutandspecificdesignrequirements,in‐cluding:AssessmentofWindFarmEnergyYield,AssessmentofSiteParametersasre‐quiredfortheDesignBasis

IberdrolaRenovables/ScottishPow‐erRenewablesOffshore,Spain/UK

23 VC13202

2013

confidential,330MW

Winddataevaluation,Evaluationofdifferentoffshoredevelopmentscenarios,AssessmentofWindFarmEnergyYield,AssessmentofSiteParametersasrequiredfortheDesignBasis

NordseeOneGmbH,Ham‐burg

24 VC14075

2014

GlobalTech1 Realisationofmethodologytopredict15‐minutestimeseriesoflostenergyyieldofoffshorewindfarm,relevantforcompensa‐tionpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Evaluationofnacelleanemometerdataandinvestigationofusabilityforthispurpose;consultancyongridcompensationrelatedquestions.

GlobalTech1OffshoreWindGmbH

25 VC14130

2014

BorkumRiffgrund1,312MW

Realisationofmethodologytopredict15‐minutestimeseriesoflostenergyyieldofoffshorewindfarm,relevantforcompensa‐tionpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Evaluationofnacelleanemometerdataandinvestigationofusabilityforthispurpose;consultancyongridcompensationrelatedquestions.

DONGEnergy,Germany

Page 28: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 28/89

No. ProjectNo.Year

ProjectName,RatedPower

TypeofServices Client

26 VC14134

2014

DanTysk Realisationofmethodologytopredict15‐minutestimeseriesoflostenergyyieldofoffshorewindfarm,relevantforcompensa‐tionpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Evaluationofnacelleanemometerdata,per‐formanceofmeasurementcampaignatoff‐shorewindfarmandinvestigationofusabilityforthispurpose;consultancyongridcom‐pensationrelatedquestions.

VattenfallGermany

27 VC14182

2014

Arkona‐BeckenSüdost,385MW

Winddataevaluation;AssessmentofWindFarmEnergyYield;AssessmentofSitePa‐rametersasrequiredfortheDesignBasis;CombinedEvaluationofwindandMetOceandata

AWEArkona‐WindparkEntwicklungs‐GmbH

28 VC14301

2014‐2015

TrianelWind‐parkBorkumPhase2,200MW

Evaluationandlongtermextrapolationofmeasuredwinddata,GISevaluationofwindfarmareaandrelatingrestrictions,calcula‐tionofeffectivewindfarmturbulenceintensi‐ty,performanceoflayoutoptimizationwithconsiderationofarearestrictionsandeffec‐tiveturbulencelimitations,calculationofeffectiveturbulenceintensityimpactonadja‐centprojectsandassessmentwithregardstopermissionissues.

TrianelWind‐kraftwerkBorkumGmbH&Co.KG

29 VC14365

2014

BardOffshoreI, Operationalwindfarmdataanalysis,Assess‐mentofWindFarmEnergyYieldonthatbasis

OceanBreezeEnergyGmbH&Co.KG

30 VC14412

2014

VejaMate,402MW

EnergyYieldandSiteSuitabilitystudywithbankablescope:evaluationandlong‐termassessmentofoffshoremeasurementdata,windresourceassessment,analysisofuncer‐taintiesandrelevanttechnicallosses.As‐sessmentofthesitelayoutaccordingtotur‐bulenceconditionsandwindturbinedesignparameters.

SIEMENSPro‐jectVenturesGmbHandCopenhagenInfrastructurePartners

31 VC15012

2015

DeltaNordsee,upto432MW

Evaluationofmeasuredwinddata,Assess‐mentofthelong‐termaveragewinddistribu‐tionatthesite,Optimizationofwindfarmlayoutwithrespecttomaximisingenergyyieldandavoidingexceedancesofthedesign‐relevanteffectivewindfarmturbulencein‐tensity,Calculationoftheexpectedannualenergyyieldofthewindfarm,Analysisoftheuncertaintiesandrelevanttechnicallosses

Offshore‐WindparkDeltaNordseeGmbH

Page 29: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 29/89

No. ProjectNo.Year

ProjectName,RatedPower

TypeofServices Client

32 VC15028

2015

BARDOffshore1,400MW

Realisationofmethodologytopredict15‐minutestimeseriesoflostenergyyieldofoffshorewindfarm,relevantforcompensa‐tionpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Considerationofcomplexrulesandalgo‐rithmstohandlecomplicatedcircumstancesofthegridoutage.Evaluationofnacelleane‐mometerdataandinvestigationofusabilityforthispurpose;consultancyongridcom‐pensationrelatedquestions.

OceanBreezeEnergyGmbH&Co.KG

33 VC15043

2015

Confidential,288MW

Realisationofmethodologytopredict15‐minutestimeseriesoflostenergyyieldofoffshorewindfarm,relevantforcompensa‐tionpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Evaluationofnacelleanemometerdataandinvestigationofusabilityforthispurpose;consultancyongridcompensationrelatedquestions.

Confidential

34 VC15051

2015

GlobalTechI,400MW

Evaluationandlongtermextrapolationofmeasuredwinddata,timeseriescalculationoftheenergyyieldofthewindfarmwithanalysisoftechnicallossesandtheirinterde‐pendencies,assessmentoflongtermenergyyield,relatinguncertaintiesandtechnicallossesforthewindfarmproject

GlobalTechIOffshoreWindGmbH

35 VC15071

2015

Riffgat(Nord‐see),113.4MW

Performanceofmonthlycalculationsoflostenergyyieldforthepurposeofquantifyingcompensationpaymentsforgridconnectiondelayandoutage

EWEErneu‐erbareEner‐gienGmbH

36 VC15125

2015

GodeWind2,252MW

Realisationofmethodologytopredict15‐minutestimeseriesoflostenergyyieldofoffshorewindfarm,relevantforcompensa‐tionpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Evaluationofnacelleanemometerdataandinvestigationofusabilityforthispurpose;consultancyongridcompensationrelatedquestions.

OceanBreezeEnergyGmbH&Co.KG

37 VC15251

2015

BardOffshore1,400MW

EnergyYieldandSiteSuitabilitystudywithbankablescope:evaluationandlong‐termassessmentofoffshoremeasurementdata,windresourceassessment,analysisofuncer‐taintiesandrelevanttechnicallosses.As‐sessmentofthesitelayoutaccordingtotur‐bulenceconditionsandwindturbinedesignparameters.

OceanBreezeEnergyGmbH&Co.KG

Page 30: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 30/89

No. ProjectNo.Year

ProjectName,RatedPower

TypeofServices Client

38 VC15502

2015‐2016

MerkurOffshore,400MW

Calculationofeffectivewindfarmturbulenceintensityimpactonadjacentprojectsandassessmentwithregardstopermissionissues

MerkurOff‐shoreGmbH

39 VC15260

2015

KriegersFlak,602MW

EnergyYieldandSiteSuitabilitystudywithbankablescope:evaluationandlong‐termassessmentofoffshoremeasurementdata,windresourceassessment,analysisofuncer‐taintiesandrelevanttechnicallosses.As‐sessmentofthesitelayoutaccordingtotur‐bulenceconditionsandwindturbinedesignparameters.WorkdoneforthepurposeofapplicationattheKriegersFlaktender,Den‐mark.

E.ONWindDenmarkAB

40 VC16278

2016

Nordergründe,111MW

Assessmentofthedesignrelevantwindtur‐bineparametersaccordingtoIEC‐61400‐1,evaluationofmastmeasurementdata,PowercurveComparison

OWPNorder‐gründeGmbH

41 VC15498

2015‐2016

BorsseleIundII,700MW

WindResourceassessmentandenergypro‐ductionestimationconcerningtheGovern‐mentoftheNetherland'stenderforthecon‐structionoftwooffshorewindfarmintheDutcheconomiczonewithintheNorthSEA,participatedbyVattenfall,Evaluationofmastmeasurementdata

N.V.NUONDuurzameEnergie

42 VC16361

2016

BorsseleIII(352.8MW)undIV(378MW)

EnergyYieldstudywithbankablescope:evaluationandlong‐termassessmentofoff‐shoremeasurementdata(mast,LiDARandfloatingLiDAR),windresourceassessment,analysisofuncertaintiesandrelevanttech‐nicallosses.WorkdoneforthepurposeofapplicationattheGovernmentoftheNether‐land'stenderfortheBorsseleIIIandIVsite.

wpdoffshoresolutionsGmbH

43 VC16199

2016

TrianelWind‐parkBorkumPhase2,200MW

EnergyYieldandSiteSuitabilitystudywithbankablescope:evaluationandlong‐termassessmentofoffshoremeasurementdata,windresourceassessment,analysisofuncer‐taintiesandrelevanttechnicallosses.As‐sessmentofthesitelayoutaccordingtotur‐bulenceconditions.

TrianelWind‐kraftwerkBorkumIIGmbH&Co.KG

44 VC16040

2016

GlobalTechI,400MW

EvaluationofLiDAR‐Datafromoffshoresub‐stationandcalculationoftimeseriesofwindspeedandwinddirectionathubheightofthewindturbines,asbasisfordetailedevaluationofturbineloadingandoperationalbehaviour.

GlobalTechIOffshoreWindGmbH

Page 31: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 31/89

No. ProjectNo.Year

ProjectName,RatedPower

TypeofServices Client

45 VC16105

2016

OffshoreWind‐parkRIFFGAT,113,4MW,Off‐shoreWindparkDanTysk,288MW

Realisationofmethodologytopredict15‐minutestimeseriesoflostenergyyieldofoffshorewindfarm,relevantforcompensa‐tionpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Evaluationofnacelleanemometerdata,per‐formanceofmeasurementcampaignatoff‐shorewindfarmandinvestigationofusabilityforthispurpose;consultingongridcompen‐sationrelatedquestions.

Offshore‐WindparkRIFFGATGmbH&Co.KG

46 VC16179 GodeWind1,330MW

Realisationofmethodologytopredict15‐minutestimeseriesoflostenergyyieldofoffshorewindfarm,relevantforcompensa‐tionpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Evaluationofnacelleanemometerdata,per‐formanceofmeasurementcampaignatoff‐shorewindfarmandinvestigationofusabilityforthispurpose;consultingongridcompen‐sationrelatedquestions.

DONGEnergy,Germany

47 VC16187

2016

BardOffshoreI,400MW

DetailedMetOceanevaluation,includingoff‐shorewindmeasurementdatarecalculatedtohubheightandhindcastdatafromhydrologi‐calstudy.

OceanBreezeEnergyGmbH&Co.KG

Page 32: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 32/89

2.6 ConceptStudiesandPre‐EvaluationsforEnergyYieldAssess‐ments

Theconceptionofwindresourceassessmentsasapreparationforenergyyieldpredic‐tionsusuallyincludesthefollowingactivities:

Layoutforwindmeasurementcampaigns,dependingontheaccuracyrequiredatdifferentstagesofprojectdevelopment(i.e.measurementset‐upaccordingtothecurrentstandards,determinationofsuitablemetmastlocationsinthearea)

Surveyandpre‐evaluationofavailablelong‐termdatasourcesusableforthelong‐termassessment

Preparationofflowmodelling,pre‐estimationofuncertainties

Thefollowingtablegivesanoverviewoftherealisedconceptstudies:

Country NumberofSites

Brazil 5

Bulgaria 1

Chile 1

China 1

Croatia 3

CzechRepublic 1

Egypt 1

Estonia 1

Finland 1

France 15

Germany 96

GreatBritain 17

Greece 6

Hungary 1

Ireland 3

Italy 10

Country NumberofSites

Kazakhstan 1

Morocco 6

Netherlands 7

Poland 1

Romania 2

Serbia 1

Spain 2

Sweden 2

Taiwan 1

Thailand 1

Turkey 14

Ukraine 7

USA 1

Vietnam 1

Total 210

Page 33: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 33/89

2.7 Research&DevelopmentActivitiesintheFieldofSiteAssessment

The following R&D‐activities in the field of site assessment have been performed byDeutscheWindGuardsince2001

IntroductionofdetaileduncertaintysurveysforwindresourceassessmentsintheGermanwindenergymarketin2001,developmentofriskmanagementsysteminco‐operationwithGermanbanks

Developmentandmarketintroductionofoverallevaluationofdifferentwindre‐sourceassessmentsforthesamewindfarm(sometimesreferredtoasmasteras‐sessment),2001‐2002

Developmentofprocedureforoptimisationofwindresourceassessmentsunderminimisationofuncertainties(iterativeminimisationofuncertainties),2002

Marketintroductionofharmonisationbetweenpredictedwindregimeandwindturbinepowercurvesinrespecttothetypeofthereferencecupanemometer,2001

Developmentofadaptationofpublicavailablewindenergyproductionindicestoindividualwindfarmconditions,2001‐2002

Developmentofnewprocedurestodescribethepowerperformanceofwindtur‐bines,since2002

Studiesaboutthelong‐termvariationofthewindpotentialinNorthernEurope,2003‐2004

DevelopmentofwindenergyproductionindexforGermanyandneighbouringcoun‐triesonthebasisofNCAR/NCEPreanalysedwinddata,2003‐2004

MemberofWindSimtestgroup,acommerciallyavailableReynoldsequationsolveradjustedtomicro‐sitingpurposes,2004

Classificationandoptimisationofcupanemometers TestingandmarketintroductionofLiDARmeasurements,since2004 Developmentofapproachesfortheestimationoflong‐termproductionlossesdueto

non‐availabilityofwindturbinessince2005 OptimisationofflowmodellingviaCFDmodels,since2007 Developmentofaprocedureforpredictingenergylossesduetorotorbladeicingin

2010 InvestigationofMERRAreanalysislong‐termwinddata,applicationforinternational

windfarmprojectsitesanddevelopmentofMERRA‐basedwindenergyproductionindicesforGermany,since2010

Influenceofforestryareasonflowmodelling,since2011 OptimisationofflowmodellingviaCFDmodel“OpenFOAM”,since2012 Developmentofproceduresfortimeseriescalculationofparkefficiencyandenergy

yieldofoffshorewindfarmsforcalculationofgriddelaycompensationandopera‐tionaldataassessment

Systematicinvestigationofaccuracyandbiasofnacelleanemometermeasurementatoffshorewindturbines

Page 34: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 34/89

2.8 CalculationofNoiseEmissionintheVicinityofProposedWindFarms

DeutscheWindGuardConsultingGmbHisaccreditedforcalculationofnoiseemissioninthevicinityofwind farmssince2012. Itsstaffmembers,however,haveseveralmoreyearsofexperience inwind turbinenoise issues. In the course ofwind farmplanning, developersandresponsibleauthoritiesneeddetailedandtrustworthyinformationabouttheexpectednoiseemissioninthevicinityofwindturbines.Consequently,calculationofnoisepropaga‐tionandemissionlevelsatreceptorlocationsaroundadesignatedprojectsiteformsanes‐sentialpartoftheapprovalprocess.Incasetheemittednoiseofacommissionedwindfarmexceedsthelegalnoiseemissionlimits,individualturbinesmayhavetobede‐ratedinpow‐erorshutdownforparticulartimeperiods.Hence,theimminentlossofincomefortheop‐eratorstrengthensthenecessityofreliablenoiseemissionpredictionsintheplanningphaseofwindfarms.

Windturbinenoisepredictionisacomplextopic.Thesoundpowerlevelofawindturbineusually increaseswithwind speed / produced electrical power. Apart from aerodynamicnoisefromtherotorblades,mechanicalnoisecanconstituteanothersourceofnoiseemis‐sion.Ontheotherhand,thenoiseemissionperceivedatareceptorlocationdependsalsoonsite‐specific conditions. In this context,we generally analyse the turbine locations and allrelevantreceptorlocationsduringasiteinspection.

Lawsandnoiseregulationsdifferfromcountrytocountryandcustomersareoftenuncer‐tain,howtomeettheserequirements.Insomecountries,thenoiseemissionlimitstobeob‐serveddependonhownearbybuildingsorstructuresareutilised(residentialareas,indus‐trialareas,etc.).Inothercountriestheacceptablenoiseemissionlevelsareassociatedtothelevelofthe(natural)ambientnoiseatthereceptorlocations.Wecanfindsolutionsandpro‐vide concepts also in complex situations. After commissioning of a wind farm DeutscheWindGuard can also verify the actual noise emissionby noisemeasurements on site (seechapter6.2).

DeutscheWindGuardoffers:

ObtainingofalldocumentsneededfortheapprovalprocessaccordingtoTALärm(Ger‐many),ISO9613‐2(international),orothercountry‐specificguidelines

Noisecalculationsbasedonwindturbinespecificationsgivenbymanufacturersorinde‐pendentnoisemeasurementlaboratories

Calculationofsoundpropagationandnoiseemissionlevels Developmentofconceptstoreducenoiseemissionwhenexceedingthecriticallimits

Page 35: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 35/89

Thefollowingtablegivesanoverviewoftherealisedacousticnoisepredictions:

Country NoiseCalculationsforProposedWinFarms

[‐] [MW]

Austria 15

Germany 2171

Morocco 1035

Country NoiseCalculationsforProposedWinFarms

Panama 78

Serbia 157

Total 3456

2.9 DeterminationofShadowFlickerImpactintheVicinityofProposedWindFarms

Shadow flicker is one of themost important “optical emissions” fromwind turbines,which must be considered during the planning phase. Rotating rotor blades cause aflashingeffectbyperiodicalblockingoff the sunlight,whichmay causedisturbanceofresidents in the vicinity of wind farms. For this reason, the determination of opticalemissions fromwind turbines forms an essential part of the approval process in theplanningphaseofwindpowerprojects.

Forthecalculationofshadowflickerimpact,factorsthatmustbetakenintoaccountarewindturbinehubheightandrotordiameter,positionof thesunandthegeometrybe‐tweentheturbineandreceptorlocations.Themaintaskistodeterminetheperiodicalshadowflickeratgivenreceptorlocationsasafunctionoftime(i.e.timeofday,timepe‐riodspermonth,etc.)andtoprovidetherelevantstatisticsofshadowflickerperiodstobeutilisedforthejuxtapositionwiththecorrespondinglimitsgivenbytheauthorities.Aspartofamandatorysiteassessment,ourexpertswillanalysetheproposedlocationsofthewindturbinesandallrelevantreceptors.

DeutscheWindGuardoffers:

Determinationofthemaximumpossible(astronomical)shadowflickerperiods(worstcase)andtheprobabletimeperiods(consideringcloudcover,etc.)

Graphicalandcalendricdescriptionoftheshadowflickerperiodsatgivenreceptorlocations

Acquisitionofalldocumentsneededfortheapprovalprocess,includingtheshadowflickercalculation

Calculationoftherequiredturbineshutdowntimesinordertoadheretothelimitssetbyauthorities

Developmentofshutdownconceptsforwindturbinestobeprogrammedintotheturbine’scontrolsystems

Page 36: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 36/89

Thefollowingtablegivesanoverviewoftherealisedshadowflickercalculations:

Country ShadowFlickerCalculationforProposedWindFarms

[‐] [MW]

Germany 2094

Morocco 150

Total 2244

2.10 VisibilityAnalysis

Visual impact of awind farm is a computer based environmental impact assessment,whichcanbedone inanearlyplanningphase. Ithelpsplannersandauthorities to in‐creasetheacceptancelevelofawindfarmprojectasitshowspotentialsignificantvisualimpacts.Furthermore,ithelpsthewideraudienceofanenvironmentalstatementtoun‐derstand the nature of these visual impacts through illustration. Forests, villages andother blocking elements can be included in the visual impact assessment.Up until now, we have performed visibility analysis for proposed wind farms with acombinedcapacityof100MW.

DeutscheWindGuardoffers:

Productionofmapsshowingabsoluteandrelativevisibilityofpartsoforthewholeplannedwindfarm(optionalvisibility:totalheightorhubheight)

Productionofaphotomontageshowingtheplannedwindfarminanalmostrealisticview,withhelpofdigitalterrainmodelsanddigitalisedwindturbinesmontagedinalandscapephoto

Page 37: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 37/89

2.11 Ice‐ThrowRiskAnalysis

In the courseofwind farmplanning, developers and responsible authoritiesneedde‐tailedandtrustworthy informationabout theexpectedprobabilityof ice impact in thevicinityofwindturbines.

IntheabsenceofalegalregulationDeutscheWindGuarddevelopedasimulationbasedonanempiricaldatabasetocalculatetheindividualrisktobestruckbyice‐throwinthevicinityofawindturbine.“Individualrisk”isdefinedastheprobabilityforonepersontobestruckby ice‐throwofapieceof icespecified inmassanddimension if thispersonstandsstillandunprotectedonadesignatedspotforoneyear.

DeutscheWindGuardoffers:

Probabilitydistributionofice‐throwriskofastoppedwindturbine Probabilitydistributionofice‐throwriskifthepiecesoficearethrownoutfromthe

tipsoftheblades(usuallythisresultsinastopoftheturbine,becauseofimbalances) Probabilitydistributionoficethrowriskofaturbineinidlemode Calculationofthemaximumicethrowdistancesfordifferentwindspeeds

Wehaveperformedriskanalysisforice‐throwforalmost160turbines.

Page 38: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 38/89

3 DueDiligenceandConsultingServices

Asoneoftheleadingindependentconsultantsforprojectdevelopers,banksandinves‐tors, we offer Technical Due Diligence for onshore and offshore projects. DeutscheWindGuardhasbeencontractedbyvariousfinanciersandinvestors,aselectionofwhichislistedbelow.

ListofBanks(Extract)

BNPParibas,Germany BremerLandesbank,Germany Commerzbank,Germany CréditAgricole,USA DALStructuredFinance,Germany DeutscheImmobilienLeasing(DeutscheBank),Germany DeutscheKreditbankAG,Germany Dexia,France DZ‐Bank,Germany Helaba,Germany HSHNordbank,Germany KeyBank,USA KfW,Germany KfW‐Ipex,Germany NordLBGermany NordLBNewYork OldenburgischeLandesbank,Germany RaiffeisenzentralbankWien,Austria SIEMENSProjectVenturesGmbH,Germany Umweltbank,Germany Unicredit,Germany/Italy

Page 39: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 39/89

ListofInternationalInvestors(Extract)

Advent,UK APG,Netherlands ArcLightCapitalPartners,USA AREAM,Germany CopenhagenInfrastructurePartners,Denmark EnergieversorgungOffenbachAG,Germany EQTPartners,Sweden ewz,Switzerland Fieldstone,UK GEFinance,USA GoodEnergiesInvestments,UK GreenTrust,Netherlands HGCapital,UK KrubinerOrmorAssets,Israel MacquarieCapital,UK Marguerite,France/Luxembourg MEAG,Germany MEAEnergieagenturGmbH,Germany MidEuropaPartners,UK PfalzwerkeAG,Germany PlatinaFinance,UK re:capglobalinvestorsag,Switzerland Sachsenfonds,Germany TechnischeWerkeLudwigshafenAG,Germany ViridisEnergy,Australia WARD,UK WPD,Germany

Page 40: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 40/89

3.1 TechnicalDueDiligence

A Technical Due Diligence for awind farm project typically consists of various tasks,proposedbyDeutscheWindGuardand/oragreeduponwiththeclient.Aduediligencemay be performed at different stages of project development (e.g. during pre‐construction,constructionoroperationalphase).ThefollowingtasksarefrequentlypartofaTechnicalDueDiligence:

Verificationandcomprehensiveevaluationofwindresourceassessments Verificationofassumedproductionlosses Technicalassessmentoftheproposedwindturbinetypeand/ormanufacturer Technicalassessmentofinfrastructure(gridconnection,accessroads,cabling,etc.) Assessmentofenvironmentalissues Technicalassessmentofthetechnicalwindfarmmanagementandmaintenance

concept Technicalassessmentofwindturbinepurchase,maintenanceandinsurancecon‐

tracts Technicalassessmentofpowerpurchaseagreements Supervisionofcivilworksduringtheconstructionphase Commissioningofcompletedwindfarms,includingacceptancetests

Deutsche WindGuard has performed Technical Due Diligence assignments for morethan300windfarmprojectswithatotalinstalledcapacityofmorethan9000MW.

Country DueDiligence:InstalledPowerofWindFarms

No.ofWindFarms

[‐] [MW] [‐]

Australia 58 2

Brazil 100 1

Canada 4 2

Estonia 70 1

Finland 14 2

France 165 12

Germany 4398 253

GreatBritain 46 3

Country DueDiligence:InstalledPowerofWindFarms

No.ofWindFarms

Greece 30 1

India 100 1

Ireland 120 1

Italy 316 3

Mexico 100 1

Netherlands 1847 5

Poland 120 3

Spain 1215 32

Sweden 321 3

Page 41: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 41/89

Country DueDiligence:InstalledPowerofWindFarms

No.ofWindFarms

Switzerland 7 1

Ukraine 299 3

Country DueDiligence:InstalledPowerofWindFarms

No.ofWindFarms

USA 262 5

Total 9592 335

3.2 StrategicDueDiligenceandAssessmentofWindTurbineTypes

The combination of long‐standing industry knowledge with a strong technical back‐groundformsasoundbasisforourstrategicduediligenceservicesinthewindenergyindustry.Nomatterifyouintendtotakeoverahardwareprovider,aserviceprovider,awind farmdeveloper,or ifyouneedadviceona specificwind turbine typeor turbinesuppliers,wecanprovideyouwithcomprehensiveanswersforyourdecisions.

No. InternalProjectNo.

TypeofSurvey Country YearofAssessment

Client

1 VC04003 validationofstormregulation

Germany 2004 Germanmanufacturer

2 VC04195 validationofturbinetype

Germany 2004 Germandeveloper

3 VC06226 adviceonturbinetype Netherlands 2006 Dutchdeveloper

4 VC07134 validationoftwoturbinetypes

International 2007 USinvestor

5 VC07174 validationofdifferentturbinetypes

USA 2007 USdeveloper

6 VC07234 strategicadviceforturbinesupplier

Denmark 2007 Danishmanufacturer

7 VC07255 strategicadviceonwindfarmdevelopment

SaudiArabia 2007 Germanbank

8 VC07263 validationofturbinemanufacturer

Germany 2007 Britishinvestor

9 VC07291 validationofturbinetype

Germany 2007 Germandeveloper

10 VC08090 validationofturbinetype

USA 2008 USbank

11 VC08171 validationofturbinetype

USA 2008 USdeveloper

Page 42: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 42/89

No. InternalProjectNo.

TypeofSurvey Country YearofAssessment

Client

12 VC08190 strategicadviceonwindfarmdevelopments

Europe 2008‐2010 Swedishinvestor

13 VC08215 strategicadviceonvari‐ouswindpowerinvest‐

ments

International since2008 Internationalinvestors

14 VC09012 adviceonselectionofoffshorewindturbines

Germany 2009 Germandeveloper

15 VC09126 strategicadviceforturbinemanufacturer

Germany 2009‐2010 Germanmanufacturer

16 VC09239 validationofturbinetype

Germany 2009‐2010 Germanmanufacturer

17 VC10006 validationoftwoturbinetypes

Denmark 2010 Irishdeveloper

18 VC10019 validationofrotorbladede‐icingsystem

international 2010‐2011 Germanmanufacturer

19 VC10068 validationofturbinemanufacturer

Germany 2010 Germanliquidator

20 VC10210 validationofturbinetype

Germany 2010 Germandeveloper

21 VC11069 validationofturbinetype

Germany 2011 Germanmanufacturer

22 VC10172 validationoftwoturbinetypes

Germany 2011 Germanmanufacturer

23 VC11044 strategicadviceonin‐vestmentinagenerator

supplier

CzechRepub‐lic

2011 USinvestor

24 VC11327 strategicadviceonin‐vestmentinaLiDAR

supplier

Israel 2011 Israeliinvestor

25 VC12059 validationoftwoturbinetypes

Germany 2012 Irishdeveloper

26 VC12262 validationofturbinetype

Germany 2012 Germanmanufacturer

27 VC12411 validationofrotorbladeicedetectionsystem

International 2012 Germanmanufacturer

28 VC13085 studyonwindfarmop‐eratingcost

Germany 2013 Germanbank

29 VC13271 modificationofwindfarmcash‐flowmodel

Germany 2013 Germanbank

Page 43: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 43/89

No. InternalProjectNo.

TypeofSurvey Country YearofAssessment

Client

30 VU13003 reviewofAsianwindturbinesuppliers

Asia 2013 Ukrainiandeveloper

31 VO13102 supportofwindturbinecertification

Germany 2013 Spanishmanufacturer

32 VC14103validationofturbinetype

Germany 2014 Germandeveloper

33 VC15018studyonwindfarmop‐

eratingcost Germany 2015 Germanbank

34 VC15180validationofoffshore

turbinetypeGermany 2015 Germandeveloper

35 VC15259validationofsmallwind

turbinesystem USA 2015 USdeveloper

36 VC151297 validationofturbinetype

Germany 2015 Germanmanufacturer

37 VC15378validationof

stormregulationInternational 2015 Germanmanufacturer

38 VC15435reviewofpowercurvetestingprocedure International 2015 Danishmanufacturer

39 VC15435 reviewpowercurvetest‐ingprocedure

international 2015 Danishmanufacturer

40 VC16166 validationturbinetype Germany 2016 Germaninvestor

41VC16194 reviewmultiplepower

curvetestingprocedureinternational 2016 Danishdeveloper

42 VC16329 validationturbinetype Germany 2016 Germaninvestor

43 VC16104 StudyoninvestmentopportunitiesintheGermanwindmarket

Germany 2016 Asianinvestor

Page 44: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 44/89

3.3 TenderandContractConsulting

Manufacturersrelyonourdecadesofexperiencetominimizeriskswhilemakingtheircustomersanattractiveoffer.Getthemaximumamountofsecurity–withthesupportofWindGuard.Weexaminethecontracts,evaluatethetechnicalcontents,andifnecessary,submitproposalsforamendment.Fullycompleteddraftcontractsarealsopossible.

Thisservicetypicallyconsistsofthefollowingworkpackages:

Procurementconsultancy Technicalvalidationofwindturbinepurchase,maintenanceandinsurancecontracts Independentadviceonnegotiationsbetweenwindfarmdevelopers,financiersand

windturbinemanufacturers Conceptsforwarrantiesfortechnicalpropertiesofwindturbinesfordevelopersand

manufacturers(powerperformance,availability,noiseemission,powerquality,etc.) Conceptsfortechnicalwindfarmmanagement,maintenanceandrepair

Country TechnicalValidationofWindTurbinePurchase

andMaintenanceContracts

[‐] [No.ofprojects]

Argentina 1

Austria 2

Australia 1

Belgium 1

France 2

Germany 52

International 2

Mexico 1

Netherlands 6

Country TechnicalValidationofWindTurbinePurchase

andMaintenanceContracts

[‐] [No.ofprojects]

Poland 1

Romania 1

Serbia 1

Spain 1

Taiwan 1

Turkey 1

Ukraine 1

USA 2

Total 77

Page 45: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 45/89

3.4 Markets&Politics

DeutscheWindGuardhas significantexperiences inwindenergymarketanalysis, eco‐nomicevaluationofwindenergyprojectsandthewindenergymarketingeneral,aswellas wind energy development statistics, cost analysis and assessment of the politicalframeworkconditions.Our clientsaree.g. governments, associationsorprivate enter‐prises.

We conductmarket analyses andpolitical consulting inGermanyandalsoworldwide.Forclientsfromtheprivateenterprisesector,weconducttailor‐mademarketanalysesandmarketforecasts.WehaveconsultedtheGermangovernmentformanyyearsonthedevelopmentandtheamendmentsoftheGermanRenewableEnergyAct(EEG).Atregu‐larintervals,weanalysethecostsituationofwindenergyprojectsinGermanyaswellasthelevelizedcostofenergy.

Forourscientificadviceprojectsandmarketanalysis,weworkonaninterdisciplinarybasisusingtheexpertsfromallovertheWindGuardUniverse.Thus,wecanassurethatthe extensive expertise from very different perspectives is available in our research.This isan important characteristicofouranalysisandensures thehighpractical rele‐vanceoftheresults.

Aselectionofourscientificworkispresentedbelow.AdetailedlistisgiveninAppendix8.1.

No. ProjectNo.,Year

ProjectType

TypeofServices Client

1 VW13130continuous

MarketAnalysis

StatusquoanddevelopmentofonshorewindenergyutilisationinGermany

BWE/VDMAPowerSyst.

2 VW14192continuous

MarketAnalysis

StatusquoanddevelopmentofoffshorewindenergyutilisationinGermany

AGOW/BWE/VDMA/WAB/OffshoreWind

EnergyFoundation.

3 VW141782009‐ongoing

WindEnergyCostEvalua‐

tion

ParticipationinIEAwindTask26“CostofWindEnergy”

Comparisonofwindenergydevelopment,technologiesandcostsinallcountriesin‐volved

supportedbyBMWi(Fed‐eralMinistryforEconomicAffairsandEnergy)

4 VW161652016‐2019

PoliticalConsulting

EvaluationEEG2004regardingwindenergy

Preparationandmonitoringofanexperi‐encereportinaccordancewith§97Re‐newableEnergySourcesAct(EEG2014)‐ProjectIIeLand‐basedwindenergy

AssessmentofcurrentsituationofthewindenergymarketinGermany,deter‐

BMWI(Fed‐eralMinistryforEconomicAffairsandEnergy)

Page 46: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 46/89

No. ProjectNo.,Year

ProjectType

TypeofServices Client

minationofcurrentcostsofwindenergyandinvestigationtheeffectsoftheEEG

5 VW151512016‐2019

Researchproject

PROMOTioN‐ProgressonMeshedHVDCOffshoreTransmissionNetworks

Seeking to develop meshed HVDC off‐shore grids on the basis of cost‐effectiveand reliable technological innovation incombinationwithasoundpolitical,finan‐cialandlegalregulatoryframework

Biggest energy project in the EU’s Hori‐zon2020ResearchProgram,including34partnersfrom11countries.

FundedbytheEuropeanUnion’sHori‐zon2020

researchandinnovationprogrammeundergrantagreementNo

691714

6 VW151062016‐2019

Researchproject

Exploration of the potential of meshedoffshoregridsfortheBalticSearegion

Contribution to a sustainable electricitygeneration, the further integration of re‐gionalelectricitymarkets,andtoenhancethe security of supply around the BalticSea

FundedbytheEuropeanUnion’sInter‐regBalticSeaRegionPro‐gramme

7 VW151102015

WindEnergyCostEvalua‐

tion

Holistic data acquisition regarding therecentcostofwindturbines

Calculation of levelized cost of energyfromwind turbinesat severalwindsitesandsensitivityanalysisregardingseveralcostfactors

BWE/VDMA

8 VW141522014

PoliticalConsulting

AnalysisofcostofonshorewindpowerinIsrael

Assessment of the relatively weak windconditionsinIsraelandtheresultingcostsituation(useoflow‐windturbines)

Assessmentof theconditions for theuseofwindenergy in Israel, forexampletheavailability of maintenance services andthe availability of the needed infrastruc‐ture

IsraeliWindEnergyAsso‐

ciation

9 VW131512013‐2014

PoliticalConsulting

Reformofthereferenceenergy‐yieldmodelofonshorewindenergyinthecon‐textoftheamendmentoftheRenewableEnergyAct(EEG)

AGORAEnergie‐wende

10 VW131142013‐2014

PoliticalConsulting

EvaluationoftheresearchfundingoftheFederalMinistryfortheEnvironment,NatureConservationandNuclearSafety(BMU)

AnalysisofwindenergyrelatedF&Epro‐jectsunderthe5thEnergyResearchPro‐gram

BMU(MinistryfortheEnviron‐

ment)

Page 47: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 47/89

No. ProjectNo.,Year

ProjectType

TypeofServices Client

11 VW110872011‐2014

PoliticalConsulting

TechnologyCooperationinwindenergyintheframeoftheCleanEnergyMiniste‐rial(CEM)

Adviceandscientificsupport

BMU(MinistryfortheEnviron‐

ment)

12 VW131452013

PoliticalConsulting

Sitesophisticatedmodelofreimburse‐mentofwindenergyuse

BWE

13 VW131532013

Windenergycostevalua‐

tion

Analysisofcostofonshorewindpowerprojectsinvariouscountries(Germany,USA,UKandDenmark).

Comparisonofspecificinvestmentcostaswellasdifferentwindsitesandtechnolo‐giestypicaltocountriesunderreview

BWE

14 VW120702012‐2013

Windenergycostevalua‐

tion

Holisticdataacquisitionregardingtherecentcostsituationofwindenergypro‐jectsinGermanyin2012

Analysisofinvestmentcostsandoperat‐ingcostsofwindenergyprojects

Calculationoflevelizedcostofenergyfromwindturbinesatseveralwindsitesandsensitivityanalysisregardingseveralcostfactors

BWE/VDMAPowerSyst.

15 VW120332012‐2013

PoliticalConsulting/MarketAnalysis

Developmentofaconversionstrategyforgeneration systems in the medium andlow voltage network tomaintain systemreliabilityathighandlowfrequency

Investigation of systemic importance ofthe connections of decentralized powergeneration plants and possible develop‐mentofrecommendations

BMWi(FederalMin‐istryforEco‐nomicAf‐fairs)

16 VW110532011‐2013

PoliticalConsulting

Opportunitiesandchallengesforhar‐bour‐andshipyardindustryconcerningoffshorewindenergydevelopment

Potentialofoffshorewindenergylogis‐ticsforharboursandshipyards

BMU(MinistryfortheEnviron‐

ment)

17 VW091432009‐2012

PoliticalConsulting

EvaluationEEG2009regardingwindenergy

Preparationandmonitoringofthecompi‐lation of an experience report accordingto§65EEG(RenewableEnergyAct)

Assessment of current situation of thewind energy market in Germany, deter‐minationofcurrentelectricitygenerationcosts for wind energy and investigationtheeffectsoftheEEG

BMU(MinistryfortheEnviron‐

ment)

Page 48: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 48/89

No. ProjectNo.,Year

ProjectType

TypeofServices Client

18 VW091482009‐2011

PoliticalConsulting

TechnologyCooperationforWindEnergyintheframeoftheMajorEconomiesFo‐rums(MEF)

Adviceandconceptualdesignoftechnol‐ogyactionplans

BMU(MinistryfortheEnviron‐

ment)

19

VW101652010

PoliticalConsulting

PoliticalConsultingregardingsubsidyforwindenergy

Optimizationofenergypolicyframe‐worksforrenewableenergyandprogramforgridconnectedwindenergyturbines

Evaluationofdraftlawonthesupportofwindenergyprojects

GTZ

3.5 FeasibilityStudiesforWindEnergyProjects

DeutscheWindGuardhasperformedapproximately20feasibilitystudiesinAsia,Africa,andSouthAmerica.Typically,feasibilitystudiesforwindfarmprojectsinclude:

Siteinspections Apre‐selectionofsitessuitableforwindenergyexploration(accessibility,gridcon‐

nection,windconditions,etc.) Windmeasurementsatselectedsites Anassessmentofthelong‐termwindresource Amarketsurveyofsuitablewindturbines Designandoptimisationofwindfarmlayoutandperformanceofenergyyieldas‐

sessments Analysisoftheelectricalutilitynetwork,performanceofloadflowcalculationsfor

theentirenetwork Assessmentofsiteaccessibility,infrastructurefortransportation,installationand

gridconnection/integrationandassessmentofrelatedcosts Loadflowanalysisformediumandhighvoltagesystemstoproposeandanalysedif‐

ferentgridsolutions Abasicevaluationofenvironmentalimpact,comparisonwithinternationalstand‐

ards Fulleconomicanalysis,includingfinancingmodel(CAPEX,OPEX,etc.)andsensitivity

analysisofinputparameters CDManalysis Technicalandeconomicfeasibilitystudy,evaluationofproblemsandrisksinthe

projectcontext,regardingwindenergyspecificandtechnicalissues

AdetailedlistofthemainfeasibilitystudiesperformedisgiveninAppendix8.2.

Page 49: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 49/89

3.6 Scientifictraining

In addition to the Safety Training DeutscheWindGuard also offers scientific training,coursesandworkshops. Since foundationofDeutscheWindGuard inyear2001 roundabout90courseswithmorethan2000participantswereheld.AdetailedtableisgiveninAppendix8.4.

4 WindFarmOperation,TechnicalManagementandTur‐bineInspection

4.1 TechnicalManagementofWindFarms

One activity of DeutscheWindGuard is the technicalmanagement ofwind farms. Thetechnicalmanagement is the basis for a successfulwind energy project, for onlywellmaintainedwindturbineswithahightechnicalavailabilityassureinvestorsandbankstheforecastedcalculatedprofits.ThetechnicalmanagementofwindfarmsbyDeutscheWindGuard follows the requirements of insurance companies for status‐orientedmaintenanceofwindfarms.

Technicalmanagement includes constantmonitoring via remote control, implementa‐tion and organisation of immediate assistance in the case of error removal, ordering,organisationaswellascheckingofmaintenance.Thepreparationofmaintenance–andmanagement protocols and periodical reports is also part of the service. At present,DeutscheWindGuardmanagesatotalof212windturbineswithatotalin‐stalledcapaci‐tyofmorethan471MW.Adetailedlistofthesewindturbinesand/orwindfarmsisgiv‐eninAppendix8.3.

4.1.1 Referenceproject:technicalmanagementofalphaventusandRiffgatoff‐shorewindfarms

Withtheextensiveexperienceandthelonglastingactivityinthetechnicalmanagementofwindfarms,DeutscheWindGuardwasentrustedaspartnerwiththetechnicalman‐agementofthefirstGermanoffshoretestfieldalphaventusaswellastheoffshorewindfarmRiffgat.Priortothis,WindGuardwasalreadyactingasconsultantforalphaventusintheareasofoperationandengineering.

Page 50: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 50/89

4.2 TechnicalInspectionofWindTurbines

Technicalinspectionsareanessentialpartoftheoperationalphaseofeveryturbine.AsBWE(GermanWindEnergyAssociation)–acceptedexpertfortherecurringinspectiononwindturbines,weemployseveralhighlyskilledandexperiencedinspectors.

Since2009,DeutscheWindGuardisaccreditedbytheDeutscheAkkreditierungsstelle–DAkkS(GermanAccreditationBody)asaninspectionbodyforwindturbinesaccordingtoDINENISO/IEC17020:2012.Weareoneofonlyahandfulofcompaniestoholdsuchanaccreditationinthewindenergysector.

DeutscheWindGuardoffersseveraltypesofinspectionsonwindturbines:

CommissioningInspections, RecurringInspections, EndofWarrantyInspections DamageAssessments InspectionsforConditionBasedMaintenance(includingvibrationanalysisofthe

wholedrivetrain) AcceptanceTest(1to3monthsintooperation)andcommissioningcertification

DeutscheWindGuardhasconducted3457technicalinspectionsforalmost70differentwind turbines since 2001. The inspections and tests are performed on all types andbrandsofwindturbines.Basedonthe long‐lastingexpertiseofour team,especially intheresearchandtheevaluationofwindturbinetechnology,DeutscheWindGuard’sstaffmembersareindependentexpertsonwindturbines.Ourtechnicalexpertshavecarriedoutagreatnumberofwind farm inspections in thepastwithin thescopeof technicalcommissioning,repeatedinspectionsanddamageassessment.

Adetailedlistwiththetypeandnumberof inspectedwindturbinesisprovidedinthetablebelow.

TypeofTurbineNo.of

Turbines

ANBonusAN‐450 5

AnBonus1.3 5

AnBonus2.0 8

ArevaM5000 11

EnerconE‐10 1

EnerconE‐17 5

TypeofTurbineNo.of

Turbines

EnerconE‐18 9

EnerconE‐20 1

EnerconE‐30 20

EnerconE‐31 2

EnerconE‐32 13

EnerconE‐40 486

Page 51: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 51/89

TypeofTurbine No.ofTurbines

EnerconE‐40/6.44 20

EnerconE‐44 36

EnerconE‐44/6.44 1

EnerconE‐48 69

EnerconE‐53 36

EnerconE‐58 39

EnerconE‐66 1060

EnerconE‐70 409

EnerconE‐70E4 64

EnerconE‐82 222

EnerconE‐92 14

EnerconE‐101 86

EnerconE‐112 10

EnerconE‐115 10

EnerconE‐126 12

EnronWind1.5sl 6

FrisiaF‐48 5

FrisiaF‐56 5

FuhrländerFLMD‐77 6

GamesaG‐52 3

GamesaG‐58 39

GamesaG‐80 72

GamesaG‐87 8

GEWind1.5 22

GEWind1.5s 10

GEWind1.5sl 61

GEWindEnergyGE2.5‐119 2

GEWindEnergyGE2.5‐120 11

TypeofTurbine No.ofTurbines

MiconM1500 5

Nedwind40/500 2

NEGMiconM700 2

NEGMiconNM64 2

NEGMiconNM82 3

NordexN‐29 2

NordexN‐60 36

NordexN‐90 39

NordexN‐100 12

NordexN117 2

PowerwindPW‐90 1

Repower3.X 6

Repower3.4M 13

Repower5M 21

Repower6.2M152 1

RepowerMD‐77 10

RepowerMM‐92 2

Senvion3.2M114 13

SiemensSWT‐2.3 1

SiemensSWT‐3.6 60

SüdwindN710 1

SüdwindS‐70 4

TackeTW‐60 1

TackeTW‐500 1

TackeTW‐600 5

VestasV‐44 1

VestasV‐47 43

VestasV‐52 31

Page 52: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 52/89

TypeofTurbine No.ofTurbines

VestasV‐66 1

VestasV‐80 137

VestasV‐82 2

VestasV‐90 65

TypeofTurbine No.ofTurbines

VestasV‐112 16

VestasV‐126 12

Total 3457

4.3 VibrationMeasurements/GearBoxAnalysis

DeutscheWindGuardprovidesofflinevibrationmeasurementsofthewholedrivetrainforthosewindturbinesthatdonothaveaCMSinstalled.Incombinationwithanendo‐scopic inspectionofwheelsandbearingsof thegearboxandanoil analysis,problemsand shortcomings can be detected at a very early stage. In total,WindGuard has per‐formedroundabout150measurementsovertheyears.

No. InternalProjectNo.

Country TypeofService TypeofTurbine

No.ofTur‐bines

Year Client

1 VW06130 Germany VibrationAnalysisofDriveTrain

VestasV80 9 2006 GermanOperator

2 VW06132 Germany VibrationAnalysisofDriveTrain

VestasV80 4 2006 GermanOperator

3 VW06133 Germany VibrationAnalysisofDriveTrain

VestasV80 4 2006 GermanOperator

4 VW09165 Germany VibrationAnalysisofDriveTrain

VestasV80 17 201020112012

GermanOperator

5 P09099 Germany EndoscopicInspec‐tionofGearbox

SWT2.3 1 2012 GermanOperator

6 VW11025 Germany EndoscopicInspec‐tionofGearbox

VestasV80,V90,V82,RepowerMD77

9 2011 AustrianOperator

7 VW11040 Germany EndoscopicInspec‐tionofGearbox/VibrationAnalysisofDriveTrain

VestasV42 1 2011 GermanOperator

8 VW11121 Germany EndoscopicInspec‐tionofGearbox

NordexN60 1 2011 GermanOperator

9 VW11119 Germany EndoscopicInspec‐tionofGearbox

SiemensSWT2.0,GE1.5s,1.5sl

15 2012 GermanOperator

Page 53: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 53/89

No. InternalProjectNo.

Country TypeofService TypeofTurbine

No.ofTur‐bines

Year Client

10 VW12068 Germany EndoscopicInspec‐tionofGearbox

PowerwindPW90

1 2012 GermanOperator

11 VW12062 USA EndoscopicInspec‐tionofGearbox

GamesaG87 1 2012 USInsur‐anceCom‐pany

12 VW12076 Germany EndoscopicInspec‐tionofGearbox

VestasV80 4 20122013

GermanOperator

13 VW13138 Germany EndoscopicInspec‐tionofGearbox/VibrationAnalysisofDriveTrain

TackeTW500

1 2013 GermanOperator

14 VW13152 Germany EndoscopicInspec‐tionofGearbox

ArevaM5000

1 2013 GermanOperator

15 VW13163 Germany EndoscopicInspec‐tionofGearbox

Repower3.4M

1 2013 GermanOperator

16 VW13165 Germany EndoscopicInspec‐tionofGearbox

SiemensSWT2.0

1 2013 GermanOperator

17 VW13180 Germany EndoscopicInspec‐tionofGearbox

NEGMiconNM64/150

0

9 2013 GermanInspectionBody

18P05005 Germany

VibrationAnalysisofDriveTrain

VestasV‐42 1 2014GermanOperator

19VW12076 Germany

EndoscopicInspec‐tionofGearbox VestasV‐80 9 2014

GermanOperator

20 VW13164 Germany EndoscopicInspec‐tionofGearbox

GE1.5 11 2014 GermanOperator

21VW13164 Germany

EndoscopicInspec‐tionofGearbox

SiemensSWT2.0

3 2014GermanOperator

22VW13187 Germany

EndoscopicInspec‐tionofGearbox VestasV‐42 1 2014

GermanOperator

23VW14104 Germany

EndoscopicInspec‐tionofGearbox

PowerwindPW‐90

1 2014GermanOperator

24VW14108 Germany

EndoscopicInspec‐tionofGearbox

PowerwindPW‐90

1 2014GermanOperator

25 VW14122 Germany EndoscopicInspec‐tionofGearbox

NordexN60 1 2014 GermanOperator

26VW14204 Germany

VibrationAnalysisofDriveTrain VestasV‐80 2 2014

GermanWTGEx‐pert

Page 54: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 54/89

No. InternalProjectNo.

Country TypeofService TypeofTurbine

No.ofTur‐bines

Year Client

27VW14222 Germany

EndoscopicInspec‐tionofGearbox

Repower3.4M 1 2014

GermanOperator

28VW14223 Germany

EndoscopicInspec‐tionofGearbox

Repower3.4M

3 2014GermanOperator

29VW14224 Germany

EndoscopicInspec‐tionofGearbox

Repower3.4M 1 2014

GermanOperator

30 VW15221 Germany EndoscopicInspec‐tionofGearbox

Repower3.4M

1 2015 GermanOperator

31 VW15111 Germany EndoscopicInspec‐tionofGearbox

PowerwindPW‐90

1 2015 GermanOperator

32 VW15149 Germany EndoscopicInspec‐tionofGearbox

Repower5M

1 2015 GermanOperator

33 VW15186 Germany EndoscopicInspec‐tionofGearbox

PowerwindPW‐90

1 2015 GermanOperator

34 VW15195 Germany EndoscopicInspec‐tionofGearbox

NordexN60 1 2015 GermanOperator

35 VW15244 Germany EndoscopicInspec‐tionofGearbox

FuhrländerFL77

1 2015 GermanOperator

36 VW15132 Germany EndoscopicInspec‐tionofGearbox

NordexN60 5 2015 GermanOperator

37 VW1657 Germany VibrationAnalysisDriveTrain

GEWindEnergyGmbH

GE2.5‐120

2 2016 GermanWTGEx‐pert

38 VW15132 Germany EndoscopicInspec‐tionofGearbox

NordexN60 10 2016 GermanOperator

39 VW16150 Germany EndoscopicInspec‐tionofGearbox

GEWindEnergyGmbH

GE2.5‐120

5 2016 GermanOperator

40 VW16153 Germany EndoscopicInspec‐tionofGearbox

GEWindEnergyGmbH

GE2.5‐120

2 2016 GermanOperator

41 VW16185 Germany EndoscopicInspec‐tionofGearbox

GEWindEnergyGmbH

GE2.5‐120

2 2016 GermanOperator

42 VW16220 Germany EndoscopicInspec‐tionofGearbox

SWT‐1300/69

2 2016 GermanOperator

Page 55: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 55/89

4.4 ThermographicBoundaryLayerVisualisationofWindTurbineRotorBladesinOperation

Thelocationofthelaminar‐turbulenttransitionhasadirecteffectontheperformanceofanairfoil.Thermographyhasbeenavaluabletoolforboundarylayervisualisationforseveralyears inbothwindtunnelsandotherapplications.Theuseofhigh‐speed,highsensitivitythermalimagingsystemsincombinationwithlongfocallengthlensesallowsapplyingthismethodtomegawattrangewindturbinesinoperation,inwhichtheinves‐tigated rotor blade and themeasurement position are several hundredmeters apart.Measurements deliver qualitative information regarding the transition location alongtherotorblade,andallowcomparisonsbetweendifferentoperationalstatesandcondi‐tions.

WindGuardOffers:

Ahighspeedactivelycooled640x512pixelsInSb‐focal‐plane‐arraywithathermalreso‐lutionbetterthan0.025Kisusedtogetherwithatelephotolenstoacquirehighresolu‐tionthermal imagesofrotorblades inoperation.The laminar‐turbulenttransitionandlaminarflowregionsarevisibleontheimages.Thereducedfieldofviewrequiresstitch‐ingseveralimagestoobtainasingleimageofonerotorblade.

SinceincorporatingthisserviceintotheWindGuardUniverse,wehaveperformedfourmeasurementsinGermanyandfourinDenmark.

4.5 AnalysisofWindFarmOperationalData

The data stored by thewind turbine orwind farm control system (SCADA) has beenidentified tobe a valuable sourceof information formanypurposes.BasedonSCADAdata,differentanalysesarepossibleandofferedbyWindGuard:

Errorstatisticsandfaultanalysis Evaluationofwindturbineavailabilityandassociatedenergylosses Evaluationof“true”windturbineavailability(independentfrommanufacturer’s

definitionavailability) Definitionoftechnicalandenergeticavailability Evaluationofwindturbinenon‐availabilityintermsofenergyloss Analysisofwindturbinecontrolparameters,e.g.pitchangle,rotorspeed,tempera‐

ture,phaseshiftbetweenvoltageandcurrent Relativepowerperformanceanalyses Long‐termenergyyieldassessments

Page 56: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 56/89

Country No.ofWindFarms

Denmark 2

France 3

Germany 30

GreatBritain 2

Ireland 5

Country No.ofWindFarms

Netherlands 1

Sweden 1

Turkey 4

Total 48

Thefollowingtablecontainsafewselectedreferenceprojectswithamoredetailedex‐planationoftheservicesdelivered.

Year ProjectName,RatedPower

TypeofServices Client

2009/2010 MiaoliiWindFarm,Taiwan

49,8MW

Assessmentofoperationalwindfarmdata:

Evaluationofwindfarmoperationaldata(SCADAdata),includingassessmentoftheLongTermAverageEnergyOutput.

MacquarieIn‐ternational

InfrastructureFundLimited

2010 Confidential,Tur‐key

24MW

Performanceofanassessmentofoperationaldatawiththeaimtoanalyzetheconsiderabledeviationstotheinitialenergyyieldstudy,in‐cludingtheanalysisofpossibleoperationalprob‐lemsoftheturbinesandindicationsonthepow‐erperformanceoftheturbines.

Confidential

2012 Confidential,

Ukraine

57,5MW

Evaluationofmeasurementmastdataincombi‐nationwiththeanalysisofoperationalwindturbinedatatopredicttheenergyyieldaswellastominimizetherelatedcalculationuncertainties.

Confidential

2012 Croisette,France

12MW

EvaluationofoperationaldataasbasisforanEnergyyieldassessment,usingwindmastmeas‐urementdataasreference.

EnertragEts.France

2013 Kores,Turkey

15MW

EvaluationofoperationaldataasbasisforanEnergyyieldassessment,usingwindmastmeas‐urementdataasreference.

KoresKocadağRüzgarEnerjisiSantraliÜretim

A.Ş.

2013 Bergres,Turkey

70MW

Analysisandcheckingtheusefulnessofopera‐tionaldatafromneighbouringwindturbinesandasresultitsconsiderationwithwindmastmeas‐urementdataforanenergyyieldassessment.

BERGRESElekt‐rikÜretimA.S.

2013 BorkumWestII

400MW

Detailedevaluationofproductiondatafromop‐eratingGermanoffshorewindfarm,Develop‐mentandrealisationofmethodologytopredictdailyandmonthlyenergyyieldofGermanoff‐shorewindfarm,relevantforcalculationofpen‐altyparametersforgridconnectiondelay,Evalu‐

TrianelGmbH,Lombardenstr.28,Aachen

Page 57: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 57/89

Year ProjectName,RatedPower

TypeofServices Client

ationandassessmentofnacelleanemometerdataforpredictionofdailyandmonthlyenergyyieldofGermanoffshorewindfarm,relevantforcalculationofpenaltypaymentsforgridconnec‐tiondelay.

2013 Battenoert,Neth‐erlands

12MW

Analysisofoperationaldataofneighbouringwindturbinesforverifyingthemastmeasure‐mentdata.

TriodosBankN.V.

2013 Riffgat,Germany

113,4MW

Powercurveevaluationonthebasisofopera‐tionaldata,additionalnacelleanemometerdataandadditionalairpressuredata.

EWEErneu‐erbareEnergien

GmbH

2013 Confidential,

Germany

24MW

Correlationandextrapolationofmeasurementdatawithwinddataofneighboringexistingwindturbines,extendingthemeasurementdataforatime‐periodof15‐months,includingtheevalua‐tionofseasonaleffects.

Confidential

2013 ProjectinSweden

Researchactivity:Analysisoftheoperationaldata(SCADA)tofigureoutthereasonsfortheperformancedifferencesbetweenactualvalueandset‐pointvalue

Confidential

2014 BardOffshoreI

400MW

Operationalwindfarmdataanalysis,AssessmentofWindFarmEnergyYieldonthatbasis.

OceanBreezeEnergyGmbH&

Co.KG

2014 Dalwitz,

Germany

27,45MW

SCADAdataanalysis,includingthefilteringandcorrection(asfaraspossible)oftheproductiondata,showingcurtailmentsregardingthemaxi‐mumpower.

ewzErneu‐erbareEnergie

2014 Killybegs,Ireland

13,8MW

EvaluationofSCADAdata,includingtheassess‐mentoftheoperationallossesduetonon‐idealbehaviorofthewindturbines.

POWERCONWINDLtd.

2014 Trakres,Turkey

33MW

Analysisofoperationaldataofneighbouringwindturbinesasbasiswiththewindmetmastsdatafortheenergyyieldassessment.

TrakresElektrikÜretimA.S.

2014 Confidential,Ger‐many

17,5MW

Correlationandextrapolationofmeasurementdatawithwinddataofneighboringexistingwindturbines,extendingthemeasurementdataforatime‐periodof24‐months,includingtheevalua‐tionofseasonaleffects.

Confidential

2014 Carrowleagh,Ire‐land

37MW

Analysisofoperationaldata(SCADA)ofaneigh‐bouringwindfarmhavingahighersignificancefortherespectiveconclusionsregardingthewindfarmenergyyield.

POWERCONWINDLtd.

2014 DanTysk,Offshore Realisationofmethodologytopredict15‐ VattenfallGer‐

Page 58: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 58/89

Year ProjectName,RatedPower

TypeofServices Client

windfarm

288MW

minutestimeseriesoflostenergyyieldofoff‐shorewindfarm,relevantforcompensationpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Evaluationofnacelleanemometerdata,performanceofmeas‐urementcampaignatoffshorewindfarmandinvestigationofusabilityforthispurpose;con‐sultingongridcompensationrelatedquestions.

many

2015/2016 GlobalTechI,Off‐shorewindfarm

400MW

Evaluationandlongtermextrapolationofmeas‐uredwinddata,timeseriescalculationoftheenergyyieldofthewindfarmwithanalysisoftechnicallossesandtheirinterdependencies,assessmentoflongtermenergyyield,relatinguncertaintiesandtechnicallossesforthewindfarmproject.

GlobalTechIOffshoreWind

GmbH

2015 GodeWind2,252MW

Realisationofmethodologytopredict15‐minutestimeseriesoflostenergyyieldofoff‐shorewindfarm,relevantforcompensationpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Evaluationofnacelleanemometerdata,performanceofmeas‐urementcampaignatoffshorewindfarmandinvestigationofusabilityforthispurpose;con‐sultingongridcompensationrelatedquestions.

Determinationofthedistancebetweenthewindturbinesoftheoffshorewindfarmandthecoast‐line.

DONGEnergy,Germany

2015 Cumbria,

GreatBritain

16MW

Operationaldataassessment:dataevaluation,correctionsofoperationaldataandlong‐termassessmentofoperationaldataconditions;Calcu‐lationoftheexpectedenergyyieldbasedontheresultsoftheoperationaldataanalysis.

SternWindLTD,SternWindSARL

2015 Skalleberg(19,4MW),Mungseröd

(15MW),

Sweden

Calculationofdiurnalandmonthlyenergydistri‐butions(12x24Matrix)onbasisofoperationaldata.

ewzAtlanticSverigeAB

2015 Confidential,Off‐shoreWindFarm

288MW

Realisationofmethodologytopredict15‐minutestimeseriesoflostenergyyieldofoff‐shorewindfarm,relevantforcompensationpaymentsforgridconnectiondelayandoutage,andapplicationforseveralmonths.Evaluationofnacelleanemometerdata,performanceofmeas‐urementcampaignatoffshorewindfarmandinvestigationofusabilityforthispurpose;con‐sultingongridcompensationrelatedquestions.

Confidential

Page 59: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 59/89

Year ProjectName,RatedPower

TypeofServices Client

2015 Confidential,

Germany

23,1MW

Verificationoftwowindenergyyieldassess‐mentsforoneplannedwindfarm:

Examinationoftheanalysisandevaluationofoperationalwindturbinedata,includinglong‐term‐correlationasbasisfortheenergyyieldassessmentoftwoenergyyieldassessmentre‐ports.

Confidential

2015 Hyndburn,UK

8,2MW

Analysis of operational wind farm data in con‐junctionwithmastmeasurement data. As basisfor the Energy Yield Assessment. Data from theHyndburn mast was used as reference and forestimatingthesitewinddirectiondistributionoftheoperationaldata.

EnergiekontorUKLtd

2015/2016 Fischbach,Germa‐ny

6,9MW

EvaluationofSCADA‐dataasadditionalsourcefortheenergyyieldassessment.Theanalysisimpliedanexaminationofincorrectvaluesandthecorrectionofdeviatingperformance.

WSBProjectGmbH

2016 Schönwalde‐Altenkrempe,

Germany

15MW

Energyyieldassessmentonbasisofoperationaldataevaluationofreferenceplants,extendingtheoperationaldatabymeansoflong‐termdataandcorrelationanalysistoatime‐periodof21‐months.

PROKONRe‐generativeEn‐ergieneG

2016 Lüdersdorf,

Germany

26MWoftheop‐erationaldataportfolio

Energyyieldassessmentonbasisofoperationaldataevaluationofreferenceplants,extendingtheoperationaldatabymeansoflong‐termdataandcorrelationanalysistoatime‐periodof17‐months.

EEConstructionGmbH&Co.KG

2016 ProjectinUK

10,25MW

AnalyseofoperationalSCADAdataandrelatingittothelongertermperiodofthepast12years,havingthebestpossibleestimationoftheaver‐ageenergyyieldpotentialatthewindfarmsite.

Confidential(projectdevel‐

oper/institutionalinvestor)

2016 ProjectinUK,

16,4MW

Analysisofoperationaldata(SCADA)providingamoresolidbasisforinvestmentdecisionsinad‐ditiontothealreadyperformedenergyyieldassessmentreport.

Confidential

(projectdevel‐oper

/institutionalinvestor)

Page 60: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 60/89

Year ProjectName,RatedPower

TypeofServices Client

2016 ProjectinFrance,10MW

Energyyieldassessmentonbasisofoperationaldatafromnearbywindturbines.Combinationofthemast’swinddirectiondistributionandwindspeedstatisticswiththeoperationaldatainor‐dertoproduceavirtualmastrepresentingtheconditionswithintheexistingwindfarm.

Confidential

Page 61: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 61/89

5 WindTunnelCentre

Optimalconditionsformeasurements,testsandresearchforthewindindustryandfarbeyond:that’swhatWindGuard’sWindTunnelCentrestandsfor.Thefacilitiesformul‐tiplefieldsofapplicationstretchoutaround2.500squaremeters.

TheWindTunnelCentreopeneditsdoorsin2003toprovidehighprecisionanemome‐ter calibrations for thewind energy industry.With these calibrations, the accuracy ofwind measurements improved significantly. As a 1% deviation of the measurementfromtheactualwindspeedarereflectedin3%energyyieldloss,thismakesahugedif‐ference.

5.1 AnemometerandWindDirectionSensorCalibrationandClassifi‐cation

DeutscheWindGuardistheleadingexpertwhenitcomestothecalibrationofanemome‐ters and wind direction sensors. Our wind tunnel centre consists of four calibrationwindtunnelsandoneclimaticwindtunneltoconductresearchontheprocessof icingonanemometersandwinddirectionsensors.DeutscheWindGuardalsooperatesa re‐searchwindtunnelwiththeabilitytovarytheambientpressure,respectivelyairdensi‐tyandtemperatureatthesametime.ThisfurtherexpandsWindGuard’sabilitytoassessanemometerperformanceandconductanemometerclassification,meetingIEC61400‐12‐1requirements,eveninthenewest2016revision.

Fourwindtunnelsspecificallydesignedforanemometercalibrations AccreditedbyDeutscheAkkreditierungsstelle(DAkkS)forthecalibrationofane‐

mometersaccordingtoDINENISO/IEC17025 Accreditedforflowspeedsfrom0.5m/supto38m/s RecognizedbyMEASNET NationalMetrologyInstituteofGermany(PTB)isusingwindtunnelVarel2asone

facilitytoembodytheGermannationalstandardfortheflowspeedofair.Thena‐tionalstandardofflowspeedishencerealizedthroughapermanentlyinstalled;PTBownedandcalibrated,LaserDopplerAnemometer(LDA)withinourtestsectionofwindtunnelVarel2

FirsteveracceptedcalibrationlaboratoryforanemometercalibrationbytheIECRE Ownopenfieldtestfacilityforanemometertestingandclassification ClassificationofanemometersaccordingtoIEC61400‐12‐1

Page 62: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 62/89

DeutscheWindGuardisalsoaccreditedtoperformcalibrationsoftheflowdirection(horizontalandverticalflow).Thereforeweareabletooffercalibrationofwinddirec‐tionsensors(variationofrelativehorizontalflowangle)and2Daswellas3Dsonican‐emometers(variationofrelativehorizontal‐andverticalflowangle).Thisisindispensa‐blewhenatractablewindtunnelcalibrationofwinddirectionsensorsisrequired. AccreditedbyDeutscheAkkreditierungsstelle(DAkkS)forthecalibrationofwind

vanesaccordingtoDINENISO/IEC17025 WinddirectionsensorcalibrationaccordingtoIEC61400‐12‐1,AnnexN Variationofrel.horizontalflowdirectionatarangeof0…360deg(continuousor

stepwise) Variationofrel.inclinationflowdirectionatarangeof±30deg

WindGuardhasperformedanemometerandwinddirectioncalibrations formorethan500customersfrommorethan40differentcountriesworldwide

Thenumberofcalibrationsperyearislistedinthetablebelow:

Year NumberofAnemometerandWindDirectionSensorCali‐

brations

2003 523

2004 862

2005 1548

2006 2908

2007 4298

2008 5600

2009 7900

2010 8850

2011 12081

2012 17300

2013 16500

2014 18685

2015 18430

2016 18500

Total 133985

Page 63: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 63/89

5.2 2DAirfoilMeasurementsinAcousticallyOptimisedLargeWindTunnelinBremerhaven

DeutscheWindGuard offers 2D airfoilmeasurements at Reynolds numbers of up to 6million, with wind speed of up to 100 m/s. The test section dimensions are(WxHxL)=(2.7mx1.25mx5m).

Themaximumairfoilchordinthetestsectionis900mm.

Standardmeasurementsinclude:

‐ 2D airfoil measurements (with surface pressure measurements, wall pressuremeasurements,wakerakeandforcebalances)

‐ Laminar/turbulenttransitionlocationmeasurementsusinghigh‐speedthermog‐raphy

‐ 360degreepolars(withfullyequippedmodels)

‐ TiporWinglettests(atspeedsofupto50m/s)

Additionaltestssuchascalibrationofsensors,loadmeasurementsoncomponents,etc.canbeoffereduponrequest.

Seetablebelowfordetails:

Country NumberofTurbines

Denmark 8

France 1

Germany 22

Netherlands 1

Total 32

Page 64: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 64/89

6 MeasurementsonWindTurbines

6.1 WindTurbinePowerCurveTesting

DeutscheWindGuardisaccreditedasatestinglaboratoryforthemeasurementofwindturbine power curves. Apart from measurements according to accepted standards,DeutscheWindGuardhasdevelopedsomeadditionalmethodstoverifythepowerper‐formanceofwindturbines,inpartwithoutapplicationofacostlymetmast.

The power performance of wind turbines often deviates from the guaranteed powercurveor fromthatpowercurve,which ismeasuredatthesametypeof turbineunderotherconditions.Furthermore, thewindturbinepowerperformance isoftennotopti‐mised.Theverificationofpowercurves inwind farms isa service that is increasinglyaskedforbywindfarmoperatorsinordertoverifytheperformanceguaranteedbythemanufacturerortoidentifypotentialforoptimisation.Sofar,DeutscheWindGuardhasanalysedpower curvesofwind turbineswith anoverall powerof around600MW inwindfarmswithatotalcapacityofabout6GW.

Themaincharacteristicsofourservicesare:

AccreditedaccordingtoDINENISO/IEC17025:2005forpowerperformancemeas‐urementsaccordingtoIEC61400‐12‐1Ed.1,draftofIEC61400‐12‐1Ed.2,IEC61400‐12‐2andtheGermanGuidelineTR2(FGW)andacceptedbyMEASNET

Extensiveexperiencewithnewtechnologies,likeapplicationofnacelleLiDARS,scanningLiDARsonthetowerfootandnumericalsitecalibrations

EfficientverificationofeachwindturbinewithinawindfarmbyapplicationofInte‐gralorRelativePowerCurveAnalysis

Resultsarewellacceptedbywindturbinemanufacturers Technicalelaborationofguaranteesregardingtheverificationprocedure,fulfilment

criteriaandmodesofpayment Experiencewithcertificationmeasurementsatwindturbinesfrom30kWto7.5MW Hiredbydifferentwindturbinemanufacturersforadvice,researchanddevelopment

inthefieldofimprovingproceduresforpowerperformancetesting:investigationofinfluenceofmeteorologicalconditionsonpowerperformance,newLiDARapplica‐tions,applicationofnacelleanemometry,applicationofnumericalsitecalibration,improvementoftermsofpowercurvewarranties,uncertaintyanalysis,uncertaintyreductionbymultipleturbinetesting

Page 65: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 65/89

Country No.ofProjects

RatedPowerofTestedTurbines

ProjectCapacity

[‐] [‐] [MW] [MW]

Australia 3 25 621

Bulgaria 2 18 312

China 1 3 3

Colombia 1 1 1

Croatia 1 3 34

Denmark 4 13 466

Finland 1 3 3

France 1 2 12

Germany 54 366 1201

GreatBritain 5 27 1320

Italy 3 23 149

Macedonia 1 2 37

Netherlands 1 3 3

Romania 2 24 381

Sweden 2 14 288

Turkey 3 12 45

Ukraine 2 24 200

UnitedStatesofAmerica 1 5 152

Total 88 568 5228

Page 66: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 66/89

6.2 AcousticNoiseMeasurementsonWindTurbines

DeutscheWindGuardConsultingGmbH is accredited for acousticnoisemeasurementssince2012andachieved conformitywith theFördergesellschaftWindenergieundan‐deredezentraleEnergien(FGWe.V.)requirementsforacousticnoisemeasurementsonwindturbines.

Standardisedacousticnoisemeasurementsonwindturbinesareusuallyperformedac‐cordingtoIEC61400‐11.Majorquantitiestodescribethenoisecharacteristicsofawindturbinearetheoverallsoundpowerlevel,socalled“tonality”(mostlyduetomechanicalnoisecomponents)andimpulsivity(periodicalsoundpowerfluctuations).Inindividualcases, analysis of low frequencynoise is of interest.Weoffer acoustic noisemeasure‐ments according to the state‐of‐the‐art standards and procedures as well as specificanalysesrequestedbyourclients.Ingeneral,standardisednoisemeasurementsarealsopartoftheturbinecertificationprocess.

Thedominatingpartoftheacousticnoiseemissionisusuallycausedbytheaerodynamicnoisefromtherotorblades.Adverseeffectsontheoverallsoundpowerlevelcanespe‐cially be causedby anunfavourable designof blade tips. Anothernoise source isme‐chanicalnoisecausedbythegearbox,thegenerator,differentaggregatesortheinvert‐er. In general, differentnoise sources canbe identifiedby adetailed analysis of noisespectra(i.e.frequencyanalysis).Thisway,valuableindicationscanbeprovidedtowindturbinesuppliersorowners,onhowtoreducethenoiseemissionandhowtoremedyunwantednoisecharacteristics.WindGuardstaffmemberslookbackonmanyyearsofexperiencegainedfromhundredsofcommercialnoisemeasurementsand,also,variousinternationalresearchprojectsonaerodynamicnoisereduction,optimisationofmeas‐urementproceduresandoutdoornoisepropagation.

After awind farmhas been commissioned, verification of the acoustic noise emissionmayberequestedby localauthorities–sometimesatregular intervalsthroughouttheoperatingperiodofwindfarms,inordertoensureobservationofthe(legal)noiselimits.Also, noise verification measurements are offered by Deutsche WindGuard, utilisingmeasurement techniques specifically developed for outdoor measurements underwindyconditions.

Page 67: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 67/89

WindGuardoffers:

Independentandprofessionalnoisemeasurementsaccordingtostate‐of‐the‐artpro‐ceduresandstandards(e.g.IEC61400‐11),e.g.forprototypetestingandcertification

Verificationmeasurementsafterwindfarmcommissioning Consultingservicesforanykindofwindturbinenoiserelatedissues(noisereduc‐

tion,optimisation,individualanalyses,etc.)

Thefollowingtablegivesanoverviewoftheperformednoisemeasurements(onlythoseperformedunderWindGuardemployment):

Country No.ofTurbines

Austria 27

Belgium 3

Finland 3

Germany 147

Total 180

Page 68: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 68/89

6.3 LoadMeasurementsonWindTurbines

DeutscheWindGuardhasbeenaccreditedasatestinglaboratoryforthemeasurementofmechanical loadsatwindturbinessince2013.Apart frommeasurements forcertifica‐tionpurposesaccordingtoIEC61400‐13standard,DeutscheWindGuardsupportsman‐ufacturerswithdifferenttypesofmeasurementsforinternaldesignoptimization.

Currently themechanical load group in cooperationwith turbinemanufacturers per‐forms test‐measurements with the scope the further development of measurementtechnics, long termmonitoringandmeasurementsathybrid towers.Thegroup isalsoinvolvedintheIEC61400‐13maintenancegroup,whichcurrentlydevelopedanewre‐visionofthestandard.

No. InternalProjectNo.

Country CapacityofTurbine

No.ofTurbines

YearofMeasurement

Client

[‐] [‐] [‐] [MW] [‐] [‐] [‐]

1 Internal Germany 3,4 1 2013 WindGuard

2 VC14233 Germany 3,4 1 2014 University

3 VC15369 Germany 3,2 1 2015 Manufacturer

4 VC15228 Finland 2,5 1 2015 Manufacturer

5 VC16039 Germany DriveTrain 1 2016 Manufacturer

Page 69: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 69/89

7 Offshore‐Services

WindGuard participated actively in and promoted the development of offshore windenergyinGermanyfromtheverybeginning.Since2010,DeutscheWindGuardOffshorehaspooled theexpertisewithin theWindGuardGroup for theoffshorewind industry.Alongside certified offshore‐safety trainings, the experts of DeutscheWindGuard Off‐shoreoffertheirknow‐howinallareasofoffshore‐consulting.Coreareasofactivityaretechnical due diligence, project management and planning, offshore load assessment,offshore structuredesign, technical support and employer requirements,maintenanceconceptsandonshorewindparkandprototypeplanning.

7.1 Offshore‐Consulting

DeutscheWindGuard offers consulting services in the entire process of offshorewindfarmdevelopment – from licenceplanning to construction and executionplanning, aswellasduring theoperationalphase.TherenownedexpertsofWindGuardofferhigh‐level engineering services and assume the management of subprojects when neededthroughout the entireproject life cycle. Because of the experienceofWindGuard staffand their extensive participation during the realisation and operation of the Germanoffshoretestfieldalphaventusaswellaslongyearexperienceinoffshoresupportstruc‐turedesign, loadassessmentand technical support fordifferentGermanoffshorepro‐jects,WindGuardisoneoftheleadingconsultingcompaniesforengineeringservicesintheGermanoffshorewindmarkettoday.Variousenergyyieldassessments(seeSection2.5)andotherstudies(seeSection2.6)havebeenperformedforoffshorewindenergyprojects.

Mainreferenceprojects:

No. InternalProjectNo.

Country Subject Year Client

1 VC08061 Germany Technicalduediligence:400MWoffshore‐project

2008 Investor

2 Germany QAWECforoffshoreworks 2010‐2012

Projectowner

3 VO10101 Germany Studycomparingdifferentfoundationconcepts

2010‐2011

Offshoreinvestor

4 VO10102 Germany Supportfortechnicalduedili‐genceandconsultancy

2010‐2013

ProjectGlobalTech1

5 VO11005 Germany Leadingofsub‐project 2011‐2013

Foundationsup‐plier

Page 70: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 70/89

No. InternalProjectNo.

Country Subject Year Client

6 VO11016 Germany StudyconcerningflyingdebrisofWECblades

2011 Projectowner

7 VO11011 Germany EvaluationofO&Mconcept 2011‐2012

ProjectBWII

8 VO11043 Germany ManufacturingcontrolofWECcastcomponents

2011‐2013

ProjectGlobalTech1

9 VO11044 Germany Conceptforpowercurvemeas‐urement

2011‐2012

Offshoreprojectowner

10 VO11090 Germany TechnicalduediligenceforGermanoffshoreproject

2011 Utilitycompany

11 VO11097 Germany Supportfortechnicalduedili‐gence,employersrequirements

forEPCcontract

2011‐2013

Offshoreprojectowner

12 VO11040 Germany Technicalduediligence:WECprototype

2012 Turbinemanufac‐turer

13 VO12022 Germany HazardanalysisstudyforonshoreWEC

2012 Turbinemanufac‐turer

14 VO12070 Germany Supportfor5MWprototypeplanningprocess

2012 Turbinemanufac‐turer

15 VO12080 Germany StudytoairdropoficingatWEC 2012 Projectowner

16 VO12093 Germany StudytoairdropoficingatWEC 2012 Projectowner

17 VO12176 Germany Projectplanningsupportforrepoweringprojectonshore

2012‐2014

Projectowner

18 VO12179 Germany Planning,approval,erectionandprovisionofawindmetmast

onshore

2012‐2013

Turbinemanufac‐turer

19 VO12203 Germany Feasibilityandpre‐designformonopilefoundation–offshore

2012‐2013

Turbinemanufac‐turer

20 VO12245 Germany Technicalsupportloadassess‐mentandfoundationdesign–offshorenorthseaproject

2012‐2013

Projectowner

21 VO13074 Germany Loadcalculationsupportandverificationwork

2013‐2014

Projectowner

22 VO13087 Germany StudytoairdropoficingatWEC 2013 Projectowner

23 VO13093 Germany Technicalsupportofinstallationwork

2013 Projectowner

24 VO13102 Germany TechnicalsupportformarketlaunchofaWEC

2013 Projectowner

25 VO13121 France Productreviewofamanufac‐turerforoffshoreproducts

2013‐2014

InstitutionoftheStateofFrance

Page 71: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 71/89

No. InternalProjectNo.

Country Subject Year Client

26 VO13126 Germany Technicalsupportatinstallationwork‐shimmingprocess

2013‐2014

Projectowner

27 VO13144 Germany ManufacturingcontrolofWECblades

2013‐2014

Projectowner

28 VO13156 Germany Verificationofajacket‐design 2013 Projectowner

29 VO13170 Germany Technicalconsultingforprojectexecution

2013‐2014

Projectowner

30 VO13180 Germany Technicalprojectmanagementforsub‐project

2013 Projectowner

31 VO13270 Germany Loadcalculationsupportandverificationwork

2013‐2014

Projectowner

32 VO13345 Germany StudytoairdropoficingatWEC 2013‐2014

Projectowner

33 VO13339 France Productreviewofamanufac‐turerforoffshoreproducts

2013‐2015

InstitutionoftheStateofFrance

34 VO14044 Germany Verificationofqualitydocumen‐tation,qualitytestofindividual

components

2014 Projectowner

35 VO14046 Germany TechnicalsupportforDesignBasis,loadcalculationandstructureverification

2014‐2015

Projectowner

36 VO14104 Germany Verificationofstructuralandmechanicalengineering

components

2014 AssubsupplierforWindGuardCerti‐

fication

37 VO14137 Germany Loadcalculationsupportandverificationwork

2014 Projectowner

38 VO14184 Germany VerificationofcomponentsofWEC

2014 AssubsupplierforWindGuardCertification

39 VO14235 France Productreviewofamanufac‐turerforoffshoreproducts

2014‐2015

InstitutionoftheStateofFrance

40 VO14264 Germany StudytoairdropoficingatWEC 2014 Projectowner

41 VO14265 Germany Creationofcommissioningprocedure

2014 Projectowner

42 VO14347 Germany Sitespecificloadcalculationandloadcomparisonforverification

ofsuitabilityofWEC

2014‐2015

Turbinemanufac‐turer

43 VO14398 Germany TechnicalsupportjacketdesignOSS

2014‐2015

Projectowner

Page 72: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 72/89

No. InternalProjectNo.

Country Subject Year Client

44 VO14398 Germany InspectionofatransportdamageofaWEC

2014 AssubsupplierofDeutscheWind‐

Guard

45 VO15007 Germany LongtermtechnicalsupportWECandTURfoundation

2015‐2016

Windfarmopera‐tor

46 VO15011 Germany 7xstudytoairdropoficingatWEC

2015 Projectowner

47 VO15034 France Productreviewofamanufac‐turerforoffshoreproducts

2015 InstitutionoftheStateofFrance

48 VO15086 Germany 3xprojectforturbinesiteloadverification

2015 Turbinemanufac‐turer

49 VO15196 China Windfarmevaluationassess‐ment

2015 Turbinemanufac‐turer

50 VO15198 Germany OffshoresitespecificturbineloadcalculationILA

2015 Projectowner

51 VO15210 Germany Offshorewindfarmlayoutandconceptoptimization

2015‐2016

Projectowner

52 VO15297 Germany Turbineduediligence 2015 Turbinemanufac‐turer

53 VO15306 Germany Offshorewindfarmtendermonopileconceptdesign

2015 Turbinemanufac‐turer

54 VO16006 China Offshoreprojectconsulting 2016 Turbinemanufac‐turer

55 VO16008ff. Germany Lifetimeextensionofwindturbines,analyticverification‐

severalwindfarms

2016 WindguardCerti‐fication

56 VO16014ff. Germany StudytoairdropoficingatWEC‐severalwindfarms

2016 Projectowner

57 VO16029 Germany Fireprotectionconceptseveralwindfarms

2016 Innovent

58 VO16043 Germany Verificationofstructuralinteg‐ritycausedbyturbulenceim‐pactofneighbouringwind

farms

2016 Offshorewindfarmoperator

59 VO16044 Germany Verificationofextendedscourlimitforpiledoffshorefounda‐

tions

2016 Offshorewindfarmoperator

60 VO16058 Germany Technicalexpertonflangefail‐ure/riskmitigationandrepair

process

2016 Offshorewindfarmoperator

Page 73: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 73/89

7.2 SafetyTraining

DeutscheWindGuardoffersadvancetrainingcourses,workshopsandemployeetrainingcoursesondemand thatareheld inGermanyandabroad.Thecoursesare specificallydesignedandtailoredtotheneedsofthecustomers.CoursesareheldmainlyinGermanandEnglishlanguage.Ourchoiceofproductsvariesfromcrashcoursestotrainingpro‐gramswithdurationofseveralmonths.

Aregularcourseprogrammeisofferedinthefieldofsafetytrainingforthewindindus‐try.SafetytrainingcoversthewholerangeofOn‐andOffshore‐projects.

Thefollowingcourseconceptsareofferedonaweeklybasis:

BOSS–BasicOffshoreSafety&Survival–thetrainingforstaffworkingonGermanoff‐shorewindprojectsaswellasinternationaloil&gasinstallations

COAST–CustomizedOffshoreAwareness&SafetyTraining–thetrainingforwindener‐gyspecialistsworkinginGermanyandabroadonoffshorewindprojects

GWOBasicSafetyTraining–TheGWOBSTstandardguaranteestrainingonahighlevelfortheinternationalon–andoffshorewindenergyindustry

Theyhavebeendesignedinamodularstructuretooffercustomersthechoiceofbook‐ingstand‐alonemodulesifneeded.Themainteachingcontentscover:

FirstAid(GWOandDGUVcompliant) ManualHandling(GWO) FireAwareness(GWOandDGUVcompliant) WorkingatHeights(GWOandDGUVcompliant) SeaSurvival(GWO) Helicopterunderwaterescapetraining(HUET)withtheuseofan(EBS)Emergency

BreathingSystem(incl.CompressedAirEBS) BasicSafetyInduction

Whether your mission is onshore or at sea, erecting and maintaining offshore windfarmsrequiresahighlevelofsafety.Thismakestraininginaccordancewiththelatest,internationally recognized safety standards essential for professional work whereveryoumaybedeployedinEurope.DeutscheWindGuardtrainingcoverstheproperuseofpersonalprotectiveequipment(PPE);rescuefromconfinedspace;manualhandling;fireawareness;firstaid;aswellasseasurvival,safeboattransferandhelicopterunderwa‐terescapetraining.

Our training facilities are someof themostmodernof their kindworldwide. Youwilltakepartincustom‐madecoursesforon‐andoffshorespecialists.AttheWesermarschMaritime Training Center in Elsfleth (near the city of Bremen, Germany), DeutscheWindGuard combines longstanding wind energy operation experience with extensivenauticalexpertise.

Page 74: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 74/89

TrainingwithDeutscheWindGuardisbasedonthelatestinternationalon‐andoffshoreindustrysafetystandards.DeutscheWindGuardisoneofthefirsttrainingproviderscer‐tifiedbyDNVGLRenewablesCertificationaccordingtotheBasicSafetyTrainingStand‐ardoftheGlobalWindOrganisation(GWO).Also,DeutscheWindGuard’sHUET‐TrainingiscertifiedbyDNVGL.ThemanagementsystemiscertifiedbyTÜVNordaccordingtoISO9001.DeutscheWindGuardhasperformedmore than300 safety training courseswithmorethanthreethousandparticipants.Detailscanbefoundinthetablebelow.

Year No.ofcourses No.ofdelegatestrained

2012 45 371

2013 50 577

2014 49 581

2015 62 888

2016 112 1195

Total 318 3612

Page 75: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 75/89

8 APPENDIX

8.1 ListofStudiesandScientificPolicyAdviceProjects

No. ProjectNo.

Subject Year

ofAssessment

1 P01101 OffshorestudyfortheGermanFederalMinistryfortheEnvi‐ronment,NatureConservationandNuclearSafety

2001

2 P01107 OffshorestudyfortheGermanFederalMinistryfortheEnvi‐ronment,NatureConservationandNuclearSafety

2001

3 P02126 Projectapprovalandplanning“TrainingAndResearchCentreWindEnergy”inChina

2002

4 P02129 Researchprojectaboutgridconnectionofoffshorewindfarms,GermanFederalMinistryfortheEnvironment,Nature

ConservationandNuclearSafety

2002

5 P02132 Studyaboutthestatusoftheplannedoffshorewindfarms 2002

6 VW03103 StudyonbehalfoftheGermanFederalMinistryfortheEnvi‐ronment,NatureConservationandNuclearSafetywithintheframeworkoftherevisionoftheRenewableEnergyLawEEG

2003

7 VW03108 Projectreviewsandduediligenceexerciseinconnectionwiththetakeoverofawindfarmdeveloper(company)

2003

8 VW03117 Marketsurveyandcoststudyregardingthedevelopmentofrenewableenergies/windenergy(ExperienceReportonthe

GermanRenewableEnergyLawEEG)

2003

9 VW03118 PolicyadvisoryworkwithintheframeworkoftheAmendmenttotheGermanRenewableenergyLawEEG

2003

10 VW04111 Etrow,Thermographyonwindturbines 2004

11 VW04113 Testbenchforrotorblades 2004

12 VW04127 DevelopmentofanenvironmentalstrategyfortheutilisationofwindenergyonbehalfoftheGermanFederalEnvironmen‐

talAgency

2004

13 VW04115 Studyregardingthepotentialofrepoweringprojects 2004

14 VW04118 OffshoreStudyGreenpeace 2004

15 VW04123 EC‐Asian‐EF;Studytriporganisationforvisitors 2004

16 VD04079 Feasibilitystudyofteststandforrotorblades 2004

17 VD04001

VD04027

VD04042

TechnicalConsultingforawindturbinemanufacturerwithrespecttothemitigationofmachinerycomponentvibration

ona750‐kWwindturbine

2004

Page 76: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 76/89

No. ProjectNo.

Subject Year

ofAssessment

18 VW05105 Studyregardingthedevelopmentofwindenergyutilisationuntiltheyear2020

2005

19 VW05111 ChinaWindEnergyCentre 2005

20 VW05112 WABRepoweringStudy 2005

21 VW05117 OffshoreTestSite 2005

22 VW05120 EC‐ASEAN:travelandmeetingorganisationforvisitors 2005

23 VW05128 PowerProject,Offshore,Bremen 2005

24 VW05132 StudyonbehalfoftheGermanFederalMinistryfortheEnvi‐ronment,NatureConservationandNuclearSafetyregardingthecostofwindenergyutilisationonshoreandoffshore

2005

25 VW05136 ExperienceReportontheGermanRenewableEnergyLawEEG 2005

26 VD05052 TechnicalConsultingforawindturbinemanufacturerwithrespecttothemitigationofmachinerycomponentvibration

ona900‐kWwindturbine

2005

27 VD05063 Developmentofasensorforupgradingofawindturbinesafe‐tysystem

2005

28 VD05087 ConceptionofaworkshopfortheAsian‐PacificWeeksinco‐operationwithInWEnt,GTZandDeutschland&Northwestern

PolytechnicUniversity(NPU),Xian,China

2005

29 VD05066 TechnicalconsultingservicesforapowerauthorityinLibyaaboutthetechnicalmanagementofawindfarm

2005

30 VD05056 TechnicalconsultingservicesforaTaiwanesepowerauthorityconcerningthegridconnectionofawindfarm

2005

31 VD06098 Technicalconsultingregardingthedevelopmentofthewindenergymarketonbehalfofasupplier

2006

32 VD07108 Technicalconsultingregardingthedevelopmentofthewindenergymarketonbehalfofasupplier

2007

33 ‐‐‐ PresentationIEAonthecostofwindenergyutilisation 2007

34 VW07164 FeasibilitystudyontheOffshoreServiceVesselSWATH(SmallWaterplaneAreaTwinHull)

2007

35 VW07111 Listofcriteriafortheassessmentofoffshorewindfarms,onbehalfofaEuropeanutility

2007

36 ‐‐‐ Malta:Studyontechnicalandeconomicaspectsonoffshorewindenergyutilisation,onbehalfoftheGermanFederalMin‐istryfortheEnvironment,NatureConservationandNuclear

Safety

2008

37 VW08119 Organisationandimplementationofthetouringexhibition"FascinationOffshore"

2008‐2011

Page 77: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 77/89

No. ProjectNo.

Subject Year

ofAssessment

38 VW08152 Conceptionforthetechnicalmanagementofoffshorewindfarms

2008

39 VW08155 "Kombi‐KWBonus":Scientificexpertmonitoringintheprepa‐rationofabonusforcombinedpowerplantsaccordingtothe

Power‐to‐Issue‐Statutory‐Instruments§64EEG2009

2008

40 VW08168 StudyregardingthedevelopmentofwindenergyutilisationinGermanyuntiltheyear2014

2008

41 VW09102 AcceleratingtheDeploymentofOffshoreRenewableEnergyTechnologies(ADORET)

2009

42 VW09105 StatusquoanddevelopmentofwindenergyutilisationinGermanyinlightofinternationaltrends

2009

43 VW09148 MEF‐InformationaboutthepositiveeffectsofwindenergyutilisationinGermanyontheeconomy

2009

44 VW09149 Investigationinto(international)windenergyclusters 2009

45 VW09150 StudyregardingthedevelopmentofwindenergyutilisationinGermanyuntiltheyear2015

2009

46 VW10165 ConsultingservicesfortheVietnameseGovernment:Imple‐mentationofaFeed‐inTariffforWindEnergy

2010

47 VW09143 PreparationandmonitoringoftheExperienceReport2011regardingtheRenewableEnergyLaw(EEG)accordingto§65

EEG‐ActII;PartWindenergy

2011

48 VW09146 PreparationandmonitoringoftheExperienceReport2011regardingtheRenewableEnergyLaw(EEG)accordingto§65

EEG‐ActII,Partgridintegration

2011

49 VW11102 Analysisofdeconstructioncostsfortwowindturbinesof6.5MW‐class

2011

50 VW11111 EstimationofcapabilityoftheharbourofBrakeconcerningoffshorewindenergydevelopment

2011

51 VW11062 Capability‐AnalysisconcerningRepoweringofWindTurbines 2011

52 VW11087 AdviceandscientificsupportfortheTechnologyCooperationinwindenergyintheframeoftheCleanEnergyMinisterial

(CEM)

2011‐2014

53 VW09105 EconomicofWindEnergyuse.Analysisofbasicinfluencingfactors

2012

54 VW11075 ImpactofthegovernmentdraftoftheRenewableEnergyLaw(EEG2012)ononshorewindenergy

2012

55 VW11104 EstimationofthepossiblecapacitycapabilityoftheOffshoreTerminalBremerhaven

2012

56 VW11053 Opportunitiesandchallengesforharbourandshipyardindus‐tryconcerningoffshorewindenergydevelopment

2012

Page 78: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 78/89

No. ProjectNo.

Subject Year

ofAssessment

57 VW10185 ScientificevaluationandmonitoringofRepowering‐Projectsforalocalcommunity

2012

58 VW12021 RisksofoffshoregridsintheGermanNorth‐Sea 2012

59 VW12049 StateofwindenergydevelopmentinGermany 2012

60 VW12079 EnergyYieldAssessmentandeconomicofawindenergypro‐ject

2012

61 VW12033 Developmentofaconversationstrategyforgeneratingplants 2012

62 VW12010 Assessmentofcontractsandcomparisonwiththerequire‐mentsforthetechnicaloperationofwindturbines

2012

63 VT121258 Developmentofnewmeasurementstrategieswithenhancedqualitystandardinthefieldofmeteorologicalmeasurements

forsiteassessment

2012‐2013

64 VE12006 TagLineForcesduringSingleBladeInstallation 2012

65 VE12007 Acoustic‐aerodynamicoptimizationofrotorbladesonwindturbines

2012‐2014

66 VC12387 Transfer‐Wind‐LiDAR:Developmentofinnovativecalibrationforwindspeedtelemetrysystemsforwindpotentialandpow‐

ercurvedetermination

2013‐2015

67 VW12035 OffshoreTestSite‐Research 2013

68 VC12439 StudyonthevariationofwindpotentialinGermany 2013

69 VW12039 OffshoreElectricityGridImplementationintheNorthSea 2013‐2015

70 VW12070 Studyoncostsituationofonshorewindenergy 2012

71 VW13101 Marketanalysiswithrespecttovariousbusinessoptionsandpotentialfortransportterminals

2013

72 VW13114 EvaluationoftheresearchfundingoftheBMUinthecontextofthe5thEnergyResearchProgram

2013

73 VW13145 Sitesophisticatedmodelofreimbursementforwindenergy 2013

74 VW13151 Studyonthereformofthereferenceenergy‐yieldmodelofonshorewindenergyuseinthecontextofRenewableEnergy

LAW(EEG)

2013

75 VW13153 Studyoncostsituationofonshorewindenergy‐Internationalcomparison

2013

76 VW13130

VW14192VW14193

StatusquoanddevelopmentofwindenergyutilisationinGermany‐asemi‐annuallyreport

2013‐2018

77 VW13195 Developmentofaconversationstrategyforgeneratingplants‐Typelist

2014

Page 79: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 79/89

No. ProjectNo.

Subject Year

ofAssessment

78 VW14101 AnalysisofcostsensitivitiesandconsultingduringEEGamendment2014

2014

79 VW14102 Analysisofcostreductionpotentialforonshorewindenergy 2014

80 VW14103 AnalysisofpossibilitiesformanipulationofasinglestepFIT 2014

81 VW14119 Realisationscheduleforanaccelerationofdevelopmentandgridconnectionofoffshorewindparks

2014‐2015

82 VW14121 Analysisofpotentialpriorityareasconsideringdistancestoresidentialbuildings

2014

83 VW14152 CostsituationoflandbasedwindenergyinIsrael–Acompar‐ativeanalysis

2014

84 VW14157 Briefassessmentonwindturbinesgeneratorswithperma‐nent‐magnet

2014

85 VW14161 UpdateonremotecontrollabilityintheEEG2014forturbinemanufacturer

2014

86 VW14163 Proveofsitequalityasinthereferenceyieldmodelforwindturbine

2014

87 VW14194

VW14200

AnalysisoftypicalwindenergyprojectsizeinGermany 2014

88 VW14199 Assessmentofstakeholderstructuresofwindenergydevelop‐ersandoperatorsinGermany

2014‐2015

89 VW14207 Projectionofrevenuegenerationofwindturbinegeneratorsinstalledin2006/07

2014

90 VW14212 AnalysisofcharacteristicsofrepoweringwindturbinesinGermany

2014

91 VW14216 AssessmentonmarketentrypossibilitiesforKoreanwindenergycompanies

2014‐2015

92 VW14160 Feasibilitystudyonthesustainableenergysupply(wind)ofalargecompany

2015

93 VW09105

VW14178

ParticipationintheIEAwindtask26"Costofwindenergy" 2009‐2015

94 VW15110 Studyoncostsituationofonshorewindenergy‐Update 2015

95 VW15124 Consultationduringprogressofrenewableenergyactamendment

2015‐2016

96 VW15134 Economicassessmentofwindfarmsconsideringdifferenthubheights

2015

97 VW15136 Reviewofthecalculationofthedurationoftheinitialreim‐bursementaccordingtoEEG2014

2015

98 VW15161 Analysisonremunerationforoldwindturbines 2015

Page 80: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 80/89

No. ProjectNo.

Subject Year

ofAssessment

99 VW15165 Briefassessmentonwindturbinesforlowwindspeeds 2015

100 VW15170 Briefanalysisononshoregridconnection 2015

101 VW15203 PlausibilitycheckoftheeconomicevaluationoftheabolitionofBorWin4

2015‐2016

102 VW15209 CreationofservicespecificationsforAcceleratednetworkexpansionforoffshoreconnectionlines

2015

103 VW15217 Suggestionforfurtherdevelopmentofthereferenceyieldmodel

2015

104 VW15252 SupportofinthedraftingofanopiniononkeyissuespaperoftheBMWi

2015

105 VW15289 WindenergymarketanalysisEU/USA 2015

106 VW15294 ConsultationonthepossibleremunerationofawindturbineaccordingBMWIKeyIssuesPaper

2015

107 VW15203 PlausibilitycheckoftheeconomicevaluationoftheabolitionofBorWin4

2015‐2016

108 VW13205 GEOWISOL‐Effectofthegeographicaldistributionandtem‐poralcorrelationofwindandsolarfeedonthepowersupply

2015‐2017

109 VW16191 ParticipationintheinternationalworkinggroupofIEAWindTask26"CostofWindEnergy"‐PeriodThree:2015‐2018

2015‐2018

110 VW15197 Assesmentforimplementationinitiativeofcostreductionpotentialsinoffshorewindenergy(UKOW)

2015‐2018

111 VW15106 IntegratedBalticOffshoreWindElectricityGridDevelopment(BalticInteGrid)

2016‐2019

112 VW16100 ExpertassessmentoftheBMWibenchmarkpaperontheRe‐newableEnergyActamendment2016

2016

113 VW16107 AssessmentonsitequalityofwindturbinesinGermany 2016

114 VW16158 Possiblecurtailmentofoffshorewindfarmsduetogridcapac‐itylimitation

2016

115 VW16196 Studyonthecontinuingoperationofland‐basedwindtur‐binesafter2020(expiryofremunerationperiod)

2016

116 VW16203 MarketpotentialanalysisEuropeforwindturbinemanufac‐turer

2016

117 VW16281 ShortassessmentondifferencesinrevenueaccordingtoEEG2012andEEG2014forspecificwindfarm

2016

118 VW16165 Preparationandmonitoringofanexperiencereportinac‐cordancewith§97RenewableEnergySourcesAct(EEG2014)

‐ProjectIIeLand‐basedwindenergy

2016‐2019

119 VW15151 PROMOTioN‐ProgressonMeshedHVDCOffshoreTransmis‐sionNetworks

2016‐2019

Page 81: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 81/89

8.2 ListofFeasibilityStudiesforWindEnergyProjects

No. ProjectNo.

Country Subject Year Client

1 P01102 Mali

FeasibilitystudyforautonomouspowersupplyofatowninMaliwithawind‐Dieselsystem,windmeasurements,siteassessment,gridanalysis,technicalconcept

forwindturbine

2001 GTZ

2 P01104 ColombiaConsultationofautilityconcern‐ingplanningandinstallationofa20MWwindfarmatlaGuajira

2001 GTZ

3 P01105 Tunisia

ConsultationoftheTunisiangovernmentinestablishinga

WindEnergyDepartmentintheDepartmentofEnergyandtheverificationofwindfarmsites

2001 GTZ

4 P01112 Tunisia Evaluationofa75MWwindfarmprojectwithinTunisia

2001 GTZ

5 P01115 Yemen

Verificationofawindfarmpro‐jectinYemenduringitsplanninganddesignphaseaswellasanassessmentoftheaccessibilityto

themaingrid

2001 GTZ

6 P01127 ColombiaAssistanceinProjectDevelop‐

ment 2001 GTZ

7 VC02172 ChinaSiteinspectionandConceptforWindresourceandwindfarm

planningatDaheishan2002

GermanCom‐pany

8 VW03120 SenegalFeasibilitystudyforthelocalGovernmentfora50MWwind

energyproject2003 GTZ

9 VW04100 Indonesia

DeterminationofpotentialwindfarmsitesinIndonesia,feasibil‐itystudiesfor12potentialsites

districtTTS

2004 PEMDATTS

10 VW04103 Indonesia

DeterminationofpotentialwindfarmsitesinIndonesia,feasibil‐itystudiesfor12potentialsites

districtRoteN’dao

2004 PEMDARoteN’dao

11 VW04104 Indonesia

DeterminationofpotentialwindfarmsitesinIndonesia,feasibil‐itystudiesfor12potentialsites,

districtofKupang

2004 Kupang

Page 82: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 82/89

No.ProjectNo.

Country Subject Year Client

12 VW04105 Tunisia Windmeasurementsystems 2004 GTZ

13 VW04106 Tunisia GTZ‐Tunisia 2004 GTZ

14 VW04107 Algeria GTZ‐Algeria 2004 GTZ

15 VW04120 VenezuelaFeasibilitystudyforthelocalGovernmentfora15‐20MW

windfarmproject2004 GTZ

16 VW04126 AlgeriaGTZ‐AlgeriawindfarmTim‐

mimoun 2004 GTZ

17 VW05137 Chile Windfarmimplementation 2005GermanCom‐

pany

18 VW05141 ChileAppraisalofwindmeasurements,

Chile 2005 GTZ‐Chile

19 VW05150 Senegal CapacityBuilding(TERNA‐Program)

2005 GTZ

20 VW09147 SenegalFeasibilityStudyforPotouwind

farm2010 GTZ

Page 83: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 83/89

8.3 ListofWindTurbinesManagedbyDeutscheWindGuard(TechnicalManagement)

No. ProjectNo.

Country TypeofTurbine No.ofTur‐bines

StartofContract

Client

1 WP002 Germany ANBONUS1.3MW/62 6 2001 Germanoperator

2 WP004 Germany ENERCONE‐66/18.70 11 2001/

2002

Germanoperator

3 WP006 Germany VESTASV802.0MW 5 2003 Germanoperator

4 WP008 Germany VESTASV80 4 2004 Germanoperator

5 WP010 Germany VESTASV802.0MW 9 2004 Germanoperator

6 WP011 Germany GamesaEólicaG80 3 2005 Internationaloperator

7 WP012 Germany GamesaEólicaG80 5 2005 Internationaloperator

8 WP013 Germany GamesaEólicaG80 7 2005 Internationaloperator

9 WP014 Germany GamesaEólicaG80 5 2006 Internationaloperator

10 WP015 Germany ENERCONE‐70/E4 2 2005 Germanoperator

11 WP016 Germany NORDEXN62 19 2006 Germanoperator

12 WP017 Germany Siemens2.3MW 1 2006 Germanoperator

13 WP018 Germany ENERCONE‐70/65m 2 2006 Germanoperator

14 WP019 Germany GamesaEólicaG80 2 2006 Internationaloperator

15 WP020 Germany ENERCONE‐82/108,3m 1 2006 Germanoperator

16 WP021 Germany ENERCONE‐40/6.44 4 2007 Germanoperator

17 WP022 Germany ENERCONE‐126/116m 1 2008 Germanoperator

18 WP022 Germany Repower5M/129m 1 2007 Germanoperator

19 WP023 Germany VESTASV661,75MW 9 2007 Germanoperator

20 WP024 Germany ENERCONE‐66/18.70 3 2008 Germanoperator

21 WP025 Germany VESTASV80/2MW 5 2008 Germanoperator

22 WP026 Germany VESTASV80/2MW 10 2008 Germanoperator

23 WP027 Germany VESTASV80/2MW 4 2008 Germanoperator

24 WP028 Germany VESTASV420,6MW 1 2008 Germanoperator

Page 84: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 84/89

No. ProjectNo.

Country TypeofTurbine No.ofTur‐bines

StartofContract

Client

25 WP031 Germany NordexN90 8 2009 Germanoperator

26 WP032 Germany EnerconE‐82 1 2010 Germanoperator

27 WP033 Germany MultibridM5000 2 2010 Germanoperator

28 WP034 Germany EnerconE‐82 4 2010 Germanoperator

29 WP035 Germany MultibridM5000 2 2010 Germanoperator

30 WP036 Germany EnerconE‐82 5 2011 Germanoperator

31 WP037 Germany Repower5M/117m 1 2011 Germanoperator

32 WP038 Germany EnerconE‐82/108m 2 2011 Germanoperator

33 WP039 Germany Repower3.4M/128m 1 2012 Germanoperator

34 WP040 Germany GE1.5sl/61,5m/ANBonus2MW/80m/GE1.5s

15 2012 Germanoperator

35 WP041 Germany Repower3.4M/128m 5 2013 Germanoperator

36 WP042 Germany PowerwindPW90/98m 1 2012 Germanoperator

37 WP043 Germany VestasV126 2 2014 Germanoperator

38 WP044 Germany MultibridM5000 1 2014 Germanoperator

39 WP046 Germany Senvion3.4M/128m 1 2014 Germanoperator

40 WP047 Germany Senvion6.2M+NH124m/EnerconE‐115NH135m

2 2014 Germanoperator

41 WP048 Germany Senvion3.2M/114NH143m

2 2015 Germanoperator

42 WP049 Germany EnerconE82NH108m 2 2015 Germanoperator

43 WP050 Germany FLMD77NH111m/VestasV90NH105m/EnerconE‐

48NH76m

9 2015 Germanoperator

44 WP052 Germany VestasV126NH137m 12 2016 Germanoperator

45 WP053 Germany VestasV112 8 2016 Germanoperator

46 WP054 Germany EnerconE115 6 2016 Germanoperator

Total 212

Page 85: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 85/89

8.4 ListofScientificTrainingCourses

Year ProjectNo.

Subject No.ofdelegates

Country

2001 P01104 TraininginProjectDevelopment,EEPPMM 2 Colombia

2001 P01112 TrainingWindMeasurements 15 Tunisia

2002 P00001 WPD‐Seminar:"Windfarmprojects‐Financingandecon‐omy"

40 Germany

2002 P02101 Workshop:"Toconfigurewindfarmprojectssafety" 32 Germany

2002 P01149 SeminarNord‐LB:"Financingandrisksofwindfarmpro‐jects"

30 Germany

2002 P00003 BWEseminar:windturbinepowercurves 50 Germany

2002 P00001 SeminarCommerzbank:"Financingofwindfarmprojects" 25 Germany

2002 P00001 SeminarCollegeWHV:"WindFarmDevelopment" 50 Germany

2003 VC02231 in‐houseseminar:measurecorrelatepredictmethodsforwindresourceassessments

10 Germany

2003 VC03106 in‐houseseminar:flowmodellingforwindresourceas‐sessments

4 Germany

2003 VC03191 in‐houseseminar:windturbinepurchaseandmainte‐nancecontracts

10 Germany

2003 VD03012 Advancedtrainingcourseover3months:"GridConnectedWindTurbines",Part1,intheframeworkof"Post‐GraduateTrainingCourse"ofInWEnt,Deutschland&

NorthwesternPolytechnicUniversity(NPU),Xian,China

30 Germany

2003 VD03023 Advancedtrainingcourseover3months:"GridConnectedWindTurbines",Part2,intheframeworkof"Post‐

GraduateTrainingCourse"

16 Germany

2003 VD03018 In‐houseseminar"Crashcoursewindenergy"foremploy‐eesofabank

25 Germany

2003 VD03005 In‐houseseminar"Crashcoursewindenergy"foremploy‐eesofamanufacturer

20 Germany

2003 P00001 WPD‐Seminar:"Windfarmprojects‐Financingandecon‐omy"

35 Germany

2004 VC04014 SeminarNord‐LB:"Financingandrisksofwindfarmpro‐jects"

33 Germany

2004 VC02126 SeminarNord‐LB:"Financingandrisksofwindfarmpro‐jects"

30 Germany

2004 VC04126 SeminarBremerLB:"Financingandrisksofwindfarmprojects"

30 Germany

2004 VC04143 in‐house:postconstructionwindfarmyieldprediction 10 Germany

Page 86: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 86/89

Year ProjectNo.

Subject No.ofdelegates

Country

2004 VD03148 Advancedtrainingcourseover3months:"GridConnectedWindTurbines",intheframeworkof"Post‐Graduate

TrainingCourse"ofInWEntincooperationwiththeISET‐instituteKassel

18 Germany

2004 VD04023 Advancedtrainingcourseover3months:"GridConnectedWindTurbines",intheframeworkof"Post‐Graduate

TrainingCourse"ofInWEnt,Deutschland&NorthwesternPolytechnicUniversity(NPU),Xian,China

16 Germany

2004 VC04013 in‐houseseminar:"Crash‐CourseWindEnergy"forem‐ployeesofamanufacturer

20 Germany

2004 VD04025 in‐houseseminar:"Crash‐CourseWindEnergy"forem‐ployeesofamanufacturer

20 Germany

2005 VD04086 Courseforadvancesover6months:"Windturbinesforperipheralenergysupplyandgrid‐connectedwindfarms"inframeworkof"Post‐GraduateTrainingCourse"ofInWEntincooperationwiththeISET‐instituteKassel

22 Germany

2005 VD05087 Seminarovertwoweeks:"WindPowerTechnology"inframeworkoftheAsia‐Pacific‐Weeks,organisedbyIn‐WEntandGTZ,Deutschland&NorthwesternPolytechnic

University(NPU),Xian,China

15 Germany

2005 VD05066 In‐houseseminarover4days:"Technicalmanagementofwindfarms"foremployeesofapowerauthority

12 Germany

2005 VD05056 Courseover3days:"Grid‐IntegrationofWindEnergy"incooperationwithamanufacturerfortheTaiwanPowerResearchInstituteandtheTaiwanPowerCompany

3 Taiwan

2005 VD05110 Courseover3days:"Basicsofwindenergyandmainte‐nanceofwindturbines"forprofessionalclamberersfor

industrypurposes

13 Germany

2005 P00001 12days‐Seminarforemployeesofpowerauthoritiescon‐cerninggridintegrationofwindenergy

30 FijiIslands

2006 VC06152 in‐houseseminar:postconstructionwindfarmyieldpre‐diction

50 Germany

2006 VC06220 in‐houseseminar:utilityscalewindpowerplants 40 Canada

2006 VC06248 TrainingPowerPerformance 5 Germany

2006 P00001 5daysIn‐housetrainingcourse:"Introductiononwindenergy,WindPro‐SoftwareandwaspmodelsforIndone‐

sianengineers"

5 Germany

2007 VC06248 two‐weeks‐trainingcourse:traininginpowerperfor‐mancemeasurementsforChineseengineers

2 Germany

2008 VC08028 Training‐Course‐CLYPG_DEKON 5 China

2008 VW08130 Workshop"WindEnergy"inTurkey 5 Turkey

2008 P00001 2‐days‐trainingforemployeesofDeutscheWindGuard 50 Germany

2008 VC08086 bankersin‐houseseminar:O&Mcostofwindfarms 35 Germany

Page 87: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 87/89

Year ProjectNo.

Subject No.ofdelegates

Country

2008 VC08105 TrainingCourseSuzlon‐Energy 35 China

2008 VC08106 Training‐CourseGTZ 8 China

2008 VC08201 GTZ‐Workshop"Advancementofrenewableenergiesandenergyefficiency"

3 Tunisia

2009 VW09104 TrainingcourseGTZforengineersofSouthAfrica 20 SouthAfrica

2009 VC09009 TrainingCourse"WindEnergy"inStettin 25 Poland

2009 VC09069 bankersin‐houseseminar:energyyieldpredictions 20 Germany

2009 P00003 BWEseminar:duediligence 35 Germany

2010 P00001 TrainingwithemployeesofaWT‐manufacturerconcern‐inganemometer

5 Germany

2010 P00001 TrainingwithemployeesofaWT‐manufacturerconcern‐inganemometerperformanceonice

5 Germany

2010 VK09012 5‐days‐training:"Technicalmanagement,maintenanceandmonitoringofWT"forChineseengineers

42 China

2011 P00003 BWEseminar:DueDiligence 30 Germany

2011 P00003 BWEseminar:DueDiligence 40 Germany

2011 P00001 TrainingwithemployeesofWT‐manufacturerconcerninganemometercalibration

10 Denmark

2011 P00001 TrainingwithemployeesofWT‐manufacturerconcerninganemometercalibration

9 Denmark

2011 VC11224 1‐day‐Seminar"Problemsofinvestigationandoperationofwindfarms"foremployeesofmunicipalutilities

25 Germany

2011 P00001 1‐day‐Seminaraboutwindenergyingeneral 20 Germany

2012 P00001 Trainingforemployeesofaanemometermanufacturer 4 Germany

2012 P00001 Trainingforemployeesofaanemometermanufacturer 5 Germany

2012 P00001 TrainingforemployeesofaWT‐manufacturerconcerninganemometercalibration

4 Germany

2012 P00001 Trainingforemployeesofawindfarmdeveloperconcern‐inganemometercalibration

4 Germany

2012 P00001 Workshop:FurthereducationandsecuritytrainingforOffshore‐staff

40 Germany

2012 P00001 PresentationofWindTunnelinBremerhavenformem‐bersofGermanFederalMinistryfortheEnvironment,

NatureConservationandNuclearSafety

12 Germany

2012 P00001 BWE‐Seminar:Onshorewindenergy:Financinganddirectmarketing

100 Germany

2012 P00001 Reliabilityanddamageanalysisofwindturbines 50 Germany

Page 88: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 88/89

Year ProjectNo.

Subject No.ofdelegates

Country

2012 VW11087 SeminaratGermanFederalMinistryfortheEnvironment,NatureConservationandNuclearSafety

4 Germany

2012 VC12104 1‐day‐Seminarforbanksandinvestorsconcerningtechnicalrisksonbackgroundoffinancing

windenergyprojects

48 Germany

2013 VW11091 3‐dayin‐houseseminar:windfarmplanningandoperation

20 Ukraine

2013 VC13052 in‐houseseminar:uncertaintiesofwindresourceassessments

5 Turkey

2013 P00003 in‐houseseminar:evaluationofrotorbladeicinglosses 10 Belgium

2013 P00001 in‐houseseminar:classificationofanemometers 6 Germany

2013 VC13041 BWE‐Seminar:Wind‐Measurements,EnergyYieldandEconomics

90 Germany

2014 VC14354 InternationalVDMI‐Workshop:WindResourceAssess‐ment

40 Germany

2014 VC14355 InternationalVDMI‐Workshop:WindResourceAssess‐ment

35 Germany

2014 P00001 ICCI‐Seminar:CurrentChallengesandStandardsinWindFarmSiteAssessment

50 Turkey

2014 P00001 BWE‐Seminar:OnshoreWindEnergy:Wind‐Measurements,Energy‐YieldandEconomics

60 Germany

2015 P00001 IWESSeminar:VerificationofWindRemoteSensingDe‐vices

60 Germany

2015 P00001 HDT‐ForwindSeminar:OnshoreWindEnergy:LiDARWindMeasurements

20 Germany

2015 P00001 VestasWorkshop:LiDARandSODARWindMeasurements 30 Germany

2015 VC13041 BWE‐Seminar:WindMeasurements,EnergyYieldandEconomics

60 Germany

2015 VC15261 in‐housetrainingforawindturbinemanufacturer:uncer‐taintiesofpowercurvetests

6 Spain

2016 VC13041 in‐houseseminaratabankorganisedbyBWE:WindMeasurements,EnergyYieldandEconomics

20 Germany

2016 VC13041 BWE‐Seminar:WindMeasurements,EnergyYieldandEconomics

30 Germany

2016 P00001 1‐day‐SeminarforbanksonimpactifthenewGermanRenewableEnergyActonfinancing,investmentandoper‐

ationofwindfarms

30 Germany

2016 P00001 SeminarfordelegationfromMexicoorganisedinframeofexportinitiativeofGermanMinistryofEconomicAffairsonfeasibilitystudies,windresourcemeasurementsand

windturbinepowercurvetesting

30 Germany

Page 89: ReferenceList DWG 2016-12 V04 final - WindGuard...ReferenceList_DWG_2016‐12_V04_final 2 / 89 Contents 1 Deutsche WindGuard Group – An Overview 4 1.1 Company Structure 6 1.2 Key

ReferenceListofDeutscheWindGuard

ReferenceList_DWG_2016‐12_V04_final 89/89

Year ProjectNo.

Subject No.ofdelegates

Country

2016 P00001 3‐dayseminarforChinesewindturbinesupplieronvari‐ousaspectsofwindengineering

15 Germany

2016 VC13041 BWE‐Seminar:WindResourceAssessments,RevenueAssessments

25 Germany

2016 P00001 IWESSeminar:ApplicationofLiDARsforWindResourceAssessments

25 Germany

Total 2133