REDCAR BLAST FURNACE: KEY CONSIDERATIONS ......Blast Furnace A Green Book Analysis based on figures from the STDC Business Case shows that the 20-acre Blast Furnace site, if developed
Upload
others
View
11
Download
0
Embed Size (px)
344 x 292
429 x 357
514 x 422
599 x 487
Citation preview
Summary of technical, financial and economic considerations
around
the retention of the Redcar Blast Furnace
Prepared for the Teesworks Heritage Taskforce
by the Tees Valley Combined Authority
Introduction This briefing sets out the most pertinent points from
the financial and economic cases for the retention and demolition
of the Redcar Blast Furnace. It was created to aid the
understanding of the Teesworks Heritage Taskforce in its
consideration of the heritage assets on the Teesworks site,
alongside consultation and expert opinion.
Extremely dangerous condition
At present, the Blast Furnace complex is in an extremely dangerous
condition wholly unsuitable for safe public access. The current
condition of the furnace complex poses a risk for trained and
competent structural inspectors and it is proving ever more
challenging for them to inspect the structures for defects and to
monitor known defects within the structures. The overall stability
of the Blast Furnace complex will only worsen without intervention.
Steps that would enable the blast furnace to be developed so that
visitors can be admitted are outlined in the South Tees Development
Corporation (STDC) Redcar Blast Furnace Visitors Centre Suitability
Study.
£35,230,000 to preserve the blast furnace for ten years
The cost of retaining the Blast Furnace plus building and operating
a visitor centre for ten years is estimated to be £35,230,000. This
is based on fixed costs of £25,410,000 and £982,000 annual running
costs. These figures are based on the STDC Redcar Blast Furnace
Visitors Centre Suitability Study and indicative costs provided by
STDC.
827 jobs could be lost by retaining the blast furnace
The Business Case for the Regeneration of the STDC Site (2020), as
submitted to Government, shows that the blast furnace site of 20
acres has the potential to sustain 516 direct jobs and as many as
827 when indirect and induced effects in the wider economy (supply
chain etc) are considered.
2
Six jobs could be created from a visitor centre
The STDC Redcar Blast Furnace Visitors Centre Suitability Study
bases its assumptions on six jobs being created in the visitor
centre. This could be considered a conservative estimate. This is
821 fewer jobs than STDC plans to create on the Blast Furnace
site.
£161.4 million boost without the Blast Furnace
A Green Book Analysis based on figures from the STDC Business Case
shows that the 20-acre Blast Furnace site, if developed as planned,
would add £161.4 million to the Tees Valley’s economy over ten
years.
Lost Investment Opportunity
Expenditure on retaining the Blast Furnace and associated heritage
support will not deliver sufficient financial return to allow
reinvestment in other Teesworks job creation. The capital
investment in retaining the blast furnace would reduce the overall
investment pot secured from Government to circa £100m, meaning that
only 80% of the impact would be realised over the original
programme period.
Appendices 1. South Tees Development Corporation (STDC) Redcar
Blast Furnace Visitors Centre Suitability Study
2. Outline economic appraisal of the possible retention of the
Redcar Blast Furnace as a visitor attraction
3. Indicative costs excluded from the Redcar Blast Furnace Visitor
Centre Sustainability Study (2020) – Provided by the South Tees
Development Corporation
4. Confidential: Full Business Case for South Tees Development
Corporation: Site Regeneration
1
REDCAR BLAST FURNACE: OUTLINE ECONOMIC APPRAISAL
Outline economic appraisal of the possible retention of the Redcar
Blast Furnace as a visitor attraction - Prepared for the Teesworks
Heritage Taskforce by the Tees Valley Combined Authority
Scope of this document
This document facilitates the comparison of actual and opportunity
costs related to the Retention of the Blast Furnace.
This document is based on the findings of the following independent
studies:
• STDC Masterplan (2019); • Business Case for the Regeneration of
the STDC site (2020); and • Redcar Blast Furnace Visitor Centre
Sustainability Study (2020)
These documents are supplemented by indicatives costs for
exclusions noted in the Redcar Blast Furnace Visitor Centre
Sustainability Study, provided by the South Tees Development
Corporation.
Assumptions:
The Masterplan clearly articulated a heritage offering at the Blast
Furnace Site and allotted 20 acres to address an unspecified
function and demand.
The Redcar Blast Furnace Study reviewed the suitability of the
Blast Furnace site for a Visitor Centre and the following aspects
were noted:
• Retention Capital Costs: £20.8m (this assumes that the entire 20
acre site is utilised);
• Construction of a Visitor Centre: £2.6m (800 sq m visitor
centre); • Ongoing costs £0.9m per annum.
The following impacts are noted:
• Retention Only: Gross Direct Cost: £20.8m: NPC: £15.45m (assuming
25% local sourcing of labour and materials (circa £4m incurred in
year 1) and secondly the proceeds of scrap metal from redundant
parts of the Blast Furnace (circa £1.35m)).
• Retention plus provision, maintenance and operation of a Visitor
Centre (No Revenue Stream) (10 year Economic Life): Gross Direct
Cost: £32m :
2
NPC: £23.85m (assuming 25% local sourcing of labour and materials
(circa £4m incurred in year 1) and secondly the proceeds of scrap
metal from redundant parts of the Blast Furnace (circa
£1.35m)).
• Retention plus provision of a Visitor Centre and assumption of
40,000 visitors by year 4 with average spend per visit £6.50: Gross
Direct Cost: £32m : NPC: £22.15m. Assumptions based on Darlington
Railway Museum as the most directly comparable proposition.
Even under the most optimistic projection for an onsite Heritage
Centre (and assuming only negligible displacement with existing
provision, such as Kirkleatham Museum), a relatively high number of
visitors and no other land costs: this option creates a net present
cost over the economic life of the project of: £22.15m (2020
prices)).
The STDC Regeneration Study did not specifically discuss the direct
costs related to the demolition of the Blast Furnace. Rather, it
considered that all redundant assets would eventually be
demolished, with the economic surplus being invested in subsequent
phases of demolition and redevelopment. The Blast Furnace site is
within the North Zone, adjacent to the Net Zero Teesside Project
and part of the 100 acres ascribed to clean technology related
advanced manufacturing.
The STDC Regeneration Business Case confirms that if fully
developed it will have the following outputs: 121,406 sq m of
specialist business accommodation and 2,583 advanced manufacturing
jobs, once fully operational. The report goes on to identify a
wider (and very prudent) multiplier effect of 0.6, meaning that
total direct, indirect and induced jobs could equate to: 4,133 or
£200m of additional GVA per annum (prudently using regional average
GVA per head) once fully operational.
To put this into perspective: Land Parcel R1a, which contains the
Blast Furnace (100 acres), accounts for circa 15% of the total site
set aside for the development of the clean technology advanced
manufacturing cluster, the development of which has two interlinked
criteria: pipeline of accessible land and creation of co-located
integrated supply chain (minimising logistics and maximising
circular economy solutions).
As well as the identified direct costs of retaining the Blast
Furnace and provision of a visitor centre, there are also a number
of other opportunity cost scenarios which need to be
considered:
• Opportunity cost of using 20% of the land: Pro rated, retention
of the blast furnace could reduce direct and indirect employment by
516 and 827 respectively, or a reduction in anticipated GVA per
annum of £24.4m (on full occupancy in year 10 in 2020 prices and
including scrappage value of £5.4m);
3
• Opportunity cost to investment on adjacent advanced manufacturing
site: Vivid Economics employment land assumptions were based on
sizeable land parcels (this is the third largest such parcel of
land ascribed for productive purposes). Reducing the land envelope
diminishes flexibility of use and consequently demand. At the very
least, this could mean a delay in uptake rate (10%), with a prudent
assumption being that the site would be fully occupied by year 11
instead of year 10. An underperformance of 10% over the course of
the development plan (potentially circa £88m of lost output over 10
years); and
• Opportunity cost of loss of recyclable investment fund to entire
STDC site: As noted above the STDC regeneration model was
predicated on using £124.7m of public sector funds to kick start
the development of the Teesworks site. In the early stages,
investment would be into those activities which were commercially
viable and would therefore produce a return on capital which could
be subsequently used for reinvestment (ultimately paying for the
demolition of the Blast Furnace). Expenditure on retaining the
Blast Furnace and associated heritage support has been demonstrated
not to deliver the necessary financial or economic return (the most
optimistic being a net cost of £23.5m after 10 years of operation).
A capital investment in the Blast Furnace of £23.4m would,
therefore, reduce the overall investment pot down to circa £100m,
meaning that only 80% of the impact would be realised over the
original programme period.
Note on methodology
In order to facilitate comparison between options, common costs
(capital and operational) and benefits (GVA per job, visitor
numbers and spend and scrappage) were identified and applied. A
consistent programme period was also applied, based upon the
standard economic life of a visitor centre and costs and benefits
were discounted over that period using the Green Book approved 3.5%
discount rate. This led to easily comparable NPC/NPV estimates for
all options with attributable costs and benefits. A number of
scenarios (opportunity costs) were also developed, but kept
separate from the cost benefit analysis, as the magnitude of
potential scale of impact would obscure vital messaging between
options.
Conclusion
In summary, the Blast Furnace site of 20 acres has the potential to
sustain 516 direct jobs or 827 (direct, indirect and induced) jobs
in the wider economy, equating to a Net Present Value of £161.4m.
Retention of the Blast Furnace and investing in a Heritage Centre
would equate to a Net Present Cost of (£22.15m) over a similar 10
year period. In addition, there may be further opportunity costs to
the wider Teesworks investment plan by spending in less productive
activity, thereby reducing the overall investment pot by 20% with
the possibility that only 80% of the impact would be realised over
the original programme period.
4
Possible Next Steps
The Teesworks Task Force may wish to request a Business Case to
consider different Heritage-based offerings. The Steel Heritage
Business Case would utilise the findings of the Taskforce to
provide a detailed Option Appraisal for pans outlined in its final
report.
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 1/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
VISITORS CENTRE SUITABILITY STUDY
01 Monetary notation changed 07/10/20 xxxxxxx xxxxxxx
Rev. Modification contents Date Made by Approved by Mandator
I&S BF Contract No
Project E.ZX0M Date Name Made by 30/09/20 xxxxxxxx Plant Blast
Furnace Checked by 01/10/20 xxxxxxx Approved by 01/10/20 xxxxxxxx
Area General CM Eng. Secl. Equipment Lang. EN Size Sheet No. Sheets
Material SubGroup Mass Unit Scale1 Scale2 SupplyGrp SAP Document
No. Consortial Partner Partno Consortial Partner No. Sub DocType
Technical Specification Sub No. Corresponding Doc. CountNo Customer
No. Doc Title Visitors Centre Suitability Study Substitute for
Replaced by
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 2/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
.
© Primetals Technologies Limited All rights reserved. This document
contains valuable trade secrets and confidential information of
Primetals Technologies Limited and the content of this document is
and shall remain our intellectual property. You shall keep this
document and all its content strictly confidential, not disclose it
or any part thereof to any third party without our express written
consent and not use any information, specification or data
contained in this document for other purposes than for the
evaluation of our document. No part of this document may be
adapted, copied, reproduced, duplicated, translated into another
language, distributed or processed (print, photocopy, microfilm or
any other process), either by the use of electronic systems nor
otherwise without the prior express written permission of Primetals
Technologies Limited You shall limit access to our document and to
any part thereof to those of your employees reasonably required
being aware thereof and you shall ensure their strict adherence to
the provisions of confidentiality and restriction of use as
expressed above. Any violation of the above provisions will be
brought before the competent court in accordance with the
applicable law. The Information contained in this document is
subject to change. Notice of changes will be made only to the
parties deemed relevant by Primetals Technologies Limited.
Primetals Technologies Limited assumes no responsibility or
liability for any errors or omissions that may appear in this
document or for incidental or consequential damages
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 3/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Revision History
Rev Description Made by Date Checked by Date 00 First Issue xx
30/09/20 xx 01/10/20
01 Monetary notation changed xx 07/10/20 xx 07/10/20
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 4/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Table of Contents
1 INTRODUCTION 5 2 SCOPE OF WORK 5 3 BLAST FURNACE LAYOUT &
TERMINOLOGY 5 4 BLAST FURNACE – CONDITION ASSESSMENT 6 5 CORRECTIVE
AND STABILISATION WORKS – COST BASIS 17 6 PROPOSED VISITOR CENTRE
20
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 5/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
1 Introduction
The purpose of this report is to assess the current condition of
the Blast furnace proper structure to enable a determination to be
made into the suitability for a visitors’ centre to be
established.
2 Scope Of Work
x Review of the current status of the blast furnace proper
structure only, to allow safe access for visitors.
x Approximate cost to upgrade / modify the existing structure to
allow safe access for visitors.
x Identification of a suitable location for a viewing platform
together with approximate costs.
3 Blast Furnace Layout & Terminology
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 6/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Overview
Based on an visual inspection made on the 16th September 2020
utilising the access routes that had been deemed safe to use, it
can be seen that the condition of the blast furnace varies
dependant on its elevation and exposure to climatic conditions. The
majority of access routes are in a severe state of dilapidation and
are cordoned off to prevent injuries occurring. The major risks
throughout the whole blast furnace site can be categorised into two
areas.
1, Items falling from height,
2, Persons falling from height
Due to the risks mentioned above, routine condition assessments of
the structures are becoming increasingly challenging due to the
unsafe conditions of access systems and building fabrics. The
condition of the blast furnace complex shall only further
deteriorate with time.
At present the lower and middle blast furnace support structure are
in an adequate condition to fulfil their duties. The furnace top
tower structure is undergoing severe corrosion, which if left
unattended shall accelerate, lead to failure and its inability to
support the furnace top equipment and the dirty gas system.
The building fabrics are in a very poor state of repair, especially
around the casthouses and ancillary sections of the plant. It is
evident that many items have fallen from considerable
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 7/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
.
height and shall continue to do so. The loss of sheeting / cladding
shall lead to an increased risk of structure / framework
collapse.
Corrosion mechanisms around the blast furnace are now very well
established. This is more noticeable on the furnace top where it is
exposed to external weathering events. The majority of painting
systems on the steelwork structures have decayed to a point where
pitting corrosion and crevice corrosion is prevalent. This shall
eventually lead to the failure of structures.
Blast furnace lower support tower
The lower support tower of the blast furnace is a double slope
structure in excess of 400te. From the available vantage points the
tower structure showed no obvious signs of degradation or
deformation that could immediately affect its load bearing
capacity. It is anticipated that small repairs would need to be
conducted to maintain its integrity.
Blast furnace middle support tower
The middle support tower of the blast furnace is the largest
structure of the blast furnace and is in excess of 900te.
The top section of the middle support tower carries the load of the
dirty gas system and transmits this load through the lower tower
structure to the foundations. From the available vantage points the
lower section of the middle tower structure showed no obvious signs
of degradation or deformation that could immediately affect its
load bearing capacity.
The top section of the middle support tower is exposed to the
elements and the paint system has deteriorated. The structure is
now undergoing severe pitting and crevice corrosion and has
structural sections that have failed in places. The connecting
splice plates of the tower structure show evidence of laminations
and deformation at the joints.
Middle tower structure (upper section) heavily corroded Pitting
corrosion and splice deformation on middle tower
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 8/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Blast furnace top support tower
The furnace top tower is a structure in excess of 400te and
incorporates a double outrigger crane. The top tower support
provides the support for housing the furnace charging equipment and
also the access systems to the bleeder platform.
The top tower structure paint system has deteriorated, and the
structure is now undergoing severe pitting and crevice corrosion
and has structural sections that have failed in places. The
connecting splice plates of the tower structure show evidence of
laminations and deformation at the joints.
The outrigger crane splice plates are showing signs of deformation
on the beam webs. This is evident at all four joints.
Pitting corrosion and failed section on beam Outrigger crane splice
plate deformation
Outrigger crane support heavily corroded
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 9/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Casthouses
The building fabrics of the casthouse are in an extreme state of
degradation due to loss of roof and wall sheeting. The exposed
supporting purlins are showing signs of damage and corrosion. The
west casthouse roof has experienced almost a complete loss of
sheeting and the east casthouse has experienced partial loss and
has many items of sheeting that have failed and are about to fall
to ground. The wall sheeting’s are in the initial stages of failing
with partial loss. The loss of wall sheeting shall only be
exacerbated due to the loss of roof sheeting.
West casthouse roof West casthouse wall sheeting
East casthouse roof
Below the casthouse floor, the supporting structure is in good
condition with the refractory brick protection still in place. The
end connections to the casthouse floor look in reasonable
condition.
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 10/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
.
On the casthouse floor, the casthouse machines look in reasonable
condition. Fallen roof sheets are evident in many areas of the
casthouse floor. The iron and slag runners have been backfilled to
allow for a level area. Pigeon carcasses and excrement is present
in many areas of the casthouse floor.
West casthouse floor East casthouse floor
The tuyere platform is in good condition with the steelwork and its
connections showing no obvious signs of serious degradation. The
tuyere platform floor is complete with its refractory and concrete
in good condition.
All 36 tuyere stocks and their respective copper cooling elements
are in position.
Tuyere platform and tuyere stocks
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 11/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Main charge conveyor
The main charge conveyor supporting structure is showing signs of
serious degradation due to corrosion on the trestles towards the
head end of the conveyor. Support trestle bracings have completely
failed in places.
The trestles towards the tail end seem to be in a reasonable
condition.
The gantry support frames are collecting dust and debris in the
webs of the structural sections which is increasing the corrosion
rate in these areas with some sections already holed.
The conveyor belt has been removed to reduce the overall load
exerted on the structural supports.
The conveyor sheeting is in reasonable condition with only small
sections of flashing missing.
Support trestle heavily corroded at bolted connection Support
trestle failed bracings
Support trestle heavily corroded braced connection Gantry frame
supports
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 12/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Off gas system
The off-gas system comprising of the offtakes, uptakes, breeches
and downcomer are in a poor state of repair and are showing signs
of pitting corrosion. The rate of corrosion is more prevalent at
the exposed areas. As the furnace is in the cold condition and with
the presence of chlorides from the North Sea the rate of corrosion
is expected to increase significantly. With sections of staircase
and walkways attached to the off gas system, a deterioration of
this system would reduce its ability to support items
attached.
Downcomer corrosion Corrosion on the Breeches
Offtake corrosion
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 13/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Access systems
The majority of the access systems (staircases, ladders and
walkways) throughout the blast furnace complex are in an extremely
poor state of repair. Many access systems have been cordoned off as
they pose a risk to users. Due to the limitation of access
throughout the complex there are many areas that can’t be
conventionally inspected due to the safety concerns. The following
areas were unavailable for inspection due to access
restrictions;
x Hot Blast Stoves
x Gas cleaning plant
x Fume extraction plant
Due to the access restrictions, the above-mentioned areas could
only be inspected from a distance.
The main defects noted on the access systems include:
x Heavily corroded and holed stair stringers
x Heavily corroded and detached stair treads
x Heavily corroded and holed handrails, standards, mid rails and
kick flats
x Sharp edges on handrails, mid rails and kick flats
Staircase with heavy corrosion and holed members Typical stair
tread in the process of failing
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 14/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Ancillary plant and infrastructure
The ancillary plant surrounding the blast furnace is in a state of
disrepair and has many risks for people accessing the area. The
major risks like the rest of the plant are items falling from
height or persons falling from height.
The sheeting to buildings is failing in many areas and this is
exposing the inner structures and workings and shall eventually
lead to a complete failure of the buildings fabrics.
The majority of column footings for the structures, gas mains and
ductwork are covered in debris that shall accelerate corrosion and
eventually lead to failure. The supporting steelwork is showing
advanced stages of corrosion and many members are unserviceable
with holed sections evident. Access systems around the ancillary
plant cannot be used due to the unsafe conditions.
Cable containment in many areas has failed and cables are left
unsupported. These cables shall eventually fall to ground.
Vent pipes around the stoves area are in a perilous unsecure state
as nearly all have heavily corroded or failed pipe supports. The
waste gas main chimney in the stoves area is showing signs of heavy
corrosion with holed plate work in the top section.
Coke oven gas pipework throughout the blast furnace area is under a
nitrogen purge due to the remnants of crystalline naphtha deposits
within the pipework. This pipework is in a poor state of repair
with leaks evident.
Fume extraction filter plant – sheeting loss Fume extraction –
exposed filter bags
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 15/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Cable containment failure Excessive build-up of material around
column footings
Holed gas main support trestle Vent pipes with corroded / failed
support brackets
Waste gas chimney, heavily corroded and holed plate work Refractory
heatshield with fallen refractory material
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 16/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Conclusion
At present the blast furnace complex is in an extremely dangerous
condition and is unsuitable for allowing access to the
public.
The current condition of the furnace poses a risk for the trained
and competent structural inspectors and it is proving evermore
challenging to inspect for defects and monitor known defects within
the structures.
The overall stability of the blast furnace complex shall only
worsen without intervention.
To enable the blast furnace to be developed so that visitors can be
admitted, the following shall need to be undertaken to ensure the
furnace’s integrity.
1. Remove all immediate risks of items falling from height.
2. Repair / reinstate access systems.
3. Conduct thorough structural inspection.
4. Conduct Refurbishment & Demolition survey for the presence
of asbestos and take appropriate action to remove or
encapsulate.
5. Repair deficiencies as per structural inspection report. Design
considerations to be made for application of temporary works during
repairs.
6. Implement corrosion protection systems (Coating and Cathodic)
and monitor.
7. Demolition of ancillary buildings / systems.
8. Develop and implement a maintenance strategy to maintain the
blast furnace integrity and prevent further degradation.
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 17/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
5 Corrective and stabilisation works – Cost Basis
The costing basis has been calculated so that the following
entities of the blast furnace are retained, and work undertaken to
stabilise the structures and corrosion mechanisms: -
x Furnace proper.
x Dustcatcher and gas cleaning plant.
x Clarifier basin.
x Fume extraction plants.
x All Heat exchangers and cooling towers.
x All brick construction buildings.
x Waste gas chimney.
x Clean gas main after the gas cleaning plant.
x Cold blast main.
x All coke oven gas, nitrogen and natural gas pipelines throughout
all areas of the furnace.
x All vent pipes.
x All storage tanks.
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 18/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Project Costs
To undertake the works required to allow visitor access to the
blast furnace the following budget costs shall be considered.
Corrective works required to stabilise structures and create safe
access £6,500,000
x Inclusive of all plant, equipment and materials.
Corrosion protection (Coating and Cathodic systems)
£2,100,000
x Cathodic protection for column footings and lower
steelwork.
x Coating protection for all other areas.
Demolition of existing ancillary entities £5,400,000
x As per item list on page above.
Site CDM infrastructure and management, consultancy and design
works £6,800,000
x Site establishment and security.
x Management, supervision & staff.
x Design (stabilisation and temporary works).
x Architectural heritage design.
x Temporary works management.
x Building including utilities and fire protection.
x Disabled access.
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 19/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
x Asbestos removal or encapsulation.
x The above costs do not include for any scrap recovery
credits.
x Scrap processing from disposal area.
x Recovery credits on copper cooling elements from within the
furnace.
x General site security.
x All demolition works are to ground floor level only and excludes
removal of foundations.
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 20/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
6 Proposed Visitor Centre
The focal point of any blast furnace complex is the casthouse floor
where people can appreciate the machinery and systems in place to
remove the hot metal from the furnace and subsequently separate the
iron and slag.
It is proposed that an 800m2 (GIFA) building is constructed in the
vicinity of the west slag pits as shown below so that visitors can
view the overall blast furnace complex and receive historical
information on iron-making within Teesside.
From the visitors centre a safe route should be established to
allow for people to enter the west casthouse using the ramp on the
north side of the slag pit.
Due to the inclined nature of the ramp this may not be suitable to
lesser abled persons and an elevator shall be considered to allow
access to the casthouse from ground floor level.
A hardstanding shall require creating around the area of the west
slag pits and shall incorporate parking for buses etc.
Approved E.ZX0M
Blast Furnace Visitors Centre Suitability Study Technical
Specification
PT No: E.ZX0M Rev: 00 Page: 21/21 File: RBF condition assessment
R01.docx Printed: 2020-10-23 14:17
© P
Maintenance management £185,000 / year
Maintenance works £285,000 / year
Electricity (200kwh) £212,000 / year
REDCAR BLAST FURNACE: DETAILED SUMMARY OF INDICATIVE COSTS
Indicative costs excluded from the Redcar Blast Furnace Visitor
Centre Sustainability Study (2020) – Provided by the South Tees
Development Corporation to the Tees Valley Combined Authority for
presentation to the Teesworks Heritage Taskforce
1. Asbestos removal or encapsulation A report from DDM Demolition
that estimates the cost of total asbestos removal connected with a
full demolition of the RBF complex at £6M. In terms of the partial
demolition proposed under a retained RBF scenario, I would assume
the following • Asbestos removal (peripheral asset demolition):
£1.0M • Partial asbestos removal (retained RBF) for safe access and
usage: £1.0M • Encapsulation of asbestos where possible: £0.5M
Asbestos removal cost: £2.5M
2. Scrap recovery credits
DDM assessed the total scrap metal content of the RBF complex at
30,000 tonnes. I would assume around 25% would be connected with
the demolition of the peripheral assets, i.e., 7,500 tonnes. Scrap
metals recovery credits: £1.35M
3. Scrap processing This is normally included in the demolition
cost. But we can assume 7,500 tonnes for processing in this
instance. Typical rates, including transport, range from
£25.00-£35.00 per tonne, I’ve assumed £35.00 per tonne due the
heavy duty nature of the demolition and related metalwork. Scrap
metals processing cost: £0.26M
4. Recovery credits on copper cooling elements It’s unclear what if
any copper elements could be recovered from the RBF under a
retained scenario without incurring appreciable costs connected
with their recovery. The assessment on copper contained in the RBF
was estimated by STSC at around 750 tonnes. Assuming we consider
that 100 tonnes is recoverable under a non-demolition scenario, and
with scrap copper typically priced at £4,000/tonne, the position
would likely be close to: Recovery credits – copper: £0.4M Cost of
recovery: £0.1M Net recovery credits: £0.3M
5. General site security Fencing (1,000m): £0.25M
2
Cameras, cabling, etc: £0.05M Security lighting: £0.05M Alarm
systems: £0.05M Site security cost: £0.4M
6. Removal of foundations This is assumed to be related to the
removal of foundations connected with the demolition of the
peripheral assets. The area of such assets is around 20,000 sq. m,
assume 0.75m thick throughout giving £15,000 cu. m of concrete Cost
of foundation removal: £0.23M Processing: £0.2M Filling voids:
£0.07M Removal of foundations – cost: £0.5M
Net position: £2.01M cost
LOAD MORE