Upload
hoangbao
View
213
Download
0
Embed Size (px)
Citation preview
Red Line South: Better, Faster, Smoother.
November 6, 2013
Elsa Gutierrez Will Gillespie General Manager Traffic Analyst CTA Service Planning & Traffic Engineering CTA Traffic Planning
Why It Was Needed
• Track more than 40 years old and beyond useful life
• Nearly 40 percent of Dan Ryan Branch was slow zone
• Slower trains = longer commutes and increased operation costs to CTA
• Improvements would save up to 20 minutes off daily round-trip commute for South Side riders
2
5 Months or 4 Years? 5 Months
• Full closure Cermak-Chinatown to 95th Street
• 20 min passenger savings by end of 2013
• More efficient and cost-effective schedule
• More consistency in construction work – better final product
4 Years • Weekend-only closures of
various portions in stages • Slow zones continue (and
increase) thru 2016 • Would increase project costs
by $75 million • Work is done in segments
which may reduce consistency
3
Rail Service Considerations • Passenger Demand:
• Red Line: 255,000 daily passengers • Green Line: 63,000 daily passengers
• Peak Rail Car Requirements • Red Line: 296 cars • Green Line: 90 cars
• Cottage Grove branch only accommodates 6-car trains
• Power and Signal limitations
4
New Rail Alignment • Red Line trains operate between
Howard and Ashland/63rd on the elevated tracks south of Roosevelt
• Green Line trains operate between Harlem/Lake and Cottage Grove • Some AM trains turn back at Roosevelt • Some PM trains operate counter-
clockwise around the Loop
5
Alternative Service
• Who is impacted? • Where are they going? • What obstacles do they face? • How can we provide
alternatives? 1. Free shuttles 2. Route extensions 3. Route enhancements
6
Rail destinations for 69th-95th riders
16%
22%
32%
17%
Other = 13%
Free Bus Shuttles
• Limited rail alternative • Accommodate passenger
demand on Red Line • Simulate Red Line service
with buses – Maintain frequency – Maintain loads – Maintain travel time – Maintain 24-hour service
7
Planning New Shuttle Routes
8
I/S Pull Tot. In Pull Tot. In Pull Tot.221 10 231 128 2 130 110 2 112
Saturday:2417
Midday Peak6
Midday Peak77
Sun/Hol:Weekday:
Route Description:
Recycle & Recovery:
Span of Service:(first NB trip to last SB trip)
Vehicle Type:
Shuttles will operate direct express service via Garfield Blvd and the Dan Ryan Expressway between Garfield/Green Line Station and 95th Terminal with no interim stopsDuring PM peak, shuttles recycle on the north side via Prairie, 51st, and Elsworth Drive (recovery location). On the south side, shuttles recycle via 95th, Michigan, 99th, and State (recovery location)
60' Articulated buses
Vehicle Hours:(I/S = In Service)
Weekday: Saturday: Sun/Hol:
Vehicles in Service: Midday LowAM Peak PM Peak
Weekday: Saturday: Sun/Hol: 00:4803:53 to 00:48 03:56 00:48to 03:56 to
Interval (begins @ terminal) 4:00 4:30 5:00 5:30 6:00 6:30 7:00 7:30 8:00 8:30 9:00 9:30NB Frequency (minutes) 12.0 12.0 7.0 6.0 4.5 3.5 3.0 3.0 3.5 5.0 6.0 7.0SB Frequency (minutes) 12.0 12.0 7.0 6.0 4.5 6.0 6.0 6.0 6.0 5.0 6.0 7.0Cycle Time (minutes) 49 49 49 49 53 53 53 53 53 53 49 49Deadhead Cycle (minutes) - - - - - 45 45 45 45 - - -NB Passenger Load Per Bus 28 53 56 63 70 71 67 66 73 70 69 58SB Passenger Load Per Bus 7 9 8 9 13 23 31 35 35 31 25 31R95 SB trips depart every 6 mins from 6:30-8:24 so some NB trips will deadhead back to 95th
Shuttle Planning Process
• Origin-Destination (O-D) model data – demand along shuttle routes – northbound & southbound – in 15 minute intervals
• Red Line frequency • Shuttle route cycle length • Bus capacity • Target passenger load
9
95th Shuttle (artics) 17:30Northbound
R/T Cycle Time 64Deadhead Cycle TimeBuses Required @ R/T cycle times 7
SouthboundR/T Cycle Time 64Deadhead Cycle Time 57Buses Required @ R/T cycle times 26
Buses on R/T Cycle 7Add'l NB buses deadhead returning
NB Frequency 10.0NB Buses per Departure 1
Add'l SB buses deadhead returning 17SB Frequency 5.0SB Buses per Departure 2
Total Buses 24
Shuttle Statistics
• Bus Requirements: – 61 - 60’ buses (+ spares) – 10 - 40’ buses (+ spares)
• 5,000 vehicle hours (weekly) • Added 1.3% traffic volume
on Dan Ryan expressway • 17,300 daily weekday riders
10
Routes Extensions • Extensions and reroutes
focused on maintaining connectivity to the rail network
• Routes were deviated or extended to serve Garfield or the Ashland Branch of the Red Line
• Service to closed Red Line stations was temporarily suspended
11
Route Enhancements • Modeled trip decisions of
current customers using O-D transit pass data
• Created a grid of half-mile zones for rider origins
• Focused on north-south routes that feed Ashland branch to minimize additional transfers
• Mostly peak periods • Short-turns focused on
areas with highest demand 12
Number of Daily:
Pre-Construction
During Construction Increase
Passengers 1,500 Trains 236 Buses 304
15,000 1,000% 615 260%
Garfield (Elevated) Transit Hub
13
1,256 413%
Garfield Boulevard
Washington Park
U of C
CTA Park
N’ Ride
CTA vacant land
U of C vacant land
Dan Ryan Expy
Site Location and Routing Options
14
Garfield Boulevard
• Historic Boulevard • Additional approvals
required to create a temporary cut-through
• Preferred alternative needed to out-weigh other options
• But in the end…
15
• Illinois Department of Transportation (IDOT) • Chicago Department of Transportation (CDOT) • Pace Suburban Bus • Metra Commuter Rail • Greyhound Buses • Chicago Parks District • University of Chicago
Agency Coordination
23
End of Project by the Numbers
380 million pounds of ballast 7.8 million pounds of rail 60 thousand rail ties 495 announcement speakers 275 security cameras 87 train tracker displays 36 assistance phones 3 elevators = 100% accessible 0 slow zones
24