Upload
others
View
15
Download
1
Embed Size (px)
Citation preview
Red Gravel Pit – Sandford – 1511 P/M Change to Operation - Supporting Document
Prepared By: Barry Williams
Date: 6 May 2011
Issue Date Recipient Organisation
draft 2 May 2011 David Oldmeadow EPA
Final 6 May 2011 David Oldmeadow EPA
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Introduction 2
CONTENTS
1. Introduction .................................................................................................................................... 3
2. Background ..................................................................................................................................... 4
3. Development Proposal.................................................................................................................. 13
3.1. Regulatory Situation.......................................................................................................... 13
3.2. Operation Description ....................................................................................................... 13
3.2.1. Extraction ...................................................................................................................... 13
3.2.2. Processing ..................................................................................................................... 13
3.2.3. Marketing ...................................................................................................................... 14
3.3. Development Details ............................................................................................................. 14
3.3.1. Current Situation ........................................................................................................... 14
3.3.2. Proposed Operational Improvements .......................................................................... 14
3.3.3. Future Relocation of Infrastructure .............................................................................. 14
4. Possible Environmental Impacts ................................................................................................... 15
4.1. Noise ..................................................................................................................................... 15
4.2. Dust ....................................................................................................................................... 16
4.3. Process water ........................................................................................................................ 16
4.4. Flora and fauna ..................................................................................................................... 16
5. Management commitments ......................................................................................................... 17
6. Conclusion ..................................................................................................................................... 19
FIGURES
Figure 1: Current (2011 – 2014) Mining and Rehabilitation Plan ........................................................... 6
Figure 2: Mid-Term (2014 – 2022) Mining and Rehabilitation Plan ....................................................... 7
Figure 3: Final (2022 – 2025) Decommissioning and Rehabilitation Plan............................................... 8
Figure 4: Mining and Rehabilitation Plan - Cross Sections through Staged Works ................................ 9
Figure 5: Machinery Shed – Plan and Elevations .................................................................................. 10
Figure 6: Loaclity Plan – showing nearest residences ........................................................................... 11
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Introduction 3
1. INTRODUCTION
Project Title Red Gravel Pit at Sandford
Mining Lease Number 1511 P/M
Lease Holder T.H. Jenkins
Lease Operator T.H. Jenkins
Category 3 – Construction Minerals
Area 9 hectares
Client Details Jenkins Hire Pty Ltd ABN 30 050 205 671
Business Transport and Civil Earthmoving
Address P.O. Box 616
Glenorchy TAS 7010
Contact Tim Jenkins Mobile 0418 129 321
Quarry Manager Steve Morrisby Mobile 0408 326 497
Fax (03) 6273 0766
The Red Gravel Pit at Sandford has operated
for over twenty years providing high quality
“red driveway gravel” to the local community.
The mining lease for the quarry, 1511P/M,
covers an area of 9 hectares and the applicant
is both the lease holder and the operator.
The resource is highly weathered dolerite
rock. The dolerite has weathered by a natural
process of moisture penetrating the joints of
the bedrock liberating blocks. The blocks are
then gradually broken down by natural
chemical weathering. The process is called
‘spheroidal weathering’ and it creates course
gravels with high clay content and roughly
spheroid shaped cobbles and boulders.
The ratio of the over-sized (boulders)
component of the gravel varies throughout
the resource area. The oversized material
must be crushed to contribute to the finished
gravel product.
Hobart
Queenstown
Triabunna
Burnie
Launceston
100 0
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Background 4
2. BACKGROUND Table 1: Site Description
Site description
Climate data for nearest weather station – Hobart Airport 094008
Mean max. Temperature (0C) 20.6 Mean min. Temperature (0C) 10.7
Mean annual rainfall (mm) 498.9
Wind data At the nearest weather station 094008 Hobart Airport the predominant wind direction (> 40 %) and the strongest winds come from the northwest. Afternoon sea breezes tend to cause summer wind conditions to change to a strongest prevailing wind from the south east.
Land capability The land occupied by the quarry has been field checked and classified as class 4; land well suited to grazing but which is limited to occasional cropping or a very restricted range of crops.
Aspect The site is located on a west facing slope of a low hill that is the terminus of a northeast running low ridge off Mount Augustus. Although the mining lease covers the crest of the ridge, the quarry has been confined to the western slope so as to retain to natural skyline. The top of the quarry’s eastern face is at around RL 70m and the sediment trap at the north west corner is at around RL 40m.
Vegetation The quarry is surrounded by agricultural land mostly sown to pasture. Remnant woodland in the vicinity of the quarry is mapped as (DTO) Eucalyptus tenuiramis forest and woodland on sediments. A small clump of (DTD) Eucalyptus tenuiramis forest and woodland on dolerite located nearby represents the floristic structure that would have existed on the land prior to clearing.
Geophysical data The target resource in the quarry is a fairly course grained dolerite gravel derived from naturally occurring weathered dolerite rock. Dolerite bedrock is exposed on the eastern face of the quarry. Massive dolerite is outcropping in parts of the floor of the quarry in front of this face. The balance of the quarry is ripping successfully. The soil type is described as a Dermosol; ‘undefined brown soil developed on Jurassic dolerite bedrock and colluvium on rolling to steep land.
Fauna There is little evidence of native fauna on the site. Frogs may periodically inhabit the two sediment retention basins.
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Background 5
Plate 1 Panorama looking west from the top of the eastern face, land recently re-habilitated in the foreground.
Plate 2 Looking west along bench in the recently rehabilitated north face Plate 3 Looking north across recently worked out area in southeast corner
Red Gravel Pit – Sandford – Development Application
Figure 1: Current (2011 – 2014) Mining and Rehabilitation Plan
0 75 150
Sediment
retention
Current
extraction
3
north
2
1
Access road
Boundary of mining
lease 1511P/M
Rehabilitation area re-
contoured with topsoil
applied
Crusher
Sediment
retention
Product
stockpiles
Overburden
Rehabilitation area re-
contoured with topsoil
applied
Contour drain for irrigation dam
Topsoil
A
A
Machinery shed
Red Gravel Pit – Sandford – Development Application
Figure 2: Mid-Term (2014 – 2022) Mining and Rehabilitation Plan
0 75 150
Sediment
retention
Mid-term
extraction
north
Boundary of mining
lease 1511P/M
Rehabilitation area with
pasture applied
Sediment
retention
Contour drain for irrigation dam
Topsoil
Rehabilitation area re-
contoured with topsoil
applied RL 45m
Rehabilitation area with
pasture applied
A
A
Machinery shed
Crusher
Rehabilitation area
re-contoured with
topsoil applied
Product
stockpiles Planting tree screen
Supplement existing
revegetation with infill
planting
Access road
Stockpiles to
screen crusher
Red Gravel Pit – Sandford – Development Application
Figure 3: Final (2022 – 2025) Decommissioning and Rehabilitation Plan
0 75 150
Sediment
retention
A
A
north
Access road
Boundary of mining
lease 1511P/M
Sediment
retention
Contour drain for irrigation dam
Rehabilitation area re-
contoured with topsoil
applied RL 45m
Rehabilitation area re-
contoured with topsoil
applied RL 50m
Rehabilitation
area re-
contoured with
topsoil applied
RL 55m
All structures and
machinery removed
New planting at toe of
eastern face
Red Gravel Pit – Sandford - Decommissioning and Rehabilitation Plan
Figure 4: Mining and Rehabilitation Plan - Cross Sections through Staged Works
Extraction area
Product stockpiles
Section A-A
RL 60 m
RL 45 m
RL 65 m
Extraction area
Stockpiles located to screen crusher
Section A-A
RL 60 m
RL 45 m
RL 50 m
Oversized against face topsoil over
and planted with woodland species.
Section A-A
RL 55 m
RL 45 m
RL 50 m
Topsoil and pasture grass
Machinery shed
Current Mining Plan and Rehabilitation Works
Mid-Term Mining Plan and Rehabilitation Works
Decommissioning Plan and Rehabilitation Works
Relocated machinery shed
Figure 6: Locality Plan – Showing residences within 1 km of the quarry
north
0 650
Screened by hill side
Screened by hill side
Plate 4 View from new crusher site looking west towards Germain Court
Plate 5 View from 43 Rushton Close towards quarry Plate 6 View from outside 64 Germain Court with 69 Germain Court in forground
64 Germain Court 41 Rushton Close 45 Rushton Close
Existing product stockpile
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Development Proposal 13
3. DEVELOPMENT PROPOSAL
3.1. REGULATORY SITUATION
The quarry operates under existing use rights with regard to the Clarence City Council and the
Environment Protection Authority regulates the quarry through’ License to Operate Scheduled
Premises’ number 5932. This license specifies a maximum production limit of 20,000 cubic metres of
product per annum. The license also has a limit of 2,000 tonnes of material that can be processed
through a crusher.
A mining lease number 1511P/M covers the quarry site and the Department of Infrastructure Energy
and Resources also regulates the quarry operation through Mineral Resources Tasmania. The quarry
must be operated in accordance with the Mineral Resources Development Act 1995 and the Quarry
Code of Practice 1999.
3.2. OPERATION DESCRIPTION
3.2.1. EXTRACTION
The product is extracted by ripping with a dozer and pushing up into stockpiles. The extraction areas
are predominantly shallow (less than ten metres). Closer to the ridgeline hard bedrock has resisted
ripping and further extraction is impractical. The current extraction area is closer to the lower
extremity of the site and the working faces will be low to maintain drainage. The extraction areas are
‘set out’ in a series of three benches separated by approximately 5 metre high faces. Excavation
proceeds from a number of extraction points, each offering slightly different product properties. The
products are then blended to produce the final specification product.
In all the extraction areas the proportion of oversized boulders and cobbles encountered during
excavation varies according to the location in the pit and the depth of excavation. When oversized
product is encountered in the extraction area or is rejected by the screens, these materials are
stockpiled.
Normal operating hours for the quarry are as listed below:
Weekdays 7:30 am to 6:00 pm
Saturdays 8:00 am to 4:00 pm
Sundays and public holidays no work
3.2.2. PROCESSING
A wheel loader is then used to transport the product to screens where oversized materials are
removed. Products with varying properties can be blended through the screens to produce a
consistent blended product for sale.
Periodically it is necessary to crush the oversized material to provide hard angular aggregate to
blend with the softer natural gravel and clay to keep the final product within specification. When
placed and compacted the crushed rock gives the pavement strength and wear resisting properties
and the finer gravel and clay binds the pavement and provides a smooth and water resistant surface.
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Development Proposal 14
3.2.3. MARKETING
The final product is stockpiled in its blended form ready to be loaded out on single tray trucks or
truck and trailers. The “red driveway gravel” is an ideal product for domestic driveways in a rural
setting but is also used to construct high quality gravel roads, walking tracks and fire trails. The
quarry is situated within a fast expanding rural residential setting; the Operator is thus able to supply
quality products at competitive prices to the local area.
3.3. DEVELOPMENT DETAILS
3.3.1. CURRENT SITUATION
To adequately supply the existing and future markets with a consistent quality product the Quarry
Manager requires the capacity to crush oversized product at a rate consistent with product
specifications. Currently the product quality is compromised by the limit on crushing product to
2,000 tonnes per annum. The maximum production capacity of the quarry is 20,000 cubic metres of
processed product. At an average bulk density of 1.5 t/m3, the quarry can produce 30,000 tonnes
per annum. With the current limit on crushing of 2,000 tonnes the crushed rock can only comprise 7
percent by mass of the finished product.
Although adequate for the product derived from some of the extraction areas, in other areas the
lack of crushing capacity has lead to lower quality product specifications and growing stockpiles of
oversized product. The oversized stockpiles are occupying valuable hardstand and extraction space
and constraining the efficient layout of the quarry.
3.3.2. PROPOSED OPERATIONAL IMPROVEMENTS
This development proposal seeks to increase the annual limit on crushed product from 2,000 tonnes
to 7,500 tonnes. This operational improvement will result in the Quarry Manager having the capacity
to blend up to 25 percent by mass of the crushed rock into the gravel.
To effect the change the Quarry Manager will operate the quarry’s Terex Jaques 20 by 12 inch jaw
crusher. This crusher has a production rate of around 100 tonnes per 8 hour day. To achieve the new
production capacity the Quarry Manager will operate the crusher around 75 days per year between
the hours of 8:00 am and 4:00 pm on weekdays only. The reduced operating hours for the crushing
operation are being introduced by the operator to further reduce the risk of neighbours being
adversely affected by noise.
3.3.3. FUTURE RELOCATION OF INFRASTRUCTURE
It will be necessary in the future to relocate the existing machinery shed to a new site within the
quarry floor. The existing site for the machinery shed was established when the quarry was first
developed. The site is now visually exposed and since the resource has been recovered from around
it, the structures are elevated.
In the mid-term (2014 to 2022) of the quarry development the machinery shed and refuelling facility
will be relocated to a ‘worked-out’ section of the quarry floor adjacent to the eastern face. This site
will reduce the prominence of the building and expose additional resource. Extraction of this
resource will enable the mining plan to progress towards the final planned landform. The tank for
the refuelling facility will be located within an impermeable bund with a minimum capacity of 110
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Possible Environmental Impacts 15
percent of the tank’s capacity. Minimal quantities of oils and chemicals will be stored on site within
machinery shed building.
The new location of the building is shown in Figures 2 and 4 and details of the building are described
in Figure 5.
4. POSSIBLE ENVIRONMENTAL IMPACTS The Red Gravel quarry at Sandford is a level 2 activity under schedule 2 of the Environmental
Management and Pollution Control Act 1994. As such the environmental impact of the activity or any
“intensification” of the activity is assessed by the Board of the Environment Protection Authority.
4.1. NOISE
Noise is best attenuated by distance and topography. The closest neighbours to the quarry are
located on the opposite side of the ridgeline to the quarry. The intervening topography effectively
screens these properties from a view of the quarry and noise. There are neighbours on elevated land
to the west of the quarry that although 750 metres distant are more likely to be affected by
operating noise from the quarry. In Figure 6 a number of residences that are located within 1
kilometre of the quarry are identified. Others on Delphis Drive are very well screened by the ridge
line and are not considered. Excavation to date has caused the operation to be lowered and the line
of sight to the majority of residences is now interrupted by cut batters. Figure 6 shows sight lines
that indicate the range of visible exposure of the quarry.
Stockpiles will be located to provide an effective screen adjacent to the crusher to protect
neighbours in the westerly direction from noise generated by the crusher. The stockpiles will absorb
and deflect much of the noise generated by the crusher away from the residences. The crusher
should no longer be visible from these residences and when a massive structure hides equipment
generating noise much of the noise is intercepted as well.
Plate 4 is a view from the proposed new location for the crusher. Three residences are clearly visible
on the hill to the west. In this plate it can also be seen that an existing product stockpile some
distance away from the proposed crusher location completely interrupts the sight line. If this
stockpile extended more to the left of the frame the residences would not be visible. It is the
intention of the Quarry Manager to relocate the crusher to this site and construct a permanent
overburden stockpile that will completely conceal the crusher from view.
The proposed revised layout of the quarry can be seen in the mid-term mining plan and cross-
section. It can be also seen on this plan that it will be necessary in the future to relocate the
machinery shed and office. The timing of the relocation will depend on progress with the mining
plan and the need to access the resource under these facilities. The arrangement of the crusher and
stockpiles will remain until quarry decommissioning at which time the overburden stockpiles will be
used for land contouring and rehabilitation works.
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Possible Environmental Impacts 16
4.2. DUST
An operating crusher can add to the amount of dust generated by a quarry operation. Other sources
are drop points from conveyors, vehicle movements, loading and unloading trucks and stockpiles,
and exposed un-vegetated surfaces.
As a condition of the continuation of the mining lease the lease holder is required to ensure that no
visible dust crosses the mining lease boundary in any direction. The worst conditions for wind
carrying dust are likely to occur in the summer months when prevailing dry conditions conspire with
strong afternoon sea breezes to potentially cause dust to be carried across the boundary to
northwest.
The Quarry Manager will continually monitor dust conditions and will introduce remedial actions if a
risk of an emission is likely. Remedial action will include:
using water sprays to dampen dusty surfaces,
either covering or wetting the surface of loads leaving the quarry, and
using water sprays to settle dust generated by the crusher and at conveyor drop points.
Surfaces and stockpiles will be damped down when dry and windy conditions are expected over
weekends when the quarry is not operating.
4.3. PROCESS WATER
Operating the crusher for longer periods during the year should not increase the amount of process
water utilised on the site other than for dust suppression purposes. The maximum amount of water
used will be during the dryer months which will coincide with the minimum amount of rainfall
runoff. The sediment retention facilities currently employed (see Figures 1, 2 and 3) will be adequate
to capture this amount of water and detain it long enough for the suspended particles to settle out.
The stages of development in Figures 1, 2 and 3 show the main drainage paths as blue lines and the
two sediment retention basins as blue shapes. It can be seen that water runoff management will
remain unchanged through the life of the quarry and after decommissioning.
4.4. FLORA AND FAUNA
The changes to the operations of the quarry will not cause any additional area of natural vegetation
to be disturbed. The only vegetation that will be removed is that planted by the Operator on
stockpiles close to the existing location of the machinery shed. The removal of this vegetation is
included in the mining and rehabilitation plan previously submitted.
No habitat for native flora and fauna will be disturbed to facilitate this change to the process; there
will be no resultant adverse impact on native flora and fauna. The sediment retention ponds will
remain for the life of the quarry and after rehabilitation. When the entire site is vegetated it will no
longer be necessary to clean accumulated silt from the ponds.
The rehabilitated areas will be planted out with plants of local provenance generally in accordance
with the planting schedule in Table 2.
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Management commitments 17
Table 2: Planting Schedule
Zone Canopy Understorey Groundcover
Native woodland E. tenuiramis (silver peppermint) Acacia dealbata (silver wattle) Epacris myrtifolia (common heath)
E. amygdalina (black peppermint) Banksia marginata (honeysuckle) Lomandra longifolia (sagg)
E. globulus (blue gum) Allocasuarina littoralis (drooping sheoak) Kennedia prostrata (running postman)
Planting rate One plant per 9 square metres
Fertilizer Accompany the seedlings with slow release fertiliser, either 30g tablet or similar volume of pellets.
Improved pasture A commercial pasture seed mix based on Lolium perenne (Perennial ryegrass) Dactylis glomerata (cocksfoot) and trifolium. repens (white clover) if appropriate.
Alternatively a mixture of native grasses will not be as persistent or invasive. Suggested species include Themeda triandra (kangaroo grass), Danthonia caespitosa (wallaby grass) and Poa labillardierei (tussock grass)
Seeding rate Ryegrass, 10kg/ha Cocksfoot, 3kg/ha White clover, 2 – 4 kg/ha
Fertilizer Apply fertilizer 14:16:11 at a rate of 600 kg/ha if soil has been stockpiled for long periods.
Stabilisation works Acacia dealbata (silver wattle) Lomandra longifolia (sagg)
Alternative for erosion control is spray applied mulch with a mixture of grass annual seed and native plant seed included.
5. MANAGEMENT COMMITMENTS Table 3: Commitments Table
Item Description Timing Responsible
1 The quarry will be laid out such that stockpiles will provide a permanent barrier between the crusher and residences to the west and south.
On approval of change Quarry Manager
2 The crusher will only operate between 8:00 am and 4:00 pm on weekdays On approval of change Quarry Manager
3 Dust conditions will be constantly monitored and remedial measures including those outlined in the document will be deployed if an emission is likely.
Immediately and ongoing Quarry Manager
4 Stormwater runoff from the site will be controlled and directed to the existing sediment retention ponds The ponds and drains will be retained and remain unchanged.
Ongoing Quarry Manager
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Management commitments 18
5 This production change will not result in any extra clearing of natural vegetation. Ongoing Quarry Manager
6 The fuel storage tank will be located in an impermeable bund with a spill capacity of no less than 110 percent of the tank volume
Immediately and ongoing Quarry Manager
7 The quarry will be progressively rehabilitated as detailed in the Decommissioning and Rehabilitation Plan and in accordance with the requirements of the Mineral Resources Development Act 1995.
Ongoing Quarry Manager
Red gravel pit – Sandford – Change to Operation Final
Integrated Land Management and Planning | Conclusion 19
6. CONCLUSION The continued efficient operation of the Red Gravel Pit at Sandford will facilitate the development of
the Sandford – South Arm district by providing locally produced quality construction materials. As
transport costs, traffic congestion and green house gas emissions become a greater problem for
growth in construction, a locally situated quarry will be an asset for residents and businesses alike.
It is essential that the Sandford Quarry should produce the highest quality product that the natural
resource and skills of the Quarry Manager allow. At present this is not always the case and this
Development Application seeks to redress this situation.