New York State Department of TransportationRegion 11

Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 -

Van Wyck ExpresswayThe Roll-in/Roll Out Method

Page 2: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Project Partners

Owners

Resident EngineerContractor

Designer

Page 3: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

PROJECT SITE

QUEENS, NEW YORK

Page 4: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Jamaica AvenueEarly 1900’s

Van Wyck Expressway1951

Page 5: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Hillside Avenue

Jamaica Avenue

AERIAL OF PROJECT SITE

Page 6: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Description of ProjectScope of Bridge Work -– Remove entire superstructure - 110 feet long– Remove and relocate abutments– Remove and replace center pier stem– Install new two-span continuous bridge - 28 feet longer than existingScope of Work on Van Wyck Expressway (I-678) -– Widen segment by addition of accel/decel lanes in both directions– Improve safety of VWE with full width flush shoulders– Resurface all six lanes over a half mile in length– Upgrades to drainage, lighting, ITS, signing, landscaping

Page 7: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Why Roll-in/Roll-Out?High local volumes –more than 1,100 VPH (peak)

High Expressway volumes ADT 160,000 (VWE)

Difficult to detour over extended period

Problematic to stage due to highly congested area

Must maintain access to Jamaica Hospital

Page 8: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Primary Roll-in/Roll-out BenefitsPotential to reduce overall construction time

Substructure and superstructure can progress concurrently

Improved quality of new structure

Mitigate the impacts on the community and traffic.

Page 9: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

JFK AIRTRAIN (PANYNJ)

Page 10: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Design IssuesCamber adjustments due to temporary support locationsFirst LRFD superstructureLimited window for rollingRolling scheme was fully designed – sled on fixed rollersSpecial specifications

Interagency CoordinationSubway tracks – vibration monitoring, no loads transferred to subway at any timeVerizon phone lines –could not relocateSubstructure design –spatial constraintsUtility relocation – utility bridge

Page 11: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Animation

Page 12: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Construction ChallengesUnconventional for roadway bridges – unknowns

Demolition while maintaining traffic

Erection and demo over traffic

Asbestos abatement

Utilities

Proximity to JFK Airport

Hours of closure – roll-in had to be completed in one weekend

Page 13: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

FULL DETOUR SIGNAGE

Page 14: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Public Outreach• Began substantial public outreach campaign 3-4 weeks in advance of

construction• Communicated project details via letters, meetings, etc. to: area elected

officials; service agencies (PANYNJ, NYPD, FDNY, MTA); hospitals; JFK Airport interests (Taxi and Limousine Commission,airlines, airport employees, private bus companies, trucking companies).

• Broadcast of press release/travel advisory to Tri-State media outlets and coordination of area-wide VMS signs (NY, NJ, CT)

• Posted construction details on State and City websites• Notifications to area residents, community boards and businesses on

Jamaica Avenue• Produced extensive radio advertisements

Special Efforts

• Established 24/7 “Command Center” at Jamaica Hospital staffed by NYSDOT, NYCDOT, NYPD, FDNY, and hospital Emergency Services. The Center remained activated for four days to monitor and report on the status of the work and address any critical situations.

Page 15: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Construction Photos

Page 16: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Construction Photos

Page 17: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Construction Photos

Page 18: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Construction Photos

Page 19: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

JACKING OF BRIDGE

Page 20: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

ROLLING THE BRIDGE

Page 21: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

LOWERING THE BRIDGE

Page 22: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

NEW BRIDGE WITH TRAFFIC

Page 23: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

Project Cost: $32 Million

Page 24: Reconstruction of Hillside and Jamaica Avenue …...New York State Department of Transportation Region 11 Reconstruction of Hillside and Jamaica Avenue Bridges over I-678 - Van Wyck

ACT II

HILLSIDE AVENUE

Hillside Avenue’s Roll-In/Roll-Out

July 2006