Page 1: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM

RECAPP Facility Evaluation Report

R. J. Hawkey Elementary SchoolB2395AAirdrie

Rocky View Sch Div #41

Page 2: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 2 of 58

B2395ABuilding Id:

R. J. Hawkey Elementary SchBuilding Name:

AirdrieLocation:233 Big Springs Drive Address:

4,058.91Gross Area (sq. m): $9,288,597Replacement Cost:1980Construction Year:

Evaluation Date: July 11 2007

Quinn Young Architects LtdEvaluation Company:

Sheldon QuinnEvaluator Name:

This one storey K-4 Elementary school was constructed in 1980 with an area of 2965.7 sq.m. In 1993 six existingportables were retrofiitted & relocated to the site and four new portables were constructed along with a connecting link foran additional area of 1097.3 sq.m. In 2000 The administration area of the school was modernized. The current total areaof the school is 4063 sq.m. With 21 classrooms the school has a current capacity of approximately 420 students

General Summary:

Structural Summary:The school is constructed with a slab on grade, concrete foundation walls and concrete strip footings. There are raisedconcrete floors over the chair storage area at the stage and at the mechanical mezzanine. Concrete block exterior walls areload bearing supporting a metal roof deck and OWSJ's . The interior structure consists of a combination of interior loadbearing concrete block walls and HSS columns on concrete pedestals and pad footings. Overall the structure is in acceptable condition.

Envelope Summary:The exterior walls are split faced concrete block and block veneer at the gymnasium. The upper fascia band of the wallwas reclad with prefinished metal cladding. Exterior doors are painted metal in pressed steel frames and windows aredark bronze anodized aluminum with double hung venting units. Recently the roof membrane has been replaced with aSBS membrane roof except for the upper mechanical room. Overall the exterior is in acceptable condition

Interior Summary:Interior flooring is undergoing replacement with sheet vinyl installed in exterior classrooms and new carpeting in thelibrary, administration, computer room, staff room. The original classroom block consist of dismountable partitions andconcrete block walls around the washrooms, mudrooms, and locker & gym areas. Ceilings are mostly acoustic tiles in a'T' bar grid system except for paint drywall bulkheads and ceilings in the mudrooms, washrooms and storage areas. Thegymnasium has a metal linear ceiling. In 2000 the administration area was modernized. Overall the interior is in acceptable condition.

Mechanical Summary:The School is serviced by two indoor ventilation units located in the mechanical room. Heating is provided by two steeltube boilers located in the mechanical room and perimeter radiation cabinet and fin. Overall the School is in acceptable condition.

Electrical Summary:The main service is rated at 600A, 120/208V, 3-phase, 4-wire. Fluorescent lighting throughout the facility has beenupgraded to T8 lamps with electronic ballasts. Exit lighting is LED. Emergency lighting is from battery packs andremote heads distributed around the school. The fire alarm panel is an Edwards ESA2000. A mix of Cat5/5e cablingprovides data throughout the school. Urgent requirements are the addition of a full-height rack for the data equipment. The PA system is also due for lifecycle replacement. Overall, the electrical systems are in Acceptable condition.

11.46%5 year Facility Condition Index (FCI):

Facility Details Evaluation Details

Total Maintenance Events Next 5 years: $1,064,911

Airdrie - R. J. Hawkey Elementary School (B2395A)

Page 3: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 3 of 58

Airdrie - R. J. Hawkey Elementary School (B2395A)

Condition Rating Performance1 - Critical Unsafe, high risk of injury or critical system failure.2 - Poor Does not meet requirements, has significant deficiencies. May have high operating/maintenance costs.

3 - Marginal Meets minimum requirements, has significant deficiencies. May have above average operating maintenance costs.4 - Acceptable Meets present requirements, minor deficiencies. Average operating/maintenance costs.

Rating Guide

5 - Good Meets all present requirements. No deficiencies.6 - Excellent As new/state of the art, meets present and foreseeable requirements.

Page 4: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 4 of 58

A1010 Standard Foundations*

A1030 Slab on Grade*

4 - Acceptable

3 - Marginal

Rating

Rating

1980

1980

Installed

Installed

0

0

Design Life

Design Life

FEB-08

FEB-08

Updated

Updated

Monitor Floor Settlement & Repair

Repair florr settlement based on study results.

Study

Repair

2008

2009

$17,160

$17,160

Medium

Medium

Wall cracking is occurring between the storage room and StaffWork Room. The floor has separated from the wall at thenorthwest mudroom opposite the washrooms.

Floor settlement between storage rm. and staff work room.

Concern:

Concern:

Review history as to how long these cracks have been visible.Make recommendations which may include: 1) repoint grout/mortar joints and repaint 2) relevel and install new quarry tile floor and base, or 3) mudjack floors as necessary

Complete repairs based on study results. Provide costallowance pending scope confirmation.

Recommendation:

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

S1 STRUCTURAL

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

FEB-08

APR-08

Cast-in place reinforced concrete foundations walls on reinforced concrete strip footings. Reinforced concrete pedestals onreinforced concrete pad footings supporting HSS columns along corridors at classroom block above.

102mm Reinforced concrete slabs throughout.

Page 5: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 5 of 58

B1010.01 Floor Structural Frame (Building Frame)*

B1010.02 Structural Interior Walls Supporting Floors (or Roof)*

B1010.03 Floor Decks, Slabs, and Toppings*

B1010.05 Mezzanine Construction*

B1010.09 Floor Construction Fireproofing*

B1010.10 Floor Construction Firestopping*

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

Rating

Rating

1980

1980

1980

1980

1980

1980

Installed

Installed

Installed

Installed

Installed

Installed

0

0

0

0

0

0

Design Life

Design Life

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Updated

Updated

Airdrie - R. J. Hawkey Elementary School (B2395A)

152mm concrete block walls on concrete slab with slab thickening at walls to support reinforced concrete stage floor. 204mm concrete block walls supporting mechanical room mezzanine floor

204mm concrete block walls supporting roof around administration, staff work room, stage, locker rooms and eastwashrooms. 204mm concrete block walls forming mudrooms at north end corridors and supporting mechanical room mezzanine floor

Cast-in place 102mm reinforced concrete slab at stage chair storage area Cast-in place 204mm reinforced concrete slab at mechanical room

Metal pan with cast-in place 102mm reinforced concrete slab at stage chair storage area Cast-in place 204mm reinforced concrete slab at mechanical room

Concrete slab on grade and concrete floor at mezzanine

No unprotected openings visible. None Reported

Page 6: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 6 of 58

B1020.01 Roof Structural Frame*

B1020.04 Canopies*

B1020.06 Roof Construction Fireproofing*

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

0

0

0

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Airdrie - R. J. Hawkey Elementary School (B2395A)

Metal roof deck supported on varying depth OWSJ's supported on concrete block or wide flange steel beams and HSScolumns, throughout Metal roof deck on 914mm deep OWSJ's at gymnasium supported on concrete block walls

Recessed doorways at main entrance and mudrooms with metal clad canopy which is an extension of the roof system withsteel angles or OWSJ's for support

One storey building with non-combustible roof construction (not required)

Page 7: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 7 of 58

B2010.01.02.02 Concrete Block: Ext. Wall Skin*

B2010.01.06.03 Metal Siding**

B2010.01.09 Expansion Control: Exterior Wall Skin*

B2010.01.11 Joint Sealers (caulking): Ext. Wall**

4 - Acceptable

4 - Acceptable

4 - Acceptable

2 - Poor

Rating

Rating

Rating

Rating

1980

1995

1980

1980

Installed

Installed

Installed

Installed

75

40

0

20

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Replace Metal Cladding

Replace Joint Sealers

Lifecycle Replacement

Failure Replacement

2035

2008

$171,600

$22,880

Unassigned

High

Expansion joints have no backing rods. Sealers are crackedand missing. Sealers at window frames and sills are crackedand separating

Concern:

Remove sealers add backer rods as necessary and install newelastomeric joint and control joint sealers

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

S2 ENVELOPE

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

FEB-08

102mm concrete block veneer over concrete block structural wall at gymnasium

Prefinished metal cladding supported on wood framing.

Expansion and control joints properly space around perimeter block walls. Joints are failing, refer to B2010.01.11 for event.

Elastomeric joint sealers around windows at flashing transitions and at control joints

Page 8: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 8 of 58

B2010.01.13 Paints (& Stains): Exterior Wall**

B2010.02.03 Masonry Units: Ext. Wall Const.*

B2010.02.05 Wood Framing : Ext. Wall Const.*

B2010.03 Exterior Wall Vapor Retarders, Air Barriers, and Insulation*

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

1980

1980

1980

1980

Installed

Installed

Installed

Installed

15

0

0

0

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Repaint Doors, Block Walls & Railings

Repaint Roof Ladders & Air Intake Louver

Lifecycle Replacement

Repair

2012

2009

$11,440

$3,432

Unassigned

Low

Roof Ladders have peeling and faded paint. Mechanical air-intake has faded paint and no longer blends in with metalcladding

Concern:

Repaint metal louvers and ladders. Coordinate with roofingupgrade to Mechanical room roof

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

FEB-08

Painted exterior metal doors, railings, louvers, concrete block below windows. Upper roof ladders and louvers are inmarginal condition.

Split faced concrete block walls around classrooms and office areas. Painted smooth faced block below windows

38x38 wood strapping to interior face of concrete blocks with 9mm plywood backing and vinyl covered fibreboard finish

38mm batt insulation between wood strapping with poly vapour barrier

Page 9: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 9 of 58

B2010.06 Exterior Louvers, Grilles, and Screens*

B2010.09 Exterior Soffits*

B2020.01.01.02 Aluminum Windows (Glass and Frame)**

B2030.01 Exterior Entrance Doors

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

1980

1980

1980

1980

Installed

Installed

Installed

Installed

0

0

40

30

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Replace Aluminum Windows

Replace Entrance Doors

Lifecycle Replacement

Lifecycle Replacement

2020

2012

$34,320

$6,864

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

Painted metal louvers at mechanical room

Prefinished metal soffits around reclad upper fascia panels. Painted plywood with wood battens at entrance door andmudroom canopies

Dark bronze anodized aluminum windows with double hung vented units and screens

Painted metal doors with vision lites and borrowed sidelight and clerestorey glazing

Page 10: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 10 of 58

B2030.02 Exterior Utility Doors**

B3010.01 Deck Vapor Retarder and Insulation*

B3010.04.01 Built-up Bituminous Roofing (Asphalt & Gravel)**

B3010.04.04 Modified Bituminous Membrane Roofing (SBS)**

4 - Acceptable

4 - Acceptable

3 - Marginal

5 - Good

Rating

Rating

Rating

Rating

1980

1980

1980

2002

Installed

Installed

Installed

Installed

40

0

25

25

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Replace Exterior Utility Doors

Preventative Maintenance

Replace SBS Mebrane Roofing

Lifecycle Replacement

Failure Replacement

Lifecycle Replacement

2020

2009

2027

$16,016

$45,760

$286,000

Unassigned

Medium

Unassigned

Roof is badly blistered and gravel is minimalConcern:

Replace with SBS membrane roofingRecommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Event:

Type

Type

Type

Year

Year

Year

Cost

Cost

Cost

Priority

Priority

Priority

Updated:

Updated:

Updated:

APR-08

FEB-08

APR-08

Painted metal doors in pressed steel frames to playground, at gymnasium exits and at portable connection

Mechanical room has original tar an gravel built-up roof

2-Ply SBS membrane roofing

Page 11: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 11 of 58

B3010.08.02 Metal Gutters and Downspouts**

B3020.02 Other Roofing Openings (Hatch,Vent, etc)*

4 - Acceptable

4 - Acceptable

Rating

Rating

1980

1980

Installed

Installed

30

0

Design Life

Design Life

FEB-08

FEB-08

Updated

Updated

Airdrie - R. J. Hawkey Elementary School (B2395A)

No external gutters or downspouts. All roof drains are connected to building storm drainage system

Plumbing stack vents, exhaust fans, chimney

Page 12: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 12 of 58

C1010.01.03 Unit Masonry Assemblies: Partitions

C1010.01.07 Framed Partitions (Stud) -

C1010.02 Interior Demountable Partitions - *

C1010.03 Interior Operable Folding Panel Partitions - **

C1010.05 Interior Windows - *

C1010.06 Interior Glazed Partitions and Storefronts - *

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

Rating

Rating

1980

2000

1980

1980

2000

2000

Installed

Installed

Installed

Installed

Installed

Installed

0

0

0

30

0

0

Design Life

Design Life

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Updated

Updated

Replace Folding Partition

Lifecycle Replacement 2012 $32,032 Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

S3 INTERIOR

Event:

Type Year Cost Priority

Updated: APR-08

Painted concrete block walls at mudrooms,at main corridor separating classroom block, between classroom and janitorsroom, at washrooms, locker rooms, between stage & administration offices

Counseling Offices at main entrance

Vinyl clad drywall with metal/vinyl battens, typical between classrooms and around corridors in classroom block

Vinyl clad folding partition at stage

Tempered glass in painted pressed steel frame at counseling office. Glass lites in demountable partition system framesbetween librarians room and reading room

Clear anodized glass storefront at administration offices

Page 13: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 13 of 58

C1010.07 Interior Partition Firestopping - *

C1020.01 Interior Swinging Doors (& Hardware) - *

C1020.03 Interior Fire Doors - *

C1030.01 Visual Display Boards - **

C1030.02 Fabricated Compartments(Toilets/Showers) - **

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

Rating

1980

1980

1980

1980

1980

Installed

Installed

Installed

Installed

Installed

0

40

0

20

30

Design Life

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Updated

Replace Tackboards and Chalkboards

Replace Toilet & Shower Compartments

Lifecycle Replacement

Lifecycle Replacement

2012

2012

$45,760

$20,592

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

Corridor wall separating classroom block is a 2hr fire separation and drawings indicate classroom corridor walls have a45min FRR

Painted wood doors in metal frames

Classroom doors have 20min. labels. Corridor doors are labeled 1 1/12hr and have panic hardware and have magnetic hold open devices

Tackboards and a combination of whiteboards and chalkboards throughout

Painted manufactured metal toilet compartments and shower stalls

Page 14: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 14 of 58

C1030.06 Handrails - *

C1030.08 Interior Identifying Devices - *

C1030.12 Storage Shelving - *

C1030.14 Toilet, Bath, and Laundry Accessories - *

C2010 Stair Construction*

C2020.05 Resilient Stair Finishes**

C2030.01 Ramp Construction*

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

Rating

Rating

Rating

1980

1980

1980

1980

1980

1980

1980

Installed

Installed

Installed

Installed

Installed

Installed

Installed

0

0

0

0

100

20

100

Design Life

Design Life

Design Life

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Updated

Updated

Updated

Airdrie - R. J. Hawkey Elementary School (B2395A)

Painted metal rectangular handrails attached to wall and centre floor mounted railing at gym staircase

Plastic lamacoid signs attached to upper door frames or on wood doors. Simple floor plan makes

Metal and wood shelving in storage rooms

Typical wall mounted mirrors, soap dispensers, paper towel dispensers, toilet paper holders in boys & girls washrooms Napkin dispenser in female staff washroom

Cast-in place reinforced concrete stirs to gymnasium

Rubber nosings and risers with VAT treads

Cast-in place reinforced concrete slab

Page 15: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 15 of 58

C2030.02 Ramp Finishes*

C2030.03 Ramp Railings*

C3010.02 Wall Paneling - **

4 - Acceptable

3 - Marginal

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

30

50

30

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Barrier Free Access Upgrade

Replace Vinyl Clad Wall Panels

Barrier Free Access Upgrade

Lifecycle Replacement

2009

2012

$3,432

$68,640

Low

Unassigned

Railings do not conform to graspability requirement andbecause the ramp is at a slope of 1:11 control will be difficultwithout assistance

Concern:

Replace with graspable pipe railingsRecommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

FEB-08

APR-08

Altro-20 walkway slip resistant sheet vinyl

Painted rectangular steel railings mounted to wall

Vinyl clad fibreboard wall panels on exterior wall and on demountable partitions

Page 16: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 16 of 58

C3010.06 Tile Wall Finishes - **

C3010.09 Acoustical Wall Treatment - **

4 - Acceptable

2 - Poor

Rating

Rating

1980

1980

Installed

Installed

40

20

Design Life

Design Life

FEB-08

FEB-08

Updated

Updated

Replace Ceramic Wall Tile

Install Acoustic Panels at Stage/Music Room

Lifecycle Replacement

Failure Replacement

2020

2009

$20,592

$9,152

Unassigned

Medium

No sound absorption in music/stage area to control noiseConcern:

Install sound absorbing panels to improve room acousticsRecommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

FEB-08

102x102mm glazed ceramic tiles between floor mounted urinals and floor to ceiling in shower areas and 50x50mm unglazedtiles behind custodial slop sinks

No acoustic wall treatment

Page 17: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 17 of 58

C3010.11 Interior Wall Painting - *

C3020.01.02 Paint Concrete Floor Finishes - *

4 - Acceptable

2 - Poor

Rating

Rating

1980

1980

Installed

Installed

10

10

Design Life

Design Life

FEB-08

FEB-08

Updated

Updated

Repair

Install Epoxy Floor Finsh

Repair

Failure Replacement

2008

2009

$2,288

$17,160

Medium

High

A few wood doors are chipped. Metal Fire door is rubbing atframe and is rusting at bottom with floor cleaning.

There are stained ceiling Tiles in the Gym storage room. Thereare significant leaks and stains on the floor in the mechanicalroom

Concern:

Concern:

Repair scratches and chips, adjust metal door and repaint(approx. 6 doors)

Install industrial epoxy floor finish with painted yellow

Recommendation:

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

FEB-08

FEB-08

Painted concrete block walls and wood and metal doors.

Unfinished concrete in mechanical room

Page 18: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 18 of 58

C3020.02 Tile Floor Finishes - **

C3020.07 Resilient Flooring - 1980**

4 - Acceptable

3 - Marginal

Rating

Rating

1980

1980

Installed

Installed

50

20

Design Life

Design Life

FEB-08

FEB-08

Updated

Updated

Replace Tile Floor Finish

Replace Original Resilient Flooring

Replace missing Tiles

Lifecycle Replacement

Lifecycle Replacement

Repair

2030

2012

2009

$45,760

$45,760

$5,720

Unassigned

Unassigned

Medium

VAT tiles are starting to pop and are missing in Custodialroom. Tiles are missing at top of stair to mechanical room

Concern:

Remove VAT tiles and install industrial epoxy floor finish inJanitor room and at staircase to mechanical room

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Event:

Type

Type

Type

Year

Year

Year

Cost

Cost

Cost

Priority

Priority

Priority

Updated:

Updated:

Updated:

APR-08

APR-08

FEB-08

102x204mm quarry tile floors and 540x50mm unglazed ceramic tiles in washrooms and janitor rooms

VAT tiles in stage, staff work room, gym storage, locker rooms, corridors, custodial, storage rooms and staircases.

Page 19: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 19 of 58

C3020.07 Resilient Flooring 2000**

C3020.08 Carpet Flooring - **

5 - Good

4 - Acceptable

Rating

Rating

2000

2000

Installed

Installed

20

15

Design Life

Design Life

FEB-08

FEB-08

Updated

Updated

Replace vinyl flooring.

Replace Carpet Flooring

Replace Carpet with Sheet Vinyl

Lifecycle Replacement

Lifecycle Replacement

Failure Replacement

2020

2016

2008

$45,760

$22,880

$7,436

Unassigned

Unassigned

High

Carpet seam has failed and children are pulling at seam.Carpet has also released from substrate

Concern:

Remove damaged carpet (approx 25%) and install marmoleum.Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Event:

Type

Type

Type

Year

Year

Year

Cost

Cost

Cost

Priority

Priority

Priority

Updated:

Updated:

Updated:

APR-08

APR-08

FEB-08

Upgraded marmoleum sheetgoods in classrooms.

Carpet flooring in library, computer room administration offices, staff room and part of one classroom

Page 20: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 20 of 58

C3030.06 Acoustic Ceiling Treatment (Susp.T-Bar) - **

C3030.07 Interior Ceiling Painting - *

C3030.09 Other Ceiling Finishes*

3 - Marginal

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

25

20

60

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Replace 40% of Acoustic Ceiling Tiles

Replace Remaining 60% of Ceiling Tiles

Failure Replacement

Lifecycle Replacement

2009

2012

$40,040

$57,200

Low

Unassigned

Ceiling tiles in administration and some classroom areas areworn and dirty

Concern:

Replace with new ceiling tilesRecommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

FEB-08

APR-08

Acoustic fissured mineral fibre ceiling tiles throughout except in the gymnasium, mechanical room, custodial rooms andwashrooms

Painted drywall ceilings in washrooms and janitor rooms

Linear metal Donn Paraline ceiling system in gymnasium

Page 21: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 21 of 58

D2010.04 Sinks - **

D2010.05 Showers - **

D2010.08 Drinking Fountains / Coolers - **

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

30

30

35

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Replace Sinks

Replace Showers

Replace Drinking Fountains

Lifecycle Replacement

Lifecycle Replacement

Lifecycle Replacement

2012

2012

2015

$10,850

$22,880

$7,415

Unassigned

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

S4 MECHANICAL

Event:

Event:

Event:

Type

Type

Type

Year

Year

Year

Cost

Cost

Cost

Priority

Priority

Priority

Updated:

Updated:

Updated:

APR-08

APR-08

APR-08

Stainless steel counter top.

Combination of gang showers and individual stall showers in the changer rooms. Change rooms are being used as storagespace. Single concrete shower in Gym Instructor's office, non-barrier free design.

Vitreous china, wall mount.

Page 22: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 22 of 58

D2010.10 Washroom Fixtures (WC, Lav, Urnl) - **

D2020.01.01 Pipes and Tubes: Domestic Water - *

D2020.01.02 Valves: Domestic Water - **

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

30

0

40

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Replace Washroom Fixtures

Replace Valves

Lifecycle Replacement

Lifecycle Replacement

2012

2020

$57,785

$22,502

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

General washrooms: Floor mounted, vitreous china, flush valve water closets. Washout stall, vitreous china, flush valve urinals. Counter top, vitreous china lavatories. Staff Washrooms: Floor mounted, vitreous china, flush tank water closets. Wall mounted, vitreous china lavatories.

Type 'L' copper pipe and fittings.

Bronze body valves.

Page 23: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 23 of 58

D2020.01.03 Piping Specialties (Backflow Preventors) - **

D2020.01.08 Hose Bibbs*

D2020.02.02 Plumbing Pumps: Domestic Water - **

2 - Poor

4 - Acceptable

5 - Good

Rating

Rating

Rating

1980

1980

2005

Installed

Installed

Installed

20

0

20

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Replace Boiler Feed Backflow Preventors

Water Service Backflow Preventer

Replace Plumbing Pump

Lifecycle Replacement

Code Upgrade

Lifecycle Replacement

2012

2008

2025

$2,860

$6,864

$3,235

Unassigned

High

Unassigned

No backflow prevention on main water service.Concern:

Install a double check valve assembly.Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Event:

Type

Type

Type

Year

Year

Year

Cost

Cost

Cost

Priority

Priority

Priority

Updated:

Updated:

Updated:

APR-08

FEB-08

APR-08

No backflow prevention installed on the domestic water service. Reduced pressure back flow preventer for boiler feed.

Exterior, non-freeze.

In-line, bronze body.

Page 24: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 24 of 58

D2020.02.06 Domestic Water Heaters - **

D2020.03 Water Supply Insulation: Domestic - *

D2030.01 Waste and Vent Piping - *

D2030.02.04 Floor Drains*

D2040.01 Rain Water Drainage Piping Systems - *

D2040.02.04 Roof Drains - *

5 - Good

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

Rating

Rating

2005

1980

1980

1980

1980

1980

Installed

Installed

Installed

Installed

Installed

Installed

20

0

0

50

0

40

Design Life

Design Life

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Updated

Updated

Replace Domestic Water Heater

Lifecycle Replacement 2025 $6,818 Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Updated: APR-08

Single A.O. Smith model BT 65-100, gas fired, tank type.

25mm fiberglass.

Cast iron and DWV copper piping and fittings.

Cast iron body, nickel bronze grate.

Cast iron piping and fittings.

Cast iron body, aluminum dome.

246Capacity Size

litreCapacity Unit

Page 25: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 25 of 58

D3010.02 Gas Supply Systems - *

D3020.02.01 Heating Boilers and Accessories: H.W. - **

D3020.02.02 Chimneys (&Comb. Air): H.W. Boiler - **

D3020.02.03 Water Treatment: H. W. Boiler - *

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

1980

1980

1980

1980

Installed

Installed

Installed

Installed

60

35

30

0

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Replace Heating Boilers

ReplaceChimneys &Comb. Air

Lifecycle Replacement

Lifecycle Replacement

2015

2012

$82,583

$17,705

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

Black malleable piping and fittings.

Two Superhot AAE-1560, steel tube boilers.

Common combustion air duct for mechanical room. Individual boiler chimneys.

Chemical pot feeder and micron filter.

Page 26: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 26 of 58

D3040.01.01 Air Handling Units: Air Distribution - **

D3040.01.04 Ducts: Air Distribution - *

D3040.01.07 Air Outlets & Inlets:Air Distribution - *

D3040.03.01 Hot Water Distribution Systems - **

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

1980

1980

1980

1980

Installed

Installed

Installed

Installed

30

0

0

40

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Replace Air Handling Units

Replace Hot Water Distribution System

Lifecycle Replacement

Lifecycle Replacement

2012

2020

$262,686

$278,636

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

Unit HV-1, core school, Trane Torrivent T25, 8069 L/s, in mechanical room. Unit Hv-2 Gymnasium, Trane Climate Changer 17, 4909 L/s, in mechanical room.

Conventional low velocity ductwork.

Conventional grilles and diffusers.

Welded and threaded black steel piping and fittings.

Page 27: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 27 of 58

D3040.04.01 Fans: Exhaust - **

D3040.04.03 Ducts: Exhaust - *

D3040.04.05 Air Outlets and Inlets: Exhaust - *

D3050.02 Air Coils - **

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

1980

1980

1980

1980

Installed

Installed

Installed

Installed

30

0

0

30

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Replace Fans

Replace Reheat Coils

Lifecycle Replacement

Lifecycle Replacement

2012

2012

$22,880

$11,440

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

Multiple ceiling mounted and roof top exhaust fans, general exhaust.

Conventional low velocity ductwork.

Conventional grilles.

Duct mounted, copper tube, aluminum fin reheat coils.

VariesCapacity Size

N/ACapacity Unit

Page 28: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 28 of 58

D3050.03 Humidifiers - **

D3050.05.02 Fan Coil Units - **

D3050.05.03 Finned Tube Radiation - **

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

25

30

40

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Replace Humidifiers

Replace Fan Coil Units

Replace Finned Tube Radiation

Lifecycle Replacement

Lifecycle Replacement

Lifecycle Replacement

2012

2012

2020

$9,857

$66,161

$132,799

Unassigned

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Event:

Type

Type

Type

Year

Year

Year

Cost

Cost

Cost

Priority

Priority

Priority

Updated:

Updated:

Updated:

APR-08

APR-08

APR-08

Units have been disabled and drained.

Ceiling recessed, flush mounted.

Copper tube, aluminum fin c/w cabinet.

VariesCapacity Size

N/ACapacity Unit

Page 29: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 29 of 58

D3060.02.02 Pneumatic Controls**

D4010 Sprinklers: Fire Protection - *

D4030.01 Fire Extinguisher, Cabinets and Accessories - *

4 - Acceptable

4 - Acceptable

3 - Marginal

Rating

Rating

Rating

1980

1993

1980

Installed

Installed

Installed

40

60

30

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Replace controls

Code Upgrade

Lifecycle Replacement

Code Upgrade

2020

2008

$57,200

$4,004

Unassigned

Unassigned

Type 'A' only.Concern:

Replace with 4.5 kg type 'ABC' extinguishers.Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

Honeywell pneumatics, controls compressor and air dryer located in mechanical room.

A single sprinkler head connected to domestic water system. For portable exit requirements.

Primarily type 'A' pressurized water extinguishers with a few type 'ABC' dry chemical wall mounted extinguishers.

VariesCapacity Size

N/ACapacity Unit

Page 30: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 30 of 58

D5010.03 Main Electrical Switchboards (Main Distribution) - **

D5010.05 Electrical Branch Circuit Panelboards (Secondary Distribution) - **

D5010.07.02 Motor Starters and Accessories - **

5 - Good

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

40

30

30

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Replace Main Electrical Switchboards (MainDistribution)

Replace Electrical Branch Circuit Panelboards(Secondary Distribution)

Replace Motor Starters and Accessories

Lifecycle Replacement

Lifecycle Replacement

Lifecycle Replacement

2020

2012

2012

$60,953

$30,670

$5,289

Unassigned

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

S5 ELECTRICAL

Event:

Event:

Event:

Type

Type

Type

Year

Year

Year

Cost

Cost

Cost

Priority

Priority

Priority

Updated:

Updated:

Updated:

APR-08

APR-08

APR-08

FPE 600A, 120/208V, 3-phase, 4-wire ~40% space Peak load=80kVA, so plenty of capacity.

Typical FPE 42 cct (with some 30), 225A, avg 15% space. Parking panels controlled.

Separate starters (AB) fed off of splitter. Tycor Filter on splitter.

600Capacity Size

ampsCapacity Unit

Page 31: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 31 of 58

D5020.01 Electrical Branch Wiring - *

D5020.02.01 Lighting Accessories (Lighting Controls) - *

D5020.02.02.01 Interior Incandescent Fixtures - *

D5020.02.02.02 Interior Fluorescent Fixtures - **

D5020.02.02.03 Interior Metal Halide Fixture - *

4 - Acceptable

4 - Acceptable

4 - Acceptable

5 - Good

4 - Acceptable

Rating

Rating

Rating

Rating

Rating

1980

1980

1980

2000

1980

Installed

Installed

Installed

Installed

Installed

0

0

30

30

0

Design Life

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Updated

Replace Interior Fluorescent Fixtures

Lifecycle Replacement 2030 $182,367 Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Updated: APR-08

Wire in conduit. Some newer runs armoured cable.

Line voltage switching throughout. Occupancy sensors in some locations as retrofits. Classrooms all changed to 1 level of switching.

In infirmary - recessed downlight.

Upgraded to T8 lamps, electronic ballasts. Recessed lensed 1x4s in corridor, stage. Recessed lensed 2x4s in classrooms, admin. Recessed parabolics in Library, computer room.

Fixtures recessed into gym ceiling.

Page 32: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 32 of 58

D5020.02.03.02 Emergency Lighting Battery Packs - **

D5020.02.03.03 Exit Signs - *

D5020.02.05 Special Purpose Lighting - *

D5020.03.01.01 Exterior Incandescent Fixtures*

D5020.03.01.04 Exterior H.P. Sodium Fixtures - *

D5020.03.02 Lighting Accessories: Exterior (Lighting Controls) - *

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

Rating

Rating

1980

2000

1980

2000

1980

1996

Installed

Installed

Installed

Installed

Installed

Installed

20

0

0

30

0

0

Design Life

Design Life

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Updated

Updated

Replace Emergency Lighting Battery Packs

Lifecycle Replacement 2012 $12,992 Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Updated: APR-08

Battery packs and heads have been replaced as they have failed.

Upgraded with LED lamping. Several fixtures not illuminated - require maintenance.

Theatrical lighting in gym.

Some halogen fixtures with photocell/motion sensors at back of building.

Wall packs around building perimeter. Recessed downlights at entrances.

Photocell and Intermatic time switch.

Page 33: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 33 of 58

D5030.01 Detection and Fire Alarm - **

D5030.02.02 Intrusion Detection - **

D5030.03 Clock and Program Systems - *

D5030.04.01 Telephone Systems - *

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

1991

1995

1980

1980

Installed

Installed

Installed

Installed

25

25

25

25

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Replace Detection and Fire Alarm

Replace Intrusion Detection

Lifecycle Replacement

Lifecycle Replacement

2016

2020

$56,908

$33,476

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

Edwards ESA2000. Pull stations at exits, heat detectors in storage/cooking areas, smoke detectors at smoke doors. Bell/strobes throughout.

Magnum Alert, keypad for disarming. Motion sensors throughout. Monitored off-hours. Cabling not in conduit.

Rauland time clock - for class change signal only.

Meridian system.

Page 34: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 34 of 58

D5030.04.05 Local Area Network Systems - *

D5030.05 Public Address and Music Systems - **

D5030.06 Television Systems - *

3 - Marginal

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

2000

Installed

Installed

Installed

0

20

0

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Maintain Local Area Network Systems

Replace Public Address and Music Systems

Preventative Maintenance

Lifecycle Replacement

2008

2012

$1,716

$13,768

Unassigned

Unassigned

Data equipment on shelves/stacked loose. Potential fordamage to equipment due to fall or inadequate ventilation.

Concern:

Provide full-size data rack for data equipment.Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

Data cabling throughout, run free-air. Cat 5 & 5e. Rack space insufficient - switches on shelves, stacked loose.

Peavey UMA 75TII amp/mixer. Cassette, CD, radio, class change signals. Has been upgraded with phone tie-in for paging/intercom function. Original wall-mount speakers/intercom still remain though intercom function no longer used.

CATV drops run to each classroom.

Page 35: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 35 of 58

E1020.02 Library Equipment - *

E1020.03 Theater and Stage Equipment - *

E1090 Other Equipment

E1090.03 Food Service Equipment*

E1090.04 Residential Equipment - *

4 - Acceptable

4 - Acceptable

3 - Marginal

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

Rating

1980

1980

1990

2000

1980

Installed

Installed

Installed

Installed

Installed

0

0

0

25

0

Design Life

Design Life

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Updated

Updated

Relocate Art Kiln

Code Repair 2008 $17,160 Medium

Staff require access to mechanical room to use kilnConcern:

Relocate art kiln and install proper ventilation to control heat(consider upgrading 1020A which appears to be used forstorage)

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

S6 EQUIPMENT, FURNISHINGS AND SPECIAL CONSTRUCTION

Event:

Type Year Cost Priority

Updated: FEB-08

Typical librarians desk and mobile book drop

Procenium stage curtain and tracks for backstage curtains

Art Kiln located in mechanical room

Upright cooler with milk in staff work room

Refrigerator, stove, two microwaves and dishwasher located in staff room. microwave in PE office, old microwave, stove andRefrigerator in 1020A. Refrigerator in staff work room

Page 36: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 36 of 58

E1090.07 Athletic, Recreational, and Therapeutic Equipment - *

E2010.02 Fixed Casework - **

E2010.03.01 Blinds - **

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

0

35

30

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Replace Fixed Casework

Replace Blinds

Lifecycle Replacement

Lifecycle Replacement

2015

2012

$200,200

$5,720

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

Fold down ceiling mounted basketball hoop in front of stage, side swing at opposite end and wall mounted hoops onsidewalls in gym. Typical volleyball and badminton courts with mats, bats and racks in gym storage room

Painted wood cabinets with sinks located in 5 classrooms, built in lower cabinets with upper cabinets in staff work roomand administration are, new birch cabinets in PE office, laminate wood vanities in washrooms. New stained birch uppercabinets installed in some classroom and staff room

Plastic Vertical blinds throughout the school

Page 37: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 37 of 58

F1010.02.04 Portable and Mobile Buildings P039*

4 - AcceptableRating

1981Installed

30Design Life

FEB-08Updated

Replace Damaged Vent Caps, Gumbox & Study

1) Vent Caps are dented and crushed due to vandalism 2) Gum Box is drying & cracking at conduit evident 3) Roof drains to asphalt walk. Walkway ices over. Crawl spaceis buried into grade with no access

Concern:

1) Replace 4 Vent caps 2) Reseal gumbox 3) Remove part of concrete board panel and inspect crawlspace for moisture & mould growth. Measure moisture reading

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Existing Portable Retrofitted and moved to site in 1993 Architectural: Floor: sheet vinyl on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated 38x235mm woodjoists with 9mm plywood bottom sheathing Lower Wall: Prefinished metal cladding on building paper on 9mm plywood sheathing over 16mm Type 'X' GWB each side ofinsulated wood studs with 6 mil poly vapour barrier on classroom side Upper Wall: same as lower except Bold Rib metal cladding is attached to wall on wood nailers to provide build-out Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Sink: birch cabinet with sink unit Visual Display Boards: Tackboards and blackboards Condition: Acceptable Recommendation: Make minor repairs Mechanical: Shares a gas fired heat/cool Lennox GCS16-953 rooftop unit with P040. Distribution ductwork is provided to bothclassrooms and a 7-day programmable Honeywell thermostat is located in P039. There are some comfort control issuesdue to a single point of control between two classrooms. Roof drains connected to individual heat traced rainwater leaders that terminate through the exterior wall and splash tograde. Stainless steel counter top sink complete with plumbing services. Domestic water lines are run in the ceiling of the linkcorridor for the full length of the corridor. Gas lines are run on the roof to the units. Condition: Acceptable Recommendation: None Electrical: Recessed 2x4s, T8s, 1 level switching, upgraded ~2000 3D typical per classroom. PA speaker each. Shares a panel with P040 - FPE 125A, 120/208V, 1-phase, 3-wire, 16 circuit, 6 spaces Condition: Acceptable Recommendation: None

Page 38: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 38 of 58

Repair 2008 $2,288 High

in crawl space

Airdrie - R. J. Hawkey Elementary School (B2395A)

Type Year Cost Priority

Updated: FEB-08

Page 39: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 39 of 58

F1010.02.04 Portable and Mobile Buildings P040*

4 - AcceptableRating

1981Installed

30Design Life

FEB-08Updated

Replace Damaged Vent Caps, Gumbox & Study

1) Vent Caps are dented and crushed due to vandalism 2) Gum Box is drying & cracking at conduit evident 3) Roof drains to asphalt walk. Walkway ices over. Crawl spaceis buried into grade with no access

Concern:

1) Replace 4 Vent caps 2) Reseal gumbox 3) Remove part of concrete board panel and inspect crawlspace for moisture & mould growth. Measure moisture reading

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Existing Portable Retrofitted and moved to site in 1993 Architectural: Floor: sheet vinyl on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated 38x235mm woodjoists with 9mm plywood bottom sheathing Lower Wall: Prefinished metal cladding on building paper on 9mm plywood sheathing over 16mm Type 'X' GWB each side ofinsulated wood studs with 6 mil poly vapour barrier on classroom side Upper Wall: same as lower except Bold Rib metal cladding is attached to wall on wood nailers to provide build-out Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Sink: birch cabinet with sink unit Visual Display Boards: Tackboards and blackboards Condition: Acceptable Recommendation: Make minor repairs Mechanical: Shares a gas fired heat/cool Lennox GCS16-953 rooftop unit with P040. Distribution ductwork is provided to bothclassrooms and a 7-day programmable Honeywell thermostat is located in P039. There are some comfort control issuesdue to a single point of control between two classrooms. Roof drains connected to individual heat traced rainwater leaders that terminate through the exterior wall and splash tograde. Stainless steel counter top sink complete with plumbing services. Domestic water lines are run in the ceiling of the linkcorridor for the full length of the corridor. Gas lines are run on the roof to the units. Condition: Acceptable Recommendation: None Electrical: Recessed 2x4s, T8s, 1 level switching, upgraded ~2000 3D typical per classroom. PA speaker each. Shares a panel with P039 - FPE 125A, 120/208V, 1-phase, 3-wire, 16 circuit, 6 spaces Condition: Acceptable Recommendation: None

Page 40: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 40 of 58

Repair 2008 $2,288 High

in crawl space

Airdrie - R. J. Hawkey Elementary School (B2395A)

Type Year Cost Priority

Updated: FEB-08

Page 41: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 41 of 58

F1010.02.04 Portable and Mobile Buildings P041*

4 - AcceptableRating

1993Installed

30Design Life

FEB-08Updated

Replace Damaged Vent Caps, Gumbox & Study

Repair 2008 $2,288 High

1) Vent Caps are dented and crushed due to vandalism 2) Gum Box is drying & cracking at conduit evident 3) Roof drains to asphalt walk. Walkway ices over. Crawl spaceis buried into grade with no access

Concern:

1) Replace 4 Vent caps 2) Reseal gumbox 3) Remove part of concrete board panel and inspect crawlspace for moisture & mould growth. Measure moisture readingin crawl space

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Architectural: Floor: sheet vinyl on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated 38x235mm woodjoists with 9mm plywood bottom sheathing Lower Wall: Prefinished metal cladding on building paper on 9mm plywood sheathing over 16mm Type 'X' GWB each side ofinsulated wood studs with 6 mil poly vapour barrier on classroom side Upper Wall: same as lower except Bold Rib metal cladding is attached to wall on wood nailers to provide build-out Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Sink: birch cabinet with sink unit Visual Display Boards: Tackboards and blackboards Condition: Acceptable Recommendation: Make minor repairs Mechanical: Gas fired heat/cool Trane GRNC-015/TTA036 rooftop unit. Distribution ductwork in ceiling and a 7-day programmableHoneywell thermostat. Roof drains connected to individual heat traced rainwater leaders that terminate through the exterior wall and splash tograde. Stainless steel counter top sink complete with plumbing services. Domestic water lines are run in the ceiling of the linkcorridor for the full length of the corridor. Gas lines are run on the roof to the units. Condition: Acceptable Recommendation: None Electrical: Recessed, 2x4s, T8s, 1 level switching, upgraded ~2000 3D typical per classroom. PA speaker each. fed from panels in room 1031 - FPE 120/208V 3-phase, 4-wire with several spaces

Page 42: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 42 of 58

Airdrie - R. J. Hawkey Elementary School (B2395A)

Updated: FEB-08

Page 43: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 43 of 58

F1010.02.04 Portable and Mobile Buildings P042*

4 - AcceptableRating

1993Installed

30Design Life

FEB-08Updated

Replace Damaged Vent Caps, Gumbox & Study

Repair 2008 $2,288 High

1) Vent Caps are dented and crushed due to vandalism 2) Gum Box is drying & cracking at conduit evident 3) Roof drains to asphalt walk. Walkway ices over. Crawl spaceis buried into grade with no access

Concern:

1) Replace 4 Vent caps 2) Reseal gumbox 3) Remove part of concrete board panel and inspect crawlspace for moisture & mould growth. Measure moisture readingin crawl space

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Architectural: Floor: sheet vinyl and carpet on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated38x235mm wood joists with 9mm plywood bottom sheathing Lower Wall: Prefinished metal cladding on building paper on 9mm plywood sheathing over 16mm Type 'X' GWB each side ofinsulated wood studs with 6 mil poly vapour barrier on classroom side Upper Wall: same as lower except Bold Rib metal cladding is attached to wall on wood nailers to provide build-out Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Sink: birch cabinet with sink unit Visual Display Boards: Tackboards and blackboards Condition: Acceptable Recommendation: Make minor repairs Mechanical: Gas fired heat/cool Trane GRNC-015/TTA036 rooftop unit. Distribution ductwork in ceiling and a 7-day programmableHoneywell thermostat. Roof drains connected to individual heat traced rainwater leaders that terminate through the exterior wall and splash tograde. Stainless steel counter top sink complete with plumbing services. Domestic water lines are run in the ceiling of the linkcorridor for the full length of the corridor. Gas lines are run on the roof to the units. Condition: Acceptable Recommendation: None Electrical: Recessed, 2x4s, T8s, 1 level switching, upgraded ~2000 3D typical per classroom. PA speaker each. fed from panels in room 1031 - FPE 120/208V 3-phase, 4-wire with several spaces

Page 44: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 44 of 58

Airdrie - R. J. Hawkey Elementary School (B2395A)

Updated: FEB-08

Page 45: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 45 of 58

F1010.02.04 Portable and Mobile Buildings P043*

4 - AcceptableRating

1993Installed

30Design Life

FEB-08Updated

Replace Damaged Vent Caps, Gumbox & Study

Repair 2008 $2,288 High

1) Vent Caps are dented and crushed due to vandalism 2) Gum Box is drying & cracking at conduit evident 3) Roof drains to asphalt walk. Walkway ices over. Crawl spaceis buried into grade with no access

Concern:

1) Replace 4 Vent caps 2) Reseal gumbox 3) Remove part of concrete board panel and inspect crawlspace for moisture & mould growth. Measure moisture readingin crawl space

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Updated: FEB-08

Architectural: Floor: sheet vinyl and carpet on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated38x235mm wood joists with 9mm plywood bottom sheathing Lower Wall: Prefinished metal cladding on building paper on 9mm plywood sheathing over 16mm Type 'X' GWB each side ofinsulated wood studs with 6 mil poly vapour barrier on classroom side Upper Wall: same as lower except Bold Rib metal cladding is attached to wall on wood nailers to provide build-out Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Visual Display Boards: Tackboards and blackboards Condition: Acceptable Recommendation: Make minor repairs Mechanical: Gas fired heat/cool Manufactured Air PAC rooftop unit. Distribution ductwork in ceiling and a 7-day programmableHoneywell thermostat. Roof drains connected to individual heat traced rainwater leaders that terminate through the exterior wall and splash tograde. Stainless steel counter top sink complete with plumbing services. Domestic water lines are run in the ceiling of the linkcorridor for the full length of the corridor. Gas lines are run on the roof to the units. Condition: Acceptable Recommendation: None Electrical: Recessed, 2x4s, T8s, 1 level switching, upgraded ~2000 3D typical per classroom. PA speaker each. fed from panels in room 1031 - FPE 120/208V 3-phase, 4-wire with several spaces

Page 46: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 46 of 58

F1010.02.04 Portable and Mobile Buildings P044*

4 - AcceptableRating

1993Installed

30Design Life

FEB-08Updated

Replace Damaged Vent Caps, Gumbox & Study

Repair 2008 $2,288 High

1) Vent Caps are dented and crushed due to vandalism 2) Gum Box is drying & cracking at conduit evident 3) Roof drains to asphalt drive way. Crawl space is buried intograde with no access

Concern:

1) Replace 4 Vent caps 2) Reseal gumbox 3) Remove part of concrete board panel and inspect crawlspace for moisture & mould growth. Measure moisture readingin crawl space

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Architectural: Floor: sheet vinyl and carpet on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated38x235mm wood joists with 9mm plywood bottom sheathing Lower Wall: Prefinished metal cladding on building paper on 9mm plywood sheathing over 16mm Type 'X' GWB each side ofinsulated wood studs with 6 mil poly vapour barrier on classroom side Upper Wall: same as lower except Bold Rib metal cladding is attached to wall on wood nailers to provide build-out Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Visual Display Boards: Tackboards and blackboards Condition: Acceptable Recommendation: Make minor repairs Mechanical: Gas fired heat/cool Manufactured Air PAC rooftop unit. Distribution ductwork in ceiling and a 7-day programmableHoneywell thermostat. Roof drains connected to individual heat traced rainwater leaders that terminate through the exterior wall and splash tograde. Stainless steel counter top sink complete with plumbing services. Domestic water lines are run in the ceiling of the linkcorridor for the full length of the corridor. Gas lines are run on the roof to the units. Condition: Acceptable Recommendation: None Electrical: Recessed, 2x4s, T8s, 1 level switching, upgraded ~2000 3D typical per classroom. PA speaker each. fed from panels in room 1031 - FPE 120/208V 3-phase, 4-wire with several spaces

Page 47: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 47 of 58

Airdrie - R. J. Hawkey Elementary School (B2395A)

Updated: FEB-08

Page 48: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 48 of 58

F1010.02.04 Portable and Mobile Buildings P045*

4 - AcceptableRating

1981Installed

30Design Life

FEB-08Updated

Replace Vent Caps, Repair Furnace Room & Study

Repair 2008 $3,432 High

1) Vent Caps are dented and crushed due to vandalism 2) Roof drains to asphalt driveway. Crawl space is buried intograde with no access 3) Furnace room floors are dirty and show leaks

Concern:

1) Replace 4 Vent caps 2) Reseal gumbox 3) Remove part of concrete board panel and inspect crawlspace for moisture & mould growth. Measure moisture readingin crawl space 4) Repair leaks at furnace, patch holes & clean floors

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Architectural: Floor: sheet vinyl and carpet on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated38x235mm wood joists with 9mm plywood bottom sheathing Lower Wall: Prefinished metal cladding on building paper on 9mm plywood sheathing over 16mm Type 'X' GWB each side ofinsulated wood studs with 6 mil poly vapour barrier on classroom side Upper Wall: same as lower except Bold Rib metal cladding is attached to wall on wood nailers to provide build-out Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Visual Display Boards: Tackboards and blackboards Condition: Acceptable Recommendation: Make minor repairs Mechanical: Gas fired counter flow Lennox model G8R-10-1 in indoor closet with wall mounted distribution ductwork in ceiling and a 7-day programmable Honeywell thermostat. Individual wall mounted air conditioning units. Roof drains connected to individual heat traced rainwater leaders that terminate through the floor and through the skirtingand splash to grade. Stainless steel counter top sink complete with plumbing services. Domestic water lines are run in the ceiling of the linkcorridor for the full length of the corridor. Gas lines are run on the roof to the units. Condition: Acceptable (furnaces unable to keep classrooms comfortable during cold weather) Recommendation: None Electrical: Recessed, 2x4s, T8s, 1 level switching, upgraded ~2000 3D typical per classroom. PA speaker each. Has its own panel - FPE 12 cct, 120/208V, 3-phase, 4-wire, ~5 spaces each.

Page 49: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 49 of 58

Airdrie - R. J. Hawkey Elementary School (B2395A)

Updated: FEB-08

Page 50: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 50 of 58

F1010.02.04 Portable and Mobile Buildings P046*

4 - AcceptableRating

1981Installed

30Design Life

FEB-08Updated

Replace Vent Caps, Repair Furnace Room & Study

Repair 2008 $3,432 High

1) Vent Caps are dented and crushed due to vandalism 2) Roof drains to asphalt driveway. Crawl space is buried intograde with no access 3) Furnace room floors are dirty and show leaks

Concern:

1) Replace 4 Vent caps 2) Reseal gumbox 3) Remove part of concrete board panel and inspect crawlspace for moisture & mould growth. Measure moisture readingin crawl space 4) Repair leaks at furnace, patch holes & clean floors

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Architectural: Floor: sheet vinyl and carpet on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated38x235mm wood joists with 9mm plywood bottom sheathing Lower Wall: Prefinished metal cladding on building paper on 9mm plywood sheathing over 16mm Type 'X' GWB each side ofinsulated wood studs with 6 mil poly vapour barrier on classroom side Upper Wall: same as lower except Bold Rib metal cladding is attached to wall on wood nailers to provide build-out Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Visual Display Boards: Tackboards and blackboards Condition: Acceptable Recommendation: Make minor repairs Mechanical: Gas fired counter flow Lennox model G8R-10-1 in indoor closet with wall mounted distribution ductwork in ceiling and a 7-day programmable Honeywell thermostat. Individual wall mounted air conditioning units. Roof drains connected to individual heat traced rainwater leaders that terminate through the floor and through the skirtingand splash to grade. Stainless steel counter top sink complete with plumbing services. Domestic water lines are run in the ceiling of the linkcorridor for the full length of the corridor. Gas lines are run on the roof to the units. Condition: Acceptable (furnaces unable to keep classrooms comfortable during cold weather) Recommendation: None Electrical: Recessed, 2x4s, T8s, 1 level switching, upgraded ~2000 3D typical per classroom. PA speaker each. Has its own panel - FPE 12 cct, 120/208V, 3-phase, 4-wire, ~5 spaces each.

Page 51: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 51 of 58

Airdrie - R. J. Hawkey Elementary School (B2395A)

Updated: FEB-08

Page 52: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 52 of 58

F1010.02.04 Portable and Mobile Buildings P047*

4 - AcceptableRating

1981Installed

30Design Life

FEB-08Updated

Replace Vent Caps, Repair Furnace Room & Study

Repair 2008 $3,432 High

1) Vent Caps are dented and crushed due to vandalism 2) Roof drains to asphalt driveway. Crawl space is buried intograde with no access 3) Furnace room floors are dirty and show leaks

Concern:

1) Replace 4 Vent caps 2) Reseal gumbox 3) Remove part of concrete board panel and inspect crawlspace for moisture & mould growth. Measure moisture readingin crawl space 4) Repair leaks at furnace, patch holes & clean floors

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Architectural: Floor: sheet vinyl and carpet on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated38x235mm wood joists with 9mm plywood bottom sheathing Lower Wall: Prefinished metal cladding on building paper on 9mm plywood sheathing over 16mm Type 'X' GWB each side ofinsulated wood studs with 6 mil poly vapour barrier on classroom side Upper Wall: same as lower except Bold Rib metal cladding is attached to wall on wood nailers to provide build-out Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Visual Display Boards: Tackboards and blackboards Condition: Acceptable Recommendation: Make minor repairs Mechanical: Gas fired counter flow Lennox model G8R-10-1 in indoor closet with wall mounted distribution ductwork in ceiling and a 7-day programmable Honeywell thermostat. Individual wall mounted air conditioning units. Roof drains connected to individual heat traced rainwater leaders that terminate through the floor and through the skirtingand splash to grade. Stainless steel counter top sink complete with plumbing services. Domestic water lines are run in the ceiling of the linkcorridor for the full length of the corridor. Gas lines are run on the roof to the units. Condition: Acceptable (furnaces unable to keep classrooms comfortable during cold weather) Recommendation: None Electrical: Recessed, 2x4s, T8s, 1 level switching, upgraded ~2000 3D typical per classroom. PA speaker each. Has its own panel - FPE 12 cct, 120/208V, 3-phase, 4-wire, ~5 spaces each.

Page 53: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 53 of 58

Airdrie - R. J. Hawkey Elementary School (B2395A)

Updated: FEB-08

Page 54: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 54 of 58

F1010.02.04 Portable and Mobile Buildings P048 *

4 - AcceptableRating

1981Installed

0Design Life

FEB-08Updated

Replace Vent Caps, Repair Furnace Room & Study

Repair 2008 $2,288 High

1) Vent Caps are dented and crushed due to vandalism 2) Roof drains to asphalt driveway. Crawl space is buried intograde with no access 4) Furnace room floors are dirty and show leaks

Concern:

1) Replace 4 Vent caps 2) Reseal gumbox 3) Remove part of concrete board panel and inspect crawlspace for moisture & mould growth. Measure moisture readingin crawl space 4) Repair leaks at furnace, patch holes & clean floors

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type Year Cost Priority

Architectural: Floor: sheet vinyl and carpet on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated38x235mm wood joists with 9mm plywood bottom sheathing Lower Wall: Prefinished metal cladding on building paper on 9mm plywood sheathing over 16mm Type 'X' GWB each side ofinsulated wood studs with 6 mil poly vapour barrier on classroom side Upper Wall: same as lower except Bold Rib metal cladding is attached to wall on wood nailers to provide build-out Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Visual Display Boards: Tackboards and blackboards Condition: Acceptable Recommendation: Make minor repairs Mechanical: Gas fired counter flow Lennox model G8R-10-1 in indoor closet with wall mounted distribution ductwork in ceiling and a 7-day programmable Honeywell thermostat. Individual wall mounted air conditioning units. Roof drains connected to individual heat traced rainwater leaders that terminate through the floor and through the skirtingand splash to grade. Stainless steel counter top sink complete with plumbing services. Domestic water lines are run in the ceiling of the linkcorridor for the full length of the corridor. Gas lines are run on the roof to the units. Condition: Acceptable (furnaces unable to keep classrooms comfortable during cold weather) Recommendation: None Electrical: Recessed, 2x4s, T8s, 1 level switching, upgraded ~2000 3D typical per classroom. PA speaker each. Has its own panel - FPE 12 cct, 120/208V, 3-phase, 4-wire, ~5 spaces each.

Page 55: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 55 of 58

Airdrie - R. J. Hawkey Elementary School (B2395A)

Updated: FEB-08

Page 56: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 56 of 58

F1010.03 Other Special Structures*

4 - AcceptableRating

1993Installed

0Design Life

FEB-08Updated

Make repairs

1) Condensation in glass lite. 2) Toilet out of order 3) Stains in ceiling tile due to leaks in fan coil drip pans 4) access hatch to roof has been removed and plywood coverat roof has been installed

Concern:

1) Replace glass lite and real all joints 2) Determine cause of toilet failure & repair 3) Adjust Fan Coil drip pans so that condensation does notdamage ceiling tiles & replace ceiling tiles 4) Fill roof void with insulation, vapour barrier and drywall tocomplete fire separation

Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

273 sq. M. Portable Connecting Link Architectural: Floor: VCT tiles and sheet vinyl on cast-in place slab on grade with slab thickening at edge of existing building and gradebeam at edge of portables. The floor at the corridor and ramp connecting the upper and lower portables is constructed withsheet vinyl on 9mm underlay over 6 Mil poly on 16mm T&G plywood subfloor supported on insulated 38x235mm wood joistswith 9mm plywood bottom sheathing Wall: 16mm Type 'X' GWB each side of insulated wood studs with 6 mil poly vapour barrier on corridor side adjacent toexisting building (note: the corridor uses the existing portables as the other wall finish) Ceiling: Acoustic mineral fibre ceiling tiles in a prefinished metal 'T' bar grid system with painted drywall bulkheads at twoskylight conditions Roof: Built-up gravel roof on 16mm T&G plywood sheathing on sloped framing supported on 328x235 roof joists filled withinsulation with 6 Mil poly vapour barrier underneath with 9mm plywood sheathing and 16mm Type 'X' bottom finish Skylights: 2 - 1200x3050mm clear anodized aluminum framed pyramidal skylights with dual glazed sealed units Ramp: slab on grade full width of corridor with non-slip sheet vinyl and painted metal pipe rails each side Washroom: Vanity with sink, toilet with grab bars, mirror, soap dispenser, paper towel dispenser, soap dispenser,fabricated toilet partition and cot Mechanical: Roof drains are tied into portable roof drains Handicapped washroom installed and tied back into existing school washroom plumbing in adjacent wall Fan Coil units installed in ceilings at 4 exit door locations Ventilation: Supply and return air fed form classrooms in ceiling Fire dampers are noted on drawings Electrical: Recessed, lensed 2x4s, T8s, 1 level switching, upgraded ~2000 Battery packs in corridors. Bell/strobes in corridors. CF potlights and recessed 2x4s for corridor lighting.

Page 57: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 57 of 58

F2020.01 Asbestos - *

F2020.04 Mould - *

F2020.09 Other Hazardous Materials - *

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

0

0

0

Design Life

Design Life

Design Life

FEB-08

FEB-08

FEB-08

Updated

Updated

Updated

Replace Door

Repair

Code Repair

2008

2008

$5,720

$1,144

High

Medium

Wood door in metal frame requires a 45min FRR. The door isnot labeled

Concern:

Replace with labeled doorRecommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

FEB-08

FEB-08

Vinyl Asbestos tiles are referred to on the drawings and appear to still remain. They are in good condition and do not pose ahealth risk. However where failure occurs they should be replaced with non-asbestos materials. The piping insulation in themechanical room may contain asbestos (elbows)

No Mould noted or reported.

No Other Hazardous Materials where visible or reported

Page 58: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: October 28, 2008 3:07 PM Page 58 of 58

K4010.02 Barrier Free Entrances - *

K4010.03 Barrier Free Interior Circulation - *

K4010.04 Barrier Free Washrooms - *

K4020 Building Code -

3 - Marginal

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

1980

1980

1980

1980

Installed

Installed

Installed

Installed

0

0

0

0

Design Life

Design Life

Design Life

Design Life

OCT-08

OCT-08

OCT-08

OCT-08

Updated

Updated

Updated

Updated

Install Auto door opener

Upgrade existing core washrooms

Barrier Free Access Upgrade

Barrier Free Access Upgrade

2009

2011

$11,000

$25,000

Medium

Medium

If link is removed existing washrooms do not meet currentaccessibility requirements

Concern:

When link is removed upgrade washrooms.Recommendation:

Airdrie - R. J. Hawkey Elementary School (B2395A)

S8 FUNCTIONAL ASSESSMENT

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

OCT-08

OCT-08

Double 914mm wide entrance doors

Single storey with wide corridors. Interior doors on hold opens. Older hardware and recessed door opening creates someproblems but is acceptable at time of construction. Full width ramps provide ease of movement for able bodies students butmakes negotiation of ramp more difficult for wheelchairs since they can only use the rail on one side.

Barrier free washrooms have been provided and a special handicapped toilet has been installed in the portable link. If theportables and link are removed a washroom upgrade is recommended to bring the current washrooms up to code

The building is divided into three fire compartments which are all one storey in height and facing one street. It appears toconform to current code requirements

Page 59: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: July 24, 2008 1:13 PM

RECAPP Facility Evaluation Report

R. J. Hawkey Elementary SchoolS2395Airdrie

Page 60: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: July 24, 2008 1:13 PM Page 2 of 10

S2395Building Id:

R. J. Hawkey Elementary SchBuilding Name:

AirdrieLocation:Address:

0.00Gross Area (sq. m): $0Replacement Cost:0Construction Year:

Evaluation Date: December 18 2007

Quinn Young Architects Ltd.Evaluation Company:

Barry McCallumEvaluator Name:

This approximately 2.6ha site slopes down approximately 3.6m from the northeast to the main floor of the school. Adrainage swale has been constructed to divert water around the school on the east edge but there are still water pondingand ice conditions affecting use of the site. The front yard and southeast corner of the site are well landscaped. Grassdoes not grow well on the hill leading up to the creative play area and children with disablities have a hard timenegotiating the slope. There is an asphalt parking lot on the south side with the garbage enclosure located at theentrance and directly visible from the street and a large asphalt play area immediately adjacent to the school on thenorth and east sides. Overall the site is in acceptable condition.

General Summary:

Structural Summary:

Envelope Summary:

Interior Summary:

Mechanical Summary:

Electrical Summary:

0%5 year Facility Condition Index (FCI):

Facility Details Evaluation Details

Total Maintenance Events Next 5 years: $179,608

Airdrie - R. J. Hawkey Elementary School (S2395)

Condition Rating Performance1 - Critical Unsafe, high risk of injury or critical system failure.2 - Poor Does not meet requirements, has significant deficiencies. May have high operating/maintenance costs.

3 - Marginal Meets minimum requirements, has significant deficiencies. May have above average operating maintenance costs.4 - Acceptable Meets present requirements, minor deficiencies. Average operating/maintenance costs.

Rating Guide

5 - Good Meets all present requirements. No deficiencies.6 - Excellent As new/state of the art, meets present and foreseeable requirements.

Page 61: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: July 24, 2008 1:13 PM Page 3 of 10

G2010.02.02 Flexible Pavement Roadway (Asphalt) - **

G2010.05 Roadway Curbs and Gutters - *

G2020.02.02 Flexible Paving Parking Lots(Asphalt) - **

G2020.05 Parking Lot Curbs and Gutters - *

4 - Acceptable

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

1980

1980

1980

1980

Installed

Installed

Installed

Installed

25

0

25

0

Design Life

Design Life

Design Life

Design Life

MAR-08

MAR-08

MAR-08

MAR-08

Updated

Updated

Updated

Updated

Replace Asphalt Road Paving

Install 50mm Asphalt Overlay

Lifecycle Replacement

Lifecycle Replacement

2012

2012

$3,432

$28,600

Unassigned

Unassigned

Airdrie - R. J. Hawkey Elementary School (S2395)

S7 SITE

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

APR-08

Asphalt entrance to parking area form Big Springs Drive

Concrete curb cut at Big Springs Drive

Asphalt Paring area was extended in 1993

Cast-in place concrete curbs

Page 62: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: July 24, 2008 1:13 PM Page 4 of 10

G2020.06.01 Traffic Barriers - *

G2020.06.03 Parking Lot Signs - *

G2020.06.04 Pavement Markings - *

G2030.02.01 Gravel Pedestrian Surfacing*

4 - Acceptable

4 - Acceptable

3 - Marginal

4 - Acceptable

Rating

Rating

Rating

Rating

1980

1980

1980

1980

Installed

Installed

Installed

Installed

0

0

0

10

Design Life

Design Life

Design Life

Design Life

MAR-08

MAR-08

MAR-08

MAR-08

Updated

Updated

Updated

Updated

Install boallards at Portables

Repaint parking lines & Handicapped symbols

Repair

Failure Replacement

2008

2009

$5,720

$1,144

High

Low

Portable is not protected at parking area and has beenpreviously damaged

Painted markings are worn and will not be visible shortly

Concern:

Concern:

Install bollards to prevent vehicles form damaging portables

Repaint

Recommendation:

Recommendation:

Airdrie - R. J. Hawkey Elementary School (S2395)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

MAR-08

MAR-08

Metal pipe rail and posts along front of school with gate and pad lock to hard play on north side of school

Painted parking lot stall lines

Crushed brick path between sidewalks at front of school

Page 63: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: July 24, 2008 1:13 PM Page 5 of 10

G2030.02.02 Asphalt Pedestrain Pavement**

3 - MarginalRating

1993Installed

20Design Life

MAR-08Updated

Replace asphalt walkway

Repair 2008 $17,160 High

Slope of walkway drains waterinto portables crawlspace. Waterfrezes on walk creating a hazardous situation.

Concern:

Remove asphalt walkway, Options include : 1) regrade ground to provide cross slope towards drainageswale. 2) provide a trench drain along edge of portable to collect waterso it does not cross walkway. 3) collect water in rain barrels connected to underground dripsystem (use it as a teaching tool?) 3) continue rain water leaders through floor and below asphaltwalkway to drain to grade and heat trace so that RWL do notfreeze up. Install new asphalt walkway with improved crossslope

Recommendation:

Airdrie - R. J. Hawkey Elementary School (S2395)

Event:

Type Year Cost Priority

Updated: APR-08

Asphalt walkway on east side of portables.

Page 64: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: July 24, 2008 1:13 PM Page 6 of 10

G2030.04 Rigid Pedestrian Pavement (Concrete) - **

G2030.06 Exterior Steps and Ramps - *

G2040.02.01 Chain Link Fences and Gates*

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

25

0

30

Design Life

Design Life

Design Life

MAR-08

MAR-08

MAR-08

Updated

Updated

Updated

Replace Concrete Sidewalks

Replace Two Concrete Pads

Lifecycle Replacement

Failure Replacement

2012

2008

$40,040

$5,720

Unassigned

High

Concrete pads are cracked and uneven at two entrance doorsConcern:

Replace concrete pad at north mudroom and at entrance toportables on east side

Recommendation:

Airdrie - R. J. Hawkey Elementary School (S2395)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

APR-08

MAR-08

Concrete sidewalks to main entrance and to mudroom facing Big Springs Drive. Concrete walkway along parking area toportables and smaller concrete walkway form parking area to main entrance

Cast-in place concrete stair in sidewalk from parking area to main entrance with painted metal pipe rail on one-side (repaintrailing - maintenance item)

Chain link fence on north side of playground to pipe rail gate. Chain link fence at end of parking lot with two gates

Page 65: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: July 24, 2008 1:13 PM Page 7 of 10

G2040.03 Athletic and Recreational Surfaces - **

G2040.05 Site and Street Furnishings - *

G2040.06 Exterior Signs - *

3 - Marginal

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

25

0

0

Design Life

Design Life

Design Life

MAR-08

MAR-08

MAR-08

Updated

Updated

Updated

Replace Asphalt Hard Play Area

Relocate Garbage Containers

Failure Replacement

Repair

2011

2010

$57,200

$9,152

Low

Low

Asphalt play area has settled and water ponding is occurring

Garbage enclosures are poorly located at the main entrance tothe parking lot and do not conform to current land-userequirements

Concern:

Concern:

Remove asphalt play surfaces, adjust grades to slope towardsdrainage swale, repave and reapply painted play markings

Relocate garbage enclosure

Recommendation:

Recommendation:

Airdrie - R. J. Hawkey Elementary School (S2395)

Event:

Event:

Type

Type

Year

Year

Cost

Cost

Priority

Priority

Updated:

Updated:

MAR-08

MAR-08

Asphalt play area around north and east ends of school

Park benches and waste receptacle in landscaped areas. Community creative play area on north side. Garbage bins arepoorly located in enclosure in the front yard near the main entrance

Wall mounted lettering on metal cladding at front of school

Page 66: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: July 24, 2008 1:13 PM Page 8 of 10

G2040.08 Flagpoles - *

G2050.01 Irrigation Systems - *

G2050.04 Lawns and Grasses - *

G2050.05 Trees, Plants and Ground Covers - *

G2050.07 Planting Accessories - *

4 - Acceptable

4 - Acceptable

3 - Marginal

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

Rating

1980

1980

1980

1980

1980

Installed

Installed

Installed

Installed

Installed

0

0

0

0

0

Design Life

Design Life

Design Life

Design Life

Design Life

MAR-08

MAR-08

MAR-08

MAR-08

MAR-08

Updated

Updated

Updated

Updated

Updated

Add Terracing & Ramp to Play Area

Repair 2009 $11,440 Medium

Grass will not grow on hill side leading to creative play area dueto amount of traffic. This has created muddy areas

Concern:

Creative terracing with hard landscaping creating a gradualramp so that the creative play area is accessible in a clean andchild safe way.

Recommendation:

Airdrie - R. J. Hawkey Elementary School (S2395)

Event:

Type Year Cost Priority

Updated: MAR-08

Clear anodized aluminum flagpole on concrete base at front of school

19mm Hose bibs on all four side of building. There is an irrigation controller near the parking lot which probably irrigatesimmediately around the building (unconfirmed)

Grassed front yard and side yards with grassed are and landscaping on the east side around the portables. On the northside the grassed areas slope up to the playing fields and creative play area

Mature evergreens, deciduous trees and shrubs in the front yard of the school, Shrubs in planter on south side

152x152mm pressure treated planter at edge of walkway along parking lot on south side

Page 67: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: July 24, 2008 1:13 PM Page 9 of 10

G3010.02 Site Domestic Water Distribution - *

G3010.03 Site Fire Protection Water Distribution - *

G3020.01 Sanitary Sewage Collection - *

G3030.01 Storm Water Collection - *

G3060.01 Gas Distribution - *

G4010.02 Electrical Power Distribution Lines - *

4 - Acceptable

4 - Acceptable

4 - Acceptable

3 - Marginal

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

Rating

Rating

Rating

1980

1980

1980

1980

1980

1980

Installed

Installed

Installed

Installed

Installed

Installed

0

0

0

0

0

0

Design Life

Design Life

Design Life

Design Life

Design Life

Design Life

MAR-08

MAR-08

MAR-08

MAR-08

MAR-08

MAR-08

Updated

Updated

Updated

Updated

Updated

Updated

Airdrie - R. J. Hawkey Elementary School (S2395)

102mm cast iron water line enters water meter room in northwest corner of building

Fire Hydrant located at the property line on the south side of Big Springs Drive

152mm Sanitary line leaves building in northwest corner of classroom area and is connected to a 305mm municipal sanitaryline in Big Springs Drive.There are 102mm sanitary are located on the north side (for future portables) and on the east side(where portables are connected)

All roof drains of core building are connected to a 305mm storm line leaving the building on the south side to a catch basinin the parking lot which is then connected to a 1220 municipal storm line in Big Springs Drive. There is a drainage swale inthe landscaped area on the east side which drains to a slotted catch basin which is connected to the catch basin in theparking lot with an 204mm line. The portables on the east side are draining to an asphalt walkway on the east side andwater may be collecting in the crawl space as well as water freezes on the walkway creating a safety problem.

Gas line with a capacity of 5510 CFM enters the building on the north east corner into the meter room

4 #500 MCM-R90 X-link PVC Jacketed Corflex (al) underground from transformer to 600A 3Phase 4 Wire Main Disconnect& Panel

Page 68: RECAPP Facility Evaluation Report - Alberta.ca · Recommendation: Airdrie - R. J. Hawkey Elementary School (B2395A) Event: Event: Type Type Year Year Cost Cost Priority Priority Updated:

Report run on: July 24, 2008 1:13 PM Page 10 of 10

G4010.03 Electrical Power Distribution Equipment - *

G4010.04 Car Plugs-ins - *

G4020.01 Area Lighting - *

4 - Acceptable

4 - Acceptable

4 - Acceptable

Rating

Rating

Rating

1980

1980

1980

Installed

Installed

Installed

0

0

0

Design Life

Design Life

Design Life

MAR-08

MAR-08

MAR-08

Updated

Updated

Updated

Airdrie - R. J. Hawkey Elementary School (S2395)

Utility supplied transformer and pad located at northeast hard play area of school

13 Duplex outlets in Metal pedestals serving 26 stalls

Wall mounted HPS lighting around the perimeter of the building