NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 1 of 21
March 4, 2019
#1259327
To: All Bidders
Re: Tender No. 237/2018 – Invitation to Bid - Design and Build of Two Bored
(TBM) Single Track Tunnels and Station Boxes for the Green Line Project
Addendum No. 3
Pursuant to Clause 6.8 (Addenda) of the ITB, Bidders are hereby informed of the
following amendments to the Tender Documents.
This Addendum shall constitute an integral part of the Tender Documents and the
Contract.
All capitalized terms used and not defined herein shall have the meaning ascribed to such
terms in the ITB or the Contract.
Each amendment to the Tender Documents which is included herein replaces the relevant
part of the Tender Documents, or any previous applicable addenda, so amended.
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 2 of 21
Amendments to Volume 1 Volume and Clause
in the Tender
Documents
1. Please insert a new definition as follows:
"Base Date "
The Base Date is 10 days prior to the Bid Submission Date."
Volume 1
Definitions
2. Please add another of NTA's Advisor to the schedule in Annex B as follows:
87. HGM Consulting Engineers & Planners
(1980) LTD
Ervin Noyman
Ohad Cristal
Itzhak Meir
Ziv Goren
Modar Scech Yosef
Yonatan Catz
88. BabEng Lars Babendererde
Volume 1
Annex B – NTA's
Advisors
Amendments to Volume 2 Volume and
Clause in the
Tender
Documents
3. The definition of "Employer's Requirements" is to be amended as follows:
"All documents set forth in Volume 3 to the Contract, also referred to as the
"Employer's General Requirements", "NTA's Requirements" or "NTA's General
Requirements."
Volume 2
Definitions
4. The definition of "Mandatory Design Criteria" is to be deleted. Volume 2
Definitions
5. The definition of "Reference Design" is to be amended as follows:
"The design information and drawings which is are included within Volume 4, and
identified as such therein, including the "Mandatory Design Criteria"."
Volume 2
Definitions
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 3 of 21
6. Please amend Clause 4.1.1. as follows:
"Volume 4 (Technical Specifications, not including drawings) ".
Volume 2
Clause 4.1.1.
7. Please amend Clause 4.2.2. as follows:
"Volume 4 (Technical Specifications, not including drawings) ".
Volume 2
Clause 4.2.2.
8. Clause 4.5 is deleted. Volume 2
Clause 4.5.
9. Please add a new Clause 20.4 as follows:
"In the event the Contractor requires early access to perform any early works, surveys,
soil investigations or any other activities on Site, such access shall be coordinated by
the Contractor with the Relevant Authorities and NTA, and the duty to obtain any
applicable Permit or Approval shall be the responsibility of the Contractor."
Volume 2
Clause 20
10. Please insert the following sentence at the end of Clause 31.3:
"Any traffic arrangement related to transportation of Material or Equipment (for
example, transportation or haulage of segments, beams, machinery such as TBMs,
hydromill/hydrofraise, etc.) to or from the Site is deemed included within the Lump
Sum Proposal."
Volume 2
Clause 31.3
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 4 of 21
11. Please amend Clause 31.4.2 as follows:
"31.4.2. In respect of Traffic Inspectors/Supervisors – NTA shall either:
31.4.2.1. Instruct the Contractor to engage a Nominated
Subcontractor and in respect of this specific nomination the
rate for overhead and profit shall be 3% of the applicable
invoices; or
31.4.2.2. Instruct the Contractor to engage its own subcontractor and
in respect of this engagement, the remuneration to the
Contractor for its actual costs as evidenced by invoices and
an additional 3% of such costs in respect of overhead and
profit, but together capped (including in respect of overhead
and profit) is fixed at the hourly rate of ILS 97.54 for day
shifts and ILS 109.88 for night shifts, per person (including
in respect of overhead and profit). These rates shall be
linked to the minimum wage fluctuations as adjusted by
Law from the Bid Submission Date.
It is clarified that this mechanism shall only apply to Traffic Inspectors /
Supervisors operating in temporary traffic arrangements.
All other traffic regulation, such as It is clarified that the cost of any traffic
inspectors, traffic controls and guards at the entrances and exits to the Site
and each part thereof, as required or shall be required, by NTA or any
Relevant Authority, are deemed to be included within the Accepted Price
Lump Sum Proposal."
The costs of Police personnel as approved as part of the Traffic
Arrangement Design by NTA and the Police shall be borne directly by
NTA. This shall not derogate from the Contractor's responsibility for the
coordination of such works and services with the Police.
Volume 2
Clause
31.4.2
12. Please amend this Clause as follows:
"All works of the types included under Netivei Israel cost index Sections 51.3.2 (Road
Marking Works) and 51.3.5 (Temporary Traffic Arrangements for Safety in Work
Sites) shall be evaluated in accordance with applicable rates and prices extrapolated
from Netivei Israel cost index (the most updated version published on the Effective
Date), applying the Discount Rate.
All other works necessary for Temporary Traffic Arrangements and are not included in
either of the above provisions are deemed to be included within the Accepted Lump
Sum Proposal."
Volume 2
Clause
31.4.3
13. Please amend Clause 56.3.2 as follows:
"The development of the Employer's Requirements, Technical Specifications and the
Reference Design to a detailed design;".
Volume 2
Clause
56.3.2.
14. Please amend Clause 60.1.3 as follows:
"For the sake of its evaluation NTA shall use the most updated Hebrew version of Dekel
published on the Effective Date."
Volume 2
Clause
60.1.3
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 5 of 21
15. Annex 1 shall be amended as follows:
Last Delivery Date of Section #2 shall be Contractual Milestone 76
Last Delivery Date of Section #3 shall be Contractual Milestone 76+30 days
Volume 2
Annex 1-
Site Delivery
Dates
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 6 of 21
Amendments to Volume 3 Volume and
Clause in the
Tender
Document
16. Table 1.2 Amended is to be replaced by the Table attached as Attachment 1.
Please note that same references to other Tender Documents have been amended.
Volume 3
Chapter 4
Table 1.2
17. Table 1.3 Amended is to be replaced by the Table attached as Attachment 2.
Please note that same references to other Tender Documents have been amended.
Volume 3
Chapter 4
Table 1.3
18. Table A1 Shall be amended as follows:
Software Version
1. Primavera P6 Management
(EPPM) or any other scheduling
software as will be approved or
instructed by NTA
P6 EPPM R17.7
2. BI software – QlikView or
QlikSense as will be instructed
by NTA
3. Microsoft Office 2016 or later
4. AutoCAD 2017 or later
5. IBM DOORS (Requirement
Management system)
Database version 9.6
6. AutoDesk Revit 2017 or later
7. Health and safety site
management system such as
Safeguard
The latest version at all times
Volume 3
Chapter 4
Annex 1
Table A1
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 7 of 21
19. Clause 5.1 is to be replaced by the following:
"5.1 Definitions
a) Mandatory Design Parameters:
1. The Technical Specifications in Volume 4 include a definition of the
Mandatory Design Parameters, which are:
The LRT Alignment
The LRT Vertical Alignment/ Profile.
Typical Tunnel cross section.
The Outer Box inner dimension and geometry
2. These parameters are binding, and no deviation is allowed or shall be
approved.
b) Employer's Requirements and Technical Specifications
1. Employer's Requirements: the requirements and obligations of the Contractor
as detailed in Volume 3 of the Contract Documents.
These include, for the purpose of the design, the following documents attached
to this Chapter 5:
DSM – Design Standard Manual - Attached in Appendix B.
Design Task Guide (מגדיר משימות) – Attached in Appendix C.
NTA QMS (Quality Management System) – Program Design Management
Plan Rev. 1 (November 2018), - Attached in Appendix B.
The approved statutory plan TATAL 71/B-( /ב 71)תת"ל (Not included in
the Contract documents but forms an integral part thereof as published)
2. Technical Specifications: the technical requirements as detailed in Volume 4 of
the Contract Documents, excluding the drawings in Volume 4.
3. In developing the design, the Contractor shall adhere to the Employer’s
Requirements and Technical Specifications, adopting only such deviations
specifically approved by the Employer and/or the Engineer through the design
process described herein.
c) Reference Design
1. The drawings in Volume 4 Part XVI comprise the Employer's Reference
Design.
2. The Reference Design is for information only and is not binding.
Volume 3
Chapter 5
Clause 5.1
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 8 of 21
3. This shall not derogate from the binding status of the Mandatory Design
Parameters or the Technical Specifications, even as such are referenced in the
drawings."
20. Paragraphs 3 and 6 of Clause 5.3 shall be amended as follows:
"The Contractor shall review, adopt, and develop the Reference Design,
and shall prepare a staged Design Package Submission process. The
Contractor shall ensure that each Design Package submission is fully
compliant with the Reference Design Employer’s Requirements and
Technical Specifications and with the Employer’s design management
processes. "
6. "The Contractor shall collaborate with the Employer, Other
Contractors and their subcontractors nominated or otherwise,
including stakeholders and the authorities to develop the Reference
Design Employer’s Requirements and Technical Specifications and
submit Design Packages through a five-stage design process, as
described in the following sections. "
Volume 3
Chapter 5
Clause 5.3
21. The first paragraph of Clause 5.3.1 shall be amended as follows:
"The Contractor shall submit for review by the Engineer each stage of the Contractor’s
Design Packages in full adherence to the Employer’s Requirements and Technical
Specifications Reference Design, the Engineer’s instructions in writing, these
Employer's Requirements and NTA deliverables definition document ( מגדיר משימות
)."
Volume 3
Chapter 5
Clause 5.3.1
22. Paragraphs 1 and 2 of Clause 5.3.2 shall be amended as follows:
"Stage 1: Preliminary Design Packages
1. The Contractor shall review and develop the Employer's Reference
Ddesign in accordance with these Employer's Requirements and
Technical Specifications.
2. The Contractor shall notify the Engineer upon any ambiguity or
discrepancy becoming apparent between the Reference Designs,
Employer's Requirements, Technical Specifications or the Particular
Specifications for the TBM and Particular Specifications for the
Boxes, within 56 days after the Commencement Date."
Volume 3
Chapter 5
Clause 5.3.2
23. Paragraph 1 of Clause 5.3.4.1 shall be amended as follows:
"Full-Size Mockups and Prototypes
1. The Contractor shall produce, where required, full-size mockups and
prototypes that are fully compliant with the Technical Specifications
requirements contained within Volume 4, Reference Design in
conjunction with these Employer's Requirements, and the Particular
Specifications for TBM and The Particular Specifications for Boxes."
Volume 3
Chapter 5
Clause 5.3.4.1
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 9 of 21
24. The following NTA Design Task Guides shall be added to Appendix C as per the List
of Contents in the beginning of Appendix C (attached herein as Attachment 3):
4. NTA Design Task Guide – Roads
5. NTA Design Task Guide – Interface between infra 1 and 2
6. NTA Design Task Guide – Bridge Design
Volume 3
Chapter 5
Appendix C
25. Clause 6.8.1.1 shall be amended as follows:
"The Contractor shall prepare a Monthly Progress Report according to Volume 3, Part
VII, Chapter 4 clause 4.3.6.2.6 1.3.6.2.5, based on the Current Time Schedule and the
Baseline Time Schedule and submit it to the Employer."
Volume 3
Chapter 6
Clause 6.8.1.1
26. Clause 6.8.1.4 shall be amended as follows:
"The Contractor shall submit the Monthly Progress Report in .pdf format together
with an .mpp file a file of the approved Schedule software presentation of the Current
Time Schedule."
Volume 3
Chapter 6
Clause 6.8.1.4
27. Clause 7.7.4 shall be amended as follows:
Interface Management Plan
"Within 40 150 days after the Commencement Date, the Contractor shall submit its
proposed Interface Management Plan (IMP) to the Engineer for
approval."
Volume 3
Chapter 7
Clause 7.7.4
28. Clause 8.3 shall be amended as follows:
Quality Plan
"The Contractor shall prepare and submit a Project Quality Plan to the Engineer for
review and acceptance within 60 120 days of the Commencement Date."
Volume 3
Chapter 8
Clause 8.3
29. Clause 1.3 shall be amended as follows:
Submittal of Risk Management Plan (RMP)
3. "Within 28 90 working days from the Commencement Date, the Contractor shall
submit its Risk Management Plan (RMP) for the Works to the Employer
for review."
Volume 3
Chapter 9
Clause 1.3
30. The fourth paragraph of Clause 12.4.5 shall be amended as follows:
"Within 28 120 days of the Commencement Date, the Contractor shall submit the
following documents"
Volume 3
Chapter 12
Clause 12.4.5
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 10 of 21
31. Clause 14.3.6 shall be amended as follows:
Environmental and Sustainability Management Plan (ESMP)
"The Contractor shall submit a Contract-specific Environmental and Sustainability
Management Plan (ESMP), according to the QMS E&S Management
Plan. The Contractor shall submit to the Engineer for review an ESMP
within 56 120 days from the Commencement Date and prior to
mobilization at sites date. "
Volume 3
Chapter 14
Clause 14.3.6
32. Clause 18.9 shall be amended as follows:
Public Relations Management Plan
"The Contractor shall submit a Public Relations Management Plan to the
Engineer for review within thirty 120 days from the Commencement Date."
Volume 3
Chapter 18
Clause 18.9
33. Clause 3.2 shall be amended as follows:
"The Contractor will develop the Requirements Management Plan, and will submit
it for the Engineer's approval within 28 120 days from the Commencement Date."
Volume 3
Chapter 20
Clause 3.2
34. Clause 4.3 shall be amended as follows:
Requirements Management Plan
"The Requirements Management Plan shall be a key component of the RMS. The
Contractor shall submit his suggested RMP for the Engineer's approval
within 28 120 days of the Commencement Date. "
Volume 3
Chapter 20
Clause 4.3
35. Clause 11.1.8 shall be amended as follows:
"The Contractor shall submit the Construction Site Security Plan, described in
clause 11.2 below, for review within 60 120 calendar days from the
Commencement Date."
Volume 3
Chapter 30
Clause 11.1.8
36. Clause 1.7 shall be amended as follows:
Document Reporting
"In addition to the Document Management Plan based on the Aconex (EDMS) to be
provided in accordance with Volume 3, Part VIII, Chapter 7
(Management of the Works), the Contractor shall prepare and submit to
the Engineer for review within 28 60 days of the Commencement Date a
Document Submission Plan for the production and submission of the
documents (including but not limited to: design documents, drawings,
contractual deliverables, engineering support documents, reports,
technical queries and requests for information, as-built drawings and
documentation, operation and maintenance manuals and records, health
and safety files, etc.). "
Volume 3
Chapter 33
Clause 1.7
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 11 of 21
37. Please insert the following sentence at the end of this clause:
Any works required by the Contractor to accommodate such events (including
security and/or traffic personnel) are deemed included in the Accepted Lump Sum
Proposal and in the Baseline Time Schedule."
Volume 3
Chapter 18
Clause 18.10.2
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 12 of 21
Amendments to Volume 4
Volume and
Clause in the
Tender
Documents
38. In the Table of contents, the title of Clause 2 shall be amended as follows:
"2. MANDATORY DESIGN CRITERIA PARAMETERS"
Volume 4
Part VIII
Chapter 1
Table of
contents
39. Clause 2 shall be amended as follows:
2. "Mandatory Design Criteria Parameters
The Contractor shall base his design on adhere with the following
Mandatory Design Criteria Parameters as defined at the attached in
Vol 3 Chapter 5- Design Management, and detailed in Volume 4
documents:
2.1. LRT Alignment
2.2. LRT Vertical Alignment/ Profile.
2.3. Typical Tunnel cross section.
2.4. Outer Box inner dimension and geometry"
Volume 4
Part VIII
Chapter 1
Clause 2
40. Clause 6.3 shall be amended as follows:
6.3 The reference design herein describes a sequence based on station first
method, it is clarified that this sequence is not binding.
Volume 4
Part VIII
Chapter 1
Clause 6.3
41.
Clause 7.1.2.1, 7.1.2.2 shall be amended as follows:
"7.1.2.1. Diaphragm Walls & Piles
7.1.2.2. Cap Beams for diaphragm Walls & Piles"
Volume 4
Part VIII
Chaper 1
Clause 7.1.2.1,
7.1.2.2
42. Clause 10.1.2.1 shall be amended as follows:
"10.1.2.1. Initial internal BCS – prior to work start and as required for completing
the BDA as stated in section 810.1.1.1 above."
Volume 4
Part VIII
Chapter 1
Clause 10.1.2.1
43. The last paragraph of Clause 13.1.4 shall be amended as follows:
"All the required related works within the Scope of Work for items 1113.1.4.1,
1113.1.4.3, and 1113.1.4.4 will paid within the Provisional Sum. For item
1113.1.4.2, only the direct works of the water supply main pipe relocation will be
paid within the Provisional Sum."
Volume 4
Part VIII
Chapter 1
Clause 13.1.4
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 13 of 21
44.
A new clause 54.17.01.26 shall be added as follows:
"54.17.01.26 The Contractor may propose the use of a refurbished TBM under the
following conditions:
1. The refurbished TBM shall fulfil all the Technical Specifications
applicable to the TBM.
2. The refurbished TBM shall be refurbished by its original
manufacturer only.
3. The manufacturer shall certify in a written statement that the
refurbished TBM shall be completely refurbished to like-new
conditions with emphasis on the following components:
a. The main bearing life expectancy shall be at least two times the
expected working hours for the project.
b. Bearing seals shall be new.
c. The main gear shall be tested with penetrating liquid and shall be
certified as free of cracks or other defects.
d. The screw conveyor flight and casing shall be reconditioned "as new"
and free of wear and tear.
e. The cutting wheel structure shall be free of any damage with new wear
protection plates installed. Worn out cutter housing shall be replaced."
Volume 4
Part X
Chapter 1
New Additional
Clause
54.17.01.26
45. The title of Clause 1.2.2 shall be amended as follows:
"Above Ground Sensitive Structures"
The title of Table 1 shall be amended accordingly as follows:
"Green Line LRT Tel Aviv G3-2- Central Underground Section- Sensitive
Structures Complex Building"
Volume 4
Part X
Chapter 2
Clause 1.2.2
46. A new paragraph shall be added at the beginning of Clause 1.4 as follows:
"Waterproofing of concrete slabs in contact with the soil at the following levels:
-1.36, -1.43, the sloped slab of platforms between 0.05 and -0.50 levels, at the
launching shaft slab at the -1.94, -1.85 levels".
Volume 4
Part XI
Chapter 4
Clause 1.4
47. Please add a new Appendix A to Chapter 1, attached herein as Attachment 4 (IWA's
letter (ref:LNL-2019) dated 22 January 2019).
Volume 4
Part XI
Chapter 1
New Appendix
A
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 14 of 21
48. A new Clause 3.16.5 shall be added as follows in Bold Letters:
"3.16.5 The instructions of this Clause 3.16- "Dewatering"- are general
instructions and shall be applied not only for station box works but to any
other work that may necessitate dewatering ".
Volume 4
Part XI
Chapter 1
A New Clause
3.16.5
49. New Clauses 3.16.1.17, 3.16.1.18 and 3.16.1.19 shall be added as follows.
"
3.16.1.17 IWA letter LNL-2019 sent on Jan 22nd 2019 is attached as Appendix A to
this Chapter 1. The IWA instructions as detailed in this letter are relevant
as of the date of the letter. The letter is attached for information only and
does not bind NTA in any way. NTA gives no warranty that such
statements within the letter are correct, exhaustive or shall remain
applicable throughout the project. The Contractor shall have sole
responsibility for any coordination with IWA for the purposes of its design.
3.16.1.18 In the event of any change in the IWA priorities for disposal of water, the
Contractor shall not be entitled to any additional payment or extension of
time and the Contractor shall not be eligible to claim concerning this
change.
3.16.1.19 The water discharge fees are the responsibility of the Contractor. However,
in the event of an increase in the water discharge fees rate (as compared to
the fee rates at the Bid Submission Date) NTA shall be responsible for the
increase (the difference between the new rate and the rate at the Bid
Submission Date)."
Volume 4
Part XI
Chapter 1
New Clauses
3.16.1.17,
3.16.1.18,
3.16.1.19
50. The first paragraph of Clause 2.3.3 shall be amended as follows:
"The stations shall be constructed by the cut and cover method. The Employer’s
Reference Preliminary Design for the construction of the inner boxes by the Infra 2/
Inner box and Fitout contractor is are based on bottom-up construction staging
procedures for the main reason:"
לבדיקה חוזרת
Volume 4
Part XI
Chapter 1
Clause 2.3.3
51. Clause 2.3.3.6.1 shall be amended as follows:
"2.3.3.6.1 As stated above, the Employer’s Reference Preliminary Design based on
station first method accommodates the need of adopting a station structural design
that permits the TBM to enter the station through the diaphragm wall, be pulled
through the station outer box and launched through the diaphragm wall at the other
end to continue the tunnel drives."
Volume 4
Part XI
Chapter 1
Clause 2.3.3.6.1
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 15 of 21
52. A new Clause 3.13.13 shall be added as follows:
"Any king pile or similar vertical structural element used for the installation of the
temporary decking must be removed prior to handover. The Contractor will deliver
and hand over the outer boxes without any vertical obstacle inside (other than the
horizontal propping system). Accordingly, the deck’s span will be the entire
transversal section of each station box. The Contractor must consider this
requirement in its design, construction-planning and scheduling."
Volume 4
Part XI
Chapter 1
A new Clause
3.13.13
53. A new Sub-Clause 11 shall be added at the end of Clause 9- Dry utilities- specification
for Electrical and Communication utilities-
"11. The Contractor Scope of Work shall include infrastructure and cabling for all
systems and utilities infrastructure."
Volume 4
Part XI
Chapter 2
A new Sub-
Clause at the
end of Clause 9
54. Paragraph 3 of Clause 3.4.2.1.2 shall be amended as follows:
" 3. The cut & cover will be constructed from two parallel lines of
diaphragm walls, with a clear opening of 9.32m between
them, a concrete ceiling floor and a rail slab, designed by Infra 2.
Volume 4
Part XI
Chapter 3
Clause 3.4.2.1.2
Paragraph 3
55. The title of Clause 1 shall be amended as follows in the Table of Contents and in the
chapter:
"Levinsky Train Station"
Volume 4
Part XI
Chapter 4
Clause 1
56. First paragraph of Clause 1.2.10 shall be amended as follows:
"On the slab perimeter, towards vertical surfaces, on top of the strengthening
bitumen membrane, an additional bitumen Membrane strip, the Bottom Covering
Membrane shall be welded. The Membrane strip shall be welded centered on the
cant, lap the strengthening bitumen Membrane and then shall climb on the vertical
surface lapping the general bitumen Membrane."
Volume 4
Part XI
Chapter 4
Clause 1.2.10
57. First paragraph of Clause 1.4.10 shall be amended as follows:
"On the slab perimeter, towards vertical surfaces, on top of the strengthening
bitumen membrane, an additional bitumen membrane strip, the covering membrane
shall be welded. The membrane strip shall be welded centered on the cant, lap the
strengthening bitumen membrane and then shall climb on the vertical surface
lapping the general bitumen membrane."
Volume 4
Part XI
Chapter 4
Clause 1.4.10
58. Clause 3.1.8 shall be amended as follows:
"On the roof perimeter, towards vertical surfaces on top of the bottom covering
bitumen membrane, an additional bitumen membrane strip, the top covering
membrane shall be welded. The membrane strip shall be welded centered on the cant,
lap the strengthening bottom covering bitumen membrane and then shall climb on
the vertical surface lapping the general bitumen membrane up to 5 cm above the
bottom covering bitumen membrane on the vertical surface. "
Volume 4
Part XI
Chapter 4
Clause 3.1.8
59. Clause 1.6 Title shall be amended as follows:
"Waterproofing of piles wall at the portal (from axis 360 to south-west direction) and
at the emergency stairs no. 1 and no. 2"
Volume 4
Part XI
Chapter 4
Clause 1.6
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 16 of 21
60. Clause 1.6.1 shall be replaced by the following new Clause 1.6.1:
"1.6.1 Surface preparation
On the surface of the walls making smoothing concrete layer including the
reinforcement bars acc. to structural engineer plans. The concrete layer will fill all the
gaps between the piles and cover them with about a 2 cm thick layer.
The concrete surface shall be smooth and cleaned properly of any dirt, dust, unbound
material residues etc. Segregation pockets shall be plugged with concrete repair
mixture according technical specification no.1, reinforcement bars shall be cute 2 cm
deep inside the concrete and plugged."
Volume 4
Part XI
Chapter 4
Clause 1.6.1
61. Existing Clause 1.6.2 shall be deleted. The following clauses 1.6.3 and 1.6.4 shall
be re-numbered 1.6.2 and 1.6.3 respectively.
Volume 4
Part XI
Chapter 4
Clause 1.6.2
62. Clause 1.5 shall be amended as follows
"The Contractor has to name a responsible senior surveying expert (CV shall be
provided) in charge of all the Contractor’s survey activities to act as the point of
contact for the Engineer. CV shall be submitted to the Engineer for review and
approval, at least 90 days before commencement of installation on site."
Volume 4
Part XI
Chapter 5
Clause 1.5
63. Clause 6.1.6 will be added
"6.1.6. The Contractor shall submit the CV of the Contractor's inspector to the
Engineer for approval at least 90 days before the commencement of the
relevant works."
Volume 4
Part XI
Chapter 5
Clause 6.1.6
64. Clause 4.3 shall be amended as follows
4.3."Upon request, The Contractor shall submit evidence of experience of personnel
in charge in their respective capacity, and details of professional registration 90
days prior to commencement of relevant construction activities. The Contractor
shall not change key Condition Survey personnel without prior approval of the
Employer and shall give at least 4 weeks’ notice of any such change."
Volume 4
Part XII
Chapter 1a
Clause 4.3
65. Building Condition Survey was extended and additional information is attached as
Attachment 5.
Volume 4 Part XVII - Report Chapter 5 - BCS Deliverables List and Status.pdf
Volume 4 Part XVII - Report Chapter 5 - BCS No 2.pdf
Volume 4 Part
XII - Report
Chapter 5 –
BCS
66. Clause 10.4 shall be amended as follows:
"The Contractor shall include CVs and notices of the availability of all personnel in
his Method Statements submitted to the Engineer for review and comments, at least
installation starts on site. Copies of all CV's shall be before 90 days one month
uploaded to the Employer´s MDB. CV's shall be updated upon each change of
personnel."
Volume 4
Part XIII
Chapter 1
Clause 10.4
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 17 of 21
67. Table 1 shall be deleted. Instead, the following sentence shall be added in its place
as follows:
"For minimum requirements of the Monitoring Team- see Volume 4, Part XIII,
Chapter 1, Clause 10".
Volume 4
Part XIII
Chapter 2
Clause 3.2
68. The following sentence shall be inserted in Clause 4 :
4. Minimum requirements for station monitoring
Table 2: Monitoring Requirements List shows below the minimum monitoring
requirements for controlling the execution of Green Line stations. The criteria
defined below has been established taken into account the, the monitoring
experience gained during Red Line stations execution and the specific monitoring
requirements defined for Green Line in [4] .
Note: The inclinometer of the D. Wall will be done by using IPI
Volume 4
Part XIII
Chapter 2
Clause 4
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 18 of 21
Amendments to Drawings Volume and
Clause in the
Tender
Documents
69. The following drawings shall be replaced with the drawings attached herein.
Text color changed from yellow to black.
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_KAPLAN-01
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_KAPLAN-02
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_KAPLAN-03
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_KAPLAN-04
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_KAPLAN-05
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_KAPLAN-06
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_KAPLAN-07
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_KAPLAN-08
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_KAPLAN-09
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_RABIN-01
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_RABIN-02
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_RABIN-03
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_RABIN-04
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_RABIN-05
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_RABIN-06
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_RABIN-07
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_RABIN-08
GL-170201-TCO-TA-FT-ST-250-V03_01-r3_WORK_STAGES_RABIN-09
GL-170201-TCO-TA-FT-ST-300-V03_01-
r3_WORK_STAGES_ARLOZOROV_WEST-01
GL-170201-TCO-TA-FT-ST-300-V03_01-
r3_WORK_STAGES_ARLOZOROV_WEST-02
GL-170201-TCO-TA-FT-ST-300-V03_01-
r3_WORK_STAGES_ARLOZOROV_WEST-03
GL-170201-TCO-TA-FT-ST-300-V03_01-
r3_WORK_STAGES_ARLOZOROV_WEST-04
GL-170201-TCO-TA-FT-ST-300-V03_01-
r3_WORK_STAGES_ARLOZOROV_WEST-05
GL-170201-TCO-TA-FT-ST-300-V03_01-
r3_WORK_STAGES_ARLOZOROV_WEST-06
GL-170201-TCO-TA-FT-ST-300-V03_01-
r3_WORK_STAGES_ARLOZOROV_WEST-07
GL-170201-TCO-TA-FT-ST-300-V03_01-
r3_WORK_STAGES_ARLOZOROV_WEST-08
GL-170201-TCO-TA-FT-ST-300-V03_01-
r3_WORK_STAGES_ARLOZOROV_WEST-09
Volume 4 Part
XVI - Design
Drawings
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 19 of 21
70. The following drawing shall be replaced with the drawing attached herein (in PDF
and DWG format).
The "arrows" defining the different buildings have been removed.
GL-170201-KMR-TA-FT-ST-0100-V03_01-LV-SD010
Volume 4
Part XVI &
XVIII
71. The following drawings shall be replaced with the drawing attached herein (in PDF
and DWG format).
The date that was shown on the previous drawing for the completion of the
contiguous piled wall was removed.
GL-170201-KMR-TA-FT-ST-0101-V03_00-LV-SD030
GL-170201-KMR-TA-FT-ST-0101-V03_00-LV-SD031
Volume 4
Part XVI &
XVIII
72. The following Detailed Survey drawings is added:
Updated Detailed Survey - Addendum 3.zip
Volume 4 Part
XVIII - DWG
for Information
73. The following updated detected utilities drawings shall be replaced with the drawing
attached herein:
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1905
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1906
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1907
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1908
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1909
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1910
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1911
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1912
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1913
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1914
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1915
GL-170201-ABX-TA-FT-UC-500-v03_01-19XX-1916
Volume 4
Part XVI &
XVIII
74. The following Mobilization Sites drawing in DWG format is added:
DWG Mobilization sites.zip
Volume 4 Part
XVIII - DWG
for Information
75. The following Levinsky parking structure survey is added:
Survey of Levinsky UG parking lot.zip
Volume 4 Part
XVIII - DWG
for Information
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 20 of 21
76. The following DWG format of Kedmor’s drawings are added:
GL-170201-KMR-TA-FT-AL-0250-V03_00-NO-SD500
GL-170201-KMR-TA-FT-CON-0200-V03_00-NO-SD510_511
GL-170201-KMR-TA-FT-CON-0100-V03_00-NO-SD512
GL-170201-KMR-TA-FT-CON-0100-V03_00-NO-SD1512
GL-170201-KMR-TA-PD-CON-VARI-V03_00-NO-SD513
GL-170201-KMR-TA-PD-CON-VARI-V03_00-NO-SD514
GL-170201-KMR-TA-PD-CON-VARI-V03_00-NO-SD515
GL-170201-KMR-TA-PD-DT-VARI-V03_00-NO-SD520
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD020
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD021_022
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD122
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD031_032
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD132
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD040
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD041_042
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD043_044
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD045_046
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD146
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD050
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD051
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD052_053
GL-170201-KMR-TA-FT-ST-0100-V03_00-LV-SD153
GL-170201-KMR-TA-PD-ST-0100-V03_00-LV-SD054
GL-170201-KMR-TA-PD-ST-0025-V03_00-LV-SD060
GL-170201-KMR-TA-PD-ST-0100-V03_00-LV-SD081
GL-170201-KMR-TA-PD-ST-0250-V03_00-LV-SD080
Volume 4 Part
XVIII - DWG
for Information
77. The following drawings shall be replaced with the drawings attached herein (in PDF
and DWG format).
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1405
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1406
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1407
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1408
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1409
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1410
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1411
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1412
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1413
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1414
GL-170201-KMR-TA-FT-ST-0500-V03_01-SR-SD1415
Volume 4
Part XVI &
XVIII
NTA – Metropolitan Mass Transit System
Tender No.237/2018 Addendum no. 3 Page 21 of 21
78. New drawings of buildings monitoring and instrumentation devices are added (in
PDF and DWG format).
GL-170201-ARE-TA-PD-TU-100-V03_00_1040-00.pdf
GL-170201-ARE-TA-PD-TU-100-V03_00_1041-00.pdf
GL-170201-ARE-TA-PD-TU-100-V03_00_1042-00.pdf
GL-170201-ARE-TA-PD-TU-100-V03_00_1043-00.pdf
Volume 4
Part XVI &
XVIII
79. Drawing list shall be replaced with the following document:
Volume 4 Part XVI - List of Drawings Addendum 3.pdf
Volume 4 Part
XVI - Design
Drawings
80. List of content shall be replaced with the following document:
Volume 4 Part XVIII - DWG Table of Contents Addendum 3.pdf
Volume 4 Part
XVIII - DWG
for Information
81. The following drawings shall be added:
GL-170201-TCO-TA-FT-ST-250-V03_00-r1_Jet Grouting for TBM Breakthrough-
01.pdf
GL-170201-TCO-TA-FT-ST-2500-V03_00-r3_GEOLOGICAL PROFILE-
ARLOZOROV WEST.pdf
GL-170201-LVE-TA-PE-BOR-2500-V03_00-1600-00.pdf
Volume 4 Part
XVI - Design
Drawings