Upload
leola
View
26
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Re-examination of PQ Standards, Mark Stephens – EPRI. NYSDPS Power Quality Technical Conference December 12, 2013. Original EPRI R&D Project (1996-2000). In 1996 EPRI Began “ Task 24: Power Quality in the Semiconductor Industry ” Original Participants:. Original Task 24 Testing. - PowerPoint PPT Presentation
Citation preview
NYSDPS Power Quality Technical Conference
December 12, 2013
Re-examination of PQ Standards, Mark Stephens – EPRI
2© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Original EPRI R&D Project (1996-2000)
• In 1996 EPRI Began “Task 24: Power Quality in the Semiconductor Industry”
• Original Participants:
Original
Task 24 Testing
3© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Original R&D Project Timeline
Mid 1996
Feb 1999T24 Final Report
April 97Workshop 1
Dallas
Sept 97Workshop 2
Tempe
June 98Workshop 3
Dallas
April 99Workshop 4
Tempe
June 97
Task 24 Research and Testing
Nov 1998
33 Tools TestedBy EPRI PEAC
Oct 97
Oct 97Approval forTask Force
By SEMI
Sept 99SEMI F47 Published
June 2000SEMI F42
AndSEMI F47Revisions
June 99Test Methodology
SEMI F42Published
SEMI Task Force Standards Work
4© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
SEMI F47-0706 Test Levels
Relevant for Single and Two Phase Voltage Sags Only – does not address
Three-Phase Events.
5© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
The Question Remains…
• Previous EPRI studies have shown that SEMI F47 has made an impact on reducing fab downtime.
• However, there are still PQ events above the SEMI F47 requirements that are causing downtime in semiconductor fabs.
•WHY?
6© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
New EPRI Research Projectto Re-Examine SEMI F47
• Understand electric service quality requirements.
• Identify post SEMI F47 mechanisms for continued semiconductor processing equipment downtime through industry collaboration.
• Determine key strategies and methodologies to further harden semiconductor equipment to power quality events.
• Inform development of revised standards, equipment designs, power system requirements, and PQ testing methodologies for current and next generation semiconductor tools.
• Improve productivity through minimizing production downtime.
7© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Example Utility PQ Data at Semiconductor Plant
• 72 Sag Events• 38 Diff. Days• 16 Events affected
production,– Only 1 clearly
below SEMI F47!
1 10 100 1000 100000
0.5
1
1.5
2
Cycles
No
min
al
Vo
lta
ge
(x
10
0%
)
SEMI F47
VoltageSag
8© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Objectives
•The key objectives of this project are:–Determine the characteristics of power quality
events still causing semiconductor plant process downtime
–Take a new look at the sensitivities in the process equipment
–Determine any required adjustments to equipment design or standards to further reduce voltage sag induced losses by the semiconductor industry.
9© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Benefits (1)
• Utility Collaborators will gain information about the characterization of a broad spectrum of equipment and fabrication tools, which will enable them to evaluate industry expectations in the context of the service capabilities of electric power systems.
• Utility Host-Collaborators will work closely with partnering Semiconductor Site-Hosts to gain specific understanding of the needs and expectations of their customer.
10© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Benefits (2)
• Semiconductor Site-Hosts will gain an in-depth understanding of why their equipment is still sensitive to specific power quality events and learn specific measures that can be taken to further harden their current and future process systems.
• Equipment and Tool Manufacturers will gain a better understanding of why their equipment may still be vulnerable to power quality issues and methods for improving their power quality robustness.
11© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Stakeholder Collaboration
System Compatibility
Electric Utilities*
Tool Suppliers/ OEMs
SEMI & SEMATECH
EPRI
Consultants
Semi Fabs Site-Hosts
• Collaboration between stakeholders will be required.
• Project approach is to
carefully examine the cause of PQ related downtime
• The outcome of basic R&D will inform processes and standards to further improve system compatibility
*Utilities can participate as Collaborators or Host-Collaborators.
12© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Project Approach and Summary (1)
• This project will methodically investigate the potential factors that continue to cause semiconductor plant downtime in a post-SEMI F47 environment.
• These factors may include: – (1) three-phase voltage sag events– (2) repeated voltage sag events due to recloser operations– (3) events outside SEMI F47 scope of magnitude, duration, phase-shift
or point-on-wave– (4) voltage sag testing methods utilized during certification, tool
software, design, or configuration differences– (5) electrical system differences between the certification environment
and the actual fab environment. – (6) Equipment not certified to SEMI F47
13© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Project Approach and Summary (2)
• Working through EPRI, Utility Host-Collaborators will partner with a specific Semiconductor Site-Hosts to investigate SEMI F47 requirements against specific site electrical environments and identify potential gaps against tool shutdown data.
• SEMI F47 certification documents will be reviewed for the sensitive tool sets and characterization of this equipment will be accomplished through additional analysis and testing.
• Specific design and mitigation strategies including cost-benefit will be determined and documented.
14© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Project Approach and Summary (3)
• The general, non-confidential findings from these partnerships will help inform the overall collaborative effort through workshops, white papers, and the final report.
• Utility Collaborators will participate in the overall effort through participation in project web-meeting and workshops, inclusion in engagement with SEMI and SEMATECH, and involvement in any proposed standards modifications.
15© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Research Project Tasks
Task Activity Plan1 Document the Electrical System Environment of the Semiconductor fab. 2 Identify gaps and opportunities for creating a successor to the current SEMI F47
standard that addresses the electrical environment for known equipment shutdowns.3 Review SEMI F47 certification documents for sensitive tool sets.4 Determine the susceptibility of the current tool sets .5 Indentify effective design and mitigation strategies. 6 Perform Cost-Benefit Analysis7 Provide Technical Materials for Host Site (Reporting, Findings, Recommendations)8 Write White Paper on Initial Findings.9 Collaborative Workshop No. 1
10 Propose modification to existing SEMI F47 performance criteria as necessary as identified by the previous tasks.
11 Develop and Validate Test Methods to Confirm that Tools Meet proposed Power Quality and Ride-Through Requirements.
12 Suggest Revisions to SEMI 49 “Review Guide for Semiconductor Factory Voltage Sag Immunity”
13 Suggest Revisions to SEMI F50 “Performance Guidelines for Power Supplied to Semiconductor Factories by utilities”
14 Perform a gap analysis to determine the potential reduction in power quality related costs.
15 Collaborative Workshop No. 216 Technical Transfer Documentation and Reporting
Specific R&D Activities at
each Host-Site
Collaborative Activities
Technical Deep Dive Slides…
17© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Potential Causes for Downtime (1)
Three-Phase voltage sag events.– SEMI F47 does not require the OEM to test their equipment against
three phase voltage sags events– CIGRE study (C4.110) has shown that three-phase (Type III) events
can make up to 20 percent of the events that occur
Sites Voltage range
Number of sites
Single-phase (Type
I)
Two-phase (Type II)
Three-phase (Type III)
MV & HV Sites
6 kV – 230 kV 969 27% 53% 20%
Sites <1KV 206 64% 25% 11%
18© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Potential Causes for Downtime (2)
Repeat voltage sag events– Reclosing to restore operations.– SEMI F47 does not require testing
for back to back events – Sag events can be multiple events
in close intervals based on fault clearing
Faulted Feeder “A”
Adjacent Feeder “B”
Line to Ground
FaultProtectiveRelays
(reclosers)
Su
bst
atio
n B
us
TD 1 TD 2
Initial Fault
Reclose Attempt 2
TD 3
Reclose Attempt 3
Reclose Attempt 1
Time
RM
S V
olt
age
TD 1 TD 2
From Initial FaultReclose
Attempt 2
TD 3
Reclose Attempt 3
Reclose Attempt 1
Sag Event Sag Event Sag Event Sag Event
Time
RM
S V
olt
age
Adjacent Feeder “B”
Faulted Feeder “A”
19© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Potential Causes for Downtime (3)
Event magnitude, duration, phase-shift, and point-on-wave are outside of SEMI F47 scope
– SEMI F47 calls for testing at 0 degree point-on-wave.• Actual events can occur at various
points-on-wave– Possible Phase-shifts are based on
set of test vectors.• Actual events can be different
– Minimum magnitudes and durations are:• 50% Vnom, 200ms• 70% Vnom, 500ms• 80% Vnom, 1 Second
20© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Potential Causes for Downtime (4)
Voltage sag testing methods utilized during certification. – There are three types of phase-to-phase voltage sag test vectors
that are allowed for SEMI F47 testing. – These three types of vectors result in various voltage magnitudes
and phase shifts.
21© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Potential Causes for Downtime (5)
Tool Software, design, or configuration differences
– The tool configuration and
software during SEMI F47 testing may have been slightly different than the equipment that is installed at the semiconductor fab’s facility.
Graphic Ref: SEMI F49 “Guide for Semiconductor Factory Voltage Sag
Immunity””
22© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Potential Causes for Downtime (6)
Electrical System Differences
– During SEMI F47 certification
testing, the equipment is tested against the nominal voltage available at the site.
– The available nominal and peak voltage at the point of connection at the semiconductor fab can change due to changes to the system configuration.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Pre
-sa
g A
ctu
al V
olta
ge
(%)
Energy Loss (%)
The Lower the Pre-Sag Voltage, the Less Energy (and ride-through time)Is Available in the Components with Capacitors
23© 2013 Electric Power Research Institute, Inc. All rights reserved.
NYSDPS Power Quality Technical Conference 12/12/2013
Potential Causes for Downtime (7)
Installed Equipment In the Fab is not Compliant to SEMI F47
• Equipment in the factory may not
actually be compliant to power quality standards such as SEMI F47.
• In procurement, tool capabilities and delivery schedule may trump testing for SEMI F47 compliance
REF: Impact of SEMI F47 on Utilities and Their Customers, EPRI, Palo Alto, CA: 2004. 1002284.