PRESENTATION ON PREPARATION OF SLUM FREE CITY UNDER RAJIV AWAS YOJANA IN MIRA BHAYANDAR MUNICIPAL CORPORATION

Date: 23/11/2012

Page 2: Ray presentation

RAJIV AWAS YOJANA (RAY) The various components of this projects includes: Identification of Slum Pockets Conduction of Socio-economic and Biometric

survey of the beneficiaries Conduction of Total Station/ Plane table survey

of the slum area. Preparation of Base map using GIS and Satellite

Images. MIS and GIS integration Preparation of architectural Layouts of the Slum

area for its development Preparation of DPR

Page 3: Ray presentation

INNOVATION IN RAY REQUIRED

All the Socio-economic, biometric and total station survey data are currently being integrated offline which will be later on submitted to the governing authority.

Such data shall be made available to WAPCOS field offices by preparing an online module of the same.

This will also ensure that the status on the work done by WAPCOS in RAY projects can be easily retrieved and produced before the clients.

Page 4: Ray presentation

UPDATE ON PREPARATION OF SLUM FREE CITY PLAN OF ACTION.

GIS Mapping: The whole GIS-MIS component shall be available on our WAPCOS site. The various components of GIS which are completed are as follows:

i. Preparation of City Base Map.ii. Slum Marking using Satellite Images.iii. Digitization of DP maps, Village/ Cadastral

maps and their rectification.iv. Road Digitization.v. Marking of important Landmarks.

Page 5: Ray presentation

STATUS ON PREPARATION OF SLUM FREE CITY PLAN OF ACTION

Page 6: Ray presentation

SLUMS DETAILS (WRT. NO. OF HUTS)

SLUM DETAILS SLUMS COVERED

15

10

52

No. of huts

Less than 100Between 100-500Between 500-1500Above 1500

1

2

1

2

No. Of Slums

Less Than 100Between 100-500Between 500-1500Above 1500

Page 7: Ray presentation

SLUM FREE CITY PLAN OF ACTION

Page 8: Ray presentation

UPDATE ON PREPARATION OF INNOVATIVE PILOT PROJECTS.

Status on Pilot projects preparedi. Pilot Projects for Ambedkar Nagar, Bhola

Nagar and Gandhinagar Pocket is on the verge of completion.

ii. Clearing the reservation of Garden and Cementry encroached by Slum, Development of Roads, water supply lines & Drainage Lines, provision for STP, Primary health care center, Electric Sub-Station and school is included in the pilot project.

Page 9: Ray presentation

COMMUNITY MEETING AT SLUMDuring community meetings information such as the objective of the scheme, the contribution of the beneficiaries in the project, the type of houses to be built if sanctioned, their area etc. are discussed.

Page 10: Ray presentation

CONDUCTION OF TOTAL STATION SURVEYThe total station survey is carried out in order to confirm the no. of huts present in the slum including tracing their exact location. This data is later on merged with the satellite images so as to propose a Slum development scheme

Page 11: Ray presentation

DPR PREPARATION

Page 12: Ray presentation

SLUM LOCATIONS

Page 13: Ray presentation

AMBEDKAR NAGAR SLUM POCKET

Page 14: Ray presentation

DEVELOPMENT PLAN FOR AMBEDKAR NAGAR SLUM POCKET

Slum Layout

Data Verificati

on

Total Station Survey

Page 15: Ray presentation

FLOOR PLAN

Page 16: Ray presentation

AMENITIES PROVIDED

No. of Tenements = 2048 Plot reserved for cemetery and Garden

released 32 Nos. of buildings with 64 tenements

each Plot allotted for Primary School, Primary

health center 92 Beneficiaries from Anna Nagar will

be relocated in Ambedkar Nagar Pocket.

Page 17: Ray presentation

MIS-GIS INTEGRATIONAfter completion of the total station and the biometric survey, the data is integrated with the GIS base map prepared. Thus, the data of each and every beneficiary can be retrieved as and when required.