79
RAJASTHAN ELECTRONICS & INSTRUMENTS LIMITED, JAIPUR (An ISO 9001 : 2015& 14001 : 2015 “Mini Ratna” Central Public Sector Enterprise) 2, KANAKPURA INDUSTRIAL AREA, SIRSI ROAD, JAIPUR-302034 Tel No: 0141- 2471083 E-mail: [email protected]. website: www.reiljp.com NOTICE INVITING TENDER FORSupply of BOS, Design, Engineering, Energy Supply, Installation, Testing, Commissioning, Synchronizing with Evacuation at 11kv substation inside the premises ,comprehensive , Operation & Maintenance for 12 years of 200 kW Grid Connected Solar PV Plant in Udaipur ,Rajasthan from regular/ approved vendorsTENDER NO. . REIL/RE/19-20/PP/19135 dated 18.10.2019 Important Dates Last Date & Time for submitting e- tender: 24/10/2019 up to 15:00 Date & Time for opening of e-tenders 25/10/2019 at 15:00 Kindly note that only online bid will be considered against this tender

RAJASTHAN ELECTRONICS & INSTRUMENTS LIMITED, JAIPUR

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

RAJASTHAN ELECTRONICS & INSTRUMENTS LIMITED, JAIPUR

(An ISO 9001 : 2015& 14001 : 2015 “Mini Ratna” Central Public Sector Enterprise)

2, KANAKPURA INDUSTRIAL AREA, SIRSI ROAD,

JAIPUR-302034

Tel No: 0141- 2471083

E-mail: [email protected]. website: www.reiljp.com

NOTICE INVITING TENDER FOR“ Supply of BOS, Design, Engineering, Energy Supply, Installation,

Testing, Commissioning, Synchronizing with Evacuation at 11kv substation inside the premises

,comprehensive , Operation & Maintenance for 12 years of 200 kW Grid Connected Solar PV Plant in

Udaipur ,Rajasthan from regular/ approved vendors”

TENDER NO. . REIL/RE/19-20/PP/19135 dated 18.10.2019

Important Dates

Last Date & Time for submitting e- tender: 24/10/2019 up to 15:00

Date & Time for opening of e-tenders 25/10/2019 at 15:00

Kindly note that only online bid will be considered against this tender

RAJASTHAN ELECTRONICS & INSTRUMENTS LIMITED, JAIPUR

NOTICE INVITING TENDER NO. REIL/RE/19-20/PP/19135

This is a Notice Inviting Tender (NIT) for Supply of BOS, Design, Engineering, Energy Supply,

Installation, Testing, Commissioning, Synchronizing with Evacuation at 11 KV substation inside the

premises ,comprehensive , Operation & Maintenance for 12 years of 200 kW Grid Connected Solar PV

Plant at Titardi, Udaipur ,Rajasthan as per description and terms & conditions specified hereinafter:

Item Description:

S. No. Description

1. Supply of BOS, Design, Engineering, Energy Supply, Installation, Testing,

Commissioning, Synchronizing with Evacuation at 11kv substation inside the

premises ,comprehensive , Operation & Maintenance for 12 years of 200 kW

Grid Connected Solar PV Plant at Titardi, Udaipur ,Rajasthan.

1.2 E-Tendering Procedure: The work shall be carried out through submission of online tenders only.

No offer in physical form will be accepted and any such offer if received by REIL will be out rightly

rejected. Tender documents can be downloaded from our website www.reiljp.com or website of CPPP

www.eprocure.gov.in.Final bids are to be submitted on website www.eprocure.gov.in.Any changes

modification in the tender enquiry will be intimated through above websites only. Tenderer are

therefore, requested to visit our Website regularly to keep themselves updated.

The bidder should have a valid Digital Signature certificate issued by any of the valid certifying

Authorities to participate in the online tender.

The bids shall be uploaded in electronic form only through e-tendering system on website

www.eprocure.gov.in.

Note: e- Procurement system does not allow submission of documents after due date of tender.

Incomplete form or non-submission of documents to verify details may results into rejection of

your offer and no communication shall be done for submission of documents.

Only those contractors who are approved with REIL for required Installation and commissioning

work can quote against this tender.

Price Bid:-Price Bid format given with tender is to be uploaded after filling all relevant information

like basic prices, taxes & duties. The Price bid should be uploaded strictly as per the format available

with the tender failing which the offer is liable for rejection (remaining or changing format of price

sheet will not be accepted by system). REIL reserve the right to distribute the work.

Annexure-I

RAJASTHAN ELECTRONICS & INSTRUMENTS LIMITED, JAIPUR

Process Compliance Form

(Tenders are required to print on their company‟s letter head and signed, stamp before uploading).

To

Dy. General Manager (Proc.)

M/s Rajasthan Electronics & Instruments Limited

2, Kanakpura Industrial Area, Sirsi Road,

Jaipur-302034

Sub:- Acceptance to the process related Terms and Conditions for the e-Tendering

Dear Sir,

This has reference to the Terms & Conditions for e-Tendering mentioned in the tenderNo.:-

REIL/RE/19-20/PP/19135

We hereby confirm the following:-

1) The undersigned is authorized representative of the company.

2) We have carefully gone through the NIT, Tender Documents and the Rules governing the e-

tendering as well as this document.

3) We will honor the Bid submitted by us during the e-tendering.

4) We undertake that if any mistake occurs while submitting the bid from our side, we will honor the

same.

5) We are aware that if REIL has to carry out e-tender again due to our mistake, REIL has the right to

disqualify us for this tender.

6) We confirm that REIL shall not be liable & responsible in any manner whatsoever for my/our

failure to access & submit offer on the e-tendering site due to loss of internet connectivity,

electricity failure, virus attack problem with the PC, digital signature certificate or any other

unforeseen circumstances etc.

With regards

Signature with company seal

Name:

Designation:

E-mail Id:

Brief of Project :-

The 200kWp grid-connected ground mounted/rooftop solar PV projects on the land in cattle

hose premises. The generated solar power shall evacuate 11kv substation inside the premises

and power will feed directly to the grid. The scheme aims to reduce the fossil fuel based

electricity load on main grid.

The Bidder is advised to read carefully all instructions and conditions appearing in this

document and understand them fully. All information and documents required as per the bid

document must be furnished. Failure to provide the information and / or documents as required

may render the bid technically unacceptable.

Annexure - II

A) ELIGIBILITY CONDITIONS:

Bidder must fulfill following criteria:-

1. Experience in Installation & Commissioning of Cumulative 200 kWp SPV Power Packs.

2. Experience in Maintenance of cumulative 200 kWp SPV Power Packs.

3. Contractor must having valid electrical Contractor License issued by Electrical inspectorate

Department, Govt. of Rajasthan.

OR

1. Party having experience for Installation – Commissioning and fabrication of 200 kWp SPV

Power Plants.

2. Contractor must having valid electrical Contractor License issued by Electrical inspectorate

Department, Govt. of Rajasthan.

NOTE:-

1. Only those contractors who are registered with REIL for Installation &

Commissioning of Solar Systems can quote against this tender.

B) FINANCIAL CAPABILITY, EXPERINCE:-

1. Firm should have average turnover of Rs. 1 Cr. in last three financial years.

Bidder should submit following documents along with Technical bid on website:-

1. Bankers Report.

2. Balance sheet for last two years.

3. Turnover and Networth value duly certified by CA.

4. Photocopy of the last Three years Income Tax Return.

5. Experience in Installation, Commissioning and maintenance of SPV Power Plant

Systems. (attached verified documents such as I&C and maintenance certificate.

6. Photocopy of GST/service tax registration No., TIN no., PAN no.

7. Any other relevant documents

C) EARNEST MONEY & SECURITY DEPOSIT

1. The tender must be accompanied by a sum of Rs. 1,50,000/- (Rupee One Lakh Fifty

Thousand only) as Earnest Money in the form of deposit receipts, demand drafts or Bank

Guarantee failing which the tender shall be summarily rejected. These forms of earnest

money could be either of the Punjab National Bank or of any of the Nationalized Banks or

by a scheduled bank.

2. Bank Guarantee should be valid for a period 06 month from the date of bid submission.

3. The Successful Bidder shall deposit the Security deposit of amounting to Rs. 3,50,000 only

(Rupee Three Lakh Fifty Thousand only) in the form of Bank Guarantee/Demand Draft

within 7 days from date of issuing of LOA and valid upto three months from the last date of

O&M period. The PBG shall be established/issued from the the Punjab National Bank or

of any of the Nationalized Banks or by a scheduled bank.

4. In case if EMD is submitted in the form of BG, it may be considered as Security Deposit

and bidder have to extend the validity of BG upto three months from the last date of O&M

period.

D) OTHER CONDITIONS:

a) Responsibility for executing Contract: The contractor is to be entirely responsible for

the execution of the contract in all respects in accordance with the terms and conditions as

specified in the acceptance of tender.

b) The contractor shall not sublet transfer or assign the contract to any part there of without the written permission of the Dy. General Manager (Proc.). In the event of the contractor contravening this condition, Dy. General Manager(Proc.) be entitled to place the contract elsewhere on the contractors account at his risk and the contractor shall be liable for any loss or damage, which the Dy. General Manager(Proc.), may sustain in consequence or arising out of such replacing of the contract.

d) Document: The bidder should have a valid PAN / TAN /GST NO & other statutory

document as applicable and produce attested copies of such certificates along with the tender

papers in Technical Bid, failing which the tender is liable to be rejected. Check list be attached.

e) Right to accept / reject: REIL reserves the right to reject any or all tender without assigning any reason whatsoever. Also, the REIL authority reserve the right to award any or part or full contract to any successful agency at its discretion and this will be binding on the bidder.

f) e quantity of the SPV Systems shown in the tender can be increased or decreased to any extent depending upon the actual requirement.

g) Assistance to contractor: The contractor shall not be entitled for assistance

either, in the procurement of raw materials required for the fulfillment of the contract or in the securing of transport facilities.

E) Service Center :The contractor shall given undertaking for providing service center in Ajmer for period of 5 years with contact details of technical persons.

F) PRICES:

a. Prices are to be quoted in Indian Rupees.

b. Prices quoted in the Price/Financial Bid must be meaningful and measurable in the context.

c. The prices quoted must be per Watt Peak (Wp) shown in the BOQ.

d. Price must be quoted in original sheet of BOQ failing which the same is liable to be rejected

e. Offer shall be valid for 90 days from the date of bid opening

f. Work may be distributed on L1 prices.

Scope of Work (REIL Jaipur) :

The following material will be supplied for Roof Top Grid Connected SPV Power Plant by

REIL Jaipur:

S. No. Description of Work

1. 300-330Wp or higher SPV Modules with MC4 Connector

2. String Inverters with Data logger

Scope of Work for 200 kWp(Vendor):

The following material will be supplied for 350 kWpRoof Top Grid Connected SPV Power

Plant :

S. No. Description of item Rating Quantity

A. Module Mounting

Structures

200 kWp for Ground

mounted/shed Structures

As per requirement

B. AC/DC/HT cables

As per Technical Specification

mentioned in Tender

As per requirement

C. Junction Boxes As per Technical Specification

mentioned in Tender

As per requirement

D. AC/DC Distribution Box As per Technical Specification

mentioned in Tender

As per requirement

E. MCB/MCCB/ACB As per Technical Specification

mentioned in Tender

As per requirement

F. Transformer and

accessories

As per Technical Specification

mentioned in Tender

As per requirement

G. Earth electrode As per Technical Specification

mentioned in Tender

As per requirement

H. Control/Communication

cables

As per Technical Specification

mentioned in Tender

As per requirement

I. Lightning arrester As per Technical Specification

mentioned in Tender

As per requirement

J. Solar Meter &Energy

Meters

As per Technical Specification

mentioned in Tender

As per requirement

K. MIP Boxes As per Technical Specification

mentioned in Tender

As per requirement

L. Fire Fighting Equipments

(Fire extinguisher, Fire

bucket etc.)

As per Technical Specification

mentioned in Tender

As per requirement

M. MCCB/MCB with enclose

&with locking facility

As per Technical Specification

mentioned in Tender

As per requirement

N. Supervisory Control And

Data Acquisition

(Scada)/Plant Monitoring

As per Technical Specification

mentioned in Tender

As per requirement

O. Isolater As per Technical Specification

mentioned in Tender

As per requirement

P. MC4 Connector As per Technical Specification

mentioned in Tender

As per requirement

Q. Ring type Copper lug As per Technical Specification

mentioned in Tender

As per requirement

R. Ring type Copper lug As per Technical Specification

mentioned in Tender

As per requirement

S. Ring type Alu. lug As per Technical Specification

mentioned in Tender

As per requirement

T. Ferrule (Alphabetic &

Numeric)

As per Technical Specification

mentioned in Tender

As per requirement

U. PVC conduit pipe As per Technical Specification

mentioned in Tender

As per requirement

V. GI Cable tray As per Technical Specification

mentioned in Tender

As per requirement

W. Cable ties As per Technical Specification

mentioned in Tender

As per requirement

X. Cable Glands Single

compression heavy duty

(Make: Comet)

As per Technical Specification

mentioned in Tender

As per requirement

Y. Sign boards for arrays,

PCU, control room, Caution

sticker (format attached)

etc

As per Technical Specification

mentioned in Tender

As per requirement

Z. Hot dipped GI strip As per Technical Specification

mentioned in Tender

As per requirement

AA. Sanitary fitting for Module

Cleaning arrangement with

pressure Motor pump

As per Technical Specification

mentioned in Tender

As per requirement

BB. Rubber Pipe flexible As per Technical Specification

mentioned in Tender

As per requirement

CC. Installation accessories

ladders, safety belts/shoes

etc required for safe I&C of

Power plants

As per Technical Specification

mentioned in Tender

As per requirement

DD. Any other

item/material/services for

completion of the particular

job as well as

commissioning of Power

Plant

As per Technical Specification

mentioned in Tender

As per requirement

EE. Other Equipments

mentioned in Technical

Specification

As per Technical Specification

mentioned in Tender

As per requirement

NOTE:-It is advised to contractor to prior visit of site before submission offer.

The scope of work of contractor for the project is as under:

Safety and security of the Materials at Site.

Material required such as cables glands, tags, cable trays, GI Strip for earthing material & item

mention in above list or in Technical specifications etc. to complete job.

Installation & commissioning of SPV Modules, String Inverter,

Supply, Installation & commissioning of Solar Meter, Energy meters, Accessories etc.

Supply,Installation of earthing material and lightning system, testing and commissioning of

complete earthing and lightning system as per specification requirement.

Laying, Termination, Glanding, Ferruling of all interconnecting cables among sub array, String

Inverter, Conduting, Cable Trays and load panel etc .

Wiring of complete solar system as per requirement.

Testing of DC/AC wiring as per requirement.

The scope of work of the contractor is to complete the Supply of BOS, I&C of SPV Power

Plant.

REIL shall handover all material at Site (SPV Modules & String Inverter only).

Any other work tools & tackle required for completion of the project shall be arranged by

the contractor.

Meter testing, CT testing in Discom Lab and liasioning with Discoms in the scope of contractor

All necessary items/manpower/arrangements required for Proper and Safe Installation &

Commissioning of Power Plant will be arranged by the agency/Contractor. Any material/item

other then mentioned in Scope of work (REIL) which is required for I&C of Power Plants is in

scope of the agency.

Contractor shall take all necessary steps, follow up &liasoning towards the Net Metering

arrangements .

Contractor will take necessary statutory approvals/ clearances from all concern departments ,

Electrical Clearance from department etc. for installation & commissioning of Power Plant.

Contractor shall re arrange the existing AC wiring if required.

All arrangements for their deployed workman/manpower at site will be take care by the agency.

Contractor/agency shall give declaration that site has been visited and all information towards

timely completion of project has been collected and taken care before quoting for the above

enquiry.

Prices quoted must be firm and fixed. No price variation/escalation shall be allowed.

Contractor shall arrange all the manpower and material required for inter-connection of the SPV

Power Plant to the load.

Contractor shall carry out the AMC of Power Plant for 12 years as per work order terms and

conditions.

After successful installation – commissioning of the Power Plant Contractor shall get a

certificate of installation, commissioning and satisfactory operation from beneficiary as per

requirement of work order. The scope of work also includes verification of documents from the

customer.

After installation – commissioning of the Power Plant Contractor shall arrange the inspection of

Power Plant from customer/ designated agency/REIL as per work order requirement and

expanses, if any, shall be borne by contractor.

Contractor shall install and commission the Power Plant in the stipulated time given by the

agency.

The payment of contractor shall be released after release of payment from agency.

Contractor will submit weekly Project Execution Plan (PEP) along with offer. In which

contractor gives the details that how will project accomplished. Contractor shall be also submit

the PERT CPM for project scheduling & Management.

Item no.1 of Schedule of Quantities: The brief scope of work included in this item is as given below.

Survey, Design, detailed Engineering, Supply (without SPV Modules & Inverters) , installation

testing and commissioning of 200 KWp Solar Photo Voltaic Power Plant including supply and

installation of the solar modules & arrays with associated system comprising of DC system,

cables & JBs, inverters, step up transformer of required rating for necessary connection to the

11 kv power station inside the premises at suitable voltage level, switchgears along with

adequate protection and monitoring facilities up to the grid connection point. all works required

for commissioning of 200KWp Solar Photo Voltaic Power Plant are included in the scope).

Conducting complete Glare analysis

Providing of suitable mounting structure including Civil foundations for PV arrays as per the

site conditions, to meet the wind speed conditions up to 200Km/Hr.

Submission & obtaining the approval of Electrical schematic of installation as well as power

evacuation scheme for the approval of statutory authorities as per the local laws at the

conceptual level and at commissioning level.

Integrated microprocessor-based SCADA with required software & hardware for control &

monitoring of SPV plant as per the best standards system

Provision of external lighting.

Earthing and lightning protection system for the whole plant.

Providing telephone / communication cables.

Providing Fire detection system and Fire fighting equipment.

Construction of RCC/PEB substation for Solar Plant.

Providing water supply including piping for distribution of water to various parts of plant.

Providing proper drainage system.

Providing internal paths required for maintenance of PV Panels

Item no.2 to 7 of Schedule of Quantities: Supply and laying of HT cables from Solar Power plant to

load center. Exact Measurement to be done by bidder during Survey and site visit.

Item no.8 to 9 of Schedule of Quantities:

Operation & Maintenance for a period of TWELVE Years (Including Initial 5Years under DLP)

& All-inclusive comprehensive maintenance contract after DLP

All other scope work as detailed in the technical specifications of the work and as mentioned in

the schedule of quantities. DRAWINGS ANDDOCUMENTS

TECHNICAL SEPCIFICATION OF EQUIPMENTS

I. Design, Detailed Engineering, Supply of BOS (except SPV Modules, Inverters) , transportation,

loading/unloading, storage, installation and commissioning of 200 kWp Capacity Solar PV Power

Plant and interconnecting to 11KV/440 V cattle house Sub-Station as required.

II. Design, Engineering of the solar modules & arrays with associated system comprising of DC

system, cables & Junction Boxes, inverters, transformation to the required voltage for necessary

connection to the grid at specified voltage level at the specified location, switchgears along with

adequate protection and monitoring facilities up to the grid connection point. Augmentation of the

Bus, to be carried out at the grid connection point at 11KV/440V, cattle house Indoor substation.

III. Optimum design, Engineering & providing of suitable mounting structure including Civil

foundations for PV arrays & layout etc. as required for mounting the modules as per the site

condition to meet the wind speed conditions up to 200Km/Hr. with anti-corrosion feature so as to

have minimum maintenance requirements during operational years of the plant.

IV. Before start of the work, the successful bidder is required to conduct its own detailed survey of

the site and submit a copy of the same to REIL. same to be incorporated in the detailed design.

V. Survey & route finalization of the transmission Cable(s) for connection to the nearby substation

feeder of 11KV/440V cattle house premises Sub- Station for power evacuation and injection.

VI. Erection/installation, of the solar PV plant along with associated system including power

transmission cable(s) and its termination(s) at the grid point etc as required.

VII. Submission & obtaining the approval of electrical schematic of installation as well as power

evacuation scheme for the approval of statutory authorities, AVVNL and Central Electricity

Authority as per the local laws at the conceptual level and at commissioning level.

VIII. Integrated Micro-Processor based SCADA with required software & hardware for control &

monitoring of SPV plant as per the best standards complete as required.

IX. All associated electrical works required for interfacing at 11 KV line as required based on site

conditions for optimal system design and usage (i.e., main step up transformer, breakers, LA, HT

switchgears, protection systems, cables, metering, earthing of required ratings based on the design

conditions etc.).

X. For Power supply and control voltage required during the start-up and pre- commissioning

suitable size underground cables shall be laid from the nearest source to the Inverter.

XI. Design, supply, laying, testing & commissioning of 11 KV Earthed line cabling & associated

equipment for connecting into 11KV/440 V Indoor Substation as per the technical specifications

XII. Provision of required size GI/HDPE pipes for laying of AC & DC Cables in solar farmyard for

crossing internal roads, without any extra cost.

XIII. Complete cleaning of existing cable duct, removal of debris, drain out of seepage & drainage

water etc., including lying of HT Cables, Communication cables and control cables through the

existing covered cable duct etc. complete as required.

XIV. Submission of Layout drawings for RCC / Pre Fabrication Structure(s) at for housing Inverter, HT

VCBs, LT Panels, Power Transformer, UPS etc., at one of the location in the enclosed drawing.

Complete design details of the infrastructure shall also be submitted.

XV. Provision of Standby power auxiliary power supply from premises Power Distribution nearby.

XVI. Earthing and advanced lightning protection system for the whole plant as per the local statutory

requirements.

XVII. Provision of power and water supply during construction phase including security etc. as required

for the installations till it is handed over to beneficiary.

XVIII. Providing Fire detection system and Fire fighting equipment.

XIX. Construction of RCC/PEB substation building for Solar Plant.

XX. Providing water supply including piping for distribution of water to various parts of plant.

XXI. Provision of Weather Monitoring System and Module Cleaning System.

XXII. The Complete Solar Power PV System shall be under Comprehensive Maintenance Contract

(CMC) and Operation & Maintenance for a period of TWELVE Years (Including Initial 5 Years

under DLP)

A. PLANNING AND DESIGNING:

I. The bidders shall provide complete design, detailed drawings, basis for selection of equipment

for all Electro-Mechanical works and shall be got approved from REIL before commencement

of installation work.

II. The bidders shall select suitable rating and capacities of the various equipment required for HT

power evacuation & injection in to the existing 11 KV system. The bidders shall ensure that

Power Evacuation & injection system is meeting the plant design & system requirements,

statutory requirements and AVVNL requirements.

III. The Contractor shall furnish the following drawings & documents on award of the work within

7 days and obtain approval from REIL.

IV. BAR/Activity Chart for the complete project in MS Project indicating various activities of

project such as time required planning, approval of drawings, fabrication of materials, factory

inspection, transportation, installation, testing and commissioning, obtaining statutory approvals

etc. complete as required. The time for the complete project shall be as indicated in the tender.

This BAR/Activity Chart to be submitted to REIL for approval within ten days on award of the

work and shall be the binding document for control and monitoring the progress of the project.

V. General arrangement and dimensioned layout of complete Solar PV System.

VI. Schematic drawing showing the SPV panel, inverter(s), Junction Boxes, AC and DC

Distribution Boards, meters etc.

VII. Detailed cable route drawings, selection of cable sizes, equipment‟s, General arrangement,

power and control drawings for all LT & HT equipment‟s, invertors, UPS, transformer etc.

VIII. Complete earthing layout, lightning protection and external lighting.

IX. Structural drawing along with foundation details for the RCC / pre- fabricated structures and

transformer foundations etc.

X. Itemized bill of material for complete SV plant covering all the components and associated

accessories.

XI. Layout of solar Power Array, Internal roads layout drawing.

XII. Water piping arrangement drawings for module cleaning. The drawing(s) should include the

pipe layout drawing and P & I drawing, with the sizes of various pipe section along with valve

locations etc. Also the successful bidder to inform the quantity and quality of water

requirements for module cleaning.

XIII. The bidder should carry out Shadow Analysis at the site and accordingly design strings & arrays

layout considering optimal usage of space, material and labour. The bidder should submit the

array layout drawings along with Shadow Analysis Report to REIL for approval on award of

work within 07 Days.

XIV. REIL reserves the right to modify the Layout and specification of sub-systems and components

at any stage as per local site conditions/requirements.

XV. The bidder shall submit preliminary drawing for approval & based on any modification or

recommendation, if any. The bidder shall submit three sets and soft copy in CD of final drawing

for formal approval to proceed with construction work.

B. ENERGY YIELD ESTIMATION & BENCH MARK FOR ENERGY YIELD COMPUTATION

Considering the site conditions, irradiance and ambient temperature, the Contractor shall calculate the

energy generation from the specified plant throughout the year, year on year for 25 years with the

annual average performance ratio and submit the same along with the bidder‟s technical bid.

Energy yield prediction essentially depends on simulations and loss assumptions. However, loss

benchmarks presented in the table below is considered for computation, Loss Description.

Soiling Bidders are advised to evaluate the dust profile on site and define the O&M strategy for

maintaining the soiling loss to 2%

Module Quality The bidders should select PV modules with positive tolerance only.

DC Cable losses Max 1.5%

AC Cable losses Max 1.5%

Grid availability 100% availability to be considered for simulation

Solar PV System(Plant)

A Grid Tied Solar Roof Mounted Photo Voltaic (SPV) power Source (Plant) shall consists of SPV

array, Module Mounting Structure, String Inverter consisting of Maximum Power Point Tracker

(MPPT), Inverter, and Controls & Protections, interconnect cables and switches. PV Array is mounted

on a suitable structure. Components and parts used in the SPV power plants including the PV modules,

metallic structures, cables, junction boxes, switches, inverters etc., should conform to the latest BIS or

IEC or international specifications, wherever such specifications are available and applicable. SPV

Modules and Inverters are supplied by REIL.

Following items shall provide by bidder (but not limited to them);

i. Mounting structures.

ii. DC Cables & Accessories, Junction Boxes

iii. String Monitoring Unit (Monitoring for each string)

iv. SCADA and Weather Monitoring Station

v. Step up transformer

vi. LT Cables and accessories as per site requirements and design.

vii. HT & LT Panels with protections.

viii. 11 KV UG Cabling from Solar Plant to 11KV/440 V cattle house Sub-Station

ix. Power Evacuation arrangement at 11KV/440 V cattle house Sub-Station

x. Earthing and lightning protections for the complete plant

xi. IR/UV protected PVC Cables, pipes and accessories and providing HDPE pipes for

laying of HT Cables, communication cables and control cables.

xii. UPS Power Supply System

xiii. External Electrification by LED fixtures

Any other item(s) or work, which is not specifically mentioned but essentially required for completion

& Successful Commissioning of the System.

C. PARTICULAR SPECIFICATIONS

I. ARRAY STRUCTURE

a) Hot dip galvanized MS / Aluminum mounting structures to be used for mounting the modules/

panels/arrays. Each structure should have angle of inclination as per the site conditions to take maximum

insulation. However, to accommodate more capacity the angle inclination may be reduced until the plant

meets the specified performance ratio requirements.

b) The Mounting structure shall be so designed to withstand the speed for the wind zone of the location

where a PV system is proposed to be installed (wind speed of 200 kM/ hour). It may be ensured that the

design has been certified by a recognized & reputed engineering college / Institution in this regard and

submit wind loading calculation sheet to REIL. Suitable fastening arrangement such as grouting and

calming should be provided to secure the installation against the specific wind speed. The mounting

structure and foundation etc. shall withstand design wind speeds as per IS 875 and meeting the local

requirements.

c) The mounting structure steel shall be as per latest IS 2062: 1992 and galvanization of the mounting

structure shall be in compliance of latest IS4759. Minimum thickness of galvanization for hot dip

galvanized sections is 120 Microns.

d) Minimum height to be maintained at the lower level of the module shall be 600mm. The entire structure

including the array shall be earthed to two independent earth electrodes and all earth electrodes shall be

interconnected.

e) Structural material shall be corrosion resistant and electrolytically compatible with the materials used in

the module frame, its fasteners, and nuts and bolts. Aluminum structures also can be used which can

withstand the wind speed of respective wind zone. Necessary protection, towards rusting need to be

provided either by coating oranodization.

f) All fasteners used in the structure and module mounting shall be made of SS 304 grade and shall meet

appropriate standards. The array structure shall be designed in such a way that it occupies minimum

space without sacrificing the output from SPV panels. As already specified, the bidder has to conduct his

own anti-glare analysis and the designs should consider and incorporate the recommendations of this

analysis by providing any modifications needed consequent to the antiglare analysis, without any extra

cost.

g) The structure shall be designed for easy replacement of any module considering either three modules in

the horizontal position or two modules in the vertical position. Depending on the roof condition for

blocks/module area, Module tables shall be designed in an aesthetical manner and in the same line/level.

the panel at regular intervals, easy maintenance and easy washing of the panels etc. as required.

h) The height of the array structure for mounting the PV modules and accessories shall not be more than

the permissible height for the respective locations as per the details given at Para1.

II. JUNCTION BOXES (JBs) /STRING MONITORING UNIT/STRING COMBINERBOX

a) String monitoring unit shall be provided for each string. Each string should have DC fuse/DC MCB, the

rating of which shall be as specified by the module manufacturer in the data sheet. The junction boxes

shall be dust, vermin and waterproof. It shall be made of thermo plastic/poly carbonate, sunlight/UV

resistive, and fire retardant having minimum IP 65 rating. It should have provision for cross ventilation

through vent plugs and suitable for structure mounting. The junction boxes shall have provision for

connecting earth wire for protection as per requirements.

b) The junction boxes shall have suitable cable entries fitted with cable glands of appropriate sizes for both

incoming and outgoing cables. Suitable markings shall be provided for easy identification and cable

ferrules shall be fitted at the cable termination points for identification. Junction boxes shall also have

suitable surge protection/arresting devices. The arrangement in the junction box shall conform to IEC

60364-7-712. A Main DC isolation switch of adequate rating shall be provided for disconnection

ofarrays/strings.

c) Copper bus bars/terminal blocks housed in the junction box with suitable termination threads

Conforming to IP65 standard and IEC 62208. Hinged door with EPDM/Poly urethane rubber gasket to

prevent water & dust entry to be provided with single compression cable glands and provision of

earthings. It should be placed at 5 feet height or above for ease of accessibility and maintenance.

d) Each Junction Box shall have High quality of suitable capacity Metal Oxide Varistors (MOVs) / surge

arrestors and suitable Reverse Blocking Diodes. The Junction Boxes shall have suitable arrangement

monitoring and disconnection for each of the groups. After disconnection, it should allow string voltages

to be measured separately.

e) Each junction shall have MODBUS RS 485 communication interface for monitoring as per IEC 61326-

1-2005 and the input current, system voltage and internal temperature to be monitored as a minimum,

and other parameter as specified in SCADA.

f) Suitable markings shall be provided on the bus bar for easy identification and the cable ferrules must be

fitted at the cable termination points for identification.

g) All the cables (Power, control and communication) from PV modules to junction box to be provided in

GI Pipe of suitable size, neatly fixed to the structure with SS Clamps and SS nuts and bolts, so that the

cables are not damaged by rats and rodent. Alternatively, the GI Pipes of suitable size may also be used

and which may be fixed neatly fixed on to the structure with SS clamps and SS nuts and bolts.

h) All the junction boxes shall be suitably identified and provided with engraved plates for easy

identification during maintenance.

III. DC & AC DISTRIBUTIONBOARDS:

The DC and AC Distribution boards shall be provided where ever required as per scope of work, design

requirements and site conditions. The distribution boards shall confirm to the following specifications

and requirements;

a) DC Distribution panel shall receive the DC output from the array field.

b) AC Distribution boards shall be provided wherever required. AC Distribution Panel Board

(DPB) shall control the AC power from String inverter and should have necessary surge

arrestors. Interconnection from ACDB to LT side of Step Up transformer for HT power

evacuation shall be made through suitable size Aluminum or copper armored cables as

required.

c) The distribution boards/panels shall be designed for minimum expected ambient temperature of

50 degree Celsius, 90% humidity and dusty weather.

d) All indoor panels will have protection of IP54 or better. All outdoor panels will have protection

of IP65 or better. The distribution boards should conform to Indian Electricity Act and rules (till

last amendment).

e) The AC Distribution boards/Panel shall be suitable for operation on a 415- Volt, 3 phases, 4

wire, 50 Hz. Earthed neutral supply, and capable of withstanding a symmetrical fault condition

of not less than 65 kA for 1second. All the 415 AC or 230 volts devices / equipment like bus

support insulators, circuit breakers etc., mounted inside the switchgear shall be suitable for

continuous operation and satisfactory performance under the following supply conditions

i. Variation in supply voltage + or -10%

ii. Variation in supply frequency + or -3Hz

f)

g) The MCBs, MCCBs, ACBs and other panel accessories shall meet the following specifications

and requirements. MCBs shall be used up to 16 Amp; MCCBs up to 400 Amp and above ACBs

shall be provided. However, for isolation, control and protection of Invertors (Centralized) only

ACBs shall be provided. The fault level shall be as specified and as per the site requirements.

IV. MINIATURE CIRCUIT BREAKER(MCB)

1. The miniature circuit breakers shall conform to IS8828-1996.

2. The miniature circuit breakers shall be single pole/double pole/triple pole/four pole as per site

requirement & required duty applications or AC or DC type. The breaking capacity of MCBs

shall have minimum 10 kA. The tripping characteristics shall meet the requirements of the duty

applications.

3. The MCB shall be of plug in type, trip reset facility and a common trip bar on TP/FPMCBs.

4. MCBs shall be with Trip free mechanism & toggle with positive contact indication.

5. The MCB shall have self-wiring contacts with full size silver tungsten alloy contracts.

6. Indications ON/OFF shall be molded into MCB.

7. Electrical endurance of the MCB shall be not less than 20,000 operations.

8. MCB used for controlling power circuits shall be with tripping characteristics of „C‟ curve

where as MCBs used to protect control transformer circuits shall be with tripping characteristic

of „D‟curve.

V. MOULDED CASE CIRCUIT BREAKER(MCCB):

i. The MCCB shall be suitable for inverter duty applications

ii. The MCCBs shall comply with IS: 13947 Part-II

iii. The thermal rating of circuit breaker shall be as specified in BOQ.

iv. Rated symmetrical breaking capacity ICS = ICU = ICS at 415 volt, 50HZ shall be as required

and not less than50KA

v. Rated insulation voltage shall be 750 volt AC50HZ.

vi. Rated operational voltage shall be 415 volt AC 50HZ.

Construction

vii. The MCCB should current limiting type with trip time less than 10msec under short circuit

conditions. The operating mechanism shall be quick make quick break type.

viii. The trip unit shall be thermal magnetic type up to 200A and Microprocessor based for rating

above 200 Amp. Thermal magnetic release should provide adjustable settings for O/L and Short

circuit. Microprocessor based release should have adjustable settings for Over Load, Short

Circuit and Earth Fault Protections.

ix. All MCCBs shall be equipped with front operated rotary handles. Outgoing from each of the

MCCB shall be extended to the cable alley by providing necessary busbar of suitable rating and

supports etc. for terminating the outgoing feeders.

x. The MCCB should be provided spreader links and phase barriers

Operation

xi. Push to trip facility shall be provided on the panel door.

VI. AIR CIRCUIT BREAKER(ACB)

General

i. The ACBs shall be suitable for inverter duty applications or as per the design requirements.

ii. The circuit breakers shall comply with IS :13947 Part –II.

iii. The thermal rating of ACBS shall be as required based on the design.

iv. Rated symmetrical breaking capacity, ICS = ICU = ICW for 1 sec at 415 volt, 50HZ shall be not

less than65KARated making capacity (peak) shall be minimum100KA

v. Rated insulation voltage shall be minimum 1000V AC,50HZ.

vi. Rated operational voltage shall be 415 volt AC, 50HZ.

Construction

vii. The air circuit breakers shall be electrically operated microprocessor based draw out type and

four pole version of rating as per requirement and site conditions and SLD.

Operating mechanism

viii. The operating mechanism shall be stored energy spring type with minimum closing time and

with Electrical chargedspring.

ix. Draw out mechanism with safety requirements

x. Positions in draw-out breakers. (Service + Test + Isolated +Maintenance)

xi. Safety shutters shall beprovided

xii. Door interlock shall beprovided

xiii. Locking in isolated position shall beprovided.

xiv. Mechanical indicators: The following mechanical indicators to be provided

xv. Main contacts closed „ON‟.

xvi. Main contacts open„OFF‟. Springcharged.

xvii. Spring discharged.

xviii. Circuit breaker in “Service”position.

xix. Circuit breaker in “Test” position.

xx. Circuit breaker in “Isolated” position.

xxi. Circuit breaker in “maintenance” position.

Characteristic of release

xxii. Microprocessor based release shall have following inbuilt protections:

xxiii. Over current release shall have a minimum range of 0.5 to 1.0 times adjustment.

xxiv. Earth fault release shall have minimum range of 0.2 to 0.5times adjustment.

xxv. Short circuit shall have minimum range of 2 to 8 times adjustment.

Communication and display

xxvi. Release should have inbuilt RS 485 communication port for SCADA connectivity and breaker

control through PC

xxvii. The release should have current display.

xxviii. The release should be provided with Zone Selective Interlocking

xxix. feature to achieve intelligent discrimination between ACBs and to reduce thermal and dynamic

stresses on the ystem

VII. INSTRUMENTATION

Digital meter shall be suitable for panel board mounting. Scale range shall meet with the requirements.

In the case of CT operated ammeters class of accuracy of CTs and protective class shall be as per the

design requirements. CTs used in the work shall be resin cast bar primary or wound primary as the case

may be and shall be in conformity with IS:2705- 1992 or IEC 185-1987. The short time rating of the CT

shall be 100 KA for one second. The burden of the CT shall be suitable for the application.

VIII. THERMAL OVER LOADRELAY

Thermal Overload Relay used in the circuit with contactor shall be in conformity with IS: 3842 part 2-

1966 and it shall withstand insulation test to IS: 12083 part 2. The relay shall be provided with

adjustable current settings and with a provision of sealing the same to make it tamper proof.

The relay shall have built in single phasing protection and over load protection as per IEC947- part 4.

The relay shall have in built NO & NC contact.

The thermal over load relay shall be suitable for Copper / Aluminum termination, with a maximum

permissible temperature rise of 65°C, at the terminals, with maximum ambient temperature of 50°C.

IX. INDICATION LAMPS

The indication lamps used in the work shall be LED Type with protection against electromagnetic

interference and over voltage. The lamps shall be suitable for operation on 240 Volts. Ingress protection

class of the lamp unit shall be IP: 65. The indication lamp unit shall be in conformity with IEC: 947 part

5 Section 1. The diameter of the lamp shall be not more than 22mm.

X. PUSH - BUTTONS

The push buttons shall be in conformity with IEC: 947 part- 5- Section 1 suitable for manual operation.

The ingress protection class of the unit shall be IP 65.

The push button units shall be suitable for operation on 240Volts and the contacts shall be rated for 3 - 5

amps on 240 volts. The color of push buttons shall be as follows:

a. Start PB -Green

b. Stop PB -Red

c. TestPB -Black

Reset PB –Yellow The successful bidder before fabrication of the distribution boards / Panel Boards

shall submit the general arrangement, Schematic, power and control wiring drawings for the approval of

REIL meeting the above specifications/requirements clearly indicating the selection criteria for the

MCBs/MCCBs/ACBs and bus bar sizes etc.

In case, the DC distribution boards are to be mounted on the array structure, then the array structures

shall be designed to meet the mounting load requirements and suitable mounting arrangements to be

provided. Only SS mounting arrangements with accessories shall b used.

All switch boards and panel boards before commissioning shall be tested with 1000 V insulation tester

and the insulation value between the live conductors and frame (ground) should not be less than 20

mega ohms. High voltage test shall be conducted at the factory where the panel boards remanufactured.

XI. INTEGRATION OF PV POWER WITHGRID:

The output power from SPV would be fed to the inverters, which converts DC produced by SPV array to

AC and feeds it into the main electricity grid after synchronization & step up to the required voltage. In

case of grid failure, or low or high voltage, solar PV system shall be out of synchronization and shall be

disconnected from the grid and shall automatically synchronize after grid restoration.

XII. UPS ANDBATTERY

An online UPS of required capacity for providing auxiliary supply to Inverters, with a backup of 30

Minutes minimum shall be supplied for each inverter room. Separate UPS of specified capacity with

battery backup of minimum 30 Minutes shall be provided for catering to the SCADA system. The

system should have the following minimum requirements. The UPS and Battery shall be of approved

make given in the tender and shall confirm to the relevant IS/BS/IEC specifications with up to date

amendments.

a) VRLA Battery with suitable rack

b) Built-in Isolation Transformer

c) UPS load power factor shall be 0.8 ormore

d) Output frequency – 50 Hz, True Sinewave

e) Overall efficiency -85% ormore

f) Input supply 1ph, 230 Volts ± 10%

g) Output Supply power 230V ±1%

XIII. TRANSFORMER

DRY TYPE DISTRIBUTION TRANSFORMERS (SOLAR CONVERTER DUTY)

General Construction

The Transformers shall comply with the following Indian Standards as amended upto date:

(i) IS 11171 : 1985 - Dry type power transformers.

(ii) IS 10028 (Part II & III) - Installation and Maintenance of Transformers.

(iii) IS 2099 - Bushing

(iv) IS 2705 - Current

Transformers. Constructional Features

All the MS parts shall be either Hot dipped galvanized or cold galvanized to make them corrosion free.

The core shall be made up of high grade low loss cold rolled grain oriented silicon steel. Both low &

high voltage windings shall be made of copper conductor. The class of winding insulation shall

correspond to class „F‟. The construction of the windings of the transformer shall be such that no

creepage path is found even in dusty & corrosive ambient conditions. The core coil assembly shall be

housed in a prefabricated enclosure. The enclosure shall be fabricated with mild steel CRCA sheets with

adequate provision for ventilation. The enclosures shall under go the seven tank process. Finally the

external and internal surfaces of the enclosure shall be powder coated with the required paint shade.

General Requirements

The transformer shall be indoor or outdoor type as specified. Unless otherwise specified the transformer

in addition shall have thermal and dynamic ability to withstand external short-circuit as per clause 9 of

IS 2026 (Part I): 1977 and clause 5 of IS 11171:1985.

Continuous rating specified shall be irrespective of tapping position.

Indoor transformers shall be suitable for IP-23 protection; outdoor transformers shall confirm to IP-33

protection.

Temperature Rise

The reference ambient temperatures assumed for the purpose of this specification are as follows:-

1. Maximum ambient air temperature 50°C.

2. Maximum daily average ambient air temperature40°C.

3. Maximum yearly weighted average ambient temperature32°C.

4. Minimum yearly weighted average ambient temperature (-)5°C.

Class of insulation F

The temperature rise limit at the above conditions and at the altitude not exceeding 1000 meters shall be

as specified.

If the site conditions indicated for a particular job is more severe than the referred ambient temperature

mentioned above, the temperature rise above ambient shall be suitably scaled down such that the hot

spot temperature shall not exceed the values for the reference conditions 90°C (F class insulation).

(A) Tap Changing Device

Preferred tapping range is +5% to -7.5% in 2.5 percent steps by means of off load tap changing links or

tap switch. The device shall be provided on HV for HV Voltage to keep LV Voltage constant.

(B) Terminal Markings Connections

Relevant provisions of IS 2026 (Part-IV): 1977 shall be applicable.

Voltage Ratio

Unless otherwise specified, the transformer shall be suitable for a voltage ratio of 11 KV/ 433 V.

Vector Group

In case of step down transformers, the winding connections shall conform to vector group Dy 11 unless

otherwise specified. In case of step up transformer the vector group unless otherwise specified shall be

star / delta.

Cooling

Unless otherwise specified the transformer cooling shall be air and naturally cooled (AN).

Accessories The transformer shall be with enclosure or without enclosure with HV and MV terminations

as specified both on HV and MV side. The MV side shall be suitable to receive bus bar trunking or MV

cable inter-connection suitable for full load current of the transformer.

Fittings

The transformer shall be complete with the following fittings: -

a) Off load type tap changing link or tap switch.

b) RTD temperature controller.

c) Lifting lugs for all transformers.

d) Bi-directional / Unidirectional Rollers to be specified.

e) Rating diagram and terminal marking plate for all transformers.

f) Additional Neutral separately brought out on a bushing for earthing for all transformers.

g) Earth terminals (2 Nos.) for body earthing for all transformers.

Necessary hardware, clamps, lugs etc. for termination on HV/MV etc. for all transformers.

Rating Plates

A rating plate of weather proof material bearing the data specified in clause-8of IS 11171:1985.

Joints and Gaskets

All gaskets used for making gas tight joints shall be of proven material.

Parallel Operation

For parallel operation of transformers, the transformers shall have the same percentage impedance, same

voltage ratio, same vector group, phase sequence etc. Where ever more than one Transformer is to be

installed in the same Sub- Station, capacity of each Transformer shall preferably be same.

Tests at Works

All routine and other tests prescribed in IS 11171 : 1985 shall be carried out at the manufacturer‟s works

before the dispatch of the transformer in the presence of inspecting officer. Copies of the test certificates

shall be furnished to the department. In addition to the prescribed routine tests, temperature rise test shall

be invariably done on one transformer of each design. A copy of the impulse test certificate done on the

same type/design of the transformer shall be furnished in accordance with IS 11171 : 1985 for purpose

of record. If no impulse test was done in an earlier unit of the same design and type, one transformer will

be subjected to impulse test in consultation with the Inspector at the firm‟s cost. Copies of the

certificates of type test for short circuit shall be supplied to the REIL.

Installation and Commissioning

(i) The transformer shall be installed in accordance with IS 10028- Code of practice for Installation

and maintenance of transformer. Necessary support channels shall be grouted in theflooring.

(ii) The transformer shall be moved to its location and shall be correctly positioned.

(iii) All devices shall be checked for satisfactory operation.

All tests of these specifications shall be carried out by the contractor in the presence of inspecting

officer/ consignee free of cost.

Maximum Allowable Power Transformer Losses

Power transformers of the proper ratings and design must be selected to satisfy the minimum acceptable

efficiency at 50% and full load rating. In addition, the transformer must be selected such that it

minimizes the total of its initial cost in addition to the present value of the cost of its total lost energy

while serving its estimated loads during its respective life span.

Total losses for dry type distribution transformers should conform as per the following table:

Maximum allowable losses for dry type distribution transformer with highest voltage for equipment 24

kV, at 50% and 100% of the load

Transformer Capacity (kVA) Maximum Allowable losses at 50% kVA or load Maximum Allowable

losses at full load/Rated kVA

100 1.88% 2.44%

160 1.61% 2.07%

200 1.50% 1.90%

250 1.36% 1.73%

400 1.19% 1.51%

500 1.12% 1.45%

630 1.06% 1.40%

1000 0.90% 1.20%

1600 0.79% 1.05%

2000 0.75% 1.00%

XIV. EARTHING

Each array structure and modules of the PV yard shall be grounded properly as per IEC 60364-7-712

and IS 3043. All metal casing / shielding of the plant shall be thoroughly grounded in accordance with

the Indian Electricity Act. All the components of the PV plant like modules, Junction Boxes & inverters

etc. shall be earthed as per manufacture‟s recommendation. The material used for earthing shall be

copper or hot dip galvanized iron strips. If GI strips are used, joints shall be properly protected against

corrosion by applying bituminous compound and as directed by the Engineer in Charge. Earth electrode

shall be copper clad iron rods or stainless-steel rods with chemical treatment for decreasing earth

resistance. Earthing shall be designed to dissipate fault current for a period of 3seconds.

XV. LIGHTNING PROTECTIONSYSTEM

Advanced Lighting protection shall be provided for the entire plant. Air terminations shall be provided

to the array as required as per the standards practices. The inverter control rooms & SCADA room,

outdoors step up transformers etc. shall also be protected against lightning as per IS 2309(1989).

Lighting protection system shall be provided as per approval of DISCOM & Central Electricity

Authority Statutory requirements.

XVI. ELECTRICALWORKS

A The various electrical works shall be carried out as per latest CPWD Specifications for

Electrical works & applicable IS standards. The Contractor shall submit the following drawings for

approval, before commencing the electrical works

i. Module mounting layout

ii. SMB/SMU cabling layout.

iii. Cabling route from SMB to Inverter

iv. Earthing layout

v. Power Evacuation system.

vi. General arrangement drawing of the inverter rooms and the allied facilities

vii. Layout of complete plant

viii. Advanced Lightning Protection System for the Complete Plant

XVII. Cables:

DC Cables:

i. Should have Multi strand, annealed high conductivity copper conductor. Cables without amour

shall be provided with anti-rodent properties or protection.

ii. All cables shall be 1500 V grade.

iii. PVC type „A‟ pressure extruded insulation

iv. Overall PVC insulation for UV protection and confirm to IEC69947.All cables shall

conform to BIS standards (IS 694) and (IS1554).

iv. The size of each type of cable selected shall be based on minimum voltage drop; continuous

current and short circuit withstand capacity. The maximum drop shall be limited to1.50%.

v. Selected cable should carry the designed current after applying de-rating factors.

vi. All electrical cables / wires of the PV installation to be fixed in accordance with specifications

for electrical works. From protection of Rats, the unarmored cables to be laid the in a GI pipes

of suitable diameter and the same to be fixed neatly to the structure with SS Clamps.

vii. For laying / termination of cables, latest BIS / IEC codes / standards shall be followed.

viii. Copper conductor cables only shall be used up to the size of10sqmm.

ix. Above 16 m² size aluminum or copper conductors can bused.

x. The cables shall be suitable for laying on racks, in ducts, trenches, conduits and underground

(buried) installations with chances of flooding by water. Proper laying of cables has to be

ensured in appropriate cable trays, pipes / trenches as per site requirement.

xi. Chemical Features : Weather resistant, resistant to mineral oils, resistant to acids & alkaline

xii. Thermal Features : Maximum conductor temperature of operation-120° C

xiii. Electrical Features: Voltage rating: 1.5 KV DC, High voltage test: Shall withstand 6.5 KV DC

for 5 minutes.

xiv. Mechanical Features: Resistant to Impact, tear & abrasion, Minimum bending radius – 4 times

of overall diameter, Safe pulling force -50 N/sqmm

XVIII. Power Cables:

HT Cables

All H.T. Cables shall be of 11 KV grade 3 Core XLPE insulated Aluminum Conductor armored U.G

Cables with electrical purity aluminum conductor, shall be manufactured & tested in accordance with IS

: 7098 (Part II). H.T. Cable shall be of earthed, grade and shall be of stranded construction, comply to IS

8130.

Termination Joints

Terminal joints shall be carried out inside the cable end boxes fixed on the equipment. Lugs shall be

fitted by the means of bolts and nuts with the terminal studs. On the glands, amour of the cable shall be

fixed by means of clamps which shall be grounded. Heat shrink/push on type cable termination kit shall

be used for terminations.

Installation of Cables

Cables in the HT Rooms of the Sub-Station shall be laid in trenches. All cables shall be bent in radius

not less than 15 times the diameter of cables or as prescribed by the manufacturer whichever is higher.

Cable laying shall be carried out as per CPWD specifications.

LV 1100 V grade XLPE Insulated Cables

Power cables for use on 415 V system shall be of 1100 volt grade, copper/aluminum conductor, XLPE

insulated, PVC sheathed, armored manufactured and tested as per IS 7098 (Part-1) amended up to date.

Cables without armor shall be provided with anti-rodent properties or protection.

All cables should have identification (marking) in every one-meter interval of length. Bi-metallic plate

washers should be provided wherever cables, lugs, and switch terminals are of different materials.

Cables and cable lugs should be of same material wherever possible.

The size of these cables shall be as per the design criteria, voltage drop not exceeding 1.50% after taking

into consideration of all de-rating factors etc and as per the site requirements. No cable of size less than

4 sq.mm shall bused

XIX. Control Cables & Communication Cables

Control cables for use on 415 V system shall be 1100 volts grade, copper conductor, PVC insulated,

PVC sheathed, steel braided / wire armored cables, strictly as per IS : 1554 (Part I) -1976 amended up to

date. Cables without armor shall be provided with anti-rodent properties or protection.

Control cable carrying current should be black color and voltage circuit shall be of grey color and shall

be segregated.

All cables should have identification (marking) in every one meter interval of length. The size of these

cables shall be as per design and site requirements. However, no cable less than 2.5sqmm shall beused.

Communication cables: Shall be designed, manufactured, tested and installed as per the requirements,

design criteria and meeting the relevant IS/BS/IEC Standards. The cables without armor shall be

provided with anti-rodent properties and protection.

Cable Glands

i. Cable glands shall be of heavy duty double compression type of brass, chrome plated for all

HT & LT Power Distribution Cables.

ii. Cable glands shall have a screwed nipple with conduit electrical thread and check nut as per

the requirement and application.

iii. Cable glands shall be suitable for armored/unarmored cables, which is beingused.

Cable Connectors

Cable connectors, lugs/sockets, shall be of copper/aluminum alloy, suitably tinned, solder-less, crimping

type. These shall be suitable for the cable being connected and type of function (such as power, control

or connection to instruments ,etc.)

G.I. Pipes for Cables

For laying of cables under floor, ground, on array structure etc. G.I. class „B‟ pipes shall be used. MS

conduits are not acceptable for this purpose. All accessories of pipes shall be threaded types.

Size of pipe shall depend upon the overall outer diameter of cable to be drawn through pipe. No G.I pipe

less than 40 mm dia. shall be used for this purpose when cables laid in ground or inside pre- fabricated

structure. To determine the size of pipe, assume that 40% area of pipe shall be free after drawing of

cable.

Cable Identification

For multi core cables PVC ferrule type indicators or tags shall be provided at both the ends for core

identification. For phase identification of 2/3/3.5 core cables coloured PVC tapes shall be used at both

theends.

All cables shall be provided with Al tags of approved design, spaced not less than 8 meters apart and

these shall contain the information on feeder number, Size and No of Coresetc.

Cable laying

LT & HT Power Cables and Control cables shall be laid strictly as per the applicable latest CPWD

Specifications for Electrical - External Works. The depth & width of underground cable trench, sand

cushioning, brick protective covering and earth refilling etc shall be done strictly as per the above

mentioned CPWD specifications for the Cable laying in ground.

Before laying the cables, the cable route drawing with details sectional details of cable trench etc.

meeting the above specified requirements shall be submitted to REIL for approval.

Cables shall be so laid that they will not interface with the other underground structures. All water

pipes, sewage lines or other structures, which becomes exposed by excavation shall be properly

supported and protected from damage until the building has been rammed solidly in places under and

around them. Any telephone or other cables coming in the way are to be properly shielded as directed by

the Engineer-In-Charge. No cable shall be laid below water and sewage lines.

Cables Route Markers

The Cable route markers as per the details given in the schedule of quantize shall be provided and the

same shall be installed as per the relevant CPWD specifications for electrical works with up to date

amendment and as per the instructions of engineer in-charge.

XX. Testing of Cables HT cables

The HT cables after laying shall be tested for the insulation resistance of each core separately with earth

and between the phases. This shall be done with a 5kV insulation tester with valid calibrated certificate.

The insulation resistance readings shall be neatly tabulated and shall be submitted to the Engineer-in-

Charge.

High Pot Test shall be conducted after the laying of the cable as per the standards mentioned and the

reading shall be recorded and submitted to the Engineer prior to the commissioning.

XXI. LT/Control Cables

The LT/Control cables after laying shall be tested for the insulation resistance of each core separately

with earth and neutral and between phases. This shall be done with a 1kV/500 V insulation tester

certified from the electrical inspectorate. The insulation resistance readings shall be neatly tabulated and

shall be submitted to the Engineer-in-Charge.

List of Standards and Codes for Cables;

i. The latest edition of the following standards, codes and specification (but not limited to) shall

apply;

ii. IS: 1753: Specification for aluminum conductors for insulated cables.

iii. IS: 2982: Specification for copper conductors in insulated cables.IS: 5831:

iv. Specification for PVC insulated and sheath of electric cables

v. IS: 6474: Polythene insulation and sheath of electric cables.

vi. IS: 3975: Specification for mild steel wires, strips & tapes for armoring of cables.

vii. IS: 694 : PVC insulated cables.

viii. IS: 1554: Specification for PVC insulated PVC sheathed cables.

ix. IS: 7098: Specification for XLPE insulated PVC sheathed cables.

x. IS: 3961: Recommended current ratings of cables.

xi. IS: 5819: Recommended short circuit ratings for high voltage PVC cables

xii. 11KV H.T. VCBPANEL

(To be installed at Proposed Solar Plant Power House & Existing 11 KV/440V Cattle house

Sub-Station)

The Panel board shall be of indoor and expandable type, having the incoming section alisation

and outgoing switch gear as per IS 13118-1991 of VCB, IEC 62271-100 for Breakers and – 300

for Panels/IS 3427 of switch board. HT panels with accessories shall be designed to conform to

the requirements of the following Indian Standard Specifications with up to date amendments:

i. IS: 13118(1991)

ii. IS: 2516 – Specification for alternating current circuit breakers.

iii. IS: 2147 – Degree of protection provided by enclosures for low- voltage Switchgear -&

Control gear.

iv. IS: 2705 – Current Transformers

v. IS: 1248 – Volt Meter setc.

vi. IS: 3427 – HT Panel

The degree of enclosure protection shall be IP-4X.

Rating

All panels assembled to form a board shall be suitable for the nominal operation voltage and rupturing

capacity as specified. They should be rated as specified with a minimum of 630 Amps. and suitable for

operation on

11KV, 3 phase 50 Hz system. Type test certificate for the breaking capacity of the panel shall be

supplied. A circuit breaker for a given duty in service is best elected by considering the individual rated

values required by load conditions and fault condition.

Type

The HV panel shall be metal clad, indoor, floor, mounting, free standing type. It shall be totally enclosed

dust, damp and vermin proof with provision of future expansion.

XXII. CIRCUIT BREAKER

General Arrangements

The circuit breaker panels shall be complete with the following:-

(a) Racking in / Racking out mechanism.

(b) Isolating plugs and sockets.

(c) Mechanical inter-locks and safety shutters.

(d) Mechanical ON/OFF indicator.

(e) Minimum of 4 NO and 4 NC Auxiliary contacts directly operated by the circuit breaker.

Additional NO & NC contacts can be provided with auxiliary contactors.

(f) Anti condensation space heaters suitable for operation on 240V, 1 Φ 50Hz

(g) Suitable tripping arrangement.

(h) Mechanical counters to assess the total number of operations of the breaker.

Type

The circuit breaker shall be horizontal isolation, horizontal draw out pattern.

XXIII. Breaker Truck

The breaker carriage shall be fabricated from steel, providing a sturdy vehicle for the circuit breaker and

its operating and tripping mechanism. The carriage shall be mounted on wheels, moving on guides,

designed to align correctly and allow easy movement of the circuit breaker and for removing the

carriage for inspection and maintenance purposes. Vacuum interrupters shall be hermetically sealed and

shall be designed for minimum contact erosion, fast recovery of di- electric strength, maintenance free

vacuum interrupter, suitable for auto-reclosing. The drive mechanism shall preferably be provided with

facility for pad locking at any position namely, “Service”, “Test” and “Fully Isolated”. It should be

possible for testing the circuit breaker for its operation without energizing the power circuit in the

“Testing” position. The contacts shall be made only after the breaker is inserted into service position.

Interlocking should prevent contacts from being disconnected if circuit breaker is tried to be moved

from service position.

General Features

Single break contacts are provided in sealed vacuum interrupter.

Rating

The circuit breaker shall be continuously rated as specified with a minimum rated current as per

schedule with voltage rating and breaking capacity as specified.

Operating Mechanism

The operating mechanism shall be one of the following as specified;

Manually operated spring charged/ motor wound spring charged with both mechanical and electrical

release for closing. The operating mechanism shall be trip free.

External auxiliary supply shall be made available for charging motors & heaters operation.

BUS BAR SECTION

General Requirement

The switch board shall be single bus bar pattern with air insulated encapsulated bus bars housed in a

separate compartment, segregated from other compartments.

Material

The bus bars shall be of high conductively electrolytic copper rated as specified with a minimum rated

current of 400 Amps. The bus bar shall be sized for carrying the rated current of 400 Amps. The bus

bars shall be sized for carrying the rated and short circuit current without over-heating. Maximum bus

bar temperature shall not exceed 95 degree C.

XXIV. CURRENT TRANSFORMER

General Requirements

Accommodation shall be provided in the circuit breaker panel to mount one set of three numbers dual

core dual ratio CTs for metering and protection purposes Access to the CTs for cleaning, testing or

changing shall be front, back or top of the panel.

Rating

Dual core & dual ratio CTs of suitable burden shall be preferred with 5 Amps secondary.

Note: CT ratio shall be compatible with the loading patternon HV side. The CTs shall conform to

relevant Indian Standards. The design and construction shall be robust to withstand thermal and dynamic

stresses during short circuits. Secondary terminal of CTs shall be brought out suitably to a terminal

block will be easily accessible for testing and terminal connections. The protection CTs shall be of

accuracy class 5 P 10 of IS 2750- Part III- 1992.

The metering CTs shall conform to the metering ratio and accuracy class 0.5 of IS 2750-1992 for

incomer and class 1 for outgoing Panels.

VOLTAGE TRANSFORMER

General Requirement

A voltage transformer of burden not less than 100 VA and of proper ratio as specified shall be provided

at the incoming panel. The accuracy class for the VT shall be class 0.5 as per IS 3156 parts I to III for

incomer and class 1 for outgoing Panels.

XXV. PROTECTION AND TRIPPING ARRANGMENT

Protection

The Relays shall be microprocessor based numerical relays with O/L,E/F and S/C protection

communicable type with RS 485 port. All Auxiliary relays, master trip relay, trip circuit supervision

relay, transformer protection relay etc shall be of numerical & communicable type Tripping relay shall

be used for tripping signal to the Shunt Trip Coil of Circuit Breaker operating on 24V/30V DC supply /

Power pack/ 110 V VT supply.

Note: 24V/30V DC shall be provided through 2 No. SMF batteries of 12 volts of minimum 180 AH

capacity with a battery charger or higher as per specifications given else where in the document both for

protection as well as indications Relays Over current Relays shall have adjustable setting for current

from 50% to 200% and earth fault from 10% to 40% or 20% to 80%. These should be of manual reset

type. All relays shall have a LED indicator which will indicate operation for each function. It shall be

possible to reset it only by manual operation. The number and relays shall be as specified.

XXVI. WIRING

The wiring shall be carried out with minimum 1.5sq. mm FRLS/HFRS insulted copper conductor cables.

CT wiring shall be done with minimum 2.5sq mm wires with color code: RYB, Gray for auxiliary DC

circuits and Black for auxiliary AC circuits. The wiring shall be securely fixed and neatly arranged to

enable easy tracing of wires. Identification tags shall be fitted to all wire terminals to render

identification easy facilitate checking in accordance with IS 375. Necessary terminal block and cable

entries shall be provided for RTD relay wiring, power supply etc.

XXVII. METERING INSTRUMENT, PANEL ACCESSORIES (DIGITAL)

Metering

Energy metering shall be done as per the requirement.

PT‟s shall be provided on each the bus sections (incomers) with individual metering on each incomer.

Instrument Panels

The instrument panel shall form part of the housing. Relays, meters and instruments shall be mounted as

per general arrangement drawings to be submitted by the tenderer. They shall be preferably of flush

mounting type at a maximum height of 1800 mm.

Instrumentation

A voltmeter of class 1.5 accuracy as per IS-1248 shall be provided at each incomer panel, with selector

switch. The instrument shall be calibrated for the range specified.

Digital tri-vector energy meters of class 1.0 conforming to IS 722 (Part IX) and power factor meter of

class of accuracy of 2 shall be provided, if specified.

Ammeter of specified range of class 1.5 accuracy as per IS-1248 shall be provided at each incomer and

outgoing panels along with necessary selector switches.

The panel assembly shall also take care of the following requirements:

Lamp indication shall be provided to indicate ON/OFF (BY red/green respectively) of switchgear.

Panel illuminating lamp.

Mechanical indication for spring charged status. If possible an indicating lamp could beprovided.

Lamp indicating tripping at fault status.

Healthy trip supply shall be indicated by clear lamp.

Separate fuses/ MCBs shall be provided for lamp, heaters, voltmeters and other instrumentation etc. on

each panel if specified.

Anti- condensation space heater shall be provided, and shall be suitable for operation on 240 V, 1 phase,

50 Hz A.C. for each panel is specified.

Where there is more than one incomer and bus sections, these shall be castle key interlocked as per

interlocking scheme as specified.

CABLE BOXES

Cable boxes shall be situated in a compartment at the rear/ side of the housing as specified.

Cable Entry

Provision for bottom side entry shall be made as per requirement with sufficient head room for cable

termination. 3mm thick, removable gland plate shall be provided for cable termination.

XXVIII. Earthing

The earthing of the breaker body and moving portion shall be so arranged that the earthing of the non-

current carrying structure to the frame earth bar is completed well before the main circuit breaker plugs

enter the fixed house sockets. The entire panel board shall have a common tinned copper earth bar of

suitable section with 2 earth terminals for effectively earthing metallic portion of the panels. The frame

earthing of panel shall be in accordance with section 7 of this specification.

XXIX. Installation

The installation work shall cover assembly of panels lining up, grouting the unites etc. In the case of

multi, panels switch boards after connecting up the bus bar all joint shall be insulated with HV insulation

tape or with approved insulation compounds. A common earth bar shall be run preferably at the back of

the switchboard connecting all the sections for connecting the earth system. All protection, indication &

metering connections and wirings shall be completed. Where trip supply battery is installed the unit shall

be commissioned, completing initial charging of the batteries. All relay instruments and meters shall be

mounted and connected with appropriate wiring. Calibration checks of units as necessary and required

by the licensee like CTs, VTs Energy Meters etc. shall be completed before pre- commission checks are

undertaken.

XXX. TESTING AND COMMISSIONING

Procedure for testing and commissioning of relay shall be in general accordance with good practice.

Commissioning checks and tests shall include in addition to checking of all small wiring connections,

relays calibration and setting tests by secondary injection method and primary injection method. Primary

injection test will be preferred for operation of relay through CTs. Before panel board is commissioned,

provision of the safety namely fire extinguishers, rubber mats and danger board shall be ensured. In

addition all routine megger tests shall be performed. Checks and test shall include following.

(a) Operation Checks and lubrication of all moving parts.

(b) Interlock function checks.

(c) Continuity checks of wiring, fuses etc. as required.

(d) Insulation tests.

(e) Trip test and protection gear tests.

(f) The complete panel shall be tested with 5000V megger for insulation between poles and poles

to earth. Insulation test of secondary of CTs and VT to earth shall be conducted using

500Vmegger.

(g) Any other tests as may be required by the Licensee/ Inspector shall be conducted.

(h) Where specified, the entire switch board shall withstand high voltage test after installation.

(i) Any other test required by the consignee/ inspecting officer.

XXXI. METERING:

Digital Summation Meter of draw out type meter with automatic CT shorting facility to measure

import/export energy of the proposed solar power plant connected to the 11kV panels to be installed in

the 11KV Cattle house substation. Accuracy class shall be 0.2 S. Communication port shall be provided

for data transfer.

The metering panel shall be provided in a separate panel along with all the required CTs, PTs, Cabling,

Instrumentation, Earthing etc. complete as required and as approved by REIL & DISCOM

The successful bidder must take approval/NOC from the Concerned DISCOM for the connectivity,

technical feasibility, and synchronization of SPV plant with distribution network and submit the same to

REIL before commissioning of SPV plant.

Reverse power relay shall be provided by bidder (if necessary), as per the DISCOM requirement.

XXXII. POWERCONSUMPTION:

Regarding the generated power consumption, priority need to give for internal consumption first and

there after any excess power can be exported to grid. Decisions of appropriate authority like DISCOM,

state regulator to be followed in this regard.

XXXIII. PROTECTIONS:

The system should be provided with all necessary protections like earthing, Lightning, and grid

islanding as follows:

XXXIV. LIGHTNING PROTECTION:

The SPV power plants shall be provided with advanced lightning &over voltage protection. The main

aim in this protection shall be to reduce the over voltage to a tolerable value before it reaches the PV or

other sub system components. The source of over voltage can be lightning, atmosphere disturbances etc.

The entire space of the Solar PV Plant occupying the SPV array(s) including transformer yards, invertor

rooms, SCADA room etc shall be suitably protected against Lightning by installing the required number

of Advanced Lightning Arrestors. Lightning protection should be provided as per IEC 62305standard.

The protection against induced high- voltages shall be provided by the use of metal oxide varistors

(MOVs) and suitable earthing such that induced transients find an alternate route toearth. The detailed

advanced lightning protection system along with the engineering drawings covering the area etc. shall be

submitted to REIL for approval meeting the system and contract requirements.

XXXV. SURGE PROTECTION:

Internal surge protection shall consist of three MOV type surge-arrestors connected from +ve and –ve

terminals to earth (via Y arrangement)

XXXVI. EARTHIN GPROTECTION:

Each array structure of the PV yard should be grounded/ earthed properly as per IS:3043-1987. In

addition the lighting arrester/masts should also be earthed inside the array field. Earth Resistance shall

be tested in presence of the representative of REIL as and when required after earthing by calibrated

earth tester.

All PCUs, ACDBs, DCDBs, All HT Panel Boards, Transformers, UPS and other current carrying

equipment installed under the scope of work should also be earthed properly.

Earth resistance shall not be more than 5 ohms. It shall be ensured that all the

Earthing points are bonded together to make them at the same potential.

XXXVII. GRID ISLANDING:

In the event of a power failure on the electric grid, it is required that any independent power-producing

inverters attached to the grid turn off in a short period of time. This prevents the DC-to-AC inverters

from continuing to feed power into small sections of the grid, known as “islands.” Powered islands

present a risk to workers who may expect the area to be unpowered, and they may also damage grid-tied

equipment. The PV system shall be equipped with islanding protection. In addition to disconnection

from the grid (due to islanding protection) disconnection due to under and over voltage conditions shall

also be provided.

A manual disconnect four pole isolation switch beside automatic disconnection to grid would have to be

provided at utility end to isolate the grid connection by the utility personnel to carry out any

maintenance. This switch shall be locked by the utility personnel.

XXXVIII. SAFETY

The following minimum safety measures shall be included as per standard requirements like;

Opto-thermal/Smoke detectors and fire alarm panels in all Inverter rooms and a fire alarm panel in the

inverter room with SCADA control room shall be provided. .

FIRE EXTINGUISHERS:

i. The fire fighting system for the proposed power plant for fire protection shall be consisting of;

ii. Portable fire extinguishers in the control room for fire caused by electrical short circuits.

iii. Fire extinguishers in the inverter rooms, SCADA rooms and transformer area as per the

standards

iv. Sand buckets in the control room.

v. The installation of Fire Extinguishers should confirm to all regulations and BIS standards. The

fire extinguishers shall be provided in the control room housing PCUs as well as on the site

where the PV arrays have been installed.

vi. ISI marked Insulation mats of required thickness and rating to be provided in front of all HT

&LT Panels, Inverters, and UPS etc as per the requirement and regulations of CEA and AP

EA. The insulations mats shall be type tested at CPRI as per the relevant and latest IS/BS

Specifications.

vii. Danger boards should be provided as and where necessary as per IE Act./IE rules as amended

up to date. Three signage‟s shall be provided one each at battery –cum- control room, solar

array area and main entry from administrative block. Text of the signage‟s may be finalized in

consultation with REIL.

The bidder shall take entire responsibility for electrical safety of the installation(s)

includingconnectivitywiththegridandfollowallthesafetyrules&regulationsapplicabl e as per Electricity

Act, 2003 and CEA guidelines etc.

XXXIX. WEATHER MONITORINGSTATION

Weather monitoring station shall be provided in the plant (in the module area) near to the control room

(One of the inverter rooms where SCADA is installed) to monitor;

i. Global Horizontal Irradiance –Pyrometer

ii. Collector plane Irradiance – Pyrometer

iii. Ambient temperature

iv. Module temperature

v. Wind speed/direction

vi. Relative Humidity

vii. Rainfall/Precipitation

viii. Any other parameter that is required as per contract to monitor the performance of Solar PV

System, measure and record the energy generated.

ix. Whether monitoring parameters to be mapped on to the system SCADA along with required

hardware and software for single window monitoring of the complete systemparameters.

XL. SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA)/PLANT

MONITORING

The SCADA shall be designed and installed in the control room and should be provided as part of the

system. SCADA shall be license free and the REIL/authorized agency shall have the absolute ownership

of the SCADA system without any obligation on the part of the REIL/authorized agency, for renewal or

payment of renewal charges for the entire life of the plant.

Additional Necessary software shall also be provided for remote monitoring the SCADA over Internet,

which also will be the part of SCADA system under absolute ownership of the REIL and no annual

renewal / license fee will be paid. The necessary internet through mobile service provider along with the

required hardware and software for remote monitoring of the system performance is included in the

scope of work. The required internet service provider charges during the DLP, CMC and O&M Contract

period is included in the scope of work and nothing extra shall be paid. For monitoring purpose, the

required software in a minimum Three designated Laptops/Desktops of REIL personal is in the scope of

work and nothing extra shall be paid.

XLI. HARDWARE AND ACCESSORIES

The SCADA shall consist of necessary routers / network switch, panels, PLC, analogue & digital I/O

units for PLC and remote terminal units as required. The SCADA system should have additional option

to incorporate future addition of 25%. The PLC shall communicate with different RTUs using Multi

fiber OFC and RTU shall communicate with SMUs and Inverter with most possible high speed channel.

The cost of providing the multi fire OFC and RTUs etc. for the complete Solar PV system is included in

the scope of work and nothing extra shall be paid.

The architecture should be capable of refreshing all analogue parameters at regular intervals of 1 min.

All analogue data shall be logged to non-volatile memory only at 5 minutes interval including time

stamp. Digital inputs should be updated within 5 seconds and all digital inputs such as:

i. Inverters (ON/OFF/Fault Indications)

ii. Transformer parameters

a. Transformer On/ OFF/Fault Indications

b. Winding Temperature Status, Alarm and Trip indications

iii. HT Panel breakers - Status – On/ OFF/Trip

a. Over current/Earth Fault trip indications

b. Under voltage/Over Voltage trip indication

c. Any other relevant indications due to which breaker tripped LT breakers –Status- On/ OFF/ Trip

The above shall be prioritized (as warning and alarm events together with the consultation with the

Engineer-in-charge) to initiate the hooter as required. Digital i/p statuses are also required to be logged

as events with time stamps.

For the supervision and monitoring of the SCADA system two PC systems (one server and one work

station) with latest configuration as approved by the Engineer- in-charge shall be made available with

two 32” LED monitors and a monochromatic laser printer along with required UPS back up at thirty

minutes. Data Acquisition System shall have real time clock and data storage capacity to record data

round the clock for a period of minimum 5 years with 100% back-up. The operating system shall be the

latest version with antivirus

software loaded and shall be renewed at the cost of Contractor till the completion of the defect liability

period, CMC and O&M Contract period i.e., [5 (DLP) + 7] years from the date of completion of work.

The system should have a net facility independent of the client broad band or any other system using a

high speed net dongle which is to be sourced by the agency and renewed by the agency till the end of

defect liability period, CMC and O&M Contract period i.e, 12 years from the date of completion of the

work. The cost of the internet, broadband and data usage charges etc is included in the rate quoted by the

contractor and nothing extra shall bepaid.

SCADA should display the following minimum details;

a) Global horizontal irradiance

b) Irradiance on collector plane

c) Ambient temperature

d) Invertor room temperature

e) Module temperature

f) Wind speed

g) Performance ratio –Day, Week, Month, Quarter andYear

h) Energy generation – Day, Week, Month, Quarter andYear

i) Ambient temperature – Day, Week, Month, Quarter andYear

j) Module temperature – Day, Week, Month, Quarter andYear

k) Invertor room temperature – Day, Week, Month, Quarter andYear

l) Wind Speed – Day, Week, Month, Quarter andYear

m) String and array DC Voltage, Current and Power, Inverter AC output voltage and current (All 3

phases and lines), AC power (Active, Reactive and Apparent), Power Factor and AC energy

(All 3 phases and cumulative) and frequency

n) All electrical parameters (I/V/W,VA,VAR/Wh,Vah,VARh, Power Factor) at different levels

such as string, AJB, Inverter, LT panel and HTpanel.

o) Custom graphs to be generated as per requirement and with any of / multiple metered analogue

parameters in y-axis (Electrical/solar/weather parameters) over a period

of day/week/month/quarter/year.

p) Any other suitable parameter as specified by the Engineer-in-charge.

Graphical comparisons between different parameters shall be made available as a standard

requirement. Historical data shall also be available graphically in the SCADA system when

requested to the system.

A consolidated report shall be generated by the SCADA system automatically at the end of a

predetermined hour at the end of a solar day which should have the following given minimum

parameters for the use of REIL/authorized agency.

a. Units produced /day

b. Cumulative units produced permonth

c. Maximum solar Irradiance during theday

d. Maximum power produced during theday

e. Ambient temperature (Max and Min)

f. Peak Moduletemperature

g. Performance Ratio of theday

h. Power production graph comparing with the solar irradiation during the day( It should be

available within the same axis forcomparison)

i. Graphical representation of solar irradiation and active power in the same time axis.

j. Any other suitable parameters as specified by theEngineer-in-charge

Mimic diagram:

SCADA shall have a mimic diagram of entire plant. It may also incorporate all digital input status

including Breaker/Isolator/Switches in AC/DC side operation, ON/OFF/TRIP indication for equipment‟s

such as;

• String

• Inverter

• Transformer

XLII. TOOLS & TACKLES AND SPARES:

a) After completion of installation & commissioning of the power plant, necessary tools & tackles

are to be provided free of cost by the bidder for maintenance purpose. A list of tools and tackles

to be supplied by the bidder shall be submitted along with theoffer.

b) A list of requisite spares in case of PCU/inverter comprising of a set of control logic cards,

IGBT driver cards etc., Junction Boxes,, Fuses,MOVs / arrestors, MCCBs etc. along with spare

set of PV modules be indicated, which shall be supplied along with the equipment. A minimum

set of spares shall be maintained in the plant itself for the entire period of warranty and CMC

and Operation & Maintenance, which upon its use shall bereplenished.

XLIII. COMPLETENESS OF FACILITIES

All equipment furnished by the Contractor shall be complete in every respect, with all mountings,

fittings, fixtures and standard accessories normally provided with such equipment and/or those needed

for erection, completion and safe operation & maintenance of the equipment and for the safety of the

operating personnel, as required by applicable codes, though they may not have been specifically

detailed in the respective specifications, unless included in the list of exclusions.

All the similar standard components/ parts of similar standard equipment provided shall be

interchangeable with one another.

XLIV. RATING PLATES, NAME PLATES AND LABELS

Each main and auxiliary item of plant including instruments, should have, permanently attached to it in

a conspicuous position, a rating plate of non- corrosive material upon which should be engraved

manufacturer‟s name, equipment, type or serial number together with details of the ratings, service

conditions under which the item of plant in question has been designed to operate and such diagram

plates as may be required by the Employer.

Such name plates/labels should be of white non-hygroscopic material with engraved black lettering or

alternately, in the case of indoor circuit breakers, starters, etc. of transparent plastic material with

suitably coloured lettering engraved on the back. The name plates shall be suitably fixed on both front

and rear sides.

All segregated phases of conductors or bus ducts, indoor or outdoor, should be provided with coloured

phase plates to clearly identify the phase of the system.

Suitable identification marks shall also be provided at site for identifying the modules connected to each

string and identification of strings connected to each string combiner box and so on.

XLV. ELECTRICAL INSPECTORATE APPROVAL

The contractor has to submit an Electrical Schematic diagram showing the equipment is used for the PV

installation and their ratings as per the format required by the AVVNL/CEA. Necessary arrangements

for associating with a licensed and qualified agency for carrying out such works shall be done by the

Contractor. The initial Scheme approval is to be taken for the installation prior to the commencement of

the work.

a. On completion of the work, the Contractor has to obtain necessary safety/energisation

certificate from AVVNL/CEA by submitting necessary completion certificates, drawings,

equipment‟s details, load details, test details, test results etc. The installation can be

commissioned only if the appropriate energisation sanction from the Inspectorate isobtained.

b. All costs incurred in obtaining such approval/certificates “including all statutory fees” etc., are

to be borne by the Contractor. The item mentioned in the schedule of quantities for the same

will cover all the expenses in connection with obtaining AVVNL /CEA approval.

XLVI. SITE ACCEPTANCE TEST(SAT)

a. Contractor shall prepare SAT documentation covering power distribution system in the plant

and system functional testing and submit it in advance and as per stipulated time schedule, for

REIL for review and approval.

Site acceptance test shall be done based on the stipulation in the approved SAT document.

Contractor shall offer fully functional system after successfully commissioning all equipment‟s

for carrying out SAT and submit reports. All the required testing and measuring equipment‟s for

conducting SAT shall be arranged by the Contractor.

A PR Test shall be conducted by the Contractor subsequent to the SAT as specified. The Plant should

run minimum two weeks without any major equipment failure to start the PR test. Contractor shall

submit two copies of O&M manual with soft copy before the start of PR Test.

XLVII. PERFORMANCE RATIO TEST (PRTEST)

a) PR shall be measured for 15 days before taking over the PV plant by the Employer. The PR test

shall be conducted at site by the Contractor in presence of the REIL officials as per IEC 61724. The PR

test procedure shall be submitted by the Contractor for review and approval. Any special equipment,

instrumentation tools and tackles required for the successful completion of the performance test shall be

arranged by the Contractor at his own cost. In addition to the one pyrometer to be supplied & installed

under the scope of work, the contractor shall install one more calibrated pyrometer at horizontal plane at

locations mutually agreed by Contractor and REIL. The additional pyrometer shall be free of cost on

returnable basis.

b) Contractor shall also install data logger to store all the pyrometers data during test period.

A valid test reports for the installed pyrometers shall be submitted by the Contractor for approval to

REIL. The output of both pyrometers mounted on horizontal plane shall be made available at SCADA

during the complete PG test duration i.e. 15 days. During the PG test period, the module tilt shall be

kept as per approved schedule.

c) If the difference of reading between the two horizontally mounted pyrometers exceeds more

than 2%, the test shall be halted and resumed only after rectification of errors which has led to

mismatch. The data of that particular day(s) shall be discarded and test period shall be extended by same

numbers of day(s).

d) The test shall be repeated in case of outage of following equipment for more than 3 days.

i. Converter transformer(s)

ii. Power Conditioning Unit(s)

iii. SCADA and data logger combined

iv. Both pyrometers.

The procedure for PR demonstration test shall be as follows:

a. Weather monitoring station(s) installed in the plant shall be in working condition for minimum

2 weeks and all the parameters shall be available for analysis and verification. The test report for

the calibration shall be submitted by the Contractor for approval.

b. After the successful verification of the initial parameters by REIL, PR test shall be conducted

for 15 consecutive days. Actual energy exported from the plant to substation shall be measured for 15

consecutive days.

Following factors shall be excluded for calculation;

a. Generation loss due to grid outage.

b. Irradiance below 250W/m²

c. The measured global solar radiation of the period of the outage of the power evacuation system

shall be excluded to calculate average global solar radiation for the period of PRtest.

PR Calculation:

PR Calculation:

Performance Ratio (PR)= Final PV System yield (Yf) / Reference Yield (Yr) PR= Yf/Yr

Yf= Plant AC Output (kWh)/Plant Capacity (kWp) Yr= Collector Plane Irradiance (kWh/m²)/Irr Ref

Irr Ref = 1kW/m²

PR Calculation Example (Sample) Plant Capacity:

12000 kWp

January Month Yield: 1812000 kWh

January Month Collector Plane Irradiance: 197.4 kWh/m² Performance Ratio

= 1812000/12000/197.4/1 = 76.49%

Contractor shall demonstrate minimum PR of 75% (measured at the HT panel incomer‟s feeder level

at 11KV/440V (cattle house substation) in the initial PR test of consecutive 15 days. If PR of 75% is not

achieved PR test shall be demonstrated in another consecutive 15 days. If PR is not achieved in the

second chance, Contractor shall correct the plant at his own cost to achieve the minimum PR of 75%.

The plant will be taken over by REIL/authorized agency only after the demonstration of achievement of

the minimum PR of 75% and the date of completion of the project shall be considered as the date of

handing over the plant. In case the contractor is failed to correct the plant at his own cost to achieve the

minimum PR of 75%, the performance bank guarantee submitted by the firm shall been cashed by REIL

in addition to other penalties and liquidated damages as specified elsewhere in the contract.

XLVIII. PROJECT COMPLETION REPORT AND COMPLETION DRAWINGS

After the work is completed, it shall be ensured that the installation is tested and commissioned. All the

test/calibration certificates, detailed operation and maintenance manual (3 sets) shall be submitted to the

Engineer-in-charge before handing over of the system. The Contractor must submit a project completion

report at the time of handing over the plant.

The Contractor shall also submit four sets of "As – Built" drawings, one set reproducible and one set in

CAD version in soft copy to the Engineer- in-charge before handing over the plant. The drawings shall

incorporate the corrections suggested by the Engineer in charge and as per the prescribed guidelines.

The Contractor shall provide a comprehensive information booklet on the equipment supplied. It should

be neatly bound and handed over at the time of handing over of the plant. It should contain the following

information:

Salient features of the system, detailed write up, equipment specification details, model, makes, name

plate details, details of accessories, date of installation/ commissioning, power distribution details,

equipment layouts, cables / panel details, layout of the entire system executed, GA, single line,

schematic diagrams, all factory test reports, Pre commissioning test reports, maintenance and operation

details of the system / machineries, drawings, BOQ as executed with each item, its rate, amount, total

cost etc., It shall be furnished in the following forms:

i. 3 sets of A4 size booklet printed in laser jet printer as hard copy. It shall also include coloured

photographs /catalogues of the equipments/ panels/system etc.

a. 3 sets of CD containing the soft copy of the CAD drawings, write ups etc.all the wiring

diagrams of the respective panels, inverter/control circuits, etc., shall be neatly printed and laminated

and to be provided inside the panels for proper maintenance.

b. The Contractor shall also prepare a Standard Operating Procedure (SOP) which shall be got

approved by the Engineer for the operation and maintenance of the PV plant. The SOP shall take into

consideration the manufacturer‟s instructions/recommendations and preventive maintenance

requirements for their respective products. The Engineer will have the right to suggest any modification

in the SOP and the Contractor shall be bound to incorporate the same in the final approvedSOP.

XLIX. LIQUIDATED DAMAGES DUE TO DECREASE IN PR DURING THE DEFECT

LIABILITY PERIOD & DURING CMC AND O&M CONTRACTPERIOD

a.The Contractor shall be required to evaluate the PR for the entire year during the operation after

handing over the Plant during the entire defect liability period as per the PR Test Method

Specified.

b.During the DLP Period and during CMC and O&M Contract period, the PR Shall conducted once

in six months of every year. However for demonstration of PR during this period, installation of second

pyrometer is not required and the PR Test shall be conducted for a period of 7 days. The acceptable

PR values to be demonstrated by the Contractor at the end of each testing period after accounting for

the degradation are given in the following table;

Sno Period & Year Minimum Guaranteed PR (%)

01 For taking over the PV Plant after completion 75.0

02 During & At the end of Year 1 75.00

03 During & At the end of Year 2 75.00

04 During & At the end of Year 3 74.25

05 During & At the end of Year 4 73.50

06 During & At the end of Year 5 72.77

07 During & At the end of Year 6 72.04

08 During & At the end of Year 7 71.32

09 During & At the end of Year 8 70.61

10 During & At the end of Year 9 69.90

11 During & At the end of Year 10 69.20

The Contractor shall be liable to pay liquidated damages to REIL for loss in revenue due to lower

generation. Monetary compensation shall be computed as the difference between the guaranteed value

and actual value multiplied by the energy tariff at which REIL procures the same from DISCOM plus a

penalty of 10% for the period of six months prior to the conducting the PR Test. Penalty will be charged

if the evaluated PR at the end of each year falls below the stipulated values given in the above table. The

REIL will reserve the right to deduct such penalty from the retention amount of the Contractor or any

other amount during the defect liability period and CMC and O&M Contract period. Decision of REIL

in this regard is final and binding by the contractor.

The amount of solar power generation month wise based on the installed capacity, required performance

ratio, capacity utilisation factor, Global Horizontal Irradiation/Insolation GHI (Month wise), Collector

Plane Irradiation/Insolation CPI (Month wise) & other requirements as specified in the contract and

industry norms etc (as being followed in NTPC & SECI, MNRE & CERC guidelines etc) shall be

worked out and will become the part of O&M Manual to meet the required targets and also base

document for performance monitoring. The O&M Manual shall be prepared by the contractor before

start of CMC and O&M Contract and shall be submitted to REIL for approval.

and LD for shortfall

The Contractor shall maintain monthly plant availability factor of 99% during the O&M period. The

contractor has to ensure all the system of solar power generation plant including HT Power evacuation

and injection components are maintained to the required system availability. In case the system

components are become unserviceable timely action to be taken for repair, rectification and replacement

etc as required. To maintain the required system availability the contractor has to plan and ensure the

timely preventive maintenance and breakdown maintenance and take action before the component fails.

The contractor has to maintain the required spares and consumables to achieve the plant availability

factor of 99% and above.

a. For any shortfall in the monthly plant availability factor w.r.t. the above target value, LD will be

levied as mentioned below. The Plant availability factor shall be calculated as per the details

given in the enclosed Annexure A.

b. As mentioned in the enclosed Annexure A, the following shall be considered while calculating

the Plant availability factor;

i. For the calculation of Monthly plant availability factor, 12 hours per day shall be considered as

the solar time i.e., Monthly solar hours: No of days in a month x 12

ii. The Monthly plant availability factor shall be rounded off to two decimal place.

iii. The plant outage periods due to natural causes like, earth quake, cyclone, flood etc and any

other such force majeure related events shall be excluded while calculating the plant availability

factor. Similarly the plant outage periods due to damage of HT Cables caused by some other

agency in the airport area accidentally shall be excluded.

iv. The planned Preventive Maintenance & breakdown maintenance for the equipment as per the

approved Operation & Maintenance Planner shall be included while calculating the plant

availability factor.

v. The equipment outage, not affecting the generation, will not be considered while calculating the

plant availability factor.

c. For any shortfall in the monthly plant availability factor w.r.t. the below target value 99.0%, LD

will be levied as mentioned below;

Sr No Plant Availability Factor LD Applicable for each month

1 99% & above NIL

2 Below 99% As per the details and sample calculations given at Annexure A

Annexure A

Calculation of Plant Availability Factor & Liquidated Damages

The Plant Availability Factor shall be calculated as per the details given below;

A. Correction Factor for annual degradation (1% every year): (X):

Sno Year of Operation Correction factor annual for degradation

01 1st year 1.00

02 2nd year 0.99

03 3rd year 0.98

04 4th year 0.97

05 5th year 0.96

06 6th year 0.95

07 7th year 0.94

08 8th year 0.93

09 9th year 0.92

10 10th year 0.91

11 11th year 0.90

12 12th year 0.89

B. Correction Factor for monthly generation variance : (Y)

TABLE – B

Month CUF

Correction

factor

Basis of correction factor *

January 1.06 20.21/19.11

February 1.02 19.59/19.11

March 1.12 21.31/19.11

April 1.06 20.31/19.11

May 1.09 20.80/19.11

June 0.96 18.43/19.11

July 0.77 14.65/19.11

August 0.75 14.27/19.11

September 0.87 16.70/19.11

October 1.07 20.43/19.11

November 1.00 19.14/19.11

December 1.01 19.25/19.11

*Monthly CUF / AnnualCUF.

C. Correction Factor for Full / Partial loading due to Full / Partial Equipment outage

TABLE –C

Sr No. Equipment Correction Factor

Ei Wi

1 Total plant shut down other than

grid outage

1

2 Transformer/ Associated HT

panel/ Associated HT cables

1/ Total No of transformers

3 Inverters / Associated switchgear

or cables

1/ Total No of Inverters

4 String monitoring unit* 1/ total No of SMU

5 PV strings* 1/ Total No of PV strings

*In case of outage of DC cable connecting to inverter, all strings connected to SMU shall be treated to

be out.

TABLE – D

a) Monthly corrected Ei X Wi X Correction factor

non availability for degradation

Correction factor for monthly generation variance Y (Table B)

Where Ei = The number of hours of generation loss due to non availability of equipment during solar

hours for the equipment Ei (Refer Table –C above)

Wi = Weight age factor for Equipment Ei (Refer Table-above)

The following shall be considered, while calculating the Plant availability factor;

1) For the calculation of Monthly Plant availability factor, 12 hours per day shall be considered as

the solar time i.e., Monthly solar hours: No of days in a month * 12

2) The Monthly plant availability factor shall be rounded off to two decimal place.

3) The plant outage periods due to natural causes like, earth quake, cyclone, flood etc and any

other such force majeure related events shall be excluded while calculating the plant

availability factor. Similarly the plant outage periods due to damage of HT Cables caused by

some other agency in the airport area accidentally shall be excluded.

4) The planned Preventive Maintenance & breakdown maintenance for the equipment as per the

approved Operation & Maintenance Planner shall be included while calculating the plant

availability factor.

5) The equipment outage, not affecting the generation, will not be considered

while calculating the plant availability factor.

L. Performance Warranty for other equipment / accessories (Except Solar PV Module, Inverter)

The mechanical structures, electrical works including power conditioners/ inverters/ charge controllers/

maximum power point tracker units/ distribution boards/ digital meters/ switch gear/ storage batteries,

cables etc. and over all workmanship of the SPV power plants/ systems must be warranted against any

manufacturing/ design / installation defects for a minimum guaranteed period of 2 years. Original

Equipment Manufacturer certificate in this regard shall be submitted to REIL.

LI. OPERATION AND COMPREHENSE MAINTENANCE CONTRACT (CMC) &

OPERATION& MAINTENANCE(O&M)

The successful bidder shall provide Comprehensive Operation and maintenance of SPV Plant along with

grid connecting system for a period of TEN (7) years from date of successful completion of 5 Years

Defects Liability Period from the date of commissioning/Completion of the plant. During C M C a n d O

& M period, REIL/authorized agency shall have unrestricted entry to the solar plant and Control Room

any time. REIL may suitably depute its personals to associate with O&M activities. Contractor shall

assist them in developing expertise through their day to day O&M activities. All records of maintenance

must be maintained by the contractor which can be accessed by REIL on demand. These records are to

be handed over to REIL after the CMC and O&M period of contract for each year. The Contractor will

be responsible for all the required activities at his own cost for the successful running, optimum energy

generation etc., during the period of CMC and Operation & Maintenance Period of TWELVE years

from the date of handing over the PV plant, which includes the DLP and the following activities and

scope of work is inclusive in the rate quoted by the firm. The CMC and O&M Contract can be extended

for further period of 10 years on mutually agreed terms and conditions. The rate quoted by the bidder

shall be firm and inclusive of increase in the wages of labour year on year etc. and nothing extra shall be

paid and shall inclusive all the scope have mentioned in the schedule of quantities and as detailed below;

The bidder shall be responsible for supply of all spare parts, repairs / replacement of any defective

equipment(s) at his own cost as required from time to time during the CMC and O&M period.

The contractor shall be responsible for the Operation and Maintenance of the entire Solar PV plant

during the CMC and O&M period. The brief scope of works is listed below. The details shall be further

elaborated by the successful bidder in the O&M manual ( SOP) to be submitted to REIL for approval.

Ensuring successful operation of SPV Plant for optimum energy generation.

a) Running the SPV plant for optimum energy generation by maintaining the guaranteed PR and

strictly following the approved SOP. The operating agency has to carry out the maintenance of the

installation as well as to supply and coordinate the man power required for cleaning of the panels and

other maintenance activities as per the approved SOP.

Ensuring Breakdown maintenance, Preventive maintenance overhauls, Arranging visit of O&M experts

(when required) to maximize the availability of the solar plant.

b) Repair and replacement of defective items of the complete plant, which includes all the SPV

Modules, junction boxes, SMUs, Invertors, PCUs, Step up transformers, AC & DC Cables, LT & HT

Cables, LT & HT Panels including all switchgear and control gear and all the equipments and

accessories installed as a part of the complete Solar PV System including SCADA.

c) Daily work of the operators involves logging the voltage, current, power factor, power and

energy output of the SPV plant, temperature, logging down individual array output data once a day.

d) The operator shall record monthly energy output of each array and transformer and reports shall

be prepared on performance of SPV plant.

e) Submission of periodical reports to the owner on the energy generation & operating conditions

of the SPV plant.

f) Monitoring, controlling, troubleshooting, maintaining of records, registers.

g) Supply of all type of spares, consumables and f i x i n g /

application of the same. The contractor shall be responsible for supply all spare parts, repairs /

replacement of any defective equipment(s) at his own cost as required from time to time during CMC

and O&M contract period.

h) Cleaning of the plant including array yard on regular basis and as and when required.

i) Cleaning of drains, cable trenches, box culvert setc

j) Module washing as per as per approved schedule.

k) Herbicide spray and grass cutting on a periodic basis

l) The contractor shall at his own expense provide all amenities to his workmen as per

applicable laws and rules.

m) The Contractor shall ensure that all safety measures are taken at the site to avoid accidents to his

employees or his Co-contractor‟s employees The Contractor shall immediately report the accidents, if

any, to the Engineer In charge & to all the concerned authorities as per prevailing laws of the state.

n) The Contractor shall comply with the provision of all relevant Acts of Central or State

Governments including payment of Wages Act 1936, Minimum Wages Act 1948, Employer's

Liability Act 1938, Workmen's Compensation Act 1923, Industrial Dispute Act 1947, Maturity

Benefit Act 1961, Employees State Insurance Act 1948, Contract Labour (Regulations & Abolishment)

Act 1970 or any modification thereof or any other law relating whereto and rules made there under

from time to time.

o) In order to ensure longevity, safety of the core equipment and optimum performance of the

system the contractor should use only genuine spares of high quality standards.

p) Deployment of Plant in Charge, adequate n u m b e r of technical support staff and other

supporting personnel during the CMC and O&M period. The manpower to be deployed shall be

clearly indicated with assessment, qualification and experience etc in the O&M Manual submission

for approval.

q) In addition to above a computer operator with minimum three years experience in MS Office

(MS Word, MS Excell, MS Power Point) and basic knowledge in Auto CAD to be provided in the

office of REIL/authorized agency on all working days (including Saturdays but excluding Sundays) in

general shift i.e., 09.30hrs to 17.30 hrs for preparation of bills, taking reports and maintenance of

documents etc in soft copies and also in hard copiesetc.

r) Bidder is required to maintain adequate O&M spare during the CMC and O&M contract

period of the Solar PV plant with the view to maximize availability of the plant. The O&M

Manual should clearly address the minimum spares to be maintained at site based on the quantity

installed and criticality of theitem.

s) At the time handing over of the plant by the contractor , the contractor shall Handover

equipment in completely safe, healthy, good working condition without any pending defect.

Failing which, the same shall be rectified at the risk and cost of the contractor.

t) Contractor shall be responsible to carry out all tests and works as required by statutory

regulation in effect as on date of Techno- commercial bid opening during CMC and O&M

period.

u) Any other tasks indicated in the approved SOP/ Operation and Maintenance manuals and for the

successful operation of the PV plant to achieve the guaranteed PR and Availability.

Insurance

The successful bidder has to take and ensure the following insurance policies during the period of CMC

and O&M contract and copies of the same to provided to REIL before release of payment in eachyear;

a. Fire & Allied Perilinsurance:

This insurance shall protect the contractor against all claims applicable under fire and allied peril

insurance. The insurance shall cover the contractor against claims of fire of the all the installations

installed and maintained.

b. Workmen‟s Compensation Insurance:

This insurance shall protect the Contractor against all claims applicable under the Workmen‟s

Compensation Act, 1948 (Government of India). This policy shall also cover the Contractor against

claims for injury, disability disease or death of his or his Sub-Contractor‟s employees, which for

any reason are not covered under the Workmen‟s Compensation Act, 1948. The liabilities shall not be

less than the following:

i. Workmen's Compensation – As per Statutory Provisions

ii. Employee's Liability – As per Statutory Provisions

LIST OF APPROVED MAKE

No

.

Components Approved Makes Category of

Test

Certificate /

Inspection

1 Solar Modules First Solar (USA)/Solar Frontier (Japan)/Avancis

(Germany -Saint Gobain Group) / Sun Power (USA)/

Q Cells (Germany/Korea/Sharp (Japan) / Miasole

(Germany)/ Sanyo (Japan)/ Panasonic (Japan)/ Tata

BP Solar / Vikram solar / BHEL / MoserBear / BEL/

Goldi Green / Waaree/ Topsun /Risen Energy

Note: The module shall strictly meet the specifications

given in technical specifications for the final approval

by AAI.

Category- 1

2 Inverter ABB /Schneider / SMA / TMEIC / Hitachi / Delta Category-1

3 SMU/ String

CombinerBox

Trinity Touch / Weidmuller / Robotina / Skytron /

Hensel /iPLON / Jakson / Respective Inverter

Manufacturer

Category-2

4 Monitoring

System

(SCAD

A)

ABB / Schneider / Siemens / GE /iPLON/Honeywell

/ Allen Bradely

Category-2

5 Transformer Crompton Greaves / AREVA / Kirloskar /Voltamp /

BHEL/kOTSON

Category-1

6 11 KV HT

Panel

withVCB

Areva / Crompton Greaves/ Siemens / Jyoti / ABB/

Schneider / Kirloskar

Category-1

7 a) H.T.

Termination &

JointingKIT.

Ray Chem / M-Seal / Cab Seal / Mahindra / Denson

/ Compaq / Birla-3M

Category-3

b) Cables

Glands

Comet / Dowell / Electromac / Siemens / Braco / HMI /

MCI / (Metal /Craft)

Category-3

c) Lugs &

Thimbles

Dowells / Johnsons / Comet / Ascon Category-4

8 11KV HT

Cable (ISI

Marked)

CCI(Bangalore) / Gloster (Kolkata Hyderabad) / Nicco

(Shyam Nagar WB) / Universal (Satna) / RPG(Asian)

(Mumbai) / ICL(Rajpura)/Torrent (Nadead) /Ravin

(Pune) / Finolex(Pune).

Category-1

9 Up to and including 1.1

KV Cables

A.C/D.C Solar

(IS

I Marked)

CCI(Bangalore) / Gloster (Kolkata Hyderabad) / Nicco

(Shyam Nagar WB) / Universal (Satna) / RPG (Asian)

(Mumbai) / Havells (Rajasthan) / Industrial

Cables(Rajpura/Torrent (Nadiad) / Gemcab (Hyderabad)

/ Hindustan Vidyut Product Ltd (Faridabad) / Plycab

(Dhaman) / Ravin (Pune) / Finolex (Pune) / KEI

(MPCAB) (Gwalior) KEI (Delhi) / AVOCAB

(Ahmedabad) / Ekta (New Delhi / Skytone (Faridabad)

In case of non-availability of the above makes other ISI

make cable shall be opted with the approval of Engg.

Officer not below DGM Engg.(E)

Category-1

10 Control Cables

A.C/D.C Solar

(ISI Marked)

CCI(Bangalore) / Gloster (Kolkata Hyderabad) / Nicco

(Shyam Nagar WB) / Universal (Satna) / RPG (Asian)

(Mumbai) / Havells (Rajasthan) / Torrent (Nadiad) /

Finolex (Pune) / Gemcab (Hyderabad) / Hindustan

Vidyut Product Ltd (Faridabad) / Polycab (Dhaman) /

Ravin (Pune) /KEI (Delhi)/LAPP / Aloke (Ankur

Technocraf)

/AVOCAB (Ahmedabad) / Ekta (New Delhi / Skytone

(Faridabad).

In case of non-availability of the above makes other ISI

make cable shall be opted with the approval of Engg.

Officer not below DGM Engg.(E)

Category-1

11 LT Panels

/

Distributio

n Boards

a) C&S / L&T / Siemens / ABB/ GE Power (Spectra)

/ Schneider / Unilec / Jakson / Milestone/ Godrej / Adlec

/ Tricolite / Sudhir / Neptune / Incotech Engg (P) Ltd. /

subject to having valid CPRI certificate of required fault

levelandIPlevelprotectionatthetimeofplacingorder.

b) By any panel manufacturer having CPRI certificate for

specified fault level and IP level protection at the time

of placingorder

Category-1

12 AIR

Circui

t Breakers

L&T / GE Power /Siemens/ ABB/ Schneider / C&S Category-2

13 Moulded Case

CircuitBreakers

a)L&T / Siemens /Schneider /GE Power / ABB / C&S /

Legrand.

Category-2

14 Digital Meter

s Intelligent

Multifunctiona

l Digital Meter

Converse / Neptune/ HPL/ L&T/ Trinity/

Schneider/ Motwani/ Rishab/ Elmeasure/ Seccure

Category-3

15 Advance

Lighting

Arrester

(Early

Streamer

Emmission

Type/Online

surge arrester)

Indelec/Erico/Duval Massian/ Pheonix / Tercel / Franklin Category-3

16 Lighting

Arraestors

Lamco/ Elaro/ International / Atlas/ Areva/

Oblum/ Alpro/ WS Ind/ Jaipuria/Jayshree

Category-3

17 Relays L&T/ Ducati/ Telemechanique and Control/

Alsphom/ABB / Universal/AVKC / Siemens /BCH

Category-3

18 Protection

Relays

Areva/ Easunreyrolle/ L&T/ ABB/ Siemens Category-2

19 Battery &

BatteryCharge

r

Exide / Amco / Prestolite/ Amaron/ Genpro/

Standard Furukawa/ Lucas/ HBL Nife

Category-3

20 UPS Powerware/ APC/Emerson / Numeric/ DB Power/ Category-2

21 Selector

Switch, Push

Button

Switch /

Emergenc

y Switch

KAY CEE/Controls & Switch Gears / L&T/ GE Power /

Siemense / BCH/ Schenider/ Rockwell (Allen Bradely)/

Teknic.

Category-4

22 LED

Indication

Lamps

AE/ C&S/ VINAY LED/ Easun/ Concord/ KayCee/

Siemens/ Vaishnov/ L&T/ Schenider/ Rockwell

(Allen Bradley)/ Prefine/ BCH

Category-3

23 CT's AE/ Kappa/ Universal/ Kaycee/ IMP/ C&S / L&T/

Meco/ Kapco/ Crompton Greaves/ Pragati/ Omstrams/

Category-3

24 Fire alarm

devices and

control panel

Siemens / Honeywell/ L&T/ Tyco / Bosch Category-2

25 Pyrometer Kipp & Zonnen Category-3

26 G.I PIPES JINDAL / GST / TATA / ZENITH / JST / BST Category-2

27 HDPE PIPE DURALINE / EMTELLE /CARLON /REX Category-2

CATEGORY REQUIREMENT OF TEST CERTIFICATE/INSPECTION

CATEGORY - 1:

Type test certificate for similar item done. If not, one of the items offered is to be

a) type tested.

b) OEMs routine test certificate.

c) Acceptance test to be conducted in the presence of REIL representative at OEMs factory.

CATEGORY - 2:

a) Type test certificate for similar item done. If not, one of the items offered is tobe typetested.

b) OEMs routine testcertificate.

c) Visual and functional check by REIL official at site.

CATEGORY - 3:

a) OEM/Dealer/Contractor routine testcertificate.

b) Visual and functional check by REIL official at site.

CATEGORY - 4:

a) Visual and functional check by REIL official at site.

LII. JET PUMP 1 HP or 1/2 HP (CROMPTON/ KIRLOSKOR/EQUIVALENT )

As per site requirement,1 H.P or 1/2HP BIS approved surface pumps shall be installed for each SPV

Power Plant. Suitable Nos of water outlets shall be provided through B-class ISI Marked GI

Pipes for cleaning of the modules.

LIII. SUPPLEMENTARY AGREEMENT FOR CMC AND O&M CONTRACT

The successful bidder has to enter into a supplementary agreement for All Inclusive Comprehensive Maintenance

and Operation and Maintenance of the Contract with the REIL . The contract period for CMC and O&M of the

Solar PV System installed shall be twelve years, which includes 5 years defects liability period.

The supplementary agreement to be signed before the completion and handing over of the Solar PV

System to beneficiary and the cost of stamp paper (Rs 100.00) shall be borne by the successful bidder.

The supplementary agreement shall be inclusive of REIL general conditions of contract, the relevant

sections of the main agreement and all the related documents and conditions.

Only after signing the supplementary agreement for All Inclusive Comprehensive Maintenance and

Operation and Maintenance of the Contract (For Item no.8 & 9 of SOQ Items), the final bill for the

SITC part i.e., main agreement shall be made.

1. STANDARDS:

The work shall be carried out in the best workmanlike manner in conformity with this specification, the

relevant specifications/codes of practice of Indian Standard Institution, approved drawings and

instructions of the Engineer-in-Charge or his authorized representative issued from time to time. In case

of any conflict between the standards, the instructions of Engineer-in-Charge shall be binding.

LIV. EARTHING NETWORK:

The earthing installation shall be done in accordance with the earthing drawings, specifications and the

standard drawings.. The entire earthing system shall fully comply with the Indian Electricity Act and

Rules framed there under.

LV. TESTING:

Earthing systems/connections shall be tested as follows:

1. Resistance of individual electrodes shall be measured by MEGGER after disconnecting it from

the grid.

2. Earthing resistance of the grid shall be measured after connecting all the electrodes to the

grid. The resistance between any point on the metallic earth grid and the general mass of earth shall

not exceed 1 ohm.

3. The resistance to earth shall be measured at the following:

4. At each electrical system earth or system neutral earth.

5. At each earth provided for structure lightning protections.

6. At one point on each earthing system used to earth electrical equipment enclosure.

7. At one point on each earthing system used to earth wiring system enclosures such as metal

conduits and cable sheaths or armor.

LVI. LIGHTNING PROTECTION:

Lightning protection system shall generally comprise lightning finials (air terminals), roof conductors,

down conductors, test links, and earth electrodes. The number, types, materials and sizes shall be in

accordance with the drawings.

LVII. MISCELLANEOUS MATERIALS SPECIFICATIONS-

Connectors & Termination: Cable terminations shall be made with aluminium/tinned copper crimped

type solder less lugs of M/s Dowells make or approved equivalent for all aluminium conductors and stud

type terminals.

Cable Identification-Cable tags shall be of 2 mm thick, 20 mm wide aluminium strap of suitable length

to contain cable number, equipment no., etc.

Ferrules-Ferrules shall be of approved type size to suit core size mentioned and shall be employed to

designate the various cores of control cable by the terminal numbers to which the cores are connected

for case in identification and maintenance.

Cable Glands- Cable glands to be supplied shall be nickel-plated Brass double compression type

of reputed make.

Cable Trays -This shall be either prefabricated hot dip galvanised sheet steel tray of suitable Size.

Cable Laying

All cable routes shall be carefully measured and cables cut to the required lengths, leaving sufficient

lengths for the final connection of the cable to the terminal of the equipment. The various cable lengths

cut from the cable reels shall be carefully selected to prevent undue wastage of cables.

LVIII. MAINTENANCE SERVICE

Free maintenance services shall be provided by the contractor during the period of 12 years, no

payment will be made on this account as it is included in the cost of I & C and 12 years maintenance

work. This Maintenance service will included such as cleaning of module in every 30 days to

maintain the CUF more than 15% yearly, check loose connection of terminal and nut bolt,

performance of SPV Plant etc. Contractor shall submit maintenance certificate as per schedule.

LIX. PREVENTIVE & ROUTINE MAINTENANCE: -

Contractor will provide maintenance services for a period of 12 years from the date of

commissioning. Preventive maintenance of Solar PV Systems shall be carried out for satisfactory

running. It shall include such checks and maintenance activities at least routine quarterly

maintenance visits and submit quarterly maintenance certificate. which are required to be carried out on

the components of the Solar PV Systems to minimize the breakdown and to ensure smooth and

trouble free running of the Solar PV Systems. Contractor shall be responsible to carry out the

routine & preventive maintenance services and shall provide all labor, materials for the same.

Contractor will submit the maintenance certificate dully signed by customer/ authorized person of

beneficiary as per Annexure- B .

LX. GENERATIONS DETAILS

Vendor shall submit monthly Solar generation details and Solar Meter reading of individual Power

Plant to REIL as per format provided by REIL.

LXI. COMPLETION PERIOD

Supply of BOS, Installation and commissioning of the SPV system should commence immediately

after release of work order and Installation & commissioning should be completed within 3 Month from

the date of work order . The plant will be taken over by the REIL/Beneficiary only after the

demonstration of achievement of the minimum PR of 75% and the date of completion of the project

shall be considered as the date of handing over the plant.

General terms: Contractor shall follow all the provisions as per labour law (including piece rate and

petty contractors) shall comply fully with all laws and statutory regulations pertaining to engagement,

payment and upkeep of labour in India.

GENERAL TERMS & CONDITIONS OF THE CONTRACT

1) AMENDMENT

Except as otherwise provided herein, no addition, amendment to or modification of the Contract shall

be effective unless it is in writing and signed by and on behalf of both parties.

2) SEVERABREILITY

In the event that any or any part of the terms conditions or provisions contained in the Contract shall

be determined invalid, unlawful or unenforceable to any extent such term, condition or provision shall

be served from the remaining terms, conditions and provisions that shall continue to be valid and

enforceable to the fullest extent permitted by law.

3) CONFIDENTIAL TREATMENT

It is understood and agreed that data, know-how and other such proprietary information that was

provided or will be provided by either party, will remain confidential.

4) RELATIONSHIP OF THE PARTIES

REIL relationship with Vendor will be that of a Business Associate, and nothing in this Contract shall

be construed to create a relationship, joint venture, partnership.

5) INDEMNITY

REIL and the Vendor will indemnify, defend, and hold harmless each other and its divisions,

successors, subsidiaries and affiliates, the assigned of each and their directors, officers, agents and

employees from and against all liabilities, claims, losses, and damages of any nature, including,

without limitation, all expenses (including attorney‟s fees), cost, and judgments incident there to

REIL and REIL‟s obligations under this indemnity will survive the expiration, termination,

completion or cancellation of this Contract or an order hereunder.

6) FORCE MAJURE

REIL and the Vendor shall not be under any liability to each other or to any other party in any

way whatsoever for the destruction, damage, delay or any other matters of the nature arising out of

reasons beyond the control of either party, including but not limited to a war, rebellion, civil

commotion, strikes, lock-outs and industrial disputes; fire, explosion, earthquake, Act of God,

flood, drought, bad weather, requisitioning or other act or order by any government department,

council or other constituted body, and similar other reasons.

7) RESTRICTIN ON EMPLOYMENT

Both the parties have agreed that they will not recruit any members of staff of other party directly or

indirectly.

8) ARBITRATION

All disputes arising out of this contract and questions relating to its interpretation etc. shall be

referred to the contract committee headed by ED/GM and if not resolved shall be referred to the sole

arbitration of Managing Director, Rajasthan Electronics & Instruments Ltd., for his decision, which

shall be final and binding on both parties. The Venue of Arbitration proceedings shall be at Jaipur.

9) RISK AND COST

In the event of failure on the part of the contractor in the supply, installation and commissioning of

goods and services, which is required in view of the pending orders, REIL shall be entitled to cancel

the remaining order and procure the outstanding quantity through other sources at risk and costs of the

contractor.

10) TERMINATION OF CONTRACT:

REIL shall be entitled to terminate this Contract, in the event of any or all or any of the

following events, with a written notice of 15 days with due consent of the Vendor:-

i. has abandoned the Contract

ii. has without valid reason failed to complete the projects in respect of the contract.

iii. persistently fails to execute the Contract in accordance with the Contract or

persistently neglects to carry out its obligations under the Contract without just and

proper cause.

11) DURATION OF CONTRACT

This contract shall take effect on the day of execution of this contract and shall endure for the

period of 12 year from date of commissioning and hand over the Power Plant(s) to beneficiary and

renewable as per mutual agreement.

12) GOVERNING LAW

This contract and its validity, interpretation and performance will take effect and be governed

under the laws of India. Venue in any action in law or equity arising from the terms and conditions

of this contract shall be the court of appropriate jurisdiction in Jaipur, Rajasthan (India)

13) PREFERENCE TO MSE

Preference to MSE will be given and procurement from SC/ST and Women Entrepreneurs shall

be done as per the government guidelines. Start Ups are exempted from condition of prior turnover

and prior experience subject to meeting of quality and technical specifications.

14) CONTRACT: Before execution of the work, security deposit be submitted and a contract agreement for execution of

the work shall be signed by the Vendor with REIL within 7 days of LOI from REIL. In case

agreement is not executed within the stipulated time, earnest money will be forfeited.

15) PAYMENTS

Interim bills shall be submitted by the Contractor as stipulated in Schedule F on or before the

date fixed by the Engineer-in-Charge for the work executed since previous bill in accordance

with provision of contract. The contractor shall submit all the bills on the Performa prescribed

by the Engineer-in-Charge, through computerized billing in triplicate as specified in general

conditions of contract. The Engineer-in-Charge shall then arrange to have the bill verified by

taking or causing to be taken, where necessary, the requisite measurements of the work.

However, in case of hidden items, it is responsibility of the contractor to submit the

measurements of the hidden items and get them verified before covering the same during the

progress of the work.

(a) Payment on account for amount admissible shall be made on the Engineer- in-

Charge certifying the sum to which the Contractor is considered entitled by way of interim

payment for the following:

(i) All work executed, after deducting there from the amounts already paid, the security deposit

and such other amounts as may be deductible or recoverable in terms of the Contract;

(ii) The payment due to the contractor shall be made within 15 days of the submission of the bill by

the contractor and the measurements shall be verified by the Engineer-in-Charge or his

representative within 7 days of submission of thebill.

(iii) The bill shall not be entertained if the gross amount of the work done including secured

advance payable is less than Rs. 50.00 lacs except Final Bill. However, this limit can be

relaxed as per the discretion of Engineer-in- Charge, if found reasonable.

For the work done by the agency, R/A bill are to be processed every month. These monthly

bills shall be prepared based on joint measurements on a prefixed date. If the contractor or his

authorized representative does not present/associates for joint measurements, ex-parte

measurements of the work done since previous bill shall be recorded by the Engineer-in-

charge or his authorized representative for the purpose of monthly bill/payments. The bills

shall be submitted on the format prescribed by the Engineer-in-Charge, through

computerized billing in triplicate.

16) PAYMENT SCHEDULE:

a) For Item no.1 of BOQ Items

i. 80% of material value evaluated by Engineer-in-charge shall be released on pro rata basis

after supply is received in good condition and respective payment received from beneficiary.

ii. 90 % of the quoted rate, less the amount already paid as per above, shall be released against

satisfactory erection/ installation on pro-rata basis, as per actual work done and respective

REIL payment received from beneficiary.

iii. 100 % of the quoted rate, less the amount already paid as per above, shall be released after

successful completion of work and submission of As-built completion drawings, O&M

manuals etc., on overall completion of work & handing over and respective REIL payment

received from beneficiary.

b) For Item no. 2 to 7 of BOQ Items for Supply items

i. 90% of quoted rate shall be released on receipt of material supply in good condition and

testing at site and respective REIL payment received from beneficiary .

ii. 100% of quoted rates, less the amount already paid shall be released against Testing &

commissioning and handing over and respective REIL payment received from beneficiary.

c) For Item no. 2 to 7 of BOQ Items for SITC items

i. 70% of quoted rate shall be released on receipt of material supply in good condition and

testing at site and respective REIL payment received from beneficiary.

ii. 90% of quoted rates, less the amount already paid shall be released against satisfactory

installation of items and respective REIL payment received from beneficiary.

iii. 100% of quoted rates, less the amount already paid shall be released against Testing &

commissioning and handing over and respective REIL payment received from beneficiary.

Note: The Cost of O&M period of 12 year including defect liability period of 5 year should

be minimum 20% of Total Quoted price.

d) For Item no. 8 & 9 of BOQ Items (All Inclusive CMC and O&M Contract)

i. Bi - Monthly payment shall be released after completion of each bill period i.e., two months

and respective REIL payment received from beneficiary

17) METERING AND GRIDCONNECTIVITY:

Metering and grid connectivity of the solar PV system under this scheme would be the

responsibility of the Bidder in accordance with the prevailing guidelines of the concerned

DISCOM and / or CEA (if available by the time of implementation).

18) FACTORY INSPECTIONS OFMATERIAL

As specified in the technical specifications the materials which are categorized under

Category 1 for acceptance are to be offered for witnessing the factory inspection. An

advance intimation of at least 30 days for indigenous material and 45 days for imported

material to be given to REIL/Beneficiary for arranging the inspecting authority to witness the

factory acceptance tests (FAT). As for as possible the material to be arranged in one lot for

each type of material for FAT. If it is not possible, then the second lot of inspection shall

be carried out at the cost of the contractor and who will arrange the air fare, local

transportation, lodging and boarding of REIL/beneficiary official to witness the FAT.

Also in case, the materials is not cleared for dispatch due to any technical reasons and

again the FAT is required to be witness by REIL/Beneficiary, the second FAT

shall be conducted at the cost of the contractor as specified above.

19) PROJECT COMPLETION REPORT ANDCOMPLETION DRAWINGS

After the work is completed, it shall be ensured by the contractor /firm to the satisfaction

of the Engineer in charge that the installation is tested and commissioned. All the

test/calibration certificates, detailed operation and maintenance manual (3 sets) shall be

submitted to the Engineer-in-charge before handing over of the system. The Contractor must

submit a project completion report at the time of handing over the plant.

The Contractor shall also submit Three sets of "As Built" drawings and one set in Auto CAD

version in soft copy to the Engineer-in-charge before handing over the plant. The drawings

shall incorporate the corrections suggested by the Engineer in charge. The Contractor shall

provide a comprehensive information booklet on the equipment supplied. It should be

neatly bound and handed over at the time of handing over of the plant. It should contain the

following information:

Salient features of the system, detailed write up, equipment specification details, model,

makes, name plate details, details of accessories, date of installation/ commissioning,

power distribution details, equipment layouts, cables / panel details, layout of the entire

system executed, GA, single line, schematic diagrams, all factory test reports, Pre-

commissioning test reports, maintenance and operation details of the system / machineries,

drawings, BOQ as executed with each item, its rate, amount, total cost etc., It shall be

furnished in the following forms:

a) 3 sets of A4 size booklet containing above as hard copy. It shall also include colored

photographs /catalogues of the equipment‟s/ panels/ system etc.

b) 3 sets of CD containing the soft copy of the drawings and documents as per above para.

All the wiring diagrams of the respective panels, inverter/control circuits, etc., shall be

neatly printed and laminated and to be provided inside the panels for proper

maintenance.

The Contractor shall also prepare a Standard Operating Procedure (SOP) which shall be got

approved by the Engineer In Charge for the operation and maintenance of the PV plant. The

SOP shall take into consideration the manufacturer‟s instructions/recommendations and

preventive maintenance requirements for their respective products. The Engineer in charge

will have the right to suggest any modification in the SOP and the Contractor shall be bound to

incorporate the same in the final approved SOP.

Failing to complete any of the above activity by the contractor, a penalty of Rs. 10,000/- will

be levied by REIL

20) Arrangements to be made by the contractor:

i. In addition to above, one All in One Desk top and having following minimum specifications

shall be provided in the office of beneficiary for remote performance monitoring of the system

along with the required software pre-loaded. The rate quoted by the bidder shall be inclusive of

the same. The system shall be under All Inclusive Comprehensive Maintenance Contract

(including the licensed software‟s) for a period of 12 years from the date of completion of work.

ii. 4th Generation Intel Core i7-6700 processor (3.4 GHz); 23 Inch LED Back Lit Display unit with

anti-glare and FHD resolution; 8GB Dual Channel DDR3L 1600 MHz (4GB x 2) memory; 1TB

5400 RPM SATA Hard drive; AMD Radeon R 7 A 265 2GB DDR 3 video card; Optical DVD

drive; Wireless key board and mouse; Sound card; With licensed windows 10, 64 Bit (English);

Microsoft Office 2016 Latest Microsoft Office and Anti-virus software etc. along with UPS,

Computer table (Godrej make or equivalent) and other accessories complete as required In

addition a computer operator with Minimum three years‟ experience in MS Office (MS Word,

MS Excel & MS Power Point) and with basic knowledge of Auto CAD to be provided during

the execution of project for preparation of bills, maintaining the records and submission of

reports etc. The period of deployment shall be till the completion of final bill of Capital work.

iii. The above system along with pre-loaded MS Project to be provided with in one week of

placement of work order for monitoring the progress of the project work along with the

computer operator as specified above.

21) FORCE MAJEURE: i. Notwithstanding the provisions contained in the Bidding Documents; the Contractor shall not be

liable to forfeit (a) Bid Security for delay and (b) termination of contract; if it is unable to fulfill its

obligation under this Contract due to force majeure conditions.

ii. For purpose of this clause, "Force majeure" means an event beyond the control of the Contractor

and not involving the Contractor's fault or negligence and not foreseeable, either in its sovereign or

contractual capacity. Such events may include but are not limited to Acts of God, wars or revolutions,

fires, floods, epidemics, quarantine restrictions and freight embargoes etc. Whether a "Force majeure"

situation exists or not, shall be decided by REIL and its decision shall be final and binding on the

Contractor. REIL may extend the date of completion for a further period corresponding to the

period of force majeure.

iii. If a force majeure situation arises, the Contractor shall notify REIL in writing promptly, not later

than 7 (seven) days from the date such situation arises. The Contractor shall notify REIL not later than 3

days of cessation of force majeure conditions. After examining the cases, REIL shall decide and grant

suitable additional time for the completion of the work, if required.

22) OTHER TERMS & CONDITIONS:

i Compliance with Regulations and Indian Standard:- All works shall be carried out in accordance

with relevant regulations, both statutory & those specified by the Indian standard related to the works

covered by this specification. In particular the equipment and installation will comply with the

following:-

a. Work man‟s compensation act.

b. Minimum wages Act.

c. Payment wages Act.

d. Contact Labour regulation & abolition Act.

e. ESI, PF & Bonus Act.

f. Regulation under Indian Electricity Rules,

g. Safety & electrical Standard as applicable

ii Watch & Ward:-

The Vendor shall supply material (including REIL SPV Modules) from his godown for

installation work at site, shall continue to be responsible for their safe custody till they are

installed in position, tested, commissioned and handed over to beneficiaries as per format

provided by REIL.

iii Vendor shall arrange for compliance with statutory provision of safety regulation and

departmental requirements of safety codes in respect of labour employed on the work by the

Vendor. Failure to provide such safety requirements would make the Vendor liable for penalty.

The department will make arrangement for the safety requirements at the cost of the Vendor &

recover the cost thereof from him.

iv Company shall not be held liable or responsible for any illness and for physical harm sustained by

the Vendor authorized representative during the execution of this agreement as they will not be

deemed in any manner as employee of the company.

v The Vendor authorized representative shall take due care in handling the SPV system under this

contract. Unwarranted activities, if found any, the company shall be authorized to recover the

same from the Vendor.

vi Correction, over-writing and alteration should be initialed and dated by the Vendor otherwise the

bid is liable to be rejected. The bid shall be typed or written in ink. Unit rates should be

mentioned in the specified format failing which the bids are not likely to be considered.

vii All Vendors shall therefore, furnish declaration that their firm is not involved in any litigation that

may have an impact of affecting or compromising the delivery if services as required under this

assignment. It is also to be declared that their firm has not been black listed by any Central/State/

Public Sector Under takings in India. The declaration should be verified by the Notary Public.

viii The Vendor shall sign these conditions on each page at the end in token of acceptance of all the

terms and it would be attached with the bid along with the declaration mentioned in above. He

should also sign at the bottom of each of the pages of his bid to be submitted.

ix The company reserves the right to visit and inspect any site under this contract at any time and if

defects are noted, payments may be stopped / recovered from Vendor. The company reserves the

right to terminate this contract without giving any notice, if in the opinion of the company, the

performance of the Vendor is not found satisfactory and according to terms stipulated by this

contract.

x The company shall be fully absolved from the third party claims and damages during the

execution of the contract.

xi All disputes arising out of this contract and questions relating to its interpretation etc. shall be

referred to the sole arbitration of General Manager (RE), Rajasthan Electronics & Instruments

Ltd., for his decision, which shall be final and binding on both parties.

xii The contract agreement shall be executed at Jaipur and shall be subject to Jaipur court jurisdiction

alone.

xiii The company shall deduct the TDS as per the Income Tax Act.

xiv The Vendor shall be fully responsible for all repairs of the defects in maintenance

during the period under contract.

23) NO NEAR RELATIVE CLAUSE The bidder should give a certificate that none of his/her near relative is working in REIL as

defined below along with their technical bid as per the attached Annexure . In case of

proprietorship firm certificate will be given by the proprietor. For partnership firm certificate

will be given by all the partners and in case of limited company by all the Directors of the

company excluding Government of India/Financial institution nominees and independent

non-Official part time Directors appointed by Govt. of India or the Governor of the state and

full time Directors of PSUs both state and central. Due to any breach of these conditions by

the company or firm or any other person the tender will be cancelled and Bid Security will

be forfeited at any stage whenever it is noticed and REIL will not pay any damage to the

company or firm or the concerned person. The company or firm or the person will also be

debarred for further participation in REIL‟s Tender. The near relatives for this purpose are

defined as:- (a) Members of a Hindu undivided family. (b) They are husband and wife. (c)

The one is related to the other in the manner as father, mother, son(s) & Son's wife (daughter

in law), Daughter(s) and daughter's husband (son in law), brother(s) and brother's wife,

sister(s) and sister's husband (brother in law).

ANNEXURE -III

RAJASTHAN ELECTRONICS & INSTRUMENTS LIMITED, JAIPUR

S.n. Term Description Complied /

Not

Complied

Deviation

if any

1. GST Tax Extra as applicable.

2. Terms of

payment

As per given in tender document

3. Contract period 12 year from date of commissioning and hand over

the Power Plant(s) to beneficiary

4. Defect liability

period (DLP)

5 year from date of commissioning and hand over the

Power Plant(s) to beneficiary

5.

Generation Detail Vender shall submit the Monthly Solar Generation

details to REIL as per format provided by REIL.

Generation details will record from Solar Meter and

Import-Export reading will record from Net Meter

6. Completion

Period

As per given in tender document/LOI /Work order

7. Rate L1 rate shall be considered on the total amount

including GST.

SIGNATURE WITH STAMP

Annexure -IV

RAJASTHAN ELECTRONICS & INSTRUMENTS LIMITED, JAIPUR

Authorization Certificate

To

Date

Dy. General Manager (Proc.),

Rajasthan Electronics & Instruments Limited,

2, Kanakpura Industrial Area,

Jaipur-302034

Rajasthan

Dear Sir,

We M/s. ……………………..are authorizing M/s. ……………………………….. to submit tender

document in reference to your tender no REIL/RE/19-20/PP/19135 dated …….. for Supply of BOS,

installation-commissioning & 12 year‟s maintenance period of 200kWp grid connected SPV Power

Plant(s) at Rooftop of various Govt. buildings in Udaipur.

On behalf of company ………………………

Name and Designation

Signed and sealed (who has signed the tender)

Annexure -V

Maintenance Certificate

Date-

Name of Site:-

Location of Site:-

Capacity of SPV Power Plant:-

Type of SPV Power Plant :- Grid Connected

Contact Person:-

S.NO

.

DESCRIPTION STATUS REMARK

1. Nos. of SPV Modules & Capacity

2. Cleaning of Modules on

Date……………

3. Nos. of String Inverter & Capacity

4. Sr. No. of String Inverter

5. Nos. of Strings

6. Nos. of Modules in each String

7. Vmp & Imp of Strings Nos. Vmp Imp

8. Reading of String Inverters Power

(kW)

E-Today

(kWh)

Cumulative (kWh)

9. Solar Meter Details

Sr. No.

Make

…………………………..kWh

10. Net Meter Details

Sr.No.

Make

Import kWh Export kWh Net kWh

11. If/Any

It is certified that the Grid Connected SPV Power Plant Capacity of ………….kWp at ……………… (Location)

is working satisfactory.

Signature of REIL

Signature of Beneficiary

Annexure-VI

RAJASTHAN ELECTRONICS & INSTRUMENTS LIMITED, JAIPUR

Tender ref. REIL/RE/19-20/PP/19135

UNDERTAKING OF NO NEAR RELATIVE

To

Date

DGM (PROC),

Rajasthan Electronics & Instruments Limited,

2, Kanakpura Industrial Area,

Jaipur-302034

Rajasthan

Dear Sir,

I………………………………S/o…………………………………… R/o………………………

hereby certify that none of my relatives) as defined in the tender document is/are employed in REIL

unit as per details given in tender document. In case at any stage, it is found that the information

given by m is false/incorrect, REIL shall have the absolute right to take any action as deemed

fit/without any prior intimation to me.

On behalf of company ………………………

Name and Designation

Annexure -VII

RAJASTHAN ELECTRONICS & INSTRUMENTS LIMITED, JAIPUR

Check List

Sr. No. Required Documents Remark

1. Sealed and signed process compliance form. (Annexure-I)

2. Sealed and signed scope of work (Annexure-II)

3. Sealed and signed General terms & conditions of tender (Annexure-III)

4. Authorization certificate ( Annexure-IV)

5. Maintenance certificate format for maintenance period (Annexure –V)

6. Sealed & signed Undertaking of No Near Relative (Annexure VI)

7. Check list (Annexure-VII)

PERFORMA (EMD)

BANK GUARANTEE TOWARDS EARNEST MONEY DEPOSIT

Bank Guarantee No.

Date

To,

Rajasthan Electronics & Instruments Limited, (REIL)

2, Kanakpura Industrial Area Sirsi Road,

Jaipur-302034 (Rajasthan)

Dear Sir,

In accordance with Invitation for Bids under your Bid Document No.………………………… dated

……………).M/s. …………………………………(Bidder Name) having its registered office at

…………......................‟ (hereinafter called the bidder) wish to participate in the said Bid for Supply of

BOS, installation-commissioning & 12 year‟s maintenance period of 200 kW Grid Connected Solar PV

Plant at Titardi, Udaipur ,Rajasthan

As an irrevocable bank guarantee against Bid Security for an amount of Rs.One Lac Fifty Thousand

only (Rs. 1,50,000/- only) valid up to …………………, required to be submitted by the Bidder as a

condition precedent for participation in the said Bid which amount is liable to be forfeited on the

happening of any contingencies mentioned in the Bidding Documents.

We, the …………………………………………………………..(Bank Name & address) guarantee and

undertake to pay immediately on demand by Rajasthan Electronics & Instruments Limited the amount

of Rs. One Lac Fifty Thousand only (Rs. 1,50,000/- only) without any reservation, protest, demand and

recourse. Any such demand made by the „REIL‟ shall be conclusive and binding on us irrespective of

any dispute or difference raised by the Bidder.

This Guarantee shall be irrevocable and shall remain valid up to ……………………..(date of expiry of

Guarantee).. If any further extension of this guarantee is required, the same shall be extended to such

required period (not exceeding one year) on receiving instructions from M/s.

……………………………………………..(Bidder Name) on whose behalf this guarantee is issued.

This guarantee will remain in force up to and including …………………………..(date of expiry of

Guarantee). , and any demand in respect thereof must reach the Bank not later than the above date.

Not withstanding anything contained herein above:

i) Our liability under this guarantee shall not exceed Rs. One Lac Fifty Thousand only (Rs.

1,50,000/- only)

ii) This bank guarantee shall be valid up to ……………….(date of expiry of Guarantee).

iii) We are liable to pay the guaranteed amount or any part thereof under this Bank Guarantee only

and only if we receive from you a written claim or demand on or before …………. (date of

expiry of Guarantee).

The said letter of guarantee has been transmitted through SFMS gateway to your bank. It is advised that

in your own interest, you may verify the genuineness of above letter of guarantee from your bank /

branch.

Dated the date of 2019.

Bank Name

(sealed& signed)

TO WHOM SO EVER IT MAY CONCERN

Bank details of e- payment

1. Name & Address :Rajasthan Electronics & Instruments Ltd., Jaipur

2 Kanakpura Industrial Area Sirsi Road, Jaipur

2. Contact No

: Tel.: (0141) 2470908,

Fax No. 0141-2470531

3. Name of the bankers

: Punjab National Bank, Mid Corporate Branch, M. I. Road, Jaipur

(Raj.) (Branch Code 0221)

4.MICR Code No. : 302024003

5. Bank Account No.

: 0221008700000152 (Cash-Credit account)

6. RTGS/IFSC Code No.

: PUNB 0022100

7. PAN No. : AABCR1528G

8. Service Tax No.

9. TIN No /VAT No.

10. CST No.

11. GST IN

: AABCR1528GST001

: 08202102675

: 1421/02723DT-18.01.1982

: 08AABCR1528G1ZL

Annexure-F Project Report Format

Format for Summary Project Report “Implementation of 200 KW Rooftop mounted Grid connected

Solar PV plant at Cattle House waste processing facility, Titardi . Udaipur”

1. Name of Bidder

2. RFS no.

3. Project details (Site location & Address)

4. Brief about the Rooftop Solar Power Generation System

5. Specifications of the Components and Bill of Material/ Quantities

Sl. no

Component

Specifications Quantity

Make

A Solar PV module

A.1 Aggregate Solar PV capacity (MWp)

B Grid Tie inverter (Type and Capacity)

B.1 Aggregate Inverter capacity (kVA)

C

Module mounting structure (Certified by

a Structural Engineer(Mandatory for this

project )

D Array Junction Box

E AC Distribution Board

F Cable (All type)

G LA &Earthing Kit(maintenance free)

H Meters

I Online monitoring system

J Any other component

K Transformer and Switch Gear

M

Transmission Line from plant substation

to nearby 11 kV GIS

7. Unit cost of solar power generation

8. Cost benefit analysis, payback period

9. Expected output/annum

10. Detailed drawings for plant layout, Plant electrical wiring connections, earthing

arrangement, Structural details and other components etc.

11. Connectivity details with grid and metering arrangement (with sketch diagram)

12. Detailed mounting and lay out drawing of switch yard inside the solar power plant

13. Any other information which may be important but missing from this list

(The above information should be limited up to 2-3 pages only)

Annexure H

Project Completion Report for 200 KW AC Rooftop mounted Grid-Connected solar plant at Titardi

Udaipur

Financial year *:

Approval No. * :

Proposal Title:

Installed by agency:

Project initiated by:

Title of the Project* :

Capacity (MWp)*:

Category of the organization * : Name of the

contact person* :

Address of contact person* :

State* : District/City* :

Mobile* : Email* :

Telephone No. : STD code- Website :

Other info

Electricity Distribution Company

Name :

Electricity consumer account no. as per as on Date :

electricity bill :

project owner:-

Name of Bank:

Name of Branch and Address:

Bank IFSC Code:

9 Digit Micr Code :

Type of Account:

Account No. :

PAN Card Number:

Technology Description & System Design /Specification

(Compliance to BIS/IEC

Standards is mandatory)

1. Module

Capacity/Power of each PV 1. Capacity/Power 1. Nos:

Module(Wp)* : 2. Capacity/Power 2. Nos:

Cumulative Capacity of

Modules( MWp):

Solar cell technology :

Module efficiency (in Percentage) :

2. Inverters

Type of inverter :

Make of inverter :

Capacity/Power of each Capacity/Power

PCU/inverters (VA)* : Nos.

Capacity/Power of PCU/inverters

(KVA) :

Inverter efficiency (Full load) :

(in percentage)

3. Metering Arrangement

Details of Metering

Type of Meter* :

Make of Meter :

5. Other information

Units of electricity generated by the

solar plant as per meter (in KWh):

Monitoring Mechanism :

No. of personnel to be trained in O&M

:

Task & Expected Schedule(in Months)

:

Grid connectivity level

Grid connectivity level phase* : Grid connectivity

level Voltage* :