16
Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective

Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

Rafal Morek

K&L Gates

Contract

Administration. Why?

Contractor’s

Perspective

Page 2: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

Why Contract Administration Matters ?

The Contractor’s Perspective in three points:

1. Number one cause of construction disputes

2. The most important activity in helping to avoid a dispute

3. Eventually, if a dispute is unavoidable, the key obstacle

in turning the Contractor’s claims into cash

or challenging the Employer’s actions

Page 3: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective
Page 4: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective
Page 5: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

The Contractors have difficulty

in turning their claims into cash because:

• failed to keep proper records

• cannot establish cause and effect

• cannot quantify their delay disruption and acceleration claims

• …

Page 6: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

The 2017 FIDIC Suite shall prevent

”messy” Contract administration?

Page 7: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

How the new FIDIC 2017 guides the Contractor

in Contract administration?

• Making use of the contract!

• Enhanced project management tools and mechanisms

• Clarity and certainty

• Balance and reciprocity

• Avoid belated, old or stale claims

More resources on administration needed

Increased risk that if the Contractor does not follow the new

requirements, it will lose its right to make a claim

Page 8: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

How the new FIDIC 2017 guides the Contractor

in Contract administration?

• Sub-clause 8.3: Increased programme requirements

• Sub-clause 14.3(c):

• Every payment application must include

the monthly Progress Report with a detailed description of progress

• Sub-clause 3.8:

• management meetings to promote effective communication; different than

progress meetings (do not replace them)

• Sub-clause 4.20: Progress Reports

• Sub-clauses 1.1.7, 1.1.69 and 4.9:

• Quality Management System & Compliance Verification System

Page 9: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

Early warning

Sub-clause 8.4:

Each Party shall advise the other and the Engineer, and the Engineer shall

advise the Parties, in advance of any known or probable future events or

circumstances which may:

(a) adversely affect the work of the Contractor’s Personnel;

(b) adversely affect the performance of the Works when completed;

(c) increase the Contract Price; and/or

(d) delay the execution of the Works or a Section (if any)

The Engineer may request the Contractor to submit a proposal under Sub-

Clause 13.3.2 [Variation by Request for Proposal] to avoid or minimise effects

of such event(s) or circumstance(s).”

Page 10: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

Contemporary records

• Sub-clause 20.2.3:

• ”records that are prepared or generated at the same time, or immediately

after, the event or circumstances giving rise to the Claim”

• The Contractor’s records may be monitored by the Engineer

who can instruct the Contractor to keep additional contemporary

records

• Higher evidentiary standards for investigation of claims?

Page 11: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

Digital construction reports

• Customized IT / Project records applications

• ”Programming software” in Sub-clause 8.3

• Real-time data

• available and synched among all participants

• also to monitor the records of subcontractors?

• BIM

• Designs and Information

• IP Rights

• Methods of working

Page 12: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

”Equality of Claims” introduced by the 2017 FIDIC

• Under Sub-Clause 2.5 of the 1999 YB the Employer needed only to

notify ”as soon as reasonably practicable after

[it] became aware of the event of circumstance

giving rise to the claim”

• The 2017 Suite places Employer’s claims on equal footing with

Contractor’s claims

• Employer must now issue a notice within 28 days and submit a fully

detailed claim within 42 days • Sub-clause 20.2.1 refers to the ”claiming Party”

Page 13: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

Notices and claims correspondence

• Applies equally to both Employer and Contractor

• Sub-clauses 1.3 & 20.2.1

• shall ”be identified as a Notice” but there is no need to identify or otherwise

include reference to the sub-clause under which it is issued

• Signed by the Contractor’s Representative, Engineer or authorized

representative of the Employer

• delivered to the address stated in the Contract Data

Page 14: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

New time limits and deeming provisions

• Examples:

• Deemed rejection under sub-clause 3.7.3

• Notice of dissatisfaction in respect of the Engineer’s determination under

sub-clause 3.7.5

• Deemed completion of the Works or Section and issue of the Taking-Over

Certificate under sub-clause 10.1

• Claims and Disputes Procedures in clauses 20 and 21

Page 15: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

Prescriptive but not ”bureaucratic”

The 2017 FIDIC promotes:

• Pro-active contract administration

and record keeping

• Communication (increasingly digital)

• Dealing with changes contemporaneously

• Resolving claims and disputes

as early as possible

Page 16: Rafal Morek K&L Gates‚... · Rafal Morek K&L Gates Contract Administration. Why? Contractor’s Perspective . Why Contract Administration Matters ? The Contractor’s Perspective

Thank You for Your Attention!

[email protected]