Rafael Bonchang HVDC Area Manager Alstom Grid England

Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Embed Size (px)

Citation preview

Page 1: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Rafael Bonchang HVDC Area Manager

Alstom GridEngland

Page 2: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Agenda

WHAT IS HVDC

ULTRA HVDC

VSC : A NEW TECHNOLOGY

PROJECT EXAMPLES

Page 3: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Why use HVDC?

• Transmission of bulk power where AC would be uneconomical

• Interconnection between systems which are non -synchronized or weak

• Improvement of AC system performance .

In many circumstances, it is economically and technically advantageous to introduce direct current (DC) links into the electrical supply syste m:

Page 4: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Types of HVDC Configurations

Page 5: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Basic HVDC Transmission

DC linkTransformer

F FHarmonic Filter

(Reactive Power )

ReceivingEnd

SendingEnd

Idc

Vdc

t

Idci

t

i

Iact

i

Iac

InverterRectifier

Page 6: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Point to Point – Overhead Line

DC Line

InverterRectifier

F F

ReceivingEnd

SendingEnd

t

i

t

i

t

i

Bulk Transmission

Page 7: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Point to Point – CableInverterRectifier

F F

ReceivingEnd

SendingEnd

t

i

t

i

t

i

Underwater or Underground

Page 8: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Back to BackReceiving

EndSending

End InverterRectifier

F F

t

i

t

i

t

i

Frequency changingAsynchronous connection

Page 9: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Why Use HVDC?

– Transmission >800km

– Submarine >50km– Frequency

conversion • 50-60Hz

– When synchronism of AC connections is impossible

Station Cost

DC

AC

Break EvenDistance

TransmissionDistance

The Perfect Tool

Page 10: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Up to 3 Times More Power

1850MW 1850MVA 5550MW

More Power Per Tower

DC DCAC

Page 11: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

AC

DC

Charges and DischargesEvery Half Cycle

Only Charges the Cable Once

T7922

Power Transmission Via Cables

Page 12: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Surviving a Black Out

Page 13: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

HVDC Price Trend

0.0

0.5

1.0

1.5

2.0

2.5

3.0

0 100 200 300 400 500 600 700 800 9001000MW

Pric

e (p

u)

Page 14: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Transmission Losses

0.2%

0.7%0.8%

0.0p.u 0.5p.u 1.0p.u0.0%

No-Load LossTransformer Converter Auxiliary

Load LossTransformerConverterFilter

Transmitted Power

Page 15: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

HVDC Valves

Page 16: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Agenda

WHAT IS HVDC

ULTRA HVDC

VSC : A NEW TECHNOLOGY

PROJECT EXAMPLES

Page 17: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

UHVDC Prospects 600kV-800kV

Page 18: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

800 kV Valve

Page 19: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Wall bushing technology

Alstom 820 kV DC gas wall bushing

Page 20: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Agenda

WHAT IS HVDC

ULTRA HVDC

VSC : A NEW TECHNOLOGY

PROJECT EXAMPLES

Page 21: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

What is VSC Transmission

• VSC = Voltage Source Converter• Capacitor normally used as energy

storage• VSC uses Transistor instead of

Thyristor technology

Page 22: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Comparison of Classical HVDC and VSC Transmission

ClassicHVDC VSC

Station Cost

Power Losses

Reliability / Availability

Control of Reactive Power

BLACK START

Footprint

Page 23: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Comparison of Classical HVDC and VSC Transmission

ClassicHVDC

VSC

Proven Experience (Service Life)

Power Range

Long Distance Transmission

Page 24: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Renewables conference, Manchester, Mar 2012

HVDC Off-shore Wind Farms

Off-shore wind farm

HVAC platform

HVDC platform

On-shore HVDC station

HVDC CABLE

Page 25: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Renewables conference, Manchester, Mar 2012

DC Grid Configurations: In-shore Point-to-point System

Page 26: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Renewables conference, Manchester, Mar 2012

DC Grid Configurations: Offshore Grid System

Page 27: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Agenda

WHAT IS HVDC

ULTRA HVDC

VSC : A NEW TECHNOLOGY

PROJECT EXAMPLES

Page 28: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

South Korea - Cheju Island

• 400 MW, ±250 kVdc,

• 122 km submarine cable

• Completion 2013/2014Seoul

S. KOREA

Cheju Island

No. 1

No. 2KEPCO Returns to Alstom Grid for supply of a second,

larger HVDC project

Page 29: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Creating a National Grid in India

• 1 Chandrapur– 2 x 500MW, W-S regions

• 2 Visakhapatnam– 1 x 500MW, E-S regions

• 3 Sasaram– 1 x 500MW, E-W regions

2000 MW supplied by Alstom Grid

3

21

Page 30: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Middle East

• Interconnects– Saudi Arabia

380kV (60Hz)– Kuwait,

Bahrain, Qatar 400kV (50Hz)

• Rating : 3 x 600MW

• Ambient temperature 55°C

Page 31: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

South America : BtB project

• Melo – Uruguay• Interconnects

– 500kV 50Hz Uruguay

– 525kV 60Hz Brazil

• 500MW pole• Turn -key project -

31 months

Montevideo

BRASIL

URUGUAYMelo

Page 32: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

2 x 3150MW bi-poles

• ±600kV• 2375 km

Rio Madeira Project - Brazil

Rio Madeira

Sao Paulo

Page 33: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Power: 2x720MWVoltage DC: +/-300kVdcDistance 200 km

Phase 1: Interconnection in Sweden

Phase 2:Sweden to Norway

EAOW 25 January 2012

Sweden - South West

Page 34: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

Champa India

• +/-800kV 3000MW Bipole

• 1300 km Line Between Champa and Kurukshetra

• Provision to include upgrade to 6000MW at a later date

Page 35: Rafael Bonchang HVDC Area Manager Alstom Grid … use HVDC? • Transmission of bulk power where AC would be uneconomical • Interconnection between systems which are non-synchronized

www.alstom.com