Upload
hesan-rajarani
View
233
Download
0
Embed Size (px)
Citation preview
7/21/2019 R0 Procedure Cendor Bridge
1/65
CENDOR BRIDGE
LOADOUT PROCEDURE
0 21/7/2014 ISSUED FOR REVIEW PRAVEEN EDMUND LEE
REV DATE DESCRIPTION PREPARED CHECKED APPROVED
CONTRACTOR APPROVED COMPANY
7/21/2019 R0 Procedure Cendor Bridge
2/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
CONTENT
1. PROPOSAL DESCRIPTION
2. SCOPE OF WORKS
3. ORGANIZATION CHART
4. TECHNICAL DRAWINGS
Transport Proposal Drawing
Bogie Path Drawing
Pump Location Drawing
5. TECHNICAL DESIGN AND ANALYSIS
Transport Stability Analysis
Ballasting calculation
Trailer Spine Beam Analysis
Ro-Ro Ramp Strength Calculation
6. EQUIPMENT SPECIFICATIONS
Goldhofer Multi-axle Trailer
Ballast Pump
Sample Operator Certificate
Sample Trailer Conformity Certificate
7/21/2019 R0 Procedure Cendor Bridge
3/65
7/21/2019 R0 Procedure Cendor Bridge
4/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
1.4 Transportation
1.4.1 Preparation
Prior to the transportation and roll on operation a few essential preparations need to take
place.
Route PreparationAccess route to be cleared with sufficient clearance and free of sharp objects.Uneven ground to be leveled, compacted and if necessary to be covered with steelplates.
Preparation of structure at site.Final Weight Control Report and COG location must be provided in order toreconfirm the SPMT capacity.Sufficient clearance underneath the structure to be confirmed and free ofobstructions.
Barge HandlingBarge to be positioned to the allocated quay and moored with mooring ropesprovided by client. If required tug boat/s to be ready to keep barge in position inlocation with high cross current.Secured access from quay onto barge to be provided.Client to provide suitable fenders/bumpers for barge contact with quay.
Daily weather forecast to be provided one week prior to load-out operation. Thegeneral environment limitation for loadout operation are as follows:Wind Speed: Beaufort 5 maximum (21 Knots or 10.81meter/sec)Visibility: 100m
Temperature: -5C minimum to 40CGround Surface: Good Traction (Asphalt/Compacted gravel or equivalent)
Following preparation works on barge to be carried out in readiness for load-out tocommence.
Barge Deck PreparationThe transportation route on the deck of transportation barge needs to be cleanedand made free from any obstacles.Trailer path needs to be clearly marked on barge and quay by Client as indicated by
7/21/2019 R0 Procedure Cendor Bridge
5/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
All Goldhofer transporter modules used for this job are presently based in Malaysia.4 possible types can be mobilised for this particular project which are the THP/SL,PST/SL or PST-SLE module. These units can be mobilised by road or by sea andwill arrive on site not later than 2 days before operation is about to commence.Once arrived they will be combined into the desired configurations for the firsttransport and tested. Further details of the transporters can be found in the followingdocument.
The ballasting pumps are usually of the type fitted with a separate Diesel engine foreach individual pump. The pumps have suction and discharge hoses which are 6(150mm) in diameter. The capacity of each pump depend on the suction depth i.e.barge size, but is maximum 400 tonnes per hour. The quantity of pumps used verymuch depends on the weight of the cargo/structure, barge size and tide restrictions.For this loadout operation, thats 10 ballast pumps being used with design capacity250 tonnes per hour.
The barge RO-RO ramp is usually supplied by Air Marine as well and will bemobilised together with the transporters modules. Part of the RO-RO ramp systemis the hinge beam. The hinge beam provides a hinge connection between the rampsand the barge. This beam will be fixed to the barge deck by means of welding byclient with supervision and approval from AM supervisor. Wooden wedges will beplaced loose on either side of the RO-RO ramps in order to allow a smoothtransition. The ramps itself will only be connected minutes before the roll operationcommences.
1.4.2 The transporters
For the task of moving the cargo/structure from its fabrication location into the barge, a
number of axles Goldhofer Self Propelled Transporters will be used. This type of
transporter is fitted with computer controlled steering mechanisms which allow an
unlimited number of separate boogies to be controlled by only 1 operator. The units are
specially designed for this type of ultra heavy movements and are fitted with hydraulic
power packs with large diesel engines. The power packs will generate a large flow ofhydraulic oil which is led to the drive motors fitted in the hubs of the driven axles.
To determine the number of axles to be utilized for a heavy move a number of criteria
will need to be studied and analyzed. This includes, but is not limited to:
7/21/2019 R0 Procedure Cendor Bridge
6/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
Transportation Preparation Works
Following preparation works for SPMT until setting up underneath structure.1.9.1 Upon arrival of SPMT and auxiliary equipments at site, Air-Marine personnel will
offload with Clients cranage and visually checking physical condition in order toidentify damages.
1.9.2 Assembly of SPMT will start with focus on making sure all sensitive hydraulic and
electrical connectors are clean.1.9.3 SPMT will be independently tested for it functions i.e. Steering, hydraulics
suspension, drive and pneumatic braking.1.9.4 After individually driven to position underneath structure, SPMT will
independently raise until it is in contact with structures supports.1.9.5 The SPMT will raise concurrently until all groupings achieve manometers reading
of 100 bars (equivalent to 7.5 Tonnes payload per axle)
1.4.3 Loading and unloadingLoading and unloading of the Module is done using the transporters built in jacking
system. The trailers are simply placed underneath the cargo and then jacked up. This is
done in two steps. First each individual module is jacked up so the top of the trailer is
just touching the bottom of the transport/loadout beam. Subsequently the hydraulics and
the steering connections are made thus interconnecting all trailers together and allowing
operation from a single source. After this is completed the trailers can take up the weight
and the transport operation can commence.
The unloading operation on the barge after loadout is done in opposite order.
One important thing to consider for this is the height of the seafastening grillages on the
barge. As a rule of thumb the height of the cargo/structure should end up exactly the
same as the fabrication height in the yard prior to loadout.
Jacking up of structure and moving towards quayside
1.8.1 A joint final inspection by client and Air-Marines personnel to be carried outaround the structure to identify any loose items such as scaffolding, weldingcables etc. which would fall during transportation.
1.8.2 Before proceeding further, a safety briefing to be conducted and lead by ClientsHSE personnel.
7/21/2019 R0 Procedure Cendor Bridge
7/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
1.8.8 When approaching the quayside, the SPMT and structure to be aligned withmarked pathways leading onto the barge.
1.8.9 If load-out does not commence immediately, the SPMTs will be valve off andpower packs powered down.
1.5 Transportation Criteria
For transportation of any of the cargoes the trailers will always be positioned in such a way
that the self propelled module will enter the barge first. Doing it this way the barge will not be
pushed away by the traction force of the trailer, but pulled towards the quay instead. One
operator who will receive its instructions from the transport superintendent will control the
whole transport operation.
1.6 Roll on and ballasting operation
During the roll on operation the barge will have the tendency to move with the changing
loading on the barge deck as well as the incoming tidal flow. In order to ensure a safeoperation of the roll on operation 3 things will be established:
Roll on operation will take place during an upcoming tide. This in order to have thetide working with the ballasting operation instead of against it.
The barge will be kept level (0o trim angle) by means of deballast the water in thebarge at the stern end during the roll on operation.
The barge deck will be kept between 0mm and 200mm above the quay by means of
de-ballast the water out from the barge at the stern end during the roll on operation.
The amount of water that needs to be pumped in and out of the barges ballast tanks very
much depends on the barge in question and will be calculated for every move. The
calculation will be made for every 9000mm the cargo moves towards the final setting
location. The basis of this calculation is to keep the moment around the LCG of the barge
equal and adjust the barges draft for the upcoming tide thus achieving our objectives.
There will be sufficient spare pump capacity available to keep the barge level with the quayduring the changing tide in case of 50% pump failure, but normally it is physically not
possible to keep the barge at that position 24 hours a day. Generally this is a situation
acceptable for loadouts using transporters.
The duration of the crossover from land to barge will take usually between 20 minutes to
7/21/2019 R0 Procedure Cendor Bridge
8/65
7/21/2019 R0 Procedure Cendor Bridge
9/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
II. If only or two of the leading axles have crossed the RO-RO ramp then it may not benecessary to hold the barge until high water to commence the retrieval operation.
III. The structure will be driven back towards the RO-RO ramp and onto the quay inconjunction with starting the necessary ballast pumps. The movement of thestructure will be intermittent to match the ballasting operation.
IV. Throughout the retrieval operation constant checks will be made on the following: Control clearance (i.e. the gap created, due to the angle of the RO-RO ramp,
between the underside of the RO-RO Ramp and the barge deck);10 mm minimum 100 mm maximum, measured by using a tape measure.
Barge trim (1000 mm maximum) measured by reading pontoon draft marks. Barge heel, (200 mm maximum) measured by monitoring the port and starboard
RORO ramp control clearances. Tide level, measured by reading the quayside tide gauge. Ballast tanks water level, measured by sonic measuring device or tape measure.
V. These checks will be carried out until the trailers and their associated power packsare clear of the RO-RO ramp.
VI. The retrieval operation will follow a complete reversal of the load-out operation.
VII. Performance of the trailers, ballast pumps and moorings will be monitoredthroughout the retrieval operation.
The possibility of postponing or termination of a load-out operation may existand its criteria prior to load-out would most probably include but not limited tothe followings.
1.8.1 Major equipments such as transport, ballast or mooring system become defective
1.8.2 Data relating to the structure and barge is found to have significant differencefrom earlier provided and thus compromising the SPMT loading calculation,drawings and related procedures.
1.8.3 Weather conditions are found to be significantly worse than forecasted.1.8.4 In the event of serious technical difficulties, there are no absolute criteria for
termination of the commencing load-out operation. The decision on whether topull back or continue with the load-out operation would be a joint decision made
7/21/2019 R0 Procedure Cendor Bridge
10/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
1.9.3 Ballast pumps to be dismantled and lifted off the barge using suitable Clientscranage.
2) SCOPE OF WORKS
No DescriptionAi r
MarineCLIENT
1 Preparation
1.1 Preparation of transportation and ballasting procedures
1.2 Supply site & cargo drawings
1.3 Supply accurate weight and center of gravity information
1.4 Moblisation and demobilisation of trailers, pumps and ramps
1.5 Assembly and dismantling of SPMT
1.6 Any ground preparations or civil works required on site
1.7 Any temporary removal of obstructions, lampposts, signs, etc
1.8 Supply suitable transport frames and/or load spreading
1.9Supply suitable loading situation enabling trailer to be positioned
underneath the items to be transported
2 Transportation works
2.1Supply all manpower and supervision required for transportation
k
7/21/2019 R0 Procedure Cendor Bridge
11/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
3 Ballasting works
3.1 Supply of barge suitable for RO-RO and ballasting operation
3.2 Supply RO-RO ramps
3.3 Install & remove RO-RO ramps (welding & cutting)
3.4 Supply main ballasting pumps
3.5 Operate barge's ballasting pumps
3.6 Overall supervision of ballasting procedure
3.7 Supply suitable area for positioning of the pumps
3.8 Supply additional standby pumps
3.9 Barge tank cleaning if required
3.10 Barge gas free certification
3.11 Barge opening and closing of manholes
4 Miscellaneous
4.1 Temporary access for trailer and personnel
4.2 Insurance of Air Marine equipment and manpower
4.3 Insurance of items to be transported
4.6 Diesel for trailers and assist equipment
4.7 Maintenance and repairs of trailers or other Air-Marine equipment
7/21/2019 R0 Procedure Cendor Bridge
12/65
7/21/2019 R0 Procedure Cendor Bridge
13/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
4) TECHNICAL DRAWINGS
Please see the next page
7/21/2019 R0 Procedure Cendor Bridge
14/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
Transport Proposal Drawing
7/21/2019 R0 Procedure Cendor Bridge
15/65
7/21/2019 R0 Procedure Cendor Bridge
16/65
7/21/2019 R0 Procedure Cendor Bridge
17/65
7/21/2019 R0 Procedure Cendor Bridge
18/65
7/21/2019 R0 Procedure Cendor Bridge
19/65
7/21/2019 R0 Procedure Cendor Bridge
20/65
7/21/2019 R0 Procedure Cendor Bridge
21/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
Transport Stability Analysis
7/21/2019 R0 Procedure Cendor Bridge
22/65
Cargo :
Client :
Project : WHEATSTONE LNG
COG cargo
Loadout Beam (cargo sits on top of beams)
Transport beams
Ballast weight (ballast weight in between cargo support)
Total
Combined cog (with trailer, distance measured from trailer deck to cog)
Distance cog (=cog to axle rotation point)
Trailer type
Capacity per line
Own weight per line
Group 1
Group 2
Group 3
Total
Note:
-Stability angles should be higher than 8.0 degrees at all tim e
CENDOR BRIDGE
SAPURA KENCANA
630
X - coordinate Y - coordinate Z-coordinate
(mm) (mm)
300 80
330
Height
(mm)
11653
0
Weight
(tonnes)
250
8
24 110
32 130.94
330.0
9000 -1650
Payload per
(tonnes/m)
45.4616.37
2.78
45.46
(tonnes)
46
32
15.46
1288
1858
1288
15.46
21.75
mm
mm
mm
4.5316.37130.94
Calculation results
(degrees)
angle
StabilityGrd Bearing
Pressure
Distance (d) to
stability triangle
(mm)
4.53
Payload on the
Driving height
Axle rotation pt36
tonnes Centre of gravity
(relative to ground level)
(relative to ground level)
(relative to trailer deck)
tonnes
4
Goldhofer SL
3881 mm
4656 mm
1175
400
-400
(mm)
7142 0 5203
0 0 0
7142
0
0
Transport stability calculation
axleline
8.52
(tonnes) %(tonnes)
68.13 23.66
Own Weight trailer
Calculation input
Y - coordinate No. of axle lines
(mm) (mm)
0
1650
8
89000
0
X - coordinate
7/21/2019 R0 Procedure Cendor Bridge
23/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
Ballasting Calculation
7/21/2019 R0 Procedure Cendor Bridge
24/65
Barge particularsBarge name Length 54.9 m Height 3.66 m
Case descri ition Loadout ballastin Width 18.3 m Li ht shi 560 tonnes
Barge ballasting Cendor Bridge
TWM 56
Ballast tank particulars
Y-coordinate X-coordinate Capacity Y-coordinate X-coordinate Capacity Y-coordinate X-coordinate Capacity
mm mm (m
3
) mm mm (m
3
) mm mm (m
3
)
Combiend center tanksPort side Starboard side
FP -44,802 -11,430 0 -44,802 0 0 -44,802 11,430 0
1 -24,348 -6,050 88 -24,348 0 88 -24,348 6,050 88
2 -16,488 -6,070 237 -16,488 0 240 -16,488 6,070 237
3 -5,498 -6,070 238 -5,498 0 240 -5,498 6,070 238
4 5,462 -6,070 238 5,462 0 240 5,462 6,070 238
5 16,452 -6,070 237 16,452 0 240 16,452 6,070 237
6 24,332 -6,060 88 24,332 0 89 24,332 6,060 88
AP 46,665 -6,060 0 46,665 0 0 46,665 6,060 0
Estimated empty barge freeboard
Water density 1.025tonnes/m3
(fresh water = 1.000, sea water = 1.025)
Estimated barge weight 588 tonnes (inclusive residual water and mud in tanks)
s ma e avg ra . mEstimated avg freeboard 2.98 m
Quay particulars
Height 4.0 m (relative to chart datum)
ax mum a ow . m r
Pumps per hour 250.0m3
Reference: R1-Ballasting Analysis Cendor Bridge.xlsx Page 1 Update: 21/7/2014
7/21/2019 R0 Procedure Cendor Bridge
25/65
Barge ballasting Cendor Bridge
Loads on the empty barge before pre-ballast
No Item Weight X-coordinate Y-coordinate X-moment Y-moment
2 0.0 0.000 0.000 0 0
3
4
5
67
Total 60 0 0
Trailer set upNo Axle lines X-coordinate Distance Axle line load Ttl weight Remarks
1 8 -1521 12750 12.5 100.2 Distance to 1st axle combination
2 8 -3171 0 20.4 163.0 Distance to 1st axle combination
3 8 129 0 20.4 163.0 Distance to 1st axle combination 0 0
0 0
103 0
.
Notes: 0 0
- Distance is to the 1st axle that will enter the barge 90 0
- Y-coordinate 0 = LCG empty barge = 42832mm from barge stern, Positive direction is towards stern 0 0
- Cross over to commence on tide +2m ACD 0 0
- Starboard and Port side center tanks to be filled e ual 0 0
- Axle line load shown included bogie self-weight 0 0
Reference: R1-Ballasting Analysis Cendor Bridge.xlsx Page 2 Update: 21/7/2014
7/21/2019 R0 Procedure Cendor Bridge
26/65
Summary of all Steps
Barge ballasting Cendor Bridge
Step 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Step time 25 18 48 11 10 12 45 89 38 79 4 7 6 6 3 2 54 0 0 0 0 0 0 0 0 0 0 0 0
Total time 25 43 91 102 111 123 168 257 295 374 378 385 391 397 400 402 456 456 456 456 456 456 456 456 456 456 456 456 456
Hei ht 0 2 12 69 117 164 -151 2 157 -6161215 1136 1014 889 775 702 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!Trim 37 19 7 -134 -243 -346 337 358 68 1719 1894 1728 1476 1221 998 852 2280 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
heel Change -372 -297 -297 -22 168 475 123 123 -1944 -1944 -1470 -2568 -3596 -4589 -5090 -5499 -5499 -4147 -4147 -4147 -4147 -4147 -4147 -4147 -4147 -4147 -4147 0 0
Draft 1.96 1.95 2.022.15 2.26 2.36 2.32 1.13 1.22 1.10 0.88 0.86 0.86 0.86 0.90 0.91 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Freeboard 1.69 1.71 1.641.51 1.40 1.30 1.34 2.53 2.44 2.56 2.78 2.79 2.80 2.80 2.76 2.75 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Tide 2.12 2.21 2.452.51 2.56 2.62 2.84 3.28 3.47 3.87 3.89 3.93 3.96 3.99 4.00 4.01 4.28 4.28 4.28 4.28 4.28 4.28 4.28 4.28 4.28 4.28 4.28 4.28 4.28
Max change 103 75 200 45 40 50 186 370 160 330 18 28 26 25 11 10 225 0 0 0 0 0 0 0 0 0 0 0 0
Max rate 250 250 250 250 250 250 250 250 250 250 250 250 250 250 250 250 250 0 0 0 0 0 0 0 0 0 0 0 0
Notes:
- Max change is the maximum change of ballast for the worst case tank
- e max ra e s e pump capac y ava a e on e an w g es pump capac y ns a e n r
Reference: R1-Ballasting Analysis Cendor Bridge.xlsx Page 4 Update: 21/7/2014
7/21/2019 R0 Procedure Cendor Bridge
27/65
7/21/2019 R0 Procedure Cendor Bridge
28/65
Pre-ballasting2.00 m (low tide at day of operation)
2.20 m to et bar e 200mm above the ett
Tide
Freeboard re uired
Barge ballasting Cendor Bridge
1.46 m (Requirement)
0.78 m (to be achieved by ballasting)
1,311 tonnes (After ballasting)
663 tonnes (this is inclusive the load on deck)
0.00 time into the loadout 0Time
Draft change
New displacement
New draft
Ballast change
Y-coordinate Y-moment Y-coordinate Y-moment Y-coordinate Y-moment
(mm) (m ) % Change (tonnesm) (mm) (m ) % Change (tonnesm) (mm) (m ) % Change (tonnesm)
FP -44,802 0 0% 0 0 -44,802 0 #DIV/0! 0 0 -44,802 0 0% 0 0
Tank contents
Starboard side
Tank contents
Port side Combined Center
Tank contents
1 -24,348 0 0% 0 0 -24,348 0 0% 0 0 -24,348 0 0% 0 0
2 -16,488 200 84% 200 -3,380 -16,488 0 0% 0 0 -16,488 200 84% 200 -3,380
3 -5,498 0 0% 0 0 -5,498 0 0% 0 0 -5,498 0 0% 0 04 5,462 0 0% 0 0 5,462 0 0% 0 0 5,462 0 0% 0 0
5 16,452 100 42% 100 1,686 16,452 237 99% 237 3,997 16,452 100 42% 100 1,686
, , ,
AP 46,665 0 0% 0 0 46,665 0 0% 0 0 46,665 0 0% 0 0
Summary 300 361.2 -2,936 15.2 0 300 361.2 2,936
a as ng o a sp acemen , c ua avg ra . mLoad on deck 60 0 Trim changing moment 609 Actual trim 15 cm
0 0 Ballasting Port Side -3,515 Ballasting Starboard Side 3,515Heel Changing Moment 0
Actual bow barge above quay 2 cm Degree of barge heel 0
308 0 0.415 88
Reference: R1-Ballasting Analysis Cendor Bridge.xlsx Page 6 Update: 21/7/2014
7/21/2019 R0 Procedure Cendor Bridge
29/65
7/21/2019 R0 Procedure Cendor Bridge
30/65
Barge ballasting Cendor Bridge
Step 1: Y= Axle no 6 on barge stern42832
Trailer no
No of axlelines on the barge 0 6 6 0 0 0 (of each trailer)
Load on deck 0.0 122.2 122.2 0.0 0.0 0.0 244.4 (all axle lines together which are on the barge)
Y-coordinate of load 0 -22932 -22932 0 0 0 (combined loads all axlelines on the barge)
Moment caused by trailer 0 -2803 -2803 0 0 0 -5,605 (over stern of the barge, x direction only)
Tide 2.12 m (low tide at day of operation)
Freeboard required 2.08 m (to get barge 200mm above the jetty)
Time 25 minutes (time into the loadout)
Port side Starboard sideCombined Center
Y-coordinate Y-moment Y-coordinate Y-moment Y-coordinate Y-moment
(mm) (m3) % Change (tonnesm) (mm) (m
3) % Change (tonnesm) (mm) (m
3) % Change (tonnesm)
FP -44,802 0 #DIV/0! 0 0 -44,802 0 #DIV/0! 0 0 -44,802 0 #DIV/0! 0 0
1 -24,348 0 0% 0 0 -24,348 0 0% 0 0 -24,348 0 0% 0 0
2 -16,488 97 41% -103 -1,639 -16,488 0 0% 0 0 -16,488 97 41% -103 -1,639
Tank contentsTank contentsTank contents
- , - , - ,
4 5,462 0 0% 0 0 5,462 0 0% 0 0 5,462 0 0% 0 0
5 16,452 190 80% 90 3,204 16,452 237 99% 0 3,997 16,452 190 80% 90 3,204
6 24,332 0 0% 0 0 24,332 0 0% 0 0 24,332 0 0% 0 0
AP 46,665 0 #DIV/0! 0 0 46,665 0 0% 0 0 46,665 0 #DIV/0! 0 0
16
Summary 90 13
Ballasting 52 848 7,126 Ttl displacement 1,740 Actual avg draft 1.96 m
Load on deck 304 -5,605 Trim changing moment 1,521 Actual trim 37 cm
X-Moment Trailer -372 Ballasting Port Side -3,362 Ballasting Starboard Side 3,362Heel Changing Moment -372
Actual bow barge above quay 0 cm
Reference: R1-Ballasting Analysis Cendor Bridge.xlsx Page 8 Update: 21/7/2014
7/21/2019 R0 Procedure Cendor Bridge
31/65
Barge ballasting Cendor Bridge
Step 1: Y= 42832 Axle no 6 on barge stern
. . . . . . . . . .
0% 0% #DIV/0! 0% 80% 0% 0% 41% 0% #DIV/0!
3.66 3.66 #DIV/0! 3.66 0.73 3.66 3.66 2.16 3.66 #DIV/0!
Ballasting Deballasting
.C .C AP.C 6.C 5.C 4.C 3.C 2.C 1.C FP.C
0% 0% 0% 0% 99% 0% 0% 0% 0% #DIV/0!
3.66 3.66 3.66 3.66 0.05 3.66 3.66 3.66 3.66 #DIV/0!Bow
Stern
Ballasting Deballasting
3.66 3.66 #DIV/0! 3.66 0.73 3.66 3.66 2.16 3.66 #DIV/0!
0% 0% #DIV/0! 0% 80% 0% 0% 41% 0% #DIV/0!
.S .S AP.S 6.S 5.S 4.S 3.S 2.S 1.S FP.S
Notes:
- information shown is after end of the step
- Action shown is after reaching desired situation Draft = 1.96 m
- Measurement in m is distance from deck to water level
Reference: R1-Ballasting Analysis Cendor Bridge.xlsx Page 9 Update: 21/7/2014
7/21/2019 R0 Procedure Cendor Bridge
32/65
7/21/2019 R0 Procedure Cendor Bridge
33/65
Barge ballasting Cendor Bridge
Step 2: Y= 38632 Axle no 12 on barge stern
. . . . . . . . . .
0% 0% #DIV/0! 0% 70% 0% 0% 9% 0% #DIV/0!
3.66 3.66 #DIV/0! 3.66 1.11 3.66 3.66 3.32 3.66 #DIV/0!
Deballasting Deballasting
.C .C AP.C 6.C 5.C 4.C 3.C 2.C 1.C FP.C
N
3.66 3.66 3.66 3.66 0.05 3.66 3.66 3.66 3.66 #DIV/0!STER
BO
3.66 3.66 #DIV/0! 3.66 1.11 3.66 3.66 2.86 3.66 #DIV/0!
0% 0% #DIV/0! 0% 70% 0% 0% 22% 0% #DIV/0!
.S .S AP.S 6.S 5.S 4.S 3.S 2.S 1.S FP.S
Notes:
- information shown is after end of the step
- Action shown is after reaching desired situation Draft = 1.95 m
- Measurement in m is distance from deck to water level
Reference: R1-Ballasting Analysis Cendor Bridge.xlsx Page 11 Update: 21/7/2014
7/21/2019 R0 Procedure Cendor Bridge
34/65
Barge ballasting Cendor Bridge
Step 3: Y= All axles at final position24319Trailer no
No of axlelines on the barge 8 8 8 0 0 0 (of each trailer)
Load on deck 100.2 163.0 163.0 0.0 0.0 0.0 426.1 (all axle lines together which are on the barge)
Y-coordinate of load 2830 11830 11830 0 0 0 (combined loads all axlelines on the barge)
Moment caused by trailer 283 1928 1928 0 0 0 4,139 (over stern of the barge, x direction only)
Tide 2.45 m (low tide at day of operation)
Freeboard required 1.75 m (to get barge 200mm above the jetty)
Time 91 minutes (time into the loadout)
Combined CenterPort side Starboard side
-coor na e -momen -coor na e -momen -coor na e -momen
(mm) (m3) % Change (tonnesm) (mm) (m
3) % Change (tonnesm) (mm) (m
3) % Change (tonnesm)
FP 0 0 0% 0 0 -44,802 0 0% 0 0 -44,802 0 0% 0 0
1 -24,348 0 0% 0 0 -24,348 0 0% 0 0 -24,348 0 0% 0 02 -16,488 222 94% 200 -3,752 -16,488 0 0% 0 0 -16,488 252 106% 200 -4,259
- - -
an con en s an con en s an con en s
, , ,
4 5,462 0 0% 0 0 5,462 0 0% 0 0 5,462 0 0% 0 0
5 16,452 5 2% -160 84 16,452 237 99% 0 3,997 16,452 5 2% -160 84
6 24,332 0 0% 0 0 24,332 0 0% 0 0 24,332 0 0% 0 0
AP 46,665 0 0% 0 0 46,665 0 0% 0 0 46,665 0 0% 0 0
Summary 160 40
Ballasting 739 -3,845 Ttl displacement 1,813 Actual avg draft 2.02 m
Load on deck 486 4,139 Trim changing moment 294 Actual trim 7 cm
X-Moment Trailer -648 Ballasting Port Side -2,659 Ballasting Starboard Side 3,011Heel Changing Moment -297
Actual bow barge above quay 12 cm
Reference: R1-Ballasting Analysis Cendor Bridge.xlsx Page 12 Update: 21/7/2014
7/21/2019 R0 Procedure Cendor Bridge
35/65
7/21/2019 R0 Procedure Cendor Bridge
36/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
Trailer Spine Beam Analysis
7/21/2019 R0 Procedure Cendor Bridge
37/65
7/21/2019 R0 Procedure Cendor Bridge
38/65
9M BEAM 9M BEAM
AM/KHL/CDW
7/21/2019 R0 Procedure Cendor Bridge
39/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
Ro-Ro Ramp Strength Calculation
7/21/2019 R0 Procedure Cendor Bridge
40/65
7/21/2019 R0 Procedure Cendor Bridge
41/65
AM/KHL/CDW-
7/21/2019 R0 Procedure Cendor Bridge
42/65
KENCANAHLSDNBHDAM/KHL/CDW
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
6) EQUIPMENT SPECIFICATIONS
Please see the next page
KENCANA HL SDN BHDAM/KHL/CDW-
7/21/2019 R0 Procedure Cendor Bridge
43/65
KENCANAHLSDNBHDAM/KHL/CDW
BDG/M
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
Goldhofer Multi-axle Trailer
7/21/2019 R0 Procedure Cendor Bridge
44/65
7/21/2019 R0 Procedure Cendor Bridge
45/65
7/21/2019 R0 Procedure Cendor Bridge
46/65
7/21/2019 R0 Procedure Cendor Bridge
47/65
BALLASTING
7/21/2019 R0 Procedure Cendor Bridge
48/65
BALLASTING
Pump dimensions
7/21/2019 R0 Procedure Cendor Bridge
49/65
7/21/2019 R0 Procedure Cendor Bridge
50/65
7/21/2019 R0 Procedure Cendor Bridge
51/65
RORO RAMP
7/21/2019 R0 Procedure Cendor Bridge
52/65
RORO RAMP
Barge ro-ro ramp and wedge dimensions
RORO RAMP
7/21/2019 R0 Procedure Cendor Bridge
53/65
Barge ro-ro ramp arrangement
7/21/2019 R0 Procedure Cendor Bridge
54/65
7/21/2019 R0 Procedure Cendor Bridge
55/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
7/21/2019 R0 Procedure Cendor Bridge
56/65
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
Sample Trailer Certif icate
7/21/2019 R0 Procedure Cendor Bridge
57/65
KENCANAHLSDNBHDAM/KHL/CDW-
BDG/M
7/21/2019 R0 Procedure Cendor Bridge
58/65
CENDORBRIDGESECTION2LOADOUTPROCEDURE Revision:0
7) JOB SAFETY ANALYSIS
7/21/2019 R0 Procedure Cendor Bridge
59/65
7/21/2019 R0 Procedure Cendor Bridge
60/65
No When things can happen Potential risk / hazardHow to avoid / counter re-act / plan
contingency
Job Safety AnalysisLoadout operations
I)Transporter assembly done in time to allow last
minute dispatch of small parts
II)Insist on flexibility from independent
subcontractors to use each other's tools/parts
I)Make sure not all transporters arrive at the
same time
II)Carefully plan quantity of assist equipment
required and closely follow up
III)Client to dedicate certain quantity of assist
equipment for this purpose
I) Clearly request and monitor the required space
II)Double check space available at least 3 days
prior to positioning date
I)
The supports are to be very precicely positioned
in line for positioning of long trailers with
sufficient gaps
II)Client to have a set of jacks on standby for last
minute required changesI)
Mobilise at least 2 pcs additional beams other
than required for contingency purpose
II)Have sufficient hardwood jacking timber on
standby for last minute adjustments/shimming
2)During assembly and dismantling of the
transporters at site
b)Not sufficient assist equipment (eg crane,
forklift) available at site
a) Some transporter connection parts are missing
3)During positioning, pick up & testing of the
transporters underneath the cargo
a)Not sufficient space under module to position
transporters
b)Module supports are not positioned in a straight
line
c)Not enough supports or support beams
available on top of the transporters
JOB SAFETY ANALYSISLoadout works
Updated: 11/7/2013Page 2 of 7
7/21/2019 R0 Procedure Cendor Bridge
61/65
No When things can happen Potential risk / hazardHow to avoid / counter re-act / plan
contingency
Job Safety AnalysisLoadout operations
I)
Close off the partition involved to be able to
continue job. Complete proper repair after
testing
II) Test all hydraulic systems to maximum pressureprior to positioning transporters under the decks
III)Mobilise a number of hoses which are most
likely to give way
IV)Designate a hydraulic hose shop in the v icinity
for quick repairs
e) Major powerpack failure I)Have sufficient contingency built in to be able to
continue the job with one powerpack less
I) Be ready for last minute adjustments oftransporter configurations
II)
Be ready to mobilise additional transporters in
case problem can not be solved by change of
transporter configurations
III)
Client to double check and closely monitor their
weight control reports and center of gravity
calculations
IV)
Be ready prepared for last minute changes in
the hydraulic grouping of the transporters'
suspension cylinders
d) Hydraulic hose bursts
f)Center of gravity not in position as expected
resulting in overloading of certain transporters
3)
( continued) During positioning, pick up
& testing of the transporters underneath the
cargo
JOB SAFETY ANALYSISLoadout works
Updated: 11/7/2013Page 3 of 7
7/21/2019 R0 Procedure Cendor Bridge
62/65
No When things can happen Potential risk / hazardHow to avoid / counter re-act / plan
contingency
Job Safety AnalysisLoadout operations
I)Initially plan transporter loading to maximum
90% of maximum loading
II)
Be ready to mobilise additional transporters in
case problem can not be solved by change of
transporter configurations
III)
Client to double check and closely monitor their
weight control reports and center of gravity
calculations
I) Have spare computers/parts on standby on site
II)Have electronic expert on standby on site for
emergency cases
III) Continue testing at manual override mode andmake proper repair prior to transportation
I) Have at least 1 control box on standby
II) Have sufficient connection cables on standby
III)Have electronic expert on standby for
emergency cases
I)Continue testing with the flat tyre and change
tyre after testing
II)Check tyre pressures prior to placing
transporters underneath the decks
III)Check transporter path for sharp objects prior to
placing transporter underneath the decks
3)
( continued) During positioning, pick up
& testing of the transporters underneath the
cargo
i) Control box failure
j) Tyre failure
g) Module heavier than expected
h) Powerpack on-board computer failure
JOB SAFETY ANALYSISLoadout works
Updated: 11/7/2013Page 4 of 7
7/21/2019 R0 Procedure Cendor Bridge
63/65
No When things can happen Potential risk / hazardHow to avoid / counter re-act / plan
contingency
Job Safety AnalysisLoadout operations
I)Close off the partition involved to be able to
continue job if feasible , if not replace the hose
II) Test all hydraulic systems to maximum pressureprior to positioning transporters under the decks
III)Mobilise a number of hoses which are most
likely to give way
IV) Have a oil splil absorbent kit on standby
V)Designate a hydraulic hose shop in the v icinity
for quick repairs
b) Major powerpack failure I)Have sufficient contingency built in to be able to
continue the job with one powerpack less
I) Have spare computers/parts on standby on site
II)Have electronic expert on standby on site for
emergency cases
III) Continue at manual override mode if possible
I)Have at least 1 control box on standby for each
system (being Goldhofer and SPMT)
II) Have sufficient connection cables on standby
III)Have electronic expert on standby for
emergency cases
Hydraulic hose bursts
Powerpack on-board computer failure
Control box failure
4) Transporter related incidents
d)
c)
a)
JOB SAFETY ANALYSISLoadout works
Updated: 11/7/2013Page 5 of 7
7/21/2019 R0 Procedure Cendor Bridge
64/65
J b S f t A l i
7/21/2019 R0 Procedure Cendor Bridge
65/65
No When things can happen Potential risk / hazardHow to avoid / counter re-act / plan
contingency
Job Safety AnalysisLoadout operations
I) Client to have rescue boat on standby
II)
All personnel on the barge to wear life vests on
board the barge when working outside the
barrier
I)Have sufficient contingency built in to be able to
continue the job with a 50% of the pumps only
II) Repair the pump if easily achieavble
I)Client to have a gas free test done prior to doin
any welding done on the barge
II)Cover transporter with fire blankets where
sparks are expected to drop down on transporter
III) Have a fire extinguisher on standby at all time
Pump failureb)
5) During ballasting & barge crossover
a) Man overboard
c) Fire during welding or other hot works
JOB SAFETY ANALYSISLoadout works Updated: 11/7/2013Page 7 of 7