Upload
adhiartha-prihananto
View
16
Download
6
Tags:
Embed Size (px)
DESCRIPTION
jj
Citation preview
THE OPERATION MANUAL
CONTENTS
1. Main data
2. Structure and performance
3. Main assembly data
4. Heating and fastening bolts
5. Conditions and technical specifications
6. Start-up, operation and maintenance
of turbine
7. Mark, package, storage and transport
8. Criterion for turbine using oil
THE OPERATION MANUAL
1. Main data 1.1 Model N30-8.83/535
1.2 Type High pressure, single casing, impulse
and condensing turbine
1.3 Governing mode Nozzle governing
1.4 Rated power 30000kW
1.5 Speed 3000r/min
1.6 Working grid frequency 50HZ
1.7 Rated working conditions
Initial pressure 8.83 MPa
Initial temperature 535 ℃
Exhaust pressure 0.0087MPa
Cooling water temperature 30℃
Feeding water temperature 219.3℃
1.8 Input steam flow under rated condition 119t/h
1.9 Rotary direction Clockwise (viewing from turbine to
generator)
1.10 Critical speed of rotor ~1796r/min
1.11 Number of stage 19 stages
1.12 Total length of turbine ~8.6mm
1.13 Extraction number 6(after stage 5,8,10,13,15,17)
1.14 Heater quantity 2 HP heaters+1 deaerator +3 LP heaters
1.15 Max. lifting weight
When installing 56 t(condenser)
When overhaul 26 t (the upper casing with diaphragms)
THE OPERATION MANUAL
1.16 Outline size (length × width × height) 8.60×4.89×3.49(m)
2. Structure and performance 2.1 Type N30-8.83/535 turbine is a high pressure, signal casing,
impulse and condensing turbine. It drives generator through stiff
coupling.
2.2 After passing through main stop valve, the initial steam shall be
led to four regulating valves by four main steam pipes, and then
enter into steam turbine. The regulating valves are controlled by
oil-relay through rack and cam steam distribution device. The
open degree of valves shall be regulated according to operation
requirement so as to control steam intake and realize change of
power.
2.3 The casing consists of front casing, intermediate casing and rear
casing. The three casings are connected by vertical flanges.
The material of front casing is alloy-steel ZG15Cr2Mo1. The
front casing shall be supported on front bearing seat by upper
paws and splits be connected by studs of which the material is
25Cr2Mo1V. The material of intermediate casing is ZG230-450
and rear casing is HT250.
2.4 The full three-dimension design shall be adopted for fixed blades,
and radial spill strips shall be inserted in diaphragms to
minimize steam leaking. Front gland, rear gland and diaphragm
seal are comb-tooth type with spring strips installed on internal
circle. The design of sealing clearance is reasonable and it can
meet requirement of economy and safety and be convenient for
examining and repairing.
2.5 The rotor is a combination of integral rotor and shrunk wheels.
The material of integral rotor is 30Cr1Mo1V and that of the last
THE OPERATION MANUAL
four stages of shrunk wheels is 34CrNi3Mo. The wheel shall be
connected with rotor through end radial keys and axial keys to
minimize stress centralized on wheel hole.
2.6 The full three-dimension design shall be adopted for pressure
stage blade which has shroud band itself. The radial packing
and axial packing shall be designed at shroud band and
entrance edge separately to minimize steam leaking and
improve internal efficiency. To prevent blade from water erosion,
the last blade shall be treated with electric spark.
2.7 Make dynamic balance test of rotor before delivery so as to meet
requirement of safe operation.
2.8 The front bearing of turbine is a thrust and supporting bearing
which is set in bearing seat. The ellipse pads shall be the
supporting of the bearing. The pads have spherical surface and
can be self-located. There are ten working pads and locating
pads separately. The pads are fan-shaped and can sway. The
rear bearing is ellipse supporting bearing which is set in rear
bearing box. The temperature measuring components shall be
installed in thrust pads (Pt resistance type Pt100).
2.9 The dead center of heat expansion of steam turbine shall be set
at rear casing which is located on rear frame by transverse
slide pin. The vertical key and longitudinal key set at front
bearing seat and front casing shall keep the center of turbine
unchanged when casing expands forward. The rotor shall be
located by thrust bearing and expands backward, the relative
expansion of casing and rotor shall be measured by relative
expansion indicator.
2.10 The turning gear shall be installed on rear bearing box. It is
THE OPERATION MANUAL
low speed turning gear and can be started in manual. When
the speed of rotor is larger than the speed of turning gear, the
turning gear shall withdraw from working position. The speed of
turning gear is 5.6r/min.。
2.11 The main oil pump shall be installed in front bearing seat and
be driven by rotor through tooth-shaped coupling. When
steam turbine operates normally, besides supplying oil for
governing system, the main oil pump shall also supply oil for
oil ejector.
2.12 Oil supplying device consists of oil tank, high pressure startup
oil pump, AC and DC low pressure lube oil pump and oil
ejector.
2.13 The smoke exhaust system consists of smoke exhaust device,
valves and pipeline, and the smoke exhaust device consists of
air door, elbow and oil and smoke separator. The smoke
exhaust device shall be installed on oil tank. When operating,
the open degree of air door can be regulated to form vacuum
range from 9.8 to 19.6×10-6 MPa in oil tank.
2.14 The oil system adopts 32# or 46# turbine oil. To improve oil
quality, the user shall prepare oil purification device.
2.15 The sound insulation cover shall be adopted in turbine, its
structure is reasonable, and the profile is good looking.
2.16 Auxiliaries system refers to Auxiliaries Instruction.
2.17 Governing and safety system refers to Governing and Safety
Instruction.
3. Main assembly data (see table 1)
THE OPERATION MANUAL
4. Heating and tightening of bolts 4.1 To obtain lasting and reliable sealing performance, the method of
heating and tightening bolts shall be adopted so that the nuts of
high pressure part and main stop valve can be screwed tightly.
The nuts and bolts shall be numbered; and the nut and bolt
matching each other shall have the same number.
Bolts of front casing M120×4 20 pieces
Bolts of intermediate casing M68×4 14 pieces
Bolts of main stop valve M56×4 16 pieces 4.2 Explanation for electric heating type bolt heater
Electric heating type bolt heater shall be adopted to heat and
tighten bolts. When using, the heater shall be inserted into the
heating hole in center of bolt. The length of resistance tube shall
suit with the working length of bolt (tension part) and only the
polish section of bolt shall be heated and extended. Then the
temperature of thread part of two ends of bolt shall be lower so
as to avoid threads occlusion tightly. The electric source,
connection and operation of heater shall be supplied by
manufacture of heater, and it is required to record the current,
voltage, actual value and change law of the heater, and then
summarize experience for comparison and reference in later
usage.
4.3 Heating and tightening of bolt
The requirement of heating and tightening bolt is to make the bolt
obtain a preloaded tension which can ensure sealing
performance of interface between casing and main stop valve
after unit operates for a period and loosening of bolts occurs.
The data about heating and tightening of bolt shall refer to table
THE OPERATION MANUAL
2 and table 3; make operation according to the following
procedure:
4.3.1 The nut shall be screwed down to the bottom by hand smoothly,
and then check if the end face of nut contacts the flange well by
feeler. The 0.04mm feeler shall not insert the interface along the
whole circle. After overhaul and the nuts and bolts are changed
newly, the nuts shall be screwed down to the bottom. Then check
the top clearance of the nut, and the clearance value shall be
more than 3mm.
4.3.2 The thread section of the nuts and bolts passed test shall be
polished by high quality ceruse(black lead) repeatedly till the
tooth root surface of threads are black and glossy, then blow
the redundant lead away by compressed air to keep the surface
clean.
4.3.3 Screw the nuts according to the serial number of bolts heated
at the same time, then the nuts checked and put on black lead
shall be tightened according to the moment value of table 2.
Draw start line on nuts and flange, the rotating arc length of
each nut shall refer to table 3.
Table 2 Data of cold tightening of nut
Thread
diameter
People
screwing
wrench
Wrench
length m
Moment of cold
tightening (N·m)
M120 M68 2 1 1100~980
M56 2 1 600~500
THE OPERATION MANUAL
Table3 Data of heating and tightening bolt
Bolt
diameter
Extended
value mm
Heating
temp.℃
Rotating
angle of
nut φ
Rotating
arc length
of nut mm
Outer
diameter
of nut mm
M120 1.37 268 73.9 110 170
M68 0.56 184 44.5 38.8 100
M56 0.24 120 17.9 15 85
Explanation:The rotating angle and arc length of nut shown in table
are value of calculation in theory. Considering casing distortion after
operation and thickness reduced of internal sealing paint of flange
when heating and tightening, the tightening force of bolt shall be
increased when heating and tightening actually. The extra rotating
arc length corresponding to the tightening force shall be decided by
power plant according to actual condition, it shall not exceed 20% of
the theory calculation value in the table.
4.3.4 Install bolt heaters of which the number is predetermined. Heat
bolt according to operation procedure of heater and check end
clearance of nut by feeler after heating for predetermined time. After
the bolt extends to rated value, one people shall screw the nut tightly
to the preloaded arc length value with one meter long wrench
without sleeve, at that time the start line on nut shall coincide with
the finish line on flange. Data of heating and tightening of bolt refer
to table 3. If the nut could not be screwed tightly to rated arc length,
it shows that the extension length of bolt is not enough. Then go on
heating the bolt and screw the nut. The wrench shall not be screwed
forcedly with sleeve to avoid extra distortion stress acting on bolt.
THE OPERATION MANUAL
4.4 Bolt disassembly
The bolt and nut heated and tightened shall be disassembled by
heating according to the following procedure:
4.4.1 Clean around the nut, screw away the plug on the nut, then
clean and blow the heating hole.
4.4.2 Install heaters of which the number is predetermined, heat bolt
according to data of table 3 and operation procedure of heater.
When the bolt extends to the predetermined value, only one people
can screw the bolt out easily. The predetermined extension value
shall include extra heating value (see explanation of table 3). When
disassembling nut, the bolt shall be heated when the temperature of
casing flange drops to about 100℃. 4.4.3 Heating bolt shall be stopped immediately under the following
condition:
4.4.3 When the time heating bolt is more than normal time, inspect
the nut by feeler and the end face of nut shall not contact the flange,
but the nut could not be screwed.
4.4.3.2 The nut is loosened and screwed for more than one circle,
then stop heating whether the nut can be screwed smoothly or not. 4.4.4 If the nut could not be screwed out smoothly (item 4.4.3 of the
above), it is forbidden to screw the nut forcedly with long sleeve to
avoid damage of threads. Here the nut and bolt shall be cooled for
1-3 hours, then use two or three 6# or 7# flame welding torch to heat
around the lower surface of nut uniformly. When the temperature is
about 400 , try to screw the nut.℃ If the nut still could not be screwed,
go on heating to achieve the following temperature according to
material of nut:
THE OPERATION MANUAL
Nut Material Temperature
M120 25Cr2MoVA 670℃
M68 45-5 500℃
M56 45-5 500℃
At that time the metal is wine in color. If the nut still could not be
screwed, it shows that the threads are held by each other seriously.
Then the nut shall be disassembled with long sleeve or by
hammering forcedly, or at last by damage method.
4.4.5 After the nut is disassembled, it is necessary to check if the
number of nut is the same with the bolt. If there is a washer under
the nut, the washer shall be marked the same number with the bolt.
5. Assurance condition and technical specification 5.1 Assurance condition
5.1.1 Initial steam condition:Pressure 8.83 MPa; 3.02.0
+−
Temperature 535 。 510
+−
5.1.2 Temperature of cooling water 30℃。
5.1.3 The main body and auxiliaries of turbine shall be in good state,
the accumulated operating time of turbine shall not be more than
6500 hours since the first startup.
5.1.4 The steel tubes of condenser are clean, and sealing
performance of condenser is good. When air ejector is stopped
under rated condition, the drop speed of vacuum in condenser shall
not be more than 266 Pa/min.
5.2 When the condition deviates as the following, the turbine shall
be allowed to operate under rated power for a long period:
5.2.1 The initial steam pressure and temperature changes at the
THE OPERATION MANUAL
same time, the pressure shall change within 9.13MPa~8.63 MPa
and the temperature change within 525℃~540 , the temperature ℃
of cooling water shall not be more than 33 .℃
5.2.2 The temperature of cooling water is 36 , the initial steam ℃
pressure and temperature shall not be lower than that of rated
condition.
5.2.3 It is permitted that the limited condition of turbine is 9.8MPa
and 545 for a short period, and the two limited ℃ condition shall not
appear at the same time. The operating time under any limited
condition shall not be more than 0.5 hour. If the operating time
exceeds the limited time, the turbine shall be shutdown forcedly at
once. The operating time of turbine under limited condition shall not
be more than 20 hours in whole year.
5.3 When the initial steam condition and the back pressure are kept
within the range of long-term operation, the over-speed test shall be
done for governing and safety system. When speed is 111%~112%
of rated speed, namely achieves 3330~3360r/min, the emergency
governor shall act. The over speed test shall be done for three times.
The difference of action speed between the first two tests shall be
smaller than 0.6%, the difference of action speed between the third
test and the average of the first two tests shall be not more than 1%,
the two fly-balls can be tested separately.
6. Startup, operation and maintenance of turbine To assure safe and economical operation, we supply the following
contents which shall be followed and noticed according to
characteristic of turbine
6.1 Starting and loading
THE OPERATION MANUAL
6.1.1 Starting mode:
According to starting conditions of steam, the starting mode is
classified into two sorts, rated condition startup and slide condition
startup. And slide condition startup is classified into two sorts,
pressure-type slide condition startup and vacuum-type slide
condition startup. Rated condition startup shall be adopted when
two turbines operate in parallel and steam is supplied by main pipe
generally. The mode shall not suit cold startup because heat stress
during startup is large and start time is long. While hot start, it is
convenient for loading to the required. When slide condition starting,
turbine and boiler shall operate in unit system. Slide condition
startup is adopted widely for the merits of small temperature
difference of parts, economical performance and short start time
during starting.
When pressure-type slide condition startup is adopted, main stop
valve and regulating valve shall be opened fully (if started by
regulating valve, main stop valve shall be opened fully and
regulating valve be opened gradually to control steam flow input to
turbine), the turbine shall be vacuumed. When pressure of boiler
rises to 0.2~0.4MPa and steam is overheated to 30 ,℃ the turbine
shall be started by bypass.
When vacuum-type slide condition startup is adopted, main stop
valve and regulating valve shall be opened fully. Boiler and turbine
shall be vacuumed at the same time. After firing boiler, the turbine
shall be started naturally. The mode to be adopted shall be decided
according to actual experience of power plant.
Besides that, the mode of startup is also classified into cold start and
hot start according to temperature of turbine itself. Generally when
THE OPERATION MANUAL
temperature of casing under velocity-compounded stage is lower
than 200 , we call it cold state; ℃ when temperature of casing under
velocity-compounded stage is higher than 200 , we call it ℃ hot state.
When hot starting, the temperature of input steam shall be
determined according to casing temperature. The turbine shall be
loaded to corresponding value as soon as possible under allowed
controlling condition to prevent casing from overcooling.
6.1.2 Slide condition cold startup
Before startup, the units shall be inspected and tested. Then
determine if start condition is provided according to general
regulations. The points which shall be paid attention to are given as
the following and are not the complete startup procedure:
6.1.2.1 Preparation
a. Start high pressure AC electric oil pump and turn gear.
b. When pressure-type slide condition startup is adopted, main stop
valve and regulating valve shall be opened fully (if started by
regulating valve, main stop valve shall be opened fully and
regulating valve be opened gradually to control steam flow input to
turbine). Considering the steam input portion of casing shall be
heated uniformly, generally it is the best to start by bypass. When
vacuum-type slide condition startup is adopted, main stop valve
and regulating valve shall be opened fully.
c. The water drain valves connecting each pipe and main body to
flash tank shall be opened fully.
d. The hot well of condenser shall be watered to achieve:
about 1/2~3/4 of water level meter, then start condensate pump
for recycle operation.
e. High and low pressure heater, the valves at side of steam and
THE OPERATION MANUAL
water shall be opened fully.
f. Start hydraulic air pump, when vacuum pressure is -0.0399MPa,
inform firing of boiler.
g. Operate sealing heater and sealing pressure regulator
h. Start water cycling system
6.1.2.2 Raising speed and loading
a. When pressure-type slide condition startup is adopted and the
condition of initial steam before isolating valve is 0.196~0.392MPa
and superheat degree is 30~50℃, the turbine shall be impulse-
rotated.
b. Monitor data of relative expansion, temperature rise and
temperature difference to be in allowable range.
C. Inspect when speed is 400~500r/min, then the speed shall be
raised continuously. When speed is 1300 ~ 1400r/min and
warming-up time of turbine is about 30min, raise speed and pass
through critical speed rapidly.
d. When passing through critical speed, steps can be adopted as the
following:
a)The open degree of isolating valve(or regulating valve)can be
increased;
b) Exhaust vacuum can be increased;
c) The open degree of bypass valve connecting to condenser before
main valve can be reduced gradually;
e. When speed is 2100~2300r/min, go on warming up of turbine;
F. Raising speed to 2850r/min,pay attention to action of speed
regulator and oil-relay, stop auxiliary oil pump;
g. During process of raising speed, the oil pressure of governing
THE OPERATION MANUAL
system shall be regulated primarily. When rated speed is obtained,
all tests for governing and safety system shall be done, then the unit
shall parallel in grind and load.
h. When paralleling in grind and loading, the turbine shall be
supplied steam.
6.1.3 Rated condition cold startup
6.1.3.1 Preparation
a. Start AC high pressure oil pump, operate tuning gear device;
b. Main stop valve and regulating valve shall be opened fully.
Bypass valve or main stop valve can be used for starting.
c. The water drain valves connecting each pipe and main body to
flash tank shall be opened fully;
d. The condenser shall be filled with water, then start condensate
pump for recycle operation;
e. Start air ejector;
f. Operate sealing heater and sealing pressure regulator.
6.1.3.2 Raising speed and loading:
a. When pressure of condenser achieves 0.04 ~ 0.0533MPa,
impulse rotor can be started. Keep speed to be 400~500r/min and
inspect.
b. Monitor data of relative expansion, temperature rise and
temperature difference to be in allowable range;
c. Warming up turbine when speed is 1300~1400r/min and the
warming time shall not be too long, and then pass through critical
speed rapidly;
d. When speed is 2100~2300r/min,go no warming up turbine.
e. Raising speed to 2850r/min,pat attention to action of oil-relay,
stop auxiliary oil pump;
THE OPERATION MANUAL
f. During process of raising speed, the oil pressure of governing
system shall be regulated primarily. When rated speed is obtained,
all tests for governing and safety system shall be done, then the unit
shall parallel in grind and load.
6.1.4 Hot start
When the temperature of casing under velocity-compounded stage
is more than 200 ,℃ we call it hot state. Because the change range
of temperature is very large, here we could not give rules concretely
and mechanically. So we only give some general rules and the
operation unit shall take corresponding measures base on actual
conditions. The key point of hot start is to prevent high temperature
parts from overcool and control negative expansion difference of
unit.
6.1.4.1 Preparation a. The turning gear device shall be put into operation before
impulse-rotating to prevent the rotor from bending. Measure bending
degree of the rotor and when the measurement data is 0.03mm
more than the initial data, impulse rotor is forbidden. The
temperature difference between the upper and lower half of casing
shall be less than 50℃.
b. Strengthen drainage and increase temperature of main steam.
When the temperature is increased to be 50℃ higher than that of
velocity-compounded stage, impulse rotor is allowed.
c. Input high temperature steam to front gland so as to increase heat
expansion of the rotor.
d. Others refer to explanation for cold start
6.1.4.2 Impulse rotor, raising speed and loading
a. When the pressure of condenser achieves 0.03~0.05MPa,
THE OPERATION MANUAL
impulse rotor can be started. Pay attention to the sound of friction
from the inside.
b. Try to raise speed to the rated value quickly, and parallel in grind
after doing required tests for governing and safety system. It is
required to increase the vacuum to reduce the negative expansion
difference.
c. The loading speed shall be decided by corresponding load
according to the casing temperature. Try to make the casing be
cooled to the least. When obtaining the pre-determined load, the
turbine shall be warmed up for about 20 minutes. Then load the
turbine according to the explanation for cold start.
6.2 Maintenance during operation
6.2.1 Criterion for steam condition
6.2.1.1 Change range of steam before main stop valve
Steam pressure 8.83 MPa 3.02.0
+−
Steam temperature 535 ℃ 510
+−
6.2.1.2 When the pressure of initial steam is high to 9.8MPa or the
temperature is high to 545 , the operating time shall be not more ℃
than 0.5h every time, the accumulative total time in whole year shall
be less than 20h.
6.2.1.3 When the pressure and temperature of steam exceed the
above value and can not be lowered, it shall be treated as
emergency stop.
6.2.2 Load limiting criterion
When the load is decreased because the initial parameters drop or
exhaust vacuum drops or other reasons, the pressure of monitoring
section shall be controlled not to exceed 10% of allowance.
THE OPERATION MANUAL
6.2.3 Main monitoring data during operation
Grind cycle 48.5~50.5 HZ
Oil pressure of governing system 1.96MPa
Lubricating oil pressure 0.078~0.118MPa
Oil pressure of main oil pump inlet 0.0981MPa
Oil temperature of bearing inlet(℃) 35~45
Oil return temperature of bearing(℃) less than 65
Pressure drop of oil filter 0.0196~0.0392MPa
Pressure after seal pressure regulator 0.1009~0.1274MPa
Pressure after seal air ejector 0.0931~0.097MPa
Exhaust temperature of rear casing(℃)
With load less than 65
Without load less than 120
Axial displacement not more than 1.2mm
Relative expansion within the range from +3 to -1
Bearing vibration not more than 0.03mm
Exhaust vacuum higher than -0.087MPa
Under the condition similar to the first start after installation or
overhaul, if the pressure measured after velocity-compounded
stage is 10% higher than the normal, cleaning shall be done. Or
decrease load according to the limited pressure value of
monitoring section, then clean the turbine while slide condition
shutdown.
6.2.4 Main tests during operation:
6.2.4.1 Oil ejecting test of emergency governor, testing once every
2-4 weeks the best;
6.2.4.2 Action test of main stop valve:Once a day
THE OPERATION MANUAL
6.2.4.3 Electric auxiliary oil pump:Once a week
6.2.4.4 Action test of extraction valve:Once a week
6.3 Shutdown
6.3.1 Rated condition shutdown
6.3.1.1 The hot load and electric load shall be decreased uniformly.
The targets such as temperature drop and temperature difference
shall be monitored and controlled strictly. Pay attention to the
relative expansion value not to exceed -1mm.
6.3.1.2 Strengthen controlling for seal system
6.3.1.3 After parallel off and shutoff of main stop valve,
measure idling curve.
6.3.1.4 During shutdown, the heaters and circulating water pump
shall be cutoff. Then start auxiliary oil pump to do tests.
6.3.1.5 Put the tuning gear device into operation. After turning gear
continuously, then turn 180° per 15 minutes; after 2 hours turn 180°
per 30 minutes. If the temperature difference between the upper and
lower casing is 50℃, then turn 180° per 4 hours till cooling down
completely. To reduce operation, it can be changed to turn gear
continuously till cooling down completely. The suggestion that turn
gear continuously shall be adopted if needing start again in short
time after shutdown.
6.3.2 Slide condition shutdown:
To cool down the turbine quickly for overhaul early, slide condition
shutdown shall be adopted when operating under unit system mode.
The key points are proposed as the following:
6.3.2.1 Decrease the load properly to about 20000kW, then cutoff
hot load gradually.
6.3.2.2 The temperature and pressure of boiler shall be decreased,
THE OPERATION MANUAL
and then the load shall drop correspondingly. The regulating valve
shall be made in state of full-open, the decreasing speed of
temperature and the temperature difference shall be controlled
within the allowed range.
6.3.2.3 Keep the temperature before the main stop valve to be 30 ℃
lower than that of the casing.
6.3.2.4 When the temperature of steam drops below 250 , the ℃
boiler can be put out of the fire. Make use of the waste heat of
boiler to decrease the load to zero and the generator shall parallel
off. To prevent the temperature of steam from dropping rapidly due
to decreasing temperature in boiler at the moment of flameout,
covering fire shall be adopted after putting out of the fire. Make use
of flue baffle to keep the decreasing speed of steam temperature.
When the speed is near 2000r/min, the open degree of regulating
valve shall be decreased to make the speed drop to 1000r/min ( the
shutdown method that stop the turbine in manual and put out of the
fire of the boiler at the same time and then parallel off for the
generator can also be adopted.)
6.4 Maintenance while shutdown
It is important to maintain the turbine while shutdown, which shall
affect the life-span of the turbine. Some key points are proposed as
the following:
6.4.1 Shutdown within 10 days;
6.4.1.1 Close tightly the steam pipeline and drainage system;
6.4.1.2 Input hot air or use air extractor regularly to make the inside
of turbine be dry.
6.4.1.3 The outer machined surface shall be coated with rust-proof
oil.
THE OPERATION MANUAL
6.4.1.4 Rotate 1/3 cycle of the rotor every day, first start electric
lubricating oil pump when rotating.
6.4.2 Shutdown within three months (except the above mentioned,
some key points shall be added as the following): 6.4.2.1 Block up the end seal
6.4.2.2 Disassemble the parts of governing and safety system, coat
them with rust-proof oil.
6.4.2.3 When the speed is low (about 100r/min), coat the flow
section of turbine with Vaseline flowing with the steam.
6.4.3 Shutdown over three months:
It is required to remove the cover of casing and coat the surface of
flow section with protective oil.
6.5 Criterion for control of temperature raising and temperature
difference
During the process of starting, loading, decreasing load and
shutdown, the temperature difference of metal shall be controlled
strictly. The heat stress shall be out of the allowed range and results
in cracks due to the overlarge difference in temperature. It shall also
result in serious distortion under which the unit operates unsafely.
The difference in temperature is relative to the rate of temperature
rise.
THE OPERATION MANUAL
Item Control criterion
Rate of temperature rise of steam before
main stop valve ( /min)℃ 2.8~3.2
Rate of temperature drop of steam before
main stop valve ( /min)℃ 2
Rate of temperature rise of outer wall of
main stop valve ( /min)℃ 4.6~5
Rate of temperature rise of outer wall of
main steam pipe ( /min)℃ 7
Rate of temperature rise of steam
chamber outer wall of regulating valve
( /min)℃
4.6~5
Rate of temperature rise of inner wall of
casing flange ( /min)℃ 4
Rate of temperature rise of outer wall of
casing flange ( /min)℃ 3
Temperature difference between the inner
and outer wall of casing flange ( )℃ Temperature rise<120
Temperature drop<80
Temperature difference between the
center of casing flange and bolts ( )℃ ≤35~50
Temperature difference between the
upper and lower casing ( )℃ ≤35~50
Temperature difference between the inner
and outer wall of casing ( )℃ Temperature rise<80
Temperature drop<40
THE OPERATION MANUAL
6.6 Dealing with accident
6.6.1 The vacuum shall be damaged to shut down the steam turbine
emergently under the following conditions:
6.6.1.1 Strong vibration or bumping voice of metal in turbine occurs;
6.6.1.2 The speed rises to 3360r/min but the emergency governor
does not act;
6.6.1.3 Serious impact of water occurs and could not be eliminated
at once;
6.6.1.4 Seal at shaft end fires;
6.6.1.5 The oil of bearing breaks off or the temperature of return oil
is more than 75 or the bearing smokes;℃ 6.6.1.6 The oil system is on fire and there is no time to put out of the
fire;
6.6.1.7 The oil level in oil tank drops below the allowed value
suddenly;
6.6.1.8 The pressure of lubricating oil drops below 0.078MPa;
6.6.1.9 High pressure main steam pipe or other pipes break;
6.6.1.10The axial displacement of rotor is more than 1.2mm;
6.6.1.11 The generator smokes.
6.6.2 The steam turbine shall be shut down not damaging the
vacuum under the following conditions:
6.6.2.1 The temperature of main steam is higher than 545 or the ℃
steam pressure is higher than 9.8MPa and it could not be lowered at
once;
6.6.2.2 When the condenser operates normally, the pressure is
lower than 0.0387MPa and could not be recovered;
6.6.2.3 The valve rod of main stop valve is locked and could not
move;
THE OPERATION MANUAL
6.6.2.4 The generator drives the steam turbine to rotate for 3
minutes in electromotor operation mode;
6.6.2.5 The rear casing exhausts to air.
7. Mark, package, storage and transportation 7.1 The nameplates shall be installed on obvious position of steam
turbine and its auxiliaries, and the manufacturer, product type, main
technical specifications and production date shall be marked on the
nameplates.
7.2 The operating parts and directing parts all have obvious and
distinguishable direction marks.
7.3 Painting and packing of steam turbine and its auxiliaries refer to
relative specifications of the factory.
7.4 The general packing list shall be set in the file box purpose
made in the first case. All equipment cases have file box with its
own packing list in it for inspection and acceptance. The attached
drawings and quality certificate shall be submitted to the user
delegate directly.
7.5 The manufacturer shall be responsible for the quality of oil seal
of steam turbine parts packed during the period of six months
dating from the production date. During the period the cases shall
not be damaged or destroyed accidentally in process of
transportation or storage, for example the damage due to collision
or water soaking.
7.6 The cases shall not move freely and collide with each other
during transportation, it is forbidden that large cases weight on little
cases.
7.7 When packing in manual, it is forbidden to roll the case and
prize the case plate with crowbar, only slide wood can be prized. It
THE OPERATION MANUAL
is forbidden to push or pull the case down from high position to low
position.
THE OPERATION MANUAL
8. Criterion for turbine using oil 8.1 The oil adopted in governing and lubricating system
shall be in accordance with the quality target 32 or 46
in national standard GB/T11120-1989 L-TSA turbine oil,
the details see the following table:
Item Quality target No.
Viscosity grade 32 46
Testing
method
Movement viscosity ( 40℃ ),
mm2/s 28.8~35.2
41.4~50.6
GB265
2 Viscosity index, not less than 90 90 GB1995
3 Pour point, ℃ no higher than ~7 ~7 GB3535
4 Flash point(open), ℃ no lower than
180 180 GB3536
5 Density(20℃),kg/m3 Report Report GB1884GB1885
6 Acid value,mg KOH/g, not more than
− − GB264
7 Neutralization value,mg KOH/g not more than
Report Report GB4945
8 Machine impurity None None GB511
9 Moisture None None GB260
10 Destroy emulsification,(40−37−3)ml,54 ,℃ min not more than
15 15 GB7305
At 24 ℃ not more than
450% 450%
At 93 ℃ not more than
100% 100%
11
Bubbling test ml/ml
At 24 ℃ again not more than
450% 450%
SY2669
12 a. Total oxide % Report Report GB8119
THE OPERATION MANUAL
b. Deposit % Report Report
12
stability
c. When acid value
reaches
2.0mgKOH/g after
oxidation,h not less
than
3000 9000
SY2680
13 Liquid phase rust corrosion test
(synthesize sea water)
Without
rust
Without
rust GB11143
14 Copper plate testing(100℃,3h)
grade not larger than
1 1 GB5096
15 Releasing value of air(50℃)
min not more than
5 6 SY2693
THE OPERATION MANUAL
8.2 The oil adopted for high temperature friction part of turbine
regulating lever will be in accordance with the national standard
GB/T447-1994 oil used for steam cylinder, mineral oil, the
viscidity grade is 1000, and the details see the following table:
Item Quality
target
Category Mineral oilNo.
Viscidity grade 1000
Testing method
1 Movement viscidity
(100 ) mm℃ 2/s 30~40 GB/T265
2 Flash point(open), ,℃
not less than 260 GB/T267
GB/T3536
3 Pour point, ℃ not higher
than 20 GB/T3535
4 Remnant ash,
% not more than 2.5 GB/T268
5 Ash,% not more than 0.03 GB/T508
6 Machine impurity,
% not more than 0.03 GB/T511
7 Asphalt content,
% not more than 0.013 SH/T0266
8 Moisture,% not more than 0.05 GB/T260
9 Water-solubility acid or
alkali None GB/T259
THE OPERATION MANUAL
8.3 The oil used for instruments of rotating part shall be in
accordance with regulation SH/T0138-1994, the details see
the following table:
No. Item Target Testing method
1 Movement viscidity
(40 ) mm℃ 2/s 9~11 GB/T265-1988
2 Acid value,mg KOH/g
not more than 0.05 GB/T264-1983
3 Ash % not more than 0.005 GB/T508-1985
4 Water-solubility acid or
alkali None GB/T259-1988
5 Machine impurity,%
not more than None GB/T511-1988
6 Moisture %
not more than None GB/T260-1977
7 Flash point(open), ,℃
no lower than 125 GB/T267-1983
8 Solidifying point,℃
no higher than -60 GB/T510-1983