Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
This release contains forward-looking statements (as defined in Section 21E of the Securities Exchange Act of 1934,as amended) which reflect management’s current views with respect to certain future events and performance,including, among others, the timing of the commencement of charter contracts. The following factors are among thosethat could cause actual results to differ materially from the forward-looking statements, which involve risks anduncertainties, and that should be considered in evaluating any such statement: delays in the commencement of chartercontracts; unanticipated market volatility (such as volatility resulting from the recent COVID-19 outbreak); and otherfactors discussed in the Partnership’s filings from time to time with the SEC, including its Report on Form 20-F for thefiscal year ended December 31, 2019. The Partnership expressly disclaims any obligation or undertaking to releasepublicly any updates or revisions to any forward-looking statements contained herein to reflect any change in thePartnership’s expectations with respect thereto or any change in events, conditions or circumstances on which anysuch statement is based.
Forward Looking Statement
3%
48%
49%
FSO Shuttle Tanker FPSO
$4.4bn(1)Forward Revenue
(1) As of June 30, 2020. Based on existing contracts; but excluding extension options and oil-tariff revenue.
~2,000Employees
54Vessels
Blue-Chip Customers
Altera Infrastructure
Recent Highlights
Q2-20 Results
Adjusted EBITDA of $143 million in Q2-20, $11 million lower than previous quarter due to non-recurring items
E-Shuttle Newbuilds
Aurora Spirit and Rainbow Spirit commenced operations in the North Sea in April 2020 andMay 2020, respectively
Tide Spirit delivered in July 2020
Kraken CoA Contract
In June, EnQuest awarded us a 5-year CoA contract for the Kraken field. The vessel requirement is equivalent to half a shuttle tanker
Randgrid FSO Contract Extension
In June, Equinor exercised an option to extend the time-charter contract for one year until minimum October 2021
• We continue to focus on the safety of operations and have implemented a number of proactive
measures to protect the health and safety of vessel crews, as well as onshore employees
• No material business interruptions or financial impact in Q2 2020 from the COVID-19 pandemic
• Our towage business continue to suffer from general travel restrictions, resulting in low utilization
• A majority of our revenues are secured under medium-term contracts that should not be materially
affected by a short-term volatility in oil prices
• We continue to closely monitor counterparty risk associated with our vessels under contract and a
potential prolonged lower oil price environment to mitigate potential impact on the business
COVID-19 Response Update
Q2-20 ResultsAdjusted EBITDA of $143 million in Q2-20, $11 million lower than previous quarterdue to non-recurring items
FPSO SegmentAdjusted EBITDA decreased by $2 million to $74 million in Q2-20 mainly due to temporary lower uptime on the Petrojarl IFPSO
Shuttle Tanker SegmentAdjusted EBITDA increased by $4 million to $66 million in Q2-20 mainly reflecting contribution from the two newbuildings,higher earnings from the conventional market, partly offset bylower utilization following a disputed off-hire situation for ashuttle tanker
FSO SegmentAdjusted EBITDA decreased by $13 million to $11 million in Q2-20, primarily due to a $7 million one-time non-cashadjustment and a $4 million one-time provision, both related tothe Dampier Spirit FSO expected earlier end of contract
Towage SegmentAdjusted EBITDA decreased by $2 million to $(6) million in Q2-20 mainly due to lower fleet utilization
FPSO Segment
Voyageur Dispute Court RulingEconomic Uptime Adjusted EBITDA (US$ millions)
In July 2020, a dispute over amountsowed to us under the Voyageur FPSOcontract, has been concluded with a courtruling in our favor. This ruling entitles usto the full claim of $12 million andcontractual interest. The ruling may beappealed
In April 2020, we entered into a partly paidconcept study with Equinor for thepossible redeployment of the PetrojarlKnarr FPSO on the UK Rosebank field
In May 2020, we entered into a partly paid,competitive pre-FEED with Santos for anFPSO for the Australian Dorado field
Pre-FEED ActivityOperationsEconomic uptime decreased to 97% in Q2-20 from 99% in Q1-20 due to temporarylower uptime on Petrojarl I as certain oil wellswere temporarily shut in while a new watertreatment plant was being installed andcommissioned
Voyageur Decommissioning
The Voyageur Spirit FPSO completed itsfinal commercial offloading at theHuntington UK field at the end of June2020 and the FPSO is in the process ofbeing decommissioned
Shuttle Tanker SegmentE-Shuttle NewbuildsContracts Update
Technical Uptime Adjusted EBITDA (US$ millions)
In June, a 5-year CoA contract was signedwith EnQuest for the Kraken field,equivalent to half a vessel
In April, an 18-month extension was signedwith Transpetro, a subsidiary of Petrobras,to extend the Navion Stavanger bareboatcontract until October 2021
In April, a four-month time-charter contractwas signed with Suncor for Navion Anglia,which commenced in May 2020
The E-shuttles Aurora Spirit and RainbowSpirit successfully commenced operationin April and May 2020
Tide Spirit was delivered in July 2020 andis expected to commence operations inOctober 2020
The remaining three E-Shuttle newbuildsare expected to be delivered betweenAugust 2020 and January 2021
Capex
Total capex for the six E-Shuttles and thefourth East Coast Canada shuttle tanker isapproximately $920 million, excludingcapitalized interest, of which $728 million isfunded with secured financing
Remaining capex at June 30, 2020 isapproximately $459 million, of which $398million will be drawn on committed,secured financing
* Q4-18 figures excludes impact of Petrobras settlement
Operations
Technical uptime decreased to 91% in Q2-20 from 98% in Q1-20 reflecting deemedoff-hire by the customer for a shuttletanker
The off-hire is disputed and we are indiscussion with the customer
FSO SegmentDampier Spirit FSO
Technical Uptime Adjusted EBITDA (US$ millions)
Operations expected to cease in September2020, resulting in a $7 million non-recurringnon-cash adjustment related to the earlier endof contract expectation and a $4 million non-recurring provision
Trion FSO Pre-FEED for BHP
Awarded a paid, competitive pre-FEED todevelop a newbuild FSO for BHP for the Trionoil field in the Gulf of Mexico. The FEED will beawarded in 2021 and first oil is expected in2025
Randgrid FSO Option Exercised
In June, Equinor exercised the first of twelveoptions to extend the time-charter contractfor one year until minimum October 2021
Towage SegmentQ2-20 Operations
Fleet utilization decreased to 25% inQ2-20 compared to 34% in Q1-20 fromslower market activity reflecting theglobal impact of COVID-19
Utilization Adjusted EBITDA (US$ millions)
Market DevelopmentMarket activity has generally picked up inQ3 as travel restrictions has eased andprojects have been restarted
Financing Update
Knarr Refinancing
In June 2020 the Partnershipcompleted the extension of the $40million commercial bank tranche relatedto the financing of the Petrojarl KnarrFPSO with an extension to June 2023
The extension was a condition for the$390 million ECA tranche not to maturein June 2020. The related interest rateswap portfolio was extended to June2022
In relation to these extensions, certaindeposit arrangements and reductions innegative mark-to-market values of theinterest rate swaps were agreed withthe lenders
Brookfield RCF
The Partnership has agreed to amendthe existing credit agreement for anunsecured Revolving Credit Facilityprovided by Brookfield by increasing theavailable amount by $75 million to $200million and extending the maturity to 31October 2024. Closing of thetransaction is subject to customarydocumentation
End Q2 2020 Debt Maturity ScheduleIncluding both scheduled amortizations and balloon payments
• Revolving Credit Facilitiesand debt related to newbuildsshown as fully drawn
• FPSO JV debt is excluded, inline with the Balance Sheetrepresentation
• Including upsizing andextension of the BrookfieldRCF from $125 to 200 million
$156
$386
$661
$1 191
$673
$134
$0
$200
$400
$600
$800
$1 000
$1 200
$1 400
Remaining 2020 2021 2022 2023 2024 2025
MIL
LIO
NS
Brookfield RCF Scheduled Amortization Secured Debt Balloons Unsecured Debt
2020 Priorities• Maintain safety standards and operational excellence
• Maintain efficient operations in the new business environment
• Continue to identify opportunities to reduce non-essential expenditures
• Optimize the offshore and onshore organizations, tax and cost structure
• Limit capital expenditures to the committed shuttle tanker newbuilding program and mandatory vessel dry-dockings
• Secure FPSO charter extensions and redeployments
• Continue to optimize capital structure
End Q2 2020 Shuttle Charter Summary
Vessel 2020 2021 2022 2023 2024
Peary Spirit
Samba Spirit
Lambada Spirit
Bossa Nova Spirit
Sertanejo Spirit
Beothuk Spirit
Norse Spirit
Dorset Spirit
Altera Thule
Nansen Spirit
Petroatlantic
Petronordic
Aurora Spirit
Rainbow Spirit
Navion Oceania
Time-charter
CoA
Bareboat
Spot
Vessel 2020 2021 2022 2023 2024
Tide Spirit
Current Spirit
Wind Spirit
Wave Spirit
Amundsen Spirit
Scott Spirit
Stena Natalita (50% JV)
Heather Knutsen (in-charter)
Ingrid Knutsen (in-charter)
Navion Oslo
Navion Anglia
Navion Gothenburg (50% JV)
Nordic Rio (50% JV)
Nordic Brasilia
Navion Stavanger
Navion Bergen
Please also refer to Form 20-F for the fiscal year ended December 31, 2019.
OptionsFirm Available
Please also refer to Form 20-F for the fiscal year ended December 31, 2019.
End Q2 2020 FPSO Charter Summary
Unit Location 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Libra Brazil Petrobras
Itajai Brazil Petrobras
Knarr Norway Shell
Petrojarl 1 Brazil Enauta
Piranema Brazil Petrobras
Voyageur UK Premier Oil
Varg Norway
(1) As of June 30, 2020
OptionsFirm Available
Please also refer to Form 20-F for the fiscal year ended December 31, 2019.
End Q2 2020 FSO Charter Summary
Unit Location 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Randgrid Norway Equinor
SuksanSalamander Thailand Salamander Energy
Dampier Spirit Australia Jadestone Energy
Falcon Spirit Qatar Qatar Petroleum
Apollo Spirit UK Teekay Corporation